Sample records for updated cost estimates

  1. Updating MIT's cost estimation model for shipbuilding

    E-Print Network [OSTI]

    Smith, Matthew B., Lieutenant, junior grade

    2008-01-01T23:59:59.000Z

    This thesis project will update the MIT ship cost estimation model by combining the two existing models (the Basic Military Training School (BMTS) Cost Model and the MIT Math Model) in order to develop a program that can ...

  2. Updated Capital Cost Estimates for Utility Scale Electricity

    E-Print Network [OSTI]

    Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants April 2013 Information Administration | Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants ii for Utility Scale Electricity Generating Plants ii Contents Introduction

  3. Updated cost estimates of meeting geothermal hydrogen sulfide emission regulations

    SciTech Connect (OSTI)

    Wells, K.D.; Currie, J.W.; Weakley, S.A.; Ballinger, M.Y.

    1981-08-01T23:59:59.000Z

    A means of estimating the cost of hydrogen sulfide (H/sub 2/S) emission control was investigated. This study was designed to derive H/sub 2/S emission abatement cost functions and illustrate the cost of H/sub 2/S emission abatement at a hydrothermal site. Four tasks were undertaken: document the release of H/sub 2/S associated with geothermal development; review H/sub 2/S environmental standards; develop functional relationships that may be used to estimate the most cose-effective available H/sub 2/S abatement process; and use the cost functions to generate abatement cost estimates for a specific site. The conclusions and recommendations derived from the research are presented. The definition of the term impacts as used in this research is discussed and current estimates of the highest expected H/sub 2/S concentrations of in geothermal reservoirs are provided. Regulations governing H/sub 2/S emissions are reviewed and a review of H/sub 2/S control technology and a summary of the control cost functions are included. A case study is presented to illustrate H/sub 2/S abatement costs at the Baca KGRA in New Mexico.

  4. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for Automotive Applications: 2008 Update

    Fuel Cell Technologies Publication and Product Library (EERE)

    This report estimates fuel cell system cost for systems produced in the years 2006, 2010, and 2015, and is the second annual update of a comprehensive automotive fuel cell cost analysis.

  5. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for Automotive Applications: 2009 Update

    Fuel Cell Technologies Publication and Product Library (EERE)

    This report is the third annual update of a comprehensive automotive fuel cell cost analysis. It contains estimates for material and manufacturing cost of complete 80 kWnet direct hydrogen proton exch

  6. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for Automotive Applications: 2007 Update

    Fuel Cell Technologies Publication and Product Library (EERE)

    This report estimates fuel cell system cost for systems produced in the years 2007, 2010, and 2015, and is the first annual update of a comprehensive automotive fuel cell cost analysis.

  7. Mass Production Cost Estimation For Direct H2 PEM Fuel Cell Systesm for Automotive Applications: 2010 Update

    Fuel Cell Technologies Publication and Product Library (EERE)

    This report is the fourth annual update of a comprehensive automotive fuel cell cost analysis. It contains estimates for material and manufacturing costs of complete 80 kWnet direct?hydrogen proton ex

  8. Operating Costs Estimates Cost Indices

    E-Print Network [OSTI]

    Boisvert, Jeff

    to update costs of specific equipment, raw material or labor or CAPEX and OPEX of entire plants Cost Indices

  9. Falcon 9 Launch Vehicle NAFCOM Cost Estimates

    E-Print Network [OSTI]

    . ­ The updated estimates provided both Cost Plus Fee and Firm Fixed Price approaches and included two flight Updated Estimate Cost Plus Fee Cost Plus Fee Firm Fixed Price Cost Plus Fee Total Total Total Total in structure Interstage (composite material) was included in structures (aluminum lithium material) Interstage

  10. Estimating Specialty Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    Specialty costs are those nonstandard, unusual costs that are not typically estimated. Costs for research and development (R&D) projects involving new technologies, costs associated with future regulations, and specialty equipment costs are examples of specialty costs. This chapter discusses those factors that are significant contributors to project specialty costs and methods of estimating costs for specialty projects.

  11. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Applications: 2007 Update Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for Automotive Applications: 2007 Update This report estimates fuel cell system cost...

  12. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems...

    Broader source: Energy.gov (indexed) [DOE]

    07 Update Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for Automotive Applications: 2007 Update This report estimates fuel cell system cost for systems...

  13. Cost Estimation Package

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    This chapter focuses on the components (or elements) of the cost estimation package and their documentation.

  14. Systems Engineering Cost Estimation

    E-Print Network [OSTI]

    Bryson, Joanna J.

    on project, human capital impact. 7 How to estimate Cost? Difficult to know what we are building early on1 Systems Engineering Lecture 3 Cost Estimation Dr. Joanna Bryson Dr. Leon Watts University of Bath: Contrast approaches for estimating software project cost, and identify the main sources of cost

  15. Cost of Oil Dependence: A 2000 Update

    SciTech Connect (OSTI)

    Greene, D.L.; Tishchishyna, N.I.

    2000-05-01T23:59:59.000Z

    Oil dependence remains a potentially serious economic and strategic problem for the United States. This report updates previous estimates of the costs of oil dependence to the U.S. economy and introduces several methodological enhancements. Estimates of the costs to the U.S. economy of the oil market upheavals of the last 30 years are in the vicinity of $7 trillion, present value 1998 dollars, about as large as the sum total of payments on the national debt over the same period. Simply adding up historical costs in 1998 dollars without converting to present value results in a Base Case cost estimate of $3.4 trillion. Sensitivity analysis indicates that cost estimates are sensitive to key parameters. A lower bound estimate of $1.7 trillion and an upper bound of $7.1 trillion (not present value) indicate that the costs of oil dependence have been large under almost any plausible set of assumptions. These cost estimates do not include military, strategic or political costs associated with U.S. and world dependence on oil imports.

  16. Costs of Oil Dependence: A 2000 Update

    SciTech Connect (OSTI)

    Greene, D.L.

    2000-05-17T23:59:59.000Z

    Oil dependence remains a potentially serious economic and strategic problem for the United States. This report updates previous estimates of the costs of oil dependence to the U.S. economy and introduces several methodological enhancements. Estimates of the costs to the U.S. economy of the oil market upheavals of the last 30 years are in the vicinity of $7 trillion, present value 1998 dollars, about as large as the sum total of payments on the national debt over the same period. Simply adding up historical costs in 1998 dollars without converting to present value results in a Base Case cost estimate of $3.4 trillion. Sensitivity analysis indicates that cost estimates are sensitive to key parameters. A lower bound estimate of $1.7 trillion and an upper bound of $7.1 trillion (not present value) indicate that the costs of oil dependence have been large under almost any plausible set of assumptions. These cost estimates do not include military, strategic or political costs associated with U.S. and world dependence on oil imports.

  17. Updated Cost Analysis of Photobiological Hydrogen Production...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Analysis of Photobiological Hydrogen Production from Chlamydomonas reinhardtii Green Algae: Milestone Completion Report Updated Cost Analysis of Photobiological Hydrogen...

  18. Types of Costs Types of Cost Estimates

    E-Print Network [OSTI]

    Boisvert, Jeff

    · Types of Costs · Types of Cost Estimates · Methods to estimate capital costs MIN E 408: Mining% accuracy. ­ 2-5% of pre-production capital Types of Cost Estimates #12;3. Definitive ­ Based on definitive-even $ Production Level Fixed Cost Break-even $ Production Level Cost-Revenue Relationships · Capital Costs (or

  19. Types of Costs Types of Cost Estimates

    E-Print Network [OSTI]

    Boisvert, Jeff

    05-1 · Types of Costs · Types of Cost Estimates · Methods to estimate capital costs MIN E 408-Revenue Relationships · Capital Costs (or first cost or capital investment): ­ Expenditures made to acquire or develop capital assets ­ Three main classes of capital costs: 1. Depreciable Investment: · Investment allocated

  20. Mass Production Cost Estimation of Direct Hydrogen PEM Fuel Cell...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Hydrogen PEM Fuel Cell Systems for Transportation Applications: 2012 Update Mass Production Cost Estimation of Direct Hydrogen PEM Fuel Cell Systems for Transportation...

  1. Mass Production Cost Estimation of Direct Hydrogen PEM Fuel Cell...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mass Production Cost Estimation of Direct H 2 PEM Fuel Cell Systems for Transportation Applications: 2012 Update October 18, 2012 Prepared By: Brian D. James Andrew B. Spisak...

  2. Check Estimates and Independent Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    Check estimates and independent cost estimates (ICEs) are tools that can be used to validate a cost estimate. Estimate validation entails an objective review of the estimate to ensure that estimate criteria and requirements have been met and well documented, defensible estimate has been developed. This chapter describes check estimates and their procedures and various types of independent cost estimates.

  3. Cost Estimating Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2011-05-09T23:59:59.000Z

    This Guide provides uniform guidance and best practices that describe the methods and procedures that could be used in all programs and projects at DOE for preparing cost estimates. No cancellations.

  4. Cost Model and Cost Estimating Software

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    This chapter discusses a formalized methodology is basically a cost model, which forms the basis for estimating software.

  5. Estimated Costs for Production, Storage and Transportation of Switchgrass

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs for Production, Storage and Transportation of Switchgrass File A1-22 February 2008 updates earlier production cost estimates for switchgrass. The earlier estimations were com- pleted University (ISU) Extension publication Costs of Producing Switchgrass for Biomass in South- ern Iowa, PM 1866

  6. MONITORED GEOLOGIC REPOSITORY LIFE CYCLE COST ESTIMATE ASSUMPTIONS DOCUMENT

    SciTech Connect (OSTI)

    R.E. Sweeney

    2001-02-08T23:59:59.000Z

    The purpose of this assumptions document is to provide general scope, strategy, technical basis, schedule and cost assumptions for the Monitored Geologic Repository (MGR) life cycle cost (LCC) estimate and schedule update incorporating information from the Viability Assessment (VA) , License Application Design Selection (LADS), 1999 Update to the Total System Life Cycle Cost (TSLCC) estimate and from other related and updated information. This document is intended to generally follow the assumptions outlined in the previous MGR cost estimates and as further prescribed by DOE guidance.

  7. Update on the Cost of Nuclear Power

    E-Print Network [OSTI]

    Parsons, John E.

    2009-01-01T23:59:59.000Z

    We update the cost of nuclear power as calculated in the MIT (2003) Future of Nuclear Power study. Our main focus is on the changing cost of construction of new plants. The MIT (2003) study provided useful data on the cost ...

  8. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Applications: 2010 Update Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for Automotive Applications: 2010 Update This report is the fourth annual update of a...

  9. Cost Estimating, Analysis, and Standardization

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1984-11-02T23:59:59.000Z

    To establish policy and responsibilities for: (a) developing and reviewing project cost estimates; (b) preparing independent cost estimates and analysis; (c) standardizing cost estimating procedures; and (d) improving overall cost estimating and analytical techniques, cost data bases, cost and economic escalation models, and cost estimating systems. Cancels DOE O 5700.2B, dated 8-5-1983; DOE O 5700.8, dated 5-27-1981; and HQ 1130.1A, dated 12-30-1981. Canceled by DOE O 5700.2D, dated 6-12-1992

  10. Use of Cost Estimating Relationships

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    Cost Estimating Relationships (CERs) are an important tool in an estimator's kit, and in many cases, they are the only tool. Thus, it is important to understand their limitations and characteristics. This chapter discusses considerations of which the estimator must be aware so the Cost Estimating Relationships can be properly used.

  11. Life Cycle Cost Estimate

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    Life-cycle costs (LCCs) are all the anticipated costs associated with a project or program alternative throughout its life. This includes costs from pre-operations through operations or to the end of the alternative.This chapter discusses life cycle costs and the role they play in planning.

  12. Updating Texas Energy Cost Containment Audit Reports

    E-Print Network [OSTI]

    Burke, T. E.; Heffington, W. M.

    1989-01-01T23:59:59.000Z

    moneys in a program known as LoanSTAR. Due to the time between the audits and availability of funds, update of the reports for current energy and equipment cost, and for accomplishment of projects was necessary. Audits in 1984 and 1986 identified total...

  13. Types of Cost Estimates

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    The chapter describes the estimates required on government-managed projects for both general construction and environmental management.

  14. 2006 Update of Business Downtime Costs

    SciTech Connect (OSTI)

    Hinrichs, Mr. Doug [Sentech, Inc.; Goggin, Mr. Michael [Sentech, Inc.

    2007-01-01T23:59:59.000Z

    The objective of this paper is to assess the downtime cost of power outages to businesses in the commercial and industrial sectors, updating and improving upon studies that have already been published on this subject. The goal is to produce a study that, relative to existing studies, (1) applies to a wider set of business types (2) reflects more current downtime costs, (3) accounts for the time duration factor of power outages, and (4) includes data on the costs imposed by real outages in a well-defined market. This study examines power outage costs in 11 commercial subsectors and 5 industrial subsectors, using data on downtime costs that was collected in the 1990's. This study also assesses power outage costs for power outages of 20 minutes, 1 hour, and 4 hours duration. Finally, this study incorporates data on the costs of real power outages for two business subsectors. However, the current limited state of data availability on the topic of downtime costs means there is room to improve upon this study. Useful next steps would be to generate more recent data on downtime costs, data that covers outages shorter than 20 minutes duration and longer than 4 hours duration, and more data that is based on the costs caused by real-world outages. Nevertheless, with the limited data that is currently available, this study is able to generate a clear and detailed picture of the downtime costs that are faced by different types of businesses.

  15. Estimating Renewable Energy Costs

    Broader source: Energy.gov [DOE]

    Some renewable energy measures, such as daylighting, passive solar heating, and cooling load avoidance, do not add much to the cost of a building. However, renewable energy technologies typically...

  16. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for Automotive Applications: 2008 Update Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for...

  17. Mass Production Cost Estimation of Direct H2 PEM Fuel Cell Systems...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mass Production Cost Estimation of Direct H2 PEM Fuel Cell Systems for Transportation Applications: 2013 Update Mass Production Cost Estimation of Direct H2 PEM Fuel Cell Systems...

  18. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mass Production Cost Estimation for Direct H 2 PEM Fuel Cell Systems for Automotive Applications: 2007 Update February 29, 2008 Final Version Brian D. James Jeffrey A. Kalinoski...

  19. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mass Production Cost Estimation for Direct H 2 PEM Fuel Cell Systems for Automotive Applications: 2010 Update September 30, 2010 Prepared by: Brian D. James, Jeffrey A. Kalinoski...

  20. mMass Production Cost Estimation for Direct H2 PEM Fuel Cell...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mass Production Cost Estimation for Direct H 2 PEM Fuel Cell Systems for Automotive Applications: 2009 Update January 1, 2010 Prepared by: Brian D. James, Jeffrey A. Kalinoski &...

  1. AN OVERVIEW OF TOOL FOR RESPONSE ACTION COST ESTIMATING (TRACE)

    SciTech Connect (OSTI)

    FERRIES SR; KLINK KL; OSTAPKOWICZ B

    2012-01-30T23:59:59.000Z

    Tools and techniques that provide improved performance and reduced costs are important to government programs, particularly in current times. An opportunity for improvement was identified for preparation of cost estimates used to support the evaluation of response action alternatives. As a result, CH2M HILL Plateau Remediation Company has developed Tool for Response Action Cost Estimating (TRACE). TRACE is a multi-page Microsoft Excel{reg_sign} workbook developed to introduce efficiencies into the timely and consistent production of cost estimates for response action alternatives. This tool combines costs derived from extensive site-specific runs of commercially available remediation cost models with site-specific and estimator-researched and derived costs, providing the best estimating sources available. TRACE also provides for common quantity and key parameter links across multiple alternatives, maximizing ease of updating estimates and performing sensitivity analyses, and ensuring consistency.

  2. Examples of Cost Estimation Packages

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    Estimates can be performed in a variety of ways. Some of these are for projects for an undefined scope, a conventional construction project, or where there is a level of effort required to complete the work. Examples of cost estimation packages for these types of projects are described in this appendix.

  3. Hydrogen Production Cost Estimate Using Biomass Gasification...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Cost Estimate Using Biomass Gasification: Independent Review Hydrogen Production Cost Estimate Using Biomass Gasification: Independent Review This independent review is the...

  4. Hydrogen Production Cost Estimate Using Biomass Gasification

    E-Print Network [OSTI]

    Hydrogen Production Cost Estimate Using Biomass Gasification National Renewable Energy Laboratory Panel, Hydrogen Production Cost Estimate Using Biomass Gasification To: Mr. Mark Ruth, NREL, DOE

  5. Update to the Fissile Materials Disposition program SST/SGT transportation estimation

    SciTech Connect (OSTI)

    John Didlake

    1999-11-15T23:59:59.000Z

    This report is an update to ``Fissile Materials Disposition Program SST/SGT Transportation Estimation,'' SAND98-8244, June 1998. The Department of Energy Office of Fissile Materials Disposition requested this update as a basis for providing the public with an updated estimation of the number of transportation loads, load miles, and costs associated with the preferred alternative in the Surplus Plutonium Disposition Final Environmental Impact Statement (EIS).

  6. Costs to Maryland utilities and ratepayers of an acid-rain control strategy: an update analysis

    SciTech Connect (OSTI)

    Kahal, M.I.

    1988-03-01T23:59:59.000Z

    In 1985, the Power Plant Research Program (PPRP) published a study that developed estimates of cost and electric-rate impacts for a hypothetical control scenario for each major electric utility operating in the State. This report updates that earlier study by incorporating new information. Important differences include revised financial/accounting assumptions, a decline in the cost premium for low-sulfur coal, increases in scrubber construction costs and changes in control strategies. Also, the update incorporates control of NOx emissions. The original study was limited to evaluating the costs of controlling sulfur-emissions only.

  7. Estimating Specialty Costs - DOE Directives, Delegations, and...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    project specialty costs and methods of estimating costs for specialty projects. g4301-1chp20.pdf -- PDF Document, 56 KB Writer: John Makepeace Subjects: Administration Management...

  8. Costs of U.S. Oil Dependence: 2005 Update

    SciTech Connect (OSTI)

    Greene, D.L.

    2005-03-08T23:59:59.000Z

    For thirty years, dependence on oil has been a significant problem for the United States. Oil dependence is not simply a matter of how much oil we import. It is a syndrome, a combination of the vulnerability of the U.S. economy to higher oil prices and oil price shocks and a concentration of world oil supplies in a small group of oil producing states that are willing and able to use their market power to influence world oil prices. Although there are vitally important political and military dimensions to the oil dependence problem, this report focuses on its direct economic costs. These costs are the transfer of wealth from the United States to oil producing countries, the loss of economic potential due to oil prices elevated above competitive market levels, and disruption costs caused by sudden and large oil price movements. Several enhancements have been made to methods used in past studies to estimate these costs, and estimates of key parameters have been updated based on the most recent literature. It is estimated that oil dependence has cost the U.S. economy $3.6 trillion (constant 2000 dollars) since 1970, with the bulk of the losses occurring between 1979 and 1986. However, if oil prices in 2005 average $35-$45/bbl, as recently predicted by the U.S. Energy Information Administration, oil dependence costs in 2005 will be in the range of $150-$250 billion. Costs are relatively evenly divided between the three components. A sensitivity analysis reflecting uncertainty about all the key parameters required to estimate oil dependence costs suggests that a reasonable range of uncertainty for the total costs of U.S. oil dependence over the past 30 years is $2-$6 trillion (constant 2000 dollars). Reckoned in terms of present value using a discount rate of 4.5%, the costs of U.S. oil dependence since 1970 are $8 trillion, with a reasonable range of uncertainty of $5 to $13 trillion.

  9. Supplemental report on cost estimates'

    SciTech Connect (OSTI)

    NONE

    1992-04-29T23:59:59.000Z

    The Office of Management and Budget (OMB) and the U.S. Army Corps of Engineers have completed an analysis of the Department of Energy's (DOE) Fiscal Year (FY) 1993 budget request for its Environmental Restoration and Waste Management (ERWM) program. The results were presented to an interagency review group (IAG) of senior-Administration officials for their consideration in the budget process. This analysis included evaluations of the underlying legal requirements and cost estimates on which the ERWM budget request was based. The major conclusions are contained in a separate report entitled, ''Interagency Review of the Department of Energy Environmental Restoration and Waste Management Program.'' This Corps supplemental report provides greater detail on the cost analysis.

  10. Cost Model and Cost Estimating Software - DOE Directives, Delegations...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    is basically a cost model, which forms the basis for estimating software. g4301-1chp22.pdf -- PDF Document, 190 KB Writer: John Makepeace Subjects: Administration...

  11. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    for Direct H2 PEM Fuel Cell Systems for Automotive Application: 2009 Update Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for Automotive Application: 2009...

  12. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Mass Production Cost Estimation for Direct H 2 PEM Fuel Cell Systems for Automotive Applications: 2008 Update March 26, 2009 v.30.2021.052209 Prepared by: Brian D. James & Jeffrey...

  13. Energy storage systems cost update : a study for the DOE Energy Storage Systems Program.

    SciTech Connect (OSTI)

    Schoenung, Susan M. (Longitude 122 West, Menlo Park, CA)

    2011-04-01T23:59:59.000Z

    This paper reports the methodology for calculating present worth of system and operating costs for a number of energy storage technologies for representative electric utility applications. The values are an update from earlier reports, categorized by application use parameters. This work presents an update of energy storage system costs assessed previously and separately by the U.S. Department of Energy (DOE) Energy Storage Systems Program. The primary objective of the series of studies has been to express electricity storage benefits and costs using consistent assumptions, so that helpful benefit/cost comparisons can be made. Costs of energy storage systems depend not only on the type of technology, but also on the planned operation and especially the hours of storage needed. Calculating the present worth of life-cycle costs makes it possible to compare benefit values estimated on the same basis.

  14. Harmonizing Systems and Software Cost Estimation

    E-Print Network [OSTI]

    Wang, Gan

    2009-07-19T23:59:59.000Z

    The objective of this paper is to examine the gaps and overlaps between software and systems engineering cost models with intent to harmonize the estimates in engineering engineering estimation. In particular, we evaluate ...

  15. Cost Estimating Handbook for Environmental Restoration

    SciTech Connect (OSTI)

    NONE

    1990-09-01T23:59:59.000Z

    Environmental restoration (ER) projects have presented the DOE and cost estimators with a number of properties that are not comparable to the normal estimating climate within DOE. These properties include: An entirely new set of specialized expressions and terminology. A higher than normal exposure to cost and schedule risk, as compared to most other DOE projects, due to changing regulations, public involvement, resource shortages, and scope of work. A higher than normal percentage of indirect costs to the total estimated cost due primarily to record keeping, special training, liability, and indemnification. More than one estimate for a project, particularly in the assessment phase, in order to provide input into the evaluation of alternatives for the cleanup action. While some aspects of existing guidance for cost estimators will be applicable to environmental restoration projects, some components of the present guidelines will have to be modified to reflect the unique elements of these projects. The purpose of this Handbook is to assist cost estimators in the preparation of environmental restoration estimates for Environmental Restoration and Waste Management (EM) projects undertaken by DOE. The DOE has, in recent years, seen a significant increase in the number, size, and frequency of environmental restoration projects that must be costed by the various DOE offices. The coming years will show the EM program to be the largest non-weapons program undertaken by DOE. These projects create new and unique estimating requirements since historical cost and estimating precedents are meager at best. It is anticipated that this Handbook will enhance the quality of cost data within DOE in several ways by providing: The basis for accurate, consistent, and traceable baselines. Sound methodologies, guidelines, and estimating formats. Sources of cost data/databases and estimating tools and techniques available at DOE cost professionals.

  16. 2009 Cost Estimates of Establishing and

    E-Print Network [OSTI]

    Collins, Gary S.

    2009 Cost Estimates of Establishing and Producing Gala Apples in Washington WASHINGTON STATE include estimating 1) the costs of the equipment, materials, supplies, and labor required to establish for any particular orchard operation due to case-specific: · Capital, labor, and natural resources · Crop

  17. 2013 Cost Estimation of Establishing a

    E-Print Network [OSTI]

    Collins, Gary S.

    1 2013 Cost Estimation of Establishing a Cider Apple Orchard in Western Washington W A S H I N G factors: · Capital, labor, and natural resources · Crop yield · Cultural practices · Input prices Cost estimations in this enterprise budget also vary depending on the budget's intended use. To avoid

  18. Mandatory Photovoltaic System Cost Estimate

    Broader source: Energy.gov [DOE]

    At the request of a customer or a potential customer, Colorado electric utilities are required to conduct a cost comparison of a photovoltaic (PV) system to any proposed distribution line extension...

  19. Mass Production Cost Estimation of Direct H2 PEM Fuel Cell Systems for

    E-Print Network [OSTI]

    1 Mass Production Cost Estimation of Direct H2 PEM Fuel Cell Systems for Transportation (2012), annually updated costs analyses will be conducted for PEM fuel cell passenger buses as well to eliminate the need for oil in the transportation sector. Fuel cell vehicles can operate on hydrogen, which

  20. Cost estimating projects for large cutter and hopper dredges

    E-Print Network [OSTI]

    Belesimo, Francesco John

    2000-01-01T23:59:59.000Z

    Estimating the cost of a dredging project is the most important part of a project's life cycle. A precise account of the costs associated with performing dredging work begins with the production estimate and ends with the cost estimate...

  1. Estimating Costs and Efficiency of Storage, Demand, and Heat...

    Energy Savers [EERE]

    Estimating Costs and Efficiency of Storage, Demand, and Heat Pump Water Heaters Estimating Costs and Efficiency of Storage, Demand, and Heat Pump Water Heaters March 10, 2015 -...

  2. Direct Hydrogen PEMFC Manufacturing Cost Estimation for Automotive...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Direct Hydrogen PEMFC Manufacturing Cost Estimation for Automotive Applications: Fuel Cell Tech Team Review Direct Hydrogen PEMFC Manufacturing Cost Estimation for Automotive...

  3. Hydrogen Supply: Cost Estimate for Hydrogen Pathways-Scoping...

    Broader source: Energy.gov (indexed) [DOE]

    Supply: Cost Estimate for Hydrogen Pathways-Scoping Analysis. January 22, 2002-July 22, 2002 Hydrogen Supply: Cost Estimate for Hydrogen Pathways-Scoping Analysis. January 22,...

  4. Updated Costs (June 2011 Basis) for Selected Bituminous Baseline...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Date:2011-Oct-17 Project: Bituminous Baseline Study Case: Case 1 GEE Radiant IGCC wo CO2 Plant Size: 622.1 MW,net Estimate Type: Conceptual Cost Base (Jun) 2011 (x1000) Acct...

  5. Research Summary Estimating Woodfuel Resource Cost Curves

    E-Print Network [OSTI]

    and extraction methods. Background Just under half of the final energy consumed in the UK (49%) is in the formResearch Summary Estimating Woodfuel Resource Cost Curves As a renewable energy source, woodfuel. The woodfuel strategy adopted by Forestry Commission England supports delivery of these. It aims to sustainably

  6. Categorical missing data imputation for software cost estimation by

    E-Print Network [OSTI]

    Bae, Doo-Hwan

    the cost usually begins by building estimation model Apply estimation method to historical data setsCategorical missing data imputation for software cost estimation by multinomial logistic regression Organization type Banking, Construction, Gas, Defense, Engergy, ... bartype Business area type Accounting

  7. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for

    E-Print Network [OSTI]

    Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for Automotive Applications: 2010 Update fuel cell vehicles have the potential to eliminate the need for oil in the transportation sector. Fuel, and biomass. Thus, fuel cell vehicles offer an environmentally clean and energysecure transportation pathway

  8. Development of a right-of-way cost estimation and cost estimate management process framework for highway projects

    E-Print Network [OSTI]

    Lucas, Matthew Allen

    2009-05-15T23:59:59.000Z

    .............................................................. 31 Results: ROW Estimation State of Practice ................................... 31 Critical Issues ....................................................................... 32 Overview of Current Practice... ............................................... 35 Analysis: Critical Review of Practices ........................................... 41 General ROW Cost Estimation Procedure ........................... 42 ROW Cost Estimation...

  9. Estimated Costs of Crop Production in Iowa 2001

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Crop Production in Iowa ­ 2001 The estimated costs of corn, corn silage. They include the annual Iowa Farm Business Association record summaries, production and costs data from and a survey of selected agriculture cooperatives around the state. These costs estimates are representative

  10. Estimated Costs of Crop Production in Iowa 2000

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Crop Production in Iowa ­ 2000 The estimated costs of corn, corn silage. They include the annual Iowa Farm Business Association record summaries, production and costs data from and a survey of selected agriculture cooperatives around the state. These costs estimates are representative

  11. INDEPENDENT COST REVIEW (ICR) and INDEPENDENT COST ESTIMATE ...

    Broader source: Energy.gov (indexed) [DOE]

    ICRICE SOPSep 2013Final.pdf More Documents & Publications ICR-ICE Standard Operating Procedures (Update Sept 2013) Contractor SOW Template - ICR Contractor SOW Template - ICE...

  12. Estimation of Highway Maintenance Marginal Cost under Multiple Maintenance Activities

    E-Print Network [OSTI]

    Anani, Shadi B.; Madanat, Samer M

    2010-01-01T23:59:59.000Z

    Marginal costs for road maintenance and operation - a cost2010-01) Estimation of Highway Maintenance Marginal Costunder Multiple Maintenance Activities Shadi B. Anani and

  13. Summary and Presentations from "Estimating the Benefits and Costs...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Summary and Presentations from "Estimating the Benefits and Costs of Distributed Energy Technologies" Workshop Now Available Summary and Presentations from "Estimating the Benefits...

  14. Estimating the Benefits and Costs of Distributed Energy Technologies...

    Broader source: Energy.gov (indexed) [DOE]

    - Carl Imhoff, PNNL More Documents & Publications Estimating the Benefits and Costs of Distributed Energy Technologies Workshop - Day 1 Presentations Estimating the...

  15. Check Estimates and Independent Costs - DOE Directives, Delegations...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    estimates and their procedures and various types of independent cost estimates. g4301-1chp13.pdf -- PDF Document, 33 KB Writer: John Makepeace Subjects: Administration Management...

  16. Types of Cost Estimates - DOE Directives, Delegations, and Requirement...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    CURRENT DOE G 430.1-1 Chp 4, Types of Cost Estimates by John Makepeace Functional areas: Procurement, Project Management The chapter describes the estimates required on...

  17. Cost and production estimation for a cutter suction dredge

    E-Print Network [OSTI]

    Miertschin, Michael Wayne

    1997-01-01T23:59:59.000Z

    The need for accurate cost estimates is well recognized in the dredging industry. In order for a dredging contractor to efficiently execute a project from its conception to its completion, an accurate estimate of the final cost is imperative...

  18. Estimating the Economic Cost of Sea-Level Rise

    E-Print Network [OSTI]

    Sugiyama, Masahiro.

    To improve the estimate of economic costs of future sea-level rise associated with global climate change,

  19. Using Natural Gas Transmission Pipeline Costs to Estimate Hydrogen Pipeline Costs

    E-Print Network [OSTI]

    Parker, Nathan

    2004-01-01T23:59:59.000Z

    future estimates of hydrogen pipelines. Construction Cost (does this mean for hydrogen pipelines? The objective of thisinto the cost of hydrogen pipelines. To this end I will

  20. Estimated Costs of Crop Production in Iowa 2005

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Crop Production in Iowa ­ 2005 The estimated costs of corn, corn silage. They include the annual Iowa Farm Business Association record summaries, production and costs data from and a survey of selected agricultural cooperatives and other input suppliers around the state. These costs

  1. Estimated Costs of Crop Production in Iowa 2002

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Crop Production in Iowa ­ 2002 The estimated costs of corn, corn silage. They include the annual Iowa Farm Business Association record summaries, production and costs data from and a survey of selected agricultural cooperatives and other input suppliers around the state. These costs

  2. Estimated Costs of Crop Production in Iowa 2006

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Crop Production in Iowa ­ 2006 The estimated costs of corn, corn silage. They include the annual Iowa Farm Business Association record summaries, production and costs data from and a survey of selected agricultural cooperatives and other input suppliers around the state. These costs

  3. ICPP tank farm closure study. Volume 3: Cost estimates, planning schedules, yearly cost flowcharts, and life-cycle cost estimates

    SciTech Connect (OSTI)

    NONE

    1998-02-01T23:59:59.000Z

    This volume contains information on cost estimates, planning schedules, yearly cost flowcharts, and life-cycle costs for the six options described in Volume 1, Section 2: Option 1 -- Total removal clean closure; No subsequent use; Option 2 -- Risk-based clean closure; LLW fill; Option 3 -- Risk-based clean closure; CERCLA fill; Option 4 -- Close to RCRA landfill standards; LLW fill; Option 5 -- Close to RCRA landfill standards; CERCLA fill; and Option 6 -- Close to RCRA landfill standards; Clean fill. This volume is divided into two portions. The first portion contains the cost and planning schedule estimates while the second portion contains life-cycle costs and yearly cash flow information for each option.

  4. Cost Estimation for Cross-organizational ERP Projects: Research Perspectives

    E-Print Network [OSTI]

    Wieringa, Roel

    Cost Estimation for Cross-organizational ERP Projects: Research Perspectives Maya Daneva, Roel There are many methods for estimating size, effort, schedule and other cost aspects of IS projects, but only one domain of cross-organizational ERP cost estimation, to survey available solutions, and to propose

  5. IDC RP2 & 3 US Industry Standard Cost Estimate Summary.

    SciTech Connect (OSTI)

    Harris, James M.; Huelskamp, Robert M.

    2015-01-01T23:59:59.000Z

    Sandia National Laboratories has prepared a ROM cost estimate for budgetary planning for the IDC Reengineering Phase 2 & 3 effort, using a commercial software cost estimation tool calibrated to US industry performance parameters. This is not a cost estimate for Sandia to perform the project. This report provides the ROM cost estimate and describes the methodology, assumptions, and cost model details used to create the ROM cost estimate. ROM Cost Estimate Disclaimer Contained herein is a Rough Order of Magnitude (ROM) cost estimate that has been provided to enable initial planning for this proposed project. This ROM cost estimate is submitted to facilitate informal discussions in relation to this project and is NOT intended to commit Sandia National Laboratories (Sandia) or its resources. Furthermore, as a Federally Funded Research and Development Center (FFRDC), Sandia must be compliant with the Anti-Deficiency Act and operate on a full-cost recovery basis. Therefore, while Sandia, in conjunction with the Sponsor, will use best judgment to execute work and to address the highest risks and most important issues in order to effectively manage within cost constraints, this ROM estimate and any subsequent approved cost estimates are on a 'full-cost recovery' basis. Thus, work can neither commence nor continue unless adequate funding has been accepted and certified by DOE.

