Title: Tidd PFBC Demonstration Project: Quarterly report, April 1--June 30, 1993

Abstract

This is the 25th Technical Progress Report submitted to the Department of Energy in connection with the cooperative agreement between the DOE and the Ohio Power Company for the Tidd PFBC Demonstration Plant. This report covers the period from April 1, 1993 to June 30, 1993. Major activities during this period involve: (1) The unit has been out of service since early February due to the failure of the gas turbine. The gas turbine was repaired during this quarter and unit was started on June 29, 1993. (2) The unit was operated for a total of 32 hours (including gas turbine air prewarming). There were three gas turbine starts, two bed preheater starts, and one operating period with coal fire. The peak gross output of 13 MWH was achieved for the period of 2200 to 2300 hours on June 30, 1993. (3) During the quarter, total gross generation was 75 MWH, and coal consumption was 107 tons. (4) New individual ash lines from cyclones to the economizer were installed. (5) New sparge ducts were installed along with sparge duct end fluidization piping and valves. (6) Expansion joint heaters and insulation for hot gas clean-up system were installed. Major items plannedmore » for the next period include: installation of SO{sub 2} analyzer equipment, and continuation with the operation and testing of the unit after all the current GT problems are resolved.« less

Publication Date:
Research Org.:
American Electric Power Service Corp., Columbus, OH (United States)
Sponsoring Org.:
USDOE, Washington, DC (United States)
OSTI Identifier:
10125659
Report Number(s):
DOE/MC/24132-3633
ON: DE94004052; TRN: 94:002892
DOE Contract Number:  
FC21-87MC24132
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: Jul 1993
Country of Publication:
United States
Language:
English
Subject:
01 COAL, LIGNITE, AND PEAT; 20 FOSSIL-FUELED POWER PLANTS; FLUIDIZED-BED COMBUSTORS; DEMONSTRATION PLANTS; PROGRESS REPORT; COAL-FIRED GAS TURBINES; OPERATION; PROGRAM MANAGEMENT; 014000; 200100; COMBUSTION; POWER PLANTS AND POWER GENERATION

Citation Formats

. Tidd PFBC Demonstration Project: Quarterly report, April 1--June 30, 1993. United States: N. p., 1993. Web. doi:10.2172/10125659.
. Tidd PFBC Demonstration Project: Quarterly report, April 1--June 30, 1993. United States. https://doi.org/10.2172/10125659
. 1993. "Tidd PFBC Demonstration Project: Quarterly report, April 1--June 30, 1993". United States. https://doi.org/10.2172/10125659. https://www.osti.gov/servlets/purl/10125659.
@article{osti_10125659,
title = {Tidd PFBC Demonstration Project: Quarterly report, April 1--June 30, 1993},
author = {},
abstractNote = {This is the 25th Technical Progress Report submitted to the Department of Energy in connection with the cooperative agreement between the DOE and the Ohio Power Company for the Tidd PFBC Demonstration Plant. This report covers the period from April 1, 1993 to June 30, 1993. Major activities during this period involve: (1) The unit has been out of service since early February due to the failure of the gas turbine. The gas turbine was repaired during this quarter and unit was started on June 29, 1993. (2) The unit was operated for a total of 32 hours (including gas turbine air prewarming). There were three gas turbine starts, two bed preheater starts, and one operating period with coal fire. The peak gross output of 13 MWH was achieved for the period of 2200 to 2300 hours on June 30, 1993. (3) During the quarter, total gross generation was 75 MWH, and coal consumption was 107 tons. (4) New individual ash lines from cyclones to the economizer were installed. (5) New sparge ducts were installed along with sparge duct end fluidization piping and valves. (6) Expansion joint heaters and insulation for hot gas clean-up system were installed. Major items planned for the next period include: installation of SO{sub 2} analyzer equipment, and continuation with the operation and testing of the unit after all the current GT problems are resolved.},
doi = {10.2172/10125659},
url = {https://www.osti.gov/biblio/10125659}, journal = {},
number = ,
volume = ,
place = {United States},
year = {Thu Jul 01 00:00:00 EDT 1993},
month = {Thu Jul 01 00:00:00 EDT 1993}
}