Sample records for uprate project capital

  1. Advanced Power Ultra-Uprates of Existing Plants (APPU) Final Scientific/Technical Report

    SciTech Connect (OSTI)

    Rubiolo, Pablo R.; Conway, Lawarence E.; Oriani, Luca; Lahoda, Edward J.; DeSilva, Greg (Westinghouse Science and Technology Department); Hu, Min H.; Hartz, Josh; Bachrach, Uriel; Smith, Larry; Dudek, Daniel F. (Westinghouse Nuclear Services Division); Toman, Gary J, (Electric Power Research Institute); Feng, Dandong; Hejzlar, Pavel; Kazimi, Mujid S. (Massachusetts Institute of Technology)

    2006-03-31T23:59:59.000Z

    This project assessed the feasibility of a Power Ultra-Uprate on an existing nuclear plant. The study determined the technical and design limitations of the current components, both inside and outside the containment. Based on the identified plant bottlenecks, the design changes for major pieces of equipment required to meet the Power Ultra-Uprate throughput were determined. Costs for modified pieces of equipment and for change-out and disposal of the replaced equipment were evaluated. These costs were then used to develop capital, fuel and operating and maintenance cost estimates for the Power Ultra-Uprate plant. The cost evaluation indicates that the largest cost components are the replacement of power (during the outage required for the uprate) and the new fuel loading. Based on these results, the study concluded that, for a ?standard? 4-loop plant, the proposed Power Ultra-Uprate is technically feasible. However, the power uprate is likely to be more expensive than the cost (per Kw electric installed) of a new plant when large capacity uprates are considered (>25%). Nevertheless, the concept of the Power Ultra-Uprate may be an attractive option for specific nuclear power plants where a large margin exists in the steam and power conversion system or where medium power increases (~600 MWe) are needed. The results of the study suggest that development efforts on fuel technologies for current nuclear power plants should be oriented towards improving the fuel performance (fretting-wear, corrosion, uranium load, manufacturing, safety) required to achieve higher burnup rather focusing on potential increases in the fuel thermal output.

  2. Program & Project Management For The Acquisition Of Capital Assets...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets Project Assessment and Reporting...

  3. CapitalProjects TrackingManual

    E-Print Network [OSTI]

    the Colorado School of Mine's capital projects from inception to completion. The task of monitoring#_____________ 1. Check Budget for required signatures 2. Assign Index Number from excel file "Available 9xxxxx projects 2. FM = 51886 ­ for Facilities Management projects 4. Assign Program code 1. 1700 = Operation/Maintenance

  4. Agricultural capital project analysis system

    E-Print Network [OSTI]

    Lopez, Ramon Antonio

    1978-01-01T23:59:59.000Z

    Ecoromic Evaluation UNIDO Method Foreign Trade Distortion Distortion in the Factor Markets Discount Rate L&M Method Comparison with UNIDO Arguments in Favor Arguments Against the L&M Method Traditional Approach "Other"Approaches. . Risk... projects are development projects in developing coun- tries. They could be private or public. Examples of these are pro- duction and irrigation projects. Objectives The general objective of this research was to develop a co' mputer simulation package...

  5. Light Water Reactor Sustainability Program Power Uprate Research and Development Strategy

    SciTech Connect (OSTI)

    Hongbin Zhang

    2011-09-01T23:59:59.000Z

    The economic incentives for low-cost electricity generation will continue to drive more plant owners to identify safe and reliable methods to increase the electrical power output of the current nuclear power plant fleet. A power uprate enables a nuclear power plant to increase its electrical output with low cost. However, power uprates brought new challenges to plant owners and operators. These include equipment damage or degraded performance, and unanticipated responses to plant conditions, etc. These problems have arisen mainly from using dated design and safety analysis tools and insufficient understanding of the full implications of the proposed power uprate or from insufficient attention to detail during the design and implementation phase. It is essential to demonstrate that all required safety margins have been properly retained and the existing safety level has been maintained or even increased, with consideration of all the conditions and parameters that have an influence on plant safety. The impact of the power uprate on plant life management for long term operation is also an important issue. Significant capital investments are required to extend the lifetime of an aging nuclear power plant. Power uprates can help the plant owner to recover the investment costs. However, plant aging issues may be aggravated by the power uprate due to plant conditions. More rigorous analyses, inspections and monitoring systems are required.

  6. Revised Date September 18, 2013 Capital Project Planning

    E-Print Network [OSTI]

    . Identify Funding Funding Source(s) 2. Cost Estimate Information (from preliminary estimate form): 3_- Project Name Cost Estimate Low Range High Range #12;Revised Date ­ January 25, 2013 Priority RankingRevised Date ­ September 18, 2013 Capital Project Planning Project Approval Form All capital

  7. Pinch Retrofits Provide Cost-Effective Plant Uprating Potential

    E-Print Network [OSTI]

    Rossiter, A. P.; Spriggs, H. D.; McMullan, A. S.

    ~2) (3) and (4), and these are, therefore, not r~p~at~d here. Rather, the specific factors that make this technique useful in debottlenecking projects a d QH Heat Sink Pinch 0.0 ._-_...... --------_. Temperature Heat Source QC Figure 1... in plant uprating paper. Specific applications are described. are in given an in this ethylene plant ETHYLENE PROCESS Ethylene plants are extremely complex and generally include dedicated utility systems for heating, cooling (including ethylene...

  8. EMAB Briefing on Capital Assets Projects and Operations Activities...

    Office of Environmental Management (EM)

    www.em.doe.gov 5 * Capital asset projects with funding at over 10 M: Richland, Savannah River Site, Portsmouth, Paducah, Oak Ridge, Idaho National Laboratory, Los Alamos National...

  9. University of Nebraska Lincoln Capital Project Planning Decision Flowchart

    E-Print Network [OSTI]

    Farritor, Shane

    originator and CPC provides general sizing, implications, cost estimate, etc. for project. Consistency of continuing? Yes No1 Project proposal with costs estimates provided to Chancellor and Senior AdministrativeUniversity of Nebraska ­ Lincoln Capital Project Planning Decision Flowchart 1. Program Concept 2

  10. Program and Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2011-05-18T23:59:59.000Z

    To provide the Department of Energy (DOE), including the National Nuclear Security Administration, with project management direction for the acquisition of capital assets with the goal of delivering projects on schedule, within budget, and fully capable of meeting mission performance, safeguards and security, and environmental, safety, and health standards. Cancels DOE O 413.3. Canceled by DOE O 413.3A Chg 1.

  11. Stress Testing Projected Capitalized Farmland Values 

    E-Print Network [OSTI]

    Gao, Bo 1988-

    2012-11-12T23:59:59.000Z

    values in each state as well as regional averages over the 2012-2015 period. These projections reflect alternative assumptions regarding future trends in real net farm income at the state level as well as the rate on 10-year constant maturity U...

  12. Significant Project Flow Chart (for Board Approved Capital Construction Projects 2 million and above)

    E-Print Network [OSTI]

    of the project. Construction documents include final detailed drawings, specifications, material lists and all the project will be constructed, schedules work with his subcontractors, and orders materials. BuildingSignificant Project Flow Chart (for Board Approved Capital Construction Projects 2 million

  13. Program and Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2006-07-28T23:59:59.000Z

    The Order provides project management direction for the acquisition of capital assets that are delivered on schedule, within budget, and capable of meeting mission performance and environmental safety and health standards. The page change incorporates requirements of DOE-STD-1189-2008, Integration of Safety into the Design Process, mandatory for Hazard Category 1, 2 and 3 nuclear facilities. Cancels DOE O 413.3. Canceled by DOE O 413.3B dated 11-29-10.

  14. Comparing strategies: State funding of capital projects versus water conservation

    E-Print Network [OSTI]

    Finch, Dr. Calvin

    2013-01-01T23:59:59.000Z

    10 tx H2O Winter 2013 Column by Dr. Calvin Finch, Water Conservation and Technology Center director COMPARING STRATEGIES State funding of capital projects versus water conservation The Texas Legislature seems intent on helping local water... purveyors #30;nance a portion of the water supply projects described in the #18;#25;#28;#18; state water plan (Water for Texas #31;#28;#29;#31;). #31;e plan says that #17;#18;#24;.#27; billion is needed from the state to meet our water needs...

  15. Technology and Education: Putting it in context A summary of the final Capital Research Project report

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    Technology and Education: Putting it in context A summary of the final Capital Research Project-00593093,version1-13May2011 #12;1 Box 1: Capital Project Capital (Curriculum and Pedagogy in Technology media and research claims such as these about the educational value of new technologies. But often

  16. Program and Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2000-10-13T23:59:59.000Z

    To provide Department of Energy (DOE), including the National Nuclear Security Administration (NNSA), project management direction for the acquisition of capital assets that are delivered on schedule, within budget, and fully capable of meeting mission performance and environmental, safety and health standards. Cancels DOE O 430.1A, paragraphs 6e(7); 7a(3); 7b(11); 7b(14); 7c(4), (6), (7), (11) and (16); 7d(4) and (8); 7e(3), (10), and (17); Attachment 1, Definitions (items 30 - Line Item Project; item 42 - Project, item 48 - Strategic System; and Attachment 2, Contractor Requirements Document paragraph 1d regarding a project management system. Cancels DOE N 430.1 and DOE O 430.1A (in part). Canceled by DOE O 413.3A.

  17. Program and Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2000-10-13T23:59:59.000Z

    To provide Department of Energy (DOE), including the National Nuclear Security Administration (NNSA), project management direction for the acquisition of capital assets that are delivered on schedule, within budget, and fully capable of meeting mission performance and environmental, safety and health standards. (Cancels DOE O 430.1A, paragraphs 6e(7); 7a(3); 7b(11); 7b(14); 7c(4), (6), (7), (11) and (16); 7d(4) and (8); 7e(3), (10), and (17); Attachment 1, Definitions (items 30 - Line Item Project; item 42 - Project, item 48 - Strategic System); and Attachment 2, Contractor Requirements Document (paragraph 1d regarding a project management system). Cancels DOE N 430.1 and DOE O 430.1A (in part). Canceled by DOE O 413.3 Chg 1.

  18. Implementation of a Project Management System for Improvement to City, State's Design and Construction Capital Project Delivery

    E-Print Network [OSTI]

    Thompson, Chad C.

    2007-05-18T23:59:59.000Z

    than 400 projects with budgets of over a half billion dollars. It has shifted the capital improvement project delivery from a “multi-departmental” style of delivery to a “project management” style of delivery through the infusion of private consultants...

  19. Financing U.S. Renewable Energy Projects Through Public Capital Vehicles: Qualitative and Quantitative Benefits

    SciTech Connect (OSTI)

    Mendelsohn, M.; Feldman, D.

    2013-04-01T23:59:59.000Z

    This paper explores the possibility of financing renewable energy projects through raising capital in the public markets. It gives an overview of the size, structure, and benefits of public capital markets, as well as showing how renewable energy projects might take advantage of this source of new funds to lower the cost of electricity.

  20. CAMPUS PLANNING COMMITTEE PLANNING AND REVIEW PROCESS FOR MAJOR CAPITAL PROJECTS

    E-Print Network [OSTI]

    California at Santa Barbara, University of

    a detailed cost estimate. F. PROJECT PLANNING GUIDE (PPG): This document is required for all State fundedCAMPUS PLANNING COMMITTEE PLANNING AND REVIEW PROCESS FOR MAJOR CAPITAL PROJECTS (Revised June 2011) ___________________________________________________________________________________________ I. INTRODUCTION An effective major capital planning and review process will: Encourage appropriate

  1. CaPS Application Form -2012 CAPITAL PROJECTS AND SPACE ALLOCATION COMMITTEE (CAPS)

    E-Print Network [OSTI]

    Toronto, University of

    No B TOTAL PROJECT COST ESTIMATE / OPERATING COSTS TOTAL PROJECT COST (TPC) $ Project Number: Requested project tendered at a cost exceeding the above pre-design estimate will not proceed unless the partyCaPS Application Form - 2012 CAPITAL PROJECTS AND SPACE ALLOCATION COMMITTEE (CAPS) APPLICATION

  2. Program and Project Management Policy for the Planning, Programming, Budgeting, and Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2000-06-10T23:59:59.000Z

    To establish Department of Energy (DOE) program and project management policy for the planning, programming, budgeting, and acquisition of capital assets consistent with the following Office of Management and Budget (OMB) circulars: OMB Circular A-11, Part 3, Planning, Budgeting, and Acquisition of Capital Assets, and the supplement to Part 3, Capital Programming Guide; OMB Circular A-123; OMB Circular A-127; and OMB Circular A-130. Does not cancel other directives. Canceled by DOE N 251.99

  3. Debt Capacity and Optimal Capital Structure for Privately-Financed Infrastructure Projects

    E-Print Network [OSTI]

    productivity, profitability, and private sector capital formation. He estimated, for example, that a 1 effective utilization of resources, when compared with the more flexible and cost conscious private sectorDebt Capacity and Optimal Capital Structure for Privately-Financed Infrastructure Projects

  4. FY 2013 Major Capital Outlay Project Request and Five-Year Comprehensive Master Plan

    E-Print Network [OSTI]

    in the following specific areas: Transmission & Distribution (smart grids technology, cyber-security) GenerationFY 2013 Major Capital Outlay Project Request and Five-Year Comprehensive Master Plan September 2011 ____ No _X__ Is There a Five-Year Capital Outlay Plan Available? Yes _X__ No ____ Are Professionally

  5. Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2003-03-28T23:59:59.000Z

    The purpose of this Manual is to provide requirements and guidance to Department of Energy (DOE) employees, including National Nuclear Security Administration (NNSA) employees on the planning and acquisition of capital assets. Does not cancel other directives.

  6. FACILITIES ENGINEER WEST CHICAGO Execute capital projects for manufacturing facilities and utilities systems: scope development, cost

    E-Print Network [OSTI]

    Heller, Barbara

    FACILITIES ENGINEER ­ WEST CHICAGO OVERVIEW: Execute capital projects for manufacturing, and externally. Additional duties as assigned. QUALIFICATIONS: BS in Engineering from ABETaccredited program, or PE certification, required. 5+ years of experience in manufacturing engineering environment

  7. 2015-04-10 Capital Asset Project List.xls

    Energy Savers [EERE]

    Spent Fuel Facility (ISFF) Project 9302020 On Hold Pre CD-2 CD-0 560,000,000 Idaho National Laboratory IFDP Integrated Facility Disposition Project (IFDP) 12312015 Active...

  8. 2015-02-09 Capital Asset Project List.xls

    Office of Environmental Management (EM)

    Improvements Project 12312015 Active CD-0 26,000,000 Idaho National Laboratory CBC-LBNL-0040 LBNL Old Town Demolition Project 3302018 Active CD-1 18,025,937 Lawrence...

  9. 2015-03-09 Capital Asset Project List.xls

    Broader source: Energy.gov (indexed) [DOE]

    9302020 On Hold Pre CD-2 CD-0 560,000,000 Idaho National Laboratory IFDP Integrated Facility Disposition Project (IFDP) 12312015 Active CD-1 14,130,000,000 Oak Ridge...

  10. Managing risks in energy capital projects -- the value of contractual risk-sharing in CCS-EOR

    E-Print Network [OSTI]

    Agarwal, Anna

    2014-01-01T23:59:59.000Z

    This thesis addresses the question of how to maximize the value of energy capital projects in light of the various risks faced by these projects. The risks can be categorized as exogenous risks (not in control of involved ...

  11. A comprehensive approach to the formulation of capital projects in developing countries : finance and implementation. Case study, Edendale, Kwazulu (housing)

    E-Print Network [OSTI]

    Davis, Trevor Paul

    1983-01-01T23:59:59.000Z

    This Thesis deals with capital project formulation in developing countries. The objective is to provide guidelines for the formulation of housing development projects, their implementation structures and financial plans ...

  12. Wind-To-Hydrogen Project: Electrolyzer Capital Cost Study

    SciTech Connect (OSTI)

    Saur, G.

    2008-12-01T23:59:59.000Z

    This study is being performed as part of the U.S. Department of Energy and Xcel Energy's Wind-to-Hydrogen Project (Wind2H2) at the National Renewable Energy Laboratory. The general aim of the project is to identify areas for improving the production of hydrogen from renewable energy sources. These areas include both technical development and cost analysis of systems that convert renewable energy to hydrogen via water electrolysis. Increased efficiency and reduced cost will bring about greater market penetration for hydrogen production and application. There are different issues for isolated versus grid-connected systems, however, and these issues must be considered. The manner in which hydrogen production is integrated in the larger energy system will determine its cost feasibility and energy efficiency.

  13. Venture Capital Finance

    Broader source: Energy.gov [DOE]

    Plenary III: Project Finance and Investment Venture Capital Finance Brian Baynes, Partner, Flagship Ventures

  14. Economic and Conservation Evaluation of Capital Renovation Projects: Hidalgo County Irrigation District No. 1 (Edinburg) - North Branch / East Main - Final

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    Initial construction costs and net annual changes in operating and maintenance expenses are identified for a single-component capital renovation project proposed by Hidalgo County Irrigation District No. 1 to the Bureau of Reclamation and North...

  15. Economic and Conservation Evaluation of Capital Renovation Projects: Hidalgo County Irrigation District No. 2 (San Juan) - Relining Lateral A - Final

    E-Print Network [OSTI]

    Popp, Michael; Robinson, John; Sturdivant, Allen; Lacewell, Ronald; Rister, Edward

    Initial construction costs and net annual changes in operating and maintenance expenses are identified for a single-component capital renovation project proposed by Hidalgo County Irrigation District No. 2, (a.k.a. San Juan) to the North American...

  16. Economic and Conservation Evaluation of Capital Renovation Projects: Hidalgo County Irrigation District No. 1 (Edinburg) - Curry Main - Final

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    Initial construction costs and net annual changes in operating and maintenance expenses are identified for a single-component capital renovation project proposed by Hidalgo County Irrigation District No. 1 to the Bureau of Reclamation and North...

  17. U.S. Department of Energy Project Review Guide for Capital Asset Projects

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-09-23T23:59:59.000Z

    This Guide addresses the various project reviews conducted during the life-cycle of a project based on the stage, complexity and duration of a project. This Guide describes typical reviews, the purpose of each, the timing during the project life-cycle, lines of inquiry, and required documentation. No cancellations.

  18. 2006-7 Schedule for Submission of Regents' Items and Project Planning Guides (PPGs) for Capital Improvement Project Approval and Financing

    E-Print Network [OSTI]

    California at Santa Cruz, University of

    ) submits final items meeting Cap Planning by date date project Budget Office VC by Office by by to OP2006-7 Schedule for Submission of Regents' Items and Project Planning Guides (PPGs) for Capital Improvement Project Approval and Financing VC approves/ CIP subcmte ACF Cap Planning Regents' Regents' Item VC

  19. CAMPUS PLANNING COMMITTEE PLANNING AND REVIEW PROCESS FOR MAJOR CAPITAL PROJECTS

    E-Print Network [OSTI]

    California at Santa Barbara, University of

    , efficient and cost effective manner; · Maximize the capital dollars available to UCSB from all sources with other campuses for scarce resources.); · Optimize the use of capital dollars; · Establish a clear; whose total cost is over $400,000. #12;B. 5-YEAR STATE-FUNDED MAJOR CAPITAL IMPROVEMENT PROGRAM

  20. Economic and Conservation Evaluation of Capital Renovation Projects: Hidalgo County Irrigation District No. 2 (San Juan) - Rehabilitation of Alamo Main Canal - Final

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.

    Initial construction costs and net annual changes in operating and maintenance expenses are identified for a two-component capital renovation project proposed by Hidalgo County Irrigation District No. 2, to the U. S. Bureau of Reclamation (USBR...

  1. Economic and Conservation Evaluation of Capital Renovation Projects: Edinburg Irrigation District Hidalgo County No. 1 - 72" Pipeline Replacing Delivery Canal and Multi-Size Pipeline Replacing Delivery Canal

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.; Ellis, John R.

    TR-205 November 2002 Economic and Conservation Evaluation of Capital Renovation Projects: Edinburg Irrigation District Hidalgo County No. 1 – 72" Pipeline Replacing Delivery Canal and Multi-Size Pipeline Replacing Delivery Canal M. Edward Rister... Ronald D. Lacewell Allen W. Sturdivant John R. C. Robinson Michael C. Popp John R. Ellis Texas Water Resources Institute Texas A&M University TR-205 November 2002 Economic and Conservation Evaluation of Capital Renovation Projects: Edinburg...

  2. U.S. Department of Energy Acquisition Strategy Guide for Capital Assets Projects

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-07-22T23:59:59.000Z

    This Guide serves as a tool for federal project directors developing a project acquisition strategy document. No cancellation.

  3. 2014 State Capital Request Board of Regents

    E-Print Network [OSTI]

    Weiblen, George D

    on FY 2015 capital budget Financial Summary Request dollars in thousands Location Project Total State U

  4. LOCA feasibility study of Almaraz NPP 110% power up-rate

    SciTech Connect (OSTI)

    Orive, Raul; Gallego, Ines; Garcia, Pablo; Concejal, Alberto [IBERDROLA Ingenieria y Construccion S.A.U. Avda. de Burgos, 8B, 28036 Madrid (Spain); Martinez-Murillo, Juan-Carlos [Almaraz-Trillo AIE, Avda. de Manoteras , 28050 Madrid (Spain)

    2006-07-01T23:59:59.000Z

    Knowledge about accidents and fuel response in extreme conditions has progressed in parallel with the simulation tools development and consequently results are today highly satisfactory. This fact allows nuclear power plants (NPP) to carry out optimization processes of its operation and yield improvements due to the development of new methodologies and tools. Power up-rates open a demand in areas like the analyses of Loss Of Coolant Accidents (LOCA's), which impact on plant design may limit the maximum operation power in a nuclear power plant. TRAC-PF1 is a thermal-hydraulic calculation code that allows the complete treatment of two-phase flows in balance, combining a three dimensional vessel, that simulates in detail the accident phenomena, with one dimensional components. TRAC-PF1 code capacities in the reproduction of experiments, transients and accidents have been widely proved. IBERINCO has modified the original code to develop a conservative model applicable to a 3-loop Westinghouse NPP. These circumstances have allowed Almaraz NPP to get deeper in the study of the plant behaviour during a LOCA, after a hypothetical Power Up-rate. The scope of the study includes the development of the plant model and the reproduction of several accidents with loss of coolant. These accidents have been simulated with the improved option and the conservative version of the modified code (TRAC-PF1/IBER). The limiting case at the current power is analyzed in 110% Power Up-rate conditions and different sensitivity studies are performed, focused in impact of axial power distribution, discharge coefficients and emergency core cooling system availability. These studies allow to verify the effectiveness of Almaraz NPP safety systems in LOCA scenarios to guarantee the required safety margins. (authors)

  5. Developing governmental decision strategies for determining involvement in highly uncertain, large-scale capital investment projects

    E-Print Network [OSTI]

    Golden, Robert J

    1978-01-01T23:59:59.000Z

    to the project. Finally, in order to test the model's applicability in assisting governmental decision-makers to rationally allocate resources, the model has been empirically tested by a Westinghouse proposal (concerning offshore floating nuclear power... . Classification of Models . Models as a Frame of Reference The Contextual Matrix Development of the Matrix Model Methodology Exmployed to Utilize ~ ~ ~ ~ the 27 29 30 32 33 Matrix Framework . IV. WESTINGHOUSE'S OFFSHORE FLOATING NUCLEAR POWER PLANT...

  6. Economic and Conservation Evaluation of Capital Renovation Projects: Cameron County Irrigation District No. 2 (San Benito) – Interconnect Between Canals 39 and 13-A1 and Replacement of Rio Grande Diversion Pumping Plant

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.; Ellis, John R.

    2003-01-01T23:59:59.000Z

    ’s Endorsement of RGIDECON © 1 This report contains economic and financial analyses results for a capital rehabilitation project proposed by the Cameron County Irrigation District No. 2 (a.k.a. San Benito) in the Rio Grande Basin. Readers interested...TR-212 March 2003 Economic and Conservation Evaluation of Capital Renovation Projects: Cameron County Irrigation District No. 2 (San Benito) – Interconnect Between Canals 39 and 13-A1 and Replacement of Rio Grande Diversion Pumping Plant M. Edward...

  7. Capital Project Prioritization

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office511041clothAdvanced Materials Advanced. C o w l i t z C o . C l a r8.05 CalendarINT'L.

  8. Capital Investment Tax Credit (Florida)

    Broader source: Energy.gov [DOE]

    The Capital Investment Tax Credit is an annual credit, provided for up to twenty years, against the corporate income tax. Eligible projects are those in designated high-impact portions of the...

  9. Economic and Conservation Evaluation of Capital Renovation Project: Hidalgo County Irrigation District No. 2 (San Juan) - Relining Lateral A – Preliminary

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    the efficiency of pumping plants. The economic water and energy savings analyses provide estimates of the economic costs per acre-foot of water savings and per BTU (kwh) of energy savings associated with one to five proposed capital improvement activity... at the time and is subject to an array of resource limitations. At times, District management’s best educated estimates (or that of the consulting engineer) are used to base cost and/or savings’ values well into the future. Obviously, this is imperfect...

  10. Economic and Conservation Evaluation of Capital Renovation Projects: Brownsville Irrigation District – 72" and 48" Pipeline Replacing Main Canal – Final

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    analyses provide estimates of the economic costs per acre-foot of water savings and per BTU (kwh) of energy savings associated with one to five proposed capital improvement activity(ies) (each referred to as a component). An aggregate assessment is also.... At times, District management’s best educated estimates (or that of the consulting engineer) are used to base cost and/or savings’ values well into the future. Obviously, this is imperfect, but given resource limitations, it is believed ample inquiry...

  11. The University of Northern British Columbia Five Year Capital Plan

    E-Print Network [OSTI]

    Northern British Columbia, University of

    and for the regional campuses; · To estimate the cost of the recommended capital projects and to identify preferred its scope to recommending new capital projects with an estimated cost exceeding $1M. Other yet-to- be-completed capital projects with a cost below $1M previously reported to government are listed in Appendix 2

  12. Economic and Conservation Evaluation of Capital Renovation Projects: Cameron County Irrigation District No. 2 (San Benito) - Infrastructure Rehabilitation - Final

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.; Popp, Michael C.

    of Reclamation (BOR). The proposed project involves rehabilitating 42+ miles of canals, laterals, and pipelines. Both nominal and real estimates of water and energy savings and expected economic and financial costs of those savings are identified throughout...

  13. Economic and Conservation Evaluation of Capital Renovation Projects: Cameron County Irrigation District No. 2 (San Benito) – Infrastructure Rehabilitation – Preliminary

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    of Reclamation (BOR). The proposed project involves rehabilitating 42+ miles of canals, laterals, and pipelines. Both nominal and real estimates of water and energy savings and expected economic and financial costs of those savings are identified throughout...

  14. Economic and Conservation Evaluation of Capital Renovation Projects: Brownsville Irrigation District – 72" and 54" Pipeline Replacing Main Canal – Preliminary 

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    2003-01-01T23:59:59.000Z

    ) and Bureau of Reclamation (BOR). The proposed project involves constructing a 72" and 54" pipeline to replace 2.29 miles of the “Main Canal.” Both nominal and real estimates of water and energy savings and expected economic and financial costs of those...

  15. Economic and Conservation Evaluation of Capital Renovation Projects: Brownsville Irrigation District – 72" and 48" Pipeline Replacing Main Canal – Final 

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    2003-01-01T23:59:59.000Z

    ) and Bureau of Reclamation (BOR). The proposed project involves constructing a 72" and 48" pipeline to replace 2.31 miles of the “Main Canal.” Both nominal and real estimates of water and energy savings and expected economic and financial costs of those...

  16. Economic and Conservation Evaluation of Capital Renovation Projects: Brownsville Irrigation District – 72" and 54" Pipeline Replacing Main Canal – Preliminary

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    ) and Bureau of Reclamation (BOR). The proposed project involves constructing a 72" and 54" pipeline to replace 2.29 miles of the “Main Canal.” Both nominal and real estimates of water and energy savings and expected economic and financial costs of those...

