National Library of Energy BETA

Sample records for total installed cost

  1. New Berkeley Lab Report Tracks a Decade of PV Installed Cost Trends

    E-Print Network [OSTI]

    Barbose, Galen

    2009-01-01

    Tracks a Decade of PV Installed Cost Trends Galen Barbose,in total average PV installed costs since 1998 appears to beNew York) exempted PV hardware costs from state sales tax

  2. Tracking the Sun III; The Installed Cost of Photovoltaics in the United States from 1998-2009

    E-Print Network [OSTI]

    Barbose, Galen

    2011-01-01

    from 1998-2009 Tracking the Sun III: The Installed Cost ofSystems MW Total Tracking the Sun III: The Installed Cost ofthrough 2009. Tracking the Sun III: The Installed Cost of

  3. Factors Affecting PMU Installation Costs (October 2014) | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Factors Affecting PMU Installation Costs (October 2014) Factors Affecting PMU Installation Costs (October 2014) The Department of Energy investigated the major cost factors that...

  4. Characterization of the Installed Costs of Prime Movers Using...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Installed Costs of Prime Movers Using Gaseous Opportunity Fuels, September 2007 Characterization of the Installed Costs of Prime Movers Using Gaseous Opportunity Fuels, September...

  5. Tracking the Sun III; The Installed Cost of Photovoltaics in the United States from 1998-2009

    E-Print Network [OSTI]

    Barbose, Galen

    2011-01-01

    U.S. from 1998-2009 Tracking the Sun III: The Installed CostMW No. Systems MW Total Tracking the Sun III: The InstalledU.S. through 2009. Tracking the Sun III: The Installed Cost

  6. Nitinol Heat Engine power plant system installation and cost optimization

    SciTech Connect (OSTI)

    Cady, E.C.; McNichols, J.L.

    1984-08-01

    Nitinol Heat Engines (NHE) use a shape memory alloy of nickel and titanium to directly convert the thermal energy in hot water to mechanical power (and, through a generator, to electricity). The authors designed a commercial version of a NHE based on the thermoturbine configuration developed in prototype form under contract to the Department of Energy in 1978-1980. The operation and cost of various forms of NHE have been described previously, but the penalties and costs associated with integrating the complete NHE system into installations supplying the thermal energy have not previously been determined. They found that these costs are most important, as they will often exceed the costs of the NHE proper. However, the total installed costs are quite low and result in very economical power from waste-heat or geothermal hot-water sources.

  7. Tracking the Sun II: The Installed Cost of Photovoltaics in the U.S. from 1998-2008

    E-Print Network [OSTI]

    Barbose, Galen L

    2010-01-01

    2008 BACK PAGE Tracking the Sun II: The Installed Cost of10-100 kW >100 kW Tracking the Sun II: The Installed Cost ofSystems MW Total Tracking the Sun II: The Installed Cost of

  8. Tracking the Sun II: The Installed Cost of Photovoltaics in the U.S. from 1998-2008

    E-Print Network [OSTI]

    Barbose, Galen L

    2010-01-01

    1998-2008 BACK PAGE Tracking the Sun II: The Installed Cost10-100 kW >100 kW Tracking the Sun II: The Installed Cost ofNo. Systems MW Total Tracking the Sun II: The Installed Cost

  9. Total cost model for making sourcing decisions

    E-Print Network [OSTI]

    Morita, Mark, M.B.A. Massachusetts Institute of Technology

    2007-01-01

    This thesis develops a total cost model based on the work done during a six month internship with ABB. In order to help ABB better focus on low cost country sourcing, a total cost model was developed for sourcing decisions. ...

  10. Advances in Energy Efficiency, Capital Cost, and Installation Schedules for Large Capacity Cooling Applications Using a Packaged Chiller Plant Approach 

    E-Print Network [OSTI]

    Pierson, T. L.; Andrepont, J. S.

    2003-01-01

    include: 1) dramatic reductions in unit capital costs of installed chiller plant capacity on a dollar per ton basis, 2) marked improvements in total procurement and installation schedules, 3) significantly smaller space requirements, and 4) enhanced...

  11. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    on U.S. Wind Power Installation, Cost, and Performanceand Capital Costs Drive Wind Power Prices. . . . . 14in installed wind project costs, wind turbine transaction

  12. Tracking the Sun: The Installed Cost of Photovoltaics in the U.S. from 1998-2007

    SciTech Connect (OSTI)

    Wiser, Ryan; Barbose, Galen; Peterman, Carla

    2009-02-11

    As installations of grid-connected solar photovoltaic (PV) systems have grown, so too has the desire to track the installed cost of these systems over time, by system characteristics, by system location, and by component. This report helps to fill this need by summarizing trends in the installed cost of grid-connected PV systems in the United States from 1998 through 2007. The report is based on an analysis of installed cost data from nearly 37,000 residential and non-residential PV systems, totaling 363 MW of capacity, and representing 76percent of all grid-connected PV capacity installed in the U.S. through 2007.

  13. Tracking the Sun III; The Installed Cost of Photovoltaics in the United States from 1998-2009

    E-Print Network [OSTI]

    Barbose, Galen

    2011-01-01

    sources of installed PV cost data for the U.S. 12 The report7 3. PV Installed Cost2005 through 2009. PV installed costs exhibit significant

  14. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    wind energy generation costs, and generation costs cannot beand operating costs of new generation projects, whereas ourof installed generation, with costs recovered through

  15. New Berkeley Lab Report Tracks a Decade of PV Installed Cost Trends

    E-Print Network [OSTI]

    Barbose, Galen

    2009-01-01

    installed cost and the module price index in each year.Module Price Index Non-Module Cost (calculated) InstalledModule price index as a proxy for module costs. The non-

  16. Total Ownership Cost (TOC) Cost as an Independent Variable

    E-Print Network [OSTI]

    $ + procurement $ + operation $ + logistical support $ + disposal $ Linked - Indirect Direct Direct Cost Life with the research, development, procurement, operation, logistical support and disposal of an individual weapon, operation, logistical support and disposal of an individual weapon system including the total supporting

  17. New Berkeley Lab Report Tracks a Decade of PV Installed Cost Trends

    SciTech Connect (OSTI)

    Barbose, Galen; Peterman, Carla; Wiser, Ryan

    2009-04-15

    Installations of PV systems have been expanding at a rapid pace in recent years. In the United States, the market for PV is driven by national, state, and local government incentives, including upfront cash rebates, production-based incentives, requirements that electricity suppliers purchase a certain amount of solar energy, and Federal and state tax benefits. These programs are, in part, motivated by the popular appeal of solar energy and by the positive attributes of PV - e.g., modest environmental impacts, avoidance of fuel price risks, coincidence with peak electrical demand, and the location of PV at the point of use. Given the relatively high cost of PV, however, a key goal of these policies is to encourage cost reductions over time. Therefore, as policy incentives have become more significant and as PV deployment has accelerated, so too has the desire to track the installed cost of PV systems over time, by system characteristics, by system location, and by component. A new Lawrence Berkeley National Laboratory report, 'Tracking the Sun: The Installed Cost of Photovoltaics in the U.S. from 1998-2007', helps to fill this need by summarizing trends in the installed cost (i.e., the cost paid by the system owner) of grid-connected PV systems in the U.S. The report is based on an analysis of project-level cost data from nearly 37,000 residential and non-residential PV systems completed from 1998-2007 and installed on the utility-customer-side of the meter. These systems total 363 MW, equal to 76% of all grid-connected PV capacity installed in the U.S. through 2007, representing the most comprehensive data source available on the installed cost of PV in the United States. The data were obtained from administrators of PV incentive programs around the country, who typically collect installed cost data for systems receiving incentives. A total of 16 programs, spanning 12 states, ultimately provided data for the study. Reflecting the broader geographical trends in the U.S. PV market, the vast majority of the systems in the data sample are located in California (83%, by capacity) and New Jersey (12%), The remaining systems are located in Arizona, Connecticut, Illinois, Massachusetts, Maryland, Minnesota, New York, Oregon, Pennsylvania, and Wisconsin. The PV systems in the dataset range in size from 100 W to 1.3 MW, almost 90% of which are smaller than 10 kW. This article briefly summarizes some of the key findings from the Berkeley Lab study (the full report can be downloaded at http://eetd.lbl.gov/ea/emp/re-pubs.html). The article begins by summarizing trends related to the installed cost of PV systems prior to receipt of any financial incentives, and then discusses how changes in incentive levels over time and variation across states have impacted the net installed cost of PV to the customer, after receipt of incentives. Note that all cost and incentive data are presented in real 2007 dollars (2007$), and all capacity and dollars-perwatt ($/W) data are presented in terms of rated module power output under Standard Test Conditions (DC-STC).

  18. Tracking the Sun II: The Installed Cost of Photovoltaics in the U.S. from 1998-2008

    E-Print Network [OSTI]

    Barbose, Galen L

    2010-01-01

    comprehensive source of installed PV cost data for the U.S.compares recent PV installed costs in the U.S. to those inthrough 2008. PV installed costs exhibit significant

  19. Tracking the Sun II: The Installed Cost of Photovoltaics in the U.S. from 1998-2008

    E-Print Network [OSTI]

    Barbose, Galen L

    2010-01-01

    The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-

  20. Tracking the Sun III; The Installed Cost of Photovoltaics in the United States from 1998-2009

    E-Print Network [OSTI]

    Barbose, Galen

    2011-01-01

    The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-

  1. Tracking the Sun: The Installed Cost of Photovoltaics in the U.S. from 1998-2007

    E-Print Network [OSTI]

    Wiser, Ryan

    2009-01-01

    The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-

  2. New Berkeley Lab Report Tracks a Decade of PV Installed Cost Trends

    E-Print Network [OSTI]

    Barbose, Galen

    2009-01-01

    Thus, even if large commercial PV installations continue tojoined by utility-scale PV), the removal of the cap on theLab Report Tracks a Decade of PV Installed Cost Trends Galen

  3. Characterization of the Installed Costs of Prime Movers Using Gaseous Opportunity Fuels, September 2007

    Office of Energy Efficiency and Renewable Energy (EERE)

    A report addendum and final white paper for the Characterization of the Installed Costs of Prime Movers Using Gaseous Opportunity Fuels

  4. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    to Drive Wind Development. . . . . . . . . . . . . . .5 GE Wind Is the Dominant Turbine Manufacturer, with SiemensAnnual Report on U.S. Wind Power Installation, Cost, and

  5. Project Functions and Activities Definitions for Total Project Cost

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter provides guidelines developed to define the obvious disparity of opinions and practices with regard to what exactly is included in total estimated cost (TEC) and total project cost (TPC).

  6. Tracking the Sun: The Installed Cost of Photovoltaics in the U.S. from 1998-2007

    E-Print Network [OSTI]

    Wiser, Ryan

    2009-01-01

    source of installed PV cost data in the United States. Inrelatively low residential PV costs in Japan may be partlyevidence confirms that PV costs have declined substantially

  7. Tracking the Sun IV: An Historical Summary of the Installed Cost of Photovoltaics in the United States from 1998 to 2010

    SciTech Connect (OSTI)

    Darghouth, Naim; Wiser, Ryan

    2011-09-07

    The present report describes installed cost trends for grid-connected PV projects installed from 1998 through 2010 (with some limited and preliminary results presented for projects installed in the first six months of 2011). The analysis is based on project-level cost data from approximately 116,500 residential, non-residential, and utility-sector PV systems in the United States. The inclusion of utility-sector PV is a new element in this year’s report. The combined capacity of all systems in the data sample totals 1,685 MW, equal to 79% of all grid-connected PV capacity installed in the United States through 2010 and representing one of the most comprehensive sources of installed PV cost data for the U.S. Based on this dataset, the report describes historical installed cost trends over time, and by location, market segment, technology type, and component. The report also briefly compares recent PV installed costs in the United States to those in Germany and Japan, and describes trends in customer incentives for PV installations and net installed costs after receipt of such incentives. The analysis presented here focuses on descriptive trends in the underlying data, serving primarily to summarize the data in tabular and graphical form.

  8. Developing a total replacement cost index for suburban office projects

    E-Print Network [OSTI]

    Hansen, David John, S.M. Massachusetts Institute of Technology

    2006-01-01

    Understanding the components of replacement costs for office developments, and how these components combine to create total development costs is essential for success in office real estate development. Surprisingly, the ...

  9. Solar PV Manufacturing Cost Model Group: Installed Solar PV System Prices (Presentation)

    SciTech Connect (OSTI)

    Goodrich, A. C.; Woodhouse, M.; James, T.

    2011-02-01

    EERE's Solar Energy Technologies Program is charged with leading the Secretary's SunShot Initiative to reduce the cost of electricity from solar by 75% to be cost competitive with conventional energy sources without subsidy by the end of the decade. As part of this Initiative, the program has funded the National Renewable Energy Laboratory (NREL) to develop module manufacturing and solar PV system installation cost models to ensure that the program's cost reduction targets are carefully aligned with current and near term industry costs. The NREL cost analysis team has leveraged the laboratories' extensive experience in the areas of project finance and deployment, as well as industry partnerships, to develop cost models that mirror the project cost analysis tools used by project managers at leading U.S. installers. The cost models are constructed through a "bottoms-up" assessment of each major cost element, beginning with the system's bill of materials, labor requirements (type and hours) by component, site-specific charges, and soft costs. In addition to the relevant engineering, procurement, and construction costs, the models also consider all relevant costs to an installer, including labor burdens and overhead rates, supply chain costs, and overhead and materials inventory costs, and assume market-specific profits.

  10. SMART Wind Consortium Virtual Meeting on Installation: Reducing Electrical and Foundation Costs

    Broader source: Energy.gov [DOE]

    This 90-minute SMART Wind Consortium virtual meeting is intended to foster dialogue on actions to improve safety and efficiency and to reduce installation costs for distributed wind turbines. Gary...

  11. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    Annual Report on U.S. Wind Power Installation, Cost, and3 U.S. Wind Power Capacity Increased by 27% inAre Significant. . . . . . . 9 Wind Power Prices Are Up in

  12. Building Life Cycle Cost Programs Software Installation Troubleshootin...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    trouble downloading the Building Life Cycle Cost (BLCC) Programs software? Macintosh Operating Systems If you are receiving the "Download.app is damaged and can't be opened"...

  13. Insulating concrete forms: Installed cost and acoustic performance

    SciTech Connect (OSTI)

    1999-03-01

    The NAHB Research Center conducted a study to compare the cost and performance of Insulating Concrete Form (ICF) walls to conventional wood-frame exterior walls. This report contains the results of the cost study and sound transmission tests. Three home were built and monitored. One home has an ICF plank system, one has an ICF block system, and one is of conventional 2x4 lumber construction. The homes have identical floor plans and are located side by side. The findings indicate that the labor costs for the ICFs were slightly to moderately higher than the wood framing. However, the sound tests indicate that the ICF walls perform significantly better than the wood walls when no openings were present. The report summarizes the findings and recommends ways to increase the cost-effectiveness of ICFs.

  14. Tracking the Sun III; The Installed Cost of Photovoltaics in the United States from 1998-2009

    SciTech Connect (OSTI)

    Barbose, Galen; Darghouth, Naim; Wiser, Ryan

    2010-12-13

    Installations of solar photovoltaic (PV) systems have been growing at a rapid pace in recent years. In 2009, approximately 7,500 megawatts (MW) of PV were installed globally, up from approximately 6,000 MW in 2008, consisting primarily of grid-connected applications. With 335 MW of grid-connected PV capacity added in 2009, the United States was the world's fourth largest PV market in 2009, behind Germany, Italy, and Japan. The market for PV in the United States is driven by national, state, and local government incentives, including up-front cash rebates, production-based incentives, requirements that electricity suppliers purchase a certain amount of solar energy, and federal and state tax benefits. These programs are, in part, motivated by the popular appeal of solar energy, and by the positive attributes of PV - modest environmental impacts, avoidance of fuel price risks, coincidence with peak electrical demand, and the possible deployment of PV at the point of use. Given the relatively high cost of PV, however, a key goal of these policies is to encourage cost reductions over time. Therefore, as policy incentives have become more significant and as PV deployment has accelerated, so too has the desire to track the installed cost of PV systems over time, by system characteristics, by system location, and by component. Despite the significant year-on-year growth, however, the share of global and U.S. electricity supply met with PV remains small, and annual PV additions are currently modest in the context of the overall electric system. To address this need, Lawrence Berkeley National Laboratory initiated a report series focused on describing trends in the installed cost of grid-connected PV systems in the United States. The present report, the third in the series, describes installed cost trends from 1998 through 2009, and provides preliminary cost data for systems installed in 2010. The analysis is based on project-level cost data from approximately 78,000 residential and non-residential PV systems in the U.S., all of which are installed at end-use customer facilities (herein referred to as 'customer-sited' systems). The combined capacity of systems in the data sample totals 874 MW, equal to 70% of all grid-connected PV capacity installed in the United States through 2009 and representing one of the most comprehensive sources of installed PV cost data for the U.S. The report also briefly compares recent PV installed costs in the United States to those in Germany and Japan. Finally, it should be noted that the analysis presented here focuses on descriptive trends in the underlying data, serving primarily to summarize the data in tabular and graphical form; later analysis may explore some of these trends with more-sophisticated statistical techniques. The report begins with a summary of the data collection methodology and resultant dataset (Section 2). The primary findings of the analysis are presented in Section 3, which describes trends in installed costs prior to receipt of any financial incentives: over time and by system size, component, state, system ownership type (customer-owned vs. third party-owned), host customer segment (residential vs. commercial vs. public-sector vs. non-profit), application (new construction vs. retrofit), and technology type (building-integrated vs. rack-mounted, crystalline silicon vs. thin-film, and tracking vs. fixed-axis). Section 4 presents additional findings related to trends in PV incentive levels over time and among states (focusing specifically on state and utility incentive programs as well as state and federal tax credits), and trends in the net installed cost paid by system owners after receipt of such incentives. Brief conclusions are offered in the final section, and several appendices provide additional details on the analysis methodology and additional tabular summaries of the data.

  15. Tracking the Sun III; The Installed Cost of Photovoltaics in the United States from 1998-2009

    E-Print Network [OSTI]

    Barbose, Galen

    2011-01-01

    level cost data provided by the California Solar Initiative,data for 2010 indicate that the average cost of systems installed through the California Solar

  16. Tracking the Sun II: The Installed Cost of Photovoltaics in the U.S. from 1998-2008

    E-Print Network [OSTI]

    Barbose, Galen L

    2010-01-01

    the Sun Shine on Solar Costs: An Empirical Investigation ofthe Sun Shine on Solar Costs: An Empirical Investigation ofcost of projects installed through the California Solar

  17. Tracking the Sun: The Installed Cost of Photovoltaics in the U.S. from 1998-2007

    E-Print Network [OSTI]

    Wiser, Ryan

    2009-01-01

    10-100 kW >100 kW Tracking the Sun: The Installed Cost ofout over five years. Tracking the Sun: The Installed Cost ofU.S. from 1998-2007 Tracking the Sun: The Installed Cost of

  18. Tracking the Sun II: The Installed Cost of Photovoltaics in the U.S. from 1998-2008

    SciTech Connect (OSTI)

    Barbose, Galen L; Wiser, Ryan; Peterman, Carla; Darghouth, Naim

    2009-10-05

    Installations of solar photovoltaic (PV) systems have been growing at a rapid pace in recent years. In 2008, 5,948 MW of PV was installed globally, up from 2,826 MW in 2007, and was dominated by grid-connected applications. The United States was the world's third largest PV market in terms of annual capacity additions in 2008, behind Spain and Germany; 335 MW of PV was added in the U.S. in 2008, 293 MW of which came in the form of grid-connected installations. Despite the significant year-on-year growth, however, the share of global and U.S. electricity supply met with PV remains small, and annual PV additions are currently modest in the context of the overall electric system. The market for PV in the U.S. is driven by national, state, and local government incentives, including up-front cash rebates, production-based incentives, requirements that electricity suppliers purchase a certain amount of solar energy, and Federal and state tax benefits. These programs are, in part, motivated by the popular appeal of solar energy, and by the positive attributes of PV - modest environmental impacts, avoidance of fuel price risks, coincidence with peak electrical demand, and the location of PV at the point of use. Given the relatively high cost of PV, however, a key goal of these policies is to encourage cost reductions over time. Therefore, as policy incentives have become more significant and as PV deployment has accelerated, so too has the desire to track the installed cost of PV systems over time, by system characteristics, by system location, and by component. To address this need, Lawrence Berkeley National Laboratory initiated a report series focused on describing trends in the installed cost of grid-connected PV systems in the U.S. The present report, the second in the series, describes installed cost trends from 1998 through 2008. The analysis is based on project-level cost data from more than 52,000 residential and non-residential PV systems in the U.S., all of which are installed at end-use customer facilities (herein referred to as 'customer-sited' systems). The combined capacity of systems in the data sample totals 566 MW, equal to 71% of all grid-connected PV capacity installed in the U.S. through 2008, representing the most comprehensive source of installed PV cost data for the U.S.9 The report also briefly compares recent PV installed costs in the U.S. to those in Germany and Japan. Finally, it should be noted that the analysis presented here focuses on descriptive trends in the underlying data, and is primarily summarized in tabular and graphical form; later analysis may explore some of these trends with more-sophisticated statistical techniques. The report begins with a summary of the data collection methodology and resultant dataset (Section 2). The primary findings of the analysis are presented in Section 3, which describes trends in installed costs prior to receipt of any financial incentives: over time and by system size, component, state, customer segment (residential vs. commercial vs. public-sector vs. non-profit), application (new construction vs. retrofit), and technology type (building-integrated vs. rack-mounted, crystalline silicon vs. thin-film, and tracking vs. rack-mounted). Section 4 presents additional findings related to trends in PV incentive levels over time and among states (focusing specifically on state and utility incentive programs as well as state and Federal tax credits), and trends in the net installed cost paid by system owners after receipt of such incentives. Brief conclusions are offered in the final section.

