Powered by Deep Web Technologies
Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


1

GSA-Utility Interconnection Agreements  

Broader source: Energy.gov [DOE]

Presentationógiven at at the Fall 2012 Federal Utility Partnership Working Group (FUPWG) meetingócovers the General Service Administration's (GSA's) utility interconnection agreements.

2

GSA- Utility Interconnection Agreements  

Broader source: Energy.gov [DOE]

Presentation given at the Spring 2010 Federal Utility Partnership Working Group (FUPWG) meeting in Providence, Rhode Island.

3

CHP: Connecting the Gap between Markets and Utility Interconnection...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

Markets and Utility Interconnection and Tariff Practices, 2006 The adoption of combined heat and power (CHP) systems by American industries has made substantial strides in the...

4

Interconnection of on-site photovoltaic generation to the electric utility. [Conference paper  

SciTech Connect (OSTI)

Electrical interconnection with the local electric utility of small, privately owned, on-site photovoltaic generating systems will be necessary. Legal guidelines exist through PURPA, administered by FERC, to establish interconnection, but economic viability will be the deciding factor in constructing photovoltaic generating systems. Although nationally recognized technical standards do not yet exist for interconnecting photovoltaic generation with an electric utility, most utilities have considered the need for developing cogeneration standards, and a few have developed such standards independently. Additional costs incurred by utilities in providing service interconnections to customers with cogeneration will be passed along to those customers, either as a direct assessment or as part of the applicable rate schedule. An economic-analysis methodology has been developed to allow comparing various possible photovoltaic-generating-system configurations under different utility rate structures and varying economic climates on a consistent basis.

Eichler, C.H.; Kilar, L.A.; Stiller, P.H.

1980-01-01T23:59:59.000Z

5

Federal Utility Partnership Working Group- Utility Interconnection Panel  

Broader source: Energy.gov [DOE]

Presentationógiven at at the Fall 2012 Federal Utility Partnership Working Group (FUPWG) meetingódiscusses solar/photovoltaic (PV) projects to connect with utility in California and their issues.

6

Utility Wind Integration Group Distributed Wind/Solar Interconnection Workshop  

Broader source: Energy.gov [DOE]

This two-day workshop will answer your questions about interconnecting wind and solar plants and other distributed generation applications to electric distribution systems while providing insight...

7

Interconnection Standards  

Broader source: Energy.gov [DOE]

In November 2005, the Indiana Utility Regulatory Commission (IURC) approved rules governing the interconnection of distributed generation (DG). Indiana's interconnection rules require the state's...

8

Interconnection Panel  

Broader source: Energy.gov [DOE]

Presentationógiven at at the Fall 2012 Federal Utility Partnership Working Group (FUPWG) meetingódiscusses the interconnection panel, including an overview of the generation interconnection process (GIP), and interconnection agreements and their terms.

9

Interconnection Standards  

Broader source: Energy.gov [DOE]

In December 2007, the Connecticut Department of Public Utility Control (DPUC) now called the Public Utilities Regulatory Authority (PURA) approved new interconnection guidelines for distributed...

10

Interconnection Standards  

Broader source: Energy.gov [DOE]

New Jersey's interconnection standards apply statewide to all electric distribution utilities, but not to the small number of municipal utilities and electric cooperatives in the state. The rules,...

11

Interconnection Standards  

Broader source: Energy.gov [DOE]

The Maine Public Utility Commission (PUC) adopted interconnection procedures in January 2010. These rules apply to all transmission and distribution utilities operating in the state and apply to...

12

Interconnection Standards  

Broader source: Energy.gov [DOE]

Different rules govern the interconnection of distributed generation facilities in Iowa, depending on whether or not the interconnection is with a utility whose rates are regulated by the Iowa...

13

Extending Quality Management to Utility Costs  

E-Print Network [OSTI]

By installing permanent instrumentation and linking it to the appropriate software, a Utility Cost Management Information System, can be created which will identify where, when and how energy is used in a facility on a dynamic and real-time basis...

Holmes, W. A.

14

Utility-Interconnected Photovoltaic Systems: Evaluating the Rationale for the Utility-Accessible External Disconnect Switch  

SciTech Connect (OSTI)

The utility-accessible alternating current (AC) external disconnect switch (EDS) for distributed generators, including photovoltaic (PV) systems, is a hardware feature that allows a utility?s employees to manually disconnect a customer-owned generator from the electricity grid. This paper examines the utility-accessible EDS debate in the context of utility-interactive PV systems for residential and small commercial installations. It also evaluates the rationale for EDS requirements.

Coddington, M.; Margolis, R.M.; Aabakken, J.

2008-01-01T23:59:59.000Z

15

Updated Capital Cost Estimates for Utility Scale Electricity  

E-Print Network [OSTI]

Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants April 2013 Information Administration | Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants ii for Utility Scale Electricity Generating Plants ii Contents Introduction

16

Interconnection Standards  

Broader source: Energy.gov [DOE]

In July 2010, the Montana Public Service Commission (PSC) adopted interconnection rules, effective August 13, 2010. These rules apply to all electric utilities under the PSC's jurisdiction,...

17

Interconnection Standards  

Broader source: Energy.gov [DOE]

In September 2007, the Washington Utilities and Transportation Commission (UTC) adopted interconnection standards for distributed generation (DG) systems up to 20 megawatts (MW) in capacity. The...

18

Interconnection Standards  

Broader source: Energy.gov [DOE]

In December 2005, the Colorado Public Utilities Commission (PUC) adopted standards for net metering and interconnection, as required by Amendment 37, a renewable-energy ballot initiative approved...

19

Interconnection Standards  

Broader source: Energy.gov [DOE]

The Pennsylvania Public Utilities Commission was required to adopt interconnection standards and net-metering rules by the Alternative Energy Portfolio Standards Act of 2004.The PUC subsequently...

20

Interconnection Standards  

Broader source: Energy.gov [DOE]

The North Carolina Utilities Commission (NCUC) adopted comprehensive interconnection standards for distributed generation in June 2008. The NCUC standards, which are similar to the Federal Energy...

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


21

Interconnection Standards  

Broader source: Energy.gov [DOE]

Note: Legislation enacted in August 2012 required the Massachusetts Department of Public Utilities (DPU) to develop an enforceable, standard interconnection timeline for distributed generation...

22

Cost of Gas Adjustment for Gas Utilities (Maine)  

Broader source: Energy.gov [DOE]

This rule, applicable to gas utilities, establishes rules for calculation of gas cost adjustments, procedures to be followed in establishing gas cost adjustments and refunds, and describes reports...

23

Utility Name Retail Sales for 2010 (MWh) Projected Annual Cost  

E-Print Network [OSTI]

All POUs Utility Name Retail Sales for 2010 (MWh) Projected Annual Cost 20122013 ($) Projected Annual Cost 20132014 ($) Projected Annual Cost 20142015 ($) Legend LADWP 22,856,346 720,123 720,123 720 Attachment B Response Utility Name Retail Sales for 2010 (MWh) Projected Annual Cost 2012 2013 ($) LADWP 22

24

Interconnection Standards  

Broader source: Energy.gov [DOE]

South Dakotaís interconnection standards for distributed generation, adopted by the state Public Utilities Commission (PUC) in May 2009, apply to customers of investor-owned utilities.* The rules...

25

The interconnection of photovoltaic power systems with the utility grid: An overview for utility engineers  

SciTech Connect (OSTI)

Utility-interactive (UI) photovoltaic power systems mounted on residences and commercial buildings are likely to become a small, but important source of electric generation in the next century. This is a new concept in utility power production--a change from large-scale central generation to small-scale dispersed generation. As such, it requires a re-examination of many existing standards and practices to enable the technology to develop and emerge into the marketplace. Much work has been done over the last 20 years to identify and solve the potential problems associated with dispersed power generation systems. This report gives an overview of these issues and also provides a guide to applicable codes, standards and other related documents. The main conclusion that can be drawn from this work is that there are no major technical barriers to the implementation of dispersed PV generating systems. While more technical research is needed in some specific areas, the remaining barriers are fundamentally price and policy.

Wills, R.H. [Solar Design Associates, Harvard, MA (United States)

1994-06-01T23:59:59.000Z

26

Advanced Interconnect Development  

SciTech Connect (OSTI)

The objectives of this project are to develop cost-effective, optimized materials for intermediate temperature SOFC interconnect and interconnect/electrode interface applications and identify and understand degradation processes in interconnects and at their interfaces with electrodes.

Yang, Z.G.; Maupin, G.; Simner, S.; Singh, P.; Stevenson, J.; Xia, G.

2005-01-27T23:59:59.000Z

27

Rising Electricity Costs: A Challenge For Consumers, Regulators, And Utilities  

Broader source: Energy.gov [DOE]

Presentation covers the rising electricity costs and is given at the Spring 2010 Federal Utility Partnership Working Group (FUPWG) meeting in Providence, Rhode Island.

28

Evolving Utility Cost-Effectiveness Test Criteria  

Broader source: Energy.gov [DOE]

Presents an overview of tests done to evaluate the cost-effectiveness of energy efficiency program benefits.

29

Interconnection Standards  

Broader source: Energy.gov [DOE]

In December 2003, the Nevada Public Utilities Commission (PUC) adopted interconnection standards for customers of NV Energy (formerly Nevada Power and Sierra Pacific Power) with on-site generation...

30

Cost analysis of energy storage systems for electric utility applications  

SciTech Connect (OSTI)

Under the sponsorship of the Department of Energy, Office of Utility Technologies, the Energy Storage System Analysis and Development Department at Sandia National Laboratories (SNL) conducted a cost analysis of energy storage systems for electric utility applications. The scope of the study included the analysis of costs for existing and planned battery, SMES, and flywheel energy storage systems. The analysis also identified the potential for cost reduction of key components.

Akhil, A. [Sandia National Lab., Albuquerque, NM (United States); Swaminathan, S.; Sen, R.K. [R.K. Sen & Associates, Inc., Bethesda, MD (United States)

1997-02-01T23:59:59.000Z

31

Utility Scale Solar PV Cost Steven SimmonsSteven Simmons  

E-Print Network [OSTI]

Nuclear Generating Station. 4 #12;6/19/2013 3 EVEN MORE SUNNY HEADLINES New solar panels glisten6/19/2013 1 Utility Scale Solar PV Cost Steven SimmonsSteven Simmons Northwest Power Cost Forecast 5. Levelized Costs 1 SOLAR POWER SYSTEM HAS BRIGHT FUTURE 1. Modest environmental impacts

32

Process based cost modeling of emerging optoelectronic interconnects : implications for material platform choice  

E-Print Network [OSTI]

Continuously increasing demand for processing power, storage capacity, and I/O capacity in personal computing, data network, and display interface suggests that optical interconnects may soon supplant copper not only for ...

Liu, Shan, S.M. Massachusetts Institute of Technology

2008-01-01T23:59:59.000Z

33

Robust Output Feedback Stabilization of Nonlinear Interconnected Systems with Application to an Industrial Utility Boiler  

E-Print Network [OSTI]

to an Industrial Utility Boiler Adarsha Swarnakar, Horacio Jose Marquez and Tongwen Chen Abstract-- This paper boiler (Utility boiler), where the nonlinear model describes the complicated dynamics of the drum

Marquez, Horacio J.

34

Investigation of anti-islanding schemes for utility interconnection of distributed fuel cell powered generations  

E-Print Network [OSTI]

The rapid emergence of distributed fuel cell powered generations (DFPGs) operating in parallel with utility has brought a number of technical concerns as more DFPGs are connected to utility grid. One of the most challenging problems is known...

Jeraputra, Chuttchaval

2006-04-12T23:59:59.000Z

35

Impact of Utility Costs on the Economics of Energy Cost Reduction & Conservation Technologies  

E-Print Network [OSTI]

IMPACT OF UTILITY COSTS ON THE ECONOMICS OF ENERGY COST REDUCTION & CONSERVATION TECHNOLOGIES Saidas M. Ranade Senior Process Engineer ARCO Chemical Company Channelview,Texas ABSTRACT This paper summarizes some key results obtained from... to ARCO Chemical Company for providing the time and space required to complete thi paper. REFERENCES 1. N. R. Friedman, Co eneration: Impacts on Utility Operations and Marketing. EPRI Conference on Placing Industrial Cogeneration in Perspective...

Ranade, S. M.; Chao, Y. T.

36

Cost and quality of fuels for electric utility plants, 1992  

SciTech Connect (OSTI)

This publication presents an annual summary of statistics at the national, Census division, State, electric utility, and plant levels regarding the quantity, quality, and cost of fossil fuels used to produce electricity. The purpose of this publication is to provide energy decision-makers with accurate and timely information that may be used in forming various perspectives on issues regarding electric power.

Not Available

1993-08-02T23:59:59.000Z

37

Cost and quality of fuels for electric utility plants, 1994  

SciTech Connect (OSTI)

This document presents an annual summary of statistics at the national, Census division, State, electric utility, and plant levels regarding the quantity, quality, and cost of fossil fuels used to produce electricity. Purpose of this publication is to provide energy decision-makers with accurate, timely information that may be used in forming various perspectives on issues regarding electric power.

NONE

1995-07-14T23:59:59.000Z

38

Interconnect Issues in NE  

Broader source: Energy.gov [DOE]

Presentation covers interconnect issues in the Northeast and is given at the Spring 2010 Federal Utility Partnership Working Group (FUPWG) meeting in Providence, Rhode Island.

39

Distributed utility technology cost, performance, and environmental characteristics  

SciTech Connect (OSTI)

Distributed Utility (DU) is an emerging concept in which modular generation and storage technologies sited near customer loads in distribution systems and specifically targeted demand-side management programs are used to supplement conventional central station generation plants to meet customer energy service needs. Research has shown that implementation of the DU concept could provide substantial benefits to utilities. This report summarizes the cost, performance, and environmental and siting characteristics of existing and emerging modular generation and storage technologies that are applicable under the DU concept. It is intended to be a practical reference guide for utility planners and engineers seeking information on DU technology options. This work was funded by the Office of Utility Technologies of the US Department of Energy.

Wan, Y.; Adelman, S.

1995-06-01T23:59:59.000Z

40

Utility Cost Calculation Example? | OpenEI Community  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home5b9fcbce19 NoPublic Utilities Address: 160 East 300 South Place: Salt Lake City, Utah Zip: 84111Jump to:AccessUtility Cost

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


41

Estimating the Actual Cost of Transmission System Congestion  

E-Print Network [OSTI]

of the utility's generation, load and tie-line flows over the study time period. Due to the common lack by most be used by a utility to estimate the actual cost of congestion on its transmission system using limited interconnected grid (i.e., the Eastern Interconnect), costs for the utility's generators, and then hourly values

42

Cost and quality of fuels for electric utility plants 1991  

SciTech Connect (OSTI)

Data for 1991 and 1990 receipts and costs for fossil fuels discussed in the Executive Summary are displayed in Tables ES1 through ES7. These data are for electric generating plants with a total steam-electric and combined-cycle nameplate capacity of 50 or more megawatts. Data presented in the Executive Summary on generation, consumption, and stocks of fossil fuels at electric utilities are based on data collected on the Energy Information Administration, Form EIA-759, ``Monthly Power Plant Report.`` These data cover all electric generating plants. The average delivered cost of coal, petroleum, and gas each decreased in 1991 from 1990 levels. Overall, the average annual cost of fossil fuels delivered to electric utilities in 1991 was $1.60 per million Btu, a decrease of $0.09 per million Btu from 1990. This was the lowest average annual cost since 1978 and was the result of the abundant supply of coal, petroleum, and gas available to electric utilities. US net generation of electricity by all electric utilities in 1991 increased by less than I percent--the smallest increase since the decline that occurred in 1982.3 Coal and gas-fired steam net generation, each, decreased by less than I percent and petroleum-fired steam net generation by nearly 5 percent. Nuclear-powered net generation, however, increased by 6 percent. Fossil fuels accounted for 68 percent of all generation; nuclear, 22 percent; and hydroelectric, 10 percent. Sales of electricity to ultimate consumers in 1991 were 2 percent higher than during 1990.

Not Available

1992-08-04T23:59:59.000Z

43

Cost and quality of fuels for electric utility plants 1991  

SciTech Connect (OSTI)

Data for 1991 and 1990 receipts and costs for fossil fuels discussed in the Executive Summary are displayed in Tables ES1 through ES7. These data are for electric generating plants with a total steam-electric and combined-cycle nameplate capacity of 50 or more megawatts. Data presented in the Executive Summary on generation, consumption, and stocks of fossil fuels at electric utilities are based on data collected on the Energy Information Administration, Form EIA-759, Monthly Power Plant Report.'' These data cover all electric generating plants. The average delivered cost of coal, petroleum, and gas each decreased in 1991 from 1990 levels. Overall, the average annual cost of fossil fuels delivered to electric utilities in 1991 was $1.60 per million Btu, a decrease of $0.09 per million Btu from 1990. This was the lowest average annual cost since 1978 and was the result of the abundant supply of coal, petroleum, and gas available to electric utilities. US net generation of electricity by all electric utilities in 1991 increased by less than I percent--the smallest increase since the decline that occurred in 1982.3 Coal and gas-fired steam net generation, each, decreased by less than I percent and petroleum-fired steam net generation by nearly 5 percent. Nuclear-powered net generation, however, increased by 6 percent. Fossil fuels accounted for 68 percent of all generation; nuclear, 22 percent; and hydroelectric, 10 percent. Sales of electricity to ultimate consumers in 1991 were 2 percent higher than during 1990.

Not Available

1992-08-04T23:59:59.000Z

44

A municipal guide to least cost utility planning  

SciTech Connect (OSTI)

The recent track record of ``traditional`` electricity planning, which entails selection of supply side resources to meet forecasted demand, has not been good. There are numerous examples of utilities incorrectly forecasting demand and over-building generating capacity while others underestimated growth and have had to cut demand and find alternate power sources to avoid outages. A potential solution to this problem is the continuing development of Least Cost Utility Plannning (LCUP). Regulatory commissions, consumer advocates and utilities are increasingly relying an LCUP as the most responsible way to avoid construction of new capacity and alleviate anticipated shortages caused by cancellation of construction projects, load growth, or natural replacement of aging capacity. The purpose of this report is to provide municipalities a starting point for evaluating their servicing utilities or states` least cost plan. This was accomplished by: Identifying key issues in LCUP; reviewing examples of the collaborative and classic approaches to LCUP in Illinois, California, New York State and Michigan; cataloging municipal authorities and strategies which can influence or support LCUP activities. Results of the project indicate that through a basic understanding of LCUP processes and issues, municipalities will be in a better position to influence plans or, if necessary, intervene in regulatory proceedings where plans are adopted. Constraints to municipal involvement in LCUP include statutory limitations, resource constraints, and a lack of knowledge of indirect authorities that support the LCUP process.

Not Available

1992-03-01T23:59:59.000Z

45

Ancillary-service costs for 12 US electric utilities  

SciTech Connect (OSTI)

Ancillary services are those functions performed by electrical generating, transmission, system-control, and distribution-system equipment and people to support the basic services of generating capacity, energy supply, and power delivery. The Federal Energy Regulatory Commission defined ancillary services as ``those services necessary to support the transmission of electric power from seller to purchaser given the obligations of control areas and transmitting utilities within those control areas to maintain reliable operations of the interconnected transmission system.`` FERC divided these services into three categories: ``actions taken to effect the transaction (such as scheduling and dispatching services) , services that are necessary to maintain the integrity of the transmission system [and] services needed to correct for the effects associated with undertaking a transaction.`` In March 1995, FERC published a proposed rule to ensure open and comparable access to transmission networks throughout the country. The rule defined six ancillary services and developed pro forma tariffs for these services: scheduling and dispatch, load following, system protection, energy imbalance, loss compensation, and reactive power/voltage control.

Kirby, B.; Hirst, E.

1996-03-01T23:59:59.000Z

46

Production Cost Modeling of Cogenerators in an Interconnected Electric Supply System  

E-Print Network [OSTI]

The Optimal State Electricity Supply System in Texas (OSEST) research project is part of the continuing Public Utility Commission of Texas (PUCT) effort to identify possible improvements in the production, transmission, and use of electricity...

Ragsdale, K.

47

Three-phase power conversion system for utility-interconnected PV applications. Phase 1 technical progress report, 1 October 1995--17 April 1997  

SciTech Connect (OSTI)

This report describes work performed by Omnion Power Corporation under Phase 1 of a two-phase subcontract. During this phase, Omnion researchers: designed an advanced product specification to guide prototype design and development; analyzed field failure data with Omnion`s hard-switched insulated-Gate Bipolar Transistor technology hardware to better understand where design improvements were needed; presented and reviewed product specifications with key customers/users; drafted a working product specification to serve as a baseline in developing the new power conversion system; developed the core-resonant converter technology in conjunction with Soft Switching Technologies Corp.; designed a 100-kW prototype power conversion system; designed a prototype system package; initiated interaction with vendors to optimize component selection and specifications; initiated the preparation of design documentation; built the prototype core-resonant converter and initiated preliminary testing; and initiated the assembly of a 1-kW prototype power conversion system. This work has demonstrated the potential of the soft-switching resonant DC link (RDCL) inverter and its application to a three-phase utility-interconnected PV power conversion system. The RDCL inverter has demonstrated its advantage over hard-switching pulse-width modulated inverters in terms of efficiency and audible noise. With proper package design and manufacturing process design and implementation, the RDCL power conversion system has the potential to be low-cost and reliable with superior performance.

Porter, D.G.; Meyer, H.; Leang, W. [Omnion Power Engineering Corp., East Troy, WI (United States)

1998-02-01T23:59:59.000Z

48

Cost and quality of fuels for electric utility plants, 1984  

SciTech Connect (OSTI)

Information on the cost and quality of fossil fuel receipts in 1984 to electric utility plants is presented, with some data provided for each year from 1979 through 1984. Data were collected on Forms FERC-423 and EIA-759. Fuels are coal, fuel oil, and natural gas. Data are reported by company and plant, by type of plant, and by State and Census Region, with US totals. This report contains information on fossil fuel receipts to electric utility plants with a combined steam capacity of 50 megawatts or larger. Previous reports contained data on all electric plants with a combined capacity of 25 megawatts or larger. All historical data in this publication have been revised to reflect the new reporting threshold. Peaking unit data are no longer collected. A glossary of terms, technical notes, and references are also provided. 7 figs., 62 tabs.

Not Available

1985-07-01T23:59:59.000Z

49

Can Solar PV Rebates Be Funded with Utility Cost Savings? | Department...  

Broader source: Energy.gov (indexed) [DOE]

Can Solar PV Rebates Be Funded with Utility Cost Savings? Can Solar PV Rebates Be Funded with Utility Cost Savings? This presentation was given by Jan Aceti of Concord Light at the...

50

Energy Management System Lowers U.S. Navy Energy Costs Through PV System Interconnection (Fact Sheet)  

SciTech Connect (OSTI)

To meet the U.S. Navy's energy goals, the National Renewable Energy Laboratory (NREL) and the Naval Facilities Engineering Command (NAVFAC) spent two years collaborating on demonstrations that tested market-ready energy efficiency measures, renewable energy generation, and energy systems integration. One such technology - an energy management system - was identified as a promising method for reducing energy use and costs, and can contribute to increasing energy security.

Not Available

2014-04-01T23:59:59.000Z

51

FACILITIES ENGINEER WEST CHICAGO Execute capital projects for manufacturing facilities and utilities systems: scope development, cost  

E-Print Network [OSTI]

facilities and utilities systems: scope development, cost estimation, system design, equipment sizing ENGINEERING: Lead capital project design, development and execution for facility and utility capital Utilities systems (Vacuum, Hydraulics, Waste Water treatment, etc.) o Buildings and grounds, including

Heller, Barbara

52

Cost-Effectiveness: Implication for Bonneville and Utility Programs Council document 2007-23 August 2007  

E-Print Network [OSTI]

incentives paid by utilities are less than present value of the avoided cost of alternative electricity1 Cost-Effectiveness: Implication for Bonneville and Utility Programs Council document 2007 found to be cost effective if the electric system paid all the costs. Council plan conservation targets

53

Interconnection Standards  

Broader source: Energy.gov [DOE]

New York first adopted uniform interconnection standards in 1999 (see history below). The Standard Interconnection Requirements (SIR) have subsequently been amended several times since, most...

54

Interconnection Agreements for Onsite Generation  

Broader source: Energy.gov [DOE]

Presentation covers Interconnection Agreements for Onsite Generation and is given at the Spring 2011 Federal Utility Partnership Working Group (FUPWG) meeting.

55

Optimizing procurement and handling costs in a utility  

E-Print Network [OSTI]

We propose a novel method to quantify the cost of activities involved in the picking portion of order fulfillment. We adapt the general method of picking cost quantification to the specific situation of TP&G, a publicly ...

Genser, Bradley Philip

2014-01-01T23:59:59.000Z

56

Low Cost High Concentration PV Systems for Utility Power Generation...  

Broader source: Energy.gov (indexed) [DOE]

Electricity On Flat Commercial Rooftops,Fully Automated Systems Technology, Concentrating Solar Panels: Bringing the Highest Power and Lowest Cost to the Rooftop Practical...

57

Can Solar PV Rebates Be Funded with Utility Cost Savings?  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

Costs 10 Years into Future is Hard Determining Actual Demand Reduction due to Solar at MonthlyAnnual Peaks Requires Long Term Data Collection Wholesale Net...

58

Micro-fluidic interconnect  

DOE Patents [OSTI]

An apparatus for simultaneously aligning and interconnecting microfluidic ports is presented. Such interconnections are required to utilize microfluidic devices fabricated in Micro-Electromechanical-Systems (MEMS) technologies, that have multiple fluidic access ports (e.g. 100 micron diameter) within a small footprint, (e.g. 3 mm.times.6 mm). Fanout of the small ports of a microfluidic device to a larger diameter (e.g. 500 microns) facilitates packaging and interconnection of the microfluidic device to printed wiring boards, electronics packages, fluidic manifolds etc.

Okandan, Murat (Albuquerque, NM); Galambos, Paul C. (Albuquerque, NM); Benavides, Gilbert L. (Los Ranchos, NM); Hetherington, Dale L. (Albuquerque, NM)

2006-02-28T23:59:59.000Z

59

Cost-Effectiveness -Implication for Bonneville and Utility Programs The Council's 5th  

E-Print Network [OSTI]

value of the avoided cost of alternative electricity resources avoided by the measure. The remainder1 Cost-Effectiveness - Implication for Bonneville and Utility Programs Background The Council's 5th Plan conservation targets are comprised of measures that were found to be cost effective

60

Evaluation of Production Cost Savings from Consolidation of Balancing Authorities in the US Western Interconnection under High Wind and Solar Penetration  

SciTech Connect (OSTI)

This paper introduces a comprehensive analysis to quantify the potential savings in production cost due to consolidation of 32 US western interconnection Balancing Authorities (BAs). Three simulation scenarios are developed: current Western Electricity Coordinating Council (WECC) BAs structure, full copper-sheet consolidation, and full consolidation with transmission congestion considered. The study uses WECC Transmission Expansion Planning Policy Committee (TEPPC) model that was developed for the year 2020. The model assumes 8% wind and 3% solar energy penetration as percentage of total WECC demand in 2020. Sensitivity analyses are carried out to assess the impact of transmission hurdle rates between WECC BAs on potential benefits. The study shows savings that ranges from $400 Million (2.4% of total one year production cost) to $600 Million (3.2%) per year in thermal units production cost due to consolidation can be achieved. The copper sheet consolidation scenario shows an extra savings of $240 Million (1.4%) per year.

Nguyen, Tony B.; Samaan, Nader A.; Jin, Chunlian

2014-12-24T23:59:59.000Z

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


61

Interconnection Standards  

Broader source: Energy.gov [DOE]

In February 2004, the Wisconsin Public Service Commission adopted interconnection standards for distributed generation (DG) systems up to 15 megawatts (MW) in capacity. All investor-owned...

62

Interconnection Standards  

Broader source: Energy.gov [DOE]

Virginia has two interconnection standards: one for net-metered systems and one for systems that are not net-metered.

63

Interconnection Standards  

Broader source: Energy.gov [DOE]

The Michigan Public Service Commission (PSC) first adopted interconnection standards for distributed generation (DG) in September 2003. The original standards provided for 5 levels of...

64

Interconnection Standards  

Broader source: Energy.gov [DOE]

In April 2008, Kentucky enacted legislation which required the Kentucky Public Service Commission (PSC) to develop interconnection and net metering guidelines for all retail electric suppliers...

65

Interconnection Standards  

Broader source: Energy.gov [DOE]

In July 2006 the District of Columbia Public Service Commission (PSC) initiated a formal inquiry into the development of uniform interconnection procedures for on-site distributed generation...

66

Interconnection Guidelines  

Broader source: Energy.gov [DOE]

'''''Note: In June 2007, the Arizona Corporation Commission (ACC) initiated a rulemaking process to establish statewide interconnection standards for distributed generation (DG). This proceeding...

67

Interconnection Guidelines  

Broader source: Energy.gov [DOE]

The South Carolina Public Service Commission (PSC) adopted simplified interconnection guidelines for small distributed generation (DG) in December 2006. These guidelines address renewable-energy...

68

Interconnection Resources  

Broader source: Energy.gov [DOE]

Interconnection is the technical procedures and legal requirements surrounding energy customers' ability to connect their small-scale renewable energy projects with the electricity grid. The...

69

Survey of state regulatory activities on least cost planning for gas utilities  

SciTech Connect (OSTI)

Integrated resource planning involves the creation of a process in which supply-side and demand-side options are integrated to create a resource mix that reliably satisfies customers' short-term and long-term energy service needs at the lowest cost. Incorporating the concept of meeting customer energy service needs entails a recognition that customers' costs must be considered along with the utility's costs in the economic analysis of energy options. As applied to gas utilities, an integrated resource plan seeks to balance cost and reliability, and should not be interpreted simply as the search for lowest commodity costs. All state commissions were surveyed to assess the current status of gas planning and demand-side management and to identify significant regulatory issues faced by commissions during the next several years. The survey was to determine the extent to which they have undertaken least-cost planning for gas utilities. The survey included the following topics: (1) status of state PUC least-cost planning regulations and practices for gas utilities; (2) type and scope ofnatural gas DSM programs in effect, includeing fuel substitution; (3) economic tests and analysis methods used to evaluate DSM programs; (4) relationship between prudence reviews of gas utility purchasing practices and integrated resource planning; and (5) key regulatory issues facing gas utilities during the next five years. 34 refs., 6 figs., 10 tabs.

Goldman, C.A. (Lawrence Berkeley Lab., CA (United States) National Association of Regulatory Utility Commissioners, Washington, DC (United States)); Hopkins, M.E. (Fleming Group, Washington, DC (United States))

1991-04-01T23:59:59.000Z

70

Using Pinch Technology to Explore Trade-Offs Between Energy Cost, Capital Cost, Process Modifications, and Utility Selection  

E-Print Network [OSTI]

USING PINCH TECHNOLOGY TO EXPLORE TRADE-OFFS BETWEEN ENERGY COST, CAPITAL COST, PROCESS MODIFICATIONS, AND UTILITY SELECTION A.S. McMullan, Consultant and H.D. Spriggs, President Linnhoff March, Inc., Leesburg, Virginia ABSTRACT Process... (3), predict payback targets in retrofit situations (4), and design flexible heat exchanger networks (5). The most recent developments enable the process designer to explore the interactions and trade-offs between design variables, prior...

McMullan, A. S.

71

The effects of utility DSM programs on electricity costs and prices  

SciTech Connect (OSTI)

More and more US utilities are running more and larger demand-side management (DSM) programs. Assessing the cost-effectiveness of these programs raises difficult questions for utilities and their regulators. Should these programs aim to minimize the total cost of providing electric-energy services or should they minimize the price of electricity This study offers quantitative estimates on the tradeoffs between total costs and electricity prices. This study uses a dynamic model to assess the effects of energy-efficiency programs on utility revenues, total resource costs, electricity prices, and electricity consumption for the period 1990 to 2010. These DSM programs are assessed under alternative scenarios. In these cases, fossil-fuel prices, load growth, the amount of excess capacity the utility has in 1990, planned retirements of power plants, the financial treatment of DSM programs, and the costs of energy- efficient programs vary. These analyses are conducted for three utilities: a base'' that is typical of US utilities; a surplus'' utility that has excess capacity, few planned retirements, and slow growth in fossil-fuel prices and incomes; and a deficit'' utility that has little excess capacity, many planned retirements, and rapid growth in fossil-fuel prices and incomes. 28 refs.

Hirst, E.

1991-11-01T23:59:59.000Z

72

The effects of utility DSM programs on electricity costs and prices  

SciTech Connect (OSTI)

More and more US utilities are running more and larger demand-side management (DSM) programs. Assessing the cost-effectiveness of these programs raises difficult questions for utilities and their regulators. Should these programs aim to minimize the total cost of providing electric-energy services or should they minimize the price of electricity? This study offers quantitative estimates on the tradeoffs between total costs and electricity prices. This study uses a dynamic model to assess the effects of energy-efficiency programs on utility revenues, total resource costs, electricity prices, and electricity consumption for the period 1990 to 2010. These DSM programs are assessed under alternative scenarios. In these cases, fossil-fuel prices, load growth, the amount of excess capacity the utility has in 1990, planned retirements of power plants, the financial treatment of DSM programs, and the costs of energy- efficient programs vary. These analyses are conducted for three utilities: a ``base`` that is typical of US utilities; a ``surplus`` utility that has excess capacity, few planned retirements, and slow growth in fossil-fuel prices and incomes; and a ``deficit`` utility that has little excess capacity, many planned retirements, and rapid growth in fossil-fuel prices and incomes. 28 refs.

Hirst, E.

1991-11-01T23:59:59.000Z

73

Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr MayAtmosphericNuclear SecurityTensile Strain Switched Ferromagnetism inS-4500II Field Emission SEM with EDAXUpdated Capital Cost Estimates

74

A New Scheme on Robust Observer Based Control Design for Nonlinear Interconnected Systems with Application to an Industrial Utility Boiler  

E-Print Network [OSTI]

with Application to an Industrial Utility Boiler Adarsha Swarnakar, Horacio Jose Marquez and Tongwen Chen Abstract. The controller design is evaluated on a natural circulation drum boiler, where the nonlinear model describes

Marquez, Horacio J.

75

Utility Service Renovations  

Broader source: Energy.gov [DOE]

Any upgrade to utility service provides an opportunity to revisit a Federal building's electrical loads and costs, but it also may provide an economic way to bundle the upgrade with an onsite renewable electricity project during renovation. Upgrading utility service to the site may involve improving or adding a transformer, upgrading utility meters, or otherwise modifying the interconnection equipment or services with the utility. In some cases, the upgrade may change the tariff structure for the facility and may qualify the property for a different structure with lower overall costs. In all cases, the implementation of renewable energy technologies should be identified during the design phase.

76

Lower cost offshore field development utilizing autonomous vehicles  

SciTech Connect (OSTI)

The offshore oil and gas industry has the requirement to inspect offshore oil and gas pipelines for scour, corrosion and damage as well as inspect and intervene on satellite production facilities. This task is currently performed with Remotely Operated Vehicles (ROV) operated from dynamically positioned (DP) offshore supply or diving support boats. Currently, these tasks are expensive due to the high day rates for DP ships and the slow, umbilical impeded, 1 knot inspection rates of the tethered ROVs, Emerging Autonomous Undersea Vehicle (AUV) technologies offer opportunities to perform these same inspection tasks for 50--75% lower cost, with comparable or improved quality. The new generation LAPV (Linked Autonomous Power Vehicles) will operate from fixed facilities such as TLPs or FPFs and cover an operating field 10 kms in diameter.

