Title: Naval Oil Shale Reserves: conceptual development plan

Technical Report ·
DOI:https://doi.org/10.2172/5123946· OSTI ID:5123946

The plan presented here is, first, to design and build a 20,000 BPD plant. After one year of operation, plant expansion to 50,000 BPD would start. Additional plants would be started every three years until 200,000 BPD production was achieved. This production rate can be sustained by the NOSR 1 resource for over 30 years, using current technology, with additional recoverable potential from lower grade shales as economics or technology improves. The development program is divided into five phases. Phase 0 includes preparing and securing the necessary approvals, competitive selection of one or more technologies for retorting, and detailed engineering design. Phase 1a is construction of the 20,000 BPD production facility, Phase 1b is expansion to 50,000 BPD. Phases 2, 3, and 4 each add an additional 50,000 BPD plant. Costs and revenues, based on the planned schedule and production, and on a $35 per barrel value for the upgraded syncrude are presented. A three-year budget of $3.2 million (in 1982 dollars) is required initially to complete and support the necessary approval packages and to provide the engineering basis for the technology selection. The subsequent 2-1/2 years will require $140 million for permits, technology selection, detailed engineering design, and complete technical, management and procurement plans for Phase 1a, the construction of the 20,000 BPD facility.

Research Organization:
TRW, Inc., McLean, VA (USA). Energy Systems Planning Div.
DOE Contract Number:
AC01-78RA32012
OSTI ID:
5123946
Report Number(s):
DOE/RA/32012-T21; ON: DE84006948
Resource Relation:
Other Information: Portions are illegible in microfiche products. Original copy available until stock is exhausted
Country of Publication:
United States
Language:
English