Title: MHD Integrated Topping Cycle Project. Twentieth quarterly technical progress report, May 1, 1992--July 31, 1992

Technical Report ·
DOI:https://doi.org/10.2172/10178333· OSTI ID:10178333

Manufacturing, assembly, and checkout of combustion subsystem hardware was completed, and the hardware delivered to CDIF along with the water electrical isolators. A successful nozzle proof test was concluded; purpose was to evaluate adequacy of the nozzle structure and sealing of sidewall-to-electrode wall joints, water tubes, and stud and wire penetrations at operating pressure. Design modifications to spare channel inlet frame were made to enable iron oxide injection. Results of tests in the CDIF 1A1 channel which compared effect of different cathode wall iron oxide injection locations indicated that injection through the side port may be more effective, particularly if one of the two ports become clogged. Design confirmation testing of a pneumatically driven ram to clear a plugged iron oxide injector tip was performed. Manufacture of spare and replacement parts for 1A4 channel and diffuser was begun. Construction of the cathode power cabinets and associated control system was completed. Hot-fire checkout series was completed for the combustion subsystem; 16.8 thermal hours were accumulated during 7 tests. This test series demonstrated adequacy of overall cooling of combustion subsystem and provided an initial evaluation of heat losses and slagging characteristics. Several major facility activities at the CDIF were accomplished including installation and testing of new iron oxide pumps, initial on-line checkout of coal feed system modifications, modification of seed system including replacement of silo rotary feeder, installation of new filter receiver on the silo, and conversion of fly ash bin to dust collector, removal of all of the electrical wiring (used for 1A1 channel) between the channel and HVR in order to install 1A4 wiring, and installation of the 1A4 channel.

Research Organization:
TRW Space and Electronics Group, Redondo Beach, CA (United States). Applied Technology Div.
Sponsoring Organization:
USDOE, Washington, DC (United States)
DOE Contract Number:
AC22-87PC90274
OSTI ID:
10178333
Report Number(s):
DOE/PC/90274-T21; MHD-ITC-92-236; ON: DE93040521