  6. Melanoma costs: A dynamic model comparing estimated overall costs of various clinical stages

    E-Print Network [OSTI]

    Alexandrescu, Doru Traian

    2009-01-01T23:59:59.000Z

    AL. Trends in treatment costs for localized prostate cancer:R, Elkin EP, et al. Cumulative cost pattern comparison ofAn estimate of the annual direct cost of treating cutaneous

  7. Estimation of cost synergies from mergers without cost data: Application to U.S. radio

    E-Print Network [OSTI]

    Niebur, Ernst

    Estimation of cost synergies from mergers without cost data: Application to U.S. radio Przemyslaw without using actual data on cost. The estimator uses a structural model in which companies play a dynamic for cost data. It turns out that between 1996 and 2006 additional ownership concentration generated $2.5b

  8. Interdisciplinary Institute for Innovation Estimating the costs of nuclear

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    Interdisciplinary Institute for Innovation Estimating the costs of nuclear power: benchmarks;1/36 Estimating the costs of nuclear power: benchmarks and uncertainties François Lévęque Introduction The debate and voters that they are being manipulated: each side is just defending its own interests and the true cost

  9. 5. ESTIMATING THE COSTS OF DIGITAL PRESERVATION 5.1 Isolating a `preservation cost'

    E-Print Network [OSTI]

    Carr, Leslie

    44 5. ESTIMATING THE COSTS OF DIGITAL PRESERVATION 5.1 Isolating a `preservation cost' Deciding preservation is--how much will it cost? One of the problems encountered in trying to answer this question costs do relate specifically to preservation, but this does not mean that those are the only costs

  10. ORNL/TM-2005/45 COSTS OF U.S. OIL DEPENDENCE: 2005 UPDATE

    E-Print Network [OSTI]

    ORNL/TM-2005/45 COSTS OF U.S. OIL DEPENDENCE: 2005 UPDATE David L. Greene Oak Ridge National. DEFINITION OF THE ECONOMIC COSTS OF OIL DEPENDENCE .....................7 3.1 DEFINITION OF OIL DEPENDENCE..................................................................7 3.2 TYPES AND MEASUREMENT OF OIL COSTS.................................................7 3

  11. Developing a Cost Model and Methodology to Estimate Capital Costs for Thermal Energy Storage

    SciTech Connect (OSTI)

    Glatzmaier, G.

    2011-12-01T23:59:59.000Z

    This report provides an update on the previous cost model for thermal energy storage (TES) systems. The update allows NREL to estimate the costs of such systems that are compatible with the higher operating temperatures associated with advanced power cycles. The goal of the Department of Energy (DOE) Solar Energy Technology Program is to develop solar technologies that can make a significant contribution to the United States domestic energy supply. The recent DOE SunShot Initiative sets a very aggressive cost goal to reach a Levelized Cost of Energy (LCOE) of 6 cents/kWh by 2020 with no incentives or credits for all solar-to-electricity technologies.1 As this goal is reached, the share of utility power generation that is provided by renewable energy sources is expected to increase dramatically. Because Concentrating Solar Power (CSP) is currently the only renewable technology that is capable of integrating cost-effective energy storage, it is positioned to play a key role in providing renewable, dispatchable power to utilities as the share of power generation from renewable sources increases. Because of this role, future CSP plants will likely have as much as 15 hours of Thermal Energy Storage (TES) included in their design and operation. As such, the cost and performance of the TES system is critical to meeting the SunShot goal for solar technologies. The cost of electricity from a CSP plant depends strongly on its overall efficiency, which is a product of two components - the collection and conversion efficiencies. The collection efficiency determines the portion of incident solar energy that is captured as high-temperature thermal energy. The conversion efficiency determines the portion of thermal energy that is converted to electricity. The operating temperature at which the overall efficiency reaches its maximum depends on many factors, including material properties of the CSP plant components. Increasing the operating temperature of the power generation system leads to higher thermal-to-electric conversion efficiency. However, in a CSP system, higher operating temperature also leads to greater thermal losses. These two effects combine to give an optimal system-level operating temperature that may be less than the upper operating temperature limit of system components. The overall efficiency may be improved by developing materials, power cycles, and system-integration strategies that enable operation at elevated temperature while limiting thermal losses. This is particularly true for the TES system and its components. Meeting the SunShot cost target will require cost and performance improvements in all systems and components within a CSP plant. Solar collector field hardware will need to decrease significantly in cost with no loss in performance and possibly with performance improvements. As higher temperatures are considered for the power block, new working fluids, heat-transfer fluids (HTFs), and storage fluids will all need to be identified to meet these new operating conditions. Figure 1 shows thermodynamic conversion efficiency as a function of temperature for the ideal Carnot cycle and 75% Carnot, which is considered to be the practical efficiency attainable by current power cycles. Current conversion efficiencies for the parabolic trough steam cycle, power tower steam cycle, parabolic dish/Stirling, Ericsson, and air-Brayton/steam Rankine combined cycles are shown at their corresponding operating temperatures. Efficiencies for supercritical steam and carbon dioxide (CO{sub 2}) are also shown for their operating temperature ranges.

  12. Estimating the Benefits and Costs of Distributed Energy Technologies...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    1 Presentations Estimating the Benefits and Costs of Distributed Energy Technologies Workshop - Day 1 Presentations On September 30 and October 1, 2014, the Department of Energy...

  13. Estimating the Benefits and Costs of Distributed Energy Technologies...

    Broader source: Energy.gov (indexed) [DOE]

    2014, the Department of Energy hosted a 2-day workshop on "Estimating the Benefits and Costs of Distributed Energy Technologies." The purpose of the workshop was to foster...

  14. Estimation and Analysis of Life Cycle Costs of Baseline Enhanced...

    Open Energy Info (EERE)

    Estimation and Analysis of Life Cycle Costs of Baseline Enhanced Geothermal Systems Geothermal Project Jump to: navigation, search Last modified on July 22, 2011. Project Title...

  15. Quality Guidline for Cost Estimation Methodology for NETL Assessments...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    20111455 National Energy Technology Laboratory Office of Program Performance and Benefits 2 Power Plant Cost Estimation Methodology Quality Guidelines for Energy System Studies...

  16. Brush Busters: How to Estimate Costs for Controlling Pricklypear

    E-Print Network [OSTI]

    Ueckert, Darrell; McGinty, Allan

    1999-04-15T23:59:59.000Z

    Simple directions help you determine the density of pricklypear on your land, and then estimate the cost of controlling these plants with the pad or stem spray method....

  17. Handbook for cost estimating. A method for developing estimates of costs for generic actions for nuclear power plants

    SciTech Connect (OSTI)

    Ball, J.R.; Cohen, S.; Ziegler, E.Z.

    1984-10-01T23:59:59.000Z

    This document provides overall guidance to assist the NRC in preparing the types of cost estimates required by the Regulatory Analysis Guidelines and to assist in the assignment of priorities in resolving generic safety issues. The Handbook presents an overall cost model that allows the cost analyst to develop a chronological series of activities needed to implement a specific regulatory requirement throughout all applicable commercial LWR power plants and to identify the significant cost elements for each activity. References to available cost data are provided along with rules of thumb and cost factors to assist in evaluating each cost element. A suitable code-of-accounts data base is presented to assist in organizing and aggregating costs. Rudimentary cost analysis methods are described to allow the analyst to produce a constant-dollar, lifetime cost for the requirement. A step-by-step example cost estimate is included to demonstrate the overall use of the Handbook.

  18. Estimating production and cost for clamshell mechanical dredges

    E-Print Network [OSTI]

    Adair, Robert Fletcher

    2005-02-17T23:59:59.000Z

    methodology for production and cost estimation for clamshell dredge projects. There are current methods of predicting clamshell dredge production which rely on production curves and constant cycle times. This thesis calculates production estimation...

  19. Comparative Analysis of the Cost Models Used for Estimating Renovation Costs of Universities in Texas

    E-Print Network [OSTI]

    Faquih, Yaquta Fakhruddin

    2010-10-12T23:59:59.000Z

    Facility managers use various cost models and techniques to estimate the cost of renovating a building and to secure the required funds needed for building renovation. A literature search indicates that these techniques offer both advantages...

  20. Cost estimate guidelines for advanced nuclear power technologies

    SciTech Connect (OSTI)

    Delene, J.G.; Hudson, C.R. II.

    1990-03-01T23:59:59.000Z

    To make comparative assessments of competing technologies, consistent ground rules must be applied when developing cost estimates. This document provides a uniform set of assumptions, ground rules, and requirements that can be used in developing cost estimates for advanced nuclear power technologies. 10 refs., 8 figs., 32 tabs.

  1. Brush Busters: How to Estimate Costs for Controlling Small Mesquite

    E-Print Network [OSTI]

    Ueckert, Darrell; McGinty, Allan

    1999-04-15T23:59:59.000Z

    , then calculate the average mesquite density for your pasture. Step 2. Use the graphs to estimate cost per acre. ? Find the appropriate figure in this brochure for the Brush Busters method you will use. (Figure 1 estimates costs for the leaf spray method...) on the left side of the chart. Make a mark on the cost axis. This point is an estimate of what your cost per acre should be in $/acre. Example: If you have an average of 100 small mesquite plants per acre, you?re using the Brush Busters leaf spray method...

  2. The unit cost factors and calculation methods for decommissioning - Cost estimation of nuclear research facilities

    SciTech Connect (OSTI)

    Kwan-Seong Jeong; Dong-Gyu Lee; Chong-Hun Jung; Kune-Woo Lee [Korea Atomic Energy Research Institute, Deokjin-dong 150, Yuseong-gu, Daejeon 305-353 (Korea, Republic of)

    2007-07-01T23:59:59.000Z

    Available in abstract form only. Full text of publication follows: The uncertainties of decommissioning costs increase high due to several conditions. Decommissioning cost estimation depends on the complexity of nuclear installations, its site-specific physical and radiological inventories. Therefore, the decommissioning costs of nuclear research facilities must be estimated in accordance with the detailed sub-tasks and resources by the tasks of decommissioning activities. By selecting the classified activities and resources, costs are calculated by the items and then the total costs of all decommissioning activities are reshuffled to match with its usage and objectives. And the decommissioning cost of nuclear research facilities is calculated by applying a unit cost factor method on which classification of decommissioning works fitted with the features and specifications of decommissioning objects and establishment of composition factors are based. Decommissioning costs of nuclear research facilities are composed of labor cost, equipment and materials cost. Of these three categorical costs, the calculation of labor costs are very important because decommissioning activities mainly depend on labor force. Labor costs in decommissioning activities are calculated on the basis of working time consumed in decommissioning objects and works. The working times are figured out of unit cost factors and work difficulty factors. Finally, labor costs are figured out by using these factors as parameters of calculation. The accuracy of decommissioning cost estimation results is much higher compared to the real decommissioning works. (authors)

  3. Title, Location, Document Number Estimated Cost Description

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn'tOriginEducationVideoStrategic|Industrial Sector,Department ThirdCostsComments

  4. Production, Cost, and Soil Compaction Estimates for Two Western Juniper

    E-Print Network [OSTI]

    Dodson, Beth

    , Crook County Soil and Water Conservation District, Prineville, OR 97754. ABSTRACT: Harvesting trialsProduction, Cost, and Soil Compaction Estimates for Two Western Juniper Extraction Systems, production rates, and soil compaction impacts of two systems for harvesting western juniper (Juniperus

  5. Cost Estimation Package - DOE Directives, Delegations, and Requirement...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    components (or elements) of the cost estimation package and their documentation. g4301-1chp2.pdf -- PDF Document, 10 KB Writer: John Makepeace Subjects: ID: DOE G 430.1-1 Chp 2...

  6. Use of Cost Estimating Relationships - DOE Directives, Delegations...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    must be aware so the Cost Estimating Relationships can be properly used. g4301-1chp18.pdf -- PDF Document, 41 KB Writer: John Makepeace Subjects: Administration Management...

  7. Web integrated cost estimation system in architecture education

    E-Print Network [OSTI]

    Darapureddy, K.S. Kiran

    2001-01-01T23:59:59.000Z

    these objectives a Web-based cost estimation system has been developed. This software has been developed using Active Server Pages (ASP), Microsoft Access database, Structured Query Language (SQL) and the Internet technology. In order to find students' inclination...

  8. Interruption Cost Estimate Calculator | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdfGetecGtelInterias Solar Energy Jump to:IES JumpUnion forInterruption Cost

  9. Estimating design costs for first-of-a-kind projects

    SciTech Connect (OSTI)

    Banerjee, Bakul; /Fermilab

    2006-03-01T23:59:59.000Z

    Modern scientific facilities are often outcomes of projects that are first-of-a-kind, that is, minimal historical data are available for project costs and schedules. However, at Fermilab, there was an opportunity to execute two similar projects consecutively. In this paper, a comparative study of the design costs for these two projects is presented using earned value methodology. This study provides some insights into how to estimate the cost of a replicated project.

  10. Updated Buildings Sector Appliance and Equipment Costs and Efficiency

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 111 1,613 122 40 Buildingto17 34 44Year Jan Feb MarDecadeFour-Dimensional2009 2010Updated

  11. Hydrogen Production Cost Estimate Using Biomass Gasification: Independent Review

    SciTech Connect (OSTI)

    Ruth, M.

    2011-10-01T23:59:59.000Z

    This independent review is the conclusion arrived at from data collection, document reviews, interviews and deliberation from December 2010 through April 2011 and the technical potential of Hydrogen Production Cost Estimate Using Biomass Gasification. The Panel reviewed the current H2A case (Version 2.12, Case 01D) for hydrogen production via biomass gasification and identified four principal components of hydrogen levelized cost: CapEx; feedstock costs; project financing structure; efficiency/hydrogen yield. The panel reexamined the assumptions around these components and arrived at new estimates and approaches that better reflect the current technology and business environments.

  12. DFMA Cost Estimates of Fuel-Cell/Reformer Systems

    E-Print Network [OSTI]

    Page 1 DFMA Cost Estimates of Fuel-Cell/Reformer Systems at Low/Medium/High Production Rates Brian estimates of complete fuel cell- reformer systems at low/medium/high manufacturing rates to assess of Boothroyd Dewhurst Inc. #12;Page 4 Scope of Project Reformer System Fuel Cell System Fuel Storage What

  13. Fuel Cell System for Transportation -- 2005 Cost Estimate

    SciTech Connect (OSTI)

    Wheeler, D.

    2006-10-01T23:59:59.000Z

    Independent review report of the methodology used by TIAX to estimate the cost of producing PEM fuel cells using 2005 cell stack technology. The U.S. Department of Energy (DOE) Hydrogen, Fuel Cells and Infrastructure Technologies Program Manager asked the National Renewable Energy Laboratory (NREL) to commission an independent review of the 2005 TIAX cost analysis for fuel cell production. The NREL Systems Integrator is responsible for conducting independent reviews of progress toward meeting the DOE Hydrogen Program (the Program) technical targets. An important technical target of the Program is the proton exchange membrane (PEM) fuel cell cost in terms of dollars per kilowatt ($/kW). The Program's Multi-Year Program Research, Development, and Demonstration Plan established $125/kW as the 2005 technical target. Over the last several years, the Program has contracted with TIAX, LLC (TIAX) to produce estimates of the high volume cost of PEM fuel cell production for transportation use. Since no manufacturer is yet producing PEM fuel cells in the quantities needed for an initial hydrogen-based transportation economy, these estimates are necessary for DOE to gauge progress toward meeting its targets. For a PEM fuel cell system configuration developed by Argonne National Laboratory, TIAX estimated the total cost to be $108/kW, based on assumptions of 500,000 units per year produced with 2005 cell stack technology, vertical integration of cell stack manufacturing, and balance-of-plant (BOP) components purchased from a supplier network. Furthermore, TIAX conducted a Monte Carlo analysis by varying ten key parameters over a wide range of values and estimated with 98% certainty that the mean PEM fuel cell system cost would be below DOE's 2005 target of $125/kW. NREL commissioned DJW TECHNOLOGY, LLC to form an Independent Review Team (the Team) of industry fuel cell experts and to evaluate the cost estimation process and the results reported by TIAX. The results of this independent review will permit NREL and DOE to better understand the credibility of the TIAX cost estimation process and to implement changes in future cost analyses, if necessary. The Team found the methodology used by TIAX to estimate the cost of producing PEM fuel cells to be reasonable and, using 2005 cell stack technology and assuming production of 500,000 units per year, to have calculated a credible cost of $108/kW.

  14. Updated Capital Cost Estimates for Utility Scale Electricity...

    Annual Energy Outlook 2013 [U.S. Energy Information Administration (EIA)]

    turbines, and other auxiliary equipment * Electrical and instrumentation and control: electrical transformers, switchgear, motor control centers, switchyards, distributed...

  15. Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants

    U.S. Energy Information Administration (EIA) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere IRaghuraji Agro IndustriesTownDells,1Stocks Nov-14TotalThe Outlook269,023Year69,023USWNCFeet)

  16. Eects of eye position on estimates of eye displacement for spatial updating

    E-Print Network [OSTI]

    Crawford, Doug

    E¡ects of eye position on estimates of eye displacement for spatial updating Masaki Tanaka cortex represent spatial memory of visual stimuli in an eye-centered coordinate frame. To preserve spatial stability across eye movements, spatial memory must be updated during each eye movement. Because

  17. Detailed cost estimate of reference residential photovoltaic designs

    SciTech Connect (OSTI)

    Palmer, R.S.; Penasa, D.A.; Thomas, M.G.

    1983-04-01T23:59:59.000Z

    This report presents estimated installation costs for four reference residential photovoltaic designs. Installation cost estimates ranged from $1.28 to $2.12/W/sub p/ for arrays installed by union labor (4.1 to 6.07 kW/sub p/-systems), and from $1.22 to $1.83 W/sub p/ for non-union installations. Standoff mounting was found to increase costs from $1.63/W/sub p/ to $2.12/W/sub p/ for a representative case, whereas 25 kWh of battery storage capacity increased installation costs from $1.44/W/sub p/ to $2.08/W/sub p/. Overall system costs (union-based were $6000 to $7000 for a 4.1 kW array in the northeast, to approx. $9000 for a 6.07 kW/sub p/ array in the southwest. This range of installation costs, approx. $1 to $2/W/sub p/ (in 1980 dollars), is representative of current installation costs for residential PV systems. Any future cost reductions are likely to be small and can be accomplished only by optimization of mounting techniques, module efficiencies, and module reliability in toto.

  18. Current (2009) State-of-the-Art Hydrogen Production Cost Estimate...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Current (2009) State-of-the-Art Hydrogen Production Cost Estimate Using Water Electrolysis Current (2009) State-of-the-Art Hydrogen Production Cost Estimate Using Water...

  19. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems...

    Broader source: Energy.gov (indexed) [DOE]

    Application Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for Automotive Application This report estimates fuel cell system cost for systems produced in the...

  20. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROMof establishing a wind transmission cost adder with respectthat involve wind and divide the cost by the relative share

  1. ELECTRICITY CASE: ECONOMIC COST ESTIMATION FACTORS FOR ECONOMIC

    E-Print Network [OSTI]

    Wang, Hai

    ELECTRICITY CASE: ECONOMIC COST ESTIMATION FACTORS FOR ECONOMIC ASSESSMENT OF TERRORIST ATTACKS Zimmerman, R. CREATE REPORT Under FEMA Grant EMW-2004-GR-0112 May 31, 2005 Center for Risk and Economic #12;2 Abstract The major economic effects of electric power outages are usually associated with three

  2. Estimating the Actual Cost of Transmission System Congestion

    E-Print Network [OSTI]

    straightforward. Assuming complete knowledge of the power system inputs, such as the loads at all system buses congestion on a large-scale power system, such as the North American Eastern Interconnect, the simplicityEstimating the Actual Cost of Transmission System Congestion Thomas J. Overbye Department

  3. Parsons Brinckerhoff New Zealand Ltd COST ESTIMATES FOR

    E-Print Network [OSTI]

    Laughlin, Robert B.

    in this Report. Limitations This Report covers technical data relating to thermal generating plants and is basedParsons Brinckerhoff New Zealand Ltd COST ESTIMATES FOR THERMAL PEAKING PLANT "FINAL REPORT information for all plant. PB has made a number of assumptive statements throughout the Report, and the Report

  4. Estimated Costs of Crop Production in Iowa -2007 File A1-20

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Crop Production in Iowa - 2007 File A1-20 T he estimated costs of corn, corn sources. They include the annual Iowa Farm Business Asso- ciation record summaries, production and costs the state. These costs estimates are representative of average costs for farms in Iowa. Very large or small

  5. Estimated Costs of Crop Production in Iowa -2009 File A1-20

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Crop Production in Iowa - 2009 File A1-20 T he estimated costs of corn, corn sources. They include the annual Iowa Farm Business Asso- ciation record summaries, production and costs the state. These costs estimates are representative of average costs for farms in Iowa. Very large or small

  6. Estimated Costs of Crop Production in Iowa -2008 File A1-20

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Crop Production in Iowa - 2008 File A1-20 T he estimated costs of corn, corn sources. They include the annual Iowa Farm Business Asso- ciation record summaries, production and costs the state. These costs estimates are representative of average costs for farms in Iowa. Very large or small

  7. Decommissioning Cost Estimating Factors And Earned Value Integration

    SciTech Connect (OSTI)

    Sanford, P.C.; Cimmarron, E. [Englewood, CO, B. Skokan, Office of Project Management Oversight, EM-53, United States Department of Energy, Washington, DC (United States)

    2008-07-01T23:59:59.000Z

    The Rocky Flats 771 Project progressed from the planning stage of decommissioning a plutonium facility, through the strip-out of highly-contaminated equipment, removal of utilities and structural decontamination, and building demolition. Actual cost data was collected from the strip-out activities and compared to original estimates, allowing the development of cost by equipment groupings and types and over time. Separate data was developed from the project control earned value reporting and compared with the equipment data. The paper discusses the analysis to develop the detailed factors for the different equipment types, and the items that need to be considered during characterization of a similar facility when preparing an estimate. The factors are presented based on direct labor requirements by equipment type. The paper also includes actual support costs, and examples of fixed or one-time start-up costs. The integration of the estimate and the earned value system used for the 771 Project is also discussed. The paper covers the development of the earned value system as well as its application to a facility to be decommissioned and an existing work breakdown structure. Lessons learned are provided, including integration with scheduling and craft supervision, measurement approaches, and verification of scope completion. In summary: The work of decommissioning the Rocky Flats 771 Project process equipment was completed in 2003. Early in the planning process, we had difficulty in identifying credible data and implementing processes for estimating and controlling this work. As the project progressed, we were able to collect actual data on the costs of removing plutonium contaminated equipment from various areas over the life of this work and associate those costs with individual pieces of equipment. We also were able to develop and test out a system for measuring the earned value of a decommissioning project based on an evolving estimate. These were elements that would have been useful to us in our early planning process, and we would expect that they would find application elsewhere as the DOE weapons complex and some commercial nuclear facilities move towards closure. (authors)

  8. Mass Production Cost Estimation of Direct H2 PEM Fuel Cell Systems...

    Broader source: Energy.gov (indexed) [DOE]

    This report is the seventh annual update of a comprehensive automotive fuel cell cost analysis conducted by Strategic Analysis under contract to the U.S. Department of Energy. In...

  9. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Application Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for Automotive Application This presentation reports on the status of mass production cost...

  10. Property:EstimatedCostMedianUSD | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation,PillarPublicationTypeEstimatedCostMedianUSD Jump to: navigation, search Property

  11. Cost Estimating Guide - DOE Directives, Delegations, and Requirements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOEThe Bonneville Power Administration would likeConstitution AndControllingCoolCorrective Action1, Cost Estimating

  12. 6 GeV LIGHT SOURCE PROJECT COST ESTIMATING PROCEDURE LS-34

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    GeV LIGHT SOURCE PROJECT COST ESTIMATING PROCEDURE LS-34 October 23, 1985 YCAVR To maintain uniformity in estimating the cost requirements of the various components of the 6 GeV...

  13. Develpment of a low Cost Method to Estimate the Seismic Signiture...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Develpment of a low Cost Method to Estimate the Seismic Signiture of a Geothemal Field from Ambient Seismic Noise Analysis Develpment of a low Cost Method to Estimate the Seismic...

  14. The estimated costs of corn, corn silage, soybeans, alfalfa, and pasture maintenance in this report are

    E-Print Network [OSTI]

    Duffy, Michael D.

    The estimated costs of corn, corn silage, soybeans, alfalfa, and pasture maintenance in this report summaries, production and costs data from the Depart- ments of Economics, Agricultural and Biosystems and other input suppliers around the state. These costs estimates are representative of average costs

  15. Estimated Costs of Crop Production in Iowa -2014 File A1-20

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Crop Production in Iowa - 2014 File A1-20 T he estimated costs of corn, corn. They include the annual Iowa Farm Busi- ness Association record summaries, production and costs data from, and a survey of selected agricultural cooperatives and other input suppliers around the state. These cost

  16. Estimated Costs of Crop Production in Iowa -2013 File A1-20

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Crop Production in Iowa - 2013 File A1-20 T he estimated costs of corn, corn. They include the annual Iowa Farm Busi- ness Association record summaries, production and costs data from and a survey of selected agricultural cooperatives and other input suppliers around the state. These cost

  17. Estimated Costs of Crop Production in Iowa -2012 File A1-20

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Crop Production in Iowa - 2012 File A1-20 T he estimated costs of corn, corn. They include the annual Iowa Farm Business Asso- ciation record summaries, production and costs data from and a survey of selected agricultural cooperatives and other input suppliers around the state. These costs

  18. COBRA: A Hybrid Method for Software Cost Estimation, Benchmarking, and Risk Assessment

    E-Print Network [OSTI]

    Briand, Lionel C.

    COBRA: A Hybrid Method for Software Cost Estimation, Benchmarking, and Risk Assessment approaches (referred to as COBRA, COst estimation, Benchmarking, and Risk Assessment). We find through a case accurate and reliable cost estimates to allocate and control project resources, and to make realistic bids

  19. Handbook for quick cost estimates. A method for developing quick approximate estimates of costs for generic actions for nuclear power plants

    SciTech Connect (OSTI)

    Ball, J.R.

    1986-04-01T23:59:59.000Z

    This document is a supplement to a ''Handbook for Cost Estimating'' (NUREG/CR-3971) and provides specific guidance for developing ''quick'' approximate estimates of the cost of implementing generic regulatory requirements for nuclear power plants. A method is presented for relating the known construction costs for new nuclear power plants (as contained in the Energy Economic Data Base) to the cost of performing similar work, on a back-fit basis, at existing plants. Cost factors are presented to account for variations in such important cost areas as construction labor productivity, engineering and quality assurance, replacement energy, reworking of existing features, and regional variations in the cost of materials and labor. Other cost categories addressed in this handbook include those for changes in plant operating personnel and plant documents, licensee costs, NRC costs, and costs for other government agencies. Data sheets, worksheets, and appropriate cost algorithms are included to guide the user through preparation of rough estimates. A sample estimate is prepared using the method and the estimating tools provided.

  20. Estimated Costs of Crop Production in Iowa -2011 File A1-20

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Crop Production in Iowa - 2011 File A1-20 T heestimatedcostsofcorn the annual Iowa Farm Business Association record summaries, production and costs data from the Departments of selected agricultural coop- eratives and other input suppliers around the state. These costs estimates

  1. Data Collection and Normalization for the Development of Cost Estimating Relationships

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    Cost estimating relationships or parametric equations are mathematical statements that indicate that the cost is proportional to a physical commodity. Parametric estimating requires that the statistical analysis be performed on data points to correlate the cost drivers and other system parameters. This chapter discusses considerations for data collection and normalization.

  2. Breckinridge Project, initial effort. Report IX. Operating cost estimate

    SciTech Connect (OSTI)

    none,

    1982-01-01T23:59:59.000Z

    Operating costs are normally broken into three major categories: variable costs including raw materials, annual catalyst and chemicals, and utilities; semi-variable costs including labor and labor related cost; and fixed or capital related charges. The raw materials and utilities costs are proportional to production; however, a small component of utilities cost is independent of production. The catalyst and chemicals costs are also normally proportional to production. Semi-variable costs include direct labor, maintenance labor, labor supervision, contract maintenance, maintenance materials, payroll overheads, operation supplies, and general overhead and administration. Fixed costs include local taxes, insurance and the time value of the capital investment. The latter charge often includes the investor's anticipated return on investment. In determining operating costs for financial analysis, return on investment (ROI) and depreciation are not treated as cash operating costs. These costs are developed in the financial analysis; the annual operating cost determined here omits ROI and depreciation. Project Annual Operating Costs are summarized in Table 1. Detailed supporting information for the cost elements listed below is included in the following sections: Electrical, catalyst and chemicals, and salaries and wages.

  3. Estimating the manufacturing cost of purely organic solar cells Joseph Kalowekamo 1

    E-Print Network [OSTI]

    Massachusetts at Amherst, University of

    to a levelized cost of electricity (LEC) of between 49˘ and 85˘/kWh. In order to achieve a more competitive COE that into a levelized electricity cost (LEC). We find that there is a great deal of uncertainty about the capital costs., Estimating the manufacturing cost of purely organic solar cells, Sol. Energy (2009), doi:10.1016/j

  4. IDC Reengineering Phase 2 & 3 Rough Order of Magnitude (ROM) Cost Estimate Summary (Leveraged NDC Case).

    SciTech Connect (OSTI)

    Harris, James M.; Prescott, Ryan; Dawson, Jericah M.; Huelskamp, Robert M.

    2014-11-01T23:59:59.000Z

    Sandia National Laboratories has prepared a ROM cost estimate for budgetary planning for the IDC Reengineering Phase 2 & 3 effort, based on leveraging a fully funded, Sandia executed NDC Modernization project. This report provides the ROM cost estimate and describes the methodology, assumptions, and cost model details used to create the ROM cost estimate. ROM Cost Estimate Disclaimer Contained herein is a Rough Order of Magnitude (ROM) cost estimate that has been provided to enable initial planning for this proposed project. This ROM cost estimate is submitted to facilitate informal discussions in relation to this project and is NOT intended to commit Sandia National Laboratories (Sandia) or its resources. Furthermore, as a Federally Funded Research and Development Center (FFRDC), Sandia must be compliant with the Anti-Deficiency Act and operate on a full-cost recovery basis. Therefore, while Sandia, in conjunction with the Sponsor, will use best judgment to execute work and to address the highest risks and most important issues in order to effectively manage within cost constraints, this ROM estimate and any subsequent approved cost estimates are on a 'full-cost recovery' basis. Thus, work can neither commence nor continue unless adequate funding has been accepted and certified by DOE.

  5. Systematic methodology for estimating direct capital costs for blanket tritium processing systems

    SciTech Connect (OSTI)

    Finn, P.A.

    1985-01-01T23:59:59.000Z

    This paper describes the methodology developed for estimating the relative capital costs of blanket processing systems. The capital costs of the nine blanket concepts selected in the Blanket Comparison and Selection Study are presented and compared.

  6. Cost estimation of functional and physical changes made to complex systems

    E-Print Network [OSTI]

    Jeziorek, Peter Nicholas, 1981-

    2005-01-01T23:59:59.000Z

    Current cost estimation practices rely on statistically relating physical parameters of a system to historical cost data. Unfortunately, this method is unable to effectively communicate the increasing complexity of system ...

  7. Feature-based investment cost estimation based on modular design of a continuous pharmaceutical manufacturing system

    E-Print Network [OSTI]

    Collins, Donovan (Donovan Scott)

    2011-01-01T23:59:59.000Z

    Previous studies of continuous manufacturing processes have used equipment-factored cost estimation methods to predict savings in initial plant investment costs. In order to challenge and validate the existing methods of ...

  8. Los Alamos Waste Management Cost Estimation Model; Final report: Documentation of waste management process, development of Cost Estimation Model, and model reference manual

    SciTech Connect (OSTI)

    Matysiak, L.M.; Burns, M.L.

    1994-03-01T23:59:59.000Z

    This final report completes the Los Alamos Waste Management Cost Estimation Project, and includes the documentation of the waste management processes at Los Alamos National Laboratory (LANL) for hazardous, mixed, low-level radioactive solid and transuranic waste, development of the cost estimation model and a user reference manual. The ultimate goal of this effort was to develop an estimate of the life cycle costs for the aforementioned waste types. The Cost Estimation Model is a tool that can be used to calculate the costs of waste management at LANL for the aforementioned waste types, under several different scenarios. Each waste category at LANL is managed in a separate fashion, according to Department of Energy requirements and state and federal regulations. The cost of the waste management process for each waste category has not previously been well documented. In particular, the costs associated with the handling, treatment and storage of the waste have not been well understood. It is anticipated that greater knowledge of these costs will encourage waste generators at the Laboratory to apply waste minimization techniques to current operations. Expected benefits of waste minimization are a reduction in waste volume, decrease in liability and lower waste management costs.

  9. Uncertainty Quantification and Calibration in Well Construction Cost Estimates

    E-Print Network [OSTI]

    Valdes Machado, Alejandro

    2013-08-05T23:59:59.000Z

    Contractual cost of drilling company performed on a daily or hourly basis. Bits & BHA All costs for drill bits and BHA components (purchased or rented): -Key seat wiper, RT tools, watermelon mills -Subs for BHA -Reamers, square drill collars, stabilizers...

  10. User's manual for the INDCEPT code for estimating industrial steam boiler plant capital investment costs

    SciTech Connect (OSTI)

    Bowers, H I; Fuller, L C; Hudson, II, C R

    1982-09-01T23:59:59.000Z

    The INDCEPT computer code package was developed to provide conceptual capital investment cost estimates for single- and multiple-unit industrial steam boiler plants. Cost estimates can be made as a function of boiler type, size, location, and date of initial operation. The output includes a detailed breakdown of the estimate into direct and indirect costs. Boiler plant cost models are provided to reflect various types and sources of coal and alternate means of sulfur and particulate removal. Cost models are also included for low-Btu and medium-Btu gas produced in coal gasification plants.

  11. Estimating Administrative and Procedural Costs Natural Resource Restoration Settlements

    E-Print Network [OSTI]

    assessment costs incurred by natural resource trustee agencies (i.e., the federal, state, Indian tribe, and, trustee costs #12;The goal of natural resource damage assessment actions undertaken subsequent to the trustees, or some combination thereof. The damage assessment costs incurred by the natural resource

  12. The estimated costs of corn, corn silage, soybeans, al-falfa, and pasture maintenance in this report are based

    E-Print Network [OSTI]

    Duffy, Michael D.

    The estimated costs of corn, corn silage, soybeans, al- falfa, and pasture maintenance record summaries, production and costs data from the Departments of Economics, Agricultural cooperatives and other input suppliers around the state. These costs estimates are representative of average

  13. Cost Estimating Database and Prototype Tool to Support Design and Construction of Rural and Small Urban Transit Facilities

    E-Print Network [OSTI]

    Zheng, Yue

    2014-10-13T23:59:59.000Z

    and small urban transit facility industry. Unique characteristics and risk factors of those facilities were identified. A cost estimating database was constructed based on the historical cost data collected through online surveys. A cost estimating prototype...

  14. Toward a Common Method ofToward a Common Method of Cost Estimation forCost Estimation for

    E-Print Network [OSTI]

    " to detailed eng'g. studies) · Specific methods and assumptions used by several leading organizations (EPRI Methods CCS Cost Methods Task ForceCCS Cost Methods Task Force · George Booras (EPRI) · John Davison

  15. Brush Busters: How to Estimate Costs for Controlling Small Cedar

    E-Print Network [OSTI]

    Ueckert, Darrell; McGinty, Allan

    2001-04-25T23:59:59.000Z

    method. Figure 3 is for the top-removal method). In Figures 1 and 2, the upper graph shows the cost for the spray only. The center graph shows total cost for spray + labor at $6 per hour. The bottom graph shows total cost for spray + labor at $12 per... hour. Figure 3 shows the costs for the top-removal method, with labor at $6 per hour in the upper graph and $12 per hour in the lower graph. ? Locate your average cedar density (the average calculated in Step #1) on the lower, horizontal axis (density...

