The Contribution of Environmental Siting and Permitting Requirements to the Cost of Energy for Oscillating Water Column Wave Energy Devices
Abstract
Responsible deployment of marine and hydrokinetic (MHK) devices in estuaries, coastal areas, and major rivers requires that biological resources and ecosystems be protected through siting and permitting (consenting) processes. Scoping appropriate deployment locations, collecting pre-installation (baseline) and post-installation data all add to the cost of developing MHK projects, and hence to the cost of energy. Under the direction of the U.S. Department of Energy, Pacific Northwest National Laboratory scientists have developed logic models that describe studies and processes for environmental siting and permitting. Each study and environmental permitting process has been assigned a cost derived from existing and proposed tidal, wave, and riverine MHK projects, as well as expert opinion of marine environmental research professionals. Cost estimates have been developed at the pilot and commercial scale. The reference model described in this document is an oscillating water column device deployed in Northern California at approximately 50 meters water depth.
- Authors:
-
- Pacific Northwest National Lab. (PNNL), Richland, WA (United States)
- Publication Date:
- Research Org.:
- Pacific Northwest National Lab. (PNNL), Richland, WA (United States)
- Sponsoring Org.:
- USDOE
- OSTI Identifier:
- 1171907
- Report Number(s):
- PNNL-22723
WC0100000
- DOE Contract Number:
- AC05-76RL01830
- Resource Type:
- Technical Report
- Country of Publication:
- United States
- Language:
- English
- Subject:
- 29 ENERGY PLANNING, POLICY, AND ECONOMY
Citation Formats
Copping, Andrea E., Geerlofs, Simon H., and Hanna, Luke A. The Contribution of Environmental Siting and Permitting Requirements to the Cost of Energy for Oscillating Water Column Wave Energy Devices. United States: N. p., 2013.
Web. doi:10.2172/1171907.
Copping, Andrea E., Geerlofs, Simon H., & Hanna, Luke A. The Contribution of Environmental Siting and Permitting Requirements to the Cost of Energy for Oscillating Water Column Wave Energy Devices. United States. https://doi.org/10.2172/1171907
Copping, Andrea E., Geerlofs, Simon H., and Hanna, Luke A. 2013.
"The Contribution of Environmental Siting and Permitting Requirements to the Cost of Energy for Oscillating Water Column Wave Energy Devices". United States. https://doi.org/10.2172/1171907. https://www.osti.gov/servlets/purl/1171907.
@article{osti_1171907,
title = {The Contribution of Environmental Siting and Permitting Requirements to the Cost of Energy for Oscillating Water Column Wave Energy Devices},
author = {Copping, Andrea E. and Geerlofs, Simon H. and Hanna, Luke A.},
abstractNote = {Responsible deployment of marine and hydrokinetic (MHK) devices in estuaries, coastal areas, and major rivers requires that biological resources and ecosystems be protected through siting and permitting (consenting) processes. Scoping appropriate deployment locations, collecting pre-installation (baseline) and post-installation data all add to the cost of developing MHK projects, and hence to the cost of energy. Under the direction of the U.S. Department of Energy, Pacific Northwest National Laboratory scientists have developed logic models that describe studies and processes for environmental siting and permitting. Each study and environmental permitting process has been assigned a cost derived from existing and proposed tidal, wave, and riverine MHK projects, as well as expert opinion of marine environmental research professionals. Cost estimates have been developed at the pilot and commercial scale. The reference model described in this document is an oscillating water column device deployed in Northern California at approximately 50 meters water depth.},
doi = {10.2172/1171907},
url = {https://www.osti.gov/biblio/1171907},
journal = {},
number = ,
volume = ,
place = {United States},
year = {Sun Sep 01 00:00:00 EDT 2013},
month = {Sun Sep 01 00:00:00 EDT 2013}
}