Title: Environment, Safety and Health Progress Assessment of the Argonne Illinois Site

Abstract

This report documents the results of the US Department of Energy (DOE) Environment, Safety and Health (ES&H) Progress Assessment of the Argonne Illinois Site (AIS), near Chicago, Illinois, conducted from October 25 through November 9, 1993. During the Progress Assessment, activities included a selective review of the ES&H management systems and programs with principal focus on the DOE Office of Energy Research (ER); CH, which includes the Argonne Area Office; the University of Chicago; and the contractor`s organization responsible for operation of Argonne National Laboratory (ANL). The ES&H Progress Assessments are part of DOE`s continuing effort to institutionalize line management accountability and the self-assessment process throughout DOE and its contractor organizations. The purpose of the AIS ES&H Progress Assessment was to provide the Secretary of Energy, senior DOE managers, and contractor management with concise independent information on the following: change in culture and attitude related to ES&H activities; progress and effectiveness of the ES&H corrective actions resulting from the previous Tiger Team Assessment; adequacy and effectiveness of the ES&H self-assessment process of the DOE line organizations, the site management, and the operating contractor; and effectiveness of DOE and contractor management structures, resources, and systems to effectively address ES&H problems andmore » new ES&H initiatives.« less

Publication Date:
Research Org.:
US Department of Energy (USDOE), Washington DC (United States)
Sponsoring Org.:
USDOE, Washington, DC (United States)
OSTI Identifier:
10115421
Report Number(s):
DOE/EH-0054
ON: DE94005317; NC: NONE; TRN: 94:012842
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: Nov 1993
Country of Publication:
United States
Language:
English
Subject:
54 ENVIRONMENTAL SCIENCES; 11 NUCLEAR FUEL CYCLE AND FUEL MATERIALS; 29 ENERGY PLANNING, POLICY AND ECONOMY; ANL; ENVIRONMENTAL QUALITY; COMPLIANCE AUDITS; REMEDIAL ACTION; ENVIRONMENTAL POLICY; WASTE MANAGEMENT; 540250; 054000; 290300; SITE RESOURCE AND USE STUDIES; HEALTH AND SAFETY; ENVIRONMENT, HEALTH, AND SAFETY

Citation Formats

. Environment, Safety and Health Progress Assessment of the Argonne Illinois Site. United States: N. p., 1993. Web. doi:10.2172/10115421.
. Environment, Safety and Health Progress Assessment of the Argonne Illinois Site. United States. https://doi.org/10.2172/10115421
. 1993. "Environment, Safety and Health Progress Assessment of the Argonne Illinois Site". United States. https://doi.org/10.2172/10115421. https://www.osti.gov/servlets/purl/10115421.
@article{osti_10115421,
title = {Environment, Safety and Health Progress Assessment of the Argonne Illinois Site},
author = {},
abstractNote = {This report documents the results of the US Department of Energy (DOE) Environment, Safety and Health (ES&H) Progress Assessment of the Argonne Illinois Site (AIS), near Chicago, Illinois, conducted from October 25 through November 9, 1993. During the Progress Assessment, activities included a selective review of the ES&H management systems and programs with principal focus on the DOE Office of Energy Research (ER); CH, which includes the Argonne Area Office; the University of Chicago; and the contractor`s organization responsible for operation of Argonne National Laboratory (ANL). The ES&H Progress Assessments are part of DOE`s continuing effort to institutionalize line management accountability and the self-assessment process throughout DOE and its contractor organizations. The purpose of the AIS ES&H Progress Assessment was to provide the Secretary of Energy, senior DOE managers, and contractor management with concise independent information on the following: change in culture and attitude related to ES&H activities; progress and effectiveness of the ES&H corrective actions resulting from the previous Tiger Team Assessment; adequacy and effectiveness of the ES&H self-assessment process of the DOE line organizations, the site management, and the operating contractor; and effectiveness of DOE and contractor management structures, resources, and systems to effectively address ES&H problems and new ES&H initiatives.},
doi = {10.2172/10115421},
url = {https://www.osti.gov/biblio/10115421}, journal = {},
number = ,
volume = ,
place = {United States},
year = {Mon Nov 01 00:00:00 EST 1993},
month = {Mon Nov 01 00:00:00 EST 1993}
}