This report is the first revision to a series of reports on radionuclides inn the SRS environment. Tritium was chosen as the first radionuclide in the series because the calculations used to assess the dose to the offsite population from SRS releases indicate that the dose due to tritium, through of small consequence, is one of the most important the radionuclides. This was recognized early in the site operation, and extensive measurements of tritium in the atmosphere, surface water, and ground water exist due to the effort of the Environmental Monitoring Section. In addition, research into the transport and fate of tritium in the environment has been supported at the SRS by both the local Department of Energy (DOE) Office and DOE`s Office of Health and Environmental Research.

Authors:
; ;  [1]
  1. and others
Publication Date:
Research Org.:
Westinghouse Savannah River Co., Aiken, SC (United States)
Sponsoring Org.:
USDOE, Washington, DC (United States)
OSTI Identifier:
10147749
Report Number(s):
WSRC-TR-93-214
ON: DE94011168; TRN: 94:013531
DOE Contract Number:
AC09-89SR18035
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: Oct 1993
Country of Publication:
United States
Language:
English
Subject:
11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS; 54 ENVIRONMENTAL SCIENCES; TRITIUM; EMISSION; SAVANNAH RIVER PLANT; RADIATION MONITORING; EARTH ATMOSPHERE; RADIONUCLIDE MIGRATION; RADIATION DOSES; OCCUPATIONAL SAFETY; PUBLIC HEALTH; RADIOACTIVE EFFLUENTS; 053002; 540130; 540230; 054000; RADIOACTIVE MATERIALS MONITORING AND TRANSPORT; HEALTH AND SAFETY

Citation Formats

Carlton, W.H., Murphy, C.E. Jr., and Bauer, L.R.. Assessment of tritium in the Savannah River Site environment. United States: N. p., 1993. Web. doi:10.2172/10147749.
Carlton, W.H., Murphy, C.E. Jr., & Bauer, L.R.. Assessment of tritium in the Savannah River Site environment. United States. doi:10.2172/10147749.
Carlton, W.H., Murphy, C.E. Jr., and Bauer, L.R.. Fri . "Assessment of tritium in the Savannah River Site environment". United States. doi:10.2172/10147749. https://www.osti.gov/servlets/purl/10147749.
@article{osti_10147749,
title = {Assessment of tritium in the Savannah River Site environment},
author = {Carlton, W.H. and Murphy, C.E. Jr. and Bauer, L.R.},
abstractNote = {This report is the first revision to a series of reports on radionuclides inn the SRS environment. Tritium was chosen as the first radionuclide in the series because the calculations used to assess the dose to the offsite population from SRS releases indicate that the dose due to tritium, through of small consequence, is one of the most important the radionuclides. This was recognized early in the site operation, and extensive measurements of tritium in the atmosphere, surface water, and ground water exist due to the effort of the Environmental Monitoring Section. In addition, research into the transport and fate of tritium in the environment has been supported at the SRS by both the local Department of Energy (DOE) Office and DOE`s Office of Health and Environmental Research.},
doi = {10.2172/10147749},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Fri Oct 01 00:00:00 EDT 1993},
month = {Fri Oct 01 00:00:00 EDT 1993}
}

Technical Report:

