Acceptance Test Procedure for New Pumping Instrumentation and Control Skid Q
This Test Plan provides a test method to dedicate the leak detection relays used on the new Pumping Instrumentation and Control (PIC) skids. The new skids are fabricated on-site. The leak detection system is a safety class system per the Authorization Basis.
- Research Organization:
- CH2M Hill Hanford Group, Inc., Richland, WA (United States)
- Sponsoring Organization:
- ENVIRONMENTAL MANAGEMENT (US)
- DOE Contract Number:
- AC27-99RL14047
- OSTI ID:
- 801351
- Report Number(s):
- RPP-5801, Rev.0; EDT-624872; TRN: US0300422
- Resource Relation:
- Other Information: PBD: 14 Feb 2000
- Country of Publication:
- United States
- Language:
- English
Similar Records
Acceptance Test Procedure for New Pumping Instrumentation and Control Skid P
Acceptance Test Procedure for New Pumping Instrumentation and Control Skid Q
Acceptance for Beneficial Use Pumping Instrumentation and Control Skid N
Technical Report
·
Mon Feb 14 00:00:00 EST 2000
·
OSTI ID:801351
Acceptance Test Procedure for New Pumping Instrumentation and Control Skid Q
Technical Report
·
Mon Mar 27 00:00:00 EST 2000
·
OSTI ID:801351
Acceptance for Beneficial Use Pumping Instrumentation and Control Skid N
Technical Report
·
Mon Mar 13 00:00:00 EST 2000
·
OSTI ID:801351