Frisbie, F.R.; Vie, K.J.; Welch, D.W.

1996-12-31T23:59:59.000Z

77

Costs and effects of electric-utility DSM programs: 1989--1997  

SciTech Connect (OSTI)

All US electric utilities are required to report to the Energy Information Administration data on their demand-side management (DSM) programs. These data provide a comprehensive view of utility DSM-program costs and effects (energy savings and load reductions) for 1989, 1990, 1991, and 1992 as well as projections for 1993 and 1997.

Hirst, E.

1994-06-01T23:59:59.000Z

78

Reducing power production costs by utilizing petroleum coke. Annual report  

SciTech Connect (OSTI)

A Powder River Basin subbituminous coal from the North Antelope mine and a petroleum shot coke were received from Northern States Power Company (NSP) for testing the effects of parent fuel properties on coal-coke blend grindability and evaluating the utility of petroleum coke blending as a strategy for improving electrostatic precipitator (ESP) particulate collection efficiency. Petroleum cokes are generally harder than coals, as indicated by Hardgrove grindability tests. Therefore, the weaker coal component may concentrate in the finer size fractions during the pulverizing of coal-coke blends. The possibility of a coal-coke size fractionation effect is being investigated because it may adversely affect combustion performance, it may enhance ESP particulate collection efficiency. Petroleum cokes contain much higher concentrations of V relative to coals. Consequently, coke blending can significantly increase the V content of fly ash resulting from coal-coke combustion. Pentavalent vanadium oxide (V{sub 2}O{sub 5}) is a known catalyst for transforming gaseous sulfur dioxide (SO{sub 2}[g]) to gaseous sulfur trioxide (SO{sub 3}[g]). The presence of SO{sub 3}(g) strongly affects fly ash resistivity and, thus, ESP performance.

Galbreath, K.C.

1998-07-01T23:59:59.000Z

79

REDUCING POWER PRODUCTION COSTS BY UTILIZING PETROLEUM COKE  

SciTech Connect (OSTI)

A Powder River Basin subbituminous coal from the North Antelope mine and a petroleum shot coke were received from Northern States Power Company (NSP) for testing the effects of parent fuel properties on coal-coke blend grindability and evaluating the utility of petroleum coke blending as a strategy for improving electrostatic precipitator (ESP) particulate collection efficiency. Petroleum cokes are generally harder than coals, as indicated by Hardgrove grindability tests. Therefore, the weaker coal component may concentrate in the finer size fractions during the pulverizing of coal-coke blends. The possibility of a coal-coke size fractionation effect is being investigated because it may adversely affect combustion performance. Although the blending of petroleum coke with coal may adversely affect combustion performance, it may enhance ESP particulate collection efficiency. Petroleum cokes contain much higher concentrations of V relative to coals. Consequently, coke blending can significantly increase the V content of fly ash resulting from coal-coke combustion. Pentavalent vanadium oxide (V{sub 2}O{sub 5}) is a known catalyst for transforming gaseous sulfur dioxide (SO{sub 2}[g]) to gaseous sulfur trioxide (SO{sub 3}[g]). The presence of SO{sub 3}(g) strongly affects fly ash resistivity and, thus, ESP performance.

NONE

1998-09-01T23:59:59.000Z

80

SAVING MONEY & TIME (EFFICIENCY) UTILITY COST AVOIDANCE: From FY 2001 through FY2012, the UW Seattle campus has avoided  

E-Print Network [OSTI]

SAVING MONEY & TIME (EFFICIENCY) UTILITY COST AVOIDANCE: From FY 2001 through FY2012, the UW Seattle campus has avoided a cumulative $95.1 million in utility costs through its conservation efforts in disposal costs. These savings are calculated by subtracting the average cost per ton to recycle material

Van Volkenburgh, Elizabeth

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


81

Cost-Effectivenessof PhotovoltaicGenerationIn A Transmission-Constrained Load Area of An InterconnectedSystem  

E-Print Network [OSTI]

Cost-Effectivenessof PhotovoltaicGenerationIn A Transmission-Constrained Load Area examines and evaluates the applicability and cost-effectiveness of Photovoltaic(PV) generation the construction of many large power stations with high efficiency, which were located far fi-om customer sites

Gross, George

82

Identifying Cost-Effective Residential Energy Efficiency Opportunities for the Kauai Island Utility Cooperative  

SciTech Connect (OSTI)

This analysis is an update to the 2005 Energy Efficiency Potential Study completed by KEMA for the Kauai Island Utility Cooperative (KIUC) and identifies potential energy efficiency opportunities in the residential sector on Kauai (KEMA 2005). The Total Resource Cost (TRC) test is used to determine which of the energy efficiency measures analyzed in the KEMA report are cost effective for KIUC to include in a residential energy efficiency program. This report finds that there remains potential energy efficiency savings that could be cost-effectively incentivized through a utility residential demand-side management program on Kauai if implemented in such a way that the program costs per measure are consistent with the current residential program costs.

Busche, S.; Hockett, S.

2010-06-01T23:59:59.000Z

83

Interconnection Guidelines  

Broader source: Energy.gov [DOE]

Nebraska enacted legislation in May 2009 [http://nebraskalegislature.gov/FloorDocs/101/PDF/Final/LB436.pdf (LB 436)], establishing general rules for interconnecting and net metering systems that...

84

Interconnection Standards  

Broader source: Energy.gov [DOE]

In March 2008, the Florida Public Service Commission (PSC) adopted interconnection rules for renewable-energy systems up to two megawatts (MW) in capacity. The PSC rules apply only to the state's...

85

Interconnection Guidelines  

Broader source: Energy.gov [DOE]

Kansas adopted the Net Metering and Easy Connection Act in May 2009 (see K.S.A. 66-1263 through 66-1271), establishing interconnection guidelines and net metering for customer-owned generators. Net...

86

Interconnection Standards  

Broader source: Energy.gov [DOE]

Oregon has three separate interconnection standards: one for net-metered systems, one for small generator facilities (non-net metered systems) and one for large generator facilities (non-net...

87

Interconnection Guidelines  

Broader source: Energy.gov [DOE]

Wyoming's net-metering law includes basic interconnection requirements for systems up to 25 kilowatts (kW) in capacity that generate electricity using solar, wind, hydropower or biomass resources....

88

Interconnection Standards  

Broader source: Energy.gov [DOE]

In 2006, West Virginia stakeholders came together to consider net metering, interconnection as required by the Federal Energy Policy Act (2005) and agreed upon a "Statement of Consensus Among...

89

Interconnection Standards  

Broader source: Energy.gov [DOE]

Vermont has adopted separate interconnection standards for net-metered energy systems that are 150 kW or less, and for all other distributed-generation (DG) systems.

90

Interconnection Standards  

Broader source: Energy.gov [DOE]

Interconnection in New Mexico is governed by New Mexico Public Regulation Commission (PRC) Rule 568 and Rule 569. These rules, adopted in July 2008, revised and clarified the state's existing rules...

91

Interconnection Standards  

Broader source: Energy.gov [DOE]

Hawaii has established simplified interconnection rules for small renewables and separate rules for all other distributed generation (DG). For inverter-based systems up to 10 kilowatts (kW) in...

92

Cost and quality of fuels for electric utility plants: Energy data report. 1980 annual  

SciTech Connect (OSTI)

In 1980 US electric utilities reported purchasng 594 million tons of coal, 408.5 million barrels of oil and 3568.7 billion ft/sup 3/ of gas. As compared with 1979 purchases, coal rose 6.7%, oil decreased 20.9%, and gas increased for the fourth year in a row. This volume presents tabulated and graphic data on the cost and quality of fossil fuel receipts to US electric utilities plants with a combined capacity of 25 MW or greater. Information is included on fuel origin and destination, fuel types, and sulfur content, plant types, capacity, and flue gas desulfurization method used, and fuel costs. (LCL)

Not Available

1981-06-25T23:59:59.000Z

93

Public Utility Commission Regulation and Cost-Effectiveness of Title IV: Lessons for CAIR  

SciTech Connect (OSTI)

There is growing evidence that the cost savings potential of the Title IV SO{sub 2} cap-and-trade program is not being reached. PUC regulatory treatment of compliance options appears to provide one explanation for this finding. That suggests that PUCs and utility companies should work together to develop incentive plans that will encourage cost-minimizing behavior for compliance with the EPA's recently issued Clean Air Interstate Rule.

Sotkiewicz, Paul M.; Holt, Lynne

2005-10-01T23:59:59.000Z

94

Case Study: Sustained Utility Cost Reduction in a Large Manufacturing Facility  

E-Print Network [OSTI]

This case study presents results of a systematic utility cost reduction plan implemented at a 450,000 sq. ft. manufacturing facility in a hot and humid climate. Electricity, natural gas, and water usage were all reduced on an absolute basis in both...

Fiorino, D.

2004-01-01T23:59:59.000Z

95

User's guide to SERICPAC: A computer program for calculating electric-utility avoided costs rates  

SciTech Connect (OSTI)

SERICPAC is a computer program developed to calculate average avoided cost rates for decentralized power producers and cogenerators that sell electricity to electric utilities. SERICPAC works in tandem with SERICOST, a program to calculate avoided costs, and determines the appropriate rates for buying and selling of electricity from electric utilities to qualifying facilities (QF) as stipulated under Section 210 of PURA. SERICPAC contains simulation models for eight technologies including wind, hydro, biogas, and cogeneration. The simulations are converted in a diversified utility production which can be either gross production or net production, which accounts for an internal electricity usage by the QF. The program allows for adjustments to the production to be made for scheduled and forced outages. The final output of the model is a technology-specific average annual rate. The report contains a description of the technologies and the simulations as well as complete user's guide to SERICPAC.

Wirtshafter, R.; Abrash, M.; Koved, M.; Feldman, S.

1982-05-01T23:59:59.000Z

96

Balancing Cost and Risk: The Treatment of Renewable Energy in Western Utility Resource Plans  

SciTech Connect (OSTI)

Markets for renewable energy have historically been motivated primarily by policy efforts, but a less widely recognized driver is poised to also play a major role in the coming years: utility integrated resource planning (IRP). Resource planning has re-emerged in recent years as an important tool for utilities and regulators, particularly in regions where retail competition has failed to take root. In the western United States, the most recent resource plans contemplate a significant amount of renewable energy additions. These planned additions--primarily coming from wind power--are motivated by the improved economics of wind power, a growing acceptance of wind by electric utilities, and an increasing recognition of the inherent risks (e.g., natural gas price risk, environmental compliance risk) in fossil-based generation portfolios. This report examines how twelve western utilities treat renewable energy in their recent resource plans. In aggregate, these utilities supply approximately half of all electricity demand in the western United States. Our purpose is twofold: (1) to highlight the growing importance of utility IRP as a current and future driver of renewable energy, and (2) to identify methodological/modeling issues, and suggest possible improvements to methods used to evaluate renewable energy as a resource option. Here we summarize the key findings of the report, beginning with a discussion of the planned renewable energy additions called for by the twelve utilities, an overview of how these plans incorporated renewables into candidate portfolios, and a review of the specific technology cost and performance assumptions they made, primarily for wind power. We then turn to the utilities' analysis of natural gas price and environmental compliance risks, and examine how the utilities traded off portfolio cost and risk in selecting a preferred portfolio.

Bolinger, Mark; Wiser, Ryan

2005-08-10T23:59:59.000Z

97

Reliable, Low-Cost Distributed Generator/Utility System Interconnect: Final Subcontract Report, November 2001-March 2004  

SciTech Connect (OSTI)

This report summarizes the detailed study and development of new GE anti-islanding controls for two classes of distributed generation. One is inverter-interfaced, while the other is synchronous machine interfaced.

Ye, Z.; Walling, R.; Miller, N.; Du, P.; Nelson, K.; Li, L.; Zhou, R.; Garces, L.; Dame, M.

2006-03-01T23:59:59.000Z

98

Flexible interconnects for fuel cell stacks  

DOE Patents [OSTI]

An interconnect that facilitates electrical connection and mechanical support with minimal mechanical stress for fuel cell stacks. The interconnects are flexible and provide mechanically robust fuel cell stacks with higher stack performance at lower cost. The flexible interconnects replace the prior rigid rib interconnects with flexible "fingers" or contact pads which will accommodate the imperfect flatness of the ceramic fuel cells. Also, the mechanical stress of stacked fuel cells will be smaller due to the flexibility of the fingers. The interconnects can be one-sided or double-sided.

Lenz, David J.; Chung, Brandon W.; Pham, Ai Quoc

2004-11-09T23:59:59.000Z

99

Utility Accrual Real-Time Scheduling Under Variable Cost Functions Haisang Wu Umut Balli Binoy Ravindran E. Douglas Jensen  

E-Print Network [OSTI]

Utility Accrual Real-Time Scheduling Under Variable Cost Functions Haisang Wu Umut Balli Binoy,binoy}@vt.edu The MITRE Corporation Bedford, MA 01730, USA jensen@mitre.org Abstract We present a utility accrual real application activities that are subject to time/utility function time constraints, VCFs, and the multi

Ravindran, Binoy

100

Interconnection Guidelines  

Broader source: Energy.gov [DOE]

Missouri enacted legislation (S.B. 54) in June 2007 requiring all of the state's electric utilities -- including municipal utilities and electric cooperatives -- to offer net metering to customers...

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


101

Interconnection Standards  

Broader source: Energy.gov [DOE]

Minnesota's net-metering law, enacted in 1983, applies to all investor-owned utilities, municipal utilities and rural electric cooperatives. Qualifying facilities of less than 1,000 kilowatts (kW)...

102

Interconnection Standards  

Broader source: Energy.gov [DOE]

The Texas Public Utility Regulatory Act (PURA) of 1999 included a provision that "a customer is entitled to have access to on-site distributed generation". As a result, the Public Utility...

103

The Program Administrator Cost of Saved Energy for Utility Customer-Funded Energy Efficiency Programs  

SciTech Connect (OSTI)

End-use energy efficiency is increasingly being relied upon as a resource for meeting electricity and natural gas utility system needs within the United States. There is a direct connection between the maturation of energy efficiency as a resource and the need for consistent, high-quality data and reporting of efficiency program costs and impacts. To support this effort, LBNL initiated the Cost of Saved Energy Project (CSE Project) and created a Demand-Side Management (DSM) Program Impacts Database to provide a resource for policy makers, regulators, and the efficiency industry as a whole. This study is the first technical report of the LBNL CSE Project and provides an overview of the project scope, approach, and initial findings, including: ē Providing a proof of concept that the program-level cost and savings data can be collected, organized, and analyzed in a systematic fashion; ē Presenting initial program, sector, and portfolio level results for the program administrator CSE for a recent time period (2009-2011); and ē Encouraging state and regional entities to establish common reporting definitions and formats that would make the collection and comparison of CSE data more reliable. The LBNL DSM Program Impacts Database includes the program results reported to state regulators by more than 100 program administrators in 31 states, primarily for the years 2009Ė2011. In total, we have compiled cost and energy savings data on more than 1,700 programs over one or more program-years for a total of more than 4,000 program-yearsí worth of data, providing a rich dataset for analyses. We use the information to report costs-per-unit of electricity and natural gas savings for utility customer-funded, end-use energy efficiency programs. The program administrator CSE values are presented at national, state, and regional levels by market sector (e.g., commercial, industrial, residential) and by program type (e.g., residential whole home programs, commercial new construction, commercial/industrial custom rebate programs). In this report, the focus is on gross energy savings and the costs borne by the program administratoróincluding administration, payments to implementation contractors, marketing, incentives to program participants (end users) and both midstream and upstream trade allies, and evaluation costs. We collected data on net savings and costs incurred by program participants. However, there were insufficient data on participant cost contributions, and uncertainty and variability in the ways in which net savings were reported and defined across states (and program administrators).

Billingsley, Megan A.; Hoffman, Ian M.; Stuart, Elizabeth; Schiller, Steven R.; Goldman, Charles A.; LaCommare, Kristina

2014-03-19T23:59:59.000Z

104

A High-Performance Optoelectronic Interconnect Router: Using Increased Bandwidth to Enable Latency Reduction  

E-Print Network [OSTI]

D R A FT 1 A High-Performance Optoelectronic Interconnect Router: Using Increased Bandwidth optoelectronic interconnection network router capable of supplying and efficiently utilizing higher bandwidth routing, interconnection network, latency hiding/reduction techniques, optoelectronic router. 1

Pinkston, Timothy M.

105

Interconnection Standards  

Broader source: Energy.gov [DOE]

'''''Note: The California Public Utilities Commission (CPUC) approved a [http://docs.cpuc.ca.gov/EFILE/MOTION/162852.PDF proposed settlement] in September 2012, enacting the first fundamental...

106

Public Service Commission Authorization to Utilize an Alternative Method of Cost Recovery for Certain Base Load Generation (Mississippi)  

Broader source: Energy.gov [DOE]

The Senate Bill 2793 authorizes the Public Service Commission (PSC) to utilize an alternative cost recovery for certain base load generation. The PSC is authorized to include in an electric...

107

National Offshore Wind Energy Grid Interconnection Study  

SciTech Connect (OSTI)

The National Offshore Wind Energy Grid Interconnection Study (NOWEGIS) considers the availability and potential impacts of interconnecting large amounts of offshore wind energy into the transmission system of the lower 48 contiguous United States. A total of 54GW of offshore wind was assumed to be the target for the analyses conducted. A variety of issues are considered including: the anticipated staging of offshore wind; the offshore wind resource availability; offshore wind energy power production profiles; offshore wind variability; present and potential technologies for collection and delivery of offshore wind energy to the onshore grid; potential impacts to existing utility systems most likely to receive large amounts of offshore wind; and regulatory influences on offshore wind development. The technologies considered the reliability of various high-voltage ac (HVAC) and high-voltage dc (HVDC) technology options and configurations. The utility system impacts of GW-scale integration of offshore wind are considered from an operational steady-state perspective and from a regional and national production cost perspective.

Daniel, John P. [ABB Inc; Liu, Shu [ABB Inc; Ibanez, Eduardo [National Renewable Energy Laboratory; Pennock, Ken [AWS Truepower; Reed, Greg [University of Pittsburgh; Hanes, Spencer [Duke Energy

2014-07-30T23:59:59.000Z

108

Interconnection Standards  

Broader source: Energy.gov [DOE]

New Hampshire requires all utilities selling electricity in the state to offer net metering to customers who own or operate systems up to one megawatt (1 MW) in capacity that generate electricity...

109

Interconnection Standards  

Broader source: Energy.gov [DOE]

Utah requires the state's only investor-owned utility, Rocky Mountain Power (RMP), and most electric cooperatives* to offer net metering to customers who generate electricity using solar energy,...

110

LSA Space Guidelines February 2011 The rising costs of utilities and building maintenance have placed increasing stress on the University's  

E-Print Network [OSTI]

1 LSA Space Guidelines ­February 2011 Overview The rising costs of utilities and building costs, the Provost has launched a University-wide Space Initiative that will unfold over a period of several years. The Initiative will inventory all University space and study its management

Resnick, Paul

111

Interconnecting PV on New York City's Secondary Network  

E-Print Network [OSTI]

Interconnecting PV on New York City's Secondary Network Distribution System K. Anderson, M #12;Technical Report Interconnecting PV on New York NREL/ TP-7A2-46902 City's Secondary Network of Concerns and Solutions to PV Interconnection in New York City 4.0 Utility Application Process Review 5

112

Interconnection networks  

DOE Patents [OSTI]

A network of interconnected processors is formed from a vertex symmetric graph selected from graphs GAMMA/sub d/(k) with degree d, diameter k, and (d + 1)exclamation/ (d /minus/ k + 1)exclamation processors for each d greater than or equal to k and GAMMA/sub d/(k, /minus/1) with degree d /minus/ 1, diameter k + 1, and (d + 1)exclamation/(d /minus/ k + 1)exclamation processors for each d greater than or equal to k greater than or equal to 4. Each processor has an address formed by one of the permutations from a predetermined sequence of letters chosen a selected number of letters at a time, and an extended address formed by appending to the address the remaining ones of the predetermined sequence of letters. A plurality of transmission channels is provided from each of the processors, where each processor has one less channel than the selected number of letters forming the sequence. Where a network GAMMA/sub d/(k, /minus/1) is provided, no processor has a channel connected to form an edge in a direction delta/sub 1/. Each of the channels has an identification number selected from the sequence of letters and connected from a first processor having a first extended address to a second processor having a second address formed from a second extended address defined by moving to the front of the first extended address the letter found in the position within the first extended address defined by the channel identification number. The second address is then formed by selecting the first elements of the second extended address corresponding to the selected number used to form the address permutations. 9 figs.

Faber, V.; Moore, J.W.

1988-06-20T23:59:59.000Z

113

Interconnection Standards  

Broader source: Energy.gov [DOE]

'''''Note: In July 2012, the Public Utilities Commission of Ohio (PUCO) opened a docket ([http://dis.puc.state.oh.us/CaseRecord.aspx?CaseNo=12-2051&x=0&y=0 Case 12-0251-EL-ORD]) to review...

114

Utility planning using least-cost principles and the role of externalities - staff report on a Keystone policy dialogue  

SciTech Connect (OSTI)

For over two years, The Keystone Center facilitated a two-phase dialogue on Utility Planning Using Least-Cost Principles and, in the second phase, on the role of Externalities. The intent of this report is to assist policy-makers faced with decisions about changes to traditional utility regulation and planning. This report is not a consensus document, rather it is staff written summary of two years of discussion on the issues. As a concept, least-cost planning has been discussed since the 1970`s and many states have implemented such programs since the mid-1980`s. Yet, the actual goals and objectives of least-cost planning remain a source of controversy between affected interest groups. Some industry observers believe that least-cost planning can help reconcile the often conflicting demands between increased capacity requirements and concerns about the external costs of power production. In traditional utility regulation practices, capital investments are rewarded and revenue is a direct function of sales. However, a number state public utility commissions have altered their practices to allow for returns on investments in more efficient end-use equipment (also known as ratebasing conservation) and adjusting revenues to account for sales lost due to utility conservation programs. Other states are planning these types of changes. Still others are observing the impacts of the changes before they commit.

NONE

1996-05-01T23:59:59.000Z

115

Updating Technical Screens for PV Interconnection: Preprint  

SciTech Connect (OSTI)

Solar photovoltaics (PV) is the dominant type of distributed generation (DG) technology interconnected to electric distribution systems in the United States, and deployment of PV systems continues to increase rapidly. Considering the rapid growth and widespread deployment of PV systems in United States electric distribution grids, it is important that interconnection procedures be as streamlined as possible to avoid unnecessary interconnection studies, costs, and delays. Because many PV interconnection applications involve high penetration scenarios, the process needs to allow for a sufficiently rigorous technical evaluation to identify and address possible system impacts. Existing interconnection procedures are designed to balance the need for efficiency and technical rigor for all DG. However, there is an implicit expectation that those procedures will be updated over time in order to remain relevant with respect to evolving standards, technology, and practical experience. Modifications to interconnection screens and procedures must focus on maintaining or improving safety and reliability, as well as accurately allocating costs and improving expediency of the interconnection process. This paper evaluates the origins and usefulness of the capacity penetration screen, offers potential short-term solutions which could effectively allow fast-track interconnection to many PV system applications, and considers longer-term solutions for increasing PV deployment levels in a safe and reliable manner while reducing or eliminating the emphasis on the penetration screen.

Coddington, M.; Ellis, A.; Lynn, K.; Razon, A.; Key, T.; Kroposki, B.; Mather, B.; Hill, R.; Nicole, K.; Smith, J.

2012-08-01T23:59:59.000Z

116

Design, development, and applications of a low-cost, dynamic neutron radiography system utilizing the TAMU NSC TRIGA reactor  

E-Print Network [OSTI]

partial fulfilment of the requirements for the degree of MASTER OF SC'IENCE May 1990 Major Subject: Nuclear Engineering DESIGN, DEVELOPMENT. AND APPLICATIONS OF A LOW ? COST, DYNAMIC NEUTRON RADIOGRAPHY SYSTEM UTILIZING THE TAMU NSC TRIGA REACTOR A...DESIGN, DEVELOPMENT. AND APPLICATIONS OF A LOW ? COST, DYNAMIC NEUTRON RADIOGRAPHY SYSTEM UTILIZING THE TAMU NSC TRIGA REACTOR A Thesis SC'OTT PATRIC'If ItIIDGETT Submitted to the Ofhce of Graduate Studies of Texas AklVI I!niversity rn...

Midgett, Scott Patrick

2012-06-07T23:59:59.000Z

117

Balancing Cost and Risk: The Treatment of Renewable Energy in Western Utility Resource Plans  

E-Print Network [OSTI]

in their treatment of renewable resources and the costs andPlanning with Renewable Resources. Ē The Electricityindirect costs of renewable resources, as well as resource

Wiser, Ryan; Bolinger, Mark

2005-01-01T23:59:59.000Z

118

Sandia National Laboratories: Water Availability, Cost, and Use  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

InterconnectsWater Availability, Cost, and Use Water Availability, Cost, and Use Water Availability, Cost, and Use Water Availability, Cost, and Use Availability, cost, and...

119

Logistics, Costs, and GHG Impacts of Utility Scale Cofiring with 20% Biomass  

SciTech Connect (OSTI)

This report presents the results of an evaluation of utility-scale biomass cofiring in large pulverized coal power plants. The purpose of this evaluation is to assess the cost and greenhouse gas reduction benefits of substituting relatively high volumes of biomass in coal. Two scenarios for cofiring up to 20% biomass with coal (on a lower heating value basis) are presented; (1) woody biomass in central Alabama where Southern Pine is currently produced for the wood products and paper industries, and (2) purpose-grown switchgrass in the Ohio River Valley. These examples are representative of regions where renewable biomass growth rates are high in correspondence with major U.S. heartland power production. While these scenarios may provide a realistic reference for comparing the relative benefits of using a high volume of biomass for power production, this evaluation is not intended to be an analysis of policies concerning renewable portfolio standards or the optimal use of biomass for energy production in the U.S.

Boardman, Richard D.; Cafferty, Kara G.; Nichol, Corrie; Searcy, Erin M.; Westover, Tyler; Wood, Richard; Bearden, Mark D.; Cabe, James E.; Drennan, Corinne; Jones, Susanne B.; Male, Jonathan L.; Muntean, George G.; Snowden-Swan, Lesley J.; Widder, Sarah H.

2014-07-22T23:59:59.000Z

120

Methods for Analyzing the Benefits and Costs of Distributed Photovoltaic Generation to the U.S. Electric Utility System  

SciTech Connect (OSTI)

This report outlines the methods, data, and tools that could be used at different levels of sophistication and effort to estimate the benefits and costs of DGPV. In so doing, we identify the gaps in current benefit-cost-analysis methods, which we hope will inform the ongoing research agenda in this area. The focus of this report is primarily on benefits and costs from the utility or electricity generation system perspective. It is intended to provide useful background information to utility and regulatory decision makers and their staff, who are often being asked to use or evaluate estimates of the benefits and cost of DGPV in regulatory proceedings. Understanding the technical rigor of the range of methods and how they might need to evolve as DGPV becomes a more significant contributor of energy to the electricity system will help them be better consumers of this type of information. This report is also intended to provide information to utilities, policy makers, PV technology developers, and other stakeholders, which might help them maximize the benefits and minimize the costs of integrating DGPV into a changing electricity system.

Denholm, P.; Margolis, R.; Palmintier, B.; Barrows, C.; Ibanez, E.; Bird, L.; Zuboy, J.

2014-09-01T23:59:59.000Z

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


121

Balancing Cost and Risk: The Treatment of Renewable Energy in Western Utility Resource Plans  

E-Print Network [OSTI]

Planning with Renewable Resources. Ē The Electricity14 4.1 Renewable Resources20 5. Renewable Resource Cost and Performance

Bolinger, Mark; Wiser, Ryan

2005-01-01T23:59:59.000Z

122

Un/DoPack: Re-Clustering of Large System-on-Chip Designs with Interconnect Variation for Low-Cost FPGAs  

E-Print Network [OSTI]

to offer separate low-cost and resource-rich families. For a similar number of logic elements (LEs. This is demonstrated by Table 1, where the low-cost Cyclone family offers significant savings. Unfortunately, some designs may fit within the Cyclone LE and memory capacity limits but not within the routing capacity

Lemieux, Guy

123

Analysis of novel, above-ground thermal energy storage concept utilizing low-cost, solid medium .  

E-Print Network [OSTI]

??Clean energy power plants cannot effectively match peak demands without utilizing energy storage technologies. Currently, several solutions address short term demand cycles, but little workÖ (more)

Barineau, Mark Michael

2010-01-01T23:59:59.000Z

124

Balancing Cost and Risk: The Treatment of Renewable Energy in Western Utility Resource Plans  

E-Print Network [OSTI]

Planning with Renewable Resources. Ē The Electricityin their treatment of renewable resources and the costs andcost and value of renewable resources, and reflect the fact

Bolinger, Mark; Wiser, Ryan

2005-01-01T23:59:59.000Z

125

Balancing Cost and Risk: The Treatment of Renewable Energy in Western Utility Resource Plans  

E-Print Network [OSTI]

Planning with Renewable Resources. Ē The Electricityindirect costs of renewable resources, as well as resourceamount of planned renewable resource additions. In the case

Wiser, Ryan; Bolinger, Mark

2005-01-01T23:59:59.000Z

126

Electric-utility DSM-program costs and effects, 1991 to 2001  

SciTech Connect (OSTI)

For the past three years (1989, 1990, and 1991), all US electric utilities that sell more than 120 GWh/year have been required to report to the Energy Information Administration data on their demand-side management (DSM) programs. These data provide a rich and uniquely comprehensive picture of electric-utility DSM programs in the United States. Altogether, 890 utilities (of about 3250 in the United States) ran DSM programs in 1991; of these, 439 sold more than 120 GWh and reported details on their DSM programs. These 439 utilities represent more than 80% of total US electricity sales and revenues. Altogether, these utilities spent almost $1.8 billion on DSM programs in 1991, equal to 1.0% of total utility revenues that year. In return for these (and prior-year) expenditures, utility DSM programs cut potential peak demand by 26,700 MW (4.8% of the national total) and cut annual electricity use by 23,300 GWh (0.9% of the national total). These 1991 numbers represent substantial increases over the 1989 and 1990 numbers on utility DSM programs. Specifically, utility DSM expenditures doubled, energy savings increased by almost 50%, and demand reductions increased by one-third between 1989 and 1991. Utilities differed enormously in their DSM-program expenditures and effects. Almost 12% of the reporting utilities spent more than 2% of total revenues on DSM programs in 1991, while almost 60% spent less than 0.5% of revenues on DSM. Utility estimates of future DSM-program expenditures and benefits show continuing growth. By the year 2001, US utilities expect to spend 1.2% of revenues on DSM and to cut demand by 8.8% and annual sales by 2.7%. Here, too, expectations vary by region. Utilities in the West and Northwest plan to spend more than 2% of revenues on DSM that year, while utilities in the Mid-Atlantic, Midwest, Southwest, Central, and North Central regions plan to spend less than 1% of revenues on DSM.

Hirst, E.

1993-05-01T23:59:59.000Z

127

Interconnecting PV on New York City's Secondary Network Distribution System  

SciTech Connect (OSTI)

The U.S. Department of Energy (DOE) has teamed with cities across the country through the Solar America Cities (SAC) partnership program to help reduce barriers and accelerate implementation of solar energy. The New York City SAC team is a partnership between the City University of New York (CUNY), the New York City Mayor s Office of Long-term Planning and Sustainability, and the New York City Economic Development Corporation (NYCEDC).The New York City SAC team is working with DOE s National Renewable Energy Laboratory (NREL) and Con Edison, the local utility, to develop a roadmap for photovoltaic (PV) installations in the five boroughs. The city set a goal to increase its installed PV capacity from1.1 MW in 2005 to 8.1 MW by 2015 (the maximum allowed in 2005). A key barrier to reaching this goal, however, is the complexity of the interconnection process with the local utility. Unique challenges are associated with connecting distributed PV systems to secondary network distribution systems (simplified to √?¬?√?¬Ę√?¬?√?¬?√?¬?√?¬?networks√?¬?√?¬Ę√?¬?√?¬?√?¬?√?¬Ě in this report). Although most areas of the country use simpler radial distribution systems to distribute electricity, larger metropolitan areas like New York City typically use networks to increase reliability in large load centers. Unlike the radial distribution system, where each customer receives power through a single line, a network uses a grid of interconnected lines to deliver power to each customer through several parallel circuits and sources. This redundancy improves reliability, but it also requires more complicated coordination and protection schemes that can be disrupted by energy exported from distributed PV systems. Currently, Con Edison studies each potential PV system in New York City to evaluate the system s impact on the network, but this is time consuming for utility engineers and may delay the customer s project or add cost for larger installations. City leaders would like to streamline this process to facilitate faster, simpler, and less expensive distributed PV system interconnections. To assess ways to improve the interconnection process, NREL conducted a four-part study with support from DOE. The NREL team then compiled the final reports from each study into this report. In Section 1√?¬?√?¬Ę√?¬?√?¬?√?¬?√?¬?PV Deployment Analysis for New York City√?¬?√?¬Ę√?¬?√?¬?√?¬?√?¬?we analyze the technical potential for rooftop PV systems in the city. This analysis evaluates potential PV power production in ten Con Edison networks of various locations and building densities (ranging from high density apartments to lower density single family homes). Next, we compare the potential power production to network loads to determine where and when PV generation is most likely to exceed network load and disrupt network protection schemes. The results of this analysis may assist Con Edison in evaluating future PV interconnection applications and in planning future network protection system upgrades. This analysis may also assist other utilities interconnecting PV systems to networks by defining a method for assessing the technical potential of PV in the network and its impact on network loads. Section 2√?¬?√?¬Ę√?¬?√?¬?√?¬?√?¬?A Briefing for Policy Makers on Connecting PV to a Network Grid√?¬?√?¬Ę√?¬?√?¬?√?¬?√?¬?presents an overview intended for nontechnical stakeholders. This section describes the issues associated with interconnecting PV systems to networks, along with possible solutions. Section 3√?¬?√?¬Ę√?¬?√?¬?√?¬?√?¬?Technical Review of Concerns and Solutions to PV Interconnection in New Y

K. Anderson; M. Coddington; K. Burman; S. Hayter; B. Kroposki; and A. Watson

2009-11-30T23:59:59.000Z

128

PJM Interconnection (Multiple States)  

Broader source: Energy.gov [DOE]

PJM (originally Pennsylvania, Jersey, Maryland) Interconnection is a Regional Transmission Organization (RTO) that coordinates the movement of wholesale electricity in all or parts of Delaware,...

129

Perforation patterned electrical interconnects  

DOE Patents [OSTI]

This disclosure describes systems and methods for increasing the usable surface area of electrical contacts within a device, such as a thin film solid state device, through the implementation of electrically conductive interconnects. Embodiments described herein include the use of a plurality of electrically conductive interconnects that penetrate through a top contact layer, through one or more multiple layers, and into a bottom contact layer. The plurality of conductive interconnects may form horizontal and vertical cross-sectional patterns. The use of lasers to form the plurality of electrically conductive interconnects from reflowed layer material further aids in the manufacturing process of a device.

