National Library of Energy BETA

Sample records for treatment procedure qualification

  1. Heat Treatment Procedure Qualification for Steel Castings

    SciTech Connect (OSTI)

    Mariol Charles; Nicholas Deskevich; Vipin Varkey; Robert Voigt; Angela Wollenburg

    2004-04-29

    Heat treatment practices used by steel foundries have been carefully studied as part of comprehensive heat treatment procedure qualification development trials. These studies highlight the relationships between critical heat treatment process control parameters and heat treatment success. Foundry heat treatment trials to develop heat treatment procedure qualifications have shed light on the relationship between heat treatment theory and current practices. Furnace load time-temperature profiles in steel foundries exhibit significant differences depending on heat treatment equipment, furnace loading practice, and furnace maintenance. Time-temperature profiles of furnace control thermocouples can be very different from the time-temperature profiles observed at the center of casting loads in the furnace. Typical austenitization temperatures and holding times used by steel foundries far exceed what is required for transformation to austenite. Quenching and hardenability concepts were also investigated. Heat treatment procedure qualification (HTPQ) schema to demonstrate heat treatment success and to pre-qualify other alloys and section sizes requiring lesser hardenability have been developed. Tempering success is dependent on both tempering time and temperature. As such, furnace temperature uniformity and control of furnace loading during tempering is critical to obtain the desired mechanical properties. The ramp-up time in the furnace prior to the establishment of steady state heat treatment conditions contributes to the extent of heat treatment performed. This influence of ramp-up to temperature during tempering has been quantified.

  2. Heat Treatment Procedure Qualification -- Final Technical Report

    SciTech Connect (OSTI)

    Robert C. Voigt

    2004-10-15

    Heat treatment practices used by steel foundries have been carefully studied as part of comprehensive heat treatment procedure development trials. These studies highlight the relationships between critical heat treatment process control parameters and heat treatment success. Foundry heat treatment trials to develop heat treatment procedure qualification have shed light on the relationship between heat treatment theory and current practices. Furnace load time-temperature profiles in steel foundries exhibit significant differences depending on heat treatment equipment, furnace loading practice, and furnace maintenance. Time-temperature profiles of the furnace control thermocouples can be very different from the time-temperature profiles observed at the center of casting loads in the furnace. Typical austenitrization temperatures and holding times used by steel foundries far exceed what is required for transformation to austenite. Quenching and hardenability concepts were also investigated. Heat treatment procedure qualification (HTPQ) schema to demonstrate heat treatment success and to pre-qualify other alloys and section sizes requiring lesser hardenability have been developed. Tempering success is dependent on both tempering time and temperature. As such, furnace temperature uniformity and control of furnace loading during tempering is critical to obtain the desired mechanical properties. The ramp-up time in the furnace prior to the establishment of steady state heat treatment conditions contributes to the extent of heat treatment performed. This influence of ramp-up to temperature during tempering has been quantified.

  3. Quality Procedure - Supplier Qualification | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Supplier Qualification Quality Procedure - Supplier Qualification This procedure establishes the responsibilities and process for supplier qualification activities conducted by Environmental Management (EM) Headquarters (HQ) Office of Standards and Quality Assurance in accordance with EM-QA-001, Environmental Management Quality Assurance Program. Quality Procedure - Supplier Qualification (2.03 MB) More Documents & Publications Quality Procedure - Approved Suppliers List Quality Procedure -

  4. Quality Procedure - Personnel Training and Qualification | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Personnel Training and Qualification Quality Procedure - Personnel Training and Qualification This procedure establishes the requirements for the training and qualification of personnel in the Office of Standards and Quality Assurance, and ensures that office personnel are properly trained and qualified to correctly perform their assigned tasks. Quality Procedure - Personnel Training and Qualification (4.29 MB) More Documents & Publications Quality Procedure - Supplier

  5. Light duty utility arm equipment qualification test procedure

    SciTech Connect (OSTI)

    Kiebel, G.R., Westinghouse Hanford

    1996-07-22

    The Equipment Qualification Test described in this test procedure document is the acceptance test procedure (ATP) for the LDUA Baseline System. It verifies that the equipment is complete and in working order, and demonstrates its readiness for being deployed into an actual underground storage tank.

  6. Lightning arrestor connector lead magnesium niobate qualification pellet test procedures.

    SciTech Connect (OSTI)

    Tuohig, W.; Mahoney, Patrick A.; Tuttle, Bruce Andrew; Wheeler, Jill Susanne

    2009-02-01

    Enhanced knowledge preservation for DOE DP technical component activities has recently received much attention. As part of this recent knowledge preservation effort, improved documentation of the sample preparation and electrical testing procedures for lead magnesium niobate--lead titanate (PMN/PT) qualification pellets was completed. The qualification pellets are fabricated from the same parent powders used to produce PMN/PT lightning arrestor connector (LAC) granules at HWF&T. In our report, the procedures for fired pellet surface preparation, electrode deposition, electrical testing and data recording are described. The dielectric measurements described in our report are an information only test. Technical reasons for selecting the electrode material, electrode size and geometry are presented. The electrical testing is based on measuring the dielectric constant and dissipation factor of the pellet during cooling from 280 C to 220 C. The most important data are the temperature for which the peak dielectric constant occurs (Curie Point temperature) and the peak dielectric constant magnitude. We determined that the peak dielectric constant for our procedure would be that measured at 1 kHz at the Curie Point. Both the peak dielectric constant and the Curie point parameters provide semi-quantitative information concerning the chemical and microstructural homogeneity of the parent material used for the production of PMN/PT granules for LACs. Finally, we have proposed flag limits for the dielectric data for the pellets. Specifically, if the temperature of the peak dielectric constant falls outside the range of 250 C {+-} 30 C we propose that a flag limit be imposed that will initiate communication between production agency and design agency personnel. If the peak dielectric constant measured falls outside the range 25,000 {+-} 10,000 we also propose that a flag limit be imposed.

  7. FAQS Qualification Card – Confinement Ventilation and Process Gas Treatment

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  8. Hanford Tank Waste Treatment and Immobilization Plant (WTP) Waste Feed Qualification Program Development Approach - 13114

    SciTech Connect (OSTI)

    Markillie, Jeffrey R.; Arakali, Aruna V.; Benson, Peter A.; Halverson, Thomas G.; Adamson, Duane J.; Herman, Connie C.; Peeler, David K.

    2013-07-01

    The Hanford Tank Waste Treatment and Immobilization Plant (WTP) is a nuclear waste treatment facility being designed and constructed for the U.S. Department of Energy by Bechtel National, Inc. and subcontractor URS Corporation (under contract DE-AC27-01RV14136 [1]) to process and vitrify radioactive waste that is currently stored in underground tanks at the Hanford Site. A wide range of planning is in progress to prepare for safe start-up, commissioning, and operation. The waste feed qualification program is being developed to protect the WTP design, safety basis, and technical basis by assuring acceptance requirements can be met before the transfer of waste. The WTP Project has partnered with Savannah River National Laboratory to develop the waste feed qualification program. The results of waste feed qualification activities will be implemented using a batch processing methodology, and will establish an acceptable range of operator controllable parameters needed to treat the staged waste. Waste feed qualification program development is being implemented in three separate phases. Phase 1 required identification of analytical methods and gaps. This activity has been completed, and provides the foundation for a technically defensible approach for waste feed qualification. Phase 2 of the program development is in progress. The activities in this phase include the closure of analytical methodology gaps identified during Phase 1, design and fabrication of laboratory-scale test apparatus, and determination of the waste feed qualification sample volume. Phase 3 will demonstrate waste feed qualification testing in support of Cold Commissioning. (authors)

  9. Development Of A Macro-Batch Qualification Strategy For The Hanford Tank Waste Treatment And Immobilization Plant

    SciTech Connect (OSTI)

    Herman, Connie C.

    2013-09-30

    The Savannah River National Laboratory (SRNL) has evaluated the existing waste feed qualification strategy for the Hanford Tank Waste Treatment and Immobilization Plant (WTP) based on experience from the Savannah River Site (SRS) Defense Waste Processing Facility (DWPF) waste qualification program. The current waste qualification programs for each of the sites are discussed in the report to provide a baseline for comparison. Recommendations on strategies are then provided that could be implemented at Hanford based on the successful Macrobatch qualification strategy utilized at SRS to reduce the risk of processing upsets or the production of a staged waste campaign that does not meet the processing requirements of the WTP. Considerations included the baseline WTP process, as well as options involving Direct High Level Waste (HLW) and Low Activity Waste (LAW) processing, and the potential use of a Tank Waste Characterization and Staging Facility (TWCSF). The main objectives of the Hanford waste feed qualification program are to demonstrate compliance with the Waste Acceptance Criteria (WAC), determine waste processability, and demonstrate unit operations at a laboratory scale. Risks to acceptability and successful implementation of this program, as compared to the DWPF Macro-Batch qualification strategy, include: Limitations of mixing/blending capability of the Hanford Tank Farm; The complexity of unit operations (i.e., multiple chemical and mechanical separations processes) involved in the WTP pretreatment qualification process; The need to account for effects of blending of LAW and HLW streams, as well as a recycle stream, within the PT unit operations; and The reliance on only a single set of unit operations demonstrations with the radioactive qualification sample. This later limitation is further complicated because of the 180-day completion requirement for all of the necessary waste feed qualification steps. The primary recommendations/changes include the

  10. Welding procedure specification. Supplement 1. Records of procedure qualification tests. Gas tungsten arc welding of nickel to nickel-copper

    SciTech Connect (OSTI)

    Wodtke, C.H.; Frizzell, D.R.; Plunkett, W.A.

    1986-06-01

    Procedure WPS-2301-ASME-3 is qualified under Section IX of the ASME Boiler and Pressure Vessel Code for gas tungsten arc welding of nickel, NO2200 or NO2201 (P-41) to nickel-copper NO4400 (P-42), in thickness range 0.035 to 0.432 inch; filler metal is ERNiCu-7 (F-42); shielding gas is argon.

  11. Welding procedure specification. Supplement 1. Records of procedure qualification tests. Gas tungsten arc welding of nickel-copper

    SciTech Connect (OSTI)

    Wodtke, C.H.; Frizzell, D.R.; Plunkett, W.A.

    1986-06-01

    Procedure WPS-1302-ASME-3 is qualified under Section IX of the ASME Boiler and Pressure Vessel Code for gas tungsten arc welding of nickel-copper NO4400 (P-42), in thickness range 0.035 to 0.432 inch; filler metal is ERNiCu-7 (F-42); shielding gas is argon.

  12. Oregon Procedure and Criteria for Hazardous Waste Treatment,...

    Open Energy Info (EERE)

    Procedure and Criteria for Hazardous Waste Treatment, Storage or Disposal Permits Fact Sheet Jump to: navigation, search OpenEI Reference LibraryAdd to library Permitting...

  13. Environmental Management (EM) Quality Procedures | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Quality Procedure - Records Management Quality Procedure - MemoCorrespondence Control and Tracking Quality Procedure - Stop Work Quality Procedure - Supplier Qualification ...

  14. Functional Area Qualification Standard Qualification Cards | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Qualification Cards Functional Area Qualification Standard Qualification Cards Note: 1. Save the document from the website onto your PC and close it. 2. Open the document on your PC. Answer "No" to the question regarding whether to open the documents as read only. Aviation Manager Aviation Safety Officer Chemical Processing Civil Structural Engineering Confinement Ventilation and Process Gas Treatment Construction Management Criticality Safety Deactivation and

  15. Welding procedure specification. Supplement 1. Records of procedure qualification tests. Gas tungsten arc welding of chromium-nickel steel to nickel-copper

    SciTech Connect (OSTI)

    Wodtke, C.H.; Frizzell, D.R.; Plunkett, W.A.

    1986-06-01

    Procedure WPS-2602-ASME-3 is qualified under Section IX of the ASME Boiler and Pressure Vessel Code for gas tungsten arc welding of 300 series Cr-Ni steels (P-8-1) to nickel-copper N04400 (P-42), in thickness range 0.035 to 0.432 inch; filler metal is ERNiCu-7 (F-42); shielding gas is argon.

  16. Welding procedure specification: gas tungsten arc welding of nickel-copper to nickel-chromium-iron. Supplement 1. Records of procedure qualification tests

    SciTech Connect (OSTI)

    Wodtke, C.H.; Frizzell, D.R.; Plunkett, W.A.

    1986-06-01

    Procedure WPS-2303-ASME-3 is qualified under Section IX of the ASME Boiler and Pressure Vessel Code for gas tungsten arc welding of nickel-copper N04400 (P-42) to nickel-chromium-iron N06600 (P-43), in thickness range of 0.035 to 0.432 inch; filler metal is ERNiCu-7 (F-42); shielding gas is argon.

  17. Nuclear Waste Treatment Program: Qualification of commercial high-level waste forms: Approach and status

    SciTech Connect (OSTI)

    Brouns, R.A.; Kuhn, W.L.

    1986-12-01

    In this document, the Nuclear Waste Treatment Program (NWTP) proposes an approach for demonstrating compliance with acceptance specifications. The proposed approach relies first on developing models of the process (vitrification) and product (waste form) to relate measurable process variables to the product quality, and then on using process control and sampling of melter feed input as the quality control method. Coordinated test programs, using pilot-scale nonradioactive and radioactive tests, will be used to establish these models at the confidence level needed to assure compliance to waste acceptance specifications. The test programs are broadly focused to encompass the range of anticipated future wastes, but the results should also be equally applicable to current wastes as well. Demonstration of waste form compliance by some other method would likely require extensive product testing, including glass sampling during production and routine destructive examination of canisters. The process and product modeling approach eliminates the need for this type of testing and should result in a very high level of statistical confidence that the individual waste forms are acceptable for disposal.

  18. Procedures

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Procedures A NSSAB outreach display is available for community events The Nevada Site Specific Advisory Board (NSSAB) abides by a variety of federal and self-imposed procedures. For more information on these procedures please click on the items below: Federal Advisory Committee Act Nevada Site Specific Advisory Board Standard Operating Procedures Advisory Committee Management Program Manual National Charter EM Site Specific Advisory Board Policies and Procedures Desk Reference Send mail to

  19. Test Cloth Qualification | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Cloth Qualification Test Cloth Qualification The Department of Energy (DOE) develops standardized data templates for reporting the results of tests conducted in accordance with current DOE test procedures. Templates may be used by third-party laboratories under contract with DOE that conduct testing in support of ENERGY STAR® verification, DOE rulemakings, and enforcement of the federal energy conservation standards. Test Cloth Correction Factors -- v2.0 (64.84 KB) More Documents &

  20. FAQS Gap Analysis Qualification Card - Occupational Safety |...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Occupational Safety FAQS Gap Analysis Qualification Card - Occupational Safety Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences ...

  1. FAQS Gap Analysis Qualification Card - Chemical Processing |...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Chemical Processing FAQS Gap Analysis Qualification Card - Chemical Processing Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences ...

  2. Firearms Qualification Courses Manual

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2002-01-17

    Provides detailed requirements for qualification with various firearms. Errata Sheet 5-29-02. Cancels DOE M 473.2-1.

  3. Siemens Government Services ESCO Qualification Sheet | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Siemens Government Services ESCO Qualification Sheet Siemens Government Services ESCO Qualification Sheet Fact sheet outlines the energy service company (ESCO) qualification for ...

  4. Firearms Qualification Courses Manual

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-08-21

    Defines the required courses of fire for authorized firearms in order to ensure the uniform qualification and requalification of DOE Federal Officers and Security Police Officers by certified Federal and contractor firearms instructors.

  5. Facility Representative Qualification Equivalencies Based on...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Facility Representative Qualification Equivalencies Based on Previous Experience Facility Representative Qualification Equivalencies Based on Previous Experience The referenced ...

  6. Functional Area Qualification Standard Gap Analysis Qualification Cards

    Broader source: Energy.gov [DOE]

    FAQS Gap Analysis Qualification Cards outline the differences between the last and latest version of the FAQ Standard.

  7. SRNL PHASE 1 ASSESSMENT OF THE WAC/DQO AND UNIT OPERATIONS FOR THE WTP WASTE QUALIFICATION PROGRAM

    SciTech Connect (OSTI)

    Peeler, D.; Adamson, D.; Bannochie, C.; Cozzi, A.; Eibling, R.; Hay, M.; Hansen, E.; Herman, D.; Martino, C.; Nash, C.; Pennebaker, F.; Poirier, M.; Reboul, S.; Stone, M.; Taylor-Pashow, K.; White, T.; Wilmarth, B.