  17. 11.1 REQUESTS FOR REMODELING OR PROJECT/CONSTRUCTION SERVICES Any plans for building remodeling must be approved by the Provost before Capital Planning and

    E-Print Network [OSTI]

    for preliminary approval and permission to obtain a conceptual cost estimate from Capital Planning and Construction. Once the cost estimate is completed, the entire request will be sent to the Space Committee must be approved by the Provost before Capital Planning and Construction or Facilities Management can

  18. Economic and Conservation Evaluation of Capital Renovation Projects: Harlingen Irrigation District Cameron County No. 1 Canal Meters and Telemetry Equipment, Impervious-Lining of Delivery Canals, Pipelines Replacing Delivery Canals, and On-Farm Delivery-Site Meters

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.; Ellis, John R.

    TR-202 October 2002 Economic and Conservation Evaluation of Capital Renovation Projects: Harlingen Irrigation District Cameron County No. 1 – Canal Meters and Telemetry Equipment, Impervious-Lining of Delivery Canals, Pipelines Replacing Delivery... Canals, and On-Farm Delivery-Site Meters M. Edward Rister Ronald D. Lacewell Allen W. Sturdivant John R. C. Robinson Michael C. Popp John R. Ellis Texas Water Resources Institute Texas A&M University TR-202 October 2002 Economic and Conservation...

  19. Cost of a Ride: The Effects of Densities on Fixed-Guideway Transit Ridership and Capital Costs

    E-Print Network [OSTI]

    Guerra, Erick; Cervero, Robert

    2010-01-01T23:59:59.000Z

    rail transit capital cost study update final. Washington,2005). Managing Capital Costs of Major Federally Fundedin US rail transit project cost overrun. Transportation

  20. Project Fact Sheet Project Update

    E-Print Network [OSTI]

    & Figures: Budget: £51,074,000 Funding Source: Capital Plan Construction Project Programme: Start on SiteProject Fact Sheet Project Update: Project Brief: The concept of the new scheme is to redevelop Gardens project http://www.imperial.ac.uk/princesgardens/ Construction Project Team: Project Facts

  1. Networks, Information & Social Capital

    E-Print Network [OSTI]

    Aral, Sinan

    2008-01-26T23:59:59.000Z

    This paper investigates how information flows enable social networks to constitute social capital. By analyzing

  2. Principal Associate Director - Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)IntegratedSpeedingTechnical News, information andNetarchive Princetonbe

  3. Delegation of Acquisition Executive Authority for Capital Asset...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    PortsmouthPaducah Project Office by murphie DelegationAcquisitionExecAuthorityCapitalAssetProjPPPO-MurphieEM.pdf -- PDF Document, 284 KB ID: NA Type: Organizations' Assignment...

  4. Planning and Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Rates Planning Ten-Year Capital Program Projects Lovell-Yellowtail Transmission Line Rebuild project Studies WACM Wind production summary overview (Oct. 2006)...

  5. Economic and Conservation Evaluation of Capital Renovation Projects: Hidalgo County Irrigation District No. 2 (San Juan) – 48" Pipeline Replacing Wisconsin Canal – Preliminary

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    improving the efficiency of pumping plants. The economic water and energy savings analyses provide estimates of the economic costs per acre-foot of water savings and per BTU (kwh) of energy savings associated with one to five proposed capital improvement... limitations. At times, District management’s best educated estimates (or that of the consulting engineer) are used to base cost and/or savings’ values well into the future. Obviously, this is imperfect, but given resource limitations, it is believed ample...

  6. Project Management Lessons Learned

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-08-05T23:59:59.000Z

    The guide supports DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, and aids the federal project directors and integrated project teams in the execution of projects.

  7. Economic and Conservation Evaluation of Capital Renovation Projects: United Irrigation District of Hidalgo County (United) – Rehabilitation of Main Canal, Laterals, and Diversion Pump Station – Final

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.

    savings analyses provide estimates of the economic costs per acre-foot of water savings and per BTU (kwh) of energy savings associated with one to five proposed capital improvement activity(ies) (each referred to as a component). An aggregate assessment... publications. This analysis report is based on the best information available at the time and is subject to an array of2 resource limitations. At times, District management’s best educated estimates (or that of the consulting engineer) are used to base cost...

  8. Capital Access Program (Vermont)

    Broader source: Energy.gov [DOE]

    The Capital Access Program provides loan guarantees to small businesses seeking access to commercial credit. Premiums paid by the borrower and matched by Vermont Economic Development Authority fund...

  9. Health Capital and Finance

    E-Print Network [OSTI]

    Holland, Sara Bryant

    2010-01-01T23:59:59.000Z

    Capital and Finance by Sara Bryant Holland A dissertationCopyright 2010 by Sara Bryant Holland Abstract Healthand Finance by Sara Bryant Holland Doctor of Philosophy in

  10. Capital Reporting Company Quadrennial ...

    Office of Environmental Management (EM)

    3 05-27-2014 (866) 448 - DEPO www.CapitalReportingCompany.com 2014 1 QUADRENNIAL ENERGY REVIEW STAKEHOLDER MEETING 3 PETROLEUM TRANSMISSION, STORAGE AND DISTRIBUTION ISSUES...

  11. Capital Reporting Company Quadrennial ...

    Broader source: Energy.gov (indexed) [DOE]

    (866) 448 - DEPO www.CapitalReportingCompany.com 2014 1 UNITED STATES DEPARTMENT OF ENERGY OFFICE OF ENERGY POLICY AND SYSTEMS ANALYSIS QUADRENNIAL ENERGY REVIEW STAKEHOLDER...

  12. Capital Reporting Company Quadrennial ...

    Broader source: Energy.gov (indexed) [DOE]

    - DEPO www.CapitalReportingCompany.com 2014 1 UNITED STATE OF AMERICA DEPARTMENT OF ENERGY ---: : IN RE: : : QUADRENNIAL ENERGY REVIEW : : NEW...

  13. Project Fact Sheet Project Brief

    E-Print Network [OSTI]

    .union.ic.ac.uk/marketing/building Construction Project Team: Project Facts & Figures: Budget: £1,400,000 Funding Source: Capital PlanProject Fact Sheet Project Brief: In the first phase of the Union Building re that it adapts to meet the needs of a changing student body. The re-development plans are grounded in a full

  14. Economic and Conservation Evaluation of Capital Renovation Projects: Hidalgo County Irrigation District No. 2 (San Juan) - 48" Pipeline Replacing Wisconsin Canal - Final 

    E-Print Network [OSTI]

    Rister, Edward; Lacewell, Ronald; Sturdivant, Allen; Robinson, John; Popp, Michael

    2003-01-01T23:59:59.000Z

    Development Bank (NADBank) and Bureau of Reclamation. The proposed project involves constructing a 48" pipeline to replace the “Wisconsin Canal.” Both nominal and real estimates of water and energy savings and expected economic and financial costs of those...

  15. Economic and Conservation Evaluation of Capital Renovation Projects: Edinburg Irrigation District Hidalgo County No. 1 - 72" Pipeline Replacing Delivery Canal and Multi-Size Pipeline Replacing Delivery Canal 

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.; Ellis, John R.

    2002-01-01T23:59:59.000Z

    ). Both nominal and real, expected economic and financial costs of water and energy savings are identified throughout the anticipated useful lives for both components of the proposed project (i.e., 72" pipeline replacing a segment of delivery canal along...

  16. Economic and Conservation Evaluation of Capital Renovation Projects: Hidalgo County Irrigation District No. 2 (San Juan) – 48" Pipeline Replacing Wisconsin Canal – Preliminary 

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    2003-01-01T23:59:59.000Z

    Development Bank (NADBank) and Bureau of Reclamation. The proposed project involves constructing a 48" pipeline to replace the “Wisconsin Canal.” Both nominal and real estimates of water and energy savings and expected economic and financial costs of those...

  17. Economic and Conservation Evaluation of Capital Renovation Projects: Hidalgo County Irrigation District No. 2 (San Juan) - 48" Pipeline Replacing Wisconsin Canal - Final

    E-Print Network [OSTI]

    Rister, Edward; Lacewell, Ronald; Sturdivant, Allen; Robinson, John; Popp, Michael

    Development Bank (NADBank) and Bureau of Reclamation. The proposed project involves constructing a 48" pipeline to replace the “Wisconsin Canal.” Both nominal and real estimates of water and energy savings and expected economic and financial costs of those...

  18. Pennsylvania Capital Access Program (Pennsylvania)

    Broader source: Energy.gov [DOE]

    The Pennsylvania Capital Access Program provides loan guarantees for all businesses for the purchase of land, buildings, machinery, equipment and working capital through participating banks. The...

  19. Virginia Capital Access Program (Virginia)

    Broader source: Energy.gov [DOE]

    The Virginia Capital Access Program (CAP), in partnership with Virginia’s Small Business Financing Authority, provides access to capital for small businesses. Businesses must apply to...

  20. Capital Access Program (CAP) (Michigan)

    Broader source: Energy.gov [DOE]

    The Capital Access Program (CAP), utilizes public resources to generate private financing for small business in Michigan seeking access to capital. Funding from the Michigan Strategic Fund is...

  1. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    capital asset line item projects (less than 50 million) are fully funded in one Fiscal Year (one Appropriation). NA NA Policy memorandum drafted and in review 12. Cost...

  2. Calculation Method for the Projection of Future Spent Nuclear Fuel Discharges

    SciTech Connect (OSTI)

    B. McLeod

    2002-02-28T23:59:59.000Z

    This report describes the calculation method developed for the projection of future utility spent nuclear fuel (SNF) discharges in regard to their timing, quantity, burnup, and initial enrichment. This projection method complements the utility-supplied RW-859 data on historic discharges and short-term projections of SNF discharges by providing long-term projections that complete the total life cycle of discharges for each of the current U.S. nuclear power reactors. The method was initially developed in mid-1999 to update the SNF discharge projection associated with the 1995 RW-859 utility survey (CRWMS M&O 1996). and was further developed as described in Rev. 00 of this report (CRWMS M&O 2001a). Primary input to the projection of SNF discharges is the utility projection of the next five discharges from each nuclear unit, which is provided via the revised final version of the Energy Information Administration (EIA) 1998 RW-859 utility survey (EIA 2000a). The projection calculation method is implemented via a set of Excel 97 spreadsheets. These calculations provide the interface between receipt of the utility five-discharge projections that are provided in the RW-859 survey, and the delivery of projected life-cycle SNF discharge quantities and characteristics in the format requisite for performing logistics analysis to support design of the Civilian Radioactive Waste Management System (CRWMS). Calculation method improvements described in this report include the addition of a reactor-specific maximum enrichment-based discharge burnup limit. This limit is the consequence of the enrichment limit, currently 5 percent. which is imposed as a Nuclear Regulatory Commission (NRC) license condition on nuclear fuel fabrication plants. In addition, the calculation method now includes the capability for projecting future nuclear plant power upratings, consistent with many such recent plant uprates and the prospect of additional future uprates. Finally. this report summarizes the results of the 2002 Reference SNF Discharge Projection.

  3. Webinar Announcement: Accessing Private Capital for Clean Energy...

    Open Energy Info (EERE)

    2012 - 10:44 On November 19th, the Clean Energy Solutions Center will host a training webinar on Financing Clean Energy Projects with Private Capital. The webinar content...

  4. Road Map to Capitalization of Power Generating Facilities

    E-Print Network [OSTI]

    Kangas, M. Y. O.

    The capital requirement in Pulp and Paper Industry projects is enormous, a new pulp mill will cost about $1 Billion Dollars. The international competition is getting stronger as countries like Indonesia, Brazil, etc., build their own industry...

  5. Federal Aviation Administration's Airport Capital Improvement Program Development Process

    E-Print Network [OSTI]

    Tener, Scott D.

    2009-12-18T23:59:59.000Z

    The Airport Capital Improvement Program (ACIP) serves as the primary tool for project planning and formulation by the Federal Aviation Administration (FAA). The FAA relies on the ACIP to serve as the basis for the distribution of Aviation Trust...

  6. Economic and Conservation Evaluation of Capital Renovation Projects: United Irrigation District of Hidalgo County (United) - Rehabilitation of Main Canal, Laterals, and Diversion Pump Station - Preliminary

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.

    project involves: installing 4.66 miles of pipeline in the Main Canal and Lateral 7N, installing 13.46 miles of pipeline in several laterals and sub-laterals, and rehabilitating the District’s Rio Grande diversion pumping plant. Both nominal and real...

  7. Texas Capital Fund (Texas)

    Broader source: Energy.gov [DOE]

    The Texas Capital Fund is designed to promote growth in rural non-entitlement areas, generally defined as cities with less than 50,000 residents or counties with less than 200,000 residents....

  8. Capital Reporting Company Quadrennial ...

    Energy Savers [EERE]

    11-2014 (866) 448 - DEPO www.CapitalReportingCompany.com 2014 1 QUADRENNIAL ENERGY REVIEW PUBLIC MEETING 10: Infrastructure Constraints Monday, August 11, 2014 New Mexico State...

  9. Capital Reporting Company Quadrennial ...

    Office of Environmental Management (EM)

    07-21-2014 (866) 448 - DEPO www.CapitalReportingCompany.com 2014 1 QUADRENNIAL ENERGY REVIEW PUBLIC MEETING 6 MONDAY, JULY 21, 2014 HELD AT: RASHID AUDITORIUM-HILLMAN CENTER...

  10. Capital Reporting Company Quadrenntial ...

    Broader source: Energy.gov (indexed) [DOE]

    Quadrenntial Energy Review 04-21-2014 (866) 448 - DEPO www.CapitalReportingCompany.com 2014 1 NEW ENGLAND REGIONAL INFRASTRUCTURE CONSTRAINTS A Public Meeting on the Quadrennial...

  11. Flexible Capital Fund (Vermont)

    Broader source: Energy.gov [DOE]

    The Vermont Sustainable Jobs Fund's Flexible Capital Fund (the “Flex Fund”) is designed for companies in Vermont's rural areas that are smaller and work on a less-than global scale, offering a...

  12. CAPITAL PROGRAMMING GUIDE SUPPLEMENT TO

    E-Print Network [OSTI]

    US Army Corps of Engineers

    Capital Plan CI Commercial Items COTS Commercial-off-the-shelf ESPC Energy Savings Performance Contract

  13. Economic and Conservation Evaluation of Capital Renovation Projects: Maverick County Water Control and Improvement District No. 1 (Eagle Pass) – Lining Main Canal – Preliminary

    E-Print Network [OSTI]

    Rister, M. Edward; Lacewell, Ronald D.; Sturdivant, Allen W.; Robinson, John R.C.; Popp, Michael C.

    is the only source of water for the City of Eagle Pass and the towns of Quemado and El Indio. Recent agricultural water use during calendar years 1994-1998 for the District has ranged from 42,677 ac-ft to 105,893 ac-ft, with the five-year average at 71,657 ac... savings forthcoming from the total project are estimated, using amortization procedures, to be 8,084 ac-ft of water per year and 2,041,095,338 BTUs (598,211 kwh) of energy per year. The calculated economic and financial cost of water savings is estimated...

  14. CAPITAL PROGRAMMING GUIDE | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    for a disciplined capital programming process, as well as techniques for planning and budgeting, acquisition, and management and disposition of capital assets. CAPITAL PROGRAMMING...

  15. 2011 Strategic Capital Discussions

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    & Us Expand News & Us Projects & Initiatives Expand Projects & Initiatives Finance & Rates Expand Finance & Rates Involvement & Outreach Expand Involvement &...

  16. CAPITAL ASSET DOCUMENT TRAINING

    E-Print Network [OSTI]

    KUALI CAPITAL ASSET MANAGEMENT DOCUMENT TRAINING Business and Financial Services, Property Management Presented by: Rachel Drenth #12;Sign On to the Training Site · CSU CAP (Campus Administration://padroni.is.colostate.edu:7778/portal/page/portal/CAPQA (THEN CHOOSE QUAL 2) · Non-production Applications: Training Kuali

  17. Capital and revenue expenditures

    E-Print Network [OSTI]

    Owens, Jack Bailey

    1948-01-01T23:59:59.000Z

    T and Charaoteristios of Various Expenditures ~ ~ 7 III. Bases for Expenditure Classifioationi ~ ~ ~ ~ ~ ~ ~ ~ r ~ ' ~ IV ~ Methods of kooountiag for Capital and Revenue Expenditure( ~ ~ I CkPITLL ERE RKVRRUm bXPLM)ITURkiS ISTRORUGTIOR kn ?ttonpt will be made... not tahe tho plass of asy asset or part of aa asset already onistiag Ln a business, but give tho already sainting fined asset ealues an a44ed physioal value whioh they did not previously possess ~ Additions rosoable original oost in that both...

  18. Capital Woodlands Project Trees for Cities

    E-Print Network [OSTI]

    the 625 square miles of urban area is a diverse natural environment of woodland, heath, wetlands, formal, by protecting woodland flora and fauna, and strengthening links between woodlands and communities - reminding residents that the natural world is not that far away. · To raise awareness and appreciation of London

  19. Florida Venture Capital Program (Florida)

    Broader source: Energy.gov [DOE]

    The Florida Venture Capital Program provides equity investments and convertible debt instruments to emerging Florida companies and companies locating in Florida with long-term growth potential. ...

  20. Information Technology Project Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-09-12T23:59:59.000Z

    This Guide provides Department of Energy recommended guidelines to ensure that the acquisition of information technology capital assets is performed in compliance with DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, dated 7-28-06. Canceled by DOE N 251.105.

  1. Weighing the Costs and Benefits of Renewables Portfolio Standards: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff; Wiser, Ryan; Bolinger, Mark

    2007-01-01T23:59:59.000Z

    data, the highest capital cost estimate in the 2010-2015multiply initial capital cost estimates by up to a factor ofand projected wind capital cost estimates from EPRI/DOE

  2. Environmental Management (EM) Cleanup Projects

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-09-24T23:59:59.000Z

    The guide supports DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, and provides guidance on environmental management cleanup projects. Canceled by DOE N 251.105.

  3. Executing major projects through Contractors

    E-Print Network [OSTI]

    McKenna, Nicholas A. (Nicholas Alan)

    2005-01-01T23:59:59.000Z

    Project based organizational structures are utilized in many industries. The firms engaged in these significant endeavors, project sponsor and contractor alike, risk both capital and reputation in the market-place with ...

  4. Human Capital Management Accountability Program

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-08-01T23:59:59.000Z

    The Order establishes requirements, roles and responsibilities for the Human Capital Management Accountability Program (HCMAP) for human resources programs and personnel and ensures that human capital activities are regulatory and procedurally compliant with Federal statutes and Departmental policies. Does not cancel other directives.

  5. Hydro Capital Asset Manager

    Broader source: Energy.gov [DOE]

    This position is located in Federal Hydro Projects, Generation Asset Management, Power Services. Additional vacancies may be filled through this vacancy announcement or if they become available.

  6. West Virginia Venture Capital (West Virginia)

    Broader source: Energy.gov [DOE]

    The West Virginia Venture Capital provides investment funds to eligible businesses stimulating economic growth and providing or retaining jobs within the state through qualified venture capital...

  7. Akeida Capital Management | Open Energy Information

    Open Energy Info (EERE)

    Akeida Capital Management Jump to: navigation, search Name: Akeida Capital Management Place: New York, New York Zip: 10036 Region: Northeast - NY NJ CT PA Area Product: Financing...

  8. Watershed Management: An Evaluation of the Mullen Slough Capital Improvement

    E-Print Network [OSTI]

    Watershed Management: An Evaluation of the Mullen Slough Capital Improvement Project Study MANAGEMENT in the School of Resource and Environmental Management Report No. 321 © Fiona Murray McNair 2003 SIMON FRASER UNIVERSITY July 2003 All rights reserved. This work may not be reproduced in whole

  9. Venture Capital Institutions and Venture Capitalists’ Investment Activities: An Empirical Study on China 

    E-Print Network [OSTI]

    Guo, Di

    2010-01-01T23:59:59.000Z

    This thesis explores institutions under which venture capital investment operates in China and whether and how these institutions affect venture capitalists’ (VCs) investment preferences, ex-ante project screening ...

  10. Florida Capital Access Program (Florida)

    Broader source: Energy.gov [DOE]

    The Florida Capital Access Program, run by the Florida Department of Economic Development, is a loan portfolio insurance program enabling lenders to make loans to credit-worthy small businesses. ...

  11. Venture Capital Program (North Dakota)

    Broader source: Energy.gov [DOE]

    The Venture Capital Program, provided by the ND Department of Commerce, is an innovative financial program that provides flexible financing through debt and equity investments for new or expanding...

  12. Nonlinear Capital Taxation Without Commitment

    E-Print Network [OSTI]

    Werning, Ivan

    We study efficient non-linear taxation of labour and capital in a dynamic Mirrleesian model incorporating political economy constraints. Policies are chosen sequentially over time, without commitment. Our main result is ...

  13. Project Project Funding Operational & Maintenance Costs Univ. Project Title GSF Brief Description of Project Location Amount Source

    E-Print Network [OSTI]

    Slatton, Clint

    Estimated Annual Amount For Amount Source STATE UNIVERSITY SYSTEM 2012-2013 Fixed Capital Outlay ProjectsProject Project Funding Operational & Maintenance Costs Univ. Project Title GSF Brief Description that will respond to the latest trends in small-group learning, technology resources, and collaboration spaces

  14. Public Project Revolving Fund (PPRF) (New Mexico)

    Broader source: Energy.gov [DOE]

    The New Mexico Finance Authority’s Public Project Revolving Fund (PPRF) funds infrastructure and capital equipment projects with low-cost and low-interest rate loans.  The key characteristics of...

  15. Capital Cooking: Order (2014-CE-23008)

    Broader source: Energy.gov [DOE]

    DOE ordered Capital Cooking Equipment, Inc. to pay a $8,000 civil penalty after finding Capital Cooking had failed to certify that certain models of cooking products comply with the applicable energy conservation standards.

  16. Fixed Capital Investment Tax Credit (Connecticut)

    Broader source: Energy.gov [DOE]

    The Fixed Capital Investment Tax Credit allows a tax credit of 5% of the amount paid for any new fixed capital investment. Companies with fewer than 800 full-time employees may take a tax credit...

  17. Essays on information technology and intangible capital

    E-Print Network [OSTI]

    Saunders, Adam

    2011-01-01T23:59:59.000Z

    This thesis consists of three essays related to information technology and intangible capital. The first essay, "Valuing IT-Related Intangible Capital," examines the value of intangible assets in the firm. Using a panel ...

  18. Public Capital, Growth and Welfare

    E-Print Network [OSTI]

    (t) + I(t) (0,1): depreciation rate. K(t+1) = (1 - )K(t) + I(t) (0,1): efficiency/governance services Private capital Rate of time preference Consumption saving decisions Investment in physical and sanitation--increase in enrolment rates (especially for girls, rural areas). 2. Electricity

  19. A Proposed Framework For Planning Deactivation And Decommissioning Engineering And Design Activities To Meet The Requirements Of DOE Order 413.3A, Program And Project Management For The Acquisition Of Capital Assets

    SciTech Connect (OSTI)

    Santos, J.K.; Gladden, J.B. [Savannah River National Laboratory (SRNL), Savannah River Site, Aiken, SC (United States); Szilagyi, A.P. [United States Department of Energy (DOE), Washington, DC (United States); Negin, C.; Urland, C. [Project Enhancement Corporation, Germantown, MD (United States)

    2008-07-01T23:59:59.000Z

    This paper applies the DOE O 413.3A Design/Engineering requirements to Deactivation and Decommissioning (D and D) projects. A list of 41 activities for which Design/Engineering is generally required and which are relevant and common to many D and D projects was generated. For several activities in this list, examples of the level of development and/or types of deliverables that might be expected at the completion of the conceptual, preliminary and final project design phases described in the Order are provided. This paper also discusses tailoring the application of the Order to a facility based on the complexity of the facility's engineered systems and the hazards existing in the facility. DOE D and D projects are expected to meet the requirements of DOE O 413.3A. For D and D engineering and design activities only, this paper provides guidance for applying these requirements to the Order. A list of 41 typical D and D engineering and design activities has been provided. The Order divides projects into conceptual, preliminary and final design phases. Development of each of the 41 activities can also be organized in conceptual, preliminary and final levels. In general, at the conceptual level project engineers should be determining the what (i.e., the scope) for each activity. At the preliminary level they should be resolving how the activity will be accomplished. At the final level, all the engineering and design details for the activity should be completed so that the activity is ready to implement in the field. It may not be appropriate that development of each individual activity correspond to the current phase of the project. For example, at CD-2 (end of the preliminary design phase) not all activities need be developed to the same level of detail. Only those that are truly significant to the project baseline must be developed to the level of detail necessary to create a reliable project baseline. (authors)

  20. Financing Co-generation Projects

    E-Print Network [OSTI]

    Young, R.

    1982-01-01T23:59:59.000Z

    profit generated by energy intensive industries will not be sufficient to provide the capital required for both normal business expansion and energy conservation projects. Debt financing for energy saving equipment will adversely impact balance sheet...

  1. Strategic Use of Human Capital | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Human Capital Strategic Use of Human Capital A report on how the DOE uses and plans to reform their use of human capital. Strategic Use of Human Capital More Documents &...

  2. Making Human Capital the Creative Core of

    E-Print Network [OSTI]

    Keinan, Alon

    . They must confront economic uncertainty, environmentalrisk,socialchangeandothervolatileforces.Toexecute on Human Capital Financial capital has lost some of its primacy as the catalyst of growth. Human capital that is constantly learning, adjusting and adapting to new technology," says Chris Collins, director of the Center

  3. Developing Renewable Energy Projects Larger Than 10 MWs at Federal...

    Broader source: Energy.gov (indexed) [DOE]

    Guide helps agency personnel navigate the complexities of developing large-scale renewable energy projects and assists them in attracting the necessary private capital to complete...

  4. Yellowstone Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnualProperty Edit withTianlinPapers HomeXuanen Shiziguan Hydropower CoYasunaga Wire SawCapital Jump

  5. Osmosis Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation, searchOfRoseConcernsCompany OilInformationPre-Tax ChargeOsmosis Capital Jump

  6. Capital Connections | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnual Siteof EnergyInnovation inOpen EnergyCallawayCapara Energia S A Jump to:Capital

  7. Greenview Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdfGetec AG ContractingGreenOrder JumpIowa:Greenport, NewGCA JumpGreenview Capital

  8. BEV Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnualProperty EditCalifornia: EnergyAvignon, France: Energy Resources JumpPáginas deBARCBEV Capital

  9. Arborview Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:Ezfeedflag JumpID-fTriWildcatAntrim County,Delhi (NCT),Arborview Capital Jump to: navigation,

  10. Cascadia Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnualProperty EditCalifornia:Power LPInformation 8thCalwindCaribbeanCaruthers,Cascadia Capital

  11. Renewable Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere IRaghuraji Agro Industries Pvt Ltd Jump to: navigation, searchRayreviewAl.,RenGen Energy LtdOpenCapital Place:

  12. Commons Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand JumpConceptual Model, clickInformationNew York:GovernorCommons Capital Jump to: navigation, search

  13. The Ohio Capital Access Program (OCAP) (Ohio)

    Broader source: Energy.gov [DOE]

    The Ohio Capital Access Program (OCAP) encourages state depository financial institutions to make loans to for-profit or nonprofit small businesses that are having difficulty obtaining business...

  14. Capital Cooking: Proposed Penalty (2014-CE-23008)

    Broader source: Energy.gov [DOE]

    DOE alleged in a Notice of Proposed Civil Penalty that Capital Cooking Equipment, Inc. failed to certify cooking products as compliant with the applicable energy conservation standards.

  15. Capital Investment Incentive (Nova Scotia, Canada)

    Broader source: Energy.gov [DOE]

    The Capital Investment Incentive (CII) is part of the Productivity Investment Program as outlined in the economic growth plan for Nova Scotia, jobsHere.

  16. UCSC Major Capital Improvement Projects -Anticipated Construction Times Showing Total Project Costs 11/20/07 2007-8 July 2008-9 July 2009-10 July 2010-11 July 2011-12 July 2012-13 July 2013-14 July

    E-Print Network [OSTI]

    California at Santa Cruz, University of

    & analysis $ 5.0 M Project scope, budget, & schedule to be determined Planning & design $ 108.07 M Phase 1-State-funded projects $ 35.45 M Planning & design $ 77.91 M Core heating water, electrical & natural gas $ 7.42 M & Safety Facility Improvements 8 9 7 11 State-funded projects Silicon Valley Center Planning & design

  17. Revealing the Hidden Value that the Federal Investment Tax Credit and Treasury Cash Grant Provide To Community Wind Projects

    E-Print Network [OSTI]

    Bolinger, Mark A.