Frey, Jonathan

2014-01-28T23:59:59.000Z

130

Strategic Plan for Utilizing Low Cost Engineering Resources at Generic Aerospace  

E-Print Network [OSTI]

of these methods are costly and may cause other issues, such as inconsistent output, high turnover and resource constraints for other sites. One concept that is being more readily adopted is the use of Low Cost Engineering Services (LCES) offered by third party...

Veach, Michael

2012-12-14T23:59:59.000Z

131

Analysis of novel, above-ground thermal energy storage concept utilizing low-cost, solid medium  

E-Print Network [OSTI]

Clean energy power plants cannot effectively match peak demands without utilizing energy storage technologies. Currently, several solutions address short term demand cycles, but little work has been done to address seasonal ...

Barineau, Mark Michael

2010-01-01T23:59:59.000Z

132

Identifying Cost-Effective Residential Energy Efficiency Opportunities for the Kauai Island Utility Cooperative  

Office of Energy Efficiency and Renewable Energy (EERE)

This analysis is an update to the Energy Efficiency Potential report completed by KEMA for the Kauai Island Utility Cooperative (KIUC) and identifies potential energy efficiency opportunities in the residential sector on KauaĎi (KEMA 2005).

133

Energy Conservation Fund: Helping Corporations Develop Energy Conservation Strategies and Reduce Utility Costs  

E-Print Network [OSTI]

Energy conservation projects can save companies significant money over time and often pay for themselves very quickly. This is especially true with the dramatic increase in energy costs over the past few years. Yet convincing corporate decision...

Swanson, G. A.; Houston, W.

2005-01-01T23:59:59.000Z

134

Utilizing an encroachment probability benefit-cost model to estimate accident reduction factors  

E-Print Network [OSTI]

Improving safety on Texas roadways is a major public concern. Over the years, the Texas Department of Transportation and other highway agencies have become interested in reducing society's accident cost while maximizing returns on accident...

Hayes, Carolyn A

1997-01-01T23:59:59.000Z

135

Solar cell array interconnects  

DOE Patents [OSTI]

Electrical interconnects are disclosed for solar cells or other electronic components using a silver-silicone paste or a lead-tin (Pb-Sn) no-clean fluxless solder cream, whereby the high breakage of thin (<6 mil thick) solar cells using conventional solder interconnect is eliminated. The interconnects of this invention employs copper strips which are secured to the solar cells by a silver-silicone conductive paste which can be used at room temperature, or by a Pb-Sn solder cream which eliminates undesired residue on the active surfaces of the solar cells. Electrical testing using the interconnects of this invention has shown that no degradation of the interconnects developed under high current testing, while providing a very low contact resistance value. 4 figs.

Carey, P.G.; Thompson, J.B.; Colella, N.J.; Williams, K.A.

1995-11-14T23:59:59.000Z

136

Solar cell array interconnects  

DOE Patents [OSTI]

Electrical interconnects for solar cells or other electronic components using a silver-silicone paste or a lead-tin (Pb-Sn) no-clean fluxless solder cream, whereby the high breakage of thin (<6 mil thick) solar cells using conventional solder interconnect is eliminated. The interconnects of this invention employs copper strips which are secured to the solar cells by a silver-silicone conductive paste which can be used at room temperature, or by a Pb-Sn solder cream which eliminates undesired residue on the active surfaces of the solar cells. Electrical testing using the interconnects of this invention has shown that no degradation of the interconnects developed under high current testing, while providing a very low contact resistance value.

Carey, Paul G. (Mountain View, CA); Thompson, Jesse B. (Brentwood, CA); Colella, Nicolas J. (Livermore, CA); Williams, Kenneth A. (Livermore, CA)

1995-01-01T23:59:59.000Z

137

Updating Small Generator Interconnection Procedures for New Market Conditions  

SciTech Connect (OSTI)

Federal and state regulators are faced with the challenge of keeping interconnection procedures updated against a backdrop of evolving technology, new codes and standards, and considerably transformed market conditions. This report is intended to educate policymakers and stakeholders on beneficial reforms that will keep interconnection processes efficient and cost-effective while maintaining a safe and reliable power system.

Coddington, M.; Fox, K.; Stanfield, S.; Varnado, L.; Culley, T.; Sheehan, M.

2012-12-01T23:59:59.000Z

138

Updated Analysis of Energy and cost Savings for Utility service Program at Federal Sites  

SciTech Connect (OSTI)

Report detailing PNNL's re-analysis of data based original analysis done in 2004. The data came from the updated Department of Energy Federal Energy Management utility energy services contract database and the analysis was also expanded to uncover information on additional areas.

Mcmordie, Katherine; Sandusky, William F.; Solana, Amy E.; Bates, Derrick J.

2006-10-31T23:59:59.000Z

139

The cost of reducing utility S02 emissions : not as low as you might think  

E-Print Network [OSTI]

A common assertion in public policy discussions is that the cost of achieving the SO2 emissions reductions under the acid rain provisions of the Clean Air Act ("Title IV") has been only one-tenth or less of what Title IV ...

Smith, Anne E.

1998-01-01T23:59:59.000Z

140

Low-Cost High-Concentration Photovoltaic Systems for Utility Power Generation  

SciTech Connect (OSTI)

Under DOE's Technology Pathway Partnership (TPP) program, Amonix, Inc. developed a new generation of high-concentration photovoltaic systems using multijunction technology and established the manufacturing capacity needed to supply multi-megawatt power plants buing using the new Amonix 7700-series solar energy systems. For this effort, Amonix Collaborated with a variety of suppliers and partners to complete project tasks. Subcontractors included: Evonik/Cyro; Hitek; the National Renewable Energy Laboratory (NREL); Raytech; Spectrolab; UL; University of Nevada, Las Vegas; and TUV Rheinland PTL. The Amonix TPP tasks included: Task 1: Multijunction Cell Optimization for Field Operation, Task 2: Fresnel Lens R&D, Task 3: Cell Package Design & Production, Task 4: Standards Compliance and Reliability Testing, Task 5: Receiver Plate Production, Task 6: MegaModule Performance, Task 7: MegaModule Cost Reduction, Task 8: Factory Setup and MegaModule Production, Task 9: Tracker and Tracking Controller, Task 10: Installation and Balance of System (BOS), Task 11: Field Testing, and Task 12: Solar Advisor Modeling and Market Analysis. Amonix's TPP addressed nearly the complete PV value chain from epitaxial layer design and wafer processing through system design, manufacturing, deployment and O&M. Amonix has made progress toward achieving these reduced costs through the development of its 28%+ efficient MegaModule, reduced manufacturing and installation cost through design for manufacturing and assembly, automated manufacturing processes, and reduced O&M costs. Program highlights include: (1) Optimized multijunction cell and cell package design to improve performance by > 10%; (2) Updated lens design provided 7% increased performance and higher concentration; (3) 28.7% DC STC MegaModule efficiency achieved in Phase II exceeded Phase III performance goal; (4) New 16' focal length MegaModule achieved target materials and manufacturing cost reduction; (5) Designed and placed into production 25 MW/yr manufacturing capacity for complete MegaModules, including cell packages, receiver plates, and structures with lenses; (6) Designed and deployed Amonix 7700 series systems rated at 63 kW PTC ac and higher. Based on an LCOE assessment using NREL's Solar Advisor Model, Amonix met DOE's LCOE targets: Amonix 2011 LCOE 12.8 cents/kWh (2010 DOE goal 10-15); 2015 LCOE 6.4 cents/kWh (2015 goal 5-7) Amonix and TPP participants would like to thank the U.S. Department of Energy Solar Energy Technology Program for funding received under this program through Agreement No. DE-FC36-07GO17042.

McConnell, R.; Garboushian, V.; Gordon, R.; Dutra, D.; Kinsey, G.; Geer, S.; Gomez, H.; Cameron, C.

2012-03-31T23:59:59.000Z

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


141

Passive microfluidic interconnects  

E-Print Network [OSTI]

Equipment and procedures were developed to test two passive microfluidic interconnect rings held together by the friction forces on the contact surfaces. The second design forms fluid seals by means of thin flared rings ...

Jonnalagadda, Aparna S

2005-01-01T23:59:59.000Z

142

Interconnection Guidelines (Rhode Island)  

Broader source: Energy.gov [DOE]

Rhode Island enacted legislation (HB 6222) in June 2011 to standardize the application process for the interconnection of customer-sited renewable-energy systems to the stateís distribution grid....

143

Puerto Rico- Interconnection Standards  

Broader source: Energy.gov [DOE]

In 2007, the Autoridad de EnergŪa Electrica de Puerto Rico (PREPA*) adopted interconnection standards based on the standard contained in the federal Energy Policy Act of 2005. PREPA promulgated...

144

Handshake and Circulation Flow Control in Nanaphotonic Interconnects  

E-Print Network [OSTI]

leads to low bandwidth utilization. This thesis proposes two handshake schemes for nanophotonic interconnects in CMPs, Global Handshake (GHS) and Distributed Handshake (DHS), which get rid of the traditional credit-based flow control, reduce the average...

Jayabalan, Jagadish

2012-10-19T23:59:59.000Z

145

Reliability of Electrical Interconnects (Presentation)  

SciTech Connect (OSTI)

This presentation discusses the status of NREL's research on the reliability of electrical interconnects.

Devoto, D.

2014-06-01T23:59:59.000Z

146

A low cost igniter utilizing an SCB and titanium sub-hydride potassium perchlorate pyrotechnic  

SciTech Connect (OSTI)

A conventional NSI (NASA standard initiator) normally employs a hot-wire ignition element to ignite ZPP (zirconium potassium perchlorate). With minor modifications to the interior of a header similar to an NSI device to accommodate an SCB (semiconductor bridge), a low cost initiator was obtained. In addition, the ZPP was replaced with THKP (titanium subhydride potassium perchlorate) to obtain increased overall gas production and reduced static-charge sensitivity. This paper reports on the all-fire and no-fire levels obtained and on a dual mix device that uses THKP as the igniter mix and a thermite as the output mix.

Bickes, R.W. Jr.; Grubelich, M.C. [Sandia National Labs., Albuquerque, NM (United States); Hartman, J.K.; McCampbell, C.B. [SCB Technologies, Inc., Albuquerque, NM (United States); Churchill, J.K. [Quantic-Holex, Hollister, CA (United States)

1993-12-31T23:59:59.000Z

147

New, Cost-Competitive Solar Plants for Electric Utilities | Department of  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:Year in3.pdfEnergy HealthCommentsAugustNationalMarketsMillion DOEEnergyCost-Effective

148

Optimization and Visualization of the North American Eastern Interconnect Power Market  

E-Print Network [OSTI]

Optimization and Visualization of the North American Eastern Interconnect Power Market Douglas R uses a first generation OPF model of the Eastern Interconnect to gauge the potential benefits deriving, there is sufficient low cost capacity to keep peak demand prices in the Eastern Interconnect below $50 MWH. Under

149

Life-cycle cost comparisons of advanced storage batteries and fuel cells for utility, stand-alone, and electric vehicle applications  

SciTech Connect (OSTI)

This report presents a comparison of battery and fuel cell economics for ten different technologies. To develop an equitable economic comparison, the technologies were evaluated on a life-cycle cost (LCC) basis. The LCC comparison involved normalizing source estimates to a standard set of assumptions and preparing a lifetime cost scenario for each technology, including the initial capital cost, replacement costs, operating and maintenance (O M) costs, auxiliary energy costs, costs due to system inefficiencies, the cost of energy stored, and salvage costs or credits. By considering all the costs associated with each technology over its respective lifetime, the technology that is most economical to operate over any given period of time can be determined. An analysis of this type indicates whether paying a high initial capital cost for a technology with low O M costs is more or less economical on a lifetime basis than purchasing a technology with a low initial capital cost and high O M costs. It is important to realize that while minimizing cost is important, the customer will not always purchase the least expensive technology. The customer may identify benefits associated with a more expensive option that make it the more attractive over all (e.g., reduced construction lead times, modularity, environmental benefits, spinning reserve, etc.). The LCC estimates presented in this report represent three end-use applications: utility load-leveling, stand-alone power systems, and electric vehicles.

Humphreys, K.K.; Brown, D.R.

1990-01-01T23:59:59.000Z

150

Learn More About Interconnections | Department of Energy  

Broader source: Energy.gov (indexed) [DOE]

About Interconnections Learn More About Interconnections EASTERN INTERCONNECTION North America is comprised of two major and three minor alternating current (AC) power grids or...

151

Capillary interconnect device  

DOE Patents [OSTI]

An interconnecting device for connecting a plurality of first fluid-bearing conduits to a corresponding plurality of second fluid-bearing conduits thereby providing fluid communication between the first fluid-bearing conduits and the second fluid-bearing conduits. The device includes a manifold and one or two ferrule plates that are held by compressive axial forces.

Renzi, Ronald F

2013-11-19T23:59:59.000Z

152

QCD Interconnection Effects  

E-Print Network [OSTI]

Heavy objects like the W, Z and t are short-lived compared with typical hadronization times. When pairs of such particles are produced, the subsequent hadronic decay systems may therefore become interconnected. We study such potential effects at Linear Collider energies.

TorbjŲrn SjŲstrand

1999-10-09T23:59:59.000Z

153

QCD Interconnection Effects  

E-Print Network [OSTI]

Heavy objects like the W, Z and t are short-lived compared with typical hadronization times. When pairs of such particles are produced, the subsequent hadronic decay systems may therefore become interconnected. We study such potential effects at Linear Collider energies.

TorbjŲrn SjŲstrand; Valery A. Khoze

1999-08-19T23:59:59.000Z

154

VLSI interconnect Avinoam Kolodny  

E-Print Network [OSTI]

1000 10000 100000 Length [um] Power Local total Global total TOTAL globallocal Power Distribution by Wirelength · Total Dynamic Power · Global clock ­ not included · Local signals nets = 66% · Global signals global signals Total dynamic power (Gate, Diffusion and Interconnect) local clock global signals global

Kolodny, Avinoam

155

North American Electric Reliability Corporation Interconnections...  

Office of Environmental Management (EM)

North American Electric Reliability Corporation Interconnections North American Electric Reliability Corporation Interconnections Map of the North American Electric Reliability...

156

Utility Cost Analysis  

E-Print Network [OSTI]

W Computere 6 Computer HVAC Computers Liebert Unite CRT's Subtotal WAC System VAV AHU' s TABLE 3: OPERATING kW BY SEASON Computers 6 Computer WAC Comput err Liebert Unitr CRT'B Sub total HVAC System VAV AHU's AHU1# Pumps Chillerr Subtotal...

Horn, S.

1984-01-01T23:59:59.000Z

157

Net Metering and Interconnection Procedures-- Incorporating Best Practices  

SciTech Connect (OSTI)

State utility commissions and utilities themselves are actively developing and revising their procedures for the interconnection and net metering of distributed generation. However, the procedures most often used by regulators and utilities as models have not been updated in the past three years, in which time most of the distributed solar facilities in the United States have been installed. In that period, the Interstate Renewable Energy Council (IREC) has been a participant in more than thirty state utility commission rulemakings regarding interconnection and net metering of distributed generation. With the knowledge gained from this experience, IREC has updated its model procedures to incorporate current best practices. This paper presents the most significant changes made to IREC√?¬?√?¬Ę√?¬?√?¬?√?¬?√?¬?s model interconnection and net metering procedures.

Jason Keyes, Kevin Fox, Joseph Wiedman, Staff at North Carolina Solar Center

2009-04-01T23:59:59.000Z

158

Comparing Germany's and California's Interconnection Processes for PV Systems (White Paper)  

SciTech Connect (OSTI)

Establishing interconnection to the grid is a recognized barrier to the deployment of distributed energy generation. This report compares interconnection processes for photovoltaic projects in California and Germany. This report summarizes the steps of the interconnection process for developers and utilities, the average length of time utilities take to process applications, and paperwork required of project developers. Based on a review of the available literature, this report finds that while the interconnection procedures and timelines are similar in California and Germany, differences in the legal and regulatory frameworks are substantial.

Tweedie, A.; Doris, E.

2011-07-01T23:59:59.000Z

159

Interconnection Standards for Small Generators  

Broader source: Energy.gov [DOE]

The Federal Energy Regulatory Commission (FERC) adopted "small generator" interconnection standards for distributed energy resources up to 20 megawatts (MW) in capacity in May 2005.* The FERC's...

160

Assessment of Industrial Load for Demand Response across Western Interconnect  

SciTech Connect (OSTI)

Demand response (DR) has the ability to both increase power grid reliability and potentially reduce operating system costs. Understanding the role of demand response in grid modeling has been difficult due to complex nature of the load characteristics compared to the modeled generation and the variation in load types. This is particularly true of industrial loads, where hundreds of different industries exist with varying availability for demand response. We present a framework considering industrial loads for the development of availability profiles that can provide more regional understanding and can be inserted into analysis software for further study. The developed framework utilizes a number of different informational resources, algorithms, and real-world measurements to perform a bottom-up approach in the development of a new database with representation of the potential demand response resource in the industrial sector across the U.S. This tool houses statistical values of energy and demand response (DR) potential by industrial plant and geospatially locates the information for aggregation for different territories without proprietary information. This report will discuss this framework and the analyzed quantities of demand response for Western Interconnect (WI) in support of evaluation of the cost production modeling with power grid modeling efforts of demand response.

Alkadi, Nasr E [ORNL; Starke, Michael R [ORNL; Ma, Ookie [United States Department of Energy (DOE), Office of Efficiency and Renewable Energy (EERE)

2013-11-01T23:59:59.000Z

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


161

Integrated Energy-Water Planning in the Western and Texas Interconnections  

SciTech Connect (OSTI)

While long-term regional electricity transmission planning has traditionally focused on cost, infrastructure utilization, and reliability, issues concerning the availability of water represent an emerging issue. Thermoelectric expansion must be considered in the context of competing demands from other water use sectors balanced with fresh and non-fresh water supplies subject to climate variability. An integrated Energy-Water Decision Support System (DSS) is being developed that will enable planners in the Western and Texas Interconnections to analyze the potential implications of water availability and cost for long-range transmission planning. The project brings together electric transmission planners (Western Electricity Coordinating Council and Electric Reliability Council of Texas) with western water planners (Western Governorsí Association and the Western States Water Council). This paper lays out the basic framework for this integrated Energy-Water DSS.

Vincent Tidwell; John Gasper; Robert Goldstein; Jordan Macknick; Gerald Sehlke; Michael Webber; Mark Wigmosta

2013-07-01T23:59:59.000Z

162

Corrosion and Protection of Metallic Interconnects in Solid Oxide Fuel Cells  

SciTech Connect (OSTI)

Energy security and increased concern over environmental protection have spurred a dramatic world-wide growth in research and development of fuel cells, which electrochemically convert incoming fuel into electricity with no or low pollution. Fuel cell technology has become increasingly attractive to a number of sectors, including utility, automotive, and defense industries. Among the various types of fuel cells, solid oxide fuel cells (SOFCs) operate at high temperature (typically 650-1,000 C) and have advantages in terms of high conversion efficiency and the flexibility of using hydrocarbon fuels, in addition to hydrogen. The high temperature operation, however, can lead to increased mass transport and interactions between the surrounding environment and components that are required to be stable during a lifetime of thousands of hours and up to hundreds of thermal cycles. For stacks with relatively low operating temperatures (<800 C), the interconnects that are used to electrically connect a number of cells in series are typically made from cost-effective metals or alloys. The metallic interconnects must demonstrate excellent stability in a very challenging environment during SOFC operation, as they are simultaneously exposed to both an oxidizing (air) environment on the cathode side and a reducing environment (hydrogen or a reformed hydrocarbon fuel) on the anode side. Other challenges include the fact that water vapor is likely to be present in both of these environments, and the fuel is likely to contain impurities, such as sulfides. Since the fuel is usually a reformed hydrocarbon fuel, such as natural gas, coal gas, biogas, gasoline, etc., the interconnect is exposed to a wet carbonaceous environment at the anode side. Finally, the interconnect must be stable towards any adjacent components, such as electrodes, seals and electrical contact materials, with which it is in physical contact.

Yang, Z Gary; Stevenson, Jeffry W.; Singh, Prabhakar

2007-12-09T23:59:59.000Z

163

Cogeneration - A Utility Perspective  

E-Print Network [OSTI]

are discussed from a utility perspective as how they influence utility participation in future projects. The avoided cost methodology is examined, and these payments for sale of energy to the utility are compared with utility industrial rates. In addition...

Williams, M.

1983-01-01T23:59:59.000Z

164

Process for electrically interconnecting electrodes  

DOE Patents [OSTI]

Electrical interconnects for solar cells or other electronic components using a silver-silicone paste or a lead-tin (Pb--Sn) no-clean fluxless solder cream, whereby the high breakage of thin (<6 mil thick) solar cells using conventional solder interconnect is eliminated. The interconnects of this invention employs copper strips which are secured to the solar cells by a silver-silicone conductive paste which can be used at room temperature, or by a Pb--Sn solder cream which eliminates undesired residue on the active surfaces of the solar cells. Electrical testing using the interconnects of this invention has shown that no degradation of the interconnects developed under high current testing, while providing a very low contact resistance value.

Carey, Paul G. (Mountain View, CA); Thompson, Jesse B. (Brentwood, CA); Colella, Nicolas J. (Livermore, CA); Williams, Kenneth A. (Livermore, CA)

2002-01-01T23:59:59.000Z

165

Extraction and Modeling of the Optoelectronic Characteristics of an Optical Interconnect Link  

E-Print Network [OSTI]

Extraction and Modeling of the Optoelectronic Characteristics of an Optical Interconnect Link a technique that enables the extraction and modeling of some of the channel's optoelectronic characteristics and optoelectronic com- ponents utilized in the link. 1. Introduction In the last decade optical interconnects have

Esener, Sadik C.

166

Repairable chip bonding/interconnect process  

DOE Patents [OSTI]

A repairable, chip-to-board interconnect process which addresses cost and testability issues in the multi-chip modules. This process can be carried out using a chip-on-sacrificial-substrate technique, involving laser processing. This process avoids the curing/solvent evolution problems encountered in prior approaches, as well is resolving prior plating problems and the requirements for fillets. For repairable high speed chip-to-board connection, transmission lines can be formed on the sides of the chip from chip bond pads, ending in a gull wing at the bottom of the chip for subsequent solder.

Bernhardt, Anthony F. (Berkeley, CA); Contolini, Robert J. (Livermore, CA); Malba, Vincent (Livermore, CA); Riddle, Robert A. (Tracy, CA)

1997-01-01T23:59:59.000Z

167

Repairable chip bonding/interconnect process  

DOE Patents [OSTI]

A repairable, chip-to-board interconnect process which addresses cost and testability issues in the multi-chip modules is disclosed. This process can be carried out using a chip-on-sacrificial-substrate technique, involving laser processing. This process avoids the curing/solvent evolution problems encountered in prior approaches, as well is resolving prior plating problems and the requirements for fillets. For repairable high speed chip-to-board connection, transmission lines can be formed on the sides of the chip from chip bond pads, ending in a gull wing at the bottom of the chip for subsequent solder. 10 figs.

Bernhardt, A.F.; Contolini, R.J.; Malba, V.; Riddle, R.A.

1997-08-05T23:59:59.000Z

168

innovati nInterconnection Standards Guide Integration of Distributed  

E-Print Network [OSTI]

Engineers (IEEE). The goal: to create consensus standards with participation from industry, utilities, government, and others to guide the integration of renewable and other small electricity generation, or used IEEE 1547 in the development of their own interconnection standards, and the Energy Policy Act

169

COMPLEAT (Community-Oriented Model for Planning Least-Cost Energy Alternatives and Technologies): A planning tool for publicly owned electric utilities. [Community-Oriented Model for Planning Least-Cost Energy Alternatives and Technologies (Compleat)  

SciTech Connect (OSTI)

COMPLEAT takes its name, as an acronym, from Community-Oriented Model for Planning Least-Cost Energy Alternatives and Technologies. It is an electric utility planning model designed for use principally by publicly owned electric utilities and agencies serving such utilities. As a model, COMPLEAT is significantly more full-featured and complex than called out in APPA's original plan and proposal to DOE. The additional complexity grew out of a series of discussions early in the development schedule, in which it became clear to APPA staff and advisors that the simplicity characterizing the original plan, while highly desirable in terms of utility applications, was not achievable if practical utility problems were to be addressed. The project teams settled on Energy 20/20, an existing model developed by Dr. George Backus of Policy Assessment Associates, as the best candidate for the kinds of modifications and extensions that would be required. The remainder of the project effort was devoted to designing specific input data files, output files, and user screens and to writing and testing the compute programs that would properly implement the desired features around Energy 20/20 as a core program. This report presents in outline form, the features and user interface of COMPLEAT.

Not Available

1990-09-01T23:59:59.000Z

170

Utilization of municipal wastewater for cooling in thermoelectric power plants: Evaluation of the combined cost of makeup water treatment and increased condenser fouling  

SciTech Connect (OSTI)

A methodology is presented to calculate the total combined cost (TCC) of water sourcing, water treatment and condenser fouling in the recirculating cooling systems of thermoelectric power plants. The methodology is employed to evaluate the economic viability of using treated municipal wastewater (MWW) to replace the use of freshwater as makeup water to power plant cooling systems. Cost analyses are presented for a reference power plant and five different tertiary treatment scenarios to reduce the scaling tendencies of MWW. Results indicate that a 550 MW sub-critical coal fired power plant with a makeup water requirement of 29.3 ML/day has a TCC of $3.0 - 3.2 million/yr associated with the use of treated MWW for cooling. (All costs USD 2009). This translates to a freshwater conservation cost of $0.29/kL, which is considerably lower than that of dry air cooling technology, $1.5/kL, as well as the 2020 conservation cost target set by the U.S. Department of Energy, $0.74/kL. Results also show that if the available price of freshwater exceeds that of secondarytreated MWW by more than $0.13-0.14/kL, it can be economically advantageous to purchase secondary MWW and treat it for utilization in the recirculating cooling system of a thermoelectric power plant.

Walker, Michael E.; Theregowda, Ranjani B.; Safari, Iman; Abbasian, Javad; Arastoopour, Hamid; Dzombak, David A.; Hsieh, Ming-Kai; Miller, David C.

2013-10-01T23:59:59.000Z

171

Optically Interconnected MulticomputersUsing  

E-Print Network [OSTI]

Optically Interconnected MulticomputersUsing Inverted-GraphTopologies Tosuccessfullyexploitthebenefitsofopticaltechnologyinatightlycoupledmulticomputer, the architecturaldesignmust reflectboth the advantages and limitationsof optics. This article systems. Although optics have con- tributed dramatically to long-distance communi- cation and more

Krchnavek, Robert R.

172

Renewable Systems Interconnection: Executive Summary  

SciTech Connect (OSTI)

The U.S. Department of Energy launched the Renewable Systems Interconnection (RSI) study in 2007 to address the challenges to high penetrations of distributed renewable energy technologies. The RSI study consists of 14 additional reports.

Kroposki, B.; Margolis, R.; Kuswa, G.; Torres, J.; Bower, W.; Key, T.; Ton, D.

2008-02-01T23:59:59.000Z

173

Analysis of interconnect microstrip lines  

E-Print Network [OSTI]

of the return loss of the slot-coupled microstrip dipole. Section C presents two simulations of the return loss on the slot- coupled rectangular patch antenna. A. Interconnect of Microstrip Lines Several circuits with the geometry of Figure 1 were fabricated.... Experimental and Theoretical Results of the Interconnect Two circuits were designed and fabricated. Each circuit consists of two substrates as shown in Figure 9. One substrate has an open microstrip line etched in one side and an aperture etched...

Luong, Giam-Minh

1992-01-01T23:59:59.000Z

174

Renewable Generation and Interconnection to the Electrical Grid in Southern California  

Broader source: Energy.gov [DOE]

Presentation covers the topic of "Renewable Generation and Interconnection to the Electrical Grid in Southern California," given at the Spring 2010 Federal Utility Partnership Working Group (FUPWG) meeting in Providence, Rhode Island.

175

Operations, Maintenance, and Replacement 10-year plan, 1990-1999 : 1989 Utility OM&R Comparison : A Comparison of BPA (Bonneville Power Administration) and Selected Utility Transmission, Operations and Maintenance Costs.  

SciTech Connect (OSTI)

For the past several years, competing resource demands within BPA have forced the Agency to stretch Operations, Maintenance and Replacement (OM R) resources. There is a large accumulation of tasks that were not accomplished when scheduled. Maintenance and replacements and outages, due to material and equipment failure, appear to be increasing. BPA has made a strategic choice to increase its emphasis on OM R programs by implementing a multi-year, levelized OM R plan which is keyed to high system reliability. This strategy will require a long-term commitment of a moderate increase in staff and dollars allocated to these programs. In an attempt to assess the direction BPA has taken in its OM R programs, a utility comparison team was assembled in early January 1989. The team included representatives from BPA's Management Analysis, Internal Audit and Financial Management organizations, and operation and maintenance program areas. BPA selected four utilities from a field of more than 250 electric utilities in the US and Canada. The selection criteria generally pertained to size, with key factors including transformation capacity, load, gross revenue, and interstate transmission and/or marketing agreements, and their OM R programs. Information was gathered during meetings with managers and technical experts representing the four utilities. Subsequent exchanges of information also took place to verify findings. The comparison focused on: Transmission operations and maintenance program direction and emphasis; Organization, management and implementation techniques; Reliability; and Program costs. 2 figs., 21 tabs.

United States. Bonneville Power Administration.

1990-09-01T23:59:59.000Z

176

Oahu Wind Integration and Transmission Study (OWITS): Hawaiian Islands Transmission Interconnection Project  

SciTech Connect (OSTI)

This report provides an independent review included an initial evaluation of the technical configuration and capital costs of establishing an undersea cable system and examining impacts to the existing electric transmission systems as a result of interconnecting the islands.

Woodford, D.

2011-02-01T23:59:59.000Z

177

Phase 2 Report: Oahu Wind Integration and Transmission Study (OWITS); Hawaiian Islands Transmission Interconnection Project  

SciTech Connect (OSTI)

This report provides an independent review including an initial evaluation of the technical configuration and capital costs of establishing an undersea cable system and examining impacts to the existing electric transmission systems as a result of interconnecting the islands

Woodford, D.

2011-02-01T23:59:59.000Z

178

Innovative Distributed Power Grid Interconnection and Control Systems: Final Report, December 11, 2000 - August 30, 2005  

SciTech Connect (OSTI)

The contract goal was to further advance distributed generation in the marketplace by making installations more cost-effective and compatible with existing systems. This was achieved by developing innovative grid interconnection and control systems.

DePodesta, K.; Birlingmair, D.; West, R.

2006-03-01T23:59:59.000Z

179

Reliability of copper interconnects in integrated circuits  

E-Print Network [OSTI]

As dimensions shrink and current densities increase, the reliability of metal interconnects becomes a serious concern. In copper interconnects, the dominant diffusion path is along the interface between the copper and the ...

Choi, Zung-Sun

2007-01-01T23:59:59.000Z

180

Survey of Transmission Cost Allocation Methodologies for Regional Transmission Organizations  

SciTech Connect (OSTI)

The report presents transmission cost allocation methodologies for reliability transmission projects, generation interconnection, and economic transmission projects for all Regional Transmission Organizations.

Fink, S.; Porter, K.; Mudd, C.; Rogers, J.

2011-02-01T23:59:59.000Z

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


181

Sandia National Laboratories: Permitting, Inspection, and Interconnect...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Tagged with: Energy * Inspecting * Interconnection * Permitting * photovoltaic * Photovoltaics * PV * Renewable Energy * solar * Solar Energy * Solar Market Transformation *...

182

New Report Characterizes Existing Offshore Wind Grid Interconnection...  

Office of Environmental Management (EM)

New Report Characterizes Existing Offshore Wind Grid Interconnection Capabilities New Report Characterizes Existing Offshore Wind Grid Interconnection Capabilities September 3,...

183

Monolithically interconnected GaAs solar cells: A new interconnection technology for high voltage solar cell output  

SciTech Connect (OSTI)

Photovoltaic linear concentrator arrays can benefit from high performance solar cell technologies being developed at AstroPower. Specifically, these are the integration of thin GaAs solar cell and epitaxial lateral overgrowth technologies with the application of monolithically interconnected solar cell (MISC) techniques. This MISC array has several advantages which make it ideal for space concentrator systems. These are high system voltage, reliable low cost monolithically formed interconnections, design flexibility, costs that are independent of array voltage, and low power loss from shorts, opens, and impact damage. This concentrator solar cell will incorporate the benefits of light trapping by growing the device active layers over a low-cost, simple, PECVD deposited silicon/silicon dioxide Bragg reflector. The high voltage-low current output results in minimal 12R losses while properly designing the device allows for minimal shading and resistance losses. It is possible to obtain open circuit voltages as high as 67 volts/cm of solar cell length with existing technology. The projected power density for the high performance device is 5 kW/m for an AMO efficiency of 26% at 1 5X. Concentrator solar cell arrays are necessary to meet the power requirements of specific mission platforms and can supply high voltage power for electric propulsion systems. It is anticipated that the high efficiency, GaAs monolithically interconnected linear concentrator solar cell array will enjoy widespread application for space based solar power needs. Additional applications include remote man-portable or ultra-light unmanned air vehicle (UAV) power supplies where high power per area, high radiation hardness and a high bus voltage or low bus current are important. The monolithic approach has a number of inherent advantages, including reduced cost per interconnect and increased reliability of array connections. There is also a high potential for a large number of consumer products.

Dinetta, L.C.; Hannon, M.H.

1995-10-01T23:59:59.000Z

184

Interconnect  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May JunDatastreamsmmcrcalgovInstrumentsruc DocumentationP-SeriesFlickrinformation for and NovelFEG-SEM with0,

185

Double interconnection fuel cell array  

DOE Patents [OSTI]

A fuel cell array is made, containing number of tubular, elongated fuel cells which are placed next to each other in rows (A, B, C, D), where each cell contains inner electrodes and outer electrodes, with solid electrolyte between the electrodes, where the electrolyte and outer electrode are discontinuous, having two portions, and providing at least two opposed discontinuities which contain at least two oppositely opposed interconnections contacting the inner electrode, each cell having only three metallic felt electrical connectors which contact surrounding cells, where each row is electrically connected to the other. 5 figures.

Draper, R.; Zymboly, G.E.

1993-12-28T23:59:59.000Z

186

EIS-0389: Trinity Public Utility District Direct Interconnection, CA  

Broader source: Energy.gov [DOE]

This EIS analyzes DOE's decision to construct and operate proposed power transmission facilities in Trinity County, California.

