National Library of Energy BETA

Sample records for units capital costs

  1. Transmission line capital costs

    SciTech Connect (OSTI)

    Hughes, K.R.; Brown, D.R.

    1995-05-01

    The displacement or deferral of conventional AC transmission line installation is a key benefit associated with several technologies being developed with the support of the U.S. Department of Energy`s Office of Energy Management (OEM). Previous benefits assessments conducted within OEM have been based on significantly different assumptions for the average cost per mile of AC transmission line. In response to this uncertainty, an investigation of transmission line capital cost data was initiated. The objective of this study was to develop a database for preparing preliminary estimates of transmission line costs. An extensive search of potential data sources identified databases maintained by the Bonneville Power Administration (BPA) and the Western Area Power Administration (WAPA) as superior sources of transmission line cost data. The BPA and WAPA data were adjusted to a common basis and combined together. The composite database covers voltage levels from 13.8 to 765 W, with cost estimates for a given voltage level varying depending on conductor size, tower material type, tower frame type, and number of circuits. Reported transmission line costs vary significantly, even for a given voltage level. This can usually be explained by variation in the design factors noted above and variation in environmental and land (right-of-way) costs, which are extremely site-specific. Cost estimates prepared from the composite database were compared to cost data collected by the Federal Energy Regulatory Commission (FERC) for investor-owned utilities from across the United States. The comparison was hampered because the only design specifications included with the FERC data were voltage level and line length. Working within this limitation, the FERC data were not found to differ significantly from the composite database. Therefore, the composite database was judged to be a reasonable proxy for estimating national average costs.

  2. LIFE Cost of Electricity, Capital and Operating Costs

    SciTech Connect (OSTI)

    Anklam, T

    2011-04-14

    Successful commercialization of fusion energy requires economic viability as well as technical and scientific feasibility. To assess economic viability, we have conducted a pre-conceptual level evaluation of LIFE economics. Unit costs are estimated from a combination of bottom-up costs estimates, working with representative vendors, and scaled results from previous studies of fission and fusion plants. An integrated process model of a LIFE power plant was developed to integrate and optimize unit costs and calculate top level metrics such as cost of electricity and power plant capital cost. The scope of this activity was the entire power plant site. Separately, a development program to deliver the required specialized equipment has been assembled. Results show that LIFE power plant cost of electricity and plant capital cost compare favorably to estimates for new-build LWR's, coal and gas - particularly if indicative costs of carbon capture and sequestration are accounted for.

  3. Electric power substation capital costs (Technical Report) |...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... Subject: 24 POWER TRANSMISSION AND DISTRIBUTION; POWER SUBSTATIONS; CAPITALIZED COST; CALCULATION METHODS; PLANNING; COST ESTIMATION; MATHEMATICAL MODELS Word Cloud More Like This ...

  4. Electric power substation capital costs

    SciTech Connect (OSTI)

    Dagle, J.E.; Brown, D.R.

    1997-12-01

    The displacement or deferral of substation equipment is a key benefit associated with several technologies that are being developed with the support of the US Department of Energy`s Office of Utility Technologies. This could occur, for example, as a result of installing a distributed generating resource within an electricity distribution system. The objective of this study was to develop a model for preparing preliminary estimates of substation capital costs based on rudimentary conceptual design information. The model is intended to be used by energy systems analysts who need ``ballpark`` substation cost estimates to help establish the value of advanced utility technologies that result in the deferral or displacement of substation equipment. This cost-estimating model requires only minimal inputs. More detailed cost-estimating approaches are recommended when more detailed design information is available. The model was developed by collecting and evaluating approximately 20 sets of substation design and cost data from about 10 US sources, including federal power marketing agencies and private and public electric utilities. The model is principally based on data provided by one of these sources. Estimates prepared with the model were compared with estimated and actual costs for the data sets received from the other utilities. In general, good agreement (for conceptual level estimating) was found between estimates prepared with the cost-estimating model and those prepared by the individual utilities. Thus, the model was judged to be adequate for making preliminary estimates of typical substation costs for US utilities.

  5. QGESS: Capital Cost Scaling Methodology

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the tonnes of CO2 utilized. The costs of the process are to include infrastructure, raw materials, processing, byproduct disposal, and utilities costs, as well as any other costs....

  6. Decommissioning Unit Cost Data

    SciTech Connect (OSTI)

    Sanford, P. C.; Stevens, J. L.; Brandt, R.

    2002-02-26

    The Rocky Flats Closure Site (Site) is in the process of stabilizing residual nuclear materials, decommissioning nuclear facilities, and remediating environmental media. A number of contaminated facilities have been decommissioned, including one building, Building 779, that contained gloveboxes used for plutonium process development but did little actual plutonium processing. The actual costs incurred to decommission this facility formed much of the basis or standards used to estimate the decommissioning of the remaining plutonium-processing buildings. Recent decommissioning activities in the first actual production facility, Building 771, implemented a number of process and procedural improvements. These include methods for handling plutonium contaminated equipment, including size reduction, decontamination, and waste packaging, as well as management improvements to streamline planning and work control. These improvements resulted in a safer working environment and reduced project cost, as demonstrated in the overall project efficiency. The topic of this paper is the analysis of how this improved efficiency is reflected in recent unit costs for activities specific to the decommissioning of plutonium facilities. This analysis will allow the Site to quantify the impacts on future Rocky Flats decommissioning activities, and to develop data for planning and cost estimating the decommissioning of future facilities. The paper discusses the methods used to collect and arrange the project data from the individual work areas within Building 771. Regression and data correlation techniques were used to quantify values for different types of decommissioning activities. The discussion includes the approach to identify and allocate overall project support, waste management, and Site support costs based on the overall Site and project costs to provide a ''burdened'' unit cost. The paper ultimately provides a unit cost basis that can be used to support cost estimates for

  7. Table 1. Updated estimates of power plant capital and operating costs

    U.S. Energy Information Administration (EIA) Indexed Site

    Updated estimates of power plant capital and operating costs" ,"Plant Characteristics",,,"Plant Costs (2012$)" ,"Nominal Capacity (MW)","Heat Rate (Btu/kWh)",,"Overnight Capital Cost ($/kW)","Fixed O&M Cost ($/kW-yr)","Variable O&M Cost ($/MWh)" ,,,,,,,"NEMS Input" " Coal" "Single Unit Advanced PC",650,8800,,3246,37.8,4.47,"N" "Dual Unit Advanced

  8. A model of the Capital Cost of a natural gas-fired fuel cell based Central Utilities Plant

    SciTech Connect (OSTI)

    Not Available

    1993-06-30

    This model defines the methods used to estimate the cost associated with acquisition and installation of capital equipment of the fuel cell systems defined by the central utility plant model. The capital cost model estimates the cost of acquiring and installing the fuel cell unit, and all auxiliary equipment such as a boiler, air conditioning, hot water storage, and pumps. The model provides a means to adjust initial cost estimates to consider learning associated with the projected level of production and installation of fuel cell systems. The capital cost estimate is an input to the cost of ownership analysis where it is combined with operating cost and revenue model estimates.

  9. Project Profile: Concurrent Optimization of Component Capital Cost and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Expected Operations and Management (SuNLaMP) | Department of Energy Project Profile: Concurrent Optimization of Component Capital Cost and Expected Operations and Management (SuNLaMP) Project Profile: Concurrent Optimization of Component Capital Cost and Expected Operations and Management (SuNLaMP) Funding Program: SuNLaMP SunShot Subprogram: CSP Location: National Renewable Energy Laboratory, Golden, CO SunShot Award Amount: $3,000,000 This project is developing and validating an open

  10. Discrete Event Modeling of Algae Cultivation and Harvesting at Commercial Scale: Capital Costs, Operating Costs, and System Bottlenecks

    SciTech Connect (OSTI)

    Lacey, Ph.D, P.E., Ronald E.

    2012-07-16

    Discrete Event Modeling of Algae Cultivation and Harvesting at Commercial Scale: Capital Costs, Operating Costs, and System Bottlenecks

  11. New developments in capital cost estimating

    SciTech Connect (OSTI)

    Stutz, R.A.; Zocher, M.A.

    1988-01-01

    The new developments in cost engineering revolve around the ability to capture information that in the past could not be automated. The purpose of automation is not to eliminate the expert cost engineer. The goal is to use available technology to have more information available to the professionals in the cost engineering field. In that sense, the demand for expertise increases in order to produce the highest quality estimate and project possible from all levels of cost engineers. We cannot overemphasize the importance of using a good source of expert information in building these types of programs. ''Garbage in, garbage out'' still applies in this form of programming. Expert systems technology will become commonplace in many vertical markets; it is important to undersand what can and cannot be accomplished in our field, and where this technology will lead us in the future.

  12. Accessing Low-Cost Capital Through Securitization (Poster)

    SciTech Connect (OSTI)

    Mendelsohn, M.

    2014-10-01

    Poster for Solar Power International conference presents information on NREL's effort to open capital markets through securitization via Solar Access to Public Capital (SAPC) working group's efforts.

  13. Low-cost inertial measurement unit.

    SciTech Connect (OSTI)

    Deyle, Travis Jay

    2005-03-01

    Sandia National Laboratories performs many expensive tests using inertial measurement units (IMUs)--systems that use accelerometers, gyroscopes, and other sensors to measure flight dynamics in three dimensions. For the purpose of this report, the metrics used to evaluate an IMU are cost, size, performance, resolution, upgradeability and testing. The cost of a precision IMU is very high and can cost hundreds of thousands of dollars. Thus the goals and results of this project are as follows: (1) Examine the data flow in an IMU and determine a generic IMU design. (2) Discuss a high cost IMU implementation and its theoretically achievable results. (3) Discuss design modifications that would save money for suited applications. (4) Design and implement a low cost IMU and discuss its theoretically achievable results. (5) Test the low cost IMU and compare theoretical results with empirical results. (6) Construct a more streamlined printed circuit board design reducing noise, increasing capabilities, and constructing a self-contained unit. Using these results, we can compare a high cost IMU versus a low cost IMU using the metrics from above. Further, we can examine and suggest situations where a low cost IMU could be used instead of a high cost IMU for saving cost, size, or both.

  14. Power plant capital investment cost estimates: current trends and sensitivity to economic parameters

    SciTech Connect (OSTI)

    Not Available

    1980-06-01

    This report describes power plant capital investment cost studies that were carried out as part of the activities of the Plans and Analysis Division, Office of Nuclear Energy Programs, US Department of Energy. The activities include investment cost studies prepared by an architect-engineer, including trends, effects of environmental and safety requirements, and construction schedules. A computer code used to prepare capital investment cost estimates under varying economic conditions is described, and application of this code is demonstrated by sensitivity studies.

  15. Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants

    Reports and Publications (EIA)

    2013-01-01

    The current and future projected cost and performance characteristics of new electric generating capacity are a critical input into the development of energy projections and analyses.

  16. Best Practices for Controlling Capital Costs in Net Zero Energy...

    Broader source: Energy.gov (indexed) [DOE]

    construction, it is necessary to demonstrate that NZE can be achieved cost effectively. This project aims to increase and accelerate the adoption of NZE design and construction ...

  17. Controlling Capital Costs in High Performance Office Buildings: A Review of Best Practices for Overcoming Cost Barriers

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Controlling Capital Costs in High Performance Office Buildings: A Review of Best Practices for Overcoming Cost Barriers Preprint Shanti Pless and Paul Torcellini To be presented at the ACEEE Summer Study on Energy Efficiency in Buildings Pacific Grove, California August 12-17, 2012 Conference Paper NREL/CP-5500-55264 May 2012 NOTICE The submitted manuscript has been offered by an employee of the Alliance for Sustainable Energy, LLC (Alliance), a contractor of the US Government under Contract No.

  18. Capital Projects Estimated >$7 Million in Direct Costs Business

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Transformer Replacement G1, G3,G5-8 Federal Hydro *-- Sustain Replace the existing transformers. Black Canyon Units 1 & 2 Upgrades Federal Hydro *-- Sustain Upgrades to increase...

  19. Wind-To-Hydrogen Project: Electrolyzer Capital Cost Study

    SciTech Connect (OSTI)

    Saur, G.

    2008-12-01

    This study is being performed as part of the U.S. Department of Energy and Xcel Energy's Wind-to-Hydrogen Project (Wind2H2) at the National Renewable Energy Laboratory. The general aim of the project is to identify areas for improving the production of hydrogen from renewable energy sources. These areas include both technical development and cost analysis of systems that convert renewable energy to hydrogen via water electrolysis. Increased efficiency and reduced cost will bring about greater market penetration for hydrogen production and application. There are different issues for isolated versus grid-connected systems, however, and these issues must be considered. The manner in which hydrogen production is integrated in the larger energy system will determine its cost feasibility and energy efficiency.

  20. Capital and operating cost estimates. Volume I. Preliminary design and assessment of a 12,500 BPD coal-to-methanol-to-gasoline plant. [Grace C-M-G Plant, Henderson County, Kentucky

    SciTech Connect (OSTI)

    Not Available

    1982-08-01

    This Deliverable No. 18b - Capital and Operating Cost Estimates includes a detailed presentation of the 12,500 BPD coal-to-methanol-to-gasoline plant from the standpoint of capital, preoperations, start-up and operations cost estimation. The base capital cost estimate in June 1982 dollars was prepared by the Ralph M. Parsons Company under the direction of Grace. The escalated capital cost estimate as well as separate estimates for preoperations, startup and operations activities were developed by Grace. The deliverable consists of four volumes. Volume I contains details of methodology used in developing the capital cost estimate, summary information on a base June 1982 capital cost, details of the escalated capital cost estimate and separate sections devoted to preoperations, start-up, and operations cost. The base estimate is supported by detailed information in Volumes II, III and IV. The degree of detail for some units was constrained due to proprietary data. Attempts have been made to exhibit the estimating methodology by including data on individual equipment pricing. Proprietary details are available for inspection upon execution of nondisclosure and/or secrecy agreements with the licensors to whom the data is proprietary. Details of factoring certain pieces of equipment and/or entire modules or units from the 50,000 BPD capital estimate are also included. In the case of the escalated capital estimate, Grace has chosen to include a sensitivity analysis which allows for ready assessment of impacts of escalation rates (inflation), contingency allowances and the construction interest financing rates on the escalated capital cost. Each of the estimates associated with bringing the plant to commercial production rates has as a basis the schedule and engineering documentation found in Deliverable No. 14b - Process Engineering and Mechanical Design Report, No. 28b - Staffing Plans, No. 31b - Construction Plan, and No. 33b - Startup and Operation Plan.

  1. Developing a Cost Model and Methodology to Estimate Capital Costs for Thermal Energy Storage

    SciTech Connect (OSTI)

    Glatzmaier, G.

    2011-12-01

    This report provides an update on the previous cost model for thermal energy storage (TES) systems. The update allows NREL to estimate the costs of such systems that are compatible with the higher operating temperatures associated with advanced power cycles. The goal of the Department of Energy (DOE) Solar Energy Technology Program is to develop solar technologies that can make a significant contribution to the United States domestic energy supply. The recent DOE SunShot Initiative sets a very aggressive cost goal to reach a Levelized Cost of Energy (LCOE) of 6 cents/kWh by 2020 with no incentives or credits for all solar-to-electricity technologies.1 As this goal is reached, the share of utility power generation that is provided by renewable energy sources is expected to increase dramatically. Because Concentrating Solar Power (CSP) is currently the only renewable technology that is capable of integrating cost-effective energy storage, it is positioned to play a key role in providing renewable, dispatchable power to utilities as the share of power generation from renewable sources increases. Because of this role, future CSP plants will likely have as much as 15 hours of Thermal Energy Storage (TES) included in their design and operation. As such, the cost and performance of the TES system is critical to meeting the SunShot goal for solar technologies. The cost of electricity from a CSP plant depends strongly on its overall efficiency, which is a product of two components - the collection and conversion efficiencies. The collection efficiency determines the portion of incident solar energy that is captured as high-temperature thermal energy. The conversion efficiency determines the portion of thermal energy that is converted to electricity. The operating temperature at which the overall efficiency reaches its maximum depends on many factors, including material properties of the CSP plant components. Increasing the operating temperature of the power generation

  2. Controlling Capital Costs in High Performance Office Buildings: A Review of Best Practices for Overcoming Cost Barriers

    SciTech Connect (OSTI)

    Pless, S.; Torcellini, P.

    2012-05-01

    This paper presents a set of 15 best practices for owners, designers, and construction teams of office buildings to reach high performance goals for energy efficiency, while maintaining a competitive budget. They are based on the recent experiences of the owner and design/build team for the Research Support Facility (RSF) on National Renewable Energy Facility's campus in Golden, CO, which show that achieving this outcome requires each key integrated team member to understand their opportunities to control capital costs.

  3. Access to Capital

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    IPR 2008 Capital Investment Review CIR 2012 Quarterly Business Review Focus 2028 2011 Strategic Capital Discussions Access to Capital Debt Optimization Asset Management Cost...

  4. 2011 Strategic Capital Discussions

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    IPR 2008 Capital Investment Review CIR 2012 Quarterly Business Review Focus 2028 2011 Strategic Capital Discussions Access to Capital Debt Optimization Asset Management Cost...

  5. Rocky Flats Closure Unit Cost Data

    SciTech Connect (OSTI)

    Sanford, P.C.; Skokan, B.

    2007-07-01

    The Rocky Flats Closure Project has completed the process of stabilizing residual nuclear materials, decommissioning nuclear facilities, remediating environmental media and closing the Rocky Flats Site (Site). The project cost approximately $4.1 B and included the decommissioning of over 700 structures including 5 major plutonium facilities and 5 major uranium facilities, shipping over 14,600 cubic meters of transuranic and 565,000 cubic meters of low level radioactive waste, and remediating a 385-acre industrial area and the surrounding land. Actual costs were collected for a large variety of closure activities. These costs can be correlated with metrics associated with the facilities and environmental media to capture cost factors from the project that could be applicable to a variety of other closure projects both within and outside of the Department of Energy's weapons complex. The paper covers four general topics: the process to correlate the actual costs and metrics, an example of the correlated data for one large sub-project, a discussion of the results, and the additional activities that are planned to correlate and make this data available to the public. The process to collect and arrange the project control data of the Closure Project relied on the actual Closure Project cost information. It was used to correlate these actual costs with the metrics for the physical work, such as building area or waste generated, to support the development of parametric cost factors. The example provides cost factors for the Industrial Sites Project. The discussion addresses the strengths and weaknesses of the data, followed by a section identifying future activities to improve and extend the analyses and integrate it within the Department's Environmental Cost Analysis System. (authors)

  6. FGD system capital and operating cost reductions based on improved thiosorbic scrubber system design and latest process innovations

    SciTech Connect (OSTI)

    Smith, K.; Tseng, S.; Babu, M.

    1994-12-31

    Dravo Lime Company has operated the Miami Fort wet scrubber FGD pilot test unit since late 1989 and has continued in-house R&D to improve the economics of the magnesium-enhanced scrubbing process. Areas investigated include the scrubber configuration, flue gas velocity, spray nozzle type, droplet size, mist eliminator design, additives to inhibit oxidation, improved solids dewatering, etc. Also tested was the forced oxidation Thioclear process. The data gathered from the pilot plant and in-house programs were used to evaluate the capital and operating costs for the improved systems. These evaluations were made with eye towards the choices electric utilities will need to make in the near future to meet the Phase II emission limits mandated by the 1990 Clean Air Act. Some of the process modifications investigated, for example, the dewatering improvements apply to potential beneficial retrofit of existing FGD systems today.

  7. A heat & mass integration approach to reduce capital and operating costs of a distillation configuration

    SciTech Connect (OSTI)

    Madenoor Ramapriya, Gautham; Jiang, Zheyu; Tawarmalani, Mohit; Agrawal, Rakesh

    2015-11-11

    We propose a general method to consolidate distillation columns of a distillation configuration using heat and mass integration. The proposed method encompasses all heat and mass integrations known till date, and includes many more. Each heat and mass integration eliminates a distillation column, a condenser, a reboiler and the heat duty associated with a reboiler. Thus, heat and mass integration can potentially offer significant capital and operating cost benefits. In this talk, we will study the various possible heat and mass integrations in detail, and demonstrate their benefits using case studies. This work will lay out a framework to synthesize an entire new class of useful configurations based on heat and mass integration of distillation columns.

  8. Cycling fossil-fired units proves costly business

    SciTech Connect (OSTI)

    Lefton, S.; Grimsrud, P.; Besuner, P.

    1997-07-01

    Competition in the electric utility business is having a far-reaching impact. Cost-cutting measures have in major downsizing efforts in virtually every utility in the country. After several cost-cutting rounds to reduce the low hanging fruit of inefficiency, utilities are still challenged to become leaner and meaner in order to compete in a deregulated environment. The problem for many power utilities, however, is they have not precisely determined their costs in every aspect of the plant`s operation. Naturally, obtaining an accurate understanding of expenditures is the starting point for utilities that wish to develop strategic plans to better manage assets, minimize costs and maximize return on investment better understand plant O&M costs and take measures to use this knowledge to their advantage. Cycling is a major reason for the increase in O&M costs of many fossil units. Cycling, in this context, refers to the operation of generating units at varying load levels in response to changes in system-load requirements.

  9. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    BPA on 242015 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  10. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    BPA on 622014 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  11. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    on 1142014 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  12. Major Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    on 2112014 and does not contain Agency-approved Financial Information. 1 Includes capital projects authorized at the agency level since August 2007 2 Direct capital costs...

  13. Philadelphia gas works medium-Btu coal gasification project: capital and operating cost estimate, financial/legal analysis, project implementation

    SciTech Connect (OSTI)

    Not Available

    1981-12-01

    This volume of the final report is a compilation of the estimated capital and operating costs for the project. Using the definitive design as a basis, capital and operating costs were developed by obtaining quotations for equipment delivered to the site. Tables 1.1 and 1.2 provide a summary of the capital and operating costs estimated for the PGW Coal Gasification Project. In the course of its Phase I Feasibility Study of a medium-Btu coal-gas facility, Philadelphia Gas Works (PGW) identified the financing mechanism as having great impact on gas cost. Consequently, PGW formed a Financial/Legal Task Force composed of legal, financial, and project analysis specialists to study various ownership/management options. In seeking an acceptable ownership, management, and financing arrangement, certain ownership forms were initially identified and classified. Several public ownership, private ownership, and third party ownership options for the coal-gas plant are presented. The ownership and financing forms classified as base alternatives involved tax-exempt and taxable financing arrangements and are discussed in Section 3. Project implementation would be initiated by effectively planning the methodology by which commercial operation will be realized. Areas covered in this report are sale of gas to customers, arrangements for feedstock supply and by-product disposal, a schedule of major events leading to commercialization, and a plan for managing the implementation.

  14. Beetle Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Beetle Capital Partners Jump to: navigation, search Logo: Beetle Capital Partners Name: Beetle Capital Partners Address: Medici Court, 67-69 New Bond Street Place: London, United...

  15. Temple Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Temple Capital Partners Jump to: navigation, search Name: Temple Capital Partners Place: United Kingdom Product: Fund manager of Clean Energy Brazil. References: Temple Capital...

  16. Green Capital Management | Open Energy Information

    Open Energy Info (EERE)

    Capital Management Jump to: navigation, search Name: Green Capital Management Place: London, United Kingdom Zip: SW10 0BB Sector: Services Product: The Green Capital Management...

  17. EXPERT ELICITATION OF ACROSS-TECHNOLOGY CORRELATIONS FOR REACTOR CAPITAL COSTS

    SciTech Connect (OSTI)

    Brent Dixon; Various

    2014-06-01

    Calculations of the uncertainty in the Levelized Cost at Equilibrium (LCAE) of generating nuclear electricity typically assume that the costs of the system component, notably reactors, are uncorrelated. Partial cancellation of independent errors thus gives rise to unrealistically small cost uncertainties for fuel cycles that incorporate multiple reactor technologies. This summary describes an expert elicitation of correlations between overnight reactor construction costs. It also defines a method for combining the elicitations into a single, consistent correlation matrix suitable for use in Monte Carlo LCAE calculations. Both the elicitation and uncertainty propagation methods are demonstrated through a pilot study where cost correlations between eight reactor technologies were elicited from experts in the US DOE Fuel Cycle Research

  18. Carbon Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Carbon Capital Place: United Kingdom Sector: Carbon Product: Manages a carbon fund specialised in forestry projects References: Carbon...

  19. Gaian Capital | Open Energy Information

    Open Energy Info (EERE)

    Gaian Capital Jump to: navigation, search Name: Gaian Capital Place: Greater London, United Kingdom Product: London-based privately held firm aimed at assisting climate change...

  20. Capital Connections | Open Energy Information

    Open Energy Info (EERE)

    Connections Jump to: navigation, search Name: Capital Connections Place: United Kingdom Product: Supplies fuel cell systems. References: Capital Connections1 This article is a...

  1. SunShot: Making Solar Energy Cost Competitive Throughout the United States (Fact Sheet)

    SciTech Connect (OSTI)

    McCamey, D.

    2011-03-01

    The U.S. Department of Energy's SunShot Initiative focuses on making solar energy cost competitive throughout the United States.

  2. Break-Even Cost for Residential Solar Water Heating in the United...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Break-even Cost for Residential Solar Water Heating in the United States: Key Drivers and Sensitivities Hannah Cassard, Paul Denholm, and Sean Ong Technical Report NREL...

  3. SunShot: Making Solar Energy Cost Competitive Throughout the United States (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2011-06-01

    The U.S. Department of Energy's SunShot Initiative focuses on making solar energy cost competitive throughout the United States.

  4. Hazel Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Hazel Capital Place: London, England, United Kingdom Zip: WC2A 1AL Sector: Efficiency, Renewable Energy Product: Hazel Capital is an asset...

  5. Capital Reporting Company Quadrennial ...

    Broader source: Energy.gov (indexed) [DOE]

    Capital Reporting Company Quadrennial Energy Review Meeting No. 4 06-19-2014 (866) 448 - DEPO www.CapitalReportingCompany.com 2014 1 UNITED STATES DEPARTMENT OF ENERGY OFFICE OF ...

  6. Residential, Commercial, and Utility-Scale Photovoltaic (PV) System Prices in the United States: Current Drivers and Cost-Reduction Opportunities

    SciTech Connect (OSTI)

    Goodrich, A.; James, T.; Woodhouse, M.

    2012-02-01

    The price of photovoltaic (PV) systems in the United States (i.e., the cost to the system owner) has dropped precipitously in recent years, led by substantial reductions in global PV module prices. However, system cost reductions are not necessarily realized or realized in a timely manner by many customers. Many reasons exist for the apparent disconnects between installation costs, component prices, and system prices; most notable is the impact of fair market value considerations on system prices. To guide policy and research and development strategy decisions, it is necessary to develop a granular perspective on the factors that underlie PV system prices and to eliminate subjective pricing parameters. This report's analysis of the overnight capital costs (cash purchase) paid for PV systems attempts to establish an objective methodology that most closely approximates the book value of PV system assets.

  7. IEA Wind Task 26. Wind Technology, Cost and Performance Trends in Denmark, Germany, Ireland, Norway, the European Union, and the United States. 2007 - 2012

    SciTech Connect (OSTI)

    Vitina, Aisma; Luers, Silke; Wallasch, Anna-Kathrin; Berkhout, Volker; Duffy, Aidan; Cleary, Brendan; Husabo, Leif I.; Weir, David E.; Lacal-Arantegui, Roberto; Hand, M. Maureen; Lantz, Eric; Belyeu, Kathy; Wiser, Ryan; Bolinger, Mark; Hoen, Ben

    2015-06-12

    This report builds from a similar previous analysis (Schwabe et al., 2011) exploring the differences in cost of wind energy in 2008 among countries participating in IEA Wind Task 26 at that time. The levelized cost of energy (LCOE) is a widely recognized metric for understanding how technology, capital investment, operations, and financing impact the life-cycle cost of building and operating a wind plant. Schwabe et al. (2011) apply a spreadsheet-based cash flow model developed by the Energy Research Centre of the Netherlands (ECN) to estimate LCOE. This model is a detailed, discounted cash flow model used to represent the various cost structures in each of the participating countries from the perspective of a financial investor in a domestic wind energy project. This model is used for the present analysis as well, and comparisons are made for those countries who contributed to both reports, Denmark, Germany, and the United States.

  8. TRANSMISSION AND DISTRIBUTION; POWER SUBSTATIONS; CAPITALIZED...

    Office of Scientific and Technical Information (OSTI)

    AND DISTRIBUTION; POWER SUBSTATIONS; CAPITALIZED COST; CALCULATION METHODS; PLANNING; COST ESTIMATION; MATHEMATICAL MODELS The displacement or deferral of substation...

  9. Renewable Energy Cost Modeling. A Toolkit for Establishing Cost-Based Incentives in the United States

    SciTech Connect (OSTI)

    Gifford, Jason S.; Grace, Robert C.; Rickerson, Wilson H.

    2011-05-01

    This report serves as a resource for policymakers who wish to learn more about levelized cost of energy (LCOE) calculations, including cost-based incentives. The report identifies key renewable energy cost modeling options, highlights the policy implications of choosing one approach over the other, and presents recommendations on the optimal characteristics of a model to calculate rates for cost-based incentives, FITs, or similar policies. These recommendations shaped the design of NREL's Cost of Renewable Energy Spreadsheet Tool (CREST), which is used by state policymakers, regulators, utilities, developers, and other stakeholders to assist with analyses of policy and renewable energy incentive payment structures. Authored by Jason S. Gifford and Robert C. Grace of Sustainable Energy Advantage LLC and Wilson H. Rickerson of Meister Consultants Group, Inc.

  10. Impacts of Renewable Generation on Fossil Fuel Unit Cycling: Costs and Emissions (Presentation)

    SciTech Connect (OSTI)

    Brinkman, G.; Lew, D.; Denholm, P.

    2012-09-01

    Prepared for the Clean Energy Regulatory Forum III, this presentation looks at the Western Wind and Solar Integration Study and reexamines the cost and emissions impacts of fossil fuel unit cycling.

  11. Cost of Capital

    Broader source: Energy.gov [DOE]

    This presentation summarizes the information given by PV Evolution Labs during the DOE SunShot Grand Challenge: Summit and Technology Forum, June 13-14, 2012.

  12. Breakeven Cost for Residential Photovoltaics in the United States: Key Drivers and Sensitivities (Report Summary) (Presentation)

    SciTech Connect (OSTI)

    Denholm, P.; Margolis, R. M.; Ong, S.; Roberts, B.

    2009-12-01

    "Break-even cost" for photovoltaic (PV) technology is defined as the point where the cost of PV-generated electricity equals the cost of electricity purchased from the grid. Break-even cost is expressed in $/W of an installed system. Achieving break-even cost is a function of many variables. Consequently, break-even costs vary by location and time for a country, such as the United States, with a diverse set of resources, electricity prices, and other variables. In this presentation, we introduce an analysis of PV break-even costs for residential customers in the United States, including an evaluation of some of the key drivers of PV breakeven both regionally and over time. This presentation includes our methodology and presents results for both near-term residential breakeven costs(2009) and future market sensitivities of break-even costs (2015). See also the the report "Break-Even Cost for Residential Photovoltaics in the United States: Key Drivers and Sensitivities". Presentation for NREL/TP-6A2-45991.

  13. Replacement energy costs for nuclear electricity-generating units in the United States: 1997--2001. Volume 4

    SciTech Connect (OSTI)

    VanKuiken, J.C.; Guziel, K.A.; Tompkins, M.M.; Buehring, W.A.

