Sample records for transmission operator rto

  1. RTO Briefing

    SciTech Connect (OSTI)

    Steve Wiese

    2003-11-01T23:59:59.000Z

    OAK-B135 Transmission Updates The summary of this report is: (1) Small generators are not happy with FERC's Small Generator Interconnection NOPR, saying the proposed rule ignores much of the consensus developed between small generators and transmission owners during the ANOPR process. California wind generators seek clarification that repowering an existing facility or changing contract terms would not trigger a reevaluation of the interconnection. (2) The choices of former Alliance companies about which RTO to join, MISO or PJM, and whether they can obtain approval from states to do so, has created such a tangle that FERC held two days of hearings at the end of September on the issues and options for resolving them. But in addition to some constructive input, the hearings produced even more uncertainty, with transmission companies announcing their need to reassess their own RTO commitments depending on the decisions of others. (3) In the West, the Seams Steering Group--Western Interconnection (SSG-WI) completed a west-wide transmission study with a renewable energy scenario, the California ISO received FERC's approval on its market redesign proposal, and RTO West worked toward finalizing high-level consensus documents describing Day 1 implementation of the proposed RTO. (4) In Texas, ERCOT began $157 million in upgrades to the transmission system around McCamey--increasing capacity in and out of the area enough to handle existing wind projects there.

  2. IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 20, NO. 1, FEBRUARY 2005 171 Dispatchable Transmission in RTO Markets

    E-Print Network [OSTI]

    Baldick, Ross

    .S. ISO/RTO markets.3 For our purposes, the core SMD elements include locational marginal pricing (LMP), flowgate marginal pricing (FMP), and financial transmission rights (FTRs).4 In addition, the SMD proposal to transmission. In the context of RTOs, marginal transmission pricing and uni

  3. A Review of Recent RTO Benefit-Cost Studies: Toward MoreComprehensive Assessments of FERC Electricity RestructuringPolicies

    SciTech Connect (OSTI)

    Eto, Joseph H.; Lesieutre, Bernard C.

    2005-12-01T23:59:59.000Z

    During the past three years, government and private organizations have issued more than a dozen studies of the benefits and costs of Regional Transmission Organizations (RTOs). Most of these studies have focused on benefits that can be readily estimated using traditional production-cost simulation techniques, which compare the cost of centralized dispatch under an RTO to dispatch in the absence of an RTO, and on costs associated with RTO start-up and operation. Taken as a whole, it is difficult to draw definitive conclusions from these studies because they have not examined potentially much larger benefits (and costs) resulting from the impacts of RTOs on reliability management, generation and transmission investment and operation, and wholesale electricity market operation. This report: (1) Describes the history of benefit-cost analysis of FERC electricity restructuring policies; (2)Reviews current practice by analyzing 11 RTO benefit-cost studies that were published between 2002 and 2004 and makes recommendations to improve the documentation of data and methods and the presentation of findings in future studies that focus primarily on estimating short-run economic impacts; and (3) Reviews important impacts of FERC policies that have been overlooked or incompletely treated by recent RTO benefit-cost studies and the challenges to crafting more comprehensive assessments of these impacts based on actual performance, including impacts on reliability management, generation and transmission investment and operation, and wholesale electricity market operation.

  4. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    Report.pdf Midwest ISO (MISO). 2003. Midwest TransmissionConference September 2007 MISO. 2007. Midwest Transmission2006 SDG&E Midwest ISO (MISO) ISO/RTO February 2007 MISO '06

  5. Abstract--Electric energy transmission is essential for the operation of competitive energy markets. Transmission

    E-Print Network [OSTI]

    Catholic University of Chile (Universidad Católica de Chile)

    TECHNIQUES Meta-heuristic techniques are a hybrid version of classical and heuristic optimization. Basically1 Abstract-- Electric energy transmission is essential for the operation of competitive energy markets. Transmission expansion planning has been defined as a complex combinatorial optimization problem

  6. Comments in response to FERC rulemaking on regional transmission organizations

    E-Print Network [OSTI]

    Joskow, Paul L.

    1999-01-01T23:59:59.000Z

    On May 13, 1999, the Federal Energy Regulatory Commission (FERC) issued a Notice of Proposed Rulemaking (NOPR) on Regional Transmission Organizations (RTO). The purpose of the NOPR is to solicit comments on proposed FERC ...

  7. Transmission Matters Now: How Will Power Market Regulations Impact the Industrial's Power Supply Costs and Reliability?

    E-Print Network [OSTI]

    James, F.; Beidas, H.; Fox, R.

    and reliability. The paper also identifies what specifically may be involved, from a technical and regulatory standpoint, in the following three areas: 1) Transmission Risks -SMD and RTO/ISO, 2) Alternative Retail Supply, and 3) Self-Generation....

  8. An operational and institutional modular analysis framework of Transmission and System Operator

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    to internalise network externality in energy price. The nodal pricing is in theory the most efficient method since the power flows externality is internalised in the energy market. It gives an energy price per PLUMEL Energy Department at Supelec Abstract Transmission and System Operator (TSO) is the power flows

  9. Property:EIA/861/RtoSpp | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation,PillarPublicationType JumpDOEInvolveRtoSpp Jump to: navigation, search Property

  10. Optimization for Design and Operation of Natural Gas Transmission Networks

    E-Print Network [OSTI]

    Dilaveroglu, Sebnem 1986-

    2012-08-22T23:59:59.000Z

    and compressor stations. On an existing network, the model also optimizes the total flow through pipelines that satisfy demand to determine the best purchase amount of gas. A mixed integer nonlinear programming model for steady-state natural gas transmission...

  11. Transmission Considerations for Market Operation: U.S. Design (Presentation)

    SciTech Connect (OSTI)

    Ela, E.

    2011-06-01T23:59:59.000Z

    Presented at the Utility Wind Integration Group (UWIG) Workshop on Market Design and Operation With Variable Renewables, 22 June 2011, Fredericia, Denmark. This presentation provides an overview of the present U.S. electricity market, how it operates, and some solutions for improving its operation, cost accounting, and integration of renewable power resources.

  12. Optimization for Design and Operation of Natural Gas Transmission Networks 

    E-Print Network [OSTI]

    Dilaveroglu, Sebnem 1986-

    2012-08-22T23:59:59.000Z

    designing and operating the network. A well-designed network helps natural gas companies minimize the costs while increasing the customer service level. The aim of the study is to determine the optimum installation scheduling and locations of new pipelines...

  13. Renewable Resource Integration Project - Scoping Study of Strategic Transmission, Operations, and Reliability Issues

    SciTech Connect (OSTI)

    Eto, Joseph; Budhraja, Vikram; Ballance, John; Dyer, Jim; Mobasheri, Fred; Eto, Joseph

    2008-07-01T23:59:59.000Z

    California is on a path to increase utilization of renewable resources. California will need to integrate approximately 30,000 megawatts (MW) of new renewable generation in the next 20 years. Renewable resources are typically located in remote locations, not near the load centers. Nearly two/thirds or 20,000 MW of new renewable resources needed are likely to be delivered to Los Angeles Basin transmission gateways. Integration of renewable resources requires interconnection to the power grid, expansion of the transmission system capability between the backbone power grid and transmission gateways, and increase in delivery capacity from transmission gateways to the local load centers. To scope the transmission, operations, and reliability issues for renewables integration, this research focused on the Los Angeles Basin Area transmission gateways where most of new renewables are likely. Necessary actions for successful renewables integration include: (1) Expand Los Angeles Basin Area transmission gateway and nomogram limits by 10,000 to 20,000 MW; (2) Upgrade local transmission network for deliverability to load centers; (3) Secure additional storage, demand management, automatic load control, dynamic pricing, and other resources that meet regulation and ramping needed in real time operations; (4) Enhance local voltage support; and (5) Expand deliverability from Los Angeles to San Diego and Northern California.

  14. Impact of Utility-Scale Distributed Wind on Transmission-Level System Operations

    SciTech Connect (OSTI)

    Brancucci Martinez-Anido, C.; Hodge, B. M.

    2014-09-01T23:59:59.000Z

    This report presents a new renewable integration study that aims to assess the potential for adding distributed wind to the current power system with minimal or no upgrades to the distribution or transmission electricity systems. It investigates the impacts of integrating large amounts of utility-scale distributed wind power on bulk system operations by performing a case study on the power system of the Independent System Operator-New England (ISO-NE).

  15. Understanding Cognitive and Collaborative Work: Observations in an Electric Transmission Operations Control Center

    SciTech Connect (OSTI)

    Obradovich, Jodi H.

    2011-09-30T23:59:59.000Z

    This paper describes research that is part of an ongoing project to design tools to assist in the integration of renewable energy into the electric grid. These tools will support control room dispatchers in real-time system operations of the electric power transmission system which serves much of the Western United States. Field observations comprise the first phase of this research in which 15 operators have been observed over various shifts and times of day for approximately 90 hours. Findings describing some of the cognitive and environmental challenges of managing the dynamically changing electric grid are presented.

  16. Transmission line relay mis-operation detection based on time-synchronized field data

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Esmaeilian, Ahad; Popovic, Tomo; Kezunovic, Mladen

    2015-08-01T23:59:59.000Z

    In this paper, a real-time tool to detect transmission line relay mis-operation is implemented. The tool uses time-synchronized measurements obtained from both ends of the line during disturbances. The proposed fault analysis tool comes into the picture only after the protective device has operated and tripped the line. The proposed methodology is able not only to detect, classify, and locate transmission line faults, but also to accurately confirm whether the line was tripped due to a mis-operation of protective relays. The analysis report includes either detailed description of the fault type and location or detection of relay mis-operation. As such,more »it can be a source of very useful information to support the system restoration. The focus of the paper is on the implementation requirements that allow practical application of the methodology, which is illustrated using the field data obtained the real power system. Testing and validation is done using the field data recorded by digital fault recorders and protective relays. The test data included several hundreds of event records corresponding to both relay mis-operations and actual faults. The discussion of results addresses various challenges encountered during the implementation and validation of the presented methodology.« less

  17. EA-1982: Parker-Davis Transmission System Routine Operation and Maintenance Project and Proposed Integrated Vegetation Management Plan

    Broader source: Energy.gov [DOE]

    Western Area Power Administration (Western) is preparing an EA to assess potential environmental impacts of the proposed continuation of operations and maintenance activities and implementation of a vegetation management program on Western’s Parker-Davis Transmission System. These actions would occur on existing transmission line and access road rights-of-way, and at substations and maintenance facilities associated with the transmission system.

  18. Independent transmission system operators and their role in maintaining reliability in a restructured electric power industry

    SciTech Connect (OSTI)

    NONE

    1998-01-01T23:59:59.000Z

    This report summarizes the current status of proposals to form Independent System Operators (ISOs) to operate high-voltage transmission systems in the United States and reviews their potential role in maintaining bulk power system reliability. As background information, the likely new industry structure, nature of deregulated markets, and institutional framework for bulk power system reliability are reviewed. The report identifies issues related to the formation of ISOs and their roles in markets and in reliability, and describes potential policy directions for encouraging the formation of effective ISOs and ensuring bulk system reliability. Two appendices are provided, which address: (1) system operation arrangements in other countries, and (2) summaries of regional U.S. ISO proposals.

  19. EMTP modeling of CIGRE benchmark based HVDC transmission system operating with weak AC systems

    SciTech Connect (OSTI)

    Sood, V.K. [Hydro-Quebec, Varennes, Quebec (Canada); Khatri, V.; Jin, H. [Concordia Univ., Montreal, Quebec (Canada). Dept. of Electrical and Computer Engineering

    1995-12-31T23:59:59.000Z

    An EMTP based study of a CIGRE benchmark based HVDC system operating with weak ac systems is carried out. The modeled system provides a starting point for (a) educators teaching HVDC transmission courses and (b) for utility planners to develop their own low-cost dedicated digital simulators for training purposes. In this paper, modeling details of the ac-dc system, dc converters and control are presented. To validate the control schemes presented, the HVDC system is tested under ac-dc fault conditions. Results obtained from an EMTP-based study under these fault conditions are also presented in this paper.

  20. The design, construction, and operation of long-distance high-voltage electricity transmission technologies.

    SciTech Connect (OSTI)

    Molburg, J. C.; Kavicky, J. A.; Picel, K. C.

    2008-03-03T23:59:59.000Z

    This report focuses on transmission lines, which operate at voltages of 115 kV and higher. Currently, the highest voltage lines comprising the North American power grid are at 765 kV. The grid is the network of transmission lines that interconnect most large power plants on the North American continent. One transmission line at this high voltage was built near Chicago as part of the interconnection for three large nuclear power plants southwest of the city. Lines at this voltage also serve markets in New York and New England, also very high demand regions. The large power transfers along the West Coast are generally at 230 or 500 kV. Just as there are practical limits to centralization of power production, there are practical limits to increasing line voltage. As voltage increases, the height of the supporting towers, the size of the insulators, the distance between conductors on a tower, and even the width of the right-of-way (ROW) required increase. These design features safely isolate the electric power, which has an increasing tendency to arc to ground as the voltage (or electrical potential) increases. In addition, very high voltages (345 kV and above) are subject to corona losses. These losses are a result of ionization of the atmosphere, and can amount to several megawatts of wasted power. Furthermore, they are a local nuisance to radio transmission and can produce a noticeable hum. Centralized power production has advantages of economies of scale and special resource availability (for instance, hydro resources), but centralized power requires long-distance transfers of power both to reach customers and to provide interconnections for reliability. Long distances are most economically served at high voltages, which require large-scale equipment and impose a substantial footprint on the corridors through which power passes. The most visible components of the transmission system are the conductors that provide paths for the power and the towers that keep these conductors at a safe distance from each other and from the ground and the natural and built environment. Common elements that are generally less visible (or at least more easily overlooked) include the maintained ROW along the path of the towers, access roads needed for maintenance, and staging areas used for initial construction that may be restored after construction is complete. Also visible but less common elements along the corridor may include switching stations or substations, where lines of similar or different voltages meet to transfer power.

  1. A long-pulse repetitive operation magnetically insulated transmission line oscillator

    SciTech Connect (OSTI)

    Fan, Yu-Wei; Zhong, Hui-Huang; Zhang, Jian-De; Shu, Ting; Liu, Jin Liang [College of Optoelectric Science and Engineering, National University of Defense Technology, Changsha 410073 (China)

    2014-05-15T23:59:59.000Z

    The improved magnetically insulated transmission line oscillator (MILO) is a gigawatt-class L-band high power microwave tube. It has allowed us to generate 3.1 GW pulse of 40 ns duration in the single-pulse operation and 500 MW pulse of 25 ns duration in the repetition rate operation. However, because of the severe impedance mismatch, the power conversion efficiency is only about 4% in the repetition rate operation. In order to eliminate the impedance mismatch and obtain repetitive long-pulse high-power microwave (HPM), a series of experiments are carried out and the recent progress is presented in this paper. In the single-pulse operation, when the diode voltage is 466 kV and current is 41.6 kA, the radiated microwave power is above 2.2 GW, the pulse duration is above 102 ns, the microwave frequency is about 1.74 GHz, and the power conversion efficiency is about 11.5%. In the repetition rate operation, under the condition of the diode voltage about 400 kV, beam current about 38 kA, the radiated microwave power is about 1.0 GW, the pulse duration is about 85 ns. Moreover, the radiated microwave power and the pulse duration decline little by little when the shot numbers increase gradually. The experimental results show that the impedance matching is a vital factor for HPM systems and one of the major technical challenges is to improve the cathode for the repetition rate operation MILO.

  2. Development of a New Coaxial Balloon Catheter System for Balloon-Occluded Retrograde Transvenous Obliteration (B-RTO)

    SciTech Connect (OSTI)

    Tanoue, Shuichi, E-mail: tanoue@med.oita-u.ac.jp; Kiyosue, Hiro; Matsumoto, Shunro [Oita University Faculty of Medicine, Department of Academic Radiology (Japan); Hori, Yuzo [Nagatomi Neurosurgical Hospital, Department of Radiology (Japan); Okahara, Mika [Oita University Faculty of Medicine, Department of Academic Radiology (Japan); Kashiwagi, Junji [Nagatomi Neurosurgical Hospital, Department of Radiology (Japan); Mori, Hiromu [Oita University Faculty of Medicine, Department of Academic Radiology (Japan)

    2006-12-15T23:59:59.000Z

    Purpose. To develop a new coaxial balloon catheter system and evaluate its clinical feasibility for balloon-occluded retrograde transvenous obliteration (B-RTO). Methods. A coaxial balloon catheter system was constructed with 9 Fr guiding balloon catheter and 5 Fr balloon catheter. A 5 Fr catheter has a high flexibility and can be coaxially inserted into the guiding catheter in advance. The catheter balloons are made of natural rubber and can be inflated to 2 cm (guiding) and 1 cm (5 Fr) maximum diameter. Between July 2003 and April 2005, 8 consecutive patients (6 men, 2 women; age range 33-72 years, mean age 55.5 years) underwent B-RTO using the balloon catheter system. Five percent ethanolamine oleate iopamidol (EOI) was used as sclerosing agent. The procedures, including maneuverability of the catheter, amount of injected sclerosing agent, necessity for coil embolization of collateral draining veins, and initial clinical results, were evaluated retrospectively. The occlusion rate was assessed by postcontrast CT within 2 weeks after B-RTO. Results. The balloon catheter could be advanced into the proximal potion of the gastrorenal shunt beyond the collateral draining vein in all cases. The amount of injected EOI ranged from 3 to 34 ml. Coil embolization of the collateral draining vein was required in 2 cases. Complete obliteration of gastric varices on initial follow-up CT was obtained in 7 cases. The remaining case required re-treatment that resulted in complete obstruction of the varices after the second B-RTO. No procedure-related complications were observed. Conclusion. B-RTO using the new coaxial balloon catheter is feasible. Gastric varices can be treated more simply by using this catheter system.

  3. Decision-Support Software for Grid Operators: Transmission Topology Control for Infrastructure Resilience to the Integration of Renewable Generation

    SciTech Connect (OSTI)

    None

    2012-03-16T23:59:59.000Z

    GENI Project: The CRA team is developing control technology to help grid operators more actively manage power flows and integrate renewables by optimally turning on and off entire power lines in coordination with traditional control of generation and load resources. The control technology being developed would provide grid operators with tools to help manage transmission congestion by identifying the facilities whose on/off status must change to lower generation costs, increase utilization of renewable resources and improve system reliability. The technology is based on fast optimization algorithms for the near to real-time change in the on/off status of transmission facilities and their software implementation.

  4. Final Report on Transmission Pricing in the Western Interconnection

    SciTech Connect (OSTI)

    Douglas C. Larson; Lawrence Nordell

    2003-06-25T23:59:59.000Z

    Under this project, the Committee on Regional Electric Power Cooperation (CREPC) of the Western Interstate Energy Board developed a ''western pricing and congestion management proposal'' in order to foster efficient wholesale power markets and efficient use and expansion of the transmission grid. Drafts of this paper provided useful information to states/provinces in the Western Interconnection as Western Regional Transmission Organization (RTO) transmission pricing proposals have continued to evolve. Throughout the project there has been a gradual, but incomplete agreement on pricing systems to be used by RTOs in the West.

  5. The Role of Demand Resources In Regional Transmission Expansion Planning and Reliable Operations

    SciTech Connect (OSTI)

    Kirby, Brendan J [ORNL

    2006-07-01T23:59:59.000Z

    Investigating the role of demand resources in regional transmission planning has provided mixed results. On one hand there are only a few projects where demand response has been used as an explicit alternative to transmission enhancement. On the other hand there is a fair amount of demand response in the form of energy efficiency, peak reduction, emergency load shedding, and (recently) demand providing ancillary services. All of this demand response reduces the need for transmission enhancements. Demand response capability is typically (but not always) factored into transmission planning as a reduction in the load which must be served. In that sense demand response is utilized as an alternative to transmission expansion. Much more demand response is used (involuntarily) as load shedding under extreme conditions to prevent cascading blackouts. The amount of additional transmission and generation that would be required to provide the current level of reliability if load shedding were not available is difficult to imagine and would be impractical to build. In a very real sense demand response solutions are equitably treated in every region - when proposed, demand response projects are evaluated against existing reliability and economic criteria. The regional councils, RTOs, and ISOs identify needs. Others propose transmission, generation, or responsive load based solutions. Few demand response projects get included in transmission enhancement plans because few are proposed. But this is only part of the story. Several factors are responsible for the current very low use of demand response as a transmission enhancement alternative. First, while the generation, transmission, and load business sectors each deal with essentially the same amount of electric power, generation and transmission companies are explicitly in the electric power business but electricity is not the primary business focus of most loads. This changes the institutional focus of each sector. Second, market and reliability rules have, understandably, been written around the capabilities and limitations of generators, the historic reliability resources. Responsive load limitations and capabilities are often not accommodated in markets or reliability criteria. Third, because of the institutional structure, demand response alternatives are treated as temporary solutions that can delay but not replace transmission enhancement. Financing has to be based on a three to five year project life as opposed to the twenty to fifty year life of transmission facilities. More can be done to integrate demand response options into transmission expansion planning. Given the societal benefits it may be appropriate for independent transmission planning organizations to take a more proactive role in drawing demand response alternatives into the resource mix. Existing demand response programs provide a technical basis to build from. Regulatory and market obstacles will have to be overcome if demand response alternatives are to be routinely considered in transmission expansion planning.

  6. Renewable Resource Integration Project - Scoping Study of Strategic Transmission, Operations, and Reliability Issues

    E-Print Network [OSTI]

    Budhraja, Vikram

    2008-01-01T23:59:59.000Z

    for transfer of renewable energy from the L.A.  Basin  Area April 2008.   Renewable Energy Transmission Initiative.  Commission  Competitive Renewable Energy Zones  California 

  7. agent-based computational economics: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Commis- sion proposed) or Regional Transmission Organizations (RTOs) using locational marginal pricing to price energyRTO operated energy regions now include over 50% of the...

  8. Electricity Monthly Update

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    month. Prices and demand are shown for six Regional Transmission Operator (RTO) markets: ISO New England (ISO-NE), New York ISO (NYISO), PJM Interconnection (PJM), Midwest ISO...

  9. Interdependencies of Electricity Markets with Gas Markets A Case Study of Transmission System Operators

    E-Print Network [OSTI]

    Dixon, Juan

    1 Interdependencies of Electricity Markets with Gas Markets ­ A Case Study of Transmission System and regulatory intervention. Three generic Case Studies of countries belonging to the Americas are discussed Case Studies (Latin America; Canada and the USA). 2. 1. Latin America The primary challenge for Latin

  10. Optimal Transmission Switching in Electric Networks for Improved Economic Operations1

    E-Print Network [OSTI]

    Ferris, Michael C.

    . Abstract Growing demand for electric power seems to necessitate new transmission lines, but obstacles demand with existing infrastructure. In this paper we present the formulation for an Optimal Power Flow have been considered static infrastructure, a "superhighway" for power delivery. However, switching

  11. Analysis of operations and cyber security policies for a system of cooperating Flexible Alternating Current Transmission System (FACTS) devices.

    SciTech Connect (OSTI)

    Phillips, Laurence R.; Tejani, Bankim; Margulies, Jonathan; Hills, Jason L.; Richardson, Bryan T.; Baca, Micheal J.; Weiland, Laura

    2005-12-01T23:59:59.000Z

    Flexible Alternating Current Transmission Systems (FACTS) devices are installed on electric power transmission lines to stabilize and regulate power flow. Power lines protected by FACTS devices can increase power flow and better respond to contingencies. The University of Missouri Rolla (UMR) is currently working on a multi-year project to examine the potential use of multiple FACTS devices distributed over a large power system region in a cooperative arrangement in which the FACTS devices work together to optimize and stabilize the regional power system. The report describes operational and security challenges that need to be addressed to employ FACTS devices in this way and recommends references, processes, technologies, and policies to address these challenges.

  12. Renewable Electricity Futures Study. Volume 4: Bulk Electric Power Systems: Operations and Transmission Planning

    SciTech Connect (OSTI)

    Milligan, M.; Ela, E.; Hein, J.; Schneider, T.; Brinkman, G.; Denholm, P.

    2012-06-01T23:59:59.000Z

    The Renewable Electricity Futures (RE Futures) Study investigated the challenges and impacts of achieving very high renewable electricity generation levels in the contiguous United States by 2050. The analysis focused on the sufficiency of the geographically diverse U.S. renewable resources to meet electricity demand over future decades, the hourly operational characteristics of the U.S. grid with high levels of variable wind and solar generation, and the potential implications of deploying high levels of renewables in the future. RE Futures focused on technical aspects of high penetration of renewable electricity; it did not focus on how to achieve such a future through policy or other measures. Given the inherent uncertainties involved with analyzing alternative long-term energy futures as well as the multiple pathways that might be taken to achieve higher levels of renewable electricity supply, RE Futures explored a range of scenarios to investigate and compare the impacts of renewable electricity penetration levels (30%-90%), future technology performance improvements, potential constraints to renewable electricity development, and future electricity demand growth assumptions. RE Futures was led by the National Renewable Energy Laboratory (NREL) and the Massachusetts Institute of Technology (MIT).

  13. Transmission and Storage Operations

    Broader source: Energy.gov (indexed) [DOE]

    Reliability Engineer November 12, 2014 Agenda * DTE Gas Snapshot * NOx & CO - Combustion stability * Methane - Packing - Blowdowns * Capture vs Flare 2 SNAPSHOT * DTE Gas -...

  14. Transmission and Storage Operations

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33Frequently AskedEnergyIssuesEnergy SolarRadioactiveITransactional7AMelissa

  15. A new Scanning Transmission X-ray Microscope at the ALS for operation up to 2500eV

    E-Print Network [OSTI]

    Kilcoyne, David

    2010-01-01T23:59:59.000Z

    and y interferometers (z is optional) sample scanning stackzone plate scanning stack FIGURE 6 Layout of functionalMagnet Beam Line for Scanning Transmission X-ray Microscopy

  16. Net Interchange Schedule Forecasting of Electric Power Exchange for RTO/ISOs

    SciTech Connect (OSTI)

    Ferryman, Thomas A.; Haglin, David J.; Vlachopoulou, Maria; Yin, Jian; Shen, Chao; Tuffner, Francis K.; Lin, Guang; Zhou, Ning; Tong, Jianzhong

    2012-07-26T23:59:59.000Z

    Neighboring independent system operators (ISOs) exchange electric power to enable efficient and reliable operation of the grid. Net interchange (NI) schedule is the sum of the transactions (in MW) between an ISO and its neighbors. Effective forecasting of the amount of actual NI can improve grid operation efficiency. This paper presents results of a preliminary investigation into various methods of prediction that may result in improved prediction accuracy. The methods studied are linear regression, forward regression, stepwise regression, and support vector machine (SVM) regression. The work to date is not yet conclusive. The hope is to explore the effectiveness of other prediction methods and apply all methods to at least one new data set. This should enable more confidence in the conclusions.

  17. Abstract--In the UK and also worldwide it is certain that future transmission systems will operate with significantly larger

    E-Print Network [OSTI]

    Taylor, Gary

    practice with regard to important areas of network management such as frequency response, reactive power at the transmission level are highly centralised and are therefore not necessarily best suited to support large is that in order to ensure continuity of supply it is necessary to predict demand levels and distribution

  18. Transmission Issues Policy Steering Committee

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Business Practices CommitteesTeams Joint Operating Committee Transmission Issues Policy Steering Committee Customer Training Interconnection Notices Rates Standards of...

  19. 13- 2 RTO-EN-AVT-131Micro Gas Turbine and Fuel Cell –

    E-Print Network [OSTI]

    Dieter Bohn

    This paper reports an assessment of coupling micro gas turbine and high temperature fuel cell (SOFC) as a possibility to realize power plant with an efficiency of 75%. The application of such a technology will be in the decentralized feed-in of housing estates and buildings with electricity, heat and cooling energy. Nowadays the first implemented prototypes reach efficiencies among 57- 58 % /1/. The paper shows the necessity of further developments to be able to reach an efficiency of 75%. The developments include improvements in all components of the system like compressor, turbine, bearing and the increasing of the operating temperature.

  20. Automated manual transmission controller

    DOE Patents [OSTI]

    Lawrie, Robert E. (Whitmore Lake, MI); Reed, Jr., Richard G. (Royal Oak, MI); Bernier, David R. (Rochester Hills, MI)

    1999-12-28T23:59:59.000Z

    A powertrain system for a hybrid vehicle. The hybrid vehicle includes a heat engine, such as a diesel engine, and an electric machine, which operates as both an electric motor and an alternator, to power the vehicle. The hybrid vehicle also includes a manual-style transmission configured to operate as an automatic transmission from the perspective of the driver. The engine and the electric machine drive an input shaft which in turn drives an output shaft of the transmission. In addition to driving the transmission, the electric machine regulates the speed of the input shaft in order to synchronize the input shaft during either an upshift or downshift of the transmission by either decreasing or increasing the speed of the input shaft. When decreasing the speed of the input shaft, the electric motor functions as an alternator to produce electrical energy which may be stored by a storage device. Operation of the transmission is controlled by a transmission controller which receives input signals and generates output signals to control shift and clutch motors to effect smooth launch, upshift shifts, and downshifts of the transmission, so that the transmission functions substantially as an automatic transmission from the perspective of the driver, while internally substantially functioning as a manual transmission.

  1. Implications of Regional Transmission Organization Design for Renewable Energy Technologies

    SciTech Connect (OSTI)

    Porter, K.

    2002-05-01T23:59:59.000Z

    This report summarizes the development of Regional Transmission Organizations (RTOs) and assesses the potential implications of market rules for renewable energy technologies. The report focuses on scheduling provisions, as these have proved problematic in some cases for intermittent renewable energy technologies. Market rules of four RTOs-the Pennsylvania-Maryland-New Jersey ISO, the ERCOT ISO, the Midwest ISO and the New York ISO (NYISO)-were examined to determine the impact on intermittent renewable energy projects such as wind energy generators. Also, a more general look was taken at how biomass power may fare in RTOs, specifically whether these technologies can participate in ancillary service markets. Lastly, an assessment was made regarding the implications for renewable energy technologies of a Northeast-wide RTO that would combine the three existing Northeast ISOs (the aforementioned PJM and NYISOs, as well as ISO New England).

  2. A Review of Recent RTO Benefit-Cost Studies: Toward More Comprehensive Assessments of FERC Electricity Restructuring Policies

    E-Print Network [OSTI]

    Eto, Joseph H.; Lesieutre, Bernard C.

    2005-01-01T23:59:59.000Z

    Sponsored by Midwest Independent System Operator (MISO) CRA.price million Midwest Independent System Operator megawatt

  3. Areal-averaged and Spectrally-resolved Surface Albedo from Ground-based Transmission Data Alone: Toward an Operational Retrieval

    SciTech Connect (OSTI)

    Kassianov, Evgueni I.; Barnard, James C.; Flynn, Connor J.; Riihimaki, Laura D.; Michalsky, Joseph; Hodges, G. B.

    2014-08-22T23:59:59.000Z

    We present here a simple retrieval of the areal-averaged and spectrally resolved surface albedo using only ground-based measurements of atmospheric transmission under fully overcast conditions. Our retrieval is based on a one-line equation and widely accepted assumptions regarding the weak spectral dependence of cloud optical properties in the visible and near-infrared spectral range. The feasibility of our approach for the routine determinations of albedo is demonstrated for different landscapes with various degrees of heterogeneity using three sets of measurements:(1) spectrally resolved atmospheric transmission from Multi-Filter Rotating Shadowband Radiometer (MFRSR) at wavelength 415, 500, 615, 673, and 870 nm, (2) tower-based measurements of local surface albedo at the same wavelengths, and (3) areal-averaged surface albedo at four wavelengths (470, 560, 670 and 860 nm) from collocated and coincident Moderate Resolution Imaging Spectroradiometer (MODIS) observations. These integrated datasets cover both long (2008-2013) and short (April-May, 2010) periods at the ARM Southern Great Plains (SGP) site and the NOAA Table Mountain site, respectively. The calculated root mean square error (RMSE), which is defined here as the root mean squared difference between the MODIS-derived surface albedo and the retrieved area-averaged albedo, is quite small (RMSE?0.01) and comparable with that obtained previously by other investigators for the shortwave broadband albedo. Good agreement between the tower-based daily averages of surface albedo for the completely overcast and non-overcast conditions is also demonstrated. This agreement suggests that our retrieval originally developed for the overcast conditions likely will work for non-overcast conditions as well.

  4. Operations, Maintenance, and Replacement 10-year plan, 1990-1999 : 1989 Utility OM&R Comparison : A Comparison of BPA (Bonneville Power Administration) and Selected Utility Transmission, Operations and Maintenance Costs.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1990-09-01T23:59:59.000Z

    For the past several years, competing resource demands within BPA have forced the Agency to stretch Operations, Maintenance and Replacement (OM R) resources. There is a large accumulation of tasks that were not accomplished when scheduled. Maintenance and replacements and outages, due to material and equipment failure, appear to be increasing. BPA has made a strategic choice to increase its emphasis on OM R programs by implementing a multi-year, levelized OM R plan which is keyed to high system reliability. This strategy will require a long-term commitment of a moderate increase in staff and dollars allocated to these programs. In an attempt to assess the direction BPA has taken in its OM R programs, a utility comparison team was assembled in early January 1989. The team included representatives from BPA's Management Analysis, Internal Audit and Financial Management organizations, and operation and maintenance program areas. BPA selected four utilities from a field of more than 250 electric utilities in the US and Canada. The selection criteria generally pertained to size, with key factors including transformation capacity, load, gross revenue, and interstate transmission and/or marketing agreements, and their OM R programs. Information was gathered during meetings with managers and technical experts representing the four utilities. Subsequent exchanges of information also took place to verify findings. The comparison focused on: Transmission operations and maintenance program direction and emphasis; Organization, management and implementation techniques; Reliability; and Program costs. 2 figs., 21 tabs.

  5. Evaluating the potential impact of transmission constraints on the operation of a competitive electricity market in Illinois.

    SciTech Connect (OSTI)

    Cirillo, R.; Thimmapuram, P.; Veselka, T.; Koritarov, V.; Conzelmann, G.; Macal, C.; Boyd, G.; North, M.; Overbye, T.; Cheng, X.; Decision and Information Sciences; Univ. of Illinois

    2006-04-30T23:59:59.000Z

    Despite the current adequacy of the generation and transmission system in Illinois, there is concern that the uncertainties of electricity restructuring warrant a more detailed analysis to determine if there might be pitfalls that have not been identified under current conditions. The problems experienced elsewhere in the country emphasize the need for an evaluation of how Illinois might fare under a restructured electricity market. The Illinois Commerce Commission (ICC) commissioned this study to be undertaken as a joint effort by the University of Illinois at Urbana-Champaign and Argonne National Laboratory to evaluate the Illinois situation in the 2007 period when restructuring is scheduled to be fully implemented in the State. The purpose of this study is to make an initial determination if the transmission system in Illinois and the surrounding region would be able to support a competitive electricity market, would allow for effective competition to keep prices in check, and would allow for new market participants to effectively compete for market share. The study seeks to identify conditions that could reasonably be expected to occur that would enable a company to exercise market power in one or more portions of the State and thereby create undue pressure on the prices charged to customers and/or inhibit new market participants from entering the market. The term 'market power' has many different definitions, and there is no universal agreement on how to measure it. For the purposes of this study, the term is defined as the ability to raise prices and increase profitability by unilateral action. A more complete definition is provided later. With this definition, the central question of this analysis becomes: 'Can a company, acting on its own, raise electricity prices and increase its profits?' It should be noted that the intent of the study is not to predict whether or not such market power would be exercised by any company. Rather, it is designed to determine if a set of reasonably expected conditions could allow any company to do so. It should also be emphasized that this study is not intended to be a comprehensive evaluation of the electric power system in the State. Rather, it is intended to identify some issues that may impact the effective functioning of a competitive market.

