Project planning and management techniques of the fast-paced TMX-Upgrade construction
The Tandem Mirror Experiment-Upgrade (TMX-Upgrade) construction will be completed in 18 months at a total cost of $14.5 million. This paper describes the project planning and the management techniques used to complete the TMX-Upgrade within its allocated cost and schedule. In the planning stages of a project, before approval of the proposal, we define major project objectives, create a work breakdown structure (WBS), detail a technical description for each level of the WBS, and provide detailed bottoms-up cost estimates and summary schedules. In the operating phase, which continues throughout the project, we establish budget and schedule baselines. The reporting phase includes The Department of Energy (DOE) reviews of project status at monthly, quarterly, and semiannual intervals. These reports include cost, schedule, manpower, major procurement, and technical status information.
- Research Organization:
- Lawrence Livermore National Lab., CA (USA)
- DOE Contract Number:
- W-7405-ENG-48
- OSTI ID:
- 6131317
- Report Number(s):
- UCRL-85985; CONF-811040-14; ON: DE82001593; TRN: 82-001406
- Resource Relation:
- Conference: 9. symposium on engineering problems of fusion research, Chicago, IL, USA, 26 Oct 1981
- Country of Publication:
- United States
- Language:
- English
Similar Records
Mixed waste management facility. Monthly report, February 1994
Technician support for operation and maintenance of large fusion experiments: the tandem mirror experiment upgrade (TMX-U) approach