187

CHP: Connecting the Gap between Markets and Utility Interconnection and  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:Year in Review: Top FiveDepartment of Energy BuildingsBuriedJuneDepartment ofJanuary 2012

188

Power Sales to Electric Utilities  

SciTech Connect (OSTI)

The Public Utilities Regulatory Policies Act (PURPA) of 1979 requires that electrical utilities interconnect with qualifying facilities and purchase electricity at a rate based upon their full avoided costs (i.e., costs of providing both capacity and energy). Qualifying facilities (QF) include solar or geothermal electric units, hydropower, municipal solid waste or biomass-fired power plants, and cogeneration projects that satisfy maximum size, fuel use, ownership, location, and/or efficiency criteria. In Washington State, neither standard power purchase prices based upon a proxy ''avoided plant'', standard contracts, or a standard offer process have been used. Instead, a variety of power purchase contracts have been negotiated by developers of qualifying facilities with investor-owned utilities, public utility districts, and municipally-owned and operated utilities. With a hydro-based system, benefits associated with resource acquisition are determined in large part by how compatible the resource is with a utility's existing generation mix. Power purchase rates are negotiated and vary according to firm energy production, guarantees, ability to schedule maintenance or downtime, rights of refusal, power plant purchase options, project start date and length of contract; front-loading or levelization provisions; and the ability of the project to provide ''demonstrated'' capacity. Legislation was also enacted which allows PURPA to work effectively. Initial laws established ownership rights and provided irrigation districts, PUDs, and municipalities with expanded enabling powers. Financial processes were streamlined and, in some cases, simplified. Finally, laws were passed which are designed to ensure that development proceeds in an environmentally acceptable manner. In retrospect, PURPA has worked well within Washington. In the state of Washington, 20 small-scale hydroelectric projects with a combined generating capacity of 77 MW, 3 solid waste-to-energy facilities with 55 MW of electrical output, 4 cogeneration projects with 34.5 MW of generating capability, and 4 wastewater treatment facility digester gas-to-energy projects with 5 MW of electrical production have come on-line (or are in the final stages of construction) since the passage of PURPA. These numbers represent only a small portion of Washington's untapped and underutilized cogeneration and renewable resource generating potentials. [DJE-2005

None

1989-02-01T23:59:59.000Z

189

Recent Development of SOFC Metallic Interconnect  

SciTech Connect (OSTI)

Interest in solid oxide fuel cells (SOFC) stems from their higher eĪciencies and lower levels of emitted pollu- tants, compared to traditional power production methods. Interconnects are a critical part in SOFC stacks, which connect cells in series electrically, and also separate air or oxygen at the cathode side from fuel at the anode side. Therefore, the requirements of interconnects are the most demanding, i:e:, to maintain high elec- trical conductivity, good stability in both reducing and oxidizing atmospheres, and close coeĪcient of thermal expansion (CTE) match and good compatibility with other SOFC ceramic components. The paper reviewed the interconnect materials, and coatings for metallic interconnect materials.

Wu JW, Liu XB

2010-04-01T23:59:59.000Z

190

NREL: Technology Deployment - Distributed Generation Interconnection...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Distributed Generation Interconnection Collaborative Become a Member DGIC members are included in quarterly informational meetings and discussions related to distributed PV...

191

Updating Interconnection Screens for PV System Integration  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Abraham Ellis, Roger Hill Sandia National Laboratories Tom Key, Kristen Nicole, Jeff Smith Electric Power Research Institute Updating Interconnection Screens for PV System...

192

Voltage Collapse SimulationVoltage Collapse Simulation (Eastern Interconnection(Eastern Interconnection  

E-Print Network [OSTI]

PSERC Voltage Collapse SimulationVoltage Collapse Simulation (Eastern Interconnection(Eastern Interconnection Scenario)Scenario) Simulation Prepared by Dennis J. RaySimulation Prepared by Dennis J. Ray Interconnection based on a series of generator and line outages. An actual voltage collapse may not occur due

193

Pricing in Information-Centric Network Interconnection  

E-Print Network [OSTI]

--ICN interconnection, economic incentives, col- laborative caching, non-cooperative games, network pricing. I economic incentives for caching and sharing content in ICN interconnection. For example, an ISP provider Engineering Department, ETH Zurich, Switzerland Abstract--We propose a pricing model to study the economic

Paris-Sud XI, Universitť de

194

FPGA Interconnect Delay Fault Testing Erik Chmelar  

E-Print Network [OSTI]

A satisfactory FPGA testing method meets several crite- ria. First, the routing resources must be explicitlyFPGA Interconnect Delay Fault Testing Erik Chmelar Center for Reliable Computing Stanford is a scalable manufactur- ing test method for all SRAM-based FPGAs, able to detect multiple interconnect delay

Stanford University

195

EPRI PEAC Corp.: Certification Model Program and Interconnection Agreement Tools  

SciTech Connect (OSTI)

Summarizes the work of EPRI PEAC Corp., under contract to DOE's Distribution and Interconnection R&D, to develop a certification model program and interconnection agreement tools to support the interconnection of distributed energy resources.

Not Available

2003-10-01T23:59:59.000Z

196

Electrically long vertical interconnects for microwave circuits and antennas  

E-Print Network [OSTI]

Interconnect. . Microstrip Orientation for the Coaxial Interconnect. . . The Microstrip to Coax Transition in Fidelity Original Transition Model New Transition Model 450 mil Stub Transition Response, Transition Capacitance Using the Stub Method. 10... Transition Response (1, =20 mils, w, =60 mila) . . . . 1000 mil Coaxial Line Response . . . The Full Coaxial Interconnect in Fidelity. . Coaxial Interconnect Items in Fidelity Final Simulated Coaxial Interconnect Response The Coaxial Interconnect Test...

Coutant, Matthew Richard

2000-01-01T23:59:59.000Z

197

A G LO BA L P OW E R TECHNOLO GIES CO M PA N Y SolarTieTM Grid Interconnection Solution  

E-Print Network [OSTI]

G f¬∑ Shipments to date sufficient to power 10 GW of wind power SWind Plant Interconnection Solutions's Wind-Generated Electricity "Powered by AMSC¬ģ" Wind Turbine Designs, Controls & Converters ¬∑ Relied upon utilized at more than 70 wind plants worldwide ¬∑ Shipments to date sufficient to allow interconnection 4 p

Homes, Christopher C.

198

Evaluation of a Functional Interconnect System for SOFC's  

SciTech Connect (OSTI)

The overall objective of this project was to validate the concept and application of a functional interconnect, based on a ferritic stainless steel, for a solid oxide fuel cell through manufacturing trials, laboratory testing, and field experience. The materials of construction and their surfaces were to be optimized for the particular service conditions and include low-cost ferritic stainless steels, novel postprocess treatments, and third-party coatings. This work aimed to optimize specific aspects of substrate alloy chemistry and to study the effects of long-term exposures on resistive oxide film structure and chemistry, interaction with applied surface coatings, and effectiveness of novel surface treatments.

Matthew Bender; James Rakowski

2010-12-31T23:59:59.000Z

199

The regulation of internet interconnection : assessing network market power  

E-Print Network [OSTI]

Interconnection agreements in the telecommunications industry have always been constrained by regulation. Internet interconnection has not received the same level of scrutiny. Recent debates regarding proposed mergers, ...

Maida, Elisabeth M. (Elisabeth Marigo)

2013-01-01T23:59:59.000Z

200

Renewable Generation and Interconnection to the Electrical Grid...  

Broader source: Energy.gov (indexed) [DOE]

Generation and Interconnection to the Electrical Grid in Southern California Renewable Generation and Interconnection to the Electrical Grid in Southern California Presentation...

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


201

Electricity prices in a competitive environment: Marginal cost pricing of generation services and financial status of electric utilities. A preliminary analysis through 2015  

SciTech Connect (OSTI)

The emergence of competitive markets for electricity generation services is changing the way that electricity is and will be priced in the United States. This report presents the results of an analysis that focuses on two questions: (1) How are prices for competitive generation services likely to differ from regulated prices if competitive prices are based on marginal costs rather than regulated {open_quotes}cost-of-service{close_quotes} pricing? (2) What impacts will the competitive pricing of generation services (based on marginal costs) have on electricity consumption patterns, production costs, and the financial integrity patterns, production costs, and the financial integrity of electricity suppliers? This study is not intended to be a cost-benefit analysis of wholesale or retail competition, nor does this report include an analysis of the macroeconomic impacts of competitive electricity prices.

NONE

1997-08-01T23:59:59.000Z

202

Changing photovoltaic array interconnections to reduce mismatch losses: a case study  

E-Print Network [OSTI]

) ­ Grenoble, France **Grupo de Investigacion y Desarollo en Energia Solar y Automatica (IDEA) ­ Jaén, Spain a wide variety of plants ranging from utility-sized solar trackers to residential building-integrated PV, resulting in lower energy production yields. The traditional series-parallel interconnection scheme of solar

Boyer, Edmond

203

Optically Interconnected Data Center Architecture for Bandwidth Intensive Energy Efficient Networking  

E-Print Network [OSTI]

Optically Interconnected Data Center Architecture for Bandwidth Intensive Energy Efficient) 854 2900, e-mail: howard@ee.columbia.edu ABSTRACT The relentless rise of data-intensive cloud will either be prohibitively costly, overly complex, or result in unsustainable energy requirements. Network

Bergman, Keren

204

WHAT IS A NETWORK? (Gas and Electricity) A complex, interconnected group or  

E-Print Network [OSTI]

WHAT IS A NETWORK? (Gas and Electricity) A complex, interconnected group or system Electricity and Gas: A system used to distribute electricity and gas around the world/certain area, by compromising to minimise costs and generate the most electricity and gas as possible, which maximises profits

Wright, Francis

205

Carbon nanotube interconnects for IC chips  

E-Print Network [OSTI]

Carbon nanotubes (CNTs) have been investigated as candidate materials to replace or augment the existing copper-based technologies as interconnects for Integrated Circuit (IC) chips. Being ballistic conductors, CNTs are ...

Anwar Ali, Hashina Parveen

2006-01-01T23:59:59.000Z

206

Carbon nanotube synthesis for integrated circuit interconnects  

E-Print Network [OSTI]

Based on their properties, carbon nanotubes (CNTs) have been identified as ideal replacements for copper interconnects in integrated circuits given their higher current density, inertness, and higher resistance to ...

Nessim, Gilbert Daniel

2009-01-01T23:59:59.000Z

207

NREL Variability Analysis for the Western Interconnect (Presentation)  

SciTech Connect (OSTI)

This presentation investigates the effects of several Energy Imbalance Markets implementations in the Western Interconnect.

Milligan, M.; Kirby, B.; King, J.

2011-07-01T23:59:59.000Z

208

Accelerating Fatigue Testing for Cu Ribbon Interconnects (Presentation)  

SciTech Connect (OSTI)

This presentation describes fatigue experiments and discusses dynamic mechanical loading for Cu ribbon interconnects.

Bosco, N.; Silverman, T.; Wohlgemuth , J.; Kurtz, S.; Inoue, M.; Sakurai, K.; Shioda, T.; Zenkoh, H.; Miyashita, M.; Tadanori, T.; Suzuki, S.

2013-05-01T23:59:59.000Z

209

Mandatory Photovoltaic System Cost Analysis  

Broader source: Energy.gov [DOE]

The Arizona Corporation Commission requires electric utilities to conduct a cost/benefit analysis to compare the cost of line extension with the cost of installing a stand-alone photovoltaic (PV)...

210

Development of a Method Using BIM Technology to Determine the Utility Bill and Total Cost of Ownership of a Single-family Home  

E-Print Network [OSTI]

they will or will not benefit from BIM. A ROI can be found by using a formula to establish the first year ROI that includes particular variables, such as the proposed systems cost, labor costs, the training time, expected percentage loss, and the percentage expected to gain... and labor. I used the wall areas to compute quantities, and made educated estimates. The RSMeans books were very good sources for all the building elements in both homes. Within the books they broke down the cost of materials and labor and explained...

McGarity, Ashley

2010-07-14T23:59:59.000Z

211

Vehicle Technologies Office Merit Review 2014: Utilization of UV or EB Curing Technology to Significantly Reduce Costs and VOCs in the Manufacture of Lithium-Ion Battery Electrodes  

Broader source: Energy.gov [DOE]

Presentation given by Miltec UV International at 2014 DOE Hydrogen and Fuel Cells Program and Vehicle Technologies Office Annual Merit Review and Peer Evaluation Meeting about the utilization of UV...

212

Residential, Commercial, and Utility-Scale Photovoltaic (PV) System Prices in the United States: Current Drivers and Cost-Reduction Opportunities  

SciTech Connect (OSTI)

The price of photovoltaic (PV) systems in the United States (i.e., the cost to the system owner) has dropped precipitously in recent years, led by substantial reductions in global PV module prices. However, system cost reductions are not necessarily realized or realized in a timely manner by many customers. Many reasons exist for the apparent disconnects between installation costs, component prices, and system prices; most notable is the impact of fair market value considerations on system prices. To guide policy and research and development strategy decisions, it is necessary to develop a granular perspective on the factors that underlie PV system prices and to eliminate subjective pricing parameters. This report's analysis of the overnight capital costs (cash purchase) paid for PV systems attempts to establish an objective methodology that most closely approximates the book value of PV system assets.

Goodrich, A.; James, T.; Woodhouse, M.

2012-02-01T23:59:59.000Z

213

COMM-OPINION-ORDER, 75 FERC 61,208, Promoting Wholesale Competition Through Open Access Non-discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and  

E-Print Network [OSTI]

COMM-OPINION-ORDER, 75 FERC ¶61,208, Promoting Wholesale Competition Through Open Access Non Wholesale Competition Through Open Access Non-discriminatory Transmission Services by Public Utilities-7-001 [61,687] [¶61,208] Promoting Wholesale Competition Through Open Access Non-discriminatory Transmission

Laughlin, Robert B.

214

IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 19, NO. 1, MARCH 2004 151 Production Cost Analysis of Dispersed Generation  

E-Print Network [OSTI]

IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 19, NO. 1, MARCH 2004 151 Production Cost Analysis the appli- cability and production cost analysis of dispersed generation (DG) resources in a transmission economics, production costing, transmission-constrained interconnected system. I. INTRODUCTION

Gross, George

215

InterconnectFabric InterconnectFabric SingleBuilding Multi-Building  

E-Print Network [OSTI]

Interconnects in Datacenter Networks Opportunities and Challenges for WDM Hong Liu, Cedric F. Lam, and Chris We review the growing need for optical interconnect bandwidth in datacenter networks growth inside datacenter networks. INTRODUCTION The rapid growth of Internet and cloud computing

Tomkins, Andrew

216

Revised Record of Decision for the Electrical Interconnection of the Summit/Westward Project  

SciTech Connect (OSTI)

The Bonneville Power Administration (BPA) has decided to amend its July 25, 2003, Record of Decision (ROD) regarding the proposed Summit/Westward Project (Project) to offer contract terms for an optional interconnection of this Project into the Federal Columbia River Transmission System (FCRTS). Under this optional interconnection plan, BPA would integrate electric power from the Project into the FCRTS at a point adjacent to Clatskanie People's Utility District (CPUD) existing Wauna Substation. In order to deliver power to this location, CPUD would develop a new substation (Bradbury Substation) at a site near the Project and a new 230-kV transmission line from there to CPUD's Wauna Substation, which is already connected to the FCRTS. As part of this revised decision, BPA will facilitate CPUD development of the Bradbury-Wauna transmission line by allowing joint use of BPA right-of-way. This will involve reconstructing a section of BPA's 115-kV Allston-Astoria No. 1 transmission line from single-circuit H-frame wood-pole design to double-circuit single metal pole design. Terms of BPA participation in CPUD's development of the Bradbury-Wauna transmission line will be documented in a Construction Agreement. This optional interconnection plan is in addition to BPA's previous offer for interconnection of the Project at BPA's Allston Substation, as documented in the July 25, 2003, ROD. As with the initial interconnection plan, the decision to offer terms to interconnect the Project through the optional interconnection plan is consistent with BPA's Business Plan Final Environmental Impact Statement (BP EIS) (DOE/EIS-0183, June 1995), and the Business Plan Record of Decision (BP ROD, August 1995). This decision thus is similarly tiered to the Business Plan ROD.

N /A

2004-10-21T23:59:59.000Z

217

Utility spot pricing study : Wisconsin  

E-Print Network [OSTI]

Spot pricing covers a range of electric utility pricing structures which relate the marginal costs of electric generation to the prices seen by utility customers. At the shortest time frames prices change every five ...

Caramanis, Michael C.

1982-01-01T23:59:59.000Z

218

Factors relevant to utility integration of intermittent renewable technologies  

SciTech Connect (OSTI)

This study assesses factors that utilities must address when they integrate intermittent renewable technologies into their power-supply systems; it also reviews the literature in this area and has a bibliography containing more than 350 listings. Three topics are covered: (1) interface (hardware and design-related interconnection), (2) operability/stability, and (3) planning. This study finds that several commonly held perceptions regarding integration of intermittent renewable energy technologies are not valid. Among findings of the study are the following: (1) hardware and system design advances have eliminated most concerns about interface; (2) cost penalties have not occurred at low to moderate penetration levels (and high levels are feasible); and (3) intermittent renewable energy technologies can have capacity values. Obstacles still interfering with intermittent renewable technologies are also identified.

Wan, Yih-huei; Parsons, B.K.

1993-08-01T23:59:59.000Z

219

Power Plant Cycling Costs  

SciTech Connect (OSTI)

This report provides a detailed review of the most up to date data available on power plant cycling costs. The primary objective of this report is to increase awareness of power plant cycling cost, the use of these costs in renewable integration studies and to stimulate debate between policymakers, system dispatchers, plant personnel and power utilities.

Kumar, N.; Besuner, P.; Lefton, S.; Agan, D.; Hilleman, D.

2012-07-01T23:59:59.000Z

220

Phase 1 - Evaluation of a Functional Interconnect System for Solid Oxide Fuel Cells  

SciTech Connect (OSTI)

This project is focused on evaluating the suitability of materials and complex multi-materials systems for use as solid oxide fuel cell interconnects. ATI Allegheny Ludlum has generated promising results for interconnect materials which incorporate modified surfaces. Methods for producing these surfaces include cladding, which permits the use of novel materials, and modifications via unique thermomechanical processing, which allows for the modification of materials chemistry. The University of Pittsburgh is assisting in this effort by providing use of their in-place facilities for dual atmosphere testing and ASR measurements, along with substantial work to characterize post-exposure specimens. Carnegie Mellon is testing interconnects for chromia scale spallation resistance using macro-scale and nano-scale indentation tests. Chromia spallation can increase electrical resistance to unacceptable levels and interconnect systems must be developed that will not experience spallation within 40,000 hours at operating temperatures. Spallation is one of three interconnect failure mechanisms, the others being excessive growth of the chromia scale (increasing electrical resistance) and scale evaporation (which can poison the cathode). The goal of indentation fracture testing at Carnegie Mellon is to accelerate the evaluation of new interconnect systems (by inducing spalls at after short exposure times) and to use fracture mechanics to understand mechanisms leading to premature interconnect failure by spallation. Tests include bare alloys from ATI and coated systems from DOE Laboratories and industrial partners, using ATI alloy substrates. West Virginia University is working towards developing a cost-effective material for use as a contact material in the cathode chamber of the SOFC. Currently materials such as platinum are well suited for this purpose, but are cost-prohibitive. For the solid-oxide fuel cell to become a commercial reality it is imperative that lower cost components be developed. Based on the results obtained to date, it appears that sterling silver could be an inexpensive, dependable candidate for use as a contacting material in the cathode chamber of the solid-oxide fuel cell. Although data regarding pure silver samples show a lower rate of thickness reduction, the much lower cost of sterling silver makes it an attractive alternative for use in SOFC operation.

James M. Rakowski

2006-09-30T23:59:59.000Z

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


221

On Irregular Interconnect Fabrics for Self-Assembled Nanoscale Electronics  

E-Print Network [OSTI]

Nanoscale electronics and novel fabrication technologies bear unique opportunities for self-assembling multi-billion component systems in a largely random manner, which would likely lower fabrication costs significantly compared to a definite ad hoc assembly. It has been shown that communication networks with the small-world property have major advantages in terms of transport characteristics and robustness over regularly connected systems. In this paper we pragmatically investigate the properties of an irregular, abstract, yet physically plausible small-world interconnect fabric that is inspired by modern network-on-chip paradigms. We vary the framework's key parameters, such as the connectivity, the number of switch blocks, the number of virtual channels, the routing strategy, the distribution of long- and short-range connections, and measure the network's transport characteristics and robustness against failures. We further explore the ability and efficiency to solve two simple toy problems, the synchronization and the density classification task. The results confirm that (1) computation in irregular assemblies is a promising new computing paradigm for nanoscale electronics and (2) that small-world interconnect fabrics have major advantages over local CA-like topologies. Finally, the results will help to make important design decisions for building self-assembled electronics in a largely random manner.

Christof Teuscher

2006-06-22T23:59:59.000Z

222

Using Interconnected Texts to Highlight Culture in the Foreign Language Classroom  

E-Print Network [OSTI]

in analyzing this interconnectivity, teachers should deviseon the nature of interconnectivity in their everydaywill look for the interconnectivity of texts in other

Smith, Maya

2013-01-01T23:59:59.000Z

223

Transmission Cost Allocation Methodologies for Regional Transmission Organizations  

SciTech Connect (OSTI)

This report describes transmission cost allocation methodologies for transmission projects developed to maintain or enhance reliability, to interconnect new generators, or to access new resources and enhance competitive bulk power markets, otherwise known as economic transmission projects.

Fink, S.; Rogers, J.; Porter, K.

2010-07-01T23:59:59.000Z

224

Original Paper Fully interconnected, linear control  

E-Print Network [OSTI]

Original Paper Fully interconnected, linear control for limit cycle walking Joseph H Solomon1 and simple control methodologies for these models (Collins & Ruina, 2005; Hobbelen & Wisse, 2008a, 2008b. Corresponding author: Joseph H. Solomon, Northwestern University, Department of Mechanical Engineering, 2145

Hartmann, Mitra J. Z.

225

Asynchronous intrusion recovery for interconnected web services  

E-Print Network [OSTI]

Asynchronous intrusion recovery for interconnected web services Ramesh Chandra, Taesoo Kim, and tracking down and recovering from such an attack re- quires significant manual effort. Web services for such web services. Aire addresses several challenges, such as propagating repair across services when some

Sabatini, David M.

226

QCD Interconnection Studies at Linear Colliders  

E-Print Network [OSTI]

Heavy objects like the W, Z and t are short-lived compared with typical hadronization times. When pairs of such particles are produced, the subsequent hadronic decay systems may therefore become interconnected. We study such potential effects at Linear Collider energies.

Valery A. Khoze; TorbjŲrn SjŲstrand

1999-12-10T23:59:59.000Z

227

subcollector Schottky collector contact & interconnect metals  

E-Print Network [OSTI]

base collector depletion layer subcollector ohmic metal (a) base collector depletion layer Schottky metal base emitter collector collector We emitter base emitter emitter We Wc Wc (b) Schottky collector contact & interconnect metals Emitter & collector Ohmics undoped collector depletion layer base N

Rodwell, Mark J. W.

228

Fast high-order variation-aware IC interconnect analysis  

E-Print Network [OSTI]

Interconnects constitute a dominant source of circuit delay for modern chip designs. The variations of critical dimensions in modern VLSI technologies lead to variability in interconnect performance that must be fully accounted for in timing...

Ye, Xiaoji

2009-05-15T23:59:59.000Z

229

High temperature solid electrolyte fuel cell configurations and interconnections  

DOE Patents [OSTI]

High temperature fuel cell configurations and interconnections are made including annular cells having a solid electrolyte sandwiched between thin film electrodes. The cells are electrically interconnected along an elongated axial outer surface.

Isenberg, Arnold O. (Forest Hills, PA)

1984-01-01T23:59:59.000Z

230

Probing Porosity and Pore Interconnectivity in Crystalline Mesoporous...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Porosity and Pore Interconnectivity in Crystalline Mesoporous TiO2 Using Hyperpolarized Xe-129 NMR. Probing Porosity and Pore Interconnectivity in Crystalline Mesoporous TiO2 Using...

231

VLSI Interconnect Optimization Considering Non-uniform Metal Stacks  

E-Print Network [OSTI]

With the advances in process technology, comes the domination of interconnect in the overall propagation delay in modern VLSI designs. Hence, interconnect synthesis techniques, such as buffer insertion, wire sizing and layer assignment play critical...

Tsai, Jung-Tai

2013-08-01T23:59:59.000Z

232

InterConnections A Report on Interdisciplinary Computing at the  

E-Print Network [OSTI]

InterConnections A Report on Interdisciplinary Computing at the University of Maryland Institute be found on pages 6 and 7 of this issue of InterConnections. ; continued on Page 2 Science/UMIACS); (2) use

Gruner, Daniel S.

233

InterConnections A Report on Interdisciplinary Computing at the  

E-Print Network [OSTI]

InterConnections A Report on Interdisciplinary Computing at the University of Maryland Institute BY BEN SHNEIDERMANPHOTO BY BEN SHNEIDERMAN #12;2 InterConnections During the past six months, a number

Gruner, Daniel S.

234

STABILITY ANALYSIS OF INTERCONNECTED POWER SYSTEMS COUPLED WITH MARKET DYNAMICS  

E-Print Network [OSTI]

STABILITY ANALYSIS OF INTERCONNECTED POWER SYSTEMS COUPLED WITH MARKET DYNAMICS F.L. Alvarado1 J of generators and network interconnections. This paper examines questions of stability in such coupled systems

235

Solar Energy to Benefit from New FERC Interconnection Procedures...  

Energy Savers [EERE]

Solar Energy to Benefit from New FERC Interconnection Procedures Solar Energy to Benefit from New FERC Interconnection Procedures October 30, 2014 - 5:15pm Addthis As a major win...

236

Interconnected hydro-thermal systems Models, methods, and applications  

E-Print Network [OSTI]

Interconnected hydro-thermal systems Models, methods, and applications Magnus Hindsberger Kgs. Lyngby 2003 IMM-PHD-2003-112 Interconnected hydro-thermalsystems #12;Technical University of Denmark 45882673 reception@imm.dtu.dk www.imm.dtu.dk IMM-PHD-2003-112 ISSN 0909-3192 #12;Interconnected hydro

237

COLLEGE OF COMPUTER, MATHEMATICAL AND PHYSICAL SCIENCES InterConnections  

E-Print Network [OSTI]

COLLEGE OF COMPUTER, MATHEMATICAL AND PHYSICAL SCIENCES InterConnections Contents 2 Director for large amounts of data FALL/WINTER 2007 continued on page 4... InterConnections is published. For her work on entity Lise Getoor: From Data to Information Lise Getoor #12;INTERCONNECTIONS Fall

Gruner, Daniel S.

238

COLLEGE OF COMPUTER, MATHEMATICAL AND PHYSICAL SCIENCES InterConnections  

E-Print Network [OSTI]

COLLEGE OF COMPUTER, MATHEMATICAL AND PHYSICAL SCIENCES InterConnections Contents 2 Director Neil Spring: Mapping the Internet 12 Ramani Duriaswami: Processing Sound AUGUST 2008 InterConnections research- ers to gauge similarities and differences continued on page 2. #12;INTERCONNECTIONS AUGUST 2008

Gruner, Daniel S.

239

InterConnections A Report on Interdisciplinary Computing at the  

E-Print Network [OSTI]

InterConnections A Report on Interdisciplinary Computing at the University of Maryland Institute of InterConnections. The Center was funded two years ago through the campus enhancement initiative #12;2 InterConnections Three events took place during the past five months, each of which will have

Gruner, Daniel S.

240

State-Level Comparison of Processes and Timelines for Distributed Photovoltaic Interconnection in the United States  

SciTech Connect (OSTI)

This report presents results from an analysis of distributed photovoltaic (PV) interconnection and deployment processes in the United States. Using data from more than 30,000 residential (up to 10 kilowatts) and small commercial (10-50 kilowatts) PV systems, installed from 2012 to 2014, we assess the range in project completion timelines nationally (across 87 utilities in 16 states) and in five states with active solar markets (Arizona, California, New Jersey, New York, and Colorado).

Ardani, K.; Davidson, C.; Margolis, R.; Nobler, E.

2015-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


241

Viscosity Solutions of Systems of PDEs with Interconnected Obstacles and Switching Problem  

SciTech Connect (OSTI)

This paper deals with existence and uniqueness of a solution in viscosity sense, for a system of m variational partial differential inequalities with inter-connected obstacles. A particular case is the Hamilton-Jacobi-Bellmann system of the Markovian stochastic optimal m-states switching problem. The switching cost functions depend on (t,x). The main tool is the notion of systems of reflected backward stochastic differential equations with oblique reflection.

Hamadene, S., E-mail: hamadene@univ-lemans.fr; Morlais, M. A., E-mail: Marie_Amelie.Morlais@univ-lemans.fr [Universite du Maine, LMM (France)

2013-04-15T23:59:59.000Z

242

Design, analysis and simulation study of a Scalable all-Optical Interconnection Network (SCOPIN) for multiprocessing systems  

E-Print Network [OSTI]

and flexible all-optical single-hop interconnection network, called Scalable Optical Interconnection Network (SCOPIN)....

Okorafor, Ekpe Apia

2002-01-01T23:59:59.000Z

243

Release Resistant Electrical Interconnections For Mems Devices  

DOE Patents [OSTI]

A release resistant electrical interconnection comprising a gold-based electrical conductor compression bonded directly to a highly-doped polysilicon bonding pad in a MEMS, IMEMS, or MOEMS device, without using any intermediate layers of aluminum, titanium, solder, or conductive adhesive disposed in-between the conductor and polysilicon pad. After the initial compression bond has been formed, subsequent heat treatment of the joint above 363 C creates a liquid eutectic phase at the bondline comprising gold plus approximately 3 wt % silicon, which, upon re-solidification, significantly improves the bond strength by reforming and enhancing the initial bond. This type of electrical interconnection is resistant to chemical attack from acids used for releasing MEMS elements (HF, HCL), thereby enabling the use of a "package-first, release-second" sequence for fabricating MEMS devices. Likewise, the bond strength of an Au--Ge compression bond may be increased by forming a transient liquid eutectic phase comprising Au-12 wt % Ge.

Peterson, Kenneth A. (Albuquerque, NM); Garrett, Stephen E. (Albuquerque, NM); Reber, Cathleen A. (Corrales, NM)

2005-02-22T23:59:59.000Z

244

Interconnection of bundled solid oxide fuel cells  

DOE Patents [OSTI]

A system and method for electrically interconnecting a plurality of fuel cells to provide dense packing of the fuel cells. Each one of the plurality of fuel cells has a plurality of discrete electrical connection points along an outer surface. Electrical connections are made directly between the discrete electrical connection points of adjacent fuel cells so that the fuel cells can be packed more densely. Fuel cells have at least one outer electrode and at least one discrete interconnection to an inner electrode, wherein the outer electrode is one of a cathode and and anode and wherein the inner electrode is the other of the cathode and the anode. In tubular solid oxide fuel cells the discrete electrical connection points are spaced along the length of the fuel cell.

Brown, Michael; Bessette, II, Norman F; Litka, Anthony F; Schmidt, Douglas S

2014-01-14T23:59:59.000Z

245

Selection and Evaluation of Heat-Resistant Alloys for Planar SOFC Interconnect Applications  

SciTech Connect (OSTI)

Over the past several years, the steady reduction in SOFC operating temperatures to the intermediate range of 700~850oC [1] has made it feasible for lanthanum chromite to be supplanted by metals or alloys as the interconnect materials. Compared to doped lanthanum chromite, metals or alloys offer significantly lower raw material and fabrication costs. However, to be a durable and reliable, a metal or alloy has to satisfy several functional requirements specific to the interconnect under SOFC operating conditions. Specifically, the interconnect metal or alloy should possess the following properties: (i) Good surface stability (resistance to oxidation, hot corrosion, and carburization) in both cathodic (air) and anodic (fuel) atmospheres; (ii) Thermal expansion matching to the ceramic PEN (positive cathode-electrolyte-negative anode) and seal materials (as least for a rigid seal design); (iii) High electrical conductivity through both the bulk material and in-situ formed oxide scales; (iv) Bulk and interfacial thermal mechanical reliability and durability at the operating temperature; (v) Compatibility with other materials in contact with interconnects such as seals and electrical contact materials.

Yang, Z Gary; Weil, K. Scott; Paxton, Dean M.; Stevenson, Jeffry W.

2002-11-21T23:59:59.000Z

246

Photovoltaics: New opportunities for utilities  

SciTech Connect (OSTI)

This publication presents information on photovoltaics. The following topics are discussed: Residential Photovoltaics: The New England Experience Builds Confidence in PV; Austin's 300-kW Photovoltaic Power Station: Evaluating the Breakeven Costs; Residential Photovoltaics: The Lessons Learned; Photovoltaics for Electric Utility Use; Least-Cost Planning: The Environmental Link; Photovoltaics in the Distribution System; Photovoltaic Systems for the Rural Consumer; The Issues of Utility-Intertied Photovoltaics; and Photovoltaics for Large-Scale Use: Costs Ready to Drop Again.

Not Available

1991-07-01T23:59:59.000Z

247

Federal Utility Partnership Working Group  

Broader source: Energy.gov [DOE]

The Federal Utility Partnership Working Group (FUPWG) establishes partnerships and facilitates communications among Federal agencies, utilities, and energy service companies. The group develops strategies to implement cost-effective energy efficiency and water conservation projects through utility incentive programs at Federal sites.

248

Startup Costs  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

This chapter discusses startup costs for construction and environmental projects, and estimating guidance for startup costs.

1997-03-28T23:59:59.000Z

249

Updating Interconnection Screens for PV System Integration  

SciTech Connect (OSTI)

This white paper evaluates the origins and usefulness of the capacity penetration screen, offer short-term solutions which could effectively allow fast-track interconnection to many PV system applications, and considers longer-term solutions for increasing PV deployment levels in a safe and reliable manner while reducing or eliminating the emphasis on the penetration screen. Short-term and longer-term alternatives approaches are offered as examples; however, specific modifications to screening procedures should be discussed with stakeholders and must ultimately be adopted by state and federal regulatory bodies.

Coddington, M.; Mather, B.; Kroposki, B.; Lynn, K.; Razon, A.; Ellis, A.; Hill, R.; Key, T.; Nicole, K.; Smith, J.

2012-02-01T23:59:59.000Z

250

Interconnecting gold islands with DNA origami  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May JunDatastreamsmmcrcalgovInstrumentsruc DocumentationP-SeriesFlickrinformation for and NovelFEG-SEM with0,Interconnecting gold islands

251

Environmental Regulation Impacts on Eastern Interconnection Performance  

SciTech Connect (OSTI)

In the United States, recent environmental regulations will likely result in the removal of nearly 30 GW of oil and coal-fired generation from the power grid, mostly in the Eastern Interconnection (EI). The effects of this transition on voltage stability and transmission line flows have previously not been studied from a system-wide perspective. This report discusses the results of power flow studies designed to simulate the evolution of the EI over the next few years as traditional generation sources are replaced with environmentally friendlier ones such as natural gas and wind.

Markham, Penn N [ORNL; Liu, Yilu [ORNL; Young II, Marcus Aaron [ORNL

2013-07-01T23:59:59.000Z

252

A novel design for monolithic interconnected modules (MIMs) for thermophotovoltaic (TPV) power conversion  

SciTech Connect (OSTI)

The design for the fabrication of Monolithic Interconnected Modules (MIMs) for thermophotovoltaic (TPV) power conversion described in this paper utilizes a novel, interdigitated contacting scheme that increases the flexibility in the size of the component cells and hence the output current and voltage of the module. This flexibility is gained at the expense of only minimally increased grid obscuration. Because the design uses the grid fingers of the component cells as the interconnect structure, the area of the device used for this purpose becomes negligible. In this paper the authors report on the specifics of the design as well as issues related to the fabrication of the modules. Preliminary performance data for representative modules also are offered.

