Powered by Deep Web Technologies
Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


1

Regional Refinery Utilization Shows Gulf Coast Pressure  

Gasoline and Diesel Fuel Update (EIA)

5 5 Notes: But there is some room for hope. Refineries generally begin maintenance in February or March, and finish in April. The East Coast was experiencing some lengthy refinery maintenance outages, as shown by the drop in utilization that remained low in most of March and April. In the meantime, the East Coast was drawing on extra supplies from the Gulf Coast and imports. The Midwest refineries seem to have been ramping up in April as they finished what maintenance was needed. But the Midwest no longer has the Blue Island refinery, so it also is pulling more product from the Gulf Coast. The high Gulf Coast prices this spring reflect extra "pull" on product from both the Midwest and the East Coast, and probably from California as well. Inputs into Gulf Coast refineries over the last 4 weeks

2

U.S. Percent Utilization of Refinery Operable Capacity (Percent)  

U.S. Energy Information Administration (EIA)

Annual : Download Data (XLS File) U.S. Percent Utilization of Refinery Operable Capacity (Percent) Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec; 1985: 74.0 ...

3

Flexible hydrogen plant utilizing multiple refinery hydrocarbon streams  

Science Conference Proceedings (OSTI)

Numerous processes are available to produce hydrogen, however, steam reforming is still the dominant and currently preferred process because it can economically process a variety of refinery feedstocks into hydrogen. This paper discusses the Air Products 88 MMSCFD hydrogen plant built by KTI, adjacent to Shell`s Martinez refinery, which utilizes up to eight separate refinery hydrocarbon streams as feed and fuel for the production of hydrogen in the steam reforming unit. The integration of refinery hydrocarbon purge streams, normally sent to fuel, allows greater flexibility in refinery operations and increases the overall refinery fuel efficiencies. The hydrogen plant also incorporates a number of process control design features to enhance reliability, such as two out of three voting systems, in-line sparing, and reduced bed PSA operation. The final section of the paper describes the environmental features of the plant required for operation in the Bay Area Air Quality Management District (BAAQMD). Air Products and KTI designed BACT features into the hydrogen plant to minimize emissions from the facility.

Kramer, K.A.; Patel, N.M. [Air Products and Chemicals Inc., Allentown, PA (United States); Sekhri, S. [Kinetics Technology International Corp., San Dimas, CA (United States); Brown, M.G. [Shell Oil Products Co., Martinez, CA (United States)

1996-12-01T23:59:59.000Z

4

U.S. Refinery Utilization and Capacity  

U.S. Energy Information Administration (EIA) Indexed Site

Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 View Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 View History Gross Input to Atmospheric Crude Oil Distillation Units 15,283 15,709 16,327 16,490 16,306 16,162 1985-2013 Operable Capacity (Calendar Day) 17,814 17,815 17,815 17,815 17,815 17,818 1985-2013 Operating 17,005 17,228 17,239 17,450 17,439 17,623 1985-2013 Idle 809 587 576 365 376 195 1985-2013 Operable Utilization Rate (%) 85.8 88.2 91.7 92.6 91.5 90.7 1985-2013 - = No Data Reported; -- = Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Totals may not equal sum of components due to independent rounding. See Definitions, Sources, and Notes link above for more information on this table. Release Date: 11/27/2013

5

Idaho Public Utilities Commission Approves Neal Hot Springs Power Purchase  

Open Energy Info (EERE)

Idaho Public Utilities Commission Approves Neal Hot Springs Power Purchase Idaho Public Utilities Commission Approves Neal Hot Springs Power Purchase Agreement Jump to: navigation, search OpenEI Reference LibraryAdd to library Report: Idaho Public Utilities Commission Approves Neal Hot Springs Power Purchase Agreement Abstract N/A Author U.S. Geothermal Inc. Published Publisher Not Provided, 2010 Report Number N/A DOI Not Provided Check for DOI availability: http://crossref.org Online Internet link for Idaho Public Utilities Commission Approves Neal Hot Springs Power Purchase Agreement Citation U.S. Geothermal Inc.. 2010. Idaho Public Utilities Commission Approves Neal Hot Springs Power Purchase Agreement. Boise Idaho: (!) . Report No.: N/A. Retrieved from "http://en.openei.org/w/index.php?title=Idaho_Public_Utilities_Commission_Approves_Neal_Hot_Springs_Power_Purchase_Agreement&oldid=682748"

6

Table N13.3. Electricity: Sales to Utility and Nonutility Purchasers, 1998  

U.S. Energy Information Administration (EIA) Indexed Site

3. Electricity: Sales to Utility and Nonutility Purchasers, 1998;" 3. Electricity: Sales to Utility and Nonutility Purchasers, 1998;" " Level: National and Regional Data; " " Row: NAICS Codes;" " Column: Utility and Nonutility Purchasers;" " Unit: Million Kilowatthours." " "," ",,,," " " "," ","Total of",,,"RSE" "NAICS"," ","Sales and","Utility","Nonutility","Row" "Code(a)","Subsector and Industry","Transfers Offsite","Purchaser(b)","Purchaser(c)","Factors" ,,"Total United States"

7

Table E13.3. Electricity: Sales to Utility and Nonutility Purchasers, 1998  

U.S. Energy Information Administration (EIA) Indexed Site

3. Electricity: Sales to Utility and Nonutility Purchasers, 1998;" 3. Electricity: Sales to Utility and Nonutility Purchasers, 1998;" " Level: National and Regional Data; " " Row: Values of Shipments and Employment Sizes;" " Column: Utility and Nonutility Purchasers;" " Unit: Million Kilowatthours." ,"Total of",,,"RSE" "Economic","Sales and","Utility","Nonutility","Row" "Characteristic(a)","Transfers Offsite","Purchaser(b)","Purchaser(c)","Factors" ,"Total United States" "RSE Column Factors:",0.9,1,1.1 "Value of Shipments and Receipts"

8

Table 11.6 Electricity: Sales to Utility and Nonutility Purchasers, 2002  

U.S. Energy Information Administration (EIA) Indexed Site

Electricity: Sales to Utility and Nonutility Purchasers, 2002;" Electricity: Sales to Utility and Nonutility Purchasers, 2002;" " Level: National and Regional Data; " " Row: Values of Shipments and Employment Sizes;" " Column: Utility and Nonutility Purchasers;" " Unit: Million Kilowatthours." ,"Total of",,,"RSE" "Economic","Sales and","Utility","Nonutility","Row" "Characteristic(a)","Transfers Offsite","Purchaser(b)","Purchaser(c)","Factors" ,"Total United States" "RSE Column Factors:",0.9,1.3,0.9 "Value of Shipments and Receipts" "(million dollars)"

9

Table A30. Quantity of Electricity Sold to Utility and Nonutility Purchasers  

U.S. Energy Information Administration (EIA) Indexed Site

Quantity of Electricity Sold to Utility and Nonutility Purchasers" Quantity of Electricity Sold to Utility and Nonutility Purchasers" " by Census Region, Census Division, Industry Group, and Selected Industries, 1994" " (Estimates in Million Kilowatthours)" " "," "," "," "," ","RSE" "SIC"," "," ","Utility ","Nonutility","Row" "Code(a)","Industry Group and Industry","Total Sold","Purchaser(b)","Purchaser(c)","Factors" ,,"Total United States" ,"RSE Column Factors:",0.9,1.1,1 , 20,"Food and Kindred Products",1829," W "," W ",28

10

Refinery Capacity Report 2007  

Reports and Publications (EIA)

Data series include fuel, electricity, and steam purchased for consumption at the refinery; refinery receipts of crude oil by method of transportation; current and projected capacities for atmospheric crude oil distillation, downstream charge, production, and storage capacities. Respondents are operators of all operating and idle petroleum refineries (including new refineries under construction) and refineries shut down during the previous year, located in the 50 States, the District of Columbia, Puerto Rico, the Virgin Islands, Guam, and other U.S. possessions.

Information Center

2007-06-29T23:59:59.000Z

11

Refinery Capacity Report 2009  

Reports and Publications (EIA)

Data series include fuel, electricity, and steam purchased for consumption at the refinery; refinery receipts of crude oil by method of transportation; current and projected capacities for atmospheric crude oil distillation, downstream charge, production, and storage capacities. Respondents are operators of all operating and idle petroleum refineries (including new refineries under construction) and refineries shut down during the previous year, located in the 50 States, the District of Columbia, Puerto Rico, the Virgin Islands, Guam, and other U.S. possessions.

Information Center

2009-06-25T23:59:59.000Z

12

Refinery Capacity Report 2008  

Reports and Publications (EIA)

Data series include fuel, electricity, and steam purchased for consumption at the refinery; refinery receipts of crude oil by method of transportation; current and projected capacities for atmospheric crude oil distillation, downstream charge, production, and storage capacities. Respondents are operators of all operating and idle petroleum refineries (including new refineries under construction) and refineries shut down during the previous year, located in the 50 States, the District of Columbia, Puerto Rico, the Virgin Islands, Guam, and other U.S. possessions.

Information Center

2008-06-20T23:59:59.000Z

13

Utility to Purchase Electricity from Innovative DOE-Supported Clean Coal  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Utility to Purchase Electricity from Innovative DOE-Supported Clean Utility to Purchase Electricity from Innovative DOE-Supported Clean Coal Project Utility to Purchase Electricity from Innovative DOE-Supported Clean Coal Project January 17, 2012 - 12:00pm Addthis Washington, DC - An innovative clean coal technology project in Texas will supply electricity to the largest municipally owned utility in the United States under a recently signed Power Purchase Agreement, the U.S. Department of Energy (DOE) announced today. Under the agreement - the first U.S. purchase by a utility of low-carbon power from a commercial-scale, coal-based power plant with carbon capture - CPS Energy of San Antonio will purchase approximately 200 megawatts (MW) of power from the Texas Clean Energy Project (TCEP), located just west of Midland-Odessa.

14

City of Palo Alto Utilities - Renewable Energy Credit Purchase...  

Open Energy Info (EERE)

commercial and industrial customers for the purchase of the SRECs associated with their solar installations. CPAU currently pays 50MWh for SRECs through 3 Degrees, Inc and...

15

Table A21. Quantity of Electricity Sold to Utility and Nonutility Purchasers  

U.S. Energy Information Administration (EIA) Indexed Site

1. Quantity of Electricity Sold to Utility and Nonutility Purchasers" 1. Quantity of Electricity Sold to Utility and Nonutility Purchasers" " by Census Region and Economic Characteristics of the Establishment, 1991" " (Estimates in Million Kilowatthours)" ,,,,"RSE" " "," ","Utility ","Nonutility","Row" "Economic Characteristics(a)","Total Sold","Purchaser(b)","Purchaser(c)","Factors" ,"Total United States",,, "RSE Column Factors:",1,1.1,1 "Value of Shipments and Receipts" "(million dollars)" " Under 20",188,122,66,35.6 " 20-49",2311,1901,410,39.5 " 50-99",2951,2721,230,9.6 " 100-249",6674,5699,974,7.1

16

Table A18. Quantity of Electricity Sold to Utility and Nonutility Purchasers  

U.S. Energy Information Administration (EIA) Indexed Site

8. Quantity of Electricity Sold to Utility and Nonutility Purchasers" 8. Quantity of Electricity Sold to Utility and Nonutility Purchasers" " by Census Region, Industry Group, and Selected Industries, 1991" " (Estimates in Million Kilowatthours)" " "," "," "," "," ","RSE" "SIC"," "," ","Utility ","Nonutility","Row" "Code(a)","Industry Groups and Industry","Total Sold","Purchaser(b)","Purchaser(c)","Factors" ,,"Total United States" ,"RSE Column Factors:",0.9,1,1 , 20,"Food and Kindred Products",988,940,48,16.2 2011," Meat Packing Plants",0,0,0,"NF"

17

Table A31. Quantity of Electricity Sold to Utility and Nonutility Purchasers  

U.S. Energy Information Administration (EIA) Indexed Site

Quantity of Electricity Sold to Utility and Nonutility Purchasers by Census Region," Quantity of Electricity Sold to Utility and Nonutility Purchasers by Census Region," " Census Division, and Economic Characteristics of the Establishment, 1994" " (Estimates in Million Kilowatthours)" ,,,,"RSE" " "," ","Utility ","Nonutility","Row" "Economic Characteristics(a)","Total Sold","Purchaser(b)","Purchaser(c)","Factors" ,"Total United States",,, "RSE Column Factors:",0.9,1.1,1 "Value of Shipments and Receipts" "(million dollars)" " Under 20",222,164," Q ",23.3 " 20-49",1131,937,194,17.2

18

Table 11.5 Electricity: Sales to Utility and Nonutility Purchasers, 2010;  

U.S. Energy Information Administration (EIA) Indexed Site

5 Electricity: Sales to Utility and Nonutility Purchasers, 2010; 5 Electricity: Sales to Utility and Nonutility Purchasers, 2010; Level: National and Regional Data; Row: NAICS Codes; Column: Utility and Nonutility Purchasers; Unit: Million Kilowatthours. Total of NAICS Sales and Utility Nonutility Code(a) Subsector and Industry Transfers Offsite Purchaser(b) Purchaser(c) Total United States 311 Food 347 168 179 3112 Grain and Oilseed Milling 142 6 136 311221 Wet Corn Milling 14 4 10 31131 Sugar Manufacturing 109 88 21 3114 Fruit and Vegetable Preserving and Specialty Foods 66 66 0 3115 Dairy Products 22 0 22 3116 Animal Slaughtering and Processing 0 0 0 312 Beverage and Tobacco Products 1 1 * 3121 Beverages 1 1 * 3122 Tobacco 0 0 0 313 Textile Mills

19

Level: National and Regional Data; Row: NAICS Codes; Column: Utility and Nonutility Purchasers;  

U.S. Energy Information Administration (EIA) Indexed Site

Next MECS will be conducted in 2010 Next MECS will be conducted in 2010 Table 11.5 Electricity: Sales to Utility and Nonutility Purchasers, 2006; Level: National and Regional Data; Row: NAICS Codes; Column: Utility and Nonutility Purchasers; Unit: Million Kilowatthours. Total of NAICS Sales and Utility Nonutility Code(a) Subsector and Industry Transfers Offsite Purchaser(b) Purchaser(c) Total United States 311 Food 111 86 25 3112 Grain and Oilseed Milling 72 51 21 311221 Wet Corn Milling 55 42 13 31131 Sugar Manufacturing 7 3 4 3114 Fruit and Vegetable Preserving and Specialty Foods 13 13 0 3115 Dairy Products 0 0 0 3116 Animal Slaughtering and Processing 0 0 0 312 Beverage and Tobacco Products * * 0 3121 Beverages

20

Refinery Capacity Report  

U.S. Energy Information Administration (EIA) Indexed Site

Refinery Capacity Report Refinery Capacity Report With Data as of January 1, 2013 | Release Date: June 21, 2013 | Next Release Date: June 20, 2014 Previous Issues Year: 2013 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 2002 2001 2000 1999 1997 1995 1994 Go Data series include fuel, electricity, and steam purchased for consumption at the refinery; refinery receipts of crude oil by method of transportation; and current and projected atmospheric crude oil distillation, downstream charge, and production capacities. Respondents are operators of all operating and idle petroleum refineries (including new refineries under construction) and refineries shut down during the previous year, located in the 50 States, the District of Columbia, Puerto Rico, the Virgin Islands, Guam, and other U.S. possessions.

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


21

Economic and legal aspects of utility consortiums for heliostat purchase  

DOE Green Energy (OSTI)

A preliminary exploration is given of the legal and economic considerations surrounding the formation and operation of some form of utility-sponsored collective buying arrangement for heliostats. Particular attention is focused on considerations of federal antitrust law surrounding collective buying and other joint operations by electric utilities. Attention is also given to considerations suggested by the economic theory of monopsony (markets with a single buyer) and oligopsony (markets with a small number of buyers). The advantages and disadvantages of such arrangements are examined from the viewpoints of the buyer and the seller. (LEW)

Cole, R.J.; Sommers, P.; Sheppard, W.J.; Nesse, R.J.

1982-07-01T23:59:59.000Z

22

Utility to Purchase Low-Carbon Power from Innovative Clean Coal Plant |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Utility to Purchase Low-Carbon Power from Innovative Clean Coal Utility to Purchase Low-Carbon Power from Innovative Clean Coal Plant Utility to Purchase Low-Carbon Power from Innovative Clean Coal Plant January 19, 2012 - 5:00pm Addthis Lawrence Livermore National Laboratory demonstrated coal gasification in large-scale field experiments at the Rocky Mountain Test Facility (above) near Hanna, Wyoming. Coal gasification and sequestration of the carbon dioxide produced are among the technologies being used in the Texas Clean Energy Project. | Photo courtesy of llnlphotos. Lawrence Livermore National Laboratory demonstrated coal gasification in large-scale field experiments at the Rocky Mountain Test Facility (above) near Hanna, Wyoming. Coal gasification and sequestration of the carbon

23

Table 11.6 Electricity: Sales to Utility and Nonutility Purchasers, 2010;  

U.S. Energy Information Administration (EIA) Indexed Site

6 Electricity: Sales to Utility and Nonutility Purchasers, 2010; 6 Electricity: Sales to Utility and Nonutility Purchasers, 2010; Level: National and Regional Data; Row: Values of Shipments and Employment Sizes; Column: Utility and Nonutility Purchasers; Unit: Million Kilowatthours. Total of Economic Sales and Utility Nonutility Characteristic(a) Transfers Offsite Purchaser(b) Purchaser(c) Total United States Value of Shipments and Receipts (million dollars) Under 20 194 100 93 20-49 282 280 3 50-99 1,115 922 194 100-249 5,225 4,288 936 250-499 5,595 2,696 2,899 500 and Over 20,770 12,507 8,263 Total 33,181 20,793 12,388 Employment Size Under 50 395 177 218 50-99 3,412 3,408 5 100-249 6,687 3,088 3,599 250-499 5,389 4,175 1,214 500-999 7,082 3,635 3,447

24

Feasibility study report for the Imperial Valley Ethanol Refinery: a 14. 9-million-gallon-per-year ethanol synfuel refinery utilizing geothermal energy  

DOE Green Energy (OSTI)

The construction and operation of a 14,980,000 gallon per year fuel ethanol from grain refinery in the Imperial Valley of California is proposed. The Imperial Valley Ethanol Refinery (refinery) will use hot geothermal fluid from geothermal resources at the East Mesa area as the source of process energy. In order to evaluate the economic viability of the proposed Project, exhaustive engineering, cost analysis, and financial studies have been undertaken. This report presents the results of feasibility studies undertaken in geothermal resource, engineering, marketing financing, management, environment, and permits and approvals. The conclusion of these studies is that the Project is economically viable. US Alcohol Fuels is proceeding with its plans to construct and operate the Refinery.

Not Available

1981-03-01T23:59:59.000Z

25

Financial impacts of nonutility power purchases on investor-owned electric utilities  

SciTech Connect

To assist in its these responsibilities in the area of electric power, EIA has prepared this report, Financial Impacts of Nonutility Power Purchases on Investor-Owned Electric Utilities. The primary purpose of this report is to provide an overview of the issues surrounding the financial impacts of nonutility generation contracts (since the passage of the Public Utility Regulatory Policies Act of 1978) on investor-owned utilities. The existing concern in this area is manifest in the provisions of Section 712 of the Energy Policy Act of 1992, which required State regulatory commissions to evaluate various aspects of long-term power purchase contracts, including their impact on investor-owned utilities` cost of capital and rates charged to customers. The EIA does not take positions on policy questions. The EIA`s responsibility is to provide timely, high quality information and to perform objective, credible analyses in support of the deliberations by both public and private decision-makers. Accordingly, this report does not purport to represent the policy positions of the US Department of Energy or the Administration.

Not Available

1994-06-01T23:59:59.000Z

26

Rocky Mountains (PADD 4) Gross Inputs to Refineries (Thousand ...  

U.S. Energy Information Administration (EIA)

Gross Input to Atmospheric Crude Oil Distillation Units ; PAD District 4 Refinery Utilization and Capacity ...

27

Refinery Operable Utilization Rate  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Totals may not equal sum ...

28

Regional Purchasing  

NLE Websites -- All DOE Office Websites (Extended Search)

Regional Purchasing Regional Purchasing Regional Purchasing Pursuant to Appendix M of Prime Contract No. DE-AC52-06NA25396 between DOE/NNSA and Los Alamos National Security, LLC (LANS), LANS is committed to building a strong supplier base with Northern New Mexico businesses and the local Native American pueblos in the purchases of goods and services. Contact Small Business Office (505) 667-4419 Email We seek out and utilize known Northern New Mexico business as suppliers The Northern New Mexico counties included are Los Alamos Santa Fe Rio Arriba Taos Mora San Miguel Sandoval The eight regional pueblos included are Nambe Ohkay Owingeh (formerly known as San Juan) Picuris Pojoaque San Ildefonso Santa Clara Taos Tesuque When the Laboratory cannot identify regional firms, it will expand its

29

Financial Impacts of Nonutility Power Purchases on Investor-Owned Electric Utilities  

Reports and Publications (EIA)

This report provides an overview of the issues surrounding the financial impacts of nonutility generation contracts (since the passage of the Public Utility Regulatory Policies Act of 1978) on investor-owned utilities.

Information Center

1994-06-15T23:59:59.000Z

30

Power Purchase Agreements Update  

Energy.gov (U.S. Department of Energy (DOE))

Presentation covers an update on power purchase agreements and is given at the Spring 2011 Federal Utility Partnership Working Group (FUPWG) meeting.

31

Refinery Capacity Report  

U.S. Energy Information Administration (EIA)

Explanatory Notes Survey Methodology Description of Survey Form The Form EIA-820, “Annual Refinery Report,” is the primary source of data in the “Refinery ...

32

Uranium purchases report 1994  

SciTech Connect

US utilities are required to report to the Secretary of Energy annually the country of origin and the seller of any uranium or enriched uranium purchased or imported into the US, as well as the country of origin and seller of any enrichment services purchased by the utility. This report compiles these data and also contains a glossary of terms and additional purchase information covering average price and contract duration. 3 tabs.

1995-07-01T23:59:59.000Z

33

Refinery burner simulation design architecture summary.  

SciTech Connect

This report describes the architectural design for a high fidelity simulation of a refinery and refinery burner, including demonstrations of impacts to the refinery if errors occur during the refinery process. The refinery burner model and simulation are a part of the capabilities within the Sandia National Laboratories Virtual Control System Environment (VCSE). Three components comprise the simulation: HMIs developed with commercial SCADA software, a PLC controller, and visualization software. All of these components run on different machines. This design, documented after the simulation development, incorporates aspects not traditionally seen in an architectural design, but that were utilized in this particular demonstration development. Key to the success of this model development and presented in this report are the concepts of the multiple aspects of model design and development that must be considered to capture the necessary model representation fidelity of the physical systems.

Pollock, Guylaine M.; McDonald, Michael James; Halbgewachs, Ronald D.

2011-10-01T23:59:59.000Z

34

Firing Excess Refinery Butane in Peaking Gas Turbines  

E-Print Network (OSTI)

New environmentally-driven regulations for motor gasoline volatility will significantly alter refinery light ends supply/demand balancing. This, in turn, will impact refinery economics. This paper presumes that one outcome will be excess refinery normal butane production, which will reduce refinery normal butane value and price. Explored is an opportunity for a new use for excess refinery normal butane- as a fuel for utility peaking gas turbines which currently fire kerosene and #2 oil. Our paper identifies the fundamental driving forces which are changing refinery butane economics, examines how these forces influence refinery production, and evaluates the potential for using normal butanes as peaking utility gas turbine fuel, especially on the US East Coast.

Pavone, A.; Schreiber, H.; Zwillenberg, M.

1989-09-01T23:59:59.000Z

35

Power Purchase Agreements  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Power Purchase Agreements Power Purchase Agreements Chandra Shah, NREL 303-384-7557 chandra.shah@nrel.gov February 2011 revised 2 | Federal Energy Management Program eere.energy.gov Overview * Customer-sited power purchase agreement (PPA) definition * Project process * Project examples * Utility Renewable Energy Services Contract (URESC) * Enhanced use lease (EUL) * PPA support, resources and key points 3 | Federal Energy Management Program eere.energy.gov * Private entity purchases, installs, owns, operates and maintains customer-sited renewable equipment * Site purchases electricity through power purchase agreement (PPA) * Pros - Renewable developer (or partner) eligible for tax incentives, accelerated depreciation - No agency up-front capital required - Renewable developer provides O&M - Minimal risk to government

36

Encon Motivation in European Refineries  

E-Print Network (OSTI)

One essential element in a successful energy conservation or Encon program is effective motivation of employees and organizations to conserve energy. Encon motivation in our European refineries is a continuing effort that requires utilization of various techniques and approaches, dependent on the local environment and effectiveness of the Encon program. In this paper, we begin with the importance for stimulating personnel, note the essential ingredients required to motivate our people, and briefly review several techniques used for Encon motivation. Two examples of Encon motivation programs are presented before introducing the characteristics of a successful Encon motivation program. The paper concludes with a review of the needs and suggestions for maintaining a continuing program. Energy utilization efficiency in Esso Europe's refineries improved about 16% in the mid 70's, due primarily to Encon motivation. Experience has since demonstrated that additional improvements can be achieved through operational and maintenance practices.

Gambera, S.; Lockett, W., Jr.

1982-01-01T23:59:59.000Z

37

Tables - Refinery Capacity Report  

U.S. Energy Information Administration (EIA)

Tables: 1: Number and Capacity of Operable Petroleum Refineries by PAD District and State as of January 1, 2009: PDF: 2: Production Capacity of Operable ...

38

Power Purchase Agreements  

NLE Websites -- All DOE Office Websites (Extended Search)

Text Text eere.energy.gov Power Purchase Agreements Chandra Shah, NREL 303-384-7557 chandra.shah@nrel.gov February 2011 revised 2 | Federal Energy Management Program eere.energy.gov Overview * Customer-sited power purchase agreement (PPA) definition * Project process * Project examples * Utility Renewable Energy Services Contract (URESC) * Enhanced use lease (EUL) * PPA support, resources and key points 3 | Federal Energy Management Program eere.energy.gov * Private entity purchases, installs, owns, operates and maintains customer-sited renewable equipment * Site purchases electricity through power purchase agreement (PPA) * Pros - Renewable developer (or partner) eligible for tax incentives, accelerated depreciation - No agency up-front capital required - Renewable developer provides O&M

39

Table 9. Refinery Receipts of Crude Oil by Method of ...  

U.S. Energy Information Administration (EIA)

Refinery Receipts of Crude Oil by Method of ... "Annual Refinery Report." 49 Energy Information Administration, Refinery Capacity 2011. Title: Refinery ...

40

Oklahoma, Kansas, Missouri Refinery District API Gravity ...  

U.S. Energy Information Administration (EIA)

Oklahoma, Kansas, Missouri Refinery District API Gravity (Weighted Average) of Crude Oil Input to Refineries (Degree)

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


41

Refinery Yield of Liquefied Refinery Gases  

U.S. Energy Information Administration (EIA) Indexed Site

Refinery Yield Refinery Yield (Percent) Product: Liquefied Refinery Gases Finished Motor Gasoline Finished Aviation Gasoline Kerosene-Type Jet Fuel Kerosene Distillate Fuel Oil Residual Fuel Oil Naphtha for Petrochemical Feedstock Use Other Oils for Petrochemical Feedstock Use Special Naphthas Lubricants Waxes Petroleum Coke Asphalt and Road Oil Still Gas Miscellaneous Products Processing Gain(-) or Loss(+) Period: Monthly Annual Download Series History Download Series History Definitions, Sources & Notes Definitions, Sources & Notes Show Data By: Product Area Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 View History U.S. 5.3 5.4 5.2 5.2 5.1 3.9 1993-2013 PADD 1 4.4 5.1 4.9 4.9 4.6 2.1 1993-2013 East Coast 4.4 5.3 5.1 5.1 4.9 2.2 1993-2013

42

Retrofitting analysis of integrated bio-refineries  

E-Print Network (OSTI)

A bio-refinery is a processing facility that produces liquid transportation fuels and/or value-added chemicals and other products. Because of the dwindling resources and escalating prices of fossil fuels, there are emerging situations in which the economic performance of fossil-based facilities can be enhanced by retrofitting and incorporation of bio-mass feedstocks. These systems can be regarded as bio-refineries or integrated fossilbio- refineries. This work presents a retrofitting analysis to integrated bio-refineries. Focus is given to the problem of process modification to an existing plant by considering capacity expansion and material substitution with biomass feedstocks. Process integration studies were conducted to determine cost-effective strategies for enhancing production and for incorporating biomass into the process. Energy and mass integration approaches were used to induce synergism and to reduce cost by exchanging heat, material utilities, and by sharing equipment. Cost-benefit analysis was used to guide the decision-making process and to compare various production routes. Ethanol production from two routes was used as a case study to illustrate the applicability of the proposed approach and the results were bio-refinery has become more attractive then fossil-refinery.

Cormier, Benjamin R.

2005-12-01T23:59:59.000Z

43

Kyrgyzstan starts up its first refinery  

Science Conference Proceedings (OSTI)

The Central Asian republic of Kyrgyzstan started up its first oil refinery in October 1996. The 10,000 b/d plant is designed to produce gasoline, diesel, and mazut (heavy fuel oil) from local Kyrgyz crude. Before construction of the Jalalabad refinery, all finished petroleum products were imported from neighboring countries. Kyrgyzstan`s demand for finished products is about 40,000 b/d. The new refinery was designed and constructed by Petrofac of Tyler, Texas, on behalf of Kyrgoil Corp., Calgary. Kyrgoil is a partner with the Kyrgyz state oil company, Kyrgyzsneft, in a venture called Kyrzgyz Petroleum Co. (KPC). KPC has undertaken restoration and continued development of the oil fields in Kyrgyzstan`s Fergana basin, in addition to the refinery project. The company also has marketing rights for finished products within Kyrgyzstan. The refinery comprises: a hydroskimming (atmospheric distillation) section, diesel steam stripping, gasoline blending, and utilities and off-sites, including steam generation, power generation, tank farm, truck and rail tank-car loading and unloading facilities, crude inlet pipeline, high-voltage power line, substation, air compression, laboratory, and maintenance facilities.

McLeod, G. [Petrofac LLC, Tyler, TX (United States)

1997-05-05T23:59:59.000Z

44

Status of Texas refineries, 1982  

Science Conference Proceedings (OSTI)

This report is a survey of current operations of the Texas refineries during the 1979-82 market slump using publicly available data from the US Department of Energy and the Texas Railroad Commission. The report looks at the small inland refineries, the large inland refineries, the small coastal refineries, the large coastal refineries in Texas, and the Louisiana coastal refineries. The report suggests that about 200 mb/d of inland capacity and 1.3 million b/d of coastal capacity has been permanently idled.

Langston, V.C.

1983-03-01T23:59:59.000Z

45

Texas Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

Atmospheric Crude Oil Distillation Capacity : Operable ... Idle refineries represent refineries where distillation units were completely idle but not ...

46

Colorado Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

Atmospheric Crude Oil Distillation Capacity : Operable ... Idle refineries represent refineries where distillation units were completely idle but not ...

47

Refinery Capacity Report  

U.S. Energy Information Administration (EIA) Indexed Site

Refinery Capacity Report Refinery Capacity Report June 2013 With Data as of January 1, 2013 Independent Statistics & Analysis www.eia.gov U.S. Department of Energy Washington, DC 20585 This report was prepared by the U.S. Energy Information Administration (EIA), the statistical and analytical agency within the U.S. Department of Energy. By law, EIA's data, analyses, and forecasts are independent of approval by any other officer or employee of the United States Government. The views in this report therefore should not be construed as representing those of the Department of Energy or other Federal agencies. Table 1. Number and Capacity of Operable Petroleum Refineries by PAD District and State as of January 1, 2013

48

Optimization of refinery hydrogen network  

Science Conference Proceedings (OSTI)

Tighter environmental regulations and more heavy-end upgrading in the petroleum industry lead to increased demand for hydrogen in oil refineries. In this paper, the method proposed to optimize the refinery hydrogen network is based upon mathematical ... Keywords: hydrogen management, optimization, refinery, superstructure

Yunqiang Jiao; Hongye Su

2010-09-01T23:59:59.000Z

49

Flare-gas recovery success at Canadian refineries  

SciTech Connect

It appears that some North American refining companies still cling to an old philosophy that flare gas recovery systems are unsafe, unreliable, uneconomic, or unnecessary. Shell Canada's recent experience with two modern systems has proven otherwise. Two of Shell Canada's refineries, at Sarnia, Ont., and Montreal East, Que., have now logged about 6 years' total operating experience with modern flare gas recovery units. The compression facilities in each utilize a two-stage reciprocating machine, one liquid seal drum per flare stack, and an automated load control strategy. The purpose was to recover the normal continuous flow of refinery flare gas for treatment and use in the refinery fuel gas system.

Allen, G.D.; Chan, H.H.; Wey, R.E.

1983-06-01T23:59:59.000Z

50

Green Purchasing & Green Technology  

NLE Websites -- All DOE Office Websites (Extended Search)

Purchasing & Technology Goals 6 & 7: Green Purchasing & Green Technology Our goal is to purchase and use environmentally sustainable products whenever possible and to implement...

51

High Performance Windows Volume Purchase: Information Resources  

NLE Websites -- All DOE Office Websites (Extended Search)

Information Information Resources to someone by E-mail Share High Performance Windows Volume Purchase: Information Resources on Facebook Tweet about High Performance Windows Volume Purchase: Information Resources on Twitter Bookmark High Performance Windows Volume Purchase: Information Resources on Google Bookmark High Performance Windows Volume Purchase: Information Resources on Delicious Rank High Performance Windows Volume Purchase: Information Resources on Digg Find More places to share High Performance Windows Volume Purchase: Information Resources on AddThis.com... Home About For Builders For Residential Buyers For Light Commercial Buyers For Manufacturers For Utilities Information Resources Information Resources Numerous publications will be available to help educate buyers, product

52

Opportunities for Biorenewables in Oil Refineries  

Science Conference Proceedings (OSTI)

Abstract: The purpose of this study was to evaluate the potential for using biorenewable feedstocks in oil refineries. Economic analyses were conducted, with support from process modeling and proof of principle experiments, to assess a variety of potential processes and configurations. The study considered two primary alternatives: the production of biodiesel and green diesel from vegetable oils and greases and opportunities for utilization of pyrolysis oil. The study identified a number of promising opportunities for biorenewables in existing or new refining operations.

Marker, T.L.

2005-12-19T23:59:59.000Z

53

Refinery Capacity Report  

U.S. Energy Information Administration (EIA) Indexed Site

1 1 Idle Operating Total Stream Day Barrels per Idle Operating Total Calendar Day Barrels per Atmospheric Crude Oil Distillation Capacity Idle Operating Total Operable Refineries Number of State and PAD District a b b 14 10 4 1,617,500 1,205,000 412,500 1,708,500 1,273,500 435,000 ............................................................................................................................................... PAD District I 1 0 1 182,200 0 182,200 190,200 0 190,200 ................................................................................................................................................................................................................................................................................................ Delaware......................................

54

Power Purchase Agreements Update  

NLE Websites -- All DOE Office Websites (Extended Search)

FEDERAL ENERGY MANAGEMENT PROGRAM FEDERAL ENERGY MANAGEMENT PROGRAM femp.energy.gov Federal Utility Partnership Working Group Meeting April 20-21 in Portland, Oregon Power Purchase Agreement Update April 21, 2011 Chandra Shah chandra.shah@nrel.gov 2 | FEDERAL ENERGY MANAGEMENT PROGRAM femp.energy.gov Overview * Power Purchase Agreement (PPA) Template * PPA Request For Information (RFI) 3 | FEDERAL ENERGY MANAGEMENT PROGRAM femp.energy.gov PPA Template * DLA Energy has an updated PPA template - Includes Best Value evaluation (rather than Low Price/Technically Acceptable) - Additional updates will be made based on the PPA RFI - Updated template will be posted on FEMP PPA Sample Document web site http://www1.eere.energy.gov/femp/financing/ppa_sampledocs.html 4 | FEDERAL ENERGY MANAGEMENT PROGRAM femp.energy.gov

55

Texas Gulf Coast Refinery District API Gravity (Weighted ...  

U.S. Energy Information Administration (EIA)

Texas Gulf Coast Refinery District API Gravity (Weighted Average) of Crude Oil Input to Refineries (Degree)

56

Texas Gulf Coast Refinery District API Gravity (Weighted Average ...  

U.S. Energy Information Administration (EIA)

Texas Gulf Coast Refinery District API Gravity (Weighted Average) of Crude Oil Input to Refineries (Degree)

57

Appalachian No. 1 Refinery District Sulfur Content (Weighted ...  

U.S. Energy Information Administration (EIA)

Appalachian No. 1 Refinery District Sulfur Content (Weighted Average) of Crude Oil Input to Refineries (Percent)

58

EIA-820 ANNUAL REFINERY REPORT INSTRUCTIONS  

U.S. Energy Information Administration (EIA)

EIA-820, Annual Refinery Report Page 1 U.S. DEPARTMENT OF ENERGY ... production outside the refinery gate. Note: capacity should include base stocks and process oils

59

Indiana Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

Notes: Idle refineries represent refineries where distillation units were completely idle but not permanently shutdown as of January 1 of the year.

