LESSONS LEARNED - STARTUP AND TRANSITION TO OPERATIONS AT THE 200 WEST PUMP AND TREAT FACILITY
This document lists key Lessons Learned from the Startup Team for the 200 West Pump and Treat Facility Project. The Startup Team on this Project was an integrated, multi-discipline team whose scope was Construction Acceptance Testing (CAT), functional Acceptance Testing Procedures (ATP), and procedure development and implementation. Both maintenance and operations procedures were developed. Included in the operations procedures were the process unit operations. In addition, a training and qualification program was also part of the scope.
- Research Organization:
- Hanford Site (HNF), Richland, WA (United States)
- Sponsoring Organization:
- USDOE Office of Environmental Management (EM)
- DOE Contract Number:
- DE-AC06-08RL14788
- OSTI ID:
- 1059485
- Report Number(s):
- SGW-53650 REV 0
- Country of Publication:
- United States
- Language:
- English
Similar Records
Lessons Learned From The 200 West Pump And Treatment Facility Construction Project At The US DOE Hanford Site - A Leadership For Energy And Environmental Design (LEED) Gold-Certified Facility
Startup of the New 200 West Pump-and-Treat, Hanford Site, Richland, Washington - 13214
Lessons Learned from the 200 West Pump and Treatment Facility Construction Project at the US DOE Hanford Site - A Leadership for Energy and Environmental Design (LEED) Gold-Certified Facility
Conference
·
Wed Nov 14 00:00:00 EST 2012
·
OSTI ID:1059485
Startup of the New 200 West Pump-and-Treat, Hanford Site, Richland, Washington - 13214
Conference
·
Mon Jul 01 00:00:00 EDT 2013
·
OSTI ID:1059485
Lessons Learned from the 200 West Pump and Treatment Facility Construction Project at the US DOE Hanford Site - A Leadership for Energy and Environmental Design (LEED) Gold-Certified Facility
Conference
·
Fri Jan 11 00:00:00 EST 2013
·
OSTI ID:1059485