  19. Tracking the Sun IV: An Historical Summary of the Installed Cost of Photovoltaics in the United States from 1998 to 2010

    E-Print Network [OSTI]

    Darghouth, Naim

    2012-01-01

    The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-The Installed Cost of Photovoltaics in the U.S. from 1998-

  20. CIGNA Study Uncovers Relationship of Disabilities to Total Benefits Costs

    Broader source: Energy.gov [DOE]

    The findings of a new study reveal an interesting trend. Integrating disability programs with health care programs can potentially lower employers' total benefits costs and help disabled employees get back to work sooner and stay at work.

  1. Tracking the Sun IV: An Historical Summary of the Installed Cost of Photovoltaics in the United States from 1998 to 2010

    E-Print Network [OSTI]

    Darghouth, Naim

    2012-01-01

    installed in 2007-2010. Tracking the Sun IV: The InstalledIncentive ($/W) Total Tracking the Sun IV: The InstalledIncentive ($/W) Total Tracking the Sun IV: The Installed

  2. Thin-film flat-plate solar collectors for low-cost manufacture and installation

    SciTech Connect (OSTI)

    Andrews, J.W.; Wilhelm, W.G.

    1980-03-01

    A flat-plate solar energy collector design using thin-film plastics in both the absorber and glazing is described. The design approach proceeded in two steps. First, cost constraints on solar collectors were determined using reasonable economic projections. Second, engineering was applied only to those ideas which had hope of falling within those cost boundaries. The use of thin-film plastics appeared most attractive according to these criteria. The nature of the marketing and distribution network can be expected to have a strong impact on the final installed cost of the collector; the proposed design has characteristics which could make possible a reduced price markup.

  3. Motivation Literature Trans. Network Models Relative Total Cost Indices Numerical Examples Summary A Relative Total Cost Index for the Evaluation of

    E-Print Network [OSTI]

    Nagurney, Anna

    A Relative Total Cost Index for the Evaluation of Transportation Network Robustness in the Presence Index #12;Motivation Literature Trans. Network Models Relative Total Cost Indices Numerical Examples, Qiang Qiang Relative Total Cost Index #12;Motivation Literature Trans. Network Models Relative Total

  4. Installation, Operation, and Maintenance Strategies to Reduce the Cost of Offshore Wind Energy

    SciTech Connect (OSTI)

    Maples, B.; Saur, G.; Hand, M.; van de Pietermen, R.; Obdam, T.

    2013-07-01

    Currently, installation, operation, and maintenance (IO&M) costs contribute approximately 30% to the LCOE of offshore wind plants. To reduce LCOE while ensuring safety, this paper identifies principal cost drivers associated with IO&M and quantifies their impacts on LCOE. The paper identifies technology improvement opportunities and provides a basis for evaluating innovative engineering and scientific concepts developed subsequently to the study. Through the completion of a case study, an optimum IO&M strategy for a hypothetical offshore wind project is identified.

  5. Plug and Play: Purchase, Install, and Connect Residential Solar...

    Office of Environmental Management (EM)

    -- like permitting, installation, and interconnection -- make up more than half the total cost of solar energy system. To tackle these soft costs, Fraunhofer CSE developed its Plug...

  6. ANALYSIS OF THE PERFORMANCE AND COST EFFECTIVENESS OF NINE SMALL WIND ENERGY CONVERSION SYSTEMS FUNDED BY THE DOE SMALL GRANTS PROGRAM

    E-Print Network [OSTI]

    Kay, J.

    2009-01-01

    Installation costs, including well drilling and the diggingplastic pipe drilling & installing pipe Total costs to beproject costs: Tower Foundation (including drilling,

  7. ANALYSIS OF THE PERFORMANCE AND COST EFFECTIVENESS OF NINE SMALL WIND ENERGY CONVERSION SYSTEMS FUNDED BY THE DOE SMALL GRANTS PROGRAM

    E-Print Network [OSTI]

    Kay, J.

    2009-01-01

    Installation costs, including well drilling and the diggingproject costs: Tower Foundation (including drilling,plastic pipe drilling & installing pipe Total costs to be

  8. Design and installation of an ultra deepwater subsea system: How to minimize risks and costs

    SciTech Connect (OSTI)

    Izetti, R.G.; Moreira, J.R.F.

    1994-12-31

    The world`s deepest Subsea Tree was successfully installed offshore Brazil at a water depth of 1,027 m. The psychological barrier of 1,000 m was finally broken. Actually, subsea completion technology reached a point where the fundamental question is no longer whether fields located at water depths beyond 1,000 m can be profitably completed. The key issue now is: is there a better and safer way to do it? PETROBRAS has pursued an aggressive strategy in research and development concept evaluations and various field studies aiming at a continuous decrease in both CAPEX and OPEX. This paper primarily describes the major subsea completion achievements, resulting from this great effort, which among other topics include: implementation of a standardization program; sharp reduction of both subsea completion and drilling time; a new flowline connection method which combines the advantages of both lay-away and pull-in methods; design and future installation of the world first subsea electrical submersible pump; completion equipment simplification and resulting cost reduction. Also addressed are the key safety aspects related to deepwater completions and the equipment design improvement necessary to safely conduct those operations.

  9. Design and installation of an ultra-deepwater subsea system: How to minimize risks and costs

    SciTech Connect (OSTI)

    Izetti, R.G.; Moreira, J.R.F.

    1995-04-01

    The world`s deepest subsea tree was successfully installed offshore Brazil at a water depth of 1,027 m, finally breaking the psychological barrier of 1,000 m. Actually, subsea completion technology has reached a point where the fundamental question no linger is whether fields located at water depths > 1,000 m can be profitably completed; is there a better and safer way to do it is now the key issue. Petrobras has pursued an aggressive strategy in R and D concept evaluations and various field studies aiming at a continuous decrease in both capital and operational expenditures. This paper describes the major subsea completion achievements resulting from this great effort, which include implementation of a standardization program; sharp reduction of subsea completion and drilling time; a new flowline connection method that combines the advantages of lay-away and pull-in methods; design and future installation of the world`s first subsea electrical submersible pump; and completion equipment simplification and resulting cost reduction. Also addressed are the key safety aspects related to deepwater completions and the equipment design improvement necessary to conduct those operations safely.

  10. Development of a total landed cost and risk analysis model for global strategic sourcing

    E-Print Network [OSTI]

    Feller, Brian (Brian C.)

    2008-01-01

    Total landed cost and supply chain risk analysis are methods that many companies use to assess strategic sourcing decisions. For this project, landed cost is defined as those costs associated with material movement from a ...

  11. Tracking the Sun IV: An Historical Summary of the Installed Cost of Photovoltaics in the United States from 1998 to 2010

    E-Print Network [OSTI]

    Darghouth, Naim

    2012-01-01

    likely differ from current PV cost benchmarks. Second, thisPV. Third, the utility-sector PV cost data presented in thissources of installed PV cost data for the U.S. Based on this

  12. A Study of the Key Variables Affecting Bus Replacement Age Decisions and1 Total Costs2

    E-Print Network [OSTI]

    Bertini, Robert L.

    A Study of the Key Variables Affecting Bus Replacement Age Decisions and1 Total Costs2 3 Jesse operational3 and maintenance (O&M) per-mile costs increase as buses age. From a purely economic4 perspective, there is a cost tradeoff between the lower O&M costs of newer fleets and their5 higher initial capital costs

  13. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    wind project costs, wind turbine transaction prices, projectincreases in the cost of wind turbines. Berkeley Lab hasrising prices wind turbine costs, and therefore wind power

  14. Evaluation of the Total Cost of Ownership of Fuel Cell-Powered Material Handling Equipment

    SciTech Connect (OSTI)

    Ramsden, T.

    2013-04-01

    This report discusses an analysis of the total cost of ownership of fuel cell-powered and traditional battery-powered material handling equipment (MHE, or more typically 'forklifts'). A number of fuel cell MHE deployments have received funding support from the federal government. Using data from these government co-funded deployments, DOE's National Renewable Energy Laboratory (NREL) has been evaluating the performance of fuel cells in material handling applications. NREL has assessed the total cost of ownership of fuel cell MHE and compared it to the cost of ownership of traditional battery-powered MHE. As part of its cost of ownership assessment, NREL looked at a range of costs associated with MHE operation, including the capital costs of battery and fuel cell systems, the cost of supporting infrastructure, maintenance costs, warehouse space costs, and labor costs. Considering all these costs, NREL found that fuel cell MHE can have a lower overall cost of ownership than comparable battery-powered MHE.

  15. An Evaluation of the Total Cost of Ownership of Fuel Cell-Powered...

    Broader source: Energy.gov (indexed) [DOE]

    by the National Renewable Energy Laboratory discusses an analysis of the total cost of ownership of fuel cell-powered and traditional battery-powered material handling equipment,...

  16. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    17 Operations and Maintenance Costs Are Affected by Projectperformance, and operations and maintenance expenses.Capacity Factor Operations and maintenance (O&M) costs are

  17. Development of a Preliminary Decommissioning Plan Following the International Structure for Decommissioning Costing (ISDC) of Nuclear Installations - 13361

    SciTech Connect (OSTI)

    Moshonas Cole, Katherine; Dinner, Julia; Grey, Mike [Candesco - A Division of Kinectrics Inc, 26 Wellington E 3rd floor, Toronto, Ontario, M5E 1S2 (Canada)] [Candesco - A Division of Kinectrics Inc, 26 Wellington E 3rd floor, Toronto, Ontario, M5E 1S2 (Canada); Daniska, Vladimir [DECOM a.s., Sibirska 1, 917 01 Trnava (Slovakia)] [DECOM a.s., Sibirska 1, 917 01 Trnava (Slovakia)

    2013-07-01

    The International Structure for Decommissioning Costing (ISDC) of Nuclear Installations, published by OECD/NEA, IAEA and EC is intended to provide a uniform list of cost items for decommissioning projects and provides a standard format that permits international cost estimates to be compared. Candesco and DECOM have used the ISDC format along with two costing codes, OMEGA and ISDCEX, developed from the ISDC by DECOM, in three projects: the development of a preliminary decommissioning plan for a multi-unit CANDU nuclear power station, updating the preliminary decommissioning cost estimates for a prototype CANDU nuclear power station and benchmarking the cost estimates for CANDU against the cost estimates for other reactor types. It was found that the ISDC format provides a well defined and transparent basis for decommissioning planning and cost estimating that assists in identifying gaps and weaknesses and facilitates the benchmarking against international experience. The use of the ISDC can also help build stakeholder confidence in the reliability of the plans and estimates and the adequacy of decommissioning funding. (authors)

  18. Tracking the Sun IV: An Historical Summary of the Installed Cost of Photovoltaics in the United States from 1998 to 2010

    E-Print Network [OSTI]

    Darghouth, Naim

    2012-01-01

    Cost_Basis_for_Solar_PV_Properties%20final.doc Most of the PV projects in the datacost data presented in this report. Preliminary data for systems installed through the California Solar

  19. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    information on wind power purchase prices, capital costs,prices and/or negotiated power purchase agreements as muchLab collection of power purchase agreements. To reduce the

  20. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    basis. Text Box 1. Offshore Wind Development Activities Inis some interest in offshore wind in several parts of theGeorgia TOTAL Proposed Offshore Wind Capacity 735 MW 650 MW

  1. Tracking the Sun: The Installed Cost of Photovoltaics in the U.S. from 1998-2007

    E-Print Network [OSTI]

    Wiser, Ryan

    2009-01-01

    the Sun Shine on Solar Costs: An Empirical Investigation ofthe Sun Shine on Solar Costs: An Empirical Investigation ofthe Sun Shine on Solar Costs: An Empirical Investigation of

  2. Tracking the Sun III; The Installed Cost of Photovoltaics in the United States from 1998-2009

    E-Print Network [OSTI]

    Barbose, Galen

    2011-01-01

    the Sun Shine on Solar Costs: An Empirical Investigation oflevel cost data provided by the California Solar Initiative,Avg. Cost Avg. Incentive ?10 kW OR ETO Solar Electric

  3. A Total Cost of Ownership Model for Low Temperature PEM Fuel Cells in Combined Heat and Power and Backup Power Applications

    SciTech Connect (OSTI)

    University of California, Berkeley; Wei, Max; Lipman, Timothy; Mayyas, Ahmad; Chien, Joshua; Chan, Shuk Han; Gosselin, David; Breunig, Hanna; Stadler, Michael; McKone, Thomas; Beattie, Paul; Chong, Patricia; Colella, Whitney; James, Brian

    2014-06-23

    A total cost of ownership model is described for low temperature proton exchange membrane stationary fuel cell systems for combined heat and power (CHP) applications from 1-250kW and backup power applications from 1-50kW. System designs and functional specifications for these two applications were developed across the range of system power levels. Bottom-up cost estimates were made for balance of plant costs, and detailed direct cost estimates for key fuel cell stack components were derived using design-for-manufacturing-and-assembly techniques. The development of high throughput, automated processes achieving high yield are projected to reduce the cost for fuel cell stacks to the $300/kW level at an annual production volume of 100 MW. Several promising combinations of building types and geographical location in the U.S. were identified for installation of fuel cell CHP systems based on the LBNL modelling tool DER CAM. Life-cycle modelling and externality assessment were done for hotels and hospitals. Reduced electricity demand charges, heating credits and carbon credits can reduce the effective cost of electricity ($/kWhe) by 26-44percent in locations such as Minneapolis, where high carbon intensity electricity from the grid is displaces by a fuel cell system operating on reformate fuel. This project extends the scope of existing cost studies to include externalities and ancillary financial benefits and thus provides a more comprehensive picture of fuel cell system benefits, consistent with a policy and incentive environment that increasingly values these ancillary benefits. The project provides a critical, new modelling capacity and should aid a broad range of policy makers in assessing the integrated costs and benefits of fuel cell systems versus other distributed generation technologies.

  4. A Total Cost of Ownership Model for Low Temperature PEM Fuel...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    cost modeling framework of other studies to include operational costs and life-cycle impact assessment of possible ancillary financial benefits during operation and at...

  5. Total Cost Per MwH for all common large scale power generation...

    Open Energy Info (EERE)

    out of the stack, toxificaiton of the lakes and streams, plant decommision costs. For nuclear yiou are talking about managing the waste in perpetuity. The plant decomission costs...

  6. Determining benefits and costs of improved central air conditioner efficiencies

    E-Print Network [OSTI]

    Rosenquist, G.

    2010-01-01

    calculation include the installed consumer cost (purchase price plus installation cost), operating expenses (energy and

  7. A Relative Total Cost Index for the Evaluation of Transportation Network Robustness in the Presence of Degradable Links and Alternative Travel Behavior

    E-Print Network [OSTI]

    Nagurney, Anna

    A Relative Total Cost Index for the Evaluation of Transportation Network Robustness in the Presence-optimization or system-optimization. We derive upper bounds of the relative total cost index for transportation networks bound for the relative total cost index under the system-optimal flow pattern for general transportation

  8. Using a total landed cost model to foster global logistics strategy in the electronics industry

    E-Print Network [OSTI]

    Jearasatit, Apichart

    2010-01-01

    Global operation strategies have been widely used in the last several decades as many companies and industries have taken advantage of lower production costs. However, in choosing a location, companies often only consider ...

  9. A cost/benefit model for insertion of technological innovation into a total quality management program 

    E-Print Network [OSTI]

    Ratliff, William L

    1997-01-01

    This study provides economic justification for insertion of technological innovation into a total quality management (TQM) program in a remanufacturing environment. One of the core principles of TQM is continuous improvement. A preferred metric...

  10. Considering the total cost of electricity from sunlight and the alternatives

    SciTech Connect (OSTI)

    none,

    2015-04-15

    Photovoltaic (PV) electricity generation has grown to about 17 GW in the United States, corresponding to one tenth of the global capacity. Most deployment in the country has happened during the last 6 years. Reflecting back in time, in early 2008 this author and his collaborators James Mason and Ken Zweibel, published in Scientific American and in Energy Policy a Solar Grand Plan demonstrating the feasibility of renewable energy in providing 69% of the U.S. electricity demand by 2050, while reducing CO2 emissions by 60% from 2005 levels; the PV contribution to this plan was assessed to be 250 GW by 2030, and 2,900 GW by 2050 [1]. The DOE’s more detailed SunShot vision study, released in 2012, showed the possibility of having 300 GW of PV installed in the United States by 2030, and 630 GW by 2050.

  11. Considering the total cost of electricity from sunlight and the alternatives

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Fthenakis, Vasilis [Brookhaven National Lab. (BNL), Upton, NY (United States); Columbia Univ., New York, NY (United States)

    2015-03-01

    Photovoltaic (PV) electricity generation has grown to about 17 GW in the United States, corresponding to one tenth of the global capacity. Most deployment in the country has happened during the last 6 years. Reflecting back in time, in early 2008 this author and his collaborators James Mason and Ken Zweibel, published in Scientific American and in Energy Policy a Solar Grand Plan demonstrating the feasibility of renewable energy in providing 69% of the U.S. electricity demand by 2050, while reducing CO2 emissions by 60% from 2005 levels; the PV contribution to this plan was assessed to be 250 GW by 2030, and 2,900 GW by 2050 [1]. The DOE’s more detailed SunShot vision study, released in 2012, showed the possibility of having 300 GW of PV installed in the United States by 2030, and 630 GW by 2050.

  12. Considering the total cost of electricity from sunlight and the alternatives

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    none,

    2015-04-15

    Photovoltaic (PV) electricity generation has grown to about 17 GW in the United States, corresponding to one tenth of the global capacity. Most deployment in the country has happened during the last 6 years. Reflecting back in time, in early 2008 this author and his collaborators James Mason and Ken Zweibel, published in Scientific American and in Energy Policy a Solar Grand Plan demonstrating the feasibility of renewable energy in providing 69% of the U.S. electricity demand by 2050, while reducing CO2 emissions by 60% from 2005 levels; the PV contribution to this plan was assessed to be 250 GWmore »by 2030, and 2,900 GW by 2050 [1]. The DOE’s more detailed SunShot vision study, released in 2012, showed the possibility of having 300 GW of PV installed in the United States by 2030, and 630 GW by 2050.« less

  13. Factors Affecting PMU Installation Costs

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:FinancingPetroleum12, 2015Executive Order14, 20111,FYDepartment of EnergySeptember 2014 United

  14. A new A&P Food Market in Mt. Kisco, New York, is enjoying annual energy cost savings of nearly $130,000 with the installation of an integrated microturbine power system

    E-Print Network [OSTI]

    Pennycook, Steve

    Background A new A&P Food Market in Mt. Kisco, New York, is enjoying annual energy cost savings, heating and power solutions, was installed in 2005 in the 57,000- square-foot facility. The New York supermarket was the first U.S. customer to take delivery of the new system. The PureComfort system is designed

  15. Tracking the Sun IV: An Historical Summary of the Installed Cost of Photovoltaics in the United States from 1998 to 2010

    E-Print Network [OSTI]

    Darghouth, Naim

    2012-01-01

    Research. Bloomberg New Energy Finance. 2011. Levelized Cost2011, and Bloomberg New Energy Finance 42 specifies a cost

  16. Hopper Installation

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    and a host of other scientific endeavors. 00.JPG Delivery 1.JPG Unloading 3.JPG Earthquake protection 4.JPG Installing cabinets 6.JPG Half way there 8.JPG Inspection and...

  17. Abstract. We consider the design of line plans in public transport at a min-imal total cost. Both, linear and nonlinear integer programming are adequate

    E-Print Network [OSTI]

    Lübbecke, Marco

    Abstract. We consider the design of line plans in public transport at a min- imal total cost. Both techniques. We derive and compare lower bounds from different lineariza- tions in order to assess the quality of the story, namely service versus cost aspects. While travelers demand for convenient, ideally direct

  18. Benchmarking Non-Hardware Balance-of-System (Soft) Costs for U.S. Photovoltaic Systems Using a Bottom-Up Approach and Installer Survey

    E-Print Network [OSTI]

    Ardani, Kristen

    2014-01-01

    and Utility-Scale Photovoltaic System Prices in the UnitedSoft) Costs for U.S. Photovoltaic Systems Using a Bottom-UpSoft) Costs for U.S. Photovoltaic Systems Using a Bottom-Up

  19. SunShot Prize: America's Most Affordable Rooftop Solar: A Competition To Spur Low-Cost Rooftop Solar Installations Across The Nation (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2012-06-01

    The SunShot Prize encourages novel public-private partnerships, original business models, and innovative approaches to installing clean, renewable solar energy. The sustainable business strategies developed by participants will provide transferable lessons that can be applied nationwide to hasten America's transition to affordable clean energy in a post-subsidy market.

  20. Benchmarking Non-Hardware Balance-of-System (Soft) Costs for U.S. Photovoltaic Systems, Using a Bottom-Up Approach and Installer Survey - Second Edition

    SciTech Connect (OSTI)

    Friedman, B.; Ardani, K.; Feldman, D.; Citron, R.; Margolis, R.; Zuboy, J.

