skip to main content
OSTI.GOV title logo U.S. Department of Energy
Office of Scientific and Technical Information

Title: Settings of the NSLS-II BSR magnets for energy interlock

Technical Report ·
DOI:https://doi.org/10.2172/1122745· OSTI ID:1122745
 [1]
  1. Brookhaven National Laboratory (BNL), Upton, NY (United States)

It was determined that for the commissioning purposes energy range of the beam reaching the NSLS-II storage ring (SR) is allowed to be 2 GeV - 3.15 GeV. The Booster to SR (BSR) bends B1 and B2 interlocked at their nominal 3 GeV settings with ± 5% window provide the required “energy filter”. Another scenario of Booster operation suggests extracting the beam from the Booster to the BSR phase 1 line (or dump line). Under these circumstances the bend B2 is turned off. An adequate shielding is planned in BSR phase one line for B1 set within the boundaries of its 2 GeV nominal setting minus 5% and its 3 GeV setting plus 5 %. The goal of this exercise is to find the proper settings of respective bends PS currents, which will realize described interlock.

Research Organization:
Brookhaven National Lab. (BNL), Upton, NY (United States)
Sponsoring Organization:
USDOE Office of Science (SC)
DOE Contract Number:
AC02-98CH10886
OSTI ID:
1122745
Report Number(s):
BNL-102623-2013-IR
Country of Publication:
United States
Language:
English