  16. Total Estimated Contract Cost: Performance Period Total Fee Paid

    Office of Environmental Management (EM)

    Services & Testing Contract September 2014 Contractor: Contract Number: Contract Type: Advanced Technologies & Labs International Inc. DE-AC27-10RV15051 Cost Plus Award Fee...

  17. FIRE Vacuum Vessel Cost estimate and R&D needs

    E-Print Network [OSTI]

    primary shell and port cost est. Includes: Torus shell · Internal shielding · Active coils · Passive for: - Octant - Midplane port - Aux port - Vertical port - Active coil segment - IB passive plate Does not include: · Internal hdwe supports cost category hours $k hours $k In-house design 24680 2468 7380 738 R

  18. 5-4079-01-P1 RIGHT-OF-WAY COST ESTIMATING TOOL

    E-Print Network [OSTI]

    Texas at Austin, University of

    5-4079-01-P1 RIGHT-OF-WAY COST ESTIMATING TOOL USER MANUAL Authors: Dr. Kara Kockelman, R.S. Dr Acquisition Cost Estimating Planning Tool AUGUST 2006 Performing Organization: Center for Transportation and the Federal Highway Administration. #12;#12;1 Tool Introduction This document is the user manual for the Right

  19. SMB Information Security Seminar (2013) Exercise 2 Estimated costs from bad things happening to your

    E-Print Network [OSTI]

    Magee, Joseph W.

    2013-01-01T23:59:59.000Z

    SMB Information Security Seminar (2013) Exercise 2 ­ Estimated costs from bad things happening to your important information. First, think about the information used in/by your organization. Second, enter into the table below your top two highest priority information types. Third, enter estimated costs

  20. A Neural Network Model for Construction Projects Site Overhead Cost Estimating in Egypt

    E-Print Network [OSTI]

    ElSawy, Ismaail; Razek, Mohammed Abdel

    2011-01-01T23:59:59.000Z

    Estimating of the overhead costs of building construction projects is an important task in the management of these projects. The quality of construction management depends heavily on their accurate cost estimation. Construction costs prediction is a very difficult and sophisticated task especially when using manual calculation methods. This paper uses Artificial Neural Network (ANN) approach to develop a parametric cost-estimating model for site overhead cost in Egypt. Fifty-two actual real-life cases of building projects constructed in Egypt during the seven year period 2002-2009 were used as training materials. The neural network architecture is presented for the estimation of the site overhead costs as a percentage from the total project price.

  1. Estimated Costs of Crop Production in Iowa -2010 File A1-20

    E-Print Network [OSTI]

    Duffy, Michael D.

    Estimated Costs of Crop Production in Iowa - 2010 File A1-20 T heestimatedcostsofcorn Farm Business Association record summaries, production and costs data from the De- partments. Thesecostsestimatesarerepresentativeofaveragecosts for farms in Iowa. Very large or small farms may have lower or higher fixed costs per acre. Due

  2. Ian Sommerville 2000 Software Engineering, 6th edition. Chapter 23 Slide 1 Software cost estimation

    E-Print Network [OSTI]

    Scharff, Christelle

    of software costing and pricing l To describe three metrics for software productivity assessment l To explain and pricing l Estimates are made to discover the cost, to the developer, of producing a software system l There is not a simple relationship between the development cost and the price charged to the customer l Broader

  3. Equipment balancing and cost estimating a computer approach

    E-Print Network [OSTI]

    Cottrell, David Sherman

    1987-01-01T23:59:59.000Z

    Selection(13. 4) REM Selection (13. 4) = Selection (Capacity. Iieneuver, Lode, No. of Dozers) FOR Q=1 TO 13 FOR R=l TO 4 29 READ Selection(Q, R) SolutionScraper (Q, R) = Selection(Q. R) DATA 11, 0. 7, 0. 9, 0, 16, 0. 7, 0. 9. 0, 20. 0. 7. 0. 7. 1. 22... Cos(Scraper(53, 4) FOR I = I T09 READ CostDozer g(l) NEXT I FOR I I T09 FORJ=I T03 READ CostDozer(I J) NEXT J CostDozer(l, 4) = CostDozer(l, 2) NEXT I DATA D38 . D4E . DSB . 06D DATA 07G, 07H, DBL . 09L, D I IN DATA 7, 10, 17, 10, 13. 20...

  4. Examples of Cost Estimation Packages - DOE Directives, Delegations...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    1997 CRD: No DNFSB: No Related History Exemptions Standards Related to: DOE G 430.1-1 Chp 9, Operating Costs DOE G 430.1-1 Chp 19, Data Collection and Normalization for the...

  5. Life Cycle Cost Estimate - DOE Directives, Delegations, and Requiremen...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    chapter discusses life cycle costs and the role they play in planning. g4301-1chp23.pdf -- PDF Document, 52 KB Writer: John Makepeace Subjects: Administration Management...

  6. Cost Estimating Guide, Table of Contents - DOE Directives, Delegations...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    1997 CRD: No DNFSB: No Related History Exemptions Standards Related to: DOE G 430.1-1 Chp 9, Operating Costs DOE G 430.1-1 Chp 19, Data Collection and Normalization for the...

  7. Cost Estimation and Production Evaluation for Hopper Dredges

    E-Print Network [OSTI]

    Hollinberger, Thomas E.

    2010-07-14T23:59:59.000Z

    Dredging projects are expensive government funded projects that are contracted out and competitively bid upon. When planning a trailing suction hopper dredge project or bidding on the request for proposal for such a project, having an accurate cost...

  8. Total Estimated Contract Cost: Performance Period Total Fee Paid

    Office of Environmental Management (EM)

    Office - Oak Ridge, TN Contract Name: Transuranic Waste Processing Contract Sep-14 2,433,940 Cost Plus Award Fee 150,664,017 Fee Information Minimum Fee 2,039,246 Maximum Fee...

  9. Total Estimated Contract Cost: Performance Period Total Fee Paid

    Office of Environmental Management (EM)

    LLC (UCOR) DE-SC-0004645 April 29, 2011 - July 13, 2016 Contract Number: Maximum Fee Cost Plus Award Fee 1,640,839,964 Fee Information Minimum Fee 0 EM Contractor Fee Site:...

  10. Total Estimated Contract Cost: Performance Period Total Fee Paid

    Office of Environmental Management (EM)

    FY2011 FY2012 Fee Information Minimum Fee Maximum Fee September 2014 Contract Number: Cost Plus Incentive Fee Contractor: 3,260,603,765 Contract Period: EM Contractor Fee Site:...

  11. Total Estimated Contract Cost: Performance Period Total Fee Paid

    Office of Environmental Management (EM)

    Wastren-EnergX Mission Support LLC Contract Number: DE-CI0000004 Contract Type: Cost Plus Award Fee 128,879,762 Contract Period: December 2009 - July 2015 Fee Information...

  12. Total Estimated Contract Cost: Performance Period Total Fee Paid

    Office of Environmental Management (EM)

    - September 2015 September 2014 Contractor: Contract Number: Contract Type: Idaho Treatment Group LLC DE-EM0001467 Cost Plus Award Fee Fee Information 444,161,295 Contract Period:...

  13. Total Estimated Contract Cost: Performance Period Total Fee Paid

    Office of Environmental Management (EM)

    Cumulative Fee Paid 22,200,285 Wackenhut Services, Inc. DE-AC30-10CC60025 Contractor: Cost Plus Award Fee 989,000,000 Contract Period: Contract Type: January 2010 - December...

  14. Total Estimated Contract Cost:) Performance Period Total Fee...

    Office of Environmental Management (EM)

    Washington Closure LLC DE-AC06-05RL14655 Contractor: Contract Number: Contract Type: Cost Plus Incentive Fee 2,366,753,325 Fee Information 0 Maximum Fee 319,511,699...

  15. Total Estimated Contract Cost: Performance Period Total Fee Paid

    Office of Environmental Management (EM)

    Number: Contract Type: Contract Period: 0 Minimum Fee Maximum Fee Washington River Protection Solutions LLC DE-AC27-08RV14800 Cost Plus Award Fee 5,553,789,617 Fee Information...

  16. Total Estimated Contract Cost: Performance Period Total Fee Paid

    Office of Environmental Management (EM)

    & Wilcox Conversion Services, LLC Contract Number: DE-AC30-11CC40015 Contract Type: Cost Plus Award Fee Fee Available 4,324,912 408,822,369 Contract Period: December 2010 -...

  17. Total Estimated Contract Cost: Performance Period Total Fee Paid

    Office of Environmental Management (EM)

    0 Contractor: Bechtel National Inc. Contract Number: DE-AC27-01RV14136 Contract Type: Cost Plus Award Fee Maximum Fee* 595,123,540 Fee Available 102,622,325 10,714,819,974...

  18. Equipment balancing and cost estimating a computer approach 

    E-Print Network [OSTI]

    Cottrell, David Sherman

    1987-01-01T23:59:59.000Z

    Selection(13. 4) REM Selection (13. 4) = Selection (Capacity. Iieneuver, Lode, No. of Dozers) FOR Q=1 TO 13 FOR R=l TO 4 29 READ Selection(Q, R) SolutionScraper (Q, R) = Selection(Q. R) DATA 11, 0. 7, 0. 9, 0, 16, 0. 7, 0. 9. 0, 20. 0. 7. 0. 7. 1. 22... Cos(Scraper(53, 4) FOR I = I T09 READ CostDozer g(l) NEXT I FOR I I T09 FORJ=I T03 READ CostDozer(I J) NEXT J CostDozer(l, 4) = CostDozer(l, 2) NEXT I DATA D38 . D4E . DSB . 06D DATA 07G, 07H, DBL . 09L, D I IN DATA 7, 10, 17, 10, 13. 20...

  19. Estimating the economic cost of sea-level rise

    E-Print Network [OSTI]

    Sugiyama, Masahiro, Ph. D. Massachusetts Institute of Technology

    2007-01-01T23:59:59.000Z

    (cont.) In the case of a classical linear sea-level rise of one meter per century, the use of DIVA generally decreases the protection fraction of the coastline, and results in a smaller protection cost because of high ...

  20. Solid Waste Operations Complex W-113: Project cost estimate. Preliminary design report. Volume IV

    SciTech Connect (OSTI)

    NONE

    1995-01-01T23:59:59.000Z

    This document contains Volume IV of the Preliminary Design Report for the Solid Waste Operations Complex W-113 which is the Project Cost Estimate and construction schedule. The estimate was developed based upon Title 1 material take-offs, budgetary equipment quotes and Raytheon historical in-house data. The W-113 project cost estimate and project construction schedule were integrated together to provide a resource loaded project network.

  1. Off-Highway Gasoline Consuption Estimation Models Used in the Federal Highway Administration Attribution Process: 2008 Updates

    SciTech Connect (OSTI)

    Hwang, Ho-Ling [ORNL; Davis, Stacy Cagle [ORNL

    2009-12-01T23:59:59.000Z

    This report is designed to document the analysis process and estimation models currently used by the Federal Highway Administration (FHWA) to estimate the off-highway gasoline consumption and public sector fuel consumption. An overview of the entire FHWA attribution process is provided along with specifics related to the latest update (2008) on the Off-Highway Gasoline Use Model and the Public Use of Gasoline Model. The Off-Highway Gasoline Use Model is made up of five individual modules, one for each of the off-highway categories: agricultural, industrial and commercial, construction, aviation, and marine. This 2008 update of the off-highway models was the second major update (the first model update was conducted during 2002-2003) after they were originally developed in mid-1990. The agricultural model methodology, specifically, underwent a significant revision because of changes in data availability since 2003. Some revision to the model was necessary due to removal of certain data elements used in the original estimation method. The revised agricultural model also made use of some newly available information, published by the data source agency in recent years. The other model methodologies were not drastically changed, though many data elements were updated to improve the accuracy of these models. Note that components in the Public Use of Gasoline Model were not updated in 2008. A major challenge in updating estimation methods applied by the public-use model is that they would have to rely on significant new data collection efforts. In addition, due to resource limitation, several components of the models (both off-highway and public-us models) that utilized regression modeling approaches were not recalibrated under the 2008 study. An investigation of the Environmental Protection Agency's NONROAD2005 model was also carried out under the 2008 model update. Results generated from the NONROAD2005 model were analyzed, examined, and compared, to the extent that is possible on the overall totals, to the current FHWA estimates. Because NONROAD2005 model was designed for emission estimation purposes (i.e., not for measuring fuel consumption), it covers different equipment populations from those the FHWA models were based on. Thus, a direct comparison generally was not possible in most sectors. As a result, NONROAD2005 data were not used in the 2008 update of the FHWA off-highway models. The quality of fuel use estimates directly affect the data quality in many tables published in the Highway Statistics. Although updates have been made to the Off-Highway Gasoline Use Model and the Public Use Gasoline Model, some challenges remain due to aging model equations and discontinuation of data sources.

  2. AREA COST FACTOR INDEXES PAX NEWSLETTER NO. 3.2.1

    E-Print Network [OSTI]

    US Army Corps of Engineers

    ). The ACF index is the combination factors of local construction costs of labor, material, and equipmentAREA COST FACTOR INDEXES PAX NEWSLETTER NO. 3.2.1 15 March 2002 1. The attached updated area cost manual TM 5-800-4, Programming Cost Estimates for Military Construction, dated May 1994. The updated ACF

  3. Survey of State-Level Cost and Benefit Estimates of Renewable Portfolio Standards

    SciTech Connect (OSTI)

    Heeter, J.; Barbose, G.; Bird, L.; Weaver, S.; Flores-Espino, F.; Kuskova-Burns, K.; Wiser, R.

    2014-05-01T23:59:59.000Z

    Most renewable portfolio standards (RPS) have five or more years of implementation experience, enabling an assessment of their costs and benefits. Understanding RPS costs and benefits is essential for policymakers evaluating existing RPS policies, assessing the need for modifications, and considering new policies. This study provides an overview of methods used to estimate RPS compliance costs and benefits, based on available data and estimates issued by utilities and regulators. Over the 2010-2012 period, average incremental RPS compliance costs in the United States were equivalent to 0.8% of retail electricity rates, although substantial variation exists around this average, both from year-to-year and across states. The methods used by utilities and regulators to estimate incremental compliance costs vary considerably from state to state and a number of states are currently engaged in processes to refine and standardize their approaches to RPS cost calculation. The report finds that state assessments of RPS benefits have most commonly attempted to quantitatively assess avoided emissions and human health benefits, economic development impacts, and wholesale electricity price savings. Compared to the summary of RPS costs, the summary of RPS benefits is more limited, as relatively few states have undertaken detailed benefits estimates, and then only for a few types of potential policy impacts. In some cases, the same impacts may be captured in the assessment of incremental costs. For these reasons, and because methodologies and level of rigor vary widely, direct comparisons between the estimates of benefits and costs are challenging.

  4. ERCB updates estimated reserves of crude bitumen and synthetic crude oil

    SciTech Connect (OSTI)

    Not Available

    1986-09-01T23:59:59.000Z

    The Alberta Energy Resources Conservation Board prepares yearly updates of Alberta reserves of crude bitumen and synthetic crude oil. The latest figures are as of the end of 1985. Alberta's crude bitumen reserves are contained in designated deposits with the oil sand areas of Athabasca, Cold Lake, and Peace River. The total initial volume of crude bitumen in-place for the designated deposits at December 31, 1985 was estimated as 266.4 billion cubic meters. Within the potentially mineable areas, the initial mineable volume in-place of crude bitumen was established to be 11.9 billion cubic meters. After allowing for surface facilities (plant sites, tailings ponds, discard dumps), environmental protection corridors along major rivers, isolated mineable areas, and assuming a combined mining/extraction recovery factor of 0.78, the resulting initial established mineable reserve of crude bitumen is estimated to be 5.2 billion cubic meters. Data are presented in three tables.

  5. Total Estimated Contract Cost: Performance Period Total Fee Paid

    Office of Environmental Management (EM)

    Fee Paid 127,390,991 Contract Number: Fee Available Contract Period: Contract Type: Cost Plus Award Fee 4,104,318,749 28,500,000 31,597,837 0 39,171,018 32,871,600 EM...

  6. Using Natural Gas Transmission Pipeline Costs to Estimate Hydrogen Pipeline Costs

    E-Print Network [OSTI]

    Parker, Nathan

    2004-01-01T23:59:59.000Z

    Warren R. “U.S. interstate pipelines begin 1993 on upbeat. ”66. ? True, Warren R. “Current pipeline costs. ” Oil & GasWarren R. “U.S. interstate pipelines ran more efficiently in

  7. Rethinking construction cost overruns: an artificial neural network approach to construction cost estimation 

    E-Print Network [OSTI]

    Ahiaga-Dagbui, Dominic Doe

    2014-11-27T23:59:59.000Z

    The main concern of a construction client is to procure a facility that is able to meet its functional requirements, of the required quality, and delivered within an acceptable budget and timeframe. The cost aspect of ...

  8. Bureau of mines cost estimating system handbook (in two parts). 1. Surface and underground mining

    SciTech Connect (OSTI)

    Not Available

    1987-01-01T23:59:59.000Z

    The handbook provides a convenient costing procedure based on the summation of the costs for unit processes required in any particular mining or mineral processing operation. The costing handbook consists of a series of costing sections, each corresponding to a specific mining unit process. Contained within each section is the methodology to estimate either the capital or operating cost for that unit process. The unit process sections may be used to generate, in January 1984 dollars, costs through the use of either costing curves or formulae representing the prevailing technology. Coverage for surface mining includes dredging, quarrying, strip mining, and open pit mining. The underground mining includes individual development sections for drifting, raising, shaft sinking, stope development, various mining methods, underground mine haulage, general plant, and underground mine administrative cost.

  9. Schedule and cost estimate for an innovative Boston Harbor concert hall

    E-Print Network [OSTI]

    Coste, Amelie, 1982-

    2004-01-01T23:59:59.000Z

    This thesis formulates a cost estimate and schedule for constructing the Boston Concert Hall, an innovative hypothetical building composed of two concert halls and a restaurant. Concert Halls are complex and expensive ...

  10. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    estimates for material and manufacturing costs of complete 80 kWnet direct-hydrogen proton exchange membrane fuel cell systems suitable for powering light-duty automobiles. Mass...

  11. Estimating the Market Penetration of Residential Cool Storage Technology Using Economic Cost Modeling 

    E-Print Network [OSTI]

    Weijo, R. O.; and Brown, D. R.

    1988-01-01T23:59:59.000Z

    This study estimated the market penetration for residential cool storage technology using economic cost modeling. Residential cool storage units produce and store chill during off-peak periods of the day to be used during times of peak electric...

  12. EM's Cost Estimating Program Highlights 2014 Accomplishments | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't Your Destiny:RevisedAdvisory Board Contributions EMEM Recovery ActSeries |of Energy Cost

  13. Hydrogen Production Cost Estimate Using Biomass Gasification: Independent Review

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy ChinaofSchaefer To:Department ofOral Testimony ofMonitoring,Hydrogen Production Cost

  14. Implementation of DOE/NFDI D&D Cost Estimating Tool (POWERtool) for Initiative Facilities at the Savannah River Site

    SciTech Connect (OSTI)

    Austin, W. E.; WSRC; Baker, S. B. III, Cutshall, C. M.; Crouse, J. L.

    2003-02-26T23:59:59.000Z

    The Savannah River Site (SRS) has embarked on an aggressive D&D program to reduce the footprint of excess facilities. Key to the success of this effort is the preparation of accurate cost estimates for decommissioning. SRS traditionally uses ''top-down'' rough order-of-magnitude (ROM) estimating for decommissioning cost estimates. A second cost estimating method (POWERtool) using a ''bottoms-up'' approach has been applied to many of the SRS excess facilities in the T and D-area. This paper describes the use of both estimating methods and compares the estimated costs to actual costs of 5 facilities that were decommissioned in 2002.

  15. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for

    E-Print Network [OSTI]

    Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for Automotive Applications for transportation. Fuel cell systems will have to be cost-competitive with conventional and advanced vehicle cell vehicles have the potential to eliminate the need for oil in the transportation sector. Fuel cell

  16. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for

    E-Print Network [OSTI]

    Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems for Automotive Applications vehicles offer an environmentally clean and energy-secure transportation pathway. Fuel cell systems number of vehicles it represents, DOE has established detailed cost targets for automotive fuel cell

  17. A Growing and Costly Issue An estimated 1.8 million adult Texans have been

    E-Print Network [OSTI]

    A Growing and Costly Issue An estimated 1.8 million adult Texans have been diagnosed with diabetes, while the diabetes in another 460,000 remains undiagnosed. The annual cost of diabetes in Texas's Response Diabetes is not curable, but it is manageable. People can learn skills to effectively manage

  18. A Growing and Costly Issue An estimated 1.8 million adult Texans have been

    E-Print Network [OSTI]

    A Growing and Costly Issue An estimated 1.8 million adult Texans have been diagnosed with diabetes, while the diabetes of another 460,000 remains undiagnosed. The annual cost of diabetes in Texas's Response Diabetes is not curable, but it is manageable. People can learn skills to effectively manage

  19. SPS susceptible-system cost factors investment summary and mitigation-cost-increment estimates

    SciTech Connect (OSTI)

    Morrison, E L

    1980-05-01T23:59:59.000Z

    The Electromagnetic Compatibility (EMC) evaluation program supporting the SPS Concept Development Evaluation Phase has included examinations of the degradation in capability of all susceptible communications and electronic systems that could be exposed to SPS emissions, the development and testing of mitigation techniques to allow operation in the SPS environment, and the development of total investment and mitigation cost data. Mitigation costs relate only to the modification or reconfiguration of susceptible systems; redeployment being a possible consideration for rectenna siting exercises during the SPS Engineering Development Phase. An extensive survey is summarized regarding the current and planned facilities using the equipment categories listed: microwave communications; radar systems; sensors; computers; medical equipment; and research support. Current investment, future plans, and mitigation costs are presented, with geographic distribution in six CONUS areas.

  20. Microsoft PowerPoint - Cost Estimating for Hydro Planning

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOEThe Bonneville PowerCherries 82981-1cnHighand Retrievals fromprocessEstimating for Hydropower Project Planning M

  1. Identification of potential strategies, methods, and tools for improving cost estimating practices for highway projects

    E-Print Network [OSTI]

    Donnell, Kelly Elaine

    2005-08-29T23:59:59.000Z

    reflect the related cost in the project?s estimate (Board on Infrastructure and the Constructed Environment 2003, Booz?Allen & Hamilton Inc. and DRI/McGraw-Hill 1995, Callahan 1998, Hufschmidt and Gerin 1970, ?Mass Transit?? 1999, Semple et al. 1994... are not adequately addressed when preparing cost estimates, cost increases are likely to occur (Board on Infrastructure and the Constructed Environment 2003, Bechtel/Parsons Brinckerhoff 2003, Booz?Allen & Hamilton Inc. and DRI/McGraw-Hill 1995, Callahan 1998...

  2. Review of cost estimates for reducing CO2 emissions. Final report, Task 9

    SciTech Connect (OSTI)

    Not Available

    1990-10-01T23:59:59.000Z

    Since the ground breaking work of William Nordhaus in 1977, cost estimates for reducing CO{sub 2} emissions have been developed by numerous groups. The various studies have reported sometimes widely divergent cost estimates for reducing CO{sub 2} emissions. Some recent analyses have indicated that large reductions in CO{sub 2} emissions could be achieved at zero or negative costs (e.g. Rocky Mountain Institute 1989). In contrast, a recent study by Alan Manne of Stanford and Richard Richels of the Electric Power Research Institute (Manne-Richels 1989) concluded that in the US the total discounted costs of reducing CO{sub 2} emissions by 20 percent below the 1990 level could be as much as 3.6 trillion dollars over the period from 1990 to 2100. Costs of this order of magnitude would represent about 5 percent of US GNP. The purpose of this briefing paper is to summarize the different cost estimates for CO{sub 2} emission reduction and to identify the key issues and assumptions that underlie these cost estimates.

  3. Regional Cost Estimates for Reclamation Practices on Arid and Semiarid Lands

    SciTech Connect (OSTI)

    W. K. Ostler

    2002-02-01T23:59:59.000Z

    The U.S. Army uses the Integrated Training Area Management program for managing training land. One of the major objectives of the Integrated Training Area Management program has been to develop a method for estimating training land carrying capacity in a sustainable manner. The Army Training and Testing Area Carrying Capacity methodology measures training load in terms of Maneuver Impact Miles. One Maneuver Impact Mile is the equivalent impact of an M1A2 tank traveling one mile while participating in an armor battalion field training exercise. The Army Training and Testing Area Carrying Capacity methodology is also designed to predict land maintenance costs in terms of dollars per Maneuver Impact Mile. The overall cost factor is calculated using the historical cost of land maintenance practices and the effectiveness of controlling erosion. Because land maintenance costs and effectiveness are influenced by the characteristics of the land, Army Training and Testing Area Carrying Capacity cost factors must be developed for each ecological region of the country. Costs for land maintenance activities are presented here for the semiarid and arid regions of the United States. Five ecoregions are recognized, and average values for reclamation activities are presented. Because there are many variables that can influence costs, ranges for reclamation activities are also presented. Costs are broken down into six major categories: seedbed preparation, fertilization, seeding, planting, mulching, and supplemental erosion control. Costs for most land reclamation practices and materials varied widely within and between ecological provinces. Although regional cost patterns were evident for some practices, the patterns were not consistent between practices. For the purpose of estimating land reclamation costs for the Army Training and Testing Area Carrying Capacity methodology, it may be desirable to use the ''Combined Average'' of all provinces found in the last row of each table to estimate costs for arid lands in general.

  4. Startup Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    This chapter discusses startup costs for construction and environmental projects, and estimating guidance for startup costs.

  5. AREA COST FACTOR INDEXES PAX NEWSLETTER NO. 3.2.1

    E-Print Network [OSTI]

    US Army Corps of Engineers

    in the continental US). The ACF index is the combination factors of the local construction costs of labor, materialAREA COST FACTOR INDEXES PAX NEWSLETTER NO. 3.2.1 01 May 1998 1. The following is a list of updated 5-800-4, Programming Cost Estimates for Military Construction, dated May 1994. The updated ACF

  6. Cost estimates for near-term depolyment of advanced traffic management systems. Final report

    SciTech Connect (OSTI)

    Stevens, S.S.; Chin, S.M.

    1993-02-15T23:59:59.000Z

    The objective of this study is to provide cost est engineering, design, installation, operation and maintenance of Advanced Traffic Management Systems (ATMS) in the largest 75 metropolitan areas in the United States. This report gives estimates for deployment costs for ATMS in the next five years, subject to the qualifications and caveats set out in following paragraphs. The report considers infrastructure components required to realize fully a functional ATMS over each of two highway networks (as discussed in the Section describing our general assumptions) under each of the four architectures identified in the MITRE Intelligent Vehicle Highway Systems (IVHS) Architecture studies. The architectures are summarized in this report in Table 2. Estimates are given for eight combinations of highway networks and architectures. We estimate that it will cost between $8.5 Billion (minimal network) and $26 Billion (augmented network) to proceed immediately with deployment of ATMS in the largest 75 metropolitan areas. Costs are given in 1992 dollars, and are not adjusted for future inflation. Our estimates are based partially on completed project costs, which have been adjusted to 1992 dollars. We assume that a particular architecture will be chosen; projected costs are broken by architecture.

  7. Estimated costs of ventilation systems complying with the HUD ventilation standard for manufactured homes

    SciTech Connect (OSTI)

    Miller, J.D.; Conner, C.C.

    1993-11-01T23:59:59.000Z

    At the request of the US Department of Housing and Urban Development (HUD), the Pacific Northwest Laboratory estimated the material, labor, and operating costs for ventilation equipment needed for compliance with HUD`s proposed revision to the ventilation standard for manufactured housing. This was intended to bound the financial impacts of the ventilation standard revision. Researchers evaluated five possible prototype ventilation systems that met the proposed ventilation requirements. Of those five, two systems were determined to be the most likely used by housing manufacturers: System 1 combines a fresh air duct with the existing central forced-air system to supply and circulate fresh air to conditioned spaces. System 2 uses a separate exhaust fan to remove air from the manufactured home. The estimated material and labor costs for these two systems range from $200 to $300 per home. Annual operating costs for the two ventilation systems were estimated for 20 US cities. The estimated operating costs for System 1 ranged from $55/year in Las Vegas, Nevada, to $83/year in Bismarck, North Dakota. Operating costs for System 2 ranged from a low of $35/year in Las Vegas to $63/year in Bismarck. Thus, HUD`s proposed increase in ventilation requirements will add less than $100/year to the energy cost of a manufactured home.

  8. Estimating costs of low-level radioactive waste disposal alternatives for the Commonwealth of Massachusetts

    SciTech Connect (OSTI)

    Not Available

    1994-02-01T23:59:59.000Z

    This report was prepared for the Commonwealth of Massachusetts by the Idaho National Engineering Laboratory, National Low-Level Waste Management Program. It presents planning life-cycle cost (PLCC) estimates for four sizes of in-state low-level radioactive waste (LLRW) disposal facilities. These PLCC estimates include preoperational and operational expenditures, all support facilities, materials, labor, closure costs, and long-term institutional care and monitoring costs. It is intended that this report bc used as a broad decision making tool for evaluating one of the several complex factors that must be examined when deciding between various LLRW management options -- relative costs. Because the underlying assumptions of these analyses will change as the Board decides how it will manage Massachusett`s waste and the specific characteristics any disposal facility will have, the results of this study are not absolute and should only be used to compare the relative costs of the options presented. The disposal technology selected for this analysis is aboveground earth-mounded vaults. These vaults are reinforced concrete structures where low-level waste is emplaced and later covered with a multi-layered earthen cap. The ``base case`` PLCC estimate was derived from a preliminary feasibility design developed for the Illinois Low-Level Radioactive Waste Disposal Facility. This PLCC report describes facility operations and details the procedure used to develop the base case PLCC estimate for each facility component and size. Sensitivity analyses were performed on the base case PLCC estimate by varying several factors to determine their influences upon the unit disposal costs. The report presents the results of the sensitivity analyses for the five most significant cost factors.

  9. Site restoration: Estimation of attributable costs from plutonium-dispersal accidents

    SciTech Connect (OSTI)

    Chanin, D.I.; Murfin, W.B. [Technadyne Engineering Consultants, Inc., Albuquerque, NM (United States)

    1996-05-01T23:59:59.000Z

    A nuclear weapons accident is an extremely unlikely event due to the extensive care taken in operations. However, under some hypothetical accident conditions, plutonium might be dispersed to the environment. This would result in costs being incurred by the government to remediate the site and compensate for losses. This study is a multi-disciplinary evaluation of the potential scope of the post-accident response that includes technical factors, current and proposed legal requirements and constraints, as well as social/political factors that could influence decision making. The study provides parameters that can be used to assess economic costs for accidents postulated to occur in urban areas, Midwest farmland, Western rangeland, and forest. Per-area remediation costs have been estimated, using industry-standard methods, for both expedited and extended remediation. Expedited remediation costs have been evaluated for highways, airports, and urban areas. Extended remediation costs have been evaluated for all land uses except highways and airports. The inclusion of cost estimates in risk assessments, together with the conventional estimation of doses and health effects, allows a fuller understanding of the post-accident environment. The insights obtained can be used to minimize economic risks by evaluation of operational and design alternatives, and through development of improved capabilities for accident response.

  10. Equipment Design and Cost Estimation for Small Modular Biomass Systems, Synthesis Gas Cleanup, and Oxygen Separation Equipment; Task 1: Cost Estimates of Small Modular Systems

    SciTech Connect (OSTI)

    Nexant Inc.

    2006-05-01T23:59:59.000Z

    This deliverable is the Final Report for Task 1, Cost Estimates of Small Modular Systems, as part of NREL Award ACO-5-44027, ''Equipment Design and Cost Estimation for Small Modular Biomass Systems, Synthesis Gas Cleanup and Oxygen Separation Equipment''. Subtask 1.1 looked into processes and technologies that have been commercially built at both large and small scales, with three technologies, Fluidized Catalytic Cracking (FCC) of refinery gas oil, Steam Methane Reforming (SMR) of Natural Gas, and Natural Gas Liquids (NGL) Expanders, chosen for further investigation. These technologies were chosen due to their applicability relative to other technologies being considered by NREL for future commercial applications, such as indirect gasification and fluidized bed tar cracking. Research in this subject is driven by an interest in the impact that scaling has on the cost and major process unit designs for commercial technologies. Conclusions from the evaluations performed could be applied to other technologies being considered for modular or skid-mounted applications.

  11. Location Estimation with a Differential Update Ali Rahimi and Trevor Darrell

    E-Print Network [OSTI]

    Darrell, Trevor

    algorithm by cal- culating globally consistent trajectories of a robot as it navigates along a 2D trajectory. To update a trajectory of length t, the update takes O(t). When all conditional distributions are linear to recover the trajectory of a robot given noisy measurements of its movement between points in its

  12. The Precision and Energetic Cost of Snapshot Estimates in Wireless Sensor Networks

    E-Print Network [OSTI]

    The Precision and Energetic Cost of Snapshot Estimates in Wireless Sensor Networks Paul G. Flikkema, the design space of wireless sensor networks is enormous, and traditional disciplinary boundaries of lower performance. I. INTRODUCTION One of the most intriguing applications of wireless sensor networking

  13. Estimating the economic cost of sea-level rise Masahiro Sugiyama

    E-Print Network [OSTI]

    Estimating the economic cost of sea-level rise by Masahiro Sugiyama Bachelor of Science in Earth Fulfillment of the Requirements for the Degree of Master of Science in Technology and Policy at the Massachusetts Institute of Technology February 2007 ©2007 Massachusetts Institute of Technology. All rights

  14. 1. Utilize recent historical cost data, estimating manuals, and actual vendor quotes as situation allows.

    E-Print Network [OSTI]

    Rock, Chris

    1. Utilize recent historical cost data, estimating manuals, and actual vendor quotes as situation Engineering Services to respond and complete customer facility projects. Return 90% of all Opinion of Probable Engineering Services to respond and complete customer facility projects. Develop accurate priority list

  15. A new database of residential building measures and estimated costs helps the U.S. building industry determine the most

    E-Print Network [OSTI]

    provides a single, consistent source of current data for DOE and private-sector energy audit and simulation at the National Renewable Energy Laboratory (NREL) have developed the National Residential Efficiency Measures to the database by uploading retrofit project and measure cost data. It is routinely updated to add new measures

  16. Item No. 3 process facilities cost estimates and schedules for facilities capability assurance program nuclear facilities modernization - FY 1989 line item, authorization No. D79

    SciTech Connect (OSTI)

    NONE

    1989-07-01T23:59:59.000Z

    Data is presented concerning cost estimates and schedules for process facilities and nuclear facilities modernization.

