Title: Buried waste integrated demonstration human engineered control station. Final report

Abstract

This document describes the Human Engineered Control Station (HECS) project activities including the conceptual designs. The purpose of the HECS is to enhance the effectiveness and efficiency of remote retrieval by providing an integrated remote control station. The HECS integrates human capabilities, limitations, and expectations into the design to reduce the potential for human error, provides an easy system to learn and operate, provides an increased productivity, and reduces the ultimate investment in training. The overall HECS consists of the technology interface stations, supporting engineering aids, platform (trailer), communications network (broadband system), and collision avoidance system.

Publication Date:
Research Org.:
Idaho National Engineering Lab., Idaho Falls, ID (United States)
Sponsoring Org.:
USDOE, Washington, DC (United States)
OSTI Identifier:
10115975
Report Number(s):
EGG-WTD-11446
ON: DE95004997; TRN: 95:001461
DOE Contract Number:
AC07-76ID01570
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: Sep 1994
Country of Publication:
United States
Language:
English
Subject:
12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES; 11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS; 42 ENGINEERING; RADIOACTIVE WASTES; UNDERGROUND DISPOSAL; REMEDIAL ACTION; RADIOACTIVE WASTE PROCESSING; REMOTE CONTROL; REMOTE HANDLING EQUIPMENT; HUMAN FACTORS ENGINEERING; FEASIBILITY STUDIES; TRAINING; REMOTE HANDLING; 052001; 054000; 420203; WASTE PROCESSING; HEALTH AND SAFETY; HANDLING EQUIPMENT AND PROCEDURES

Citation Formats

Not Available. Buried waste integrated demonstration human engineered control station. Final report. United States: N. p., 1994. Web. doi:10.2172/10115975.
Not Available. Buried waste integrated demonstration human engineered control station. Final report. United States. doi:10.2172/10115975.
Not Available. Thu . "Buried waste integrated demonstration human engineered control station. Final report". United States. doi:10.2172/10115975. https://www.osti.gov/servlets/purl/10115975.
@article{osti_10115975,
title = {Buried waste integrated demonstration human engineered control station. Final report},
author = {Not Available},
abstractNote = {This document describes the Human Engineered Control Station (HECS) project activities including the conceptual designs. The purpose of the HECS is to enhance the effectiveness and efficiency of remote retrieval by providing an integrated remote control station. The HECS integrates human capabilities, limitations, and expectations into the design to reduce the potential for human error, provides an easy system to learn and operate, provides an increased productivity, and reduces the ultimate investment in training. The overall HECS consists of the technology interface stations, supporting engineering aids, platform (trailer), communications network (broadband system), and collision avoidance system.},
doi = {10.2172/10115975},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Thu Sep 01 00:00:00 EDT 1994},
month = {Thu Sep 01 00:00:00 EDT 1994}
}

Technical Report:

Save / Share:
  • The work described in this report was conducted by Pacific Northwest Laboratory to provide information to the Buried Waste Integrated Demonstration (BWID) program. The information in this report is intended to provide a complex-wide planning base for th.e BWID to ensure that BWID activities are appropriately focused to address the range of remediation problems existing across the US Department of Energy (DOE) complex. This report contains information characterizing the 2.1 million m{sup 3} of buried and stored wastes and their associated sites at six major DOE facilities. Approximately 85% of this waste is low-level waste, with about 12% TRU ormore » TRU mixed waste; the remaining 3% is low-level mixed waste. In addition, the report describes soil contamination sites across the complex. Some of the details that would be useful in further characterizing the buried wastes and contaminated soil sites across the DOE complex are either unavailable or difficult to locate. Several options for accessing this information and/or improving the information that is available are identified in the report. This document is a companion to Technology Needs for Remediation: Hanford and Other DOE Sites, PNL-8328 (Stapp 1993).« less
  • The first step towards identifying primary Buried Waste Integrated Demonstration locations is the selection of potential demonstration sites within the Subsurface Disposal Area. The sites selected are Pits 4, 5, 6, and 9, containing transuranic waste of Rocky Flats origin, the Acid Pit, and Pad A. The criteria and methodology for selection of these sites, as well as a description of the wastes present in each area, are included in this report. At a later date, technology-specific demonstration locations will be selected from these six potential sites. The selected locations will be used as necessary to demonstrate technologies whose potentialmore » abilities may be optimal on waste forms present at these identified locations.« less
  • The first step towards identifying primary Buried Waste Integrated Demonstration locations is the selection of potential demonstration sites within the Subsurface Disposal Area. The sites selected are Pits 4, 5, 6, and 9, containing transuranic waste of Rocky Flats origin, the Acid Pit, and Pad A. The criteria and methodology for selection of these sites, as well as a description of the wastes present in each area, are included in this report. At a later date, technology-specific demonstration locations will be selected from these six potential sites. The selected locations will be used as necessary to demonstrate technologies whose potentialmore » abilities may be optimal on waste forms present at these identified locations.« less
  • The Integrated Test Schedule incorporates the various schedules the Buried Waste Integrated Demonstration (BWID) supports into one document. This document contains the Federal Facilities Agreement and Consent Order schedules for the Idaho National Engineering Laboratory, Hanford Reservation, Oak Ridge Reservation, and Fernald Environmental Materials Center. Included in the Integrated Test Schedule is the Buried Waste Integrated Demonstration windows of opportunity'' schedule. The windows of opportunity'' schedule shows periods of time in which Buried Waste Integrated Demonstration Program-sponsored technology demonstrations could support key decisions in the Federal Facilities Agreement and Consent Order. Schedules for the Buried Waste Integrated Demonstration-sponsored technology taskmore » plans are categorized by technology area and divided by current fiscal year and out-year. Total estimated costs for Buried Waste Integrated Demonstration-sponsored Technology Task Plans for FY-92 through FY-97 are $74.756M.« less
  • The Integrated Test Schedule incorporates the various schedules the Buried Waste Integrated Demonstration (BWID) supports into one document. This document contains the Federal Facilities Agreement and Consent Order schedules for the Idaho National Engineering Laboratory, Hanford Reservation, Oak Ridge Reservation, and Fernald Environmental Materials Center. Included in the Integrated Test Schedule is the Buried Waste Integrated Demonstration ``windows of opportunity`` schedule. The ``windows of opportunity`` schedule shows periods of time in which Buried Waste Integrated Demonstration Program-sponsored technology demonstrations could support key decisions in the Federal Facilities Agreement and Consent Order. Schedules for the Buried Waste Integrated Demonstration-sponsored technology taskmore » plans are categorized by technology area and divided by current fiscal year and out-year. Total estimated costs for Buried Waste Integrated Demonstration-sponsored Technology Task Plans for FY-92 through FY-97 are $74.756M.« less