Ward, J.S.; Duda, A.; Wanlass, M.W. [National Renewable Energy Lab., Golden, CO (United States)] [and others

1997-06-01T23:59:59.000Z

253

Flip chip electrical interconnection by selective electroplating and bonding  

E-Print Network [OSTI]

on a glass substrate made of 500/2000 A¬į of Cr/Au with 3150 lm in length and 10 lm in width. Two silicon. The interconnection chip has 102 Cr/Au interconnection lines with 3150 lm in length and 10 lm in width. The bonding pads on the ends of the interconnection lines are 40 lm by 40 lm. A 0.8 lm thick layer of aluminum

Lin, Liwei

254

Impact of High Solar Penetration in the Western Interconnection  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Impact of High Solar Penetration in the Western Interconnection Debra Lew National Renewable Energy Laboratory Nicholas Miller, Kara Clark, Gary Jordan, and Zhi Gao GE Energy...

255

Response from PJM Interconnection LLC and Pepco to Department...  

Broader source: Energy.gov (indexed) [DOE]

PJM Interconnection LLC and Pepco to Department of Energy Request for Information Concerning the Potential Need for Potomac River Station Generation Response from PJM...

256

Pepco and PJM Interconnection Comments on District of Columbia...  

Broader source: Energy.gov (indexed) [DOE]

Pepco and PJM Interconnection Comments on District of Columbia Public Service Commission, Docket No. EO-05-01 Comments and Answer to Requests for Rehearing Pepco and PJM...

257

Microgrid V2G Charging Station Interconnection Testing (Presentation)  

SciTech Connect (OSTI)

This presentation by Mike Simpson of the National Renewable Energy Laboratory (NREL) describes NREL's microgrid vehicle-to-grid charging station interconnection testing.

Simpson, M.

2013-07-01T23:59:59.000Z

258

Optimization of solid oxide fuel cell interconnect design.  

E-Print Network [OSTI]

??Performance of solid oxide fuel cells (SOFC) is dependent of a set of complex physical and chemical processes occurring simultaneously. Interconnect for SOFC is importantÖ (more)

Pulagam, Krishna C.

2009-01-01T23:59:59.000Z

259

Proposed rule for Interconnection for Wind Energy and Other Alternativ...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

REGULATORY COMMISSION 18 CFR Part 35 (Docket No. RM05-4-000) Interconnection for Wind Energy and Other Alternative Technologies (January 24, 2005) AGENCY: Federal Energy...

260

Dynamic Simulation Studies of the Frequency Response of the Three U.S. Interconnections with Increased Wind Generation  

SciTech Connect (OSTI)

Utility Systems Efficiencies, Inc. was tasked by Lawrence Berkeley National Laboratory (LBNL) to conduct dynamic simulation studies of the three U.S. interconnections (Eastern, Western, and Texas). The simulations were prepared in support of LBNL's project for the Federal Energy Regulatory Commission to study frequency-response-related issues that must be addressed to operate the power system reliably with large amounts of variable renewable generation. The objective of the simulation studies of each interconnection was to assess the effects of different amounts of wind generation on frequency behavior of each interconnection following a sudden loss of generation. The scenarios created to study these effects considered an operating circumstance in which system load is at or close to its minimum. The event studied was the sudden loss of the largest amount of generation recorded within each interconnection. The simulations calculated the impact of this event on interconnection frequency for three levels of wind generation. In addition to varying the amount of wind generation, the simulations varied the amount of operating reserves between a high level representative of current operating practices and a low level representative of the minimum required by present operating rules.

Mackin, Peter; Daschmans, R.; Williams, B.; Haney, B.; Hung, R.; Ellis, J.

2010-12-20T23:59:59.000Z

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


261

Tribal Utility Feasibility Study  

SciTech Connect (OSTI)

The Schatz Energy Research Center (SERC) assisted the Yurok Tribe in investigating the feasibility of creating a permanent energy services program for the Tribe. The original purpose of the DOE grant that funded this project was to determine the feasibility of creating a full-blown Yurok Tribal electric utility to buy and sell electric power and own and maintain all electric power infrastructure on the Reservation. The original project consultant found this opportunity to be infeasible for the Tribe. When SERC took over as project consultant, we took a different approach. We explored opportunities for the Tribe to develop its own renewable energy resources for use on the Reservation and/or off-Reservation sales as a means of generating revenue for the Tribe. We also looked at ways the Tribe can provide energy services to its members and how to fund such efforts. We identified opportunities for the development of renewable energy resources and energy services on the Yurok Reservation that fall into five basic categories: ē Demand-side management Ė This refers to efforts to reduce energy use through energy efficiency and conservation measures. ē Off-grid, facility and household scale renewable energy systems Ė These systems can provide electricity to individual homes and Tribal facilities in areas of the Reservation that do not currently have access to the electric utility grid. ē Village scale, micro-grid renewable energy systems - These are larger scale systems that can provide electricity to interconnected groups of homes and Tribal facilities in areas of the Reservation that do not have access to the conventional electric grid. This will require the development of miniature electric grids to serve these interconnected facilities. ē Medium to large scale renewable energy development for sale to the grid Ė In areas where viable renewable energy resources exist and there is access to the conventional electric utility grid, these resources can be developed and sold to the wholesale electricity market. ē Facility scale, net metered renewable energy systems Ė These are renewable energy systems that provide power to individual households or facilities that are connected to conventional electric utility grid.

Engel, R. A.; Zoellick, J. J.

2007-06-30T23:59:59.000Z

262

Evaluating Utility Costs from Cogeneration Facilities  

E-Print Network [OSTI]

)] / ~b [Btu/lb] (7) The additional feedwater flow (6M ) to generate fw a net incremental I Ib/hr of fresh steam is 6M (l + ~) [1 + (l - d /d ) Cl + (l fw c hP hp a d /d ) ClIP) x [1 + LW d + Cl (l C l P a c hp d / d ) + CI~p (l - d /d... for the simplified plant shown in Figure 1. From the material and heat balance for this plant the following is applicable: The thermal energy required to generate a net incremental 1 Ib/hr of fresh steam is Q = [6M (h - h ) -~ x 6M fw sh fw fw (h sh - h bd...

Polsky, M. P.

1983-01-01T23:59:59.000Z

263

Impact of Utility Costs on Pinch Designs  

E-Print Network [OSTI]

EEIIOCI.COI fSlIst'IRtCXI.COl ....tCTJltfC0CI.COf Baw.-srEI?ATIEI/ EaClCl'RI!CIXl!R CIoAB:fU EIlJ7~RB1!B: EDCllVIlICXI. 51 .. ? ? 71 ? ? 43 ? II ? 43 E:IllallCWXI.M EII1 EJlCXI.... 111 111 EllS CXI. ... 40 E4ClII'OUen. fU ZI E41MPO CXl.RB1 III...

Ranade, S. M.; Jones, D. H.; Zapata-Suarez, A.

264

Correct Marginal Utility Costs Underwrite Plant Profitability  

E-Print Network [OSTI]

for an olefins plant. The base case for this system has excess 65 psig steam which is being condensed. This is quite common for olefins plants after furnace and turbine additions have occurred without a proportional increase in new 65 psig steam demand. Ge... of Step 1 and Step 2 for this analysis are shown iri Figure 1. Ba?? Loads Steam Rates Equipment EfficiencY MW 10001bs/h Boiler Process SteAm Generator 94.0 94.0 312 371 Turbine 1(600/200 9&19) 79.4 Turbine 2 (600/4"HII.abs.Cond)7J. 2 Turbine 3...

Ranade, S. M.; Robert, W. E.

265

Operating Costs Estimates Cost Indices  

E-Print Network [OSTI]

to update costs of specific equipment, raw material or labor or CAPEX and OPEX of entire plants Cost Indices

Boisvert, Jeff

266

COLLEGE OF COMPUTER, MATHEMATICAL AND PHYSICAL SCIENCES InterConnections  

E-Print Network [OSTI]

COLLEGE OF COMPUTER, MATHEMATICAL AND PHYSICAL SCIENCES InterConnections Contents 2 Director- tious diseases and water issues.The network would include research from scientists in coun- InterConnections.V.Williams Bldg. University of Maryland College Park, MD 20742-3251 Phone: 301.405.6722 #12;INTERCONNECTIONS

Gruner, Daniel S.

267

SciTech Connect: Cost analysis of energy storage systems for...  

Office of Scientific and Technical Information (OSTI)

Cost analysis of energy storage systems for electric utility applications Citation Details In-Document Search Title: Cost analysis of energy storage systems for electric utility...

268

Financing for Utility Energy Service Contracts  

Broader source: Energy.gov [DOE]

Financing is a significant portion of utility energy service contract (UESC) costs. Experience shows several things the Federal Government can do to get the best value by reducing UESC financial transaction costs and interest.

269

Solid-state energy storage module employing integrated interconnect board  

DOE Patents [OSTI]

An electrochemical energy storage device includes a number of solid-state thin-film electrochemical cells which are selectively interconnected in series or parallel through use of an integrated interconnect board. The interconnect board is typically disposed within a sealed housing which also houses the electrochemical cells, and includes a first contact and a second contact respectively coupled to first and second power terminals of the energy storage device. The interconnect board advantageously provides for selective series or parallel connectivity with the electrochemical cells, irrespective of electrochemical cell position within the housing. Fuses and various electrical and electro-mechanical devices, such as bypass, equalization, and communication devices for example, may also be mounted to the interconnect board and selectively connected to the electrochemical cells.

Rouillard, Jean; Comte, Christophe; Daigle, Dominik; Hagen, Ronald A.; Knudson, Orlin B.; Morin, Andre; Ranger, Michel; Ross, Guy; Rouillard, Roger; St-Germain, Philippe; Sudano, Anthony; Turgeon, Thomas A.

2004-09-28T23:59:59.000Z

270

Solid-state energy storage module employing integrated interconnect board  

DOE Patents [OSTI]

The present invention is directed to an improved electrochemical energy storage device. The electrochemical energy storage device includes a number of solid-state, thin-film electrochemical cells which are selectively interconnected in series or parallel through use of an integrated interconnect board. The interconnect board is typically disposed within a sealed housing which also houses the electrochemical cells, and includes a first contact and a second contact respectively coupled to first and second power terminals of the energy storage device. The interconnect board advantageously provides for selective series or parallel connectivity with the electrochemical cells, irrespective of electrochemical cell position within the housing. Fuses and various electrical and electromechanical devices, such as bypass, equalization, and communication devices for example, may also be mounted to the interconnect board and selectively connected to the electrochemical cells.

Rouillard, Jean; Comte, Christophe; Daigle, Dominik; Hagen, Ronald A.; Knudson, Orlin B.; Morin, Andre; Ranger, Michel; Ross, Guy; Rouillard, Roger; St-Germain, Philippe; Sudano, Anthony; Turgeon, Thomas A.

2003-11-04T23:59:59.000Z

271

Near-Bulk Conductivity of Gold Nanowires as Nanoscale Interconnects and the Role of Atomically  

E-Print Network [OSTI]

Near-Bulk Conductivity of Gold Nanowires as Nanoscale Interconnects and the Role of Atomically, a significant portion of the chip is composed of interconnects. Besides, the engineering problems associated loss, signal degradation, interconnection delays, and other performance limitations related

Zubarev, Eugene

272

Electric Utility Demand-Side Evaluation Methodologies  

E-Print Network [OSTI]

, in the case of electric utilities society and the ratepayer. Commissio~ Substanti ve Rul es Sec. 23.22 stops short of specifying an evaluation methodology or requiring a benefit-cost analysis for each conservation program, but it does require that util... of view using a standard benefit-cost methodology. The methodology now in use by several. electric utilities and the Public Utility Commlsslon of Texas includes measures of efficiency and equity. The nonparticipant test as a measure of equity...

Treadway, N.

273

Energy and water in the Western and Texas interconnects.  

SciTech Connect (OSTI)

The Department of Energy's Office of Electricity has initiated a $60M program to assist the electric industry in interconnection-level analysis and planning. The objective of this effort is to facilitate the development or strengthening of capabilities in each of the three interconnections serving the lower 48 states of the United States, to prepare analyses of transmission requirements under a broad range of alternative futures and develop long-term interconnection-wide transmission expansion plans. The interconnections are the Western Interconnection, the Eastern Interconnection, and the Texas Interconnection. One element of this program address the support and development of an integrated energy-water Decision Support System (DSS) that will enable planners in the Western and Texas Interconnections to analyze the potential implications of water stress for transmission and resource planning (the Eastern Interconnection is not participating in this element). Specific objectives include: (1) Develop an integrated Energy-Water Decision Support System (DSS) that will enable planners in the Western and Texas Interconnections to analyze the potential implications of water stress for transmission and resource planning. (2) Pursue the formulation and development of the Energy-Water DSS through a strongly collaborative process between members of this proposal team and the Western Electricity Coordinating Council (WECC), Western Governors Association (WGA), the Electric Reliability Council of Texas (ERCOT) and their associated stakeholder teams. (3) Exercise the Energy-Water DSS to investigate water stress implications of the transmission planning scenarios put forward by WECC, WGA, and ERCOT. The goals of this project are: (1) Develop an integrated Energy-Water Decision Support System (DSS) that will enable planners to analyze the potential implications of water stress for transmission and resource planning. (2) Pursue the formulation and development of the Energy-Water DSS through a strongly collaborative process between Western Electricity Coordinating Council, Electric Reliability Council of Texas, Western Governors Association, and Western States Water Council. (3) Exercise the Energy-Water DSS to investigate water transmission planning scenarios.

Tidwell, Vincent Carroll

2010-08-01T23:59:59.000Z

274

Effect of interconnect creep on long-term performance of SOFC of one cell stacks  

SciTech Connect (OSTI)

Creep deformation becomes relevant for a material when the operating temperature is near or exceeds half of its melting temperature (in degrees of Kelvin). The operating temperatures for most of the solid oxide fuel cells (SOFC) under development in the SECA program are around 1073oK. High temperature ferritic alloys are potential candidates as interconnect (IC) materials and spacers due to their low cost and CTE compatibility with other SOFC components. Since the melting temperature of most stainless steel is around 1800oK, possible creep deformation of IC under the typical cell operating temperature should not be neglected. In this paper, the effects of interconnect creep behavior on stack geometry change and stress redistribution of different cell components are predicted and summarized. The goal of the study is to investigate the performance of the fuel cell stack by obtaining the fuel and air channel geometry changes due to creep of the ferritic stainless steel interconnect, therefore indicating possible SOFC performance change under long term operations. IC creep models were incorporated into SOFC-MP and Mentat FC, and finite element analyses were performed to quantify the deformed configuration of the SOFC stack under the long term steady state operating temperature. It is found that creep behavior of the ferritic stainless steel IC contributes to narrowing of both the fuel and the air flow channels. In addition, stress re-distribution of the cell components suggests the need for a compliant sealing material that also relaxes at operating temperature.

Liu, Wenning N.; Sun, Xin; Khaleel, Mohammad A.

2008-02-01T23:59:59.000Z

275

Low-power approaches for parallel, free-space photonic interconnects  

SciTech Connect (OSTI)

Future advances in the application of photonic interconnects will involve the insertion of parallel-channel links into Multi-Chip Modules (MCMS) and board-level parallel connections. Such applications will drive photonic link components into more compact forms that consume far less power than traditional telecommunication data links. These will make use of new device-level technologies such as vertical cavity surface-emitting lasers and special low-power parallel photoreceiver circuits. Depending on the application, these device technologies will often be monolithically integrated to reduce the amount of board or module real estate required by the photonics. Highly parallel MCM and board-level applications will also require simplified drive circuitry, lower cost, and higher reliability than has been demonstrated in photonic and optoelectronic technologies. An example is found in two-dimensional point-to-point array interconnects for MCM stacking. These interconnects are based on high-efficiency Vertical Cavity Surface Emitting Lasers (VCSELs), Heterojunction Bipolar Transistor (HBT) photoreceivers, integrated micro-optics, and MCM-compatible packaging techniques. Individual channels have been demonstrated at 100 Mb/s, operating with a direct 3.3V CMOS electronic interface while using 45 mW of electrical power. These results demonstrate how optoelectronic device technologies can be optimized for low-power parallel link applications.

Carson, R.F.; Lovejoy, M.L.; Lear, K.L.; WSarren, M.E.; Seigal, P.K.; Craft, D.C.; Kilcoyne, S.P.; Patrizi, G.A.; Blum, O.

1995-12-31T23:59:59.000Z

276

Value of Improved Wind Power Forecasting in the Western Interconnection (Poster)  

SciTech Connect (OSTI)

Wind power forecasting is a necessary and important technology for incorporating wind power into the unit commitment and dispatch process. It is expected to become increasingly important with higher renewable energy penetration rates and progress toward the smart grid. There is consensus that wind power forecasting can help utility operations with increasing wind power penetration; however, there is far from a consensus about the economic value of improved forecasts. This work explores the value of improved wind power forecasting in the Western Interconnection of the United States.

Hodge, B.

2013-12-01T23:59:59.000Z

277

California and Washington: Utilities Receive Honors for Innovative Wind Deployment  

Office of Energy Efficiency and Renewable Energy (EERE)

Public Power Wind Award winners' efforts lower energy costs and enable utilities to use wind power more reliably.

278

Viscosity solutions of systems of PDEs with interconnected obstacles and Multi modes switching problems  

E-Print Network [OSTI]

This paper deals with existence and uniqueness, in viscosity sense, of a solution for a system of m variational partial differential inequalities with inter-connected obstacles. A particular case of this system is the deterministic version of the Verification Theorem of the Markovian optimal m-states switching problem. The switching cost functions are arbitrary. This problem is connected with the valuation of a power plant in the energy market. The main tool is the notion of systems of reflected BSDEs with oblique reflection.

HamadŤne, Said

2011-01-01T23:59:59.000Z

279

E-Print Network 3.0 - attach interconnection technology Sample...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Barbara; NONE Collection: Biology and Medicine ; Engineering 7 Call for Papers Optoelectronic Interconnects XII (OE113) Summary: interconnect technologies ultra-short reach...

280

Evaluating the cost-effectiveness of DR programs/tariffs: Questions for Pacific Northwest utilities o Conceptually, do you distinguish among different types of DR resources in your resource  

E-Print Network [OSTI]

Northwest utilities o Conceptually, do you distinguish among different types of DR resources in your of analytic process does your utility use to select DR programs/pricing tariffs (e.g., screening analysis vs. resource portfolio planning)? o In valuing the potential benefits of DR programs, how does your utility

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


281

Exact Coupling Threshold for Structural Transition in Interconnected Networks  

E-Print Network [OSTI]

Interconnected networks are mathematical representation of systems where two or more simple networks are coupled to each other. Depending on the coupling weight between the two components, the interconnected network can function in two regimes: one where the two networks are structurally distinguishable, and one where they are not. The coupling threshold--denoting this structural transition--is one of the most crucial concepts in interconnected networks. Yet, current information about the coupling threshold is limited. This letter presents an analytical expression for the exact value of the coupling threshold and outlines network interrelation implications.

Sahneh, Faryad Darabi; Van Mieghem, Piet

2014-01-01T23:59:59.000Z

282

5 F 13 Optica1 Interconnection T ransmitter Power BER  

E-Print Network [OSTI]

¬ľ 5¬ł ¬§ √ľ √? √ł √ź √ź √ļ ¬ł √? √≠ ¬ģ F√? 13 Optica1 Interconnection√? T ransmitter Power √ć BER√? √? √Ľ - ¬° √ľ √?

Choi, Woo-Young

283

Interconnecting PV on New York City's Secondary Network Distribution System  

SciTech Connect (OSTI)

This study describes technical assistance provided by NREL to help New York City and Con Edison improve the interconnection of distributed PV systems on a secondary network distribution system.

Anderson, K.; Coddington, M.; Burman, K.; Hayter, S.; Kroposki, B.; Watson, A.

2009-12-01T23:59:59.000Z

284

Energy scalability of on-chip interconnection networks  

E-Print Network [OSTI]

On-chip interconnection networks (OCN) such as point-to-point networks and buses form the communication backbone in multiprocessor systems-on-a-chip, multicore processors, and tiled processors. OCNs consume significant ...

Konstantakopoulos, Theodoros K., 1977-

2007-01-01T23:59:59.000Z

285

Evaluation of phase change materials for reconfigurable interconnects  

E-Print Network [OSTI]

The possible use of programmable integrated circuit interconnect vias using an indirectly heated phase change material is evaluated. Process development and materials investigations are examined. Devices capable of multiple ...

Khoo, Chee Ying

2010-01-01T23:59:59.000Z

286

Mortality Dependence of Cu Dual Damascene Interconnects on Adjacent Segments  

E-Print Network [OSTI]

Electromigration experiments have been carried out on straight interconnects that have single vias at each end, and are divided into two segments by a via in the center ("dotted-I" structures). For dotted-i structures in ...

Chang, Choon Wai

287

Low-Swing Signaling on Monolithically Integrated Global Graphene Interconnects  

E-Print Network [OSTI]

In this paper, we characterize the performance of monolithically integrated graphene interconnects on a prototype 0.35-?m CMOS chip. The test chip implements an array of transmitter/receivers to analyze the end-to-end data ...

Lee, Kyeong-Jae

288

The Other Face of On-Chip Interconnect  

E-Print Network [OSTI]

The multicore revolution has changed the way we think about computing. The same movement has also changed the way we look at on-chip interconnect because it is a key determinant of the performance and power efficiency of ...

Agarwal, Anant

289

Fabrication and Characterization of Through-Substrate Interconnects  

E-Print Network [OSTI]

We developed a through-substrate copper-damascene interconnect technology in silicon with minimal impedance. Via impedance was extracted using parameter measurements at 50 GHz that were matched to simple circuit models. ...

del Alamo, Jesus A.

290

Advanced Unit Commitment Strategies in the United States Eastern Interconnection  

SciTech Connect (OSTI)

This project sought to evaluate the impacts of high wind penetrations on the U.S. Eastern Interconnection and analyze how different unit commitment strategies may affect these impacts.

Meibom, P.; Larsen, H. V.; Barth, R.; Brand, H.; Tuohy, A.; Ela, E.

2011-08-01T23:59:59.000Z

291

Photovoltaic Systems Interconnected onto Secondary Network Distribution Systems Ė Success Stories  

Broader source: Energy.gov [DOE]

This report examines six case studies of photovoltaic (PV) systems integrated into secondary network systems. The six PV systems were chosen for evaluation because they are interconnected to secondary network systems located in four major Solar America Cities.

292

Interconnecting PV on NYC's Secondary Network Distribution System  

Broader source: Energy.gov [DOE]

To assess ways to improve the interconnection process, NREL conducted a four-part study with support from DOE. The NREL team then compiled the final reports from each study into this report.

293

Developing Generic Dynamic Models for the 2030 Eastern Interconnection Grid  

SciTech Connect (OSTI)

The Eastern Interconnection Planning Collaborative (EIPC) has built three major power flow cases for the 2030 Eastern Interconnection (EI) based on various levels of energy/environmental policy conditions, technology advances, and load growth. Using the power flow cases, this report documents the process of developing the generic 2030 dynamic models using typical dynamic parameters. The constructed model was validated indirectly using the synchronized phasor measurements by removing the wind generation temporarily.

Kou, Gefei [ORNL; Hadley, Stanton W [ORNL; Markham, Penn N [ORNL; Liu, Yilu [ORNL

2013-12-01T23:59:59.000Z

294

EA-1990: Ridgenose Solar Energy Interconnection Facility, Mohave County, Arizona  

Broader source: Energy.gov [DOE]

DOEís Western Area Power Administration (Desert Southwest Region) is preparing an EA that will assess the potential environmental impacts of a proposal to interconnect the planned Ridgenose Solar Energy Project to Westernís transmission system. Westernís actions could include constructing less than a mile of new transmission line from the solar facility to an existing substation, constructing an interconnection substation, and adding, moving, or modifying structures.

295

2010 Cost of Wind Energy Review  

SciTech Connect (OSTI)

This document provides a detailed description of NREL's levelized cost of wind energy equation, assumptions and results in 2010, including historical cost trends and future projections for land-based and offshore utility-scale wind.

Tegen, S.; Hand, M.; Maples, B.; Lantz, E.; Schwabe, P.; Smith, A.

2012-04-01T23:59:59.000Z

296

Mandatory Photovoltaic System Cost Estimate  

Broader source: Energy.gov [DOE]

At the request of a customer or a potential customer, Colorado electric utilities are required to conduct a cost comparison of a photovoltaic (PV) system to any proposed distribution line extension...

297

Solid-state energy storage module employing integrated interconnect board  

DOE Patents [OSTI]

The present invention is directed to an improved electrochemical energy storage device. The electrochemical energy storage device includes a number of solid-state, thin-film electrochemical cells which are selectively interconnected in series or parallel through use of an integrated interconnect board. The interconnect board is typically disposed within a sealed housing which also houses the electrochemical cells, and includes a first contact and a second contact respectively coupled to first and second power terminals of the energy storage device. The interconnect board advantageously provides for selective series or parallel connectivity with the electrochemical cells, irrespective of electrochemical cell position within the housing. In one embodiment, a sheet of conductive material is processed by employing a known milling, stamping, or chemical etching technique to include a connection pattern which provides for flexible and selective interconnecting of individual electrochemical cells within the housing, which may be a hermetically sealed housing. Fuses and various electrical and electro-mechanical devices, such as bypass, equalization, and communication devices for example, may also be mounted to the interconnect board and selectively connected to the electrochemical cells.

Rouillard, Jean (Saint-Luc, CA); Comte, Christophe (Montreal, CA); Daigle, Dominik (St-Hyacinthe, CA); Hagen, Ronald A. (Stillwater, MN); Knudson, Orlin B. (Vadnais Heights, MN); Morin, Andre (Longueuil, CA); Ranger, Michel (Lachine, CA); Ross, Guy (Beloeil, CA); Rouillard, Roger (Beloeil, CA); St-Germain, Philippe (Outremont, CA); Sudano, Anthony (Laval, CA); Turgeon, Thomas A. (Fridley, MN)

2000-01-01T23:59:59.000Z

298

Cost of Fuel to General Electricity  

Broader source: Energy.gov [DOE]

Presentation covers the topic of the cost of fuel to general electricity for the Federal Utility Partnership Working Group (FUPWG) meeting, held on November 18-19, 2009.

299

Utilities and offsites design baseline. Outside Battery Limits Facility 6000 tpd SRC-I Demonstration Plant. Volume 1  

SciTech Connect (OSTI)

As part of the overall Solvent Refined Coal (SRC-1) project baseline being prepared by International Coal Refining Company (ICRC), the RUST Engineering Company is providing necessary input for the Outside Battery Limits (OSBL) Facilities. The project baseline is comprised of: design baseline - technical definition of work; schedule baseline - detailed and management level 1 schedules; and cost baseline - estimates and cost/manpower plan. The design baseline (technical definition) for the OSBL Facilities has been completed and is presented in Volumes I, II, III, IV, V and VI. The OSBL technical definition is based on, and compatible with, the ICRC defined statement of work, design basis memorandum, master project procedures, process and mechanical design criteria, and baseline guidance documents. The design basis memorandum is included in Paragraph 1.3 of Volume I. The baseline design data is presented in 6 volumes. Volume I contains the introduction section and utility systems data through steam and feedwater. Volume II continues with utility systems data through fuel system, and contains the interconnecting systems and utility system integration information. Volume III contains the offsites data through water and waste treatment. Volume IV continues with offsites data, including site development and buildings, and contains raw materials and product handling and storage information. Volume V contains wastewater treatment and solid wastes landfill systems developed by Catalytic, Inc. to supplement the information contained in Volume III. Volume VI contains proprietary information of Resources Conservation Company related to the evaporator/crystallizer system of the wastewater treatment area.

None

1984-05-25T23:59:59.000Z

300

Cost Estimator  

Broader source: Energy.gov [DOE]

A successful candidate in this position will serve as a senior cost and schedule estimator who is responsible for preparing life-cycle cost and schedule estimates and analyses associated with the...

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


301

Operating Costs  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

This chapter is focused on capital costs for conventional construction and environmental restoration and waste management projects and examines operating cost estimates to verify that all elements of the project have been considered and properly estimated.

1997-03-28T23:59:59.000Z

302

Characterization of micro-contact resistance between a gold nanocrystalline line and a tungsten electrode probe in interconnect fatigue testing  

SciTech Connect (OSTI)

An electromechanically-coupled micro-contact resistance measurement system is built to mimic the contact process during fatigue testing of nanoscale-thickness interconnects using multiple probe methods. The design combines an optical microscope, high-resolution electronic balance, and micromanipulator-controlled electric probe, and is coupled with electrical measurements to investigate microscale contact physics. Experimental measurements are performed to characterize the contact resistance response of the gold nanocrystalline pad of a 35-nm-thick interconnect under mechanical force applied by a tungsten electrode probe. Location of a stable region for the contact resistance and the critical contact force provides better understanding of micro-contact behavior relative to the effects of the contact force and the nature of the contact surface. Increasing contact temperature leads to reduced contact resistance, softens the pad material, and modifies the contact surface. The stability of both contact resistance and interconnect resistance is studied under increasing contact force. Major fluctuations emerge when the contact force is less than the critical contact force, which shows that temporal contact resistance will affect interconnect resistance measurement accuracy, even when using the four-wire method. This performance is demonstrated experimentally by heating the Au line locally with a laser beam. Finally, the contact resistances are calculated using the LET (LiĖEtsionĖTalke) model together with combined Holm and Sharvin theory under various contact forces. Good agreement between the results is obtained. This research provides a way to measure change in interconnect line resistance directly under a stable contact resistance regime with a two-wire method that will greatly reduce the experimental costs.

Ling, Xue; Wang, Yusheng [Department of Engineering Mechanics, AML, Tsinghua University, Beijing 100084 (China); Li, Xide, E-mail: lixide@tsinghua.edu.cn [Department of Engineering Mechanics, AML, Tsinghua University, Beijing 100084 (China); Center for Nano and Micro Mechanics, Tsinghua University, Beijing 100084 (China)

2014-10-15T23:59:59.000Z

303

New Mexico Interconnection Manual | Open Energy Information  

Open Energy Info (EERE)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia: Energy ResourcesLoading map...(Utility Company) Jump to: navigation, searchOhio:MO) JumpPermitsfor

304

Operating Reserve Implication of Alternative Implementations of an Energy Imbalance Service on Wind Integration in the Western Interconnection: Preprint  

SciTech Connect (OSTI)

During the past few years, there has been significant interest in alternative ways to manage power systems over a larger effective electrical footprint. Large regional transmission organizations in the Eastern Interconnection have effectively consolidated balancing areas, achieving significant economies of scale that result in a reduction in required reserves. Conversely, in the Western Interconnection there are many balancing areas, which will result in challenges if there is significant wind and solar energy development in the region. A recent proposal to the Western Electricity Coordinating Council suggests a regional energy imbalance service (EIS). To evaluate this EIS, a number of analyses are in process or are planned. This paper describes one part of an analysis of the EIS's implication on operating reserves under several alternative scenarios of the market footprint and participation. We improve on the operating reserves method utilized in the Eastern Wind Integration and Transmission Study and apply this modified approach to data from the Western Wind and Solar Integration Study.

Milligan, M.; Kirby, B.; King, J.; Beuning, S.

2011-07-01T23:59:59.000Z

305

Jetway: Minimizing Costs on Inter-Datacenter Video Traffic  

E-Print Network [OSTI]

Jetway: Minimizing Costs on Inter-Datacenter Video Traffic Yuan Feng, Baochun Li Department deploy a number of datacenters inter-connected by high-capacity links, spanning different geographical-to-customer video serving, constitutes a large portion of a cloud provider's inter- datacenter traffic. Charged

Li, Baochun

306

Interconnection Networks for Scalable Quantum Computers  

E-Print Network [OSTI]

We show that the problem of communication in a quantum computer reduces to constructing reliable quantum channels by distributing high-fidelity EPR pairs. We develop analytical models of the latency, bandwidth, error rate and resource utilization of such channels, and show that 100s of qubits must be distributed to accommodate a single data communication. Next, we show that a grid of teleportation nodes forms a good substrate on which to distribute EPR pairs. We also explore the control requirements for such a network. Finally, we propose a specific routing architecture and simulate the communication patterns of the Quantum Fourier Transform to demonstrate the impact of resource contention.

Nemanja Isailovic; Yatish Patel; Mark Whitney; John Kubiatowicz

2006-04-07T23:59:59.000Z

307

Transmission line capital costs  

SciTech Connect (OSTI)

The displacement or deferral of conventional AC transmission line installation is a key benefit associated with several technologies being developed with the support of the U.S. Department of Energy`s Office of Energy Management (OEM). Previous benefits assessments conducted within OEM have been based on significantly different assumptions for the average cost per mile of AC transmission line. In response to this uncertainty, an investigation of transmission line capital cost data was initiated. The objective of this study was to develop a database for preparing preliminary estimates of transmission line costs. An extensive search of potential data sources identified databases maintained by the Bonneville Power Administration (BPA) and the Western Area Power Administration (WAPA) as superior sources of transmission line cost data. The BPA and WAPA data were adjusted to a common basis and combined together. The composite database covers voltage levels from 13.8 to 765 W, with cost estimates for a given voltage level varying depending on conductor size, tower material type, tower frame type, and number of circuits. Reported transmission line costs vary significantly, even for a given voltage level. This can usually be explained by variation in the design factors noted above and variation in environmental and land (right-of-way) costs, which are extremely site-specific. Cost estimates prepared from the composite database were compared to cost data collected by the Federal Energy Regulatory Commission (FERC) for investor-owned utilities from across the United States. The comparison was hampered because the only design specifications included with the FERC data were voltage level and line length. Working within this limitation, the FERC data were not found to differ significantly from the composite database. Therefore, the composite database was judged to be a reasonable proxy for estimating national average costs.

Hughes, K.R.; Brown, D.R.

1995-05-01T23:59:59.000Z

308

Monte Carlo analysis of a monolithic interconnected module with a back surface reflector  

SciTech Connect (OSTI)

Recently, the photon Monte Carlo code, RACER-X, was modified to include wave-length dependent absorption coefficients and indices of refraction. This work was done in an effort to increase the code`s capabilities to be more applicable to a wider range of problems. These new features make RACER-X useful for analyzing devices like monolithic interconnected modules (MIMs) which have etched surface features and incorporates a back surface reflector (BSR) for spectral control. A series of calculations were performed on various MIM structures to determine the impact that surface features and component reflectivities have on spectral utilization. The traditional concern of cavity photonics is replaced with intra-cell photonics in the MIM design. Like the cavity photonic problems previously discussed, small changes in optical properties and/or geometry can lead to large changes in spectral utilization. The calculations show that seemingly innocuous surface features (e.g., trenches and grid lines) can significantly reduce the spectral utilization due to the non-normal incident photon flux. Photons that enter the device through a trench edge are refracted onto a trajectory where they will not escape. This leads to a reduction in the number of reflected below bandgap photons that return to the radiator and reduce the spectral utilization. In addition, trenches expose a lateral conduction layer in this particular series of calculations which increase the absorption of above bandgap photons in inactive material.

