Controls Advanced Research Turbine (CART) Commissioning and Baseline Data Collection
During FY2002, the CART turbine and controller were developed and commissioned. This included developing and checking out the protection and operational control systems. More than 50 hours of data were collected in constant and variable-speed modes. A new strategy, which underwent limited testing on the machine, was created for avoiding tower resonance. All the data from the checkout through the operational periods were organized, archived, and backed up.
- Research Organization:
- National Renewable Energy Lab. (NREL), Golden, CO (United States)
- Sponsoring Organization:
- US Department of Energy (US)
- DOE Contract Number:
- AC36-99-GO10337
- OSTI ID:
- 15002211
- Report Number(s):
- NREL/TP-500-32879; TRN: US200408%%170
- Resource Relation:
- Other Information: PBD: 1 Oct 2002
- Country of Publication:
- United States
- Language:
- English
Similar Records
Geometry and Structural Properties for the Controls Advanced Research Turbine (CART) from Model Tuning: August 25, 2003--November 30, 2003
Progress in Implementing and Testing State-Space Controls for the Controls Advanced Research Turbine: Preprint
Baseline Results and Future Plans for the NREL Controls Advanced Research Turbine: Preprint
Technical Report
·
Wed Sep 01 00:00:00 EDT 2004
·
OSTI ID:15002211
Progress in Implementing and Testing State-Space Controls for the Controls Advanced Research Turbine: Preprint
Conference
·
Wed Dec 01 00:00:00 EST 2004
·
OSTI ID:15002211
Baseline Results and Future Plans for the NREL Controls Advanced Research Turbine: Preprint
Conference
·
Sat Nov 01 00:00:00 EST 2003
·
OSTI ID:15002211