    2011-01-01T23:59:59.000Z

    third of the installed cost of a wind project, and thereforeto 95% of the total costs of a wind project qualify for 5-depending on the wind project’s capital cost and capacity

  18. Corporate Venture Capital (CVC) Seeking Innovation and

    E-Print Network [OSTI]

    , Technology Innovation Program, National Institute of Standards and Technology #12;Corporate Venture Capital, Deputy Director Technology Innovation Program Marc G. Stanley, Director #12;ii Acknowledgments T his policymakers in the role of corporate venture capital (CVC) in technology innovation. The research included

  19. Avoided Gigawatts Through Utility Capital Recovery Fees

    E-Print Network [OSTI]

    Frosenfeld, A. N.; Verdict, M. E.

    1985-01-01T23:59:59.000Z

    structure is possible through the use of capital recovery fees for new electric meter hookups similar to those commonly used for new water and wastewater hookups where the developer/owner is required to capitalize the marginal cost of new demand. By giving...

  20. Trade and Capital Flows: A Financial Frictions Perspective

    E-Print Network [OSTI]

    Antràs, Pol

    The classical Heckscher?Ohlin?Mundell paradigm states that trade and capital mobility are substitutes in the sense that trade integration reduces the incentives for capital to flow to capital?scarce countries. In this paper ...

  1. Best Practices for Controlling Capital Costs in Net Zero Energy...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Best Practices for Controlling Capital Costs in Net Zero Energy Design and Construction - 2014 BTO Peer Review Best Practices for Controlling Capital Costs in Net Zero Energy...

  2. Accessing Low-Cost Capital Through Securitization (Poster)

    SciTech Connect (OSTI)

    Mendelsohn, M.

    2014-10-01T23:59:59.000Z

    Poster for Solar Power International conference presents information on NREL's effort to open capital markets through securitization via Solar Access to Public Capital (SAPC) working group's efforts.

  3. Preliminary Project Execution Plan for the Remote-Handled Low-Level Waste Disposal Project

    SciTech Connect (OSTI)

    David Duncan

    2011-05-01T23:59:59.000Z

    This preliminary project execution plan (PEP) defines U.S. Department of Energy (DOE) project objectives, roles and responsibilities of project participants, project organization, and controls to effectively manage acquisition of capital funds for construction of a proposed remote-handled low-level waste (LLW) disposal facility at the Idaho National Laboratory (INL). The plan addresses the policies, requirements, and critical decision (CD) responsibilities identified in DOE Order 413.3B, 'Program and Project Management for the Acquisition of Capital Assets.' This plan is intended to be a 'living document' that will be periodically updated as the project progresses through the CD process to construction and turnover for operation.

  4. Electric power substation capital costs

    SciTech Connect (OSTI)

    Dagle, J.E.; Brown, D.R.

    1997-12-01T23:59:59.000Z

    The displacement or deferral of substation equipment is a key benefit associated with several technologies that are being developed with the support of the US Department of Energy`s Office of Utility Technologies. This could occur, for example, as a result of installing a distributed generating resource within an electricity distribution system. The objective of this study was to develop a model for preparing preliminary estimates of substation capital costs based on rudimentary conceptual design information. The model is intended to be used by energy systems analysts who need ``ballpark`` substation cost estimates to help establish the value of advanced utility technologies that result in the deferral or displacement of substation equipment. This cost-estimating model requires only minimal inputs. More detailed cost-estimating approaches are recommended when more detailed design information is available. The model was developed by collecting and evaluating approximately 20 sets of substation design and cost data from about 10 US sources, including federal power marketing agencies and private and public electric utilities. The model is principally based on data provided by one of these sources. Estimates prepared with the model were compared with estimated and actual costs for the data sets received from the other utilities. In general, good agreement (for conceptual level estimating) was found between estimates prepared with the cost-estimating model and those prepared by the individual utilities. Thus, the model was judged to be adequate for making preliminary estimates of typical substation costs for US utilities.

  5. Capitalize on Existing Assets with Demand Response

    E-Print Network [OSTI]

    Collins, J.

    2008-01-01T23:59:59.000Z

    Industrial facilities universally struggle with escalating energy costs. EnerNOC will demonstrate how commercial, industrial, and institutional end-users can capitalize on their existing assets—at no cost and no risk. Demand response, the voluntary...

  6. Lining Over Refractory - Conserve Energy and Capital

    E-Print Network [OSTI]

    Jost, M. L.; Barrows, G. L.

    1980-01-01T23:59:59.000Z

    .~. LINING OVER REFRACTORY - CONSERVE ENERGY & CAPITAL by Mark L. Jost Gerald L. Barrows The Carborundum Company Niagara Falls, New York INTRODUCTION Companies operating industrial heating equip Advantages ment find themselves coming under...

  7. An Introduction to Venture Capital Granite representatives

    E-Print Network [OSTI]

    Anderson, Richard

    May 2006 An Introduction to Venture Capital #12;2 Granite representatives Sam Kingsland ­ Managing;3 Introduction to Granite Ventures Founded in 1992 Granite has 9 investment professionals Over $1B under

  8. North Carolina Capital Access Program (North Carolina)

    Broader source: Energy.gov [DOE]

    The North Carolina Capital Access Program provides matching reserve funds for business loans that are beyond the traditional lending means of a lender’s usual standards. The average CAP loan is ...

  9. 2011-2015 Human Capital Management Plan

    Broader source: Energy.gov [DOE]

    The Office of Legacy Management (LM) needs skilled and engaged staff to accomplish our mission and carry out our responsibilities to the American people. This Human Capital Management Plan (HCMP or...

  10. The Production of Child Human Capital: Endowments, Investments and Fertility

    E-Print Network [OSTI]

    Barrett, Jeffrey A.

    The Production of Child Human Capital: Endowments, Investments and Fertility Anna Aizer Brown the human capital production function. Exploiting an exogenous source of investment, the launch of Head of the production of human capital also support an important role played by early human capital which is largely

  11. Favors from Facebook Friends: Unpacking Dimensions of Social Capital

    E-Print Network [OSTI]

    Michigan, University of

    capital [5, 14, 19]. Social capital is a conceptual framework that considers the resources held by thoseFavors from Facebook Friends: Unpacking Dimensions of Social Capital Yumi Jung, Rebecca Gray]@umich.edu ABSTRACT Past research has demonstrated a link between perceptions of social capital and use of the popular

  12. DegreeinMasters CapitalProjectsSupplyChain

    E-Print Network [OSTI]

    Bolding, M. Chad

    of Quality Discussions of selected topics from quality control, total quality management, and Six Sigma, and maintain a quality home-life, as well. Students report that this balance results in an enjoyable learning to be considered for admission. For more information, see our website at About the Program 10 total courses 3

  13. Memo Issuance of EM Capital and Major Operating Project Standard...

    Office of Environmental Management (EM)

    CNS Distribution David A. Brockman, Manager, Richland Operations Office (RL) Shirley Olinger, Manager, Office of River Protection (ORP) Jack Craig, Acting Manager, Savannah River...

  14. 2015-05-14 Capital Asset Project List.xls

    Energy Savers [EERE]

    Treatment Facility 9302016 Active CD-1 244,000,000 Oak Ridge Office Underground Ventilation System (UVS) 6302016 Active CD-0 309,000,000 Waste Isolation Pilot Plant...

  15. DOE executes a diverse portfolio of capital asset projects supporting...

    Broader source: Energy.gov (indexed) [DOE]

    None December 2011 12511 12811 Federal Budgeting Process in DOE 28* Richland, WA (HAMMER) Level 2 Elective 0010340015 None 12611 12811 Performance-Based Management...

  16. Implementation of Carbon Reduction in Capital Projects Introduction

    E-Print Network [OSTI]

    Chittka, Lars

    spin off companies); new plant and equipment (e.g. boiler and heating plant, electrical infrastructure with the following mandatory inclusions: a. All domestic hot water shall be delivered through solar or geothermal

  17. EM Capital Asset Project List | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: Since the YouTube|6721 Federal Register / Vol.6: Record ofRecord

  18. EM Contractors for Capital Asset Projects | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't Your Destiny:Revised FindingDepartmentDepartmentStatementEnergy EMEMof EnergyContractors

  19. Improving Capital Assets Project Documentation | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33Frequently20,000 RussianBy: Thomas P.Department of EnergyLessons LearnedU.S.Memorandum from

  20. Statement on Department of Energy's Major System Capital Asset Projects

    National Nuclear Security Administration (NNSA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOn AprilA groupTuba City,Enriched UraniumPhysical| Nationaltechnicalbefore the

  1. Facility Software Quality Assurance for Capital Project Decisions RM

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic Plan| Department of.pdf6-OPAMDepartment6 FY 2007FYFacility Software Quality

  2. Program & Project Management For The Acquisition Of Capital Assets |

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic2 OPAM615_CostNSAR - TProcuring Solar for Federal FacilitiesProducts

  3. Program & Project Management For The Acquisition Of Capital Assets |

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic2 OPAM615_CostNSAR - TProcuring Solar for Federal FacilitiesProductsDepartment

  4. 2015-07-21 Capital Asset Project List.xls

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy China 2015ofDepartment ofCBFO-13-3322(EE)DepartmentVery5Dryers; Request for

  5. Program & Project Management For The Acquisition Of Capital Assets

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOn April 23, 2014, an OHASeptember 2010 | Department of Energy ThisManagement Office of

  6. Program and Project Management for the Acquisition of Capital Assets |

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOn April 23, 2014, an OHASeptember 2010 | Department of EnergyTheTheUpdate:

  7. 2015-06-12 Capital Asset Project List.xls

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't Your Destiny: The Future of BadTHEEnergyReliability2015 Peer Review |5Dryers; RequestNumber

  8. Delegation of Acquisition Executive Authority for Capital Asset Projects at

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOEThe Bonneville Power Administration wouldDECOMPOSITIONPortal Decision SupportIntelligenceAuthorityIdaho

  9. Delegation of Acquisition Executive Authority for Capital Asset Projects at

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOEThe Bonneville Power Administration wouldDECOMPOSITIONPortal Decision

  10. Delegation of Acquisition Executive Authority for Capital Asset Projects at

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOEThe Bonneville Power Administration wouldDECOMPOSITIONPortal DecisionRichland Operations Office - DOE

  11. Delegation of Acquisition Executive Authority for Capital Asset Projects at

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOEThe Bonneville Power Administration wouldDECOMPOSITIONPortal DecisionRichland Operations Office - DOEthe Oak

  12. Program and Project Management for the Acquisition of Capital Assets -

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)IntegratedSpeedingTechnical News,Program Direction and Analysis DeputyStructure |DOE

  13. Program and Project Management for the Acquisition of Capital Assets -

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible forPortsmouth/Paducah47,193.70 Hg Mercury 35Information &ProgramProgramDOE

  14. Cogeneration Project Analysis Update

    E-Print Network [OSTI]

    Robinson, A. M.; Garcia, L. N.

    diverse factors, such as, but no limited to: Fuel Considerations, Heat System Analysis, Electric Power Considerations, Key Technical Project Considerations, and Economic Analysis. INTRODUCTION The cogeneration systems being developed for industrial... power marched upward at a higher rate than fuel, capital equipment cost, and the prime interest rate. Typical Cogeneration System One system has been chosen as typical. This is one of the cogeneration systems which have proliferated over the past...

  15. Dragonfly Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnualPropertyd8c-a9ae-f8521cbb8489 No revision| Open EnergyProject

  16. Capital gains tax treatment and the cattleman

    E-Print Network [OSTI]

    Rister, M. Edward

    1976-01-01T23:59:59.000Z

    Major Subject: Agricultural Economics CAPITAL GAINS TAX TREATMENT AND THE CATTLEMAN A Thesis by M I LTDN EDWARD R I STE R Approved as to style and content by: airman o ommi e Dr. Ronald R. Kay Head o D artment Dr. John opkin Mem er Dr. Donald... R. Levi e er Dr. Howard Hesby December 1976 ABSTRACT Capital Gains Tax Treatment and the Catt leman. (December 1976) Milton Edward Rister, B. S. , Texas ASM University Chairman of Advisory Committee: Or. Ronald D. Kay The federal tax...

  17. Capital Electric Coop, Inc | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnual Siteof EnergyInnovation inOpen EnergyCallawayCapara Energia S A Jump to:CapitalCapital

  18. Understanding Leasing Options for Energy Projects

    E-Print Network [OSTI]

    Davenport, B.

    2005-01-01T23:59:59.000Z

    UNDERSTANDING LEASING OPTIONS FOR ENERGY PROJECTS Baker Davenport Davenport Finance Company Richmond, Virginia Industrials often find it difficult to fund energy projects with internal monies. Energy projects must compete with the company...?s ?core? assets for capital dollars. Leasing can be used to overcome some of these hurdles. Topics of discussion will include several key leasing structures, with benefits and disadvantages noted. Project financing is also discussed as a way...

  19. Safeguards and Security Program and Project Management

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2013-04-18T23:59:59.000Z

    The proposed revision to this Department of Energy Guide focuses on alignment of guidance for implementing key safeguard and security components to the DOE capital asset acquisition process with the revised DOE O 413.3B, Program and Project Management for Acquisition of Capital Assets, the revised DOE O 470.4B, Safeguard and Security Program, and the new series of DOE Orders replacing the DOE M 470.4 series of manuals.

  20. Updated Capital Cost Estimates for Utility Scale Electricity

    E-Print Network [OSTI]

    Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants April 2013 Information Administration | Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants ii for Utility Scale Electricity Generating Plants ii Contents Introduction

  1. Capital Controls: Mud in the Wheels of Market Discipline

    E-Print Network [OSTI]

    Forbes, Kristin J.

    2004-03-12T23:59:59.000Z

    Widespread support for capital account liberalization in emerging markets has recently shifted to skepticism and even support for capital controls in certain circumstances. This sea-change in attitudes has been bolstered ...

  2. WORKING PAPER N 2009 -41 Migration and capital accumulation

    E-Print Network [OSTI]

    Boyer, Edmond

    , remittances, capital accumulation, rural poverty PARIS-JOURDAN SCIENCES ECONOMIQUES LABORATOIRE D. Key Words: Migration; Remittances; Capital Accumulation; Rural Poverty. Paris School of Economics (PSE) and Poverty Action Lab (J-PAL Europe), 48 Boulevard Jourdan, 75014 Paris, France. chiodi

  3. Taxation and Capital Spending Alan J. Auerbach

    E-Print Network [OSTI]

    Sadoulet, Elisabeth

    of the Federal Reserve System, October 7, 2005. #12;I. Introduction Why should macroeconomists care about of capital accumulation and hence the rate of economic growth. Current discussions of fundamental tax reform of consumption and the health of the financial sector. I limit my focus to business fixed investment

  4. A Comparative Analysis of Predicting Energy Savings from Energy Service Projects

    E-Print Network [OSTI]

    Kim, Amy A

    2014-05-01T23:59:59.000Z

    Implementation of energy service projects continue to increase as building owners are faced with higher utility bills, rigorous environmental regulations, and shrinking capital allocation for such projects. Different techniques and guidelines...

  5. A hedge fund business plan : investment theory, operations, and capital raising for Broadgates Capital Management

    E-Print Network [OSTI]

    Mills, Jeffrey David

    2014-01-01T23:59:59.000Z

    Launching a start-up hedge fund is a complex, multifaceted endeavor that requires an understanding of the interconnectivity between capital raising, investment strategy, regulation, and fund operations. The purpose of this ...

  6. Is the Insurance Cost-of-Capital Fair? Mathieu Gatumel

    E-Print Network [OSTI]

    Boyer, Edmond

    companies or on the modelling of insurance business profit and loss. We estimate a cost-of-capital rateIs the Insurance Cost-of-Capital Fair? Mathieu Gatumel CAHIER DE RECHERCHE n°2011-07 E2 Unité Mixte the Insurance Cost-of-Capital Fair? MathieuMathieuMathieuMathieu GatumelGatumelGatumelGatumel University

  7. Tier I Canada Research Chair Human Capital and Productivity

    E-Print Network [OSTI]

    Lennard, William N.

    Tier I Canada Research Chair in Human Capital and Productivity The University of Western Ontario and international candidates for a Tier I Canada Research Chair in the area of Human Capital and Productivity renowned group of economists who work on research related to human capital and productivity. This includes

  8. Can New Nuclear Power Plants be Project Financed?

    E-Print Network [OSTI]

    Taylor, Simon

    This paper considers the prospects for financing a wave of new nuclear power plants (NPP) using project financing, which is used widely in large capital intensive infrastructure investments, including the power and gas sectors, but has...

  9. Safeguards and Security for Program and Project Management

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2007-11-15T23:59:59.000Z

    This Guide provides approaches for implementing security provisions within the functional areas contained in DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets. Canceled by DOE G 413.3-3A.

  10. Sustainable Places Project/Project Connect

    E-Print Network [OSTI]

    Spillar, R.; Arguello, J.

    2013-01-01T23:59:59.000Z

    Needs and Opportunities Project Details System: Corridors and Gaps System Optimization Funding Organization All answered…at the system level ESL-KT-13-12-50 CATEE 2013: Clean Air Through Energy Efficiency Conference, San Antonio, Texas Dec. 16-18 14...1Presented to: Clean Air Trough Energy Efficiency CATEE Conference San Antonio December 18, 2013 ESL-KT-13-12-50 CATEE 2013: Clean Air Through Energy Efficiency Conference, San Antonio, Texas Dec. 16-18 2• Capital Metro jurisdiction, and prior...

  11. Detailed Execution Planning for Large Oil and Gas Construction Projects

    E-Print Network [OSTI]

    Calgary, University of

    Detailed Execution Planning for Large Oil and Gas Construction Projects Presented by James Lozon, University of Calgary There is currently 55.8 billion dollars worth of large oil and gas construction projects scheduled or underway in the province of Alberta. Recently, large capital oil and gas projects

  12. Long Branch Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere I Geothermal Pwer Plant Jump to:Landowners andLodgepole, Nebraska: EnergyLomita,Capital Jump to: navigation,

  13. Longboard Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere I Geothermal Pwer Plant Jump to:Landowners andLodgepole, Nebraska:Longboard Capital Advisors Jump to:

  14. Absolute Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnualProperty Edit withTianlinPapersWindey Wind6:00-06:00About OpenEI Jump to:Absecon, NewCapital

  15. Capital Pride 2015 | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE: Alternative FuelsNovember 13, 2014 Building America UpdateCX-001638:6BreakthroughAward |Capital

  16. IT Capital Planning | Department of Energy

    Energy Savers [EERE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directed off Energy.gov. Are you sure you want toworldPowerHome| DepartmentPumpHomeof EnergyofIT Capital

  17. Sequoia Capital Ltda | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnualProperty Edit with form HistoryRistma AG Jump638324°,Schnell ZToolsSupply ofSequoia Capital

  18. Jane Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdfGetecGtelInterias SolarJane Capital Partners Jump to: navigation, search Logo:

  19. MVP Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation, searchOfRose Bend < MHKconverter <WAG BuoyYOG <MP2 CapitalLLCMSEMUTIMVP

  20. Sindicatum Carbon Capital SCC | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:Ezfeedflag JumpID-f < RAPID‎ |Rippey JumpAirPowerSilcio SASindicatum Carbon Capital SCC

  1. Chestnut Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnual Siteof EnergyInnovation inOpenadd: ChinaInformationChestnut Capital LLC Jump to:

  2. Working Capital for Contractors | Department of Energy

    Energy Savers [EERE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnual Siteof Energy 2, 2015Visiting Strong,Women @ Energy:Terri Workers'WorkforceCapital for

  3. Mont Vista Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation, searchOfRose BendMiasole IncMinutemanVista Capital LLC Place: New York, New York

  4. New Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation, searchOfRoseConcerns Jump to:Neppel Wind PowerNevadaPennsylvania:Capital Jump to:

  5. Nimes Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation, searchOfRoseConcerns Jump to:Neppelsource History(CTI PFAN) | OpenNimes Capital

  6. Transmission Capital Limited | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:Ezfeedflag JumpID-f <MaintainedInformationThePtyTownTrama TecnoTransmission Capital

  7. Strategic Capital Investments LLC | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnualProperty Edit with formSoutheastern IL ElecStrategic Capital Investments LLC Jump to:

  8. Atlantic Ethanol Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:EzfeedflagBiomass Conversions Inc Jump to: navigation, search Name:Ethanol Capital Jump to:

  9. Conservation Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnualProperty EditCalifornia:PowerCER.png ElColumbia,2005)Conservation Capital LLC Jump to:

  10. Cora Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnualProperty EditCalifornia:PowerCER.pngRoofs and Heat Islands Jump to:Coppell, Texas:Cora Capital

  11. Prospect Capital Corporation | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere I GeothermalPotentialBiopowerSolidGenerationMethod Jump to:This propertyVolume Jump to:s)Prospect Capital

  12. RAM Capital Management Group | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere I GeothermalPotentialBiopowerSolidGenerationMethod JumpGeorgia: Energy Resources JumpRAM Capital Management

  13. Black Coral Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnual Siteof EnergyInnovation in CarbonofBiotins Energia Jump to: navigation,BirahiCoral Capital

  14. EnerTech Capital | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnualPropertyd8c-a9ae-f8521cbb8489 No revision| OpenElectromagneticElmwoodEnerSpective JumpCapital

  15. NREL Activities to Open Capital Market Investment and Bank Lending...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    to Open Capital Market Investment and Bank Lending for Solar Deployment For NREL Finance Team Website Michael Mendelsohn and John Johsi U.S. Department of Energy Washington,...

  16. New York State Capital District Regional Middle School Science...

    Office of Science (SC) Website

    New York State Capital District Regional Middle School Science Bowl National Science Bowl (NSB) NSB Home About High School Middle School Middle School Students Middle School...

  17. Credit Enhancements and Capital Markets to Fund Solar Deployment...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Credit Enhancements and Capital Markets to Fund Solar Deployment: Leveraging Public Funds to Open Private Sector Investment Michael Mendelsohn and Marley Urdanick National...

  18. Capital requirements for the transportation of energy materials: 1979 arc estimates

    SciTech Connect (OSTI)

    Not Available

    1980-08-29T23:59:59.000Z

    Summaries of transportation investment requirements through 1990 are given for the low, medium and high scenarios. Total investment requirements for the three modes and the three energy commodities can accumulate to a $46.3 to $47.0 billion range depending on the scenario. The high price of oil, following the evidence of the last year, is projected to hold demand for oil below the recent past. Despite the overall decrease in traffic some investment in crude oil and LPG pipelines is necessary to reach new sources of supply. Although natural gas production and consumption is projected to decline through 1990, new investments in carrying capacity also are required due to locational shifts in supply. The Alaska Natural Gas Transportation System is the dominant investment for energy transportation in the next ten years. This year's report focuses attention on waterborne coal transportation to the northeast states in keeping with a return to significant coal consumption projected for this area. A resumption of such shipments will require a completely new fleet. The investment estimates given in this report identify capital required to transport projected energy supplies to market. The requirement is strategic in the sense that other reasonable alternatives do not exist or that a shared load of new growth can be expected. Not analyzed or forecasted are investments in transportation facilities made in response to local conditions. The total investment figures, therefore, represent a minimum necessary capital improvement to respond to changes in interregional supply conditions.

  19. Investor Confidence Project

    E-Print Network [OSTI]

    Golden, M.

    2013-01-01T23:59:59.000Z

    Actionable Data ESL-KT-13-12-38 CATEE 2013: Clean Air Through Energy Efficiency Conference, San Antonio, Texas Dec. 16-18 Near-Term: Not Enough Deal-Flow • High Transaction Costs • Lack of Viable Origination Channels • Highly Variable Performance • Complex... Custom Projects ESL-KT-13-12-38 CATEE 2013: Clean Air Through Energy Efficiency Conference, San Antonio, Texas Dec. 16-18 Long-Term: High Cost of Capital • More equity than debt • Not enough volume to securitize • Insufficient actuarial data...

  20. Natural Capital Management: An Evolutionary Paradigm for Sustainable Restoration Investment - 13455

    SciTech Connect (OSTI)

    Koetz, Maureen T. [Koetz and Duncan LLC, Suite 30J, 355 South End Avenue, New York, NY 10280 (United States)] [Koetz and Duncan LLC, Suite 30J, 355 South End Avenue, New York, NY 10280 (United States)

    2013-07-01T23:59:59.000Z

    Unlike other forms of capital assets (built infrastructure, labor, financial capital), the supply of usable or accessible air, land, and water elements (termed Natural Capital Assets or NCA) available to enterprise processes is structurally shrinking due to increased demand and regulatory restriction. This supply/demand imbalance is affecting all forms of public and private enterprise (including Federal Facilities) in the form of encroachment, production limits, cost increases, and reduced competitiveness. Department of Energy (DOE) sites are comprised of significant stocks of NCA that function as both conserved capital (providing ecosystem services and other reserve capacity), and as natural infrastructure (supporting major Federal enterprise programs). The current rubric of 'Environmental Stewardship' provides an unduly constrained management paradigm that is focused largely on compliance process metrics, and lacks a value platform for quantifying, documenting, and sustainably re-deploying re-capitalized natural asset capacity and capability. By adopting value-based system concepts similar to built infrastructure accounting and information management, 'stewarded' natural assets relegated to liability- or compliance-focused outcomes become 're-capitalized' operational assets able to support new or expanded mission. This growing need for new accounting and management paradigms to capture natural capital value is achieving global recognition, most recently by the United Nations, world leaders, and international corporations at the Rio+20 Summit in June of 2012. Natural Capital Asset Management (NCAM){sup TM} is such an accounting framework tool. Using a quantification-based design, NCAM{sup TM} provides inventory, capacity and value data to owners or managers of natural assets such as the DOE that parallel comparable information systems currently used for facility assets. Applied to Environmental Management (EM) and other DOE program activities, the natural asset capacity and value generated by EM projects and other investment and operational programming can be recorded and then allocated to mission and/or ecosystem needs as part of overall site, complex, and Federal decision-making. NCAM{sup TM} can also document post-restoration asset capability and value for use in weighing loss mitigation and ecosystem damage claims arising from past operational activities. A prototype NCAM{sup TM} evaluation developed at the Savannah River Site (SRS) demonstrates use of this framework as an advanced paradigm for NCA accounting and decision-making for the larger DOE complex and other enterprise using natural capital in operations. Applying a quantified value paradigm, the framework catalogues the results of activities that sustain, restore, and modernize natural assets for enterprise-wide value beyond that of compliance milestones. Capturing and assigning recapitalization value using NCAM{sup TM} concepts and tools improves effective reuse of taxpayer-sustained assets, records ecosystem service value, enables mission and enterprise optimization, and assures the sustainability of shared natural capital assets in regional pools vital to both complex sites and local and regional economies. (authors)

  1. U.S. Department of Energy Project Review Guide for Capital Asset Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What'sis Taking Over OurThe Iron Spin Transition in2,EHSS A-Zandofpoint motional%^6 Annual U.S. N- DOE

  2. Quantifying capital goods for waste incineration

    SciTech Connect (OSTI)

    Brogaard, L.K., E-mail: lksb@env.dtu.dk [Department of Environmental Engineering, Building 115, Technical University of Denmark, DK-2800 Kongens Lyngby (Denmark); Riber, C. [Ramboll, Consulting Engineers, Hannemanns Allé 53, DK-2300 Copenhagen S (Denmark); Christensen, T.H. [Department of Environmental Engineering, Building 115, Technical University of Denmark, DK-2800 Kongens Lyngby (Denmark)

    2013-06-15T23:59:59.000Z

    Highlights: • Materials and energy used for the construction of waste incinerators were quantified. • The data was collected from five incineration plants in Scandinavia. • Included were six main materials, electronic systems, cables and all transportation. • The capital goods contributed 2–3% compared to the direct emissions impact on GW. - Abstract: Materials and energy used for the construction of modern waste incineration plants were quantified. The data was collected from five incineration plants (72,000–240,000 tonnes per year) built in Scandinavia (Norway, Finland and Denmark) between 2006 and 2012. Concrete for the buildings was the main material used amounting to 19,000–26,000 tonnes per plant. The quantification further included six main materials, electronic systems, cables and all transportation. The energy used for the actual on-site construction of the incinerators was in the range 4000–5000 MW h. In terms of the environmental burden of producing the materials used in the construction, steel for the building and the machinery contributed the most. The material and energy used for the construction corresponded to the emission of 7–14 kg CO{sub 2} per tonne of waste combusted throughout the lifetime of the incineration plant. The assessment showed that, compared to data reported in the literature on direct emissions from the operation of incinerators, the environmental impacts caused by the construction of buildings and machinery (capital goods) could amount to 2–3% with respect to kg CO{sub 2} per tonne of waste combusted.