Ballinger, C.T.; Charache, G.W. [Lockheed Martin Corp., Schenectady, NY (United States); Murray, C.S. [Bettis Atomic Power Lab., West Mifflin, PA (United States)

1998-10-01T23:59:59.000Z

309

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA  

E-Print Network [OSTI]

CALIFORNIA EDISON COMPANY (U 338-E) AND THE UTILITY REFORM NETWORK RECOMMENDING A DEMAND RESPONSE COST Douglass & Liddell The Utility Reform Network On behalf of Ice Energy, Inc. 711 Van Ness Avenue, Suite 350 CALIFORNIA EDISON COMPANY (U 338-E) AND THE UTILITY REFORM NETWORK RECOMMENDING A DEMAND RESPONSE COST

310

PFBC Utility Demonstration Project  

SciTech Connect (OSTI)

This report provides a summary of activities by American Electric Power Service Corporation during the first budget period of the PFBC Utility Demonstration Project. In April 1990, AEP signed a Cooperative Agreement with the US Department of Energy to repower the Philip Sporn Plant, Units 3 4 in New Haven, West Virginia, with a 330 KW PFBC plant. The purpose of the program was to demonstrate and verify PFBC in a full-scale commercial plant. The technical and cost baselines of the Cooperative Agreement were based on a preliminary engineering and design and a cost estimate developed by AEP subsequent to AEP's proposal submittal in May 1988, and prior to the signing of the Cooperative Agreement. The Statement of Work in the first budget period of the Cooperative Agreement included a task to develop a preliminary design and cost estimate for erecting a Greenfield plant and to conduct a comparison with the repowering option. The comparative assessment of the options concluded that erecting a Greenfield plant rather than repowering the existing Sporn Plant could be the technically and economically superior alternative. The Greenfield plant would have a capacity of 340 MW. The ten additional MW output is due to the ability to better match the steam cycle to the PFBC system with a new balance of plant design. In addition to this study, the conceptual design of the Sporn Repowering led to several items which warranted optimization studies with the goal to develop a more cost effective design.

Not Available

1992-11-01T23:59:59.000Z

311

Utility Solar Generation Valuation Methods  

SciTech Connect (OSTI)

Tucson Electric Power (TEP) developed, tested and verified the results of a new and appropriate method for accurately evaluating the capacity credit of time variant solar generating sources and reviewed new methods to appropriately and fairly evaluate the value of solar generation to electric utilities. The project also reviewed general integrated approaches for adequately compensating owners of solar generation for their benefits to utilities. However, given the limited funding support and time duration of this project combined with the significant differences between utilities regarding rate structures, solar resource availability and coincidence of solar generation with peak load periods, it is well beyond the scope of this project to develop specific rate, rebate, and interconnection approaches to capture utility benefits for all possible utilities. The project developed computer software based evaluation method models to compare solar generation production data measured in very short term time increments called Sample Intervals over a typical utility Dispatch Cycle during an Evaluation Period against utility system load data. Ten second resolution generation production data from the SGSSS and actual one minute resolution TEP system load data for 2006 and 2007, along with data from the Pennington Street Garage 60 kW DC capacity solar unit installed in downtown Tucson will be applied to the model for testing and verification of the evaluation method. Data was provided by other utilities, but critical time periods of data were missing making results derived from that data inaccurate. The algorithms are based on previous analysis and review of specific 2005 and 2006 SGSSS production data. The model was built, tested and verified by in house TEP personnel. For this phase of the project, TEP communicated with, shared solar production data with and collaborated on the development of solar generation valuation tools with other utilities, including Arizona Public Service, Salt River Project, Xcel and Nevada Power Company as well as the Arizona electric cooperatives. In the second phase of the project, three years of 10 second power output data of the SGSSS was used to evaluate the effectiveness of frequency domain analysis, normal statistical distribution analysis and finally maximum/minimum differential output analysis to test the applicability of these mathematic methods in accurately modeling the output variations produced by clouds passing over the SGSSS array.

Hansen, Thomas N.; Dion, Phillip J.

2009-06-30T23:59:59.000Z

312

Utility Formation  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr MayAtmosphericNuclear SecurityTensile Strain Switched Ferromagnetism inS-4500II Field EmissionFunctional MaterialsRobertUtility-Formation

313

Analysis of electric vehicle interconnection with commercial building microgrids  

SciTech Connect (OSTI)

The outline of this presentation is: (1) global concept of microgrid and electric vehicle (EV) modeling; (2) Lawrence Berkeley National Laboratory's Distributed Energy Resources Customer Adoption Model (DER-CAM); (3) presentation summary - how does the number of EVs connected to the building change with different optimization goals (cost versus CO{sub 2}); (3) ongoing EV modeling for California: the California commercial end-use survey (CEUS) database, objective: 138 different typical building - EV connections and benefits; (4) detailed analysis for healthcare facility: optimal EV connection at a healthcare facility in southern California; and (5) conclusions. Conclusions are: (1) EV Charging/discharging pattern mainly depends on the objective of the building (cost versus CO{sub 2}); (2) performed optimization runs show that stationary batteries are more attractive than mobile storage when putting more focus on CO{sub 2} emissions. Why? Stationary storage is available 24 hours a day for energy management - more effective; (3) stationary storage will be charged by PV, mobile only marginally; (4) results will depend on the considered region and tariff - final work will show the results for 138 different buildings in nine different climate zones and three major utility service territories.

Stadler, Michael; Mendes, Goncalo; Marnay, Chris; M& #233; gel, Olivier; Lai, Judy

2011-04-01T23:59:59.000Z

314

On the Configuration of the US Western Interconnection Voltage Stability Boundary  

SciTech Connect (OSTI)

AbstractóStability limits are considered in power system planning and operations to estimate the available stability margins and, if possible, to maximize the utilization of transmission facilities. These important tasks are influenced by configuration of the stability boundary. The paper introduces a new fast approach to explore the voltage stability boundary of a large system and reveal its detailed multidimensional structure. The 17939-bus U.S. Western Interconnection planning model was used to illustrate the method. Significant peculiarities of the boundaryís configuration were identified, including its nonconvexity, discontinuity, branching and internal singularities (ďholesĒ) that were not known before and could not been found by traditional methods. Experiments using WECC system are performed to evaluate the computation time using different methods. Our results show that the proposed methods are very promising in reducing calculation time and complexity

Makarov, Yuri V.; Vyakaranam, Bharat; Wu, Di; Hou, Zhangshuan; Elbert, Stephen T.; Huang, Zhenyu

2014-04-01T23:59:59.000Z

315

Hermetic aluminum radio frequency interconnection and method for making  

DOE Patents [OSTI]

The present invention provides a light-weight, hermetic coaxial radio-frequency (RF) interconnection having an electrically conductive outer housing made of aluminum or an aluminum alloy, a central electrical conductor made of ferrous or non-ferrous material, and a cylinder of dielectric material comprising a low-melting-temperature, high-thermal-expansion aluminophosphate glass composition for hermetically sealing between the aluminum-alloy outer housing and the ferrous or non-ferrous center conductor. The entire RF interconnection assembly is made permanently hermetic by thermally fusing the center conductor, glass, and housing concurrently by bringing the glass to the melt point by way of exposure to an atmospheric temperature sufficient to melt the glass, less than 540.degree. C., but that does not melt the center conductor or the outer aluminum or aluminum alloy housing. The composition of the glass used is controlled to provide a suitable low dielectric constant so that an appropriate electrical characteristic impedance, for example 50 ohms, can be achieved for an electrical interconnection that performs well at high radio frequencies and also provides an interconnection maintaining a relatively small physical size.

Kilgo, Riley D. (Albuquerque, NM); Kovacic, Larry (Albuquerque, NM); Brow, Richard K. (Rolla, MO)

2000-01-01T23:59:59.000Z

316

Energy and Reliability in Future NOC Interconnected CMPS  

E-Print Network [OSTI]

In this dissertation, I explore energy and reliability in future NoC (Network-on-Chip) interconnected CMPs (chip multiprocessors) as they have become a first-order constraint in future CMP design. In the first part, we target the root cause...

Kim, Hyungjun

2013-08-01T23:59:59.000Z

317

A Holistic Approach to Designing Energy-Efficient Cluster Interconnects  

E-Print Network [OSTI]

, new data centers in the Seattle area are forecast to increase the city's power demands by 25 percentA Holistic Approach to Designing Energy-Efficient Cluster Interconnects Eun Jung Kim, Member, IEEE--Designing energy-efficient clusters has recently become an important concern to make these systems economically

Kim, Eun Jung "EJ"

318

Optimum Wire Tapering for Minimum Power Dissipation in RLC Interconnects  

E-Print Network [OSTI]

tapering is shown to reduce the (a CMOS inverter) with the driver (a CMOS inverter). The power dissipatedOptimum Wire Tapering for Minimum Power Dissipation in RLC Interconnects Magdy A. El-Moursy and Eby G. Friedman Department of Electrical and Computer Engineering University of Rochester Rochester, New

Friedman, Eby G.

319

High-temperature quenching of electrical resistance in graphene interconnects  

E-Print Network [OSTI]

into the chip interconnect design the materials with low electrical resistance and high thermal con- ductivity dependence of the resistance were explained by the thermal generation of the electron-hole pairs and carrier, increased total thermal boundary resistance of the chip layers, incorporation of the alternative dielectric

320

Dynamic management of water transfer between two interconnected river basins  

E-Print Network [OSTI]

Dynamic management of water transfer between two interconnected river basins Francisco Cabo Katrin cause environmental damage in the donor basin. The recipient faces a trade-off between paying the price of the irrigated soil, or demand for water for highly productive activities like tourism), then the existence

Boyer, Edmond

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


321

Electric power from offshore wind via synoptic-scale interconnection  

E-Print Network [OSTI]

Electric power from offshore wind via synoptic-scale interconnection Willett Kemptona,1 , Felipe M regional estimate, Kempton et al. (2) calculated that two-thirds of the offshore wind power off the U in the U.S. Atlantic region is already underway. Fig. 1 shows as black squares offshore wind developments

Firestone, Jeremy

322

What does a negawatt really cost?  

E-Print Network [OSTI]

We use data from ten utility conservation programs to calculate the cost per kWh of electricity saved -- the cost of a "negawatthour" -- resulting from these programs. We first compute the life-cycle cost per kWh saved ...

Joskow, Paul L.

1991-01-01T23:59:59.000Z

323

Preliminary Characterisation of Low-Temperature Bonded Copper Interconnects for 3-D Integrated Circuits  

E-Print Network [OSTI]

Three dimensional (3-D) integrated circuits can be fabricated by bonding previously processed device layers using metal-metal bonds that also serve as layer-to-layer interconnects. Bonded copper interconnects test structures ...

Leong, Hoi Liong

324

Multiparameter Moment Matching Model Reduction Approach for Generating Geometrically Parameterized Interconnect Performance Models  

E-Print Network [OSTI]

In this paper we describe an approach for generating geometrically-parameterized integrated-circuit interconnect models that are efficient enough for use in interconnect synthesis. The model generation approach presented ...

Daniel, Luca

325

Length Effects on the Reliability of Dual-Damascene Cu Interconnects  

E-Print Network [OSTI]

The effects of interconnect length on the reliability of dual-damascene Cu metallization have been investigated. As in Al-based interconnects, the lifetimes of Cu lines increase with decreasing length. However, unlike ...

Wei, F.

326

Vibration control in plates by uniformly distributed PZT actuators interconnected via electric networks  

E-Print Network [OSTI]

improve the performances of piezoelectric actuation. internal resonance / equivalent circuits 1Vibration control in plates by uniformly distributed PZT actuators interconnected via electric vibrations of plates by means of a set of electrically-interconnected piezoelectric actuators is described

Paris-Sud XI, Université de

327

COMM-OPINION-ORDER, 76 FERC 61,347, Promoting Wholesale Competition Through Open-Access Non-discriminatory Transmission Services by Public Utilities, Docket No. RM95-8-000, Recovery of Stranded Costs by  

E-Print Network [OSTI]

COMM-OPINION-ORDER, 76 FERC ¶61,347, Promoting Wholesale Competition Through Open-Access Non Incorporated Promoting Wholesale Competition Through Open-Access Non-discriminatory Transmission Services Utilities, Docket No. RM94-7-001 [62,646] [¶61,347] Promoting Wholesale Competition Through Open-Access Non

Laughlin, Robert B.

328

H C26 Performance Analysis of Optica1 Interconnection Systems Inch-ing  

E-Print Network [OSTI]

Analysis of Optica1 Interconnection Systems Inch- ing T ransmitter T emperature Dependence .√® ¬Į √? , √? √? √¨

Choi, Woo-Young

329

What Marketing Strategies Make Sense for Utilities  

E-Print Network [OSTI]

A number of pressures are being placed on the electric utility industry to develop much closer relationships with customers and key allies. Some of these pressures include: 1. The threat of rising marginal costs, 2. New entrants into the energy...

Davis, T. D.

330

The Utility Relationship to its Key Industries  

E-Print Network [OSTI]

While the price of energy may have stabilized for the moment, the impact of several years of rate increases in the cost of energy, materials, and labor have made American industry re-evaluate their operations. Utilities serving clusters...

Gilbert, J. S.

331

Clark Public Utilities- Residential Weatherization Loan Program  

Broader source: Energy.gov [DOE]

Loans of up to $15,000 at a 5.25% interest are available through Clark Public Utilities' Weatherization Loan Program. The loans can pay for the average local cost of eligible measures, based on...

332

A Utility View of Energy Conservation  

E-Print Network [OSTI]

. S., to move away from natural gas and oil as boiler fuels to coal and nuclear requires substantial time and money, with much of the cost borne by the utilities' customers....

Grant, S. A.

1979-01-01T23:59:59.000Z

333

Reliability of Nano-Structured Nickel Interconnections Replacing FlipChip Solder Assembly without Underfill  

E-Print Network [OSTI]

Reliability of Nano-Structured Nickel Interconnections Replacing FlipChip Solder Assembly without of Technology, GA 30332-0560 Abstract This paper reports the reliability of fine pitch interconnections using lower stresses in the interconnections and enhance reliability though they add electrical parasitics

Swaminathan, Madhavan

334

Supplying Baseload Power and Reducing Transmission Requirements by Interconnecting Wind Farms  

E-Print Network [OSTI]

Supplying Baseload Power and Reducing Transmission Requirements by Interconnecting Wind Farms is not used to supply baseload electric power today. Interconnecting wind farms through the transmission grid farms are interconnected in an array, wind speed correlation among sites decreases and so does

335

Analysis of free-space optical interconnects for the three-dimensional optoelectronic stacked processor  

E-Print Network [OSTI]

Analysis of free-space optical interconnects for the three-dimensional optoelectronic stacked of free-space optical interconnect for the three-dimensional optoelectronic stacked processor (3DOESP) has VLSI; Optoelectronics; VCSELs 1. Introduction Current electronic interconnection technology cannot keep

Esener, Sadik C.

336

Ionized physical vapor deposition of integrated circuit interconnects* J. Hopwood,a)  

E-Print Network [OSTI]

Ionized physical vapor deposition of integrated circuit interconnects* J. Hopwood,a) Northeastern University, Boston, Massachusetts 02115 Received 19 November 1997; accepted 25 November 1997 Interconnects to the interconnection of semiconductor devices while the remaining 10 percent is due to transistor-related delay

337

Interconnection of nitrogen fixers and iron in the Pacific Ocean: Theory and numerical simulations  

E-Print Network [OSTI]

Interconnection of nitrogen fixers and iron in the Pacific Ocean: Theory and numerical simulations, F. Monteiro, and M. J. Follows (2012), Interconnection of nitrogen fixers and iron in the Pacific interconnected. Microbial community structure is shaped by the variable physical, chemical and predatory

338

Network Interconnection with Two-Sided User Benefits Benjamin E. Hermalin & Michael L. Katz  

E-Print Network [OSTI]

Network Interconnection with Two-Sided User Benefits Benjamin E. Hermalin & Michael L. Katz Walter Abstract Previous work on network interconnection has tended to overlook that both the sender and receiver interconnection charge is independent of the "direction" of the message and is used to induce optimal end

Sadoulet, Elisabeth

339

THE ANALYSYS OF INFORMATION IMPACTS IN COORDINATING DEFENCE AGAINST MALICIOUS ATTACKS FOR INTERCONNECTED  

E-Print Network [OSTI]

FOR INTERCONNECTED POWER SYSTEMS Ettore Bompard George Gross Roberto Napoli Fei Xue Politecnico di Torino University) in an interconnected power system to counteract such attacks has become an important problem. This paper presents to the interconnected system operators on the outcomes of the decision making process under attack. A 34-buses test

Gross, George

340

Many SIMD interconnection networks have been proposed. To put the different approaches into perspective, this analysis  

E-Print Network [OSTI]

Many SIMD interconnection networks have been proposed. To put the different approaches==Emumuuu Interconnection Netwots for SIMD Machines Howard Jay Siegel Purdue University With the advent of microprocessors our discussion to SIMD machine networks (other types are explored else- where17-19). Interconnecting N

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


341

High performance low cost interconnections for flip chip attachment with electrically conductive adhesive. Final report  

SciTech Connect (OSTI)

This final report is a compilation of final reports from each of the groups participating in the program. The main three groups involved in this effort are the Thomas J. Watson Research Center of IBM Corporation in Yorktown Heights, New York, Assembly Process Design of IBM Corporation in Endicott, New York, and SMT Laboratory of Universal Instruments Corporation in Binghamton, New York. The group at the research center focused on the conductive adhesive materials development and characterization. The group in process development focused on processing of the Polymer-Metal-Solvent Paste (PMSP) to form conductive adhesive bumps, formation of the Polymer-Metal Composite (PMC) on semiconductor devices and study of the bonding process to circuitized organic carriers, and the long term durability and reliability of joints formed using the process. The group at Universal Instruments focused on development of an equipment set and bonding parameters for the equipment to produce bond assembly tooling. Reports of each of these individual groups are presented here reviewing their technical efforts and achievements.

NONE

1998-05-01T23:59:59.000Z

342

Vehicle Technologies Office Merit Review 2014: Utilization of...  

Broader source: Energy.gov (indexed) [DOE]

or EB Curing Technology to Significantly Reduce Costs and VOCs in the Manufacture of Lithium-Ion Battery Electrodes Vehicle Technologies Office Merit Review 2014: Utilization of...

343

Anaheim Public Utilities- Green Building and New Construction Rebate Program  

Broader source: Energy.gov [DOE]

Anaheim Public Utilities (APU) offers commercial, industrial, residential, and institutional customers the Green Building Incentives Program to offset construction, installation and upgrade costs...

344

New Report: Integrating More Wind and Solar Reduces Utilities...  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

New Report: Integrating More Wind and Solar Reduces Utilities' Carbon Emissions and Fuel Costs October 1, 2013 - 3:51pm Addthis The National Renewable Energy Laboratory (NREL)...

345

Anaheim Public Utilities- Commercial & Industrial New Construction Rebate Program  

Broader source: Energy.gov [DOE]

Anaheim Public Utilities (APU) offers commercial, industrial, and institutional customers the New Construction Incentives Program to offset construction and installation costs of energy efficient...

346

Report to the Legislature in Compliance with Public Utilities Code  

E-Print Network [OSTI]

"................................................................................................................................8 DISTRIBUTED GENERATION COSTS AND SAVINGSReport to the Legislature in Compliance with Public Utilities Code Section 910 March 2013 #12...................................................................17 Self-Generation Incentive Program (SGIP

347

Marshall Municipal Utilities- Commercial Energy Efficiency Rebate Program  

Broader source: Energy.gov [DOE]

Marshall Municipal Utilities offers incentives to commercial customers which help cover the installation costs of energy efficient lighting, heating and cooling equipment, motors, variable...

348

Anaheim Public Utilities- Low-Interest Energy Efficiency Loan Program  

Broader source: Energy.gov [DOE]

Anaheim Public Utilities offers low-cost financing for energy efficiency measures through State Assistance Fund for Enterprise, Business and Industrial Development Corporation ([http://www.safe...

349

Hualapai Tribal Utility Development Project  

SciTech Connect (OSTI)

The first phase of the Hualapai Tribal Utility Development Project (Project) studied the feasibility of establishing a tribally operated utility to provide electric service to tribal customers at Grand Canyon West (see objective 1 below). The project was successful in completing the analysis of the energy production from the solar power systems at Grand Canyon West and developing a financial model, based on rates to be charged to Grand Canyon West customers connected to the solar systems, that would provide sufficient revenue for a Tribal Utility Authority to operate and maintain those systems. The objective to establish a central power grid over which the TUA would have authority and responsibility had to be modified because the construction schedule of GCW facilities, specifically the new air terminal, did not match up with the construction schedule for the solar power system. Therefore, two distributed systems were constructed instead of one central system with a high voltage distribution network. The Hualapai Tribal Council has not taken the action necessary to establish the Tribal Utility Authority that could be responsible for the electric service at GCW. The creation of a Tribal Utility Authority (TUA) was the subject of the second objective of the project. The second phase of the project examined the feasibility and strategy for establishing a tribal utility to serve the remainder of the Hualapai Reservation and the feasibility of including wind energy from a tribal wind generator in the energy resource portfolio of the tribal utility (see objective 2 below). It is currently unknown when the Tribal Council will consider the implementation of the results of the study. Objective 1 - Develop the basic organizational structure and operational strategy for a tribally controlled utility to operate at the Tribeís tourism enterprise district, Grand Canyon West. Coordinate the development of the Tribal Utility structure with the development of the Grand Canyon West Power Project construction of the power infrastructure at Grand Canyon West. Develop the maintenance and operations capacity necessary to support utility operations. Develop rates for customers on the Grand Canyon West ďmini-gridĒ sufficient for the tribal utility to be self-sustaining. Establish an implementation strategy for tribal utility service at Grand Canyon West Objective 2 - Develop a strategy for tribal utility takeover of electric service on the Reservation. Perform a cost analysis of Reservation electrical service. Develop an implementation strategy for tribal takeover of Reservation electrical service. Examine options and costs associated with integration of the Tribeís wind resources.

Hualapai Tribal Nation

2008-05-25T23:59:59.000Z

350

Federal Utility Partnership Working Group Utility Partners  

Broader source: Energy.gov [DOE]

Federal Utility Partnership Working Group (FUPWG) utility partners are eager to work closely with Federal agencies to help achieve energy management goals.

351

features Utility Generator  

E-Print Network [OSTI]

#12;#12;#12;#12;features function utility Training Pool Utility Generator Per-frame function content utility classes utility classes utility Tree Decision Generator Module Utility Clustering Adaptive Content Classification Loop features content VO selection & Utility Selector content features Real

Chang, Shih-Fu

352

Home Health and Informal Care Utilization  

E-Print Network [OSTI]

Home Health and Informal Care Utilization and Costs Over Time in Alzheimer's Disease Carolyn W. Zhu, NY 10468 (E-mail: Carolyn.zhu@mssm.edu). Home Health Care Services Quarterly, Vol. 27(1) 2008, and (3) estimate possible interdependence of home health and informal care utilization. Methods

353

Spontaneous synchronization driven by energy transport in interconnected networks  

E-Print Network [OSTI]

Understanding dynamical processes on networks is an important area of research in complex systems, with far reaching implications and applications in many real-world cases. Here we introduce and study a model of intertwined dynamics on interconnected networks, inspired by the human brain, which consists of bidirectionally coupled synchronization and energy transport processes. Remarkably, the proposed model allows the emergence of spontaneous switch-like synchronization transitions driven by the energy transport dynamics, which qualitatively mirror the transitions observed in human brain dynamics between resting-state and cognitive activity. We provide a steady-state analytical explanation for the observed behavior and show that the switch-like transition is robust over a wide range of model parameters and network topologies. Finally, we suggest that the complexity inherent in other interconnected dynamical processes might be responsible for various other emergent behaviors observed in natural systems.

Vincenzo Nicosia; Per Sebastian Skardal; Vito Latora; Alex Arenas

2015-02-26T23:59:59.000Z

354

Reliability assessment of autonomous power systems incorporating HVDC interconnection links  

SciTech Connect (OSTI)

The objective of this paper is to present an improved computational method for the overall reliability assessment of autonomous power systems that may or may not contain HVdc interconnection links. This is a hybrid method based on a Monte-Carlo simulation sequential approach which incorporates an analytical approach for the reliability modeling of the HVdc transmission links. The developed models and techniques have been implemented into a computer program that can be used to simulate the operational practices and characteristics of the overall system under study efficiently and realistically. A set of reliability indices are calculated for each load-point of interest and the entire system while a set of additional indices is calculated for quantifying the reliability performance of the interconnection links under the specified operating requirements. The analysis of a practical system is also included for a number of studies representing its various operating and design characteristics.

Dialynas, E.N.; Koskolos, N.C. [National Technical Univ., Athens (Greece). Dept. of Electrical and Computer Engineering] [National Technical Univ., Athens (Greece). Dept. of Electrical and Computer Engineering; Agoris, D. [Public Power Corp., Athens (Greece)] [Public Power Corp., Athens (Greece)

1996-01-01T23:59:59.000Z

355

E-Print Network 3.0 - avoided external costs Sample Search Results  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Economic Analysis Report Summary: Utility Commission. In determining avoided costs, no externality credits were included for items like... . Societal Avoided Costs...

356

The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies  

E-Print Network [OSTI]

Interconnectivity.degree of network interconnectivity; and the level of studyof Transmission Network Interconnectivity A number of the

Mills, Andrew D.

2009-01-01T23:59:59.000Z

357

Types of Costs Types of Cost Estimates  

E-Print Network [OSTI]

∑ Types of Costs ∑ Types of Cost Estimates ∑ Methods to estimate capital costs MIN E 408: Mining% accuracy. ≠ 2-5% of pre-production capital Types of Cost Estimates #12;3. Definitive ≠ Based on definitive-even $ Production Level Fixed Cost Break-even $ Production Level Cost-Revenue Relationships ∑ Capital Costs (or

Boisvert, Jeff

358

Series interconnected photovoltaic cells and method for making same  

DOE Patents [OSTI]

A novel photovoltaic module and method for constructing the same are disclosed. The module includes a plurality of photovoltaic cells formed on a substrate and laterally separated by interconnection regions. Each cell includes a bottom electrode, a photoactive layer and a top electrode layer. Adjacent cells are connected in electrical series by way of a conductive-buffer line. The buffer line is also useful in protecting the bottom electrode against severing during downstream layer cutting processes. 11 figs.

Albright, S.P.; Chamberlin, R.R.; Thompson, R.A.

1995-01-31T23:59:59.000Z

359

Corrosion of Metallic SOFC Interconnects in Coal Syngas  

SciTech Connect (OSTI)

With recent reductions in the operating temperature of Solid Oxide Fuel Cells (SOFC), the potential of using metallic interconnect has gone up. There is also an interest in using Coal syngas as the fuel gas and thus there is a need to analyze the behavior and performance of metallic interconnects when exposed to Coal syngas. Three high temperature material alloys, Crofer 22 APU, Ebrite and Haynes 230, having the potential to be used as SOFC interconnects were studied in simulated wet coal syngas. These alloys were exposed to syngas at 800 degrees C and for 100 hours. The exposure to coal syngas led to the formation of oxides and spinels, which evidently led to an increase in electrical resistance. Oxidation in a reducing and carburizing environment leads to unique phase and morphology formations. A comparative analysis was carried out for all the three alloys, wherein the samples were characterized by using SEM, EDS, Raman and X-Ray diffraction to obtain the morphology, thickness, composition and crystal structure of the oxides and spinels

Dastane, R.R. (University of West Virginia); Liu, X. (University of West Virginia); Johnson, C., Mao, Scott (University of Pittsburgh)

2007-09-01T23:59:59.000Z

360

Spontaneous synchronization driven by energy transport in interconnected networks  

E-Print Network [OSTI]

Understanding dynamical processes on networks is an important area of research in complex systems, with far reaching implications and applications in many real-world cases. However, the research to date has mainly focused on single dynamical processes occurring on isolated networks, and very little is known about the more interesting and realistic case of different kinds of intertwined dynamical processes taking place on interconnected networks. An example of the non-trivial combination of two types of dynamics can be found in the human brain, where cerebral circulation delivers the nutrients and oxygenated blood needed for the activity of the different brain areas, and in turn the activity of a region can induce changes in the distribution of blood flow. Here, we introduce and study a model of intertwined dynamics on interconnected networks, inspired by the human brain, which consists of bidirectionally coupled synchronization and energy transport processes. Remarkably, the proposed model allows the emergence of spontaneous switch-like synchronization transitions driven by the energy transport dynamics, which qualitatively mirror the transitions observed in human brain dynamics between resting-state and cognitive activity. We provide a steady-state analytical explanation for the observed behavior and furthermore show that the switch-like transition is robust over a wide range of model parameters and network topologies. We suggest that the complexity inherent in other interconnected dynamical processes might be responsible for various other emergent behaviors observed in natural systems.

Vincenzo Nicosia; Per Sebastian Skardal; Vito Latora; Alex Arenas

2014-07-22T23:59:59.000Z

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


361

Benchmarking Soft Costs for PV Systems in the United States (Presentation)  

SciTech Connect (OSTI)

This paper presents results from the first U.S. based data collection effort to quantify non-hardware, business process costs for PV systems at the residential and commercial scales, using a bottom-up approach. Annual expenditure and labor hour productivity data are analyzed to benchmark business process costs in the specific areas of: (1) customer acquisition; (2) permitting, inspection, and interconnection; (3) labor costs of third party financing; and (4) installation labor.

Ardani, K.

2012-06-01T23:59:59.000Z

362

Utilization Analysis Page 1 UTILIZATION ANALYSIS  

E-Print Network [OSTI]

Utilization Analysis Page 1 UTILIZATION ANALYSIS Section 46a-68-40 and HIRING/PROMOTION GOALS utilized in the Health Center's workforce, the numbers of protected classes in the workforce must conducted for each occupational category and position classification. The Utilization Analysis was performed

Oliver, Douglas L.

363

utility functions scaling profiles utility-fair  

E-Print Network [OSTI]

bandwidth utility functions scaling profiles utility-fair I. INTRODUCTION The emerging MPEG-4 video. This can result in a significant increase in the utilization of network capacity [1]. These techniques. Bandwidth utility functions [9] can be used to characterize an application's capability to adapt over

Chang, Shih-Fu

364

Incentive Rates- At What Cost?  

E-Print Network [OSTI]

with interruptible services. Instead, I filed "ISB" which was priced slightly above the marginal fuel cost on a time of use basis. Many of the periods of the year the first year that I proposed that rate, the cost of interruptible would have been higher than... forms centers on four issues; cost scope of the topic, so let me describe what I feel based pricing, discrimination, competition between is an incentive rate. My view is likely to strike utilities, and effectiveness. You've already some of you...

Schaeffer, S. C.

365

Weighing the Costs and Benefits of State Renewables Portfolio Standards in the United States: A Comparative Analysis of State-Level Policy Impact Projections  

E-Print Network [OSTI]

renewable resources and avoided costs. Section 7 summarizes,renewable energy and the avoided cost of conventional fuelsdispatch model of utility avoided cost using reference case-

Chen, Cliff

2009-01-01T23:59:59.000Z

366

Utility Monitor September 2010  

E-Print Network [OSTI]

Utility Monitor September 2010 Why monitor utility syntax? Enforce and Maintain Company-Wide DB2 Utility Standards. Jennifer Nelson Product Specialist, Rocket Software © 2010 IBM Corporation © 2010............................................................................................................... iv 1 Why Monitor DB2 Utility Syntax

367

NET PRED UTILITY  

Energy Science and Technology Software Center (OSTI)

002602IBMPC00 Normalized Elution Time Prediction Utility† http://omics.pnl.gov/software/NETPredictionUtility.php†

368

DC electrodeposition of MnĖCo alloys on stainless steels for SOFC interconnect application  

SciTech Connect (OSTI)

High conductivity coatings that resist oxide scale growth and reduce chromium evaporation are needed to make stainless steel interconnect materials viable for long-term stable operation of solid oxide fuel cells (SOFC). Mn1.5Co1.5O4 spinel is one of the most promising coatings for interconnect application because of its high conductivity, good chromium retention capability, as well as good CTE match to ferritic stainless steels. MnĖCo electrodeposition followed by oxidization is potentially a low cost method for fabrication of (Mn,Co)3O4 spinel coatings. This work looks at the co-deposition of MnĖCo alloys for this application. As a guide to optimize the deposition process, characterizations of the cathodic reactions and reaction potentials are done using polarization curves. It was found that as cobalt concentration was varied that the alloy composition became richer in cobalt, indicating that the deposition is regular co-deposition process. It was also found that at 0.05M Co concentration in excess gluconate the MnĖCo alloys composition could be tuned by varying the current density. Coatings with MnĖCo around 1:1 could be obtained at a current density of 250 mA/cm2. However, the higher potential increased hydrogen production making the films more porous. Oxidation of the alloy coatings showed that much of the porosities could be eliminated during oxidation. It was found in a number of samples that fully dense coatings where obtained. The composition of the oxidized coating was found to become enriched in Mn, possibly due to the Mn fast diffusion from the substrate.

Wu, Junwei; Jiang, Yinglu; Johnson, Christopher; Liu, Xingbo

2008-03-01T23:59:59.000Z

369

Steam Basics: Use Available Data to Lower Steam System Cost  

E-Print Network [OSTI]

Industrial steam users recognize the need to reduce system cost in order to remain internationally competitive. Steam systems are a key utility that influence cost significantly, and represent a high value opportunity target. However, the quality...

Risko, J. R.

2011-01-01T23:59:59.000Z

370

It's SO Easy Being Green: Low and No Cost Solutions  

E-Print Network [OSTI]

Table of Contents Mobile Carts PVC Pipe Glass Syringe Clearģ Utility Trolleyô Cost $50 PVC Pipe Problem Solution LocalHardware Store 1Ē, 3ft PVC Pipe Cost $2 Glass Syringe

Kennedy, Megan

2011-01-01T23:59:59.000Z

371

Project Profile: The Sacramento Municipal Utility District Consumnes Power Plant Solar Augmentation Project  

Broader source: Energy.gov [DOE]

The Sacramento Municipal Utility District (SMUD), under the Concentrating Solar Power (CSP) Heat Integration for Baseload Renewable Energy Development (HIBRED) program, is demonstrating a hybrid CSP solar energy system that takes advantage of an existing electrical generator for its power block and transmission interconnection.

372

Dynamic Portfolio Optimization with Transaction Costs: Heuristics ...  

E-Print Network [OSTI]

Aug 10, 2010 ... With no transaction costs, the optimal investments typically depend on the investor's ... new gradient-based approach for generating penalties that exploits the ..... If the investor has a power utility function, the frictionless model†...

2011-02-03T23:59:59.000Z

373

Purdue Solar Energy Utilization Laboratory  

SciTech Connect (OSTI)

The objective of this project is to establish and set-up a laboratory that will facilitate research and development of new low-cost and high-efficiency solar energy utilization technologies at Purdue University. The outcome will help spur the creation of solar energy start-up companies and eventually a solar energy industry in Indiana that can help fulfill the growing national demand for solar energy.

Agrawal, Rakesh [Purdue] [Purdue

2014-01-21T23:59:59.000Z

374

Ecient trading strategies with transaction costs Elys JOUINI,  

E-Print Network [OSTI]

, an important feature of our analysis is the setting of multidimensional model of the market as well as utility, utility maximization, transaction costs, utility price. Introduction We consider a general multivariate...nite probability space, where preferences of agents are repre- sented with the help of a multidimensional utility

Paris-Sud XI, Université de

375

Types of Costs Types of Cost Estimates  

E-Print Network [OSTI]

05-1 ∑ Types of Costs ∑ Types of Cost Estimates ∑ Methods to estimate capital costs MIN E 408-Revenue Relationships ∑ Capital Costs (or first cost or capital investment): ≠ Expenditures made to acquire or develop capital assets ≠ Three main classes of capital costs: 1. Depreciable Investment: ∑ Investment allocated

Boisvert, Jeff

376

Wind Power: How Much, How Soon, and At What Cost?  