    1997-09-01

    This report updates previous estimates of replacement energy costs for potential short-term shutdowns of 109 US nuclear electricity-generating units. This information was developed to assist the US Nuclear Regulatory Commission (NRC) in its regulatory impact analyses, specifically those that examine the impacts of proposed regulations requiring retrofitting of or safety modifications to nuclear reactors. Such actions might necessitate shutdowns of nuclear power plants while these changes are being implemented. The change in energy cost represents one factor that the NRC must consider when deciding to require a particular modification. Cost estimates were derived from probabilistic production cost simulations of pooled utility system operations. Factors affecting replacement energy costs, such as random unit failures, maintenance and refueling requirements, and load variations, are treated in the analysis. This report describes an abbreviated analytical approach as it was adopted to update the cost estimates published in NUREG/CR-4012, Vol. 3. The updates were made to extend the time frame of cost estimates and to account for recent changes in utility system conditions, such as change in fuel prices, construction and retirement schedules, and system demand projects.

  14. Climate Human Capital | Open Energy Information

    Open Energy Info (EERE)

    Human Capital Jump to: navigation, search Name: Climate Human Capital Place: London, United Kingdom Zip: W1K 6NG Sector: Carbon, Renewable Energy, Services Product: Green executive...

  15. Cape Verde Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Cape Verde Capital Place: Leatherhead, United Kingdom Zip: KT22 7SW Sector: Renewable Energy Product: The renewable energy investment arm...

  16. Transmission Capital Limited | Open Energy Information

    Open Energy Info (EERE)

    Transmission Capital Limited Jump to: navigation, search Name: Transmission Capital Limited Place: London, United Kingdom Zip: EC2V 7HR Sector: Renewable Energy, Services Product:...

  17. Sustainable Development Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Capital LLP Jump to: navigation, search Name: Sustainable Development Capital LLP Place: London, United Kingdom Zip: W1S 3AT Product: Investment bank working with financial...

  18. Clean Earth Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Capital LLP Jump to: navigation, search Name: Clean Earth Capital LLP Place: EDINBURGH, United Kingdom Zip: EH6 4NW Sector: Renewable Energy Product: Edinburgh-based corporate...

  19. James Monroe Capital Corporation | Open Energy Information

    Open Energy Info (EERE)

    Monroe Capital Corporation Jump to: navigation, search Name: James Monroe Capital Corporation Place: United States Sector: Services Product: General Financial & Legal Services (...

  20. Evaluation of syngas production unit cost of bio-gasification facility using regression analysis techniques

    SciTech Connect (OSTI)

    Deng, Yangyang; Parajuli, Prem B.

    2011-08-10

    Evaluation of economic feasibility of a bio-gasification facility needs understanding of its unit cost under different production capacities. The objective of this study was to evaluate the unit cost of syngas production at capacities from 60 through 1800Nm 3/h using an economic model with three regression analysis techniques (simple regression, reciprocal regression, and log-log regression). The preliminary result of this study showed that reciprocal regression analysis technique had the best fit curve between per unit cost and production capacity, with sum of error squares (SES) lower than 0.001 and coefficient of determination of (R 2) 0.996. The regression analysis techniques determined the minimum unit cost of syngas production for micro-scale bio-gasification facilities of $0.052/Nm 3, under the capacity of 2,880 Nm 3/h. The results of this study suggest that to reduce cost, facilities should run at a high production capacity. In addition, the contribution of this technique could be the new categorical criterion to evaluate micro-scale bio-gasification facility from the perspective of economic analysis.

  1. Break-Even Cost for Residential Photovoltaics in the United States: Key Drivers and Sensitivities

    SciTech Connect (OSTI)

    Denholm, P.; Margolis, R. M.; Ong, S.; Roberts, B.

    2009-12-01

    Grid parity--or break-even cost--for photovoltaic (PV) technology is defined as the point where the cost of PV-generated electricity equals the cost of electricity purchased from the grid. Break-even cost is expressed in $/W of an installed system. Achieving break-even cost is a function of many variables. Consequently, break-even costs vary by location and time for a country, such as the United States, with a diverse set of resources, electricity prices, and other variables. In this report, we analyze PV break-even costs for U.S. residential customers. We evaluate some key drivers of grid parity both regionally and over time. We also examine the impact of moving from flat to time-of-use (TOU) rates, and we evaluate individual components of the break-even cost, including effect of rate structure and various incentives. Finally, we examine how PV markets might evolve on a regional basis considering the sensitivity of the break-even cost to four major drivers: technical performance, financing parameters, electricity prices and rates, and policies. We find that local incentives rather than ?technical? parameters are in general the key drivers of the break-even cost of PV. Additionally, this analysis provides insight about the potential viability of PV markets.

  2. Osmosis Capital | Open Energy Information

    Open Energy Info (EERE)

    Osmosis Capital Jump to: navigation, search Name: Osmosis Capital Place: London, United Kingdom Zip: EC4M 9DN Sector: Carbon Product: An investment firm seeking low carbon economy...

  3. (OECD Expert Group meeting on reduction of capital costs of nuclear power plants, Paris, France, July 21--26, 1989): Foreign trip report

    SciTech Connect (OSTI)

    Hudson, C.R. II

    1989-08-09

    The OECD initiated a study of means to reduce the capital costs of nuclear power plants in the latter part of 1988. To accomplish the study, an Expert Group consisting of representatives of OECD member countries was formed. The initial meeting of the Expert Group was held in November 1988. A second meeting, documented in an ORNL trip report by this author, was held in May 1989. This meeting represents the third follow-on meeting with the primary goal of reviewing the draft report written by members of the Expert Group.

  4. Cost Effectiveness of Home Energy Retrofits in Pre-Code Vintage Homes in the United States

    SciTech Connect (OSTI)

    Fairey, Philip

    2012-11-01

    This analytical study examines the opportunities for cost-effective energy efficiency and renewable energy retrofits in residential archetypes constructed prior to 1980 (Pre-Code) in fourteen U.S. cities. These fourteen cities are representative of each of the International Energy Conservation Code (IECC) climate zones in the contiguous United States. The analysis is conducted using an in-house version of EnergyGauge USA v.2.8.05 named CostOpt that has been programmed to perform iterative, incremental economic optimization on a large list of residential energy efficiency and renewable energy retrofit measures. The principle objectives of the study are to determine the opportunities for cost effective source energy reductions in this large cohort of existing residential building stock as a function of local climate and energy costs; and to examine how retrofit financing alternatives impact the source energy reductions that are cost effectively achievable.

  5. Microsoft PowerPoint - Cost Escalation.ppt

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Hydroelectric Design Center Hydroelectric Design Center " " Cost Trends for Cost Trends for Hydropower Capital Hydropower Capital Replacements" Replacements" Presentation Outline ...

  6. Cost and Performance Assumptions for Modeling Electricity Generation...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... 16 Figure 6. Overnight capital costs-coal ......22 Figure 8. Overnight capital costs-combustion turbine ......

  7. Cost of Wind Energy in the United States: Trends from 2007 to 2012 (Presentation)

    SciTech Connect (OSTI)

    Hand, M.

    2015-01-01

    This presentation provides an overview of recent technology trends observed in the United States including project size, turbine size, rotor diameter, hub height, annual average wind speed, and annual energy production. It also highlights area where system analysis is required to fully understand how these technology trends relate to the cost of wind energy.

  8. EM Capital Asset Project List

    Broader source: Energy.gov [DOE]

    Read the EM Capital Asset Project List, which includes the project's name, site, current critical decision and current total project cost.

  9. Cost-effectiveness of emission control at fossil-fuel units for different cumulative load patterns

    SciTech Connect (OSTI)

    Roy, S.

    1997-02-01

    This paper describes a method to recommend allocation of generating units, with a view to achieve cost-effective control of particulate and gaseous emissions over an energy scenario. Definition of relative cost and relative emission, with respect to corresponding base-case values, allows one to develop a model that describes cost and emission aspects of the chosen scenario. Optimization of this model, by any appropriate linear-programming software, yields the allocation levels to be recommended. The emphasis of this paper is on the way in which results of the said optimization model reflect the effect of demand patterns on the allocation levels. Depending on the demands, required generation levels from each individual unit may differ. This affects the overall generation cost, and simultaneously the emissions from the thermal units, both relative to respective base values. Since the optimization algorithm attempts to reduce both the relative quantities, its results always reflect the changing generation vs. emission tradeoff for utilities vis-a-vis different demand patterns.

  10. Energy Conservation Program for Consumer Products: Representative Average Unit Costs of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Conservation Program for Consumer Products: Representative Average Unit Costs of Energy, is a notice issued by the Department of Energy. Though it is not intended or expected, should any discrepancy occur between the document posted here and the document published in the Federal Register, the Federal Register publication controls. This document is being made available through the Internet solely as a means to facilitate the public's access to this document."

  11. Best Practices for Controlling Capital Costs in Net Zero Energy Design and Construction- 2014 BTO Peer Review

    Broader source: Energy.gov [DOE]

    Presenter: Shanti Pless, National Renewable Energy Laboratory For net zero energy (NZE) building performance to become the norm in new commercial construction, it is necessary to demonstrate that NZE can be achieved cost effectively.

  12. The Capital Intensity of Photovoltaics Manufacturing

    SciTech Connect (OSTI)

    Basore, Paul

    2015-10-19

    Factory capital expenditure (capex) for photovoltaic (PV) module manufacturing strongly influences the per-unit cost of a c-Si module. This provides a significant opportunity to address the U.S. DOE SunShot module price target through capex innovation. Innovation options to reduce the capex of PV manufacturing include incremental and disruptive process innovation with c-Si, platform innovations, and financial approaches. and financial approaches.

  13. Operating Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter is focused on capital costs for conventional construction and environmental restoration and waste management projects and examines operating cost estimates to verify that all elements of the project have been considered and properly estimated.

  14. Energy Savings and Breakeven Costs for Residential Heat Pump Water Heaters in the United States

    SciTech Connect (OSTI)

    Maguire, Jeff; Burch, Jay; Merrigan, Tim; Ong, Sean

    2013-07-01

    Heat pump water heaters (HPWHs) have recently re-emerged in the U.S. residential water heating market and have the potential to provide homeowners with significant energy savings. However, there are questions as to the actual performance and energy savings potential of these units, in particular in regards to the heat pump's performance in unconditioned space and the impact of the heat pump on space heating and cooling loads when it is located in conditioned space. To help answer these questions, NREL performed simulations of a HPWH in both conditioned and unconditioned space at over 900 locations across the continental United States and Hawaii. Simulations included a Building America benchmark home so that any interaction between the HPWH and the home's HVAC equipment could be captured. Comparisons were performed to typical gas and electric water heaters to determine the energy savings potential and cost effectiveness of a HPWH relative to these technologies. HPWHs were found to have a significant source energy savings potential when replacing typical electric water heaters, but only saved source energy relative to gas water heater in the most favorable installation locations in the southern United States. When replacing an electric water heater, the HPWH is likely to break even in California, the southern United States, and parts of the northeast in most situations. However, the HPWH will only break even when replacing a gas water heater in a few southern states.

  15. Ricmore Capital PLC Formerly Energy Asset Management Plc | Open...

    Open Energy Info (EERE)

    Ricmore Capital PLC Formerly Energy Asset Management Plc Jump to: navigation, search Name: Ricmore Capital PLC (Formerly Energy Asset Management Plc) Place: United Kingdom Sector:...

  16. Free Stream Capital Partners Limited | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Limited Jump to: navigation, search Name: Free Stream Capital Partners Limited Place: London, Greater London, United Kingdom Zip: SW1Y 4AA Sector: Wind energy...

  17. A preliminary design and BOP cost analysis of M-C Power`s MCFC commerical unit

    SciTech Connect (OSTI)

    Chen, T.P.

    1996-12-31

    M-C Power Corporation plans to introduce its molten carbonate fuel cell (MCFC) market entry unit in the year 2000 for distributed and on-site power generation. Extensive efforts have been made to analyze the cell stack manufacturing costs. The major objective of this study is to conduct a detailed analysis of BOP costs based on an initial design of the market entry unit.

  18. Access to Capital | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Soft Costs Access to Capital Access to Capital Photo of a room full of people seated in rows with a few standing in the background. Two hands in the crowd are holding up sheets ...

  19. Pulsar Energy Capital L L P | Open Energy Information

    Open Energy Info (EERE)

    Pulsar Energy Capital L L P Jump to: navigation, search Name: Pulsar Energy Capital L.L.P. Place: London, United Kingdom Zip: SW20 0PU Product: Pulsar Energy Capital LLP is a...

  20. Sindicatum Carbon Capital SCC | Open Energy Information

    Open Energy Info (EERE)

    Sindicatum Carbon Capital SCC Jump to: navigation, search Name: Sindicatum Carbon Capital (SCC) Place: London, United Kingdom Zip: W1S 1HX Product: SCC is a specialist end-to-end...

  1. Carbon Capital Markets | Open Energy Information

    Open Energy Info (EERE)

    Capital Markets Jump to: navigation, search Name: Carbon Capital Markets Place: London, United Kingdom Zip: W1J 8DY Sector: Carbon Product: London-based fund manager and trader...

  2. Absolute Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Absolute Energy Capital Place: London, United Kingdom Zip: SW1Y 5NQ Product: London-based private equity firm. Coordinates: 51.506325,...

  3. Englefield Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Englefield Capital LLP Jump to: navigation, search Name: Englefield Capital LLP Place: London, Greater London, United Kingdom Zip: SW3 6RD Product: London-based private equity fund...

  4. Emerging Edge Capital EEC | Open Energy Information

    Open Energy Info (EERE)

    Edge Capital EEC Jump to: navigation, search Name: Emerging Edge Capital (EEC) Place: London, United Kingdom Zip: SW1Y 4RS Sector: Renewable Energy Product: London-based company...

  5. Plane Tree Capital LLP | Open Energy Information

    Open Energy Info (EERE)

    Plane Tree Capital LLP Jump to: navigation, search Name: Plane Tree Capital LLP Place: London, United Kingdom Zip: W1J 8DY Sector: Carbon Product: London-based investment...

  6. Absolut Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Absolut Energy Capital Jump to: navigation, search Name: Absolut Energy Capital Place: London, England, United Kingdom Zip: W1H - 6HN Sector: Renewable Energy Product: London-based...

  7. Renewable Energy Cost Modeling: A Toolkit for Establishing Cost-Based Incentives in the United States; March 2010 -- March 2011

    SciTech Connect (OSTI)

    Gifford, J. S.; Grace, R. C.; Rickerson, W. H.

    2011-05-01

    This report is intended to serve as a resource for policymakers who wish to learn more about establishing cost-based incentives. The report will identify key renewable energy cost modeling options, highlight the policy implications of choosing one approach over the other, and present recommendations on the optimal characteristics of a model to calculate rates for cost-based incentives, feed-in tariffs (FITs), or similar policies. These recommendations will be utilized in designing the Cost of Renewable Energy Spreadsheet Tool (CREST). Three CREST models will be publicly available and capable of analyzing the cost of energy associated with solar, wind, and geothermal electricity generators. The CREST models will be developed for use by state policymakers, regulators, utilities, developers, and other stakeholders to assist them in current and future rate-setting processes for both FIT and other renewable energy incentive payment structures and policy analyses.

  8. Economic impacts of oil spills: Spill unit costs for tankers, pipelines, refineries, and offshore facilities. [Task 1, Final report

    SciTech Connect (OSTI)

    Not Available

    1993-10-15

    The impacts of oil spills -- ranging from the large, widely publicized Exxon Valdez tanker incident to smaller pipeline and refinery spills -- have been costly to both the oil industry and the public. For example, the estimated costs to Exxon of the Valdez tanker spill are on the order of $4 billion, including $2.8 billion (in 1993 dollars) for direct cleanup costs and $1.125 billion (in 1992 dollars) for settlement of damages claims caused by the spill. Application of contingent valuation costs and civil lawsuits pending in the State of Alaska could raise these costs appreciably. Even the costs of the much smaller 1991 oil spill at Texaco`s refinery near Anacortes, Washington led to costs of $8 to 9 million. As a result, inexpensive waming, response and remediation technologies could lower oil spin costs, helping both the oil industry, the associated marine industries, and the environment. One means for reducing the impact and costs of oil spills is to undertake research and development on key aspects of the oil spill prevention, warming, and response and remediation systems. To target these funds to their best use, it is important to have sound data on the nature and size of spills, their likely occurrence and their unit costs. This information could then allow scarce R&D dollars to be spent on areas and activities having the largest impact. This report is intended to provide the ``unit cost`` portion of this crucial information. The report examines the three key components of the US oil supply system, namely, tankers and barges; pipelines and refineries; and offshore production facilities. The specific purpose of the study was to establish the unit costs of oil spills. By manipulating this key information into a larger matrix that includes the size and frequency of occurrence of oil spills, it will be possible` to estimate the likely future impacts, costs, and sources of oil spills.

  9. Energy Savings and Breakeven Cost for Residential Heat Pump Water Heaters in the United States

    SciTech Connect (OSTI)

    Maguire, J.; Burch, J.; Merrigan, T.; Ong, S.

    2013-07-01

    Heat pump water heaters (HPWHs) have recently reemerged in the U.S. residential water heating market and have the potential to provide homeowners with significant energy savings. However, there are questions as to the actual performance and energy savings potential of these units, in particular in regards to the heat pump's performance in unconditioned space and the impact of the heat pump on space heating and cooling loads when it is located in conditioned space. To help answer these questions, simulations were performed of a HPWH in both conditioned and unconditioned space at over 900 locations across the continental United States and Hawaii. Simulations included a Building America benchmark home so that any interaction between the HPWH and the home's HVAC equipment could be captured. Comparisons were performed to typical gas and electric water heaters to determine the energy savings potential and cost effectiveness of a HPWH relative to these technologies. HPWHs were found to have a significant source energy savings potential when replacing typical electric water heaters, but only saved source energy relative to gas water heater in the most favorable installation locations in the southern US. When replacing an electric water heater, the HPWH is likely to break even in California, the southern US, and parts of the northeast in most situations. However, the HPWH will only break even when replacing a gas water heater in a few southern states.

  10. QGESS: Capital Cost Scaling Methodology

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    QUALITY GUIDELINES FOR ENERGY SYSTEM STUDIES Performing a Techno-economic Analysis for Power Generation Plants DOENETL-2010???? DOENETL-20151726 Techno-economic Analysis...

  11. Break-Even Cost for Residential Solar Water Heating in the United States: Key Drivers and Sensitivities

    SciTech Connect (OSTI)

    Cassard, H.; Denholm, P.; Ong, S.

    2011-02-01

    This paper examines the break-even cost for residential rooftop solar water heating (SWH) technology, defined as the point where the cost of the energy saved with a SWH system equals the cost of a conventional heating fuel purchased from the grid (either electricity or natural gas). We examine the break-even cost for the largest 1,000 electric and natural gas utilities serving residential customers in the United States as of 2008. Currently, the break-even cost of SWH in the United States varies by more than a factor of five for both electricity and natural gas, despite a much smaller variation in the amount of energy saved by the systems (a factor of approximately one and a half). The break-even price for natural gas is lower than that for electricity due to a lower fuel cost. We also consider the relationship between SWH price and solar fraction and examine the key drivers behind break-even costs. Overall, the key drivers of the break-even cost of SWH are a combination of fuel price, local incentives, and technical factors including the solar resource location, system size, and hot water draw.

  12. Foundation Capital

    Broader source: Energy.gov (indexed) [DOE]

    FC, ORNL, MB Confidential 3 Foundation Capital Confidential Distribution of 1,500 reviewed ORNL IP Out of 3,000 Total Disclosures Filed Over 25 yrs FC, ORNL, MB Confidential Many ...

  13. Benchmarking Soft Costs for PV Systems in the United States (Presentation)

    SciTech Connect (OSTI)

    Ardani, K.

    2012-06-01

    This paper presents results from the first U.S. based data collection effort to quantify non-hardware, business process costs for PV systems at the residential and commercial scales, using a bottom-up approach. Annual expenditure and labor hour productivity data are analyzed to benchmark business process costs in the specific areas of: (1) customer acquisition; (2) permitting, inspection, and interconnection; (3) labor costs of third party financing; and (4) installation labor.

  14. Tracking the Sun III; The Installed Cost of Photovoltaics in the United States from 1998-2009

    SciTech Connect (OSTI)

    Barbose, Galen; Darghouth, Naim; Wiser, Ryan

    2010-12-13

    Installations of solar photovoltaic (PV) systems have been growing at a rapid pace in recent years. In 2009, approximately 7,500 megawatts (MW) of PV were installed globally, up from approximately 6,000 MW in 2008, consisting primarily of grid-connected applications. With 335 MW of grid-connected PV capacity added in 2009, the United States was the world's fourth largest PV market in 2009, behind Germany, Italy, and Japan. The market for PV in the United States is driven by national, state, and local government incentives, including up-front cash rebates, production-based incentives, requirements that electricity suppliers purchase a certain amount of solar energy, and federal and state tax benefits. These programs are, in part, motivated by the popular appeal of solar energy, and by the positive attributes of PV - modest environmental impacts, avoidance of fuel price risks, coincidence with peak electrical demand, and the possible deployment of PV at the point of use. Given the relatively high cost of PV, however, a key goal of these policies is to encourage cost reductions over time. Therefore, as policy incentives have become more significant and as PV deployment has accelerated, so too has the desire to track the installed cost of PV systems over time, by system characteristics, by system location, and by component. Despite the significant year-on-year growth, however, the share of global and U.S. electricity supply met with PV remains small, and annual PV additions are currently modest in the context of the overall electric system. To address this need, Lawrence Berkeley National Laboratory initiated a report series focused on describing trends in the installed cost of grid-connected PV systems in the United States. The present report, the third in the series, describes installed cost trends from 1998 through 2009, and provides preliminary cost data for systems installed in 2010. The analysis is based on project-level cost data from approximately 78

  15. Return to 1990: The cost of mitigating United States carbon emissions in the post-2000 period

    SciTech Connect (OSTI)

    Edmonds, J.A.; Kim, S.H.; MacCracken, C.N.; Sands, R.D.; Wise, M.A.

    1997-10-01

    The Second Generation Model (SGM) is employed to examine four hypothetical agreements to reduce emissions in Annex 1 nations (OECD nations plus most of the nations of Eastern Europe and the former Soviet Union) to levels in the neighborhood of those which existed in 1990, with obligations taking effect in the year 2010. The authors estimate the cost to the US of complying with such agreements under three distinct conditions: no trading of emissions rights, trading of emissions rights only among Annex 1 nations, and a fully global trading regime. The authors find that the marginal cost of returning to 1990 emissions levels in the US in the absence of trading opportunities is approximately $108 per metric ton carbon in 2010. The total cost in that year is approximately 0.2% of GDP. International trade in emissions permits lowers the cost of achieving any mitigation objective by equalizing the marginal cost of carbon mitigation among countries. For the four mitigation scenarios in this study, economic costs to the US remain below 1% of GDP through at least the year 2020.

  16. Cost of Power Interruptions to Electricity Consumers in the UnitedStates (U.S.)

    SciTech Connect (OSTI)

    Hamachi LaCommare, Kristina; Eto, Joseph H.

    2006-02-16

    The massive electric power blackout in the northeastern U.S.and Canada on August 14-15, 2003 catalyzed discussions about modernizingthe U.S. electricity grid. Industry sources suggested that investments of$50 to $100 billion would be needed. This work seeks to better understandan important piece of information that has been missing from thesediscussions: What do power interruptions and fluctuations in powerquality (power-quality events) cost electricity consumers? We developed abottom-up approach for assessing the cost to U.S. electricity consumersof power interruptions and power-quality events (referred to collectivelyas "reliability events"). The approach can be used to help assess thepotential benefits of investments in improving the reliability of thegrid. We developed a new estimate based on publicly availableinformation, and assessed how uncertainties in these data affect thisestimate using sensitivity analysis.

  17. Analysis of Cycling Costs in Western Wind and Solar Integration Study

    SciTech Connect (OSTI)

    Jordan, G.; Venkataraman, S.

    2012-06-01

    The Western Wind and Solar Integration Study (WWSIS) examined the impact of up to 30% penetration of variable renewable generation on the Western Electricity Coordinating Council system. Although start-up costs and higher operating costs because of part-load operation of thermal generators were included in the analysis, further investigation of additional costs associated with thermal unit cycling was deemed worthwhile. These additional cycling costs can be attributed to increases in capital as well as operations and maintenance costs because of wear and tear associated with increased unit cycling. This analysis examines the additional cycling costs of the thermal fleet by leveraging the results of WWSIS Phase 1 study.

  18. Utility-Scale Solar 2014. An Empirical Analysis of Project Cost, Performance, and Pricing Trends in the United States

    SciTech Connect (OSTI)

    Bolinger, Mark; Seel, Joachim

    2015-09-01

    Other than the nine Solar Energy Generation Systems (“SEGS”) parabolic trough projects built in the 1980s, virtually no large-scale or “utility-scale” solar projects – defined here to include any groundmounted photovoltaic (“PV”), concentrating photovoltaic (“CPV”), or concentrating solar thermal power (“CSP”) project larger than 5 MWAC – existed in the United States prior to 2007. By 2012 – just five years later – utility-scale had become the largest sector of the overall PV market in the United States, a distinction that was repeated in both 2013 and 2014 and that is expected to continue for at least the next few years. Over this same short period, CSP also experienced a bit of a renaissance in the United States, with a number of large new parabolic trough and power tower systems – some including thermal storage – achieving commercial operation. With this critical mass of new utility-scale projects now online and in some cases having operated for a number of years (generating not only electricity, but also empirical data that can be mined), the rapidly growing utility-scale sector is ripe for analysis. This report, the third edition in an ongoing annual series, meets this need through in-depth, annually updated, data-driven analysis of not just installed project costs or prices – i.e., the traditional realm of solar economics analyses – but also operating costs, capacity factors, and power purchase agreement (“PPA”) prices from a large sample of utility-scale solar projects in the United States. Given its current dominance in the market, utility-scale PV also dominates much of this report, though data from CPV and CSP projects are presented where appropriate.

  19. Sustainable Investments Capital SI Capital | Open Energy Information

    Open Energy Info (EERE)

    Investments Capital SI Capital Jump to: navigation, search Name: Sustainable Investments Capital (SI Capital) Place: Barcelona, Spain Zip: 8021 Sector: Renewable Energy, Services...

  20. Mapping water availability, projected use and cost in the western United States

    SciTech Connect (OSTI)

    Vincent C. Tidwell; Barbara D. Moreland; Katie M. Zemlick; Barry L. Roberts; Howard D. Passell; Daniel Jensen; Christopher Forsgren; Gerald Sehlke; Margaret A. Cook; Carey W. King

    2014-06-01

    New demands for water can be satisfied through a variety of source options. In some basins surface and/or groundwater may be available through permitting with the state water management agency (termed unappropriated water), alternatively water might be purchased and transferred out of its current use to another (termed appropriated water), or non-traditional water sources can be captured and treated (e.g., wastewater). The relative availability and cost of each source are key factors in the development decision. Unfortunately, these measures are location dependent with no consistent or comparable set of data available for evaluating competing water sources. With the help of western water managers, water availability was mapped for over 1200 watersheds throughout the western US. Five water sources were individually examined, including unappropriated surface water, unappropriated groundwater, appropriated water, municipal wastewater and brackish groundwater. Also mapped was projected change in consumptive water use from 2010 to 2030. Associated costs to acquire, convey and treat the water, as necessary, for each of the five sources were estimated. These metrics were developed to support regional water planning and policy analysis with initial application to electric transmission planning in the western US.

  1. Reduced coated-tubing failures cut costs at Dickinson Heath Sand Unit

    SciTech Connect (OSTI)

    Brus, K.R. )

    1990-03-01

    In the Dickinson Heath Sand Unit waterflood, corrosion-related failures of coated injection tubing began accelerating in 1979 with the increased water production attributed to waterflood response. The trend peaked in 1984 when $164,000 was spent pulling failed tubing (34 workovers). Starting in 1983, the selection of coatings, coating-application-process quality control, and handling/installation procedures were examined, modified, and refined. The author discusses how these changes and improvements resulted in fewer pulling jobs and less money spent on associated workovers during 1988.

  2. 2011 Cost of Wind Energy Review

    SciTech Connect (OSTI)

    Tegen, S.; Lantz, E.; Hand, M.; Maples, B.; Smith, A.; Schwabe, P.

    2013-03-01

    This report describes the levelized cost of energy (LCOE) for a typical land-based wind turbine installed in the United States in 2011, as well as the modeled LCOE for a fixed-bottom offshore wind turbine installed in the United States in 2011. Each of the four major components of the LCOE equation are explained in detail, such as installed capital cost, annual energy production, annual operating expenses, and financing, and including sensitivity ranges that show how each component can affect LCOE. These LCOE calculations are used for planning and other purposes by the U.S. Department of Energy's Wind Program.

  3. Wind Technology, Cost, and Performance Trends in Denmark, Germany, Ireland, Norway, the European Union, and the United States: 2007 - 2012; NREL (National Renewable Energy Laboratory)

    SciTech Connect (OSTI)

    Hand, Maureen

    2015-06-15

    This presentation provides a summary of IEA Wind Task 26 report on Wind Technology, Cost, and Performance Trends in Denmark, Germany, Ireland, Norway, the European Union, and the United States: 2007-2012

  4. Venture Capital Finance

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Venture Capital Finance DOE Biomass Conference July 2014 Priced Out of Oil ... Into What? Energy Source Commodity Price Sun: $0 / GJ Oil (6.2 GJ/bbl) $10/bbl = $1.6 / GJ (late 1990s) Coal: $3 - 6 / GJ Natural Gas (N America) $3 - 4 / GJ Biomass (15 GJ/dt) $60-100/dt = $4 - 6 / GJ Natural Gas (ex N America) $10 - 15 / GJ Oil (6.2 GJ/bbl) $100/bbl = $16 / GJ Corn $4-7/bu= $10 - 20 / GJ 2 * Higher oil prices create a disruptive opportunity for lower cost feedstocks * North American shale gas is a

  5. Building a market for small wind: The break-even turnkey cost of residential wind systems in the United States

    SciTech Connect (OSTI)

    Edwards, Jennifer L.; Wiser, Ryan; Bolinger, Mark; Forsyth, Trudy

    2004-03-01

    Although small wind turbine technology and economics have improved in recent years, the small wind market in the United States continues to be driven in large part by state incentives, such as cash rebates, favorable loan programs, and tax credits. This paper examines the state-by-state economic attractiveness of small residential wind systems. Economic attractiveness is evaluated primarily using the break-even turnkey cost (BTC) of a residential wind system as the figure of merit. The BTC is defined here as the aggregate installed cost of a small wind system that could be supported such that the system owner would break even (and receive a specified return on investment) over the life of the turbine, taking into account current available incentives, the wind resource, and the retail electricity rate offset by on-site generation. Based on the analysis presented in this paper, we conclude that: (1) the economics of residential, grid-connected small wind systems is highly variable by state and wind resource class, (2) significant cost reductions will be necessary to stimulate widespread market acceptance absent significant changes in the level of policy support, and (3) a number of policies could help stimulate the market, but state cash incentives currently have the most significant impact, and will be a critical element of continued growth in this market.

  6. An Evaluation of the Total Cost of Ownership of Fuel Cell-Powered...

    Broader source: Energy.gov (indexed) [DOE]

    handling equipment, including the capital costs of battery and fuel cell systems, the cost of supporting infrastructure, maintenance costs, warehouse space costs, and labor costs. ...

  7. Capital Asset Project List.xls

    Broader source: Energy.gov (indexed) [DOE]

    as defined by DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets. CD0 Approve Mission Need CD1 Approve Alternative Selection and Cost Range CD2...

  8. How three smart managers control steam costs

    SciTech Connect (OSTI)

    Kendall, R.

    1982-11-01

    Three steam-intensive companies report innovative ways to reduce steam-production costs. Goodyear Tire and Rubber Co. concentrated on regular maintenance, process modifications, and heat recovery, but also has an on-going policy of seeking further cost savings. Future efforts will explore computer-based boiler controls. Zenith Radio Corporation's color picture tube-making process uses 12% less steam after 700 mechanical steam traps were replaced with fixed-orifice traps. Petro-Tex Chemical Corp. reduced steam costs by monitoring and optimizing process units and by making capital investments to improve steam management. (DCK)

  9. Beetle Capital Partners BCP | Open Energy Information

    Open Energy Info (EERE)

    Partners BCP Jump to: navigation, search Name: Beetle Capital Partners (BCP) Place: London, United Kingdom Zip: W1S 1UA Sector: Carbon Product: London-based asset management...

