  1. Gas Utility Pipeline Tax (Texas)

    Broader source: Energy.gov [DOE]

    All gas utilities, including any entity that owns, manages, operates, leases, or controls a pipeline for the purpose of transporting natural gas in the state for sale or compensation, as well as...

  2. Natural Gas Pipeline Utilities (Maine)

    Broader source: Energy.gov [DOE]

    These regulations apply to entities seeking to develop and operate natural gas pipelines and provide construction requirements for such pipelines. The regulations describe the authority of the...

  3. EIA - Natural Gas Pipeline Network - Pipeline Capacity and Utilization

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for On-Highway4,1,50022,3,,,,6,1,9,1,50022,3,,,,6,1,Decade Year-0E (2001)gasoline353/06)Pipeline Utilization & Capacity About

  4. Sedimentation in Coal-Water Slurry Pipelining Fabio Rosso

    E-Print Network [OSTI]

    Rosso, Fabio

    Sedimentation in Coal-Water Slurry Pipelining Fabio Rosso Dipartimento di Matematica `Ulisse Dini related to the pipelin- ing of a Coal-Water Slurry. The main aspects of the problem are both with experiments finding a remarkable agreement with the available data. 1 #12;1 Slurry handling and pipeline

  5. Special Provisions Affecting Gas, Water, or Pipeline Companies (South Carolina)

    Broader source: Energy.gov [DOE]

    This legislation confers the rights and privileges of telegraph and telephone companies (S.C. Code 58-9) on pipeline and water companies, and contains several additional provisions pertaining to...

  6. Survey of state water laws affecting coal slurry pipeline development

    SciTech Connect (OSTI)

    Rogozen, M.B.

    1980-11-01T23:59:59.000Z

    This report summarizes state water laws likely to affect the development of coal slurry pipelines. It was prepared as part of a project to analyze environmental issues related to energy transportation systems. Coal slurry pipelines have been proposed as a means to expand the existing transportation system to handle the increasing coal shipments that will be required in the future. The availability of water for use in coal slurry systems in the coal-producing states is an issue of major concern.

  7. Utility solar water heating workshops

    SciTech Connect (OSTI)

    Barrett, L.B. [Barrett Consulting Associates, Inc., Colorado Springs, CO (United States)

    1992-01-01T23:59:59.000Z

    The objective of this project was to explore the problems and opportunities for utility participation with solar water heating as a DSM measure. Expected benefits from the workshops included an increased awareness and interest by utilities in solar water heating as well as greater understanding by federal research and policy officials of utility perspectives for purposes of planning and programming. Ultimately, the project could result in better information transfer, increased implementation of solar water heating programs, greater penetration of solar systems, and more effective research projects. The objective of the workshops was satisfied. Each workshop succeeded in exploring the problems and opportunities for utility participation with solar water heating as a DSM option. The participants provided a range of ideas and suggestions regarding useful next steps for utilities and NREL. According to evaluations, the participants believed the workshops were very valuable, and they returned to their utilities with new information, ideas, and commitment.

  8. Disinfection Procedure for Water Distribution Pipelines Drinking water contamination can be prevented by hydrostatic testing and disinfection of

    E-Print Network [OSTI]

    de Lijser, Peter

    Disinfection Procedure for Water Distribution Pipelines Drinking water contamination can be prevented by hydrostatic testing and disinfection of potable water distribution pipelines before connecting-921 3. Assess residual chlorine concentrations 4. Confirm that residual chlorine concentrations do

  9. Will heat from the pipeline affect groundwater and surface water? Response by Professor James Goeke The temperature of a pipeline buried 4 feet would

    E-Print Network [OSTI]

    Nebraska-Lincoln, University of

    of the pipeline as a way to check for leaks? Do you have any specific concerns regarding oil or natural gas1 Water Will heat from the pipeline affect groundwater and surface water? Response by Professor James Goeke ­ The temperature of a pipeline buried 4 feet would probably affect surface water

  10. Water Loss Test Results for the West Main Pipeline United Irrigation District of Hidalgo County 

    E-Print Network [OSTI]

    Leigh, E.; Fipps, G.

    2008-01-01T23:59:59.000Z

    TR-322 2008 Water Loss Test Results for the West Main Pipeline United Irrigation District of Hidalgo County Eric Leigh Texas AgriLife Extension Associate, Biological and Agricultural Engineering, College... Station Guy Fipps Texas AgriLife Extension Professor and Extension Agricultural Engineer, Biological and Agricultural Engineering, College Station March 20, 2007 Water Loss Test Results for the West Main Pipeline United Irrigation...

  11. Water Loss Test Results for the West Main Pipeline United Irrigation District of Hidalgo County

    E-Print Network [OSTI]

    Leigh, E.; Fipps, G.

    TR-322 2008 Water Loss Test Results for the West Main Pipeline United Irrigation District of Hidalgo County Eric Leigh Texas AgriLife Extension Associate, Biological and Agricultural Engineering, College... Station Guy Fipps Texas AgriLife Extension Professor and Extension Agricultural Engineer, Biological and Agricultural Engineering, College Station March 20, 2007 Water Loss Test Results for the West Main Pipeline United Irrigation...

  12. Freight pipelines

    SciTech Connect (OSTI)

    Liu, H. (University of Missouri, Columbia, MO (US)); Round, G.F. (McMaster University (CA))

    1989-01-01T23:59:59.000Z

    This book presents papers on slurry pipelines, pneumatic pipelines, capsule pipelines, pipeline education, and pipeline research.

  13. Clark Public Utilities- Solar Water Heater Rebate

    Broader source: Energy.gov [DOE]

    Clark Public Utilities offers a rebate of $500 to customers who install a solar water heating system. Customers must own the residence or business where the solar water heating system is installed...

  14. Gas Pipeline Safety (Indiana)

    Broader source: Energy.gov [DOE]

    This section establishes the Pipeline Safety Division within the Utility Regulatory Commission to administer federal pipeline safety standards and establish minimum state safety standards for...

  15. Pipeline Safety (South Dakota)

    Broader source: Energy.gov [DOE]

    The South Dakota Pipeline Safety Program, administered by the Public Utilities Commission, is responsible for regulating hazardous gas intrastate pipelines. Relevant legislation and regulations...

  16. Pipeline Safety (Pennsylvania)

    Broader source: Energy.gov [DOE]

    The Pennsylvania legislature has empowered the Public Utility Commission to direct and enforce safety standards for pipeline facilities and to regulate safety practices of certificated utilities...

  17. Fort Pierce Utilities Authority- Solar Water Heating Rebate (Florida)

    Broader source: Energy.gov [DOE]

    '''''Fort Pierce Utilities Authority has suspended the Solar Water Heating rebate program until 2013. Contact the utility for more information on these offerings.'''''

  18. Pipeline Construction Guidelines (Indiana)

    Broader source: Energy.gov [DOE]

    The Division of Pipeline Safety of the Indiana Utility Regulatory Commission regulates the construction of any segment of an interstate pipeline on privately owned land in Indiana. The division has...

  19. Orlando Utilities Commission- Residential Solar Water Heater Rebate Program (Florida)

    Broader source: Energy.gov [DOE]

    The Orlando Utilities Commission (OUC) offers residential electric customers a point-of-sale rebate of $1,000 for new solar water heating systems.

  20. Ocala Utility Services- Solar Hot Water Heating Rebate Program

    Broader source: Energy.gov [DOE]

    The Solar Water Heater Rebate Program is offered to residential retail electric customers by the City of Ocala Utility Services. Interested customers must complete an application and receive...

  1. Cedarburg Light and Water Utility- Commercial Energy Efficiency Rebate Program

    Broader source: Energy.gov [DOE]

    Cedarburg Light and Water Utility provides incentives for commercial, industrial and agricultural customers to increase the energy efficiency of eligible facilities. Upon request, Cedarburg Light...

  2. Opportunities for utility involvement with solar domestic hot water

    SciTech Connect (OSTI)

    Carlisle, N.; Christensen, C. (National Renewable Energy Lab., Golden, CO (United States)); Barrett, L. (Barrett Consulting Associates, Inc., Colorado Springs, CO (United States))

    1992-05-01T23:59:59.000Z

    Solar water heating is one of a number of options that can be considered under utility demand-side management (DSM) programs. Utilities perceive a range of potential benefits for solar water heating in terms of customer service, energy conservation, load management, environmental enhancement, and public relations. The solar industry may benefit from utility marketing efforts, economies of scale, added credibility, financing options, and long-term maintenance arrangements. This paper covers three topics: (1) the energy and demand impacts of solar water heating on utility load profiles based on the results of four studies in the literature, (2) the results of workshops sponsored by the National Renewable Energy Laboratory (NREL) to identify key issues faced by utilities in considering residential solar water heating as a DSM option, (3) several current or planned utility programs to promote solar water heating. 7 refs.

  3. Marshall Municipal Utilities- Solar Thermal Water Heater Rebate Program

    Broader source: Energy.gov [DOE]

    Marshall Municipal Utilities (MMU) offers residential customers rebates for installing a ENERGY STAR Solar Thermal Water Heater. Rebates are based on the size of the system; MMU offers $20 per...

  4. Lake Worth Utilities- Residential Solar Water Heating Rebate Program

    Broader source: Energy.gov [DOE]

    The City of Lake Worth Utilities (CLWU), in conjunction with Florida Municipal Power Agency, offers rebates to customers who purchase and install a solar water heating system for residential use. A...

  5. City of Palo Alto Utilities- Solar Water Heating Program

    Broader source: Energy.gov [DOE]

    City of Palo Alto Utilities is offering incentives for their residential, commercial and industrial customers to install solar water heating systems on their homes and facilities with a goal of 1...

  6. New Braunfels Utilities- Residential Solar Water Heater Rebate Program

    Broader source: Energy.gov [DOE]

    New Braunfels Utilities offers a rebate for residential customers who purchase and install solar water heating systems on eligible homes. A rebate of the equivalent of $0.265 per kWh is available...

  7. Rock Hill Utilities- Water Heater and Heat Pump Rebate Program

    Broader source: Energy.gov [DOE]

    Through the SmartChoice program, Rock Hill Utilities offers rebates for water heater and heat pump replacements. Information on financing for heat pumps can also be found on the web site listed...

  8. Water Loss Test Results for the Pipeline Units: I-19/I-18, I-7A, and I-22 Hidalgo County Irrigation District No. 2 

    E-Print Network [OSTI]

    Fipps, G.; Leigh, E.

    2008-01-01T23:59:59.000Z

    TR-330 2008 Water Loss Test Results for the Pipeline Units: I-19/I-18, I-7A and I-22 Hidalgo County Irrigation District No. 2 By: Eric Leigh, Extension Associate, Biological and Agricultural Engineering... Guy Fipps, Professor and Extension Agricultural Engineer, Biological and Agricultural Engineering Texas Water Resources Institute Technical Report October 2008 Water Loss Test Results for the Pipeline Units: I-19/I-18, I-7A, and I...

  9. Water Loss Test Results for the Pipeline Units: I-19/I-18, I-7A, and I-22 Hidalgo County Irrigation District No. 2

    E-Print Network [OSTI]

    Fipps, G.; Leigh, E.

    TR-330 2008 Water Loss Test Results for the Pipeline Units: I-19/I-18, I-7A and I-22 Hidalgo County Irrigation District No. 2 By: Eric Leigh, Extension Associate, Biological and Agricultural Engineering... Guy Fipps, Professor and Extension Agricultural Engineer, Biological and Agricultural Engineering Texas Water Resources Institute Technical Report October 2008 Water Loss Test Results for the Pipeline Units: I-19/I-18, I-7A, and I...

  10. Soil water utilization by herbaceous species of the southern Great Plains: evidence from isotopically labeled water

    E-Print Network [OSTI]

    Yoder, Carolyn Kay

    1993-01-01T23:59:59.000Z

    Understanding spatial and temporal patterns of soil water utilization by plants has broad implications for physiological, ecological, and hydrological processes. Water labeled with the stable isotopes deuterium ('H) or oxygen-18 ("'O) was injected...

  11. Gas Pipeline Securities (Indiana)

    Broader source: Energy.gov [DOE]

    This statute establishes that entities engaged in the transmission of gas by pipelines are not required to obtain the consent of the Utility Regulatory Commission for issuance of stocks,...

  12. 50-Plus Ways to Be Water Smart 1. If your local water utility offers water-saving incentives or in-home water audits, take advantage

    E-Print Network [OSTI]

    50-Plus Ways to Be Water Smart BEHAVIORS 1. If your local water utility offers water-saving incentives or in-home water audits, take advantage of these programs. 2. Don't let water run while brushing

  13. Utilization of Heat Pump Water Heaters for Load Management

    SciTech Connect (OSTI)

    Boudreaux, Philip R [ORNL; Jackson, Roderick K [ORNL; Munk, Jeffrey D [ORNL; Gehl, Anthony C [ORNL; Lyne, Christopher T [ORNL

    2014-01-01T23:59:59.000Z

    The Energy Conservation Standards for Residential Water Heaters require residential electric storage water heaters with volumes larger than 55 gallons to have an energy factor greater than 2.0 after April 2015. While this standard will significantly increase the energy efficiency of water heaters, large electric storage water heaters that do not use heat pump technologies may no longer be available. Since utilities utilize conventional large-volume electric storage water heaters for thermal storage in demand response programs, there is a concern that the amended standard will significantly limit demand response capacity. To this end, Oak Ridge National Laboratory partnered with the Tennessee Valley Authority to investigate the load management capability of heat pump water heaters that meet or exceed the forthcoming water heater standard. Energy consumption reduction during peak periods was successfully demonstrated, while still meeting other performance criteria. However, to minimize energy consumption, it is important to design load management strategies that consider the home s hourly hot water demand so that the homeowner has sufficient hot water.

  14. Introduction Water conservation is becoming increasingly important to many utilities worldwide. Not only are water

    E-Print Network [OSTI]

    Mangel, Marc

    , to conserve. Utilities often use price structure and other demand side management tools to send a conservation on water demand. Ward (2012) discusses the management of residential water demand. Through survey data for managing residential consumption. Klaiber et al. (2010) estimate price elasticity of water demand using

  15. Pipelines (Minnesota)

    Broader source: Energy.gov [DOE]

    This section regulates pipelines that are used to carry natural or synthetic gas at a pressure of more than 90 pounds per square inch, along with pipelines used to carry petroleum products and coal...

  16. Virginia Natural Gas's Hampton Roads Pipeline Crossing

    Broader source: Energy.gov [DOE]

    Presentation—given at the Federal Utility Partnership Working Group (FUPWG) Fall 2008 meeting—covers Virginia Natural Gas's (VNG's) pipeline project at Hampton Roads Crossing (HRX).

  17. Non-intrusive water utility monitoring and free-space load monitoring

    E-Print Network [OSTI]

    Neuman, Sabrina M

    2011-01-01T23:59:59.000Z

    This work presents a non-intrusive, single-point sensing scheme to monitor the water usage for various loads on a water utility pipe network through the vibration of a pipe near the water intake source. Experiments with ...

  18. Interstate Natural Gas Pipelines (Iowa)

    Broader source: Energy.gov [DOE]

    This statute confers upon the Iowa Utilities Board the authority to act as an agent of the federal government in determining pipeline company compliance with federal standards within the boundaries...

  19. Sensor Acquisition for Water Utilities: A Survey and Technology List

    SciTech Connect (OSTI)

    Alai, M; Glascoe, L; Love, A; Johnson, M; Einfeld, W

    2005-03-07T23:59:59.000Z

    The early detection of the deliberate biological and chemical contamination of water distribution systems is a necessary capability for securing the nation's water supply. Current and emerging early-detection technology capabilities and shortcomings need to be identified and assessed to provide government agencies and water utilities with an improved methodology for assessing the value of installing these technologies. The Department of Homeland Security (DHS) has tasked a multi-laboratory team to evaluate current and future needs to protect the nation's water distribution infrastructure by supporting an objective evaluation of current and new technologies. The primary deliverables from this Operational Technology Demonstration (OTD) are the following: (1) establishment of an advisory board for review and approval of testing protocols, technology acquisition processes and recommendations for technology test and evaluation in laboratory and field settings; (2) development of a technology acquisition process; (3) creation of laboratory and field testing and evaluation capability; and (4) testing of candidate technologies for insertion into a water early warning system. The initial phase of this study involves the development of two separate but complementary strategies to be reviewed by the advisory board: (1) a technology acquisition strategy, and (2) a technology evaluation strategy. Lawrence Livermore National Laboratory and Sandia National Laboratories are tasked with the first strategy, while Los Alamos, Pacific Northwest, and Oak Ridge National Laboratories are tasked with the second strategy. The first goal of the acquisition strategy is the development of a technology survey process that includes a review of previous sensor surveys and current test programs and then the development of a method to solicit and select existing and emerging sensor technologies for evaluation and testing. In this paper we discuss a survey of previous efforts by governmental agencies and private companies with the aim of facilitating a water sensor technology acquisition procedure. We provide a survey of previous sensor studies with regard to the use of Early Warning Systems (EWS) including earlier surveys, testing programs, and response studies. In the project we extend this earlier work by developing a list of important sensor specifications that are then used to help assemble a sensor selection criteria. A list of sensor technologies with their specifications is appended to this document. This list will assist the second goal of the project which is a recommendation of candidate technologies for laboratory and field testing.

  20. Fort Pierce Utilities Authority- Solar Water Heating Rebate

    Broader source: Energy.gov [DOE]

    Note: Fort Pierce Utilities Authority has completed its rebate program for 2015. Check the website for updates.

  1. Cathodic protection retrofit of an offshore pipeline

    SciTech Connect (OSTI)

    Winters, R.H.; Holk, A.C. [Tenneco Energy, Houston, TX (United States)

    1997-09-01T23:59:59.000Z

    Cathodic protection (CP) anodes and corrosion coating on two offshore pipelines were damaged during deep water installation. In-situ methods for deep-water inspection and repair of the pipelines` CP and coating systems were developed and used. High-pressure natural gas Pipeline. A design was 5.6 miles of 8.625 in. OD by 0.406 in. W.T. API SL, Grade X-42, seamless line pipe. Pipeline B design was 0.3 miles of similar specification pipe. Both pipelines were mill-coated with 14 mil of fusion-bonded epoxy (FBE) corrosion coating. Girth welds were field-coated with FBE.

  2. New Advanced System Utilizes Industrial Waste Heat to Power Water...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    is crucial to ensuring their status as global competitors. Currently, most industries treat water to meet standards for direct discharge to surface water. The process includes a...

  3. New Braunfels Utilities- Energy Efficiency and Water Conservation Rebate Programs

    Broader source: Energy.gov [DOE]

    New Braunfels Utilities offer a variety of programs encouraging its customers to make their homes more energy efficiency. Rebates are available for washing machines, air conditioners, heat pumps,...

  4. Pipeline Setback Ordinance (Minnesota)

    Broader source: Energy.gov [DOE]

    This statute establishes the Office of Pipeline Safety to regulate pipelines in Minnesota. Among other duties, the office is responsible for implementing a Model Pipeline Setback Ordinance.

  5. TVA Partner Utilities- Energy Right Water Heater Program

    Broader source: Energy.gov [DOE]

    The TVA energy right Water Heater Plan promotes the installation of high efficiency water heaters in homes and small businesses. TVA provides a $50 incentive to local power companies for each...

  6. TVA Partner Utilities- Energy Right Water Heater Program

    Broader source: Energy.gov [DOE]

    The Tennessee Valley Authority (TVA) energy right Water Heater Plan promotes the installation of high efficiency water heaters in homes and small businesses. TVA provides a $50 incentive to local...

  7. TVA Partner Utilities- Energy Right' Water Heater Program

    Broader source: Energy.gov [DOE]

    The TVA energy right Water Heater Plan promotes the installation of high efficiency water heaters in homes and small businesses. TVA provides a $50 incentive to local power companies for each...

  8. Gainesville Regional Utilities- Solar Water Heating Rebate Program

    Broader source: Energy.gov [DOE]

    The Gainesville Regional Utilities (GRU) Solar Rebate Program, established in early 1997 as part of GRU's demand-side management initiatives, provides rebates of $500 to residential customers of...

  9. Pipeline ADC Design Methodology

    E-Print Network [OSTI]

    Zhao, Hui

    2012-01-01T23:59:59.000Z

    Scaling vs. R. Figure 4.8 Pipeline ADC Structures. Figure2.4 A Pipelined ADC. Figure 3.1 Pipeline ADC Transfer Curve.Modes (b) data latency in pipeline ADC Figure 3.3 Detailed

  10. Coal slurry pipeline based midwest fuel hub

    SciTech Connect (OSTI)

    Huettenhain, H. [Bechtel Technology & Consulting San Francisco, CA (United States)

    1998-12-31T23:59:59.000Z

    Low sulfur Powder River Basin (PRB) coal is a sought after fuel to comply with the year 2000 emission regulation for utility boilers. PRB coal is presently not competitive East of the Mississippi mainly because of railroad switching requirements and boiler designs not compatible with the PRB fuel characteristics. The use of the Lakes for transportation is an exception. The Lakes shipping lanes however, are only open part of the year. It is proposed to construct a coal slurry pipeline from the center of Wyoming coalfields to a hub near Detroit with access to low cost waste energy from power generation stations. The coal slurry pipeline will transport up to 25 million tons per year of fine PRB coal which has been removed from the conventionally transported coal, namely coal transported by rail. The rail delivered coal will have less dust. The system fits the DOE Vision 21 concept to mine and utilize coal in highly efficient systems and with the least environmental impact. The PRB coal is of subbituminous rank and not directly compatible with the boilers in Michigan/Indiana/Ohio area, which are designed to burn bituminous coal. Upgrading of the PRB coal using the hydrothermal slurry upgrading process can transform the PRB coal into a higher Btu content fuel by removing a large portion of the inherent moisture. Such upgraded PRB coal has proven an excellent reactive fuel when burned conventionally as PC fuel, or even when burned in slurry form as Coal Water Fuel (CWF). The cost of the process can be recovered when the process is combined with a coal slurry pipeline transport system. The result is an upgraded competitive fuel or fuels, which can be used for co-firing or re-burning applications to reduce SO{sub 2} and NOx emissions of utility boilers. The fuels can be powdered for direct fuel injection into boilers or blast furnaces as well as CWF. Depending on the stability of the upgraded PRB coal, the pipeline product could also be dewatered and prepared for export. This paper describes the concept and preliminary cost information. It also reports on reactions of the industries, which could be involved in the complex system, namely, coal mining companies, railroads, pipeline operators, fuel suppliers, and utilities.

  11. Theoretical Study of Steam Condensation Induced Water Hammer Phenomena in Horizontal Pipeline

    E-Print Network [OSTI]

    Barna, Imre Ferenc

    2014-01-01T23:59:59.000Z

    We investigate steam condensation induced water hammer (CIWH) phenomena and present new theoretical results. We use the WAHA3 model based on two-phase flow six first-order partial differential equations that present one dimensional, surface averaged mass, momentum and energy balances. A second order accurate high-resolution shock-capturing numerical scheme was applied with different kind of limiters in the numerical calculations. The applied two-fluid model shows some similarities to Relap5 which is widely used in the nuclear industry to simulate nuclear power plant accidents. This model was validated with different CIWH experiments which were performed in the PMK-2 facility, which is a full-pressure thermo-hydraulic model of the nuclear power plant of VVER-440/312 type in the Energy Research Center of the Hungarian Academy of Sciences in Budapest and in the Rosa facility in Japan. In our recent study we show the first part of a planned large database which will give us the upper and lower flooding mass flow ...

  12. Analysis of strategies for improving uranium utilization in pressurized water reactors

    E-Print Network [OSTI]

    Sefcik, Joseph A.

    1981-01-01T23:59:59.000Z

    Systematic procedures have been devised and applied to evaluate core design and fuel management strategies for improving uranium utilization in Pressurized Water Reactors operated on a once-through fuel cycle. A principal ...

  13. City of Tallahassee Utilities- Solar Water Heating Rebate

    Broader source: Energy.gov [DOE]

    The homeowner must allow the City of Tallahassee to conduct an energy audit on the home in order to make a preliminary assessment of sun exposure and to provide program guidance. All solar water...

  14. Cedarburg Light & Water Utility- Residential Energy Efficiency Rebate Program

    Broader source: Energy.gov [DOE]

    Cedarburg Light & Water (CL&W) offers rebates to residential customers for a variety of energy-efficient equipment and upgrades.  Through Wisconsin Focus on Energy, CL&W provides...

  15. Orlando Utilities Commission- Residential Solar Water Heater Rebate Program

    Broader source: Energy.gov [DOE]

    Through a partnership with the Orlando Federal Credit Union (OFCU), OUC also offers a Residential Solar Loan Program to finance the solar hot water system. Customers who choose to finance through...

  16. City of Water Valley, Mississippi (Utility Company) | Open Energy

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand JumpConceptual Model, clickInformation Smyrna Beach,Stuart, Iowa (UtilityCityInformation City

  17. Driving Water and Wastewater Utilities to More Sustainable Energy Management 

    E-Print Network [OSTI]

    Ferrel, L.; Liner, B.

    2013-01-01T23:59:59.000Z

    conservation and focus on overall energy management. This roadmap leverages the framework developed in the electric power sector to move to smart grid technology: the smart grid maturity model (SGMM). The basis of this material originated at a workshop of water...

  18. Final joint environmental assessment for the construction and routine operation of a 12-kilovolt (KV) overhead powerline right-of-way, and formal authorization for a 10-inch and 8-inch fresh water pipeline right-of-way, Naval Petroleum Reserve No. 1, Kern County, California

    SciTech Connect (OSTI)

    Not Available

    1994-10-01T23:59:59.000Z

    The purpose and need of the proposed action, which is the installation of an overhead powerline extension from an Naval Petroleum Reserve No. 1 (NPR-1) power source to the WKWD Station A, is to significantly reduce NPR-1`s overall utility costs. While the proposed action is independently justified on its own merits and is not tied to the proposed NPR-1 Cogeneration Facility, the proposed action would enable DOE to tie the NPR-1 fresh water pumps at Station A into the existing NPR-1 electrical distribution system. With the completion of the cogeneration facility in late 1994 or early 1995, the proposed action would save additional utility costs. This report deals with the environmental impacts of the construction of the powerline and the water pipeline. In addition, information is given about property rights and attaining permission to cross the property of proposed affected owners.

  19. Enter the Post-Doc: The Untapped Sourcing Pipeline

    SciTech Connect (OSTI)

    Boscow, Ryan B.

    2011-07-30T23:59:59.000Z

    This article addresses the potential formulation and utilization of an industry-based Post-Doc program in order to create workforce candidate pipelines with targeted universities.

  20. Natural gas pipeline technology overview.

    SciTech Connect (OSTI)

    Folga, S. M.; Decision and Information Sciences

    2007-11-01T23:59:59.000Z

    The United States relies on natural gas for one-quarter of its energy needs. In 2001 alone, the nation consumed 21.5 trillion cubic feet of natural gas. A large portion of natural gas pipeline capacity within the United States is directed from major production areas in Texas and Louisiana, Wyoming, and other states to markets in the western, eastern, and midwestern regions of the country. In the past 10 years, increasing levels of gas from Canada have also been brought into these markets (EIA 2007). The United States has several major natural gas production basins and an extensive natural gas pipeline network, with almost 95% of U.S. natural gas imports coming from Canada. At present, the gas pipeline infrastructure is more developed between Canada and the United States than between Mexico and the United States. Gas flows from Canada to the United States through several major pipelines feeding U.S. markets in the Midwest, Northeast, Pacific Northwest, and California. Some key examples are the Alliance Pipeline, the Northern Border Pipeline, the Maritimes & Northeast Pipeline, the TransCanada Pipeline System, and Westcoast Energy pipelines. Major connections join Texas and northeastern Mexico, with additional connections to Arizona and between California and Baja California, Mexico (INGAA 2007). Of the natural gas consumed in the United States, 85% is produced domestically. Figure 1.1-1 shows the complex North American natural gas network. The pipeline transmission system--the 'interstate highway' for natural gas--consists of 180,000 miles of high-strength steel pipe varying in diameter, normally between 30 and 36 inches in diameter. The primary function of the transmission pipeline company is to move huge amounts of natural gas thousands of miles from producing regions to local natural gas utility delivery points. These delivery points, called 'city gate stations', are usually owned by distribution companies, although some are owned by transmission companies. Compressor stations at required distances boost the pressure that is lost through friction as the gas moves through the steel pipes (EPA 2000). The natural gas system is generally described in terms of production, processing and purification, transmission and storage, and distribution (NaturalGas.org 2004b). Figure 1.1-2 shows a schematic of the system through transmission. This report focuses on the transmission pipeline, compressor stations, and city gates.

  1. Phase I: the pipeline-gas demonstration plant. Demonstration plant engineering and design. Volume 18. Plant Section 2700 - Waste Water Treatment

    SciTech Connect (OSTI)

    none,

    1981-05-01T23:59:59.000Z

    Contract No. EF-77-C-01-2542 between Conoco Inc. and the US Department of Energy provides for the design, construction, and operation of a demonstration plant capable of processing bituminous caking coals into clean pipeline quality gas. The project is currently in the design phase (Phase I). This phase is scheduled to be completed in June 1981. One of the major efforts of Phase I is the process and project engineering design of the Demonstration Plant. The design has been completed and is being reported in 24 volumes. This is Volume 18 which reports the design of Plant Section 2700 - Waste Water Treatment. The objective of the Waste Water Treatment system is to collect and treat all plant liquid effluent streams. The system is designed to permit recycle and reuse of the treated waste water. Plant Section 2700 is composed of primary, secondary, and tertiary waste water treatment methods plus an evaporation system which eliminates liquid discharge from the plant. The Waste Water Treatment Section is designed to produce 130 pounds per hour of sludge that is buried in a landfill on the plant site. The evaporated water is condensed and provides a portion of the make-up water to Plant Section 2400 - Cooling Water.

  2. A cash-flow economic model for analyzing utility/ESCO solar hot water programs

    SciTech Connect (OSTI)

    Bircher, C. [ENSTAR, De Pere, WI (United States); DeLaune, J.L. [Wisconsin Public Service Corp., Green Bay, WI (United States); Lyons, C.R. [Energy Alliance Group, Boston, MA (United States)

    1996-11-01T23:59:59.000Z

    Wisconsin Public Service Corporation (WPSC), in partnership with Energy Alliance Group (EAG), has developed a robust cash-flow economic model to analyze an energy service company (ESCO) approach to utility solar water heating programs. This paper describes the ESCO approach and its potential to increase penetration of solar water heating. The economic model is presented, and its use in designing WPSC`s Solar-Wise Water Heating Service program is described. The model`s results for WPSC are positive, indicating that an ESCO approach has strong potential. A feasibility study of ESCO solar water heating programs for a varied sample of other US utilities was also conducted using the model, and the results are summarized. Sensitivity analyses from the study reveal that the three key drivers of ESCO solar water heating success are electric rate, length of the service agreement, and the amount of the customer`s payment for the service.

  3. Dispute Resolution Process Utility Owner

    E-Print Network [OSTI]

    Minnesota, University of

    State One Call (GSOC) for "Design Call" Provide "as-builts", marked plans or field locates MnDOT Utility? Underground Utility? Contact Minnesota Office of Pipeline Safety Minnesota Office of Pipeline Safety Step 1 - Utility Identification for Construction Investigate and take appropriate action up to and including

  4. Pipeline Safety (Maryland)

    Broader source: Energy.gov [DOE]

    The Public Service Commission has the authority enact regulations pertaining to pipeline safety. These regulations address pipeline monitoring, inspections, enforcement, and penalties.

  5. Intrastate Pipeline Safety (Minnesota)

    Broader source: Energy.gov [DOE]

    These regulations provide standards for gas and liquid pipeline maintenance and operating procedures, per the Federal Hazardous Liquid and Natural Gas Pipeline Safety Acts, and give the...

  6. Pipeline Operations Program (Louisiana)

    Broader source: Energy.gov [DOE]

    The Pipeline Operations Program regulates the construction, acquisition, abandonment and interconnection of natural gas pipelines, as well as, the transportation and use of natural gas supplies.

  7. Economic and Financial Costs of Saving Water and Energy: Preliminary Analysis for Hidalgo County Irrigation District No. 2 (San Juan) – Replacement of Pipeline Units I-7A, I-18, and I-22 

    E-Print Network [OSTI]

    Sturdivant, Allen W.; Rister, M. Edward; Lacewell, Ronald D.

    2007-01-01T23:59:59.000Z

    of replacing aged mortar-joint pipe in pipeline units I-7A, I-18, and I-22 with new rubber-gasketed, reinforced concrete pipe. Both nominal and real estimates of water and energy savings and expected economic and financial costs of those savings are identified...

  8. UTILITIES PROBLEMS AND FAILURES Electrical or plumbing failure/Flooding/Water leak/Natural gas

    E-Print Network [OSTI]

    Fernandez, Eduardo

    UTILITIES PROBLEMS AND FAILURES Electrical or plumbing failure/Flooding/Water leak/Natural gas for electrical shock. NOTIFY University Police. What should I do if I smell natural or propane gas? LEAVE/Repair line, 7-6333, or CALL the Campus University Police or Security at (561) 297-3500 or 911

  9. UTILITIES PROBLEMS AND FAILURES ELECTRICAL OR PLUMBING FAILURE/FLOODING/WATER LEAK

    E-Print Network [OSTI]

    Fernandez, Eduardo

    UTILITIES PROBLEMS AND FAILURES ELECTRICAL OR PLUMBING FAILURE/FLOODING/WATER LEAK NATURAL GAS - F 8a - 5p HBOI@FAU Security (772) 216-1124 Afterhours, Weekends or Holidays What should I do Police 911. · NOTIFY Building Safety personnel when possible. What should I do if I smell natural

  10. UTILITIES PROBLEMS AND FAILURES Electrical or plumbing failure/Flooding/Water leak/Natural gas or

    E-Print Network [OSTI]

    Fernandez, Eduardo

    UTILITIES PROBLEMS AND FAILURES Electrical or plumbing failure/Flooding/Water leak/Natural gas Physical Plant (772) 242-2246 M - F 8a - 5p (954) 762-5040 HBOI@FAU Security (772) 216-1124 Afterhours University Police. NOTIFY Building Safety personnel when possible. What should I do if I smell natural

  11. Water use and supply concerns for utility-scale solar projects in the Southwestern United States.

    SciTech Connect (OSTI)

    Klise, Geoffrey Taylor; Tidwell, Vincent Carroll; Reno, Marissa Devan; Moreland, Barbara D.; Zemlick, Katie M.; Macknick, Jordan [National Renewable Energy Laboratory Golden, CO] [National Renewable Energy Laboratory Golden, CO

    2013-07-01T23:59:59.000Z

    As large utility-scale solar photovoltaic (PV) and concentrating solar power (CSP) facilities are currently being built and planned for locations in the U.S. with the greatest solar resource potential, an understanding of water use for construction and operations is needed as siting tends to target locations with low natural rainfall and where most existing freshwater is already appropriated. Using methods outlined by the Bureau of Land Management (BLM) to determine water used in designated solar energy zones (SEZs) for construction and operations & maintenance, an estimate of water used over the lifetime at the solar power plant is determined and applied to each watershed in six Southwestern states. Results indicate that that PV systems overall use little water, though construction usage is high compared to O&M water use over the lifetime of the facility. Also noted is a transition being made from wet cooled to dry cooled CSP facilities that will significantly reduce operational water use at these facilities. Using these water use factors, estimates of future water demand for current and planned solar development was made. In efforts to determine where water could be a limiting factor in solar energy development, water availability, cost, and projected future competing demands were mapped for the six Southwestern states. Ten watersheds, 9 in California, and one in New Mexico were identified as being of particular concern because of limited water availability.

  12. Self lubrication of bitumen froth in pipelines

    SciTech Connect (OSTI)

    Joseph, D.D. [Univ. of Minnesota, Minneapolis, MN (United States)

    1997-12-31T23:59:59.000Z

    In this paper I will review the main properties of water lubricated pipelines and explain some new features which have emerged from studies of self-lubrication of Syncrudes` bitumen froth. When heavy oils are lubricated with water, the water and oil are continuously injected into a pipeline and the water is stable when in a lubricating sheath around the oil core. In the case of bitumen froth obtained from the Alberta tar sands, the water is dispersed in the bitumen and it is liberated at the wall under shear; water injection is not necessary because the froth is self-lubricating.

  13. Hydrogen Embrittlement of Pipeline Steels: Causes and Remediation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Barriers: Hydrogen embrittlement of pipelines and remediation (mixing with water vapor?) hpwgwembrittlementsteelssofronis.pdf More Documents & Publications Webinar: I2CNER: An...

  14. Cathodic protection retrofit of an offshore pipeline

    SciTech Connect (OSTI)

    Winters, R.H.; Holk, A.C. [Tenneco Energy, Houston, TX (United States)

    1997-09-01T23:59:59.000Z

    The cathodic protection anodes and corrosion coating on two 8-inch (203.2 mm) outside diameter (O.D.) offshore pipelines were damaged during deep water ({minus}380 feet, {minus}116 m) installation. In-situ methods for deep water inspection and repair of the pipelines` cathodic protection and coating systems were developed and performed. Methods are described in which underwater anode retrofits were performed and friction welding technology was used to re-attach anode leads. Standard procedures for underwater pipeline coating repair and remediation of damaged line pipe are provided.

  15. Sensor Acquisition for Water Utilities: Survey, Down Selection Process, and Technology List

    SciTech Connect (OSTI)

    Alai, M; Glascoe, L; Love, A; Johnson, M; Einfeld, W

    2005-06-29T23:59:59.000Z

    The early detection of the biological and chemical contamination of water distribution systems is a necessary capability for securing the nation's water supply. Current and emerging early-detection technology capabilities and shortcomings need to be identified and assessed to provide government agencies and water utilities with an improved methodology for assessing the value of installing these technologies. The Department of Homeland Security (DHS) has tasked a multi-laboratory team to evaluate current and future needs to protect the nation's water distribution infrastructure by supporting an objective evaluation of current and new technologies. The LLNL deliverable from this Operational Technology Demonstration (OTD) was to assist the development of a technology acquisition process for a water distribution early warning system. The technology survey includes a review of previous sensor surveys and current test programs and a compiled database of relevant technologies. In the survey paper we discuss previous efforts by governmental agencies, research organizations, and private companies. We provide a survey of previous sensor studies with regard to the use of Early Warning Systems (EWS) that includes earlier surveys, testing programs, and response studies. The list of sensor technologies was ultimately developed to assist in the recommendation of candidate technologies for laboratory and field testing. A set of recommendations for future sensor selection efforts has been appended to this document, as has a down selection example for a hypothetical water utility.

  16. Components in the Pipeline

    SciTech Connect (OSTI)

    Gorton, Ian; Wynne, Adam S.; Liu, Yan (Jenny); Yin, Jian

    2011-02-24T23:59:59.000Z

    Scientists commonly describe their data processing systems metaphorically as software pipelines. These pipelines input one or more data sources and apply a sequence of processing steps to transform the data and create useful results. While conceptually simple, pipelines often adopt complex topologies and must meet stringent quality of service requirements that place stress on the software infrastructure used to construct the pipeline. In this paper we describe the MeDICi Integration Framework, which is a component-based framework for constructing complex software pipelines. The framework supports composing pipelines from distributed heterogeneous software components and provides mechanisms for controlling qualities of service to meet demanding performance, reliability and communication requirements.

  17. Environmental Assessment for the Strategic Petroleum Reserve West Hackberry Facility Raw Water Intake Pipeline Replacement Cameron and Calcasieu Parishes, Louisiana

    SciTech Connect (OSTI)

    N /A

    2004-08-31T23:59:59.000Z

    The proposed action and three alternatives, including a No Build alternative, were evaluated along the existing RWIPL alignment to accommodate the placement of the proposed RWIPL. Construction feasibility, reasonableness and potential environmental impacts were considered during the evaluation of the four actions (and action alternatives) for the proposed RWIPL activities. Reasonable actions were identified as those actions which were considered to be supported by common sense and sound technical principles. Feasible actions were those actions which were considered to be capable of being accomplished, practicable and non-excessive in terms of cost. The evaluation process considered the following design specifications, which were determined to be important to the feasibility of the overall project. The proposed RWIPL replacement project must therefore: (1) Comply with the existing design basis and criteria, (2) Maintain continuity of operation of the facility during construction, (3)Provide the required service life, (4) Be cost effective, (5)Improve the operation and maintenance of the pipeline, and (6) Maintain minimal environmental impact while meeting the performance requirements. Sizing of the pipe, piping construction materials, construction method (e.g., open-cut trench, directional drilling, etc.) and the acquisition of new Right-of-Way (ROW) were additionally evaluated in the preliminary alternative identification, selection and screening process.

