National Library of Energy BETA

Sample records for units capital costs

  1. Transmission line capital costs

    SciTech Connect (OSTI)

    Hughes, K.R.; Brown, D.R.

    1995-05-01

    The displacement or deferral of conventional AC transmission line installation is a key benefit associated with several technologies being developed with the support of the U.S. Department of Energy`s Office of Energy Management (OEM). Previous benefits assessments conducted within OEM have been based on significantly different assumptions for the average cost per mile of AC transmission line. In response to this uncertainty, an investigation of transmission line capital cost data was initiated. The objective of this study was to develop a database for preparing preliminary estimates of transmission line costs. An extensive search of potential data sources identified databases maintained by the Bonneville Power Administration (BPA) and the Western Area Power Administration (WAPA) as superior sources of transmission line cost data. The BPA and WAPA data were adjusted to a common basis and combined together. The composite database covers voltage levels from 13.8 to 765 W, with cost estimates for a given voltage level varying depending on conductor size, tower material type, tower frame type, and number of circuits. Reported transmission line costs vary significantly, even for a given voltage level. This can usually be explained by variation in the design factors noted above and variation in environmental and land (right-of-way) costs, which are extremely site-specific. Cost estimates prepared from the composite database were compared to cost data collected by the Federal Energy Regulatory Commission (FERC) for investor-owned utilities from across the United States. The comparison was hampered because the only design specifications included with the FERC data were voltage level and line length. Working within this limitation, the FERC data were not found to differ significantly from the composite database. Therefore, the composite database was judged to be a reasonable proxy for estimating national average costs.

  2. LIFE Cost of Electricity, Capital and Operating Costs

    SciTech Connect (OSTI)

    Anklam, T

    2011-04-14

    Successful commercialization of fusion energy requires economic viability as well as technical and scientific feasibility. To assess economic viability, we have conducted a pre-conceptual level evaluation of LIFE economics. Unit costs are estimated from a combination of bottom-up costs estimates, working with representative vendors, and scaled results from previous studies of fission and fusion plants. An integrated process model of a LIFE power plant was developed to integrate and optimize unit costs and calculate top level metrics such as cost of electricity and power plant capital cost. The scope of this activity was the entire power plant site. Separately, a development program to deliver the required specialized equipment has been assembled. Results show that LIFE power plant cost of electricity and plant capital cost compare favorably to estimates for new-build LWR's, coal and gas - particularly if indicative costs of carbon capture and sequestration are accounted for.

  3. Electric power substation capital costs (Technical Report) |...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... Subject: 24 POWER TRANSMISSION AND DISTRIBUTION; POWER SUBSTATIONS; CAPITALIZED COST; CALCULATION METHODS; PLANNING; COST ESTIMATION; MATHEMATICAL MODELS Word Cloud More Like This ...

  4. Electric power substation capital costs

    SciTech Connect (OSTI)

    Dagle, J.E.; Brown, D.R.

    1997-12-01

    The displacement or deferral of substation equipment is a key benefit associated with several technologies that are being developed with the support of the US Department of Energy`s Office of Utility Technologies. This could occur, for example, as a result of installing a distributed generating resource within an electricity distribution system. The objective of this study was to develop a model for preparing preliminary estimates of substation capital costs based on rudimentary conceptual design information. The model is intended to be used by energy systems analysts who need ``ballpark`` substation cost estimates to help establish the value of advanced utility technologies that result in the deferral or displacement of substation equipment. This cost-estimating model requires only minimal inputs. More detailed cost-estimating approaches are recommended when more detailed design information is available. The model was developed by collecting and evaluating approximately 20 sets of substation design and cost data from about 10 US sources, including federal power marketing agencies and private and public electric utilities. The model is principally based on data provided by one of these sources. Estimates prepared with the model were compared with estimated and actual costs for the data sets received from the other utilities. In general, good agreement (for conceptual level estimating) was found between estimates prepared with the cost-estimating model and those prepared by the individual utilities. Thus, the model was judged to be adequate for making preliminary estimates of typical substation costs for US utilities.

  5. QGESS: Capital Cost Scaling Methodology

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the tonnes of CO2 utilized. The costs of the process are to include infrastructure, raw materials, processing, byproduct disposal, and utilities costs, as well as any other costs....

  6. Decommissioning Unit Cost Data

    SciTech Connect (OSTI)

    Sanford, P. C.; Stevens, J. L.; Brandt, R.

    2002-02-26

    The Rocky Flats Closure Site (Site) is in the process of stabilizing residual nuclear materials, decommissioning nuclear facilities, and remediating environmental media. A number of contaminated facilities have been decommissioned, including one building, Building 779, that contained gloveboxes used for plutonium process development but did little actual plutonium processing. The actual costs incurred to decommission this facility formed much of the basis or standards used to estimate the decommissioning of the remaining plutonium-processing buildings. Recent decommissioning activities in the first actual production facility, Building 771, implemented a number of process and procedural improvements. These include methods for handling plutonium contaminated equipment, including size reduction, decontamination, and waste packaging, as well as management improvements to streamline planning and work control. These improvements resulted in a safer working environment and reduced project cost, as demonstrated in the overall project efficiency. The topic of this paper is the analysis of how this improved efficiency is reflected in recent unit costs for activities specific to the decommissioning of plutonium facilities. This analysis will allow the Site to quantify the impacts on future Rocky Flats decommissioning activities, and to develop data for planning and cost estimating the decommissioning of future facilities. The paper discusses the methods used to collect and arrange the project data from the individual work areas within Building 771. Regression and data correlation techniques were used to quantify values for different types of decommissioning activities. The discussion includes the approach to identify and allocate overall project support, waste management, and Site support costs based on the overall Site and project costs to provide a ''burdened'' unit cost. The paper ultimately provides a unit cost basis that can be used to support cost estimates for

  7. Table 1. Updated estimates of power plant capital and operating costs

    U.S. Energy Information Administration (EIA) Indexed Site

    Updated estimates of power plant capital and operating costs" ,"Plant Characteristics",,,"Plant Costs (2012$)" ,"Nominal Capacity (MW)","Heat Rate (Btu/kWh)",,"Overnight Capital Cost ($/kW)","Fixed O&M Cost ($/kW-yr)","Variable O&M Cost ($/MWh)" ,,,,,,,"NEMS Input" " Coal" "Single Unit Advanced PC",650,8800,,3246,37.8,4.47,"N" "Dual Unit Advanced

  8. A model of the Capital Cost of a natural gas-fired fuel cell based Central Utilities Plant

    SciTech Connect (OSTI)

    Not Available

    1993-06-30

    This model defines the methods used to estimate the cost associated with acquisition and installation of capital equipment of the fuel cell systems defined by the central utility plant model. The capital cost model estimates the cost of acquiring and installing the fuel cell unit, and all auxiliary equipment such as a boiler, air conditioning, hot water storage, and pumps. The model provides a means to adjust initial cost estimates to consider learning associated with the projected level of production and installation of fuel cell systems. The capital cost estimate is an input to the cost of ownership analysis where it is combined with operating cost and revenue model estimates.

  9. Project Profile: Concurrent Optimization of Component Capital Cost and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Expected Operations and Management (SuNLaMP) | Department of Energy Project Profile: Concurrent Optimization of Component Capital Cost and Expected Operations and Management (SuNLaMP) Project Profile: Concurrent Optimization of Component Capital Cost and Expected Operations and Management (SuNLaMP) Funding Program: SuNLaMP SunShot Subprogram: CSP Location: National Renewable Energy Laboratory, Golden, CO SunShot Award Amount: $3,000,000 This project is developing and validating an open

  10. Discrete Event Modeling of Algae Cultivation and Harvesting at Commercial Scale: Capital Costs, Operating Costs, and System Bottlenecks

    SciTech Connect (OSTI)

    Lacey, Ph.D, P.E., Ronald E.

    2012-07-16

    Discrete Event Modeling of Algae Cultivation and Harvesting at Commercial Scale: Capital Costs, Operating Costs, and System Bottlenecks

  11. New developments in capital cost estimating

    SciTech Connect (OSTI)

    Stutz, R.A.; Zocher, M.A.

    1988-01-01

    The new developments in cost engineering revolve around the ability to capture information that in the past could not be automated. The purpose of automation is not to eliminate the expert cost engineer. The goal is to use available technology to have more information available to the professionals in the cost engineering field. In that sense, the demand for expertise increases in order to produce the highest quality estimate and project possible from all levels of cost engineers. We cannot overemphasize the importance of using a good source of expert information in building these types of programs. ''Garbage in, garbage out'' still applies in this form of programming. Expert systems technology will become commonplace in many vertical markets; it is important to undersand what can and cannot be accomplished in our field, and where this technology will lead us in the future.

  12. Accessing Low-Cost Capital Through Securitization (Poster)

    SciTech Connect (OSTI)

    Mendelsohn, M.

    2014-10-01

    Poster for Solar Power International conference presents information on NREL's effort to open capital markets through securitization via Solar Access to Public Capital (SAPC) working group's efforts.

  13. Low-cost inertial measurement unit.

    SciTech Connect (OSTI)

    Deyle, Travis Jay

    2005-03-01

    Sandia National Laboratories performs many expensive tests using inertial measurement units (IMUs)--systems that use accelerometers, gyroscopes, and other sensors to measure flight dynamics in three dimensions. For the purpose of this report, the metrics used to evaluate an IMU are cost, size, performance, resolution, upgradeability and testing. The cost of a precision IMU is very high and can cost hundreds of thousands of dollars. Thus the goals and results of this project are as follows: (1) Examine the data flow in an IMU and determine a generic IMU design. (2) Discuss a high cost IMU implementation and its theoretically achievable results. (3) Discuss design modifications that would save money for suited applications. (4) Design and implement a low cost IMU and discuss its theoretically achievable results. (5) Test the low cost IMU and compare theoretical results with empirical results. (6) Construct a more streamlined printed circuit board design reducing noise, increasing capabilities, and constructing a self-contained unit. Using these results, we can compare a high cost IMU versus a low cost IMU using the metrics from above. Further, we can examine and suggest situations where a low cost IMU could be used instead of a high cost IMU for saving cost, size, or both.

  14. Power plant capital investment cost estimates: current trends and sensitivity to economic parameters

    SciTech Connect (OSTI)

    Not Available

    1980-06-01

    This report describes power plant capital investment cost studies that were carried out as part of the activities of the Plans and Analysis Division, Office of Nuclear Energy Programs, US Department of Energy. The activities include investment cost studies prepared by an architect-engineer, including trends, effects of environmental and safety requirements, and construction schedules. A computer code used to prepare capital investment cost estimates under varying economic conditions is described, and application of this code is demonstrated by sensitivity studies.

  15. Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants

    Reports and Publications (EIA)

    2013-01-01

    The current and future projected cost and performance characteristics of new electric generating capacity are a critical input into the development of energy projections and analyses.

  16. Best Practices for Controlling Capital Costs in Net Zero Energy...

    Broader source: Energy.gov (indexed) [DOE]

    construction, it is necessary to demonstrate that NZE can be achieved cost effectively. This project aims to increase and accelerate the adoption of NZE design and construction ...

  17. Controlling Capital Costs in High Performance Office Buildings: A Review of Best Practices for Overcoming Cost Barriers

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Controlling Capital Costs in High Performance Office Buildings: A Review of Best Practices for Overcoming Cost Barriers Preprint Shanti Pless and Paul Torcellini To be presented at the ACEEE Summer Study on Energy Efficiency in Buildings Pacific Grove, California August 12-17, 2012 Conference Paper NREL/CP-5500-55264 May 2012 NOTICE The submitted manuscript has been offered by an employee of the Alliance for Sustainable Energy, LLC (Alliance), a contractor of the US Government under Contract No.

  18. Capital Projects Estimated >$7 Million in Direct Costs Business

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Transformer Replacement G1, G3,G5-8 Federal Hydro *-- Sustain Replace the existing transformers. Black Canyon Units 1 & 2 Upgrades Federal Hydro *-- Sustain Upgrades to increase...

  19. Wind-To-Hydrogen Project: Electrolyzer Capital Cost Study

    SciTech Connect (OSTI)

    Saur, G.

    2008-12-01

    This study is being performed as part of the U.S. Department of Energy and Xcel Energy's Wind-to-Hydrogen Project (Wind2H2) at the National Renewable Energy Laboratory. The general aim of the project is to identify areas for improving the production of hydrogen from renewable energy sources. These areas include both technical development and cost analysis of systems that convert renewable energy to hydrogen via water electrolysis. Increased efficiency and reduced cost will bring about greater market penetration for hydrogen production and application. There are different issues for isolated versus grid-connected systems, however, and these issues must be considered. The manner in which hydrogen production is integrated in the larger energy system will determine its cost feasibility and energy efficiency.

  20. Capital and operating cost estimates. Volume I. Preliminary design and assessment of a 12,500 BPD coal-to-methanol-to-gasoline plant. [Grace C-M-G Plant, Henderson County, Kentucky

    SciTech Connect (OSTI)

    Not Available

    1982-08-01

    This Deliverable No. 18b - Capital and Operating Cost Estimates includes a detailed presentation of the 12,500 BPD coal-to-methanol-to-gasoline plant from the standpoint of capital, preoperations, start-up and operations cost estimation. The base capital cost estimate in June 1982 dollars was prepared by the Ralph M. Parsons Company under the direction of Grace. The escalated capital cost estimate as well as separate estimates for preoperations, startup and operations activities were developed by Grace. The deliverable consists of four volumes. Volume I contains details of methodology used in developing the capital cost estimate, summary information on a base June 1982 capital cost, details of the escalated capital cost estimate and separate sections devoted to preoperations, start-up, and operations cost. The base estimate is supported by detailed information in Volumes II, III and IV. The degree of detail for some units was constrained due to proprietary data. Attempts have been made to exhibit the estimating methodology by including data on individual equipment pricing. Proprietary details are available for inspection upon execution of nondisclosure and/or secrecy agreements with the licensors to whom the data is proprietary. Details of factoring certain pieces of equipment and/or entire modules or units from the 50,000 BPD capital estimate are also included. In the case of the escalated capital estimate, Grace has chosen to include a sensitivity analysis which allows for ready assessment of impacts of escalation rates (inflation), contingency allowances and the construction interest financing rates on the escalated capital cost. Each of the estimates associated with bringing the plant to commercial production rates has as a basis the schedule and engineering documentation found in Deliverable No. 14b - Process Engineering and Mechanical Design Report, No. 28b - Staffing Plans, No. 31b - Construction Plan, and No. 33b - Startup and Operation Plan.

  1. Developing a Cost Model and Methodology to Estimate Capital Costs for Thermal Energy Storage

    SciTech Connect (OSTI)

    Glatzmaier, G.