60

Number of Idle Refineries - Energy Information Administration  

U.S. Energy Information Administration (EIA)

Notes: Idle refineries represent refineries where distillation units were completely idle but not permanently shutdown as of January 1 of the year.

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


61

California Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

Notes: Idle refineries represent refineries where distillation units were completely idle but not permanently shutdown as of January 1 of the year.

62

Refinery, petrochemical plant injuries decline  

Science Conference Proceedings (OSTI)

The National Petroleum Refiners Association (NPRA) reports a 7% reduction in workplace injury and illness incidence rates for refineries in 1993, and a 21% decrease for petrochemical plants. The report summarizes data from 135 of the 162 US member refineries, and 117 of the 172 US member petrochemical plants. This paper summarizes the report findings.

Not Available

1994-07-25T23:59:59.000Z

63

High Performance Windows Volume Purchase: Contacts  

NLE Websites -- All DOE Office Websites (Extended Search)

Contacts to Contacts to someone by E-mail Share High Performance Windows Volume Purchase: Contacts on Facebook Tweet about High Performance Windows Volume Purchase: Contacts on Twitter Bookmark High Performance Windows Volume Purchase: Contacts on Google Bookmark High Performance Windows Volume Purchase: Contacts on Delicious Rank High Performance Windows Volume Purchase: Contacts on Digg Find More places to share High Performance Windows Volume Purchase: Contacts on AddThis.com... Home About For Builders For Residential Buyers For Light Commercial Buyers For Manufacturers For Utilities Information Resources Contacts Web site and High Performance Windows Volume Purchase Program contacts are provided below. Website Contact Send us your comments, report problems, and/or ask questions about

64

Puerto Rico Refinery Catalytic Reforming Downstream Charge ...  

U.S. Energy Information Administration (EIA)

Puerto Rico Refinery Catalytic Reforming Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

65

Puerto Rico Refinery Desulfurization, Gasoline Downstream Charge ...  

U.S. Energy Information Administration (EIA)

Puerto Rico Refinery Desulfurization, Gasoline Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

66

Mississippi Refinery Catalytic Reforming Downstream Charge ...  

U.S. Energy Information Administration (EIA)

Mississippi Refinery Catalytic Reforming Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

67

Louisiana Refinery Catalytic Reforming Downstream Charge Capacity ...  

U.S. Energy Information Administration (EIA)

Louisiana Refinery Catalytic Reforming Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

68

Oklahoma Refinery Vacuum Distillation Downstream Charge Capacity ...  

U.S. Energy Information Administration (EIA)

Oklahoma Refinery Vacuum Distillation Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

69

Mississippi Refinery Vacuum Distillation Downstream Charge ...  

U.S. Energy Information Administration (EIA)

Mississippi Refinery Vacuum Distillation Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

70

Georgia Refinery Marketable Petroleum Coke Production Capacity ...  

U.S. Energy Information Administration (EIA)

Georgia Refinery Marketable Petroleum Coke Production Capacity as of January 1 (Barrels per Stream Day)

71

Minnesota Refinery Marketable Petroleum Coke Production ...  

U.S. Energy Information Administration (EIA)

Minnesota Refinery Marketable Petroleum Coke Production Capacity as of January 1 (Barrels per Stream Day)

72

Texas Gulf Coast Refinery Utilization and Capacity  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Totals may not equal sum ...

73

Texas Inland Refinery Utilization and Capacity  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Totals may not equal sum ...

74

Midwest (PADD 2) Refinery Utilization and Capacity  

U.S. Energy Information Administration (EIA)

Process: Area: 2007 2008 2009 2010 2011 2012 View History; Gross Input to Atmospheric Crude Oil Distillation Units: 3,238: 3,244: 3,153: 3,305: 3,395: 3,425: 1985-2012:

75

U.S. Refinery Utilization and Capacity  

U.S. Energy Information Administration (EIA) Indexed Site

2007 2008 2009 2010 2011 2012 View History Gross Input to Atmospheric Crude Oil Distillation Units 15,450 15,027 14,659 15,177 15,289 15,362 1985-2012 Operable Capacity (Calendar...

76

PAD District 5 Refinery Utilization and Capacity  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Totals may not equal sum ...

77

New Mexico Refinery Utilization and Capacity  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Totals may not equal sum ...

78

Midwest (PADD 2) Refinery Utilization and Capacity  

U.S. Energy Information Administration (EIA)

Gross Input to Atmospheric Crude Oil Distillation Units: 3,318: 3,217: 3,151: 3,087: 3,336: 3,572: 1985-2013: Operable Capacity (Calendar Day) 3,769: 3,769: 3,769 ...

79

PAD District 4 Refinery Utilization and Capacity  

U.S. Energy Information Administration (EIA)

Gross Input to Atmospheric Crude Oil Distillation Units: 575: 577: 562: 542: 578: 587: 1985-2013: Operable Capacity (Calendar Day) 625: 625: 630: 630: 630: 630: 1985 ...

80

Power Purchase Agreements  

Energy.gov (U.S. Department of Energy (DOE))

Presentation covers the power purchase agreements taken from the FEMP Alternative Finance Options (AFO) webinar.

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


81

Upgrade Your Refinery for Energy Conservation  

E-Print Network (OSTI)

Upgrading existing refineries for efficient energy utilization imposes strict restraints upon design engineers. Present and future production requirements must be defined. Reliable operating data must be obtained from historical records and test runs to accurately define actual performance of each piece of equipment. A complete simulation model of the facility is developed and tested. Future operations are evaluated using the model to define heat and material balance requirements for all projected operations. Energy conservation projects are evaluated with the model to define energy savings over the life of each project. A discounted cash flow analysis is formulated and an optimum set of projects yielding maximum rates of return are selected for implementation.

Johnnie, D. H., Jr.; Klooster, H. J.

1983-01-01T23:59:59.000Z

82

Pemex to acquire interest in Shell Texas refinery  

Science Conference Proceedings (OSTI)

This paper reports that Petroleos Mexicanos and Shell Oil Co. have signed a memorandum of understanding to form a joint refining venture involving Shell's 225,000 b/d Deer Park, Tex., refinery. Under the agreement, Mexico's state owned oil company is to purchase a 50% interest in the refinery, and Shell is to sell Pemex unleaded gasoline on a long term basis. Under the venture, Shell and Pemex plan to add undisclosed conversion and upgrading units tailored to process heavy Mexican crude. The revamp will allow Pemex to place more than 100,000 b/d of Mayan heavy crude on the U.S. market. Mayan accounts for 70% of Mexico's crude oil exports. In turn, Shell will sell Pemex as much as 45,000 b/d of unleaded gasoline to help meet Mexico's rapidly growing demand.

Not Available

1992-08-31T23:59:59.000Z

83

Biological treatment of refinery wastes  

SciTech Connect

A detailed study of the treatment situation at a Thai refinery that used an API separator with no equalization tank, followed by an activated-sludge system, showed that only 42% of the total COD and 57% of the soluble COD was degradable. In a study of the possibility of additional treatments, an aerated lagoon showed promising results. The wastewater composition of the three main Thai refineries was surveyed.

Mahmud, Z.; Thanh, N.C.

1978-01-01T23:59:59.000Z

84

Green Power Purchasing | Open Energy Information  

Open Energy Info (EERE)

Purchasing Purchasing Jump to: navigation, search Government entities, businesses, residents, schools, non-profits and others can play a significant role in supporting renewable energy by buying electricity from renewable resources, or by buying renewable energy credits (RECs). Many state and local governments, as well as the federal government, have committed to buying green power to account for a certain percentage of their electricity consumption. Green power purchases are typically executed through contracts with green power marketers or project developers, through utility green power programs, or through community aggregation. [1] Green Power Purchasing Incentives CSV (rows 1 - 77) Incentive Incentive Type Place Applicable Sector Eligible Technologies Active

85

Obstacles and Opportunity: Turbine Motorization in Refineries Today  

E-Print Network (OSTI)

Steam turbines have been widely used in oil refineries for driving pumps, compressors and other rotary machines. However, in recent years, the authors of this paper have seen substantial turbine motorization projects completed or being planned in the refineries. This paper discusses the key aspects that should be considered in evaluating the feasibility of motorization projects. Based on the literature review and a refinery survey conducted by the authors, the key factors include the critical level of the related equipment, the potential energy savings and capital cost, the steam and power balance in the related area, and the reliability in the refinery's power supply. Based on the authors' experience, the utilities' energy efficiency incentive programs in California also influence the decision-making process for turbine motorization projects. Therefore, this paper includes a description of the utilities' guidelines for fuel substitution projects. In particular, the utilities' three-prong requirements on net source-BTU energy savings, cost effectiveness, and avoidance of adverse impacts to the environment are discussed. Two real life case studies are presented to demonstrate how the above criteria should be applied for determining if a motorization opportunity is economically viable. A discussion on suggested features is also included for prescreening turbine motorization project candidates for better energy and environment economics such as venting of exhaust steam from a back pressure turbine and oversized design of the existing turbine and pump.

Feng, Hua; Liu, Jinghing; Liu, Xiang; Ahmad, Mushtaq; Deng, Alan

2012-01-01T23:59:59.000Z

86

New Jersey Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

Atmospheric Crude Oil Distillation Capacity : Operable ... Idle refineries represent refineries where distillation units were completely idle but not ...

87

Production of coal-based fuels and value-added products: coal to liquids using petroleum refinery streams  

SciTech Connect

We are studying several processes that utilize coal, coal-derived materials, or biomass in existing refining facilities. A major emphasis is the production of a coal-based replacement for JP-8 jet fuel. This fuel is very similar to Jet A and jet A-1 in commercial variation, so this work has significant carry-over into the private sector. We have been focusing on three processes that would be retrofitted into a refinery: (1) coal tar/refinery stream blending and hydro-treatment; (2) coal extraction using refinery streams followed by hydro-treatment; and (3) co-coking of coal blended with refinery streams. 4 figs., 5 tabs.

Clifford, C.E.B.; Schobert, H.H. [Pennsylvania State University, PA (United States)

2008-07-01T23:59:59.000Z

88

Motiva Refinery | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Refinery Refinery Motiva Refinery May 18, 2006 - 10:45am Addthis Remarks Prepared for Energy Secretary Bodman Much of my time lately has been devoted to explaining why the price of gasoline has risen so sharply. President Bush understands the pinch this is creating for American consumers and has come forward with a variety of steps to address the problem. Rapid economic growth in emerging economies like China and India-and the growth here in the U.S.-have pushed up demand. Political unrest in some oil-producing regions has tightened supply. The transition from winter gasoline to summer blends, and the phase out of the additive MTBE in favor of ethanol, have increased the pressure on the market. Most significantly, we have very little spare refining capacity in this

89

Refinery suppliers face tough times  

SciTech Connect

Despite a handful of bright spots in hydroprocessing and petrochemical sectors, economic woes plague much of the refinery and petrochemical catalysts business, as suppliers are feeling the impact of mature markets and refiners` ongoing cost cutting. Industry experts say the doldrums could spur further restructuring in the catalyst business, with suppliers scrambling for market share and jockeying for position in growing sectors. Expect further consolidation over the next several years, says Pierre Bonnifay, president of IFP Enterprises (New York). {open_quotes}There are still too many players for the mature [refinery catalyst] markets.{close_quotes} Others agree. {open_quotes}Only about seven [or] eight major suppliers will survive,{close_quotes} says Robert Allsmiller, v.p./refinery and petrochemical catalysts at United Catalysts Inc. (UCI; Louisville, KY). {open_quotes}Who they [will be] is still up in the air.{close_quotes}

Rotman, D.; Walsh, K.

1997-03-12T23:59:59.000Z

90

Refinery Capacity Report - Energy Information Administration  

U.S. Energy Information Administration (EIA)

Respondents are operators of all operating and idle petroleum refineries ... Sources & Uses Petroleum Coal Natural Gas Renewable Nuclear Electricity Consumption

91

Louisiana Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

92

Delaware Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

93

Washington Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

94

Ohio Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

95

Mississippi Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

96

Utah Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

97

Number of Operating Refineries - Energy Information Administration  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

98

Montana Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

99

Oklahoma Refinery Catalytic Hydrotreating, Heavy Gas Oil ...  

U.S. Energy Information Administration (EIA)

Cat. Hydro. Heavy Gas Oil Downstream Charge Capacity (B/SD)y ; Oklahoma Downstream Charge Capacity of Operable Petroleum Refineries ...

100

Alaska Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


101

Florida Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

102

Mississippi Refinery Catalytic Hydrotreating, Heavy Gas Oil ...  

U.S. Energy Information Administration (EIA)

Cat. Hydro. Heavy Gas Oil Downstream Charge Capacity (B/SD)y ; Mississippi Downstream Charge Capacity of Operable Petroleum Refineries ...

103

Nebraska Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

104

North Carolina Refinery Operable Atmospheric Crude Oil ...  

U.S. Energy Information Administration (EIA)

North Carolina Refinery Operable Atmospheric Crude Oil Distillation Capacity as of January 1 (Barrels per Calendar Day)

105

Michigan Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

106

Reformulated Gasoline Foreign Refinery Rules  

Gasoline and Diesel Fuel Update (EIA)

Reformulated Gasoline Reformulated Gasoline Foreign Refinery Rules Contents * Introduction o Table 1. History of Foreign Refiner Regulations * Foreign Refinery Baseline * Monitoring Imported Conventional Gasoline * Endnotes Related EIA Short-Term Forecast Analysis Products * Areas Participating in the Reformulated Gasoline Program * Environmental Regulations and Changes in Petroleum Refining Operations * Oxygenate Supply/Demand Balances in the Short-Term Integrated Forecasting Model * Refiners Switch to Reformulated Gasoline Complex Model * Demand, Supply, and Price Outlook for Reformulated Motor Gasoline, 1995 Introduction On August 27, 1997, the EPA promulgated revised the rules that allow foreign refiners to establish and use individual baselines, but it would not be mandatory (the optional use of an

107

Kansas refinery starts up coke gasification unit  

SciTech Connect

Texaco Refining and Marketing Inc. has started up a gasification unit at its El Dorado, Kan., refinery. The unit gasifies delayed coke and other refinery waste products. This is the first refinery to install a coke-fueled gasification unit for power generation. Start-up of the $80-million gasification-based power plant was completed in mid-June. The gasifier produces syngas which, along with natural gas, fuels a combustion turbine. The turbine produces virtually 100% of the refinery`s electricity needs and enough heat to generate 40% of its steam requirements.

Rhodes, A.K.

1996-08-05T23:59:59.000Z

108

Refinery and Blender Net Inputs  

Annual Energy Outlook 2012 (EIA)

Refinery and Blender Net Inputs Crude OIl ... 14.54 15.14 15.26 15.08 14.51 15.30 15.70 14.93 14.47 15.30 15.54 14.97 15.01...

109

Purchasing Renewable Power | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Technologies » Renewable Energy » Purchasing Renewable Power Technologies » Renewable Energy » Purchasing Renewable Power Purchasing Renewable Power October 7, 2013 - 9:43am Addthis Federal agencies can purchase renewable power or renewable energy certificates (RECs) from a utility or other organization to meet Federal renewable energy requirements. Renewable power and RECs are good choices for facilities where on-site projects may be difficult or capital budgets are limited. There are three methods for purchasing renewable power that's not generated on a Federal site: Renewable Energy Certificates: Also known as renewable energy credits, green certificates, green tags, or tradable renewable certificates, RECs represent the environmental attributes of the power produced from renewable energy projects and are sold separately from commodity electricity. RECs

110

Uranium Purchases Report  

Reports and Publications (EIA)

Final issue. This report details natural and enriched uranium purchases as reported by owners and operators of commercial nuclear power plants. 1996 represents the most recent publication year.

Douglas Bonnar

1996-06-01T23:59:59.000Z

111

Uranium Purchases Report 1995  

U.S. Energy Information Administration (EIA)

DOE/EIA–0570(95) Distribution Category UC–950 Uranium Purchases Report 1995 June 1996 Energy Information Administration Office of Coal, Nuclear, ...

112

Application of Pinch Technology in Refinery Retrofits  

E-Print Network (OSTI)

This paper reviews the application of pinch technology in the identification of the most attractive retrofit prospects in typical refineries. In the first part of the paper, methodology is described to identify attractive inter-unit heat integration opportunities as well as attractive process-utility system integration (co-generation). An example of an atmospheric pipestill-alkylation unit integration evaluation is given using both composite stream and Grand composite stream methods. In the second part of the paper, the application of pinch technology in a typical intra-unit heat integration problem is given. It is explained how inefficiencies in an APS crude preheat train are identified, and a typical small retrofit project is described.

Thomas, W. R.; Siegell, J. H.; Sideropoulos, T.; Robertson, J. L.; Papoulias, S. A.

1987-09-01T23:59:59.000Z

113

High Performance Windows Volume Purchase: The Windows Volume Purchase RFP  

NLE Websites -- All DOE Office Websites (Extended Search)

The Windows The Windows Volume Purchase RFP to someone by E-mail Share High Performance Windows Volume Purchase: The Windows Volume Purchase RFP on Facebook Tweet about High Performance Windows Volume Purchase: The Windows Volume Purchase RFP on Twitter Bookmark High Performance Windows Volume Purchase: The Windows Volume Purchase RFP on Google Bookmark High Performance Windows Volume Purchase: The Windows Volume Purchase RFP on Delicious Rank High Performance Windows Volume Purchase: The Windows Volume Purchase RFP on Digg Find More places to share High Performance Windows Volume Purchase: The Windows Volume Purchase RFP on AddThis.com... Home About FAQs Low-E Storm Windows Request for Proposal Contacts For Builders For Residential Buyers For Light Commercial Buyers For Manufacturers

114

Federal Energy Management Program: On-Site Renewable Power Purchase  

NLE Websites -- All DOE Office Websites (Extended Search)

On-Site Renewable On-Site Renewable Power Purchase Agreements to someone by E-mail Share Federal Energy Management Program: On-Site Renewable Power Purchase Agreements on Facebook Tweet about Federal Energy Management Program: On-Site Renewable Power Purchase Agreements on Twitter Bookmark Federal Energy Management Program: On-Site Renewable Power Purchase Agreements on Google Bookmark Federal Energy Management Program: On-Site Renewable Power Purchase Agreements on Delicious Rank Federal Energy Management Program: On-Site Renewable Power Purchase Agreements on Digg Find More places to share Federal Energy Management Program: On-Site Renewable Power Purchase Agreements on AddThis.com... Energy Savings Performance Contracts ENABLE Utility Energy Service Contracts On-Site Renewable Power Purchase Agreements

115

Natural Gas Purchasing Options  

E-Print Network (OSTI)

As a result of economic and regulatory changes, the natural gas marketplace now offers multiple options for purchasers. The purpose of this panel is to discuss short-term purchasing options and how to take advantage of these options both to lower energy costs and to secure supply.

Watkins, G.

1988-09-01T23:59:59.000Z

116

DOE Issues Solicitation for Purchase of Oil for the Strategic Petroleum  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Issues Solicitation for Purchase of Oil for the Strategic Issues Solicitation for Purchase of Oil for the Strategic Petroleum Reserve DOE Issues Solicitation for Purchase of Oil for the Strategic Petroleum Reserve March 16, 2007 - 11:37am Addthis WASHINGTON, DC - The U.S. Department of Energy (DOE) today announced that it will seek solicitations to purchase up to four million barrels of crude oil for the Strategic Petroleum Reserve (SPR). This is the first of a series of solicitations planned to replace 11 million barrels of oil sold in the fall of 2005 after Hurricane Katrina disrupted refinery supplies. This would be the first direct purchase of crude oil for the reserve since 1994. The Strategic Petroleum Reserve will use the proceeds from the emergency sale totaling $584 million to complete the purchases.

117

DOE Issues Solicitation for Purchase of Oil for the Strategic Petroleum  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Solicitation for Purchase of Oil for the Strategic Solicitation for Purchase of Oil for the Strategic Petroleum Reserve DOE Issues Solicitation for Purchase of Oil for the Strategic Petroleum Reserve March 16, 2007 - 11:37am Addthis WASHINGTON, DC - The U.S. Department of Energy (DOE) today announced that it will seek solicitations to purchase up to four million barrels of crude oil for the Strategic Petroleum Reserve (SPR). This is the first of a series of solicitations planned to replace 11 million barrels of oil sold in the fall of 2005 after Hurricane Katrina disrupted refinery supplies. This would be the first direct purchase of crude oil for the reserve since 1994. The Strategic Petroleum Reserve will use the proceeds from the emergency sale totaling $584 million to complete the purchases. "The Strategic Petroleum Reserve is a critical national asset that bolsters

118

Large Industrial Renewable Energy Purchase Program (New Brunswick) |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Large Industrial Renewable Energy Purchase Program (New Brunswick) Large Industrial Renewable Energy Purchase Program (New Brunswick) Large Industrial Renewable Energy Purchase Program (New Brunswick) < Back Eligibility Agricultural Commercial Developer Industrial Investor-Owned Utility Local Government Municipal/Public Utility Rural Electric Cooperative Tribal Government Utility Savings Category Buying & Making Electricity Water Home Weatherization Solar Wind Program Info State New Jersey Program Type Performance-Based Incentive Provider New Brunswick Energy and Mines Beginning January 1, 2012 the Large Industrial Renewable Energy Purchase Program allows NB Power to purchase renewable energy generated by its largest customers at a rate of $95/MWh. This renewable energy will count towards meeting the Province's renewable energy targets at a purchase

119

Jackson Purchase Energy Corporation | Open Energy Information  

Open Energy Info (EERE)

Purchase Energy Corporation Purchase Energy Corporation Jump to: navigation, search Name Jackson Purchase Energy Corporation Place Kentucky Utility Id 9605 Utility Location Yes Ownership C NERC Location SERC Activity Distribution Yes References EIA Form EIA-861 Final Data File for 2010 - File1_a[1] LinkedIn Connections CrunchBase Profile No CrunchBase profile. Create one now! This article is a stub. You can help OpenEI by expanding it. Utility Rate Schedules Grid-background.png 1,000 watt - Metal Flood Lighting 100 watt - High Pressure Sodium Lighting 150 watt - Metal Halide Lighting 250 watt - High Pressure Sodium Lighting 250 watt - High Pressure Sodium Flood Lighting 400 watt - MV Lighting 400 watt - Metal Halide Lighting Commercial and Industrial - Schedule D Industrial Industrial Schedule I-E Industrial

120

Table 12. Refinery Sales During 2010  

U.S. Energy Information Administration (EIA)

Former Corporation/Refiner Total Atmospheric Crude Oil Distillation Capacity (bbl/cd) New Corporation/Refiner Date of Sale Table 12. Refinery Sales During 2010

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


121

Opportunities for Biorenewables in Petroleum Refineries  

Science Conference Proceedings (OSTI)

a summary of our collaborative 2005 project “Opportunities for Biorenewables in Petroleum Refineries” at the Rio Oil and Gas Conference this September.

Holmgren, Jennifer; Arena, Blaise; Marinangelli, Richard; McCall, Michael; Marker, Terry; Petri, John; Czernik, Stefan; Elliott, Douglas C.; Shonnard, David

2006-10-11T23:59:59.000Z

122

Opportunities for Biorenewables in Petroleum Refineries  

SciTech Connect

A presentation by UOP based on collaborative work from FY05 using some results from PNNL for upgrading biomass pyrolysis oil to petroleum refinery feedstock

Holmgren, Jennifer; Marinangelli, Richard; Marker, Terry; McCall, Michael; Petri, John; Czernik, Stefan; Elliott, Douglas C.; Shonnard, David

2007-02-01T23:59:59.000Z

123

Areas of Corrosion in the Refinery  

Science Conference Proceedings (OSTI)

...J.D. Poindexter, Corrosion Inhibitors for Crude Oil Refineries, Corrosion: Fundamentals, Testing, and Protection, Vol 13A, ASM Handbook, ASM International, 2003, p 887â??890...

124

Refinery Investments and Future Market Incentives  

U.S. Energy Information Administration (EIA)

Presentation given at the Annual NPRA Meeting that discusses factors affecting refinery investments. Refiners have plunged from a seeming “golden age” investment ...

125

Refinery Capacity Report - Energy Information Administration  

U.S. Energy Information Administration (EIA)

Energy Information Administration (U.S. Dept. of Energy) ... Tables: 1: Number and Capacity of Operable Petroleum Refineries by PAD District and State as of ...

126

A Louisiana Refinery Success Story  

E-Print Network (OSTI)

"Refining 155,000 barrels of crude oil daily, a Louisiana plant markets oil products to gas stations in at least 26 states, including Washington, D.C. The plant uses 8,538 steam traps with 1,200-, 600-, 250-, 75-, 40- and 15-psi nominal pressures. Standardized with inverted bucket steam traps, the Louisiana refinery’s maintenance and energy coordinator was content with the results. The Spirax Sarco Inc (SSI) team demonstrated SSI’s Energy Service Group (ESG) capabilities and successes to the refinery manager, operations manager and production manager. From 2004 through 2006, the team presented a series of ESG seminars at the refinery site. The numerous models demonstrated quantitative savings with 3- to 12-mo paybacks. For a complete SSI turnkey program, for example, the SSI team presented an ROI with less than six months payback. The ESG survey found that only 3,952 (46.3%) of the steam traps were operating correctly. The remaining steam traps experienced a variety of failures, including: 613 (7.2%) that failed open; 2,763 (32.4%) were cold; 1,012 (11.9%) that failed closed; 6 (0.0%) exhibited rapid cycling; and 192 (2.2%) were disconnected. The team also found performance and temperature issues with the HP sulfur reactors in the SRU units, largely due to the application of inverted bucket steam traps. Plus, as a result of excessive steam leaks, the sulfur reactors were creating a safety hazard. When these results were presented, management agreed that the sulfur reactors needed process improvement. The SSI team recommended replacing the inverted bucket steam traps with 1-1/2-in. strainers and 1-1/2-in. flanged float & thermostatic steam traps. They also suggested that the existing trap discharge piping should be removed and re-piped with globe-style bypass valves and gate-style isolation valves to reduce flow velocity. Once the SSI team began negotiations, it only took one survey for the Louisiana refinery to realize all the energy savings opportunities. In fact, the ESG survey uncovered more than $1.3 million in steam losses through failed steam traps and another $1 million in steam leak opportunities and production, process, safety and environmental improvements. Impressed with the survey results, the refinery approved the estimated $110,000 turnkey project, which offered a 5.3-month payback. Further negotiations netted the team annual steam trap surveys for the next three years, as well as an approved 2008 energy budget of $600,000. Additionally, the Louisiana refinery has indicated that upon successful completion of the ESG program, SSI’s annual energy budget will increase to $1,000,000."

Kacsur, D.

2009-05-01T23:59:59.000Z

127

U.S. Refining Capacity Utilization - Energy Information Administration  

U.S. Energy Information Administration (EIA)

distillation utilization rate that exceeded their reported stream day capacities. The observation that almost 40 percent of the domestic refineries reported a one ...

128

Energy efficiency improvement and cost saving opportunities for petroleum refineries  

E-Print Network (OSTI)

MTC. Marano, J.J. , 2003. Refinery Technology Profiles:Deep Desulfurization of Oil Refinery Streams: A Review. FuelSavings for Flying J Refinery. Oil & Gas Journal, December 2

Worrell, Ernst; Galitsky, Christina

2005-01-01T23:59:59.000Z

129

U.S. Refining Capacity Utilization  

Reports and Publications (EIA)

This article briefly reviews recent trends in domestic refining capacity utilization and examines in detail the differences in reported crude oil distillation capacities and utilization rates among different classes of refineries.

Tancred Lidderdale

1995-10-01T23:59:59.000Z

130

Federal Energy Management Program: Purchasing Renewable Power  

NLE Websites -- All DOE Office Websites (Extended Search)

Purchasing Renewable Power Purchasing Renewable Power Federal agencies can purchase renewable power or renewable energy certificates (RECs) from a utility or other organization to meet Federal renewable energy requirements. Renewable power and RECs are good choices for facilities where on-site projects may be difficult or capital budgets are limited. There are three methods for purchasing renewable power that's not generated on a Federal site: Renewable Energy Certificates: Also known as renewable energy credits, green certificates, green tags, or tradable renewable certificates, RECs represent the environmental attributes of the power produced from renewable energy projects and are sold separately from commodity electricity. RECs are an attractive option for Federal facilities located where renewable power is not readily available.

131

High Performance Windows Volume Purchase: For Utilities  

NLE Websites -- All DOE Office Websites (Extended Search)

and mixed climates, R-5 windows on average reduce window heat loss by 40% and overall space conditioning costs by 10% relative to common ENERGY STAR windows. Promotion of high...

132

Fossil Energy Techline, “Utility to Purchase Electricity  

E-Print Network (OSTI)

and represents a summary of carbon sequestration news covering the past month. Readers are referred to the actual article(s) for complete information. It is produced by the National Energy Technology Laboratory to provide information on recent activities and publications related to carbon sequestration. It covers domestic, international, public sector, and private sector news. Hi g h l i g h t s Wh at ’s In s i d e? Sequestration in the News

unknown authors

2012-01-01T23:59:59.000Z

133

Table 2. Production Capacity of Operable Petroleum Refineries by ...  

U.S. Energy Information Administration (EIA)

Includes hydrogen production capacity of hydrogen plants on refinery grounds. MMcfd = Million cubic feet per day. a ... (EIA), Form EIA-820, "Annual Refinery Report."

134

Energy efficiency improvement and cost saving opportunities for petroleum refineries  

E-Print Network (OSTI)

fuels in the graph. Source: Petroleum Supply Annual, Energypetroleum products, refineries are still a substantial sourceadded produced by petroleum refineries. Source: U.S. Census,

Worrell, Ernst; Galitsky, Christina

2005-01-01T23:59:59.000Z

135

Refinery receipts of crude oil by rail, truck, and barge ...  

U.S. Energy Information Administration (EIA)

While refinery receipts of crude by truck, rail, and barge remain a small percentage of total receipts, EIA's recently released Refinery Capacity ...

136

Petroleum refineries vary by level of complexity - Today in Energy ...  

U.S. Energy Information Administration (EIA)

A refinery is an industrial complex that manufactures petroleum products, such as gasoline, from crude oil and other feedstocks. Many different types of refineries ...

137

Energy efficiency improvement and cost saving opportunities for petroleum refineries  

E-Print Network (OSTI)

Aspropyrgos Refinery Combined Cycle Cogeneration System.refineries operate combined cycles with higher efficiencies.in an Integrated Gasifier Combined Cycle (IGCC). In this

Worrell, Ernst; Galitsky, Christina

2005-01-01T23:59:59.000Z

138

EIA-800 WEEKLY REFINERY AND FRACTIONATOR REPORT INSTRUCTIONS  

U.S. Energy Information Administration (EIA)

EIA-800, Weekly Refinery and Fractionator Report Page 3 Crude Oil (Code 050) Report all refinery input of domestic and foreign crude oil (including ...

139

PAD District 4 Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

Notes: Idle refineries represent refineries where distillation units were completely idle but not permanently shutdown as of January 1 of the year.

140

Purchased Gas Adjustment Rules (Tennessee) | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Purchased Gas Adjustment Rules (Tennessee) Purchased Gas Adjustment Rules (Tennessee) Purchased Gas Adjustment Rules (Tennessee) < Back Eligibility Commercial Developer Fuel Distributor General Public/Consumer Industrial Installer/Contractor Investor-Owned Utility Rural Electric Cooperative Utility Program Info State Tennessee Program Type Generating Facility Rate-Making Industry Recruitment/Support Provider Tennessee Regulatory Authority The Purchased Gas Adjustment Rules are implemented by the Tennessee Regulatory Authority (Authority). Purchased Gas Adjustment (PGA) Rules are intended to permit the company/LDC (local gas distribution company regulated by the Authority) to recover, in timely fashion, the total cost of gas purchased for delivery to its customers and to assure that the Company does not over-collect or under-collect Gas Costs from its

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


141

Take an integrated approach to refinery automation  

Science Conference Proceedings (OSTI)

An integrated approach to designing refinery automation systems is essential to guaranteeing systems compatibility and maximizing benefits. Several aspects of implementing integrated refinery automation should be considered early in the project. Many refineries have major parts of their business automated, starting from corporate planning at the higher level, down to DCS and field instrumentation. A typical refinery automation system architecture of the mid-eighties is shown. Automation systems help refineries improve their business through: Rationalization of man power; Increased throughputs; Reduced give-away; Reduced energy consumption; Better response to market demands and changes; Effective use of offsite areas through scheduling and automatic line-up systems; Reduced losses; and Decision support systems.

Wadi, I. (Abu Dhabi National Oil Co. (United Arab Emirates))

1993-09-01T23:59:59.000Z

142

Feasibility study on the modernization and expansion of the Tema Oil Refinery. Executive Summary. Export trade information  

Science Conference Proceedings (OSTI)

The Tema Oil Refinery (TOR), which was commissioned in 1963, is a simple hydro-skimming plant which processes crude oil into LPG, gasoline, kerosene, gasoil, and fuel oil. It is the only petroleum refinery in Ghana. Over the years some of the equipment in the refinery has deteriorated or become obsolete necessitating major rehabilitation. A study of the refinery expansion project takes into consideration earlier studies and, equally important, recognizes the extensive work done by TOR in rehabilitating the refinery. The program, carried out in phases because of funding limitations, has addressed the critical repairs and replacements in the process units and utilities necessary to prolong the life of the refinery and assure reliability and safe operation. It undertook the task of investigating the feasibility of modernizing and expanding the refinery at Tema, Ghana to meet projected market demands until the year 2005. A process planning study was conducted to select the optimal process and utility configuration which would result in economic benefits to Ghana.

Not Available

1992-04-01T23:59:59.000Z

143

Documentation: The automated ORAD (Oil Refinery and Distribution Model) to RYMs (Refinery Yield Model) linked system  

SciTech Connect

The Refinery Evaluation Modeling System (REMS) is an analytic tool used by the Energy Information Administration (EIA) to provide insight into the domestic operations of United States refineries. REMS can be used to determine the potential impacts of changes in demands for petroleum products, crude and feedstock qualities, refinery processing capacities, foreign and domestic crude availabilities, transportation modes and costs, and government regulations. REMS is a set of linear programming models that solve for a partial equilibrium in the US refinery market by equating supply and demand while maximizing profits for US refiners. REMS consists of two models: the Refinery Yield Model (RYM), and the Oil Refinery and Distribution Model (ORAD). RYMs consists of nine separate regional models that represent the contiguous US refinery system. These nine regions are aggregates of the 13 Bureau of Mines (BOM) refinery districts. ORAD integrates the results from the individual RYMs into a transportation network which represents the US refinery market. ORAD uses the extreme point refinery representation from RYMs to solve for the optimal product prices in ORAD.

Sanders, R.P.; Kydes, A.S.

1987-01-01T23:59:59.000Z

144

Wisconsin Propane and Propylene Stocks at Refineries, Bulk ...  

U.S. Energy Information Administration (EIA)

Wisconsin Propane and Propylene Stocks at Refineries, Bulk Terminals, and Natural Gas Plants (Thousand Barrels)

145

Ohio Distillate Fuel Oil Stocks at Refineries, Bulk Terminals, and ...  

U.S. Energy Information Administration (EIA)

Ohio Distillate Fuel Oil Stocks at Refineries, Bulk Terminals, and Natural Gas Plants (Thousand Barrels)

146

Colorado Propane and Propylene Stocks at Refineries, Bulk ...  

U.S. Energy Information Administration (EIA)

Colorado Propane and Propylene Stocks at Refineries, Bulk Terminals, and Natural Gas Plants (Thousand Barrels)

147

Colorado Finished Motor Gasoline Stocks at Refineries, Bulk ...  

U.S. Energy Information Administration (EIA)

Colorado Finished Motor Gasoline Stocks at Refineries, Bulk Terminals, and Natural Gas Plants (Thousand Barrels)

148

Colorado Refinery Marketable Petroleum Coke Production Capacity as ...  

U.S. Energy Information Administration (EIA)

Colorado Refinery Marketable Petroleum Coke Production Capacity as of January 1 (Barrels per Stream Day)

149

Midwest (PADD 2) Refinery and Blender Net Production of ...  

U.S. Energy Information Administration (EIA)

Midwest (PADD 2) Refinery and Blender Net Production of Finished Motor Gasoline (Thousand Barrels per Day)

150

Guam Refinery Operable Atmospheric Crude Oil Distillation Capacity ...  

U.S. Energy Information Administration (EIA)

Guam Refinery Operable Atmospheric Crude Oil Distillation Capacity as of January 1 (Barrels per Calendar Day)

151

Michigan Finished Motor Gasoline Stocks at Refineries, Bulk ...  

U.S. Energy Information Administration (EIA)

Michigan Finished Motor Gasoline Stocks at Refineries, Bulk Terminals, and Natural Gas Plants (Thousand Barrels)

152

South Dakota Distillate Fuel Oil Stocks at Refineries, Bulk ...  

U.S. Energy Information Administration (EIA)

South Dakota Distillate Fuel Oil Stocks at Refineries, Bulk Terminals, and Natural Gas Plants (Thousand Barrels)

153

South Dakota Propane and Propylene Stocks at Refineries, Bulk ...  