  17. Estimated increases in the cost of electricity under three acid-rain control bills

    SciTech Connect (OSTI)

    Hillsman, E.L. (Oak Ridge National Lab., TN (United States)); Alvic, D.R. (Tennessee Univ., Knoxville, TN (United States))

    1991-01-01T23:59:59.000Z

    Several bills were introduced in the past two Congresses to reduce emissions of sulfur dioxide and nitrogen oxides from electric power plants. The effects of these bills on electricity costs depend on features of the bills, on the mix of generating capacity owned by different electric utilities, on the technologies available for complying with the legislation, and on the time horizon used to calculate the costs. A system of computer software has been developed to make utility-specific estimates of the effects of different legislation on electricity costs. This paper presents sample results from a larger analysis of six pieces of legislation. These results suggest that the emissions trading systems proposed in some legislation, and adopted in the Clean Air Act Amendments of 1991, may have less effect than expected on the cost of complying with the legislation. 5 refs., 2 figs., 2 tabs.

  18. A comparison of estimates of cost-effectiveness of alternative fuels and vehicles for reducing emissions

    SciTech Connect (OSTI)

    Hadder, G.R.

    1995-11-01T23:59:59.000Z

    The cost-effectiveness ratio (CER) is a measure of the monetary value of resources expended to obtain reductions in emissions of air pollutants. The CER can lead to selection of the most effective sequence of pollution reduction options. Derived with different methodologies and technical assumptions, CER estimates for alternative fuel vehicles (AFVs) have varied widely among pervious studies. In one of several explanations of LCER differences, this report uses a consistent basis for fuel price to re-estimate CERs for AFVs in reduction of emissions of criteria pollutants, toxics, and greenhouse gases. The re-estimated CERs for a given fuel type have considerable differences due to non-fuel costs and emissions reductions, but the CERs do provide an ordinal sense of cost-effectiveness. The category with CER less than $5,000 per ton includes compressed natural gas and ed Petroleum gas vehicles; and E85 flexible-fueled vehicles (with fuel mixture of 85 percent cellulose-derived ethanol in gasoline). The E85 system would be much less attractive if corn-derived ethanol were used. The CER for E85 (corn-derived) is higher with higher values placed on the reduction of gas emissions. CER estimates are relative to conventional vehicles fueled with Phase 1 California reformulated gasoline (RFG). The California Phase 2 RFG program will be implemented before significant market penetration by AFVs. CERs could be substantially greater if they are calculated incremental to the Phase 2 RFG program. Regression analysis suggests that different assumptions across studies can sometimes have predictable effects on the CER estimate of a particular AFV type. The relative differences in cost and emissions reduction assumptions can be large, and the effect of these differences on the CER estimate is often not predictable. Decomposition of CERs suggests that methodological differences can make large contributions to CER differences among studies.

  19. DEEPWATER HORIZON OIL SPILL ESTIMATE: UPDATE JUNE 11, 2010 by Professor Satish Nagarajaiah, Rice University (www.ruf.rice.edu/~nagaraja &

    E-Print Network [OSTI]

    Nagarajaiah, Satish

    DEEPWATER HORIZON OIL SPILL ESTIMATE: UPDATE JUNE 11, 2010 by Professor Satish Nagarajaiah, Rice. http://www.nytimes.com/2010/06/11/us/11spill.html?hp New Estimates Double Rate of Oil Flowing on Thursday essentially doubled its estimate of how much oil has been spewing from the out-of-control BP well

  20. Lead Coolant Test Facility Systems Design, Thermal Hydraulic Analysis and Cost Estimate

    SciTech Connect (OSTI)

    Soli Khericha; Edwin Harvego; John Svoboda; Ryan Dalling

    2012-01-01T23:59:59.000Z

    The Idaho National Laboratory prepared a preliminary technical and functional requirements (T&FR), thermal hydraulic design and cost estimate for a lead coolant test facility. The purpose of this small scale facility is to simulate lead coolant fast reactor (LFR) coolant flow in an open lattice geometry core using seven electrical rods and liquid lead or lead-bismuth eutectic coolant. Based on review of current world lead or lead-bismuth test facilities and research needs listed in the Generation IV Roadmap, five broad areas of requirements were identified as listed: (1) Develop and Demonstrate Feasibility of Submerged Heat Exchanger; (2) Develop and Demonstrate Open-lattice Flow in Electrically Heated Core; (3) Develop and Demonstrate Chemistry Control; (4) Demonstrate Safe Operation; and (5) Provision for Future Testing. This paper discusses the preliminary design of systems, thermal hydraulic analysis, and simplified cost estimate. The facility thermal hydraulic design is based on the maximum simulated core power using seven electrical heater rods of 420 kW; average linear heat generation rate of 300 W/cm. The core inlet temperature for liquid lead or Pb/Bi eutectic is 4200 C. The design includes approximately seventy-five data measurements such as pressure, temperature, and flow rates. The preliminary estimated cost of construction of the facility is $3.7M (in 2006 $). It is also estimated that the facility will require two years to be constructed and ready for operation.

  1. Making appropriate comparisons of estimated and actual costs of reducing SO{sub 2} emissions under Title IV

    SciTech Connect (OSTI)

    Smith, A.E. [DFI/Aeronomics Inc., Washington, DC (United States)

    1998-12-31T23:59:59.000Z

    A current sentiment within some parts of the environmental policy community is that market-based regulatory approaches such as emissions trading have proven so effective that actual costs will be only a small fraction of what ex ante cost estimation procedures would project. With this line of reasoning, some have dismissed available cost estimates for major proposed new regulations, such as the new PM and ozone NAAQS, as not meaningful for policy decisions. The most commonly used evidence in support of this position is the experience with SO{sub 2} reductions under Title IV of the 1990 Clean Air Act Amendments. In Title IV, a market for emissions allowances has been used to achieve reductions in sulfur dioxides (SO{sub 2}) to ameliorate acid rain. It is commonly asserted today that the cost of achieving the SO{sub 2} emissions reductions has been only one-tenth or less of what Title IV was originally expected to cost. This paper demonstrates that, to the contrary, actual costs for SO{sub 2} reductions remain roughly in line with original estimates associated with Title IV. Erroneous conclusions about Title IV`s costs are due to inappropriate comparisons of a variety of different measures that appear to be comparable only because they are all stated in dollars per ton. Program cost estimates include the total costs of a fully-implemented regulatory program. The very low costs of Title IV that are commonly cited today are neither directly reflective of a fully implemented Title IV, (which is still many years away) nor reflective of all the costs already incurred. Further, a careful review of history finds that the initial cost estimates that many cite were never associated with Title IV. Technically speaking, people are comparing the estimated control costs for the most-costly power plant associated with earlier acid rain regulatory proposals with prices from a market that do not directly reflect total costs.

  2. Critical analysis of the Hanford spent nuclear fuel project activity based cost estimate

    SciTech Connect (OSTI)

    Warren, R.N.

    1998-09-29T23:59:59.000Z

    In 1997, the SNFP developed a baseline change request (BCR) and submitted it to DOE-RL for approval. The schedule was formally evaluated to have a 19% probability of success [Williams, 1998]. In December 1997, DOE-RL Manager John Wagoner approved the BCR contingent upon a subsequent independent review of the new baseline. The SNFP took several actions during the first quarter of 1998 to prepare for the independent review. The project developed the Estimating Requirements and Implementation Guide [DESH, 1998] and trained cost account managers (CAMS) and other personnel involved in the estimating process in activity-based cost (ABC) estimating techniques. The SNFP then applied ABC estimating techniques to develop the basis for the December Baseline (DB) and documented that basis in Basis of Estimate (BOE) books. These BOEs were provided to DOE in April 1998. DOE commissioned Professional Analysis, Inc. (PAI) to perform a critical analysis (CA) of the DB. PAI`s review formally began on April 13. PAI performed the CA, provided three sets of findings to the SNFP contractor, and initiated reconciliation meetings. During the course of PAI`s review, DOE directed the SNFP to develop a new baseline with a higher probability of success. The contractor transmitted the new baseline, which is referred to as the High Probability Baseline (HPB), to DOE on April 15, 1998 [Williams, 1998]. The HPB was estimated to approach a 90% confidence level on the start of fuel movement [Williams, 1998]. This high probability resulted in an increased cost and a schedule extension. To implement the new baseline, the contractor initiated 26 BCRs with supporting BOES. PAI`s scope was revised on April 28 to add reviewing the HPB and the associated BCRs and BOES.

  3. Table 1. Updated estimates of power plant capital and operating costs

    U.S. Energy Information Administration (EIA) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere IRaghuraji Agro IndustriesTownDells,1Stocks Nov-14 Dec-14TableConference |6:Welcome toU.S.

  4. Estimated groundwater restoration costs associated with commercial underground coal gasification operations. Topical report

    SciTech Connect (OSTI)

    Fischer, D.D.

    1985-12-17T23:59:59.000Z

    The objective of this program was to complete a preliminary cost estimate for groundwater restoration for the Hoe Creek commercial underground coal gasification (UCG) facility under a set of ground rules based on field data measurements and specific compound removal requirements. Of the three approaches evaluated for disposal of the contaminated groundwater, deep well injection is the least expensive, followed by the alternate treatment approach.

  5. Equipment Design and Cost Estimation for Small Modular Biomass Systems, Synthesis Gas Cleanup, and Oxygen Separation Equipment; Task 2: Gas Cleanup Design and Cost Estimates -- Black Liquor Gasification

    SciTech Connect (OSTI)

    Nexant Inc.

    2006-05-01T23:59:59.000Z

    As part of Task 2, Gas Cleanup and Cost Estimates, Nexant investigated the appropriate process scheme for removal of acid gases from black liquor-derived syngas for use in both power and liquid fuels synthesis. Two 3,200 metric tonne per day gasification schemes, both low-temperature/low-pressure (1100 deg F, 40 psi) and high-temperature/high-pressure (1800 deg F, 500 psi) were used for syngas production. Initial syngas conditions from each of the gasifiers was provided to the team by the National Renewable Energy Laboratory and Princeton University. Nexant was the prime contractor and principal investigator during this task; technical assistance was provided by both GTI and Emery Energy.

  6. Methodological Approaches for Estimating the Benefits and Costs of Smart Grid Demonstration Projects

    SciTech Connect (OSTI)

    Lee, Russell [ORNL

    2010-01-01T23:59:59.000Z

    This report presents a comprehensive framework for estimating the benefits and costs of Smart Grid projects and a step-by-step approach for making these estimates. The framework identifies the basic categories of benefits, the beneficiaries of these benefits, and the Smart Grid functionalities that lead to different benefits and proposes ways to estimate these benefits, including their monetization. The report covers cost-effectiveness evaluation, uncertainty, and issues in estimating baseline conditions against which a project would be compared. The report also suggests metrics suitable for describing principal characteristics of a modern Smart Grid to which a project can contribute. This first section of the report presents background information on the motivation for the report and its purpose. Section 2 introduces the methodological framework, focusing on the definition of benefits and a sequential, logical process for estimating them. Beginning with the Smart Grid technologies and functions of a project, it maps these functions to the benefits they produce. Section 3 provides a hypothetical example to illustrate the approach. Section 4 describes each of the 10 steps in the approach. Section 5 covers issues related to estimating benefits of the Smart Grid. Section 6 summarizes the next steps. The methods developed in this study will help improve future estimates - both retrospective and prospective - of the benefits of Smart Grid investments. These benefits, including those to consumers, society in general, and utilities, can then be weighed against the investments. Such methods would be useful in total resource cost tests and in societal versions of such tests. As such, the report will be of interest not only to electric utilities, but also to a broad constituency of stakeholders. Significant aspects of the methodology were used by the U.S. Department of Energy (DOE) to develop its methods for estimating the benefits and costs of its renewable and distributed systems integration demonstration projects as well as its Smart Grid Investment Grant projects and demonstration projects funded under the American Recovery and Reinvestment Act (ARRA). The goal of this report, which was cofunded by the Electric Power Research Institute (EPRI) and DOE, is to present a comprehensive set of methods for estimating the benefits and costs of Smart Grid projects. By publishing this report, EPRI seeks to contribute to the development of methods that will establish the benefits associated with investments in Smart Grid technologies. EPRI does not endorse the contents of this report or make any representations as to the accuracy and appropriateness of its contents. The purpose of this report is to present a methodological framework that will provide a standardized approach for estimating the benefits and costs of Smart Grid demonstration projects. The framework also has broader application to larger projects, such as those funded under the ARRA. Moreover, with additional development, it will provide the means for extrapolating the results of pilots and trials to at-scale investments in Smart Grid technologies. The framework was developed by a panel whose members provided a broad range of expertise.

  7. Use of experience curves to estimate the future cost of power plants with CO2 capture

    E-Print Network [OSTI]

    Rubin, Edward S.; Yeh, Sonia; Antes, Matt; Berkenpas, Michael; Davison, John

    2007-01-01T23:59:59.000Z

    and storage costs) Technology Cost of electricity (excludingstages of commercialization Technology Capital cost Flue gasPlant type and technology Capital cost $/kW NGCC plant

  8. Estimates of Energy Cost Savings Achieved from 2009 IECC Code-Compliant, Single Family Residences in Texas

    E-Print Network [OSTI]

    Kim, H.; Baltazar, J. C.; Haberl, J.

    The annual energy cost savings were estimated with $0.11/kWh for electricity and $0.84/therm (Climate Zone 2) and $0.64/therm (Climate Zone 3 and 4) for natural gas. 2009 IECC Cost Savings Report, p.ii January 2011 Energy Systems Laboratory, Texas A...). 3.2 Annual Total Energy Cost Similar trends were observed in the annual energy costs estimated with $0.11/kWh for electricity and $0.84/therm (Climate Zone 2) and $0.64/therm (Climate Zone 3 and 4) for natural gas. Across the counties, the 2001...

  9. Hydrogen Pathways: Updated Cost, Well-to-Wheels Energy Use, and Emissions for the Current Technology Status of Ten Hydrogen Production, Delivery, and Distribution Scenarios

    SciTech Connect (OSTI)

    Ramsden, T.; Ruth, M.; Diakov, V.; Laffen, M.; Timbario, T. A.

    2013-03-01T23:59:59.000Z

    This report describes a life-cycle assessment conducted by the National Renewable Energy Laboratory (NREL) of 10 hydrogen production, delivery, dispensing, and use pathways that were evaluated for cost, energy use, and greenhouse gas (GHG) emissions. This evaluation updates and expands on a previous assessment of seven pathways conducted in 2009. This study summarizes key results, parameters, and sensitivities to those parameters for the 10 hydrogen pathways, reporting on the levelized cost of hydrogen in 2007 U.S. dollars as well as life-cycle well-to-wheels energy use and GHG emissions associated with the pathways.

  10. Design Study and Cost Estimate for an Assurred Isolation Facility in Texas

    SciTech Connect (OSTI)

    Baird, R. D.; Rogers, B. C.; Chau, N.; Kerr, Thomas A

    1999-08-01T23:59:59.000Z

    The optimized assured isolation facility (AIF) consists of waste shipping containers being placed inside steel-reinforced concrete overpacks, which are, in turn, placed in steel-reinforced concrete vaults without an earthen cover system. The concrete vaults are designed to remain in service for hundreds of years, with the aid of ongoing active maintenance. This will be required since the facility will remain under license as long as waste is present in the facility. The estimated present value of life-cycle costs total about $318 million. Of this amount, over 30 percent is attributable to the need to accumulate the financial assurance fund which allows future management options to be implemented. The charge for waste received at the AIF in order to recover all costs and ensure proper facility function following the waste acceptance period was calculated for each year of AIF operation, considering annual variations in the volume received and the costs that must be recovered. The present value of the AID unit charges range for $84 to $420 per cubic foot with a life-cycle average of about $177 per cubic foot. When making decisions on cost factors and comparing alternatives, the lifetime average of $177 per cubic foot is most meaningful.

  11. Cost and energy consumption estimates for the aluminum-air battery anode fuel cycle

    SciTech Connect (OSTI)

    Humphreys, K.K.; Brown, D.R.

    1990-01-01T23:59:59.000Z

    At the request of DOE's Office of Energy Storage and Distribution (OESD), Pacific Northwest Laboratory (PNL) conducted a study to generate estimates of the energy use and costs associated with the aluminum anode fuel cycle of the aluminum-air (Al-air) battery. The results of this analysis indicate that the cost and energy consumption characteristics of the mechanically rechargeable Al-air battery system are not as attractive as some other electrically rechargeable electric vehicle battery systems being developed by OESD. However, there are distinct advantages to mechanically rechargeable batteries, which may make the Al-air battery (or other mechanically rechargeable batteries) attractive for other uses, such as stand-alone applications. Fuel cells, such as the proton exchange membrane (PEM), and advanced secondary batteries may be better suited to electric vehicle applications. 26 refs., 3 figs., 25 tabs.

  12. AREA COST FACTOR INDEXES PAX NEWSLETTER NO. 3.2.1

    E-Print Network [OSTI]

    US Army Corps of Engineers

    in the continental US). The ACF index is the combination factors of local construction costs of labor, materialAREA COST FACTOR INDEXES PAX NEWSLETTER NO. 3.2.1 2 January 2003 1. The attached updated area cost technical manual TM 5-800-4, Programming Cost Estimates for Military Construction, dated May 1994

  13. AREA COST FACTOR INDEXES PAX NEWSLETTER NO. 3.2.1

    E-Print Network [OSTI]

    US Army Corps of Engineers

    in the continental US). The ACF index is the combination factors of local construction costs of labor, material1 AREA COST FACTOR INDEXES PAX NEWSLETTER NO. 3.2.1 10 April 2001 1. The attached updated area cost technical manual TM 5-800-4, Programming Cost Estimates for Military Construction, dated May 1994

  14. AREA COST FACTOR INDEXES PAX NEWSLETTER NO. 3.2.1

    E-Print Network [OSTI]

    US Army Corps of Engineers

    in the continental US). The ACF index is the combination factors of local construction costs of labor, materialAREA COST FACTOR INDEXES PAX NEWSLETTER NO. 3.2.1 10 March 2000 1. The attached updated area cost technical manual TM 5-800-4, Programming Cost Estimates for Military Construction, dated May 1994

  15. Hanford ETR- Tank Waste Treatment and Immobilization Plant- Hanford Tank Waste Treatment and Immobilization Plant Technical Review- Estimate at Completion (Cost) Report

    Broader source: Energy.gov [DOE]

    This is a comprehensive review ofthe Hanford WTP estimate at completion - assessing the project scope, contract requirements, management execution plant, schedule, cost estimates, and risks.

  16. Estimation of costs for applications of remediation technologies for the Department of Energy`s Programmatic Environmental Impact Statement

    SciTech Connect (OSTI)

    Villegas, A.J.; Hansen, R.I.; Humphreys, K.K.; Paananen, J.M.; Gildea, L.F.

    1994-03-01T23:59:59.000Z

    The Programmatic Environmental impact Statement (PEIS) being developed by the US Department of Energy (DOE) for environmental restoration (ER) and waste management (WM) activities expected to be carried out across the DOE`s nationwide complex of facilities is assessing the impacts of removing, transporting, treating, storing, and disposing of waste from these ER and WM activities. Factors being considered include health and safety impacts to the public and to workers, impacts on the environment, costs and socio-economic impacts, and near-term and residual risk during those ER and WM operations. The purpose of this paper is to discuss the methodology developed specifically for the PEIS to estimate costs associated with the deployment and application of individual remediation technologies. These individual costs are used in developing order-of-magnitude cost estimates for the total remediation activities. Costs are developed on a per-unit-of-material-to-be-treated basis (i.e., $/m{sup 3}) to accommodate remediation projects of varying sizes. The primary focus of this cost-estimating effort was the development of capital and operating unit cost factors based on the amount of primary media to be removed, handled, and treated. The unit costs for individual treatment technologies were developed using information from a variety of sources, mainly from periodicals, EPA documentation, handbooks, vendor contacts, and cost models. The unit cost factors for individual technologies were adjusted to 1991 dollars.

  17. Enhance accuracy in Software cost and schedule estimation by using "Uncertainty Analysis and Assessment" in the system modeling process

    E-Print Network [OSTI]

    Vasantrao, Kardile Vilas

    2011-01-01T23:59:59.000Z

    Accurate software cost and schedule estimation are essential for software project success. Often it referred to as the "black art" because of its complexity and uncertainty, software estimation is not as difficult or puzzling as people think. In fact, generating accurate estimates is straightforward-once you understand the intensity of uncertainty and framework for the modeling process. The mystery to successful software estimation-distilling academic information and real-world experience into a practical guide for working software professionals. Instead of arcane treatises and rigid modeling techniques, this will guide highlights a proven set of procedures, understandable formulas, and heuristics that individuals and development teams can apply to their projects to help achieve estimation proficiency with choose appropriate development approaches In the early stage of software life cycle project manager are inefficient to estimate the effort, schedule, cost estimation and its development approach .This in tu...

  18. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    in calculating the unit cost of wind energy transmissionimpacts of the cost of transmission for wind energy. Only inj = Transmission cost per unit of wind energy weighted by

  19. Validating the Estimated Cost of Saving Water Through Infrastructure Rehabilitation in the Texas Lower Rio Grande Valley 

    E-Print Network [OSTI]

    Sturdivant, A.; Rister, M.; Lacewell, R.

    2007-01-01T23:59:59.000Z

    SR- 2007-06 Validating the Estimated Cost of Saving Water Through Infrastructure Rehabilitation in the Texas Lower Rio Grande Valley A Case Study Using Actual Construction Costs for the Main Pipeline, Brownsville Irrigation... Grande Valley A Case Study Using Actual Construction Costs for the Main Pipeline, Brownsville Irrigation District by: Allen W. Sturdivant; Extension Associate 1, 2 M. Edward Rister; Professor and Associate Head 1, 3 Ronald D. Lacewell; Professor...

  20. update: Species–area curves and the estimation of extinction rates

    E-Print Network [OSTI]

    Beck, Jan

    2011-01-01T23:59:59.000Z

    2011)  Extinctions:  consider  all  species.   Nature, 474, Species–area  relationships  always overestimate extinction and the estimation of extinction rates  The  species–area 

  1. Cost estimation of HVDC transmission system of Bangka’s NPP candidates

    SciTech Connect (OSTI)

    Liun, Edwaren, E-mail: edwaren@batan.go.id; Suparman, E-mail: edwaren@batan.go.id [Centre for Nuclear Energy Development, National Nuclear Energy Agency of Indonesia (Indonesia)

    2014-09-30T23:59:59.000Z

    Regarding nuclear power plant development in Bangka Island, it can be estimated that produced power will be oversupply for the Bangka Island and needs to transmit to Sumatra or Java Island. The distance between the regions or islands causing considerable loss of power in transmission by alternating current, and a wide range of technical and economical issues. The objective of this paper addresses to economics analysis of direct current transmission system to overcome those technical problem. Direct current transmission has a stable characteristic, so that the power delivery from Bangka to Sumatra or Java in a large scale efficiently and reliably can be done. HVDC system costs depend on the power capacity applied to the system and length of the transmission line in addition to other variables that may be different.

  2. Risk information in support of cost estimates for the Baseline Environmental Management Report (BEMR). Section 1

    SciTech Connect (OSTI)

    Gelston, G.M.; Jarvis, M.F.; Warren, B.R. [Pacific Northwest Lab., Richland, WA (United States); Von Berg, R. [ICF Kaiser Engineers, Inc., Oakland, CA (United States)

    1995-06-01T23:59:59.000Z

    The Pacific Northwest Laboratory (PNL)(1) effort on the overall Baseline Environmental Management Report (BEMR) project consists of four installation-specific work components performed in succession. These components include (1) development of source terms, 92) collection of data and preparation of environmental settings reports, (3) calculation of unit risk factors, and (4) utilization of the unit risk factors in Automated Remedial Action Methodology (ARAM) for computation of target concentrations and cost estimates. This report documents work completed for the Nevada Test Site, Nevada, for components 2 and 3. The product of this phase of the BEMR project is the development of unit factors (i.e., unit transport factors, unit exposure factors, and unit risk factors). Thousands of these unit factors are gene rated and fill approximately one megabyte of computer information per installation. The final unit risk factors (URF) are transmitted electronically to BEMR-Cost task personnel as input to a computer program (ARAM). Abstracted files and exhibits of the URF information are included in this report. These visual formats are intended to provide a sample of the final task deliverable (the URF files) which can be easily read without a computer.

  3. Solid Waste Operations Complex W-113, Detail Design Report (Title II). Volume 4: Project cost estimate

    SciTech Connect (OSTI)

    NONE

    1995-09-01T23:59:59.000Z

    The Solid Waste Retrieval Facility--Phase 1 (Project W113) will provide the infrastructure and the facility required to retrieve from Trench 04, Burial ground 4C, contact handled (CH) drums and boxes at a rate that supports all retrieved TRU waste batching, treatment, storage, and disposal plans. This includes (1) operations related equipment and facilities, viz., a weather enclosure for the trench, retrieval equipment, weighing, venting, obtaining gas samples, overpacking, NDE, NDA, shipment of waste and (2) operations support related facilities, viz., a general office building, a retrieval staff change facility, and infrastructure upgrades such as supply and routing of water, sewer, electrical power, fire protection, roads, and telecommunication. Title I design for the operations related equipment and facilities was performed by Raytheon/BNFL, and that for the operations support related facilities including infrastructure upgrade was performed by KEH. These two scopes were combined into an integrated W113 Title II scope that was performed by Raytheon/BNFL. This volume represents the total estimated costs for the W113 facility. Operating Contractor Management costs have been incorporated as received from WHC. The W113 Facility TEC is $19.7 million. This includes an overall project contingency of 14.4% and escalation of 17.4%. A January 2001 construction contract procurement start date is assumed.

  4. DOE TASK 99-5 Update REFINEMENT AND VALIDATION OF IN SITU PARAMETER ESTIMATION

    E-Print Network [OSTI]

    and Aerospace Engineering Stillwater, OK KEY WORDS geothermal energy, ground coupled, heat pump, heat exchanger facing designers of Ground Source Heat Pump (GSHP) systems applied in commercial, institutional as well as large residential buildings. The number of boreholes and the depth and cost of each borehole are highly

  5. Development of Decision Support Software to Estimate the Cost of Transporting and Ginning of Seed Cotton

    E-Print Network [OSTI]

    Grier, Jordan Lee

    2014-08-13T23:59:59.000Z

    transportation model produced in 2009 is being updated to reflect current economic conditions. This paper explains how non-conventional module types were incorporated into the transportation calculator to aid cotton ginners and producers in making sound...

  6. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    Contingency Analysis Cost Model Flow Analysis Non-Wind Windthe cost of transmission for wind through a meta-analysis ofanalysis in Section 4. Although the results focus on the unit cost of wind

  7. Updated estimation of energy efficiencies of U.S. petroleum refineries.

    SciTech Connect (OSTI)

    Palou-Rivera, I.; Wang, M. Q. (Energy Systems)

    2010-12-08T23:59:59.000Z

    Evaluation of life-cycle (or well-to-wheels, WTW) energy and emission impacts of vehicle/fuel systems requires energy use (or energy efficiencies) of energy processing or conversion activities. In most such studies, petroleum fuels are included. Thus, determination of energy efficiencies of petroleum refineries becomes a necessary step for life-cycle analyses of vehicle/fuel systems. Petroleum refinery energy efficiencies can then be used to determine the total amount of process energy use for refinery operation. Furthermore, since refineries produce multiple products, allocation of energy use and emissions associated with petroleum refineries to various petroleum products is needed for WTW analysis of individual fuels such as gasoline and diesel. In particular, GREET, the life-cycle model developed at Argonne National Laboratory with DOE sponsorship, compares energy use and emissions of various transportation fuels including gasoline and diesel. Energy use in petroleum refineries is key components of well-to-pump (WTP) energy use and emissions of gasoline and diesel. In GREET, petroleum refinery overall energy efficiencies are used to determine petroleum product specific energy efficiencies. Argonne has developed petroleum refining efficiencies from LP simulations of petroleum refineries and EIA survey data of petroleum refineries up to 2006 (see Wang, 2008). This memo documents Argonne's most recent update of petroleum refining efficiencies.

  8. Cost Analysis of Fuel Cell Systems for Transportation

    E-Print Network [OSTI]

    Cost Analysis of Fuel Cell Systems for Transportation Compressed Hydrogen and PEM Fuel Cell System Discussion Fuel Cell Tech Team FreedomCar Detroit. MI October 20, 2004 TIAX LLC Acorn Park Cambridge Estimates Task 3: Identify Opportunities for System Cost Reduction Tasks 4, 5, 6 & 7: Annual Updates Develop

  9. AREA COST FACTOR INDEXES PAX NEWSLETTER NO. 3.2.1

    E-Print Network [OSTI]

    US Army Corps of Engineers

    in the continental US). The ACF index is the combination factors of local construction costs of labor, materialAREA COST FACTOR INDEXES PAX NEWSLETTER NO. 3.2.1 15 December 2003 1. The attached updated area of the Army technical manual TM 5-800-4, Programming Cost Estimates for Military Construction, dated May 1994

  10. Testing the normality of the gravitational wave data with a low cost recursive estimate of the kurtosis

    E-Print Network [OSTI]

    E. Chassande-Mottin

    2002-12-02T23:59:59.000Z

    We propose a monitoring indicator of the normality of the output of a gravitational wave detector. This indicator is based on the estimation of the kurtosis (i.e., the 4th order statistical moment normalized by the variance squared) of the data selected in a time sliding window. We show how a low cost (because recursive) implementation of such estimation is possible and we illustrate the validity of the presented approach with a few examples using simulated random noises.

  11. Cost and U.S. public policy for new coal power plants with carbon capture and sequestration

    E-Print Network [OSTI]

    Hamilton, Michael R.

    This paper provides a financial analysis for new supercritical pulverized coal plants with carbon capture and sequestration (CCS) that compares the effects of two relevant climate policies. First, an updated cost estimate ...

  12. Estimating the variable cost for high-volume and long-haul transportation of densified biomass and biofuel

    SciTech Connect (OSTI)

    Jacob J. Jacobson; Erin Searcy; Md. S. Roni; Sandra D. Eksioglu

    2014-06-01T23:59:59.000Z

    This article analyzes rail transportation costs of products that have similar physical properties as densified biomass and biofuel. The results of this cost analysis are useful to understand the relationship and quantify the impact of a number of factors on rail transportation costs of denisfied biomass and biofuel. These results will be beneficial and help evaluate the economic feasibility of high-volume and long-haul transportation of biomass and biofuel. High-volume and long-haul rail transportation of biomass is a viable transportation option for biofuel plants, and for coal plants which consider biomass co-firing. Using rail optimizes costs, and optimizes greenhouse gas (GHG) emissions due to transportation. Increasing bioenergy production would consequently result in lower GHG emissions due to displacing fossil fuels. To estimate rail transportation costs we use the carload waybill data, provided by Department of Transportation’s Surface Transportation Board for products such as grain and liquid type commodities for 2009 and 2011. We used regression analysis to quantify the relationship between variable transportation unit cost ($/ton) and car type, shipment size, rail movement type, commodity type, etc. The results indicate that: (a) transportation costs for liquid is $2.26/ton–$5.45/ton higher than grain type commodity; (b) transportation costs in 2011 were $1.68/ton–$5.59/ton higher than 2009; (c) transportation costs for single car shipments are $3.6/ton–$6.68/ton higher than transportation costs for multiple car shipments of grains; (d) transportation costs for multiple car shipments are $8.9/ton and $17.15/ton higher than transportation costs for unit train shipments of grains.

  13. Rough order of magnitude cost estimate for immobilization of 50MT of plutonium using new faciliites at the Savannah River site: alternative 12A

    SciTech Connect (OSTI)

    DiSabatino, A., LLNL

    1998-06-01T23:59:59.000Z

    The purpose of this Cost Estimate Report is to identify preliminary capital and operating costs for a facility to immobilize 50 metric tons of plutonium using ceramic in a new facility at Savannah River Site (SRS).

  14. Rough order of magnitude cost estimate for immobilization of 50 MT of plutonium using existing facilities at the Savannah River site: alternative 12B

    SciTech Connect (OSTI)

    DiSabatino, A., LLNL

    1998-06-01T23:59:59.000Z

    The purpose of this Cost Estimate Report is to identify preliminary capital and operating costs for a facility to immobilize 50 metric tons of plutonium using ceramic in an existing facility (221-F) at an Savannah River Site (SRS).

  15. Improving the parametric method of cost estimating relationships of naval ships

    E-Print Network [OSTI]

    Lee, Ungtae (Jeremy Ungtae)

    2014-01-01T23:59:59.000Z

    In light of recent military budget cuts, there has been a recent focus on determining methods to reduce the cost of Navy ships. A RAND National Defense Research Institute study showed many sources of cost escalation for ...

  16. Mass Production Cost Estimation for Direct H2 PEM Fuel Cell Systems...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    technology * 2015 projected technology 2 Determine costs for these 3 tech level Fuel Cell System Battery System Storage 2. Determine costs for these 3 tech level systems at 5...

  17. Current (2009) State-of-the-Art Hydrogen Production Cost Estimate Using Water Electrolysis

    Fuel Cell Technologies Publication and Product Library (EERE)

    This independent review examines DOE cost targets for state-of-the art hydrogen production using water electrolysis.

  18. Current (2009) State-of-the-Art Hydrogen Production Cost Estimate Using Water Electrolysis: Independent Review

    SciTech Connect (OSTI)

    Not Available

    2009-09-01T23:59:59.000Z

    This independent review examines DOE cost targets for state-of-the art hydrogen production using water electrolysis.

  19. Repository of NSF Funded Publications and Data Sets: "Back of Envelope" 15 year Cost Estimate

    E-Print Network [OSTI]

    Plale, Beth

    Repository of NSF Funded Publications and Data Sets: "Back of Envelope" 15 year Cost and variable costs of setting up and running a data repository (or database) to store and serve for rapid access, and tape for high reliability and cost efficient long-term storage. Data are ingested

  20. Costs and Benefits of Renewables Portfolio Standards in the United States

    E-Print Network [OSTI]

    Barbose, Galen

    2014-01-01T23:59:59.000Z

    Interagency Working Group on Social Cost of Carbon (2013).Technical Update of the Social Cost of Carbon for Regulatorytechnical-update-social-cost-of-carbon-for-regulator-

  1. The Costs and Benefits of Compliance with Renewable Portfolio Standards: Reviewing Experience to Date

    E-Print Network [OSTI]

    Heeter, Jenny

    2014-01-01T23:59:59.000Z

    Interagency Working Group on Social Cost of Carbon (2013).Technical Update of the Social Cost of Carbon for Regulatorytechnical-update-social-cost-of-carbon- for-regulator-

  2. Operating Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    This chapter is focused on capital costs for conventional construction and environmental restoration and waste management projects and examines operating cost estimates to verify that all elements of the project have been considered and properly estimated.

  3. Cost Estimating for Decommissioning of a Plutonium Facility--Lessons Learned From The Rocky Flats Building 771 Project

    SciTech Connect (OSTI)

    Stevens, J. L.; Titus, R.; Sanford, P. C.

    2002-02-26T23:59:59.000Z

    The Rocky Flats Closure Site is implementing an aggressive approach in an attempt to complete Site closure by 2006. The replanning effort to meet this goal required that the life-cycle decommissioning effort for the Site and for the major individual facilities be reexamined in detail. As part of the overall effort, the cost estimate for the Building 771 decommissioning project was revised to incorporate both actual cost data from a recently-completed similar project and detailed planning for all activities. This paper provides a brief overview of the replanning process and the original estimate, and then discusses the modifications to that estimate to reflect new data, methods, and planning rigor. It provides the new work breakdown structure and discusses the reasons for the final arrangement chosen. It follows with the process used to assign scope, cost, and schedule elements within the new structure, and development of the new code of accounts. Finally, it describes the project control methodology used to track the project, and provides lessons learned on cost tracking in the decommissioning environment.