  18. WRI 50: Strategies for Cooling Electric Generating Facilities Utilizing Mine Water

    SciTech Connect (OSTI)

    Joseph J. Donovan; Brenden Duffy; Bruce R. Leavitt; James Stiles; Tamara Vandivort; Paul Ziemkiewicz

    2004-11-01T23:59:59.000Z

    Power generation and water consumption are inextricably linked. Because of this relationship DOE/NETL has funded a competitive research and development initiative to address this relationship. This report is part of that initiative and is in response to DOE/NETL solicitation DE-PS26-03NT41719-0. Thermal electric power generation requires large volumes of water to cool spent steam at the end of the turbine cycle. The required volumes are such that new plant siting is increasingly dependent on the availability of cooling circuit water. Even in the eastern U.S., large rivers such as the Monongahela may no longer be able to support additional, large power stations due to subscription of flow to existing plants, industrial, municipal and navigational requirements. Earlier studies conducted by West Virginia University (WV 132, WV 173 phase I, WV 173 Phase II, WV 173 Phase III, and WV 173 Phase IV in review) have identified that a large potential water resource resides in flooded, abandoned coal mines in the Pittsburgh Coal Basin, and likely elsewhere in the region and nation. This study evaluates the technical and economic potential of the Pittsburgh Coal Basin water source to supply new power plants with cooling water. Two approaches for supplying new power plants were evaluated. Type A employs mine water in conventional, evaporative cooling towers. Type B utilizes earth-coupled cooling with flooded underground mines as the principal heat sink for the power plant reject heat load. Existing mine discharges in the Pittsburgh Coal Basin were evaluated for flow and water quality. Based on this analysis, eight sites were identified where mine water could supply cooling water to a power plant. Three of these sites were employed for pre-engineering design and cost analysis of a Type A water supply system, including mine water collection, treatment, and delivery. This method was also applied to a ''base case'' river-source power plant, for comparison. Mine-water system cost estimates were then compared to the base-case river source estimate. We found that the use of net-alkaline mine water would under current economic conditions be competitive with a river-source in a comparable-size water cooling system. On the other hand, utilization of net acidic water would be higher in operating cost than the river system by 12 percent. This does not account for any environmental benefits that would accrue due to the treatment of acid mine drainage, in many locations an existing public liability. We also found it likely that widespread adoption of mine-water utilization for power plant cooling will require resolution of potential liability and mine-water ownership issues. In summary, Type A mine-water utilization for power plant cooling is considered a strong option for meeting water needs of new plant in selected areas. Analysis of the thermal and water handling requirements for a 600 megawatt power plant indicated that Type B earth coupled cooling would not be feasible for a power plant of this size. It was determined that Type B cooling would be possible, under the right conditions, for power plants of 200 megawatts or less. Based on this finding the feasibility of a 200 megawatt facility was evaluated. A series of mines were identified where a Type B earth-coupled 200 megawatt power plant cooling system might be feasible. Two water handling scenarios were designed to distribute heated power-plant water throughout the mines. Costs were developed for two different pumping scenarios employing a once-through power-plant cooling circuit. Thermal and groundwater flow simulation models were used to simulate the effect of hot water injection into the mine under both pumping strategies and to calculate the return-water temperature over the design life of a plant. Based on these models, staged increases in required mine-water pumping rates are projected to be part of the design, due to gradual heating and loss of heat-sink efficiency of the rock sequence above the mines. Utilizing pumping strategy No.1 (two mines) capital costs were 25 percent lower a

  19. Pipeline Safety Rule (Tennessee)

    Broader source: Energy.gov [DOE]

    The Pipeline Safety Rule simply states, "The Minimum Federal Safety Standards for the transportation of natural and other gas by pipeline (Title 49, Chapter 1, Part 192) as published in the Federal...

  20. Arkansas Water Resources Center

    E-Print Network [OSTI]

    Soerens, Thomas

    Arkansas Water Resources Center WATER RESOURCES ASPECTS OF COAL TRANSPORTATION BY SLURRY PIPELINE Electric Power Production with Transmission by EHV Power lines 8 Coal Slurry Pipelining versus Rail Shipment. 10 General Description of the Coal Slurry Pipelining Process. 14 History of Coal Slurry Pipelines

  1. Keystone XL pipeline update

    Broader source: Energy.gov [DOE]

    Questions have been raised recently about the Keystone XL pipeline project, so we wanted to make some points clear.

  2. Utilization of solid wastes from the gasification of coal-water slurries

    SciTech Connect (OSTI)

    M.Y. Shpirt; N.P. Goryunova [Institute for Fossil Fuels, Moscow (Russian Federation)

    2009-07-01T23:59:59.000Z

    It was found that only fly and bottom ashes are the solid wastes of water-coal slurry gasification in a direct-flow gasifier. The yields and chemical compositions of fly and bottom ashes obtained after the gasification of water-coal slurries prepared using brown (B) and long-flame (D) coals from the Berezovskii and Mokhovskii strip mines (Kansk-Achinsk and Kuznetsk Basins, respectively) were characterized. Based on an analysis of currently available information, the areas of utilization of fly and bottom ashes after water-coal slurry gasification with dry ash removal were summarized. The use of these wastes in the construction of high-ways and earthwork structures (for the parent coals of B and D grades) and in the manufacture of ash concrete (for the parent coal of D grade) is most promising.

  3. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Bill Bruce; Nancy Porter; George Ritter; Matt Boring; Mark Lozev; Ian Harris; Bill Mohr; Dennis Harwig; Robin Gordon; Chris Neary; Mike Sullivan

    2005-07-20T23:59:59.000Z

    The two broad categories of fiber-reinforced composite liner repair and deposited weld metal repair technologies were reviewed and evaluated for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Principal conclusions from a survey of natural gas transmission industry pipeline operators can be summarized in terms of the following performance requirements for internal repair: (1) Use of internal repair is most attractive for river crossings, under other bodies of water, in difficult soil conditions, under highways, under congested intersections, and under railway crossings. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling when a new bore must be created to solve a leak or other problem. (3) Typical travel distances can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). All three groups require pig-based systems. A despooled umbilical system would suffice for the first two groups which represents 81% of survey respondents. The third group would require an onboard self-contained power unit for propulsion and welding/liner repair energy needs. (4) The most common size range for 80% to 90% of operators surveyed is 508 mm (20 in.) to 762 mm (30 in.), with 95% using 558.8 mm (22 in.) pipe. Evaluation trials were conducted on pipe sections with simulated corrosion damage repaired with glass fiber-reinforced composite liners, carbon fiber-reinforced composite liners, and weld deposition. Additional un-repaired pipe sections were evaluated in the virgin condition and with simulated damage. Hydrostatic failure pressures for pipe sections repaired with glass fiber-reinforced composite liner were only marginally greater than that of pipe sections without liners, indicating that this type of liner is only marginally effective at restoring the pressure containing capabilities of pipelines. Failure pressures for larger diameter pipe repaired with a semi-circular patch of carbon fiber-reinforced composite lines were also marginally greater than that of a pipe section with un-repaired simulated damage without a liner. These results indicate that fiber reinforced composite liners have the potential to increase the burst pressure of pipe sections with external damage Carbon fiber based liners are viewed as more promising than glass fiber based liners because of the potential for more closely matching the mechanical properties of steel. Pipe repaired with weld deposition failed at pressures lower than that of un-repaired pipe in both the virgin and damaged conditions, indicating that this repair technology is less effective at restoring the pressure containing capability of pipe than a carbon fiber-reinforced liner repair. Physical testing indicates that carbon fiber-reinforced liner repair is the most promising technology evaluated to-date. In lieu of a field installation on an abandoned pipeline, a preliminary nondestructive testing protocol is being developed to determine the success or failure of the fiber-reinforced liner pipeline repairs. Optimization and validation activities for carbon-fiber repair methods are ongoing.

  4. Experience with pipelined multiple instruction streams

    SciTech Connect (OSTI)

    Jordon, H.F.

    1984-01-01T23:59:59.000Z

    Pipelining has been used to implement efficient, high-speed vector computers. It is also an effective method for implementing multiprocessors. The Heterogeneous Element Processor (HEP) built by Denelcor Incorporated is the first commercially available computer system to use pipelining to implement multiple processes. This paper introduces the architecture and programming environment of the HEP and surveys a range of scientific applications programs for which parallel versions have been produced, tested, and analyzed on this computer. In all cases, the ideal of one instruction completion every pipeline step time is closely approached. Speed limitations in the parallel programs are more often a result of the extra code necessary to ensure synchronization than of actual synchronization lockout at execution time. The pipelined multiple instruction stream architecture is shown to cover a wide range of applications with good utilization of the parallel hardware.

  5. Heat Pump Water Heater Technology: Experiences of Residential Consumers and Utilities

    SciTech Connect (OSTI)

    Ashdown, BG

    2004-08-04T23:59:59.000Z

    This paper presents a case study of the residential heat pump water heater (HPWH) market. Its principal purpose is to evaluate the extent to which the HPWH will penetrate the residential market sector, given current market trends, producer and consumer attributes, and technical parameters. The report's secondary purpose is to gather background information leading to a generic framework for conducting market analyses of technologies. This framework can be used to compare readiness and to factor attributes of market demand back into product design. This study is a rapid prototype analysis rather than a detailed case analysis. For this reason, primary data collection was limited and reliance on secondary sources was extensive. Despite having met its technical goals and having been on the market for twenty years, the HPWH has had virtually no impact on contributing to the nation's water heating. In some cases, HPWH reliability and quality control are well below market expectations, and early units developed a reputation for unreliability, especially when measured against conventional water heaters. In addition to reliability problems, first costs of HPWH units can be three to five times higher than conventional units. Without a solid, well-managed business plan, most consumers will not be drawn to this product. This is unfortunate. Despite its higher first costs, efficiency of an HPWH is double that of a conventional water heater. The HPWH also offers an attractive payback period of two to five years, depending on hot water usage. On a strict life-cycle basis it supplies hot water very cost effectively. Water heating accounts for 17% of the nation's residential consumption of electricity (see chart at left)--water heating is second only to space heating in total residential energy use. Simple arithmetic suggests that this figure could be reduced to the extent HPWH technology displaces conventional water heating. In addition, the HPWH offers other benefits. Because it produces hot water by extracting heat from the air it tends to dehumidify and cool the room in which it is placed. Moreover, it tends to spread the water heating load across utility non-peak periods. Thus, electric utilities with peak load issues could justify internal programs to promote this technology to residential and commercial customers. For practical purposes, consumers are indifferent to the manner in which water is heated but are very interested in product attributes such as initial first cost, operating cost, performance, serviceability, product size, and installation costs. Thus, the principal drivers for penetrating markets are demonstrating reliability, leveraging the dehumidification attributes of the HPWH, and creating programs that embrace life-cycle cost principles. To supplement this, a product warranty with scrupulous quality control should be implemented; first-price reduction through engineering, perhaps by reducing level of energy efficiency, should be pursued; and niche markets should be courted. The first step toward market penetration is to address the HPWH's performance reliability. Next, the manufacturers could engage select utilities to aggressively market the HPWH. A good approach would be to target distinct segments of the market with the potential for the highest benefits from the technology. Communications media that address performance issues should be developed. When marketing to new home builders, the HPWH could be introduced as part of an energy-efficient package offered as a standard feature by builders of new homes within a community. Conducting focus groups across the United States to gather input on HPWH consumer values will feed useful data back to the manufacturers. ''Renaming'' and ''repackaging'' the HPWH to improve consumer perception, appliance aesthetics, and name recognition should be considered. Once an increased sales volume is achieved, the manufacturers should reinvest in R&D to lower the price of the units. The manufacturers should work with ''do-it-yourself'' (DIY) stores to facilitate introduction of th

  6. Use of intelligent pigs to detect stress corrosion cracking in gas pipelines

    SciTech Connect (OSTI)

    Culbertson, D.L. [Tenneco Energy, Houston, TX (United States)

    1996-08-01T23:59:59.000Z

    To ensure the integrity and serviceability of gas pipelines, operators periodically utilize intelligent pigging. This inspection technique has proven to be a cost effective approach for determining the condition of operating pipelines. Recent advancements in intelligent pigging technology are now aiding the pipeline industry in the detection of stress corrosion cracking.

  7. Water treatment capacity of forward osmosis systems utilizing power plant waste heat

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Zhou, Xingshi; Gingerich, Daniel B.; Mauter, Meagan S.

    2015-06-11T23:59:59.000Z

    Forward osmosis (FO) has the potential to improve the energy efficiency of membrane-based water treatment by leveraging waste heat from steam electric power generation as the primary driving force for separation. In this study, we develop a comprehensive FO process model, consisting of membrane separation, heat recovery, and draw solute regeneration (DSR) models. We quantitatively characterize three alternative processes for DSR: distillation, steam stripping, and air stripping. We then construct a mathematical model of the distillation process for DSR that incorporates hydrodynamics, mass and heat transport resistances, and reaction kinetics, and we integrate this into a model for the fullmore »FO process. Finally, we utilize this FO process model to derive a first-order approximation of the water production capacity given the rejected heat quantity and quality available at U.S. electric power facilities. We find that the upper bound of FO water treatment capacity using low-grade heat sources at electric power facilities exceeds process water treatment demand for boiler water make-up and flue gas desulfurization wastewater systems.« less

  8. Water treatment capacity of forward osmosis systems utilizing power plant waste heat

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Zhou, Xingshi [Carnegie Mellon Univ., Pittsburgh, PA (United States); Gingerich, Daniel B. [Carnegie Mellon Univ., Pittsburgh, PA (United States); Mauter, Meagan S. [Carnegie Mellon Univ., Pittsburgh, PA (United States)

    2015-06-11T23:59:59.000Z

    Forward osmosis (FO) has the potential to improve the energy efficiency of membrane-based water treatment by leveraging waste heat from steam electric power generation as the primary driving force for separation. In this study, we develop a comprehensive FO process model, consisting of membrane separation, heat recovery, and draw solute regeneration (DSR) models. We quantitatively characterize three alternative processes for DSR: distillation, steam stripping, and air stripping. We then construct a mathematical model of the distillation process for DSR that incorporates hydrodynamics, mass and heat transport resistances, and reaction kinetics, and we integrate this into a model for the full FO process. Finally, we utilize this FO process model to derive a first-order approximation of the water production capacity given the rejected heat quantity and quality available at U.S. electric power facilities. We find that the upper bound of FO water treatment capacity using low-grade heat sources at electric power facilities exceeds process water treatment demand for boiler water make-up and flue gas desulfurization wastewater systems.

  9. Watering the slums : how a utility and its street-level bureaucrats connected the poor in Bangalore

    E-Print Network [OSTI]

    Connors, Genevieve

    2007-01-01T23:59:59.000Z

    This dissertation is about how urban water utilities behave and what makes them interested in serving the poor. The infrastructure literature tends to treat public service agencies as monolithic entities and to ignore the ...

  10. Pipeline Decommissioning Trial AWE Berkshire UK - 13619

    SciTech Connect (OSTI)

    Agnew, Kieran [AWE, Aldermaston, Reading, RG7 4PR (United Kingdom)] [AWE, Aldermaston, Reading, RG7 4PR (United Kingdom)

    2013-07-01T23:59:59.000Z

    This Paper details the implementation of a 'Decommissioning Trial' to assess the feasibility of decommissioning the redundant pipeline operated by AWE located in Berkshire UK. The paper also presents the tool box of decommissioning techniques that were developed during the decommissioning trial. Constructed in the 1950's and operated until 2005, AWE used a pipeline for the authorised discharge of treated effluent. Now redundant, the pipeline is under a care and surveillance regime awaiting decommissioning. The pipeline is some 18.5 km in length and extends from AWE site to the River Thames. Along its route the pipeline passes along and under several major roads, railway lines and rivers as well as travelling through woodland, agricultural land and residential areas. Currently under care and surveillance AWE is considering a number of options for decommissioning the pipeline. One option is to remove the pipeline. In order to assist option evaluation and assess the feasibility of removing the pipeline a decommissioning trial was undertaken and sections of the pipeline were removed within the AWE site. The objectives of the decommissioning trial were to: - Demonstrate to stakeholders that the pipeline can be removed safely, securely and cleanly - Develop a 'tool box' of methods that could be deployed to remove the pipeline - Replicate the conditions and environments encountered along the route of the pipeline The onsite trial was also designed to replicate the physical prevailing conditions and constraints encountered along the remainder of its route i.e. working along a narrow corridor, working in close proximity to roads, working in proximity to above ground and underground services (e.g. Gas, Water, Electricity). By undertaking the decommissioning trial AWE have successfully demonstrated the pipeline can be decommissioned in a safe, secure and clean manor and have developed a tool box of decommissioning techniques. The tool box of includes; - Hot tapping - a method of breaching the pipe while maintaining containment to remove residual liquids, - Crimp and shear - remote crimping, cutting and handling of pipe using the excavator - Pipe jacking - a way of removing pipes avoiding excavations and causing minimal disturbance and disruption. The details of the decommissioning trial design, the techniques employed, their application and effectiveness are discussed and evaluated here in. (authors)

  11. Application Filing Requirements for Natural Gas Pipeline Construction Projects (Wisconsin)

    Broader source: Energy.gov [DOE]

    Any utility proposing to construct a natural gas pipeline requiring a Certificate of Authority (CA) under Wis. Stat. §196.49 must prepare an application for Commission review.  These regulations ...

  12. UTILIZING WATER EMULSIFICATION TO REDUCE NOX AND PARTICULATE EMISSIONS ASSOCIATED WITH BIODIESEL

    SciTech Connect (OSTI)

    Kass, Michael D [ORNL; Lewis Sr, Samuel Arthur [ORNL; Lee, Doh-Won [ORNL; Huff, Shean P [ORNL; Storey, John Morse [ORNL; Swartz, Matthew M [ORNL; Wagner, Robert M [ORNL

    2009-01-01T23:59:59.000Z

    A key barrier limiting extended utilization of biodiesel is higher NOx emissions compared to petrodiesel fuels. The reason for this effect is unclear, but various researchers have attributed this phenomena to the higher liquid bulk modulus associated with biodiesel and the additional heat released during the breaking of C-C double bonds in the methyl ester groups. In this study water was incorporated into neat biodiesel (B100) as an emulsion in an attempt to lower NOx and particulate matter (PM) emissions. A biodiesel emulsion containing 10wt% water was formulated and evaluated against an ultra-low sulfur petroleum diesel (ULSD) and neat biodiesel (B100) in a light-duty diesel engine operated at 1500RPM and at loads of 68Nm (50ft-lbs) and 102Nm (75ft-lbs). The influence of exhaust gas recirculation (EGR) was also examined. The incorporation of water was found to significantly lower the NOx emissions of B100, while maintaining fuel efficiency when operating at 0 and 27% EGR. The soot fraction of the particulates (as determined using an opacity meter) was much lower for the B100 and B100-water emulsion compared ULSD. In contrast, total PM mass (for the three fuel types) was unchanged for the 0% EGR condition but was significantly lower for the B100 and B100-emulsion during the 27% EGR condition compared to the ULSD fuel. Analysis of the emissions and heat release data indicate that water enhances air-fuel premixing to maintain fuel economy and lower soot formation. The exhaust chemistry of the biodiesel base fuels (B100 and water-emulsified B100) was found to be unique in that they contained measurable levels of methyl alkenoates, which were not found for the ULSD. These compounds were formed by the partial cracking of the methyl ester groups during combustion.

  13. Energy Reduction in California Pipeline Operations

    E-Print Network [OSTI]

    technologies that can help California's industrial sectors reduce their energy consumption, their water use. In addition to significant baseline energy consumption, more energy is often required by pipelines Energy Commission Public Interest Energy Research Program Industrial/Agriculture/Water EndUse Phone

  14. EIA - Natural Gas Pipeline Network - Largest Natural Gas Pipeline...

    U.S. Energy Information Administration (EIA) Indexed Site

    Interstate Pipelines Table About U.S. Natural Gas Pipelines - Transporting Natural Gas based on data through 20072008 with selected updates Thirty Largest U.S. Interstate Natural...

  15. Finding of No Significant Impact for the Environmental Assessment for the Strategic Petroleum Reserve West Hackberry Facility Raw Water Intake Pipeline Replacement Cameron and Calcasieu Parishes, Louisiana

    SciTech Connect (OSTI)

    N /A

    2004-08-31T23:59:59.000Z

    DOE has prepared an Environmental Assessment (EA), DOE/EA-1497, for the proposed replacement of the existing 107 centimeter (cm) [42 inch (in)] 6.87 kilometer (km) [4.27 mile (mi)] raw water intake pipeline (RWIPL). This action is necessary to allow for continued, optimum operations at the West Hackberry facility (main site/facility). The EA described the proposed action (including action alternatives) and three alternatives to the proposed action. The EA evaluated only the potential environmental consequences of the proposed action (one action alternative), and Alternative 3, which consisted of the No Build Action that is required by 10 CFR 1021.321(c). Based on the analysis in DOE/EA-1497, DOE has determined that the proposed action does not constitute a major Federal action significantly affecting humans or the natural environment within the meaning of the National Environmental Policy Act of 1969 (NEPA), 42 USC 4321 et seq. Therefore, an Environmental Impact Statement (EIS) is not required, and DOE is issuing this Finding of No Significant Impact (FONSI). To further minimize impacts to environmental media, the DOE will also implement a Mitigation Action Plan (MAP) for this action. The MAP is included as Appendix F of this EA, which is appended to this FONSI. The Energy Policy and Conservation Act of 1975 (EPCA), as amended, authorizes the creation of the Strategic Petroleum Reserve (SPR) to store crude oil to reduce the United States' vulnerability to energy supply disruptions. Crude oil is stored in geologic formations, or salt domes, located under these facilities. The purpose of this proposed project is to construct a new RWIPL at the main site to replace the existing RWIPL which services this facility.

  16. Natural Gas Pipeline Safety (Kansas)

    Broader source: Energy.gov [DOE]

    This article states minimum safety standards for the transportation of natural gas by pipeline and reporting requirements for operators of pipelines.

  17. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Ian Harris; Dennis Harwig; Nancy Porter; Mike Sullivan; Chris Neary

    2004-04-12T23:59:59.000Z

    The two broad categories of deposited weld metal repair and fiber-reinforced composite liner repair technologies were reviewed for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Preliminary test programs were developed for both deposited weld metal repair and for fiber-reinforced composite liner repair. Evaluation trials have been conducted using a modified fiber-reinforced composite liner provided by RolaTube and pipe sections without liners. All pipe section specimens failed in areas of simulated damage. Pipe sections containing fiber-reinforced composite liners failed at pressures marginally greater than the pipe sections without liners. The next step is to evaluate a liner material with a modulus of elasticity approximately 95% of the modulus of elasticity for steel. Preliminary welding parameters were developed for deposited weld metal repair in preparation of the receipt of Pacific Gas & Electric's internal pipeline welding repair system (that was designed specifically for 559 mm (22 in.) diameter pipe) and the receipt of 559 mm (22 in.) pipe sections from Panhandle Eastern. The next steps are to transfer welding parameters to the PG&E system and to pressure test repaired pipe sections to failure. A survey of pipeline operators was conducted to better understand the needs and performance requirements of the natural gas transmission industry regarding internal repair. Completed surveys contained the following principal conclusions: (1) Use of internal weld repair is most attractive for river crossings, under other bodies of water, in difficult soil conditions, under highways, under congested intersections, and under railway crossings. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling (HDD) when a new bore must be created to solve a leak or other problem. (3) Typical travel distances can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). All three groups require pig-based systems. A despooled umbilical system would suffice for the first two groups which represents 81% of survey respondents. The third group would require an onboard self-contained power unit for propulsion and welding/liner repair energy needs. (4) Pipe diameter sizes range from 50.8 mm (2 in.) through 1,219.2 mm (48 in.). The most common size range for 80% to 90% of operators surveyed is 508 mm to 762 mm (20 in. to 30 in.), with 95% using 558.8 mm (22 in.) pipe. An evaluation of potential repair methods clearly indicates that the project should continue to focus on the development of a repair process involving the use of GMAW welding and on the development of a repair process involving the use of fiber-reinforced composite liners.

  18. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Ian Harris; Dennis Harwig; George Ritter; Bill Mohr; Matt Boring; Nancy Porter; Mike Sullivan; Chris Neary

    2004-12-31T23:59:59.000Z

    The two broad categories of fiber-reinforced composite liner repair and deposited weld metal repair technologies were reviewed and evaluated for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Principal conclusions from a survey of natural gas transmission industry pipeline operators can be summarized in terms of the following performance requirements for internal repair: (1) Use of internal repair is most attractive for river crossings, under other bodies of water, in difficult soil conditions, under highways, under congested intersections, and under railway crossings. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling when a new bore must be created to solve a leak or other problem. (3) Typical travel distances can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). All three groups require pig-based systems. A despooled umbilical system would suffice for the first two groups which represents 81% of survey respondents. The third group would require an onboard self-contained power unit for propulsion and welding/liner repair energy needs. (4) The most common size range for 80% to 90% of operators surveyed is 508 mm (20 in.) to 762 mm (30 in.), with 95% using 558.8 mm (22 in.) pipe. Evaluation trials were conducted on pipe sections with simulated corrosion damage repaired with glass fiber-reinforced composite liners, carbon fiber-reinforced composite liners, and weld deposition. Additional un-repaired pipe sections were evaluated in the virgin condition and with simulated damage. Hydrostatic failure pressures for pipe sections repaired with glass fiber-reinforced composite liner were only marginally greater than that of pipe sections without liners, indicating that this type of liner is only marginally effective at restoring the pressure containing capabilities of pipelines. Failure pressures for larger diameter pipe repaired with a semi-circular patch of carbon fiber-reinforced composite lines were also marginally greater than that of a pipe section with un-repaired simulated damage without a liner. These results indicate that fiber reinforced composite liners have the potential to increase the burst pressure of pipe sections with external damage Carbon fiber based liners are viewed as more promising than glass fiber based liners because of the potential for more closely matching the mechanical properties of steel. Pipe repaired with weld deposition failed at pressures lower than that of un-repaired pipe in both the virgin and damaged conditions, indicating that this repair technology is less effective at restoring the pressure containing capability of pipe than a carbon fiber-reinforced liner repair. Physical testing indicates that carbon fiber-reinforced liner repair is the most promising technology evaluated to-date. The first round of optimization and validation activities for carbon-fiber repairs are complete. Development of a comprehensive test plan for this process is recommended for use in the field trial portion of this program.

  19. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Ian Harris; Dennis Harwig; George Ritter; Bill Mohr; Matt Boring; Nancy Porter; Mike Sullivan; Chris Neary

    2004-08-17T23:59:59.000Z

    The two broad categories of fiber-reinforced composite liner repair and deposited weld metal repair technologies were reviewed and evaluated for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Principal conclusions from a survey of natural gas transmission industry pipeline operators can be summarized in terms of the following performance requirements for internal repair: (1) Use of internal repair is most attractive for river crossings, under other bodies of water, in difficult soil conditions, under highways, under congested intersections, and under railway. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling when a new bore must be created to solve a leak or other problem. (3) Typical travel distances can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). All three groups require pig-based systems. A despooled umbilical system would suffice for the first two groups which represents 81% of survey respondents. The third group would require an onboard self-contained power unit for propulsion and welding/liner repair energy needs. (4) The most common size range for 80% to 90% of operators surveyed is 508 mm (20 in.) to 762 mm (30 in.), with 95% using 558.8 mm (22 in.) pipe. Evaluation trials were conducted on pipe sections with simulated corrosion damage repaired with glass fiber-reinforced composite liners, carbon fiber-reinforced composite liners, and weld deposition. Additional un-repaired pipe sections were evaluated in the virgin condition and with simulated damage. Hydrostatic failure pressures for pipe sections repaired with glass fiber-reinforced composite liner were only marginally greater than that of pipe sections without liners, indicating that this type of liner is only marginally effective at restoring the pressure containing capabilities of pipelines. Failure pressures for larger diameter pipe repaired with a semi-circular patch of carbon fiber-reinforced composite lines were also marginally greater than that of a pipe section with un-repaired simulated damage without a liner. These results indicate that fiber reinforced composite liners have the potential to increase the burst pressure of pipe sections with external damage Carbon fiber based liners are viewed as more promising than glass fiber based liners because of the potential for more closely matching the mechanical properties of steel. Pipe repaired with weld deposition failed at pressures lower than that of un-repaired pipe in both the virgin and damaged conditions, indicating that this repair technology is less effective at restoring the pressure containing capability of pipe than a carbon fiber-reinforced liner repair. Physical testing indicates that carbon fiber-reinforced liner repair is the most promising technology evaluated to-date. Development of a comprehensive test plan for this process is recommended for use in the field trial portion of this program.

  20. A Cheap Levitating Gas/Load Pipeline

    E-Print Network [OSTI]

    Alexander Bolonkin

    2008-12-02T23:59:59.000Z

    Design of new cheap aerial pipelines, a large flexible tube deployed at high altitude, for delivery of natural (fuel) gas, water and other payload over a long distance is delineated. The main component of the natural gas is methane which has a specific weight less than air. A lift force of one cubic meter of methane equals approximately 0.5 kg (1 pound). The lightweight film flexible pipeline can be located in air at high altitude and, as such, does not damage the environment. Using the lift force of this pipeline and wing devices payloads of oil, water, or other fluids, or even solids such as coal, cargo, passengers can be delivered cheaply at long distance. This aerial pipeline dramatically decreases the cost and the time of construction relative to conventional pipelines of steel which saves energy and greatly lowers the capital cost of construction. The article contains a computed project for delivery 24 billion cubic meters of gas and tens of million tons of oil, water or other payload per year.

  1. Experience with pipelined multiple instruction streams

    SciTech Connect (OSTI)

    Jordan, H.F.

    1984-01-01T23:59:59.000Z

    The authors introduces the architecture and programming environment of the heterogeneous element processor (HEP) and surveys a range of scientific applications programs for which parallel versions have been produced, tested, and analyzed on this computer. In all cases, the ideal of one instruction completion every pipeline step time is closely approached. Speed limitations in the parallel programs are more often a result of the extra code necessary to ensure synchronization than of actual synchronization lockout at execution time. The pipelined multiple instruction stream architecture is shown to cover a wide range of applications with good utilization of the parallel hardware. 35 references.

  2. FEATURE ARTICLE Pipeline Corrosion

    E-Print Network [OSTI]

    Botte, Gerardine G.

    F FEATURE ARTICLE Pipeline Corrosion Issues Related to Carbon Capture, Transportation, and Storage Capture, Transportation, and Storage--Aspects of Corrosion and Materials. "Until these new technologies are developed and applied, corrosion engineers are focusing on how to best design pipelines for CO2 transport

  3. LASER TRIGGERED GAS SWITCHES UTILIZING BEAM TRANSPORT THROUGH 1 MO-cm DEIONIZED WATER.

    SciTech Connect (OSTI)

    Woodworth, Joseph Ray; Lehr, Jane [Sandia National Laboratories, Albuquerque, NM; Blickem, James R.; Wallace, Zachariah R.; Anaya, Victor Jr; Corley, John P; Lott, John; Hodge, Keith; Zameroski, Nathan D. [Sandia National Laboratories, Albuquerque, NM

    2005-11-01T23:59:59.000Z

    We report on the successful attempts to trigger high voltage pressurized gas switches by utilizing beam transport through 1 MO-cm deionized water. The wavelength of the laser radiation was 532 nm. We have investigated Nd: YAG laser triggering of a 6 MV, SF6 insulated gas switch for a range of laser and switch parameters. Laser wavelength of 532 nm with nominal pulse lengths of 10 ns full width half maximum (FWHM) were used to trigger the switch. The laser beam was transported through 67 cm-long cell of 1 MO-cm deionized water constructed with anti reflection UV grade fused silica windows. The laser beam was then focused to form a breakdown arc in the gas between switch electrodes. Less than 10 ns jitter in the operation of the switch was obtained for laser pulse energies of between 80-110 mJ. Breakdown arcs more than 35 mm-long were produced by using a 70 cm focusing optic.

  4. BP and Hydrogen Pipelines DOE Hydrogen Pipeline Working Group Workshop

    E-Print Network [OSTI]

    efforts were undertaken · Conversion took place during a period of less regulation on pipeline activityBP and Hydrogen Pipelines DOE Hydrogen Pipeline Working Group Workshop August 30-31, 2005 Gary P · UK partnership opened the first hydrogen demonstration refueling station · Two hydrogen pipelines

  5. Overview of interstate hydrogen pipeline systems.

    SciTech Connect (OSTI)

    Gillette, J .L.; Kolpa, R. L

    2008-02-01T23:59:59.000Z

    The use of hydrogen in the energy sector of the United States is projected to increase significantly in the future. Current uses are predominantly in the petroleum refining sector, with hydrogen also being used in the manufacture of chemicals and other specialized products. Growth in hydrogen consumption is likely to appear in the refining sector, where greater quantities of hydrogen will be required as the quality of the raw crude decreases, and in the mining and processing of tar sands and other energy resources that are not currently used at a significant level. Furthermore, the use of hydrogen as a transportation fuel has been proposed both by automobile manufacturers and the federal government. Assuming that the use of hydrogen will significantly increase in the future, there would be a corresponding need to transport this material. A variety of production technologies are available for making hydrogen, and there are equally varied raw materials. Potential raw materials include natural gas, coal, nuclear fuel, and renewables such as solar, wind, or wave energy. As these raw materials are not uniformly distributed throughout the United States, it would be necessary to transport either the raw materials or the hydrogen long distances to the appropriate markets. While hydrogen may be transported in a number of possible forms, pipelines currently appear to be the most economical means of moving it in large quantities over great distances. One means of controlling hydrogen pipeline costs is to use common rights-of-way (ROWs) whenever feasible. For that reason, information on hydrogen pipelines is the focus of this document. Many of the features of hydrogen pipelines are similar to those of natural gas pipelines. Furthermore, as hydrogen pipeline networks expand, many of the same construction and operating features of natural gas networks would be replicated. As a result, the description of hydrogen pipelines will be very similar to that of natural gas pipelines. The following discussion will focus on the similarities and differences between the two pipeline networks. Hydrogen production is currently concentrated in refining centers along the Gulf Coast and in the Farm Belt. These locations have ready access to natural gas, which is used in the steam methane reduction process to make bulk hydrogen in this country. Production centers could possibly change to lie along coastlines, rivers, lakes, or rail lines, should nuclear power or coal become a significant energy source for hydrogen production processes. Should electrolysis become a dominant process for hydrogen production, water availability would be an additional factor in the location of production facilities. Once produced, hydrogen must be transported to markets. A key obstacle to making hydrogen fuel widely available is the scale of expansion needed to serve additional markets. Developing a hydrogen transmission and distribution infrastructure would be one of the challenges to be faced if the United States is to move toward a hydrogen economy. Initial uses of hydrogen are likely to involve a variety of transmission and distribution methods. Smaller users would probably use truck transport, with the hydrogen being in either the liquid or gaseous form. Larger users, however, would likely consider using pipelines. This option would require specially constructed pipelines and the associated infrastructure. Pipeline transmission of hydrogen dates back to late 1930s. These pipelines have generally operated at less than 1,000 pounds per square inch (psi), with a good safety record. Estimates of the existing hydrogen transmission system in the United States range from about 450 to 800 miles. Estimates for Europe range from about 700 to 1,100 miles (Mohipour et al. 2004; Amos 1998). These seemingly large ranges result from using differing criteria in determining pipeline distances. For example, some analysts consider only pipelines above a certain diameter as transmission lines. Others count only those pipelines that transport hydrogen from a producer to a customer (e.g., t

  6. Code for Hydrogen Hydrogen Pipeline

    E-Print Network [OSTI]

    #12;2 Code for Hydrogen Pipelines Hydrogen Pipeline Working Group Workshop Augusta, Georgia August development · Charge from BPTCS to B31 Standards Committee for Hydrogen Piping/Pipeline code development · B31.12 Status & Structure · Hydrogen Pipeline issues · Research Needs · Where Do We Go From Here? #12;4 Code

  7. Composites Technology for Hydrogen Pipelines

    E-Print Network [OSTI]

    Composites Technology for Hydrogen Pipelines Barton Smith, Barbara Frame, Larry Anovitz and Cliff;Composites Technology for Hydrogen Pipelines Fiber-reinforced polymer pipe Project Overview: Investigate of pipeline per day. · $190k/mile capital cost for distribution pipelines · Hydrogen delivery cost below $1

  8. GAS PIPELINE PIGABILITY

    SciTech Connect (OSTI)

    Ted Clark; Bruce Nestleroth

    2004-04-01T23:59:59.000Z

    In-line inspection equipment is commonly used to examine a large portion of the long distance transmission pipeline system that transports natural gas from well gathering points to local distribution companies. A piece of equipment that is inserted into a pipeline and driven by product flow is called a ''pig''. Using this term as a base, a set of terms has evolved. Pigs that are equipped with sensors and data recording devices are called ''intelligent pigs''. Pipelines that cannot be inspected using intelligent pigs are deemed ''unpigable''. But many factors affect the passage of a pig through a pipeline, or the ''pigability''. The pigability pipeline extend well beyond the basic need for a long round hole with a means to enter and exit. An accurate assessment of pigability includes consideration of pipeline length, attributes, pressure, flow rate, deformation, cleanliness, and other factors as well as the availability of inspection technology. All factors must be considered when assessing the appropriateness of ILI to assess specific pipeline threats.

  9. Pipeline system insulation: Thermal insulation and corrosion prevention. (Latest citations from the Rubber and Plastics Research Association database). Published Search

    SciTech Connect (OSTI)

    Not Available

    1994-05-01T23:59:59.000Z

    The bibliography contains citations concerning thermal and corrosion insulation of pipeline systems used to transport liquids and gases. Topics include thermal aging of polyurethane used for foam heating pipes, extrusion film pipeline insulation materials and processes, flexible expanded nitrile rubber pipeline insulation with Class 1 fire rating, and underground fiberglass reinforced polyester insulated pipeline systems. Applications in solar heating systems; underground water, oil, and gas pipelines; interior hot and cold water lines under seawater; and chemical plant pipeline system insulation are included. (Contains 250 citations and includes a subject term index and title list.)

  10. The Mobile Test and Demonstration Unit, A Cooperative Project Between EPRI, Utilities and Industry to Demonstrate New Water Treatment Technologies

    E-Print Network [OSTI]

    Strasser, J.; Mannapperuma, J.

    THE MOBILE TEST AND DEMONSTRATION UNIT, A COOPERATIVE PROJECT BETWEEN EPRl, UTll.JTIES AND INDUSTRY TO DEMONSTRATE NEW WATER TREATMENT TECHNOLOGIES Jurgen Strasser Consultant to the EPRI Food Office Process & Equipment Technology... agencies are encouraging the reduction of the discharge of high BOD and TSS waste water to the local mlUlicipalities and/or waterways. EPRI collaborated with utilities, the US Dept. of Energy, food processor trade groups, and scientists from the Calif...

  11. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Nancy Porter; Mike Sullivan; Chris Neary

    2003-05-01T23:59:59.000Z

    The two broad categories of deposited weld metal repair and fiber-reinforced composite repair technologies were reviewed for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Preliminary test programs were developed for both deposited weld metal repairs and for fiber-reinforced composite repair. To date, all of the experimental work pertaining to the evaluation of potential repair methods has focused on fiber-reinforced composite repairs. Hydrostatic testing was also conducted on four pipeline sections with simulated corrosion damage: two with composite liners and two without.

