National Library of Energy BETA

Sample records for transmission upgrades needed

  1. Single-shell tank ventilation upgrades needs analysis report

    SciTech Connect (OSTI)

    Kriskovich, J.R., Fluor Daniel Hanford

    1997-02-03

    This report was written to comply with the objectives of the Hanford Federal Facility Agreement and Consent Order, Tri-Party Agreement Milestone M-43-03 Provide to the Washington State Department of Ecology and Department of Health the Results of the Single-Shell Tank Ventilation Upgrades Needs Analysis. The needs analysis consists of identifying the current type and status of each single-shell tank ventilation system, identifying current and projected authorization basis requirements, and identifying ventilation system compliance deficiencies.

  2. Marys Lake 69/115-kV transmission line upgrade and substation expansion projects

    SciTech Connect (OSTI)

    1996-05-01

    Western Area Power Administration (Western) and the Platte River Power Authority (Platte River) propose to upgrade portions of the existing electric transmission and substation system that serves the Town of Estes Park, Colorado. The existing transmission lines between the Estes Power Plant Switchyard and the Marys Lake Substation include a 115,000 volt (115-kV) line and 69,000 volt (69-kV) line. Approximately one mile is a double-circuit 115/69-kV line on steel lattice structures, and approximately two miles consists of separate single-circuit 115-kV and a 69-kV lines, constructed on wood H-Frame structures. Both lines were constructed in 1951 by the US Bureau of Reclamation. The existing transmission lines are on rights-of-way (ROW) that vary from 75 feet to 120 feet and are owned by Western. There are 48 landowners adjacent to the existing ROW. All of the houses were built adjacent to the existing ROW after the transmission lines were constructed. Upgrading the existing 69-kV transmission line between the Marys Lake Substation and the Estes Power Plant Switchyard to 115-kV and expanding the Marys Lake Substation was identified as the most effective way in which to improve electric service to Estes Park. The primary purpose and need of the proposed project is to improve the reliability of electric service to the Town of Estes Park. Lack of reliability has been a historical concern, and reliability will always be less than desired until physical improvements are made to the electrical facilities serving Estes Park.

  3. Request for Proposals for New or Upgraded Transmission Line Projects Under

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Section 1222 of the Energy Policy Act of 2005: Federal Register Notice Volume 75, No. 111 - Jun 10, 2012 | Department of Energy Proposals for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005: Federal Register Notice Volume 75, No. 111 - Jun 10, 2012 Request for Proposals for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005: Federal Register Notice Volume 75, No. 111 - Jun 10, 2012 FRN Request for

  4. Heavy oil development in Canada - The need for upgrading

    SciTech Connect (OSTI)

    Quinn, P.C.

    1987-01-01

    The author first reviews Canada's petroleum reserves, then summarizes the problem facing Canada regarding dwindling supplies of conventional light and medium crude oils and briefly describes Canada's refining capability. With that background, he attempts to analyze the problems that face heavy oil producers in attempting to market their product and propose a potential solution to these problems as illustrated by Husky Oil's approach - the construction of a heavy oil upgrader. He closes by sharing his views on the future of heavy oil development and the policy issues facing our governments.

  5. Infrastructure Needs: Natural Gas/Electricity Transmission,...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... This will require significant northsouth transmission investment that falls outside of our ... We are a partner with the New England States Committee on Electricity (NESCOE) ...

  6. Infrastructure Needs: Natural Gas/Electricity Transmission,...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Through our six operating companies, Eversource operates over 4,300 miles of transmission lines, 72,000 miles of distribution lines, and 6,500 miles of natural gas pipelines. ...

  7. EA-1948: Gila-North Gila Transmission Line Rebuild and Upgrade Project, Yuma County, Arizona

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration (Western) prepared this EA to analyze the potential environmental impacts of a proposal to rebuild and upgrade two parallel 4.8-mile transmission lines between the Gila and North Gila Substations and take actions in support of portions of Arizona Public Service’s construction of a new, 12.8 mile 230-kV transmission line between North Gila and a proposed substation in Yuma County, Arizona. The U.S. Bureau of Reclamation and U.S. Army Corps of Engineers are cooperating agencies.

  8. EA-1951: Midway-Moxee Rebuild and Midway-Grandview Upgrade Transmission Line Project; Benton and Yakima Counties, Washington

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration is preparing an EA to assess the potential environmental impacts of the proposed rebuilding of the existing 34-mile Midway-Moxee transmission line and the proposed rebuilding and upgrading of the existing 26-mile Midway-Grandview transmission line. Both 115-kV lines originate at the BPA Midway Substation in Benton County and terminate in Yakima County.

  9. EA-1951: Midway-Moxee Rebuild and Midway-Grandview Upgrade Transmission Line; Benton and Yakima Counties, Washington

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration is preparing an EA to assess the potential environmental impacts of the proposed rebuilding of the existing 34-mile Midway-Moxee transmission line and the proposed rebuilding and upgrading of the existing 26-mile Midway-Grandview transmission line. Both 115-kV lines originate at the BPA Midway Substation in Benton County and terminate in Yakima County.

  10. Potential impacts of nanotechnology on energy transmission applications and needs.

    SciTech Connect (OSTI)

    Elcock, D.; Environmental Science Division

    2007-11-30

    The application of nanotechnologies to energy transmission has the potential to significantly impact both the deployed transmission technologies and the need for additional development. This could be a factor in assessing environmental impacts of right-of-way (ROW) development and use. For example, some nanotechnology applications may produce materials (e.g., cables) that are much stronger per unit volume than existing materials, enabling reduced footprints for construction and maintenance of electricity transmission lines. Other applications, such as more efficient lighting, lighter-weight materials for vehicle construction, and smaller batteries having greater storage capacities may reduce the need for long-distance transport of energy, and possibly reduce the need for extensive future ROW development and many attendant environmental impacts. This report introduces the field of nanotechnology, describes some of the ways in which processes and products developed with or incorporating nanomaterials differ from traditional processes and products, and identifies some examples of how nanotechnology may be used to reduce potential ROW impacts. Potential environmental, safety, and health impacts are also discussed.

  11. Needs analysis and project schedule for the Los Alamos National Laboratory (LANL) Health Physics Analysis Laboratory (HPAL) upgrade

    SciTech Connect (OSTI)

    Rhea, T.A.; Rucker, T.L.; Stafford, M.W.

    1990-09-28

    This report is a needs assessment and project schedule for the Health Physics Analysis Laboratory (HPAL) upgrade project at Los Alamos National Laboratory (LANL). After reviewing current and projected HPAL operations, two custom-developed laboratory information management systems (LIMS) for similar facilities were reviewed; four commercially available LIMS products were also evaluated. This project is motivated by new regulations for radiation protection and training and by increased emphasis on quality assurance (QA). HPAL data are used to: protect the health of radiation workers; document contamination levels for transportation of radioactive materials and for release of materials to the public for uncontrolled use; and verify compliance with environmental emission regulations. Phase 1 of the HPAL upgrade project concentrates on four types of counting instruments which support in excess of 90% of the sample workload at the existing central laboratories. Phase 2 is a refinement phase and also integrates summary-level databases on the central Health, Safety, and Environment (HSE) VAX. Phase 3 incorporates additional instrument types and integrates satellite laboratories into the HPAL LIMS. Phase 1 will be a multi-year, multimillion dollar project. The temptation to approach the upgrade of the HPAL program in a piece meal fashion should be avoided. This is a major project, with clearly-defined goals and priorities, and should be approached as such. Major programmatic and operational impacts will be felt throughout HSE as a result of this upgrade, so effective coordination with key customer contacts will be critical.

  12. Evaluating the Effect of Upgrade, Control and Development Strategies on Robustness and Failure Risk of the Power Transmission Grid

    SciTech Connect (OSTI)

    Newman, David E; Carreras, Benjamin A; Lynch, Vickie E; Dobson, Ian

    2008-01-01

    We use the OPA complex systems model of the power transmission system to investigate the effect of a series of different network upgrade scenarios on the long time dynamics and the probability of large cascading failures. The OPA model represents the power grid at the level of DC load flow and LP generation dispatch and represents blackouts caused by randomly triggered cascading line outages and overloads. We examine the effect of increased component reliability on the long-term risks, the effect of changing operational margins and the effect of redundancy on those same long-term risks. The general result is that while increased reliability of the components decreases the probability of small blackouts, depending on the implementation, it actually can increase the probability of large blackouts. When we instead increase some types of redundancy of the system there is an overall decrease in the large blackouts. As some of these results are counter intuitive these studies suggest that care must be taken when making what seem to be logical upgrade decisions.

  13. Montana ARM 17.20.1606, Electric Transmission Lines, Need Standard...

    Open Energy Info (EERE)

    search OpenEI Reference LibraryAdd to library Legal Document- RegulationRegulation: Montana ARM 17.20.1606, Electric Transmission Lines, Need StandardLegal Abstract Need...

  14. Bonneville upgrades lines

    SciTech Connect (OSTI)

    Not Available

    1993-08-30

    A stretch of Bonneville Power Administration transmission line between Spokane and the Grand Coulee Dam is an 82-mile bottleneck as it is the last 115-kv section of [open quotes]road[close quotes] along a 500-kv transmission [open quotes]highway[close quotes]. Soon the administration will change all that. A number of independent and utility powerplants have been proposed in Idaho, Montana and the Spokane, Wash., area during the 1990s. As the operators will need to move their power, Bonneville is planning to build a $144-million, 500-kv line to upgrade the 115-kv section. The agency is planning to use its existing right-of-way.

  15. Electric utility transmission and distribution upgrade deferral benefits from modular electricity storage : a study for the DOE Energy Storage Systems Program.

    SciTech Connect (OSTI)

    Eyer, James M.

    2009-06-01

    The work documented in this report was undertaken as part of an ongoing investigation of innovative and potentially attractive value propositions for electricity storage by the United States Department of Energy (DOE) and Sandia National Laboratories (SNL) Electricity Storage Systems (ESS) Program. This study characterizes one especially attractive value proposition for modular electricity storage (MES): electric utility transmission and distribution (T&D) upgrade deferral. The T&D deferral benefit is characterized in detail. Also presented is a generalized framework for estimating the benefit. Other important and complementary (to T&D deferral) elements of possible value propositions involving MES are also characterized.

  16. EA-1951: Midway-Moxee Rebuild and Midway-Grandview Upgrade Transmissio...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    51: Midway-Moxee Rebuild and Midway-Grandview Upgrade Transmission Line; Benton and Yakima Counties, Washington EA-1951: Midway-Moxee Rebuild and Midway-Grandview Upgrade ...

  17. Status of TMX upgrade diagnostics construction

    SciTech Connect (OSTI)

    Hornady, R.S.; Davis, J.C.; Simonen, T.C.

    1981-07-20

    This report describes the status of the initial TMX Upgrade diagnostics and the state of development of additional diagnostics being prepared for later TMX Upgrade experiments. The initial diagnostic instrument set has been described in the TMX Upgrade Proposal. This set is required to get TMX Upgrade operational and to evaluate its initial performance. Additional diagnostic instruments are needed to then carry out the more detailed experiments outlined by the TMX Upgrade program milestones. The relation of these new measurements to the physics program is described in The TMX Upgrade Program Plan.

  18. RHIC LUMINOSITY UPGRADE PROGRAM

    SciTech Connect (OSTI)

    Fischer, W.

    2010-05-23

    The Relativistic Heavy Ion Collider (RHIC) operates with either ions or polarized protons. After increasing the heavy ion luminosity by two orders of magnitude since its commissioning in 2000, the current luminosity upgrade program aims for an increase by another factor of 4 by means of 3D stochastic cooling and a new 56 MHz SRF system. An Electron Beam Ion Source is being commissioned that will allow the use of uranium beams. Electron cooling is considered for collider operation below the current injection energy. For the polarized proton operation both luminosity and polarization are important. In addition to ongoing improvements in the AGS injector, the construction of a new high-intensity polarized source has started. In RHIC a number of upgrades are under way to increase the intensity and polarization transmission to 250 GeV beam energy. Electron lenses will be installed to partially compensate the head-on beam-beam effect.

  19. LHC detector upgrades

    SciTech Connect (OSTI)

    Dan Green

    2003-09-15

    The LHC detectors are well into their construction phase. The LHC schedule shows first beam to ATLAS and CMS in 2007. Because the LHC accelerator has begun to plan for a ten fold increase in LHC design luminosity (the SLHC or super LHC) it is none too soon to begin to think about the upgrades which will be required of the present LHC detectors. In particular, the tracking systems of ATLAS and CMS will need to be completely rebuilt. Given the time needed to do the R & D, make prototypes, and construct the new detectors and given the accelerator schedule for the SLHC, work needs to begin rather soon.

  20. Plains & Eastern Clean Line Project Proposal for New or Upgraded

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 | Department of Energy Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 Plains & Eastern Clean Line Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 Plains & Eastern Clean Line Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy

  1. Safety analysis report for packaging upgrade plan

    SciTech Connect (OSTI)

    Kelly, D.L.

    1998-03-12

    This SARP Upgrade Plan reflects a revised SARP upgrade schedule based on the most current program needs. A performance agreement has been assigned, beginning in FY 1997, to update, revise, and/or cancel 20 percent of the existing onsite SARPS, so that 100 percent are reviewed and within current standards by the completion of the Project Hanford Management Contract (five-year period).

  2. Estimating electricity storage power rating and discharge duration for utility transmission and distribution deferral :a study for the DOE energy storage program.

    SciTech Connect (OSTI)

    Eyer, James M. (Distributed Utility Associates, Livermore, CA); Butler, Paul Charles; Iannucci, Joseph J., Jr.

    2005-11-01

    This report describes a methodology for estimating the power and energy capacities for electricity energy storage systems that can be used to defer costly upgrades to fully overloaded, or nearly overloaded, transmission and distribution (T&D) nodes. This ''sizing'' methodology may be used to estimate the amount of storage needed so that T&D upgrades may be deferred for one year. The same methodology can also be used to estimate the characteristics of storage needed for subsequent years of deferral.

  3. Richard Shaheen named Senior VP of Transmission

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    transmission lines and initiated upgrades to Celilo Substation and the Pacific Direct Current Intertie. "Richard is an excellent leader, and his 25-plus years of experience at a...

  4. Home Upgrades: Leveraging HVAC Upgrades for Greater Impact (201)

    Broader source: Energy.gov [DOE]

    Better Buildings Residential Network Peer Exchange Call Series: Home Upgrades: Leveraging HVAC Upgrades for Greater Impact (201), November 18, 2015.

  5. Financing Small Business Upgrades

    Broader source: Energy.gov [DOE]

    Better Buildings Neighborhood Program Financing Peer Exchange Call: Financing Small Business Upgrades, call slides and discussion summary, October 25, 2012.

  6. Algal Lipid Extraction and Upgrading to Hydrocarbons Technology Pathway |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Lipid Extraction and Upgrading to Hydrocarbons Technology Pathway Algal Lipid Extraction and Upgrading to Hydrocarbons Technology Pathway This technology pathway case investigates the cultivation of algal biomass followed by further lipid extraction and upgrading to hydrocarbon biofuels. Technical barriers and key research needs have been assessed in order for the algal lipid extraction and upgrading pathway to be competitive with petroleum-derived gasoline-, diesel-,

  7. Algal Lipid Extraction and Upgrading to Hydrocarbons Technology Pathway

    Office of Scientific and Technical Information (OSTI)

    (Technical Report) | SciTech Connect Algal Lipid Extraction and Upgrading to Hydrocarbons Technology Pathway Citation Details In-Document Search Title: Algal Lipid Extraction and Upgrading to Hydrocarbons Technology Pathway This technology pathway case investigates the cultivation of algal biomass followed by further lipid extraction and upgrading to hydrocarbon biofuels. Technical barriers and key research needs have been assessed in order for the algal lipid extraction and upgrading

  8. The Need for Essential Consumer Protections: Smart Metering Proposals and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    the Move to Time-Based Pricing | Department of Energy Metering Proposals and the Move to Time-Based Pricing The Need for Essential Consumer Protections: Smart Metering Proposals and the Move to Time-Based Pricing There is a widespread consensus that the U.S. distribution and transmission systems for vital electricity service need to be modernized and upgraded to handle not only load growth, but the integration of renewable resources and the potential for a significant increase in

  9. Plains & Eastern Clean Line Project Proposal for New or Upgraded...

    Broader source: Energy.gov (indexed) [DOE]

    Clean Line Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 (July 2010) PDF icon Update to Plains & Eastern Clean ...

  10. Power Electronics for Distributed Energy Systems and Transmission and Distribution Applications: Assessing the Technical Needs for Utility Applications

    SciTech Connect (OSTI)

    Tolbert, L.M.

    2005-12-21

    Power electronics can provide utilities the ability to more effectively deliver power to their customers while providing increased reliability to the bulk power system. In general, power electronics is the process of using semiconductor switching devices to control and convert electrical power flow from one form to another to meet a specific need. These conversion techniques have revolutionized modern life by streamlining manufacturing processes, increasing product efficiencies, and increasing the quality of life by enhancing many modern conveniences such as computers, and they can help to improve the delivery of reliable power from utilities. This report summarizes the technical challenges associated with utilizing power electronics devices across the entire spectrum from applications to manufacturing and materials development, and it provides recommendations for research and development (R&D) needs for power electronics systems in which the U.S. Department of Energy (DOE) could make a substantial impact toward improving the reliability of the bulk power system.

  11. Safety analysis report for packaging upgrade plan

    SciTech Connect (OSTI)

    KELLY, D.L.

    1998-11-18

    This Safety Analysis Report for Packaging (SARP) Upgrade Plan reflects a revised SARP upgrade schedule based on the most current program needs. A Project Hanford Management Contract (PHMC) Performance Expectation exists to update, revise, and/or cancel seven onsite SARPS during FY 1999. It is the U.S. Department of Energy's desire that 100% of the SARPs (which existed at the beginning of the PHMC Contract) be upgraded, revised, and/or canceled by the end of the five year contract. This plan is a ''living'' document and is used as a management tool.

  12. Capturing Energy Upgrades

    Broader source: Energy.gov [DOE]

    Provides an overview of how to capture the value of energy efficiency upgrades in the real estate market, from CNT Energy.

  13. Lowell, Massachusetts, Preserves Historic Home Through Energy Upgrades |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Preserves Historic Home Through Energy Upgrades Lowell, Massachusetts, Preserves Historic Home Through Energy Upgrades Photo of a two-story historic home. Artist James MacNeil Whistler's birthplace home in Lowell, Massachusetts, was built in 1823 and now houses the Lowell Art Association. The house was in need of a series of upgrades that improved energy efficiency while catering to the specific needs of a historic home and museum. Through the BetterBuildings Lowell

  14. Safety analysis report for packaging upgrade plan

    SciTech Connect (OSTI)

    Kelly, D.L., Westinghouse Hanford

    1996-12-09

    This Safety Analysis Report for Packaging (SARP) Upgrade Plan reflects a SARP upgrade schedule based on the most current program needs. A performance agreement has been assigned, beginning in FY 1997, to update, revise, and/or cancel 20 percent of the existing onsite SARPS, so that 100 percent are reviewed and within current standards by the completion of the Project Hanford Management Contract (five-year period).

  15. Hydrocarbonaceous material upgrading method

    SciTech Connect (OSTI)

    Brecher, Lee E.; Mones, Charles G.; Guffey, Frank D.

    2015-06-02

    A hydrocarbonaceous material upgrading method may involve a novel combination of heating, vaporizing and chemically reacting hydrocarbonaceous feedstock that is substantially unpumpable at pipeline conditions, and condensation of vapors yielded thereby, in order to upgrade that feedstock to a hydrocarbonaceous material condensate that meets crude oil pipeline specification.

  16. NSLS control system upgrade

    SciTech Connect (OSTI)

    Smith, J.D.; Ramamoorthy, S.; Tang, Yong N.

    1995-12-31

    The NSLS consists of two storage rings, a booster and a linac. A major upgrade of the control system (installed in 1978) was undertaken and has been completed. The computer architecture is being changed from a three level star-network to a two level distributed system. The microprocessor subsystem, host computer and workstations, communication link and the main software components are being upgraded or replaced. Since the NSLS rings operate twenty four hours a day a year with minimum maintenance time, the key requirement during the upgrade phase is a non-disruptive transition with minimum downtime. Concurrent with the upgrade, some immediate improvements were required. This paper describes the various components of the upgraded system and outlines the future plans.

  17. Energy Upgrade California

    Office of Energy Efficiency and Renewable Energy (EERE)

    The Energy Upgrade California program serves as a one-stop shop for California homeowners who want to improve the energy efficiency of their homes. The program connects homeowners with qualified...

  18. Algal Lipid Extraction and Upgrading to Hydrocarbons Technology Pathway

    SciTech Connect (OSTI)

    Davis, R.; Biddy, M.; Jones, S.

    2013-03-01

    This technology pathway case investigates the cultivation of algal biomass followed by further lipid extraction and upgrading to hydrocarbon biofuels. Technical barriers and key research needs have been assessed in order for the algal lipid extraction and upgrading pathway to be competitive with petroleum-derived gasoline-, diesel-, and jet-range hydrocarbon blendstocks.

  19. Cyclotron Institute Upgrade Project

    SciTech Connect (OSTI)

    Clark, Henry; Yennello, Sherry; Tribble, Robert

    2014-08-26

    The Cyclotron Institute at Texas A&M University has upgraded its accelerator facilities to extend research capabilities with both stable and radioactive beams. The upgrade is divided into three major tasks: (1) re-commission the K-150 (88”) cyclotron, couple it to existing beam lines to provide intense stable beams into the K-500 experimental areas and use it as a driver to produce radioactive beams; (2) develop light ion and heavy ion guides for stopping radioactive ions created with the K-150 beams; and (3) transport 1+ ions from the ion guides into a charge-breeding electron-cyclotron-resonance ion source (CB-ECR) to produce highly-charged radioactive ions for acceleration in the K-500 cyclotron. When completed, the upgraded facility will provide high-quality re-accelerated secondary beams in a unique energy range in the world.

  20. Honeymoons Lead to Upgrades in Western Vermont

    Broader source: Energy.gov [DOE]

    For homeowners who are hesitant to make energy efficiency upgrades, offering them a honeymoon might just be the motivation they need. NeighborWorks of Western Vermont (NWWVT) created a "honeymoon period" for its loan payments and has seen success by allowing homeowners to experience six months of comfort and energy savings before they begin making loan payments.

  1. Energy Efficiency Upgrades in Multifamily Housing | Department...

    Energy Savers [EERE]

    Upgrades in Multifamily Housing Energy Efficiency Upgrades in Multifamily Housing Better Buildings Residential Network Case Study: Energy Efficiency Upgrades in Multifamily ...

  2. Heavy oil. upgrading integrated with steam drive

    SciTech Connect (OSTI)

    Van Driesen, R.; Viens, C.H.; Fornoff, L.L.

    1980-01-01

    A study of the upgrading of heavy oil from a representative Venezuelan Jobo crude (9.2/sup 0/API, 4.1% sulfur, and 500 ppm total metals) from the Orinoco area involved 110 computer simulations based on a modified C-E Lummus Refinery Linear Program model on the assumptions of a 125,000 bbl/day refinery built, starting at 1979 prices, for completion by 1986 near the producing field to supply the fuel oil needed to provide oil field steam. All of the upgrading systems were economically attractive; the per cent return-on-investment (ROI) before taxes for the methods studied were: for Lummus LC-Fining, 135.9%; for Exxon's FLEXICOKING, 132.4%; for delayed coking, 119.2%; and for deasphalting, 106.5%. LC-Fining provided the best over-all combination of flexibility, product yield, product quality, and return on investment. The economics favored upgrading to the maximum extent possible; there was a reduction in the ROI for all the upgrading systems when product specifications were lowered from the premium base case (1.2% SO/sub 2/ emitted per million Btu fired). The premium upgraded heavy crude oils should be worth $3.00-$3.50/bbl more than comparable conventional crude oils, could be of up to 27/sup 0/API, and could be substituted, at up to 50%, for conventional crude oils in a typical U.S. refinery.

  3. Climate balance of biogas upgrading systems

    SciTech Connect (OSTI)

    Pertl, A.; Mostbauer, P.; Obersteiner, G.

    2010-01-15

    One of the numerous applications of renewable energy is represented by the use of upgraded biogas where needed by feeding into the gas grid. The aim of the present study was to identify an upgrading scenario featuring minimum overall GHG emissions. The study was based on a life-cycle approach taking into account also GHG emissions resulting from plant cultivation to the process of energy conversion. For anaerobic digestion two substrates have been taken into account: (1) agricultural resources and (2) municipal organic waste. The study provides results for four different upgrading technologies including the BABIU (Bottom Ash for Biogas Upgrading) method. As the transport of bottom ash is a critical factor implicated in the BABIU-method, different transport distances and means of conveyance (lorry, train) have been considered. Furthermore, aspects including biogas compression and energy conversion in a combined heat and power plant were assessed. GHG emissions from a conventional energy supply system (natural gas) have been estimated as reference scenario. The main findings obtained underlined how the overall reduction of GHG emissions may be rather limited, for example for an agricultural context in which PSA-scenarios emit only 10% less greenhouse gases than the reference scenario. The BABIU-method constitutes an efficient upgrading method capable of attaining a high reduction of GHG emission by sequestration of CO{sub 2}.

  4. Biochemical upgrading of oils

    DOE Patents [OSTI]

    Premuzic, E.T.; Lin, M.S.

    1999-01-12

    A process for biochemical conversion of heavy crude oils is provided. The process includes contacting heavy crude oils with adapted biocatalysts. The resulting upgraded oil shows, a relative increase in saturated hydrocarbons, emulsions and oxygenates and a decrease in compounds containing organic sulfur, organic nitrogen and trace metals. Adapted microorganisms which have been modified under challenged growth processes are also disclosed. 121 figs.

  5. Biochemical upgrading of oils

    DOE Patents [OSTI]

    Premuzic, Eugene T. (East Moriches, NY); Lin, Mow S. (Rocky Point, NY)

    1999-01-12

    A process for biochemical conversion of heavy crude oils is provided. The process includes contacting heavy crude oils with adapted biocatalysts. The resulting upgraded oil shows, a relative increase in saturated hydrocarbons, emulsions and oxygenates and a decrease in compounds containing in organic sulfur, organic nitrogen and trace metals. Adapted microorganisms which have been modified under challenged growth processes are also disclosed.

  6. The Need for Essential Consumer Protections: Smart metering proposals and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    the move to time-based pricing. August 2010 | Department of Energy metering proposals and the move to time-based pricing. August 2010 The Need for Essential Consumer Protections: Smart metering proposals and the move to time-based pricing. August 2010 There is widespread consensus that the U.S. distribution and transmission systems for vital electricity service need to be modernized and upgraded. This modernization has been recently promoted under the rubric of the Smart Grid. The Smart Grid

  7. Advanced Photon Source Upgrade Project

    ScienceCinema (OSTI)

    Mitchell, John; Gibson, Murray; Young, Linda; Joachimiak, Andrzej

    2013-04-19

    Upgrade to Advanced Photon Source announced by Department Of Energy. Read more: http://go.usa.gov/ivZ

  8. Analysis Efforts Supporting NSTX Upgrades

    SciTech Connect (OSTI)

    H.Zhang, P. Titus, P. Rogoff, A.Zolfaghari, D. Mangra, M. Smith

    2010-11-29

    The National Spherical Torus Experiment (NSTX) is a low aspect ratio, spherical torus (ST) configuration device which is located at Princeton Plasma Physics Laboratory (PPPL) This device is presently being updated to enhance its physics by doubling the TF field to 1 Tesla and increasing the plasma current to 2 Mega-amperes. The upgrades include a replacement of the centerstack and addition of a second neutral beam. The upgrade analyses have two missions. The first is to support design of new components, principally the centerstack, the second is to qualify existing NSTX components for higher loads, which will increase by a factor of four. Cost efficiency was a design goal for new equipment qualification, and reanalysis of the existing components. Showing that older components can sustain the increased loads has been a challenging effort in which designs had to be developed that would limit loading on weaker components, and would minimize the extent of modifications needed. Two areas representing this effort have been chosen to describe in more details: analysis of the current distribution in the new TF inner legs, and, second, analysis of the out-of-plane support of the existing TF outer legs.

  9. Financing Multifamily Energy Efficiency Upgrades | Department...

    Energy Savers [EERE]

    Multifamily Energy Efficiency Upgrades Financing Multifamily Energy Efficiency Upgrades Better Buildings Residential Network Peer Exchange Call Series: Financing Multifamily Energy ...

  10. Preparation for upgrading western subbituminous coal

    SciTech Connect (OSTI)

    Grimes, R.W.; Cha, C.Y.; Sheesley, D.C.

    1990-11-01

    The objective of this project was to establish the physical and chemical characteristics of western coal and determine the best preparation technologies for upgrading this resource. Western coal was characterized as an abundant, easily mineable, clean, low-sulfur coal with low heating value, high moisture, susceptibility to spontaneous ignition, and considerable transit distances from major markets. Project support was provided by the Morgantown Energy Technology Center (METC) of the US Department of Energy (DOE). The research was conducted by the Western Research Institute, (WRI) in Laramie, Wyoming. The project scope of work required the completion of four tasks: (1) project planning, (2) literature searches and verbal contacts with consumers and producers of western coal, (3) selection of the best technologies to upgrade western coal, and (4) identification of research needed to develop the best technologies for upgrading western coals. The results of this research suggest that thermal drying is the best technology for upgrading western coals. There is a significant need for further research in areas involving physical and chemical stabilization of the dried coal product. Excessive particle-size degradation and resulting dustiness, moisture reabsorption, and high susceptibility to spontaneous combustion are key areas requiring further research. Improved testing methods for the determination of equilibrium moisture and susceptibility to spontaneous ignition under various ambient conditions are recommended.

  11. CRYOGENICS IN BEPCII UPGRADE.

    SciTech Connect (OSTI)

    JIA,L.; WANG,L.; LI,S.

    2002-07-22

    THIS PAPER PRESENTS A CRYOGENIC DESIGN FOR UPGRADING THE BEIJING ELECTRON POSITRON COLLIDER AT THE INSTITUTE OF HIGH ENERGY PHYSICS IN BEIJING. THE UPGRADE INVOLVES 3 NEW SUPERCONDUCTING FACILITIES, THE INTERACTION REGION QUADRUPOLE MAGNETS, THE DETECTOR SOLENOID MAGNETS AND THE SRF CAVITIES. FOR COOLING OF THESE DEVICES, A NEW CRYPLANT WITH A TOTAL CAPACITY OF 1.0KW AT 4.5K IS TO BE BUILT AT IHEP. AN INTEGRATED CRYOGENIC DESIGN TO FIT THE BEPCII CRYOGENIC LOADS WITH HIGH EFFICIENCY IS CARRIEDOUT USING COMPUTATIONAL PROCESS ANALYSIS SOFTWARE WITH THE EMPHASES ON ECONOMICS AND SAFETY IN BOTH CONSTRUCTION AND OPERATION OF THE PLANT. THIS PAPER DESCRIBES THE CRYOGENIC CHARACTERISTICS OF EACH SUPERCONDUCTING DEVICE, THEIR COOLING SCHEMES AND THE OVERALL CRYOPLANT.

  12. Home Upgrades: Leveraging HVAC Upgrades for Greater Impact (201...

    Office of Environmental Management (EM)

    More Documents & Publications Where Do We Go From Here? The Changing Landscape of Residential Energy Efficiency (201) Staged Upgrades as a Strategy for Residential Energy ...

  13. Upgrading residual oil

    SciTech Connect (OSTI)

    Angevine, P.J.; Stein, T.R.

    1982-04-13

    Residual oil fractions are upgraded in that Conradson Carbon Residue (CCR) is selectively removed without undue hydrogen consumption by hydroprocessing with a catalyst comprising a single metal such as molybdenum, tungsten, nickel, iron or palladium or multimetallic combination of such metals, excluding, however, active desulfurization compositions such as nickel molybdenum and nickel-tungsten. Said catalyst is characterized as having greater than about 50% of its pore volume contribution in pores having diameters in the range of between about 100 and 200 angstroms. The product of such hydroprocessing is a particularly preferable feedstock for coking to give more liquid yield and less coke make.

  14. Upgraded Coal Interest Group

    SciTech Connect (OSTI)

    Evan Hughes

    2009-01-08

    The Upgraded Coal Interest Group (UCIG) is an EPRI 'users group' that focuses on clean, low-cost options for coal-based power generation. The UCIG covers topics that involve (1) pre-combustion processes, (2) co-firing systems and fuels, and (3) reburn using coal-derived or biomass-derived fuels. The UCIG mission is to preserve and expand the economic use of coal for energy. By reducing the fuel costs and environmental impacts of coal-fired power generation, existing units become more cost effective and thus new units utilizing advanced combustion technologies are more likely to be coal-fired.

  15. Upgrading Troffer Luminaires to LED

    SciTech Connect (OSTI)

    none,

    2014-01-31

    Solid-state lighting technology fact sheet providing guidance on the various factors to consider when deciding on an LED upgrade for a fluorescent troffer system.

  16. upgrade | OpenEI Community

    Open Energy Info (EERE)

    by Rmckeel(297) Contributor 22 October, 2012 - 07:23 Semantic Mediawiki Semantic Forms update developer Incentives and Policies Semantic Mediawiki upgrade Utility Rates We have...

  17. Financing Multifamily Energy Efficiency Upgrades

    Broader source: Energy.gov [DOE]

    Better Buildings Residential Network Peer Exchange Call Series: Financing Multifamily Energy Efficiency Upgrades, Call Slides and Discussion Summary, February 12, 2015.

  18. Microsoft Word - NTS Security Upgrades-Article _2_.doc

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    NTS Security Upgrades in Full Swing NTS takes 21 st century technology lead From 1992 to 2004 the Nevada Test Site (NTS) sat underutilized. A moratorium had eliminated the primary mission of the NTS - underground nuclear testing. The stringent security requirements needed to safeguard operations would go a decade without upgrades or improvements. But in 2004, the National Nuclear Security Administration (NNSA) tasked the Nevada Site Office with a new nuclear materials mission. "Our security

  19. Renewable Resource Integration Project - Scoping Study of Strategic Transmission, Operations, and Reliability Issues

    SciTech Connect (OSTI)

    Eto, Joseph; Budhraja, Vikram; Ballance, John; Dyer, Jim; Mobasheri, Fred; Eto, Joseph

    2008-07-01

    California is on a path to increase utilization of renewable resources. California will need to integrate approximately 30,000 megawatts (MW) of new renewable generation in the next 20 years. Renewable resources are typically located in remote locations, not near the load centers. Nearly two/thirds or 20,000 MW of new renewable resources needed are likely to be delivered to Los Angeles Basin transmission gateways. Integration of renewable resources requires interconnection to the power grid, expansion of the transmission system capability between the backbone power grid and transmission gateways, and increase in delivery capacity from transmission gateways to the local load centers. To scope the transmission, operations, and reliability issues for renewables integration, this research focused on the Los Angeles Basin Area transmission gateways where most of new renewables are likely. Necessary actions for successful renewables integration include: (1) Expand Los Angeles Basin Area transmission gateway and nomogram limits by 10,000 to 20,000 MW; (2) Upgrade local transmission network for deliverability to load centers; (3) Secure additional storage, demand management, automatic load control, dynamic pricing, and other resources that meet regulation and ramping needed in real time operations; (4) Enhance local voltage support; and (5) Expand deliverability from Los Angeles to San Diego and Northern California.

  20. July 31 Webinar to Provide Guidance on Transmission Feasibility and System Impact Studies

    Broader source: Energy.gov [DOE]

    Join the next free tribal renewable energy series webinar and learn about analyzing and assessing the impacts, costs, and benefits of transmission line upgrades and additions.

  1. Upgrading the ATLAS control system

    SciTech Connect (OSTI)

    Munson, F.H.; Ferraretto, M.

    1993-09-01

    Heavy-ion accelerators are tools used in the research of nuclear and atomic physics. The ATLAS facility at the Argonne National Laboratory is one such tool. The ATLAS control system serves as the primary operator interface to the accelerator. A project to upgrade the control system is presently in progress. Since this is an upgrade project and not a new installation, it was imperative that the development work proceed without interference to normal operations. An additional criteria for the development work was that the writing of additional ``in-house`` software should be kept to a minimum. This paper briefly describes the control system being upgraded, and explains some of the reasons for the decision to upgrade the control system. Design considerations and goals for the new system are described, and the present status of the upgrade is discussed.

  2. Generating Demand for Multifamily Building Upgrades | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Generating Demand for Multifamily Building Upgrades Generating Demand for Multifamily Building Upgrades Better Buildings Residential Network Peer Exchange Call Series: Generating...

  3. Energy Efficiency Upgrades Help Build Better Neighborhoods |...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Efficiency Upgrades Help Build Better Neighborhoods Energy Efficiency Upgrades Help Build Better Neighborhoods May 6, 2013 - 4:55pm Addthis In neighborhoods all across the...

  4. Steam-system upgrades | Open Energy Information

    Open Energy Info (EERE)

    upgrades Jump to: navigation, search TODO: Add description List of Steam-system upgrades Incentives Retrieved from "http:en.openei.orgwindex.php?titleSteam-systemupgrades&old...

  5. Energy Efficiency Upgrades for Sanitation Facilities Selawik...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Selawik Sanitation Facilities 1970s Original Facility 1984 Renovations 1997 Improvements 2000- 2002 Upgrades 2005- 2008 WTP Rehab 2011 Current Energy Upgrades 2014 What's Next? ...

  6. Webinar: "Upgrading Renewable and Sustainable Carbohydrates for...

    Energy Savers [EERE]

    "Upgrading Renewable and Sustainable Carbohydrates for the Production of High Energy Density Fuels" Webinar: "Upgrading Renewable and Sustainable Carbohydrates for the Production of ...

  7. Financing Small Business Upgrades | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Small Business Upgrades Financing Small Business Upgrades Better Buildings Neighborhood ... Exchange Kickoff Call Strategies for Marketing and Driving Demand for Commercial ...

