Project B610 process control configuration acceptance test procedure
The purpose of this test is to verify the Westinghouse configuration of the MICON A/S Distributed Control System for project B610. The following will be verified: proper assignment and operation of all field inputs to and outputs from the MICON Termination panels; proper operation of all display data on the operator`s console; proper operation of all required alarms; and proper operation of all required interlocks. The MICON A/S control system is configured to replace all the control, indication, and alarm panels now located in the Power Control Room. Nine systems are covered by this control configuration, 2736-ZB HVAC, 234-5Z HVAC, Process Vacuum, Dry Air, 291-Z Closed Loop Cooling, Building Accelerometer, Evacuation Siren, Stack CAMs, and Fire. The 2736-ZB HVAC system consists of the ventilation controls for 2736-ZB and 2736-Z as well as alarms for the emergency generators and 232-Z. The 234-5Z HVAC system is the ventilation controls for 235-5Z and 236-Z buildings. Process Vacuum covers the controls for the 26 inch vacuum system. Dry Air covers the controls for the steam and electric air dryers. The 291-Z Closed Loop Cooling system consists of the status indications and alarms for the 291-Z compressor and vacuum pump closed loop cooling system. The rest of closed loop cooling was tested earlier. The Building Accelerometer system consists of the status indications for the two seismic system accelerometers. The Evacuation Siren system includes the controls for the evacuation and take cover sirens. Stack CAMs cover the alarms for the various building ventilation stack continuous air monitors. Finally, the Fire system covers the various fire alarms now located in Room 321-A.
- Research Organization:
- Westinghouse Hanford Co., Richland, WA (United States)
- Sponsoring Organization:
- USDOE, Washington, DC (United States)
- DOE Contract Number:
- AC06-87RL10930
- OSTI ID:
- 10187556
- Report Number(s):
- WHC-SD-610-ATP-002; ON: DE95000995; BR: 35AF11201/35AF11202; TRN: 94:021038
- Resource Relation:
- Other Information: PBD: 20 Sep 1994
- Country of Publication:
- United States
- Language:
- English
Similar Records
PFP Wastewater Sampling Facility
Preliminary safety analysis report for project 89-GEB-610 Plutonium Finishing Plant instrumentation upgrade. Revision 1
Related Subjects
HANFORD RESERVATION
FUEL REPROCESSING PLANTS
AUXILIARY SYSTEMS
PERFORMANCE TESTING
PLUTONIUM
SCRAP METALS
SPACE HVAC SYSTEMS
GAS COMPRESSORS
VACUUM SYSTEMS
ALARM SYSTEMS
FIRE DETECTORS
ACCELEROMETERS
SEISMIC EVENTS
COOLING SYSTEMS
VENTILATION SYSTEMS
AIR POLLUTION MONITORS
050800
SPENT FUELS REPROCESSING