Title: D0 Silicon Upgrade: End Calorimeter Transfer Bridge Design and Installation Procedures

Abstract

The North Endcap Calorimeter (NEC) is to be moved from the clean room to the north sidewalk in preparation for the final installation on the DO detector center beam. In order to make this move, the cable bridge must be 'flattened' and the NEC lifted to move over it. The detector is moved west, approximately 24 feet, while the moveable counting house remains stationary. This movement allows the cable bridge to 'flatten' i.e. become horizontal. The cable bridge lowering is steadied and stabilized by 7.5 ton hoist mounted on the moveable counting house. By moving the detector to lower the bridge, a vacancy has been created in the pit that must be filled to the level of the clean room rail elevation. This filler will consist of concrete shield blocks, stacked in two rows. These rows are spaced appropriately to match the wheel base of the EC transporter. A steel plate is placed on top of each row of shield blocks and leveled to the elevation of the clean room rails. Steel plates will be installed and leveled on the north sidewalk similar to those used on the south sidewalk for the CC installation. These plates are used as railsmore » for the Hilman rollers, bearing surfaces for shim blocks used during lifting and anchors for holding the transporter extension units and the transfer bridge. After the plates are installed, the transfer bridge is put in place, spanning the cable bridge, shimmed and leveled. The transporter extension units are positioned next to the transfer bridge on the north sidewalk. With the completion of this prep work, the actual transfer of the NEC from the clean room can begin. The NEC is pulled from the clean room with the same mechanism (cyl. and chain) that was used for the CC and the pull anchor point will be located at the end of the concrete blocks. The NEC will come out of the north west door in the clean room and move along the temporary rail plates in the pit until it is in line with the transfer bridge. At this point the NEC is ready to be elevated to the level of the transfer bridge. The elevation process is the same as that used for the CC installation. When the correct elevation is attained the transporter extensions are positioned and fastened to the transporter on the south side. Static column supports will be added underneath the transporter to minimize deflections as the NEC is rolled off. The carriage extensions are now put in place and the Hilman rollers transferred into position under the extensions. The NEC is now ready to be pulled off of the transporter and onto the transfer bridge. Again using the Cyl. and chain mechanism, with the anchor point attached to the transporter extension on the north sidewalk, pull the NEC completely off of the transporter and onto the transfer bridge. Once the NEC is on the transfer bridge a rearrangement of equipment must be done. The transporter extension on the north sidewalk is decoupled from the transfer bridge and moved against the wall of the fixed counting area. The transporter extension at the south end of the transporter is removed, the transporter is decoupled from and moved to the north side of the transfer bridge. The transporter is supported from the floor at an elevation equal to the transfer bridge and coupled to it. The transporter extension is fastened to the north end of the transporter. The movement of the NEC now continues until it is back on the transporter. At this time the transfer bridge, concrete shield blocks and steel plates in the pit are removed. The detector is moved back to its normal parked position(cable bridge up). The NEC is lowered to the sidewalk (reverse of elevation procedure). Welding of the heads is then finished prior to final installation on the center beam. The final installation is identical to the CC installation, using all the same equipment. The finite element analysis of the transfer bridge design was done by Kay Weber of the Accelerator Mechanical Support Group.« less

Authors:
Publication Date:
Research Org.:
Fermi National Accelerator Lab. (FNAL), Batavia, IL (United States)
Sponsoring Org.:
USDOE Office of Science (SC)
OSTI Identifier:
1033280
Report Number(s):
FERMILAB-D0-EN-451
TRN: US1200357
DOE Contract Number:  
AC02-07CH11359
Resource Type:
Technical Report
Country of Publication:
United States
Language:
English
Subject:
43 PARTICLE ACCELERATORS; ACCELERATORS; CABLES; CALORIMETERS; CLEAN ROOMS; CONCRETE BLOCKS; CONCRETES; DESIGN; FERMILAB TEVATRON; FILLERS; PLATES; SHIELDS; SILICON; SPECIFICATIONS; STEELS; WELDING; Experiment-HEP

