Rough order of magnitude cost estimate for immobilization of 18.2 MT of plutonium using existing facilities at the Savannah River site: alternatives 3B/5B/6C/6D/7B/9B
The purpose of this Cost Estimate Report is to identify preliminary capital and operating costs for a facility to immobilize 18.2 metric tons (nominal) of plutonium using ceramic in an existing facility (221-F) at Savannah River Site (SRS).
- Research Organization:
- Lawrence Livermore National Lab. (LLNL), Livermore, CA (United States)
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- W-7405-ENG-48
- OSTI ID:
- 314015
- Report Number(s):
- UCRL-ID-131073; ON: DE98058788; BR: GA0102011; TRN: 99:002959
- Resource Relation:
- Other Information: PBD: 1 Jun 1998
- Country of Publication:
- United States
- Language:
- English
Similar Records
Rough order of magnitude cost estimate for immobilization of 18.2 MT of plutonium using existing facilities at the Savannah River site: alternatives 3A/5A/6A/6B/7A/9A
Rough order of magnitude cost estimate for immobilization of 18.2 MT of plutonium sharing existing facilities at Hanford with pit disassembly {ampersand} conversion facility: alternative 2
Rough order of magnitude cost estimate for immobilization of 50 MT of plutonium using existing facilities at the Savannah River site: alternative 12B
Technical Report
·
Mon Jun 01 00:00:00 EDT 1998
·
OSTI ID:314015
Rough order of magnitude cost estimate for immobilization of 18.2 MT of plutonium sharing existing facilities at Hanford with pit disassembly {ampersand} conversion facility: alternative 2
Technical Report
·
Mon Jun 01 00:00:00 EDT 1998
·
OSTI ID:314015
Rough order of magnitude cost estimate for immobilization of 50 MT of plutonium using existing facilities at the Savannah River site: alternative 12B
Technical Report
·
Mon Jun 01 00:00:00 EDT 1998
·
OSTI ID:314015