  8. Generating Demand for Multifamily Building Upgrades | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Generating Demand for Multifamily Building Upgrades Generating Demand for Multifamily Building Upgrades Better Buildings Residential Network Peer Exchange Call Series: Generating ...

  9. SLHC, the High-Luminosity Upgrade (public event)

    ScienceCinema (OSTI)

    None

    2011-10-06

    In the morning of June 23rd a public event is organised in CERN's Council Chamber with the aim of providing the particle physics community with up-to-date information about the strategy for the LHC luminosity upgrade and to describe the current status of preparation work. The presentations will provide an overview of the various accelerator sub-projects, the LHC physics prospects and the upgrade plans of ATLAS and CMS. This event is organised in the framework of the SLHC-PP project, which receives funding from the European Commission for the preparatory phase of the LHC High Luminosity Upgrade project. Informing the public is among the objectives of this EU-funded project. A simultaneous transmission of this meeting will be broadcast, available at the following address: http://webcast.cern.ch/

  10. The RHIC polarized source upgrade

    SciTech Connect (OSTI)

    Zelenski, A.; Atoian, G.; Davydenko, V.; Ivanov, A.; Kolmogorov, A.; Ritter, J.; Steski, D.; Zubets, V.

    2010-09-27

    The RHIC polarized H{sup -} ion source is being upgraded to higher intensity (5-10 mA) and polarization for use in the RHIC polarization physics program at enhanced luminosity RHIC operation. The higher beam peak intensity will allow reduction of the transverse beam emittance at injection to AGS to reduce polarization losses in AGS. There is also a planned RHIC luminosity upgrade by using the electron beam lens to compensate the beam-beam interaction at collision points. This upgrade is also essential for future BNL plans for a high-luminosity electron - proton (ion) Collider eRHIC.

  11. Transmission Infrastructure Program

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    TRANSMISSION INFRASTRUCTURE PROGRAM DOE Tribal Energy Summit 2015 SECRETARYOF ENERGY'S FINANCING ROUNDTABLE Tracey A. LeBeau Senior Vice President & Transmission Infrastructure Program Manager 1 Program Description Western's Loan Authority * $3.25 billion permanent authority (revolving) * Goal: Attract investment in infrastructure & address market needs * Commercial underwriting standards TIP Portfolio Management Fundamentals * Reflective of Market Need(s) * Ensure Funds Revolve 2 Recent

  12. Conversion Technologies for Advanced Biofuels - Carbohydrates Upgrading |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Upgrading Conversion Technologies for Advanced Biofuels - Carbohydrates Upgrading PNNL report-out presentation at the CTAB webinar on carbohydrates upgrading. ctab_webinar_carbohydrates_upgrading.pdf (583.49 KB) More Documents & Publications Advanced Conversion Roadmap Workshop Conversion Technologies for Advanced Biofuels - Carbohydrates Production Innovative Topics for Advanced Biofuels

  13. Syngas Upgrading to Hydrocarbon Fuels Technology Pathway

    SciTech Connect (OSTI)

    Talmadge, M.; Biddy, M.; Dutta, A.; Jones, S.; Meyer, A.

    2013-03-01

    This technology pathway case investigates the upgrading of woody biomass derived synthesis gas (syngas) to hydrocarbon biofuels. While this specific discussion focuses on the conversion of syngas via a methanol intermediate to hydrocarbon blendstocks, there are a number of alternative conversion routes for production of hydrocarbons through a wide array of intermediates from syngas. Future work will also consider the variations to this pathway to determine the most economically viable and lowest risk conversion route. Technical barriers and key research needs have been identified that should be pursued for the syngas-to-hydrocarbon pathway to be competitive with petroleum-derived gasoline-, diesel- and jet-range hydrocarbon blendstocks.

  14. User and Performance Impacts from Franklin Upgrades

    SciTech Connect (OSTI)

    He, Yun

    2009-05-10

    The NERSC flagship computer Cray XT4 system"Franklin" has gone through three major upgrades: quad core upgrade, CLE 2.1 upgrade, and IO upgrade, during the past year. In this paper, we will discuss the various aspects of the user impacts such as user access, user environment, and user issues etc from these upgrades. The performance impacts on the kernel benchmarks and selected application benchmarks will also be presented.

  15. Midway-Moxee Rebuild and Midway-Grandview Upgrade Transmission...

    Energy Savers [EERE]

    ... Similarly, commercial, industrial, and municipal customers can experience impacts when infrastructure such as machinery, traffic signals, light rail, or elevators stops ...

  16. FRN Request for Proposals for New or Upgraded Transmission Line...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... Energy, Department of Energy, 1000 Independence Avenue, SW., Washington, DC 20585; or ... Nebraska, Nevada, New Mexico, North Dakota, South Dakota, Texas, Utah, and Wyoming. ...

  17. Request for Proposals for New or Upgraded Transmission Line Projects...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Projects Under Section 1222 of the Energy Policy Act of 2005: Federal Register Notice ... Projects Under Section 1222 of the Energy Policy Act of 2005: Federal Register Notice ...

  18. Midway-Moxee Rebuild and Midway-Grandview Upgrade Transmission...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    About BPA Newsroom Integrated Fish & Wildlife Program Information for Contractors Environmental Services BPA Home Triangle Bullet Point EFW Home Triangle Bullet Point...

  19. Staged Upgrades — Homeowner-focused Strategies for Encouraging Energy Upgrades over Time

    Broader source: Energy.gov [DOE]

    Better Buildings Residential Network Peer Exchange Call Series: Staged Upgrades — Homeowner-Focused Strategies for Encouraging Energy Upgrades over Time, call slides and discussion summary.

  20. Conversion Technologies for Advanced Biofuels - Bio-Oil Upgrading...

    Office of Environmental Management (EM)

    Oil Upgrading Conversion Technologies for Advanced Biofuels - Bio-Oil Upgrading PNNL report-out at the CTAB webinar on Bio-Oil Upgrading. ctabwebinarbiooilsupgrading.pdf ...

  1. Energy Upgrade California Drives Demand From Behind the Wheel...

    Energy Savers [EERE]

    Upgrade California Drives Demand From Behind the Wheel Energy Upgrade California Drives Demand From Behind the Wheel Photo of a trailer with the Energy Upgrade California logo and ...

  2. Staged Upgrades - Homeowner-focused Strategies for Encouraging...

    Office of Environmental Management (EM)

    Staged Upgrades - Homeowner-focused Strategies for Encouraging Energy Upgrades over Time Better Buildings Residential Network Peer Exchange Call Series: Staged Upgrades - ...

  3. Upgrading Orinoco Belt heavy oil

    SciTech Connect (OSTI)

    Aliantara, J.; Castillo, O.

    1982-05-01

    Petroleos de Venezuela, S.A. (PDVSA), in an effort to develop new oil resources, has undertaken a program to evaluate and develop the Orinoco Heavy Oil Belt, in the eastern part of Venezuela. Lagoven, S.A., a subsidiary of PDVSA, has been assigned the responsibility for developing and upgrading part of the Orinoco belt. This paper describes the most relevant aspects of Lagoven's first upgrading module, a facility that will convert Orinoco oil into a premium crude with a very high yield of products of great market demand.

  4. High efficiency, low cost scrubber upgrades

    SciTech Connect (OSTI)

    Klingspor, J.S.; Walters, M.

    1998-07-01

    ABB introduced the LS-2 technology; a limestone based wet FGD system, which is capable of producing high purity gypsum from low grade limestone, in late 1995. Drawing from 30,000 MWe of worldwide wet FGD experience, ABB has incorporated several innovations in the new system designed to reduce the overall cost of SO{sub 2} compliance. Collectively, these improvements are referred to as LS-2. The improvements include a compact high efficiency absorber, a simple dry grinding system, a closed coupled flue gas reheat system, and a tightly integrated dewatering system. The compact absorber includes features such a high velocity spray zone, significantly improved gas-liquid contact system, compact reaction tank, and a high velocity mist eliminator. The LS-2 system is being demonstrated at Ohio Edison's Niles Plant at the 130 MWe level, and this turnkey installation was designed and erected in a 20-month period. At Niles, all of the gypsum is sold to a local wallboard manufacturer. Many of the features included in the LS-2 design and demonstrated at Niles can be used to improve the efficiency and operation of existing systems including open spray towers and tray towers. The SO{sub 2} removal efficiency can be significantly improved by installing the high efficiency LS-2 style spray header design and the unique wall rings. The absorber bypass can be eliminated or reduced by including the LS-2 style high velocity mist eliminator. Also, the LS-2 style spray header design combined with wall rings allow for an increase in absorber gas velocity at a maintained or improved performance without the need for costly upgrades of the absorber recycle pumps. the first upgrade using LS-2 technology was done at CPA's Coal Creek Station (2{times}545 MWe). The experience form the scrubber upgrade at Coal Creek is discussed along with operating results.

  5. Reactive plasma upgrade of squalane - a heavy oil simulant

    SciTech Connect (OSTI)

    Kong, P.C.; Watkins, A.D.; Detering, B.A.; Thomas, C.P.

    1995-10-01

    U.S. light crude oil production has steadily declined over the last two decades. However, huge known heavy oil deposits in the North American continent remain largely untapped. In the past 10 years, the API gravity of crude oils has been decreasing by about 0.17% per year, and the sulfur content has been increasing by about 0.027% per year. As the API gravity of crude oil decreases, there will be an urgent need for economically viable new technologies to upgrade the heavy oil to a high API gravity feed stock for the refineries. The Idaho National Engineering Laboratory is investigating an innovative plasma process to upgrade heavy oil and refinery residuum. This paper will present some of the results and the implications of this technology for heavy oil upgrade and conversion.

  6. Parris Island Wastewater Treatment Plant SCADA Upgrades Final Report

    SciTech Connect (OSTI)

    Meador, Richard J.; Hatley, Darrel D.

    2004-03-18

    Marine Corp Recruit Depot (MCRD), Parris Island, SC, home of the Easter Recruiting Region Marine Corp Boot Camp, found itself in a situation common to Department of Defense (DOD) facilities. It had to deal with several different types of installed energy-related control systems that could not talk to each other. This situation was being exacerbated by the installation of a new and/or unique type of control system for every new building being constructed or older facility that was being upgraded. The Wastewater Treatment Facility (WWTF) and lift station controls were badly in need of a thorough inspection and a new Supervisory Control and Data Acquisition (SCADA) system upgrade to meet environmental, safety, manpower, and maintenance concerns. A project was recently completed to implement such a wastewater treatment SCADA upgrade, which is compatible with other upgrades to the energy monitoring and control systems for Parris Island buildings and the Pacific Northwest National Laboratory (PNNL) Decision Support for Operations and Maintenance (DSOM) system installed at the Central Energy Plant (CEP). This project included design, specification, procurement, installation, and testing an upgraded SCADA alarm, process monitoring, and display system; and training WWTF operators in its operation. The ultimate goal of this and the other PNNL projects at Parris Island is to allow monitoring and control of energy and environmental components from a central location.

  7. Facility Upgrade - Cyclotron Institute - TAMU

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the Cyclotron Institute Facility Upgrade White Paper Follow the links below to open the files, or right click and select "Save Target As..." to save the file to your computer. File Type File Size Adobe PDF 752 KB MS-Word 18840 KB Postscript 1660 KB

  8. Cyclotron Institute Upgrade Project - Facilities - Cyclotron Institute

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Upgrade Overview / K150 Cyclotron / Light Ion Guide / Heavy Ion Guide / Negative Ion Source / CB-ECRIS Facility Upgrade White Paper Overview Picture of the experimental set up to measure beta-decay half-lives. On January 3, 2005 the Cyclotron Institute Upgrade Project (CIUP) began with the approval of the CIUP management plan by the Department of Energy Nuclear Physics Office. The project will extend to the first quarter of calendar year 2011. When completed, the upgraded facility will provide

  9. CEBAF Upgrade: Cryomodule Performance And Lessons Learned

    SciTech Connect (OSTI)

    Drury, Michael A.; Davis, G. Kirk; Hogan, John P.; Hovater, J. Curt; King, Lawrence; Marhauser, Frank; Park, HyeKyoung; Preble, Joe; Reece, Charles E.; Rimmer, Robert A.; Wang, Haipeng; Wiseman, Mark A.

    2014-02-01

    The Thomas Jefferson National Accelerator Facility is currently engaged in the 12 GeV Upgrade Project. The goal of the 12 GeV Upgrade is a doubling of the available beam energy of the Continuous Electron Beam Accelerator Facility (CEBAF) from 6 GeV to 12 GeV. This increase in beam energy will be due in large part to the addition of ten C100 cryomodules plus associated new RF in the CEBAF linacs. The C100 cryomodules are designed to deliver 100 MeV per installed cryomodule. Each C100 cryomodule is built around a string of eight seven-cell, electro-polished, superconducting RF cavities. While an average performance of 100MV per cryomodule is needed to achieve the overall 12 GeV beam energy goal, the actual performance goal for the cryomodules is an average energy gain of 108 MV to provide operational headroom. Cryomodule production started in December 2010. All ten of the C100 cryomodules are installed in the linac tunnels and are on schedule to complete commissioning by September 2013. Performance during Commissioning has ranged from 104 MV to 118 MV. In May, 2012 a test of an early C100 achieved 108 MV with full beam loading. This paper will discuss the performance of the C100 cryomodules along with operational challenges and lessons learned for future designs.

  10. Quality Control, Standardization of Upgrades, and Workforce Expectatio...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Quality Control, Standardization of Upgrades, and Workforce Expectations Quality Control, Standardization of Upgrades, and Workforce Expectations Better Buildings Residential ...

  11. RHIC and its upgrade programmes.

    SciTech Connect (OSTI)

    Roser,T.

    2008-06-23

    As the first hadron accelerator and collider consisting of two independent superconducting rings RHIC has operated with a wide range of beam energies and particle species. After a brief review of the achieved performance the presentation will give an overview of the plans, challenges and status of machine upgrades, that range from a new heavy ion pre-injector and beam cooling at 100 GeV to a high luminosity electron-ion collider.

  12. Energy Efficiency Through Lighting Upgrades

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Chickasaw Nation Energy Efficiency Through Lighting Upgrades The Chickasaw Nation  The Chickasaw Nation consists of 13 counties in southeastern Oklahoma  Tribal enrollment exceeds 35,000  The Tribal headquarters complex is located in Ada, Oklahoma  The Division of Commerce operates 17 facilities which are included in this grant Chickasaw Nation Boundaries Main Objectives  Retrofit Casino Lighting to the most energy efficient option available  Reduce energy consumption and

  13. Energy Efficiency through Lighting Upgrades

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Through Lighting Upgrades The Chickasaw Nation The Chickasaw Nation * The Chickasaw Nation consists of 13.5 counties in southeastern Oklahoma * Tribal enrollment exceeds 35,000 * The Tribal headquarters complex is located in Ada, Oklahoma * The Division of Commerce operates 17 facilities most of which are included in this grant Chickasaw Nation Boundaries Main Objectives * Retrofit Casino Lighting to the most energy efficient option available * Reduce energy consumption and energy bills by 30%

  14. Transmission Workshop

    Broader source: Energy.gov [DOE]

    On November 1-2, 2012, the GTT presented a workshop on grid integration on the transmission system at the DoubleTree Crystal City near Washington, DC.

  15. Transmission Workshop

    Broader source: Energy.gov (indexed) [DOE]

    Grid Tech Team U.S. Department of Energy DOE Grid Tech Team (GTT) The Grid Tech Team ... regional diversity, AC-DC transmission and distribution solutions, ...

  16. Compression Technology and Needs

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    M ohawk Innovative Technology, Inc. HYDROGEN TRANSMISSION AND DISTRIBUTION WORKSHOP NATIONAL RENEWABLE ENERGY LABORATORY GOLDEN, COLORADO COMPRESSION TECHNOLOGY AND NEEDS Hooshang Heshmat, PH.D. February 25 TH , 2014 ® M ohawk Innovative Technology, Inc. * Overall pipeline delivery steps, production to file up * Different types of compressors * Pipeline compressor development steps and accomplishments * Need for Forecourt Compression system * Other major components: drive, sealing, pipeline,

  17. EA-1937: Pacific Direct Intertie Upgrade Project; Lake, Jefferson, Crook, Deschutes, and Wasco Counties, Oregon

    Broader source: Energy.gov [DOE]

    Bonneville Power Administration prepared an EA that assesses the potential environmental impacts of a proposal to replace equipment at BPA’s Celilo converter station and upgrade equipment on the Celilo-Sylmar 500-kilovolt (kV) transmission line from The Dalles, Oregon, to the Nevada-Oregon border.

  18. Concurrent Wind Cooling in Power Transmission Lines

    SciTech Connect (OSTI)

    Jake P Gentle

    2012-08-01

    Idaho National Laboratory and the Idaho Power Company, with collaboration from Idaho State University, have been working on a project to monitor wind and other environmental data parameters along certain electrical transmission corridors. The combination of both real-time historical weather and environmental data is being used to model, validate, and recommend possibilities for dynamic operations of the transmission lines for power and energy carrying capacity. The planned results can also be used to influence decisions about proposed design criteria for or upgrades to certain sections of the transmission lines.

  19. Transmission decisions

    SciTech Connect (OSTI)

    Ellison, C.T. )

    1993-03-01

    As the US FERC moves forward to implement the transmission access provisions of the National Energy Policy Act of 1992, the debate over Regional Transmission Groups continues. Independent energy producers have much at stake in this debate and their reaction to the general RTG concept and to specific RTG proposals will weigh heavily in determining the fate of these proposals.

  20. Catalytic Upgrading of Sugars to Hydrocarbons Technology Pathway |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy of Sugars to Hydrocarbons Technology Pathway Catalytic Upgrading of Sugars to Hydrocarbons Technology Pathway This technology pathway case investigates the catalytic conversion of solubilized carbohydrate streams to hydrocarbon biofuels, utilizing data from recent efforts within the National Advanced Biofuels Consortium (NABC) in collaboration with Virent, Inc. Technical barriers and key research needs that should be pursued for the catalytic conversion of sugars pathway

  1. The Upgraded D0 detector

    SciTech Connect (OSTI)

    Abazov, V.M.; Abbott, B.; Abolins, M.; Acharya, B.S.; Adams, D.L.; Adams, M.; Adams, T.; Agelou, M.; Agram, J.-L.; Ahmed, S.N.; Ahn, S.H.; Ahsan, M.; Alexeev, G.D.; Alkhazov, G.; Alton, A.; Alverson, G.; Alves, G.A.; Anastasoaie, M.; Andeen, T.; Anderson, J.T.; Anderson, S.; ,

    2005-07-01

    The D0 experiment enjoyed a very successful data-collection run at the Fermilab Tevatron collider between 1992 and 1996. Since then, the detector has been upgraded to take advantage of improvements to the Tevatron and to enhance its physics capabilities. We describe the new elements of the detector, including the silicon microstrip tracker, central fiber tracker, solenoidal magnet, preshower detectors, forward muon detector, and forward proton detector. The uranium/liquid-argon calorimeters and central muon detector, remaining from Run I, are discussed briefly. We also present the associated electronics, triggering, and data acquisition systems, along with the design and implementation of software specific to D0.

  2. Jefferson Lab awards upgrade contracts | Jefferson Lab

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    awards upgrade contracts Jefferson Lab awards upgrade contracts Michael Schwartz Inside Business, January 9, 2009 Jefferson Lab announced last week it awarded three contracts worth approximately a combined $5 million as part of its planned $310 million upgrade that will double the power of its electron beam accelerator. The Newport News-based nuclear physics lab, known officially as the U.S. Department of Energy's Thomas Jefferson National Accelerator Facility, received approval from DOE for the

  3. Research Laboratory Experiments with Energy Efficiency Upgrades...

    Office of Environmental Management (EM)

    Center for Applied Energy Research (CAER), the new facility includes energy efficiency upgrades that will reduce energy use and help the building achieve LEED Gold status. ...

  4. Upgrade Boilers with Energy-Efficient Burners

    SciTech Connect (OSTI)

    Not Available

    2006-01-01

    This revised ITP steam tip sheet on upgrading boilers provides how-to advice for improving industrial steam systems using low-cost, proven practices and technologies.

  5. Moving Multifamily Buildings From Assessments to Upgrades

    Broader source: Energy.gov [DOE]

    Better Buildings Neighborhood Program Multifamily Peer Exchange Call: Moving Multifamily Buildings from Assessments to Upgrades, call slides and discussion summary, January 24, 2013.

  6. Staged Upgrades - Homeowner-focused Strategies for Encouraging Energy Upgrades over Time

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Exchange Call: Staged Upgrades-Homeowner-focused Strategies for Encouraging Energy Upgrades over Time August 20, 2015 Call Slides and Discussion Summary Agenda  Call Logistics  Residential Network and Peer Exchange Call Overview  Update on Staged Upgrades Initiative, Steve Dunn, U.S. DOE  Poll on Staged Upgrade Resources  Featured Speakers:  Patrick Hunt, Fiveworx  David Hatchimonji, Boulder County (CO) (Network Member)  Discussion  What are effective "entry

  7. Canada's heavy oil, bitumen upgrading activity is growing

    SciTech Connect (OSTI)

    Corbett, R.A.

    1989-06-26

    Heavy oil and bitumen upgrading activity in Canada is surging with the recent start-up of two new upgraders and with plans to build others. These new upgraders make use of modern hydrocracking technology. Articles in this special report on upgrading focus on Canada's oil and bitumen reserves, the promising technologies that upgrade them, and present details of some of the current upgrader projects. This article covers the following areas: Canada's heavy oils; Upgrading expands; Upgrading technologies; Test results; Regional upgraders; High-quality light product.

  8. Functional performance requirements for seismic network upgrade

    SciTech Connect (OSTI)

    Lee, R.C.

    1991-08-18

    The SRL seismic network, established in 1976, was developed to monitor site and regional seismic activity that may have any potential to impact the safety or reduce containment capability of existing and planned structures and systems at the SRS, report seismic activity that may be relevant to emergency preparedness, including rapid assessments of earthquake location and magnitude, and estimates of potential on-site and off-site damage to facilities and lifelines for mitigation measures. All of these tasks require SRL seismologists to provide rapid analysis of large amounts of seismic data. The current seismic network upgrade, the subject of this Functional Performance Requirements Document, is necessary to improve system reliability and resolution. The upgrade provides equipment for the analysis of the network seismic data and replacement of old out-dated equipment. The digital network upgrade is configured for field station and laboratory digital processing systems. The upgrade consists of the purchase and installation of seismic sensors,, data telemetry digital upgrades, a dedicated Seismic Data Processing (SDP) system (already in procurement stage), and a Seismic Signal Analysis (SSA) system. The field stations and telephone telemetry upgrades include equipment necessary for three remote station upgrades including seismic amplifiers, voltage controlled oscillators, pulse calibrators, weather protection (including lightning protection) systems, seismometers, seismic amplifiers, and miscellaneous other parts. The central receiving and recording station upgrades will include discriminators, helicopter amplifier, omega timing system, strong motion instruments, wide-band velocity sensors, and other miscellaneous equipment.

  9. Project W-420 stack monitoring system upgrades

    SciTech Connect (OSTI)

    CARPENTER, K.E.

    1999-02-25

    This project will execute the design, procurement, construction, startup, and turnover activities for upgrades to the stack monitoring system on selected Tank Waste Remediation System (TWRS) ventilation systems. In this plan, the technical, schedule, and cost baselines are identified, and the roles and responsibilities of project participants are defined for managing the Stack Monitoring System Upgrades, Project W-420.

  10. Better Buildings Neighborhood Program Data Upgrade Projects

    Office of Energy Efficiency and Renewable Energy (EERE)

    Building project data for 75,110 single-family homes upgraded between July 1, 2010, and September 30, 2013, are available. Reported data for some elements have been transformed, and to protect privacy, data for some upgraded homes have been omitted.

  11. Beam intensity upgrade at Fermilab

    SciTech Connect (OSTI)

    Marchionni, A.; /Fermilab

    2006-07-01

    The performance of the Fermilab proton accelerator complex is reviewed. The coming into operation of the NuMI neutrino line and the implementation of slip-stacking to increase the anti-proton production rate has pushed the total beam intensity in the Main Injector up to {approx} 3 x 10{sup 13} protons/pulse. A maximum beam power of 270 kW has been delivered on the NuMI target during the first year of operation. A plan is in place to increase it to 350 kW, in parallel with the operation of the Collider program. As more machines of the Fermilab complex become available with the termination of the Collider operation, a set of upgrades are being planned to reach first 700 kW and then 1.2 MW by reducing the Main Injector cycle time and by implementing proton stacking.

  12. Upgrading of heavy hydrocarbonaceous feeds

    SciTech Connect (OSTI)

    Bhattacharya, A.K.; Storm, D.A.; DeRosa, T.F.

    1995-12-31

    This paper is based on our work in the area of upgrading of heavy hydrocarbonaceous feedstocks. The work involves the development of a method of catalytically hydroconverting a hydrocarbon feed stream containing a substantial quantity of components boiling above about 538{degrees}C to a substantial portion thereof to components boiling below 538{degrees}C. More particularly, an oil-miscible or oil-soluble poly(ether)diol or a derivative thereof and an aromatic additive oil, such as Heavy Cycle Gas oil, are added to a heavy hydrocarbon feed and the mixed stream is contacted at elevated temperatures with a solid catalyst such as a sulfided nickel molybdenum oxide on alumina in the presence of hydrogen under pressure. This method advantageously affords higher conversion to more valuable liquid products containing lower amounts of heteroatoms such as sulfur, substantially eliminates plugging of the hydroconversion reactor, and reduces the amount of insolubles in the total liquid product.

  13. Venezuelan plant completes instrument upgrade

    SciTech Connect (OSTI)

    Martinez, H.; Garcia, C.O.

    1996-07-22

    The Lamarliquido LPG plant, offshore Lake Maracaibo, Venezuela, has received a major upgrade to its control system after 25 years of pneumatic instrumentation. The plant is now operating fully remote from a new central control room with a maximum production of 5,500 b/d, expected to go to 6,600 b/d. The phases of the project included installation and integration of four control systems: distributed control system; fire prevention, detection, and control system; refrigeration process turbocompressor control system; and emergency shutdown system. The paper describes the 1960s vintage instrumentation, the modernization objectives and phases, the distributed control system, the fire control system, gas and fire detection, the turbocompressor system, emergency shutdown system, and plant shutdown logic.

  14. Energy Efficiency Through Lighting Upgrades

    SciTech Connect (OSTI)

    Berst, Kara; Howeth, Maria

    2013-02-26

    Lighting upgrades including neon to LED, incandescent to CFL's and T-12 to T-8 and T-5's were completed through this grant. A total of 16 Chickasaw nation facilities decreased their carbon footprint because of these grant funds. Calculations used were based on comparing the energy usage from the previous year's average and the current energy usage. For facilities without a full year's set of energy bills, the month after installation was compared to the same month from the previous year. Overall, the effect the lighting change-outs had for the gaming centers and casinos far exceeded expectations. For the Madill Gaming Center; both an interior and exterior upgrade was performed which resulted in a 31% decrease in energy consumption. This same reduction was seen in every facility that participated in the grant. Just by simply changing out light bulbs to newer energy efficient equivalents, a decrease in energy usage can be achieved and this was validated by the return on investment seen at Chickasaw Nation facilities. Along with the technical project tasks were awareness sessions presented at Chickasaw Head Starts. The positive message of environmental stewardship was passed down to head start students and passed along to Chickasaw employees. Excitement was created in those that learned what they could do to help reduce their energy bills and many followed through and took the idea home. For a fairy low cost, the general public can also use this technique to lower their energy consumption both at home and at work. Although the idea behind the project was somewhat simple, true benefits have been gained through environmental awareness and reductions of energy costs.

  15. Reactive plasma upgrade of squalane - a heavy oil simulant

    SciTech Connect (OSTI)

    Kong, P.C.; Watkins, A.D.; Detering, B.A.

    1995-07-01

    U.S. light crude oil production has steadily declined over the last two decades. However, huge known heavy oil deposits in the North American continent remain largely untapped. In the past 10 years, the API gravity of crude oils has been decreasing by about 0.17% per year, and the sulfur content has been increasing by about 0.027% per year. As the API gravity of crude oil decreases, there will be an urgent need for economically viable new technologies to ungrade the heavy oil to a high API gravity feed stock for the refineries. The Idaho National Engineering Laboratory is investigating an innovative plasma process to upgrade heavy oil and refinery residuum. This paper will present some of the results and the implications of this technology for heavy oil upgrade and conversion.

  16. Algal Lipid Extraction and Upgrading to Hydrocarbons Technology Pathway

    SciTech Connect (OSTI)

    Davis, Ryan; Biddy, Mary J.; Jones, Susanne B.

    2013-03-31

    In support of the Bioenergy Technologies Office, the National Renewable Energy Laboratory (NREL) and the Pacific Northwest National Laboratory (PNNL) are undertaking studies of biomass conversion technologies to identify barriers and target research toward reducing conversion costs. Process designs and preliminary economic estimates for each of these pathway cases were developed using rigorous modeling tools (Aspen Plus and Chemcad). These analyses incorporated the best information available at the time of development, including data from recent pilot and bench-scale demonstrations, collaborative industrial and academic partners, and published literature and patents. This technology pathway case investigates the cultivation of algal biomass followed by further lipid extraction and upgrading to hydrocarbon biofuels. Technical barriers and key research needs have been assessed in order for the algal lipid extraction and upgrading pathway to be competitive with petroleum-derived gasoline, diesel and jet range hydrocarbon blendstocks.

  17. Shared Space vs. In-Unit Upgrades in Multifamily Buildings |...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Shared Space vs. In-Unit Upgrades in Multifamily Buildings Shared Space vs. In-Unit Upgrades in Multifamily Buildings Better Buildings Neighborhood Program Multifamily Peer...

  18. Shared Space vs. In-Unit Upgrades in Multifamily Buildings |...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Shared Space vs. In-Unit Upgrades in Multifamily Buildings Shared Space vs. In-Unit Upgrades in Multifamily Buildings Better Buildings Neighborhood Program Multifamily Peer ...

  19. ATU Advanced Technology Upgrading Ltd | Open Energy Information

    Open Energy Info (EERE)

    Upgrading) Ltd Place: Israel Product: Focused on development of rechargeable magnesium battery. References: ATU (Advanced Technology Upgrading) Ltd1 This article is a stub. You...

  20. PERSONNEL PROTECTION SYSTEM UPGRADE FOR THE LCLS ELECTRON BEAM...

    Office of Scientific and Technical Information (OSTI)

    PERSONNEL PROTECTION SYSTEM UPGRADE FOR THE LCLS ELECTRON BEAM LINAC Citation Details In-Document Search Title: PERSONNEL PROTECTION SYSTEM UPGRADE FOR THE LCLS ELECTRON BEAM LINAC...

  1. EMPOWERING SANTA BARBARA TO INVEST IN UPGRADES | Department of...

    Energy Savers [EERE]

    EMPOWERING SANTA BARBARA TO INVEST IN UPGRADES In Santa Barbara County, California, the ... Financing: In addition to partnering with the statewide Energy Upgrade California program ...

  2. Capturing Energy Upgrades in the Real Estate Transaction | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Capturing Energy Upgrades in the Real Estate Transaction Capturing Energy Upgrades in the Real Estate Transaction Because green building techniques and products may impact the ...

  3. Spotlight on Austin, Texas: Best Offer Ever Produces 564 Upgrades...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Spotlight on Austin, Texas: Best Offer Ever Produces 564 Upgrades in Record Time Spotlight on Austin, Texas: Best Offer Ever Produces 564 Upgrades in Record Time This Better ...

  4. Spotlight on Austin, Texas: Best Offer Ever Produces Upgrades...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Best Offer Ever Produces Upgrades in Record Time Spotlight on Austin, Texas: Best Offer Ever Produces Upgrades in Record Time Spotlight on Austin, Texas: Best Offer Ever Produces ...

  5. Financing Energy Upgrades for K-12 School Districts

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Financing Energy Upgrades for K-12 School Districts Page 2 Table of Contents ... 6 Chapter 1: Principles of Financing Energy Upgrades for Schools ...

  6. What's Working in Residential Energy Efficiency Upgrade Programs...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    What's Working in Residential Energy Efficiency Upgrade Programs - Promising Approaches and Lessons Learned What's Working in Residential Energy Efficiency Upgrade Programs - ...

  7. Standard Work Specifications for Single-Family Home Energy Upgrades...

    Energy Savers [EERE]

    stakeholders developed the Standard Work Specifications for Single-Family Home Energy Upgrades to define the minimum requirements for high-quality residential energy upgrades. ...

  8. What's Working in Residential Energy Efficiency Upgrade Programs...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    What's Working in Residential Energy Efficiency Upgrade Programs Workshop, May 2011 What's Working in Residential Energy Efficiency Upgrade Programs Workshop, May 2011 On May 20, ...

  9. Find Financing for Energy Efficiency Upgrades | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Efficiency Upgrades Find Financing for Energy Efficiency Upgrades Photo of a block in lower downtown Denver that is part of Living City Block, a DOE Commercial Building ...

  10. Employee-Focused Structure Helps Produce Upgrades for Contractor...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Employee-Focused Structure Helps Produce Upgrades for Contractor Employee-Focused Structure Helps Produce Upgrades for Contractor Photo of a young man sitting on a couch, looking ...

  11. Boiler Upgrades and Decentralizing Steam Systems Save Water and...

    Energy Savers [EERE]

    Boiler Upgrades and Decentralizing Steam Systems Save Water and Energy at Naval Air Station Oceana Boiler Upgrades and Decentralizing Steam Systems Save Water and Energy at Naval ...

  12. THREE VIRGINIA PROGRAMS OVERCOME BARRIERS TO UPGRADES | Department...

    Energy Savers [EERE]

    designed to target communities with limited upgrade capacity and educate homeowners about the benefits of home energy upgrades. The LEAP program employed a paid membership ...

  13. Bioenergy Technologies Office R&D Pathways: Algal Lipid Upgrading...

    Office of Environmental Management (EM)

    Algal Lipid Upgrading Bioenergy Technologies Office R&D Pathways: Algal Lipid Upgrading ... chosen to convert biomass into hydrocarbon fuels by the Bioenergy Technologies Office. ...

  14. Energy Star Building Upgrade Value Calculator | Open Energy Informatio...

    Open Energy Info (EERE)

    Upgrade Value Calculator Jump to: navigation, search Tool Summary LAUNCH TOOL Name: Energy Star Building Upgrade Value Calculator (for Office Properties) AgencyCompany...

  15. Federal Finance Facilities Available for Energy Efficiency Upgrades...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Federal Finance Facilities Available for Energy Efficiency Upgrades and Clean Energy Deployment Federal Finance Facilities Available for Energy Efficiency Upgrades and Clean Energy ...

  16. Transmission Planning

    Broader source: Energy.gov [DOE]

    The Department's research into a variety of tools that will improve advanced system monitoring, visualization, control, operations, and market structure will ultimately modernize the electricity transmission infrastructure to ease congestion, allow for increases in demand, and provide a greater degree of security.

  17. Transmission Services

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Transmission Services BPA Clarifications on the DSO216 1 Document updated on 2242015 at 3:29:25 PM B O N N E V I L L E P O W E R A D M I N I S T R A T I O N BPA Clarifications on...

  18. Syngas Upgrading to Hydrocarbon Fuels Technology Pathway

    SciTech Connect (OSTI)

    Talmadge, M.; Biddy, Mary J.; Dutta, Abhijit; Jones, Susanne B.; Meyer, Pimphan A.

    2013-03-31

    In support of the Bioenergy Technologies Office, the National Renewable Energy Laboratory (NREL) and the Pacific Northwest National Laboratory (PNNL) are undertaking studies of biomass conversion technologies to hydrocarbon fuels to identify barriers and target research toward reducing conversion costs. Process designs and preliminary economic estimates for each of these pathway cases were developed using rigorous modeling tools (Aspen Plus and Chemcad). These analyses incorporated the best information available at the time of development, including data from recent pilot and bench-scale demonstrations, collaborative industrial and academic partners, and published literature and patents. This pathway case investigates the upgrading of biomass derived synthesis gas (‘syngas’) to hydrocarbon biofuels. While this specific discussion focuses on the conversion of syngas via a methanol intermediate to hydrocarbon blendstocks, there are a number of alternative conversion routes for production of hydrocarbons through a wide array of intermediates from syngas. Future work will also consider the variations to this pathway to determine the most economically viable and risk adverse conversion route. Technical barriers and key research needs have been identified that should be pursued for the syngas to hydrocarbon pathway to be competitive with petroleum-derived gasoline, diesel and jet range blendstocks.

  19. HPSS Disk Cache Upgrade Caters to Capacity

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    HPSS Disk Cache Upgrade Caters to Capacity HPSS Disk Cache Upgrade Caters to Capacity Analysis of NERSC Users' Data-Access Habits Reveals Sweet Spot for Short-term Storage October 16, 2015 Contact: Kathy Kincade, +1 510 495 2124, kkincade@lbl.gov HPSS 09 vert NERSC users today are benefiting from a business decision made three years ago by the center's Storage Systems Group (SSG) as they were looking to upgrade the High-Performance Storage System (HPSS) disk cache: rather than focus primarily on

  20. Recovery and upgrading of heavy oil analyzed

    SciTech Connect (OSTI)

    Fornoff, L.L.; Van Driesen, R.P.; Viens, C.H.

    1980-10-13

    An analysis has been made of recovery and upgrading of Venezuelan heavy crudes by integrating steam-drive production data with an upgraded computer processing program. A study used 110 computer cases to analyze a project using Venezuelan heavy crude from the Jobo field with gravity of 9.2 API and 4.1% by wt sulfur for the base case. Sensitivity cases used 12.2 API oil from the Lot 9 field, Monagas state, Venezuela, with sulfur content of 2.3%. Four upgrading methods were studied (deasphalting, delayed coking, flexicoking, and LC-fining), all with favorable resulting economics.

  1. HVDC power transmission technology assessment

    SciTech Connect (OSTI)

    Hauth, R.L.; Tatro, P.J.; Railing, B.D.; Johnson, B.K.; Stewart, J.R.; Fink, J.L.