  6. Electric Transmission Lines (Iowa)

    Broader source: Energy.gov [DOE]

    Electric transmission lines capable of operating at 69 kV or greater cannot be constructed along, across, or over any public highways or grounds outside of cities without a franchise from the...

  7. Automated manual transmission clutch controller

    DOE Patents [OSTI]

    Lawrie, Robert E. (9375 Kearney Rd., Whitmore Lake, MI 48189); Reed, Jr., Richard G. (3003 Bembridge, Royal Oak, MI 48073); Rausen, David J. (519 S. Gaylord St., Denver, CO 80209)

    1999-11-30T23:59:59.000Z

    A powertrain system for a hybrid vehicle. The hybrid vehicle includes a heat engine, such as a diesel engine, and an electric machine, which operates as both an electric motor and an alternator, to power the vehicle. The hybrid vehicle also includes a manual-style transmission configured to operate as an automatic transmission from the perspective of the driver. The engine and the electric machine drive an input shaft which in turn drives an output shaft of the transmission. In addition to driving the transmission, the electric machine regulates the speed of the input shaft in order to synchronize the input shaft during either an upshift or downshift of the transmission by either decreasing or increasing the speed of the input shaft. When decreasing the speed of the input shaft, the electric motor functions as an alternator to produce electrical energy which may be stored by a storage device. Operation of the transmission is controlled by a transmission controller which receives input signals and generates output signals to control shift and clutch motors to effect smooth launch, upshift shifts, and downshifts of the transmission, so that the transmission functions substantially as an automatic transmission from the perspective of the driver, while internally substantially functioning as a manual transmission.

  8. Transmission Services

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Return to Daylight Saving Time Posted: 2232015 Effective Date: 382015 This document provides the procedure for reserving and scheduling transmission that spans the time change...

  9. MASe UCRL-15037 CONTINUOUSLY VARIABLE TRANSMISSIONS: THEORY AND...

    Office of Scientific and Technical Information (OSTI)

    transmission when operating in the power recirculation mode 20 Simple manual system to control the speed ratio of a variable V-belt continuously variable transmission 21 Schematic...

  10. Transmission Services J7000

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Transmission Business Unit - J7300 CRSP - DSW - RMR Open Access Transmission Tariff Management Transmission Service Requests Interconnection Requests OASIS...

  11. Hydrogen Delivery Technologies and Pipeline Transmission of Hydrogen

    E-Print Network [OSTI]

    Hydrogen Delivery Technologies and Systems Pipeline Transmission of Hydrogen Strategic Initiatives, and Infrastructure Technologies Program #12;Pipeline Transmission of Hydrogen --- 2 Copyright: Design & Operation development) #12;Pipeline Transmission of Hydrogen --- 3 Copyright: Future H2 Infrastructure Wind Powered

  12. EIS-0231: Navajo Transmission Project

    Broader source: Energy.gov [DOE]

    This EIS evaluates the environmental impacts of a proposal to by Dine Power Authority, a Navajo Nation enterprise, to construct, operate, and maintain a 500 kilovolt (kV) transmission line planned...

  13. Draft environmental impact statement for construction and operation of the proposed Bangor Hydro-Electric Company`s second 345-kV transmission tie line to New Brunswick

    SciTech Connect (OSTI)

    NONE

    1993-10-01T23:59:59.000Z

    This Draft Environmental Impact Statement (DEIS) was prepared by the US Department of Energy (US DOE). The proposed action is the issuance of Presidential Permit PP-89 by DOE to Bangor Hydro-Electric Company to construct and operate a new international transmission line interconnection to New Brunswick, Canada that would consist of an 83.8 mile (US portion), 345-kilovolt (kV) alternating current transmission line from the US-Canadian border at Baileyville, Maine to an existing substation at Orrington, Maine. The principal environmental impacts of the construction and operation of the transmission line would be incremental in nature and would include the conversion of forested uplands (mostly commercial timberlands) and wetlands to right-of-way (small trees, shrubs, and herbaceous vegetation). The proposed line would also result in localized minor to moderate visual impacts and would contribute a minor incremental increase in the exposure of some individuals to electromagnetic fields. This DEIS documents the purpose and need for the proposed action, describes the proposed action and alternatives considered and provides a comparison of the proposed and alternatives routes, and provides detailed information on analyses of the environmental consequences of the proposed action and alternatives, as well as mitigative measures to minimize impacts.

  14. An Annotated Bibliography of High-Voltage Direct-Current Transmission and Flexible AC Transmission (FACTS) Devices, 1991-1993.

    SciTech Connect (OSTI)

    Litzenberger, Wayne; Lava, Val

    1994-08-01T23:59:59.000Z

    References are contained for HVDC systems, converter stations and components, overhead transmission lines, cable transmission, system design and operations, simulation of high voltage direct current systems, high-voltage direct current installations, and flexible AC transmission system (FACTS).

  15. Transmission Line Security Monitor: Final Report

    SciTech Connect (OSTI)

    John Svoboda

    2011-04-01T23:59:59.000Z

    The Electric Power Transmission Line Security Monitor System Operational Test is a project funded by the Technical Support Working Group (TSWG). TSWG operates under the Combating Terrorism Technical Support Office that functions under the Department of Defense. The Transmission Line Security Monitor System is based on technology developed by Idaho National Laboratory. The technology provides a means for real-time monitoring of physical threats and/or damage to electrical transmission line towers and conductors as well as providing operational parameters to transmission line operators to optimize transmission line operation. The end use is for monitoring long stretches of transmission lines that deliver electrical power from remote generating stations to cities and industry. These transmission lines are generally located in remote transmission line corridors where security infrastructure may not exist. Security and operational sensors in the sensor platform on the conductors take power from the transmission line and relay security and operational information to operations personnel hundreds of miles away without relying on existing infrastructure. Initiated on May 25, 2007, this project resulted in pre-production units tested in realistic operational environments during 2010. A technology licensee, Lindsey Manufacturing of Azusa California, is assisting in design, testing, and ultimately production. The platform was originally designed for a security monitoring mission, but it has been enhanced to include important operational features desired by electrical utilities.

  16. Transmission and Generation Investment in Electricity Markets

    E-Print Network [OSTI]

    Grimm Veronika

    2015-03-04T23:59:59.000Z

    Mar 4, 2015 ... The model incorporates investment decisions of the transmission operator and private firms in expectation of an energy-only market and ...

  17. Transmission INTRODUCTION

    E-Print Network [OSTI]

    , to a significant degree, on a well-functioning wholesale power market. The transmission system is integral the consequences of a poorly designed wholesale power market, and the Council does not want to see those Regulatory Commission began taking actions to further facilitate competition in wholesale power supply. Today

  18. Cogeneration Operational Issues

    E-Print Network [OSTI]

    Williams, M.

    operations. Other operational issues also include utility transmission planning, generation planning and fuel mix decisions. All of these operational problems have an impact on the ratepayer in regard to quality of electric service and future rates. Both...

  19. Transmission Investment: A Primer

    SciTech Connect (OSTI)

    McGarvey, Joe

    2006-10-15T23:59:59.000Z

    This primer highlights recent trends in transmission investment, summarizes the division of jurisdictional authority over transmission, and presents four alternative models for transmission ownership. (author)

  20. Transmission Workshop

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOn April 23,EnergyChicopeeTechnologyfact sheetTransferring the Wayne,TRANSMISSION WORKSHOP

  1. AC and DC power transmission

    SciTech Connect (OSTI)

    Not Available

    1985-01-01T23:59:59.000Z

    The technical and economic assessment of AC and DC transmission systems; long distance transmission, cable transmission, system inter-connection, voltage support, reactive compensation, stabilisation of systems; parallel operation of DC links with AC systems; comparison between alternatives for particular schemes. Design and application equipment: design, testing and application of equipment for HVDC, series and shunt static compensated AC schemes, including associated controls. Installations: overall design of stations and conductor arrangements for HVDC, series and shunt static AC schemes including insulation co-ordination. System analysis and modelling.

  2. Automated manual transmission mode selection controller

    DOE Patents [OSTI]

    Lawrie, Robert E. (Whitmore Lake, MI)

    1999-11-09T23:59:59.000Z

    A powertrain system for a hybrid vehicle. The hybrid vehicle includes a heat engine, such as a diesel engine, and an electric machine, which operates as both an electric motor and an alternator, to power the vehicle. The hybrid vehicle also includes a manual-style transmission configured to operate as an automatic transmission from the perspective of the driver. The engine and the electric machine drive an input shaft which in turn drives an output shaft of the transmission. In addition to driving the transmission, the electric machine regulates the speed of the input shaft in order to synchronize the input shaft during either an upshift or downshift of the transmission by either decreasing or increasing the speed of the input shaft. When decreasing the speed of the input shaft, the electric motor functions as an alternator to produce electrical energy which may be stored by a storage device. Operation of the transmission is controlled by a transmission controller which receives input signals and generates output signals to control shift and clutch motors to effect smooth launch, upshift shifts, and downshifts of the transmission, so that the transmission functions substantially as an automatic transmission from the perspective of the driver, while internally substantially functioning as a manual transmission.

  3. Automated manual transmission shift sequence controller

    DOE Patents [OSTI]

    Lawrie, Robert E. (Whitmore Lake, MI); Reed, Richard G. (Royal Oak, MI); Rausen, David J. (Denver, CO)

    2000-02-01T23:59:59.000Z

    A powertrain system for a hybrid vehicle. The hybrid vehicle includes a heat engine, such as a diesel engine, and an electric machine, which operates as both, an electric motor and an alternator, to power the vehicle. The hybrid vehicle also includes a manual-style transmission configured to operate as an automatic transmission from the perspective of the driver. The engine and the electric machine drive an input shaft which in turn drives an output shaft of the transmission. In addition to driving the transmission, the electric machine regulates the speed of the input shaft in order to synchronize the input shaft during either an upshift or downshift of the transmission by either decreasing or increasing the speed of the input shaft. When decreasing the speed of the input shaft, the electric motor functions as an alternator to produce electrical energy which may be stored by a storage device. Operation of the transmission is controlled by a transmission controller which receives input signals and generates output signals to control shift and clutch motors to effect smooth launch, upshift shifts, and downshifts of the transmission, so that the transmission functions substantially as an automatic transmission from the perspective of the driver, while internally substantially functioning as a manual transmission.

  4. How Compatible is Perfect Competition with Transmission Loss Allocation Methods?

    E-Print Network [OSTI]

    Boyer, Edmond

    the problem of transmission loss allocation in a power system where the generators, the demands and the system. INTRODUCTION IN power systems where generation and transmission are unbundled, the transmission operationalHow Compatible is Perfect Competition with Transmission Loss Allocation Methods? Jing Dai, Yannick

  5. Power superconducting power transmission cable

    DOE Patents [OSTI]

    Ashworth, Stephen P. (Cambridge, GB)

    2003-01-01T23:59:59.000Z

    The present invention is for a compact superconducting power transmission cable operating at distribution level voltages. The superconducting cable is a conductor with a number of tapes assembled into a subconductor. These conductors are then mounted co-planarly in an elongated dielectric to produce a 3-phase cable. The arrangement increases the magnetic field parallel to the tapes thereby reducing ac losses.

  6. Manual transmission shift linkage

    SciTech Connect (OSTI)

    Sewell, J.S.

    1991-10-01T23:59:59.000Z

    This patent describes a sliding gear manual transmission (10) for an automotive vehicle including a transmission housing (11), an input shaft (12) journalled in the housing, an output shaft (13) axially aligned with the input shaft and journalled in the housing, a countershaft (15) journalled in the housing and carrying a cluster gear (17) thereon, the input shaft (12) terminating in an input gear (14), a plurality of gears (26,27,28,29,31,31) on the output shaft (13) in meshing engagement with the cluster gear (17), and a plurality of synchronizing clutches (36,38,41,42) on the output shaft and countershaft for engagement of gear ratios of the meshing gears, and an axially movable and rotatable shift rail (81) located in the housing and operatively connected to a shift lever (82) actuated by the vehicle operator, the improvement comprising an auxiliary shift rail (98) located in the housing (11) generally paralleling the first mentioned shift rail (81) to provide for actuation of fifth, sixth and reverse gears the auxiliary shift rail (98) having a 5-6 shift arm (104) journalled thereon for axial movement relative thereto, and a reverse shift arm (99) rotatably mounted thereon for axial movement therewith.

  7. Survey of Transmission Cost Allocation Methodologies for Regional Transmission Organizations

    SciTech Connect (OSTI)

    Fink, S.; Porter, K.; Mudd, C.; Rogers, J.

    2011-02-01T23:59:59.000Z

    The report presents transmission cost allocation methodologies for reliability transmission projects, generation interconnection, and economic transmission projects for all Regional Transmission Organizations.

  8. Merchant transmission investment

    E-Print Network [OSTI]

    Joskow, Paul L.

    2003-01-01T23:59:59.000Z

    We examine the performance attributes of a merchant transmission investment framework that relies on "market driven" transmission investment to provide the infrastructure to support competitive wholesale markets for ...

  9. Electric Power Generation and Transmission (Iowa)

    Broader source: Energy.gov [DOE]

    Electric power generating facilities with a combined capacity greater than 25 MW, as well as associated transmission lines, may not be constructed or begin operation prior to the issuance of a...

  10. Final Report Navajo Transmission Project (NTP)

    SciTech Connect (OSTI)

    Bennie Hoisington; Steven Begay

    2006-09-14T23:59:59.000Z

    The Diné Power Authority is developing the Navajo Transmission Project (NTP) to relieve the constraints on the transmission of electricity west of the Four Corners area and to improve the operation flexibility and reliability of the extra-high-voltage transmission system in the region. The NTP creates the wholesale transmission capacity for more economical power transfers, sales, and purchases in the region. It will facilitate the development of Navajo energy resources, improve economic conditions on the Navajo Nation as well as allow DPA to participate in the western electrical utility industry.

  11. 1 Introduction Danish transmission system operator

    E-Print Network [OSTI]

    Bak, Claus Leth

    of graph 6,5 s) in a modulated manner. Three frequencies are recognizable; change from 50 Hz to a lower

  12. Eastern Wind Integration and Transmission Study: Executive Summary...

    Energy Savers [EERE]

    Study: Executive Summary and Project Overview Eastern Wind Integration and Transmission Study: Executive Summary and Project Overview This study evaluates the future operational...

  13. Hydrogen Delivery Technologies and Systems- Pipeline Transmission of Hydrogen

    Broader source: Energy.gov [DOE]

    Hydrogen Delivery Technologies and Systems - Pipeline Transmission of Hydrogen. Design and operations standards and materials for hydrogen and natural gas pipelines.

  14. Sixth Northwest Conservation and Electric Power Plan Chapter 7: Transmission

    E-Print Network [OSTI]

    Sixth Northwest Conservation and Electric Power Plan Chapter 7: Transmission Summary of Key, both in operating the existing system and in planning for new major transmission lines. Since then transmission system is an integral part of the regional power system. It functions roughly like the highway

  15. Transmission power control game with SINR as objective function

    E-Print Network [OSTI]

    Avrachenkov, Konstantin

    Transmission power control game with SINR as objective function E. Altman1 , K. Avrachenkov1 State University, Russia agarnaev@rambler.ru Abstract. We consider the transmission power control networks, Power Control, Nash Equilibrium, Co- operation 1 Introduction We consider the transmission power

  16. Midwest Transmission Workshop II Summary

    SciTech Connect (OSTI)

    Kevin Bryan

    2002-12-05T23:59:59.000Z

    OAK-B135 After introductions of all participants, Abby Arnold, RESOLVE, reviewed the purpose of the meeting and the agenda. The purpose of the workshop was to share the results of the Midwest Independent System Operator (MISO) scenario development for wind and other fuel sources and the corresponding implications for transmission throughout the MISO control area. The workshop agenda is included in Attachment A.

  17. Transmission Commercial Project Integration

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Improvement (CBPI) Customer Forum Energy Imbalance Market Generator Interconnection Reform Implementation Network Integration Transmission Service (NT Service) Network Open...

  18. Electricity Transmission Congestion Costs: A Review of Recent Reports

    E-Print Network [OSTI]

    operator ISO-NE Independent System Operator - New England LMP Locational marginal price MW Megawatt MWh price FERC Federal Energy Regulatory Commission FTR Fixed transmission right ISO Independent system

  19. Methods, apparatus, and systems for monitoring transmission systems

    DOE Patents [OSTI]

    Polk, Robert E. (Idaho Falls, ID) [Idaho Falls, ID; Svoboda, John M. (Idaho Falls, ID) [Idaho Falls, ID; West, Phillip B. (Idaho Falls, ID) [Idaho Falls, ID; Heath, Gail L. (Iona, ID) [Iona, ID; Scott, Clark L. (Idaho Falls, ID) [Idaho Falls, ID

    2010-08-31T23:59:59.000Z

    A sensing platform for monitoring a transmission system, and method therefor, may include a sensor that senses one or more conditions relating to a condition of the transmission system and/or the condition of an environment around the transmission system. A control system operatively associated with the sensor produces output data based on an output signal produced by the sensor. A transmitter operatively associated with the control system transmits the output data from the control system.

  20. Method of calibrating clutches in transmissions

    SciTech Connect (OSTI)

    Bulgrien, G.H.

    1991-02-05T23:59:59.000Z

    This paper describes a microprocessor controlling a shuttle shift transmission programmed to effect a calibration of the final drive clutches in the transmission so that the microprocessor can efficiently effect engagement of each respective clutch by applying the proper hydraulic pressure to cause proper engagement thereof. This method of calibrating the final drive clutches in the transmission includes braking the output shaft of the transmission so that any engagement of the selected final drive clutch being calibrated will cause a load to be applied to the engine. The hydraulic pressure is then incrementally increased until the engine RPM's decrease because of the load being placed on the engine. The value of this engagement hydraulic pressure is stored in the microprocessor for use when effecting engagement of the selected clutch during operation of the transmission. Service indicators are programmed into the microprocessor should the selected clutch not be capable of being calibrated.

  1. Online Transmission Line Loadability Assessment Using Synchrophasor Measurements

    E-Print Network [OSTI]

    Liberzon, Daniel

    a stable operation. Transmission line loading limits are also essential to deter- mine locational marginal loading margins provide a useful metric to operate the power sys- tem to satisfy demands while ensuring prices in power markets. Therefore, the assessment of transmission line loadability under various

  2. Concurrent Wind Cooling in Power Transmission Lines

    SciTech Connect (OSTI)

    Jake P Gentle

    2012-08-01T23:59:59.000Z

    Idaho National Laboratory and the Idaho Power Company, with collaboration from Idaho State University, have been working on a project to monitor wind and other environmental data parameters along certain electrical transmission corridors. The combination of both real-time historical weather and environmental data is being used to model, validate, and recommend possibilities for dynamic operations of the transmission lines for power and energy carrying capacity. The planned results can also be used to influence decisions about proposed design criteria for or upgrades to certain sections of the transmission lines.

  3. Series Transmission Line Transformer

    DOE Patents [OSTI]

    Buckles, Robert A. (Livermore, CA); Booth, Rex (Livermore, CA); Yen, Boris T. (El Cerrito, CA)

    2004-06-29T23:59:59.000Z

    A series transmission line transformer is set forth which includes two or more of impedance matched sets of at least two transmissions lines such as shielded cables, connected in parallel at one end ans series at the other in a cascading fashion. The cables are wound about a magnetic core. The series transmission line transformer (STLT) which can provide for higher impedance ratios and bandwidths, which is scalable, and which is of simpler design and construction.

  4. Midwest Independent System Operator (Multiple States)

    Broader source: Energy.gov [DOE]

    Midwest Independent Transmission System Operator (MISO) is a Regional Transmission Organization, which administers wholesale electricity markets in all or parts of 11 U.S. states and the Canadian...

  5. 2012 Transmission Rate Schedules

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    2014 Transmission, Ancillary, and Control Area Service Rate Schedules and General Rate Schedule Provisions (FY 2014-2015) October 2013 United States Department of Energy...

  6. Electric Transmission Lines (Nebraska)

    Broader source: Energy.gov [DOE]

    The Public Service Commission has jurisdiction over all electricity transmission lines crossing over or under railroad tracks at public highway crossings. This section contains general regulations...

  7. Patterns of transmission investment

    E-Print Network [OSTI]

    Joskow, Paul L.

    2005-01-01T23:59:59.000Z

    This paper examines a number of issues associated with alternative analytical approaches for evaluating investments in electricity transmission infrastructure and alternative institutional arrangements to govern network ...

  8. Collaborative Transmission Technology Roadmap

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    techniques, and tools to analyze data from power quality recorders Size-up demand response opportunities Transmission level monitoring with PMUs is not sufficient and needs to...

  9. EC Transmission Line Risk Identification and Analysis

    SciTech Connect (OSTI)

    Bigelow, Tim S [ORNL

    2012-04-01T23:59:59.000Z

    The purpose of this document is to assist in evaluating and planning for the cost, schedule, and technical project risks associated with the delivery and operation of the EC (Electron cyclotron) transmission line system. In general, the major risks that are anticipated to be encountered during the project delivery phase associated with the implementation of the Procurement Arrangement for the EC transmission line system are associated with: (1) Undefined or changing requirements (e.g., functional or regulatory requirements) (2) Underperformance of prototype, first unit, or production components during testing (3) Unavailability of qualified vendors for critical components Technical risks associated with the design and operation of the system are also identified.

  10. EIS-0256: Sierra Pacific Power Company Alturas Transmission Line Project (adopted from BLM)

    Broader source: Energy.gov [DOE]

    This EIS evaluates the environmental setting and consequences of the construction and operation of the proposal Alturas Transmission Line Project. Sierra Pacific Power Company (SPPCO) has proposed this electric power transmission line to improve the existing operational capacity and reliability of its power transmission system and provide for anticipated growth in demand for electric power.

  11. Transmission Line Security Monitor

    ScienceCinema (OSTI)

    None

    2013-05-28T23:59:59.000Z

    The Transmission Line Security Monitor is a multi-sensor monitor that mounts directly on high-voltage transmission lines to detect, characterize and communicate terrorist activity, human tampering and threatening conditions around support towers. For more information about INL's critical infrastructure protection research, visit http://www.facebook.com/idahonationallaboratory.

  12. Transmission Line Security Monitor

    SciTech Connect (OSTI)

    None

    2011-01-01T23:59:59.000Z

    The Transmission Line Security Monitor is a multi-sensor monitor that mounts directly on high-voltage transmission lines to detect, characterize and communicate terrorist activity, human tampering and threatening conditions around support towers. For more information about INL's critical infrastructure protection research, visit http://www.facebook.com/idahonationallaboratory.

  13. Transmission Enhancement Technology Report

    E-Print Network [OSTI]

    of Existing Transmission 6 5. Potential New Equipment to Improve Transmission Capability 9 6. Potential New parties for the sites that should be studied as potential locations for new generation and to consult lignite and wind energy. " As per the requirements of the above-referenced Congressional direction

  14. Coiled transmission line pulse generators

    DOE Patents [OSTI]

    McDonald, Kenneth Fox (Columbia, MO)

    2010-11-09T23:59:59.000Z

    Methods and apparatus are provided for fabricating and constructing solid dielectric "Coiled Transmission Line" pulse generators in radial or axial coiled geometries. The pour and cure fabrication process enables a wide variety of geometries and form factors. The volume between the conductors is filled with liquid blends of monomers, polymers, oligomers, and/or cross-linkers and dielectric powders; and then cured to form high field strength and high dielectric constant solid dielectric transmission lines that intrinsically produce ideal rectangular high voltage pulses when charged and switched into matched impedance loads. Voltage levels may be increased by Marx and/or Blumlein principles incorporating spark gap or, preferentially, solid state switches (such as optically triggered thyristors) which produce reliable, high repetition rate operation. Moreover, these Marxed pulse generators can be DC charged and do not require additional pulse forming circuitry, pulse forming lines, transformers, or an a high voltage spark gap output switch. The apparatus accommodates a wide range of voltages, impedances, pulse durations, pulse repetition rates, and duty cycles. The resulting mobile or flight platform friendly cylindrical geometric configuration is much more compact, light-weight, and robust than conventional linear geometries, or pulse generators constructed from conventional components. Installing additional circuitry may accommodate optional pulse shape improvements. The Coiled Transmission Lines can also be connected in parallel to decrease the impedance, or in series to increase the pulse length.

  15. Transmission Cost Allocation Methodologies for Regional Transmission Organizations

    SciTech Connect (OSTI)

    Fink, S.; Rogers, J.; Porter, K.

    2010-07-01T23:59:59.000Z

    This report describes transmission cost allocation methodologies for transmission projects developed to maintain or enhance reliability, to interconnect new generators, or to access new resources and enhance competitive bulk power markets, otherwise known as economic transmission projects.

  16. SUBMITTED TO IEEE TRANSACTIONS ON POWER SYSTEMS, FEBRUARY 2002 1 Quantifying Transmission Reliability Margin

    E-Print Network [OSTI]

    SUBMITTED TO IEEE TRANSACTIONS ON POWER SYSTEMS, FEBRUARY 2002 1 Quantifying Transmission, power transmission reliability, power system security, power system availability I. Introduction Bulk power transfer capability computations have many uses in electric power system operation and planning

  17. Transmission Expansion Planning with Re-design

    E-Print Network [OSTI]

    2010-05-17T23:59:59.000Z

    distribution sectors, with a centralized regulation for transmission. In this context, the regulating entity is in charge, not only of operating the grid while maximizing energy ... generation sites are usually far away from the consumption centers. .... Typical examples of commodities are passengers using public transportation,.

  18. A MIXED INTEGER DISJUNCTIVE MODEL FOR TRANSMISSION ...

    E-Print Network [OSTI]

    Laura

    2001-10-26T23:59:59.000Z

    the transmission network expansion problem cannot guarantee ... disjunctive model, optimality can be proven for several hard ..... the size of the RCL list is dynamically self-adjusted (the so ... the RCL size is controlled by the parameter ?, where 0 ? ? ?. 1. ... and senior researcher in power system planning and operation.

  19. WEYL ASYMPTOTICS OF THE TRANSMISSION EIGENVALUES ...

    E-Print Network [OSTI]

    2014-09-02T23:59:59.000Z

    plex internal transmission eigenvalues when the domain is a ball and the index ..... parameter in the operators in a non-linear way; and the implicit choice of the .... in the interior of I, and thus, q ?p ITEs in I, since we include the right endpoint in.

  20. Methods and systems for micro transmissions

    DOE Patents [OSTI]

    Stalford, Harold L

    2014-12-23T23:59:59.000Z

    Methods and systems for micro transmissions for a micro machine may comprise an input shaft assembly coupled to a micro actuator, an output shaft assembly coupled to a micro shaft, and one or more power conversion elements operable to convert a first type of movement from the micro actuator into a second, disparate type of movement for the micro shaft.

  1. Design and operating characteristics of a transient kinetic analysis...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    operating characteristics of a transient kinetic analysis catalysis reactor system employing in situ transmission Design and operating characteristics of a transient kinetic...

  2. Designing electricity transmission auctions

    E-Print Network [OSTI]

    Greve, Thomas; Pollitt, Michael G.

    2012-10-26T23:59:59.000Z

    The UK has ambitious plans for exploiting offshore wind for electricity production in order to meet its challenging target under the EU Renewable Energy Directive. This could involve investing up to 20bn in transmission assets to bring electricity...

  3. Transmission Services Bulletin

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Standard Time On the first Sunday in November Transmission Services sets clocks from Daylight Savings Time (PD) back to Standard Time (PS). At 02:00 the time becomes 01:00. In...

  4. Downhole transmission system

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Fox, Joe (Spanish Fork, UT)

    2008-01-15T23:59:59.000Z

    A transmission system in a downhole component comprises a data transmission element in both ends of the downhole component. Each data transmission element houses an electrically conducting coil in a MCEI circular trough. An electrical conductor connects both the transmission elements. The electrical conductor comprises at least three electrically conductive elements insulated from each other. In the preferred embodiment the electrical conductor comprises an electrically conducting outer shield, an electrically conducting inner shield and an electrical conducting core. In some embodiments of the present invention, the electrical conductor comprises an electrically insulating jacket. In other embodiments, the electrical conductor comprises a pair of twisted wires. In some embodiments, the electrical conductor comprises semi-conductive material.

  5. Down hole transmission system

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT)

    2007-07-24T23:59:59.000Z

    A transmission system in a downhole component comprises a data transmission element in both ends of the downhole component. Each data transmission element houses an electrically conducting coil in a MCEI circular trough. The electrically conducting coil comprises at least two generally fractional loops. In the preferred embodiment, the transmission elements are connected by an electrical conductor. Preferably, the electrical conductor is a coaxial cable. Preferably, the MCEI trough comprises ferrite. In the preferred embodiment, the fractional loops are connected by a connecting cable. In one aspect of the present invention, the connecting cable is a pair of twisted wires. In one embodiment the connecting cable is a shielded pair of twisted wires. In another aspect of the present invention, the connecting cable is a coaxial cable. The connecting cable may be disposed outside of the MCEI circular trough.

  6. Flexible Transmission in the Smart Grid

    E-Print Network [OSTI]

    Hedman, Kory Walter

    2010-01-01T23:59:59.000Z

    Planning . 102 vi Transmission Line Maintenance Scheduling 103 Just-in-time Transmission 103 Flexible Transmission in the Smart Grid

  7. Honda Transmission Technical Center

    High Performance Buildings Database

    Russells Point, OH The Honda Transmission Technical Center is located on the Honda of America Manufacturing Plant facility site in Russells Point, Ohio. This facility is used for product engineering and market quality testing and analysis of automatic transmissions. The building contains a large workshop area for ten cars, a future dynamometer, two laboratories, an open office area, three conference rooms, a break room, restrooms, and related support areas.

  8. Bulk Power Transmission Study

    E-Print Network [OSTI]

    John, T.

    BULK POWER TRANSMISSION STUDY TOMMY JOH~ P. E. Manager of Resource Recovery Waste Management of North America, Inc. Houston, Texas Texans now have a choice. We can become more efficient and maintain our standard of living, or we can... continue business as usual and watch our standard of living erode from competition from other regions. In the past, except for improving reliability, there was no need for a strong transmission system. When Texas generation was primarily gas fueled...

  9. Managing transmission curtailment risk in wholesale power markets

    SciTech Connect (OSTI)

    Morey, Mathew J.; Kirsch, Laurence D.

    2009-11-15T23:59:59.000Z

    Risk resulting from transmission loading relief calls made by transmission system operators can be managed with information estimated by a statistical model capable of predicting one day in advance the probability that a particular wholesale power transaction might be curtailed. The model predicts this probability with a reasonable degree of accuracy using information on variables that can be obtained publicly. (author)

  10. EIS-0101: Thermopolis, Alcova, Casper Transmission Line Project

    Broader source: Energy.gov [DOE]

    The Western Area Power Administration developed this statement to evaluate the environmental impacts of constructing, operating and maintaining a 230-kilovolt transmission line between Thermopolis, Wyoming, and Alcova, Wyoming, and a 230/345-kilovolt transmission line between Alcova, Wyoming, and Casper, Wyoming.

  11. Wireless power transmission utilizing a phased array of Tesla coils

    E-Print Network [OSTI]

    Stark, Joseph C. (Joseph Charles), 1980-

    2004-01-01T23:59:59.000Z

    This thesis discusses the theory and design of coupled resonant systems and how they can be linked in a phased array for the wireless transmission of electrical power. A detailed derivation of their operational theory is ...

  12. EIS-0106: Great Falls-Conrad Transmission Line Project, Montana

    Broader source: Energy.gov [DOE]

    The Western Area Power Administration prepared this EIS to evaluate the environmental impacts of the construction and operation of a 230-kilovolt transmission line from Great Falls, Montana, to Conrad, Montana.

  13. Hybrid Transmission Corridor study

    SciTech Connect (OSTI)

    Clairmont, B.A.; Johnson, G.B.; Zaffanella, L.E. (General Electric Co., Lenox, MA (United States))

    1992-06-01T23:59:59.000Z

    Hybrid Transmission Corridors are areas where High Voltage Alternating Current (HVAC) transmission lines and High Voltage Direct Current (HVDC) transmission lines exist in close proximity of each other. Because of the acceptance of HVDC as a means of transporting electric power over long distances and the difficulties associated with obtaining new right-of-ways, HVDC lines may have to share the same transmission corridor with HVAC lines. The interactions between conductors energized with different types of voltages causes changes in the electrical stresses applied to the conductors and insulators. As a result, corona phenomena, field effects and insulation performance can be affected. This report presents the results of an investigation of the HVAC-HVDC interaction and its effect on corona and AC and DC electric field phenomena. The method of investigation was based on calculation methods developed at the EPRI High Voltage Transmission Research Center (HVTRC) and supported by the results of full and reduced-scale line tests. Also, a survey of existing hybrid corridors is given along with the results of measurements made at one of those corridors. A number of examples in which an existing AC corridor may be transformed into a hybrid corridor are discussed. The main result of the research is an analytical/empirical model for predicting the electrical/environmental performance of hybrid corridors, a definition of ACDC interaction and a set of criteria for specifying when the interaction becomes significant, and a set of design rules.

  14. PJM Interconnection (Multiple States)

    Broader source: Energy.gov [DOE]

    PJM (originally Pennsylvania, Jersey, Maryland) Interconnection is a Regional Transmission Organization (RTO) that coordinates the movement of wholesale electricity in all or parts of Delaware,...

  15. Printed circuit dispersive transmission line

    DOE Patents [OSTI]

    Ikezi, H.; Lin-Liu, Y.R.; DeGrassie, J.S.

    1991-08-27T23:59:59.000Z

    A printed circuit dispersive transmission line structure is disclosed comprising an insulator, a ground plane formed on one surface of the insulator, a first transmission line formed on a second surface of the insulator, and a second transmission line also formed on the second surface of the insulator and of longer length than the first transmission line and periodically intersecting the first transmission line. In a preferred embodiment, the transmission line structure exhibits highly dispersive characteristics by designing the length of one of the transmission line between two adjacent periodic intersections to be longer than the other. 5 figures.

  16. North Dakota Energy Conversion and Transmission Facility Siting Act (North Dakota)

    Broader source: Energy.gov [DOE]

    This chapter aims to ensure that the location, construction, and operation of energy conversion facilities and transmission facilities will produce minimal adverse effects on the environment and...

  17. Enhanced Geothermal Systems (EGS) with CO2as Heat Transmission Fluid

    Broader source: Energy.gov [DOE]

    The overall objective of the research is to explore the feasibility of operating enhanced geothermal systems (EGS) with CO2as heat transmission fluid.

  18. EIS-0344: Grand Coulee-Bell 500 kV Transmission Line

    Broader source: Energy.gov [DOE]

    This EIS analyzes DOE's proposed action for the construction and operation of the proposed Grand Coulee-Bell 500-kV Transmission Line Project.

  19. Exploration of Resource and Transmission Expansion Decisions in the Western Renewable Energy Zone Initiative

    E-Print Network [OSTI]

    Mills, Andrew

    2010-01-01T23:59:59.000Z

    operating costs, and substation costs for substations thatsubstation, and are derived from a simple levelized-cost-of-above) transmission substation. Capital costs vary for the

  20. Low Frequency Transmission Final Project Report

    E-Print Network [OSTI]

    to HVDC transmission and conventional AC transmission in different configurations. The issue is quite

  1. Omega Transmission Lines

    E-Print Network [OSTI]

    Vehmas, Joni

    2013-01-01T23:59:59.000Z

    In this paper, we show how bi-anisotropic media with omega-type response can be realized using periodically loaded transmission lines. General conditions for the needed unit cell circuit block are derived. Also, an implementation is shown and analyzed.