U.S. Energy Information Administration (EIA)

South Dakota Propane and Propylene Stocks at Refineries, Bulk Terminals, and Natural Gas Plants (Thousand Barrels)

154

Total Number of Operable Refineries  

U.S. Energy Information Administration (EIA) Indexed Site

Data Series: Total Number of Operable Refineries Number of Operating Refineries Number of Idle Refineries Atmospheric Crude Oil Distillation Operable Capacity (B/CD) Atmospheric Crude Oil Distillation Operating Capacity (B/CD) Atmospheric Crude Oil Distillation Idle Capacity (B/CD) Atmospheric Crude Oil Distillation Operable Capacity (B/SD) Atmospheric Crude Oil Distillation Operating Capacity (B/SD) Atmospheric Crude Oil Distillation Idle Capacity (B/SD) Vacuum Distillation Downstream Charge Capacity (B/SD) Thermal Cracking Downstream Charge Capacity (B/SD) Thermal Cracking Total Coking Downstream Charge Capacity (B/SD) Thermal Cracking Delayed Coking Downstream Charge Capacity (B/SD Thermal Cracking Fluid Coking Downstream Charge Capacity (B/SD) Thermal Cracking Visbreaking Downstream Charge Capacity (B/SD) Thermal Cracking Other/Gas Oil Charge Capacity (B/SD) Catalytic Cracking Fresh Feed Charge Capacity (B/SD) Catalytic Cracking Recycle Charge Capacity (B/SD) Catalytic Hydro-Cracking Charge Capacity (B/SD) Catalytic Hydro-Cracking Distillate Charge Capacity (B/SD) Catalytic Hydro-Cracking Gas Oil Charge Capacity (B/SD) Catalytic Hydro-Cracking Residual Charge Capacity (B/SD) Catalytic Reforming Charge Capacity (B/SD) Catalytic Reforming Low Pressure Charge Capacity (B/SD) Catalytic Reforming High Pressure Charge Capacity (B/SD) Catalytic Hydrotreating/Desulfurization Charge Capacity (B/SD) Catalytic Hydrotreating Naphtha/Reformer Feed Charge Cap (B/SD) Catalytic Hydrotreating Gasoline Charge Capacity (B/SD) Catalytic Hydrotreating Heavy Gas Oil Charge Capacity (B/SD) Catalytic Hydrotreating Distillate Charge Capacity (B/SD) Catalytic Hydrotreating Kerosene/Jet Fuel Charge Capacity (B/SD) Catalytic Hydrotreating Diesel Fuel Charge Capacity (B/SD) Catalytic Hydrotreating Other Distillate Charge Capacity (B/SD) Catalytic Hydrotreating Residual/Other Charge Capacity (B/SD) Catalytic Hydrotreating Residual Charge Capacity (B/SD) Catalytic Hydrotreating Other Oils Charge Capacity (B/SD) Fuels Solvent Deasphalting Charge Capacity (B/SD) Catalytic Reforming Downstream Charge Capacity (B/CD) Total Coking Downstream Charge Capacity (B/CD) Catalytic Cracking Fresh Feed Downstream Charge Capacity (B/CD) Catalytic Hydro-Cracking Downstream Charge Capacity (B/CD) Period:

155

Wastewater reuse and recycle in petroleum refineries  

SciTech Connect

The objectives of this study were to identify feasible reuse and recycle techniques that can be successful in reducing wastewater discharge and to estimate their associated costs. Wastewater reduction is a fundamental aspect of the US EPA's proposed regulations for the petroleum refining industry. EPA undertook this study to confirm the cost estimates used in the proposed guidelines, to identify specific technologies, and to accurately assess their costs. Fifteen refineries were chosen to represent the range of refinery characteristics including crude capacity, process employed, and wastewater generation. Significant wastewater reductions were found possible at 12 refineries studied.

Langer, B.S.

1983-05-01T23:59:59.000Z

156

Former Soviet refineries face modernization, restructuring  

Science Conference Proceedings (OSTI)

A massive modernization and restructuring program is under way in the refining sector of Russia and other former Soviet republics. Economic reforms and resulting economic dislocation following the collapse of the Soviet Union has left refineries in the region grappling with a steep decline and changes in product demand. At the same time, rising oil prices and an aging, dilapidated infrastructure promise a massive shakeout. Even as many refineries in the former Soviet Union (FSU) face possible closure because they are running at a fraction of capacity, a host of revamps, expansions, and grass roots refineries are planned or under way. The paper discusses plans.

Not Available

1993-11-29T23:59:59.000Z

157

Texas facility treats, recycles refinery, petrochemical wastes  

Science Conference Proceedings (OSTI)

A US Gulf Coast environmental services company is treating refinery and petrochemical plant wastes to universal treatment standards (UTS). DuraTherm Inc.`s recycling center uses thermal desorption to treat a variety of refinery wastes and other hazardous materials. The plant is located in San Leon, Tex., near the major Houston/Texas City refining and petrochemical center. DuraTherm`s customers include major US refining companies, plus petrochemical, terminal, pipeline, transportation, and remediation companies. Examples of typical contaminant concentrations and treatment levels for refinery wastes are shown. The paper discusses thermal desorption, the process description and testing.

NONE

1996-09-16T23:59:59.000Z

158

A Texas Refinery Success Story  

E-Print Network (OSTI)

"Common knowledge rules that maintenance is the key to long-lasting machinery performance. Yet steam traps are often left to their own devices, to fail or succeed alone. And without steam trap programs, plants are certain to experience a high failure rate. An oil refinery in Texas was continuously experiencing a high failure rate on its 4,790-steam trap system. Finally, the steam losses were judged to be too high, and plant management called on Spirax Sarco Inc. (SSI) to reduce costs. The SSI team noticed symptoms of subpar efficiency within the steam system. Steam traps were improperly installed, water hammer problems were evident and the condensate recovery system was damaged."

Kacsur, D.

2009-05-01T23:59:59.000Z

159

Refinery Waste Heat Ammonia Absorption Refrigeration Plant (WHAARP) Recovers LPG's and Gasoline, Saves Energy, and Reduces Air Pollution  

E-Print Network (OSTI)

A first-of-its-kind Waste Heat Ammonia Absorption Refrigeration Plant (WHAARP™) was installed by Planetec Utility Services Co., Inc. in partnership with Energy Concepts Co. at Ultramar Diamond Shamrock's 30,000 barrel per day refinery in Denver, Colorado. The refrigeration unit is designed to provide refrigeration for two process units at the refinery while utilizing waste heat as the energy source. The added refrigeration capacity benefits the refinery by recovering salable products, debottlenecking process units, avoiding additional electrical demand, and reducing the refinery Energy Intensity Index. In addition, the WHAARP unit lowers air pollutant emissions by reducing excess fuel gas that is combusted in the refinery flare. A comprehensive utility and process efficiency Master Plan developed for the Denver refinery by Planetec provided the necessary platform for implementing this distinctive project. The $2.3 million WHAARP system was paid for in part by a $760,000 grant from the U.S. Department of Energy, as part of their "Industry of the Future Program". Total combined benefits are projected to be approximately $1 million/year with a 1.6 year simple payback including the grant funding.

Brant, B.; Brueske, S.; Erickson, D.; Papar, R.

1998-04-01T23:59:59.000Z

160

High Performance Windows Volume Purchase: For Light Commercial Buyers  

NLE Websites -- All DOE Office Websites (Extended Search)

For Light For Light Commercial Buyers to someone by E-mail Share High Performance Windows Volume Purchase: For Light Commercial Buyers on Facebook Tweet about High Performance Windows Volume Purchase: For Light Commercial Buyers on Twitter Bookmark High Performance Windows Volume Purchase: For Light Commercial Buyers on Google Bookmark High Performance Windows Volume Purchase: For Light Commercial Buyers on Delicious Rank High Performance Windows Volume Purchase: For Light Commercial Buyers on Digg Find More places to share High Performance Windows Volume Purchase: For Light Commercial Buyers on AddThis.com... Home About For Builders For Residential Buyers For Light Commercial Buyers For Manufacturers For Utilities Information Resources For Light Commercial Buyers Significant energy savings from low-E window technology are possible in the

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


161

High Performance Windows Volume Purchase: For Residential Buyers  

NLE Websites -- All DOE Office Websites (Extended Search)

Residential Buyers to someone by E-mail Residential Buyers to someone by E-mail Share High Performance Windows Volume Purchase: For Residential Buyers on Facebook Tweet about High Performance Windows Volume Purchase: For Residential Buyers on Twitter Bookmark High Performance Windows Volume Purchase: For Residential Buyers on Google Bookmark High Performance Windows Volume Purchase: For Residential Buyers on Delicious Rank High Performance Windows Volume Purchase: For Residential Buyers on Digg Find More places to share High Performance Windows Volume Purchase: For Residential Buyers on AddThis.com... Home About For Builders For Residential Buyers For Light Commercial Buyers For Manufacturers For Utilities Information Resources For Residential Buyers Both home owners and buyers can take advantage of the energy savings from

162

Property:EnergyPurchaser | Open Energy Information  

Open Energy Info (EERE)

EnergyPurchaser EnergyPurchaser Jump to: navigation, search This is a property of type Page. Subproperties This property has the following 1 subproperty: G GRR/Section 4-FD-a - Exploration Permit BLM Pages using the property "EnergyPurchaser" Showing 25 pages using this property. (previous 25) (next 25) A AB Tehachapi Wind Farm + Southern California Edison Co + AFCEE MMR Turbines + Distributed generation - net metered + AG Land 1 + Alliant Energy + AG Land 2 + Alliant Energy + AG Land 3 + Alliant Energy + AG Land 4 + Alliant Energy + AG Land 5 + Alliant Energy + AG Land 6 + Alliant Energy + AVTEC + AVTEC + Adair Wind Farm I + Alliant/IES Utilities + Adair Wind Farm II + MidAmerican Energy + Aeroman Repower Wind Farm + Southern California Edison Co + Agassiz Beach Wind Farm + Xcel Energy +

163

Minimum Purchase Price Regulations (Prince Edward Island, Canada)  

Energy.gov (U.S. Department of Energy (DOE))

The Minimum Purchase Price Regulations establish the price which utilities must pay for power produced by large-scale renewable energy generators – that is those capable of producing more than 100...

164

Inbicon Biomass Refinery Cellulosic Ethanol Technology Platforms  

U.S. Energy Information Administration (EIA)

for biogas production Inbicon Biomass Refinery Energy integrated solutions Wheat Straw 50 t/h (at 86 % dm) C5 molasses Power The Lignin and biogas are used in power

165

Motiva Enterprises Refinery Expansion Groundbreaking | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

it. When this expansion is complete this facility which is now one of the preeminent refineries on the Gulf Coast will become the largest in the United States and one of the...

166

Refinery siting workbook: appendices A and B  

Science Conference Proceedings (OSTI)

The objective of this effort is to develop and provide basic refinery-related information for use by state and local government officials as a basis for establishing responsible refinery siting requirements and policies consistent with the federal clean air and water standards and socio-economic concerns. The report will be organized into two volumes. The main text comprises the basic topics of physical concerns, regulatory requirements, and permitting activities, while the second volume includes the detailed appendix materials such as the applicable laws, and the necessary permits, as available and a glossary of pertinent terms. As a means to this objective, three refinery sizes, 200,000, 100,000 and 30,000 barrels per day crude charge will be discussed in technical terms. Process unit configuration will be presented which will maximize either gasoline or heating oil production with either sweet or sour crude oil feedstocks. The major issues affecting the socio-economic impact of siting the refinery in a given locale will be presented. These data will review the factors affecting the human environment and the issues that must be addressed to assess the impact that a refinery will have on a community. The key federal registrations which impact upon a refinery siting decision shall be reviewed. Summaries of these regulations and a simplified decision diagram for the air and water acts shall be presented to assist both government and refinery officials in understanding the scope of regulatory impact. All pertinent procedures required for refinery permitting shall be reviewed under the generalized headings of air, water, health and safety, land use, and miscellaneous permits. This categorization at the federal, state and local levels of government shall be used as a basis for establishing degrees of emphasis.

Not Available

1980-07-01T23:59:59.000Z

167

Table 4b. U.S. Petroleum Refinery Balance (Million Barrels per Day ...  

U.S. Energy Information Administration (EIA)

Refinery Distillation Utilization Factor ..... 0.86 0.90 0.90 0.89 0.83 0.89 0.91 0.87 0.83 0.88 0.90 0.87 0.89 0.88 0.87 - = no data available Table 4b. U.S ...

168

Table A44. Average Prices of Purchased Electricity and Steam  

U.S. Energy Information Administration (EIA) Indexed Site

4. Average Prices of Purchased Electricity and Steam" 4. Average Prices of Purchased Electricity and Steam" " by Type of Supplier, Census Region, Census Division, and" " Economic Characteristics of the Establishment, 1994" " (Estimates in Dollars per Physical Units)" ," Electricity",," Steam" ," (kWh)",," (million Btu)" ,,,,,"RSE" ,"Utility","Nonutility","Utility","Nonutility","Row" "Economic Characteristics(a)","Supplier(b)","Supplier(c)","Supplier(b)","Supplier(c)","Factors"

169

Table A39. Total Expenditures for Purchased Electricity and Steam  

U.S. Energy Information Administration (EIA) Indexed Site

9. Total Expenditures for Purchased Electricity and Steam" 9. Total Expenditures for Purchased Electricity and Steam" " by Type of Supplier, Census Region, Census Division, and" " Economic Characteristics of the Establishment, 1994" " (Estimates in Million Dollars)" ," Electricity",," Steam" ,,,,,"RSE" ,"Utility","Nonutility","Utility","Nonutility","Row" "Economic Characteristics(a)","Supplier(b)","Supplier(c)","Supplier(b)","Supplier(c)","Factors" ,"Total United States" "RSE Column Factors:",0.3,2,1.6,1.2

170

Refinery analytical techniques optimize unit performance  

Science Conference Proceedings (OSTI)

Refinery process engineers need to consider benefits of laboratory analytical techniques when evaluating unit performance. Refinery heavy-oil laboratory analytical techniques use both old and new technologies. Knowing how to use available laboratory analytical techniques within their limitations are critical to obtain correct refinery optimization decisions. Better refinery stream distillation and contaminant data ultimately improves the accuracy of various refinery decision-making tools. These laboratory analytical techniques are covered: high-temperature simulated distillation (HTSD); true boiling point (TBP) distillation--ASTM D2892; vacuum distillation--ASTM D5236; continuous-flash vaporizers; wiped-film evaporators; inductively coupled plasma atomic-emission spectroscopy (ICP-AES); Conradson--ASTM D189/Microcarbon residue--ASTM D4530; and asphaltene IP-143, ASTM D3279, ASTM D4124. Analysis of atmospheric crude, vacuum crude and delayed coker units highlight these laboratory techniques to identify potential yield and product quality benefits. Physical distillation or wiped-film evaporation in conjunction with HTSD, ICP-AES, microcarbon residue and asphaltened data will better characterize a feedstock as well as determine the source of contaminants. Economics are refinery specific, therefore, these examples focus on applying laboratory techniques as opposed to discussing specifics of unit improvement. These are discussed qualitatively.

Golden, S.W. [Process Consulting Services Inc., Grapevine, TX (United States); Craft, S. [Chempro, Inc., LaPorte, TX (United States); Villalanti, D.C. [Triton Analytics Corp., Houston, TX (United States)

1995-11-01T23:59:59.000Z

171

Complexity index indicates refinery capability, value  

Science Conference Proceedings (OSTI)

Refinery size usually is measured in terms of distillation capacity. Relative size, however, can be measured using refinery complexity--a concept developed by W.L. Nelson in the 1960s. Nelson developed the complexity index to quantify the relative cost of components that make up a refinery. It is a pure cost index that provides a relative measure of the construction costs of a particular refinery based on its crude and upgrading capacity. The Nelson index compares the costs of various upgrading units--such as a fluid catalytic cracking (FCC) unit or a catalytic reformer--to the cost of a crude distillation unit. Computation of the index is an attempt to quantify the relative cost of a refinery based on the added cost of various upgrading units and the relative upgrading capacity. A review of complexity calculations, and an explanation of how indices have changed, provide a simple means of determining the complexity of single refineries or refining regions. The impact of complexity on product slate is also examined in this paper.

Johnston, D. [Daniel Johnston and Co. Inc., Dallas, TX (United States)

1996-03-18T23:59:59.000Z

172

Power Purchase Agreements Update  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

April 20-21 in Portland, Oregon April 20-21 in Portland, Oregon Power Purchase Agreement Update April 21, 2011 Chandra Shah chandra.shah@nrel.gov 2 | FEDERAL ENERGY MANAGEMENT PROGRAM femp.energy.gov Overview * Power Purchase Agreement (PPA) Template * PPA Request For Information (RFI) 3 | FEDERAL ENERGY MANAGEMENT PROGRAM femp.energy.gov PPA Template * DLA Energy has an updated PPA template - Includes Best Value evaluation (rather than Low Price/Technically Acceptable) - Additional updates will be made based on the PPA RFI - Updated template will be posted on FEMP PPA Sample Document web site http://www1.eere.energy.gov/femp/financing/ppa_sampledocs.html 4 | FEDERAL ENERGY MANAGEMENT PROGRAM femp.energy.gov PPA Request for Information * Background - PPA issues identified based on meetings/telecons

173

Solar Power Purchase Agreements  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Solar Power Purchase Agreements Solar Power Purchase Agreements Brian Millberg | Energy Manager, City of Minneapolis Direct Ownership * Financial: Even at $3/kW installed cost, simple payback is 18 years (initial electricity cost of $0.10/kWh and 3%/year electricity cost inflation) * Politics: How to justify expense with such a long payback * If RECS begin to have some real value, this would be a positive for ownership. 2 PPA Advantages * No/low up-front costs * City can take advantage of Investment Tax Credits (ITCs) - This leads to low electricity costs * Predictable electricity cost for length of contract * Avoid direct design/rebate/permitting work * No maintenance/operation headaches 3 PPA Financial Case (1 MW system) * PPA allows a developer to reduce system cost through:

174

A Case Study of Steam System Evaluation in a Petroleum Refinery  

E-Print Network (OSTI)

ASI conducted a steam system evaluation study at a multinational petroleum Refinery located in the Eastern UK during June-July, 1999. At this refinery, Steam, Fuel and Electricity systems are inter-connected. Steam is generated from direct fuel fired boilers as well from Furnace and Kiln waste heat. Steam is also supplied from the CHP waste heat boilers. Steam generation averages 1,500,000 lbs/hr and does not change significantly between winter and summer since steam needs for process and power generation dominates way above comfort heating. To generate steam, the refinery spends about £28 million per year ($46 million). The system evaluation study identified 31 Energy & steam system cost savings measures (ECM) to save fuel, steam and condensate in the areas of: Steam generation, Steam distribution, Steam Utilization, Condensate recovery, and Combustion optimization in kilns. By implementing all the above 31 ECMs, the refinery is estimated to save $3.5 million annually. Based on our preliminary investment estimate the average payback would be within 2 years. The refinery also would reduce 5600 metric tons Carbon emission to environment. Some of the opportunities address the installation defects of the steam system components that would improve the system reliability and longevity.

Venkatesan, V. V.; Iordanova, N.

2003-05-01T23:59:59.000Z

175

FEASIBILITY STUDY FOR A PETROLEUM REFINERY FOR THE JICARILLA APACHE TRIBE  

Science Conference Proceedings (OSTI)

A feasibility study for a proposed petroleum refinery for the Jicarilla Apache Indian Reservation was performed. The available crude oil production was identified and characterized. There is 6,000 barrels per day of crude oil production available for processing in the proposed refinery. The proposed refinery will utilize a lower temperature, smaller crude fractionation unit. It will have a Naphtha Hydrodesulfurizer and Reformer to produce high octane gasoline. The surplus hydrogen from the reformer will be used in a specialized hydrocracker to convert the heavier crude oil fractions to ultra low sulfur gasoline and diesel fuel products. The proposed refinery will produce gasoline, jet fuel, diesel fuel, and a minimal amount of lube oil. The refinery will require about $86,700,000 to construct. It will have net annual pre-tax profit of about $17,000,000. The estimated return on investment is 20%. The feasibility is positive subject to confirmation of long term crude supply. The study also identified procedures for evaluating processing options as a means for American Indian Tribes and Native American Corporations to maximize the value of their crude oil production.

John D. Jones

2004-10-01T23:59:59.000Z

176

Table A23. Quantity of Purchased Electricity, Steam, and Natural Gas by Type  

U.S. Energy Information Administration (EIA) Indexed Site

3. Quantity of Purchased Electricity, Steam, and Natural Gas by Type" 3. Quantity of Purchased Electricity, Steam, and Natural Gas by Type" " of Supplier, Census Region, Industry Group, and Selected Industries, 1991" " (Estimates in Btu or Physical Units)" ,," Electricity",," Steam",," Natural Gas" ,," (Million kWh)",," (Billion Btu)",," (Billion cu ft)" ,," -------------------------",," -------------------------",," ---------------------------------------",,,"RSE" "SIC",,"Utility","Nonutility","Utility","Nonutility","Utility","Transmission","Other","Row"

177

Table A27. Quantity of Purchased Electricity, Steam, and Natural Gas by Type  

U.S. Energy Information Administration (EIA) Indexed Site

Quantity of Purchased Electricity, Steam, and Natural Gas by Type" Quantity of Purchased Electricity, Steam, and Natural Gas by Type" " of Supplier, Census Region, and Economic Characteristics of the Establishment," 1991 " (Estimates in Btu or Physical Units)" " "," Electricity",," Steam",," Natural Gas" ," (Million (kWh)",," (Billion Btu)",," (Billion cu ft)" ," -----------------------",," -----------------------",," ------------------------------------",,,"RSE" ,"Utility","Nonutility","Utility","Nonutility","Utility","Transmission","Other","Row"

178

"Table A49. Average Prices of Purchased Electricity, Steam, and Natural Gas"  

U.S. Energy Information Administration (EIA) Indexed Site

9. Average Prices of Purchased Electricity, Steam, and Natural Gas" 9. Average Prices of Purchased Electricity, Steam, and Natural Gas" " by Type of Supplier, Census Region, and Economic Characteristics of the" " Establishment, 1991" " (Estimates in Dollars per Physical Units)" ," Electricity",," Steam",," Natural Gas" ," (Million kWh)",," (Billion Btu)",," (1000 cu ft)" ,"-","-----------","-","-----------","-","-","-","RSE" " ","Utility","Nonutility","Utility","Nonutility","Utility","Transmission","Other","Row"

179

Implementing an Energy Management Strategy for a Houston Refinery  

E-Print Network (OSTI)

Intense competition and environmental regulation of industries utilizing combustion equipment have motivated many owners and operators to seek ways to reduce costs, improve performance, and minimize emissions. Energy management programs are being implemented throughout industry to improve equipment operating efficiencies, profitability, extend equipment life, prevent forced shutdowns, generate substantial fuel savings, track valuable information, and enhance compliance margins. A well designed and maintained energy management program translates to PROFIT added directly to the BOTTOM LINE. Woodward-Clyde Consultants (WCC) recently implemented and energy management program at the Lyondell-Citgo Refinery in Houston, Texas. The basis of the program is the 80/20 rule where 80% of the total potential savings are derived from optimizing the energy utilization from 20% of the combustion equipment. In this case, 11 out of 55 heaters were targeted for inclusion in the program. The fuel savings potential alone exceeded $1,250,000. In addition to the fuel savings, there were reduced costs from improved operation, as well as reduction in maintenance requirements and forced shutdowns. The remainder of this paper discusses the technical approach, the benefits, and the results of the program implemented at the Lyondell-Citgo Refinery.

Wood, S. C.; Agrawal, R. K.; Canon, D.

1996-04-01T23:59:59.000Z

180

OMB No. 1905-0165 Version No.:xxxx.xx FORM EIA-820 ANNUAL REFINERY ...  

U.S. Energy Information Administration (EIA)

the comparable capacity numbers reported on the Form EIA-810, "Monthly Refinery Report," filed for January 2014. ... ANNUAL REFINERY REPORT.

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


181

U.S. Exports of Natural Gas Liquids and Liquid Refinery Gases ...  

U.S. Energy Information Administration (EIA)

Natural Gas Plant Liquids and Liquefied Refinery Gases Exports; Natural Gas Plant Liquids and Liquefied Refinery Gases Supply and Disposition;

182

Mandatory Utility Green Power Option  

Energy.gov (U.S. Department of Energy (DOE))

In Montana, regulated electric utilities are required to offer customers the option of purchasing electricity generated by certified, environmentally-preferred resources that include, but are not...

183

U.S. Refinery Yield  

U.S. Energy Information Administration (EIA) Indexed Site

Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 View Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 View History Liquefied Refinery Gases 5.3 5.4 5.2 5.2 5.1 3.9 1993-2013 Finished Motor Gasoline 44.4 44.1 44.4 43.9 43.9 44.9 1993-2013 Finished Aviation Gasoline 0.1 0.1 0.1 0.1 0.1 0.1 1993-2013 Kerosene-Type Jet Fuel 10.0 9.1 9.3 9.4 9.8 9.6 1993-2013 Kerosene 0.0 0.1 0.1 0.1 0.0 0.0 1993-2013 Distillate Fuel Oil 28.4 29.4 28.7 29.2 29.3 29.7 1993-2013 Residual Fuel Oil 3.3 2.9 2.8 2.8 2.5 2.6 1993-2013 Naphtha for Petrochemical Feedstock Use 1.4 1.5 1.5 1.6 1.5 1.5 1993-2013 Other Oils for Petrochemical Feedstock Use 0.6 0.6 0.7 0.7 0.6 0.7 1993-2013 Special Naphthas 0.3 0.3 0.3 0.2 0.3 0.2 1993-2013 Lubricants 0.9 1.1 1.1 1.1 1.1 1.1 1993-2013 Waxes

184

U.S. Refinery Yield  

U.S. Energy Information Administration (EIA) Indexed Site

2007 2008 2009 2010 2011 2012 View 2007 2008 2009 2010 2011 2012 View History Liquefied Refinery Gases 4.1 4.1 4.1 4.3 4.0 4.1 1993-2012 Finished Motor Gasoline 45.5 44.2 46.1 45.7 44.9 45.0 1993-2012 Finished Aviation Gasoline 0.1 0.1 0.1 0.1 0.1 0.1 1993-2012 Kerosene-Type Jet Fuel 9.1 9.7 9.3 9.3 9.4 9.5 1993-2012 Kerosene 0.2 0.1 0.1 0.1 0.1 0.1 1993-2012 Distillate Fuel Oil 26.1 27.8 26.9 27.5 28.9 29.1 1993-2012 Residual Fuel Oil 4.2 4.0 4.0 3.8 3.4 3.2 1993-2012 Naphtha for Petrochemical Feedstock Use 1.3 1.0 1.3 1.4 1.3 1.3 1993-2012 Other Oils for Petrochemical Feedstock Use 1.3 1.2 0.8 0.8 0.7 0.6 1993-2012 Special Naphthas 0.3 0.3 0.2 0.2 0.2 0.3 1993-2012 Lubricants 1.1 1.1 1.0 1.1 1.1 1.0 1993-2012 Waxes 0.1 0.1 0.1 0.1 0.1 0.1 1993-2012

185

Green Power Purchasing Commitment (Massachusetts) | Open Energy...  

Open Energy Info (EERE)

Green Power Purchasing Commitment Incentive Type Green Power Purchasing Applicable Sector State Government Eligible Technologies Anaerobic Digestion, Biomass, CHPCogeneration,...

186

Indiana, Illinois, Kentucky Refinery District Gross Inputs to ...  

U.S. Energy Information Administration (EIA)

Indiana, Illinois, Kentucky Refinery District Gross Inputs to Refineries (Thousand Barrels per Day) Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec; 1985: 1,739 ...

187

Texas City Refinery Update: The Price of Safety Complacency  

NLE Websites -- All DOE Office Websites (Extended Search)

Texas City Refinery Update: The Price of Safety Complacency DOEEH-0699 2006-01 January 2006 ES&H Safety Bulletin 2005-09 (July 2005) discussed the Texas City Refinery accident in...

188

Improved oil refinery operations and cheaper crude oil to help...  

Annual Energy Outlook 2012 (EIA)

Improved oil refinery operations and cheaper crude oil to help reduce gasoline prices U.S. gasoline prices are expected to fall as more oil refineries come back on line and crude...

189

Flare Gas Recovery in Shell Canada Refineries  

E-Print Network (OSTI)

Two of Shell Canada's refineries have logged about six years total operating experience with modern flare gas recovery facilities. The flare gas recovery systems were designed to recover the normal continuous flare gas flow for use in the refinery fuel gas system. The system consists of liquid knock-out, compression, and liquid seal facilities. Now that the debugging-stage challenges have been dealt with, Shell Canada is more than satisfied with the system performance. A well-thought-out installation can today be safe, trouble-free, and attractive from an economic and environmental viewpoint. This paper highlights general guidelines for the sizing, design and operation of a refinery flare gas recovery facility.

Allen, G. D.; Wey, R. E.; Chan, H. H.

1983-01-01T23:59:59.000Z

190

How refinery fuel indexes have varied  

Science Conference Proceedings (OSTI)

Refinery fuels costs have endured a steady incline since 1993, except for a period in 1993. As shown in the accompanying table, these increases in cost have occurred for residual fuel oil costs in three of the five PADD districts. The cost for natural gas for refinery usage also dropped steadily during the 3-year study. These conclusions are based on costs of an average refinery fuel consisting of 1 bbl each of PADD Districts 1--5 and an average US cost of 4.4 MMscf natural gas (a 1 bbl equivalent on a BTU content basis). Raw residual fuel oil and natural gas prices come from publications put out by the US Department of Labor.

Farrar, G.

1997-01-06T23:59:59.000Z

191

U.S. Refinery Thermal Cracking, Visbreaking Downstream Charge ...  

U.S. Energy Information Administration (EIA)

U.S. Refinery Thermal Cracking, Visbreaking Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

192

Guam Refinery Thermal Cracking/Visbreaking Downstream Charge ...  

U.S. Energy Information Administration (EIA)

Guam Refinery Thermal Cracking/Visbreaking Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

193

Guam Refinery Thermal Cracking/Other (including Gas Oil ...  

U.S. Energy Information Administration (EIA)

Guam Refinery Thermal Cracking/Other (including Gas Oil) Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

194

U.S. Refinery Thermal Cracking, Fluid Coking Downstream Charge ...  

U.S. Energy Information Administration (EIA)

U.S. Refinery Thermal Cracking, Fluid Coking Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

195

Market Assessment of Refinery Outages Planned for October 2009 ...  

U.S. Energy Information Administration (EIA)

January fuel demand with availability of the refinery process units for distillate and gasoline production net of outages.

196

Virgin Islands Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

197

Midwest (PADD 2) Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

198

Puerto Rico Number and Capacity of Petroleum Refineries  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Idle refineries ...

199

Refineries are also indirectly exposed to forced processing rate ...  

U.S. Energy Information Administration (EIA)

Refineries receive crude oil from two sources: waterborne deliveries by ship and domestic production from California crude oil producing fields.

200

Potential Impacts of Reductions in Refinery Activity on Northeast ...  

U.S. Energy Information Administration (EIA)

receipt of crude oil at idled refineries require considerable modification before they can be used to receive products. Moreover, ...

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


201

Michigan Refinery Catalytic Hydrotreating, Kerosene/Jet Fuel ...  

U.S. Energy Information Administration (EIA)

Cat. Hydro.. Kerosene/Jet Fuel Downstream Charge Capacity (B/SD) Michigan Downstream Charge Capacity of Operable Petroleum Refineries ...

202

Colorado Refinery Catalytic Hydrotreating, Other/Residual Fuel Oil ...  

U.S. Energy Information Administration (EIA)

Colorado Refinery Catalytic Hydrotreating, Other/Residual Fuel Oil Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

203

Energy efficiency improvement and cost saving opportunities for petroleum refineries  

E-Print Network (OSTI)

Refinery Technology Profiles: Gasification and SupportingGasification.to be carried out. 18.5 Gasification Gasification provides

Worrell, Ernst; Galitsky, Christina

2005-01-01T23:59:59.000Z

204

Puerto Rico Refinery Thermal Cracking/Visbreaking Downstream ...  

U.S. Energy Information Administration (EIA)

Puerto Rico Refinery Thermal Cracking/Visbreaking Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

205

Puerto Rico Refinery Catalytic Hydrotreating, Kerosene/Jet Fuel ...  

U.S. Energy Information Administration (EIA)

Puerto Rico Refinery Catalytic Hydrotreating, Kerosene/Jet Fuel Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

206

Puerto Rico Refinery Catalytic Hydrocracking, Gas Oil Downstream ...  

U.S. Energy Information Administration (EIA)

Puerto Rico Refinery Catalytic Hydrocracking, Gas Oil Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

207

Refining District Oklahoma-Kansas-Missouri Refinery and ...  

U.S. Energy Information Administration (EIA)

Refining District Oklahoma-Kansas-Missouri Refinery and Blender Net Input of Fuel Ethanol (Thousand Barrels per Day)

208

New Jersey Refinery Catalytic Reforming/High Pressure Downstream ...  

U.S. Energy Information Administration (EIA)

New Jersey Refinery Catalytic Reforming/High Pressure Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

209

Arkansas Refinery Catalytic Reforming/High Pressure Downstream ...  

U.S. Energy Information Administration (EIA)

Arkansas Refinery Catalytic Reforming/High Pressure Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

210

U.S. Refinery Catalytic Hydrotreating, Heavy Gas Oil ...  

U.S. Energy Information Administration (EIA)

U.S. Refinery Catalytic Hydrotreating, Heavy Gas Oil Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

211

East Coast (PADD 1) Refinery Operable Atmospheric Crude Oil ...  

U.S. Energy Information Administration (EIA)

East Coast (PADD 1) Refinery Operable Atmospheric Crude Oil Distillation Capacity as of January 1 (Barrels per Calendar Day)

212

East Coast (PADD 1) Refinery Vacuum Distillation Downstream Charge ...  

U.S. Energy Information Administration (EIA)

East Coast (PADD 1) Refinery Vacuum Distillation Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

213

West Coast (PADD 5) Refinery Operable Atmospheric Crude Oil ...  

U.S. Energy Information Administration (EIA)

West Coast (PADD 5) Refinery Operable Atmospheric Crude Oil Distillation Capacity as of January 1 (Barrels per Calendar Day)

214

Puerto Rico Refinery Operable Atmospheric Crude Oil Distillation ...  

U.S. Energy Information Administration (EIA)

Puerto Rico Refinery Operable Atmospheric Crude Oil Distillation Capacity as of January 1 (Barrels per Calendar Day)

215

Rocky Mountain (PADD 4) Refinery Operable Atmospheric Crude Oil ...  

U.S. Energy Information Administration (EIA)

Rocky Mountain (PADD 4) Refinery Operable Atmospheric Crude Oil Distillation Capacity as of January 1 (Barrels per Calendar Day)

216

Gulf Coast (PADD 3) Refinery Operable Atmospheric Crude Oil ...  

U.S. Energy Information Administration (EIA)

Gulf Coast (PADD 3) Refinery Operable Atmospheric Crude Oil Distillation Capacity as of January 1 (Barrels per Calendar Day)

217

U.S. Refinery Operating Atmospheric Crude Oil Distillation ...  

U.S. Energy Information Administration (EIA)

U.S. Refinery Operating Atmospheric Crude Oil Distillation Capacity as of January 1 (Barrels per Calendar Day)

218

U.S. Refinery Operable Atmospheric Crude Oil Distillation Capacity ...  

U.S. Energy Information Administration (EIA)

U.S. Refinery Operable Atmospheric Crude Oil Distillation Capacity as of January 1 (Barrels per Calendar Day)

219

U.S. Refinery Operable Atmospheric Crude Oil Distillation Capacity ...  

U.S. Energy Information Administration (EIA)

U.S. Refinery Operable Atmospheric Crude Oil Distillation Capacity as of January 1 (Barrels per Stream Day)

220

U.S. Refinery Marketable Petroleum Coke Production Capacity as ...  

U.S. Energy Information Administration (EIA)

U.S. Refinery Marketable Petroleum Coke Production Capacity as of January 1 (Barrels per Stream Day)

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


221

Structural, energy and environmental aspects in Iranian oil refineries  

Science Conference Proceedings (OSTI)

Petroleum refineries extract and upgrade the valuable components of crude oil to produce a variety of marketable petroleum products. However Iranian refineries are old and their efficiency and structure do not satisfy demand of the country in which their ... Keywords: Iran, demand, energy, refinery

Sourena Sattari; Akram Avami

2008-02-01T23:59:59.000Z

222

Exxon reduces production at U. S. refineries  

SciTech Connect

This paper reports that Exxon Co. U.S.A. has trimmed output of its U.S. refineries by a combined 15% because of depressed margins on products markets. The company made the announcement last week as it began increasing crude runs at its 396,000 b/cd refinery at Baytown, Tex., on the Houston Ship Channel. Exxon trimmed Baytown crude runs late last month to manage feedstock inventories after a barge was rammed and sunk in the ship channel, briefly halting traffic. Most feedstock is delivered to the Baytown plant by water.

Not Available

1993-01-11T23:59:59.000Z

223

Monitoring and Management of Refinery Energy Consumption  

E-Print Network (OSTI)

Since 1972, the U.S. refining industry has made much progress in reducing energy consumption. Lately, falling energy prices have de-emphasized the need to appropriate new capital for additional energy conservation projects. One area neglected in most refineries is the need to monitor and manage the daily use of energy. Setting up an energy auditing system will tell management how well each unit in the refinery is being operated and can be used as a valuable tool in reducing energy costs. An example of an energy monitorirg and management system is discussed and illustrated with examples.