    2012-05-16

    The Hanford Tank Waste Treatment and Immobilization Plant (WTP) is currently transitioning its emphasis from a design and construction phase toward start-up and commissioning. With this transition, the WTP Project has initiated more detailed assessments of the requirements related to actual processing of the Hanford Site tank waste. One particular area of interest is the waste qualification program to be implemented to support the WTP. Given the successful implementation of similar waste qualification efforts at the Savannah River Site (SRS), based on critical technical support and guidance from the Savannah River National Laboratory (SRNL), WTP requested the utilization of subject matter experts from SRNL to support a technology exchange to perform a review of the WTP waste qualification program, discuss the general qualification approach at SRS, and to identify critical lessons learned through the support of DWPF's sludge batch qualification efforts. As part of Phase 1, SRNL subject matter experts in critical technical and/or process areas reviewed specific WTP waste qualification information. The Phase 1 review was a collaborative, interactive, and iterative process between the two organizations. WTP provided specific analytical procedures, descriptions of equipment, and general documentation as baseline review material. SRNL subject matter experts reviewed the information and, as appropriate, requested follow-up information or clarification to specific areas of interest. This process resulted in multiple teleconferences with key technical contacts from both organizations resolving technical issues that lead to the results presented in this report. This report provides the results of SRNL's Phase 1 review of the WAC-DQO waste acceptance criteria and processability parameters, and the specific unit operations which are required to support WTP waste qualification efforts. The review resulted in SRNL providing concurrence, alternative methods, or gap identification

  8. Firearms Qualification Courses Manual

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-07-08

    Defines the required courses of fire for authorized firearms in order to ensure the uniform qualification and requalification of DOE Federal Officers and Security Police Officers by certified Federal and contractor firearms instructors. DOE N 251.40, dated 5-3-01, extends this directive until 12-31-01. Cancels DOE M 5632.7-1.

  9. Quality control procedures for dynamic treatment delivery techniques involving couch motion

    SciTech Connect (OSTI)

    Yu, Victoria Y.; Fahimian, Benjamin P.; Xing, Lei; Hristov, Dimitre H.

    2014-08-15

    In this study, the authors introduce and demonstrate quality control procedures for evaluating the geometric and dosimetric fidelity of dynamic treatment delivery techniques involving treatment couch motion synchronous with gantry and multileaf collimator (MLC). Tests were designed to evaluate positional accuracy, velocity constancy and accuracy for dynamic couch motion under a realistic weight load. A test evaluating the geometric accuracy of the system in delivering treatments over complex dynamic trajectories was also devised. Custom XML scripts that control the Varian TrueBeam STx (Serial #3) axes in Developer Mode were written to implement the delivery sequences for the tests. Delivered dose patterns were captured with radiographic film or the electronic portal imaging device. The couch translational accuracy in dynamic treatment mode was 0.01 cm. Rotational accuracy was within 0.3, with 0.04 cm displacement of the rotational axis. Dose intensity profiles capturing the velocity constancy and accuracy for translations and rotation exhibited standard deviation and maximum deviations below 3%. For complex delivery involving MLC and couch motions, the overall translational accuracy for reproducing programmed patterns was within 0.06 cm. The authors conclude that in Developer Mode, TrueBeam is capable of delivering dynamic treatment delivery techniques involving couch motion with good geometric and dosimetric fidelity.

  10. Quality Procedure - Audits | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Audits Quality Procedure - Audits This procedure establishes the responsibilities and process for scheduling, planning, performing, and reporting Quality Assurance (QA) audits of EM-QA-001, Environmental Management Quality Assurance Program implementation at EM Headquarters and Field Office programs, facilities and projects. Quality Procedure - Audits (5.04 MB) More Documents & Publications Quality Procedure - Document Control Quality Procedure - Supplier Qualification Quality Procedure -

  11. Quality Procedure - Document Control | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Control Quality Procedure - Document Control This procedure establishes the responsibilities and process for preparing, managing, and revising EM Headquarters Office of Standards and Quality Assurance controlled documents in accordance with EM-QA-001, Environmental Management Quality Assurance Program. Quality Procedure - Document Control (2.6 MB) More Documents & Publications Quality Procedure - Supplier Qualification Quality Procedure - Approved Suppliers List Quality Procedure - Records

  12. Sandia Satellite Program summary of operational procedures

    SciTech Connect (OSTI)

    Not Available

    1989-08-01

    Operational procedures for the Space Systems Department and Space Sensors Department are described. Departmental policies and procedures from design of systems for space applications through qualification for spaceflight are summarized. 1 fig.

  13. Firearms Qualification Courses Manual

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1992-12-01

    The U.S. Department of Energy (DOE) requires all protective force personnel authorized to carry firearms to receive proper firearms training and qualification. The most important part of such training is the proper use of deadly force, which is included in the DOE Basic Security policy officer Program and is available as a separate program through the Safeguards and Security Central Training Academy. Canceled by DOE M 473.2-1 dated 07/08/1997.

  14. Lockheed Martin ESCO Qualification Sheet

    Office of Energy Efficiency and Renewable Energy (EERE)

    Document outlines the energy service company (ESCO) qualifications sheet for Lockheed Martin under the Department of Energy's (DOEs) energy savings performance contract (ESPC).

  15. ORISE: Training and Qualification Programs

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    By completing the program-which features qualification standards and corresponding training activities-DOE personnel build knowledge, skills and confidence to carry out...

  16. Schneider Electric ESCO Qualification Sheet

    Broader source: Energy.gov [DOE]

    Fact sheet outlines the energy service company (ESCO) qualifications for Schneider Electric in relation to the U.S. Department of Energy's (DOEs) energy savings performance contracts (ESPC).

  17. Consolidated Edison Solutions, Inc. ESCO Qualification Sheet...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Sheet Consolidated Edison Solutions, Inc. ESCO Qualification Sheet Document outlines the energy service company (ESCO) qualifications for ConEdison Solutions. PDF icon ces

  18. Advanced Qualification of Additive Manufacturing Materials Workshop

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Advanced Qualification of Additive Manufacturing Materials Workshop Advanced Qualification of Additive Manufacturing Materials Workshop WHEN: Jul 20, 2015 8:30 AM - Jul 21, 2015...

  19. FAQS Gap Analysis Qualification Card Emergency Management

    Broader source: Energy.gov [DOE]

    Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between the last and latest version of the FAQ Standard.

  20. FAQS Qualification Card - Nuclear Safety Specialist | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Programs is a set of common Functional Area Qualification Standards (FAQS) and ... More Documents & Publications FAQS Gap Analysis Qualification Card - Nuclear Safety ...

  1. FAQS Qualification Card - NNSA Package Certification Engineer...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Programs is a set of common Functional Area Qualification Standards (FAQS) and ... More Documents & Publications FAQS Gap Analysis Qualification Card - Nuclear Explosive ...

  2. FAQS Qualification Card - Industrial Hygiene | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Programs is a set of common Functional Area Qualification Standards (FAQS) and ... More Documents & Publications FAQS Gap Analysis Qualification Card - Industrial Hygiene ...

  3. FAQS Qualification Card - Instrumentation and Control | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Programs is a set of common Functional Area Qualification Standards (FAQS) and ... DOE-STD-1162-2013 FAQS Qualification Card - Chemical Processing FAQS Gap Analysis ...

  4. FAQS Qualification Card - Mechanical Systems | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Programs is a set of common Functional Area Qualification Standards (FAQS) and ... More Documents & Publications FAQS Gap Analysis Qualification Card - Mechanical Systems ...

  5. FAQS Qualification Card - Chemical Processing | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Programs is a set of common Functional Area Qualification Standards (FAQS) and ... More Documents & Publications FAQS Gap Analysis Qualification Card - Chemical Processing ...

  6. Chemical Processing Qualification Standard

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    6-2010 February 2010 DOE STANDARD CHEMICAL PROCESSING QUALIFICATION STANDARD DOE Defense Nuclear Facilities Technical Personnel U.S. Department of Energy AREA TRNG Washington, D.C. 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. DOE-STD-1176-2010 ii This document is available on the Department of Energy Technical Standards Program Web Site at http://www.hss.energy.gov/nuclearsafety/ns/techstds DOE-STD-1176-2010 iv INTENTIONALLY BLANK DOE-STD-1176-2010 v

  7. FAQS Qualification Card- Aviation Manager

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  8. FAQS Qualification Card Emergency Management

    Broader source: Energy.gov [DOE]

    A key element for the Departments Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  9. FAQS Qualification Card Waste Management

    Broader source: Energy.gov [DOE]

    A key element for the Departments Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  10. FAQS Qualification Card- Construction Management

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  11. SRNL PHASE 1 ASSESSMENT OF THE WTP WASTE QUALIFICATION PROGRAM

    SciTech Connect (OSTI)

    Peeler, D.; Hansen, E.; Herman, C.; Marra, S.; Wilmarth, B.

    2012-03-06

    The Hanford Tank Waste Treatment and Immobilization Plant (WTP) Project is currently transitioning its emphasis from an engineering design and construction phase toward facility completion, start-up and commissioning. With this transition, the WTP Project has initiated more detailed assessments of the requirements that must be met during the actual processing of the Hanford Site tank waste. One particular area of interest is the waste qualification program. In general, the waste qualification program involves testing and analysis to demonstrate compliance with waste acceptance criteria, determine waste processability, and demonstrate laboratory-scale unit operations to support WTP operations. The testing and analysis are driven by data quality objectives (DQO) requirements necessary for meeting waste acceptance criteria for transfer of high-level wastes from the tank farms to the WTP, and for ensuring waste processability including proper glass formulations during processing within the WTP complex. Given the successful implementation of similar waste qualification efforts at the Savannah River Site (SRS) which were based on critical technical support and guidance from the Savannah River National Laboratory (SRNL), WTP requested subject matter experts (SMEs) from SRNL to support a technology exchange with respect to waste qualification programs in which a critical review of the WTP program could be initiated and lessons learned could be shared. The technology exchange was held on July 18-20, 2011 in Richland, Washington, and was the initial step in a multi-phased approach to support development and implementation of a successful waste qualification program at the WTP. The 3-day workshop was hosted by WTP with representatives from the Tank Operations Contractor (TOC) and SRNL in attendance as well as representatives from the US DOE Office of River Protection (ORP) and the Defense Nuclear Facility Safety Board (DNFSB) Site Representative office. The purpose of the

  12. NORESCO ESCO Qualification Sheet | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    NORESCO ESCO Qualification Sheet NORESCO ESCO Qualification Sheet Document outlines the energy service company (ESCO) qualifications for NORESCO in relation to the U.S. Department of Energy's (DOEs) energy savings performance contracts (ESPC). Download the NORESCO ESCO Qualification Sheet. (173.64 KB)

  13. Ameresco ESCO Qualification Sheet | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Ameresco ESCO Qualification Sheet Ameresco ESCO Qualification Sheet Document outlines the energy service company (ESCO) qualifications for Ameresco in relation to the U.S. Department of Energy's (DOEs) energy savings performance contracts (ESPC). Download the Ameresco ESCO Qualification Sheet. (125.39 KB

  14. Technical Qualification Program Accreditation Schedule | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Schedule Technical Qualification Program Accreditation Schedule Technical Qualification Program (TQP) Accreditation Schedule for CY 2013 and 2014. TQP Accreditation Schedule (74.14 KB) More Documents & Publications Technical Qualification Program Self-Assessment Report - Nevada Site Office - 2009 Technical Qualification Program Self-Assessment Report - Richland Operations Office - 2014 FTCP Corrective Action Plan - Revision 1

  15. TOUGH2 software qualification

    SciTech Connect (OSTI)

    Pruess, K.; Simmons, A.; Wu, Y.S.; Moridis, G.

    1996-02-01

    TOUGH2 is a numerical simulation code for multi-dimensional coupled fluid and heat flow of multiphase, multicomponent fluid mixtures in porous and fractured media. It belongs to the MULKOM ({open_quotes}MULti-KOMponent{close_quotes}) family of codes and is a more general version of the TOUGH simulator. The MULKOM family of codes was originally developed with a focus on geothermal reservoir simulation. They are suited to modeling systems which contain different fluid mixtures, with applications to flow problems arising in the context of high-level nuclear waste isolation, oil and gas recovery and storage, and groundwater resource protection. TOUGH2 is essentially a subset of MULKOM, consisting of a selection of the better tested and documented MULKOM program modules. The purpose of this package of reports is to provide all software baseline documents necessary for the software qualification of TOUGH2.

  16. Protocol, Qualification Standard for the Site Lead Program -...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Qualification Standard for the Site Lead Program - May 2011 Protocol, Qualification Standard for the Site Lead Program - May 2011 May 2011 Qualification Standard for the Site Lead...

  17. Microsoft Word - Attachment D - Position Qualifications.docx

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    D - POSITION QUALIFICATIONS POSITION QUALIFICATIONS NOTE: If accepted, the labor category and minimum position qualifications proposed will be incorporated into (andor replace)...

  18. FAQS Gap Analysis Qualification Card - Technical Training | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Technical Training FAQS Gap Analysis Qualification Card - Technical Training Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between ...

  19. FAQS Gap Analysis Qualification Card - Industrial Hygiene | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Industrial Hygiene FAQS Gap Analysis Qualification Card - Industrial Hygiene Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between ...

  20. FAQS Gap Analysis Qualification Card - Nuclear Safety Specialist...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Nuclear Safety Specialist FAQS Gap Analysis Qualification Card - Nuclear Safety Specialist Functional Area Qualification Standard Gap Analysis Qualification Cards outline the ...

  1. FAQS Gap Analysis Qualification Card - Quality Assurance | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Quality Assurance FAQS Gap Analysis Qualification Card - Quality Assurance Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between ...

  2. FAQS Gap Analysis Qualification Card - Senior Technical Safety...

    Office of Environmental Management (EM)

    Senior Technical Safety Manager FAQS Gap Analysis Qualification Card - Senior Technical Safety Manager Functional Area Qualification Standard Gap Analysis Qualification Cards ...

  3. Benham Companies ESCO Qualification Sheet

    Office of Energy Efficiency and Renewable Energy (EERE)

    Document outlines the energy service company (ESCO) qualifications for Leidos Engineering (part of Benham Companies) in relation to the U.S. Department of Energy's (DOE) energy savings performance contracts (ESPC).

  4. CONSIDERATIONS FOR THE TREATMENT OF COMPUTERIZED PROCEDURES IN HUMAN RELIABILITY ANALYSIS

    SciTech Connect (OSTI)

    Ronald L. Boring; David I. Gertman

    2012-07-01

    Computerized procedures (CPs) are an emerging technology within nuclear power plant control rooms. While CPs have been implemented internationally in advanced control rooms, to date no US nuclear power plant has implemented CPs in its main control room. Yet, CPs are a reality of new plant builds and are an area of considerable interest to existing plants, which see advantages in terms of easier records management by omitting the need for updating hardcopy procedures. The overall intent of this paper is to provide a characterization of human reliability analysis (HRA) issues for computerized procedures. It is beyond the scope of this document to propose a new HRA approach or to recommend specific methods or refinements to those methods. Rather, this paper serves as a review of current HRA as it may be used for the analysis and review of computerized procedures.

  5. Construction, Qualification, and Low Rate Production Start-up...

    Broader source: Energy.gov (indexed) [DOE]

    More Documents & Publications Construction, Qualification, and Low Rate Production ... 100,000 Electric Drive Vehicles Construction, Qualification, and Low Rate ...

  6. Construction, Qualification, and Low Rate Production Start-up...

    Broader source: Energy.gov (indexed) [DOE]

    KB) More Documents & Publications Construction, Qualification, and Low Rate ... 100,000 Electric Drive Vehicles Construction, Qualification, and Low Rate ...

  7. FTCP-08-002, Technical Qualification Program Requalification...

    Broader source: Energy.gov (indexed) [DOE]

    More Documents & Publications Technical Qualification Program Self-Assessment Report - Richland Operations Office - 2014 Technical Qualification Program Accreditation Report - ...

  8. Functional Area Qualification Standards | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Qualification Standard Qualification Standard Number Approved Aviation Manager DOE-STD-1165-2003 (CN-1) 2009-12 Aviation Safety Officer DOE-STD-1164-2003 (CN-1) 2010-01 Chemical ...

