Tampa Electric Company -- IGCC Project. Quarterly report, July--September 1995
This is the quarterly report for 1995 of the Tampa Electric Company integrated gasification combined-cycle project at Polk Power Station. As of the end of the third quarter of 1995, engineering is essentially complete; construction is about 50% complete. The project is on schedule for the Target Project Completion Date of September 15, 1996. The work force at the site now stands at 1,300 people. Recently the project was recognized for reaching 1 million man-hours without a lost time injury. The report discusses engineering issues, project management issues, construction issues, and accomplishments of each.
- Research Organization:
- Tampa Electric Co., FL (United States)
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- FC21-91MC27363
- OSTI ID:
- 392807
- Report Number(s):
- DOE/MC/27363-5168; ON: DE96004440; TRN: AHC29622%%43
- Resource Relation:
- Other Information: PBD: Oct 1995
- Country of Publication:
- United States
- Language:
- English
Similar Records
Tampa Electric Company IGCC Project. Quarterly report, April 1 - June 30, 1996
[Tampa Electric Company IGCC project]. Final public design report; Technical progress report
Tampa Electric Company, Polk Power Station Unit No. 1, preliminary public design report
Technical Report
·
Tue Dec 31 00:00:00 EST 1996
·
OSTI ID:392807
[Tampa Electric Company IGCC project]. Final public design report; Technical progress report
Technical Report
·
Mon Jul 01 00:00:00 EDT 1996
·
OSTI ID:392807
Tampa Electric Company, Polk Power Station Unit No. 1, preliminary public design report
Technical Report
·
Wed Jun 01 00:00:00 EDT 1994
·
OSTI ID:392807