Title: Westinghouse Hanford Company Pollution Prevention Program Implementation Plan

Abstract

This plan documents Westinghouse Hanford Company`s (WHC) Pollution Prevention (P2) (formerly Waste Minimization) program. The program includes WHC; BCS Richland, Inc. (BCSR); and ICF Kaiser Hanford Company (ICF KH). The plan specifies P2 program activities and schedules for implementing the Hanford Site Waste Minimization and Pollution Prevention Awareness (WMin/P2) Program Plan requirements (DOE 1994a). It is intended to satisfy the U.S. Department of Energy (DOE) and other legal requirements that are discussed in both the Hanford Site WMin/P2 plan and paragraph C of this plan. As such, the Pollution Prevention Awareness Program required by DOE Order 5400.1 (DOE 1988) is included in the WHC P2 program. WHC, BCSR, and ICF KH are committed to implementing an effective P2 program as identified in the Hanford Site WMin/P2 Plan. This plan provides specific information on how the WHC P2 program will develop and implement the goals, activities, and budget needed to accomplish this. The emphasis has been to provide detailed planning of the WHC P2 program activities over the next 3 years. The plan will guide the development and implementation of the program. The plan also provides background information on past program activities. Because the plan contains greater detail than in themore » past, activity scope and implementation schedules may change as new priorities are identified and new approaches are developed and realized. Some activities will be accelerated, others may be delayed; however, all of the general program elements identified in this plan and contractor requirements identified in the Site WMin/P2 plan will be developed and implemented during the next 3 years. This plan applies to all WHC, BCSR, and ICF KH organizations and subcontractors. It will be distributed to those with defined responsibilities in this plan; and the policy, goals, objectives, and strategy of the program will be communicated to all WHC, BCSR, and ICF KH employees.« less

Authors:
Publication Date:
Research Org.:
Westinghouse Hanford Co., Richland, WA (United States)
Sponsoring Org.:
USDOE, Washington, DC (United States)
OSTI Identifier:
10103402
Report Number(s):
WHC-EP-0496-Rev.1
ON: DE95003268; TRN: 95:000327
DOE Contract Number:  
AC06-87RL10930
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: Oct 1994
Country of Publication:
United States
Language:
English
Subject:
12 MANAGEMENT OF RADIOACTIVE AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES; 11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS; 29 ENERGY PLANNING, POLICY AND ECONOMY; POLLUTION CONTROL; IMPLEMENTATION; PROGRAM MANAGEMENT; POLLUTION ABATEMENT; MITIGATION; SCHEDULES; WASTE MANAGEMENT; 052000; 053000; 290300; ENVIRONMENTAL ASPECTS; ENVIRONMENT, HEALTH, AND SAFETY

Citation Formats

Floyd, B C. Westinghouse Hanford Company Pollution Prevention Program Implementation Plan. United States: N. p., 1994. Web. doi:10.2172/10103402.
Floyd, B C. Westinghouse Hanford Company Pollution Prevention Program Implementation Plan. United States. https://doi.org/10.2172/10103402
Floyd, B C. 1994. "Westinghouse Hanford Company Pollution Prevention Program Implementation Plan". United States. https://doi.org/10.2172/10103402. https://www.osti.gov/servlets/purl/10103402.
@article{osti_10103402,
title = {Westinghouse Hanford Company Pollution Prevention Program Implementation Plan},
author = {Floyd, B C},
abstractNote = {This plan documents Westinghouse Hanford Company`s (WHC) Pollution Prevention (P2) (formerly Waste Minimization) program. The program includes WHC; BCS Richland, Inc. (BCSR); and ICF Kaiser Hanford Company (ICF KH). The plan specifies P2 program activities and schedules for implementing the Hanford Site Waste Minimization and Pollution Prevention Awareness (WMin/P2) Program Plan requirements (DOE 1994a). It is intended to satisfy the U.S. Department of Energy (DOE) and other legal requirements that are discussed in both the Hanford Site WMin/P2 plan and paragraph C of this plan. As such, the Pollution Prevention Awareness Program required by DOE Order 5400.1 (DOE 1988) is included in the WHC P2 program. WHC, BCSR, and ICF KH are committed to implementing an effective P2 program as identified in the Hanford Site WMin/P2 Plan. This plan provides specific information on how the WHC P2 program will develop and implement the goals, activities, and budget needed to accomplish this. The emphasis has been to provide detailed planning of the WHC P2 program activities over the next 3 years. The plan will guide the development and implementation of the program. The plan also provides background information on past program activities. Because the plan contains greater detail than in the past, activity scope and implementation schedules may change as new priorities are identified and new approaches are developed and realized. Some activities will be accelerated, others may be delayed; however, all of the general program elements identified in this plan and contractor requirements identified in the Site WMin/P2 plan will be developed and implemented during the next 3 years. This plan applies to all WHC, BCSR, and ICF KH organizations and subcontractors. It will be distributed to those with defined responsibilities in this plan; and the policy, goals, objectives, and strategy of the program will be communicated to all WHC, BCSR, and ICF KH employees.},
doi = {10.2172/10103402},
url = {https://www.osti.gov/biblio/10103402}, journal = {},
number = ,
volume = ,
place = {United States},
year = {Sat Oct 01 00:00:00 EDT 1994},
month = {Sat Oct 01 00:00:00 EDT 1994}
}