  4. Cost estimate and economic issues associated with the MOX option (prior to DOE`s record of decision)

    SciTech Connect (OSTI)

    Reid, R.L.; Miller, J.W.

    1997-04-01T23:59:59.000Z

    Before the January 1997 Record of Decision (ROD), the U.S. Department of Energy Office of Fissile Materials Disposition (DOE-MD) evaluated three technologies for the disposition of {approximately}50 MT of surplus plutonium from defense-related programs-reactors, immobilization, and deep boreholes. As part of the process supporting the ROD, and comprehensive assessment of technical viability, cost, and schedule was conducted by DOE-MD and its national laboratory contractors. Oak Ridge National Laboratory managed and coordinated the life-cycle cost (LCC) assessment effort for this program. This report discusses the economic analysis methodology and the results for the reactor options considered prior to ROD. A secondary intent of the report is to discuss major technical and economic issues that impact cost and schedule. To evaluate the economics of the reactor option and other technologies on an equitable basis, a set of cost-estimating guidelines and a common cost-estimating format were utilized by all three technology teams. This report includes the major economic analysis assumptions and the comparative constant-dollar and discounted-dollar LCCs for all nine reactor scenarios.

  5. A SURVEY OF STATE-LEVEL COST ESTIMATES OF RENEWABLES PORTFOLIO STANDARDS

    E-Print Network [OSTI]

    Barbose, Galen

    2014-01-01T23:59:59.000Z

    Energy Efficiency and Renewable Energy (Solar TechnologiesRPS costs, per unit of renewable energy generation, rangedFlores-Espino National Renewable Energy Laboratory 15013

  6. Program Potential: Estimates of Federal Energy Cost Savings from Energy Efficient Procurement

    E-Print Network [OSTI]

    Taylor, Margaret

    2014-01-01T23:59:59.000Z

    Water Heaters ..Table 7: Annual energy and cost savings of water heaters (Boilers Commercial Water Heater See Appendix F for

  7. Use of experience curves to estimate the future cost of power plants with CO2 capture

    E-Print Network [OSTI]

    Rubin, Edward S.; Yeh, Sonia; Antes, Matt; Berkenpas, Michael; Davison, John

    2007-01-01T23:59:59.000Z

    2004. Experience curves for power plant emission controlassessments of fossil fuel power plants with CO 2 capturethe future cost of power plants with CO 2 capture Edward S.

  8. Comparing Life-Cycle Costs of ESPCs and Appropriations-Funded Energy Projects: An Update to the 2002 Report

    SciTech Connect (OSTI)

    Shonder, John A [ORNL; Hughes, Patrick [ORNL; Atkin, Erica [ORNL

    2006-11-01T23:59:59.000Z

    A study was sponsored by FEMP in 2001 - 2002 to develop methods to compare life-cycle costs of federal energy conservation projects carried out through energy savings performance contracts (ESPCs) and projects that are directly funded by appropriations. The study described in this report follows up on the original work, taking advantage of new pricing data on equipment and on $500 million worth of Super ESPC projects awarded since the end of FY 2001. The methods developed to compare life-cycle costs of ESPCs and directly funded energy projects are based on the following tasks: (1) Verify the parity of equipment prices in ESPC vs. directly funded projects; (2) Develop a representative energy conservation project; (3) Determine representative cycle times for both ESPCs and appropriations-funded projects; (4) Model the representative energy project implemented through an ESPC and through appropriations funding; and (5) Calculate the life-cycle costs for each project.

  9. MRS/IS facility co-located with a repository: preconceptual design and life-cycle cost estimates

    SciTech Connect (OSTI)

    Smith, R.I.; Nesbitt, J.F.

    1982-11-01T23:59:59.000Z

    A program is described to examine the various alternatives for monitored retrievable storage (MRS) and interim storage (IS) of spent nuclear fuel, solidified high-level waste (HLW), and transuranic (TRU) waste until appropriate geologic repository/repositories are available. The objectives of this study are: (1) to develop a preconceptual design for an MRS/IS facility that would become the principal surface facility for a deep geologic repository when the repository is opened, (2) to examine various issues such as transportation of wastes, licensing of the facility, and environmental concerns associated with operation of such a facility, and (3) to estimate the life cycle costs of the facility when operated in response to a set of scenarios which define the quantities and types of waste requiring storage in specific time periods, which generally span the years from 1990 until 2016. The life cycle costs estimated in this study include: the capital expenditures for structures, casks and/or drywells, storage areas and pads, and transfer equipment; the cost of staff labor, supplies, and services; and the incremental cost of transporting the waste materials from the site of origin to the MRS/IS facility. Three scenarios are examined to develop estimates of life cycle costs of the MRS/IS facility. In the first scenario, HLW canisters are stored, starting in 1990, until the co-located repository is opened in the year 1998. Additional reprocessing plants and repositories are placed in service at various intervals. In the second scenario, spent fuel is stored, starting in 1990, because the reprocessing plants are delayed in starting operations by 10 years, but no HLW is stored because the repositories open on schedule. In the third scenario, HLW is stored, starting in 1990, because the repositories are delayed 10 years, but the reprocessing plants open on schedule.

  10. Validating the Estimated Cost of Saving Water Through Infrastructure Rehabilitation in the Texas Lower Rio Grande Valley

    E-Print Network [OSTI]

    Sturdivant, A.; Rister, M.; Lacewell, R.

    As shown in Table 1, the original estimated initial capital construction costs totaled $2,356,000, with the revised, actual value being $2,504,435 (Balcombe). The installation period was projected to take (and remained at) one year, with an ensuing... uncertainty and multiple analyses are an underlying theme and related inference that consistent and attentive methods of analysis, such as those documented in Rister et al. 2002, are warranted. References Balcombe, Collins. Director, Special Projects, U...

  11. A conceptual model to estimate cost effectiveness of the indoor environment improvements

    SciTech Connect (OSTI)

    Seppanen, Olli; Fisk, William J.

    2003-06-01T23:59:59.000Z

    Macroeconomic analyses indicate a high cost to society of a deteriorated indoor climate. The few example calculations performed to date indicate that measures taken to improve IEQ are highly cost-effective when health and productivity benefits are considered. We believe that cost-benefit analyses of building designs and operations should routinely incorporate health and productivity impacts. As an initial step, we developed a conceptual model that shows the links between improvements in IEQ and the financial gains from reductions in medical care and sick leave, improved work performance, lower employee turn over, and reduced maintenance due to fewer complaints.

  12. The impact of trade costs on rare earth exports : a stochastic frontier estimation approach.

    SciTech Connect (OSTI)

    Sanyal, Prabuddha; Brady, Patrick Vane; Vugrin, Eric D.

    2013-09-01T23:59:59.000Z

    The study develops a novel stochastic frontier modeling approach to the gravity equation for rare earth element (REE) trade between China and its trading partners between 2001 and 2009. The novelty lies in differentiating betweenbehind the border' trade costs by China and theimplicit beyond the border costs' of China's trading partners. Results indicate that the significance level of the independent variables change dramatically over the time period. While geographical distance matters for trade flows in both periods, the effect of income on trade flows is significantly attenuated, possibly capturing the negative effects of financial crises in the developed world. Second, the total export losses due tobehind the border' trade costs almost tripled over the time period. Finally, looking atimplicit beyond the border' trade costs, results show China gaining in some markets, although it is likely that some countries are substituting away from Chinese REE exports.

  13. Electric Power Interruption Cost Estimates for Individual Industries, Sectors, and the U.S. Economy

    E-Print Network [OSTI]

    Balducci, P. J.; Roop, J. M.; Schienbein, L. A.; DeSteese, J. G.; Weimar, M. R.

    Distributed energy resources (DER) have been promoted as the least-cost approach to meeting steadily increasing energy demand. However, it is unclear whether DER deployment can maintain or improve the electric power supply reliability and quality...

  14. Utilizing an encroachment probability benefit-cost model to estimate accident reduction factors

    E-Print Network [OSTI]

    Hayes, Carolyn A

    1997-01-01T23:59:59.000Z

    Improving safety on Texas roadways is a major public concern. Over the years, the Texas Department of Transportation and other highway agencies have become interested in reducing society's accident cost while maximizing returns on accident...

  15. Estimating Marginal Cost of Quality Improvements: The Case of the UK Electricity Distribution Companies

    E-Print Network [OSTI]

    Jamasb, Tooraj; Orea, Luis; Pollitt, Michael G.

    of operational and capital expenditures (Totex) as the dependent variable. Improving quality of services involves operating cost (Opex) and capital cost (Capex) for the utilities. Due to the presence of possible trade-offs between Opex and Capex (Giannakis et... saving Opex than by an equal amount of Capex reduction (Ofgem, 2003a). Hence, in order to examine existence of different strategies in the UK utilities to improve quality, and to ascertain whether the current regulation has distorted the allocation...

  16. Letters of Interest PRICE/COST Estimate Sheet for [Insert LOI...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    (Typed Name) NREL Form (10-5-2000) Letters of Interest PRICECOST Estimate Sheet for Description Base Year Phase Option Year I Phase Option Year II...

  17. Electric Power Interruption Cost Estimates for Individual Industries, Sectors, and U.S. Economy

    SciTech Connect (OSTI)

    Balducci, Patrick J.; Roop, Joseph M.; Schienbein, Lawrence A.; DeSteese, John G.; Weimar, Mark R.

    2002-02-27T23:59:59.000Z

    During the last 20 years, utilities and researchers have begun to understand the value in the collection and analysis of interruption cost data. The continued investigation of the monetary impact of power outages will facilitate the advancement of the analytical methods used to measure the costs and benefits from the perspective of the energy consumer. More in-depth analysis may be warranted because of the privatization and deregulation of power utilities, price instability in certain regions of the U.S. and the continued evolution of alternative auxiliary power systems.

  18. Estimated Costs and Returns for Catfish Farms with Recirculating Ponds Along the Upper Texas Coast.

    E-Print Network [OSTI]

    Lambregts, J.A.D.; Griffin, W.L.; Lacewell R.D.; Davis, J.T.; Clary, G.M.

    1992-01-01T23:59:59.000Z

    . Hypothetical farms using the modified recirculating system are studied. Three farm sizes are cost engi neered and evaluated, a small farm with 66 (163) total land ha (ac), a medium farm with 132 (323), and a large farm with 264 (643). The farms are analyzed... with a farm-level simulation program (CATSIM) to determine costs, returns, and economies of scale of catfish farm ing. Production of the catfish ponds is set at 11,227 kg per ha (10,000 lb per ac) when the ponds are in full production, with an annual...

  19. Supercritical Pulverized Coal and Integrated Gasification Combined Cycle Partial CO2 Capture Cases - Updated Performance and Cost Effects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What'sis Taking Over Our InstagramStructure of All-Polymer.SupercomputingSuperconductivity at DawnCost

  20. Estimating costs and benefits of advanced control for wastewater treatment plants the MAgIC

    E-Print Network [OSTI]

    Benchmarking; cost­benefit analysis; full-scale plant control; on-line process control; sensors Introduction plants. The effective coupling of the sensors to on-line control algorithms is now operational in 10 al., 2004). The methodology is designed such that the evaluation should be possible from existing

  1. Updated U.S. Geothermal Supply Characterization and Representation for Market Penetration Model Input

    SciTech Connect (OSTI)

    Augustine, C.

    2011-10-01T23:59:59.000Z

    The U.S. Department of Energy (DOE) Geothermal Technologies Program (GTP) tasked the National Renewable Energy Laboratory (NREL) with conducting the annual geothermal supply curve update. This report documents the approach taken to identify geothermal resources, determine the electrical producing potential of these resources, and estimate the levelized cost of electricity (LCOE), capital costs, and operating and maintenance costs from these geothermal resources at present and future timeframes under various GTP funding levels. Finally, this report discusses the resulting supply curve representation and how improvements can be made to future supply curve updates.

  2. Estimating the Market Penetration of Residential Cool Storage Technology Using Economic Cost Modeling

    E-Print Network [OSTI]

    Weijo, R. O.; and Brown, D. R.

    1988-01-01T23:59:59.000Z

    use, which occur on hot summer days for summer peaking utilities. Cool storage technology, developed for both commercial and residential applications, is one solution to meeting peak power needs. Demand for this technology is derived from... utilities' hesitancy to pay the extremely high-capacity costs (per kW) required to generate electricity for use at peak periods. This technology does not save energy--it merely shifts its use to a time when residential, commercial, and industrial demand...

  3. A computer solution for estimating owning and operating costs for over-the-road hauling units

    E-Print Network [OSTI]

    Wenners, Edward Bernard

    1972-01-01T23:59:59.000Z

    OF CONTENTS PAGE ABSTRACT ACKNOWLEDGEMENT S iv LIST OF TABLES LIST OF FIGURES vii ix CHAPTER I INTRODUCTION II OVER-THE-ROAD HAULING UNITS Characteristics Preliminary Purchase Investigation Vehicle Specifications Fuel Type Weight Restrictions... SIMULATION RUN III OUTPUT, SECOND SIMULATION RUN 88 101 113 VITA 125 yii LIST OF TABLES TABLE PAGE Major On-Highway Truck Manufacturers Gross Vehicle Weight (GVW) Components 10 12 3. (a) Fuel Costs Per Gallon 3. (b) Fuel Consumed Per Brake HP...

  4. Biological remediation of contaminated soils at Los Angeles Air Force Base: Facility design and engineering cost estimate

    SciTech Connect (OSTI)

    Montemagno, C.D.; Irvine, R.L.

    1990-08-01T23:59:59.000Z

    This report presents a system design for using bioremediation to treat contaminated soil at Fort MacArthur near Los Angeles, California. The soil was contaminated by petroleum products that leaked from two underground storage tanks. Laboratory studies indicated that, with the addition of water and nutrients, soil bacteria can reduce the petroleum content of the soils to levels that meet regulatory standards. The system design includes soil excavation, screening, and mixing; treatment in five soil-slurry/sequencing-batch reactors; and dewatering by a rapid-infiltration basin. System specifications and cost estimates are provided. 5 refs., 8 figs., 5 tabs.

  5. Validating the Estimated Cost of Saving Water Through Infrastructure Rehabilitation in the Texas Lower Rio Grande Valley

    E-Print Network [OSTI]

    Sturdivant, A. W.; Rister, M.; Lacewell, R. D.; Rogers, C. S.

    316,871 ....................same $?s $ 20,071 ....................same As shown in Table 1, the original estimated initial capital construction costs totaled $3,585,300 with the revised, actual value equaling $3,278,276 (Balcombe). The installation...,715,000 with the revised, actual value being $7,273,360 (Balcombe). The installation period was projected to take two years, with an ensuing expected useful life of 48 years. No losses of operations or other adverse impacts were anticipated (nor did they occur...

  6. Costing of Joining Methods -Arc Welding Costs

    E-Print Network [OSTI]

    Colton, Jonathan S.

    Costing of Joining Methods - Arc Welding Costs ver. 1 ME 6222: Manufacturing Processes and Systems Prof. J.S. Colton © GIT 2009 1 #12;OverviewOverview · Cost components · Estimation of costsEstimation of costs · Examples ME 6222: Manufacturing Processes and Systems Prof. J.S. Colton © GIT 2009 2 #12;Cost

  7. Rough order of magnitude cost estimate for immobilization of 50 MT of plutonium using existing facilities at Hanford: alternative 11B

    SciTech Connect (OSTI)

    DiSabatino, A., LLNL

    1998-06-01T23:59:59.000Z

    The purpose of this Cost Estimate Report is to identify preliminary capital and operating costs for a facility to immobilize 50 metric tons (nominal) of plutonium as a ceramic in an existing facility at Hanford, the Fuels and Materials Examination Facility (FMEF).

  8. Rough order of magnitude cost estimate for immobilization of 18.2 MT of plutonium using existing facilities at Hanford: alternative 4A/8/10/011

    SciTech Connect (OSTI)

    DiSabatino, A., LLNL

    1998-06-01T23:59:59.000Z

    The purpose of this Cost Estimate Report is to identify preliminary capital and operating costs for a facility to immobilize 18.2 metric tons (nominal) of plutonium as a ceramic in an existing facility, the Fuels and Materials Examination Facility (FMEF), at Hanford.

  9. Rough order of magnitude cost estimate for immobilization of 50 MT of plutonium sharing existing facilities at Hanford with pit disassembly {ampersand} conversion facility: alternative 11

    SciTech Connect (OSTI)

    DiSabatino, A., LLNL

    1998-06-01T23:59:59.000Z

    The purpose of this Cost Estimate Report is to identify preliminary capital and operating costs for a facility to immobilize 50 metric tons (nominal) of plutonium as a ceramic in an existing facility at Hanford, the Fuels and Materials Examination Facility (FMEF). The Pit Disassembly and Conversion Facility (PDCF), which is being costed in a separate report by LANL, will also be located in the FMEF in this co-location option.

  10. Energy savings estimates and cost benefit calculations for high performance relocatable classrooms

    SciTech Connect (OSTI)

    Rainer, Leo I.; Hoeschele, Marc A.; Apte, Michael G.; Shendell, Derek G.; Fisk, Wlliam J.

    2003-12-01T23:59:59.000Z

    This report addresses the results of detailed monitoring completed under Program Element 6 of Lawrence Berkeley National Laboratory's High Performance Commercial Building Systems (HPCBS) PIER program. The purpose of the Energy Simulations and Projected State-Wide Energy Savings project is to develop reasonable energy performance and cost models for high performance relocatable classrooms (RCs) across California climates. A key objective of the energy monitoring was to validate DOE2 simulations for comparison to initial DOE2 performance projections. The validated DOE2 model was then used to develop statewide savings projections by modeling base case and high performance RC operation in the 16 California climate zones. The primary objective of this phase of work was to utilize detailed field monitoring data to modify DOE2 inputs and generate performance projections based on a validated simulation model. Additional objectives include the following: (1) Obtain comparative performance data on base case and high performance HVAC systems to determine how they are operated, how they perform, and how the occupants respond to the advanced systems. This was accomplished by installing both HVAC systems side-by-side (i.e., one per module of a standard two module, 24 ft by 40 ft RC) on the study RCs and switching HVAC operating modes on a weekly basis. (2) Develop projected statewide energy and demand impacts based on the validated DOE2 model. (3) Develop cost effectiveness projections for the high performance HVAC system in the 16 California climate zones.

  11. The South Wilmington Area remedial cost estimating methodology (RCEM) -- A planning tool and reality check for brownfield development

    SciTech Connect (OSTI)

    Yancheski, T.B. [Tetra Tech, Inc., Christiana, DE (United States); Swanson, J.E. [Tetra Tech, Inc., Fairfax, VA (United States)

    1996-12-31T23:59:59.000Z

    The South Wilmington Area (SWA), which is comprised of 200 acres of multi-use urban lowlands adjacent to the Christina River, is a brownfields area that has been targeted for redevelopment/restoration as part of a major waterfront revitalization project for the City of Wilmington, Delaware. The vision for this riverfront development, which is being promoted by a state-funded development corporation, includes plans for a new harbor, convention and entertainment facilities, upscale residences, an urban wildlife refuge, and the restoration of the Christina River. However, the environmental quality of the SWA has been seriously impacted by an assortment of historic and current heavy industrial land-uses since the late 1800`s, and extensive environmental cleanup of this area will be required as part of any redevelopment plan. Given that the environmental cleanup cost will be a major factor in determining the overall economic feasibility of brownfield development in the SWA, a reliable means of estimating potential preliminary remedial costs, without the expense of costly investigative and engineering studies, was needed to assist with this redevelopment initiative. The primary chemicals-of-concern (COCs) area-wide are lead and petroleum compounds, however, there are hot-spot occurrences of polynuclear aromatic hydrocarbons (PAHs), PCBs, and other heavy metals such as arsenic and mercury.

  12. Energy Storage Systems 2010 Update Conference Presentations ...

    Broader source: Energy.gov (indexed) [DOE]

    chaired by NETL's Kim Nuhfer, are below. ESS 2010 Update Conference - Low Cost Energy Storage - Ted Wiley, Aquion.pdf Ess 2010 Update Conference - Solid State Li Metal Batteries...

  13. Estimating Costs and Efficiency of Storage, Demand, and Heat Pump Water

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: Since the YouTube|6721 FederalTexas EnergyofIdaho | Department of EnergyEstimating

  14. Cost Recovery Charge (CRC) Calculation Tables

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Cost Recovery Charge (CRC) Calculation Table Updated: March 20, 2015 FY 2016 February 2015 CRC Calculation Table (pdf) Final FY 2015 CRC Letter & Table (pdf) Note: The Cost...

  15. Microsoft PowerPoint - EM_Update.061011.pptx

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic2 OPAM615_Cost Estimating Panel Microsoft PowerPoint -ofUpdatesUpdate

  16. Cost of a Ride: The Effects of Densities on Fixed-Guideway Transit Ridership and Capital Costs

    E-Print Network [OSTI]

    Guerra, Erick; Cervero, Robert

    2010-01-01T23:59:59.000Z

    rail transit capital cost study update final. Washington,2005). Managing Capital Costs of Major Federally Fundedin US rail transit project cost overrun. Transportation

  17. Systematic Approach for Decommissioning Planning and Estimating

    SciTech Connect (OSTI)

    Dam, A. S.

    2002-02-26T23:59:59.000Z

    Nuclear facility decommissioning, satisfactorily completed at the lowest cost, relies on a systematic approach to the planning, estimating, and documenting the work. High quality information is needed to properly perform the planning and estimating. A systematic approach to collecting and maintaining the needed information is recommended using a knowledgebase system for information management. A systematic approach is also recommended to develop the decommissioning plan, cost estimate and schedule. A probabilistic project cost and schedule risk analysis is included as part of the planning process. The entire effort is performed by a experienced team of decommissioning planners, cost estimators, schedulers, and facility knowledgeable owner representatives. The plant data, work plans, cost and schedule are entered into a knowledgebase. This systematic approach has been used successfully for decommissioning planning and cost estimating for a commercial nuclear power plant. Elements of this approach have been used for numerous cost estimates and estimate reviews. The plan and estimate in the knowledgebase should be a living document, updated periodically, to support decommissioning fund provisioning, with the plan ready for use when the need arises.

  18. Preliminary estimates of the total-system cost for the restructured program: An addendum to the May 1989 analysis of the total-system life cycle cost for the Civilian Radioactive Waste Management Program

    SciTech Connect (OSTI)

    NONE

    1990-12-01T23:59:59.000Z

    The total-system life-cycle cost (TSLCC) analysis for the Department of Energy`s (DOE) Civilian Radioactive Waste Management Program is an ongoing activity that helps determine whether the revenue-producing mechanism established by the Nuclear Waste Policy Act of 1982 - a fee levied on electricity generated and sold by commercial nuclear power plants - is sufficient to cover the cost of the program. This report provides cost estimates for the sixth annual evaluation of the adequacy of the fee. The costs contained in this report represent a preliminary analysis of the cost impacts associated with the Secretary of Energy`s Report to Congress on Reassessment of the Civilian Radioactive Waste Management Program issued in November 1989. The major elements of the restructured program announced in this report which pertain to the program`s life-cycle costs are: a prioritization of the scientific investigations program at the Yucca Mountain candidate site to focus on identification of potentially adverse conditions, a delay in the start of repository operations until 2010, the start of limited waste acceptance at the monitored retrievable storage (MRS) facility in 1998, and the start of waste acceptance at the full-capability MRS facility in 2,000. Based on the restructured program, the total-system cost for the system with a repository at the candidate site at Yucca Mountain in Nevada, a facility for monitored retrievable storage (MRS), and a transportation system is estimated at $26 billion (expressed in constant 1988 dollars). In the event that a second repository is required and is authorized by the Congress, the total-system cost is estimated at $34 to $35 billion, depending on the quantity of spent fuel and high-level waste (HLW) requiring disposal. 17 figs., 17 tabs.

  19. Equipment Design and Cost Estimation for Small Modular Biomass Systems, Synthesis Gas Cleanup, and Oxygen Separation Equipment; Task 2.3: Sulfur Primer

    SciTech Connect (OSTI)

    Nexant Inc.

    2006-05-01T23:59:59.000Z

    This deliverable is Subtask 2.3 of Task 2, Gas Cleanup Design and Cost Estimates, of NREL Award ACO-5-44027, ''Equipment Design and Cost Estimation for Small Modular Biomass Systems, Synthesis Gas Cleanup and Oxygen Separation Equipment''. Subtask 2.3 builds upon the sulfur removal information first presented in Subtask 2.1, Gas Cleanup Technologies for Biomass Gasification by adding additional information on the commercial applications, manufacturers, environmental footprint, and technical specifications for sulfur removal technologies. The data was obtained from Nexant's experience, input from GTI and other vendors, past and current facility data, and existing literature.

  20. CONTAMINATED SOIL VOLUME ESTIMATE TRACKING METHODOLOGY

    SciTech Connect (OSTI)

    Durham, L.A.; Johnson, R.L.; Rieman, C.; Kenna, T.; Pilon, R.

    2003-02-27T23:59:59.000Z

    The U.S. Army Corps of Engineers (USACE) is conducting a cleanup of radiologically contaminated properties under the Formerly Utilized Sites Remedial Action Program (FUSRAP). The largest cost element for most of the FUSRAP sites is the transportation and disposal of contaminated soil. Project managers and engineers need an estimate of the volume of contaminated soil to determine project costs and schedule. Once excavation activities begin and additional remedial action data are collected, the actual quantity of contaminated soil often deviates from the original estimate, resulting in cost and schedule impacts to the project. The project costs and schedule need to be frequently updated by tracking the actual quantities of excavated soil and contaminated soil remaining during the life of a remedial action project. A soil volume estimate tracking methodology was developed to provide a mechanism for project managers and engineers to create better project controls of costs and schedule. For the FUSRAP Linde site, an estimate of the initial volume of in situ soil above the specified cleanup guidelines was calculated on the basis of discrete soil sample data and other relevant data using indicator geostatistical techniques combined with Bayesian analysis. During the remedial action, updated volume estimates of remaining in situ soils requiring excavation were calculated on a periodic basis. In addition to taking into account the volume of soil that had been excavated, the updated volume estimates incorporated both new gamma walkover surveys and discrete sample data collected as part of the remedial action. A civil survey company provided periodic estimates of actual in situ excavated soil volumes. By using the results from the civil survey of actual in situ volumes excavated and the updated estimate of the remaining volume of contaminated soil requiring excavation, the USACE Buffalo District was able to forecast and update project costs and schedule. The soil volume tracking methodology helped the USACE Buffalo District track soil quantity changes from projected excavation work over time and across space, providing the basis for an explanation of some of the project cost and schedule variances.

  1. Rough order of magnitude cost estimate for immobilization of 18.2 MT of plutonium using existing facilities at the Savannah River site: alternatives 3A/5A/6A/6B/7A/9A

    SciTech Connect (OSTI)

    DiSabatino, A., LLNL

    1998-06-01T23:59:59.000Z

    The purpose of this Cost Estimate Report is to identify preliminary capital and operating costs for a facility to immobilize 18.2 metric tons (nominal) of plutonium using ceramic in a new facility at Savannah River Site (SRS).

  2. Estimating Methods

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    Based on the project's scope, the purpose of the estimate, and the availability of estimating resources, the estimator can choose one or a combination of techniques when estimating an activity or project. Estimating methods, estimating indirect and direct costs, and other estimating considerations are discussed in this chapter.

  3. The economics of alternative fuel cycles on sodium-cooled fast reactors and uncertainty and sensitivity analysis of cost estimates

    E-Print Network [OSTI]

    Russo, Genevieve V. (Genevieve Virgina)

    2010-01-01T23:59:59.000Z

    Previous work was done to create a baseline capital cost model for the SFR in which case studies were performed to identify ways to decrease the capital costs while maintaining safety and performance. This thesis expands ...

  4. A Stochastic Unit-Commitment Model to Estimate the Costs of Changing Power Plant Operation under High Amounts of Intermittent Wind Power

    E-Print Network [OSTI]

    A Stochastic Unit-Commitment Model to Estimate the Costs of Changing Power Plant Operation under High Amounts of Intermittent Wind Power Integration Meibom, P.1 , Brand, H.2 , Barth, R.2 and Weber, C in several European countries. The introduction of substantial amounts of wind power in a liberalized

  5. Joint U.S./Russian Study on the Development of a Preliminary Cost Estimate of the SAFSTOR Decommissioning Alternative for the Leningrad Nuclear Power Plant Unit #1

    SciTech Connect (OSTI)

    SM Garrett

    1998-09-28T23:59:59.000Z

    The objectives of the two joint Russian/U.S. Leningrad Nuclear Power Plant (NPP) Unit #1 studies were the development of a safe, technically feasible, economically acceptable decom missioning strategy, and the preliminary cost evaluation of the developed strategy. The first study, resulting in the decommissioning strategy, was performed in 1996 and 1997. The preliminary cost estimation study, described in this report, was performed in 1997 and 1998. The decommissioning strategy study included the analyses of three basic RBM.K decommission- ing alternatives, refined for the Leningrad NPP Unit #1. The analyses included analysis of the requirements for the planning and preparation as well as the decommissioning phases.

  6. Activity Based Costing

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    Activity Based Costing (ABC) is method for developing cost estimates in which the project is subdivided into discrete, quantifiable activities or a work unit. This chapter outlines the Activity Based Costing method and discusses applicable uses of ABC.

  7. Reformulated gasoline: Costs and refinery impacts

    SciTech Connect (OSTI)

    Hadder, G.R.

    1994-02-01T23:59:59.000Z

    Studies of reformulated gasoline (RFG) costs and refinery impacts have been performed with the Oak Ridge National Laboratory Refinery Yield Model (ORNL-RYM), a linear program which has been updated to blend gasolines to satisfy emissions constraints defined by preliminary complex emissions models. Policy makers may use the reformulation cost knee (the point at which costs start to rise sharply for incremental emissions control) to set emissions reduction targets, giving due consideration to the differences between model representations and actual refining operations. ORNL-RYM estimates that the reformulation cost knee for the US East Coast (PADD I) is about 15.2 cents per gallon with a 30 percent reduction of volatile organic compounds (VOCs). The estimated cost knee for the US Gulf Coast (PADD III) is about 5.5 cents per gallon with a VOC reduction of 35 percent. Reid vapor pressure (RVP) reduction is the dominant VOC reduction mechanism. Even with anti-dumping constraints, conventional gasoline appears to be an important sink which permits RFG to be blended with lower aromatics and sulfur contents in PADD III. In addition to the potentially large sensitivity of RFG production to different emissions models, RFG production is sensitive to the non-exhaust VOC share assumption for a particular VOC model. ORNL-RYM has also been used to estimate the sensitivity of RFG production to the cost of capital; to the RVP requirements for conventional gasoline; and to the percentage of RFG produced in a refining region.

  8. Cost of a Ride: The Effects of Densities on Fixed-Guideway Transit Ridership and Capital Costs

    E-Print Network [OSTI]

    Guerra, Erick; Cervero, Robert

    2010-01-01T23:59:59.000Z

    transit – exceeded capital cost estimates by 40% duringfound that capital costs exceeded estimates by an averagesystems. We estimate the total capital cost, average weekday

  9. Interim Update: Global Automotive Power Electronics R&D Relevant...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Interim Update: Global Automotive Power Electronics R&D Relevant To DOE 2015 and 2020 Cost Targets Interim Update: Global Automotive Power Electronics R&D Relevant To DOE 2015 and...

  10. EUV lithography cost of ownership analysis

    SciTech Connect (OSTI)

    Hawryluk, A.M.; Ceglio, N.M.

    1995-01-19T23:59:59.000Z

    The cost of fabricating state-of-the-art integrated circuits (ICs) has been increasing and it will likely be economic rather than technical factors that ultimately limit the progress of ICs toward smaller devices. It is estimated that lithography currently accounts for approximately one-third the total cost of fabricating modem ICs({sup 1}). It is expected that this factor will be fairly stable for the forseeable future, and as a result, any lithographic process must be cost-effective before it can be considered for production. Additionally, the capital equipment cost for a new fabrication facility is growing at an exponential rate (2); it will soon require a multibillion dollar investment in capital equipment alone to build a manufacturing facility. In this regard, it is vital that any advanced lithography candidate justify itself on the basis of cost effectiveness. EUV lithography is no exception and close attention to issues of wafer fabrication costs have been a hallmark of its early history. To date, two prior cost analyses have been conducted for EUV lithography (formerly called {open_quotes}Soft X-ray Projection Lithography{close_quotes}). The analysis by Ceglio, et. al., provided a preliminary system design, set performance specifications and identified critical technical issues for cost control. A follow-on analysis by Early, et.al., studied the impact of issues such as step time, stepper overhead, tool utilization, escalating photoresist costs and limited reticle usage on wafer exposure costs. This current study provides updated system designs and specifications and their impact on wafer exposure costs. In addition, it takes a first cut at a preliminary schematic of an EUVL fabrication facility along with an estimate of the capital equipment costs for such a facility.

  11. Rough order of magnitude cost estimate for immobilization of 18.2 MT of plutonium sharing existing facilities at Hanford with pit disassembly {ampersand} conversion facility: alternative 2

    SciTech Connect (OSTI)

    DiSabatino, A., LLNL

    1998-06-01T23:59:59.000Z

    The purpose of this Cost Estimate Report is to identify preliminary capital and operating costs for a facility to immobilize 18.2 metric tons (nominal) of plutonium as a ceramic in an existing facility at Hanford, the Fuels and Materials Examination Facility (FMEF). The Pit Disassembly and Conversion Facility (PDCF), which is being costed in a separate report will also be located in the FMEF in this co- location option. The technical engineering data used as the basis for this study is presented in the EIS Data Call Input Report, `Plutonium Immobilization Plant Using Ceramic in Existing Facilities at Hanford.` The FMEF will require minimal facility modifications to accommodate the Plutonium Immobilization Plant (PIP). Adequate space is available within the FMEF for installation of the immobilization process equipment. Facility HVAC, utility, and support systems exist to support the immobilization operations. Building modifications are primarily the removal of the SAF line (gloveboxes and support equipment) on the 70` level and building interior changes. The plutonium immobilization equipment will primarily occupy the 42` and 70` levels of the FMEF, with the same equipment layout as in the sole occupancy case. The Pit Disassembly and Conversion Facility would occupy the 21` and O` (Entry) levels. Elements of the FMEF and adjacent Fuel Assembly Area (FAA) that will be shared by PIP and PDCF include shipping and receiving, laboratory, waste handling, security, offices, maintenance shops, SNM storage vault, and utilities. It was assumed that the existing utilities and support systems are adequate or only need minor upgrades to support both the PIP and PDCF. The PIP cost estimate was reconciled with the PDCF cost estimate to confirm the use and costs of shared systems and personnel. The facility design for a 50 metric ton plutonium throughput plant will be used for the 18.2 metric ton facility. Plutonium conversion operations will operate at the same design rate as the 50 metric ton facility over the 10 year operating period. Some of the process equipment will operate for a shorter period of time and fewer operators will be required. The assumptions, missions, design bases, facility and process descriptions, and accident analyses are the same. Therefore it is assumed that the capital cost for the 18.2 metric ton facility is identical to that of the 50 metric ton facility. However, the following operating costs will be less: consumable materials, equipment replacement and maintenance labor, employment requirements, and waste generation.