  12. Leaving the Premedical Pipeline at Cal

    E-Print Network [OSTI]

    Kwan, Elizabeth

    2001-01-01T23:59:59.000Z

    Why students drop out of the pipeline to health professionsLeaving the Premedical Pipeline at Cal By Elizabeth Kwanattrition from the premedical pipeline is appropriate. Not

  13. Capturing Latino Students in the Academic Pipeline

    E-Print Network [OSTI]

    Gándara, Patricia; Larson, Katherine; Mehan, Hugh; Rumberger, Russell

    1998-01-01T23:59:59.000Z

    The Latino Educational Pipeline Why Latino Students are atSTUDENTS IN THE ACADEMIC PIPELINE CAPTURING LATINO STUDENTSIN THE ACADEMIC PIPELINE Patricia Gcindara, Editor Katherine

  14. Pipeline Carriers (Montana)

    Broader source: Energy.gov [DOE]

    Pipeline carriers transporting crude petroleum, coal, the products of crude petroleum or coal, or carbon dioxide produced in the combustion or gasification of fossil fuels are required to abide by...

  15. Rnnotator Assembly Pipeline

    SciTech Connect (OSTI)

    Martin, Jeff [DOE Joint Genome Institute

    2010-06-03T23:59:59.000Z

    Jeff Martin of the DOE Joint Genome Institute discusses a de novo transcriptome assembly pipeline from short RNA-Seq reads on June 3, 2010 at the "Sequencing, Finishing, Analysis in the Future" meeting in Santa Fe, NM

  16. Gas Pipelines (Texas)

    Broader source: Energy.gov [DOE]

    This chapter applies to any entity that owns, manages, operates, leases, or controls a pipeline for the purpose of transporting natural gas in the state for sale or compensation, as well as any...

  17. New Mexico Water Resources Research Institute, New Mexico State University http://wrri.nmsu.edu Utilization of Saline and Other Impaired Waters for

    E-Print Network [OSTI]

    Johnson, Eric E.

    used for turf irrigation and increase the efficiency of irrigation systems in turf areas. The study irrigation systems on changes in soil chemical properties at several depths in the turfgrass root zone://wrri.nmsu.edu Utilization of Saline and Other Impaired Waters for Turfgrass Irrigation Bernd Leinauer, Extension Plant

  18. Licensing for tritium production in a commercial light water reactor: A utility view

    SciTech Connect (OSTI)

    Chardos, J.S.; Sorensen, G.C.; Erickson, L.W.

    2000-07-01T23:59:59.000Z

    In a December 1995 Record of Decision for the Final Programmatic Environmental Impact Statement for Tritium Supply and Recycling, the US Department of Energy (DOE) decided to pursue a dual-track approach to determine the preferred option for future production of tritium for the nuclear weapons stockpile. The two options to be pursued were (a) the Accelerator Production of Tritium and (b) the use of commercial light water reactors (CLWRs). DOE committed to select one of these two options as the primary means of tritium production by the end of 1998. The other option would continue to be pursued as a backup to the primary option. The Tennessee Valley Authority (TVA) became involved in the tritium program in early 1996, in response to an inquiry from Pacific Northwest National Laboratory (PNNL) for an expression of interest by utilities operating nuclear power plants (NPPs). In June 1996, TVA was one of two utilities to respond to a request for proposals to irradiate lead test assemblies (LTAs) containing tritium-producing burnable absorber rods (TPBARs). TVA proposed that the LTAs be placed in Watts Bar NPP Unit 1 (WBN). TVA participated with DOE (the Defense Programs Office of CLWR Tritium Production), PNNL, and Westinghouse Electric Company (Westinghouse) in the design process to ensure that the TPBARs would be compatible with safe operation of WBN. Following US Nuclear Regulatory Commission (NRC) issuance of a Safety Evaluation Report (SER) (NUREG-1607), TVA submitted a license amendment request to the NRC for approval to place four LTAs, containing eight TPBARs each, in WBN during the September 1997 refueling outage. In December 1998, DOE announced the selection of the CLWR program as the primary option for tritium production and identified the TVA WBN and Sequoyah NPP (SQN) Units 1 and 2 (SQN-1 and SQN-2, respectively) reactors as the preferred locations to perform tritium production. TVA will prepare license amendment requests for the three plants (WBN, SQN-1, and SQN-2). While the TPBARs replace discreet burnable absorbers in the reactor cores, there are differences in the reactions that occur in the absorber material (lithium aluminate versus boron). At end of life, the lithium aluminate provides considerably more reactivity holddown than the standard boron-containing burnable absorbers. Therefore, it will be necessary for the TVA plant engineering and fuels staffs, working with the fuel vendors, to define the appropriate core loading (number of fresh fuel assemblies, enrichment, etc.) to maintain safe operating limits under both operating and accident conditions. It is recognized that the irradiation of TPBARs in the TVA reactors will also require additional radiological and chemistry program upgrades.

  19. Life Cycle Water Consumption and Water Resource Assessment for Utility-Scale Geothermal Systems: An In-Depth Analysis of Historical and Forthcoming EGS Projects

    SciTech Connect (OSTI)

    Schroeder, Jenna N.

    2013-08-31T23:59:59.000Z

    This report is the third in a series of reports sponsored by the U.S. Department of Energy Geothermal Technologies Program in which a range of water-related issues surrounding geothermal power production are evaluated. The first report made an initial attempt at quantifying the life cycle fresh water requirements of geothermal power-generating systems and explored operational and environmental concerns related to the geochemical composition of geothermal fluids. The initial analysis of life cycle fresh water consumption of geothermal power-generating systems identified that operational water requirements consumed the vast majority of water across the life cycle. However, it relied upon limited operational water consumption data and did not account for belowground operational losses for enhanced geothermal systems (EGSs). A second report presented an initial assessment of fresh water demand for future growth in utility-scale geothermal power generation. The current analysis builds upon this work to improve life cycle fresh water consumption estimates and incorporates regional water availability into the resource assessment to improve the identification of areas where future growth in geothermal electricity generation may encounter water challenges.

  20. Life Cycle Water Consumption and Water Resource Assessment for Utility-Scale Geothermal Systems: An In-Depth Analysis of Historical and Forthcoming EGS Projects

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Schroeder, Jenna N.

    This report is the third in a series of reports sponsored by the U.S. Department of Energy Geothermal Technologies Program in which a range of water-related issues surrounding geothermal power production are evaluated. The first report made an initial attempt at quantifying the life cycle fresh water requirements of geothermal power-generating systems and explored operational and environmental concerns related to the geochemical composition of geothermal fluids. The initial analysis of life cycle fresh water consumption of geothermal power-generating systems identified that operational water requirements consumed the vast majority of water across the life cycle. However, it relied upon limited operational water consumption data and did not account for belowground operational losses for enhanced geothermal systems (EGSs). A second report presented an initial assessment of fresh water demand for future growth in utility-scale geothermal power generation. The current analysis builds upon this work to improve life cycle fresh water consumption estimates and incorporates regional water availability into the resource assessment to improve the identification of areas where future growth in geothermal electricity generation may encounter water challenges.

  1. Pipeline Safety Program Oak Ridge National Laboratory

    E-Print Network [OSTI]

    programs prepared by pipeline operators in accordance with Federal pipeline safety regulations, grounding, and interference, · environmentally sensitive areas, · federal pipeline safety regulationsPipeline Safety Program Oak Ridge National Laboratory managed by UT-Battelle, LLC for the U

  2. Life Cycle Water Consumption and Water Resource Assessment for Utility-Scale Geothermal Systems: An In-Depth Analysis of Historical and Forthcoming EGS Projects

    SciTech Connect (OSTI)

    Clark, Corrie E. [Environmental Science Division] [Environmental Science Division; Harto, Christopher B. [Environmental Science Division] [Environmental Science Division; Schroeder, Jenna N. [Environmental Science Division] [Environmental Science Division; Martino, Louis E. [Environmental Science Division] [Environmental Science Division; Horner, Robert M. [Environmental Science Division] [Environmental Science Division

    2013-11-05T23:59:59.000Z

    This report is the third in a series of reports sponsored by the U.S. Department of Energy Geothermal Technologies Program in which a range of water-related issues surrounding geothermal power production are evaluated. The first report made an initial attempt at quantifying the life cycle fresh water requirements of geothermal power-generating systems and explored operational and environmental concerns related to the geochemical composition of geothermal fluids. The initial analysis of life cycle fresh water consumption of geothermal power-generating systems identified that operational water requirements consumed the vast majority of water across the life cycle. However, it relied upon limited operational water consumption data and did not account for belowground operational losses for enhanced geothermal systems (EGSs). A second report presented an initial assessment of fresh water demand for future growth in utility-scale geothermal power generation. The current analysis builds upon this work to improve life cycle fresh water consumption estimates and incorporates regional water availability into the resource assessment to improve the identification of areas where future growth in geothermal electricity generation may encounter water challenges. This report is divided into nine chapters. Chapter 1 gives the background of the project and its purpose, which is to assess the water consumption of geothermal technologies and identify areas where water availability may present a challenge to utility-scale geothermal development. Water consumption refers to the water that is withdrawn from a resource such as a river, lake, or nongeothermal aquifer that is not returned to that resource. The geothermal electricity generation technologies evaluated in this study include conventional hydrothermal flash and binary systems, as well as EGSs that rely on engineering a productive reservoir where heat exists, but where water availability or permeability may be limited. Chapter 2 describes the approach and methods for this work and identifies the four power plant scenarios evaluated: a 20-MW EGS binary plant, a 50-MW EGS binary plant, a 10-MW hydrothermal binary plant, and a 50-MW hydrothermal flash plant. The methods focus on (1) the collection of data to improve estimation of EGS stimulation volumes, aboveground operational consumption for all geothermal technologies, and belowground operational consumption for EGS; and (2) the mapping of the geothermal and water resources of the western United States to assist in the identification of potential water challenges to geothermal growth. Chapters 3 and 4 present the water requirements for the power plant life cycle. Chapter 3 presents the results of the current data collection effort, and Chapter 4 presents the normalized volume of fresh water consumed at each life cycle stage per lifetime energy output for the power plant scenarios evaluated. Over the life cycle of a geothermal power plant, from construction through 30 years of operation, the majority of water is consumed by plant operations. For the EGS binary scenarios, where dry cooling was assumed, belowground operational water loss is the greatest contributor depending upon the physical and operational conditions of the reservoir. Total life cycle water consumption requirements for air-cooled EGS binary scenarios vary between 0.22 and 1.85 gal/kWh, depending upon the extent of belowground operational water consumption. The air-cooled hydrothermal binary and flash plants experience far less fresh water consumption over the life cycle, at 0.04 gal/kWh. Fresh water requirements associated with air- cooled binary operations are primarily from aboveground water needs, including dust control, maintenance, and domestic use. Although wet-cooled hydrothermal flash systems require water for cooling, these plants generally rely upon the geofluid, fluid from the geothermal reservoir, which typically has high salinity and total dissolved solids concentration and is much warmer than normal groundwater sources, for their cooling water needs; thus,

  3. Gas Pipeline Safety (West Virginia)

    Broader source: Energy.gov [DOE]

    The Gas Pipeline Safety Section of the Engineering Division is responsible for the application and enforcement of pipeline safety regulations under Chapter 24B of the West Virginia Code and 49 U.S...

  4. Programmable Graphics Pipelines Anjul Patney

    E-Print Network [OSTI]

    Yoo, S. J. Ben

    Programmable Graphics Pipelines By Anjul Patney B.Tech. (Indian Institute of Technology Delhi) 2007 as Abstractions for Computer Graphics 5 2.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 2.2 Modern Graphics Pipelines . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 2

  5. CASE CRITICAL Keystone XL Pipeline

    E-Print Network [OSTI]

    Hall, Sharon J.

    CASE CRITICAL Keystone XL Pipeline: A Line in the Sand? Case Critical is presented by ASU's Global Professor, ASU's School of Geographical Sciences and Urban Planning The Keystone XL Pipeline, a large

  6. PID control of gas pipelines

    SciTech Connect (OSTI)

    Coltharp, B.; Bergmann, J. [Baker CAC, Kingwood, TX (United States)

    1996-09-01T23:59:59.000Z

    The use of low cost digital controllers for pipeline control is increasing as the reliability and cost improves. In pipeline applications, the proportional, integral, and derivative (PID) controller algorithm is often used. However, the unique problems associated with pipeline operation have caused manufacturers to modify the basic control algorithms. Features such as set point ramping, built in pressure control, freeze on input error, and high and low output limits help assure safe and predictable pipeline operation.

  7. A Low-Cost Natural Gas/Freshwater Aerial Pipeline

    E-Print Network [OSTI]

    Alexander Bolonkin; Richard Cathcart

    2007-01-05T23:59:59.000Z

    Offered is a new type of low-cost aerial pipeline for delivery of natural gas, an important industrial and residential fuel, and freshwater as well as other payloads over long distances. The offered pipeline dramatically decreases the construction and operation costs and the time necessary for pipeline construction. A dual-use type of freight pipeline can improve an arid rural environment landscape and provide a reliable energy supply for cities. Our aerial pipeline is a large, self-lofting flexible tube disposed at high altitude. Presently, the term "natural gas" lacks a precise technical definition, but the main components of natural gas are methane, which has a specific weight less than air. A lift force of one cubic meter of methane equals approximately 0.5 kg. The lightweight film flexible pipeline can be located in the Earth-atmosphere at high altitude and poses no threat to airplanes or the local environment. The authors also suggest using lift force of this pipeline in tandem with wing devices for cheap shipment of a various payloads (oil, coal and water) over long distances. The article contains a computed macroproject in northwest China for delivery of 24 billion cubic meter of gas and 23 millions tonnes of water annually.

  8. The Influence of Residential Solar Water Heating on Electric Utility Demand 

    E-Print Network [OSTI]

    Vliet, G. C.; Askey, J. L.

    1984-01-01T23:59:59.000Z

    Similar sets of residences in Austin, Texas with electric water heaters and solar water heaters with electric back-up were monitored during 1982 to determine their instantaneous electric demands, the purpose being to determine the influence...

  9. The Influence of Residential Solar Water Heating on Electric Utility Demand

    E-Print Network [OSTI]

    Vliet, G. C.; Askey, J. L.

    1984-01-01T23:59:59.000Z

    Similar sets of residences in Austin, Texas with electric water heaters and solar water heaters with electric back-up were monitored during 1982 to determine their instantaneous electric demands, the purpose being to determine the influence...

  10. Using Natural Gas Transmission Pipeline Costs to Estimate Hydrogen Pipeline Costs

    E-Print Network [OSTI]

    Parker, Nathan

    2004-01-01T23:59:59.000Z

    future estimates of hydrogen pipelines. Construction Cost (does this mean for hydrogen pipelines? The objective of thisinto the cost of hydrogen pipelines. To this end I will

  11. Mobile sensor network to monitor wastewater collection pipelines

    E-Print Network [OSTI]

    Lim, Jungsoo

    2012-01-01T23:59:59.000Z

    Advanced pipeline monitoringDesign of mobile pipeline floating sensor “SewerSnortIllustration of mobile pipeline floating sensor monitoring

  12. Data-stationary pipelined machine

    SciTech Connect (OSTI)

    Abdou, I.E.

    1984-01-01T23:59:59.000Z

    The paper presents the data-stationary control concept of pipelined machines, with emphasis on its application in image processing systems. A parallel array of pipelined machines for image processing is considered, and data-stationary control is compared with time-stationary control. A system is proposed that is a parallel array of pipelined machines. Each pipeline is a multifunctional, statically configured, data-stationary device. The pipelines do not accommodate branching instructions or interrupts, and the design focus on vector processing only. The system can be used in other applications such as signal processing and arithmetic number crunching. 5 references.

  13. Deliverability on the interstate natural gas pipeline system

    SciTech Connect (OSTI)

    NONE

    1998-05-01T23:59:59.000Z

    Deliverability on the Interstate Natural Gas Pipeline System examines the capability of the national pipeline grid to transport natural gas to various US markets. The report quantifies the capacity levels and utilization rates of major interstate pipeline companies in 1996 and the changes since 1990, as well as changes in markets and end-use consumption patterns. It also discusses the effects of proposed capacity expansions on capacity levels. The report consists of five chapters, several appendices, and a glossary. Chapter 1 discusses some of the operational and regulatory features of the US interstate pipeline system and how they affect overall system design, system utilization, and capacity expansions. Chapter 2 looks at how the exploration, development, and production of natural gas within North America is linked to the national pipeline grid. Chapter 3 examines the capability of the interstate natural gas pipeline network to link production areas to market areas, on the basis of capacity and usage levels along 10 corridors. The chapter also examines capacity expansions that have occurred since 1990 along each corridor and the potential impact of proposed new capacity. Chapter 4 discusses the last step in the transportation chain, that is, deliverability to the ultimate end user. Flow patterns into and out of each market region are discussed, as well as the movement of natural gas between States in each region. Chapter 5 examines how shippers reserve interstate pipeline capacity in the current transportation marketplace and how pipeline companies are handling the secondary market for short-term unused capacity. Four appendices provide supporting data and additional detail on the methodology used to estimate capacity. 32 figs., 15 tabs.

  14. Enhancing protection for unusually sensitive ecological areas from pipeline releases

    E-Print Network [OSTI]

    Sames, Christina; Fink, Dennis

    2001-01-01T23:59:59.000Z

    ECOLOGICAL AREAS FROM PIPELINE RELEASES Christina Sames;Administration, Office of Pipeline Safety, DPS-10/ 400 7thof a hazardous liquid pipeline accident. Pipeline operators

  15. The SINFONI pipeline

    E-Print Network [OSTI]

    Andrea Modigliani; Wolfgang Hummel; Roberto Abuter; Paola Amico; Pascal Ballester; Richard Davies; Christophe Dumas; Mattew Horrobin; Mark Neeser; Markus Kissler-Patig; Michele Peron; Juha Rehunanen; Juergen Schreiber; Thomas Szeifert

    2007-02-05T23:59:59.000Z

    The SINFONI data reduction pipeline, as part of the ESO-VLT Data Flow System, provides recipes for Paranal Science Operations, and for Data Flow Operations at Garching headquarters. At Paranal, it is used for the quick-look data evaluation. For Data Flow Operations, it fulfills several functions: creating master calibrations; monitoring instrument health and data quality; and reducing science data for delivery to service mode users. The pipeline is available to the science community for reprocessing data with personalised reduction strategies and parameters. The pipeline recipes can be executed either with EsoRex at the command line level or through the Gasgano graphical user interface. The recipes are implemented with the ESO Common Pipeline Library (CPL). SINFONI is the Spectrograph for INtegral Field Observations in the Near Infrared (1.1-2.45 um) at the ESO-VLT. SINFONI was developed and build by ESO and MPE in collaboration with NOVA. It consists of the SPIFFI integral field spectrograph and an adaptive optics module which allows diffraction limited and seeing limited observations. The image slicer of SPIFFI chops the SINFONI field of view on the sky in 32 slices which are re-arranged to a pseudo slit. The latter is dispersed by one of the four possible gratings (J, H, K, H+K). The detector thus sees a spatial dimension (along the pseudo-slit) and a spectral dimension. We describe in this paper the main data reduction procedures of the SINFONI pipeline, which is based on SPRED - the SPIFFI data reduction software developed by MPE, and the most recent developments after more than a year of SINFONI operations.

  16. Kern River natural gas pipeline commissioned

    SciTech Connect (OSTI)

    Not Available

    1992-03-16T23:59:59.000Z

    Kern River Gas Transmission Co., the biggest gas pipeline built in the U.S. in the last decade, has been commissioned. The system was dedicated Mar. 6 at a meter station in an oil field near Bakersfield, Calif. The $984 million, 904 mile pipeline is a 50-50 venture of Tenneco Inc. and Williams Cos. Planning for the project began about 7 years ago. Current operating capacity of the line is 700 MMcfd. Plans call for boosting capacity by 452 MMcfd with added compression. Most of the gas will go to thermal enhanced oil recovery projects in heavy oil fields in California. This paper reports that other customers include utilities, independent electrical power producers, and cogeneration projects.

  17. Parallel finite element method utilizing the mode splitting and sigma coordinate for shallow water flows

    E-Print Network [OSTI]

    Tezduyar, Tayfun E.

    the sediment transport, the dispersion of contaminants, the exchange of sea water and so on accurately for the shallow water ¯ow based on the two di- mensional model have been presented in the past. The present, it is necessary to evaluate the vertical velocity pro®le. Several quasi-three dimen- sional models have been also

  18. Improved water allocation utilizing probabilistic climate forecasts: Short-term water contracts in a risk management framework

    E-Print Network [OSTI]

    Arumugam, Sankar

    . Thus, integrated supply and demand management can be achieved. In this paper, a single period multiuser, forecast consumers, water managers and reservoir operators, have difficulty interpreting such products in a risk management framework A. Sankarasubramanian,1 Upmanu Lall,2 Francisco Assis Souza Filho,3

  19. Economically Optimum Agricultural Utilization of a Reclaimed Water Resource in the Texas Rolling Plains

    E-Print Network [OSTI]

    Zacharias, T.; Taylor, C. R.; Lacewell, R. D.

    the effects of the initial assumptions on the measure of project benefits. The first scenario applied guidelines established by the Water Resources Council (WRC). WRC guidelines required the use of OBERS SERIES E' yield projections, normalized prices...

  20. Automation of Pivot Sprinkler Irrigation Systems to More Efficiently Utilize Rainfall and Irrigation Water

    E-Print Network [OSTI]

    Wendt, C. W.; Runkles, J. R.; Gerst, M. D.; Harbert, H. P. III; Hutmacher, R. B.

    A study was conducted to develop automated pivot sprinkler irrigation systems and determine if such systems use less water and energy than manually operated systems. The study was conducted near Earth, Texas, using irrigation systems located...

  1. DOE Hydrogen Pipeline Working Group Workshop

    E-Print Network [OSTI]

    Laporte, TX to near Lake Charles, LA. This system has approximately 228 miles of DOT regulated H2 pipeline of DOT regulated H2 pipeline. Portions of this system operating since early 1983. Pipeline sizeDOE Hydrogen Pipeline Working Group Workshop August 31, 2005 Augusta, Georgia #12;Hydrogen Pipeline

  2. Instrumented Pipeline Initiative

    SciTech Connect (OSTI)

    Thomas Piro; Michael Ream

    2010-07-31T23:59:59.000Z

    This report summarizes technical progress achieved during the cooperative agreement between Concurrent Technologies Corporation (CTC) and U.S. Department of Energy to address the need for a for low-cost monitoring and inspection sensor system as identified in the Department of Energy (DOE) National Gas Infrastructure Research & Development (R&D) Delivery Reliability Program Roadmap.. The Instrumented Pipeline Initiative (IPI) achieved the objective by researching technologies for the monitoring of pipeline delivery integrity, through a ubiquitous network of sensors and controllers to detect and diagnose incipient defects, leaks, and failures. This report is organized by tasks as detailed in the Statement of Project Objectives (SOPO). The sections all state the objective and approach before detailing results of work.

  3. The relationship between soil water utilization and the phosphorus status of sorghum

    E-Print Network [OSTI]

    Sow, Abdoul Abdoulaye

    1990-01-01T23:59:59.000Z

    if water use efficiency is a function of P fertilization. Grain sorghum cultivars, CSM 63, a cultivai from Mali and an improved cultivsr, Tx 7078 -1 were grown at four levels ol' P fertilization (0, 15, 30, and 60 mg P kg soil) and two levels... grain yield as CSM 63 despite the fact that it is a non-tillering cultivar with fewer heads at harvest. Higher total dry matter and grain yields were obtained v, 'hen plants were groivn without water stress. Total dry matter produced at anthesis...

  4. Hydrodynamic forces on piggyback pipelines

    SciTech Connect (OSTI)

    Jakobsen, M.L.; Sayer, P. [Univ. of Strathclyde, Glasgow (United Kingdom)

    1995-12-31T23:59:59.000Z

    An increasing number of new offshore pipelines have been designed as bundles, mainly because of overall cost reductions. One popular way of combining two pipelines with different diameters is the piggyback configuration, with the smaller pipeline strapped on top of the main pipeline. The external hydrodynamic forces on this combination are at present very roughly estimated; pipeline engineers need more data to support their designs. This paper presents experimental results for the in-line hydrodynamic loading on three different piggyback set-ups. The models comprised a 0.4 m main pipeline, and three piggyback pipelines with diameters of 0.038 m, 0.059 m and 0.099 m. Each small pipeline was separately mounted to the main pipeline, with a gap equal to its own diameter. These model sizes lie approximately between half- and full-scale. Experiments were undertaken for K{sub C} between 5 and 42, and R{sub e} in the range 0.0 * 10{sup 4} to 8.5 * 10{sup 5}. The results based on Morison`s equation indicate that a simple addition of the separate forces acting on each cylinder underestimates the actual force by up to 35% at low K{sub C} (< {approximately} 10) and by as much as 100% in the drag-dominated regime (K{sub C} > {approximately} 20).

  5. RNA-Seq Pipeline in Galaxy

    E-Print Network [OSTI]

    Meng, Xiandong

    2014-01-01T23:59:59.000Z

    Assembly in Galaxy RNA-Seq q Pipeline p • QC : To find outRNA-Seq Pipeline in Galaxy Xiandong Meng 1 , Jeffrey Martinof California RNA--Seq Pipeline in Galaxy RNA Xiandong Meng

  6. Leaking Pipelines: Doctoral Student Family Formation

    E-Print Network [OSTI]

    Serrano, Christyna M.

    2008-01-01T23:59:59.000Z

    Sari M. “Why the Academic Pipeline Leaks: Fewer Men thanone reason the academic pipeline leaks. 31 Blair-Loy, Mary.to leak out of the “academic pipeline. ” The term “academic

  7. EIA - Natural Gas Pipeline Network - Regional Definitions

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for On-Highway4,1,50022,3,,,,6,1,9,1,50022,3,,,,6,1,Decade Year-0E (2001)gasoline353/06)Pipeline Utilization &

  8. EIA - Natural Gas Pipeline Network - Regulatory Authorities

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for On-Highway4,1,50022,3,,,,6,1,9,1,50022,3,,,,6,1,Decade Year-0E (2001)gasoline353/06)Pipeline Utilization &Overview

  9. Detection of the internal corrosion in pipeline

    E-Print Network [OSTI]

    2006-10-17T23:59:59.000Z

    Detection of the internal corrosion in pipeline. Hyeonbae Kang. In this talk I will explain our new methods to detect internal corrosions in pipelines.

  10. Machinist Pipeline/Apprentice Program Program Description

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Machinist PipelineApprentice Program Program Description The Machinist Pipeline Program was created by the Prototype Fabrication Division to fill a critical need for skilled...

  11. Economic and Conservation Evaluation of Capital Renovation Projects: Edinburg Irrigation District Hidalgo County No. 1 - 72" Pipeline Replacing Delivery Canal and Multi-Size Pipeline Replacing Delivery Canal 

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.; Ellis, John R.

    2002-01-01T23:59:59.000Z

    ). Both nominal and real, expected economic and financial costs of water and energy savings are identified throughout the anticipated useful lives for both components of the proposed project (i.e., 72" pipeline replacing a segment of delivery canal along...

  12. Economic and Financial Costs of Saving Water and Energy: Preliminary Analysis for Hidalgo County Irrigation District No. 2 (San Juan) – Replacement of Pipeline Units I-7A, I-18, and I-22

    E-Print Network [OSTI]

    Sturdivant, Allen W.; Rister, M. Edward; Lacewell, Ronald D.

    to the project’s construction cost when evaluating the cost of saving water. The historic average diversion-energy usage level of 201,384 BTU {59.02 kwh} per ac-ft of water diverted (by the District) for calendar years 2002-2006 is used to estimate energy... or longer period is possible, but 49 years is considered reasonable and consistent with engineering expectations (Michalewicz). Sensitivity analyses are utilized to examine the effects of this assumption. Initial Construction Costs: Total initial...

  13. Direct utilization of geothermal energy for space and water heating at Marlin, Texas. Final report

    SciTech Connect (OSTI)

    Conover, M.F.; Green, T.F.; Keeney, R.C.; Ellis, P.F. II; Davis, R.J.; Wallace, R.C.; Blood, F.B.

    1983-05-01T23:59:59.000Z

    The Torbett-Hutchings-Smith Memorial Hospital geothermal heating project, which is one of nineteen direct-use geothermal projects funded principally by DOE, is documented. The five-year project encompassed a broad range of technical, institutional, and economic activities including: resource and environmental assessments; well drilling and completion; system design, construction, and monitoring; economic analyses; public awareness programs; materials testing; and environmental monitoring. Some of the project conclusions are that: (1) the 155/sup 0/F Central Texas geothermal resource can support additional geothermal development; (2) private-sector economic incentives currently exist, especially for profit-making organizations, to develop and use this geothermal resource; (3) potential uses for this geothermal resource include water and space heating, poultry dressing, natural cheese making, fruit and vegetable dehydrating, soft-drink bottling, synthetic-rubber manufacturing, and furniture manufacturing; (4) high maintenance costs arising from the geofluid's scaling and corrosion tendencies can be avoided through proper analysis and design; (5) a production system which uses a variable-frequency drive system to control production rate is an attractive means of conserving parasitic pumping power, controlling production rate to match heating demand, conserving the geothermal resource, and minimizing environmental impacts.

  14. Integrated Water Gas Shift Membrane Reactors Utilizing Novel, Non Precious Metal Mixed Matrix Membrane

    SciTech Connect (OSTI)

    Ferraris, John

    2013-09-30T23:59:59.000Z

    Nanoparticles of zeolitic imidazolate frameworks and other related hybrid materials were prepared by modifying published synthesis procedures by introducing bases, changing stoichiometric ratios, or adjusting reaction conditions. These materials were stable at temperatures >300 °C and were compatible with the polymer matrices used to prepare mixed- matrix membranes (MMMs). MMMs tested at 300 °C exhibited a >30 fold increase in permeability, compared to those measured at 35 °C, while maintaining H{sub 2}/CO{sub 2} selectivity. Measurements at high pressure (up to 30 atm) and high temperature (up to 300 °C) resulted in an increase in gas flux across the membrane with retention of selectivity. No variations in permeability were observed at high pressures at either 35 or 300 °C. CO{sub 2}-induced plasticization was not observed for Matrimid®, VTEC, and PBI polymers or their MMMs at 30 atm and 300 °C. Membrane surface modification by cross-linking with ethanol diamine resulted in an increase in H{sub 2}/CO{sub 2} selectivity at 35 °C. Spectrometric analysis showed that the cross-linking was effective to temperatures <150 °C. At higher temperatures, the cross-linked membranes exhibit a H{sub 2}/CO{sub 2} selectivity similar to the uncross-linked polymer. Performance of the polybenzimidazole (PBI) hollow fibers prepared at Santa Fe Science and Technology (SFST, Inc.) showed increased flux o to a flat PBI membrane. A water-gas shift reactor has been built and currently being optimized for testing under DOE conditions.

  15. Questions and Issues on Hydrogen Pipelines: Pipeline Transmission...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Pipping of GH2 Pipeline. Background: FG 64 built in 50ies, KP added in 70ies, active mining area over total length hpwgwquestissuescampbell.pdf More Documents & Publications...

  16. The LOFAR Transients Pipeline

    E-Print Network [OSTI]

    Swinbank, John D; Molenaar, Gijs J; Rol, Evert; Rowlinson, Antonia; Scheers, Bart; Spreeuw, Hanno; Bell, Martin E; Broderick, Jess W; Carbone, Dario; van der Horst, Alexander J; Law, Casey J; Wise, Michael; Breton, Rene P; Cendes, Yvette; Corbel, Stéphane; Eislöffel, Jochen; Falcke, Heino; Fender, Rob; Greißmeier, Jean-Mathias; Hessels, Jason W T; Stappers, Benjamin W; Stewart, Adam J; Wijers, Ralph A M J; Wijnands, Rudy; Zarka, Philippe

    2015-01-01T23:59:59.000Z

    Current and future astronomical survey facilities provide a remarkably rich opportunity for transient astronomy, combining unprecedented fields of view with high sensitivity and the ability to access previously unexplored wavelength regimes. This is particularly true of LOFAR, a recently-commissioned, low-frequency radio interferometer, based in the Netherlands and with stations across Europe. The identification of and response to transients is one of LOFAR's key science goals. However, the large data volumes which LOFAR produces, combined with the scientific requirement for rapid response, make automation essential. To support this, we have developed the LOFAR Transients Pipeline, or TraP. The TraP ingests multi-frequency image data from LOFAR or other instruments and searches it for transients and variables, providing automatic alerts of significant detections and populating a lightcurve database for further analysis by astronomers. Here, we discuss the scientific goals of the TraP and how it has been desig...

  17. About U.S. Natural Gas Pipelines

    Reports and Publications (EIA)

    2007-01-01T23:59:59.000Z

    This information product provides the interested reader with a broad and non-technical overview of how the U.S. natural gas pipeline network operates, along with some insights into the many individual pipeline systems that make up the network. While the focus of the presentation is the transportation of natural gas over the interstate and intrastate pipeline systems, information on subjects related to pipeline development, such as system design and pipeline expansion, are also included.

  18. Water Efficiency

    Energy Savers [EERE]

    Water Efficiency Hosted by: FEDERAL UTILITY PARTNERSHIP WORKING GROUP SEMINAR November 5-6, 2014 Cape Canaveral, Florida WATER EFFICIENCY Federal Utility Partnership Working Group...

  19. Using Natural Gas Transmission Pipeline Costs to Estimate Hydrogen Pipeline Costs

    E-Print Network [OSTI]

    Parker, Nathan

    2004-01-01T23:59:59.000Z

    Warren R. “U.S. interstate pipelines begin 1993 on upbeat. ”66. ? True, Warren R. “Current pipeline costs. ” Oil & GasWarren R. “U.S. interstate pipelines ran more efficiently in

  20. Hydrogen permeability and Integrity of hydrogen transfer pipelines...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    permeability and Integrity of hydrogen transfer pipelines Hydrogen permeability and Integrity of hydrogen transfer pipelines Presentation by 03-Babu for the DOE Hydrogen Pipeline...

  1. Latinas Straddling the Prison Pipeline through Gender (Non) Conformity

    E-Print Network [OSTI]

    Caraves, Jacqueline

    2014-01-01T23:59:59.000Z

    the School-to-Prison Pipeline/Building Abolition Futures.rights/school-prison-pipeline Retrieved: September 12, 2014Chicano Educational Pipeline. New York: Routledge ------(

  2. The pipeline and future of drug development in schizophrenia

    E-Print Network [OSTI]

    Gray, J A; Roth, B L

    2007-01-01T23:59:59.000Z

    The Pipeline and Future of Drug Development in SchizophreniaThe Drug Discovery Pipeline in Schizophrenia Keywords:discuss the current pipeline of drugs for schizophrenia,

  3. PIPELINES AS COMMUNICATION NETWORK LINKS

    SciTech Connect (OSTI)

    Kelvin T. Erickson; Ann Miller; E. Keith Stanek; C.H. Wu; Shari Dunn-Norman

    2005-03-14T23:59:59.000Z

    This report presents the results of an investigation into two methods of using the natural gas pipeline as a communication medium. The work addressed the need to develop secure system monitoring and control techniques between the field and control centers and to robotic devices in the pipeline. In the first method, the pipeline was treated as a microwave waveguide. In the second method, the pipe was treated as a leaky feeder or a multi-ground neutral and the signal was directly injected onto the metal pipe. These methods were tested on existing pipeline loops at UMR and Batelle. The results reported in this report indicate the feasibility of both methods. In addition, a few suitable communication link protocols for this network were analyzed.

  4. Decoupled Sampling for Graphics Pipelines

    E-Print Network [OSTI]

    Ragan-Kelley, Jonathan Millar

    We propose a generalized approach to decoupling shading from visibility sampling in graphics pipelines, which we call decoupled sampling. Decoupled sampling enables stochastic supersampling of motion and defocus blur at ...

  5. Common Pipeline Carriers (North Dakota)

    Broader source: Energy.gov [DOE]

    Any entity that owns, operates, or manages a pipeline for the purpose of transporting crude petroleum, gas, coal, or carbon dioxide within or through the state of North Dakota, or is engaged in the...

  6. Pipeline Processing of VLBI Data

    E-Print Network [OSTI]

    C. Reynolds; Z. Paragi; M. Garrett

    2002-05-08T23:59:59.000Z

    As part of an on-going effort to simplify the data analysis path for VLBI experiments, a pipeline procedure has been developed at JIVE to carry out much of the data reduction required for EVN experiments in an automated fashion. This pipeline procedure runs entirely within AIPS, the standard data reduction package used in astronomical VLBI, and is used to provide preliminary calibration of EVN experiments correlated at the EVN MkIV data processor. As well as simplifying the analysis for EVN users, the pipeline reduces the delay in providing information on the data quality to participating telescopes, hence improving the overall performance of the array. A description of this pipeline is presented here.

  7. Gas Pipelines, County Roads (Indiana)

    Broader source: Energy.gov [DOE]

    A contract with any Board of County Commissioners is required prior to the construction of a pipeline, conduit, or private drain across or along any county highway. The contract will include terms...

  8. Pipelines programming paradigms: Prefab plumbing

    SciTech Connect (OSTI)

    Boeheim, C.

    1991-08-01T23:59:59.000Z

    Mastery of CMS Pipelines is a process of learning increasingly sophisticated tools and techniques that can be applied to your problem. This paper presents a compilation of techniques that can be used as a reference for solving similar problems

  9. EIA - Natural Gas Pipeline Network - U.S. Natural Gas Pipeline Network Map

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for On-Highway4,1,50022,3,,,,6,1,9,1,50022,3,,,,6,1,Decade Year-0E (2001)gasoline353/06)Pipeline UtilizationProcess and

  10. EIS-0140: Ocean State Power Project, Tennessee Gas Pipeline Company

    Broader source: Energy.gov [DOE]

    The Federal Energy Regulatory Commission prepared this statement to evaluate potential impacts of construction and operation of a new natural gas-fired, combined-cycle power plant which would be located on a 40.6-acre parcel in the town of Burrillville, Rhode Island, as well as construction of a 10-mile pipeline to transport process and cooling water to the plant from the Blackstone River and a 7.5-mile pipeline to deliver No. 2 fuel oil to the site for emergency use when natural gas may not be available. The Economic Regulatory Administration adopted the EIS on 7/15/1988.

  11. The validity of analytical methods for predicting self burial of offshore pipelines

    E-Print Network [OSTI]

    Hamilton, Thomas Kenwood

    1977-01-01T23:59:59.000Z

    . To accomplish this, the pipeline is filled with water and tested at pressures equal to approximately 125% of the design maximum operating pressure (41). During this phase, the static loading consists of the weight of the submerged pipe plus the water... techn1ques. For example, the state of equilibrium resulting from a pipeline sinking until the soil pressure is sufficient for support is somewhat d1fferent from the static conditions on wh1ch bearing capacity equations have been derived. However...

  12. Natural disasters and the gas pipeline system. Topical report, August 1994-June 1995

    SciTech Connect (OSTI)

    Atallah, S.; Saxena, S.; Martin, S.B.; Willowby, A.B.; Alger, R.

    1996-11-15T23:59:59.000Z

    Episodic descriptions are provided of the effect of the Loma Prieta earthquake (1989) on the gas pipeline systems of Pacific Gas & Electric Company and the City of Palo Alto and of the Northridge earthquake (1994) on Southern California Gas` pipeline system. The emergency response plans and activities of South Carolina Electric & Gas Company during hurricane Hugo (1989) and of City Gas Company of Florida and other small gas companies during hurricane Andrew (1992) are also reviewed. Descriptions of the great Flood of 1993 and its effects on the operations of Iowa-Illinois Gas & Electric Company and Laclede Gas Company and of the San Jacinto River Floods on the transmission lines of Valero Gas Co. are also provided. Local and federal regulatory requirements, and the current practices by the gas industry for dealing with natural disasters, such as through preventive measures (e.g., strapping of water heaters, excess flow valves), and the tracking of weather-related events are described. The important role that preplanning and coordination with the local emergency response bodies and other gas utilities plays during a natural disaster is examined.

