Title: Budget Period 2 Summary Report Part 1: Hywind Maine Project

Abstract

This project was performed under the Work for Others—Funds in Agreement FIA-14-1793 between Statoil and the Alliance for Sustainable Energy, manager and operator of the National Renewable Energy Laboratory (NREL). To support the development of a 6-MW spar-mounted offshore wind turbine, Statoil funded NREL to perform tasks in the following three categories: 1. Design and analysis 2. Wake modeling 3. Concept resource assessment. This summarizes the document reports on the design and analysis work package, which built a FAST [Jonkman & Buhl, 2005] computer model of the Hywind 6-MW floating wind turbine system and uses this tool to evaluate the performance of a set of design load cases (DLCs). The FAST model was also used in Work Package 2: Wake Modeling.

Authors:
; ;
Publication Date:
Research Org.:
Statoil Wind US LLC
Sponsoring Org.:
USDOE Office of Energy Efficiency and Renewable Energy (EERE)
OSTI Identifier:
1247164
Report Number(s):
DOE-SWUS-05988
DOE Contract Number:  
EE0005988
Resource Type:
Technical Report
Country of Publication:
United States
Language:
English
Subject:
99 GENERAL AND MISCELLANEOUS

Citation Formats

Driscoll, Frederick, Platt, Andrew, and Sirnivas, Senu. Budget Period 2 Summary Report Part 1: Hywind Maine Project. United States: N. p., 2015. Web. doi:10.2172/1247164.
Driscoll, Frederick, Platt, Andrew, & Sirnivas, Senu. Budget Period 2 Summary Report Part 1: Hywind Maine Project. United States. doi:10.2172/1247164.
Driscoll, Frederick, Platt, Andrew, and Sirnivas, Senu. Sat . "Budget Period 2 Summary Report Part 1: Hywind Maine Project". United States. doi:10.2172/1247164. https://www.osti.gov/servlets/purl/1247164.
@article{osti_1247164,
title = {Budget Period 2 Summary Report Part 1: Hywind Maine Project},
author = {Driscoll, Frederick and Platt, Andrew and Sirnivas, Senu},
abstractNote = {This project was performed under the Work for Others—Funds in Agreement FIA-14-1793 between Statoil and the Alliance for Sustainable Energy, manager and operator of the National Renewable Energy Laboratory (NREL). To support the development of a 6-MW spar-mounted offshore wind turbine, Statoil funded NREL to perform tasks in the following three categories: 1. Design and analysis 2. Wake modeling 3. Concept resource assessment. This summarizes the document reports on the design and analysis work package, which built a FAST [Jonkman & Buhl, 2005] computer model of the Hywind 6-MW floating wind turbine system and uses this tool to evaluate the performance of a set of design load cases (DLCs). The FAST model was also used in Work Package 2: Wake Modeling.},
doi = {10.2172/1247164},
journal = {},
number = ,
volume = ,
place = {United States},
year = {2015},
month = {8}
}