    1997-04-01

    The purpose of this study was to develop an assessment of the national utility system`s needs for electric transmission during the period 1995-2020 that could be met by future reduced-cost HVDC systems. The assessment was to include an economic evaluation of HVDC as a means for meeting those needs as well as a comparison with competing technologies such as ac transmission with and without Flexible AC Transmission System (FACTS) controllers. The role of force commutated dc converters was to be assumed where appropriate. The assessment begins by identifying the general needs for transmission in the U.S. in the context of a future deregulated power industry. The possible roles for direct current transmission are then postulated in terms of representative scenarios. A few of the scenarios are illustrated with the help of actual U.S. system examples. non-traditional applications as well as traditional applications such as long lines and asynchronous interconnections are discussed. The classical ``break-even distance`` concept for comparing HVDC and ac lines is used to assess the selected scenarios. The impact of reduced-cost converters is reflected in terms of the break-even distance. This report presents a comprehensive review of the functional benefits of HVDC transmission and updated cost data for both ac and dc system components. It also provides some provocative thoughts on how direct current transmission might be applied to better utilize and expand our nation`s increasingly stressed transmission assets.

  2. Wallula Power Project and Wallula - McNary Transmission Line Project Final Environmental Impact Statement

    SciTech Connect (OSTI)

    N /A

    2002-08-16

    Wallula Generation, LLC proposes to construct a 1,300-megawatt (MW) natural gas-fired combined-cycle combustion gas turbine facility (the Wallula Power Project). The project would be located in the northwestern portion of Walla Walla County, Washington, approximately 8 miles south of the City of Pasco, 2 miles north of the unincorporated community of Wallula, and 7 miles southeast of the unincorporated community of Burbank. The purpose of the proposed power project is to provide energy to meet the needs of the Northwest and other interconnected electric transmission areas where electrical energy is needed. Firm transmission of the power generated by the Wallula Power Project would require construction of a new 500-kilovolt (kV) transmission line and construction of a new switchyard near Smiths Harbor. Approximately 5.1 miles of new transmission line from the proposed generation plant to the new switchyard would be completed. An additional 28 miles of new transmission line from the Smiths Harbor Switchyard to the McNary Substation would be constructed adjacent to the existing Lower Monumental-McNary transmission line and upgrades completed to the existing McNary Substation if loads are exceeded on the existing line. Wallula Generation, LLC, would construct and operate the generation plant and associated facilities, including the makeup water supply line. Bonneville would design, construct, and operate the two 500 kV transmission line segments and switchyard. To supply natural gas to the plant site, a 5.9-mile pipeline interconnection would be engineered, constructed, owned, and operated by PG&E Gas Transmission-Northwest (GTN). This EIS evaluates the environmental impacts of the proposed action, which includes the proposed power plant and 33-mile transmission line. It also evaluates an alternative using taller towers and longer spans between towers along part of the transmission line, and the use of an alternative approach for the transmission line where it would

  3. Regional Transmission Projects: Finding Solutions

    SciTech Connect (OSTI)

    The Keystone Center

    2005-06-15

    The Keystone Center convened and facilitated a year-long Dialogue on "Regional Transmission Projects: Finding Solutions" to develop recommendations that will help address the difficult and contentious issues related to expansions of regional electric transmission systems that are needed for reliable and economic transmission of power within and across regions. This effort brought together a cross-section of affected stakeholders and thought leaders to address the problem with the collective wisdom of their experience and interests. Transmission owners sat at the table with consumer advocates and environmental organizations. Representatives from regional transmission organizations exchanged ideas with state and federal regulators. Generation developers explored common interests with public power suppliers. Together, the Dialogue participants developed consensus solutions about how to begin unraveling some of the more intractable issues surrounding identification of need, allocation of costs, and reaching consensus on siting issues that can frustrate the development of regional transmission infrastructure. The recommendations fall into three broad categories: 1. Recommendations on appropriate institutional arrangements and processes for achieving regional consensus on the need for new or expanded transmission infrastructure 2. Recommendations on the process for siting of transmission lines 3. Recommendations on the tools needed to support regional planning, cost allocation, and siting efforts. List of Dialogue participants: List of Dialogue Participants: American Electric Power American Transmission Company American Wind Energy Association California ISO Calpine Corporation Cinergy Edison Electric Institute Environmental Defense Federal Energy Regulatory Commission Great River Energy International Transmission Company ISO-New England Iowa Public Utility Board Kanner & Associates Midwest ISO National Association of Regulatory Utility Commissioners National Association

  4. Advanced Photon Source Upgrade Project - Energy

    ScienceCinema (OSTI)

    Gibson, Murray; Chamberlain, Jeff; Young, Linda

    2013-04-19

    An upgrade to the Advanced Photon Source (announced by DOE - http://go.usa.gov/ivZ) will help scientists better understand complex environments such as in catalytic reactions.

  5. Pacific DC Intertie Upgrade Project Status Update

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    T I O N Pre-Decisional. For Discussion Purposes Only. PDCI Upgrade Project Replace aging Celilo 4 converter terminal with a new 2 converter terminal rated 560kV and 3410A...

  6. RECOVERY ACT: TAPOCO PROJECT: CHEOAH UPGRADE

    SciTech Connect (OSTI)

    Tran, Paul

    2013-02-28

    Under Funding Opportunity Announcement Number: DE-FOA-0000120, Recovery Act: Hydroelectric Facility Modernization, Alcoa Power Generating Inc. (APGI), a fully owned subsidiary of Alcoa Inc., implemented major upgrades at its Cheoah hydroelectric facility near Robbinsville, North Carolina.

  7. Better Buildings Neighborhood Program Data Upgrade Projects ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Building project data for 75,110 single-family homes upgraded between July 1, 2010, and September 30, 2013, are available. Reported data for some elements have been transformed, ...

  8. Advanced Photon Source Upgrade Project - Materials

    ScienceCinema (OSTI)

    Gibbson, Murray;

    2013-04-19

    An upgrade to Advanced Photon Source announced by DOE - http://go.usa.gov/ivZ -- will help scientists break through bottlenecks in materials design in order to develop materials with desirable functions.

  9. Process for upgrading heavy crude oils

    SciTech Connect (OSTI)

    Rankel, L. A.; Shu, P.

    1985-07-23

    A combination process of oxidation/mild coking and in-situ deasphalting provides a process wherein upgraded crude with high levels of demetalation and low solids rejection is produced.

  10. ATLAS upgrade June09_v3

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ATLAS efficiency and intensity upgrade Guy Savard and Robert V. F. Janssens June 12, 2009 The ATLAS facility is on a constant quest to improve and increase the capabilities it...

  11. Idaho Power- Easy Upgrades Efficiency Incentive Program

    Broader source: Energy.gov [DOE]

    Idaho Power offers incentives for its commercial and industrial customers in Idaho and Oregon to upgrade to more efficient equipment in their facilities. The utility provides rebates for lighting...

  12. System and process for upgrading hydrocarbons

    SciTech Connect (OSTI)

    Bingham, Dennis N.; Klingler, Kerry M.; Smith, Joseph D.; Turner, Terry D.; Wilding, Bruce M.

    2015-08-25

    In one embodiment, a system for upgrading a hydrocarbon material may include a black wax upgrade subsystem and a molten salt gasification (MSG) subsystem. The black wax upgrade subsystem and the MSG subsystem may be located within a common pressure boundary, such as within a pressure vessel. Gaseous materials produced by the MSG subsystem may be used in the process carried out within the black wax upgrade subsystem. For example, hydrogen may pass through a gaseous transfer interface to interact with black wax feed material to hydrogenate such material during a cracking process. In one embodiment, the gaseous transfer interface may include one or more openings in a tube or conduit which is carrying the black wax material. A pressure differential may control the flow of hydrogen within the tube or conduit. Related methods are also disclosed.

  13. HPSS Disk Cache Upgrade Caters to Capacity

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    HPSS Disk Cache Upgrade Caters to Capacity Analysis of NERSC Users' Data-Access Habits Reveals Sweet Spot for Short-term Storage October 16, 2015 Contact: Kathy Kincade, +1 510 495 ...

  14. PHOENIX ENERGIZES LIGHT RAIL CORRIDOR WITH UPGRADES

    Broader source: Energy.gov [DOE]

    Designed to promote energy efficiency in buildings in Phoenix, Arizona’s 10-mile-long Light Rail Corridor, Energize Phoenix focused on performing energy upgrades and reducing energy use in...

  15. MMCR Upgrades: Present Status and Future Plans

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    MMCR Upgrades: Present Status and Future Plans K. B. Widener and A. S. Koontz Pacific Northwest National Laboratory Richland, Washington K. P. Moran and K. A. Clark National Oceanic and Atmospheric Administration Environmental Technology Laboratory Boulder, Colorado C. Chander STC xxxxxxxxx M. A. Miller and K. L. Johnson Brookhaven National Laboratory Upton, New York Abstract In September 2003, the Southern Great Plains (SGP) millimeter wave cloud radar (MMCR) was upgraded to a new digital

  16. Why Energy Efficiency Upgrades | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Why Energy Efficiency Upgrades Why Energy Efficiency Upgrades How We Use Energy in Our Buildings Start with an Energy Evaluation Understand How Typical Home Energy Improvements Can Result in a Better Building Tools and Calculators for Homes Homes and commercial buildings consume 40% of the energy used in the United States. Of the $2,000 the average American spends paying for energy annually, $200 to $400 could be going to waste from drafts, air leaks around openings, and outdated heating and

  17. Plains and Eastern Clean Line Transmission Line: Federal Register Notice,

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Volume 80, No. 81 - April 28, 2015 | Department of Energy Federal Register Notice, Volume 80, No. 81 - April 28, 2015 Plains and Eastern Clean Line Transmission Line: Federal Register Notice, Volume 80, No. 81 - April 28, 2015 The Department of Energy (DOE) requests public comment on the first complete application submitted in response to its June 10, 2010 Request for Proposals for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 in the Federal

  18. Jefferson Lab awards upgrade contracts (Inside Business) | Jefferson...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    https:www.jlab.orgnewsreleasesjefferson-lab-awards-upgrade-contracts Submitted: Friday, January 9...

  19. IPNS upgrade: A feasibility study

    SciTech Connect (OSTI)

    1995-04-01

    Many of Argonne National Laboratory`s (ANL`s) scientific staff members were very active in R&D work related to accelerator-based spoliation sources in the 1970s and early 1980s. In 1984, the Seitz/Eastman Panel of the National Academy of Sciences reviewed U.S. materials science research facilities. One of the recommendations of this panel was that the United States build a reactor-based steady-state source, the Advanced Neutron Source (ANS), at Oak Ridge National Laboratory. Subsequently, R&D activities related to the design of an accelerator-based source assumed a lower priority. The resumption of pulsed-source studies in this country started simultaneously with design activities in Europe aimed at the European Spallation Source (ESS). The European Community funded a workshop in September 1991 to define the parameters of the ESS. Participants in this workshop included both accelerator builders and neutron source users. A consortium of European countries has proposed to build a 5-MW pulsed source, and a feasibility study is currently under way. Soon after the birth of the ESS, a small group at ANL set about bringing themselves up to date on pulsed-source information since 1984 and studied the feasibility of upgrading ANL`s Intense Pulsed Neutron Source (IPNS) to 1 MW by means of a rapidly cycling synchrotron that could be housed, along with its support facilities, in existing buildings. In early 1993, the Kohn panel recommended that (1) design and construction of the ANS should be completed according to the proposed project schedule and (2) development of competitive proposals for cost-effective design and construction of a 1-MW pulsed spallation source should be authorized immediately.

  20. Microsoft PowerPoint - ATLAS_upgrade_physics_program

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Guy Savard Argonne National Laboratory and University of Chicago Science with the ATLAS Efficiency and Intensity Upgrade ATLAS Users Meeting August 8-9 2009 2 G. Savard 2009 ATLAS S&T Review May 18-19, 2009 Outline Evolving landscape for low-energy nuclear physics Self-assessment of ATLAS present and near future program Process followed to evaluate near and longer term physics program needs and role in community Option proposed - Physics - Machine - Instrumentation 3 G. Savard 2009 ATLAS

  1. Energy Efficiency Upgrades in Multifamily Housing | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Efficiency Upgrades in Multifamily Housing Energy Efficiency Upgrades in Multifamily Housing Better Buildings Residential Network Case Study: Energy Efficiency Upgrades in Multifamily Housing. This case study addresses multifamily energy upgrade experiences by two members of the Better Buildings Residential Network-Elevate Energy and the International Center for Appropriate and Sustainable Technology (ICAST). Energy Efficiency Upgrades in Multifamily Housing (426.94 KB) More Documents

  2. Jefferson Lab accelerator upgrade completed: Initial operations set to

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    begin while experimental equipment upgrades continue | Jefferson Lab accelerator upgrade completed: Initial operations set to begin while experimental equipment upgrades continue Jefferson Lab accelerator upgrade completed: Initial operations set to begin while experimental equipment upgrades continue areial Aerial of Jefferson Lab NEWPORT NEWS, VA, August 12, 2014 - The Department of Energy's Thomas Jefferson National Accelerator Facility ("Jefferson Lab") has just received formal

  3. Transmission | Department of Energy

    Energy Savers [EERE]

    resources for Tribes on transmission. Transmission 101 Presentation from the National Council on Electricity Policy's Transmissions Technologies workshop. Includes information on...

  4. Transmission Business Line

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Transmission Business Line Non-Federal Financing of Transmission Projects - March 2004 Critical paths on the Northwest transmission grid are congested and the system is near or at...

  5. Storage & Transmission Projects | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Storage & Transmission Projects Storage & Transmission Projects Storage & Transmission Projects Storage & Transmission Projects Storage & Transmission Projects Storage & ...

  6. DOE Transmission Workshop

    Broader source: Energy.gov (indexed) [DOE]

    Order No. 1000 Transmission Ratemaking Enabling New Resources - Demand Response - Variable Generation - Storage 2 Stages of Transmission Planning - Local, ...

  7. Appendix S-51 - Transmission Line Approval - Public Utilities...

    Open Energy Info (EERE)

    from "http:en.openei.orgwindex.php?titleAppendixS-51-TransmissionLineApproval-PublicUtilitiesCommission&oldid800735" Feedback Contact needs updating Image needs...

  8. Level-2 Calorimeter Trigger Upgrade at CDF

    SciTech Connect (OSTI)

    Flanagan, G.U.; /Purdue U.

    2007-04-01

    The CDF Run II Level-2 calorimeter trigger is implemented in hardware and is based on an algorithm used in Run I. This system insured good performance at low luminosity obtained during the Tevatron Run II. However, as the Tevatron instantaneous luminosity increases, the limitations of the current system due to the algorithm start to become clear. In this paper, we will present an upgrade of the Level-2 calorimeter trigger system at CDF. The upgrade is based on the Pulsar board, a general purpose VME board developed at CDF and used for upgrading both the Level-2 tracking and the Level-2 global decision crate. This paper will describe the design, hardware and software implementation, as well as the advantages of this approach over the existing system.

  9. Bitumen and heavy oil upgrading in Canada

    SciTech Connect (OSTI)

    Chrones, J. ); Germain, R.R. )

    1989-01-01

    A review is presented of the heavy oil upgrading industry in Canada. Up to now it has been based on the processing of bitumen extracted from oil sands mining operations at two sites, to produce a residue-free, low sulphur, synthetic crude. Carbon rejection has been the prime process technology with delayed coking being used by Suncor and FLUID COKING at Syncrude. Alternative processes for recovering greater amounts of synthetic crude are examined. These include a variety of hydrogen addition processes and combinations which produce pipelineable materials requiring further processing in downstream refineries with expanded capabilities. The Newgrade Energy Inc. upgrader now under construction in Regina, will use fixed-bed, catalytic, atmospheric-residue, hydrogen processing. Two additional projects, also based on hydrogenation, will use ebullated bed catalyst systems; the expansion of Syncrude, now underway, is using the LC Fining Process whereas the announced Husky Bi-Provincial upgrader is based on H-Oil.

  10. Bitumen and heavy oil upgrading in Canada

    SciTech Connect (OSTI)

    Chrones, J.

    1988-06-01

    A review is presented of the heavy oil upgrading industry in Canada. Up to now it has been based on the processing of bitumen extracted from oil sands mining operations at two sites, to produce a residue-free, low sulfur, synthetic crude. Carbon rejection has been the prime process technology with delayed coking being used by Suncor and FLUID COKING at Syncrude. Alternative processes for recovering greater amounts of synthetic crude are examined. These include a variety of hydrogen addition processes and combinations which produce pipelineable materials requiring further processing in downstream refineries with expanded capabilities. The Newgrade Energy Inc. upgrader, now under construction in Regina, will use fixed-bed, catalytic, atmospheric-residue, hydrogen processing. Two additional products, also based on hydrogenation, will use ebullated bed catalyst systems: the expansion of Syncrude, now underway, is using the LC Fining Process whereas the announced Husky Bi-Provincial upgrader is based on H-Oil.

  11. Hydromechanical transmission

    DOE Patents [OSTI]

    Orshansky, Jr. deceased, Elias; Weseloh, William E.

    1978-01-01

    A power transmission having three planetary assemblies, each having its own carrier and its own planet, sun, and ring gears. A speed-varying module is connected in driving relation to the input shaft and in driving relationship to the three sun gears, all of which are connected together. The speed-varying means may comprise a pair of hydraulic units hydraulically interconnected so that one serves as a pump while the other serves as a motor and vice versa, one of the units having a variable stroke and being connected in driving relation to the input shaft, the other unit, which may have a fixed stroke, being connected in driving relation to the sun gears. The input shaft also drives the carrier of the third planetary assembly. A brake grounds the first carrier in the first range and in reverse and causes drive to be delivered to the output through the first ring gear in a hydrostatic mode. The carrier of the third planetary assembly drives the ring gear of the second planetary assembly, and a first clutching means connects the second carrier with the output in a second range, the brake for grounding the first carrier then being released. A second clutching means enables the third ring gear to drive the output shaft in a third range.

  12. The LANSCE RICE control system upgrade.

    SciTech Connect (OSTI)

    Oothoudt, Michael; Schaller, S.; Bjorklund, E. A.; Burns, M. J.; Carr, G.; Carr, G.; Faucett, John Allen,; Hayden, D. J.; Lusk, M. D.; Merl, R. B.; Potter, J. M.; Reynolds, J. A.; Romero, D. B.; Shelley, F. E.

    2003-01-01

    The LANSCE (Los Alamos Neutron Science Center) control system upgrade program continues with the impending replacement of the RICE (Remote Instrumentation and Control Equipment) subsystem. The RICE subsystem upgrade is a challenge because of its technology (late 1960s), number of channels (>10,000), and unique characteristics (all-modules data takes, timed/flavored data takes). The plan is to replace at least the non-timed data and the command portions of the subsystem with Programmable Logic Controllers (PLCs). We discuss motivations, technological challenges, proof-of-principle, and planning. The boundary condition, as usual, is that we must implement these major changes on a running accelerator.

  13. Energy Upgrade of the Siam Photon Source

    SciTech Connect (OSTI)

    Rugmai, S.; Rujirawat, S.; Hoyes, G. G.; Prawanta, S.; Kwankasem, A.; Siriwattanapitoon, S.; Suradet, N.; Pimol, P.; Junthong, N.; Boonsuya, S.; Janpuang, P.; Prawatsri, P.; Klysubun, P.

    2007-01-19

    The energy upgrade of the storage ring is part of the plans to develop x-ray production capability of the Siam Photon Source. Simulations have been carried out. The bending magnet power supply has been replaced. Energy of the injected 1 GeV beam from the injector is then ramped up 20% in the storage ring. Studies for modification of bending magnet poles have been done to evaluate possibility of further increasing the beam energy to 1.4 GeV in the future. Studies of the energy upgrade plan and details of energy ramping process, together with beam measurements are presented.

  14. LHC luminosity upgrade with large Piwinski angle scheme: a recent look

    SciTech Connect (OSTI)

    Bhat, C.M.; Zimmermann, f.; /CERN

    2011-09-01

    Luminosity upgrade at the LHC collider using longitudinally flat bunches in combination with the large crossing angle (large Piwinski angle scheme) is being studied with renewed interest in recent years. By design, the total beam-beam tune shift at the LHC is less than 0.015 for two interaction points together. But the 2010-11 3.5 TeV collider operation and dedicated studies indicated that the beam-beam tune shift is >0.015 per interaction point. In view of this development we have revisited the requirements for the Large Piwinski Angle scheme at the LHC. In this paper we present a new set of parameters and luminosity calculations for the desired upgrade by investigating: (1) current performance of the LHC injectors, (2) e-cloud issues on nearly flat bunches and (3) realistic beam particle distributions from longitudinal beam dynamics simulations. We also make some remarks on the needed upgrades on the LHC injector accelerators.

  15. Plains and Eastern Clean Line Transmission Line: Comment from Save The

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Ozarks | Department of Energy from Save The Ozarks Plains and Eastern Clean Line Transmission Line: Comment from Save The Ozarks Comment submitted on updated Part 2 application. Comment by Save the Ozarks 07-13-15.pdf (112.79 KB) More Documents & Publications Plains & Eastern Clean Line Transmission Line - Part 2 Application Plains & Eastern Clean Line Project Proposal for New or Upgraded Transmission Line Projects Under Section 1222 of the Energy Policy Act of 2005 Plains and

  16. Design of heavy oil upgrading units

    SciTech Connect (OSTI)

    Farrell, W.D.; Phodes, R.P.; Zeno, D.Y.

    1985-01-01

    Heavy oil upgrading has become an increasingly important aspect of ER and E's research. Due to high costs of experimental catalysts, small catalyst charges are used (20-150cc). Tubular design and tree-stage stirred design are discussed with emphasis on the techniques and equipment used to handle heavy oil. Mechanical design and fluid mechanics are discussed.

  17. T-Farm complex alarm upgrades

    SciTech Connect (OSTI)

    Roberts, J.B.

    1995-01-01

    The alarm and controls associated with the T, TX, and TY farms are located in the 242-T control room. The design data for replacement and upgrades of the alarm panels is in this document. This task was canceled previous to the 90% design review point.

  18. ELECTRONICS UPGRADE OF HIGH RESOLUTION MASS SPECTROMETERS

    SciTech Connect (OSTI)

    Mcintosh, J; Joe Cordaro, J

    2008-03-10

    High resolution mass spectrometers are specialized systems that allow researchers to determine the exact mass of samples to four significant digits by using magnetic and electronic sector mass analyzers. Many of the systems in use today at research laboratories and universities were designed and built more than two decades ago. The manufacturers of these systems have abandoned the support for some of the mass spectrometers and parts to power and control them have become scarce or obsolete. The Savannah River National Laboratory has been involved in the upgrade of the electronics and software for these legacy machines. The Electronics Upgrade of High Resolution Mass Spectrometers consists of assembling high-end commercial instrumentation from reputable manufacturers with a minimal amount of customization to replace the electronics for the older systems. By taking advantage of advances in instrumentation, precise magnet control can be achieved using high resolution current sources and continuous feedback from a high resolution hall-effect probe. The custom equipment include a precision voltage divider/summing amplifier chassis, high voltage power supply chassis and a chassis for controlling the voltage emission for the mass spectrometer source tube. The upgrade package is versatile enough to interface with valve control, vacuum and other instrumentation. Instrument communication is via a combination of Ethernet and traditional IEEE-488 GPIB protocols. The system software upgrades include precision control, feedback and spectral waveform analysis tools.

  19. Testing of FMI's Coal Upgrading Process

    SciTech Connect (OSTI)

    Vijay Sethi

    2009-03-21

    WRI and FMI have collaborated to develop and test a novel coal upgrading technology. Proprietary coal upgrading technology is a fluidized bed-based continuous process which allows high through-puts, reducing the coal processing costs. Processing is carried out under controlled oxidizing conditions at mild enough conditions that compared to other coal upgrading technologies; the produced water is not as difficult to treat. All the energy required for coal drying and upgrading is derived from the coal itself. Under the auspices of the Jointly Sponsored Research Program, Cooperative Agreement DE-FC26-98FT40323, a nominal 400 lbs/hour PDU was constructed and operated. Over the course of this project, several low-rank coals were successfully tested in the PDU. In all cases, a higher Btu, low moisture content, stable product was produced and subsequently analyzed. Stack emissions were monitored and produced water samples were analyzed. Product stability was established by performing moisture readsorption testing. Product pyrophobicity was demonstrated by instrumenting a coal pile.

  20. Biological Pyrolysis Oil Upgrading Presentation for BETO 2015...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Pyrolysis Oil Upgrading WBS 2.3.2.301 2015 DOE BioEnergy Technologies Office (BETO) ... * Tt-J Catalytic Upgrading of Bio-Oil Intermediates to Fuels and Chemicals ...

  1. Fractionation and Catalytic Upgrading of Bio-Oil Presentation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Office (BETO) 2015 Project Peer Review Fractionation and Catalytic Upgrading of Bio-Oil ... Deconstruction of Biomass to Form Bio-Oil Intermediates Tt-I. Catalytic Upgrading of ...

  2. Sandia Lightning Early Warning Network: Digital-based upgrade

    SciTech Connect (OSTI)

    Boyd, G.M.

    1994-05-01

    This report describes the layout and operation of the recently upgraded Sandia Lightning Early Warning Network, which was upgraded from an analog-based to a digital-based telemetry system.

  3. J.R. Simplot: Burner Upgrade Project Improves Performance and...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    J.R. Simplot: Burner Upgrade Project Improves Performance and Saves Energy at a Large Food Processing Plant J.R. Simplot: Burner Upgrade Project Improves Performance and Saves ...

  4. EECBG Success Story: HVAC Upgrade Saving Money, Protecting History...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    HVAC Upgrade Saving Money, Protecting History EECBG Success Story: HVAC Upgrade Saving Money, Protecting History November 2, 2010 - 5:37pm Addthis A new heating and cooling system...

  5. Structural analysis of fuel assembly clads for the Upgraded Transient Reactor Test Facility (TREAT Upgrade)

    SciTech Connect (OSTI)

    Ewing, T.F.; Wu, T.S.

    1986-01-01

    The Upgraded Transient Reactor Test Facility (TREAT Upgrade) is designed to test full-length, pre-irradiated fuel pins of the type used in large LMFBRs under accident conditions, such as severe transient overpower and loss-of-coolant accidents. In TREAT Upgrade, the central core region is to contain new fuel assemblies of higher fissile loadings to maximize the energy deposition to the test fuel. These fuel assemblies must withstand normal peak clad temperatures of 850/sup 0/C for hundreds of test transients. Due to high temperatures and gradients predicted in the clad, creep and plastic strain effects are significant, and the clad structural behavior cannot be analyzed by conventional linear techniques. Instead, the detailed elastic-plastic-creep behavior must be followed along the time-dependent load history. This paper presents details of the structural evaluations of the conceptual TREAT Upgrade fuel assembly clads.

  6. Guidelines for Home Energy Upgrade Professionals: Standard Work Specifications for Multifamily Energy Upgrades (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2011-08-01

    This fact sheet provides essential information about the 2011 publication of the Workforce Guidelines for Multifamily Home Energy Upgrades, including their origin, their development with the help of industry leaders to create the standard work specifications for retrofit work.

  7. Common Industrial Lighting Upgrade Technologies | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Common Industrial Lighting Upgrade Technologies Common Industrial Lighting Upgrade Technologies This tip sheet provides information on two lighting types and upgrade options, fluorescent lighting and high-bay lighting, for the purpose of improving plant-wide lighting performance. Common Industrial Lighting Upgrade Technologies (January 2010) (1002.53 KB) More Documents & Publications Energy Savings Potential of Solid-State Lighting in General Illumination Applications - Report Energy Savings

  8. Energy Upgrade California Drives Demand From Behind the Wheel | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Energy Upgrade California Drives Demand From Behind the Wheel Energy Upgrade California Drives Demand From Behind the Wheel Photo of a trailer with the Energy Upgrade California logo and graphics painted on the side. With a goal of "energy efficiency or bust," the California Center for Sustainable Energy (CCSE) recently completed a statewide tour of its ongoing Energy Upgrade California Roadshow. The mobile exhibit made 11 stops in nine cities across California during November

  9. LOWELL ADDS ENERGY EFFICIENCY TO HISTORIC UPGRADES | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    LOWELL ADDS ENERGY EFFICIENCY TO HISTORIC UPGRADES LOWELL ADDS ENERGY EFFICIENCY TO HISTORIC UPGRADES LOWELL ADDS ENERGY EFFICIENCY TO HISTORIC UPGRADES Faced with the challenge of making buildings in a National Historical Park area more energy efficient, the City of Lowell, Massachusetts, used $5 million in seed funding from the U.S. Department of Energy's Better Buildings Neighborhood Program to launch the BetterBuildings Lowell Energy Upgrade (BLEU) project. From the beginning, the project

  10. Energy Efficiency Upgrades: Benefiting Homeowners and the Environment

    Broader source: Energy.gov [DOE]

    Learn how energy efficiency upgrades are helping a homeowner improve her home's comfort and reduce her impact on the environment.

  11. EMPOWERING SANTA BARBARA TO INVEST IN UPGRADES | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EMPOWERING SANTA BARBARA TO INVEST IN UPGRADES EMPOWERING SANTA BARBARA TO INVEST IN UPGRADES EMPOWERING SANTA BARBARA TO INVEST IN UPGRADES In Santa Barbara County, California, the weather is so temperate that even the least energy-efficient homes can still feel comfortable year-round. To help residents see that energy upgrades can have benefits even in their climate, Santa Barbara County formed the Elective Municipal Programs to Optimize Water, Energy and Renewables (emPower) program.

  12. Conversion Technologies for Advanced Biofuels - Bio-Oil Upgrading |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Oil Upgrading Conversion Technologies for Advanced Biofuels - Bio-Oil Upgrading PNNL report-out at the CTAB webinar on Bio-Oil Upgrading. ctab_webinar_bio_oils_upgrading.pdf (361.56 KB) More Documents & Publications Conversion Technologies for Advanced Biofuels - Bio-Oil Production Thermochemical Conversion Proceeses to Aviation Fuels 2013 Peer Review Presentations-Bio-oil

  13. Quality Control, Standardization of Upgrades, and Workforce Expectations

    Office of Energy Efficiency and Renewable Energy (EERE)

    Better Buildings Residential Network Workforce Peer Exchange Call Series: Quality Control, Standardization of Upgrades, and Workforce Expectations, March 27, 2014.

  14. CHICAGO HOUSE PARTIES SHOW WAYS TO UPGRADE | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    CHICAGO HOUSE PARTIES SHOW WAYS TO UPGRADE CHICAGO HOUSE PARTIES SHOW WAYS TO UPGRADE CHICAGO HOUSE PARTIES SHOW WAYS TO UPGRADE The Chicago Metropolitan Agency for Planning (CMAP) and its partners created Energy Impact Illinois (EI2) to promote home energy upgrades in single-family homes, multifamily housing units, and commercial buildings to help the region meet its 2008 Chicago Climate Action Plan and longer term GO TO 2040 Strategic Plan. EI2 enlisted the help of the Elevate Energy, a

  15. Capitalizing on Multibenefits of Energy Upgrades at Multifamily Housing

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    (301) | Department of Energy Capitalizing on Multibenefits of Energy Upgrades at Multifamily Housing (301) Capitalizing on Multibenefits of Energy Upgrades at Multifamily Housing (301) Buildings Residential Network Peer Exchange Call Series: Capitalizing on Multibenefits of Energy Upgrades at Multifamily Housing (301), call slides and discussion summary. Call Slides and Discussion Summary (3.36 MB) More Documents & Publications Staged Upgrades as a Strategy for Residential Energy

  16. Integrating Wind into Transmission Planning: The Rocky Mountain Area Transmission Study (RMATS): Preprint

    SciTech Connect (OSTI)

    Hamilton, R.; Lehr, R.; Olsen, D.; Nielsen, J.; Acker, T.; Milligan, M.; Geller, H.

    2004-03-01

    Plans to expand the western grid are now underway. Bringing power from low-cost remote resources--including wind--to load centers could reduce costs for all consumers. But many paths appear to be already congested. Locational marginal price-based modeling is designed to identify the most cost-effective paths to be upgraded. The ranking of such paths is intended as the start of a process of political and regulatory approvals that are expected to result in the eventual construction of new and upgraded lines. This paper reviews the necessary data and analytical tasks to accurately represent wind in such modeling, and addresses some policy and regulatory issues that can help with wind integration into the grid. Providing wind fair access to the grid also (and more immediately) depends on tariff and regulatory changes. Expansion of the Rocky Mountain Area Transmission Study (RMATS) study scope to address operational issues supports the development of transmission solutions that enable wind to connect and deliver power in the next few years--much sooner than upgrades can be completed.

  17. The JLAB 12 GeV Energy Upgrade of CEBAF

    SciTech Connect (OSTI)

    Harwood, Leigh H.

    2013-12-01

    This presentation should describe the progress of the 12GeV Upgrade of CEBAF at Jefferson Lab. The status of the upgrade should be presented as well as details on the construction, procurement, installation and commissioning of the magnet and SRF components of the upgrade.

  18. Catalytic Upgrading Sugars To Hydrocarbons | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Sugars To Hydrocarbons Catalytic Upgrading Sugars To Hydrocarbons PDF on catalytic bioenergy process Catalytic Upgrading Sugars To Hydrocarbons (477.56 KB) More Documents & Publications Biological Conversion of Sugars To Hydrocarbons Technology Pathway Selection Effort Catalytic Upgrading of Sugars to Hydrocarbons Technology Pathway

  19. RAPID/BulkTransmission/Transmission Siting & Interconnection...

    Open Energy Info (EERE)

    federal review). Bulk Transmission Transmission Siting & Interconnection in New Mexico New Mexico Statutes (N.M.S.) 62-9-1, 62-9-3(B), and 62-9-3.2 No Location Permit may be...

  20. THERMAL UPGRADING OF 9977 RADIOACTIVE MATERIAL (RAM) TYPE B PACKAGE

    SciTech Connect (OSTI)

    Gupta, N.; Abramczyk, G.

    2012-03-26

    The 9977 package is a radioactive material package that was originally certified to ship Heat Sources and RTG contents up to 19 watts and it is now being reviewed to significantly expand its contents in support of additional DOE missions. Thermal upgrading will be accomplished by employing stacked 3013 containers, a 3013 aluminum spacer and an external aluminum sleeve for enhanced heat transfer. The 7th Addendum to the original 9977 package Safety Basis Report describing these modifications is under review for the DOE certification. The analyses described in this paper show that this well-designed and conservatively analyzed package can be upgraded to carry contents with decay heat up to 38 watts with some simple design modifications. The Model 9977 package has been designed as a replacement for the Department of Transportation (DOT) Fissile Specification 6M package. The 9977 package is a very versatile Type B package which is certified to transport and store a wide spectrum of radioactive materials. The package was analyzed quite conservatively to increase its usefulness and store different payload configurations. Its versatility is evident from several daughter packages such as the 9978 and H1700, and several addendums where the payloads have been modified to suit the Shipper's needs without additional testing.

  1. NREL: Transmission Grid Integration - Transmission Planning and...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Printable Version Transmission Grid Integration Home Issues Projects Western Wind & Solar ... Electricity Market Operations Energy Imbalance Markets FESTIV Model Active ...

  2. Transmission Capacity Forum

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Email Address: Name: Organization Entity Type: Select the best fit for your role... Energy Trader Transmission Provider Employee Transmission Purchaser Energy Scheduler...

  3. Survey of Transmission Cost Allocation Methodologies for Regional Transmission Organizations

    SciTech Connect (OSTI)

    Fink, S.; Porter, K.; Mudd, C.; Rogers, J.

    2011-02-01

    The report presents transmission cost allocation methodologies for reliability transmission projects, generation interconnection, and economic transmission projects for all Regional Transmission Organizations.

  4. A poloidal section neutron camera for MAST upgrade

    SciTech Connect (OSTI)

    Sangaroon, S.; Weiszflog, M.; Cecconello, M.; Conroy, S.; Ericsson, G.; Wodniak, I.; Keeling, D.; Turnyanskiy, M. [EURATOM Collaboration: MAST Team

    2014-08-21

    The Mega Ampere Spherical Tokamak Upgrade (MAST Upgrade) is intended as a demonstration of the physics viability of the Spherical Tokamak (ST) concept and as a platform for contributing to ITER/DEMO physics. Concerning physics exploitation, MAST Upgrade plasma scenarios can contribute to the ITER Tokamak physics particularly in the field of fast particle behavior and current drive studies. At present, MAST is equipped with a prototype neutron camera (NC). On the basis of the experience and results from previous experimental campaigns using the NC, the conceptual design of a neutron camera upgrade (NC Upgrade) is being developed. As part of the MAST Upgrade, the NC Upgrade is considered a high priority diagnostic since it would allow studies in the field of fast ions and current drive with good temporal and spatial resolution. In this paper, we explore an optional design with the camera array viewing the poloidal section of the plasma from different directions.

  5. An Upgrade for the Advanced Light Source

    SciTech Connect (OSTI)

    Chemla, Daniel S.; Feinberg, Benedict; Hussain, Zahid; Kirz, Janos; Krebs, Gary F.; Padmore, Howard A.; Robin, David S.; Robinson, Arthur L.; Smith, Neville V.

    2004-09-01

    One of the first third-generation synchrotron light sources, the ALS, has been operating for almost a decade at Berkeley Lab, where experimenters have been exploiting its high brightness for forefront science. However, accelerator and insertion-device technology have significantly changed since the ALS was designed. As a result, the performance of the ALS is in danger of being eclipsed by that of newer, more advanced sources. The ALS upgrade that we are planning includes full-energy, top-off injection with higher storage-ring current and the replacement of five first-generation insertion devices with nine state-of-the art insertion devices and four new application-specific beamlines now being identified in a strategic planning process. The upgrade will help keep the ALS at the forefront of soft x-ray synchrotron light sources for the next two decades.

