Title: Project management plan for Project W-178, 219-S secondary containment

Technical Report ·
DOI:https://doi.org/10.2172/10118790· OSTI ID:10118790

This Project Management Plan (PMP) establishes the organizational responsibilities, control systems, and procedures for managing the execution of project activities for Project W-178, the 219-S Secondary Containment Upgrade. The scope of this project will provide the 219-S Facility with secondary containment for all tanks and piping systems. Tank 103 will be replaced with a new tank which will be designated as Tank 104. Corrosion protection shall be installed as required. The cells shall be cleaned and the surface repaired as required. The 219-S Waste Handling Facility (219-S Facility), located in the 200 West Area, was constructed in 1951 to support the 222-S Laboratory Facility. The 219-S Facility has three tanks, TK-101, TK-102, and TK-103, which receive and neutralize low level radioactive wastes from the 222-S Laboratory. For purposes of the laboratory, the different low level waste streams have been designated as high activity and intermediate activity. The 219-S Facility accumulates and treats the liquid waste prior to transferring it to SY Tank Farm in the 200-W Area. Transfers are normally made by pipeline from the 219-S Facility to the 241-SY Tank Farm. Presently transfers are being made by tanker truck to the 200-E Area Tank Farms due to the diversion box catch tank which has been removed from service.

Research Organization:
Westinghouse Hanford Co., Richland, WA (United States)
Sponsoring Organization:
USDOE, Washington, DC (United States)
DOE Contract Number:
AC06-87RL10930
OSTI ID:
10118790
Report Number(s):
WHC-SD-W178-PMP-001; ON: DE95006883; BR: 35AF11201/35AF11202; TRN: AHC29508%%70
Resource Relation:
Other Information: PBD: 26 Jan 1995