  10. Human Capital: The Role of Ombudsmen in Dispute Resolution

    Broader source: Energy.gov (indexed) [DOE]

    United States General Accounting Office GAO April 2001 HUMAN CAPITAL The Role of Ombudsmen ... Accounting Office GS General Schedule HR human resource IBB International Broadcasting ...

  11. Copy of Capitalized Property RO23_120213_1.xlsx

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capitalized Property 1 RO BARCODE DESCRIPTION MANUF. MODEL SN COST BLDG ROOM INVT_DATE 23 C5508 PRECISION ION POLISH GATAN INC 691 UNIT 427 01070301 $50,626.00 28 113 24-Sep-13 23 0000002116 TouchTable System TOUCHTABLE TT45 TT45S000378 $52,986.00 B03 134 19-Sep-13 23 0000002362 SYSTEM PUMP AMETEK Q AMETEK Q5000 CYL1A1308CYLIB1309CM $56,260.00 OFF TEXAS 11-Sep-12 23 0000000577 ANALYSIS SYSTEM BENC PFEIFFER GSD 301 C 44253789 $57,731.50 B25 115 30-Sep-13 23 0000002222 SLAVE NODES PSSC LABS PSSC

  12. Tracking the Sun IV: An Historical Summary of the Installed Cost of Photovoltaics in the United States from 1998 to 2010

    SciTech Connect (OSTI)

    Darghouth, Naim; Wiser, Ryan

    2011-09-07

    The present report describes installed cost trends for grid-connected PV projects installed from 1998 through 2010 (with some limited and preliminary results presented for projects installed in the first six months of 2011). The analysis is based on project-level cost data from approximately 116,500 residential, non-residential, and utility-sector PV systems in the United States. The inclusion of utility-sector PV is a new element in this year’s report. The combined capacity of all systems in the data sample totals 1,685 MW, equal to 79% of all grid-connected PV capacity installed in the United States through 2010 and representing one of the most comprehensive sources of installed PV cost data for the U.S. Based on this dataset, the report describes historical installed cost trends over time, and by location, market segment, technology type, and component. The report also briefly compares recent PV installed costs in the United States to those in Germany and Japan, and describes trends in customer incentives for PV installations and net installed costs after receipt of such incentives. The analysis presented here focuses on descriptive trends in the underlying data, serving primarily to summarize the data in tabular and graphical form.

  13. Report: EM Human Capital Initiatives

    Office of Environmental Management (EM)

    HUMAN CAPITAL September 25, 2008 Submitted by the EMAB Human Capital Subcommittee Background: The enhancement of the Office of Environmental Management's (EM) human capital has ...

  14. Greenworld Capital | Open Energy Information

    Open Energy Info (EERE)

    Greenworld Capital Jump to: navigation, search Name: Greenworld Capital Place: Pennsylvania Zip: 10000 Sector: Services Product: GreenWorld Capital provides investment banking...

  15. Greencore Capital | Open Energy Information

    Open Energy Info (EERE)

    Greencore Capital Jump to: navigation, search Name: Greencore Capital Place: San Diego, California Zip: 92121 Sector: Services Product: String representation "GreenCore Capit ... s...

  16. Yellowstone Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Logo: Yellowstone Capital Name: Yellowstone Capital Address: 5555 San Felipe, Suite 1650 Place: Houston, Texas Zip: 77056 Region: Texas Area...

  17. Nite Capital | Open Energy Information

    Open Energy Info (EERE)

    Nite Capital Jump to: navigation, search Name: Nite Capital Place: Libertyville, Illinois Zip: 60048 Product: Nite Capital provides private financing for small-cap and micro-cap...

  18. Greener Capital | Open Energy Information

    Open Energy Info (EERE)

    Greener Capital Jump to: navigation, search Name: Greener Capital Place: San Francisco, California Product: San Francisco-based clean technology VC. References: Greener Capital1...

  19. GGV Capital | Open Energy Information

    Open Energy Info (EERE)

    GGV Capital Jump to: navigation, search Name: GGV Capital Place: Menlo Park, California Zip: 94025 Product: String representation "GGV Capital" ... U.S. and China." is too...

  20. CMEA Capital | Open Energy Information

    Open Energy Info (EERE)

    CMEA Capital Jump to: navigation, search Logo: CMEA Capital Name: CMEA Capital Address: 1 Embarcadero Center Place: San Francisco, California Zip: 94111 Region: Bay Area Number of...

  1. Clarey Capital | Open Energy Information

    Open Energy Info (EERE)

    Clarey Capital Jump to: navigation, search Name: Clarey Capital Place: Irvine, California Zip: 92617 Sector: Renewable Energy Product: String representation "Clarey Capital ... of...

  2. BEV Capital | Open Energy Information

    Open Energy Info (EERE)

    BEV Capital Jump to: navigation, search Logo: BEV Capital Name: BEV Capital Address: 263 Tresser Blvd., 9th Floor Place: Stamford, Connecticut Zip: 06901 Region: Northeast - NY NJ...

  3. Infield Capital | Open Energy Information

    Open Energy Info (EERE)

    Infield Capital Jump to: navigation, search Name: Infield Capital Place: Boulder, Colorado Product: Infield Capital was founded in 2008, and is focused on investment in early-stage...

  4. Greenview Capital | Open Energy Information

    Open Energy Info (EERE)

    Greenview Capital Jump to: navigation, search Name: Greenview Capital Place: Libertyville, Illinois Zip: 60048 Product: Greenview Capital is a U.S. based consulting firm and...

  5. Earthrise Capital | Open Energy Information

    Open Energy Info (EERE)

    Earthrise Capital Jump to: navigation, search Logo: Earthrise Capital Name: Earthrise Capital Address: 45 Rockefeller Plaza, 20th Floor Place: New York, New York Zip: 10111 Region:...

  6. Atrium Capital | Open Energy Information

    Open Energy Info (EERE)

    Atrium Capital Jump to: navigation, search Logo: Atrium Capital Name: Atrium Capital Address: 3000 Sand Hill Road, Building 2, Suite 240 Place: Menlo Park, California Zip: 94025...

  7. Commons Capital | Open Energy Information

    Open Energy Info (EERE)

    Commons Capital Jump to: navigation, search Logo: Commons Capital Name: Commons Capital Address: 320 Washington Street, 4th floor Place: Brookline, Massachusetts Zip: 02445 Region:...

  8. IEA Wind Task 26. Wind Technology, Cost, and Performance Trends in Denmark, Germany, Ireland, Norway, the European Union, and the United States: 2007–2012

    SciTech Connect (OSTI)

    Vitina, Aisma; Lüers, Silke; Wallasch, Anna-Kathrin; Berkhout, Volker; Duffy, Aidan; Cleary, Brendan; Husabø, Lief I.; Weir, David E.; Lacal-Arántegui, Roberto; Hand, Maureen; Lantz, Eric; Belyeu, Kathy; Wiser, Ryan H; Bolinger, Mark; Hoen, Ben

    2015-06-01

    The International Energy Agency Implementing Agreement for cooperation in Research, Development, and Deployment of Wind Energy Systems (IEA Wind) Task 26—The Cost of Wind Energy represents an international collaboration dedicated to exploring past, present and future cost of wind energy. This report provides an overview of recent trends in wind plant technology, cost, and performance in those countries that are currently represented by participating organizations in IEA Wind Task 26: Denmark, Germany, Ireland, Norway, and the United States as well as the European Union.

  9. An examination of the costs and critical characteristics of electric utility distribution system capacity enhancement projects

    SciTech Connect (OSTI)

    Balducci, Patrick J.; Schienbein, Lawrence A.; Nguyen, Tony B.; Brown, Daryl R.; Fathelrahman, Eihab M.

    2004-06-01

    This report classifies and analyzes the capital and total costs (e.g., income tax, property tax, depreciation, centralized power generation, insurance premiums, and capital financing) associated with 130 electricity distribution system capacity enhancement projects undertaken during 1995-2002 or planned in the 2003-2011 time period by three electric power utilities operating in the Pacific Northwest. The Pacific Northwest National Laboratory (PNNL), in cooperation with participating utilities, has developed a large database of over 3,000 distribution system projects. The database includes brief project descriptions, capital cost estimates, the stated need for each project, and engineering data. The database was augmented by additional technical (e.g., line loss, existing substation capacities, and forecast peak demand for power in the area served by each project), cost (e.g., operations, maintenance, and centralized power generation costs), and financial (e.g., cost of capital, insurance premiums, depreciations, and tax rates) data. Though there are roughly 3,000 projects in the database, the vast majority were not included in this analysis because they either did not clearly enhance capacity or more information was needed, and not available, to adequately conduct the cost analyses. For the 130 projects identified for this analysis, capital cost frequency distributions were constructed, and expressed in terms of dollars per kVA of additional capacity. The capital cost frequency distributions identify how the projects contained within the database are distributed across a broad cost spectrum. Furthermore, the PNNL Energy Cost Analysis Model (ECAM) was used to determine the full costs (e.g., capital, operations and maintenance, property tax, income tax, depreciation, centralized power generation costs, insurance premiums and capital financing) associated with delivering electricity to customers, once again expressed in terms of costs per kVA of additional capacity

  10. Heliostat cost reduction study.

    SciTech Connect (OSTI)

    Jones, Scott A.; Lumia, Ronald. (University of New Mexico, Albuquerque, NM); Davenport, Roger (Science Applications International Corporation, San Diego, CA); Thomas, Robert C. (Advanced Thermal Systems, Centennial, CO); Gorman, David; Kolb, Gregory J.; Donnelly, Matthew W.

    2007-06-01

    Power towers are capable of producing solar-generated electricity and hydrogen on a large scale. Heliostats are the most important cost element of a solar power tower plant. Since they constitute {approx} 50% of the capital cost of the plant it is important to reduce heliostat cost as much as possible to improve the economic performance of power towers. In this study we evaluate current heliostat technology and estimate a price of $126/m{sup 2} given year-2006 materials and labor costs for a deployment of {approx}600 MW of power towers per year. This 2006 price yields electricity at $0.067/kWh and hydrogen at $3.20/kg. We propose research and development that should ultimately lead to a price as low as $90/m{sup 2}, which equates to $0.056/kWh and $2.75/kg H{sup 2}. Approximately 30 heliostat and manufacturing experts from the United States, Europe, and Australia contributed to the content of this report during two separate workshops conducted at the National Solar Thermal Test Facility.

  11. NREL Analysis: Cost-Effective and Reliable Integration of High-Penetration Solar in the Western United States (Poster)

    SciTech Connect (OSTI)

    Lew, D.; Brinkman, G.; Ibanez, E.; Hodge, B.; Lefton, S.; Kumar, N.; Agan, D.; Jordan, G.; Venkatataman, S.

    2012-07-01

    SunShot Initiative awardee posters describing the different technologies within the four subprograms of the DOE Solar Program (Photovoltaics, Concentrating Solar Power, Soft Costs, and Systems Integration).

  12. Cost-Effectiveness of Home Energy Retrofits in Pre-Code Vintage Homes in the United States

    SciTech Connect (OSTI)

    Fairey, P.; Parker, D.

    2012-11-01

    This analytical study examines the opportunities for cost-effective energy efficiency and renewable energy retrofits in residential archetypes constructed prior to 1980 (Pre-Code) in fourteen U.S. cities. These fourteen cities are representative of each of the International Energy Conservation Code (IECC) climate zones in the contiguous U.S. The analysis is conducted using an in-house version of EnergyGauge USA v.2.8.05 named CostOpt that has been programmed to perform iterative, incremental economic optimization on a large list of residential energy efficiency and renewable energy retrofit measures. The principle objectives of the study are as follows: to determine the opportunities for cost effective source energy reductions in this large cohort of existing residential building stock as a function of local climate and energy costs; and to examine how retrofit financing alternatives impact the source energy reductions that are cost effectively achievable.

  13. PAFC Cost Challenges

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    PAFC Cost Challenges Sridhar Kanuri Manager, PAFC Technology *Sridhar.Kanuri@utcpower.com 2 AGENDA Purecell® 400 cost challenge Cost reduction opportunities Summary 3 PURECELL ® FUEL CELL SYSTEM First cost 2010 cost reduction is being accomplished by incremental changes in technology & low cost sourcing Technology advances are required to reduce further cost and attain UTC Power's commercialization targets 2010 First unit 2010 Last unit Commercialization target Powerplant cost 4

  14. Solar Access to Public Capital | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Solar Access to Public Capital Solar Access to Public Capital The Solar Access to Public Capital (SAPC) working group has developed standard residential lease and commercial power purchase agreement (PPA) contracts available for use by solar developers, customers, and third-party finance providers. These documents are designed to improve consumer transparency, reduce transaction costs in the solar asset contracting process, and facilitate the pooling of associated cash flows so that they may be

  15. Energy Department Report Calculates Emissions and Costs of Power...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    does not consider other factors such as capital costs of construction for wind, solar, fossil-fueled power plants, or transmission. These costs are significant, but outside the...

  16. PROJECT PROFILE: Promotion of PV Soft Cost Reductions in the Southeastern United States (SuNLaMP)

    Broader source: Energy.gov [DOE]

    This project creates a replicable model for solar photovoltaic (PV) soft cost reduction in South Carolina through human capacity-building at the local level and direct efforts to harmonize policy at the inter-county or regional level. This effort will close the gap between South Carolina installed costs of residential rooftop solar and national averages and develop a portable and replicable model that can be applied to other jurisdictions in the future.

  17. Capital Project Prioritization

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capital-Project-Prioritization Sign In About | Careers | Contact | Investors | bpa.gov Search News & Us Expand News & Us Projects & Initiatives Expand Projects &...

  18. CAPITAL PROJECT PROPOSAL

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Non-Discretionary, please provide explanation: 07 Approval for: Ongoing Program 08 Investment Type: Capital Replacement 09 Emergency? YES NO 09A If "YES", please provide...

  19. Utility-Scale Solar 2013: An Empirical Analysis of Project Cost, Performance, and Pricing Trends in the United States

    Office of Energy Efficiency and Renewable Energy (EERE)

    Other than the SEGS I-IX parabolic trough projects built in the 1980s, virtually no large-scale or "utility-scale" solar projects existed in the United States prior to 2007. By 2012 – just five years later – utility-scale had become the largest sector of the overall PV market in the United States, a distinction that was repeated in 2013 and is expected to continue for at least the next few years.

  20. Human Capital - DOE Directives, Delegations, and Requirements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Human Capital by Website Administrator Back

  1. 2015-09-25 Capital Asset Project List.xls

    Broader source: Energy.gov (indexed) [DOE]

    as defined by DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets. CD-0 Approve Mission Need CD-1 Approve Alternative Selection and Cost Range...

  2. BG Capital | Open Energy Information

    Open Energy Info (EERE)

    BG Capital Jump to: navigation, search Name: BG-Capital Place: Spain Zip: 8860 Product: BG-capital designs, installs and invests in PV medium scale (100-500kW) systems,...

  3. Life cycle cost study for coated conductor manufacture by metal organic chemical vapor deposition

    SciTech Connect (OSTI)

    Chapman, J.N.

    1999-07-13

    The purpose of this report is to calculate the cost of producing high temperature superconducting wire by the Metal Organic Chemical Vapor Deposition (MOCVD) process. The technology status is reviewed from the literature and a plant conceptual design is assumed for the cost calculation. The critical issues discussed are the high cost of the metal organic precursors, the material utilization efficiency and the capability of the final product as measured by the critical current density achieved. Capital, operating and material costs are estimated and summed as the basis for calculating the cost per unit length of wire. Sensitivity analyses of key assumptions are examined to determine their effects on the final wire cost. Additionally, the cost of wire on the basis of cost per kiloampere per meter is calculated for operation at lower temperatures than the liquid nitrogen boiling temperature. It is concluded that this process should not be ruled out on the basis of high cost of precursors alone.

  4. The Status of Clean Energy in the United States

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    The Status of Clean Energy in the United States Tribal Energy Program Review May 6, 2015 Travis Lowder, NREL 2 Lazard's Levelized Cost of Energy (LCOE) Estimates Source: Lazard 2013 3 Lazard's Capital Cost Estimates Source: Lazard 2013 4 EIA Estimates (2012 data) 5 Solar PV 6 Solar PV Installed Capacity and Weighted Average System Cost $0 $2 $4 $6 $8 $10 $12 0 1000 2000 3000 4000 5000 6000 7000 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 Wtd. Avg. System Price ($/W)

  5. Arborview Capital | Open Energy Information

    Open Energy Info (EERE)

    Arborview Capital Jump to: navigation, search Name: Arborview Capital Place: Chevy Chase, Maryland Zip: 20815 Product: Maryland-based private equity firm that provides growth...

  6. Greenrock Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Greenrock Capital Place: San Francisco, California Zip: 94111 Sector: Renewable Energy Product: San Francisco-based, investment firm....

  7. Dragonfly Capital | Open Energy Information

    Open Energy Info (EERE)

    Dragonfly Capital Jump to: navigation, search Name: Dragonfly Capital Place: Charlotte, North Carolina Zip: 28203 Sector: Renewable Energy, Services Product: Charlotte-based...

  8. Renewable Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Renewable Capital Place: Las Vegas, Nevada Zip: 89109 Sector: Solar Product: Investment vehicle of Ed Stevenson, founder of Solar...

  9. Cascadia Capital | Open Energy Information

    Open Energy Info (EERE)

    Cascadia Capital Jump to: navigation, search Name: Cascadia Capital Address: 701 Fifth Avenue Place: Seattle, Washington Zip: 98104 Region: Pacific Northwest Area Product:...

  10. Peony Capital | Open Energy Information

    Open Energy Info (EERE)

    Peony Capital Jump to: navigation, search Name: Peony Capital Place: Dongcheng District Beijing, Beijing Municipality, China Zip: 100027 Product: Manages a fund dedicated to...

  11. Capital Point | Open Energy Information

    Open Energy Info (EERE)

    Point Jump to: navigation, search Name: Capital Point Place: Israel Sector: Services Product: General Financial & Legal Services ( Joint Venture Consortium ) References: Capital...

  12. Workplace Charging Challenge Partner: Capital One Financial Corporatio...

    Energy Savers [EERE]

    As of early 2014, Capital One has installed 60 Level 2 plug-in electric vehicle (PEV) charging units at five company sites. These charging stations support associates who purchase ...

  13. Final project report - CRADA with United Solar Technologies and Pacific Northwest Laboratory (PNL-021): Thin film materials for low-cost high performance solar concentrators

    SciTech Connect (OSTI)

    Martin, P.M.; Affinito, J.D.; Gross, M.E.; Bennett, W.D.

    1995-03-01

    The objectives of this project were as follows: To develop and evaluate promising low-cost dielectric and polymer-protected thin-film reflective metal coatings to be applied to preformed continuously-curved solar reflector panels to enhance their solar reflectance, and to demonstrate protected solar reflective coatings on preformed solar concentrator panels. The opportunity for this project arose from a search by United Solar Technologies (UST) for organizations and facilities capable of applying reflective coatings to large preformed panels. PNL was identified as being uniquely qualified to participate in this collaborative project.

  14. Activity Based Costing

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Activity Based Costing (ABC) is method for developing cost estimates in which the project is subdivided into discrete, quantifiable activities or a work unit. This chapter outlines the Activity Based Costing method and discusses applicable uses of ABC.

  15. Capital intensity of photovoltaics manufacturing: Barrier to scale and opportunity for innovation

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Powell, Douglas M.; Fu, Ran; Horowitz, Kelsey; Basore, Paul A.; Woodhouse, Michael; Buonassisi, Tonio

    2015-09-07

    In this study, using a bottom-up cost model, we assess the impact of initial factory capital expenditure (capex) on photovoltaic (PV) module minimum sustainable price (MSP) and industry-wide trends. We find capex to have two important impacts on PV manufacturing. First, capex strongly influences the per-unit MSP of a c-Si module: we calculate that the capex-related elements sum to 22% of MSP for an integrated wafer, cell, and module manufacturer. This fraction provides a significant opportunity to reduce MSP toward the U.S. DOE SunShot module price target through capex innovation.

  16. Capital Reporting Company Quadrennial ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... The war on poverty, which was 20 initiated with very dramatics walks from 21 Appalachia ... 07-21-2014 (866) 448 - DEPO www.CapitalReportingCompany.com 2014 44 1 poverty there. ...

  17. Capital Reporting Company Quadrennial ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ...CapitalReportingCompany.com 2014 120 1 how to adapt to the new oil which is, in New 2 Mexico, a sweet API 40, essentially similar to the 3 North Dakota oil. We have a sweet oil. ...

  18. Capital Project Authorization

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    This policy applies to capital projects in these asset categories: 1. Transmission investment in assets owned or leased by BPA, whether funded by bonds issued to the U.S....

  19. CHARACTERIZING COSTS, SAVINGS AND BENEFITS OF A SELECTION OF ENERGY EFFICIENT EMERGING TECHNOLOGIES IN THE UNITED STATES

    SciTech Connect (OSTI)

    Xu, T.; Slaa, J.W.; Sathaye, J.

    2010-12-15

    Implementation and adoption of efficient end-use technologies have proven to be one of the key measures for reducing greenhouse gas (GHG) emissions throughout the industries. In many cases, implementing energy efficiency measures is among one of the most cost effective investments that the industry could make in improving efficiency and productivity while reducing CO2 emissions. Over the years, there have been incentives to use resources and energy in a cleaner and more efficient way to create industries that are sustainable and more productive. With the working of energy programs and policies on GHG inventory and regulation, understanding and managing the costs associated with mitigation measures for GHG reductions is very important for the industry and policy makers around the world. Successful implementation of emerging technologies not only can help advance productivities and competitiveness but also can play a significant role in mitigation efforts by saving energy. Providing evaluation and estimation of the costs and energy savings potential of emerging technologies is the focus of our work in this project. The overall goal of the project is to identify and select emerging and under-utilized energy-efficient technologies and practices as they are important to reduce energy consumption in industry while maintaining economic growth. This report contains the results from performing Task 2"Technology evaluation" for the project titled"Research Opportunities in Emerging and Under-Utilized Energy-Efficient Industrial Technologies," which was sponsored by California Energy Commission and managed by CIEE. The project purpose is to analyze market status, market potential, and economic viability of selected technologies applicable to the U.S. In this report, LBNL first performed re-assessments of all of the 33 emerging energy-efficient industrial technologies, including re-evaluation of the 26 technologies that were previously identified by Martin et al. (2000) and

  20. Wind energy`s declining costs

    SciTech Connect (OSTI)

    Gipe, P.

    1995-11-01

    Wind energy is competitive with traditional energy sources for the first time since European windmills graced the landscapes of the Old World. This article explores the current economics of wind power. Topics discussed include the following: standardizing cost of energy reporting and the cost of wind energy; wind power plant price; maintenance costs; effect of installed cost on the cost of energy; future costs; decommissioning; modularity; social or environmental costs; cost of capital; bidding and price.

  1. ASPEN costing manual

    SciTech Connect (OSTI)

    Schwint, K.J.

    1986-07-25

    The ASPEN program contains within it a Cost Estimation System (CES) which estimates the purchase cost and utility consumption rates for major pieces of equipment in a process flowsheet as well as installed equipment costs. These estimates are ''preliminary-study grade'' with an accuracy of plus or minus 30%. The ASPEN program also contains within it an Economic Evaluation System (EES) which estimates overall capital investment costs, annual operating expenses and profitability indices for a chemical plant. This ASPEN costing manual has been written as a guide for those inexperienced in the use of ASPEN and unfamiliar with standard cost estimating techniques who want to use the ASPEN CES and EES. The ASPEN Costing Manual is comprised of the following sections: (1) Introduction, (2) ASPEN Input Language, (3) ASPEN Cost Estimation System (CES), (4) ASPEN Cost Blocks; and (5) ASPEN Economic Evaluation System (EES).

  2. Manufacturing Cost Levelization Model – A User’s Guide

    SciTech Connect (OSTI)

    Morrow, William R.; Shehabi, Arman; Smith, Sarah Josephine

    2015-08-01

    The Manufacturing Cost Levelization Model is a cost-performance techno-economic model that estimates total large-scale manufacturing costs for necessary to produce a given product. It is designed to provide production cost estimates for technology researchers to help guide technology research and development towards an eventual cost-effective product. The model presented in this user’s guide is generic and can be tailored to the manufacturing of any product, including the generation of electricity (as a product). This flexibility, however, requires the user to develop the processes and process efficiencies that represents a full-scale manufacturing facility. The generic model is comprised of several modules that estimate variable costs (material, labor, and operating), fixed costs (capital & maintenance), financing structures (debt and equity financing), and tax implications (taxable income after equipment and building depreciation, debt interest payments, and expenses) of a notional manufacturing plant. A cash-flow method is used to estimate a selling price necessary for the manufacturing plant to recover its total cost of production. A levelized unit sales price ($ per unit of product) is determined by dividing the net-present value of the manufacturing plant’s expenses ($) by the net present value of its product output. A user defined production schedule drives the cash-flow method that determines the levelized unit price. In addition, an analyst can increase the levelized unit price to include a gross profit margin to estimate a product sales price. This model allows an analyst to understand the effect that any input variables could have on the cost of manufacturing a product. In addition, the tool is able to perform sensitivity analysis, which can be used to identify the key variables and assumptions that have the greatest influence on the levelized costs. This component is intended to help technology researchers focus their research attention on tasks

  3. Walnut Capital Acquisitions | Open Energy Information

    Open Energy Info (EERE)

    Walnut Capital Acquisitions Jump to: navigation, search Name: Walnut Capital Acquisitions Place: Pittsburgh, Pennsylvania Zip: 15232 Product: Walnut Capital Acquisitions is the...

  4. American Wind Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: American Wind Capital Place: Essex, Connecticut Zip: 64260 Sector: Wind energy Product: Connecticut-based American Wind Capital buys wind...

  5. Sustainable Technology Capital, LP | Open Energy Information

    Open Energy Info (EERE)

    Capital, LP Jump to: navigation, search Logo: Sustainable Technology Capital, LP Name: Sustainable Technology Capital, LP Address: 625 Liberty Ave., Suite 3200 Place: Pittsburgh,...

  6. Long Branch Capital | Open Energy Information

    Open Energy Info (EERE)

    Branch Capital Jump to: navigation, search Name: Long Branch Capital Place: Austin, Texas Zip: 78744 Sector: Efficiency, Renewable Energy Product: Long Branch Capital makes...

  7. Tonga Capital Corporation | Open Energy Information

    Open Energy Info (EERE)

    Tonga Capital Corporation Jump to: navigation, search Name: Tonga Capital Corporation Place: Arvada, Colorado Sector: Biofuels Product: Capital pool company, which ran out of...

  8. Hereford Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Hereford Capital Advisors Jump to: navigation, search Name: Hereford Capital Advisors Place: Denver, Colorado Product: US-based firm offering PV project management and capital...

  9. Prospect Capital Corporation | Open Energy Information

    Open Energy Info (EERE)

    Prospect Capital Corporation Jump to: navigation, search Logo: Prospect Capital Corporation Name: Prospect Capital Corporation Address: 10 East 40th Street, 44th Floor Place: New...

  10. Energy Capital Solutions | Open Energy Information

    Open Energy Info (EERE)

    Capital Solutions Jump to: navigation, search Logo: Energy Capital Solutions Name: Energy Capital Solutions Address: 2651 North Harwood Street, Suite 410 Place: Dallas, Texas Zip:...

  11. KRK Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    KRK Capital Partners Jump to: navigation, search Name: KRK Capital Partners Place: Washington DC, Washington, DC Zip: 20002 Product: String representation "KRK Capital Par ......

  12. Chrysalix Energy Venture Capital | Open Energy Information

    Open Energy Info (EERE)

    Chrysalix Energy Venture Capital Jump to: navigation, search Logo: Chrysalix Energy Venture Capital Name: Chrysalix Energy Venture Capital Address: 1367 West Broadway, Suite 400...

  13. New Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Logo: New Energy Capital Name: New Energy Capital Address: 53 South Main Street, Third Floor Place: Hanover, New Hampshire Zip: 03755 Product:...

  14. Applied Intellectual Capital AIC | Open Energy Information

    Open Energy Info (EERE)

    Intellectual Capital AIC Jump to: navigation, search Name: Applied Intellectual Capital (AIC) Place: California Zip: 94501-1010 Product: Applied Intellectual Capital (AIC) was...

  15. Booner Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Booner Capital LLC Jump to: navigation, search Name: Booner Capital LLC Place: Florida Sector: Wind energy Product: Booner Capital LLC is PE investor in wind power companies....

  16. Chestnut Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital LLC Jump to: navigation, search Name: Chestnut Capital LLC Place: West Newton, Massachusetts Zip: 2465 Sector: Wind energy Product: Chestnut Capital is a wind energy...

  17. Cora Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Cora Capital Advisors Jump to: navigation, search Logo: Cora Capital Advisors Name: Cora Capital Advisors Address: 445 Park Avenue, 9th Floor Place: New York Zip: 10022 Region:...

  18. Development of surface mine cost estimating equations

    SciTech Connect (OSTI)

    Not Available

    1980-09-26

    Cost estimating equations were developed to determine capital and operating costs for five surface coal mine models in Central Appalachia, Northern Appalachia, Mid-West, Far-West, and Campbell County, Wyoming. Engineering equations were used to estimate equipment costs for the stripping function and for the coal loading and hauling function for the base case mine and for several mines with different annual production levels and/or different overburden removal requirements. Deferred costs were then determined through application of the base case depreciation schedules, and direct labor costs were easily established once the equipment quantities (and, hence, manpower requirements) were determined. The data points were then fit with appropriate functional forms, and these were then multiplied by appropriate adjustment factors so that the resulting equations yielded the model mine costs for initial and deferred capital and annual operating cost. (The validity of this scaling process is based on the assumption that total initial and deferred capital costs are proportional to the initial and deferred costs for the primary equipment types that were considered and that annual operating cost is proportional to the direct labor costs that were determined based on primary equipment quantities.) Initial capital costs ranged from $3,910,470 in Central Appalachia to $49,296,785; deferred capital costs ranged from $3,220,000 in Central Appalachia to $30,735,000 in Campbell County, Wyoming; and annual operating costs ranged from $2,924,148 in Central Appalachia to $32,708,591 in Campbell County, Wyoming. (DMC)

  19. US nuclear power plant operating cost and experience summaries

    SciTech Connect (OSTI)

    Kohn, W.E.; Reid, R.L.; White, V.S.

    1998-02-01

    NUREG/CR-6577, U.S. Nuclear Power Plant Operating Cost and Experience Summaries, has been prepared to provide historical operating cost and experience information on U.S. commercial nuclear power plants. Cost incurred after initial construction are characterized as annual production costs, representing fuel and plant operating and maintenance expenses, and capital expenditures related to facility additions/modifications which are included in the plant capital asset base. As discussed in the report, annual data for these two cost categories were obtained from publicly available reports and must be accepted as having different degrees of accuracy and completeness. Treatment of inconclusive and incomplete data is discussed. As an aid to understanding the fluctuations in the cost histories, operating summaries for each nuclear unit are provided. The intent of these summaries is to identify important operating events; refueling, major maintenance, and other significant outages; operating milestones; and significant licensing or enforcement actions. Information used in the summaries is condensed from annual operating reports submitted by the licensees, plant histories contained in Nuclear Power Experience, trade press articles, and the Nuclear Regulatory Commission (NRC) web site (www.nrc.gov).

  20. Survey Results and Analysis of the Cost and Efficiency of Various Operating Hydrogen Fueling Stations

    SciTech Connect (OSTI)

    Cornish, John

    2011-03-05

    Existing Hydrogen Fueling Stations were surveyed to determine capital and operational costs. Recommendations for cost reduction in future stations and for research were developed.