Pelham, R. O.; Moriarty, R. D.; Hudgens, P. D.

1986-06-01T23:59:59.000Z

224

Partners for Progress- A Utility Perspective  

E-Print Network (OSTI)

Central Power and Light Company, an Investor Owned Utility serving the greater part of South Texas, got the largest setback of its 75 year life during the 1980's when cogeneration hit home. It's no secret that the Texas Gulf Coast in 1980 was one of the greenest pastures in the country for the integration of cogeneration. Scattered throughout our coastal service area was a concentration of petrochemical plants and refineries placed like a row of dominoes waiting to be knocked over. These plants while operating in Texas were really doing business in a world market. If one company took advantage of a technology that could reduce its operation costs significantly, then very definite pressure was placed on all its competitors to follow suit in quick order or lose a share in the market. To make the story short, CPL lost over 250 MWs and eight of its largest customers in about a six year period to the implementation of cogeneration technology. By CPL I mean the stockholders who expected a dividend, the employees who faced possible layoffs and the remaining customers who faced the possibility of increased rates necessary to pick up embedded costs of the system. All these groups had a stake in turning the situation around. I have to add that even the customers who began to serve their own load had a stake in tile health of the utility with which they remained interconnected with and purchased standby and maintenance service from.

Pierce, C. S.

1990-06-01T23:59:59.000Z

225

CONTRACTOR PURCHASING SYSTEM REVIEWS  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Page 1 Page 1 APPENDIX C CONTRACTOR PURCHASING SYSTEM REVIEWS RISK ASSESSMENT MATRIX RISK CATEGORY PERFORMANCE SCHEDULE COST HIGH (3) --Performance data casts significant doubt on the ability of the system or key process ability to meet requirements. A major disruption is highly probable and the likelihood is that the supplier will not achieve the performance, schedule or cost objectives · Delinquent end item delivery · Poor or nonexistent internal audit/self governance · Failure to meet socio-economic subcontract goals · Frequent overruns · Inadequate incoming inspection methods · Frequent late supplier deliveries<80% · Inadequate lead time provided to ensure on-time delivery of critical items · Inadequate subcontract

226

Quick Guide: Power Purchase Agreements  

Energy.gov (U.S. Department of Energy (DOE))

Fact sheet explains on-site renewable power purchase agreements (PPAs) and includes which questions to ask when evaluating a PPA for a Federal renewable energy project.

227

U.S. Refinery Net Production  

U.S. Energy Information Administration (EIA)

Liquefied Refinery Gases: 11,903: 12,936: 13,591: 20,226: 24,599: 26,928: 2005-2013: ... Asphalt and Road Oil: 10,230: 9,328: 8,595: 9,973: 9,494: 9,914: 2005-2013 ...

228

Refinery siting workbook: appendices C to O  

Science Conference Proceedings (OSTI)

Applicable laws and permits available for the selection and building of petroleum refineries are enclosed. A glossary of pertinent terms is also included. References related to the National Environmental Policy Act, the Clean Air Act, the Federal Water Pollution Control Act, Resource Conservation and Recovery Act, Toxic Substance Control Act, and Wetlands and Coastal Zone are included. Permit information is also presented. (DC)

Not Available

1980-07-01T23:59:59.000Z

229

Refinery Investments and Future Market Incentives  

Reports and Publications (EIA)

Presentation given at the Annual NPRA Meeting that discusses factors affecting refinery investments. Refiners have plunged from a seeming "golden age" investment environment to a world with excess capacity, flat to declining demand, and weak margins. What is happening to refining investments in this turbulent and uncertain situation?

Information Center

2009-03-25T23:59:59.000Z

230

East Coast (PADD 1) Refinery Utilization and Capacity  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Totals may not equal sum ...

231

Refinery Operable Utilization Rate - U.S. Energy Information ...  

U.S. Energy Information Administration (EIA)

Process: Period: Download Series History: Definitions, Sources & Notes: Show Data By: Process: Area: Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 View History; U.S. 84.0 ...

232

Gulf Coast (PADD 3) Refinery Utilization and Capacity  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Totals may not equal sum ...

233

Indiana, Illinois and Kentucky Refinery Utilization and Capacity  

U.S. Energy Information Administration (EIA)

-No Data Reported; --= Not Applicable; NA = Not Available; W = Withheld to avoid disclosure of individual company data. Notes: Totals may not equal sum ...

234

Weekly U.S. Percent Utilization of Refinery Operable Capacity ...  

U.S. Energy Information Administration (EIA)

Year-Month Week 1 Week 2 Week 3 Week 4 Week 5; End Date Value End Date Value End Date Value End Date Value End Date Value; 1990-Nov: 11/02 : 84.0 : 11/09 : 83.0 : 11/16

235

Refinery utilization rates react to economics in 2011 - Today in ...  

U.S. Energy Information Administration (EIA)

Petroleum & Other Liquids. Crude oil, gasoline, heating oil, diesel, propane, and other liquids including biofuels and natural gas liquids. Natural Gas

236

East Coast (PADD 1) Percent Utilization of Refinery Operable ...  

U.S. Energy Information Administration (EIA)

75.9: 76.7: 70.0: 68.1: 57.8: 2012: 73.3: 77.0: 79.6: 80.9: 78.2: 82.7: 82.8: 87.5: 78.2: 80.9: 71.6: 80.1: 2013: 82.4: 72.4: 81.6: 87.7: 91.8: 91.0: 88.2-= No Data ...

237

Rocky Mountains (PADD 4) Percent Utilization of Refinery Operable ...  

U.S. Energy Information Administration (EIA)

75.3: 75.6: 74.6: 86.6: 89.7: 89.0: 91.1: 90.1: 81.0: 84.6: 83.9: 1990: 80.2: 80.5: 77.1: 78.7: 89.0: 89.5: 90.2: 92.2: 88.7: 79.2: 78.9: 77.5: 1991: 73.5: 78.5: 83.3 ...

238

West Coast (PADD 5) Percent Utilization of Refinery Operable ...  

U.S. Energy Information Administration (EIA)

75.2: 81.8: 81.7: 78.9: 82.3: 81.5: 82.3: 75.5: 75.5: 80.8: 1988: 82.2: 78.9: 82.5: 86.1: 85.0: 85.8: 85.8: 85.4: 85.8: 82.0: 84.6: 86.5: 1989: 88.3: 81.6: 84.1: 87.6 ...

239

Weekly East Coast (PADD 1) Percent Utilization of Refinery ...  

U.S. Energy Information Administration (EIA)

75.1 : 02/18 : 66.3 : 02/25 : 65.3 : 2011-Mar: 03/04 : 75.0 : 03/11 : 76.7 : 03/18 : 76.9 : 03/25 : 66.4 : 2011-Apr: 04/01 : 60.4 : 04/08 : 39.0 : 04/15 : 54.4 : 04/22 :

240

East Coast (PADD 1) Percent Utilization of Refinery Operable ...  

U.S. Energy Information Administration (EIA)

Decade Year-0 Year-1 Year-2 Year-3 Year-4 Year-5 Year-6 Year-7 Year-8 Year-9; 1980's: 75.4: 84.3: 86.6: 88.5: 87.2: 1990's: 83.6: 81.3: 81.5: 88.0: 89.3: 91.6: 89.8 ...

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


241

Weekly West Coast (PADD 5) Percent Utilization of Refinery ...  

U.S. Energy Information Administration (EIA)

75.3 : 11/18 : 77.5 : 11/25 : 75.2 : 2011-Dec: 12/02 : 81.3 : 12/09 : 73.6 : 12/16 : 81.3 : 12/23 : 81.9 : 12/30 : 84.2 : 2012-Jan: 01/06 : 83.0 : 01/13 : 82.3 : 01 ...

242

Green Power Network: Government Purchasing  

NLE Websites -- All DOE Office Websites (Extended Search)

Government Purchasing Government Purchasing Community Choice Aggregation Disclosure Policies Green Power Policies Net Metering Policies Government Purchasing A number of governments, at both the federal, state, and local level, have established targets or goals for the amount of green power that their facilities should use. At the federal level, the Energy Policy Act of 2005 requires that federal government purchase 3% renewable energy in fiscal years 2007-2009, 5% in fiscal years 2010-2012, and 7.5% in fiscal year 2013 and thereafter. In January 2007, Executive Order 13423 established that at least half of the mandated renewable energy come from generation built after January 1, 1999. State governments, including Connecticut, Illinois, Indiana, Maine, Maryland, Massachusetts, New York, Pennsylvania, and Wisconsin, have committed to purchasing green power.

243

Make the Most of Your Purchasing Power  

E-Print Network (OSTI)

The expansion and maintenance of building systems on educational campuses require huge financial expenditures. Public schools and colleges must make the most of each available dollar. The combination of effective building systems master planning and purchasing standardization program management (PSPM) maximizes purchasing power. Proper building systems master planning helps owners get what they want from buildings with greater opportunity for success. Master planning yields benefits in budgeting, staffing, equipment, and opportunities for standardization. PSPM is a strategy utilizing the “buy now-pay later” concept. Equipment is pre-selected and prepriced for projects as outlined in building systems master plans, and, frequently, in bond programs. Bulk purchasing and standardization, while normally thought of in reference to office and cleaning supplies, can also be applied to big-ticket items. The result is reduced first costs and a domino effect of other savings. Case studies will be presented from Texas school districts that demonstrate successful building systems master planning and PSPM programs. The authors' experience in assisting Texas ISDs implement these programs will also be shared.

Bristow, G.; Clendenin, M.; McClure, J. D.

2004-01-01T23:59:59.000Z

244

The New Rules for Purchasing Electric Power  

E-Print Network (OSTI)

"The creation of new rules for purchasing electric power is largely an outgrowth of several recent developments affecting the electric utility business: -deregulation has created a competitive business -demand side management has grown in stature to rival supply side challenges -power rates have become marketing tools These developments affect the industrial sector more than others, largely because of its size and electricity consumption per customer. Industry today sees these changes manifested in a variety of ways, several of which represent alternative power costs. These include: -conventional published tariffs -negotiated rates -utility incentive programs -cogeneration A key conclusion that may be drawn from these trends in that traditional barriers between utilities and industries are breaking down. Utilities are becoming increasingly marketing-oriented rather than sales-driven. Interestingly, the choices available can yield economic benefits on both sides of the meter. This is particularly evident in electric-intensive industries, such as chlor-alkali production or air separation. This paper reviews efforts by selected utilities to work jointly with their industrial customers in simultaneously addressing utility load shaping objectives and industry demands relative to quality of service and cost. Air separation and plastics fabrication are highlighted as two very different kinds of industries that have been addressed by utility-sponsored programs to date."

Stern, K.

1989-09-01T23:59:59.000Z

245

Federal Energy Management Program: Purchasing Renewable Power  

NLE Websites -- All DOE Office Websites (Extended Search)

Purchasing Renewable Power to someone by E-mail Share Federal Energy Management Program: Purchasing Renewable Power on Facebook Tweet about Federal Energy Management Program:...

246

Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Green Power Purchasing Green Power Purchasing Eligibility State Government Savings For Bioenergy Alternative Fuel Vehicles Hydrogen & Fuel Cells Buying & Making Electricity Water...

247

Austin - Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Power Marketing Administration Other Agencies You are here Home Savings Austin - Green Power Purchasing Austin - Green Power Purchasing Eligibility Local Government Savings...

248

High Performance Windows Volume Purchase: For Builders  

NLE Websites -- All DOE Office Websites (Extended Search)

For Builders to someone by E-mail Share High Performance Windows Volume Purchase: For Builders on Facebook Tweet about High Performance Windows Volume Purchase: For Builders on...

249

High Performance Windows Volume Purchase: For Manufacturers  

NLE Websites -- All DOE Office Websites (Extended Search)

For Manufacturers to someone by E-mail Share High Performance Windows Volume Purchase: For Manufacturers on Facebook Tweet about High Performance Windows Volume Purchase: For...

250

High Performance Windows Volume Purchase: Events  

NLE Websites -- All DOE Office Websites (Extended Search)

Events to someone by E-mail Share High Performance Windows Volume Purchase: Events on Facebook Tweet about High Performance Windows Volume Purchase: Events on Twitter Bookmark High...

251

High Performance Windows Volume Purchase: News  

NLE Websites -- All DOE Office Websites (Extended Search)

News to someone by E-mail Share High Performance Windows Volume Purchase: News on Facebook Tweet about High Performance Windows Volume Purchase: News on Twitter Bookmark High...

252

Green Power Purchasing (Maine) | Open Energy Information  

Open Energy Info (EERE)

Maine Name Green Power Purchasing Incentive Type Green Power Purchasing Applicable Sector State Government Eligible Technologies Biomass, Fuel Cells, Fuel Cells using Renewable...

253

Green Power Purchasing (Wisconsin) | Open Energy Information  

Open Energy Info (EERE)

Name Green Power Purchasing Incentive Type Green Power Purchasing Applicable Sector State Government Eligible Technologies Biomass, Fuel Cells using Renewable Fuels,...

254

Purchasing and procurement case studies | ENERGY STAR  

NLE Websites -- All DOE Office Websites (Extended Search)

Purchase energy-saving products Purchasing and procurement case studies Secondary menu About us Press room Contact Us Portfolio Manager Login Facility owners and managers...

255

PAD District / Refinery Location Total Atmospheric Distillation  

U.S. Energy Information Administration (EIA) Indexed Site

Operable Date of Last Operation Date Shutdown Table 11. New, Shutdown and Reactivated Refineries During 2012 a b REACTIVATED PAD District I 185,000 366,700 Monroe Energy LLC Trainer, PA 185,000 366,700 09/12 c SHUTDOWN PAD District I 80,000 47,000 ChevronUSA Inc Perth Amboy, NJ 80,000 47,000 03/08 07/12 PAD District III 16,800 19,500 Western Refining Southwest Inc Bloomfield, NM 16,800 19,500 12/09 11/12 PAD District VI 500,000 1,086,000 Hovensa LLC Kingshill, VI 500,000 1,086,000 02/12 02/12 a b bbl/cd=Barrels per calendar day. bbl/sd=Barrels per stream day. Sources: Energy Information Administration (EIA) Form EIA-810, "Monthly Refinery Report" and Form EIA-820, "Annual Refinery Report." c Formerly owned by ConocoPhillips Company.

256

GreenHunter Biodiesel Refinery Grand Opening | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

GreenHunter Biodiesel Refinery Grand Opening GreenHunter Biodiesel Refinery Grand Opening GreenHunter Biodiesel Refinery Grand Opening June 2, 2008 - 12:51pm Addthis Remarks as Prepared for (Acting) Deputy Secretary Kupfer Today, Acting Deputy Secretary Jeffrey Kupfer delivered remarks at the launch of GreenHunter Energy's biodiesel refinery, which will be the nation's single largest biodiesel refinery, producing 105 million gallons of "white-water" B100 biodiesel per year. Thank you Gary. I'm pleased to join with Governor Perry, Congressmen Green and Lampson, and Mayor Garcia in celebrating this important occasion. Today, as we open the nation's largest biodiesel refinery, we reach another milestone in our effort to make America more energy secure. As you know, global energy demand is surging. We must act swiftly and aggressively to

257

Economic impact analysis for the petroleum refineries NESHAP. Final report  

Science Conference Proceedings (OSTI)

An economic analysis of the industries affected by the Petroleum Refineries National Emmissions Standard for Hazardous Air Pollutants (NESHAP) was completed in support of this standard. The industry for which economic impacts was computed was the petroleum refinery industry. Affected refineries must reduce HAP emissions by the level of control required in the standard. Several types of economic impacts, among them price product changes, output changes, job impacts, and effects on foriegn trade, were computed for the selected regulatory alternative.

NONE

1995-08-01T23:59:59.000Z

258

U.S. Refinery Thermal Cracking, Other (including Gas Oil ...  

U.S. Energy Information Administration (EIA)

U.S. Refinery Thermal Cracking, Other (including Gas Oil) Downstream Charge Capacity as of January 1 (Barrels per Stream Day)

259

Summary of Market Assessment of Planned Refinery Outages  

U.S. Energy Information Administration (EIA)

Home > Petroleum > Analysis > Summary of Market Assessment of Planned Refinery ... As required under Section 804 of the Energy Independence and Security Act of 2007 ...

260

U.S. refineries and blenders produced record amounts of ...  

U.S. Energy Information Administration (EIA)

Because of its chemical composition, crude oil run through a refinery typically yields roughly twice as much motor gasoline as distillate fuels.

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


261

Directory of Operable Petroleum Refineries on Tables 38 and 39  

U.S. Energy Information Administration (EIA)

Directory of Operable Petroleum Refineries on Tables 38 and 39 Refiner State(s)aRefiner State(s)a.....Age Refining Inc ...

262

Environmentally advanced refinery nears start-up in Germany  

SciTech Connect

Mitteldeutsche Erdoel-Raffinerie GmbH (Mider), is building a 170,000 b/d, grassroots refinery in Leuna, Germany. The refinery is scheduled to start up in third quarter of this year. At the heart of the new refinery is a new technology called progressive distillation. Other major units include: vacuum distillation, catalytic reforming, alkylation, visbreaking, fluid catalytic cracking (FCC), and hydrodesulfurization (HDS). In addition, an existing partial oxidation (POX)/methanol production unit will be integrated with the new refinery. The paper describes the plant and its major processes.

Rhodes, A.K.

1997-03-17T23:59:59.000Z

263

Energy efficiency improvement and cost saving opportunities for petroleum refineries  

E-Print Network (OSTI)

are also listed. The Energy Guide draws upon the experiencesmanagement programs. This Energy Guide describes researchpetroleum refineries. This Energy Guide introduces energy

Worrell, Ernst; Galitsky, Christina

2005-01-01T23:59:59.000Z

264

Gulf Coast (PADD 3) Refinery Grade Butane Stocks at Bulk ...  

U.S. Energy Information Administration (EIA)

Gulf Coast (PADD 3) Refinery Grade Butane Stocks at Bulk Terminals (Thousand Barrels) Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec; 2005: 935: ...

265

EIA Energy Kids - Carson Refinery - Energy Information Administration  

U.S. Energy Information Administration (EIA)

Hydrogen. Recent Statistics ... and then distributed to gas stations all over Los Angeles and Southern ... you are probably filling up with gas from the Carson refinery.

266

U.S. Refinery Operable Capacity is Updated  

U.S. Energy Information Administration (EIA)

Released: March 28, 2012 Notice: Reported refinery operable capacity data shown in the Weekly Petroleum Status Report (WPSR) for the week-ended March 23, 2012, has ...

267

U.S. Refinery Catalytic Hydrotreating, Kerosene/Jet Fuel ...  

U.S. Energy Information Administration (EIA)

Cat. Hydro.. Kerosene/Jet Fuel Downstream Charge Capacity (B/SD) U.S. Downstream Charge Capacity of Operable Petroleum Refineries ...

268

Market Assessment of Refinery Outages Planned for March 2010 ...  

U.S. Energy Information Administration (EIA)

DOE/EIA-0641(2010)/1 Market Assessment of Refinery Outages Planned for March 2010 through June 2010 March 2010 Energy Information Administration

269

Gas Purchasing Strategies for the '90s  

E-Print Network (OSTI)

The purpose of my talk today is to: 1. provide a brief summary of the structural changes which have occurred in the natural gas market over the last several years 2. discuss some of the effects of these changes and some of the potential issues that could result from these changes, and 3. finally to offer some advice on how to develop an effective strategy for purchasing natural gas in the '90s given these changes. To set the stage for my talk today, I need to give you some of the more significant facts relative to our Company and its use of natural gas. Houston Lighting & Power Company (HL&P) is an investor-owned electric utility which serves the city of Houston and the surrounding area. This area is highly industrialized and home to a significant portion of the nation's refining in petrochemical capacity. HL&P has 12,855 MW of generating capacity and sells approximately 25% of Texas' total electric utility sales. As a gas purchaser, HL&P is situated in "pipeline alley" and now has pipeline connections to eight different pipelines and, as a result, access to virtually every major pipeline system that operates within the state of Texas.

Schuler, S. H.

1989-09-01T23:59:59.000Z

270

"Table A46. Total Expenditures for Purchased Electricity, Steam, and Natural"  

U.S. Energy Information Administration (EIA) Indexed Site

6. Total Expenditures for Purchased Electricity, Steam, and Natural" 6. Total Expenditures for Purchased Electricity, Steam, and Natural" " Gas by Type of Supplier, Census Region, Industry Group, and Selected Industries," 1991 " (Estimates in Million Dollars)" ,," Electricity",," Steam",," Natural Gas" ,,"-","-----------","-","-----------","-","------------","-","RSE" "SIC",,"Utility","Nonutility","Utility","Nonutility","Utility","Transmission","Other","Row" "Code(a)","Industry Groups and Industry","Supplier(b)","Supplier(c)","Supplier(b)","Supplier(c)","Supplier(b)","Pipelines","Supplier(d)","Factors"

271

"Table A48. Total Expenditures for Purchased Electricity, Steam, and Natural"  

U.S. Energy Information Administration (EIA) Indexed Site

8. Total Expenditures for Purchased Electricity, Steam, and Natural" 8. Total Expenditures for Purchased Electricity, Steam, and Natural" " Gas by Type of Supplier, Census Region, and Economic Characteristics of the" " Establishment, 1991" " (Estimates in Million Dollars)" ," Electricity",," Steam",," Natural Gas" ,"-","-----------","-","-----------","-","------------","-----------","RSE" " ","Utility","Nonutility","Utility","Nonutility","Utility","Transmission","Other","Row" "Economic Characteristics(a)","Supplier(b)","Supplier(c)","Supplier(b)","Supplier(c)","Supplier(b)","Pipelines","Supplier(d)","Factors"," "

272

Purchasing Renewable Energy: A Guidebook for Federal Agencies  

E-Print Network (OSTI)

LBNL-46766 Purchasing Renewable Energy: A Guidebook for Federal Agencies William Golove, Mark://eetd.lbl.gov/EA/EMP/ The work described in this study was funded by the Assistant Secretary of Energy Efficiency and Renewable programs by paying a premium to have renewable energy supplied to the grid by their local utility. Whether

273

When was the last refinery built in the United States? - FAQ ...  

U.S. Energy Information Administration (EIA)

When was the last refinery built in the United States? There were a total of 143 operable petroleum refineries in the United States as of January 1, 2013.

274

www.ResponsiblePurchasing.org Sustainable Purchasing 101  

E-Print Network (OSTI)

.ResponsiblePurchasing.org EPPs are... · Made with recycled content · Highly energy efficient · Designed to be long lasting · Creating local "green collar" jobs · Securing green building (LEED) credits · Life-cycle cost savings 8 OSU-Off Compostable food containers with "Teflon" coating Worshipping False Labels Lesser of Two Evils Organic

Escher, Christine

275

Poland petroleum refinery sludge lagoon demonstration project  

SciTech Connect

The US Department of Energy and the Institute for Ecology of Industrial Area have been working together to develop mutually beneficial, cost-effective environmental remediation technologies such as the demonstration of bioremediation techniques for the clean up of acidic petroleum sludge impacted soils at an oil refinery in southern Poland. After an expedited site characterization, treatability study, and a risk assessment study, a remediation strategy was devised. The waste material was composed primarily of high molecular weight paraffinic and polynuclear aromatic hydrocarbons. A biopile design which employed a combination of passive and active aeration in conjunction with nutrient and surfactant application as used to increase the biodegradation of the contaminants of concern.

Altman, D.J.

2000-05-05T23:59:59.000Z

276

Organic Rankine Cycle Systems for Waste Heat Recovery in Refineries and Chemical Process Plants  

E-Print Network (OSTI)

The design of a low temperature Rankine cycle system using R-113 working fluid for recovery and conversion of process waste heat is described for typical applications in oil refineries and chemical plants. The system is designed to produce electric power from waste heat available in a temperature range from 180oF to 400oF. The design of a new ORC turbo generator uniquely adapted to applications of this type is presented. The unit has been designed for power outputs from 3/4 to 2 1/2 MW and turbine inlet temperatures from 170 to 260oF. The machine design has eliminated the need for shaft seals, shaft couplings and the usual lube oil console normally required for turbine-generator units. Results of prototype tests of a 1 MW unit are presented. A product package and recommended division of responsibilities between purchaser, A&E company and supplier is presented for installations in refineries and process plants. The product package covers the electrical power range from 3/4 to 5 MW and waste heat streams from 20 to 130 million BTU/hr.

Meacher, J. S.

1981-01-01T23:59:59.000Z

277

The potential application of fuel cell cogeneration systems in petroleum refineries. [Phosphoric acid, molten carbonate and solid oxide fuel cells  

Science Conference Proceedings (OSTI)

The market potential for fuel cell cogeneration systems within the petroleum refinery industry is evaluated. Phosphoric acid (PAFC), molten carbonate (MCFC), and solid oxide (SOFC) fuel cells were considered. Conventional competitive systems now available including purchased power plus boiler-generated steam, gas turbine combined cycle, and a relatively new coke fluidized bed-boiler were characterized. Refineries use large quantities of steam at pressures ranging from about 15 to 650 psig. PAFCs can only meet a limited number of steam requirements because of their relatively low operating temperature. The high temperature MCFC and SOFC are technically much more attractive for this application. However, current estimates of their capital costs are too large to make the technologies competitive. The capital costs of MCFCs and SOFCs would have to decrease approx.50% from their present estimated $1300/kWe. If costs could be decreased to give a 10% energy cost advantage to fuel cells, the industry projects that fuel cells might supply about 300 MWe by the year 2000, and modules in the 5- to 20-MWe size would be of interest. The market opportunities in refineries are varied - the industry is large, each plant is unique, thermal energy consumption is large, and both domestic and international competitiveness is intense. 10 refs., 26 figs., 17 tabs.

Altseimer, J.H.; Roach, F.; Anderson, J.M.; Krupka, M.C.

1987-08-01T23:59:59.000Z

278

The Use of Oil Refinery Wastes as a Dust Suppression Surfactant for Use in Mining  

Science Conference Proceedings (OSTI)

In this research, the suitability of a selection of petroleum refinery wastes as a dust suppressant were examined. Dust is a significant problem in surface and underground mining mainly because of its adverse effects on human health and machinery. Hence, dust control and suppression is a vital part of mine planning for mining engineers. Water is the oldest and the cheapest suppressant in dealing with the mine dusts. However, surfactant use has recently been used for a wider range of applications in the mining industry. In order to carry out laboratory experiments, a dust chamber was designed and manufactured. The chamber has an inlet for coal dust entrance and a nozzle for spraying water and the oil refinery wastes. Water and the surfactants were mixed at various ratios and then sprayed onto the coal dusts within the cell. Dust concentration was measured systematically to determine the effects of surfactant containing solution on the coal dust and the data obtained by the measurements were analyzed. The results showed that the oil refinery wastes could be used as a dust suppressant, which may create an economical utilization for the wastes concerned.

Dixon-Hardy, D.W.; Beyhan, S.; Ediz, I.G.; Erarslan, K. [University of Leeds, Leeds (United Kingdom)

2008-10-15T23:59:59.000Z

279

UES - Renewable Energy Credit Purchase Program | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

UES - Renewable Energy Credit Purchase Program UES - Renewable Energy Credit Purchase Program UES - Renewable Energy Credit Purchase Program < Back Eligibility Commercial Residential Savings Category Bioenergy Home Weatherization Commercial Weatherization Solar Lighting Windows, Doors, & Skylights Buying & Making Electricity Energy Sources Water Heating & Cooling Swimming Pool Heaters Water Heating Commercial Heating & Cooling Heating Wind Maximum Rebate Up-front incentives can pay for no more than 50% of the cost Residential solar water heating and space heating: $1,750 Small commercial solar water heating and space heating: $200,000 Program Info Start Date 2004 State Arizona Program Type Utility Rebate Program Rebate Amount PV incentives may be de-rated based on expected performance Residential PV: Funding has been depleted

280

Dominion Virginia Power - Solar Purchase Program | Open Energy Information  

Open Energy Info (EERE)

Dominion Virginia Power - Solar Purchase Program Dominion Virginia Power - Solar Purchase Program No revision has been approved for this page. It is currently under review by our subject matter experts. Jump to: navigation, search Summary Quantitative Data Last modified on June 21, 2013. Financial Incentive Program Place Virginia Name Dominion Virginia Power - Solar Purchase Program Incentive Type Performance-Based Incentive Applicable Sector Agricultural, Commercial, Fed. Government, Institutional, Local Government, Multi-Family Residential, Nonprofit, Residential, State Government Eligible Technologies Photovoltaics Active Incentive Yes Implementing Sector Utility Energy Category Renewable Energy Incentive Programs Amount $0.15/kWh Eligible System Size Residential: 20 kW Nonresidential: 50 kW Start Date 6/20/2013

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


281

TEP - Renewable Energy Credit Purchase Program | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

TEP - Renewable Energy Credit Purchase Program TEP - Renewable Energy Credit Purchase Program TEP - Renewable Energy Credit Purchase Program < Back Eligibility Residential Savings Category Solar Buying & Making Electricity Heating & Cooling Commercial Heating & Cooling Heating Water Heating Maximum Rebate Residential PV: 50% of system cost. Systems greater than 30 kW DC will receive incentives on the first 30 kW DC only. Residential Solar Water Heating and Space Heating: $1,750 Program Info Funding Source RES Surchage State Arizona Program Type Utility Rebate Program Rebate Amount Incentives for PV may be de-rated based on expected performance Residential grid-tied PV: $0.10/W-DC Residential Solar Water Heating and Space Heating: $0.40/kWh-equivalent Provider Tucson Electric Power '''''Note: The Arizona Corporation Commission (ACC) recently approved

282

Energy Department Receives EPA Award for Top Green Power Purchase |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Energy Department Receives EPA Award for Top Green Power Purchase Energy Department Receives EPA Award for Top Green Power Purchase Energy Department Receives EPA Award for Top Green Power Purchase September 24, 2013 - 12:19pm Addthis The Energy Department announced today that it has received a 2013 Green Power Leadership Award from the U.S. Environmental Protection Agency (EPA). The annual awards recognize the country's leading green power consumers for their commitment and contribution to helping advance the development of the nation's voluntary green power market. EPA presented the Energy Department with the award at an event held in conjunction with the 2013 Renewable Energy Markets Conference in Austin, Texas, on September 23, 2013. The Department was one of only eight organizations nationwide to receive a Leadership Award for utilization of green power. The award recognizes EPA

283

Energy Department Receives EPA Award for Top Green Power Purchase |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Energy Department Receives EPA Award for Top Green Power Purchase Energy Department Receives EPA Award for Top Green Power Purchase Energy Department Receives EPA Award for Top Green Power Purchase September 24, 2013 - 12:19pm Addthis The Energy Department announced today that it has received a 2013 Green Power Leadership Award from the U.S. Environmental Protection Agency (EPA). The annual awards recognize the country's leading green power consumers for their commitment and contribution to helping advance the development of the nation's voluntary green power market. EPA presented the Energy Department with the award at an event held in conjunction with the 2013 Renewable Energy Markets Conference in Austin, Texas, on September 23, 2013. The Department was one of only eight organizations nationwide to receive a Leadership Award for utilization of green power. The award recognizes EPA

284

Summary of Market Assessment of Upcoming Planned Refinery Outages  

Gasoline and Diesel Fuel Update (EIA)

Summary of Market Assessment of Upcoming Planned Refinery Outages Summary of Market Assessment of Upcoming Planned Refinery Outages Summary of Market Assessment of Upcoming Planned Refinery Outages Market Assessment of Upcoming Planned Refinery Outages, December 2008 - March 2009 reviews planned U.S. refinery outages from December 2008 though March 2009 in order to identify any regions where outages might create enough supply pressure to impact prices significantly. As required under Section 804 of the Energy Independence and Security Act of 2007 (Pub. L. 110-140), this report reviews the supply implications of planned refinery outages for December 2008 through March 2009, which covers the winter period when demand for distillate fuels (diesel and heating oil) is high. As a result, emphasis in this report is on distillate rather than gasoline. Refinery outages are the result of planned maintenance and unplanned outages. Maintenance is usually scheduled during the times when demand is lowest - in the first quarter and again in the fall. Unplanned outages, which occur for many reasons including mechanical failures, fires, and flooding, can occur at any time.

285

Public Sector Leadership: Government Purchasing of Energy-efficient  

NLE Websites -- All DOE Office Websites (Extended Search)

Public Sector Leadership: Government Purchasing of Energy-efficient Public Sector Leadership: Government Purchasing of Energy-efficient Products to Save Energy and "Pull" the Market Title Public Sector Leadership: Government Purchasing of Energy-efficient Products to Save Energy and "Pull" the Market Publication Type Conference Proceedings Year of Publication 2004 Authors Coleman, Philip, and Jeffrey P. Harris Conference Name Kuwait ASST Workshop on Energy Conservation in Buildings Series Title Energy Efficiency for Fuelling the World Date Published 01/2004 Conference Location Kuwait Abstract In most countries, government spending represents between 10% and 25% of total economic activity, with the national government generally accounting for the largest portion. Consequently, governments' spending can exert a strong influence on the markets for the products and services they purchase, especially when this procurement is concerted. In the last decade, several governments have instituted programs designed to direct their purchasing of energy-using products to the more efficient models on the market. This has two impacts: It provides substantial direct savings to the government on its utility bills while also helping to increase the availability and lower the prices of these more efficient models for all buyers.

286

"Table A38. Total Expenditures for Purchased Electricity, Steam, and Natural Gas"  

U.S. Energy Information Administration (EIA) Indexed Site

8. Total Expenditures for Purchased Electricity, Steam, and Natural Gas" 8. Total Expenditures for Purchased Electricity, Steam, and Natural Gas" " by Type of Supplier, Census Region, Census Division, Industry Group," " and Selected Industries, 1994" " (Estimates in Million Dollars)" ,," Electricity",," Steam" ,,,,,,"RSE" "SIC",,"Utility","Nonutility","Utility","Nonutility","Row" "Code(a)","Industry Group and Industry","Supplier(b)","Supplier(c)","Supplier(b)","Supplier(c)","Factors" ,,"Total United States"

287

Master development plan for the Cartagena Refinery. Export trade information  

Science Conference Proceedings (OSTI)

This study, conducted by the M.W. Kellogg Company, was funded by the U.S. Trade and Development Agency on behalf of ECOPETROL, Colombia`s national oil company. The objective of the study was to investigate technical, economic, and environmental issues that challenge the Cartagena Refinery. The study also recommends the most attractive options for the refinery to improve profitability. The document is divided into the following sections: (1) Executive Summary; (2) Market Survey; (3) Refinery Configuration; (4) Economic Evaluation; (5) Other Technical/Strategic Considerations; (6) Appendix.

NONE

1996-09-01T23:59:59.000Z

288

Purchase Obligations, Earnings Persistence and Stock Returns  

E-Print Network (OSTI)

Power purchase, natural gas supply and transportation, andsupply agreements Ball Corp • Aluminum, steel, plastic resin, other direct materials, natural gas

Lee, Kwang June

2010-01-01T23:59:59.000Z

289

Table 7.3 Average Prices of Purchased Electricity, Natural Gas, and Steam, 2010;  

U.S. Energy Information Administration (EIA) Indexed Site

3 Average Prices of Purchased Electricity, Natural Gas, and Steam, 2010; 3 Average Prices of Purchased Electricity, Natural Gas, and Steam, 2010; Level: National and Regional Data; Row: NAICS Codes; Column: Supplier Sources of Purchased Electricity, Natural Gas, and Steam; Unit: U.S. Dollars per Physical Units. Electricity Components Natural Gas Components Steam Components Electricity Natural Gas Steam Electricity from Sources Natural Gas from Sources Steam from Sources Electricity from Local Other than Natural Gas from Local Other than Steam from Local Other than NAICS Total Utility(b) Local Utility(c) Total Utility(b) Local Utility(c) Total Utility(b) Local Utility(c) Code(a) Subsector and Industry (kWh) (kWh) (kWh) (1000 cu ft) (1000 cu ft) (1000 cu ft) (million Btu)

290

Table 7.7 Quantity of Purchased Electricity, Natural Gas, and Steam, 2010;  

U.S. Energy Information Administration (EIA) Indexed Site

7 Quantity of Purchased Electricity, Natural Gas, and Steam, 2010; 7 Quantity of Purchased Electricity, Natural Gas, and Steam, 2010; Level: National and Regional Data; Row: NAICS Codes; Column: Supplier Sources of Purchased Electricity, Natural Gas, and Steam; Unit: Physical Units or Btu. Electricity Components Natural Gas Components Steam Components Electricity Natural Gas Steam Electricity from Sources Natural Gas from Sources Steam from Sources Electricity from Local Other than Natural Gas from Local Other than Steam from Local Other than NAICS Total Utility(b) Local Utility(c) Total Utility(b) Local Utility(c) Total Utility(b) Local Utility(c) Code(a) Subsector and Industry (million kWh) (million kWh) (million kWh) (billion cu ft) (billion cu ft)

291

DOE Indian Energy Purchase Preference Policy Guidance | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Indian Energy Purchase Preference Policy Guidance DOE Indian Energy Purchase Preference Policy Guidance PDFFINAL DOE Indian Energy purchase preference policy guidance.pdf More...

