Title: Advanced Reactors Transition Program Resource Loaded Schedule

Technical Report ·
DOI:https://doi.org/10.2172/801171· OSTI ID:801171

The Advanced Reactors Transition (ART) Resource Loaded Schedule (RLS) provides a cost and schedule baseline for managing the project elements within the ART Program. The Fast Flux Test Facility (FETF) activities are delineated through the end of FY 2000, assuming continued standby. The Nuclear Energy (NE) Legacies and Plutonium Recycle Test Reactor (PRTR) activities are delineated through the end of the deactivation process. This revision reflects the 19 Oct 1999 baseline.

Research Organization:
BWHC (US)
Sponsoring Organization:
ENVIRONMENTAL MANAGEMENT (US)
DOE Contract Number:
AC06-96RL13200
OSTI ID:
801171
Report Number(s):
HNF-SD-FF-SSP-050, Rev.8; TRN: US200224%%817
Resource Relation:
Other Information: PBD: 12 Jan 2000
Country of Publication:
United States
Language:
English

Similar Records

Advanced Reactors Transition Program Resource Loaded Schedule
Technical Report · Mon Nov 08 00:00:00 EST 1999 · OSTI ID:801171

FFTF and Advanced Reactors Transition Program Resource Loaded Schedule
Technical Report · Tue Oct 31 00:00:00 EST 2000 · OSTI ID:801171

Fast Flux Test Facility transition project resource loaded schedule. Revision 1
Technical Report · Mon Oct 31 00:00:00 EST 1994 · OSTI ID:801171