  9. Fire Protection Engineering Functional Area Qualification Standard

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    FIRE PROTECTION ENGINEERING FUNCTIONAL AREA QUALIFICATION STANDARD DOE Defense Nuclear Facilities Technical ... by applied engineering fundamentals, research, fire hazard ...

  10. Functional Area Qualification Standard Reference Guides

    Broader source: Energy.gov [DOE]

    The reference guides have been developed to address the competency statements in DOE Functional Area Qualification Standard.

  11. Memorandum, Technical Qualification Program Accreditation Incentives |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Technical Qualification Program Accreditation Incentives Memorandum, Technical Qualification Program Accreditation Incentives The National Nuclear Security Admin istration (NNSA) Technica l Qualification Program (TQP) was established as a process to ensure Federal technical employees possess the necessary knowledge, skills, and abilities to perform their assigned duties and responsibilities. The TQP enhances the ability of the NNSA and Department of Energy (DOE) to

  12. Technical Qualification Program Accreditation Objectives and Criteria |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Objectives and Criteria Technical Qualification Program Accreditation Objectives and Criteria The program clearly identifies and documents the process used to demonstrate employee technical competence. TQP Accreditation Objectives and Criteria (40.57 KB) More Documents & Publications Technical Qualification Program Self-Assessment Report - Sandia Site Office - 2012 Technical Qualification Program Self-Assessment Report - Richland Operations Office - 2014 Technical

  13. General numerical procedure for the treatment of moving interfaces in implicit continuous Eulerian (ICE) hydrodynamics

    SciTech Connect (OSTI)

    Smith, B.L.

    1988-08-01

    The implicit continuous Eulerian (ICE) finite difference method in hydrodynamic computations has proven very successful when applied to flow situations in which there are excessive fluid distortions. Code logic becomes exceedingly complex, however, if the boundaries of the fluid domain are material interfaces whose orientations with respect to the Eulerian grid evolve during the calculation. It is shown in this article that within the ICE methodology it is possible to express the discrete mass conservation condition in an identical form for all computational cells, even those containing, or close to, moving fluid boundaries. From this basis a generalised ICE algorithm is built up alleviating many of the difficulties associated with complicated configurations of free and structure boundaries. In particular, an effective treatment of slug impact with fluid-structure interaction is readily formulated. To illustrate the technique in practical situations, the method has been incorporated into a version of the coupled fluid-structure code SEURBNUK-EURDYN, used for LMFBR safety analysis, and a number of fluid--gas, fluid--structure situations are analysed. Results are compared with analytic solutions, experimental measurement, and/or other code predictions, as appropriate. Two oblique, slug impact situations are included. copyright 1988 Academic Press, Inc.

  14. Accelerated Stress Testing, Qualification Testing, HAST, Field...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Accelerated Stress Testing, Qualification Testing, HAST, Field Experience This presentation, which was the opening session of the NREL 2013 Photovoltaic Module Reliability Workshop ...

  15. Clark Energy Group ESCO Qualification Sheet

    Broader source: Energy.gov [DOE]

    Document outlines the energy service company (ESCO) qualifications for Clark Energy Group in relation to the U.S. Department of Energy's (DOEs) energy savings performance contracts (ESPC).

  16. Safeguards and Security Functional Area Qualification Standard

    Energy Savers [EERE]

    ... Describe the levels, associated responsibilities, and qualification requirements of PF personnel within DOE. e. Discuss the authority and responsibility for issuing credentials and ...

  17. Qualification of Alternative Fuels | Department of Energy

    Energy Savers [EERE]

    Oil Workshop on the qualification of alternative fuels. pyrolysisbutcher.pdf (1.23 MB) More Documents & Publications Technical Information Exchange on Pyrolysis Oil: ...

  18. Energy Systems Group ESCO Qualification Sheet

    Broader source: Energy.gov [DOE]

    Document outlines the energy service company (ESCO) qualifications for Energy Systems Group in relation to U.S. Department of Energy (DOE) energy savings performance contracts (ESPC).

  19. AVIATION MANAGER QUALIFICATION STANDARD REFERENCE GUIDE

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Manager Qualification Standard Reference Guide MARCH 2010 i This page is intentionally blank. Table of Contents ii LIST OF FIGURES ..................................................................................................................... iii LIST OF TABLES ....................................................................................................................... iii ACRONYMS

  20. AVIATION SAFETY OFFICER QUALIFICATION STANDARD REFERENCE GUIDE

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Safety Officer Qualification Standard Reference Guide MARCH 2010 i This page is intentionally blank. Table of Contents ii LIST OF FIGURES ..................................................................................................................... iii LIST OF TABLES ....................................................................................................................... iii ACRONYMS

  1. Safety Software Quality Assurance Functional Area Qualification...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    72-2011, Safety Software Quality Assurance Functional Area Qualification Standard by Diane Johnson This SSQA FAQS identifies the minimum technical competency requirements for DOE...

  2. FPL Energy Services ESCO Qualification Sheet

    Broader source: Energy.gov [DOE]

    Document outlines the energy service company (ESCO) qualifications for FPL Energy Services in relation to the U.S. Department of Energy's (DOEs) energy savings performance contract (ESPC).

  3. Advanced Qualification of Additive Manufacturing Workshop

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Additive Manufacturing Workshop Poster Abstract Submission - deadline July 10, 2015 Advanced Qualification of Additive Manufacturing Materials using in situ sensors, diagnostics...

  4. Technical Qualification Program Accreditation Objectives and...

    Broader source: Energy.gov (indexed) [DOE]

    TQP Accreditation Objectives and Criteria (40.57 KB) More Documents & Publications Technical Qualification Program Self-Assessment Report - Sandia Site Office - 2012 Technical ...

  5. Business Case for Technical Qualification Program Accreditation...

    Broader source: Energy.gov (indexed) [DOE]

    Business Case for TQP Accreditation Incentives (21.27 KB) More Documents & Publications Technical Qualification Program Self-Assessment Report - Los Alamos Site Office - 2007 ...

  6. Technical Qualification Program Reaccreditation Report - Y-12...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Reaccreditation Report - Y-12 Site Office Technical Qualification Program Reaccreditation Report - Y-12 Site Office The accreditation process consists of three distinct activities: ...

  7. FAQS Qualification Card - Confinement Ventilation and Process...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    For each functional area, the FAQS identify the minimum technical competencies and ... More Documents & Publications DOE-STD-1168-2013 FAQS Gap Analysis Qualification Card - ...

  8. FAQS Gap Analysis Qualification Card – Environmental Restoration

    Broader source: Energy.gov [DOE]

    Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between the last and latest version of the FAQ Standard.

  9. FAQS Gap Analysis Qualification Card – Nuclear Explosive Safety Study

    Broader source: Energy.gov [DOE]

    Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between the last and latest version of the FAQ Standard.

  10. FAQS Gap Analysis Qualification Card – Facility Representative

    Broader source: Energy.gov [DOE]

    Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between the last and latest version of the FAQ Standard.

  11. FAQS Gap Analysis Qualification Card – Senior Technical Safety Manager

    Broader source: Energy.gov [DOE]

    Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between the last and latest version of the FAQ Standard.

  12. FAQS Gap Analysis Qualification Card – Criticality Safety

    Broader source: Energy.gov [DOE]

    Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between the last and latest version of the FAQ Standard.

  13. Model Request for Qualifications to Pre-Qualify Energy Service...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Request for Qualifications to Pre-Qualify Energy Service Companies Model Request for Qualifications to Pre-Qualify Energy Service Companies This page contains a model Request for ...

  14. FAQS Gap Analysis Qualification Card – Radiation Protection

    Office of Energy Efficiency and Renewable Energy (EERE)

    Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between the last and latest version of the FAQ Standard.

  15. FAQS Gap Analysis Qualification Card – Civil Structural Engineering

    Office of Energy Efficiency and Renewable Energy (EERE)

    Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between the last and latest version of the FAQ Standard.

  16. FAQS Gap Analysis Qualification Card – Construction Management

    Broader source: Energy.gov [DOE]

    Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between the last and latest version of the FAQ Standard.

  17. FAQS Gap Analysis Qualification Card – Mechanical Systems

    Broader source: Energy.gov [DOE]

    Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between the last and latest version of the FAQ Standard.

  18. FAQS Gap Analysis Qualification Card – Fire Protection Engineering

    Office of Energy Efficiency and Renewable Energy (EERE)

    Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between the last and latest version of the FAQ Standard.

  19. Technical Qualification Program Self-Assessment Report - Los...

    Office of Environmental Management (EM)

    Site Office - 2013 Technical Qualification Program Self-Assessment Report - Los Alamos Site Office - 2013 This self-assessment of the Technical Qualifications and Federal Technical ...

  20. Technical Qualification Program Self-Assessment Report - Los...

    Office of Environmental Management (EM)

    FY15 Technical Qualification Program Self-Assessment Report - Los Alamos Field Office - FY15 The FY15 self-assessment of the Technical Qualifications and Federal Technical ...

  1. FAQS Gap Analysis Qualification Card – General Technical Base

    Broader source: Energy.gov [DOE]

    Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between the last and latest version of the FAQ Standard.

  2. FAQS Qualification Card - Quality Assurance | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Programs is a set of common Functional Area Qualification Standards (FAQS) and ... More Documents & Publications FAQS Gap Analysis Qualification Card - Quality Assurance ...

  3. FAQS Qualification Card - Electrical Systems and Safety Oversight...

    Office of Environmental Management (EM)

    Safety Oversight FAQS Qualification Card - Electrical Systems and Safety Oversight A key element for the Department's Technical Qualification Programs is a set of common Functional ...

  4. Certification and Listing Process and Procedures Workshop | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Certification and Listing Process and Procedures Workshop Certification and Listing Process and Procedures Workshop Slides from the U.S. Department of Energy Hydrogen Component and System Qualification Workshop held November 4, 2010 in Livermore, CA. csqw_mahnken.pdf (246.25 KB) More Documents & Publications Component and System Qualification Workshop Proceedings CSA International Certification Discussion Hydrogen Technology Workshop U.S. Department of Energy Onboard Storage Tank

  5. FAQS Qualification Card – Weapon Quality Assurance

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  6. FAQS Qualification Card – Safeguards and Security

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  7. FAQS Qualification Card – Facility Representative

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  8. FAQS Qualification Card Technical Program Manager

    Broader source: Energy.gov [DOE]

    A key element for the Departments Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  9. FAQS Qualification Card – Radiation Protection

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  10. Chapter 9 - Contracting Qualifications | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    9 - Contracting Qualifications Chapter 9 - Contracting Qualifications 9.4 - Contractor Responsibility Determinations 9.1_Conflict_of_Interest_0.pdf (26.76 KB) 9.2_Performance_Guarantees_0.pdf (16.88 KB) More Documents & Publications AcqGuide9pt2.doc� Chapter 9.2: Performance Guarantees Policy Flash 2016-32

  11. FAQS Qualification Card – Criticality Safety

    Office of Energy Efficiency and Renewable Energy (EERE)

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  12. FAQS Qualification Card- Aviation Safety Officer

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  13. FAQS Qualification Card – Facility Maintenance Management

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  14. FAQS Qualification Card – Environmental Restoration

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  15. FAQS Qualification Card Nuclear Operations Specialist

    Broader source: Energy.gov [DOE]

    A key element for the Departments Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  16. FAQS Qualification Card – Fire Protection Engineering

    Office of Energy Efficiency and Renewable Energy (EERE)

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  17. FAQS Qualification Card – Technical Training

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  18. IHE material qualification tests description and criteria

    SciTech Connect (OSTI)

    Slape, R J

    1984-06-01

    This report describes the qualification tests presently being used at Pantex Plant, Lawrence Livermore National Laboratory, and Los Alamos National Laboratory that are required by the Department of Energy prior to the approval for an explosive as an Insensitive High Explosive (IHE) material. The acceptance criteria of each test for IHE qualification is also discussed. 5 references, 10 figures.

  19. FAQS Qualification Card – General Technical Base

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  20. Technical Qualification Program | National Nuclear Security Administration

    National Nuclear Security Administration (NNSA)

    Technical Qualification Program NNSA's safety office accredited and recognized for leadership in safe operation of defense nuclear facilities Part of NNSA's commitment to maintaining the nation's safe, secure, and effective nuclear deterrent are relentlessly high standards for technically capable nuclear enterprise personnel qualifications for all aspects of Defense Nuclear Facility operations. In December 2015, the Department of Energy

  1. FAQS Qualification Card- Civil Structural Engineering

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  2. FAQS Qualification Card – Environment Compliance

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  3. Methods Data Qualification Interim Report

    SciTech Connect (OSTI)

    R. Sam Alessi; Tami Grimmett; Leng Vang; Dave McGrath

    2010-09-01

    The overall goal of the Next Generation Nuclear Plant (NGNP) Data Management and Analysis System (NDMAS) is to maintain data provenance for all NGNP data including the Methods component of NGNP data. Multiple means are available to access data stored in NDMAS. A web portal environment allows users to access data, view the results of qualification tests and view graphs and charts of various attributes of the data. NDMAS also has methods for the management of the data output from VHTR simulation models and data generated from experiments designed to verify and validate the simulation codes. These simulation models represent the outcome of mathematical representation of VHTR components and systems. The methods data management approaches described herein will handle data that arise from experiment, simulation, and external sources for the main purpose of facilitating parameter estimation and model verification and validation (V&V). A model integration environment entitled ModelCenter is used to automate the storing of data from simulation model runs to the NDMAS repository. This approach does not adversely change the why computational scientists conduct their work. The method is to be used mainly to store the results of model runs that need to be preserved for auditing purposes or for display to the NDMAS web portal. This interim report demonstrates the currently development of NDMAS for Methods data and discusses data and its qualification that is currently part of NDMAS.

  4. CEG Solutions LLC ESCO Qualification Sheet | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    CEG Solutions LLC ESCO Qualification Sheet CEG Solutions LLC ESCO Qualification Sheet Document outlines the energy service company (ESCO) qualifications for CEG Solutions LLC in relation to the U.S. Department of Energy's (DOE) energy savings performance contracts. Download the CEG Solutions qualification sheet. (45.49

  5. Constellation NewEnergy ESCO Qualification Sheet | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Constellation NewEnergy ESCO Qualification Sheet Constellation NewEnergy ESCO Qualification Sheet Document outlines the energy service company (ESCO) qualifications for Constellation NewEnergy, Inc., in relation to the U.S. Department of Energy's energy savings performance contract. Download the Constellation NewEnergy ESCO Qualification Sheet. (130.78

  6. Honeywell International ESCO Qualification Sheet | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Honeywell International ESCO Qualification Sheet Honeywell International ESCO Qualification Sheet Document outlines the energy service company (ESCO) qualifications for Honeywell International in relation to the U.S. Department of Energy's (DOEs) energy savings performance contracts (ESPC). Download the Honeywell International ESCO Qualification Sheet. (152.97 KB)

  7. Technical Qualification Program Administrative Forms | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Administrative Forms Technical Qualification Program Administrative Forms TQP Position Evaluation Questionnaire Form and TQP Resource Management Questionnaire Form TQP Position Evaluation Questionnaire Form (7.19 KB) TQP Resource Management Questionnaire Form (12.85 KB) More Documents & Publications Technical Qualification Program Reaccreditation Report - Sandia Site Office Technical Qualification Program Self-Assessment Report - Oak Ridge Office - 2014 Technical Qualification Program

  8. Johnson Controls ESCO Qualification Sheet | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Johnson Controls ESCO Qualification Sheet Johnson Controls ESCO Qualification Sheet Document outlines the energy service company (ESCO) qualifications for Johnson Controls in relation to the U.S. Department of Energy's (DOEs) energy savings performance contracts (ESPC). Download the Johnson Controls ESCO Qualification Sheet. (136.48 KB)

  9. Pepco Energy Services ESCO Qualification Sheet | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Pepco Energy Services ESCO Qualification Sheet Pepco Energy Services ESCO Qualification Sheet Document outlines the energy service company (ESCO) qualifications for Pepco Energy Services in relation to the U.S. Department of Energy's (DOEs) energy savings performance contracts (ESPC). Download the Pepco Energy Services ESCO Qualification Sheet. (120.19 KB)

  10. DOE handbook: Guide to good practices for the selection, training, and qualification of shift supervisors

    SciTech Connect (OSTI)

    1999-04-01

    This Department of Energy (DOE) handbook is approved for use by all DOE Components and their contractors. The Handbook incorporates editorial changes to DOE-STD-1061-93, ``Guide to Good Practices for the Selection, Training, and Qualification of shift Supervisors,`` and supersedes DOE-STD-1061-93. Technical content of this Handbook has not changed from the original technical standard. Changes are primarily editorial improvements, redesignation of the standard to a Handbook, and format changes to conform with current Technical Standards Program procedures. This guide, used in conjunction with a facility-specific job analysis, provides a framework for the selection, training, qualification, and professional development of reactor facility and non-reactor nuclear facility shift supervisors. Training and qualification programs based on this guide should provide assurance that shift supervisors perform their jobs safely and competently.

