ANALYTICAL RESULTS OF MOX COLEMANITE CONCRETE SAMPLES POURED AUGUST 29, 2012
The Mixed Oxide Fuel Fabrication Facility (MFFF) will use colemanite bearing concrete neutron absorber panels credited with attenuating neutron flux in the criticality design analyses and shielding operators from radiation. The Savannah River National Laboratory is tasked with measuring the total density, partial hydrogen density, and partial boron density of the colemanite concrete. Samples poured 8/29/12 were received on 9/20/2012 and analyzed. The average total density of each of the samples measured by the ASTM method C 642 was within the lower bound of 1.88 g/cm{sup 3}. The average partial hydrogen density of samples 8.6.1, 8.7.1, and 8.5.3 as measured using method ASTM E 1311 met the lower bound of 6.04E-02 g/cm{sup 3}. The average measured partial boron density of each sample met the lower bound of 1.65E-01 g/cm{sup 3} measured by the ASTM C 1301 method. The average partial hydrogen density of samples 8.5.1, 8.6.3, and 8.7.3 did not meet the lower bound. The samples, as received, were not wrapped in a moist towel as previous samples and appeared to be somewhat drier. This may explain the lower hydrogen partial density with respect to previous samples.
- Research Organization:
- Savannah River Site (SRS), Aiken, SC (United States)
- Sponsoring Organization:
- USDOE
- DOE Contract Number:
- DE-AC09-08SR22470
- OSTI ID:
- 1053993
- Report Number(s):
- SRNL-STI-2012-00684
- Country of Publication:
- United States
- Language:
- English
Similar Records
ANALYTICAL RESULTS OF MOX COLEMANITE CONCRETE SAMPLE POURED JULY 25, 2012 - CURED 28 DAYS
Analytical Results Of MOX Colemanite Concrete Sample PBC-44.2