  1. Ardour Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Ardour Capital Investments LLC Address: 350 5th ave Place: New York, New York Zip: 10118 Region: Northeast - NY NJ CT PA Area Number of...

  2. Greentech Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Place: Sao Paulo, Sao Paulo, Brazil Zip: 04536-001 Product: Brazilian investment group. References: Greentech Capital1 This article is a stub. You can help OpenEI...

  3. Best Practices for Net Zero Energy Cost Control

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    teams, which are key parties that influence construction capital cost. ... http:www1.eere.energy.govbuildingsalliancesmedia20111031webinarcontrollingcosts.wmv * Energy ...

  4. Replacement Cost of Domestic Crude

    Energy Science and Technology Software Center (OSTI)

    1994-12-01

    The DEEPWATER model forecasts the replacement cost of domestic crude oil for 13 offshore regions in the lower 48 states. The replacement cost of domestic crude oil is the constant or levelized selling price that will recover the full expense of exploration, development, and productions with a reasonable return on capital.

  5. Natural Capital Management: An Evolutionary Paradigm for Sustainable Restoration Investment - 13455

    SciTech Connect (OSTI)

    Koetz, Maureen T.

    2013-07-01

    Unlike other forms of capital assets (built infrastructure, labor, financial capital), the supply of usable or accessible air, land, and water elements (termed Natural Capital Assets or NCA) available to enterprise processes is structurally shrinking due to increased demand and regulatory restriction. This supply/demand imbalance is affecting all forms of public and private enterprise (including Federal Facilities) in the form of encroachment, production limits, cost increases, and reduced competitiveness. Department of Energy (DOE) sites are comprised of significant stocks of NCA that function as both conserved capital (providing ecosystem services and other reserve capacity), and as natural infrastructure (supporting major Federal enterprise programs). The current rubric of 'Environmental Stewardship' provides an unduly constrained management paradigm that is focused largely on compliance process metrics, and lacks a value platform for quantifying, documenting, and sustainably re-deploying re-capitalized natural asset capacity and capability. By adopting value-based system concepts similar to built infrastructure accounting and information management, 'stewarded' natural assets relegated to liability- or compliance-focused outcomes become 're-capitalized' operational assets able to support new or expanded mission. This growing need for new accounting and management paradigms to capture natural capital value is achieving global recognition, most recently by the United Nations, world leaders, and international corporations at the Rio+20 Summit in June of 2012. Natural Capital Asset Management (NCAM){sup TM} is such an accounting framework tool. Using a quantification-based design, NCAM{sup TM} provides inventory, capacity and value data to owners or managers of natural assets such as the DOE that parallel comparable information systems currently used for facility assets. Applied to Environmental Management (EM) and other DOE program activities, the natural asset

  6. Swiftsure Capital | Open Energy Information

    Open Energy Info (EERE)

    Place: San Francisco, California Product: Swiftsure Capital, US-based private investment corporation focusing on the financing of early-stage businesses in the software,...

  7. Principal Associate Director - Capital Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    As Principal Associate Director for Capital Projects (interim), Larry Simmons is responsible for institutional large-project construction and management and environmental cleanup ...

  8. Financing U.S. Renewable Energy Projects Through Public Capital Vehicles: Qualitative and Quantitative Benefits

    SciTech Connect (OSTI)

    Mendelsohn, M.; Feldman, D.

    2013-04-01

    This paper explores the possibility of financing renewable energy projects through raising capital in the public markets. It gives an overview of the size, structure, and benefits of public capital markets, as well as showing how renewable energy projects might take advantage of this source of new funds to lower the cost of electricity.

  9. Analysis of the applicability and probable cost effectiveness of advancing longwall-mining systems in the United States. Final technical report. [Advance vs retreat

    SciTech Connect (OSTI)

    Hill, F.E.; Peake, C.V.; Sharkey, A.

    1981-07-01

    In the first phase of this study it was concluded that there are a number of advancing longwall systems that might well be applicable in the United States and, furthermore, meet the health and safety requirements of MSHA, state inspectors, operating management, and unions. Comparative analyses showed that only two of the advancing-type systems evaluated in the Phase I report failed to approach or better, economically, the typical retreating method in at least some conditions; the others appeared to warrant further attention. And if the mining plan could be worked out to allow for a switch from advancing to retreating after the early years of mining, then almost any combination of advancing and retreating would provide a better return on investment, or in our terms, have a higher net present value than would a typical retreating system. The reason for this lies in the higher initial production rates of the advancing systems and in the lower operating cost and higher ultimate productivity of a retreating system once it is established. After analyzing the advantages and disadvantages of the various advancing longwall systems for a trial program it became apparent that the modified Z System offered the best combination of economic potential and lack of conflict with US mining laws. The major attraction of the modified Z system is that it provides separate roadways to the face for intake air, exhaust air and a beltway. Thus regulatory approval of the ventilation system should not be a major obstacle. The Kaiser Steel Corporation agreed to cooperate with the development of a specification for a trial of the system at its Sunnyside Mine in Utah. The specification was developed for one longwall face to mine a series of panels at Sunnyside.

  10. Levelized Power Generation Cost Codes

    Energy Science and Technology Software Center (OSTI)

    1996-04-30

    LPGC is a set of nine microcomputer programs for estimating power generation costs for large steam-electric power plants. These programs permit rapid evaluation using various sets of economic and technical ground rules. The levelized power generation costs calculated may be used to compare the relative economics of nuclear and coal-fired plants based on life-cycle costs. Cost calculations include capital investment cost, operation and maintenance cost, fuel cycle cost, decommissioning cost, and total levelized power generationmore » cost. These programs can be used for quick analyses of power generation costs using alternative economic parameters, such as interest rate, escalation rate, inflation rate, plant lead times, capacity factor, fuel prices, etc. The two major types of electric generating plants considered are pressurized water reactor (PWR) and pulverized coal-fired plants. Data are also provided for the Large Scale Prototype Breeder (LSPB) type liquid metal reactor.« less

  11. EA-355 Scotia Capital Energy, Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    5 Scotia Capital Energy, Inc. EA-355 Scotia Capital Energy, Inc. Order authorizing Scotia Capital Energy, Inc. to export electric energy to Canada EA-355 Scotia Capital Energy, ...

  12. Hydrogen Production Cost Estimate Using Biomass Gasification: Independent Review

    Office of Energy Efficiency and Renewable Energy (EERE)

    This independent review report assesses the 2009 state-of-the-art and 2020 projected capital cost, energy efficiency, and levelized cost for hydrogen production from biomass via gasification.

  13. Human Capital Management Accountability Program

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-08-01

    The Order establishes requirements, roles and responsibilities for the Human Capital Management Accountability Program (HCMAP) for human resources programs and personnel and ensures that human capital activities are regulatory and procedurally compliant with Federal statutes and Departmental policies. Does not cancel other directives.

  14. Where might I find simplified Data on Capital, O&M, and fuel...

    Open Energy Info (EERE)

    Where might I find simplified Data on Capital, O&M, and fuel costs? Home I teach math to high school seniors. My students are studying energy in all their classes. I have just...

  15. Mont Vista Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Vista Capital LLC Jump to: navigation, search Name: Mont Vista Capital LLC Place: New York, New York Zip: 10167 Sector: Services Product: Mont Vista Capital is a leading global...

  16. EnerTech Capital | Open Energy Information

    Open Energy Info (EERE)

    EnerTech Capital Jump to: navigation, search Logo: EnerTech Capital Name: EnerTech Capital Address: 625 W. Ridge Pike, Building D, Suite 105 Place: Conshohocken, Pennsylvania Zip:...

  17. GreenCore Capital | Open Energy Information

    Open Energy Info (EERE)

    GreenCore Capital Jump to: navigation, search Logo: GreenCore Capital Name: GreenCore Capital Address: 10509 Vista Sorrento Parkway Place: San Diego, California Zip: 92121 Region:...

  18. EarthRise Capital | Open Energy Information

    Open Energy Info (EERE)

    EarthRise Capital Jump to: navigation, search Name: EarthRise Capital Place: New York, New York Zip: NY 10111 Sector: Efficiency Product: Venture capital fund focused on new...

  19. Ethanol Capital Funding | Open Energy Information

    Open Energy Info (EERE)

    Ethanol Capital Funding Jump to: navigation, search Name: Ethanol Capital Funding Place: Atlanta, Georgia Zip: 30328 Product: Provides funding for ethanol and biodiesel plants....

  20. Atlantic Ethanol Capital | Open Energy Information

    Open Energy Info (EERE)

    Ethanol Capital Jump to: navigation, search Name: Atlantic Ethanol Capital Place: Washington, Washington, DC Product: Biofuel Investor in Caribbean and Central American region....

  1. Carbon Credit Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Carbon Credit Capital Place: New York, New York Zip: 10012 Sector: Carbon, Services Product: Project Advisory Services and Carbon...

  2. Capital Energy Offshore | Open Energy Information

    Open Energy Info (EERE)

    Sector: Wind energy Product: JV between Gamesa and Capital Energy to develop offshore wind farms References: Capital Energy Offshore1 This article is a stub. You can help...

  3. Marathon Capital LLC (California) | Open Energy Information

    Open Energy Info (EERE)

    Marathon Capital LLC (California) Name: Marathon Capital LLC (California) Address: 42 Miller Avenue Place: Mill Valley, California Zip: 94941 Region: Bay Area Product: Investment...

  4. Viresco International Capital Management | Open Energy Information

    Open Energy Info (EERE)

    International Capital Management Jump to: navigation, search Name: Viresco International Capital Management Place: San Diego, California Zip: 92130 Product: San Diego-based hedge...

  5. Greenwood Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Greenwood Capital Partners Jump to: navigation, search Name: Greenwood Capital Partners Place: Charlotte, North Carolina Zip: 28266 Product: Corporate finance boutique working on...

  6. Montauk Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Montauk Energy Capital Jump to: navigation, search Name: Montauk Energy Capital Place: Pittsburg, Pennsylvania Zip: 15220 Product: Owns and operates landfill gas plants across the...

  7. New Energy Capital Corp | Open Energy Information

    Open Energy Info (EERE)

    Capital Corp Jump to: navigation, search Name: New Energy Capital Corp. Place: Hanover, New Hampshire Zip: 3755 Sector: Renewable Energy Product: Private equity fund focused on...

  8. Quadrant Capital Advisors Inc | Open Energy Information

    Open Energy Info (EERE)

    Quadrant Capital Advisors Inc Jump to: navigation, search Name: Quadrant Capital Advisors Inc. Place: New York, New York Zip: 10022 Sector: Hydro, Wind energy Product: US based...

  9. Arctas Capital Group | Open Energy Information

    Open Energy Info (EERE)

    Arctas Capital Group Jump to: navigation, search Name: Arctas Capital Group Place: Houston, Texas Zip: 77056 Sector: Geothermal energy, Renewable Energy, Wind energy Product: A...

  10. Krass Capital Group AG | Open Energy Information

    Open Energy Info (EERE)

    Krass Capital Group AG Jump to: navigation, search Name: Krass Capital Group AG Place: Grfelfing, Bulgaria Zip: 82166 Sector: Renewable Energy Product: Grafelfing-based firm...

  11. North Cove Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Cove Capital Advisors Jump to: navigation, search Name: North Cove Capital Advisors Place: Connecticut Sector: Carbon Product: North Cove is an advisory firm that works...

  12. Starlight Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Starlight Capital Advisors Jump to: navigation, search Name: Starlight Capital Advisors Place: Carlsbad, California Zip: 92011 Sector: Renewable Energy Product: California-based...

  13. Digital Power Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital LLC Jump to: navigation, search Name: Digital Power Capital LLC Place: Greenwich, Connecticut Zip: 6830 Product: A private equity firm focused on new technologies that...

  14. Solution Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Solution Capital Partners Jump to: navigation, search Name: Solution Capital Partners Place: New York Zip: NY 10036 Product: A New York-based investment firm active in the...

  15. American Capital Energy | Open Energy Information

    Open Energy Info (EERE)

    Energy Jump to: navigation, search Logo: American Capital Energy Name: American Capital Energy Address: 15 Tyngsboro Rd. Suite 4A Place: North Chelmsford, Massachusetts Zip: 01863...

  16. Greentech Capital Advisors GCA | Open Energy Information

    Open Energy Info (EERE)

    Capital Advisors GCA Jump to: navigation, search Name: Greentech Capital Advisors (GCA) Place: New York, New York Zip: 10017 Sector: Renewable Energy Product: New York-based...

  17. Conservation Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Conservation Capital LLC Jump to: navigation, search Name: Conservation Capital LLC Place: Houston, Texas Zip: 77018 Product: Houston-based land investment and consulting company...

  18. Longboard Capital Advisors | Open Energy Information

    Open Energy Info (EERE)

    Longboard Capital Advisors Jump to: navigation, search Name: Longboard Capital Advisors Place: Santa Monica, California Zip: 90405 Product: Longboard is a small hedge fund focused...

  19. Haywood Dorland Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Dorland Energy Capital Jump to: navigation, search Name: Haywood Dorland Energy Capital Place: New York, New York Sector: Renewable Energy Product: New York-based private equity...

  20. Energy Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    LLC Jump to: navigation, search Name: Energy Capital LLC Place: Ketchum, Idaho Zip: ID 83340 Sector: Renewable Energy Product: Energy Capital LLc is a financial catalyst focusing...

  1. Wind Farm Capital | Open Energy Information

    Open Energy Info (EERE)

    Farm Capital Jump to: navigation, search Name: Wind Farm Capital Place: Connecticut Sector: Wind energy Product: US-based company that buys wind leases from farmers and landowners,...

  2. Beijing Capital International Airport | Open Energy Information

    Open Energy Info (EERE)

    International Airport Jump to: navigation, search Name: Beijing Capital International Airport Place: Beijing, Beijing Municipality, China Zip: 100621 Product: Beijing Capital...

  3. Nimes Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Nimes Capital LLC Jump to: navigation, search Name: Nimes Capital LLC Place: Los Angeles, California Zip: 90067 Product: Los Angeles-based private equity firm that provides growth...

  4. Sequoia Capital Ltda | Open Energy Information

    Open Energy Info (EERE)

    Capital Ltda Jump to: navigation, search Name: Sequoia Capital Ltda Place: Sao Paulo, Sao Paulo, Brazil Sector: Wind energy Product: Brazilian-based wind project developer....

  5. Wind Capital Group | Open Energy Information

    Open Energy Info (EERE)

    Capital Group Jump to: navigation, search Name: Wind Capital Group Place: St. Louis, Missouri Zip: 63101 Sector: Wind energy Product: Missouri-based wind project developer, focused...

  6. Impact Capital Partners Limited | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Limited Jump to: navigation, search Name: Impact Capital Partners Limited Place: Los Angeles, California Zip: CA 90067-1509 Product: Los Angeles-based, investment...

  7. Ambata Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Ambata Capital Partners Jump to: navigation, search Name: Ambata Capital Partners Place: New York, New York Zip: 10169 Product: New York-based global investment and advisory firm...

  8. Strategic Capital Investments LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital Investments LLC Jump to: navigation, search Name: Strategic Capital Investments LLC Place: Short Hills, New Jersey Zip: 7078 Product: New Jersey-based, project development...

  9. Black Coral Capital | Open Energy Information

    Open Energy Info (EERE)

    Coral Capital Jump to: navigation, search Name: Black Coral Capital Address: 55 Union Street, 3rd Floor Place: Boston, Massachusetts Zip: 02108 Region: Greater Boston Area Product:...

  10. Birch Tree Capital | Open Energy Information

    Open Energy Info (EERE)

    Birch Tree Capital Jump to: navigation, search Name: Birch Tree Capital Place: Framingham, Massachusetts Zip: 1701 Sector: Renewable Energy Product: Financial advisory service with...

  11. American Capital Energy Inc | Open Energy Information

    Open Energy Info (EERE)

    Capital Energy Inc Jump to: navigation, search Name: American Capital Energy Inc Place: North Chelmsford, Massachusetts Zip: 1863 Sector: Services Product: Full-service PV...

  12. Bannockburn Capital LTD | Open Energy Information

    Open Energy Info (EERE)

    Bannockburn Capital LTD Jump to: navigation, search Name: Bannockburn Capital, LTD. Place: Newport Beach, California Zip: 92657 Sector: Carbon, Renewable Energy Product: String...

  13. Sustainable World Capital | Open Energy Information

    Open Energy Info (EERE)

    World Capital Jump to: navigation, search Name: Sustainable World Capital Place: Atlanta, Georgia Zip: 30326 Product: Atlanta-based firm that connects companies with institutional...

  14. West Mountain Energy Capital | Open Energy Information

    Open Energy Info (EERE)

    Energy Capital Jump to: navigation, search Name: West Mountain Energy Capital Place: Salisbury, Connecticut Zip: 6070 Sector: Renewable Energy Product: Provides renewable resource...

  15. Marathon Capital LLC (Illinois) | Open Energy Information

    Open Energy Info (EERE)

    Logo: Marathon Capital LLC (Illinois) Name: Marathon Capital LLC (Illinois) Address: 2801 Lakeside Drive, Suite 210 Place: Bannockburn, Illinois Zip: 60015 Product: Investment...

  16. Cate Street Capital Inc | Open Energy Information

    Open Energy Info (EERE)

    Cate Street Capital Inc Jump to: navigation, search Name: Cate Street Capital, Inc. Place: Portsmouth, New Hampshire Zip: 3801 Sector: Renewable Energy Product: New Hampshire-based...

  17. New Cycle Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Cycle Capital LLC Jump to: navigation, search Name: New Cycle Capital, LLC. Place: San Francisco, California Zip: 94103 Product: San Francisco-based venture capitalist firm...

  18. Nature Elements Capital | Open Energy Information

    Open Energy Info (EERE)

    Capital Jump to: navigation, search Name: Nature Elements Capital Place: Beijing, Beijing Municipality, China Zip: 100125 Product: Beijing-based private equity firm investing in...

  19. Blue Green Capital | Open Energy Information

    Open Energy Info (EERE)

    Green Capital Jump to: navigation, search Name: Blue Green Capital Place: Spain Zip: 8860 Sector: Renewable Energy, Solar Product: String representation "Spanish develop ... their...

  20. Green Energy Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Jump to: navigation, search Name: Green Energy Capital Partners Place: Plymouth Meeting, Pennsylvania Zip: 19462 Sector: Wind energy Product: Pennsylvania-based...

  1. Jane Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    search Logo: Jane Capital Partners Name: Jane Capital Partners Address: 505 Montgomery, 2nd Floor Place: San Francisco, California Zip: 94111 Region: Bay Area Product:...

  2. L A Investment Capital | Open Energy Information

    Open Energy Info (EERE)

    A Investment Capital Jump to: navigation, search Name: L.A. Investment Capital Place: Beverly Hills, California Zip: CA 90210 Sector: Biofuels Product: Investment firm with funds...

  3. MVP Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    navigation, search Logo: MVP Capital Partners Name: MVP Capital Partners Address: 201 King of Prussia Road, Suite 240 Place: Radnor, Pennsylvania Zip: 19087 Region: Northeast -...

  4. Human Capital Management | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    human capital requires comprehensive planning and analysis in order to develop, implement, and evaluate programs that support every facet of employee work life. DOE human capital ...

  5. Capital Reporting Company Quadrennial ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... percent annual job growth rate. 19 When you look at ... And 15 that's the first refinery in the United States 16 being ... It 5 was just a slow, decline of death. Closing 6 schools ...

  6. Soft Costs | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Soft Costs » Soft Costs Soft Costs The U.S. Department of Energy (DOE) SunShot Initiative's soft costs program works to lower the non-hardware costs of solar and accelerate the adoption of solar energy technologies throughout the United States. In support of the SunShot Initiative goals, the soft costs program works in the following strategic areas: networking and technical assistance, data analysis, business innovation, and training. Soft Costs Activity Areas, Business Innovation, Networking

  7. Nuclear economics 2000: Deterministic and probabilistic projections of nuclear and coal electric power generation costs for the year 2000

    SciTech Connect (OSTI)

    Williams, K.A.; Delene, J.G.; Fuller, L.C.; Bowers, H.I.

    1987-06-01

    The total busbar electric generating costs were estimated for locations in ten regions of the United States for base-load nuclear and coal-fired power plants with a startup date of January 2000. For the Midwest region a complete data set that specifies each parameter used to obtain the comparative results is supplied. When based on the reference set of input variables, the comparison of power generation costs is found to favor nuclear in most regions of the country. Nuclear power is most favored in the northeast and western regions where coal must be transported over long distances; however, coal-fired generation is most competitive in the north central region where large reserves of cheaply mineable coal exist. In several regions small changes in the reference variables could cause either option to be preferred. The reference data set reflects the better of recent electric utility construction cost experience (BE) for nuclear plants. This study assumes as its reference case a stable regulatory environment and improved planning and construction practices, resulting in nuclear plants typically built at the present BE costs. Today's BE nuclear-plant capital investment cost model is then being used as a surrogate for projected costs for the next generation of light-water reactor plants. An alternative analysis based on today's median experience (ME) nuclear-plant construction cost experience is also included. In this case, coal is favored in all ten regions, implying that typical nuclear capital investment costs must improve for nuclear to be competitive.

  8. Startup Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter discusses startup costs for construction and environmental projects, and estimating guidance for startup costs.

  9. Weighing the Costs and Benefits of State Renewables Portfolio Standards in the United States: A Comparative Analysis of State-Level Policy Impact Projections

    SciTech Connect (OSTI)

    Chen, Cliff; Wiser, Ryan; Mills, Andrew; Bolinger, Mark

    2008-01-07

    State renewables portfolio standards (RPS) have emerged as one of the most important policy drivers of renewable energy capacity expansion in the U.S. As RPS policies have been proposed or adopted in an increasing number of states, a growing number of studies have attempted to quantify the potential impacts of these policies, focusing primarily on cost impacts, but sometimes also estimating macroeconomic, risk reduction, and environmental effects. This article synthesizes and analyzes the results and methodologies of 31 distinct state or utility-level RPS cost-impact analyses completed since 1998. Together, these studies model proposed or adopted RPS policies in 20 different states. We highlight the key findings of these studies on the projected costs of state RPS policies, examine the sensitivity of projected costs to model assumptions, evaluate the reasonableness of key input assumptions, and suggest possible areas of improvement for future RPS analyses. We conclude that while there is considerable uncertainty in the study results, the majority of the studies project modest cost impacts. Seventy percent of the state RPS cost studies project retail electricity rate increases of no greater than one percent. Nonetheless, there is considerable room for improving the analytic methods, and therefore accuracy, of these estimates.

  10. Electricity Generation Cost Simulation Model

    Energy Science and Technology Software Center (OSTI)

    2003-04-25

    The Electricity Generation Cost Simulation Model (GENSIM) is a user-friendly, high-level dynamic simulation model that calculates electricity production costs for variety of electricity generation technologies, including: pulverized coal, gas combustion turbine, gas combined cycle, nuclear, solar (PV and thermal), and wind. The model allows the user to quickly conduct sensitivity analysis on key variables, including: capital, O&M, and fuel costs; interest rates; construction time; heat rates; and capacity factors. The model also includes consideration ofmore » a wide range of externality costs and pollution control options for carbon dioxide, nitrogen oxides, sulfur dioxide, and mercury. Two different data sets are included in the model; one from the U.S. Department of Energy (DOE) and the other from Platt's Research Group. Likely users of this model include executives and staff in the Congress, the Administration and private industry (power plant builders, industrial electricity users and electric utilities). The model seeks to improve understanding of the economic viability of various generating technologies and their emission trade-offs. The base case results using the DOE data, indicate that in the absence of externality costs, or renewable tax credits, pulverized coal and gas combined cycle plants are the least cost alternatives at 3.7 and 3.5 cents/kwhr, respectively. A complete sensitivity analysis on fuel, capital, and construction time shows that these results coal and gas are much more sensitive to assumption about fuel prices than they are to capital costs or construction times. The results also show that making nuclear competitive with coal or gas requires significant reductions in capital costs, to the $1000/kW level, if no other changes are made. For renewables, the results indicate that wind is now competitive with the nuclear option and is only competitive with coal and gas for grid connected applications if one includes the federal production tax

  11. Riba Capital | Open Energy Information

    Open Energy Info (EERE)

    Place: Spain Sector: Renewable Energy Product: Riba Capital is a fund developed to invest in renewable projects in Iberia. It raised 800 million euros of financing in 2003 and...

  12. Capital Solar | Open Energy Information

    Open Energy Info (EERE)

    Solar Jump to: navigation, search Name: Capital Solar Place: Lecce, Italy Sector: Solar Product: Lecce-based solar project developer. Coordinates: 40.357955, 18.16801 Show Map...

  13. Computerized operating cost model for industrial steam generation

    SciTech Connect (OSTI)

    Powers, T.D.

    1983-02-01

    Pending EPA regulations, establishing revised emission levels for industrial boilers are perceived to have an effect on the relative costs of steam production technologies. To aid in the comparison of competitive boiler technologies, the Steam Cost Code was developed which provides levelized steam costs reflecting the effects of a number of key steam cost parameters. The Steam Cost Code is a user interactive FORTRAN program designed to operate on a VAX computer system. The program requires the user to input a number of variables describing the design characteristics, capital costs, and operating conditions for a specific boiler system. Part of the input to the Steam Cost Code is the capital cost of the steam production system. The capital cost is obtained from a program called INDCEPT, developed by Oak Ridge National Laboratory under Department of Energy, Morgantown Energy Technology Center sponsorship.

  14. Factors Impacting Decommissioning Costs - 13576

    SciTech Connect (OSTI)

    Kim, Karen; McGrath, Richard

    2013-07-01

    The Electric Power Research Institute (EPRI) studied United States experience with decommissioning cost estimates and the factors that impact the actual cost of decommissioning projects. This study gathered available estimated and actual decommissioning costs from eight nuclear power plants in the United States to understand the major components of decommissioning costs. Major costs categories for decommissioning a nuclear power plant are removal costs, radioactive waste costs, staffing costs, and other costs. The technical factors that impact the costs were analyzed based on the plants' decommissioning experiences. Detailed cost breakdowns by major projects and other cost categories from actual power plant decommissioning experiences will be presented. Such information will be useful in planning future decommissioning and designing new plants. (authors)

  15. IT Capital Planning | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    IT Capital Planning IT Capital Planning IT7 (003).jpg What is Capital Planning? The Office of Management and Budget (OMB) Circular A-11, defines capital planning as "a decision-making process for ensuring IT investments integrate strategic planning, budgeting, procurement, and IT management in support of agency missions and business needs." Who's Responsible for DOE Capital Planning? The Office of the Chief Information Officer (OCIO) oversees the DOE IT portfolio, while the Information

  16. Trends in U.S. Oil and Natural Gas Upstream Costs - Energy Information...

    U.S. Energy Information Administration (EIA) Indexed Site

    The IHS report assesses capital and operating costs associated with drilling, completing, and operating wells and facilities. The report focuses on five onshore regions, including ...

  17. Low Cost Hydrogen Production Platform

    SciTech Connect (OSTI)

    Timothy M. Aaron, Jerome T. Jankowiak

    2009-10-16

    A technology and design evaluation was carried out for the development of a turnkey hydrogen production system in the range of 2.4 - 12 kg/h of hydrogen. The design is based on existing SMR technology and existing chemical processes and technologies to meet the design objectives. Consequently, the system design consists of a steam methane reformer, PSA system for hydrogen purification, natural gas compression, steam generation and all components and heat exchangers required for the production of hydrogen. The focus of the program is on packaging, system integration and an overall step change in the cost of capital required for the production of hydrogen at small scale. To assist in this effort, subcontractors were brought in to evaluate the design concepts and to assist in meeting the overall goals of the program. Praxair supplied the overall system and process design and the subcontractors were used to evaluate the components and system from a manufacturing and overall design optimization viewpoint. Design for manufacturing and assembly (DFMA) techniques, computer models and laboratory/full-scale testing of components were utilized to optimize the design during all phases of the design development. Early in the program evaluation, a review of existing Praxair hydrogen facilities showed that over 50% of the installed cost of a SMR based hydrogen plant is associated with the high temperature components (reformer, shift, steam generation, and various high temperature heat exchange). The main effort of the initial phase of the program was to develop an integrated high temperature component for these related functions. Initially, six independent concepts were developed and the processes were modeled to determine overall feasibility. The six concepts were eventually narrowed down to the highest potential concept. A US patent was awarded in February 2009 for the Praxair integrated high temperature component design. A risk analysis of the high temperature component was

  18. ErgyCapital SpA formerly Greenergy Capital | Open Energy Information

    Open Energy Info (EERE)

    SpA formerly Greenergy Capital Jump to: navigation, search Name: ErgyCapital SpA (formerly Greenergy Capital) Place: Milan, Italy Zip: 20121 Sector: Efficiency, Renewable Energy...

  19. Summary Max Total Units

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Summary Max Total Units *If All Splits, No Rack Units **If Only FW, AC Splits 1000 52 28 28 2000 87 59 35 3000 61 33 15 4000 61 33 15 Totals 261 153 93 ***Costs $1,957,500.00 $1,147,500.00 $697,500.00 Notes: added several refrigerants removed bins from analysis removed R-22 from list 1000lb, no Glycol, CO2 or ammonia Seawater R-404A only * includes seawater units ** no seawater units included *** Costs = (total units) X (estimate of $7500 per unit) 1000lb, air cooled split systems, fresh water

  20. Wind-To-Hydrogen Project: Electrolyzer Capital Cost Study

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    2008 Technical Report Wind-To-Hydrogen Project: NREL... H271.3730 National Renewable Energy Laboratory 1617 Cole ... hydrogen on a scale much greater than current production. ...

  1. Updated Capital Cost Estimates for Utility Scale Electricity...

    Annual Energy Outlook [U.S. Energy Information Administration (EIA)]

    ... update, the assumed characteristics of a coal plant with CCS in NEMS were assumed to be ... which is a nominal 650 MW coal-fired supercritical steam-electric generating ...

  2. Bench-Scale Silicone Process for Low-Cost CO{sub 2} Capture

    SciTech Connect (OSTI)

    Vipperla, Ravikumar; Yee, Michael; Steele, Ray

    2012-11-01

    This report presents system and economic analysis for a carbon capture unit which uses an amino-silicone solvent for CO{sub 2} capture and sequestration (CCS) in a pulverized coal (PC) boiler. The amino-silicone solvent is based on GAP-1 with Tri-Ethylene Glycol (TEG) as a co-solvent. The report also shows results for a CCS unit based on a conventional approach using mono-ethanol amine (MEA). Models were developed for both processes and used to calculate mass and energy balances. Capital costs and energy penalty were calculated for both systems, as well as the increase in cost of electricity. The amino-silicone solvent based system demonstrates significant advantages compared to the MEA system.

  3. Capital Sources and Providers | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Capital Sources and Providers Capital Sources and Providers An image of a blue diagram showing an arrow labeled "Lender" pointing to a rectangle labeled "Borrower" with a curved arrow labeled "Repayment" pointing back to "Lender." Another arrow labeled "Capital Sources" also points to the arrow labeled "Lender." The most important elements of a clean energy lending program are the capital source and the capital provider. The capital

  4. DOE Strategic Human Capital Plan (FY 2011 - 2015) | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Strategic Human Capital Plan (FY 2011 - 2015) DOE Strategic Human Capital Plan (FY 2011 - 2015) The Strategic Human Capital Plan sets forth the framework for managing the ...

  5. EA-185 Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Morgan Stanley Capital Group Inc. EA-185 Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Canada. EA-185 Morgan ...

  6. RockPort Capital Partners (California) | Open Energy Information

    Open Energy Info (EERE)

    RockPort Capital Partners (California) Jump to: navigation, search Logo: RockPort Capital Partners (California) Name: RockPort Capital Partners (California) Address: 3000 Sand Hill...