  11. FAQS Gap Analysis Qualification Card - Waste Management | Department of

    Office of Environmental Management (EM)

    Energy Technical Training FAQS Gap Analysis Qualification Card - Technical Training Functional Area Qualification Standard Gap Analysis Qualification Cards outline the differences between the last and latest version of the FAQ Standard. Technical Training Gap Analysis Qualification Card (83.77 KB) More Documents & Publications DOE-STD-1179-2004 DOE-HDBK-1078-94 FAQS Reference Guide - Technical Training Energy

    Waste Management FAQS Gap Analysis Qualification Card - Waste Management

  12. Quality Procedure - Approved Suppliers List | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Approved Suppliers List Quality Procedure - Approved Suppliers List This procedure establishes the responsibilities, process, and records for developing and maintaining the Approved Suppliers List (ASL) for EM Headquarters Office of Standards and Quality Assurance in accordance with EM-QA-001, Environmental Management Quality Assurance Program. Quality Procedure - Approved Suppliers List (2.06 MB) More Documents & Publications Quality Procedure - Supplier Qualification Quality Procedure -

  13. Component and System Qualification Workshop Proceedings

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Hydrogen Component and System Qualification Workshop Sandia National Laboratory, Livermore, CA November 4, 2010 Background The Workshop was held at the Combustion Research Center, Sandia National Laboratories, Livermore, CA, on November 4, 2010. The goal of the Workshop was to identify key needs, barriers, and actions to facilitate the qualification and listing of hydrogen and fuel cell systems and components essential for widespread market deployment. To this end, representatives of fuel cell

  14. Advanced Qualification of Additive Manufacturing Materials Workshop

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    July » Advanced Qualification of Additive Manufacturing Materials Workshop Advanced Qualification of Additive Manufacturing Materials Workshop WHEN: Jul 20, 2015 8:30 AM - Jul 21, 2015 7:30 PM WHERE: La Fonda on the Plaza Santa Fe, New Mexico SPEAKER: Multiple speakers CONTACT: Caryll Blount (505) 665-3950 CATEGORY: Science TYPE: Workshop INTERNAL: Calendar Login Event Description Invited speakers from universities and research centers, both US-based and Europe-based, will provide updates on

  15. Qualifications | Y-12 National Security Complex

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Qualifications Qualifications The CNS Veterans Program is for military members just completing their service but still on active duty who want to work in a STEM discipline. To be admitted to the program, participants must: have a high school diploma or equivalent, be departing the service with an "Honorable" discharge, be able to meet admission standards of the chosen institution of higher learning, be responsible for their own financial and logistical support, and provide any and all

  16. Qualification tests for {sup 192}Ir sealed sources

    SciTech Connect (OSTI)

    Iancso, Georgeta Iliescu, Elena Iancu, Rodica

    2013-12-16

    This paper describes the results of qualification tests for {sup 192}Ir sealed sources, available in Testing and Nuclear Expertise Laboratory of National Institute for Physics and Nuclear Engineering 'Horia Hulubei' (I.F.I.N.-HH), Romania. These sources had to be produced in I.F.I.N.-HH and were tested in order to obtain the authorization from The National Commission for Nuclear Activities Control (CNCAN). The sources are used for gammagraphy procedures or in gammadefectoscopy equipments. Tests, measurement methods and equipments used, comply with CNCAN, AIEA and International Quality Standards and regulations. The qualification tests are: 1. Radiological tests and measurements: dose equivalent rate at 1 m; tightness; dose equivalent rate at the surface of the transport and storage container; external unfixed contamination of the container surface. 2. Mechanical and climatic tests: thermal shock; external pressure; mechanic shock; vibrations; boring; thermal conditions for storage and transportation. Passing all tests, it was obtained the Radiological Security Authorization for producing the {sup 192}Ir sealed sources. Now IFIN-HH can meet many demands for this sealed sources, as the only manufacturer in Romania.

  17. Construction, Qualification, and Low Rate Production Start-up...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Construction, Qualification, and Low Rate Production Start-up of a DC Bus Capacitor High ... Construction, Qualification, and Low Rate Production Start-up of a DC Bus Capacitor High ...

  18. Technical Qualification Program Self-Assessment Report - Los...

    Office of Environmental Management (EM)

    Field Office - FY14 Technical Qualification Program Self-Assessment Report - Los Alamos Field Office - FY14 The FY14 self-assessment of the Technical Qualifications Program and ...

  19. FAQS Qualification Card - Occupational Safety | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Qualification Card - Occupational Safety FAQS Qualification Card - Occupational Safety A key element for the Department's Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA). For each functional area,

  20. Technical Qualification Program Accreditation Pros and Cons | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Pros and Cons Technical Qualification Program Accreditation Pros and Cons Business Case for Accreditation Incentives - Challenge the Enterprise to Foster Confidence and Support of TQP Accreditation TQP Accreditation Lessons Learned TQP Accreditation Pros and Cons (75.22 KB) More Documents & Publications Technical Qualification Program Reaccreditation Report - Y-12 Site Office Technical Qualification Program Reaccreditation Report - Sandia Site Office Technical Qualification

  1. Component and System Qualification Workshop Proceedings | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Component and System Qualification Workshop Proceedings Component and System Qualification Workshop Proceedings Proceedings from the U.S. DOE Hydrogen Component and System Qualification Workshop, held at Sandia National Laboratory in Livermore, CA, on November 4, 2010. Component and System Qualification Workshop Proceedings (106.01 KB) More Documents & Publications CSA International Certification Discussion Hydrogen Technology Workshop Certification and Listing Process and

  2. Business Case for Technical Qualification Program Accreditation Incentives

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    | Department of Energy Business Case for Technical Qualification Program Accreditation Incentives Business Case for Technical Qualification Program Accreditation Incentives TQP Accreditation standardize the program throughout the Department by ensuring consistent application of TQP requirements. Business Case for TQP Accreditation Incentives (21.27 KB) More Documents & Publications Technical Qualification Program Self-Assessment Report - Los Alamos Site Office - 2007 Technical

  3. AGC-2 Irradiation Data Qualification Final Report

    SciTech Connect (OSTI)

    Laurence C. Hull

    2012-07-01

    The Graphite Technology Development Program will run a series of six experiments to quantify the effects of irradiation on nuclear grade graphite. The second Advanced Graphite Creep (AGC) experiment (AGC-2) began with Advanced Test Reactor (ATR) Cycle 149A on April 12, 2011, and ended with ATR Cycle 151B on May 5, 2012. The purpose of this report is to qualify AGC-2 irradiation monitoring data following INL Management and Control Procedure 2691, Data Qualification. Data that are Qualified meet the requirements for data collection and use as described in the experiment planning and quality assurance documents. Data that do not meet the requirements are Failed. Some data may not quite meet the requirements, but may still provide some useable information. These data are labeled as Trend. No Trend data were identified for the AGC-2 experiment. All thermocouples functioned throughout the AGC-2 experiment. There was one instance where spurious signals or instrument power interruption resulted in a recorded temperature value being well outside physical reality. This value was identified and labeled as Failed data. All other temperature data are Qualified. All helium and argon gas flow data are within expected ranges. Total gas flow was approximately 50 sccm through the capsule. Helium gas flow was briefly increased to 100 sccm during reactor shutdown. All gas flow data are Qualified. At the start of the experiment, moisture in the outflow gas line increased to 200 ppmv then declined to less than 10 ppmv over a period of 5 days. This increase in moisture coincides with the initial heating of the experiment and drying of the system. Moisture slightly exceeded 10 ppmv three other times during the experiment. While these moisture values exceed the 10 ppmv threshold value, the reported measurements are considered accurate and to reflect moisture conditions in the capsule. All moisture data are Qualified. Graphite creep specimens are subjected to one of three loads, 393 lbf

  4. Quality Assurance Functional Area Qualification Standard

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2013-12-02

    The Quality Assurance (QA) Functional Area Qualification Standard (FAQS) establishes common functional area competency requirements for all DOE QA personnel who provide assistance, direction, guidance, oversight, or evaluation of contractor technical activities that could impact the safe operation of DOE’s defense nuclear facilities.

  5. Quality Assurance Functional Area Qualification Standard

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2002-04-22

    Replaced by DOE-1150-2013 This QA Functional Area Qualification Standard establishes common functional area competency requirements for DOE personnel who provide assistance, direction, guidance, oversight, or evaluation of contractor technical QA activities impacting the safe operation of defense nuclear facilities.

  6. Functional Area Qualification Standard Job Task Analyses

    Broader source: Energy.gov [DOE]

    FAQS Job Task Analyses are performed on the Function Area Qualification Standards. The FAQS Job Task Analyses consists of: Developing a comprehensive list of tasks that define the job such as the duties and responsibilities which include determining their levels of importance and frequency. Identifying and evaluating competencies. Last step is evaluating linkage between job tasks and competencies.

  7. AGR-2 Data Qualification Interim Report

    SciTech Connect (OSTI)

    Michael L. Abbott

    2010-09-01

    Projects for the very high temperature reactor (VHTR) Technology Development Office program provide data in support of Nuclear Regulatory Commission licensing of the VHTR. Fuel and materials to be used in the reactor are tested and characterized to quantify performance in high temperature and high fluence environments. The VHTR program established the NGNP Data Management and Analysis System (NDMAS) to manage and document VHTR data qualification, for storage of the data in a readily accessible electronic form, and to assist in the analysis and presentation of the data. This document gives the status of NDMAS processing and qualification of data associated with the initial reactor cycle (147A) of the second Advanced Gas Reactor (AGR-2) experiment which began on June 21, 2010. Because it is early in the AGR-2 experiment, data from only two AGR-2 data streams are reported on: Fuel Fabrication and Fuel Irradiation data. As of August 1, 2010, approximately 311,000 irradiation data records have been stored in NDMAS, and qualification tests are in progress. Preliminary information indicates that TC 2 in Capsule 2 failed prior to start of the experiment, and NDMAS testing has thus far identified only two invalid data values from the METSO data collection system Data from the Fission Product Monitoring System (FPMS) are not currently processed until after reactor cycle shutdown and have not yet been received. A description of the ATR operating conditions data associated with the AGR-2 experiment (e.g., power levels) are summarized in the AGR-1 data qualification report (INL/EXT-09-16460). Since ATR data are collected under ATR program data quality requirements (i.e., outside the VHTR program), the NGNP program and NDMAS do not take additional actions to qualify these data other than NDMAS capture testing. Data qualification of graphite characterization data collected under the Graphite Technology Development Project is reported in a separate status report (Hull 2010).

  8. SU-E-T-615: Investigation of the Dosimetric Impact of Tandem Loading in the Treatment of Cervical Cancer for HDR Brachytherapy Procedures

    SciTech Connect (OSTI)

    Esquivel, C; Patton, L; Nelson, K; Lin, B

    2014-06-01

    Purpose: To quantify the dosimetric impact of the tandem loading in the treatment of cervical cancer for HDR brachytherapy procedures. Methods: Ten patients were evaluated, each of whom received 5 fractions of treatment. Tandem and ovoid sets were inserted into the uterine cavity based on institutional protocols and procedures. Following insertion and stabilization, CT image sets of 1.5mm slice thickness were acquired and sent to the Oncentra V4.3 Treatment Planning System. Critical structures such as the CTV, bladder, rectum, sigmoid, and bowel were contoured and a fractional dose of 5.5Gy was prescribed to Point A for each patient. Six different treatment plans were created for each fraction using varying tandem weightings; from 0.5 to 1.4 times that of the ovoids. Surface dose evaluation of various ovoid diameters, 2.0-3.5cm, at the vaginal fornices was also investigated. Results: Critical structures were evaluated based on varying dose and volume constraints, in particular the 2.0 cc volume recommendation cited by the gynecological GEC-ESTRO working group. Based on dose volume histogram evaluation, a reduction of dose to the critical structures was most often discovered when the tandem weighting was increased. CTV coverage showed little change as the tandem weighting was varied. Ovoid surface dose decreased by 50-65% as the tandem weighting increased. Conclusion: The advantage of 3D planning with HDR brachytherapy is the dose optimization for each individual treatment plan. This investigation shows that by utilizing large tandem weightings, 1.4 times greater than the ovoid, one can still achieve adequate coverage of the CTV and relatively low doses to the critical structures. In some cases, one would still have to optimize further per individual case. In addition, the ovoid surface dose was greatly decreased when large tandem weighting was utilized; especially for small ovoid diameters.

  9. RERTR Fuel Developmemt and Qualification Plan

    SciTech Connect (OSTI)

    Dan Wachs

    2007-01-01

    In late 2003 it became evident that U-Mo aluminum fuels under development exhibited significant fuel performance problems under the irradiation conditions required for conversion of most high-powered research reactors. Solutions to the fuel performance issue have been proposed and show promise in early testing. Based on these results, a Reduced Enrichment Research and Test Reactor (RERTR) program strategy has been mapped to allow generic fuel qualification to occur prior to the end of FY10 and reactor conversion to occur prior to the end of FY14. This strategy utilizes a diversity of technologies, test conditions, and test types. Scoping studies using miniature fuel plates will be completed in the time frame of 2006-2008. Irradiation of larger specimens will occur in the Advanced Test Reactor (ATR) in the United States, the Belgian Reactor-2 (BR2) reactor in Belgium, and in the OSIRIS reactor in France in 2006-2009. These scoping irradiation tests provide a large amount of data on the performance of advanced fuel types under irradiation and allow the down selection of technology for larger scale testing during the final stages of fuel qualification. In conjunction with irradiation testing, fabrication processes must be developed and made available to commercial fabricators. The commercial fabrication infrastructure must also be upgraded to ensure a reliable low enriched uranium (LEU) fuel supply. Final qualification of fuels will occur in two phases. Phase I will obtain generic approval for use of dispersion fuels with density less than 8.5 g-U/cm3. In order to obtain this approval, a larger scale demonstration of fuel performance and fabrication technology will be necessary. Several Materials Test Reactor (MTR) plate-type fuel assemblies will be irradiated in both the High Flux Reactor (HFR) and the ATR (other options include the BR2 and Russian Research Reactor, Dmitrovgrad, Russia [MIR] reactors) in 2008-2009. Following postirradiation examination, a report

  10. Advanced Qualification of Additive Manufacturing Workshop

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Additive Manufacturing Workshop Poster Abstract Submission - deadline July 10, 2015 Advanced Qualification of Additive Manufacturing Materials using in situ sensors, diagnostics and modeling Contact Institute Director Dr. Alexander V. Balatsky Institute for Materials Science (505) 665-0077 Email Deputy Director Dr. Jennifer S. Martinez Institute for Materials Science (505) 665-0045 Email Deputy Director Dr. Nathan A. Mara Institute for Materials Science (505) 667 8665 Email Institute

  11. Radiation Protection Functional Area Qualification Standard

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    MEASUREMENT SENSITIVE DOE-STD-1174-2013 November 2013 DOE STANDARD RADIATION PROTECTION FUNCTIONAL AREA QUALIFICATION STANDARD DOE Defense Nuclear Facilities Technical Personnel U.S. Department of Energy AREA TRNG Washington, D.C. 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. DOE-STD-1174-2013 This document is available on the Department of Energy Technical Standards Program Website at http://www.hss.energy.gov/nuclearsafety/techstds/ ii ii

  12. Advanced Qualification of Additive Manufacturing Workshop

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Additive Manufacturing Workshop Advanced Qualification of Additive Manufacturing Materials (AM) Workshop Our goal is to define opportunities and research gaps within additive manufacturing (AM) and to engage the broader scientific/engineering community to discuss future research directions. thumbnail of thumbnail of Contact Institute Director Dr. Alexander V. Balatsky Institute for Materials Science (505) 665-0077 Email Deputy Director Dr. Jennifer S. Martinez Institute for Materials Science

  13. High Temperature Materials Interim Data Qualification Report

    SciTech Connect (OSTI)

    Nancy Lybeck

    2010-08-01

    ABSTRACT Projects for the very high temperature reactor (VHTR) Technology Development Office provide data in support of Nuclear Regulatory Commission licensing of the VHTR. Fuel and materials to be used in the reactor are tested and characterized to quantify performance in high temperature and high fluence environments. The VHTR program has established the NGNP Data Management and Analysis System (NDMAS) to ensure that VHTR data are qualified for use, stored in a readily accessible electronic form, and analyzed to extract useful results. This document focuses on the first NDMAS objective. It describes the High Temperature Materials characterization data stream, the processing of these data within NDMAS, and reports the interim FY2010 qualification status of the data. Data qualification activities within NDMAS for specific types of data are determined by the data qualification category assigned by the data generator. The High Temperature Materials data are being collected under NQA-1 guidelines, and will be qualified data. For NQA-1 qualified data, the qualification activities include: (1) capture testing, to confirm that the data stored within NDMAS are identical to the raw data supplied, (2) accuracy testing to confirm that the data are an accurate representation of the system or object being measured, and (3) documenting that the data were collected under an NQA-1 or equivalent Quality Assurance program. Currently, data from two test series within the High Temperature Materials data stream have been entered into the NDMAS vault: 1. Tensile Tests for Sm (i.e., Allowable Stress) Confirmatory Testing 1,403,994 records have been inserted into the NDMAS database. Capture testing is in process. 2. Creep-Fatigue Testing to Support Determination of Creep-Fatigue Interaction Diagram 918,854 records have been processed and inserted into the NDMAS database. Capture testing is in process.