  3. Cost of a Ride: The Effects of Densities on Fixed-Guideway Transit Ridership and Capital Costs

    E-Print Network [OSTI]

    Guerra, Erick; Cervero, Robert

    2010-01-01T23:59:59.000Z

    transit – exceeded capital cost estimates by 40% duringfound that capital costs exceeded estimates by an averagesystems. We estimate the total capital cost, average weekday

  4. Does imperfect competition foster capital accumulation in a developing economy ?

    E-Print Network [OSTI]

    Boyer, Edmond

    Does imperfect competition foster capital accumulation in a developing economy ? Pascal Belan competition and capital accumulation in a dual economy, with traditional and modern sectors and two types. Capitalists accumulate wealth in the modern sector. The economy is open to cap- ital flows, but capitalists

  5. A Two State Capital Asset Pricing Model Moshe Fridman

    E-Print Network [OSTI]

    as Hidden Markov Models (HMM). We apply the model to monthly return data for three oil industry corporation expected returns on capital assets investments with ex- pected market returns. Under the model, the returnA Two State Capital Asset Pricing Model Moshe Fridman Institute for Mathematics and its

  6. Valuing Rail Transit: Comparing Capital and Operating Costs to Consumer Benefits

    E-Print Network [OSTI]

    Guerra, Erick

    2010-01-01T23:59:59.000Z

    years gives an annual capital cost estimate of $321 million,further adjust the capital cost estimates for these systemscosts. In order to estimate capital costs for five systems

  7. On the relation between expected returns and implied cost of capital

    E-Print Network [OSTI]

    Hughes, John; Liu, Jing; Liu, Jun

    2009-01-01T23:59:59.000Z

    coef?cient estimate on implied cost of capital to be biased.the implied cost of capital literature estimates of the exestimates of ex ante risk premiums inferred from implied cost of capital

  8. Electricity Market Module

    Annual Energy Outlook 2013 [U.S. Energy Information Administration (EIA)]

    added throughout the projection, excluding the capacity already planned and under construction. The case also assumes that only those capacity uprates reported to EIA will be...

  9. Risks and decision making in development of new power plant projects

    E-Print Network [OSTI]

    Kristinsdottir, Asbjorg

    2012-01-01T23:59:59.000Z

    Power plant development projects are typically capital intensive and subject to a complex network of interconnected risks that impact development's performance. Failure to develop a power plant to meet performance constraints ...

  10. Factors to improve project performance : lessons from a Chilean urban agriculture program

    E-Print Network [OSTI]

    Scott, Maggie, 1975-

    2003-01-01T23:59:59.000Z

    This thesis investigates a Chilean urban agriculture project that has been underway for more than twenty years in Tome, a small coastal town located near the regional capital of Concepcion. Initiated in the early 1980s by ...

  11. Validation of Energy Efficiency Projects: Can You Run Effective Energy Management Programs Without It?

    E-Print Network [OSTI]

    Martin, V.; Falk, M. A.

    would have been". Since competition exists within organizations for limited capital resources, project approval is based on the principle that the short or long term benefits of a specific upgrade exceed the investment potential of other proposed...

  12. Quick Estimate of IRR From Capital Estimate Ratios 

    E-Print Network [OSTI]

    Larson, R. J.

    1985-01-01T23:59:59.000Z

    Value of a unit of capital = $821 / $1000 of capital Table III Net Present Value of a Unit of Revenue (or Savings; unit is $1000) TilDe year 0 1 2 3 4 5 6 Cash Flow (after $ 0 520 562 606 655 707 764 Taxes) Discounted Cash $ 0 452 425 399 375... proposes to invest $3500 to achieve SaVings of $1300 (b.t) in the first year of operation, economically attractive? Evaluations Criteria: Investment Equivalent of $1 of Savings $2.84. Solution: Maximum Capital allowed; $1300' $2.84 = $3 Since...

  13. The Mississippi CCS Project

    SciTech Connect (OSTI)

    Doug Cathro

    2010-09-30T23:59:59.000Z

    The Mississippi CCS Project is a proposed large-scale industrial carbon capture and sequestration (CCS) project which would have demonstrated advanced technologies to capture and sequester carbon dioxide (CO{sub 2}) emissions from industrial sources into underground formations. Specifically, the Mississippi CCS Project was to accelerate commercialization of large-scale CO{sub 2} storage from industrial sources by leveraging synergy between a proposed petcoke to Substitute Natural Gas (SNG) plant that is selected for a Federal Loan Guarantee and would be the largest integrated anthropogenic CO{sub 2} capture, transport, and monitored sequestration program in the U.S. Gulf Coast Region. The Mississippi CCS Project was to promote the expansion of enhanced oil recovery (EOR) in the Mississippi, Alabama and Louisiana region which would supply greater energy security through increased domestic energy production. The capture, compression, pipeline, injection, and monitoring infrastructure would have continued to sequester CO{sub 2} for many years after the completion of the term of the DOE agreement. The objectives of this project were expected to be fulfilled through two distinct phases. The overall objective of Phase 1 was to develop a fully definitive project basis for a competitive Renewal Application process to proceed into Phase 2 - Design, Construction and Operations. Phase 1 included the studies that establish the engineering design basis for the capture, compression and transportation of CO{sub 2} from the MG SNG Project, and the criteria and specifications for a monitoring, verification and accounting (MVA) plan at the Soso oil field in Mississippi. The overall objective of Phase 2, was to execute design, construction and operations of three capital projects: the CO{sub 2} capture and compression equipment, the Mississippi CO{sub 2} Pipeline to Denbury's Free State Pipeline, and an MVA system at the Soso oil field.

  14. Corporate intellectual capital reporting: the case of Germany 

    E-Print Network [OSTI]

    Zerr, Viktoria

    2013-11-26T23:59:59.000Z

    This study investigates potential motivations for intellectual capital (IC) reporting in management reports of 428 German companies for the accounting year 2010. To infer motivations, agency theory and legitimacy theory ...

  15. Small Business Venture Capital Tax Credit Program (Manitoba, Canada)

    Broader source: Energy.gov [DOE]

    The Small Business Venture Capital Tax Credit Program (SBVCTC) assists eligible small corporations to issue new equity to primarily new investors. The small corporation will be able to issue from ...

  16. Tenant-in-common capital in value added transactions

    E-Print Network [OSTI]

    Smith, Jared Steven

    2005-01-01T23:59:59.000Z

    Billions of dollars of equity is flowing into the emerging tenant-in-common (TIC) market, forcing demand for such investments to outweigh the current supply of TIC offerings. Investors seeking deferral of capital gains are ...

  17. Essays on the real and financial allocation of capital

    E-Print Network [OSTI]

    Ramírez Verdugo, Arturo

    2006-01-01T23:59:59.000Z

    This dissertation consists of three papers studying how firms allocate real and financial capital, and how taxes, the labor market and asymmetric information affect these allocation decisions. The first paper studies the ...

  18. What Matters for Financial Development? Capital Controls, Institutions, and Interactions

    E-Print Network [OSTI]

    Chinn, Menzie David; Ito, Hiro

    2005-01-01T23:59:59.000Z

    Bureaucracy Quality) FULL, LDC, and EMG: Five year panels,Mkt Turnover Private Credit LDC Stock Mkt Capital'n StockTransactions) FULL, LDC, and EMG: Five year panels, 1980-

  19. 15.391 Early Stage Capital, Fall 2003

    E-Print Network [OSTI]

    Loessberg, Shari

    15.391 examines the elements of raising early stage capital, focusing on start-up ventures and the early stages of company development. This course also prepares entrepreneurs to make the best use of outside advisors, and ...

  20. Lasting social impact : Community Development Venture Capital investing

    E-Print Network [OSTI]

    Silberberg, Hattie Paige

    2008-01-01T23:59:59.000Z

    Community Development Venture Capital Funds (CDVC) funds are an emerging group of Community Development Financial Institutions, that make equity investments in businesses in economically distressed areas. As equity investors, ...

  1. UNITED STATES AIR FORCE OUTSIDE THE NATIONAL CAPITAL REGION

    E-Print Network [OSTI]

    program in order to reduce Federal employee's contribution to traffic congestion and air pollutionUNITED STATES AIR FORCE OUTSIDE THE NATIONAL CAPITAL REGION PUBLIC TRANSPORTATION BENEFIT PROGRAM): ____________ City (Residence): __________________________State: _______________ Zip Code: ________________ Air Force

  2. When Does Information Asymmetry Affect the Cost of Capital?

    E-Print Network [OSTI]

    Armstrong, Christopher S.

    This paper examines when information asymmetry among investors affects the cost of capital in excess of standard risk factors. When equity markets are perfectly competitive, information asymmetry has no separate effect on ...

  3. Some Observations on Energy Efficiency and Capital Cost

    E-Print Network [OSTI]

    Kenney, W. F.

    1982-01-01T23:59:59.000Z

    be required. This paper explores several cases where energy efficiency was improved with no increase in total plant capital (including the energy system). Cogeneration, driver selection and direct exchange are discussed. To explore the limitations...

  4. DROWNED AND DAMMED Colonial Capitalism and Flood Control

    E-Print Network [OSTI]

    Sussex, University of

    DROWNED AND DAMMED Colonial Capitalism and Flood Control in Eastern India ROHAN D, Jawaharlal Nehru University, New Delhi. Drowned and Dammed comprehensively reconsiders the debate with physical infrastructure such as embankments, canal networks, and inevitably the Hirakud Dam. In seeking

  5. Process Integration: Designing for Energy, Capital and Operability

    E-Print Network [OSTI]

    Linnhoff, B.

    Over the last five years, significant energy savings have been achieved by several international companies using the pinch concept for heat integration. New concepts are now being added to help the designer deal with capital cost minimization...

  6. Job Maintenance and Capital Development Fund (North Carolina)

    Broader source: Energy.gov [DOE]

    The Job Maintenance and Capital Development Fund provides annual grants to businesses which are located in Development Tier I counties. The Fund is intended to encourage the retention of...

  7. Capital Taxation: Quantitative Explorations of the Inverse Euler Equation

    E-Print Network [OSTI]

    Farhi, Emmanuel

    Economies with private information provide a rationale for capital taxation. In this paper we ask what the welfare gains from following this prescription are. We develop a method to answer this question in standard general ...

  8. Fuel costs and the retirement of capital goods

    E-Print Network [OSTI]

    Goolsbee, Austan Dean

    1993-01-01T23:59:59.000Z

    This paper explores the effect that energy prices and market conditions have on the retirement rates of capital goods using new micro data on aircraft lifetimes and fuel costs. The oil shocks of the 1970s made fuel intensive ...

  9. Women in engineering conference: capitalizing on today`s challenges

    SciTech Connect (OSTI)

    Metz, S.S.; Martins, S.M. [eds.] [eds.

    1996-06-01T23:59:59.000Z

    This document contains the conference proceedings of the Women in Engineering Conference: Capitalizing on Today`s Challenges, held June 1-4, 1996 in Denver, Colorado. Topics included engineering and science education, career paths, workplace issues, and affirmative action.

  10. Project Year Project Title

    E-Print Network [OSTI]

    Gray, Jeffrey J.

    Project Year 2011-2012 Project Title Using M-Health and GIS Technology in the Field to Improve-specialized, but practically useless skill. Solution One goal of this summer's Applied Geographic Information Systems in Public lessons about observational epidemiology. Technologies Used Geographic Info System (GIS), Blackboard

  11. Project Funding

    Broader source: Energy.gov [DOE]

    Federal energy projects require funding to generate results. Carefully matching available funding options with specific project needs can make the difference between a stalled, unfunded project and a successful project generating energy and cost savings.

  12. CALIFORNIA INSTITUTE OF TECHNOLOGY CAPITAL CONSTRUCTION POLICY

    E-Print Network [OSTI]

    Goddard III, William A.

    construction, significant building exterior or landscape modifications, and major renovation projects. No new as the construction of a new building or facility at Caltech for which the total cost exceeds $3 million. "Building renovation" is defined as an upgrade to a building or facility that; materially increases the estimated

  13. An examination of the costs and critical characteristics of electric utility distribution system capacity enhancement projects

    SciTech Connect (OSTI)

    Balducci, Patrick J.; Schienbein, Lawrence A.; Nguyen, Tony B.; Brown, Daryl R.; Fathelrahman, Eihab M.

    2004-06-01T23:59:59.000Z

    This report classifies and analyzes the capital and total costs (e.g., income tax, property tax, depreciation, centralized power generation, insurance premiums, and capital financing) associated with 130 electricity distribution system capacity enhancement projects undertaken during 1995-2002 or planned in the 2003-2011 time period by three electric power utilities operating in the Pacific Northwest. The Pacific Northwest National Laboratory (PNNL), in cooperation with participating utilities, has developed a large database of over 3,000 distribution system projects. The database includes brief project descriptions, capital cost estimates, the stated need for each project, and engineering data. The database was augmented by additional technical (e.g., line loss, existing substation capacities, and forecast peak demand for power in the area served by each project), cost (e.g., operations, maintenance, and centralized power generation costs), and financial (e.g., cost of capital, insurance premiums, depreciations, and tax rates) data. Though there are roughly 3,000 projects in the database, the vast majority were not included in this analysis because they either did not clearly enhance capacity or more information was needed, and not available, to adequately conduct the cost analyses. For the 130 projects identified for this analysis, capital cost frequency distributions were constructed, and expressed in terms of dollars per kVA of additional capacity. The capital cost frequency distributions identify how the projects contained within the database are distributed across a broad cost spectrum. Furthermore, the PNNL Energy Cost Analysis Model (ECAM) was used to determine the full costs (e.g., capital, operations and maintenance, property tax, income tax, depreciation, centralized power generation costs, insurance premiums and capital financing) associated with delivering electricity to customers, once again expressed in terms of costs per kVA of additional capacity. The projects were sorted into eight categories (capacitors, load transfer, new feeder, new line, new substation, new transformer, reconductoring, and substation capacity increase) and descriptive statistics (e.g., mean, total cost, number of observations, and standard deviation) were constructed for each project type. Furthermore, statistical analysis has been performed using ordinary least squares regression analysis to identify how various project variables (e.g., project location, the primary customer served by the project, the type of project, the reason for the upgrade, size of the upgrade) impact the unit cost of the project.

  14. INL Wind Farm Project Description Document

    SciTech Connect (OSTI)

    Gary Siefert

    2009-07-01T23:59:59.000Z

    The INL Wind Farm project proposes to install a 20 MW to 40 MW wind farm on government property, consisting of approximately ten to twenty full-sized (80-meter hub height) towers with 2 MW turbines, and access roads. This includes identifying the optimal turbine locations, building access roads, and pouring the tower foundations in preparation for turbine installation. The project successfully identified a location on INL lands with commercially viable wind resources (i.e., greater than 11 mph sustained winds) for a 20 to 40 MW wind farm. Additionally, the proposed Wind Farm was evaluated against other General Plant Projects, General Purpose Capital Equipment projects, and Line Item Construction Projects at the INL to show the relative importance of the proposed Wind Farm project.

  15. Wind Capital Group | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:Ezfeedflag JumpID-fTriWildcat 1 Wind Project Jump to:Wilson Hot SpringNevada: Energy

  16. Project Title:

    Broader source: Energy.gov (indexed) [DOE]

    Repair flowline 61-66-SX-3 DOE Code: Project Lead: Wes Riesland NEPA COMPLIANCE SURVEY 291 Project Information Date: 31 12010 Contractor Code: Project Overview In order to...

  17. Developing Renewable Energy Projects Larger Than 10 MWs at Federal Facilities: Large-Scale Renewable Energy Guide

    Broader source: Energy.gov [DOE]

    Guide helps agency personnel navigate the complexities of developing large-scale renewable energy projects and assists them in attracting the necessary private capital to complete these projects. It also serves as a general resource to develop Federal employees' awareness and understanding of a project developer’s operating environment and the private sector’s awareness and understanding of the Federal environment.

  18. Systematic methodology for estimating direct capital costs for blanket tritium processing systems

    SciTech Connect (OSTI)

    Finn, P.A.

    1985-01-01T23:59:59.000Z

    This paper describes the methodology developed for estimating the relative capital costs of blanket processing systems. The capital costs of the nine blanket concepts selected in the Blanket Comparison and Selection Study are presented and compared.

  19. Interaction model of private equity and venture capital developing factors in Chile and Latin America

    E-Print Network [OSTI]

    Sevil Esteban, Ángel

    2012-01-01T23:59:59.000Z

    Private equity and venture capital (PE/VC) are efficient resource allocation systems that provide equity capital to selected entrepreneurs, industries or firms that contribute to advance the economic welfare of society. ...

  20. Program management systems for the semiconductor processing capital equipment supply chain

    E-Print Network [OSTI]

    Chandler, Thomas B. (Thomas Brian), 1970-

    2004-01-01T23:59:59.000Z

    The Capital Equipment Procurement group of Intel Corporation is responsible for developing and procuring the semiconductor processing capital equipment that is used throughout all of the company's development and manufacturing ...

  1. A credit risk model for agricultural loan portfolios under the new Basel Capital Accord

    E-Print Network [OSTI]

    Kim, Juno

    2005-08-29T23:59:59.000Z

    The New Basel Capital Accord (Basel II) provides added emphasis to the development of portfolio credit risk models. An important regulatory change in Basel II is the differentiated treatment in measuring capital requirements for the corporate...

  2. Tax Avoidance and Investment: Distinguishing the Effects of Capital Rationing and Overinvestment

    E-Print Network [OSTI]

    Mayberry, Michael 1985-

    2012-10-02T23:59:59.000Z

    I examine the relation between tax avoidance and firm investment by drawing on two capital market imperfections, adverse selection and moral hazard, to provide a link between tax avoidance and investment. Firms experiencing capital rationing because...

  3. Measuring and managing intellectual capital in the U.S. aerospace industry

    E-Print Network [OSTI]

    Siegel, Lawrence R

    2004-01-01T23:59:59.000Z

    "Intellectual capital" has been heralded in business journals as an important component for successful business development in today's economy. Intellectual capital consists of knowledge-based assets -- including people, ...

  4. Organizational Capital as a Strategic Field of Corporate Action Panagiotis Damaskopoulos, MA, PhD

    E-Print Network [OSTI]

    Corran, Ruth

    Organizational Capital as a Strategic Field of Corporate Action Panagiotis Damaskopoulos, MA, Ph factors of corporate competitiveness. The nodal concept of this framework is "organizational capital) knowledge management, and 3) their deployment for organizational learning and continuous adaptation

  5. Venture Capital and private equity in India : systems analysis and development framework

    E-Print Network [OSTI]

    Surineni, Shravan Kumar

    2012-01-01T23:59:59.000Z

    Venture Capital (VC) has been an important driver of innovation, entrepreneurship and economic growth in the U.S. and around the world for the past few decades. The astounding success of Venture Capital prompted various ...

  6. The New York Business Development Corporation (NYBDC) Loans for Working Capital (New York)

    Broader source: Energy.gov [DOE]

    The New York Business Development Corporation (NYBDC) Loans for Working Capital provides working capital for long-term needs, repayable over three to seven years. The program works with partner...

  7. Australian capital cities and Gold Coast residential property market

    E-Print Network [OSTI]

    Peters, Richard

    settings. The Chinese economy is also back on track recording strong and rising growth over the December.2 percent and South Australia at 5.7 percent. Prospects remain positive for a generally solid 2013. Buyer and seller confidence has increased although activity levels remained patchy and mixed between capital cities

  8. Human Capital Evolution and Economic Crisis: Minding `The Gap'*

    E-Print Network [OSTI]

    Royal Holloway, University of London

    and aggregate demand. Ferri and Tae (1999) argue that this over-reaction by financial institution not always be the optimal response to crisis. At certain levels of human capital, maintaining the pre was responsible for worsening the crisis and if uninterrupted would have plunged the economies further

  9. New Technology, Human Capital and Growth for Developing Countries.

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    New Technology, Human Capital and Growth for Developing Countries. Cuong Le Van, Manh-Hung Nguyen country with three sectors in economy: con- sumption goods, new technology, and education. Productivity of the con- sumption goods sector depends on new technology and skilled labor used for production of the new

  10. Optics and Fluid Dynamics Department Intellectual Capital Accounts 1998

    E-Print Network [OSTI]

    Optics and Fluid Dynamics Department Intellectual Capital Accounts 1998 Resources, production and results RISØ-R-1108(EN) Risø National Laboratory Optics and Fluid Dynamics Department Building 128 P for optical information storage, · novel schemes for spatial cryptography, and · new models for surface

  11. The Value of New Jersey's Ecosystem Services and Natural Capital

    E-Print Network [OSTI]

    The Value of New Jersey's Ecosystem Services and Natural Capital Robert Costanza Matthew Wilson services are are mainly provided by ecosystems. Examples of ecosystem services ("ecoservices") include of ecoservices in a variety of locations using a variety of valuation methods and applies them to New Jersey

  12. Housing market report Australian capital cities and Gold Coast

    E-Print Network [OSTI]

    Peters, Richard

    point to a market heating up. Historically low interest rates are the fuel to this emerging fire whichHousing market report Australian capital cities and Gold Coast residential property market February Economist Australian Property Monitors 1300 799 109 | domain.com.au The housing market is up and running

  13. Genetic and Economic Interaction in the Formation of Human Capital.

    E-Print Network [OSTI]

    Mateo, Jill M.

    Genetic and Economic Interaction in the Formation of Human Capital. The Case of Obesity Pietro by changes in the incentives to invest. I take the model to the data using the Avon Longitudinal Study regulation of food intake, and shed light on the interdependence between genes and economic choices regarding

  14. Tax policies, vintage capital, and exit and entry of plants

    E-Print Network [OSTI]

    Chang, Shao-Jung

    2006-04-12T23:59:59.000Z

    caused by different types of shocks. The simulation method used here is linear approximation. My results show that in the steady-state economy, given a fixed level of gov- ernment expenditure and a zero property tax rate, the capital-income tax rate...

  15. Brief description of Valuing Intellectual Capital, Multinationals and Taxhavens

    E-Print Network [OSTI]

    Pratt, Vaughan

    methods for measuring the value of intangible assets within their company Author is an emeritus professor at Stanford University and a leading consultant on IP valuation Valuing Intellectual Capital provides readers that illustrates how large corporations need to measure the worth of their intangible assets. Each method

  16. Online Social Network Sites and the Concept of Social Capital

    E-Print Network [OSTI]

    Steinfield, Charles

    Online Social Network Sites and the Concept of Social Capital Charles Steinfield, Nicole of online social network sites has grown dramatically, now rivaling search engines as the most visited users (Internet World Stats, 2010). Growing evidence from analyses of online social network site use

  17. Regional Transportation Coordination Plan for the Capital Area

    E-Print Network [OSTI]

    Capital Area Regional Transit Coordination Committee

    3588 is to ensure that the benefits of the State?s public transportation resources are maximized through development #24; Regional Transportation Coordination Plan for the Capital Area and implementation of regional public transportation services... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B-24 Appendix C ? Public Transportation Providers and Resources in the Region . . . . . . . . . . . . . C-1 Public Transit Providers...

  18. The Lake Charles CCS Project

    SciTech Connect (OSTI)

    Doug Cathro

    2010-06-30T23:59:59.000Z

    The Lake Charles CCS Project is a large-scale industrial carbon capture and sequestration (CCS) project which will demonstrate advanced technologies that capture and sequester carbon dioxide (CO{sub 2}) emissions from industrial sources into underground formations. Specifically the Lake Charles CCS Project will accelerate commercialization of large-scale CO{sub 2} storage from industrial sources by leveraging synergy between a proposed petroleum coke to chemicals plant (the LCC Gasification Project) and the largest integrated anthropogenic CO{sub 2} capture, transport, and monitored sequestration program in the U.S. Gulf Coast Region. The Lake Charles CCS Project will promote the expansion of EOR in Texas and Louisiana and supply greater energy security by expanding domestic energy supplies. The capture, compression, pipeline, injection, and monitoring infrastructure will continue to sequester CO{sub 2} for many years after the completion of the term of the DOE agreement. The objectives of this project are expected to be fulfilled by working through two distinct phases. The overall objective of Phase 1 was to develop a fully definitive project basis for a competitive Renewal Application process to proceed into Phase 2 - Design, Construction and Operations. Phase 1 includes the studies attached hereto that will establish: the engineering design basis for the capture, compression and transportation of CO{sub 2} from the LCC Gasification Project, and the criteria and specifications for a monitoring, verification and accounting (MVA) plan at the Hastings oil field in Texas. The overall objective of Phase 2, provided a successful competitive down-selection, is to execute design, construction and operations of three capital projects: (1) the CO{sub 2} capture and compression equipment, (2) a Connector Pipeline from the LLC Gasification Project to the Green Pipeline owned by Denbury and an affiliate of Denbury, and (3) a comprehensive MVA system at the Hastings oil field.

  19. Project Controls

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    Project controls are systems used to plan, schedule, budget, and measure the performance of a project/program. The cost estimation package is one of the documents that is used to establish the baseline for project controls. This chapter gives a brief description of project controls and the role the cost estimation package plays.

  20. Does Corporate Social Responsibility Affect the Cost of Capital? * Sadok El Ghoul

    E-Print Network [OSTI]

    Saskatchewan, University of

    capital for a large sample of U.S. firms. Using several approaches to estimate firms' ex ante costDoes Corporate Social Responsibility Affect the Cost of Capital? * Sadok El Ghoul University the effect of corporate social responsibility (CSR) on the cost of equity capital for a large sample of U

  1. Capital accumulation and non-renewable energy resources: a special functions case

    E-Print Network [OSTI]

    Nesterov, Yurii

    2007/9 Capital accumulation and non-renewable energy resources: a special functions case Agustin Pérez-Barahona #12;CORE DISCUSSION PAPER 2007/9 Capital accumulation and non-renewable energy resources the implications of assuming different technologies for physical capital accumulation and consumption. More

  2. Project Fact Sheet Project Update

    E-Print Network [OSTI]

    Project Fact Sheet Project Update: Project Brief: The works cover the refurbishment of floors 4, 5, with `wet' labs for molecular biology, materials characterisation, cell culture and flow studies, and `dry operating theatre. The Bionanotechnology Centre is one of the projects funded from the UK Government's £20

  3. Project Fact Sheet Project Brief

    E-Print Network [OSTI]

    Facts & Figures: Budget: £3,500,000 Funding Source: SRIF III Construction Project Programme: StartProject Fact Sheet Project Brief: This project refurbished half of the 5th and 7th floors of work includes: · Building fabric replacement and revised space planning · New mechanical and electrical

  4. The Distorted Transformation of Mexico: Arbitralism and Developmentalism, and Political Capitalism and Subcapitalism. A Pathway towards Balancing Capitalism and Balanced Development, or Demdevelopment

    E-Print Network [OSTI]

    Nunez, Ramon

    2013-01-01T23:59:59.000Z

    from Antiquity to Feudalism (Verso Classics). Anguiano,international transition from feudalism to capitalism. Thiseconomies and societies from feudalism. Throughout the long

  5. Project Execution Plan, Rev. 3

    SciTech Connect (OSTI)

    IT Corporation, Las Vegas

    2002-08-01T23:59:59.000Z

    This plan addresses project activities encompassed by the U.S. Department of Energy's (DOE's), National Nuclear Security Administration Nevada Operations Office, Environmental Restoration Division and conforms to the requirements contained in the Life-Cycle Asset Management, DOE Order 430.1A; The Joint Program Office Policy on Project Management in Support of DOE Order 430.1; Program and Project Management for the Acquisition of Capital Assets, DOE Order 413.3; the Project Execution and Engineering Management Planning Guide, GPG-FM-010; and other applicable Good Practice Guides; and the FY 2001 Integrated Planning, Accountability, and Budgeting System Policy Guidance. The plan also reflects the milestone philosophies of the Federal Facility Agreement and Consent Order, as agreed to by the State of Nevada, the DOE, and the U.S. Department of Defense; and traditional project management philosophies such as the development of life-cycle costs, schedules, and work scope; identification o f roles and responsibilities; and baseline management and controls.