    2011-12-01

    This report provides an update on the previous cost model for thermal energy storage (TES) systems. The update allows NREL to estimate the costs of such systems that are compatible with the higher operating temperatures associated with advanced power cycles. The goal of the Department of Energy (DOE) Solar Energy Technology Program is to develop solar technologies that can make a significant contribution to the United States domestic energy supply. The recent DOE SunShot Initiative sets a very aggressive cost goal to reach a Levelized Cost of Energy (LCOE) of 6 cents/kWh by 2020 with no incentives or credits for all solar-to-electricity technologies.1 As this goal is reached, the share of utility power generation that is provided by renewable energy sources is expected to increase dramatically. Because Concentrating Solar Power (CSP) is currently the only renewable technology that is capable of integrating cost-effective energy storage, it is positioned to play a key role in providing renewable, dispatchable power to utilities as the share of power generation from renewable sources increases. Because of this role, future CSP plants will likely have as much as 15 hours of Thermal Energy Storage (TES) included in their design and operation. As such, the cost and performance of the TES system is critical to meeting the SunShot goal for solar technologies. The cost of electricity from a CSP plant depends strongly on its overall efficiency, which is a product of two components - the collection and conversion efficiencies. The collection efficiency determines the portion of incident solar energy that is captured as high-temperature thermal energy. The conversion efficiency determines the portion of thermal energy that is converted to electricity. The operating temperature at which the overall efficiency reaches its maximum depends on many factors, including material properties of the CSP plant components. Increasing the operating temperature of the power generation

  2. Controlling Capital Costs in High Performance Office Buildings: A Review of Best Practices for Overcoming Cost Barriers

    SciTech Connect (OSTI)

    Pless, S.; Torcellini, P.

    2012-05-01

    This paper presents a set of 15 best practices for owners, designers, and construction teams of office buildings to reach high performance goals for energy efficiency, while maintaining a competitive budget. They are based on the recent experiences of the owner and design/build team for the Research Support Facility (RSF) on National Renewable Energy Facility's campus in Golden, CO, which show that achieving this outcome requires each key integrated team member to understand their opportunities to control capital costs.

  3. Access to Capital

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    IPR 2008 Capital Investment Review CIR 2012 Quarterly Business Review Focus 2028 2011 Strategic Capital Discussions Access to Capital Debt Optimization Asset Management Cost...

  4. 2011 Strategic Capital Discussions

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    IPR 2008 Capital Investment Review CIR 2012 Quarterly Business Review Focus 2028 2011 Strategic Capital Discussions Access to Capital Debt Optimization Asset Management Cost...

  5. Rocky Flats Closure Unit Cost Data

    SciTech Connect (OSTI)

    Sanford, P.C.; Skokan, B.

    2007-07-01

    The Rocky Flats Closure Project has completed the process of stabilizing residual nuclear materials, decommissioning nuclear facilities, remediating environmental media and closing the Rocky Flats Site (Site). The project cost approximately $4.1 B and included the decommissioning of over 700 structures including 5 major plutonium facilities and 5 major uranium facilities, shipping over 14,600 cubic meters of transuranic and 565,000 cubic meters of low level radioactive waste, and remediating a 385-acre industrial area and the surrounding land. Actual costs were collected for a large variety of closure activities. These costs can be correlated with metrics associated with the facilities and environmental media to capture cost factors from the project that could be applicable to a variety of other closure projects both within and outside of the Department of Energy's weapons complex. The paper covers four general topics: the process to correlate the actual costs and metrics, an example of the correlated data for one large sub-project, a discussion of the results, and the additional activities that are planned to correlate and make this data available to the public. The process to collect and arrange the project control data of the Closure Project relied on the actual Closure Project cost information. It was used to correlate these actual costs with the metrics for the physical work, such as building area or waste generated, to support the development of parametric cost factors. The example provides cost factors for the Industrial Sites Project. The discussion addresses the strengths and weaknesses of the data, followed by a section identifying future activities to improve and extend the analyses and integrate it within the Department's Environmental Cost Analysis System. (authors)

  6. FGD system capital and operating cost reductions based on improved thiosorbic scrubber system design and latest process innovations

    SciTech Connect (OSTI)

    Smith, K.; Tseng, S.; Babu, M.

    1994-12-31

    Dravo Lime Company has operated the Miami Fort wet scrubber FGD pilot test unit since late 1989 and has continued in-house R&D to improve the economics of the magnesium-enhanced scrubbing process. Areas investigated include the scrubber configuration, flue gas velocity, spray nozzle type, droplet size, mist eliminator design, additives to inhibit oxidation, improved solids dewatering, etc. Also tested was the forced oxidation Thioclear process. The data gathered from the pilot plant and in-house programs were used to evaluate the capital and operating costs for the improved systems. These evaluations were made with eye towards the choices electric utilities will need to make in the near future to meet the Phase II emission limits mandated by the 1990 Clean Air Act. Some of the process modifications investigated, for example, the dewatering improvements apply to potential beneficial retrofit of existing FGD systems today.

  7. A heat & mass integration approach to reduce capital and operating costs of a distillation configuration

    SciTech Connect (OSTI)

    Madenoor Ramapriya, Gautham; Jiang, Zheyu; Tawarmalani, Mohit; Agrawal, Rakesh

    2015-11-11

    We propose a general method to consolidate distillation columns of a distillation configuration using heat and mass integration. The proposed method encompasses all heat and mass integrations known till date, and includes many more. Each heat and mass integration eliminates a distillation column, a condenser, a reboiler and the heat duty associated with a reboiler. Thus, heat and mass integration can potentially offer significant capital and operating cost benefits. In this talk, we will study the various possible heat and mass integrations in detail, and demonstrate their benefits using case studies. This work will lay out a framework to synthesize an entire new class of useful configurations based on heat and mass integration of distillation columns.

  8. Cycling fossil-fired units proves costly business

    SciTech Connect (OSTI)

    Lefton, S.; Grimsrud, P.; Besuner, P.

    1997-07-01

    Competition in the electric utility business is having a far-reaching impact. Cost-cutting measures have in major downsizing efforts in virtually every utility in the country. After several cost-cutting rounds to reduce the low hanging fruit of inefficiency, utilities are still challenged to become leaner and meaner in order to compete in a deregulated environment. The problem for many power utilities, however, is they have not precisely determined their costs in every aspect of the plant`s operation. Naturally, obtaining an accurate understanding of expenditures is the starting point for utilities that wish to develop strategic plans to better manage assets, minimize costs and maximize return on investment better understand plant O&M costs and take measures to use this knowledge to their advantage. Cycling is a major reason for the increase in O&M costs of many fossil units. Cycling, in this context, refers to the operation of generating units at varying load levels in response to changes in system-load requirements.

  9. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    BPA on 242015 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  10. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    BPA on 622014 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  11. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    on 1142014 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  12. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    on 2112014 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  13. Philadelphia gas works medium-Btu coal gasification project: capital and operating cost estimate, financial/legal analysis, project implementation

    SciTech Connect (OSTI)

    Not Available

    1981-12-01

    This volume of the final report is a compilation of the estimated capital and operating costs for the project. Using the definitive design as a basis, capital and operating costs were developed by obtaining quotations for equipment delivered to the site. Tables 1.1 and 1.2 provide a summary of the capital and operating costs estimated for the PGW Coal Gasification Project. In the course of its Phase I Feasibility Study of a medium-Btu coal-gas facility, Philadelphia Gas Works (PGW) identified the financing mechanism as having great impact on gas cost. Consequently, PGW formed a Financial/Legal Task Force composed of legal, financial, and project analysis specialists to study various ownership/management options. In seeking an acceptable ownership, management, and financing arrangement, certain ownership forms were initially identified and classified. Several public ownership, private ownership, and third party ownership options for the coal-gas plant are presented. The ownership and financing forms classified as base alternatives involved tax-exempt and taxable financing arrangements and are discussed in Section 3. Project implementation would be initiated by effectively planning the methodology by which commercial operation will be realized. Areas covered in this report are sale of gas to customers, arrangements for feedstock supply and by-product disposal, a schedule of major events leading to commercialization, and a plan for managing the implementation.

  14. Beetle Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Beetle Capital Partners Jump to: navigation, search Logo: Beetle Capital Partners Name: Beetle Capital Partners Address: Medici Court, 67-69 New Bond Street Place: London, United...

  15. Temple Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Temple Capital Partners Jump to: navigation, search Name: Temple Capital Partners Place: United Kingdom Product: Fund manager of Clean Energy Brazil. References: Temple Capital...

  16. Green Capital Management | Open Energy Information

    Open Energy Info (EERE)

    Capital Management Jump to: navigation, search Name: Green Capital Management Place: London, United Kingdom Zip: SW10 0BB Sector: Services Product: The Green Capital Management...

  17. EXPERT ELICITATION OF ACROSS-TECHNOLOGY CORRELATIONS FOR REACTOR CAPITAL COSTS

    SciTech Connect (OSTI)

    Brent Dixon; Various

    2014-06-01

    Calculations of the uncertainty in the Levelized Cost at Equilibrium (LCAE) of generating nuclear electricity typically assume that the costs of the system component, notably reactors, are uncorrelated. Partial cancellation of independent errors thus gives rise to unrealistically small cost uncertainties for fuel cycles that incorporate multiple reactor technologies. This summary describes an expert elicitation of correlations between overnight reactor construction costs. It also defines a method for combining the elicitations into a single, consistent correlation matrix suitable for use in Monte Carlo LCAE calculations. Both the elicitation and uncertainty propagation methods are demonstrated through a pilot study where cost correlations between eight reactor technologies were elicited from experts in the US DOE Fuel Cycle Research

  18. Gaian Capital | Open Energy Information

    Open Energy Info (EERE)

    Gaian Capital Jump to: navigation, search Name: Gaian Capital Place: Greater London, United Kingdom Product: London-based privately held firm aimed at assisting climate change...

  19. Capital Connections | Open Energy Information

    Open Energy Info (EERE)

    Connections Jump to: navigation, search Name: Capital Connections Place: United Kingdom Product: Supplies fuel cell systems. References: Capital Connections1 This article is a...

  20. Carbon Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Carbon Capital Place: United Kingdom Sector: Carbon Product: Manages a carbon fund specialised in forestry projects References: Carbon...

  1. Break-Even Cost for Residential Solar Water Heating in the United...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Break-even Cost for Residential Solar Water Heating in the United States: Key Drivers and Sensitivities Hannah Cassard, Paul Denholm, and Sean Ong Technical Report NREL...

  2. SunShot: Making Solar Energy Cost Competitive Throughout the United States (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2011-06-01

    The U.S. Department of Energy's SunShot Initiative focuses on making solar energy cost competitive throughout the United States.

  3. SunShot: Making Solar Energy Cost Competitive Throughout the United States (Fact Sheet)

    SciTech Connect (OSTI)

    McCamey, D.

    2011-03-01

    The U.S. Department of Energy's SunShot Initiative focuses on making solar energy cost competitive throughout the United States.

  4. Hazel Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Hazel Capital Place: London, England, United Kingdom Zip: WC2A 1AL Sector: Efficiency, Renewable Energy Product: Hazel Capital is an asset...

  5. Capital Reporting Company Quadrennial ...

    Broader source: Energy.gov (indexed) [DOE]

    Capital Reporting Company Quadrennial Energy Review Meeting No. 4 06-19-2014 (866) 448 - DEPO www.CapitalReportingCompany.com 2014 1 UNITED STATES DEPARTMENT OF ENERGY OFFICE OF ...

  6. Residential, Commercial, and Utility-Scale Photovoltaic (PV) System Prices in the United States: Current Drivers and Cost-Reduction Opportunities

    SciTech Connect (OSTI)

    Goodrich, A.; James, T.; Woodhouse, M.

    2012-02-01

    The price of photovoltaic (PV) systems in the United States (i.e., the cost to the system owner) has dropped precipitously in recent years, led by substantial reductions in global PV module prices. However, system cost reductions are not necessarily realized or realized in a timely manner by many customers. Many reasons exist for the apparent disconnects between installation costs, component prices, and system prices; most notable is the impact of fair market value considerations on system prices. To guide policy and research and development strategy decisions, it is necessary to develop a granular perspective on the factors that underlie PV system prices and to eliminate subjective pricing parameters. This report's analysis of the overnight capital costs (cash purchase) paid for PV systems attempts to establish an objective methodology that most closely approximates the book value of PV system assets.

  7. IEA Wind Task 26. Wind Technology, Cost and Performance Trends in Denmark, Germany, Ireland, Norway, the European Union, and the United States. 2007 - 2012

    SciTech Connect (OSTI)

    Vitina, Aisma; Luers, Silke; Wallasch, Anna-Kathrin; Berkhout, Volker; Duffy, Aidan; Cleary, Brendan; Husabo, Leif I.; Weir, David E.; Lacal-Arantegui, Roberto; Hand, M. Maureen; Lantz, Eric; Belyeu, Kathy; Wiser, Ryan; Bolinger, Mark; Hoen, Ben

    2015-06-12

    This report builds from a similar previous analysis (Schwabe et al., 2011) exploring the differences in cost of wind energy in 2008 among countries participating in IEA Wind Task 26 at that time. The levelized cost of energy (LCOE) is a widely recognized metric for understanding how technology, capital investment, operations, and financing impact the life-cycle cost of building and operating a wind plant. Schwabe et al. (2011) apply a spreadsheet-based cash flow model developed by the Energy Research Centre of the Netherlands (ECN) to estimate LCOE. This model is a detailed, discounted cash flow model used to represent the various cost structures in each of the participating countries from the perspective of a financial investor in a domestic wind energy project. This model is used for the present analysis as well, and comparisons are made for those countries who contributed to both reports, Denmark, Germany, and the United States.

  8. TRANSMISSION AND DISTRIBUTION; POWER SUBSTATIONS; CAPITALIZED...

    Office of Scientific and Technical Information (OSTI)

    AND DISTRIBUTION; POWER SUBSTATIONS; CAPITALIZED COST; CALCULATION METHODS; PLANNING; COST ESTIMATION; MATHEMATICAL MODELS The displacement or deferral of substation...

  9. Renewable Energy Cost Modeling. A Toolkit for Establishing Cost-Based Incentives in the United States

    SciTech Connect (OSTI)

    Gifford, Jason S.; Grace, Robert C.; Rickerson, Wilson H.

    2011-05-01

    This report serves as a resource for policymakers who wish to learn more about levelized cost of energy (LCOE) calculations, including cost-based incentives. The report identifies key renewable energy cost modeling options, highlights the policy implications of choosing one approach over the other, and presents recommendations on the optimal characteristics of a model to calculate rates for cost-based incentives, FITs, or similar policies. These recommendations shaped the design of NREL's Cost of Renewable Energy Spreadsheet Tool (CREST), which is used by state policymakers, regulators, utilities, developers, and other stakeholders to assist with analyses of policy and renewable energy incentive payment structures. Authored by Jason S. Gifford and Robert C. Grace of Sustainable Energy Advantage LLC and Wilson H. Rickerson of Meister Consultants Group, Inc.