E-Print Network [OSTI]

2007. "Utility Wind Integration and Operating Impact Statethat the integration of 20% wind into US electricity marketsand integration costs, Figure 8 provides a supply curve for wind

Wiser, Ryan H

2010-01-01T23:59:59.000Z

377

BPA to share costs with PUDs in regional planning project  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

BPA to share costs with PUDs in regional planning project Portland, Ore. - Three public utility districts and the Bonneville Power Administration signed an agreement today that...

378

Report on Transmission Cost Allocation for RTOs and Others (Presentation)  

SciTech Connect (OSTI)

This presentation describes in summary fashion some present transmission cost allocation methods, especially as this relates to the development of utility-scale renewable power sources.

Coles, L.; Porter, K.

2011-05-01T23:59:59.000Z

379

Resource planning for gas utilities: Using a model to analyze pivotal issues  

SciTech Connect (OSTI)

With the advent of wellhead price decontrols that began in the late 1970s and the development of open access pipelines in the 1980s and 90s, gas local distribution companies (LDCs) now have increased responsibility for their gas supplies and face an increasingly complex array of supply and capacity choices. Heretofore this responsibility had been share with the interstate pipelines that provide bundled firm gas supplies. Moreover, gas supply an deliverability (capacity) options have multiplied as the pipeline network becomes increasing interconnected and as new storage projects are developed. There is now a fully-functioning financial market for commodity price hedging instruments and, on interstate Pipelines, secondary market (called capacity release) now exists. As a result of these changes in the natural gas industry, interest in resource planning and computer modeling tools for LDCs is increasing. Although in some ways the planning time horizon has become shorter for the gas LDC, the responsibility conferred to the LDC and complexity of the planning problem has increased. We examine current gas resource planning issues in the wake of the Federal Energy Regulatory Commission`s (FERC) Order 636. Our goal is twofold: (1) to illustrate the types of resource planning methods and models used in the industry and (2) to illustrate some of the key tradeoffs among types of resources, reliability, and system costs. To assist us, we utilize a commercially-available dispatch and resource planning model and examine four types of resource planning problems: the evaluation of new storage resources, the evaluation of buyback contracts, the computation of avoided costs, and the optimal tradeoff between reliability and system costs. To make the illustration of methods meaningful yet tractable, we developed a prototype LDC and used it for the majority of our analysis.

Busch, J.F.; Comnes, G.A.

1995-11-01T23:59:59.000Z

380

Utility Conservation Programs: A Regulatory and Design Framework  

E-Print Network [OSTI]

, it provides that a conservation program may be implemented as long as the utility's revenue requirements (the total costs to the utility of providing electric services) do not rise over what they would have been in the absence of a utility conservation... is to achieve the greatest reduction in revenue requirements (to provide electric services at least cost to society), a utility would never pay an incentive for an in dividual ECO greater than the marginal cost it saves. If it offered incentives greater...

Norland, D. L.; Wolf, J. L.

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


381

Cost Curves for Gas Supply Security: The Case of Bulgaria  

E-Print Network [OSTI]

. Interconnections: 8.64 7.92 14 - 5 Figure 2. Structure of gas consumption by sector, Bulgaria (2007) Figure 3. Structure of heat generation by fuel type, Bulgaria (2007) Figure 4. Electricity generation mix, Bulgaria (2007) Chemical industry 31... to put the vertical dotted line). The government may want to insure the gas consumption of some specific categories of customers, the interruption of which Cost per unit of peak gas consumption insured (mÄ/mcm/day) Cumulative level of peak gas...

Silve, Florent; NoŽl, Pierre

382

Final Report on Transmission Pricing in the Western Interconnection  

SciTech Connect (OSTI)

Under this project, the Committee on Regional Electric Power Cooperation (CREPC) of the Western Interstate Energy Board developed a ''western pricing and congestion management proposal'' in order to foster efficient wholesale power markets and efficient use and expansion of the transmission grid. Drafts of this paper provided useful information to states/provinces in the Western Interconnection as Western Regional Transmission Organization (RTO) transmission pricing proposals have continued to evolve. Throughout the project there has been a gradual, but incomplete agreement on pricing systems to be used by RTOs in the West.

Douglas C. Larson; Lawrence Nordell

2003-06-25T23:59:59.000Z

383

Novel Composite Materials for SOFC Cathode-Interconnect Contact  

SciTech Connect (OSTI)

This report summarized the research efforts and major conclusions of our University Coal Research Project, which focused on developing a new class of electrically-conductive, Cr-blocking, damage-tolerant Ag-perovksite composite materials for the cathode-interconnect contact of intermediate-temperature solid oxide fuel cell (SOFC) stacks. The Ag evaporation rate increased linearly with air flow rate initially and became constant for the air flow rate {ge} {approx} 1.0 cm {center_dot} s{sup -1}. An activation energy of 280 KJ.mol{sup -1} was obtained for Ag evaporation in both air and Ar+5%H{sub 2}+3%H{sub 2}O. The exposure environment had no measurable influence on the Ag evaporation rate as well as its dependence on the gas flow rate, while different surface morphological features were developed after thermal exposure in the oxidizing and reducing environments. Pure Ag is too volatile at the SOFC operating temperature and its evaporation rate needs to be reduced to facilitate its application as the cathode-interconnect contact. Based on extensive evaporation testing, it was found that none of the alloying additions reduced the evaporation rate of Ag over the long-term exposure, except the noble metals Au, Pt, and Pd; however, these noble elements are too expensive to justify their practical use in contact materials. Furthermore, the addition of La{sub 0.8}Sr{sub 0.2}MnO{sub 3} (LSM) into Ag to form a composite material also did not significantly modify the Ag evaporation rate. The Ag-perovskite composites with the perovskite being either (La{sub 0.6}Sr{sub 0.4})(Co{sub 0.8}Fe{sub 0.2})O{sub 3} (LSCF) or LSM were systematically evaluated as the contact material between the ferritic interconnect alloy Crofer 22 APU and the LSM cathode. The area specific resistances (ASRs) of the test specimens were shown to be highly dependent on the volume percentage and the type of the perovskite present in the composite contact material as well as the amount of thermal cycling that the specimens were subjected to during testing. The Ag-LSCF composite contact materials proved more effective in trapping Cr within the contact material and preventing Cr migration into the cathode than the Ag-LSM composites. Ag-perovskite composite contact materials are promising candidates for use in intermediate-temperature SOFC stacks with ferritic stainless steel interconnects due to their ability to maintain acceptably low ASRs while reducing Cr migration into the cathode material.

J. H. Zhu

2009-07-31T23:59:59.000Z

384

Electromigration kinetics and critical current of Pb-free interconnects  

SciTech Connect (OSTI)

Electromigration kinetics of Pb-free solder bump interconnects have been studied using a single bump parameter sweep technique. By removing bump to bump variations in structure, texture, and composition, the single bump sweep technique has provided both activation energy and power exponents that reflect atomic migration and interface reactions with fewer samples, shorter stress time, and better statistics than standard failure testing procedures. Contact metallurgies based on Cu and Ni have been studied. Critical current, which corresponds to the Blech limit, was found to exist in the Ni metallurgy, but not in the Cu metallurgy. A temperature dependence of critical current was also observed.

Lu, Minhua; Rosenberg, Robert [IBM T. J. Watson Research Center, Yorktown Heights, New York 10598 (United States)

2014-04-07T23:59:59.000Z

385

Series interconnected photovoltaic cells and method for making same  

DOE Patents [OSTI]

A novel photovoltaic module (10) and method for constructing the same are disclosed. The module (10) includes a plurality of photovoltaic cells (12) formed on a substrate (14) and laterally separated by interconnection regions (15). Each cell (12) includes a bottom electrode (16), a photoactive layer (18) and a top electrode layer (20). Adjacent cells (12) are connected in electrical series by way of a conductive-buffer line (22). The buffer line (22) is also useful in protecting the bottom electrode (16) against severing during downstream layer cutting processes.

Albright, Scot P. (El Paso, TX); Chamberlin, Rhodes R. (El Paso, TX); Thompson, Roger A. (Littleton, CO)

1995-01-01T23:59:59.000Z

386

Western Interconnection Energy Imbalance Market Status and Prospects (Presentation)  

SciTech Connect (OSTI)

This presentation describes how a new wholesale electricity market for energy imbalance ancillary services could be implemented and operated. Some conclusions of this presentation are: (1) Method for calculating additional reserve requirements due to wind and solar production; (2) EIM results in substantial reduction in reserves requirements and ramping demand; (3) Reduced participation reduces benefits for all but reduces the benefits to non-participants the most; (4) Full participation leads to maximum benefit across the Western Interconnection, up to 42% of total reserve requirement; and (5) Regional EIM implementations have smaller but substantial benefits.

Milligan, M.; Kirby, B.; King, J.; Beuning, S.

2011-10-01T23:59:59.000Z

387

National Electric Transmission Study 2006 Western Interconnection Analysis  

Office of Environmental Management (EM)

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) "of EnergyEnergyENERGY TAXBalanced Scorecard Federal2 to:DieselEnergy AuditorWestern Interconnection 2006

388

Estimating Specialty Costs  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

Specialty costs are those nonstandard, unusual costs that are not typically estimated. Costs for research and development (R&D) projects involving new technologies, costs associated with future regulations, and specialty equipment costs are examples of specialty costs. This chapter discusses those factors that are significant contributors to project specialty costs and methods of estimating costs for specialty projects.

1997-03-28T23:59:59.000Z

389

Utility Theory Social Intelligence  

E-Print Network [OSTI]

Utility Theory Social Intelligence Daniel Polani Utility Theory ­ p.1/15 Utilities: Motivation Consider: game scenario For Instance: 2-or-more players Necessary: development of concept for utilities decisions sequential decisions (time) games Utility The Prototypical Scenario Consider: agent that can take

Polani, Daniel

390

Analysis of electric vehicle interconnection with commercial building microgrids  

E-Print Network [OSTI]

energy costs, CO 2 emissions, or multiple objectives of providing services to a building microgrid produces technology neutral

Stadler, Michael

2011-01-01T23:59:59.000Z

391

2012 MELLANOX TECHNOLOGIES 1 The Interconnect is the Cloud  

E-Print Network [OSTI]

IT costs from CAPEX to OPEX IT Efficiency and Business Agility Hybrid Cloud Compute and Storage Resource

Schuster, Assaf

392

WECC releases its first-ever transmission plan for the Western Interconnection  

Broader source: Energy.gov [DOE]

The Western Electricity Coordinating Council (WECC) announced the release of its first 10-Year Regional Transmission Plan (Plan) for the Western Interconnection.

393

Interconnection of Direct-drive Wind Turbines Using A Series Connected DC Grid.  

E-Print Network [OSTI]

??This thesis presents the concept of a "distributed HVDC converter" for offshore wind farms. The proposed converter topology allows series interconnection of wind turbines obviatingÖ (more)

Veilleux, Etienne

2010-01-01T23:59:59.000Z

394

Generation Interconnection Policies and Wind Power: A Discussion of Issues, Problems, and Potential Solutions  

SciTech Connect (OSTI)

This report describes the adoption and implementation of FERC Order 2003 and the reasons for the sharp rise in generation interconnection filings in recent years.

Porter, K.; Fink, S.; Mudd, C.; DeCesaro, J.

2009-01-01T23:59:59.000Z

395

Utility-based Routing in Wireless Sensor Networks  

E-Print Network [OSTI]

Utility-based Routing in Wireless Sensor Networks Xiaoguang Li and Jie Wu Department of Computer the existing utility-based routing protocols for WSNs. We put them into sev- eral categories according to their utility properties, such as delay, cost, and packet delivery ratio. In addition, we will also cover

Wu, Jie

396

Using Utility Information to Calibrate Customer Demand Management Behavior Models  

E-Print Network [OSTI]

Using Utility Information to Calibrate Customer Demand Management Behavior Models Murat Fahrio ­ Madison Report PSerc 99­06 June 10, 1999 Abstract In times of stress customers can help a utility by means be optimized if the utility can estimate the outage or substitution costs of its customers. This report

397

Electrical isolation of component cells in monolithically interconnected modules  

DOE Patents [OSTI]

A monolithically interconnected photovoltaic module having cells which are electrically connected which comprises a substrate, a plurality of cells formed over the substrate, each cell including a primary absorber layer having a light receiving surface and a p-region, formed with a p-type dopant, and an n-region formed with an n-type dopant adjacent the p-region to form a single pn-junction, and a cell isolation diode layer having a p-region, formed with a p-type dopant, and an n-region formed with an n-type dopant adjacent the p-region to form a single pn-junction, the diode layer intervening the substrate and the absorber layer wherein the absorber and diode interfacial regions of a same conductivity type orientation, the diode layer having a reverse-breakdown voltage sufficient to prevent inter-cell shunting, and each cell electrically isolated from adjacent cells with a vertical trench trough the pn-junction of the diode layer, interconnects disposed in the trenches contacting the absorber regions of adjacent cells which are doped an opposite conductivity type, and electrical contacts.

Wanlass, Mark W. (Golden, CO)

2001-01-01T23:59:59.000Z

398

Overview of PV balance-of-systems technology: Experience and guidelines for utility ties in the United States of America  

SciTech Connect (OSTI)

The U.S. National Photovoltaic Program began in 1975 by supporting the development of terrestrial PV modules and hardware associated with grid-connected PV systems. Early PV-system demonstration programs were also supported and cost shared by the U.S. Department of Energy (DOE). A wide variety of PV systems were deployed, usually with utility participation. The early demonstration projects provided, and continue to provide, valuable PV system experience to utilities, designers and suppliers. As a result of experience gained, several important milestones in codes and standards pertaining to the design, installation and operation of photovoltaic (PV) systems have been completed. These code and standard activities were conducted through collaboration of participants from all sectors of the PV industry, utilities and the US DOE National Photovoltaic Program. Codes and standards that have been proposed, written, or modified include changes and additions for the 1999 National Electric Code{reg_sign} (NEC{reg_sign}), standards for fire and personnel safety, system testing, field acceptance, component qualification, and utility interconnection. Project authorization requests with the Institute of Electrical and Electronic Engineers (IEEE) have resulted in standards for component qualification and were further adapted for standards used to list PV modules and balance-of-system components. Industry collaboration with Underwriter Laboratories, Inc., with the American Society for Testing and Materials, and through critical input and review for international standards with the International Electrotechnical Commission have resulted in new and revised domestic and international standards for PV applications. Activities related to work on codes and standards through the International Energy Agency are also being supported by the PV industry and the US DOE. The paper shows relationships between activities in standards writing.

Bower, W. [Sandia National Labs., Albuquerque, NM (United States); Whitaker, C. [Endecon Engineering, San Ramon, CA (United States)

1997-10-01T23:59:59.000Z

399

Regulatory treatment of allowances and compliance costs  

SciTech Connect (OSTI)

The Clean Air Act Amendments of 1990 (CAAA) established a national emission allowance trading system, a market-based form of environmental regulation designed to reduce and limit sulfur dioxide emissions. However, the allowance trading system is being applied primarily to an economically regulated electric utility industry. The combining of the new form of environmental regulation and economic regulation of electric utilities has raised a number of questions including what the role should be of the federal and state utility regulating commissions and how those actions will affect the decision making process of the utilities and the allowance market. There are several dimensions to the regulatory problems that commissions face. Allowances and utility compliance expenditures have implications for least-cost/IPR (integrated resource planning), prudence review procedures, holding company and multistate utility regulation and ratemaking treatment. The focus of this paper is on the ratemaking treatment. The following topics are covered: ratemaking treatment of allowances and compliance costs; Traditional cost-recovery mechanisms; limitations to the traditional approach; traditional approach and the allowance trading market; market-based cost recovery mechanisms; methods of determining the benchmark; determining the split between ratepayers and the utility; other regulatory approaches; limitations of incentive mechanisms.

Rose, K. [National Regulatory Research Institute, Columbus, OH (United States)

1993-07-01T23:59:59.000Z

400

Employee Replacement Costs  

E-Print Network [OSTI]

Employee Replacement Costs Arindrajit Dube, Eric Freeman andproperties of employee replacement costs, using a panel2008. We establish that replacement costs are sub- stantial

Dube, Arindrajit; Freeman, Eric; Reich, Michael

2010-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


401

DOE Electrolysis-Utility Integration Workshop  

E-Print Network [OSTI]

·Solutions ­ Live with it and bear cost increases ­ Storage · Compressed Air · Pumped Storage · Positive cost Planning Xcel Energy #12;September 22, 2004 Xcel Energy 2 Xcel Energy and Wind ·Who we are? ·Amount of wind? ·Issues and Experiences #12;September 22, 2004 Xcel Energy 3 Xcel Energy Utilities ·Northern States Power

402

Predictions, Challenges, and Opportunities in CMOS Compatible On-Chip Optical Interconnect  

E-Print Network [OSTI]

to a few picoseconds. IV. ELECTRICAL VS. OPTICAL INTERCONNECTS Different criteria used in the design of the . Friedman Department of Electrical and Computer Engineering University of Rochester, Rochester, New York for electrical interconnect. Predictions of the performance of CMOS compatible optical devices are made based

Friedman, Eby G.

403

Plasticity contributions to interface adhesion in thin-film interconnect structures  

E-Print Network [OSTI]

Plasticity contributions to interface adhesion in thin-film interconnect structures Michael Lanea of plasticity in thin copper layers on the interface fracture resistance in thin-film interconnect structures yield properties together with a plastic flow model for the metal layers were used to predict

Vainchtein, Anna

404

Power Reduction of CMP Communication Networks via RF-Interconnects M-C. Frank Chang  

E-Print Network [OSTI]

- alized via integration of Radio Frequency Interconnect (RF- I) through on-chip transmission lines of analog waves over on- chip transmission lines. These technologies include radio fre- quency interconnect latency and low energy consumption [5][7]. RF-I transmission lines provide single-cycle cross

Cong, Jason "Jingsheng"

405

Control Design for Interconnected Power Systems with OLTCs via Robust Decentralized Control  

E-Print Network [OSTI]

Control Design for Interconnected Power Systems with OLTCs via Robust Decentralized Control the problem of designing a decentralized control of interconnected power systems, with OLTC and SVCs, under-scale Markov jump parameter systems framework. In this paper, unlike other control schemes, OLTC transformers

Pota, Himanshu Roy

406

A Case Study of Danville Utilities: Utilizing Industrial Assessment...  

Broader source: Energy.gov (indexed) [DOE]

A Case Study of Danville Utilities: Utilizing Industrial Assessment Centers to Provide Energy Efficiency Resources for Key Accounts A Case Study of Danville Utilities: Utilizing...

407

Wideband Chip-to-Chip Interconnects for High Performance Computing.  

E-Print Network [OSTI]

??The fact that modern processors can utilize data faster than modern memory systems can supply it results in the "processor-memory gap." This disparity in supplyÖ (more)

Buckhanan, Wayne L.

2013-01-01T23:59:59.000Z

408

Catalytic bipolar interconnection plate for use in a fuel cell  

DOE Patents [OSTI]

A bipolar interconnection plate for use between adjacent fuel cell units in a stacked fuel cell assembly. Each plate is manufactured from an intermetallic composition, examples of which include NiAl or Ni.sub.3 Al which can catalyze steam reforming of hydrocarbons. Distributed within the intermetallic structure of the plate is a ceramic filler composition. The plate includes a first side with gas flow channels therein and a second side with fuel flow channels therein. A protective coating is applied to the first side, with exemplary coatings including strontium-doped or calcium-doped lanthanum chromite. To produce the plate, Ni and Al powders are combined with the filler composition, compressed at a pressure of about 10,000-30,000 psi, and heated to about 600.degree.-1000.degree. C. The coating is then applied to the first side of the completed plate using liquid injection plasma deposition or other deposition techniques.

Lessing, Paul A. (Idaho Falls, ID)

1996-01-01T23:59:59.000Z

409

Catalytic bipolar interconnection plate for use in a fuel cell  

DOE Patents [OSTI]

A bipolar interconnection plate is described for use between adjacent fuel cell units in a stacked fuel cell assembly. Each plate is manufactured from an intermetallic composition, examples of which include NiAl or Ni{sub 3}Al which can catalyze steam reforming of hydrocarbons. Distributed within the intermetallic structure of the plate is a ceramic filler composition. The plate includes a first side with gas flow channels therein and a second side with fuel flow channels therein. A protective coating is applied to the first side, with exemplary coatings including strontium-doped or calcium-doped lanthanum chromite. To produce the plate, Ni and Al powders are combined with the filler composition, compressed at a pressure of about 10,000--30,000 psi, and heated to about 600--1000 C. The coating is then applied to the first side of the completed plate using liquid injection plasma deposition or other deposition techniques. 6 figs.

Lessing, P.A.

1996-03-05T23:59:59.000Z

410

Geothermal Power and Interconnection: The Economics of Getting to Market  

SciTech Connect (OSTI)

This report provides a baseline description of the transmission issues affecting geothermal technologies. The report begins with a comprehensive overview of the grid, how it is planned, how it is used, and how it is paid for. The report then overlays onto this 'big picture' three types of geothermal technologies: conventional hydrothermal systems; emerging technologies such as enhanced engineered geothermal systems (EGS) and geopressured geothermal; and geothermal co-production with existing oil and gas wells. Each category of geothermal technology has its own set of interconnection issues, and these are examined separately for each. The report draws conclusions about each technology's market affinities as defined by factors related to transmission and distribution infrastructure. It finishes with an assessment of selected markets with known geothermal potential, identifying those that offer the best prospects for near-term commercial development and for demonstration projects.

Hurlbut, D.

2012-04-01T23:59:59.000Z

411

Quantum Dissipative Systems and Feedback Control Design by Interconnection  

E-Print Network [OSTI]

The purpose of this paper is to extend J.C. Willems' theory of dissipative systems to the quantum domain. This general theory, which combines perspectives from the quantum physics and control engineering communities, provides useful methods for analysis and design of dissipative quantum systems. We describe the interaction of the plant and a class of exosystems in general quantum feedback network terms. Our results include an infinitesimal characterization of the dissipation property, which generalizes the well-known Positive Real and Bounded Real Lemmas, and is used to study some properties of quantum dissipative systems. We also show how to formulate control design problems using quantum network models, which implements Willems' `control by interconnection' for open quantum systems. This control design formulation includes, for example, standard problems of stabilization, regulation, and robust control.

Matthew R. James; John Gough

2009-05-07T23:59:59.000Z

412

Efficient algorithm to compute mutually connected components in interconnected networks  

E-Print Network [OSTI]

Mutually connected components (MCCs) play an important role as a measure of resilience in the study of interconnected networks. Despite their importance, an efficient algorithm to obtain physical properties of all MCCs during the removals of links is not available. Here, using a well-known fully-dynamic graph algorithm, we propose an efficient algorithm to accomplish this. We show that the time complexity of this algorithm is approximately $\\mathcal{O}(N^{1.2})$, which is more efficient than the brute-force algorithm with complexity $\\mathcal{O}(N^{2})$. We anticipate this algorithm to allow simulations with complex dynamic rules to research a size regime that was not permitted before.

Hwang, S; Lee, Deokjae; Kahng, B

2014-01-01T23:59:59.000Z

413

Using CrAIN Multilayer Coatings to Improve Oxidation Resistance of Steel Interconnects for Solid Oxide Fuel Cell Stacks  

SciTech Connect (OSTI)

The requirements of low cost and high-tempurature corrosion resistance for bipolar interconnect plates in solid oxide fuel cell stacks has directed attention to the use of metal plates with oxidation resistant coatings. We have investigatedt he performance of steel plates with multilayer coatings consisting of CrN for electrical conductivity and CrAIN for oxidation resistance. The coatings were deposited usin large area filterd arc deposition technolgy, and subsequently annealed in air for up to 25 hours at 800 degrees celsius. The composition, structer and morphology of the coated plates were characterized using RBS, nuclear reaction analysis, AFM and TEM techniques. By altering the architecture of the layers within the coatings, the rate of oxidation was reduced by more than an order of magnitute. Electrical resistance was measured at room temperature.

Smith, Richard J.; Tripp, C.; Knospe, Anders; Ramana, C. V.; Gorokhovsky, Vladimir I.; Shutthanandan, V.; Gelles, David S.

2004-06-01T23:59:59.000Z

414

Page 1 of 11 The Value of IBM's DB2 Utilities and Tools in 2011 The Value of IBM's DB2 Utilities and Tools in 2011  

E-Print Network [OSTI]

Page 1 of 11 The Value of IBM's DB2 Utilities and Tools in 2011 The Value of IBM's DB2 Utilities The Value of IBM's DB2 Utilities and Tools in 2011 Table of Contents I. EXECUTIVE SUMMARY.................................................................................... 5 IV. UTILITY PERFORMANCE AND TOTAL COST OF OWNERSHIP

415

Partners for Progress- A Utility Perspective  

E-Print Network [OSTI]

a cogeneration facility. Given a competitive cost and CPL's quality serVice these industriales are choosing cPt as thei~ primary power supplier. The estimated cost of power from a ~6MW cogeneration facility is 3.4 cents/KWH which is the same... as the cost of CPL power. CU9'1'OM!R U9PQND TO HI!! INTDRUP'l'~ !m? Since the Public Utility COmm19B1on or Texas approved our latest interruptible rates for large industriales (10 MW and above) the company has Bold over 200 MWa of this service. This has...

Pierce, C. S.

416

Reading the Tea Leaves: How Utilities in the West Are Managing Carbon Regulatory Risk in their Resource Plans  

E-Print Network [OSTI]

market potential or avoided costs. Nine utilities (Avista,It then derived the avoided cost of that portfolio forbe acquired based on the avoided cost values derived in its

Barbose, Galen

2008-01-01T23:59:59.000Z

417

Abstract--It is impractical to analyze all of the possible contingencies in a large-scale interconnected power network.  

E-Print Network [OSTI]

University. He joined PJM Interconnection as a transmission planning engineer recently. (e-mail: chenq@pjm

McCalley, James D.

418

EXECUTIVE SUMMARY: RETHINKING STANDBY & FIXED COST CHARGES REGULATORY & RATE DESIGN PATHWAYS TO DEEPER SOLAR PV COST  

E-Print Network [OSTI]

to be recovered through variable, volume-based charges per kilowatt-hour (kWh). At the same time, however, someEXECUTIVE SUMMARY: RETHINKING STANDBY & FIXED COST CHARGES REGULATORY & RATE DESIGN PATHWAYS TO DEEPER SOLAR PV COST REDUCTIONS The Current Terrain In recent years, electric utilities have experienced

419

Efficient selection of binary choice bundles with cost considerations  

E-Print Network [OSTI]

of a consumer wishing to evaluate bundles of options from a list of N independently selectable binary options to supplied utility and cost functions. Although 2N is very large (e.g., for N = 100, 2N 1030 ), we show how of the individual activity prices) and a total utility value derived according to each guest's individual utility

Washington at Seattle, University of

420

Seasonal Movements and Spatial Distributions of Common Carp in an Interconnected Glacial Lake System in Eastern South Dakota  

E-Print Network [OSTI]

0 Seasonal Movements and Spatial Distributions of Common Carp in an Interconnected Glacial Lake in an Interconnected Glacial Lake System in Eastern South Dakota This thesis is approved as a creditable Distributions of Common Carp in an Interconnected Glacial Lake System in Eastern South Dakota Matthew J.

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


421

p r o g r e s s r e p o r t s Interconnect: A Fundamental Constraint  

E-Print Network [OSTI]

p r o g r e s s r e p o r t s Interconnect: A Fundamental Constraint André DeHon e n g e n i o u devices. This shows up most clearly when we need to interconnect physically distinct computa- tional to implement some larger computation or compu- tational structure. The interconnect which links these elements

Haile, Sossina M.

422

Utilizing Bacteria for Sustainable Manufacturing of Low-Cost Nanoparticles  

Broader source: Energy.gov [DOE]

Presentation for the Sustainable Nanomaterials Workshop by Oak Ridge National Laboratory held on June 26, 2012

423

Low Cost High Concentration PV Systems for Utility Power Generation |  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-UpHeatMulti-Dimensionalthe10IO1OP001Long-Term Storage of Cesium1940sofof10

424

Rising Electricity Costs: A Challenge For Consumers, Regulators, And Utilities  

U.S. Energy Information Administration (EIA) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data CenterFranconia, Virginia:FAQ <Information Administration (EIA) 10 MECS Survey Data 2010Feet) Year53Electricity: 30 Years of

425

Cost and Quality of Fuels for Electric Utility Plants  

Annual Energy Outlook 2013 [U.S. Energy Information Administration (EIA)]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) " ,"ClickPipelines AboutDecemberSteam Coal Import96 4.87CBECS Public Use Data CBECSYearThousandPADDecade1)

426

Cost and Quality of Fuels for Electric Utility Plants 1997  

Annual Energy Outlook 2013 [U.S. Energy Information Administration (EIA)]

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE:1 First Use of Energy for All Purposes (Fuel and Nonfuel),Feet) Year Jan Feb Mar Apr May Jun Jul(Summary) " ,"ClickPipelines AboutDecemberSteam Coal Import96 4.87CBECS Public Use Data CBECSYearThousandPADDecade1)7

427

New, Cost-Competitive Solar Plants for Electric Utilities  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustion | Department ofT ib l L d F S iPartnership Program |Million DOEYellow SchoolNewNew

428

Utilizing Bacteria for Sustainable Manufacturing of Low-Cost Nanoparticles  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankCombustion |Energy Usage ¬Ľof EnergyTheTwo New12.'6/0.2Contract (UESC) is notthe CaseVOCs in

429

Calculating Costs for Quality of Security Service Evdoxia Spyropoulou  

E-Print Network [OSTI]

utilization costs. The estimated costs can be fed into a resource management system to facilitate the process the design of the QoSS costing demonstration, which we believe is suitable for incorporation into a resource resource availability. As part of the process of estimating efficient task schedules, the RMS must balance

430

Utility Roles in Preserving the Industrial Base  

E-Print Network [OSTI]

While the price of energy may have stabilized for the moment, the impact of several years of rate increases in the cost of energy, materials, and labor has made American industry re-evaluate its operations. Utilities serving clusters of industrial...

Gilbert, J. S.

431

Methane Gas Utilization Project from Landfill at Ellery (NY)  

SciTech Connect (OSTI)

Landfill Gas to Electric Energy Generation and Transmission at Chautauqua County Landfill, Town of Ellery, New York. The goal of this project was to create a practical method with which the energy, of the landfill gas produced by the decomposing waste at the Chautauqua County Landfill, could be utilized. This goal was accomplished with the construction of a landfill gas to electric energy plant (originally 6.4MW and now 9.6MW) and the construction of an inter-connection power-line, from the power-plant to the nearest (5.5 miles) power-grid point.

Pantelis K. Panteli

2012-01-10T23:59:59.000Z

432

Avista Utilities- Net Metering  

Broader source: Energy.gov [DOE]

Idaho does not have a statewide net-metering policy. However, each of the state's three investor-owned utilities -- Avista Utilities, Idaho Power and Rocky Mountain Power -- has developed a net...

433

Mississippi Public Utility Act  

Broader source: Energy.gov [DOE]

The Mississippi Public Utility Act is relevant to any project that plans to generate energy. It requires that a utility must first obtain a Certificate of Public Convenience and Necessity (CPCN)...

434

Non-Hardware ("Soft") Cost-Reduction Roadmap for Residential and Small Commercial Solar Photovoltaics, 2013-2020  

SciTech Connect (OSTI)

The objective of this analysis is to roadmap the cost reductions and innovations necessary to achieve the U.S. Department of Energy (DOE) SunShot Initiative's total soft-cost targets by 2020. The roadmap focuses on advances in four soft-cost areas: (1) customer acquisition; (2) permitting, inspection, and interconnection (PII); (3) installation labor; and (4) financing. Financing cost reductions are in terms of the weighted average cost of capital (WACC) for financing PV system installations, with real-percent targets of 3.0% (residential) and 3.4% (commercial).

Ardani, K.; Seif, D.; Margolis, R.; Morris, J.; Davidson, C.; Truitt, S.; Torbert, R.

2013-08-01T23:59:59.000Z

435

Solid oxide fuel cell with internal reforming, catalyzed interconnect for use therewith, and methods  

DOE Patents [OSTI]

A catalyzed interconnect for an SOFC electrically connects an anode and an anodic current collector and comprises a metallic substrate, which provides space between the anode and anodic current collector for fuel gas flow over at least a portion of the anode, and a catalytic coating on the metallic substrate comprising a catalyst for catalyzing hydrocarbon fuel in the fuel gas to hydrogen rich reformate. An SOFC including the catalyzed anodic inter-connect, a method for operating an SOFC, and a method for making a catalyzed anodic interconnect are also disclosed.

Liu, Di-Jia; Guan, Jie; Minh, Nguyen

2010-06-08T23:59:59.000Z

436

Clark Public Utilities- Residential Heat Pump Loan Program  

Broader source: Energy.gov [DOE]

Clark Public Utilities offers loans of up to $20,000 for air-source heat pumps and $30,000 for geothermal heat pumps. Loans will help customers cover the up-front cost of installing a highly...

437

Cogeneration: The Need for Utility-Industry Cooperation  

E-Print Network [OSTI]

Cogeneration is receiving increasing attention because of its potential for efficient utilization of energy. Many recent cogeneration studies, however, have concentrated on the benefits and costs of cogeneration to industry, giving little...

Limaye, D. R.

1982-01-01T23:59:59.000Z

438

U.S. electric utility demand-side management 1993  

SciTech Connect (OSTI)

This report presents comprehensive information on electric power industry demand-side management activities in the United States at the national, regional, and utility levels. Data is included for energy savings, peakload reductions, and costs.

NONE

1995-07-01T23:59:59.000Z

439

The Strong Case for Thermal Energy Storage and Utility Incentives  

E-Print Network [OSTI]

construction costs, more stringent regulations, and increasing environmental constraints regarding development of new generating facilities. As the thermal cooling storage technology has matured, more and more utilities are recognizing that widespread use...

McCannon, L. W.