Save / Share:
  • A Draft Technical Information Document (HNF-1855) is being prepared to evaluate proposed interim tritium and medical isotope production at the Fast Flux Test Facility (FFTF). This report examines the potential health and safety impacts associated with transportation of irradiated tritium targets from FFTF to the Savannah River Site for processing at the Tritium Extraction Facility. Potential risks to workers and members of the public during normal transportation and accident conditions are assessed.
  • Tritium is released to the environment from many of the operations at the Savannah River Site. The releases from each facility to the atmosphere and to the soil and streams, both from normal operations and inadvertent releases, over the period of operation from the early 1950s through 1988 are presented. The fate of the tritium released is evaluated through environmental monitoring, special studies, and modeling. It is concluded that approximately 91% of the tritium remaining after decay is now in the oceans. A dose and risk assessment to the population around the site is presented. It is concluded that aboutmore » 0.6 fatal cancers may be associated with the tritium released during all the years of operation to the population of about 625,000. This same population (based on the overall US cancer statistics) is expected to experience about 105,000 cancer fatalities from all types of cancer. Therefore, it is considered unlikely that a relationship between any of the cancer deaths occurring in this population and releases of tritium from the SRS will be found.« less
  • Tritium is released to the environment from many of the operations at the Savannah River Site. The releases from each facility to the atmosphere and to the soil and streams, both from normal operations and inadvertent releases, over the period of operation from the early 1950s through 1988 are presented. The fate of the tritium released is evaluated through environmental monitoring, special studies, and modeling. It is concluded that approximately 91% of the tritium remaining after decay is now in the oceans. A dose and risk assessment to the population around the site is presented. It is concluded that aboutmore » 0.6 fatal cancers may be associated with the tritium released during all the years of operation to the population of about 625,000. This same population (based on the overall US cancer statistics) is expected to experience about 105,000 cancer fatalities from all types of cancer. Therefore, it is considered unlikely that a relationship between any of the cancer deaths occurring in this population and releases of tritium from the SRS will be found.« less
  • This report presents the results of an oversight assessment (OA) conducted by the US Department of Energy's (DOE) Office of Environment, Safety and Health (EH) of operational readiness review (ORR) activities for the Replacement Tritium Facility (RTF) located at Savannah River Site (SRS). The EH OA of this facility took place concurrently with an ORR conducted by the DOE Office of Defense Programs (DP). The DP ORR was conducted from January 19 through February 5, 1993. The EH OA was performed in accordance with the protocol and procedures specified in EH Program for Oversight Assessment of Operational Readiness Evaluations formore » Startups and Restarts,'' dated September 15, 1992. The EH OA Team evaluated the DP ORR to determine whether it was thorough and demonstrated sufficient inquisitiveness to verify that the implementation of programs and procedures adequately ensures the protection of worker safety and health. The EH OA Team performed its evaluation of the DP ORR in the following technical areas: occupational safety, industrial hygiene, and respiratory protection; fire protection; and chemical safety. In the areas of fire protection and chemical safety, the EH OA Team conducted independent vertical-slice reviews to confirm DP ORR results. Within each technical area, the EH OA Team reviewed the DP ORR Plan, including the Criteria Review and Approach Documents (CRADs); the qualifications of individual DP ORR team members; the performance of planned DP ORR activities; and the results of the DP ORR.« less
  • This report presents the results of an oversight assessment (OA) conducted by the US Department of Energy`s (DOE) Office of Environment, Safety and Health (EH) of operational readiness review (ORR) activities for the Replacement Tritium Facility (RTF) located at Savannah River Site (SRS). The EH OA of this facility took place concurrently with an ORR conducted by the DOE Office of Defense Programs (DP). The DP ORR was conducted from January 19 through February 5, 1993. The EH OA was performed in accordance with the protocol and procedures specified in ``EH Program for Oversight Assessment of Operational Readiness Evaluations formore » Startups and Restarts,`` dated September 15, 1992. The EH OA Team evaluated the DP ORR to determine whether it was thorough and demonstrated sufficient inquisitiveness to verify that the implementation of programs and procedures adequately ensures the protection of worker safety and health. The EH OA Team performed its evaluation of the DP ORR in the following technical areas: occupational safety, industrial hygiene, and respiratory protection; fire protection; and chemical safety. In the areas of fire protection and chemical safety, the EH OA Team conducted independent vertical-slice reviews to confirm DP ORR results. Within each technical area, the EH OA Team reviewed the DP ORR Plan, including the Criteria Review and Approach Documents (CRADs); the qualifications of individual DP ORR team members; the performance of planned DP ORR activities; and the results of the DP ORR.« less