    2013-10-01

    This report presents results from the second U.S. Department of Energy (DOE) sponsored, bottom-up data-collection and analysis of non-hardware balance-of-system costs -- often referred to as 'business process' or 'soft' costs -- for U.S. residential and commercial photovoltaic (PV) systems. In service to DOE's SunShot Initiative, annual expenditure and labor-hour-productivity data are analyzed to benchmark 2012 soft costs related to (1) customer acquisition and system design (2) permitting, inspection, and interconnection (PII). We also include an in-depth analysis of costs related to financing, overhead, and profit. Soft costs are both a major challenge and a major opportunity for reducing PV system prices and stimulating SunShot-level PV deployment in the United States. The data and analysis in this series of benchmarking reports are a step toward the more detailed understanding of PV soft costs required to track and accelerate these price reductions.

  1. Benchmarking Non-Hardware Balance of System (Soft) Costs for U.S. Photovoltaic Systems Using a Data-Driven Analysis from PV Installer Survey Results

    SciTech Connect (OSTI)

    Ardani, K.; Barbose, G.; Margolis, R.; Wiser, R.; Feldman, D.; Ong, S.

    2012-11-01

    This report presents results from the first U.S. Department of Energy (DOE) sponsored, bottom-up data-collection and analysis of non-hardware balance-of-system costs--often referred to as 'business process' or 'soft' costs--for residential and commercial photovoltaic (PV) systems.

  2. Wind Power: How Much, How Soon, and At What Cost?

    E-Print Network [OSTI]

    Wiser, Ryan H

    2010-01-01

    on U.S. Wind Power Installation, Cost, and Performanceaccess the nation's lowest-cost wind resources can be builtpressure on installed wind project costs while the industry

  3. Tracking the Sun IV: An Historical Summary of the Installed Cost of Photovoltaics in the United States from 1998 to 2010

    E-Print Network [OSTI]

    Darghouth, Naim

    2012-01-01

    cost of electricity (LCOE) for PV. Third, the utility-sectorthe related impact on the LCOE. The wide distribution in thecost of electricity (LCOE) for PV. Third, the utility-sector

  4. Development of a coiled tubing cable installation system

    SciTech Connect (OSTI)

    Newman, K.R.; Haver, N.A.; Stone, L.R.

    1995-12-31

    A system has been developed which installs and de-installs an electric wireline cable in coiled tubing (CT) while the CT is still on the reel. This cable installation system reduces the cost of a cable installation significantly compared with previous installation methods. This paper discusses the need for such a system, the theory used to develop this system, the various concepts considered, the system that was developed and test installation cases.

  5. A Method for Evaluating the Distribution of the Total Cost of a Random Process over its Lifetime

    E-Print Network [OSTI]

    Pollett, Phil

    state i to state j, for j = i, and qii = -qi, where qi := j=i qij (rate out process (X(t), t 0), suppose that there is a cost fx associated with being in state x. This paper of f, usually linear functions of the state. We will describe a method which assumes only that f is non

  6. Sandia Energy - Installation

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Installation Home Stationary Power Energy Conversion Efficiency Solar Energy Photovoltaics Solar Market Transformation Installation InstallationTara Camacho-Lopez2015-03-20T19:23:2...

  7. software installation page

    E-Print Network [OSTI]

    Installing software used in CS/MA 615. There are sources for various software packages. Gambit web site. You can download install packages for Windows and

  8. Costs Associated With Compressed Natural Gas Vehicle Fueling Infrastructure

    SciTech Connect (OSTI)

    Smith, M.; Gonzales, J.

    2014-09-01

    This document is designed to help fleets understand the cost factors associated with fueling infrastructure for compressed natural gas (CNG) vehicles. It provides estimated cost ranges for various sizes and types of CNG fueling stations and an overview of factors that contribute to the total cost of an installed station. The information presented is based on input from professionals in the natural gas industry who design, sell equipment for, and/or own and operate CNG stations.

  9. SMART Wind Consortium Virtual Meeting on Installation: Reducing...

    Broader source: Energy.gov (indexed) [DOE]

    to improve safety and efficiency and to reduce installation costs for distributed wind turbines. Gary Harcourt of Great Rock Windpower will discuss the electrician's work and...

  10. Low-Cost Installation of Concentrating Photovoltaic

    E-Print Network [OSTI]

    allow for minimal disturbance of soil and ecosystem, and comprehensive full system delivery: April 2009 to March 2012 For more information, please contact: · Placing concentrating photovoltaic for this information or the researc

  11. Case studies of six high priority DOD installations

    SciTech Connect (OSTI)

    1994-11-01

    This is a supplement to the report entitled Environmental Cleanup: Too Many High Priority Sites Impede DOD`s Program. It provides six installation case studies addressing issues including the status of the restoration program, the cost of cleanup to date and projected costs, the cleanup options considered, the option selected, expected completion, and the applicable cleanup standards. The case studies also provide installation specific information on reasons installation was listed on the NPL, the regulatory process, cooperation between the installation and the regulatory agencies, staffing at the installations and the regulatory agencies, and the process for funding the cleanup.

  12. Non-Hardware ("Soft") Cost-Reduction Roadmap for Residential and Small Commercial Solar Photovoltaics, 2013-2020

    SciTech Connect (OSTI)

    Ardani, K.; Seif, D.; Margolis, R.; Morris, J.; Davidson, C.; Truitt, S.; Torbert, R.

    2013-08-01

    The objective of this analysis is to roadmap the cost reductions and innovations necessary to achieve the U.S. Department of Energy (DOE) SunShot Initiative's total soft-cost targets by 2020. The roadmap focuses on advances in four soft-cost areas: (1) customer acquisition; (2) permitting, inspection, and interconnection (PII); (3) installation labor; and (4) financing. Financing cost reductions are in terms of the weighted average cost of capital (WACC) for financing PV system installations, with real-percent targets of 3.0% (residential) and 3.4% (commercial).

  13. Installation and Acceptance Stage

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-05-21

    This chapter addresses activities required to install the software, data bases, or data that comprise the software product onto the hardware platform at sites of operation.

  14. Installation of a Low Flow Unit at the Abiquiu Hydroelectric Facility

    SciTech Connect (OSTI)

    Jack Q. Richardson

    2012-06-28

    Final Technical Report for the Recovery Act Project for the Installation of a Low Flow Unit at the Abiquiu Hydroelectric Facility. The Abiquiu hydroelectric facility existed with two each 6.9 MW vertical flow Francis turbine-generators. This project installed a new 3.1 MW horizontal flow low flow turbine-generator. The total plant flow range to capture energy and generate power increased from between 250 and 1,300 cfs to between 75 and 1,550 cfs. Fifty full time equivalent (FTE) construction jobs were created for this project - 50% (or 25 FTE) were credited to ARRA funding due to the ARRA 50% project cost match. The Abiquiu facility has increased capacity, increased efficiency and provides for an improved aquatic environment owing to installed dissolved oxygen capabilities during traditional low flow periods in the Rio Chama. A new powerhouse addition was constructed to house the new turbine-generator equipment.

  15. Structural Code Considerations for Solar Rooftop Installations.

    SciTech Connect (OSTI)

    Dwyer, Stephen F.; Dwyer, Brian P.; Sanchez, Alfred

    2014-12-01

    Residential rooftop solar panel installations are limited in part by the high cost of structural related code requirements for field installation. Permitting solar installations is difficult because there is a belief among residential permitting authorities that typical residential rooftops may be structurally inadequate to support the additional load associated with a photovoltaic (PV) solar installation. Typical engineering methods utilized to calculate stresses on a roof structure involve simplifying assumptions that render a complex non-linear structure to a basic determinate beam. This method of analysis neglects the composite action of the entire roof structure, yielding a conservative analysis based on a rafter or top chord of a truss. Consequently, the analysis can result in an overly conservative structural analysis. A literature review was conducted to gain a better understanding of the conservative nature of the regulations and codes governing residential construction and the associated structural system calculations.

  16. Client Configuration and Installation

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Instructions below. In certain environments (e.g., if your installation is on a machine which has more than one network interface or has a high bandwidth network connection...

  17. Measuring the Effects of Peaking, Vehicle Capital, and Passenger Capacity on the Cost of Providing Transit Service

    E-Print Network [OSTI]

    Taylor, Brian D; Garrett, Mark; Iseki, Hiroyuki

    1999-01-01

    include both operating costs and capital costs, though mostthe Peak Period Operating Vehicle Non-vehicle Costs CapitalCosts Capital Costs Total Capital Total Costs Costs This

  18. CFPL installs products pipeline with directional drilling

    SciTech Connect (OSTI)

    1996-01-01

    Central Florida Pipeline Company (CFPL), a subsidiary of GATX Terminals Corp., Tampa, FL, has used directional drilling under seven water bodies in Hillsborough, Polk and Osceola Counties in constructing its new pipeline from Tampa to Orlando. Primary reason for using directional drilling is to protect the environment by minimizing water turbidity while the 16-inch diameter, 109-mile refined petroleum products pipeline is being installed. Total cost of the project is pegged at $68.5 million. Directional drilling enabled the pipe to be placed about 20 feet below the bottom of: The Alafia River in Riverview with 999 feet drilled; Port Sutton Channel near the Port of Tampa with 2,756 feet drilled; Reedy Creek Swamp at the intersection of Interstate 4 and Highway 192 which had 1,111 feet drilled; Wetland {number_sign}70 southwest of Lake Wales with 1,575 feet drilled; Peace River south of Bartow had 2,470 feet drilled; Bonnet Creek west of Kissimmee had 693 feet drilled. Shingle Creek near the borders of Osceola and Orange Counties with 1,700 feet drilled. This paper reviews the design plans for construction and the emergency response plans should a rupture occur in the line.

  19. Letting The Sun Shine On Solar Costs: An Empirical Investigation Of Photovoltaic Cost Trends In California

    E-Print Network [OSTI]

    Wiser, Ryan; Bolinger, Mark; Cappers, Peter; Margolis, Robert

    2006-01-01

    incentives have impacted pre-rebate installed costs, andMost prominent are capital cost rebates offered to PV systemtwo most significant current rebate programs are overseen by

  20. Research and Development of a Low Cost Solar Collector

    SciTech Connect (OSTI)

    Ansari, Asif; Philip, Lee; Thouppuarachchi, Chirath

    2012-08-01

    This is a Final Technical Report on the Research and Development completed towards the development of a Low Cost Solar Collector conducted under the DOE cost-sharing award EE-0003591. The objective of this project was to develop a new class of solar concentrators with geometries and manufacturability that could significantly reduce the fully installed cost of the solar collector field for concentrated solar thermal power plants. The goal of the project was to achieve an aggressive cost target of $170/m2, a reduction of up to 50% in the total installed cost of a solar collector field as measured against the current industry benchmark of a conventional parabolic trough. The project plan, and the detailed activities conducted under the scope of the DOE Award project addressed all major drivers that affect solar collector costs. In addition to costs, the study also focused on evaluating technical performance of new collector architectures and compared them to the performance of the industry benchmark parabolic trough. The most notable accomplishment of this DOE award was the delivery of a full-scale integrated design, manufacturing and field installation solution for a new class of solar collector architecture which has been classified as the Bi-Planar Fresnel Collector (BPFC) and may be considered as a viable alternative to the conventional parabolic trough, as well as the conventional Fresnel collectors. This was in part accomplished through the design and development, all the way through fabrication and test validation of a new class of Linear Planar Fresnel Collector architecture. This architecture offers a number of key differentiating features which include a planar light-weight frame geometry with small mass-manufacturable elements utilizing flat mirror sections. The designs shows significant promise in reducing the material costs, fabrication costs, shipping costs, and on-site field installation costs compared to the benchmark parabolic trough, as well as the conventional Fresnel collector. The noteworthy design features of the BPFC architecture include the use of relatively cheaper flat mirrors and a design which allows the mirror support beam sections to act as load-bearing structural elements resulting in more than a 36% reduction in the overall structural weight compared to an optimized parabolic trough. Also, it was shown that the utilization of small mass-produced elements significantly lowers mass-production and logistics costs that can more quickly deliver economies of scale, even for smaller installations while also reducing shipping and installation costs. Moreover, unlike the traditional Fresnel trough the BPFC architecture does not require complex articulating drive mechanisms but instead utilizes a standard parabolic trough hydraulic drive mechanism. In addition to the development of the Bi-Planar Fresnel Collector, an optimized conventional space-frame type parabolic trough was also designed, built, analyzed and field-tested during the first phase of this award. The design of the conventional space-frame parabolic collector was refined with extensive FEA and CFD analysis to reduce material costs and re-designed for simpler fabrication and more accurate lower-cost field assembly. This optimized parabolic trough represented an improvement over the state-of-the art of the traditional parabolic trough architecture and also served as a more rigorous and less subjective benchmark that was used for comparison of new candidate design architectures. The results of the expanded 1st phase of the DOE award project showed that both the Optimized Parabolic Trough and the new Bi-Planar Fresnel Collector design concepts failed to meet the primary objectives for the project of achieving a 50% cost reduction from the industry reference total installed cost of $350/m2. Results showed that the BPFC came in at projected total installed cost of $237/m2 representing a 32% savings compared to the industry benchmark conventional parabolic trough. And the cost reduction obtained by the Optimized Parabolic Trough compared to the

  1. Letting The Sun Shine On Solar Costs: An Empirical Investigation Of Photovoltaic Cost Trends In California

    E-Print Network [OSTI]

    Wiser, Ryan; Bolinger, Mark; Cappers, Peter; Margolis, Robert

    2006-01-01

    Total Cost (CPUC) Module Cost Index (CEC, CPUC) CEC CPUC *an external index of worldwide module costs from Strategies

  2. Install and Automatic Blowdown Control System - Steam Tip Sheet #23

    SciTech Connect (OSTI)

    2012-01-01

    This revised AMO steam tip sheet on installing automatic blowdown controls provide how-to advice for improving industrial steam systems using low-cost, proven practices and technologies.

  3. Installation Metered Rack Power

    E-Print Network [OSTI]

    van Hemmen, J. Leo

    . . . . . . . . . . . . . . . . . . . 1 Please recycle . . . . . . . . . . . . . . . . . . . . . . . . 1 Install the PDU interface on the PDU shows the aggregate current being used by the PDU and its attached devices. An alarm occurs if the aggregate current is above the high threshold value or below the low threshold value

  4. Development of a Method Using BIM Technology to Determine the Utility Bill and Total Cost of Ownership of a Single-family Home 

    E-Print Network [OSTI]

    McGarity, Ashley

    2010-07-14

    Perspective ........................................................................ 23 5 Production: Annual Fuel End Use ........................................................................ 26 6 Production: Annual Electric End Use... .............................................. 18 3 Affordable: Amortized Payment of Single-Family Home ................................... 21 4 Method #1, Total Time ......................................................................................... 21 5 Production: Mortgage...

  5. Consider Installing Turbulators on Two- and Three-Pass Firetube Boilers - Steam Tip Sheet #25

    SciTech Connect (OSTI)

    2012-01-01

    This revised AMO tip sheet on installing turbulators on firetube boilers provides how-to advice for improving the system using low-cost, proven practices and technologies.

  6. Consider Installing Turbulators on Two- and Three-Pass Firetube Boilers

    SciTech Connect (OSTI)

    Not Available

    2006-01-01

    This revised ITP tip sheet on installing turbulators on firetube boilers provides how-to advice for improving the system using low-cost, proven practices and technologies.

  7. Consider Installing Turbulators on Two- and Three-Pass Firetube Boilers - Steam Tip Sheet #25

    SciTech Connect (OSTI)

    None

    2006-01-01

    This revised AMO tip sheet on installing turbulators on firetube boilers provides how-to advice for improving the system using low-cost, proven practices and technologies.

  8. Cutting-Edge Savannah River Site Project Avoids Millions in Costs, Removes Chemical Solvents from Underground: Project avoided costs totaling more than $15 million, removed tons of chemical solvents from beneath the Savannah River Site

    Broader source: Energy.gov [DOE]

    AIKEN, S.C. – Workers recently completed a multiyear project that removed more than 33,000 gallons of non-radioactive chemical solvents from beneath a portion of the Savannah River Site (SRS), preventing those pollutants from entering the local water table and helping the site avoid costs of more than $15 million.

  9. The Market Value and Cost of Solar Photovoltaic Electricity Production

    E-Print Network [OSTI]

    Borenstein, Severin

    2008-01-01

    2007 Figure 4: Installed Solar PV Capacity and Annual Valuesolar PV is hardly ever installed in a manner that targets speci?c capacitysolar PV in- stallations in the CEC dataset (a total installed capacity

  10. An Assessment of the Near-Term Costs of Hydrogen Refueling Stations and Station Components

    E-Print Network [OSTI]

    Lipman, T E; Weinert, Jonathan X.

    2006-01-01

    connections) Installation Costs: 1. Engineering and Designstation works properly) 6. Contingency Operating Costs: 1.Feedstock Costs (natural gas, electricity) 2. Equipment

  11. You Don't Need to Raise the Roof: Cutting Solar Permitting Costs...

    Energy Savers [EERE]

    officials, installers, and engineers the information they need to support safe and cost-effective solar rooftop installations. Learn more about the study by visiting...

  12. Low Cost Heliostat Development Phase II Final Report

    SciTech Connect (OSTI)

    Kusek, Stephen M.

    2014-04-21

    The heliostat field in a central receiver plant makes up roughly one half of the total plant cost. As such, cost reductions for the installed heliostat price greatly impact the overall plant cost and hence the plant’s Levelized Cost of Energy. The general trend in heliostat size over the past decades has been to make them larger. One part of our thesis has been that larger and larger heliostats may drive the LCOE up instead of down due to the very nature of the precise aiming and wind-load requirements for typical heliostats. In other words, it requires more and more structure to precisely aim the sunlight at the receiver as one increases heliostat mirror area and that it becomes counter-productive, cost-wise, at some point.

  13. Preemptive scheduling with position costs

    E-Print Network [OSTI]

    In most scheduling models presented in the literature [3, 10], the cost for ... Preemptive scheduling in order to minimize the total position costs also stems.

  14. Hydrogen refueling station costs in Shanghai

    E-Print Network [OSTI]

    Weinert, Jonathan X.; Shaojun, Liu; Ogden, Joan M; Jianxin, Ma

    2007-01-01

    Kingdom; 2004. [8] Amos W. Costs of storing and transportingcon- nections). Capital costs for this equipment must bein an analysis of station costs. Total station construction

  15. Use of experience curves to estimate the future cost of power plants with CO2 capture

    E-Print Network [OSTI]

    Rubin, Edward S.; Yeh, Sonia; Antes, Matt; Berkenpas, Michael; Davison, John

    2007-01-01

    learning rates for capital cost and O&M cost for the sevencomponent to the total capital cost and total O&M cost ofin Table 6, the capital cost and total cost of capture are

  16. The Cost of Transmission for Wind Energy in the United States: A Review of Transmission Planning Studies.

    E-Print Network [OSTI]

    Wiser, Ryan

    2014-01-01

    on U. S . Wind Power Installation, Cost, and Performance30% wind penetration. Wind transmission costs in the severalof Transmission ($/kW-wind) Unit Cost of Transmission ($/

  17. Building a market for small wind: The break-even turnkey cost of residential wind systems in the United States

    E-Print Network [OSTI]

    Edwards, Jennifer L.; Wiser, Ryan; Bolinger, Mark; Forsyth, Trudy

    2004-01-01

    Break-Even Turnkey Cost of Residential Wind Systems in theaggregate installed cost of a small wind system that couldand wind resource class, (2) significant cost reductions

  18. Effects of installing economizers in boilers used in space heating applications

    SciTech Connect (OSTI)

    Gonzalez, M.A.; Medina, M.A.; Schruben, D.L.

    1999-07-01

    This paper discusses how the performance of a boiler can be improved by adding an economizer to preheat the boiler's feedwater. An energy analysis was applied to a boiler and then to both a boiler and an economizer (water pre-heater) to evaluate the benefits of heat recovery. Exergy rates calculated for both the boiler and the economizer determined that the temperature of the stack gases had primary effects on the performance of a boiler. The results from this study showed that 57% of the heat rejected at the boiler's stack could be recovered by installing an economizer to preheat the feedwater. As a result, the average cost savings that would be realized for a 36,400 kg/h (80,000 lbm/h) boiler averages US$8 per hour. The cost savings to steam production averaged US$0.20 per 455 kg (1,000 lbm) of steam and the ration between the cost savings to stack temperature averaged $0.02 per C (1.8 F). For this case, the fuel and the cost savings realized from using an economizer were averaged at 3.8% and 3.7%, respectively. These results translated to total cost savings, for an eight-day period considered, of US$940.

  19. Wind Power: How Much, How Soon, and At What Cost?

    E-Print Network [OSTI]

    Wiser, Ryan H

    2010-01-01

    Annual Report on U.S. Wind Power Installation, Cost, andand costs for rapid wind energy deployment in the US haveinstalled cost for wind projects in the US has increased

  20. The Outlook for CO2 Capture Costs

    E-Print Network [OSTI]

    Common Measures of CCS Cost · Capital cost · Increased cost of electricity · Cost of CO2 avoided · Cost of CO2 captured E.S. Rubin, Carnegie Mellon Elements of Capital Cost Note: · Nomenclature and cost items construction Total Capital Requirement (TCR) E.S. Rubin, Carnegie Mellon Cost of Electricity (COE) COE ($/MWh

  1. Magnet Girder Assembly and Installation

    ScienceCinema (OSTI)

    None

    2013-07-17

    It takes teamwork to assemble and install magnet girders for the storage ring of the National Synchrotron Light Source II. NSLS-II is now under construction at Brookhaven Lab.