  7. Costs and benefits of industrial reporting and voluntary targets for energy efficiency. A report to the Congress of the United States. Volume I: Main report

    SciTech Connect (OSTI)

    Not Available

    1994-02-01

    Section 131(c) of the Energy Policy Act of 1992 (EPACT) (Public Law 102-486) requires the Department of Energy (DOE) to evaluate the costs and benefits of federally mandated energy efficiency reporting requirements and voluntary energy efficiency improvement targets for energy-intensive industries. It also requires DOE to evaluate the role of reporting and targets in improving energy efficiency. Specifically, the legislation states: Not later than one year after the data of the enactment of this Act, the Secretary shall, in consultation with affected industries, evaluate and report to the Congress regarding the establishment of Federally mandated energy efficiency reporting requirements and voluntary energy efficiency improvement targets for energy intensive industries. Such report shall include an evaluation of the costs and benefits of such reporting requirements and voluntary energy efficiency improvement targets, and recommendations regarding the role of such activities in improving energy efficiency in energy intensive industries. This report is DOE`s response to that directive. It is the culmination of a year-long study that included (1) analysis of documents pertaining to a previous reporting and targets effort, the industrial Energy Efficiency Improvements Program (or the CE-189 program, following the designation of the reporting form used to collect data in that program), administered by DOE from 1976 to 1985, as well as other important background information; (2) extensive consultations with government and industry officials regarding the CE-189 Program, experience with other programs that have reporting elements, and the attributes of possible alternative strategies for reporting and targets; and (3) analyses of the costs and benefits of the CE-189 Program and several alternatives to the CE-189 approach.

  8. Solar Access to Public Capital (SAPC) Mock Securitization Project

    SciTech Connect (OSTI)

    Mendelsohn, Michael; Lowder, Travis; Rottman, Mary; Borod, Ronald; Gabig, Nathan; Henne, Stephen; Caplin, Conrad; Notte, Quentin

    2015-12-21

    In late 2012, the National Renewable Energy Laboratory (NREL) initiated the Solar Access to Public Capital (SAPC) working group. Backed by a three-year funding facility from the U.S. Department of Energy (DOE), NREL set out to organize the solar, legal, banking, capital markets, engineering, and other relevant stakeholder communities in order to open lower-cost debt investment for solar asset deployment. SAPC engaged its members to standardize contracts, develop best practices, and comprehend how the rating agencies perceive solar project portfolios as an investment asset class. Rating agencies opine on the future creditworthiness of debt obligations. Issuers often seek investment-grade ratings from the rating agencies in order to satisfy the desires of their investors. Therefore, for the solar industry to access larger pools of capital at a favorable cost, it is critical to increase market participants' understanding of solar risk parameters. The process provided valuable information to address rating agency perceptions of risk that, without such information, could require costly credit enhancement or higher yields to attract institutional investors. Two different securities were developed--one for a hypothetical residential solar portfolio and one for a hypothetical commercial solar portfolio. Five rating agencies (Standard and Poor's, Moody's, KBRA, Fitch, and DBRS) participated and provided extensive feedback, some through conversations that extended several months. The findings represented in this report are a composite summary of that feedback and do not indicate any specific feedback from any single rating agency.

  9. Selected bibliography: cost and energy savings of conservation and renewable energy technologies

    SciTech Connect (OSTI)

    1980-05-01

    This bibliography is a compilation of reports on the cost and energy savings of conservation and renewable energy applications throughout the United States. It is part of an overall effort to inform utilities of technological developments in conservation and renewable energy technologies and so aid utilities in their planning process to determine the most effective and economic combination of capital investments to meet customer needs. Department of Energy assessments of the applications, current costs and cost goals for the various technologies included in this bibliography are presented. These assessments are based on analyses performed by or for the respective DOE Program Offices. The results are sensitive to a number of variables and assumptions; however, the estimates presented are considered representative. These assessments are presented, followed by some conclusions regarding the potential role of the conservation and renewable energy alternative. The approach used to classify the bibliographic citations and abstracts is outlined.

  10. Eco Drive Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners Jump to: navigation, search Name: Eco-Drive Capital Partners Place: New York Product: New York-based Eco-Drive is a European-American investment consortium,...

  11. Cinergy Capital & Trading, Inc | Open Energy Information

    Open Energy Info (EERE)

    Cinergy Capital & Trading, Inc Jump to: navigation, search Name: Cinergy Capital & Trading, Inc Place: Indiana Phone Number: (704) 382-3747 or (513) 287-2226 or (317) 838-1338...

  12. Eco Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital LLC Jump to: navigation, search Name: Eco Capital LLC Place: New York, New York Zip: 10166 Sector: Carbon, Renewable Energy Product: New York-based advisory and investment...

  13. Capital Cooking: Order (2014-CE-23008)

    Broader source: Energy.gov [DOE]

    DOE ordered Capital Cooking Equipment, Inc. to pay a $8,000 civil penalty after finding Capital Cooking had failed to certify that certain models of cooking products comply with the applicable energy conservation standards.

  14. Capital Asset Project List.xls

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... by DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets. ... Start of Operations or Project Completion Capital Asset Project List 4112016 1 of 1

  15. Human Capital: The Role of Ombudsmen in Dispute Resolution

    Office of Environmental Management (EM)

    the Ranking Member, Subcommittee on International Security, Proliferation, and Federal Services, Committee on Government Affairs, U.S. Senate United States General Accounting Office GAO April 2001 HUMAN CAPITAL The Role of Ombudsmen in Dispute Resolution GAO-01-466 Page i GAO-01-466 The Role of Ombudsmen in Dispute Resolution Letter 1 Results in Brief 2 Background 5 Objectives, Scope, and Methodology 12 Some Agencies Use Ombudsmen to Deal With Workplace Issues 14 The Case Illustrations: Varied

  16. EM Contractors for Capital Asset Projects

    Broader source: Energy.gov [DOE]

    Read the EM Contractors for Capital Asset Projects list, which includes the project name, number, site, and contractor.

  17. Venture Capital Finance | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Venture Capital Finance Venture Capital Finance Plenary III: Project Finance and Investment Venture Capital Finance Brian Baynes, Partner, Flagship Ventures baynes_biomass_2014.pdf (1.07 MB) More Documents & Publications Biomass 2011 Conference Agenda U.S. Biofuels Industry: Mind the Gap Review of Recent Pilot Scale Cellulosic Ethanol Demonstration

  18. Cost benefit analysis of waste compaction alternatives at Lawrence Livermore National Laboratory

    SciTech Connect (OSTI)

    Not Available

    1990-11-01

    This report presents a cost benefit analysis of the potential procurement and operation of various solid waste compactors, or, of the use of commercial compaction services, for compaction of solid transuranic (TRU), low-level radioactive, hazardous, and mixed wastes at Lawrence Livermore National Laboratory (LLNL) Hazardous Waste Management (HWM) facilities. The cost benefit analysis was conducted to determine if increased compaction capacity at HWM might afford the potential for significant waste volume reduction and annual savings in material, shipping, labor, and disposal costs. In the following cost benefit analysis, capital costs and recurring costs of increased HWM compaction capabilities are considered. Recurring costs such as operating and maintenance costs are estimated based upon detailed knowledge of system parameters. When analyzing the economic benefits of enhancing compaction capabilities, continued use of the existing HWM compaction units is included for comparative purposes. In addition, the benefits of using commercial compaction services instead of procuring a new compactor system are evaluated. 31 refs., 1 fig., 6 tabs.

  19. Life Cycle Cost (LCC) Handbook Final Version 9-30-14

    Broader source: Energy.gov [DOE]

    This handbook provides procedures, information, examples, and tools to develop consistent and defensible life-cycle cost estimates (LCCE) and perform appropriate life-cycle cost analyses (LCCA) for capital projects. LCC Handbook – Final, September 2014

  20. National Lab Uses OGJ Data to Develop Cost Equations

    SciTech Connect (OSTI)

    Brown, Daryl R.; Cabe, James E.; Stout, Tyson E.

    2011-01-03

    For the past 30 years, the Oil and Gas Journal (OGJ) has published data on the costs of onshore and offshore oil and gas pipelines and related equipment. This article describes the methodology employed and resulting equations developed for conceptual capital cost estimating of onshore pipelines. Also described are cost trends uncovered during the course of the analysis.

  1. Novel Low Cost, High Reliability Wind Turbine Drivetrain

    SciTech Connect (OSTI)

    Chobot, Anthony; Das, Debarshi; Mayer, Tyler; Markey, Zach; Martinson, Tim; Reeve, Hayden; Attridge, Paul; El-Wardany, Tahany

    2012-09-13

    Clipper Windpower, in collaboration with United Technologies Research Center, the National Renewable Energy Laboratory, and Hamilton Sundstrand Corporation, developed a low-cost, deflection-compliant, reliable, and serviceable chain drive speed increaser. This chain and sprocket drivetrain design offers significant breakthroughs in the areas of cost and serviceability and addresses the key challenges of current geared and direct-drive systems. The use of gearboxes has proven to be challenging; the large torques and bending loads associated with use in large multi-MW wind applications have generally limited demonstrated lifetime to 8-10 years [1]. The large cost of gearbox replacement and the required use of large, expensive cranes can result in gearbox replacement costs on the order of $1M, representing a significant impact to overall cost of energy (COE). Direct-drive machines eliminate the gearbox, thereby targeting increased reliability and reduced life-cycle cost. However, the slow rotational speeds require very large and costly generators, which also typically have an undesirable dependence on expensive rare-earth magnet materials and large structural penalties for precise air gap control. The cost of rare-earth materials has increased 20X in the last 8 years representing a key risk to ever realizing the promised cost of energy reductions from direct-drive generators. A common challenge to both geared and direct drive architectures is a limited ability to manage input shaft deflections. The proposed Clipper drivetrain is deflection-compliant, insulating later drivetrain stages and generators from off-axis loads. The system is modular, allowing for all key parts to be removed and replaced without the use of a high capacity crane. Finally, the technology modularity allows for scalability and many possible drivetrain topologies. These benefits enable reductions in drivetrain capital cost by 10.0%, levelized replacement and O&M costs by 26.7%, and overall cost of

  2. A GIS COST MODEL TO ASSESS THE AVAILABILITY OF FRESHWATER, SEAWATER, AND SALINE GROUNDWATER FOR ALGAL BIOFUEL PRODUCTION IN THE UNITED STATES

    SciTech Connect (OSTI)

    Venteris, Erik R.; Skaggs, Richard; Coleman, Andre M.; Wigmosta, Mark S.

    2013-03-15

    A key advantage of using microalgae for biofuel production is the ability of some algal strains to thrive in waters unsuitable for conventional crop irrigation such as saline groundwater or seawater. Nonetheless, the availability of sustainable water supplies will provide significant challenges for scale-up and development of algal biofuels. We conduct a limited techno-economic assessment based on the availability of freshwater, saline groundwater, and seawater for use in open pond algae cultivation systems. We explore water issues through GIS-based models of algae biofuel production, freshwater supply, and cost models for supplying seawater and saline groundwater. We estimate that combined, within the coterminous US these resources can support production on the order of 9.46E+7 m3 yr-1 (25 billion gallons yr-1) of renewable biodiesel. Achievement of larger targets requires the utilization of less water efficient sites and relatively expensive saline waters. Geographically, water availability is most favorable for the coast of the Gulf of Mexico and Florida peninsula, where evaporation relative to precipitation is moderate and various saline waters are economically available. As a whole, barren and scrub lands of the southwestern US have limited freshwater supplies so accurate assessment of alternative waters is critical.

  3. Offshore Wind Balance-of-System Cost Modeling

    SciTech Connect (OSTI)

    Maness, Michael; Stehly, Tyler; Maples, Ben; Mone, Christopher

    2015-09-29

    Offshore wind balance-of-system (BOS) costs contribute up to 70% of installed capital costs. Thus, it is imperative to understand the impact of these costs on project economics as well as potential cost trends for new offshore wind technology developments. As a result, the National Renewable Energy Laboratory (NREL) developed and recently updated a BOS techno-economic model using project cost estimates created from wind energy industry sources.

  4. Program and Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2010-11-29

    The purpose of this Order is to a) provide the Department of Energy (DOE) Elements, including the National Nuclear Security Administration (NNSA), with program and project management direction for the acquisition of capital assets with the goal of delivering projects within the original performance baseline (PB), cost and schedule, and fully capable of meeting mission performance, safeguards and security, and environmental, safety, and health requirements unless impacted by a directed change; and b) implement Office of Management and Budget (OMB) Circulars to include: A-11, Part 7, Capital Programming Guide, which prescribes new requirements and leading practices for project and acquisition management; A-123, Management's Responsibility for Internal Control, which defines management's responsibility for internal control in Federal agencies; and A-131, Value Engineering, which requires that all Federal agencies use Value Engineering (VE) as a management tool. Supersedes DOE O 413.3B Chg 1 (AdminChg)

  5. Program and Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2010-11-29

    The purpose of this Order is to a) provide the Department of Energy (DOE) Elements, including the National Nuclear Security Administration (NNSA), with program and project management direction for the acquisition of capital assets with the goal of delivering projects within the original performance baseline (PB), cost and schedule, and fully capable of meeting mission performance, safeguards and security, and environmental, safety, and health requirements unless impacted by a directed change; and b) implement Office of Management and Budget (OMB) Circulars to include: A-11, Part 7, Capital Programming Guide, which prescribes new requirements and leading practices for project and acquisition management; A-123, Management's Responsibility for Internal Control, which defines management's responsibility for internal control in Federal agencies; and A-131, Value Engineering, which requires that all Federal agencies use Value Engineering (VE) as a management tool.

  6. HTGR Cost Model Users' Manual

    SciTech Connect (OSTI)

    A.M. Gandrik

    2012-01-01

    The High Temperature Gas-Cooler Reactor (HTGR) Cost Model was developed at the Idaho National Laboratory for the Next Generation Nuclear Plant Project. The HTGR Cost Model calculates an estimate of the capital costs, annual operating and maintenance costs, and decommissioning costs for a high-temperature gas-cooled reactor. The user can generate these costs for multiple reactor outlet temperatures; with and without power cycles, including either a Brayton or Rankine cycle; for the demonstration plant, first of a kind, or nth of a kind project phases; for a single or four-pack configuration; and for a reactor size of 350 or 600 MWt. This users manual contains the mathematical models and operating instructions for the HTGR Cost Model. Instructions, screenshots, and examples are provided to guide the user through the HTGR Cost Model. This model was design for users who are familiar with the HTGR design and Excel. Modification of the HTGR Cost Model should only be performed by users familiar with Excel and Visual Basic.

  7. Search for: All records | SciTech Connect

    Office of Scientific and Technical Information (OSTI)

    boiler units that minimizes overall capital investment and operating costs; Evaluate ... boiler units that minimizes overall capital investment and operating costs. * ...

  8. Working Capital for Contractors | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Capital for Contractors Working Capital for Contractors Better Buildings Neighborhood Program Financing Peer Exchange Call: Working Capital for Contractors, Call Slides and Discussion Summary, August 30, 2012. Call Slides and Discussion Summary (673.52 KB) More Documents & Publications Streamline Service Delivery via Customer Communication and Contractor Coordination Focus Series: OREGON-On Bill Financing Program: On-Bill Financing Brings Lenders and Homeowners On Board Lessons from On-Bill

  9. GE Capital Partnership | GE Global Research

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Global Research and GE Capital: Middle Market Collaboration Click to email this to a friend (Opens in new window) Share on Facebook (Opens in new window) Click to share (Opens in new window) Click to share on LinkedIn (Opens in new window) Click to share on Tumblr (Opens in new window) Global Research and GE Capital: Middle Market Collaboration In 2013, a partnering initiative between Global Research and GE Capital resulted in dozens of middle market companies collaborating with Global Research

  10. U-AVLIS feed conversion using continuous metallothermic reduction of UF{sub 4}: System description and cost estimate

    SciTech Connect (OSTI)

    Not Available

    1994-04-01

    The purpose of this document is to present a system description and develop baseline capital and operating cost estimates for commercial facilities which produced U-Fe feedstock for AVLIS enrichment plants using the continuous fluoride reduction (CFR) process. These costs can then be used together with appropriate economic assumptions to calculate estimated unit costs to the AVLIS plant owner (or utility customer) for such conversion services. Six cases are being examined. All cases assume that the conversion services are performed by a private company at a commercial site which has an existing NRC license to possess source material and which has existing uranium processing operations. The cases differ in terms of annual production capacity and whether the new process system is installed in a new building or in an existing building on the site. The six cases are summarized here.

  11. Expansion Capital Partners LLC | Open Energy Information

    Open Energy Info (EERE)

    Area Product: Venture capital firm that invests in expansion-stage, clean technology enterprises Year Founded: 2001 Phone Number: (415) 788-8802 Website: www.expansioncapital.com...

  12. Ethanol Capital Management | Open Energy Information

    Open Energy Info (EERE)

    Management Jump to: navigation, search Name: Ethanol Capital Management Place: Tucson, Arizona Zip: 85711 Product: Manages funds investing in Ethanol plants in the US Coordinates:...

  13. Persimmon Tree Capital | Open Energy Information

    Open Energy Info (EERE)

    Renewable Energy Product: Persimmon is a private equity fund established in 2008 to invest in renewable energy firms. References: Persimmon Tree Capital1 This article is a...

  14. Environmental Capital Partners LLC | Open Energy Information

    Open Energy Info (EERE)

    Partners LLC Jump to: navigation, search Name: Environmental Capital Partners LLC Place: New York, New York Zip: 10017 Sector: Services Product: Private equity firm funded with USD...

  15. Global Capital Finance | Open Energy Information

    Open Energy Info (EERE)

    Finance Jump to: navigation, search Name: Global Capital Finance Place: Purchase, New York Zip: 10577 Sector: Renewable Energy, Services Product: New York-based international...

  16. Environmental Capital Group LLC | Open Energy Information

    Open Energy Info (EERE)

    Group LLC Jump to: navigation, search Name: Environmental Capital Group LLC Place: Grass Valley, California Zip: 95945 Product: String representation "Environmental C ... tartup...

  17. Energy Capital Investments | Open Energy Information

    Open Energy Info (EERE)

    Investments Jump to: navigation, search Name: Energy Capital Investments Place: Phoenix, Arizona Zip: 85016 Product: An investment firm established by Najafi Companies with the...

  18. Solar Capital Inc | Open Energy Information

    Open Energy Info (EERE)

    Inc Jump to: navigation, search Name: Solar Capital Inc Place: Benicia, California Zip: 94510 Sector: Solar Product: Start-up investment firm seeking control positions in companies...

  19. Capital Electric Coop, Inc | Open Energy Information

    Open Energy Info (EERE)

    Capital Electric Coop, Inc Place: North Dakota Phone Number: 1.701.223.1513 Website: capitalelec.com Facebook: https:www.facebook.comcapitalelectricnd?refhl Outage Hotline:...

  20. RAM Capital Management Group | Open Energy Information

    Open Energy Info (EERE)

    Hydrogen Product: Private VC fund and investment banking advisory firm investing in fuel cells and hydrogen. References: RAM Capital Management Group1 This article is a...

  1. Capital Energy SL | Open Energy Information

    Open Energy Info (EERE)

    search Name: Capital Energy SL Place: Madrid, Spain Zip: 28016 Sector: Solar, Wind energy Product: Offshore wind farm, solar and biodiesel plant developer. Coordinates:...

  2. Capital Cooking: Proposed Penalty (2014-CE-23008)

    Broader source: Energy.gov [DOE]

    DOE alleged in a Notice of Proposed Civil Penalty that Capital Cooking Equipment, Inc. failed to certify cooking products as compliant with the applicable energy conservation standards.

  3. Human Capital Management Accountability Program (HCMAP) | Department...

    Broader source: Energy.gov (indexed) [DOE]

    Human Capital Management Accountability Program (HCMAP) is an online program which serves ... and financial HR metrics that assist human resources professionals in identifying ...

  4. Human Capital Organization | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Human Capital Officer provides leadership to the Department of Energy (DOE) on the impact and use of policies, proposals, programs, and partnerships related to all aspects of Human ...

  5. Human Capital Management Accountability Program (HCMAP)

    Broader source: Energy.gov [DOE]

    Human Capital Management Accountability Program (HCMAP) is an online program which serves as the vehicle for identifying and measuring these three factors, effectiveness, efficiency, and timeliness...

  6. Geothermal power plant R and D: an analysis of cost-performance tradeoffs and the Heber Binary-Cycle Demonstration Project

    SciTech Connect (OSTI)

    Cassel, T.A.V.; Amundsen, C.B.; Blair, P.D.

    1983-06-30

    A study of advancements in power plant designs for use at geothermal resources in the low to moderate (300 to 400F) temperature range is reported. In 3 case studies, the benefits of R and D to achieve these advancements are evaluated in terms of expected increases in installed geothermal generating capacity over the next 2 decades. A parametric sensitivity study is discussed which analyzes differential power development for combinations of power plant efficiency and capitol cost. Affordable tradeoffs between plant performance and capital costs are illustrated. The independent review and analysis of the expected costs of construction, operation and maintenance of the Heber Binary Cycle Geothermal Power Demonstration Plant are described. Included in this assessment is an analysis of each of the major cost components of the project, including (1) construction cost, (2) well field development costs, (3) fluid purchase costs, and (4) well field and power plant operation and maintenance costs. The total cost of power generated from the Heber Plant (in terms of mills per kWh) is then compared to the cost of power from alternative fossil-fueled base load units. Also evaluated are the provisions of both: (a) the Cooperative Agreement between the federal government and San Diego Gas and Electric (SDG and E); and (b) the Geothermal Heat Sales Contract with Union Oil Company.

  7. Natural Gas Vehicle Cost Calculator | Open Energy Information

    Open Energy Info (EERE)

    Vehicle Cost Calculator Jump to: navigation, search Tool Summary LAUNCH TOOL Name: Natural Gas Vehicle Cost Calculator AgencyCompany Organization: United States Department of...

  8. EA-184-B MORGAN STANLEY CAPITAL GROUP | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    -B MORGAN STANLEY CAPITAL GROUP EA-184-B MORGAN STANLEY CAPITAL GROUP Order authorizing Morgan Stanley Capital Group to export electric energy to Mexico. EA-184-B MSCG MX.pdf ...

  9. Agri capital GmbH | Open Energy Information

    Open Energy Info (EERE)

    capital GmbH Jump to: navigation, search Name: agri.capital GmbH Place: Muenster, North Rhine-Westphalia, Germany Zip: 48155 Product: Muenster-based agri.capital develops and...

  10. BluePlanet Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    BluePlanet Capital LLC Jump to: navigation, search Name: BluePlanet Capital LLC Place: Washington, Connecticut Zip: 6793 Sector: Services Product: BluePlanet Capital is an...

  11. BPA's Costs

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    links Financial Information Financial Public Processes Asset Management Cost Verification Process Rate Cases BP-18 Rate Case Related Publications Meetings and Workshops Customer...

  12. Estimating Renewable Energy Economic Potential in the United States. Methodology and Initial Results

    SciTech Connect (OSTI)

    Brown, Austin; Beiter, Philipp; Heimiller, Donna; Davidson, Carolyn; Denholm, Paul; Melius, Jennifer; Lopez, Anthony; Hettinger, Dylan; Mulcahy, David; Porro, Gian

    2015-07-30

    This report describes a geospatial analysis method to estimate the economic potential of several renewable resources available for electricity generation in the United States. Economic potential, one measure of renewable generation potential, may be defined in several ways. For example, one definition might be expected revenues (based on local market prices) minus generation costs, considered over the expected lifetime of the generation asset. Another definition might be generation costs relative to a benchmark (e.g., a natural gas combined cycle plant) using assumptions of fuel prices, capital cost, and plant efficiency. Economic potential in this report is defined as the subset of the available resource technical potential where the cost required to generate the electricity (which determines the minimum revenue requirements for development of the resource) is below the revenue available in terms of displaced energy and displaced capacity. The assessment is conducted at a high geospatial resolution (more than 150,000 technology-specific sites in the continental United States) to capture the significant variation in local resource, costs, and revenue potential. This metric can be a useful screening factor for understanding the economic viability of renewable generation technologies at a specific location. In contrast to many common estimates of renewable energy potential, economic potential does not consider market dynamics, customer demand, or most policy drivers that may incent renewable energy generation.

  13. Microsoft PowerPoint - Crouther.HumanCapitalInitiatives.042909

    Office of Environmental Management (EM)

    Human Capital Initiatives Presented to the Environmental Management Advisory Board (EMAB) By Desi Crouther, Acting Director Office of Human Capital Office of Environmental Management ...

  14. Grupo Maris Capital ethanol refinery | Open Energy Information

    Open Energy Info (EERE)

    Maris Capital ethanol refinery Jump to: navigation, search Name: Grupo Maris (Capital ethanol refinery) Place: Nuporanga, Brazil Product: 32,000 m3 ethanol refinery owner...

  15. Carbon Credit Capital and Feedback Ventures JV | Open Energy...

    Open Energy Info (EERE)

    Capital and Feedback Ventures JV Jump to: navigation, search Name: Carbon Credit Capital and Feedback Ventures JV Place: India Sector: Carbon Product: String representation "Carbon...

  16. Program & Project Management For The Acquisition Of Capital Assets...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets 2014 DOE Project Management Workshop ...

  17. Maryland-National Capital Building Industry Association Regulatory...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Maryland-National Capital Building Industry Association Regulatory Burden RFI (Federal Register August 8, 2012) Maryland-National Capital Building Industry Association Regulatory ...

  18. Energy and Environmental Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital LLC Jump to: navigation, search Name: Energy and Environmental Capital LLC Place: Washington, DC Sector: Carbon Product: The company focuses on carbon trading in ex-Soviet...

  19. BlueWave Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    BlueWave Capital LLC Jump to: navigation, search Name: BlueWave Capital LLC Place: Boston, Massachusetts Sector: Renewable Energy Product: Knowledge-based investment firm focused...

  20. MissionPoint Capital Partners | Open Energy Information

    Open Energy Info (EERE)

    MissionPoint Capital Partners Jump to: navigation, search Name: MissionPoint Capital Partners Place: Norwalk, Connecticut Zip: CT 06854 Product: Private Investment company...

  1. Sustainable Energy Capital Partners SECP | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners SECP Jump to: navigation, search Name: Sustainable Energy Capital Partners (SECP) Place: Santa Ana, California Zip: 92705 Sector: Renewable Energy Product:...

  2. Program & Project Management For The Acquisition Of Capital Assets...

    Broader source: Energy.gov (indexed) [DOE]

    More Documents & Publications Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets PARS II...

  3. DTE Energy Venture formerly EdVenture Capital Corporation | Open...

    Open Energy Info (EERE)

    Venture formerly EdVenture Capital Corporation Jump to: navigation, search Name: DTE Energy Venture (formerly EdVenture Capital Corporation) Place: Detroit, Michigan Zip: 48226...

  4. Noventi Venture Capital formerly CIR Ventures | Open Energy Informatio...

    Open Energy Info (EERE)

    Noventi Venture Capital formerly CIR Ventures Jump to: navigation, search Name: Noventi Venture Capital (formerly CIR Ventures) Place: Menlo Park, California Zip: CA 94025 Product:...

  5. RockPort Capital Partners (Massachusetts) | Open Energy Information

    Open Energy Info (EERE)

    RockPort Capital Partners (Massachusetts) Name: RockPort Capital Partners (Massachusetts) Address: 160 Federal Street, 18th Floor Place: Boston, Massachusetts Zip: 02110 Region:...

  6. Sinopec Beijing Capital Sci Tech Group JV | Open Energy Information

    Open Energy Info (EERE)

    Sinopec Beijing Capital Sci Tech Group JV Jump to: navigation, search Name: Sinopec & Beijing Capital Sci Tech Group JV Place: Beijing Municipality, China Product: China-based...

  7. Acro Energy Technologies formerly Lonestar Capital | Open Energy...

    Open Energy Info (EERE)

    Energy Technologies formerly Lonestar Capital Jump to: navigation, search Name: Acro Energy Technologies (formerly Lonestar Capital) Place: Oakdale, California Zip: 95361 Sector:...

  8. Green Capital Consulting Company GCCC | Open Energy Information

    Open Energy Info (EERE)

    Consulting Company GCCC Jump to: navigation, search Name: Green Capital Consulting Company (GCCC) Place: Beijing, China Zip: 100022 Product: Green Capital Consulting Company (GCCC)...

  9. IFCI Venture Capital Funds Ltd | Open Energy Information

    Open Energy Info (EERE)

    IFCI Venture Capital Funds Ltd Jump to: navigation, search Name: IFCI Venture Capital Funds Ltd Place: New Delhi, Delhi (NCT), India Zip: 110019 Product: Manager of several funds...

  10. Clean World Capital A S | Open Energy Information

    Open Energy Info (EERE)

    World Capital A S Jump to: navigation, search Name: Clean World Capital AS Place: Lyngby, Denmark Sector: Carbon Product: A cleantech finance house based in Copenhagen and London....

  11. CE2 Capital Partners LLC | Open Energy Information

    Open Energy Info (EERE)

    Capital Partners LLC Jump to: navigation, search Name: CE2 Capital Partners LLC Place: Solana Beach, California Zip: 92075 Sector: Carbon, Renewable Energy Product:...

  12. Low Capital Photovoltaic Panel Electrical Output-Booster System...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Low Capital Photovoltaic Panel Electrical Output-Booster System Low Capital Photovoltaic Panel Electrical Output-Booster System This presentation summarizes the information given ...

  13. TianDi Growth Capital | Open Energy Information

    Open Energy Info (EERE)

    Venture capital investor interested in projects in Wind energy, Electric vehicles, Energy-efficient lighting, Biodiesel and Clean water. References: TianDi Growth Capital1...

  14. Manager's Desk Reference on Human Capital Management Flexibilities...

    Broader source: Energy.gov (indexed) [DOE]

    that can be used in day-to-day human capital management activities, especially ... Manager's Desk Reference on Human Capital Management Flexibilities (640.69 KB) Responsible ...

  15. DOE Strategic Human Capital Plan | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    The current Strategic Human Capital Plan (SHCP) sets forth the framework for managing the Department of Energy's (DOE) human capital system through 2020. This Plan, which replaces ...

  16. Office of the Chief Human Capital Officer (HC-1) | Department...

    Broader source: Energy.gov (indexed) [DOE]

    HC-1 Mission and Function Statement The Office of the Chief Human Capital Officer (HC) ... agreementsrelationships related to all aspects of Human Capital Management (HCM). ...

  17. EGov PMA Scorecard Cost, Schedule & Performance Standard.tif | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Energy EGov PMA Scorecard Cost, Schedule & Performance Standard.tif EGov PMA Scorecard Cost, Schedule & Performance Standard.tif EGov PMA Scorecard Cost, Schedule & Performance Standard.tif (1.8 MB) More Documents & Publications Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets Program & Project Management For The Acquisition Of Capital Assets

  18. Cost of presumptive source term Remedial Actions Laboratory for energy-related health research, University of California, Davis

    SciTech Connect (OSTI)

    Last, G.V.; Bagaasen, L.M.; Josephson, G.B.; Lanigan, D.C.; Liikala, T.L.; Newcomer, D.R.; Pearson, A.W.; Teel, S.S.

    1995-12-01

    A Remedial Investigation/Feasibility Study (RI/FS) is in progress at the Laboratory for Energy Related Health Research (LEHR) at the University of California, Davis. The purpose of the RI/FS is to gather sufficient information to support an informed risk management decision regarding the most appropriate remedial actions for impacted areas of the facility. In an effort to expedite remediation of the LEHR facility, the remedial project managers requested a more detailed evaluation of a selected set of remedial actions. In particular, they requested information on both characterization and remedial action costs. The US Department of Energy -- Oakland Office requested the assistance of the Pacific Northwest National Laboratory to prepare order-of-magnitude cost estimates for presumptive remedial actions being considered for the five source term operable units. The cost estimates presented in this report include characterization costs, capital costs, and annual operation and maintenance (O&M) costs. These cost estimates are intended to aid planning and direction of future environmental remediation efforts.