  2. Borehole data transmission apparatus

    DOE Patents [OSTI]

    Kotlyar, O.M.

    1993-03-23T23:59:59.000Z

    A borehole data transmission apparatus is described whereby a centrifugal pump impeller(s) is used to provide a turbine stage having substantial pressure characteristics in response to changing rotational speed of a shaft for the pressure pulsing of data from the borehole through the drilling mud to the surface of the earth.

  3. Borehole data transmission apparatus

    DOE Patents [OSTI]

    Kotlyar, Oleg M. (1739 Grandview #2, Idaho Falls, ID 83402)

    1993-01-01T23:59:59.000Z

    A borehole data transmission apparatus whereby a centrifugal pump impeller(s) is used to provide a turbine stage having substantial pressure characteristics in response to changing rotational speed of a shaft for the pressure pulsing of data from the borehole through the drilling mud to the surface of the earth.

  4. Autonomous data transmission apparatus

    DOE Patents [OSTI]

    Kotlyar, Oleg M. (4675 W. 3825 S, Salt Lake City, UT 84120)

    1997-01-01T23:59:59.000Z

    A autonomous borehole data transmission apparatus for transmitting measurement data from measuring instruments at the downhole end of a drill string by generating pressure pulses utilizing a transducer longitudinally responsive to magnetic field pulses caused by electrical pulses corresponding to the measured downhole parameters.

  5. Autonomous data transmission apparatus

    DOE Patents [OSTI]

    Kotlyar, O.M.

    1997-03-25T23:59:59.000Z

    A autonomous borehole data transmission apparatus is described for transmitting measurement data from measuring instruments at the downhole end of a drill string by generating pressure pulses utilizing a transducer longitudinally responsive to magnetic field pulses caused by electrical pulses corresponding to the measured downhole parameters. 4 figs.

  6. Hydraulic system for a ratio change transmission

    DOE Patents [OSTI]

    Kalns, Ilmars (Northville, MI)

    1981-01-01T23:59:59.000Z

    Disclosed is a drive assembly (10) for an electrically powered vehicle (12). The assembly includes a transaxle (16) having a two-speed transmission (40) and a drive axle differential (46) disposed in a unitary housing assembly (38), an oil-cooled prime mover or electric motor (14) for driving the transmission input shaft (42), an adapter assembly (24) for supporting the prime mover on the transaxle housing assembly, and a hydraulic system (172) providing pressurized oil flow for cooling and lubricating the electric motor and transaxle and for operating a clutch (84) and a brake (86) in the transmission to shift between the two-speed ratios of the transmission. The adapter assembly allows the prime mover to be supported in several positions on the transaxle housing. The brake is spring-applied and locks the transmission in its low-speed ratio should the hydraulic system fail. The hydraulic system pump is driven by an electric motor (212) independent of the prime mover and transaxle.

  7. Installing and operating FEGTEMs

    SciTech Connect (OSTI)

    Hetherington, C.J.; Cullis, A.G.; Walker, S.; Turner, J.; Nelson, E.C.; O'Keefe, M.A.

    1997-11-03T23:59:59.000Z

    In order to operate at full potential, Field-Emission-Gun Transmission Electron Microscopes (FEG-TEMs) require special environments designed to minimize the effects of vibration and electromagnetic noise. This report shows how careful attention to these details can enable such instruments to achieve their design parameters and produce information transfer to sub-Angstrom resolutions.

  8. Secure sequential transmission of quantum information

    E-Print Network [OSTI]

    Kabgyun Jeong; Jaewan Kim

    2015-01-19T23:59:59.000Z

    We propose a quantum communication protocol that can be used to transmit any quantum state, one party to another via several intermediate nodes, securely on quantum communication network. The scheme makes use of the sequentially chained and approximate version of private quantum channels satisfying certain commutation relation of $n$-qubit Pauli operations. In this paper, we study the sequential structure, security analysis, and efficiency of the quantum sequential transmission (QST) protocol in depth.

  9. Drill string transmission line

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David S. (Lehi, UT); Bradford, Kline (Orem, UT); Fox, Joe (Spanish Fork, UT)

    2006-03-28T23:59:59.000Z

    A transmission line assembly for transmitting information along a downhole tool comprising a pin end, a box end, and a central bore traveling between the pin end and the box end, is disclosed in one embodiment of the invention as including a protective conduit. A transmission line is routed through the protective conduit. The protective conduit is routed through the central bore and the ends of the protective conduit are routed through channels formed in the pin end and box end of the downhole tool. The protective conduit is elastically forced into a spiral or other non-linear path along the interior surface of the central bore by compressing the protective conduit to a length within the downhole tool shorter than the protective conduit.

  10. Transmission line: design manual

    SciTech Connect (OSTI)

    Farr, H.H.

    1980-01-01T23:59:59.000Z

    The purpose of this manual is to outline the various requirements for, and the procedures to be followed in the design of power transmission lines by the Bureau of Reclamation, US Department of the Interior. Numerous design studies, which have been made on specific aspects of transmission line design, are included with explanations of their applications. Information is presented concerning such aspects as selection of type of construction, conductor sags and tensions, insulation, lightning protection, clearance patterns, galloping conductors, structure limitation and guying charts, and structure spotting. Structure design examples are limited to wood-pole construction. Interpretations of the National Electrical Safety Code and other codes are made as required. Some of the example problems were developed when the sixth edition of NESC was current, and are so noted; however, most examples use the 1977 edition of NESC.

  11. Patterns of Transmission Investment

    E-Print Network [OSTI]

    Joskow, Paul

    2006-03-14T23:59:59.000Z

    while providing imperfect protection against abusive self-dealing behavior by the TSO. The creation of truly independent TSOs reduces the regulatory burdens and creates entities whose management focuses on the transmission business. 15... of physical components that are to be added to the network or to replace components that are already in the network. They include: a. new relays and switches b. new remote monitoring and control equipment c. transformer upgrades d. substation...

  12. Geothermal Resources and Transmission Planning

    Broader source: Energy.gov [DOE]

    This project addresses transmission-related barriers to utility-scale deployment of geothermal electric generation technologies.

  13. Boardman to Hemingway Transmission Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Improvement (CBPI) Customer Forum Energy Imbalance Market Generator Interconnection Reform Implementation Network Integration Transmission Service (NT Service) Network Open...

  14. Evaluation of power system security and development of transmission pricing method

    E-Print Network [OSTI]

    Kim, Hyungchul

    2004-11-15T23:59:59.000Z

    classifier is also proposed. This method can be useful for system operators to make security decisions during on-line power system operation. This dissertation also suggests an approach for allocating transmission transaction costs based on reliability...

  15. Transmission - Contact Information

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of ScienceandMesa del SolStrengthening a solidSynthesisAppliances » DataContact-Information-Transmission

  16. Transmission | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:Ezfeedflag JumpID-f <MaintainedInformationThePtyTownTrama TecnoTransmission

  17. Transmission | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere IRaghuraji Agro IndustriesTown of Ladoga, Indiana (Utility Company) JumpTradeWindPrepared asTransmission

  18. Colorado Electrical Transmission Grid

    SciTech Connect (OSTI)

    Zehner, Richard E.

    2012-02-01T23:59:59.000Z

    Citation Information: Originator: Earth Science &Observation Center (ESOC), CIRES, University of Colorado at Boulder Originator: Xcel Energy Publication Date: 2012 Title: Colorado XcelEnergy NonXcel Transmission Network Edition: First Publication Information: Publication Place: Earth Science & Observation Center, Cooperative Institute for Research in Environmental Science (CIRES), University of Colorado, Boulder Publisher: Earth Science &Observation Center (ESOC), CIRES, University of Colorado at Boulder Description: This layer contains transmission network of Colorado Spatial Domain: Extent: Top: 4540689.017558 m Left: 160606.141934 m Right: 758715.946645 m Bottom: 4098910.893397m Contact Information: Contact Organization: Earth Science &Observation Center (ESOC), CIRES, University of Colorado at Boulder Contact Person: Khalid Hussein Address: CIRES, Ekeley Building Earth Science & Observation Center (ESOC) 216 UCB City: Boulder State: CO Postal Code: 80309-0216 Country: USA Contact Telephone: 303-492-6782 Spatial Reference Information: Coordinate System: Universal Transverse Mercator (UTM) WGS’1984 Zone 13N False Easting: 500000.00000000 False Northing: 0.00000000 Central Meridian: -105.00000000 Scale Factor: 0.99960000 Latitude of Origin: 0.00000000 Linear Unit: Meter Datum: World Geodetic System ’1984 (WGS ’1984) Prime Meridian: Greenwich Angular Unit: Degree Digital Form: Format Name: Shapefile

  19. Electricity transmission congestion costs: A review of recent reports

    SciTech Connect (OSTI)

    Lesieutre, Bernard C.; Eto, Joseph H.

    2003-10-01T23:59:59.000Z

    Recently, independent system operators (ISOs) and others have published reports on the costs of transmission congestion. The magnitude of congestion costs cited in these reports has contributed to the national discussion on the current state of U.S. electricity transmission system and whether it provides an adequate platform for competition in wholesale electricity markets. This report reviews reports of congestion costs and begins to assess their implications for the current national discussion on the importance of the U.S. electricity transmission system for enabling competitive wholesale electricity markets. As a guiding principle, we posit that a more robust electricity system could reduce congestion costs; and thereby, (1) facilitate more vibrant and fair competition in wholesale electricity markets, and (2) enable consumers to seek out the lowest prices for electricity. Yet, examining the details suggests that, sometimes, there will be trade-offs between these goals. Therefore, it is essential to understand who pays, how much, and how do they benefit in evaluating options (both transmission and non-transmission alternatives) to address transmission congestion. To describe the differences among published estimates of congestion costs, we develop and motivate three ways by which transmission congestion costs are calculated in restructured markets. The assessment demonstrates that published transmission congestion costs are not directly comparable because they have been developed to serve different purposes. More importantly, critical information needed to make them more comparable, for example in order to evaluate the impacts of options to relieve congestion, is sometimes not available.

  20. Factors influencing quantitative liquid (scanning) transmission...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Factors influencing quantitative liquid (scanning) transmission electron microscopy. Factors influencing quantitative liquid (scanning) transmission electron microscopy. Abstract:...

  1. Electric vehicle drive train with direct coupling transmission

    DOE Patents [OSTI]

    Tankersley, Jerome B. (Fredericksburg, VA); Boothe, Richard W. (Roanoke, VA); Konrad, Charles E. (Roanoke, VA)

    1995-01-01T23:59:59.000Z

    An electric vehicle drive train includes an electric motor and an associated speed sensor, a transmission operable in a speed reduction mode or a direct coupled mode, and a controller responsive to the speed sensor for operating the transmission in the speed reduction mode when the motor is below a predetermined value, and for operating the motor in the direct coupled mode when the motor speed is above a predetermined value. The controller reduces the speed of the motor, such as by regeneratively braking the motor, when changing from the speed reduction mode to the direct coupled mode. The motor speed may be increased when changing from the direct coupled mode to the speed reduction mode. The transmission is preferably a single stage planetary gearbox.

  2. Electric vehicle drive train with direct coupling transmission

    DOE Patents [OSTI]

    Tankersley, J.B.; Boothe, R.W.; Konrad, C.E.

    1995-04-04T23:59:59.000Z

    An electric vehicle drive train includes an electric motor and an associated speed sensor, a transmission operable in a speed reduction mode or a direct coupled mode, and a controller responsive to the speed sensor for operating the transmission in the speed reduction mode when the motor is below a predetermined value, and for operating the motor in the direct coupled mode when the motor speed is above a predetermined value. The controller reduces the speed of the motor, such as by regeneratively braking the motor, when changing from the speed reduction mode to the direct coupled mode. The motor speed may be increased when changing from the direct coupled mode to the speed reduction mode. The transmission is preferably a single stage planetary gearbox. 6 figures.

  3. Operations & Maintenance

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    and Resources Contact Information Transmission Planning Western OATT Revision Maintenance Data Outage Coordination Request (Doc - 21K) Right of Way - Vegetation Management...

  4. Device for adapting continuously variable transmissions to infinitely variable transmissions with forward-neutral-reverse capabilities

    DOE Patents [OSTI]

    Wilkes, Donald F. (Albuquerque, NM); Purvis, James W. (Albuquerque, NM); Miller, A. Keith (Albuquerque, NM)

    1997-01-01T23:59:59.000Z

    An infinitely variable transmission is capable of operating between a maximum speed in one direction and a minimum speed in an opposite direction, including a zero output angular velocity, while being supplied with energy at a constant angular velocity. Input energy is divided between a first power path carrying an orbital set of elements and a second path that includes a variable speed adjustment mechanism. The second power path also connects with the orbital set of elements in such a way as to vary the rate of angular rotation thereof. The combined effects of power from the first and second power paths are combined and delivered to an output element by the orbital element set. The transmission can be designed to operate over a preselected ratio of forward to reverse output speeds.

  5. Transmission Planning | Department of Energy

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Improving Performance of Federal Permitting and Review of Infrastructure Projects Energy Corridors on Federal Lands Transmission Projects Proposed Under EPAct Section 1222 Activity...

  6. AGENDA: PETROLEUM PRODUCT TRANSMISSION & DISTRIBUTION

    Broader source: Energy.gov [DOE]

    The agenda for the Quadrennial Energy Review (QER) public stakeholder meeting in New Orleans on petroleum product transmission, distribution, and storage.

  7. Comments by the American Electric Power System on Proposed Coordination of Federal Authorizations for Electric Transmission Facilities

    Broader source: Energy.gov [DOE]

     Proposed Coordination of Federal Authorizations for Electric Transmission Facilities – Interim Final Rule and Proposed Rule (DOE, 10 CR Part 900): The utility operating companies of the American...

  8. Raj JainThe Ohio State University Data TransmissionData TransmissionData Transmission

    E-Print Network [OSTI]

    Jain, Raj

    The Ohio State University 2-14 Bit Error RateBit Error RateBit Error Rate Energy/bit Eb =STb, where TbRaj JainThe Ohio State University 2-1 Data TransmissionData TransmissionData Transmission Raj Jain Professor of CIS The Ohio State University Columbus, OH 43210 Jain@ACM.Org http://www.cis.ohio

  9. HVDC power transmission technology assessment

    SciTech Connect (OSTI)

    Hauth, R.L.; Tatro, P.J.; Railing, B.D. [New England Power Service Co., Westborough, MA (United States); Johnson, B.K.; Stewart, J.R. [Power Technologies, Inc., Schenectady, NY (United States); Fink, J.L.

    1997-04-01T23:59:59.000Z

    The purpose of this study was to develop an assessment of the national utility system`s needs for electric transmission during the period 1995-2020 that could be met by future reduced-cost HVDC systems. The assessment was to include an economic evaluation of HVDC as a means for meeting those needs as well as a comparison with competing technologies such as ac transmission with and without Flexible AC Transmission System (FACTS) controllers. The role of force commutated dc converters was to be assumed where appropriate. The assessment begins by identifying the general needs for transmission in the U.S. in the context of a future deregulated power industry. The possible roles for direct current transmission are then postulated in terms of representative scenarios. A few of the scenarios are illustrated with the help of actual U.S. system examples. non-traditional applications as well as traditional applications such as long lines and asynchronous interconnections are discussed. The classical ``break-even distance`` concept for comparing HVDC and ac lines is used to assess the selected scenarios. The impact of reduced-cost converters is reflected in terms of the break-even distance. This report presents a comprehensive review of the functional benefits of HVDC transmission and updated cost data for both ac and dc system components. It also provides some provocative thoughts on how direct current transmission might be applied to better utilize and expand our nation`s increasingly stressed transmission assets.

  10. Direct current power transmission systems

    SciTech Connect (OSTI)

    Padiyar, K.R.

    1991-01-01T23:59:59.000Z

    This book represents text on HVDC transmission available. It deals with the various aspects of the state of the art in HVDC transmission technology. This book presents many aspects of interactions of AC/DC systems. Modeling and analysis of DC systems are also discussed in detail.

  11. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01T23:59:59.000Z

    Wind Energy Access, Transmission, and Intermittency Really Cost?transmission cost barrier for wind energy. A secondary goalfocus on the cost of transmission for wind energy does not

  12. EC Transmission Line Materials

    SciTech Connect (OSTI)

    Bigelow, Tim S [ORNL

    2012-05-01T23:59:59.000Z

    The purpose of this document is to identify materials acceptable for use in the US ITER Project Office (USIPO)-supplied components for the ITER Electron cyclotron Heating and Current Drive (ECH&CD) transmission lines (TL), PBS-52. The source of material property information for design analysis shall be either the applicable structural code or the ITER Material Properties Handbook. In the case of conflict, the ITER Material Properties Handbook shall take precedence. Materials selection, and use, shall follow the guidelines established in the Materials Assessment Report (MAR). Materials exposed to vacuum shall conform to the ITER Vacuum Handbook. [Ref. 2] Commercial materials shall conform to the applicable standard (e.g., ASTM, JIS, DIN) for the definition of their grade, physical, chemical and electrical properties and related testing. All materials for which a suitable certification from the supplier is not available shall be tested to determine the relevant properties, as part of the procurement. A complete traceability of all the materials including welding materials shall be provided. Halogenated materials (example: insulating materials) shall be forbidden in areas served by the detritiation systems. Exceptions must be approved by the Tritium System and Safety Section Responsible Officers.

  13. Key-shift transmission

    SciTech Connect (OSTI)

    Nemoto, S.

    1989-03-07T23:59:59.000Z

    A key-shift transmission is described, characterized by the speed-change shaft being divided into a pair of trough-shaped shaft halves each having an arched inner surface which defines a part of a cylindrical bore extending axially through the speed-change shaft thereby the shaft being formed into a hollow shaft, and by each of the shaft halves including a pair of flattened end surfaces which extend axially of each shaft half at both sides of the inner surface, one of the end surfaces having thereon an axially elongated projection and the other of the end surfaces having herein an axially elongated recess of a depth smaller than the height of the projection. The pair of shaft halves are engaged to each other co-rotatably by fitting the projections of the respective shaft halves into the recesses of the respective shaft halves so as to form in an outer surface of the speed-change shaft a pair of elongated axial grooves which are located radially outwardly of the elongated projections of the respective shaft halves and between the flattened end surfaces of the respective shaft halves. A pair of the shift keys are disposed within the pair of elongated axial grooves.

  14. Regional Transmission Projects: Finding Solutions

    SciTech Connect (OSTI)

    The Keystone Center

    2005-06-15T23:59:59.000Z

    The Keystone Center convened and facilitated a year-long Dialogue on "Regional Transmission Projects: Finding Solutions" to develop recommendations that will help address the difficult and contentious issues related to expansions of regional electric transmission systems that are needed for reliable and economic transmission of power within and across regions. This effort brought together a cross-section of affected stakeholders and thought leaders to address the problem with the collective wisdom of their experience and interests. Transmission owners sat at the table with consumer advocates and environmental organizations. Representatives from regional transmission organizations exchanged ideas with state and federal regulators. Generation developers explored common interests with public power suppliers. Together, the Dialogue participants developed consensus solutions about how to begin unraveling some of the more intractable issues surrounding identification of need, allocation of costs, and reaching consensus on siting issues that can frustrate the development of regional transmission infrastructure. The recommendations fall into three broad categories: 1. Recommendations on appropriate institutional arrangements and processes for achieving regional consensus on the need for new or expanded transmission infrastructure 2. Recommendations on the process for siting of transmission lines 3. Recommendations on the tools needed to support regional planning, cost allocation, and siting efforts. List of Dialogue participants: List of Dialogue Participants: American Electric Power American Transmission Company American Wind Energy Association California ISO Calpine Corporation Cinergy Edison Electric Institute Environmental Defense Federal Energy Regulatory Commission Great River Energy International Transmission Company ISO-New England Iowa Public Utility Board Kanner & Associates Midwest ISO National Association of Regulatory Utility Commissioners National Association of State Utility Consumer Advocates National Grid Northeast Utilities PA Office of Consumer Advocates Pacific Gas & Electric Corporation Pennsylvania Public Utility Commission PJM Interconnection The Electricity Consumers Resource Council U.S. Department of Energy US Department of the Interior Van Ness Feldman Western Interstate Energy Board Wind on the Wires Wisconsin Public Service Commission Xcel Energy

  15. Abstract: During power deregulation, power companies are releasing their transmission grids to form ISOs/RTOs while

    E-Print Network [OSTI]

    to form ISOs/RTOs while maintaining their own state estimators over their own areas. A recent trend for these ISOs/RTOs is to further combine and enlarge to become a bigger Mega-RTO grid for a better market the whole state; in our algorithm, the existing state estimators in local companies/ISOs/RTOs are fully

  16. Some operating features of a 100,000-volt transmission

    E-Print Network [OSTI]

    Jones, Raymond

    1914-03-17T23:59:59.000Z

    . Climatic conditions. c. Low strength of conductors. E. Effects of high altitudes - - - Page 15. a. Presence of static. b. Lower dielectric strength. c. Lowering of critical voltage. F. Effect of pitch blende deposits - - Page 21. a. Ionization... conditions very peculiar to this line due primarily to the high altitude. 1. The presence of a large static charge on the line even when not energized. 2. The lowering of the dielectric strength of the air. 3. The lowering of the critical voltage...

  17. EA-343 Midwest Independent Transmission Operator (MISO) | Department of

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't Your Destiny:Revised Finding of No53197EFindingEA-257-CEA-296-B22

  18. Midwest Independent Transmission System Operator | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation, searchOfRose BendMiasole Inc JumpMicroPlanet Name: Midwest Independent

  19. EA-343 Midwest Independent Transmission Operator (MISO) | Department of

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy China 2015 Business42.1Energy |Final Site-WideBPAPowerEE US No.SubsidaryShellEnergy

  20. Midwest Independent Transmission System Operator Smart Grid Project | Open

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnual SiteofEvaluatingGroup |JilinLu anMicrogreen Polymers Inc Jump to:JumpMidwest Energy IncEnergy

  1. NWCC Transmission Case Study III

    SciTech Connect (OSTI)

    Terry Allison, Steve Wiese

    2000-03-01T23:59:59.000Z

    OAK-B135 Transmission System Improvements for Wind Energy Development in the Upper Midwest and Great Plains: Opportunities and Obstacles. This case study set out to ascertain the validity of three assumptions from the perspectives of stakeholders involved in wind energy and transmission issues in the Upper Midwest and Great Plains. The assumptions, and the stakeholders' reactions to each, are summarized below: Assumption 1--Transmission system improvements would provide significant benefits to the electricity network and its customers. Respondents acknowledge the potential for overall system benefits in the form of reduced line losses, improved grid stability and reliability, and enhanced ability to conduct spot market transactions. They also agree that these benefits relate to specific regional needs. However, there is disagreement over the extent of other benefits such as efficiency gains and cost savings from reduced line losses. Further, environmental and community interest groups point out that none of these benefits are realized without significant financial, environmental and social costs. Assumption 2--The benefits of transmission improvements would be helpful, but not confined, to wind power. All respondents agree that wind energy could benefit from transmission system improvements. But they also acknowledge, reluctantly, in the case of environmental stakeholders, that the benefits of an improved transmission system cannot be limited to environmentally preferable forms of generation. Some environmental and community advocate respondents also feel that transmission system improvement projects can be avoided altogether through energy conservation and efficiency measures, and by substituting wind energy for fossil generation. Assumption 3--Transmission alliances among stakeholders within and external to the wind community can provide benefits in the public interest. The fractured, multi-jurisdictional governance of the regional transmission system, and the distrust and diversity of perspectives among affected stakeholders, may make the formation of multi-stakeholder alliances necessary to accomplishing transmission goals. If the wind industry and utilities want to partner with environmental and community advocate groups in supporting a transmission project, they may have to convince these groups that the project would result in a net environmental benefit. The project proponents would have to make the case that the benefits of the additional wind energy will at least offset the emissions of any additional fossil generation made possible by the transmission project, as well as offset the environmental impact of the transmission project itself.

  2. Great Plains Wind Energy Transmission Development Project

    SciTech Connect (OSTI)

    Brad G. Stevens, P.E.; Troy K. Simonsen; Kerryanne M. Leroux

    2012-06-09T23:59:59.000Z

    In fiscal year 2005, the Energy & Environmental Research Center (EERC) received funding from the U.S. Department of Energy (DOE) to undertake a broad array of tasks to either directly or indirectly address the barriers that faced much of the Great Plains states and their efforts to produce and transmit wind energy at the time. This program, entitled Great Plains Wind Energy Transmission Development Project, was focused on the central goal of stimulating wind energy development through expansion of new transmission capacity or development of new wind energy capacity through alternative market development. The original task structure was as follows: Task 1 - Regional Renewable Credit Tracking System (later rescoped to Small Wind Turbine Training Center); Task 2 - Multistate Transmission Collaborative; Task 3 - Wind Energy Forecasting System; and Task 4 - Analysis of the Long-Term Role of Hydrogen in the Region. As carried out, Task 1 involved the creation of the Small Wind Turbine Training Center (SWTTC). The SWTTC, located Grand Forks, North Dakota, consists of a single wind turbine, the Endurance S-250, on a 105-foot tilt-up guyed tower. The S-250 is connected to the electrical grid on the 'load side' of the electric meter, and the power produced by the wind turbine is consumed locally on the property. Establishment of the SWTTC will allow EERC personnel to provide educational opportunities to a wide range of participants, including grade school through college-level students and the general public. In addition, the facility will allow the EERC to provide technical training workshops related to the installation, operation, and maintenance of small wind turbines. In addition, under Task 1, the EERC hosted two small wind turbine workshops on May 18, 2010, and March 8, 2011, at the EERC in Grand Forks, North Dakota. Task 2 involved the EERC cosponsoring and aiding in the planning of three transmission workshops in the midwest and western regions. Under Task 3, the EERC, in collaboration with Meridian Environmental Services, developed and demonstrated the efficacy of a wind energy forecasting system for use in scheduling energy output from wind farms for a regional electrical generation and transmission utility. With the increased interest at the time of project award in the production of hydrogen as a critical future energy source, many viewed hydrogen produced from wind-generated electricity as an attractive option. In addition, many of the hydrogen production-related concepts involve utilization of energy resources without the need for additional electrical transmission. For this reason, under Task 4, the EERC provided a summary of end uses for hydrogen in the region and focused on one end product in particular (fertilizer), including several process options and related economic analyses.

  3. Energy Transmission and Infrastructure

    SciTech Connect (OSTI)

    Mathison, Jane

    2012-12-31T23:59:59.000Z

    The objective of Energy Transmission and Infrastructure Northern Ohio (OH) was to lay the conceptual and analytical foundation for an energy economy in northern Ohio that will: • improve the efficiency with which energy is used in the residential, commercial, industrial, agricultural, and transportation sectors for Oberlin, Ohio as a district-wide model for Congressional District OH-09; • identify the potential to deploy wind and solar technologies and the most effective configuration for the regional energy system (i.e., the ratio of distributed or centralized power generation); • analyze the potential within the district to utilize farm wastes to produce biofuels; • enhance long-term energy security by identifying ways to deploy local resources and building Ohio-based enterprises; • identify the policy, regulatory, and financial barriers impeding development of a new energy system; and • improve energy infrastructure within Congressional District OH-09. This objective of laying the foundation for a renewable energy system in Ohio was achieved through four primary areas of activity: 1. district-wide energy infrastructure assessments and alternative-energy transmission studies; 2. energy infrastructure improvement projects undertaken by American Municipal Power (AMP) affiliates in the northern Ohio communities of Elmore, Oak Harbor, and Wellington; 3. Oberlin, OH-area energy assessment initiatives; and 4. a district-wide conference held in September 2011 to disseminate year-one findings. The grant supported 17 research studies by leading energy, policy, and financial specialists, including studies on: current energy use in the district and the Oberlin area; regional potential for energy generation from renewable sources such as solar power, wind, and farm-waste; energy and transportation strategies for transitioning the City of Oberlin entirely to renewable resources and considering pedestrians, bicyclists, and public transportation as well as drivers in developing transportation policies; energy audits and efficiency studies for Oberlin-area businesses and Oberlin College; identification of barriers to residential energy efficiency and development of programming to remove these barriers; mapping of the solar-photovoltaic and wind-energy supply chains in northwest Ohio; and opportunities for vehicle sharing and collaboration among the ten organizations in Lorain County from the private, government, non-profit, and educational sectors. With non-grant funds, organizations have begun or completed projects that drew on the findings of the studies, including: creation of a residential energy-efficiency program for the Oberlin community; installation of energy-efficient lighting in Oberlin College facilities; and development by the City of Oberlin and Oberlin College of a 2.27 megawatt solar photovoltaic facility that is expected to produce 3,000 megawatt-hours of renewable energy annually, 12% of the College’s yearly power needs. Implementation of these and other projects is evidence of the economic feasibility and technical effectiveness of grant-supported studies, and additional projects are expected to advance to implementation in the coming years. The public has benefited through improved energydelivery systems and reduced energy use for street lighting in Elmore, Oak Harbor, and Wellington; new opportunities for assistance and incentives for residential energy efficiency in the Oberlin community; new opportunities for financial and energy savings through vehicle collaboration within Lorain County; and decreased reliance on fossil fuels and expanded production of renewable energy in the region. The dissemination conference and the summary report developed for the conference also benefited the public, but making the findings and recommendations of the regional studies broadly available to elected officials, city managers, educators, representatives of the private sector, and the general public.

  4. Multi-ratio transmission

    SciTech Connect (OSTI)

    Polak, J.C.

    1987-07-14T23:59:59.000Z

    A preselected multi-ratio power transmission is described comprising: input means for transmitting drive forces; output means; first, second and third friction clutch means each selectively engageable with the input means for accepting drive forces. First input gear means drivingly connects with the first friction clutch means; second input gear means drivingly connects with the second friction clutch means; third input gear means drivingly connects with the third clutch means; first output gear means drivingly connects with the first input gear means; second output gear means drivingly connects with the first and second input gear means; third output means drivingly connects between the third input gear means and the output means; and one double-acting synchronizer clutch for selectively engaging the first output gear means with the output means and alternately the second output gear means with the output means. The first friction clutch means and the one double-acting synchronizer clutch cooperates during engagement to establish two forward drive ratios between the input and output means. The second friction clutch means and the one double-acting synchronizer clutch cooperates during engagement to establish two other forward drive ratios between the input and output means. The third friction clutch means is engageable to provide another forward drive ratio between the input means and the output means; and the one double-acting synchronizer clutch is relieved of transmitting drive forces during the engagement of the third friction clutch means and being manipulable for alternate connection with either the first output gear or the second output gear while the third friction clutch means is engaged.

  5. Electrical transmission line diametrical retainer

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David (Lehi, UT); Dahlgren, Scott (Provo, UT); Sneddon, Cameron (Provo, UT); Briscoe, Michael (Lehi, UT); Fox, Joe (Spanish Fork, UT)

    2004-12-14T23:59:59.000Z

    The invention is a mechanism for retaining an electrical transmission line. In one embodiment of the invention it is a system for retaining an electrical transmission line within down hole components. In accordance with one aspect of the invention, the system includes a plurality of downhole components, such as sections of pipe in a drill string. The system also includes a coaxial cable running between the first and second end of a drill pipe, the coaxial cable having a conductive tube and a conductive core within it. The invention allows the electrical transmission line to with stand the tension and compression of drill pipe during routine drilling cycles.

  6. Midwest Transmission Workshop I Summary

    SciTech Connect (OSTI)

    Kevin Bryan

    2001-05-01T23:59:59.000Z

    OAK-B135 The meeting was opened with a review of the purposes of the workshop: (1) Present and discuss key studies and assessments of transmission upgrades, additions and related issues for the upper Midwest, including work that addresses the full range of views on these topics; (2) Understand the various transmission issues in the upper Midwest and discuss options for addressing the issues; and (3) Identify the decision makers and entities that need to play an active role if transmission issues are to be resolved, and agree on next steps for engaging these individuals and organizations through education, outreach, and information dissemination.

  7. EA-1960: Townsite Solar Project Transmission Line, Clark County, Nevada

    Broader source: Energy.gov [DOE]

    The Bureau of Land Management, with Western Area Power Administration as a cooperating agency, prepared an EA to evaluate potential impacts of a proposal to build and operate a 180-MW photovoltaic facility; a 220, 230, or 500 kV transmission line; and associated facilities in Clark County, Nevada.

  8. EIS-0090: Fort Peck-Havre Transmission Line Project, Montana

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy’s Western Area Power Administration prepared this statement to assess the potential environmental and socioeconomic implications of its proposed action to construct and operate a 230kV transmission line from Fort Peck to Havre, Montana, with three intermediate interconnecting substations.

  9. System Operation 1 Introduction to System Operation, Optimization, and Control

    E-Print Network [OSTI]

    McCalley, James D.

    not be confused with regional transmission organizations (RTOs) indicated in Fig. 0.c (and are generally also disaggregation." The motivation for doing so was to create conditions conducive for competition within this very well. In #12;System Operation 5 bringing marketplace competition to the industry, it was necessary

  10. Flexible Transmission in the Smart Grid

    E-Print Network [OSTI]

    Hedman, Kory Walter

    2010-01-01T23:59:59.000Z

    S. S. Oren, “Smart flexible just-in-time transmission andFlexible Transmission in the Smart Grid By Kory WalterAll rights reserved. A BSTRACT Flexible Transmission in the

  11. Transmission Workshop | Department of Energy

    Energy Savers [EERE]

    - November 1-2, 2012 On November 1-2, 2012, the GTT presented a workshop on grid integration on the transmission system at the DoubleTree Crystal City near Washington, DC. A...

  12. Video transmission over wireless networks 

    E-Print Network [OSTI]

    Zhao, Shengjie

    2005-08-29T23:59:59.000Z

    Compressed video bitstream transmissions over wireless networks are addressed in this work. We first consider error control and power allocation for transmitting wireless video over CDMA networks in conjunction with multiuser detection. We map a...

  13. Video transmission over wireless networks

    E-Print Network [OSTI]

    Zhao, Shengjie

    2005-08-29T23:59:59.000Z

    Compressed video bitstream transmissions over wireless networks are addressed in this work. We first consider error control and power allocation for transmitting wireless video over CDMA networks in conjunction with multiuser detection. We map a...

  14. Immunology of naturally transmissible tumours

    E-Print Network [OSTI]

    Siddle, Hannah V.; Kaufman, Jim

    2014-09-04T23:59:59.000Z

    in a graft. These APCs move to the draining lymph nodes of the host, after which primed effector T cells migrate back to the graft site and target foreign cells (reviewed in (10)). Alternatively, T cells can be primed with graft-derived peptides... transmissible venereal tumour at different stages of growth. Vet Immunol Immunopathol. 1998;64(2):133-47. 57. Chandler JP, Yang TJ. Canine transmissible venereal sarcoma: distribution of T and B lymphocytes in blood, draining lymph nodes and tumours...

