Review of consolidated Edison`s integrated resource bidding program
Abstract
Competitive bidding has emerged as the dominant method for procuring new resources by US utilities. In New York, the Public Service Commission (NYPSC) ordered the state`s seven investor-owned utilities to develop bidding programs to acquire supply and DSM resource options. Utilities were allowed significant discretion in program design in order to encourage experimentation. Competitive bidding programs pose formidable policy, design, and management challenges for utilities and their regulators. Yet, there have been few detailed case studies of bidding programs, particularly of those utilities that take on the additional challenge of having supply and DSM resources compete head-to-head for a designated block of capacity. To address that need, the New York State Energy Research and Development Authority (NYSERDA), the New York Department of Public Service, and the Department of Energy`s Integrated Resource Planning program asked Lawrence Berkeley Laboratory (LBL) to review the bidding programs of two utilities that tested the integrated ``all-sources`` approach. This study focuses primarily on Consolidated Edison Company of New York`s (Con Edison) bidding program; an earlier report discusses our review of Niagara Mohawk`s program (Goldman et al 1992). We reviewed relevant Commission decisions, utility filings and signed contracts, interviewed utility and regulatory staff, surveyed DSM bidders andmore »
- Authors:
- Publication Date:
- Research Org.:
- Lawrence Berkeley Lab., CA (United States)
- Sponsoring Org.:
- USDOE, Washington, DC (United States); New York State Energy Research and Development Authority, Albany, NY (United States)
- OSTI Identifier:
- 10181912
- Report Number(s):
- LBL-33599
ON: DE93040447; CNN: Contract 1515-EEED-BES-91
- DOE Contract Number:
- AC03-76SF00098
- Resource Type:
- Technical Report
- Resource Relation:
- Other Information: PBD: Jul 1993
- Country of Publication:
- United States
- Language:
- English
- Subject:
- 29 ENERGY PLANNING, POLICY AND ECONOMY; 99 GENERAL AND MISCELLANEOUS//MATHEMATICS, COMPUTING, AND INFORMATION SCIENCE; ELECTRIC UTILITIES; BIDS; CONTRACTS; NEW YORK; SUPPLY AND DEMAND; ENERGY MANAGEMENT; COST; COMPETITION; 296000; 990100; ELECTRIC POWER; MANAGEMENT
Citation Formats
Goldman, C.A., Busch, J.F., Kahn, E.P., Baldick, R., and Milne, A.. Review of consolidated Edison`s integrated resource bidding program. United States: N. p., 1993.
Web. doi:10.2172/10181912.
Goldman, C.A., Busch, J.F., Kahn, E.P., Baldick, R., & Milne, A.. Review of consolidated Edison`s integrated resource bidding program. United States. doi:10.2172/10181912.
Goldman, C.A., Busch, J.F., Kahn, E.P., Baldick, R., and Milne, A.. Thu .
"Review of consolidated Edison`s integrated resource bidding program". United States.
doi:10.2172/10181912. https://www.osti.gov/servlets/purl/10181912.
@article{osti_10181912,
title = {Review of consolidated Edison`s integrated resource bidding program},
author = {Goldman, C.A. and Busch, J.F. and Kahn, E.P. and Baldick, R. and Milne, A.},
abstractNote = {Competitive bidding has emerged as the dominant method for procuring new resources by US utilities. In New York, the Public Service Commission (NYPSC) ordered the state`s seven investor-owned utilities to develop bidding programs to acquire supply and DSM resource options. Utilities were allowed significant discretion in program design in order to encourage experimentation. Competitive bidding programs pose formidable policy, design, and management challenges for utilities and their regulators. Yet, there have been few detailed case studies of bidding programs, particularly of those utilities that take on the additional challenge of having supply and DSM resources compete head-to-head for a designated block of capacity. To address that need, the New York State Energy Research and Development Authority (NYSERDA), the New York Department of Public Service, and the Department of Energy`s Integrated Resource Planning program asked Lawrence Berkeley Laboratory (LBL) to review the bidding programs of two utilities that tested the integrated ``all-sources`` approach. This study focuses primarily on Consolidated Edison Company of New York`s (Con Edison) bidding program; an earlier report discusses our review of Niagara Mohawk`s program (Goldman et al 1992). We reviewed relevant Commission decisions, utility filings and signed contracts, interviewed utility and regulatory staff, surveyed DSM bidders and a selected sample of DSM non-bidders, and analyzed the bid evaluation system used in ranking bids based on detailed scoring information on individual bids provided by Con Edison.},
doi = {10.2172/10181912},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Thu Jul 01 00:00:00 EDT 1993},
month = {Thu Jul 01 00:00:00 EDT 1993}
}
-
In June 1988, the New York Public Service Commission (PSC) ordered the state's investor-owned utilities to develop competitive bidding programs that included both supply and demandside resource options. The New York State Energy Research Development Authority (NYSERDA), the New York Department of Public Service, and the Department of Energy's Integrated Resource Planning program asked Lawrence Berkeley Laboratory (LBL) to review the integrated bidding processes of two New York utilities, Niagara Mohawk and Consolidated Edison. This interim report focuses on Niagara Mohawk (NMPC). In terms of overall approach, our analysis is intended as a critical review of a large-scale experiment inmore »
-
Review of integrated resource bidding at Niagara Mohawk
In June 1988, the New York Public Service Commission (PSC) ordered the state`s investor-owned utilities to develop competitive bidding programs that included both supply and demandside resource options. The New York State Energy Research & Development Authority (NYSERDA), the New York Department of Public Service, and the Department of Energy`s Integrated Resource Planning program asked Lawrence Berkeley Laboratory (LBL) to review the integrated bidding processes of two New York utilities, Niagara Mohawk and Consolidated Edison. This interim report focuses on Niagara Mohawk (NMPC). In terms of overall approach, our analysis is intended as a critical review of a large-scale experimentmore » -
Review of Boston Edison`s feedwater heater condition assessment program
Boston Edison Co. has proactively conducted numerous heat exchanger condition assessments at Mystic and New Boston Stations. This paper focuses upon low and high pressure feedwater heater assessments, performed in accordance with EPRI GS-6724, Condition Assessment Guidelines for Fossil Fuel Power Plants. The elements of this EPRI guideline are reviewed. Thereafter, Boston Edison`s condition assessment approach, techniques employed, typical findings obtained and benefits derived are described on a multiple case history basis. -
Examination of the integrated effects of adopting various energy conservation and load leveling policies for the metropolitan area of New York City. Final report. [Consolidated Edison]
Utilities generally, and Consolidated Edison Company of New York in particular, exhibit load curves with definite daily and seasonal characteristics and peaks. Peak demands are costly to serve in two respects: capacity must be built to meet peaks and, since every effort is made to rely for base load on the most-efficient generation available to a system, relatively inefficient fuel-consumptive units are normally pressed into service as demand approaches its peak. Society can no longer afford the luxury of capacity expansions that are the results of demands inefficiently induced, or of the subsidized consumption of electricity at times when itsmore » -
Consolidated Edison`s experience with substation RCM
This paper describes Consolidated Edison`s experience with reliability centered maintenance in its service area centered on New York City. The paper summarizes the scope of the service area, and discusses experience with RCM on a demonstration system serving the City Hall network.