  19. Realistic costs of carbon capture

    SciTech Connect (OSTI)

    Al Juaied, Mohammed . Belfer Center for Science and International Affiaris); Whitmore, Adam )

    2009-07-01

    There is a growing interest in carbon capture and storage (CCS) as a means of reducing carbon dioxide (CO2) emissions. However there are substantial uncertainties about the costs of CCS. Costs for pre-combustion capture with compression (i.e. excluding costs of transport and storage and any revenue from EOR associated with storage) are examined in this discussion paper for First-of-a-Kind (FOAK) plant and for more mature technologies, or Nth-of-a-Kind plant (NOAK). For FOAK plant using solid fuels the levelised cost of electricity on a 2008 basis is approximately 10 cents/kWh higher with capture than for conventional plants (with a range of 8-12 cents/kWh). Costs of abatement are found typically to be approximately US$150/tCO2 avoided (with a range of US$120-180/tCO2 avoided). For NOAK plants the additional cost of electricity with capture is approximately 2-5 cents/kWh, with costs of the range of US$35-70/tCO2 avoided. Costs of abatement with carbon capture for other fuels and technologies are also estimated for NOAK plants. The costs of abatement are calculated with reference to conventional SCPC plant for both emissions and costs of electricity. Estimates for both FOAK and NOAK are mainly based on cost data from 2008, which was at the end of a period of sustained escalation in the costs of power generation plant and other large capital projects. There are now indications of costs falling from these levels. This may reduce the costs of abatement and costs presented here may be 'peak of the market' estimates. If general cost levels return, for example, to those prevailing in 2005 to 2006 (by which time significant cost escalation had already occurred from previous levels), then costs of capture and compression for FOAK plants are expected to be US$110/tCO2 avoided (with a range of US$90-135/tCO2 avoided). For NOAK plants costs are expected to be US$25-50/tCO2. Based on these considerations a likely representative range of costs of abatement from CCS excluding

  20. Economic effects of fracture in the United States. Part 1. A synopsis of the September 30, 1982 report to NBS by Battelle Columbus Laboratories

    SciTech Connect (OSTI)

    Reed, R.P.; Smith, J.H.; Christ, B.W.

    1983-03-01

    The National Bureau of Standards and Battelle Columbus Laboratories (BCL) have completed a study to assess the costs of material fracture to the United States for the year 1978. This exhaustive assessment used the econometric input-output model to identify contributions from the entire US economy. The study included all materials and all types of structures and included both fracture occurrence and fracture prevention costs. The costs were large. In 1982 dollars the total cost was estimated to be $119 billion per year, about 4 percent of the gross national product. An estimated $35 billion per year could be saved through the use of currently available technology. Costs could be further reduced by as much as $28 billion per year through fracture-related research. The costs are primarily associated with the transportation and construction industries: motor vehicles, aircraft, and the building of homes and non-residential construction. Metal structures contributed substantially larger costs than non-metal structures. A greater percentage of these costs were expended on fracture prevention than on fracture occurrence. The study concluded that substantial material, transportation, and capital investment costs could be saved if technology transfer, combined with research and development, succeeded in reducing the factors of uncertainty related to structural design. Equally safe or safer structures could be produced with substantial cost savings in material, transportation, and capital investment. This could be done by reducing the uncertainty currently related to structural design through better predictions of structural performance from materials properties, better process and quality control and in-service flaw monitoring, and less materials variability.

  1. Capital Equity Partners LLC | Open Energy Information

    Open Energy Info (EERE)

    Partners LLC Jump to: navigation, search Name: Capital Equity Partners LLC Address: 410 Park Avenue Place: New York, New York Zip: 10022 Region: Northeast - NY NJ CT PA Area...

  2. Cora Capital Advisors LLC | Open Energy Information

    Open Energy Info (EERE)

    Advisors LLC Jump to: navigation, search Name: Cora Capital Advisors LLC Place: New York, New York Zip: 10022 Sector: Renewable Energy Product: New York-based investment bank and...

  3. Capital Equipment Validation Form | The Ames Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capital Equipment Validation Form Version Number: 2.0 Document Number: Form 48100.001 Effective Date: 02/2015 File (public): Office spreadsheet icon form_48100.001_rev2.xls

  4. 2011-2015 Human Capital Management Plan

    Broader source: Energy.gov [DOE]

    The Office of Legacy Management (LM) needs skilled and engaged staff to accomplish our mission and carry out our responsibilities to the American people. This Human Capital Management Plan (HCMP or...

  5. 2016-2020 Strategic Human Capital Plan

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    the Chief Human Capital Officer 2016-2020 Strategic Human Capital Plan Cover Photo Description Beyond Double-Pane Windows While the invention of double-pane windows dates back to 1935, a true turning point in the technology came in the 1980s with a collaboration between the Department of Energy, private industry, and Lawrence Berkeley National Lab. Initial research and development by Berkeley Lab and a start-up company, Suntek Research Associates (now called Southwall Technologies), led to the

  6. Understanding Cost Growth and Performance Shortfalls in Pioneer Process

    Office of Environmental Management (EM)

    Plants | Department of Energy Cost Growth and Performance Shortfalls in Pioneer Process Plants Understanding Cost Growth and Performance Shortfalls in Pioneer Process Plants This report presents an empirical and quantitative analysis of the misestimation of the capital costs and performance of innovative energy process plants and other chemical process facilities that create fundamental problems for government and industry in planning the development and commercialization of such plants.

  7. Building Life Cycle Cost Programs | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Building Life Cycle Cost Programs Building Life Cycle Cost Programs The National Institute of Standards and Technology (NIST) developed the Building Life Cycle Cost (BLCC) Programs to provide computational support for the analysis of capital investments in buildings. They include BLCC5, the Energy Escalation Rate Calculator, Handbook 135, and the Annual Supplement to Handbook 135. BLCC5 Program Register and download. BLCC 5.3-15 (for Windows or Mac OS X). BLCC version 5.3-15 contains the

  8. Building Life Cycle Cost Programs | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Building Life Cycle Cost Programs Building Life Cycle Cost Programs The National Institute of Standards and Technology (NIST) developed the Building Life Cycle Cost (BLCC) Programs to provide computational support for the analysis of capital investments in buildings. They include BLCC5, the Energy Escalation Rate Calculator, Handbook 135, and the Annual Supplement to Handbook 135. BLCC5 Program Register and download. BLCC 5.3-15 (for Windows or Mac OS X). BLCC version 5.3-15 contains the

  9. WREF 2012: THE PAST AND FUTURE COST OF WIND ENERGY

    SciTech Connect (OSTI)

    NREL,; Wiser, Ryan; Lantz, Eric; Hand, Maureen

    2012-03-26

    The future of wind power will depend on the ability of the industry to continue to achieve cost reductions. To better understand the potential for cost reductions, this report provides a review of historical costs, evaluates near-term market trends, and summarizes the range of projected costs. It also notes potential sources of future cost reductions. Our findings indicate that steady cost reductions were interrupted between 2004 and 2010, but falling turbine prices and improved turbine performance are expected to drive a historically low LCOE for current installations. In addition, the majority of studies indicate continued cost reductions on the order of 20%-30% through 2030. Moreover, useful cost projections are likely to benefit from stronger consideration of the interactions between capital cost and performance as well as trends in the quality of the wind resource where projects are located, transmission, grid integration, and other cost variables.

  10. Floating oil production unit slated in small field off Gabon

    SciTech Connect (OSTI)

    Not Available

    1991-10-14

    This paper reports on the first U.S. tanker converted to a floating production, storage, and offloading (FPSO) unit which takes up station in Gombe-Beta field off Gabon by Dec. 1. FPSO Ocean Producer will work under a 3 year, day rate contract let late in 1990 by Amoco-Gabon Bombe Marin co., a unit of Amoco Production Co. (OGJ, Dec. 24, 1990, p. 27). Gombe-Beta field is in the Atlantic Ocean about 70 miles south of Port Gentil, Gabon. Ocean Producer will be moored in 50 ft of water 3.7 miles off Gabon, with Bombe-Beta's unmanned production platform about 820 ft astern. The vessel will be held in position by a disconnectable, asymmetric, six point, spread mooring system, It is owned and operated by Oceaneering International Services Ltd. (OISL). Affiliate Oceaneering Production Systems (OPS) converted the 78,061 dwt oil tanker MT Baltimore Sea at a capital cost of $25 million at Gulf Copper Manufacturing Corp.'s Port Arthur, Tex., shipyard. Both companies are units of Oceaneering International Inc., Houston. OPS the Ocean Producer's use in Gombe-Beta field is the shallowest water FPSO application in the world. Amoco-Gabon chose an FPSO production system for Gombe-Beta because it expects the remote field to have a short economic life, and the oil requires extensive processing.

  11. Trends in U.S. Oil and Natural Gas Upstream Costs

    Reports and Publications (EIA)

    2016-01-01

    Average 2015 well drilling and completion costs in five onshore areas decline 25% and 30% below their level in 2012 The U.S. Energy Information Administration (EIA) commissioned IHS Global Inc. (IHS) to perform a study of upstream drilling and production costs. The IHS report assesses capital and operating costs associated with drilling, completing, and operating wells and facilities.

  12. Load Leveling Battery System Costs

    Energy Science and Technology Software Center (OSTI)

    1994-10-12

    SYSPLAN evaluates capital investment in customer side of the meter load leveling battery systems. Such systems reduce the customer's monthly electrical demand charge by reducing the maximum power load supplied by the utility during the customer's peak demand. System equipment consists of a large array of batteries, a current converter, and balance of plant equipment and facilities required to support the battery and converter system. The system is installed on the customer's side of themore » meter and controlled and operated by the customer. Its economic feasibility depends largely on the customer's load profile. Load shape requirements, utility rate structures, and battery equipment cost and performance data serve as bases for determining whether a load leveling battery system is economically feasible for a particular installation. Life-cycle costs for system hardware include all costs associated with the purchase, installation, and operation of battery, converter, and balance of plant facilities and equipment. The SYSPLAN spreadsheet software is specifically designed to evaluate these costs and the reduced demand charge benefits; it completes a 20 year period life cycle cost analysis based on the battery system description and cost data. A built-in sensitivity analysis routine is also included for key battery cost parameters. The life cycle cost analysis spreadsheet is augmented by a system sizing routine to help users identify load leveling system size requirements for their facilities. The optional XSIZE system sizing spreadsheet which is included can be used to identify a range of battery system sizes that might be economically attractive. XSIZE output consisting of system operating requirements can then be passed by the temporary file SIZE to the main SYSPLAN spreadsheet.« less

  13. Factory Cost Model

    Energy Science and Technology Software Center (OSTI)

    1996-12-17

    The Factory Cost Model (FCM) is an economic analysis tool intended to provide flat panel display (FPD) and other similar discrete component manufacturers with the ability to make first-order estimates of the cost of unit production. This software has several intended uses. Primary among these is the ability to provide first-order economic analysis for future factories. Consequently, the model requires a minimal level of input detail, and accomodates situations where actual production data are notmore » available. This software is designed to be activity based such that most of the calculated direct costs are associated with the steps of a manufacturibg process. The FCM architecture has the ability to accomodate the analysis of existing manufacturing facilities. The FCM can provide assistance with strategic economic decisions surrounding production related matters. For instance, the program can project the effect on costs and resources of a new product''s introduction, or it can assess the potential cost reduction produced by step yield improvements in the manufacturing process.« less

  14. United Nations Population Information Network | Open Energy Informatio...

    Open Energy Info (EERE)

    Focus Area: People and Policy Resource Type: Dataset Website: www.un.orgpopin Cost: Free United Nations Population Information Network Screenshot References: United Nations...

  15. An Evaluation of the Total Cost of Ownership of Fuel Cell-Powered Material

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Handling Equipment | Department of Energy An Evaluation of the Total Cost of Ownership of Fuel Cell-Powered Material Handling Equipment An Evaluation of the Total Cost of Ownership of Fuel Cell-Powered Material Handling Equipment This report by the National Renewable Energy Laboratory discusses an analysis of the total cost of ownership of fuel cell-powered and traditional battery-powered material handling equipment, including the capital costs of battery and fuel cell systems, the cost of

  16. Wind Levelized Cost of Energy: A Comparison of Technical and Financing Input Variables

    SciTech Connect (OSTI)

    Cory, K.; Schwabe, P.

    2009-10-01

    The expansion of wind power capacity in the United States has increased the demand for project development capital. In response, innovative approaches to financing wind projects have emerged and are proliferating in the U.S. renewable energy marketplace. Wind power developers and financiers have become more efficient and creative in structuring their financial relationships, and often tailor them to different investor types and objectives. As a result, two similar projects may use very different cash flows and financing arrangements, which can significantly vary the economic competitiveness of wind projects. This report assesses the relative impact of numerous financing, technical, and operating variables on the levelized cost of energy (LCOE) associated with a wind project under various financing structures in the U.S. marketplace. Under this analysis, the impacts of several financial and technical variables on the cost of wind electricity generation are first examined individually to better understand the relative importance of each. Then, analysts examine a low-cost and a high-cost financing scenario, where multiple variables are modified simultaneously. Lastly, the analysis also considers the impact of a suite of financial variables versus a suite of technical variables.

  17. Understanding coal quality and its relationship to power plant performance and costs

    SciTech Connect (OSTI)

    Jennison, K.D.; Stallard, G.S.

    1995-12-01

    The availability of reliable, reasonably priced energy is a necessary cornerstone for established and emerging economies. In addition to addressing coal quality issues strictly at a plant level, it is now prudent to consider long-term performance and economics of particular fuel sources to be selected in the light of system economics and reliability. In order to evaluate coal quality issues in a more comprehensive manner, it is important to develop both an approach and a set of tools which can support the various phases of the planning/analysis processes. The processes must consider the following: (1) Cost/availability of other potential coal supplies, including {open_quotes}raw{close_quotes} domestic sources, {open_quotes}cleaned {close_quotes} domestic sources, and other internationally marketed coals. (2) Power plant performance issues as function of plant design and fuel properties. (3) System expansion plans, candidate technologies, and associated capital and operating costs. (4) Projected load demand, for system and for individual units within the system. (5) Legislative issues such as environmental pressures, power purchase agreements, etc. which could alter the solution. (6) Economics of potential plans/strategies based on overall cost-effectiveness of the utility system, not just individual units. (7) Anticipated unit configuration, including addition of environmental control equipment or other repowering options. The Coal Quality Impact Model (CQIM{trademark}) is a PC-based computer program capable of predicting coal-related cost and performance impacts at electric power generating sites. The CQIM was developed for EPRI by Black & Veatch and represents over a decade of effort geared toward developing an extensible state-of-the-art coal quality assessment tool. This paper will introduce CQIM, its capabilities, and its application to Eastern European coal quality assessment needs.

  18. levelized costs

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    levelized costs - Sandia Energy Energy Search Icon Sandia Home Locations Contact Us Employee Locator Energy & Climate Secure & Sustainable Energy Future Stationary Power Energy Conversion Efficiency Solar Energy Wind Energy Water Power Supercritical CO2 Geothermal Natural Gas Safety, Security & Resilience of the Energy Infrastructure Energy Storage Nuclear Power & Engineering Grid Modernization Battery Testing Nuclear Energy Defense Waste Management Programs Advanced Nuclear

  19. Cost Contributors to Geothermal Power Production

    SciTech Connect (OSTI)

    Nathwani, Jay; Mines, Greg

    2011-07-01

    The US Department of Energy Geothermal Technologies Office (DOE-GTO) has developed the tool Geothermal Electricity Technologies Evaluation Model (GETEM) to assess the levelized cost of electricity (LCOE) of power produced from geothermal resources. Recently modifications to GETEM allow the DOE-GTO to better assess how different factors impact the generation costs, including initial project risk, time required to complete a development, and development size. The model characterizes the costs associated with project risk by including the costs to evaluate and drill those sites that are considered but not developed for commercial power generation, as well as to assign higher costs to finance those activities having more risk. This paper discusses how the important parameters impact the magnitude project costs for different project scenarios. The cost distributions presented include capital cost recovery for the exploration, confirmation, well field completion and power plant construction, as well as the operation and maintenance (O&M) costs. The paper will present these cost distributions for both EGS and hydrothermal resources.

  20. Rural electric cooperatives and the cost structure of the electric power industry: A multiproduct analysis

    SciTech Connect (OSTI)

    Berry, D.M.

    1992-01-01

    Since 1935, the federal government of the United States has administered a program designed to make electricity available to rural Americans. This dissertation traces the history of the rural electrification program, as well as its costs. While the Congress intended to simply provide help in building the capital structure of rural electric distribution systems, the program continues to flourish some 35 years after these systems first fully covered the countryside. Once the rural distribution systems were built, the government began to provide cooperatives with billions of dollars in subsidized loans for the generation of electric power. Although this program costs the taxpayers nearly $1 billion per year, no one has ever tested its efficacy. The coops' owner/members do not have the right to trade their individual ownership shares. The RECs do not fully exploit the scale and scope economies observed in the investor-owned sector of this industry. This dissertation compares the relative productive efficiencies of the RECs and the investor-owned electric utilities (IOUs) in the United States. Using multiproduct translog cost functions, the estimated costs of cooperatives are compared to those of IOUs in providing identical output bundles. Three separate products are considered as outputs: (1) wholesale power; (2) power sold to large industrial customers; and (3) power sold to residential and commercial customers. It is estimated that, were the RECs forced to pay market prices for their inputs, their costs would exceed those incurred by the IOUs by about 24 percent. Several policy recommendations are made: (1) the RECs should be converted to stockholder-owned, tax-paying corporations; (2) the government should discontinue its subsidized loan program; (3) the government should sell its hydroelectric power at market prices, nullifying the current preference given to cooperatives and municipal distributors in the purchase of this currently underpriced power.

  1. Support for Cost Analyses on

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    35 Hartwell Ave Lexington, MA 02421 Support for Cost Analyses on Solar-Driven High Temperature Thermochemical Water-Splitting Cycles Final Report to: Department of Energy Order DE-DT0000951 Report prepared by TIAX LLC Reference D0535 February 22, 2011 Matt Kromer (Principal Investigator) Kurt Roth Rosalind Takata Paul Chin Copyright 2011, TIAX LLC Notice: This report was prepared as an account of work sponsored by an agency of the United States government. Neither the United States government

  2. Least cost options for life extension

    SciTech Connect (OSTI)

    Davis, F.; Bradaric, M.

    1995-12-01

    Rehabilitation of existing electric generating capacity offers one of the most cost-effective ways of meeting near-term power needs in many Eastern and Central European countries. In particular, the uncertainty associated with other supply sources and severe capital constraints tends to favor investments which maximize the utilization of existing fossil-fired equipment. However, it is critical that least-cost planning principles, including the consideration of environmental impacts, be applied to the economic analysis of rehabilitation options. This paper draws on Bechtel`s experience in applying least-cost planning to plant rehabilitation studies in Bulgaria, Romania and Slovakia. The examples provided illustrate the importance of least-cost planning and the effect of the value placed on environmental emissions.

  3. CE2 Carbon Capital LLC | Open Energy Information

    Open Energy Info (EERE)

    Carbon Capital LLC Jump to: navigation, search Name: CE2 Carbon Capital LLC Place: California Sector: Carbon, Renewable Energy Product: US-based carbon trader that looks to take...

  4. Capital Asset Project List_rev1.xls

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... by DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets. ... Start of Operations or Project Completion Capital Asset Project List 1152016 1 of 1

  5. Marathon Capital LLC (New York) | Open Energy Information

    Open Energy Info (EERE)

    Marathon Capital LLC (New York) Name: Marathon Capital LLC (New York) Address: 245 Park Avenue, 24th Floor Place: New York, New York Zip: 10167 Region: Northeast - NY NJ CT PA Area...

  6. FreshTracks Capital LP | Open Energy Information

    Open Energy Info (EERE)

    FreshTracks Capital LP Jump to: navigation, search Name: FreshTracks Capital LP Address: 29 Harbor Road, Suite 200 Place: Shelburne, New Hampshire Zip: 05482 Product: Venture...

  7. NewWorld Capital Group LLC | Open Energy Information

    Open Energy Info (EERE)

    NewWorld Capital Group LLC Jump to: navigation, search Name: NewWorld Capital Group LLC Place: New York, New York Zip: 10022 Sector: Efficiency Product: New York-based private...

  8. BioLogical Capital BLC | Open Energy Information

    Open Energy Info (EERE)

    BioLogical Capital BLC Jump to: navigation, search Name: BioLogical Capital (BLC) Place: Denver, Colorado Zip: 80202 Product: Denver Colorado-based group focusing on generating...

  9. CO2e Capital Limited | Open Energy Information

    Open Energy Info (EERE)

    e Capital Limited Jump to: navigation, search Name: CO2e Capital Limited Place: New York City, New York Zip: 10022 Product: New York based merchant bank focused on reducing global...

  10. Morgan Stanley Capital Grp Inc | Open Energy Information

    Open Energy Info (EERE)

    Capital Grp Inc Jump to: navigation, search Name: Morgan Stanley Capital Grp Inc Place: New York References: EIA Form EIA-861 Final Data File for 2010 - File1a1 EIA Form 861...

  11. Office of Executive Resources Office of the Chief Human Capital...

    Broader source: Energy.gov (indexed) [DOE]

    Office of Executive Resources Office of the Chief Human Capital Officer U.S. Department of ... The request must be submitted to the Office of the Chief Human Capital Officer, Office of ...

  12. Office of Executive Resources Office of the Chief Human Capital...

    Broader source: Energy.gov (indexed) [DOE]

    Office of Executive Resources Office of the Chief Human Capital Officer U.S. Department of ... Chief Human Capital Officer (CHCO) and Office of Executive Resources (OER). (1) Develop ...

  13. Energy efficiency improvement and cost saving opportunities forpetroleum refineries

    SciTech Connect (OSTI)

    Worrell, Ernst; Galitsky, Christina

    2005-02-15

    The petroleum refining industry in the United States is the largest in the world, providing inputs to virtually any economic sector,including the transport sector and the chemical industry. The industry operates 146 refineries (as of January 2004) around the country,employing over 65,000 employees. The refining industry produces a mix of products with a total value exceeding $151 billion. Refineries spend typically 50 percent of cash operating costs (i.e., excluding capital costs and depreciation) on energy, making energy a major cost factor and also an important opportunity for cost reduction. Energy use is also a major source of emissions in the refinery industry making energy efficiency improvement an attractive opportunity to reduce emissions and operating costs. Voluntary government programs aim to assist industry to improve competitiveness through increased energy efficiency and reduced environmental impact. ENERGY STAR (R), a voluntary program managed by the U.S. Environmental Protection Agency, stresses the need for strong and strategic corporate energy management programs. ENERGY STAR provides energy management tools and strategies for successful corporate energy management programs. This Energy Guide describes research conducted to support ENERGY STAR and its work with the petroleum refining industry.This research provides information on potential energy efficiency opportunities for petroleum refineries. This Energy Guide introduces energy efficiency opportunities available for petroleum refineries. It begins with descriptions of the trends, structure, and production of the refining industry and the energy used in the refining and conversion processes. Specific energy savings for each energy efficiency measure based on case studies of plants and references to technical literature are provided. If available, typical payback periods are also listed. The Energy Guide draws upon the experiences with energy efficiency measures of petroleum refineries worldwide

  14. Energy prices and capital obsolescence: evidence from the oil embargo period

    SciTech Connect (OSTI)

    Gibbons, J.C.

    1984-01-01

    Energy costs replaced maintenance costs on existing fixed assets as a determinant of optimal retirement age after the 1973-74 oil embargo. The economic aging of manufacturing facilities was the product of both normal wear-and-tear and design obsolescence. The adjustment, however, was toward substitution of other factors for capital services and replacement of outmoded asset types by other more expensive ones. The author examines data derived from a dynamic regression model showing that between 8 and 10% of an aggregate plant of the US became obsolete as a result of the embargo. 9 references, 1 figure, 3 tables.

  15. EA-184 Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Morgan Stanley Capital Group Inc. EA-184 Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Mexico. EA-184 Morgan Stanley Capital Group Inc. (25.77 KB) More Documents & Publications EA-167 PG&E Energy Trading-Power, L.P EA-166 Duke Energy Trading and Marketing, L.L.C EA-181 H.Q Energy Services (U.S) Inc

  16. Program and Project Management for the Acquisition of Capital Assets |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Program and Project Management for the Acquisition of Capital Assets Program and Project Management for the Acquisition of Capital Assets This Order provides project management direction for the acquisition of capital assets that are delivered on schedule, within budget, and capable of meeting mission performance and environmental safety and health standards. Program and Project Management for the Acquisition of Capital Assets More Documents & Publications Guiding

  17. Guide to IT Capital Planning and Investment Control

    Energy Savers [EERE]

    Guide to IT Capital Planning and Investment Control April 2014 i TABLE OF CONTENTS TABLE OF CONTENTS ......

  18. Estimating Specialty Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Specialty costs are those nonstandard, unusual costs that are not typically estimated. Costs for research and development (R&D) projects involving new technologies, costs associated with future regulations, and specialty equipment costs are examples of specialty costs. This chapter discusses those factors that are significant contributors to project specialty costs and methods of estimating costs for specialty projects.

  19. Cost Study Manual

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    2 Cost Study Manual Executive Summary This Cost Study Manual documents the procedures for preparing a Cost Study to compare the cost of a contractor's employee benefits to the industry average from a broad-based national benefit cost survey. The annual Employee Benefits Cost Study Comparison (Cost Study) assists with the analysis of contractors' employee benefits costs. The Contracting Officer (CO) may require corrective action when the average benefit per capita cost or the benefit cost as a

  20. Wind Electrolysis: Hydrogen Cost Optimization

    SciTech Connect (OSTI)

    Saur, G.; Ramsden, T.

    2011-05-01

    This report describes a hydrogen production cost analysis of a collection of optimized central wind based water electrolysis production facilities. The basic modeled wind electrolysis facility includes a number of low temperature electrolyzers and a co-located wind farm encompassing a number of 3MW wind turbines that provide electricity for the electrolyzer units.

  1. A Review of Cost Estimation in New Technologies - Implications for Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Process Plants | Department of Energy A Review of Cost Estimation in New Technologies - Implications for Energy Process Plants A Review of Cost Estimation in New Technologies - Implications for Energy Process Plants This report reviews literature on cost estimation in several areas involving major capital expenditure programs: energy process plants, major weapons systems acquisition, public works and larger construction projects, and cost estimating techniques and problems for chemical

  2. Costs and benefits of pneumatic collection in three specific New York City cases

    SciTech Connect (OSTI)

    Miller, Benjamin; Spertus, Juliette; Kamga, Camille

    2014-11-15

    Highlights: • Pneumatic and truck collection were compared in three New York City locations. • Relative costs, energy use, and greenhouse gas emissions varied significantly. • Variations were due to location-specific factors (e.g., route density, truck type). • Under appropriate conditions, pneumatic collection reduces TMT, BTU, and GHG. • Pneumatic capex may be offset by operating savings and externality benefits. - Abstract: Truck-based collection of municipal solid waste imposes significant negative externalities on cities and constrains the efficiency of separate collection of recyclables and organics and of unit-price-based waste-reduction systems. In recent decades, hundreds of municipal-scale pneumatic collection systems have been installed in Europe and Asia. Relatively few prior studies have compared the economic or environmental impacts of these systems to those of truck collection. A critical factor to consider when making this comparison is the extent to which the findings reflect the specific geographic, demographic, and operational characteristics of the systems considered. This paper is based on three case studies that consider the specific characteristics of three locations, comparing pneumatic systems with conventional collection on the basis of actual waste tonnages, composition, sources, collection routes, truck trips, and facility locations. In one case, alternative upgrades to an existing pneumatic system are compared to a potential truck-collection operation. In the other cases, existing truck operations are compared to proposed pneumatic systems which, to reduce capital costs, would be installed without new trenching or tunneling through the use of existing linear infrastructure. For the two proposed retrofit pneumatic systems, up to 48,000 truck kilometers travelled would be avoided and energy use would be reduced by up to 60% at an incremental cost of up to $400,000 USD per year over the total operating-plus-capital cost of

  3. Assessing Coal Unit Retirement Risk

    U.S. Energy Information Administration (EIA) Indexed Site

    Ventures Analysis 1901 N. Moore St. Arlington, VA 22209 (703) 276 8900 A S S E S S I N G C O A L U N I T R E T I R E M E N T R I S K Tom Hewson Principal June 14, 2016 Presentation for the US Energy Information Administration Workshop Coal Fleet Aging 1 COAL CAPACITY CHALLENGES E N E R G Y V E N T U R E S A N A L Y S I S , I N C .  Environmental Regulatory Risk-- Compliance often requires coal units to make large capital investment in additional retrofit control measures and/or increase their

  4. NPR (New Production Reactor) capacity cost evaluation

    SciTech Connect (OSTI)

    1988-07-01

    The ORNL Cost Evaluation Technical Support Group (CETSG) has been assigned by DOE-HQ Defense Programs (DP) the task defining, obtaining, and evaluating the capital and life-cycle costs for each of the technology/proponent/site/revenue possibilities envisioned for the New Production Reactor (NPR). The first part of this exercise is largely one of accounting, since all NPR proponents use different accounting methodologies in preparing their costs. In order to address this problem of comparing ''apples and oranges,'' the proponent-provided costs must be partitioned into a framework suitable for all proponents and concepts. If this is done, major cost categories can then be compared between concepts and major cost differences identified. Since the technologies proposed for the NPR and its needed fuel and target support facilities vary considerably in level of technical and operational maturity, considerable care must be taken to evaluate the proponent-derived costs in an equitable manner. The use of cost-risk analysis along with derivation of single point or deterministic estimates allows one to take into account these very real differences in technical and operational maturity. Chapter 2 summarizes the results of this study in tabular and bar graph form. The remaining chapters discuss each generic reactor type as follows: Chapter 3, LWR concepts (SWR and WNP-1); Chapter 4, HWR concepts; Chapter 5, HTGR concept; and Chapter 6, LMR concept. Each of these chapters could be a stand-alone report. 39 refs., 36 figs., 115 tabs.

  5. Rough order of magnitude cost estimate for immobilization of 18.2 MT of plutonium using existing facilities at the Savannah River site: alternatives 3A/5A/6A/6B/7A/9A

    SciTech Connect (OSTI)

    DiSabatino, A., LLNL

    1998-06-01

    The purpose of this Cost Estimate Report is to identify preliminary capital and operating costs for a facility to immobilize 18.2 metric tons (nominal) of plutonium using ceramic in a new facility at Savannah River Site (SRS).

  6. Cost and Performance Assumptions for Modeling Electricity Generation Technologies

    SciTech Connect (OSTI)

    Tidball, Rick; Bluestein, Joel; Rodriguez, Nick; Knoke, Stu

    2010-11-01

    The goal of this project was to compare and contrast utility scale power plant characteristics used in data sets that support energy market models. Characteristics include both technology cost and technology performance projections to the year 2050. Cost parameters include installed capital costs and operation and maintenance (O&M) costs. Performance parameters include plant size, heat rate, capacity factor or availability factor, and plant lifetime. Conventional, renewable, and emerging electricity generating technologies were considered. Six data sets, each associated with a different model, were selected. Two of the data sets represent modeled results, not direct model inputs. These two data sets include cost and performance improvements that result from increased deployment as well as resulting capacity factors estimated from particular model runs; other data sets represent model input data. For the technologies contained in each data set, the levelized cost of energy (LCOE) was also evaluated, according to published cost, performance, and fuel assumptions.

  7. Property:EstimatedCostLowUSD | Open Energy Information

    Open Energy Info (EERE)

    Name EstimatedCostLowUSD Property Type Quantity Description the low estimate of cost in USD Use this type to express a monetary value in US Dollars. The default unit is one...

  8. Property:EstimatedCostHighUSD | Open Energy Information

    Open Energy Info (EERE)

    Name EstimatedCostHighUSD Property Type Quantity Description the high estimate of cost in USD Use this type to express a monetary value in US Dollars. The default unit is one...

