Title: Technical WOrk Plan for: Construction Effects Monitoring

Abstract

This document is the technical work plan (TWP) for performing the Construction Effects Monitoring (CEM) activity, which is one of 20 testing and monitoring activities included in Performance Confirmation Plan (BSC 2004 [DIRS 172452]). Collectively, the 20 activities make up the Performance Confirmation Program described in the plan. Each of the other 19 activities will have a separate TWP. This plan, though titled Construction Effects Monitoring, in accordance with the Performance Confirmation Plan, also includes testing that may be performed in addition to monitoring, if required. Performance confirmation is required by regulation 10 CFR Part 63 [DIRS 173273], and was started during site characterization (consistent with the regulation) and will continue until permanent closure of the repository (10 CFR 63.13 1 (b) [DIRS 173273]). This CEM activity has two primary goals: (1) to collect, analyze, and report on repository rock properties data for the purpose of confirming geotechnical and design parameters used in repository design, and (2) to provide information intended to confirm that the ability to retrieve waste from the repository has been preserved. It will be necessary for information from this CEM activity to be evaluated in combination with that obtained from other Performance Confirmation Program activities tomore » achieve these goals. These relationships with other Performance Confirmation Program activities (e.g., drift inspection, subsurface mapping, and seismicity monitoring) will be discussed in later sections of this TWP.« less

Authors:
Publication Date:
Research Org.:
Yucca Mountain Project, Las Vegas, NV (United States)
Sponsoring Org.:
USDOE
OSTI Identifier:
895365
Report Number(s):
TWP-MGR-GE-000006, Rev 01
DOC.20060915.0004, DC# 48868; TRN: US0702063
DOE Contract Number:  
NA
Resource Type:
Technical Report
Country of Publication:
United States
Language:
English
Subject:
12 MANAGEMENT OF RADIOACTIVE WASTES, AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES; RADIOACTIVE WASTE FACILITIES; CONSTRUCTION; DESIGN; MONITORING; PERFORMANCE; SEISMICITY; SITE CHARACTERIZATION; TESTING; PLANNING; ROCK MECHANICS; MONITORED RETRIEVABLE STORAGE

Citation Formats

Goodin, S. Technical WOrk Plan for: Construction Effects Monitoring. United States: N. p., 2006. Web. doi:10.2172/895365.
Goodin, S. Technical WOrk Plan for: Construction Effects Monitoring. United States. https://doi.org/10.2172/895365
Goodin, S. 2006. "Technical WOrk Plan for: Construction Effects Monitoring". United States. https://doi.org/10.2172/895365. https://www.osti.gov/servlets/purl/895365.
@article{osti_895365,
title = {Technical WOrk Plan for: Construction Effects Monitoring},
author = {Goodin, S},
abstractNote = {This document is the technical work plan (TWP) for performing the Construction Effects Monitoring (CEM) activity, which is one of 20 testing and monitoring activities included in Performance Confirmation Plan (BSC 2004 [DIRS 172452]). Collectively, the 20 activities make up the Performance Confirmation Program described in the plan. Each of the other 19 activities will have a separate TWP. This plan, though titled Construction Effects Monitoring, in accordance with the Performance Confirmation Plan, also includes testing that may be performed in addition to monitoring, if required. Performance confirmation is required by regulation 10 CFR Part 63 [DIRS 173273], and was started during site characterization (consistent with the regulation) and will continue until permanent closure of the repository (10 CFR 63.13 1 (b) [DIRS 173273]). This CEM activity has two primary goals: (1) to collect, analyze, and report on repository rock properties data for the purpose of confirming geotechnical and design parameters used in repository design, and (2) to provide information intended to confirm that the ability to retrieve waste from the repository has been preserved. It will be necessary for information from this CEM activity to be evaluated in combination with that obtained from other Performance Confirmation Program activities to achieve these goals. These relationships with other Performance Confirmation Program activities (e.g., drift inspection, subsurface mapping, and seismicity monitoring) will be discussed in later sections of this TWP.},
doi = {10.2172/895365},
url = {https://www.osti.gov/biblio/895365}, journal = {},
number = ,
volume = ,
place = {United States},
year = {Thu Sep 14 00:00:00 EDT 2006},
month = {Thu Sep 14 00:00:00 EDT 2006}
}