  14. Industrial Hygiene Functional Area Qualification Standard

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    38-2007 November 2007 DOE STANDARD INDUSTRIAL HYGIENE FUNCTIONAL AREA QUALIFICATION STANDARD DOE Defense Nuclear Facilities Technical Personnel U.S. Department of Energy AREA TRNG Washington, D.C. 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. DOE-STD-1138-2007 ii This document is available on the Department of Energy Technical Standards Program Web Site at http://www.hss.energy.gov/nuclearsafety/techstds/ DOE-STD-1138-2007 iv INTENTIONALLY BLANK

  15. Instrumentation and Control Functional Area Qualification Standard

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    NOT MEASUREMENT SENSITIVE DOE-STD-1162-2013 June 2013 DOE STANDARD INSTRUMENTATION AND CONTROL FUNCTIONAL AREA QUALIFICATION STANDARD DOE Defense Nuclear Facilities Technical Personnel U.S. Department of Energy AREA TRNG Washington, D.C. 20585 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. DOE-STD-1162-2013 This document is available on the Department of Energy Technical Standards Program website at http://www.hss.energy.gov/nuclearsafety/ns/techstds/ ii

  16. Nuclear Safety Specialist Functional Area Qualification Standard

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    83-2007 November 2007 DOE STANDARD NUCLEAR SAFETY SPECIALIST FUNCTIONAL AREA QUALIFICATION STANDARD DOE Defense Nuclear Facilities Technical Personnel U.S. Department of Energy AREA TRNG Washington, D.C. 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. DOE-STD-1183-2007 ii This document is available on the Department of Energy Technical Standards Program Web Site at http://www.hss.energy.gov/nuclearsafety/techstds/ DOE-STD-1183-2007 iv INTENTIONALLY BLANK

  17. Occupational Safety Functional Area Qualification Standard

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    11 July 2011 DOE STANDARD OCCUPATIONAL SAFETY FUNCTIONAL AREA QUALIFICATION STANDARD DOE Defense Nuclear Facilities Technical Personnel U.S. Department of Energy AREA TRNG Washington, D.C. 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. NOT MEASUREMENT SENSITIVE DOE-STD-1160-2011 ii This document is available on the Department of Energy Technical Standards Program website at http://www.hss.energy.gov/nuclearsafety/ns/techstds/ DOE-STD-1160-2011 iv

  18. Quality Assurance Functional Area Qualification Standard

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    NOT MEASUREMENT SENSITIVE DOE-STD-1150-2013 December 2013 DOE STANDARD QUALITY ASSURANCE FUNCTIONAL AREA QUALIFICATION STANDARD DOE Defense Nuclear Facilities Technical Personnel U.S. Department of Energy AREA TRNG Washington, D.C. 20585 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. DOE-STD-1150-2013 This document is available on the Department of Energy Technical Standards Program Website at http://www.hss.energy.gov/nuclearsafety/ns/techstds/ ii

  19. Request for Qualifications for Sacramento Landfill

    Broader source: Energy.gov [DOE]

    This Request for Qualifications (RFQ) solicits experienced companies to design, permit, finance, build, and operate a solar photovoltaic farm (SPV Farm) on the City of Sacramento’s 28th Street Landfill. Respondents to this RFQ must demonstrate experience and capacity to design, permit, finance, build, and operate a SPV Farm that generates electricity that can be sold for electrical use through a power-purchase agreement. Submittals must be prepared and delivered in accordance with the requirements set forth in this document.

  20. Technical Qualification Program Self-Assessment Report - Los Alamos Field

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Office - 2014 | Department of Energy Los Alamos Field Office - 2014 Technical Qualification Program Self-Assessment Report - Los Alamos Field Office - 2014 This self-assessment for the Verification of the Closure of Federal Training & Qualification Deficiencies was conducted to provide Los Alamos Field Office (NA-LA) management specific information related to effectiveness of the closure actions for Federal Training and Qualification (T &Q) deficiencies identified by a recent

  1. Microsoft Word - Attachment D - Position Qualifications.docx

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    D - POSITION QUALIFICATIONS POSITION QUALIFICATIONS NOTE: If accepted, the labor category and minimum position qualifications proposed will be incorporated into (and/or replace) the below listing. Historical Allocation (FTE) DESCRIPTION Program Manager 1 Requirements for the Program Manager include a Bachelors or higher degree in a social science, business, or related field; at least 10 years of supervisory and management experience of which 5 years must be in the operation, administration,

  2. Preliminary Assessment of the Hanford Tank Waste Feed Acceptance and Product Qualification Programs

    SciTech Connect (OSTI)

    Herman, C. C.; Adamson, Duane J.; Herman, D. T.; Peeler, David K.; Poirier, Micheal R.; Reboul, S. H.; Stone, M. E.; Peterson, Reid A.; Chun, Jaehun; Fort, James A.; Vienna, John D.; Wells, Beric E.

    2013-04-01

    The U.S. Department of Energy Office of Environmental Management (EM) is engaging the national laboratories to provide the scientific and technological rigor to support EM program and project planning, technology development and deployment, project execution, and assessment of program outcomes. As an early demonstration of this new responsibility, Savannah River National Laboratory (SRNL) and Pacific Northwest National Laboratory (PNNL) have been chartered to implement a science and technology program addressing Hanford Tank waste feed acceptance and product qualification. As a first step, the laboratories examined the technical risks and uncertainties associated with the planned waste feed acceptance and qualification testing for Hanford tank wastes. Science and technology gaps were identified for work associated with 1) feed criteria development with emphasis on identifying the feed properties and the process requirements, 2) the Tank Waste Treatment and Immobilization Plant (WTP) process qualification program, and 3) the WTP HLW glass product qualification program. Opportunities for streamlining the accetpance and qualification programs were also considered in the gap assessment. Technical approaches to address the science and technology gaps and/or implement the opportunities were identified. These approaches will be further refined and developed as strong integrated teams of researchers from national laboratories, contractors, industry, and academia are brought together to provide the best science and technology solutions. Pursuing the identified approaches will have immediate and long-term benefits to DOE in reducing risks and uncertainties associated with tank waste removal and preparation, transfers from the tank farm to the WTP, processing within the WTP Pretreatment Facility, and in producing qualified HLW glass products. Additionally, implementation of the identified opportunities provides the potential for long-term cost savings given the anticipated

  3. BLM Manual 2803: Qualifications for Holding FLPMA Grants | Open...

    Open Energy Info (EERE)

    search OpenEI Reference LibraryAdd to library PermittingRegulatory Guidance - GuideHandbook: BLM Manual 2803: Qualifications for Holding FLPMA GrantsPermitting...

  4. CRAD, NNSA - Federal Employee Training and Qualification Program...

    Office of Environmental Management (EM)

    & Publications CRAD, NNSA - Facility Representatives (FR) Technical Qualification Program Self-Assessment Report - NNSA Production Office - 2014 CRAD, NNSA - Contractor Training...

  5. New Geothermal Site Identification and Qualification | Open Energy...

    Open Energy Info (EERE)

    Citation Geothermex Inc.. 2004. New Geothermal Site Identification and Qualification. Richmond, CA: California Energy Commission. Report No.: P500-04-051. Contract No.: 500-04-051....

  6. Technical Qualification Program Self-Assessment Report - NNSA...

    Office of Environmental Management (EM)

    NNSA Production Office - 2014 Technical Qualification Program Self-Assessment Report - NNSA Production Office - 2014 In preparation for the upcoming Chief for Defense Nuclear ...

  7. Technical Qualification Program Self-Assessment Report - Los...

    Office of Environmental Management (EM)

    2014 Technical Qualification Program Self-Assessment Report - Los Alamos Field Office - 2014 This self-assessment for the Verification of the Closure of Federal Training & ...

  8. Technical Qualification Program Self-Assessment Report - Richland...

    Office of Environmental Management (EM)

    Richland Operations Office - 2014 Technical Qualification Program Self-Assessment Report - Richland Operations Office - 2014 The Richland Operations Office (RL) Technical ...

  9. Technical Qualification Program Self-Assessment Report - Los...

    Office of Environmental Management (EM)

    07 Technical Qualification Program Self-Assessment Report - Los Alamos Site Office - 2007 The Federal Technical Capability Manual requires periodic self-assessment of the ...

  10. Technical Qualification Program Self-Assessment Report - Nevada...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Nevada Field Office - 2014 Technical Qualification Program Self-Assessment Report - Nevada Field Office - 2014 This self-assessment examined how the Nevada Field Office (NFO) ...

  11. Defense Program Equivalencies for Technical Qualification Standard Competencies12/12/1995

    Broader source: Energy.gov [DOE]

    Defense Programs has undertaken an effort to compare the competencies in the GeneralTechnical Base Qualification Standard and the Functional Area Qualification Standards withvarious positions in...

  12. Emergency Procedures

    Broader source: Energy.gov [DOE]

    Note: This page is pending deletion, please refer to the Safety and health main page for emergency procedure information:

  13. Large Bore Powder Gun Qualification (U)

    SciTech Connect (OSTI)

    Rabern, Donald A.; Valdiviez, Robert

    2012-04-02

    A Large Bore Powder Gun (LBPG) is being designed to enable experimentalists to characterize material behavior outside the capabilities of the NNSS JASPER and LANL TA-55 PF-4 guns. The combination of these three guns will create a capability to conduct impact experiments over a wide range of pressures and shock profiles. The Large Bore Powder Gun will be fielded at the Nevada National Security Site (NNSS) U1a Complex. The Complex is nearly 1000 ft below ground with dedicated drifts for testing, instrumentation, and post-shot entombment. To ensure the reliability, safety, and performance of the LBPG, a qualification plan has been established and documented here. Requirements for the LBPG have been established and documented in WE-14-TR-0065 U A, Large Bore Powder Gun Customer Requirements. The document includes the requirements for the physics experiments, the gun and confinement systems, and operations at NNSS. A detailed description of the requirements is established in that document and is referred to and quoted throughout this document. Two Gun and Confinement Systems will be fielded. The Prototype Gun will be used primarily to characterize the gun and confinement performance and be the primary platform for qualification actions. This gun will also be used to investigate and qualify target and diagnostic modifications through the life of the program (U1a.104 Drift). An identical gun, the Physics Gun, will be fielded for confirmatory and Pu experiments (U1a.102D Drift). Both guns will be qualified for operation. The Gun and Confinement System design will be qualified through analysis, inspection, and testing using the Prototype Gun for the majority of process. The Physics Gun will be qualified through inspection and a limited number of qualification tests to ensure performance and behavior equivalent to the Prototype gun. Figure 1.1 shows the partial configuration of U1a and the locations of the Prototype and Physics Gun/Confinement Systems.

  14. Criticality Safety Functional Area Qualification Standard

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    DOE-STD-1173-2009 April 2009 DOE STANDARD CRITICALITY SAFETY FUNCTIONAL AREA QUALIFICATION STANDARD DOE Nuclear Facilities Technical Personnel U.S. Department of Energy AREA TRNG Washington, D.C. 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. DOE-STD-1173-2009 ii This document is available on the Department of Energy Technical Standards Program Web Page at http://www.hss.energy.gov/nuclearsafety/techstds/ DOE-STD-1173-2009 iii APPROVAL The Federal

  15. FAQS Qualification Card – Safeguards and Security General Technical Base

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  16. FAQS Qualification Card – Nuclear Explosive Safety Study

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  17. FAQS Qualification Card – Safety Software Quality Assurance

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  18. FAQS Qualification Card – Senior Technical Safety Manager

    Broader source: Energy.gov [DOE]

    A key element for the Department’s Technical Qualification Programs is a set of common Functional Area Qualification Standards (FAQS) and associated Job Task Analyses (JTA). These standards are developed for various functional areas of responsibility in the Department, including oversight of safety management programs identified as hazard controls in Documented Safety Analyses (DSA).

  19. Qualification Plus: Performance and Durability Tests Beyond IEC 61215 (Presentation)

    SciTech Connect (OSTI)

    Kurtz, S.; Jordan, J.; Kempe, M.; Miller, D.; Bosco, N.; Silverman, T.; Hacke, P.; Phillips, N.; Earnest, T.; Romero, R.

    2014-03-01

    Qualification Plus is an accelerated test protocol and quality management system that gives higher confidence in field performance of PV modules compared with conventional qualification testing. The test sequences are being developed as consensus standards, but the early publication of these tests enables the community to begin benefiting from them sooner.

  20. Technical Qualification Program Self-Assessment Report - Richland

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Operations Office - 2014 | Department of Energy Richland Operations Office - 2014 Technical Qualification Program Self-Assessment Report - Richland Operations Office - 2014 The Richland Operations Office (RL) Technical Qualification Program Plan establishes a process to objectively determine that individuals performing activities related to the technical support, management, oversight, or operation possess the necessary knowledge, skills, and abilities to perform their assigned duties and

  1. Essential elements of an effective data qualification

    SciTech Connect (OSTI)

    Jenkins, E.W.

    1994-07-01

    Before data is used in any statistical evaluation, it should be subjected to a thorough data qualification to ensure its integrity. Data Qualification efforts may vary in scope but should all contain certain basic elements. Outliers should be eliminated so that any estimates obtained from the data will not be overly biased. Plots may be generated to uncover potential outliers, and these observations can be confirmed as being anomalous through the use of statistical testing. Non-stationarity of the data (i.e., time trends) may also be initially identified through the use of plots and confirmed by the results of statistical analyses, e.g., the use of the Kendall`s tau statistic. When the dataset has been qualified, replicates and duplicates should be averaged to create a pseudo-independence between data points. An algorithm based on the groundwater data from the Savannah River Site has been used by the Applied Statistics Group at Westinghouse Savannah River Company for this.

  2. Product consistency test and toxicity characteristic leaching procedure results of the ceramic waste form from the electrometallurgical treatment process for spent fuel

    SciTech Connect (OSTI)

    Johnson, S. G.; Adamic, M. L.: DiSanto, T.; Warren, A. R.; Cummings, D. G.; Foulkrod, L.; Goff, K. M.

    1999-11-11

    The ceramic waste form produced from the electrometallurgical treatment of sodium bonded spent fuel from the Experimental Breeder Reactor-II was tested using two immersion tests with separate and distinct purposes. The product consistency test is used to assess the consistency of the waste forms produced and thus is an indicator of a well-controlled process. The toxicity characteristic leaching procedure is used to determine whether a substance is to be considered hazardous by the Environmental Protection Agency. The proposed high level waste repository will not be licensed to receive hazardous waste, thus any waste forms destined to be placed there cannot be of a hazardous nature as defined by the Resource Conservation and Recovery Act. Results are presented from the first four fully radioactive ceramic waste forms produced and from seven ceramic waste forms produced from cold surrogate materials. The fully radioactive waste forms are approximately 2 kg in weight and were produced wit h salt used to treat 100 driver subassemblies of spent fuel.