  15. Transmission Workshop | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn'tOriginEducationVideoStrategic|IndustrialCenter Gets PeopleTransmission Workshop Transmission

  16. Downhole Data Transmission System

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David (Lehi, UT); Dahlgren, Scott (Provo, UT); Fox, Joe (Spanish Fork, UT)

    2003-12-30T23:59:59.000Z

    A system for transmitting data through a string of downhole components. In one aspect, the system includes first and second magnetically conductive, electrically insulating elements at both ends of the component. Each element includes a first U-shaped trough with a bottom, first and second sides and an opening between the two sides. Electrically conducting coils are located in each trough. An electrical conductor connects the coils in each component. In operation, a varying current applied to a first coil in one component generates a varying magnetic field in the first magnetically conductive, electrically insulating element, which varying magnetic field is conducted to and thereby produces a varying magnetic field in the second magnetically conductive, electrically insulating element of a connected component, which magnetic field thereby generates a varying electrical current in the second coil in the connected component.

  17. EIS-0447: Champlain Hudson Power Express Transmission Line Project, New York

    Broader source: Energy.gov [DOE]

    This EIS evaluated the potential environmental impacts of a DOE proposal to grant a Presidential permit to Champlain Hudson Power Express, Inc., to construct, operate, maintain, and connect a new 1000-megawatt (MW) electric transmission system across the U.S.-Canada border in northeastern New York State. The proposed transmission line would run from the Canadian Province of Quebec to New York City.

  18. Transmission Design at the National Level: Benefits, Risks and Possible Paths Forward

    E-Print Network [OSTI]

    Independent Transmission System Operator (MISO) #12;ii Executive Summary Today all areas of the contiguous U Initiative White Paper Power Systems Engineering Research Center Empowering Minds to Engineer the Future Electric Energy System #12;Transmission Design at the National Level: Benefits, Risks and Possible Paths

  19. Briefing Memo: Petroleum Product Transmission & Distribution...

    Energy Savers [EERE]

    Briefing Memo: Petroleum Product Transmission & Distribution Briefing Memo: Petroleum Product Transmission & Distribution Click below to download a PDF of the briefing memo....

  20. Agenda: Natural Gas: Transmission, Storage and Distribution ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Natural Gas: Transmission, Storage and Distribution Agenda: Natural Gas: Transmission, Storage and Distribution A Public Meeting on the Quadrennial Energy Review, Hosted by the...

  1. Operations & Maintenance

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations and Maintenance Operations OASIS: OATI (Note: this site is not hosted by Western and requires a digital certificate and login for full access.) Contact Information...

  2. Operations & Maintenance

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Rates Operations & Maintenance Operations OASIS: WACM (Note: this site is not hosted by Western and requires a digital certificate and login for full access.) wesTTrans Common...

  3. EIS-0332: McNary-John Day Transmission Line Project, OR

    Broader source: Energy.gov [DOE]

    This EIS analyzes BPA's decision to construct, operate, and maintain a 79-mile-long 500-kilovolt transmission line in Benton and Klickitat Counties, Washington, and Umatilla and Sherman counties, Oregon.

  4. Cryogenic System for a High Temperature Superconducting Power Transmission Cable

    SciTech Connect (OSTI)

    Demko, J.A.; Gouge, M.J.; Hughey, R.L.; Lue, J.W.; Martin, R.; Sinha, U.; Stovall, J.P.

    1999-07-12T23:59:59.000Z

    High-temperature superconducting (HTS) cable systems for power transmission are under development that will use pressurized liquid nitrogen to provide cooling of the cable and termination hardware. Southwire Company and Oak Ridge National Laboratory have been operating a prototype HTS cable system that contains many of the typical components needed for a commercial power transmission application. It is being used to conduct research in the development of components and systems for eventual commercial deployment. The cryogenic system was built by Air Products and Chemicals, Allentown, Pennsylvania, and can circulate up to 0.35 kg/s of liquid nitrogen at temperatures as low as 67 K at pressures of 1 to 10 bars. Sufficient cooling is provided for testing a 5-m-long HTS transmission cable system that includes the terminations required for room temperature electrical connections. Testing of the 5-m HTS transmission cable has been conducted at the design ac conditions of 1250 A and 7.5 kV line to ground. This paper contains a description of the essential features of the HTS cable cryogenic system and performance results obtained during operation of the system. The salient features of the operation that are important in large commercial HTS cable applications will be discussed.

  5. High speed, long distance, data transmission multiplexing circuit

    DOE Patents [OSTI]

    Mariotti, Razvan (Boulder, CO)

    1991-01-01T23:59:59.000Z

    A high speed serial data transmission multiplexing circuit, which is operable to accurately transmit data over long distances (up to 3 Km), and to multiplex, select and continuously display real time analog signals in a bandwidth from DC to 100 Khz. The circuit is made fault tolerant by use of a programmable flywheel algorithm, which enables the circuit to tolerate one transmission error before losing synchronization of the transmitted frames of data. A method of encoding and framing captured and transmitted data is used which has a low overhead and prevents some particular transmitted data patterns from locking an included detector/decoder circuit.

  6. Low pressure electrospray ionization system and process for effective transmission of ions

    DOE Patents [OSTI]

    Tang, Keqi (Richland, WA); Page, Jason S (Kennewick, WA); Kelly, Ryan T (West Richland, WA); Smith, Richard D (Richland, WA)

    2012-05-08T23:59:59.000Z

    Systems and methods that provide up to complete transmission of ions between coupled stages with low effective ion losses. An "interfaceless" electrospray ionization system is further described that operates an electrospray at a reduced pressure such that standard electrospray sample solutions can be directly sprayed into an electrodynamic ion funnel which provides ion focusing and transmission of ions into a mass analyzer. Furthermore, chambers maintained at different pressures can allow for more optimal operating conditions for an electrospray emitter and an ion guide.

  7. July 2, 2007 1 Optimal Transmission Switching

    E-Print Network [OSTI]

    Mangasarian, Olvi L.

    d to node n. zk: binary variable indicating whether transmission line k is removed from the system limit on number of open transmission lines Manuscript received July 2, 2007. This work was supported-mail: ferris@cs.wisc.edu). Sets : Set of all transmission lines L: Set of open transmission lines in solution

  8. Transmission Lines Emulating Moving Media

    E-Print Network [OSTI]

    Vehmas, Joni; Tretyakov, Sergei

    2014-01-01T23:59:59.000Z

    In this paper, we show how the electromagnetic phenomena in moving magnetodielectric media can be emulated using artificial composite structures at rest. In particular, we introduce nonreciprocal periodically loaded transmission lines which support waves obeying the same rules as plane electromagnetic waves in moving media. Because the actual physical structure is at rest, in these transmission lines there are no fundamental limitations on the velocity values, which may take values larger than the speed of light or even complex values (considering complex amplitudes in the time-harmonic regime). An example circuit of a unit cell of a "moving" transmission line is presented and analyzed both numerically and experimentally. The special case of composite right/left handed host line is also studied numerically. Besides the fundamental interest, the study is relevant for potential applications in realizing engineered materials for various transformations of electromagnetic fields.

  9. Midwest Transmission Workshop III Summary

    SciTech Connect (OSTI)

    Kevin Bryan

    2003-03-12T23:59:59.000Z

    OAK-B135 On March 12-13, 2002, the National Wind Coordinating Committee (NWCC), in cooperation with regional stakeholders, held a two-day workshop: Planning for Electrical Transmission Needs in the Upper Midwest. The workshop was the outgrowth of an effort to develop a forum and process for consideration of transmission options that strives for equitable allocation of benefits and impacts among all affected parties. The goal of this workshop was to provide a catalyst for an enhanced, inclusive process for transmission planning with participation of and acceptance by all affected stakeholders. Participants in the meeting included representatives of state and regional regulatory agencies, utilities and power generators, the wind industry, environmental and landowner interests, and other interested parties (see Attachment A for a list of meeting participants).

  10. ITC Transmission | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdfGetecGtel JumpCounty, Texas:ITC Transmission Jump to: navigation, search Name:

  11. The Centre for Power Transmission

    E-Print Network [OSTI]

    Burton, Geoffrey R.

    The Centre for Power Transmission and Motion Control Centre for PTMC Department of Mechanical) 1225 38-6371 Email: ptmc@bath.ac.uk Web: http://www.bath.ac.uk/ptmc/ Consultancy Project WAVE POWER SYSTEM SIMULATIONS Power take-off systems Wave power take-off systems are an exciting new development

  12. The Centre for Power Transmission

    E-Print Network [OSTI]

    Burton, Geoffrey R.

    precision and high bandwidth motion control In fluid power systems, seals are typically passive elements Bois) PTO #12;5. Modelling and Development of Low Noise Hydraulic Fluid Power Systems Hydraulic fluidThe Centre for Power Transmission and Motion Control The Centre for PTMC: analytical

  13. Development of superconducting transmission cable. CRADA final report

    SciTech Connect (OSTI)

    Hawsey, R.; Stovall, J.P. [Oak Ridge National Lab., TN (United States); Hughey, R.L.; Sinha, U.K. [Southwire Co., Carrollton, GA (United States)

    1997-10-01T23:59:59.000Z

    The purpose of this Cooperative Research and Development Agreement (CRADA) between Oak Ridge National Laboratory (ORNL) and Southwire Company is to develop the technology necessary to proceed to commercialization of high-temperature superconducting (HTS) transmission cables. Power transmission cables are a promising near-term electric utility application for high-temperature superconductivity. Present HTS wires match the needs for a three-phase transmission cable: (1) the wires must conduct high currents in self-field, (2) there are no high forces developed, and (3) the cables may operate at relatively low current density. The commercially-available HTS wires, in 100-m lengths, make construction of a full three-phase, alternating current (ac) transmission cable possible. If completed through the pre-commercialization phase, this project will result in a new capability for electric power companies. The superconducting cable will enable delivery with greater efficiency, higher power density, and lower costs than many alternatives now on the market. Job creation in the US is expected as US manufacturers supply transmission cables to the expanding markets in Asia and to the densely populated European cities where pipe-type cable is prevalent. Finally, superconducting cables may enable delivery of the new, diverse and distributed sources of electricity that will constitute the majority of new installed electrical generation in the world during the coming decades.

  14. EIS-0478: Antelope Valley Station to Neset Transmission Project, Mercer, Dunn, Billings, Williams, McKenzie, and Mountrail Counties, North Dakota

    Broader source: Energy.gov [DOE]

    USDA Rural Utilities Service prepared an EIS that evaluates the potential environmental impacts of constructing, operating, and maintaining a proposed transmission line and associated facilities in western North Dakota. DOE’s Western Area Power Administration, a cooperating agency, would modify its existing Williston Substation to allow a connection of the proposed new transmission line to Western’s transmission system.

  15. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01T23:59:59.000Z

    analysis of the difference in transmission costs for wind andour meta-analysis on the unit cost of transmission for windanalysis of these studies reveals considerable differences in the implied unit cost of transmission for wind.

  16. Instrument Series: Microscopy Environmental Transmission

    E-Print Network [OSTI]

    and spectroscopic studies of materials under dynamic operating conditions. In contrast to traditional operation evaluation such as in situ observation of microstructural evolution during device operation (e.g., a battery, ion, and charge transport in a battery), microstructural evolution, catalytic reactions, nucleation

  17. Reliability modeling and evaluation of HVDC power transmission systems

    SciTech Connect (OSTI)

    Dialynas, E.N.; Koskolos, N.C. (National Technical Univ., Athens (Greece). Dept. of Electrical and Computer Engineering)

    1994-04-01T23:59:59.000Z

    The objective of this paper is to present an improved computational method for evaluating the reliability indices of HVdc transmission systems. The developed models and computational techniques are described. These can be used to simulate the operational practices and characteristics of a system under study efficiently and realistically. This method is based on the failure modes and effects analysis and uses the event tree method and the minimal cut set approach to represent the system's operational behavior and deduce the appropriate system's failure modes. A set of five reliability indices is evaluated for each output node being analyzed together with the probability and frequency of encountering particular regions of system performance levels. The analysis of an assumed HVdc bipolar transmission system is also included.

  18. NREL: Transmission Grid Integration - Transmission Planning and Analysis

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for Renewable Energy: Grid IntegrationReportTransmission Planning and Analysis Thumbnail

  19. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01T23:59:59.000Z

    2007. “Inclusion of Wind in the MISO Transmission Expansionhttp://www.jcspstudy.org/ Midwest ISO (MISO). 2007. Midwest+Planning Midwest ISO (MISO). 2003. Midwest Transmission

  20. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROMof establishing a wind transmission cost adder with respectthat involve wind and divide the cost by the relative share

  1. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    in calculating the unit cost of wind energy transmissionimpacts of the cost of transmission for wind energy. Only inj = Transmission cost per unit of wind energy weighted by

  2. Transmission

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33Frequently AskedEnergyIssuesEnergy SolarRadioactiveITransactional7AMelissa Howell |

  3. Transmission

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of ScienceandMesa del SolStrengthening a solidSynthesisAppliances » Data ManagementTransit

  4. NREL: Transmission Grid Integration - Webinars

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for Renewable Energy: Grid IntegrationReportTransmission Planning and Analysis

  5. NREL: Transmission Grid Integration - Webmaster

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for Renewable Energy: Grid IntegrationReportTransmission Planning and AnalysisWebmaster

  6. Grand Coulee Transmission Line Replacement Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    by the Bureau of Reclamation to design and construct six new 500-kV overhead transmission lines at Grand Coulee Dam. BPA will replace the existing underground transmission...

  7. Scanning Transmission Electron Microscopy for Nanostructure

    E-Print Network [OSTI]

    Pennycook, Steve

    152 6 Scanning Transmission Electron Microscopy for Nanostructure Characterization S. J. Pennycook. Introduction The scanning transmission electron microscope (STEM) is an invaluable tool atom. The STEM works on the same principle as the normal scanning electron microscope (SEM), by forming

  8. Sandia National Laboratories: energy transmission and distribution

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    grid relies on power transmission from the production source-be it a coal-fired plant, solar array, or wind farm-to the consumer. Long-distance transmission results in...

  9. Sandia National Laboratories: transmission grid integration

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    grid relies on power transmission from the production source-be it a coal-fired plant, solar array, or wind farm-to the consumer. Long-distance transmission results in...

  10. Florida Electric Transmission Line Siting Act (Florida)

    Broader source: Energy.gov [DOE]

    The Transmission Line Siting Act (TLSA) is the state’s centralized process for licensing electrical transmission lines which; (a) are 230 kV or larger; (b) cross a county line; and, (c) are 15...

  11. Uncertain Power Flows and Transmission Planning

    E-Print Network [OSTI]

    capability and quantifying transmission revenues under uncertainty. Illustrative analyses demonstrated potential uses in transmission planning. Part I:Stochastic-Algebraic Evaluation of Available Transfer using a deterministic model for a given system state specified by given loads, generation, line

  12. Transmission Issues and Power Exchanges in Texas

    E-Print Network [OSTI]

    Hughes, H. L.

    on the transmission owning utilities by several parties, primary distribution cooperatives, cogenerators, and large industrial customers, to grant wider access to the system. This pressure is coming at a time when transmission lines are becoming increasingly difficult...

  13. Articles about Grid Integration and Transmission

    Broader source: Energy.gov [DOE]

    Stories about grid integration and transmission featured by the U.S. Department of Energy (DOE) Wind Program.

  14. California - Establishing Transmission Project Review Streamlining...

    Open Energy Info (EERE)

    LibraryAdd to library PermittingRegulatory Guidance - Supplemental Material: California - Establishing Transmission Project Review Streamlining DirectivesPermitting...

  15. Discontinuities in transmission lines and wave guides

    E-Print Network [OSTI]

    Mathis, Harold Fletcher

    1952-01-01T23:59:59.000Z

    DISCONTINUITIES IN TRANSMISSION LINES AND WAVEGUIDES H. F. MATHIS DISCONTINUITIES IN TRANSMISSION LINES AND liVAVNGUIDBS A Thesis By Harola Fletcher htathis Approved as to style and content by: Chairman of Committee DISCONTINUITIES... Subject. Electrical Engineering COHERENT S PAGE I Introduct ion, II Dl. scontlnuit les in Transmission Lines 2 1. Some Seneral char aeter 1 st 1 ca of the transmission lines. . . , . . . , ~ 5 2 ~ 2. Types of dlscontlnuitles ln transmls- sl...

  16. Quantifying transmission reliability margin J. Zhang, I. Dobson*, F.L. Alvarado

    E-Print Network [OSTI]

    Dobson, Ian

    , it is likely that the power system will remain secure despite the uncertainty. The transmission reliability uses in electric power system operation and planning. In the operation of bilateral markets, available capability can be used to assess power system security when local power sources are replaced by imported

  17. System for computer controlled shifting of an automatic transmission

    DOE Patents [OSTI]

    Patil, Prabhakar B. (Detroit, MI)

    1989-01-01T23:59:59.000Z

    In an automotive vehicle having an automatic transmission that driveably connects a power source to the driving wheels, a method to control the application of hydraulic pressure to a clutch, whose engagement produces an upshift and whose disengagement produces a downshift, the speed of the power source, and the output torque of the transmission. The transmission output shaft torque and the power source speed are the controlled variables. The commanded power source torque and commanded hydraulic pressure supplied to the clutch are the control variables. A mathematical model is formulated that describes the kinematics and dynamics of the powertrain before, during and after a gear shift. The model represents the operating characteristics of each component and the structural arrangement of the components within the transmission being controlled. Next, a close loop feedback control is developed to determine the proper control law or compensation strategy to achieve an acceptably smooth gear ratio change, one in which the output torque disturbance is kept to a minimum and the duration of the shift is minimized. Then a computer algorithm simulating the shift dynamics employing the mathematical model is used to study the effects of changes in the values of the parameters established from a closed loop control of the clutch hydraulic and the power source torque on the shift quality. This computer simulation is used also to establish possible shift control strategies. The shift strategies determine from the prior step are reduced to an algorithm executed by a computer to control the operation of the power source and the transmission.

  18. Closed loop computer control for an automatic transmission

    DOE Patents [OSTI]

    Patil, Prabhakar B. (Detroit, MI)

    1989-01-01T23:59:59.000Z

    In an automotive vehicle having an automatic transmission that driveably connects a power source to the driving wheels, a method to control the application of hydraulic pressure to a clutch, whose engagement produces an upshift and whose disengagement produces a downshift, the speed of the power source, and the output torque of the transmission. The transmission output shaft torque and the power source speed are the controlled variables. The commanded power source torque and commanded hydraulic pressure supplied to the clutch are the control variables. A mathematical model is formulated that describes the kinematics and dynamics of the powertrain before, during and after a gear shift. The model represents the operating characteristics of each component and the structural arrangement of the components within the transmission being controlled. Next, a close loop feedback control is developed to determine the proper control law or compensation strategy to achieve an acceptably smooth gear ratio change, one in which the output torque disturbance is kept to a minimum and the duration of the shift is minimized. Then a computer algorithm simulating the shift dynamics employing the mathematical model is used to study the effects of changes in the values of the parameters established from a closed loop control of the clutch hydraulic and the power source torque on the shift quality. This computer simulation is used also to establish possible shift control strategies. The shift strategies determined from the prior step are reduced to an algorithm executed by a computer to control the operation of the power source and the transmission.

  19. Method and apparatus for executing an asynchronous clutch-to-clutch shift in a hybrid transmission

    DOE Patents [OSTI]

    Demirovic, Besim; Gupta, Pinaki; Kaminsky, Lawrence A.; Naqvi, Ali K.; Heap, Anthony H.; Sah, Jy-Jen F.

    2014-08-12T23:59:59.000Z

    A hybrid transmission includes first and second electric machines. A method for operating the hybrid transmission in response to a command to execute a shift from an initial continuously variable mode to a target continuously variable mode includes increasing torque of an oncoming clutch associated with operating in the target continuously variable mode and correspondingly decreasing a torque of an off-going clutch associated with operating in the initial continuously variable mode. Upon deactivation of the off-going clutch, torque outputs of the first and second electric machines and the torque of the oncoming clutch are controlled to synchronize the oncoming clutch. Upon synchronization of the oncoming clutch, the torque for the oncoming clutch is increased and the transmission is operated in the target continuously variable mode.

  20. Transmission Dr. Sandra Cruz-Pol

    E-Print Network [OSTI]

    Cruz-Pol, Sandra L.

    Transmission Lines Dr. Sandra Cruz-Pol ECE Dept. UPRM Exercise 11.3 n A 40-m long TL has Vg=15 Vrms to electric circuits! cmc kmc GHz Hz 15000,000,2000/ 000,560/ 2 60 == == Transmission Lines I. TL parameters-wave transformer ¨ Slotted line ¨ Single stub VI. Microstrips Transmission Lines (TL) n TL have two conductors

  1. Smart Grid Application of Optimal Transmission Switching

    E-Print Network [OSTI]

    Ferris, Michael C.

    ;6 Introduction continued Electric Transmission Network Flow Problem Optimal Power Flow (OPF) AlternatingSmart Grid Application of Optimal Transmission Switching By, Kory W. Hedman, et al.* University (Professor, UC Berkeley) #12;2 Motivation Co-optimize transmission topology and generation dispatch

  2. A Distributed System for Cooperative MIMO Transmissions

    E-Print Network [OSTI]

    Kalyanaraman, Shivkumar

    a distributed system for facilitating cooperative MIMO transmissions in networks without multiple antenna diversity can be leveraged at the network, link or physical layers to provide energy efficient transmissions for reliable low-power transmissions. The rest of this paper is organized as follows: the proposed system

  3. > MEPS06 Preprint Version Transmission Loss

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    .phulpin@supelec.fr Abstract - In the deregulated electrical power system, the allocation of transmission losses is becoming a key issue. The electric transmission power system is more and more constrained due to the increasing electrical power system, the allocation of transmission losses is becoming a key issue. The electric

  4. Integrated Transmission and Distribution Control

    SciTech Connect (OSTI)

    Kalsi, Karanjit; Fuller, Jason C.; Tuffner, Francis K.; Lian, Jianming; Zhang, Wei; Marinovici, Laurentiu D.; Fisher, Andrew R.; Chassin, Forrest S.; Hauer, Matthew L.

    2013-01-16T23:59:59.000Z

    Distributed, generation, demand response, distributed storage, smart appliances, electric vehicles and renewable energy resources are expected to play a key part in the transformation of the American power system. Control, coordination and compensation of these smart grid assets are inherently interlinked. Advanced control strategies to warrant large-scale penetration of distributed smart grid assets do not currently exist. While many of the smart grid technologies proposed involve assets being deployed at the distribution level, most of the significant benefits accrue at the transmission level. The development of advanced smart grid simulation tools, such as GridLAB-D, has led to a dramatic improvement in the models of smart grid assets available for design and evaluation of smart grid technology. However, one of the main challenges to quantifying the benefits of smart grid assets at the transmission level is the lack of tools and framework for integrating transmission and distribution technologies into a single simulation environment. Furthermore, given the size and complexity of the distribution system, it is crucial to be able to represent the behavior of distributed smart grid assets using reduced-order controllable models and to analyze their impacts on the bulk power system in terms of stability and reliability. The objectives of the project were to: • Develop a simulation environment for integrating transmission and distribution control, • Construct reduced-order controllable models for smart grid assets at the distribution level, • Design and validate closed-loop control strategies for distributed smart grid assets, and • Demonstrate impact of integrating thousands of smart grid assets under closed-loop control demand response strategies on the transmission system. More specifically, GridLAB-D, a distribution system tool, and PowerWorld, a transmission planning tool, are integrated into a single simulation environment. The integrated environment allows the load flow interactions between the bulk power system and end-use loads to be explicitly modeled. Power system interactions are modeled down to time intervals as short as 1-second. Another practical issue is that the size and complexity of typical distribution systems makes direct integration with transmission models computationally intractable. Hence, the focus of the next main task is to develop reduced-order controllable models for some of the smart grid assets. In particular, HVAC units, which are a type of Thermostatically Controlled Loads (TCLs), are considered. The reduced-order modeling approach can be extended to other smart grid assets, like water heaters, PVs and PHEVs. Closed-loop control strategies are designed for a population of HVAC units under realistic conditions. The proposed load controller is fully responsive and achieves the control objective without sacrificing the end-use performance. Finally, using the T&D simulation platform, the benefits to the bulk power system are demonstrated by controlling smart grid assets under different demand response closed-loop control strategies.

  5. Fact #850: December 8, 2014 Automatic Transmissions have closed...

    Broader source: Energy.gov (indexed) [DOE]

    Historically, manual transmissions have delivered better fuel economy than automatic transmissions. However, improvements in the efficiency of automatic transmissions have closed...

  6. Comments of New England Electric Transmission Corporation on...

    Broader source: Energy.gov (indexed) [DOE]

    out of time and comments of New England Electric Transmission Corporation, New England Hydro-Transmission Electric Company, Inc. and New England Hydro-Transmission Corporation and...

  7. Dynamic Power Flow Controller: Compact Dynamic Phase Angle Regulators for Transmission Power Routing

    SciTech Connect (OSTI)

    None

    2012-01-03T23:59:59.000Z

    GENI Project: Varentec is developing compact, low-cost transmission power controllers with fractional power rating for controlling power flow on transmission networks. The technology will enhance grid operations through improved use of current assets and by dramatically reducing the number of transmission lines that have to be built to meet increasing contributions of renewable energy sources like wind and solar. The proposed transmission controllers would allow for the dynamic control of voltage and power flow, improving the grid’s ability to dispatch power in real time to the places where it is most needed. The controllers would work as fail-safe devices whereby the grid would be restored to its present operating state in the event of a controller malfunction instead of failing outright. The ability to affordably and dynamically control power flow with adequate fail-safe switchgear could open up new competitive energy markets which are not possible under the current regulatory structure and technology base.

  8. The Cost of Transmission for Wind Energy in the United States: A Review of Transmission Planning Studies.

    E-Print Network [OSTI]

    Wiser, Ryan

    2014-01-01T23:59:59.000Z

    on U. S . Wind Power Installation, Cost, and Performance30% wind penetration. Wind transmission costs in the severalof Transmission ($/kW-wind) Unit Cost of Transmission ($/

  9. Transmission grid access and pricing in Norway, Spain, and California: A comparative study

    SciTech Connect (OSTI)

    Gronli, H.; Gomez San Ramon, T.; Marnay, C.

    1999-09-01T23:59:59.000Z

    The openness of the transmission grid and the incentives given by transmission pricing form the foundation for retail and wholesale competition in the electricity market. The deregulated markets of Norway, Spain, and California all have introduced retail access and wholesale competition, although with different approaches to pricing of transmission grid services. This paper will briefly describe the three different solutions, and discuss some of their implications. Of the three electricity systems, Norway was the first to open the grid to competition in electricity trade. The Norwegian Energy Law of 1990 introduced open competition to wholesale and retail trade starting January 1991. In Spain, the Electricity Law of 1997 came into force early in 1998. Wholesale and retail markets in California were opened for competition on April 1, 1998, following the passage of Assembly Bill 1890, in August 1996. Introducing competition in electricity markets also implies introducing Third Party Access to the transmission grid. All potential competitors have to be given access to the grid in order to compete, no matter who owns the actual wires. This principle raises several challenges, notably, how to price transmission services. Who is to pay for which transmission services? The Norwegian grid is divided into three levels depending on its function. The transmission grid includes all parts of the national grid having a transmission function, meaning that some lower voltage levels also are included. In Spain, the definition of the transmission grid is similar, including the 400 kV and 220 kV national grid as well as lower voltage installations that could affect transmission operation or generation dispatch. For historic reasons, wholesale electricity transactions in the US are regulated by the federal government through the FERC. However, operations of utility systems within one state fall primarily under state jurisdiction. Because the utility systems in California generally are large and exchanges between them limited, the role of FERC was small prior to restructuring, although the state is a large importer of power.

  10. Computer controlled synchronous shifting of an automatic transmission

    DOE Patents [OSTI]

    Davis, Roy I. (9214 Abbey La., Ypsilanti, MI 48198); Patil, Prabhakar B. (10294 W. Outer Dr., Detroit, MI 48223)

    1989-01-01T23:59:59.000Z

    A multiple forward speed automatic transmission produces its lowest forward speed ratio when a hydraulic clutch and hydraulic brake are disengaged and a one-way clutch connects a ring gear to the transmission casing. Second forward speed ratio results when the hydraulic clutch is engaged to connect the ring gear to the planetary carrier of a second gear set. Reverse drive and regenerative operation result when an hydraulic brake fixes the planetary and the direction of power flow is reversed. Various sensors produce signals representing the torque at the output of the transmission or drive wheels, the speed of the power source, and the hydraulic pressure applied to a clutch and brake. A control algorithm produces input data representing a commanded upshift, a commanded downshift, a commanded transmission output torque, and commanded power source speed. A microprocessor processes the inputs and produces a response to them in accordance with the execution of a control algorithm. Output or response signals cause selective engagement and disengagement of the clutch and brake at a rate that satisfies the requirements for a short gear ratio change and smooth torque transfer between the friction elements.

  11. Computer controllable synchronous shifting of an automatic transmission

    DOE Patents [OSTI]

    Davis, R.I.; Patil, P.B.

    1989-08-08T23:59:59.000Z

    A multiple forward speed automatic transmission produces its lowest forward speed ratio when a hydraulic clutch and hydraulic brake are disengaged and a one-way clutch connects a ring gear to the transmission casing. Second forward speed ratio results when the hydraulic clutch is engaged to connect the ring gear to the planetary carrier of a second gear set. Reverse drive and regenerative operation result when an hydraulic brake fixes the planetary and the direction of power flow is reversed. Various sensors produce signals representing the torque at the output of the transmission or drive wheels, the speed of the power source, and the hydraulic pressure applied to a clutch and brake. A control algorithm produces input data representing a commanded upshift, a commanded downshift, a commanded transmission output torque, and commanded power source speed. A microprocessor processes the inputs and produces a response to them in accordance with the execution of a control algorithm. Output or response signals cause selective engagement and disengagement of the clutch and brake at a rate that satisfies the requirements for a short gear ratio change and smooth torque transfer between the friction elements. 6 figs.

  12. Pulse shaping with transmission lines

    DOE Patents [OSTI]

    Wilcox, Russell B. (Oakland, CA)

    1987-01-01T23:59:59.000Z

    A method and apparatus for forming shaped voltage pulses uses passive reflection from a transmission line with nonuniform impedance. The impedance of the reflecting line varies with length in accordance with the desired pulse shape. A high voltage input pulse is transmitted to the reflecting line. A reflected pulse is produced having the desired shape and is transmitted by pulse removal means to a load. Light activated photoconductive switches made of silicon can be utilized. The pulse shaper can be used to drive a Pockels cell to produce shaped optical pulses.

  13. Pulse shaping with transmission lines

    DOE Patents [OSTI]

    Wilcox, R.B.

    1985-08-15T23:59:59.000Z

    A method and apparatus for forming shaped voltage pulses uses passive reflection from a transmission line with nonuniform impedance. The impedance of the reflecting line varies with length in accordance with the desired pulse shape. A high voltage input pulse is transmitted to the reflecting line. A reflected pulse is produced having the desired shape and is transmitted by pulse removal means to a load. Light activated photoconductive switches made of silicon can be utilized. The pulse shaper can be used to drive a Pockels cell to produce shaped optical pulses.

  14. Sandia Energy - Transmission Grid Integration

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of ScienceandMesa del Sol Home Distribution GridDocumentsInstituteThree-DimensionalTransmission Grid

  15. Scanning/Transmission Electron Microscopes

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOnItemResearch > TheNuclearHomeland andEffectsScanning/Transmission Electron Microscopes

  16. Transmission Workshop | Department of Energy

    Energy Savers [EERE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnual Siteof Energy 2, 2015 - JanuaryTankToledo, Ohio,Transmission

  17. Property:EIA/861/RtoPjm | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to: navigation,PillarPublicationType JumpDOEInvolve

  18. Dr. Kelli Joseph, NYISO Representing the ISO-RTO Council

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy China U.S.ContaminationJuly 2011 U.S. DEPARTMENTAssociateExtractedDecember 20,

  19. History of wireless power transmission

    SciTech Connect (OSTI)

    Brown, W.C. [Microwave Power Transmission Systems, Weston, MA (United States)] [Microwave Power Transmission Systems, Weston, MA (United States)

    1996-12-31T23:59:59.000Z

    The history of wireless power transmission at microwave frequencies is reviewed with emphasis upon the time period starting with the post World War II efforts to use the new microwave technology developed during the war. A nationally televised demonstration of a microwave powered helicopter at the Spencer Laboratory of the Raytheon Co., in 1964 was the result of these early efforts and broadly introduced the concept of wireless power transmission to scientific and engineering communities and to the public. Subsequent development efforts centered on improving the efficiency of the interconversion of d.c. and microwave power at the ends of the system to reach a demonstrated overall d.c. to d.c. system efficiency of 54% in 1974. The response to the requirements of applications such as the Solar Power Satellite and high altitude microwave powered aircraft have changed the direction of technology development and greatly expanded the technology base. Recent and current efforts are centered on examining the use of higher frequencies than the baseline 2.45 GHz, and in reducing the system costs at 2.45 GHz. 26 refs., 14 figs.

  20. Operating Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    This chapter is focused on capital costs for conventional construction and environmental restoration and waste management projects and examines operating cost estimates to verify that all elements of the project have been considered and properly estimated.

  1. The integration of renewable energy sources into electric power transmission systems

    SciTech Connect (OSTI)

    Barnes, P.R.; Dykas, W.P.; Kirby, B.J.; Purucker, S.L. [Oak Ridge National Lab., TN (United States); Lawler, J.S. [Univ. of Tennessee, Knoxville, TN (United States)

    1995-07-01T23:59:59.000Z

    Renewable energy technologies such as photovoltaics, solar thermal power plants, and wind turbines are nonconventional, environmentally attractive sources of energy that can be considered for electric power generation. Many of the areas with abundant renewable energy resources (very sunny or windy areas) are far removed from major load centers. Although electrical power can be transmitted over long distances of many hundreds of miles through high-voltage transmission lines, power transmission systems often operate near their limits with little excess capacity for new generation sources. This study assesses the available capacity of transmission systems in designated abundant renewable energy resource regions and identifies the requirements for high-capacity plant integration in selected cases. In general, about 50 MW of power from renewable sources can be integrated into existing transmission systems to supply local loads without transmission upgrades beyond the construction of a substation to connect to the grid. Except in the Southwest, significant investment to strengthen transmission systems will be required to support the development of high-capacity renewable sources of 1000 MW or greater in areas remote from major load centers. Cost estimates for new transmission facilities to integrate and dispatch some of these high-capacity renewable sources ranged from several million dollars to approximately one billion dollars, with the latter figure an increase in total investment of 35%, assuming that the renewable source is the only user of the transmission facility.

  2. A Multiple Access Protocol for Multimedia Transmission over Wireless Networks

    E-Print Network [OSTI]

    Yu, Hong

    2012-01-01T23:59:59.000Z

    This paper develops and evaluates the performance of an advanced multiple access protocol for transmission of full complement of multimedia signals consisting of various combinations of voice, video, data, text and images over wireless networks. The protocol is called Advanced Multiple Access Protocol for Multimedia Transmission (AMAPMT) and is to be used in the Data Link Layer of the protocol stack. The principle of operation of the protocol is presented in a number of logical flow charts. The protocol grants permission to transmit to a source on the basis of a priority scheme that takes into account a time-to-live (TTL) parameter of all the transactions, selectable priorities assigned to all the sources and relevant channel state information (CSI) in this order. Performance of the protocol is evaluated in terms of quality of service parameters like packet loss ratio (PLR), mean packet transfer delay (MPTD) and throughput. Using a simulation model based on an OPNET simulation software package does the evalua...

  3. Fast neutron transmission spectroscopy for illicit substance detection

    SciTech Connect (OSTI)

    Yule, T.J.; Micklich, B.J.; Fink, C.L.; Sagalovsky, L.