  6. Human Capital Management Plan Fiscal Years 2003- 2010

    SciTech Connect (OSTI)

    none,

    2000-03-09T23:59:59.000Z

    Western, like many other Federal agencies, will face significant and challenging human capital issues in the next decade. The Federal workforce is aging; baby boomers, with their valuable skills and experience, are drawing nearer to retirement and new employees joining the Federal workforce today have different career expectations from the generation that preceded them. The average age of Western’s workforce is approaching 48. Almost a third of the workforce is between 50 and 54 years and most will be eligible to retire in five years. Western has almost twice as many employees who are 55 and older as it has who are 35 and younger. As the workforce ages, the proportion of younger workers is shrinking. The U.S. Census Bureau says you can expect these developments for the next 20 years. The 45 to 65 year-old work group will grow by 54 percent but the 18 to 44 population will rise by only 4 percent. According to the Bureau of Labor Statistics workers age 25 to 44 will decline by 3 million, dropping from 51 percent of the labor force in 1998 to 44 percent in 2008. Western employees who will retire include highly skilled workers in fields such as information technology, engineering, and craft occupations. Deregulation of the electric utility industry and the establishment of regional transmission organizations and independent system operators are also demanding new and different skill mixes than those currently available in Western. Changes in workforce demographic, in the education and skills that will be required in the future, and an increasingly competitive job market, will require flexible and responsive human capital tools to attract and retain talented employees. These trends were the reason for a comprehensive review of Western’s human capital programs to determine its readiness for the future. In July 2001, a team of managers conducted a comprehensive assessment of Western’s human capital needs. The team used the assessment to draft a framework that addresses the most critical human capital challenges in Western. Comments on the draft plan were then solicited from Western’s EEO committees and managers and supervisors. The framework outlines seven initiatives for implementation: 1) Develop a human capital plan linked to Western’s strategic goals. 2) Develop and implement a Westernwide workforce planning program. 3) Establish a succession planning program. 4) Create and foster a workplace environment that will attract and retain talented employees. 5) Establish a Western-wide recruitment program. 6) Develop a training program on human capital management for managers and supervisors. 7) Develop pay options for improving the link between pay and performance. Our goal in developing this plan is to help Western achieve its mission to be a premier power marketing and transmission organization. This plan serves as a first step in addressing Western’s human capital issues in the next decade.

  7. LIFE Cost of Electricity, Capital and Operating Costs

    SciTech Connect (OSTI)

    Anklam, T

    2011-04-14T23:59:59.000Z

    Successful commercialization of fusion energy requires economic viability as well as technical and scientific feasibility. To assess economic viability, we have conducted a pre-conceptual level evaluation of LIFE economics. Unit costs are estimated from a combination of bottom-up costs estimates, working with representative vendors, and scaled results from previous studies of fission and fusion plants. An integrated process model of a LIFE power plant was developed to integrate and optimize unit costs and calculate top level metrics such as cost of electricity and power plant capital cost. The scope of this activity was the entire power plant site. Separately, a development program to deliver the required specialized equipment has been assembled. Results show that LIFE power plant cost of electricity and plant capital cost compare favorably to estimates for new-build LWR's, coal and gas - particularly if indicative costs of carbon capture and sequestration are accounted for.

  8. The Orthodox ethic and the spirit of anti-capitalism 

    E-Print Network [OSTI]

    Kartashov, Andrei Valerievich

    1998-01-01T23:59:59.000Z

    . TABLE OF CONTENTS Page ABSTRACT TABLE OF CONTENTS. CHAPTER 1V I INTRODUCTION. . II WEBER'S NATIONALISM AND THE HATRED OF RUSSIA. . a. Weber and the East-West Cultural Clash. . . . . . b. Weber's Concept of the Nation. . c. The Nation...-State and Dynasty. . . . . . . . . . . . . . . . . . . d. Nations and Social Change 8 15 19 21 III THE BI-POLAR MIND: BERDIAEV AND TOMASIC. . . . . . 27 IV THE ORTHODOX ETHIC 37 V COMMUNAL CAPITALISM: THE OLD BELIEF IN RUSSIA. . . . 46 a. The Old Belief...

  9. Leveraging Inefficient and Failing Infrastructure to Accomplish Capital Improvements

    E-Print Network [OSTI]

    Mumper, M.; Taylor, C.

    2005-01-01T23:59:59.000Z

    , 3-wire. The generator operates in parallel with the utility. Generated power will be used on site and will not be sold back to the utility. Electrical switchgear and controls interface the generator with the existing power distribution system...Leveraging Inefficient and Failing Infrastructure to Accomplish Capital Improvements Mike Mumper, CPMM Carol Taylor Sales Representative Institutional Business Manager TAC-Abacus Hiram G. Andrews Center Harrisburg, PA Johnstown, PA...

  10. FutureGen Project Report

    SciTech Connect (OSTI)

    Cabe, Jim; Elliott, Mike

    2010-09-30T23:59:59.000Z

    This report summarizes the comprehensive siting, permitting, engineering, design, and costing activities completed by the FutureGen Industrial Alliance, the Department of Energy, and associated supporting subcontractors to develop a first of a kind near zero emissions integrated gasification combined cycle power plant and carbon capture and storage project (IGCC-CCS). With the goal to design, build, and reliably operate the first IGCC-CCS facility, FutureGen would have been the lowest emitting pulverized coal power plant in the world, while providing a timely and relevant basis for coal combustion power plants deploying carbon capture in the future. The content of this report summarizes key findings and results of applicable project evaluations; modeling, design, and engineering assessments; cost estimate reports; and schedule and risk mitigation from initiation of the FutureGen project through final flow sheet analyses including capital and operating reports completed under DOE award DE-FE0000587. This project report necessarily builds upon previously completed siting, design, and development work executed under DOE award DE-FC26- 06NT4207 which included the siting process; environmental permitting, compliance, and mitigation under the National Environmental Policy Act; and development of conceptual and design basis documentation for the FutureGen plant. For completeness, the report includes as attachments the siting and design basis documents, as well as the source documentation for the following: • Site evaluation and selection process and environmental characterization • Underground Injection Control (UIC) Permit Application including well design and subsurface modeling • FutureGen IGCC-CCS Design Basis Document • Process evaluations and technology selection via Illinois Clean Coal Review Board Technical Report • Process flow diagrams and heat/material balance for slurry-fed gasifier configuration • Process flow diagrams and heat/material balance for dry-fed gasifier configuration • Full capital cost report and cost category analysis (CAPEX) • Full operating cost report and assumptions (OPEX) Comparative technology evaluations, value engineering exercises, and initial air permitting activities are also provided; the report concludes with schedule, risk, and cost mitigation activities as well as lessons learned such that the products of this report can be used to support future investments in utility scale gasification and carbon capture and sequestration. Collectively, the FutureGen project enabled the comprehensive site specific evaluation and determination of the economic viability of IGCC-CCS. The project report is bound at that determination when DOE formally proposed the FutureGen 2.0 project which focuses on repowering a pulverized coal power plant with oxy-combustion technology including CCS.

  11. RESIDENTIAL ON SITE SOLAR HEATING SYSTEMS: A PROJECT EVALUATION USING THE CAPITAL ASSET PRICING MODEL

    E-Print Network [OSTI]

    Schutz, Stephen Richard

    2011-01-01T23:59:59.000Z

    solar energy with rooftop panels, store excess energy in water storage tanks and can, in certain circumstances, provide 100% of the space heating

  12. Data Integration for Capital Projects via Community-Specific Conceptual Representations

    E-Print Network [OSTI]

    Chen, Shu-Ching

    industry standard for data exchange, and oftentimes a reluctance to share business-sensitive information

  13. EM Capital and Major Operating Project Standard Review Plan Edition Two |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE: Alternative FuelsNovember 13,Statement | Department of Energy 99: DOE Notice ofDepartment of

  14. STATEMENT OF WORK AND KEY PERFORMANCE PARAMETERS HANDBOOK FOR CAPITAL ASSET PROJECTS

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic2 OPAM615_CostNSARDevelopmental AssignmentApril 2,OCTOBER 2-3,

  15. DOE Order Program and Project Management for the Acquisition of Capital

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: Since the YouTube| Department of Energy81stEnforcement Effort with 20 Newin AlaskaAssets |

  16. Memo Issuance of EM Capital and Major Operating Project Standard Review Plan Edition Two

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: Since the.pdfBreaking ofOil & GasTechnicalMeeting with EarthJustice RegardingMemberWorkshopMAR

  17. EMAB Briefing on Capital Assets Projects and Operations Activities Presentation by Mark Gilbertson

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic Plan Department ofNotices |Notice of38:3:1:EMOperations |Celebrating

  18. Financing U.S. Renewable Energy Projects Through Public Capital Vehicles: Qualitative and Quantitative Benefits

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC) Environmental Assessments (EA)Budget »Travel andFifth

  19. Summary of Initial Examination of Lighting-Only Utility Projects in the Federal Sector

    SciTech Connect (OSTI)

    Solana, Amy E.; Sandusky, William F.; Mcmordie, Katherine

    2007-07-26T23:59:59.000Z

    This work complements earlier work on an analysis of Federal utility energy projects that implemented excusively lighting upgrades. The objective of this analysis is to better understand the lighting-only projects through determination of the relationship of capital invested and the resulting energy and cost savings, in terms of geographic locale, project size, and potential according to specific lighting technologies and/or control technology implemented.

  20. Proposed changes to generating capacity 1980-1989 for the contiguous United States: as projected by the Regional Electric Reliability Councils in their April 1, 1980 long-range coordinated planning reports to the Department of Energy

    SciTech Connect (OSTI)

    None

    1980-12-01T23:59:59.000Z

    The changes in generating capacity projected for 1980 to 1989 are summarized. Tabulated data provide summaries to the information on projected generating unit construction, retirements, and changes, in several different categories and groupings. The new generating units to be completed by the end of 1989 total 699, representing 259,490 megawatts. This total includes 10 wind power and one fuel cell installations totaling 48.5 MW to be completed by the end of 1989. There are 321 units totaling 13,222 MW to be retired. There are capacity changes due to upratings and deratings. Summary data are presented for: total requirement for electric energy generation for 1985; hydroelectric energy production for 1985; nuclear energy production for 1985; geothermal and other energy production for 1985; approximate non-fossil generation for 1985; range of fossil energy requirements for 1985; actual fossil energy sources 1974 to 1979; estimated range of fossil fuel requirements for 1985; coal capacity available in 1985; and computation of fuel use in 1985. Power plant capacity factors are presented. Extensive data on proposed generating capacity changes by individual units in the 9 Regional Electric Reliability Councils are presented.

  1. Magnesium Projects

    Broader source: Energy.gov (indexed) [DOE]

    cyberinfrastructure projects and will be augmented by original research in Computer Science and Software Engineering towards the creation of large, distributed, autonomic and...

  2. Project Construction

    Broader source: Energy.gov [DOE]

    Integrating renewable energy into Federal new construction or major renovations requires effective structuring of the construction team and project schedule. This overview discusses key construction team considerations for renewable energy as well as timing and expectations for the construction phase. The project construction phase begins after a project is completely designed and the construction documents (100%) have been issued. Construction team skills and experience with renewable energy technologies are crucial during construction, as is how the integration of renewable energy affects the project construction schedule.

  3. Strategic evaluation central to LNG project formation

    SciTech Connect (OSTI)

    Nissen, D. [Poten and Partners Inc., New York, NY (United States); DiNapoli, R.N. [Merlin Associates, Atlanta, GA (United States); Yost, C.C. [Merlin Associates, Houston, TX (United States)

    1995-07-03T23:59:59.000Z

    An efficient-scale, grassroots LNG facility of about 6 million metric tons/year capacity requires a prestart-up outlay of $5 billion or more for the supply facilities--production, feedgas pipeline, liquefaction, and shipping. The demand side of the LNG chain requires a similar outlay, counting the import-regasification terminal and a combination of 5 gigawatts or more of electric power generation or the equivalent in city gas and industrial gas-using facilities. There exist no well-developed commodity markets for free-on-board (fob) or delivered LNG. A new LNG supply project is dedicated to its buyers. Indeed, the buyers` revenue commitment is the project`s only bankable asset. For the buyer to make this commitment, the supply venture`s capability and commitment must be credible: to complete the project and to deliver the LNG reliably over the 20+ years required to recover capital committed on both sides. This requirement has technical, economic, and business dimensions. In this article the authors describe a LNG project evaluation system and show its application to typical tasks: project cost of service and participant shares; LNG project competition; alternative project structures; and market competition for LNG-supplied electric power generation.

  4. Quick Estimate of IRR From Capital Estimate Ratios

    E-Print Network [OSTI]

    Larson, R. J.

    specific problem. However, the derivation is simple enough so that a new chart can be derived, using the principles described, which is applicable to a specific situation or class of situations. Using conventional Discounted Cash Flow techniques... of the use of this chart is as follows: The estimate capital to carry out a proj ct is $24,000. The estimated savings to be experienced n the first year of operation is $11,300. 21 ESL-IE-85-05-05 Proceedings from the Seventh National Industrial Energy...

  5. Cinergy Capital & Trading, Inc | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand JumpConceptual Model, click here.TelluricPower InternationalChuichu,Cima NanoTechCinergy Capital &

  6. CE2 Capital Partners LLC | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnualProperty EditCalifornia:Power LP Biomass Facilityin Charts Jump to: navigation,CE2 Capital

  7. PvT Capital Gmbh | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnualProperty Edit with form History Facebook icon TwitterZip JumpProwindPudaPvT Capital Gmbh Jump

  8. EA-355 Scotia Capital Energy, Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't Your Destiny:Revised Finding of No53197EFindingEA-257-CEA-296-B2244 TwinEA-355 Scotia Capital

  9. Clean Cities: Capital District Clean Communities coalition (Albany)

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office511041clothAdvanced Materials Advanced. C o w l i t z CPlasma0 12 BONNEVILLE POWERPropaneofAlamoCapital

  10. MP2 CapitalLLC | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation, searchOfRose Bend < MHKconverter <WAG BuoyYOG <MP2 CapitalLLC Jump to:

  11. RockPort Capital Partners (Massachusetts) | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:Ezfeedflag JumpID-f < RAPID‎ |Rippey Jump to: navigation,RockPort Capital Partners

  12. Nevaro Capital Corporation Formerly VRB Power Systems | Open Energy

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnual SiteofEvaluatingGroup |JilinLuOpen EnergyNelsoniX Ltd JumpNepaliInformation Nevaro Capital

  13. Workplace Charging Challenge Partner: Capital One Financial Corporation |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: SinceDevelopment | Department ofPartnershipsAngieTerriDepartment of Energy Capital One

  14. RockPort Capital Partners (California) | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere IRaghuraji Agro Industries Pvt Ltd Jump to: navigation,MazeOhio:Ohio: Energy Jump to:RockPort Capital Partners

  15. Clean World Capital A S | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand JumpConceptual Model, clickInformation SmyrnaNewClay ElectricClean EdgeProtection Tool forCapital

  16. IFCI Venture Capital Funds Ltd | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnual SiteofEvaluatingGroup | OpenHunan Runhua New Energy DevelopmentListIIFCI Venture Capital Funds

  17. Appalachia's new region-wide CDFI : building local community with global capital?

    E-Print Network [OSTI]

    Spicer, Jason S. (Jason Simpson)

    2014-01-01T23:59:59.000Z

    The Appalachian Regional Commission is currently working with a major foundation on the development of a new regional Community Development Financial Institution (CDFI), Appalachian Community Capital. By connecting ...

  18. A capital cost comparison of commercial ground-source heat pump systems

    SciTech Connect (OSTI)

    Rafferty, K.

    1994-06-01T23:59:59.000Z

    The report provides a capital cost comparison of commercial ground source heat pump systems. The study includes groundwater systems, ground-coupled systems and hybrid systems.

  19. Native American Housing Stakeholder Meeting- Tribal Data: Building the Bridge to New Capital

    Office of Energy Efficiency and Renewable Energy (EERE)

    Hosted by the Housing Assistance Council, the Native American Housing Stakeholder Meeting will discuss effective strategies for tribally led data collection, ways to access and leverage new capital...

  20. Investment performance of life-science venture capital investment funds, persistence, and subsector analysis

    E-Print Network [OSTI]

    Behrens, Jeffrey S

    2007-01-01T23:59:59.000Z

    Venture capital investment performance data and performance attribution are not typically published. Venture investors articulate (and sell to LPs) conflicting strategies; the popular business literature and culture is ...

  1. Valuing Rail Transit: Comparing Capital and Operating Costs to Consumer Benefits

    E-Print Network [OSTI]

    Guerra, Erick

    2010-01-01T23:59:59.000Z

    D.C. , 1994; Booz Allen Hamilton, Inc. Light rail transitD.C. , 2003; Booz Allen Hamilton, Inc. , Managing Capital

  2. OFFICE of MATERIALS & LOGISTICS MANAGEMENT CAPITAL ASSET INVENTORY CERTIFICATE --IC-10

    E-Print Network [OSTI]

    Oliver, Douglas L.

    OFFICE of MATERIALS & LOGISTICS MANAGEMENT CAPITAL ASSET INVENTORY CERTIFICATE -- IC-10 DATE: From: Jack Ferraro University Director Office of Materials & Logistics Management (MLM) LB058, MC 2012

  3. Demonstration project in Energy Management Programs

    SciTech Connect (OSTI)

    Not Available

    1989-05-01T23:59:59.000Z

    The Energy Management Plan of the campuses developed under this project showed that there were a number of low-cost Energy Conservation Opportunities (ECO's) with a payback of under one year, (Short term Opportunities, STO). There were also other ECO's identified that had paybacks of more than one year. By combining these ECO's into one contract with the ESCO and paying for the costs of the ECO's by the savings resulting in the reduced energy bills, the University enhanced it's ability to carry out its mission of providing higher educational opportunities without spending money on non-educational activities. The low cost projects subsidize'' or provide leverage for the capital intensive, longer payback projects, to make an overall package that lends itself to innovative financing. JC Smith's contract also guarantees that the annual energy levels will not be increased.

  4. Project Manager

    Broader source: Energy.gov [DOE]

    A successful candidate in this position will serve as a project manager in the Fuel Cell Technologies Office in the DOE-EERE Office of Transportation responsible for a wide variety of highly...

  5. RENOTER Project

    Broader source: Energy.gov [DOE]

    Overview of French project on thermoelectric waste heat recovery for cars and trucks with focus on cheap, available, efficient, and sustainable TE materials, as well as efficient material integration and production process.

  6. A Closer Evaluation of Capital Punishment: Viewing Executions through the Lens of Former Prison Employees

    E-Print Network [OSTI]

    Griffith, Athena Renee'

    2014-09-03T23:59:59.000Z

    : Authority and Compliance ............................... 15 C. Wright Mills Study: Power and Authority, Responsibility, and the Power Elite ....................................................................... 18 Capital Murder Inmates during the Pre... payers billions of dollars annually (Alexander 2012; Perkinson 2010; Reiman 2003), as well as the differences in costs for housing capital murder inmates living on death and those who are not living on death row (Johnson 2005; Vago 1997). In terms...

  7. The Ties That Bond: Re-Examining the Relationship between Facebook Use and Bonding Social Capital

    E-Print Network [OSTI]

    Michigan, University of

    The Ties That Bond: Re-Examining the Relationship between Facebook Use and Bonding Social Capital established a positive relationship between measures of Facebook use and perceptions of social capital. Like other social network sites, Facebook is especially well-positioned to enhance users' bridging social

  8. The Externalities of Strong Social Capital: Post-Tsunami Recovery in Southeast India

    E-Print Network [OSTI]

    1 The Externalities of Strong Social Capital: Post-Tsunami Recovery in Southeast India DANIEL P villages in Tamil Nadu, India following the 2004 Indian Ocean tsunami, this paper demonstrates that high findings have important implications for academic studies of social capital and policy formation for future

  9. The Kuznets-Kaldor-Puzzle and Neutral Cross-Capital-Intensity

    E-Print Network [OSTI]

    Güting, Ralf Hartmut

    The Kuznets-Kaldor-Puzzle and Neutral Cross-Capital-Intensity Structural Change by Denis Stijepic://www.fernuni-hagen.de/ls_wagner/en/ #12;The Kuznets-Kaldor-Puzzle and Neutral Cross- Capital-Intensity Structural Change* Denis Stijepic The Kuznets-Kaldor stylized facts are one of the most striking empirical observations about the development

  10. Capital improvements can contribute greatly to an airport's future success, but

    E-Print Network [OSTI]

    Minnesota, University of

    description, cost estimate, federal programming sheets (available at www.mnaero.com), and start date. FederalCapital improvements can contribute greatly to an airport's future success, but they require a serious financial commit- ment by the airport owner. Planning ahead for capital improvements is critical

  11. Trends in U.S. Venture Capital Investments Related to Energy: 1980-2007

    SciTech Connect (OSTI)

    Dooley, James J.

    2008-10-10T23:59:59.000Z

    This report documents trends in U.S. venture capital investments over the period 1980-2008. Particular attention is given to U.S. venture capital investments for “internet-specific”, biotechnology, and energy / industrial sectors over the period 1980-2007. During the early 1980s, U.S. venture capital investments in the energy / industrial area accounted for more than 20% of all venture capital investments. However subsequent periods of low energy prices and the emergence of fast growing new industries like computers (both hardware and software), biotechnology and the Internet quickly reduced the priority accorded to energy / industrial investments as by 2000 these investments accounted for only 1% of the $119 billion dollars invested that year by the U.S. venture capital community. The significant increase in the real price of oil that began in 2003-2004 correlates with renewed interest and increased investment by the venture capital community in energy / industrial investment opportunities. Venture capital investments in 2007 for the energy / industrial sector accounted for $3 billion or slightly more than 10% of all venture capital invested that year.

  12. Investment and the Cost of Capital in the Nineties in France: A Panel Data Investigation

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    Investment and the Cost of Capital in the Nineties in France: A Panel Data Investigation by Jean Genehmigung des ifo Instituts. #12;Investment and the Cost of Capital in the Nineties in France: A Panel Data of Firms III. Data and Econometric Results IV. Conclusion I. Introduction It is a widespread belief among

  13. WORKING PAPER N 2008 -51 Human capital investment and long-term poverty

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    WORKING PAPER N° 2008 - 51 Human capital investment and long-term poverty reduction in rural Mexico SUPÉRIEURE halshs-00586227,version1-15Apr2011 #12;Human capital investment and long-term poverty reduction poor (World Bank, 2005). To address chronic poverty, the Mexican government has developed an overall

  14. 42 UNIVERSITY OF CALIFORNIA -CAPITAL FINANCIAL PLAN 2012-22 Coastal Biology Building

    E-Print Network [OSTI]

    California at Santa Cruz, University of

    42 UNIVERSITY OF CALIFORNIA - CAPITAL FINANCIAL PLAN 2012-22 Coastal Biology Building University&Figures SANTA CRUZ Coastal Biology Building Site #12;43UNIVERSITY OF CALIFORNIA - CAPITAL FINANCIAL PLAN 2012 C ­ multiple locations Coastal Biology Building - (Marine Science Campus) Infrastructure

  15. Towards Software Product Lines Application in the Context of a Smart Building Project

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    Towards Software Product Lines Application in the Context of a Smart Building Project Thibaut. This paper presents proposals on how to apply software prod- uct lines in the context of smart buildings the various components involved in smart buildings, and to capitalize on the devel- oped IT components

  16. Exploring Flexible Strategies in Engineering Systems Using Screening Models Applications to Offshore Petroleum Projects

    E-Print Network [OSTI]

    de Weck, Olivier L.

    , such as offshore petroleum exploration and production systems, generally require a significant amount of capital to Offshore Petroleum Projects by Jijun Lin B.E., Mechanical Engineering, Beijing University of Aeronautics Flexible Strategies in Engineering Systems Using Screening Models Applications to Offshore Petroleum

  17. Economic Evaluation of the Cadiz Groundwater Storage and Dry Year Supply Project,

    E-Print Network [OSTI]

    - 800 - 600 - 400 - 200 - 0 MWD Estimate DollarsperAcre-Foot The Estimated Cost of Water from the Cadiz uncertainties in studies of water is the cost of new water supply. Estimates of project cost depend on a wide range of uncertain factors, including water yields, the cost of money, expected capital costs

  18. Discrete Event Modeling of Algae Cultivation and Harvesting at Commercial Scale: Capital Costs, Operating Costs, and System Bottlenecks

    SciTech Connect (OSTI)

    Lacey, Ph.D, P.E., Ronald E. [Texas A& M University

    2012-07-16T23:59:59.000Z

    Discrete Event Modeling of Algae Cultivation and Harvesting at Commercial Scale: Capital Costs, Operating Costs, and System Bottlenecks

  19. The contribution of built, human, social and natural capital to quality of life in intentional and unintentional communities

    E-Print Network [OSTI]

    Vermont, University of

    have a better balance between built, human, social, and natural capital than unintentional communities ICs, social capital is substituted for built capital thereby reducing the level of material throughput. © 2005 Elsevier B.V. All rights reserved. Keywords: Quality of life survey Intentional communities Social

  20. Genetic algorithm evolved agent-based equity trading using Technical Analysis and the Capital Asset Pricing Model

    E-Print Network [OSTI]

    Aickelin, Uwe

    Genetic algorithm evolved agent-based equity trading using Technical Analysis and the Capital Asset data using technical analysis, the capital asset pricing model and a hybrid model of the two approaches. Results indicated that the technical analysis based approach performed better than the capital asset

  1. Electronic copy available at: http://ssrn.com/abstract=2065816 Ultimate Ownership Structure and Bank Regulatory Capital Adjustment

    E-Print Network [OSTI]

    Boyer, Edmond

    their capital structure (debt/equity), firms in general and banks more specifically take control dilution costs into consideration, beyond the asymmetric information and transaction costs considered in prior research on capital and Bank Regulatory Capital Adjustment: Evidence from European Commercial Banks Laetitia Lepetita , Amine

  2. Cloudnet Project

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Hogan, Robin

    Cloudnet is a research project supported by the European Commission. This project aims to use data obtained quasi-continuously for the development and implementation of cloud remote sensing synergy algorithms. The use of active instruments (lidar and radar) results in detailed vertical profiles of important cloud parameters which cannot be derived from current satellite sensing techniques. A network of three already existing cloud remote sensing stations (CRS-stations) will be operated for a two year period, activities will be co-ordinated, data formats harmonised and analysis of the data performed to evaluate the representation of clouds in four major european weather forecast models.

  3. Spent Nuclear Fuel project, project management plan

    SciTech Connect (OSTI)

    Fuquay, B.J.

    1995-10-25T23:59:59.000Z

    The Hanford Spent Nuclear Fuel Project has been established to safely store spent nuclear fuel at the Hanford Site. This Project Management Plan sets forth the management basis for the Spent Nuclear Fuel Project. The plan applies to all fabrication and construction projects, operation of the Spent Nuclear Fuel Project facilities, and necessary engineering and management functions within the scope of the project

  4. Conceptual design report for tank farm restoration and safe operations, project W-314

    SciTech Connect (OSTI)

    Briggs, S.R., Westinghouse Hanford

    1996-05-02T23:59:59.000Z

    This Conceptual Design Report (CDR) presents the conceptual level design approach that satisfies the established technical requirements for Project W-314, `Tank Farm Restoration and Safe Operations.` The CDR also addresses the initial cost and schedule baselines for performing the proposed Tank Farm infrastructure upgrades. The scope of this project includes capital improvements to Hanford`s existing tank farm facilities(primarily focused on Double- Shell Tank Farms) in the areas of instrumentation/control, tank ventilation, waste transfer, and electrical systems.

  5. Project financing knits parts of costly LNG supply chain

    SciTech Connect (OSTI)

    Minyard, R.J.; Strode, M.O. [Mobil Corp., Fairfax, VA (United States)

    1997-06-02T23:59:59.000Z

    The supply and distribution infrastructure of an LNG project requires project sponsors and LNG buyers to make large, interdependent capital investments. For a grassroots project, substantial investments may be necessary for each link in the supply chain: field development; liquefaction plant and storage; ports and utilities; ships; receiving terminal and related facilities; and end-user facilities such as power stations or a gas distribution network. The huge sums required for these projects make their finance ability critical to implementation. Lenders have become increasingly comfortable with LNG as a business and now have achieved a better understanding of the risks associated with it. Raising debt financing for many future LNG projects, however, will present new and increasingly difficult challenges. The challenge of financing these projects will be formidable: political instability, economic uncertainty, and local currency volatility will have to be recognized and mitigated. Described here is the evolution of financing LNG projects, including the Rasgas LNG project financing which broke new ground in this area. The challenges that lie ahead for sponsors seeking to finance future projects selling LNG to emerging markets are also discussed. And the views of leading experts from the field of project finance, specifically solicited for this article, address major issues that must be resolved for successful financing of these projects.

