Title: W-026 acceptance test plan plant control system hardware (submittal {number_sign} 216)

Technical Report ·
DOI:https://doi.org/10.2172/328704· OSTI ID:328704

Acceptance Testing of the WRAP 1 Plant Control System Hardware will be conducted throughout the construction of WRAP I with the final testing on the Process Area hardware being completed in November 1996. The hardware tests will be broken out by the following functional areas; Local Control Units, Operator Control Stations in the WRAP Control Room, DMS Server, PCS Server, Operator Interface Units, printers, DNS terminals, WRAP Local Area Network/Communications, and bar code equipment. This document will contain completed copies of each of the hardware tests along with the applicable test logs and completed test exception reports.

Research Organization:
Fluor Daniel Hanford, Inc., Richland, WA (United States)
Sponsoring Organization:
USDOE Office of Environmental Restoration and Waste Management, Washington, DC (United States)
DOE Contract Number:
AC06-96RL13200
OSTI ID:
328704
Report Number(s):
HNF-SD-W026-ATP-022; ON: DE98059597; BR: 39EW31300; TRN: 97000104
Resource Relation:
Other Information: PBD: 14 Feb 1997
Country of Publication:
United States
Language:
English

Similar Records

W-026 acceptance test report plant control system hardware (submittal {number_sign} 220.C)
Technical Report · Fri Feb 14 00:00:00 EST 1997 · OSTI ID:328704

W-026 acceptance test plan plant control system software (submittal {number_sign} 216)
Technical Report · Fri Feb 14 00:00:00 EST 1997 · OSTI ID:328704

W-026 acceptance test report plant control system software(submittal {number_sign}223.02)
Technical Report · Fri Feb 14 00:00:00 EST 1997 · OSTI ID:328704