    1996-05-01T23:59:59.000Z

    Fast Neutron Transmission Spectroscopy (FNTS) is being investigated for detecting explosives in luggage and other small containers. It uses an accelerator to generate nanosecond-pulsed neutron beams that strike a target, producing a white source of neutrons. Elemental distributions along projections through the interrogated object are obtained by analyzing neutron transmission data. Tomographic reconstruction is used to determine the spatial variations of individual elemental densities. Elemental densities are combined in a detection algorithm that indicates presence or absence of explosives. The elemental unfolding and tomographic reconstruction algorithms have been validated by application to experimental data. System studies have been performed to study the operational characteristics and limitations of a FNTS system, and to determine the system`s sensitivity to several important parameters such as flight path length and position of the interrogated object.

  4. A test of a 2 Tesla superconducting transmission line magnet system

    SciTech Connect (OSTI)

    Piekarz, Henryk; Carcagno, Ruben; Claypool, Brad; Foster, George W.; Hays, Steven L.; Huang, Yuenian; Kashikhin, Vladimir; Malamud, Ernest; Mazur, Peter O.; Nehring,; Oleck, Andrew; Rabehl, Roger; Schlabach, Phil; Sylvester, Cosmore; Velev, Gueorgui; Volk, James; /Fermilab; Wake, Masayoshi; /KEK, Tsukuba

    2005-09-01T23:59:59.000Z

    Superconducting transmission line magnet test system for an injector accelerator of a staged VLHC proton-proton colliding beam accelerator has been built and operated at Fermilab. The 1.5 m long, twin-aperture, combined function dipole magnet of 2 Tesla field is excited by a single turn 100 kA transmission line superconductor. The 100 kA dc current is generated using dc-dc switching converters powered by a bulk 240 kW supply. A pair of horizontally placed conventional leads facilitates transfer of this current to the magnet transmission line superconductor operating at liquid helium temperature. Fabrication of magnet components and magnet assembly work are described. The magnet test system and its operation are presented, and the performance is summarized.

  5. The Reliability Investigation on ACSR Splice Connector Systems Used in Overhead Power transmission Lines

    SciTech Connect (OSTI)

    Wang, Jy-An John [ORNL] [ORNL; Jiang, Hao [ORNL] [ORNL; Ren, Fei [ORNL] [ORNL

    2012-01-01T23:59:59.000Z

    Due to material discontinuity and inherited forming mechanism from a crimped-type splice connector, the associated conductor-connector system is highly sensitive to system components aging, especially during high-temperature operations. Furthermore, due to the increase in power demand and limited investment in new infrastructure, existing overhead power transmission lines often need to operate at temperatures higher than the original designed values. This has led to the accelerated aging and degradation of conductor-connector systems. The implications of connector aging are two-fold: (1) significant increase in resistivity of the splice connector and (2) significant reduction in the connector clamping strength. Therefore, splice connectors are one of the weakest links in the electric power transmission infrastructure. In this paper we will discuss the reliability of splice connector systems, including both single stage and two stage splice connectors, used in ACSR conductor of transmission lines under high temperature operations.

  6. Microstrip transmission line tapers on ferrites

    SciTech Connect (OSTI)

    Albuquerque, M.R.; dAssuncao, A.G.; Lima, F. [Departamento de Engenharia Eletrica, Universidade Federal do Rio Grande do Norte, 59072-970 Natal, RN (Brazil)] [Departamento de Engenharia Eletrica, Universidade Federal do Rio Grande do Norte, 59072-970 Natal, RN (Brazil)

    1997-04-01T23:59:59.000Z

    The spectral domain approach is employed to perform a theoretical investigation of tapered microstrip lines on magnetized ferrite substrates. A linear variation of the conducting strip width along the direction of propagation is considered. The analysis takes into account the effects of the applied dc magnetic bias field in the transmission characteristics of these structures. The properties of the taper are determined by a model based on a segmentation of the considered line into uniform microstrip line subsections. Normalized phase constants and characteristic impedances are obtained by using the Hertz vector potentials method and Galerkin numerical technique. Numerical results are presented to show the taper input parameters as a function of the load impedance, geometrical dimensions, operating frequency, and ferrite parameters, considering the orientation and magnitude changes of the biasing magnetic-field {bold H}{sub 0}. The results agree fairly well with those available in the literature for tapered microstrip lines on isotropic dielectric substrates. {copyright} {ital 1997 American Institute of Physics.}

  7. AC Losses of Prototype HTS Transmission Cables

    SciTech Connect (OSTI)

    Demko, J.A.; Dresner, L.; Hughey, R.L.; Lue, J.W.; Olsen, S.K.; Sinha, U.; Tolbert, J.C.

    1998-09-13T23:59:59.000Z

    Since 1995 Southwire Company and Oak Ridge National Laboratory (ORNL) have jointly designed, built, and tested nine, l-m long, high temperature superconducting (HTS) transmission cable prototypes. This paper summarizes the AC loss measurements of five of the cables not reported elsewhere, and compares the losses with each other and with theory developed by Dresner. Losses were measured with both a calorimetric and an electrical technique. Because of the broad resistive transition of the HTS tapes, the cables can be operated stably beyond their critical currents. The AC losses were measured in this region as well as below critical currents. Dresner's theory takes into account the broad resistive transition of the HTS tapes and calculates the AC losses both below and above the critical current. The two sets of AC 10SS data agree with each other and with the theory quite welL In particular, at low currents of incomplete penetration, the loss data agree with the theoretical prediction of hysteresis loss based on only the outer two Iayers carrying the total current.

  8. Magnetically insulated transmission line oscillator

    DOE Patents [OSTI]

    Bacon, Larry D. (Albuquerque, NM); Ballard, William P. (Albuquerque, NM); Clark, M. Collins (Albuquerque, NM); Marder, Barry M. (Albuquerque, NM)

    1988-01-01T23:59:59.000Z

    A magnetically insulated transmission line oscillator employs self-generated magnetic fields to generate microwave energy. An anode of the oscillator includes slow-wave structures which are formed of a plurality of thin conductive vanes defining cavities therebetween, and a gap is formed between the anode and a cathode of the oscillator. In response to a pulsed voltage applied to the anode and cathode, self-generated magnetic fields arfe produced in a cross-field orientation with respect to the orientation of the electric field between the anode and the cathode. The cross-field magnetic fields insulate the flow of electrons in the gap and confine the flow of electrons within the gap.

  9. Superconducting transmission line particle detector

    DOE Patents [OSTI]

    Gray, Kenneth E. (Naperville, IL)

    1989-01-01T23:59:59.000Z

    A microvertex particle detector for use in a high energy physic collider including a plurality of parallel superconducting thin film strips separated from a superconducting ground plane by an insulating layer to form a plurality of superconducting waveguides. The microvertex particle detector indicates passage of a charged subatomic particle by measuring a voltage pulse measured across a superconducting waveguide caused by the transition of the superconducting thin film strip from a superconducting to a non-superconducting state in response to the passage of a charged particle. A plurality of superconducting thin film strips in two orthogonal planes plus the slow electromagnetic wave propogating in a superconducting transmission line are used to resolve N.sup.2 ambiguity of charged particle events.

  10. Superconducting transmission line particle detector

    DOE Patents [OSTI]

    Gray, K.E.

    1988-07-28T23:59:59.000Z

    A microvertex particle detector for use in a high energy physic collider including a plurality of parallel superconducting thin film strips separated from a superconducting ground plane by an insulating layer to form a plurality of superconducting waveguides. The microvertex particle detector indicates passage of a charged subatomic particle by measuring a voltage pulse measured across a superconducting waveguide caused by the transition of the superconducting thin film strip from a superconducting to a non- superconducting state in response to the passage of a charged particle. A plurality of superconducting thin film strips in two orthogonal planes plus the slow electromagnetic wave propagating in a superconducting transmission line are used to resolve N/sup 2/ ambiguity of charged particle events. 6 figs.

  11. Transmission Expansion Planning Using an AC Model ...

    E-Print Network [OSTI]

    Periodicals

    2013-01-02T23:59:59.000Z

    Western Interconnection” under contract DOE-FOA0000068. ... problem to determine locations for placing new transmission ... KNITRO and BONMIN are de

  12. Exploring the Business Link Opportunity: Transmission & Clean...

    Energy Savers [EERE]

    Jennifer Weddle, Greenberg Traurig LLP Rapid Response Team for Transmission: Laura Smith Morton, DOE Energy Storage: Michael Stosser, Day Pitney LLP Centennial West Clean...

  13. In Situ Electrochemical Transmission Electron Microscopy for...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    for Battery Research. Abstract: The recent development of in situ liquid stages for (scanning) transmission electron microscopes now makes it possible for us to study the details...

  14. Sandia National Laboratories: Transmission Grid Integration

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Transmission Grid Integration Wind Generator Modeling On June 26, 2014, in Computational Modeling & Simulation, Energy, Energy Surety, Grid Integration, Infrastructure Security,...

  15. Natural Gas Transmission Pipeline Siting Act (Florida)

    Broader source: Energy.gov [DOE]

    This Act establishes a centralized and coordinated permitting process for the location of natural gas transmission pipeline corridors and the construction and maintenance of natural gas...

  16. Natural Gas Transmission and Distribution Module This

    Annual Energy Outlook 2013 [U.S. Energy Information Administration (EIA)]

    They relate to (1) structural components of the model, (2) capacity expansion and pricing of transmission and distribution services, (3) Arctic pipelines, and (4) imports...

  17. Natural Gas Transmission and Distribution Module

    Annual Energy Outlook 2013 [U.S. Energy Information Administration (EIA)]

    They relate to (1) structural components of the model, (2) capacity expansion and pricing of transmission and distribution services, (3) Arctic pipelines, and (4) imports...

  18. Proponent's Environmental Assessment (PEA) Checklist for Transmission...

    Open Energy Info (EERE)

    Proponent's Environmental Assessment (PEA) Checklist for Transmission Line and Substation Projects Jump to: navigation, search OpenEI Reference LibraryAdd to library Permitting...

  19. Transmission Reassignment Reporting Requirement - April 2, 2014

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    CommitteesTeams Customer Training Interconnection Notices Rates Standards of Conduct Tariff TF Web Based Training Transmission Reassignment Reporting Requirement This notice...

  20. 2006 National Electric Transmission Congestion Study Federal...

    Office of Environmental Management (EM)

    Comments to the Feb 06 FRN received after March 9, 2006 More Documents & Publications Proceedings of the March 29, 2006 Conference for the 2006 National Electric Transmission...

  1. Coordinating Interstate Electric Transmission Siting: An Introduction...

    Open Energy Info (EERE)

    the near future. While improved demand-side management (including energy effi ciency and demand response), bett er utilization of the existing transmission grid, and other...

  2. Flexible Transmission in the Smart Grid

    E-Print Network [OSTI]

    Hedman, Kory Walter

    2010-01-01T23:59:59.000Z

    New England Outlook: Smart Grid is About Consumers,” Apr. [Transmission in the Smart Grid By Kory Walter Hedman ATransmission in the Smart Grid by Kory Walter Hedman Doctor

  3. Detonator comprising a nonlinear transmission line

    DOE Patents [OSTI]

    Elizondo-Decanini, Juan M

    2014-12-30T23:59:59.000Z

    Detonators are described herein. In a general embodiment, the detonator includes a nonlinear transmission line that has a variable capacitance. Capacitance of the nonlinear transmission line is a function of voltage on the nonlinear transmission line. The nonlinear transmission line receives a voltage pulse from a voltage source and compresses the voltage pulse to generate a trigger signal. Compressing the voltage pulse includes increasing amplitude of the voltage pulse and decreasing length of the voltage pulse in time. An igniter receives the trigger signal and detonates an explosive responsive to receipt of the trigger signal.

  4. Operations Videos

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)IntegratedSpeeding access toTest and EvaluationOperational ManagementCenterOperations

  5. Control system and method for a power delivery system having a continuously variable ratio transmission

    DOE Patents [OSTI]

    Frank, A.A.

    1984-07-10T23:59:59.000Z

    A control system and method for a power delivery system, such as in an automotive vehicle, having an engine coupled to a continuously variable ratio transmission (CVT). Totally independent control of engine and transmission enable the engine to precisely follow a desired operating characteristic, such as the ideal operating line for minimum fuel consumption. CVT ratio is controlled as a function of commanded power or torque and measured load, while engine fuel requirements (e.g., throttle position) are strictly a function of measured engine speed. Fuel requirements are therefore precisely adjusted in accordance with the ideal characteristic for any load placed on the engine. 4 figs.

  6. Control system and method for a power delivery system having a continuously variable ratio transmission

    DOE Patents [OSTI]

    Frank, Andrew A. (1034 Hillside Ave., Madison, WI 53705)

    1984-01-01T23:59:59.000Z

    A control system and method for a power delivery system, such as in an automotive vehicle, having an engine coupled to a continuously variable ratio transmission (CVT). Totally independent control of engine and transmission enable the engine to precisely follow a desired operating characteristic, such as the ideal operating line for minimum fuel consumption. CVT ratio is controlled as a function of commanded power or torque and measured load, while engine fuel requirements (e.g., throttle position) are strictly a function of measured engine speed. Fuel requirements are therefore precisely adjusted in accordance with the ideal characteristic for any load placed on the engine.

  7. Doubly Fed Induction Generator in an Offshore Wind Power Plant Operated at Rated V/Hz: Preprint

    SciTech Connect (OSTI)

    Muljadi, E.; Singh, M.; Gevorgian, V.

    2012-06-01T23:59:59.000Z

    This paper introduces the concept of constant Volt/Hz operation of offshore wind power plants. The deployment of offshore WPPs requires power transmission from the plant to the load center inland. Since this power transmission requires submarine cables, there is a need to use High-Voltage Direct Current transmission, which is economical for transmission distances longer than 50 kilometers. In the concept presented here, the onshore substation is operated at 60 Hz synced with the grid, and the offshore substation is operated at variable frequency and voltage, thus allowing the WPP to be operated at constant Volt/Hz.

  8. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01T23:59:59.000Z

    on U.S. Wind Power Installation, Cost, and PerformanceTransmission ($/kW-wind) Unit Cost (Capacity-weighted) Windof Transmission ($/MWh- wind) Unit Cost (Capacity-weighted)

  9. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01T23:59:59.000Z

    2006. Transmission and Wind Energy: Capturing the Prevailingand Renewable Energy (Wind & Hydropower Technologiesand Renewable Energy Wind & Hydropower Technologies Program

  10. International 345 kV transmission line to Highgate, Vermont: environmental assessment

    SciTech Connect (OSTI)

    Not Available

    1985-02-01T23:59:59.000Z

    The action under consideration is the issuance of a Presidential permit to the Vermont Electric Power Company, Inc. (VELCO) for the construction, operation, maintenance and connection of a facility that will cross the United States-Canada border for international transmission of electric energy. The proposed transmission facilities will consist of a 7.5 mile, alternating current (ac) transmission line and a 200 MW back-to-back direct current (dc) converter terminal station. None of the facilities will involve any polluting emissions. The construction and maintenance of the proposed converter terminal station and transmission facilities will have little or no impact on the geologic features of the region. The transmission line will have little or no effect on agricultural land. Impacts on commercial forestry in the area will be minimal. The proposed route will require clearing about 36 acres of forest. The proposed transmission line and converter terminal site will have no effect on recreational activities, mining activites, residential, commercial, or industrial land use. The proposed corridor will have a minimal impact on area terrestrial wildlife and plant communities. The proposed project will have little or no impact on future population distribution, the operation of local services, employment and economic benefit, or housing in either Franklin or Highgate. 16 references, 3 figures. (ACR)

  11. Probabilistic Reliable Message Transmission Subodh Kumar

    E-Print Network [OSTI]

    North Carolina at Chapel Hill, University of

    Probabilistic Reliable Message Transmission Subodh Kumar January 17, 1996 Abstract Most communication systems require reliable transmission of a sequence of messages over a physical network which can with messages by the sender and they are acknowledged by the receiver. It is known that protocols that use

  12. Empirical Analysis of Transmission Power Control Algorithms

    E-Print Network [OSTI]

    Culler, David E.

    Empirical Analysis of Transmission Power Control Algorithms for Wireless Sensor Networks Jaein · Power saving techniques in WSN ­ Duty-cycling, TX-power control, clustering ­ We study effect of TX-power transmission. End-to-end delivery rate TX Power Control Best of Fixed TX Power El Batt [1] 36.5% 35.5% PCBL [6

  13. A Transmission Control Framework Continuous Media

    E-Print Network [OSTI]

    Whitton, Mary C.

    Rights Reserved #12;ABSTRACT A Transmission Control Framework for Continuous Media (Under the directionA Transmission Control Framework for Continuous Media by Terry Michael Talley A dissertation by integrating real-time two-way audio and video with the computer system. Unfortunately, the quality of video

  14. Operation Poorman

    SciTech Connect (OSTI)

    Pruvost, N.; Tsitouras, J.

    1981-03-18T23:59:59.000Z

    The objectives of Operation Poorman were to design and build a portable seismic system and to set up and use this system in a cold-weather environment. The equipment design uses current technology to achieve a low-power, lightweight system that is configured into three modules. The system was deployed in Alaska during wintertime, and the results provide a basis for specifying a mission-ready seismic verification system.

  15. Operating Strategies

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for RenewableSpeeding accessSpeedingOctoberResearchOpen→ globalOPERATING PLAN

  16. Operations Office

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for RenewableSpeeding accessSpeedingOctoberResearchOpen→ globalOPERATING

  17. Low cost Image Transmission System

    SciTech Connect (OSTI)

    Skogmo, D.

    1994-06-01T23:59:59.000Z

    Throughout the Department of Energy (DOE) complex, sites protect themselves with intrusion detection systems. Some of these systems have sensors in remote areas. These sensors frequently alarm -- not because they have detected a terrorist skulking around the area, but because they have detected a horse, or a dog, or a bush moving in the breeze. Even though the local security force is 99% sure there is no real threat, they must assess each of these nuisance or false alarms. Generally, the procedure consists of dispatching an inspector to drive to the area and make an assessment. This is expensive in terms of manpower and the assessment is not timely. Often, by the time the inspector arrives, the cause of the alarm has vanished. A television camera placed to view the area protected by the sensor could be used to help in this assessment, but this requires the installation of high-quality cable, optical fiber, or a microwave link. Further, to be of use at the present time, the site must have had the foresight to have installed these facilities in the past and have them ready for use now. What is needed is a device to place between the television camera and a modem connecting to a low-bandwidth channel such as radio or a telephone line. This paper discusses the development of such a device: an Image Transmission System, or ITS.

  18. Development of the IMPACS materials management system at Tennessee Gas Transmission

    SciTech Connect (OSTI)

    Danko, W.A.; Owen, R.J.

    1985-08-01T23:59:59.000Z

    Tennessee Gas Transmission is one of the largest natural-gas-transmission companies in the world. Its revenues in 1983 exceeded $4 billion, and it employs approximately 3600 people. TGT was incorporated as the Tennessee Gas and Transmission Company in 1943. It has several subsidiaries including Midwestern Gas Transmission, East Tennessee Natural Gas, Channel Industries, and Tenngasco. TGT is also the original corporation from which the Tenneco, Inc., group of companies emerged. In this issue this article deals with the materials management function at TGT. More specifically, it elaborates on TGT's new fully integrated materials management system, IMPACS. The article details the need for a new system, the implementation of the system, the benefits derived from the system, and the operation of the system. 4 figures.

  19. Transmission Line Jobs and Economic Development Impact (JEDI) Model User Reference Guide

    SciTech Connect (OSTI)

    Goldberg, M.; Keyser, D.

    2013-10-01T23:59:59.000Z

    The Jobs and Economic Development Impact (JEDI) models, developed through the National Renewable Energy Laboratory (NREL), are freely available, user-friendly tools that estimate the potential economic impacts of constructing and operating power generation projects for a range of conventional and renewable energy technologies. The Transmission Line JEDI model can be used to field questions about the economic impacts of transmission lines in a given state, region, or local community. This Transmission Line JEDI User Reference Guide was developed to provide basic instruction on operating the model and understanding the results. This guide also provides information on the model's underlying methodology, as well as the parameters and references used to develop the cost data contained in the model.

  20. Conductive Channel for Energy Transmission

    SciTech Connect (OSTI)

    Apollonov, Victor V. [A.M. Prokhorov General Physics Institute, Vavilov Str. 38, Moscow, 119991 (Russian Federation)

    2011-11-10T23:59:59.000Z

    For many years the attempts to create conductive channels of big length were taken in order to study the upper atmosphere and to settle special tasks, related to energy transmission. There upon the program of creation of 'Impulsar' represents a great interest, as this program in a combination with high-voltage high repetition rate electrical source can be useful to solve the above mentioned problems (N. Tesla ideas for the days of high power lasers). The principle of conductive channel production can be shortly described as follows. The 'Impulsar' - laser jet engine vehicle - propulsion take place under the influence of powerful high repetition rate pulse-periodic laser radiation. In the experiments the CO{sub 2}-laser and solid state Nd:YAG laser systems had been used. Active impulse appears thanks to air breakdown (<30 km) or to the breakdown of ablated material on the board (>30 km), placed in the vicinity of the focusing mirror-acceptor of the breakdown waves. With each pulse of powerful laser the device rises up, leaving a bright and dense trace of products with high degree of ionization and metallization by conductive nano-particles due to ablation. Conductive dust plasma properties investigation in our experiments was produced by two very effective approaches: high power laser controlled ablation and by explosion of wire. Experimental and theoretical results of conductive canal modeling will be presented. The estimations show that with already experimentally demonstrated figures of specific thrust impulse the lower layers of the Ionosphere can be reached in several ten seconds that is enough to keep the high level of channel conductivity and stability with the help of high repetition rate high voltage generator. Some possible applications for new technology are highlighted.

  1. Operational Excellence

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOnItemResearch > TheNuclear Astrophysics One ofSpeedingthis site » OpenOperational

  2. Operations Information

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for RenewableSpeeding accessSpeedingOctoberResearchOpen→ globalOPERATING Who We

  3. Traction drive automatic transmission for gas turbine engine driveline

    DOE Patents [OSTI]

    Carriere, Donald L. (Livonia, MI)

    1984-01-01T23:59:59.000Z

    A transaxle driveline for a wheeled vehicle has a high speed turbine engine and a torque splitting gearset that includes a traction drive unit and a torque converter on a common axis transversely arranged with respect to the longitudinal centerline of the vehicle. The drive wheels of the vehicle are mounted on a shaft parallel to the turbine shaft and carry a final drive gearset for driving the axle shafts. A second embodiment of the final drive gearing produces an overdrive ratio between the output of the first gearset and the axle shafts. A continuously variable range of speed ratios is produced by varying the position of the drive rollers of the traction unit. After starting the vehicle from rest, the transmission is set for operation in the high speed range by engaging a first lockup clutch that joins the torque converter impeller to the turbine for operation as a hydraulic coupling.

  4. Superconducting magnetic energy storage for BPA transmission-line stabilization

    SciTech Connect (OSTI)

    Rogers, J.D.; Barron, M.H.; Boenig, H.J.; Criscuolo, A.L.; Dean, J.W.; Schermer, R.I.

    1982-01-01T23:59:59.000Z

    The Bonneville Power Administration (BPA) operates the electrical transmission system that joins the Pacific Northwest with southern California. A 30 MJ (8.4 kWh) Superconducting Magnetic Energy Storage (SMES) unit with a 10 MW converter is being installed at the Tacoma Substation to provide system damping for low frequency oscillations of 0.35 Hz. The integrated system status is described and reviewed. Components included in the system are the superconducting coil, seismically mounted in an epoxy fiberglass nonconducting dewar; a helium refrigerator; a heat rejection subsystem; a high pressure gas recovery subsystem; a liquid nitrogen trailer; the converter with power transformers and switchgear; and a computer system for remote microwave link operation of the SMES unit.

  5. IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 15, NO. 3, AUGUST 2000 909 Transmission Loss Compensation in Multiple

    E-Print Network [OSTI]

    Gross, George

    an independent grid operator (IGO) whose mission is to facilitate access to the grid and ensure comparableIEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 15, NO. 3, AUGUST 2000 909 Transmission Loss Compensation(es) or to purchase the loss compensation service from a central in- dependent grid operator (IGO). The IGO can

  6. EA-1972: Electric District 2 to Saguaro No. 2 Transmission Line Rebuild, Pinal County, Arizona

    Broader source: Energy.gov [DOE]

    Western Area Power Administration issued a Draft EA that assesses the potential environmental impacts of the proposed rebuild of a 35.6-mile transmission line that Western operates and maintains under an agreement with the Central Arizona Project. Additional information is available on the project website, http://www.wapa.gov/dsw/environment/ED2DOEEA1972.htm.

  7. A Supply Chain Network Perspective for Electric Power Generation, Supply, Transmission, and Consumption

    E-Print Network [OSTI]

    Nagurney, Anna

    A Supply Chain Network Perspective for Electric Power Generation, Supply, Transmission, and Consumption Anna Nagurney and Dmytro Matsypura Department of Finance and Operations Management Isenberg School, Berlin, Germany, pp. 3-27. Abstract: A supply chain network perspective for electric power production

  8. Flashover vulnerability of transmission and distribution lines to high-altitude electromagnetic pulse

    SciTech Connect (OSTI)

    Kruse, V.J. (Westinghouse Electric Corp., Pittsburgh, PA (USA). Advanced Systems Technology Div.); Tesche, F.M. (E-Systems, Inc., Greenville, TX (USA)); Liu, T.K. (Lutech, Inc., Oakland, CA (US)); Barnes, P.R. (Oak Ridge National Lab., TN (USA))

    1990-04-01T23:59:59.000Z

    This paper estimates the vulnerability of transmission and distribution lines to flashover from the electromagnetic pulse generated by a nuclear detonation 400 kilometers above the earth. The analysis consists of first determining the cumulative probability of induced-voltage on three-phase lines, including shield and neutral conductors, for four operating voltages and then comparing these stresses to estimates of line insulation strength.

  9. EIS-0141: Washington Water Power/B.C. Hydro Transmission Interconnection Project

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy developed this statement to evaluate the environmental impacts of constructing and operating a double-circuit 230-kilovolt electrical transmission line that would link the electrical systems of the Washington Water Power Company and the British Columbia Hydro and Power Authority.

  10. EIS-0103: New England/Hydro-Quebec 450-kV Direct Current Transmission Line Interconnection

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration prepared this statement to evaluate the environmental impacts of the construction, maintenance and operation of a 57-mile transmission line from Monroe, New Hampshire, to the U.S./Canadian border for the purpose of economic exchange of power and increased reliability.

  11. EIS-0129: New England/Hydro-Quebec 450 kV Transmission Line Interconnection- Phase II

    Broader source: Energy.gov [DOE]

    The Economic Regulatory Administration issued this EIS to explore the impacts of amending Presidential Permit PP-76 to allow the Vermont Electrical Company to operate at power levels above those stipulated in the permit and to build additional transmission facilities to distribute the increased power.

  12. MATHEMATICAL ANALYSIS OF CONDUCTING AND SUPERCONDUCTING TRANSMISSION LINES

    E-Print Network [OSTI]

    Ramdani, Karim - Institut de Mathématiques �lie Cartan, Université Henri Poincaré

    MATHEMATICAL ANALYSIS OF CONDUCTING AND SUPERCONDUCTING TRANSMISSION LINES ANNE-SOPHIE BONNET propagation in the microstrip transmission lines used in microelectronics. In the first part, the case of the perfectly conducting strip. Key words. superconducting transmission lines, waveguides, spectral analysis

  13. CHARACTERIZING LOSSES IN MICROSTRIP TRANSMISSION LINES Rashmi Pathak

    E-Print Network [OSTI]

    Timbie, Peter

    CHARACTERIZING LOSSES IN MICROSTRIP TRANSMISSION LINES by Rashmi Pathak A dissertation submitted . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 2.1 Transmission Lines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 2 Engineering) at the UNIVERSITY OF WISCONSIN­MADISON Summer 2005 #12;i Characterizing Losses in Transmission

  14. STEPS TO ESTABLISH A REAL-TIME TRANSMISSION MONITORING SYSTEM FOR TRANSMISSION OWNERS AND OPERATORS WITHIN THE

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn'tOrigin ofEnergy atLLC - FE DKT. 10-160-LNG - ORDERSTATE ENERGY PROGRAMJulyExecutive S

  15. Articles about Grid Integration and Transmission | Department...

    Broader source: Energy.gov (indexed) [DOE]

    grid integration and transmission featured by the U.S. Department of Energy (DOE) Wind Program. May 18, 2015 New Report Says Western Grid Can Weather Disturbances with High Wind,...

  16. Efficient Spectral Methods for Transmission Eigenvalues and ...

    E-Print Network [OSTI]

    2014-03-24T23:59:59.000Z

    Mar 20, 2014 ... The scattered electric and magnetic fields Es and Hs satisfy the Silver-M¨uller radiation ... of k for which the (homogeneous) interior transmission problem ...... Mathematical methods in the applied sciences, 27(18):2111–. 2129 ...

  17. Scanning Transmission Electron Microscopy Investigations of Complex...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Scanning Transmission Electron Microscopy Investigations of Complex Oxides Monday, May 23, 2011 - 3:30pm SSRL Conference room 137-322 Professor Tom Vogt, NanoCenter & Department of...

  18. Data transmission element for downhole drilling components

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David S. (Lehi, UT); Dahlgren, Scott (Provo, UT); Fox, Joe (Spanish Fork, UT); Sneddon, Cameron (Provo, UT); Briscoe, Michael (Lehi, UT)

    2006-01-31T23:59:59.000Z

    A robust data transmission element for transmitting information between downhole components, such as sections of drill pipe, in the presence of hostile environmental conditions, such as heat, dirt, rocks, mud, fluids, lubricants, and the like. The data transmission element components include a generally U-shaped annular housing, a generally U-shaped magnetically conductive, electrically insulating element such as ferrite, and an insulated conductor. Features on the magnetically conducting, electrically insulating element and the annular housing create a pocket when assembled. The data transmission element is filled with a polymer to retain the components within the annular housing by filling the pocket with the polymer. The polymer can bond with the annular housing and the insulated conductor but preferably not the magnetically conductive, electrically insulating element. A data transmission element is mounted within a recess proximate a mating surface of a downhole drilling component, such as a section of drill pipe.

  19. Electrical Transmission Line Diametrical Retention Mechanism

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Hall, Jr., H. Tracy (Provo, UT); Pixton, David (Lehi, UT); Dahlgren, Scott (Provo, UT); Sneddon, Cameron (Provo, UT); Briscoe, Michael (Lehi, UT); Fox, Joe (Spanish Fork, UT)

    2006-01-03T23:59:59.000Z

    The invention is a mechanism for retaining an electrical transmission line. In one embodiment of the invention it is a system for retaining an electrical transmission line within downhole components. The invention allows a transmission line to be attached to the internal diameter of drilling components that have a substantially uniform drilling diameter. In accordance with one aspect of the invention, the system includes a plurality of downhole components, such as sections of pipe in a drill string, drill collars, heavy weight drill pipe, and jars. The system also includes a coaxial cable running between the first and second end of a drill pipe, the coaxial cable having a conductive tube and a conductive core within it. The invention allows the electrical transmission line to withstand the tension and compression of drill pipe during routine drilling cycles.

  20. Load-resistant coaxial transmission line

    DOE Patents [OSTI]

    Hall, David R.; Fox, Joe

    2006-01-03T23:59:59.000Z

    A transmission line for downhole tools that make up all or part of a tool string for drilling and production of oil, gas, and geothermal wells that can withstand the dynamic gravitational forces and other accelerations associated with downhole excavations. The transmission line has a metal tube, or outer conductor, that houses a coaxial wire inner conductor. A non-metallic dielectric material is interposed between the inner and outer conductors. The outer and inner conductors and the dielectric are sufficiently compressed together so that independent motion between them is abated. Compression of the components of the transmission line may be achieved by drawing the transmission through one or more dies in order to draw down the outer conductor onto the dielectric, or by expanding the inner conductor against the dielectric using a mandrel or hydraulic pressure. Non-metallic bead segments may be used in aid of the compression necessary to resist the dynamic forces and accelerations of drilling.

  1. Transmission policy in the United States

    E-Print Network [OSTI]

    Joskow, Paul L.

    2004-01-01T23:59:59.000Z

    This paper provides an overview of the development of electric power transmission access, pricing and investment policies in the U.S. over the last 15 years and evaluates the current state of those policies. Pre-liberalization ...

  2. Infrastructure Needs: Natural Gas/Electricity Transmission,...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    4,200 miles of transmission lines, 72,000 miles of distribution lines, and 6,300 miles of natural gas pipelines. Our over 8,600 employees are committed to our mission to deliver...

  3. Polarization transmission at RHIC, numerical simulations

    SciTech Connect (OSTI)

    Meot F.; Bai, M.; Liu, C.; Minty, M.; Ranjbar, V.

    2012-05-20T23:59:59.000Z

    Typical tracking simulations regarding the transmission of the polarization in the proton-proton collider RHIC are discussed. They participate in general studies aimed at understanding and improving polarization performances during polarized proton-proton runs.

  4. X-ray transmissive debris shield

    DOE Patents [OSTI]

    Spielman, Rick B. (Albuquerque, NM)

    1994-01-01T23:59:59.000Z

    A composite window structure is described for transmitting x-ray radiation and for shielding radiation generated debris. In particular, separate layers of different x-ray transmissive materials are laminated together to form a high strength, x-ray transmissive debris shield which is particularly suited for use in high energy fluences. In one embodiment, the composite window comprises alternating layers of beryllium and a thermoset polymer.

  5. On Fast Transmission Topology Control Heuristics Pablo A. Ruiz, Member, IEEE, Justin M. Foster, Student Member, IEEE, Aleksandr Rudkevich, Member, IEEE,

    E-Print Network [OSTI]

    Caramanis, Michael

    flow, renewable integra- tion. I. INTRODUCTION TRADITIONALLY, power system operational decision making1 On Fast Transmission Topology Control Heuristics Pablo A. Ruiz, Member, IEEE, Justin M. Foster the OPF problem accordingly. This paper discusses the inclusion of tractable dynamic transmission topol

  6. EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild...

    Broader source: Energy.gov (indexed) [DOE]

    EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild Project, Larimer County, Colorado EIS-0483: Estes to Flatiron Substation Transmission Lines Rebuild Project,...

  7. EIS-0325: Schultz-Hanford Area Transmission Line Project, WA

    Broader source: Energy.gov [DOE]

    BPA proposes to construct a new 500-kilovolt (kV) transmission line in central Washington. This project would increase transmission system capacity north of Hanford.

  8. OAHU Wind Integration And Transmission Study: Summary Report...

    Energy Savers [EERE]

    OAHU Wind Integration And Transmission Study: Summary Report, NREL (National Renewable Energy Laboratory) OAHU Wind Integration And Transmission Study: Summary Report, NREL...

  9. QER Public Meeting in Newark, NJ: Electricity Transmission and...

    Energy Savers [EERE]

    Newark, NJ: Electricity Transmission and Distribution - East QER Public Meeting in Newark, NJ: Electricity Transmission and Distribution - East New Jersey Institute of Technology...

  10. DOE EAC Electricity Adequacy Report. Transmission Chapter DRAFT...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EAC Electricity Adequacy Report. Transmission Chapter DRAFT- September 18, 2008 DOE EAC Electricity Adequacy Report. Transmission Chapter DRAFT- September 18, 2008 The purpose of...