  10. Impacts of Renewable Generation on Fossil Fuel Unit Cycling: Costs and Emissions (Presentation)

    SciTech Connect (OSTI)

    Brinkman, G.; Lew, D.; Denholm, P.

    2012-09-01

    Prepared for the Clean Energy Regulatory Forum III, this presentation looks at the Western Wind and Solar Integration Study and reexamines the cost and emissions impacts of fossil fuel unit cycling.

  11. Cost of Capital

    Broader source: Energy.gov [DOE]

    This presentation summarizes the information given by PV Evolution Labs during the DOE SunShot Grand Challenge: Summit and Technology Forum, June 13-14, 2012.

  12. Breakeven Cost for Residential Photovoltaics in the United States: Key Drivers and Sensitivities (Report Summary) (Presentation)

    SciTech Connect (OSTI)

    Denholm, P.; Margolis, R. M.; Ong, S.; Roberts, B.

    2009-12-01

    "Break-even cost" for photovoltaic (PV) technology is defined as the point where the cost of PV-generated electricity equals the cost of electricity purchased from the grid. Break-even cost is expressed in $/W of an installed system. Achieving break-even cost is a function of many variables. Consequently, break-even costs vary by location and time for a country, such as the United States, with a diverse set of resources, electricity prices, and other variables. In this presentation, we introduce an analysis of PV break-even costs for residential customers in the United States, including an evaluation of some of the key drivers of PV breakeven both regionally and over time. This presentation includes our methodology and presents results for both near-term residential breakeven costs(2009) and future market sensitivities of break-even costs (2015). See also the the report "Break-Even Cost for Residential Photovoltaics in the United States: Key Drivers and Sensitivities". Presentation for NREL/TP-6A2-45991.

  13. Replacement energy costs for nuclear electricity-generating units in the United States: 1997--2001. Volume 4

    SciTech Connect (OSTI)

    VanKuiken, J.C.; Guziel, K.A.; Tompkins, M.M.; Buehring, W.A.

    1997-09-01

    This report updates previous estimates of replacement energy costs for potential short-term shutdowns of 109 US nuclear electricity-generating units. This information was developed to assist the US Nuclear Regulatory Commission (NRC) in its regulatory impact analyses, specifically those that examine the impacts of proposed regulations requiring retrofitting of or safety modifications to nuclear reactors. Such actions might necessitate shutdowns of nuclear power plants while these changes are being implemented. The change in energy cost represents one factor that the NRC must consider when deciding to require a particular modification. Cost estimates were derived from probabilistic production cost simulations of pooled utility system operations. Factors affecting replacement energy costs, such as random unit failures, maintenance and refueling requirements, and load variations, are treated in the analysis. This report describes an abbreviated analytical approach as it was adopted to update the cost estimates published in NUREG/CR-4012, Vol. 3. The updates were made to extend the time frame of cost estimates and to account for recent changes in utility system conditions, such as change in fuel prices, construction and retirement schedules, and system demand projects.

  14. Climate Human Capital | Open Energy Information

    Open Energy Info (EERE)

    Human Capital Jump to: navigation, search Name: Climate Human Capital Place: London, United Kingdom Zip: W1K 6NG Sector: Carbon, Renewable Energy, Services Product: Green executive...

  15. Cape Verde Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Cape Verde Capital Place: Leatherhead, United Kingdom Zip: KT22 7SW Sector: Renewable Energy Product: The renewable energy investment arm...

  16. Transmission Capital Limited | Open Energy Information

    Open Energy Info (EERE)

    Transmission Capital Limited Jump to: navigation, search Name: Transmission Capital Limited Place: London, United Kingdom Zip: EC2V 7HR Sector: Renewable Energy, Services Product:...

  17. Sustainable Development Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Capital LLP Jump to: navigation, search Name: Sustainable Development Capital LLP Place: London, United Kingdom Zip: W1S 3AT Product: Investment bank working with financial...

  18. Clean Earth Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Capital LLP Jump to: navigation, search Name: Clean Earth Capital LLP Place: EDINBURGH, United Kingdom Zip: EH6 4NW Sector: Renewable Energy Product: Edinburgh-based corporate...

  19. James Monroe Capital Corporation | Open Energy Information

    Open Energy Info (EERE)

    Monroe Capital Corporation Jump to: navigation, search Name: James Monroe Capital Corporation Place: United States Sector: Services Product: General Financial & Legal Services (...

  20. Osmosis Capital | Open Energy Information

    Open Energy Info (EERE)

    Osmosis Capital Jump to: navigation, search Name: Osmosis Capital Place: London, United Kingdom Zip: EC4M 9DN Sector: Carbon Product: An investment firm seeking low carbon economy...

  1. Evaluation of syngas production unit cost of bio-gasification facility using regression analysis techniques

    SciTech Connect (OSTI)

    Deng, Yangyang; Parajuli, Prem B.

    2011-08-10

    Evaluation of economic feasibility of a bio-gasification facility needs understanding of its unit cost under different production capacities. The objective of this study was to evaluate the unit cost of syngas production at capacities from 60 through 1800Nm 3/h using an economic model with three regression analysis techniques (simple regression, reciprocal regression, and log-log regression). The preliminary result of this study showed that reciprocal regression analysis technique had the best fit curve between per unit cost and production capacity, with sum of error squares (SES) lower than 0.001 and coefficient of determination of (R 2) 0.996. The regression analysis techniques determined the minimum unit cost of syngas production for micro-scale bio-gasification facilities of $0.052/Nm 3, under the capacity of 2,880 Nm 3/h. The results of this study suggest that to reduce cost, facilities should run at a high production capacity. In addition, the contribution of this technique could be the new categorical criterion to evaluate micro-scale bio-gasification facility from the perspective of economic analysis.

  2. Break-Even Cost for Residential Photovoltaics in the United States: Key Drivers and Sensitivities

    SciTech Connect (OSTI)

    Denholm, P.; Margolis, R. M.; Ong, S.; Roberts, B.

    2009-12-01

    Grid parity--or break-even cost--for photovoltaic (PV) technology is defined as the point where the cost of PV-generated electricity equals the cost of electricity purchased from the grid. Break-even cost is expressed in $/W of an installed system. Achieving break-even cost is a function of many variables. Consequently, break-even costs vary by location and time for a country, such as the United States, with a diverse set of resources, electricity prices, and other variables. In this report, we analyze PV break-even costs for U.S. residential customers. We evaluate some key drivers of grid parity both regionally and over time. We also examine the impact of moving from flat to time-of-use (TOU) rates, and we evaluate individual components of the break-even cost, including effect of rate structure and various incentives. Finally, we examine how PV markets might evolve on a regional basis considering the sensitivity of the break-even cost to four major drivers: technical performance, financing parameters, electricity prices and rates, and policies. We find that local incentives rather than ?technical? parameters are in general the key drivers of the break-even cost of PV. Additionally, this analysis provides insight about the potential viability of PV markets.

  3. (OECD Expert Group meeting on reduction of capital costs of nuclear power plants, Paris, France, July 21--26, 1989): Foreign trip report

    SciTech Connect (OSTI)

    Hudson, C.R. II

    1989-08-09

    The OECD initiated a study of means to reduce the capital costs of nuclear power plants in the latter part of 1988. To accomplish the study, an Expert Group consisting of representatives of OECD member countries was formed. The initial meeting of the Expert Group was held in November 1988. A second meeting, documented in an ORNL trip report by this author, was held in May 1989. This meeting represents the third follow-on meeting with the primary goal of reviewing the draft report written by members of the Expert Group.

  4. Cost and Performance Assumptions for Modeling Electricity Generation...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... 16 Figure 6. Overnight capital costs-coal ......22 Figure 8. Overnight capital costs-combustion turbine ......

  5. Microsoft PowerPoint - Cost Escalation.ppt

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Hydroelectric Design Center Hydroelectric Design Center " " Cost Trends for Cost Trends for Hydropower Capital Hydropower Capital Replacements" Replacements" Presentation Outline ...

  6. Cost Effectiveness of Home Energy Retrofits in Pre-Code Vintage Homes in the United States

    SciTech Connect (OSTI)

    Fairey, Philip

    2012-11-01

    This analytical study examines the opportunities for cost-effective energy efficiency and renewable energy retrofits in residential archetypes constructed prior to 1980 (Pre-Code) in fourteen U.S. cities. These fourteen cities are representative of each of the International Energy Conservation Code (IECC) climate zones in the contiguous United States. The analysis is conducted using an in-house version of EnergyGauge USA v.2.8.05 named CostOpt that has been programmed to perform iterative, incremental economic optimization on a large list of residential energy efficiency and renewable energy retrofit measures. The principle objectives of the study are to determine the opportunities for cost effective source energy reductions in this large cohort of existing residential building stock as a function of local climate and energy costs; and to examine how retrofit financing alternatives impact the source energy reductions that are cost effectively achievable.

  7. Cost of Wind Energy in the United States: Trends from 2007 to 2012 (Presentation)

    SciTech Connect (OSTI)

    Hand, M.

    2015-01-01

    This presentation provides an overview of recent technology trends observed in the United States including project size, turbine size, rotor diameter, hub height, annual average wind speed, and annual energy production. It also highlights area where system analysis is required to fully understand how these technology trends relate to the cost of wind energy.

  8. EM Capital Asset Project List

    Broader source: Energy.gov [DOE]

    Read the EM Capital Asset Project List, which includes the project's name, site, current critical decision and current total project cost.

  9. Cost-effectiveness of emission control at fossil-fuel units for different cumulative load patterns

    SciTech Connect (OSTI)

    Roy, S.

    1997-02-01

    This paper describes a method to recommend allocation of generating units, with a view to achieve cost-effective control of particulate and gaseous emissions over an energy scenario. Definition of relative cost and relative emission, with respect to corresponding base-case values, allows one to develop a model that describes cost and emission aspects of the chosen scenario. Optimization of this model, by any appropriate linear-programming software, yields the allocation levels to be recommended. The emphasis of this paper is on the way in which results of the said optimization model reflect the effect of demand patterns on the allocation levels. Depending on the demands, required generation levels from each individual unit may differ. This affects the overall generation cost, and simultaneously the emissions from the thermal units, both relative to respective base values. Since the optimization algorithm attempts to reduce both the relative quantities, its results always reflect the changing generation vs. emission tradeoff for utilities vis-a-vis different demand patterns.

  10. Energy Conservation Program for Consumer Products: Representative Average Unit Costs of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Conservation Program for Consumer Products: Representative Average Unit Costs of Energy, is a notice issued by the Department of Energy. Though it is not intended or expected, should any discrepancy occur between the document posted here and the document published in the Federal Register, the Federal Register publication controls. This document is being made available through the Internet solely as a means to facilitate the public's access to this document."

  11. The Capital Intensity of Photovoltaics Manufacturing

    SciTech Connect (OSTI)

    Basore, Paul

    2015-10-19

    Factory capital expenditure (capex) for photovoltaic (PV) module manufacturing strongly influences the per-unit cost of a c-Si module. This provides a significant opportunity to address the U.S. DOE SunShot module price target through capex innovation. Innovation options to reduce the capex of PV manufacturing include incremental and disruptive process innovation with c-Si, platform innovations, and financial approaches. and financial approaches.

  12. Best Practices for Controlling Capital Costs in Net Zero Energy Design and Construction- 2014 BTO Peer Review

    Broader source: Energy.gov [DOE]

    Presenter: Shanti Pless, National Renewable Energy Laboratory For net zero energy (NZE) building performance to become the norm in new commercial construction, it is necessary to demonstrate that NZE can be achieved cost effectively.

  13. Operating Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter is focused on capital costs for conventional construction and environmental restoration and waste management projects and examines operating cost estimates to verify that all elements of the project have been considered and properly estimated.

  14. Energy Savings and Breakeven Costs for Residential Heat Pump Water Heaters in the United States

    SciTech Connect (OSTI)

    Maguire, Jeff; Burch, Jay; Merrigan, Tim; Ong, Sean

    2013-07-01

    Heat pump water heaters (HPWHs) have recently re-emerged in the U.S. residential water heating market and have the potential to provide homeowners with significant energy savings. However, there are questions as to the actual performance and energy savings potential of these units, in particular in regards to the heat pump's performance in unconditioned space and the impact of the heat pump on space heating and cooling loads when it is located in conditioned space. To help answer these questions, NREL performed simulations of a HPWH in both conditioned and unconditioned space at over 900 locations across the continental United States and Hawaii. Simulations included a Building America benchmark home so that any interaction between the HPWH and the home's HVAC equipment could be captured. Comparisons were performed to typical gas and electric water heaters to determine the energy savings potential and cost effectiveness of a HPWH relative to these technologies. HPWHs were found to have a significant source energy savings potential when replacing typical electric water heaters, but only saved source energy relative to gas water heater in the most favorable installation locations in the southern United States. When replacing an electric water heater, the HPWH is likely to break even in California, the southern United States, and parts of the northeast in most situations. However, the HPWH will only break even when replacing a gas water heater in a few southern states.

  15. Ricmore Capital PLC Formerly Energy Asset Management Plc | Open...

    Open Energy Info (EERE)

    Ricmore Capital PLC Formerly Energy Asset Management Plc Jump to: navigation, search Name: Ricmore Capital PLC (Formerly Energy Asset Management Plc) Place: United Kingdom Sector:...

  16. Free Stream Capital Partners Limited | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Limited Jump to: navigation, search Name: Free Stream Capital Partners Limited Place: London, Greater London, United Kingdom Zip: SW1Y 4AA Sector: Wind energy...

  17. A preliminary design and BOP cost analysis of M-C Power`s MCFC commerical unit

    SciTech Connect (OSTI)

    Chen, T.P.

    1996-12-31

    M-C Power Corporation plans to introduce its molten carbonate fuel cell (MCFC) market entry unit in the year 2000 for distributed and on-site power generation. Extensive efforts have been made to analyze the cell stack manufacturing costs. The major objective of this study is to conduct a detailed analysis of BOP costs based on an initial design of the market entry unit.

  18. Access to Capital | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Soft Costs Access to Capital Access to Capital Photo of a room full of people seated in rows with a few standing in the background. Two hands in the crowd are holding up sheets ...

  19. Pulsar Energy Capital L L P | Open Energy Information

    Open Energy Info (EERE)

    Pulsar Energy Capital L L P Jump to: navigation, search Name: Pulsar Energy Capital L.L.P. Place: London, United Kingdom Zip: SW20 0PU Product: Pulsar Energy Capital LLP is a...

  20. Absolute Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Absolute Energy Capital Place: London, United Kingdom Zip: SW1Y 5NQ Product: London-based private equity firm. Coordinates: 51.506325,...

