This interim response action consists of the design and construction of improvements to the North Boundary Containment System. The purpose of this document is to outline the main elements developed in the preliminary design phase of the IRA. The following elements of the IRA are discussed: (1) recharge trenches; (2) well closure; (3) design flow rate; (4) existing ground water treatment process; (5) treatment system modifications; (6) additional carbon storage; (7) Building modifications; and (8) treatment plant operational improvements.
- Research Organization:
- Shell Oil Co., Denver, CO (United States)
- OSTI ID:
- 137402
- Report Number(s):
- AD-A-295224/0/XAB; TRN: 52890993
- Resource Relation:
- Other Information: PBD: Aug 1989
- Country of Publication:
- United States
- Language:
- English
Similar Records
Final decision document for the north boundary system improvements, Interim Response Action at the Rocky Mountain Arsenal
Draft final decision document for the north boundary system improvements interim response action at the Rocky Mountain Arsenal
Draft final decision document for the interim response action for the improvement of the north boundary system at Rocky Mountain Arsenal via construction of groundwater recharge trenches. Final report
Technical Report
·
Sat Apr 01 00:00:00 EST 1989
·
OSTI ID:137402
Draft final decision document for the north boundary system improvements interim response action at the Rocky Mountain Arsenal
Technical Report
·
Sat Apr 01 00:00:00 EST 1989
·
OSTI ID:137402
Draft final decision document for the interim response action for the improvement of the north boundary system at Rocky Mountain Arsenal via construction of groundwater recharge trenches. Final report
Technical Report
·
Wed Jun 01 00:00:00 EDT 1988
·
OSTI ID:137402