  6. Chapter 1: ASDEX Upgrade - Introduction and Overview

    SciTech Connect (OSTI)

    Herrmann, Albrecht; Gruber, Otto

    2003-11-15

    This special issue of Fusion Science and Technology is a comprehensive review of the main physical and technological results achieved with the Axial Symmetric Divertor EXperiment (ASDEX) Upgrade located at the Max-Planck-Institut fuer Plasmaphysik in Garching, Germany. It includes special chapters presenting details of machine operation and control as well as results from the main topics of scientific investigations. This introductory chapter gives a survey of the aims of ASDEX Upgrade and the evolution of the scientific goals, which were accompanied by technical modifications during the more than 10 yr of operation. It presents a short overview on hardware modifications and on the scientific program. This chapter is also a summary of major scientific results, which are then described in more detail in the following chapters.

  7. Process for upgrading a heavy viscous hydrocarbon

    SciTech Connect (OSTI)

    Lutz, I.H.

    1984-06-12

    A process for upgrading a heavy viscous hydrocarbon, for example, rendering a heavy viscous crude pipelinable, includes visbreaking, distillation and solvent extraction steps. A heavy viscous hydrocarbon is fed through the visbreaker which forms a feed to the distillation step. A heavier fraction from distillation is fed to a solvent extraction unit which produces a fraction which contains resin. At least a portion of the resin containing fraction separated in the solvent extraction unit is recycled and combined with the feed which is to be subjected to visbreaking so that the total yield of products, residual and gas-free, is increased. The recycled resin reduces the tendency of the asphaltenes to separate from the oil and thereby reduces the tendency to lay down coke in the visbreaker; this allows higher conversion to upgraded liquid products.

  8. The Use of TaBoRR as a Heavy Oil Upgrader

    SciTech Connect (OSTI)

    Lee Brecher; Charles Mones

    2009-02-05

    Preliminary testing has shown that Western Research Institute's (WRI) Tank Bottom Recovery and Remediation (TaBoRR{reg_sign}) technology shows promise for heavy oil upgrading. Approximately 70 to 75 wt% of a Canadian Cold Lake bitumen feed was converted to a partially upgraded overhead product that could be transported directly by pipeline or blended with the parent bitumen to produce transportable crude. TaBoRR{reg_sign} was originally developed to remediate tank bottom wastes by producing a distillate product and solid waste. TaBoRR{reg_sign}'s processing steps include breaking a water-oil emulsion, recovering a light hydrocarbon fraction by distillation in a stripper unit, and pyrolyzing the residua reducing it to additional overhead and a benign coke for disposal. Cold Lake bitumen was tested in WRI's bench-scale equipment to evaluate the potential use of TaBoRR{reg_sign} technology for heavy oil upgrading to produce a stable, partially (or fully) upgraded product that will allow diluent-reduced or diluent-free transportation of bitumen or ultra-heavy crudes to market. Runs were conducted at temperatures of low, intermediate and high severity in the stripper to produce stripper overhead and bottoms. The bottoms from each of these runs were processed further in a 6-inch screw pyrolyzer to produce pyrolyzer overhead for blending with the corresponding stripper overheads. Proceeding in this fashion yielded three partially upgraded crudes. The products from TaBoRR{reg_sign} processing, the parent bitumen, and bitumen blends were subjected to stability and compatibility testing at the National Centre for Upgrading Technology (NCUT). Chemical analyses of the overhead product blends have met pipeline specifications for viscosity and density; however the bromine number does not, which might indicate the need for mild hydrotreating. Storage stability tests showed the blends to be stable. The blends were also soluble and compatible with most other Alberta crudes.

  9. CORRECTION SYSTEMS UPGRADE FOR THE SNS RING.

    SciTech Connect (OSTI)

    PAPAPHILIPPOU,Y.; GARDNER,C.J.; LEE,Y.Y.; WEI,J.

    2001-06-18

    In view of the changes in the design of the SNS ring from the original FODO lattice [l] to the 220m hybrid lattice [2] and finally 1.3GeV compatible 248m ring [3], complementary studies have been undertaken, in order to upgrade its correction packages. We review the evolution of the correction systems and present the accelerator physics studies for the adopted schemes and powering plan.

  10. 12 GeV Upgrade | Jefferson Lab

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    12 GeV Upgrade Physicists at Jefferson Lab are trying to find answers to some of nature's most perplexing questions about the universe by exploring the nucleus of the atom. Their goal is to answer such questions as: "What is the universe made of?" and "What holds everyday matter together?" In their search for answers, physicists smash electrons into atoms using Jefferson Lab's Continuous Electron Beam Accelerator Facility. CEBAF provides physicists with an unprecedented

  11. Instrumentation upgrades for the Macromolecular Crystallography beamlines

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    of the Swiss Light Source | Stanford Synchrotron Radiation Lightsource Instrumentation upgrades for the Macromolecular Crystallography beamlines of the Swiss Light Source Monday, October 29, 2012 - 2:00am SSRL, Bldg. 137, Rm. 322 Martin Fuchs, MX Group, Swiss Light Source; Paul Scherrer Institute (Villigen, Switzerland) A new unified diffractometer - the D3 - has been developed for the three MX beamlines. The first of the instruments is in general user operation at beamline X10SA since April

  12. Sandia Energy - Transmission Grid Integration

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Transmission Grid Integration Home Stationary Power Energy Conversion Efficiency Solar Energy Photovoltaics Grid Integration Transmission Grid Integration Transmission Grid...

  13. Research and development of RHIC injection kicker upgrade with nano second FID pulse generator

    SciTech Connect (OSTI)

    Zhang W.; Sandberg, J.; Hahn, H.; Fischer, W.; Liaw, C.J.; Pai, C.; Tuozzolo, J.

    2012-05-20

    Our recent effort to test a 50 kV, 1 kA, 50 ns pulse width, 10 ns pulse rise time FID pulse generator with a 250 ft transmission cable, resistive load, and existing RHIC injection kicker magnet has produced unparalleled results. This is the very first attempt to drive a high strength fast kicker magnet with a nano second high pulsed power (50 MVA) generator for large accelerator and colliders. The technology is impressive. We report here the result and future plan of RHIC Injection kicker upgrade.

  14. Current Lead Design for the Accelerator Project for Upgrade of LHC

    SciTech Connect (OSTI)

    Brandt, Jeffrey S.; Cheban, Sergey; Feher, Sandor; Kaducak, Marc; Nobrega, Fred; Peterson, Tom

    2010-01-01

    The Accelerator Project for Upgrade of LHC (APUL) is a U.S. project participating in and contributing to CERN's Large Hadron Collider (LHC) upgrade program. In collaboration with Brookhaven National Laboratory, Fermilab is developing sub-systems for an upgrade of the LHC final focus magnet systems. A concept of main and auxiliary helium flow was developed that allows the superconductor to remain cold while the lead body warms up to prevent upper section frosting. The auxiliary flow will subsequently cool the thermal shields of the feed box and the transmission line cryostats. A thermal analysis of the current lead central heat exchange section was performed using analytic and FEA techniques. A method of remote soldering was developed that allows the current leads to be field replaceable. The remote solder joint was designed to be made without flux or additional solder, and able to be remade up to ten full cycles. A method of upper section attachment was developed that allows high pressure sealing of the helium volume. Test fixtures for both remote soldering and upper section attachment for the 13 kA lead were produced. The cooling concept, thermal analyses, and test results from both remote soldering and upper section attachment fixtures are presented.

  15. NSTX-U Control System Upgrades

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Erickson, K. G.; Gates, D. A.; Gerhardt, S. P.; Lawson, J. E.; Mozulay, R.; Sichta, P.; Tchilinguirian, G. J.

    2014-06-01

    The National Spherical Tokamak Experiment (NSTX) is undergoing a wealth of upgrades (NSTX-U). These upgrades, especially including an elongated pulse length, require broad changes to the control system that has served NSTX well. A new fiber serial Front Panel Data Port input and output (I/O) stream will supersede the aging copper parallel version. Driver support for the new I/O and cyber security concerns require updating the operating system from Redhat Enterprise Linux (RHEL) v4 to RedHawk (based on RHEL) v6. While the basic control system continues to use the General Atomics Plasma Control System (GA PCS), the effort to forwardmore » port the entire software package to run under 64-bit Linux instead of 32-bit Linux included PCS modifications subsequently shared with GA and other PCS users. Software updates focused on three key areas: (1) code modernization through coding standards (C99/C11), (2) code portability and maintainability through use of the GA PCS code generator, and (3) support of 64-bit platforms. Central to the control system upgrade is the use of a complete real time (RT) Linux platform provided by Concurrent Computer Corporation, consisting of a computer (iHawk), an operating system and drivers (RedHawk), and RT tools (NightStar). Strong vendor support coupled with an extensive RT toolset influenced this decision. The new real-time Linux platform, I/O, and software engineering will foster enhanced capability and performance for NSTX-U plasma control.« less

  16. Value-based reliability transmission planning

    SciTech Connect (OSTI)

    Dalton, J.G. III; Garrison, D.L.; Fallon, C.M.

    1996-08-01

    This paper presents a new value-based reliability planning (VBRP) process proposed for planning Duke Power Company`s (DPC) regional transmission system. All transmission served customers are fed from DPC`s regional transmission system which consists of a 44-kV predominantly radial system and a 100-kV predominantly non-radial system. In the past, any single contingency that could occur during system peak conditions and cause a thermal overload required the overloaded facility to be upgraded, regardless of the costs or the likelihood of the overload occurring. The new VBRP process is based on transmission system reliability evaluation and includes the following important elements: (1) a ten-year historical data base describing the probabilities of forced outages for lines and transformers; (2) a five-year average load duration curve describing the probability of an overload should a contingency occur; (3) a customer outage cost data base; (4) and probabilistic techniques. The new process attempts to balance the costs of improving service reliability with the benefits or value that these improvements bring to these customers. The objective is to provide the customers their required level of reliability while minimizing the Total Cost of their electric service.

  17. The value of steam turbine upgrades

    SciTech Connect (OSTI)

    Potter, K.; Olear, D.

    2005-11-01

    Technological advances in mechanical and aerodynamic design of the turbine steam path are resulting in higher reliability and efficiency. A recent study conducted on a 390 MW pulverized coal-fired unit revealed just how much these new technological advancements can improve efficiency and output. The empirical study showed that the turbine upgrade raised high pressure (HP) turbine efficiency by 5%, intermediate pressure (IP) turbine efficiency by 4%, and low pressure (LP) turbine efficiency by 2.5%. In addition, the unit's highest achievable gross generation increased from 360 MW to 371 MW. 3 figs.

  18. Process for upgrading heavy hydrocarbonaceous oils

    SciTech Connect (OSTI)

    Fisher, I.P.; Souhrada, F.; Woods, H.J.

    1981-10-13

    An integrated upgrading process is disclosed which can be used to lower the specific gravity, viscosity and boiling range of heavy, viscous hydrocarbonaceous oil . The process consists of fractionally distilling the oil, treating its residuum with a hydrogen donor material under hydrocracking conditions, fractionally distilling the effluent from the hydrocracking zone and rehydrogenating that portion boiling from about 180/sup 0/ C to 350/sup 0/ C for recycling to the hydrocracking zone. The liquid portion of the oil not recycled can be recombined into a reconstituted crude suitable for transporting by normal crude pipelines.

  19. WISCONSIN CITIES WORK TOGETHER TO ADVANCE UPGRADES | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    WISCONSIN CITIES WORK TOGETHER TO ADVANCE UPGRADES WISCONSIN CITIES WORK TOGETHER TO ADVANCE UPGRADES WISCONSIN CITIES WORK TOGETHER TO ADVANCE UPGRADES When Milwaukee, Madison, and Racine, Wisconsin, decided to work together, the result was three programs that benefited from shared ideas and individual community support. With $20 million in seed funding from the U.S. Department of Energy's Better Buildings Neighborhood Program, the Wisconsin Energy Conservation Corporation (WECC) created

  20. Security Upgrades Completed at Three Russian Nuclear Facilities | National

    National Nuclear Security Administration (NNSA)

    Nuclear Security Administration | (NNSA) Security Upgrades Completed at Three Russian Nuclear Facilities December 10, 2004 NNSA continues work to keep nuclear material out of the hands of terrorists RUSSIA -- The National Nuclear Security Administration (NNSA) commemorated ten years of work securing nuclear and radiological material in Russia and the former Soviet Union by completing security upgrades at two Russian nuclear facilities this week. Upgrades at a third facility were completed in

  1. Nuclear Materials Safeguards and Security Upgrade Project Completed Under

    National Nuclear Security Administration (NNSA)

    Budget | National Nuclear Security Administration | (NNSA) Nuclear Materials Safeguards and Security Upgrade Project Completed Under Budget April 03, 2014 WASHINGTON, D.C. - The National Nuclear Security Administration's (NNSA) Nuclear Materials Safeguards and Security Upgrade Project (NMSSUP) was recently completed approximately $1 million under its original budget of $245 million. NMSSUP upgrades security at Los Alamos National Laboratory's (LANL) Technical Area-55, a facility that houses

  2. Syngas Upgrading to Hydrocarbon Fuels Technology Pathway | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Syngas Upgrading to Hydrocarbon Fuels Technology Pathway Syngas Upgrading to Hydrocarbon Fuels Technology Pathway This technology pathway case investigates the upgrading of woody biomass derived synthesis gas (syngas) to hydrocarbon biofuels. While this specific discussion focuses on the conversion of syngas via a methanol intermediate to hydrocarbon blendstocks, there are a number of alternative conversion routes for production of hydrocarbons through a wide array of intermediates

  3. THREE VIRGINIA PROGRAMS OVERCOME BARRIERS TO UPGRADES | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy THREE VIRGINIA PROGRAMS OVERCOME BARRIERS TO UPGRADES THREE VIRGINIA PROGRAMS OVERCOME BARRIERS TO UPGRADES THREE VIRGINIA PROGRAMS OVERCOME BARRIERS TO UPGRADES Using $2.9 million in seed funding from the U.S. Department of Energy's (DOE's) Better Buildings Neighborhood Program, the Virginia Department of Mines, Minerals, and Energy (VDMME) set out to overcome marketplace barriers and catalyze home energy improvements in different regions of the state. Three regional energy alliances

  4. Methods and apparatuses for preparing upgraded pyrolysis oil

    DOE Patents [OSTI]

    Brandvold, Timothy A; Baird, Lance Awender; Frey, Stanley Joseph

    2013-10-01

    Methods and apparatuses for preparing upgraded pyrolysis oil are provided herein. In an embodiment, a method of preparing upgraded pyrolysis oil includes providing a biomass-derived pyrolysis oil stream having an original oxygen content. The biomass-derived pyrolysis oil stream is hydrodeoxygenated under catalysis in the presence of hydrogen to form a hydrodeoxygenated pyrolysis oil stream comprising a cyclic paraffin component. At least a portion of the hydrodeoxygenated pyrolysis oil stream is dehydrogenated under catalysis to form the upgraded pyrolysis oil.

  5. BEST OFFER EVER ACCELERATED TEXAS UPGRADES | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    BEST OFFER EVER ACCELERATED TEXAS UPGRADES BEST OFFER EVER ACCELERATED TEXAS UPGRADES BEST OFFER EVER ACCELERATED TEXAS UPGRADES In Austin, Texas, air conditioners hum constantly from April to October, which creates a powerful opportunity to eliminate air leaks in homes and other buildings. That's also why contractors often find themselves with more than enough work during some months of the year but are quite slow in others, often resulting in layoffs. To tackle this challenge, municipal

  6. Bedford Energizes Other Communities to Upgrade | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Bedford Energizes Other Communities to Upgrade Bedford Energizes Other Communities to Upgrade Bedford Energizes Other Communities to Upgrade Spurred by the creation of a Climate Action Plan to reduce the town of Bedford, New York's greenhouse gas emissions by 20% by 2020, Energize New York used combined funding of $2.52 million from the U.S. Department of Energy's Better Buildings Neighborhood Program and the New York State Energy Research and Development Authority (NYSERDA) to pilot a

  7. MICHIGAN PUTS COMMERCIAL UPGRADES ON THE MENU | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    MICHIGAN PUTS COMMERCIAL UPGRADES ON THE MENU MICHIGAN PUTS COMMERCIAL UPGRADES ON THE MENU MICHIGAN PUTS COMMERCIAL UPGRADES ON THE MENU Homeowners weren't the only ones affected by the economic downturn in Michigan. Because businesses were also looking for ways to reduce operating costs and save resources, the Michigan State Energy Program (SEP) worked with a nonprofit organization, Michigan Saves, to create the Michigan Saves Business Energy Financing (BEF) program. Using $5 million in seed

  8. Addressing Barriers to Upgrade Projects at Affordable Multifamily

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Properties (201) | Department of Energy Addressing Barriers to Upgrade Projects at Affordable Multifamily Properties (201) Addressing Barriers to Upgrade Projects at Affordable Multifamily Properties (201) Better Buildings Residential Network Peer Exchange Call Series: Addressing Barriers to Upgrade Projects at Affordable Multifamily Properties (201), call slides and discussion summary. Call Slides and Discussion Summary (1.83 MB) More Documents & Publications Incorporating Energy

  9. Local firms benefit from Jefferson Lab upgrade | Jefferson Lab

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Local firms benefit from Jefferson Lab upgrade Local firms benefit from Jefferson Lab upgrade Michael Schwartz, Staff Writer Inside Business, February 16, 2009 Just two months into the year, the $310 million upgrade at the U.S. Department of Energy's Thomas Jefferson National Accelerator Facility is already paying off for local companies. A $14.1 million contract awarded earlier this month to S.B. Ballard made the Virginia Beach-based construction company the second local firm to reap the

  10. Home Improvement Catalyst: Sequencing Upgrades and Engaging Homeowners Over

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Time (201) | Department of Energy Sequencing Upgrades and Engaging Homeowners Over Time (201) Home Improvement Catalyst: Sequencing Upgrades and Engaging Homeowners Over Time (201) Better Buildings Residential Network Peer Exchange Call Series: Home Improvement Catalyst: Sequencing Upgrades and Engaging Homeowners Over Time (201), March 24, 2016, call slides and discussion summary. Call Slides and Discussion Summary (5.69 MB) More Documents & Publications Five and Dime: Revisiting

  11. REPOWERING BAINBRIDGE AND BREMERTON WITH UPGRADES | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    REPOWERING BAINBRIDGE AND BREMERTON WITH UPGRADES REPOWERING BAINBRIDGE AND BREMERTON WITH UPGRADES REPOWERING BAINBRIDGE AND BREMERTON WITH UPGRADES Faced with a utility system capacity challenge that would have required a new substation and additional power lines across their community, the environmentally conscious residents of Bainbridge Island, Washington, responded with a plan to show that the island's existing infrastructure could support energy demand-if residents reduced energy use.

  12. RESORT COMMUNITIES GET SMART WITH UPGRADES | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    RESORT COMMUNITIES GET SMART WITH UPGRADES RESORT COMMUNITIES GET SMART WITH UPGRADES RESORT COMMUNITIES GET SMART WITH UPGRADES Colorado's popular ski resorts attract a diverse population of vacationers and seasonal workers. Half of the homes in these resort communities are claimed as second homes, occupied only 25% of the year, and the rest are a mix of middle-income and multifamily rental properties. When it comes to reaching this diverse array of residences with an energy efficiency program,

  13. Generating Demand for Multifamily Building Upgrades | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Demand for Multifamily Building Upgrades Generating Demand for Multifamily Building Upgrades Better Buildings Residential Network Peer Exchange Call Series: Generating Demand for Multifamily Building Upgrades, call slides and discussion summary, May 14, 2015. Call Slides and Discussion Summary (1.2 MB) More Documents & Publications Strategies to Address Split Incentives in Multifamily Buildings Outreach to Multifamily Landlords and Tenants Trends in Multifamily Programs: What's Working and

  14. Federal Finance Facilities Available for Energy Efficiency Upgrades and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Clean Energy Deployment | Department of Energy Federal Finance Facilities Available for Energy Efficiency Upgrades and Clean Energy Deployment Federal Finance Facilities Available for Energy Efficiency Upgrades and Clean Energy Deployment The Federal Finance Facilities Available for Energy Efficiency Upgrades and Clean Energy Deployment resource guide lists the various federal financing programs for which energy efficiency and clean energy qualify - meant to make it easier for state, local

  15. EECBG Success Story: County Partners with Siemens on Energy Upgrades |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy County Partners with Siemens on Energy Upgrades EECBG Success Story: County Partners with Siemens on Energy Upgrades July 9, 2010 - 11:11am Addthis McHenry County, Illinois was awarded with an Energy Efficiency and Conservation Block Grant (EECBG) to develop projects including a solar photovoltaic energy system, LED lighting at municipal buildings, boiler upgrades, energy efficiency retrofits at the county government center, and a public education energy savings

  16. Flexibility in heavy oil upgrading with unicracking/HDS technology

    SciTech Connect (OSTI)

    Hennig, H.; Baron, K.; Moorhead, E.L.; Smith, M.

    1984-03-01

    With petroleum reserves becoming heavier and the demand for bottom of the barrel products greatly reduced, refiners are increasing their capabilities to upgrade heavy oil. Many heavy oil upgrading options are available and the best strategy for each refiner is not obvious. The best approach will depend on the specific circumstances and goals of the refiner. This presentation discusses the relative merits of several heavy oil upgrading options utilizing the Unicracking/HDS process.

  17. Characteristics and upgrading technologies of Chinese heavy oil

    SciTech Connect (OSTI)

    Ghuang Yang; Jinsen Gao

    1995-12-31

    The characteristics of typical Chinese heavy oils produced in the eastern, northwestern, and northeastern parts of China are presented to show the uniqueness of heavy oils on the Chinese mainland. Henceforth, upgrading technologies of Chinese domestic heavy crudes are discussed along this line. Two main categories of upgrading technologies, decarbonization and hydrogenation, as realized or being developed in this country are presented. It is concluded that most Chinese heavy crudes are adaptable to conventional upgrading processes.

  18. DOE Campaign Proves Commercial Lighting Upgrades Drive Savings | Department

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Energy Campaign Proves Commercial Lighting Upgrades Drive Savings DOE Campaign Proves Commercial Lighting Upgrades Drive Savings July 11, 2016 - 12:08pm Addthis DOE Campaign Proves Commercial Lighting Upgrades Drive Savings By Monica Kanojia The Interior Lighting Campaign (Campaign) has seen tremendous success since its inception with more than 160 leading organizations signing on as participants and supporters. Launched as one of the Better Buildings Initiative's Technology Campaigns in

  19. Using Qualified Energy Conservation Bonds for Public Building Upgrades:

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Reducing Energy Bills in the City of Philadelphia | Department of Energy Qualified Energy Conservation Bonds for Public Building Upgrades: Reducing Energy Bills in the City of Philadelphia Using Qualified Energy Conservation Bonds for Public Building Upgrades: Reducing Energy Bills in the City of Philadelphia Summarizes how the City of Philadelphia leveraged $6.25 million in qualified energy conservation bonds to upgrade the energy efficiency of city buildings. Author: Lawrence Berkeley

  20. CONSORTIUM GETS WISE ABOUT ENERGY UPGRADES | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    CONSORTIUM GETS WISE ABOUT ENERGY UPGRADES CONSORTIUM GETS WISE ABOUT ENERGY UPGRADES CONSORTIUM GETS WISE ABOUT ENERGY UPGRADES In a region where energy efficiency is a relatively new concept, the Southeast Energy Efficiency Alliance (SEEA) joined with a consortium of 13 cities across eight states and one territory to build a framework for energy efficiency programs that could be replicated and implemented across the Southeast. Because each city took a unique approach to developing and

  1. California Member Connects Solar Adoption With Upgrades | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Connects Solar Adoption With Upgrades California Member Connects Solar Adoption With Upgrades Photo of a young man working on solar panels. Studies on the connection between solar adoption and energy upgrades by Better Buildings Residential Network member Center for Sustainable Energy (CSE) in California are helping solar companies realize that partnering with local energy efficiency programs can help turn potential competition into an addition to their business. According to CSE,

  2. New Science on the Horizon as Upgraded Particle Accelerator Meets...

    Office of Science (SC) Website

    ... Leigh Harwood Jefferson Lab, 12 GeV CEBAF Upgrade - Associate Project Manager harwood@jlab.org Funding DOE Office of Science Nuclear Physics Program. Commonwealth of Virginia. ...

  3. Solar Test Facility Upgrades Complete, Leading to Better Sandia...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Test Facility Upgrades Complete, Leading to Better Sandia Capabilities to Support Power ... Applications National Solar Thermal Test Facility Nuclear Energy Systems ...

  4. Security Upgrades Completed in Russian Northern Fleet | National...

    National Nuclear Security Administration (NNSA)

    An important mission of NNSA is to reduce the threat of the proliferation of nuclear weapons by working cooperatively with Russia to upgrade the security of nuclear facilities. ...

  5. Using QECBs for Street Lighting Upgrades: Lighting the Way to...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    the Internal Revenue Service Qualified Energy Conservation Bonds Using Qualified Energy Conservation Bonds for Public Building Upgrades: Reducing Energy Bills in the City of...

  6. The /scratc3 performance degradation after GridRaid upgrade

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    The The /scratc3 performance degradation after GridRaid upgrade The /scratc3 performance degradation after GridRaid upgrade April 7, 2016 The Edison /scratch3 file system was upgraded to Grid Raid from MDRaid during the move to the CRT building (Dec, 2015). This upgrade was recommended by the vendors because it greatly enhances the drive rebuild time and write performance when compared to the traditional MDRaid that was deployed on Edison /scratch3 file system before the move (The /scratch1 and

  7. EFFICIENCY MAINE DIRECT INSTALLS INCREASE UPGRADE PACE | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... Maine offered limited-time rebates to drive demand for residential energy upgrades. ... While the program also drove demand through radio and television advertising, many ...

  8. Federal Finance Facilities Available for Energy Efficiency Upgrades...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Federal Finance Facilities Available for Energy Efficiency Upgrades and Clean Energy Deployment This webinar, held on Sept. 24, 2013, provides information on federal finance ...

  9. DOE Campaign Proves Commercial Lighting Upgrades Drive Savings...

    Broader source: Energy.gov (indexed) [DOE]

    DOE Campaign Proves Commercial Lighting Upgrades Drive Savings By Monica Kanojia The Interior Lighting Campaign (Campaign) has seen tremendous success since its inception with more ...

  10. EECBG Success Story: Energy Efficiency Upgrades Part of Winning...

    Office of Environmental Management (EM)

    This feature, along with upgrades to the building envelope and lighting, are estimated to reduce the school district's annual energy usage by 43 percent. Learn more. Addthis ...

  11. Energy Upgrade Program Revitalizing Oregon | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    lighting, will be about 760, meaning the upgrades will pay for themselves in ... Upfront Costs to Save Energy Smart for Life received a loan from Palm Beach County's ...

  12. Shared Space vs. In-Unit Upgrades in Multifamily Buildings

    Broader source: Energy.gov [DOE]

    Better Buildings Neighborhood Program Multifamily Peer Exchange Call: Shared Space vs. In-Unit Upgrades in Multifamily Buildings, Call Slides and Summary, May 9, 2013.

  13. NSTX-U Control System Upgrades | Princeton Plasma Physics Lab

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Control System Upgrades This system can serve as a control system for any fusion device, including ITER. Currently, the PCS calculates many complicated and disjoint algorithms...

  14. Algal Lipid Extraction and Upgrading to Hydrocarbons Technology...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Technology Pathway More Documents & Publications Pathways for Algal Biofuels Bioenergy Technologies Office R&D Pathways: Algal Lipid Upgrading 2013 Peer Review Presentations-Algae

  15. Direct Catalytic Upgrading of Current Dilute Alcohol Fermentation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    or Catalyst Tuning * Beyond the Ethanol "Blend-wall" * Uses existing ... * The program objective is to take the ethanol upgrading technology from TRL 2 to TRL ...

  16. Conceptual design report for Project W-420, stack monitoring upgrade

    SciTech Connect (OSTI)

    Lott, D.T., Fluor Daniel Hanford

    1997-03-10

    This document provides the Conceptual Design for the upgrade of seven designated Tank Farm stacks to meet NESHAP Title 40, CFR, Part 61, Sub-part H requirements.

  17. EA-1190: Wastewater Treatment Capability Upgrade, Amarillo, Texas

    Broader source: Energy.gov [DOE]

    This EA evaluates the environmental impacts for the proposed upgrade of the U.S. Department of Energy Pantex Plant Wastewater Treatment Plant in Amarillo, Texas.

  18. PHOENIX ENERGIZES LIGHT RAIL CORRIDOR WITH UPGRADES | Department...

    Energy Savers [EERE]

    in Phoenix, Arizona's 10-mile-long Light Rail Corridor, Energize Phoenix focused on performing energy upgrades and reducing energy use in commercial and residential spaces. ...

  19. Capitalizing on Multibenefits of Energy Upgrades at Multifamily...

    Energy Savers [EERE]

    Call Slides and Discussion Summary (3.36 MB) More Documents & Publications Staged Upgrades as a Strategy for Residential Energy Efficiency Trends in Multifamily Programs: What's ...

  20. Staged Upgrades as a Strategy for Residential Energy Efficiency...

    Energy Savers [EERE]

    as a Strategy for Residential Energy Efficiency Staged Upgrades as a Strategy for Residential Energy Efficiency Better Buildings Residential Network Peer Exchange Call Series: ...

  1. Syngas Upgrading to Hydrocarbon Fuels Technology Pathway (Technical...

    Office of Scientific and Technical Information (OSTI)

    This technology pathway case investigates the upgrading of woody biomass derived synthesis ... Sponsoring Org: USDOE Office of Energy Efficiency and Renewable Energy Biomass Program ...

  2. Bedford Energizes Other Communities to Upgrade | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Bedford Energizes Other Communities to Upgrade Spurred by the creation of a ... (NYSERDA) to pilot a successful energy efficiency program in Bedford that became a launching ...

  3. Office of Energy Policy and Systems Analysis Site Upgrade

    Broader source: Energy.gov [DOE]

    Office of Energy Policy and Systems Analysis site is currently being upgraded to better serve on audience. Please check back shortly.

  4. Syngas Upgrading to Hydrocarbon Fuels Technology Pathway | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Pathway This technology pathway case investigates the upgrading of woody biomass derived synthesis gas (syngas) to hydrocarbon biofuels. While this specific discussion...

  5. Computing Sciences Staff Help East Bay High Schoolers Upgrade...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    from underrepresented groups learn about careers in a variety of IT fields, the Laney College Computer Information Systems Department offered its Upgrade: Computer Science Program. ...

  6. Staged Upgrades as a Strategy for Residential Energy Efficiency

    Office of Energy Efficiency and Renewable Energy (EERE)

    Better Buildings Residential Network Peer Exchange Call Series: Staged Upgrades as a Strategy for Residential Energy Efficiency, call slides and discussion summary.

  7. The enhanced ASDEX Upgrade pellet centrifuge launcher

    SciTech Connect (OSTI)

    Plöckl, B.; Lang, P. T.

    2013-10-15

    Pellets played an important role in the program of ASDEX Upgrade serving both for investigations on efficient particle fuelling and high density scenarios but also for pioneering work on Edge Localised Mode (ELM) pacing and mitigation. Initially designed for launching fuelling pellets from the magnetic low field side, the system was converted already some time ago to inject pellets from the magnetic high field side as much higher fuelling efficiency was found using this configuration. In operation for more than 20 years, the pellet launching system had to undergo a major revision and upgrading, in particular of its control system. Furthermore, the control system installed adjacent to the launcher had to be transferred to a more distant location enforcing a complete galvanic separation from torus potential and a fully remote control solution. Changing from a hybrid system consisting of PLC S5/S7 and some hard wired relay control to a state of the art PLC system allowed the introduction of several new operational options enabling more flexibility in the pellet experiments. This article describes the new system architecture of control hardware and software, the operating procedure, and the extended operational window. First successful applications for ELM pacing and triggering studies are presented as well as utilization for the development of high density scenarios.

  8. EIS-0100: Liberty-Coolidge 230-kV Transmission Line, Arizona

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration prepared this statement to assess the potential environmental and socioeconomic implications of various alternatives associated with an upgrade of electrical transmission capability between the Liberty and Coolidge Substations.

  9. 2006 Final Transmission Proposal: Revenue Requirements Study.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    2005-06-01

    The purpose of the Revenue Requirement Study (Study) is to establish the level of revenues needed from rates for Bonneville Power Administration's (BPA's) transmission and ancillary services to recover, in accordance with sound business principles, costs associated with the transmission of electric power over the Federal Columbia River Transmission System (FCRTS). The FCRTS is part of the larger Federal Columbia River Power System (FCRPS) which also includes the hydroelectric, multipurpose facilities constructed and operated by the U.S. Army Corps of Engineers and the Bureau of Reclamation in the Pacific Northwest. The FCRPS costs that are not included in the FCRTS costs are funded and repaid through BPA power rates. The transmission revenue requirements herein include: recovery of the Federal investment in transmission and transmission-related assets; the operations and maintenance (O&M) and other annual expenses associated with the provision of transmission and ancillary services; the cost of generation inputs for ancillary services and other between business-line services necessary for the transmission of power; and all other transmission-related costs incurred by the Administrator. The cost evaluation period for this rate proposal includes Fiscal Years (FYs) 2005-2007, the period extending from the last year for which historical information is available through the proposed rate test period. The Study includes the transmission revenue requirements for the rate test period, FYs 2006-2007 (Rate Period) and the results of transmission repayment studies. This Study outlines the policies, forecasts, assumptions, and calculations used to determine BPA's transmission revenue requirements. Legal requirements are summarized in Chapter 5 of this Study. The Revenue Requirement Study Documentation (Documentation), TR-06-FS-BPA-01A, contains key technical assumptions and calculations, the results of the transmission repayment studies, and a further explanation of the

  10. Preliminary business plan: Plzen district heating system upgrade

    SciTech Connect (OSTI)

    1996-06-01

    The district heating system of the City of Plzen, Czech Republic, needs to have physical upgrades to replace aging equipment and to comply with upcoming environmental regulations. Also, its ownership and management are being changed as a result of privatization. As majority owner, the City has the primary goal of ensuring that the heating needs of its customers are met as reliably and cost-effectively as possible. This preliminary business plan is part of the detailed analysis (5 reports in all) done to assist the City in deciding the issues. Preparation included investigation of ownership, management, and technology alternatives; estimation of market value of assets and investment requirements; and forecasting of future cash flow. The district heating system consists of the Central Plzen cogeneration plant, two interconnected heating plants [one supplying both hot water and steam], three satellite heating plants, and cooperative agreements with three industrial facilities generating steam and hot water. Most of the plants are coal-fired, with some peaking units fired by fuel oil.

  11. Ammonia removal process upgrade to the Acme Steel Coke Plant

    SciTech Connect (OSTI)

    Harris, J.L.

    1995-12-01

    The need to upgrade the ammonia removal process at the Acme Steel Coke Plant developed with the installation of the benzene NESHAP (National Emission Standard for Hazardous Air Pollutants) equipment, specifically the replacement of the final cooler. At Acme Steel it was decided to replace the existing open cooling tower type final cooler with a closed loop direct spray tar/water final cooler. This new cooler has greatly reduced the emissions of benzene, ammonia, hydrogen sulfide and hydrogen cyanide to the atmosphere, bringing them into environmental compliance. At the time of its installation it was not fully recognized as to the effect this would have on the coke oven gas composition. In the late seventies the decision had been made at Acme Steel to stop the production of ammonia sulfate salt crystals. The direction chosen was to make a liquid ammonia sulfate solution. This product was used as a pickle liquor at first and then as a liquid fertilizer as more markets were developed. In the fall of 1986 the ammonia still was brought on line. The vapors generated from the operation of the stripping still are directed to the inlet of the ammonia absorber. At that point in time it was decided that an improvement to the cyclical ammonia removal process was needed. The improvements made were minimal yet allowed the circulation of solution through the ammonia absorber on a continuous basis. The paper describes the original batch process and the modifications made which allowed continuous removal.

  12. Design review report: AN valve pit upgrades for Project W-314, tank farm restoration and safe operations

    SciTech Connect (OSTI)

    Boes, K.A.

    1998-01-13

    This Design Review Report (DRR) documents the contractor design verification methodology and records associated with project W-314`s AN Valve Pit Upgrades design package. The DRR includes the documented comments and their respective dispositions for this design. Acceptance of the comment dispositions and closure of the review comments is indicated by the signatures of the participating reviewers. Project W-314, Tank Farm Restoration and Safe Operations, is a project within the Tank Waste Remediation System (TWRS) Tank Waste Retrieval Program. This project provides capital upgrades for the existing Hanford tank farms` waste transfer, instrumentation, ventilation, and electrical infrastructure systems. To support established TWRS programmatic objectives, the project is organized into two distinct phases. The initial focus of the project (i.e., Phase 1) is on waste transfer system upgrades needed to support the TWRS Privatization waste feed delivery system. Phase 2 of the project will provide upgrades to support resolution of regulatory compliance issues, improve tank infrastructure reliability, and reduce overall plant operating/maintenance costs. Within Phase 1 of the W-314 project, the waste transfer system upgrades are further broken down into six major packages which align with the project`s work breakdown structure. Each of these six sub-elements includes the design, procurement, and construction activities necessary to accomplish the specific tank farm upgrades contained within the package. The first package to be performed is the AN Valve Pit Upgrades package. The scope of the modifications includes new pit cover blocks, valve manifolds, leak detectors, transfer line connections (for future planned transfer lines), and special protective coating for the 241-AN-A and 241-AN-B valve pits.