  1. Englefield Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Englefield Capital LLP Jump to: navigation, search Name: Englefield Capital LLP Place: London, Greater London, United Kingdom Zip: SW3 6RD Product: London-based private equity fund...

  2. Emerging Edge Capital EEC | Open Energy Information

    Open Energy Info (EERE)

    Edge Capital EEC Jump to: navigation, search Name: Emerging Edge Capital (EEC) Place: London, United Kingdom Zip: SW1Y 4RS Sector: Renewable Energy Product: London-based company...

  3. Plane Tree Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Plane Tree Capital LLP Jump to: navigation, search Name: Plane Tree Capital LLP Place: London, United Kingdom Zip: W1J 8DY Sector: Carbon Product: London-based investment...

  4. Absolut Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Absolut Energy Capital Jump to: navigation, search Name: Absolut Energy Capital Place: London, England, United Kingdom Zip: W1H - 6HN Sector: Renewable Energy Product: London-based...

  5. Sindicatum Carbon Capital SCC | Open Energy Information

    Open Energy Info (EERE)

    Sindicatum Carbon Capital SCC Jump to: navigation, search Name: Sindicatum Carbon Capital (SCC) Place: London, United Kingdom Zip: W1S 1HX Product: SCC is a specialist end-to-end...

  6. Carbon Capital Markets | Open Energy Information

    Open Energy Info (EERE)

    Capital Markets Jump to: navigation, search Name: Carbon Capital Markets Place: London, United Kingdom Zip: W1J 8DY Sector: Carbon Product: London-based fund manager and trader...

  7. Renewable Energy Cost Modeling: A Toolkit for Establishing Cost-Based Incentives in the United States; March 2010 -- March 2011

    SciTech Connect (OSTI)

    Gifford, J. S.; Grace, R. C.; Rickerson, W. H.

    2011-05-01

    This report is intended to serve as a resource for policymakers who wish to learn more about establishing cost-based incentives. The report will identify key renewable energy cost modeling options, highlight the policy implications of choosing one approach over the other, and present recommendations on the optimal characteristics of a model to calculate rates for cost-based incentives, feed-in tariffs (FITs), or similar policies. These recommendations will be utilized in designing the Cost of Renewable Energy Spreadsheet Tool (CREST). Three CREST models will be publicly available and capable of analyzing the cost of energy associated with solar, wind, and geothermal electricity generators. The CREST models will be developed for use by state policymakers, regulators, utilities, developers, and other stakeholders to assist them in current and future rate-setting processes for both FIT and other renewable energy incentive payment structures and policy analyses.

  8. Economic impacts of oil spills: Spill unit costs for tankers, pipelines, refineries, and offshore facilities. [Task 1, Final report

    SciTech Connect (OSTI)

    Not Available

    1993-10-15

    The impacts of oil spills -- ranging from the large, widely publicized Exxon Valdez tanker incident to smaller pipeline and refinery spills -- have been costly to both the oil industry and the public. For example, the estimated costs to Exxon of the Valdez tanker spill are on the order of $4 billion, including $2.8 billion (in 1993 dollars) for direct cleanup costs and $1.125 billion (in 1992 dollars) for settlement of damages claims caused by the spill. Application of contingent valuation costs and civil lawsuits pending in the State of Alaska could raise these costs appreciably. Even the costs of the much smaller 1991 oil spill at Texaco`s refinery near Anacortes, Washington led to costs of $8 to 9 million. As a result, inexpensive waming, response and remediation technologies could lower oil spin costs, helping both the oil industry, the associated marine industries, and the environment. One means for reducing the impact and costs of oil spills is to undertake research and development on key aspects of the oil spill prevention, warming, and response and remediation systems. To target these funds to their best use, it is important to have sound data on the nature and size of spills, their likely occurrence and their unit costs. This information could then allow scarce R&D dollars to be spent on areas and activities having the largest impact. This report is intended to provide the ``unit cost`` portion of this crucial information. The report examines the three key components of the US oil supply system, namely, tankers and barges; pipelines and refineries; and offshore production facilities. The specific purpose of the study was to establish the unit costs of oil spills. By manipulating this key information into a larger matrix that includes the size and frequency of occurrence of oil spills, it will be possible` to estimate the likely future impacts, costs, and sources of oil spills.

  9. Energy Savings and Breakeven Cost for Residential Heat Pump Water Heaters in the United States

    SciTech Connect (OSTI)

    Maguire, J.; Burch, J.; Merrigan, T.; Ong, S.

    2013-07-01

    Heat pump water heaters (HPWHs) have recently reemerged in the U.S. residential water heating market and have the potential to provide homeowners with significant energy savings. However, there are questions as to the actual performance and energy savings potential of these units, in particular in regards to the heat pump's performance in unconditioned space and the impact of the heat pump on space heating and cooling loads when it is located in conditioned space. To help answer these questions, simulations were performed of a HPWH in both conditioned and unconditioned space at over 900 locations across the continental United States and Hawaii. Simulations included a Building America benchmark home so that any interaction between the HPWH and the home's HVAC equipment could be captured. Comparisons were performed to typical gas and electric water heaters to determine the energy savings potential and cost effectiveness of a HPWH relative to these technologies. HPWHs were found to have a significant source energy savings potential when replacing typical electric water heaters, but only saved source energy relative to gas water heater in the most favorable installation locations in the southern US. When replacing an electric water heater, the HPWH is likely to break even in California, the southern US, and parts of the northeast in most situations. However, the HPWH will only break even when replacing a gas water heater in a few southern states.

  10. QGESS: Capital Cost Scaling Methodology

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    QUALITY GUIDELINES FOR ENERGY SYSTEM STUDIES Performing a Techno-economic Analysis for Power Generation Plants DOENETL-2010???? DOENETL-20151726 Techno-economic Analysis...

  11. Break-Even Cost for Residential Solar Water Heating in the United States: Key Drivers and Sensitivities

    SciTech Connect (OSTI)

    Cassard, H.; Denholm, P.; Ong, S.

    2011-02-01

    This paper examines the break-even cost for residential rooftop solar water heating (SWH) technology, defined as the point where the cost of the energy saved with a SWH system equals the cost of a conventional heating fuel purchased from the grid (either electricity or natural gas). We examine the break-even cost for the largest 1,000 electric and natural gas utilities serving residential customers in the United States as of 2008. Currently, the break-even cost of SWH in the United States varies by more than a factor of five for both electricity and natural gas, despite a much smaller variation in the amount of energy saved by the systems (a factor of approximately one and a half). The break-even price for natural gas is lower than that for electricity due to a lower fuel cost. We also consider the relationship between SWH price and solar fraction and examine the key drivers behind break-even costs. Overall, the key drivers of the break-even cost of SWH are a combination of fuel price, local incentives, and technical factors including the solar resource location, system size, and hot water draw.

  12. Foundation Capital

    Broader source: Energy.gov (indexed) [DOE]

    FC, ORNL, MB Confidential 3 Foundation Capital Confidential Distribution of 1,500 reviewed ORNL IP Out of 3,000 Total Disclosures Filed Over 25 yrs FC, ORNL, MB Confidential Many ...

  13. Benchmarking Soft Costs for PV Systems in the United States (Presentation)

    SciTech Connect (OSTI)

    Ardani, K.

    2012-06-01

    This paper presents results from the first U.S. based data collection effort to quantify non-hardware, business process costs for PV systems at the residential and commercial scales, using a bottom-up approach. Annual expenditure and labor hour productivity data are analyzed to benchmark business process costs in the specific areas of: (1) customer acquisition; (2) permitting, inspection, and interconnection; (3) labor costs of third party financing; and (4) installation labor.

  14. Tracking the Sun III; The Installed Cost of Photovoltaics in the United States from 1998-2009

    SciTech Connect (OSTI)

    Barbose, Galen; Darghouth, Naim; Wiser, Ryan

    2010-12-13

    Installations of solar photovoltaic (PV) systems have been growing at a rapid pace in recent years. In 2009, approximately 7,500 megawatts (MW) of PV were installed globally, up from approximately 6,000 MW in 2008, consisting primarily of grid-connected applications. With 335 MW of grid-connected PV capacity added in 2009, the United States was the world's fourth largest PV market in 2009, behind Germany, Italy, and Japan. The market for PV in the United States is driven by national, state, and local government incentives, including up-front cash rebates, production-based incentives, requirements that electricity suppliers purchase a certain amount of solar energy, and federal and state tax benefits. These programs are, in part, motivated by the popular appeal of solar energy, and by the positive attributes of PV - modest environmental impacts, avoidance of fuel price risks, coincidence with peak electrical demand, and the possible deployment of PV at the point of use. Given the relatively high cost of PV, however, a key goal of these policies is to encourage cost reductions over time. Therefore, as policy incentives have become more significant and as PV deployment has accelerated, so too has the desire to track the installed cost of PV systems over time, by system characteristics, by system location, and by component. Despite the significant year-on-year growth, however, the share of global and U.S. electricity supply met with PV remains small, and annual PV additions are currently modest in the context of the overall electric system. To address this need, Lawrence Berkeley National Laboratory initiated a report series focused on describing trends in the installed cost of grid-connected PV systems in the United States. The present report, the third in the series, describes installed cost trends from 1998 through 2009, and provides preliminary cost data for systems installed in 2010. The analysis is based on project-level cost data from approximately 78

  15. Return to 1990: The cost of mitigating United States carbon emissions in the post-2000 period

    SciTech Connect (OSTI)

    Edmonds, J.A.; Kim, S.H.; MacCracken, C.N.; Sands, R.D.; Wise, M.A.

    1997-10-01

    The Second Generation Model (SGM) is employed to examine four hypothetical agreements to reduce emissions in Annex 1 nations (OECD nations plus most of the nations of Eastern Europe and the former Soviet Union) to levels in the neighborhood of those which existed in 1990, with obligations taking effect in the year 2010. The authors estimate the cost to the US of complying with such agreements under three distinct conditions: no trading of emissions rights, trading of emissions rights only among Annex 1 nations, and a fully global trading regime. The authors find that the marginal cost of returning to 1990 emissions levels in the US in the absence of trading opportunities is approximately $108 per metric ton carbon in 2010. The total cost in that year is approximately 0.2% of GDP. International trade in emissions permits lowers the cost of achieving any mitigation objective by equalizing the marginal cost of carbon mitigation among countries. For the four mitigation scenarios in this study, economic costs to the US remain below 1% of GDP through at least the year 2020.

  16. Cost of Power Interruptions to Electricity Consumers in the UnitedStates (U.S.)

    SciTech Connect (OSTI)

    Hamachi LaCommare, Kristina; Eto, Joseph H.

    2006-02-16

    The massive electric power blackout in the northeastern U.S.and Canada on August 14-15, 2003 catalyzed discussions about modernizingthe U.S. electricity grid. Industry sources suggested that investments of$50 to $100 billion would be needed. This work seeks to better understandan important piece of information that has been missing from thesediscussions: What do power interruptions and fluctuations in powerquality (power-quality events) cost electricity consumers? We developed abottom-up approach for assessing the cost to U.S. electricity consumersof power interruptions and power-quality events (referred to collectivelyas "reliability events"). The approach can be used to help assess thepotential benefits of investments in improving the reliability of thegrid. We developed a new estimate based on publicly availableinformation, and assessed how uncertainties in these data affect thisestimate using sensitivity analysis.

  17. Analysis of Cycling Costs in Western Wind and Solar Integration Study

    SciTech Connect (OSTI)

    Jordan, G.; Venkataraman, S.

    2012-06-01

    The Western Wind and Solar Integration Study (WWSIS) examined the impact of up to 30% penetration of variable renewable generation on the Western Electricity Coordinating Council system. Although start-up costs and higher operating costs because of part-load operation of thermal generators were included in the analysis, further investigation of additional costs associated with thermal unit cycling was deemed worthwhile. These additional cycling costs can be attributed to increases in capital as well as operations and maintenance costs because of wear and tear associated with increased unit cycling. This analysis examines the additional cycling costs of the thermal fleet by leveraging the results of WWSIS Phase 1 study.

  18. Sustainable Investments Capital SI Capital | Open Energy Information

    Open Energy Info (EERE)

    Investments Capital SI Capital Jump to: navigation, search Name: Sustainable Investments Capital (SI Capital) Place: Barcelona, Spain Zip: 8021 Sector: Renewable Energy, Services...

  19. Utility-Scale Solar 2014. An Empirical Analysis of Project Cost, Performance, and Pricing Trends in the United States

    SciTech Connect (OSTI)

    Bolinger, Mark; Seel, Joachim

    2015-09-01

    Other than the nine Solar Energy Generation Systems (“SEGS”) parabolic trough projects built in the 1980s, virtually no large-scale or “utility-scale” solar projects – defined here to include any groundmounted photovoltaic (“PV”), concentrating photovoltaic (“CPV”), or concentrating solar thermal power (“CSP”) project larger than 5 MWAC – existed in the United States prior to 2007. By 2012 – just five years later – utility-scale had become the largest sector of the overall PV market in the United States, a distinction that was repeated in both 2013 and 2014 and that is expected to continue for at least the next few years. Over this same short period, CSP also experienced a bit of a renaissance in the United States, with a number of large new parabolic trough and power tower systems – some including thermal storage – achieving commercial operation. With this critical mass of new utility-scale projects now online and in some cases having operated for a number of years (generating not only electricity, but also empirical data that can be mined), the rapidly growing utility-scale sector is ripe for analysis. This report, the third edition in an ongoing annual series, meets this need through in-depth, annually updated, data-driven analysis of not just installed project costs or prices – i.e., the traditional realm of solar economics analyses – but also operating costs, capacity factors, and power purchase agreement (“PPA”) prices from a large sample of utility-scale solar projects in the United States. Given its current dominance in the market, utility-scale PV also dominates much of this report, though data from CPV and CSP projects are presented where appropriate.

  20. Mapping water availability, projected use and cost in the western United States

    SciTech Connect (OSTI)

    Vincent C. Tidwell; Barbara D. Moreland; Katie M. Zemlick; Barry L. Roberts; Howard D. Passell; Daniel Jensen; Christopher Forsgren; Gerald Sehlke; Margaret A. Cook; Carey W. King

    2014-06-01

    New demands for water can be satisfied through a variety of source options. In some basins surface and/or groundwater may be available through permitting with the state water management agency (termed unappropriated water), alternatively water might be purchased and transferred out of its current use to another (termed appropriated water), or non-traditional water sources can be captured and treated (e.g., wastewater). The relative availability and cost of each source are key factors in the development decision. Unfortunately, these measures are location dependent with no consistent or comparable set of data available for evaluating competing water sources. With the help of western water managers, water availability was mapped for over 1200 watersheds throughout the western US. Five water sources were individually examined, including unappropriated surface water, unappropriated groundwater, appropriated water, municipal wastewater and brackish groundwater. Also mapped was projected change in consumptive water use from 2010 to 2030. Associated costs to acquire, convey and treat the water, as necessary, for each of the five sources were estimated. These metrics were developed to support regional water planning and policy analysis with initial application to electric transmission planning in the western US.