  12. Numerical simulation of hydrothermal salt separation process and analysis and cost estimating of shipboard liquid waste disposal

    E-Print Network [OSTI]

    Hunt, Andrew Robert

    2007-01-01T23:59:59.000Z

    Due to environmental regulations, waste water disposal for US Navy ships has become a requirement which impacts both operations and the US Navy's budget. In 2006, the cost for waste water disposal Navy-wide was 54 million ...

  13. Washington Update

    Energy Savers [EERE]

    Text eere.energy.gov Federal Energy Management Program FederalUtility Partnership Working Group David McAndrew April 14, 2010 Providence RI Washington Update Federal Energy...

  14. Updated U.S. Geothermal Supply Curve

    SciTech Connect (OSTI)

    Augustine, C.; Young, K. R.; Anderson, A.

    2010-02-01T23:59:59.000Z

    This paper documents the approach used to update the U.S. geothermal supply curve. The analysis undertaken in this study estimates the supply of electricity generation potential from geothermal resources in the United States and the levelized cost of electricity (LCOE), capital costs, and operating and maintenance costs associated with developing these geothermal resources. Supply curves were developed for four categories of geothermal resources: identified hydrothermal (6.4 GWe), undiscovered hydrothermal (30.0 GWe), near-hydrothermal field enhanced geothermal systems (EGS) (7.0 GWe) and deep EGS (15,900 GWe). Two cases were considered: a base case and a target case. Supply curves were generated for each of the four geothermal resource categories for both cases. For both cases, hydrothermal resources dominate the lower cost range of the combined geothermal supply curve. The supply curves indicate that the reservoir performance improvements assumed in the target case could significantly lower EGS costs and greatly increase EGS deployment over the base case.

  15. Critical Update - Renwable Guidance Update

    Broader source: Energy.gov (indexed) [DOE]

    Renewable Update FUPWG May 1, 2007 Chandra Shah, National Renewable Energy Laboratory 303-384-7557, chandrashah@nrel.gov Presentation Overview * Energy Policy Act of 2005 (EPACT...

  16. Cost of Capital and Regulator’s Preferences: Investigation into a new method of estimating regulatory bias

    E-Print Network [OSTI]

    Sancetta, Alessio; Satchell, Stephen E

    When computing regulated prices, the standard method is the capital asset pricing model (CAPM) which involves the estimation of a single parameter: the beta of the company. Yet, these computational methods fail to take into account any preference...

  17. IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 24, NO. 2, APRIL 2009 961 Estimates of Comparative Costs for

    E-Print Network [OSTI]

    Baldick, Ross

    assets. I. INTRODUCTION I NCREASING real-estate costs and continued opposition to new transmission lines. MODEL OF AC TRANSMISSION LINES A. Parameters Specifying Electrical Model and Characteristics In this section, we review the electrical model and charac- teristics of AC transmission lines, focusing

  18. Hardware and software architecture for state estimation on an experimental low-cost small-scaled helicopter

    E-Print Network [OSTI]

    : Low-cost sensors Embedded systems MEMS Unmanned aerial vehicle Autonomous helicopter Data fusion a b contribution of this paper is to detail, at the light of a successful reported autonomous hovering flight of unmanned aerial vehicles (UAV) with various degrees of auton- omy (see Wise, 2004). Prime examples

  19. Costing Summaries for Selected Water Treatment

    E-Print Network [OSTI]

    · Engineering News-Record Construction Cost Index · Consumer Prices Index · Year Index = average of the monthly;Develop Costing Curves for : · Construction · Operation and Maintenance #12;Small Systems · Limited · Construction Costs · O&M Costs · General Design and Operational Information #12;Update The Costs for year 2000

  20. Estimating the Energy, Demand and Cost Savings from a Geothermal Heat Pump ESPC Project at Fort Polk, LA Through Utility Bill Analysis.

    SciTech Connect (OSTI)

    Shonder, John A [ORNL; Hughes, Patrick [ORNL

    2006-01-01T23:59:59.000Z

    Energy savings performance contracts (ESPCs) are a method of financing energy conservation projects using the energy cost savings generated by the conservation measures themselves. Ideally, reduced energy costs are visible as reduced utility bills, but in fact this is not always the case. On large military bases, for example, a single electric meter typically covers hundreds of individual buildings. Savings from an ESPC involving only a small number of these buildings will have little effect on the overall utility bill. In fact, changes in mission, occupancy, and energy prices could cause substantial increases in utility bills. For this reason, other, more practical, methods have been developed to measure and verify savings in ESPC projects. Nevertheless, increasing utility bills--when ESPCs are expected to be reducing them--are problematic and can lead some observers to question whether savings are actually being achieved. In this paper, the authors use utility bill analysis to determine energy, demand, and cost savings from an ESPC project that installed geothermal heat pumps in the family housing areas of the military base at Fort Polk, Louisiana. The savings estimates for the first year after the retrofits were found to be in substantial agreement with previous estimates that were based on submetered data. However, the utility bills also show that electrical use tended to increase as time went on. Since other data show that the energy use in family housing has remained about the same over the period, the authors conclude that the savings from the ESPC have persisted, and increases in electrical use must be due to loads unassociated with family housing. This shows that under certain circumstances, and with the proper analysis, utility bills can be used to estimate savings from ESPC projects. However, these circumstances are rare and over time the comparison may be invalidated by increases in energy use in areas unaffected by the ESPC.

  1. T ti E St S tTetiaroa Energy Storage System Estimated ZBB Zinc Bromide Battery Performance and Costs

    E-Print Network [OSTI]

    Kammen, Daniel M.

    ://rael.berkeley.edu 1 #12;Island Load and DieselIsland Load and Diesel Generation Assumptions #12;Estimated Elect ical variation #12;Diesel Gene ationDiesel Generation It was assumed that backup generation will be met via (2) 455 kW diesel generator sets These generator sets were modeled using data available

  2. Rough order of magnitude cost estimate for immobilization of 18.2 MT of plutonium using existing facilities at the Savannah River site: alternatives 3B/5B/6C/6D/7B/9B

    SciTech Connect (OSTI)

    DiSabatino, A., LLNL

    1998-06-01T23:59:59.000Z

    The purpose of this Cost Estimate Report is to identify preliminary capital and operating costs for a facility to immobilize 18.2 metric tons (nominal) of plutonium using ceramic in an existing facility (221-F) at Savannah River Site (SRS).

  3. Rough order of magnitude cost estimate for immobilization of 18.2 MT of plutonium sharing existing facilities at Hanford with MOX fuel fabrication facility: alternative 4B/011

    SciTech Connect (OSTI)

    DiSabatino, A., LLNL

    1998-06-01T23:59:59.000Z

    The purpose of this Cost Estimate Report is to identify preliminary capital and operating costs for a facility to immobilize 18.2 metric tons (nominal) of plutonium as a ceramic in an existing facility at Hanford, the Fuels and Materials Examination Facility (FMEF). The MOX Fuel Fabrication Facility (MFFF), which is being costed in a separate report, will also be located in the FMEF in this co-location option.

  4. Microsoft PowerPoint - Crouther - Human Capital Update

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic2 OPAM615_Cost Estimating Panel Microsoft PowerPoint -ofUpdates Presented to the

  5. Microsoft PowerPoint - Triay - EM Program Update

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic2 OPAM615_Cost Estimating Panel MicrosoftSeptember 15, September T I A liUpdate

  6. Cost estimate report for the long-term management of depleted uranium hexafluoride : storage of depleted uranium metal.

    SciTech Connect (OSTI)

    Folga, S.M.; Kier, P.H.; Thimmapuram, P.R.

    2001-01-24T23:59:59.000Z

    This report contains a cost analysis of the long-term storage of depleted uranium in the form of uranium metal. Three options are considered for storage of the depleted uranium. These options are aboveground buildings, partly underground vaults, and mined cavities. Three cases are presented. In the first case, all the depleted uranium metal that would be produced from the conversion of depleted uranium hexafluoride (UF{sub 6}) generated by the US Department of Energy (DOE) prior to July 1993 would be stored at the storage facility (100% Case). In the second case, half the depleted uranium metal would be stored at this storage facility (50% Case). In the third case, one-quarter of the depleted uranium metal would be stored at the storage facility (25% Case). The technical basis for the cost analysis presented in this report is principally found in the companion report, ANL/EAD/TM-100, ''Engineering Analysis Report for the Long-Term Management of Depleted Uranium Hexafluoride: Storage of Depleted Uranium Metal'', prepared by Argonne National Laboratory.

  7. Estimate of Cost-Effective Potential for Minimum Efficiency Performance Standards in 13 Major World Economies Energy Savings, Environmental and Financial Impacts

    E-Print Network [OSTI]

    Letschert, Virginie E.

    2013-01-01T23:59:59.000Z

    inclusion of the social cost of carbon impact the evaluationinclusion of the social cost of carbon impact the evaluation

  8. Direct/Indirect Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    This chapter provides recommended categories for direct and indirect elements developed by the Committee for Cost Methods Development (CCMD) and describes various estimating techniques for direct and indirect costs.

  9. Determining the Lowest-Cost Hydrogen Delivery Mode

    E-Print Network [OSTI]

    Yang, Christopher; Ogden, Joan M

    2008-01-01T23:59:59.000Z

    Costs to Estimate Hydrogen Pipeline Costs. 2004, ITS-Davis:hydrogen. The cost of hydrogen pipeline delivery depends onCosts to Estimate Hydrogen Pipeline Costs. 2004, ITS-Davis:

  10. Spent fuel disassembly hardware and other non-fuel bearing components: characterization, disposal cost estimates, and proposed repository acceptance requirements

    SciTech Connect (OSTI)

    Luksic, A.T.; McKee, R.W.; Daling, P.M.; Konzek, G.J.; Ludwick, J.D.; Purcell, W.L.

    1986-10-01T23:59:59.000Z

    There are two categories of waste considered in this report. The first is the spent fuel disassembly (SFD) hardware. This consists of the hardware remaining after the fuel pins have been removed from the fuel assembly. This includes end fittings, spacer grids, water rods (BWR) or guide tubes (PWR) as appropriate, and assorted springs, fasteners, etc. The second category is other non-fuel-bearing (NFB) components the DOE has agreed to accept for disposal, such as control rods, fuel channels, etc., under Appendix E of the standard utiltiy contract (10 CFR 961). It is estimated that there will be approximately 150 kg of SFD and NFB waste per average metric ton of uranium (MTU) of spent uranium. PWR fuel accounts for approximately two-thirds of the average spent-fuel mass but only 50 kg of the SFD and NFB waste, with most of that being spent fuel disassembly hardware. BWR fuel accounts for one-third of the average spent-fuel mass and the remaining 100 kg of the waste. The relatively large contribution of waste hardware in BWR fuel, will be non-fuel-bearing components, primarily consisting of the fuel channels. Chapters are devoted to a description of spent fuel disassembly hardware and non-fuel assembly components, characterization of activated components, disposal considerations (regulatory requirements, economic analysis, and projected annual waste quantities), and proposed acceptance requirements for spent fuel disassembly hardware and other non-fuel assembly components at a geologic repository. The economic analysis indicates that there is a large incentive for volume reduction.

  11. Development of a Preliminary Decommissioning Plan Following the International Structure for Decommissioning Costing (ISDC) of Nuclear Installations - 13361

    SciTech Connect (OSTI)

    Moshonas Cole, Katherine; Dinner, Julia; Grey, Mike [Candesco - A Division of Kinectrics Inc, 26 Wellington E 3rd floor, Toronto, Ontario, M5E 1S2 (Canada)] [Candesco - A Division of Kinectrics Inc, 26 Wellington E 3rd floor, Toronto, Ontario, M5E 1S2 (Canada); Daniska, Vladimir [DECOM a.s., Sibirska 1, 917 01 Trnava (Slovakia)] [DECOM a.s., Sibirska 1, 917 01 Trnava (Slovakia)

    2013-07-01T23:59:59.000Z

    The International Structure for Decommissioning Costing (ISDC) of Nuclear Installations, published by OECD/NEA, IAEA and EC is intended to provide a uniform list of cost items for decommissioning projects and provides a standard format that permits international cost estimates to be compared. Candesco and DECOM have used the ISDC format along with two costing codes, OMEGA and ISDCEX, developed from the ISDC by DECOM, in three projects: the development of a preliminary decommissioning plan for a multi-unit CANDU nuclear power station, updating the preliminary decommissioning cost estimates for a prototype CANDU nuclear power station and benchmarking the cost estimates for CANDU against the cost estimates for other reactor types. It was found that the ISDC format provides a well defined and transparent basis for decommissioning planning and cost estimating that assists in identifying gaps and weaknesses and facilitates the benchmarking against international experience. The use of the ISDC can also help build stakeholder confidence in the reliability of the plans and estimates and the adequacy of decommissioning funding. (authors)

  12. RCRA/UST, superfund, and EPCRA hotline training module. Introduction to toxics release inventory: Estimating releases (EPCRA section 313; 40 CFR part 372). Updated as of November 1995

    SciTech Connect (OSTI)

    NONE

    1996-03-01T23:59:59.000Z

    The module provides an overview of general techniques that owners and operators of reporting facilities may use to estimate their toxic chemical releases. It exlains the basic release estimation techniques used to determine the chemical quantities reported on the Form R and uses those techniques, along with fundamental chemical or physical principles and properties, to estimate releases of listed toxic chemicals. It converts units of mass, volume, and time. It states the rules governing significant figures and rounding techniques, and references general and industry-specific estimation documents.

  13. The Cost of Superconducting Magnets as a Function of Stored Energy and Design Magnetic Induction Times the Field Volume

    SciTech Connect (OSTI)

    Green, Mike; Green, M.A.; Strauss, B.P.

    2007-08-27T23:59:59.000Z

    By various theorems one can relate the capital cost of superconducting magnets to the magnetic energy stored within that magnet. This is particularly true for magnet where the cost is dominated by the structure needed to carry the magnetic forces. One can also relate the cost of the magnet to the product of the magnetic induction and the field volume. The relationship used to estimate the cost the magnet is a function of the type of magnet it is. This paper updates the cost functions given in two papers that were published in the early 1990 s. The costs (escalated to 2007 dollars) of large numbers of LTS magnets are plotted against stored energy and magnetic field time field volume. Escalated costs for magnets built since the early 1990 s are added to the plots.

  14. Sandia National Laboratories: most promising strategies for cost...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    promising strategies for cost-efficient biorefinery operations JBEI Updates Techno-Economic Modeling Tools for Biofuels On September 18, 2013, in Biofuels, Biomass, Computational...

  15. Changing the Climate: Looking Towards a More Cost Effective,...

    Broader source: Energy.gov (indexed) [DOE]

    updated "National Action Plan Vision for 2025: A Framework for Change." Changing the Climate: Looking Towards a More Cost Effective, Energy Efficient Future, November 18, 2008...

  16. U.S. Department of Energy Hydrogen Storage Cost Analysis

    SciTech Connect (OSTI)

    Law, Karen; Rosenfeld, Jeffrey; Han, Vickie; Chan, Michael; Chiang, Helena; Leonard, Jon

    2013-03-11T23:59:59.000Z

    The overall objective of this project is to conduct cost analyses and estimate costs for on- and off-board hydrogen storage technologies under development by the U.S. Department of Energy (DOE) on a consistent, independent basis. This can help guide DOE and stakeholders toward the most-promising research, development and commercialization pathways for hydrogen-fueled vehicles. A specific focus of the project is to estimate hydrogen storage system cost in high-volume production scenarios relative to the DOE target that was in place when this cost analysis was initiated. This report and its results reflect work conducted by TIAX between 2004 and 2012, including recent refinements and updates. The report provides a system-level evaluation of costs and performance for four broad categories of on-board hydrogen storage: (1) reversible on-board metal hydrides (e.g., magnesium hydride, sodium alanate); (2) regenerable off-board chemical hydrogen storage materials(e.g., hydrolysis of sodium borohydride, ammonia borane); (3) high surface area sorbents (e.g., carbon-based materials); and 4) advanced physical storage (e.g., 700-bar compressed, cryo-compressed and liquid hydrogen). Additionally, the off-board efficiency and processing costs of several hydrogen storage systems were evaluated and reported, including: (1) liquid carrier, (2) sodium borohydride, (3) ammonia borane, and (4) magnesium hydride. TIAX applied a â��bottom-upâ� costing methodology customized to analyze and quantify the processes used in the manufacture of hydrogen storage systems. This methodology, used in conjunction with DFMA�® software and other tools, developed costs for all major tank components, balance-of-tank, tank assembly, and system assembly. Based on this methodology, the figure below shows the projected on-board high-volume factory costs of the various analyzed hydrogen storage systems, as designed. Reductions in the key cost drivers may bring hydrogen storage system costs closer to this DOE target. In general, tank costs are the largest component of system cost, responsible for at least 30 percent of total system cost, in all but two of the 12 systems. Purchased BOP cost also drives system cost, accounting for 10 to 50 percent of total system cost across the various storage systems. Potential improvements in these cost drivers for all storage systems may come from new manufacturing processes and higher production volumes for BOP components. In addition, advances in the production of storage media may help drive down overall costs for the sodium alanate, SBH, LCH2, MOF, and AX-21 systems.

  17. Low-Risk and Cost-Effective Prior Savings Estimates for Large-Scale Energy Conservation Projects in Housing: Learning from the Fort Polk GHP Project

    SciTech Connect (OSTI)

    Shonder, John A [ORNL; Hughes, Patrick [ORNL; Thornton, Jeff W. [Thermal Energy Systems Specialists, Inc.

    1997-08-01T23:59:59.000Z

    Many opportunities exist for large-scale energy conservation projects in housing: military housing, federally-subsidized low-income housing, and planned communities (condominiums, townhomes, senior centers) to name a few. Energy savings performance contracting (ESPC) is now receiving greater attention, as a means to implement such projects. This paper proposes an improved method for prior (to construction) savings estimates for these projects. More accurate prior estimates reduce project risk, decrease financing costs, and help avoid post-construction legal disputes over performance contract baseline adjustments. The proposed approach to prior estimates is verified against data from Fort Polk, LA. In the course of evaluating the ESPC at Fort Polk, Louisiana, we have collected energy use data - both at the electrical feeder level and at the level of individual residences - which allowed us to develop calibrated engineering models which accurately predict pre-retrofit energy consumption. We believe that such calibrated models could be used to provide much more accurate estimates of energy savings in retrofit projects, particularly in cases where the energy consumption of large populations of housing can be captured on one or a few meters. The improved savings estimating approach described here is based on an engineering model calibrated to field-collected data from the pre-retrofit period. A dynamic model of pre-retrofit energy use was developed for all housing and non-housing loads on a complete electrical feeder at Fort Polk. The feeder serves 46 buildings containing a total of 200 individual apartments. Of the 46 buildings, there are three unique types, and among these types the only difference is compass orientation. The model included the heat transfer characteristics of the buildings, the pre-retrofit air source heat pump, a hot water consumption model and a profile for electrical use by lights and other appliances. Energy consumption for all 200 apartments was totaled, and by adjusting thermostat setpoints and outdoor air infiltration parameters, the models were matched to field-collected energy consumption data for the entire feeder. The energy conservation measures were then implemented in the calibrated model: the air source heat pumps were replaced by geothermal heat pumps (GHPs) with desuperheaters; hot water loads were reduced to account for the low-flow shower heads; and lighting loads were reduced to account for fixture delamping and replacement with compact fluorescent lights (CFLs). Our analysis of pre- and post-retrofit data (Shonder and Hughes, 1997) indicates that the retrofits have saved 30.3% of pre-retrofit electrical energy consumption on the feeder modeled in this paper. Using the method outlined, we have been able to predict this savings within 0.1% of its measured value, using only pre-construction energy consumption data, and data from one pilot test site. It is well-known that predictions of savings from energy conservation programs are often optimistic, especially in the case of residential retrofits. Fels and keating (1993) cite several examples of programs which achieved as little as 20% of the predicted energy savings. Factors which influence the sometimes large discrepancies between actual and predicted savings include changes in occupancy, take-back effects (in which more efficient system operation leads occupants to choose higher levels of comfort), and changes in base energy use (e.g. through purchase of additional appliances such as washing machines and clothes dryers). An even larger factor, perhaps, is the inaccuracy inherent in the engineering models (BLAST, DOE-2, etc.) commonly used to estimate building energy consumption, if these models are not first calibrated to site-monitored data. For example, prior estimates of base-wide savings from the Fort Polk ESPC were on the order of 40% of pre-retrofit electrical use; our analysis has shown the true savings for the entire project (which includes 16 separate electrical feeders) to be about 32%. It should be noted that the retrofits ca

  18. Estimation of ship construction costs

    E-Print Network [OSTI]

    Miroyannis, Aristides

    2006-01-01T23:59:59.000Z

    Since the end of the Cold War naval procurement for the US Navy has seen a dramatic decrease. This decrease in defense spending has placed existing programs under more scrutiny than previous years. As a result there is ...

  19. Estimated Cost Description Determination Date:

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't Your Destiny:RevisedAdvisoryStandardGeneration |10 DOEGoals During NRELHighTitle, Location

  20. Evaluation of Global Onshore Wind Energy Potential and Generation Costs

    SciTech Connect (OSTI)

    Zhou, Yuyu; Luckow, Patrick; Smith, Steven J.; Clarke, Leon E.

    2012-06-20T23:59:59.000Z

    In this study, we develop an updated global estimate of onshore wind energy potential using reanalysis wind speed data, along with updated wind turbine technology performance and cost assumptions as well as explicit consideration of transmission distance in the calculation of transmission costs. We find that wind has the potential to supply a significant portion of world energy needs, although this potential varies substantially by region as well as with assumptions such as on what types of land can be used to site wind farms. Total global wind potential under central assumptions is estimated to be approximately 89 petawatt hours per year at less than 9 cents/kWh with substantial regional variations. One limitation of global wind analyses is that the resolution of current global wind speed reanalysis data can result in an underestimate of high wind areas. A sensitivity analysis of eight key parameters is presented. Wind potential is sensitive to a number of input parameters, particularly those related to land suitability and turbine density as well as cost and financing assumptions which have important policy implications. Transmission cost has a relatively small impact on total wind costs, changing the potential at a given cost by 20-30%. As a result of sensitivities studied here we suggest that further research intended to inform wind supply curve development focus not purely on physical science, such as better resolved wind maps, but also on these less well-defined factors, such as land-suitability, that will also have an impact on the long-term role of wind power.

  1. Estimate of Cost-Effective Potential for Minimum Efficiency Performance Standards in 13 Major World Economies Energy Savings, Environmental and Financial Impacts

    E-Print Network [OSTI]

    Letschert, Virginie E.

    2013-01-01T23:59:59.000Z

    heating and space heating, for which cost data were not available, and the specificity of the marketheating and space heating, for which cost data were not available, and the specificity of the market

  2. EPA Diesel Update

    Broader source: Energy.gov (indexed) [DOE]

    EPA Diesel Update 2005 DEER Conference Bill Charmley EPAOffice of Transportation and Air Quality August 22, 2005 2 Overview * Implementation update on mobile source diesel...

  3. Validating the Estimated Cost of Saving Water Through Infrastructure Rehabilitation in the Texas Lower Rio Grande Valley (Hidalgo County Irrigation District No. 1) 

    E-Print Network [OSTI]

    Lacewell, R. D.; Rister, M.; Sturdivant, A. W.

    2005-01-01T23:59:59.000Z

    A Case Study Using Actual Construction Costs for the Curry Main Pipeline Project, Hidalgo County Irrigation District No. 1 (Edinburg)...

  4. Validating the Estimated Cost of Saving Water Through Infrastructure Rehabilitation in the Texas Lower Rio Grande Valley (Hidalgo County Irrigation District No. 1)

    E-Print Network [OSTI]

    Lacewell, R. D.; Rister, M.; Sturdivant, A. W.

    A Case Study Using Actual Construction Costs for the Curry Main Pipeline Project, Hidalgo County Irrigation District No. 1 (Edinburg)...

  5. ESnet Update

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625govInstrumentstdmadapInactiveVisitingContract ManagementDiscoveringESnet Update Winter 2008 Joint Techs Workshop

  6. Realized and prospective impacts of U.S. energy efficiency standards for residential appliances: 2004 update

    SciTech Connect (OSTI)

    Meyers, Stephen; McMahon, James; McNeil, Michael

    2005-06-24T23:59:59.000Z

    This study estimated energy, environmental and consumer economic impacts of U.S. federal residential energy efficiency standards that became effective in the 1988-2001 period or will take effect by the end of 2007. These standards have been the subject of in-depth analyses conducted as part of DOE's standards rulemaking process. This study drew on those analyses, but updated certain data and developed a common framework and assumptions for all of the products in order to estimate realized impacts and to update projected impacts. We estimate that the considered standards will reduce residential primary energy consumption and CO{sub 2} emissions in 2020 by 8% compared to the levels expected without any standards. They will save a cumulative total of 34 quads by 2020, and 54 quads by 2030. The estimated cumulative net present value of consumer benefit amounts to $93 billion by 2020, and grows to $125 billion by 2030. The overall benefit/cost ratio of cumulative consumer impacts is 2.45 to 1. While the results of this study are subject to a fair degree of uncertainty, we believe that the general conclusions--DOE's energy efficiency standards save significant quantities of energy (and associated carbon emissions) and reduce consumers' net costs--are robust.

  7. Factors Impacting Decommissioning Costs - 13576

    SciTech Connect (OSTI)

    Kim, Karen; McGrath, Richard [Electric Power Research Institute, 3420 Hillview Ave., Palo Alto, California (United States)] [Electric Power Research Institute, 3420 Hillview Ave., Palo Alto, California (United States)

    2013-07-01T23:59:59.000Z

    The Electric Power Research Institute (EPRI) studied United States experience with decommissioning cost estimates and the factors that impact the actual cost of decommissioning projects. This study gathered available estimated and actual decommissioning costs from eight nuclear power plants in the United States to understand the major components of decommissioning costs. Major costs categories for decommissioning a nuclear power plant are removal costs, radioactive waste costs, staffing costs, and other costs. The technical factors that impact the costs were analyzed based on the plants' decommissioning experiences. Detailed cost breakdowns by major projects and other cost categories from actual power plant decommissioning experiences will be presented. Such information will be useful in planning future decommissioning and designing new plants. (authors)

  8. Driltac (Drilling Time and Cost Evaluation)

    SciTech Connect (OSTI)

    None

    1986-08-01T23:59:59.000Z

    The users manual for the drill tech model for estimating the costs of geothermal wells. The report indicates lots of technical and cost detail. [DJE-2005

  9. Statistical Inference for Costs and Incremental Cost-Effectiveness Ratios with Censored Data

    E-Print Network [OSTI]

    Chen, Shuai

    2012-07-16T23:59:59.000Z

    Cost-effectiveness analysis is widely conducted in the economic evaluation of new treatment options. In many clinical and observational studies of costs, data are often censored. Censoring brings challenges to both medical cost estimation and cost...

  10. Statistical Inference for Costs and Incremental Cost-Effectiveness Ratios with Censored Data 

    E-Print Network [OSTI]

    Chen, Shuai

    2012-07-16T23:59:59.000Z

    Cost-effectiveness analysis is widely conducted in the economic evaluation of new treatment options. In many clinical and observational studies of costs, data are often censored. Censoring brings challenges to both medical cost estimation and cost...

  11. Validating the Estimated Cost of Saving Water Through Infrastructure Rehabilitation in the Texas Lower Rio Grande Valley (Hidalgo County Irrigation District No. 2)

    E-Print Network [OSTI]

    Lacewell, R. D.; Rister, M.; Sturdivant, A. W.

    A Case Study Using Actual Construction Costs for the Lateral A Lining Project, Hidalgo County Irrigation District No. 2 (San Juan)...

  12. Determining the lowest-cost hydrogen delivery mode

    E-Print Network [OSTI]

    Yang, Christopher; Ogden, Joan M

    2007-01-01T23:59:59.000Z

    costs to estimate hydrogen pipeline costs. Davis, CA: ITS-hydrogen. The cost of hydrogen pipeline delivery de- pendshydrogen trucks, and hydrogen pipelines, were devel- oped

  13. Updated 11/1/2012 GEORGIA INSTITUTE OF TECHNOLOGY

    E-Print Network [OSTI]

    Li, Mo

    Updated 11/1/2012 GEORGIA INSTITUTE OF TECHNOLOGY OFFICE OF FINANCIAL SERVICES ADMINSTRATION Cash/Investment Management Debt Management Georgia Tech Facilities, Inc. Georgia Advanced Technology Ventures, Inc. Project Accounting Cost Accounting Rate Studies Negotiations Salary, Planning

  14. Microsoft Word - Updated By-Laws for EM QA Corporate Board from October 2014-FOR VOTE

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic2 OPAM615_Cost Estimating35.doc Microsoft Word -Secretary ofUpdated014 1 By-Laws

  15. Updated 1-12 David E. Burgess

    E-Print Network [OSTI]

    advisor for naval aviation cost estimating and analysis, and Earned Value Management (EVM). He leads Department Deputy Director. Just prior, he served as Cost Department Site Manager for the Naval Air Warfare

  16. Hydrogen refueling station costs in Shanghai

    E-Print Network [OSTI]

    Weinert, Jonathan X.; Shaojun, Liu; Ogden, Joan M; Jianxin, Ma

    2007-01-01T23:59:59.000Z

    total installed capital cost (TIC) 1% Of TIC 25% Estimate ofcost estimates for six station types SMR 100 a Equipment capital

  17. Electric power substation capital costs

    SciTech Connect (OSTI)

    Dagle, J.E.; Brown, D.R.

    1997-12-01T23:59:59.000Z

    The displacement or deferral of substation equipment is a key benefit associated with several technologies that are being developed with the support of the US Department of Energy`s Office of Utility Technologies. This could occur, for example, as a result of installing a distributed generating resource within an electricity distribution system. The objective of this study was to develop a model for preparing preliminary estimates of substation capital costs based on rudimentary conceptual design information. The model is intended to be used by energy systems analysts who need ``ballpark`` substation cost estimates to help establish the value of advanced utility technologies that result in the deferral or displacement of substation equipment. This cost-estimating model requires only minimal inputs. More detailed cost-estimating approaches are recommended when more detailed design information is available. The model was developed by collecting and evaluating approximately 20 sets of substation design and cost data from about 10 US sources, including federal power marketing agencies and private and public electric utilities. The model is principally based on data provided by one of these sources. Estimates prepared with the model were compared with estimated and actual costs for the data sets received from the other utilities. In general, good agreement (for conceptual level estimating) was found between estimates prepared with the cost-estimating model and those prepared by the individual utilities. Thus, the model was judged to be adequate for making preliminary estimates of typical substation costs for US utilities.

  18. LIFE Cost of Electricity, Capital and Operating Costs

    SciTech Connect (OSTI)

    Anklam, T

    2011-04-14T23:59:59.000Z

    Successful commercialization of fusion energy requires economic viability as well as technical and scientific feasibility. To assess economic viability, we have conducted a pre-conceptual level evaluation of LIFE economics. Unit costs are estimated from a combination of bottom-up costs estimates, working with representative vendors, and scaled results from previous studies of fission and fusion plants. An integrated process model of a LIFE power plant was developed to integrate and optimize unit costs and calculate top level metrics such as cost of electricity and power plant capital cost. The scope of this activity was the entire power plant site. Separately, a development program to deliver the required specialized equipment has been assembled. Results show that LIFE power plant cost of electricity and plant capital cost compare favorably to estimates for new-build LWR's, coal and gas - particularly if indicative costs of carbon capture and sequestration are accounted for.

  19. Estimate of Cost-Effective Potential for Minimum Efficiency Performance Standards in 13 Major World Economies Energy Savings, Environmental and Financial Impacts

    E-Print Network [OSTI]

    Letschert, Virginie E.

    2013-01-01T23:59:59.000Z

    systems for which heat pump water heaters are found to beachieved by 2030. Heat-pump water heaters, which represent aU.S. and the EU. Heat-pump water heaters have a high cost

  20. Final Report What Will Adaptation Cost?

    E-Print Network [OSTI]

    ..................................................................................................................26 Task 3: Estimate Costs of Implementing Adaptation Strategies ....................................................................34 Task 2: Calculate the Capital and Maintenance CostsFinal Report What Will Adaptation Cost? An Economic Framework for Coastal Community Infrastructure

  1. LEAD at Unidata Status Update, April 2009

    E-Print Network [OSTI]

    LEAD at Unidata Status Update, April 2009 Mohan Ramamurthy The LEAD project is currently in the no-cost extension period and nearing the end of its period of performance as an NSF Large ITR award. LEAD has and networking to huge data sets, human decision making and complex virtual organizations ­ LEAD functionality

  2. LEAD at Unidata Status Update, October 2009

    E-Print Network [OSTI]

    LEAD at Unidata Status Update, October 2009 Mohan Ramamurthy The official period of performance for the LEAD project ended on 30 September 2009 after a one-year the no-cost extension period. The six year ITR computing and networking to huge data sets, human decision making and complex virtual organizations ­ LEAD

  3. Techno-Economic Models for Carbon Dioxide Compression, Transport, and Storage & Correlations for Estimating Carbon Dioxide Density and Viscosity

    E-Print Network [OSTI]

    McCollum, David L; Ogden, Joan M

    2006-01-01T23:59:59.000Z

    Ogden models use capital cost estimates from Skovholt’s 1993are below average but estimate capital costs that are abovediameter, it estimates capital cost below the average.

  4. Cost analysis guidelines

    SciTech Connect (OSTI)

    Strait, R.S.

    1996-01-10T23:59:59.000Z

    The first phase of the Depleted Uranium Hexafluoride Management Program (Program)--management strategy selection--consists of several program elements: Technology Assessment, Engineering Analysis, Cost Analysis, and preparation of an Environmental Impact Statement (EIS). Cost Analysis will estimate the life-cycle costs associated with each of the long-term management strategy alternatives for depleted uranium hexafluoride (UF6). The scope of Cost Analysis will include all major expenditures, from the planning and design stages through decontamination and decommissioning. The costs will be estimated at a scoping or preconceptual design level and are intended to assist decision makers in comparing alternatives for further consideration. They will not be absolute costs or bid-document costs. The purpose of the Cost Analysis Guidelines is to establish a consistent approach to analyzing of cost alternatives for managing Department of Energy`s (DOE`s) stocks of depleted uranium hexafluoride (DUF6). The component modules that make up the DUF6 management program differ substantially in operational maintenance, process-options, requirements for R and D, equipment, facilities, regulatory compliance, (O and M), and operations risk. To facilitate a consistent and equitable comparison of costs, the guidelines offer common definitions, assumptions or basis, and limitations integrated with a standard approach to the analysis. Further, the goal is to evaluate total net life-cycle costs and display them in a way that gives DOE the capability to evaluate a variety of overall DUF6 management strategies, including commercial potential. The cost estimates reflect the preconceptual level of the designs. They will be appropriate for distinguishing among management strategies.