  13. Energy and Cost Optimized Technology Options to Meet Energy Needs of Food Processors

    SciTech Connect (OSTI)

    Makhmalbaf, Atefe; Srivastava, Viraj; Hoffman, Michael G.; Wagner, Anne W.; Thornton, John

    2015-04-02

    ABSTRACT Combined cooling, heating and electric power (CCHP) distributed generation (DG) systems can provide electricity, heat, and cooling power to buildings and industrial processes directly onsite, while significantly increasing energy efficiency, security of energy supply, and grid independence. Fruit, vegetable, dairy and meat processing industries with simultaneous requirements for heat, steam, chilling and electricity, are well suited for the use of such systems to supply base-load electrical demand or as peak reducing generators with heat recovery in the forms of hot water, steam and/or chilled water. This paper documents results and analysis from a pilot project to evaluate opportunities for energy, emission, and cost for CCHP-DG and energy storage systems installed onsite at food processing facilities. It was found that a dairy processing plant purchasing 15,000 MWh of electricity will need to purchase 450 MWh with the integration of a 1.1 MW CCHP system. Here, the natural gas to be purchased increased from 190,000 MMBtu to 255,000 MMBtu given the fuel requirements of the CCHP system. CCHP systems lower emissions, however, in the Pacific Northwest the high percentage of hydro-power results in CO2 emissions from CCHP were higher than that attributed to the electric utility/regional energy mix. The value of this paper is in promoting and educating financial decision makers to seriously consider CCHP systems when building or upgrading facilities. The distributed generation aspect can reduce utility costs for industrial facilities and show non-wires solution benefits to delay or eliminate the need for upgrades to local electric transmission and distribution systems.

  14. TMX-Upgrade neutral-beam injection system

    SciTech Connect (OSTI)

    Felker, B.; Kane, R.J.; Wong, R.L.; Calderon, M.O.; Moore, T.L.

    1981-10-05

    The TMX experiment proved that axial confinement of central-cell ions is improved ninefold by the electrostatic potential of end-cell plasmas. The TMX Upgrade task is to improve this confinement further. This paper discusses the injector system aspects of the TMX Upgrade.

  15. Rebates Cut the Price of Big-Time Efficiency Upgrades

    Broader source: Energy.gov [DOE]

    One of the smartest ways for homeowners to save money on major appliance upgrades is to hook into an energy efficiency rebate program. The Neighborhood Energy Connection (NEC), a non-profit organization in St. Paul, Minnesota, helps local residents take advantage of Xcel Energy’s rebate programs that cut the cost of whole-house energy efficiency upgrades.

  16. Automated manual transmission controller

    DOE Patents [OSTI]

    Lawrie, Robert E.; Reed, Jr., Richard G.; Bernier, David R.

    1999-12-28

    A powertrain system for a hybrid vehicle. The hybrid vehicle includes a heat engine, such as a diesel engine, and an electric machine, which operates as both an electric motor and an alternator, to power the vehicle. The hybrid vehicle also includes a manual-style transmission configured to operate as an automatic transmission from the perspective of the driver. The engine and the electric machine drive an input shaft which in turn drives an output shaft of the transmission. In addition to driving the transmission, the electric machine regulates the speed of the input shaft in order to synchronize the input shaft during either an upshift or downshift of the transmission by either decreasing or increasing the speed of the input shaft. When decreasing the speed of the input shaft, the electric motor functions as an alternator to produce electrical energy which may be stored by a storage device. Operation of the transmission is controlled by a transmission controller which receives input signals and generates output signals to control shift and clutch motors to effect smooth launch, upshift shifts, and downshifts of the transmission, so that the transmission functions substantially as an automatic transmission from the perspective of the driver, while internally substantially functioning as a manual transmission.

  17. The 12 GeV Energy Upgrade at Jefferson Laboratory

    SciTech Connect (OSTI)

    Pilat, Fulvia C.

    2012-09-01

    Two new cryomodules and an extensive upgrade of the bending magnets at Jefferson Lab has been recently completed in preparation for the full energy upgrade in about one year. Jefferson Laboratory has undertaken a major upgrade of its flagship facility, the CW re-circulating CEBAF linac, with the goal of doubling the linac energy to 12 GeV. I will discuss here the main scope and timeline of the upgrade and report on recent accomplishments and the present status. I will then discuss in more detail the core of the upgrade, the new additional C100 cryomodules, their production, tests and recent successful performance. I will then conclude by looking at the future plans of Jefferson Laboratory, from the commissioning and operations of the 12 GeV CEBAF to the design of the MEIC electron ion collider.

  18. Upgrading the TFTR Transrex Power Supplies

    SciTech Connect (OSTI)

    J. E. Lawson, R. Marsala, S. Ramakrishnan, X. Zhao, P. Sichta

    2009-05-29

    In order to provide improved and expanded experimental capabilities, the existing Transrex power supplies at PPPL are to be upgraded and modernized. Each of the 39 power supplies consists of two six pulse silicon controlled rectifier sections forming a twelve pulse power supply. The first modification is to split each supply into two independent six pulse supplies by replacing the existing obsolete twelve pulse firing generator with two commercially available six pulse firing generators. The second change replaces the existing control link with a faster system, with greater capacity, which will allow for independent control of all 78 power supply sections. The third change replaces the existing Computer Automated Measurement and Control (CAMAC) based fault detector with an Experimental Physics and Industrial Control System (EPICS) compatible unit, eliminating the obsolete CAMAC modules. Finally the remaining relay logic and interfaces to the "Hardwired Control System" will be replaces with a Programmable Logic Controller (PLC).

  19. LLRF System for the CEBAF Separator Upgrade

    SciTech Connect (OSTI)

    Plawski, Tomasz E.; Bachimanchi, Ramakrishna; Hovater, J. Curt; Seidman, David J.; Wissmann, Mark J.

    2014-12-01

    The Continuous Electron Beam Accelerator Facility (CEBAF) energy upgrade from 6 GeV to 12 GeV includes the installation of four new 748.5 MHz normal conducting deflecting cavities in the 5th pass extraction region. This system will work together with the existing 499 MHz RF Separator in order to allow simultaneous delivery of the beam to four CEBAF experimental halls. The RF system employs two digital LLRF systems controlling four cavities in a vector sum. Cavity tune information of the individual cavities is also obtained using a multiplexing scheme of the forward and reflected RF signals. In this paper we will present detailed LLRF design and the current status of the CEBAF 748.5/499 MHz beam extraction system.

  20. Steam turbine upgrading: low-hanging fruit

    SciTech Connect (OSTI)

    Peltier, R.

    2006-04-15

    The thermodynamic performance of the steam turbine, more than any other plant component, determines overall plant efficiency. Upgrading steam path components and using computerized design tools and manufacturing techniques to minimise internal leaks are two ways to give tired steam turbines a new lease on life. The article presents three case studies that illustrate how to do that. These are at Unit 1 of Dairyland's J.P. Madgett Station in Alma, WI, a coal-fired subcritical steam plant; the four units at AmerenUE's 600 MW coal-fired Labadie plant west of St. Louis; and Unit 3 of KeyPlan Corp's Northport Power Station on Long Island. 8 figs.

  1. Heavy crude upgrading using remote natural gas

    SciTech Connect (OSTI)

    Grosboll, M.P.

    1991-12-03

    This paper describes a method of forming an upgraded crude. It comprises: forming hydrogen from methane gas for hydroconverting heavy crude to form a better crude and reduce its viscosity; hydrogenating under hydroconverting conditions of 650 degrees Fahrenheit ({degrees}F)-1000{degrees}F; and 500-3000 pounds per square inch gauge (psig) only a first portion of a crude oil stream less than the total crude oil stream to produce a light oil that has a lowered viscosity; admixing the light oil with the remainder of the crude oil stream not hydrogenated to produce a flowable crude; and transporting the flowable crude to a refinery including a substep of flowing the crude through a pipeline.

  2. Sludge formation during heavy oil upgrading

    SciTech Connect (OSTI)

    Storm, D.A.; Decanio, S.J.; Edwards, J.C.

    1995-12-31

    A soft coke-like substance often forms in the liquid product of visbreaking and hydrocracking processes for upgrading vacuum residue of heavy crude oil. This material usually limits the severity or conversion of the process because it accumulates in downstream equipment. Although the amount of such material produced depends on the crude oil, it has not been possible to correlate its production rate to chemical characteristics of the vacuum residue in a quantitative manner In this work we show that the amount of sludge produced per unit weight of vacuum residue feed in laboratory hydrotreating experiments can be correlated with four chemical characteristic of the vacuum residue: the degree of condensed polynuclear aromaticity, the average number of alkyl-groups substituting the polynuclear aromatics, the ratio of heptane insolubles to pentane insoluble-heptane solubles, and the H/C ratio of the latter fraction. The correlation coefficient is 0.95.

  3. PEP-II Transverse Feedback Electronics Upgrade

    SciTech Connect (OSTI)

    Weber, J.M.; Chin, M.J.; Doolittle, L.R.; Akre, R.; /SLAC

    2006-03-13

    The PEP-II B Factory at the Stanford Linear Accelerator Center (SLAC) requires an upgrade of the transverse feedback system electronics. The new electronics require 12-bit resolution and a minimum sampling rate of 238 Msps. A Field Programmable Gate Array (FPGA) is used to implement the feedback algorithm. The FPGA also contains an embedded PowerPC 405 (PPC-405) processor to run control system interface software for data retrieval, diagnostics, and system monitoring. The design of this system is based on the Xilinx{reg_sign} ML300 Development Platform, a circuit board set containing an FPGA with an embedded processor, a large memory bank, and other peripherals. This paper discusses the design of a digital feedback system based on an FPGA with an embedded processor. Discussion will include specifications, component selection, and integration with the ML300 design.

  4. PEP-II Transverse Feedback Electronics Upgrade

    SciTech Connect (OSTI)

    Weber, J.; Chin, M.; Doolittle, L.; Akre, R.

    2005-05-09

    The PEP-II B Factory at the Stanford Linear Accelerator Center (SLAC) requires an upgrade of the transverse feedback system electronics. The new electronics require 12-bit resolution and a minimum sampling rate of 238 Msps. A Field Programmable Gate Array (FPGA) is used to implement the feedback algorithm. The FPGA also contains an embedded PowerPC 405 (PPC-405) processor to run control system interface software for data retrieval, diagnostics, and system monitoring. The design of this system is based on the Xilinx(R) ML300 Development Platform, a circuit board set containing an FPGA with an embedded processor, a large memory bank, and other peripherals. This paper discusses the design of a digital feedback system based on an FPGA with an embedded processor. Discussion will include specifications, component selection, and integration with the ML300 design.

  5. EIS-0484: Montana-to-Washington Transmission System Upgrade Project in Washington, Idaho, and Montana

    Broader source: Energy.gov [DOE]

    This EIS has been cancelled. Additional information is available at http://efw.bpa.gov/environmental_services/Document_Library/M2W/.

  6. Upgraded HFIR Fuel Element Welding System

    SciTech Connect (OSTI)

    Sease, John D

    2010-02-01

    The welding of aluminum-clad fuel plates into aluminum alloy 6061 side plate tubing is a unique design feature of the High Flux Isotope Reactor (HFIR) fuel assemblies as 101 full-penetration circumferential gas metal arc welds (GMAW) are required in the fabrication of each assembly. In a HFIR fuel assembly, 540 aluminum-clad fuel plates are assembled into two nested annular fuel elements 610 mm (24-inches) long. The welding process for the HFIR fuel elements was developed in the early 1960 s and about 450 HFIR fuel assemblies have been successfully welded using the GMAW process qualified in the 1960 s. In recent years because of the degradation of the electronic and mechanical components in the old HFIR welding system, reportable defects in plate attachment or adapter welds have been present in almost all completed fuel assemblies. In October 2008, a contract was awarded to AMET, Inc., of Rexburg, Idaho, to replace the old welding equipment with standard commercially available welding components to the maximum extent possible while maintaining the qualified HFIR welding process. The upgraded HFIR welding system represents a major improvement in the welding system used in welding HFIR fuel elements for the previous 40 years. In this upgrade, the new inner GMAW torch is a significant advancement over the original inner GMAW torch previously used. The innovative breakthrough in the new inner welding torch design is the way the direction of the cast in the 0.762 mm (0.030-inch) diameter aluminum weld wire is changed so that the weld wire emerging from the contact tip is straight in the plane perpendicular to the welding direction without creating any significant drag resistance in the feeding of the weld wire.

  7. The DIII-D cryogenic system upgrade

    SciTech Connect (OSTI)

    Schaubel, K.M.; Laughon, G.J.; Campbell, G.L.; Langhorn, A.R.; Stevens, N.C.; Tupper, M.L.

    1993-10-01

    The original DIII-D cryogenic system was commissioned in 1981 and was used to cool the cryopanel arrays for three hydrogen neutral beam injectors. Since then, new demands for liquid helium have arisen including: a fourth neutral beam injector, ten superconducting magnets for the electron cyclotron heating gyrotrons, and more recently, the advanced diverter cryopump which resides inside the tokamak vacuum vessel. The original cryosystem could not meet these demands. Consequently, the cryosystem was upgraded in several phases to increase capacity, improve reliability, and reduce maintenance. The majority of the original system has been replaced with superior equipment. The capacity now exists to support present as well as future demands for liquid helium at DIII-D including a hydrogen pellet injector, which is being constructed by Oak Ridge National Laboratory. Upgrades to the cryosystem include: a recently commissioned 150 {ell}/hr helium liquefier, two 55 g/sec helium screw compressors, a fully automated 20-valve cryogen distribution box, a high efficiency helium wet expander, and the conversion of equipment from manual or pneumatic to programmable logic controller (PLC) control. The distribution box was designed and constructed for compactness due to limited space availability. Overall system efficiency was significantly improved by replacing the existing neutral beam reliquefier Joule-Thomson valve with a reciprocating wet expander. The implementation of a PLC-based automatic control system has resulted in increased efficiency and reliability. This paper will describe the cryosystem design with emphasis on newly added equipment. In addition, performance and operational experience will be discussed.

  8. Kitchen Appliance Upgrades Improve Water Efficiency at U.S. Department...

    Energy Savers [EERE]

    Kitchen Appliance Upgrades Improve Water Efficiency at U.S. Department of Defense Exchange Facilities Kitchen Appliance Upgrades Improve Water Efficiency at U.S. Department of Defense ...

  9. FY 2013 Reactor Upgrades FOA (DE-FOA-0000815) | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    University Programs (NEUP) University Reactor Upgrades Infrastructure Support for the ... FY 2013 Reactor Upgrades FOA (DE-FOA-0000815).pdf (270.3 KB) More Documents & Publications ...

  10. Transmission Planning Analysis Tool

    Energy Science and Technology Software Center (OSTI)

    2015-06-23

    Developed to solve specific problem: Assist transmission planning for regional transfers in interconnected power systems. This work was originated in a study for the U.S. Department of State, to recommend transmission reinforcements for the Central American regional system that interconnects 6 countries. Transmission planning analysis is currently performed by engineers with domainspecific and systemspecific knowledge without a unique methodology. The software codes of this disclosure assists engineers by defining systematic analysis procedures to help identifymore » weak points and make decisions on transmission planning of regional interconnected power systems. Transmission Planning Analysis Tool groups PSS/E results of multiple AC contingency analysis and voltage stability analysis and QV analysis of many scenarios of study and arrange them in a systematic way to aid power system planning engineers or transmission operators in effective decision]making process or in the off]line study environment.« less

  11. Transmission Planning Analysis Tool

    SciTech Connect (OSTI)

    2015-06-23

    Developed to solve specific problem: Assist transmission planning for regional transfers in interconnected power systems. This work was originated in a study for the U.S. Department of State, to recommend transmission reinforcements for the Central American regional system that interconnects 6 countries. Transmission planning analysis is currently performed by engineers with domainspecific and systemspecific knowledge without a unique methodology. The software codes of this disclosure assists engineers by defining systematic analysis procedures to help identify weak points and make decisions on transmission planning of regional interconnected power systems. Transmission Planning Analysis Tool groups PSS/E results of multiple AC contingency analysis and voltage stability analysis and QV analysis of many scenarios of study and arrange them in a systematic way to aid power system planning engineers or transmission operators in effective decision]making process or in the off]line study environment.

  12. NREL: Transmission Grid Integration - Publications

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Publications Want updates about future transmission grid integration webinars and ... and Transmission Study Flexible Energy Scheduling Tool for Integration of ...

  13. Coordinating Interstate ElectricTransmission Siting: An Introduction to the

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Debate | Department of Energy Coordinating Interstate ElectricTransmission Siting: An Introduction to the Debate Coordinating Interstate ElectricTransmission Siting: An Introduction to the Debate In recent years, experts have started drawing att ention to the need to improve the system that transmits electricity from power plants to demand centers. Congestion on existing lines, increased energy demand that suggests a need for new electric transmission and the challenge of connecting

  14. Series Transmission Line Transformer

    DOE Patents [OSTI]

    Buckles, Robert A.; Booth, Rex; Yen, Boris T.

    2004-06-29

    A series transmission line transformer is set forth which includes two or more of impedance matched sets of at least two transmissions lines such as shielded cables, connected in parallel at one end ans series at the other in a cascading fashion. The cables are wound about a magnetic core. The series transmission line transformer (STLT) which can provide for higher impedance ratios and bandwidths, which is scalable, and which is of simpler design and construction.

  15. Transmission and Storage Operations

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Transmission and Storage Operations Natural Gas Infrastructure R&D and Methane Mitigation Workshop Mary Savalle, PMP, LSSGB Compression Reliability Engineer November 12, 2014 ...

  16. Current Transmission Rates

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    links Financial Information Financial Public Processes Asset Management Cost Verification Process Rate Cases Rate Information Current Power Rates Current Transmission Rates...

  17. Previous Transmission Rates

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    links Financial Information Financial Public Processes Asset Management Cost Verification Process Rate Cases Rate Information Current Power Rates Current Transmission Rates...

  18. 2012 Transmission Rate Schedules

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    2014 Transmission, Ancillary, and Control Area Service Rate Schedules and General Rate Schedule Provisions (FY 2014-2015) October 2013 United States Department of Energy...

  19. Collaborative Transmission Technology Roadmap

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Addendum to the Collaborative Transmission Technology Roadmap March 2014 Bonneville Power Administration Enhanced PDF Functionality Functionality of the PDF version of this...

  20. Transmission - Contact Information

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Contact-Information-Transmission Sign In About | Careers | Contact | Investors | bpa.gov Search News & Us Expand News & Us Projects & Initiatives Expand Projects &...

  1. Electrical Engineer- Transmission Lines

    Broader source: Energy.gov [DOE]

    (See Frequently Asked Questions for more information). Where would I be working? Western Area Power Administration, Upper Great Plains Region, Maintenance, North Dakota Maintenance, Transmission...

  2. Transmission Grid Integration

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... Energy, SMART Grid, Systems Analysis, Transmission Grid Integration, Wind Energy Sandia Contributes to International Electrotechnical Commission IEC 61400-26 Availability ...

  3. Detector development for Jefferson Lab's 12GeV Upgrade

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Qiang, Yi

    2015-05-01

    Jefferson Lab will soon finish its highly anticipated 12 GeV Upgrade. With doubled maximum energy, Jefferson Lab’s Continuous Electron Beam Accelerator Facility (CEBAF) will enable a new experimental program with substantial discovery potential, addressing important topics in nuclear, hadronic and electroweak physics. In order to take full advantage of the high energy, high luminosity beam, new detectors are being developed, designed and constructed to fit the needs of different physics topics. The paper will give an overview of various new detector technologies to be used for 12 GeV experiments. It will then focus on the development of two solenoid-based spectrometers,more » the GlueX and SoLID spectrometers. The GlueX experiment in Hall D will study the complex properties of gluons through exotic hybrid meson spectroscopy. The GlueX spectrometer, a hermetic detector package designed for spectroscopy and the associated partial wave analysis, is currently in the final stage of construction. Hall A, on the other hand, is developing the SoLID spectrometer to capture the 3D image of the nucleon from semi-inclusive processes and to study the intrinsic properties of quarks through mirror symmetry breaking. Such a spectrometer will have the capability to handle very high event rates while still maintaining a large acceptance in the forward region.« less

  4. Linac cryogenic distribution system maintenance and upgrades at JLab

    SciTech Connect (OSTI)

    Dixon, K.; Wright, M.; Ganni, V.

    2014-01-29

    The Central Helium Liquefier (CHL) distribution system to the CEBAF and FEL linacs at Jefferson Lab (JLab) experienced a planned warm up during the late summer and fall of 2012 for the first time after its commissioning in 1991. Various maintenance and modifications were performed to support high beam availability to the experimental users, meet 10 CFR 851 requirements for pressure systems, address operational issues, and prepare the cryogenic interfaces for the high-gradient cryomodules needed for the 12 GeV upgrade. Cryogenic maintenance and installation work had to be coordinated with other activities in the linacs and compete for manpower from other department installation activities. With less than a quarter of the gas storage capacity available to handle the boil-off from the more than 40 cryomodules, 35,000 Nm{sup 3} of helium was re-liquefied and shipped to a vendor via a liquid tanker trailer. Nearly 200 u-tubes had to be removed and stored while seals were replaced on related equipment such as vacuum pump outs, bayonet isolation and process valves.

  5. Linac cryogenic distribution system maintenance and upgrades at Jlab

    SciTech Connect (OSTI)

    Dixon, Kelly D.; Wright, Mathew C.; Ganni, Venkatarao

    2014-01-01

    The Central Helium Liquefier (CHL) distribution system to the CEBAF and FEL linacs at Jefferson Lab (JLab) experienced a planned warm up during the late summer and fall of 2012 for the first time after its commissioning in 1991. Various maintenance and modifications were performed to support high beam availability to the experimental users, meet 10 CFR 851 requirements for pressure systems, address operational issues, and prepare the cryogenic interfaces for the high-gradient cryomodules needed for the 12 GeV upgrade. Cryogenic maintenance and installation work had to be coordinated with other activities in the linacs and compete for manpower from other department installation activities. With less than a quarter of the gas storage capacity available to handle the boil-off from the more than 40 cryomodules, 35,000 Nm{sup 3} of helium was re-liquefied and shipped to a vendor via a liquid tanker trailer. Nearly 200 u-tubes had to be removed and stored while seals were replaced on related equipment such as vacuum pump outs, bayonet isolation and process valves.

  6. Booster Synchrotron RF System Upgrade for SPEAR3

    SciTech Connect (OSTI)

    Park, Sanghyun; Corbett, Jeff; /SLAC

    2012-07-06

    Recent progress at the SPEAR3 includes the increase in stored current from 100 mA to 200 mA and top-off injection to allow beamlines to stay open during injection. Presently the booster injects 3.0 GeV beam to SPEAR3 three times a day. The stored beam decays to about 150 mA between the injections. The growing user demands are to increase the stored current to the design value of 500 mA, and to maintain it at a constant value within a percent or so. To achieve this goal the booster must inject once every few minutes. For improved injection efficiency, all RF systems at the linac, booster and SPEAR3 need to be phase-locked. The present booster RF system is basically a copy of the SPEAR2 RF system with 358.5 MHz and 40 kW peak RF power driving a 5-cell RF cavity for 1.0 MV gap voltage. These requirements entail a booster RF system upgrade to a scaled down version of the SPEAR3 RF system of 476.3 MHz with 1.2 MW cw klystron output power capabilities. We will analyze each subsystem option for their merits within budgetary and geometric space constraints. A substantial portion of the system will come from the decommissioned PEP-II RF stations.

  7. Extension - Upgrading Methane Using Ultra-Fast Thermal Swing Adsorption

    SciTech Connect (OSTI)

    Anna Lee Tonkovich

    2008-08-11

    The need for cost effective technologies for upgrading coal mine methane to pipeline quality natural gas is becoming ever greater. The current work presents and investigates a new approach to reduce the impact of the most costly step in the conventional technology, nitrogen rejection. The proposed approach is based on the Velocys microchannel platform, which is being developed to commercialize compact and cost efficient chemical processing technology. For this separation, ultra fast thermal swing sorption is enabled by the very high rates of heat and mass transfer inherent in microchannel processing. In a first phase of the project solid adsorbents were explored. Feasibility of ultrafast thermal swing was demonstrated but the available adsorbents had insufficient differential methane capacity to achieve the required commercial economics. In a second phase, ionic liquids were adopted as absorbents of choice, and experimental work and economic analyses, performed to gauge their potential, showed promise for this novel alternative. Final conclusions suggest that a combination of a required cost target for ionic liquids or a methane capacity increase or a combination of both is required for commercialization.

  8. Upgrading of petroleum oil feedstocks using alkali metals and hydrocarbons

    SciTech Connect (OSTI)

    Gordon, John Howard

    2014-09-09

    A method of upgrading an oil feedstock by removing heteroatoms and/or one or more heavy metals from the oil feedstock composition. This method reacts the oil feedstock with an alkali metal and an upgradant hydrocarbon. The alkali metal reacts with a portion of the heteroatoms and/or one or more heavy metals to form an inorganic phase separable from the organic oil feedstock material. The upgradant hydrocarbon bonds to the oil feedstock material and increases the number of carbon atoms in the product. This increase in the number of carbon atoms of the product increases the energy value of the resulting oil feedstock.

  9. AMI FW UPGRADEABILITY TEST PROCEDURE AND SECURITY ASSESSMENT

    SciTech Connect (OSTI)

    Snyder, Isabelle B

    2014-01-01

    The National Institute of Standards and Technology (NIST) is producing NISTIR 7823 to define test requirements for Smart Meter upgradability. The term Smart Meter refers specifically to advanced electric meters being deployed to enhance management of electricity distribution for residential and industrial consumers. The underlying functional and security requirements for Smart Meter upgradability are specified in NEMA standard SG-AMI 1-2009. The purpose of NISTIR 7823 is to describe conformance test requirements that may be used voluntarily by testers and/or test laboratories to determine whether Smart Meters and Upgrade Management Systems conform to the requirements of NEMA SG-AMI 1-2009.

  10. Jefferson Lab's upgraded Free-Electron Laser produces first ligh |

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Jefferson Lab upgraded Free-Electron Laser produces first ligh Jefferson Lab's upgraded Free-Electron Laser produces first light June 18, 2003 Researchers at the U.S. Department of Energy's Thomas Jefferson National Accelerator Facility have produced first light from their 10-kilowatt Free-Electron Laser (FEL). Entrance to Free-Electron Laser building The Free-Electron Laser (FEL) facility at Jefferson Lab. Researchers have produced first light from the upgraded 10-kW FEL, located on the

  11. Upgrading liquid products: Notes from the workshop at the international conference research in thermochemical biomass conversion

    SciTech Connect (OSTI)

    Elliott, D.C.

    1988-07-01

    A workshop was held at the International Energy Agency conference, Research in Thermochemical Biomass Conversion, on the subject of upgrading liquid products. The workshop discussion focused on the two prominent methods of liquids upgrading, catalytic hydroprocessing and catalytic cracking. Catalytic hydroprocessing as applied to biomass liquids relies heavily on petroleum developed technology; similar catalysts and operating conditions are used, although lower space velocities are typical. The need for stabilization of the pyrolytic products prior to hydroprocessing was also discussed. Catalytic cracking of biomass liquids also relies heavily on petroleum processing technology. Zeolite catalyst development has focused on the ZSM-5 of Mobil and its application to pyrolysis products. Significant olefinic gas yields are obtained in the zeolitic processing of biomass pyrolyzates and the conversion of these to liquid fuels is a primary research goal. Aromatic gasoline is the primary product in both catalytic processes. A general conclusion of the workshop participants was that the cost of liquid fuels for internal combustion engines would be higher in the foreseeable future. Due to the high cost of initial biomass liquefaction plants (including upgrading) a more likely near-term product would be aromatic chemicals produced under constrained economic circumstances. 16 refs.

  12. Transmission Line Security Monitor

    ScienceCinema (OSTI)

    None

    2013-05-28

    The Transmission Line Security Monitor is a multi-sensor monitor that mounts directly on high-voltage transmission lines to detect, characterize and communicate terrorist activity, human tampering and threatening conditions around support towers. For more information about INL's critical infrastructure protection research, visit http://www.facebook.com/idahonationallaboratory.

  13. Transmission Line Security Monitor

    SciTech Connect (OSTI)

    2011-01-01

    The Transmission Line Security Monitor is a multi-sensor monitor that mounts directly on high-voltage transmission lines to detect, characterize and communicate terrorist activity, human tampering and threatening conditions around support towers. For more information about INL's critical infrastructure protection research, visit http://www.facebook.com/idahonationallaboratory.

  14. Idaho Power- Easy Upgrades for Simple Retrofits Rebate Program

    Broader source: Energy.gov [DOE]

    Idaho Power offers incentives for its commercial and industrial customers in Idaho and Oregon to upgrade to more efficient equipment in their facilities. The utility provides rebates for lighting...

  15. Idaho: Nez Perce Tribe Energy-Efficient Facilities Upgrade |...

    Broader source: Energy.gov (indexed) [DOE]

    Utilizing 67,000 of EERE's Tribal Energy Program funding, energy-efficiency upgrades were installed in five Nez Perce Reservation buildings that house a large portion of the Nez ...

  16. Project W-420 Stack Monitoring system upgrades conceptual design report

    SciTech Connect (OSTI)

    TUCK, J.A.

    1998-11-06

    This document describes the scope, justification, conceptual design, and performance of Project W-420 stack monitoring system upgrades on six NESHAP-designated, Hanford Tank Farms ventilation exhaust stacks.

  17. Innovative Technology Improves Upgrading Process for Unconventional Oil Resources

    Broader source: Energy.gov [DOE]

    An innovative oil-upgrading technology that can increase the economics of unconventional petroleum resources has been developed under a U.S. Department of Energy-funded project.

  18. Direct Catalytic Upgrading of Current Dilute Alcohol Fermentation...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Goal * The program objective is take the ethanol upgrading technology from TRL 2 to TRL 3 ... reactions produce coke which impedes the primary reaction of ethanol to C3+ hydrocarbons. ...

  19. Federal Finance Facilities Available for Energy Efficiency Upgrades

    Energy Savers [EERE]

    Federal Finance Facilities Available for Energy Efficiency Upgrades and Clean Energy Deployment A Guide for State, Local & Tribal Leaders and their Partners August 28, 2013 2 Contents 1 Foreword ................................................................................................................................... 5 2 Acknowledgements ................................................................................................................... 6 3 Federal Finance Facilities

  20. Upgrade Boilers with Energy-Efficient Burners | Department of...

    Energy Savers [EERE]

    STEAM TIP SHEET 24 Upgrade Boilers with Energy-Efficient Burners (January 2012) (416.98 ... Improve Your Boiler's Combustion Efficiency Minimize Boiler Short Cycling Losses J.R. ...

  1. Capturing Energy Efficiency Upgrades in the Real Estate Transaction

    Broader source: Energy.gov [DOE]

    "Capturing Energy Efficiency Upgrades in the Real Estate Transaction," by Residential Energy Efficiency Solutions, July 10, 2012. Describes the concept of a residential MPG number as a simple way of describing a home’s energy consumption.

  2. Energy Savers: Your One Stop Shop for Energy Efficiency Upgrades...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Your One Stop Shop for Energy Efficiency Upgrades Energy Savers: Your One Stop Shop for ... Energy Savers: A one-stop energy efficiency shop for multifamily building owners Energy ...

  3. Forthcoming Upgrades to the ARM MMCRs: Improved Radar Processor...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... laboratory test of the new processor, operating the current modes used on the SGP radar. ... In the upgrade the hardware is altered with the addition of an ortho- mode transducer ...

  4. What’s Working in Residential Energy Efficiency Upgrade Programs

    Broader source: Energy.gov [DOE]

    Slides presented in the "What’s Working in Residential Energy Efficiency Upgrade Programs Conference - Promising Approaches and Lessons Learned" on May 20, 2011 in Washington, D.C.

  5. EECBG Success Story: Energy Upgrades to Save Small Arizona Town...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of Oro Valley Energy Upgrades to Save Small Arizona Town Big Money Workers demonstrate the nitrogen tank used to inflate tires in St. Peters, MO. | Courtesy of the City of St. ...

  6. Webinar: Introduction to Better Buildings Home Upgrade Program Accelerator

    Broader source: Energy.gov [DOE]

    DOE recently launched the new Better Buildings Home Upgrade Program Accelerator that will focus on the adoption of HPXML and other process improvements to reduce administrative costs and improve...

  7. Weatherization and Workforce Guidelines for Home Energy Upgrades Fact Sheet

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    | Department of Energy and Workforce Guidelines for Home Energy Upgrades Fact Sheet Weatherization and Workforce Guidelines for Home Energy Upgrades Fact Sheet This fact sheet provides essential information about the 2011 publication of the Residential Retrofit Workforce Guidelines, including their origin, their development with the help of industry leaders to create the standard work specifications for retrofit work, their public review, and the JTAs/KSAs (job-task analyses/knowledge,

  8. Ribbon cutting marks chemistry laboratory upgrades at Northern New Mexico

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    College Ribbon cutting marks chemistry laboratory upgrades at Northern New Mexico College Community Connections: Your link to news and opportunities from Los Alamos National Laboratory Latest Issue: September 1, 2016 all issues All Issues » submit Ribbon cutting marks chemistry laboratory upgrades at Northern New Mexico College Los Alamos National Security, LLC provides support November 1, 2013 Ribbon cutting at Northern New Mexico College As others look on, Northern New Mexico College

  9. Small Towns Achieve Big Savings with Lighting Upgrades | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Towns Achieve Big Savings with Lighting Upgrades Small Towns Achieve Big Savings with Lighting Upgrades August 28, 2014 - 4:16pm Addthis A worker installs energy efficient lights as part of the Smart Lights for Smart Cities program. | Photo courtesy of Mid-America Regional Council. A worker installs energy efficient lights as part of the Smart Lights for Smart Cities program. | Photo courtesy of Mid-America Regional Council. Crystal McDonald Project Officer, Department of Energy.

  10. Energy Department Supports Efficiency Upgrades in Alaska's Lake and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Peninsula Borough | Department of Energy Supports Efficiency Upgrades in Alaska's Lake and Peninsula Borough Energy Department Supports Efficiency Upgrades in Alaska's Lake and Peninsula Borough March 24, 2016 - 4:48pm Addthis Insulation is a key element of weatherization because it provides resistance to heat flow which lowers a family’s heating and cooling costs. Insulation is especially important for homes in arctic climates, like this home in Alaska. The Energy Department's

  11. Scientific Opportunities and Challenges in the Upgraded National Spherical

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Torus Experiment | Princeton Plasma Physics Lab March 14, 2015, 9:30am to 11:00am Science On Saturday MBG Auditorium Scientific Opportunities and Challenges in the Upgraded National Spherical Torus Experiment Dr. Jonathan Menard, Principal Research Physicist PPPL Abstract: PDF icon Menard.pdf Science On Saturday, March 14, 2015, "Scientific Opportunities & Challenges in the Upgraded National Spherical Torus Experiment", Dr. Jonathan Menard, PPPL Contact Information Website:

  12. Webinar: "Upgrading Renewable and Sustainable Carbohydrates for the

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Production of High Energy Density Fuels" | Department of Energy "Upgrading Renewable and Sustainable Carbohydrates for the Production of High Energy Density Fuels" Webinar: "Upgrading Renewable and Sustainable Carbohydrates for the Production of High Energy Density Fuels" This webinar, part of the Biomass Program's bimonthly webinar series, featured presenters from Los Alamos National Laboratory who focused on high energy density fuels december2012_lanl_webinar.pdf

  13. Staged Upgrades as a Strategy for Residential Energy Efficiency

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Better Buildings Residential Network Peer Exchange Call Series: Staged Upgrades as a Strategy for Residential Energy Efficiency June 18, 2015 Call Slides and Discussion Summary Agenda  Call Logistics and Introductions  Residential Network and Peer Exchange Call Overview  Overview of DOE Staged Upgrades Initiative  Steve Dunn, U.S. Department of Energy  Participant Poll  Featured Presenters  Jennifer Parsons, United Illuminating Company, Southern Connecticut Gas, and

  14. Minto Upgrades Community Lodge with START Support | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Minto Upgrades Community Lodge with START Support Minto Upgrades Community Lodge with START Support October 20, 2014 - 5:00pm Addthis With DOE support, workers weatherize the exterior of the Lakeview Lodge in Minto, Alaska. Photo from Russell Snyder, Interior Regional Housing Authority, NREL 31796 With DOE support, workers weatherize the exterior of the Lakeview Lodge in Minto, Alaska. Photo from Russell Snyder, Interior Regional Housing Authority, NREL 31796 The Lakeview Lodge is the heart of

  15. Living Comfortably: A Consumer's Guide to Home Energy Upgrades |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Living Comfortably: A Consumer's Guide to Home Energy Upgrades Living Comfortably: A Consumer's Guide to Home Energy Upgrades March 7, 2013 - 3:15pm Addthis A weatherization worker drills holes to blow cellulose insulation in the interior walls of this home. | Photo courtesy of Dennis Schroeder, NREL A weatherization worker drills holes to blow cellulose insulation in the interior walls of this home. | Photo courtesy of Dennis Schroeder, NREL Dr. Richard Knaub Project

  16. Hydropower Advancement Project (HAP): Audits and Feasibility Studies for Capacity and Efficiency Upgrades

    Broader source: Energy.gov [DOE]

    Hydropower Advancement Project (HAP): Audits and Feasibility Studies for Capacity and Efficiency Upgrades

  17. Commissioning results from the recently upgraded RHIC LLRF system

    SciTech Connect (OSTI)

    Smith, K.S.; Harvey, M.; Hayes, T.; Narayan, G.; Severino, F.; Yuan, S.; Zaltsman, A.

    2011-03-28

    During RHIC Run 10, the first phase of the LLRF Upgrade was successfully completed. This involved replacing the aging VME based system with a modern digital system based on the recently developed RHIC LLRF Upgrade Platform, and commissioning the system as part of the normal RHIC start up process. At the start of Run 11, the second phase of the upgrade is underway, involving a significant expansion of both hardware and functionality. This paper will review the commissioning effort and provide examples of improvements in system performance, flexibility and scalability afforded by the new platform. The RHIC LLRF upgrade is based on the recently developed RHIC LLRF Upgrade Platform. The major design goals of the platform are: (1) Design a stand alone, generic, digital, modular control architecture which can be configured to satisfy all of the application demands we currently have, and which will be supportable and upgradeable into the foreseeable future; and (2) It should integrate seamlessly into existing controls infrastructure, be easy to deploy, provide access to all relevant control parameters (eliminate knobs), provide vastly improved diagnostic data capabilities, and permit remote reconfiguration. Although the system is still in its infancy, we think the initial commissioning results from RHIC indicate that these goals have been achieved, and that we've only begun to realize the benefits the platform provides.

