Incorporating the Technology Roadmap Uncertainties into the Project Risk Assessment
This paper describes two methods, Technology Roadmapping and Project Risk Assessment, which were used to identify and manage the technical risks relating to the treatment of sodium bearing waste at the Idaho National Engineering and Environmental Laboratory. The waste treatment technology under consideration was Direct Vitrification. The primary objective of the Technology Roadmap is to identify technical data uncertainties for the technologies involved and to prioritize the testing or development studies to fill the data gaps. Similarly, project management's objective for a multi-million dollar construction project includes managing all the key risks in accordance to DOE O 413.3 - ''Program and Project Management for the Acquisition of Capital Assets.'' In the early stages, the Project Risk Assessment is based upon a qualitative analysis for each risk's probability and consequence. In order to clearly prioritize the work to resolve the technical issues identified in the Technology Roadmap, the issues must be cross- referenced to the project's Risk Assessment. This will enable the project to get the best value for the cost to mitigate the risks.
- Research Organization:
- Idaho National Lab. (INL), Idaho Falls, ID (United States)
- Sponsoring Organization:
- USDOE Office of Environmental Management (EM) (US)
- DOE Contract Number:
- AC07-99ID13727
- OSTI ID:
- 797099
- Report Number(s):
- INEEL/CON-02-00064; TRN: US0201793
- Resource Relation:
- Conference: Waste Management 2002, Tucson, AZ (US), 02/24/2002--02/28/2002; Other Information: PBD: 16 Jan 2002
- Country of Publication:
- United States
- Language:
- English
Similar Records
Pre-Decisional Sodium Bearing Waste Technology Development Roadmap FY-01 Update
Roadmapping or development of future investments in environmental science and technology