  13. Pipeline bottoming cycle study. Final report

    SciTech Connect (OSTI)

    Not Available

    1980-06-01T23:59:59.000Z

    The technical and economic feasibility of applying bottoming cycles to the prime movers that drive the compressors of natural gas pipelines was studied. These bottoming cycles convert some of the waste heat from the exhaust gas of the prime movers into shaft power and conserve gas. Three typical compressor station sites were selected, each on a different pipeline. Although the prime movers were different, they were similar enough in exhaust gas flow rate and temperature that a single bottoming cycle system could be designed, with some modifications, for all three sites. Preliminary design included selection of the bottoming cycle working fluid, optimization of the cycle, and design of the components, such as turbine, vapor generator and condensers. Installation drawings were made and hardware and installation costs were estimated. The results of the economic assessment of retrofitting bottoming cycle systems on the three selected sites indicated that profitability was strongly dependent upon the site-specific installation costs, how the energy was used and the yearly utilization of the apparatus. The study indicated that the bottoming cycles are a competitive investment alternative for certain applications for the pipeline industry. Bottoming cycles are technically feasible. It was concluded that proper design and operating practices would reduce the environmental and safety hazards to acceptable levels. The amount of gas that could be saved through the year 2000 by the adoption of bottoming cycles for two different supply projections was estimated as from 0.296 trillion ft/sup 3/ for a low supply projection to 0.734 trillion ft/sup 3/ for a high supply projection. The potential market for bottoming cycle equipment for the two supply projections varied from 170 to 500 units of varying size. Finally, a demonstration program plan was developed.

  14. Economic and Conservation Evaluation of Capital Renovation Projects: Edinburg Irrigation District Hidalgo County No. 1 - 72" Pipeline Replacing Delivery Canal and Multi-Size Pipeline Replacing Delivery Canal

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.; Ellis, John R.

    TR-205 November 2002 Economic and Conservation Evaluation of Capital Renovation Projects: Edinburg Irrigation District Hidalgo County No. 1 – 72" Pipeline Replacing Delivery Canal and Multi-Size Pipeline Replacing Delivery Canal M. Edward Rister... Ronald D. Lacewell Allen W. Sturdivant John R. C. Robinson Michael C. Popp John R. Ellis Texas Water Resources Institute Texas A&M University TR-205 November 2002 Economic and Conservation Evaluation of Capital Renovation Projects: Edinburg...

  15. Cooling Semiconductor Manufacturing Facilities with Chilled Water Storage 

    E-Print Network [OSTI]

    Fiorino, D. P.

    1995-01-01T23:59:59.000Z

    of 35 psig was applied to the 36" diameter return header in the basement of the Central Utility Plant by a pressure-activated make-up valve. In addition, a hydro-pneumatic tank allowed for expansion. Chilled water was supplied at 42"F year... and a 5,000 gpm peak chilled water flow rate (1.33 gpmlton). Outside ofDPIIDMOS5, a pair of 600' long, 18" diameter overhead welded-steel primary chilled water pipelines were direct-connected with the Expressway manufacturing complex's existing...

  16. REMOTE DETECTION OF INTERNAL PIPELINE CORROSION USING FLUIDIZED SENSORS

    SciTech Connect (OSTI)

    Narasi Sridhar; Garth Tormoen; Ashok Sabata

    2005-10-31T23:59:59.000Z

    Pipelines present a unique challenge to monitoring because of the great geographical distances they cover, their burial depth, their age, and the need to keep the product flowing without much interruption. Most other engineering structures that require monitoring do not pose such combined challenges. In this regard, a pipeline system can be considered analogous to the blood vessels in the human body. The human body has an extensive ''pipeline'' through which blood and other fluids are transported. The brain can generally sense damage to the system at any location and alert the body to provide temporary repair, unless the damage is severe. This is accomplished through a vast network of fixed and floating sensors combined with a vast and extremely complex communication/decision making system. The project described in this report mimics the distributed sensor system of our body, albeit in a much more rudimentary fashion. Internal corrosion is an important factor in pipeline integrity management. At present, the methods to assess internal corrosion in pipelines all have certain limitations. In-line inspection tools are costly and cannot be used in all pipelines. Because there is a significant time interval between inspections, any impact due to upsets in pipeline operations can be missed. Internal Corrosion Direct Assessment (ICDA) is a procedure that can be used to identify locations of possible internal corrosion. However, the uncertainties in the procedure require excavation and location of damage using more detailed inspection tools. Non-intrusive monitoring techniques can be used to monitor internal corrosion, but these tools also require pipeline excavation and are limited in the spatial extent of corrosion they can examine. Therefore, a floating sensor system that can deposit at locations of water accumulation and communicate the corrosion information to an external location is needed. To accomplish this, the project is divided into four main tasks related to wireless data transmission, corrosion sensor development, sensor system motion and delivery, and consideration of other pipeline operations issues. In the first year of the program, focus was on sensor development and wireless data transmission. The second year of the program, which was discontinued due to funding shortfall, would have focused on further wireless transmission development, packaging of sensor on wireless, and other operational issues. Because, the second year funding has been discontinued, recommendations are made for future studies.

  17. Network Connectivity and Price Convergency: Gas Pipeline Deregulation

    E-Print Network [OSTI]

    De Vany, Arthur; Walls, W. David

    1993-01-01T23:59:59.000Z

    Convergence: Gas Pipeline Deregulation Arthur De Vany W.Price Convergence: Gas Pipeline Deregulation Arthur De Vany

  18. Method and system for pipeline communication

    SciTech Connect (OSTI)

    Richardson; John G. (Idaho Falls, ID)

    2008-01-29T23:59:59.000Z

    A pipeline communication system and method includes a pipeline having a surface extending along at least a portion of the length of the pipeline. A conductive bus is formed to and extends along a portion of the surface of the pipeline. The conductive bus includes a first conductive trace and a second conductive trace with the first and second conductive traces being adapted to conformally couple with a pipeline at the surface extending along at least a portion of the length of the pipeline. A transmitter for sending information along the conductive bus on the pipeline is coupled thereto and a receiver for receiving the information from the conductive bus on the pipeline is also couple to the conductive bus.

  19. Computer Science and Information Technology Student Pipeline

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Student Pipeline Program Description Los Alamos National Laboratory's High Performance Computing and Information Technology Divisions recruit and hire promising...

  20. NAZ EDUCATION PIPELINE the-naz.org

    E-Print Network [OSTI]

    Amin, S. Massoud

    NAZ EDUCATION PIPELINE the-naz.org 1200 W. Broadway #250 | Minneapolis, MN 55411 | Family Academy is a foundational component of the NAZ "cradle to career" pipeline. NAZ families can enroll in the Family Academy college ready. Families and children move through a "cradle to career" pipeline that provides

  1. Modeling and Validation of Pipeline Specifications

    E-Print Network [OSTI]

    Mishra, Prabhat

    -on-Chip design process. Many existing approaches employ a bottom-up approach to pipeline validation, where description language (ADL) constructs, and thus allows a powerful top-down approach to pipeline validationModeling and Validation of Pipeline Specifications PRABHAT MISHRA and NIKIL DUTT University

  2. Reducing the Risks. In the aftermath of a terrorist attack, wastewater utilities may have to contend with decontamination water containing chemical, biological, or radiological substances

    SciTech Connect (OSTI)

    Warren, Linda P.; Hornback, Chris; Strom, Daniel J.

    2006-08-01T23:59:59.000Z

    In the aftermath of a chemical, biological, or radiological (CBR) attack, decontamination of people and infrastructure will be needed. Decontamination inevitably produces wastewater, and wastewater treatment plants (WTPs) need to know how to handle decontamination wastewater. This article describes CBR substances; planning, coordinating, and communicating responses across agencies; planning within a utility; coordination with local emergency managers and first responders; mitigating effects of decontamination wastewater; and mitigating effects on utility personnel. Planning for Decontamination Wastewater: A Guide for Utilities, the document on which this article is based, was developed under a cooperative agreement from the U.S. Environmental Protection Agency by the National Association of Clean Water Agencies (NACWA) and its contractor, CH2MHILL, Inc.

  3. Chris Jesshope! 2. Pipelined and

    E-Print Network [OSTI]

    Jesshope, Chris

    to sequential tasks: Op: A ; B ; C ; D A B C D Pipelined concurrency requires sequences of operations. Given Opi, 0in, we execute sub-tasks concurrently as follows: Opi: Ai+3||Bi+2||Ci+1||Di Ai+3 Bi+2 Ci+1 Di

  4. Overview of pipeline safety legislation

    SciTech Connect (OSTI)

    Caldwell, J. [Caldwell and Associates, Arlington, VA (United States)

    1995-12-31T23:59:59.000Z

    Pipeline regulation in the US as it has been known since 1968 is being changed. Several major actions are occurring in Government that will redirect the focus of pipeline safety regulation and how it is carried out by government and industry. The Congress is proposing to accept risk management as away of regulation and requiring risk assessment and cost analysis on all regulatory requirements. The DOT/OPS is developing a risk-prioritization program for regulatory activities to be used in evaluating existing regulations to identify those that are obsolete and need modifying or eliminating. The pipeline industry is taking on a proactive role in working with Congress and DOT/OPS to develop this agenda. For the first time in the regulatory history of pipeline safety, Congress, DOT/OPS, and the industry are talking to each other and working toward a common goal of less regulation, more flexible regulation, and placing the responsibility for safety in the hands of the industry.

  5. Robot design for leak detection in water-pipe systems

    E-Print Network [OSTI]

    Choi, Changrak

    2012-01-01T23:59:59.000Z

    Leaks are major problem that occur in the water pipelines all around the world. Several reports indicate loss of around 20 to 30 percent of water in the distribution of water through water pipe systems. Such loss of water ...

  6. NRC review of Electric Power Research Institute`s advanced light water reactor utility requirements document. Passive plant designs, chapter 1, project number 669

    SciTech Connect (OSTI)

    Not Available

    1994-08-01T23:59:59.000Z

    The Electric Power Research Institute (EPRI) is preparing a compendium of technical requirements, referred to as the {open_quotes}Advanced Light Water Reactor [ALWR] Utility Requirements Document{close_quotes}, that is acceptable to the design of an ALWR power plant. When completed, this document is intended to be a comprehensive statement of utility requirements for the design, construction, and performance of an ALWR power plant for the 1990s and beyond. The Requirements Document consists of three volumes. Volume 1, {open_quotes}ALWR Policy and Summary of Top-Tier Requirements{close_quotes}, is a management-level synopsis of the Requirements Document, including the design objectives and philosophy, the overall physical configuration and features of a future nuclear plant design, and the steps necessary to take the proposed ALWR design criteria beyond the conceptual design state to a completed, functioning power plant. Volume II consists of 13 chapters and contains utility design requirements for an evolutionary nuclear power plant [approximately 1350 megawatts-electric (MWe)]. Volume III contains utility design requirements for nuclear plants for which passive features will be used in their designs (approximately 600 MWe). In April 1992, the staff of the Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, issued Volume 1 and Volume 2 (Parts 1 and 2) of its safety evaluation report (SER) to document the results of its review of Volumes 1 and 2 of the Requirements Document. Volume 1, {open_quotes}NRC Review of Electric Power Research Institute`s Advanced Light Water Reactor Utility Requirements Document - Program Summary{close_quotes}, provided a discussion of the overall purpose and scope of the Requirements Document, the background of the staff`s review, the review approach used by the staff, and a summary of the policy and technical issues raised by the staff during its review.

  7. NRC review of Electric Power Research Institute`s advanced light water reactor utility requirements document. Passive plant designs, chapters 2-13, project number 669

    SciTech Connect (OSTI)

    Not Available

    1994-08-01T23:59:59.000Z

    The Electric Power Research Institute (EPRI) is preparing a compendium of technical requirements, referred to as the {open_quotes}Advanced Light Water Reactor [ALWR] Utility Requirements Document{close_quotes}, that is acceptable to the design of an ALWR power plant. When completed, this document is intended to be a comprehensive statement of utility requirements for the design, construction, and performance of an ALWR power plant for the 1990s and beyond. The Requirements Document consists of three volumes. Volume I, {open_quotes}ALWR Policy and Summary of Top-Tier Requirements{close_quotes}, is a management-level synopsis of the Requirements Document, including the design objectives and philosophy, the overall physical configuration and features of a future nuclear plant design, and the steps necessary to take the proposed ALWR design criteria beyond the conceptual design state to a completed, functioning power plant. Volume II consists of 13 chapters and contains utility design requirements for an evolutionary nuclear power plant [approximately 1350 megawatts-electric (MWe)]. Volume III contains utility design requirements for nuclear plants for which passive features will be used in their designs (approximately 600 MWe). In April 1992, the staff of the Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, issued Volume 1 and Volume 2 (Parts 1 and 2) of its safety evaluation report (SER) to document the results of its review of Volumes 1 and 2 of the Requirements Document. Volume 1, {open_quotes}NRC Review of Electric Power Research Institute`s Advanced Light Water Reactor Utility Requirements Document - Program Summary{close_quotes}, provided a discussion of the overall purpose and scope of the Requirements Document, the background of the staff`s review, the review approach used by the staff, and a summary of the policy and technical issues raised by the staff during its review.

  8. Seismic fragility formulations for segmented buried pipeline systems including the impact of differential ground subsidence

    SciTech Connect (OSTI)

    Pineda Porras, Omar Andrey [Los Alamos National Laboratory; Ordaz, Mario [UNAM, MEXICO CITY

    2009-01-01T23:59:59.000Z

    Though Differential Ground Subsidence (DGS) impacts the seismic response of segmented buried pipelines augmenting their vulnerability, fragility formulations to estimate repair rates under such condition are not available in the literature. Physical models to estimate pipeline seismic damage considering other cases of permanent ground subsidence (e.g. faulting, tectonic uplift, liquefaction, and landslides) have been extensively reported, not being the case of DGS. The refinement of the study of two important phenomena in Mexico City - the 1985 Michoacan earthquake scenario and the sinking of the city due to ground subsidence - has contributed to the analysis of the interrelation of pipeline damage, ground motion intensity, and DGS; from the analysis of the 48-inch pipeline network of the Mexico City's Water System, fragility formulations for segmented buried pipeline systems for two DGS levels are proposed. The novel parameter PGV{sup 2}/PGA, being PGV peak ground velocity and PGA peak ground acceleration, has been used as seismic parameter in these formulations, since it has shown better correlation to pipeline damage than PGV alone according to previous studies. By comparing the proposed fragilities, it is concluded that a change in the DGS level (from Low-Medium to High) could increase the pipeline repair rates (number of repairs per kilometer) by factors ranging from 1.3 to 2.0; being the higher the seismic intensity the lower the factor.

  9. Utility Partnerships

    Broader source: Energy.gov [DOE]

    Utility Partnerships 7/10/12. Provides an overview of LEAP's (Charlottesville, VA) partnership with local utilities.

  10. Capsule injection system for a hydraulic capsule pipelining system

    DOE Patents [OSTI]

    Liu, Henry (Columbia, MO)

    1982-01-01T23:59:59.000Z

    An injection system for injecting capsules into a hydraulic capsule pipelining system, the pipelining system comprising a pipeline adapted for flow of a carrier liquid therethrough, and capsules adapted to be transported through the pipeline by the carrier liquid flowing through the pipeline. The injection system comprises a reservoir of carrier liquid, the pipeline extending within the reservoir and extending downstream out of the reservoir, and a magazine in the reservoir for holding capsules in a series, one above another, for injection into the pipeline in the reservoir. The magazine has a lower end in communication with the pipeline in the reservoir for delivery of capsules from the magazine into the pipeline.

  11. Questions and Issues on Hydrogen Pipeline Transmission of Hydrogen

    E-Print Network [OSTI]

    Questions and Issues on Hydrogen Pipelines Pipeline Transmission of Hydrogen Doe Hydrogen Pipeline Working Group Meeting August 31, 2005 #12;Pipeline Transmission of Hydrogen --- 2 Copyright: Air Liquide Transmission of Hydrogen --- 3 Copyright: #12;Pipeline Transmission of Hydrogen --- 4 Copyright: 3. Special

  12. Equivalence Checking for Function Pipelining in Behavioral Synthesis

    E-Print Network [OSTI]

    Xie, Fei

    on subtle design invariants. Function pipelining (a.k.a. system-level pipelining) is an important, correct-by-construction abstraction of function pipeline; thus, instead of developing pipelineEquivalence Checking for Function Pipelining in Behavioral Synthesis Kecheng Hao, Sandip Ray

  13. Analytic prognostic for petrochemical pipelines

    E-Print Network [OSTI]

    Jaoude, Abdo Abou; El-Tawil, Khaled; Noura, Hassan; Ouladsine, Mustapha

    2012-01-01T23:59:59.000Z

    Pipelines tubes are part of vital mechanical systems largely used in petrochemical industries. They serve to transport natural gases or liquids. They are cylindrical tubes and are submitted to the risks of corrosion due to high PH concentrations of the transported liquids in addition to fatigue cracks due to the alternation of pressure-depression of gas along the time, initiating therefore in the tubes body micro-cracks that can propagate abruptly to lead to failure. The development of the prognostic process for such systems increases largely their performance and their availability, as well decreases the global cost of their missions. Therefore, this paper deals with a new prognostic approach to improve the performance of these pipelines. Only the first mode of crack, that is, the opening mode, is considered.

  14. Analytic prognostic for petrochemical pipelines

    E-Print Network [OSTI]

    Abdo Abou Jaoude; Seifedine Kadry; Khaled El-Tawil; Hassan Noura; Mustapha Ouladsine

    2012-12-25T23:59:59.000Z

    Pipelines tubes are part of vital mechanical systems largely used in petrochemical industries. They serve to transport natural gases or liquids. They are cylindrical tubes and are submitted to the risks of corrosion due to high PH concentrations of the transported liquids in addition to fatigue cracks due to the alternation of pressure-depression of gas along the time, initiating therefore in the tubes body micro-cracks that can propagate abruptly to lead to failure. The development of the prognostic process for such systems increases largely their performance and their availability, as well decreases the global cost of their missions. Therefore, this paper deals with a new prognostic approach to improve the performance of these pipelines. Only the first mode of crack, that is, the opening mode, is considered.

  15. Flow of suspensions in pipelines

    SciTech Connect (OSTI)

    Nasr-El-Din, H.A. [Laboratory R& D Center, Saudi Aramco, Dhahran (Saudi Arabia)

    1996-12-31T23:59:59.000Z

    Slurry pipelines are used in many industrial applications. Several parameters are often needed by the operator, including critical deposit velocity, solids concentration, and particle velocity profiles. This chapter first reviews important formulas used to predict critical deposit velocity both in Newtonian and non-Newtonian (power-law) carrier fluids. Various methods to measure local velocity and solids concentration profiles in slurry pipelines are discussed. Local solids concentration can be measured by sample withdrawal technique. However, the sample should be withdrawn at isokinetic conditions. Sampling downstream of tees and elbows can result in significant errors in measuring solids concentration. Gamma-ray absorption methods can be used; however, two scans are needed to obtain local solids concentration. Bulk velocity of conductive slurries can be obtained using magnetic flow meters mounted on a vertical section of the pipe. Local particle velocity can be obtained using conductivity probes. NMR methods can be used to measure concentration and particle velocity profiles but are limited to small-diameter pipes. Vertical solids concentration of coarse slurries flowing in a horizontal pipeline exhibits a positive gradient near the bottom of the pipe. Traditional models to predict these profiles are given, and new mathematical models and computer software to determine these profiles are introduced. 104 refs., 31 figs., 1 tab.

  16. Exotic drilling: contractor drills pipelines

    SciTech Connect (OSTI)

    McReynolds, L.

    1980-04-01T23:59:59.000Z

    Drilling of pipelines has been technologically developed for applications such as river crossings, tunnelling through tar-sand or oil-shale strata for more effective in situ combustion production projects, and drilling inside rather than through heavy oil pays to create extensive horizontal well bores suitable for steam heating the formation. The horizontal drilling concept for river crossing involves installation of pipelines in an inverted arc 25 to 100 ft below a river bed. The directional control required to produce a curved hole is maintained by rotating the bit without rotating the pipe. When the drill string is activated by a forward thrust, it creates a reactive subsurface pressure against the front surface of the bent sub, thus causing the bend. The bit then deviates in the direction of the bend. Little disruption of the environment occurs, and the directionally drilled crossings offer improved pipeline security, maintenance of year-round construction schedules, easier permitting, no navigational hazards or interruption for waterway traffic, elimination of bank restoration costs and most repair costs, and a maintenance-free crossing section.

  17. Minimizing the Energy Cost of Throughput in a Linear Pipeline by Opportunistic Time Borrowing

    E-Print Network [OSTI]

    Pedram, Massoud

    of heat generation on the chip [1]. Many techniques have been proposed to reduce the power consumption for a fixed energy consumption level, or alternatively, lowers the energy consumption for the same effective to processor performance. Due to their high utilization, pipeline data path in a modern microprocessor

  18. Water Content Determination of Rubber Stoppers Utilized for Sealing Lyophilized Pharmaceutical Products: Assessment of Two Karl Fischer Titration Methods

    E-Print Network [OSTI]

    Voth, Laura Marie

    2013-08-31T23:59:59.000Z

    In the pharmaceutical industry, the success of a new drug product is strongly impacted by the stability of the drug formulation. For many formulations, stability is governed by the drug product's water content, thus the ...

  19. Utilization of the upper Houston Ship Channel by fish and macroinvertebrates with respect to water quality trends

    E-Print Network [OSTI]

    Seiler, Richard Dale

    1994-01-01T23:59:59.000Z

    regression analysis (MAXR) to test the effect (p&0. 05) of salinity (SAL, ppt), water temperature (TEMP, C), and dissolved oxygen content (DO, mg/I) on CPUE, biomass, number of taxa, species diversity (H'), and evenness (J) from seine collections...- relations) . . . . . . . . . . . . . . . . . . . . . . . ~ . . . . . . . . ~ 86 22 Stepwise multiple regression analysis (MAXR) to test the effect (p&0. 05) of salinity (S, ppt), water temperature (T, C), dissolved oxygen content (O, mg/I), and flow...

  20. Natural Gas Transmission Pipeline Siting Act (Florida)

    Broader source: Energy.gov [DOE]

    This Act establishes a centralized and coordinated permitting process for the location of natural gas transmission pipeline corridors and the construction and maintenance of natural gas...

  1. Acoustic system for communication in pipelines

    SciTech Connect (OSTI)

    Martin, II, Louis Peter (San Ramon, CA); Cooper, John F. (Oakland, CA)

    2008-09-09T23:59:59.000Z

    A system for communication in a pipe, or pipeline, or network of pipes containing a fluid. The system includes an encoding and transmitting sub-system connected to the pipe, or pipeline, or network of pipes that transmits a signal in the frequency range of 3-100 kHz into the pipe, or pipeline, or network of pipes containing a fluid, and a receiver and processor sub-system connected to the pipe, or pipeline, or network of pipes containing a fluid that receives said signal and uses said signal for a desired application.

  2. GLAST (FERMI) Data-Processing Pipeline

    SciTech Connect (OSTI)

    Flath, Daniel L.; Johnson, Tony S.; Turri, Massimiliano; Heidenreich, Karen A.; /SLAC

    2011-08-12T23:59:59.000Z

    The Data Processing Pipeline ('Pipeline') has been developed for the Gamma-Ray Large Area Space Telescope (GLAST) which launched June 11, 2008. It generically processes graphs of dependent tasks, maintaining a full record of its state, history and data products. The Pipeline is used to automatically process the data down-linked from the satellite and to deliver science products to the GLAST collaboration and the Science Support Center and has been in continuous use since launch with great success. The pipeline handles up to 2000 concurrent jobs and in reconstructing science data produces approximately 750GB of data products using 1/2 CPU-year of processing time per day.

  3. Hazardous Liquid Pipelines and Storage Facilities (Iowa)

    Broader source: Energy.gov [DOE]

    This statute regulates the permitting, construction, monitoring, and operation of pipelines transporting hazardous liquids, including petroleum products and coal slurries. The definition used in...

  4. Illinois Gas Pipeline Safety Act (Illinois)

    Broader source: Energy.gov [DOE]

    Standards established under this Act may apply to the design, installation, inspection, testing, construction, extension, operation, replacement, and maintenance of pipeline facilities. Whenever...

  5. Pipelines and Underground Gas Storage (Iowa)

    Broader source: Energy.gov [DOE]

    These rules apply to intrastate transport of natural gas and other substances via pipeline, as well as underground gas storage facilities. The construction and operation of such infrastructure...

  6. Petroleum Pipeline Eminent Domain Permit Procedures (Georgia)

    Broader source: Energy.gov [DOE]

    The Petroleum Pipeline Eminent Domain Permit Procedures serve to protect Georgia's natural and environmental resources by requiring permits be issued by the Director of the Environmental Protection...

  7. Hydrogen Delivery Technologies and Pipeline Transmission of Hydrogen

    E-Print Network [OSTI]

    Hydrogen Delivery Technologies and Systems Pipeline Transmission of Hydrogen Strategic Initiatives, and Infrastructure Technologies Program #12;Pipeline Transmission of Hydrogen --- 2 Copyright: Design & Operation development) #12;Pipeline Transmission of Hydrogen --- 3 Copyright: Future H2 Infrastructure Wind Powered

  8. A feminist perspective on the school-to-labor pipeline

    E-Print Network [OSTI]

    Hextrum, Kirsten

    2014-01-01T23:59:59.000Z

    on the School-to-Labor Pipeline Collins, P. (1986) Learningon the School-to-Labor Pipeline Leonardo, Z. (2010).on the School-to-Labor Pipeline Kirsten Hextrum 1 University

  9. Structural Genomics of Minimal Organisms: Pipeline and Results

    E-Print Network [OSTI]

    Kim, Sung-Hou

    2008-01-01T23:59:59.000Z

    of Minimal Organisms: Pipeline and Results Sung-Hou Kim*,~500 genes, respectively). Pipeline: To achieve our mission,determination. Over all pipeline schemes for the single-path

  10. Trenches Under The Pipeline: The Educational Trajectories of Chicano Male Continuation High School Students

    E-Print Network [OSTI]

    Malagon, Maria

    2010-01-01T23:59:59.000Z

    Trenches Under The Pipeline: The Educational Trajectories ofnavigate the educational pipeline, continuation high school

  11. EIA - Natural Gas Pipeline Network - Region To Region System Capacity

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for On-Highway4,1,50022,3,,,,6,1,9,1,50022,3,,,,6,1,Decade Year-0E (2001)gasoline353/06)Pipeline Utilization & Capacity

  12. EIA - Natural Gas Pipeline Network - Regional Overview and Links

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for On-Highway4,1,50022,3,,,,6,1,9,1,50022,3,,,,6,1,Decade Year-0E (2001)gasoline353/06)Pipeline Utilization &Overview and

  13. EIA - Natural Gas Pipeline Network - States Dependent on Interstate

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for On-Highway4,1,50022,3,,,,6,1,9,1,50022,3,,,,6,1,Decade Year-0E (2001)gasoline353/06)Pipeline Utilization

  14. EIA - Natural Gas Pipeline Network - Transportation Process & Flow

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for On-Highway4,1,50022,3,,,,6,1,9,1,50022,3,,,,6,1,Decade Year-0E (2001)gasoline353/06)Pipeline UtilizationProcess and Flow

  15. EIA - Natural Gas Pipeline Network - Underground Natural Gas Storage

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for On-Highway4,1,50022,3,,,,6,1,9,1,50022,3,,,,6,1,Decade Year-0E (2001)gasoline353/06)Pipeline UtilizationProcess andStorage

  16. EIA - Natural Gas Pipeline Network - Underground Natural Gas Storage

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for On-Highway4,1,50022,3,,,,6,1,9,1,50022,3,,,,6,1,Decade Year-0E (2001)gasoline353/06)Pipeline UtilizationProcess

  17. EIA - Natural Gas Pipeline Network - Underground Natural Gas Storage

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for On-Highway4,1,50022,3,,,,6,1,9,1,50022,3,,,,6,1,Decade Year-0E (2001)gasoline353/06)Pipeline UtilizationProcessFacilities

  18. Pipeline Structural Health Monitoring Using Macro-fiber Composite Active Sensors

    SciTech Connect (OSTI)

    A.B. Thien

    2006-03-01T23:59:59.000Z

    The United States economy is heavily dependent upon a vast network of pipeline systems to transport and distribute the nation's energy resources. As this network of pipelines continues to age, monitoring and maintaining its structural integrity remains essential to the nation's energy interests. Numerous pipeline accidents over the past several years have resulted in hundreds of fatalities and billions of dollars in property damages. These accidents show that the current monitoring methods are not sufficient and leave a considerable margin for improvement. To avoid such catastrophes, more thorough methods are needed. As a solution, the research of this thesis proposes a structural health monitoring (SHM) system for pipeline networks. By implementing a SHM system with pipelines, their structural integrity can be continuously monitored, reducing the overall risks and costs associated with current methods. The proposed SHM system relies upon the deployment of macro-fiber composite (MFC) patches for the sensor array. Because MFC patches are flexible and resilient, they can be permanently mounted to the curved surface of a pipeline's main body. From this location, the MFC patches are used to monitor the structural integrity of the entire pipeline. Two damage detection techniques, guided wave and impedance methods, were implemented as part of the proposed SHM system. However, both techniques utilize the same MFC patches. This dual use of the MFC patches enables the proposed SHM system to require only a single sensor array. The presented Lamb wave methods demonstrated the ability to correctly identify and locate the presence of damage in the main body of the pipeline system, including simulated cracks and actual corrosion damage. The presented impedance methods demonstrated the ability to correctly identify and locate the presence of damage in the flanged joints of the pipeline system, including the loosening of bolts on the flanges. In addition to damage to the actual pipeline itself, the proposed methods were used to demonstrate the capability of detecting deposits inside of pipelines. Monitoring these deposits can prevent clogging and other hazardous situations. Finally, suggestions are made regarding future research issues which are needed to advance this research. Because the research of this thesis has only demonstrated the feasibility of the techniques for such a SHM system, these issues require attention before any commercial applications can be realized.

  19. Remedial investigation report on the abandoned nitric acid pipeline at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    SciTech Connect (OSTI)

    Not Available

    1993-12-01T23:59:59.000Z

    Upper East Fork Poplar Creek OU-2 consists of the Abandoned Nitric Acid Pipeline. This pipeline was installed in 1951 to transport liquid wastes {approximately} 4,800 ft from Buildings 9212, 9215, and 9206 to the S-3 Ponds. Materials known to have been discharged through the pipeline include nitric acid, depleted and enriched uranium, various metal nitrates, salts, and lead skimmings. A total of nineteen locations were chosen to be investigated along the pipeline for the first phase of this Remedial Investigation. Sampling consisted of drilling down to obtain a soil sample at a depth immediately below the pipeline. Additional samples were obtained deeper in the subsurface depending upon the depth of the pipeline, the depth of the water table, and the point of auger refusal. The nineteen samples collected below the pipeline were analyzed by the Y-12 Plant laboratory for metals, nitrate/nitrite, and isotopic uranium. Samples collected from three boreholes were also analyzed for volatile organic compounds because these samples produced a response with organic vapor monitoring equipment. The results of the baseline human health risk assessment for the Abandoned Nitric Acid Pipeline contaminants of potential concern show no unacceptable risks to human health via incidental ingestion of soil, inhalation of dust, dermal contact with the soil, or external exposure to radionuclides in the ANAP soils, under the construction worker and/or the residential land-use scenarios.

  20. Hydrogen Permeability and Integrity of Hydrogen Delivery Pipelines...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Permeability and Integrity of Hydrogen Delivery Pipelines Hydrogen Permeability and Integrity of Hydrogen Delivery Pipelines Project Objectives: To gain basic understanding of...

  1. Report to Congress: Dedicated Ethanol Pipeline Feasability Study...

    Energy Savers [EERE]

    Report to Congress: Dedicated Ethanol Pipeline Feasability Study - Energy Independence and Security Act of 2007 Section 243 Report to Congress: Dedicated Ethanol Pipeline...

  2. argentinian pipeline enlargement: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Fiber-reinforced polymer pipe Project Overview: Investigate 25 Code for Hydrogen Hydrogen Pipeline Renewable Energy Websites Summary: 12;2 Code for Hydrogen Pipelines...

  3. acicular ferrite pipeline: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Fiber-reinforced polymer pipe Project Overview: Investigate 18 Code for Hydrogen Hydrogen Pipeline Renewable Energy Websites Summary: 12;2 Code for Hydrogen Pipelines...

  4. automatic pipeline monitoring: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Fiber-reinforced polymer pipe Project Overview: Investigate 67 Code for Hydrogen Hydrogen Pipeline Renewable Energy Websites Summary: 12;2 Code for Hydrogen Pipelines...

  5. alaska gas pipeline: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    and ROW Lower South Carolina Electric and Gas University of South Carolina Praxair Hydrogen Pipeline Working Group 4 A moving horizon solution to the gas pipeline...

  6. alaska pipeline system: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Fiber-reinforced polymer pipe Project Overview: Investigate 93 Code for Hydrogen Hydrogen Pipeline Renewable Energy Websites Summary: 12;2 Code for Hydrogen Pipelines...

  7. automatic pipeline analysing: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Fiber-reinforced polymer pipe Project Overview: Investigate 45 Code for Hydrogen Hydrogen Pipeline Renewable Energy Websites Summary: 12;2 Code for Hydrogen Pipelines...

  8. annotation pipelines differences: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Fiber-reinforced polymer pipe Project Overview: Investigate 73 Code for Hydrogen Hydrogen Pipeline Renewable Energy Websites Summary: 12;2 Code for Hydrogen Pipelines...

  9. arctic gas pipeline: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    and ROW Lower South Carolina Electric and Gas University of South Carolina Praxair Hydrogen Pipeline Working Group 3 A moving horizon solution to the gas pipeline...

  10. arctic gas pipelines: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    and ROW Lower South Carolina Electric and Gas University of South Carolina Praxair Hydrogen Pipeline Working Group 3 A moving horizon solution to the gas pipeline...

  11. alaska highway pipeline: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Fiber-reinforced polymer pipe Project Overview: Investigate 45 Code for Hydrogen Hydrogen Pipeline Renewable Energy Websites Summary: 12;2 Code for Hydrogen Pipelines...

  12. areas osbra pipeline: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Fiber-reinforced polymer pipe Project Overview: Investigate 16 Code for Hydrogen Hydrogen Pipeline Renewable Energy Websites Summary: 12;2 Code for Hydrogen Pipelines...

  13. Hydrogen Delivery Technologies and Systems- Pipeline Transmission of Hydrogen

    Broader source: Energy.gov [DOE]

    Hydrogen Delivery Technologies and Systems - Pipeline Transmission of Hydrogen. Design and operations standards and materials for hydrogen and natural gas pipelines.

  14. Evalutation of Natural Gas Pipeline Materials and Infrastructure...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Evalutation of Natural Gas Pipeline Materials and Infrastructure for HydrogenMixed Gas Service Evalutation of Natural Gas Pipeline Materials and Infrastructure for HydrogenMixed...

  15. Energy Department Moves Forward on Alaska Natural Gas Pipeline...

    Broader source: Energy.gov (indexed) [DOE]

    guarantee program to encourage the construction of a pipeline that will bring Alaskan natural gas to the continental United States. The pipeline will provide access to Alaska's...

  16. Assessment of the Adequacy of Natural Gas Pipeline Capacity in...

    Office of Environmental Management (EM)

    Assessment of the Adequacy of Natural Gas Pipeline Capacity in the Northeast United States - November 2013 Assessment of the Adequacy of Natural Gas Pipeline Capacity in the...

  17. Evaluation of Natural Gas Pipeline Materials for Hydrogen Science...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Evaluation of Natural Gas Pipeline Materials for Hydrogen Science Evaluation of Natural Gas Pipeline Materials for Hydrogen Science Presentation by 04-Adams to DOE Hydrogen...

  18. EIA - Natural Gas Pipeline Network - Regional Overview and Links

    U.S. Energy Information Administration (EIA) Indexed Site

    Overview and Links About U.S. Natural Gas Pipelines - Transporting Natural Gas based on data through 20072008 with selected updates Regional Overviews and Links to Pipeline...

  19. Harmonic distortion correction in pipelined analog to digital converters

    E-Print Network [OSTI]

    Panigada, Andrea

    2009-01-01T23:59:59.000Z

    Background Correction of Harmonic Distortion in PipelinedBackground Correction of Harmonic Distortion in PipelinedADC with 69dB SNDR Enabled by Digital Harmonic Distortion

  20. Case Study of Stratified Chilled Water Storage Utilization for Comfort and Process Cooling in a Hot, Humid Climate

    E-Print Network [OSTI]

    Bahnfleth, W. P.; Musser, A.

    1998-01-01T23:59:59.000Z

    by approximately $1.5 million per year. The thermal storage tank is a fully buried cylindrical, precast, pre-stressed tank with four-ring single pipe octagonal diffusers. It holds 5.2 million gallons (1 9.7 million L) of water, and is 140 ft (42.7 m... of the system and its operation is followed by presentation of operating data taken during 1997. INTRODUCTION Chilled water thermal energy storage ('TES) in naturally stratified tanks has been shown to be a valuable central cooling plant load management...

  1. Utilization of municipal wastewater for cooling in thermoelectric power plants: Evaluation of the combined cost of makeup water treatment and increased condenser fouling

    SciTech Connect (OSTI)

    Walker, Michael E.; Theregowda, Ranjani B.; Safari, Iman; Abbasian, Javad; Arastoopour, Hamid; Dzombak, David A.; Hsieh, Ming-Kai; Miller, David C.

    2013-10-01T23:59:59.000Z

    A methodology is presented to calculate the total combined cost (TCC) of water sourcing, water treatment and condenser fouling in the recirculating cooling systems of thermoelectric power plants. The methodology is employed to evaluate the economic viability of using treated municipal wastewater (MWW) to replace the use of freshwater as makeup water to power plant cooling systems. Cost analyses are presented for a reference power plant and five different tertiary treatment scenarios to reduce the scaling tendencies of MWW. Results indicate that a 550 MW sub-critical coal fired power plant with a makeup water requirement of 29.3 ML/day has a TCC of $3.0 - 3.2 million/yr associated with the use of treated MWW for cooling. (All costs USD 2009). This translates to a freshwater conservation cost of $0.29/kL, which is considerably lower than that of dry air cooling technology, $1.5/kL, as well as the 2020 conservation cost target set by the U.S. Department of Energy, $0.74/kL. Results also show that if the available price of freshwater exceeds that of secondarytreated MWW by more than $0.13-0.14/kL, it can be economically advantageous to purchase secondary MWW and treat it for utilization in the recirculating cooling system of a thermoelectric power plant.

  2. Pressure Capacity Reduction of X52 Pipeline Steel Damaged by a Semi-Elliptical Pitting Corrosion

    E-Print Network [OSTI]

    S. M. Kazerouni Sangi; Y. Gholipour

    Abstract—Steel made pipelines with different diameters are used for transmitting oil and gas which in many cases are buried in soil under the sea bed or immersed in sea water. External corrosion of pipes is an important form of deterioration due to the aggressive environment of sea water. Corrosion normally results in pits. Hence, using the finite element method, namely ABAQUS software, this paper estimates the amount of pressure capacity reduction of a pipecontaining a semi-elliptical pitting corrosion and the rate of corrosion during the pipeline life of 25 years.

  3. Pipeline corridors through wetlands -- Impacts on plant communities: Little Timber Creek Crossing, Gloucester County, New Jersey. Topical report, August 1991--January 1993

    SciTech Connect (OSTI)

    Shem, L.M.; Zimmerman, R.E.; Alsum, S.K. [Argonne National Lab., IL (United States). Center for Environmental Restoration Systems; Van Dyke, G.D. [Argonne National Lab., IL (United States). Center for Environmental Restoration Systems]|[Trinity Christian Coll., Palos Heights, IL (United States). Dept. of Biology

    1994-12-01T23:59:59.000Z

    The goal of the Gas Research Institute Wetland Corridors Program is to document impacts of existing pipelines on the wetlands they traverse. To accomplish this goal, 12 existing wetland crossings were surveyed. These sites varied in elapsed time since pipeline construction, wetland type, pipeline installation techniques, and right-of-way (ROW) management practices. This report presents results of a survey conducted over the period of August 5--7, 1991, at the Little Timber Creek crossing in Gloucester County, New Jersey, where three pipelines, constructed in 1950, 1960, and 1990, cross the creek and associated wetlands. The old side of the ROW, created by the installation of the 1960 pipeline, was designed to contain a raised peat bed over the 1950 pipeline and an open-water ditch over the 1960 pipeline. The new portion of the ROW, created by installation of the 1990 pipeline, has an open-water ditch over the pipeline (resulting from settling of the backfill) and a raised peat bed (resulting from rebound of compacted peat). Both the old and new ROWs contain dense stands of herbs; the vegetation on the old ROW was more similar to that in the adjacent natural area than was vegetation in the new ROW. The ROW increased species and habitat diversity in the wetlands. It may contribute to the spread of purple loosestrife and affect species sensitive to habitat fragmentation.