  5. Plans, Updates, Regulatory Documents

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Stewardship Environmental Protection Obeying Environmental Laws Individual Permit Documents Individual Permit: Plans, Updates, Regulatory Documents1335769200000Plans...

  6. Societal lifetime cost of hydrogen fuel cell vehicles

    E-Print Network [OSTI]

    Sun, Yongling; Ogden, J; Delucchi, Mark

    2010-01-01T23:59:59.000Z

    Fuel-cell system cost estimate Fuel cell performance andsignificantly affect the cost of fuel cell stack. In aTo estimate how the costs of fuel-cell system components

  7. Energy Efficiency Improvement and Cost Saving Opportunities for the Dairy Processing Industry

    E-Print Network [OSTI]

    Brush, Adrian

    2012-01-01T23:59:59.000Z

    technologies/water_efficiency.cfm. High pressure low volumefor Compressed Air Efficiency. E-Source Tech Update.Refrigeration Plant Efficiently -- A Cost Saving Guide for

  8. Cost per-User as Key Factor in Project Prioritization: A Case Study of the San Francisco Bay Area

    E-Print Network [OSTI]

    Nuworsoo, Cornelius; Parks, Kamala; Deakin, Elizabeth

    2006-01-01T23:59:59.000Z

    The total estimated investment cost of network-related. ll0Vdistribution of capital investment costs and consequentlyThe total estimated investment cost of service-related

  9. Industrial Heat Pumps--Types and Costs 

    E-Print Network [OSTI]

    Chappell, R. N.; Bliem, C. J.; Mills, J. I.; Demuth, O. J.; Plaster, D. S.

    1985-01-01T23:59:59.000Z

    this categorization, the cost of recovering waste energy with heat pumps was examined. Examples were evaluated in which the cost of energy delivered was calculated based on estimates of capital cost, operating costs, and maintenance costs. Heat pumps from the various...

  10. Decommissioning Unit Cost Data

    SciTech Connect (OSTI)

    Sanford, P. C.; Stevens, J. L.; Brandt, R.

    2002-02-26T23:59:59.000Z

    The Rocky Flats Closure Site (Site) is in the process of stabilizing residual nuclear materials, decommissioning nuclear facilities, and remediating environmental media. A number of contaminated facilities have been decommissioned, including one building, Building 779, that contained gloveboxes used for plutonium process development but did little actual plutonium processing. The actual costs incurred to decommission this facility formed much of the basis or standards used to estimate the decommissioning of the remaining plutonium-processing buildings. Recent decommissioning activities in the first actual production facility, Building 771, implemented a number of process and procedural improvements. These include methods for handling plutonium contaminated equipment, including size reduction, decontamination, and waste packaging, as well as management improvements to streamline planning and work control. These improvements resulted in a safer working environment and reduced project cost, as demonstrated in the overall project efficiency. The topic of this paper is the analysis of how this improved efficiency is reflected in recent unit costs for activities specific to the decommissioning of plutonium facilities. This analysis will allow the Site to quantify the impacts on future Rocky Flats decommissioning activities, and to develop data for planning and cost estimating the decommissioning of future facilities. The paper discusses the methods used to collect and arrange the project data from the individual work areas within Building 771. Regression and data correlation techniques were used to quantify values for different types of decommissioning activities. The discussion includes the approach to identify and allocate overall project support, waste management, and Site support costs based on the overall Site and project costs to provide a ''burdened'' unit cost. The paper ultimately provides a unit cost basis that can be used to support cost estimates for decommissioning at other facilities with similar equipment and labor costs. It also provides techniques for extracting information from limited data using extrapolation and interpolation techniques.

  11. The Cost of Helium Refrigerators and Coolers for SuperconductingDevices as a Function of Cooling at 4 K

    SciTech Connect (OSTI)

    Green, Michael A.

    2007-08-27T23:59:59.000Z

    This paper is an update of papers written in 1991 and in1997 by Rod Byrns and this author concerning estimating the cost ofrefrigeration for superconducting magnets and cavities. The actual costsof helium refrigerators and coolers (escalated to 2007 dollars) areplotted and compared to a correlation function. A correlation functionbetween cost and refrigeration at 4.5 K is given. The capital cost oflarger refrigerators (greater than 10 W at 4.5 K) is plotted as afunction of 4.5-K cooling. The cost of small coolers is plotted as afunction of refrigeration available at 4.2 K. A correlation function forestimating efficiency (percent of Carnot) of both types of refrigeratorsis also given.

  12. Assessment of Impacts from Updating Iowa's Residential Energy Code to Comply with the 2003 International Energy Conservation Code

    SciTech Connect (OSTI)

    Lucas, Robert G.

    2003-10-31T23:59:59.000Z

    The state of Iowa currently requires that new buildings comply with the Council of American Building Officials? (CABO) 1992 Model Energy Code (MEC) (CABO 1992). CABO has been transformed into the International Code Council (ICC) and the MEC has been renamed the International Energy Conservation Code (IECC). The most recent edition of the code is the 2003 IECC (ICC 2003). Iowa?s Department of Natural Resources requested that the U.S. Department of Energy (DOE) compare the 1992 MEC with the 2003 IECC to estimate impacts from updating Iowa?s residential energy code to comply with the new code. Under DOE's direction, Pacific Northwest National Laboratory (PNNL) completed an assessment of the impacts from this potential code upgrade, including impacts on construction and energy consumption costs. This report is an update to a similar report completed by PNNL in 2002 (Lucas 2002) that compared the 1992 MEC to the 2000 IECC.

  13. Handles Revisited: Optimising Performance and Memory Costs in a Real-Time Collector

    E-Print Network [OSTI]

    Kent, University of

    Handles Revisited: Optimising Performance and Memory Costs in a Real-Time Collector Tomas Kalibera garbage collectors must update all references to ob- jects they move. Updating is a lengthy operation references have been updated which, in a real-time collector, must be done incrementally. One solution

  14. Cost-E ective Flow Table Designs for High-Speed Routers: Architecture and Performance Evaluation

    E-Print Network [OSTI]

    Xu, Jun "Jim"

    Cost-E#11;ective Flow Table Designs for High-Speed Routers: Architecture and Performance Evaluation State variables Service Parameters update read read Incoming packet action Search Y N Lookup Initialize to be performed (e.g., which output port to route the packet) on the packet and the new values the state variables

  15. Clean Coal Technology Programs: Program Update 2009

    SciTech Connect (OSTI)

    None

    2009-10-01T23:59:59.000Z

    The purpose of the Clean Coal Technology Programs: Program Update 2009 is to provide an updated status of the U.S. Department of Energy (DOE) commercial-scale demonstrations of clean coal technologies (CCT). These demonstrations have been performed under the Clean Coal Technology Demonstration Program (CCTDP), the Power Plant Improvement Initiative (PPII), and the Clean Coal Power Initiative (CCPI). Program Update 2009 provides: (1) a discussion of the role of clean coal technology demonstrations in improving the nation’s energy security and reliability, while protecting the environment using the nation’s most abundant energy resource—coal; (2) a summary of the funding and costs of the demonstrations; and (3) an overview of the technologies being demonstrated, along with fact sheets for projects that are active, recently completed, or recently discontinued.

  16. Clean coal technology programs: program update 2006

    SciTech Connect (OSTI)

    NONE

    2006-09-15T23:59:59.000Z

    The purpose of the Clean Coal Technology Programs: Program Update 2006 is to provide an updated status of the DOE commercial-scale demonstrations of clean coal technologies (CCTs). These demonstrations are performed under the Clean Coal Technology Demonstration Program (CCTDP), the Power Plant Improvement Initiative (PPII) and the Clean Coal Power Initiative (CCPI). Program Update 2006 provides 1) a discussion of the role of clean coal technology demonstrations in improving the nation's energy security and reliability, while protecting the environment using the nation's most abundant energy resource - coal; 2) a summary of the funding and costs of the demonstrations; and 3) an overview of the technologies being demonstrated, with fact sheets for demonstration projects that are active, recently completed, withdrawn or ended, including status as of June 30 2006. 4 apps.

  17. Cost Analysis of Fuel Cell Systems for Transportation Compressed Hydrogen and PEM Fuel Cell System

    SciTech Connect (OSTI)

    Eric J. Carlson

    2004-10-20T23:59:59.000Z

    PEMFC technology for transportation must be competitive with internal combustion engine powertrains in a number of key metrics, including performance, life, reliability, and cost. Demonstration of PEMFC cost competitiveness has its own challenges because the technology has not been applied to high volume automotive markets. The key stack materials including membranes, electrodes, bipolar plates, and gas diffusion layers have not been produced in automotive volumes to the exacting quality requirements that will be needed for high stack yields and to the evolving property specifications of high performance automotive stacks. Additionally, balance-of-plant components for air, water, and thermal management are being developed to meet the unique requirements of fuel cell systems. To address the question of whether fuel cells will be cost competitive in automotive markets, the DOE has funded this project to assess the high volume production cost of PEM fuel cell systems. In this report a historical perspective of our efforts in assessment of PEMFC cost for DOE is provided along with a more in-depth assessment of the cost of compressed hydrogen storage is provided. Additionally, the hydrogen storage costs were incorporated into a system cost update for 2004. Assessment of cost involves understanding not only material and production costs, but also critical performance metrics, i.e., stack power density and associated catalyst loadings that scale the system components. We will discuss the factors influencing the selection of the system specification (i.e., efficiency, reformate versus direct hydrogen, and power output) and how these have evolved over time. The reported costs reflect internal estimates and feedback from component developers and the car companies. Uncertainty in the cost projection was addressed through sensitivity analyses.

  18. Low-risk and cost-effective prior savings estimates for large-scale energy conservation projects in housing: Learning from the Fort Polk GHP project

    SciTech Connect (OSTI)

    Shonder, J.A.; Hughes, P.J. [Oak Ridge National Lab., TN (United States); Thornton, J.W. [Thermal Energy Systems Specialists, Inc., Madison, WI (United States)

    1997-08-01T23:59:59.000Z

    Many opportunities exist for large-scale energy conservation projects in housing. Energy savings performance contracting (ESPC) is now receiving greater attention, as a means to implement such projects. This paper proposes an improved method for prior (to construction) savings estimates for these projects. The proposed approach to prior estimates is verified against data from Fort Polk, LA. In the course of evaluating the ESPC at Fort Polk, the authors have collected energy use data which allowed them to develop calibrated engineering models which accurately predict pre-retrofit energy consumption. They believe that such calibrated models could be used to provide much more accurate estimates of energy savings in retrofit projects. The improved savings estimating approach described here is based on an engineering model calibrated to field-collected data from the pre-retrofit period. A dynamic model of pre-retrofit energy use was developed for all housing and non-housing loads on a complete electrical feeder at Fort Polk. The model included the heat transfer characteristics of the buildings, the pre-retrofit air source heat pump, a hot water consumption model and a profile for electrical use by lights and other appliances. Energy consumption for all 200 apartments was totaled, and by adjusting thermostat setpoints and outdoor air infiltration parameters, the models were matched to field-collected energy consumption data for the entire feeder. The energy conservation measures were then implemented in the calibrated model: the air source heat pumps were replaced by geothermal heat pumps with desuperheaters; hot water loads were reduced to account for the low-flow shower heads; and lighting loads were reduced to account for fixture delamping and replacement with compact fluorescent lights. The analysis of pre- and post-retrofit data indicates that the retrofits have saved 30.3% of pre-retrofit electrical energy consumption on the feeder modeled in this paper.

  19. Valuing Rail Transit: Comparing Capital and Operating Costs to Consumer Benefits

    E-Print Network [OSTI]

    Guerra, Erick

    2010-01-01T23:59:59.000Z

    years gives an annual capital cost estimate of $321 million,further adjust the capital cost estimates for these systemscosts. In order to estimate capital costs for five systems

  20. How to Estimate the Value of Service Reliability Improvements

    E-Print Network [OSTI]

    Sullivan, Michael J.

    2010-01-01T23:59:59.000Z

    and costs per annual kWh. Cost estimates are provided forper event, costs per average kW, costs per un-served kWhinvestments: 1. Cost per un-served kWh is substantially

  1. Power Purchase Agreements Update

    Broader source: Energy.gov [DOE]

    Presentation covers an update on power purchase agreements and is given at the Spring 2011 Federal Utility Partnership Working Group (FUPWG) meeting.

  2. Electricity Monthly Update

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Electricity Monthly Update Explained Highlights The Highlights page features in the center a short article about a major event or an informative topic. The left column contains...

  3. Navy Technology Evaluation Update

    Broader source: Energy.gov [DOE]

    Presentation covers the Navy Technology Evaluation update at the Federal Utility Partnership Working Group (FUPWG) meeting, held on November 18-19, 2009.

  4. TINSSL Update | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    an electronic newsletter designed to help TINSSL members keep up to date on the latest SSL news and events. TINSSL Update, May 2014 TINSSL Update, March 2014 TINSSL Update,...

  5. Electric Turbo Compounding Technology Update

    Broader source: Energy.gov (indexed) [DOE]

    Turbo Compounding Technology Update Electric Turbo Compounding Technology Update 15 August, 2007 Carl Vuk 15 August, 2007 Carl Vuk Electric Turbo Compounding Highlights Electric...

  6. Determining the lowest-cost hydrogen delivery mode

    E-Print Network [OSTI]

    Yang, Christopher; Ogden, Joan M

    2007-01-01T23:59:59.000Z

    costs to estimate hydrogen pipeline costs. Davis, CA: ITS-hydrogen trucks, and hydrogen pipelines, were devel- opedFor large amounts of hydrogen, pipeline transmission is pre-

  7. Learning and cost reductions for generating technologies in the national energy modeling system (NEMS)

    E-Print Network [OSTI]

    Gumerman, Etan; Marnay, Chris

    2004-01-01T23:59:59.000Z

    of International Learning on Technology Cost. In Issues ofbetween initial new technology cost estimates and actualthe revolutionary technologies have cost reductions beyond

  8. Updated U.S. Geothermal Supply Characterization

    SciTech Connect (OSTI)

    Petty, S.; Porro, G.

    2007-03-01T23:59:59.000Z

    This paper documents the approach taken to characterize and represent an updated assessment of U.S. geothermal supply for use in forecasting the penetration of geothermal electrical generation in the National Energy Modeling System (NEMS). This work is motivated by several factors: The supply characterization used as the basis of several recent U.S. Department of Energy (DOE) forecasts of geothermal capacity is outdated; additional geothermal resource assessments have been published; and a new costing tool that incorporates current technology, engineering practices, and associated costs has been released.

  9. Costs Associated With Propane Vehicle Fueling Infrastructure

    SciTech Connect (OSTI)

    Smith, M.; Gonzales, J.

    2014-08-01T23:59:59.000Z

    This document is designed to help fleets understand the cost factors associated with propane vehicle fueling infrastructure. It provides an overview of the equipment and processes necessary to develop a propane fueling station and offers estimated cost ranges.

  10. Realistic costs of carbon capture

    SciTech Connect (OSTI)

    Al Juaied, Mohammed (Harvard Univ., Cambridge, MA (US). Belfer Center for Science and International Affiaris); Whitmore, Adam (Hydrogen Energy International Ltd., Weybridge (GB))

    2009-07-01T23:59:59.000Z

    There is a growing interest in carbon capture and storage (CCS) as a means of reducing carbon dioxide (CO2) emissions. However there are substantial uncertainties about the costs of CCS. Costs for pre-combustion capture with compression (i.e. excluding costs of transport and storage and any revenue from EOR associated with storage) are examined in this discussion paper for First-of-a-Kind (FOAK) plant and for more mature technologies, or Nth-of-a-Kind plant (NOAK). For FOAK plant using solid fuels the levelised cost of electricity on a 2008 basis is approximately 10 cents/kWh higher with capture than for conventional plants (with a range of 8-12 cents/kWh). Costs of abatement are found typically to be approximately US$150/tCO2 avoided (with a range of US$120-180/tCO2 avoided). For NOAK plants the additional cost of electricity with capture is approximately 2-5 cents/kWh, with costs of the range of US$35-70/tCO2 avoided. Costs of abatement with carbon capture for other fuels and technologies are also estimated for NOAK plants. The costs of abatement are calculated with reference to conventional SCPC plant for both emissions and costs of electricity. Estimates for both FOAK and NOAK are mainly based on cost data from 2008, which was at the end of a period of sustained escalation in the costs of power generation plant and other large capital projects. There are now indications of costs falling from these levels. This may reduce the costs of abatement and costs presented here may be 'peak of the market' estimates. If general cost levels return, for example, to those prevailing in 2005 to 2006 (by which time significant cost escalation had already occurred from previous levels), then costs of capture and compression for FOAK plants are expected to be US$110/tCO2 avoided (with a range of US$90-135/tCO2 avoided). For NOAK plants costs are expected to be US$25-50/tCO2. Based on these considerations a likely representative range of costs of abatement from CCS excluding transport and storage costs appears to be US$100-150/tCO2 for first-of-a-kind plants and perhaps US$30-50/tCO2 for nth-of-a-kind plants.The estimates for FOAK and NOAK costs appear to be broadly consistent in the light of estimates of the potential for cost reductions with increased experience. Cost reductions are expected from increasing scale, learning on individual components, and technological innovation including improved plant integration. Innovation and integration can both lower costs and increase net output with a given cost base. These factors are expected to reduce abatement costs by approximately 65% by 2030. The range of estimated costs for NOAK plants is within the range of plausible future carbon prices, implying that mature technology would be competitive with conventional fossil fuel plants at prevailing carbon prices.

  11. Contracting with reading costs and renegotiation costs

    E-Print Network [OSTI]

    Brennan, James R.

    2007-01-01T23:59:59.000Z

    Reading Costs, Competition, and ContractReading Costs . . . . . . . . . . . . . . . . C. EquilibriumUnconscionability A?ect Reading Costs . . . . . . . . . .

  12. Manufacturing Cost Analysis for YSZ-Based FlexCells at Pilot and Full Scale Production Scales

    SciTech Connect (OSTI)

    Scott Swartz; Lora Thrun; Robin Kimbrell; Kellie Chenault

    2011-05-01T23:59:59.000Z

    Significant reductions in cell costs must be achieved in order to realize the full commercial potential of megawatt-scale SOFC power systems. The FlexCell designed by NexTech Materials is a scalable SOFC technology that offers particular advantages over competitive technologies. In this updated topical report, NexTech analyzes its FlexCell design and fabrication process to establish manufacturing costs at both pilot scale (10 MW/year) and full-scale (250 MW/year) production levels and benchmarks this against estimated anode supported cell costs at the 250 MW scale. This analysis will show that even with conservative assumptions for yield, materials usage, and cell power density, a cost of $35 per kilowatt can be achieved at high volume. Through advancements in cell size and membrane thickness, NexTech has identified paths for achieving cell manufacturing costs as low as $27 per kilowatt for its FlexCell technology. Also in this report, NexTech analyzes the impact of raw material costs on cell cost, showing the significant increases that result if target raw material costs cannot be achieved at this volume.

  13. The Product Oriented Design and Construction (PODAC) Cost Model

    E-Print Network [OSTI]

    from one rate year to another 5.2. Product Variations 5.2.1. Modify the Cost Item cost data 5 cost data 5.3.2. Modifying labor-hour estimates, labor costs, or material costs 5.3.3. ChangingThe Product Oriented Design and Construction (PODAC) Cost Model A Proposed Procedure for Product

  14. Supporting Documentation for the 2008 Update to the Insulation Fact Sheet

    SciTech Connect (OSTI)

    Stovall, Therese K [ORNL

    2008-02-01T23:59:59.000Z

    The Insulation Fact Sheet provides consumers for general guidance and recommended insulation levels for their home. This fact sheet has been on-line since 1995 and this update addresses new insulation materials, as well as updated costs for energy and materials.

  15. Startup Costs - DOE Directives, Delegations, and Requirements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    and environmental projects, and estimating guidance for startup costs. g4301-1chp8.pdf -- PDF Document, 8 KB Writer: John Makepeace Subjects: Administration Management...

  16. Updated Higgs cross section at approximate N$^3$LO

    E-Print Network [OSTI]

    Marco Bonvini; Richard D. Ball; Stefano Forte; Simone Marzani; Giovanni Ridolfi

    2014-07-03T23:59:59.000Z

    We update our estimate of the cross section for Higgs production in gluon fusion at next-to-next-to-next-to-leading order (N$^3$LO) in $\\alpha_s$ in view of the recent full computation of the result in the soft limit for infinite top mass, which determines a previously unknown constant. We briefly discuss the phenomenological implications. Results are available through the updated version of the ggHiggs code.

  17. Cost Improvements, Returns to Scale, and Cost Inefficiencies for Real Estate Investment Trusts*

    E-Print Network [OSTI]

    Ahmad, Sajjad

    ) operating efficiencies. We estimate stochastic-frontier, panel-data models specifying a translog cost of the competitive advantage include economies of scale, lower capital costs, and superior sources of capital. Specifying a translog cost function and using 1995 to 2003 data, we estimate a stochastic-frontier panel

  18. FUPWG Spring 2010 Providence: Washington Update | Department...

    Energy Savers [EERE]

    Spring 2010 Providence: Washington Update FUPWG Spring 2010 Providence: Washington Update Presentation covers an update on Washington and is given at the Spring 2010 Federal...

  19. Policy Flash 2014-37 Update to the Department of Energy Acquisition...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    and Measurement Plans for Cost-Reimbursement, Non-Management and Operating Contracts Policy Flash 2014-37 Update to the Department of Energy Acquisition Guide Chapter 16.2,...

  20. PPA Tools and Update

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    PPA Tools & Update Chandra Shah chandra.shah@nel.gov October 21, 2010 2 | FEDERAL ENERGY MANAGEMENT PROGRAM femp.energy.gov * PPA (15 minutes) - Resources - Discussion * URESC (15...

  1. Fuel Cell System Cost for Transportation-2008 Cost Estimate (Book)

    SciTech Connect (OSTI)

    Not Available

    2009-05-01T23:59:59.000Z

    Independent review prepared for the U.S. Department of Energy (DOE) Hydrogen, Fuel Cells and Infrastructure Technologies (HFCIT) Program Manager.

  2. INDEPENDENT COST REVIEW (ICR) and INDEPENDENT COST ESTIMATE (ICE) Standard

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33Frequently20,000 RussianBy: Thomas P.Department of Energy InternetHydrogenApril 30, link

  3. The costs of environmental regulation in a concentrated industry

    E-Print Network [OSTI]

    Ryan, Stephen

    2005-01-01T23:59:59.000Z

    The typical cost analysis of an environmental regulation consists of an engineering estimate of the compliance costs. In industries where fixed costs are an important determinant of market structure this static analysis ...

  4. The Costs of Environmental Regulation in a Concentrated Industry

    E-Print Network [OSTI]

    Ryan, Stephen

    The typical cost analysis of an environmental regulation consists of an engineering estimate of the compliance costs. In industries where fixed costs are an important determinant of market structure, this static analysis ...

  5. Selective Reporting and the Social Cost of Carbon

    E-Print Network [OSTI]

    Havranek, Tomas; Irsova, Zuzana; Janda, Karel; Zilberman, David

    2014-01-01T23:59:59.000Z

    estimating the social cost of carbon. meta-analysis.cz/scc.Formula for the Social Cost of Carbon. ” Working PaperP. Watkiss (2005): “Social Cost of Carbon: A Closer Look at

  6. Department of Energy Environmental Management cost infrastructure development program: Cost analysis requirements

    SciTech Connect (OSTI)

    Custer, W.R. Jr.; Messick, C.D.

    1996-03-31T23:59:59.000Z

    This report was prepared to support development of the Department of Energy Environmental Management cost infrastructure -- a new capability to independently estimate and analyze costs. Currently, the cost data are reported according to a structure that blends level of effort tasks with product and process oriented tasks. Also. the budgetary inputs are developed from prior year funding authorizations and from contractor-developed parametric estimates that have been adjusted to planned funding levels or appropriations. Consequently, it is difficult for headquarters and field-level activities to use actual cost data and technical requirements to independently assess the costs generated and identify trends, potential cost savings from process improvements, and cost reduction strategies.

  7. Weighing the Costs and Benefits of Renewables Portfolio Standards: A Comparative Analysis of State-Level Policy Impact Projections

    E-Print Network [OSTI]

    Chen, Cliff; Wiser, Ryan; Bolinger, Mark

    2007-01-01T23:59:59.000Z

    data, the highest capital cost estimate in the 2010-2015multiply initial capital cost estimates by up to a factor ofand projected wind capital cost estimates from EPRI/DOE

  8. Air, High Speed Rail, or Highway: A Cost Comparison in the California Corridor

    E-Print Network [OSTI]

    Levinson, David M.

    these reduced social costs offset rail's high capital and operating costs. The development of cost estimates, any of these three modes. In this study we include estimates of four types of external, social costs design characteristics observed in the California corridor. We estimate rail costs with models adapted

  9. Abstract--This paper describes an approach for choosing and updating measurement weights used in weighted least squares

    E-Print Network [OSTI]

    -- Auto Tuning; Measurement Weights; Power System State Estimation; Random Error Variances. I is not always true. M is used for estimating measurement e1 Abstract--This paper describes an approach for choosing and updating measurement weights used

  10. Cash Flow and Discount Rate news estimation: which method to choose?

    E-Print Network [OSTI]

    Khimich, Natalya V.

    2012-01-01T23:59:59.000Z

    form the VAR method . Implied Cost of Capital estimates byt+1 . TABLE 3: Cost of Capital Estimates by Year Year Numberdifferent estimates of the implied cost of capital. See

  11. Hurricane Katrina, A Climatological Perspective October 2005, Updated August 2006

    E-Print Network [OSTI]

    #12;1 Hurricane Katrina, A Climatological Perspective October 2005, Updated August 2006 1. Introduction Hurricane Katrina is the most costly natural disaster ever to strike the United States, and the deadliest since the Lake Okeechobee disaster (hurricane) of September, 1928. In addition, Katrina was one

  12. Updated 11.17.14 JM UNIVERSITY OF CALIFORNIA

    E-Print Network [OSTI]

    California at Santa Cruz, University of

    Updated 11.17.14 JM UNIVERSITY OF CALIFORNIA OFFICE OF THE CHIEF INVESTMENT OFFICER 1111 BROADWAY of securities or mutual funds to benefit UC Santa Cruz. The UC Office of the Chief Investment Officer provides broker services for securities and mutual fund gifts to the UC Santa Cruz Foundation at no cost. By using

  13. Updating Small Generator Interconnection Procedures for New Market Conditions

    SciTech Connect (OSTI)

    Coddington, M.; Fox, K.; Stanfield, S.; Varnado, L.; Culley, T.; Sheehan, M.

    2012-12-01T23:59:59.000Z

    Federal and state regulators are faced with the challenge of keeping interconnection procedures updated against a backdrop of evolving technology, new codes and standards, and considerably transformed market conditions. This report is intended to educate policymakers and stakeholders on beneficial reforms that will keep interconnection processes efficient and cost-effective while maintaining a safe and reliable power system.

  14. On the relation between expected returns and implied cost of capital

    E-Print Network [OSTI]

    Hughes, John; Liu, Jing; Liu, Jun

    2009-01-01T23:59:59.000Z

    coef?cient estimate on implied cost of capital to be biased.the implied cost of capital literature estimates of the exestimates of ex ante risk premiums inferred from implied cost of capital

  15. An Assessment of the Near-Term Costs of Hydrogen Refueling Stations and Station Components

    E-Print Network [OSTI]

    Lipman, T E; Weinert, Jonathan X.

    2006-01-01T23:59:59.000Z

    Installed Capital Figure 4-21: Cost Estimates for 1,000 kg/station. H2Gen’s estimates for capital costs are also lowerestimates and show high variability (26%-117% of capital costs).

  16. Smart Buildings: Business Case and Action Plan

    E-Print Network [OSTI]

    Ehrlich, Paul

    2009-01-01T23:59:59.000Z

    Subtotal  Estimated Investment: Costs, Assumptions and 22   Part 3. Costs, Investment, andresponse. Part 3. Costs, Investment and Savings • Updated

  17. Academy Member Annual Update Report 1Academy Member Update Report

    E-Print Network [OSTI]

    Academy Member Annual Update Report 1Academy Member Update Report The annual update report is an important activity associated with active membership in the Academy. These reports are due annually@lsuhsc.edu or call 504-568-2140 if you have other questions. Why an annual report? As an Academy member

  18. IFE Target Fabrication, Delivery, and Cost Estimates

    E-Print Network [OSTI]

    synergism but key differences that lead to specific technologies Heavy Ion Fusion Laser Fusion Z-Pinch IFE of this talk....... 1. IFE target technology builds upon the larger ICF program - Not starting from "zero" for IFE - Large effort for NIC fosters efficiency (e.g., foam shells) 2. The recent IFE target technology

  19. June 5, 2001 1 FIRE Cost Estimate

    E-Print Network [OSTI]

    $177.3M4 ­ Power Systems $26.9M$4.9M$22.0M3 ­ Diagnostic Systems $178.1M$42.5M$135.6M2 ­ Auxiliary.6 ­ Hot Cell Facility Remote Handling $19.7MWBS 7.5 ­ Remote Handling Systems $5.9MWBS 2.4 ­ RF Heating & Current Drive $1.1MWBS 2.2 ­ Vacuum Pumping Systems $0.1MWBS 2.1 ­ Gas & Pellet Fueling Systems FY99M$ (w

  20. Estimated Costs of Pasture and Hay Production

    E-Print Network [OSTI]

    Duffy, Michael D.

    , when developed with moderate success, and with good grazing management practices, can be expected Recommendations in Iowa, and WC-92, Herbicide Manual for Agricultural Professionals. Complete renovation

  1. Estimating the Economic Costs of Espionage

    E-Print Network [OSTI]

    Bell, Rich; Bennett, J. Ethan; Boles, Jillian R.; Goodoien, David M.; Irving, Jeff W.; Kuhlman, Phillip B.; White, Amanda K.

    2010-01-01T23:59:59.000Z

    , could be used in different products and in different industries. The loss of a trade secret is an immeasurable value. Instead of attempting to measure such an overarching elusive concept, the research team sought to measure the potential... corresponds to a „low?, „moderate?, and „high? consequence. The severity score incorporates the model?s four main variables into two primary components: „Industry? and „Case Variables?. „Industry? assesses the significance of where the incident...

  2. Cost estimation of human systems integration

    E-Print Network [OSTI]

    Liu, Kevin K. (Kevin Kaitan), 1986-

    2010-01-01T23:59:59.000Z

    Human Systems Integration (HSI) is the interdisciplinary technical and management processes for integrating human considerations within and across all system elements. The goal of this research is to develop a better ...

  3. Process Equipment Cost Estimation, Final Report

    Office of Scientific and Technical Information (OSTI)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOn AprilAElectronicCurvesSpeedingScientificof Scientific andPredictive Models ofl* t ,

  4. Program Review Updates and Briefings

    Broader source: Energy.gov [DOE]

    You can learn more about the U.S. Department of Energy (DOE) Geothermal Technologies Program by reading its program review updates and program briefings. These updates and briefings feature...

  5. Building Distributed Energy Performance Optimization for China a Regional Analysis of Building Energy Costs and CO2 Emissions

    E-Print Network [OSTI]

    Feng, Wei

    2013-01-01T23:59:59.000Z

    electricity tariff, technology costs, and governmenttariff Natural gas tariff Technology costs and financialand estimated the technology costs in the current Chinese

  6. Renewable Portfolio Standards: Costs and Benefits (Poster)

    SciTech Connect (OSTI)

    Bird, L.; Heeter, J.; Barbose, G.; Weaver, S.; Flores, F.; Kuskova-Burns, K.; Wiser, R.

    2014-10-01T23:59:59.000Z

    This report summarizes state-level RPS costs to date, and considers how those costs may evolve going forward given scheduled increases in RPS targets and cost containment mechanisms. The report also summarizes RPS benefits estimates, based on published studies for individual states and discusses key methodological considerations.

  7. HIGH SPEED RAIL COSTS, BENEFITS, AND FINANCING RAYMOND H. ELLIS

    E-Print Network [OSTI]

    Bustamante, Fabián E.

    Corridor PHASE 1 ­ TAMPA TO ORLANDO #12;FLORIDA TAMPA ­ ORLANDO (PHASE 1) HSR CAPITAL COST · Estimated Incremental Capital Cost Capital Cost Year of (Billions (Billions Completion Expenditure Section 2010$) 2010$) of Section Capital Cost #12;CALIFORNIA HIGH SPEED RAIL PHASE 1 CAPITAL COSTS SECTION INCREMENTAL CAPITAL

  8. Richmond Bay Campus: Project Update

    E-Print Network [OSTI]

    Lee, Jason R.

    Coordinate with City of Richmond South Shoreline Area planning #12;Richmond Bay Campus Vision A stateRichmond Bay Campus: Project Update Prepared for the Richmond City Council October 1, 2013 #12 and UCB · City of Richmond Updates · Summary · Questions & Answers #12;LBNL Project Update #12;University

  9. Information Updates: Position/Title

    E-Print Network [OSTI]

    Sheridan, Jennifer

    Information Updates: Name: Position/Title: Business Mailing Address: Home Mailing Address: Phone of nurse involvement and patient education. She is an active nurse leader that brings thoughtful discussion be a chapter update for upcoming future events and plans for the future. Don't miss this exciting update! Beta

  10. CAC Update: HFBR and BGRR

    E-Print Network [OSTI]

    Homes, Christopher C.

    rod blades and casks has been installed and tested #12;HFBR Update #12;HFBR Update Personnel have been on procedures for completing the work · Drills and dry-runs have been conducted to develop worker proficiency under normal and off-normal conditions #12;HFBR Update Transportation cask Certificates of Compliance

  11. Advanced Fuel Cycle Cost Basis

    SciTech Connect (OSTI)

    D. E. Shropshire; K. A. Williams; W. B. Boore; J. D. Smith; B. W. Dixon; M. Dunzik-Gougar; R. D. Adams; D. Gombert; E. Schneider

    2009-12-01T23:59:59.000Z

    This report, commissioned by the U.S. Department of Energy (DOE), provides a comprehensive set of cost data supporting a cost analysis for the relative economic comparison of options for use in the Advanced Fuel Cycle Initiative (AFCI) Program. The report describes the AFCI cost basis development process, reference information on AFCI cost modules, a procedure for estimating fuel cycle costs, economic evaluation guidelines, and a discussion on the integration of cost data into economic computer models. This report contains reference cost data for 25 cost modules—23 fuel cycle cost modules and 2 reactor modules. The cost modules were developed in the areas of natural uranium mining and milling, conversion, enrichment, depleted uranium disposition, fuel fabrication, interim spent fuel storage, reprocessing, waste conditioning, spent nuclear fuel (SNF) packaging, long-term monitored retrievable storage, near surface disposal of low-level waste (LLW), geologic repository and other disposal concepts, and transportation processes for nuclear fuel, LLW, SNF, transuranic, and high-level waste.