  11. Updating the Electric Grid: An Introduction to Non-Transmission...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    the transmission system. Updating the Electric Grid: An Introduction to Non-Transmission Alternatives for Policymakers More Documents & Publications EAC Recommendations for DOE...

  12. In-situ Transmission Electron Microscopy and Spectroscopy Studies...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Transmission Electron Microscopy and Spectroscopy Studies of Interfaces in Li-ion Batteries: Challenges and In-situ Transmission Electron Microscopy and Spectroscopy Studies of...

  13. Regulatory Roadmap Workshop for Federal Bulk Transmission Regulations...

    Open Energy Info (EERE)

    for bulk transmission. Date: Tuesday, 29 July, 2014 - 09:30 - 15:30 Location: NREL Education Center Auditorium Golden, Colorado Groups: Federal Bulk Transmission Regulatory...

  14. Request for Information on Permitting of Transmission Lines:...

    Energy Savers [EERE]

    Request for Information on Permitting of Transmission Lines: Federal Register Notice Volume 77, No. 38 - Feb. 27, 2012 Request for Information on Permitting of Transmission Lines:...

  15. An environmental sample chamber for reliable scanning transmission...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    environmental sample chamber for reliable scanning transmission x-ray microscopy measurements under water vapor. An environmental sample chamber for reliable scanning transmission...

  16. CFN | Hitachi HD2700C Scanning Transmission Electron Microscope

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Hitachi HD2700C Scanning Transmission Electron Microscope Contacts: Dong Su | Lihua Zhang | Huolin Xin The Hitachi 2700C is a dedicated Scanning Transmission Electron Microscope...

  17. EIS-0484: Montana-to-Washington Transmission System Upgrade Project...

    Energy Savers [EERE]

    4: Montana-to-Washington Transmission System Upgrade Project in Washington, Idaho, and Montana EIS-0484: Montana-to-Washington Transmission System Upgrade Project in Washington,...

  18. Integrating Renewable Energy into the Transmission and Distribution...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Integrating Renewable Energy into the Transmission and Distribution System of the U.S. Virgin Islands Integrating Renewable Energy into the Transmission and Distribution System of...

  19. EIS-0447: Champlain Hudson Power Express Transmission Line Project...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    47: Champlain Hudson Power Express Transmission Line Project, New York EIS-0447: Champlain Hudson Power Express Transmission Line Project, New York Summary This EIS evaluated the...

  20. EA-1880: Big Bend to Witten Transmission Line Project, South...

    Office of Environmental Management (EM)

    880: Big Bend to Witten Transmission Line Project, South Dakota EA-1880: Big Bend to Witten Transmission Line Project, South Dakota Summary The USDA Rural Utilities Service, with...

  1. Eastern Wind Integration and Transmission Study -- Preliminary Findings: Preprint

    SciTech Connect (OSTI)

    Corbus, D.; Milligan, M.; Ela, E.; Schuerger, M.; Zavadil, B.

    2009-09-01T23:59:59.000Z

    This paper reviews the Eastern Wind Integration and Transmission Study, the development of wind datasets, the transmission analysis, and the results of wind integration analysis for four scenarios.

  2. power transmission network design by a greedy randomized ...

    E-Print Network [OSTI]

    of new transmission facilities should be installed, i.e. the ... whole, much more complex, power transmission network ..... 17 new rights of way (corridors).

  3. 2006 National Electric Transmission Congestion Study and Related...

    Office of Environmental Management (EM)

    6 National Electric Transmission Congestion Study and Related Materials 2006 National Electric Transmission Congestion Study and Related Materials The 2006 National Congestion...

  4. Factsheet: An Initiative to Help Modernize Natural Gas Transmission...

    Energy Savers [EERE]

    An Initiative to Help Modernize Natural Gas Transmission and Distribution Infrastructure Factsheet: An Initiative to Help Modernize Natural Gas Transmission and Distribution...

  5. QER Public Meeting in Pittsburgh, PA: Natural Gas: Transmission...

    Office of Environmental Management (EM)

    Pittsburgh, PA: Natural Gas: Transmission, Storage and Distribution QER Public Meeting in Pittsburgh, PA: Natural Gas: Transmission, Storage and Distribution Meeting Date and...

  6. 9-26 QER Report: Energy Transmission, Storage, and Distribution...

    Office of Environmental Management (EM)

    -26 QER Report: Energy Transmission, Storage, and Distribution Infrastructure | April 2015 QER Report: Energy Transmission, Storage, and Distribution Infrastructure | April 2015...

  7. EA-1679: Grand Coulee's Third Powerplant 500-kV Transmission Line Replacement Project, Grant and Okanogon Counties, Washington

    Broader source: Energy.gov [DOE]

    This EA evaluates potential environmental impacts from the construction and operation of six new 500-kV overhead transmission lines to replace six existing underground lines at Grand Coulee Dam. DOE’s Bonneville Power Administration (BPA), a cooperating agency, was asked by the U. S. Department of the Interior’s Bureau of Reclamation to design and construct the proposed new transmission lines. A Finding of No Significant Impact was issued by BPA in December 2011.

  8. Fact #850: December 8, 2014 Automatic Transmissions have closed the Fuel Economy Gap with Manual Transmissions- Dataset

    Broader source: Energy.gov [DOE]

    Excel file with dataset for Fact #850: December 8, 2014 Automatic Transmissions have closed the Fuel Economy Gap with Manual Transmissions

  9. Environmental Assessment of the Gering-Stegall 115-kV Transmission Line Consolidation Project, Scotts Bluff County, Nebraska

    SciTech Connect (OSTI)

    NONE

    1995-05-01T23:59:59.000Z

    The Department of Energy (DOE), Western Area Power Administration (Western) proposes to consolidate segments of two transmission lines near the Gering Substation in Gering, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska. The transmission lines are both located in Scotts Bluff County, Nebraska, within the city of Gering. Presently, there are three parallel 115-kilovolt (kV) transmission lines on separate rights-of-way (ROW) that terminate at the Gering Substation. The project would include dismantling the Archer-Gering wood-pole transmission line and rebuilding the remaining two lines on single-pole steel double circuit structures. The project would consolidate the Gering-Stegall North and Gering-Stegall South 115-kV transmission lines on to one ROW for a 1.33-mile segment between the Gering Substation and a point west of the Gering Landfill. All existing wood-pole H-frame structures would be removed, and the Gering-Stegall North and South ROWs abandoned. Western is responsible for the design, construction, operation, and maintenance of the line. Western prepared an environmental assessment (EA) that analyzed the potential environmental impacts of the proposed construction, operation, and maintenance of the 115-kV transmission line consolidation. Based on the analyses in the EA, the DOE finds that the proposed action is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act of 1969 (NEPA).

  10. Pulse-excited, auto-zeroing multiple channel data transmission system

    DOE Patents [OSTI]

    Fasching, George E. (Morgantown, WV)

    1987-01-01T23:59:59.000Z

    A multiple channel data transmission system is provided in which signals from a plurality of pulse operated transducers and a corresponding plurality of pulse operated signal processor channels are multiplexed for single channel FM transmission to a receiving station. The transducers and corresponding channel amplifiers are powered by pulsing the dc battery power to these devices to conserve energy and battery size for long-term data transmission from remote or inaccessible locations. Auto zeroing of the signal channel amplifiers to compensate for drift associated with temperature changes, battery decay, component aging, etc., in each channel is accomplished by means of a unique auto zero feature which between signal pulses holds a zero correction voltage on an integrating capacitor coupled to the corresponding channel amplifier output. Pseudo-continuous outputs for each channel are achieved by pulsed sample-and-hold circuits which are updated at the pulsed operation rate. The sample-and-hold outputs are multiplexed into an FM/FM transmitter for transmission to an FM receiver station for demultiplexing and storage in separate channel recorders.

  11. Pulse-excited, auto-zeroing multiple channel data transmission system

    DOE Patents [OSTI]

    Fasching, G.E.

    1985-02-22T23:59:59.000Z

    A multiple channel data transmission system is provided in which signals from a plurality of pulse operated transducers and a corresponding plurality of pulse operated signal processor channels are multiplexed for single channel FM transmission to a receiving station. The transducers and corresponding channel amplifiers are powered by pulsing the dc battery power to these devices to conserve energy and battery size for long-term data transmission from remote or inaccessible locations. Auto zeroing of the signal channel amplifiers to compensate for drift associated with temperature changes, battery decay, component aging, etc., in each channel is accomplished by means of a unique auto zero feature which between signal pulses holds a zero correction voltage on an integrating capacitor coupled to the corresponding channel amplifier output. Pseudo-continuous outputs for each channel are achieved by pulsed sample-and-hold circuits which are updated at the pulsed operation rate. The sample-and-hold outputs are multiplexed into an FM/FM transmitter for transmission to an FM receiver station for demultiplexing and storage in separate channel recorders.

  12. Comparative evaluation of neural-network-based and PI current controllers for HVDC transmission

    SciTech Connect (OSTI)

    Sood, V.K.; Kandil, N.; Patel, R.V.; Khorasani, K. (Concordia Univ., Montreal, Quebec (Canada). Dept. of Electrical and Computer Engineering)

    1994-05-01T23:59:59.000Z

    An investigation into a neural network (NN)-based controller, composed of a NN trained off-line in parallel with a NN trained on-line, is described in this paper. This NN controller has the potential of replacing the PI controller traditionally used for HVDC transmission systems. A theoretical basis for the operational behavior of the individual NN controllers is presented. Comparisons between the responses obtained with the NN and PI controllers for the rectifier of an HVDC transmission system are made under typical system perturbations and faults.

  13. Questions and Issues on Hydrogen Pipeline Transmission of Hydrogen

    E-Print Network [OSTI]

    Questions and Issues on Hydrogen Pipelines Pipeline Transmission of Hydrogen Doe Hydrogen Pipeline Working Group Meeting August 31, 2005 #12;Pipeline Transmission of Hydrogen --- 2 Copyright: Air Liquide Transmission of Hydrogen --- 3 Copyright: #12;Pipeline Transmission of Hydrogen --- 4 Copyright: 3. Special

  14. Wireless Sensor Network for Electric Transmission Line Monitoring

    SciTech Connect (OSTI)

    Alphenaar, Bruce

    2009-06-30T23:59:59.000Z

    Generally, federal agencies tasked to oversee power grid reliability are dependent on data from grid infrastructure owners and operators in order to obtain a basic level of situational awareness. Since there are many owners and operators involved in the day-to-day functioning of the power grid, the task of accessing, aggregating and analyzing grid information from these sources is not a trivial one. Seemingly basic tasks such as synchronizing data timestamps between many different data providers and sources can be difficult as evidenced during the post-event analysis of the August 2003 blackout. In this project we investigate the efficacy and cost effectiveness of deploying a network of wireless power line monitoring devices as a method of independently monitoring key parts of the power grid as a complement to the data which is currently available to federal agencies from grid system operators. Such a network is modeled on proprietary power line monitoring technologies and networks invented, developed and deployed by Genscape, a Louisville, Kentucky based real-time energy information provider. Genscape measures transmission line power flow using measurements of electromagnetic fields under overhead high voltage transmission power lines in the United States and Europe. Opportunities for optimization of the commercial power line monitoring technology were investigated in this project to enable lower power consumption, lower cost and improvements to measurement methodologies. These optimizations were performed in order to better enable the use of wireless transmission line monitors in large network deployments (perhaps covering several thousand power lines) for federal situational awareness needs. Power consumption and cost reduction were addressed by developing a power line monitor using a low power, low cost wireless telemetry platform known as the ''Mote''. Motes were first developed as smart sensor nodes in wireless mesh networking applications. On such a platform, it has been demonstrated in this project that wireless monitoring units can effectively deliver real-time transmission line power flow information for less than $500 per monitor. The data delivered by such a monitor has during the course of the project been integrated with a national grid situational awareness visualization platform developed by Oak Ridge National Laboratory. Novel vibration energy scavenging methods based on piezoelectric cantilevers were also developed as a proposed method to power such monitors, with a goal of further cost reduction and large-scale deployment. Scavenging methods developed during the project resulted in 50% greater power output than conventional cantilever-based vibrational energy scavenging devices typically used to power smart sensor nodes. Lastly, enhanced and new methods for electromagnetic field sensing using multi-axis magnetometers and infrared reflectometry were investigated for potential monitoring applications in situations with a high density of power lines or high levels of background 60 Hz noise in order to isolate power lines of interest from other power lines in close proximity. The goal of this project was to investigate and demonstrate the feasibility of using small form factor, highly optimized, low cost, low power, non-contact, wireless electric transmission line monitors for delivery of real-time, independent power line monitoring for the US power grid. The project was divided into three main types of activity as follows; (1) Research into expanding the range of applications for non-contact power line monitoring to enable large scale low cost sensor network deployments (Tasks 1, 2); (2) Optimization of individual sensor hardware components to reduce size, cost and power consumption and testing in a pilot field study (Tasks 3,5); and (3) Demonstration of the feasibility of using the data from the network of power line monitors via a range of custom developed alerting and data visualization applications to deliver real-time information to federal agencies and others tasked with grid reliability (Tasks 6,8)

  15. Solar light transmission of polymer optical fibers

    SciTech Connect (OSTI)

    Tekelioglu, Murat [Mechanical Engineering Department, University of Nevada, Reno, NV 89557 (United States); Wood, Byard D. [Mechanical and Aerospace Engineering Department, Utah State University, Logan, UT 84322 (United States)

    2009-11-15T23:59:59.000Z

    Light transfer (10 m) has been shown in recent experiments that used large-core optical fibers. Theoretical models are not extensive, however, and a further correlation between the theory and experiments has not been given. In this paper, straight and bent fiber subsystem models are introduced with skew and meridional rays to predict the light transmission of POFs (plastic optical fibers). Such fibers have been realized, for example, in HSL (hybrid solar lighting) systems. The purpose of this paper is to combine the straight and bent fiber subsystems to estimate the light transmission of HSL systems. It is shown that meridional rays, for which the optical-loss parameters were estimated, better represent the experimental results compared to skew rays ({+-}5.3% vs {+-}24.7% of %-difference). Model predictions were compared with the results of a commercial software. Sensitivity analysis on the subsystems indicated the most-to-least significant parameters in light transmission. (author)

  16. Downhole transmission system comprising a coaxial capacitor

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Pixton, David S. (Lehi, UT); Johnson, Monte L. (Orem, UT); Bartholomew, David B. (Springville, UT); Hall, Jr., H. Tracy (Provo, UT); Rawle, Michael (Springville, UT)

    2011-05-24T23:59:59.000Z

    A transmission system in a downhole component comprises a plurality of data transmission elements. A coaxial cable having an inner conductor and an outer conductor is disposed within a passage in the downhole component such that at least one capacitor is disposed in the passage and having a first terminal coupled to the inner conductor and a second terminal coupled to the outer conductor. Preferably the transmission element comprises an electrically conducting coil. Preferably, within the passage a connector is adapted to electrically connect the inner conductor of the coaxial cable and the lead wire. The coaxial capacitor may be disposed between and in electrically communication with the connector and the passage. In another embodiment a connector is adapted to electrical connect a first and a second portion of the inner conductor of the coaxial cable and a coaxial capacitor is in electrical communication with the connector and the passage.

  17. Unbundling generation and transmission services for competitive electricity markets

    SciTech Connect (OSTI)

    Hirst, E.; Kirby, B.

    1998-01-01T23:59:59.000Z

    Ancillary services are those functions performed by the equipment and people that generate, control, and transmit electricity in support of the basic services of generating capacity, energy supply, and power delivery. The Federal Energy Regulatory Commission (FERC) defined such services as those `necessary to support the transmission of electric power from seller to purchaser given the obligations of control areas and transmitting utilities within those control areas to maintain reliable operations of the interconnected transmission system.` The nationwide cost of ancillary services is about $12 billion a year, roughly 10% of the cost of the energy commodity. More important than the cost, however, is the necessity of these services for bulk-power reliability and for the support of commercial transactions. FERC`s landmark Order 888 included a pro forma tariff with provision for six key ancillary services. The Interconnected Operations Services Working Group identified another six services that it felt were essential to the operation of bulk-power systems. Several groups throughput the United States have created or are forming independent system operators, which will be responsible for reliability and commerce. To date, the electricity industry (including traditional vertically integrated utilities, distribution utilities, power markets and brokers, customers, and state and federal regulators) has paid insufficient attention to these services. Although the industry had made substantial progress in identifying and defining the key services, much remains to be doe to specify methods to measure the production, delivery, and consumption of these services; to identify the costs and cost-allocation factors for these services; and to develop market and operating rules for their provision and pricing. Developing metrics, determining costs, and setting pricing rules are important because most of these ancillary services are produced by the same pieces of equipment that produce the basic electricity commodity. Thus, the production of energy and ancillary services is highly interactive, sometimes complementary and sometimes competing. In contrast to today`s typical time-invariant, embedded-cost prices, competitive prices for ancillary services would vary with system loads and spot prices for energy.

  18. Idaho/Transmission | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdfGetecGtel JumpCounty, Texas:ITCSolid WasteIdahoTransmissionHeader.png Roadmap

  19. Idaho/Transmission/Roadmap | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdfGetecGtel JumpCounty, Texas:ITCSolidIdaho‎ | Transmission Jump to:

  20. Idaho/Transmission/Summary | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdfGetecGtel JumpCounty, Texas:ITCSolidIdaho‎ | Transmission JumpIdaho, the

  1. Three-dimensional isotropic perfect lens based on LC-loaded transmission lines

    E-Print Network [OSTI]

    P. Alitalo; S. Maslovski; S. Tretyakov

    2005-09-16T23:59:59.000Z

    An isotropic three-dimentional perfect lens based on cubic meshes of interconnected transmission lines and bulk loads is proposed. The lens is formed by a slab of a loaded mesh placed in between two similar unloaded meshes. The dispersion equations and the characteristic impedances of the eigenwaves in the meshes are derived analytically, with an emphasis on generality. This allows designing of transmission-line meshes with desired dispersion properties. The required backward-wave mode of operation in the lens is realized with simple inductive and capacitive loads. An analytical expression for the transmission through the lens is derived and the amplification of evanescent waves is demonstrated. Factors that influence enhancement of evanescent waves in the lens are studied and the corresponding design criteria are established. A possible realization of the structure is outlined.

  2. Supplement Analysis for the Transmission System Vegetation Management Program FEIS (DOE/EIS-0285/SA-10)

    SciTech Connect (OSTI)

    N /A

    2001-05-15T23:59:59.000Z

    BPA proposes to clear unwanted vegetation in the rights-of-ways and around tower structures that may impede the operation and maintenance of the subject transmission line. All work will be in accordance with the National Electrical Safety Code and BPA standards. BPA plans to conduct vegetation control with the goal of removing tall growing vegetation that is currently or will soon be a hazard to the transmission line. BPA's overall goal is to have low-growing plant communities along the rights-of-way to control the development of potentially threatening vegetation. This project meets the standards and guidelines for the Transmission System Vegetation Management Program Final Environmental Impact Statement (FEIS) and Record of Decision (ROD).

  3. Giga-bit optical data transmission module for Beam Instrumentation

    E-Print Network [OSTI]

    Roedne, L T; Cenkeramaddi, L R; Jiao, L

    Particle accelerators require electronic instrumentation for diagnostic, assessment and monitoring during operation of the transferring and circulating beams. A sensor located near the beam provides an electrical signal related to the observable quantity of interest. The front-end electronics provides analog-to-digital conversion of the quantity being observed and the generated data are to be transferred to the external digital back-end for data processing, and to display to the operators and logging. This research project investigates the feasibility of radiation-tolerant giga-bit data transmission over optic fibre for beam instrumentation applications, starting from the assessment of the state of the art technology, identification of challenges and proposal of a system level solution, which should be validated with a PCB design in an experimental setup. Radiation tolerance of 10 kGy (Si) Total Ionizing Dose (TID) over 10 years of operation, Bit Error Rate (BER) 10-6 or better. The findings and results of th...

  4. Radio-Frequency Interference (RFI) From Extra-High-Voltage (EHV) Transmission Lines

    E-Print Network [OSTI]

    Ellingson, Steven W.

    -current (HVAC) transmission lines; high-voltage direct-current (HVDC) transmission lines will be addressed

  5. In-Situ Electrochemical Transmission Electron Microscopy for Battery Research

    SciTech Connect (OSTI)

    Mehdi, Beata L [Pacific Northwest National Laboratory (PNNL)] [Pacific Northwest National Laboratory (PNNL); Gu, Meng [Pacific Northwest National Laboratory (PNNL)] [Pacific Northwest National Laboratory (PNNL); Parent, Lucas [Pacific Northwest National Laboratory (PNNL)] [Pacific Northwest National Laboratory (PNNL); Xu, WU [Pacific Northwest National Laboratory (PNNL)] [Pacific Northwest National Laboratory (PNNL); Nasybulin, Eduard [Pacific Northwest National Laboratory (PNNL)] [Pacific Northwest National Laboratory (PNNL); Chen, Xilin [Pacific Northwest National Laboratory (PNNL)] [Pacific Northwest National Laboratory (PNNL); Unocic, Raymond R [ORNL] [ORNL; Xu, Pinghong [University of California, Davis] [University of California, Davis; Welch, David [Pacific Northwest National Laboratory (PNNL)] [Pacific Northwest National Laboratory (PNNL); Abellan, Patricia [Pacific Northwest National Laboratory (PNNL)] [Pacific Northwest National Laboratory (PNNL); Zhang, Ji-Guang [Pacific Northwest National Laboratory (PNNL)] [Pacific Northwest National Laboratory (PNNL); Liu, Jun [Pacific Northwest National Laboratory (PNNL)] [Pacific Northwest National Laboratory (PNNL); Wang, Chongmin [Pacific Northwest National Laboratory (PNNL)] [Pacific Northwest National Laboratory (PNNL); Arslan, Ilke [Pacific Northwest National Laboratory (PNNL)] [Pacific Northwest National Laboratory (PNNL); Evans, James E [Pacific Northwest National Laboratory (PNNL)] [Pacific Northwest National Laboratory (PNNL); Browning, Nigel [Pacific Northwest National Laboratory (PNNL)] [Pacific Northwest National Laboratory (PNNL)

    2014-01-01T23:59:59.000Z

    The recent development of in-situ liquid stages for (scanning) transmission electron microscopes now makes it possible for us to study the details of electrochemical processes under operando conditions. As electrochemical processes are complex, care must be taken to calibrate the system before any in-situ/operando observations. In addition, as the electron beam can cause effects that look similar to electrochemical processes at the electrolyte/electrode interface, an understanding of the role of the electron beam in modifying the operando observations must also be understood. In this paper we describe the design, assembly, and operation of an in-situ electrochemical cell, paying particular attention to the method for controlling and quantifying the experimental parameters. The use of this system is then demonstrated for the lithiation/delithiation of silicon nanowires.

  6. Summary of multiterminal high-voltage direct current transmission technology

    SciTech Connect (OSTI)

    Biggs, R.B.; Jewell, W.T.

    1984-05-01T23:59:59.000Z

    This report summarizes the present state of multiterminal (MT) high-voltage direct current (HVDC) power transmission. The purpose is to reassess the need for HVDC circuit breakers and to identify needed research for MT HVDC. The fundamentals of this technology are presented, and previous research and development is reviewed. Although no MT HVDC systems have yet been built, many concepts have been proposed. Some require a dc breaker, and others do not. Both options have advantages and disadvantages for various applications, so the selection will depend on the proposed application. Research is needed to define operating characteristics of various MT HVDC systems. In some applications, dc breakers will be useful, so research into HVDC interruption should continue. Also, dc fault detection and control algorithms for MT systems should be studied.

  7. UNDERSTANDING METHANE EMISSIONS SOURCES AND VIABLE MITIGATION MEASURES IN THE NATURAL GAS TRANSMISSION SYSTEMS: RUSSIAN AND U.S. EXPERIENCE

    SciTech Connect (OSTI)

    Ishkov, A.; Akopova, Gretta; Evans, Meredydd; Yulkin, Grigory; Roshchanka, Volha; Waltzer, Suzie; Romanov, K.; Picard, David; Stepanenko, O.; Neretin, D.

    2011-10-01T23:59:59.000Z

    This article will compare the natural gas transmission systems in the U.S. and Russia and review experience with methane mitigation technologies in the two countries. Russia and the United States (U.S.) are the world's largest consumers and producers of natural gas, and consequently, have some of the largest natural gas infrastructure. This paper compares the natural gas transmission systems in Russia and the U.S., their methane emissions and experiences in implementing methane mitigation technologies. Given the scale of the two systems, many international oil and natural gas companies have expressed interest in better understanding the methane emission volumes and trends as well as the methane mitigation options. This paper compares the two transmission systems and documents experiences in Russia and the U.S. in implementing technologies and programs for methane mitigation. The systems are inherently different. For instance, while the U.S. natural gas transmission system is represented by many companies, which operate pipelines with various characteristics, in Russia predominately one company, Gazprom, operates the gas transmission system. However, companies in both countries found that reducing methane emissions can be feasible and profitable. Examples of technologies in use include replacing wet seals with dry seals, implementing Directed Inspection and Maintenance (DI&M) programs, performing pipeline pump-down, applying composite wrap for non-leaking pipeline defects and installing low-bleed pneumatics. The research methodology for this paper involved a review of information on methane emissions trends and mitigation measures, analytical and statistical data collection; accumulation and analysis of operational data on compressor seals and other emission sources; and analysis of technologies used in both countries to mitigate methane emissions in the transmission sector. Operators of natural gas transmission systems have many options to reduce natural gas losses. Depending on the value of gas, simple, low-cost measures, such as adjusting leaking equipment components, or larger-scale measures, such as installing dry seals on compressors, can be applied.

  8. Nordic electricity congestion's arrangement as a model for Europe : physical constraints or operators' opportunism?

    E-Print Network [OSTI]

    Glachant, Jean-Michel

    2002-01-01T23:59:59.000Z

    Congestion on power grids seems a physical reality, a "hard" fact easy to check. Our paper models a different idea: congestion signal may be distorted by transmission system operators (TSOs), which puts the European ...

  9. Extraordinary acoustic transmission mediated by Helmholtz resonators

    SciTech Connect (OSTI)

    Koju, Vijay [Computation Science Program, Middle Tennessee State University, Murfreesboro, Tennessee 37132 (United States); Rowe, Ebony [Department of Physics and Astronomy, Middle Tennessee State University, Murfreesboro, Tennessee 37132 (United States); Robertson, William M., E-mail: William.Robertson@mtsu.edu [Computation Science Program, Middle Tennessee State University, Murfreesboro, Tennessee 37132 (United States); Department of Physics and Astronomy, Middle Tennessee State University, Murfreesboro, Tennessee 37132 (United States)

    2014-07-15T23:59:59.000Z

    We demonstrate perfect transmission of sound through a rigid barrier embedded with Helmholtz resonators. The resonators are confined within a waveguide and they are oriented such that one neck protrudes onto each side of the barrier. Perfect sound transmission occurs even though the open area of the necks is less than 3% of the barrier area. Maximum transmission occurs at the resonant frequency of the Helmholtz resonator. Because the dimensions of the Helmholtz resonators are much smaller than the resonant wavelength, the transmission is independent of the direction of sound on the barrier and of the relative placement of the necks. Further, we show that the transmitted sound experiences a continuous phase transition of ? radians as a function of frequency through resonance. In simulations of adjacent resonators with slightly offset resonance frequencies, the phase difference leads to destructive interference. By expanding the simulation to a linear array of tuned Helmholtz resonators we show that it is possible to create an acoustic lens. The ability of Helmholtz resonator arrays to manipulate the phase of a plane acoustic wave enables a new class of sonic beam-forming devices analogous to diffractive optics.

  10. Transmission-Planning Research & Development Scoping Project

    E-Print Network [OSTI]

    -99-013 Prepared For: Linda Kelly, Project Manager Energy Systems Integration Program Laurie ten Hope, PIER ProgramTransmission-Planning Research & Development Scoping Project CALIFORNIA ENERGY COMMISSION, California Institute for Energy and the Environment under Contract No. 500-99-013 and by the U.S. Department

  11. ADAPTIVE MULTIMEDIA TRANSMISSION OVER THE INTERNET

    E-Print Network [OSTI]

    Bouras, Christos

    Chapter 20 ADAPTIVE MULTIMEDIA TRANSMISSION OVER THE INTERNET CHRISTOS BOURAS and APOSTOLOS GKAMAS that are available to multimedia applications can be modified very quickly. Multimedia applications must have to multimedia applications, we can use techniques both at the network and application layers. Adaptive

  12. DISTRIBUTED OPPORTUNISTIC TRANSMISSION FOR WIRELESS SENSOR NETWORKS

    E-Print Network [OSTI]

    Islam, M. Saif

    DISTRIBUTED OPPORTUNISTIC TRANSMISSION FOR WIRELESS SENSOR NETWORKS Qing Zhao and Lang Tong School Strategy We consider the problem of information retrieval in sensor networks with mobile access points on Communica- tion and Networks under Grant DAAD19-01-2-0011. ˘ Fig. 1: Sensor networks with mobile access

  13. A neutron transmission study of environmental Gd

    E-Print Network [OSTI]

    Cristiana Oprea; Ioan Alexandru Oprea; Alexandru Mihul

    2014-06-02T23:59:59.000Z

    A new method for the determination of environmental Gd by neutron transmission (NT) experiments is proposed. The NT method is based on the measurements of neutron spectra passing through a target. From the attenuation neutron spectra new data as concentration, width, resonance energies and cross section have been obtained.

  14. Transmission line environmental assessment guidance document

    SciTech Connect (OSTI)

    Jackson, J.; Pentecost, E.; Muzzarelli, J.

    1994-01-01T23:59:59.000Z

    Since 1939, U.S. utility companies have been required to obtain a Presidential Permit to construct electric transmission lines that cross a U.S. border and connect with a foreign utility. The purpose of this document is to provide Presidential Permit applicants with two types of guidance: (1) on the type of environmental and project descriptive information needed to assess the potential impacts of the proposed and alternative actions and (2) on compliance with applicable federal and state regulations. The main three chapters present information on the purpose and content of this document (Chapter 1); legislative, regulatory, and consultation requirements for transmission line interconnect projects (Chapter 2); and identification of basic transmission system design parameters and environmental data requirements for analysis of potential impacts of the proposed action (Chapter 3). Chapter 3 also includes information on possible techniques or measures to mitigate impacts. Appendix A presents an overview of NEPA requirements and DOE`s implementing procedures. Appendix B summarizes information on legislation that may be applicable to transmission line projects proposed in Presidential Permit applications.

  15. Nanolithography Using High Transmission Nanoscale Bowtie

    E-Print Network [OSTI]

    Xu, Xianfan

    Nanolithography Using High Transmission Nanoscale Bowtie Apertures Liang Wang, Sreemanth M demonstrate that bowtie apertures can be used for contact lithography to achieve nanometer scale resolution. The bowtie apertures with a 30 nm gap size are fabricated in aluminum thin films coated on quartz substrates

  16. Neurons and Neural Transmission Part I / IV

    E-Print Network [OSTI]

    of neurons ­ Classification of neurons ­ Neuron Doctrine "Father of modern neuroscience" #12;Ramon y CajalNeurons and Neural Transmission Part I / IV Anton Kapliy February 24, 2009 #12;Nervous system of optical nerve #12;Ramon y Cajal's neurons Information in neurons flows in one direction: "from dendrites

  17. HVDC transmission: a path to the future?

    SciTech Connect (OSTI)

    Teichler, Stephen L.; Levitine, Ilia

    2010-05-15T23:59:59.000Z

    Direct current transmission has been the poor stepchild of the U.S. electric industry. Although early-generation plants were based on DC technology, it was soon deemed uneconomical to transmit electricity over long distances, but it now appears poised for a change. Both the increasing technical potential and changing economics of HVDC lines promise a growing role in the future. (author)

  18. Policy Issues for Retail Beamed Power Transmission

    E-Print Network [OSTI]

    solar electric power using retail delivery of beamed power. Recent advances in power beaming have made to enable widespread adoption of this clean and sustainable contribution to meeting energy needs. It is seen to micro-renewable energy resource exploitation since wired power transmission is only cost effective over

  19. Bordereau de transmission accident du travail

    E-Print Network [OSTI]

    Pouyanne, Nicolas

    Bordereau de transmission accident du travail Service des pensions et accidents du travail accidents du travail du CNRS Accompagné des pièces requises Nom .................................................... Prénom ........................ Matricule ...... Composition du dossier Observations Déclaration d'accident

  20. Supplement Analysis for the Transmission System Vegetation Management Program FEIS (DOE/EIS-0285/SA-07)

    SciTech Connect (OSTI)

    N /A

    2001-04-18T23:59:59.000Z

    Vegetation Management on section of three ROWs. The ROWs include selected sections of the McNary Powerhouse, the present and proposed new sections of the McNary-Roundup and the McNary Switchyard South Transmission lines. BPA proposes to clear unwanted vegetation in the rights-of-ways and around tower structures that may impede the operation and maintenance of the subject transmission lines. All work will be in accordance with the National Electrical Safety Code and BPA standards. See Section 1.1 of the attached checklist for pertinent information on each section of referenced transmission line. BPA would conduct the vegetation control with the goal of removing tall-growing vegetation that is currently or will soon be a hazard to the transmission lines and to promote low-growing plant communities in the right-of-way and to clear vegetation from new rights-of-way corridors. This project meets the standards and guidelines for the Transmission System Vegetation Management Program Final Environmental Impact Statement (FEIS) and Record of Decision (ROD).

  1. Fort Peck-Havre transmission line project, Hill, Blaine, Phillips, Valley and McCone Counties, Montana

    SciTech Connect (OSTI)

    Not Available

    1982-09-01T23:59:59.000Z

    Construction and operation of a 180-mile, 230-kilovlt (kV) transmission line between Fort Peck and Havre, Montana is proposed to provide a replacement for the 161-kV line that currently runs between the two cities. The new line would be carried on woodpole, H-frame structures. The existing 161-kV line would be removed, and the Richardson Coulee Substation would be relocated. Intermediate facilities to be improved would include the Fort Peck Switchyard and the Richardson Coulee, Malta, Harlem, and Havre substations.Construction of the line would commence in August 1983, and operation would commence in January 1986. The expected life of the transmission system would be 100 years. Estimated cost of the project, in 1983 dollars, is $36.1 million. The project would upgrade an essential element of the Western Area Power Administration's electric power system and the Montana Power Company's interconnected transmission network. Continued electric service reliability would be improved, and safety conditions affecting personnel who maintain the line would be enhanced. Additional transmission capacity would be provided to accommodate future load growth, precluding the need for multiple transmission lines. The line would eleminate seven acres of productive land and create physical conflicts with present and future agricultural activities. The line would traverse areas characterized by concentrations of archaeological resources and cultural resources of importance to native Americans. Transmission structures could mar scenery in areas with historically significant architecture and would interfere with waterfowl.

  2. Optimal meter placement and transaction-based loss allocation in deregulated power system operation

    E-Print Network [OSTI]

    Ding, Qifeng

    2005-02-17T23:59:59.000Z

    (OPF) algorithm to optimize the loss compensation if some transactions elect to purchase the loss service from the Independent System Operator (ISO) and accordingly the incurred losses are fairly allocated back to individual transactions. IEEE test... regulations have been causing the power industry to move rapidly toward the open transmission access, the unbundling of previously integrated services and the creation of regional transmission organizations (RTOs), Independent System Operators (ISOs) and so...