  4. Addressing the workforce pipeline challenge

    SciTech Connect (OSTI)

    Leonard Bond; Kevin Kostelnik; Richard Holman

    2006-11-01T23:59:59.000Z

    A secure and affordable energy supply is essential for achieving U.S. national security, in continuing U.S. prosperity and in laying the foundations to enable future economic growth. To meet this goal the next generation energy workforce in the U.S., in particular those needed to support instrumentation, controls and advanced operations and maintenance, is a critical element. The workforce is aging and a new workforce pipeline, to support both current generation and new build has yet to be established. The paper reviews the challenges and some actions being taken to address this need.

  5. Reducing Power Dissipation in Pipelined Accumulators

    E-Print Network [OSTI]

    Nannarelli, Alberto

    Reducing Power Dissipation in Pipelined Accumulators Gian Carlo Cardarilli(1), Alberto Nannarelli(2 Informatics, Technical University of Denmark, Kongens Lyngby, Denmark Abstract-- Fast accumulation is required). Accumulators nec- essary for DDFS are then deeply pipelined down to the bit-level with two main consequences

  6. Liquefaction and Pipeline Costs Bruce Kelly

    E-Print Network [OSTI]

    1 Liquefaction and Pipeline Costs Bruce Kelly Nexant, Inc. Hydrogen Delivery Analysis Meeting May 8 are representative of hydrogen pipeline costs; 10 percent added to unit hydrogen costs as a contingency Better-9, 2007 Columbia, Maryland #12;2 Hydrogen Liquefaction Basic process Compress Cool to temperature

  7. Economic principles and applications to natural gas pipelines and other industries

    SciTech Connect (OSTI)

    Kolbe, L.; Tye, W.; Myers, S.C.

    1993-12-31T23:59:59.000Z

    This book combines and expands several of the authors` papers on regulatory risk and a report on risk in the interstate natural gas pipeline industry which the authors prepared for the Interstate Natural Gas Association of America. The first four chapters present the authors` theory of risk in regulated industries. The remaining five chapters provide a detailed analysis of risk under historic and pending regulation of the interstate natural gas pipeline industry. An appendix provides an excellent, detailed and highly annotated regulatory history of interstate natural gas pipeline regulation from roughly the Natural Gas Policy Act of 1978 to 1990. In some 350 pages this book appears to make two primary points. First, rate base regulation is a camel, where the definition of a camel is a horse designed by a committee, or in the case of utility regulation, a horse designed by congress, state legislatures, and the courts. The second point is that realized rates of return in regulated utilities are subject to a reverse Lake Wobegone effect. In the regulatory world of the authors, all utility returns are below average. This book contains some interesting new ideas and some excellent insights into some old issues in rate base regulation. It is worth the somewhat tedious read just for the wealth of institutional information on the pipeline industry and its regulation.

  8. A leak detecting technique utilizing an abrupt and large pressure drop

    E-Print Network [OSTI]

    Torres, James, S.M. Massachusetts Institute of Technology.

    2010-01-01T23:59:59.000Z

    The distribution of clean, drinkable water is a problem that has been addressed in all civilizations. The most common form of transportation today, is the use of pressurized pipelines to carry the water long distances, but ...

  9. Utilization of coal-water fuels in fire-tube boilers. Final report, October 1990--August 1994

    SciTech Connect (OSTI)

    Sommer, T.; Melick, T.; Morrison, D.

    1994-12-31T23:59:59.000Z

    The objective of this DOE sponsored project was to successfully fire coal-water slurry in a fire-tube boiler that was designed for oil/gas firing and establish a data base that will be relevant to a large number of existing installations. Firing slurry in a fire-tube configuration is a very demanding application because of the extremely high heat release rates and the correspondingly low furnace volume where combustion can be completed. Recognizing that combustion efficiency is the major obstacle when firing slurry in a fire-tube boiler, the program was focused on innovative approaches for improving carbon burnout without major modifications to the boiler. The boiler system was successfully designed and operated to fire coal-water slurry for extended periods of time with few slurry related operational problems. The host facility was a 3.8 million Btu/hr Cleaver-Brooks fire-tube boiler located on the University of Alabama Campus. A slurry atomizer was designed that provided outstanding atomization and was not susceptible to pluggage. The boiler was operated for over 1000 hours and 12 shipments of slurry were delivered. The new equipment engineered for the coal-water slurry system consisted of the following: combustion air and slurry heaters; cyclone; baghouse; fly ash reinjection system; new control system; air compressor; CWS/gas burner and gas valve train; and storage tank and slurry handling system.

  10. Austin Utilities- Solar Rebate Program

    Broader source: Energy.gov [DOE]

    Austin Utilities provides incentives for their residential and commercial customers to install photovoltaic (PV) and solar water heating systems. Qualifying PV systems can earn $1 per watt;...

  11. FLUID TRANSIENTS IN A PIPELINE WITH ONE END OPEN

    SciTech Connect (OSTI)

    Leishear, R

    2008-06-09T23:59:59.000Z

    Water hammer during multi-phase flow is rather complex, but in some cases an upper limit to the pressure surge magnitude during water hammer can be estimated. In the case considered here, a two mile long pipeline with a single high point was permitted to partially drain. Due to gravitational effects, air bubbles up through the pipe line to its highest point, but the time required for air to reach the top of the pipe is rather long. Consequently, some transients caused by valve operations are affected by air entrapment and some are not. The intent of this research was to investigate the complex interactions between air, water vapor, and liquid during water hammer in a long pipe with one end of the pipe open to atmospheric conditions. To understand the system dynamics, experimental data was obtained from a long pipeline with an open end and also from a short, transparent tube. Transient calculations were performed for valve closures and pump operations as applicable. The limitations of available calculation techniques were considered in detail.

  12. Rotary Pipeline Processors Simon Moore, Peter Robinson, Steve Wilcox

    E-Print Network [OSTI]

    Robinson, Peter

    to the current range of superscalar designs using multiple instruction issue into parallel pipelines to increase] is designed around a bi-directional pipeline carry- ing instructions and arguments in one direction it will start to execute as soon as the data arrives. 2.2 Basic Pipeline Construction A rotary pipeline

  13. Utilization of geopressured resources in the oxidation of organic waste in supercritical water. Phase I, Final report

    SciTech Connect (OSTI)

    Diaz, Alexander F.; Herzog, Howard J.; Tester, Jefferson W.

    1992-11-01T23:59:59.000Z

    Geopressured resources are geothermal reservoirs containing dissolved methane in hot brine at pressures well in excess of their in situ hydrostatic pressure. In the US, geopressured resources are primarily located in the Gulf (of Mexico) Coast. The wells in this area are characterized by typical bottomhole temperatures of 120-180 C (250-360 F) (Negus-de Wys, 1991a) and bottomhole pressures of 675-1275 bar (9,800-18,500 psia) (Negus-de Wys, 1991b). Supercritical water oxidation (SCWO) is an emerging technology for the destruction of hazardous organic waste in which oxidation is carried out in a water medium above the critical point of pure water (374 C/705 F, 221 bar/3208 psia) (Tester et al., 1992). Geopressured resources are particularly suitable as an input stream to a SCWO waste treatment process due to the near critical conditions of their hot brine. By using a Rankine-type power cycle, electric power can be generated by capturing the available thermal and hydraulic energy from the geothermal resource and the chemical energy of the dissolved methane released by the oxidation process. In addition to oxidizing the methane to convert the chemical energy to thermal energy, auxiliary fuel in the form of an organic waste can be co-oxidized to increase the energy output to commercially sustainable levels. Coupling the treatment of geopressured brine with an organic waste in a SCWO process synergistically improves power production while providing a means for treating hazardous waste. The objective of this study is to assess the feasibility of using geopressured resources to simultaneously detoxify hazardous waste and generate electric power. Our ultimate aim is to develop conceptual process designs for above-ground and fully or modified in situ approaches to co-processing organic waste with geopressured brine in supercritical water. As a preparatory step for investigating in situ approaches, a realistic above-ground conceptual design was developed in this study. In that concept, the waste, brine and oxidant (air or oxygen) are introduced into the SCWO reactor at the system pressure of 234 bar (3400 psia). The heat of oxidation raises the temperature of the system to about 600 C (1100 F). Due to the low solubility of inorganic salts in supercritical water (about 200 ppm or less) (Armellini and Tester, 1990, 1991a, 1991b), solid salt forms and falls to the lower section of the reactor, where it is cooled and quenched with water, creating a concentrated (organic-free) brine that would be mixed with brackish water and reinjected back to the geopressured well. Power is generated by the expansion of the products of the SCWO process through a series of multi-stage turboexpanden. A processing capacity of 100,000 gallons per day (gpd) was initially taken as the design basis, following some investigations carried out at the Idaho National Engineering Laboratory (Propp et al., 1990). The process was modeled using the ASPEN PLUS{trademark} process flowsheet simulator and material and energy balances were determined. Both the cases of using air and oxygen as oxidant were investigated. Toluene was chosen as the model compound to represent the organic waste. Turbine design calculations based on the volumetric flowrates obtained for a 100,000 gpd capacity resulted in unrealistically high rotor rotational speeds and small wheel pitch diameters to achieve optimum efficiencies. Higher SCWO effluent flowrates would lower rotor rotational speeds and increase wheel pitch diameters to more practical levels. Thus, a 42-fold larger design capacity of 100,000 barrels per day (bpd) was adopted as the basis for an above-ground base case. The results for the material and energy balances for a processing capacity of 100,000 bpd using air and oxygen as oxidant scale up linearly from the results for the 100,000 gpd case. The best case flowsheet corresponding to a 100,000 bpi case using oxygen as oxidant is given in Figure 1. Our conceptual design study suggests that simultaneous detoxification of hazardous waste and production of power is possible by co-pr

  14. Sensor Networks for Monitoring and Control of Water Distribution Systems

    E-Print Network [OSTI]

    Whittle, Andrew

    Water distribution systems present a significant challenge for structural monitoring. They comprise a complex network of pipelines buried underground that are relatively inaccessible. Maintaining the integrity of these ...

  15. The Construction and Maintenance Plan for a Grand Banks Multi-Purpose Pipeline

    E-Print Network [OSTI]

    Bruneau, Steve

    ;Pipeline Repair Protocol 1 Leak detection and compressor shut down 2 Damage location 3 Excavate pipe 4 Murdoch Gorm Dunkirk Existing Gas Pipeline Proposed Gas Pipeline Existing Oil Pipeline 20" 30" 36" (2) 40 Gas Pipeline Proposed Gas Pipeline Existing Oil Pipeline 20" 30" 36" (2) 40" 40" 28" 42" 36" 40" 30

  16. New regulatory environment changing pipeline operations

    SciTech Connect (OSTI)

    Fields, J.H. (Northwest Pipeline Corp., Salt Lake City, UT (United States))

    1994-04-01T23:59:59.000Z

    This paper reviews the effects of deregulation of the natural gas and pipeline industry as a result of the Federal Energy Regulatory Commission's Orders 436, 500, and 636. It describes the changes as they affected Northwest Pipeline's structure and marketing strategies as the company had to move from a gas merchandiser to a gas transporter. It describes the capacity release options of the pipeline which allow the customers to buy, release, and renegotiate prices whenever they need to because of an increase or decrease in demand using current market prices. The paper discusses the natural gas distribution system which has evolved as a result of these regulations.

  17. Regulation changes create opportunities for pipeline manufacturers

    SciTech Connect (OSTI)

    Santon, J.

    1999-09-01T23:59:59.000Z

    The US Department of Transportation`s (DOT) Research and Special Programs Administration (RSPA) is proposing to change its safety standards for the repair of corroded or damaged steel pipe in gas and hazardous liquid pipelines. For pipeline operators, the expected revisions will allow new flexibility in approaches to pipeline repair. Less costly and less disruptive procedures will be acceptable. For manufacturers, the changes will open opportunities for development of corrosion repair technology. A highly competitive market in new repair technology can be expected to arise. Current regulations, new technologies, and proposed safety standards are described.

  18. EIS-0433: Keystone XL Pipeline

    Broader source: Energy.gov [DOE]

    The proposed Keystone XL project consists of a 1,700-mile crude oil pipeline and related facilities that would primarily be used to transport Western Canadian Sedimentary Basin crude oil from an oil supply hub in Alberta, Canada to delivery points in Oklahoma and Texas. This EIS, prepared by the Department of State, evaluates the environmental impacts of the proposed Keystone XL project. DOE’s Western Area Power Administration, a cooperating agency, has jurisdiction over certain proposed transmission facilities (construction and operation of a short 230-kv transmission line and construction of a new substation). The State Department published a notice in the Federal Register on February 3, 2012, regarding the denial of the Keystone XL presidential permit (77 FR 5614).

  19. IEEE TRANSACTIONS ON ROBOTICS, VOL. 28, NO. 1, FEBRUARY 2012 223 On Optimizing Autonomous Pipeline Inspection

    E-Print Network [OSTI]

    Li, Xin "Shane"

    health. As the most economical way to transport gas, oil, bio fuels, water resource, sewer, and so forth. For example, the leak of petroleum pipeline causes ocean pollution and ecocatastrophe. Regular inspections Editor T. Murphey and Editor J.-P. Laumond upon evaluation of the reviewers' comments. This work

  20. Federal Utility Partnership Working Group

    Broader source: Energy.gov [DOE]

    The Federal Utility Partnership Working Group (FUPWG) establishes partnerships and facilitates communications among Federal agencies, utilities, and energy service companies. The group develops strategies to implement cost-effective energy efficiency and water conservation projects through utility incentive programs at Federal sites.

  1. Economic and Conservation Evaluation of Capital Renovation Projects: Hidalgo County Irrigation District No. 2 (San Juan) - 48" Pipeline Replacing Wisconsin Canal - Final 

    E-Print Network [OSTI]

    Rister, Edward; Lacewell, Ronald; Sturdivant, Allen; Robinson, John; Popp, Michael

    2003-01-01T23:59:59.000Z

    Development Bank (NADBank) and Bureau of Reclamation. The proposed project involves constructing a 48" pipeline to replace the “Wisconsin Canal.” Both nominal and real estimates of water and energy savings and expected economic and financial costs of those...

  2. Economic and Conservation Evaluation of Capital Renovation Projects: Hidalgo County Irrigation District No. 2 (San Juan) – 48" Pipeline Replacing Wisconsin Canal – Preliminary 

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    2003-01-01T23:59:59.000Z

    Development Bank (NADBank) and Bureau of Reclamation. The proposed project involves constructing a 48" pipeline to replace the “Wisconsin Canal.” Both nominal and real estimates of water and energy savings and expected economic and financial costs of those...

  3. Economic and Conservation Evaluation of Capital Renovation Projects: Hidalgo County Irrigation District No. 2 (San Juan) - 48" Pipeline Replacing Wisconsin Canal - Final

    E-Print Network [OSTI]

    Rister, Edward; Lacewell, Ronald; Sturdivant, Allen; Robinson, John; Popp, Michael

    Development Bank (NADBank) and Bureau of Reclamation. The proposed project involves constructing a 48" pipeline to replace the “Wisconsin Canal.” Both nominal and real estimates of water and energy savings and expected economic and financial costs of those...

  4. Pipeline Access and Market Integration in the Natural Gas Industry: Evidence from Cointegration Tests

    E-Print Network [OSTI]

    De Vany, Arthur; Walls, W. David

    1993-01-01T23:59:59.000Z

    System for Natural Gas Pipelines." Study prepared underin the Natural Gas Pipeline Industry. Ph.D. dissertation,the remaining barfers to pipeline integration. REFERENCES

  5. Stuck in the Pipeline: A Critical Review of STEM Workforce Literature

    E-Print Network [OSTI]

    Metcalf, Heather

    2010-01-01T23:59:59.000Z

    and science careers: Leaky pipeline or gender filter? GenderL. (2006). Expanding the pipeline: Transforming the cultureThe incredible shrinking pipeline. Inroads: SIGCE Bulletin,

  6. Applications of the pipeline environment for visual informatics and genomics computations

    E-Print Network [OSTI]

    2011-01-01T23:59:59.000Z

    et al. : Applications of the pipeline environment for visualusing the LONI pipeline. Frontiers in Neuroinformatics 2010,Access Applications of the pipeline environment for visual

  7. BS-Seeker2: a versatile aligning pipeline for bisulfite sequencing data

    E-Print Network [OSTI]

    2013-01-01T23:59:59.000Z

    RL: MethylCoder: software pipeline for bisulfite-treateda versatile aligning pipeline for bisulfite sequencing dataof BS Seeker, as a full pipeline for mapping bisulfite

  8. A Crack in the Pipeline: Why Female Underrepresented Racial Minority Students Leave Engineering

    E-Print Network [OSTI]

    Vazquez-Akim, Jenn

    2014-01-01T23:59:59.000Z

    Espinosa, Lorelle L. (2011). Pipelines and pathways: womenAngeles A Crack in the Pipeline: Why Female UnderrepresentedA Crack in the Pipeline: Why Female Underrepresented Racial

  9. GenePRIMP: A GENE PRediction IMprovement Pipeline for Prokaryotic genomes

    E-Print Network [OSTI]

    Pati, Amrita

    2012-01-01T23:59:59.000Z

    PRediction IMprovement Pipeline for Amrita Pati 1 , NataliaGene Prediction IMprovement Pipeline, http://geneprimp.jgi-based post-processing pipeline that identifies erroneously

  10. Rnnotator: an automated de novo transcriptome assembly pipeline from stranded RNA-Seq reads

    E-Print Network [OSTI]

    Martin, Jeffrey

    2011-01-01T23:59:59.000Z

    transcriptome assembly pipeline from stranded RNA-Seq readsRnnotator assembly pipeline. Figure 2. Read dereplicationan automated software pipeline that generates transcript

  11. Applications of the Pipeline Environment for Visual Informatics and Genomics Computations

    E-Print Network [OSTI]

    2011-01-01T23:59:59.000Z

    et al. : Applications of the pipeline environment for visualusing the LONI pipeline. Frontiers in Neuroinformatics 2010,Access Applications of the pipeline environment for visual

  12. Pipelines, Pathways, and Payoffs: Economic Challenges and Returns to Changing Demographics in California

    E-Print Network [OSTI]

    Stiles, Jon; Brady, Henry

    2007-01-01T23:59:59.000Z

    on Multiple Pathways Pipelines, Pathways, and Payoffs:Jon Stiles & Henry Brady Pipelines, Pathways, and Payoffs:of the educational pipeline to describe how students

  13. Efficient, distributed and interactive neuroimaging data analysis using the LONI Pipeline

    E-Print Network [OSTI]

    2009-01-01T23:59:59.000Z

    A. W. (2003). The LONI pipeline process- ing environment.in Neuroinformatics LONI Pipeline Thompson, P. M. (2006).provenance using the LONI pipeline workfl ow environment.

  14. Exploiting level sensitive latches in wire pipelining 

    E-Print Network [OSTI]

    Seth, Vikram

    2005-02-17T23:59:59.000Z

    The present research presents procedures for exploitation of level sensitive latches in wire pipelining. The user gives a Steiner tree, having a signal source and set of destination or sinks, and the location in rectangular plane, capacitive load...

  15. Pipeline Politics: Natural Gas in Eurasia 

    E-Print Network [OSTI]

    Landrum, William W.; Llewellyn, Benjamin B.; Limesand, Craig M.; Miller, Dante J.; Morris, James P.; Nowell, Kathleen S.; Sherman, Charlotte L.

    2010-01-01T23:59:59.000Z

    important to US efforts to reduce its reliance on Middle Eastern energy resources. Presently, pipelines in Eurasia stretch across thousands of miles throughout unstable political regions. Disruptions in gas and oil supplies negatively affect the economies...

  16. Natural Pipeline of America Check Presentation 

    E-Print Network [OSTI]

    Unknown

    2011-08-17T23:59:59.000Z

    An archaeological investigation of approximately 1000 feet of a proposed 22,000 foot natural gas pipeline in southeastern Orange County, Texas was performed by Brazos Valley Research Associates of Bryan, Texas in August 2001. No archaeological sites...

  17. On-the-fly pipeline parallelism

    E-Print Network [OSTI]

    Lee, I-Ting Angelina

    Pipeline parallelism organizes a parallel program as a linear sequence of s stages. Each stage processes elements of a data stream, passing each processed data element to the next stage, and then taking on a new element ...

  18. A Pipeline for Computational Historical Linguistics

    E-Print Network [OSTI]

    #12;A Pipeline for Computational Historical Linguistics Lydia Steiner Bioinformatics Group of computational methods. In the biological context, computational methods play a dominating role due, Interdisciplinary Center for Bioinformatics, University of Leipzig Peter F. Stadler Bioinformatics Group

  19. Gas Pipeline Safety Rules (Alabama)

    Broader source: Energy.gov [DOE]

    All public utilities and persons subject to this rule shall file with the commission an operating and maintenance plan as well as an emergency plan. All construction work involving the addition and...

  20. Field tests of probes for detecting internal corrosion of natural gas transmission pipelines

    SciTech Connect (OSTI)

    Covino, Bernard S., Jr.; Bullard, Sophie J.; Cramer, Stephen D.; Holcomb, Gordon R.; Ziomek-Moroz, M.; Cayard, Michael S. (Intercorr International Inc.); Kane, Russell D. (Intercorr International Inc.); Meidinger, Brian (RMOTC-DOE)

    2005-01-01T23:59:59.000Z

    A field study was conducted to evaluate the use of electrochemical corrosion rate (ECR) probes for detecting corrosion in environments similar to those found in natural gas transmission pipelines. Results and interpretation will be reported from four different field tests. Flange and flush-mount probes were used in four different environments at a gas-gathering site and one environment but two different orientations at a natural gas plant. These sites were selected to represent normal and upset conditions in a gas transmission pipeline. The environments consisted of 2 different levels of humidified natural gas/organic/water mixtures removed from natural gas, and the environments at the 6 and 12 o'clock positions of a natural gas pipeline carrying 2-phase gas/liquid flow. Data are also presented comparing the ECR probe data to that for coupons used to determine corrosion rate and to detect the presence of microbiologically influenced corrosion (MIC).

  1. Climate Change and Water Resources in California: The Cost of Conservation versus Supply Augmentation for the East Bay Municipal Utility District

    E-Print Network [OSTI]

    Mourad, Bessma

    2009-01-01T23:59:59.000Z

    Gammon, Rovert. 2009. Sierra Water Grab. East Bay Express,www.eastbayexpress.com/news/sierra_water_grab/Content? oid=UCB: 1070. Maddaus Water Management.   Conservation

  2. Report of the Committee on oil pipeline regulation

    SciTech Connect (OSTI)

    Not Available

    1992-01-01T23:59:59.000Z

    Safety, interpretations of FERC Opinion 154-B, and a variation on the theme of oil pipeline deregulation were the significant developments affecting oil pipelines in the year 1991 and early 1992. The introduction of amendments to the Hazardous Liquid Pipeline Safety Act will result in Department of Transportation Regulations concerning in-depth reporting requirements of pipeline incidents and more frequent testing procedures to insure the safety of the pipeline. In November, 1991, Congressman Synar introduced a bill to streamline Federal Energy Regulatory Commission (FERC) procedures concerning oil pipelines.

  3. Figure 3-11 South Table Mountain Utilities Map

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Existing Buildings Electrical Figure 3-11 South Table Mountain Utilities Map Sewer Communication Water Surface Drainage Storm Water WATER TANK FACILITIES QUAKER STREET OLD QUA RRY...

  4. Overview of the design, construction, and operation of interstate liquid petroleum pipelines.

    SciTech Connect (OSTI)

    Pharris, T. C.; Kolpa, R. L.

    2008-01-31T23:59:59.000Z

    The U.S. liquid petroleum pipeline industry is large, diverse, and vital to the nation's economy. Comprised of approximately 200,000 miles of pipe in all fifty states, liquid petroleum pipelines carried more than 40 million barrels per day, or 4 trillion barrel-miles, of crude oil and refined products during 2001. That represents about 17% of all freight transported in the United States, yet the cost of doing so amounted to only 2% of the nation's freight bill. Approximately 66% of domestic petroleum transport (by ton-mile) occurs by pipeline, with marine movements accounting for 28% and rail and truck transport making up the balance. In 2004, the movement of crude petroleum by domestic federally regulated pipelines amounted to 599.6 billion tonmiles, while that of petroleum products amounted to 315.9 billion ton-miles (AOPL 2006). As an illustration of the low cost of pipeline transportation, the cost to move a barrel of gasoline from Houston, Texas, to New York Harbor is only 3 cents per gallon, which is a small fraction of the cost of gasoline to consumers. Pipelines may be small or large, up to 48 inches in diameter. Nearly all of the mainline pipe is buried, but other pipeline components such as pump stations are above ground. Some lines are as short as a mile, while others may extend 1,000 miles or more. Some are very simple, connecting a single source to a single destination, while others are very complex, having many sources, destinations, and interconnections. Many pipelines cross one or more state boundaries (interstate), while some are located within a single state (intrastate), and still others operate on the Outer Continental Shelf and may or may not extend into one or more states. U.S. pipelines are located in coastal plains, deserts, Arctic tundra, mountains, and more than a mile beneath the water's surface of the Gulf of Mexico (Rabinow 2004; AOPL 2006). The network of crude oil pipelines in the United States is extensive. There are approximately 55,000 miles of crude oil trunk lines (usually 8 to 24 inches in diameter) in the United States that connect regional markets. The United States also has an estimated 30,000 to 40,000 miles of small gathering lines (usually 2 to 6 inches in diameter) located primarily in Texas, Oklahoma, Louisiana, and Wyoming, with small systems in a number of other oil producing states. These small lines gather the oil from many wells, both onshore and offshore, and connect to larger trunk lines measuring 8 to 24 inches in diameter. There are approximately 95,000 miles of refined products pipelines nationwide. Refined products pipelines are found in almost every state in the United States, with the exception of some New England states. These refined product pipelines vary in size from relatively small, 8- to 12-inch-diameter lines, to up to 42 inches in diameter. The overview of pipeline design, installation, and operation provided in the following sections is only a cursory treatment. Readers interested in more detailed discussions are invited to consult the myriad engineering publications available that provide such details. The two primary publications on which the following discussions are based are: Oil and Gas Pipeline Fundamentals (Kennedy 1993) and the Pipeline Rules of Thumb Handbook (McAllister 2002). Both are recommended references for additional reading for those requiring additional details. Websites maintained by various pipeline operators also can provide much useful information, as well as links to other sources of information. In particular, the website maintained by the U.S. Department of Energy's Energy Information Administration (EIA) (http://www.eia.doe.gov) is recommended. An excellent bibliography on pipeline standards and practices, including special considerations for pipelines in Arctic climates, has been published jointly by librarians for the Alyeska Pipeline Service Company (operators of the Trans-Alaska Pipeline System [TAPS]) and the Geophysical Institute/International Arctic Research Center, both located in Fairbanks (Barboza and Trebelhorn 2001)

  5. The inspection of a radiologically contaminated pipeline using a teleoperated pipe crawler

    SciTech Connect (OSTI)

    Fogle, R.F.; Kuelske, K.; Kellner, R.A.

    1995-08-01T23:59:59.000Z

    In the 1950s, the Savannah River Site built an open, unlined retention basin to temporarily store potentially radionuclide contaminated cooling water from a chemical separations process and storm water drainage from a nearby waste management facility that stored large quantities of nuclear fission byproducts in carbon steel tanks. The retention basin was retired from service in 1972 when a new, lined basin was completed. In 1978, the old retention basin was excavated, backfilled with uncontaminated dirt, and covered with grass. At the same time, much of the underground process pipeline leading to the basin was abandoned. Since the closure of the retention basin, new environmental regulations require that the basin undergo further assessment to determine whether additional remediation is required. A visual and radiological inspection of the pipeline was necessary to aid in the remediation decision making process for the retention basin system. A teleoperated pipe crawler inspection system was developed to survey the abandoned sections of underground pipelines leading to the retired retention basin. This paper will describe the background to this project, the scope of the investigation, the equipment requirements, and the results of the pipeline inspection.

  6. Public Utilities Commission Consumer Programs

    E-Print Network [OSTI]

    California Public Utilities Commission Consumer Programs Water Programs The CPUC regulates privately owned water companies, which may provide specific as- sistance programs that are unique to each about consumer programs. For infor- mation on income eligibility limits and for a list of water

  7. api pipeline conference: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    of both pipelining methods. We applied our method to 1-bit and 2-bit adder Ha, Dong S. 7 Hydrogen Pipeline Material Testing We provide critical data, measurement methods and...

  8. ,"U.S. Natural Gas Pipeline Imports From Canada (MMcf)"

    U.S. Energy Information Administration (EIA) Indexed Site

    2015 1:45:50 PM" "Back to Contents","Data 1: U.S. Natural Gas Pipeline Imports From Canada (MMcf)" "Sourcekey","N9102CN2" "Date","U.S. Natural Gas Pipeline Imports From Canada...

  9. Some applications of pipelining techniques in parallel scientific computing 

    E-Print Network [OSTI]

    Deng, Yuanhua

    1996-01-01T23:59:59.000Z

    In this thesis, we study the applicability of pipelining techniques to the development of parallel algorithms for scientific computation. General principles for pipelining techniques are discussed and two applications, Gram-Schmidt orthogonalization...

  10. Statistical Modeling of Corrosion Failures in Natural Gas Transmission Pipelines 

    E-Print Network [OSTI]

    Cobanoglu, Mustafa Murat

    2014-03-28T23:59:59.000Z

    Natural gas pipelines are a critical component of the U.S. energy infrastructure. The safety of these pipelines plays a key role for the gas industry. Therefore, the understanding of failure characteristics and their consequences are very important...

  11. Statistical Modeling of Corrosion Failures in Natural Gas Transmission Pipelines

    E-Print Network [OSTI]

    Cobanoglu, Mustafa Murat

    2014-03-28T23:59:59.000Z

    and deterioration processes in pipeline networks. Therefore, pipeline operators need to rethink their corrosion prevention strategies. These results of corrosion failures are forcing the companies to develop accurate maintenance models based on failure frequency...

  12. Some applications of pipelining techniques in parallel scientific computing

    E-Print Network [OSTI]

    Deng, Yuanhua

    1996-01-01T23:59:59.000Z

    In this thesis, we study the applicability of pipelining techniques to the development of parallel algorithms for scientific computation. General principles for pipelining techniques are discussed and two applications, Gram-Schmidt orthogonalization...

  13. Blending Hydrogen into Natural Gas Pipeline Networks: A Review...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Blending Hydrogen into Natural Gas Pipeline Networks: A Review of Key Issues Blending Hydrogen into Natural Gas Pipeline Networks: A Review of Key Issues The United States has 11...

  14. Leakage Risk Assessment of CO{sub 2} Transportation by Pipeline at the Illinois Basin Decatur Project, Decatur, Illinois

    SciTech Connect (OSTI)

    Mazzoldi, A.; Oldenburg, C. M.

    2013-12-17T23:59:59.000Z

    The Illinois Basin Decatur Project (IBDP) is designed to confirm the ability of the Mt. Simon Sandstone, a major regional saline-water-bearing formation in the Illinois Basin, to store 1 million tons of carbon dioxide (CO{sub 2}) injected over a period of three years. The CO{sub 2} will be provided by Archer Daniels Midland (ADM) from its Decatur, Illinois, ethanol plant. In order to transport CO{sub 2} from the capture facility to the injection well (also located within the ADM plant boundaries), a high-pressure pipeline of length 3,200 ft (975 m) has been constructed, running above the ground surface within the ADM plant footprint. We have qualitatively evaluated risks associated with possible pipeline failure scenarios that lead to discharge of CO{sub 2} within the real-world environment of the ADM plant in which there are often workers and visitors in the vicinity of the pipeline. There are several aspects of CO{sub 2} that make its transportation and potential leakage somewhat different from other substances, most notable is its non-flammability and propensity to change to solid (dry ice) upon strong decompression. In this study, we present numerical simulations using Computational Fluid Dynamics (CFD) methods of the release and dispersion of CO{sub 2} from individual hypothetical pipeline failures (i.e., leaks). Failure frequency of the various components of a pipeline transportation system over time are taken from prior work on general pipeline safety and leakage modeling and suggest a 4.65% chance of some kind of pipeline failure over the three-years of operation. Following the Precautionary Principle (see below), we accounted for full-bore leakage scenarios, where the temporal evolution of the mass release rate from the high-pressure pipeline leak locations was simulated using a state-of-the-art Pipe model which considers the thermodynamic effects of decompression in the entire pipeline. Failures have been simulated at four representative locations along the pipeline route within the ADM plant. Leakage scenarios at sites along the route of the pipeline, where plant operations (e.g., vehicular and train transportation) seem to present a higher likelihood of accidental failure, for example due to vehicles or equipment crashing into the pipeline and completely severing it, were modeled by allowing them to have a double source consistent with the pipeline releasing high-pressure CO{sub 2} from both ends of the broken pipe after a full-bore offset rupture. Simulation results show that the built environment of the plant plays a significant role in the dispersion of the gas as leaking CO{sub 2} can impinge upon buildings and other infrastructure. In all scenarios simulated, the region of very high-concentration of CO{sub 2} is limited to a small area around the pipeline failure, suggesting the likelihood of widespread harmful CO{sub 2} exposure to plant personnel from pipeline leakage is low. An additional risk is posed by the blast wave that emanates from a high-pressure pipeline when it is breached quickly. We estimate the blast wave risk as low because it occurs only for a short time in the immediate vicinity of the rupture, and requires an instantaneous large-scale rupture to occur. We recommend consideration of signage and guard rails and posts to mitigate the likelihood of vehicles crashing into the pipeline. A standardized emergency response plan applicable to capture plants within industrial sites could be developed based on the IBDP that would be useful for other capture plants. Finally, we recommend carrying out coupled wellbore-reservoir blowout scenario modeling to understand the potential for hazardous conditions arising from an unexpected blowout at the wellhead.

  15. Altamont gas pipeline project delayed 1 year

    SciTech Connect (OSTI)

    Not Available

    1992-08-03T23:59:59.000Z

    Altamont Gas Transmission Co. will delay laying a 30 in., 620 mile pipeline to deliver Canadian gas to California until markets become more responsive. This paper reports that the decision will delay until November 1994 completion of the proposed 719 MMcfd, $612 million line. The original schedule called for construction to begin in spring 1993 with an in-service date of late 1993. Altamont pipeline is to transport gas from the US-Canadian border at Port of Wild Horse, Mont., to Opal, Wyo., where it will interconnect with the Kern River Transmission Co. pipeline to California. Altamont has obtained all regulatory approvals for its project. Altamont the project sponsors Tenneco Gas, Amoco Corp., and Entech Inc. support the decision to delay the start of construction.

  16. Coal-log pipeline system development

    SciTech Connect (OSTI)

    Liu, H.

    1991-12-01T23:59:59.000Z

    Project tasks include: (1) Perform the necessary testing and development to demonstrate that the amount of binder in coal logs can be reduced to 8% or lower to produce logs with adequate strength to eliminate breakage during pipeline transportation, under conditions experienced in long distance pipeline systems. Prior to conducting any testing and demonstration, grantee shall perform an information search and make full determination of all previous attempts to extrude or briquette coal, upon which the testing and demonstration shall be based. (2) Perform the necessary development to demonstrate a small model of the most promising injection system for coal-logs, and tests the logs produced. (3) Conduct economic analysis of coal-log pipeline, based upon the work to date. Refine and complete the economic model. (VC)

  17. Design of a model pipeline for testing of piezoelectric micro power generator for the Trans-Alaska Pipeline System

    E-Print Network [OSTI]

    Lah, Mike M. (Mike Myoung)

    2007-01-01T23:59:59.000Z

    In order to provide a reliable corrosion detection system for the Trans-Alaska Pipeline System (TAPS), a distributed wireless self-powered sensor array is needed to monitor the entire length of the pipeline at all times. ...

  18. Evolution of Graphics Pipelines 1 Understanding the Graphics Heritage

    E-Print Network [OSTI]

    Verschelde, Jan

    Evolution of Graphics Pipelines 1 Understanding the Graphics Heritage the era of fixed-function graphics pipelines the stages to render triangles 2 Programmable Real-Time Graphics programmable vertex and fragment processors an example of a programmable pipeline unified graphics and computing processors GPU

  19. Sensor and transmitter system for communication in pipelines

    DOE Patents [OSTI]

    Cooper, John F.; Burnham, Alan K.

    2013-01-29T23:59:59.000Z

    A system for sensing and communicating in a pipeline that contains a fluid. An acoustic signal containing information about a property of the fluid is produced in the pipeline. The signal is transmitted through the pipeline. The signal is received with the information and used by a control.

  20. Architectural Considerations for Application-Specific Counterflow Pipelines

    E-Print Network [OSTI]

    Childers, Bruce

    a new pipeline organization called the Counterflow Pipeline (CFP). This paper evaluates CFP design to an application can be constructed automatically. Third, we present measurements that evaluate CFP design tradeArchitectural Considerations for Application-Specific Counterflow Pipelines Bruce R. Childers, Jack

  1. Method for route selection of transcontinental natural gas pipelines

    E-Print Network [OSTI]

    Kouroupetroglou, Georgios

    1 Method for route selection of transcontinental natural gas pipelines Fotios G. Thomaidis1@kepa.uoa.gr Abstract. The route of transcontinental natural gas pipelines is characterized by complexity, compared choices. Keywords: Optimum route method, natural gas, transcontinental pipelines, Caspian Region ­ E

  2. Pipeline inspection using an autonomous underwater vehicle

    SciTech Connect (OSTI)

    Egeskov, P.; Bech, M. [Maridan Aps., Hoersholm (Denmark); Bowley, R. [TSS Ltd., Weston-on-the-Green (United Kingdom); Aage, C. [Technical Univ. of Denmark, Lyngby (Denmark). Dept. of Ocean Engineering

    1995-12-31T23:59:59.000Z

    Pipeline inspection can be carried out by means of small Autonomous Underwater Vehicles (AUVs), operating either with a control link to a surface vessel, or totally independently. The AUV offers an attractive alternative to conventional inspection methods where Remotely Operated Vehicles (ROVs) or paravanes are used. A flatfish type AUV ``MARTIN`` (Marine Tool for Inspection) has been developed for this purpose. The paper describes the proposed types of inspection jobs to be carried out by ``MARTIN``. The design and construction of the vessel, its hydrodynamic properties, its propulsion and control systems are discussed. The pipeline tracking and survey systems, as well as the launch and recovery systems are described.

  3. Software design for panoramic astronomical pipeline processing

    E-Print Network [OSTI]

    Lior Shamir; Robert J. Nemiroff; David O. Torrey; Wellesley E. Pereira

    2005-11-23T23:59:59.000Z

    We describe the software requirement and design specifications for all-sky panoramic astronomical pipelines. The described software aims to meet the specific needs of super-wide angle optics, and includes cosmic-ray hit rejection, image compression, star recognition, sky opacity analysis, transient detection and a web server allowing access to real-time and archived data. The presented software is being regularly used for the pipeline processing of 11 all-sky cameras located in some of the world's premier observatories. We encourage all-sky camera operators to use our software and/or our hosting services and become part of the global Night Sky Live network.