  2. Solar Installation Labor Market Analysis

    SciTech Connect (OSTI)

    Friedman, B.; Jordan, P.; Carrese, J.

    2011-12-01

    The potential economic benefits of the growing renewable energy sector have led to increased federal, state, and local investments in solar industries, including federal grants for expanded workforce training for U.S. solar installers. However, there remain gaps in the data required to understand the size and composition of the workforce needed to meet the demand for solar power. Through primary research on the U.S. solar installation employer base, this report seeks to address that gap, improving policymakers and other solar stakeholders understanding of both the evolving needs of these employers and the economic opportunity associated with solar market development. Included are labor market data covering current U.S. employment, expected industry growth, and employer skill preferences for solar installation-related occupations. This study offers an in-depth look at the solar installation sectors. A study published by the Solar Foundation in October 2011 provides a census of labor data across the entire solar value chain.

  3. Net Zero Energy Installations (Presentation)

    SciTech Connect (OSTI)

    Booth, S.

    2012-05-01

    A net zero energy installation (NZEI) is one that produces as much energy from on-site renewable sources as it consumes. NZEI assessment provides a systematic approach to energy projects.

  4. Installation and Commissioning Automated Demand Response Systems

    SciTech Connect (OSTI)

    Global Energy Partners; Pacific Gas and Electric Company; Kiliccote, Sila; Kiliccote, Sila; Piette, Mary Ann; Wikler, Greg; Prijyanonda, Joe; Chiu, Albert

    2008-04-21

    Demand Response (DR) can be defined as actions taken to reduce electric loads when contingencies, such as emergencies and congestion, occur that threaten supply-demand balance, or market conditions raise supply costs. California utilities have offered price and reliability DR based programs to customers to help reduce electric peak demand. The lack of knowledge about the DR programs and how to develop and implement DR control strategies is a barrier to participation in DR programs, as is the lack of automation of DR systems. Most DR activities are manual and require people to first receive notifications, and then act on the information to execute DR strategies. Levels of automation in DR can be defined as follows. Manual Demand Response involves a labor-intensive approach such as manually turning off or changing comfort set points at each equipment switch or controller. Semi-Automated Demand Response involves a pre-programmed demand response strategy initiated by a person via centralized control system. Fully-Automated Demand Response does not involve human intervention, but is initiated at a home, building, or facility through receipt of an external communications signal. The receipt of the external signal initiates pre-programmed demand response strategies. We refer to this as Auto-DR (Piette et. al. 2005). Auto-DR for commercial and industrial facilities can be defined as fully automated DR initiated by a signal from a utility or other appropriate entity and that provides fully-automated connectivity to customer end-use control strategies. One important concept in Auto-DR is that a homeowner or facility manager should be able to 'opt out' or 'override' a DR event if the event comes at time when the reduction in end-use services is not desirable. Therefore, Auto-DR is not handing over total control of the equipment or the facility to the utility but simply allowing the utility to pass on grid related information which then triggers facility defined and programmed strategies if convenient to the facility. From 2003 through 2006 Lawrence Berkeley National Laboratory (LBNL) and the Demand Response Research Center (DRRC) developed and tested a series of demand response automation communications technologies known as Automated Demand Response (Auto-DR). In 2007, LBNL worked with three investor-owned utilities to commercialize and implement Auto-DR programs in their territories. This paper summarizes the history of technology development for Auto-DR, and describes the DR technologies and control strategies utilized at many of the facilities. It outlines early experience in commercializing Auto-DR systems within PG&E DR programs, including the steps to configure the automation technology. The paper also describes the DR sheds derived using three different baseline methodologies. Emphasis is given to the lessons learned from installation and commissioning of Auto-DR systems, with a detailed description of the technical coordination roles and responsibilities, and costs.

  5. Factors Affecting PMU Installation Costs (October 2014) | Department of

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustmentsShirleyEnergy A plug-inPPLforLDRD Report to Congress MoreHyd rog enOffice|DOEofPrimus

  6. CALiPER Report 21.3. Cost Effectiveness of Linear (T8) LED Lamps

    SciTech Connect (OSTI)

    2014-05-01

    Meeting performance expectations is important for driving adoption of linear LED lamps, but cost-effectiveness may be an overriding factor in many cases. Linear LED lamps cost more initially than fluorescent lamps, but energy and maintenance savings may mean that the life-cycle cost is lower. This report details a series of life-cycle cost simulations that compared a two-lamp troffer using LED lamps (38 W total power draw) or fluorescent lamps (51 W total power draw) over a 10-year study period. Variables included LED system cost ($40, $80, or $120), annual operating hours (2,000 hours or 4,000 hours), LED installation time (15 minutes or 30 minutes), and melded electricity rate ($0.06/kWh, $0.12/kWh, $0.18/kWh, or $0.24/kWh). A full factorial of simulations allows users to interpolate between these values to aid in making rough estimates of economic feasibility for their own projects. In general, while their initial cost premium remains high, linear LED lamps are more likely to be cost-effective when electric utility rates are higher than average and hours of operation are long, and if their installation time is shorter.

  7. CALiPER Report 21.3: Cost-Effectiveness of Linear (T8) LED Lamps

    SciTech Connect (OSTI)

    Miller, Naomi J.; Perrin, Tess E.; Royer, Michael P.

    2014-05-27

    Meeting performance expectations is important for driving adoption of linear LED lamps, but cost-effectiveness may be an overriding factor in many cases. Linear LED lamps cost more initially than fluorescent lamps, but energy and maintenance savings may mean that the life-cycle cost is lower. This report details a series of life-cycle cost simulations that compared a two-lamp troffer using LED lamps (38 W total power draw) or fluorescent lamps (51 W total power draw) over a 10-year study period. Variables included LED system cost ($40, $80, or $120), annual operating hours (2,000 hours or 4,000 hours), LED installation time (15 minutes or 30 minutes), and melded electricity rate ($0.06/kWh, $0.12/kWh, $0.18/kWh, or $0.24/kWh). A full factorial of simulations allows users to interpolate between these values to aid in making rough estimates of economic feasibility for their own projects. In general, while their initial cost premium remains high, linear LED lamps are more likely to be cost-effective when electric utility rates are higher than average and hours of operation are long, and if their installation time is shorter.

  8. Better Buildings Neighborhood Program Data Installed Measures...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Installed Measures Better Buildings Neighborhood Program Data Installed Measures Building project data for 75,110 single-family homes upgraded between July 1, 2010, and September...

  9. Optimizing Installation, Operation, and Maintenance at Offshore...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Optimizing Installation, Operation, and Maintenance at Offshore Wind Projects in the United States Optimizing Installation, Operation, and Maintenance at Offshore Wind Projects in...

  10. DOE Announces $27 Million to Reduce Costs of Solar Energy Projects...

    Energy Savers [EERE]

    Announces 27 Million to Reduce Costs of Solar Energy Projects, Streamline Permitting and Installations DOE Announces 27 Million to Reduce Costs of Solar Energy Projects,...

  11. JUMP DIFFUSION OPTION WITH TRANSACTION COSTS

    E-Print Network [OSTI]

    Mocioalca, Oana

    JUMP DIFFUSION OPTION WITH TRANSACTION COSTS "non-systematic" risk, inclusive of transaction costs. We compute the total transac- tion costs and the turnover for different options, transaction costs, and revision intervals

  12. Title: Greening the Grid: The Cost-Effectiveness of Residential Solar Programs in Oregon

    E-Print Network [OSTI]

    Tullos, Desiree

    Nadine Hanhan, MS Title: Greening the Grid: The Cost-Effectiveness of Residential Solar Programs purchase agreements from third-party installers, and solar leasing ­ and compares the cost of these options to not installing. The paper considers the problem of solar installation to be a cost minimization problem

  13. Renewable Energy Opportunities at the Kanto Installations, Japan

    SciTech Connect (OSTI)

    Solana, Amy E.; Horner, Jacob A.; Russo, Bryan J.; Gorrissen, Willy J.; Kora, Angela R.; Weimar, Mark R.; Hand, James R.; Orrell, Alice C.; Williamson, Jennifer L.

    2010-09-24

    This document provides an overview of renewable resource development potential at the U.S. Army installations in the Kanto region in Japan, which includes Camp Zama, Yokohama North Dock, Sagamihara Family Housing Area (SFHA), Sagami General Depot, and Akasaka Press Center. This effort focuses on grid-connected generation of electricity from renewable energy sources and also on ground source heat pumps for heating and cooling buildings. The effort was funded by the Huntsville Army Corps of Engineers, and includes the development of a methodology for renewable resource assessment at Army installations located on foreign soil. The methodology is documented in Renewable Energy Assessment Methodology for Japanese OCONUS Army Installations. The site visit to the Kanto installations took place on April 5 and 6, 2010. At the current time, there are some renewable technologies that show economic potential. Because of siting restrictions and the small size of these installations, development of most renewable energy technologies will likely be limited to Camp Zama. Project feasibility is based on installation-specific resource availability and energy costs and projections based on accepted life-cycle cost methods. Development of any renewable energy project will be challenging, as it will require investigation into existing contractual obligations, new contracts that could be developed, the legality of certain partnerships, and available financing avenues, which involves the U.S. Forces Japan (USFJ), the Government of Japan (GOJ), and a number of other parties on both sides. The Army will not be able to implement a project without involvement and approval from the other services and multiple levels of Japanese government. However, implementation of renewable energy projects could be an attractive method for GOJ to reduce greenhouse gas emissions and lower annual utility payments to USFJ. This report recommends projects to pursue and offers approaches to use. The most promising opportunities include waste-to-energy and ground source heat pumps. Solar photovoltaics (PV) may also prove successful. Other resources were found to be insufficient on the Kanto installations.

  14. SeaStar: Subsea cluster manifold system design and installation

    SciTech Connect (OSTI)

    Mason, P.G.T.; Upchurch, J.L.

    1996-12-31

    The SeaStar Cluster Manifold system was engineered as a low cost alternative to larger and more expensive completion template designs. Utilizing field-proven equipment and installation techniques, it was the first of its kind to be installed in the Gulf of Mexico. The Cluster Manifold system allows the connection of flowlines from adjacent satellite wells and numerous infield flowlines consisting of export, service, and methanol lines. With new technological advances, and a variety of flowline connection systems on the market today, deep water completions are being used with increasing frequency. Subsea operations are becoming more routine and installation times are being reduced. The SeaStar system was successfully installed in Garden Banks Block 70/71 in the Gulf of Mexico during the first quarter of 1995. Currently two 4 x 2-in. 10,000 psi lay-away trees are installed and connected to the manifold. Production is being processed at a Marathon platform in Vermilion Block 386B approximately 13.5 miles away from the subsea installation.

  15. Volume XVII, No. 5 A publication of the U.S. Army Installation Management Agency

    E-Print Network [OSTI]

    US Army Corps of Engineers

    /October 2005 U.S. Army Installation Management Agency In this issue: Energy and Water Conservation #12;2 Public Volkman 16 Commentary: Sustainable energy demands decisions that look beyond cost by Eileen WesterveltVolume XVII, No. 5 A publication of the U.S. Army Installation Management Agency September

  16. Consider Installing High-Pressure Boilers with Backpressure Turbine-Generators - Steam Tip Sheet #22

    SciTech Connect (OSTI)

    2012-01-01

    This revised AMO tip sheet on installing high-pressure boilers provides how-to advice for improving industrial steam systems using low-cost, proven practices and technologies.

  17. Install Removable Insulation on Valves and Fittings - Steam Tip Sheet #17

    SciTech Connect (OSTI)

    2012-01-01

    This revised AMO tip sheet on installing removable insulation on valves and fittings provides how-to advice for improving the system using low-cost, proven practices and technologies.

  18. Consider Installing High-Pressure Boilers with Backpressure Turbine-Generators

    SciTech Connect (OSTI)

    Not Available

    2006-01-01

    This revised ITP tip sheet on installing high-pressure boilers provides how-to advice for improving industrial steam systems using low-cost, proven practices and technologies.

  19. Startup Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter discusses startup costs for construction and environmental projects, and estimating guidance for startup costs.

  20. Aasgard subsea installation on schedule

    SciTech Connect (OSTI)

    Perdue, J.M.

    1998-09-01

    Statoil`s Aasgard A FPSO vessel is set to sail away from the Aker Stord yard on November 22, 1998, and construction of the Aasgard B semisubmersible gas platform has begun at the Daewoo yard in Korea. While Aasgard A and Aasgard B are receiving a lot of attention on land, the Aasgard subsea installation is quietly being readied for the big day.

  1. Facility Energy Decision System (FEDS) Assessment Report for US Army Garrison, Japan - Honshu Installations

    SciTech Connect (OSTI)

    Kora, Angela R.; Brown, Daryl R.; Dixon, Douglas R.

    2010-03-09

    This report documents an assessment was performed by a team of engineers from Pacific Northwest National Laboratory (PNNL) under contract to the Installation Management Command (IMCOM) Pacific Region Office (PARO). The effort used the Facility Energy Decision System (FEDS) model to determine how energy is consumed at five U.S. Army Garrison-Japan (USAG-J) installations in the Honshu area, identify the most cost-effective energy retrofit measures, and calculate the potential energy and cost savings.

  2. SOM ARRA Grant Activity Proposals Submitted as of 7-15-2010 Project Costs*

    E-Print Network [OSTI]

    Bushman, Frederic

    SOM ARRA Grant Activity Proposals Submitted as of 7-15-2010 Project Costs* Total # of Proposals 1,264 Total Project Costs $1,093,036,719 Total Direct Costs $803,739,425 Total Indirects $290,408,131 Awards Received as of 2-11-2011 Project Costs* Year 1 Costs Total # of Awards 333 Total Project Costs $186

  3. Project Profile: High-Concentration, Low-Cost Parabolic Trough...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    of the larger aperture, while incorporating additional advancements that substantially lower installed solar field costs. For example, the reflective film surfaces are being...

  4. Retail Infrastructure Costs Comparison for Hydrogen and Electricity for Light-Duty Vehicles: Preprint

    SciTech Connect (OSTI)

    Melaina, M.; Sun, Y.; Bush, B.

    2014-08-01

    Both hydrogen and plug-in electric vehicles offer significant social benefits to enhance energy security and reduce criteria and greenhouse gas emissions from the transportation sector. However, the rollout of electric vehicle supply equipment (EVSE) and hydrogen retail stations (HRS) requires substantial investments with high risks due to many uncertainties. We compare retail infrastructure costs on a common basis - cost per mile, assuming fueling service to 10% of all light-duty vehicles in a typical 1.5 million person city in 2025. Our analysis considers three HRS sizes, four distinct types of EVSE and two distinct EVSE scenarios. EVSE station costs, including equipment and installation, are assumed to be 15% less than today's costs. We find that levelized retail capital costs per mile are essentially indistinguishable given the uncertainty and variability around input assumptions. Total fuel costs per mile for battery electric vehicle (BEV) and plug-in hybrid vehicle (PHEV) are, respectively, 21% lower and 13% lower than that for hydrogen fuel cell electric vehicle (FCEV) under the home-dominant scenario. Including fuel economies and vehicle costs makes FCEVs and BEVs comparable in terms of costs per mile, and PHEVs are about 10% less than FCEVs and BEVs. To account for geographic variability in energy prices and hydrogen delivery costs, we use the Scenario Evaluation, Regionalization and Analysis (SERA) model and confirm the aforementioned estimate of cost per mile, nationally averaged, but see a 15% variability in regional costs of FCEVs and a 5% variability in regional costs for BEVs.

  5. Field installation proves coiled tubing ESP completions successful

    SciTech Connect (OSTI)

    Tovar, J.J.; Head, P.; Jordan, R.

    1995-06-01

    Coiled tubing (CT) technology has contributed new and innovative solutions for wells using electrical submersible pumps (ESP). A CT-ESP deployment system was developed as part of a joint industry project to take advantage of this new technology. Ten oil and service companies and the EEC, under the Thermie program, participated in its development. Two main areas were identified to introduce these innovations. The first was deployment and well control. This area has a great impact on the safety and operational aspects of installing and servicing ESPs. The second is cost. As ESPs are considered for new field developments and recompletion of old fields, installation and workover costs play a major role in the selection of completion alternatives. One of the main limitations of ESPs in the past has been the economics of installation and uncertainty about pump life. With focus in these two major areas, a system was successfully produced that offers considerable advantages over existing technologies. The reduction in rig time and equipment cost makes this alternative very attractive for areas where technical and economic obstacles such as live well deployment and high operating cost limit the use of ESP technology. Two field tests have been carried successfully during the development of this system.

  6. Determination of Total Petroleum Hydrocarbons (TPH) Using Total Carbon Analysis

    SciTech Connect (OSTI)

    Ekechukwu, A.A.

    2002-05-10

    Several methods have been proposed to replace the Freon(TM)-extraction method to determine total petroleum hydrocarbon (TPH) content. For reasons of cost, sensitivity, precision, or simplicity, none of the replacement methods are feasible for analysis of radioactive samples at our facility. We have developed a method to measure total petroleum hydrocarbon content in aqueous sample matrixes using total organic carbon (total carbon) determination. The total carbon content (TC1) of the sample is measured using a total organic carbon analyzer. The sample is then contacted with a small volume of non-pokar solvent to extract the total petroleum hydrocarbons. The total carbon content of the resultant aqueous phase of the extracted sample (TC2) is measured. Total petroleum hydrocarbon content is calculated (TPH = TC1-TC2). The resultant data are consistent with results obtained using Freon(TM) extraction followed by infrared absorbance.

  7. Total Imports

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight Paths30,2,8,Product: Total Crude

  8. Robust Cost Colorings Takuro Fukunaga

    E-Print Network [OSTI]

    Halldórsson, Magnús M.

    Robust Cost Colorings Takuro Fukunaga Magn´us M. Halld´orsson Hiroshi Nagamochi Abstract We consider graph coloring problems where the cost of a coloring is the sum of the costs of the colors, and the cost of a color is a monotone concave function of the total weight of the class. This models resource

  9. Low-cost thin-material solar technology, the key to a viable energy alternative

    SciTech Connect (OSTI)

    Wilhelm, W.G.; Ripel, B.D.

    1985-08-01

    The creation of a solar technology based on a dramatic reduction in material intensity and greater simplicity of design is the result of a cost-guided research approach. It takes advantage of a progressive material science based on polymer films and unique construction methods that optimize material requirements, performance and durability. The current level of technical maturity has revealed a solar collector design that has the potential for a dramatic reduction in installed cost while maintaining high thermal performance and durability. In addition, the same methodology has guided total solar system designs with similar economies and performance advantages.

  10. Evaluation of Trenchless Installation Technology for Radioactive Wastewater Piping Applications

    SciTech Connect (OSTI)

    Robinson, Sharon M; Jubin, Robert Thomas; Patton, Bradley D; Sullivan, Nicholas M; Bugbee, Kathy P

    2009-09-01

    The U.S. Department of Energy (DOE) Office of Environmental Management (EM) cleanup mission at Oak Ridge National Laboratory (ORNL) includes dispositioning facilities, contaminated legacy materials/waste, and contamination sources and remediation of soil under facilities, groundwater, and surface water to support final Records of Decision (RODs). The Integrated Facilities Disposition Project (IFDP) is a roughly $15B project for completion of the EM mission at Oak Ridge, with a project duration of up to 35 years. The IFDP Mission Need Statement - Critical Decision-0 (CD-0) - was approved by DOE in July 2007, and the IFDP Alternative Selection and Cost Range - Critical Decision-1 (CD-1) - was approved in November 2008. The IFDP scope includes reconfiguration of waste collection and treatment systems as needed to complete the IFDP remediation and decontamination and decommissioning (D&D) missions in a safe and cost-effective manner while maintaining compliance with all governing regulations and bodies and preserving the support of continuing operations at ORNL. A step in the CD-1 approval process included an external technical review (ETR) of technical approaches proposed in the CD-1 document related to the facility reconfiguration for the ORNL radioactive waste and liquid low-level waste management systems. The ETR team recommended that the IFDP team consider the use of trenchless technologies for installing pipelines underground in and around contaminated sites as part of the alternatives evaluations required in support of the CD-2 process. The team specifically recommended evaluating trenchless technologies for installing new pipes in existing underground pipelines as an alternative to conventional open trench installation methods. Potential benefits could include reduction in project costs, less costly underground piping, fewer disruptions of ongoing and surface activities, and lower risk for workers. While trenchless technologies have been used extensively in the sanitary sewer and natural gas pipeline industries, they have been used far less in contaminated environments. Although trenchless technologies have been used at ORNL in limited applications to install new potable water and gas lines, the technologies have not been used in radioactive applications. This study evaluates the technical risks, benefits, and economics for installing gravity drained and pressurized piping using trenchless technologies compared to conventional installation methods for radioactive applications under ORNL geological conditions. A range of trenchless installation technologies was reviewed for this report for general applicability for replacing existing contaminated piping and/or installing new pipelines in potentially contaminated areas. Installation methods that were determined to have potential for use in typical ORNL contaminated environments were then evaluated in more detail for three specific ORNL applications. Each feasible alternative was evaluated against the baseline conventional open trench installation method using weighted criteria in the areas of environment, safety, and health (ES&H); project cost and schedule; and technical operability. The formulation of alternatives for evaluation, the development of selection criteria, and the scoring of alternatives were performed by ORNL staff with input from vendors and consultants. A description of the evaluation methodology and the evaluation results are documented in the following sections of this report.

