Central receiver solar thermal power system, Phase 1. Quarterly progress report (final) for period ending March 31, 1976
During this period (January 1976 through March 1976), the primary program effort was expended toward the completion of the detail design of the three major research experiments. Also, the Preliminary Pilot Plant Economic Cost Study was completed. In the Collector Subsystem, the designs for both the twenty-five mirror and the nine-mirror heliostats were completed and released. In the Receiver Subsystem, Foster Wheeler continued with the detail design of the 5 MW research experiment receiver. A preliminary draft of the detailed test plan for the receiver subsystem research experiment was prepared and is now undergoing a final review. The detailed design of the Thermal Storage Subsystem continued at Georgia Institute of Technology. Several incremental detail design reviews were held as the design progressed. During this period, Bechtel completed the preliminary environmental analysis for the Pilot Plant. The optimization studies of the electrical power generation subsystem were initiated. A major effort was the preparation of the preliminary cost analysis for the 10 MWe Central Receiver Solar Thermal Pilot Plant. This task required the development of a cost accounting structure and a definition of all of the costs associated with the design, construction, checkout, and two-year test of the Pilot Plant. (WDM)
- Research Organization:
- Martin Marietta Corp., Denver, CO (USA)
- Sponsoring Organization:
- US Energy Research and Development Administration (ERDA)
- DOE Contract Number:
- E(04-3)-1110
- OSTI ID:
- 7331415
- Report Number(s):
- SAN-1110-76/1; MCR-76-131
- Country of Publication:
- United States
- Language:
- English