Title: Technical progress report for the Magnetohydrodynamics Coal-Fired Flow Facility: October 1, 1992--December 31, 1992

Technical Report ·
DOI:https://doi.org/10.2172/10184887· OSTI ID:10184887

Progress is reported on a multitask contract to develop technology for steam bottoming cycle of a Combined Cycle MHD Steam Power Plant. The report describes a 314 hour proof-of-concept (POC) test completed during the quarter. Results include secondary combustion and effect of potassium on the light-off temperature, fouling of heat transfer surfaces, particulate clean-up device performance and advanced diagnostic system performance. Test results on ceramic materials and tubes directed toward the development of a high temperature recuperative air heater are summarized. Results of data analysis of previous tests that are reported include the continuing analysis of tube materials that were exposed to 1500 and 2000 hours of eastern coal fired operation during the previously completed 2000 hour POC test series on eastern, high sulfur coal.

Research Organization:
Tennessee Univ., Tullahoma, TN (United States). Space Inst.
Sponsoring Organization:
USDOE, Washington, DC (United States)
DOE Contract Number:
AC02-79ET10815
OSTI ID:
10184887
Report Number(s):
DOE/ET/10815-205; UTSI-93-01; ON: DE94000879
Resource Relation:
Other Information: PBD: Jun 1993
Country of Publication:
United States
Language:
English