  6. ERIS Project 

    E-Print Network [OSTI]

    Hunter, Philip

    repositories. If these (generally) smaller institutions wished to continue to have access to these hosted repository spaces after the end of the project, it was proposed that these repository-lite services would be administered by the SDLC (the Scottish Digital...

  7. Confined zone dispersion project. Final technical report

    SciTech Connect (OSTI)

    NONE

    1994-06-01T23:59:59.000Z

    This report describes the performance of the confined zone dispersion (CZD) flue gas desulfurization (FGD) system in removing sulfur dioxide (SO{sub 2}) from flue gas in the coal-fired boiler. The CZD-FGD system, installed at Pennsylvania Electric Company`s (Penelec`s) Seward Power Station, was designed to remove 50% of the SO{sub 2} from one-half of Unit No. 5`s flue gas when the boiler is fired with 1.5% sulfur coal. Section 1 discusses the significance of CZD, the purpose of this report, the history of the project, and the role of DOE in the project, describes the project organization, and lists the six design areas involving proprietary information. Section 2 presents project location, objectives, and phases, and discusses the test program. Section 3 explains the process flow diagram, piping and instrumentation diagrams and operating controls, site plan, equipment layouts, and process equipment. Section 4 provides an integrated discussion of all the test results obtained during the test program, backed by tabulations and graphics. Section 5 describes the testing failures and corrective actions taken. Section 6, reliability/availability/maintainability analysis data of major equipment, covers the following systems: atomizing, sootblowing, lime, flue gas, and controls and instrumentation. Section 7 summarizes the capital cost requirements for the Seward CZD demonstration unit and discusses the capital and operating costs of installing the process at plants with various unit capacities. Section 8 discusses plans to continue the CZD demonstration to achieve longer term continuous operation at SO{sub 2} removals of 50%. Section 9 presents the principal findings of the CZD demonstration and recommends additional testing.

  8. Tri-County solid waste-to-fuel production project feasibility study

    SciTech Connect (OSTI)

    Not Available

    1983-09-01T23:59:59.000Z

    The analysis and preliminary findings of refuse-derived fuel and recovered components markets are presented. Other topics covered are: municipal solid waste composition, quantity and constraints; technical assessment and capital cost assessment; economic feasibility of burning process residue to generate steam; review of commercially available equipment for the densification of refuse-derived fuel; final pre-feasibility analysis for the Tri-County Municipal Solid Waste to Fuel Production Project; preliminary economic and sensitivity analysis for the Tri-County Project; risks assessment for the Tri-County Project; and environmental, health, safety, and socioeconomic assessment for the Tri-County Project. (MHR)

  9. Project Fact Sheet Project Brief

    E-Print Network [OSTI]

    Name: Centre for Assisted Robotic Surgery Number: BESS1002b Project Champion: Professor Guang-Zong Yang of the refurbishment is to renew and expand the laboratory space for Robotic Assisted Surgery at the South Kensington Campus as par to the Hamlyn Centre for Robotic Surgery. The overall programme incorpo- rates both core

  10. The Department of Energy, Office of Environmental Restoration and Waste Management: Project performance study

    SciTech Connect (OSTI)

    Not Available

    1993-11-01T23:59:59.000Z

    The Office of Environmental Restoration and Waste Management (EM) of the US Department of Energy commissioned Independent Project Analysis, Inc. (IPA) to perform this Project Performance Study to provide a quantitative analysis determining how well EM develops and executes environmental remediation and waste management projects. The approach consisted of collecting detailed data on a sample of 65 completed and ongoing EM projects conducted since 1984. These data were then compared with key project characteristics and outcomes from 233 environmental remediation projects (excluding EM) in IPA`s Environmental Remediation Database and 951 projects In IPA`s Capital Projects Database. The study establishes the standing of the EM system relative to other organizations, and suggests areas and opportunities for improvement.

  11. Annual energy outlook 1998 with projections to 2020

    SciTech Connect (OSTI)

    NONE

    1997-12-01T23:59:59.000Z

    The Annual Energy Outlook 1998 (AEO98) is the first AEO with projections to 2020. Key issues for the forecast extension are trends in energy efficiency improvements, the effects of increasing production and productivity improvements on energy prices, and the reduction in nuclear generating capacity. Projections in AEO98 also reflect a greater shift to electricity market restructuring. Restructuring is addressed through several changes that are assumed to occur in the industry, including a shorter capital recovery period for capacity expansion decisions and a revised financial structure that features a higher cost of capital as the result of higher competitive risk. Both assumptions tend to favor less capital-intensive generation technologies, such as natural gas, over coal or baseload renewable technologies. The forecasts include specific restructuring plans in those regions that have announced plans. California, New York, and New England are assumed to begin competitive pricing in 1998. The provisions of the California legislation for stranded cost recovery and price caps are incorporated. In New York and New England, stranded cost recovery is assumed to be phased out by 2008.

  12. Information Processing, Psychopathy, and Juror Decision Making in a Capital Murder Case

    E-Print Network [OSTI]

    Cox, Jennifer

    2014-04-25T23:59:59.000Z

    by the judge. Specifically, participants were primed to employ a rational, analytical mindset or rely on their gut-instincts and intuition. Participants were then presented with a capital murder case vignette and expert testimony (clinical opinion or actuarial...

  13. International Capital Flows and Financial Markets in Transition Economies: The Case of Croatia

    E-Print Network [OSTI]

    Sohinger, Jasminka; Horvatin, Darko

    2006-01-01T23:59:59.000Z

    instruments TOTAL Source: Croatian National Bank (2005) TheFrankfurt, J2 / J2-2 Croatian National Bank (2005),capital flows had on the Croatian banking industry as well

  14. International Capital Flows and Financial Markets in Transition Economies: The Case of Croatia

    E-Print Network [OSTI]

    Sohinger, Jasminka; Horvatin, Darko

    2006-01-01T23:59:59.000Z

    of portfolio capital inflows to Croatia 1998- Table 4.Portfolio Investment in Croatia 1998-2003 ( in Mil US$) 1.reveals a surprising ratio in Croatia when compared to other

  15. Investigation of the most appropriate capital structure theory and leverage level determinants 

    E-Print Network [OSTI]

    Lew, Sung Hee

    2012-10-03T23:59:59.000Z

    This thesis examines capital structure theories and debt level determinants to develop a better understanding, and to establish the most appropriate theory to explain the behaviour of firms? debt and equity choices. It ...

  16. Structuring public REIT-sponsored private capital fund : the case of US industrial and retail REITs

    E-Print Network [OSTI]

    Lee, Cervantes (Cervantes Chih-Chieh), 1975-

    2008-01-01T23:59:59.000Z

    The private capital business for public REITs was started by Kimco Realty, Developer Diversified, AMB and ProLogis during the years 1998-2000, at the time when the public equity was not easily available. Over the past ...

  17. Seeds of growth : the challenges of venture capital in the Australian landscape

    E-Print Network [OSTI]

    Lu, Adrian C. (Adrian Chian)

    2012-01-01T23:59:59.000Z

    The Australian venture capital (VC) industry is young and relatively immature compared to the United States. Even though the first Australian VC firm appeared in 1970, the industry remained a niche with low levels of ...

  18. Dynamics of shared capitalism policies in a startup company by Joe C. Hsueh.

    E-Print Network [OSTI]

    Hsueh, Joe C. (Joe Chiao-Jen)

    2011-01-01T23:59:59.000Z

    Shared capitalism is a diverse set of compensation practices through which worker pay, or wealth, depends on the performance of the firm or work group; compensation practices include employee ownership, stock options, and ...

  19. Agency conflicts in financial contracting with applications to venture capital and CDO markets

    E-Print Network [OSTI]

    Garrison, Kedran

    2005-01-01T23:59:59.000Z

    In these papers I examine efficient financial contracting when incentive problems play a significant role. In the first chapter (joint with Z. Fluck and S. Myers) we focus on the venture capital industry. We build a two-stage ...

  20. Relational Capital and Appropriate Incentives: A Recipe for Human Resource Sustainability?1

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    economic literature on incentives, experimental economics and research in cognitive psychology can provideRelational Capital and Appropriate Incentives: A Recipe for Human Resource Sustainability?1 Agnès Festré University of Picardie Jules Verne, France Faculty of Economics Agnes

  1. Growth strategies : how software start-ups can leverage alliances, acquisitions, IPOs and venture capital

    E-Print Network [OSTI]

    Ybanez, Sergio D

    2007-01-01T23:59:59.000Z

    The identification of the different factors impacting a software start-up company's decision to pursue an alliance, acquisition, IPO or venture capital to sustain growth is the main objective of this research study. First ...

  2. Dynamic cycles of strategy, marketing and sales : a framework for capital goods industries

    E-Print Network [OSTI]

    Rezende de Azevedo, Tadeu

    2013-01-01T23:59:59.000Z

    This thesis proposes a framework to help managers facing growth challenges or commoditization problems in business to business, particularly with capital goods. The framework is based on the proposition that strategy, ...

  3. Academic entrepreneurial ecosystem strategy in the New York state capital region

    E-Print Network [OSTI]

    Adsit, Daniel Mark

    2014-01-01T23:59:59.000Z

    The upstate New York regions are historically significant, but experienced economic decline throughout the later twentieth century. The New York State capital region, located approximately 150 miles north of New York City ...

  4. Social capital's dark side: knowledge, reciprocity, and the liability of relationships 

    E-Print Network [OSTI]

    Collins, Jamie D.

    2009-05-15T23:59:59.000Z

    members with greater influence over decision making are more able to achieve their goals than less well-connected members. In addition to providing greater power over individual decisions, higher levels of social capital are also accompanied by greater...

  5. Essays using military-induced variation to study social interactions, human capital development, and labor markets

    E-Print Network [OSTI]

    Lyle, David S. (David Stephen), 1971-

    2003-01-01T23:59:59.000Z

    This dissertation consists of four empirical studies, each using military-induced variation to examine various aspects of human capital production and the U.S. labor market. The first two chapters study the effects of ...

  6. Social capital's dark side: knowledge, reciprocity, and the liability of relationships

    E-Print Network [OSTI]

    Collins, Jamie D.

    2009-05-15T23:59:59.000Z

    follow that of the Academy of Management Journal. T 2 terms of connections within and across networks (Burt, 1992, 1997; Gulati, 1995a; Tsai & Ghoshal, 1998). These and other authors have presented a convincing argument that social capital can...

  7. Balancing capital and condition : an emerging approach to facility investment strategy

    E-Print Network [OSTI]

    Wooldridge, Stephen C. (Stephen Craig), 1967-

    2002-01-01T23:59:59.000Z

    Capital facilities - land and buildings - provide a long-standing environment in which public and private enterprise works, communicates, and thrives. Aligning how facilities "fit" with the dynamic demands of enterprise ...

  8. JOB SEARCH PATTERNS OF COLLEGE GRADUATES: THE ROLE OF SOCIAL CAPITAL

    E-Print Network [OSTI]

    Coonfield, Emily Suzanne

    2012-12-31T23:59:59.000Z

    This dissertation addresses job search patterns of college graduates and the implications of social capital by race and class. The purpose of this study is to explore (1) how the job search transpires for recent college graduates, (2) how potential...

  9. Spreading The Word: Capital Market Consequences of Business Press Coverage of Management Earnings Guidance

    E-Print Network [OSTI]

    Twedt, Brady J

    2013-06-21T23:59:59.000Z

    This study investigates the role of the business press in disseminating management earnings guidance news to capital market participants. Using a unique sample of over 55,000 articles that relate specifically to management guidance, I find that 48...

  10. Operations improvement in a semiconductor capital equipment manufacturing plant : component level and assembly level inventory management

    E-Print Network [OSTI]

    Wu, Yiming, M. Eng. Massachusetts Institute of Technology

    2012-01-01T23:59:59.000Z

    Semiconductor capital equipment is manufactured in a high-mix and low-volume environment at Varian Semiconductor Equipment business unit of Applied Materials. Due to the demand growth over the past years, Varian has been ...

  11. ECOLOGY & ENVIRONMENTAL SCIENCE Programs of Study The graduate program in Ecology & Environmental Science capitalizes on University

    E-Print Network [OSTI]

    Thomas, Andrew

    Science capitalizes on University strengths in ecology, environmental science, and environmental policy programs in ecology, environmental science, and environmental policy. The EES Graduate Program includes studying a wide range of challenging problems in ecology, environmental science, and environmental policy

  12. Capital, labor, and energy cost prediction in timber harvesting: a microcomputer solution

    E-Print Network [OSTI]

    Kusmertz, Timothy Jon

    1983-01-01T23:59:59.000Z

    Organization Capital. 17 17 Labor 22 Energy. III. CAPITAL COST CALCULATION. 22 25 Depreciation. Taxes, Insurance, and Interest. 25 30 IV. LABOR COST CALCULATION. 36 Nages and Salaries. Fringe Benefits. 36 38 Chapter Page V. ENERGY COST... Summary for Champion International Corporation's Harvesting Unit g2 60 15 List of Equipment in Champion's Harvesting Unit N2 61 Table page 16 Breakdown of Workers in Champion's Harvesting Unit 42 and Their Respective Salary or Wage. . 62 17 Monthly...

  13. Belleville Hydroelectric Project: A {open_quotes}model{close_quotes} project

    SciTech Connect (OSTI)

    Hughes, B.R. [Northwest Hydraulic Consultants Ltd., North Vancouver, British Columbia (Canada); Gemperline, E.J. [Harza Engineering Co., Chicago, IL (United States); Meier, P.E. [American Municipal Power - Ohio, Inc., Westerville, OH (United States)

    1995-12-31T23:59:59.000Z

    With the development of hydropower stations at existing lock and dam structures, there is a need to develop a project layout that will provide efficient power generation with minimal impacts on the existing river conditions. Model studies have proven to be a cost effective method of ensuring that the most appropriate project layout is achieved prior to the large capital investment required for construction. Physical models provide a means of visualizing the overall project, including river flow patterns and sedimentation, and permit the acquisition of numerical data which can be used to aid in the refinement of the project design or to guide the regulatory bodies in assessing the potential impacts. As part of the proposed hydropower add-on at the existing Belleville Lock and Dam, a physical hydraulic model study was undertaken at Northwest Hydraulic Consultants laboratories in Vancouver, British Columbia to aid in the development of a project layout which would meet all project objectives. These objectives included refinement of the approach and tailrace channels to optimize the powerhouse performance and minimize the potential impacts on river navigation.

  14. PROJECT SUMMARY

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy ChinaofSchaeferAprilOverviewEfficiencyofHSSPIAProperty Management PlanPROJECT SUMMARY 1

  15. Hallmark Project

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy ChinaofSchaefer To: CongestionDevelopmentHEADQUARTERSOutreachApril 23, 2013Project

  16. Project Management

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)IntegratedSpeedingTechnical News,Program DirectionProject ATHENA creates

  17. Project Overview

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)IntegratedSpeedingTechnical News,Program DirectionProject ATHENAManagement

  18. Projects | ORNL

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)IntegratedSpeedingTechnical News,Program DirectionProject ATHENAManagementIn ThisPages

  19. Project Gnome

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible forPortsmouth/Paducah47,193.70 Hg MercuryProject Final Report: HPC-Colony IIProject Gnome

  20. Project Title

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible forPortsmouth/Paducah47,193.70 Hg MercuryProject FinalFluids |Storage Research and

  1. NEPA COMPLIANCE SURVEY Project Information Project Title:

    Broader source: Energy.gov (indexed) [DOE]

    Boxes Date: Nov. 11 , 2010 DOE Code: 6740.010.00000 Contractor Code: 8067-451 Project Lead: Anthony Bowler Project Overview 1. Brief project description include anything that...

  2. Evolution of project planning tools in a matrix organization

    SciTech Connect (OSTI)

    Furaus, J.P.; Figueroa-McInteer, C.; McKeever, P.S.; Wisler, D.B. [Sandia National Labs., Albuquerque, NM (United States); Zavadil, J.T. [Infomatrix (United States)

    1996-10-01T23:59:59.000Z

    Until recently, the Corporate Construction Program at Sandia was experiencing difficulties in managing projects: poor planning and cost estimating caused schedule and budget problems. The first step taken was a Microsoft {reg_sign} Project schedule that provides a standard template for scheduling individual construction projects. It is broken down according to the life cycle of the project and prevents the project team from leaving out an important item. A WBS (work breakdown structure) dictionary was also developed that describes how capital and operating funds are used to develop, design, construct, equip, and manage projects. We also developed a matrix chart that maps the planning guide against the major types of construction projects at Sandia. The guide, dictionary, and matrix chart offer enough flexibility that the project manager can make choices about how to structure work, yet ensure that all work rolls up to the cost categories and key DOE WBS elements. As requirements change, the tools can be updated; they also serve as training tools for new project team members.

  3. CAPITAL PLAN UPDATE Fiscal Year 2013 to 2017

    E-Print Network [OSTI]

    Massachusetts at Lowell, University of

    academic and research spaces, increase residential capacity, renew our existing buildings, develop new reduce our backlog of critical maintenance and our energy consumption while we create additional modern enrollment and research growth trends as well as projected future growth in academic programs, sponsored

  4. National Ignition Facility project acquisition plan

    SciTech Connect (OSTI)

    Callaghan, R.W.

    1996-04-01T23:59:59.000Z

    The purpose of this National Ignition Facility Acquisition Plan is to describe the overall procurement strategy planned for the National Ignition Facility (NIF) Project. The scope of the plan describes the procurement activities and acquisition strategy for the following phases of the NIF Project, each of which receives either plant and capital equipment (PACE) or other project cost (OPC) funds: Title 1 and 2 design and Title 3 engineering (PACE); Optics manufacturing facilitization and pilot production (OPC); Convention facility construction (PACE); Procurement, installation, and acceptance testing of equipment (PACE); and Start-up (OPC). Activities that are part of the base Inertial Confinement Fusion (ICF) Program are not included in this plan. The University of California (UC), operating Lawrence Livermore National Laboratory (LLNL) and Los Alamos National Laboratory, and Lockheed-Martin, which operates Sandia National Laboratory (SNL) and the University of Rochester Laboratory for Laser Energetics (UR-LLE), will conduct the acquisition of needed products and services in support of their assigned responsibilities within the NIF Project structure in accordance with their prime contracts with the Department of Energy (DOE). LLNL, designated as the lead Laboratory, will have responsibility for all procurements required for construction, installation, activation, and startup of the NIF.

  5. Livingston Solar Canopy Project The Project

    E-Print Network [OSTI]

    Delgado, Mauricio

    ,000 high efficiency solar panels on canopy structures over two major surface parking areasLivingston Solar Canopy Project The Project: This project entails the installation of more than 40. In conjunction with the existing 1.4 megawatt solar energy facility on this campus, this project will generate

  6. Information Visualization Graduate Project (Group Project)

    E-Print Network [OSTI]

    Rusu, Adrian

    Information Visualization Fall 2011 Graduate Project (Group Project) (100 points total) Handed out:59PM Research Article due by online submission on Sunday, December 11, 2011, 11:59PM Project Demo due last week of classes The idea of the project is to take the knowledge and background that you

  7. Cost of a Ride: The Effects of Densities on Fixed-Guideway Transit Ridership and Capital Costs

    E-Print Network [OSTI]

    Guerra, Erick; Cervero, Robert

    2010-01-01T23:59:59.000Z

    mile. Soaring capital investment costs are today’ s biggestof riders for the investment costs? If so, what minimumrelationship between investment costs and urban densities

  8. Assessment of capital requirements for alternative fuels infrastructure under the PNGV program

    SciTech Connect (OSTI)

    Stork, K.; Singh, M.; Wang, M.; Vyas, A.

    1998-12-31T23:59:59.000Z

    This paper presents an assessment of the capital requirements of using six different fuels in the vehicles with tripled fuel economy (3X vehicles) that the Partnership for a new Generation of Vehicles is currently investigating. The six fuels include two petroleum-based fuels (reformulated gasoline and low-sulfur diesel) and four alternative fuels (methanol, ethanol, dimethyl ether, and hydrogen). This study develops estimates of cumulative capital needs for establishing fuels production and distribution infrastructure to accommodate 3X vehicle fuel needs. Two levels of fuel volume-70,000 barrels per day and 1.6 million barrels per day-were established for meeting 3X-vehicle fuel demand. As expected, infrastructure capital needs for the high fuel demand level are much higher than for the low fuel demand level. Between fuel production infrastructure and distribution infrastructure, capital needs for the former far exceed those for the latter. Among the four alternative fuels, hydrogen bears the largest capital needs for production and distribution infrastructure.

  9. Status report of the EPA`s Air Pollution Prevention and Control Division`s biomass-to-energy development and demonstration projects

    SciTech Connect (OSTI)

    Purvis, C.R. [Environmental Protection Agency, Research Triangle Park, NC (United States); Cleland, J. [Research Triangle Institute, Research Triangle Park, NC (United States); Craig, J.D. [Cratech, Inc., Tahoka, TX (United States)] [and others

    1996-12-31T23:59:59.000Z

    The US Environmental Protection Agency`s (EPA`s) Air Pollution Prevention and Control Division (APPCD) is participating in research, development, and demonstration projects that will convert biomass energy to electrical power, resulting in waste utilization, pollution alleviation, and energy conservation. The goal is to demonstrate the technical, economic, and environmental feasibility of an innovative energy conversion technology. This paper describes the status of each project. The first project is a demonstration of a design that consists of a fixed-bed gasifier, a gas cleaning system, a spark ignited syngas engine, and a diesel dual fuel engine. The technology will use wood waste as fuel and produce approximately 1 MWe. The design of the technology is complete, equipment fabrication is underway, and installation, start-up, testing, and demonstration will follow by September 1996. The second project is a biomass-fueled intergrated-gasifier gas turbine (BIGGT) power plant. Phase 1 is complete and consisted of the design, fabrication, and operation of a 0.5 metric ton per hour (tph) (0.55 tph) pressurized fluidized-bed gasifier with a slipstream hot gas cleanup system. Phase 2 is to increase the feed rate to 1 metric tph (1.1 tph) and uprate the gasifier to operate at 10 atmospheres (981 kPa) with a full scale, dry, hot gas cleanup system capable of being integrated with a 1 MWe rated gas turbine engine. Construction of Phase 2 will begin in the summer of 1996. The third project is a demonstration of a biomass-fueled power plant. The system operates with an open Brayton cycle using a fluidized-bed combustor and heat exchangers to heat compressed air and drive a turbine/generator set. The system discharges clean hot air which can be used for cogeneration applications. The system will use lumber wastes as fuel and will produce approximately 200 kWe. Fabrication is underway, and the demonstration is scheduled to accumulate 8000 hours of operation over 1 to 2 years.

  10. Valuation of Government Policies and Projects

    E-Print Network [OSTI]

    Lucas, Deborah J.

    Governments play a central role in the allocation of capital and risk in the economy. Evaluating the cost to taxpayers of government investments requires an assumption about the government’s cost of capital. Governments ...

  11. UTILITY INVESTMENT IN ON-SITE SOLAR: RISK AND RETURN ANALYSIS FOR CAPITALIZATION AND FINANCING

    E-Print Network [OSTI]

    Kahn, E.

    2011-01-01T23:59:59.000Z

    lying determinants of energy project risk premiums lies in adeterminants of risk for energy technology projects.the elements of risk in energy projects. energy investments.

  12. Preliminary assessment of potential CDM early start projects in Brazil

    SciTech Connect (OSTI)

    Meyers, S.; Sathaye, J.; Lehman, B.; Schumacher, K.; van Vliet, O.; Moreira, J.R.

    2000-11-01T23:59:59.000Z

    The Brazil/US Aspen Global Forum on Climate Change Policies and Programs has facilitated a dialogue between key Brazil and US public and private sector leaders on the subject of the Clean Development Mechanism (CDM). With support from the US government, a cooperative effort between Lawrence Berkeley National Laboratory and the University of Sao Paulo conducted an assessment of a number of projects put forth by Brazilian sponsors. Initially, we gathered information and conducted a screening assessment for ten projects in the energy sector and six projects in the forestry sector. Some of the projects appeared to offer greater potential to be attractive for CDM, or had better information available. We then conducted a more detailed assessment of 12 of these projects, and two other projects that were submitted after the initial screening. An important goal was to assess the potential impact of Certified Emission Reductions (CERs) on the financial performance of projects. With the exception of the two forestry-based fuel displacement projects, the impact of CERs on the internal rate of return (IRR) is fairly small. This is true for both the projects that displace grid electricity and those that displace local (diesel-based) electricity production. The relative effect of CERs is greater for projects whose IRR without CERs is low. CERs have a substantial effect on the IRR of the two short-rotation forestry energy substitution projects. One reason is that the biofuel displaces coke and oil, both of which are carbon-intensive. Another factor is that the product of these projects (charcoal and woodfuel, respectively) is relatively low value, so the revenue from carbon credits has a strong relative impact. CERs also have a substantial effect on the NPV of the carbon sequestration projects. Financial and other barriers pose a challenge for implementation of most of the projects. In most cases, the sponsor lacks sufficient capital, and loans are available only at high interest rate and with substantial guarantee. A few of the projects might go ahead without the benefit of CERs, but most probably would not. Whether the projected revenue from CERs would be sufficient to induce sponsors to proceed with the projects is an important issue that requires further investigation. All of the projects contribute to economic development in Brazil. The forestry projects in particular would create a significant number of rural jobs, and contribute income to rural communities. Some of the carbon sequestration projects would provide environmental benefits with respect to protection of biodiversity and soil.

  13. Trends in U.S. Venture Capital Investments Related to Energy: 1980 through the Third Quarter of 2010

    SciTech Connect (OSTI)

    Dooley, James J.

    2010-11-08T23:59:59.000Z

    This report documents trends in U.S. venture capital investments over the period 1980 through the third quarter of calendar year 2010 (2010 Q1+Q2+Q3). Particular attention is given to U.S. venture capital investments in the energy/industrial sector over the period 1980-2010 Q1+Q2+Q3 as well as in the more recently created cross-cutting category of CleanTech over the period 1995-2010 Q1+Q2+Q3. During the early 1980s, U.S. venture capital investments in the energy/industrial sector accounted for more than 20% of all venture capital investments. However subsequent periods of low energy prices, the deregulation of large aspects of the energy industry, and the emergence of fast growing new industries like computers (both hardware and software), biotechnology and the Internet quickly reduced the priority accorded to energy/industrial investments. To wit, venture capital investments related to the energy/industrial sector accounted for only 1% of the $132 billion (in real 2010 US$) invested in 2000 by the U.S. venture capital community. The significant increase in the real price of oil that began in 2003-2004 correlates with renewed interest and increased investment by the venture capital community in energy/industrial investment opportunities. Venture capital investments for 2009 for the energy/industrial sector accounted for $2.4 billion or slightly more than 13% of all venture capital invested that year. The total venture capital invested in energy/industrial during the first three quarters of 2010 is close to $2.4 billion accounting for slightly less than 15% of all venture capital investments during the first three quarters of 2010. In 2009, the aggregate amount invested in CleanTech was $2.1 billion (11% of the total US venture capital invested in that lean year) and for the first three quarters of 2010 US venture capital investments in CleanTech have already exceeded $2.8 billion (18% of all US venture capital investments made during the first three quarters of 2010). Between 2004 and 2009, U.S. venture capital investments in energy/industrial as well as CleanTech have more than quadrupled in real terms.

  14. Trends in U.S. Venture Capital Investments Related to Energy: 1980 through the Second Quarter of 2010

    SciTech Connect (OSTI)

    Dooley, James J.

