Engineering task plan and status of 241-S-106 Enraf level gauge wire break
This report discusses the findings of a task team which was formed which identified the need for short-term actions to re-establish tank waste level monitoring and to permanently address wire failure. The failed wire was removed and sent to Pacific Northwest Laboratory (PNL) for analysis. It was determined that the cause of the wire failure was due to chloride ion stress corrosion cracking (SCC) of the 316 stainless steel (SS) wire. Radiation induced breakdown of the polyvinyl chloride (PVC) riser liners is suspected to be the source of the chloride ions.
- Research Organization:
- Westinghouse Hanford Co., Richland, WA (United States)
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- AC06-87RL10930
- OSTI ID:
- 10187719
- Report Number(s):
- WHC-SD-WM-ETP-119; ON: DE95001038; BR: 35AF11201/35AF11202
- Resource Relation:
- Other Information: PBD: Sep 1994
- Country of Publication:
- United States
- Language:
- English
Similar Records
Test plan for Enraf Series 854 level gauge wire testing
Test plan for the selection of the ENRAF gauge wire material
Selection of replacement material for the failed surface level gauge wire in Hanford waste tanks
Technical Report
·
Thu Sep 15 00:00:00 EDT 1994
·
OSTI ID:10187719
Test plan for the selection of the ENRAF gauge wire material
Technical Report
·
Wed Nov 16 00:00:00 EST 1994
·
OSTI ID:10187719
Selection of replacement material for the failed surface level gauge wire in Hanford waste tanks
Conference
·
Sun Oct 01 00:00:00 EDT 1995
·
OSTI ID:10187719