  4. Innovative Electromagnetic Sensors for Pipeline Crawlers

    SciTech Connect (OSTI)

    J. Bruce Nestleroth

    2006-05-04T23:59:59.000Z

    Internal inspection of pipelines is an important tool for ensuring safe and reliable delivery of fossil energy products. Current inspection systems that are propelled through the pipeline by the product flow cannot be used to inspect all pipelines because of the various physical barriers they encounter. Recent development efforts include a new generation of powered inspection platforms that crawl slowly inside a pipeline and are able to maneuver past the physical barriers that can limit inspection. At Battelle, innovative electromagnetic sensors are being designed and tested for these new pipeline crawlers. The various sensor types can be used to assess a wide range of pipeline anomalies including corrosion, mechanical damage, and cracks. Battelle is in the final year on a projected three-year development effort. In the first year, two innovative electromagnetic inspection technologies were designed and tested. Both were based on moving high-strength permanent magnets to generate inspection energy. One system involved translating permanent magnets towards the pipe. A pulse of electric current would be induced in the pipe to oppose the magnetization according to Lenz's Law. The decay of this pulse would indicate the presence of defects in the pipe wall. This inspection method is similar to pulsed eddy current inspection methods, with the fundamental difference being the manner in which the current is generated. Details of this development effort were reported in the first semiannual report on this project. The second inspection methodology is based on rotating permanent magnets. The rotating exciter unit produces strong eddy currents in the pipe wall. At distances of a pipe diameter or more from the rotating exciter, the currents flow circumferentially. These circumferential currents are deflected by pipeline defects such as corrosion and axially aligned cracks. Simple sensors are used to detect the change in current densities in the pipe wall. The second semiannual report on this project reported on experimental and modeling results. The results showed that the rotating system was more adaptable to pipeline inspection and therefore only this system will be carried into the second year of the sensor development. In the third reporting period, the rotating system inspection was further developed. Since this is a new inspection modality without published fundamentals to build upon, basic analytical and experimental investigations were performed. A closed form equation for designing rotating exciters and positioning sensors was derived from fundamental principles. Also signal processing methods were investigated for detection and assessment of pipeline anomalies. A lock in amplifier approach was chosen as the method for detecting the signals. Finally, mechanical implementations for passing tight restrictions such as plug valves were investigated. This inspection concept is new and unique; a United States patent application has been submitted. In this reporting period, a general design of the rotating permanent magnet inspection system is presented. The rotating permanent magnet inspection system is feasible for pipes ranging in diameter from 8 to 18 inches using a two pole configuration. Experimental results and theoretical calculations provide the basis for selection of the critical design parameters. The parameters include a significant magnet to pipe separation that will facilitate the passage of pipeline features. With the basic values of critical components established, the next step is a detailed mechanical design of a pipeline ready inspection system.

  5. Utility Energy Service Contracts for Renewable Energy Projects

    Broader source: Energy.gov [DOE]

    Utility energy service contracts (UESCs) offer Federal agencies an effective means to implement energy efficiency, renewable energy, and water efficiency projects. In a UESC, a utility arranges...

  6. Climate Change and Water Resources in California: The Cost of Conservation versus Supply Augmentation for the East Bay Municipal Utility District

    E-Print Network [OSTI]

    Mourad, Bessma

    2009-01-01T23:59:59.000Z

    Climate change is projected to result in increasing water scarcity scenarios in California, and similar Mediterranean

  7. New system pinpoints leaks in ethylene pipeline

    SciTech Connect (OSTI)

    Hamande, A. [Solvay et Cie, Jemeppe sur Sambre (Belgium); Condacse, V.; Modisette, J. [Modisette Associates, Inc., Houston, TX (United States)

    1995-04-01T23:59:59.000Z

    A model-based leak detection, PLDS, developed by Modisette Associates, Inc., Houston has been operating on the Solvay et Cie ethylene pipeline since 1989. The 6-in. pipeline extends from Antwerp to Jemeppe sur Sambre, a distance of 73.5 miles and is buried at a depth of 3 ft. with no insulation. Except for outlets to flares, located every 6 miles for test purposes, there are no injections or deliveries along the pipeline. Also, there are block valves, which are normally open, at each flare location. This paper reviews the design and testing procedures used to determine the system performance. These tests showed that the leak system was fully operational and no false alarms were caused by abrupt changes in inlet/outlet flows of the pipeline. It was confirmed that leaks larger than 2 tonnes/hr. (40 bbl/hr) are quickly detected and accurately located. Also, maximum leak detection sensitivity is 1 tonne/hr. (20 bbl/hr) with a detection time of one hour. Significant operational, configuration, and programming issues also were found during the testing program. Data showed that temperature simulations needed re-examining for improvement since accurate temperature measurements are important. This is especially true for ethylene since its density depends largely on temperature. Another finding showed the averaging period of 4 hrs. was too long and a 1 to 2 hr. interval was better.

  8. The Coordinated Control of a Central Air Conditioning System Based on Variable Chilled Water Temperature and Variable Chilled Water Flow 

    E-Print Network [OSTI]

    Liu, J.; Mai, Y.; Liu, X.

    2006-01-01T23:59:59.000Z

    energy consumption of chiller and chiller water pump was taken as the objective function of the optimization model. The performance characteristics of a chiller, water pump, regulation valve and pipeline are taken into account, and the optimization...

  9. The Coordinated Control of a Central Air Conditioning System Based on Variable Chilled Water Temperature and Variable Chilled Water Flow

    E-Print Network [OSTI]

    Liu, J.; Mai, Y.; Liu, X.

    2006-01-01T23:59:59.000Z

    energy consumption of chiller and chiller water pump was taken as the objective function of the optimization model. The performance characteristics of a chiller, water pump, regulation valve and pipeline are taken into account, and the optimization...

  10. Sustainable Water Management in the Minerals Industry 1 SUSTAINABLE WATER MANAGEMENT IN THE MINERALS

    E-Print Network [OSTI]

    McGuinness, Mark

    Sustainable Water Management in the Minerals Industry 1 SUSTAINABLE WATER MANAGEMENT interest. It arises in the provision of water for Queensland coal mines, where additional water is available via a pipeline from a public supply, and also in cases where recycled or more expensive water

  11. Economic and Conservation Evaluation of Capital Renovation Projects: Brownsville Irrigation District – 72" and 54" Pipeline Replacing Main Canal – Preliminary 

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    2003-01-01T23:59:59.000Z

    ) and Bureau of Reclamation (BOR). The proposed project involves constructing a 72" and 54" pipeline to replace 2.29 miles of the “Main Canal.” Both nominal and real estimates of water and energy savings and expected economic and financial costs of those...

  12. Economic and Conservation Evaluation of Capital Renovation Projects: Brownsville Irrigation District – 72" and 48" Pipeline Replacing Main Canal – Final 

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    2003-01-01T23:59:59.000Z

    ) and Bureau of Reclamation (BOR). The proposed project involves constructing a 72" and 48" pipeline to replace 2.31 miles of the “Main Canal.” Both nominal and real estimates of water and energy savings and expected economic and financial costs of those...

  13. Economic and Conservation Evaluation of Capital Renovation Projects: Brownsville Irrigation District – 72" and 54" Pipeline Replacing Main Canal – Preliminary

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    ) and Bureau of Reclamation (BOR). The proposed project involves constructing a 72" and 54" pipeline to replace 2.29 miles of the “Main Canal.” Both nominal and real estimates of water and energy savings and expected economic and financial costs of those...

  14. Rochester Public Utilities- Solar Rebate Program

    Broader source: Energy.gov [DOE]

    Rochester Public Utilities provides incentives for residential and commercial customers to install photovoltaic (PV) and solar water heating systems. Qualifying PV systems can earn $1 per watt...

  15. Crossing Active Faults on the Sakhalin II Onshore Pipeline Route: Pipeline Design and Risk Analysis

    SciTech Connect (OSTI)

    Mattiozzi, Pierpaolo [Snamprogetti-Saipem, Via Toniolo, 1, 61032 Fano (Italy); Strom, Alexander [Institute of Geospheres Dynamics, Leninskiy Avenue, 38, Building 1, 119334, Moscow (Russian Federation)

    2008-07-08T23:59:59.000Z

    Twin oil (20 and 24 inch) and gas (20 and 48 inch) pipeline systems stretching 800 km are being constructed to connect offshore hydrocarbon deposits from the Sakhalin II concession in the North to an LNG plant and oil export terminal in the South of Sakhalin island. The onshore pipeline route follows a regional fault zone and crosses individual active faults at 19 locations. Sakhalin Energy, Design and Construction companies took significant care to ensure the integrity of the pipelines, should large seismic induced ground movements occur during the Operational life of the facilities. Complex investigations including the identification of the active faults, their precise location, their particular displacement values and assessment of the fault kinematics were carried out to provide input data for unique design solutions. Lateral and reverse offset displacements of 5.5 and 4.5 m respectively were determined as the single-event values for the design level earthquake (DLE) - the 1000-year return period event. Within the constraints of a pipeline route largely fixed, the underground pipeline fault crossing design was developed to define the optimum routing which would minimize stresses and strain using linepipe materials which had been ordered prior to the completion of detailed design, and to specify requirements for pipe trenching shape, materials, drainage system, etc. Detailed Design was performed with due regard to actual topography and to avoid the possibility of the trenches freezing in winter, the implementation of specific drainage solutions and thermal protection measures.

  16. The e-MERLIN Data Reduction Pipeline

    E-Print Network [OSTI]

    Argo, Megan

    2015-01-01T23:59:59.000Z

    Written in Python and utilising ParselTongue to interface with the Astronomical Image Processing System (AIPS), the e-MERLIN data reduction pipeline is intended to automate the procedures required in processing and calibrating radio astronomy data from the e-MERLIN correlator. Driven by a plain text file of input parameters, the pipeline is modular and can be run in stages by the user, depending on requirements. The software includes options to load raw data, average in time and/or frequency, flag known sources of interference, flag more comprehensively with SERPent, carry out some or all of the calibration procedures including self-calibration), and image in either normal or wide-field mode. It also optionally produces a number of useful diagnostic plots at various stages so that the quality of the data can be assessed. The software is available for download from the e-MERLIN website or via Github.

  17. Pipeline safety joint eliminates need for divers

    SciTech Connect (OSTI)

    Not Available

    1983-04-01T23:59:59.000Z

    The Sea-Hook coupling is a diverless pressure-compensated pipeline safety joint designed to protect the pipe from damage by excessive physical loads. The coupling provides a predetermined weak point in the line that will cause a controlled separation when the line is exposed to strong wave action or dragging anchors. Moreover, it offers prepressurized remote lockout protection, metal seal integrity, no hand-up separation, enclosed bolting, optimal manual lockout, and no springs or shear rings.

  18. Detecting internal corrosion of natural gas transmission pipelines: field tests of probes and systems for real-time corrosion measurement

    SciTech Connect (OSTI)

    Covino, Bernard S., Jr.; Bullard, Sophie J.; Cramer, Stephen D.; Holcomb, Gordon R.; Ziomek-Moroz, M.; Kane, R.D. (InterCorr International); Meidinger, B. (Rocky Mountain Oilfield Testing Center)

    2005-01-01T23:59:59.000Z

    A field study was conducted to evaluate the use of automated, multi-technique electrochemical corrosion-rate monitoring devices and probes for detecting corrosion in environments similar to those found in natural gas transmission pipelines. It involved measurement of real-time corrosion signals from operating pipelines. Results and interpretation were reported from four different field test locations. Standard flush-mount and custom flange probes were used in four different environments at a gas-gathering site and one environment but two different probe orientations at a natural gas site. These sites were selected to represent normal and upset conditions common in gas transmission pipelines. The environments consisted of two different levels of humidified natural gas, liquid hydrocarbon, and water from natural gas. Probe locations included the 6 and 12 o?clock positions of a natural gas pipeline carrying 2-phase gas/liquid flow. The probe data was monitored using completely remote solar powered systems that provided real-time data transmission via wireless back to a pipeline control station. Data are also presented comparing the ECR probe data to that for coupons used to determine corrosion rate and to detect the presence of microbiologically influenced corrosion (MIC).

  19. Remarks Concerning the Public Utility Commission of Texas Study on Bulk Power Transmission

    E-Print Network [OSTI]

    Sweatman, R. T.

    REMARKS CONCERNING THE PUBLIC UTILITY COMMISSION OF TEXAS STUDY ON BULK POWER TRANSMISSION R. T. SWEATMAN Executive Director Electric Reliability Council of Texas The citizens of Texas need reliable electric service. Our economy, our way... amounts of transmission capacity must alwavs be available in the event generation is lost in one area, so that the other utility's power can be transmitted to the utility in need. A pipeline system can suffer equipment outages easily, without loss...

  20. Hydrogen pipeline compressors annual progress report.

    SciTech Connect (OSTI)

    Fenske, G. R.; Erck, R. A. (Energy Systems)

    2011-07-15T23:59:59.000Z

    The objectives are: (1) develop advanced materials and coatings for hydrogen pipeline compressors; (2) achieve greater reliability, greater efficiency, and lower capital in vestment and maintenance costs in hydrogen pipeline compressors; and (3) research existing and novel hydrogen compression technologies that can improve reliability, eliminate contamination, and reduce cost. Compressors are critical components used in the production and delivery of hydrogen. Current reciprocating compressors used for pipeline delivery of hydrogen are costly, are subject to excessive wear, have poor reliability, and often require the use of lubricants that can contaminate the hydrogen (used in fuel cells). Duplicate compressors may be required to assure availability. The primary objective of this project is to identify, and develop as required, advanced materials and coatings that can achieve the friction, wear, and reliability requirements for dynamically loaded components (seal and bearings) in high-temperature, high-pressure hydrogen environments prototypical of pipeline and forecourt compressor systems. The DOE Strategic Directions for Hydrogen Delivery Workshop identified critical needs in the development of advanced hydrogen compressors - notably, the need to minimize moving parts and to address wear through new designs (centrifugal, linear, guided rotor, and electrochemical) and improved compressor materials. The DOE is supporting several compressor design studies on hydrogen pipeline compression specifically addressing oil-free designs that demonstrate compression in the 0-500 psig to 800-1200 psig range with significant improvements in efficiency, contamination, and reliability/durability. One of the designs by Mohawk Innovative Technologies Inc. (MiTi{reg_sign}) involves using oil-free foil bearings and seals in a centrifual compressor, and MiTi{reg_sign} identified the development of bearings, seals, and oil-free tribological coatings as crucial to the successful development of an advanced compressor. MiTi{reg_sign} and ANL have developed potential coatings for these rigorous applications; however, the performance of these coatings (as well as the nickel-alloy substrates) in high-temperature, high-speed hydrogen environments is unknown at this point.

  1. Virtual Pipeline System Testbed to Optimize the U.S. Natural Gas Transmission Pipeline System

    SciTech Connect (OSTI)

    Kirby S. Chapman; Prakash Krishniswami; Virg Wallentine; Mohammed Abbaspour; Revathi Ranganathan; Ravi Addanki; Jeet Sengupta; Liubo Chen

    2005-06-01T23:59:59.000Z

    The goal of this project is to develop a Virtual Pipeline System Testbed (VPST) for natural gas transmission. This study uses a fully implicit finite difference method to analyze transient, nonisothermal compressible gas flow through a gas pipeline system. The inertia term of the momentum equation is included in the analysis. The testbed simulate compressor stations, the pipe that connects these compressor stations, the supply sources, and the end-user demand markets. The compressor station is described by identifying the make, model, and number of engines, gas turbines, and compressors. System operators and engineers can analyze the impact of system changes on the dynamic deliverability of gas and on the environment.

  2. api x80 pipeline: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    C Fortran API 3. c 1959 Information Processing Society of Japan 3 Kasahara, Hironori 9 Hydrogen Pipeline Material Testing We provide critical data, measurement methods and...

  3. alaska oil pipeline: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Applied Oil Spill Research & Development Program Electronic Bibliography 1998-01-01 24 Hydrogen Pipeline Safety Our goal is to establish the codes and standards necessary...

  4. ,"International Falls, MN Natural Gas Pipeline Imports From Canada...

    U.S. Energy Information Administration (EIA) Indexed Site

    International Falls, MN Natural Gas Pipeline Imports From Canada (MMcf)" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description"," Of...

  5. ,"Highgate Springs, VT Natural Gas Pipeline Imports From Canada...

    U.S. Energy Information Administration (EIA) Indexed Site

    Highgate Springs, VT Natural Gas Pipeline Imports From Canada (MMcf)" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description"," Of Series","Frequency","L...

  6. ,"Corsby, ND Natural Gas Pipeline Imports From Canada (MMcf)...

    U.S. Energy Information Administration (EIA) Indexed Site

    Corsby, ND Natural Gas Pipeline Imports From Canada (MMcf)" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description"," Of Series","Frequency","Latest Data...

  7. ,"Sault St Marie, MI Natural Gas Pipeline Exports to Canada ...

    U.S. Energy Information Administration (EIA) Indexed Site

    Sault St Marie, MI Natural Gas Pipeline Exports to Canada (Million Cubic Feet)" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description"," Of...

  8. ,"Sweetgrass, MT Natural Gas Pipeline Imports From Canada (MMcf...

    U.S. Energy Information Administration (EIA) Indexed Site

    Sweetgrass, MT Natural Gas Pipeline Imports From Canada (MMcf)" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description"," Of Series","Frequency","Latest...

  9. ,"North Troy, VT Natural Gas Pipeline Imports From Canada (MMcf...

    U.S. Energy Information Administration (EIA) Indexed Site

    Troy, VT Natural Gas Pipeline Imports From Canada (MMcf)" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description"," Of Series","Frequency","Latest Data...

  10. ,"Whitlash, MT Natural Gas Pipeline Imports From Canada (MMcf...

    U.S. Energy Information Administration (EIA) Indexed Site

    Whitlash, MT Natural Gas Pipeline Imports From Canada (MMcf)" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description"," Of Series","Frequency","Latest...

  11. ,"Champlain, NY Natural Gas Pipeline Imports From Canada (MMcf...

    U.S. Energy Information Administration (EIA) Indexed Site

    Champlain, NY Natural Gas Pipeline Imports From Canada (MMcf)" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description"," Of Series","Frequency","Latest...

  12. ,"Portal, ND Natural Gas Pipeline Imports From Canada (MMcf)...

    U.S. Energy Information Administration (EIA) Indexed Site

    Portal, ND Natural Gas Pipeline Imports From Canada (MMcf)" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description"," Of Series","Frequency","Latest Data...

  13. ,"New York Natural Gas Pipeline and Distribution Use Price (Dollars...

    U.S. Energy Information Administration (EIA) Indexed Site

    Name","Description"," Of Series","Frequency","Latest Data for" ,"Data 1","New York Natural Gas Pipeline and Distribution Use Price (Dollars per Thousand Cubic...

  14. Panel 2, Hydrogen Delivery in the Natural Gas Pipeline Network

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    in the Natural Gas Pipeline Network DOE'S HYDROGEN ENERGY STORAGE FOR GRID AND TRANSPORTATION SERVICES WORKSHOP Sacramento, CA May 14, 2014 Brian Weeks Gas Technology Institute 2 2...

  15. Sequencing Technologies and Computational pipelines at the JGI

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Sequencing Technologies and Computational pipelines at the JGI September 17, 2013 JGI logo 2 James Han, JGI sequencing QAQC group lead Tuesday, Sep. 17, 2003 OSF Room 238...

  16. EIA - Natural Gas Pipeline Network - Aquifer Storage Reservoir...

    Gasoline and Diesel Fuel Update (EIA)

    Configuration About U.S. Natural Gas Pipelines - Transporting Natural Gas based on data through 20072008 with selected updates Aquifer Underground Natural Gas Storage...

  17. EIA - Natural Gas Pipeline Network - Depleted Reservoir Storage...

    Gasoline and Diesel Fuel Update (EIA)

    Configuration About U.S. Natural Gas Pipelines - Transporting Natural Gas based on data through 20072008 with selected updates Depleted Production Reservoir Underground...

  18. Comparing Existing Pipeline Networks with the Potential Scale of Future U.S. CO2 Pipeline Networks

    SciTech Connect (OSTI)

    Dooley, James J.; Dahowski, Robert T.; Davidson, Casie L.

    2008-02-29T23:59:59.000Z

    There is growing interest regarding the potential size of a future U.S. dedicated CO2 pipeline infrastructure if carbon dioxide capture and storage (CCS) technologies are commercially deployed on a large scale. In trying to understand the potential scale of a future national CO2 pipeline network, comparisons are often made to the existing pipeline networks used to deliver natural gas and liquid hydrocarbons to markets within the U.S. This paper assesses the potential scale of the CO2 pipeline system needed under two hypothetical climate policies and compares this to the extant U.S. pipeline infrastructures used to deliver CO2 for enhanced oil recovery (EOR), and to move natural gas and liquid hydrocarbons from areas of production and importation to markets. The data presented here suggest that the need to increase the size of the existing dedicated CO2 pipeline system should not be seen as a significant obstacle for the commercial deployment of CCS technologies.

  19. Extending the Fermi-LAT Data Processing Pipeline to the Grid

    E-Print Network [OSTI]

    Stephan Zimmer; Luisa Arrabito; Tom Glanzman; Tony Johnson; Claudia Lavalley; Andrei Tsaregorodtsev

    2012-12-17T23:59:59.000Z

    The Data Handling Pipeline ("Pipeline") has been developed for the Fermi Gamma-Ray Space Telescope (Fermi) Large Area Telescope (LAT) which launched in June 2008. Since then it has been in use to completely automate the production of data quality monitoring quantities, reconstruction and routine analysis of all data received from the satellite and to deliver science products to the collaboration and the Fermi Science Support Center. Aside from the reconstruction of raw data from the satellite (Level 1), data reprocessing and various event-level analyses are also reasonably heavy loads on the pipeline and computing resources. These other loads, unlike Level 1, can run continuously for weeks or months at a time. In addition it receives heavy use in performing production Monte Carlo tasks. The software comprises web-services that allow online monitoring and provides charts summarizing work flow aspects and performance information. The server supports communication with several batch systems such as LSF and BQS and recently also Sun Grid Engine and Condor. This is accomplished through dedicated job control services that for Fermi are running at SLAC and the other computing site involved in this large scale framework, the Lyon computing center of IN2P3. While being different in the logic of a task, we evaluate a separate interface to the Dirac system in order to communicate with EGI sites to utilize Grid resources, using dedicated Grid optimized systems rather than developing our own. (abstract abridged)

  20. A Dredging Knowledge-Base Expert System for Pipeline Dredges with Comparison to Field Data 

    E-Print Network [OSTI]

    Wilson, Derek Alan

    2011-02-22T23:59:59.000Z

    A Pipeline Analytical Program and Dredging Knowledge{Base Expert{System (DKBES) determines a pipeline dredge's production and resulting cost and schedule. Pipeline dredge engineering presents a complex and dynamic process necessary to maintain...

  1. Analysis of oil-pipeline distribution of multiple products subject to delivery time-windows 

    E-Print Network [OSTI]

    Jittamai, Phongchai

    2006-04-12T23:59:59.000Z

    This dissertation defines the operational problems of, and develops solution methodologies for, a distribution of multiple products into oil pipeline subject to delivery time-windows constraints. A multiple-product oil pipeline is a pipeline system...

  2. Tool Path Planning Generation For Finish Machining of Freeform Surfaces in the Cybercut Process Planning Pipeline

    E-Print Network [OSTI]

    Wright, Paul K; Dornfeld, David; Sundararajan, V.; Misra, Debananda

    2007-01-01T23:59:59.000Z

    CYBERCUT PROCESS PLANNING PIPELINE Paul K. Wright, David A.describes part of a "Pipeline of De- sign and Manufacturingversus surface finish. 2.5D PIPELINE AND 3D SURFACES Figure

  3. Black Radicals Make for Bad Citizens: Undoing the Myth of the School to Prison Pipeline

    E-Print Network [OSTI]

    Sojoyner, Damien M

    2013-01-01T23:59:59.000Z

    December 13). Prison pipeline hits Black students harder,http://politic365.com/2012/12/13/prison-pipeline-hits-black-The school-to-prison pipeline: Structuring legal reform. New

  4. MetAMOS: a modular and open source metagenomic assembly and analysis pipeline

    E-Print Network [OSTI]

    2013-01-01T23:59:59.000Z

    assembly and analysis pipeline. Genome Biology 2013 14:R2.assembly and analysis pipeline Todd J Treangen 1,2† , Sergeyassembly and analysis pipeline. MetAMOS represents an

  5. Analysis of oil-pipeline distribution of multiple products subject to delivery time-windows

    E-Print Network [OSTI]

    Jittamai, Phongchai

    2006-04-12T23:59:59.000Z

    This dissertation defines the operational problems of, and develops solution methodologies for, a distribution of multiple products into oil pipeline subject to delivery time-windows constraints. A multiple-product oil pipeline is a pipeline system...

  6. Beyond Myopic Inference in Big Data Pipelines Karthik Raman, Adith Swaminathan, Johannes Gehrke, Thorsten Joachims

    E-Print Network [OSTI]

    Joachims, Thorsten

    ]: Learning General Terms Algorithms, Experimentation, Theory Keywords Big Data Pipelines, Modular Design Detection & Recognition pipeline. creation, model construction, testing, and visualization. In orderBeyond Myopic Inference in Big Data Pipelines Karthik Raman, Adith Swaminathan, Johannes Gehrke

  7. The Oil Network in US:The Oil Network in US: A Closer Look at PipelinesA Closer Look at Pipelines

    E-Print Network [OSTI]

    Nagurney, Anna

    The Oil Network in US:The Oil Network in US: A Closer Look at PipelinesA Closer Look at Pipelines of Oil Network in USHistory of Oil Network in US Origin of pipelines:Origin of pipelines: WWII: Relied of transportationtransportation Need for a complex network:Need for a complex network: Move the raw materials (crude oils), from

  8. Panel: The Intersections of the IDEA and the School-to-Prison Pipeline (Audio file)

    E-Print Network [OSTI]

    Waterstone, Julie; Cannon, Yael; Rivera, Anna; Dudakia, Kunti

    2013-01-01T23:59:59.000Z

    as the School-to-Prison Pipeline-occurs, and will explorein the School-to-Prison Pipeline discourse will help the

  9. The VVDS data reduction pipeline: introducing VIPGI, the VIMOS Interactive Pipeline and Graphical Interface

    E-Print Network [OSTI]

    M. Scodeggio; P. Franzetti; B. Garilli; A. Zanichelli; S. Paltani; D. Maccagni; D. Bottini; V. Le Brun; T. Contini; R. Scaramella; C. Adami; S. Bardelli; E. Zucca; L. Tresse; O. Ilbert; S. Foucaud; A. Iovino; R. Merighi; G. Zamorani; I. Gavignaud; D. Rizzo; H. J. McCracken; O. Le Fevre; J. P. Picat; G. Vettolani; M. Arnaboldi; S. Arnouts; M. Bolzonella; A. Cappi; S. Charlot; L. Guzzo; B. Marano; C. Marinoni; G. Mathez; A. Mazure; B. Meneux; R. Pello; A. Pollo; L. Pozzetti M. Radovich

    2004-09-10T23:59:59.000Z

    The VIMOS VLT Deep Survey (VVDS), designed to measure 150,000 galaxy redshifts, requires a dedicated data reduction and analysis pipeline to process in a timely fashion the large amount of spectroscopic data being produced. This requirement has lead to the development of the VIMOS Interactive Pipeline and Graphical Interface (VIPGI), a new software package designed to simplify to a very high degree the task of reducing astronomical data obtained with VIMOS, the imaging spectrograph built by the VIRMOS Consortium for the European Southern Observatory, and mounted on Unit 3 (Melipal) of the Very Large Telescope (VLT) at Paranal Observatory (Chile). VIPGI provides the astronomer with specially designed VIMOS data reduction functions, a VIMOS-centric data organizer, and dedicated data browsing and plotting tools, that can be used to verify the quality and accuracy of the various stages of the data reduction process. The quality and accuracy of the data reduction pipeline are comparable to those obtained using well known IRAF tasks, but the speed of the data reduction process is significantly increased, thanks to the large set of dedicated features. In this paper we discuss the details of the MOS data reduction pipeline implemented in VIPGI, as applied to the reduction of some 20,000 VVDS spectra, assessing quantitatively the accuracy of the various reduction steps. We also provide a more general overview of VIPGI capabilities, a tool that can be used for the reduction of any kind of VIMOS data.

  10. A bubble detection system for propellant filling pipeline

    SciTech Connect (OSTI)

    Wen, Wen; Zong, Guanghua; Bi, Shusheng [Robotics Institute, Beihang University, 100191 Beijing (China)

    2014-06-15T23:59:59.000Z

    This paper proposes a bubble detection system based on the ultrasound transmission method, mainly for probing high-speed bubbles in the satellite propellant filling pipeline. First, three common ultrasonic detection methods are compared and the ultrasound transmission method is used in this paper. Then, the ultrasound beam in a vertical pipe is investigated, suggesting that the width of the beam used for detection is usually smaller than the internal diameter of the pipe, which means that when bubbles move close to the pipe wall, they may escape from being detected. A special device is designed to solve this problem. It can generate the spiral flow to force all the bubbles to ascend along the central line of the pipe. In the end, experiments are implemented to evaluate the performance of this system. Bubbles of five different sizes are generated and detected. Experiment results show that the sizes and quantity of bubbles can be estimated by this system. Also, the bubbles of different radii can be distinguished from each other. The numerical relationship between the ultrasound attenuation and the bubble radius is acquired and it can be utilized for estimating the unknown bubble size and measuring the total bubble volume.

  11. Materials Solutions for Hydrogen Delivery in Pipelines

    SciTech Connect (OSTI)

    Ningileri, Shridas T.; Boggess, Todd A; Stalheim, Douglas

    2013-01-02T23:59:59.000Z

    The main objective of the study is as follows: Identify steel compositions/microstructures suitable for construction of new pipeline infrastructure and evaluate the potential use of the existing steel pipeline infrastructure in high pressure gaseous hydrogen applications. The microstructures of four pipeline steels were characterized and tensile testing was conducted in gaseous hydrogen and helium at pressures of 5.5 MPa (800 psi), 11 MPa (1600 psi) and 20.7 MPa (3000 psi). Based on reduction of area, two of the four steels that performed the best across the pressure range were selected for evaluation of fracture and fatigue performance in gaseous hydrogen at 5.5 MPa (800 psi) and 20.7 MPa (3000 psi). The basic format for this phase of the study is as follows: Microstructural characterization of volume fraction of phases in each alloy; Tensile testing of all four alloys in He and H{sub 2} at 5.5 MPa (800 psi), 11 MPa (1600 psi), and 20.7 MPa (3000 psi). RA performance was used to choose the two best performers for further mechanical property evaluation; Fracture testing (ASTM E1820) of two best tensile test performers in H{sub 2} at 5.5 MPa (800 psi) and 20.7 MPa (3000 psi); Fatigue testing (ASTM E647) of two best tensile test performers in H2 at 5.5 MPa (800 psi) and 20.7 MPa (3000 psi) with frequency =1.0 Hz and R-ratio=0.5 and 0.1.

  12. Praxair extending hydrogen pipeline in Southeast Texas

    SciTech Connect (OSTI)

    Not Available

    1992-08-24T23:59:59.000Z

    This paper reports that Praxair Inc., an independent corporation created by the spinoff of Union Carbide Corp.'s Linde division, is extending its high purity hydrogen pipeline system from Channelview, Tex., to Port Arthur, Tex. The 70 mile, 10 in. extension begins at a new pressure swing adsorption (PSA) purification unit next to Lyondell Petrochemical Co.'s Channelview plant. The PSA unit will upgrade hydrogen offgas from Lyondell's methanol plant to 99.99% purity hydrogen. The new line, advancing at a rate of about 1 mile/day, will reach its first customer, Star Enterprise's 250,000 b/d Port Arthur refinery, in September.

  13. The QUEST Data Processing Software Pipeline

    E-Print Network [OSTI]

    Peter Andrews; Charles Baltay; Anne Bauer; Nancy Ellman; Jonathan Jerke; Rochelle Lauer; David Rabinowitz; Julia Silge

    2007-03-16T23:59:59.000Z

    A program that we call the QUEST Data Processing Software Pipeline has been written to process the large volumes of data produced by the QUEST camera on the Samuel Oschin Schmidt Telescope at the Palomar Observatory. The program carries out both aperture and PSF photometry, combines data from different repeated observations of the same portion of sky, and produces a Master Object Catalog. A rough calibration of the data is carried out. This program, as well as the calibration procedures and quality checks on the output are described.

  14. EIA - Natural Gas Pipeline System - Southwest Region

    Annual Energy Outlook 2013 [U.S. Energy Information Administration (EIA)]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 111 1,613 122 40Coal Stocks at1,066,688 760,877Southwest Region About U.S. Natural Gas Pipelines

  15. Hydrogen Pipeline Working Group | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy ChinaofSchaefer To:Department ofOral Testimony ofMonitoring, ProtectionofHydrogen Pipeline

  16. EIA-812, Monthly Product Pipeline Report

    U.S. Energy Information Administration (EIA) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere IRaghuraji Agro IndustriesTownDells, Wisconsin:DeploymentSite Name: Email: Terminal2, Monthly Product Pipeline

  17. Hydrogen Pipeline Discussion | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't YourTransport(Fact Sheet), GeothermalGridHYDROGEND D e e&FundingDiscussion Hydrogen Pipeline

  18. Federal Utility Partnership Working Group Utility Partners

    Broader source: Energy.gov [DOE]

    Federal Utility Partnership Working Group (FUPWG) utility partners are eager to work closely with Federal agencies to help achieve energy management goals.

  19. Term-Level Verification of a Pipelined CISC Microprocessor

    E-Print Network [OSTI]

    Term-Level Verification of a Pipelined CISC Microprocessor Randal E. Bryant December, 2005 CMU verification, Microprocessor verification, UCLID #12;Abstract By abstracting the details of the data representations and operations in a microprocessor, term-level verification can formally prove that a pipelined

  20. TermLevel Verification of a Pipelined CISC Microprocessor

    E-Print Network [OSTI]

    Term­Level Verification of a Pipelined CISC Microprocessor Randal E. Bryant December, 2005 CMU verification, Microprocessor verification, UCLID #12; Abstract By abstracting the details of the data representations and operations in a microprocessor, term­level verification can formally prove that a pipelined

  1. Accelerating Pipelined Integer and Floating-Point Accumulations in Configurable

    E-Print Network [OSTI]

    Martonosi, Margaret

    Accelerating Pipelined Integer and Floating-Point Accumulations in Configurable Hardware addition until the end of a repeated calculation such as accumulation or dot- product; this effectively and floating- point designs that use our technique. Our pipelined integer multiply-accumulate (MAC) design

  2. How Safe Are Pipelines? Diana Furchtgott-Roth

    E-Print Network [OSTI]

    Calgary, University of

    18% 11% 14% 26% Natural Gas Distribution 25% 78% 76% 15% Hazardous Liquid 55% 11% 9% 53% #12;NumberHow Safe Are Pipelines? Diana Furchtgott-Roth Director, Economics21, Manhattan Institute Moving-Miles Transported: Petroleum Pipeline and Class I Rail Source: "Final Supplemental Environmental Impact Statement

  3. Rapid communication Mapping urban pipeline leaks: Methane leaks across Boston

    E-Print Network [OSTI]

    Jackson, Robert B.

    transmission and distribution pipelines for natural gas in the U. S. cause an average of 17 fatalities, 68 signatures w20& lighter (m ¼ À57.8&, Æ1.6& s.e., n ¼ 8). Repairing leaky natural gas distribution systems injuries, and $133 M in property damage each year (PHMSA, 2012). A natural gas pipeline explosion in San

  4. ABB Review 4/2000 55 ultiphase pipelines connecting

    E-Print Network [OSTI]

    Skogestad, Sigurd

    ABB Review 4/2000 55 ultiphase pipelines connecting remote wellhead platforms and subsea wells of the multi-phase pipelines connecting wells and remote installations to the processing unit. One common form and unstable, it is difficult to predict the pressure drop, heat and mass transfer. In addition, the flow

  5. Localized Pipeline Encroachment Detector System Using Sensor Network 

    E-Print Network [OSTI]

    Ou, Xiaoxi 1986-

    2011-08-08T23:59:59.000Z

    Detection of encroachment on pipeline right-of-way is important for pipeline safety. An effective system can provide on-time warning while reducing the probability of false alarms. There are a number of industry and academic developments to tackle...

  6. Pipelined Mutual Exclusion and The Design of an Asynchronous Microprocessor *

    E-Print Network [OSTI]

    Martin, Alain

    RVM46 -1 Pipelined Mutual Exclusion and The Design of an Asynchronous Microprocessor * Rajit; Pipelining; Microprocessor design; Program transformation. 1. Introduction Formal transformations are an e#11 by construction [3]. In the design of asynchronous systems, it is important to be able to decouple various parts

  7. Program permits fast solution to pipeline loop requirements

    SciTech Connect (OSTI)

    Bierman, G.D.

    1983-10-31T23:59:59.000Z

    A program developed for the HP-41CV hand-held calculator can provide pipeline engineers with a quick and easy means for determining loop requirements on existing gas-transmission pipelines. Adding pipe in parallel to an existing pipeline, referred to as looping, is necessary to insure that with a given flow rate, the gas will arrive at a certain point on the pipeline with a pressure equal to or greater than the minimum required pressure. The automatic loop program calculates loop by first determining the total number of segments which require looping within the section of pipeline being evaluated. A section of pipe is usually the pipeline between compressor stations and is divided into segments by either receipt or delivery points along the pipeline. The number of segments which require looping is found by adding loop to individual segments until the final pressure (i.e., the pressure at the point of interest downstream on the pipeline) is equal to or greater than the specified design pressure.

  8. Natural Gas Pipeline Leaks Across Washington, DC Robert B. Jackson,,,

    E-Print Network [OSTI]

    Jackson, Robert B.

    Natural Gas Pipeline Leaks Across Washington, DC Robert B. Jackson,,, * Adrian Down, Nathan G increased in recent decades, but incidents involving natural gas pipelines still cause an average of 17 fatalities and $133 M in property damage annually. Natural gas leaks are also the largest anthropogenic

  9. A Pipelined Turbo Decoder with Random Convolutional Interleaver Werner Henkel

    E-Print Network [OSTI]

    Henkel, Werner

    A Pipelined Turbo Decoder with Random Convolutional Interleaver Werner Henkel University of Applied: jusif, sayir¡ @ftw.at Abstract-- This paper describes a pipelined iterative decoder ("Turbo" decoder. INTRODUCTION SINCE the introduction of "Turbo" codes in 1993 [1] the coding community has put much effort

  10. Statistical Methods for Estimating the Minimum Thickness Along a Pipeline

    E-Print Network [OSTI]

    along the pipeline can be used to estimate corrosion levels. The traditional parametric model method for this problem is to estimate parameters of a specified corrosion distribution and then to use these parameters companies use pipelines to transfer oil, gas and other materials from one place to another. Manufactures

  11. MHK Technologies/Deep Water Pipelines | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere I Geothermal Pwer Plant Jump to:LandownersLuther, Oklahoma:Energy

  12. Leak detection on an ethylene pipeline

    SciTech Connect (OSTI)

    Hamande, A.; Condacse, V.; Modisette, J.

    1995-12-31T23:59:59.000Z

    A model-based leak detection system has been in operation on the Solvay et Cie ethylene pipeline from Antwerp to Jemeppe on Sambre since 1989. The leak detection system, which is the commercial product PLDS of Modisette Associations, Inc., was originally installed by the supplier. Since 1991, all system maintenance and configuration changes have been done by Solvay et Cie personnel. Many leak tests have been performed, and adjustments have been made in the configuration and the automatic tuning parameters. The leak detection system is currently able to detect leaks of 2 tonnes/hour in 11 minutes with accurate location. Larger leaks are detected in about 2 minutes. Leaks between 0.5 and 1 tonne per hour are detected after several hours. (The nominal mass flow in the pipeline is 15 tonnes/hour, with large fluctuations.) Leaks smaller than 0.5 tonnes per hour are not detected, with the alarm thresholds set at levels to avoid false alarms. The major inaccuracies of the leak detection system appear to be associated with the ethylene temperatures.

  13. Capsule Pipeline Research Center. 3-year Progress report, September 1, 1993--August 31, 1994

    SciTech Connect (OSTI)

    Not Available

    1994-04-01T23:59:59.000Z

    The Capsule Pipeline Research Center is devoted to performing research in capsule pipelines so that this emerging technology can be developed for early use to transport solids including coal, grain, other agricultural products, solid wastes, etc. Important research findings and accomplishments during the first-three years include: success in making durable binderless coal logs by compaction, success in underwater extrusion of binderless coal logs, success in compacting and extruding coal logs with less than 3% hydrophobic binder at room temperature, improvement in the injection system and the pump-bypass scheme, advancement in the state-of-the-art of predicting the energy loss (pressure drop) along both stationary and moving capsules, demonstrated the effectiveness of using polymer for drag reduction in CLP, demonstrated the influence of zeta potential on coal log fabrication, improved understanding of the water absorption properties of coal logs, better understanding of the mechanism of coal log abrasion (wear), completed a detailed economic evaluation of the CLP technology and compared coal transportation cost by CLP to that by rail, truck and slurry pipelines, and completion of several areas of legal research. The Center also conducted important technology transfer activities including workshops, work sessions, company seminars, involvement of companies in CLP research, issuance of newsletters, completion of a video tape on CLP, and presentation of research findings at numerous national and international meetings.