440

YEAR 2 BIOMASS UTILIZATION  

SciTech Connect (OSTI)

This Energy & Environmental Research Center (EERC) Year 2 Biomass Utilization Final Technical Report summarizes multiple projects in biopower or bioenergy, transportation biofuels, and bioproducts. A prototype of a novel advanced power system, termed the high-temperature air furnace (HITAF), was tested for performance while converting biomass and coal blends to energy. Three biomass fuels--wood residue or hog fuel, corn stover, and switchgrass--and Wyoming subbituminous coal were acquired for combustion tests in the 3-million-Btu/hr system. Blend levels were 20% biomass--80% coal on a heat basis. Hog fuel was prepared for the upcoming combustion test by air-drying and processing through a hammer mill and screen. A K-Tron biomass feeder capable of operating in both gravimetric and volumetric modes was selected as the HITAF feed system. Two oxide dispersion-strengthened (ODS) alloys that would be used in the HITAF high-temperature heat exchanger were tested for slag corrosion rates. An alumina layer formed on one particular alloy, which was more corrosion-resistant than a chromia layer that formed on the other alloy. Research activities were completed in the development of an atmospheric pressure, fluidized-bed pyrolysis-type system called the controlled spontaneous reactor (CSR), which is used to process and condition biomass. Tree trimmings were physically and chemically altered by the CSR process, resulting in a fuel that was very suitable for feeding into a coal combustion or gasification system with little or no feed system modifications required. Experimental procedures were successful for producing hydrogen from biomass using the bacteria Thermotoga, a deep-ocean thermal vent organism. Analytical procedures for hydrogen were evaluated, a gas chromatography (GC) method was derived for measuring hydrogen yields, and adaptation culturing and protocols for mutagenesis were initiated to better develop strains that can use biomass cellulose. Fly ash derived from cofiring coal with waste paper, sunflower hulls, and wood waste showed a broad spectrum of chemical and physical characteristics, according to American Society for Testing and Materials (ASTM) C618 procedures. Higher-than-normal levels of magnesium, sodium, and potassium oxide were observed for the biomass-coal fly ash, which may impact utilization in cement replacement in concrete under ASTM requirements. Other niche markets for biomass-derived fly ash were explored. Research was conducted to develop/optimize a catalytic partial oxidation-based concept for a simple, low-cost fuel processor (reformer). Work progressed to evaluate the effects of temperature and denaturant on ethanol catalytic partial oxidation. A catalyst was isolated that had a yield of 24 mole percent, with catalyst coking limited to less than 15% over a period of 2 hours. In biodiesel research, conversion of vegetable oils to biodiesel using an alternative alkaline catalyst was demonstrated without the need for subsequent water washing. In work related to biorefinery technologies, a continuous-flow reactor was used to react ethanol with lactic acid prepared from an ammonium lactate concentrate produced in fermentations conducted at the EERC. Good yields of ester were obtained even though the concentration of lactic acid in the feed was low with respect to the amount of water present. Esterification gave lower yields of ester, owing to the lowered lactic acid content of the feed. All lactic acid fermentation from amylose hydrolysate test trials was completed. Management activities included a decision to extend several projects to December 31, 2003, because of delays in receiving biomass feedstocks for testing and acquisition of commercial matching funds. In strategic studies, methods for producing acetate esters for high-value fibers, fuel additives, solvents, and chemical intermediates were discussed with several commercial entities. Commercial industries have an interest in efficient biomass gasification designs but are waiting for economic incentives. Utility, biorefinery, pulp and paper, or o

Christopher J. Zygarlicke

2004-11-01T23:59:59.000Z

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


441

Cost Model and Cost Estimating Software  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

This chapter discusses a formalized methodology is basically a cost model, which forms the basis for estimating software.

1997-03-28T23:59:59.000Z

442

Nuclear-renewable hybrid energy systems: Opportunities, interconnections, and needs  

SciTech Connect (OSTI)

As the U.S. energy system evolves, the amount of electricity from variable-generation sources is likely to increase, which could result in additional times when electricity demand is lower than available production. Thus, purveyors of technologies that traditionally have provided base-load electricityósuch as nuclear power plantsócan explore new operating procedures to deal with the associated market signals. Concurrently, innovations in nuclear reactor design coupled with sophisticated control systems now allow for more complex apportionment of heat within an integrated system such as one linked to energy-intensive chemical processes. This paper explores one opportunity Ė nuclear-renewable hybrid energy systems. These are defined as integrated facilities comprised of nuclear reactors, renewable energy generation, and industrial processes that can simultaneously address the need for grid flexibility, greenhouse gas emission reductions, and optimal use of investment capital. Six aspects of interaction (interconnections) between elements of nuclear-renewable hybrid energy systems are identified: Thermal, electrical, chemical, hydrogen, mechanical, and information. Additionally, system-level aspects affect selection, design, and operation of this hybrid system type. Throughout the paper, gaps and research needs are identified to promote further exploration of the topic.

Mark F. Ruth; Owen R. Zinaman; Mark Antkowiak; Richard D. Boardman; Robert S. Cherry; Morgan D. Bazilian

2014-02-01T23:59:59.000Z

443

Pulsed laser planarization of metal films for multilevel interconnects  

SciTech Connect (OSTI)

Multilevel interconnect schemes for integrated circuits generally require one or more planarization steps, in order to maintain an acceptably flat topography for lithography and thin-film step coverage on the higher levels. Traditional approaches have involved planarization of the interlevel insulation (dielectric) layers, either by spin-on application (e.g., polyimide), or by reflow (e.g., phosphosilicate glass). We have pursued an alternative approach, in which each metal level is melted (hence planarized) using a pulsed laser prior to patterning. Short (approx.1 ..mu..s) pulses are used to preclude undesirable metallurgical reactions between the film, adhesion or barrier layer, and dielectric layer. Laser planarization of metals is particularly well suited to multilevel systems which include ground or power planes. Results are presented for planarization of gold films on SiO/sub 2/ dielectric layers using a flashlamp-pumped dye laser. The pulse duration is approx.1 ..mu..s, which allows the heat pulse to uniformly penetrate the gold while not penetrating substantially through the underlying SiO/sub 2/ (hence not perturbing the lower levels of metal). Excellent planarization of the gold films is achieved (less than 0.1 ..mu..m surface roughness, even starting with extreme topographic variations), as well as improved conductivity. To demonstrate the process, numerous planarized two-layer structures (transmission lines under a ground plane) were fabricated and characterized. 9 refs., 2 figs.

Tuckerman, D.B.; Schmitt, R.L.

1985-05-01T23:59:59.000Z

444

Costing of Joining Methods -Arc Welding Costs  

E-Print Network [OSTI]

Costing of Joining Methods - Arc Welding Costs ver. 1 ME 6222: Manufacturing Processes and Systems.S. Colton © GIT 2009 5 #12;LaborLabor Di t ti f ldi· Direct time of welding ­ time to produce a length of weld ­ labor rate ­ multiplication gives labor cost per length · Set-up time, etc. · Personal time

Colton, Jonathan S.

445

Smart buildings with electric vehicle interconnection as buffer for local renewables?  

SciTech Connect (OSTI)

Some conclusions from this presentation are: (1) EV Charging/discharging pattern mainly depends on the objective of the building (cost versus CO{sub 2}); (2) performed optimization runs show that stationary batteries are more attractive than mobile storage when putting more focus on CO{sub 2} emissions because stationary storage is available 24 hours a day for energy management - it's more effective; (3) stationary storage will be charged by PV, mobile only marginally; and (4) results will depend on the considered region and tariff. Final research work will show the results for 138 different buildings in nine different climate zones and three major utility service territories.

Stadler, Michael; Cardoso, Goncalo; DeForest, Nicholas; Donadee, Jon; Gomez, Tomaz; Lai, Judy; Marnay, Chris; Megel, Olivier; Mendes, Goncalo; Siddiqui, Afzal

2011-05-01T23:59:59.000Z

446

Energy Scalability of On-Chip Interconnection Networks in Multicore Architectures  

E-Print Network [OSTI]

On-chip interconnection networks (OCNs) such as point-to-point networks and buses form the communication backbone in systems-on-a-chip, multicore processors, and tiled processors. OCNs can consume significant portions of ...

Agarwal, Anant

2008-11-11T23:59:59.000Z

447

Modeling and Analysis of Large-Scale On-Chip Interconnects  

E-Print Network [OSTI]

in computer aided design areas. This dissertation presents new methodologies for addressing the above two important challenging issues for large scale on-chip interconnect modeling and analysis: In the past, the standard statistical circuit modeling techniques...

Feng, Zhuo

2010-07-14T23:59:59.000Z

448

Reliability of Multi-Terminal Copper Dual-Damascene Interconnect Trees  

E-Print Network [OSTI]

Electromigration tests on different Cu dual-damascene interconnect tree structures consisting of various numbers of straight via-to-via lines connected at the common middle terminal have been carried out. Like Al-based ...

Gan, C.L.

449

Determination of Interfacial Adhesion Strength between Oxide Scale and Substrate for Metallic SOFC Interconnects  

SciTech Connect (OSTI)

The interfacial adhesion strength between the oxide scale and the substrate is crucial to the reliability and durability of metallic interconnects in SOFC operating environments. It is necessary, therefore, to establish a methodology to quantify the interfacial adhesion strength between the oxide scale and the metallic interconnect substrate, and furthermore to design and optimize the interconnect material as well as the coating materials to meet the design life of an SOFC system. In this paper, we present an integrated experimental/analytical methodology for quantifying the interfacial adhesion strength between oxide scale and a ferritic stainless steel interconnect. Stair-stepping indentation tests are used in conjunction with subsequent finite element analyses to predict the interfacial strength between the oxide scale and Crofer 22 APU substrate.

Sun, Xin; Liu, Wenning N.; Stephens, Elizabeth V.; Khaleel, Mohammad A.

2008-01-21T23:59:59.000Z

450

Fast Algorithms for High Frequency Interconnect Modeling in VLSI Circuits and Packages  

E-Print Network [OSTI]

to handle multiple dielectrics and magnetic materials. In this research, we solve three problems in interconnect modeling for high frequency circuits and packages. 1) Multiple dielectrics are common in integrated circuits and packages. We propose the first...

Yi, Yang

2011-02-22T23:59:59.000Z

451

ACTIVE SUBSTRATES FOR OPTOELECTRONIC INTERCONNECT Donald Chiarulli, Steven Levitan, Jason Bakos  

E-Print Network [OSTI]

ACTIVE SUBSTRATES FOR OPTOELECTRONIC INTERCONNECT Donald Chiarulli, Steven Levitan, Jason Bakos Semiconductor ABSTRACT We present the design of an intelligent optoelectronic chip carrier (IOCC the sapphire. The result is an optoelectronic package that supports full CMOS performance, is mechanically

Bakos, Jason D.

452

High-performance parallel processors based on star-coupled wavelength division multiplexing optical interconnects  

DOE Patents [OSTI]

As the performance of individual elements within parallel processing systems increases, increased communication capability between distributed processor and memory elements is required. There is great interest in using fiber optics to improve interconnect communication beyond that attainable using electronic technology. Several groups have considered WDM, star-coupled optical interconnects. The invention uses a fiber optic transceiver to provide low latency, high bandwidth channels for such interconnects using a robust multimode fiber technology. Instruction-level simulation is used to quantify the bandwidth, latency, and concurrency required for such interconnects to scale to 256 nodes, each operating at 1 GFLOPS performance. Performance scales have been shown to .apprxeq.100 GFLOPS for scientific application kernels using a small number of wavelengths (8 to 32), only one wavelength received per node, and achievable optoelectronic bandwidth and latency.

Deri, Robert J. (Pleasanton, CA); DeGroot, Anthony J. (Castro Valley, CA); Haigh, Ronald E. (Arvada, CO)

2002-01-01T23:59:59.000Z

453

Record of Decision for the Electrical Interconnection of the Windy Point Wind Energy Project.  

SciTech Connect (OSTI)

The Bonneville Power Administration (BPA) has decided to offer contract terms for interconnection of 250 megawatts (MW) of power to be generated by the proposed Windy Point Wind Energy Project (Wind Project) into the Federal Columbia River Transmission System (FCRTS). Windy Point Partners, LLC (WPP) propose to construct and operate the proposed Wind Project and has requested interconnection to the FCRTS. The Wind Project will be interconnected at BPA's Rock Creek Substation, which is under construction in Klickitat County, Washington. The Rock Creek Substation will provide transmission access for the Wind Project to BPA's Wautoma-John Day No.1 500-kilovolt (kV) transmission line. BPA's decision to offer terms to interconnect the Wind Project is consistent with BPA's Business Plan Final Environmental Impact Statement (BP EIS) (DOE/EIS-0183, June 1995), and the Business Plan Record of Decision (BP ROD, August 15, 1995). This decision thus is tiered to the BP ROD.

United States. Bonneville Power Administration.

2006-11-01T23:59:59.000Z

454

EIS-0438: Interconnection of the Proposed Hermosa West Wind Farm Project, Albany County, Wyoming  

Broader source: Energy.gov [DOE]

After the applicant withdrew its request to interconnect the proposed Hermosa West Wind Farm Project with Western Area Power Administrationís transmission system, Western cancelled preparation of an EIS to evaluate the potential environmental impacts of the proposal.

455

ELECTRIFICATION OF ISOLATED AREAS BY INTERCONNECTING DIFFERENT RENEWABLE SOURCES OF ENERGY: A SUSTANAIBLE APPROACH  

E-Print Network [OSTI]

development integration of different aspects: > human > social > technical > economic > environmental FirstELECTRIFICATION OF ISOLATED AREAS BY INTERCONNECTING DIFFERENT RENEWABLE SOURCES OF ENERGY intend to join their efforts to develop a technique to generate electricity from primary renewable

456

Relevance of Generation Interconnection Procedures to Feed-in Tariffs in the United States  

SciTech Connect (OSTI)

Feed-in tariffs (FITs) have been used to promote renewable electricity development in over 40 countries throughout the past two decades. These policies generally provide guaranteed prices for the full system output from eligible generators for a fixed time period (typically 15-20 years). Due in part to the success of FIT policies in Europe, some jurisdictions in the United States are considering implementing similar policies, and a few have already put such policies in place. This report is intended to offer some guidance to policymakers and regulators on how generator interconnection procedures may affect the implementation of FITs and how state generator interconnection procedures can be formulated to support state renewable energy objectives. This report is based on a literature review of model interconnection procedures formulated by several organizations, as well as other documents that have reviewed, commented on, and in some cases, ranked state interconnection procedures.

Fink, S.; Porter, K.; Rogers, J.

2010-10-01T23:59:59.000Z

457

Design of a decentralized detection filter for a class of interconnected LTI systems  

E-Print Network [OSTI]

In this thesis, we consider the problem of designing a decentralized detection filter for a class of homogeneous interconnected systems. In this class of systems, all subsystems have an identical structure. A fault in a subsystem propagates via...

Shankar, Shamanth

2001-01-01T23:59:59.000Z

458

The Influence of Adjacent Segment on the Reliability of Cu Dual Damascene Interconnects  

E-Print Network [OSTI]

Three terminal ‚??dotted-Ií interconnect structures, with vias at both ends and an additional via in the middle, were tested under various test conditions. Mortalities (failures) were found in right segments with jL value ...

Chang, Choon Wai

459

Guest Editorial for Special Issue on High-Performance Multichip Interconnections  

E-Print Network [OSTI]

The ten papers in this special issue focus on high-performance multichip interconnections. The papers span novel transmitter and receiver equalization and data-recovery architectures, channel architecture organizations, ...

Stojanovic, Vladimir Marko

460

Reliable low latency I/O in torus-based interconnection networks  

E-Print Network [OSTI]

In today's high performance computing environment I/O remains the main bottleneck in achieving the optimal performance expected of the ever improving processor and memory technologies. Interconnection networks therefore combines processing units...

Azeez, Babatunde

2007-04-25T23:59:59.000Z

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


461

Fully Integrated Graphene and Carbon Nanotube Interconnects for Gigahertz High-Speed Cmos Electronics  

E-Print Network [OSTI]

Carbon-based nanomaterials such as metallic single-walled carbon nanotubes, multiwalled carbon nanotubes (MWCNTs), and graphene have been considered as some of the most promising candidates for future interconnect technology ...

Chen, Xiangyu

462

EIS-0437: Interconnection of the Buffalo Ridge III Wind Project, Brookings and Deuel Counties, South Dakota  

Broader source: Energy.gov [DOE]

This EIS evaluates the environmental impacts of a proposal to interconnect the Heartland Wind, LLC, proposed Buffalo Ridge III Wind Project in Brookings and Deuel Counties, South Dakota, to DOEís Western Area Power Administration transmission system.

463

Priority Based Switch Allocator in Adaptive Physical Channel Regulator for On Chip Interconnects  

E-Print Network [OSTI]

Chip multiprocessors (CMPs) are now popular design paradigm for microprocessors due to their power, performance and complexity advantages where a number of relatively simple cores are integrated on a single die. On chip interconnection network (No...

Mahapatra, Sonali

2014-08-04T23:59:59.000Z

464

Reuse Distance Based Circuit Replacement in Silicon Photonic Interconnection Networks for HPC  

E-Print Network [OSTI]

-scale distance, can help to further scale data-movement capabilities in high performance computing (HPC demands within high performance computing (HPC) systems. Silicon photonic (SiP) interconnects [1-3], which

Bergman, Keren

465

Demonstration of monolithically integrated graphene interconnects for low-power CMOS applications  

E-Print Network [OSTI]

In recent years, interconnects have become an increasingly difficult design challenge as their relative performance has not improved at the same pace with transistor scaling. The specifications for complex features, clock ...

Lee, Kyeong-Jae

2011-01-01T23:59:59.000Z

466

E-Print Network 3.0 - at-speed interconnect bist Sample Search...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

Explorit Topic List Advanced Search Sample search results for: at-speed interconnect bist Page: << < 1 2 3 4 5 > >> 1 JOURNAL OF ELECTRONIC TESTING: Theory and Applications 19,...

467

Pricing Games among Interconnected Microgrids Gaurav S. Kasbekar and Saswati Sarkar  

E-Print Network [OSTI]

1 Pricing Games among Interconnected Microgrids Gaurav S. Kasbekar and Saswati Sarkar Abstract than, less than or as much aggregate power as it requires. G. Kasbekar and S. Sarkar

Sarkar, Saswati

468

ELECTR-5939; No of Pages 6 Please cite this article in press as: A. Sopinka, Variable Energy Resources: VERy Interesting Implications for the Western Interconnect, Electr. J. (2013), http://dx.doi.org/10.1016/j.tej.2013.04.015  

E-Print Network [OSTI]

Resources: VERy Interesting Implications for the Western Interconnect, Electr. J. (2013), http Interconnect Variable energy resources (VERs) are growing in the Western Interconnect. To backstop The North American bulk power system is comprised of four interconnected regions: the Western Interconnect

Pedersen, Tom

469

Activity Based Costing  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

Activity Based Costing (ABC) is method for developing cost estimates in which the project is subdivided into discrete, quantifiable activities or a work unit. This chapter outlines the Activity Based Costing method and discusses applicable uses of ABC.

1997-03-28T23:59:59.000Z

470

"List of Covered Electric Utilities" under the Public Utility...  

Broader source: Energy.gov (indexed) [DOE]

6 Revised "List of Covered Electric Utilities" under the Public Utility Regulatory Policies Act of 1978 (PURPA) - 2006 Revised Under Title I of the Public Utility Regulatory...

471

THOR Concept Complex simulation Autonomous control Conclusion Interconnection of the behavior-based control  

E-Print Network [OSTI]

Schmidt Interconnection of iB2C and a detailed machine model rrlab.cs.uni-kl.de 2 #12;THOR Concept Complex of iB2C and a detailed machine model rrlab.cs.uni-kl.de 3 #12;THOR Concept Complex simulation Schmidt Interconnection of iB2C and a detailed machine model rrlab.cs.uni-kl.de 5 #12;THOR Concept Complex

Berns, Karsten

472

Utilizing Mobility to Minimize the Total Communication and Motion Energy  

E-Print Network [OSTI]

Utilizing Mobility to Minimize the Total Communication and Motion Energy Consumption of a Robotic costs. However, simplified path loss models are utilized to model the communication channels. In Yan Operation Yuan Yan and Yasamin Mostofi Department of Electrical and Computer Engineering University

Mostofi, Yasamin

473

Effects of resource acquisitions on electric-utility shareholders  

SciTech Connect (OSTI)

The purpose of this study is to see how shareholders fare when the utility acquires different kinds of resources. The resources considered are utility-built, -operated, and -owned power plants with different combinations of construction and operation costs; purchases of power; and DSM programs. We calculated the net present value of realized (cash) return on equity as the primary factor used to represent shareholder interests. We examined shareholder returns for these resources as functions of public utility commission regulation, taxes, and the utility`s operating environment. Our treatment of regulation considers the frequency and type (future vs historic test year) of rate cases, inclusion of construction work in progress in ratebase vs allowance for funds used during construction, ratebase vs expensing of DSM programs, book and tax depreciation schedules, possible disallowances of ``excess`` power-plant or DSM capital costs, and possible lack of adjustment for ``excess`` fuel or purchased power costs. The tax policies we studied include the existence and rates for property, sales, and income taxes and the existence and regulatory treatment of deferred taxes. The utility`s operating environment includes the overall inflation rate, load-growth rate, escalation in nonproduction expenses, and nongeneration construction (capital) requirements. Finally, given the increasingly competitive nature of electricity markets, we briefly considered alternatives to traditional cost-of-service regulation. We examined shareholder returns for the resources described above in an environment where the utility competes with other suppliers solely on the basis of electricity price.

Hirst, E.; Hadley, S.

1994-05-01T23:59:59.000Z

474

Utility Marketing Strategies and Pricing Trends (An Overview)  

E-Print Network [OSTI]

utility's costs and provide a sound fiscal footing for the utility, and yet still be attractive to industry and encourage the economic development of the region. However, lower rates are simply not the only answer in a sound marketing strategy. Rather than...

Reynolds, S.

475

Combined Heat and Power: Connecting the Gap Between Markets and Utility Interconnection and Tariff Practices (Part 1)  

E-Print Network [OSTI]

, integrated system (Elliott and Spurr 1999). CHP is not a technology, but an approach to applying technologies. CHP is more energy efficient than separate generation of electricity and thermal energy. Heat that is normally wasted in conventional power... installations are considered DERóonly large central generation CHP that focuses on wholesale power generation is not included. Because this report focuses on smaller CHP, we can consider the barriers for these installations to be largely the same...

Brooks, S.; Elswick, B.; Elliott, R. N.

2006-01-01T23:59:59.000Z

476

Combined Heat and Power: Connecting the Gap Between Markets and Utility Interconnection and Tariff Practices (Part II)  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-Up fromDepartmentTieCelebrate Earth Codes andDepartment of EnergyPowerStates in

477

Combined Heat and Power: Connecting the Gap between Markets and Utility Interconnection and Tariff Practices (Part I)  

Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:YearRound-Up fromDepartmentTieCelebrate Earth Codes andDepartment of EnergyPowerStates

478

Upgrade of the LHC magnet interconnections thermal shielding  

SciTech Connect (OSTI)

The about 1700 interconnections (ICs) between the Large Hadron Collider (LHC) superconducting magnets include thermal shielding at 50-75 K, providing continuity to the thermal shielding of the magnet cryostats to reduce the overall radiation heat loads to the 1.9 K helium bath of the magnets. The IC shield, made of aluminum, is conduction-cooled via a welded bridge to the thermal shield of the adjacent magnets which is actively cooled. TIG welding of these bridges made in the LHC tunnel at installation of the magnets induced a considerable risk of fire hazard due to the proximity of the multi-layer insulation of the magnet shields. A fire incident occurred in one of the machine sectors during machine installation, but fortunately with limited consequences thanks to prompt intervention of the operators. LHC is now undergoing a 2 years technical stop during which all magnet's ICs will have to be opened to consolidate the magnet electrical connections. The IC thermal shields will therefore have to be removed and re-installed after the work is completed. In order to eliminate the risk of fire hazard when re-welding, it has been decided to review the design of the IC shields, by replacing the welded bridges with a mechanical clamping which also preserves its thermal function. An additional advantage of this new solution is the ease in dismantling for maintenance, and eliminating weld-grinding operations at removal needing radioprotection measures because of material activation after long-term operation of the LHC. This paper describes the new design of the IC shields and in particular the theoretical and experimental validation of its thermal performance. Furthermore a status report of the on-going upgrade work in the LHC is given.

Musso, Andrea; Barlow, Graeme; Bastard, Alain; Charrondiere, Maryline; Deferne, Guy; Dib, GaŽlle; Duret, Max; Guinchard, Michael; Prin, Hervť; Craen, Arnaud Vande; Villiger, Gilles [CERN European Organization for Nuclear Research, Meyrin 1211, Geneva 23, CH (Switzerland); Chrul, Anna [The Henryk Niewodniczanski Institute of Nuclear Physics, Polish Academy of Sciences, ul.Radzikowskiego 152, 31-324 Krakow (Poland); Damianoglou, Dimitrios [NTUA National Technical University of Athens, Heeron Polytechniou 9, 15780 Zografou (Greece); Strychalski, Micha? [Wroclaw University of Technology, Faculty of Mechanical and Power Engineering, Wyb. Wyspianskiego 27, Wroclaw, 50-370 (Poland); Wright, Loren [Lancaster University, Bailrigg, Lancaster, LA1 4YW (United Kingdom)

2014-01-29T23:59:59.000Z

479

Generalized utility metrics for supercomputers  

E-Print Network [OSTI]

2007:1Ė12 Generalized utility metrics for supercomputers 12.ISSUE PAPER Generalized utility metrics for supercomputersproblem of ranking the utility of supercom- puter systems

Strohmaier, Erich

2009-01-01T23:59:59.000Z

480

Utility battery storage systems program report for FY 94  

SciTech Connect (OSTI)

Sandia National Laboratories, New Mexico, conducts the Utility Battery Storage Systems Program, which is sponsored by the US Department of Energy`s Office of Energy Management. The goal of this program is to assist industry in developing cost-effective battery systems as a utility resource option by 2000. Sandia is responsible for the engineering analyses, contracted development, and testing of rechargeable batteries and systems for utility energy storage applications. This report details the technical achievements realized during fiscal year 1994.

Butler, P.C.

1995-03-01T23:59:59.000Z

Note: This page contains sample records for the topic "utility interconnection costs" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


481

Utility Data Collection Service  

Broader source: Energy.gov [DOE]

Presentation covers the utility data collection service and is given at the FUPWG 2006 Spring meeting, held on May 3-4, 2006 in Atlanta, Georgia.

482

Joint Electrical Utilities (Iowa)  

Broader source: Energy.gov [DOE]

Cities may establish utilities to acquire existing electric generating facilities or distribution systems. Acquisition, in this statute, is defined as city involvement, and includes purchase, lease...

483

Utility Regulation (Indiana)  

Broader source: Energy.gov [DOE]

The Indiana Utility Regulatory Commission enforces regulations in this legislation that apply to all individuals, corporations, companies, and partnerships that may own, operate, manage, or control...

484

Utility Energy Service Contracts  

Broader source: Energy.gov [DOE]

Utility energy service contracts (UESCs) offer Federal agencies an effective means to implement energy-efficiency, renewable-energy, and water-efficiency projects.

485

Electric Utility Industry Update  

Broader source: Energy.gov [DOE]

Presentationógiven at the April 2012 Federal Utility Partnership Working Group (FUPWG) meetingócovers significant electric industry trends and industry priorities with federal customers.

486

Municipal Utility Districts (Texas)  

Broader source: Energy.gov [DOE]

Municipal Utility Districts, regulated by the Texas Commission on Environmental Quality, may be created for the following purposes: (1) the control, storage, preservation, and distribution of its...

487

''Measuring the Costs of Climate Change Policies''  

SciTech Connect (OSTI)

Studies of the costs of climate change policies have utilized a variety of measures or metrics for summarizing costs. The leading economic models have utilized GNP, GDP, the ''area under a marginal cost curve,'' the discounted present value of consumption, and a welfare measure taken directly from the utility function of the model's representative agent (the ''Equivalent Variation''). Even when calculated using a single model, these metrics do not necessarily give similar magnitudes of costs or even rank policies consistently. This paper discusses in non-technical terms the economic concepts lying behind each concept, the theoretical basis for expecting each measure to provide a consistent ranking of policies, and the reasons why different measures provide different rankings. It identifies a method of calculating the ''Equivalent Variation'' as theoretically superior to the other cost metrics in ranking policies. When regulators put forward new economic or regulatory policies, there is a need to compare the costs and benefits of these new policies to existing policies and other alternatives to determine which policy is most cost-effective. For command and control policies, it is quite difficult to compute costs, but for more market-based policies, economists have had a great deal of success employing general equilibrium models to assess a policy's costs. Not all cost measures, however, arrive at the same ranking. Furthermore, cost measures can produce contradictory results for a specific policy. These problems make it difficult for a policy-maker to determine the best policy. For a cost measures to be of value, one would like to be confident of two things. First one wants to be sure whether the policy is a winner or loser. Second, one wants to be confident that a measure produces the correct policy ranking. That is, one wants to have confidence in a policy measure's ability to correctly rank policies from most beneficial to most harmful. This paper analyzes empirically these two properties of different costs measures as they pertain to assessing the costs of the carbon abatement policies, especially the Kyoto Protocol, under alternative assumptions about implementation.

Montgomery, W. D.; Smith, A. E.; Biggar, S. L.; Bernstein, P.M.

2003-05-09T23:59:59.000Z

488

Accelerating Communication in On-Chip Interconnection Networks  

E-Print Network [OSTI]

Escape Channel Utilization ................................................................. 13? 2. Reducing the Overhead of Adaptive Routing Algorithms ................................... 15? E. Experimental Methodology...? Figure 14. Pipeline Stages: Numbers are indicating critical path delay (ps). .................. 42? Figure 15. Layout of On-Chip Networks ......................................................................... 48? Figure 16. Overall Performance...

Ahn, Minseon

2012-07-16T23:59:59.000Z

489

Photovoltaics for demand-side management utility markets: A utility/customer partnership approach  

SciTech Connect (OSTI)

Photovoltaic (PV) systems located at customer sites can be used to meet utility needs for demand-side management (DSM) applications. PV-DSM can also represent a high-value intermediate market for PV in the utility sector. Maximum value for PV in DSM applications can be achieved by incorporating a dispatching capability to PV systems (through the addition of storage). This enables utilities to evaluate PV systems as a peak-shaving technology. To date, peak-shaving has been the higher value DSM application for US utilities. This analysis of the value of dispatchable PV-DSM systems indicates that small-scale, customer-sited systems are approaching competitive cost levels in several regions of the US that have favorable load matching and peak demand pricing characteristics. This paper presents the results for PV-DSM systems located within the service territories of five case study utilities.

Byrne, J.; Letendre, S.; Govindarajalu, C.; Wang, Y.D. [Univ. of Delaware, Newark, DE (United States). Center for Energy and Environmental Policy; Nigro, R. [Delmarva Power and Light Co., Wilmington, DE (United States); Wallace, W. [National Renewable Energy Lab., Golden, CO (United States)

1994-12-31T23:59:59.000Z

490

INDEPENDENT COST REVIEW (ICR) and INDEPENDENT COST ESTIMATE ...  

Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

INDEPENDENT COST REVIEW (ICR) and INDEPENDENT COST ESTIMATE (ICE) Standard Operating Procedures INDEPENDENT COST REVIEW (ICR) and INDEPENDENT COST ESTIMATE (ICE) Standard Operating...

491

Voltage Impacts of Utility-Scale Distributed Wind  

SciTech Connect (OSTI)

Although most utility-scale wind turbines in the United States are added at the transmission level in large wind power plants, distributed wind power offers an alternative that could increase the overall wind power penetration without the need for additional transmission. This report examines the distribution feeder-level voltage issues that can arise when adding utility-scale wind turbines to the distribution system. Four of the Pacific Northwest National Laboratory taxonomy feeders were examined in detail to study the voltage issues associated with adding wind turbines at different distances from the sub-station. General rules relating feeder resistance up to the point of turbine interconnection to the expected maximum voltage change levels were developed. Additional analysis examined line and transformer overvoltage conditions.

Allen, A.

2014-09-01T23:59:59.000Z

492

Confidential data in a competitive utility environment: A regulatory perspective  

SciTech Connect (OSTI)

Historically, the electric utility industry has been regarded as one of the most open industries in the United States in sharing information but their reputation is being challenged by competitive energy providers, the general public, regulators, and other stakeholders. As the prospect of competition among electricity power providers has increased in recent years, many utilities have been requesting that the data they submit to their utility regulatory commissions remain confidential. Withholding utility information from the public is likely to have serious and significant policy implications with respect to: (1) consumer education, the pursuit of truth, mutual respect among parties, and social cooperation; (2) the creation of a fair market for competitive energy services; (3) the regulatory balance; (4) regional and national assessments of energy-savings opportunities; (5) research and development; and (6) evaluations of utility programs, plans, and policies. In a telephone survey of all public utility commissions (PUCs) that regulate electric and gas utilities in the U.S., we found that almost all PUCs have received requests from utility companies for data to be filed as confidential, and confidential data filings appear to have increased (both in scope and in frequency) in those states where utility restructuring is being actively discussed. The most common types of data submitted as confidential by utilities dealt with specific customer data, market data, avoided costs, and utility costs.

Vine, E.

1996-08-01T23:59:59.000Z

493

Contracting with reading costs and renegotiation costs  

E-Print Network [OSTI]

OF CALIFORNIA, SAN DIEGO Contracting with Reading Costs andrents, and the competitive contracting process. Journal ofReiche. Foundation of incomplete contracting in a model of

Brennan, James R.

2007-01-01T23:59:59.000Z

494

Systems Engineering Cost Estimation  

E-Print Network [OSTI]

on project, human capital impact. 7 How to estimate Cost? Difficult to know what we are building early on1 Systems Engineering Lecture 3 Cost Estimation Dr. Joanna Bryson Dr. Leon Watts University of Bath: Contrast approaches for estimating software project cost, and identify the main sources of cost

Bryson, Joanna J.

495

Life Cycle Cost Estimate  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

Life-cycle costs (LCCs) are all the anticipated costs associated with a project or program alternative throughout its life. This includes costs from pre-operations through operations or to the end of the alternative.This chapter discusses life cycle costs and the role they play in planning.

1997-03-28T23:59:59.000Z

496

Cost Estimation Package  

Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

This chapter focuses on the components (or elements) of the cost estimation package and their documentation.

1997-03-28T23:59:59.000Z

497

Nuclear plant cancellations: causes, costs, and consequences  

SciTech Connect (OSTI)

This study was commissioned in order to help quantify the effects of nuclear plant cancellations on the Nation's electricity prices. This report presents a historical overview of nuclear plant cancellations through 1982, the costs associated with those cancellations, and the reasons that the projects were terminated. A survey is presented of the precedents for regulatory treatment of the costs, the specific methods of cost recovery that were adopted, and the impacts of these decisions upon ratepayers, utility stockholders, and taxpayers. Finally, the report identifies a series of other nuclear plants that remain at risk of canellation in the future, principally as a result of similar demand, finance, or regulatory problems cited as causes of cancellation in the past. The costs associated with these potential cancellations are estimated, along with their regional distributions, and likely methods of cost recovery are suggested.

Not Available

1983-04-01T23:59:59.000Z

498

By-Products Utilization  

E-Print Network [OSTI]

clean coal technology, are not extensively utilized in the cast concrete masonry products (bricks both conventional and clean coal technologies. A clean coal ash is defined as the ash derived from SO2Center for By-Products Utilization USE OF CLASS F FLY ASH AND CLEAN-COAL ASH BLENDS FOR CAST

Wisconsin-Milwaukee, University of

499

By-Products Utilization  

E-Print Network [OSTI]

combustion by-products #12;3 generated by using both conventional and clean-coal technologies. A clean-coal that obtained from clean-coal technology, are not utilized in cast-concrete masonry products (bricks, blocksCenter for By-Products Utilization RECENT ADVANCES IN RECYCLING CLEAN- COAL ASH By Tarun R. Naik

Wisconsin-Milwaukee, University of

500

WOOD PRODUCTS AND UTILIZATION  

E-Print Network [OSTI]

WOOD PRODUCTS AND UTILIZATION V #12;#12;443USDA Forest Service Gen. Tech. Rep. PSW-GTR-160. 1997. Section Overview Wood Products and Utilization1 John R. Shelly2 Forests are obviously a very important asset to California, and their economic and social value to the state is well documented. Wood

Standiford, Richard B.