292

Motiva Enterprises Refinery Expansion Groundbreaking | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Enterprises Refinery Expansion Groundbreaking Enterprises Refinery Expansion Groundbreaking Motiva Enterprises Refinery Expansion Groundbreaking December 10, 2007 - 4:44pm Addthis Remarks as Prepared for Secretary Bodman Thank you, Bill. It's good to see Congressman Poe, Rob Routs, Mr. Al-Khayyal and Mayor Prince here. Thank you all for inviting me to be part of this occasion. In 1901 Texas wildcatters struck oil near here at a place called Spindletop, setting off the Texas Oil Boom. Like the California Gold Rush some 50 years before, the Texas Oil Boom helped to build America. People moved across the country in search of prosperity. To achieve it, they needed to develop new technologies and build new infrastructure like the original parts of the Port Arthur refinery, which opened here in 1903. As America's need for energy expanded as our demand for oil and gas

293

Secretary Bodman Tours Refinery and Calls for More Domestic Refining  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Tours Refinery and Calls for More Domestic Tours Refinery and Calls for More Domestic Refining Capacity Secretary Bodman Tours Refinery and Calls for More Domestic Refining Capacity May 18, 2006 - 10:43am Addthis Highlights President Bush's Four-Point Plan to Combat High Energy Prices PORT ARTHUR, TX - Secretary of Energy Samuel W. Bodman today renewed the call for expanded oil refining capacity in the United States and discussed additional steps the Department of Energy (DOE) is taking to prepare for the upcoming hurricane season. Secretary Bodman made the statements after touring the Motiva Refinery in Port Arthur, Texas. "We need a more robust energy sector; and one way to do that is to strengthen and expand our domestic oil refining capacity. We're hopeful that Motiva will continue to work to expand their capacity to 600,000

294

Rocky Mountain (PADD 4) Refinery and Blender Net Production of ...  

U.S. Energy Information Administration (EIA)

Rocky Mountain (PADD 4) Refinery and Blender Net Production of Normal Butane (Thousand Barrels) Decade Year-0 Year-1 Year-2 Year-3 Year-4 Year-5 Year-6 Year-7 Year-8

295

,"U.S. Refinery Crude Oil Input Qualities"  

U.S. Energy Information Administration (EIA) Indexed Site

,,"(202) 586-8800",,,"7242013 11:46:42 PM" "Back to Contents","Data 1: U.S. Refinery Crude Oil Input Qualities" "Sourcekey","MCRS1US2","MCRAPUS2" "Date","U.S. Sulfur...

296

Coal Use in Petroleum Refineries -- Opportunities and Issues  

Science Conference Proceedings (OSTI)

This report is a brief review of the technologies and key issues involved in considering the use of coal as a replacement, supplemental, or additional fuel in petroleum refineries.

2002-10-21T23:59:59.000Z

297

World Energy Projection System Plus Model Documentation: Refinery Model  

Reports and Publications (EIA)

This report documents the objectives, analytical approach and development of the World Energy Projection System Plus (WEPS+) Refinery Model. It also catalogues and describes critical assumptions, computational methodology, parameter estimation techniques, and model source code.

Adrian Geagla

2011-10-04T23:59:59.000Z

298

Rocky Mountain (PADD 4) Foreign Crude Oil Refinery Receipts by ...  

U.S. Energy Information Administration (EIA)

Rocky Mountain (PADD 4) Foreign Crude Oil Refinery Receipts by Tank Cars (Rail) (Thousand Barrels) Decade Year-0 Year-1 Year-2 Year-3 Year-4 Year-5 Year-6 Year-7 Year-8

299

U.S. Petroleum Coke Consumed at Refineries (Thousand Barrels)  

U.S. Energy Information Administration (EIA)

U.S. Petroleum Coke Consumed at Refineries (Thousand Barrels) Decade Year-0 Year-1 Year-2 Year-3 Year-4 Year-5 Year-6 Year-7 Year-8 Year-9; 1980's: ...

300

U.S. Petroleum Coke Stocks at Refineries (Thousand Barrels)  

U.S. Energy Information Administration (EIA)

U.S. Petroleum Coke Stocks at Refineries (Thousand Barrels) Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec; 1993: 10,747: 11,072: 11,444: ...

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


301

Engineering firm has designed refinery of the future  

SciTech Connect

Four years ago, JGC Corp. organized a project team called ``Refinery Engineering for the Future in the Twenty-First Century,`` or REF-21. The purpose of the team was to forecast the environment facing the refining industry in Japan, long-range energy supply and demand, population and economic growth, traffic system trends, and technology and science progress through the middle of the twenty-first century. The REF-21 team also was charged with developing a conceptual design for the future refinery. The team proposed four types of configurations for the so-called new-generation refineries. These schemes included some new technologies that it deemed commercializable by 2000. JGC evaluated these new-generation refinery schemes in terms of overall yields, energy efficiencies, emissions, and economics, as compared with existing refineries. JGC also has developed an amenity design program (ADP), and is applying it to a refinery in Japan to produce a new-concept operation center. Through amenity design, JGC intends to improve the operating environment for employees in order to enhance overall productivity.

Inomata, Makoto; Sato, Kyohei; Yamada, Yu; Sasaki, Hajime [JGC Corp., Yokohama (Japan)

1997-04-28T23:59:59.000Z

302

Utility to Purchase Electricity from Innovative DOE-Supported...  

NLE Websites -- All DOE Office Websites (Extended Search)

In a non-carbon-capture plant, the syngas is cleaned to remove impurities and sent to a gas turbine where it undergoes combustion to produce electricity. The hot flue gas from...

303

Alaska North Slope First Purchase Price (Dollars per Barrel)  

U.S. Energy Information Administration (EIA)

Referring Pages: Domestic Crude Oil First Purchase Prices by Area; Domestic Crude Oil First Purchase Prices for Selected Crude Streams

304

U.S. Refinery Net Production  

U.S. Energy Information Administration (EIA) Indexed Site

2007 2008 2009 2010 2011 2012 View 2007 2008 2009 2010 2011 2012 View History Total 5,383,494 5,119,100 4,676,865 4,568,301 4,484,600 4,395,128 2005-2012 Liquefied Refinery Gases 238,904 230,431 227,470 240,454 225,992 230,413 2005-2012 Ethane/Ethylene 7,323 6,671 7,069 7,228 7,148 6,597 2005-2012 Ethane 5,145 4,608 5,229 5,200 5,105 4,835 2005-2012 Ethylene 2,178 2,063 1,840 2,028 2,043 1,762 2005-2012 Propane/Propylene 205,179 190,020 196,011 204,223 201,492 202,309 2005-2012 Propane 120,596 114,268 106,177 102,913 98,508 100,933 2005-2012 Propylene 84,583 75,752 89,834 101,310 102,984 101,376 2005-2012 Normal Butane/Butylene 24,285 30,887 24,148 30,281 17,449 20,580 2005-2012 Normal Butane 25,715 33,092 25,825 32,094 19,263 22,965 2005-2012

305

PAD District / Refinery Location Total Atmospheric Distillation  

U.S. Energy Information Administration (EIA) Indexed Site

of Last of Last Operation Date Shutdown Table 13. Refineries Permanently Shutdown By PAD District Between January 1, 1990 and January 1, 2013 PAD District I 542,450 GNC Energy Corp Greensboro, NC 3,000 0 a Primary Energy Corp Richmond, VA 6,100 0 a Saint Mary's Refining Co Saint Mary's, WV 4,000 4,480 02/93 03/93 Cibro Refining Albany, NY 41,850 27,000 07/93 09/93 Calumet Lubricants Co LP Rouseville, PA 12,800 26,820 03/00 06/00 Young Refining Corp. Douglasville, GA 5,400 0 07/04 07/04 Sunoco Inc Westville, NJ 145,000 263,000 11/09 02/10 Western Refining Yorktown Inc Yorktown, VA 66,300 182,600 09/10 12/11 Sunoco Inc Marcus Hook, PA 178,000 278,000 12/11 12/11 ChevronUSA Inc Perth Amboy, NJ 80,000 47,000 03/08 07/12 PAD District II 460,315 Coastal Refining & Mktg El Dorado, KS 0 20,000 b Intercoastal Energy Svcs

306

Green Power Purchase Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Green Power Purchase Plan Green Power Purchase Plan Green Power Purchase Plan < Back Eligibility State Government Savings Category Bioenergy Alternative Fuel Vehicles Hydrogen & Fuel Cells Water Solar Buying & Making Electricity Home Weatherization Wind Program Info State Connecticut Program Type Green Power Purchasing Provider Department of Energy and Environmental Protection In April 2004, Connecticut's governor signed an executive order directing state-government agencies and universities to purchase an increasing amount of electricity generated by renewable resources. Under terms of the order, the state government has a goal to increase "Class I" renewable energy purchases to 20% of electricity used in 2010, 50% in 2020 and 100% in 2050. The order also authorizes the use of savings generated by state energy

307

Electronic bidding in Brazilian public administration purchases  

Science Conference Proceedings (OSTI)

This paper intended to evaluate the determinative factors in the price variation of the purchases through e-bidding in Brazil. A survey in 195 e-bidding winners was carried through to test the relation between the price variation and representative ... Keywords: Brazil, asset specificity, auction theory, bids, central government, e-bidding, e-finance, electronic bidding, electronic finance, multiple regression, online bidding, price variations, public administration, public expenditure, purchases, purchasing, suppliers, transaction costs, transaction frequency

Evandro Rodrigues De Faria; Marco Aurelio Marques Ferreira; Lucas Maia Dos Santos

2010-10-01T23:59:59.000Z

308

Idaho Public Utilities Commission Approves Neal Hot Springs Power...  

Open Energy Info (EERE)

Number NA DOI Not Provided Check for DOI availability: http:crossref.org Online Internet link for Idaho Public Utilities Commission Approves Neal Hot Springs Power Purchase...

309

City of Tallahassee Utilities- Residential Energy Efficiency Rebate Program  

Energy.gov (U.S. Department of Energy (DOE))

City of Tallahassee Utilities (CTU) offers residential customers rebates for the purchase of ENERGY STAR appliances and heating and cooling equipment. Qualifying appliances include refrigerators,...

310

Mandatory Utility Green Power Option | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

to purchase green power from any licensed retail supplier. For information about the green power utilities and suppliers in Virginia, see the Department of Energy, Energy...

311

Green Power Purchasing Commitment | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Green Power Purchasing Commitment Green Power Purchasing Commitment Green Power Purchasing Commitment < Back Eligibility State Government Savings Category Bioenergy Commercial Heating & Cooling Manufacturing Buying & Making Electricity Alternative Fuel Vehicles Hydrogen & Fuel Cells Water Energy Sources Solar Home Weatherization Wind Program Info State Massachusetts Program Type Green Power Purchasing Provider Massachusetts Department of Energy Resources (DOER) In April 2007, Massachusetts Gov. Deval Patrick signed Executive Order 484, titled "Leading by Example: Clean Energy and Efficient Buildings." This order establishes numerous energy targets and mandates for state government buildings under control of the executive office. The order directed state government agencies to procure 15% of annual electricity consumption from

312

Austin - Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Bioenergy Solar Buying & Making Electricity Wind Program Information Texas Program Type Green Power Purchasing Under the Austin Climate Protection Plan, the City Council has set...

313

Environmental Regulation and Productivity: Evidence from Oil Refineries  

E-Print Network (OSTI)

Abstract: We examine the effect of air quality regulation on the productivity of some of the most heavily regulated manufacturing plants in the United States, the oil refineries of the Los Angeles (South Coast) Air Basin. We use direct measures of local air pollution regulation in this region to estimate their effects on abatement investment. Refineries not subject to these local environmental regulations are used as a comparison group. We study the period of increased regulation between 1979 and 1992. On average, each regulation cost $3M per plant on compliance dates and a further $5M per plant on dates of increased stringency. We also construct measures of total factor productivity using plant level data which allow us to observe physical quantities of inputs and outputs for the entire population of refineries. Despite the high costs associated with the local regulations, productivity in the Los Angeles Air Basin refineries rose sharply during the 1987-92 period, a period of decreased refinery productivity in other regions. We conclude that measures of the cost of environmental regulation may be significantly overstated. The gross costs may be far greater than the net cost, as abatement may be productive.

Eli Berman; Linda T. M. Bui

1998-01-01T23:59:59.000Z

314

Assessment of coal liquids as refinery feedstocks  

Science Conference Proceedings (OSTI)

The R D of direct coal liquefaction has reached such a stage that current two-stage processes can produce coal liquids with high yields and improved quality at a reasonable cost. To fully realize the potential value, these coal liquids should be refined into high-value liquid transportation fuels. The purpose of this study is to assess coal liquids as feedstocks to be processed by modern petroleum refining technologies. After the introduction, Section 2.0 summarizes ASTM specifications for major transportation fuels: gasoline, jet fuel, and diesel fuel, which serve as a target for coal-liquid refining. A concise description of modern refining processes follows with an emphasis on the requirements for the raw materials. These provide criteria to judge the quality of coal liquids as a refinery feedstock for the production of marketable liquid fuels. Section 3.0 surveys the properties of coal liquids produced by various liquefaction processes. Compared with typical petroleum oils, the current two-stage coal liquids are: Light in boiling range and free of resids and metals; very low in sulfur but relatively high in oxygen; relatively low in hydrogen and high in cyclics content; and essentially toxicologically inactive when end point is lower than 650[degrees]F, particularly after hydroprocessing. Despite these characteristics, the coal liquids are basically similar to petroleum. The modern refining technology is capable of processing coal liquids into transportation fuels meeting all specifications, and hydroprocessinq is obviously the major tool. The important point is the determination of a reasonable product slate and an appropriate refining scheme.

Zhou, P.

1992-02-01T23:59:59.000Z

315

Assessment of coal liquids as refinery feedstocks  

Science Conference Proceedings (OSTI)

The R&D of direct coal liquefaction has reached such a stage that current two-stage processes can produce coal liquids with high yields and improved quality at a reasonable cost. To fully realize the potential value, these coal liquids should be refined into high-value liquid transportation fuels. The purpose of this study is to assess coal liquids as feedstocks to be processed by modern petroleum refining technologies. After the introduction, Section 2.0 summarizes ASTM specifications for major transportation fuels: gasoline, jet fuel, and diesel fuel, which serve as a target for coal-liquid refining. A concise description of modern refining processes follows with an emphasis on the requirements for the raw materials. These provide criteria to judge the quality of coal liquids as a refinery feedstock for the production of marketable liquid fuels. Section 3.0 surveys the properties of coal liquids produced by various liquefaction processes. Compared with typical petroleum oils, the current two-stage coal liquids are: Light in boiling range and free of resids and metals; very low in sulfur but relatively high in oxygen; relatively low in hydrogen and high in cyclics content; and essentially toxicologically inactive when end point is lower than 650{degrees}F, particularly after hydroprocessing. Despite these characteristics, the coal liquids are basically similar to petroleum. The modern refining technology is capable of processing coal liquids into transportation fuels meeting all specifications, and hydroprocessinq is obviously the major tool. The important point is the determination of a reasonable product slate and an appropriate refining scheme.

Zhou, P.

1992-02-01T23:59:59.000Z

316

High Performance Windows Volume Purchase: About the High Performance  

NLE Websites -- All DOE Office Websites (Extended Search)

High Performance Windows Volume Purchase: About the High Performance Windows Volume Purchase: About the High Performance Windows Volume Purchase Program to someone by E-mail Share High Performance Windows Volume Purchase: About the High Performance Windows Volume Purchase Program on Facebook Tweet about High Performance Windows Volume Purchase: About the High Performance Windows Volume Purchase Program on Twitter Bookmark High Performance Windows Volume Purchase: About the High Performance Windows Volume Purchase Program on Google Bookmark High Performance Windows Volume Purchase: About the High Performance Windows Volume Purchase Program on Delicious Rank High Performance Windows Volume Purchase: About the High Performance Windows Volume Purchase Program on Digg Find More places to share High Performance Windows Volume Purchase:

317

2013 Short Course Analytical Techniques: Quality Control, Process Control, and Refinery Optimization  

Science Conference Proceedings (OSTI)

Analytical Techniques: Quality Control, Process Control, and Refinery Optimization held at the 104th AOCS Annual Meeting and Expo. 2013 Short Course Analytical Techniques: Quality Control, Process Control, and Refinery Optimization Analytical Techn

318

DOE - Office of Legacy Management -- International Rare Metals Refinery Inc  

Office of Legacy Management (LM)

Rare Metals Refinery Rare Metals Refinery Inc - NY 38 FUSRAP Considered Sites Site: International Rare Metals Refinery, Inc. (NY.38 ) Eliminated from consideration under FUSRAP Designated Name: Not Designated Alternate Name: Canadian Radium and Uranium Corporation NY.38-1 Location: 69 Kisko Avenue , Mt. Kisko , New York NY.38-1 NY.38-3 Evaluation Year: 1987 NY.38-4 Site Operations: Manufactured and distributed radium and polonium products. NY.38-5 Site Disposition: Eliminated - No Authority - Site was a commercial operation not under the jurisdiction of DOE predecessor agencies NY.38-2 NY.38-4 Radioactive Materials Handled: Yes Primary Radioactive Materials Handled: Radium, Plutonium NY.38-5 Radiological Survey(s): Yes NY.38-1 NY.38-5 Site Status: Eliminated from consideration under FUSRAP

319

Alternative multimedia regulatory programs for next-generation refineries  

Science Conference Proceedings (OSTI)

The 25-year-old command-and-control environmental regulatory structure in the US has resulted in significant environmental improvements. Recently, however, its limitations (e.g., rigid application regardless of site-specific conditions, disregard of cross-media and multimedia impacts, limited incentives for new technology development and use) have become increasingly apparent. New regulatory approaches that recognize current and anticipated economic constraints, new knowledge of environmental processes and impacts, and the benefits of new technologies are needed. Such approaches could be especially important for the US petroleum refining industry. This industry operates under thin profit margins, releases chemicals that can produce adverse health and environmental impacts, and must meet the technological challenges of producing more highly refined fuels from poorer quality feedstocks. Under a grant from the Environmental Technology Initiative (ETI), Argonne National Laboratory and its subcontractor, Analytical Services, Inc. developed two alternative environmental regulatory programs for next-generation petroleum refineries. (In this report, next-generation refineries refers to the refineries of today as they operate in the next 20 or more years rather than to fully reengineered future refineries.) The objective of the ETI refinery project was to develop future-oriented regulatory programs for next-generation refineries that will expand the use of innovative technologies, encourage pollution prevention, demonstrate environmental responsibility, and maintain refinery economic performance. Rather than suggesting targeted, short-term modifications to existing media-specific command-and-control regulations, the ETI project suggests the use of new approaches that are broader and more flexible. It recognizes that giving refineries flexibility in meeting environmental protection goals can stimulate new technology development and use. Unlike most US Environmental Protection Agency (EPA) reinvention efforts, which seek results in 12 to 18 months, this ETI effort assumes a time frame of 20 years or more. It also assumes that existing laws and regulations can be changed. An iterative and interactive process was used by the project team to develop the alternative approaches. Information and stakeholder input were integrated to provide for constant revision and improvement. First, guidelines and principles were established to bound the study and set parameters for developing the approaches. Next, existing and projected environmental laws and regulations affecting petroleum refineries were examined to identify areas needing change. Then, to understand future challenges and opportunities, the projected refinery operating environment was described in terms of feedstock, product, technology, and economics. Finally several goals and indicators for assessing and comparing the alternatives were identified. On the basis of this background information, more than 60 options that could efficiently and effectively protect human health and the environment were identified. These options ranged from fundamental changes in program philosophy to procedural improvements. After the options were evaluated against the goals and indicators, many of them were integrated into two separate thematic paradigms: a risk-based paradigm and a goal-based paradigm. Elements common to both approaches include the following: (1) Establish the baseline--In establishing the baseline, the refinery and the regulator jointly identify residuals for which release limits must be established; (2) Set residual release limits--The refinery and the regulator jointly specify release limits on a facility-wide rather than a source-specific basis. A facility-wide permit documents the release limits; and (3) Assure compliance--Incentives provide the basis for assuring compliance, and flexibility in the compliance method is encouraged. Penalties apply if releases exceed the limits, and reporting requirements are streamlined relative to current practices.

Elcock, D.; Gasper, J.; Arguerro, R.; Emerson, D.

2000-06-22T23:59:59.000Z

320

Mazheikiai refinery modernization study. Executive summary. Export trade information  

Science Conference Proceedings (OSTI)

The study, conducted by Foster Wheeler Corporation, was funded by the U.S. Trade and Development Agency on behalf of Lithuania's Ministry of Energy. The Mazheikiai Oil Refinery is the only one in the Baltic Region and serves the needs of Lithuania, Latvia, Estonia, and Kaliningrad. Before Lithuania's independence in 1990, the refinery was assured of crude supplies from Russia. However, since then the need has arisen to secure alternate sources of crude oil and the ability to process them. The purpose of the report is to provide recommendations to the Ministry of Energy for process improvements, environmental control measures, physical rehabilitation and energy conservation plans for the Mazheikiai Oil Refinery. The volume contains the Executive Summary.

Not Available

1994-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


321

Monitoring near refineries or airborne chemicals on the SARA Title 3 section 313 list  

Science Conference Proceedings (OSTI)

In this volume, detailed procedures recommended for the measurement of selected petroleum refinery emissions in ambient air are presented.

Not Available

1988-01-01T23:59:59.000Z

322

Monitoring near refineries for airborne chemicals on the SARA Title 3 Section 313 list  

SciTech Connect

This study provides an ambient air concentration perspective to the engineering estimates of petroleum refinery emissions required under SARA Title III Section 313. It presents and discusses ambient air concentrations of 25 selected target chemicals measured at and near the perimeter (fenceline) of three refineries. Measurements were made over three consecutive 24-hour sampling periods at each refinery. The extent to which the concentrations of the target chemicals were due to fugitive emissions from the refineries is estimated.

Not Available

1989-01-01T23:59:59.000Z

323

Monitoring near refineries or airborne chemicals on the SARA Title 3 Section 313 list  

Science Conference Proceedings (OSTI)

This volume identifies publications and databases that address ambient air concentrations measured near petroleum refineries for the selected target chemicals.

Not Available

1988-01-01T23:59:59.000Z

324

Lyondell, Citgo join for heavy oil upgrade project at Houston refinery  

Science Conference Proceedings (OSTI)

Lyondell-Citgo Refining Co. Ltd. is beginning an $800-million upgrade and expansion of its Houston refinery. The project will enable the refinery. The project will enable the refinery to produce clean fuels while processing about 80% heavy, high-sulfur Venezuelan crude oil. The paper describes the Houston refinery, the expansion project, the technologies to be used, operational changes, environmental impacts, and construction.

Rhodes, A.K.

1994-03-21T23:59:59.000Z

325

Distillate yields at U.S. refineries are rising - Today in ...  

U.S. Energy Information Administration (EIA)

Refinery processing gain results from some refining processes, such as fluid catalytic cracking and hydrocracking, where volumes can increase when ...

326

Fuzzy possibilistic modeling and sensitivity analysis for optimal fuel gas scheduling in refinery  

Science Conference Proceedings (OSTI)

In refinery, fuel gas which is continuously generated during the production process is one of the most important energy sources. Optimal scheduling of fuel gas system helps the refinery to achieve energy cost reduction and cleaner production. However, ... Keywords: Fuel gas, Fuzzy possibilistic programming, Marginal value analysis, Refinery, Scheduling, Sensitivity analysis

J. D. Zhang; G. Rong

2010-04-01T23:59:59.000Z

327

Domestic utility attitudes toward foreign uranium supply  

SciTech Connect

The current embargo on the enrichment of foreign-origin uranium for use in domestic utilization facilities is scheduled to be removed in 1984. The pending removal of this embargo, complicated by a depressed worldwide market for uranium, has prompted consideration of a new or extended embargo within the US Government. As part of its on-going data collection activities, Nuclear Resources International (NRI) has surveyed 50 domestic utility/utility holding companies (representing 60 lead operator-utilities) on their foreign uranium purchase strategies and intentions. The most recent survey was conducted in early May 1981. A number of qualitative observations were made during the course of the survey. The major observations are: domestic utility views toward foreign uranium purchase are dynamic; all but three utilities had some considered foreign purchase strategy; some utilities have problems with buying foreign uranium from particular countries; an inducement is often required by some utilities to buy foreign uranium; opinions varied among utilities concerning the viability of the domestic uranium industry; and many utilities could have foreign uranium fed through their domestic uranium contracts (indirect purchases). The above observations are expanded in the final section of the report. However, it should be noted that two of the observations are particularly important and should be seriously considered in formulation of foreign uranium import restrictions. These important observations are the dynamic nature of the subject matter and the potentially large and imbalanced effect the indirect purchases could have on utility foreign uranium procurement.

1981-06-01T23:59:59.000Z

328

Table 7.10 Expenditures for Purchased Electricity, Natural Gas, and Steam, 2010;  

U.S. Energy Information Administration (EIA) Indexed Site

0 Expenditures for Purchased Electricity, Natural Gas, and Steam, 2010; 0 Expenditures for Purchased Electricity, Natural Gas, and Steam, 2010; Level: National and Regional Data; Row: NAICS Codes; Column: Supplier Sources of Purchased Electricity, Natural Gas, and Steam; Unit: Million U.S. Dollars. Electricity Components Natural Gas Electricity Electricity from Sources Natural Gas NAICS Electricity from Local Other than Natural Gas from Local Code(a) Subsector and Industry Total Utility(b) Local Utility(c) Total Utility(b) Total United States 311 Food 5,328 4,635 692 3,391 1,675 3112 Grain and Oilseed Milling 932 850 82 673 261 311221 Wet Corn Milling 352 331 21 296 103 31131 Sugar Manufacturing 105 87 18 87 39 3114 Fruit and Vegetable Preserving and Specialty Foods 698

329

Impact of Large Scale Energy Efficiency Programs On Consumer Tariffs and Utility Finances in India  

E-Print Network (OSTI)

as sources of low-cost baseload power. 4.6.3 Large­Scale EE b is the variable cost of baseload power purchases, and L isbut simply avoids baseload power purchases. Utilities that

Abhyankar, Nikit

2011-01-01T23:59:59.000Z

330

Saudi Aramco Mobile Refinery Company (SAMREF) | Open Energy Information  

Open Energy Info (EERE)

Saudi Aramco Mobile Refinery Company (SAMREF) Saudi Aramco Mobile Refinery Company (SAMREF) Jump to: navigation, search Logo: Saudi Aramco Mobile Refinery Company (SAMREF) Name Saudi Aramco Mobile Refinery Company (SAMREF) Address P.O. Box 30078 Place Yanbu, Saudi Arabia Sector Oil and Gas Product Crude Oil Refining Phone number (966) (4) 396-4443 Website http://www.samref.com.sa/ Coordinates 24.0866932°, 38.0585527° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":24.0866932,"lon":38.0585527,"alt":0,"address":"","icon":"","group":"","inlineLabel":"","visitedicon":""}]}

331

Refinery Outages: Description and Potential Impact on Petroleum Product Prices  

Reports and Publications (EIA)

This report responds to a July 13, 2006 request from Chairman Jeff Bingaman of the Senate Committee on Energy and Natural Resources requested that EIA conduct a study of the impact that refinery shutdowns have had on the price of oil and gasoline.

Joanne Shore

2007-03-27T23:59:59.000Z

332

U.S. LPG's Consumed at Refineries (Thousand Barrels)  

U.S. Energy Information Administration (EIA)

U.S. LPG's Consumed at Refineries (Thousand Barrels) Decade Year-0 Year-1 Year-2 Year-3 Year-4 Year-5 Year-6 Year-7 Year-8 Year-9; 1980's: 8,966: 8,021: 9,466: 11,962 ...

333

U.S. Refinery Yield of Petroleum Coke (Percent)  

U.S. Energy Information Administration (EIA)

U.S. Refinery Yield of Petroleum Coke (Percent) Decade Year-0 Year-1 Year-2 Year-3 Year-4 Year-5 Year-6 Year-7 Year-8 Year-9; 1990's: 4.3: 4.3: 4.3: ...

334

U.S. Refinery Yield of Petroleum Coke (Percent)  

U.S. Energy Information Administration (EIA)

U.S. Refinery Yield of Petroleum Coke (Percent) Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec; 1993: 4.4: 4.6: 4.5: 4.3: 4.1: 4.2: 4.4: 4.3: ...

335

Energy efficiency improvement and cost saving opportunities forpetroleum refineries  

Science Conference Proceedings (OSTI)

The petroleum refining industry in the United States is the largest in the world, providing inputs to virtually any economic sector,including the transport sector and the chemical industry. The industry operates 146 refineries (as of January 2004) around the country,employing over 65,000 employees. The refining industry produces a mix of products with a total value exceeding $151 billion. Refineries spend typically 50 percent of cash operating costs (i.e., excluding capital costs and depreciation) on energy, making energy a major cost factor and also an important opportunity for cost reduction. Energy use is also a major source of emissions in the refinery industry making energy efficiency improvement an attractive opportunity to reduce emissions and operating costs. Voluntary government programs aim to assist industry to improve competitiveness through increased energy efficiency and reduced environmental impact. ENERGY STAR (R), a voluntary program managed by the U.S. Environmental Protection Agency, stresses the need for strong and strategic corporate energy management programs. ENERGY STAR provides energy management tools and strategies for successful corporate energy management programs. This Energy Guide describes research conducted to support ENERGY STAR and its work with the petroleum refining industry.This research provides information on potential energy efficiency opportunities for petroleum refineries. This Energy Guide introduces energy efficiency opportunities available for petroleum refineries. It begins with descriptions of the trends, structure, and production of the refining industry and the energy used in the refining and conversion processes. Specific energy savings for each energy efficiency measure based on case studies of plants and references to technical literature are provided. If available, typical payback periods are also listed. The Energy Guide draws upon the experiences with energy efficiency measures of petroleum refineries worldwide. The findings suggest that given available resources and technology, there are opportunities to reduce energy consumption cost-effectively in the petroleum refining industry while maintaining the quality of the products manufactured. Further research on the economics of the measures, as well as the applicability of these to individual refineries, is needed to assess the feasibility of implementation of selected technologies at individual plants.

Worrell, Ernst; Galitsky, Christina

2005-02-15T23:59:59.000Z

336

Market survey on products from the Tema Oil Refinery carried out as part of the feasibility study on the Tema Oil Refinery expansion project. Export trade information  

SciTech Connect

The Tema Oil Refinery (TOR), which was commissioned in 1963, is a simple hydroskimming plant which processes crude oil into LPG, gasoline, kerosene, gasoil, and fuel oil. It is the only petroleum refinery in Ghana. Over the years some of the equipment in the refinery has deteriorated or become obsolete necessitating major rehabilitation. A feasibility study is investigating the modernization and expansion of the refinery to meet projected market demands until the year 2005. The report presents the results of a market survey done on products from TOR.

Not Available

1991-10-01T23:59:59.000Z

337

High Performance Windows Volume Purchase: Subscribe to Windows...  

NLE Websites -- All DOE Office Websites (Extended Search)

Subscribe to Windows Volume Purchase Event News and Updates to someone by E-mail Share High Performance Windows Volume Purchase: Subscribe to Windows Volume Purchase Event News and...

338

Vehicle Technologies Office: Fact #482: August 13, 2007 Refinery Output by  

NLE Websites -- All DOE Office Websites (Extended Search)

2: August 13, 2: August 13, 2007 Refinery Output by World Region to someone by E-mail Share Vehicle Technologies Office: Fact #482: August 13, 2007 Refinery Output by World Region on Facebook Tweet about Vehicle Technologies Office: Fact #482: August 13, 2007 Refinery Output by World Region on Twitter Bookmark Vehicle Technologies Office: Fact #482: August 13, 2007 Refinery Output by World Region on Google Bookmark Vehicle Technologies Office: Fact #482: August 13, 2007 Refinery Output by World Region on Delicious Rank Vehicle Technologies Office: Fact #482: August 13, 2007 Refinery Output by World Region on Digg Find More places to share Vehicle Technologies Office: Fact #482: August 13, 2007 Refinery Output by World Region on AddThis.com... Fact #482: August 13, 2007

339

Government Purchase Card Program | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Government Purchase Card Program Government Purchase Card Program Government Purchase Card Program The General Services Administration (GSA) SmartPay2 program provides charge cards to U.S. Government agencies, including the Department of Energy (DOE). Through GSA, DOE has contracted with JP Morgan Chase Bank to provide charge cards to pay for supplies/services to support our business purpose. All terms and conditions, including but not limited to, fees, liabilities, discounts, and rebates have been negotiated on behalf of all participants in the program. DOE allows the use of GSA SmartPay2 charge cards to cost reimbursement contractors that have been authorized to use Government Supply Sources pursuant to FAR Subpart 51.1. Charge cards provide DOE with a means to simplify its small purchase

340

Property:Purchasers | Open Energy Information  

Open Energy Info (EERE)

Property Property Edit with form History Facebook icon Twitter icon » Property:Purchasers Jump to: navigation, search Property Name Purchasers Property Type String Description A unique list of power purchasers of all geothermal power plants in the area. Automatically populated using ask query on Property: EnergyPurchaser of Category: Energy Generation Facility with property GeothermalArea set to the variable Name of the Geothermal Resource Area Subproperties This property has the following 321 subproperties: A Abraham Hot Springs Geothermal Area Adak Geothermal Area Akun Strait Geothermal Area Akutan Fumaroles Geothermal Area Alum Geothermal Area Alvord Hot Springs Geothermal Area Amedee Geothermal Area Arrowhead Hot Springs Geothermal Area Ashton Warm Springs Geothermal Area

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


341

City of Bellingham- Green Power Purchasing  

Energy.gov (U.S. Department of Energy (DOE))

In July 2006, the Bellingham City Council adopted a policy to begin purchasing 100% green power for all facilities owned by the city -- one of the most aggressive such goals in the United States....

342

Quick Guide: Power Purchase Agreements (Fact Sheet)  

Science Conference Proceedings (OSTI)

Introduction to Federal power purchase agreements (PPAs), including available FEMP services and technical assistance as well as questions to ask when evaluating PPAs for a Federal renewable energy project.

Not Available

2011-07-01T23:59:59.000Z

343

Alternative Fuels Data Center: State Vehicle Purchasing Guidance  

Alternative Fuels and Advanced Vehicles Data Center (EERE)

Vehicle Vehicle Purchasing Guidance to someone by E-mail Share Alternative Fuels Data Center: State Vehicle Purchasing Guidance on Facebook Tweet about Alternative Fuels Data Center: State Vehicle Purchasing Guidance on Twitter Bookmark Alternative Fuels Data Center: State Vehicle Purchasing Guidance on Google Bookmark Alternative Fuels Data Center: State Vehicle Purchasing Guidance on Delicious Rank Alternative Fuels Data Center: State Vehicle Purchasing Guidance on Digg Find More places to share Alternative Fuels Data Center: State Vehicle Purchasing Guidance on AddThis.com... More in this section... Federal State Advanced Search All Laws & Incentives Sorted by Type State Vehicle Purchasing Guidance The Washington Department of Enterprise Services must develop guidelines

344

Alternative Fuels Data Center: Biodiesel Blend Purchase Requirement  

Alternative Fuels and Advanced Vehicles Data Center (EERE)

Blend Blend Purchase Requirement to someone by E-mail Share Alternative Fuels Data Center: Biodiesel Blend Purchase Requirement on Facebook Tweet about Alternative Fuels Data Center: Biodiesel Blend Purchase Requirement on Twitter Bookmark Alternative Fuels Data Center: Biodiesel Blend Purchase Requirement on Google Bookmark Alternative Fuels Data Center: Biodiesel Blend Purchase Requirement on Delicious Rank Alternative Fuels Data Center: Biodiesel Blend Purchase Requirement on Digg Find More places to share Alternative Fuels Data Center: Biodiesel Blend Purchase Requirement on AddThis.com... More in this section... Federal State Advanced Search All Laws & Incentives Sorted by Type Biodiesel Blend Purchase Requirement Diesel fuel that the New Hampshire Department of Transportation

345

Federal Energy Management Program: Information Resources on Purchasing...  

NLE Websites -- All DOE Office Websites (Extended Search)

Information Resources on Purchasing Renewable Power to someone by E-mail Share Federal Energy Management Program: Information Resources on Purchasing Renewable Power on Facebook...

346

Guide to Purchasing Green Power: Renewable Electricity, Renewable...  

NLE Websites -- All DOE Office Websites (Extended Search)

Guide to Purchasing Green Power: Renewable Electricity, Renewable Energy Certificates and On-Site Renewable Generation Title Guide to Purchasing Green Power: Renewable Electricity,...

347

City of Dallas - Green Energy Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Dallas - Green Energy Purchasing City of Dallas - Green Energy Purchasing Eligibility Local Government Savings For Wind Buying & Making Electricity Program Information Texas...

348

,"Domestic Crude Oil First Purchase Prices for Selected Crude...  

U.S. Energy Information Administration (EIA) Indexed Site

(Dollars per Barrel)","Mars Blend First Purchase Price (Dollars per Barrel)","West Texas Intermediate First Purchase Price (Dollars per Barrel)","West Texas Sour First...