  3. Equipment qualification issues research and resolution: Status report

    SciTech Connect (OSTI)

    Bonzon, L.L.; Wyant, F.J.; Bustard, L.D.; Gillen, K.T.

    1986-11-01

    Since its inception in 1975, the Qualification Testing Evaluation (QTE) Program has produced numerous results pertinent to equipment qualification issues. Many have been incorporated into Regulatory Guides, Rules, and industry practices and standards. This report summarizes the numerous reports and findings to date. Thirty separate issues are discussed encompassing three generic areas: accident simulation methods, aging simulation methods, and special topics related to equipment qualification. Each issue-specific section contains (1) a brief description of the issue, (2) a summary of the applicable research effort, and (3) a summary of the findings to date.

  4. Data Qualification Report: Calculated Porosity and Porosity-Derived Values for Lithostratigraphic Units for use on the Yucca Mountain Project

    SciTech Connect (OSTI)

    P. Sanchez

    2001-05-30

    The qualification is being completed in accordance with the Data Qualification Plan DQP-NBS-GS-000006, Rev. 00 (CRWMS M&O 2001). The purpose of this data qualification activity is to evaluate for qualification the unqualified developed input and porosity output included in Data Tracking Number (DTN) M09910POROCALC.000. The main output of the analyses documented in DTN M09910POROCALC.000 is the calculated total porosity and effective porosity for 40 Yucca Mountain Project boreholes. The porosity data are used as input to Analysis Model Report (AMR) 10040, ''Rock Properties Model'' (MDL-NBS-GS-000004, Rev. 00), Interim Change Notice [ICN] 02 (CRWMS M&O 2000b). The output from the rock properties model is used as input to numerical physical-process modeling within the context of a relationship developed in the AMR between hydraulic conductivity, bound water and zeolitic zones for use in the unsaturated zone model. In accordance with procedure AP-3.15Q, the porosity output is not used in the direct calculation of Principal Factors for post-closure safety or disruptive events. The original source for DTN M09910POROCALC.000 is a Civilian Radioactive Waste Management System (CRWMS) Management and Operating Contractor (M&O) report, ''Combined Porosity from Geophysical Logs'' (CRWMS M&O 1999a and hereafter referred to as Rael 1999). That report recalculated porosity results for both the historical boreholes covered in Nelson (1996), and the modern boreholes reported in CRWMS M&O (1996a,b). The porosity computations in Rael (1999) are based on density-porosity mathematical relationships requiring various input parameters, including bulk density, matrix density and air and/or fluid density and volumetric water content. The main output is computed total porosity and effective porosity reported on a foot-by-foot basis for each borehole, although volumetric water content is derived from neutron data as an interim output. This qualification report uses technical assessment and

  5. CRAD, NNSA- Contractor Training and Qualification (T&Q)

    Office of Energy Efficiency and Renewable Energy (EERE)

    CRAD for Contractor Training and Qualification (T&Q). Criteria Review and Approach Documents (CRADs) that can be used to conduct a well-organized and thorough assessment of elements of safety and health programs.

  6. Technical Qualification Program Self-Assessment Report - Los...

    Office of Environmental Management (EM)

    11 Technical Qualification Program Self-Assessment Report - Los Alamos Site Office - 2011 The purpose of the FTCP TQP self-assessment team evaluation was to conduct a thorough ...

  7. Waste Form Qualification Compliance Strategy for Bulk Vitrification

    SciTech Connect (OSTI)

    Bagaasen, Larry M.; Westsik, Joseph H.; Brouns, Thomas M.

    2005-01-03

    The Bulk Vitrification System is being pursued to assist in immobilizing the low-activity tank waste from the 53 million gallons of radioactive waste in the 177 underground storage tanks on the Hanford Site. To demonstrate the effectiveness of the bulk vitrification process, a research and development facility known as the Demonstration Bulk Vitrification System (DBVS) is being built to demonstrate the technology. Specific performance requirements for the final packaged bulk vitrification waste form have been identified. In addition to the specific product-performance requirements, performance targets/goals have been identified that are necessary to qualify the waste form but do not lend themselves to specifications that are easily verified through short-term testing. Collectively, these form the product requirements for the DBVS. This waste-form qualification (WFQ) strategy document outlines the general strategies for achieving and demonstrating compliance with the BVS product requirements. The specific objectives of the WFQ activities are discussed, the bulk vitrification process and product control strategy is outlined, and the test strategy to meet the WFQ objectives is described. The DBVS product performance targets/goals and strategies to address those targets/goals are described. The DBVS product-performance requirements are compared to the Waste Treatment and Immobilization Plant immobilized low-activity waste product specifications. The strategies for demonstrating compliance with the bulk vitrification product requirements are presented.

  8. 40 MM Grenade Launcher Qualification Requirements at Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Sites, IG-0806 | Department of Energy 40 MM Grenade Launcher Qualification Requirements at Department of Energy Sites, IG-0806 40 MM Grenade Launcher Qualification Requirements at Department of Energy Sites, IG-0806 The Department of Energy and its National Nuclear Security Administration (NNSA), operate some of the most sensitive Federal facilities in the United States. Because of the mission requirements, safeguards and security is a top priority at these sites. As part of its security

  9. Technical Qualification Program Self-Assessment Report - Los Alamos Field

    Office of Environmental Management (EM)

    Office - FY14 | Department of Energy Field Office - FY14 Technical Qualification Program Self-Assessment Report - Los Alamos Field Office - FY14 The FY14 self-assessment of the Technical Qualifications Program and Federal Technical Capabilities Program was conducted to provide Los Alamos Field Office (NA-LA) management specific information related to effectiveness of the documentation and implementation of these programs. The conclusion of this assessment is that the areas assessed herein

  10. Technical Qualification Program Self-Assessment Report - Los Alamos Site

    Office of Environmental Management (EM)

    Office - 2013 | Department of Energy Site Office - 2013 Technical Qualification Program Self-Assessment Report - Los Alamos Site Office - 2013 This self-assessment of the Technical Qualifications and Federal Technical Capability program was conducted to provide Los Alamos Field Office management specific information related to effectiveness of the documentation and implementation of these programs. The conclusion of this assessment is that the areas assessed herein are compliant with the

  11. An overview of component qualification using Bayesian statistics and energy

    Office of Scientific and Technical Information (OSTI)

    methods. (Technical Report) | SciTech Connect An overview of component qualification using Bayesian statistics and energy methods. Citation Details In-Document Search Title: An overview of component qualification using Bayesian statistics and energy methods. The below overview is designed to give the reader a limited understanding of Bayesian and Maximum Likelihood (MLE) estimation; a basic understanding of some of the mathematical tools to evaluate the quality of an estimation; an

  12. Model Energy Service Company Pre-Qualification Contract | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Energy Service Company Pre-Qualification Contract Model Energy Service Company Pre-Qualification Contract This page provides model documents for developing a contract between an Energy Service Company (ESCO) and a state energy office (or other entity managing a performance contracting program). This model contract establishes requirements for each pre-qualified ESCO to provide performance contracting services for the program. Requirements include data collection and reporting,

  13. Technical Qualification Program Self-Assessment Report - Office of Science

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    - 2013 | Department of Energy Office of Science - 2013 Technical Qualification Program Self-Assessment Report - Office of Science - 2013 Under DOE 426.1, Change 1. Headquarters and Field elements must conduct a self-assessment of Technical Qualification Program (TQP) and Federal Technical Capability Program (FTCP) implementation within their organization at least every four years. These assessments must be conducted in accordance with the requirements of DOE Order (0) 226.1 B, Implementation

  14. Technical Qualification Program and FTCP Assessment CRADs | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy and FTCP Assessment CRADs Technical Qualification Program and FTCP Assessment CRADs This document provides guidance and objectives and criteria to support assessments required by DOE O 426.1 Federal Technical Capability (FTC), Section 4. REQUIREMENTS, paragraph b. FTC Program Implementation, subparagraph (7) Self-Assessment. FTCP and TQP Assessment CRADs, 2012 (60.96 KB) More Documents & Publications Technical Qualification Program Self-Assessment Report - Richland Operations

  15. Technical Qualification Program Self-Assessment Report - Los Alamos Site

    Office of Environmental Management (EM)

    Office - 2007 | Department of Energy 07 Technical Qualification Program Self-Assessment Report - Los Alamos Site Office - 2007 The Federal Technical Capability Manual requires periodic self-assessment of the effectiveness of the implementation of the Manual and the Technical Qualification Program utilizing a defined set of Objectives and Criteria. The assessment documented by this report is the first periodic review conducted at LASO to meet this requirement. The assessment results are

  16. Secondary Waste Cast Stone Waste Form Qualification Testing Plan

    SciTech Connect (OSTI)

    Westsik, Joseph H.; Serne, R. Jeffrey

    2012-09-26

    The Hanford Tank Waste Treatment and Immobilization Plant (WTP) is being constructed to treat the 56 million gallons of radioactive waste stored in 177 underground tanks at the Hanford Site. The WTP includes a pretreatment facility to separate the wastes into high-level waste (HLW) and low-activity waste (LAW) fractions for vitrification and disposal. The LAW will be converted to glass for final disposal at the Integrated Disposal Facility (IDF). Cast Stone – a cementitious waste form, has been selected for solidification of this secondary waste stream after treatment in the ETF. The secondary-waste Cast Stone waste form must be acceptable for disposal in the IDF. This secondary waste Cast Stone waste form qualification testing plan outlines the testing of the waste form and immobilization process to demonstrate that the Cast Stone waste form can comply with the disposal requirements. Specifications for the secondary-waste Cast Stone waste form have not been established. For this testing plan, Cast Stone specifications are derived from specifications for the immobilized LAW glass in the WTP contract, the waste acceptance criteria for the IDF, and the waste acceptance criteria in the IDF Permit issued by the State of Washington. This testing plan outlines the testing needed to demonstrate that the waste form can comply with these waste form specifications and acceptance criteria. The testing program must also demonstrate that the immobilization process can be controlled to consistently provide an acceptable waste form product. This testing plan also outlines the testing needed to provide the technical basis for understanding the long-term performance of the waste form in the disposal environment. These waste form performance data are needed to support performance assessment analyses of the long-term environmental impact of the secondary-waste Cast Stone waste form in the IDF

  17. Standard for the qualification of high capacity fossil fuel fired plant operators

    SciTech Connect (OSTI)

    Axtman, W.

    1996-12-31

    The American Society of Mechanical Engineers, at the request of the U.S. Environmental Protection Agency (EPA) and, in recognition of the needs and benefits associated with standard qualifications of operators of high capacity fossil fuel fired plants, established the Qualifications of High Capacity Fossil Fuel Fired Operator (QFO) Committee in 1994. The purpose of the QFO Committee is to develop and maintain such a standard for operators. This standard includes qualifications, duties, responsibilities and the certification requirements for operators as appropriate to The Clean Air Act as amended in 1990 for fossil fuel fired plants with inputs equal to or greater than 10,000 Btu/hr. This Standard does not cover the certification or validation of fossil plant operating procedures, operating practices, facility performance, nor compliance with any particular permit requirement. This standard recognizes the titles or positions to which any particular fossil plant operator may apply, will vary within a facility. Therefore, this standard does not attempt to identify the individual who is required to obtain certification in any class designation. The fossil plant owner is urged to contact the local jurisdiction in which the fossil plant is located in this regard. This standard does not in itself require certification but rather it serves as a means for complying with federal, state, and local regulations which require operators of fossil fuel fired boilers with inputs equal to or greater than 10,000,000 But/hr to be certified. Safety codes and standards are intended to enhance public health and safety. Revisions to this Standard result from committee considerations of factors such as technological advances, new data, and changing environmental and industry needs. Revisions do not imply that previous editions of this standard were inadequate.

  18. Workshop on environmental qualification of electric equipment

    SciTech Connect (OSTI)

    Lofaro, R.; Gunther, W.; Villaran, M.; Lee, B.S.; Taylor, J.

    1994-05-01

    Questions concerning the Environmental Qualification (EQ) of electrical equipment used in commercial nuclear power plants have recently become the subject of significant interest to the US Nuclear Regulatory Commission (NRC). Initial questions centered on whether compliance with the EQ requirements for older plants were adequate to support plant operation beyond 40 years. After subsequent investigation, the NRC Staff concluded that questions related to the differences in EQ requirements between older and newer plants constitute a potential generic issue which should be evaluated for backfit, independent of license renewal activities. EQ testing of electric cables was performed by Sandia National Laboratories (SNL) under contract to the NRC in support of license renewal activities. Results showed that some of the environmentally qualified cables either failed or exhibited marginal insulation resistance after a simulated plant life of 20 years during accident simulation. This indicated that the EQ process for some electric cables may be non-conservative. These results raised questions regarding the EQ process including the bases for conclusions about the qualified life of components based upon artificial aging prior to testing.

  19. Environmental Qualification at Savannah River Site

    SciTech Connect (OSTI)

    Martin, S.A.; Murphy, S.L.; Riley, P.J.; Sharma, M.K.; Sheikh, N.A.; Weister, T.E.

    1992-01-01

    The objective of Environmental Qualification (EQ) is to demonstrate that equipment essential to the mitigation of consequences from, and monitoring of plant conditions following Design Basis Accidents (DBAs) will operate as intended under normal/abnormal and accident environmental conditions over the installed life. For example, if a component is needed to maintain the reactor in a safe shutdown condition during an accident, and if the component is subjected to a harsh environment during that accident, then documentation must be prepared addressing the ability of the equipment to work properly in the accident environment. The requirement for an EQ program at SRS was mandated by the Department of Energy (DOE) K-Reactor Safety Evaluation Report (SER) which requires SRS to: (1) provide a long term plan for an EQ program with DOE approval prior to restart and (2) prepare and submit to DOE, Justifications for Continued Operations, that justify restarting and operating the K-Reactor until a long term compliance can be achieved with DOE approval.

  20. FTCP-08-001, Methodology for Counting TQP Personnel and Qualifications...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    1, Methodology for Counting TQP Personnel and Qualifications FTCP-08-001, Methodology for Counting TQP Personnel and Qualifications FTCP Issue Paper: FTCP-08-001 Approved by FTCP, ...

  1. U.S. Department of Energy Hydrogen Component and System Qualification

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Workshop - Presentations | Department of Energy U.S. Department of Energy Hydrogen Component and System Qualification Workshop - Presentations U.S. Department of Energy Hydrogen Component and System Qualification Workshop - Presentations These presentations were given at the U.S. Department of Energy Hydrogen Component and System Qualification Workshop held November 4, 2010 in Livermore, CA. Hydrogen Industrial Trucks: Component and System Qualification Workshop Mr. Aaron Harris Nuvera Fuel

  2. Nondestructive Testing Qualification of Main Circulatory Tube Pipes DU 500

    SciTech Connect (OSTI)

    Tabakova, Bojana M.; Tzokov, Petio

    2004-07-01

    The criteria for safe operation of nuclear energetic installations is given a higher priority in the policy of Kozloduy Nuclear Power Plant. An efficient non-destructive inspection is the key point for the safe service. Kozloduy NPP keeps on making investments in equipment and qualification of specialists in this field. The processes of qualification of the NDT components, important for the nuclear and radiation safety, make considerable improvement in Kozloduy NPP, thanks to the accumulated in the years experience in the activities of NDT inspection qualification, and to the help of our partners Serco Assurance and the Institute of Rzes. The results obtained by ultrasonic non-destructive inspection of circulation tube mains DU 500 WWER 440 type are under discussion in this report. (authors)

  3. Hanford Waste Vitrification Plant Project Waste Form Qualification Program Plan

    SciTech Connect (OSTI)

    Randklev, E.H.

    1993-06-01

    The US Department of Energy has created a waste acceptance process to help guide the overall program for the disposal of high-level nuclear waste in a federal repository. This Waste Form Qualification Program Plan describes the hierarchy of strategies used by the Hanford Waste Vitrification Plant Project to satisfy the waste form qualification obligations of that waste acceptance process. A description of the functional relationship of the participants contributing to completing this objective is provided. The major activities, products, providers, and associated scheduling for implementing the strategies also are presented.