  14. For Immediate Release --Monday, March 18, 2013 From Glaciers to drinking water: University of Lethbridge

    E-Print Network [OSTI]

    Seldin, Jonathan P.

    change and increasing demands due to human population and industrial activity to drinking water: University of Lethbridge Water Resource Experts Available on World gone? - Pipeline oil spills and river systems ­ how fast do

  15. Demonstration of the Rapid Assessment Tool: Analysis of Water Supply Conditions in the Harlingen Irrigation District 

    E-Print Network [OSTI]

    Leigh, E.; Fipps, G.

    2008-01-01T23:59:59.000Z

    network of irrigation districts. The Water Supply (Head) Conditions component of RAT is designed to determine the extent of the area affected from less than optimal water supply, to identify associated canal and pipeline segments, and to define the major...

  16. Analysis and design of an in-pipe system for water leak detection

    E-Print Network [OSTI]

    Chatzigeorgiou, Dimitris M

    2010-01-01T23:59:59.000Z

    Leaks are a major factor for unaccounted water losses in almost every water distribution network. Pipeline leak may result, for example, from bad workmanship or from any destructive cause, due to sudden changes of pressure, ...

  17. Utility Partnerships Webinar Series: Gas Utility Energy Efficiency...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Utility Partnerships Webinar Series: Gas Utility Energy Efficiency Programs Utility Partnerships Webinar Series: Gas Utility Energy Efficiency Programs gasutilityeewebinarnov2...

  18. Comparing Existing Pipeline Networks with the Potential Scale of Future U.S. CO2 Pipeline Networks

    SciTech Connect (OSTI)

    Dooley, James J.; Dahowski, Robert T.; Davidson, Casie L.

    2009-04-20T23:59:59.000Z

    There is growing interest regarding the potential size of a future U.S. dedicated carbon dioxide (CO2) pipeline infrastructure if carbon dioxide capture and storage (CCS) technologies are commercially deployed on a large scale within the United States. This paper assesses the potential scale of the CO2 pipeline system needed under two hypothetical climate policies (so called WRE450 and WRE550 stabilization scenarios) and compares this to the extant U.S. pipeline infrastructures used to deliver CO2 for enhanced oil recovery (EOR), and to move natural gas and liquid hydrocarbons from areas of production and importation to markets. The analysis reveals that between 11,000 and 23,000 additional miles of dedicated CO2 pipeline might be needed in the U.S. before 2050 across these two cases. While that is a significant increase over the 3,900 miles that comprise the existing national CO2 pipeline infrastructure, it is critically important to realize that the demand for additional CO2 pipeline capacity will unfold relatively slowly and in a geographically dispersed manner as new dedicated CCS-enabled power plants and industrial facilities are brought online. During the period 2010-2030, the growth in the CO2 pipeline system is on the order of a few hundred to less than a thousand miles per year. In comparison during the period 1950-2000, the U.S. natural gas pipeline distribution system grew at rates that far exceed these projections in growth in a future dedicated CO2 pipeline system. This analysis indicates that the need to increase the size of the existing dedicated CO2 pipeline system should not be seen as a major obstacle for the commercial deployment of CCS technologies in the U.S. Nevertheless, there will undoubtedly be some associated regulatory and siting issues to work through but these issues should not be unmanageable based on the size of infrastructure requirements alone.

  19. NET PRED UTILITY

    Energy Science and Technology Software Center (OSTI)

    002602IBMPC00 Normalized Elution Time Prediction Utility  http://omics.pnl.gov/software/NETPredictionUtility.php 

  20. Online Pipeline Transportation of Petroleum Products with no Due Dates 1

    E-Print Network [OSTI]

    Endler, Markus

    On­line Pipeline Transportation of Petroleum Products with no Due Dates 1 Ruy Luiz Milidi'u milidiu; 1 Introduction Petroleum products are typically transported through pipelines. Pipelines, 2001 Abstract: In this paper, we introduce a new model for pipeline transportation of petroleum

  1. Technoeconomic Analysis of Biomethane Production from Biogas and Pipeline Delivery (Presentation)

    SciTech Connect (OSTI)

    Jalalzadeh-Azar, A.

    2010-10-18T23:59:59.000Z

    This presentation summarizes "A Technoeconomic Analysis of Biomethane Production from Biogas and Pipeline Delivery".

  2. A Reconfigurable, On-The-Fly, Resource-Aware, Streaming Pipeline Scheduler

    E-Print Network [OSTI]

    Massachusetts at Amherst, University of

    that create pipelines that are fully aware of the system's resources. In this paper, we present the design not offer enough expressiveness to cover all pipelines that can be constructed. Fully automated efficient pipeline construction presents multiple challenges. Some systems5, 17­19 build the pipeline on

  3. A Reconfigurable, OnTheFly, ResourceAware, Streaming Pipeline Scheduler

    E-Print Network [OSTI]

    Massachusetts at Amherst, University of

    that create pipelines that are fully aware of the system's resources. In this paper, we present the design not offer enough expressiveness to cover all pipelines that can be constructed. Fully automated efficient pipeline construction presents multiple challenges. Some systems 5, 17--19 build the pipeline on

  4. The Pipeline Design Pattern Allan Vermeulen, Gabe BegedDov, Patrick Thompson

    E-Print Network [OSTI]

    Schmidt, Douglas C.

    1 The Pipeline Design Pattern Allan Vermeulen, Gabe Beged­Dov, Patrick Thompson ã Copyright Rogue in the processing pipeline. For example, the Web browser pipeline can be constructed in various ways depending Wave Software, Inc., 1995 Intent Build data pipelines in a configurable and typesafe manner. Motivation

  5. Effect of Title V air permitting on pipeline operations

    SciTech Connect (OSTI)

    Bost, R.C.; Donnan, G.T. [ERM-Southwest, Inc., Houston, TX (United States)

    1995-12-31T23:59:59.000Z

    Pursuant to the passage of the Clean Air Act Amendments of 1990, the US Environmental Protection Agency has promulgated what are known as Title V permitting requirements for major sources of air pollutants, including pipeline operations. In contrast to most existing air permitting programs, the new Title V regulations will require periodic certification of compliance with applicable air regulations. In the same way that water dischargers report their own discharge violations to regulatory agencies pursuant to the NPDES permitting system, Title V permittees must implement an acceptable monitoring program and similarly report violations of permit conditions or applicable air regulations. Only those facilities whose potential emissions are less than or can be controlled to be less than certain regulatory limits will be exempt from standard Title V permitting. If a facility`s throughput or the concentration levels of certain volatile toxic levels in a particular crude or natural gas were to exceed corresponding regulatory limits, then the facility could be in violation. If an operator were to expand a field, then the changes in the gathering system and emission levels could constitute a violation. Constraints on operations can be avoided by careful strategizing of an operator`s Title V permit application.

  6. Consortium for coal log pipeline research and development. Final technical progress report, August 10, 1993--August 9, 1996

    SciTech Connect (OSTI)

    Marrero, T.R.

    1996-10-01T23:59:59.000Z

    The main objective of this project was to conduct intensive research and development of the Coal Log Pipeline (CLP). Specifically, the R & D was to concentrate on previously neglected and insufficiently studied aspects of CLP which were deemed significant. With improvements in these areas, CLP could be implemented for commercial use within five years. CLP technology is capable of transporting coal logs for long distances. The many potential advantages of CLP over truck and railroad transportation include: lower freight costs, less energy consumption, less air pollution, decreased environmental problems, increased safety, and improved reliability. Previous studies have shown that CLP is advantageous over slurry pipeline technology. First, CLP uses one-third the water required by a coal slurry pipeline. Second, CLP provides easier coal dewatering. Third, the CLP conveying capacity of coal is twice as much as a slurry transport line of equal diameter. In many situations, the cost for transporting each ton of coal is expected to be less expensive by CLP as compared to other competing modes of transportation such as: truck, unit train and slurry pipeline.

  7. America's "Circulatory System" The 2.3 million miles of pipelines in the United States carry materials and data vital to our

    E-Print Network [OSTI]

    Neimark, Alexander V.

    be able to meet ever-increasing demands for the volumes of natural gas, oil, water, chemicals, electricity and Natural Gas Engineering West Virginia University (WVU) Colleen Richwall, P.E., Chair New Jersey Common CAIT's Pipeline Safety and Security Program (PSSP) aims to play a major role in developing technologies

  8. Water Quality and Quantity Concerns Population growth, increasing water demands,

    E-Print Network [OSTI]

    systems, private water well screening, and soil nutrient management. Water conservation programs of Agri, efficient use, sustainable practices, watershed management and environmental stewardship. Through 660 and utilizing water-conservation practices will be essential to sustain the state's water supply

  9. Santa Clara Water and Sewer- Solar Water Heating Program

    Broader source: Energy.gov [DOE]

    In 1975, the City of Santa Clara established the nation's first municipal solar utility. Under the Solar Water Heating Program, the Santa Clara Water and Sewer Utilities Department supplies,...

  10. The Role of Peer Support for Girls and Women in the STEM Pipeline: Promoting Identification with STEM and Mitigating the Negative Effects of Sexism

    E-Print Network [OSTI]

    Robnett, Rachael

    2013-01-01T23:59:59.000Z

    AND WOMEN IN THE STEM PIPELINE: PROMOTING IDENTIFICATIONand Women in the STEM Pipeline: Promoting Identificationand Women in the STEM Pipeline: Promoting Identification

  11. The development of a chemical biology pipeline for the identification of small molecules that induce cardiopoiesis in murine embryonic stem cells

    E-Print Network [OSTI]

    Bushway, Paul Jay

    2012-01-01T23:59:59.000Z

    of a Chemical Biology Pipeline for the Identification ofof a Chemical Biology Pipeline for the Identification ofhinge on the drug development pipeline and the importance of

  12. Response of continuous pipelines to tunnel induced ground deformations

    E-Print Network [OSTI]

    Ieronymaki, Evangelia S

    2011-01-01T23:59:59.000Z

    This thesis develops analytical solutions for estimating the bending moments and axial loads in a buried pipeline due to ground movements caused by tunnel construction in soft ground. The solutions combine closed-form, ...

  13. Ductile fracture and structural integrity of pipelines & risers

    E-Print Network [OSTI]

    Kofiani, Kirki N. (Kirki Nikolaos)

    2013-01-01T23:59:59.000Z

    The Oil and Gas (O&G) industry has recently turned its interest towards deep and ultra-deep offshore installations in order to address the global increase of energy demand. Pipelines and risers are key components for the ...

  14. Simulation effectively sites surge-relief facilities on Saudi pipeline

    SciTech Connect (OSTI)

    Dempsey, J.J.; Al-Gouhi, A.H. (Saudi Arabian Oil Co., Dhahrain (Saudi Arabia))

    1993-09-20T23:59:59.000Z

    Pipeline hydraulic and surge analysis studies of the Saudi Aramco East-West crude-oil pipeline assisted in expanding the system's capacity by 50%. Surge studies predicted that operational upsets, such as the trip of a pump station, cause excessive surge pressures in the pipeline system at new flow rates. Additional surge studies showed that surge-relief stations must be located downstream from each of six pump stations. The new surge-relief stations and an increase in capacity of existing surge-relief stations protect the pipelines at the higher flow rates. The paper describes modeling the system, the analysis of the hydraulics, surge analysis, acoustic transit times, relief valve simulation, surge-relief protection, surge-relief stations, station locations, simulation results, tank sizing, and valve testing.

  15. Structural Genomics of Minimal Organisms: Pipeline and Results

    E-Print Network [OSTI]

    Kim, Sung-Hou

    2008-01-01T23:59:59.000Z

    of recombinant proteins. J. Struct. Funct. Genomics 5:69-74.proteins. J. Struct. Funct. Genomics 5:69-74. Oganesyan,Structural Genomics of Minimal Organisms: Pipeline and

  16. Calculating Horsepower Requirements and Sizing Supply Pipelines for Irrigation 

    E-Print Network [OSTI]

    Fipps, Guy

    1995-09-05T23:59:59.000Z

    Pumping costs are often one of the largest single expenses in irrigated agriculture. This publication explains how to lower pumping costs by calculating horsepower requirements and sizing supply pipelines correctly. Examples take the reader through...

  17. Analysis of Subsea Buried Pipelines and Partially Buried Cables 

    E-Print Network [OSTI]

    Bai, Yanbin

    2014-08-26T23:59:59.000Z

    This research investigation addresses the analysis and numerical simulation of two very important offshore engineering problems. The first deals with the modeling of the steady state thermal field around buried pipelines conveying high temperature...

  18. Extensible microprocessor without interlocked pipeline stages (emips), the reconfigurable microprocessor

    E-Print Network [OSTI]

    Pittman, Richard Neil

    2007-09-17T23:59:59.000Z

    have called our dynamically extensible microprocessor design the Extensible Microprocessor without Interlocked Pipeline Stages, or eMIPS. The eMIPS architecture uses the interaction of fixed and configurable logic available in modern...

  19. "Assessment of the Adequacy of Natural Gas Pipeline Capacity...

    Broader source: Energy.gov (indexed) [DOE]

    its "Assessment of the Adequacy of Natural Gas Pipeline Capacity in the Northeast United States" report. The report is now available for downloading. In 2005-06, the Office of...

  20. EIA - Natural Gas Pipeline Network - Natural Gas Supply Basins...

    U.S. Energy Information Administration (EIA) Indexed Site

    Corridors About U.S. Natural Gas Pipelines - Transporting Natural Gas based on data through 20072008 with selected updates U.S. Natural Gas Supply Basins Relative to Major Natural...

  1. Hydrogen Embrittlement of Pipeline Steels: Causes and Remediation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Presentation by 09-Sofronis to DOE Hydrogen Pipeline R&D Project Review Meeting held January 5-6, 2005 at Oak Ridge National Laboratory in Oak Ridge, Tennessee....

  2. EIS-0152: Iroquois, Tenn. Phase I, Pipeline Line Project

    Broader source: Energy.gov [DOE]

    The Federal Energy Regulatory Commission prepared this statement to asses the environmental impacts of constructing and operating an interstate natural gas pipeline and associated infrastructure to transport gas from Canada and domestic sources to the New England Market, as proposed by the Iroquois Gas Transmission System and the Tennessee Gas Pipeline Company. The U.S. Department of Energy Office of Fossil Energy was a cooperating agency during statement development and adopted the statement on 9/1/1990.

  3. Report of the Committee on oil pipeline regulation

    SciTech Connect (OSTI)

    Not Available

    1994-01-01T23:59:59.000Z

    This report of the Committee on Oil Pipeline Regulations is divided into five sections. Section I addresses Order 561, a final rule entitled [open quotes]Revisions to Oil Pipeline Regulations Pursuant to the Energy Policy Act of 1992,[close quotes] which was released by the Federal Energy Regulatory Commission (FERC) on October 23, 1993. Section II discusses the question of FERC jurisdiction over partial abandments of service, focusing on the ARCO Pipe Line Co. case which centered on whether a pipeline may discontinue shipping in one direction even though the pipeline will continue to ship in another direction, and the Chevron Pipe Line Co. case in which the Commission ruled that it does not have the authority to prevent a pipeline from temporarily suspending service. Section II addresses the Lakehead Pipe Line Co., Ltd. Partnership case, in which the Administrative Law Judge issued an Initial Decision resolving Phase I issues. Section IV of the article discusses whether or not a pipeline may base its rates on the cost of leasing capacity from an other pipeline. Five cases are examined in which pipelines that proposed initial rates allegedly based on the cost of a lease found their tariffs protested. Section V reviews the matter of the Williams Pipe Line Co. rate case in which the Commission issued an order on complaint in which it granted in part and denied in part several shippers' request for an order directing Williams Pipe Line Co. to (1) cease levying unauthorized charges, (2) pay reparations to shippers, and (3) be subjected to sanction for violations of the Interstate Commerce Act.

  4. The quality assurance of heat fused thermoplastic pipeline joints 

    E-Print Network [OSTI]

    Earles, Larry Lee

    1982-01-01T23:59:59.000Z

    THE QUALITY ASSURANCE OF HEAT FUSED THERMOPLASTIC PIPELINE JOINTS A Thesis by LARRY LEE EARLES Submitted to the Graduate College of Texas A&M University in partial fulfillment for the requirements for the degree of MASTER OF SCIENCE... December 1982 Major Subject: Mechanical Engineering THE QUALITY ASSURANCE OF HEAT FUSED THERMOPLASTIC PIPELINE JOINTS A Thesis LARRY LEE EARLES Approved as to style and content by: Mario A. Colaluca (Chairman of Committee) Carl Gerhold (Member...

  5. EIS-0152: Iroquois/Tennessee Phase I Pipeline Project

    Broader source: Energy.gov [DOE]

    The Federal Energy Regulatory Commission prepared this statement to asses the environmental impacts of constructing and operating an interstate natural gas pipeline and associated infrastructure to transport gas from Canada and domestic sources to the New England Market, as proposed by the Iroquois Gas Transmission System and the Tennessee Gas Pipeline Company. The U.S. Department of Energy Office of Fossil Energy was a cooperating agency during statement development and adopted the statement on 9/1/1990.

  6. The liquefied natural gas pipeline: a system study 

    E-Print Network [OSTI]

    Hazel, Thomas Ray

    1972-01-01T23:59:59.000Z

    THE LIQUEFIED NATURAL GAS PIPELINE: A SYSTEM STUDY A Thesis by THOMAS RAY HAZEL Submitted to the Graduate College of Texas A&M University in partial fulfillment of the requirement for the degree of MASTER OF SCIENCE May 1972 Major Subject...: Mechanical Engineering THE LIQUEFIED NATURAL GAS PIPELINE: A SYSTEM STUDY A Thesis by THOMAS RAY HAZEL Approved as to style and content by: Chairman o 'Committee) (Head of Department) (Member) (Member) (Member) (Member) (Member) May 1972 ABSTRACT...

  7. Modeling fatique behavior of dents in petroleum pipelines

    E-Print Network [OSTI]

    Hoffmann, Roger Lynn

    1997-01-01T23:59:59.000Z

    MODELING FATIGUE BEHAVIOR OF DENTS IN PETROLEUM PIPELINES A Thesis by ROGER LYNN HOFFMANN Submitted to the Office of Graduate Studies of Texas A&M University in partial fulfillment of the requirements for the degree of MASTER OF SCIENCE... August 1997 Major Subject: Civil Engineering MODELING FATIGUE BEHAVIOR OF DENTS IN PETROLEUM PIPELINES A Thesis by ROGER LYNN HOFFMANN Submitted to Texas A&M University in partial fulfillment of the requirements for the degree of MASTER...

  8. The liquefied natural gas pipeline: a system study

    E-Print Network [OSTI]

    Hazel, Thomas Ray

    1972-01-01T23:59:59.000Z

    THE LIQUEFIED NATURAL GAS PIPELINE: A SYSTEM STUDY A Thesis by THOMAS RAY HAZEL Submitted to the Graduate College of Texas A&M University in partial fulfillment of the requirement for the degree of MASTER OF SCIENCE May 1972 Major Subject...: Mechanical Engineering THE LIQUEFIED NATURAL GAS PIPELINE: A SYSTEM STUDY A Thesis by THOMAS RAY HAZEL Approved as to style and content by: Chairman o 'Committee) (Head of Department) (Member) (Member) (Member) (Member) (Member) May 1972 ABSTRACT...

  9. The Economics of the Nord Stream Pipeline System

    E-Print Network [OSTI]

    Chyong, Chi Kong; Noël, Pierre; Reiner, David M.

      to  those  set  by  the  Polish  energy regulator  for  the Yamal?Europe pipeline  in Poland (€1.108/tcm/100km  in 2009) (A'LEMAR, 2009... The Economics of the Nord Stream Pipeline System Chi Kong Chyong, Pierre Noël and David M. Reiner September 2010 CWPE 1051 & EPRG 1026 www.eprg.group.cam.ac.uk E P R G W O R K IN G P A P E R Abstract...

  10. Colorado Springs Utilities- Renewable Energy Rebate Program

    Broader source: Energy.gov [DOE]

    Through its Renewable Energy Rebate Program, Colorado Springs Utilities (CSU) offers a rebate to customers who install grid-connected solar-electric (PV) systems, wind systems, and solar water...

  11. Hot Water Draw Patterns in Single-Family Houses: Findings from Field Studies

    E-Print Network [OSTI]

    Lutz, Jim

    2012-01-01T23:59:59.000Z

    Two Demand Electric Water Heaters for Northeast Utilities.Two Demand Electric Water Heaters for Northeast Utilities.Johnson. Heat Pump Water Heater Field Test: 30 Crispaire

  12. AWWA, WEF Utility Management Conference | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AWWA, WEF Utility Management Conference AWWA, WEF Utility Management Conference February 17, 2015 1:00PM CST to February 20, 2015 10:00PM CST Austin, TX The American Water Works...

  13. Nondestructive inspection of the condition of oil pipeline cleaning units

    SciTech Connect (OSTI)

    Berdonosov, V.A.; Boiko, D.A.; Lapshin, B.M.; Chakhlov, V.L.

    1989-02-01T23:59:59.000Z

    One of the reasons for shutdowns of main oil pipelines is stoppage of the cleaning unit in cleaning of the inner surface of paraffin deposits caused by damage to the cleaning unit. The authors propose a method of searching for and determining the condition of the cleaning unit not requiring dismantling of the pipeline according to which the initial search for the cleaning unit is done with acoustic instruments (the increased acoustic noise at the point of stoppage of its is recorded) and subsequent inspection by a radiographic method. An experimental model of an instrument was developed making it possible to determine the location of a cleaning unit in an oil pipeline in stoppage of it from the acoustic noise. The instrument consists of two blocks, the remote sensor and the indicator block, which are connected to each other with a cable up to 10 m long. The design makes it possible to place the sensor at any accessible point of a linear part of the pipeline (in a pit, on a valve, etc.) while the indicator block may remain on the surface of the ground. The results obtained make it possible to adopt the optimum solutions on elimination of their malfunctioning and to prevent emergency situations without dismantling of the pipeline. With the equipment developed it is possible to inspect oil and gas pipelines with different reasons for a reduction in their throughput.

  14. New developments in pipeline charging preheated coal at Inland Steel

    SciTech Connect (OSTI)

    Sorensen, S.M. Jr.; Arsenault, A.A.; Rupp, P.A.

    1982-01-01T23:59:59.000Z

    The first commercial installation of a new pipeline oven charging system for preheated coal, designed by Dynamic Air, Inc., was made at Inland Steel's C Battery in October 1979. With the Dynamic Air charging sytem, production losses due to pipeline delays have been virtually eliminated, pipeline maintenance requirements have been reduced by 90%, conveying steam requirements have been significantly reduced, and oven charge weights have been increased by 500 kg (1000 lb). A test program was subsequently conducted during November and December 1980, to evaluate the use of nitrogen as a conveying medium for pipeline oven charging with the Dynamic Air system. The test results clearly demonstrated that the same weight of preheated coal could be charged into an oven by using either steam or nitrogen as the conveying medium. Moreover, it was found that pipeline oven charging with the Dynamic Air system is a function of the mass flow rate of the conveying medium. With nitrogen charging, an average 9% increase in oven charge rates was obtained at comparable conveying gas mass flow rates and charging bin pressures. In addition, average oven pressure during charging was reduced by approximately 40% and solids carryover was reduced by 100 kg (220 lb) per oven charge with nitrogen charging. It was found that solids carryover during pipeline oven charging is a function of the average pressure generated in the oven during charging, but it was also found that a large oven pressure surge at the end of the charge can produce excessive carryover to completely mask the effect.

  15. TASSEL 3.0 / 4.0 Pipeline Command Line Interface: Guide to using Tassel Pipeline Terry Casstevens (tmc46@cornell.edu)

    E-Print Network [OSTI]

    Buckler, Edward S.

    1 TASSEL 3.0 / 4.0 Pipeline Command Line Interface: Guide to using Tassel Pipeline Terry Casstevens values via the command line. ./run_pipeline.pl -Xms512m -Xmx10g -fork1... Examples ./run to change the following line to use a ; instead of a :. my $CP = join(":", @fl); #12;2 To launch the Tassel

  16. Water Resources Research Center Annual Technical Report

    E-Print Network [OSTI]

    and quantity Water quality standards and regulation for Hawaii Pipeline forensics and asset replacement of Hawaii Water Resources Research Center, in the FY2006 reporting period, initiated three new projects under the 104(b) program and renewed funding for a fourth project. Work continued on a 104(g) award

  17. Remaining Sites Verification Package for the 100-F-26:12, 1.8-m (72-in.) Main Process Sewer Pipeline, Waste Site Reclassification Form 2007-034

    SciTech Connect (OSTI)

    J. M. Capron

    2008-04-29T23:59:59.000Z

    The 100-F-26:12 waste site was an approximately 308-m-long, 1.8-m-diameter east-west-trending reinforced concrete pipe that joined the North Process Sewer Pipelines (100-F-26:1) and the South Process Pipelines (100-F-26:4) with the 1.8-m reactor cooling water effluent pipeline (100-F-19). In accordance with this evaluation, the verification sampling results support a reclassification of this site to Interim Closed Out. The results of verification sampling show that residual contaminant concentrations do not preclude any future uses and allow for unrestricted use of shallow zone soils. The results also demonstrate that residual contaminant concentrations are protective of groundwater and the Columbia River.

  18. Method and apparatus utilizing ionizing and microwave radiation for saturation determination of water, oil and a gas in a core sample

    DOE Patents [OSTI]

    Maerefat, Nicida L. (Sugar Land, TX); Parmeswar, Ravi (Marlton, NJ); Brinkmeyer, Alan D. (Tulsa, OK); Honarpour, Mehdi (Bartlesville, OK)

    1994-01-01T23:59:59.000Z

    A system for determining the relative permeabilities of gas, water and oil in a core sample has a microwave emitter/detector subsystem and an X-ray emitter/detector subsystem. A core holder positions the core sample between microwave absorbers which prevent diffracted microwaves from reaching a microwave detector where they would reduce the signal-to-noise ratio of the microwave measurements. The microwave emitter/detector subsystem and the X-ray emitter/detector subsystem each have linear calibration characteristics, allowing one subsystem to be calibrated with respect to the other subsystem. The dynamic range of microwave measurements is extended through the use of adjustable attenuators. This also facilitates the use of core samples with wide diameters. The stratification characteristics of the fluids may be observed with a windowed cell separator at the outlet of the core sample. The condensation of heavy hydrocarbon gas and the dynamic characteristics of the fluids are observed with a sight glass at the outlet of the core sample.

  19. Method and apparatus utilizing ionizing and microwave radiation for saturation determination of water, oil and a gas in a core sample

    DOE Patents [OSTI]

    Maerefat, N.L.; Parmeswar, R.; Brinkmeyer, A.D.; Honarpour, M.

    1994-08-23T23:59:59.000Z

    A system is described for determining the relative permeabilities of gas, water and oil in a core sample has a microwave emitter/detector subsystem and an X-ray emitter/detector subsystem. A core holder positions the core sample between microwave absorbers which prevent diffracted microwaves from reaching a microwave detector where they would reduce the signal-to-noise ratio of the microwave measurements. The microwave emitter/detector subsystem and the X-ray emitter/detector subsystem each have linear calibration characteristics, allowing one subsystem to be calibrated with respect to the other subsystem. The dynamic range of microwave measurements is extended through the use of adjustable attenuators. This also facilitates the use of core samples with wide diameters. The stratification characteristics of the fluids may be observed with a windowed cell separator at the outlet of the core sample. The condensation of heavy hydrocarbon gas and the dynamic characteristics of the fluids are observed with a sight glass at the outlet of the core sample. 11 figs.

  20. INTERNAL REPAIR OF PIPELINES REVIEW & EVALUATION OF INTERNAL PIPELINE REPAIR TRIALS REPORT

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Ian Harris; Dennis Harwig; George Ritter; Bill Mohr; Matt Boring; Nancy Porter; Mike Sullivan; Chris Neary

    2004-09-01T23:59:59.000Z

    The two broad categories of fiber-reinforced composite liner repair and deposited weld metal repair technologies were reviewed and evaluated for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Evaluation trials were conducted on pipe sections with simulated corrosion damage repaired with glass fiber-reinforced composite liners, carbon fiber-reinforced composite liners, and weld deposition. Additional un-repaired pipe sections were evaluated in the virgin condition and with simulated damage. Hydrostatic failure pressures for pipe sections repaired with glass fiber-reinforced composite liner were only marginally greater than that of pipe sections without liners, indicating that this type of liner is generally ineffective at restoring the pressure containing capabilities of pipelines. Failure pressure for pipe repaired with carbon fiber-reinforced composite liner was greater than that of the un-repaired pipe section with damage, indicating that this type of liner is effective at restoring the pressure containing capability of pipe. Pipe repaired with weld deposition failed at pressures lower than that of un-repaired pipe in both the virgin and damaged conditions, indicating that this repair technology is less effective at restoring the pressure containing capability of pipe than a carbon fiber-reinforced liner repair. Physical testing indicates that carbon fiber-reinforced liner repair is the most promising technology evaluated to-date. Development of a comprehensive test plan for this process is recommended for use in the next phase of this project.

  1. Ninja data analysis with a detection pipeline based on the Hilbert-Huang Transform

    E-Print Network [OSTI]

    Alexander Stroeer; Jordan Camp

    2009-03-11T23:59:59.000Z

    The Ninja data analysis challenge allowed the study of the sensitivity of data analysis pipelines to binary black hole numerical relativity waveforms in simulated Gaussian noise at the design level of the LIGO observatory and the VIRGO observatory. We analyzed NINJA data with a pipeline based on the Hilbert Huang Transform, utilizing a detection stage and a characterization stage: detection is performed by triggering on excess instantaneous power, characterization is performed by displaying the kernel density enhanced (KD) time-frequency trace of the signal. Using the simulated data based on the two LIGO detectors, we were able to detect 77 signals out of 126 above SNR 5 in coincidence, with 43 missed events characterized by signal to noise ratio SNR less than 10. Characterization of the detected signals revealed the merger part of the waveform in high time and frequency resolution, free from time-frequency uncertainty. We estimated the timelag of the signals between the detectors based on the optimal overlap of the individual KD time-frequency maps, yielding estimates accurate within a fraction of a millisecond for half of the events. A coherent addition of the data sets according to the estimated timelag eventually was used in a characterization of the event.

  2. Urethane coatings rehabilitate large crude oil pipeline

    SciTech Connect (OSTI)

    Kresic, W. [Interprovincial Pipe Line Inc., Edmonton, Alberta (Canada)

    1995-10-01T23:59:59.000Z

    Interprovincial Pipe Line Inc. (IPL) provides a vital transportation link for moving liquid petroleum resources from oil-producing areas of western Canada to refining centers and markets in eastern canada and the midwestern US. Together with Lakehead Pipe Line Co., Inc., the pipeline system consists of about 7,600 miles of pipe. Approximately 1.6 million bpd of crude oil and liquid hydrocarbons are transported by the system. Along with high-resolution inspection data, an in-house engineering critical assessment process based on Battelle`s NG-18 surface flaw equation was developed to identify corrosion anomalies needing structural reinforcement sleeve repairs. A majority of ht non-critical anomalies remained unearthed and were exposed to possible future growth which could become critical. Several rehabilitation methods were considered including on-going sleeve repair, selective pipe replacement, and coating reconditioning. Economics and logistics of sleeving programs and selective pipe replacement were well known at IPL. However, aspects of replacing a coating system over a relatively long length of pipe were not completely known. Preliminary cost estimates favored replacement of the coating over a massive sleeving program or pipe replacement. To gain further insight, IPL began a two-year pilot program to research long length coating replacement feasibility. Two sections of Line 3 ultimately were rehabilitated in this manner. This paper reviews the project.

  3. Compression station key to Texas pipeline project

    SciTech Connect (OSTI)

    NONE

    1996-10-01T23:59:59.000Z

    This was probably the largest pipeline project in the US last year, and the largest in Texas in the last decade. The new compressor station is a key element in this project. TECO, its servicing dealer, and compression packager worked closely throughout the planning and installation stages of the project. To handle the amount of gas required, TECO selected the GEMINI F604-1 compressor, a four-throw, single-stage unit with a six-inch stroke manufactured by Weatherford Enterra Compression Co. (WECC) in Corpus Christi, TX. TECO also chose WECC to package the compressors. Responsibility for ongoing support of the units will be shared among TECO, the service dealer and the packager. TECO is sending people to be trained by WECC, and because the G3600 family of engines is still relatively new, both the Caterpillar dealer and WECC sent people for advanced training at Caterpillar facilities in Peoria, IL. As part of its service commitment to TECO, the servicing dealer drew up a detailed product support plan, encompassing these five concerns: Training, tooling; parts support; service support; and commissioning.

  4. Disproportionality fills in the gaps: Connections between achievement, discipline and special education in the School-to-Prison Pipeline

    E-Print Network [OSTI]

    Annamma, Subini; Morrison, Deb; Jackson, Darrell

    2014-01-01T23:59:59.000Z

    the school to prison pipeline. Journal of Law and EducationThe school-to-prison-pipeline: Structuring legal reform. New2005). School to prison pipeline. Retrieved from http://

  5. Leakage Risk Assessment of CO2 Transportation by Pipeline at the Illinois Basin Decatur Project, Decatur, Illinois

    E-Print Network [OSTI]

    Mazzoldi, A.

    2014-01-01T23:59:59.000Z

    S.M. , 2007, Natural Gas Pipeline Technology Overview.high-pressure natural- gas pipelines: J. Loss Prevention inrisk assessments of CO 2 pipelines, in Elsevier, ed. , 9th

  6. Three-dimensional morphology and gene expression in the Drosophila blastoderm at cellular resolution I: data acquisition pipeline

    E-Print Network [OSTI]

    2006-01-01T23:59:59.000Z

    I: data acquisition pipeline The electronic version of thiswe describe an integrated pipeline of methods for studyingA three-dimensional analysis pipeline To be able to analyze

  7. Genome-wide SNP discovery in walnut with an AGSNP pipeline updated for SNP discovery in allogamous organisms

    E-Print Network [OSTI]

    2012-01-01T23:59:59.000Z

    in walnut with an AGSNP pipeline updated for SNP discoveryin walnut with an AGSNP pipeline updated for SNP discoverythe development of a pipeline (AGSNP) for genome-wide SNP

  8. Water and Waste Water Tariffs for New Residential Construction in California

    E-Print Network [OSTI]

    Fisher, Diane; Lutz, James

    2006-01-01T23:59:59.000Z

    Utility_Cities Table of the Water TAP Database Field NameWater andWaste Water Tariffs for New Residential Construction in

  9. Central Lincoln People's Utility District- Renewable Energy Incentive Program

    Broader source: Energy.gov [DOE]

    Central Lincoln People's Utility District provides financial incentives for its commercial and residential customers to install photovoltaic (PV), solar water heating, wind, and hydro electric...

  10. Orange and Rockland Utilities (Gas)- Residential Efficiency Program

    Broader source: Energy.gov [DOE]

    Orange and Rockland Utilities provides rebates for residential customers purchasing energy efficient natural gas equipment. Rebates exist for furnaces, water boilers and controls, steam boilers,...

  11. Colorado Springs Utilities- Commercial Energy Efficiency Rebate Program

    Broader source: Energy.gov [DOE]

    The Colorado Springs Utilities (CSU) Business Energy and Water Efficiency Rebate Program offers a variety of incentives to business customers who upgrade evaporative cooling, HVAC, irrigation,...

  12. Central Lincoln People's Utility District- Renewable Energy Incentive Program (Oregon)

    Broader source: Energy.gov [DOE]

    Central Lincoln People's Utility District provides financial incentives for its commercial and residential customers to install photovoltaic (PV), solar water heating, wind, and hydro electric...

  13. Montana-Dakota Utilities (Gas)- Residential Energy Efficiency Rebate Program

    Broader source: Energy.gov [DOE]

    Montana-Dakota Utilities (MDU) offers several residential rebates on energy efficient measures and natural gas equipment. New furnaces, water heaters and programmable thermostats are eligible for a...

  14. Performance Assurance for Multi-Year Contracts Under the Utility...

    Broader source: Energy.gov (indexed) [DOE]

    describes guidance for Federal energy and facility managers about participating in utility programs for the management of electricity demand and energy and water conservation....

  15. Truckee Donner Public Utility District- Energy Conservation Rebate Program

    Broader source: Energy.gov [DOE]

    Truckee Donner Public Utility District (TDPUD) offers incentives for customers to improve the energy efficiency of homes and businesses. Participants must be a TDPUD electric customer (and water...

  16. Colorado Springs Utilities- Residential Energy Efficiency Rebate Program

    Broader source: Energy.gov [DOE]

    Colorado Springs Utilities offers a variety of energy and water efficiency incentives to its residential customers through the Residential Rebate Program. Rebates are offered for single and multi...

  17. Qualification of Innovative High Level Waste Pipeline Unplugging Technologies

    SciTech Connect (OSTI)

    McDaniel, D.; Gokaltun, S.; Varona, J.; Awwad, A.; Roelant, D.; Srivastava, R. [Applied Research Center, Florida International University, Miami, FL (United States)

    2008-07-01T23:59:59.000Z

    In the past, some of the pipelines have plugged during high level waste (HLW) transfers resulting in schedule delays and increased costs. Furthermore, pipeline plugging has been cited by the 'best and brightest' technical review as one of the major issues that can result in unplanned outages at the Waste Treatment Plant causing inconsistent operation. As the DOE moves toward a more active high level waste retrieval, the site engineers will be faced with increasing cross-site pipeline waste slurry transfers that will result in increased probability of a pipeline getting plugged. Hence, availability of a pipeline unplugging tool/technology is crucial to ensure smooth operation of the waste transfers and in ensuring tank farm cleanup milestones are met. FIU had earlier tested and evaluated various unplugging technologies through an industry call. Based on mockup testing, two technologies were identified that could withstand the rigors of operation in a radioactive environment and with the ability to handle sharp 90 elbows. We present results of the second phase of detailed testing and evaluation of pipeline unplugging technologies and the objective is to qualify these pipeline unplugging technologies for subsequent deployment at a DOE facility. The current phase of testing and qualification comprises of a heavily instrumented 3-inch diameter (full-scale) pipeline facilitating extensive data acquisition for design optimization and performance evaluation, as it applies to three types of plugs atypical of the DOE HLW waste. Furthermore, the data from testing at three different lengths of pipe in conjunction with the physics of the process will assist in modeling the unplugging phenomenon that will then be used to scale-up process parameters and system variables for longer and site typical pipe lengths, which can extend as much as up to 19,000 ft. Detailed information resulting from the testing will provide the DOE end-user with sufficient data and understanding of the technology, and its limitations to aid in the benefit-cost analysis for management decision whether to deploy the technology or to abandon the pipeline as has been done in the past. In conclusion: The ultimate objective of this study is to qualify NuVision's unplugging technology for use at Hanford. Experimental testing has been conducted using three pipeline lengths and three types of blockages. Erosion rates have been obtained and pressure data is being analyzed. An amplification of the inlet pressure has been observed along the pipeline and is the key to determining up to what pipe lengths the technology can be used without surpassing the site pressure limit. In addition, we will attempt to establish what the expected unplugging rates will be at the longer pipe lengths for each of the three blockages tested. Detailed information resulting from the testing will provide the DOE end-user with sufficient data and understanding of the technology, and its limitations so that management decisions can be made whether the technology has a reasonable chance to successfully unplug a pipeline, such as a cross site transfer line or process transfer pipeline at the Waste Treatment Plant. (authors)

  18. Complexity analysis of pipeline mapping problems in distributed heterogeneous networks

    SciTech Connect (OSTI)

    Lin, Ying [University of Tennessee, Knoxville (UTK); Wu, Qishi [ORNL; Zhu, Mengxia [ORNL; Rao, Nageswara S [ORNL

    2009-04-01T23:59:59.000Z

    Largescale scientific applications require using various system resources to execute complex computing pipelines in distributed networks to support collaborative research. System resources are typically shared in the Internet or over dedicated connections based on their location, availability, capability, and capacity. Optimizing the network performance of computing pipelines in such distributed environments is critical to the success of these applications. We consider two types of largescale distributed applications: (1) interactive applications where a single dataset is sequentially processed along a pipeline; and (2) streaming applications where a series of datasets continuously flow through a pipeline. The computing pipelines of these applications consist of a number of modules executed in a linear order in network environments with heterogeneous resources under different constraints. Our goal is to find an efficient mapping scheme that allocates the modules of a pipeline to network nodes for minimum endtoend delay or maximum frame rate. We formulate the pipeline mappings in distributed environments as optimization problems and categorize them into six classes with different optimization goals and mapping constraints: (1) Minimum Endtoend Delay with No Node Reuse (MEDNNR), (2) Minimum Endtoend Delay with Contiguous Node Reuse (MEDCNR), (3) Minimum Endtoend Delay with Arbitrary Node Reuse (MEDANR), (4) Maximum Frame Rate with No Node Reuse or Share (MFRNNRS), (5) Maximum Frame Rate with Contiguous Node Reuse and Share (MFRCNRS), and (6) Maximum Frame Rate with Arbitrary Node Reuse and Share (MFRANRS). Here, 'contiguous node reuse' means that multiple contiguous modules along the pipeline may run on the same node and 'arbitrary node reuse' imposes no restriction on node reuse. Note that in interactive applications, a node can be reused but its resource is not shared. We prove that MEDANR is polynomially solvable and the rest are NP-complete. MEDANR, where either contiguous or noncontiguous modules in the pipeline can be mapped onto the same node, is essentially the Maximum n-hop Shortest Path problem, and can be solved using a dynamic programming method. In MEDNNR and MFRNNRS, any network node can be used only once, which requires selecting the same number of nodes for onetoone onto mapping. We show its NP-completeness by reducing from the Hamiltonian Path problem. Node reuse is allowed in MEDCNR, MFRCNRS and MFRANRS, which are similar to the Maximum n-hop Shortest Path problem that considers resource sharing. We prove their NP-completeness by reducing from the Disjoint-Connecting-Path Problem and Widest path with the Linear Capacity Constraints problem, respectively.

