Title: Advanced Reactors Transition Program Resource Loaded Schedule

Abstract

The Advanced Reactors Transition (ART) Resource Loaded Schedule (RLS) provides a cost and schedule baseline for managing the project elements within the ART Program. The Fast Flux Test Facility (FETF) activities are delineated through the end of FY 2000, assuming continued standby. The Nuclear Energy (NE) Legacies and Plutonium Recycle Test Reactor (PRTR) activities are delineated through the end of the deactivation process. This revision reflects the 19 Oct 1999 baseline.

Authors:
Publication Date:
Research Org.:
BWHC (US)
Sponsoring Org.:
ENVIRONMENTAL MANAGEMENT (US)
OSTI Identifier:
801171
Report Number(s):
HNF-SD-FF-SSP-050, Rev.8
TRN: US200224%%817
DOE Contract Number:  
AC06-96RL13200
Resource Type:
Technical Report
Resource Relation:
Other Information: PBD: 12 Jan 2000
Country of Publication:
United States
Language:
English
Subject:
29 ENERGY PLANNING, POLICY AND ECONOMY; NUCLEAR ENERGY; PRTR REACTOR; SCHEDULES

Citation Formats

GANTT, D A. Advanced Reactors Transition Program Resource Loaded Schedule. United States: N. p., 2000. Web. doi:10.2172/801171.
GANTT, D A. Advanced Reactors Transition Program Resource Loaded Schedule. United States. https://doi.org/10.2172/801171
GANTT, D A. 2000. "Advanced Reactors Transition Program Resource Loaded Schedule". United States. https://doi.org/10.2172/801171. https://www.osti.gov/servlets/purl/801171.
@article{osti_801171,
title = {Advanced Reactors Transition Program Resource Loaded Schedule},
author = {GANTT, D A},
abstractNote = {The Advanced Reactors Transition (ART) Resource Loaded Schedule (RLS) provides a cost and schedule baseline for managing the project elements within the ART Program. The Fast Flux Test Facility (FETF) activities are delineated through the end of FY 2000, assuming continued standby. The Nuclear Energy (NE) Legacies and Plutonium Recycle Test Reactor (PRTR) activities are delineated through the end of the deactivation process. This revision reflects the 19 Oct 1999 baseline.},
doi = {10.2172/801171},
url = {https://www.osti.gov/biblio/801171}, journal = {},
number = ,
volume = ,
place = {United States},
year = {Wed Jan 12 00:00:00 EST 2000},
month = {Wed Jan 12 00:00:00 EST 2000}
}