  11. Hawaii Natural Energy Institute installs PV systems at public schools Pacific Business News

    E-Print Network [OSTI]

    well-established products in the solar industry. Three net-zero energy buildings created by CaliforniaHawaii Natural Energy Institute installs PV systems at public schools Pacific Business News Energy Institute said Tuesday that it has recently installed six solar photovoltaic systems totaling 15

  12. Groundwater Monitoring Well Installation Work Plan

    E-Print Network [OSTI]

    Groundwater Monitoring Well Installation Work Plan CSMRI Site Prepared for: Colorado School;CSMRI Site Groundwater Monitoring Well Installation Work Plan December 6, 2006 Page ii Table of Contents

  13. Validating the Estimated Cost of Saving Water Through Infrastructure Rehabilitation in the Texas Lower Rio Grande Valley 

    E-Print Network [OSTI]

    Sturdivant, A. W.; Rister, M.; Lacewell, R. D.; Rogers, C. S.

    2006-01-01

    : Allen W. Sturdivant; Extension Associate a, b M. Edward Rister; Professor and Associate Head a, c Ronald D. Lacewell; Professor and Assistant Vice Chancellor a, c Callie S. Rogers; Student Technician a Background The original economic analysis reporting... $ 20,071 ....................same As shown in Table 1, the original estimated initial capital construction costs totaled $3,585,300 with the revised, actual value equaling $3,278,276 (Balcombe). The installation period was projected to take one year...

  14. Automated solar collector installation design

    DOE Patents [OSTI]

    Wayne, Gary; Frumkin, Alexander; Zaydman, Michael; Lehman, Scott; Brenner, Jules

    2014-08-26

    Embodiments may include systems and methods to create and edit a representation of a worksite, to create various data objects, to classify such objects as various types of pre-defined "features" with attendant properties and layout constraints. As part of or in addition to classification, an embodiment may include systems and methods to create, associate, and edit intrinsic and extrinsic properties to these objects. A design engine may apply of design rules to the features described above to generate one or more solar collectors installation design alternatives, including generation of on-screen and/or paper representations of the physical layout or arrangement of the one or more design alternatives.

  15. Sandia Energy - Installation Energy Security

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home RoomPreservation of Fe(II)Geothermal Energy & DrillingNanomaterialsAssuranceInstallation

  16. Carpe Diem: Install Insulated Roman Shades

    Broader source: Energy.gov [DOE]

    As I mentioned in yesterday's blog, I had insulated window quilts installed on most of my home's windows.

  17. Operating Costs Estimates Cost Indices

    E-Print Network [OSTI]

    Boisvert, Jeff

    cost projections · Chemical Engineering (CE) Plant Construction Cost Index ­ Base value = 100 in 1957.0 in 2Q 2001 · Engineering News Record (ENR) · Nelson Refinery (NR) Construction Cost Index Cost Indices available for estimation are based upon the past · These data must be updated using cost indexes . · Cost

  18. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01

    on U.S. Wind Power Installation, Cost, and PerformanceTransmission ($/kW-wind) Unit Cost (Capacity-weighted) Windof Transmission ($/MWh- wind) Unit Cost (Capacity-weighted)

  19. 2011 Cost of Wind Energy Review

    SciTech Connect (OSTI)

    Tegen, S.; Lantz, E.; Hand, M.; Maples, B.; Smith, A.; Schwabe, P.

    2013-03-01

    This report describes the levelized cost of energy (LCOE) for a typical land-based wind turbine installed in the United States in 2011, as well as the modeled LCOE for a fixed-bottom offshore wind turbine installed in the United States in 2011. Each of the four major components of the LCOE equation are explained in detail, such as installed capital cost, annual energy production, annual operating expenses, and financing, and including sensitivity ranges that show how each component can affect LCOE. These LCOE calculations are used for planning and other purposes by the U.S. Department of Energy's Wind Program.

  20. Low-cost light-weight thin material solar heating system

    SciTech Connect (OSTI)

    Wilhelm, W.G.

    1985-03-01

    Presented in this paper are innovative concepts to substantially reduce the cost of residential solar application. They were based on a research and development approach that establishes cost goals which if successfully met can insure high marketability. Included in this cost goal-oriented approach is the additional need to address aesthetics and performance. With such constraints established, designs were initialized, tested, and iterated towards appropriate solutions. These solutions are based on methods for reducing the material intensity of the products, improving the simplicity for ease of production, and reducing the cost of installation. Such a development approach has yielded past proof-of-concept designs in the solar collector and in the other components that constitute a total solar heating system.

  1. Transmission line capital costs

    SciTech Connect (OSTI)

    Hughes, K.R.; Brown, D.R.

    1995-05-01

    The displacement or deferral of conventional AC transmission line installation is a key benefit associated with several technologies being developed with the support of the U.S. Department of Energy`s Office of Energy Management (OEM). Previous benefits assessments conducted within OEM have been based on significantly different assumptions for the average cost per mile of AC transmission line. In response to this uncertainty, an investigation of transmission line capital cost data was initiated. The objective of this study was to develop a database for preparing preliminary estimates of transmission line costs. An extensive search of potential data sources identified databases maintained by the Bonneville Power Administration (BPA) and the Western Area Power Administration (WAPA) as superior sources of transmission line cost data. The BPA and WAPA data were adjusted to a common basis and combined together. The composite database covers voltage levels from 13.8 to 765 W, with cost estimates for a given voltage level varying depending on conductor size, tower material type, tower frame type, and number of circuits. Reported transmission line costs vary significantly, even for a given voltage level. This can usually be explained by variation in the design factors noted above and variation in environmental and land (right-of-way) costs, which are extremely site-specific. Cost estimates prepared from the composite database were compared to cost data collected by the Federal Energy Regulatory Commission (FERC) for investor-owned utilities from across the United States. The comparison was hampered because the only design specifications included with the FERC data were voltage level and line length. Working within this limitation, the FERC data were not found to differ significantly from the composite database. Therefore, the composite database was judged to be a reasonable proxy for estimating national average costs.

  2. Design and installation manual for thermal energy storage

    SciTech Connect (OSTI)

    Cole, R L; Nield, K J; Rohde, R R; Wolosewicz, R M

    1980-01-01

    The purpose of this manual is to provide information on the design and installation of thermal energy storage in active solar systems. It is intended for contractors, installers, solar system designers, engineers, architects, and manufacturers who intend to enter the solar energy business. The reader should have general knowledge of how solar heating and cooling systems operate and knowledge of construction methods and building codes. Knowledge of solar analysis methods such as f-Chart, SOLCOST, DOE-1, or TRNSYS would be helpful. The information contained in the manual includes sizing storage, choosing a location for the storage device, and insulation requirements. Both air-based and liquid-based systems are covered with topics on designing rock beds, tank types, pump and fan selection, installation, costs, and operation and maintenance. Topics relevant to latent heat storage include properties of phase-change materials, sizing the storage unit, insulating the storage unit, available systems, and cost. Topics relevant to heating domestic water include safety, single- and dual-tank systems, domestic water heating with air- and liquid-based space heating systems, and stand alone domestics hot water systems. Several appendices present common problems with storage systems and their solutions, heat transfer fluid properties, economic insulation thickness, heat exchanger sizing, and sample specifications for heat exchangers, wooden rock bins, steel tanks, concrete tanks, and fiberglass-reinforced plastic tanks.

  3. Installing and Maintaining a Small Wind Electric System | Department...

    Office of Environmental Management (EM)

    Installing and Maintaining a Small Wind Electric System Installing and Maintaining a Small Wind Electric System Installing and Maintaining a Small Wind Electric System If you went...

  4. Departments of Energy, Defense Partner to Install Fuel Cell Backup...

    Energy Savers [EERE]

    Departments of Energy, Defense Partner to Install Fuel Cell Backup Power Units at Eight Military Installations Departments of Energy, Defense Partner to Install Fuel Cell Backup...

  5. Improved supplier selection and cost management for globalized automotive production

    E-Print Network [OSTI]

    Franken, Joseph P., II (Joseph Philip)

    2012-01-01

    For many manufacturing and automotive companies, traditional sourcing decisions rely on total landed cost models to determine the cheapest supplier. Total landed cost models calculate the cost to purchase a part plus all ...

  6. Assessing the costs of solar power plants for the Island of Roatàn

    E-Print Network [OSTI]

    Huwe, Ethan (Ethan L.)

    2011-01-01

    This is an analysis assessing the installation costs of different solar power plant technologies and the current commercial availability for installation on the Island or Roatàn. Commercial large-scale power plants have ...

  7. Technology Solutions Case Study: A Homeowner’s Guide to Window Air Conditioner Installation for Efficiency and Comfort

    SciTech Connect (OSTI)

    C. Booten

    2013-06-01

    This fact sheet offers a step-by-step guide to proper installation of window air conditioning units, in order to improve energy efficiency, cost savings, and comfort for homeowners.

  8. Wind power costs in Portugal Saleiro, Carla

    E-Print Network [OSTI]

    Wind power costs in Portugal Saleiro, Carla Department of Biological Engineering, University, following the European tendency. This analysis sets out to evaluate the total generating cost of wind power and CCGT in Portugal. A life cycle cost analysis was conducted, including investment costs, O&M costs, fuel

  9. The Nuclear Installations (Dangerous Occurrences) Regulations 1965 

    E-Print Network [OSTI]

    Lee, Fred; Ross, William

    1965-01-01

    STATUTORY INSTRUMENTS 1965 No. 1824 ATOMIC ENERGY AND RADIOACTIVE SUBSTANCES LICENSING AND REGULATION OF SITES The Nuclear Installations (Dangerous Occurrences) Regulations 1965...

  10. Sequential Linker Installation: Precise Placement of Functional...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Sequential Linker Installation: Precise Placement of Functional Groups in Multivariate Metal-Organic Frameworks Previous Next List Yuan, Shuai; Lu, Weigang; Chen, Ying-Pin; Zhang,...

  11. Installing and Maintaining a Small Wind Electric System

    Broader source: Energy.gov [DOE]

    Installing a small wind electric system? Proper installation and maintenance are key to getting the most out of your system.

  12. Photovoltaic Installations at Williams College Ruth Aronoff

    E-Print Network [OSTI]

    Aalberts, Daniel P.

    generation using solar power. Photovoltaic (PV) panel installations are a simple way for the College facilities, it is now evaluating in detail the environmental impact of these actions. In addition to making1 Photovoltaic Installations at Williams College Ruth Aronoff Williams Luce Project SUMMARY

  13. A DISTRIBUTED AUTOMATION SYSTEM FOR ELECTROPHYSICAL INSTALLATIONS

    E-Print Network [OSTI]

    Kozak, Victor R.

    A DISTRIBUTED AUTOMATION SYSTEM FOR ELECTROPHYSICAL INSTALLATIONS V.R. Kozak Budker Institute There was designed a set of devices for automation systems of physical installations. On this basis approach. KEY WORDS Automation, systems, applications, CANBUS, embedded, controller. 1. Introduction Budker

  14. Arduino Tool: For Interactive Artwork Installations

    E-Print Network [OSTI]

    Shaikh, Murtaza Hussain

    2012-01-01

    The emergence of the digital media and computational tools has widened the doors for creativity. The cutting edge in the digital arts and role of new technologies can be explored for the possible creativity. This gives an opportunity to involve arts with technologies to make creative works. The interactive artworks are often installed in the places where multiple people can interact with the installation, which allows the art to achieve its purpose by allowing the people to observe and involve with the installation. The level of engagement of the audience depends on the various factors such as aesthetic satisfaction, how the audience constructs meaning, pleasure and enjoyment. The method to evaluate these experiences is challenging as it depends on integration between the artificial life and real life by means of human computer interaction. This research investigates "How Adriano fits for creative and interactive artwork installations?" using an artwork installation in the campus of NTNU (Norwegian University...

  15. Operating Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter is focused on capital costs for conventional construction and environmental restoration and waste management projects and examines operating cost estimates to verify that all elements of the project have been considered and properly estimated.

  16. Building America Top Innovations 2012: Low-Cost Ventilation in Production Housing

    SciTech Connect (OSTI)

    2013-01-01

    This Building America Top Innovations profile describes Building America research on simple whole-house ventilation systems that cost less than $350 to install and meet code requirements.

  17. An overview of the sustainability of solid waste management at military installations

    E-Print Network [OSTI]

    Borglin, S.

    2010-01-01

    in the soil. The advantage of pyrolysis over conventionalsoil, air water Social and or/ market acceptance Waste reduction (to landfills) Energy savings/production Cost Totals Pyrolysis

  18. Solar hot water system installed at Las Vegas, Nevada. Final report

    SciTech Connect (OSTI)

    None

    1981-01-01

    The solar hot water system installed at LaQuinta Motor Inn Inc., at Las Vegas, Nevada is described. The Inn is a three-story building with a flat roof for installation of the solar panels. The system consists of 1200 square feet of liquid flat plate collectors, a 2500 gallon insulated vertical steel storage tank, two heat exchangers and pumps and controls. The system was designed to supply approximately 74 percent of the total hot water load.

  19. Cost analysis guidelines

    SciTech Connect (OSTI)

    Strait, R.S.

    1996-01-10

    The first phase of the Depleted Uranium Hexafluoride Management Program (Program)--management strategy selection--consists of several program elements: Technology Assessment, Engineering Analysis, Cost Analysis, and preparation of an Environmental Impact Statement (EIS). Cost Analysis will estimate the life-cycle costs associated with each of the long-term management strategy alternatives for depleted uranium hexafluoride (UF6). The scope of Cost Analysis will include all major expenditures, from the planning and design stages through decontamination and decommissioning. The costs will be estimated at a scoping or preconceptual design level and are intended to assist decision makers in comparing alternatives for further consideration. They will not be absolute costs or bid-document costs. The purpose of the Cost Analysis Guidelines is to establish a consistent approach to analyzing of cost alternatives for managing Department of Energy`s (DOE`s) stocks of depleted uranium hexafluoride (DUF6). The component modules that make up the DUF6 management program differ substantially in operational maintenance, process-options, requirements for R and D, equipment, facilities, regulatory compliance, (O and M), and operations risk. To facilitate a consistent and equitable comparison of costs, the guidelines offer common definitions, assumptions or basis, and limitations integrated with a standard approach to the analysis. Further, the goal is to evaluate total net life-cycle costs and display them in a way that gives DOE the capability to evaluate a variety of overall DUF6 management strategies, including commercial potential. The cost estimates reflect the preconceptual level of the designs. They will be appropriate for distinguishing among management strategies.

  20. INDIRECT COST CALCULATION [IN REVERSE] YOU WANT TO CALCULATE THE DIRECT COSTS

    E-Print Network [OSTI]

    Finley Jr., Russell L.

    INDIRECT COST CALCULATION [IN REVERSE] YOU WANT TO CALCULATE THE DIRECT COSTS YOU KNOW WHAT THE TUITION, STIPEND AND EQUIPMENT COSTS ARE YOU KNOW WHAT THE TOTAL COST IS CALCULATION IS USING THE 2010 FED F&A RATE FOR WSU OF 52% (.52) [ DIRECT COST ­ TUITION ­ STIPEND ­ EQUIPMENT] (.52 ) + DIRECT

  1. Structural considerations for solar installers : an approach for small, simplified solar installations or retrofits.

    SciTech Connect (OSTI)

    Richards, Elizabeth H.; Schindel, Kay; Bosiljevac, Tom; Dwyer, Stephen F.; Lindau, William; Harper, Alan

    2011-12-01

    Structural Considerations for Solar Installers provides a comprehensive outline of structural considerations associated with simplified solar installations and recommends a set of best practices installers can follow when assessing such considerations. Information in the manual comes from engineering and solar experts as well as case studies. The objectives of the manual are to ensure safety and structural durability for rooftop solar installations and to potentially accelerate the permitting process by identifying and remedying structural issues prior to installation. The purpose of this document is to provide tools and guidelines for installers to help ensure that residential photovoltaic (PV) power systems are properly specified and installed with respect to the continuing structural integrity of the building.

  2. Facility Location with Hierarchical Facility Costs Zoya Svitkina #

    E-Print Network [OSTI]

    Tardos, Ã?va

    Facility Location with Hierarchical Facility Costs Zoya Svitkina # â?? Eva Tardos + Abstract We consider the facility location problem with hierarchi­ cal facility costs, and give a (4 installation costs. Shmoys, Swamy and Levi [13] gave an approxi­ mation algorithm for a two­level version

  3. Federal Grant Fully Funds Small Turbine Installation at Maine Senior Housing Complex

    SciTech Connect (OSTI)

    Not Available

    2008-01-01

    In March 2007, local agencies in Maine launched an effort to reduce energy costs for residents of a subsidized elderly housing complex in Winter Harbor, resulting in a federal Residential Energy Assistance Challenge (REACH) grant that entirely funded the installation of a 10-kW Bergey Excel turbine. This fact sheet describes the project, including difficulties encountered during the permitting process and a summary of the costs covered by the REACH grant.

  4. Net Zero Energy Military Installations: A Guide to Assessment and Planning

    SciTech Connect (OSTI)

    Booth, S.; Barnett, J.; Burman, K.; Hambrick, J.; Westby, R.

    2010-08-01

    The U.S. Department of Defense (DoD) recognizes the strategic importance of energy to its mission, and is working to reduce energy consumption and enhance energy self-sufficiency by drawing on local clean energy sources. A joint initiative formed between DoD and the U.S. Department of Energy (DOE) in 2008 to address military energy use led to a task force to examine the potential for net zero energy military installations, which would produce as much energy on site as they consume in buildings, facilities, and fleet vehicles. This report presents an assessment and planning process to examine military installations for net zero energy potential. Net Zero Energy Installation Assessment (NZEIA) presents a systematic framework to analyze energy projects at installations while balancing other site priorities such as mission, cost, and security.

  5. The Social Costs of an MTBE Ban in California

    E-Print Network [OSTI]

    Rausser, Gordon C.; Adams, Gregory D.; Montgomery, W. David; Smith, Anne E.

    2005-01-01

    California Energy Commission, Staff Report: Supply and CostCalifornia Energy Commission. Staff Report: Supply and Costthe total cost of gasoline in California. California Energy

  6. AIR LEAKAGE OF NEWLY INSTALLED RESIDENTIAL WINDOWS

    E-Print Network [OSTI]

    Weidt, John

    2013-01-01

    Tables 2.0.2a 2.0.2b PAGE Air Leakage Through Sash/FrameOperation Types . . . . . Air Leakage of Installed WindowsComparison of Window Types Air Leakage Performance of

  7. Interactive Stereoscopic Installation: A Photographic Collage 

    E-Print Network [OSTI]

    Kannapurakkaran, Shyam

    2010-10-12

    The research involves the creation of an interactive installation showcasing the dynamic nature of human visual observation of a still photograph. Using an eye tracker as an input device, the data collected is used to create a photographic collage...

  8. North Shore Gas- Single Family Direct Install

    Broader source: Energy.gov [DOE]

    Owners of single-family homes, condos, townhomes and two-flats may be eligible for a free installation of new programmable thermostats, pipe insulation, showerheads, Compact Fluorescent Bulbs (CFLs...

  9. Chapter 21. Installation and Testing the Hardware

    E-Print Network [OSTI]

    Brookhaven National Laboratory - Experiment 821

    .10.1.1.4 Extract the energy with the quench protection circuit ­ 1 day G. Bunce 1.10.1.1.5 Analyse the coil Meas. G. Danby 1.10.2.5 Install & Test Yoke Tilt Sensors G. Danby 1.10.2.6 Yoke Corrections I. Polk 1 Z. Armoza 1.10.2.13 Install & Test Pole­face windings S. Dhawan 1.10.2.14 Pole­face Winding

  10. Volume XVIII, No. 5 A publication of the U.S. Army Installation Management Agency

    E-Print Network [OSTI]

    US Army Corps of Engineers

    20-21 Fort McCoy work force asked to reduce energy use, costs by Rob Schuette 22-23 Solar panels help by Don Juhasz 25-26 Central energy plant assessment strategy used at Redstone, Fort Jackson by William D/October 2006 U.S. Army Installation Management Agency In this issue: Energy Management and Conservation Special

  11. Hay Harvesting Costs $$$$$ in Texas. 

    E-Print Network [OSTI]

    Long, James T.; Taylor, Wayne D.

    1972-01-01

    would be approximately 34 cents. Labor cost was calculated at $1.50 per hour. Total operating cost, including labor and all equipmen! use, was 8.2 cents per bale and $5.73 per acre (a$ shown in Table 2). Assuming an average yieltl oi seventy 60.... averaged $5.73 per acre for each be 8.2 cents per bale. At a cost of 10 cents per baly cutting or $2.73 per ton. With an average of 70 for custom hauling, direct, out-of-pocket costs will be 18.2 cents per bale. I Table 3. Estimated Cost Per Ton and Per...

  12. Allocating Costs in Ninth Circuit Predatory Pricing Cases: Marsann Co. v. Brammall, Inc. and its Problematic Progeny, Inglis v. Continental Baking and Thales v. Matsushita

    E-Print Network [OSTI]

    Frech, Ted E; Wazzan, C. Paul

    2008-01-01

    treatment of prices above average variable cost, but belowaverage total cost varies greatly. In the Sixth and Ninthto be below Average Total Cost, but above Average Variable

  13. Contracting with reading costs and renegotiation costs

    E-Print Network [OSTI]

    Brennan, James R.

    2007-01-01

    Reading Costs, Competition, and ContractReading Costs . . . . . . . . . . . . . . . . C. EquilibriumUnconscionability A?ect Reading Costs . . . . . . . . . .

  14. The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies

    E-Print Network [OSTI]

    Mills, Andrew D.