  12. Advanced Fuel Cycle Cost Basis

    SciTech Connect (OSTI)

    D. E. Shropshire; K. A. Williams; W. B. Boore; J. D. Smith; B. W. Dixon; M. Dunzik-Gougar; R. D. Adams; D. Gombert; E. Schneider

    2008-03-01T23:59:59.000Z

    This report, commissioned by the U.S. Department of Energy (DOE), provides a comprehensive set of cost data supporting a cost analysis for the relative economic comparison of options for use in the Advanced Fuel Cycle Initiative (AFCI) Program. The report describes the AFCI cost basis development process, reference information on AFCI cost modules, a procedure for estimating fuel cycle costs, economic evaluation guidelines, and a discussion on the integration of cost data into economic computer models. This report contains reference cost data for 25 cost modules—23 fuel cycle cost modules and 2 reactor modules. The cost modules were developed in the areas of natural uranium mining and milling, conversion, enrichment, depleted uranium disposition, fuel fabrication, interim spent fuel storage, reprocessing, waste conditioning, spent nuclear fuel (SNF) packaging, long-term monitored retrievable storage, near surface disposal of low-level waste (LLW), geologic repository and other disposal concepts, and transportation processes for nuclear fuel, LLW, SNF, transuranic, and high-level waste.

  13. Advanced Fuel Cycle Cost Basis

    SciTech Connect (OSTI)

    D. E. Shropshire; K. A. Williams; W. B. Boore; J. D. Smith; B. W. Dixon; M. Dunzik-Gougar; R. D. Adams; D. Gombert

    2007-04-01T23:59:59.000Z

    This report, commissioned by the U.S. Department of Energy (DOE), provides a comprehensive set of cost data supporting a cost analysis for the relative economic comparison of options for use in the Advanced Fuel Cycle Initiative (AFCI) Program. The report describes the AFCI cost basis development process, reference information on AFCI cost modules, a procedure for estimating fuel cycle costs, economic evaluation guidelines, and a discussion on the integration of cost data into economic computer models. This report contains reference cost data for 26 cost modules—24 fuel cycle cost modules and 2 reactor modules. The cost modules were developed in the areas of natural uranium mining and milling, conversion, enrichment, depleted uranium disposition, fuel fabrication, interim spent fuel storage, reprocessing, waste conditioning, spent nuclear fuel (SNF) packaging, long-term monitored retrievable storage, near surface disposal of low-level waste (LLW), geologic repository and other disposal concepts, and transportation processes for nuclear fuel, LLW, SNF, and high-level waste.

  14. State Energy Price System: 1982 update

    SciTech Connect (OSTI)

    Imhoff, K.L.; Fang, J.M.

    1984-10-01T23:59:59.000Z

    The State Energy Price System (STEPS) contains estimates of energy prices for ten major fuels (electricity, natural gas, metallurgical coal, steam coal, distillate, motor gasoline, diesel, kerosene/jet fuel, residual fuel, and liquefied petroleum gas), by major end-use sectors (residential, commercial, industrial, transportation, and electric utility), and by state through 1982. Both physical unit prices and prices per million Btu are included in STEPS. Major changes in STEPS data base for 1981 and 1982 are described. The most significant changes in procedures for the updates occur in the residential sector distillate series and the residential sector kerosene series. All physical unit and Btu prices are shown with three significant digits instead of with four significant digits as shown in the original documentation. Details of these and other changes are contained in this report, along with the updated data files. 31 references, 65 tables.

  15. WECC and Peak Update

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    WECC and Peak Update Transmission B O N N E V I L L E P O W E R A D M I N I S T R A T I O N Pre-decisional. For Discussion Purposes Only. WECC and Peak Background In the...

  16. RESEARCH UPDATE Ecology Division

    E-Print Network [OSTI]

    1 RESEARCH UPDATE Ecology Division Biotype has changed its name to Ecotype! Following the re-organisation of Forest Research into five science Divisions and three Support Divisions, the former Woodland Ecology Branches to form the new Ecology Division. We decided to give the divisional newsletter a new name (and

  17. When Equal is Not Equitable: Adjusting for Geographic Differences in Education Costs

    E-Print Network [OSTI]

    Taylor, Lori L.

    cost differences into its school funding formula with the Texas Cost of Education Index (CEI), but the CEI has not been updated since its creation 25 years ago. The pattern of costs has shifted dramatically in Texas since then and school districts face...

  18. Reassessing Wind Potential Estimates for India: Economic and Policy Implications

    E-Print Network [OSTI]

    Phadke, Amol

    2012-01-01T23:59:59.000Z

    MW installed worldwide. 6 Wind energy costs in India areWe estimate the cost of wind energy and compare it with

  19. Cost Accounting System for fusion studies

    SciTech Connect (OSTI)

    Hamilton, W.R.; Keeton, D.C.; Thomson, S.L.

    1985-12-01T23:59:59.000Z

    A Cost Accounting System that is applicable to all magnetic fusion reactor design studies has been developed. This system provides: (1) definitions of the elements of cost and methods for the combination of these elements to form a cost estimate; (2) a Code of Accounts that uses a functional arrangement for identification of the plant components; and (3) definitions and methods to analyze actual cost data so that the data can be directly reported into this Cost Accounting System. The purpose of the Cost Accounting System is to provide the structure for the development of a fusion cost data base and for the development of validated cost estimating procedures. This system has been developed through use at the Fusion Engineering Design Center (FEDC) and has been applied to different confinement concepts (tokamaks and tandem mirrors) and to different types of projects (experimental devices and commercial power plants). The use of this Cost Accounting System by all magnetic fusion projects will promote the development of a common cost data base, allow the direct comparison of cost estimates, and ultimately establish the cost credibility of the program.

  20. LeZi-Update: An Information-Theoretic Approach to Track Mobile Users in PCS Networks*

    E-Print Network [OSTI]

    Bhattacharya, Amiya

    -to-fixed length encoding of the acclaimed Lempel- Ziv family of algorithms reduces the update cost, whereas their built-in predictive power can be effectively used to re- duce paging cost. 1 Introduction Seamless, while enjoy- ing the freedom of being mobile, the user creates an un- certainty about the exact location

  1. Fourth update of the Energy Economic Data Base (EEDB) Program. Phase IV, Final report. Volume I

    SciTech Connect (OSTI)

    Allen, R.E.; Brown, P.E.; Kaminski, R.S.; Smith, M.H.; Ziegler, E.J.

    1981-09-01T23:59:59.000Z

    EEDB deals with the development of cost data for nuclear and comparison electric power plants. Its objective is to provide periodic updates of technical and cost (capital, fuel and operating and maintenance) information for use in evaluating and monitoring US civilian nuclear power programs. It contains six nuclear power plant technical models and five comparison coal-fired fossil power plant technical models. (DLC)

  2. Optimal Bayesian experimental design for contaminant transport parameter estimation

    E-Print Network [OSTI]

    Tsilifis, Panagiotis; Hajali, Paris

    2015-01-01T23:59:59.000Z

    Experimental design is crucial for inference where limitations in the data collection procedure are present due to cost or other restrictions. Optimal experimental designs determine parameters that in some appropriate sense make the data the most informative possible. In a Bayesian setting this is translated to updating to the best possible posterior. Information theoretic arguments have led to the formation of the expected information gain as a design criterion. This can be evaluated mainly by Monte Carlo sampling and maximized by using stochastic approximation methods, both known for being computationally expensive tasks. We propose an alternative framework where a lower bound of the expected information gain is used as the design criterion. In addition to alleviating the computational burden, this also addresses issues concerning estimation bias. The problem of permeability inference in a large contaminated area is used to demonstrate the validity of our approach where we employ the massively parallel vers...

  3. Heliostat cost reduction study.

    SciTech Connect (OSTI)

    Jones, Scott A.; Lumia, Ronald. (University of New Mexico, Albuquerque, NM); Davenport, Roger (Science Applications International Corporation, San Diego, CA); Thomas, Robert C. (Advanced Thermal Systems, Centennial, CO); Gorman, David (Advanced Thermal Systems, Larkspur, CO); Kolb, Gregory J.; Donnelly, Matthew W.

    2007-06-01T23:59:59.000Z

    Power towers are capable of producing solar-generated electricity and hydrogen on a large scale. Heliostats are the most important cost element of a solar power tower plant. Since they constitute {approx} 50% of the capital cost of the plant it is important to reduce heliostat cost as much as possible to improve the economic performance of power towers. In this study we evaluate current heliostat technology and estimate a price of $126/m{sup 2} given year-2006 materials and labor costs for a deployment of {approx}600 MW of power towers per year. This 2006 price yields electricity at $0.067/kWh and hydrogen at $3.20/kg. We propose research and development that should ultimately lead to a price as low as $90/m{sup 2}, which equates to $0.056/kWh and $2.75/kg H{sup 2}. Approximately 30 heliostat and manufacturing experts from the United States, Europe, and Australia contributed to the content of this report during two separate workshops conducted at the National Solar Thermal Test Facility.

  4. Ionosphere Threat to LAAS: Updated Model, User Impact, and Mitigations

    E-Print Network [OSTI]

    Stanford University

    1 Ionosphere Threat to LAAS: Updated Model, User Impact, and Mitigations Ming Luo, Sam Pullen-4], a "linear spatial gradient front" model was established and a threat space was extrapolated based on data from the 6 April 2000 ionospheric storm. User vertical error was estimated based on this threat model

  5. HTGR Cost Model Users' Manual

    SciTech Connect (OSTI)

    A.M. Gandrik

    2012-01-01T23:59:59.000Z

    The High Temperature Gas-Cooler Reactor (HTGR) Cost Model was developed at the Idaho National Laboratory for the Next Generation Nuclear Plant Project. The HTGR Cost Model calculates an estimate of the capital costs, annual operating and maintenance costs, and decommissioning costs for a high-temperature gas-cooled reactor. The user can generate these costs for multiple reactor outlet temperatures; with and without power cycles, including either a Brayton or Rankine cycle; for the demonstration plant, first of a kind, or nth of a kind project phases; for a single or four-pack configuration; and for a reactor size of 350 or 600 MWt. This users manual contains the mathematical models and operating instructions for the HTGR Cost Model. Instructions, screenshots, and examples are provided to guide the user through the HTGR Cost Model. This model was design for users who are familiar with the HTGR design and Excel. Modification of the HTGR Cost Model should only be performed by users familiar with Excel and Visual Basic.

  6. Updated Buildings Sector Appliance and Equipment Costs and Efficiency

    Annual Energy Outlook 2013 [U.S. Energy Information Administration (EIA)]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 111 1,613 122 40Coal Stocks at Commercial and InstitutionalArea:Mnt(N) COFeet) Decade3445Full

  7. Updated Buildings Sector Appliance and Equipment Costs and Efficiency

    Annual Energy Outlook 2013 [U.S. Energy Information Administration (EIA)]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 111 1,613 122 40Coal Stocks at Commercial and InstitutionalArea:Mnt(N) COFeet)

  8. Updated Buildings Sector Appliance and Equipment Costs and Efficiency

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What'sis Taking Over OurThe Iron SpinPrinceton PlasmaAfternoon TalksDigitalRevision toNetworkMay 9,Full

  9. Updated Costs (June 2011 Basis) for Selected Bituminous Baseline Cases

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What'sis Taking Over OurThe Iron SpinPrinceton PlasmaAfternoon TalksDigitalRevision

  10. Updated Cost Analysis of Photobiological Hydrogen Production from

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your DensityEnergy U.S.-China Electric Vehicle and03/02 TUE 08:59 FAX 423Department ofChlamydomonas reinhardtii

  11. Calculating Costs for Quality of Security Service Evdoxia Spyropoulou

    E-Print Network [OSTI]

    utilization costs. The estimated costs can be fed into a resource management system to facilitate the process the design of the QoSS costing demonstration, which we believe is suitable for incorporation into a resource resource availability. As part of the process of estimating efficient task schedules, the RMS must balance

  12. Cost Sharing What is Cost Sharing?

    E-Print Network [OSTI]

    Tsien, Roger Y.

    sharing using various data fields (bin, fund, PI, index, etc.) x Create a Bin Generate a bin where cost;3 Cost Sharing Steps Search for & Create a Bin Search Results Display Select AWARD Type the correct data1 Cost Sharing What is Cost Sharing? x Cost sharing is a commitment to use university resources

  13. Texas Electricity Update

    E-Print Network [OSTI]

    Lloyd, B.

    2012-01-01T23:59:59.000Z

    Texas Electricity Update CATEE 2012 Galveston, Texas Brian Lloyd Executive Director Public Utility Commission of Texas October 10, 2012 1 2 Drought Summary May Reserve Margin Report 3 Demand Growth by Region 4 105? Normal... 917 Firm Load Forecast, MW 65,649 68,403 71,692 73,957 75,360 76,483 CATEE 2012 Questions? Brian H. Lloyd Executive Director Public Utility Commission of Texas 512-936-7040 14 ...

  14. Electricity Monthly Update

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    End Use: December 2014 Retail ratesprices and consumption In this section, we look at what electricity costs and how much is purchased. Charges for retail electric service are...

  15. Download Data | Transparent Cost Database

    Open Energy Info (EERE)

    You are here Home Download Data Click to download data from the following areas: Generation data - last updated November 14, 2014. Fuels data - last updated August 8, 2014....

  16. Update of Part 61 Impacts Analysis Methodology. Methodology report. Volume 1

    SciTech Connect (OSTI)

    Oztunali, O.I.; Roles, G.W.

    1986-01-01T23:59:59.000Z

    Under contract to the US Nuclear Regulatory Commission, the Envirosphere Company has expanded and updated the impacts analysis methodology used during the development of the 10 CFR Part 61 rule to allow improved consideration of the costs and impacts of treatment and disposal of low-level waste that is close to or exceeds Class C concentrations. The modifications described in this report principally include: (1) an update of the low-level radioactive waste source term, (2) consideration of additional alternative disposal technologies, (3) expansion of the methodology used to calculate disposal costs, (4) consideration of an additional exposure pathway involving direct human contact with disposed waste due to a hypothetical drilling scenario, and (5) use of updated health physics analysis procedures (ICRP-30). Volume 1 of this report describes the calculational algorithms of the updated analysis methodology.

  17. Progress Update: TRU Waste Shipping

    ScienceCinema (OSTI)

    Cody, Tom

    2012-06-14T23:59:59.000Z

    A progress update at the Savannah River Site. A continued effort on shipping TRU waste to WIPP in Carlsbad, New Mexico.

  18. Agricultural and Resource Economics Update

    E-Print Network [OSTI]

    2012-01-01T23:59:59.000Z

    Consumer Choices of Genetically Modified Food. ” ARE UpdateConsumer Choices of Genetically Modified Food Amir HeimanConsumer Choices of Genetically Modified Food Amir Heiman

  19. Agricultural and Resource Economics Update

    E-Print Network [OSTI]

    Lee, Hyunok; Sumner, Daniel A.; Martin, Philip; Hochman, Gal; Rajagopal, Deepak; Zilberman, David

    2011-01-01T23:59:59.000Z

    Environmental Impact of Biofuels. ” ARE Update 15(2):9-11.and the Environmental Impact of Biofuels Gal Hochman, Deepakand the Environmental Impact of Biofuels Gal Hochman, Deepak

  20. Agricultural and Resource Economics Update

    E-Print Network [OSTI]

    2012-01-01T23:59:59.000Z

    Analysis for Evaluating Biofuels. ” ARE Update 11(3) (2008):the RFS conventional biofuels mandate is severely harmingThe first is growth in biofuels demand. Notably, corn

  1. The Cost of Debt Jules H. van Binsbergen

    E-Print Network [OSTI]

    § This version: January 2008 Abstract We estimate firm-specific cost of corporate debt functions for thousands of debt benefit curves. By integrating the area between the benefit and cost functions we estimate in capital structure policies by studying the signs of estimated slope coefficients for factors such as firm

  2. Employee Replacement Costs

    E-Print Network [OSTI]

    Dube, Arindrajit; Freeman, Eric; Reich, Michael

    2010-01-01T23:59:59.000Z

    Samuel Schenker, “The Costs of Hir- u ing Skilled Workers”,Employee Replacement Costs Arindrajit Dube, Eric Freeman andof employee replacement costs, using a panel survey of

  3. Employee Replacement Costs

    E-Print Network [OSTI]

    Dube, Arindrajit; Freeman, Eric; Reich, Michael

    2010-01-01T23:59:59.000Z

    Employee Replacement Costs Arindrajit Dube, Eric Freeman andproperties of employee replacement costs, using a panel2008. We establish that replacement costs are sub- stantial

  4. Technical and Cost Assessment of the PCAST Machine

    E-Print Network [OSTI]

    ANNEX I - ITER DATA SHEETS ANNEX II - DERIVATION OF COST SCALINGS AND ESTIMATES ANNEX III - DERIVATION wherever approp.nate and to use the data from other projects for deriving cost scalings ir, areas where the cost data bases of three recently baselined fusion devices; ITER, BPX, and TPX Cost scaling, as opposed

  5. Cost uncertainty for different levels of technology maturity

    SciTech Connect (OSTI)

    DeMuth, S.F. [Los Alamos National Lab., NM (United States); Franklin, A.L. [Pacific Northwest National Lab., Richland, WA (United States)

    1996-08-07T23:59:59.000Z

    It is difficult at best to apply a single methodology for estimating cost uncertainties related to technologies of differing maturity. While highly mature technologies may have significant performance and manufacturing cost data available, less well developed technologies may be defined in only conceptual terms. Regardless of the degree of technical maturity, often a cost estimate relating to application of the technology may be required to justify continued funding for development. Yet, a cost estimate without its associated uncertainty lacks the information required to assess the economic risk. For this reason, it is important for the developer to provide some type of uncertainty along with a cost estimate. This study demonstrates how different methodologies for estimating uncertainties can be applied to cost estimates for technologies of different maturities. For a less well developed technology an uncertainty analysis of the cost estimate can be based on a sensitivity analysis; whereas, an uncertainty analysis of the cost estimate for a well developed technology can be based on an error propagation technique from classical statistics. It was decided to demonstrate these uncertainty estimation techniques with (1) an investigation of the additional cost of remediation due to beyond baseline, nearly complete, waste heel retrieval from underground storage tanks (USTs) at Hanford; and (2) the cost related to the use of crystalline silico-titanate (CST) rather than the baseline CS100 ion exchange resin for cesium separation from UST waste at Hanford.

  6. 1 POSTGRADUATE SCHOLARSHIPS UPDATE -July -August 2014 Postgraduate Scholarships Update

    E-Print Network [OSTI]

    Frean, Marcus

    - August 2014 ADDRESSENQUIRIESAND YOURCOMPLETEDFORMTO: SCHOLARSHIPSMANAGER ScholarshipsOffice Victoria1 POSTGRADUATE SCHOLARSHIPS UPDATE - July - August 2014 Postgraduate Scholarships Update JulyUniversityofWellington POBox600 Wellington6140 NewZealand PHONE +64-4-4635113 EMAIL scholarships-office@vuw.ac.nz WEBSITE www.victoria

  7. Transition-cost issues for a restructuring US electricity industry

    SciTech Connect (OSTI)

    NONE

    1997-03-01T23:59:59.000Z

    Utilities regulators can use a variety of approaches to calculate transition costs. We categorized these approaches along three dimensions. The first dimension is the use of administrative vs. market procedures to value the assets in question. Administrative approaches use analytical techniques to estimate transition costs. Market valuation relies on the purchase price of particular assets to determine their market values. The second dimension concerns when the valuation is done, either before or after the restructuring of the electricity industry. The third dimension concerns the level of detail involved in the valuation, what is often called top-down vs. bottom-up valuation. This paper discusses estimation approaches, criteria to assess estimation methods, specific approaches to estimating transition costs, factors that affect transition-cost estimates, strategies to address transition costs, who should pay transition costs, and the integration of cost recovery with competitive markets.

  8. Building America Residential Energy Efficiency Technical Update...

    Energy Savers [EERE]

    Residential Energy Efficiency Technical Update Meeting: August 2011 Building America Residential Energy Efficiency Technical Update Meeting: August 2011 On this page, you may link...

  9. Energy Storage Systems 2010 Update Conference Presentations ...

    Energy Savers [EERE]

    Systems 2010 Update Conference Presentations - Day 1, Session 1 Energy Storage Systems 2010 Update Conference Presentations - Day 1, Session 1 The U.S. DOE Energy Storage Systems...

  10. Generation IV International Forum Updates Technology Roadmap...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Updates Technology Roadmap and Builds Future Collaboration Generation IV International Forum Updates Technology Roadmap and Builds Future Collaboration December 31, 2013 - 12:14pm...

  11. Utility Energy Services Contracts: Enabling Documents Update...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Update Utility Energy Services Contracts: Enabling Documents Update Presentation covers the FUPWG Fall Meeting, held on November 28-29, 2007 in San Diego, California....

  12. A methodology to assess cost implications of automotive customization

    E-Print Network [OSTI]

    Fournier, Laëtitia

    2005-01-01T23:59:59.000Z

    This thesis focuses on determining the cost of customization for different components or groups of components of a car. It offers a methodology to estimate the manufacturing cost of a complex system such as a car. This ...

  13. Project Functions and Activities Definitions for Total Project Cost

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    This chapter provides guidelines developed to define the obvious disparity of opinions and practices with regard to what exactly is included in total estimated cost (TEC) and total project cost (TPC).

  14. SEE Action Webinar – Energy Efficiency Measure Cost Studies

    Broader source: Energy.gov [DOE]

    In this webinar, leading experts will explain the importance of measure cost studies, review the current “state of the science” of measure cost development and estimation, and explore opportunities...

  15. Prediction markets for cost and risk assessment

    E-Print Network [OSTI]

    Aggarwal, Taroon

    2011-01-01T23:59:59.000Z

    Several temporal and political factors can sometimes limit the effectiveness of traditional methods of project tracking and cost estimation. A large organization is susceptible to internal and external risks that are ...

  16. An Updated Methodology for Enhancing Risk Monitors with Integrated Equipment Condition Assessment

    SciTech Connect (OSTI)

    Ramuhalli, Pradeep; Hirt, Evelyn H.; Coles, Garill A.; Bonebrake, Christopher A.; Ivans, William J.; Wootan, David W.; Mitchell, Mark R.

    2014-07-18T23:59:59.000Z

    Small modular reactors (SMRs) generally include reactors with electric output of ~350 MWe or less (this cutoff varies somewhat but is substantially less than full-size plant output of 700 MWe or more). Advanced SMRs (AdvSMRs) refer to a specific class of SMRs and are based on modularization of advanced reactor concepts. Enhancing affordability of AdvSMRs will be critical to ensuring wider deployment, as AdvSMRs suffer from loss of economies of scale inherent in small reactors when compared to large (~greater than 600 MWe output) reactors and the controllable day-to-day costs of AdvSMRs will be dominated by operation and maintenance (O&M) costs. Technologies that help characterize real-time risk are important for controlling O&M costs. Risk monitors are used in current nuclear power plants to provide a point-in-time estimate of the system risk given the current plant configuration (e.g., equipment availability, operational regime, and environmental conditions). However, current risk monitors are unable to support the capability requirements listed above as they do not take into account plant-specific normal, abnormal, and deteriorating states of active components and systems. This report documents technology developments towards enhancing risk monitors that, if integrated with supervisory plant control systems, can provide the capability requirements listed and meet the goals of controlling O&M costs. The report describes research results on augmenting an initial methodology for enhanced risk monitors that integrate real-time information about equipment condition and POF into risk monitors. Methods to propagate uncertainty through the enhanced risk monitor are evaluated. Available data to quantify the level of uncertainty and the POF of key components are examined for their relevance, and a status update of this data evaluation is described. Finally, we describe potential targets for developing new risk metrics that may be useful for studying trade-offs for economic operation while maintaining adequate safety margins.

  17. Updated 4-13 James S. Ketchum

    E-Print Network [OSTI]

    , program planning, scheduling and earned value management support. As Program Control Officer he provided served as Head of the Resources Branch. He was responsible for all financial management (budget overall leadership, guidance and direction for program life- cycle estimates, program cost and earned

  18. Next Update: November 2013

    U.S. Energy Information Administration (EIA) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere IRaghurajiConventionalMississippi"site. IfProved(Million Barrels)21 4.65 2013 Next Update: November

  19. Next Update: November 2013

    U.S. Energy Information Administration (EIA) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere IRaghurajiConventionalMississippi"site. IfProved(Million Barrels)21 4.65 2013 Next Update:

  20. Hopper Updates and Status

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC) EnvironmentalGyroSolé(tm) HarmonicbetandEnergy 2010 A File Storage Updates and

  1. Carver Updates and Status

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625govInstrumentstdmadapInactiveVisiting the TWPSuccess StoriesFebruary 26,ComputersTrinitytheOptimization Updates and

  2. Updates and Status

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of ScienceandMesa del SolStrengthening aTurbulence mayUndergraduateAbout Us Updates and Status Current

  3. Timeline and updates

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of ScienceandMesa del SolStrengthening a solidSynthesis ofwasSynchrotron RadiationTimeline and Updates

  4. The cost effectiveness of geotechnical investigations in commercial building construction

    E-Print Network [OSTI]

    Temple, Merdith Wyndham Bolling

    1985-01-01T23:59:59.000Z

    and conducting thorough geotechnical investigations will be demonstrated. A range estimation and frequency histogram are introduced to illustrate the nominal expense of such studies compared to total project cost. These cost estimation techniques are based... have on project construction costs, particularly with respect to foundation expenditures. This data ". . . is believed by many to hold the key to significant cost reductions in. . . construction programs" . (46). It will be clearly demonstrated...

  5. Estimating Methods - DOE Directives, Delegations, and Requirements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    direct costs, and other estimating considerations are discussed in this chapter. g4301-1chp15.pdf -- PDF Document, 28 KB Writer: John Makepeace Subjects: Administration Management...

  6. GAO Cost Estimating and Assessment Guide Twelve Steps of a High-Quality Cost Estimating Process

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic2 OPAM Flash2011-12 OPAM RevisedFunding Opportunities1 - TheD,

  7. Accuracy of Contemporary Parametric Software Estimation Models: A Comparative Analysis

    E-Print Network [OSTI]

    Tomkins, Andrew

    with delays and being costly and error- prone. Inaccurate estimation of project resources is considered as one the costs, schedule and the resources for IT projects. Software estimation is the process of predicting the effort, duration and cost required to develop a software system [2]. Estimators often rely on one or more

  8. Phase II final report and second update of the energy economic data base (EEDB) program. Volume 1 of 1

    SciTech Connect (OSTI)

    Not Available

    1981-04-01T23:59:59.000Z

    The Energy Economic Data Base (EEDB) Program deals with the development of cost data for nuclear and comparison electric power generating stations. The objective of the USDOE EEDB Program is to provide periodic updates of technical and cost (capital, fuel and operating and maintenance) information of significance to the US Department of Energy. This information is intended to be used by USDOE in evaluating and monitoring US Civilian nuclear power programs, and to provide them with a consistent means of evaluating the nuclear option against alternatives. This report presents the Second Update of the EEDB for a cost and regulation date of January 1, 1979, prepared during Phase II of the EEDB Program. The Second Update is the first of a series of periodic updates marking the beginning of the next step in meeting the objective of the EEDB Program.

  9. Electricity Monthly Update

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    increase consumption. On the supply side, increases in the average cost of fossil fuel to power plants (9.2%), including a 26.6% increase in natural gas prices, added to the...

  10. Waste Management Facilities Cost Information Report

    SciTech Connect (OSTI)

    Feizollahi, F.; Shropshire, D.

    1992-10-01T23:59:59.000Z

    The Waste Management Facility Cost Information (WMFCI) Report, commissioned by the US Department of Energy (DOE), develops planning life-cycle cost (PLCC) estimates for treatment, storage, and disposal facilities. This report contains PLCC estimates versus capacity for 26 different facility cost modules. A procedure to guide DOE and its contractor personnel in the use of estimating data is also provided. Estimates in the report apply to five distinctive waste streams: low-level waste, low-level mixed waste, alpha contaminated low-level waste, alpha contaminated low-level mixed waste, and transuranic waste. The report addresses five different treatment types: incineration, metal/melting and recovery, shredder/compaction, solidification, and vitrification. Data in this report allows the user to develop PLCC estimates for various waste management options.

  11. Backup Power Cost of Ownership Analysis and Incumbent Technology...

    Energy Savers [EERE]

    backup power and presents the estimated annualized cost of ownership for fuel cell backup power systems compared with the incumbent technologies of battery and diesel generator...

  12. Updated NGNP Fuel Acquisition Strategy

    SciTech Connect (OSTI)

    David Petti; Tim Abram; Richard Hobbins; Jim Kendall

    2010-12-01T23:59:59.000Z

    A Next Generation Nuclear Plant (NGNP) fuel acquisition strategy was first established in 2007. In that report, a detailed technical assessment of potential fuel vendors for the first core of NGNP was conducted by an independent group of international experts based on input from the three major reactor vendor teams. Part of the assessment included an evaluation of the credibility of each option, along with a cost and schedule to implement each strategy compared with the schedule and throughput needs of the NGNP project. While credible options were identified based on the conditions in place at the time, many changes in the assumptions underlying the strategy and in externalities that have occurred in the interim requiring that the options be re-evaluated. This document presents an update to that strategy based on current capabilities for fuel fabrication as well as fuel performance and qualification testing worldwide. In light of the recent Pebble Bed Modular Reactor (PBMR) project closure, the Advanced Gas Reactor (AGR) fuel development and qualification program needs to support both pebble and prismatic options under the NGNP project. A number of assumptions were established that formed a context for the evaluation. Of these, the most important are: • Based on logistics associated with the on-going engineering design activities, vendor teams would start preliminary design in October 2012 and complete in May 2014. A decision on reactor type will be made following preliminary design, with the decision process assumed to be completed in January 2015. Thus, no fuel decision (pebble or prismatic) will be made in the near term. • Activities necessary for both pebble and prismatic fuel qualification will be conducted in parallel until a fuel form selection is made. As such, process development, fuel fabrication, irradiation, and testing for pebble and prismatic options should not negatively influence each other during the period prior to a decision on reactor type. • Additional funding will be made available beginning in fiscal year (FY) 2012 to support pebble bed fuel fabrication process development and fuel testing while maintaining the prismatic fuel schedule. Options for fuel fabrication for prismatic and pebble bed were evaluated based on the credibility of each option, along with a cost and schedule to implement each strategy. The sole prismatic option is Babcock and Wilcox (B&W) producing uranium oxycarbide (UCO) tristructural-isotropic (TRISO) fuel particles in compacts. This option finishes in the middle of 2022 . Options for the pebble bed are Nuclear Fuel Industries (NFI) in Japan producing uranium dioxide (UO2) TRISO fuel particles, and/or B&W producing UCO or UO2 TRISO fuel particles. All pebble options finish in mid to late 2022.

  13. Optimized Pathways for Regional H2 Infrastructure Transitions: The Least-Cost Hydrogen for Southern California

    E-Print Network [OSTI]

    Lin, Zhenhong; Chen, Chien-Wei; Fan, Yueyue; Ogden, Joan M.

    2008-01-01T23:59:59.000Z

    Costs to Estimate Hydrogen Pipeline Costs. University ofPipeline network gradually expands and eventually takes over all hydrogenpipelines. These technologies compete with each other to meet an exogenously estimated hydrogen

  14. UNIT COSTS fot ARMY FACILITIES -MILITARY CONSTRUCTION PAX NEWSLETTER NO. 3.2.2, dated 30 Mar 2006

    E-Print Network [OSTI]

    US Army Corps of Engineers

    ENGLISH UNIT COSTS fot ARMY FACILITIES - MILITARY CONSTRUCTION PAX NEWSLETTER NO. 3.2.2, dated 30 Mar 2006 1. APPENDIX A - FACILITY UNIT COST TABLE (FOR FY08 and later MILCON, BRAC, IGPBS Projects Newsletter No. 3.2.2, 15 March 2005, and updates the Appendix A, Facility Unit Cost Table, Appendix C, Tri

  15. APPROVED MINORS Updated on April 4, 2013

    E-Print Network [OSTI]

    New Hampshire, University of

    APPROVED MINORS Updated on April 4, 2013 Note: Please go to Department webpages for updates. Page 1;APPROVED MINORS Updated on April 4, 2013 Note: Please go to Department webpages for updates. Page 2 COLLEGE Studies Cinema Studies Classics Communication Dance Education English European Cultural Studies Forensics

  16. Chapter 11Chapter 11 Estimating the Weighted

    E-Print Network [OSTI]

    Schubart, Christoph

    Chapter 11Chapter 11 Estimating the Weighted Average Cost of Capital DES Chapter 11 1 #12;U i th C.xls for shortfor short. DES Chapter 11 2 #12;S i l i hSteps to estimate value using the Corporate Valuation stockholders DES Chapter 11 7 #12;Estimating Target Weights Page 223: To calculate WACC, we need to estimate

  17. IEAB Invasive Mussels Update September 2013 Invasive Mussels Update

    E-Print Network [OSTI]

    ....................................................... 16 8. Update on Mussel Control Agents Area MFWP Montana Fish Wildlife and Parks NASQAN National Stream Quality Accounting Network NGO Non, respectively, during 2012. A total of 109 mussel-infested boats were found during

  18. PHENIX WBS notes. Cost and schedule review copy

    SciTech Connect (OSTI)

    Not Available

    1994-02-01T23:59:59.000Z

    The Work Breakdown Structure (WBS) Book begins with this Overview section, which contains the high-level summary cost estimate, the cost profile, and the global construction schedule. The summary cost estimate shows the total US cost and the cost in terms of PHENIX construction funds for building the PHENIX detector. All costs in the WBS book are shown in FY 1993 dollars. Also shown are the institutional and foreign contributions, the level of pre-operations funding, and the cost of deferred items. Pie charts are presented at PHENIX WBS level 1 and 2 that show this information. The PHENIX construction funds are shown broken down to PHENIX WBS level 3 items per fiscal year, and the resulting profile is compared to the RHIC target profile. An accumulated difference of the two profiles is also shown. The PHENIX global construction schedule is presented at the end of the Overview section. Following the Overview are sections for each subsystem. Each subsystem section begins with a summary cost estimate, cost profile, and critical path. The total level 3 cost is broken down into fixed costs (M&S), engineering costs (EDIA) and labor costs. Costs are further broken down in terms of PHENIX construction funds, institutional and foreign contributions, pre-operations funding, and deferred items. Also shown is the contingency at level 3 and the level 4 breakdown of the total cost. The cost profile in fiscal years is shown at level 3. The subsystem summaries are followed by the full cost estimate and schedule sheets for that subsystem. These detailed sheets are typically carried down to level 7 or 8. The cost estimate Total, M&S, EDIA, and Labor breakdowns, as well as contingency, for each WBS entry.

  19. Fermilab D-0 Experimental Facility: Energy conservation report and mechanical systems design optimization and cost analysis study

    SciTech Connect (OSTI)

    Krstulovich, S.F.

    1987-10-31T23:59:59.000Z

    This report is developed as part of the Fermilab D-0 Experimental Facility Project Title II Design Documentation Update. As such, it concentrates primarily on HVAC mechanical systems design optimization and cost analysis.

  20. An Assessment of the Near-Term Costs of Hydrogen Refueling Stations and Station Components

    E-Print Network [OSTI]

    Weinert, Jonathan X.; Lipman, Timothy

    2006-01-01T23:59:59.000Z

    station. H2Gen’s estimates for capital costs are also lowerestimates and show high variability (26%-117% of capital costs).capital costs of about $250,000. Existing hydrogen station cost analyses tend to under-estimate