    2010-07-29T23:59:59.000Z

    This report documents trends in U.S. venture capital investments over the period 1980 through the second quarter of calendar year 2010 (2010Q1+Q2). Particular attention is given to U.S. venture capital investments in the energy/industrial sector over the period 1980-2010Q1+Q2 as well as in the more recently created cross-cutting category of CleanTech over the period 1995-2010Q1+Q2. During the early 1980s, U.S. venture capital investments in the energy/industrial sector accounted for more than 20% of all venture capital investments. However subsequent periods of low energy prices, the deregulation of large aspects of the energy industry, and the emergence of fast growing new industries like computers (both hardware and software), biotechnology and the Internet quickly reduced the priority accorded to energy/industrial investments. To wit, venture capital investments related to the energy/industrial sector accounted for only 1% of the $119 billion dollars invested in 2000 by the U.S. venture capital community. The significant increase in the real price of oil that began in 2003-2004 correlates with renewed interest and increased investment by the venture capital community in energy/industrial investment opportunities. Venture capital investments for 2009 for the energy/industrial sector accounted for $2.1 billion or slightly more than 13% of all venture capital invested that year. The total venture capital invested in energy/industrial during the first two quarters of 2010 is close to $1.8 billion accounting for 17% of all venture capital investments during the first two quarters of 2010. In 2009, the aggregate amount invested in CleanTech was $1.8 billion (30% of the total US venture capital invested in that lean year) and for the first two quarters of 2010 US venture capital investments in CleanTech have already exceeded $1.9 billion (19% of all US venture capital investments made during the first half of 2010). Between 2004 and 2009, U.S. venture capital investments in energy/industrial as well as CleanTech have more than quadrupled in real terms.

  15. OPEC production: Capital limitations, environmental movements may interfere with expansion plans

    SciTech Connect (OSTI)

    Ismail, I.A.H. (Organization of the Petroleum Exporting Countries, Vienna (Austria))

    1994-05-09T23:59:59.000Z

    Obtaining capital is a critical element in the production expansion plans of OPEC member countries. Another issue that may impact the plans is the environmental taxes that may reduce the call on OPEC oil by 5 million b/d in 2000 and about 16 million b/d in the year 2010. This concluding part of a two-part series discusses the expansion possibilities of non-Middle East OPEC members, OPEC's capital requirements, and environmental concerns. Non-Middle East OPEC includes Algeria, Gabon, Indonesia, Libya, Nigeria, and Venezuela.

  16. Seneca Compressed Air Energy Storage (CAES) Project

    SciTech Connect (OSTI)

    None

    2012-11-30T23:59:59.000Z

    Compressed Air Energy Storage (CAES) is a hybrid energy storage and generation concept that has many potential benefits especially in a location with increasing percentages of intermittent wind energy generation. The objectives of the NYSEG Seneca CAES Project included: for Phase 1, development of a Front End Engineering Design for a 130MW to 210 MW utility-owned facility including capital costs; project financials based on the engineering design and forecasts of energy market revenues; design of the salt cavern to be used for air storage; draft environmental permit filings; and draft NYISO interconnection filing; for Phase 2, objectives included plant construction with a target in-service date of mid-2016; and for Phase 3, objectives included commercial demonstration, testing, and two-years of performance reporting. This Final Report is presented now at the end of Phase 1 because NYSEG has concluded that the economics of the project are not favorable for development in the current economic environment in New York State. The proposed site is located in NYSEG’s service territory in the Town of Reading, New York, at the southern end of Seneca Lake, in New York State’s Finger Lakes region. The landowner of the proposed site is Inergy, a company that owns the salt solution mining facility at this property. Inergy would have developed a new air storage cavern facility to be designed for NYSEG specifically for the Seneca CAES project. A large volume, natural gas storage facility owned and operated by Inergy is also located near this site and would have provided a source of high pressure pipeline quality natural gas for use in the CAES plant. The site has an electrical take-away capability of 210 MW via two NYSEG 115 kV circuits located approximately one half mile from the plant site. Cooling tower make-up water would have been supplied from Seneca Lake. NYSEG’s engineering consultant WorleyParsons Group thoroughly evaluated three CAES designs and concluded that any of the designs would perform acceptably. Their general scope of work included development of detailed project construction schedules, capital cost and cash flow estimates for both CAES cycles, and development of detailed operational data, including fuel and compression energy requirements, to support dispatch modeling for the CAES cycles. The Dispatch Modeling Consultant selected for this project was Customized Energy Solutions (CES). Their general scope of work included development of wholesale electric and gas market price forecasts and development of a dispatch model specific to CAES technologies. Parsons Brinkerhoff Energy Storage Services (PBESS) was retained to develop an air storage cavern and well system design for the CAES project. Their general scope of work included development of a cavern design, solution mining plan, and air production well design, cost, and schedule estimates for the project. Detailed Front End Engineering Design (FEED) during Phase 1 of the project determined that CAES plant capital equipment costs were much greater than the $125.6- million originally estimated by EPRI for the project. The initial air storage cavern Design Basis was increased from a single five million cubic foot capacity cavern to three, five million cubic foot caverns with associated air production wells and piping. The result of this change in storage cavern Design Basis increased project capital costs significantly. In addition, the development time required to complete the three cavern system was estimated at approximately six years. This meant that the CAES plant would initially go into service with only one third of the required storage capacity and would not achieve full capability until after approximately five years of commercial operation. The market price forecasting and dispatch modeling completed by CES indicated that the CAES technologies would operate at only 10 to 20% capacity factors and the resulting overall project economics were not favorable for further development. As a result of all of these factors, the Phase 1 FEED developed an installe

  17. Iskuulpa Watershed ProjectIskuulpa Watershed Project BPA Project # 199506001BPA Project # 199506001

    E-Print Network [OSTI]

    Hydroelectric Power Project impacts Improve natural salmonid habitat and production #12;Project ActivitiesProject Activities Land purchaseLand purchase HEP evaluationHEP evaluation Rest from livestockRest from livestock;Project ActivitiesProject Activities Land purchaseLand purchase HEP evaluationHEP evaluation Rest from

  18. CAPITAL ASSET MANAGEMENT (CAM) NEWS 2014 CAM has barcode scanners available for use when inventorying your equipment.

    E-Print Network [OSTI]

    records can be updated at any time via the Capital Asset Management section (CAMs) within EBS - FinanceCAPITAL ASSET MANAGEMENT (CAM) NEWS 2014 CAM has barcode scanners available for use when. You must have Role 6 ­ CAM Processor, in EBS - Finance, to edit/update asset records. For more

  19. Project Name Project Number Tagging Type

    E-Print Network [OSTI]

    Project Name Project Number Primary Tagging Type Secondary Tagging Type Fish Species Tagging/ Secondary Legal Driver (BiOp, MOA, Accord, etc.) Tagging Purpose Funded Entity Tagging Location Retrieval CWT Recovery Project 2010-036-00 CWT PIT Chinook, coho retrieval, analysis, address PSMFC sampling

  20. Projects | Department of Energy

    Office of Environmental Management (EM)

    Projects Projects All 1703 1705 ATVM Current Portfolio 32.4 B in Loans 55 K Jobs Current Portfolio Loans 32.4 B Jobs 55,000 Loan Program Office Projects 1703 1705 ATVM...

  1. CRSP Power Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    expenses of the project each year, and receive all of the energy it produces. Salt Lake City AreaIntegrated Projects: Power from the Colorado River Storage Project plants was...

  2. Project Selection - Record Keeping

    E-Print Network [OSTI]

    Howard, Jeff W.

    2005-05-10T23:59:59.000Z

    4-H members have many project areas to choose from, depending on where they live. Members should consult with their parents and 4-H leaders when choosing a project. This publication outlines project considerations....

  3. Super Projects (Arkansas)

    Broader source: Energy.gov [DOE]

    A 2004 amendment to the state constitution authorizes the state to attract super projects by issuing bonds to fund a project’s infrastructure, limited to 5% of the net general revenues during the...

  4. Asset sharing and stakeholder arrangements : human capital investments, the distribution of powers, and the role of property rights and economic institutions

    E-Print Network [OSTI]

    Hughes, J. Jerome (Jermaine Jerome)

    2014-01-01T23:59:59.000Z

    Theories of human capital investment, which emphasize encouraging and protecting investments in human capital, have become salient in rationalizing the adoption of firm asset-sharing and employee stakeholder arrangements, ...

  5. Project BETA Cover Page

    E-Print Network [OSTI]

    Cover Page, Project BETA

    2012-01-01T23:59:59.000Z

    and Distribution of the Project BETA articles were funded inproduct is discussed in the BETA articles. Western JournalProject BETA: Best practices in Evaluation and Treatment of

  6. Project Finance and Investments

    Broader source: Energy.gov [DOE]

    Plenary III: Project Finance and Investment Project Finance and Investments Chris Cassidy, National Business Renewable Energy Advisor, U.S. Department of Agriculture

  7. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    3 rd Quarter Overall Contract and Project Management Performance Metrics and Targets ContractProject Management Performance Metrics FY 2009 Target FY 2009 Actual Comment 1....

  8. Operations Cost Allocation Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations Consolidation Project Operations Consolidation Project (OCP) Cost Allocation Presentation - September 20, 2011 OCP Cost Allocation Customer Presentation List of Acronyms...

  9. Clean Coal Projects (Virginia)

    Broader source: Energy.gov [DOE]

    This legislation directs the Virginia Air Pollution Control Board to facilitate the construction and implementation of clean coal projects by expediting the permitting process for such projects.

  10. Falls Creek Hydroelectric Project

    SciTech Connect (OSTI)

    Gustavus Electric Company; Richard Levitt; DOE Project Officer - Keith Bennett

    2007-06-12T23:59:59.000Z

    This project was for planning and construction of a 700kW hydropower project on the Fall River near Gustavus, Alaska.

  11. Consumption, Social Capital, and the 'Industrious Revolution' in Early Modern Germany

    E-Print Network [OSTI]

    Ogilvie, Sheilagh

    Consumption, Social Capital, and the “Industrious Revolution” in Early Modern Germany SHEILAGH OGILVIE Faculty of Economics, University of Cambridge Acknowledgements: I am grateful to Marco Belfanti, André... ; labour; discrimination; gender; Germany 1 Expanding market consumption is widely ascribed a key role in European economic growth before industrialization. A “Consumer Revolution” between 1650 and 1800 is thought to have seen the middle classes...

  12. EDUCATION: Energy capital's colleges tailor new programs to oil and gas

    E-Print Network [OSTI]

    Alvarez, Pedro J.

    EDUCATION: Energy capital's colleges tailor new programs to oil and gas industry (Wednesday and prospective computer science majors interested in careers with the oil and gas industry. "The hardest in oil and gas activity. This city's entire network of academic institutions is busy remaking itself

  13. PLEASE READ ALL INSTRUCTIONS BEFORE BEGINNING INVENTORY Procedures for Completing Annual Capital Equipment Inventory

    E-Print Network [OSTI]

    Provancher, William

    PLEASE READ ALL INSTRUCTIONS BEFORE BEGINNING INVENTORY Procedures for Completing Annual Capital Equipment Inventory 1. Check off each item on the inventory report, as it is located. Place one of the small white inventory FY 2011 stickers on the equipment, as it is located. This will eliminate counting

  14. GREEN BUILDING TRENDS How Green Building Impacted the National Capital Region Between 2003 and 2009

    E-Print Network [OSTI]

    GREEN BUILDING TRENDS How Green Building Impacted the National Capital Region Between 2003 and 2009 ecofriend.org 2 OVERVIEW What is LEED®? The LEED green building certification program is rapidly emerging as the standard in sustainable building design, construction, and operations. Scale of LEED Development Through

  15. The problem of non-renewable energy resources in the production of physical capital

    E-Print Network [OSTI]

    Nesterov, Yurii

    2007/8 The problem of non-renewable energy resources in the production of physical capital Agustin Pérez-Barahona #12;CORE DISCUSSION PAPER 2007/8 The problem of non-renewable energy resources-run growth, although energy is produced by means of non-renewable energy resources. The mechanism behind

  16. Cultural Capital in Spain'S MeMory WarS Dr. SebaStiaan Faberoberlin College

    E-Print Network [OSTI]

    Andrews, Peter B.

    History MeMory trutH Cultural Capital in Spain'S MeMory WarS Dr. SebaStiaan Faberoberlin College Since the late 1990s, Spain has seen a series of public disputes over the historical memory tell it--and the relationship that today's Spain should have with that past. In the past fifteen years

  17. The adaptive value of energy storage and capital breeding in seasonal environments

    E-Print Network [OSTI]

    Heino, Mikko

    where reproductive values are used to optimise energy allocation and diapause strategies over the yearThe adaptive value of energy storage and capital breeding in seasonal environments Øystein Varpe zooplankton inhabiting seasonal, high-latitude environments. We apply a state-dependent life history model

  18. *Excludes capital investment for P&R facility EFFECTS OF MAP-21 ON SEAMLESS TRANSIT FROM

    E-Print Network [OSTI]

    *Excludes capital investment for P&R facility EFFECTS OF MAP-21 ON SEAMLESS TRANSIT FROM FORT BEND is not available for residents making the commute from FBC to Downtown Houston. · Researchers estimate latent demand for 1,700+ P&R one-way passenger trips per day. SEAMLESS TRANSIT COST · Federal funds may

  19. A review of "Florence Ducal Capital, 1530-1630" by R. Burr Litchfield

    E-Print Network [OSTI]

    Judith, Brown

    2009-01-01T23:59:59.000Z

    reviews 1 R. Burr Litchfield. Florence Ducal Capital, 1530-1630. ACLS Humanities E-Book, 2008. Review by judith c. brown, wesleyan university. This is an important book. It is the culmination of years of work by one of the leading historians...

  20. Investing in human and natural capital: An alternative paradigm for sustainable development in Awassa, Ethiopia

    E-Print Network [OSTI]

    Vermont, University of

    strategy. Local stakeholders identified firewood shortages, degradation of croplands, rising lake levels necessary for major capital investments of any kind. The atelier therefore helped local participants developed countries on the planet. Human life is impossible without adequate food, water and energy, yet

  1. ORGANIZATIONAL SUPPORT FOR INTRAPRENEURSHIP AND ITS INTERACTION WITH HUMAN CAPITAL TO

    E-Print Network [OSTI]

    Yanikoglu, Berrin

    1 ORGANIZATIONAL SUPPORT FOR INTRAPRENEURSHIP AND ITS INTERACTION WITH HUMAN CAPITAL TO ENHANCE separately the individual but not the interaction effects of organizational support mechanisms and human resources of an organization and the level of organizational support provided for the intrapreneurial

  2. INICIO POLTICA ECONOMA MUNDO ESTADOS CAPITAL SOCIEDAD Y JUSTICIA CIENCIAS CULTURA ESPECTCULOS DEPORTES Noticias del da

    E-Print Network [OSTI]

    Islas, León

    INICIO POLÍTICA ECONOMÍA MUNDO ESTADOS CAPITAL SOCIEDAD Y JUSTICIA CIENCIAS CULTURA ESPECTÁCULOS DEPORTES Noticias del día No hay noticias publicadas. Ciencias No hay noticias publicadas. BUSCAR Buscar en, del Instituto de Ciencias del Mar y Limnología de la UNAM La Jornada en línea Publicado: 24/01/2012 12

  3. Deforestation and Cattle Ranching in the Brazilian Amazon: External Capital and Household Processes

    E-Print Network [OSTI]

    Walker, Robert T.

    Deforestation and Cattle Ranching in the Brazilian Amazon: External Capital and Household Processes decomposes recent deforestation in four study areas in the Brazilian Amazon into components associated deforestation with respect to the proximate causes of their farming systems, and the household drivers

  4. Cyclical adjustment, capital-labor substitution and total factor productivity convergence East Germany after unification

    E-Print Network [OSTI]

    Pfeifer, Holger

    Cyclical adjustment, capital-labor substitution and total factor productivity convergence ­ East integration and massive help from the Federal Government East German productivity catching up faded out in the nineties. This paper presents panel-data estimates of the productivity adjustment based on a production

  5. Poverty Trap with Convex Production Function: The role of Public and Private Capital

    E-Print Network [OSTI]

    Bandyopadhyay, Antar

    Poverty Trap with Convex Production Function: The role of Public and Private Capital Kumar Aniket University of Cambridge 20 September 2014 Abstract. The objective of the paper is to explain why poverty, there is a poverty trap region or a threshold below which the economy is in a low steady state. The paper shows

  6. Heterogeneous capital stocks and the optimal timing for CO2 abatement

    E-Print Network [OSTI]

    June 2006 Abstract Some recent research suggests benefits to a delayed CO2 emission reduction strategy delay may be small. A delayed start for CO2 emission reductions, which accelerates reduction in laterHeterogeneous capital stocks and the optimal timing for CO2 abatement Mark Jaccard *, Nic Rivers

  7. Manhattan Project | Department of Energy

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Manhattan Project Manhattan Project Manhattan Project New Manhattan Project Interactive Website The Department of Energy traces its origins to World War II and the Manhattan...

  8. MRIP Operations Team Projects (2012 Funded) Project Name Project Description Project Objectives

    E-Print Network [OSTI]

    MRIP Operations Team Projects (2012 Funded) Project Name Project Description Project Objectives vessel registries to conduct recreational catch and effort surveys. Develop a recreational fishing. Accuracy Funded 2012 Oregon Shore and EstuaryBoat Survey Design Review Develop a new or revised

  9. Laboratory technology research: Abstracts of FY 1998 projects

    SciTech Connect (OSTI)

    NONE

    1998-11-01T23:59:59.000Z

    The Laboratory Technology Research (LTR) program supports high-risk, multidisciplinary research partnerships to investigate challenging scientific problems whose solutions have promising commercial potential. These partnerships capitalize on two great strengths of the country: the world-class basic research capability of the DOE Office of Science (SC) national laboratories and the unparalleled entrepreneurial spirit of American industry. Projects supported by the LTR program in FY 1998 explore the applications of basic research advances relevant to DOE`s mission over a full range of scientific disciplines. The program presently emphasizes three critical areas of mission-related research: advanced materials, intelligent processing and manufacturing research, and environmental and biomedical research. Abstracts for 85 projects are contained in this report.

  10. The Distorted Transformation of Mexico: Arbitralism and Developmentalism, and Political Capitalism and Subcapitalism. A Pathway towards Balancing Capitalism and Balanced Development, or Demdevelopment

    E-Print Network [OSTI]

    Nunez, Ramon

    2013-01-01T23:59:59.000Z

    projects (integrated by both the electoral authority and the Legislature) as an institutionally obligation for governments´ planning and budgeting.

  11. Senior projectS corporate Sponsored

    E-Print Network [OSTI]

    Stuart, Josh

    --Professor, Computer Engineering | http://users.soe.ucsc. edu/~larrabee/Site/Professor_Tracy_Larrabee.html Charlie McSenior projectS program corporate Sponsored Partner's Day May 31, 2012 Baskin School of Engineering earning their engineering degree and fulfilling this capstone design sequence. Our students who have

  12. Livingston Campus Geothermal Project The Project

    E-Print Network [OSTI]

    Delgado, Mauricio

    Livingston Campus Geothermal Project The Project: Geothermal power is a cost effective, reliable is a Closed Loop Geothermal System involving the removal and storage of approximately four feet of dirt from the entire Geothermal Field and the boring of 321 vertical holes reaching a depth of 500 feet. These holes

  13. The Capital Structure and Financial Management Practices of the Texas Cattle Feeding Industry.

    E-Print Network [OSTI]

    Dietrich, Raymond A.; Martin, J. R.; Ljungdahl, P. W.

    1972-01-01T23:59:59.000Z

    examines the capital structure and financial management practices of feedlots in the Panhandle-Plains area of Texas. More specif- ically, the study considers the characteristics of the Panhandle-Plains cattle feeding industry, the asset-debt structure... high proportion of the larger lots and a majority of all feedlots are incorporated. These incorporated feedlots account for about 80 percent of the cattle fed in the Texas Panhandle-Plains area. Approximately 50 percent of the total assets...

  14. Systematic Engine Uprate Technology Development and Deployment for Pipeline Compressor Engines through Increased Torque

    SciTech Connect (OSTI)

    Dennis Schmitt; Daniel Olsen

    2005-09-30T23:59:59.000Z

    Three methods were utilized to analyze key components of slow-speed, large-bore, natural gas integral engines. These three methods included the application of computational fluid dynamics (CFD), dynamic modal analysis using finite element analysis (FEA), and a stress analysis method also using FEA. The CFD analysis focuses primarily on the fuel mixing in the combustion chamber of a TLA engine. Results indicate a significant increase in the homogeneity of the air and fuel using high-pressure fuel injection (HPFI) instead of standard low-pressure mechanical gas admission valve (MGAV). A modal analysis of three engine crankshafts (TLA-6, HBA-6, and GMV-10) is developed and presented. Results indicate that each crankshaft has a natural frequency and corresponding speed that is well away from the typical engine operating speed. A frame stress analysis method is also developed and presented. Two different crankcases are examined. A TLA-6 crankcase is modeled and a stress analysis is performed. The method of dynamic load determination, model setup, and the results from the stress analysis are discussed. Preliminary results indicate a 10%-15% maximum increase in frame stress due to a 20% increase in HP. However, the high stress regions were localized. A new hydraulically actuated mechanical fuel valve is also developed and presented. This valve provides equivalent high-energy (supersonic) fuel injection comparable to a HPFI system, at 1/5th of the natural gas fuel pressure. This valve was developed in cooperation with the Dresser-Rand Corporation.

  15. Maximizing nuclear power plant performance via mega-uprates and subsequent license renewal

    E-Print Network [OSTI]

    DeWitte, Jacob D. (Jacob Dominic)

    2014-01-01T23:59:59.000Z

    The goal of this thesis is to develop a methodology to evaluate the engineering and economic implications of maximizing performance of the United States' commercial fleet of nuclear power plants. This methodology addresses ...

  16. Long-Term Wisconsin Capital Assets Deferral and Wisconsin-Source Asset Exclusion Qualified Wisconsin Business Certification (Wisconsin)

    Broader source: Energy.gov [DOE]

    WEDC may certify businesses as a “Qualified Wisconsin Business”. The designation allows investors with WI capital gains tax liability to both defer that tax liability and if an investment is...

  17. How Can Child Labor Lead to an Increase in Human Capital of Child Laborers and What Are Policy Implications?

    E-Print Network [OSTI]

    Luong, Quoc Viet

    2011-01-01T23:59:59.000Z

    How Can Child Labor Lead to an Increase in Human Capital ofAbstract How Can Child Labor Lead to an Increase in Humanshows that child labor leads to an increase in human

  18. Cost of Capital and Regulator’s Preferences: Investigation into a new method of estimating regulatory bias

    E-Print Network [OSTI]

    Sancetta, Alessio; Satchell, Stephen E

    When computing regulated prices, the standard method is the capital asset pricing model (CAPM) which involves the estimation of a single parameter: the beta of the company. Yet, these computational methods fail to take into account any preference...

  19. Using Pinch Technology to Explore Trade-Offs Between Energy Cost, Capital Cost, Process Modifications, and Utility Selection 

    E-Print Network [OSTI]

    McMullan, A. S.

    1988-01-01T23:59:59.000Z

    on the total cost of installing and operatlng a process. Understanding the impact of these decisions in the context of the overall process can lead to significant savings in both capital and operating costs. Full investigation of these interactions through...

  20. Private equity and venture capital in emerging markets : a case study of Egypt and the MENA region

    E-Print Network [OSTI]

    Ismail, Ayman (Ayman Adel), 1973-

    2009-01-01T23:59:59.000Z

    Private equity and venture capital investments in emerging markets grew significantly over the past five years (2003-2008), both in absolute and relative terms. In this study, we examine the industry's role in emerging ...

  1. The cartography of capitalism: cartographic evidence for the emergence of the capitalist world-system in early modern europe 

    E-Print Network [OSTI]

    Woodfin, Thomas McCall

    2009-05-15T23:59:59.000Z

    , but only in so far as cartography seems embedded in some of the long-term structural changes of the transition from feudalism to capitalism. The world economy and its new geographical division of labour was produced with the aid of geographical.... Advancements in mathematics led to increasingly scientific land surveying techniques. David Harvey asserts that The history of cartography in the transition from feudalism to capitalism has, like the history of time-keeping, been very much about refinement...

  2. The cartography of capitalism: cartographic evidence for the emergence of the capitalist world-system in early modern europe 

    E-Print Network [OSTI]

    Woodfin, Thomas McCall

    2008-10-10T23:59:59.000Z

    , but only in so far as cartography seems embedded in some of the long-term structural changes of the transition from feudalism to capitalism. The world economy and its new geographical division of labour was produced with the aid of geographical.... Advancements in mathematics led to increasingly scientific land surveying techniques. David Harvey asserts that The history of cartography in the transition from feudalism to capitalism has, like the history of time-keeping, been very much about refinement...

  3. Information Technology Project Management

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2012-12-03T23:59:59.000Z

    The Order provides program and project management direction for the acquisition and management of IT projects, investments, and initiatives. Cancels DOE G 200.1-1. Admin Chg 1, dated 1-16-2013, cancels DOE O 415.1.

  4. The 4-H Project

    E-Print Network [OSTI]

    Howard, Jeff W.

    2005-05-10T23:59:59.000Z

    As a 4-H volunteer, you will find that projects are useful tools for teaching a wide variety of skills to young people. This publication will help you plan and evaluate 4-H learning projects....

  5. Information Technology Project Management

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2012-12-03T23:59:59.000Z

    The Order provides program and project management direction for the acquisition and management of IT projects, investments, and initiatives. Cancels DOE G 200.1-1. Admin Chg 1 approved 1-16-2013.

  6. GHPsRUS Project

    SciTech Connect (OSTI)

    Battocletti, Liz

    2013-07-09T23:59:59.000Z

    The GHPsRUS Project's full name is "Measuring the Costs and Benefits of Nationwide Geothermal Heat Pump Deployment." The dataset contains employment and installation price data collected by four economic surveys: (1)GHPsRUS Project Manufacturer & OEM Survey, (2) GHPsRUS Project Geothermal Loop Survey, (3) GHPsRUS Project Mechanical Equipment Installation Survey, and (4) GHPsRUS Geothermal Heat Pump Industry Survey

  7. GHPsRUS Project

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Battocletti, Liz

    The GHPsRUS Project's full name is "Measuring the Costs and Benefits of Nationwide Geothermal Heat Pump Deployment." The dataset contains employment and installation price data collected by four economic surveys: (1)GHPsRUS Project Manufacturer & OEM Survey, (2) GHPsRUS Project Geothermal Loop Survey, (3) GHPsRUS Project Mechanical Equipment Installation Survey, and (4) GHPsRUS Geothermal Heat Pump Industry Survey

  8. WIPP Projects Interative Map

    Broader source: Energy.gov [DOE]

    View WIPP Projects in a larger map. To report corrections, please email WeatherizationInnovation@ee.doe.gov.

  9. Bacteria TMDL Projects 

    E-Print Network [OSTI]

    Wythe, Kathy

    2007-01-01T23:59:59.000Z

    of the projects are listed below. ? Peach CreekWater Quality Improvement Project ? Monitoring and Educational Programs Focused on Bacteria and Nutrient Runoff on Dairy Operations in the LeonWatershed ? Development of the Plum CreekWPP ? Impact of Proper... Star Healthy Streams * ? Environmental Management of Grazing Lands * *TWRI-managed projects More information on the initiative is available at www.tsswcb.state.tx.us/managementprogram/ initiatives/bacteria. Bacteria Projects Across the State...

  10. Kansas Advanced Semiconductor Project

    SciTech Connect (OSTI)

    Baringer, P.; Bean, A.; Bolton, T.; Horton-Smith, G.; Maravin, Y.; Ratra, B.; Stanton, N.; von Toerne, E.; Wilson, G.

    2007-09-21T23:59:59.000Z

    KASP (Kansas Advanced Semiconductor Project) completed the new Layer 0 upgrade for D0, assumed key electronics projects for the US CMS project, finished important new physics measurements with the D0 experiment at Fermilab, made substantial contributions to detector studies for the proposed e+e- international linear collider (ILC), and advanced key initiatives in non-accelerator-based neutrino physics.

  11. Product Guide Project Standard and Project Professional

    E-Print Network [OSTI]

    Narasayya, Vivek

    ................................................................................................................................................................6 Manage Projects and Programs, or other intellectual property that are the subject matter of this document. #12;Table of Contents .......................................................................................................9 Make It Yours ­ Personalize the Ribbon

  12. Sandia National Laboratories: Reference Model Project (RMP)

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    * wave energy converters Comments are closed. Renewable Energy Wind Energy Wind Plant Optimization Test Site Operations & Maintenance Safety: Test Facilities Capital Equipment...