    2009-01-01

    Annual Report on U.S. Wind Power Installation, Cost, andcost of transmission implied by this study is $207/kW-wind (U.S.lead us to overstate the unit cost of transmission for wind.

  15. On-Site Diesel Generation- How You Can Reduce Your Energy Costs 

    E-Print Network [OSTI]

    Charles, D.

    1996-01-01

    Interruptible power rates, Utility special rate negotiations, and the emergence of a spot electrical power market all can lead to lower industrial energy costs. The installation of low cost on-site diesel powered generation, or the proposed...

  16. Energy Information: The Key to Cost-Effective Conservation 

    E-Print Network [OSTI]

    McBride, J. R.; Flanagan, D. E.

    1998-01-01

    This paper analyzes the cost-effectiveness- simple payback, Net Present Value (NPV) and Return on Investment (ROI) -of permanently installed energy consumption monitoring equipment used as the basis for applying value-added engineering services...

  17. WREF 2012: THE PAST AND FUTURE COST OF WIND ENERGY

    E-Print Network [OSTI]

    Wiser, Ryan

    2013-01-01

    E. (2011). Development in LCOE for Wind Turbines in Denmark.to drive a historically low LCOE for current installations.the levelized cost of energy (LCOE) for onshore wind energy

  18. Installing and Maintaining a Small Wind Electric System | Department...

    Energy Savers [EERE]

    Installing and Maintaining a Small Wind Electric System Installing and Maintaining a Small Wind Electric System July 2, 2012 - 8:22pm Addthis Installing and Maintaining a Small...

  19. Performance Testing of Window Installation and Flashing Details 

    E-Print Network [OSTI]

    Weston, T. A.; Herrin, J.

    2002-01-01

    to determine water resistance, air leakage resistance and durability of several installation methods with different flashing materials. Windows were installed in test wall sections using several methods. The installations were monitored and evaluated for ease...

  20. U.S. CHP Installations Incorporating Thermal Energy Storage ...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    CHP Installations Incorporating Thermal Energy Storage (TES) andor Turbine Inlet Cooling (TIC), September 2003 U.S. CHP Installations Incorporating Thermal Energy Storage (TES)...

  1. Database (Report) of U.S. CHP Installations Incorporating Thermal...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    (Report) of U.S. CHP Installations Incorporating Thermal Energy Storage (TES) andor Turbine Inlet Cooling (TIC), 2004 Database (Report) of U.S. CHP Installations Incorporating...

  2. Floodplain Assessment for Installation of a Renewable Energy...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    for Installation of a Renewable Energy Anaerobic Digester Facility Floodplain Assessment for Installation of a Renewable Energy Anaerobic Digester Facility Floodplain Assessment...

  3. Secretary Chu Announces Two Million Smart Grid Meters Installed...

    Energy Savers [EERE]

    Secretary Chu Announces Two Million Smart Grid Meters Installed Nationwide Secretary Chu Announces Two Million Smart Grid Meters Installed Nationwide August 31, 2010 - 12:00am...

  4. Choosing and Installing Geothermal Heat Pumps | Department of...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    most economical) are typically used for newly constructed buildings with sufficient land. Vertical installations or more compact horizontal "Slinky(tm)" installations are often...

  5. Solar Photovoltaic Installation Market Trends | OpenEI Community

    Open Energy Info (EERE)

    Solar Photovoltaic Installation Market Trends Home John55364's picture Submitted by John55364(95) Contributor 14 May, 2015 - 02:24 Global Solar Photovoltaic (PV) Installation...

  6. Energy Department Completes Cool Roof Installation on DC Headquarters...

    Energy Savers [EERE]

    Energy Department Completes Cool Roof Installation on DC Headquarters Building to Save Money by Saving Energy Energy Department Completes Cool Roof Installation on DC Headquarters...

  7. Obama Administration Announces Plans to Install New Solar Panels...

    Energy Savers [EERE]

    Plans to Install New Solar Panels on the White House Residence Obama Administration Announces Plans to Install New Solar Panels on the White House Residence October 5, 2010 -...

  8. Purchase and Installation of a Geothermal Power Plant to Generate...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Purchase and Installation of a Geothermal Power Plant to Generate Electricity Using Geothermal Water Resources Purchase and Installation of a Geothermal Power Plant to Generate...

  9. U.S. Installation, Operation, and Performance Standards for Microturbi...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Installation, Operation, and Performance Standards for Microturbine Generator Sets, August 2000 U.S. Installation, Operation, and Performance Standards for Microturbine Generator...

  10. Tracking the Sun VIII: The Installed Price of Residential and...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Tracking the Sun VIII: The Installed Price of Residential and Non-Residential Photovoltaic Systems in the United States Tracking the Sun VIII: The Installed Price of Residential...

  11. ,"Total Natural Gas Consumption

    U.S. Energy Information Administration (EIA) Indexed Site

    Gas Consumption (billion cubic feet)",,,,,"Natural Gas Energy Intensity (cubic feetsquare foot)" ,"Total ","Space Heating","Water Heating","Cook- ing","Other","Total ","Space...

  12. Forecasting technology costs via the Learning Curve - Myth or Magic?

    E-Print Network [OSTI]

    Alberth, Stephan

    Gas Turbine (CCGT) where data provided by Colpier was already converted from ‘costs per installed capacity’ to ‘costs per electricity produced’ (2002). The focus has been on technologies that remained in their growth stages in order to avoid... Electricity Usc(90)/kWh - TWh 1981 1997 15 3.6 Cleason Colpier 2002 Nuclear Instalation US$(90)/W - GW 1975 1993 19 2.0 Kouvaritakis et al. (2000) in M&S 2001 SCGT Instalation US$(90)/W - GW 1956 1981 14 8.9 IIASA-WEC (1998), p.50 Solar Production $/Wp - MWp...

  13. Cost of Adding E85 Fueling Capability to Existing Gasoline Stations: NREL Survey and Literature Search (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2008-03-01

    Fact sheet provides framework for gas station owners to access what a reasonable cost would be to install E85 infrastructure.

  14. GENERAL PURPOSE CLASSROOMS (GPC) * not installed but available for checkout TOTAL GPC 343

    E-Print Network [OSTI]

    Yorke, James

    . 142 ANS 0402 20 GPC 1 ANS 0408 88 TECH 1 1 1 1 1 1 1 1 1 1 1 ANS 0412 45 GPC 1 Architecture Bldg. 145 ARC 0204 300 TECH 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 portable equip available ARC 1101 54 TECH 1 1 1 1 1 1 1 1 1 1 1 for checkout ARC 1103 54 TECH 1 1 1 1 1 1 1 1 to ARC faculty ARC 1105 54 TECH 1 1 1 1 1

  15. Page 1 of 8 Installation Name ____________________________________________________________

    E-Print Network [OSTI]

    US Army Corps of Engineers

    to aid in evaluating the overall performance of ground water extraction systems designed and installed of the subsurface performance of a ground water extraction system and the identification of the need for system of alternatives) 2) Typical Treatment Objectives There are two typical objectives for ground water extraction

  16. Page 1 of 6 Installation Name ____________________________________________________________

    E-Print Network [OSTI]

    US Army Corps of Engineers

    information Coordinate this checklist with the Ground Water Extraction System Subsurface Performance Well Design, Installation, and Documentation at HTRW Sites ETL 1110-1-201: Ground Water Extraction ASTM to aid in evaluating the performance and maintenance of extraction, injection, and monitoring wells

  17. flash informatique888 Automatiser votre installation

    E-Print Network [OSTI]

    Floreano, Dario

    ) Domaine Installation de systèmes d'exploitation Linux Licence GPLv2 langue anglais version Fedora Kickstartestuneméthoded'installationautomatiséepourlesdistri- butions GNU/Linux RedHat1 , et dérivées (Fedora, Cent-clés, ou options, est fournie de la part de RedHat5 et de Fedora3 . Cette section requiert des mots

  18. Transforming PV Installations Toward Dispatchable, Schedulable...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    B C N A B C N A B C N A B C N Ai n Bi n Ci n Aout Bout Cout A B C N A B C N Transforming PV insTallaTions Toward disPaTchable, schedulable energy soluTions MIChAEl MIllS-PrICE,...

  19. Installing Small Wind Turbines Seminar and Workshop

    E-Print Network [OSTI]

    Seminar and Workshop Installing Small Wind Turbines Seminar and Workshop Location: Murdoch January 2011 Details for Registration and Payment: Mr Daniel Jones, National Small Wind Turbine Test: The National Small Wind Turbine Centre at Murdoch University is holding a Small Wind Turbine short training

  20. Extending Quality Management to Utility Costs 

    E-Print Network [OSTI]

    Holmes, W. A.

    1994-01-01

    By installing permanent instrumentation and linking it to the appropriate software, a Utility Cost Management Information System, can be created which will identify where, when and how energy is used in a facility on a dynamic and real-time basis...

  1. PV Fact Sheets Argument B1Some people state that "The external costs of PV electricity

    E-Print Network [OSTI]

    PV Fact Sheets Argument B1Some people state that "The external costs of PV electricity is much shows the external costs for current PV systems at Southern and Central European locations in addition to other costs". For current PV installations in South-Europe the external costs are about 0.15 per k

  2. Implementation of Army privatization directives at Forscom installations

    SciTech Connect (OSTI)

    Armstrong, R.C.; Patwardhan, S.

    1997-06-01

    {open_quotes}Privatization{close_quotes} has become the buzzword of the 1990s not only here in the United States but throughout the world. Privatization has been traditionally defined as the sale/transfer of state-owned (i.e. federal, state, county, city or public) assets to the private sector. Although there are numerous reasons for the privatization of state-owned assets, the primary reasons include the generation of a significant amount of cash to the state (Great Britain`s sale of electric power industry); capitalization of the formerly state-owned utility (sale of the utilities within many countries of the former Soviet Union); and state policy goals of eliminating monopolies, encouraging competition, and restructuring (Chile). Several year ago, the Department of Defense (DoD) and specifically the Department of Army (DoA) initiated its own `Privatization Process`. Coupled with shrinking budgets, workforce and funding resources from the Government, the Army was faced with antiquated utility infrastructure in need of significant upgrades and in some cases total replacements. Recognizing that the provision of utility services was not a core mission of the Army, DoA has encouraged its Installations throughout the country to consider the privatization of the Government-owned utility systems. In compliance with DoA policy, Forces Command (FORSCOM) has been at the forefront of the privatization process. To date, FORSCOM has initiated the process of analyzing the potential privatization of over 30 utility systems at 12 FORSCOM Installations located throughout the country. The FORSCOM Installations include Fort Irwin, CA; Fort Campbell, KY; Fort Bragg, NC; Fort McPherson, GA; Fort Hood, TX; Fort Polk, LA; Fort Lewis, WA; Fort Riley, KS; Fort Stewart, GA; Hunter Army Airfield, GA; Fort Carson, CO; Fort Devens, MA; Fort Dix, NJ; and Fort Gillem, GA.

  3. Memorial University of Newfoundland Indirect Costs Report

    E-Print Network [OSTI]

    deYoung, Brad

    Memorial University of Newfoundland Indirect Costs Report 2012-13 The grant provided through the Government of Canada Indirect Costs Program (ICP) is essential to Memorial's research success. Funding and impact can be found in the following section. Total 2013 Indirect Costs Grant: $4,318,814 Management

  4. 2014-2015 Projected Aviation Program Costs

    E-Print Network [OSTI]

    Delene, David J.

    2014-2015 Projected Aviation Program Costs UND Aerospace offers two aviation degree programs with a total of seven academic majors. Each has its own flight course requirements, which affect the cost of a degree program. BACHELOR of BUSINESS ADMINISTRATION ** Flight Costs Airport Management Survey of Flight

  5. TRANSACTION COSTS AND NONMARKOVIAN DELTA HEDGING

    E-Print Network [OSTI]

    TRANSACTION COSTS AND NON­MARKOVIAN DELTA HEDGING Claudio Albanese and Stathis Tompaidis. The underlying security is a stock whose trading involves a small relative transaction cost k . If k = 0 find an optimal trading strategy that minimizes total transaction costs for a given degree of risk

  6. Total Estimated Contract Cost: Contract Option Period: Maximum...

    Office of Environmental Management (EM)

    Fee March 2015 Site: Portsmouth Paducah Project Office Contract Name: Operation of DUF6 Contractor: Babcock & Wilcox Conversion Services, LLC Contract Number:...

  7. Total Estimated Contract Cost: Contract Option Period: Performance

    Office of Environmental Management (EM)

    Performance Period Fee Earned FY2000 thru 2008 102,622,325 FY2009 12,259,719 FY2010 35,789,418 FY2011 24,126,240 FY2012 24,995,209 FY2013 6,340,762 FY2014 16,285,867 FY2015...

  8. Property:Geothermal/TotalProjectCost | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QAsource History ViewMayo,AltFuelVehicle2 Jump to: navigation, search This is

  9. U.S. Total Refiner Acquisition Cost of Crude Oil

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet)Decade Year-0Proved ReservesData20092009 2010 2011 20126 Table 1Feet)2009

  10. Measuring the Costs & Benefits of Nationwide Geothermal Heat

    E-Print Network [OSTI]

    Measuring the Costs & Benefits of Nationwide Geothermal Heat Pump (GHP) Deployment ­ A Progress to measure the costs and benefits of nationwide geothermal heat pump (GHP) deployment. · First market study to quantify the entire GHP chain ­ Manufacturing ­ Design ­ Installation · GHPsRUS is short for "geothermal

  11. Planning a Commercial Fuel Cell Installation 

    E-Print Network [OSTI]

    Bowden, J. R.; May, G. W.

    1986-01-01

    COMMERCIAL FUEL CELL INSTALLATION J. R.Bowden & G. W. May Bechtel National, Inc. San Francisco, California Fuel cell power plants represent a unique opportunity for industrial users to combine on-site electricity generation and heat recovery... with high efficiencies and no significant environmental releases. Thus in some circumstances, the fuel cell may be the best option for industrial cogeneration in locations with environmental restrictions. Because of the modular nature of fuel cell...

  12. Installation and Performance | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankADVANCED MANUFACTURING OFFICE INDUSTRIAL TECHNICAL8-02 Inspection Report:Department ofInstall

  13. Developing Information on Energy Savings and Associated Costs and Benefits of Energy Efficient Emerging Technologies Applicable in California

    E-Print Network [OSTI]

    Xu, Tengfang

    2011-01-01

    costs and energy savings potential of emerging technologies applicable to Californiacosts and energy savings potential of emerging technologies applicable to Californiaof cost- and energy-efficient installations. California has

  14. Shifting the cost curve for subsea developments

    SciTech Connect (OSTI)

    Solheim, B.J.; Hestad, E.

    1995-12-31

    A steadily increasing challenge in offshore oil and gas field developments in the Norwegian part of the North Sea is to design, construct, and install offshore installations that give an acceptable return of investment Deeper water, limited reservoirs and a low, fluctuating oil price make the task even more demanding. Saga Petroleum has recently faced this challenge with its last field development project. Attention in this paper is focused on the Vigdis subsea production system. However, the considerations and cost reduction elements are valid for offshore field developments in general. The main cost reductions are obtained by: Maximum use of industry capability; Application of new organization principles; Focus on functional requirements; Shortened project execution time; Technological development. In addition this paper presents thoughts on further cost reduction possibilities for future subsea field developments.

  15. Subsea pipeline isolation systems: Reliability and costs

    SciTech Connect (OSTI)

    Masheder, R.R.

    1996-08-01

    Since the Piper Alpha disaster, more than 80 subsea isolation systems (SSIS) have been installed in subsea gas and oil pipelines in the U.K. continental shelf at an estimated cost in the region of {Brit_pounds}500 million. The reliability and costs of these installations have now been assessed between Dec. 1992 and Oct. 1993. This assessment was based upon comprehensive reliability and cost databases which were established so that the studies could be based upon factual information in order to obtain a current status as required by the sponsoring group. The study consultants report findings have now been consolidated into a report by the UKOOA Pipeline Valve Work Group. Probabilities of failure for different types of valves and systems have been assessed and expenditures broken down and compared. The results of the studies and the conclusions drawn by UKOOA Pipeline Valve Group and the HSE Offshore Safety Division are presented in this paper.

  16. Minimization of Life Cycle Costs Through Optimization of the Validation Program A Test Sample Size and Warranty Cost

    E-Print Network [OSTI]

    Sandborn, Peter

    unit cost to the customer (customer's price) d = design cost of the total program pv = cost of productMinimization of Life Cycle Costs Through Optimization of the Validation Program ­ A Test Sample Size and Warranty Cost Approach Andre Kleyner, Delphi Delco Electronics, Kokomo Peter Sandborn, Ph

  17. Solar Schools Assessment and Implementation Project: Financing Options for Solar Installations on K-12 Schools

    SciTech Connect (OSTI)

    Coughlin, J.; Kandt, A.

    2011-10-01

    This report focuses on financial options developed specifically for renewable energy and energy efficiency projects in three California public school districts. Solar energy systems installed on public schools have a number of benefits that include utility bill savings, reductions in greenhouse gas emissions (GHGs) and other toxic air contaminants, job creation, demonstrating environmental leadership, and creating learning opportunities for students. In the 2011 economic environment, the ability to generate general-fund savings as a result of reducing utility bills has become a primary motivator for school districts trying to cut costs. To achieve meaningful savings, the size of the photovoltaic (PV) systems installed (both individually on any one school and collectively across a district) becomes much more important; larger systems are required to have a material impact on savings. Larger PV systems require a significant financial commitment and financing therefore becomes a critical element in the transaction. In simple terms, school districts can use two primary types of ownership models to obtain solar installations and cost savings across a school district. The PV installations can be financed and owned directly by the districts themselves. Alternatively, there are financing structures whereby another entity, such as a solar developer or its investors, actually own and operate the PV systems on behalf of the school district. This is commonly referred to as the 'third-party ownership model.' Both methods have advantages and disadvantages that should be weighed carefully.

  18. WREF 2012: THE PAST AND FUTURE COST OF WIND ENERGY

    SciTech Connect (OSTI)

    NREL,; Wiser, Ryan; Lantz, Eric; Hand, Maureen

    2012-03-26

    The future of wind power will depend on the ability of the industry to continue to achieve cost reductions. To better understand the potential for cost reductions, this report provides a review of historical costs, evaluates near-term market trends, and summarizes the range of projected costs. It also notes potential sources of future cost reductions. Our findings indicate that steady cost reductions were interrupted between 2004 and 2010, but falling turbine prices and improved turbine performance are expected to drive a historically low LCOE for current installations. In addition, the majority of studies indicate continued cost reductions on the order of 20%-30% through 2030. Moreover, useful cost projections are likely to benefit from stronger consideration of the interactions between capital cost and performance as well as trends in the quality of the wind resource where projects are located, transmission, grid integration, and other cost variables.

  19. A study of the coherent structures and installation effects in an orifice flow meter 

    E-Print Network [OSTI]

    Pattabhi, Srikanth

    1993-01-01

    of MASTER OF SCIENCE August 1993 Major Subject: Mechanical Engineering A STUDY OF THE COHERENT STRUCTURES AND INSTALLATION EFFECTS IN AN ORIFICE FLOW METER A Thesis by SRIKANTH PATTABHI Approved as to style and content by: G. L. Morris (Chair...) Srikanth Pattabhi, B, E, University of Mysore, India Chair of Advisory Committee: Dr. G. L. Morrison Orifice meters are used extensively in the natural gas industry for custody transfer, an application where inaccuracies in measurement can be costly...

  20. Cooling energy performance and installation of a retrofitted exterior insulation and finish system on masonry residences in the southwestern United States

    SciTech Connect (OSTI)

    Ternes, M.P.; Wilkes, K.E.; McLain, H.A.

    1992-12-31

    A field test involving eight single-family houses was performed during the summer of 1991 in Scottsdale, Arizona to evaluate the potential of reducing air-conditioning electricity consumption and demand by insulating their exterior masonry walls using a site-fabricated (non-commercially available) insulation and finish system. The exterior insulation system developed for the field test was easily performed and should result in a durable installation. Total per house costs to perform the installations ranged from $3610 to $4550. The average annual savings was estimated to be 491 kWh, or 9% of pre-retrofit consumption. Peak demands without and with insulation on the hottest day of an average weather year for Phoenix were estimated to be 4.26 and 3.61 kill, for a demand reduction of 0.65 kill (15%). We conclude that exterior masonry wall insulation offers the greatest potential for air-conditioning electricity savings and peak demand reductions in hot, dry climates similar to that of Phoenix. Retrofit economics need to be thoroughly examined from societal, utility, and consumer perspectives and must consider other benefits such as space-heating energy savings and improved house value.

  1. Estimating Specialty Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Specialty costs are those nonstandard, unusual costs that are not typically estimated. Costs for research and development (R&D) projects involving new technologies, costs associated with future regulations, and specialty equipment costs are examples of specialty costs. This chapter discusses those factors that are significant contributors to project specialty costs and methods of estimating costs for specialty projects.

  2. Optimizing Installation, Operation, and Maintenance at Offshore...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    The report also discusses the cost implications for the onerous wave climate in the Pacific Ocean, the impact of sea ice on projects in the Great Lakes, and the limitations...

  3. Installing and Operating an Efficient Swimming Pool Pump | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Installing and Operating an Efficient Swimming Pool Pump Installing and Operating an Efficient Swimming Pool Pump May 29, 2012 - 7:54pm Addthis Photo courtesy iStockphoto.com Photo...