  1. Reduced coated-tubing failures cut costs at Dickinson Heath Sand Unit

    SciTech Connect (OSTI)

    Brus, K.R. )

    1990-03-01

    In the Dickinson Heath Sand Unit waterflood, corrosion-related failures of coated injection tubing began accelerating in 1979 with the increased water production attributed to waterflood response. The trend peaked in 1984 when $164,000 was spent pulling failed tubing (34 workovers). Starting in 1983, the selection of coatings, coating-application-process quality control, and handling/installation procedures were examined, modified, and refined. The author discusses how these changes and improvements resulted in fewer pulling jobs and less money spent on associated workovers during 1988.

  2. Venture Capital Finance

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Venture Capital Finance DOE Biomass Conference July 2014 Priced Out of Oil ... Into What? Energy Source Commodity Price Sun: $0 / GJ Oil (6.2 GJ/bbl) $10/bbl = $1.6 / GJ (late 1990s) Coal: $3 - 6 / GJ Natural Gas (N America) $3 - 4 / GJ Biomass (15 GJ/dt) $60-100/dt = $4 - 6 / GJ Natural Gas (ex N America) $10 - 15 / GJ Oil (6.2 GJ/bbl) $100/bbl = $16 / GJ Corn $4-7/bu= $10 - 20 / GJ 2 * Higher oil prices create a disruptive opportunity for lower cost feedstocks * North American shale gas is a

  3. 2011 Cost of Wind Energy Review

    SciTech Connect (OSTI)

    Tegen, S.; Lantz, E.; Hand, M.; Maples, B.; Smith, A.; Schwabe, P.

    2013-03-01

    This report describes the levelized cost of energy (LCOE) for a typical land-based wind turbine installed in the United States in 2011, as well as the modeled LCOE for a fixed-bottom offshore wind turbine installed in the United States in 2011. Each of the four major components of the LCOE equation are explained in detail, such as installed capital cost, annual energy production, annual operating expenses, and financing, and including sensitivity ranges that show how each component can affect LCOE. These LCOE calculations are used for planning and other purposes by the U.S. Department of Energy's Wind Program.

  4. Wind Technology, Cost, and Performance Trends in Denmark, Germany, Ireland, Norway, the European Union, and the United States: 2007 - 2012; NREL (National Renewable Energy Laboratory)

    SciTech Connect (OSTI)

    Hand, Maureen

    2015-06-15

    This presentation provides a summary of IEA Wind Task 26 report on Wind Technology, Cost, and Performance Trends in Denmark, Germany, Ireland, Norway, the European Union, and the United States: 2007-2012

  5. An Evaluation of the Total Cost of Ownership of Fuel Cell-Powered...

    Broader source: Energy.gov (indexed) [DOE]

    handling equipment, including the capital costs of battery and fuel cell systems, the cost of supporting infrastructure, maintenance costs, warehouse space costs, and labor costs. ...

  6. Building a market for small wind: The break-even turnkey cost of residential wind systems in the United States

    SciTech Connect (OSTI)

    Edwards, Jennifer L.; Wiser, Ryan; Bolinger, Mark; Forsyth, Trudy

    2004-03-01

    Although small wind turbine technology and economics have improved in recent years, the small wind market in the United States continues to be driven in large part by state incentives, such as cash rebates, favorable loan programs, and tax credits. This paper examines the state-by-state economic attractiveness of small residential wind systems. Economic attractiveness is evaluated primarily using the break-even turnkey cost (BTC) of a residential wind system as the figure of merit. The BTC is defined here as the aggregate installed cost of a small wind system that could be supported such that the system owner would break even (and receive a specified return on investment) over the life of the turbine, taking into account current available incentives, the wind resource, and the retail electricity rate offset by on-site generation. Based on the analysis presented in this paper, we conclude that: (1) the economics of residential, grid-connected small wind systems is highly variable by state and wind resource class, (2) significant cost reductions will be necessary to stimulate widespread market acceptance absent significant changes in the level of policy support, and (3) a number of policies could help stimulate the market, but state cash incentives currently have the most significant impact, and will be a critical element of continued growth in this market.

  7. Capital Asset Project List.xls

    Broader source: Energy.gov (indexed) [DOE]

    as defined by DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets. CD0 Approve Mission Need CD1 Approve Alternative Selection and Cost Range CD2...

  8. How three smart managers control steam costs

    SciTech Connect (OSTI)

    Kendall, R.

    1982-11-01

    Three steam-intensive companies report innovative ways to reduce steam-production costs. Goodyear Tire and Rubber Co. concentrated on regular maintenance, process modifications, and heat recovery, but also has an on-going policy of seeking further cost savings. Future efforts will explore computer-based boiler controls. Zenith Radio Corporation's color picture tube-making process uses 12% less steam after 700 mechanical steam traps were replaced with fixed-orifice traps. Petro-Tex Chemical Corp. reduced steam costs by monitoring and optimizing process units and by making capital investments to improve steam management. (DCK)

  9. Beetle Capital Partners BCP | Open Energy Information

    Open Energy Info (EERE)

    Partners BCP Jump to: navigation, search Name: Beetle Capital Partners (BCP) Place: London, United Kingdom Zip: W1S 1UA Sector: Carbon Product: London-based asset management...

  10. Human Capital: The Role of Ombudsmen in Dispute Resolution

    Broader source: Energy.gov (indexed) [DOE]

    United States General Accounting Office GAO April 2001 HUMAN CAPITAL The Role of Ombudsmen ... Accounting Office GS General Schedule HR human resource IBB International Broadcasting ...

  11. Copy of Capitalized Property RO23_120213_1.xlsx

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capitalized Property 1 RO BARCODE DESCRIPTION MANUF. MODEL SN COST BLDG ROOM INVT_DATE 23 C5508 PRECISION ION POLISH GATAN INC 691 UNIT 427 01070301 $50,626.00 28 113 24-Sep-13 23 0000002116 TouchTable System TOUCHTABLE TT45 TT45S000378 $52,986.00 B03 134 19-Sep-13 23 0000002362 SYSTEM PUMP AMETEK Q AMETEK Q5000 CYL1A1308CYLIB1309CM $56,260.00 OFF TEXAS 11-Sep-12 23 0000000577 ANALYSIS SYSTEM BENC PFEIFFER GSD 301 C 44253789 $57,731.50 B25 115 30-Sep-13 23 0000002222 SLAVE NODES PSSC LABS PSSC

  12. Tracking the Sun IV: An Historical Summary of the Installed Cost of Photovoltaics in the United States from 1998 to 2010

    SciTech Connect (OSTI)

    Darghouth, Naim; Wiser, Ryan

    2011-09-07

    The present report describes installed cost trends for grid-connected PV projects installed from 1998 through 2010 (with some limited and preliminary results presented for projects installed in the first six months of 2011). The analysis is based on project-level cost data from approximately 116,500 residential, non-residential, and utility-sector PV systems in the United States. The inclusion of utility-sector PV is a new element in this year’s report. The combined capacity of all systems in the data sample totals 1,685 MW, equal to 79% of all grid-connected PV capacity installed in the United States through 2010 and representing one of the most comprehensive sources of installed PV cost data for the U.S. Based on this dataset, the report describes historical installed cost trends over time, and by location, market segment, technology type, and component. The report also briefly compares recent PV installed costs in the United States to those in Germany and Japan, and describes trends in customer incentives for PV installations and net installed costs after receipt of such incentives. The analysis presented here focuses on descriptive trends in the underlying data, serving primarily to summarize the data in tabular and graphical form.

  13. Greenworld Capital | Open Energy Information

    Open Energy Info (EERE)

    Greenworld Capital Jump to: navigation, search Name: Greenworld Capital Place: Pennsylvania Zip: 10000 Sector: Services Product: GreenWorld Capital provides investment banking...

  14. Greencore Capital | Open Energy Information

    Open Energy Info (EERE)

    Greencore Capital Jump to: navigation, search Name: Greencore Capital Place: San Diego, California Zip: 92121 Sector: Services Product: String representation "GreenCore Capit ... s...

  15. Yellowstone Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Logo: Yellowstone Capital Name: Yellowstone Capital Address: 5555 San Felipe, Suite 1650 Place: Houston, Texas Zip: 77056 Region: Texas Area...

  16. Nite Capital | Open Energy Information

    Open Energy Info (EERE)

    Nite Capital Jump to: navigation, search Name: Nite Capital Place: Libertyville, Illinois Zip: 60048 Product: Nite Capital provides private financing for small-cap and micro-cap...

  17. Greener Capital | Open Energy Information

    Open Energy Info (EERE)

    Greener Capital Jump to: navigation, search Name: Greener Capital Place: San Francisco, California Product: San Francisco-based clean technology VC. References: Greener Capital1...

  18. GGV Capital | Open Energy Information

    Open Energy Info (EERE)

    GGV Capital Jump to: navigation, search Name: GGV Capital Place: Menlo Park, California Zip: 94025 Product: String representation "GGV Capital" ... U.S. and China." is too...

  19. CMEA Capital | Open Energy Information

    Open Energy Info (EERE)

    CMEA Capital Jump to: navigation, search Logo: CMEA Capital Name: CMEA Capital Address: 1 Embarcadero Center Place: San Francisco, California Zip: 94111 Region: Bay Area Number of...

  20. Clarey Capital | Open Energy Information

    Open Energy Info (EERE)

    Clarey Capital Jump to: navigation, search Name: Clarey Capital Place: Irvine, California Zip: 92617 Sector: Renewable Energy Product: String representation "Clarey Capital ... of...

  1. BEV Capital | Open Energy Information

    Open Energy Info (EERE)

    BEV Capital Jump to: navigation, search Logo: BEV Capital Name: BEV Capital Address: 263 Tresser Blvd., 9th Floor Place: Stamford, Connecticut Zip: 06901 Region: Northeast - NY NJ...

  2. Infield Capital | Open Energy Information

    Open Energy Info (EERE)

    Infield Capital Jump to: navigation, search Name: Infield Capital Place: Boulder, Colorado Product: Infield Capital was founded in 2008, and is focused on investment in early-stage...

  3. Greenview Capital | Open Energy Information

    Open Energy Info (EERE)

    Greenview Capital Jump to: navigation, search Name: Greenview Capital Place: Libertyville, Illinois Zip: 60048 Product: Greenview Capital is a U.S. based consulting firm and...

  4. Earthrise Capital | Open Energy Information

    Open Energy Info (EERE)

    Earthrise Capital Jump to: navigation, search Logo: Earthrise Capital Name: Earthrise Capital Address: 45 Rockefeller Plaza, 20th Floor Place: New York, New York Zip: 10111 Region:...

  5. Atrium Capital | Open Energy Information

    Open Energy Info (EERE)

    Atrium Capital Jump to: navigation, search Logo: Atrium Capital Name: Atrium Capital Address: 3000 Sand Hill Road, Building 2, Suite 240 Place: Menlo Park, California Zip: 94025...

  6. Commons Capital | Open Energy Information

    Open Energy Info (EERE)

    Commons Capital Jump to: navigation, search Logo: Commons Capital Name: Commons Capital Address: 320 Washington Street, 4th floor Place: Brookline, Massachusetts Zip: 02445 Region:...

  7. Report: EM Human Capital Initiatives

    Office of Environmental Management (EM)

    HUMAN CAPITAL September 25, 2008 Submitted by the EMAB Human Capital Subcommittee Background: The enhancement of the Office of Environmental Management's (EM) human capital has ...

  8. IEA Wind Task 26. Wind Technology, Cost, and Performance Trends in Denmark, Germany, Ireland, Norway, the European Union, and the United States: 2007–2012

    SciTech Connect (OSTI)

    Vitina, Aisma; Lüers, Silke; Wallasch, Anna-Kathrin; Berkhout, Volker; Duffy, Aidan; Cleary, Brendan; Husabø, Lief I.; Weir, David E.; Lacal-Arántegui, Roberto; Hand, Maureen; Lantz, Eric; Belyeu, Kathy; Wiser, Ryan H; Bolinger, Mark; Hoen, Ben

    2015-06-01

    The International Energy Agency Implementing Agreement for cooperation in Research, Development, and Deployment of Wind Energy Systems (IEA Wind) Task 26—The Cost of Wind Energy represents an international collaboration dedicated to exploring past, present and future cost of wind energy. This report provides an overview of recent trends in wind plant technology, cost, and performance in those countries that are currently represented by participating organizations in IEA Wind Task 26: Denmark, Germany, Ireland, Norway, and the United States as well as the European Union.

  9. An examination of the costs and critical characteristics of electric utility distribution system capacity enhancement projects

    SciTech Connect (OSTI)

    Balducci, Patrick J.; Schienbein, Lawrence A.; Nguyen, Tony B.; Brown, Daryl R.; Fathelrahman, Eihab M.

    2004-06-01

    This report classifies and analyzes the capital and total costs (e.g., income tax, property tax, depreciation, centralized power generation, insurance premiums, and capital financing) associated with 130 electricity distribution system capacity enhancement projects undertaken during 1995-2002 or planned in the 2003-2011 time period by three electric power utilities operating in the Pacific Northwest. The Pacific Northwest National Laboratory (PNNL), in cooperation with participating utilities, has developed a large database of over 3,000 distribution system projects. The database includes brief project descriptions, capital cost estimates, the stated need for each project, and engineering data. The database was augmented by additional technical (e.g., line loss, existing substation capacities, and forecast peak demand for power in the area served by each project), cost (e.g., operations, maintenance, and centralized power generation costs), and financial (e.g., cost of capital, insurance premiums, depreciations, and tax rates) data. Though there are roughly 3,000 projects in the database, the vast majority were not included in this analysis because they either did not clearly enhance capacity or more information was needed, and not available, to adequately conduct the cost analyses. For the 130 projects identified for this analysis, capital cost frequency distributions were constructed, and expressed in terms of dollars per kVA of additional capacity. The capital cost frequency distributions identify how the projects contained within the database are distributed across a broad cost spectrum. Furthermore, the PNNL Energy Cost Analysis Model (ECAM) was used to determine the full costs (e.g., capital, operations and maintenance, property tax, income tax, depreciation, centralized power generation costs, insurance premiums and capital financing) associated with delivering electricity to customers, once again expressed in terms of costs per kVA of additional capacity

  10. Heliostat cost reduction study.

    SciTech Connect (OSTI)

    Jones, Scott A.; Lumia, Ronald. (University of New Mexico, Albuquerque, NM); Davenport, Roger (Science Applications International Corporation, San Diego, CA); Thomas, Robert C. (Advanced Thermal Systems, Centennial, CO); Gorman, David; Kolb, Gregory J.; Donnelly, Matthew W.