  9. Property:EstimatedCostMedianUSD | Open Energy Information

    Open Energy Info (EERE)

    Name EstimatedCostMedianUSD Property Type Quantity Description the median estimate of cost in USD Use this type to express a monetary value in US Dollars. The default unit is one...

  10. Energy Efficiency Improvement and Cost Saving Opportunities for Breweries: An ENERGY STAR(R) Guide for Energy and Plant Managers

    SciTech Connect (OSTI)

    Galitsky, Christina; Martin, Nathan; Worrell, Ernst; Lehman, Bryan

    2003-09-01

    Annually, breweries in the United States spend over $200 million on energy. Energy consumption is equal to 38 percent of the production costs of beer, making energy efficiency improvement an important way to reduce costs, especially in times of high energy price volatility. After a summary of the beer making process and energy use, we examine energy efficiency opportunities available for breweries. We provide specific primary energy savings for each energy efficiency measure based on case studies that have implemented the measures, as well as references to technical literature. If available, we have also listed typical payback periods. Our findings suggest that given available technology, there are still opportunities to reduce energy consumption cost-effectively in the brewing industry. Brewers value highly the quality, taste and drinkability of their beer. Brewing companies have and are expected to continue to spend capital on cost-effective energy conservation measures that meet these quality, taste and drinkability requirements. For individual plants, further research on the economics of the measures, as well as their applicability to different brewing practices, is needed to assess implementation of selected technologies.

  11. 2013 Cost of Wind Energy Review

    SciTech Connect (OSTI)

    Mone, C.; Smith, A.; Maples, B.; Hand, M.

    2015-02-01

    This report uses representative project types to estimate the levelized cost of wind energy (LCOE) in the United States for 2013. Scheduled to be published on an annual basis, it relies on both market and modeled data to maintain a current understanding of wind generation cost trends and drivers. It is intended to provide insight into current component-level costs and a basis for understanding current component-level costs and a basis for understanding variability in the LCOE across the industry. Data and tools developed from this analysis are used to inform wind technology cost projections, goals, and improvement opportunities.

  12. Evaluation of the Total Cost of Ownership of Fuel Cell-Powered Material Handling Equipment

    SciTech Connect (OSTI)

    Ramsden, T.

    2013-04-01

    This report discusses an analysis of the total cost of ownership of fuel cell-powered and traditional battery-powered material handling equipment (MHE, or more typically 'forklifts'). A number of fuel cell MHE deployments have received funding support from the federal government. Using data from these government co-funded deployments, DOE's National Renewable Energy Laboratory (NREL) has been evaluating the performance of fuel cells in material handling applications. NREL has assessed the total cost of ownership of fuel cell MHE and compared it to the cost of ownership of traditional battery-powered MHE. As part of its cost of ownership assessment, NREL looked at a range of costs associated with MHE operation, including the capital costs of battery and fuel cell systems, the cost of supporting infrastructure, maintenance costs, warehouse space costs, and labor costs. Considering all these costs, NREL found that fuel cell MHE can have a lower overall cost of ownership than comparable battery-powered MHE.

  13. Program and Project Management for the Acquisition of Capital Assets (Informational Purposes Only)

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2016-01-11

    The purpose of this Order is to a) provide the Department of Energy (DOE) Elements, including the National Nuclear Security Administration (NNSA), with program and project management direction for the acquisition of capital assets with the goal of delivering projects within the original performance baseline (PB), cost and schedule, and fully capable of meeting mission performance, safeguards and security, and environmental, safety, and health requirements unless impacted by a directed change; and b) implement Office of Management and Budget (OMB) Circulars to include: A-11, Part 7, Capital Programming Guide, which prescribes new requirements and leading practices for project and acquisition management; A-123, Management's Responsibility for Internal Control, which defines management's responsibility for internal control in Federal agencies; and A-131, Value Engineering, which requires that all Federal agencies use Value Engineering (VE) as a management tool. The Page Change is a limited update to incorporate recent Secretarial policies and issues raised by external stakeholders.

  14. Retrofit costs for lime/limestone FGD and lime spray drying at coal-fired utility boilers

    SciTech Connect (OSTI)

    Emmel, T.E.; Jones, J.W.

    1990-01-01

    The paper gives results of a research program the objective of which was to significantly improve engineering cost estimates currently being used to evaluate the economic effects of applying SO2 controls to existing coal-fired utility boilers. The costs of retrofitting conventional lime/limestone wet flue gas desulfurization (L/LS FGD) and lime spray drying (LSD) FGD at 100-200 coal-fired power plants are being estimated under this program. The retrofit capital cost estimating procedures used for L/LS FGD and LSD FGD make two cost adjustments to current procedures used to estimate FGD costs: cost adders (for items not normally included in FGD system costs; e.g., demolition and relocation of existing facilities) and cost multipliers (to adjust capital costs for site access, congestion, and underground obstructions).

  15. Hydropower Baseline Cost Modeling

    SciTech Connect (OSTI)

    O'Connor, Patrick W.; Zhang, Qin Fen; DeNeale, Scott T.; Chalise, Dol Raj; Centurion, Emma E.

    2015-01-01

    Recent resource assessments conducted by the United States Department of Energy have identified significant opportunities for expanding hydropower generation through the addition of power to non-powered dams and on undeveloped stream-reaches. Additional interest exists in the powering of existing water resource infrastructure such as conduits and canals, upgrading and expanding existing hydropower facilities, and the construction new pumped storage hydropower. Understanding the potential future role of these hydropower resources in the nation’s energy system requires an assessment of the environmental and techno-economic issues associated with expanding hydropower generation. To facilitate these assessments, this report seeks to fill the current gaps in publically available hydropower cost-estimating tools that can support the national-scale evaluation of hydropower resources.

  16. Capital requirements and fuel-cycle energy and emissions impacts of potential PNGV fuels.

    SciTech Connect (OSTI)

    Johnson, L.; Mintz, M.; Singh, M.; Stork, K.; Vyas, A.; Wang, M.

    1999-03-11

    emissions relative to the reference scenario. The table clearly shows the trade-off between costs and benefits. For example, while H{sub 2} FCVs have the greatest incremental capital needs, they offer the largest energy and emissions benefits. On the basis of the cost and benefit changes shown, methanol and gasoline FCVs appear to have particularly promising benefits-to-costs ratios.

  17. Cost and Performance Model for Redox Flow Batteries

    SciTech Connect (OSTI)

    Viswanathan, Vilayanur V.; Crawford, Aladsair J.; Stephenson, David E.; Kim, Soowhan; Wang, Wei; Li, Bin; Coffey, Greg W.; Thomsen, Edwin C.; Graff, Gordon L.; Balducci, Patrick J.; Kintner-Meyer, Michael CW; Sprenkle, Vincent L.

    2014-02-01

    A cost model was developed for all vanadium and iron-vanadium redox flow batteries. Electrochemical performance modeling was done to estimate stack performance at various power densities as a function of state of charge. This was supplemented with a shunt current model and a pumping loss model to estimate actual system efficiency. The operating parameters such as power density, flow rates and design parameters such as electrode aspect ratio, electrolyte flow channel dimensions were adjusted to maximize efficiency and minimize capital costs. Detailed cost estimates were obtained from various vendors to calculate cost estimates for present, realistic and optimistic scenarios. The main drivers for cost reduction for various chemistries were identified as a function of the energy to power ratio of the storage system. Levelized cost analysis further guided suitability of various chemistries for different applications.

  18. United States

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EA- 3 14 Order Authorizing Electricity Exports to Mexico Order No. EA-3 14 February ... to transmit electric energy from the United States to Mexico as a power marketer. ...

  19. Office of the Chief Human Capital Officer | Department of Energy

    Broader source: All U.S. Department of Energy (DOE) Office Webpages

    Human Capital Officer Search Search form Search Office of the Chief Human Capital Officer Office of the Chief Human Capital Officer Services Services Home Benefits Benefits Home DOE Workers' Compensation Program Insurance Military/Reservist Retirement Telework Thrift Savings Plan (TSP) Wellness Programs Executive Resources Learning and Workforce Development New Employee Orientation Policy and Guidance Policy and Guidance Home Compensation Employment/Staffing Employment/Staffing Home Recruitment

  20. Capitalizing on Multibenefits of Energy Upgrades at Multifamily Housing

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    (301) | Department of Energy Capitalizing on Multibenefits of Energy Upgrades at Multifamily Housing (301) Capitalizing on Multibenefits of Energy Upgrades at Multifamily Housing (301) Buildings Residential Network Peer Exchange Call Series: Capitalizing on Multibenefits of Energy Upgrades at Multifamily Housing (301), call slides and discussion summary. Call Slides and Discussion Summary (3.36 MB) More Documents & Publications Staged Upgrades as a Strategy for Residential Energy

  1. United States

    Office of Legacy Management (LM)

    Office of Research and EPA 600/R-941209 Environmental Protection Development January 1993 Agency Washington, DC 20460 Offsite Environmental 57,,7 Monitoring Report Radiation Monitoring Around United States Nuclear Test Areas, Calendar Year 1992 UNITED STATES ENVIRONMENTAL PROTECTION AGENCY OFFICE OF RESEARCH AND DEVELOPMENT ENVIRONMENTAL MONITORING SYSTEMS LABORATORY-LAS VEGAS P.O. BOX 93478 LAS VEGAS. NEVADA 891 93-3478 702/798-2100 Dear Reader: Since 1954, the U.S. Environmental Protection

  2. Utilization of UV Curing Technology to Significantly Reduce the Manufacturing Cost of LIB Electrodes

    SciTech Connect (OSTI)

    Voelker, Gary; Arnold, John

    2015-11-30

    Previously identified novel binders and associated UV curing technology have been shown to reduce the time required to apply and finish electrode coatings from tens of minutes to less than one second. This revolutionary approach can result in dramatic increases in process speeds, significantly reduced capital (a factor of 10 to 20) and operating costs, reduced energy requirements, and reduced environmental concerns and costs due to the virtual elimination of harmful volatile organic solvents and associated solvent dryers and recovery systems. The accumulated advantages of higher speed, lower capital and operating costs, reduced footprint, lack of VOC recovery, and reduced energy cost is a reduction of 90% in the manufacturing cost of cathodes. When commercialized, the resulting cost reduction in Lithium batteries will allow storage device manufacturers to expand their sales in the market and thereby accrue the energy savings of broader utilization of HEVs, PHEVs and EVs in the U.S., and a broad technology export market is also envisioned.

  3. Cost reduction ideas for LNG terminals

    SciTech Connect (OSTI)

    Habibullah, A.; Weldin, F.

    1999-07-01

    LNG projects are highly capital intensive and this has long been regarded as being inevitable. However, recent developments are forcing the LNG industry to aggressively seek cost reductions. For example, the gas-to-liquids (GTL) process is increasingly seen as a potential rival technology and is often being touted as an economically superior alternative fuel source. Another strong driving force behind needed cost reductions is the low crude oil price which seems to have settled in the $10--13/bb. range. LNG is well positioned as the fuel of choice for environmentally friendly new power projects. As a result of the projected demand for power especially in the Pacific Rim countries several LNG terminal projects are under consideration. Such projects will require a new generation of LNG terminal designs emphasizing low cost, small scale and safe and fully integrated designs from LNG supply to power generation. The integration of the LNG terminal with the combined cycle gas turbine (CCGT) power plant offers substantial cost savings opportunities for both plants. Various cost reduction strategies and their impact on the terminal design are discussed including cost reduction due to integration.

  4. Mexico-Capital Markets Climate Initiative | Open Energy Information

    Open Energy Info (EERE)

    Low emission development planning, -LEDS Website http:www.decc.gov.ukencont Country Mexico Central America References CMCI1 World Economic Forum2 The Capital Markets...

  5. Program & Project Management For The Acquisition Of Capital Assets...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Program & Project Management For The Acquisition Of Capital Assets (310.65 KB) More Documents & Publications "Paper" Energy Systems Acquisition Advisory Board Process ESAAB ...

  6. Program and Project Management for the Acquisition of Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    3.3B, Program and Project Management for the Acquisition of Capital Assets by Jay Glascock Functional areas: Acquisition, Defense Nuclear Facility Safety and Health Requirement,...

  7. Webinar Announcement: Accessing Private Capital for Clean Energy...

    Open Energy Info (EERE)

    Webinar Announcement: Accessing Private Capital for Clean Energy Investments in Developing Countries (Webinar) Home > Groups > OpenEI Community Central Graham7781's picture...

  8. Delegation of Acquisition Executive Authority for Capital Asset...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Idaho Cleanup Project by cooper DelegationAcquisitionExecAuthorityCapitalAssetProjectsIDCleanupProject-CooperEM.pdf -- PDF Document, 256 KB ID: NA Type: Organizations' Assignment...

  9. Global Capital Finance Americas LLC | Open Energy Information

    Open Energy Info (EERE)

    Finance Americas LLC Jump to: navigation, search Name: Global Capital Finance Americas LLC Place: Purchase, New York Zip: 10577 Sector: Renewable Energy, Services Product: An...

  10. Financing U.S. Renewable Energy Projects Through Public Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Financing U.S. Renewable Energy Projects Through Public Capital Vehicles: Qualitative and ... Energy, Office of Energy Efficiency & Renewable Energy, operated by the Alliance for ...

  11. Program and Project Management for the Acquisition of Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    B Chg 1 (Admin Chg), Program and Project Management for the Acquisition of Capital Assets by Jay Glascock Functional areas: Acquisition, Defense Nuclear Facility Safety and Health ...

  12. Statement on Department of Energy's Major System Capital Asset...

    National Nuclear Security Administration (NNSA)

    Department of Energy's Major System Capital Asset Projects before the House Committee on Appropriations Subcommittee on Energy & Water Development March 20, 2013 INTRODUCTION ...

  13. Energy Department and GSA Assist in Capital Solar Challenge Industry...

    Office of Environmental Management (EM)

    General Services Administration (GSA) are charged with assisting agencies in leading the Capital Solar Challenge with the goal of developing solar renewable power on Federal sites. ...

  14. Office of the Chief Human Capital Officer | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Office of the Chief Human Capital Officer Most Requested Benefits CHRIS (DOE Only) DOE & ... HR Contacts by Sub Agency Servicing Area HC Contacts by Functional Area Human Resource ...

  15. Human Capital Policy Division (HC-11) | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    Provide a full range of staff support to the Chief Human Capital Officer including support required for internal and external responsibilities. Develop and revise the agency human ...

  16. Project Profile: Concurrent Optimization of Component Capital...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    solar power (CSP) plants by characterizing and forecasting operations and maintenance costs, component failure behavior, and the impact of design and maintenance policies. ...

  17. Cost Model and Cost Estimating Software

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter discusses a formalized methodology is basically a cost model, which forms the basis for estimating software.

  18. 2014 Cost of Wind Energy Review

    SciTech Connect (OSTI)

    Mone, Christopher; Stehly, Tyler; Maples, Ben; Settle, Edward

    2015-10-01

    This report uses representative commercial projects to estimate the levelized cost of energy (LCOE) for both land-based and offshore wind plants in the United States for 2014. Scheduled to be published on an annual basis, the analysis relies on both market and modeled data to maintain an up-to-date understanding of wind generation cost trends and drivers. It is intended to provide insight into current component-level costs and a basis for understanding variability in the LCOE across the industry. Data and tools developed by the National Renewable Energy Laboratory (NREL) are used in this analysis to inform wind technology cost projections, goals, and improvement opportunities.

  19. Land-Based Wind Plant Balance-of-System Cost Drivers and Sensitivities (Poster)

    SciTech Connect (OSTI)

    Mone, C.; Maples, B.; Hand, M.

    2014-04-01

    With Balance of System (BOS) costs contributing up to 30% of the installed capital cost, it is fundamental to understand the BOS costs for wind projects as well as potential cost trends for larger turbines. NREL developed a BOS model using project cost estimates developed by industry partners. Aspects of BOS covered include engineering and permitting, foundations for various wind turbines, transportation, civil work, and electrical arrays. The data introduce new scaling relationships for each BOS component to estimate cost as a function of turbine parameters and size, project parameters and size, and geographic characteristics. Based on the new BOS model, an analysis to understand the non‐turbine wind plant costs associated with turbine sizes ranging from 1-6 MW and wind plant sizes ranging from 100-1000 MW has been conducted. This analysis establishes a more robust baseline cost estimate, identifies the largest cost components of wind project BOS, and explores the sensitivity of the capital investment cost and the levelized cost of energy to permutations in each BOS cost element. This presentation shows results from the model that illustrate the potential impact of turbine size and project size on the cost of energy from US wind plants.

  20. United sail windmill

    SciTech Connect (OSTI)

    Labrador, G.A.

    1988-07-12

    This windmill provides low cost energy out of the wind in the form of compressed air, etc, by maximizing wind-contact at the least cost construction and maintenance, at the least cost of project site - making the ''Output/Cost Ratio'' very high. This is done by making the sails very large using light fabrics with aluminum or bamboo frames forming a square face, supported by light strong ropes, by arranging the sails on a single file close to one after the other at erect posture free to clip to the right or to the left, forming a long procession line transverse to the wind which is in close loop with another long procession line parallel to it but moving to the opposite direction, to produce a very large windmill without the need of additional set up units of windmills; by carrying the large sails high about the ground for better wind-contact thru a two level Aerial Cable Railway by means of a deep-groove roller wheel attached to the top end and to the bottom end of each sail-mast; by separating the two parallel lines of sails at least 100 feet apart for better wind-contact thru the use of set of three Terminal Gear Wheels at a Half-Hexagonal formation that hold the end loops of the Power Cable Chain being tugged by each sail; by making the windmill work during strong winds and storing the energy in compressed air tunnels, elevated water.

  1. Portable brine evaporator unit, process, and system

    DOE Patents [OSTI]

    Hart, Paul John; Miller, Bruce G.; Wincek, Ronald T.; Decker, Glenn E.; Johnson, David K.

    2009-04-07

    The present invention discloses a comprehensive, efficient, and cost effective portable evaporator unit, method, and system for the treatment of brine. The evaporator unit, method, and system require a pretreatment process that removes heavy metals, crude oil, and other contaminates in preparation for the evaporator unit. The pretreatment and the evaporator unit, method, and system process metals and brine at the site where they are generated (the well site). Thus, saving significant money to producers who can avoid present and future increases in transportation costs.

  2. Cellulosic Ethanol Cost Target

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Plenary Talk May 21, 2013 Cellulosic Ethanol Cost Target 2 | Biomass Program ... "Our goal is to make cellulosic ethanol practical and cost competitive within 6 ...

  3. DOE Guide to IT Capital Planning and Investment Control BY 2016...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Guide to IT Capital Planning and Investment Control BY 2016 DOE Guide to IT Capital Planning and Investment Control BY 2016 DOE Guide to IT Capital Planning and Investment Control...

  4. EA-184-A Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    4-A Morgan Stanley Capital Group Inc. EA-184-A Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Mexico. EA-184-A ...

  5. EA-185-D Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    D Morgan Stanley Capital Group Inc. EA-185-D Morgan Stanley Capital Group Inc. Order authorizing MSCG to export electric energy to Canada. EA-185-D Morgan Stanley Capital Group.pdf ...

  6. EA-185-C Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    C Morgan Stanley Capital Group Inc. EA-185-C Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Canada. EA-185-C ...

  7. EA-185-A Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    -A Morgan Stanley Capital Group Inc. EA-185-A Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Canada. EA-185-A ...

  8. EA-260 EPCOR Merchant and Capital (US) Inc | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EPCOR Merchant and Capital (US) Inc EA-260 EPCOR Merchant and Capital (US) Inc Order authorizing EPCOR Merchant and Capital (US) Inc to export electric energy to Canada. EA-260 ...

  9. EA-185-B Morgan Stanley Capital Group Inc. | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    B Morgan Stanley Capital Group Inc. EA-185-B Morgan Stanley Capital Group Inc. Order authorizing Morgan Stanley Capital Group Inc. to export electric energy to Canada. EA-185-B ...

  10. EA-260-A EPCOR Merchant and Capital (US) Inc | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    -A EPCOR Merchant and Capital (US) Inc EA-260-A EPCOR Merchant and Capital (US) Inc Order authorizing EPCOR Merchant and Capital (US) Inc to export electric energy to Canada. ...

  11. EA-260-C EPCOR Merchant and Capital (US) Inc | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    60-C EPCOR Merchant and Capital (US) Inc EA-260-C EPCOR Merchant and Capital (US) Inc Order authorizing EPCOR Merchant and Capital (US) Inc to export electric energy to Canada. ...

  12. Integration of Variable Generation and Cost-Causation (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2012-09-01

    Variable renewable energy generation sources, such as wind and solar energy, provide benefits such as reduced environmental impact, zero fuel consumption, and low and stable costs. Advances in both technologies can reduce capital costs and provide significant control capabilities. However, their variability and uncertainty - which change with weather conditions, time of day, and season - can cause an increase in power system operating costs compared to a fully controllable power plant. Although a number of studies have assessed integration costs, calculating them correctly is challenging because it is difficult to accurately develop a baseline scenario without variable generation that properly accounts for the energy value. It is also difficult to appropriately allocate costs given the complex, nonlinear interactions between resources and loads.

  13. Cost estimate for muddy water palladium production facility at Mound

    SciTech Connect (OSTI)

    McAdams, R.K.

    1988-11-30

    An economic feasibility study was performed on the ''Muddy Water'' low-chlorine content palladium powder production process developed by Mound. The total capital investment and total operating costs (dollars per gram) were determined for production batch sizes of 1--10 kg in 1-kg increments. The report includes a brief description of the Muddy Water process, the process flow diagram, and material balances for the various production batch sizes. Two types of facilities were evaluated--one for production of new, ''virgin'' palladium powder, and one for recycling existing material. The total capital investment for virgin facilities ranged from $600,000 --$1.3 million for production batch sizes of 1--10 kg, respectively. The range for recycle facilities was $1--$2.3 million. The total operating cost for 100% acceptable powder production in the virgin facilities ranged from $23 per gram for a 1-kg production batch size to $8 per gram for a 10-kg batch size. Similarly for recycle facilities, the total operating cost ranged from $34 per gram to $5 per gram. The total operating cost versus product acceptability (ranging from 50%--100% acceptability) was also evaluated for both virgin and recycle facilities. Because production sizes studied vary widely and because scale-up factors are unknown for batch sizes greater than 1 kg, all costs are ''order-of-magnitude'' estimates. All costs reported are in 1987 dollars.

  14. U.S. Department of Energy Selects Venture Capital Firms to Accelerate...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Venture Capital Firms to Accelerate Adoption of Advanced Energy Technologies U.S. Department of Energy Selects Venture Capital Firms to Accelerate Adoption of Advanced Energy ...

  15. MicroPlanet Technology Corp formerly HF Capital Corp | Open Energy...

    Open Energy Info (EERE)

    Technology Corp formerly HF Capital Corp Jump to: navigation, search Name: MicroPlanet Technology Corp (formerly HF Capital Corp) Place: Seattle, Washington Zip: 98104 Sector:...

  16. Microsoft Word - DOE Human Capital Strategic Plan 2011-2015.docx

    Broader source: Energy.gov (indexed) [DOE]

    DOE HUMAN CAPITAL STRATEGIC PLAN FY 2011 - FY 2015 DOE HUMAN CAPITAL STRATEGIC PLAN FY 2011 - FY 2015 TABLE OF CONTENTS EXECUTIVE SUMMARY ......

  17. Future of Wind Energy Technology in the United States

    SciTech Connect (OSTI)

    Thresher, R.; Robinson, M.; Veers, P.

    2008-10-01

    This paper describes the status of wind energy in the United States as of 2007, its cost, the potential for growth, offshore development, and potential technology improvements.

  18. Geothermal Heat Pumps as a Cost Saving and Capital Renewal Too!

    SciTech Connect (OSTI)

    Hughes, P.J.

    1998-11-06

    An independent evaluation of the Fort Polk, Louisiana energy savings performance contract (ESPC) has verified the financial value of geothermal heat pump (GHP)-centered ESPCS to the federal government. The Department of Energy (DOE) Federal Energy Management Program (FEMP) has responded by issuing an RFP for the "National GHP-Technology-Specific Super ESPC Procurement." Federal agency sites anywhere in the nation will be able to implement GHP-centered ESPC projects as delivery orders against the awarded contracts.

  19. Wind Turbine Control Design to Reduce Capital Costs: 7 January 2009 - 31 August 2009

    SciTech Connect (OSTI)

    Darrow, P. J.

    2010-01-01

    This report first discusses and identifies which wind turbine components can benefit from advanced control algorithms and also presents results from a preliminary loads case analysis using a baseline controller. Next, it describes the design, implementation, and simulation-based testing of an advanced controller to reduce loads on those components. The case-by-case loads analysis and advanced controller design will help guide future control research.

  20. Life Cycle Cost Estimate

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Life-cycle costs (LCCs) are all the anticipated costs associated with a project or program alternative throughout its life. This includes costs from pre-operations through operations or to the end of the alternative.This chapter discusses life cycle costs and the role they play in planning.

  1. Cost Estimation Package

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter focuses on the components (or elements) of the cost estimation package and their documentation.

  2. A chronicle of costs

    SciTech Connect (OSTI)

    Elioff, T.

    1994-04-01

    This report contains the history of all estimated costs associated with the superconducting super collider.

  3. " Million Housing Units, Final...

    U.S. Energy Information Administration (EIA) Indexed Site

    ... Vacant housing units, seasonal units, second homes, military housing, and group quarters ... Vacant housing units, seasonal units, second homes, military housing, and group quarters ...

  4. " Million Housing Units, Final"

    U.S. Energy Information Administration (EIA) Indexed Site

    ... Vacant housing units, seasonal units, second homes, military housing, and group quarters ... Vacant housing units, seasonal units, second homes, military housing, and group quarters ...

  5. Life-cycle cost comparisons of advanced storage batteries and fuel cells for utility, stand-alone, and electric vehicle applications

    SciTech Connect (OSTI)

    Humphreys, K.K.; Brown, D.R.

    1990-01-01

    This report presents a comparison of battery and fuel cell economics for ten different technologies. To develop an equitable economic comparison, the technologies were evaluated on a life-cycle cost (LCC) basis. The LCC comparison involved normalizing source estimates to a standard set of assumptions and preparing a lifetime cost scenario for each technology, including the initial capital cost, replacement costs, operating and maintenance (O M) costs, auxiliary energy costs, costs due to system inefficiencies, the cost of energy stored, and salvage costs or credits. By considering all the costs associated with each technology over its respective lifetime, the technology that is most economical to operate over any given period of time can be determined. An analysis of this type indicates whether paying a high initial capital cost for a technology with low O M costs is more or less economical on a lifetime basis than purchasing a technology with a low initial capital cost and high O M costs. It is important to realize that while minimizing cost is important, the customer will not always purchase the least expensive technology. The customer may identify benefits associated with a more expensive option that make it the more attractive over all (e.g., reduced construction lead times, modularity, environmental benefits, spinning reserve, etc.). The LCC estimates presented in this report represent three end-use applications: utility load-leveling, stand-alone power systems, and electric vehicles.

  6. Hydrogen Threshold Cost Calculation

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Program Record (Offices of Fuel Cell Technologies) Record #: 11007 Date: March 25, 2011 Title: Hydrogen Threshold Cost Calculation Originator: Mark Ruth & Fred Joseck Approved by: Sunita Satyapal Date: March 24, 2011 Description: The hydrogen threshold cost is defined as the hydrogen cost in the range of $2.00-$4.00/gge (2007$) which represents the cost at which hydrogen fuel cell electric vehicles (FCEVs) are projected to become competitive on a cost per mile basis with the competing

  7. OOTW COST TOOLS

    SciTech Connect (OSTI)

    HARTLEY, D.S.III; PACKARD, S.L.

    1998-09-01

    This document reports the results of a study of cost tools to support the analysis of Operations Other Than War (OOTW). It recommends the continued development of the Department of Defense (DoD) Contingency Operational Support Tool (COST) as the basic cost analysis tool for 00TWS. It also recommends modifications to be included in future versions of COST and the development of an 00TW mission planning tool to supply valid input for costing.

  8. Hydrogen Pathway Cost Distributions

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Pathway Cost Distributions Jim Uihlein Fuel Pathways Integration Tech Team January 25, 2006 2 Outline * Pathway-Independent Cost Goal * Cost Distribution Objective * Overview * H2A Influence * Approach * Implementation * Results * Discussion Process * Summary 3 Hydrogen R&D Cost Goal * Goal is pathway independent * Developed through a well defined, transparent process * Consumer fueling costs are equivalent or less on a cents per mile basis * Evolved gasoline ICE and gasoline-electric

  9. United States

    Office of Environmental Management (EM)

    E-T Global Energy, LLC OE Docket No. EA-381 Order Authorizing Electricity Exports to Mexico Order No. EA-381 June 10, 2011 I. BACKGROUND E-T Global Energy, LLC Order No. EA-381 Exports of electricity from the United States to a foreign country are regulated by the Department of Energy (DOE) pursuant to sections 301(b) and 402(f) of the Department ofEnergy Organization Act (42 U.S.C. 7151(b), 7172(f)) and require authorization under section 202(e) ofthe Federal Power Act (FPA) (16 U.S.C.824a(e))

  10. United States

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    E-T Global Energy, LLC OE Docket No. EA-381 Order Authorizing Electricity Exports to Mexico Order No. EA-381 June 10, 2011 I. BACKGROUND E-T Global Energy, LLC Order No. EA-381 Exports of electricity from the United States to a foreign country are regulated by the Department of Energy (DOE) pursuant to sections 301(b) and 402(f) of the Department ofEnergy Organization Act (42 U.S.C. 7151(b), 7172(f)) and require authorization under section 202(e) ofthe Federal Power Act (FPA) (16 U.S.C.824a(e))

  11. United States

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Tenaslta Power Services Co. OE Docket No. EA-243-A Order Authorizing Electricity Exports to Canada Order No. EA-243-A March 1,2007 Tenaska Power Services Co. Order No. EA-243-A I. BACKGROUND Exports of elcctricity from the United States to a foreign country are regulated by the Department of Energy (DOE) pursuant to sections 30 I(b) and 402(f) of the Departrncnt of' Energy Organizatio~l Act (42 U, S.C. 7 15 1 (b), 7 1 72Cf)) and rcquirc authorization under section 202(e) of the Federal Power Act

  12. United States

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    TexMex Energy, LLC OE Docket No. EA-294-A Order Authorizing Electricity Exports to Mexico Order No. EA-294-A February 22, 2007 TexMex Energy, LLC Order No. EA-294-A I. BACKGROUND Exports of electricity from the United States to a foreign count~y are regulated by the Department of Energy (DOE) pursuant to sections 301(b) and 402(f) of the Department of Energy Organization Act (42 U.S.C. 7 15 1 (b), 71 72(f)) and require authorization under section 202(e) of the Federal Power Act (FPA) (16

  13. United States

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    CSW Power Marketing OE Docket No. EA-3 1 8 Order Authorizing Electricity Exports to Mexico Order No. EA-3 18 February 22,2007 CSW Power Marketing Order No. EA-318 I. BACKGROUND Exports of electricity from the United States to a foreign country are regulated by the Department of Energy (DOE) pursuant to sections 30l(b) and 402(f) of the Department of Energy Organization Act (42 U.S.C. 7 1 5 1 (b), 7 1 72(f)) and require authorization under section 202(e) of the Federal Power Act (FPA) (16

  14. United States National Seismographic Network

    SciTech Connect (OSTI)

    Buland, R.