  3. Flexible Transmission in the Smart Grid

    E-Print Network [OSTI]

    Hedman, Kory Walter

    2010-01-01T23:59:59.000Z

    which is an additional cost if wind energy penetration isthe operational costs required to integrate more wind energy

  4. Oahu Wind Integration and Transmission Study (OWITS): Hawaiian Islands Transmission Interconnection Project

    SciTech Connect (OSTI)

    Woodford, D.

    2011-02-01T23:59:59.000Z

    This report provides an independent review included an initial evaluation of the technical configuration and capital costs of establishing an undersea cable system and examining impacts to the existing electric transmission systems as a result of interconnecting the islands.

  5. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    Contingency Analysis Cost Model Flow Analysis Non-Wind Windthe cost of transmission for wind through a meta-analysis ofanalysis in Section 4. Although the results focus on the unit cost of wind

  6. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    179c/179c9e0086c0.pdf National Wind CoordinatingTransmission Planning and Wind Energy. Issue Brief. August.and Renewable Energy, Wind & Hydropower Technologies Program

  7. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    SciTech Connect (OSTI)

    Mills, Andrew D.; Wiser, Ryan; Porter, Kevin

    2009-02-02T23:59:59.000Z

    The rapid development of wind power that the United States has experienced over the last several years has been coupled with a growing concern that wind development will require substantial additions to the nation's transmission infrastructure. Transmission is particularly important for wind power due to the locational dependence of wind resources, the relatively low capacity factor of wind plants, and the mismatch between the short lead time to build a new wind project and the longer lead time often needed to plan, permit, and construct transmission. It is clear that institutional issues related to transmission planning, siting, and cost allocation will pose major obstacles to accelerated wind power deployment, but also of concern is the potential cost of this infrastructure build out. Simply put, how much extra cost will society bear to deliver wind power to load centers? Without an answer to this question, there can be no consensus on whether or not the cost of developing transmission for wind will be a major barrier to further wind deployment, or whether the institutional barriers to transmission expansion are likely to be of more immediate concern. In this report, we review a sample of 40 detailed transmission studies that have included wind power. These studies cover a broad geographic area, and were completed from 2001-2008. Our primary goal in reviewing these studies is to develop a better understanding of the transmission costs needed to access growing quantities of wind generation. A secondary goal is to gain a better appreciation of the differences in transmission planning approaches in order to identify those methodologies that seem most able to estimate the incremental transmission costs associated with wind development. Finally, we hope that the resulting dataset and discussion might be used to inform the assumptions, methods, and results of higher-level assessment models that are sometimes used to estimate the cost of wind deployment (e.g. NEMS and WinDS). The authors and general location of the 40 detailed transmission studies included in our review are illustrated in Figure ES-1. As discussed in the body of the report, these studies vary considerably in scope, authorship, objectives, methodology, and tools. Though we recognize this diversity and are cognizant that comparisons among these studies are therefore somewhat inappropriate, we nonetheless emphasize such simple comparisons in this report. We do so in order to improve our understanding of the range of transmission costs needed to access greater quantities of wind, and to highlight some of the drivers of those costs. In so doing, we gloss over many important details and differences among the studies in our sample. In emphasizing simple comparisons, our analysis focuses primarily on the unit cost of transmission implied by each of the studies. The unit cost of transmission for wind in $/kW terms on a capacity-weighted basis is estimated by simply dividing the total transmission cost in a study by the total amount of incremental generation capacity (wind and non-wind) modeled in that study. In so doing, this metric assumes that within any individual study all incremental generation capacity imposes transmission costs in proportion to its nameplate capacity rating. The limitations to this approach are described in some detail in the body of the report.

  8. Phase 2 Report: Oahu Wind Integration and Transmission Study (OWITS); Hawaiian Islands Transmission Interconnection Project

    SciTech Connect (OSTI)

    Woodford, D.

    2011-02-01T23:59:59.000Z

    This report provides an independent review including an initial evaluation of the technical configuration and capital costs of establishing an undersea cable system and examining impacts to the existing electric transmission systems as a result of interconnecting the islands

  9. Regulations for Electric Transmission and Fuel Gas Transmission Lines Ten or More Miles Long (New York)

    Broader source: Energy.gov [DOE]

    Any person who wishes to construct an electric or gas transmission line that is more than ten miles long must file documents describing the construction plans and potential land use and...

  10. A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS

    E-Print Network [OSTI]

    Mills, Andrew; Wiser, Ryan; Porter, Kevin

    2007-01-01T23:59:59.000Z

    factor of individual wind farms leads to concerns thatplants. The location of wind farms is dependent on the winda lower-performing wind farm than to build new transmission

  11. California Energy Commission Public Interest EnergyResearch/Energy System Integration -- Transmission-Planning Research&Development Scoping Project

    SciTech Connect (OSTI)

    Eto, Joseph H.; Lesieutre, Bernard; Widergren, Steven

    2004-07-01T23:59:59.000Z

    The objective of this Public Interest Energy Research (PIER)scoping project is to identify options for public-interest research and development (R&D) to improve transmission-planning tools, techniques, and methods. The information presented was gathered through a review of current California utility, California Independent System Operator (ISO), and related western states electricity transmission-planning activities and emerging needs. This report presents the project teams findings organized under six topic areas and identifies 17 distinct R&D activities to improve transmission-planning in California and the West. The findings in this report are intended for use, along with other materials, by PIER staff, to facilitate discussions with stakeholders that will ultimately lead to development of a portfolio of transmission-planning R&D activities for the PIER program.

  12. Bonneville Project Act, Federal Columbia River Transmission System Act and Other Related Legislation.

    SciTech Connect (OSTI)

    Not Available

    1985-01-01T23:59:59.000Z

    Legislative texts are provided for: Bonneville Project Act which authorizes the completion, maintenance, and operation of Bonneville project for navigation, and for other purposes; Federal Columbia River Transmission system Act which enables the Secretary of the Interior to provide for operation, maintenance, and continued construction of the Federal transmission system in the Pacific Northwest by use of the revenues of the Federal Columbia River Power System and the proceeds of revenue bonds, and for other purposes; public law 88--552 which guarantees electric consumers of the Pacific Northwest first call on electric energy generated at Federal hydroelectric plants in that regions and reciprocal priority, and for other purposes; and public law 78--329 which provides for the partial construction of the Hungary Horse Dam on the South Fork of the Flathead River in the state of Montana, and for other purposes

  13. Energy harvesting and wireless energy transmission for powering SHM sensor nodes

    SciTech Connect (OSTI)

    Taylor, Stuart G [Los Alamos National Laboratory; Farinholt, Kevin M [Los Alamos National Laboratory; Park, Gyuhae [Los Alamos National Laboratory; Farrar, Charles R [Los Alamos National Laboratory

    2009-01-01T23:59:59.000Z

    In this paper, we present a feasibility study of using energy harvesting and wireless energy transmission systems to operate SHM sensor nodes. The energy harvesting approach examines the use of kinetic energy harvesters to scavenge energy from the ambient sources. Acceleration measurements were made on a bridge, and serve as the basis for a series of laboratory experiments that replicate these sources using an electromagnetic shaker. We also investigated the use of wireless energy transmission systems to operate SHM sensor nodes. The goal of this investigation is to develop SHM sensing systems which can be permanently embedded in the host structure and do not require on-board power sources. This paper summarizes considerations needed to design such systems, experimental procedures and results, and additional issues that can be used as guidelines for future investigations.

  14. Remarks Concerning the Public Utility Commission of Texas Study on Bulk Power Transmission 

    E-Print Network [OSTI]

    Sweatman, R. T.

    1988-01-01T23:59:59.000Z

    . However, there is a dangerous misconception among many who are seeking to find remedies to the cost and supply problems of electric energy. There are those who believe that an electric transmission system operates simply like a gas pipeline system... supply of electric energy will be in peril. A pipeline system is constructed for the sole purpose of transporting large quantities of fuel from the oil and gas fields to the large metropolitan areas where it is consumed, largely by electri...

  15. Flashover vulnerability of transmission and distribution lines to high-altitude electromagnetic pulse (HEMP)

    SciTech Connect (OSTI)

    Kruse, V.J.; Liu, T.K.; Tesche, F.M.; Barnes, P.R.

    1989-01-01T23:59:59.000Z

    This paper estimates the vulnerability of transmission and distribution lines to flashover from the electromagnetic pulse generated by a nuclear detonation 400 kilometers above the earth. The analysis consists of first determining the cumulative probability of induced-voltage on three-phase lines, including shield and neutral conductors, for four operating voltages and then comparing these stresses to estimates of line insulation strength. 11 refs., 9 figs., 5 tabs.

  16. Electric Utility Transmission and Distribution Line Engineering Program

    SciTech Connect (OSTI)

    Peter McKenny

    2010-08-31T23:59:59.000Z

    Economic development in the United States depends on a reliable and affordable power supply. The nation will need well educated engineers to design a modern, safe, secure, and reliable power grid for our future needs. An anticipated shortage of qualified engineers has caused considerable concern in many professional circles, and various steps are being taken nationwide to alleviate the potential shortage and ensure the North American power system's reliability, and our world-wide economic competitiveness. To help provide a well-educated and trained workforce which can sustain and modernize the nation's power grid, Gonzaga University's School of Engineering and Applied Science has established a five-course (15-credit hour) Certificate Program in Transmission and Distribution (T&D) Engineering. The program has been specifically designed to provide working utility engineering professionals with on-line access to advanced engineering courses which cover modern design practice with an industry-focused theoretical foundation. A total of twelve courses have been developed to-date and students may select any five in their area of interest for the T&D Certificate. As each course is developed and taught by a team of experienced engineers (from public and private utilities, consultants, and industry suppliers), students are provided a unique opportunity to interact directly with different industry experts over the eight weeks of each course. Course material incorporates advanced aspects of civil, electrical, and mechanical engineering disciplines that apply to power system design and are appropriate for graduate engineers. As such, target students for the certificate program include: (1) recent graduates with a Bachelor of Science Degree in an engineering field (civil, mechanical, electrical, etc.); (2) senior engineers moving from other fields to the utility industry (i.e. paper industry to utility engineering or project management positions); and (3) regular working professionals wishing to update their skills or increase their knowledge of utility engineering design practices and procedures. By providing graduate educational opportunities for the above groups, the T&D Program will help serve a strong industry need for training the next generation of engineers in the cost-effective design, construction, operation, and maintenance of modern electrical transmission and distribution systems. In addition to developing the on-line engineering courses described above, the T&D Program also focused significant efforts towards enhancing the training opportunities available to power system operators in the northwest. These efforts have included working with outside vendors to provide NERC-approved training courses in Gonzaga University's (GU) system operator training facility, support for an accurate system model which can be used in regional blackstart exercises, and the identification of a retired system operator who could provide actual regional training courses. The GU system operator training facility is also being used to recruit young workers, veterans, and various under-represented groups to the utility industry. Over the past three years students from Columbia Gorge Community College, Spokane Falls Community College, Walla Walla Community College, Central Washington University, Eastern Washington University, Gonzaga University, and various local high schools have attended short (one-day) system operator training courses free of charge. These collaboration efforts has been extremely well received by both students and industry, and meet T&D Program objectives of strengthening the power industry workforce while bridging the knowledge base across power worker categories, and recruiting new workers to replace a predominantly retirement age workforce. In the past three years the T&D Program has provided over 170 utility engineers with access to advanced engineering courses, been involved in training more than 300 power system operators, and provided well over 500 college and high school students with an experienc

  17. Dispersion-free radial transmission lines

    DOE Patents [OSTI]

    Caporaso, George J. (Livermore, CA); Nelson, Scott D. (Patterson, CA)

    2011-04-12T23:59:59.000Z

    A dispersion-free radial transmission line ("DFRTL") preferably for linear accelerators, having two plane conductors each with a central hole, and an electromagnetically permeable material ("EPM") between the two conductors and surrounding a channel connecting the two holes. At least one of the material parameters of relative magnetic permeability, relative dielectric permittivity, and axial width of the EPM is varied as a function of radius, so that the characteristic impedance of the DFRTL is held substantially constant, and pulse transmission therethrough is substantially dispersion-free. Preferably, the EPM is divided into concentric radial sections, with the varied material parameters held constant in each respective section but stepwise varied between sections as a step function of the radius. The radial widths of the concentric sections are selected so that pulse traversal time across each section is the same, and the varied material parameters of the concentric sections are selected to minimize traversal error.

  18. Acoustic data transmission through a drillstring

    DOE Patents [OSTI]

    Drumheller, Douglas S. (Cedar Crest, NM)

    1992-01-01T23:59:59.000Z

    A method and apparatus for acoustically transmitting data along a drillstring is presented. In accordance with one embodiment of the present invention, acoustic data signals are conditioned to counteract distortions caused by the drillstring. Preferably, this conditioning step comprises multiplying each frequency component of the data signal by exp (-ikL) where L is the transmission length of the drillstring, k is the wave number in the drillstring at the frequency of each component and i is (-1).sup.1/2. In another embodiment of this invention, data signals having a frequency content in at least one passband of the drillstring are generated preferably traveling in only one direction (e.g., up the drillstring) while echoes in the drillstring resulting from the data transmission are suppressed.

  19. Acoustic data transmission through a drillstring

    DOE Patents [OSTI]

    Drumheller, D.S.

    1992-07-07T23:59:59.000Z

    A method and apparatus for acoustically transmitting data along a drillstring are presented. In accordance with one embodiment of the present invention, acoustic data signals are conditioned to counteract distortions caused by the drillstring. Preferably, this conditioning step comprises multiplying each frequency component of the data signal by exp ([minus]ikL) where L is the transmission length of the drillstring, k is the wave number in the drillstring at the frequency of each component and i is ([minus]1)[sup 1/2]. In another embodiment of this invention, data signals having a frequency content in at least one passband of the drillstring are generated preferably traveling in only one direction (e.g., up the drillstring) while echoes in the drillstring resulting from the data transmission are suppressed. 20 figs.

  20. Transmissive optomechanical platforms with engineered spatial defects

    E-Print Network [OSTI]

    Edoardo Tignone; Guido Pupillo; Claudiu Genes

    2014-06-23T23:59:59.000Z

    We investigate the optomechanical photon-phonon coupling of a single light mode propagating through an array of vibrating mechanical elements. As recently shown for the particular case of a periodic array of membranes embedded in a high-finesse optical cavity [A. Xuereb, C. Genes and A. Dantan, Phys. Rev. Lett., \\textbf{109}, 223601, (2012)], the intracavity linear optomechanical coupling can be considerably enhanced over the single element value in the so-called \\textit{transmissive regime}, where for motionless membranes the whole system is transparent to light. Here, we extend these investigations to quasi-periodic arrays in the presence of engineered spatial defects in the membrane positions. In particular we show that the localization of light modes induced by the defect combined with the access of the transmissive regime window can lead to additional enhancement of the strength of both linear and quadratic optomechanical couplings.

  1. NREL: Transmission Grid Integration - Wholesale Electricity Market

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for Renewable Energy: Grid IntegrationReportTransmission Planning andStudy Phase

  2. NREL: Transmission Grid Integration - Working With Us

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for Renewable Energy: Grid IntegrationReportTransmission Planning andStudy

  3. NREL: Transmission Grid Integration Home Page

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for Renewable Energy: Grid IntegrationReportTransmission Planning andStudyPhoto of

  4. Mode conversation losses in overmolded millimeter wave transmission lines

    E-Print Network [OSTI]

    Tax, David S. (David Samuel)

    2008-01-01T23:59:59.000Z

    Millimeter wave transmission lines are integral components for many important applications like nuclear fusion and NMR spectroscopy. In low loss corrugated transmission lines propagating the HE,1 mode with a high waveguide ...

  5. EIS-0421: Big Eddy-Knight Transmission Line

    Broader source: Energy.gov [DOE]

    BPA is proposing to build a new 500 kilovolt (kV) transmission line in Wasco County, Oregon and Klickitat County, Washington and a new substation in Klickitat County. The new BPA transmission line...

  6. Biennial Assessment of the Fifth Power Plan Transmission Issues

    E-Print Network [OSTI]

    unscheduled electricity flows over transmission lines leading to increased risks to electric system by the partners in the Colstrip 500 kV transmission lines (Northwestern Energy, Puget Sound Energy, Portland

  7. Statistical Image Reconstruction Algorithms Using Paraboloidal Surrogates for PET Transmission

    E-Print Network [OSTI]

    Fessler, Jeffrey A.

    Statistical Image Reconstruction Algorithms Using Paraboloidal Surrogates for PET Transmission Reconstruction Algorithms Using Paraboloidal Surrogates for PET Transmission Scans by Hakan Erdogan Chair: Jeffrey A. Fessler Positron Emission Tomography (PET) is a diagnostic imaging tool that provides images

  8. 20% Wind Energy by 2030 - Chapter 4: Transmission and Integration...

    Energy Savers [EERE]

    4: Transmission and Integration into the U.S. Electric System Summary Slides 20% Wind Energy by 2030 - Chapter 4: Transmission and Integration into the U.S. Electric System Summary...

  9. Forced cooling of underground electric power transmission lines : design manual

    E-Print Network [OSTI]

    Brown, Jay A.

    1978-01-01T23:59:59.000Z

    The methodology utilized for the design of a forced-cooled pipe-type underground transmission system is presented. The material is divided into three major parts: (1) The Forced-cooled Pipe-Type Underground Transmission ...

  10. An improved speech transmission index for intelligibility prediction Belinda Schwerin

    E-Print Network [OSTI]

    transmission index; Modulation transfer function; Speech enhancement; Objective evaluation; Speech intelligibility; Short-time modulation spectrum 1. Introduction The enhancement of speech corrupted by noise hasAn improved speech transmission index for intelligibility prediction Belinda Schwerin , Kuldip

  11. Electric Transmission One Year after the Energy Bill

    SciTech Connect (OSTI)

    Gray, Ed

    2006-08-15T23:59:59.000Z

    The Energy Policy Act of 2005 embodies numerous provisions that will increase investment in the electric transmission grid. Many actions have occurred in the first year of implementation that should strengthen the transmission system in the United States. (author)

  12. Sandia National Laboratories: long-distance power transmission

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    grid relies on power transmission from the production source-be it a coal-fired plant, solar array, or wind farm-to the consumer. Long-distance transmission results in...

  13. Transmission System Performance Analysis for High-Penetration Photovoltaics

    SciTech Connect (OSTI)

    Achilles, S.; Schramm, S.; Bebic, J.

    2008-02-01T23:59:59.000Z

    This study is an assessment of the potential impact of high levels of penetration of photovoltaic (PV) generation on transmission systems. The effort used stability simulations of a transmission system with different levels of PV generation and load.

  14. Investigation of Multi-Frequency Power Transmission and System

    E-Print Network [OSTI]

    Barazarte Conte, Ronald

    2012-10-19T23:59:59.000Z

    This dissertation presents a new power system transmission concept based on frequency selectivity named Multi-Frequency Power System (MFPS). This system allows for selective power transmission among terminals in an interconnected system...

  15. 1996 Wholesale Power and Transmission Rate Schedules.

    SciTech Connect (OSTI)

    United States. Bonneville Power Administration.

    1996-10-01T23:59:59.000Z

    Bonneville Power Administration`s (BPA) 1996 Wholesale Power Rate Schedules, 1996 Ancillary Products and Services Rate Schedule, 1996 Transmission Rate Schedules, and General Rate Schedule Provisions, contained herein, were approved on an interim basis effective October 1, 1996. These rate schedules and provisions were approved by the Federal Energy Regulatory Commission (FERC), United States Department of Energy, in September 1996 (Docket Nos EF96-2011-000 and EF96f-2021-000). These rate schedules and General Rate Schedule Provisions were approved on a final basis by the FERC July 30, 1997, in Dept. of Energy--Bonneville Power Administration, Docket Nos. EF96-2011-000 and EF96-2021-000. Except as noted elsewhere, these 1996 rate schedules and provisions supersede BPA`s Wholesale Power Rate Schedules and General Rate Schedule Provisions, and Transmission Rate Schedules and General Transmission Rate Schedule Provisions, effective October 1, 1995. These rate schedules and general rate schedule provisions include all errata.

  16. An Overview of the Operation of Ontario's Electricity Market

    E-Print Network [OSTI]

    Cańizares, Claudio A.

    1 An Overview of the Operation of Ontario's Electricity Market H. Zareipour, Student Member, IEEE electricity market, which opened on May 1, 2002, consists of physical markets for energy and operat- ing reserves as well as a financial market for transmission rights, administered by the Independent Electricity

  17. 30-MJ superconducting magnetic energy storage for BPA transmission-line stabilizer

    SciTech Connect (OSTI)

    Schermer, R.I.

    1981-01-01T23:59:59.000Z

    The Bonneville Power Administration operates the transmission system that joins the Pacific Northwest and southern California. A 30 MJ (8.4 kWh) superconducting Magnetic Energy Storage (SMES) unit with a 10 MW converter can provide system damping for low frequency oscillations. The unit is scheduled to operate in late 1982. Progress to date is described. The coil is complete. All major components of the electrical and cryogenic systems have been received and testing has begun. Computer control hardware is in place and software development is proceeding. Support system components and dewar lid are being fabricated and foundation design is complete. A contract for dewar fabrication is being negotiated.

  18. 30-MJ superconducting magnetic-energy storage for BPA transmission-line stabilizer

    SciTech Connect (OSTI)

    Schermer, R.I.

    1981-01-01T23:59:59.000Z

    The Bonneville Power Administration operates the transmission system that joins the Pacific Northwest and southern California. A 30 MJ (8.4 kWh) Superconducting Magnetic Energy Storage (SMES) unit with a 10 MW converter can provide system damping for low frequency oscillations. The unit is scheduled to operate in 1982. Progress during FY 81 is described. The coil is complete. All major components of the electrical and cryogenic systems have been received and testing has begun. Computer control hardware is in place and software development is proceeding. Support system components and dewar lid are being fabricated and foundation design is complete. A contract for dewar fabrication is being negotiated.

  19. Operations and compositions in transrecursive operators

    SciTech Connect (OSTI)

    Burgin, M.S.; Borodyanskii, Yu.M.

    1995-03-01T23:59:59.000Z

    The present study is a continuation of a study focusing on introduction and analysis of operations on transrecursive operators, which are similar to the operators considered in the theory of algorithms. Such operations may be standard product of algorithms) or special ({alpha}-disjunction and {alpha}-iteration. In some respects, these operations in the class of transrecursive operators are similar to their traditional analogs. In other respects, however, they are essentially different. For instance, they may have different types and modes. Specific features of operations on transrecursive operators are attributable to explicit omission of some restrictions on their construction compared with the construction of algorithms. The standard approaches to mathematical modeling of the concept of algorithm assume a number of essential restrictions. Specifically, they assume finiteness of (1) the input data arriving during a finite time interval; (2) the list of rules underlying the operations of the algorithm; (3) the transformations executed by a single operation; (4) the description of each rule; (5) the time to execute one operation; (6) the time to execute one operation; (7) the number of cycles that the algorithm executes in order to realize the mapping. In application to Turing machines, these restrictions imply finiteness of the initial word, finiteness of the command table of the read head, and ultimate stopping when the result is obtained after finitely many steps. Various classes of transrecursive operators are constructed by dropping various combinations of the {open_quotes}finiteness{close_quotes} restrictions. Two classes of transrecursive operators - the limit (inductive) Turing machines and transalgorithms - have been obtained by dropping respectively the assumption of finiteness of the number of execution cycles and the assumption of finiteness of the list of rules.

  20. Hybrid powertrain system including smooth shifting automated transmission

    DOE Patents [OSTI]

    Beaty, Kevin D.; Nellums, Richard A.

    2006-10-24T23:59:59.000Z

    A powertrain system is provided that includes a prime mover and a change-gear transmission having an input, at least two gear ratios, and an output. The powertrain system also includes a power shunt configured to route power applied to the transmission by one of the input and the output to the other one of the input and the output. A transmission system and a method for facilitating shifting of a transmission system are also provided.

  1. Transmission Project Reporting FPA 216h | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Disturbance Events Incident Reporting Emergency Situation Reports Energy Assurance Daily Transmission Project Reporting Library New Reports & Other Materials Meetings & Events...

  2. Operating Permits (New Jersey)

    Broader source: Energy.gov [DOE]

    The owner or operator of a facility subject to this article shall obtain and maintain an operating permit for the facility. The owner or operator of a facility subject to this article shall ensure...

  3. Reference: RGL 83-09 Subject: POWER TRANSMISSION LINES

    E-Print Network [OSTI]

    US Army Corps of Engineers

    Reference: RGL 83-09 Subject: POWER TRANSMISSION LINES Title: MARKING OF AERIAL POWER TRANSMISSION. 1. The marking of aerial power transmission lines, cables, and structures over the navigable waters LINES, CABLES, & STRUCTURES Issued: 07/13/83 Expires: 12/31/85 Originator: DAEN-CWO-N Description: ARMY

  4. Using Transmission Lines for Global On-Chip Communication

    E-Print Network [OSTI]

    Huang, Michael C.

    1 Using Transmission Lines for Global On-Chip Communication Aaron Carpenter, Jianyun Hu, Jie Xu-switched network-on-chip a less attractive option. An alternative solution uses well-engineered transmission lines as communication links. These transmission lines, along with simple, practical circuits using modern CMOS technol

  5. Asymmetric parametric amplification in nonlinear left-handed transmission lines

    E-Print Network [OSTI]

    Asymmetric parametric amplification in nonlinear left-handed transmission lines David A. Powell amplification in nonlinear left-handed transmission lines, which serve as model systems for nonlinear negative-handed regime. © 2009 American Institute of Physics. DOI: 10.1063/1.3089842 Left-handed transmission lines

  6. Multifrequency Wilkinson Power Divider Using Microstrip Nonuniform Transmission Lines

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    Multifrequency Wilkinson Power Divider Using Microstrip Nonuniform Transmission Lines Mohammad desired frequencies. The proposed structure contains two Microstrip Nonuniform Transmission Lines (MNTLs­6] and using composite right/left-handed transmission line (CRLH) [7]. The main disadvantage of multistage

  7. New approach for modelling distributed MEMS transmission lines

    E-Print Network [OSTI]

    Akin, Tayfun

    New approach for modelling distributed MEMS transmission lines K. Topalli, M. Unlu, S. Demir, O for the distributed MEMS transmission line (DMTL) structures. In this new model, the MEMS bridges that are used as the loading elements of the DMTL structures are represented as low-impedance transmission lines, rather than

  8. Empirical Analysis of Transmission Power Control Algorithms for Wireless

    E-Print Network [OSTI]

    California at Berkeley, University of

    Empirical Analysis of Transmission Power Control Algorithms for Wireless Sensor Networks CENTS sensor network testbed. #12;Related Work · Some number of works tried to adjust radio transmission power command in WSN. · Many-to-one · In-network processing. #12;Index · Description of transmission power

  9. Network Coding for Joint Storage and Transmission with Minimum Cost

    E-Print Network [OSTI]

    Jiang, Anxiao "Andrew"

    transmission and data storage in networks. Its power comes from the improved flexibility that codeword symbolsNetwork Coding for Joint Storage and Transmission with Minimum Cost Anxiao (Andrew) Jiang@cs.tamu.edu. Abstract-- Network coding provides elegant solutions to many data transmission problems. The usage

  10. Application of High-Angle Annular Dark Field Scanning Transmission

    E-Print Network [OSTI]

    Utsunomiya, Satoshi

    Transmission Electron Microscopy-Energy Dispersive X-ray Spectrometry, and Energy-Filtered Transmission field scanning transmission electron microscopy (HAADF-STEM), STEM-energy-dispersive X-ray spectrometry). Techniquesthatareusefulinanalyzingultrafineatmospheric particles, such as STEM, EELS (electron energy loss spec- trometry), AFM, and mass spectrometry

  11. Electricity generation with looped transmission networks: Bidding to an ISO

    E-Print Network [OSTI]

    Ferris, Michael C.

    on a transmission network from net generation nodes to net consumption nodes is governed by the Kirchoff Laws [45Electricity generation with looped transmission networks: Bidding to an ISO Xinmin Hu Daniel Ralph to model markets for delivery of electrical power on looped transmission networks. It analyzes

  12. EIS-0474: Southline Transmission Line Project; Arizona and New Mexico

    Broader source: Energy.gov [DOE]

    DOE’s Western Area Power Administration is preparing this EIS to evaluate the environmental impacts of the proposed Southline Transmission Project, which would consist of a new 225-mile transmission line between existing substations at Afton, New Mexico, and Apache, Arizona, and improvements to approximately 130 miles of existing transmission lines between the Apache and Saguaro, Arizona substations.

  13. Structural Optimization of High Voltage Transmission Line Towers considering

    E-Print Network [OSTI]

    Colominas, Ignasi

    Structural Optimization of High Voltage Transmission Line Towers considering Continuum and Discrete/or to common designs largely repeated (e.g. automotive compo- nents), and high voltage transmission towers can than conventional designs of high voltage transmission line towers. The optimization model proposed

  14. Classification of the Visual Landscape for Transmission Planning1

    E-Print Network [OSTI]

    Standiford, Richard B.

    . The third concept is that the specific design of transmission towers can result in a negative re- sponseClassification of the Visual Landscape for Transmission Planning1 Curtis Miller2/ , Nargis Jetha3 can be made of the visual change to the landscape due to the introduction of transmission facilities

  15. Transmission and Generation Investment In a Competitive Electric Power Industry

    E-Print Network [OSTI]

    California at Berkeley. University of

    .3 Transmission Property Rights and Congestion Contracts . . . . . . . . . . . . . . . . . 7 2.4 How TransmissionPWP-030 Transmission and Generation Investment In a Competitive Electric Power Industry James of California Energy Institute 2539 Channing Way Berkeley, California 94720-5180 www.ucei.berkeley.edu/ucei #12

  16. EIS-0390: Eastern Plains Transmission Project, Colorado and Kansas.

    Broader source: Energy.gov [DOE]

    This EIS is for Western Area Power Administration's proposal to participate with Tri-State Generation and Transmission Association, Inc. (Tri-State), to construct the proposed Eastern Plains Transmission Project (Project). Western’s participation with Tri-State would be in exchange for capacity rights on the transmission lines.

  17. Heat Transfer Operators Associated with Quantum Operations

    E-Print Network [OSTI]

    Ç. Aksak; S. Turgut

    2011-04-14T23:59:59.000Z

    Any quantum operation applied on a physical system is performed as a unitary transformation on a larger extended system. If the extension used is a heat bath in thermal equilibrium, the concomitant change in the state of the bath necessarily implies a heat exchange with it. The dependence of the average heat transferred to the bath on the initial state of the system can then be found from the expectation value of a hermitian operator, which is named as the heat transfer operator (HTO). The purpose of this article is the investigation of the relation between the HTOs and the associated quantum operations. Since, any given quantum operation on a system can be realized by different baths and unitaries, many different HTOs are possible for each quantum operation. On the other hand, there are also strong restrictions on the HTOs which arise from the unitarity of the transformations. The most important of these is the Landauer erasure principle. This article is concerned with the question of finding a complete set of restrictions on the HTOs that are associated with a given quantum operation. An answer to this question has been found only for a subset of quantum operations. For erasure operations, these characterizations are equivalent to the generalized Landauer erasure principle. For the case of generic quantum operations however, it appears that the HTOs obey further restrictions which cannot be obtained from the entropic restrictions of the generalized Landauer erasure principle.

  18. Building Operator Certification

    E-Print Network [OSTI]

    Lilley, D.

    2013-01-01T23:59:59.000Z

    Building Operator Certification Energy Efficiency through Operator Training CATEE December 18, 2013 – San Antonio, TX Dennis Lilley, CEM, PMP ESL-KT-13-12-49 CATEE 2013: Clean Air Through Energy Efficiency Conference, San Antonio, Texas Dec. 16...-18 Building Operator Certification Energy Efficiency through Operator Training What is Building Operator Certification? Industry-recognized credential in energy efficient building operation practices Created with 100 industry experts Launched in 1996 9...

  19. Operation and Maintenance

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations and Maintenance Operations OASIS: WALC-DSW (Note: this site is not hosted by Western and requires a digital certificate and login for full access.) Contact Information...

  20. Operations Information for Studies

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations Information for Studies This page contains historical information about hydropower operations. Reclamation UC Region 24-Month Studies FY2009 Load Information (pdf) SLIP...

  1. Operations Cost Allocation Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations Consolidation Project Operations Consolidation Project (OCP) Cost Allocation Presentation - September 20, 2011 OCP Cost Allocation Customer Presentation List of Acronyms...

  2. Operations Research Analyst

    Broader source: Energy.gov [DOE]

    The incumbent in this position will serve as an Operations Research Analyst in the Generation Scheduling (PGS). The Operations Research Analyst is responsible for analytical work that involves...

  3. Capturing the cloud of MRSA diversity after transmission and during infection 2 reveals complex and heterogenous carriage and transmission

    E-Print Network [OSTI]

    Paterson, Gavin K.; Harrison, Ewan M.; Murray, Gemma G.R.; Welch, John J.; Warland, James H.; Holden, Matthew T.G.; Morgan, Fiona J.E.; Ba, Xiaoliang; Koop, Gerrit; Harris, Simon R.; Maskell, Duncan J.; Peacock, Sharon J.; Herrtage, Michael E.; Parkhill, Julian; Holmes, Mark A.

    2015-01-01T23:59:59.000Z

    1 Capturing the cloud of MRSA diversity after transmission and during infection 1 reveals complex and heterogenous carriage and transmission 2 3 Running title: MRSA tracking and the cloud of diversity 4 5 Gavin K. Paterson 1#¶, Ewan M... transmission event. To 55 further understand the cloud of diversity that exists within colonized individuals and 56 5 during transmission, we undertook deep sequencing of a methicillin-resistant S. aureus 57 (MRSA) ‘outbreak’ at a veterinary hospital...

  4. Evaluation of a EMCCD detector for emission-transmission computed tomography

    E-Print Network [OSTI]

    Teo, B K; Shestakova, I; Sun, M; Barber, W C; Nagarkar, V V; Hasegawa, B H

    2006-01-01T23:59:59.000Z

    emission-transmission computed-tomography imaging system,”for Emission-Transmission Computed Tomography B. K. Teo, I.sion-transmission computed tomography. The detector has an

  5. Tucson Electric Power Company Sahuarita-Nogales Transmission Line Draft Environmental Impact Statement

    SciTech Connect (OSTI)

    N /A

    2003-08-27T23:59:59.000Z

    Tucson Electric Power Company (TEP) has applied to the U.S. Department of Energy (DOE) for a Presidential Permit to construct and operate a double-circuit, 345,000-volt (345-kV) electric transmission line across the United States border with Mexico. Under Executive Order (EO) 10485 of September 3, 1953, as amended by EO 12038 of February 3, 1978, a Presidential Permit is required to construct, connect, operate, or maintain facilities at the U.S. international border for the transmission of electric energy between the United States and a foreign country. DOE has determined that the issuance of a Presidential Permit to TEP for the proposed project would constitute a major Federal action that may have a significant impact on the environment within the meaning of the ''National Environmental Policy Act of 1969'' (NEPA) 42 United States Code (U.S.C.) {section}4321 et seq. For this reason, DOE has prepared this Draft Environmental Impact Statement (EIS) to evaluate potential environmental impacts from the proposed Federal action (granting a Presidential Permit for the proposed transmission facilities) and reasonable alternatives, including the No Action Alternative. This EIS was prepared in accordance with Section 102(2)(c) of NEPA, Council of Environmental Quality (CEQ) regulations (40 Code of Federal Regulations [CFR] 1500-1508), and DOE NEPA Implementing Procedures (10 CFR 1021). DOE is the lead Federal Agency, as defined by 40 CFR 1501.5. The U.S. Department of Agriculture Forest Service (USFS), the Bureau of Land Management (BLM) of the U.S. Department of the Interior, and the U.S. Section of the International Boundary and Water Commission, U.S. and Mexico (USIBWC), are cooperating agencies. Each of these organizations will use the EIS for its own NEPA purposes, as described in the Federal Agencies' Purpose and Need and Authorizing Actions section of this summary. The 345-kV double-circuit transmission line would consist of twelve transmission line wires, or conductors, and two neutral ground wires that would provide both lightning protection and fiber optic communications, on a single set of support structures. The transmission line would originate at TEP's existing South Substation (which TEP would expand), in the vicinity of Sahuarita, Arizona, and interconnect with the Citizens Communications (Citizens) system at a Gateway Substation that TEP would construct west of Nogales, Arizona. The double-circuit transmission line would continue from the Gateway Substation south to cross the U.S.-Mexico border and extend approximately 60 miles (mi) (98 kilometers [km]) into the Sonoran region of Mexico, connecting with the Comision Federal de Electricidad (CFE, the national electric utility of Mexico) at CFE's Santa Ana Substation.

