Title: Project Management Plan for the Hanford Environmental Dose Reconstruction Project

Abstract

This Project Management Plan (PMP) describes the approach being used to manage the Hanford Environmental Dose Reconstruction (HEDR) Project. The plan describes the management structure and the technical and administrative control systems used to plan and control HEDR Project performance. The plan also describes the relationship among key project participants: Battelle, the Centers for Disease control (CDC), and the Technical Steering Panel (TSP). Battelle`s contract with CDC only extends through May 1994 when the key technical work will be completed. There-fore, this plan is focused only on the period during which Battelle is a participant.

Authors:
; ;
Publication Date:
Research Org.:
Battelle Pacific Northwest Lab., Richland, WA (United States)
Sponsoring Org.:
Department of Health and Human Services, Washington, DC (United States)
OSTI Identifier:
10185701
Report Number(s):
PNWD-2021-HEDR
ON: DE93001494
DOE Contract Number:
AC06-76RL01830
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: Sep 1992
Country of Publication:
United States
Language:
English
Subject:
61 RADIATION PROTECTION AND DOSIMETRY; 99 GENERAL AND MISCELLANEOUS//MATHEMATICS, COMPUTING, AND INFORMATION SCIENCE; HUMAN POPULATIONS; RADIATION DOSES; HANFORD RESERVATION; RADIOACTIVE EFFLUENTS; PROGRAM MANAGEMENT; HISTORICAL ASPECTS; ADMINISTRATIVE PROCEDURES; RADIONUCLIDE MIGRATION; 560101; 990100; DOSIMETRY AND MONITORING; MANAGEMENT

Citation Formats

Shipler, D.B., McMakin, A.H., and Finch, S.M. Project Management Plan for the Hanford Environmental Dose Reconstruction Project. United States: N. p., 1992. Web. doi:10.2172/10185701.
Shipler, D.B., McMakin, A.H., & Finch, S.M. Project Management Plan for the Hanford Environmental Dose Reconstruction Project. United States. doi:10.2172/10185701.
Shipler, D.B., McMakin, A.H., and Finch, S.M. 1992. "Project Management Plan for the Hanford Environmental Dose Reconstruction Project". United States. doi:10.2172/10185701. https://www.osti.gov/servlets/purl/10185701.
@article{osti_10185701,
title = {Project Management Plan for the Hanford Environmental Dose Reconstruction Project},
author = {Shipler, D.B. and McMakin, A.H. and Finch, S.M.},
abstractNote = {This Project Management Plan (PMP) describes the approach being used to manage the Hanford Environmental Dose Reconstruction (HEDR) Project. The plan describes the management structure and the technical and administrative control systems used to plan and control HEDR Project performance. The plan also describes the relationship among key project participants: Battelle, the Centers for Disease control (CDC), and the Technical Steering Panel (TSP). Battelle`s contract with CDC only extends through May 1994 when the key technical work will be completed. There-fore, this plan is focused only on the period during which Battelle is a participant.},
doi = {10.2172/10185701},
journal = {},
number = ,
volume = ,
place = {United States},
year = 1992,
month = 9
}

Technical Report:

Save / Share:
  • This Project Management Plan (PMP) describes the approach that will be used to manage the Hanford Environmental Dose Reconstruction (HEDR) Project. The plan describes the management structure and the technical and administrative control systems that will be used to plan and control the HEDR Project performance. The plan also describes the relationship among key project participants: Battelle, the Centers for Disease Control (CDC), and the Technical Steering Panel (TSP).
  • This Project Management Plan (PMP) describes the approach being used to manage the Hanford Environmental Dose Reconstruction (HEDR) Project. The plan describes the management structure and the technical and administrative control systems used to plan and control HEDR Project performance. The plan also describes the relationship among key project participants: Battelle, the Centers for Disease control (CDC), and the Technical Steering Panel (TSP). Battelle's contract with CDC only extends through May 1994 when the key technical work will be completed. There-fore, this plan is focused only on the period during which Battelle is a participant.
  • This Project Management Plan (PMP) describes the approach that will be used to manage the Hanford Environmental Dose Reconstruction (HEDR) Project. The plan describes the management structure and the technical and administrative control systems that will be used to plan and control the HEDR Project performance. The plan also describes the relationship among key project participants: Battelle, the Centers for Disease Control (CDC), and the Technical Steering Panel (TSP).
  • This letter report is a description of work performed for the Hanford Environmental Dose Reconstruction (HEDR) Project. The HEDR Project was established to estimate the radiation doses to individuals resulting from releases of radionuclides from the Hanford Site since 1944. This work is being done by staff at Battelle, Pacific Northwest Laboratories (Battelle) under a contract with the Centers for Disease Control (CDC) with technical direction provided by an independent Technical Steering Panel (TSP). The objective of this report is to-document the environmental accumulation and dose-assessment parameters that will be used to estimate the impacts of past Hanford Site airbornemore » releases. During 1993, dose estimates made by staff at Battelle will be used by the Fred Hutchinson Cancer Research Center as part of the Hanford Thyroid Disease Study (HTDS). This document contains information on parameters that are specific to the airborne release of the radionuclide iodine-131. Future versions of this document will include parameter information pertinent to other pathways and radionuclides.« less
  • Phase 1 of the Hanford Environmental Dose Reconstruction Project was designed to develop and demonstrate a method for estimating radiation doses people may have received from Hanford Site operations since 1944. The method researchers developed relied on a variety of measured and reconstructed data as input to a modular computer model that generates dose estimates and their uncertainties. As part of Phase 1, researchers used the reconstructed data and computer model to calculate preliminary dose estimates for populations in a limited geographical area and time period. Phase 2, now under way, is designed to evaluate the Phase 1 data andmore » model and improve them to calculate more accurate and precise dose estimates. Phase 2 will also be used to obtain preliminary estimates of two categories of doses: for Native American tribes and for individuals included in the pilot phase of the Hanford Thyroid Disease Study (HTDS). TSP Directive 90-1 required HEDR staff to develop Phase 2 task plans for TSP approval. Draft task plans for Phase 2 were submitted to the TSP at the October 11--12, 1990 public meeting, and, after discussions of each activity and associated budget needs, the TSP directed HEDR staff to proceed with a slate of specific project activities for FY 1991 of Phase 2. This project plan contains detailed information about those activities. Phase 2 is expected to last 15--18 months. In mid-FY 1991, project activities and budget will be reevaluated to determine whether technical needs or priorities have changed. Separate from, but related to, this project plan, will be an integrated plan for the remainder of the project. HEDR staff will work with the TSP to map out a strategy that clearly describes end products'' for the project and the work necessary to complete them. This level of planning will provide a framework within which project decisions in Phases 2, 3, and 4 can be made.« less