  18. Upgrading heavy oil using slurry processes

    SciTech Connect (OSTI)

    Del Bianco, A.; Panariti, N.; Marchionna, M.

    1995-11-01

    There is a growing interest in processes capable of converting heavy feedstocks (petroleum residues and heavy oils) into lower boiling products of high quality. The operational problems of upgrading heavy feeds relate to the presence of sulfur, nitrogen, metals, and considerable amounts of Conradson carbon residue. An efficient residue conversion process must be able to reduce the molecular weight of the feedstocks to material with boiling points below 550 C, increase the H-to-C ratio of the refined product, and remove heteroatoms and metals. Whereas the molecular weight reduction is normally achieved by C-C bond cracking above 400 C, often in the presence of acid catalysts, a higher H-to-C ratio can be obtained by either the rejection of carbon (as in coking) or the addition of hydrogen (as in hydrogenation processes). Slurry processes combine the flexibility of the carbon rejection with the high performance of the hydrogen addition processes. The origin of slurry processes is the Bergius-Pier technology (1920--1930) for the conversion of heavy oils and coal into distillates. Whereas the original Bergius-Pier technology did not use a catalyst, small amounts of inexpensive additives or finely dispersed hydrogenation catalysts can be used to increase the rates of the desired reactions. Catalysts can also inhibit coke formation by physically interfering with the coalescence of mesophase, which is the precursor of solid coke. Catalysts are used to reduce the severity of the process and to improve the quality of the products. Most of the research carried out in the past decade in the field of slurry processes has dealt with the identification of more effective and/or less expensive catalysts and the technological problems related to their use. Here the authors discuss both subjects, describing the path from the fundamental chemistry of dispersed catalytic systems to the development and initial commercialization of slurry processes.

  19. Contractor Sales Training: Providing the Skills Necessary to Sell Comprehensive Home Energy Upgrades

    SciTech Connect (OSTI)

    Billingsley, Megan; Stuart, Elizabeth

    2011-08-17

    Many comprehensive home energy efficiency programs rely on contractors as the customer-facing ‘front line’ to sell energy improvements. Adding sales skills to contractors’ existing technical expertise is key to converting more assessments into comprehensive home energy upgrades. Leading programs recognize the need to support contractors with sales and business training to help them succeed and to support the growth of the home performance industry for the long term. A number of contractor sales training efforts are emerging, including some programs that are seeing encouraging early results.

  20. Electric Transmission System Workshop

    Broader source: Energy.gov (indexed) [DOE]

    Lauren Azar Senior Advisor to Secretary Chu November 2, 2012 Electric Transmission System ... Can we agree on several key design attributes for the future grid? Taking Action in the ...

  1. Downhole transmission system

    DOE Patents [OSTI]

    Hall, David R.; Fox, Joe

    2008-01-15

    A transmission system in a downhole component comprises a data transmission element in both ends of the downhole component. Each data transmission element houses an electrically conducting coil in a MCEI circular trough. An electrical conductor connects both the transmission elements. The electrical conductor comprises at least three electrically conductive elements insulated from each other. In the preferred embodiment the electrical conductor comprises an electrically conducting outer shield, an electrically conducting inner shield and an electrical conducting core. In some embodiments of the present invention, the electrical conductor comprises an electrically insulating jacket. In other embodiments, the electrical conductor comprises a pair of twisted wires. In some embodiments, the electrical conductor comprises semi-conductive material.

  2. Electricity Transmission, A Primer

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... the power from low-cost, mine- mouth coal power plants and wind generators in Wyoming. ... As a result, the transmission system helps to insulate electricity consumers from the ...

  3. Down hole transmission system

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT)

    2007-07-24

    A transmission system in a downhole component comprises a data transmission element in both ends of the downhole component. Each data transmission element houses an electrically conducting coil in a MCEI circular trough. The electrically conducting coil comprises at least two generally fractional loops. In the preferred embodiment, the transmission elements are connected by an electrical conductor. Preferably, the electrical conductor is a coaxial cable. Preferably, the MCEI trough comprises ferrite. In the preferred embodiment, the fractional loops are connected by a connecting cable. In one aspect of the present invention, the connecting cable is a pair of twisted wires. In one embodiment the connecting cable is a shielded pair of twisted wires. In another aspect of the present invention, the connecting cable is a coaxial cable. The connecting cable may be disposed outside of the MCEI circular trough.

  4. Transmission Grid Integration

    Office of Energy Efficiency and Renewable Energy (EERE)

    The levels of solar energy penetration envisioned by the DOE SunShot Initiative must be interconnected effectively onto the transmission grid. This interconnection requires an in-depth...

  5. Transmission SEAB Presentation

    Broader source: Energy.gov (indexed) [DOE]

    "05 * Nine Agency MOU - Oct. 2009 * Transmission Cabinet * Designated 7 Pilot Projects DOD CEQ FERC USDA DOE ACHP EPA DOI DOC RRTT Pilot Projects RRTT Rapid Response Team for ...

  6. Transmission Developers Inc.

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ' % ~ Transmission Developers Inc. July 7, 2011 Mr. Anthony J. Como Director, Permitting and Siting Office ofElectricity Delivery and Energy Reliability (OE-20) U.S. Department of Energy 1000 Independence A venue SW, Room 8G-024 Washington, D.C. 20585 Subject: Champlain Hudson Power Express Project U.S. Department of Energy Presidential Permit Application PP-362 Dear Mr. Como: On January 25, 2010, Transmission Developers, Inc. ("TDI'' or "Applicants") submitted on behalf of

  7. EIS-0411: Transmission Agency of Northern California Transmission Project

    Broader source: Energy.gov [DOE]

    This EIS is for the Western Area Power Administration construction, operation, and maintenance of the proposed transmission agency of Northern California Transmission Project, California.

  8. Energy Transmission and Infrastructure

    SciTech Connect (OSTI)

    Mathison, Jane

    2012-12-31

    The objective of Energy Transmission and Infrastructure Northern Ohio (OH) was to lay the conceptual and analytical foundation for an energy economy in northern Ohio that will: • improve the efficiency with which energy is used in the residential, commercial, industrial, agricultural, and transportation sectors for Oberlin, Ohio as a district-wide model for Congressional District OH-09; • identify the potential to deploy wind and solar technologies and the most effective configuration for the regional energy system (i.e., the ratio of distributed or centralized power generation); • analyze the potential within the district to utilize farm wastes to produce biofuels; • enhance long-term energy security by identifying ways to deploy local resources and building Ohio-based enterprises; • identify the policy, regulatory, and financial barriers impeding development of a new energy system; and • improve energy infrastructure within Congressional District OH-09. This objective of laying the foundation for a renewable energy system in Ohio was achieved through four primary areas of activity: 1. district-wide energy infrastructure assessments and alternative-energy transmission studies; 2. energy infrastructure improvement projects undertaken by American Municipal Power (AMP) affiliates in the northern Ohio communities of Elmore, Oak Harbor, and Wellington; 3. Oberlin, OH-area energy assessment initiatives; and 4. a district-wide conference held in September 2011 to disseminate year-one findings. The grant supported 17 research studies by leading energy, policy, and financial specialists, including studies on: current energy use in the district and the Oberlin area; regional potential for energy generation from renewable sources such as solar power, wind, and farm-waste; energy and transportation strategies for transitioning the City of Oberlin entirely to renewable resources and considering pedestrians, bicyclists, and public transportation as well as drivers

  9. National transmission grid study

    SciTech Connect (OSTI)

    Abraham, Spencer

    2003-05-31

    The National Energy Policy Plan directed the U.S. Department of Energy (DOE) to conduct a study to examine the benefits of establishing a national electricity transmission grid and to identify transmission bottlenecks and measures to address them. DOE began by conducting an independent analysis of U.S. electricity markets and identifying transmission system bottlenecks using DOE’s Policy Office Electricity Modeling System (POEMS). DOE’s analysis, presented in Section 2, confirms the central role of the nation’s transmission system in lowering costs to consumers through increased trade. More importantly, DOE’s analysis also confirms the results of previous studies, which show that transmission bottlenecks and related transmission system market practices are adding hundreds of millions of dollars to consumers’ electricity bills each year. A more detailed technical overview of the use of POEMS is provided in Appendix A. DOE led an extensive, open, public input process and heard a wide range of comments and recommendations that have all been considered.1 More than 150 participants registered for three public workshops held in Detroit, MI (September 24, 2001); Atlanta, GA (September 26, 2001); and Phoenix, AZ (September 28, 2001).

  10. Trends In U.S. Electric Power Transmission

    SciTech Connect (OSTI)

    NONE

    2007-11-15

    The report provides an overview of the changes that are occurring in the industry to implement the goals of improved reliability and reduced congestion costs. As the electric industry works to become a more efficient market, transmission stands as a key link between the competitive generation and the regulated distribution sectors. In this role as a key link, transmission is a major focus of government efforts to improve reliability and reduce congestion costs. The scope of the report is to analyze the dominant reliability, investment, siting, and competition/open access trends that are occurring in the domestic electric transmission industry. Topics covered include: the impact of the 2003 Northeast blackout on reliability rules; the move from voluntary to mandatory reliability standards; the advent of real-time transmission system monitoring; ISO/RTO efforts to improve system reliability; the drivers of government intervention in transmission investment; the move towards incentive-based rates for transmission investment; legislative and regulatory efforts to spur transmission investment to support renewable energy resources; the emergence of merchant transmission; the need for federal backstop authority on regional transmission projects; the designation of national interest electric transmission corridors; FERC Orders on siting transmission; the need for changes in open access and competition regulations; FERC efforts to increase open access and competition; legislative efforts to increase competition; and, current competitive issues in the industry.

  11. UNIVERSITY PARK SCHOOLS SMALL TOWNS ON UPGRADES

    Broader source: Energy.gov [DOE]

    University Park, Maryland, a town of only 2,500 residents, sought to address the energy efficiency needs of its homeowners. To create a model for other resource-constrained small communities...

  12. Transmission Workshop | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    DOE Grid Tech Team » Activities/Outreach » GTT Activities » Transmission Workshop Transmission Workshop Transmission Workshop GTT Transmission Workshop - November 1-2, 2012 On November 1-2, 2012, the GTT presented a workshop on grid integration on the transmission system at the DoubleTree Crystal City near Washington, DC. A draft of the DOE Action Plan Addressing the Electricity Transmission System was discussed during the workshop, which addressed the challenges and opportunities presented

  13. Production and Upgrading of Infrastructure Compatible Bio-Oil with VTT Presentation for BETO 2015 Project Peer Review

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Production and Upgrading of Infrastructure Compatible Bio-Oil with VTT March 25, 2015 Thermochemical Conversion Douglas C. Elliott Pacific Northwest National Laboratory This presentation does not contain any proprietary, confidential, or otherwise restricted information Goal Statement Problem Statement: Methods with higher yields or less expensive operation are needed to produce liquid fuels from biomass Goal: Validate, in collaboration with international process technology leaders, integrated

  14. ITC Transmission | Open Energy Information

    Open Energy Info (EERE)

    ITC Transmission Jump to: navigation, search Name: ITC Transmission Place: Michigan Phone Number: Western Michigan Office: (269) 792-7223 -- Northern Michigan Office: (989)...

  15. High Resolution BPM Upgrade for the ATF Damping Ring at KEK

    SciTech Connect (OSTI)

    Eddy, N.; Briegel, C.; Fellenz, B.; Gianfelice-Wendt, E.; Prieto, P.; Rechenmacher, R.; Semenov, A.; Voy, D.; Wendt, M.; Zhang, D.; Terunuma, N.; /KEK, Tsukuba

    2011-08-17

    A beam position monitor (BPM) upgrade at the KEK Accelerator Test Facility (ATF) damping ring has been accomplished, carried out by a KEK/FNAL/SLAC collaboration under the umbrella of the global ILC R&D effort. The upgrade consists of a high resolution, high reproducibility read-out system, based on analog and digital down-conversion techniques, digital signal processing, and also implements a new automatic gain error correction schema. The technical concept and realization as well as results of beam studies are presented. The next generation of linear colliders require ultra-low vertical emittance of <2 pm-rad. The damping ring at the KEK Accelerator Test Facility (ATF) is designed to demonstrate this mission critical goal. A high resolution beam position monitor (BPM) system for the damping ring is one of the key tools for realizing this goal. The BPM system needs to provide two distnict measurements. First, a very high resolution ({approx}100-200nm) closed-orbit measurement which is averaged over many turns and realized with narrowband filter techniques - 'narrowband mode'. This is needed to monitor and steer the beam along an optimum orbit and to facilitate beam-based alignment to minimize non-linear field effects. Second, is the ability to make turn by turn (TBT) measurements to support optics studies and corrections necessary to achieve the design performance. As the TBT measurement necessitates a wider bandwidth, it is often referred to as 'wideband mode'. The BPM upgrade was initiated as a KEK/SLAC/FNAL collaboration in the frame of the Global Design Initiative of the International Linear Collider. The project was realized and completed using Japan-US funds with Fermilab as the core partner.

  16. Transmission pricing is the key to generation competition

    SciTech Connect (OSTI)

    Rozier, G.C.

    1994-12-31

    A slide presentation is given on tomorrow`s pricing of power transmission. Topics discussed include; distance factors, loop flow compensation, coordinated planning function, principles of comparability and restructuring issues. Financial stress for the utilities is anticipated in the transistion to unbundling the electric power industry with juridictional segmentation by Federal and State Regulators. Transmission will be the sole regulatory responsibility of the Federal Energy Resource Commission. Pricing policies for transmission will be critical to ensure that customers are treated equitably, investors are adequately compensated and expansion of transmission capability facilitates competition for power generation. A new pricing method is needed that allocates transmission costs in proportion to usage of facilities. Problems with current transmission pricing policies include; not being sensitive to distance, systems are path based, loop flows are ignored, cross subsidization and costs not recovered. Examples of Transmission Cost Actural Path Pricing techniques are given.

  17. A new hydrocracking catalyst for heavy oil upgrading

    SciTech Connect (OSTI)

    Itoh, T. )

    1987-04-01

    In comparison with ordinary oil, tar sands bitumen and vacuum residue contain large quantities of impurities such as asphaltene, heavy metal compounds, sulfur, and nitrogen, which are obstacles to upgrading the refining process. Therefore, these types of materials are extremely difficult to treat with existing refining technologies. In order to upgrade oil feedstocks that are of poor quality, such as tar sands bitumen, new upgrading technologies must be established. In this paper, the author discusses first, the results of catalyst screening, second, the factors of the active catalyst, and finally, the performance of a semi-industrially produced catalyst. The catalyst has high middle-distillate yield, coke plus gum (coke precursors) suppressing ability, low hydrogen consumption and mechanical strength and high temperature stability in slurry reactors.

  18. Heavy oil upgrading using an integrated gasification process

    SciTech Connect (OSTI)

    Quintana, M.E.; Falsetti, J.S.

    1995-12-31

    The value of abundant, low-grade heavy crude oil reserves can be enhanced by appropriate upgrade processing at the production site to yield marketable refinery feedstocks or ultimate products. One of the upgrading process sequences most commonly considered involves vacuum distillation followed by a bottoms processing step such as solvent deasphalting or coking. These schemes can be further enhanced with the addition of a gasification step to convert the unsaleable, bottom-of-the-barrel residues into useful products, such as high-purity hydrogen for hydrotreating, electrical power, steam for enhanced oil recovery and distillation, etc. This paper describes the Texaco Gasification Process and the T-STARs hydrotreating process, and their application in an integrated upgrade processing scheme in which an optimal, virtually bottomless oil utilization can be achieved. Illustrative examples of this integration are provided with comparative economic information.

  19. Technology needs for decommissioning and decontamination

    SciTech Connect (OSTI)

    Bundy, R.D.; Kennerly, J.M.

    1993-12-01

    This report summarizes the current view of the most important decontamination and decommissioning (D & D) technology needs for the US Department of Energy facilities for which the D & D programs are the responsibility of Martin Marietta Energy Systems, Inc. The source of information used in this assessment was a survey of the D & D program managers at each facility. A summary of needs presented in earlier surveys of site needs in approximate priority order was supplied to each site as a starting point to stimulate thinking. This document reflects a brief initial assessment of ongoing needs; these needs will change as plans for D & D are finalized, some of the technical problems are solved through successful development programs, and new ideas for D and D technologies appear. Thus, this assessment should be updated and upgraded periodically, perhaps, annually. This assessment differs from others that have been made in that it directly and solely reflects the perceived need for new technology by key personnel in the D & D programs at the various facilities and does not attempt to consider the likelihood that these technologies can be successfully developed. Thus, this list of technology needs also does not consider the cost, time, and effort required to develop the desired technologies. An R & D program must include studies that have a reasonable chance for success as well as those for which there is a high need. Other studies that considered the cost and probability of successful development as well as the need for new technology are documented. However, the need for new technology may be diluted in such studies; this document focuses only on the need for new technology as currently perceived by those actually charged with accomplishing D & D.

  20. Transmission line capital costs

    SciTech Connect (OSTI)

    Hughes, K.R.; Brown, D.R.

    1995-05-01

    The displacement or deferral of conventional AC transmission line installation is a key benefit associated with several technologies being developed with the support of the U.S. Department of Energy`s Office of Energy Management (OEM). Previous benefits assessments conducted within OEM have been based on significantly different assumptions for the average cost per mile of AC transmission line. In response to this uncertainty, an investigation of transmission line capital cost data was initiated. The objective of this study was to develop a database for preparing preliminary estimates of transmission line costs. An extensive search of potential data sources identified databases maintained by the Bonneville Power Administration (BPA) and the Western Area Power Administration (WAPA) as superior sources of transmission line cost data. The BPA and WAPA data were adjusted to a common basis and combined together. The composite database covers voltage levels from 13.8 to 765 W, with cost estimates for a given voltage level varying depending on conductor size, tower material type, tower frame type, and number of circuits. Reported transmission line costs vary significantly, even for a given voltage level. This can usually be explained by variation in the design factors noted above and variation in environmental and land (right-of-way) costs, which are extremely site-specific. Cost estimates prepared from the composite database were compared to cost data collected by the Federal Energy Regulatory Commission (FERC) for investor-owned utilities from across the United States. The comparison was hampered because the only design specifications included with the FERC data were voltage level and line length. Working within this limitation, the FERC data were not found to differ significantly from the composite database. Therefore, the composite database was judged to be a reasonable proxy for estimating national average costs.

  1. Energy Department, Arizona Utilities Announce Transmission Infrastructure Project Energization

    Broader source: Energy.gov [DOE]

    Today, the Department of Energy’s Western Area Power Administration (Western) and a group of Arizona utilities celebrated the energizing of a new transmission infrastructure project that will serve the state’s growing electrical energy needs, attract renewable energy development to the area, and strengthen the transmission system in the Southwestern United States.

  2. National Spherical Torus Experiment Upgrade (NSTX-U) | Princeton Plasma

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Physics Lab National Spherical Torus Experiment Upgrade (NSTX-U) NSTX-U The National Spherical Torus Experiment Upgrade (NSTX-U) is an innovative magnetic fusion device that was constructed by the Princeton Plasma Physics Laboratory (PPPL) in collaboration with the Oak Ridge National Laboratory, Columbia University, and the University of Washington at Seattle. History First plasma was obtained on NSTX on Friday, February 12, 1999 at 6:06 p.m. NSTX-U is being used to study the physics

  3. HOM Survey of the First CEBAF Upgrade Style Cavity Pair

    SciTech Connect (OSTI)

    Marhauser, Frank; Davis, G; Drury, Michael; Grenoble, Christiana; Hogan, John; Manus, Robert; Preble, Joseph; Reece, Charles; Rimmer, Robert; Tian, Kai; Wang, Haipeng

    2009-05-01

    The planned upgrade of the Continuous Electron Beam Accelerator Facility (CEBAF) at the Thomas Jefferson National Accelerator Laboratory (JLab) requires ten new superconducting rf (SRF) cavity cryomodules to double the beam energy to the envisaged 12 GeV. Adequate cavity Higher Order Mode (HOM) suppression is essential to avoid multipass, multibunch beam break-up (BBU) instabilities of the recirculating beam. We report on detailed HOM surveys performed for the first two upgrade style cavities tested in a dedicated cavity pair cryomodule at 2K. The safety margin to the BBU threshold budget at 12 GeV has been assessed.

  4. Status of the ATF Damping Ring BPM Upgrade Project

    SciTech Connect (OSTI)

    Briegel, C.; Eddy, N.; Haynes, B.; May, J.; McCormick, D.; Nelson, J.; Nicklaus, D.; Prieto, P.; Rechenmacher, R.; Smith, T.; Teranuma, N.; Urakawa, J.; Voy, D.; Wendt, M.; Woodley, M.; /SLAC

    2011-12-01

    A substantial upgrade of the beam position monitors (BPM) at the ATF (Accelerator Test Facility) damping ring is currently in progress. Implementing digital read-out signal processing techniques in line with an optimized, low-noise analog downconverter, a resolution well below 1 mum could be demonstrated at 20 (of 96) upgraded BPM stations. The narrowband, high resolution BPM mode permits investigation of all types of non-linearities, imperfections and other obstacles in the machine which may limit the very low target aimed vertical beam emittance of < 2 pm. The technical status of the project, first beam measurements and an outlook to it's finalization are presented.

  5. Optical Metrology Lab Receives New Funding for Upgrades

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Optical Metrology Lab Receives New Funding for Upgrades Optical Metrology Lab Receives New Funding for Upgrades Print The Optical Metrology Lab (OML) at the ALS is renowned for its precision and technical expertise in metrology of x-ray optics. It has achieved this notoriety with only two full-time staff members and extremely limited laboratory facilities. Now, with new funding from the DOE that provides $1.2M to build a new clean room laboratory with environmental controls, and the promise of

  6. Optical Metrology Lab Receives New Funding for Upgrades

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Optical Metrology Lab Receives New Funding for Upgrades Print The Optical Metrology Lab (OML) at the ALS is renowned for its precision and technical expertise in metrology of x-ray optics. It has achieved this notoriety with only two full-time staff members and extremely limited laboratory facilities. Now, with new funding from the DOE that provides $1.2M to build a new clean room laboratory with environmental controls, and the promise of $1.4M to upgrade and replace outdated instrumentation,

  7. Optical Metrology Lab Receives New Funding for Upgrades

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Optical Metrology Lab Receives New Funding for Upgrades Print The Optical Metrology Lab (OML) at the ALS is renowned for its precision and technical expertise in metrology of x-ray optics. It has achieved this notoriety with only two full-time staff members and extremely limited laboratory facilities. Now, with new funding from the DOE that provides $1.2M to build a new clean room laboratory with environmental controls, and the promise of $1.4M to upgrade and replace outdated instrumentation,

  8. Michigan County's Energy Upgrades Back on Track | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    County's Energy Upgrades Back on Track Michigan County's Energy Upgrades Back on Track August 26, 2010 - 1:00pm Addthis Michigan's Shiawassee County, located in the 'middle of the mitten,' is using over $300,000 in Recovery Act funds to perform ene Michigan's Shiawassee County, located in the 'middle of the mitten,' is using over $300,000 in Recovery Act funds to perform ene Stephen Graff Former Writer & editor for Energy Empowers, EERE Just like energy, an energy audit is a terrible thing

  9. Phoenix Overcomes Barriers and Energizes Homeowners to Make Upgrades

    Broader source: Energy.gov [DOE]

    Energize Phoenix is saving energy and money for homeowners, generating jobs, and transforming a diverse array of neighborhoods along a 10-mile stretch of the city's light rail line. Energize Phoenix's residential programs are open to homeowners of all income levels, but low-to-moderate income homeowners may realize greater benefits from energy efficiency upgrades because their homes often have older, inefficient equipment. Because upfront costs can deter low- to moderate-income residents from making upgrades, Energize Phoenix developed two programs to specifically address energy efficiency with this audience.

  10. Microsoft Word - Facility Upgrades 11-21-08

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Energy Carlsbad Field Office Waste Isolation Pilot Plant P.O. Box 3090 Carlsbad, New Mexico 88221 Media Contact: Roger Nelson U.S. DOE Carlsbad Field Office (575) 234-7213 www.wipp.energy.gov For Immediate Release WIPP Sets Schedule for Facility Upgrades CARLSBAD, N.M., November 21, 2008 - The U.S. Department of Energy's (DOE) Carlsbad Field Office (CBFO) plans to perform some of the most extensive facility upgrades to the Waste Isolation Pilot Plant (WIPP) since its initial construction. The

  11. Upgrading RESRAD-RDD and Planning for Improvised Nuclear Device

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Incidents--The RESRAD-RDD&IND | Department of Energy Upgrading RESRAD-RDD and Planning for Improvised Nuclear Device Incidents--The RESRAD-RDD&IND Upgrading RESRAD-RDD and Planning for Improvised Nuclear Device Incidents--The RESRAD-RDD&IND Charley Yu*, Argonne National Laboratory ; Carlos Corredor, U.S. Department of Energy; Jing-Jy Cheng, Argonne National Laboratory; Sunita Kamboj, Argonne National Laboratory; David LePoire, Argonne National Laboratory; Paul Flood, Argonne

  12. EIS-0173: Bonneville Power Administration/Puget Power Northwest Washington Transmission Project

    Broader source: Energy.gov [DOE]

    The Bonneville Power Administration (BPA) prepared this environmental impact statement to analyze the environmental impacts of an upgrade that BPA and Puget Sound Power & Light Company are considering implementing on the existing high-voltage transmission system in the Whatcom and Skagit Counties area of the State of Washington, between the towns of Custer and Sedro Woolley, including some areas within the City of Bellingham, starting in 1995.

  13. Impact of Utility-Scale Distributed Wind on Transmission-Level System Operations

    SciTech Connect (OSTI)

    Brancucci Martinez-Anido, C.; Hodge, B. M.

    2014-09-01

    This report presents a new renewable integration study that aims to assess the potential for adding distributed wind to the current power system with minimal or no upgrades to the distribution or transmission electricity systems. It investigates the impacts of integrating large amounts of utility-scale distributed wind power on bulk system operations by performing a case study on the power system of the Independent System Operator-New England (ISO-NE).

  14. EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild Project, Larimer County, Colorado

    Office of Energy Efficiency and Renewable Energy (EERE)

    Western Area Power Administration (Western) – with USDA Forest Service, Arapaho and Roosevelt National Forest, as a cooperating agency – is preparing an EIS that analyzes the potential environmental impacts of a proposal to rebuild and upgrade two 115-kilovolt single-circuit transmission lines between the Flatiron Substation and the intersection of Mall Road and U.S. Highway 36 in Estes Park, Larimer County, Colorado.

  15. Printed circuit dispersive transmission line

    DOE Patents [OSTI]

    Ikezi, H.; Lin-Liu, Y.R.; DeGrassie, J.S.

    1991-08-27

    A printed circuit dispersive transmission line structure is disclosed comprising an insulator, a ground plane formed on one surface of the insulator, a first transmission line formed on a second surface of the insulator, and a second transmission line also formed on the second surface of the insulator and of longer length than the first transmission line and periodically intersecting the first transmission line. In a preferred embodiment, the transmission line structure exhibits highly dispersive characteristics by designing the length of one of the transmission line between two adjacent periodic intersections to be longer than the other. 5 figures.

  16. Printed circuit dispersive transmission line

    DOE Patents [OSTI]

    Ikezi, Hiroyuki; Lin-Liu, Yuh-Ren; DeGrassie, John S.

    1991-01-01

    A printed circuit dispersive transmission line structure is disclosed comprising an insulator, a ground plane formed on one surface of the insulator, a first transmission line formed on a second surface of the insulator, and a second transmission line also formed on the second surface of the insulator and of longer length than the first transmission line and periodically intersecting the first transmission line. In a preferred embodiment, the transmission line structure exhibits highly dispersive characteristics by designing the length of one of the transmission line between two adjacent periodic intersections to be longer than the other.

  17. Autonomous data transmission apparatus

    DOE Patents [OSTI]

    Kotlyar, O.M.

    1997-03-25

    A autonomous borehole data transmission apparatus is described for transmitting measurement data from measuring instruments at the downhole end of a drill string by generating pressure pulses utilizing a transducer longitudinally responsive to magnetic field pulses caused by electrical pulses corresponding to the measured downhole parameters. 4 figs.

  18. Autonomous data transmission apparatus

    DOE Patents [OSTI]

    Kotlyar, Oleg M. (4675 W. 3825 S, Salt Lake City, UT 84120)

    1997-01-01

    A autonomous borehole data transmission apparatus for transmitting measurement data from measuring instruments at the downhole end of a drill string by generating pressure pulses utilizing a transducer longitudinally responsive to magnetic field pulses caused by electrical pulses corresponding to the measured downhole parameters.

  19. Borehole data transmission apparatus

    DOE Patents [OSTI]

    Kotlyar, Oleg M.

    1993-01-01

    A borehole data transmission apparatus whereby a centrifugal pump impeller(s) is used to provide a turbine stage having substantial pressure characteristics in response to changing rotational speed of a shaft for the pressure pulsing of data from the borehole through the drilling mud to the surface of the earth.

  20. Borehole data transmission apparatus

    DOE Patents [OSTI]

    Kotlyar, O.M.

    1993-03-23

    A borehole data transmission apparatus is described whereby a centrifugal pump impeller(s) is used to provide a turbine stage having substantial pressure characteristics in response to changing rotational speed of a shaft for the pressure pulsing of data from the borehole through the drilling mud to the surface of the earth.

  1. OVERVIEW OF A RECONFIGURABLE SIMULATOR FOR MAIN CONTROL ROOM UPGRADES IN NUCLEAR POWER PLANTS

    SciTech Connect (OSTI)

    Ronald L. Boring

    2012-10-01

    This paper provides background on a reconfigurable control room simulator for nuclear power plants. The main control rooms in current nuclear power plants feature analog technology that is growing obsolete. The need to upgrade control rooms serves the practical need of maintainability as well as the opportunity to implement newer digital technologies with added functionality. There currently exists no dedicated research simulator for use in human factors design and evaluation activities for nuclear power plant modernization in the U.S. The new research simulator discussed in this paper provides a test bed in which operator performance on new control room concepts can be benchmarked against existing control rooms and in which new technologies can be validated for safety and usability prior to deployment.

  2. Puget Sound Area Electric Reliability Plan. Appendix E: Transmission Reinforcement Analysis : Draft Environmental Impact Statement.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1991-09-01

    Five transmission line options and several reactive (voltage support) options are presently being considered as possible solutions to the PSAERP by the Transmission Team. The first two line options would be built on new rights-of way adjacent (as much as possible) to existing corridors. The reactive options would optimize the existing transmission system capability by adding new stations for series capacitors and/or switchgear. The other three line options are rebuilds or upgrades of existing cross mountain transmission lines. These options are listed below and include a preliminary assessment of the additional transmission system reinforcement required to integrate the new facilities into the existing transmission system. These options were derived from earlier study work that was summarized in Puget Sound Reinforcement Transmission Options'' and New Cross Mountain Transmission Line Alternative: The Crosstie'', which are attached. The initial Transmission Options study report recognized the value to system performance of adding an entirely new circuit rather than rebuilding an existing one. However, siting realities require that rebuild options be considered. Typically, the most attractive rebuild options would be the lowest capacity (lowest voltage) circuits. But because of corridor location, length and terminal proximity, the rebuild options listed below appear to be the most promising. Schematic diagrams and QV Curves of each option are also attached. It should be noted that Snoqualmie and Echo Lake refer to the same station east of Puget Sound and Naneum and Kittitas refer to the same station in the Ellensburg area. 100 figs., 20 tabs.

  3. Cultural Resource Investigation for the Materials and Fuels Complex Wastewater System Upgrade at the Idaho National Laboratory

    SciTech Connect (OSTI)

    Brenda R. Pace; Julie B raun Williams; Hollie Gilbert; Dino Lowrey; Julie Brizzee

    2010-05-01

    The Materials and Fuels Complex (MFC) located in Bingham County at the Idaho National Laboratory (INL) in southeastern Idaho is considering several alternatives to upgrade wastewater systems to meet future needs at the facility. In April and May of 2010, the INL Cultural Resource Management Office conducted archival searches, archaeological field surveys, and coordination with the Shoshone-Bannock Tribes to identify cultural resources that may be adversely affected by the proposed construction and to provide recommendations to protect any resources listed or eligible for listing on the National Register of Historic Places. These investigations showed that one National Register-eligible archaeological site is located on the boundary of the area of potential effects for the wastewater upgrade. This report outlines protective measures to help ensure that this resource is not adversely affected by construction.

  4. Technologies for Upgrading Light Water Reactor Outlet Temperature

    SciTech Connect (OSTI)

    Daniel S. Wendt; Piyush Sabharwall; Vivek Utgikar

    2013-07-01

    Nuclear energy could potentially be utilized in hybrid energy systems to produce synthetic fuels and feedstocks from indigenous carbon sources such as coal and biomass. First generation nuclear hybrid energy system (NHES) technology will most likely be based on conventional light water reactors (LWRs). However, these LWRs provide thermal energy at temperatures of approximately 300°C, while the desired temperatures for many chemical processes are much higher. In order to realize the benefits of nuclear hybrid energy systems with the current LWR reactor fleets, selection and development of a complimentary temperature upgrading technology is necessary. This paper provides an initial assessment of technologies that may be well suited toward LWR outlet temperature upgrading for powering elevated temperature industrial and chemical processes during periods of off-peak power demand. Chemical heat transformers (CHTs) are a technology with the potential to meet LWR temperature upgrading requirements for NHESs. CHTs utilize chemical heat of reaction to change the temperature at which selected heat sources supply or consume thermal energy. CHTs could directly utilize LWR heat output without intermediate mechanical or electrical power conversion operations and the associated thermodynamic losses. CHT thermal characteristics are determined by selection of the chemical working pair and operating conditions. This paper discusses the chemical working pairs applicable to LWR outlet temperature upgrading and the CHT operating conditions required for providing process heat in NHES applications.

  5. Final Technical Report. Upgrades to Alabama Power Company Hydroelectric Developments

    SciTech Connect (OSTI)

    Crew, James F.; Johnson, Herbie N.

    2015-03-31

    From 2010 to 2014, Alabama Power Company (“Alabama Power”) performed upgrades on four units at three of the hydropower developments it operates in east-central Alabama under licenses issued by the Federal Energy Regulatory Commission (“FERC”). These three hydropower developments are located on the Coosa River in Coosa, Chilton, and Elmore counties in east-central Alabama.

  6. Role of fuel upgrading for industry and residential heating

    SciTech Connect (OSTI)

    Merriam, N.W.; Gentile, R.H.

    1995-12-01

    The Koppleman Series C Process is presently being used in pilot plant tests with Wyoming coal to upgrade the Powder River Basin coal containing 30 wt% moisture and having a heating value of 8100 Btu/lb to a product containing less than 1 wt% moisture and having a heating value of 12,200 Btu/lb. This process is described.

  7. T Plant secondary containment and leak detection upgrades

    SciTech Connect (OSTI)

    Carlson, T.A.

    1995-10-19

    The W-259 project will provide upgrades to the 2706-T/TA Facility to comply with Federal and State of Washington environmental regulations for secondary containment and leak detection. The project provides decontamination activities supporting the environmental restoration mission and waste management operations on the Hanford Site.

  8. Apparatus for upgrading heavy hydrocarbons employing a diluent

    SciTech Connect (OSTI)

    Calderon, J. L.; Layrisse, I.

    1985-06-04

    Apparatus for upgrading heavy hydrocarbonaceous materials for making coke suitable for metallurgical purposes comprises mixing the heavy hydrocarbonaceous materials with a diluent having a closely controlled boiling range so as to facilitate transport, dehydration and desalting of the crude oil. In addition, the diluent aids in controlling temperature and residence time of the crude thereby avoiding premature decomposition.

  9. Combined process for heavy oil, upgrading and synthetic fuel production

    SciTech Connect (OSTI)

    Polomski, R.E.

    1984-06-05

    A process for upgrading heavy oil to fuel products comprises deasphalting the heavy oil with an oxygenated solvent and simultaneously converting the oxygenated solvent and deasphalted oil over a ZSM-5 type catalyst to produce gasoline and distillate boiling range hydrocarbons.

  10. Process for upgrading heavy hydrocarbons employing a diluent

    SciTech Connect (OSTI)

    Calderon, J.L.; Layrisse, I.

    1984-06-19

    A process for upgrading heavy hydrocarbonaceous materials for making coke suitable for metallurgical purposes comprises mixing the heavy hydrocarbonaceous materials with a diluent having a closely controlled boiling range so as to facilitate transport, dehydration and desalting of the crude oil. In addition, the diluent aids in controlling temperature and residence time of the crude thereby avoiding premature decomposition.

  11. Upgrading heavy hydrocarbons with supercritical water and light olefins

    SciTech Connect (OSTI)

    Paspek, S. C. Jr.

    1984-11-20

    Heavy hydrocarbons are upgraded and cracked in a process comprising contacting the heavy hydrocarbons with olefins containing 5 or less carbon atoms and a solvent, at a temperature both sufficient for cracking and greater than or equal to the critical temperature of the solvent.

  12. Financing Energy Upgrades for K-12 School Districts

    Broader source: Energy.gov [DOE]

    This guide focuses on clean energy financing options for school administrators, facility managers, and other K-12 school decision makers who are considering investments in high performance school projects. It focuses on comprehensive energy upgrades and walks through the financing options available to K-12 schools and provides case studies of six school districts from around the country.

  13. Employee-Focused Structure Helps Produce Upgrades for Contractor

    Office of Energy Efficiency and Renewable Energy (EERE)

    Progressive Building Solutions, an energy efficiency contractor participating in Seattle, Washington's Community Power Works program, has an intriguing model to help its employees feel connected to the company's success—employees are part owners. The company's creator, Suraj Lobo, built Progressive Energy Solutions around three pillars: employee ownership; development of energy efficiency best practices; and superior energy upgrade work.

  14. Residual oil upgrading utilizing fixed bed hydroprocessing technology

    SciTech Connect (OSTI)

    Hohnholt, J.; Fausto, C.