  4. Reviewing Post-Installation and Annual Reports for Federal ESPC...

    Office of Environmental Management (EM)

    Reviewing Post-Installation and Annual Reports for Federal ESPC Projects Reviewing Post-Installation and Annual Reports for Federal ESPC Projects The purpose of this document is to...

  5. PNNL Reports Distributed Wind Installations Down, Exports Up...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    PNNL Reports Distributed Wind Installations Down, Exports Up in 2013 PNNL Reports Distributed Wind Installations Down, Exports Up in 2013 March 31, 2014 - 11:14am Addthis According...

  6. Energy Saving "Cool Roofs" Installed at Y-12 | National Nuclear...

    National Nuclear Security Administration (NNSA)

    Home Field Offices Welcome to the NNSA Production Office NPO News Releases Energy Saving "Cool Roofs" Installed at Y-12 Energy Saving "Cool Roofs" Installed at Y-12 The...

  7. Energy Department Launches SunShot Prize Competition to Install...

    Office of Environmental Management (EM)

    SunShot Prize Competition to Install Solar Energy Systems at a Fraction of Today's Price Energy Department Launches SunShot Prize Competition to Install Solar Energy Systems at a...

  8. Total Space Heat-

    Gasoline and Diesel Fuel Update (EIA)

    Revised: December, 2008 Total Space Heat- ing Cool- ing Venti- lation Water Heat- ing Light- ing Cook- ing Refrig- eration Office Equip- ment Com- puters Other All Buildings...

  9. Total Space Heat-

    Gasoline and Diesel Fuel Update (EIA)

    Released: September, 2008 Total Space Heat- ing Cool- ing Venti- lation Water Heat- ing Light- ing Cook- ing Refrig- eration Office Equip- ment Com- puters Other All Buildings*...

  10. ,"Total Fuel Oil Expenditures

    U.S. Energy Information Administration (EIA) Indexed Site

    . Fuel Oil Expenditures by Census Region for Non-Mall Buildings, 2003" ,"Total Fuel Oil Expenditures (million dollars)",,,,"Fuel Oil Expenditures (dollars)" ,,,,,"per...

  11. ,"Total Fuel Oil Consumption

    U.S. Energy Information Administration (EIA) Indexed Site

    0. Fuel Oil Consumption (gallons) and Energy Intensities by End Use for Non-Mall Buildings, 2003" ,"Total Fuel Oil Consumption (million gallons)",,,,,"Fuel Oil Energy Intensity...

  12. ,"Total Fuel Oil Expenditures

    U.S. Energy Information Administration (EIA) Indexed Site

    4. Fuel Oil Expenditures by Census Region, 1999" ,"Total Fuel Oil Expenditures (million dollars)",,,,"Fuel Oil Expenditures (dollars)" ,,,,,"per Gallon",,,,"per Square Foot"...

  13. ,"Total Fuel Oil Expenditures

    U.S. Energy Information Administration (EIA) Indexed Site

    A. Fuel Oil Expenditures by Census Region for All Buildings, 2003" ,"Total Fuel Oil Expenditures (million dollars)",,,,"Fuel Oil Expenditures (dollars)" ,,,,,"per Gallon",,,,"per...

  14. ,"Total Fuel Oil Consumption

    U.S. Energy Information Administration (EIA) Indexed Site

    A. Fuel Oil Consumption (gallons) and Energy Intensities by End Use for All Buildings, 2003" ,"Total Fuel Oil Consumption (million gallons)",,,,,"Fuel Oil Energy Intensity...

  15. Installed Geothermal Capacity | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QA J-E-1 SECTION J APPENDIXsource History View NewGuam:on Openei |sourceAndInformationInstalled Geothermal

  16. NREL Job Task Analysis: Retrofit Installer Technician (Revised)

    SciTech Connect (OSTI)

    Kurnik, C.; Woodley, C.

    2012-04-01

    A summary of job task analyses for the position of retrofit installer technician when conducting weatherization work on a residence.

  17. A Near-Term Economic Analysis of Hydrogen Fueling Stations

    E-Print Network [OSTI]

    Weinert, Jonathan X.

    2005-01-01

    Photovoltaic System Additional Equipment $/yr Installation Costs Contingency Electricity Fixed Operating Costs Total Annual Cost ($/yr) Hydrogen Price (

  18. A Near-term Economic Analysis of Hydrogen Fueling Stations

    E-Print Network [OSTI]

    Weinert, Jonathan X.

    2005-01-01

    Photovoltaic System Additional Equipment $/yr Installation Costs Contingency Electricity Fixed Operating Costs Total Annual Cost ($/yr) Hydrogen Price (

  19. A GUIDE TO PHOTOVOLTAIC (PV) SYSTEM DESIGN AND INSTALLATION

    E-Print Network [OSTI]

    CALIFORNIA ENERGY COMMISSION A GUIDE TO PHOTOVOLTAIC (PV) SYSTEM DESIGN AND INSTALLATION JUNE 2001 500-01-020 CONSULTANTREPORT Gray Davis, Governor #12;PV Installation Guide June 2001 Page 1 A GUIDE TO PHOTOVOLTAIC (PV) SYSTEM DESIGN AND INSTALLATION Prepared for: California Energy Commission Energy Technology

  20. Cost Sharing What is Cost Sharing?

    E-Print Network [OSTI]

    California at San Diego, University of

    into COEUS x OPAFS establishes project related IFIS fund and index numbers x Department tracks cost sharing sharing using various data fields (bin, fund, PI, index, etc.) x Create a Bin Generate a bin where cost1 Cost Sharing What is Cost Sharing? x Cost sharing is a commitment to use university resources

  1. Alstom 3-MW Wind Turbine Installed at NWTC (Fact Sheet)

    SciTech Connect (OSTI)

    Not Available

    2011-09-01

    The 3-MW Alstom wind turbine was installed at NREL's NWTC in October 2010. Test data will be used to validate advanced turbine design and analysis tools. NREL signed a Cooperative Research and Development Agreement with Alstom in 2010 to conduct certification testing on the company's 3-MW ECO 100 wind turbine and to validate models of Alstom's unique drivetrain concept. The turbine was installed at NREL's National Wind Technology Center (NWTC) in October 2010 and engineers began certification testing in 2011. Tests to be conducted by NREL include a power quality test to finalize the International Electrotechnical Commission (IEC) requirements for type certification of the 60-Hz unit. The successful outcome of this test will enable Alstom to begin commercial production of ECO 100 in the United States. NREL also will obtain additional measurements of power performance, acoustic noise, and system frequency to complement the 50 Hz results previously completed in Europe. After NREL completes the certification testing on the ECO 100, it will conduct long-term testing to validate gearbox performance to gain a better understanding of the machine's unique ALSTOM PURE TORQUE{trademark} drivetrain concept. In conventional wind turbines, the rotor is supported by the shaft-bearing gearbox assembly. Rotor loads are partially transmitted to the gearbox and may reduce gearbox reliability. In the ALSTOM PURE TORQUE concept, the rotor is supported by a cast frame running through the hub, which transfers bending loads directly to the tower. Torque is transmitted to the shaft through an elastic coupling at the front of the hub. According to Alstom, this system will increase wind turbine reliability and reduce operation and maintenance costs by isolating the gearbox from rotor loads. Gearbox reliability has challenged the wind energy industry for more than two decades. Gearbox failures require expensive and time-consuming replacement, significantly increasing the cost of wind plant operation while reducing the plant's power output and revenue. To solve gearbox reliability issues, NREL launched a Gearbox Reliability Collaborative (GRC) in 2006 and brought together the world's leading turbine manufacturers, consultants, and experts from more than 30 companies and organizations. GRC's goal was to validate the typical design process-from wind turbine system loads to bearing ratings-through a comprehensive dynamometer and field-test program. Design analyses will form a basis for improving reliability of future designs and retrofit packages. Through its study of Alstom's Eco 100 gearbox, NREL can compare its GRC model gearbox with Alstom's and add the results to the GRC database, which is helping to advance more reliable wind turbine technology.

  2. Drum ring removal/installation tool

    DOE Patents [OSTI]

    Andrade, William Andrew (Livermore, CA)

    2006-11-14

    A handheld tool, or a pair of such tools, such as for use in removing/installing a bolt-type clamping ring on a container barrel/drum, where the clamping ring has a pair of clamping ends each with a throughbore. Each tool has an elongated handle and an elongated lever arm transversely connected to one end of the handle. The lever arm is capable of being inserted into the throughbore of a selected clamping end and leveraged with the handle to exert a first moment on the selected clamping end. Each tool also has a second lever arm, such as a socket with an open-ended slot, which is suspended alongside the first lever arm. The second lever arm is capable of engaging the selected clamping end and being leveraged with the handle to exert a second moment which is orthogonal to the first moment. In this manner, the first and second moments operate to hold the selected clamping end fixed relative to the tool so that the selected clamping end may be controlled with the handle. The pair of clamping ends may also be simultaneously and independently controlled with the use of two handles/tools so as to contort the geometry of the drum clamping ring and enable its removal/installation.

  3. Assembling and Installing LRUs for NIF

    SciTech Connect (OSTI)

    Bonanno, R E

    2003-12-31

    Within the 192 National Ignition Facility (NIF) beamlines, there are over 7000 large (40 x 40 cm) optical components, including laser glass, mirrors, lenses, and polarizers. These optics are held in large opto-mechanical assemblies called line-replaceable units (LRUs). Each LRU has strict specifications with respect to cleanliness, alignment, and wavefront so that once activated, each NIF beamline will meet its performance requirements. NIF LRUs are assembled, tested, and refurbished in on-site cleanroom facilities. The assembled LRUs weigh up to 1800 kilograms, and are about the size of a phone booth. They are transported in portable clean canisters and inserted into the NIF beampath using robotic transporters. This plug and play design allows LRUs to be easily removed from the beampath for maintenance or upgrades. Commissioning of the first NIF quad, an activity known as NIF Early Light (NEL), has validated LRU designs and architecture, as well as demonstrated that LRUs can be assembled and installed as designed. Furthermore, it has served to develop key processes and tools forming the foundation for NIF s long-term LRU production and maintenance strategy. As we look forward to building out the rest of NIF, the challenge lies in scaling up the production rate while maintaining quality, implementing process improvements, and fully leveraging the learning and experience gained from NEL. This paper provides an overview of the facilities, equipment and processes used to assemble and install LRUs in NIF.

  4. Installation of an innovative remedial technology

    SciTech Connect (OSTI)

    Hines, B. [CDM Federal Programs Corp., Kevil, KY (United States)

    1995-12-31

    The major goal of the Lasagna{trademark} project was to design, construct, install, and operate an in situ remediation system in low-permeability soil. A new technology--the Lasagna process--uses electro-osmosis to move contaminated groundwater through treatment zones. The treatment zones are installed in contaminated soils, thereby forming an integrated in situ remedial process. Electro-osmosis, well known for its effectiveness and extremely low power consumption, uses a direct current to cause Groundwater to travel through low-permeability soil. When a bench-scale version of the technology was 98 percent effective in removing contamination, an actual field test was the next step. The site chosen for this first field effort was the DOE-owned Paducah Gaseous Diffusion Plant located in Paducah, Kentucky. The target contaminant for this project was trichloroethylene (TCE) because it is found at many sites across the country and is present at approximately 60 percent of DOE`s sites.

  5. Energy Use and Costs in Texas Schools and Hospitals 

    E-Print Network [OSTI]

    Dunn, J. R.

    1998-01-01

    demand charges, monthly natural gas consumed, monthly total natural gas costs, and total facility conditioned area. From this data, the monthly and annual energy use and cost performance of the facility is presented with the calculation of 10 use and cost...

  6. Cost Sharing Basics Definitions

    E-Print Network [OSTI]

    Finley Jr., Russell L.

    Cost Sharing Basics Definitions Some funding agencies require the grantee institution the project costs. Cost sharing is defined as project costs not borne by the sponsor. Cost sharing funds may resources or facilities. If the award is federal, only acceptable non-federal costs qualify as cost sharing

  7. Avoiding Distribution System Upgrade Costs Using Distributed Generation

    SciTech Connect (OSTI)

    Schienbein, Lawrence A.; Balducci, Patrick J.; Nguyen, Tony B.; Brown, Daryl R.; DeSteese, John G.; Speer, Gregory A.

    2004-01-20

    PNNL, in cooperation with three utilities, developed a database and methodology to analyze and characterize the avoided costs of Distributed Generation (DG) deployment as an alternative to traditional distribution system investment. After applying a number of screening criteria to the initial set of 307 cases, eighteen were selected for detailed analysis. Alternative DG investment scenarios were developed for these cases to permit capital, operation, maintenance, and fuel costs to be identified and incorporated into the analysis. The “customer-owned” backup power generator option was also investigated. The results of the analysis of the 18 cases show that none yielded cost savings under the alternative DG scenarios. However, the DG alternative systems were configured using very restrictive assumptions concerning reliability, peak rating, engine types and acceptable fuel. In particular it was assumed that the DG alternative in each case must meet the reliability required of conventional distribution systems (99.91% reliability). The analysis was further constrained by a requirement that each substation meet the demands placed upon it by a one in three weather occurrence. To determine if, by relaxing these requirements, the DG alternative might be more viable, one project was re-examined. The 99.91% reliability factor was still assumed for normal operating conditions but redundancy required to maintain reliability was relaxed for the relatively few hours every three years where extreme weather caused load to exceed present substation capacity. This resulted in the deferment of capital investment until later years and reduced the number of engines required for the project. The cost of both the conventional and DG alternative also dropped because the centralized power generation, variable O&M, and DG fuels costs were calculated based on present load requirements in combination with long-term forecasts of load growth, as opposed to load requirements plus a buffer based on predictions of extraordinary weather conditions. Application of the relaxed set of assumptions reduced the total cost of the DG alternative by roughly 57 percent from $7.0 million to $3.0 million. The reduction, however, did not change the overall result of the analysis, as the cost of the conventional distribution system upgrade alternative remained lower at $1.7 million. This paper also explores the feasibility of using a system of backup generators to defer investment in distribution system infrastructure. Rather than expanding substation capacity at substations experiencing slow load growth rates, PNNL considered a scenario where diesel generators were installed on location at customers participating in a program designed to offer additional power security and reliability to the customer and connection to the grid. The backup generators, in turn, could be used to meet peak demand for a limited number of hours each year, thus deferring distribution system investment. Data from an existing program at one of the three participating utilities was used to quantify the costs associated with the backup generator scenario. The results of the “customer owned” backup power generator analysis showed that in all cases the nominal cost of the DG scenario is more than the nominal cost of the base-case conventional distribution system upgrade scenario. However, in two of the cases the total present value costs of the alternative backup generator scenarios were between 15 and 22% less than those for the conventional scenarios. Overall, the results of the study offer considerable encouragement that the use of DG systems can defer conventional distribution system upgrades under the right conditions and when the DG configurations are intelligently designed. Using existing customer-owned DG to defer distribution system upgrades appears to be an immediate commercially-viable opportunity.

  8. Utility-Scale Solar 2012: An Empirical Analysis of Project Cost, Performance, and Pricing Trends in the United States

    E-Print Network [OSTI]

    Bolinger, Mark

    2014-01-01

    installed since 2007 in both DC and AC terms. Because solar project capacityinstalled project costs or prices – i.e. , the traditional realm of solar economics analyses – but also operating costs, capacityinstalled project costs or prices – i.e. , the traditional realm of solar economics analyses – but also operating costs, capacity

  9. The Program Administrator Cost of Saved Energy for Utility Customer-Funded Energy Efficiency Programs

    E-Print Network [OSTI]

    Billingsley, Megan A.

    2014-01-01

    2013. State Energy Efficiency Resource Standards (EERS).The total resource costs of energy efficiency (includingtotal resource costs of energy efficiency for comparison

  10. Employee Replacement Costs

    E-Print Network [OSTI]

    Dube, Arindrajit; Freeman, Eric; Reich, Michael

    2010-01-01

    Samuel Schenker, “The Costs of Hir- u ing Skilled Workers”,Employee Replacement Costs Arindrajit Dube, Eric Freeman andof employee replacement costs, using a panel survey of

  11. Total Space Heat-

    Gasoline and Diesel Fuel Update (EIA)

    Survey: Energy End-Use Consumption Tables Total Space Heat- ing Cool- ing Venti- lation Water Heat- ing Light- ing Cook- ing Refrig- eration Office Equip- ment Com- puters Other...

  12. Total Synthesis of (?)-Himandrine

    E-Print Network [OSTI]

    Movassaghi, Mohammad

    We describe the first total synthesis of (?)-himandrine, a member of the class II galbulimima alkaloids. Noteworthy features of this chemistry include a diastereoselective Diels?Alder reaction in the rapid synthesis of the ...

  13. Resource Form Factor and Installation of GFA Controllers

    SciTech Connect (OSTI)

    DeSteese, John G.; Hammerstrom, Donald J.

    2009-11-15

    The focus of this task is to optimize the form and placement of a controller comprising the Grid Friendly™ appliance (GFA) controller, power supply and power relay (and/or a solid-state power electronic switch) that would command a domestic water heater to shed its load in response to stress on the electric power grid. The GFA controller would disconnect the water heater from its supply circuit whenever it senses a low voltage signal or other indicators of system stress communicated via the electric power distribution system. Power would be reconnected to the appliance when the GFA controller senses the absence of these signals. This project has also considered more frequent cycling of this controller’s relay switch to perform demand-side frequency regulation. The principal criteria considered in this optimization are reliability, cost and life expectancy of the GFA components. The alternative embodiments of the GFA equipment under consideration are: Option 1- installation inside the insulation space of the water heater between the tank and jacket Option 2 containment in a separate nearby electrical enclosure Option 3 - as a modification or adjunct to the distribution panel housing and/or the breaker that protects the water heater supply circuit.

  14. Costs and Consequences of Flooding Camilo Sarmiento, Ph.D.

    E-Print Network [OSTI]

    Costs and Consequences of Flooding Camilo Sarmiento, Ph.D. Senior Economist Fannie Mae #12 the impact that the NFIP has had on the flooding costs and the distribution of these costs among payers the NFIP loss database, the model examines losses in known flood events, infers total losses by cost

  15. AMVER-SEAS Installation Guide 7/12/2010 Page 2/59 This installation guide provides instructions on how to install, and configure AMVER-

    E-Print Network [OSTI]

    on how to install, and configure AMVER- SEAS on computer for cruise. Note that you can find it under-SEAS Installation Guide 7/12/2010 Page 3/59 Table of contents Computer Hardware and Operating System Requirements............................................................................................................................ 4 Step1: Removing anti virus software

  16. Incorporating uncertainty in the Life Cycle Cost Analysis of pavements

    E-Print Network [OSTI]

    Swei, Omar Abdullah

    2012-01-01

    Life Cycle Cost Analysis (LCCA) is an important tool to evaluate the economic performance of alternative investments for a given project. It considers the total cost to construct, maintain, and operate a pavement over its ...

  17. Cost of heliostats in low volume production

    SciTech Connect (OSTI)

    Drumheller, K.; Williams, T. A.; Dilbeck, R. A.; Allison, G. S.

    1980-01-01

    This study indicates that in small volumes, heliostats can be produced at an installed cost of approximately 200 $/M/sup 2/ for a 49.053 m/sup 2/ heliostat. Initial one-time costs of $10 to $15 million would be required, although part of the one-time costs are recoverable. This study provides estimated costs of heliostats that are produced in a plant operating on a continuous basis for a period of four years at a production rate of 2,500 heliostats per year. This scenario was selected somewhat arbitrarily as a scenario that could lead to heliostat market of 5,000 to 10,000 units per year.

  18. Tracking the Sun VII: An Historical Summary of the Installed Price of Photovoltaics in the United States from 1998-2013

    Broader source: Energy.gov [DOE]

    As the deployment of grid-connected solar photovoltaic (PV) systems has increased, so too has the desire to track the cost and price of these systems. This report helps fill this need by summarizing trends in the installed price of grid-connected PV systems in the United States from 1998 through 2013, with partial data for the first half of 2014. The analysis is based on project level data for more than 300,000 individual residential, commercial, and utility-scale PV systems installed across 33 states, representing 80% of all grid-connected PV capacity installed in the United States through 2013. Researchers found that installed prices continued declining in 2013, falling year-over-year by $0.7/W, or 12-15% depending on system size range, and data for the first six months of 2014 indicate that installed prices have continued to fall. This recorded decline since 2008 is largely attributable to module price reductions.

  19. Solar Projects to Reduce Non-Hardware Balance of System Costs

    Office of Energy Efficiency and Renewable Energy (EERE)

    Seven projects are focused on creating tools and developing methods to reduce the cost of non-hardware components for installed solar energy systems and reducing market barriers. These projects...

  20. Low cost monitoring system to diagnose problematic rail bed : case study of Mud Pumping Site

    E-Print Network [OSTI]

    Aw, Eng Sew, 1978-

    2007-01-01

    This thesis describes the development of low cost sensors and wireless sensor network (WSN) platform aimed at characterizing problematic rail beds (subgrade). The instrumentations are installed at a busy high-speed Northeast ...

  1. Installation of the first Distributed Energy Storage System (DESS) at American Electric Power (AEP).

    SciTech Connect (OSTI)

    Nourai, Ali (American Electric Power Company, Columbus, OH)

    2007-06-01

    AEP studied the direct and indirect benefits, strengths, and weaknesses of distributed energy storage systems (DESS) and chose to transform its entire utility grid into a system that achieves optimal integration of both central and distributed energy assets. To that end, AEP installed the first NAS battery-based, energy storage system in North America. After one year of operation and testing, AEP has concluded that, although the initial costs of DESS are greater than conventional power solutions, the net benefits justify the AEP decision to create a grid of DESS with intelligent monitoring, communications, and control, in order to enable the utility grid of the future. This report details the site selection, construction, benefits and lessons learned of the first installation, at Chemical Station in North Charleston, WV.