  19. REALTIME MONITORING OF PIPELINES FOR THIRD-PARTY CONTACT

    SciTech Connect (OSTI)

    Gary L. Burkhardt

    2005-12-31T23:59:59.000Z

    Third-party contact with pipelines (typically caused by contact with a digging or drilling device) can result in mechanical damage to the pipe, in addition to coating damage that can initiate corrosion. Because this type of damage often goes unreported and can lead to eventual catastrophic failure of the pipe, a reliable, cost-effective method is needed for monitoring the pipeline and reporting third-party contact events. The impressed alternating cycle current (IACC) pipeline monitoring method developed by Southwest Research Institute (SwRI) consists of impressing electrical signals on the pipe by generating a time-varying voltage between the pipe and the soil. The signal voltage between the pipe and ground is monitored continuously at receiving stations located some distance away. Third-party contact to the pipe that breaks through the coating (thus resulting in a signal path to ground) changes the signal received at the receiving stations. The IACC method was shown to be a viable method that can be used to continuously monitor pipelines for third-party contact. Electrical connections to the pipeline can be made through existing cathodic protection (CP) test points without the need to dig up the pipe. The instrumentation is relatively simple, consisting of (1) a transmitting station with a frequency-stable oscillator and amplifier and (2) a receiving station with a filter, lock-in amplifier, frequency-stable oscillator, and remote reporting device (e.g. cell phone system). Maximum distances between the transmitting and receiving stations are approximately 1.61 km (1 mile), although the length of pipeline monitored can be twice this using a single transmitter and one receiver on each side (since the signal travels in both directions). Certain conditions such as poor pipeline coatings or strong induced 60-Hz signals on the pipeline can degrade IACC performance, so localized testing should be performed to determine the suitability for an IACC installation at a given location. The method can be used with pipelines having active CP systems in place without causing interference with operation of the CP system. The most appropriate use of IACC is monitoring of localized high-consequence areas where there is a significant risk of third-party contact (e.g. construction activity). The method also lends itself to temporary, low-cost installation where there is a short-term need for monitoring.

  20. Centrifuge modelling of lateral pipeline/soil interaction -- Phase 2

    SciTech Connect (OSTI)

    Paulin, M.J.; Phillips, R. [Memorial Univ. of Newfoundland, St. John`s, Newfoundland (Canada). Centre for Cold Ocean Resources Engineering; Boivin, R. [NOVA Corp., Calgary, Alberta (Canada). NOVA Gas Transmission Limited Division

    1995-12-31T23:59:59.000Z

    An ongoing research program is investigating the load transfer behavior of buried pipelines subjected to lateral soil movement in cohesive soil. Phase 1 of this study, reported to OMAE `92, demonstrated that the centrifuge technique was appropriate for this application in determining the interaction conditions for the lateral loading of pipelines. Limited control of the shear strength masked geometric effects (trench width and burial depth) on the interaction factors and desiccation affected the interpretation of some of the interaction factors. The Phase 2 study investigated the geometric effects of pipeline soil cover, ditch width and also displacement rate. The study included a ``modelling of models`` test to verify the reliability of the centrifuge modelling technique. This paper addresses two issues: (1) The Phase 1 soil strength profiles and interaction factors were reanalyzed based on an improved understanding of the soil conditions at the time of testing; (2) A selection of the Phase 2 results are presented for a 0.95m diameter pipeline subjected to lateral soil movement. The program results are discussed and compared with current pipeline/soil interaction analysis methods.

  1. Blending Hydrogen into Natural Gas Pipeline Networks: A Review of Key Issues

    Fuel Cell Technologies Publication and Product Library (EERE)

    This study assesses the potential to deliver hydrogen through the existing natural gas pipeline network as a hydrogen and natural gas mixture to defray the cost of building dedicated hydrogen pipeline

  2. Alternatives for reducing the environmental risks associated with natural disasters and their effects on pipelines 

    E-Print Network [OSTI]

    Wellborn, Michael Wayne

    1996-01-01T23:59:59.000Z

    Past pipeline failure reports have typically focused on corrosion and third party related events. However, natural disasters pose a substantial risk to pipeline integrity as well. Therefore, it was the objective of this thesis to analyze the risks...

  3. Behavioral modeling and digital calibration of pipeline analog to digital converters 

    E-Print Network [OSTI]

    Bilhan, Erkan

    2001-01-01T23:59:59.000Z

    This research focuses on digital calibration of pipeline analog to digital converters (ADCs) and also modeling of error sources and design parameters of pipeline ADCs. Modern applications such as communications systems require high resolution ADCs...

  4. Workgroup #2 Emerging Solutions and Technologies How can we keep the pipeline full of

    E-Print Network [OSTI]

    Workgroup #2 Emerging Solutions and Technologies ­ How can we keep the pipeline full of energy to keep the pipeline full of energy efficiency innovations for use in the Pacific Northwest." Our Phase 1

  5. Behavioral modeling and digital calibration of pipeline analog to digital converters

    E-Print Network [OSTI]

    Bilhan, Erkan

    2001-01-01T23:59:59.000Z

    This research focuses on digital calibration of pipeline analog to digital converters (ADCs) and also modeling of error sources and design parameters of pipeline ADCs. Modern applications such as communications systems require high resolution ADCs...

  6. Isolation valve selections play important role in pipelining

    SciTech Connect (OSTI)

    Hingoraney, R.; Goto, D.N. [Saudi Aramco, Dhahran (Saudi Arabia)

    1995-08-01T23:59:59.000Z

    Isolation valves are an integral part of every pipeline and play an important role in safe and proper operation. For almost every project, pipeline designers wrestle with choosing between the through-conduit gate valves and ball valves and their associated actuating mechanisms. Complicating this selection process are variables such as individual preferences and the lack of broad-based operating experience. As expected, there is no single valve and actuator combination that is correct for every pipeline or every application. Variables which must be considered and specifically evaluated for each valve installation include: operating characteristics, function, location, process fluid, materials options, space availability, maintenance, repair capability, delivery schedule, and costs. This paper reviews these issues.

  7. U. S. gas pipelines move to comply with Order 636

    SciTech Connect (OSTI)

    Not Available

    1992-06-15T23:59:59.000Z

    This paper reports that more US interstate gas pipelines have unveiled plans to comply with the Federal Energy Regulatory Commission's Order 636 megarestructuring rule. In the latest developments: Texas Eastern Transmission Corp. (Tetco) filed the first Order 636 compliance proposal with FERC outlining new transportation rates, operational issues, and services the company plans to offer. Tenneco Gas will eliminate a layer of managers and split marketing and transportation functions into four divisions to deal with Order 646. ANR Pipeline Co. made organizational changes expected to help it participate faster and more effectively under Order 636. The company in mid-May made gas sales a stand alone activity, reorganized system sales by region, and consolidated transportation and storage functions. FERC's long awaited megarestructuring rule, issued early in April, aims to assure the open access, interstate pipelines provide equal services for all gas supplies. Companies are to submit transition plans to FERC by Nov. 2.

  8. Data Reduction Pipeline for the MMT and Magellan Infrared Spectrograph

    E-Print Network [OSTI]

    Chilingarian, Igor; Moran, Sean; Brown, Warren; McLeod, Brian; Fabricant, Daniel

    2015-01-01T23:59:59.000Z

    We describe the new spectroscopic data reduction pipeline for the multi-object MMT/Magellan Infrared Spectrograph. The pipeline is implemented in idl as a stand-alone package and is publicly available in both stable and development versions. We describe novel algorithms for sky subtraction and correction for telluric absorption. We demonstrate that our sky subtraction technique reaches the Poisson limit set by the photon statistics. Our telluric correction uses a hybrid approach by first computing a correction function from an observed stellar spectrum, and then differentially correcting it using a grid of atmosphere transmission models for the target airmass value. The pipeline provides a sufficient level of performance for real time reduction and thus enables data quality control during observations. We reduce an example dataset to demonstrate the high data reduction quality.

  9. Soft-Decision-Driven Channel Estimation for Pipelined Turbo Receivers

    E-Print Network [OSTI]

    Yoon, Daejung

    2011-01-01T23:59:59.000Z

    We consider channel estimation specific to turbo equalization for multiple-input multiple-output (MIMO) wireless communication. We develop a soft-decision-driven sequential algorithm geared to the pipelined turbo equalizer architecture operating on orthogonal frequency division multiplexing (OFDM) symbols. One interesting feature of the pipelined turbo equalizer is that multiple soft-decisions become available at various processing stages. A tricky issue is that these multiple decisions from different pipeline stages have varying levels of reliability. This paper establishes an effective strategy for the channel estimator to track the target channel, while dealing with observation sets with different qualities. The resulting algorithm is basically a linear sequential estimation algorithm and, as such, is Kalman-based in nature. The main difference here, however, is that the proposed algorithm employs puncturing on observation samples to effectively deal with the inherent correlation among the multiple demappe...

  10. Alaskan Natural Gas Pipeline Developments (released in AEO2007)

    Reports and Publications (EIA)

    2007-01-01T23:59:59.000Z

    The Annual Energy Outlook 2007 reference case projects that an Alaska natural gas pipeline will go into operation in 2018, based on the Energy Information Administration's current understanding of the projects time line and economics. There is continuing debate, however, about the physical configuration and the ownership of the pipeline. In addition, the issue of Alaskas oil and natural gas production taxes has been raised, in the context of a current market environment characterized by rising construction costs and falling natural gas prices. If rates of return on investment by producers are reduced to unacceptable levels, or if the project faces significant delays, other sources of natural gas, such as unconventional natural gas production and liquefied natural gas imports, could fulfill the demand that otherwise would be served by an Alaska pipeline.

  11. Blending Hydrogen into Natural Gas Pipeline Networks: A Review of Key Issues

    SciTech Connect (OSTI)

    Melaina, M. W.; Antonia, O.; Penev, M.

    2013-03-01T23:59:59.000Z

    The United States has 11 distinct natural gas pipeline corridors: five originate in the Southwest, four deliver natural gas from Canada, and two extend from the Rocky Mountain region. This study assesses the potential to deliver hydrogen through the existing natural gas pipeline network as a hydrogen and natural gas mixture to defray the cost of building dedicated hydrogen pipelines.

  12. Pipeline Transportation of Petroleum Products 1 Ruy Luiz Milidi'u

    E-Print Network [OSTI]

    Endler, Markus

    Pipeline Transportation of Petroleum Products 1 Ruy Luiz Milidi'u milidiu@inf.puc­rio.br Artur Introdution Petroleum products are typically transported in pipelines which are different from all other, 2000 Abstract: In this paper, we introduce a new model for pipeline transportation of petroleum

  13. REAL-TIME ACTIVE PIPELINE INTEGRITY DETECTION (RAPID) SYSTEM FOR CORROSION DETECTION AND QUANTIFICATION

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    alone there are over 2 million miles of natural gas transmission and distribution pipeline providing 24REAL-TIME ACTIVE PIPELINE INTEGRITY DETECTION (RAPID) SYSTEM FOR CORROSION DETECTION detection Acellent has developed a Real-time Active Pipeline Integrity Detection (RAPID) system. The RAPID

  14. Hydrogen Pipeline Safety Our goal is to establish the codes and standards necessary

    E-Print Network [OSTI]

    Perkins, Richard A.

    Hydrogen Pipeline Safety METALS Our goal is to establish the codes and standards necessary miles of hydrogen pipelines are currently in operation in the U.S. (compared to > 1M miles of natural, materials, mechanical properties, and standards for hydrogen pipelines. Construction is complete on the 750

  15. AROW A 128 Channel Analogue Pipeline with Wilkinson ADC and Sparsification ASIC

    E-Print Network [OSTI]

    California at Santa Cruz, University of

    AROW ­ A 128 Channel Analogue Pipeline with Wilkinson ADC and Sparsification ASIC Authors: FS on a capacitor pipeline. A level­1 trigger is sent to the front end electronics from the trigger processorA/fC, giving a combined gain of approximately 100mV/MIP. .Analogue storage capacitor pipeline with differential

  16. Optimized Sampling Frequencies for Weld Reliability Assessments of Long Pipeline Segments

    E-Print Network [OSTI]

    Kreinovich, Vladik

    p. If this probability exceeds a certain regulated (small) threshold p 0 , the pipeline must. To be on the safe side, regulations require that a pipeline be repaired when it is possible that p â?? p 0 , iOptimized Sampling Frequencies for Weld Reliability Assessments of Long Pipeline Segments Cesar J

  17. Optimized Sampling Frequencies for Weld Reliability Assessments of Long Pipeline Segments

    E-Print Network [OSTI]

    Kreinovich, Vladik

    p. If this probability exceeds a certain regulated (small) threshold p0, the pipeline must. To be on the safe side, regulations require that a pipeline be repaired when it is possible that p p0, i.e., when pOptimized Sampling Frequencies for Weld Reliability Assessments of Long Pipeline Segments Cesar J

  18. Automatic Modeling and Validation of Pipeline Specifications driven by an Architecture Description Language

    E-Print Network [OSTI]

    Mishra, Prabhat

    ) design process. Many existing approaches employ a bottom-up approach to pipeline validation, where about the behavior of the pipelined ar- chitecture through ADL constructs, which allows a powerful topAutomatic Modeling and Validation of Pipeline Specifications driven by an Architecture Description

  19. An Automatic Image Reduction Pipeline for the Advanced Camera for Surveys

    E-Print Network [OSTI]

    Johns Hopkins University, Department of Physics and Astonomy, Advanced Camera for Surveys Team

    are constructed similar to those used in STScI OPUS pipeline. Reading and manipulation of FITS images and tables and catalogs) for archiving purposes. Although Apsis was designed primarily as an automated pipeline, it canAn Automatic Image Reduction Pipeline for the Advanced Camera for Surveys John P. Blakeslee

  20. Transverse wave loading on partially buried marine pipelines

    E-Print Network [OSTI]

    Webb, Richard Edgar

    1988-01-01T23:59:59.000Z

    TRANSVERSE WAVE LOADING ON PARTIALLY BURIED MARINE PIPELINES A Thesis by RICHARD EDGAR WEBB Submitted to the Office of Graduate Studies of Texas A&M University in partial fulfillment of the requirements for the degree of MASTER OF SCIENCE... December l988 Ma)or Subject: Civil Engineering TRANSVERSE WAVE LOADING ON PARTIALLY BURIED MARINE PIPELINES A Thesis bY RICHARD EDGAR WEBB Approved as to style and content by: Derek V. M ris (Chair of Committee) Calvin E. Woods (Member) Norman R...

  1. Using Fuzzy Logic for Automatic Analysis of Astronomical Pipelines

    E-Print Network [OSTI]

    Lior Shamir; Robert J. Nemiroff

    2005-06-27T23:59:59.000Z

    Fundamental astronomical questions on the composition of the universe, the abundance of Earth-like planets, and the cause of the brightest explosions in the universe are being attacked by robotic telescopes costing billions of dollars and returning vast pipelines of data. The success of these programs depends on the accuracy of automated real time processing of the astronomical images. In this paper the needs of modern astronomical pipelines are discussed in the light of fuzzy-logic based decision-making. Several specific fuzzy-logic algorithms have been develop for the first time for astronomical purposes, and tested with excellent results on data from the existing Night Sky Live sky survey.

  2. The effect of pipe spacing on marine pipeline scour

    E-Print Network [OSTI]

    Westerhorstmann, Joseph Henry

    1988-01-01T23:59:59.000Z

    . The stability of these subsea pipelines is threatened by loss of bed support resulting from scour. This thesis reviews pipeline scour and presents results of model testing on single and multiple pipes in contact with a sand bed. Few theoretical models exist... and clamp attachment. The maximum recommended cable and circuit resistance is 1. 0 ohm and frequency range in autocompensation mode is 0. 2 to above 10. 0 Hz. Scour profiles were measured with a point gauge profiler. The profiler was manually operated...

  3. ENERGY UTILIZATION AND ENVIRONMENTAL CONTROL TECHNOLOGIES IN THE COAL-ELECTRIC CYCLE

    E-Print Network [OSTI]

    Ferrell, G.C.

    2010-01-01T23:59:59.000Z

    plants. Only one coal slurry pipeline is currently operatinggenerally agreed that new coal slurry pipelines may have amade in railroad capacity, coal-slurry pipelines or expanded

  4. National Smart Water Grid

    SciTech Connect (OSTI)

    Beaulieu, R A

    2009-07-13T23:59:59.000Z

    The United States repeatedly experiences floods along the Midwest's large rivers and droughts in the arid Western States that cause traumatic environmental conditions with huge economic impact. With an integrated approach and solution these problems can be alleviated. Tapping into the Mississippi River and its tributaries, the world's third largest fresh water river system, during flood events will mitigate the damage of flooding and provide a new source of fresh water to the Western States. The trend of increased flooding on the Midwest's large rivers is supported by a growing body of scientific literature. The Colorado River Basin and the western states are experiencing a protracted multi-year drought. Fresh water can be pumped via pipelines from areas of overabundance/flood to areas of drought or high demand. Calculations document 10 to 60 million acre-feet (maf) of fresh water per flood event can be captured from the Midwest's Rivers and pumped via pipelines to the Colorado River and introduced upstream of Lake Powell, Utah, to destinations near Denver, Colorado, and used in areas along the pipelines. Water users of the Colorado River include the cities in southern Nevada, southern California, northern Arizona, Colorado, Utah, Indian Tribes, and Mexico. The proposed start and end points, and routes of the pipelines are documented, including information on right-of-ways necessary for state and federal permits. A National Smart Water Grid{trademark} (NSWG) Project will create thousands of new jobs for construction, operation, and maintenance and save billions in drought and flood damage reparations tax dollars. The socio-economic benefits of NWSG include decreased flooding in the Midwest; increased agriculture, and recreation and tourism; improved national security, transportation, and fishery and wildlife habitats; mitigated regional climate change and global warming such as increased carbon capture; decreased salinity in Colorado River water crossing the US-Mexico border; and decreased eutrophication (excessive plant growth and decay) in the Gulf of Mexico to name a few. The National Smart Water Grid{trademark} will pay for itself in a single major flood event.

  5. HANFORD SITE LOW EXPOSURE PIPELINE REPAIR USING A NON-METALLIC COMPOSITE SYSTEM

    SciTech Connect (OSTI)

    HUTH RJ

    2009-11-12T23:59:59.000Z

    At the Department of Energy, Richland Operations (DOE-RL) Hanford site in eastern Washington, a 350 mm (14 inch) diameter high density polyethylene (HDPE) pump recirculation pipeline failed at a bonded joint adjacent to a radiologically and chemically contaminated groundwater storage basin. The responsible DOE-RL contractor, CH2MHill Plateau Remediation Company, applied a fiberglass reinforced plastic (composite) field repair system to the failed joint. The system was devised specifically for the HDPE pipe repair at the Hanford site, and had not been used on this type of plastic piping previously. This paper introduces the pipe failure scenario, describes the options considered for repair and discusses the ultimate resolution of the problem. The failed pipeline was successfully returned to service with minimal impact on waste water treatment plant operating capacity. Additionally, radiological and chemical exposures to facility personnel were maintained as low as reasonably achievable (ALARA). The repair is considered a success for the near term, and future monitoring will prove whether the repair can be considered for long term service and as a viable alternative for similar piping failures at the Hanford site.

  6. Use of geographic information systems for applications on gas pipeline rights-of-way

    SciTech Connect (OSTI)

    Sydelko, P.J.; Wilkey, P.L.

    1992-01-01T23:59:59.000Z

    Geographic information system (GIS) applications for the siting and monitoring of gas pipeline rights-of-way (ROWS) were developed for areas near Rio Vista, California. The data layers developed for this project represent geographic features, such as landcover, elevation, aspect, slope, soils, hydrography, transportation, endangered species, wetlands, and public line surveys. A GIS was used to develop and store spatial data from several sources; to manipulate spatial data to evaluate environmental and engineering issues associated with the siting, permitting, construction, maintenance, and monitoring of gas pipeline ROWS; and to graphically display analysis results. Examples of these applications include (1) determination of environmentally sensitive areas, such as endangered species habitat, wetlands, and areas of highly erosive soils; (2) evaluation of engineering constraints, including shallow depth to bedrock, major hydrographic features, and shallow water table; (3) classification of satellite imagery for landuse/landcover that will affect ROWS; and (4) identification of alternative ROW corridors that avoid environmentally sensitive areas or areas with severe engineering constraints.

  7. Use of geographic information systems for applications on gas pipeline rights-of-way

    SciTech Connect (OSTI)

    Sydelko, P.J.

    1993-10-01T23:59:59.000Z

    Geographic information system (GIS) applications for the siting and monitoring of gas pipeline rights-of-way (ROWS) were developed for areas near Rio Vista, California. The data layers developed for this project represent geographic features, such as landcover, elevation, aspect, slope, soils, hydrography, transportation, endangered species, wetlands, and public line surveys. A GIS was used to develop and store spatial data from several sources; to manipulate spatial data to evaluate environmental and engineering issues associated with the siting, permitting, construction, maintenance, and monitoring of gas pipeline ROWS; and to graphically display analysis results. Examples of these applications include (1) determination of environmentally sensitive areas, such as endangered species habitat, wetlands, and areas of highly erosive soils; (2) evaluation of engineering constraints, including shallow depth to bedrock, major hydrographic features, and shallow water table; (3) classification of satellite imagery for land use/landcover that will affect ROWS; and (4) identification of alternative ROW corridors that avoid environmentally sensitive areas or areas with severe engineering constraints.

  8. Use of geographic information systems for applications on gas pipeline rights-of-way

    SciTech Connect (OSTI)

    Sydelko, P.J.; Wilkey, P.L.

    1992-12-01T23:59:59.000Z

    Geographic information system (GIS) applications for the siting and monitoring of gas pipeline rights-of-way (ROWS) were developed for areas near Rio Vista, California. The data layers developed for this project represent geographic features, such as landcover, elevation, aspect, slope, soils, hydrography, transportation, endangered species, wetlands, and public line surveys. A GIS was used to develop and store spatial data from several sources; to manipulate spatial data to evaluate environmental and engineering issues associated with the siting, permitting, construction, maintenance, and monitoring of gas pipeline ROWS; and to graphically display analysis results. Examples of these applications include (1) determination of environmentally sensitive areas, such as endangered species habitat, wetlands, and areas of highly erosive soils; (2) evaluation of engineering constraints, including shallow depth to bedrock, major hydrographic features, and shallow water table; (3) classification of satellite imagery for landuse/landcover that will affect ROWS; and (4) identification of alternative ROW corridors that avoid environmentally sensitive areas or areas with severe engineering constraints.

  9. Avista Utilities- Net Metering

    Broader source: Energy.gov [DOE]

    Idaho does not have a statewide net-metering policy. However, each of the state's three investor-owned utilities -- Avista Utilities, Idaho Power and Rocky Mountain Power -- has developed a net...

  10. Mississippi Public Utility Act

    Broader source: Energy.gov [DOE]

    The Mississippi Public Utility Act is relevant to any project that plans to generate energy. It requires that a utility must first obtain a Certificate of Public Convenience and Necessity (CPCN)...

  11. Electrical utilities relay settings

    SciTech Connect (OSTI)

    HACHE, J.M.

    1999-02-24T23:59:59.000Z

    This document contains the Hanford transmission and distribution system relay settings that are under the control of Electrical Utilities.

  12. GSA- Utility Interconnection Agreements

    Broader source: Energy.gov [DOE]

    Presentation given at the Spring 2010 Federal Utility Partnership Working Group (FUPWG) meeting in Providence, Rhode Island.

  13. By-Products Utilization

    E-Print Network [OSTI]

    Wisconsin-Milwaukee, University of

    International Conference onFly Ash Disposal and Utilization,onJanuary 20-22, 1998, New Delhi, India. COAL ASH and Applied Science THE UNIVERSITY OF WISCONSIN - MILWAUKEE #12;COAL ASH GENERATIONANDUTILIZATION: A REVIEW and utilization of coal ash in many parts of the world. The utilization potential for coal ash generated from

  14. YEAR 2 BIOMASS UTILIZATION

    SciTech Connect (OSTI)

    Christopher J. Zygarlicke

    2004-11-01T23:59:59.000Z

    This Energy & Environmental Research Center (EERC) Year 2 Biomass Utilization Final Technical Report summarizes multiple projects in biopower or bioenergy, transportation biofuels, and bioproducts. A prototype of a novel advanced power system, termed the high-temperature air furnace (HITAF), was tested for performance while converting biomass and coal blends to energy. Three biomass fuels--wood residue or hog fuel, corn stover, and switchgrass--and Wyoming subbituminous coal were acquired for combustion tests in the 3-million-Btu/hr system. Blend levels were 20% biomass--80% coal on a heat basis. Hog fuel was prepared for the upcoming combustion test by air-drying and processing through a hammer mill and screen. A K-Tron biomass feeder capable of operating in both gravimetric and volumetric modes was selected as the HITAF feed system. Two oxide dispersion-strengthened (ODS) alloys that would be used in the HITAF high-temperature heat exchanger were tested for slag corrosion rates. An alumina layer formed on one particular alloy, which was more corrosion-resistant than a chromia layer that formed on the other alloy. Research activities were completed in the development of an atmospheric pressure, fluidized-bed pyrolysis-type system called the controlled spontaneous reactor (CSR), which is used to process and condition biomass. Tree trimmings were physically and chemically altered by the CSR process, resulting in a fuel that was very suitable for feeding into a coal combustion or gasification system with little or no feed system modifications required. Experimental procedures were successful for producing hydrogen from biomass using the bacteria Thermotoga, a deep-ocean thermal vent organism. Analytical procedures for hydrogen were evaluated, a gas chromatography (GC) method was derived for measuring hydrogen yields, and adaptation culturing and protocols for mutagenesis were initiated to better develop strains that can use biomass cellulose. Fly ash derived from cofiring coal with waste paper, sunflower hulls, and wood waste showed a broad spectrum of chemical and physical characteristics, according to American Society for Testing and Materials (ASTM) C618 procedures. Higher-than-normal levels of magnesium, sodium, and potassium oxide were observed for the biomass-coal fly ash, which may impact utilization in cement replacement in concrete under ASTM requirements. Other niche markets for biomass-derived fly ash were explored. Research was conducted to develop/optimize a catalytic partial oxidation-based concept for a simple, low-cost fuel processor (reformer). Work progressed to evaluate the effects of temperature and denaturant on ethanol catalytic partial oxidation. A catalyst was isolated that had a yield of 24 mole percent, with catalyst coking limited to less than 15% over a period of 2 hours. In biodiesel research, conversion of vegetable oils to biodiesel using an alternative alkaline catalyst was demonstrated without the need for subsequent water washing. In work related to biorefinery technologies, a continuous-flow reactor was used to react ethanol with lactic acid prepared from an ammonium lactate concentrate produced in fermentations conducted at the EERC. Good yields of ester were obtained even though the concentration of lactic acid in the feed was low with respect to the amount of water present. Esterification gave lower yields of ester, owing to the lowered lactic acid content of the feed. All lactic acid fermentation from amylose hydrolysate test trials was completed. Management activities included a decision to extend several projects to December 31, 2003, because of delays in receiving biomass feedstocks for testing and acquisition of commercial matching funds. In strategic studies, methods for producing acetate esters for high-value fibers, fuel additives, solvents, and chemical intermediates were discussed with several commercial entities. Commercial industries have an interest in efficient biomass gasification designs but are waiting for economic incentives. Utility, biorefinery, pulp and paper, or o

  15. Water and Energy Interactions

    E-Print Network [OSTI]

    McMahon, James E.

    2013-01-01T23:59:59.000Z

    truck, conveyor belts, and coal slurry pipelines (17).Coal slurry pipelines transport coal over long distances andto-one ratio to create a coal slurry transportable through

  16. A contingency plan helps companies prepare for oilfield, pipeline spills

    SciTech Connect (OSTI)

    Duey, R.

    1996-02-01T23:59:59.000Z

    There are many hazards associated with oilfield, pipeline spills such as fires, litigation, fines, etc. Operators and companies need to have a plan in place and make sure their employees know what to do when disaster strikes. This paper describes emergency preparedness plans.

  17. Pipelined Implementation of the Hough Transform in a Pyramid Multiprocessor

    E-Print Network [OSTI]

    Atiquzzaman, Mohammed

    of the transform is its requirement for a large amount of computing power. The computational requirement. 1 Introduction The Hough transform [1] is a powerful technique to detect patterns in imagesPipelined Implementation of the Hough Transform in a Pyramid Multiprocessor M. Atiquzzaman Dept

  18. Planned oil pipeline vital to economy of Kazakhstan

    SciTech Connect (OSTI)

    NONE

    1996-08-01T23:59:59.000Z

    The West Kazakhstan-Kumkol pipeline project is extremely vital to the economy of the Republic of Kazakhstan`s ultimate goal of transporting crude oil produced from the western part of the country eastward to Kumkol, from where it is further transported through existing pipelines to refineries in Chimkent in the south and Pavoldar in the northeast. The two refineries are now mainly supplied with west Siberian crudes imported through a pipeline that approaches Kazakhstan via Omsk. The planned pipeline will allow increased use of local crudes, thereby considerably improving a secure supply for the consumers while also increasing the flexibility of the nation`s overall import/export situation. The importance of this project is stressed by the Kazakh government which has officially classified it as a national priority project. The technical feasibility study of the project was prepared by ILF Consulting Engineers of Germany and Price Waterhouse Financial Consultants is conducting a study to determine the economical viability of the project. The overall cost is estimated at $1.1 billion, with the cost of Phase 1 placed at $600 million.

  19. Gas supplies of interstate/natural gas pipeline companies 1989

    SciTech Connect (OSTI)

    Not Available

    1990-12-18T23:59:59.000Z

    This publication provides information on the interstate pipeline companies' supply of natural gas during calendar year 1989, for use by the FERC for regulatory purposes. It also provides information to other Government agencies, the natural gas industry, as well as policy makers, analysts, and consumers interested in current levels of interstate supplies of natural gas and trends over recent years. 5 figs., 18 tabs.

  20. MODELING AND VERIFICATION OF A PIPELINED CPU Lubomir Ivanov

    E-Print Network [OSTI]

    Ivanov, Lubomir

    of complex hardware and software systems. Several powerful verification methods, such as Symbolic ModelMODELING AND VERIFICATION OF A PIPELINED CPU Lubomir Ivanov Department of Computer Science, Iona interleavings of events in a system. In [8] we introduced a new partial order verification method, referred

  1. The RNA-Seq Analysis pipeline on Galaxy

    SciTech Connect (OSTI)

    Meng, Xiandong; Martin, Jeffrey; Wang, Zhong

    2011-05-31T23:59:59.000Z

    Q: How do I know my RNA-Seq experiments worked well A: RNA-Seq QC PipelineQ: How do I detect transcripts which are over expressed or under expressed in my samples A: Counting and Statistic AnalysisQ: What do I do if I don't have a reference genome A: Rnnotator de novo Assembly.

  2. Northampton planners `thrilled' with affordable housing in pipeline

    E-Print Network [OSTI]

    Mountziaris, T. J.

    Northampton planners `thrilled' with affordable housing in pipeline By CHAD CAIN Daily Hampshire and two other significant developments under construction for senior citizens and veterans elsewhere's senior land use planner, said both panels offered small design tweaks but lauded the project overall

  3. Data Management & Characterization: Pipeline Approaches to Calibration/Reduction

    E-Print Network [OSTI]

    Ellingson, Steven W.

    /23/2001 LWA Data Management 1 #12;The LWA & the VLSS · VLSS 74 MHz all sky survey will deliver initialData Management & Characterization: Pipeline Approaches to Calibration/Reduction Namir Kassim NRL 5 ­ emerging ionospheric weather diagnostics 5/23/2001 LWA Data Management 2 #12;VLSS: Good science, Good

  4. Natural Gas Pipeline Research: Best Practices in Monitoring Technology

    E-Print Network [OSTI]

    Natural Gas Pipeline Research: Best Practices in Monitoring Technology Energy Systems Research/index.html January 2012 The Issue California is the secondlargest natural gas consuming state in the United States, just behind Texas. About 85% of the natural gas consumed in California is delivered on interstate

  5. Optimal Design of Synchronous Circuits Using Software Pipelining Techniques

    E-Print Network [OSTI]

    Boyer, Michel

    Computer Society Press, Los Alamitos, Calif., pp. 62-67. Author's addresses: F. R. Boyer, E. M. AboulhamidOptimal Design of Synchronous Circuits Using Software Pipelining Techniques FRANC¸OIS R. BOYER´eal and MICHEL BOYER Universit´e de Montr´eal We present a method to optimize clocked circuits by relocating

  6. ReCycle: Pipeline Adaptation to Tolerate Process Variation

    E-Print Network [OSTI]

    Torrellas, Josep

    ReCycle: Pipeline Adaptation to Tolerate Process Variation Abhishek Tiwari, Smruti R. Sarangi, Josep Torrellasg 1 #12;OutlineOutline · MotivationMotivation · ReCycle Idea U i R C l· Using ReCycle · ReCycle System overview · Results 2 #12;MotivationMotivation V i ti k t l th· Variation makes some

  7. Utilization of low-quality natural gas: A current assessment. Final report

    SciTech Connect (OSTI)

    Acheson, W.P.; Hackworth, J.H.; Kasper, S.; McIlvried, H.G.

    1993-01-01T23:59:59.000Z

    The objective of this report is to evaluate the low quality natural gas (LQNG) resource base, current utilization of LQNG, and environmental issues relative to its use, to review processes for upgrading LQNG to pipeline quality, and to make recommendations of research needs to improve the potential for LQNG utilization. LQNG is gas from any reservoir which contains amounts of nonhydrocarbon gases sufficient to lower the heating value or other properties of the gas below commercial, pipeline standards. For the purposes of this study, LQNG is defined as natural gas that contains more than 2% carbon dioxide, more than 4% nitrogen, or more than 4% combined CO{sub 2} plus N{sub 2}. The other contaminant of concern is hydrogen sulfide. A minor contaminant in some natural gases is helium, but this inert gas usually presents no problems.

  8. Lakeland Electric- Solar Water Heating Program

    Broader source: Energy.gov [DOE]

    Lakeland Electric, a municipal utility in Florida, is the nation's first utility to offer solar-heated domestic hot water on a "pay-for-energy" basis. The utility has contracted with a solar...

  9. Carrots for Utilities: Providing Financial Returns for Utility...

    Open Energy Info (EERE)

    Carrots for Utilities: Providing Financial Returns for Utility Investments in Energy Efficiency Jump to: navigation, search Tool Summary LAUNCH TOOL Name: Carrots for Utilities:...

  10. "List of Covered Electric Utilities" under the Public Utility...

    Energy Savers [EERE]

    6 Revised "List of Covered Electric Utilities" under the Public Utility Regulatory Policies Act of 1978 (PURPA) - 2006 Revised Under Title I of the Public Utility Regulatory...

  11. Copyright Awwa Research Foundation 2006 Advanced Water Treatment Impacts onAdvanced Water Treatment Impacts on

    E-Print Network [OSTI]

    Keller, Arturo A.

    , brackish groundwater, produced water, etc.produced water, etc. Advanced treatmentAdvanced treatment Water© Copyright Awwa Research Foundation 2006 Advanced Water Treatment Impacts onAdvanced Water Treatment Impacts on EnergyEnergy--Water LinkagesWater Linkages (The Water Utility Perspective)(The Water

  12. Florida Sunshine -- Natural Source for Heating Water

    SciTech Connect (OSTI)

    Not Available

    2002-05-01T23:59:59.000Z

    This brochure, part of the State Energy Program (SEP) Stellar Project series, describes a utility solar hot water program in Lakeland, Florida. It is the first such utility-run solar hot water program in the country.

  13. Electric Utility Industry Update

    Broader source: Energy.gov [DOE]

    Presentation—given at the April 2012 Federal Utility Partnership Working Group (FUPWG) meeting—covers significant electric industry trends and industry priorities with federal customers.

  14. Utility Data Collection Service

    Broader source: Energy.gov [DOE]

    Presentation covers the utility data collection service and is given at the FUPWG 2006 Spring meeting, held on May 3-4, 2006 in Atlanta, Georgia.

  15. Joint Electrical Utilities (Iowa)

    Broader source: Energy.gov [DOE]

    Cities may establish utilities to acquire existing electric generating facilities or distribution systems. Acquisition, in this statute, is defined as city involvement, and includes purchase, lease...

  16. Utility Regulation (Indiana)

    Broader source: Energy.gov [DOE]

    The Indiana Utility Regulatory Commission enforces regulations in this legislation that apply to all individuals, corporations, companies, and partnerships that may own, operate, manage, or control...

  17. Utility Service Renovations

    Broader source: Energy.gov [DOE]

    Any upgrade to utility service provides an opportunity to revisit a Federal building's electrical loads and costs, but it also may provide an economic way to bundle the upgrade with an onsite renewable electricity project during renovation. Upgrading utility service to the site may involve improving or adding a transformer, upgrading utility meters, or otherwise modifying the interconnection equipment or services with the utility. In some cases, the upgrade may change the tariff structure for the facility and may qualify the property for a different structure with lower overall costs. In all cases, the implementation of renewable energy technologies should be identified during the design phase.

  18. Municipal Utility Districts (Texas)

    Broader source: Energy.gov [DOE]

    Municipal Utility Districts, regulated by the Texas Commission on Environmental Quality, may be created for the following purposes: (1) the control, storage, preservation, and distribution of its...

  19. Validating the Estimated Cost of Saving Water Through Infrastructure Rehabilitation in the Texas Lower Rio Grande Valley

    E-Print Network [OSTI]

    Sturdivant, A. W.; Rister, M.; Lacewell, R. D.

    The original ‘final’ economic analysis reporting on the Wisconsin Pipeline project was reported in July, 2003 in Texas Water Resources Institute TR-220R, entitled “Economic and Conservation Evaluation of Capital Renovation Projects: Hidalgo County...

  20. Validating the Estimated Cost of Saving Water Through Infrastructure Rehabilitation in the Texas Lower Rio Grande Valley 

    E-Print Network [OSTI]

    Sturdivant, A. W.; Rister, M.; Lacewell, R. D.

    2005-01-01T23:59:59.000Z

    The original ‘final’ economic analysis reporting on the Wisconsin Pipeline project was reported in July, 2003 in Texas Water Resources Institute TR-220R, entitled “Economic and Conservation Evaluation of Capital Renovation Projects: Hidalgo County...