  4. Accelerated Stress Testing, Qualification Testing, HAST, Field Experience

    Broader source: Energy.gov [DOE]

    This presentation, which was the opening session of the NREL 2013 Photovoltaic Module Reliability Workshop held on February 26, 2013 in Golden, CO, was presented by John Wohlgemuth. Entitled "Accelerated Stress Testing, Qualification Testing, HAST, Field Experience -- What Do They All Mean?" the presentation details efforts to develop accelerated stress tests beyond the qualification test levels, which are necessary to predict PV module wear-out. The commercial success of PVs is ultimately based on the long-term reliability and safety of the deployed PV modules.

  5. Policies and Procedures

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    procedures Policies and Procedures Guidelines Safety Computer Security Conduct of Operations JLF Forms Publication Policy

  6. Functional Area Qualification Standards Review Process | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Review Process Functional Area Qualification Standards Review Process Document Available for Download Review Process for Technical Standards (116.38 KB) More Documents & Publications DOE-STD-1176-2004 DOE-TSPP-4-2013, Developing DOE Technical Standards DOE Project Management Risk Committee (PMRC) SOP

  7. Facility Representative Qualification Equivalencies Based on Previous Experience

    Broader source: Energy.gov [DOE]

    The purpose of this Memorandum is to provide guidance, Attachment 1, to Qualifying Officials (QO) on how to use the cross-walk, Attachment 2, in granting equivalencies to Facility Representative (FR) candidates using the most current FR Functional Area Qualification Standards, DOE-STD-1151-2010.

  8. Personnel Selection, Qualification, and Training Requirements for DOE Nuclear Facilities

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2001-07-12

    To establish selection, qualification, and training requirements for management and operating (M&O) contractor personnel involved in the operation, maintenance, and technical support of Department of Energy and National Nuclear Security Administration Category A and B reactors and non-reactor nuclear facilities. Canceled by DOE O 426.2

  9. Decant pump assembly and controls qualification testing - test report

    SciTech Connect (OSTI)

    Staehr, T.W., Westinghouse Hanford

    1996-05-02

    This report summarizes the results of the qualification testing of the supernate decant pump and controls system to be used for in-tank sludge washing in aging waste tank AZ-101. The test was successful and all components are qualified for installation and use in the tank.

  10. Procedures - 88-Inch Cyclotron

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Procedures You must be logged in with your Berkeley Lab LDAP to view these documents PUB-3000 Cyclotron Procedures Mechanical Procedures Electrical Procedures Ion Source Procedures Accelerator Safety (SAD & ASE) Radiological Work Authorizations Memorandums Forms Abbreviations & Acronyms

  11. Civil/Structural Engineering Functional Area Qualification Standard

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    82-2014 September 2014 DOE STANDARD CIVIL/STRUCTURAL ENGINEERING FUNCTIONAL AREA QUALIFICATION STANDARD DOE Defense Nuclear Facilities Technical Personnel U.S. Department of Energy AREA TRNG Washington, D.C. 20585 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. DOE-STD-1182-2014 ii This document is available on the Department of Energy Technical Standards Program website at

  12. Technical Qualification Program Self-Assessment Report - NNSA Production

    Office of Environmental Management (EM)

    Office - 2014 | Department of Energy NNSA Production Office - 2014 Technical Qualification Program Self-Assessment Report - NNSA Production Office - 2014 In preparation for the upcoming Chief for Defense Nuclear Safety (CDNS) review, a self-assessment of NNSA Production Office (NPO) oversight of the B&W Pantex Plant and the Y-12 National Security Complex was completed from October 2013 - January 2014. The scope included all available CDNS Criteria, Review, and Approach Documents (CRADS)

  13. Plutonium metal and oxide container weld development and qualification

    SciTech Connect (OSTI)

    Fernandez, R.; Horrell, D.R.; Hoth, C.W.; Pierce, S.W.; Rink, N.A.; Rivera, Y.M.; Sandoval, V.D.

    1996-01-01

    Welds were qualified for a container system to be used for long-term storage of plutonium metal and oxide. Inner and outer containers are formed of standard tubing with stamped end pieces gas-tungsten-arc (GTA) welded onto both ends. The weld qualification identified GTA parameters to produce a robust weld that meets the requirements of the Department of Energy standard DOE-STD-3013-94, ``Criteria for the Safe Storage of Plutonium Metals and Oxides.``

  14. High Temperature Materials Interim Data Qualification Report FY 2011

    SciTech Connect (OSTI)

    Nancy Lybeck

    2011-08-01

    Projects for the very high temperature reactor (VHTR) Technology Development Office provide data in support of Nuclear Regulatory Commission licensing of the VHTR. Fuel and materials to be used in the reactor are tested and characterized to quantify performance in high temperature and high fluence environments. The VHTR program has established the Next Generation Nuclear Plant (NGNP) Data Management and Analysis System (NDMAS) to ensure that VHTR data are qualified for use, stored in a readily accessible electronic form, and analyzed to extract useful results. This document focuses on the first NDMAS objective. It describes the High Temperature Materials characterization data stream, the processing of these data within NDMAS, and reports the interim fiscal year (FY) 2011 qualification status of the data. Data qualification activities within NDMAS for specific types of data are determined by the data qualification category assigned by the data generator. The High Temperature Materials data are being collected under the Nuclear Quality Assurance (NQA)-1 guidelines and will be qualified data. For NQA-1 qualified data, the qualification activities include: (1) capture testing to confirm that the data stored within NDMAS are identical to the raw data supplied, (2) accuracy testing to confirm that the data are an accurate representation of the system or object being measured, and (3) documenting that the data were collected under an NQA-1 or equivalent Quality Assurance program. Currently, data from seven test series within the High Temperature Materials data stream have been entered into the NDMAS vault, including tensile tests, creep tests, and cyclic tests. Of the 5,603,682 records currently in the vault, 4,480,444 have been capture passed, and capture testing is in process for the remaining 1,123,238.

  15. Technical Qualification Program Reaccreditation Report - Y-12 Site Office |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Reaccreditation Report - Y-12 Site Office Technical Qualification Program Reaccreditation Report - Y-12 Site Office The accreditation process consists of three distinct activities: (1) a thorough self-evaluation by the organization requesting accreditation; (2) an independent, onsite evaluation by a TQP Accreditation Review Team; and (3) a review by an independent TQP Accreditation Board. This report documents the results of the review of the National Nuclear Security

  16. Technical Qualification Program Self-Assessment Report - Los Alamos Site

    Office of Environmental Management (EM)

    Office - 2011 | Department of Energy 11 Technical Qualification Program Self-Assessment Report - Los Alamos Site Office - 2011 The purpose of the FTCP TQP self-assessment team evaluation was to conduct a thorough evaluation of the status of the implementation of the National Nuclear Security Administration (NNSA) LASO TQP. This report documents the activities and results of the team evaluation of the LASO TQP. The overall approach of the TQP self-assessment was to evaluate the personnel,

  17. Nuclear Explosive Safety Study Functional Area Qualification Standard

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    i NOT MEASUREMENT SENSITIVE DOE-STD-1185-2007 CHANGE NOTICE No.1 April 2010 DOE STANDARD NUCLEAR EXPLOSIVE SAFETY STUDY FUNCTIONAL AREA QUALIFICATION STANDARD DOE Defense Nuclear Facilities Technical Personnel U.S. Department of Energy AREA TRNG Washington, D.C. 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. DOE-STD-1185-2007 ii This document is available on the Department of Energy Technical Standards Program Web Site at

  18. Nuclear Explosives Safety Study Functional Area Qualification Standard

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    85-2007 September 2007 DOE STANDARD NUCLEAR EXPLOSIVE SAFETY STUDY FUNCTIONAL AREA QUALIFICATION STANDARD DOE Defense Nuclear Facilities Technical Personnel U.S. Department of Energy AREA TRNG Washington, D.C. 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. DRAFT DOE-STD-1185-2007 ii This document is available on the Department of Energy Technical Standards Program Web Site at http://www.hss.energy.gov/nuclearsafety/techstds/ DRAFT DOE-STD-1185-2007 iv

  19. AGR-2 Data Qualification Report for ATR Cycle 154B

    SciTech Connect (OSTI)

    Binh Pham; Jeff Einerson

    2014-01-01

    This report provides the data qualification status of Advanced Gas Reactor-2 (AGR-2) fuel irradiation experimental data from Advanced Test Reactor (ATR) Cycle 154B as recorded in the Nuclear Data Management and Analysis System (NDMAS). This is the last cycle of AGR-2 irradiation, as the test train was pulled from the ATR core during the outage portion of ATR Cycle 155A. The AGR-2 data streams addressed in this report include thermocouple (TC) temperatures, sweep gas data (flow rates including new Fission Product Monitoring (FPM) downstream flows from Fission Product Monitoring System (FPMS) detectors, pressure, and moisture content), and FPMS data (release rates and release-to-birth rate ratios [R/Bs]) for each of the six capsules in the AGR-2 experiment. The final data qualification status for these data streams is determined by a Data Review Committee (DRC) comprised of AGR technical leads, Sitewide Quality Assurance (QA), and NDMAS analysts. The Data Review Committee reviewed the data acquisition process, considered whether the data met the requirements for data collection as specified in QA-approved Very High Temperature Reactor (VHTR) data collection plans, examined the results of NDMAS data testing and statistical analyses, and confirmed the qualification status of the data as given in this report.

  20. Qualification of uranium-molybdenum alloy fuel -- conclusions of an international workshop

    SciTech Connect (OSTI)

    Snelgrove, J. L.; Languilee, A.

    2000-02-14

    Thirty-one participants representing 21 reactors, fuel developers, fuel fabricators, and fuel reprocessors in 11 countries discussed the requirements for qualification of U-MO alloy fuel at a workshop held at Argonne National Laboratory on January 17--18, 2000. Consensus was reached that the qualification plans of the US RERTR program and the French U-Mo fuel development program are valid. The items to be addressed during qualification are summarized in the paper.

  1. Model Request for Qualifications to Pre-Qualify Energy Service Companies |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Request for Qualifications to Pre-Qualify Energy Service Companies Model Request for Qualifications to Pre-Qualify Energy Service Companies This page contains a model Request for Qualifications (RFQ) and associated documents intended for use by a state program to pre-qualify Energy Service Companies (ESCOs) to be available for as-needed Energy Savings Performance Contracting (ESPC) services for state and local governments within that state. The RFQ sets the stage for a

  2. Qualification of Innovative High Level Waste Pipeline Unplugging Technologies

    SciTech Connect (OSTI)

    McDaniel, D.; Gokaltun, S.; Varona, J.; Awwad, A.; Roelant, D.; Srivastava, R.

    2008-07-01

    In the past, some of the pipelines have plugged during high level waste (HLW) transfers resulting in schedule delays and increased costs. Furthermore, pipeline plugging has been cited by the 'best and brightest' technical review as one of the major issues that can result in unplanned outages at the Waste Treatment Plant causing inconsistent operation. As the DOE moves toward a more active high level waste retrieval, the site engineers will be faced with increasing cross-site pipeline waste slurry transfers that will result in increased probability of a pipeline getting plugged. Hence, availability of a pipeline unplugging tool/technology is crucial to ensure smooth operation of the waste transfers and in ensuring tank farm cleanup milestones are met. FIU had earlier tested and evaluated various unplugging technologies through an industry call. Based on mockup testing, two technologies were identified that could withstand the rigors of operation in a radioactive environment and with the ability to handle sharp 90 elbows. We present results of the second phase of detailed testing and evaluation of pipeline unplugging technologies and the objective is to qualify these pipeline unplugging technologies for subsequent deployment at a DOE facility. The current phase of testing and qualification comprises of a heavily instrumented 3-inch diameter (full-scale) pipeline facilitating extensive data acquisition for design optimization and performance evaluation, as it applies to three types of plugs atypical of the DOE HLW waste. Furthermore, the data from testing at three different lengths of pipe in conjunction with the physics of the process will assist in modeling the unplugging phenomenon that will then be used to scale-up process parameters and system variables for longer and site typical pipe lengths, which can extend as much as up to 19,000 ft. Detailed information resulting from the testing will provide the DOE end-user with sufficient data and understanding of the

  3. Technical Qualification Program Self-Assessment Report- Pacific Northwest Site Office- 2013

    Broader source: Energy.gov [DOE]

    This self-assessment evaluated how well the Technical Qualification and Federal Capability Programs were implemented at the Pacific Northwest Site Office (PNSO).

  4. Technical Qualification Program Self-Assessment Report- Office of River Protection- 2014

    Broader source: Energy.gov [DOE]

    A self-assessment was performed in accordance with TRS-OA-IP-07, Management (Self) Assessment, Rev. 2, where information was retrieved from MGT-QT-PL-01, Technical Qualification Program (TQP) Plan, Rev. 3; MGT-QT-DI-01, Technical Qualification Program: Federal Technical Capability Agent Duties, Rev. 2; technical staff electronic training and qualifications files; and ORP's technical staff hard copy training and qualification files to determine the effectiveness of the implemented program and identify any weaknesses of the existing program at turn-over of responsibilities.

  5. U.S. Department of Energy Component and System Qualification Workshop |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy U.S. Department of Energy Component and System Qualification Workshop U.S. Department of Energy Component and System Qualification Workshop The U.S. Department of Energy (DOE) and Sandia National Laboratories co-hosted the U.S. DOE Component and System Qualification Workshop on November 4, 2010 in Livermore, CA. The goal of the Workshop was to identify key needs, barriers, and actions to facilitate the qualification and listing of hydrogen and fuel cell systems and

  6. Qualification of Three On-line Slurry Monitoring Devices for Application during Waste Retrieval Operations at DOE Sites

    SciTech Connect (OSTI)

    Bontha, Jagannadha R.; Bamberger, Judith A.; Hylton, Tom D.; May, T. H.

    2000-10-18

    Qualification of Three On-line Slurry Monitoring Devices for Application during Waste Retrieval Operations at DOE Sites

  7. Code qualification of structural materials for AFCI advanced recycling reactors.

    SciTech Connect (OSTI)

    Natesan, K.; Li, M.; Majumdar, S.; Nanstad, R.K.; Sham, T.-L.

    2012-05-31

    This report summarizes the further findings from the assessments of current status and future needs in code qualification and licensing of reference structural materials and new advanced alloys for advanced recycling reactors (ARRs) in support of Advanced Fuel Cycle Initiative (AFCI). The work is a combined effort between Argonne National Laboratory (ANL) and Oak Ridge National Laboratory (ORNL) with ANL as the technical lead, as part of Advanced Structural Materials Program for AFCI Reactor Campaign. The report is the second deliverable in FY08 (M505011401) under the work package 'Advanced Materials Code Qualification'. The overall objective of the Advanced Materials Code Qualification project is to evaluate key requirements for the ASME Code qualification and the Nuclear Regulatory Commission (NRC) approval of structural materials in support of the design and licensing of the ARR. Advanced materials are a critical element in the development of sodium reactor technologies. Enhanced materials performance not only improves safety margins and provides design flexibility, but also is essential for the economics of future advanced sodium reactors. Code qualification and licensing of advanced materials are prominent needs for developing and implementing advanced sodium reactor technologies. Nuclear structural component design in the U.S. must comply with the ASME Boiler and Pressure Vessel Code Section III (Rules for Construction of Nuclear Facility Components) and the NRC grants the operational license. As the ARR will operate at higher temperatures than the current light water reactors (LWRs), the design of elevated-temperature components must comply with ASME Subsection NH (Class 1 Components in Elevated Temperature Service). However, the NRC has not approved the use of Subsection NH for reactor components, and this puts additional burdens on materials qualification of the ARR. In the past licensing review for the Clinch River Breeder Reactor Project (CRBRP) and the

  8. Awardee Share Procedures

    Broader source: Energy.gov (indexed) [DOE]

    Share Procedures Procedures for Correctly Reporting Awardee Share on the FAADSFAADS Plus reporting screen in STRIPES To ensure proper reporting by DOE to USASpending.gov, you...

