Environmental Cost Analysis System (ECAS) Status and Compliance Requirements for EM Consolidated Business Center Contracts - 13204
Abstract
The Department of Energy (DOE) Office of Environmental Management (EM) has developed a web-accessible database to collect actual cost data from completed EM projects to support cost estimating and analysis. This Environmental Cost Analysis System (ECAS) database was initially deployed in early 2009 containing the cost and parametric data from 77 decommissioning, restoration, and waste management projects completed under the Rocky Flats Closure Project. In subsequent years we have added many more projects to ECAS and now have a total of 280 projects from 8 major DOE sites. This data is now accessible to DOE users through a web-based reporting tool that allows users to tailor report outputs to meet their specific needs. We are using it as a principal resource supporting the EM Consolidated Business Center (EMCBC) and the EM Applied Cost Engineering (ACE) team cost estimating and analysis efforts across the country. The database has received Government Accountability Office review as supporting its recommended improvements in DOE's cost estimating process, as well as review from the DOE Office of Acquisition and Project Management (APM). Moving forward, the EMCBC has developed a Special Contract Requirement clause or 'H-Clause' to be included in all current and future EMCBC procurements identifyingmore »
- Authors:
-
- Consultant, 11221 E. Cimmarron Dr., Englewood, CO 80111 (United States)
- EMCBC Office of Cost Estimating and Analysis, United States Department of Energy, 250 E. 5th Street, Suite 500, Cincinnati, OH 45202 (United States)
- Team Analysis, Inc., 2 Cardinal Park Drive, Suite 105A, Leesburg, VA 20175 (United States)
- Project Performance Corporation, 1760 Old Meadow Road, McLean, VA 22102 (United States)
- Publication Date:
- Research Org.:
- WM Symposia, 1628 E. Southern Avenue, Suite 9-332, Tempe, AZ 85282 (United States)
- OSTI Identifier:
- 22224963
- Report Number(s):
- INIS-US-13-WM-13204
TRN: US14V0410045918
- Resource Type:
- Conference
- Resource Relation:
- Conference: WM2013: Waste Management Conference: International collaboration and continuous improvement, Phoenix, AZ (United States), 24-28 Feb 2013; Other Information: Country of input: France; 5 refs.
- Country of Publication:
- United States
- Language:
- English
- Subject:
- 12 MANAGEMENT OF RADIOACTIVE WASTES, AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES; 54 ENVIRONMENTAL SCIENCES; COMPLIANCE; COST; DECOMMISSIONING; NUCLEAR MATERIALS MANAGEMENT; PROCUREMENT; PROGRAM MANAGEMENT; WASTE MANAGEMENT
Citation Formats
Sanford, P. C., Moe, M. A., Hombach, W. G., and Urdangaray, R. Environmental Cost Analysis System (ECAS) Status and Compliance Requirements for EM Consolidated Business Center Contracts - 13204. United States: N. p., 2013.
Web.
Sanford, P. C., Moe, M. A., Hombach, W. G., & Urdangaray, R. Environmental Cost Analysis System (ECAS) Status and Compliance Requirements for EM Consolidated Business Center Contracts - 13204. United States.
Sanford, P. C., Moe, M. A., Hombach, W. G., and Urdangaray, R. 2013.
"Environmental Cost Analysis System (ECAS) Status and Compliance Requirements for EM Consolidated Business Center Contracts - 13204". United States.
@article{osti_22224963,
title = {Environmental Cost Analysis System (ECAS) Status and Compliance Requirements for EM Consolidated Business Center Contracts - 13204},
author = {Sanford, P. C. and Moe, M. A. and Hombach, W. G. and Urdangaray, R.},
abstractNote = {The Department of Energy (DOE) Office of Environmental Management (EM) has developed a web-accessible database to collect actual cost data from completed EM projects to support cost estimating and analysis. This Environmental Cost Analysis System (ECAS) database was initially deployed in early 2009 containing the cost and parametric data from 77 decommissioning, restoration, and waste management projects completed under the Rocky Flats Closure Project. In subsequent years we have added many more projects to ECAS and now have a total of 280 projects from 8 major DOE sites. This data is now accessible to DOE users through a web-based reporting tool that allows users to tailor report outputs to meet their specific needs. We are using it as a principal resource supporting the EM Consolidated Business Center (EMCBC) and the EM Applied Cost Engineering (ACE) team cost estimating and analysis efforts across the country. The database has received Government Accountability Office review as supporting its recommended improvements in DOE's cost estimating process, as well as review from the DOE Office of Acquisition and Project Management (APM). Moving forward, the EMCBC has developed a Special Contract Requirement clause or 'H-Clause' to be included in all current and future EMCBC procurements identifying the process that contractors will follow to provide DOE their historical project data in a format compatible with ECAS. Changes to DOE O 413.3B implementation are also in progress to capture historical costs as part of the Critical Decision project closeout process. (authors)},
doi = {},
url = {https://www.osti.gov/biblio/22224963},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Mon Jul 01 00:00:00 EDT 2013},
month = {Mon Jul 01 00:00:00 EDT 2013}
}