  6. Method for bonding a transmission line to a downhole tool

    DOE Patents [OSTI]

    Hall, David R. (Provo, UT); Fox, Joe (Spanish Fork, UT)

    2007-11-06T23:59:59.000Z

    An apparatus for bonding a transmission line to the central bore of a downhole tool includes a pre-formed interface for bonding a transmission line to the inside diameter of a downhole tool. The pre-formed interface includes a first surface that substantially conforms to the outside contour of a transmission line and a second surface that substantially conforms to the inside diameter of a downhole tool. In another aspect of the invention, a method for bonding a transmission line to the inside diameter of a downhole tool includes positioning a transmission line near the inside wall of a downhole tool and placing a mold near the transmission line and the inside wall. The method further includes injecting a bonding material into the mold and curing the bonding material such that the bonding material bonds the transmission line to the inside wall.

  7. NUCLEAR PLANT OPERATIONS AND

    E-Print Network [OSTI]

    Pázsit, Imre

    NUCLEAR PLANT OPERATIONS AND CONTROL KEYWORDS: neutron flux, cur- rent noise, vibration diagnostics: Swedish Nuclear Powe

  8. OPERATIONS MANAGEMENT Spring 2008

    E-Print Network [OSTI]

    Almor, Amit

    the operations and supply chain strategy. This survey course in operations management introduces students1 MGSC 395 OPERATIONS MANAGEMENT Spring 2008 Course Syllabus Instructor: Professor Anand Nair Class MATERIALS Required Text Books Textbook: Krajewski, Lee, Ritzman, Larry, and Malhotra, Manoj. Operations

  9. Ponderomotive phase plate for transmission electron microscopes

    DOE Patents [OSTI]

    Reed, Bryan W. (Livermore, CA)

    2012-07-10T23:59:59.000Z

    A ponderomotive phase plate system and method for controllably producing highly tunable phase contrast transfer functions in a transmission electron microscope (TEM) for high resolution and biological phase contrast imaging. The system and method includes a laser source and a beam transport system to produce a focused laser crossover as a phase plate, so that a ponderomotive potential of the focused laser crossover produces a scattering-angle-dependent phase shift in the electrons of the post-sample electron beam corresponding to a desired phase contrast transfer function.

  10. The year in review: Electric transmission

    SciTech Connect (OSTI)

    Hebert, C. Jr.

    1999-12-01T23:59:59.000Z

    This writing and the comments contained herein support the conclusion that mandating a solution to transmission woes is not the proper choice. Even if it were the right choice, it would not be the way to go. FERC exists in a sophisticated energy world and must comprehend that without the help of the energy industry it is doomed to fail. Technology changes, economies change, and even the FERC itself changes, and will again. This is all part of the energy journey. RTOs, pools, ISOs, RTOs, and, yes, Transcos are a part of the evolution of energy regulation and perhaps deregulation to some degree.

  11. California/Transmission/Summary | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:EzfeedflagBiomassSustainableCSL Gas RecoveryInformationTransmission Permitting at a Glance

  12. Transmission SEAB Presentation | Department of Energy

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOn April 23,EnergyChicopeeTechnologyfact sheetTransferring the Wayne, NJ,Know?'Transmission

  13. Eldorado Ivanpah Transmission Project | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand JumpConceptual Model,DOEHazel Crest, Illinois:EdinburghEldorado Ivanpah Transmission Project Jump to:

  14. Richard Shaheen named Senior VP of Transmission

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's PossibleRadiation Protection TechnicalResonant SoftRichard-Shaheen-named-Senior-VP-of-Transmission

  15. American Transmission Systems Inc | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are being directedAnnualProperty EditCalifornia: Energy Resources Jump to:Almo,Transmission Systems Inc Jump to:

  16. NREL: Transmission Grid Integration - Wind Integration Datasets

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for Renewable Energy: Grid IntegrationReportTransmission Planning andStudy PhaseWind

  17. Transmission Capital Limited | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand Jump to:Ezfeedflag JumpID-f <MaintainedInformationThePtyTownTrama TecnoTransmission Capital

  18. Gateway West Transmission Line | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdf Jump1946865°,Park, Texas: EnergyGarvin County,|GasconadeOhio:Gateway

  19. Georgia Transmission Corp | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are8COaBulkTransmissionSitingProcess.pdf Jump1946865°,Park,2005) | Open

  20. Transmission/Nepa Database | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere IRaghuraji Agro IndustriesTown of Ladoga, Indiana (Utility Company) JumpTradeWindPrepared asTransmissionNepa

  1. Transmission/Resource Library | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere IRaghuraji Agro IndustriesTown of Ladoga, Indiana (Utility Company)Library < Transmission Jump to:

  2. Performance and economic comparison between point-to-point HVDC transmission and hybrid back-to-back HVDC/AC transmissions

    SciTech Connect (OSTI)

    Hammad, A.E. (ABB, Asea Brown Boveri Ltd., Baden (CH)); Long, W.F. (Wisconsin Univ., Madison, WI (USA))

    1990-04-01T23:59:59.000Z

    Two alternative schemes to interconnect asynchronous or independent ac systems by a limited capacity link are presented. The first alternative is a conventional point-to-point HVDC transmission system; the second alternative comprises an ac line terminated by an HVDC back- to-back link. Technical and operational properties of both schemes are illustrated with emphasis on var regulation capability and control flexibility to improve the overall performance of the interconnected ac systems. Cost comparisons for the principal components of the two alternatives are made. A brief description of two existing HVDC installations is given to demonstrate the practical implementation of the considered schemes.

  3. Operator pencil passing through a given operator

    SciTech Connect (OSTI)

    Biggs, A., E-mail: khudian@manchester.ac.uk, E-mail: adam.biggs@student.manchester.ac.uk; Khudaverdian, H. M., E-mail: khudian@manchester.ac.uk, E-mail: adam.biggs@student.manchester.ac.uk [School of Mathematics, University of Manchester, Oxford Road, Manchester M13 9PL (United Kingdom)

    2013-12-15T23:59:59.000Z

    Let ? be a linear differential operator acting on the space of densities of a given weight ?{sub 0} on a manifold M. One can consider a pencil of operators ?-circumflex(?)=(?{sub ?}) passing through the operator ? such that any ?{sub ?} is a linear differential operator acting on densities of weight ?. This pencil can be identified with a linear differential operator ?-circumflex acting on the algebra of densities of all weights. The existence of an invariant scalar product in the algebra of densities implies a natural decomposition of operators, i.e., pencils of self-adjoint and anti-self-adjoint operators. We study lifting maps that are on one hand equivariant with respect to divergenceless vector fields, and, on the other hand, with values in self-adjoint or anti-self-adjoint operators. In particular, we analyze the relation between these two concepts, and apply it to the study of diff?(M)-equivariant liftings. Finally, we briefly consider the case of liftings equivariant with respect to the algebra of projective transformations and describe all regular self-adjoint and anti-self-adjoint liftings. Our constructions can be considered as a generalisation of equivariant quantisation.

  4. Renewable Resource Integration Project - Scoping Study of Strategic Transmission, Operations, and Reliability Issues

    E-Print Network [OSTI]

    Budhraja, Vikram

    2008-01-01T23:59:59.000Z

    May 30, 2008.  California Power Plant Database,  [http://Energy Commission California Power Plant Database; 2006 of  aging power plant generation in the Southern California 

  5. Renewable Resource Integration Project - Scoping Study of Strategic Transmission, Operations, and Reliability Issues

    E-Print Network [OSTI]

    Budhraja, Vikram

    2008-01-01T23:59:59.000Z

    The 20,000 MW of renewable resources to be developed will greater utilization of renewable  resources and meeting the of renewable resources. ..16 Table 8.

  6. Renewable Resource Integration Project - Scoping Study of Strategic Transmission, Operations, and Reliability Issues

    E-Print Network [OSTI]

    Budhraja, Vikram

    2008-01-01T23:59:59.000Z

    Devers,  Antelope and Vincent; solar thermal at Lugo; and scale  development of wind, solar thermal, and geothermal within load centers.   Solar Thermal—7,000 MW total, with 

  7. Renewable Resource Integration Project - Scoping Study of Strategic Transmission, Operations, and Reliability Issues

    E-Print Network [OSTI]

    Budhraja, Vikram

    2008-01-01T23:59:59.000Z

    in 2020.   Table 4. Renewable Energy and Capacity—200612 Table 4. Renewable Energy and Capacity—2006 Recorded,In-State Renewable energy and capacity requirements for 20% 

  8. On the Efficiency of the New York Independent System Operator Market for Transmission

    E-Print Network [OSTI]

    947208061, USA.; Emily S. Bartholomew, Senior Research Associate, Electricity Market Studies, Environmental-8061, USA, Chris Marnay, Staff Scientist, Electricity Market Studies, Environmental Energy Technologies of California, Berkeley, CA 94720, USA. Abstract The physical nature of electricity generation and delivery

  9. Renewable Resource Integration Project - Scoping Study of Strategic Transmission, Operations, and Reliability Issues

    E-Print Network [OSTI]

    Budhraja, Vikram

    2008-01-01T23:59:59.000Z

    13 Table 6. 2006 Renewable Energy & Estimated Requirementsin 2020.   Table 4. Renewable Energy and Capacity—2006for transfer of renewable energy from the L.A.  Basin  Area 

  10. Distributed generation and demand side management : applications to transmission system operation 

    E-Print Network [OSTI]

    Hayes, Barry Patrick

    2013-07-01T23:59:59.000Z

    Electricity networks are undergoing a period of rapid change and transformation, with increased penetration levels of renewable-based distributed generation, and new influences on electricity end-use patterns from ...

  11. Renewable Resource Integration Project - Scoping Study of Strategic Transmission, Operations, and Reliability Issues

    E-Print Network [OSTI]

    Budhraja, Vikram

    2008-01-01T23:59:59.000Z

    production level from small hydro as recorded in 2006.  kWH Geothermal Biomass Small Hydro 830 est Wind Solar TotalRPS Geothermal Biomass Small Hydro 830 est Wind Solar Total

  12. Renewable Resource Integration Project - Scoping Study of Strategic Transmission, Operations, and Reliability Issues

    E-Print Network [OSTI]

    Budhraja, Vikram

    2008-01-01T23:59:59.000Z

    Energy Policy Report 2007 Commission Final Report.   2030 capacity estimates  for wind and Policy Report 2007 Commission Final Report; Energy based on assumed  capacity factors: 90% for geothermal and biomass; 30% for wind and 

  13. EA-1982: Parker-Davis Transmission System Routine Operation and Maintenance

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy China U.S.ContaminationJuly 2011DDelphiFEA-2013.pdfBasedTheCounty, Idaho |

  14. Final environmental impact statement, Washington Water Power/B.C. Hydro Transmission Interconnection Project

    SciTech Connect (OSTI)

    Not Available

    1992-10-01T23:59:59.000Z

    Washington Water Power (WWP) proposes to construct and operate an electric transmission line that would connect with the electrical system of the British Columbia Hydro and Power Authority (B.C. Hydro). The project would be composed of a double-circuit, 230-kilovolt (kV) transmission line from WWP`s existing Beacon Substation located northeast of Spokane, Washington to the international border located northwest of Metaline Falls, Washington. The original Presidential permit application and associated proposed route presented in the draft environmental impact statement (DEIS) have been modified to terminate at the Beacon Substation, instead of WWP`s initially proposed termination point at the planned Marshall Substation located southwest of Spokane. A supplemental draft EIS was prepared and submitted for review to not only examine the new proposed 5.6 miles of route, but to also compare the new Proposed Route to the other alternatives previously analyzed in the DEIS. This final EIS (FEIS) assesses the environmental effects of the proposed transmission line through construction, operation, maintenance, and abandonment activities and addresses the impacts associated with the Proposed Action, Eastern Alternative, Western Alternative, Northern Crossover Alternative, Southern Crossover Alternative, and No Action Alternative. The FEIS also contains the comments received and the responses to these comments submitted on the DEIS and Supplemental DEIS.

  15. Femtosecond Operation of the LCLS for User Experiments

    SciTech Connect (OSTI)

    Frisch, Josef; /SLAC; Bostedt, Christoph; /SLAC; Bozek, John; /SLAC; Brachmann, Axel; /SLAC; Coffee, Ryan; /SLAC; Decker, Franz-Josef; /SLAC; Ding, Yuantao; /SLAC; Dowell, David; /SLAC; Emma, Paul; /SLAC; Gilevich, Sasha; /SLAC; Haller, Gunther; /SLAC; Hays, Gregory; /SLAC; Hering, Philippe; /SLAC; Hill, Bruce; /SLAC; Huang, Zhirong; /SLAC; Iverson, Richard /SLAC; Kanter, Elliot; /SLAC; Kraessig, Bertold; /SLAC; Loos, Henrik; /SLAC; Miahnahri, Alan; /SLAC; Nuhn, Heinz-Dieter; /SLAC /SLAC /SLAC /SLAC /SLAC /SLAC /SLAC /SLAC /SLAC /SLAC /SLAC /LBL, Berkeley; ,

    2010-09-02T23:59:59.000Z

    In addition to its normal operation at 250pC, the LCLS has operated with 20pC bunches delivering X-ray beams to users with energies between 800eV and 2 keV and with bunch lengths below 10 fs FWHM. A bunch arrival time monitor and timing transmission system provide users with sub 50 fs synchronization between a laser and the X-rays for pump/probe experiments. We describe the performance and operational experience of the LCLS for short bunch experiments.

  16. Moving Beyond Paralysis: How States and Regions Are Creating Innovative Transmission Projects; May 2009 - May 2010

    SciTech Connect (OSTI)

    Schumacher, A.; Fink, S.; Porter, K.

    2009-10-01T23:59:59.000Z

    This report profiles certain state and regional transmission policy initiatives aimed at promoting transmission development, mainly to access renewable resources.

  17. Exploration of Resource and Transmission Expansion Decisions in the Western Renewable Energy Zone Initiative

    E-Print Network [OSTI]

    Mills, Andrew

    2010-01-01T23:59:59.000Z

    based on existing transmission corridors or rights of way.The transmission costs also include right-of-way costs,

  18. Integrated Retail and Wholesale Power System Operation with Smart-Grid Functionality

    E-Print Network [OSTI]

    Tesfatsion, Leigh

    1 Integrated Retail and Wholesale Power System Operation with Smart-Grid Functionality Dionysios of retail and wholesale power markets operating over transmission and distribution networks with smart-grid functionality. This test bed seams together two existing test beds, the AMES Wholesale Power Market Test Bed

  19. Optimal Power Control for Concurrent Transmissions of Location-aware Mobile Cognitive Radio Ad Hoc Networks

    E-Print Network [OSTI]

    Song, Yi

    2011-01-01T23:59:59.000Z

    In a cognitive radio (CR) network, CR users intend to operate over the same spectrum band licensed to legacy networks. A tradeoff exists between protecting the communications in legacy networks and maximizing the throughput of CR transmissions, especially when CR links are unstable due to the mobility of CR users. Because of the non-zero probability of false detection and implementation complexity of spectrum sensing, in this paper, we investigate a sensing-free spectrum sharing scenario for mobile CR ad hoc networks to improve the frequency reuse by incorporating the location awareness capability in CR networks. We propose an optimal power control algorithm for the CR transmitter to maximize the concurrent transmission region of CR users especially in mobile scenarios. Under the proposed power control algorithm, the mobile CR network achieves maximized throughput without causing harmful interference to primary users in the legacy network. Simulation results show that the proposed optimal power control algori...

  20. Power Transmission From The ITER Model Negative Ion Source

    SciTech Connect (OSTI)

    Boilson, D. [Association EURATOM-DCU, PRL/NCPST, Glasnevin, Dublin 13 (Ireland); Esch, H. P. L. de; Grand, C.; Hemsworth, R. S.; Krylov, A. [Association EURATOM-CEA, CEA/DSM/DRFC, CEA-Cadarache, 13108 St Paul-Lez-Durance (France)

    2007-08-10T23:59:59.000Z

    In Cadarache development on negative ion sources is being carried out on the KAMABOKO III ion source on the MANTIS test bed. This is a model of the ion source designed for the neutral beam injectors of ITER. This ion source has been developed in collaboration with JAERI, Japan, who also designed and supplied the ion source. Its target performance is to accelerate a D- beam, with a current density of 200 A/m2 and <1 electron extracted per accelerated D- ion, at a source filling pressure of 0.3 Pa. For ITER a continuous ion beam must be assured for pulse lengths of 1000 s, but beams of up to 3,600 s are also envisaged. The ion source is attached to a 3 grid 30 keV accelerator (also supplied by JAERI) and the accelerated negative ion current is determined from the energy deposited on a calorimeter. During long pulse operation ({<=}1000 s) it was found that the current density of both D- and H- beams, measured at the calorimeter was lower than expected and that a large discrepancy existed between the accelerated currents measured electrically and those transmitted to the calorimeter. The possibility that this discrepancy arose because the accelerated current included electrons (which would not be able to reach the calorimeter) was investigated and subsequently eliminated. Further studies have shown that the fraction of the electrical current reaching the calorimeter varies with the pulse length, which led to the suggestion that one or more of the accelerator grids were distorting due to the incident power during operation, leading to a progressive deterioration in the beam quality.. New extraction and acceleration grids have been designed and installed, which should have a better tolerance to thermal loads than those previously used. This paper describes the measurements of the power transmission and distribution using these grids.

  1. Wild Horse 69-kV transmission line environmental assessment

    SciTech Connect (OSTI)

    NONE

    1996-12-01T23:59:59.000Z

    Hill County Electric Cooperative Inc. (Hill County) proposes to construct and operate a 69-kV transmission line from its North Gildford Substation in Montana north to the Canadian border. A vicinity project area map is enclosed as a figure. TransCanada Power Corporation (TCP), a Canadian power-marketing company, will own and construct the connecting 69-kV line from the international border to Express Pipeline`s pump station at Wild Horse, Alberta. This Environmental Assessment is prepared for the Department of Energy (DOE) as lead federal agency to comply with the requirements of the National Environmental Policy Act (NEPA), as part of DOE`s review and approval process of the applications filed by Hill County for a DOE Presidential Permit and License to Export Electricity to a foreign country. The purpose of the proposed line is to supply electric energy to a crude oil pump station in Canada, owned by Express Pipeline Ltd. (Express). The pipeline would transport Canadian-produced oil from Hardisty, Alberta, Canada, to Caster, Wyoming. The Express Pipeline is scheduled to be constructed in 1996--97 and will supply crude oil to refineries in Wyoming and the midwest.

  2. Radio frequency communication system utilizing radiating transmission lines

    DOE Patents [OSTI]

    Struven, Warren C. (San Carlos, CA)

    1984-01-01T23:59:59.000Z

    A radio communication system for use in tunnels, mines, buildings or other shielded locations in which a pair of radiating transmission lines (30), (31) extend through such location in spaced coextensive relation to each other. Each transmission line (30), (31) has at least one unidirectional amplifier (32), (33) interposed therein with the sense of the unidirectional amplifier (32) of one transmission line (30) being opposite to the sense of the unidirectional amplifier (33) of the other transmission line (31). Each of the amplifiers (32), (33) has a gain which is less than the coupling loss between the transmission lines (30), (31). Two or more mobile transceivers (35) in the location served by the system are coupled to the transmission lines (30), (31) by electromagnetic wave propagation in space in order to communicate directly with each other at a given radio frequency within the frequency range of the system.

  3. 30-MJ superconducting magnetic energy storage for electric-transmission stabilization

    SciTech Connect (OSTI)

    Turner, R.D.; Rogers, J.D.

    1981-01-01T23:59:59.000Z

    The Bonneville Power Administration operates the electric power transmission system that connects the Pacific Northwest and southern California. The HVAC interties develop 0.35 Hz oscillations when the lines are heavily loaded. A 30 MJ (8.4 kWh) Superconducting Magnetic Energy Storage (SMES) unit with a 10 MW converter can provide system damping for the oscillation. The unit is scheduled for installation in 1982 and operation in 1982-83. Status of the project is described. The conductor has been fully tested electrically and mechanically and the 5 kA superconducting cable has been produced. The 30 MJ superconducting coil is essentially complete. All major components of the electrical and cryogenic systems except the nonconducting dewar have been completed. The refrigerator and converter are undergoing tests. The system is to be located at the BPA Tacoma Substation and operated by microwave link from Portland, OR.

  4. Multi-transmission-line-beam interactive system

    SciTech Connect (OSTI)

    Figotin, Alexander; Reyes, Guillermo [Department of Mathematics, University of California at Irvine, Irvine, California 92697-3875 (United States)] [Department of Mathematics, University of California at Irvine, Irvine, California 92697-3875 (United States)

    2013-11-15T23:59:59.000Z

    We construct here a Lagrangian field formulation for a system consisting of an electron beam interacting with a slow-wave structure modeled by a possibly non-uniform multiple transmission line (MTL). In the case of a single line we recover the linear model of a traveling wave tube due to J. R. Pierce. Since a properly chosen MTL can approximate a real waveguide structure with any desired accuracy, the proposed model can be used in particular for design optimization. Furthermore, the Lagrangian formulation provides: (i) a clear identification of the mathematical source of amplification, (ii) exact expressions for the conserved energy and its flux distributions obtained from the Noether theorem. In the case of uniform MTLs we carry out an exhaustive analysis of eigenmodes and find sharp conditions on the parameters of the system to provide for amplifying regimes.

  5. Nonlinear transmission line based electron beam driver

    SciTech Connect (OSTI)

    French, David M.; Hoff, Brad W.; Tang Wilkin; Heidger, Susan; Shiffler, Don [Directed Energy Directorate, Air Force Research Laboratory, Kirtland AFB, New Mexico 87117 (United States); Allen-Flowers, Jordan [Program in Applied Mathematics, University of Arizona, Tucson, Arizona 85721 (United States)

    2012-12-15T23:59:59.000Z

    Gated field emission cathodes can provide short electron pulses without the requirement of laser systems or cathode heating required by photoemission or thermionic cathodes. The large electric field requirement for field emission to take place can be achieved by using a high aspect ratio cathode with a large field enhancement factor which reduces the voltage requirement for emission. In this paper, a cathode gate driver based on the output pulse train from a nonlinear transmission line is experimentally demonstrated. The application of the pulse train to a tufted carbon fiber field emission cathode generates short electron pulses. The pulses are approximately 2 ns in duration with emission currents of several mA, and the train contains up to 6 pulses at a frequency of 100 MHz. Particle-in-cell simulation is used to predict the characteristic of the current pulse train generated from a single carbon fiber field emission cathode using the same technique.

  6. Giant vacuum forces via transmission lines

    E-Print Network [OSTI]

    Ephraim Shahmoon; Igor Mazets; Gershon Kurizki

    2014-07-23T23:59:59.000Z

    Quantum electromagnetic fluctuations induce forces between neutral particles, known as the van der Waals (vdW) and Casimir interactions. These fundamental forces, mediated by virtual photons from the vacuum, play an important role in basic physics and chemistry, and in emerging technologies involving, e.g. micro-electromechanical systems or quantum information processing. Here we show that these interactions can be enhanced by many orders of magnitude upon changing the character of the mediating vacuum-modes. By considering two polarizable particles in the vicinity of any standard electric transmission line, along which photons can propagate in one dimension (1d), we find a much stronger and longer-range interaction than in free-space. This enhancement may have profound implications on many-particle and bulk systems, and impact the quantum technologies mentioned above. The predicted giant vacuum force is estimated to be measurable in a coplanar waveguide line.

  7. QER Public Meeting: Petroleum Product Transmission & Distribution

    Broader source: Energy.gov [DOE]

    May 27, 2014 Public Meeting: Petroleum Product Transmission & Distribution (including CO2/EOR) On May 27, 2014, the DOE will hold a public meeting in New Orleans, Louisiana. The May 27, 2014 public meeting will feature facilitated panel discussions, followed by an open microphone session. Persons desiring to speak during the 6 open microphone session at the public meeting should come prepared to speak for no more than 3 minutes and will be accommodated on a first- come, first- serve basis, according to the order in which they register to speak on a sign-in sheet available at the meeting location, on the morning of the meeting. In advance of the meeting, DOE anticipates making publicly available a briefing memorandum providing useful background information regarding the topics under discussion at the meeting. DOE will post this memorandum on its website: http://energy.gov

  8. Boost type PWM HVDC transmission system

    SciTech Connect (OSTI)

    Ooi, B.T.; Wang, X. (McGill Univ., Montreal, PQ (Canada). Dept. of Electrical Engineering)

    1991-10-01T23:59:59.000Z

    This paper reports that conventional HVdc is built around the mercury arc rectifier or the thyristor which requires line commutation. The advances of fast, high power GTO's and future devices such as MCT's with turn off capabilities, are bringing PWM techniques within the range of HVdc applications. By combining PWM techniques to the boost type bridge topology, one has an alternate system of HVdc Transmission. On the ac side, the converter station has active controls over: the voltage amplitude, the voltage angle and the frequency. On the dc side, parallel connections facilitate multi-terminal load sharing by simple local controls so that redundant communication channels are not required. Bidirectional power through each station is accomplished by the reversal of the direction of dc current flow. These claims have been substantiated by experimental results from laboratory size multi-terminal models.

  9. GTO thyristor applications for HVDC transmission systems

    SciTech Connect (OSTI)

    Yamada, H.; Sampei, M. (Electric Power Development Co. Ltd., Tokyo (Japan)); Kashiwazaki, H.; Tanaka, C. (Hitachi Ltd., Tokyo (Japan)); Takahashi, T.; Horivchi, T. (Toshiba Corp., Tokyo (JP))

    1990-07-01T23:59:59.000Z

    The development of a large capacity gate turn off thyristor (GTO) has made it possible to manufacture self-commutated convertors employing GTO for power applications. In this paper, conceptual designs for convertor station equipment for a HVDC transmission system employing current as well as voltage source type GTO convertors (simply referred to as VSTGC and CSTGC) are presented. The study result indicates that the VSTGC is preferable over the CSTGC. Also presented in this paper is a preliminary economic comparison between two HVDC system alternatives for applying power to a weak ac system, one employing a self-commutated GTO convertor and the other employing a combination of line-commutated convertor and a synchronous condenser. The result indicates that the two HVDC convertor station alternatives cost about the same.

  10. Storage Ring Operation Modes

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Longitudinal bunch profile and Up: APS Storage Ring Parameters Previous: Source Parameter Table Storage Ring Operation Modes Standard Operating Mode, top-up Fill pattern: 102 mA in...

  11. Aerosol Sampler Operations Manual

    E-Print Network [OSTI]

    Fischer, Emily V.

    -1123 Laboratory FAX (916) 752-4107 Standard Operating Procedures Technical Information Document TI 201A #12;TI 201.................................................................................................................................................. 3 1.0 Weekly Maintenance ProceduresIMPROVE Aerosol Sampler Operations Manual February 10, 1997 Air Quality Group Crocker Nuclear

  12. Climate Data Operators (CDO)

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Climate Data Operators (CDO) Climate Data Operators (CDO) Description and Overview CDO is a large tool set for working on climate data. NetCDF 34, GRIB including SZIP compression,...

  13. Reservoir Operation in Texas

    E-Print Network [OSTI]

    Wurbs, Ralph A.

    management of the surface water resources of the various river basins of the state. The operation of these essential water control facilities is examined in this report. Reservoir operation is viewed here from the perspective of deciding how much water...

  14. SWPF Crane Lift Operation

    SciTech Connect (OSTI)

    None

    2010-01-01T23:59:59.000Z

    A multiple vview shot of the SWPF crane lift operation at the Savannah River Site. Funded by the Recovery Act.

  15. The Integrity of ACSR Full Tension Single-Stage Splice Connector at Higher Operation Temperature

    SciTech Connect (OSTI)

    Wang, Jy-An John [ORNL; Lara-Curzio, Edgar [ORNL; King Jr, Thomas J [ORNL

    2008-10-01T23:59:59.000Z

    Due to increases in power demand and limited investment in new infrastructure, existing overhead power transmission lines often need to operate at temperatures higher than those used for the original design criteria. This has led to the accelerated aging and degradation of splice connectors. It is manifested by the formation of hot-spots that have been revealed by infrared imaging during inspection. The implications of connector aging is two-fold: (1) significant increases in resistivity of the splice connector (i.e., less efficient transmission of electricity) and (2) significant reductions in the connector clamping strength, which could ultimately result in separation of the power transmission line at the joint. Therefore, the splice connector appears to be the weakest link in electric power transmission lines. This report presents a protocol for integrating analytical and experimental approaches to evaluate the integrity of full tension single-stage splice connector assemblies and the associated effective lifetime at high operating temperature.

  16. Microsoft PowerPoint - WAPA Transmission Developments in NM ...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    NM, CO, WY, KS, ND, UT, SD & ID Tasked with planning and financing of transmission lines within their respective states RETA has the additional requirement that 30% of...

  17. DOE/EA-1366; Environmental Assessment Santiam-Bethel Transmission...

    Broader source: Energy.gov (indexed) [DOE]

    "Plans should designate sites of power generation and the location of electric transmission lines in areas intended to support desired levels of urban and rural development." The...

  18. Wind Integration, Transmission, and Resource Assessment andCharacteri...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    totaling more than 25 million for 41 projects focused on integration, transmission, and resource assessment and characterization. This report highlights each of these R&D...

  19. Report on Transmission Cost Allocation for RTOs and Others (Presentation)

    SciTech Connect (OSTI)

    Coles, L.; Porter, K.

    2011-05-01T23:59:59.000Z

    This presentation describes in summary fashion some present transmission cost allocation methods, especially as this relates to the development of utility-scale renewable power sources.

  20. Coordinating Interstate ElectricTransmission Siting: An Introduction...

    Broader source: Energy.gov (indexed) [DOE]

    the near future. While improved demand-side management (including energy effi ciency and demand response), bett er utilization of the existing transmission grid, and other...

  1. In-Situ Transmission Electron Microscopy Probing of Native Oxide...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Probing of Native Oxide and Artificial Layers on Silicon Nanoparticles for Lithium Ion In-Situ Transmission Electron Microscopy Probing of Native Oxide and Artificial...

  2. Interstate Transmission Challenges for Renewable Energy: A Federalism...

    Open Energy Info (EERE)

    laws governing renewable energy; state and local laws governing the siting of electric transmission lines; the jurisdiction's relationship to a state or regional...

  3. Investing in the NW transmission system - revised Oct 2009.indd

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    transmission grid. Most renewable energy will come from wind generation, and most wind farms are located away from population centers, which means that additional...

  4. Phase 2 Report: Oahu Wind Integration and Transmission Study...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    technical configuration and capital costs of establishing an undersea cable system and examining impacts to the existing electric transmission systems as a result of...

  5. Oahu Wind Integration and Transmission Study (OWITS): Hawaiian...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    technical configuration and capital costs of establishing an undersea cable system and examining impacts to the existing electric transmission systems as a result of...

  6. Edison Electric Institute State Generation and Transmission Siting...

    Open Energy Info (EERE)

    Institute State Generation and Transmission Siting Directory Jump to: navigation, search OpenEI Reference LibraryAdd to library PermittingRegulatory Guidance - GuideHandbook:...

  7. Reserving and Scheduling Transmission over the Time Change -...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the Time Change Posted Date: 10172014 Effective November 2, 2014 at 0200 Pacific Daylight Savings Time (Advanced Standard Time), BPA Transmission Services will set all clocks...

  8. Reserving and Scheduling Transmission over the Time Change -...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Pacific Prevailing Time, BPA Transmission Services will set all clocks to Pacific Daylight Saving Time (Advanced Standard Time). For more information concerning how to submit...

  9. Reminder Reserving and Scheduling Transmission over the Time...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    the Time Change Posted Date: 10292014 Effective November 2, 2014 at 0200 Pacific Daylight Savings Time (Advanced Standard Time), BPA Transmission Services will set all clocks...

  10. EIS-0317: Kangley-Echo Lake Transmission Line Project

    Broader source: Energy.gov [DOE]

    This EIS analyzes BPA's proposal to build a new transmission line to accommodate increasing demand for electricity and ensure reliability in the Puget Sound area.

  11. ac transmission system: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    limits. The models are used to estimate the benefits of electricity locational marginal pricing (LMP) that arise from de Gispert, Adri 333 Heat transmission in Relativity...

  12. ac transmission systems: Topics by E-print Network

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    limits. The models are used to estimate the benefits of electricity locational marginal pricing (LMP) that arise from de Gispert, Adri 333 Heat transmission in Relativity...

  13. Jobs and Economic Development from New Transmission and Generation...

    Wind Powering America (EERE)

    from New Transmission and Generation in Wyoming Introduction Wyoming is a significant energy exporter, producing nearly 40% of the nation's coal and 10% of the nation's natural...

  14. National Electric Transmission Congestion Study - Draft for Public...

    Office of Environmental Management (EM)

    On August 19, 2014, the Department issued a Federal Register Notice announcing the availability of a draft of its National Electric Transmission Congestion Study for public...

  15. Coordination of Federal Transmission Permitting on Federal Lands...

    Office of Environmental Management (EM)

    transmission facilities on federal lands. In most instances, the Departments of Agriculture or Interior will be the Lead Agency, since they have jurisdiction over most of the...

  16. Wind Integration, Transmission, and Resource Assessment and Characterization Projects

    Broader source: Energy.gov [DOE]

    This report covers the Wind and Water Power Program’s Wind Integration, Transmission, and Resource Assessment and Characterization Projects from FY 2006 to FY 2014.

  17. Update Invalid Reservation Points for Transmission Service Requests...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    CommitteesTeams Customer Training Interconnection Notices Rates Standards of Conduct Tariff TF Web Based Training Update: Invalid Reservation Points for Transmission Service...

  18. Highline Pacific Northwests High-Voltage Transmission System

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    made substantial contributions to BPA, including the innovation of vibration dampers on transmission towers, which help reduce wind noise. It was the first color film produced by...

  19. Modeling Interregional Transmission Congestion in the National Energy Modeling System

    E-Print Network [OSTI]

    Gumerman, Etan; Chan, Peter; Lesieutre, Bernard; Marnay, Chris; Wang, Juan

    2006-01-01T23:59:59.000Z

    Coal Case About two-thirds of the additional transmission represents imports into California from the Northwest and Arizona/New Mexico (

  20. Microsoft Word - DOE RFI on Transmission Planning - PGE Comments...

    Broader source: Energy.gov (indexed) [DOE]

    generation, procurement and transmission, and natural gas procurement, transportation and storage. PG&E serves approximately 5.2 million electricity distribution customers and...