349

City of Bellingham - Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Administration Other Agencies You are here Home Savings City of Bellingham - Green Power Purchasing City of Bellingham - Green Power Purchasing Eligibility Local...

350

Riverside, CA Vehicle Purchase Incentives | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

are eligible to receive a rebate toward the purchase of qualified natural gas or hybrid electric vehicles purchased from a City of Riverside automobile dealership. The...

351

Use of New Strategically Sourced Blanket Purchase Agreement....  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Use of New Strategically Sourced Blanket Purchase Agreement. . . Use of New Strategically Sourced Blanket Purchase Agreement. . . Policy Flash Use of New Strategically Sourced...

352

City of Dallas - Green Energy Purchasing (Texas) | Open Energy...  

Open Energy Info (EERE)

purchasing program through 2013. The purchase amounts to roughly 40% of total expected electricity consumption by municipal facilities for the year and will be supplied...

353

Energy Department Issues Tribal Renewable Energy Purchase Guidance...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Energy Department Issues Tribal Renewable Energy Purchase Guidance and Project Development Resources Energy Department Issues Tribal Renewable Energy Purchase Guidance and Project...

354

Green Power Purchase Plan (Connecticut) | Open Energy Information  

Open Energy Info (EERE)

Name Green Power Purchase Plan Incentive Type Green Power Purchasing Applicable Sector State Government Eligible Technologies Biomass, Fuel Cells, Landfill Gas, Ocean Thermal,...

355

Alternative Fuels Data Center: Natural Gas Vehicle (NGV) Purchase...  

Alternative Fuels and Advanced Vehicles Data Center (EERE)

Natural Gas Vehicle (NGV) Purchase Vouchers to someone by E-mail Share Alternative Fuels Data Center: Natural Gas Vehicle (NGV) Purchase Vouchers on Facebook Tweet about...

356

Alternative future environmental regulatory approaches for petroleum refineries.  

Science Conference Proceedings (OSTI)

Recently, many industrial, regulatory, and community leaders have expressed concern that the current environmental regulatory structure disregards multimedia environmental impacts, provides few incentives to develop and use new technologies, and fails to consider site-specific conditions. For the US petroleum refining industry, faced with the need to produce higher-quality fuels from poorer-quality feedstocks, such criticisms are expected to increase. This article offers two alternative environmental regulatory approaches for existing petroleum refineries to use in the future. These alternative approaches are multimedia in scope, provide for new technology development and use, and allow flexibility in the means for meeting environmental goals. They have been reviewed and critiqued by various stakeholders, including industry representatives, regulators, and local and national community and environmental organizations. The integration of stakeholder comments and findings of ongoing national and international regulatory reinvention efforts in the development of these approaches positions them for potential use by other industries in addition to petroleum refineries.

Elcock, D.; Gasper, J.; Moses, D. O.; Emerson, D.; Arguerro, R.; Environmental Assessment; DOE; Analytical Services, Inc.

2000-01-01T23:59:59.000Z

357

New process effectively recovers oil from refinery waste streams  

Science Conference Proceedings (OSTI)

A new process uses chemically assisted, thermal flashing to break difficult emulsions and recover oil for reprocessing. The process is best suited for refinery waste management and slop oil systems, where it can process streams with high oil content to recover high-quality oil. Recent testing of a full-scale, commercial prototype unit on slop oil emulsions at a major Gulf Coast refinery resulted in: 97.9% recovery of oil with 99.3--99.6% purity; 99.5% recovery of water with 99+% purity; and a centrifuge cake containing 49-60% solids, 23--30 oil, and 17--22% water. The paper discusses background of the process, then gives a process description as well as results of field studies and cost.

Rhodes, A.

1994-08-15T23:59:59.000Z

358

Request for Information: Federal Government Power Purchase Agreements (PPA) Issues  

Energy.gov (U.S. Department of Energy (DOE))

Document describes the request for information for federal government power purchase agreement (PPA) issues.

359

Martinez Refinery Completes Plant-Wide Energy Assessment  

SciTech Connect

This OIT BestPractices Case Study describes how the Equilon Enterprises oil refinery in Martinez, California undertook a plant-wide energy assessment that focused on three key areas: waste minimization, process debottlenecking, and operations optimization. The assessment yielded recommendations, which, if implemented, can save more than 6,000,000 MMBtu per year and an estimated $52,000,000 per year, plus improve process control and reduce waste.

Not Available

2002-11-01T23:59:59.000Z

360

Aggregated Purchasing - A Clean Energy Strategy  

NLE Websites -- All DOE Office Websites (Extended Search)

A number of organizations, including municipalities, state and federal agencies, businesses and even religious organizations are leading the way to a renewable energy future by using their collective buying power to purchase green power. The city of Chicago has formed an alliance with 47 other local government agencies to increase their reliance on clean energy sources. As part of this effort, Chicago has installed solar electric systems on a number of the city's buildings, including the Chicago Center for Green Technology shown here. City of Chicago Aggregated Purchasing-A Clean Energy Strategy SOLAR TODAY Aggregated Purchasing-A Clean Energy Strategy by Lori A. Bird and Edward A. Holt November/December 2002 35 Power generated from renewable resources, also known as "green" power, is

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


361

Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Water Water Buying & Making Electricity Solar Wind Program Info State Maine Program Type Green Power Purchasing In 2003, Maine's governor established a goal for the state government to buy at least 50% of its electricity from "reasonably priced" renewable-power sources, paid for by energy conservation improvements in all state buildings. The goal was contained in the governor's "Vision" for meeting Maine's environmental needs. As of March 2007, Maine's state government was purchasing 100% of its power from renewable energy resources. The state's existing renewable energy portfolio standard accounts for 30% of this total. For the remaining 70%, the state is purchasing renewable-energy credits (RECs) from the Rumford Falls hydropower project in Rumford, Maine.

362

Green Purchasing under DOE Architect Engineer Contracts  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Purchasing under DOE Architect Engineer Contracts Purchasing under DOE Architect Engineer Contracts Prescription for Use: This clause should be used in any architect-engineer type contract unless Leadership in Energy and Environmental Design (LEED) Green Building Certification is being pursued. In case of LEED Certification, a detailed series of energy and environmental standards would take the place of this clause. Section I of the contract should also contain the clauses at FAR 52.223-2, Affirmative Procurement of Biobased Products under Service and Construction Contracts, 52.223-15, Energy Efficiency in Energy Consuming Products, and 52.223-17 Affirmative Procurement of EPA- Designated Items in Service and Construction Contracts. H-xx. Green Purchasing under DOE Architect Engineer Contracts

363

Joint Electrical Utilities (Iowa) | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Joint Electrical Utilities (Iowa) Joint Electrical Utilities (Iowa) Joint Electrical Utilities (Iowa) < Back Eligibility Investor-Owned Utility Local Government Municipal/Public Utility Rural Electric Cooperative Tribal Government Utility Savings Category Alternative Fuel Vehicles Hydrogen & Fuel Cells Buying & Making Electricity Water Home Weatherization Solar Wind Program Info State Iowa Program Type Environmental Regulations Provider Iowa Utilities Board Cities may establish utilities to acquire existing electric generating facilities or distribution systems. Acquisition, in this statute, is defined as city involvement, and includes purchase, lease, construction, reconstruction, extension, remodeling, improvement, repair, and equipping of the facility. This chapter does not limit the powers or authority of

364

Updated estimation of energy efficiencies of U.S. petroleum refineries.  

SciTech Connect

Evaluation of life-cycle (or well-to-wheels, WTW) energy and emission impacts of vehicle/fuel systems requires energy use (or energy efficiencies) of energy processing or conversion activities. In most such studies, petroleum fuels are included. Thus, determination of energy efficiencies of petroleum refineries becomes a necessary step for life-cycle analyses of vehicle/fuel systems. Petroleum refinery energy efficiencies can then be used to determine the total amount of process energy use for refinery operation. Furthermore, since refineries produce multiple products, allocation of energy use and emissions associated with petroleum refineries to various petroleum products is needed for WTW analysis of individual fuels such as gasoline and diesel. In particular, GREET, the life-cycle model developed at Argonne National Laboratory with DOE sponsorship, compares energy use and emissions of various transportation fuels including gasoline and diesel. Energy use in petroleum refineries is key components of well-to-pump (WTP) energy use and emissions of gasoline and diesel. In GREET, petroleum refinery overall energy efficiencies are used to determine petroleum product specific energy efficiencies. Argonne has developed petroleum refining efficiencies from LP simulations of petroleum refineries and EIA survey data of petroleum refineries up to 2006 (see Wang, 2008). This memo documents Argonne's most recent update of petroleum refining efficiencies.

Palou-Rivera, I.; Wang, M. Q. (Energy Systems)

2010-12-08T23:59:59.000Z

365

Petroleum complex of Russia. Reconstruction of petroleum refineries: Means for accomplishing the task  

SciTech Connect

This report describes the refining industry in Russia with respect to production and economic factors. The modernization and reconstruction of the refineries is also discussed.

Rykunova, T.

1994-11-01T23:59:59.000Z

366

New desorption process treats refinery K and F wastes in demo trial  

SciTech Connect

A new desorption process for treating refinery wastes has been proven in pilot demonstrations at Amoco Oil Co.'s Texas City, Tex., refinery. The process -- Waste-Tech Services Inc.'s desorption and recovery unit (DRU) -- treats petroleum-contaminated refinery wastes and recovers oil and water suitable for recycling to the refinery. The DRU meets Resource Conservation and Recovery Act (RCRA) recycle exemptions and produces solids that satisfy US Environmental Protection Agency (EPA) land disposal restrictions (LDRs). This paper discusses RCRA wastes, the process, the demonstration unit, operating conditions, and analyses of semivolatiles, volatiles, leachable metals, and recovered oil and water.

Rasmussen, G.P. (Waste-Tech Services Inc., Golden, CO (United States))

1994-01-10T23:59:59.000Z

367

Economic forces push down selling prices of U.S. refineries  

Science Conference Proceedings (OSTI)

Recent data on US refinery sales reveal that selling prices have continued to decline in the 1990s. Reasons for this decrease include increased plant investments to meet regulatory requirements, excess refining capacity, increased imports of refined products, and reduced margins. While these expenditures enable a refinery to continue operating, they do not make the refinery more profitable or valuable. Other factors contributing to reduced selling prices of US refineries are: declining local crude production; unstable crude costs; increased energy conservation; growing competition from alternative fuels.

NONE

1996-03-25T23:59:59.000Z

368

The Revival of Onahama Smelter & Refinery from the Disaster by the ...  

Science Conference Proceedings (OSTI)

Presentation Title, The Revival of Onahama Smelter & Refinery from the ... Study of Modified Semi-Coke on the Advanced Treatment of Coking Wastewater's Oil.

369

Aspects of Holly Corporation's Acquisition of Sunoco Inc.'s Tulsa, Oklahoma Refinery  

Reports and Publications (EIA)

The Energy Information Administration has produced a review of aspects of the Holly's acquisition of Sunoco's 85,000-barrels-per-day Tulsa refinery

Neal Davis

2009-04-22T23:59:59.000Z

370

Carbon Capture and Sequestration from a Hydrogen Production Facility in an Oil Refinery  

SciTech Connect

The project proposed a commercial demonstration of advanced technologies that would capture and sequester CO2 emissions from an existing hydrogen production facility in an oil refinery into underground formations in combination with Enhanced Oil Recovery (EOR). The project is led by Praxair, Inc., with other project participants: BP Products North America Inc., Denbury Onshore, LLC (Denbury), and Gulf Coast Carbon Center (GCCC) at the Bureau of Economic Geology of The University of Texas at Austin. The project is located at the BP Refinery at Texas City, Texas. Praxair owns and operates a large hydrogen production facility within the refinery. As part of the project, Praxair would construct a CO2 capture and compression facility. The project aimed at demonstrating a novel vacuum pressure swing adsorption (VPSA) based technology to remove CO2 from the Steam Methane Reformers (SMR) process gas. The captured CO2 would be purified using refrigerated partial condensation separation (i.e., cold box). Denbury would purchase the CO2 from the project and inject the CO2 as part of its independent commercial EOR projects. The Gulf Coast Carbon Center at the Bureau of Economic Geology, a unit of University of Texas at Austin, would manage the research monitoring, verification and accounting (MVA) project for the sequestered CO2, in conjunction with Denbury. The sequestration and associated MVA activities would be carried out in the Hastings field at Brazoria County, TX. The project would exceed DOE?s target of capturing one million tons of CO2 per year (MTPY) by 2015. Phase 1 of the project (Project Definition) is being completed. The key objective of Phase 1 is to define the project in sufficient detail to enable an economic decision with regard to proceeding with Phase 2. This topical report summarizes the administrative, programmatic and technical accomplishments completed in Phase 1 of the project. It describes the work relative to project technical and design activities (associated with CO2 capture technologies and geologic sequestration MVA), and Environmental Information Volume. Specific accomplishments of this Phase include: 1. Finalization of the Project Management Plan 2. Development of engineering designs in sufficient detail for defining project performance and costs 3. Preparation of Environmental Information Volume 4. Completion of Hazard Identification Studies 5. Completion of control cost estimates and preparation of business plan During the Phase 1 detailed cost estimate, project costs increased substantially from the previous estimate. Furthermore, the detailed risk assessment identified integration risks associated with potentially impacting the steam methane reformer operation. While the Phase 1 work identified ways to mitigate these integration risks satisfactorily from an operational perspective, the associated costs and potential schedule impacts contributed to the decision not to proceed to Phase 2. We have concluded that the project costs and integration risks at Texas City are not commensurate with the potential benefits of the project at this time.

Engels, Cheryl; Williams, Bryan, Valluri, Kiranmal; Watwe, Ramchandra; Kumar, Ravi; Mehlman, Stewart

2010-06-21T23:59:59.000Z

371

Purchase, Delivery, and Storage of Gases  

NLE Websites -- All DOE Office Websites (Extended Search)

Purchase, Delivery, and Storage of Gases Print Purchase, Delivery, and Storage of Gases Print ALS users should follow Berkeley Lab policy, as described below, for the purchase, delivery, storage, and use of all gases at the ALS. See Shipping and Receiving for information on any non-gas deliveries. Contacts: Gas purchase or delivery: ALS Receiving, 510-486-4494 Gas use and storage: Experiment Coordination, 510-486-7222, This e-mail address is being protected from spambots. You need JavaScript enabled to view it Gas Storage: Berkeley Lab Chemical Inventory All gas bottles and cylinders at the ALS must be identified with bar code and logged into the Berkeley Lab Chemical Inventory by ALS staff. The inventory will be updated periodically; for more information contact Experiment Coordination. Gases are stored either in the racks between buildings 6 and 7; toxic and corrosive gases are stored in Building 6, room 6C across the walkway from beamline 10.0.

372

Purchase Card Policies for Hq | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Services » Procurement Services » Purchase Card Policies for Hq Services » Procurement Services » Purchase Card Policies for Hq Purchase Card Policies for Hq HQ Procurement Services Policies & Operating Procedures Table of Contents PURPOSE RESPONSIBILITIES PERSONAL PROPERTY MANAGEMENT AND PROPERTY ACCOUNTABILITY ADDITIONAL PROHIBITIONS AND RESTRICTIONS PURCHASE CARD FINANCIAL PROCEDURES EMPLOYEES TRANSFERRING WITHIN HEADQUARTERS PROGRAM SUPPORT ADDITIONAL CARDHOLDER AND APPROVING OFFICIAL TRAINING USE OF PRIVATE SECTOR TEMPORARIES STRIPES Purpose To establish Headquarters Procurement Services Policies and Operating Procedures for the use of the Government purchase card at Department of Energy (DOE) - Headquarters (HQ). These Policies supplement the "Policy and Operating Procedures for Use of the GSA SmartPay Purchase

373

Montgomery County - Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Montgomery County - Green Power Purchasing Montgomery County - Green Power Purchasing Montgomery County - Green Power Purchasing < Back Eligibility Local Government Savings Category Bioenergy Buying & Making Electricity Solar Water Wind Program Info State Maryland Program Type Green Power Purchasing Provider Montgomery County In October 2000, a group six county agencies, consisting of Montgomery County, Montgomery County Public Schools, Montgomery County Housing Opportunities Commission, Montgomery College, the Washington Suburban Sanitary Commission, and the Maryland-National Capital Park and Planning Commission, began purchasing power on a competitive basis. In March 2003, the county's energy policy was amended to incorporate the purchase of renewable energy and to expand energy-efficiency efforts. This resolution

374

Non-utility power generation continues to grow  

SciTech Connect

This article examines why the number of non-utility power plants is increasing. The topics include the impact of the changes to the Public Utility Holding Company Act, and bidding for capacity. It includes a look at Texaco's Puget Sound oil refinery and how its efficiency problems were solved using cogeneration including the need to improve energy balance and engineering of the plant. Grayling generating station (wood waste) and Kalaeloa cogeneration power plant (low sulfur fuel oil) are also discussed.

Smith, D.J.

1993-05-01T23:59:59.000Z

375

Collective economics : leveraging purchasing power of low-income communities for collective gain : Lawrence Community Works and the Network Advantage Program  

E-Print Network (OSTI)

This thesis focuses on the concept of Collective Economics and develops a set of recommendations by which groups with common interests can effectively utilize their purchasing power for collective benefits. Working with ...

Espino, Eric V

2007-01-01T23:59:59.000Z

376

Clean air amendments put big burden on refinery planners  

SciTech Connect

The Clean Air Act Amendments of 1990 will not only require the production of reformulated gasoline but also have significant impact on other refinery-related construction. This must be considered when developing sound planning strategy. The three titles of the Clean Air Act Amendments that will have the greatest effect on refining are: Title I: Nonattainment; Title III: Air toxics; Title V: Permitting. To understand the ramifications of these amendments, it is necessary to review the interactions of new requirements with the permitting and construction schedule shown.

Scherr, R.C.; Smalley, G.A. Jr.; Norman, M.E. (ENSR Consulting and Engineering, Houston, TX (US))

1991-06-10T23:59:59.000Z

377

GovEnergy 2008 Session Presentation on Power Purchase Agreements  

NLE Websites -- All DOE Office Websites (Extended Search)

Agreements Agreements Power Purchase Agreements for for Renewable Energy Renewable Energy Jim Snook Steve Dumont Jim Snook Steve Dumont Mike Warwick Mike Warwick AFCESA/CENF AFCESA/CENF ACC/A7OE PNNL ACC/A7OE PNNL U.S. Air Force U.S. Air Force U.S. Air Force U.S. Air Force Pacific NW Pacific NW National Lab National Lab AGENDA * PPA Basics * PPA "How to" Guide * Nellis Experience * Ft. Carson Experience Renewable Energy Projects * Objective: Develop renewable generation - Reduce fossil fuel use & foreign oil dependence - Meet Federal renewable energy goals (EPAct, Executive Order 13423, etc) - Reduce and stabilize utility costs - Improve energy supply security & reliability Renewable Energy Projects * Key requirements

378

GovEnergy 2008 Session Presentation on Power Purchase Agreements  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Agreements Agreements Power Purchase Agreements for for Renewable Energy Renewable Energy Jim Snook Steve Dumont Jim Snook Steve Dumont Mike Warwick Mike Warwick AFCESA/CENF AFCESA/CENF ACC/A7OE PNNL ACC/A7OE PNNL U.S. Air Force U.S. Air Force U.S. Air Force U.S. Air Force Pacific NW Pacific NW National Lab National Lab AGENDA * PPA Basics * PPA "How to" Guide * Nellis Experience * Ft. Carson Experience Renewable Energy Projects * Objective: Develop renewable generation - Reduce fossil fuel use & foreign oil dependence - Meet Federal renewable energy goals (EPAct, Executive Order 13423, etc) - Reduce and stabilize utility costs - Improve energy supply security & reliability Renewable Energy Projects * Key requirements

379

Resources on Purchasing Renewable Power | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Resources on Purchasing Renewable Power Resources on Purchasing Renewable Power Resources on Purchasing Renewable Power October 7, 2013 - 9:44am Addthis Many helpful resources about purchasing renewable power are available. Publications Renewable Energy Certificate (REC) Quick Guide: Guide for Federal agencies considering renewable energy certificate (REC) purchases to fulfill Federal renewable energy requirements. Guide to Purchasing Green Power: Guide for organizations considering the merits of buying green power, as well as those that have decided to buy green power but need help with the purchasing process. Renewable Resources for Federal Agencies: Brochure describing the Western Area Power Administration's program for purchasing power from renewable energy resources. Presentations Renewable Energy Certificate (REC) Tracking Systems: Costs & Verification

380

Vehicle Technologies Office: Fact #417: March 27, 2006 Why Purchase...  

NLE Websites -- All DOE Office Websites (Extended Search)

17: March 27, 2006 Why Purchase a Hybrid Vehicle? to someone by E-mail Share Vehicle Technologies Office: Fact 417: March 27, 2006 Why Purchase a Hybrid Vehicle? on Facebook Tweet...

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


381

Purchase of High Performance Computing (HPC) Central Compute Resources  

E-Print Network (OSTI)

Purchase of High Performance Computing (HPC) Central Compute Resources by Northwestern Researchers summarizes High Performance Computing (HPC) compute resources that faculty engaged in research may purchase of code on the Quest high performance computing system. The installation cycles for new

Shull, Kenneth R.

382

What Is Your Latest Energy Efficient Purchase? | Department of...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Latest Energy Efficient Purchase? What Is Your Latest Energy Efficient Purchase? February 10, 2011 - 6:30am Addthis On Tuesday, Andrea told us about her new door and the research...

383

High Performance Windows Volume Purchase: NewsDetail  

NLE Websites -- All DOE Office Websites (Extended Search)

NewsDetail to someone by E-mail Share High Performance Windows Volume Purchase: NewsDetail on Facebook Tweet about High Performance Windows Volume Purchase: NewsDetail on Twitter...

384

City of Madison - Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Madison - Green Power Purchasing Madison - Green Power Purchasing City of Madison - Green Power Purchasing < Back Eligibility Local Government Savings Category Biofuels Alternative Fuel Vehicles Bioenergy Solar Buying & Making Electricity Wind Program Info State Wisconsin Program Type Green Power Purchasing Provider City of Madison In 1999, Madison's Metro Maintenance and Administration Facility began purchasing 25% of its electricity from Madison Gas and Electric's wind power program. The additional cost to purchase the wind power is approximately $26,000 per year. Metro officials estimate that their wind power purchase is equivalent to running ten buses per year with no carbon monoxide emissions. In 2005, the city established a goal to increase the entire city's electricity purchases to 10% renewable energy by 2006 and

385

High-Octane Fuel from Refinery Exhaust Gas: Upgrading Refinery Off-Gas to High-Octane Alkylate  

Science Conference Proceedings (OSTI)

Broad Funding Opportunity Announcement Project: Exelus is developing a method to convert olefins from oil refinery exhaust gas into alkylate, a clean-burning, high-octane component of gasoline. Traditionally, olefins must be separated from exhaust before they can be converted into another source of useful fuel. Exelus’ process uses catalysts that convert the olefin to alkylate without first separating it from the exhaust. The ability to turn up to 50% of exhaust directly into gasoline blends could result in an additional 46 million gallons of gasoline in the U.S. each year.

None

2009-12-01T23:59:59.000Z

386

Table 23. Domestic Crude Oil First Purchase Prices by API ...  

U.S. Energy Information Administration (EIA)

23. Domestic Crude Oil First Purchase Prices by API Gravity Energy Information Administration / Petroleum Marketing Annual 1996 45. Created Date:

387

Refinery Integration of By-Products from Coal-Derived Jet Fuels  

SciTech Connect

The final report summarizes the accomplishments toward project goals during length of the project. The goal of this project was to integrate coal into a refinery in order to produce coal-based jet fuel, with the major goal to examine the products other than jet fuel. These products are in the gasoline, diesel and fuel oil range and result from coal-based jet fuel production from an Air Force funded program. The main goal of Task 1 was the production of coal-based jet fuel and other products that would need to be utilized in other fuels or for non-fuel sources, using known refining technology. The gasoline, diesel fuel, and fuel oil were tested in other aspects of the project. Light cycle oil (LCO) and refined chemical oil (RCO) were blended, hydrotreated to removed sulfur, and hydrogenated, then fractionated in the original production of jet fuel. Two main approaches, taken during the project period, varied where the fractionation took place, in order to preserve the life of catalysts used, which includes (1) fractionation of the hydrotreated blend to remove sulfur and nitrogen, followed by a hydrogenation step of the lighter fraction, and (2) fractionation of the LCO and RCO before any hydrotreatment. Task 2 involved assessment of the impact of refinery integration of JP-900 production on gasoline and diesel fuel. Fuel properties, ignition characteristics and engine combustion of model fuels and fuel samples from pilot-scale production runs were characterized. The model fuels used to represent the coal-based fuel streams were blended into full-boiling range fuels to simulate the mixing of fuel streams within the refinery to create potential 'finished' fuels. The representative compounds of the coal-based gasoline were cyclohexane and methyl cyclohexane, and for the coal-base diesel fuel they were fluorine and phenanthrene. Both the octane number (ON) of the coal-based gasoline and the cetane number (CN) of the coal-based diesel were low, relative to commercial fuels ({approx}60 ON for coal-based gasoline and {approx}20 CN for coal-based diesel fuel). Therefore, the allowable range of blending levels was studied where the blend would achieve acceptable performance. However, in both cases of the coal-based fuels, their ignition characteristics may make them ideal fuels for advanced combustion strategies where lower ON and CN are desirable. Task 3 was designed to develop new approaches for producing ultra clean fuels and value-added chemicals from refinery streams involving coal as a part of the feedstock. It consisted of the following three parts: (1) desulfurization and denitrogenation which involves both new adsorption approach for selective removal of nitrogen and sulfur and new catalysts for more effective hydrotreating and the combination of adsorption denitrogenation with hydrodesulfurization; (2) saturation of two-ring aromatics that included new design of sulfur resistant noble-metal catalysts for hydrogenation of naphthalene and tetralin in middle distillate fuels, and (3) value-added chemicals from naphthalene and biphenyl, which aimed at developing value-added organic chemicals from refinery streams such as 2,6-dimethylnaphthalene and 4,4{prime}-dimethylbiphenyl as precursors to advanced polymer materials. Major advances were achieved in this project in designing the catalysts and sorbent materials, and in developing fundamental understanding. The objective of Task 4 was to evaluate the effect of introducing coal into an existing petroleum refinery on the fuel oil product, specifically trace element emissions. Activities performed to accomplish this objective included analyzing two petroleum-based commercial heavy fuel oils (i.e., No. 6 fuel oils) as baseline fuels and three co-processed fuel oils, characterizing the atomization performance of a No. 6 fuel oil, measuring the combustion performance and emissions of the five fuels, specifically major, minor, and trace elements when fired in a watertube boiler designed for natural gas/fuel oil, and determining the boiler performance when firing the five fuels. Two

Caroline Clifford; Andre Boehman; Chunshan Song; Bruce Miller; Gareth Mitchell

2008-03-31T23:59:59.000Z

388

Trends in Utility Green Pricing Programs (2006)  

SciTech Connect

In the early 1990s, only a handful of utilities offered their customers a choice of purchasing electricity generated from renewable energy sources. Today, more than 750 utilities--or about 25% of all utilities nationally--provide their customers a "green power" option. Through these programs, more than 70 million customers have the ability to purchase renewable energy to meet some portion or all of their electricity needs--or make contributions to support the development of renewable energy resources. Typically, customers pay a premium above standard electricity rates for this service. This report presents year-end 2006 data on utility green pricing programs, and examines trends in consumer response and program implementation over time. The data in this report, which were obtained via a questionnaire distributed to utility green pricing program managers, can be used by utilities to benchmark the success of their green power programs.

Bird, L.; Kaiser, M.

2007-10-01T23:59:59.000Z

389

Utility Green Pricing Programs: A Statistical Analysis of Program Effectiveness  

DOE Green Energy (OSTI)

This report analyzes actual utility green pricing program data to provide further insight into which program features might help maximize both customer participation in green pricing programs and the amount of renewable energy purchased by customers in those programs.

Wiser, R.; Olson, S.; Bird, L.; Swezey, B.

2004-02-01T23:59:59.000Z

390

Table 5.9 Refinery Capacity and Utilization, 1949-2011  

U.S. Energy Information Administration (EIA)

1954. 308: 7,984: na: 7,266: 88.8: 1955. 296: 8,386: na: 7,820: 92.2: 1956. 317: 8,583: na: 8,250: 93.5: 1957. 317: 9,072: na: 8,222: 89.2: 1958. 315: ...

391

Table 5.9 Refinery Capacity and Utilization, 1949-2011  

U.S. Energy Information Administration (EIA)

1954. 308: 7,984: na : 2,651,992 : 88.8 : 1955. 296: 8,386: na : 2,854,137 : 92.2 : 1956. 317: 8,583: na : 3,019,601 : 93.5 : 1957. 317: 9,072: na : ...

392

Hydrotreating Pyrolytic Lignin to Produce a Refinery Feedstock (Poster)  

Science Conference Proceedings (OSTI)

Fast pyrolysis of biomass followed by water separation to produce pyrolytic lignin and hydrotreating of the lignin could be used to produce a stable volatile low-oxygen intermediate liquid. Such a liquid could be converted into a finished motor-fuel in a refinery, taking advantage of the existing infrastructure and economies of scale of refineries. Hydrotreating just the lignin would consume less hydrogen while preserving about half of the energy of the original oil. The aqueous by-products could be reformed to produce the needed hydrogen and would contain much of the unwanted acids and unstable oxygenates. To assess such intermediate liquids, several pyrolytic lignins were prepared by mixing pyrolysis oil with water at 1:1 and 3:1 ratios. The carboxylic acidity in the pyrolytic lignin was reduced to 24 and 10 mg-KOH/g-lignin compared to 81 in the whole oil. These lignins were hydrotreated using Ni-Mo(S)/alumina, Pt/char, or Pd/C(activated) in a semi-batch 1 L stirred autoclave. The oil was stabilized under hydrogen at 150-280 degrees C, then water and light organics were removed by partial depressurization. Hydrodeoxygenation was then performed at 340-400 degrees C. Total pressure was controlled at 70 or 170 bar with hydrogen gas. Organic liquid yields of 39-56% were obtained. For many experiments the organic oxygen content was oil, the volatility was greater than or equal to 94% and, on a carbon basis, the total yield of organic products miscible in hydrocarbons at a 1:10 ratio was over 50%. These properties are probably acceptable to a refinery.The residual liquids left in the reactor at the end of the experiment comprised 60-85% of the organic-phase product while the rest was condensate. 13C-NMR of the residual liquids showed that they were 50-80% aliphatic. 13C-NMR coupled with GC-MS identified phenolic compounds as the main oxygenates in most residual liquids.

French, R. J.

2013-09-01T23:59:59.000Z

393

Hydrotreating Pyrolytic Lignin to Produce a Refinery Feedstock (Poster)  

DOE Green Energy (OSTI)

Fast pyrolysis of biomass followed by water separation to produce pyrolytic lignin and hydrotreating of the lignin could be used to produce a stable volatile low-oxygen intermediate liquid. Such a liquid could be converted into a finished motor-fuel in a refinery, taking advantage of the existing infrastructure and economies of scale of refineries. Hydrotreating just the lignin would consume less hydrogen while preserving about half of the energy of the original oil. The aqueous by-products could be reformed to produce the needed hydrogen and would contain much of the unwanted acids and unstable oxygenates. To assess such intermediate liquids, several pyrolytic lignins were prepared by mixing pyrolysis oil with water at 1:1 and 3:1 ratios. The carboxylic acidity in the pyrolytic lignin was reduced to 24 and 10 mg-KOH/g-lignin compared to 81 in the whole oil. These lignins were hydrotreated using Ni-Mo(S)/alumina, Pt/char, or Pd/C(activated) in a semi-batch 1 L stirred autoclave. The oil was stabilized under hydrogen at 150-280 degrees C, then water and light organics were removed by partial depressurization. Hydrodeoxygenation was then performed at 340-400 degrees C. Total pressure was controlled at 70 or 170 bar with hydrogen gas. Organic liquid yields of 39-56% were obtained. For many experiments the organic oxygen content was <7%, acidity was < 7 mg-KOH/g-oil, the volatility was greater than or equal to 94% and, on a carbon basis, the total yield of organic products miscible in hydrocarbons at a 1:10 ratio was over 50%. These properties are probably acceptable to a refinery.The residual liquids left in the reactor at the end of the experiment comprised 60-85% of the organic-phase product while the rest was condensate. 13C-NMR of the residual liquids showed that they were 50-80% aliphatic. 13C-NMR coupled with GC-MS identified phenolic compounds as the main oxygenates in most residual liquids.

French, R. J.

2013-09-01T23:59:59.000Z

394

Revisiting the "Buy versus Build" decision for publicly owned utilities in California considering wind and geothermal resources  

E-Print Network (OSTI)

for renewable energy projects than for non-renewable ones.Non-Utility Generator Power Purchase Agreement Public Power Renewable Energy

Bolinger, Mark; Wiser, Ryan; Golove, William

2001-01-01T23:59:59.000Z

395

,"U.S. Production Capacity of Operable Petroleum Refineries"  

U.S. Energy Information Administration (EIA) Indexed Site

Production Capacity of Operable Petroleum Refineries" Production Capacity of Operable Petroleum Refineries" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description","# Of Series","Frequency","Latest Data for" ,"Data 1","U.S. Production Capacity of Operable Petroleum Refineries",11,"Annual",2013,"6/30/1982" ,"Release Date:","6/21/2013" ,"Next Release Date:","6/20/2014" ,"Excel File Name:","pet_pnp_capprod_dcu_nus_a.xls" ,"Available from Web Page:","http://www.eia.gov/dnav/pet/pet_pnp_capprod_dcu_nus_a.htm" ,"Source:","Energy Information Administration" ,"For Help, Contact:","infoctr@eia.gov"

396

,"U.S. Working Storage Capacity at Operable Refineries"  

U.S. Energy Information Administration (EIA) Indexed Site

Storage Capacity at Operable Refineries" Storage Capacity at Operable Refineries" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description","# Of Series","Frequency","Latest Data for" ,"Data 1","U.S. Working Storage Capacity at Operable Refineries",28,"Annual",2013,"6/30/1982" ,"Release Date:","6/21/2013" ,"Next Release Date:","6/20/2014" ,"Excel File Name:","pet_pnp_capwork_dcu_nus_a.xls" ,"Available from Web Page:","http://www.eia.gov/dnav/pet/pet_pnp_capwork_dcu_nus_a.htm" ,"Source:","Energy Information Administration" ,"For Help, Contact:","infoctr@eia.gov"

397

,"U.S. Downstream Charge Capacity of Operable Petroleum Refineries"  

U.S. Energy Information Administration (EIA) Indexed Site

Charge Capacity of Operable Petroleum Refineries" Charge Capacity of Operable Petroleum Refineries" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description","# Of Series","Frequency","Latest Data for" ,"Data 1","U.S. Downstream Charge Capacity of Operable Petroleum Refineries",32,"Annual",2013,"6/30/1982" ,"Release Date:","6/21/2013" ,"Next Release Date:","6/20/2014" ,"Excel File Name:","pet_pnp_capchg_dcu_nus_a.xls" ,"Available from Web Page:","http://www.eia.gov/dnav/pet/pet_pnp_capchg_dcu_nus_a.htm" ,"Source:","Energy Information Administration" ,"For Help, Contact:","infoctr@eia.gov"

398

,"U.S. Total Shell Storage Capacity at Operable Refineries"  

U.S. Energy Information Administration (EIA) Indexed Site

Shell Storage Capacity at Operable Refineries" Shell Storage Capacity at Operable Refineries" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description","# Of Series","Frequency","Latest Data for" ,"Data 1","U.S. Total Shell Storage Capacity at Operable Refineries",28,"Annual",2013,"6/30/1982" ,"Release Date:","6/21/2013" ,"Next Release Date:","6/20/2014" ,"Excel File Name:","pet_pnp_capshell_dcu_nus_a.xls" ,"Available from Web Page:","http://www.eia.gov/dnav/pet/pet_pnp_capshell_dcu_nus_a.htm" ,"Source:","Energy Information Administration" ,"For Help, Contact:","infoctr@eia.gov"

399

Market Assessment of Planned Refinery Outages March Â… June 2009  

Gasoline and Diesel Fuel Update (EIA)

09)/1 09)/1 Market Assessment of Planned Refinery Outages March - June 2009 March 2009 Energy Information Administration Office of Oil and Gas U.S. Department of Energy Washington, DC 20585 This report was prepared by the Energy Information Administration, the independent statistical and analytical agency within the U.S. Department of Energy. The information contained herein should be attributed to the Energy Information Administration and should not be construed as advocating or reflecting any policy position of the U.S. Department of Energy or any other organization. Service Reports are prepared by the Energy Information Administration upon special request and are based on assumptions specified by the requestor.

400

Optimization of Steam Network in Tehran Oil Refinery  

E-Print Network (OSTI)

Dominated energy crisis in the world dictates to reduce energy consumption and identify energy saving opportunities in large and complex industries especially in oil refining industry. In this paper, Tehran oil refinery is considered as a proper case study and its steam network is analyzed. At the first step, using STAR software, the steam network is simulated and then optimized, which determines the optimum conditions. In this regard, energy saving potential was identified and total operating costs (TOC) in two states of fixed fuel fraction and changeable fuel fraction was calculated. In addition, different scenarios were proposed like using HRSG instead of two boilers. The results showed that amount of total operating cost has been reduced, as the result the best scenario regarding TOC is selected.