  13. EMPLOYMENT IMPACTS OF GEOTHERMAL ELECTRIC PROJECTS

    Office of Scientific and Technical Information (OSTI)

    costs had inflated over the three year interval, but that neither wages nor worker productivity had changed. The inflation factor used was the Producer Price index for Capital...

  14. TULSA UNIVERSITY PARAFFIN DEPOSITION PROJECTS

    SciTech Connect (OSTI)

    Michael Volk; Cem Sarica

    2003-10-01T23:59:59.000Z

    As oil and gas production moves to deeper and colder water, subsea multiphase production systems become critical for economic feasibility. It will also become increasingly imperative to adequately identify the conditions for paraffin precipitation and predict paraffin deposition rates to optimize the design and operation of these multiphase production systems. Although several oil companies have paraffin deposition predictive capabilities for single-phase oil flow, these predictive capabilities are not suitable for the multiphase flow conditions encountered in most flowlines and wellbores. For deepwater applications in the Gulf of Mexico, it is likely that multiphase production streams consisting of crude oil, produced water and gas will be transported in a single multiphase pipeline to minimize capital cost and complexity at the mudline. Existing single-phase (crude oil) paraffin deposition predictive tools are clearly inadequate to accurately design these pipelines because they do not account for the second and third phases, namely, produced water and gas. The objective of this program is to utilize the current test facilities at The University of Tulsa, as well as member company expertise, to accomplish the following: enhance our understanding of paraffin deposition in single and two-phase (gas-oil) flows; conduct focused experiments to better understand various aspects of deposition physics; and, utilize knowledge gained from experimental modeling studies to enhance the computer programs developed in the previous JIP for predicting paraffin deposition in single and two-phase flow environments. These refined computer models will then be tested against field data from member company pipelines. The following deliverables are scheduled during the first three projects of the program: (1) Single-Phase Studies, with three different black oils, which will yield an enhanced computer code for predicting paraffin deposition in deepwater and surface pipelines. (2) Two-Phase Studies, with a focus on heat transfer and paraffin deposition at various pipe inclinations, which will be used to enhance the paraffin deposition code for gas-liquid flow in pipes. (3) Deposition Physics and Water Impact Studies, which will address the aging process, improve our ability to characterize paraffin deposits and enhance our understanding of the role water plays in paraffin deposition in deepwater pipelines. As in the previous two studies, knowledge gained in this suite of studies will be integrated into a state-of-the-art three-phase paraffin deposition computer program.

  15. Breckinridge Project, initial effort. Report IX. Operating cost estimate

    SciTech Connect (OSTI)

    none,

    1982-01-01T23:59:59.000Z

    Operating costs are normally broken into three major categories: variable costs including raw materials, annual catalyst and chemicals, and utilities; semi-variable costs including labor and labor related cost; and fixed or capital related charges. The raw materials and utilities costs are proportional to production; however, a small component of utilities cost is independent of production. The catalyst and chemicals costs are also normally proportional to production. Semi-variable costs include direct labor, maintenance labor, labor supervision, contract maintenance, maintenance materials, payroll overheads, operation supplies, and general overhead and administration. Fixed costs include local taxes, insurance and the time value of the capital investment. The latter charge often includes the investor's anticipated return on investment. In determining operating costs for financial analysis, return on investment (ROI) and depreciation are not treated as cash operating costs. These costs are developed in the financial analysis; the annual operating cost determined here omits ROI and depreciation. Project Annual Operating Costs are summarized in Table 1. Detailed supporting information for the cost elements listed below is included in the following sections: Electrical, catalyst and chemicals, and salaries and wages.

  16. The CHPRC Columbia River Protection Project Quality Assurance Project Plan

    SciTech Connect (OSTI)

    Fix, N. J.

    2008-11-30T23:59:59.000Z

    Pacific Northwest National Laboratory researchers are working on the CHPRC Columbia River Protection Project (hereafter referred to as the Columbia River Project). This is a follow-on project, funded by CH2M Hill Plateau Remediation Company, LLC (CHPRC), to the Fluor Hanford, Inc. Columbia River Protection Project. The work scope consists of a number of CHPRC funded, related projects that are managed under a master project (project number 55109). All contract releases associated with the Fluor Hanford Columbia River Project (Fluor Hanford, Inc. Contract 27647) and the CHPRC Columbia River Project (Contract 36402) will be collected under this master project. Each project within the master project is authorized by a CHPRC contract release that contains the project-specific statement of work. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by the Columbia River Project staff.

  17. CAPITAL REGION

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy China U.S. Department ofJune 2,The BigSidingState6 (2-91)A (04-86)SnapshotCAOmemo.pdf t

  18. River Protection Project (RPP) Project Management Plan

    SciTech Connect (OSTI)

    SEEMAN, S.E.

    2000-04-01T23:59:59.000Z

    The U.S. Department of Energy (DOE), in accordance with the Strom Thurmond National Defense Authorization Act for Fiscal Year 1999, established the Office of River Protection (ORP) to successfully execute and manage the River Protection Project (RPP), formerly known as the Tank Waste Remediation System (TWRS). The mission of the RPP is to store, retrieve, treat, and dispose of the highly radioactive Hanford tank waste in an environmentally sound, safe, and cost-effective manner. The team shown in Figure 1-1 is accomplishing the project. The ORP is providing the management and integration of the project; the Tank Farm Contractor (TFC) is responsible for providing tank waste storage, retrieval, and disposal; and the Privatization Contractor (PC) is responsible for providing tank waste treatment.

  19. Battleground Energy Recovery Project

    SciTech Connect (OSTI)

    Daniel Bullock

    2011-12-31T23:59:59.000Z

    In October 2009, the project partners began a 36-month effort to develop an innovative, commercial-scale demonstration project incorporating state-of-the-art waste heat recovery technology at Clean Harbors, Inc., a large hazardous waste incinerator site located in Deer Park, Texas. With financial support provided by the U.S. Department of Energy, the Battleground Energy Recovery Project was launched to advance waste heat recovery solutions into the hazardous waste incineration market, an area that has seen little adoption of heat recovery in the United States. The goal of the project was to accelerate the use of energy-efficient, waste heat recovery technology as an alternative means to produce steam for industrial processes. The project had three main engineering and business objectives: Prove Feasibility of Waste Heat Recovery Technology at a Hazardous Waste Incinerator Complex; Provide Low-cost Steam to a Major Polypropylene Plant Using Waste Heat; and ï?· Create a Showcase Waste Heat Recovery Demonstration Project.

  20. User's manual for the INDCEPT code for estimating industrial steam boiler plant capital investment costs

    SciTech Connect (OSTI)

    Bowers, H I; Fuller, L C; Hudson, II, C R

    1982-09-01T23:59:59.000Z

    The INDCEPT computer code package was developed to provide conceptual capital investment cost estimates for single- and multiple-unit industrial steam boiler plants. Cost estimates can be made as a function of boiler type, size, location, and date of initial operation. The output includes a detailed breakdown of the estimate into direct and indirect costs. Boiler plant cost models are provided to reflect various types and sources of coal and alternate means of sulfur and particulate removal. Cost models are also included for low-Btu and medium-Btu gas produced in coal gasification plants.

  1. Audit of the internal control structure of the Department of Energy`s Working Capital Fund

    SciTech Connect (OSTI)

    NONE

    1997-10-08T23:59:59.000Z

    The Subcommittee on Energy and Water Development of the Committee on Appropriations, in its report dated July 16, 1996, approved the implementation of a Working Capital Fund (Fund) at the U.S. Department of Energy. The Subcommittee also directed the Office of Inspector General to conduct periodic audits of the Fund. This audit was conducted to determine if the Department established an effective system of controls over the Fund. The specific objectives were to determine if internal controls were sufficient to ensure that appropriate costs were allocated in a reasonable and unbiased manner and in a way what was consistent with the expectations established by the Congress.

  2. Office of the Chief Human Capital Officer (HC-1) | Department of Energy

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 111 1,613 122Commercial602 1,39732onMake YourDepartment ofCDepartmentthe Chief Human Capital

  3. BY 2011 DOE IT Capital Plan 9/18/09 | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: Since the YouTube platform is alwaysISOSource1-01 AuditRevised: January 2005BY 2011 DOE IT Capital

  4. Operational Waste Volume Projection

    SciTech Connect (OSTI)

    STRODE, J.N.

    1999-08-24T23:59:59.000Z

    Waste receipts to the double-shell tank system are analyzed and wastes through the year 2018 are projected based on assumption as of July 1999. A computer simulation of site operations is performed, which results in projections of tank fill schedules, tank transfers, evaporator operations, tank retrieval, and aging waste tank usage. This projection incorporates current budget planning and the clean-up schedule of the Tri-Party Agreement.

  5. Operational Waste Volume Projection

    SciTech Connect (OSTI)

    STRODE, J.N.

    2000-08-28T23:59:59.000Z

    Waste receipts to the double-shell tank system are analyzed and wastes through the year 2015 are projected based on generation trends of the past 12 months. A computer simulation of site operations is performed, which results in projections of tank fill schedules, tank transfers, evaporator operations, tank retrieval, and aging waste tank usage. This projection incorporates current budget planning and the clean-up schedule of the Tri-Party Agreement. Assumptions were current as of June. 2000.

  6. Operational waste volume projection

    SciTech Connect (OSTI)

    Koreski, G.M.

    1996-09-20T23:59:59.000Z

    Waste receipts to the double-shell tank system are analyzed and wastes through the year 2015 are projected based on generation trends of the past 12 months. A computer simulation of site operations is performed, which results in projections of tank fill schedules, tank transfers, evaporator operations, tank retrieval, and aging waste tank usage. This projection incorporates current budget planning and the clean-up schedule of the Tri-Party Agreement. Assumptions were current as of June 1996.

  7. Project: BELLA Bldg. #: 71

    E-Print Network [OSTI]

    TO CONSTRUCTION AS OF 10/4/2011 Current/Approved Projects Project: Solar Energy Research Center Bldg. #:TBD. #: TBD Affected Area: R1 Road & V Road (58) Dates: 8/2011 - 9/2013 6 Small Projects: A. B50 Electrical/1/2014 N3 (58) 42 11/1/2011 2/1/2014 M-1 (35) 12 10/1/2010 11/1/2011 B81 (21) 18 10/1/2010 11/1/2011 V Road

  8. National Biomedical Tracer Facility: Project definition study

    SciTech Connect (OSTI)

    Heaton, R.; Peterson, E. [Los Alamos National Lab., NM (United States); Smith, P. [Smith (P.A.) Concepts and Designs (United States)

    1995-05-31T23:59:59.000Z

    The Los Alamos National Laboratory is an ideal institution and New Mexico is an ideal location for siting the National Biomedical Tracer Facility (NBTF). The essence of the Los Alamos proposal is the development of two complementary irradiation facilities that combined with our existing radiochemical processing hot cell facilities and waste handling and disposal facilities provide a low cost alternative to other proposals that seek to satisfy the objectives of the NBTF. We propose the construction of a 30 MeV cyclotron facility at the site of the radiochemical facilities, and the construction of a 100 MeV target station at LAMPF to satisfy the requirements and objectives of the NBTF. We do not require any modifications to our existing radiochemical processing hot cell facilities or our waste treatment and disposal facilities to accomplish the objectives of the NBTF. The total capital cost for the facility defined by the project definition study is $15.2 M. This cost estimate includes $9.9 M for the cyclotron and associated facility, $2.0 M for the 100 MeV target station at LAMPF, and $3.3 M for design.

  9. 2015 Technology Innovation Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    for RTU and Lighting Retrofits Energy Efficiency TIP 140: Energy Efficiency Emerging Technology Assessment and Demonstration Projects TIP 261: Determining and Improving the...

  10. Custom Renewable Energy Projects

    Broader source: Energy.gov [DOE]

    Project development assistance funding is available for a variety of purposes, including grant writing, feasibility studies, or technical assistance with design, permitting, or utility interconne...

  11. Mascoma: Frontier Biorefinery Project

    Broader source: Energy.gov [DOE]

    This project involves the construction and operation of a biorefinery that produces ethanol and other co-products from cellulosic materials through advanced consolidated bioprocessing.

  12. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    by FY12. 95% Line Item 85% Cleanup 97% Line Item 85% Cleanup EVM represents Earned Value Management. FY2011 Second Quarter Overall Contract and Project Management Improvement...

  13. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    by FY12. 95% Line Item 85% Cleanup 100% Line Item 88% Cleanup EVM represents Earned Value Management. FY2011 Fourth Quarter Overall Contract and Project Management Improvement...

  14. Contract/Project Management

    Energy Savers [EERE]

    by FY12. 95% Line Item 85% Cleanup 100% Line Item 88% Cleanup EVM represents Earned Value Management. FY2011 First Quarter Overall Contract and Project Management Performance...

  15. Contract/Project Management

    Energy Savers [EERE]

    by FY12. 95% Line Item 85% Cleanup 97% Line Item 89% Cleanup EVM represents Earned Value Management. FY2011 Third Quarter Overall Contract and Project Management Improvement...

  16. Recovery Act Project Stories

    Broader source: Energy.gov [DOE]

    Funded by the American Recovery and Reinvestment Act, these Federal Energy Management Program (FEMP) projects exemplify the range of technical assistance provided to federal agencies.

  17. Project Finance Case Studies

    Broader source: Energy.gov [DOE]

    Presentation covers the Project Finance Case Studies and is given at the Spring 2010 Federal Utility Partnership Working Group (FUPWG) meeting in Rapid City, South Dakota.

  18. TThe {\\sc Majorana} Project

    E-Print Network [OSTI]

    The MAJORANA collaboration

    2009-10-23T23:59:59.000Z

    The {\\sc Majorana} Project, a neutrinoless double-beta decay experiment is described with an emphasis on the choice of Ge-detector configuration.

  19. The MAJORANA project

    SciTech Connect (OSTI)

    Elliott, Steven R [Los Alamos National Laboratory

    2009-01-01T23:59:59.000Z

    The Majorana Project, a neutrinoless double-beta decay experiment is described with an emphasis on the choice of Ge-detector configuration.

  20. Energy Markets and Projections

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    National Governors Association Governors' Advisors Energy Policy Institute July 24, 2014 | Washington, DC By Adam Sieminski, EIA Administrator Energy Markets and Projections NGA...

  1. Our Project Regional, community,

    E-Print Network [OSTI]

    Minnesota, University of

    City departments -City Engineering and Traffic Engineering Public engagement early in project process modes and all users See.Safe.Smart.Rochester campaign to decrease modal conflict Connection

  2. Barstow Wind Turbine Project

    Broader source: Energy.gov [DOE]

    Presentation covers the Barstow Wind Turbine project for the Federal Utility Partnership Working Group (FUPWG) meeting, held on November 18-19, 2009.

  3. Prison Solar Project

    Broader source: Energy.gov [DOE]

    Presentation covers the Prison Solar Project for the Federal Utility Partnership Working Group (FUPWG) meeting, held on November 18-19, 2009.

  4. Developing Renewable Energy Projects Larger Than 10 MWs at Federal Facilities (Book)

    SciTech Connect (OSTI)

    Not Available

    2013-03-01T23:59:59.000Z

    To accomplish Federal goals for renewable energy, sustainability, and energy security, large-scale renewable energy projects must be developed and constructed on Federal sites at a significant scale with significant private investment. The U.S. Department of Energy's Federal Energy Management Program (FEMP) helps Federal agencies meet these goals and assists agency personnel navigate the complexities of developing such projects and attract the necessary private capital to complete them. This guide is intended to provide a general resource that will begin to develop the Federal employee's awareness and understanding of the project developer's operating environment and the private sector's awareness and understanding of the Federal environment. Because the vast majority of the investment that is required to meet the goals for large-scale renewable energy projects will come from the private sector, this guide has been organized to match Federal processes with typical phases of commercial project development. The main purpose of this guide is to provide a project development framework to allow the Federal Government, private developers, and investors to work in a coordinated fashion on large-scale renewable energy projects. The framework includes key elements that describe a successful, financially attractive large-scale renewable energy project.

  5. River Protection Project (RPP) Project Management Plan

    SciTech Connect (OSTI)

    NAVARRO, J.E.

    2001-03-07T23:59:59.000Z

    The Office of River Protection (ORP) Project Management Plan (PMP) for the River Protection Project (RPP) describes the process for developing and operating a Waste Treatment Complex (WTC) to clean up Hanford Site tank waste. The Plan describes the scope of the project, the institutional setting within which the project must be completed, and the management processes and structure planned for implementation. The Plan is written from the perspective of the ORP as the taxpayers' representative. The Hanford Site, in southeastern Washington State, has one of the largest concentrations of radioactive waste in the world, as a result of producing plutonium for national defense for more than 40 years. Approximately 53 million gallons of waste stored in 177 aging underground tanks represent major environmental, social, and political challenges for the U.S. Department of Energy (DOE). These challenges require numerous interfaces with state and federal environmental officials, Tribal Nations, stakeholders, Congress, and the US Department of Energy-Headquarters (DOE-HQ). The cleanup of the Site's tank waste is a national issue with the potential for environmental and economic impacts to the region and the nation.

  6. The Home Microbiome Project

    ScienceCinema (OSTI)

    Gilbert, Jack

    2014-09-15T23:59:59.000Z

    The Home Microbiome Project is an initiative aimed at uncovering the dynamic co-associations between people's bacteria and the bacteria found in their homes.The hope is that the data and project will show that routine monitoring of the microbial diversity of your body and of the environment in which you live is possible.

  7. Bacteria TMDL Projects

    E-Print Network [OSTI]

    Wythe, Kathy

    2007-01-01T23:59:59.000Z

    of TMDL projects for water bodies where swimming or wading may be unsafe or harvesting of oysters is limited or prohibited due to high concentrations of bacteria. ? Atascosa River: A TMDL Project for Bacteria ? Buffalo andWhite Oak Bayous: A TMDL...

  8. CA la electricidad de caracas: Arrecifes repowering project. Feasibility study report. Export trade information

    SciTech Connect (OSTI)

    NONE

    1993-10-01T23:59:59.000Z

    The study, conducted by Raytheon Engineers & Constructors, was funded by the U.S. Trade and Development agency on behalf of C.A. La Electricidad de Caracas. The report shows the results of a feasibility study conducted to evaluate the repowering of the Arrecifes Power Plant. The study focuses on capital cost for the project, refurbishment of existing equipment, and the installation of new repowering equipment. The study also evaluates combustion turbine generators of different manufacturers and sizes to determine the most beneficial configuration. The report is divided into the following sections: (1) Introduction; (2) Conclusions and Recommendations; (3) Study Basis; (4) Alternatives Analysis; (5) Layout and Equipment Issues; (6) Performance and Economic Analysis; (7) Repowered Facility Description; (8) Mechanical Systems; (9) Civil/Structural/Architectural; (10) Electrical Systems; (11) Instrumentation and Controls; (12) Environmental Overview; (13) Project Implementation Plan; (14) Project Conceptual Cost Estimate.

  9. North American LNG Project Sourcebook

    SciTech Connect (OSTI)

    NONE

    2007-06-15T23:59:59.000Z

    The report provides a status of the development of LNG Import Terminal projects in North America, and includes 1-2 page profiles of 63 LNG projects in North America which are either in operation, under construction, or under development. For each project, the sourcebook provides information on the following elements: project description, project ownership, project status, projected operation date, storage capacity, sendout capacity, and pipeline interconnection.

  10. Construction and startup experience for Milliken FGD Retrofit Project

    SciTech Connect (OSTI)

    Harvilla, J.; Mahlmeister, M. [New York State Electric and Gas Corp., Binghamton, NY (United States); Buchanan, T.; Jackson, C. [Parsons Power Group, Inc., Reading, PA (United States); Watts, J. [USDOE, Pittsburgh Energy Technology Center, PA (United States)

    1996-12-01T23:59:59.000Z

    Under Round 4 of the U.S. Department of Energy`s Clean Coal Technology program, New York State Electric & Gas Corp. (NYSEG), in partnership with Saarbereg-Stebbins Engineering and Manufacturing Company, has retrofitted a formic acid enhanced forced oxidation wet limestone scrubber on Units 1 & 2 at the Milliken Steam Electric Station. Units 1 & 2 are 1950`s vintage Combustion Engineering tangentially fired pulverized coal units which are rated at nominal 150 MW each and operate in balanced draft mode. The FGD system for Unit 2 was placed into operation in January 1995 and the Unit 1 system in June, 1995. The project incorporates several unique aspects including low pH operation, a ceramic tile-lined cocurrent/countercurrent, split module absorber, a wet stack supported on the roof of the FGD building, and closed loop, zero liquid discharge operation producing commercial grade gypsum, and calcium chloride brine. The project objectives include 98% SO{sub 2} removal efficiency while burning high sulfur coal, the production of marketable byproducts to minimize solid waste disposal, zero wastewater discharge and space-saving design. The paper provides a brief overview of the project design, discusses construction and startup issues and presents early operating results. Process capital cost and economics of this design, procure and construct approach are reviewed relative to competing technologies.

  11. NAVAJO ELECTRIFICATION DEMONSTRATION PROJECT

    SciTech Connect (OSTI)

    Terry W. Battiest

    2008-06-11T23:59:59.000Z

    The Navajo Electrification Demonstration Project (NEDP) is a multi-year project which addresses the electricity needs of the unserved and underserved Navajo Nation, the largest American Indian tribe in the United States. The program serves to cumulatively provide off-grid electricty for families living away from the electricty infrastructure, line extensions for unserved families living nearby (less than 1/2 mile away from) the electricity, and, under the current project called NEDP-4, the construction of a substation to increase the capacity and improve the quality of service into the central core region of the Navajo Nation.

  12. LIMB demonstration project extension

    SciTech Connect (OSTI)

    Not Available

    1990-09-21T23:59:59.000Z

    The purpose of the DOE limestone injection multistage burner (LIMB) Demonstration Project Extension is to extend the data base on LIMB technology and to expand DOE's list of Clean Coal Technologies by demonstrating the Coolside process as part of the project. The main objectives of this project are: to demonstrate the general applicability of LIMB technology by testing 3 coals and 4 sorbents (total of 12 coal/sorbent combinations) at the Ohio Edison Edgewater plant; and to demonstrate that Coolside is a viable technology for improving precipitator performance and reducing sulfur dioxide emissions while acceptable operability is maintained. Progress is reported. 3 figs.

  13. NEPA COMPLIANCE SURVEY Project Information Project Title: Casing...

    Broader source: Energy.gov (indexed) [DOE]

    Casing Drilling Test Date: 5-17-201 1 DOE Code: 6730-020-72000 Contractor Code: 8067-806 Project Lead: Marl< Duletsky Project Overview 1, Brief project description nclude The...

  14. Kellogg and Russ Forest projects. 2002 Project sand highlights

    E-Print Network [OSTI]

    Kellogg and Russ Forest projects. 2002 Project sand highlights MacCready Reserve a new property of insects Galeerucella calmariensis,and G.pusilla to control purple loosestrife on May 13. #12;New Project

  15. NEPA COMPLIANCE SURVEY Project Information Project Title: South...

    Broader source: Energy.gov (indexed) [DOE]

    Facility 2 Da te: 1-6-10 DOE Code: 6730.020.0000 Contracto r Code: 8067-788 Project Lead: Anthony Bowler Project Ove rview The purpose of the project is to build an additional...

  16. Funding Solar Projects at Federal Agencies: Mechanisms and Selection Criteria (Brochure)

    SciTech Connect (OSTI)

    Not Available

    2012-03-01T23:59:59.000Z

    Implementing solar energy projects at federal facilities is a process. The project planning phase of the process includes determining goals, building a team, determining site feasibility and selecting the appropriate project funding tool. This fact sheet gives practical guidance to assist decision-makers with understanding and selecting the funding tool that would best address their site goals. Because project funding tools are complex, federal agencies should seek project assistance before making final decisions. High capital requirements combined with limits on federal agency energy contracts create challenges for funding solar projects. Solar developers typically require long-term contracts (15-20) years to spread out the initial investment and to enable payments similar to conventional utility bill payments. In the private sector, 20-year contracts have been developed, vetted, and accepted, but the General Services Administration (GSA) contract authority (federal acquisition regulation [FAR] part 41) typically limits contract terms to 10 years. Payments on shorter-term contracts make solar economically unattractive compared with conventional generation. However, in several instances, the federal sector has utilized innovative funding tools that allow long-term contracts or has created a project package that is economically attractive within a shorter contract term.

  17. Applying EVM principles to Tevatron Beam Position Monitor Project

    SciTech Connect (OSTI)

    Banerjee, Bakul; /Fermilab

    2005-08-01T23:59:59.000Z

    At Fermi National Accelerator Laboratory (Fermilab), the Tevatron high energy particle collider must meet the increasing scientific demand of higher beam luminosity. To achieve this higher luminosity goal, U. S. Department of Energy (DOE) sponsored a major upgrade of capabilities of Fermilab's accelerator complex that spans five years and costs over fifty million dollars. Tevatron Beam Position Monitor (BPM) system upgrade is a part of this project, generally called RunII upgrade project. Since the purpose of the Tevatron collider is to detect the smashing of proton and anti-protons orbiting the circular accelerator in opposite directions, capability to detect positions of both protons and antiprotons at a high resolution level is a desirable functionality of the monitoring system. The original system was installed during early 1980s, along with the original construction of the Tevatron. However, electronic technology available in 1980s did not allow for the detection of significantly smaller resolution of antiprotons. The objective of the upgrade project is to replace the existing BPM system with a new system utilizing capabilities of modern electronics enhanced by a front-end software driven by a real-time operating software. The new BPM system is designed to detect both protons and antiprotons with increased resolution of up to an order of magnitude. The new system is capable of maintaining a very high-level of data integrity and system reliability. The system consists of 27 VME crates installed at 27 service buildings around the Tevatron ring servicing 236 beam position monitors placed underground, inside the accelerator tunnel. Each crate consists of a single Timing Generator Fanout module, custom made by Fermilab staff, one MVME processor card running VxWorks 5.5, multiple Echotek Digital Receiver boards complimented by custom made Filter Board. The VxWorks based front-end software communicates with the Main Accelerator Control software via a special-purpose network called ACNET. New software algorithms are designed to decouple antiproton signals from the mixed proton and antiproton signals. Along with many technical challenges, it was necessary to meet various project management challenges as well. Since 1999, U.S. Department of Energy (DOE) has taken various measures to improve project management of the acquisition of capital assets. U.S. National Laboratories, with their charter of driving scientific efforts of DOE, have put into place project management methodologies recommended by DOE. One of the outcomes of such measures is the deployment of a formal project management system for large projects. This recommendation is detailed in the DOE order M 413.3. The Tevatron BPM Upgrade project, as a part of the Run II Upgrade project, used the methodology prescribed in the DOE order. Particular attention was concentrated on the performance management since the accelerator complex will be in operation for several years in the future. Because of the cost and schedule constraints on the project, it was also important to deploy Earned Value Management (EVM) methodology recommended by the DOE orders. In this paper, we discuss how the earned value project management methodology was implemented using a work breakdown structure based on system life cycle phases. Tevatron BPM upgrade project, now nearing completion, has been a significant learning experience for the organization. We discuss important lessons learned from the phase-dependant earned value management project model. Hardware and software co-design along with simultaneously developed high-precision algorithm was a major challenge. Since formal project management process is not fully ingrained into the cultural environment of the laboratory dedicated to high-energy physics research, we also gained significant experience with the planning for schedule and cost in this environment. We also present a set of earned value project management data that may serve as a baseline for future projects.

  18. Flash Steam Recovery Project 

    E-Print Network [OSTI]

    Bronhold, C. J.

    2000-01-01T23:59:59.000Z

    /condensate recovery system, resulting in condensate flash steam losses to the atmosphere. Using computer simulation models and pinch analysis techniques, the Operational Excellence Group (Six Sigma) was able to identify a project to recover the flash steam losses as a...

  19. RM Power Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    rate-setting functions were integrated in 1990. The projects serve Colorado, Kansas, Nebraska and Wyoming with 830 MW of installed capacity and 3,360 miles of transmission line....

  20. Navajo Electrification Demonstraiton Project

    SciTech Connect (OSTI)

    Larry Ahasteen, Project Manager

    2006-07-17T23:59:59.000Z

    This is a final technical report required by DOE for the Navajo Electrification Demonstration Program, This report covers the electric line extension project for Navajo families that currently without electric power.