  9. The DOE Advanced Gas Reactor Fuel Development and Qualification Program

    SciTech Connect (OSTI)

    David Petti

    2010-09-01

    The high outlet temperatures and high thermal-energy conversion efficiency of modular High Temperature Gas-cooled Reactors (HTGRs) enable an efficient and cost effective integration of the reactor system with non-electricity generation applications, such as process heat and/or hydrogen production, for the many petrochemical and other industrial processes that require temperatures between 300C and 900C. The Department of Energy (DOE) has selected the HTGR concept for the Next Generation Nuclear Plant (NGNP) Project as a transformative application of nuclear energy that will demonstrate emissions-free nuclear-assisted electricity, process heat, and hydrogen production, thereby reducing greenhouse-gas emissions and enhancing energy security. The objective of the DOE Advanced Gas Reactor (AGR) Fuel Development and Qualification program is to qualify tristructural isotropic (TRISO)-coated particle fuel for use in HTGRs. The Advanced Gas Reactor Fuel Development and Qualification Program consists of five elements: fuel manufacture, fuel and materials irradiations, post-irradiation examination (PIE) and safety testing, fuel performance modeling, and fission-product transport and source term evaluation. An underlying theme for the fuel development work is the need to develop a more complete, fundamental understanding of the relationship between the fuel fabrication process and key fuel properties, the irradiation and accident safety performance of the fuel, and the release and transport of fission products in the NGNP primary coolant system. An overview of the program and recent progress is presented.

  10. Resistance Weld Qualification Analysis for Radioactive Waste Canisters

    SciTech Connect (OSTI)

    Gupta, N.K.; Gong, C.

    1995-01-10

    High level radioactive waste canisters are sealed by resistance upset welding to ensure leak tight closures. Resistance welding is fast, uniform, and can be performed remotely to minimize radiation exposure to the operators. Canisters are constructed in accordance with ASME Band PV Code, Section VIII, Division 1, however, the resistance welds are not used in Section VIII. The resistance welds are qualified by analysis using material properties obtained from the test coupons. Burst tests are performed on canister welds to meet ASME Section IX welder qualification requirements. Since burst tests are not used in Section IX for resistance weld qualification, finite element results of canister resistance welds are compared with the finite element analysis results of resistance weld tests in ASME Section IX, QW-196 to establish similarity between the two weld tests. Detailed analyses show that the primary mode of failure in both the tests is shear and, therefore, the use of burst test in place of shear test is acceptable. It is believed that the detailed analyses and results could help in establishing acceptance criteria for resistance upset welding in ASME B&PV Code, Sections VIII, and IX.

  11. Trial Run of a Junction-Box Attachment Test for Use in Photovoltaic Module Qualification (Presentation)

    SciTech Connect (OSTI)

    Miller, D.; Deibert, S.; Wohlgemuth, J.

    2014-06-01

    Engineering robust adhesion of the junction-box (j-box) is a hurdle typically encountered by photovoltaic (PV) module manufacturers during product development and manufacturing process control. There are historical incidences of adverse effects (e.g., fires), caused when the j-box/adhesive/module system has failed in the field. The addition of a weight to the j-box during the 'damp-heat', 'thermal-cycle', or 'creep' tests within the IEC qualification protocol is proposed to verify the basic robustness of the adhesion system. The details of the proposed test are described, in addition to a trial run of the test procedure. The described experiments examine 4 moisture-cured silicones, 4 foam tapes, and a hot-melt adhesive used in conjunction with glass, KPE, THV, and TPE substrates. For the purpose of validating the experiment, j-boxes were adhered to a substrate, loaded with a prescribed weight, and then subjected to aging. The replicate mock-modules were aged in an environmental chamber (at 85 deg C/85% relative humidity for 1000 hours; then 100 degrees C/<10% relative humidity for 200 hours) or fielded in Golden, Miami, and Phoenix for 1 year. Attachment strength tests, including pluck and shear test geometries, were also performed on smaller component specimens.

  12. DEVELOPMENT QUALIFICATION AND DISPOSAL OF AN ALTERNATIVE IMMOBILIZED LOW-ACTIVITY WASTE FORM AT THE HANFORD SITE

    SciTech Connect (OSTI)

    SAMS TL; EDGE JA; SWANBERG DJ; ROBBINS RA

    2011-01-13

    Demonstrating that a waste form produced by a given immobilization process is chemically and physically durable as well as compliant with disposal facility acceptance criteria is critical to the success of a waste treatment program, and must be pursued in conjunction with the maturation of the waste processing technology. Testing of waste forms produced using differing scales of processing units and classes of feeds (simulants versus actual waste) is the crux of the waste form qualification process. Testing is typically focused on leachability of constituents of concern (COCs), as well as chemical and physical durability of the waste form. A principal challenge regarding testing immobilized low-activity waste (ILAW) forms is the absence of a standard test suite or set of mandatory parameters against which waste forms may be tested, compared, and qualified for acceptance in existing and proposed nuclear waste disposal sites at Hanford and across the Department of Energy (DOE) complex. A coherent and widely applicable compliance strategy to support characterization and disposal of new waste forms is essential to enhance and accelerate the remediation of DOE tank waste. This paper provides a background summary of important entities, regulations, and considerations for nuclear waste form qualification and disposal. Against this backdrop, this paper describes a strategy for meeting and demonstrating compliance with disposal requirements emphasizing the River Protection Project (RPP) Integrated Disposal Facility (IDF) at the Hanford Site and the fluidized bed steam reforming (FBSR) mineralized low-activity waste (LAW) product stream.

  13. GAP analysis towards a design qualification standard development for grid-connected photovoltaic inverters.

    SciTech Connect (OSTI)

    Tamizhmani, Govindasamy; Granata, Jennifer E.; Maracas, George; Ayyanar, Raja; Marinella, Matthew; Venkataramanan, Sai Balasubramanian Alampoondi

    2011-06-01

    A dedicated design qualification standard for PV inverters does not exist. Development of a well-accepted design qualification standard, specifically for PV inverters will significantly improve the reliability and performance of inverters. The existing standards for PV inverters such as ANSI/UL 1741 and IEC 62109-1 primarily focus on safety of PV inverters. The IEC 62093 discusses inverter qualification but it includes all the BOS components. There are other general standards for distributed generators including the IEEE 1547 series of standards which cover major concerns like utility integration but they are not dedicated to PV inverters and are not written from a design qualification point of view. In this paper some of the potential requirements for a design qualification standard for PV inverters are addressed. The missing links in existing PV inverter related standards are identified and with the IEC 62093 as a guideline, the possible inclusions in the framework for a dedicated design qualification standard of PV inverter are discussed. Some of the key missing links are related to electric stress tests. Hence, a method to adapt the existing surge withstand test standards for use in design qualification standard of PV inverter is presented.

  14. Computerized procedures system

    SciTech Connect (OSTI)

    Lipner, Melvin H.; Mundy, Roger A.; Franusich, Michael D.

    2010-10-12

    An online data driven computerized procedures system that guides an operator through a complex process facility's operating procedures. The system monitors plant data, processes the data and then, based upon this processing, presents the status of the current procedure step and/or substep to the operator. The system supports multiple users and a single procedure definition supports several interface formats that can be tailored to the individual user. Layered security controls access privileges and revisions are version controlled. The procedures run on a server that is platform independent of the user workstations that the server interfaces with and the user interface supports diverse procedural views.

  15. U.S. Commits $14 million to U.S. - Ukraine Nuclear Fuel Qualification

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project | Department of Energy Commits $14 million to U.S. - Ukraine Nuclear Fuel Qualification Project U.S. Commits $14 million to U.S. - Ukraine Nuclear Fuel Qualification Project March 15, 2007 - 10:55am Addthis KYIV, Ukraine - U.S. Department of Energy Deputy Secretary Clay Sell today announced that the United States will invest $14 million to provide 42 nuclear fuel assemblies to the South Ukraine Nuclear Power Plant under the U.S.-Ukraine Nuclear Fuel Qualification Project (UNFQP). In

  16. Low-level radioactive waste form qualification testing

    SciTech Connect (OSTI)

    Sohal, M.S.; Akers, D.W.

    1998-06-01

    This report summarizes activities that have already been completed as well as yet to be performed by the Idaho National Engineering and Environmental Laboratory (INEEL) to develop a plan to quantify the behavior of radioactive low-level waste forms. It briefly describes the status of various tasks, including DOE approval of the proposed work, several regulatory and environmental related documents, tests to qualify the waste form, preliminary schedule, and approximate cost. It is anticipated that INEEL and Brookhaven National Laboratory will perform the majority of the tests. For some tests, services of other testing organizations may be used. It should take approximately nine months to provide the final report on the results of tests on a waste form prepared for qualification. It is anticipated that the overall cost of the waste quantifying service is approximately $150,000. The following tests are planned: compression, thermal cycling, irradiation, biodegradation, leaching, immersion, free-standing liquid tests, and full-scale testing.

  17. EDS V25 containment vessel explosive qualification test report.

    SciTech Connect (OSTI)

    Rudolphi, John Joseph

    2012-04-01

    The V25 containment vessel was procured by the Project Manager, Non-Stockpile Chemical Materiel (PMNSCM) as a replacement vessel for use on the P2 Explosive Destruction Systems. It is the first EDS vessel to be fabricated under Code Case 2564 of the ASME Boiler and Pressure Vessel Code, which provides rules for the design of impulsively loaded vessels. The explosive rating for the vessel based on the Code Case is nine (9) pounds TNT-equivalent for up to 637 detonations. This limit is an increase from the 4.8 pounds TNT-equivalency rating for previous vessels. This report describes the explosive qualification tests that were performed in the vessel as part of the process for qualifying the vessel for explosive use. The tests consisted of a 11.25 pound TNT equivalent bare charge detonation followed by a 9 pound TNT equivalent detonation.

  18. Federal Agency NEPA Procedures

    Broader source: Energy.gov [DOE]

    Each Federal agency is required to develop NEPA procedures that supplement the CEQ Regulations. Developed in consultation with CEQ, Federal agency NEPA procedures must meet the standards in the CEQ...

  19. CRAD, NNSA- Federal Employee Training and Qualification Program (FED T&Q)

    Office of Energy Efficiency and Renewable Energy (EERE)

    CRAD for Federal Employee Training and Qualification Program (FED T&Q). Criteria Review and Approach Documents (CRADs) that can be used to conduct a well-organized and thorough assessment of elements of safety and health programs.

  20. Technical Qualification Program Self-Assessment Report- Livermore Field Office- 2013

    Broader source: Energy.gov [DOE]

    The purpose of the Livermore Field Office (LFO) Teclmical Qualification Program (TQP) is to ensure that federal teclmical personnel with safety oversight responsibilities at defense nuclear facilities at Lawrence Livermore National Laboratory possess competence commensurate with responsibilities.

  1. Senior Technical Safety Manager Qualification Program Self-Assessment- Chief of Nuclear Safety

    Broader source: Energy.gov [DOE]

    This Chief of Nuclear Safety (CNS) Report was prepared to summarize the results of the July 2013 CNS self-assessment of the Senior Technical Safety Manager Qualification Program.

  2. H.A.R. 13-281 - Rules Governing Professional Qualifications ...

    Open Energy Info (EERE)

    search OpenEI Reference LibraryAdd to library Legal Document- RegulationRegulation: H.A.R. 13-281 - Rules Governing Professional QualificationsLegal Published NA Year Signed or...

  3. Technical Qualification Program Self-Assessment Report- Y-12 Site Office- 2010

    Office of Energy Efficiency and Renewable Energy (EERE)

    The National Nuclear Security Administration Y-12 Site Office (YSO) has successfully implemented a Technical Qualification Program (YSO TQP) that produces highly qualified, technical individuals to execute oversight of site activities and support the site missions.

  4. Sample results from the interim salt disposition program macrobatch 9 tank 21H qualification samples

    SciTech Connect (OSTI)

    Peters, T. B.

    2015-11-01

    Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 9 for the Interim Salt Disposition Program (ISDP). This document reports characterization data on the samples of Tank 21H.

  5. Technical Qualification Program Self-Assessment Report- Savannah River Site Office- 2011

    Broader source: Energy.gov [DOE]

    This self assessment evaluates the effective implementation of the Technical Qualification Programs (TQP). The Federal Technical Capability Panel (FTCP) also reviews the results of the TQP self-assessments and determines if further action is necessary on a Departmental level.

  6. Technical Qualification Program Self-Assessment Report- Sandia Site Office- 2012

    Broader source: Energy.gov [DOE]

    This self assessment examined how Sandia Site Office (SSO) executes the Technical Qualification Program (TQP) as measured by the current Federal Technical Capability Panel criteria review and approach documents (CRADs) included in the assessment plan.

  7. An analysis of the qualification criteria for small radioactive material shipping packages

    SciTech Connect (OSTI)

    McClure, J.D.

    1983-05-01

    The RAM package design certification process has two important elements, testing and acceptance. These terms sound very similar but they have specific meanings. Qualification testing in the context of this study is the imposition of simulated accident test conditions upon the candidate package design. (Normal transportation environments may also be included.) Following qualification testing, the acceptance criteria provide the performance levels which, if demonstrated, indicate the ability of the RAM package to sustain the severity of the qualification testing sequence and yet maintain specified levels of package integrity. This study has used Severities of Transportation Accidents as a data base to examine the regulatory test criteria which are required to be met by small packages containing Type B quantities of radioactive material (RAM). The basic findings indicate that the present regulatory test standards provide significantly higher levels of protection for the surface transportation modes (truck, rail) than for RAM packages shipped by aircraft. It should also be noted that various risk assessment studies have shown that the risk to the public due to severe transport accidents by surface and air transport modes is very low. A key element in this study was the quantification of the severity of the transportation accident environment and the severity of the present qualification test standards (called qualification test standards in this document) so that a direct comparison could be made between them to assess the effectiveness of the existing qualification test standards. The manner in which this was accomplished is described.

  8. Senior Technical Safety Manager Qualification Program Self-Assessment...

    Energy Savers [EERE]

    In accordance CNS Standard Operating Procedure SOP-016, Senior Technical Safety Manager ... More Documents & Publications 2011 Annual Workforce Analysis and Staffing Plan Report - ...

  9. AGR-2 Final Data Qualification Report for U.S. Capsules - ATR Cycles 147A Through 154B

    SciTech Connect (OSTI)

    Pham, Binh T; Einerson, Jeffrey J

    2014-07-01

    end of irradiation when the recording frequency was higher. For sweep gas data, there were 10,144,020 gas flow records and of these data only 503,803 gas flow records (5.0% of the gas flow data) were Failed and 1,135,600 gas flow records (11.2% of the gas flow data) were Trend. The Failed gas flow records are mostly missing values and the number was reduced due to the repair of some missing and negative neon and helium flow rates. Trend flow rate records are the FPM flow rates during ATR Cycles 153A and 153B. Because of capsule gas cross-talk and leakage problems that occurred after Cycle 150A, a procedure was implemented by AGR-2 operations staff on January 17, 2012 (Cycle 151A) that used uniform neon fraction of gas mixtures in all six capsules and the leadout so the capsules’ actual gas mixture can be accurately defined. Use of the capsule outlet gas flow data after Cycle 150A in calculating FPMS release rate and R/B data should take into account possibilities of fission product cross-talk between capsules. The downstream flow meters help in detection of the capsule relief valves lifting. For FPMS data, NDMAS received and processed release and R/B data for all “full power” reactor cycles. This data consists of 190,416 release rate records and 190,416 R/B records for the 12 radionuclides reported. The R/B data are calculated using the isotope daily birthrates. According to FPMS data qualification status reported in ECAR-2420 [Scates 2014], due to the relief valve failure during cycles 149A and 149B and the capsule flow cross-talk failure that began during Cycle 150B, the FPMS data will not be Qualified after the end of Cycle 148B. However, the data still provide useful information for identifying particle failures and performing additional analyses and will be flagged as Trend. All of the above data have been processed and tested using a SAS®-based enterprise application software system, stored in a secure Structured Query Language database, made available on

  10. Simplified Acquisition Procedures

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ------------------------- Chapter 13.3 (March 2014) 1 [Reference: FAR Subpart 13. 3 and FAR Subpart 13.5] Simplified Acquisition Procedures 1. Introduction Simplified Acquisition Procedures (SAP) are contracting methods designed to streamline the acquisition process and facilitate the procurement of goods and services. The results include less paperwork and lower costs for both the contractor and the Government. FAR 13.003(a) states, "Agencies shall use simplified acquisition procedures to