Title: Quality Assurance Plan for site electrical replacements at substation line item subproject: 69 KV Substation

Technical Report ·
DOI:https://doi.org/10.2172/253349· OSTI ID:253349

The 69 KV Substation Project is based on the recognized need to provide a continuous, reliable source of power and to improve the firm capacity of the electrical service to all production facilities at Mound. The project consists of the following major element: 69 KV Substation: (1) Install a 69 KV Substation and associated equipment with two parallel 18 MVA transformers. (2) Install duct bank as required and provide 15 KV feeder cable from new substation to existing Substation 95 for connection to Mound`s existing primary distribution system. (3) Install duct bank for underground routing of the 15 KV feeder cable from Manhole 5C to the existing power house cable pit. (4) Reconfigure existing Dayton Power and Light Co. 15 KV switchgear in P Building. The purpose of this Quality Assurance Plan (QA Plan) is to assure that the objectives of the United States Department of Energy (D.O.E.) and EG&G Mound Applied Technologies, Miamisburg, Ohio (Mound) are met for this non-weapons project relative to health and safety, protection of the environment, reliability and continuity of operations, and documentation of quality efforts. This QA Plan identifies the activities and responsibilities which are necessary in the design, procurement, fabrication, installation, and start up of this project in order to meet these objectives.

Research Organization:
EG and G Mound Applied Technologies, Miamisburg, OH (United States)
Sponsoring Organization:
USDOE, Washington, DC (United States)
DOE Contract Number:
AC24-88DP43495
OSTI ID:
253349
Report Number(s):
MLM-MU-91-65-0005; ON: DE96012397
Resource Relation:
Other Information: PBD: 21 May 1991