Postulated licensing schedule for an independent spent fuel storage installation
Abstract
A review of licensing requirements, processes, and anticipated actions for independent spent fuel storage installations (ISFSIs) was conducted in order to develop an estimated schedule and sequence of events for licensing a new ISFSI. This estimate will be useful to potential ISFSI owners in planning for the licensing of their facilities. It is concluded that, although many uncertainties exist with respect to such things as legal appeals, about 29 months are estimated to elapse between license application and license issuance for an ISFSI. This estimate is in reasonable agreement with a previous time estimate for licensing an ISFSI, and, taking into account the special circumstances involved, with the actual licensing schedule for the GE-Morris ISFSI. However, individual portions of the licensing schedule from each case studied sometimes vary significantly.
- Authors:
- Publication Date:
- Research Org.:
- Pacific Northwest National Lab. (PNNL), Richland, WA (United States)
- OSTI Identifier:
- 6900720
- Report Number(s):
- PNL-4498
ON: DE83003828
- DOE Contract Number:
- AC06-76RL01830
- Resource Type:
- Technical Report
- Resource Relation:
- Other Information: Portions of document are illegible. Printed copy available until stock is exhausted
- Country of Publication:
- United States
- Language:
- English
- Subject:
- 11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS; SPENT FUEL STORAGE; LICENSING; STORAGE FACILITIES; STORAGE; 050900* - Nuclear Fuels- Transport, Handling, & Storage
Citation Formats
Ludwick, J D. Postulated licensing schedule for an independent spent fuel storage installation. United States: N. p., 1982.
Web. doi:10.2172/6900720.
Ludwick, J D. Postulated licensing schedule for an independent spent fuel storage installation. United States. https://doi.org/10.2172/6900720
Ludwick, J D. 1982.
"Postulated licensing schedule for an independent spent fuel storage installation". United States. https://doi.org/10.2172/6900720. https://www.osti.gov/servlets/purl/6900720.
@article{osti_6900720,
title = {Postulated licensing schedule for an independent spent fuel storage installation},
author = {Ludwick, J D},
abstractNote = {A review of licensing requirements, processes, and anticipated actions for independent spent fuel storage installations (ISFSIs) was conducted in order to develop an estimated schedule and sequence of events for licensing a new ISFSI. This estimate will be useful to potential ISFSI owners in planning for the licensing of their facilities. It is concluded that, although many uncertainties exist with respect to such things as legal appeals, about 29 months are estimated to elapse between license application and license issuance for an ISFSI. This estimate is in reasonable agreement with a previous time estimate for licensing an ISFSI, and, taking into account the special circumstances involved, with the actual licensing schedule for the GE-Morris ISFSI. However, individual portions of the licensing schedule from each case studied sometimes vary significantly.},
doi = {10.2172/6900720},
url = {https://www.osti.gov/biblio/6900720},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Mon Nov 01 00:00:00 EST 1982},
month = {Mon Nov 01 00:00:00 EST 1982}
}