    2007-06-01

    Power towers are capable of producing solar-generated electricity and hydrogen on a large scale. Heliostats are the most important cost element of a solar power tower plant. Since they constitute {approx} 50% of the capital cost of the plant it is important to reduce heliostat cost as much as possible to improve the economic performance of power towers. In this study we evaluate current heliostat technology and estimate a price of $126/m{sup 2} given year-2006 materials and labor costs for a deployment of {approx}600 MW of power towers per year. This 2006 price yields electricity at $0.067/kWh and hydrogen at $3.20/kg. We propose research and development that should ultimately lead to a price as low as $90/m{sup 2}, which equates to $0.056/kWh and $2.75/kg H{sup 2}. Approximately 30 heliostat and manufacturing experts from the United States, Europe, and Australia contributed to the content of this report during two separate workshops conducted at the National Solar Thermal Test Facility.

  11. NREL Analysis: Cost-Effective and Reliable Integration of High-Penetration Solar in the Western United States (Poster)

    SciTech Connect (OSTI)

    Lew, D.; Brinkman, G.; Ibanez, E.; Hodge, B.; Lefton, S.; Kumar, N.; Agan, D.; Jordan, G.; Venkatataman, S.

    2012-07-01

    SunShot Initiative awardee posters describing the different technologies within the four subprograms of the DOE Solar Program (Photovoltaics, Concentrating Solar Power, Soft Costs, and Systems Integration).

  12. Cost-Effectiveness of Home Energy Retrofits in Pre-Code Vintage Homes in the United States

    SciTech Connect (OSTI)

    Fairey, P.; Parker, D.

    2012-11-01

    This analytical study examines the opportunities for cost-effective energy efficiency and renewable energy retrofits in residential archetypes constructed prior to 1980 (Pre-Code) in fourteen U.S. cities. These fourteen cities are representative of each of the International Energy Conservation Code (IECC) climate zones in the contiguous U.S. The analysis is conducted using an in-house version of EnergyGauge USA v.2.8.05 named CostOpt that has been programmed to perform iterative, incremental economic optimization on a large list of residential energy efficiency and renewable energy retrofit measures. The principle objectives of the study are as follows: to determine the opportunities for cost effective source energy reductions in this large cohort of existing residential building stock as a function of local climate and energy costs; and to examine how retrofit financing alternatives impact the source energy reductions that are cost effectively achievable.

  13. Solar Access to Public Capital | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Solar Access to Public Capital Solar Access to Public Capital The Solar Access to Public Capital (SAPC) working group has developed standard residential lease and commercial power purchase agreement (PPA) contracts available for use by solar developers, customers, and third-party finance providers. These documents are designed to improve consumer transparency, reduce transaction costs in the solar asset contracting process, and facilitate the pooling of associated cash flows so that they may be

  14. PAFC Cost Challenges

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    PAFC Cost Challenges Sridhar Kanuri Manager, PAFC Technology *Sridhar.Kanuri@utcpower.com 2 AGENDA Purecell® 400 cost challenge Cost reduction opportunities Summary 3 PURECELL ® FUEL CELL SYSTEM First cost 2010 cost reduction is being accomplished by incremental changes in technology & low cost sourcing Technology advances are required to reduce further cost and attain UTC Power's commercialization targets 2010 First unit 2010 Last unit Commercialization target Powerplant cost 4

  15. Energy Department Report Calculates Emissions and Costs of Power...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    does not consider other factors such as capital costs of construction for wind, solar, fossil-fueled power plants, or transmission. These costs are significant, but outside the...

  16. Capital Project Prioritization

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capital-Project-Prioritization Sign In About | Careers | Contact | Investors | bpa.gov Search News & Us Expand News & Us Projects & Initiatives Expand Projects &...

  17. CAPITAL PROJECT PROPOSAL

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Non-Discretionary, please provide explanation: 07 Approval for: Ongoing Program 08 Investment Type: Capital Replacement 09 Emergency? YES NO 09A If "YES", please provide...

  18. PROJECT PROFILE: Promotion of PV Soft Cost Reductions in the Southeastern United States (SuNLaMP)

    Broader source: Energy.gov [DOE]

    This project creates a replicable model for solar photovoltaic (PV) soft cost reduction in South Carolina through human capacity-building at the local level and direct efforts to harmonize policy at the inter-county or regional level. This effort will close the gap between South Carolina installed costs of residential rooftop solar and national averages and develop a portable and replicable model that can be applied to other jurisdictions in the future.

  19. Human Capital - DOE Directives, Delegations, and Requirements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Human Capital by Website Administrator Back

  20. Utility-Scale Solar 2013: An Empirical Analysis of Project Cost, Performance, and Pricing Trends in the United States

    Office of Energy Efficiency and Renewable Energy (EERE)

    Other than the SEGS I-IX parabolic trough projects built in the 1980s, virtually no large-scale or "utility-scale" solar projects existed in the United States prior to 2007. By 2012 – just five years later – utility-scale had become the largest sector of the overall PV market in the United States, a distinction that was repeated in 2013 and is expected to continue for at least the next few years.

  1. BG Capital | Open Energy Information

    Open Energy Info (EERE)

    BG Capital Jump to: navigation, search Name: BG-Capital Place: Spain Zip: 8860 Product: BG-capital designs, installs and invests in PV medium scale (100-500kW) systems,...

  2. 2015-09-25 Capital Asset Project List.xls

    Broader source: Energy.gov (indexed) [DOE]

    as defined by DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets. CD-0 Approve Mission Need CD-1 Approve Alternative Selection and Cost Range...

  3. Life cycle cost study for coated conductor manufacture by metal organic chemical vapor deposition

    SciTech Connect (OSTI)

    Chapman, J.N.

    1999-07-13

    The purpose of this report is to calculate the cost of producing high temperature superconducting wire by the Metal Organic Chemical Vapor Deposition (MOCVD) process. The technology status is reviewed from the literature and a plant conceptual design is assumed for the cost calculation. The critical issues discussed are the high cost of the metal organic precursors, the material utilization efficiency and the capability of the final product as measured by the critical current density achieved. Capital, operating and material costs are estimated and summed as the basis for calculating the cost per unit length of wire. Sensitivity analyses of key assumptions are examined to determine their effects on the final wire cost. Additionally, the cost of wire on the basis of cost per kiloampere per meter is calculated for operation at lower temperatures than the liquid nitrogen boiling temperature. It is concluded that this process should not be ruled out on the basis of high cost of precursors alone.

  4. The Status of Clean Energy in the United States

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    The Status of Clean Energy in the United States Tribal Energy Program Review May 6, 2015 Travis Lowder, NREL 2 Lazard's Levelized Cost of Energy (LCOE) Estimates Source: Lazard 2013 3 Lazard's Capital Cost Estimates Source: Lazard 2013 4 EIA Estimates (2012 data) 5 Solar PV 6 Solar PV Installed Capacity and Weighted Average System Cost $0 $2 $4 $6 $8 $10 $12 0 1000 2000 3000 4000 5000 6000 7000 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 Wtd. Avg. System Price ($/W)

  5. Arborview Capital | Open Energy Information

    Open Energy Info (EERE)

    Arborview Capital Jump to: navigation, search Name: Arborview Capital Place: Chevy Chase, Maryland Zip: 20815 Product: Maryland-based private equity firm that provides growth...

  6. Greenrock Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Greenrock Capital Place: San Francisco, California Zip: 94111 Sector: Renewable Energy Product: San Francisco-based, investment firm....

  7. Dragonfly Capital | Open Energy Information

    Open Energy Info (EERE)

    Dragonfly Capital Jump to: navigation, search Name: Dragonfly Capital Place: Charlotte, North Carolina Zip: 28203 Sector: Renewable Energy, Services Product: Charlotte-based...

  8. Renewable Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Renewable Capital Place: Las Vegas, Nevada Zip: 89109 Sector: Solar Product: Investment vehicle of Ed Stevenson, founder of Solar...

  9. Cascadia Capital | Open Energy Information

    Open Energy Info (EERE)

    Cascadia Capital Jump to: navigation, search Name: Cascadia Capital Address: 701 Fifth Avenue Place: Seattle, Washington Zip: 98104 Region: Pacific Northwest Area Product:...

  10. Peony Capital | Open Energy Information

    Open Energy Info (EERE)

    Peony Capital Jump to: navigation, search Name: Peony Capital Place: Dongcheng District Beijing, Beijing Municipality, China Zip: 100027 Product: Manages a fund dedicated to...

  11. Capital Point | Open Energy Information

    Open Energy Info (EERE)

    Point Jump to: navigation, search Name: Capital Point Place: Israel Sector: Services Product: General Financial & Legal Services ( Joint Venture Consortium ) References: Capital...

  12. Workplace Charging Challenge Partner: Capital One Financial Corporatio...

    Energy Savers [EERE]

    As of early 2014, Capital One has installed 60 Level 2 plug-in electric vehicle (PEV) charging units at five company sites. These charging stations support associates who purchase ...

  13. Final project report - CRADA with United Solar Technologies and Pacific Northwest Laboratory (PNL-021): Thin film materials for low-cost high performance solar concentrators

    SciTech Connect (OSTI)

    Martin, P.M.; Affinito, J.D.; Gross, M.E.; Bennett, W.D.

    1995-03-01

    The objectives of this project were as follows: To develop and evaluate promising low-cost dielectric and polymer-protected thin-film reflective metal coatings to be applied to preformed continuously-curved solar reflector panels to enhance their solar reflectance, and to demonstrate protected solar reflective coatings on preformed solar concentrator panels. The opportunity for this project arose from a search by United Solar Technologies (UST) for organizations and facilities capable of applying reflective coatings to large preformed panels. PNL was identified as being uniquely qualified to participate in this collaborative project.

  14. Activity Based Costing

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Activity Based Costing (ABC) is method for developing cost estimates in which the project is subdivided into discrete, quantifiable activities or a work unit. This chapter outlines the Activity Based Costing method and discusses applicable uses of ABC.

  15. Capital intensity of photovoltaics manufacturing: Barrier to scale and opportunity for innovation

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Powell, Douglas M.; Fu, Ran; Horowitz, Kelsey; Basore, Paul A.; Woodhouse, Michael; Buonassisi, Tonio

    2015-09-07

    In this study, using a bottom-up cost model, we assess the impact of initial factory capital expenditure (capex) on photovoltaic (PV) module minimum sustainable price (MSP) and industry-wide trends. We find capex to have two important impacts on PV manufacturing. First, capex strongly influences the per-unit MSP of a c-Si module: we calculate that the capex-related elements sum to 22% of MSP for an integrated wafer, cell, and module manufacturer. This fraction provides a significant opportunity to reduce MSP toward the U.S. DOE SunShot module price target through capex innovation.

  16. Capital Reporting Company Quadrennial ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... The war on poverty, which was 20 initiated with very dramatics walks from 21 Appalachia ... 07-21-2014 (866) 448 - DEPO www.CapitalReportingCompany.com 2014 44 1 poverty there. ...

  17. Capital Reporting Company Quadrennial ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ...CapitalReportingCompany.com 2014 120 1 how to adapt to the new oil which is, in New 2 Mexico, a sweet API 40, essentially similar to the 3 North Dakota oil. We have a sweet oil. ...

  18. Capital Project Authorization

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    This policy applies to capital projects in these asset categories: 1. Transmission investment in assets owned or leased by BPA, whether funded by bonds issued to the U.S....

  19. CHARACTERIZING COSTS, SAVINGS AND BENEFITS OF A SELECTION OF ENERGY EFFICIENT EMERGING TECHNOLOGIES IN THE UNITED STATES

    SciTech Connect (OSTI)

    Xu, T.; Slaa, J.W.; Sathaye, J.

    2010-12-15

    Implementation and adoption of efficient end-use technologies have proven to be one of the key measures for reducing greenhouse gas (GHG) emissions throughout the industries. In many cases, implementing energy efficiency measures is among one of the most cost effective investments that the industry could make in improving efficiency and productivity while reducing CO2 emissions. Over the years, there have been incentives to use resources and energy in a cleaner and more efficient way to create industries that are sustainable and more productive. With the working of energy programs and policies on GHG inventory and regulation, understanding and managing the costs associated with mitigation measures for GHG reductions is very important for the industry and policy makers around the world. Successful implementation of emerging technologies not only can help advance productivities and competitiveness but also can play a significant role in mitigation efforts by saving energy. Providing evaluation and estimation of the costs and energy savings potential of emerging technologies is the focus of our work in this project. The overall goal of the project is to identify and select emerging and under-utilized energy-efficient technologies and practices as they are important to reduce energy consumption in industry while maintaining economic growth. This report contains the results from performing Task 2"Technology evaluation" for the project titled"Research Opportunities in Emerging and Under-Utilized Energy-Efficient Industrial Technologies," which was sponsored by California Energy Commission and managed by CIEE. The project purpose is to analyze market status, market potential, and economic viability of selected technologies applicable to the U.S. In this report, LBNL first performed re-assessments of all of the 33 emerging energy-efficient industrial technologies, including re-evaluation of the 26 technologies that were previously identified by Martin et al. (2000) and

  20. Wind energy`s declining costs

    SciTech Connect (OSTI)

    Gipe, P.

    1995-11-01

    Wind energy is competitive with traditional energy sources for the first time since European windmills graced the landscapes of the Old World. This article explores the current economics of wind power. Topics discussed include the following: standardizing cost of energy reporting and the cost of wind energy; wind power plant price; maintenance costs; effect of installed cost on the cost of energy; future costs; decommissioning; modularity; social or environmental costs; cost of capital; bidding and price.

  1. ASPEN costing manual

    SciTech Connect (OSTI)

    Schwint, K.J.

    1986-07-25

    The ASPEN program contains within it a Cost Estimation System (CES) which estimates the purchase cost and utility consumption rates for major pieces of equipment in a process flowsheet as well as installed equipment costs. These estimates are ''preliminary-study grade'' with an accuracy of plus or minus 30%. The ASPEN program also contains within it an Economic Evaluation System (EES) which estimates overall capital investment costs, annual operating expenses and profitability indices for a chemical plant. This ASPEN costing manual has been written as a guide for those inexperienced in the use of ASPEN and unfamiliar with standard cost estimating techniques who want to use the ASPEN CES and EES. The ASPEN Costing Manual is comprised of the following sections: (1) Introduction, (2) ASPEN Input Language, (3) ASPEN Cost Estimation System (CES), (4) ASPEN Cost Blocks; and (5) ASPEN Economic Evaluation System (EES).