Citation Formats

Stredde, H. J., and /Fermilab. D0 Silicon Upgrade: End Calorimeter Transfer Bridge Design and Installation Procedures. United States: N. p., 1991. Web. doi:10.2172/1033280.
Stredde, H. J., & /Fermilab. D0 Silicon Upgrade: End Calorimeter Transfer Bridge Design and Installation Procedures. United States. https://doi.org/10.2172/1033280
Stredde, H. J., and /Fermilab. Mon . "D0 Silicon Upgrade: End Calorimeter Transfer Bridge Design and Installation Procedures". United States. https://doi.org/10.2172/1033280. https://www.osti.gov/servlets/purl/1033280.
@article{osti_1033280,
title = {D0 Silicon Upgrade: End Calorimeter Transfer Bridge Design and Installation Procedures},
author = {Stredde, H. J. and /Fermilab},
abstractNote = {The North Endcap Calorimeter (NEC) is to be moved from the clean room to the north sidewalk in preparation for the final installation on the DO detector center beam. In order to make this move, the cable bridge must be 'flattened' and the NEC lifted to move over it. The detector is moved west, approximately 24 feet, while the moveable counting house remains stationary. This movement allows the cable bridge to 'flatten' i.e. become horizontal. The cable bridge lowering is steadied and stabilized by 7.5 ton hoist mounted on the moveable counting house. By moving the detector to lower the bridge, a vacancy has been created in the pit that must be filled to the level of the clean room rail elevation. This filler will consist of concrete shield blocks, stacked in two rows. These rows are spaced appropriately to match the wheel base of the EC transporter. A steel plate is placed on top of each row of shield blocks and leveled to the elevation of the clean room rails. Steel plates will be installed and leveled on the north sidewalk similar to those used on the south sidewalk for the CC installation. These plates are used as rails for the Hilman rollers, bearing surfaces for shim blocks used during lifting and anchors for holding the transporter extension units and the transfer bridge. After the plates are installed, the transfer bridge is put in place, spanning the cable bridge, shimmed and leveled. The transporter extension units are positioned next to the transfer bridge on the north sidewalk. With the completion of this prep work, the actual transfer of the NEC from the clean room can begin. The NEC is pulled from the clean room with the same mechanism (cyl. and chain) that was used for the CC and the pull anchor point will be located at the end of the concrete blocks. The NEC will come out of the north west door in the clean room and move along the temporary rail plates in the pit until it is in line with the transfer bridge. At this point the NEC is ready to be elevated to the level of the transfer bridge. The elevation process is the same as that used for the CC installation. When the correct elevation is attained the transporter extensions are positioned and fastened to the transporter on the south side. Static column supports will be added underneath the transporter to minimize deflections as the NEC is rolled off. The carriage extensions are now put in place and the Hilman rollers transferred into position under the extensions. The NEC is now ready to be pulled off of the transporter and onto the transfer bridge. Again using the Cyl. and chain mechanism, with the anchor point attached to the transporter extension on the north sidewalk, pull the NEC completely off of the transporter and onto the transfer bridge. Once the NEC is on the transfer bridge a rearrangement of equipment must be done. The transporter extension on the north sidewalk is decoupled from the transfer bridge and moved against the wall of the fixed counting area. The transporter extension at the south end of the transporter is removed, the transporter is decoupled from and moved to the north side of the transfer bridge. The transporter is supported from the floor at an elevation equal to the transfer bridge and coupled to it. The transporter extension is fastened to the north end of the transporter. The movement of the NEC now continues until it is back on the transporter. At this time the transfer bridge, concrete shield blocks and steel plates in the pit are removed. The detector is moved back to its normal parked position(cable bridge up). The NEC is lowered to the sidewalk (reverse of elevation procedure). Welding of the heads is then finished prior to final installation on the center beam. The final installation is identical to the CC installation, using all the same equipment. The finite element analysis of the transfer bridge design was done by Kay Weber of the Accelerator Mechanical Support Group.},
doi = {10.2172/1033280},
url = {https://www.osti.gov/biblio/1033280}, journal = {},
number = ,
volume = ,
place = {United States},
year = {1991},
month = {2}
}