Khodaie, H.; Nasr, M. R. J.

2008-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


401

Low Temperature Waste Energy Recovery at Chemical Plants and Refineries  

E-Print Network (OSTI)

Technologies to economically recover low-temperature waste energy in chemical plants and refineries are the holy grail of industrial energy efficiency. Low temperature waste energy streams were defined by the Texas Industries of the Future Chemical and Refining Sectors Advisory Committee as streams with a temperature below 400 degrees F. Their waste energy streams were also characterized as to state, flow rate, heat content, source and temperature. These criteria were then used to identify potential candidates of waste heat recovery technologies that might have an application in these industries. Four technologies that met the criteria of the Advisory Committee included: organic rankine cycle (ORC), absorption refrigeration and chilling, Kalina cycle, and fuel cell technologies. This paper characterizes each of these technologies, technical specifications, limitations, potential costs/ payback and commercialization status as was discussed in the Technology Forum held in Houston, TX in May 2012 (TXIOF 2012).

Ferland, K.; papar, R.; Quinn, J.; Kumar, S.

2013-01-01T23:59:59.000Z

402

Refinery & Blenders Net Input of Crude Oil  

U.S. Energy Information Administration (EIA) Indexed Site

Input Input Product: Total Crude Oil & Petroleum Products Crude Oil Natural Gas Plant Liquids and Liquefied Refinery Gases Pentanes Plus Liquefied Petroleum Gases Ethane Normal Butane Isobutane Other Liquids Hydrogen/Oxygenates/Renewables/Other Hydrocarbons Hydrogen Oxygenates (excl. Fuel Ethanol) Methyl Tertiary Butyl Ether (MTBE) All Other Oxygenates Renewable Fuels (incl. Fuel Ethanol) Fuel Ethanol Renewable Diesel Fuel Other Renewable Fuels Other Hydrocarbons Unfinished Oils (net) Unfinished Oils, Naphthas and Lighter Unfinished Oils, Kerosene and Light Gas Oils Unfinished Oils, Heavy Gas Oils Residuum Motor Gasoline Blending Components (MGBC) (net) MGBC - Reformulated MGBC - Reformulated - RBOB MGBC - Reformulated, RBOB for Blending w/ Alcohol MGBC - Reformulated, RBOB for Blending w/ Ether MGBC - Reformulated, GTAB MGBC - Conventional MGBC - CBOB MGBC - Conventional, GTAB MGBC - Other Conventional Aviation Gasoline Blending Components (net) Period-Unit: Monthly-Thousand Barrels Monthly-Thousand Barrels per Day Annual-Thousand Barrels Annual-Thousand Barrels per Day

403

1170-MW(t) HTGR-PS/C plant application study report: Geismar, Louisiana refinery/chemical complex application  

SciTech Connect

This report summarizes a study to apply an 1170-MW(t) high-temperature gas-cooled reactor - process steam/cogeneration (HTGR-PS/C) to an industrial complex at Geismar, Louisiana. This study compares the HTGR with coal and oil as process plant fuels. This study uses a previous broad energy alternative study by the Stone and Webster Corporation on refinery and chemical plant needs in the Gulf States Utilities service area. The HTGR-PS/C was developed by General Atomic (GA) specifically for industries which require both steam and electric energy. The GA 1170-MW(t) HTGR-PC/C design is particularly well suited to industrial applications and is expected to have excellent cost benefits over other energy sources.

McMain, Jr., A. T.; Stanley, J. D.

1981-05-01T23:59:59.000Z

404

Power Sales to Electric Utilities  

SciTech Connect

The Public Utilities Regulatory Policies Act (PURPA) of 1979 requires that electrical utilities interconnect with qualifying facilities and purchase electricity at a rate based upon their full avoided costs (i.e., costs of providing both capacity and energy). Qualifying facilities (QF) include solar or geothermal electric units, hydropower, municipal solid waste or biomass-fired power plants, and cogeneration projects that satisfy maximum size, fuel use, ownership, location, and/or efficiency criteria. In Washington State, neither standard power purchase prices based upon a proxy ''avoided plant'', standard contracts, or a standard offer process have been used. Instead, a variety of power purchase contracts have been negotiated by developers of qualifying facilities with investor-owned utilities, public utility districts, and municipally-owned and operated utilities. With a hydro-based system, benefits associated with resource acquisition are determined in large part by how compatible the resource is with a utility's existing generation mix. Power purchase rates are negotiated and vary according to firm energy production, guarantees, ability to schedule maintenance or downtime, rights of refusal, power plant purchase options, project start date and length of contract; front-loading or levelization provisions; and the ability of the project to provide ''demonstrated'' capacity. Legislation was also enacted which allows PURPA to work effectively. Initial laws established ownership rights and provided irrigation districts, PUDs, and municipalities with expanded enabling powers. Financial processes were streamlined and, in some cases, simplified. Finally, laws were passed which are designed to ensure that development proceeds in an environmentally acceptable manner. In retrospect, PURPA has worked well within Washington. In the state of Washington, 20 small-scale hydroelectric projects with a combined generating capacity of 77 MW, 3 solid waste-to-energy facilities with 55 MW of electrical output, 4 cogeneration projects with 34.5 MW of generating capability, and 4 wastewater treatment facility digester gas-to-energy projects with 5 MW of electrical production have come on-line (or are in the final stages of construction) since the passage of PURPA. These numbers represent only a small portion of Washington's untapped and underutilized cogeneration and renewable resource generating potentials. [DJE-2005

None

1989-02-01T23:59:59.000Z

405

Power Sales to Electric Utilities  

SciTech Connect

The Public Utilities Regulatory Policies Act (PURPA) of 1979 requires that electrical utilities interconnect with qualifying facilities and purchase electricity at a rate based upon their full avoided costs (i.e., costs of providing both capacity and energy). Qualifying facilities (QF) include solar or geothermal electric units, hydropower, municipal solid waste or biomass-fired power plants, and cogeneration projects that satisfy maximum size, fuel use, ownership, location, and/or efficiency criteria. In Washington State, neither standard power purchase prices based upon a proxy ''avoided plant'', standard contracts, or a standard offer process have been used. Instead, a variety of power purchase contracts have been negotiated by developers of qualifying facilities with investor-owned utilities, public utility districts, and municipally-owned and operated utilities. With a hydro-based system, benefits associated with resource acquisition are determined in large part by how compatible the resource is with a utility's existing generation mix. Power purchase rates are negotiated and vary according to firm energy production, guarantees, ability to schedule maintenance or downtime, rights of refusal, power plant purchase options, project start date and length of contract; front-loading or levelization provisions; and the ability of the project to provide ''demonstrated'' capacity. Legislation was also enacted which allows PURPA to work effectively. Initial laws established ownership rights and provided irrigation districts, PUDs, and municipalities with expanded enabling powers. Financial processes were streamlined and, in some cases, simplified. Finally, laws were passed which are designed to ensure that development proceeds in an environmentally acceptable manner. In retrospect, PURPA has worked well within Washington. In the state of Washington, 20 small-scale hydroelectric projects with a combined generating capacity of 77 MW, 3 solid waste-to-energy facilities with 55 MW of electrical output, 4 cogeneration projects with 34.5 MW of generating capability, and 4 wastewater treatment facility digester gas-to-energy projects with 5 MW of electrical production have come on-line (or are in the final stages of construction) since the passage of PURPA. These numbers represent only a small portion of Washington's untapped and underutilized cogeneration and renewable resource generating potentials. [DJE-2005

1989-02-01T23:59:59.000Z

406

Renewable Electricity Purchases: History and Recent Developments  

Reports and Publications (EIA)

This article presents an analysis of prices of renewable-based electricity that utilities have paid to nonutilities, the primary generators of renewable electricity.

Information Center

1999-02-01T23:59:59.000Z

407

House Passage of H.R. 5254 - The Refinery Permit Process Schedule Act |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Passage of H.R. 5254 - The Refinery Permit Process Schedule Passage of H.R. 5254 - The Refinery Permit Process Schedule Act House Passage of H.R. 5254 - The Refinery Permit Process Schedule Act June 8, 2006 - 2:17pm Addthis Statement from Secretary Bodman WASHINGTON, DC - The following is a statement from the Secretary Samuel W. Bodman of the Department of Energy on the passage of House Resolution 5254, The Refinery Permit Process Schedule Act: "I commend the House of Representatives for their passage of this important piece of legislation. Expanding our nation's refining capacity is an important part of President Bush's four-point plan to confront high gasoline prices and is a key component to strengthening our nation's energy security. By increasing our nation's domestic refining capacity we can help grow our nation's economy and reduce our reliance on foreign sources

408

Market Assessment of Refinery Outages Planned for March 2011 through June 2011  

Gasoline and Diesel Fuel Update (EIA)

Assessment of Refinery Assessment of Refinery Outages Planned for March 2011 through June 2011 APRIL 2011 www.eia.gov U.S. Department of Energy Washington, DC 20585 U.S. Energy Information Administration / Market Assessment of Planned Refinery Outages / March 2011 - June 2011 ii This report was prepared by the U.S. Energy Information Administration (EIA), the statistical and analytical agency within the U.S. Department of Energy. By law, EIA's data, analyses, and forecasts are independent of approval by any other officer or employee of the United States Government. The views in this report therefore should not be construed as representing those of the Department of Energy or other Federal agencies. U.S. Energy Information Administration / Market Assessment of Planned Refinery Outages /

409

Appendix D Short-Term Analysis of Refinery Costs and Supply  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Short-Term Analysis of Refinery Costs and Supply 9302 Appendix D Short-Term Analysis of Refinery Costs and Supply As a result of the new regulations issued by the U.S. Estimating Components of the Distillate Environmental Protection Agency (EPA) for ultra-low- Blend Pool sulfur diesel fuel (ULSD) the U.S. refining industry faces two major challenges: to meet the more stringent specifi- The initial step of the analysis was to analyze the poten- cations for diesel product, and to keep up with demand tial economics of producing ULSD for each refinery. by producing more diesel product from feedstocks of Using input and output data submitted to the Energy lower quality. Some refineries in the United States and Information Administration (E1A) by refiners, the cur-

410

Refinery Furnaces Retrofit with Gas Turbines Achieve Both Energy Savings and Emission Reductions  

E-Print Network (OSTI)

Integrating gas turbines with refinery furnaces can be a cost effective means of reducing NOx emissions while also generating electricity at an attractive heat rate. Design considerations and system costs are presented.

Giacobbe, F.; Iaquaniello, G.; Minet, R. G.; Pietrogrande, P.

1985-05-01T23:59:59.000Z

411

,"U.S. Refinery, Bulk Terminal, and Natural Gas Plant Stocks...  

U.S. Energy Information Administration (EIA) Indexed Site

S1","MDGSXUS1","MRESXUS1","MPRSXUS1" "Date","U.S. Finished Motor Gasoline Stocks at Refineries, Bulk Terminals, and Natural Gas Plants (Thousand Barrels)","U.S. Reformulated Motor...

412

U.S. Refinery and Blender Net Production of Normal Butane ...  

U.S. Energy Information Administration (EIA)

U.S. Refinery and Blender Net Production of Normal Butane (Thousand Barrels) Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec; 1993-884: 268: 4,851: 6,387: 6,489 ...

413

Valero: Houston Refinery Uses Plant-Wide Assessment to Develop an Energy Optimization and Management System  

SciTech Connect

This Industrial Technologies Program case study describes an energy assessment team's recommendations for saving $5 million in energy, water, and other costs at an oil refinery in Houston, Texas.

Not Available

2005-08-01T23:59:59.000Z

414

U.S. Refinery Hydrogen Production Capacity as of January 1 ...  

U.S. Energy Information Administration (EIA)

U.S. Refinery Hydrogen Production Capacity as of January 1 (Million Cubic Feet per Day) Decade Year-0 Year-1 Year-2 Year-3 Year-4 Year-5 Year-6 Year-7 Year-8 Year-9 ...

415

U.S. Refinery Grade Butane Stocks at Bulk Terminals (Thousand ...  

U.S. Energy Information Administration (EIA)

U.S. Refinery Grade Butane Stocks at Bulk Terminals (Thousand Barrels) Decade Year-0 Year-1 Year-2 Year-3 Year-4 Year-5 Year-6 Year-7 Year-8 Year-9; ...

416

U.S. Refinery Normal Butane/Butylene Shell Storage Capacity as ...  

U.S. Energy Information Administration (EIA)

U.S. Refinery Normal Butane/Butylene Shell Storage Capacity as of January 1 (Thousand Barrels) Decade Year-0 Year-1 Year-2 Year-3 Year-4 Year-5 Year-6 ...

417

U.S. Refinery Grade Butane Stocks at Bulk Terminals (Thousand ...  

U.S. Energy Information Administration (EIA)

U.S. Refinery Grade Butane Stocks at Bulk Terminals (Thousand Barrels) Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec; 2005: 1,077: 999: 1,362: ...

418

Models and algorithms for a multilevel control system of primary oil refinery installations  

Science Conference Proceedings (OSTI)

Algorithms and mathematical models for the technological process of primary oil refinery operating in the uncertain conditions are developed; the solution of the optimal control problem in the form of stochastic programming with probabilistic characteristics ...

I. A. Guseinov; E. A. Melikov; N. A. Khanbutaeva; I. R. Efendiev

2012-02-01T23:59:59.000Z

419

West Coast (PADD 5) Foreign Crude Oil Refinery Receipts by Tank ...  

U.S. Energy Information Administration (EIA)

West Coast (PADD 5) Foreign Crude Oil Refinery Receipts by Tank Cars (Rail) (Thousand Barrels) Decade Year-0 Year-1 Year-2 Year-3 Year-4 Year-5 Year-6 Year-7 Year-8 ...

420

City of Boulder - Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

City of Boulder - Green Power Purchasing City of Boulder - Green Power Purchasing City of Boulder - Green Power Purchasing < Back Eligibility Local Government Savings Category Wind Buying & Making Electricity Program Info State Colorado Program Type Green Power Purchasing Provider City of Boulder The City of Boulder purchases a portion of its electricity supply from wind power through Xcel Energy's Windsource program and Renewable Choice Energy, headquartered in Colorado. Boulder purchases approximately 470,000 kWh annually to provide clean power for its municipal buildings. Boulder also installed a solar water heating system with 128 thermal panels on one of its city-owned pools. The city now has 1,955 kilowatts (kW) of photovoltaics installed with an additional 349 kW planned. These efforts

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


421

High Performance Windows Volume Purchase: Presentations for Past Events and  

NLE Websites -- All DOE Office Websites (Extended Search)

Presentations for Past Events and Webinars to someone by E-mail Share High Performance Windows Volume Purchase: Presentations for Past Events and Webinars on Facebook Tweet about High Performance Windows Volume Purchase: Presentations for Past Events and Webinars on Twitter Bookmark High Performance Windows Volume Purchase: Presentations for Past Events and Webinars on Google Bookmark High Performance Windows Volume Purchase: Presentations for Past Events and Webinars on Delicious Rank High Performance Windows Volume Purchase: Presentations for Past Events and Webinars on Digg Find More places to share High Performance Windows Volume Purchase: Presentations for Past Events and Webinars on AddThis.com... Home About For Builders For Residential Buyers For Light Commercial Buyers

422

Federal Energy Management Program: On-Site Renewable Power Purchase  

NLE Websites -- All DOE Office Websites (Extended Search)

On-Site Renewable Power Purchase Agreements On-Site Renewable Power Purchase Agreements Graphic of the eTraining logo Training Available Federal On-Site Renewable Power Purchase Agreements: Learn how to develop an on-site renewable Power Purchase Agreement (PPA) by taking this FEMP eTraining course. At a Glance Power purchase agreements feature a variety of benefits and considerations for Federal agencies, including: Benefits: No up-front capital costs Ability to monetize tax incentives Typically a known, long-term energy price No operations and maintenance responsibilities Minimal risk to the agency Considerations: Federal sector experience with PPAs is still growing Contract term limitations Inherent transaction costs Challenges with site access contracts and concerns On-site renewable power purchase agreements (PPAs) allow Federal agencies to fund on-site renewable energy projects with no up-front capital costs incurred.

423

City of Santa Monica - Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Green Power Purchasing Green Power Purchasing City of Santa Monica - Green Power Purchasing < Back Eligibility Local Government Savings Category Bioenergy Buying & Making Electricity Program Info State California Program Type Green Power Purchasing Provider City of Santa Monica The City of Santa Monica made history June 1, 1999, as green electricity began powering all municipal facilities -- including the Santa Monica Airport, City Hall and the Santa Monica Pier -- making it the first city in the world to switch to 100% renewable resources to meet the power needs of city facilities. Under the contract, the city purchases approximately 5MW of renewables. The proposed purchase is equivalent to the amount of electricity used by 5,000 to 6,000 homes. Commerce Energy (formerly "Commonwealth Energy") currently provides the

424

Assuring Mechanical Integrity of Refinery Equipment Through Global ON-Stream Inspection  

SciTech Connect

The development of global on-stream inspection technology will have a dramatic effect on how refinery operations are managed in the U.S. in the future. Global on-stream inspection will provide assurance of the mechanical integrity of critical plant equipment and will allow refineries to operate more efficiently with less impact on our environment and with an increased margin of safety.

John W. Berthold

2006-02-22T23:59:59.000Z

425

Purchase energy-saving products | ENERGY STAR Buildings & Plants  

NLE Websites -- All DOE Office Websites (Extended Search)

Purchase energy-saving products Purchase energy-saving products Secondary menu About us Press room Contact Us Portfolio Manager Login Facility owners and managers Existing buildings Commercial new construction Industrial energy management Small business Service providers Service and product providers Verify applications for ENERGY STAR certification Design commercial buildings Energy efficiency program administrators Commercial and industrial program sponsors Associations State and local governments Federal agencies Tools and resources Training In this section Learn the benefits Get started Use Portfolio Manager Save energy Stamp out energy waste Find cost-effective investments Engage occupants Purchase energy-saving products Purchasing and procurement case studies Put computers to sleep Get help from an expert

426

Kansas Crude Oil First Purchase Price (Dollars per Barrel)  

U.S. Energy Information Administration (EIA)

Release Date: 11/1/2013: Next Release Date: 12/2/2013: Referring Pages: Domestic Crude Oil First Purchase Prices by Area

427

Wyoming Crude Oil First Purchase Price (Dollars per Barrel)  

U.S. Energy Information Administration (EIA)

96.51: 97.39-= No Data Reported; --= Not Applicable; NA = Not Available; ... Domestic Crude Oil First Purchase Prices by Area ...

428

North Dakota Crude Oil First Purchase Price (Dollars per ...  

U.S. Energy Information Administration (EIA)

Release Date: 1/2/2014: Next Release Date: 2/3/2014: Referring Pages: Domestic Crude Oil First Purchase Prices by Area

429

Texas Crude Oil First Purchase Price (Dollars per Barrel)  

U.S. Energy Information Administration (EIA)

Release Date: 10/1/2013: Next Release Date: 11/1/2013: Referring Pages: Domestic Crude Oil First Purchase Prices by Area

430

Crude Oil Prices Table 21. Domestic Crude Oil First Purchase...  

Gasoline and Diesel Fuel Update (EIA)

Information Administration Petroleum Marketing Annual 1995 41 Table 21. Domestic Crude Oil First Purchase Prices (Dollars per Barrel) - Continued Year Month PAD District II...

431

City of Houston - Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

January 2009 and December 2012, Houston has captured the second spot on the EPA's list of green energy purchases by local governments. http:www.dsireusa.orgincentives...

432

West Texas Intermediate First Purchase Price (Dollars per Barrel)  

U.S. Energy Information Administration (EIA)

Release Date: 7/1/2013: Next Release Date: 8/1/2013: Referring Pages: Domestic Crude Oil First Purchase Prices for Selected Crude Streams

433

EIA-182 DOMESTIC CRUDE OIL FIRST PURCHASE REPORT INSTRUCTIONS  

U.S. Energy Information Administration (EIA)

average wellhead price for selected domestic crude oil streams aggregated by State. First purchase volumes are also used in ... such as butane and

434

GovEnergy 2008 Session Presentation on Power Purchase Agreements  

Energy.gov (U.S. Department of Energy (DOE))

Presentation describes an overview of power purchase agreements given at GovEnergy 2008. The document includes several case studies and considerations for Federal agencies.

435

City of Madison - Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

1999, Madison's Metro Maintenance & Administration Facility began purchasing 25% of its electricity from Madison Gas & Electric's wind power program. The additional cost to...

436

On EOQ Cost Models with Arbitrary Purchase and Transportation ...  

E-Print Network (OSTI)

Abstract: We analyze an economic order quantity cost model with unit ... For the remaining purchase-transportation cost functions, when this problem becomes a  ...

437

Highly Insulating Windows Volume Purchase Program Final Report  

SciTech Connect

This report summarizes the Highly Insulating Windows Volume Purchase Program, conduced by PNNL for DOE-BTP, including a summary of outcomes and lessons learned.

Parker, Graham B.; Mapes, Terry S.; Zalis, WJ

2013-02-01T23:59:59.000Z

438

Colorado Crude Oil First Purchase Price (Dollars per Barrel)  

U.S. Energy Information Administration (EIA)

Release Date: 10/1/2013: Next Release Date: 11/1/2013: Referring Pages: Domestic Crude Oil First Purchase Prices by Area

439

Revisiting the Income Effect: Gasoline Prices and Grocery Purchases  

E-Print Network (OSTI)

On Sale Residuals Log Gas Price Residuals Week Log %On Sale Residuals Log Gas Price Residuals Week Log %On Sale Residuals Log Gas Price Residuals Log % Purchased On

Gicheva, Dora; Hastings, Justine; Villas-Boas, Sofia B

2008-01-01T23:59:59.000Z

440

Michigan Crude Oil First Purchase Price (Dollars per Barrel)  

U.S. Energy Information Administration (EIA)

Release Date: 10/1/2013: Next Release Date: 11/1/2013: Referring Pages: Domestic Crude Oil First Purchase Prices by Area

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


441

New Mexico Crude Oil First Purchase Price (Dollars per Barrel)  

U.S. Energy Information Administration (EIA)

Release Date: 11/1/2013: Next Release Date: 12/2/2013: Referring Pages: Domestic Crude Oil First Purchase Prices by Area

442

Farmers Electric Cooperative (Kalona) - Renewable Energy Purchase...  

Open Energy Info (EERE)

Clean Energy Analysis Low Emission Development Strategies Oil & Gas Smart Grid Solar U.S. OpenLabs Utilities Water Wind Page Actions View form View source History View New Pages...

443

Using Renewable Energy Purchases to Achieve Institutional Carbon Goals: A Review of Current Practices and Considerations  

SciTech Connect

With organizations and individuals increasingly interested in accounting for their carbon emissions, greater attention is being placed on how to account for the benefits of various carbon mitigation actions available to consumers and businesses. Generally, organizations can address their own carbon emissions through energy efficiency, fuel switching, on-site renewable energy systems, renewable energy purchased from utilities or in the form of renewable energy certificates (RECs), and carbon offsets. This paper explores the role of green power and carbon offsets in carbon footprinting and the distinctions between the two products. It reviews how leading greenhouse gas (GHG) reporting programs treat green power purchases and discusses key issues regarding how to account for the carbon benefits of renewable energy. It also discusses potential double counting if renewable energy generation is used in multiple markets.

Bird, L.; Sumner, J.

2011-01-01T23:59:59.000Z

444

U.S. Refinery & Blender Net Input  

U.S. Energy Information Administration (EIA) Indexed Site

Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 View Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 View History Total 526,996 566,851 559,032 581,600 578,456 543,388 1981-2013 Crude Oil 445,937 474,296 474,991 497,241 489,887 468,825 1981-2013 Natural Gas Plant Liquids and Liquefied Refinery Gases 12,805 11,759 12,769 13,227 13,760 16,794 1981-2013 Pentanes Plus 4,949 4,341 4,752 4,734 5,331 5,666 1981-2013 Liquefied Petroleum Gases 7,856 7,418 8,017 8,493 8,429 11,128 1981-2013 Ethane 1981-1992 Normal Butane 2,668 1,880 1,998 2,014 2,083 4,711 1981-2013 Isobutane 5,188 5,538 6,019 6,479 6,346 6,417 1981-2013 Other Liquids 68,254 80,796 71,272 71,132 74,809 57,769 1981-2013 Hydrogen/Oxygenates/Renewables/ Other Hydrocarbons 32,667 34,665 34,097 35,446 36,356 33,881 1981-2013

445

U.S. Refinery and Blender Net Production  

U.S. Energy Information Administration (EIA) Indexed Site

2007 2008 2009 2010 2011 2012 View 2007 2008 2009 2010 2011 2012 View History Total 6,567,929 6,641,293 6,527,069 6,735,067 6,815,590 6,794,407 1981-2012 Liquefied Refinery Gases 238,904 230,431 227,470 240,454 225,992 230,413 1981-2012 Ethane/Ethylene 7,323 6,671 7,069 7,228 7,148 6,597 1981-2012 Ethane 5,145 4,608 5,229 5,200 5,105 4,835 1993-2012 Ethylene 2,178 2,063 1,840 2,028 2,043 1,762 1993-2012 Propane/Propylene 205,179 190,020 196,011 204,223 201,492 202,309 1981-2012 Propane 120,596 114,268 106,177 102,913 98,508 100,933 1995-2012 Propylene 84,583 75,752 89,834 101,310 102,984 101,376 1993-2012 Normal Butane/Butylene 24,285 30,887 24,148 30,281 17,449 20,580 1981-2012 Normal Butane 25,715 33,092 25,825 32,094 19,263 22,965 1993-2012

446

U.S. Refinery and Blender Net Production  

U.S. Energy Information Administration (EIA) Indexed Site

Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 View Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 View History Total 559,639 599,643 591,916 616,905 613,451 578,101 1981-2013 Liquefied Refinery Gases 24,599 26,928 25,443 26,819 25,951 19,023 1981-2013 Ethane/Ethylene 464 426 407 441 487 379 1981-2013 Ethane 317 277 283 312 332 232 1993-2013 Ethylene 147 149 124 129 155 147 1993-2013 Propane/Propylene 16,840 17,792 16,966 17,839 18,063 17,254 1981-2013 Propane 8,051 8,949 8,756 9,002 9,153 8,816 1995-2013 Propylene 8,789 8,843 8,210 8,837 8,910 8,438 1993-2013 Normal Butane/Butylene 7,270 8,876 8,122 8,676 7,664 1,738 1981-2013 Normal Butane 7,447 9,044 8,314 8,832 8,067 1,743 1993-2013 Butylene -177 -168 -192 -156 -403 -5 1993-2013 Isobutane/Isobutylene

447

U.S. Refinery & Blender Net Input  

U.S. Energy Information Administration (EIA) Indexed Site

2007 2008 2009 2010 2011 2012 View 2007 2008 2009 2010 2011 2012 View History Total 6,204,500 6,277,893 6,169,893 6,345,372 6,422,710 6,406,693 1981-2012 Crude Oil 5,532,097 5,361,287 5,232,656 5,374,094 5,404,347 5,489,516 1981-2012 Natural Gas Plant Liquids and Liquefied Refinery Gases 184,383 177,559 177,194 161,479 178,884 186,270 1981-2012 Pentanes Plus 64,603 55,497 59,100 56,686 63,385 63,596 1981-2012 Liquefied Petroleum Gases 119,780 122,062 118,094 104,793 115,499 122,674 1981-2012 Ethane 1981-1992 Normal Butane 48,292 50,024 48,509 43,802 47,571 52,246 1981-2012 Isobutane 71,488 72,038 69,585 60,991 67,928 70,428 1981-2012 Other Liquids 488,020 739,047 760,043 809,799 839,479 730,907 1981-2012 Hydrogen/Oxygenates/Renewables/ Other Hydrocarbons

448

Refinery & Blender Net Production of Total Finished Petroleum Products  

U.S. Energy Information Administration (EIA) Indexed Site

& Blender Net Production & Blender Net Production Product: Total Finished Petroleum Products Liquefied Refinery Gases Ethane/Ethylene Ethane Ethylene Propane/Propylene Propane Propylene Normal Butane/Butylene Normal Butane Butylene Isobutane/Isobutylene Isobutane Isobutylene Finished Motor Gasoline Reformulated Gasoline Reformulated Blended w/ Fuel Ethanol Reformulated Other Gasoline Conventional Gasoline Conventional Blended w/ Fuel Ethanol Conventional Blended w/ Fuel Ethanol, Ed55 and Lower Conventional Blended w/ Fuel Ethanol, Greater than Ed55 Conventional Other Finished Aviation Gasoline Kerosene-Type Jet Fuel Kerosene Distillate Fuel Oil Distillate F.O., 15 ppm Sulfur and under Distillate F.O., Greater than 15 ppm to 500 ppm Sulfur Distillate F.O., Greater than 500 ppm Sulfur Residual Fuel Oil Residual Fuel Less Than 0.31 Percent Sulfur Residual Fuel 0.31 to 1.00 Percent Sulfur Residual Fuel Greater Than 1.00 Percent Sulfur Petrochemical Feedstocks Naphtha For Petro. Feed. Use Other Oils For Petro. Feed. Use Special Naphthas Lubricants Waxes Petroleum Coke Marketable Petroleum Coke Catalyst Petroleum Coke Asphalt and Road Oil Still Gas Miscellaneous Products Processing Gain(-) or Loss(+) Period-Unit: Monthly-Thousand Barrels Monthly-Thousand Barrels per Day Annual-Thousand Barrels Annual-Thousand Barrels per Day

449

STANDARD TERMS OF PURCHASE APPLICABLE TO SUPPLY AND SERVICES CONTRACTS  

E-Print Network (OSTI)

STANDARD TERMS OF PURCHASE APPLICABLE TO SUPPLY AND SERVICES CONTRACTS ENTERED INTO BY INSTITUT DE PHYSIQUE DU GLOBE DE PARIS Article 1 ­ Scope of application of these terms The purpose of these standard terms of purchase is to define the framework of the contractual relationship between the IPGP and its co

Benzerara, Karim

450

Carbon Capture and Sequestration (via Enhanced Oil Recovery) from a Hydrogen Production Facility in an Oil Refinery  

Science Conference Proceedings (OSTI)

The project proposed a commercial demonstration of advanced technologies that would capture and sequester CO2 emissions from an existing hydrogen production facility in an oil refinery into underground formations in combination with Enhanced Oil Recovery (EOR). The project is led by Praxair, Inc., with other project participants: BP Products North America Inc., Denbury Onshore, LLC (Denbury), and Gulf Coast Carbon Center (GCCC) at the Bureau of Economic Geology of The University of Texas at Austin. The project is located at the BP Refinery at Texas City, Texas. Praxair owns and operates a large hydrogen production facility within the refinery. As part of the project, Praxair would construct a CO2 capture and compression facility. The project aimed at demonstrating a novel vacuum pressure swing adsorption (VPSA) based technology to remove CO2 from the Steam Methane Reformers (SMR) process gas. The captured CO2 would be purified using refrigerated partial condensation separation (i.e., cold box). Denbury would purchase the CO2 from the project and inject the CO2 as part of its independent commercial EOR projects. The Gulf Coast Carbon Center at the Bureau of Economic Geology, a unit of University of Texas at Austin, would manage the research monitoring, verification and accounting (MVA) project for the sequestered CO2, in conjunction with Denbury. The sequestration and associated MVA activities would be carried out in the Hastings field at Brazoria County, TX. The project would exceed DOE’s target of capturing one million tons of CO2 per year (MTPY) by 2015. Phase 1 of the project (Project Definition) is being completed. The key objective of Phase 1 is to define the project in sufficient detail to enable an economic decision with regard to proceeding with Phase 2. This topical report summarizes the administrative, programmatic and technical accomplishments completed in Phase 1 of the project. It describes the work relative to project technical and design activities (associated with CO2 capture technologies and geologic sequestration MVA), and Environmental Information Volume. Specific accomplishments of this Phase include: 1. Finalization of the Project Management Plan 2. Development of engineering designs in sufficient detail for defining project performance and costs 3. Preparation of Environmental Information Volume 4. Completion of Hazard Identification Studies 5. Completion of control cost estimates and preparation of business plan During the Phase 1 detailed cost estimate, project costs increased substantially from the previous estimate. Furthermore, the detailed risk assessment identified integration risks associated with potentially impacting the steam methane reformer operation. While the Phase 1 work identified ways to mitigate these integration risks satisfactorily from an operational perspective, the associated costs and potential schedule impacts contributed to the decision not to proceed to Phase 2. We have concluded that the project costs and integration risks at Texas City are not commensurate with the potential benefits of the project at this time.

Stewart Mehlman

2010-06-16T23:59:59.000Z

451

City of Philadelphia - Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Philadelphia - Green Power Purchasing Philadelphia - Green Power Purchasing City of Philadelphia - Green Power Purchasing < Back Eligibility Local Government Savings Category Water Buying & Making Electricity Solar Home Weatherization Wind Bioenergy Program Info State Pennsylvania Program Type Green Power Purchasing Provider Mayor's Office of Sustainability Philadelphia has committed to purchasing green power to supply 20% of the city's electricity by 2015.* In doing so, the city is exceeding the Pennsylvania Alternative Energy Portfolio Standard, which requires 11.2% renewables and "alternative" energy resources by 2015. Philadelphia also has a goal of producing 57.7 megawatts (MW) of solar power by 2021, of which 3.8 MW is currently on-line. The city's [http://www.phila.gov/green/pdfs/GW2012Report.pdf 2012 Greenworks Progress

452

On-Site Renewable Power Purchase Agreements | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Project Funding » On-Site Renewable Power Purchase Agreements Project Funding » On-Site Renewable Power Purchase Agreements On-Site Renewable Power Purchase Agreements October 7, 2013 - 3:35pm Addthis On-site renewable power purchase agreements (PPAs) allow Federal agencies to fund on-site renewable energy projects with no up-front capital costs incurred. With a PPA, a developer installs a renewable energy system on agency property under an agreement that the agency will purchase the power generated by the system. The agency pays for the system through these power payments over the life of the contract. After installation, the developer owns, operates, and maintains the system for the life of the contract. For more information, read the Federal Energy Mangement Program's (FEMP) introductory guide to PPAs and sample documents.

453

On-Site Renewable Power Purchase Agreements | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

On-Site Renewable Power Purchase Agreements On-Site Renewable Power Purchase Agreements On-Site Renewable Power Purchase Agreements October 16, 2013 - 5:09pm Addthis An on-site renewable power purchase agreement (PPA) enables Federal agencies to fund a renewable energy project by contracting to purchase the power generated by the system. The renewable energy equipment is installed and owned by a developer but located on-site at the agency facility. As noted in the renewable energy project funding overview, PPAs provide a range of attractive benefits to Federal agencies trying to access renewable energy. These include no up-front capital costs; the ability to monetize tax incentives; typically a known, long-term energy price; no operations and maintenance (O&M) responsibilities; and minimal risk to the agency.