    1985-01-01

    Saber Refinery embarked upon major residual oil upgrading project in an effort to convert heavy atmospheric resids into gasoline and other marketable products. Selection of resid hydroprocessing as an HOC feed preparation unit was necessary for removal of impurities which include organic metallic compounds, nitrogen and sulfur, while enhancing feedstock crackability.

  15. Recent Upgrade of the Klystron Modulator at SLAC

    SciTech Connect (OSTI)

    Nguyen, M.N.; Burkhart, C.P.; Lam, B.K.; Morris, B.; /SLAC

    2011-11-04

    The SLAC National Accelerator Laboratory employs 244 klystron modulators on its two-mile-long linear accelerator that has been operational since the early days of the SLAC establishment in the sixties. Each of these original modulators was designed to provide 250 kV, 262 A and 3.5 {mu}S at up to 360 pps using an inductance-capacitance resonant charging system, a modified type-E pulse-forming network (PFN), and a pulse transformer. The modulator internal control comprised of large step-start resistor-contactors, vacuum-tube amplifiers, and 120 Vac relays for logical signals. A major, power-component-only upgrade, which began in 1983 to accommodate the required beam energy of the SLAC Linear Collider (SLC) project, raised the modulator peak output capacity to 360 kV, 420 A and 5.0 {mu}S at a reduced pulse repetition rate of 120 pps. In an effort to improve safety, performance, reliability and maintainability of the modulator, this recent upgrade focuses on the remaining three-phase AC power input and modulator controls. The upgrade includes the utilization of primary SCR phase control rectifiers, integrated fault protection and voltage regulation circuitries, and programmable logic controllers (PLC) -- with an emphasis on component physical layouts for safety and maintainability concerns. In this paper, we will describe the design and implementation of each upgraded component in the modulator control system. We will also report the testing and present status of the modified modulators.

  16. Solar Classroom Update: Making Clean Energy Upgrades a Back-to...

    Energy Savers [EERE]

    Classroom Update: Making Clean Energy Upgrades a Back-to-School Priority Solar Classroom Update: Making Clean Energy Upgrades a Back-to-School Priority August 21, 2013 - 2:52pm ...

  17. Building Value with Energy-Saving Upgrades in Homes and Businesses...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Building Value with Energy-Saving Upgrades in Homes and Businesses Building Value with Energy-Saving Upgrades in Homes and Businesses July 12, 2011 - 10:09am Addthis Eric Barendsen...

  18. The JLAB 12 GeV Energy Upgrade of CEBAF (Conference) | SciTech...

    Office of Scientific and Technical Information (OSTI)

    This presentation should describe the progress of the 12GeV Upgrade of CEBAF at Jefferson Lab. The status of the upgrade should be presented as well as details on the construction, ...

  19. Bioenergy Technologies Office R&D Pathways: Algal Lipid Upgrading |

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Department of Energy Algal Lipid Upgrading Bioenergy Technologies Office R&D Pathways: Algal Lipid Upgrading Algal lipid upgrading is one of eight priority pathways chosen to convert biomass into hydrocarbon fuels by the Bioenergy Technologies Office. These pathways were down-selected from an initial list of 18. Bioenergy Technologies Office R&D Pathways: Algal Lipid Upgrading (490.16 KB) More Documents & Publications Pathways for Algal Biofuels Algal Lipid Extraction and

  20. Standard Work Specifications for Single-Family Home Energy Upgrades Summary Fact Sheet

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy (DOE), the National Renewable Energy Laboratory (NREL) and numerous industry stakeholders developed the Standard Work Specifications for Single-Family Home Energy Upgrades to define the minimum requirements for high-quality residential energy upgrades. Today, the Standard Work Specifications provide a unique source for defining high-quality home energy upgrades, establishing clear expectations for homeowners, contractors, trainers, workers, program administrators, and organizations that provide financing for energy upgrades.

  1. Standard Work Specifications for Single-Family Home Energy Upgrades Summary (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2012-11-01

    The U.S. Department of Energy (DOE), the National Renewable Energy Laboratory (NREL) and numerous industry stakeholders developed the Standard Work Specifications for Single-Family Home Energy Upgrades to define the minimum requirements for high-quality residential energy upgrades. Today, the Standard Work Specifications provide a unique source for defining high-quality home energy upgrades, establishing clear expectations for homeowners, contractors, trainers, workers, program administrators, and organizations that provide financing for energy upgrades.

  2. Spotlight on Austin, Texas: Best Offer Ever Produces Upgrades in Record

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Time | Department of Energy Best Offer Ever Produces Upgrades in Record Time Spotlight on Austin, Texas: Best Offer Ever Produces Upgrades in Record Time Spotlight on Austin, Texas: Best Offer Ever Produces Upgrades in Record Time, as posted on the U.S. Department of Energy's Better Buildings Neighborhood Program website. Spotlight on Austin, Texas (554.64 KB) More Documents & Publications Spotlight on Austin, Texas: Best Offer Ever Produces 564 Upgrades in Record Time Spotlight on

  3. WPN 03-6: Manufactured Home Energy Audit (MHEA) Software Upgrade Availability and Licensing Requirements

    Broader source: Energy.gov [DOE]

    To provide states instructions for obtaining the Weatherization Assistance Program's upgraded audit software package for manufactured/mobile homes.

  4. Energy Upgrade California in Los Angeles County, Loan Loss Reserve Fund Agreement

    Broader source: Energy.gov [DOE]

    Energy Upgrade California in Los Angeles County, Loan Loss Reserve Fund Agreement. Example of loan loss reserve agreement.

  5. Paducah Needs Assessment

    Office of Energy Efficiency and Renewable Energy (EERE)

    Needs Assessment for former Oak Ridge K-25, Paducah, and Portsmouth Gaseous Diffusion Plant production workers.

  6. South Ukraine NPP: Safety improvements through Plant Computer upgrade

    SciTech Connect (OSTI)

    Brenman, O.; Chernyshov, M. A.; Denning, R. S.; Kolesov, S. A.; Balakan, H. H.; Bilyk, B. I.; Kuznetsov, V. I.; Trosman, G.

    2006-07-01

    This paper summarizes some results of the Plant Computer upgrade at the Units 2 and 3 of South Ukraine Nuclear Power Plant (NPP). A Plant Computer, which is also called the Computer Information System (CIS), is one of the key safety-related systems at VVER-1000 nuclear plants. The main function of the CIS is information support for the plant operators during normal and emergency operational modes. Before this upgrade, South Ukraine NPP operated out-of-date and obsolete systems. This upgrade project wax founded by the U.S. DOE in the framework of the International Nuclear Safety Program (INSP). The most efficient way to improve the quality and reliability of information provided to the plant operator is to upgrade the Human-System Interface (HSI), which is the Upper Level (UL) CIS. The upgrade of the CIS data-acquisition system (DAS), which is the Lower Level (LL) CIS, would have less effect on the unit safety. Generally speaking, the lifetime of the LL CIS is much higher than one of the UL CIS. Unlike Plant Computers at the Western-designed plants, the functionality of the WER-1000 CISs includes a control function (Centralized Protection Testing) and a number of the plant equipment monitoring functions, for example, Protection and Interlock Monitoring and Turbo-Generator Temperature Monitoring. The new system is consistent with a historical migration of the format by which information is presented to the operator away from the traditional graphic displays, for example, Piping and Instrument Diagrams (P and ID's), toward Integral Data displays. The cognitive approach to information presentation is currently limited by some licensing issues, but is adapted to a greater degree with each new system. The paper provides some lessons learned on the management of the international team. (authors)

  7. Low rank coal upgrading in a flow of hot water

    SciTech Connect (OSTI)

    Masato Morimoto; Hiroyuki Nakagawa; Kouichi Miura

    2009-09-15

    Simultaneous hydrothermal degradation and extraction at around 350{sup o}C using flowing solvent as a reaction/extraction medium were proposed for upgrading brown coal, more specifically, for converting brown coal into several fractions having different molecular weight and chemical structure under mild conditions. When an Australian brown coal, Loy Yang coal, was treated by water at 350{sup o}C under 18 MPa, the coal was separated into four fractions: gaseous product by 8% yield, water-soluble extract at room temperature (soluble) by 23% yield, extract precipitates as solid at room temperature (deposit) by 23% yield, and residual coal (upgraded coal) by 46% yield on daf basis. The separation was found to be realized by in situ extraction of low-molecular-weight substances released from coal macromolecular structure and/or those generated by hydrothermal decomposition reactions at 350{sup o}C. The solid products obtained, deposit and upgraded coal, were characterized in detail to examine the possibility of their effective utilization as solid fuel and chemical feed stock. The upgraded coal showed higher heating value and higher gasification reactivity than the parent coal, indicating that the upgraded coal can be a better solid fuel than the parent coal. The solid extract, deposit, was found to show thermoplasticity at less than 200{sup o}C, suggesting the possibility of utilizing the deposit as a raw material of high performance carbon materials. Several variables affecting the performance of the proposed method are also examined in detail in this paper. 12 refs., 8 figs., 3 tabs.

  8. Drill string transmission line

    DOE Patents [OSTI]

    Hall, David R.; Hall, Jr., H. Tracy; Pixton, David S.; Bradford, Kline; Fox, Joe

    2006-03-28

    A transmission line assembly for transmitting information along a downhole tool comprising a pin end, a box end, and a central bore traveling between the pin end and the box end, is disclosed in one embodiment of the invention as including a protective conduit. A transmission line is routed through the protective conduit. The protective conduit is routed through the central bore and the ends of the protective conduit are routed through channels formed in the pin end and box end of the downhole tool. The protective conduit is elastically forced into a spiral or other non-linear path along the interior surface of the central bore by compressing the protective conduit to a length within the downhole tool shorter than the protective conduit.

  9. Appendix TFIELD: Transmissivity Fields

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Appendix TFIELD-2014 Transmissivity Fields United States Department of Energy Waste Isolation Pilot Plant Carlsbad Field Office Carlsbad, New Mexico Compliance Recertification Application 2014 Appendix TFIELD-2014 Table of Contents TFIELD-1.0 Overview of the T-field Development, Calibration, and Mining Modification Process TFIELD-2.0 Geologic Data TFIELD-2.1 Culebra Hydrogeologic Setting TFIELD-2.2 Refinement of Geologic Boundaries TFIELD-2.2.1 Rustler Halite Margins TFIELD-2.2.2 Salado

  10. Transmission and Storage Operations

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Transmission and Storage Operations Natural Gas Infrastructure R&D and Methane Mitigation Workshop Mary Savalle, PMP, LSSGB Compression Reliability Engineer November 12, 2014 Agenda * DTE Gas Snapshot * NOx & CO - Combustion stability * Methane - Packing - Blowdowns * Capture vs Flare 2 SNAPSHOT * DTE Gas - 41 Units * Age Range: 8-59yrs (Average 45yrs) - 118,200HP * 1,000-15,000HP - 7 different manufacturers * Cooper-Bessemer, Solar, Waukesha, DeLaval, IR, CAT, Ariel - Complete Mixture *

  11. He Puff System For Dust Detector Upgrade

    SciTech Connect (OSTI)

    B. Rais, C.H. Skinner A.L. Roquemore

    2010-10-01

    Local detection of surface dust is needed for the safe operation of next-step magnetic fusion devices such as ITER. An electrostatic dust detector, based on a 5 cm x 5 cm grid of interlocking circuit traces biased to 50 V, has been developed to detect dust on remote surfaces and was successfully tested for the first time on the National Spherical Torus Experiment (NSTX). We report on a helium puff system that clears residual dust from this detector and any incident debris or fibers that might cause a permanent short circuit. The entire surface of the detector was cleared of carbon particles by two consecutive helium puffs delivered by three nozzles of 0.45 mm inside diameter. The optimal configuration was found to be with the nozzles at an angle of 30o with respect to the surface of the detector and a helium backing pressure of 6 bar. __________________________________________________

  12. THE COUNCIL OF STATE GOVERNMENTS THE ELECTRIC TRANSMISSION LINE SITING COMPACT

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    COUNCIL OF STATE GOVERNMENTS THE ELECTRIC TRANSMISSION LINE SITING COMPACT LEGISLATIVE BRIEFING Background and Summary Background and Need The siting of interstate transmission lines has long been a problem that has vexed both states and the federal government. With the expected growth in electricity demand, coupled with the need to bring renewable energy to market and the necessity to enhance and secure the nation's energy infrastructure, the need for added transmission capacity has never been

  13. Process and economic model of in-field heavy oil upgrading using aqueous pyrolysis

    SciTech Connect (OSTI)

    Thorsness, C. B., LLNL

    1997-01-21

    A process and economic model for aqueous pyrolysis in-field upgrading of heavy oil has been developed. The model has been constructed using the ASPEN PLUS chemical process simulator. The process features cracking of heavy oil at moderate temperatures in the presence of water to increase oil quality and thus the value of the oil. Calculations with the model indicate that for a 464 Mg/day (3,000 bbl/day) process, which increases the oil API gravity of the processed oil from 13.5{degree} to 22.4{degree}, the required value increase of the oil would need to be at least $2.80/Mg{center_dot}{degree}API($0.40/bbl{center_dot}{degree}API) to make the process economically attractive. This level of upgrading has been demonstrated in preliminary experiments with candidate catalysts. For improved catalysts capable of having the coke make and increasing the pyrolysis rate, a required price increase for the oil as low as $1.34/Mg{center_dot}{degree}API ($0.21/bbl{center_dot}{degree}API)has been calculated.

  14. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    SciTech Connect (OSTI)

    Mills, Andrew D.; Wiser, Ryan; Porter, Kevin

    2009-02-02

    The rapid development of wind power that the United States has experienced over the last several years has been coupled with a growing concern that wind development will require substantial additions to the nation's transmission infrastructure. Transmission is particularly important for wind power due to the locational dependence of wind resources, the relatively low capacity factor of wind plants, and the mismatch between the short lead time to build a new wind project and the longer lead time often needed to plan, permit, and construct transmission. It is clear that institutional issues related to transmission planning, siting, and cost allocation will pose major obstacles to accelerated wind power deployment, but also of concern is the potential cost of this infrastructure build out. Simply put, how much extra cost will society bear to deliver wind power to load centers? Without an answer to this question, there can be no consensus on whether or not the cost of developing transmission for wind will be a major barrier to further wind deployment, or whether the institutional barriers to transmission expansion are likely to be of more immediate concern. In this report, we review a sample of 40 detailed transmission studies that have included wind power. These studies cover a broad geographic area, and were completed from 2001-2008. Our primary goal in reviewing these studies is to develop a better understanding of the transmission costs needed to access growing quantities of wind generation. A secondary goal is to gain a better appreciation of the differences in transmission planning approaches in order to identify those methodologies that seem most able to estimate the incremental transmission costs associated with wind development. Finally, we hope that the resulting dataset and discussion might be used to inform the assumptions, methods, and results of higher-level assessment models that are sometimes used to estimate the cost of wind deployment (e.g. NEMS and

  15. Transmission Infrastructure Program

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... by new facilities; however, additional reconfiguration, integration and reliability needs may also arise - ICF International, July 2015 6 Program Process: Summary * Goal: Provide ...

  16. GTT 2012 Transmission Workshop- Documents

    Broader source: Energy.gov [DOE]

    Use the links below to download documents from the GTT's Transmission Workshop, held November 1-2, 2012

  17. Geothermal Resources and Transmission Planning

    Broader source: Energy.gov [DOE]

    This project addresses transmission-related barriers to utility-scale deployment of geothermal electric generation technologies.

  18. The integration of renewable energy sources into electric power transmission systems

    SciTech Connect (OSTI)

    Barnes, P.R.; Dykas, W.P.; Kirby, B.J.; Purucker, S.L.; Lawler, J.S.

    1995-07-01

    Renewable energy technologies such as photovoltaics, solar thermal power plants, and wind turbines are nonconventional, environmentally attractive sources of energy that can be considered for electric power generation. Many of the areas with abundant renewable energy resources (very sunny or windy areas) are far removed from major load centers. Although electrical power can be transmitted over long distances of many hundreds of miles through high-voltage transmission lines, power transmission systems often operate near their limits with little excess capacity for new generation sources. This study assesses the available capacity of transmission systems in designated abundant renewable energy resource regions and identifies the requirements for high-capacity plant integration in selected cases. In general, about 50 MW of power from renewable sources can be integrated into existing transmission systems to supply local loads without transmission upgrades beyond the construction of a substation to connect to the grid. Except in the Southwest, significant investment to strengthen transmission systems will be required to support the development of high-capacity renewable sources of 1000 MW or greater in areas remote from major load centers. Cost estimates for new transmission facilities to integrate and dispatch some of these high-capacity renewable sources ranged from several million dollars to approximately one billion dollars, with the latter figure an increase in total investment of 35%, assuming that the renewable source is the only user of the transmission facility.

  19. Puget Sound Area Electric Reliability Plan : Appendix E, Transmission Reinforcement Analysis.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1992-04-01

    The purpose of this appendix to the draft environmental impact statement (EIS) report is to provide an update of the latest study work done on transmission system options for the Puget Sound Area Electric Reliability Plan. Also included in the attachments to the EIS are 2 reports analyzing the voltage stability of the Puget Sound transmission system and a review by Power Technologies, Inc. of the BPA voltage stability analysis and reactive options. Five transmission line options and several reactive options are presently being considered as possible solutions to the PSAFRP by the Transmission Team. The first two line options would be built on new rights-of way adjacent (as much as possible) to existing corridors. The reactive options would optimize the existing transmission system capability by adding new stations for series capacitors and/or switchgear. The other three line options are rebuilds or upgrades of existing cross mountain transmission lines. These options are listed below and include a preliminary assessment of the additional transmission system reinforcement required to integrate the new facilities into the existing transmission system. Plans were designed to provide at least 500 MVAR reactive margin.

  20. 2006 Final Transmission Proposal: Revenue Requirement Study Documentation.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    2005-06-01

    The purpose of the Revenue Requirement Study (Study) is to establish the level of revenues needed from rates for Bonneville Power Administration's (BPA's) transmission and ancillary services to recover, in accordance with sound business principles, costs associated with the transmission of electric power over the Federal Columbia River Transmission System (FCRTS). The FCRTS is part of the larger Federal Columbia River Power System (FCRPS) which also includes the hydroelectric, multipurpose facilities constructed and operated by the U.S. Army Corps of Engineers and the Bureau of Reclamation in the Pacific Northwest. The FCRPS costs that are not included in the FCRTS costs are funded and repaid through BPA power rates. The transmission revenue requirements herein include: recovery of the Federal investment in transmission and transmission-related assets; the operations and maintenance (O&M) and other annual expenses associated with the provision of transmission and ancillary services; the cost of generation inputs for ancillary services and other between business-line services necessary for the transmission of power; and all other transmission-related costs incurred by the Administrator. The cost evaluation period for this rate proposal includes Fiscal Years (FYs) 2005-2007, the period extending from the last year for which historical information is available through the proposed rate test period. The Study includes the transmission revenue requirements for the rate test period, FYs 2006-2007 (Rate Period) and the results of transmission repayment studies. This Study outlines the policies, forecasts, assumptions, and calculations used to determine BPA's transmission revenue requirements. Legal requirements are summarized in Chapter 5 of this Study. The Revenue Requirement Study Documentation (Documentation), TR-06-FS-BPA-01A, contains key technical assumptions and calculations, the results of the transmission repayment studies, and a further explanation of the

  1. Guideline for Evaluating Analytical Chemistry Capabilities and Recommending Upgraded Methods and Instrumentation for Nuclear Material Control and Accountability at Russian Nuclear Facilities

    SciTech Connect (OSTI)

    Russ, G.P.

    1999-10-21

    Analytical chemistry plays a key role in nuclear material control and accounting (MC and A). A large part of Special Nuclear Material (SNM) inventories and virtually all of the highly attractive SNM inventories are based on sampling bulk materials followed by destructive assay (DA) of these materials. These measurements support MC and A in process control, physical inventory verification, evaluation of the effects of process changes, detecting and resolving shipper-receiver differences, and the resolution of inspector-facility differences. When evaluating these important functions, US Project Teams need to carefully assess the existing Russian analytical chemistry capabilities and to specify appropriate upgrades where needed. This evaluation and the specification of upgrades have proven difficult, in part, because of the highly specialized and technical nature of DA and because of the wide variety of methods and applications. In addition, providing a DA capability to a Russian analytical laboratory requires much more than simply supplying new instrumentation. Experience has shown that DA upgrades at Russian analytical facilities require more support equipment than was originally anticipated by US Teams. The purpose of this guidance document is to: (1) recommend criteria for US Projects Teams to use in their evaluation of Russian DA capabilities; (2) provide a basis for selection of appropriate upgrades where capabilities are inadequate to support MC and A goals; and (3) to provide a list of Da methods suitable for MC and A with the following information: performance and applications information, strengths and limitations, and references and information on cost. Criteria for evaluating existing capabilities and determining appropriate upgrades are difficult to define. However, this is the basic information needed by the US project Teams. Section IV addresses these criteria.

  2. Electricity Transmission, A Primer | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Transmission, A Primer Electricity Transmission, A Primer This primer on electric transmission is intended to help policymakers understand the physics of the transmission system, the economics, and the policies. Electricity Transmission, A Primer (1.95 MB) More Documents & Publications Draft Chapter 4: Transmission Adequacy Electricity Grid Basics Webinar Presentation Slides and Text Version Chapter 4 Transmission Adequacy

  3. First lasing of the IR upgrade FEL at Jefferson lab

    SciTech Connect (OSTI)

    Christopher Behre; Stephen Benson; George Biallas; James Boyce; Christopher Curtis; David Douglas; H. Dylla; L. Dillon-townes; Richard Evans; Albert Grippo; Joseph Gubeli; David Hardy; John Heckman; Carlos Hernandez-Garcia; Tommy Hiatt; Kevin Jordan; Nikolitsa Merminga; George Neil; Joseph Preble; Harvey Rutt; Michelle D. Shinn; Timothy Siggins; Hiroyuki Toyokawa; David W. Waldman; Richard Walker; Neil Wilson; Byung Yunn; Shukui Zhang

    2004-08-01

    We report initial lasing results from the IR Upgrade FEL at Jefferson Lab[1]. The electron accelerator was operated with low average current beam at 80 MeV. The time structure of the beam was 120 pC bunches at 4.678 MHz with up to 750 {micro}sec pulses at 2Hz. Lasing was established over the entire wavelength range of the mirrors (5.5-6.6 {micro}m). The detuning curve length, turn-on time, and power were in agreement with modeling results assuming a 1 psec FWHM micropulse. The same model predicts over 10 kW of power output with 10 mA of beam and 10% output coupling, which is the ultimate design goal of the IR Upgrade FEL. The behavior of the laser while the dispersion section strength was varied was found to qualitatively match predictions. Initial CW lasing results also will be presented.

  4. Heavy oil and tar sands recovery and upgrading. International technology

    SciTech Connect (OSTI)

    Schumacher, M.M.

    1982-01-01

    This work provides an in-depth assessment of international technology for the recovery and upgrading of heavy crude oil and tar sands. The technologies included are currently in use, under development, or planned; emphasis is placed on post-1978 activities. The heavy oil technologies and processes considered include methods relating to the exploitation of heavy oil reservoirs, such as production from underground workings, all types of improved or enhanced recovery, subsurface extraction, and well rate stimulation. The tar sands section includes sizing the resource base and reviewing and evaluating past, present, and planned research and field developments on processes for mining, producing, extracting, and upgrading very heavy oils recovered from tar sands, e.g., bitumen recovery from tar sands where primary production was impossible because of the oil's high viscosity. 616 references.

  5. 2 MW upgrade of the Fermilab Main Injector

    SciTech Connect (OSTI)

    Weiren Chou

    2003-06-04

    In January 2002, the Fermilab Director initiated a design study for a high average power, modest energy proton facility. An intensity upgrade to Fermilab's 120-GeV Main Injector (MI) represents an attractive concept for such a facility, which would leverage existing beam lines and experimental areas and would greatly enhance physics opportunities at Fermilab and in the U.S. With a Proton Driver replacing the present Booster, the beam intensity of the MI is expected to be increased by a factor of five. Accompanied by a shorter cycle, the beam power would reach 2 MW. This would make the MI a more powerful machine than the SNS or the J-PARC. Moreover, the high beam energy (120 GeV) and tunable energy range (8-120 GeV) would make it a unique high power proton facility. The upgrade study has been completed and published. This paper gives a summary report.

  6. Present Status of the DAFNE Upgrade And Perspectives

    SciTech Connect (OSTI)

    Milardi, C.; Alesini, D.; Biagini, M.E.; Biscari, C.; Boni, R.; Boscolo, M.; Bossi, F.; Buonomo, B.; Clozza, A.; Delle Monache, G.; Demma, T.; Di Pasquale, E.; Di Pirro, G.; Drago, A.; Gallo, A.; Ghigo, A.; Guiducci, S.; Ligi, C.; Marcellini, F.; Mazzitelli, G.; Murtas, F.; /Frascati /Novosibirsk, IYF /CERN /INFN, Cosenza /INFN, Rome /KEK, Tsukuba /Orsay, LAL /Rome U. /Pisa U. /INFN, Pisa /SLAC /Rome III U.

    2009-06-05

    The DA{Phi}NE collider has been recently upgraded in order to implement a new collision scheme based on large Piwinski angle and cancellation of the synchro-betatron resonances by means of electromagnetic sextupoles (Crab-Waist compensation). The novel approach has proved to be effective in improving beam-beam interaction and collider luminosity. The results and the measurements taken during commissioning as well as the perspectives for the SIDDHARTA run are presented and discussed.

  7. MFRSR Head Refurbishment, Data Logger Upgrade and Calibration Improvements

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    MFRSR Head Refurbishment, Data Logger Upgrade and Calibration Improvements Gary Hodges, CIRES/NOAA and John Schmelzer, PNL gary.hodges@noaa.gov, john.schmelzer@pnl.gov 17th Annual ARM Science Team Meeting 26-30 March 2006 Monterey, CA Head Refurbishment The Process Includes: * New filter detectors * Relocate internal thermistors * New connectors * Gain resistors moved to head * Improved insulation The Finished Heads: * Are lamp calibrated * Have filter profiles measured * Cosine characterized *

  8. Heavy oil and tar sands recovery and upgrading: international technology

    SciTech Connect (OSTI)

    Schumacher, M.M.

    1982-01-01

    This book provides an in-depth assessment of international technology for the recovery and upgrading of heavy crude oil and tar sands. The technologies included are currently in use, under development, or planned; emphasis is placed on post-1978 activities. The heavy oil technologies and processes considered in Part I include methods relating to the exploitation of heavy oil reservoirs, such as production from undergorun workings, all types of improved or enhanced recovery, subsurface extraction, and well rate stimulation. Furthermore, even though heavy crudes are understood to include only those liquid or semiliquid hydrocarbons with a gravity of 20/sup 0/API or less, technology applied to lighter crude oils with in situ viscosities of the same order of magnitude as some US heavy oils is also included. The scope of the tar sands section (Part II) includes sizing the resource base and reviewing and evaluatin past, present, and planned research and field developments on processes for mining, producing, extracting, and upgrading very heavy oils recovered from tar sands, e.g., bitumen recovery from tar sands where primary production was impossible because of the oil's high viscosity. On the production side, very heavy oil is defined as having a gravity less than 10/sup 0/ to 12/sup 0/API and greater than 100,000-centipoise viscosity at 50/sup 0/F. On the upgrading side, hydrocarbons whose characteristics dictated additional processing prior to conventional refining into salable products (1050+/sup 0/ material) were included, regardless of origin, in order to encompass all pertinent upgrading technologies.

  9. QuikChill software for efficient chiller upgrade assessment

    SciTech Connect (OSTI)

    Rose, R.J.; Anderson, D.

    1998-07-01

    Chiller upgrades, required by recent CFC legislation, have not occurred in most large US facilities. Opportunities for compliance via efficient, correctly-sized chillers is significant, but there is little industry infrastructure encouraging downsizing and maximum efficiency, nor are changeouts approached as investments. Upgrade performance analysis is either too simplistic (missing integration and downsizing opportunities) or too difficult, detailed, and expensive. A niche exists for dedicated tools that can be used for both early screening and more detailed final design analysis, including downsizing, system integration, and staging. QuickChill, a chiller upgrade analysis software tool, as developed by EPA's ENERGY STAR Buildings Program to address these issues. It performs economic and energy analyses of potential centrifugal chiller upgrades using minimal information, and performs more accurate calculations as the quality and detail or inputs are increased. QuikChill assesses the consolidation of existing chillers, integration/staging of new chillers, and refrigerant conversion retrofits. QuikChill was designed for facility managers and consulting engineers facing CFC phaseouts. Rather than require time-consuming, detailed building shell and operational inputs, QuikChill estimates loads using DOE2-generated curves which plot the relationship between cooling load and outdoor temperature. Surprisingly, these curves reasonably predict annual cooling system operating requirements when used with local hourly temperatures and the peak load met by the existing system. Hourly temperature data is available for over 240 locations and users can easily supply peak information. QuikChill's combination of simplified inputs, investment-orientation, and unique approach to hourly cooling load estimation help fill an analytical void for the post-CFC chiller industry.

  10. Solar Test Facility Upgrades Complete, Leading to Better Sandia

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Capabilities to Support Power Industry Test Facility Upgrades Complete, Leading to Better Sandia Capabilities to Support Power Industry - Sandia Energy Energy Search Icon Sandia Home Locations Contact Us Employee Locator Energy & Climate Secure & Sustainable Energy Future Stationary Power Energy Conversion Efficiency Solar Energy Wind Energy Water Power Supercritical CO2 Geothermal Natural Gas Safety, Security & Resilience of the Energy Infrastructure Energy Storage Nuclear Power

  11. Catalytic Upgrading of Sugars to Hydrocarbons Technology Pathway

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Catalytic Upgrading of Sugars to Hydrocarbons Technology Pathway Mary Biddy National Renewable Energy Laboratory Susanne Jones Pacific Northwest National Laboratory NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency & Renewable Energy, operated by the Alliance for Sustainable Energy, LLC, under contract DE-AC36-08GO28308. Pacific Northwest National Laboratory is operated by Battelle for the United States Department of Energy under contract

  12. Proposal to upgrade the MIPP data acquisition system

    SciTech Connect (OSTI)

    Baker, W.; Carey, D.; Johnstone, C.; Kostin, M.; Meyer, H.; Raja, R.; /Fermilab

    2005-03-01

    The MIPP TPC is the largest contributor to the MIPP event size by far. Its readout system and electronics were designed in the 1990's and limit it to a readout rate of 60 Hz in simple events and {approx} 20 Hz in complicated events. With the readout chips designed for the ALICE collaboration at the LHC, we propose a low cost effective scheme of upgrading the MIPP data acquisition speed to 3000 Hz.

  13. Nuclear Materials Safeguards and Security Upgrade Project | National

    National Nuclear Security Administration (NNSA)

    Nuclear Security Administration Materials Safeguards and Security Upgrade Project NNSA Announces 2014 Security Professional of the Year Awards WASHINGTON, D.C. - The National Nuclear Security Administration (NNSA) today announced the recipients of the 2014 Bradley A. Peterson Federal and Contractor Security Professional of the Year Awards. Pamela Valdez from the Los Alamos Field Office will receive the federal award and Randy Fraser from

  14. Colorado Electrical Transmission Grid

    SciTech Connect (OSTI)

    Zehner, Richard E.

    2012-02-01

    Citation Information: Originator: Earth Science &Observation Center (ESOC), CIRES, University of Colorado at Boulder Originator: Xcel Energy Publication Date: 2012 Title: Colorado XcelEnergy NonXcel Transmission Network Edition: First Publication Information: Publication Place: Earth Science & Observation Center, Cooperative Institute for Research in Environmental Science (CIRES), University of Colorado, Boulder Publisher: Earth Science &Observation Center (ESOC), CIRES, University of Colorado at Boulder Description: This layer contains transmission network of Colorado Spatial Domain: Extent: Top: 4540689.017558 m Left: 160606.141934 m Right: 758715.946645 m Bottom: 4098910.893397m Contact Information: Contact Organization: Earth Science &Observation Center (ESOC), CIRES, University of Colorado at Boulder Contact Person: Khalid Hussein Address: CIRES, Ekeley Building Earth Science & Observation Center (ESOC) 216 UCB City: Boulder State: CO Postal Code: 80309-0216 Country: USA Contact Telephone: 303-492-6782 Spatial Reference Information: Coordinate System: Universal Transverse Mercator (UTM) WGS’1984 Zone 13N False Easting: 500000.00000000 False Northing: 0.00000000 Central Meridian: -105.00000000 Scale Factor: 0.99960000 Latitude of Origin: 0.00000000 Linear Unit: Meter Datum: World Geodetic System ’1984 (WGS ’1984) Prime Meridian: Greenwich Angular Unit: Degree Digital Form: Format Name: Shapefile

  15. Automated manual transmission clutch controller

    DOE Patents [OSTI]

    Lawrie, Robert E.; Reed, Jr., Richard G.; Rausen, David J.

    1999-11-30

    A powertrain system for a hybrid vehicle. The hybrid vehicle includes a heat engine, such as a diesel engine, and an electric machine, which operates as both an electric motor and an alternator, to power the vehicle. The hybrid vehicle also includes a manual-style transmission configured to operate as an automatic transmission from the perspective of the driver. The engine and the electric machine drive an input shaft which in turn drives an output shaft of the transmission. In addition to driving the transmission, the electric machine regulates the speed of the input shaft in order to synchronize the input shaft during either an upshift or downshift of the transmission by either decreasing or increasing the speed of the input shaft. When decreasing the speed of the input shaft, the electric motor functions as an alternator to produce electrical energy which may be stored by a storage device. Operation of the transmission is controlled by a transmission controller which receives input signals and generates output signals to control shift and clutch motors to effect smooth launch, upshift shifts, and downshifts of the transmission, so that the transmission functions substantially as an automatic transmission from the perspective of the driver, while internally substantially functioning as a manual transmission.

  16. Snowflake divertor configuration studies for NSTX-Upgrade

    SciTech Connect (OSTI)

    Soukhanovskii, V A

    2011-11-12

    Snowflake divertor experiments in NSTX provide basis for PMI development toward NSTX-Upgrade. Snowflake configuration formation was followed by radiative detachment. Significant reduction of steady-state divertor heat flux observed in snowflake divertor. Impulsive heat loads due to Type I ELMs are partially mitigated in snowflake divertor. Magnetic control of snowflake divertor configuration is being developed. Plasma material interface development is critical for NSTX-U success. Four divertor coils should enable flexibility in boundary shaping and control in NSTX-U. Snowflake divertor experiments in NSTX provide good basis for PMI development in NSTX-Upgrade. FY 2009-2010 snowflake divertor experiments in NSTX: (1) Helped understand control of magnetic properties; (2) Core H-mode confinement unchanged; (3) Core and edge carbon concentration reduced; and (4) Divertor heat flux significantly reduced - (a) Steady-state reduction due to geometry and radiative detachment, (b) Encouraging results for transient heat flux handling, (c) Combined with impurity-seeded radiative divertor. Outlook for snowflake divertor in NSTX-Upgrade: (1) 2D fluid modeling of snowflake divertor properties scaling - (a) Edge and divertor transport, radiation, detachment threshold, (b) Compatibility with cryo-pump and lithium conditioning; (2) Magnetic control development; and (3) PFC development - PFC alignment and PFC material choice.

  17. Upgrades to the Polarized Neutron Reflectometer Asterix at LANSCE

    SciTech Connect (OSTI)

    Pynn, Roger

    2015-03-16

    We have upgraded the polarized neutron reflectometer, Asterix, at the Lujan Neutron Scattering Center at Los Alamos for the benefit of the research communities that study magnetic and complex-fluid films, both of which play important roles in support of the DOE’s energy mission. The upgrades to the instrument include: • A secondary spectrometer that was integrated with a Huber sample goniometer purchased with other funds just prior to the start of our project. The secondary spectrometer provides a flexible length for the scattered flight path, includes a mechanism to select among 3 alternative polarization analyzers as well as a support for new neutron detectors. Also included is an optic rail for reproducible positioning of components for Spin Echo Scattering Angle Measurement (SESAME). The entire secondary spectrometer is now non-magnetic, as required for neutron Larmor labeling. • A broad-band neutron polarizer for the incident neutron beam based on the V geometry. • A wide-angle neutron polarization analyzer • A 2d position-sensitive neutron detector • Electromagnetic coils (Wollaston prisms) for SESAME plus the associated power supplies, cooling, safety systems and integration into the data acquisition system. The upgrades allowed a nearly effortless transition between configurations required to serve the polarized neutron reflectometry community, users of the 11 T cryomagnet and users of SESAME.

  18. A novel process for upgrading heavy oil emulsions

    SciTech Connect (OSTI)

    Ng, F.T.T.; Rintjema, R.T.

    1994-12-31

    Canada has extensive reserves of high sulfur heavy oils. These heavy oils are recovered primarily by steam injection techniques. As a result, the heavy oils are obtained as emulsions at well-heads. The heavy oils, being high in sulfur and metals, and low in hydrogen to carbon atomic ratio, require upgrading such as desulfurization and hydrocracking before it can be used in conventional refineries. Conventional emulsion treatment and desulfurization technology require multistage processing. Thus, alternative technologies for processing heavy oil emulsions would be attractive. The authors have recently developed a novel single stage process for upgrading emulsions via activation of water to provide hydrogen in situ for catalytic desulfurization and hydrocracking. Current work is focused on the desulfurization aspect of upgrading, using benzothiophene as the model sulfur compound and molybdic acid as the catalyst. At 340 C and a CO loading pressure of 600 psi, up to 86% sulfur removal was obtained. As well, in situ generated H{sub 2} was found to be more active than externally supplied molecular H{sub 2}. A likely pathway for desulfurization of benzothiophene was via the initial hydrogenation of benzothiophene to dihydrobenzothiophene followed by hydrogenolysis to give ethylbenzene and H{sub 2}S.