    1993-09-01

    The concept of a United States National Seismograph Network (USNSN) dates back nearly 30 years. The idea was revived several times over the decades. but never funded. For, example, a national network was proposed and discussed at great length in the so called Bolt Report (U. S. Earthquake Observatories: Recommendations for a New National Network, National Academy Press, Washington, D.C., 1980, 122 pp). From the beginning, a national network was viewed as augmenting and complementing the relatively dense, predominantly short-period vertical coverage of selected areas provided by the Regional Seismograph Networks (RSN`s) with a sparse, well-distributed network of three-component, observatory quality, permanent stations. The opportunity finally to begin developing a national network arose in 1986 with discussions between the US Geological Survey (USGS) and the Nuclear Regulatory Commission (NRC). Under the agreement signed in 1987, the NRC has provided $5 M in new funding for capital equipment (over the period 1987-1992) and the USGS has provided personnel and facilities to develop. deploy, and operate the network. Because the NRC funding was earmarked for the eastern United States, new USNSN station deployments are mostly east of 105{degree}W longitude while the network in the western United States is mostly made up of cooperating stations (stations meeting USNSN design goals, but deployed and operated by other institutions which provide a logical extension to the USNSN).

  15. Preconceptual design studies and cost data of depleted uranium hexafluoride conversion plants

    SciTech Connect (OSTI)

    Jones, E

    1999-07-26

    One of the more important legacies left with the Department of Energy (DOE) after the privatization of the United States Enrichment Corporation is the large inventory of depleted uranium hexafluoride (DUF6). The DOE Office of Nuclear Energy, Science and Technology (NE) is responsible for the long-term management of some 700,000 metric tons of DUF6 stored at the sites of the two gaseous diffusion plants located at Paducah, Kentucky and Portsmouth, Ohio, and at the East Tennessee Technology Park in Oak Ridge, Tennessee. The DUF6 management program resides in NE's Office of Depleted Uranium Hexafluoride Management. The current DUF6 program has largely focused on the ongoing maintenance of the cylinders containing DUF6. However, the long-term management and eventual disposition of DUF6 is the subject of a Programmatic Environmental Impact Statement (PEIS) and Public Law 105-204. The first step for future use or disposition is to convert the material, which requires construction and long-term operation of one or more conversion plants. To help inform the DUF6 program's planning activities, it was necessary to perform design and cost studies of likely DUF6 conversion plants at the preconceptual level, beyond the PEIS considerations but not as detailed as required for conceptual designs of actual plants. This report contains the final results from such a preconceptual design study project. In this fast track, three month effort, Lawrence Livermore National Laboratory and Bechtel National Incorporated developed and evaluated seven different preconceptual design cases for a single plant. The preconceptual design, schedules, costs, and issues associated with specific DUF6 conversion approaches, operating periods, and ownership options were evaluated based on criteria established by DOE. The single-plant conversion options studied were similar to the dry-conversion process alternatives from the PEIS. For each of the seven cases considered, this report contains information on

  16. NUCLEAR ENERGY SYSTEM COST MODELING

    SciTech Connect (OSTI)

    Francesco Ganda; Brent Dixon

    2012-09-01

    The U.S. Department of Energys Fuel Cycle Technologies (FCT) Program is preparing to perform an evaluation of the full range of possible Nuclear Energy Systems (NES) in 2013. These include all practical combinations of fuels and transmuters (reactors and sub-critical systems) in single and multi-tier combinations of burners and breeders with no, partial, and full recycle. As part of this evaluation, Levelized Cost of Electricity at Equilibrium (LCAE) ranges for each representative system will be calculated. To facilitate the cost analyses, the 2009 Advanced Fuel Cycle Cost Basis Report is being amended to provide up-to-date cost data for each step in the fuel cycle, and a new analysis tool, NE-COST, has been developed. This paper explains the innovative Island approach used by NE-COST to streamline and simplify the economic analysis effort and provides examples of LCAE costs generated. The Island approach treats each transmuter (or target burner) and the associated fuel cycle facilities as a separate analysis module, allowing reuse of modules that appear frequently in the NES options list. For example, a number of options to be screened will include a once-through uranium oxide (UOX) fueled light water reactor (LWR). The UOX LWR may be standalone, or may be the first stage in a multi-stage system. Using the Island approach, the UOX LWR only needs to be modeled once and the module can then be reused on subsequent fuel cycles. NE-COST models the unit operations and life cycle costs associated with each step of the fuel cycle on each island. This includes three front-end options for supplying feedstock to fuel fabrication (mining/enrichment, reprocessing of used fuel from another island, and/or reprocessing of this islands used fuel), along with the transmuter and back-end storage/disposal. Results of each island are combined based on the fractional energy generated by each islands in an equilibrium system. The cost analyses use the probability distributions of

  17. Program and Project Management for the Acquisition of Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    13.B, Chg 1 (PgChg), Program and Project Management for the Acquisition of Capital Assets by Jay Glascock Functional areas: Acquisition, Defense Nuclear Facility Safety and Health...

  18. Delegation of Acquisition Executive Authority for Capital Asset...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the Oak Ridge Office by whitney Delegation-AcquisitionExecAuthorityforCapitalAsset Projects-OR-WhitneyEM.pdf -- PDF Document, 627 KB ID: NA Type: Organizations' Assignment of...

  19. Program and Project Management for the Acquisition of Capital...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ARCHIVED DOE O 413.3A Chg 1, Program and Project Management for the Acquisition of Capital Assets by John Makepeace Functional areas: Acquisition, Defense Nuclear Facility Safety...

  20. Delegation of Acquisition Executive Authority for Capital Asset...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Related to: DOE O 413.3B, Program and Project Management for the Acquisition of Capital Assets There is no history to display for this document. Document Actions Print this...

  1. ErgyCapital Beghelli JV | Open Energy Information

    Open Energy Info (EERE)

    & Beghelli JV Place: Italy Product: Italy-based JV, formed to design and install photovoltaic systems. References: ErgyCapital & Beghelli JV1 This article is a stub. You can...

  2. Three State Capitals to Receive Green Design Assistance from EPA

    Broader source: Energy.gov [DOE]

    The U.S. Environmental Protection Agency (EPA) on January 9 announced urban planning design assistance to help the capital cities of Michigan, Washington, and Wisconsin develop greener designs, including the use of renewable energy technologies.

  3. Project Management for the Acquisition of Capital Assets

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2003-03-28

    The purpose of this Manual is to provide requirements and guidance to Department of Energy (DOE) employees, including National Nuclear Security Administration (NNSA) employees on the planning and acquisition of capital assets. Does not cancel other directives.

  4. Chief Human Capital Officer Memo on Improving DOE Recruitment...

    Broader source: Energy.gov (indexed) [DOE]

    Improving DOE Recruitment and Hiring Processes (540.02 KB) Responsible Contacts Kenneth Venuto Director, Office of Human Capital Management E-mail kenneth.venuto@hq.doe.gov More ...

  5. Human Capital: The Role of Ombudsmen in Dispute Resolution |...

    Broader source: Energy.gov (indexed) [DOE]

    Human Capital: The Role of Ombudsmen in Dispute Resolution (339.67 KB) More Documents & Publications The Role of Ombudsmen in Dispute Resolution TT Coordinator Ltr dated May 13 ...

  6. Women in engineering conference: capitalizing on today`s challenges

    SciTech Connect (OSTI)

    Metz, S.S.; Martins, S.M.

    1996-06-01

    This document contains the conference proceedings of the Women in Engineering Conference: Capitalizing on Today`s Challenges, held June 1-4, 1996 in Denver, Colorado. Topics included engineering and science education, career paths, workplace issues, and affirmative action.

  7. Driving Down HB-LED Costs. Implementation of Process Simulation Tools and Temperature Control Methods of High Yield MOCVD Growth

    SciTech Connect (OSTI)

    Quinn, William

    2012-04-30

    The overall objective of this multi-faceted program is to develop epitaxial growth systems that meet a goal of 75% (4X) cost reduction in the epitaxy phase of HB-LED manufacture. A 75% reduction in yielded epitaxy cost is necessary in order to achieve the cost goals for widespread penetration of HB-LED's into back-lighting units (BLU) for LCD panels and ultimately for solid-state lighting (SSL). To do this, the program will address significant improvements in overall equipment Cost of Ownership, or CoO. CoO is a model that includes all costs associated with the epitaxy portion of production. These aspects include cost of yield, capital cost, operational costs, and maintenance costs. We divide the program into three phases where later phases will incorporate the gains of prior phases. Phase one activities are enabling technologies. In collaboration with Sandia National Laboratories we develop a Fluent-compatible chemistry predictive model and a set of mid-infrared and near-ultraviolet pyrometer monitoring tools. Where previously the modeling of the reactor dynamics were studied within FLUENT alone, here, FLUENT and Chemkin are integrated into a comprehensive model of fluid dynamics and the most advanced transport equations developed for Chemkin. Specifically, the Chemkin model offered the key reaction terms for gas-phase nucleation, a key consideration in the optimization of the MOCVD process. This new predictive model is used to design new MOCVD reactors with optimized growth conditions and the newly developed pyrometers are used monitor and control the MOCVD process temperature to within 0.5°C run-to-run and within each wafer. This portion of the grant is in collaboration with partners at Sandia National Laboratories. Phase two activities are continuous improvement projects which extend the current reactor platform along the lines of improved operational efficiency, improved systems control for throughput, and carrier modifications for increased yield

  8. Tribal Renewable Energy Webinar: Accessing Capital for Tribal Energy and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Economic Development | Department of Energy Accessing Capital for Tribal Energy and Economic Development Tribal Renewable Energy Webinar: Accessing Capital for Tribal Energy and Economic Development October 26, 2016 11:00AM to 12:30PM MDT Understand available financing mechanisms that can be used to make energy efficiency and renewable energy projects economically feasible, including utility community solar models, third-party vendors, green bonds, energy savings performance contracts, and

  9. Low Capital Photovoltaic Panel Electrical Output-Booster System |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Low Capital Photovoltaic Panel Electrical Output-Booster System Low Capital Photovoltaic Panel Electrical Output-Booster System This presentation summarizes the information given during the DOE SunShot Grand Challenge: Summit and Technology Forum, June 13-14, 2012. ssgrandchallenge_finance_schrag.pdf (63.07 KB) More Documents & Publications The SunShot Vision Study SunShot Vision Study: February 2012 (Book), SunShot, Energy Efficiency & Renewable Energy (EERE)

  10. Program and Project Management for the Acquisition of Capital Assets -

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    DOE Directives, Delegations, and Requirements B, Program and Project Management for the Acquisition of Capital Assets by Jay Glascock Functional areas: Acquisition, Defense Nuclear Facility Safety and Health Requirement, Program Management The purpose of this Order is to a) provide the Department of Energy (DOE) Elements, including the National Nuclear Security Administration (NNSA), with program and project management direction for the acquisition of capital assets with the goal of

  11. Direct/Indirect Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter provides recommended categories for direct and indirect elements developed by the Committee for Cost Methods Development (CCMD) and describes various estimating techniques for direct and indirect costs.

  12. Vehicle Cost Calculator

    Alternative Fuels and Advanced Vehicles Data Center [Office of Energy Efficiency and Renewable Energy (EERE)]

    Annual Fuel Cost gal Annual GHG Emissions (lbs of CO2) Vehicle Cost Calculator See Assumptions and Methodology Back Next U.S. Department of Energy Energy Efficiency and ...

  13. Development of Advanced Technologies to Reduce Design, Fabrication and Construction Costs for Future Nuclear Power Plants

    SciTech Connect (OSTI)

    DiNunzio, Camillo A.; Gupta, Abhinav; Golay, Michael; Luk, Vincent; Turk, Rich; Morrow, Charles; Jin, Geum-Taek

    2002-11-30

    This report presents a summation of the third and final year of a three-year investigation into methods and technologies for substantially reducing the capital costs and total schedule for future nuclear plants. In addition, this is the final technical report for the three-year period of studies.

  14. PEM Electrolyzer Incorporating an Advanced Low-Cost Membrane

    SciTech Connect (OSTI)

    Hamdan, Monjid

    2013-08-29

    The Department of Energy (DOE) has identified hydrogen production by electrolysis of water at forecourt stations as a critical technology for transition to the hydrogen economy; however, the cost of hydrogen produced by present commercially available electrolysis systems is considerably higher than the DOE 2015 and 2020 cost targets. Analyses of proton-exchange membrane (PEM) electrolyzer systems indicate that reductions in electricity consumption and electrolyzer stack and system capital cost are required to meet the DOE cost targets. The primary objective is to develop and demonstrate a cost-effective energy-based system for electrolytic generation of hydrogen. The goal is to increase PEM electrolyzer efficiency and to reduce electrolyzer stack and system capital cost to meet the DOE cost targets for distributed electrolysis. To accomplish this objective, work was conducted by a team consisting of Giner, Inc. (Giner), Virginia Polytechnic Institute & University (VT), and domnick hunter group, a subsidiary of Parker Hannifin (Parker). The project focused on four (4) key areas: (1) development of a high-efficiency, high-strength membrane; (2) development of a long-life cell-separator; (3) scale-up of cell active area to 290 cm2 (from 160 cm²); and (4) development of a prototype commercial electrolyzer system. In each of the key stack development areas Giner and our team members conducted focused development in laboratory-scale hardware, with analytical support as necessary, followed by life-testing of the most promising candidate materials. Selected components were then scaled up and incorporated into low-cost scaled-up stack hardware. The project culminated in the fabrication and testing of a highly efficient electrolyzer system for production of 0.5 kg/hr hydrogen and validation of the stack and system in testing at the National Renewable Energy Laboratory (NREL).

  15. Multiple-Reheat Brayton Cycles for Nuclear Power Conversion with...

    Office of Scientific and Technical Information (OSTI)

    Volume: 144; Journal Issue: 3; Other Information: Copyright (c) 2006 American Nuclear Society (ANS), United States, ... CAPITALIZED COST; CHEMICAL REACTIONS; ...

  16. Power Plant Cycling Costs

    SciTech Connect (OSTI)

    Kumar, N.; Besuner, P.; Lefton, S.; Agan, D.; Hilleman, D.

    2012-07-01

    This report provides a detailed review of the most up to date data available on power plant cycling costs. The primary objective of this report is to increase awareness of power plant cycling cost, the use of these costs in renewable integration studies and to stimulate debate between policymakers, system dispatchers, plant personnel and power utilities.

  17. Simple cost model for EV traction motors

    SciTech Connect (OSTI)

    Cuenca, R.M.

    1995-02-01

    A simple cost model has been developed that allows the calculation of the OEM cost of electric traction motors of three different types, normalized as a function of power in order to accommodate different power and size. The model includes enough information on the various elements integrated in the motors to allow analysis of individual components and to factor-in the effects of changes in commodities prices. A scalable cost model for each of the main components of an electric vehicle (EV) is a useful tool that can have direct application in computer simulation or in parametric studies. For the cost model to have wide usefulness, it needs to be valid for a range of values of some parameter that determines the magnitude or size of the component. For instance, in the case of batteries, size may be determined by energy capacity, usually expressed in kilowatt-hours (kWh), while in the case of traction motors, size is better determined by rated power, usually expressed in kilowatts (kW). The simplest case is when the cost of the component in question is a direct function of its size; then cost is simply the product of its specific cost ($/unit size) and the number of units (size) in the vehicle in question. Batteries usually fall in this category (cost = energy capacity x $/kWh). But cost is not always linear with size or magnitude; motors (and controllers), for instance, become relatively less expensive as power rating increases. Traction motors, one of the main components for EV powertrains are examined in this paper, and a simplified cost model is developed for the three most popular design variations.

  18. Better Buildings Alliance, Advanced Rooftop Unit Campaign: Rooftop Unit Measurement and Verification (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2014-09-01

    This document provides facility managers and building owners an introduction to measurement and verification (M&V) methods to estimate energy and cost savings of rooftop units replacement or retrofit projects to estimate paybacks or to justify future projects.

  19. Application to Export Electric Energy OE Docket No. EA-355 Scotia Capital

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy | Department of Energy 5 Scotia Capital Energy Application to Export Electric Energy OE Docket No. EA-355 Scotia Capital Energy Application from Scotia Capital Energyto export electric energy to Canada Application to Export Electric Energy OE Docket No EA-355 Scotia Capital Energy (209.34 KB) More Documents & Publications EA-355 Scotia Capital Energy, Inc. Application to Export Electric Energy OE Docket No. EA-407 Vitol Inc.: Federal Register Notice, Volume 80, No. 42 - March 4,

  20. Termination unit

    DOE Patents [OSTI]

    Traeholt, Chresten [Frederiksberg, DK; Willen, Dag [Klagshamn, SE; Roden, Mark [Newnan, GA; Tolbert, Jerry C [Carrollton, GA; Lindsay, David [Carrollton, GA; Fisher, Paul W [Heiskell, TN; Nielsen, Carsten Thidemann [Jaegerspris, DK

    2014-01-07

    This invention relates to a termination unit comprising an end-section of a cable. The end section of the cable defines a central longitudinal axis and comprising end-parts of N electrical phases, an end-part of a neutral conductor and a surrounding thermally insulation envelope adapted to comprising a cooling fluid. The end-parts of the N electrical phases and the end-part of the neutral conductor each comprising at least one electrical conductor and being arranged in the cable concentrically around a core former with a phase 1 located relatively innermost, and phase N relatively outermost in the cable, phase N being surrounded by the neutral conductor, electrical insulation being arrange between neighboring electrical phases and between phase N and the neutral conductor, and wherein the end-parts of the neutral conductor and the electrical phases each comprise a contacting surface electrically connected to at least one branch current lead to provide an electrical connection: The contacting surfaces each having a longitudinal extension, and being located sequentially along the longitudinal extension of the end-section of the cable. The branch current leads being individually insulated from said thermally insulation envelope by individual electrical insulators.

  1. Comparison of financing costs for wind turbine and fossil powerplants

    SciTech Connect (OSTI)

    Kahn, E.

    1995-02-01

    This paper compares the financing costs of wind turbine powerplants with those of fossil powerplants. The goal of this examination is to determine the extent to which these costs differ and what the sources of such differences may be. The discussion is organized in the following fashion. Section 2 introduces basic terminology and concepts from finance, as they apply in the powerplant setting. Section 3 reviews available data from a variety of sources to estimate the magnitude of the variables identified in Section 2. In Section 4 we examine the effect of the production tax credit enacted in the Energy Policy Act of 1992 on the financing of wind turbine projects. Conclusions are offered in Section 5. In the past two years there have been only two wind turbine projects that have been financed, so the basis for broad conclusions is limited. Nonetheless, there appears to be a significant advantage in financing costs for conventional projects compared to wind turbines. The two sources of disadvantage to wind power are first, the cost of equity capital is significantly more expensive, and second, the capital structure of wind projects has a much greater fraction of expensive equity than conventional alternatives.

  2. Maximizing productivity & profitability through best cost shift schedules

    SciTech Connect (OSTI)

    Coleman, R.

    1996-12-31

    If you have the right equipment and employees at the right place, the fight time, and the right cost, you have the perfect business schedule. But, if you`re like most mines, you can probably improve your schedule, improvements that will reach all the way to the bottom line. And unlike adding employees, materials, or capital equipment, better scheduling is a cost-free way improve profitability. A good schedule can save millions. A bad schedule will cost money every year. A shift schedule is not a day off pattern or shift length. A shift schedule is a complete system deploying personnel and capital equipment. Most mining schedules are either copied from another operation, based on tradition or the result of a contract negotiation made far from the mine site. Unfortunately, most mine managers don`t give much thought to schedules until a crisis develops; at which point the tendency is to implement the first solution that comes along as quickly as possible. Costly mistakes are made.

  3. Low Cost Lithography Tool for High Brightness LED Manufacturing

    SciTech Connect (OSTI)

    Andrew Hawryluk; Emily True

    2012-06-30

    The objective of this activity was to address the need for improved manufacturing tools for LEDs. Improvements include lower cost (both capital equipment cost reductions and cost-ofownership reductions), better automation and better yields. To meet the DOE objective of $1- 2/kilolumen, it will be necessary to develop these highly automated manufacturing tools. Lithography is used extensively in the fabrication of high-brightness LEDs, but the tools used to date are not scalable to high-volume manufacturing. This activity addressed the LED lithography process. During R&D and low volume manufacturing, most LED companies use contact-printers. However, several industries have shown that these printers are incompatible with high volume manufacturing and the LED industry needs to evolve to projection steppers. The need for projection lithography tools for LED manufacturing is identified in the Solid State Lighting Manufacturing Roadmap Draft, June 2009. The Roadmap states that Projection tools are needed by 2011. This work will modify a stepper, originally designed for semiconductor manufacturing, for use in LED manufacturing. This work addresses improvements to yield, material handling, automation and throughput for LED manufacturing while reducing the capital equipment cost.

  4. High SO{sub 2} removal duct injection: A low-cost FGD alternative

    SciTech Connect (OSTI)

    Nelson, S.G.

    1995-12-01

    Sorbent Technologies Corporation, of the United States, is currently developing and demonstrating a new waste free, retrofitable, high-SO{sub 2} removal duct-injection process. Up to 85 percent SO{sub 2} removal is achieved by simply injecting a new dry lime-based sorbent into the flue-gas duct, collecting the sorbent downstream in a particulate collector, and then recycling the sorbent. By avoiding large, expensive components, the process can have low capital costs, making it especially appropriate for smaller, older, less-utilized plants. The key to the new technology is the use of sorbent supports. Supported sorbents are produced by coating hydrated lime onto inexpensive mineral supports, such as exfoliated vermiculite or perlite. Consequently, there are no liquid, sludge, or solid wastes with the new technology. Once saturated with SO{sub 2}, the spent sorbent can be easily pelletized into a valuable soil-conditioning agricultural by-product, for the sustainable development that the future requires. This paper describes Sorbent Technologies` pilot demonstration of supported sorbent injection at the Ohio Edison Company`s R.E. Burger station. The Burger effort is also the first demonstration of the Electric Power Research Institute`s new {open_quotes}COHPAC{close_quotes} baghouse technology in a sorbent-injection desulfurization application.

  5. " Million Housing Units, Final...

    U.S. Energy Information Administration (EIA) Indexed Site

    ... Vacant housing units, seasonal units, second homes, military housing, and group quarters are excluded. 2Use of central air conditioning equipment for another housing unit also ...

  6. " Million Housing Units, Final...

    U.S. Energy Information Administration (EIA) Indexed Site

    ... Vacant housing units, seasonal units, second homes, military housing, and group quarters are excluded. 2Housing units are classified as urban or rural using definitions created by ...

  7. " Million Housing Units, Final...

    U.S. Energy Information Administration (EIA) Indexed Site

    ... Vacant housing units, seasonal units, second homes, military housing, and group quarters are excluded. 2Use of heating equipment for another housing unit also includes the use of ...

  8. " Million Housing Units, Final"

    U.S. Energy Information Administration (EIA) Indexed Site

    ... Vacant housing units, seasonal units, second homes, military housing, and group quarters are excluded. 2Use of central air conditioning equipment for another housing unit also ...

  9. Processing Cost Analysis for Biomass Feedstocks

    SciTech Connect (OSTI)

    Badger, P.C.

    2002-11-20

    The receiving, handling, storing, and processing of woody biomass feedstocks is an overlooked component of biopower systems. The purpose of this study was twofold: (1) to identify and characterize all the receiving, handling, storing, and processing steps required to make woody biomass feedstocks suitable for use in direct combustion and gasification applications, including small modular biopower (SMB) systems, and (2) to estimate the capital and operating costs at each step. Since biopower applications can be varied, a number of conversion systems and feedstocks required evaluation. In addition to limiting this study to woody biomass feedstocks, the boundaries of this study were from the power plant gate to the feedstock entry point into the conversion device. Although some power plants are sited at a source of wood waste fuel, it was assumed for this study that all wood waste would be brought to the power plant site. This study was also confined to the following three feedstocks (1) forest residues, (2) industrial mill residues, and (3) urban wood residues. Additionally, the study was confined to grate, suspension, and fluidized bed direct combustion systems; gasification systems; and SMB conversion systems. Since scale can play an important role in types of equipment, operational requirements, and capital and operational costs, this study examined these factors for the following direct combustion and gasification system size ranges: 50, 20, 5, and 1 MWe. The scope of the study also included: Specific operational issues associated with specific feedstocks (e.g., bark and problems with bridging); Opportunities for reducing handling, storage, and processing costs; How environmental restrictions can affect handling and processing costs (e.g., noise, commingling of treated wood or non-wood materials, emissions, and runoff); and Feedstock quality issues and/or requirements (e.g., moisture, particle size, presence of non-wood materials). The study found that over the

  10. Capital investment requirements for greenhouse gas emissions mitigation in power generation on near term to century time scales and global to regional spatial scales

    SciTech Connect (OSTI)

    Chaturvedi, Vaibhav; Clarke, Leon E.; Edmonds, James A.; Calvin, Katherine V.; Kyle, G. Page

    2014-11-01

    Electrification plays a crucial role in cost-effective greenhouse gas emissions mitigation strategies. Such strategies in turn carry implications for financial capital markets. This paper explores the implication of climate mitigation policy for capital investment demands by the electric power sector on decade to century time scales. We go further to explore the implications of technology performance and the stringency of climate policy for capital investment demands by the power sector. Finally, we discuss the regional distribution of investment demands. We find that stabilizing GHG emissions will require additional investment in the electricity generation sector over and above investments that would be need in the absence of climate policy, in the range of 16 to 29 Trillion US$ (60-110%) depending on the stringency of climate policy during the period 2015 to 2095 under default technology assumptions. This increase reflects the higher capital intensity of power systems that control emissions. Limits on the penetration of nuclear and carbon capture and storage technology could increase costs substantially. Energy efficiency improvements can reduce the investment requirement by 8 to21 Trillion US$ (default technology assumptions), depending on climate policy scenario with higher savings being obtained under the most stringent climate policy. The heaviest investments in power generation were observed in the China, India, SE Asia and Africa regions with the latter three regions dominating in the second half of the 21st century.

  11. Capital Asset Project List-June.xls

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Number Project Name Site Critical Decision Total Project Cost Approved Project End Date 15-D-411 Safety Significant Confinement Ventilation System Carlsbad CD-1 $280,000,000 3/31/2021 15-D-412 Exhaust Shaft Carlsbad CD-1 $118,000,000 3/31/2021 CBC-ETEC-0040.C1 Energy Technology Engineering Center Demolition Project ETEC CD-0 $29,000,000 9/30/2019 15-D-401 KW Basin Sludge Removal Project Hanford Site CD-3 $311,000,000 11/30/2019 RL-0011.C1 Plutonium Finishing Plant (PFP) Decontamination and

  12. Manufacturing R&D Initiative Lowers Costs and Boosts Quality

    SciTech Connect (OSTI)

    2015-06-30

    Fact sheet that provides an overview of DOE's Manufacturing R&D Initiative, which supports projects aimed at developing better-performing, lower-cost solid-state lighting while encouraging engineering and manufacturing in the United States.

  13. Estimating Costs and Efficiency of Storage, Demand, and Heat...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... Then, use the following calculations: For gas and oil water heaters You need to know the unit cost of fuel by Btu ... Water Heating Blogs Tax Tips for Energy Savers: Get Money ...

  14. Non-Hardware ("Soft") Cost-Reduction Roadmap for Residential and Small Commercial Solar Photovoltaics, 2013-2020

    SciTech Connect (OSTI)

    Ardani, K.; Seif, D.; Margolis, R.; Morris, J.; Davidson, C.; Truitt, S.; Torbert, R.

    2013-08-01

    The objective of this analysis is to roadmap the cost reductions and innovations necessary to achieve the U.S. Department of Energy (DOE) SunShot Initiative's total soft-cost targets by 2020. The roadmap focuses on advances in four soft-cost areas: (1) customer acquisition; (2) permitting, inspection, and interconnection (PII); (3) installation labor; and (4) financing. Financing cost reductions are in terms of the weighted average cost of capital (WACC) for financing PV system installations, with real-percent targets of 3.0% (residential) and 3.4% (commercial).

  15. " Million Housing Units, Final...

    U.S. Energy Information Administration (EIA) Indexed Site

    Water Heating in U.S. Homes, by Housing Unit Type, 2009" " Million Housing Units, Final" ... Units","5 or More Units","Mobile Homes" "Water Heating" "Total Homes",113.6,71.8,6.7,9,19...

  16. Cost analysis guidelines

    SciTech Connect (OSTI)

    Strait, R.S.

    1996-01-10

    The first phase of the Depleted Uranium Hexafluoride Management Program (Program)--management strategy selection--consists of several program elements: Technology Assessment, Engineering Analysis, Cost Analysis, and preparation of an Environmental Impact Statement (EIS). Cost Analysis will estimate the life-cycle costs associated with each of the long-term management strategy alternatives for depleted uranium hexafluoride (UF6). The scope of Cost Analysis will include all major expenditures, from the planning and design stages through decontamination and decommissioning. The costs will be estimated at a scoping or preconceptual design level and are intended to assist decision makers in comparing alternatives for further consideration. They will not be absolute costs or bid-document costs. The purpose of the Cost Analysis Guidelines is to establish a consistent approach to analyzing of cost alternatives for managing Department of Energy`s (DOE`s) stocks of depleted uranium hexafluoride (DUF6). The component modules that make up the DUF6 management program differ substantially in operational maintenance, process-options, requirements for R and D, equipment, facilities, regulatory compliance, (O and M), and operations risk. To facilitate a consistent and equitable comparison of costs, the guidelines offer common definitions, assumptions or basis, and limitations integrated with a standard approach to the analysis. Further, the goal is to evaluate total net life-cycle costs and display them in a way that gives DOE the capability to evaluate a variety of overall DUF6 management strategies, including commercial potential. The cost estimates reflect the preconceptual level of the designs. They will be appropriate for distinguishing among management strategies.

  17. A Cost-Benefit Assessment of Gasification-Based Biorefining in the Kraft Pulp and Paper Industry

    SciTech Connect (OSTI)

    Eric D. Larson; Stefano Consonni; Ryan E. Katofsky; Kristiina Iisa; W. James Frederick

    2007-03-31

    Production of liquid fuels and chemicals via gasification of kraft black liquor and woody residues (''biorefining'') has the potential to provide significant economic returns for kraft pulp and paper mills replacing Tomlinson boilers beginning in the 2010-2015 timeframe. Commercialization of gasification technologies is anticipated in this period, and synthesis gas from gasifiers can be converted into liquid fuels using catalytic synthesis technologies that are in most cases already commercially established today in the ''gas-to-liquids'' industry. These conclusions are supported by detailed analysis carried out in a two-year project co-funded by the American Forest and Paper Association and the Biomass Program of the U.S. Department of Energy. This work assessed the energy, environment, and economic costs and benefits of biorefineries at kraft pulp and paper mills in the United States. Seven detailed biorefinery process designs were developed for a reference freesheet pulp/paper mill in the Southeastern U.S., together with the associated mass/energy balances, air emissions estimates, and capital investment requirements. Commercial (''Nth'') plant levels of technology performance and cost were assumed. The biorefineries provide chemical recovery services and co-produce process steam for the mill, some electricity, and one of three liquid fuels: a Fischer-Tropsch synthetic crude oil (which would be refined to vehicle fuels at existing petroleum refineries), dimethyl ether (a diesel engine fuel or LPG substitute), or an ethanol-rich mixed-alcohol product. Compared to installing a new Tomlinson power/recovery system, a biorefinery would require larger capital investment. However, because the biorefinery would have higher energy efficiencies, lower air emissions, and a more diverse product slate (including transportation fuel), the internal rates of return (IRR) on the incremental capital investments would be attractive under many circumstances. For nearly all of the

  18. substantially reduced production costs

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    production costs - Sandia Energy Energy Search Icon Sandia Home Locations Contact Us Employee Locator Energy & Climate Secure & Sustainable Energy Future Stationary Power Energy ...

  19. SOFT COST GRAND CHALLENGE

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    energycenter.org California Center for Sustainable Energy Soft Cost Grand Challenge May 22, 2014 Accelerating the transition to a sustainable world powered by clean energy 2...

  20. Low Cost, Durable Seal

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    UTC Power Corporation February 14, 2007 This presentation does not contain any proprietary or confidential information 1 LOW COST, DURABLE SEAL Outline * Project Objective * ...