454

Building Technologies Office: High Performance Windows Volume Purchase  

NLE Websites -- All DOE Office Websites (Extended Search)

High Performance Windows Volume Purchase High Performance Windows Volume Purchase DOE's Building Technologies Office (BTO) is coordinating a volume purchase of high performance windows, and low-e storm windows, to expand the market of these high efficiency products. Price is the principal barrier to more widespread market commercialization. The aim of this volume purchase initiative is to work with industry and potential buyers to make highly insulated windows more affordable. Announcement EPA Most Efficient Program for window technology to launched in January 2013. Program Highlights Features Image of person signing document. Volume Purchase RFP Arrow Image of a question mark. Frequently Asked Questions Arrow Image of low-e storm window with two orange-yellow arrows hitting the window and reflecting back inside. Building Envelope and Windows R&D Program Blog Arrow

455

City of Boston - Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Boston - Green Power Purchasing Boston - Green Power Purchasing City of Boston - Green Power Purchasing < Back Eligibility Local Government Savings Category Bioenergy Alternative Fuel Vehicles Hydrogen & Fuel Cells Solar Buying & Making Electricity Water Wind Program Info State Massachusetts Program Type Green Power Purchasing Provider City of Boston Environment Department In April 2007, Boston Mayor Thomas Menino issued an executive order that established a green power purchasing goal of 11% for the city government, effective immediately, and a goal of 15% by 2012. The executive order also requires all existing municipal properties to be evaluated for the feasibility of installing solar, wind, bio-energy, combined heat and power (CHP), and green roofs. (The executive order updated an announcement by

456

The Greenhouse Gas Protocol Initiative: GHG Emissions from Purchased  

Open Energy Info (EERE)

The Greenhouse Gas Protocol Initiative: GHG Emissions from Purchased The Greenhouse Gas Protocol Initiative: GHG Emissions from Purchased Electricity Jump to: navigation, search Tool Summary Name: The Greenhouse Gas Protocol Initiative: GHG Emissions from Purchased Electricity Agency/Company /Organization: World Resources Institute, World Business Council for Sustainable Development Sector: Energy, Climate Focus Area: Buildings, Greenhouse Gas Phase: Determine Baseline, Evaluate Effectiveness and Revise as Needed Resource Type: Software/modeling tools User Interface: Spreadsheet Website: www.ghgprotocol.org/calculation-tools/all-tools Cost: Free References: Electricity Heat, and Steam Purchase Guidance v1.2[1] The Greenhouse Gas Protocol tool for purchased electricity is a free Excel spreadsheet calculator designed to calculate GHG emissions specifically

457

City of Aspen - Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

City of Aspen - Green Power Purchasing City of Aspen - Green Power Purchasing City of Aspen - Green Power Purchasing < Back Eligibility Local Government Savings Category Water Buying & Making Electricity Wind Program Info State Colorado Program Type Green Power Purchasing Provider City of Aspen In 2005, the City of Aspen set a goal to purchase 75% of the city government's energy from renewable sources by 2010. As of December 2006, Aspen had accomplished its goal to provide 75% non-carbon electricity. The city has a new goal of powering 100% of the city-owned buildings with renewable sources by 2020. 27% of the electricity used by the City of Aspen comes from wind turbines located in Kimball, Nebraska. An additional 45% of the City's electricity comes from hydroelectric plants, with an additional plant, the Castle Creek

458

Sample Documents for On-Site Renewable Power Purchase Agreements |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Funding » On-Site Renewable Power Purchase Agreements » Funding » On-Site Renewable Power Purchase Agreements » Sample Documents for On-Site Renewable Power Purchase Agreements Sample Documents for On-Site Renewable Power Purchase Agreements October 7, 2013 - 3:37pm Addthis The Federal Energy Management Program (FEMP) works with Federal agencies and partners to assemble sample documents from past on-site renewable power purchase agreement (PPA) projects to help streamline the PPA process. Requests for Proposal and Contracts Sample documents are available for the following requests for proposal: Photovoltaics at the Department of Energy's (DOE) Princeton Plasma Physics Laboratory: PPA request for proposal issued by DLA Energy on behalf of Princeton Plasma Physics Laboratory. National Renewable Energy Laboratory (NREL) Photovoltaics Opportunity

459

Conversion of high carbon refinery by-products. Quarterly report, October 1--December 31, 1995  

SciTech Connect

The overall objective of the project is to demonstrate that a partial oxidation system, which utilizes a transport reactor, is a viable means of converting refinery wastes, byproducts, and other low value materials into valuable products. The primary product would be a high quality fuel gas, which could also be used as a source of hydrogen. The concept involves subjecting the hydrocarbon feed to pyrolysis and steam gasification in a circulating bed of solids. Carbon residue formed during pyrolysis, as well as metals in the feed, are captured by the circulating solids which are returned to the bottom of the transport reactor. Air or oxygen is introduced in this lower zone and sufficient carbon is burned, sub-stoichiometrically, to provide the necessary heat for the endothermic pyrolysis and gasification reactions. The hot solids and gases leaving this zone pass upward to contact the feed material and continue the partial oxidation process. Studies were conducted in the Transport Reactor Test Unit (TRTU) to pyrolyze naphtha with untreated as well as potassium-impregnated spent FCC (Fluid Catalytic Cracker) catalyst as the circulating medium over a temperature range of 1,400 to 1,600 F. The results from these studies are presented and discussed here. Studies were also performed in the Bench Scale Reactor Unit (BRU) in an effort to develop suitable catalyst formulations and to study the steam reforming of methane and propane in support of the experiments conducted in the TRTU. The results from these studies are also presented here. A Cold Flow Simulator (CFS) was designed and built to investigate the flow problems experienced in the TRTU.

O`Donnell, J.; Katta, S.; Henningsen, G.; Lin, Y.Y.

1996-01-19T23:59:59.000Z

460

,"U.S. Refinery Net Input"  

U.S. Energy Information Administration (EIA) Indexed Site

3,"Monthly","9/2013","1/15/2005" 3,"Monthly","9/2013","1/15/2005" ,"Data 2","Alaskan Crude Oil Receipts",1,"Monthly","9/2013","1/15/1986" ,"Release Date:","11/27/2013" ,"Next Release Date:","Last Week of December 2013" ,"Excel File Name:","pet_pnp_inpt2_dc_nus_mbbl_m.xls" ,"Available from Web Page:","http://www.eia.gov/dnav/pet/pet_pnp_inpt2_dc_nus_mbbl_m.htm" ,"Source:","Energy Information Administration" ,"For Help, Contact:","infoctr@eia.gov" ,,"(202) 586-8800",,,"11/25/2013 11:21:05 AM" "Back to Contents","Data 1: Refinery Net Input" "Sourcekey","MTTRO_NUS_1","MCRRO_NUS_1","MNGRO_NUS_1","MPPRO_NUS_1","MLPRO_NUS_1","MBNRO_NUS_1","MBIRO_NUS_1","MOLRO_NUS_1","MOHRO_NUS_1","M_EPOOOH_YIY_NUS_MBBL","M_EPOOXXFE_YIY_NUS_MBBL","MMTRO_NUS_1","MOORO_NUS_1","M_EPOOR_YIY_NUS_MBBL","MFERO_NUS_1","M_EPOORD_YIY_NUS_MBBL","M_EPOORO_YIY_NUS_MBBL","M_EPOOOXH_YIY_NUS_MBBL","MUORO_NUS_1","MNLRO_NUS_1","MKORO_NUS_1","MH1RO_NUS_1","MRURO_NUS_1","MBCRO_NUS_1","MO1RO_NUS_1","M_EPOBGRR_YIY_NUS_MBBL","MO3RO_NUS_1","MO4RO_NUS_1","MO5RO_NUS_1","MO6RO_NUS_1","MO7RO_NUS_1","MO9RO_NUS_1","MBARO_NUS_1"

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


461

,"U.S. Refinery Net Input"  

U.S. Energy Information Administration (EIA) Indexed Site

2,"Annual",2012,"6/30/2005" 2,"Annual",2012,"6/30/2005" ,"Data 2","Alaskan Crude Oil Receipts",1,"Annual",2012,"6/30/1986" ,"Release Date:","9/27/2013" ,"Next Release Date:","9/26/2014" ,"Excel File Name:","pet_pnp_inpt2_dc_nus_mbbl_a.xls" ,"Available from Web Page:","http://www.eia.gov/dnav/pet/pet_pnp_inpt2_dc_nus_mbbl_a.htm" ,"Source:","Energy Information Administration" ,"For Help, Contact:","infoctr@eia.gov" ,,"(202) 586-8800",,,"11/25/2013 11:21:04 AM" "Back to Contents","Data 1: Refinery Net Input" "Sourcekey","MTTRO_NUS_1","MCRRO_NUS_1","MNGRO_NUS_1","MPPRO_NUS_1","MLPRO_NUS_1","MBNRO_NUS_1","MBIRO_NUS_1","MOLRO_NUS_1","MOHRO_NUS_1","M_EPOOOH_YIY_NUS_MBBL","M_EPOOXXFE_YIY_NUS_MBBL","MMTRO_NUS_1","MOORO_NUS_1","M_EPOOR_YIY_NUS_MBBL","MFERO_NUS_1","M_EPOORD_YIY_NUS_MBBL","M_EPOOOXH_YIY_NUS_MBBL","MUORO_NUS_1","MNLRO_NUS_1","MKORO_NUS_1","MH1RO_NUS_1","MRURO_NUS_1","MBCRO_NUS_1","MO1RO_NUS_1","M_EPOBGRR_YIY_NUS_MBBL","MO3RO_NUS_1","MO4RO_NUS_1","MO5RO_NUS_1","MO6RO_NUS_1","MO7RO_NUS_1","MO9RO_NUS_1","MBARO_NUS_1"

462

Petroleum Refinery Catalytic Reforming -- Cutting High Energy Costs  

E-Print Network (OSTI)

Hydrocarbon reforming involves a variety of chemical reactions at high temperatures and pressures in the presence of suitable catalysts. The conversion of naptha to high octane aromatics requires high energy to initiate and sustain the reaction at temperatures of 850-950oF. Hydrogen - rich off - gases are fired in combinations of process furnaces. Heat is transferred to hydrocarbon fluids by radiation, principally. Feed or return stream temperatures determine the need for convection sections. It is essential that the operation and maintenance of these furnaces be optimized to minimize production costs. This paper describes the performance testing and evaluation of a set of ten refinery furnaces used to thermally drive several reforming reactors and to regenerate catalysts. Firing rates provide an input of 216.2 x 106 Btu/hr. to the furnaces, at $1.90 per 106 Btu. The units are fitted with multiple natural draft burners. There is insufficient turbulence and swirl in the burners. Operators manually set up the burners with excessive airflows for normal, full-load firing. These furnaces represent production limits. Products of combustion exhaust at high thermal levels - the range is from 985-1700oF. The mixed gases flow through a "waste heat" boiler, or they bypass the boiler and enter a single stack. Steam generation at 150 psig averages 38,200 lb/hr. Heat is wasted via the bypass at a rate of 41.1x106 Btu /hr. at 1240oF. When airflows are reduced (to 15% excess air) the loss will be 18.7x106 Btu/hr. at 1180oF. Installation of a second, parallel waste heat boiler will result in a saving of l3.4x106 Btu/hr. Energy savings at this furnace complex will be equivalent to $628,700 per year. Investment costs were estimated to be less than $250,000 for the proposed heat trap addition.

Viar, W. L.

1979-01-01T23:59:59.000Z

463

NSLS Utilities  

NLE Websites -- All DOE Office Websites (Extended Search)

Utilities Utilities The Utilities Group, led by project engineer Ron Beauman, is responsible for providing Utilities Engineering and Technical services to NSLS, Users, and SDL including cooling water at controlled flow rates, pressures, and temperatures, compressed air and other gases. In addition, they provide HVAC engineering, technical, and electrical services as needed. Utilities systems include cooling and process water, gas, and compressed air systems. These systems are essential to NSLS operations. Working behind the scenes, the Utilities group continuously performs preventative maintenance to ensure that the NSLS has minimal downtime. This is quite a feat, considering that the Utilities group has to maintain seven very large and independent systems that extent throughout NSLS. Part of the group's

464

Product Purchasing & Procurement template | ENERGY STAR Buildings & Plants  

NLE Websites -- All DOE Office Websites (Extended Search)

Product Purchasing & Procurement template Product Purchasing & Procurement template Secondary menu About us Press room Contact Us Portfolio Manager Login Facility owners and managers Existing buildings Commercial new construction Industrial energy management Small business Service providers Service and product providers Verify applications for ENERGY STAR certification Design commercial buildings Energy efficiency program administrators Commercial and industrial program sponsors Associations State and local governments Federal agencies Tools and resources Training In This Section Campaigns Commercial building design Communications resources Energy management guidance Financial resources Portfolio Manager Products and purchasing Recognition Research and reports Service and product provider (SPP) resources Success stories

465

Technical, Engineering, and Programmatic Support (TEPS) Blanket Purchase  

National Nuclear Security Administration (NNSA)

Technical, Engineering, and Programmatic Support (TEPS) Blanket Purchase Technical, Engineering, and Programmatic Support (TEPS) Blanket Purchase Agreements (BPAs) | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Continuing Management Reform Countering Nuclear Terrorism About Us Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Media Room Congressional Testimony Fact Sheets Newsletters Press Releases Speeches Events Social Media Video Gallery Photo Gallery NNSA Archive Federal Employment Apply for Our Jobs Our Jobs Working at NNSA Blog Technical, Engineering, and Programmatic Support (TEPS) Blanket Purchase Agreements (BPAs) Home > About Us > Our Operations > Acquisition and Project Management >

466

Technical, Engineering, and Programmatic Support (TEPS) Blanket Purchase  

NLE Websites -- All DOE Office Websites (Extended Search)

Technical, Engineering, and Programmatic Support (TEPS) Blanket Purchase Technical, Engineering, and Programmatic Support (TEPS) Blanket Purchase Agreements (BPAs) | National Nuclear Security Administration Our Mission Managing the Stockpile Preventing Proliferation Powering the Nuclear Navy Emergency Response Recapitalizing Our Infrastructure Continuing Management Reform Countering Nuclear Terrorism About Us Our Programs Our History Who We Are Our Leadership Our Locations Budget Our Operations Media Room Congressional Testimony Fact Sheets Newsletters Press Releases Speeches Events Social Media Video Gallery Photo Gallery NNSA Archive Federal Employment Apply for Our Jobs Our Jobs Working at NNSA Blog Technical, Engineering, and Programmatic Support (TEPS) Blanket Purchase Agreements (BPAs) Home > About Us > Our Operations > Acquisition and Project Management >

467

,"Sulfur Content, Weighted Average Refinery Crude Oil Input Qualities"  

U.S. Energy Information Administration (EIA) Indexed Site

Sulfur Content, Weighted Average Refinery Crude Oil Input Qualities" Sulfur Content, Weighted Average Refinery Crude Oil Input Qualities" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description","# Of Series","Frequency","Latest Data for" ,"Data 1","Sulfur Content, Weighted Average Refinery Crude Oil Input Qualities",16,"Monthly","9/2013","1/15/1985" ,"Release Date:","11/27/2013" ,"Next Release Date:","Last Week of December 2013" ,"Excel File Name:","pet_pnp_crq_a_epc0_ycs_pct_m.xls" ,"Available from Web Page:","http://www.eia.gov/dnav/pet/pet_pnp_crq_a_epc0_ycs_pct_m.htm" ,"Source:","Energy Information Administration"

468

Mazheikiai refinery modernization study. Final report. Volume 1. Export trade information  

SciTech Connect

The study, conducted by Foster Wheeler Corporation, was funded by the U.S. Trade and Development Agency on behalf of Lithuania's Ministry of Energy. The Mazheikiai Oil Refinery is the only one in the Baltic Region and serves the needs of Lithuania, Latvia, Estonia, and Kaliningrad. Before Lithuania's independence in 1990, the refinery was assured of crude supplies from Russia. However, since then the need has arisen to secure alternate sources of crude oil and the ability to process them. The purpose of the report is to provide recommendations to the Ministry of Energy for process improvements, environmental control measures, physical rehabilitation and energy conservation plans for the Mazheikiai Oil Refinery. This is Volume 1 of the study.

Not Available

1994-01-01T23:59:59.000Z

469

Mazheikiai refinery modernization study. Final report. Volume 3. Export trade information  

Science Conference Proceedings (OSTI)

The study, conducted by Foster Wheeler Corporation, was funded by the U.S. Trade and Development Agency on behalf of Lithuania's Ministry of Energy. The Mazheikiai Oil Refinery is the only one in the Baltic Region and serves the needs of Lithuania, Latvia, Estonia, and Kaliningrad. Before Lithuania's independence in 1990, the refinery was assured of crude supplies from Russia. However, since then the need has arisen to secure alternate sources of crude oil and the ability to process them. The purpose of the report is to provide recommendations to the Ministry of Energy for process improvements, environmental control measures, physical rehabilitation and energy conservation plans for the Mazheikiai Oil Refinery. This is Volume 3 of the study.

Not Available

1994-01-01T23:59:59.000Z

470

Mazheikiai refinery modernization study. Final report. Volume 2. Export trade information  

Science Conference Proceedings (OSTI)

The study, conducted by Foster Wheeler Corporation, was funded by the U.S. Trade and Development Agency on behalf of Lithuania's Ministry of Energy. The Mazheikiai Oil Refinery is the only one in the Baltic Region and serves the needs of Lithuania, Latvia, Estonia, and Kaliningrad. Before Lithuania's independence in 1990, the refinery was assured of crude supplies from Russia. However, since then the need has arisen to secure alternate sources of crude oil and the ability to process them. The purpose of the report is to provide recommendations to the Ministry of Energy for process improvements, environmental control measures, physical rehabilitation and energy conservation plans for the Mazheikiai Oil Refinery. This is Volume 2 of the study.

Not Available

1994-01-01T23:59:59.000Z

471

Potentials for fuel cells in refineries and chlor-alkali plants  

DOE Green Energy (OSTI)

The market potentials for fuel cell cogeneration systems in petroleum refineries and chlor-alkali plants were evaluated. the most promising application appears to be in chlor-alkali plants where the production process is electricity intensive. Future anticipated changes in the production process are favorable to the use of fuel cells. The energy use in refineries is steam intensive with the required steam pressures ranging from approximately 15 to 650 psig. The near-term use of fuel cell cogeneration in refineries is not as attractive as in chlor-alkali plants. The phosphoric acid fuel cell is the most developed and the most competitive, but its use is limited by its being able to produce only low-pressure steam. Over the longer term, the molten carbonate and the solid oxide fuel cell both of which operate at significantly higher temperatures, are technically very attractive. However, they do not appear to be cost competitive with conventional systems.

Altseimer, J.H.; Roach, F.

1986-01-01T23:59:59.000Z

472

Increasing Distillate Production at U.S. Refineries Â… Past Changes and Future Potential  

Gasoline and Diesel Fuel Update (EIA)

Increasing Distillate Production at U.S. Refineries - Past Changes and Future Increasing Distillate Production at U.S. Refineries - Past Changes and Future Potential U.S. Energy Information Administration Office of Petroleum, Gas, and Biofuels Analysis Department of Energy Office of Policy and International Affairs October 2010 Summary World consumption growth for middle distillate fuels (diesel fuel, heating oil, kerosene, and jet fuel) has exceeded the consumption growth for gasoline for some time, and the United States is no exception. Although the decrease in the ratio of total gasoline consumption to consumption for middle distillate fuels has been small in the United States, recent legislation requiring increased use of renewable fuels has resulted in forecasts that project a decline in consumption for petroleum-based gasoline from refineries, which would accelerate the decline in the

473

Short-Term Schedulability Analysis of Crude Oil Operations in Refinery With Oil Residency Time Constraint Using Petri Nets  

Science Conference Proceedings (OSTI)

A short-term schedule for oil refinery should arrange all the activities in every detail for the whole scheduling horizon, leading to a complex problem. There lacks efficient techniques and software tools for its solution applicable to industrial oil ... Keywords: Automated manufacturing system, Petri net (PN), hybrid Petri net, oil refinery, scheduling, short-term scheduling

NaiQi Wu; Feng Chu; Chengbin Chu; MengChu Zhou

2008-11-01T23:59:59.000Z

474

Modeling and Conflict Detection of Crude Oil Operations for Refinery Process Based on Controlled Colored Timed Petri Net  

Science Conference Proceedings (OSTI)

Recently, there has been a great interest in the modeling and analysis of process industry, and various models are proposed for different uses. It is meaningful to have a model to serve as an analytical aid tool in short-term scheduling for oil refinery ... Keywords: Hybrid systems, petri net, refinery process, system modeling

Naiqi Wu; Liping Bai; Chengbin Chu

2007-07-01T23:59:59.000Z

475

CTR/ANL, July 2010 1 Updated Estimation of Energy Efficiencies of U.S. Petroleum Refineries  

E-Print Network (OSTI)

for emissions associated with hydrogen production. Hydrogen is generated in a refinery's catalytic reformer-process distillate material into commercial diesel and jet fuel. From this perspective catalytic reforming transfers refinery operations, most notably catalytic reforming. References Bredeson, L., Quiceno-Gonzalez, R., Riera

Argonne National Laboratory

476

Request for Information: Federal Government Power Purchase Agreements (PPA) Issues  

NLE Websites -- All DOE Office Websites (Extended Search)

Request for Information Request for Information Federal Government Power Purchase Agreements (PPA) Issues BACKGROUND: In order to respond to increasing demand for long term renewable energy, stemming from renewable goals established in the Energy Policy Act of 2005, Executive Order 13423, and the Energy Independence and Security Act of 2007, federal agencies are attempting to facilitate project development and the purchase of electricity from renewable sources on federal facilities. One means of execution is through the use of long term Power Purchase Agreements (PPAs), whereby a third party funds, develops, operates, maintains and owns a renewable energy project, and the Government commits to purchase the renewable power from the project owner. This method reduces the overall risk to the Government, since it will avoid having to build, own and

477

Request for Information: Federal Government Power Purchase Agreements (PPA) Issues  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Request for Information Request for Information Federal Government Power Purchase Agreements (PPA) Issues BACKGROUND: In order to respond to increasing demand for long term renewable energy, stemming from renewable goals established in the Energy Policy Act of 2005, Executive Order 13423, and the Energy Independence and Security Act of 2007, federal agencies are attempting to facilitate project development and the purchase of electricity from renewable sources on federal facilities. One means of execution is through the use of long term Power Purchase Agreements (PPAs), whereby a third party funds, develops, operates, maintains and owns a renewable energy project, and the Government commits to purchase the renewable power from the project owner. This method reduces the overall risk to the Government, since it will avoid having to build, own and

478

Energy Department Issues Tribal Renewable Energy Purchase Guidance and  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Energy Department Issues Tribal Renewable Energy Purchase Guidance Energy Department Issues Tribal Renewable Energy Purchase Guidance and Project Development Resources Energy Department Issues Tribal Renewable Energy Purchase Guidance and Project Development Resources December 5, 2012 - 4:40pm Addthis News Media Contact (202) 586-4940 WASHINGTON - At the White House Tribal Nations Conference today, the Energy Department announced two new initiatives aimed at driving increased energy production and sustainable economic development in Indian Country. As part of the Energy Department's efforts to support Tribal renewable energy production, Energy Secretary Steven Chu issued a policy statement and guidance that gives preference to Indian tribes when its facilities contract to purchase renewable energy products or by products, based on

479

City of Ann Arbor - Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Ann Arbor - Green Power Purchasing Ann Arbor - Green Power Purchasing City of Ann Arbor - Green Power Purchasing < Back Eligibility Local Government Savings Category Bioenergy Solar Buying & Making Electricity Home Weatherization Water Program Info State Michigan Program Type Green Power Purchasing Provider City of Ann Arbor In May 2006, the Ann Arbor City Council adopted a resolution that established a goal of 30% renewable energy for all municipal operations by 2010, with an associated 20% reduction in greenhouse gases. The resolution also established a goal of 20% renewable energy for the entire Ann Arbor community by 2015. In July 2009, the EPA [http://www.a2gov.org/news/Documents/2009_News_Releases/EPA-On-site_Green... announced] that the city of Ann Arbor was among the top-20 users of on-site

480

Pallets of PV: Communities Purchase Solar and Drive Down Costs...  

Open Energy Info (EERE)

Pallets of PV: Communities Purchase Solar and Drive Down Costs Together Home > Groups > OpenEI Community Central Graham7781's picture Submitted by Graham7781(1982) Super...

Note: This page contains sample records for the topic "utility purchases refinery" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


481

CNR PURCHASING ASSIGNMENTS as of September 27, 2013  

E-Print Network (OSTI)

CNR PURCHASING ASSIGNMENTS as of September 27, 2013 Jessie Jessie Jessie Robin Robin Darshan.talley@ leaf@ leaf@ leaf@ roberson@ 664-4058 664-9469 664-9469 664-9469 664-9466 Beissinger Allen

Wildermuth, Mary C

482

City of Grand Rapids - Green Power Purchasing Policy | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

three-year renewable with http:www.consumersenergy.comcontent.aspx?ID1458 Consumers Energy to purchase Green-e Certified blocks of renewable energy valued at a reduced rate....

483

City of Evanston - Green Power Purchase (Illinois) | Open Energy...  

Open Energy Info (EERE)

(kWh) of electricity. The RECs purchased are derived from electricity generated by wind turbines. The city has issued a Climate Change Action Plan to chart a path towards...

484

Conway - Green Power Purchasing (South Carolina) | Open Energy...  

Open Energy Info (EERE)

blocks for a premium of 3.00. The price for businesses is based on overall power consumption. "Green Power Partners" are commercial customers who have agreed to purchase a...

485

Purchased Energy, Energy Intensity, and Policy Impacts in the...  

NLE Websites -- All DOE Office Websites (Extended Search)

Purchased Energy, Energy Intensity, and Policy Impacts in the U.S. Manufacturing Sector: Tentative Findings Speaker(s): Marvin J. Horowitz Date: July 8, 2011 - 12:00pm Location:...

486

PROGRAM OPPORTUNITY NOTICE Solicitation to Address High Purchase Costs  

E-Print Network (OSTI)

PROGRAM OPPORTUNITY NOTICE Solicitation to Address High Purchase Costs and Disposal Impacts of PEV Battery Packs PON-12-501 http://www.energy.ca.gov/contracts/index.html State of California California.......................................................................................... 19 COST OF DEVELOPING APPLICATION

487

Table 21. Domestic Crude Oil First Purchase Prices  

Gasoline and Diesel Fuel Update (EIA)

18.60 19.11 18.73 18.63 17.97 18.75 18.10 See footnotes at end of table. 21. Domestic Crude Oil First Purchase Prices Energy Information Administration Petroleum Marketing Annual...

488

City of Dallas - Green Energy Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

City of Dallas finalized purchase contracts for more than 333 million kilowatt-hours (kWh) of green electricity for city facilities during 2008. The city has elected to continue...

489

City of Chicago - Green Power Purchasing | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

end of 2005. The city reached this goal in 2008, the city with a purchase of 215 million kWh of wind and biomass energy from MidAmerican Energy. The http:www.chicagoclimateactio...

490

South Carolina Municipalities - Green Power Purchasing | Department of  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

South Carolina Municipalities - Green Power Purchasing South Carolina Municipalities - Green Power Purchasing South Carolina Municipalities - Green Power Purchasing < Back Eligibility Local Government Savings Category Bioenergy Solar Buying & Making Electricity Wind Program Info State South Carolina Program Type Green Power Purchasing Provider Santee Cooper Santee Cooper's Green Power Program was launched in September of 2001. All of the state's 20 electric cooperatives and the City of Georgetown participate in the Green Power Program, which is Green-e accredited. The renewable resources sold under the Green Power Program are comprised of 99% landfill gas (methane) and less than 1% solar energy. Santee Cooper is currently using landfill gas (methane) to produce electricity at six facilities in South Carolina: Horry Solid Waste

491

Table 7.9 Expenditures for Purchased Energy Sources, 2002  

U.S. Energy Information Administration (EIA) Indexed Site

9 Expenditures for Purchased Energy Sources, 2002;" 9 Expenditures for Purchased Energy Sources, 2002;" " Level: National and Regional Data;" " Row: NAICS Codes; Column: Energy Sources;" " Unit: Million U.S. Dollars." " "," "," ",," "," "," "," "," "," "," "," ",," " " "," ",,,,,,,,,,"RSE" "NAICS"," "," ",,"Residual","Distillate","Natural ","LPG and",,"Coke"," ","Row" "Code(a)","Subsector and Industry","Total","Electricity","Fuel Oil","Fuel Oil(b)","Gas(c)","NGL(d)","Coal","and Breeze","Other(e)","Factors"

492

,"U.S. Refinery Net Production"  

U.S. Energy Information Administration (EIA) Indexed Site

Monthly","9/2013","1/15/1993" Monthly","9/2013","1/15/1993" ,"Release Date:","11/27/2013" ,"Next Release Date:","Last Week of December 2013" ,"Excel File Name:","pet_pnp_refp2_dc_nus_mbbl_m.xls" ,"Available from Web Page:","http://www.eia.gov/dnav/pet/pet_pnp_refp2_dc_nus_mbbl_m.htm" ,"Source:","Energy Information Administration" ,"For Help, Contact:","infoctr@eia.gov" ,,"(202) 586-8800",,,"11/25/2013 11:28:06 AM" "Back to Contents","Data 1: U.S. Refinery Net Production" "Sourcekey","MTTRX_NUS_1","MLPRX_NUS_1","METRX_NUS_1","MENRX_NUS_1","MEYRX_NUS_1","MPRRX_NUS_1","MPARX_NUS_1","MPLRX_NUS_1","MBNRX_NUS_1","MBURX_NUS_1","MBYRX_NUS_1","MBIRX_NUS_1","MIIRX_NUS_1","MIYRX_NUS_1","MGFRX_NUS_1","MGRRX_NUS_1","MG1RX_NUS_1","M_EPM0RO_YPY_NUS_MBBL","MG4RX_NUS_1","MG5RX_NUS_1","M_EPM0CAL55_YPY_NUS_MBBL","M_EPM0CAG55_YPY_NUS_MBBL","MG6RX_NUS_1","MGARX_NUS_1","MKJRX_NUS_1","M_EPJKC_YPY_NUS_MBBL","M_EPJKM_YPY_NUS_MBBL","MKERX_NUS_1","MDIRX_NUS_1","MD0RX_NUS_1","MD1RX_NUS_1","MDGRX_NUS_1","MRERX_NUS_1","MRXRX_NUS_1","MRMRX_NUS_1","MRGRX_NUS_1","MPCRX_NUS_1","MPNRX_NUS_1","MPORX_NUS_1","MNSRX_NUS_1","MLURX_NUS_1","M_EPPLN_YPY_NUS_MBBL","M_EPPLP_YPY_NUS_MBBL","MWXRX_NUS_1","MCKRX_NUS_1","MCMRX_NUS_1","MCORX_NUS_1","MAPRX_NUS_1","MSGRX_NUS_1","MMSRX_NUS_1","MMFRX_NUS_1","MMNRX_NUS_1","MPGRX_NUS_1"

493

,"U.S. Refinery Net Production"  

U.S. Energy Information Administration (EIA) Indexed Site

Annual",2012,"6/30/1993" Annual",2012,"6/30/1993" ,"Release Date:","9/27/2013" ,"Next Release Date:","9/26/2014" ,"Excel File Name:","pet_pnp_refp2_dc_nus_mbbl_a.xls" ,"Available from Web Page:","http://www.eia.gov/dnav/pet/pet_pnp_refp2_dc_nus_mbbl_a.htm" ,"Source:","Energy Information Administration" ,"For Help, Contact:","infoctr@eia.gov" ,,"(202) 586-8800",,,"11/25/2013 11:28:05 AM" "Back to Contents","Data 1: U.S. Refinery Net Production" "Sourcekey","MTTRX_NUS_1","MLPRX_NUS_1","METRX_NUS_1","MENRX_NUS_1","MEYRX_NUS_1","MPRRX_NUS_1","MPARX_NUS_1","MPLRX_NUS_1","MBNRX_NUS_1","MBURX_NUS_1","MBYRX_NUS_1","MBIRX_NUS_1","MIIRX_NUS_1","MIYRX_NUS_1","MGFRX_NUS_1","MGRRX_NUS_1","MG1RX_NUS_1","M_EPM0RO_YPY_NUS_MBBL","MG4RX_NUS_1","MG5RX_NUS_1","M_EPM0CAL55_YPY_NUS_MBBL","M_EPM0CAG55_YPY_NUS_MBBL","MG6RX_NUS_1","MGARX_NUS_1","MKJRX_NUS_1","M_EPJKC_YPY_NUS_MBBL","M_EPJKM_YPY_NUS_MBBL","MKERX_NUS_1","MDIRX_NUS_1","MD0RX_NUS_1","MD1RX_NUS_1","MDGRX_NUS_1","MRERX_NUS_1","MRXRX_NUS_1","MRMRX_NUS_1","MRGRX_NUS_1","MPCRX_NUS_1","MPNRX_NUS_1","MPORX_NUS_1","MNSRX_NUS_1","MLURX_NUS_1","M_EPPLN_YPY_NUS_MBBL","M_EPPLP_YPY_NUS_MBBL","MWXRX_NUS_1","MCKRX_NUS_1","MCMRX_NUS_1","MCORX_NUS_1","MAPRX_NUS_1","MSGRX_NUS_1","MMSRX_NUS_1","MMFRX_NUS_1","MMNRX_NUS_1","MPGRX_NUS_1"

494

Table 23. Domestic Crude Oil First Purchase Prices by API Gravity  

Annual Energy Outlook 2012 (EIA)

"Domestic Crude Oil First Purchase Report." 23. Domestic Crude Oil First Purchase Prices by API Gravity Energy Information Administration Petroleum Marketing Annual 1997...

495

Table 23. Domestic Crude Oil First Purchase Prices by API Gravity  

Gasoline and Diesel Fuel Update (EIA)

EIA-182, "Domestic Crude Oil First Purchase Report." 23. Domestic Crude Oil First Purchase Prices by API Gravity Energy Information Administration Petroleum Marketing Annual 1996...

496

DOE to Issue Second Solicitation for Purchase of Crude Oil for...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Issue Second Solicitation for Purchase of Crude Oil for the Strategic Petroleum Reserve DOE to Issue Second Solicitation for Purchase of Crude Oil for the Strategic Petroleum...

497

Lake Worth Utilities - Residential Solar Water Heating Rebate Program |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Lake Worth Utilities - Residential Solar Water Heating Rebate Lake Worth Utilities - Residential Solar Water Heating Rebate Program Lake Worth Utilities - Residential Solar Water Heating Rebate Program < Back Eligibility Residential Savings Category Heating & Cooling Solar Water Heating Maximum Rebate $450 Rebates must not exceed purchase price Program Info State Florida Program Type Utility Rebate Program Rebate Amount $450 per system Provider City of Lake Worth Utilities The City of Lake Worth Utilities (CLWU), in conjunction with Florida Municipal Power Agency, offers rebates to customers who purchase and install a solar water heating system for residential use. A rebate of $450 per system is available to eligible applicants. Eligible equipment must be located on customer premises within the CLWU service territory, and must

498

Mandatory Utility Green Power Option | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Mandatory Utility Green Power Option Mandatory Utility Green Power Option Mandatory Utility Green Power Option < Back Eligibility Utility Savings Category Bioenergy Alternative Fuel Vehicles Hydrogen & Fuel Cells Buying & Making Electricity Water Solar Wind Program Info State New Mexico Program Type Mandatory Utility Green Power Option Provider New Mexico Public Regulation Commission In addition to meeting the requirements of the state [http://www.dsireusa.org/library/includes/incentive2.cfm?Incentive_Code=N... renewables portfolio standard], New Mexico investor-owned utilities (IOUs) are required to offer a voluntary program for purchasing renewable energy to customers. The voluntary renewable tariff may also allow consumers to purchase renewable energy within certain energy blocks and by source of

499

Allocation of energy use in petroleum refineries to petroleum products : implications for life-cycle energy use and emission inventory of petroleum transportation fuels.  

Science Conference Proceedings (OSTI)

Studies to evaluate the energy and emission impacts of vehicle/fuel systems have to address allocation of the energy use and emissions associated with petroleum refineries to various petroleum products because refineries produce multiple products. The allocation is needed in evaluating energy and emission effects of individual transportation fuels. Allocation methods used so far for petroleum-based fuels (e.g., gasoline, diesel, and liquefied petroleum gas [LPG]) are based primarily on mass, energy content, or market value shares of individual fuels from a given refinery. The aggregate approach at the refinery level is unable to account for the energy use and emission differences associated with producing individual fuels at the next sub-level: individual refining processes within a refinery. The approach ignores the fact that different refinery products go through different processes within a refinery. Allocation at the subprocess level (i.e., the refining process level) instead of at the aggregate process level (i.e., the refinery level) is advocated by the International Standard Organization. In this study, we seek a means of allocating total refinery energy use among various refinery products at the level of individual refinery processes. We present a petroleum refinery-process-based approach to allocating energy use in a petroleum refinery to petroleum refinery products according to mass, energy content, and market value share of final and intermediate petroleum products as they flow through refining processes within a refinery. The results from this study reveal that product-specific energy use based on the refinery process-level allocation differs considerably from that based on the refinery-level allocation. We calculated well-to-pump total energy use and greenhouse gas (GHG) emissions for gasoline, diesel, LPG, and naphtha with the refinery process-based allocation approach. For gasoline, the efficiency estimated from the refinery-level allocation underestimates gasoline energy use, relative to the process-level based gasoline efficiency. For diesel fuel, the well-to-pump energy use for the process-level allocations with the mass- and energy-content-based weighting factors is smaller than that predicted with the refinery-level allocations. However, the process-level allocation with the market-value-based weighting factors has results very close to those obtained by using the refinery-level allocations. For LPG, the refinery-level allocation significantly overestimates LPG energy use. For naphtha, the refinery-level allocation overestimates naphtha energy use. The GHG emission patterns for each of the fuels are similar to those of energy use.We presented a refining-process-level-based method that can be used to allocate energy use of individual refining processes to refinery products. The process-level-based method captures process-dependent characteristics of fuel production within a petroleum refinery. The method starts with the mass and energy flow chart of a refinery, tracks energy use by individual refining processes, and distributes energy use of a given refining process to products from the process. In allocating energy use to refinery products, the allocation method could rely on product mass, product energy contents, or product market values as weighting factors. While the mass- and energy-content-based allocation methods provide an engineering perspective of energy allocation within a refinery, the market-value-ased allocation method provides an economic perspective. The results from this study show that energy allocations at the aggregate refinery level and at the refining process level could make a difference in evaluating the energy use and emissions associated with individual petroleum products. Furthermore, for the refining-process-level allocation method, use of mass -- energy content- or market value share-based weighting factors could lead to different results for diesel fuels, LPG, and naphtha. We suggest that, when possible, energy use allocations should be made at the lowest subprocess level

Wang, M.; Lee, H.; Molburg, J.

2004-01-01T23:59:59.000Z

500

Mt Peak Utility | Open Energy Information  

Open Energy Info (EERE)

Peak Utility Peak Utility Jump to: navigation, search Name Mt Peak Utility Facility Mt Peak Utility Sector Wind energy Facility Type Small Scale Wind Facility Status In Service Owner Mnt Peak Utility Energy Purchaser Mnt Peak Utility Location Midlothian TX Coordinates 32.42144978°, -97.02427357° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":32.42144978,"lon":-97.02427357,"alt":0,"address":"","icon":"","group":"","inlineLabel":"","visitedicon":""}]}