  2. Manufacturing Cost Levelization Model – A User’s Guide

    SciTech Connect (OSTI)

    Morrow, William R.; Shehabi, Arman; Smith, Sarah Josephine

    2015-08-01

    The Manufacturing Cost Levelization Model is a cost-performance techno-economic model that estimates total large-scale manufacturing costs for necessary to produce a given product. It is designed to provide production cost estimates for technology researchers to help guide technology research and development towards an eventual cost-effective product. The model presented in this user’s guide is generic and can be tailored to the manufacturing of any product, including the generation of electricity (as a product). This flexibility, however, requires the user to develop the processes and process efficiencies that represents a full-scale manufacturing facility. The generic model is comprised of several modules that estimate variable costs (material, labor, and operating), fixed costs (capital & maintenance), financing structures (debt and equity financing), and tax implications (taxable income after equipment and building depreciation, debt interest payments, and expenses) of a notional manufacturing plant. A cash-flow method is used to estimate a selling price necessary for the manufacturing plant to recover its total cost of production. A levelized unit sales price ($ per unit of product) is determined by dividing the net-present value of the manufacturing plant’s expenses ($) by the net present value of its product output. A user defined production schedule drives the cash-flow method that determines the levelized unit price. In addition, an analyst can increase the levelized unit price to include a gross profit margin to estimate a product sales price. This model allows an analyst to understand the effect that any input variables could have on the cost of manufacturing a product. In addition, the tool is able to perform sensitivity analysis, which can be used to identify the key variables and assumptions that have the greatest influence on the levelized costs. This component is intended to help technology researchers focus their research attention on tasks

  3. Walnut Capital Acquisitions | Open Energy Information

    Open Energy Info (EERE)

    Walnut Capital Acquisitions Jump to: navigation, search Name: Walnut Capital Acquisitions Place: Pittsburgh, Pennsylvania Zip: 15232 Product: Walnut Capital Acquisitions is the...

  4. American Wind Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: American Wind Capital Place: Essex, Connecticut Zip: 64260 Sector: Wind energy Product: Connecticut-based American Wind Capital buys wind...

  5. Sustainable Technology Capital, LP | Open Energy Information

    Open Energy Info (EERE)

    Capital, LP Jump to: navigation, search Logo: Sustainable Technology Capital, LP Name: Sustainable Technology Capital, LP Address: 625 Liberty Ave., Suite 3200 Place: Pittsburgh,...

  6. Long Branch Capital | Open Energy Information

    Open Energy Info (EERE)

    Branch Capital Jump to: navigation, search Name: Long Branch Capital Place: Austin, Texas Zip: 78744 Sector: Efficiency, Renewable Energy Product: Long Branch Capital makes...

  7. Tonga Capital Corporation | Open Energy Information

    Open Energy Info (EERE)

    Tonga Capital Corporation Jump to: navigation, search Name: Tonga Capital Corporation Place: Arvada, Colorado Sector: Biofuels Product: Capital pool company, which ran out of...

  8. Hereford Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Hereford Capital Advisors Jump to: navigation, search Name: Hereford Capital Advisors Place: Denver, Colorado Product: US-based firm offering PV project management and capital...

  9. Prospect Capital Corporation | Open Energy Information

    Open Energy Info (EERE)

    Prospect Capital Corporation Jump to: navigation, search Logo: Prospect Capital Corporation Name: Prospect Capital Corporation Address: 10 East 40th Street, 44th Floor Place: New...

  10. Energy Capital Solutions | Open Energy Information

    Open Energy Info (EERE)

    Capital Solutions Jump to: navigation, search Logo: Energy Capital Solutions Name: Energy Capital Solutions Address: 2651 North Harwood Street, Suite 410 Place: Dallas, Texas Zip:...

  11. KRK Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    KRK Capital Partners Jump to: navigation, search Name: KRK Capital Partners Place: Washington DC, Washington, DC Zip: 20002 Product: String representation "KRK Capital Par ......

  12. Chrysalix Energy Venture Capital | Open Energy Information

    Open Energy Info (EERE)

    Chrysalix Energy Venture Capital Jump to: navigation, search Logo: Chrysalix Energy Venture Capital Name: Chrysalix Energy Venture Capital Address: 1367 West Broadway, Suite 400...

  13. New Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Logo: New Energy Capital Name: New Energy Capital Address: 53 South Main Street, Third Floor Place: Hanover, New Hampshire Zip: 03755 Product:...

  14. Applied Intellectual Capital AIC | Open Energy Information

    Open Energy Info (EERE)

    Intellectual Capital AIC Jump to: navigation, search Name: Applied Intellectual Capital (AIC) Place: California Zip: 94501-1010 Product: Applied Intellectual Capital (AIC) was...

  15. Booner Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Booner Capital LLC Jump to: navigation, search Name: Booner Capital LLC Place: Florida Sector: Wind energy Product: Booner Capital LLC is PE investor in wind power companies....

  16. Chestnut Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital LLC Jump to: navigation, search Name: Chestnut Capital LLC Place: West Newton, Massachusetts Zip: 2465 Sector: Wind energy Product: Chestnut Capital is a wind energy...

  17. Cora Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Cora Capital Advisors Jump to: navigation, search Logo: Cora Capital Advisors Name: Cora Capital Advisors Address: 445 Park Avenue, 9th Floor Place: New York Zip: 10022 Region:...

  18. Development of surface mine cost estimating equations

    SciTech Connect (OSTI)

    Not Available

    1980-09-26

    Cost estimating equations were developed to determine capital and operating costs for five surface coal mine models in Central Appalachia, Northern Appalachia, Mid-West, Far-West, and Campbell County, Wyoming. Engineering equations were used to estimate equipment costs for the stripping function and for the coal loading and hauling function for the base case mine and for several mines with different annual production levels and/or different overburden removal requirements. Deferred costs were then determined through application of the base case depreciation schedules, and direct labor costs were easily established once the equipment quantities (and, hence, manpower requirements) were determined. The data points were then fit with appropriate functional forms, and these were then multiplied by appropriate adjustment factors so that the resulting equations yielded the model mine costs for initial and deferred capital and annual operating cost. (The validity of this scaling process is based on the assumption that total initial and deferred capital costs are proportional to the initial and deferred costs for the primary equipment types that were considered and that annual operating cost is proportional to the direct labor costs that were determined based on primary equipment quantities.) Initial capital costs ranged from $3,910,470 in Central Appalachia to $49,296,785; deferred capital costs ranged from $3,220,000 in Central Appalachia to $30,735,000 in Campbell County, Wyoming; and annual operating costs ranged from $2,924,148 in Central Appalachia to $32,708,591 in Campbell County, Wyoming. (DMC)

  19. US nuclear power plant operating cost and experience summaries

    SciTech Connect (OSTI)

    Kohn, W.E.; Reid, R.L.; White, V.S.

    1998-02-01

    NUREG/CR-6577, U.S. Nuclear Power Plant Operating Cost and Experience Summaries, has been prepared to provide historical operating cost and experience information on U.S. commercial nuclear power plants. Cost incurred after initial construction are characterized as annual production costs, representing fuel and plant operating and maintenance expenses, and capital expenditures related to facility additions/modifications which are included in the plant capital asset base. As discussed in the report, annual data for these two cost categories were obtained from publicly available reports and must be accepted as having different degrees of accuracy and completeness. Treatment of inconclusive and incomplete data is discussed. As an aid to understanding the fluctuations in the cost histories, operating summaries for each nuclear unit are provided. The intent of these summaries is to identify important operating events; refueling, major maintenance, and other significant outages; operating milestones; and significant licensing or enforcement actions. Information used in the summaries is condensed from annual operating reports submitted by the licensees, plant histories contained in Nuclear Power Experience, trade press articles, and the Nuclear Regulatory Commission (NRC) web site (www.nrc.gov).

  20. Ardour Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Ardour Capital Investments LLC Address: 350 5th ave Place: New York, New York Zip: 10118 Region: Northeast - NY NJ CT PA Area Number of...

  1. Greentech Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Place: Sao Paulo, Sao Paulo, Brazil Zip: 04536-001 Product: Brazilian investment group. References: Greentech Capital1 This article is a stub. You can help OpenEI...

  2. Survey Results and Analysis of the Cost and Efficiency of Various Operating Hydrogen Fueling Stations

    SciTech Connect (OSTI)

    Cornish, John

    2011-03-05

    Existing Hydrogen Fueling Stations were surveyed to determine capital and operational costs. Recommendations for cost reduction in future stations and for research were developed.

  3. Best Practices for Net Zero Energy Cost Control

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    teams, which are key parties that influence construction capital cost. ... http:www1.eere.energy.govbuildingsalliancesmedia20111031webinarcontrollingcosts.wmv * Energy ...

  4. Replacement Cost of Domestic Crude

    Energy Science and Technology Software Center (OSTI)

    1994-12-01

    The DEEPWATER model forecasts the replacement cost of domestic crude oil for 13 offshore regions in the lower 48 states. The replacement cost of domestic crude oil is the constant or levelized selling price that will recover the full expense of exploration, development, and productions with a reasonable return on capital.

  5. Natural Capital Management: An Evolutionary Paradigm for Sustainable Restoration Investment - 13455

    SciTech Connect (OSTI)

    Koetz, Maureen T.

    2013-07-01

    Unlike other forms of capital assets (built infrastructure, labor, financial capital), the supply of usable or accessible air, land, and water elements (termed Natural Capital Assets or NCA) available to enterprise processes is structurally shrinking due to increased demand and regulatory restriction. This supply/demand imbalance is affecting all forms of public and private enterprise (including Federal Facilities) in the form of encroachment, production limits, cost increases, and reduced competitiveness. Department of Energy (DOE) sites are comprised of significant stocks of NCA that function as both conserved capital (providing ecosystem services and other reserve capacity), and as natural infrastructure (supporting major Federal enterprise programs). The current rubric of 'Environmental Stewardship' provides an unduly constrained management paradigm that is focused largely on compliance process metrics, and lacks a value platform for quantifying, documenting, and sustainably re-deploying re-capitalized natural asset capacity and capability. By adopting value-based system concepts similar to built infrastructure accounting and information management, 'stewarded' natural assets relegated to liability- or compliance-focused outcomes become 're-capitalized' operational assets able to support new or expanded mission. This growing need for new accounting and management paradigms to capture natural capital value is achieving global recognition, most recently by the United Nations, world leaders, and international corporations at the Rio+20 Summit in June of 2012. Natural Capital Asset Management (NCAM){sup TM} is such an accounting framework tool. Using a quantification-based design, NCAM{sup TM} provides inventory, capacity and value data to owners or managers of natural assets such as the DOE that parallel comparable information systems currently used for facility assets. Applied to Environmental Management (EM) and other DOE program activities, the natural asset

  6. Principal Associate Director - Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    As Principal Associate Director for Capital Projects (interim), Larry Simmons is responsible for institutional large-project construction and management and environmental cleanup ...

  7. Swiftsure Capital | Open Energy Information

    Open Energy Info (EERE)

    Place: San Francisco, California Product: Swiftsure Capital, US-based private investment corporation focusing on the financing of early-stage businesses in the software,...

  8. Financing U.S. Renewable Energy Projects Through Public Capital Vehicles: Qualitative and Quantitative Benefits

    SciTech Connect (OSTI)

    Mendelsohn, M.; Feldman, D.

    2013-04-01

    This paper explores the possibility of financing renewable energy projects through raising capital in the public markets. It gives an overview of the size, structure, and benefits of public capital markets, as well as showing how renewable energy projects might take advantage of this source of new funds to lower the cost of electricity.

  9. Analysis of the applicability and probable cost effectiveness of advancing longwall-mining systems in the United States. Final technical report. [Advance vs retreat

    SciTech Connect (OSTI)

    Hill, F.E.; Peake, C.V.; Sharkey, A.

    1981-07-01

    In the first phase of this study it was concluded that there are a number of advancing longwall systems that might well be applicable in the United States and, furthermore, meet the health and safety requirements of MSHA, state inspectors, operating management, and unions. Comparative analyses showed that only two of the advancing-type systems evaluated in the Phase I report failed to approach or better, economically, the typical retreating method in at least some conditions; the others appeared to warrant further attention. And if the mining plan could be worked out to allow for a switch from advancing to retreating after the early years of mining, then almost any combination of advancing and retreating would provide a better return on investment, or in our terms, have a higher net present value than would a typical retreating system. The reason for this lies in the higher initial production rates of the advancing systems and in the lower operating cost and higher ultimate productivity of a retreating system once it is established. After analyzing the advantages and disadvantages of the various advancing longwall systems for a trial program it became apparent that the modified Z System offered the best combination of economic potential and lack of conflict with US mining laws. The major attraction of the modified Z system is that it provides separate roadways to the face for intake air, exhaust air and a beltway. Thus regulatory approval of the ventilation system should not be a major obstacle. The Kaiser Steel Corporation agreed to cooperate with the development of a specification for a trial of the system at its Sunnyside Mine in Utah. The specification was developed for one longwall face to mine a series of panels at Sunnyside.

  10. Levelized Power Generation Cost Codes

    Energy Science and Technology Software Center (OSTI)

    1996-04-30

    LPGC is a set of nine microcomputer programs for estimating power generation costs for large steam-electric power plants. These programs permit rapid evaluation using various sets of economic and technical ground rules. The levelized power generation costs calculated may be used to compare the relative economics of nuclear and coal-fired plants based on life-cycle costs. Cost calculations include capital investment cost, operation and maintenance cost, fuel cycle cost, decommissioning cost, and total levelized power generationmore » cost. These programs can be used for quick analyses of power generation costs using alternative economic parameters, such as interest rate, escalation rate, inflation rate, plant lead times, capacity factor, fuel prices, etc. The two major types of electric generating plants considered are pressurized water reactor (PWR) and pulverized coal-fired plants. Data are also provided for the Large Scale Prototype Breeder (LSPB) type liquid metal reactor.« less

  11. EA-355 Scotia Capital Energy, Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    5 Scotia Capital Energy, Inc. EA-355 Scotia Capital Energy, Inc. Order authorizing Scotia Capital Energy, Inc. to export electric energy to Canada EA-355 Scotia Capital Energy, ...

  12. Hydrogen Production Cost Estimate Using Biomass Gasification: Independent Review

    Office of Energy Efficiency and Renewable Energy (EERE)

    This independent review report assesses the 2009 state-of-the-art and 2020 projected capital cost, energy efficiency, and levelized cost for hydrogen production from biomass via gasification.

  13. Human Capital Management Accountability Program

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-08-01

    The Order establishes requirements, roles and responsibilities for the Human Capital Management Accountability Program (HCMAP) for human resources programs and personnel and ensures that human capital activities are regulatory and procedurally compliant with Federal statutes and Departmental policies. Does not cancel other directives.

  14. Mont Vista Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Vista Capital LLC Jump to: navigation, search Name: Mont Vista Capital LLC Place: New York, New York Zip: 10167 Sector: Services Product: Mont Vista Capital is a leading global...

