Title: Use of phenomena identification and ranking (PIRT) process in research related to design certification of the AP600 advanced passive light water reactor (LWR)

Conference ·
OSTI ID:248191
;  [1];  [2]
  1. Idaho National Engineering Lab., Idaho Falls, ID (United States)
  2. Nuclear Regulatory Commission, Washington, DC (United States). Office of Nuclear Regulatory Research

The AP600 LWR is a new advanced passive design that has been submitted to the USNRC for design certification. Within the certification process the USNRC will perform selected system thermal hydraulic response audit studies to help confirm parts of the vendor`s safety analysis submittal. Because of certain innovative design features of the safety systems, new experimental data and related advances in the system thermal hydraulic analysis computer code are being developed by the USNRC. The PIRT process is being used to focus the experimental and analytical work to obtain a sufficient and cost effective research effort. The objective of this paper is to describe the application and most significant results of the PIRT process, including several innovative features needed in the application to accommodate the short design certification schedule. The short design certification schedule has required that many aspects of the USNRC experimental and analytical research be performed in parallel, rather than in series as was normal for currently operating LWRS. This has required development and use of management techniques that focus and integrate the various diverse parts of the research. The original PIRTs were based on inexact knowledge of an evolving reactor design, and concentrated on the new passive features of the design. Subsequently, the PIRTs have evolved in two more stages as the design became more firm and experimental and analytical data became available. A fourth and final stage is planned and in progress to complete the PIRT development. The PIRTs existing at the end of each development stage have been used to guide the experimental program, scaling analyses and code development supporting the audit studies.

DOE Contract Number:
AC07-94ID13223
OSTI ID:
248191
Report Number(s):
CONF-960306-; ISBN 0-7918-1226-X; TRN: 96:014875
Resource Relation:
Conference: ICONE 4: ASME/JSME international conference on nuclear engineering, New Orleans, LA (United States), 10-13 Mar 1996; Other Information: PBD: 1996; Related Information: Is Part Of ICONE-4: Proceedings. Volume 2: Advanced reactors; Rao, A.S. [ed.] [General Electric Nuclear Engineering, San Jose, CA (United States)]; Duffey, R.B. [ed.] [Brookhaven National Lab., Upton, NY (United States)]; Elias, D. [ed.] [Commonwealth Edison, Downers Grove, IL (United States)]; PB: 637 p.
Country of Publication:
United States
Language:
English