  19. UPGRADING METHANE USING ULTRA-FAST THERMAL SWING ADSORPTION

    SciTech Connect (OSTI)

    Anna Lee Tonkovich

    2004-01-01

    The purpose of this project is to design and demonstrate an approach to upgrade low-BTU methane streams from coal mines to pipeline-quality natural gas. The objective of Phase I of the project was to assess the feasibility of upgrading low-Btu methane streams using ultra-fast thermal swing adsorption (TSA) using Velocys' modular microchannel process technology. The project is on schedule and under budget. For Task 1.1, the open literature, patent information, and vendor contacts were surveyed to identify adsorbent candidates for experimental validation and subsequent demonstration in an MPT-based ultra-fast TSA separation for methane upgrading. The leading candidates for preferential adsorption of methane over nitrogen are highly microporous carbons. A Molecular Gate{trademark} zeolite from Engelhard Corporation has emerged as a candidate. For Task 1.2, experimental evaluation of adsorbents was initiated, and data were collected on carbon (MGN-101) from PICA, Inc. This carbon demonstrated a preferential capacity for methane over nitrogen, as well as a reasonable thermal swing differential capacity for a 90% methane and 10% nitrogen mixture. A similar methane swing capacity at 2 psig was measured. The mixture composition is relevant because gob gas contains nearly 85% methane and must be purified to 97% methane for pipeline quality.

  20. 2015 National Electric Transmission Congestion Study | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    2015 National Electric Transmission Congestion Study 2015 National Electric Transmission Congestion Study 2015 National Electric Transmission Congestion Study Section 1221(a) of ...

  1. Electricity Transmission, A Primer | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Electricity Transmission, A Primer Electricity Transmission, A Primer This primer on electric transmission is intended to help policymakers understand the physics of the...

  2. RAPID/Bulk Transmission | Open Energy Information

    Open Energy Info (EERE)

    Page Edit History RAPIDBulk Transmission < RAPID(Redirected from RAPIDOverviewBulkTransmission) Redirect page Jump to: navigation, search REDIRECT RAPIDBulkTransmission...

  3. Bordertown to California Transmission | Open Energy Information

    Open Energy Info (EERE)

    Transmission EIS Bordertown to California 120kV Transmission Line Project Environmental Impact Statement General NEPA Document Info Energy Sector Transmission Environmental...

  4. WPN 05-7: Weatherization Assistant [National Energy Audit (Neat) and Manufactured Home Energy Audit (MHEA)] Software Upgrade Availability

    Broader source: Energy.gov [DOE]

    To provide states with instructions for obtaining the Weatherization Assistance Program's 2005 upgraded audit software package.

  5. Federal Finance Facilities Available for Energy Efficiency Upgrades...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    ... Junta, Chief Distributions Branch H. Robert Lash, Chief Transmissions Branch Gerard Moore, Chief Energy Forecasting Branch Victor Vu, Director Power Supply Division Vacant ...

  6. Transmission line environmental assessment guidance document

    SciTech Connect (OSTI)

    Jackson, J.; Pentecost, E.; Muzzarelli, J.

    1994-01-01

    Since 1939, U.S. utility companies have been required to obtain a Presidential Permit to construct electric transmission lines that cross a U.S. border and connect with a foreign utility. The purpose of this document is to provide Presidential Permit applicants with two types of guidance: (1) on the type of environmental and project descriptive information needed to assess the potential impacts of the proposed and alternative actions and (2) on compliance with applicable federal and state regulations. The main three chapters present information on the purpose and content of this document (Chapter 1); legislative, regulatory, and consultation requirements for transmission line interconnect projects (Chapter 2); and identification of basic transmission system design parameters and environmental data requirements for analysis of potential impacts of the proposed action (Chapter 3). Chapter 3 also includes information on possible techniques or measures to mitigate impacts. Appendix A presents an overview of NEPA requirements and DOE`s implementing procedures. Appendix B summarizes information on legislation that may be applicable to transmission line projects proposed in Presidential Permit applications.

  7. Dynamic Transmission Electron Microscopy

    SciTech Connect (OSTI)

    Evans, James E.; Jungjohann, K. L.; Browning, Nigel D.

    2012-10-12

    Dynamic transmission electron microscopy (DTEM) combines the benefits of high spatial resolution electron microscopy with the high temporal resolution of ultrafast lasers. The incorporation of these two components into a single instrument provides a perfect platform for in situ observations of material processes. However, previous DTEM applications have focused on observing structural changes occurring in samples exposed to high vacuum. Therefore, in order to expand the pump-probe experimental regime to more natural environmental conditions, in situ gas and liquid chambers must be coupled with Dynamic TEM. This chapter describes the current and future applications of in situ liquid DTEM to permit time-resolved atomic scale observations in an aqueous environment, Although this chapter focuses mostly on in situ liquid imaging, the same research potential exists for in situ gas experiments and the successful integration of these techniques promises new insights for understanding nanoparticle, catalyst and biological protein dynamics with unprecedented spatiotemporal resolution.

  8. Upgrade of the PNNL TEPC and Multisphere Spectrometer

    SciTech Connect (OSTI)

    Scherpelz, Robert I.; Conrady, Matthew M.

    2008-09-10

    The Pacific Northwest National Laboratory (PNNL) has used two types of instruments, the tissue equivalent proportional counter (TEPC) and the multisphere spectrometer for characterizing neutron radiation fields in support of neutron dosimetry at the Hanford site. The US Department of Energy recently issued new requirements for radiation protection standards in 10 CFR 835 which affect the way that neutron dose equivalent rates are evaluated. In response to the new requirements, PNNL has upgraded the analyses used in conjunction with the TEPC and multisphere. The analysis software for the TEPC was modified for this effort, and a new analysis code was selected for the multisphere. These new analysis techniques were implemented and tested with measurement data that had been collected in previous measurements. In order to test the effectiveness of the changes, measurements were taken in PNNL’s Low Scatter Room using 252Cf sources in both unmoderated and D2O-moderated configurations that generate well-characterized neutron fields. The instruments were also used at Los Alamos National Laboratory (LANL), in their Neutron Free-in-Air calibration room, also using neutron sources that generate well-characterized neutron fields. The results of the software modifications and the measurements are documented in this report. The TEPC measurements performed at PNNL agreed well with accepted dose equivalent rates using the traditional analysis, agreeing with the accepted value to within 13% for both unmoderated and moderated 252Cf sources. When the new analysis was applied to the TEPC measurement data, the results were high compared to the new accepted value. A similar pattern was seen for TEPC measurements at LANL. Using the traditional analysis method, results for all neutron sources showed good agreement with accepted values, nearly always less than 10%. For the new method of analysis, however, the TEPC responded with higher dose equivalent rates than accepted, by as much as 25

  9. 2012 National Electric Transmission Congestion Study: Presentation...

    Energy Savers [EERE]

    2012 National Electric Transmission Congestion Study: Presentation from Congestion Study Webinar Series 2012 National Electric Transmission Congestion Study: Presentation from...

  10. Technical Workshop: Resilience Metrics for Energy Transmission and

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Distribution Infrastructure | Department of Energy Resilience Metrics for Energy Transmission and Distribution Infrastructure Technical Workshop: Resilience Metrics for Energy Transmission and Distribution Infrastructure During this workshop, EPSA invited technical experts from industry, national laboratories, academia, and NGOs to discuss the state of play of and need for resilience metrics and how they vary by natural gas, liquid fuels and electric grid infrastructures. Issues important to

  11. Vice President, Transmission System Operations

    Broader source: Energy.gov [DOE]

    The VP for Transmission System Operations provides strategic leadership, direction, and oversight of the people, business processes, and systems that are responsible for the safe, reliable, and...

  12. AGENDA: PETROLEUM PRODUCT TRANSMISSION & DISTRIBUTION

    Broader source: Energy.gov [DOE]

    The agenda for the Quadrennial Energy Review (QER) public stakeholder meeting in New Orleans on petroleum product transmission, distribution, and storage.

  13. Electric Transmission Line Siting Compact

    Office of Environmental Management (EM)

    ... creates a method for states to site multi-state electric transmission lines. Three 4 levels of organization are provided: 5 A state project review panel within each ...

  14. Transmission Expansion in the Midwest

    Broader source: Energy.gov [DOE]

    At this unique forum, participants will hear top executives from the area's RTOs, utilities, transmission developers, and state regulatory agencies discuss and debate the most critical issues...

  15. Transmission Reliability | Department of Energy

    Office of Environmental Management (EM)

    ... Research focuses on five key areas: market design, long-term supply and transmission investment, renewable integration, demand response, and environmental impacts. Researchers use ...

  16. NREL: Transmission Grid Integration - News

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    The National Renewable Energy Laboratory (NREL) will be strongly supporting this ... Archives 2015 | 2014 Printable Version Transmission Grid Integration Home Issues Projects ...

  17. NREL: Transmission Grid Integration - Webmaster

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Your message: Send Message Printable Version Transmission Grid Integration Home Issues ... NREL is a national laboratory of the U.S. Department of Energy, Office of Energy ...

  18. DOE Electricity Transmission System Workshop

    Broader source: Energy.gov (indexed) [DOE]

    ... Activities can span from basic R&D through demonstration projects. Parallel Breakout Sessions (see white paper: "DOE Action Plan Addressing the Electricity Transmission System") ...

  19. The Wheeling and Transmission Manual, Second Edition

    SciTech Connect (OSTI)

    Weiss, L.; Spiewak, S.

    1991-01-01

    The Wheeling and Transmission Manual addresses the key issues involved in the debate: the need for coordination, the extent to which access should be permitted, various pricing methodologies which might be employed, obstacles to the addition of new transmission capacity, and contractual matters which should be considered in negotiations between the parties. As one shall see, these matters are all interrelated and the resolution of any of them may affect the outcome of the others. The Manual is designed to give an overview of the issues involved. It is not intended exclusively for the expert engineer or attorney, although both might benefit from it. Rather, the Manual was written with the objective of providing decisionmakers and policymakers with detailed, timely and understandable materials to evaluate the specific circumstances affecting their companies. Each chapter of the book is indexed separately.

  20. Small passenger car transmission test: Chevrolet Luv transmission

    SciTech Connect (OSTI)

    Bujold, M.P.

    1980-06-01

    The small passenger car transmission test was initiated to supply electric vehicle manufacturers with technical information regarding the performance of commercially available transmissions. This information would enable EV manufacturers to design a more energy efficient vehicle. With this information the manufacturers would be able to estimate vehicle driving range as well as speed and torque requirements for specific roadload performance characteristics. This report covers the 1978 Chevrolet Luv Truck manual transmission. This transmission was tested per a passenger car automatic transmission test code (SAE J65lb) which required drive performance, coast performance, and no load test conditions. The portion of the test code which involved the throttle valve modulation and line pressure were deleted since they did not apply to the manual transmission. Under these test conditions the transmission attained maximum efficiencies in the upper 90% range at rated load for both drive performance tests and coast performance tests. The major results of this test are the torque speed and efficiency curves which are located in the data section of this report. These graphs map the complete performance characteristics for the Chevrolet Luv Truck Manual transmission. This information will facilitate the vehicle manufacturer in the design of a more energy efficient vehicle.

  1. EC Transmission Line Materials

    SciTech Connect (OSTI)

    Bigelow, Tim S

    2012-05-01

    The purpose of this document is to identify materials acceptable for use in the US ITER Project Office (USIPO)-supplied components for the ITER Electron cyclotron Heating and Current Drive (ECH&CD) transmission lines (TL), PBS-52. The source of material property information for design analysis shall be either the applicable structural code or the ITER Material Properties Handbook. In the case of conflict, the ITER Material Properties Handbook shall take precedence. Materials selection, and use, shall follow the guidelines established in the Materials Assessment Report (MAR). Materials exposed to vacuum shall conform to the ITER Vacuum Handbook. [Ref. 2] Commercial materials shall conform to the applicable standard (e.g., ASTM, JIS, DIN) for the definition of their grade, physical, chemical and electrical properties and related testing. All materials for which a suitable certification from the supplier is not available shall be tested to determine the relevant properties, as part of the procurement. A complete traceability of all the materials including welding materials shall be provided. Halogenated materials (example: insulating materials) shall be forbidden in areas served by the detritiation systems. Exceptions must be approved by the Tritium System and Safety Section Responsible Officers.

  2. Upgrade of the Los Alamos Plutonium Facility control system

    SciTech Connect (OSTI)

    Pope, N.G.; Turner, W.J.; Brown, R.E.; Bibeau, R.A.; Davis, R.R.; Hogan, K.

    1996-05-01

    After 20 yrs service, the Los Alamos Plutonium Facility is undergoing an upgrade to its aging Facility Control System. The new system design includes a network of redundantly-paired programmable logic controllers that will interface with about 2200 field data points. The data communications network that has been designed includes a redundant, self-healing fiber optic data highway as well as a fiber optic ethernet. Commercially available human-machine interface software running on a UNIX-based system displays facility subsystem status operator X-terminals. Project design features, methods, costs, and schedule are discussed.

  3. The D0 level 3 DAQ system: operation and upgrades

    SciTech Connect (OSTI)

    Garcia-Bellido, Aran; Bose, Tulika; Brooijmans, Gustaaf; Chapin, Doug; Cutts, David; Fuess, Stuart; Gadfort, Thomas; Haas, Andrew; Lee, William; Rechenmacher, Ron; Snyder, Scott; /Washington U., Seattle /Brown U. /Columbia U. /Fermilab /Brookhaven

    2007-05-01

    The D{O} Level 3 data acquisition system for Run II of the Tevatron has been reliably operating since May 2002. Designed to handle average event sizes of 250 kilobytes at a rate of 1 kHz, the system has been upgraded to be able to process more events, doubling its typical output rate from 50 Hz to 100 Hz, while coping with higher event sizes at the beginning of high luminosity collider stores. The system routes and transfers event fragments from 63 VME crates to any of approximately 320 processing nodes. The addition of more farm nodes, the performance of the components, and the running experience are described here.

  4. PERFORMANCE OF AND UPGRADES TO THE SNS COLLIMATOR SYSTEMS

    SciTech Connect (OSTI)

    Plum, Michael A; Abdou, Ashraf A; Jacobs, Lorelei L; Janney, Jim G; Geoghegan, Patrick J; McTeer, Stephen Mark; Popova, Irina; Ferguson, Phillip D; Zhukov, Alexander P

    2009-01-01

    As the Spallation Neutron Source (SNS) beam power is increased, the collimator systems are becoming correspondingly more important. The High Energy Beam Transport (HEBT) transverse collimators are now routinely used during neutron production. We are in the process of redesigning the HEBT momentum collimation system due to problems with gas production from radiolysis. The Ring collimators are designed for two-stage operation but to date they are mainly used in one-stage mode. In this paper we will discuss the status, the operational performance, and upgrades to the collimation systems.

  5. A number of upgrades on RHIC power supply system

    SciTech Connect (OSTI)

    Mi, C.; Bruno, D.; Drozd, J.; Nolan, T.; Orsatti, F.; Heppener, G.; Di Lieto, A.; Schultheiss, C.; Samms, T.; Zapasek, R.; Sandberg, J.

    2015-05-03

    This year marks the 15th run for the Relativistic Heavy Ion Collider (RHIC). Operation of a reliable superconducting magnet power supply system is a key factor of an accelerator’s performance. Over the past 15 years, the RHIC power supply group has made many improvements to increase the machine availability and reduce failures. During these past 15 years of operating RHIC a lot of problems have been solved or addressed. In this paper some of the essential upgrades/improvements are discussed.

  6. Network Upgrade for the SLC: Control System Modifications

    SciTech Connect (OSTI)

    Crane, M.; Mackenzie, R.; Sass, R.; Himel, T.; /SLAC

    2011-09-09

    Current communications between the SLAC Linear Collider control system central host and the SLCmicros is built upon the SLAC developed SLCNET communication hardware and protocols. We will describe how the Internet Suite of protocols (TCP/IP) are used to replace the SLCNET protocol interface. The major communication pathways and their individual requirements are described. A proxy server is used to reduce the number of total system TCP/IP connections. The SLCmicros were upgraded to use Ethernet and TCP/IP as well as SLCNET. Design choices and implementation experiences are addressed.

  7. 2009 Section V: Superconducting Cyclotron, Instrumentation, and RIB Upgrade

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    09 - March 31, 2010 H. L. Clark, J. Brinkley, G. Chubarian, V. Horvat, B. Hyman, and G. Tabacaru Cyclotron computing R. Burch and K. Hagel Cyclotron Institute upgrade project H. L. Clark, F. Abegglen, G. Chubarian, G. Derrig, G. Kim, D. May, G. Souliotis and G. Tabacaru Testing the injection of ions in the CB-ECRIS at the Cyclotron Institute G. Tabacaru, D. P. May, and J. Saathoff Digital signal processing for improved half-life measurements L. Chen and J. C. Hardy A new TDC-based data

  8. Boiler Upgrades and Decentralizing Steam Systems Save Water and Energy at

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Naval Air Station Oceana | Department of Energy Boiler Upgrades and Decentralizing Steam Systems Save Water and Energy at Naval Air Station Oceana Boiler Upgrades and Decentralizing Steam Systems Save Water and Energy at Naval Air Station Oceana January 7, 2015 - 4:52pm Addthis Boiler Upgrades and Decentralizing Steam Systems Save Water and Energy at Naval Air Station Oceana Addthis Related Articles Building Science Corporation worked with Transformations, Inc., on a subdivision of

  9. Kitchen Appliance Upgrades Improve Water Efficiency at U.S. Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Defense Exchange Facilities | Department of Energy Kitchen Appliance Upgrades Improve Water Efficiency at U.S. Department of Defense Exchange Facilities Kitchen Appliance Upgrades Improve Water Efficiency at U.S. Department of Defense Exchange Facilities Kitchen Appliance Upgrades Improve Water Efficiency at U.S. Department of Defense Exchange Facilities Case study details the U.S. Department of Defense (DOD) Exchange (formerly the Army and Air Force Exchange Service), which took a

  10. NIST Releases Test Framework for Upgrading of Smart Meters | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Energy Releases Test Framework for Upgrading of Smart Meters NIST Releases Test Framework for Upgrading of Smart Meters July 12, 2012 - 10:46am Addthis The National Institute of Standards and Technology (NIST) has released a draft set of guidelines that will help utilities test their procedures for upgrading their smart meters securely from a remote location and determine whether their procedures conform with the National Electrical Manufacturers Association (NEMA) Standard for Smart Grid

  11. Spotlight on Austin, Texas: Best Offer Ever Produces 564 Upgrades in Record

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Time | Department of Energy Spotlight on Austin, Texas: Best Offer Ever Produces 564 Upgrades in Record Time Spotlight on Austin, Texas: Best Offer Ever Produces 564 Upgrades in Record Time This Better Buildings case study from April 2011 focuses on grantee partner Austin. Spotlight on Austin, Texas (296.86 KB) More Documents & Publications Spotlight on Austin, Texas: Best Offer Ever Produces Upgrades in Record Time Spotlight on Austin, Texas: Let Your Contractor Be Your Guide for Big

  12. Computing Sciences Staff Help East Bay High Schoolers Upgrade their Summer

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Computing Sciences Staff Help East Bay High Schoolers Upgrade their Summer Computing Sciences Staff Help East Bay High Schoolers Upgrade their Summer August 6, 2015 Jon Bashor, jbashor@lbl.gov, +1 510 486 5849 To help prepare students from underrepresented groups learn about careers in a variety of IT fields, the Laney College Computer Information Systems Department offered its Upgrade: Computer Science Program. Thirty-eight students from 10 East Bay high schools registered for the eight-week

  13. PACE Adds Market Value for Home Energy Upgrades | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    PACE Adds Market Value for Home Energy Upgrades PACE Adds Market Value for Home Energy Upgrades July 19, 2016 - 6:56pm Addthis PACE Adds Market Value for Home Energy Upgrades Dr. Kathleen Hogan Dr. Kathleen Hogan Deputy Assistant Secretary for Energy Efficiency What are the key facts? Newly announced partnerships and resources by the Energy Department will bring the benefits of energy efficiency and renewable energy to more states and communities. The Energy Department is releasing updated

  14. ALS-U Update: BESAC Announces Results of Facility Upgrade Prioritization

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ALS-U Update: BESAC Announces Results of Facility Upgrade Prioritization ALS-U Update: BESAC Announces Results of Facility Upgrade Prioritization Print by Dave Robin, on behalf of the ALS-U Project Development Team On Thursday, June 9, DOE's Basic Energy Sciences Advisory Committee (BESAC) released the recommendations of the BES Facility Upgrade Prioritization Subcommittee. I'm pleased to announce that the subcommittee (whose full report can be found here) considers the proposed ALS-U project

  15. Design and Validation of Control Room Upgrades Using a Research Simulator Facility

    SciTech Connect (OSTI)

    Ronald L. Boring; Vivek Agarwal; Jeffrey C. Joe; Julius J. Persensky

    2012-11-01

    Since 1981, the United States (U.S.) Nuclear Regulatory Commission (NRC) [1] requires a plant- specific simulator facility for use in training at U.S. nuclear power plants (NPPs). These training simulators are in near constant use for training and qualification of licensed NPP operators. In the early 1980s, the Halden Man-Machine Laboratory (HAMMLab) at the Halden Reactor Project (HRP) in Norway first built perhaps the most well known set of research simulators. The HRP offered a high- fidelity simulator facility in which the simulator is functionally linked to a specific plant but in which the human-machine interface (HMI) may differ from that found in the plant. As such, HAMMLab incorporated more advanced digital instrumentation and controls (I&C) than the plant, thereby giving it considerable interface flexibility that researchers took full advantage of when designing and validating different ways to upgrade NPP control rooms. Several U.S. partnersthe U.S. NRC, the Electrical Power Research Institute (EPRI), Sandia National Laboratories, and Idaho National Laboratory (INL) as well as international members of the HRP, have been working with HRP to run control room simulator studies. These studies, which use crews from Scandinavian plants, are used to determine crew behavior in a variety of normal and off-normal plant operations. The findings have ultimately been used to guide safety considerations at plants and to inform advanced HMI designboth for the regulator and in industry. Given the desire to use U.S. crews of licensed operators on a simulator of a U.S. NPP, there is a clear need for a research simulator facility in the U.S. There is no general-purpose reconfigurable research oriented control room simulator facility in the U.S. that can be used for a variety of studies, including the design and validation of control room upgrades.

  16. Developing Enzyme and Biomimetic Catalysts for Upgrading Heavy Crudes via Biological Hydrogenation and Hydrodesulfurization

    SciTech Connect (OSTI)

    Borole, A P

    2006-08-22

    The recovery and conversion of heavy oils is limited due to the high viscosity of these crudes and their high heteroatom content. Conventional technology relies on thermochemical hydrogenation and hydrodesulfurization to address these problems and is energy intensive due to the high operating temperature and pressure. This project was initiated to explore biological catalysts for adding hydrogen to the heavy oil molecules. Biological enzymes are efficient at hydrogen splitting at very mild conditions such as room temperature and pressure, however, they are very specific in terms of the substrates they hydrogenate. The goal of the project was to investigate how the specificity of these enzymes can be altered to develop catalysts for oil upgrading. Three approaches were used. First was to perform chemical modification of the enzyme surface to improve binding of other non-natural substrates. Second approach was to expose the deeply buried catalytic active site of the enzyme by removal of protein scaffolding to enable better interaction with other substrates. The third approach was based on molecular biology to develop genetically engineered systems for enabling targeted structural changes in the enzyme. The first approach was found to be limited in success due to the non-specificity of the chemical modification and inability to target the region near the active site or the site of substrate binding. The second approach produced a smaller catalyst capable of catalyzing hydrogen splitting, however, further experimentation is needed to address reproducibility and stability issues. The third approach which targeted cloning of hydrogenase in alternate hosts demonstrated progress, although further work is necessary to complete the cloning process. The complex nature of the hydrogenase enzyme structure-function relationship and role of various ligands in the protein require significant more research to better understand the enzyme and to enable success in strategies in

  17. Y-12 Completes Major Upgrade of Compressed Air Systems | National Nuclear

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Security Administration | (NNSA) Major Upgrade of Compressed Air Systems September 26, 2007 Microsoft Office document icon NR-09-07

  18. CRAD, Safety Basis Upgrade Review (DOE-STD-3009-2014) - May 15...

    Office of Environmental Management (EM)

    1) provides objectives, criteria, and approaches for establishing and maintaining the safety basis at nuclear facilities. CRAD, Safety Basis Upgrade Review (DOE-STD-3009-2014)...

  19. Project X ICD-2 and its upgrades for Neutrino Factory or Muon Collider

    SciTech Connect (OSTI)

    Lebedev, Valeri; Nagaitsev, Sergei; /Fermilab

    2009-10-01

    This paper reviews the Initial Configuration Document for Fermilab's Project X and considers its possible upgrades for neutrino factory or muon collider.

  20. What's Working in Residential Energy Efficiency Upgrade Programs Workshop, May 2011

    Broader source: Energy.gov [DOE]

    On May 20, 2011, the Better Buildings Neighborhood Program held the What's Working in Residential Energy Efficiency Upgrade Programs workshop. Better Buildings hosted the workshop in collaboration...

  1. PPPL to launch major upgrade of key fusion energy test facility...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    to launch major upgrade of key fusion energy test facility NSTX project will produce most ... of nuclear fusion as a clean, safe and abundant fuel for generating electricity. ...

  2. Energy Upgrade California in Los Angeles County-- The Flex Path Program

    Broader source: Energy.gov [DOE]

    Energy Upgrade California in Los Angeles County: The Flex Path Program. Provides an overview of the Flex Path Pilot Program, progress and next steps.

  3. Upgrading of heavy oil from the San Joaquin Valley of California by aqueous pyrolysis

    SciTech Connect (OSTI)

    Reynolds, J.G.; Murray, A.M.; Nuxoll, E.V.; Fox, G.A.

    1995-10-01

    Midway Sunset crude oil and well-head oil were treated at elevated temperatures in a closed system with the presence of water. Mild to moderate upgrading, as measured by increase in API gravity, was observed at 400{degrees}C or above. Reduced pressure operation exhibited upgrading activity comparable to upgrading under normal aqueous pyrolysis conditions. Reduced pressure operation was obtained by the use of specific blending methods, a surfactant, and the proper amount of water. The use of additives provided additional upgrading. The best of the minimum set tested was Co(II) 2-ethylhexanoate. Fe(III) 2-ethylhexanoate also showed some activity under certain conditions.

  4. Upgrading of heavy oil from the San Joaquin valley of California by aqueous pyrolysis

    SciTech Connect (OSTI)

    Reynolds, J.G.; Murray, A.M.; Nuxoll, E.V.; Fox, G.A.; Thorsness, C.B.; Khan, M.R.

    1997-08-01

    Midway Sunset crude oil and well-head oil were treated at elevated temperatures in a closed system with the presence of water. Mild to moderate upgrading, as measured by increasing in API gravity, was observed at 400 C or above. Reduced pressure operation exhibited upgrading activity comparable to upgrading under normal aqueous pyrolysis conditions. Reduced pressure operation was obtained by the use of specific blending methods, a surfactant, and the proper amount of water. The use of metal complexes provided additional upgrading. The best of the minimum set tested was Co(II) 2-ethylhexanoate. Fe, Zn, Mo, Cu, and Ni complexes also showed some levels of activity.

  5. Upgrade Boilers with Energy-Efficient Burners - Steam Tip Sheet #24

    SciTech Connect (OSTI)

    2012-01-01

    This revised AMO steam tip sheet on upgrading boilers provides how-to advice for improving industrial steam systems using low-cost, proven practices and technologies.

  6. Federal Finance Facilities Available for Energy Efficiency Upgrades and Clean Energy Deployment

    Broader source: Energy.gov [DOE]

    This webinar, held on Sept. 24, 2013, provides information on federal finance facilities available for energy efficiency upgrades and clean energy deployment.

  7. Federal Finance Facilities Available for Energy Efficiency Upgrades and Clean Energy Deployment

    Broader source: Energy.gov [DOE]

    This presentation, given through the DOE's Technical Assitance Program (TAP), provides information on Federal Finance Facilities Available for Energy Efficiency Upgrades and Clean Energy Deployment.

  8. RF Power Upgrade for CEBAF at Jefferson Laboratory

    SciTech Connect (OSTI)

    Andrew Kimber,Richard Nelson

    2011-03-01

    Jefferson Laboratory (JLab) is currently upgrading the 6GeV Continuous Electron Beam Accelerator Facility (CEBAF) to 12GeV. As part of the upgrade, RF systems will be added, bringing the total from 340 to 420. Existing RF systems can provide up to 6.5 kW of CW RF at 1497 MHZ. The 80 new systems will provide increased RF power of up to 13 kW CW each. Built around a newly designed and higher efficiency 13 kW klystron developed for JLab by L-3 Communications, each new RF chain is a completely revamped system using hardware different than our present installations. This paper will discuss the main components of the new systems including the 13 kW klystron, waveguide isolator, and HV power supply using switch-mode technology. Methodology for selection of the various components and results of initial testing will also be addressed. Notice: Authored by Jefferson Science Associates, LLC under U.S. DOE Contract No. DE-AC05-06OR23177. The U.S. Government retains a non-exclusive, paid-up, irrevocable, world-wide license to publish or reproduce this manuscript for U.S. Government purposes.

  9. Post Retort, Pre Hydro-treat Upgrading of Shale Oil

    SciTech Connect (OSTI)

    Gordon, John

    2012-09-30

    Various oil feedstocks, including oil from oil shale, bitumen from tar sands, heavy oil, and refin- ery streams were reacted with the alkali metals lithium or sodium in the presence of hydrogen or methane at elevated temperature and pressure in a reactor. The products were liquids with sub- stantially reduced metals, sulfur and nitrogen content. The API gravity typically increased. Sodi- um was found to be more effective than lithium in effectiveness. The solids formed when sodium was utilized contained sodium sulfide which could be regenerated electrochemically back to so- dium and a sulfur product using a "Nasicon", sodium ion conducting membrane. In addition, the process was found to be effective reducing total acid number (TAN) to zero, dramatically reduc- ing the asphaltene content and vacuum residual fraction in the product liquid. The process has promise as a means of eliminating sulfur oxide and carbon monoxide emissions. The process al- so opens the possibility of eliminating the coking process from upgrading schemes and upgrad- ing without using hydrogen.

  10. Analysis of NSTX Upgrade OH Magnet and Center Stack

    SciTech Connect (OSTI)

    A. Zolfaghari, P. Titus, J. Chrzanowski, A. Salehzadeh, F. Dahlgren

    2010-11-30

    The new ohmic heating (OH) coil and center stack for the National Spherical Torus Experiment (NSTX) upgrade are required to meet cooling and structural requirements for operation at the enhanced 1 Tesla toroidal field and 2 MA plasma current. The OH coil is designed to be cooled in the time between discharges by water flowing in the center of the coil conductor. We performed resistive heating and thermal hydraulic analyses to optimize coolant channel size to keep the coil temperature below 100 C and meet the required 20 minute cooling time. Coupled electromagnetic, thermal and structural FEA analyses were performed to determine if the OH coil meets the requirements of the structural design criteria. Structural response of the OH coil to its self-field and the field from other coils was analyzed. A model was developed to analyze the thermal and electromagnetic interaction of centerstack components such as the OH coil, TF inner legs and the Bellville washer preload mechanism. Torsional loads from the TF interaction with the OH and poloidal fields are transferred through the TF flag extensions via a torque transfer coupling to the rest of the tokamak structure. A 3D FEA analysis was performed to qualify this design. The results of these analyses, which will be presented in this paper, have led to the design of OH coil and centerstack components that meet the requirements of the NSTX-upgrade structural design criteria.

  11. Fact #850: December 8, 2014 Automatic Transmissions have closed the Fuel Economy Gap with Manual Transmissions

    Broader source: Energy.gov [DOE]

    Historically, manual transmissions have delivered better fuel economy than automatic transmissions. However, improvements in the efficiency of automatic transmissions have closed that gap in recent...

  12. Environmental Assessment for Central Power and Light Company`s proposed Military Highway-CFE tie 138/69-kV transmission line project Brownsville, Cameron County, Texas

    SciTech Connect (OSTI)

    Not Available

    1992-04-01

    Central Power and Light Company (CPL) intends to upgrade its existing transmission line ties with the Commision Federal de Electricidad (CFE) system in Mexico. CPL currently has a single 69-kilovolt (kV) transmission line in the Brownsville area which connects CPL`s system with the system of CFE. This existing line runs between the Brownsville Switching Station, located on Laredo Road in Brownsville, Cameron County, Texas, and an existing CFE 69-kV line at the Rusteberg Bend of the Rio Grande in Cameron County. Under current conditions of need, the existing 69-kV line does not possess sufficient capability to engage in appropriate power exchanges. Therefore, CPL is proposing to build a new line to link up with CFE. This proposed line would be a double-circuit line, which would (1) continue (on a slightly relocated route) the existing 69-kV tie from CPL`s Brownsville Switching Station to CFE`s facilities, and (2) add a 138-kV tie from the Military Highway Substation, located on Military Highway (US Highway 281), to CFE`s facilities. The proposed 138/69-kV line, which will be constructed and operated by CPL, will be built primarily on steel single-pole structures within an average 60-foot (ft) wide right-of-way (ROW). It will be approximately 6900--9200 ft (1.3--1.7 miles) in length, depending on the alternative route constructed.

  13. Electrical transmission line diametrical retainer

    DOE Patents [OSTI]

    Hall, David R.; Hall, Jr., H. Tracy; Pixton, David; Dahlgren, Scott; Sneddon, Cameron; Briscoe, Michael; Fox, Joe

    2004-12-14

    The invention is a mechanism for retaining an electrical transmission line. In one embodiment of the invention it is a system for retaining an electrical transmission line within down hole components. In accordance with one aspect of the invention, the system includes a plurality of downhole components, such as sections of pipe in a drill string. The system also includes a coaxial cable running between the first and second end of a drill pipe, the coaxial cable having a conductive tube and a conductive core within it. The invention allows the electrical transmission line to with stand the tension and compression of drill pipe during routine drilling cycles.

  14. EIS-0107: Mead-Phoenix +500-kV Direct Current Transmission Line

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration (WAPA) prepared this statement to analyze the potential environmental and socioeconomic impacts arising from WAPA and regional project sponsors’ proposal to construct a 500 kilovolt (kV) alternating current (AC) transmission line with the capability to be upgraded later to 500kV direct current (DC), connecting the Westwing Substation, located north of Phoenix, Arizona, with a new McCullough II Substation, located approximately 14 miles west of Boulder City, Nevada. This statement modifies a previously prepared federal statement from which the participants' election to proceed had not occurred at the time this statement was prepared.

  15. Great Plains Wind Energy Transmission Development Project

    SciTech Connect (OSTI)

    Brad G. Stevens, P.E.; Troy K. Simonsen; Kerryanne M. Leroux

    2012-06-09

    EERC, in collaboration with Meridian Environmental Services, developed and demonstrated the efficacy of a wind energy forecasting system for use in scheduling energy output from wind farms for a regional electrical generation and transmission utility. With the increased interest at the time of project award in the production of hydrogen as a critical future energy source, many viewed hydrogen produced from wind-generated electricity as an attractive option. In addition, many of the hydrogen production-related concepts involve utilization of energy resources without the need for additional electrical transmission. For this reason, under Task 4, the EERC provided a summary of end uses for hydrogen in the region and focused on one end product in particular (fertilizer), including several process options and related economic analyses.

  16. Integrated survey and design for transmission lines

    SciTech Connect (OSTI)

    Miller, M.A.; Simpson, K.D.

    1994-12-31

    Gathering and compiling information on the features and uses of the land within a proposed corridor provides the basis for selecting a route, obtaining easements, and designing and constructing a transmission line. Traditionally, gathering this information involved searches of existing maps and records to obtain the available information, which would then be supplemented with aerial photography to record current conditions. Ground surveys were performed to collect topographic data for design purposes. This information was manually transferred to drawings and other documents to show the terrain, environmentally sensitive areas, property ownership, and existing facilities. These drawing served as the base to which the transmission line right-of-way, structures, and other design information were added. As the design was completed, these drawings became the source of information for constructing the line and ultimately, the record of the facility. New technologies and the every growing need for instantly accessible information have resulted in changes in almost every step of gathering, storing and using information. Electronic data collection, global positioning systems (GPS), digitized terrain models, computerized design techniques, development of drawings using CAD, and graphical information systems (GIS) have individually resulted in significant advancements in this process. Combining these components into an integrated system, however, is truly revolutionizing transmission line engineering. This paper gives an overview of the survey and mapping information that is required for transmission line projects, review the traditional techniques that have been employed to obtain and utilize this information, and discuss the recent advances in the technology. Additionally, a system is presented that integrates the components in this process to achieve efficiency, minimize chances of errors, and provide improved access to project information.

  17. National Transmission Grid Study: 2002

    Broader source: Energy.gov [DOE]

    National Transmission Grid Study: The National Energy Policy Plan directed the U.S. Department of Energy (DOE) to conduct a study to examine the benefits of establishing a national electricity...

  18. National Electric Transmission Congestion Studies

    Office of Energy Efficiency and Renewable Energy (EERE)

    Section 216(a) of the Federal Power Act, as amended by the Energy Policy Act of 2005, directs the U.S. Department of Energy (DOE) to conduct a study every three years on electric transmission congestion and constraints within the Eastern and Western Interconnections. The American Reinvestment and Recovery Act of 2009 (Recovery Act) further directed the Secretary to include in the 2009 Congestion Study an analysis of significant potential sources of renewable energy that are constrained by lack of adequate transmission capacity. Based on this study, and comments concerning it from states and other stakeholders, the Secretary of Energy may designate any geographic area experiencing electric transmission capacity constraints or congestion as a national interest electric transmission corridor (National Corridor).

  19. Bulk Power Generation and Transmission

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Innovative Opportunities Blue lines: Transmission Grid Red lines: Lines that are congested or at outages - in RealTime Yellow and Red iconsdots: Power plant RealTime production ...

  20. EIS-0231: Navajo Transmission Project

    Broader source: Energy.gov [DOE]

    This EIS evaluates the environmental impacts of a proposal to by Dine Power Authority, a Navajo Nation enterprise, to construct, operate, and maintain a 500 kilovolt (kV) transmission line planned...