  15. EnerTech Capital | Open Energy Information

    Open Energy Info (EERE)

    EnerTech Capital Jump to: navigation, search Logo: EnerTech Capital Name: EnerTech Capital Address: 625 W. Ridge Pike, Building D, Suite 105 Place: Conshohocken, Pennsylvania Zip:...

  16. GreenCore Capital | Open Energy Information

    Open Energy Info (EERE)

    GreenCore Capital Jump to: navigation, search Logo: GreenCore Capital Name: GreenCore Capital Address: 10509 Vista Sorrento Parkway Place: San Diego, California Zip: 92121 Region:...

  17. EarthRise Capital | Open Energy Information

    Open Energy Info (EERE)

    EarthRise Capital Jump to: navigation, search Name: EarthRise Capital Place: New York, New York Zip: NY 10111 Sector: Efficiency Product: Venture capital fund focused on new...

  18. Where might I find simplified Data on Capital, O&M, and fuel...

    Open Energy Info (EERE)

    Where might I find simplified Data on Capital, O&M, and fuel costs? Home I teach math to high school seniors. My students are studying energy in all their classes. I have just...

  19. Viresco International Capital Management | Open Energy Information

    Open Energy Info (EERE)

    International Capital Management Jump to: navigation, search Name: Viresco International Capital Management Place: San Diego, California Zip: 92130 Product: San Diego-based hedge...

  20. Greenwood Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Greenwood Capital Partners Jump to: navigation, search Name: Greenwood Capital Partners Place: Charlotte, North Carolina Zip: 28266 Product: Corporate finance boutique working on...

  1. Montauk Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Montauk Energy Capital Jump to: navigation, search Name: Montauk Energy Capital Place: Pittsburg, Pennsylvania Zip: 15220 Product: Owns and operates landfill gas plants across the...

  2. New Energy Capital Corp | Open Energy Information

    Open Energy Info (EERE)

    Capital Corp Jump to: navigation, search Name: New Energy Capital Corp. Place: Hanover, New Hampshire Zip: 3755 Sector: Renewable Energy Product: Private equity fund focused on...

  3. Quadrant Capital Advisors Inc | Open Energy Information

    Open Energy Info (EERE)

    Quadrant Capital Advisors Inc Jump to: navigation, search Name: Quadrant Capital Advisors Inc. Place: New York, New York Zip: 10022 Sector: Hydro, Wind energy Product: US based...

  4. Arctas Capital Group | Open Energy Information

    Open Energy Info (EERE)

    Arctas Capital Group Jump to: navigation, search Name: Arctas Capital Group Place: Houston, Texas Zip: 77056 Sector: Geothermal energy, Renewable Energy, Wind energy Product: A...

  5. Krass Capital Group AG | Open Energy Information

    Open Energy Info (EERE)

    Krass Capital Group AG Jump to: navigation, search Name: Krass Capital Group AG Place: Grfelfing, Bulgaria Zip: 82166 Sector: Renewable Energy Product: Grafelfing-based firm...

  6. North Cove Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Cove Capital Advisors Jump to: navigation, search Name: North Cove Capital Advisors Place: Connecticut Sector: Carbon Product: North Cove is an advisory firm that works...

  7. Starlight Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Starlight Capital Advisors Jump to: navigation, search Name: Starlight Capital Advisors Place: Carlsbad, California Zip: 92011 Sector: Renewable Energy Product: California-based...

  8. Digital Power Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital LLC Jump to: navigation, search Name: Digital Power Capital LLC Place: Greenwich, Connecticut Zip: 6830 Product: A private equity firm focused on new technologies that...

  9. Solution Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Solution Capital Partners Jump to: navigation, search Name: Solution Capital Partners Place: New York Zip: NY 10036 Product: A New York-based investment firm active in the...

  10. American Capital Energy | Open Energy Information

    Open Energy Info (EERE)

    Energy Jump to: navigation, search Logo: American Capital Energy Name: American Capital Energy Address: 15 Tyngsboro Rd. Suite 4A Place: North Chelmsford, Massachusetts Zip: 01863...

  11. Greentech Capital Advisors GCA | Open Energy Information

    Open Energy Info (EERE)

    Capital Advisors GCA Jump to: navigation, search Name: Greentech Capital Advisors (GCA) Place: New York, New York Zip: 10017 Sector: Renewable Energy Product: New York-based...

  12. Conservation Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Conservation Capital LLC Jump to: navigation, search Name: Conservation Capital LLC Place: Houston, Texas Zip: 77018 Product: Houston-based land investment and consulting company...

  13. Longboard Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Longboard Capital Advisors Jump to: navigation, search Name: Longboard Capital Advisors Place: Santa Monica, California Zip: 90405 Product: Longboard is a small hedge fund focused...

  14. Haywood Dorland Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Dorland Energy Capital Jump to: navigation, search Name: Haywood Dorland Energy Capital Place: New York, New York Sector: Renewable Energy Product: New York-based private equity...

  15. Energy Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    LLC Jump to: navigation, search Name: Energy Capital LLC Place: Ketchum, Idaho Zip: ID 83340 Sector: Renewable Energy Product: Energy Capital LLc is a financial catalyst focusing...

  16. Wind Farm Capital | Open Energy Information

    Open Energy Info (EERE)

    Farm Capital Jump to: navigation, search Name: Wind Farm Capital Place: Connecticut Sector: Wind energy Product: US-based company that buys wind leases from farmers and landowners,...

  17. Beijing Capital International Airport | Open Energy Information

    Open Energy Info (EERE)

    International Airport Jump to: navigation, search Name: Beijing Capital International Airport Place: Beijing, Beijing Municipality, China Zip: 100621 Product: Beijing Capital...

  18. Nimes Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Nimes Capital LLC Jump to: navigation, search Name: Nimes Capital LLC Place: Los Angeles, California Zip: 90067 Product: Los Angeles-based private equity firm that provides growth...

  19. Sequoia Capital Ltda | Open Energy Information

    Open Energy Info (EERE)

    Capital Ltda Jump to: navigation, search Name: Sequoia Capital Ltda Place: Sao Paulo, Sao Paulo, Brazil Sector: Wind energy Product: Brazilian-based wind project developer....

  20. Wind Capital Group | Open Energy Information

    Open Energy Info (EERE)

    Capital Group Jump to: navigation, search Name: Wind Capital Group Place: St. Louis, Missouri Zip: 63101 Sector: Wind energy Product: Missouri-based wind project developer, focused...

  1. Impact Capital Partners Limited | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Limited Jump to: navigation, search Name: Impact Capital Partners Limited Place: Los Angeles, California Zip: CA 90067-1509 Product: Los Angeles-based, investment...

  2. Ambata Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Ambata Capital Partners Jump to: navigation, search Name: Ambata Capital Partners Place: New York, New York Zip: 10169 Product: New York-based global investment and advisory firm...

  3. Strategic Capital Investments LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital Investments LLC Jump to: navigation, search Name: Strategic Capital Investments LLC Place: Short Hills, New Jersey Zip: 7078 Product: New Jersey-based, project development...

  4. Black Coral Capital | Open Energy Information

    Open Energy Info (EERE)

    Coral Capital Jump to: navigation, search Name: Black Coral Capital Address: 55 Union Street, 3rd Floor Place: Boston, Massachusetts Zip: 02108 Region: Greater Boston Area Product:...

  5. Birch Tree Capital | Open Energy Information

    Open Energy Info (EERE)

    Birch Tree Capital Jump to: navigation, search Name: Birch Tree Capital Place: Framingham, Massachusetts Zip: 1701 Sector: Renewable Energy Product: Financial advisory service with...

  6. American Capital Energy Inc | Open Energy Information

    Open Energy Info (EERE)

    Capital Energy Inc Jump to: navigation, search Name: American Capital Energy Inc Place: North Chelmsford, Massachusetts Zip: 1863 Sector: Services Product: Full-service PV...

  7. Bannockburn Capital LTD | Open Energy Information

    Open Energy Info (EERE)

    Bannockburn Capital LTD Jump to: navigation, search Name: Bannockburn Capital, LTD. Place: Newport Beach, California Zip: 92657 Sector: Carbon, Renewable Energy Product: String...

  8. Sustainable World Capital | Open Energy Information

    Open Energy Info (EERE)

    World Capital Jump to: navigation, search Name: Sustainable World Capital Place: Atlanta, Georgia Zip: 30326 Product: Atlanta-based firm that connects companies with institutional...

  9. West Mountain Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Energy Capital Jump to: navigation, search Name: West Mountain Energy Capital Place: Salisbury, Connecticut Zip: 6070 Sector: Renewable Energy Product: Provides renewable resource...

  10. Marathon Capital LLC (Illinois) | Open Energy Information

    Open Energy Info (EERE)

    Logo: Marathon Capital LLC (Illinois) Name: Marathon Capital LLC (Illinois) Address: 2801 Lakeside Drive, Suite 210 Place: Bannockburn, Illinois Zip: 60015 Product: Investment...

  11. Cate Street Capital Inc | Open Energy Information

    Open Energy Info (EERE)

    Cate Street Capital Inc Jump to: navigation, search Name: Cate Street Capital, Inc. Place: Portsmouth, New Hampshire Zip: 3801 Sector: Renewable Energy Product: New Hampshire-based...

  12. New Cycle Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Cycle Capital LLC Jump to: navigation, search Name: New Cycle Capital, LLC. Place: San Francisco, California Zip: 94103 Product: San Francisco-based venture capitalist firm...

  13. Nature Elements Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Nature Elements Capital Place: Beijing, Beijing Municipality, China Zip: 100125 Product: Beijing-based private equity firm investing in...

  14. Blue Green Capital | Open Energy Information

    Open Energy Info (EERE)

    Green Capital Jump to: navigation, search Name: Blue Green Capital Place: Spain Zip: 8860 Sector: Renewable Energy, Solar Product: String representation "Spanish develop ... their...

  15. Green Energy Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Jump to: navigation, search Name: Green Energy Capital Partners Place: Plymouth Meeting, Pennsylvania Zip: 19462 Sector: Wind energy Product: Pennsylvania-based...

  16. Ethanol Capital Funding | Open Energy Information

    Open Energy Info (EERE)

    Ethanol Capital Funding Jump to: navigation, search Name: Ethanol Capital Funding Place: Atlanta, Georgia Zip: 30328 Product: Provides funding for ethanol and biodiesel plants....

  17. Atlantic Ethanol Capital | Open Energy Information

    Open Energy Info (EERE)

    Ethanol Capital Jump to: navigation, search Name: Atlantic Ethanol Capital Place: Washington, Washington, DC Product: Biofuel Investor in Caribbean and Central American region....

  18. Carbon Credit Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Carbon Credit Capital Place: New York, New York Zip: 10012 Sector: Carbon, Services Product: Project Advisory Services and Carbon...

  19. Capital Energy Offshore | Open Energy Information

    Open Energy Info (EERE)

    Sector: Wind energy Product: JV between Gamesa and Capital Energy to develop offshore wind farms References: Capital Energy Offshore1 This article is a stub. You can help...

  20. Marathon Capital LLC (California) | Open Energy Information

    Open Energy Info (EERE)

    Marathon Capital LLC (California) Name: Marathon Capital LLC (California) Address: 42 Miller Avenue Place: Mill Valley, California Zip: 94941 Region: Bay Area Product: Investment...

  1. MVP Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    navigation, search Logo: MVP Capital Partners Name: MVP Capital Partners Address: 201 King of Prussia Road, Suite 240 Place: Radnor, Pennsylvania Zip: 19087 Region: Northeast -...

  2. L A Investment Capital | Open Energy Information

    Open Energy Info (EERE)

    A Investment Capital Jump to: navigation, search Name: L.A. Investment Capital Place: Beverly Hills, California Zip: CA 90210 Sector: Biofuels Product: Investment firm with funds...

  3. Jane Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    search Logo: Jane Capital Partners Name: Jane Capital Partners Address: 505 Montgomery, 2nd Floor Place: San Francisco, California Zip: 94111 Region: Bay Area Product:...

  4. Human Capital Management | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    human capital requires comprehensive planning and analysis in order to develop, implement, and evaluate programs that support every facet of employee work life. DOE human capital ...

  5. Capital Reporting Company Quadrennial ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... percent annual job growth rate. 19 When you look at ... And 15 that's the first refinery in the United States 16 being ... It 5 was just a slow, decline of death. Closing 6 schools ...

  6. Soft Costs | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Soft Costs » Soft Costs Soft Costs The U.S. Department of Energy (DOE) SunShot Initiative's soft costs program works to lower the non-hardware costs of solar and accelerate the adoption of solar energy technologies throughout the United States. In support of the SunShot Initiative goals, the soft costs program works in the following strategic areas: networking and technical assistance, data analysis, business innovation, and training. Soft Costs Activity Areas, Business Innovation, Networking

  7. Nuclear economics 2000: Deterministic and probabilistic projections of nuclear and coal electric power generation costs for the year 2000

    SciTech Connect (OSTI)

    Williams, K.A.; Delene, J.G.; Fuller, L.C.; Bowers, H.I.

    1987-06-01

    The total busbar electric generating costs were estimated for locations in ten regions of the United States for base-load nuclear and coal-fired power plants with a startup date of January 2000. For the Midwest region a complete data set that specifies each parameter used to obtain the comparative results is supplied. When based on the reference set of input variables, the comparison of power generation costs is found to favor nuclear in most regions of the country. Nuclear power is most favored in the northeast and western regions where coal must be transported over long distances; however, coal-fired generation is most competitive in the north central region where large reserves of cheaply mineable coal exist. In several regions small changes in the reference variables could cause either option to be preferred. The reference data set reflects the better of recent electric utility construction cost experience (BE) for nuclear plants. This study assumes as its reference case a stable regulatory environment and improved planning and construction practices, resulting in nuclear plants typically built at the present BE costs. Today's BE nuclear-plant capital investment cost model is then being used as a surrogate for projected costs for the next generation of light-water reactor plants. An alternative analysis based on today's median experience (ME) nuclear-plant construction cost experience is also included. In this case, coal is favored in all ten regions, implying that typical nuclear capital investment costs must improve for nuclear to be competitive.

  8. Startup Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter discusses startup costs for construction and environmental projects, and estimating guidance for startup costs.

  9. Riba Capital | Open Energy Information

    Open Energy Info (EERE)

    Place: Spain Sector: Renewable Energy Product: Riba Capital is a fund developed to invest in renewable projects in Iberia. It raised 800 million euros of financing in 2003 and...

  10. Capital Solar | Open Energy Information

    Open Energy Info (EERE)

    Solar Jump to: navigation, search Name: Capital Solar Place: Lecce, Italy Sector: Solar Product: Lecce-based solar project developer. Coordinates: 40.357955, 18.16801 Show Map...