  2. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    sources and others, e.g. , Windpower Monthly and the Globalmanufacturer – Clipper Windpower – is in the process ofutilities commissions, Windpower Monthly magazine, AWEA’s

  3. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2007 (Revised)

    SciTech Connect (OSTI)

    Wiser, R.; Bolinger, M.

    2008-05-01

    This report focuses on key trends in the U.S. wind power market, with an emphasis on the latest year, and presents a wealth of data, some of which has not historically been mined by wind power analysts.

  4. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    of the U.S. DOE’s Wind & Hydropower Technologies Program. Weand Renewable Energy (Wind & Hydropower Technologies ProgramManager Office of Wind and Hydropower Technologies Energy

  5. Test plan : reducing soft costs of rooftop solar installations attributed to structural considerations.

    SciTech Connect (OSTI)

    Dwyer, Stephen F.

    2013-05-01

    This test plan is a document that provides a systematic approach to the planned testing of rooftop structures to determine their actual load carrying capacity. This document identifies typical tests to be performed, the responsible parties for testing, the general feature of the tests, the testing approach, test deliverables, testing schedule, monitoring requirements, and environmental and safety compliance.

  6. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    National Interest Electric Transmission Corridors, and thedraft National Interest Electric Transmission CorridorNational Interest Electric Transmission Corridors, one in

  7. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    likewise, FPL Energy and others may finance portions ofsheet finance (e.g. , that used by FPL Energy) and so-Energy Weekly, DOE/EPRI’s Turbine Verification Program, Project Finance

  8. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    all in-state wind is used in-state, New Mexico could meetWind Power Rankings: The Top 20 States Cumulative Capacity (end of 2006, MW) Texas California Iowa Minnesota Washington Oklahoma New Mexico

  9. Literature review : reducing soft costs of rooftop solar installations attributed to structural considerations.

    SciTech Connect (OSTI)

    Dwyer, Stephen F.

    2013-03-01

    Typical engineering methods utilized to calculate stresses on a roof structure involve simplifying assumptions that render a complex non-linear structure a simple and basic determinate beam. That is, instead of considering the composite action of the entire roof structure, the engineer evaluates only a single beam that is deemed conservatively to represent an affected rafter or top chord of a truss. This simplification based on assumptions of a complex problem is where significant conservatism can be introduced. Empirical data will be developed to evaluate this issue. Simple wood beams will be tested to failure. More complex and complete sections of roof structures that include composite action will also be tested to failure. The results can then be compared. An initial step in this process involves a literature review of any work that has been performed on roof structure composite action. The following section summarizes the literature review that was completed.

  10. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    RPS obliga- tions, and green power markets in which RECs arecustomer demand for “green” power, especially amongplanning require- ments, green power markets, and growing

  11. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    7, private independent power producers (IPPs) continued towind additions in 2006 Independent Power Producer (IPP) IPP:independent power Projects with no 2005/06 O&M data producers

  12. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    National Laboratories Wind Energy Technology Department P.O.Office of Wind and Hydropower Technologies Energy EfficiencyOF ENERGY WIND AND HYDROPOWER TECHNOLOGIES PROGRAM http://

  13. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    Lab), Kathy Belyeu (AWEA), Maureen Hand (NREL), DonnaHeimiller (NREL), DebraLew (NREL), Michael Milligan (NREL), Andrew Mills (Berkeley

  14. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    E-Print Network [OSTI]

    2008-01-01

    Western Wind, and Midwest Wind Energy. Table 4. Merger andHorizon) Noble Power CPV Wind Catamount Western Wind EnergyCoastal Wind Energy LLC Tierra Energy, LLC Renewable

  15. Annual Report on U.S. Wind Power Installation, Cost, and Performance Trends: 2006

    SciTech Connect (OSTI)

    Wiser, R.; Bolinger, M.

    2007-05-01

    This report--the first in what is envisioned to be an ongoing annual series--attempts to fill this need by providing a detailed overview of developments and trends in the U.S. wind power market, with a particular focus on 2006.

  16. Have a great idea about how to cut the cost of solar panel installation? |

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QAsource History View New PagesSustainableGlynnMassachusetts:Ohio: EnergyMinnesota: EnergyHauula, Hawaii:OpenEI

  17. Savannah River Site Liquid-Waste Contractor Installs New Cost-Saving Pump

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankADVANCED MANUFACTURINGEnergy BillsNo. 195 -RobSSL INDepartment of EnergyD-Area OilReview|

  18. TOTAL ANNUAL Rent / Mortgage $

    E-Print Network [OSTI]

    Snider, Barry B.

    etc.) $ Child Care Expenses $ Educational Loans taken out in parent's name $ Other (itemize below): $ $ RESOURCES TOTAL ANNUAL AMOUNT Parent 1 Wages $ Parent 2 Wages $ Interest and/or Dividend Income $ Net Income $ Contributions to tax deferred plans(401K) $ Non Educational Veterans' Benefits $ Unemployment Compensation

  19. Total Sustainability Humber College

    E-Print Network [OSTI]

    Thompson, Michael

    1 Total Sustainability Management Humber College November, 2012 SUSTAINABILITY SYMPOSIUM Green An Impending Global Disaster #12;3 Sustainability is NOT Climate Remediation #12;Our Premises "We cannot, you cannot improve it" (Lord Kelvin) "First rule of sustainability is to align with natural forces

  20. Gasket and snap ring installation tool

    DOE Patents [OSTI]

    Southerland, Jr., James M. (Aiken, SC); Barringer, Jr., Curtis N. (Orangeburg, SC)

    1994-01-01

    A tool for installing a gasket and a snap ring including a shaft, a first plate attached to the forward end of the shaft, a second plate slidably carried by the shaft, a spring disposed about the shaft between the first and second plates, and a sleeve that is free to slide over the shaft and engage the second plate. The first plate has a loading surface with a loading groove for receiving a snap ring and a shoulder for holding a gasket. A plurality of openings are formed through the first plate, communicating with the loading groove and approximately equally spaced about the groove. A plurality of rods are attached to the second plate, each rod slidable in one of the openings. In use, the loaded tool is inserted into a hollow pipe or pipe fitting having an internal flange and an internal seating groove, such that the gasket is positioned against the flange and the ring is in the approximate plane of the seating groove. The sleeve is pushed against the second plate, sliding the second plate towards the first plate, compressing the spring and sliding the rods forwards in the openings. The rods engage the snap ring and urge the ring from the loading groove into the seating groove.

  1. Microsoft Word - VitPlantCompletesMechanicalInstallation_20110818...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    August 18, 2011 Hanford Waste Treatment Plant completes important mechanical installation in Pretreatment Facility MEDIA CONTACTS: Suzanne Heaston, Bechtel National, Inc., (509)...

  2. Global Solar Photovoltaic (PV) Installation Market to be Propelled...

    Open Energy Info (EERE)

    Global Solar Photovoltaic (PV) Installation Market to be Propelled by Greater Concerns over Carbon Footprint Home > Groups > Renewable Energy RFPs John55364's picture Submitted by...

  3. Permit for Charging Equipment Installation: Electric Vehicle Supply Equipment (EVSE)

    Broader source: Energy.gov [DOE]

    Jurisdiction's can use this template to develop a standard permit for residential charging stations that allows for quick, safe installation of EVSE.

  4. DOE-DOD Emergency Backup Power Fuel Cell Installations

    Fuel Cell Technologies Publication and Product Library (EERE)

    Ths fact sheet describes a collaboration between the departments of Energy and Defense to install and operate 18 fuel cell backup power systems across the United States.

  5. Focus Series: Maine - Residential Direct Install Program | Department...

    Broader source: Energy.gov (indexed) [DOE]

    Better Buildings Neighborhood Program Focus Series: Maine - Residential Direct Install Program: Residential Air Sealing Program Drives Maine Home Energy Savings Through the Roof....

  6. Energy Secretary Chu Announces Five Million Smart Meters Installed...

    Broader source: Energy.gov (indexed) [DOE]

    TX) project involves deployment of a fully integrated advanced metering system and Web portal access to over 2.2 million customers and installation of advanced monitoring and...

  7. Helping Ensure High-Quality Installation of Solar Power Technologies...

    Broader source: Energy.gov (indexed) [DOE]

    Lorain County Community College Instructors install PV modules on training roof labs during the Midwest Renewable Energy Associations Train-the-Trainer PV Instructor...

  8. The Nuclear Installations (Dangerous Occurrences )(Amendment) Regulations 1963 

    E-Print Network [OSTI]

    Wood, Richard; Noble, Michael

    1963-01-01

    STATUTORY INSTRUMENTS 1963 No. 1358 ATOMIC ENERGY AND RADIOACTIVE SUBSTANCES LICENSING AND REGULATION OF SITES The Nuclear Installations (Dangerous Occurrences) (Amendment) Regulations 1963...

  9. Consider Installing High-Pressure Boilers with BackpressureTurbine...

    Broader source: Energy.gov (indexed) [DOE]

    high-pressure boilers with backpressure turbine-generators as part of optimized steam systems. STEAM TIP SHEET 22 Consider Installing High-Pressure Boilers with Backpressure...

  10. Fact #893: October 5, 2015 Incentives for the Installation of...

    Broader source: Energy.gov (indexed) [DOE]

    Incentives for the Installation of Electric Vehicle Charging Stations fotw893web.xlsx More Documents & Publications Richmond Electric Vehicle Initiative Electric Vehicle...

  11. Net Zero Energy Military Installations: A Guide to Assessment...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    for each installation is strongly site-specific, and may be identified using an optimization approach. Other nonrenewable load reduction projects (examples include co-...

  12. Combined Heat and Power (CHP) Installation Market to be Driven...

    Open Energy Info (EERE)

    overall combined heat and power installation market owing to widespread application in residential, commercial, and industrial segments. The growth of the Europe market can also...

  13. Installing and Maintaining a Home Solar Electric System | Department...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    | Photo courtesy of Dennis Schroeder, NREL. Making sure your home solar electric or photovoltaic (PV) system is sized, sited, installed, and maintained correctly is essential...

  14. Helping Ensure High-Quality Installation of Solar Power Technologies...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    April 15, 2013 - 12:00am Addthis Lorain County Community College Instructors install PV modules on training roof labs during the Midwest Renewable Energy Associations...

  15. DOE-DOD Emergency Backup Power Fuel Cell Installations

    SciTech Connect (OSTI)

    Fuel Cell Technologies Program

    2012-06-01

    Ths fact sheet describes a collaboration between the departments of Energy and Defense to install and operate 18 fuel cell backup power systems across the United States.

  16. Install Removable Insulation on Valves and Fittings | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    & Publications Insulate Steam Distribution and Condensate Return Lines Improving Steam System Performance: A Sourcebook for Industry, Second Edition Install an Automatic...

  17. Design, Installation, and Field Verification of Integrated Active...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Design, Installation, and Field Verification of Integrated Active Desiccant Hybrid Rooftop Systems Combined with a Natural Gas Driven Cogeneration Package, 2008 Design,...

  18. Installing and Maintaining a Home Solar Electric System | Department...

    Energy Savers [EERE]

    Making sure your home solar electric or photovoltaic (PV) system is sized, sited, installed, and maintained correctly is essential for maximizing its energy performance. When...

  19. Install an Automatic Blowdown-Control System | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Install an Automatic Blowdown-Control System (January 2012) More Documents & Publications Minimize Boiler Blowdown Recover Heat from Boiler Blowdown CIBO Energy Efficiency Handbook...

  20. Incorporating psychological influences in probabilistic cost analysis

    SciTech Connect (OSTI)

    Kujawski, Edouard; Alvaro, Mariana; Edwards, William

    2004-01-08

    Today's typical probabilistic cost analysis assumes an ''ideal'' project that is devoid of the human and organizational considerations that heavily influence the success and cost of real-world projects. In the real world ''Money Allocated Is Money Spent'' (MAIMS principle); cost underruns are rarely available to protect against cost overruns while task overruns are passed on to the total project cost. Realistic cost estimates therefore require a modified probabilistic cost analysis that simultaneously models the cost management strategy including budget allocation. Psychological influences such as overconfidence in assessing uncertainties and dependencies among cost elements and risks are other important considerations that are generally not addressed. It should then be no surprise that actual project costs often exceed the initial estimates and are delivered late and/or with a reduced scope. This paper presents a practical probabilistic cost analysis model that incorporates recent findings in human behavior and judgment under uncertainty, dependencies among cost elements, the MAIMS principle, and project management practices. Uncertain cost elements are elicited from experts using the direct fractile assessment method and fitted with three-parameter Weibull distributions. The full correlation matrix is specified in terms of two parameters that characterize correlations among cost elements in the same and in different subsystems. The analysis is readily implemented using standard Monte Carlo simulation tools such as {at}Risk and Crystal Ball{reg_sign}. The analysis of a representative design and engineering project substantiates that today's typical probabilistic cost analysis is likely to severely underestimate project cost for probability of success values of importance to contractors and procuring activities. The proposed approach provides a framework for developing a viable cost management strategy for allocating baseline budgets and contingencies. Given the scope and magnitude of the cost-overrun problem, the benefits are likely to be significant.

  1. Non-Epitaxial Thin-Film Indium Phosphide Photovoltaics: Growth, Devices, and Cost Analysis

    E-Print Network [OSTI]

    Zheng, Maxwell S

    2015-01-01

    solar_retaken_the_lowest_cost_pv_manufacturer_ mantle 10. M.the Context of PV Manufacturing Costs. IEEE Journal ofsilicon. Figure 3. Total PV system costs over time showing

  2. Cost and Performance Assumptions for Modeling Electricity Generation Technologies

    SciTech Connect (OSTI)

    Tidball, R.; Bluestein, J.; Rodriguez, N.; Knoke, S.

    2010-11-01

    The goal of this project was to compare and contrast utility scale power plant characteristics used in data sets that support energy market models. Characteristics include both technology cost and technology performance projections to the year 2050. Cost parameters include installed capital costs and operation and maintenance (O&M) costs. Performance parameters include plant size, heat rate, capacity factor or availability factor, and plant lifetime. Conventional, renewable, and emerging electricity generating technologies were considered. Six data sets, each associated with a different model, were selected. Two of the data sets represent modeled results, not direct model inputs. These two data sets include cost and performance improvements that result from increased deployment as well as resulting capacity factors estimated from particular model runs; other data sets represent model input data. For the technologies contained in each data set, the levelized cost of energy (LCOE) was also evaluated, according to published cost, performance, and fuel assumptions.

  3. Cost Model and Cost Estimating Software

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter discusses a formalized methodology is basically a cost model, which forms the basis for estimating software.

  4. Deliverable 3 Turbine Installation: Site Preparation and Footings

    E-Print Network [OSTI]

    Deliverable 3 Turbine Installation: Site Preparation and Footings Crissy Field Center Wind Power sufficient for industry standard analysis. Performance of the turbines on the site will be monitored programs. Deliverable 3 Turbine Installation: Site Preparation and Footings The Deliverables and Payment

  5. Targeting Net Zero Energy for Military Installations (Presentation)

    SciTech Connect (OSTI)

    Burman, K.

    2012-05-01

    Targeting Net Zero Energy for Military Installations in Kaneohe Bay, Hawaii. A net zero energy installation (NZEI) is one that produces as much energy from on-site renewable sources as it consumes. NZEI assessment provides a systematic approach to energy projects.

  6. Installing the VTF/AMROC Software July 28, 2011

    E-Print Network [OSTI]

    Deiterding, Ralf

    Ubuntu, Fedora, and RedHat. It is assumed that the user has the privileges to install system software software installation tool for your distribution (requires the root password). Fedora, for instance, in the graphical Add/Remove Software tool, shows a section Programming. On my Fedora system, the following packages

  7. Information Technology Systems April, 2012 BIDS 2008 Installation Instructions

    E-Print Network [OSTI]

    Olszewski Jr., Edward A.

    Information Technology Systems April, 2012 BIDS 2008 Installation Instructions Operating System Go developer's site #12;Information Technology Systems April, 2012 Note: If you receive an error on SQL Server 2005 before BIDS 2008 will load. #12;Information Technology Systems April, 2012 BIDS 2008 install

  8. Study Guide for Photovoltaic System Installers and Sample Examination Questions

    Office of Energy Efficiency and Renewable Energy (EERE)

    This study guide presents some of the basic cognitive material that individuals who install and maintain PV systems should understand. This information is intended primarily as a study guide to help better prepare for the NABCEP PV installer examination but does not provide all of the information needed for completing the certification examination.

  9. Paint with Your Voice: An Interactive, Sonic Installation

    E-Print Network [OSTI]

    Paint with Your Voice: An Interactive, Sonic Installation Abstract In this paper, we describe the design and implementa- tion of an interactive, sonic installation that lets visitors paint pictures paintbrush that paints onto a projected canvas. Depending on both pitch and volume of the visitor's voice

  10. Costing of Joining Methods -Arc Welding Costs

    E-Print Network [OSTI]

    Colton, Jonathan S.

    Costing of Joining Methods - Arc Welding Costs ver. 1 ME 6222: Manufacturing Processes and Systems.S. Colton © GIT 2009 5 #12;LaborLabor Di t ti f ldi· Direct time of welding ­ time to produce a length of weld ­ labor rate ­ multiplication gives labor cost per length · Set-up time, etc. · Personal time

  11. Total Crude by Pipeline

    U.S. Energy Information Administration (EIA) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home PageMonthly","10/2015"4,"Ames5 Tables July 1996 Energy Information Administration Office of Coal, Nuclear,DecadeYearbyWithdrawalsHome6,672(MillionFeet)Product: Total

  12. Information erasure without an energy cost

    E-Print Network [OSTI]

    Joan A. Vaccaro; Stephen M. Barnett

    2011-06-01

    Landauer argued that the process of erasing the information stored in a memory device incurs an energy cost in the form of a minimum amount of mechanical work. We find, however, that this energy cost can be reduced to zero by paying a cost in angular momentum or any other conserved quantity. Erasing the memory of Maxwell's demon in this way implies that work can be extracted from a single thermal reservoir at a cost of angular momentum and an increase in total entropy. The implications of this for the second law of thermodynamics are assessed.

  13. Low cost robotic imaging system for high precision photometry

    E-Print Network [OSTI]

    Guyon, Olivier

    Low cost robotic imaging system for high precision photometry Olivier Guyon (Subaru Telescope robotic, robust to weather, hardware failures, software errors automatic decision making (flats, darks angular resolution (with longer focal length lens) Installed Dec 30, 2010 ­ working robotically now New

  14. Utility Cost Analysis 

    E-Print Network [OSTI]

    Horn, S.

    1984-01-01

    One of the first steps in setting up an energy management program in a commercial building is determining operating costs per energy consuming system through a utility cost analysis. This paper illustrates utility cost analysis methods used...

  15. Activity Based Costing

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Activity Based Costing (ABC) is method for developing cost estimates in which the project is subdivided into discrete, quantifiable activities or a work unit. This chapter outlines the Activity Based Costing method and discusses applicable uses of ABC.

  16. Install Sun Java Plug-In for PRISM You will need administrator rights to your computer to install Java.

    E-Print Network [OSTI]

    Jiang, Huiqiang

    Install Sun Java Plug-In for PRISM You will need administrator rights to your computer to install Java. Please contact your technical support group for assistance. 1. Go to the following web site to download the Sun Java plug-in. http://www.java.com/en/download/manual.jsp 2. Click the link for your

  17. Install Sun Java Plug-In for PRISM You will need administrator rights to your computer to install Java.

    E-Print Network [OSTI]

    Sibille, Etienne

    Install Sun Java Plug-In for PRISM You will need administrator rights to your computer to install Java. Please contact your technical support group for assistance. 1. Go to the following web site to download the Sun Java plug-in. http://www.java.com/en/download/manual.jsp 2. Click the Windows 7, XP Online

  18. Install Sun Java Plug-In for PRISM You will need administrator rights to your computer to install Java.

    E-Print Network [OSTI]

    Sibille, Etienne

    Install Sun Java Plug-In for PRISM You will need administrator rights to your computer to install Java. Please contact your technical support group for assistance. 1. Go to the following web site to download the Sun Java plug-in. http://www.oracle.com/technetwork/java/javase/downloads/index.html 2. Next

  19. Install, both Arduino and AmaSeis software programs: Installing Arduino and drivers: Setting up AmaSeis

    E-Print Network [OSTI]

    Barrash, Warren

    Install, both Arduino and AmaSeis software programs: Installing Arduino and drivers: Setting up Ama the Arduino drivers. Take note of the assigned com port number, and set up AmaSeis to that number. 3. Some computers will require the following. Keep in mind, Arduino, does not need to run or be involved. You just

  20. Final report on the waste area grouping perimeter groundwater quality monitoring well installation program at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    SciTech Connect (OSTI)

    Greene, J.A.

    1991-06-01

    A groundwater quality monitoring well installation program was conducted at Oak Ridge National Laboratory (ORNL) to meet the requirements of environmental regulations, including the Resource Conservation and Recovery Act (RCRA) and the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). A total of 173 wells were installed and developed at 11 different waste area groupings (WAGs) between June 1986 and November 1990. A location map of the wells is included.

  1. Sharing Supermodular Costs

    E-Print Network [OSTI]

    2010-06-23

    For a particular class of supermodular cost cooperative games that arises from a scheduling ... the costs collectively incurred by a group of cooperating agents.

  2. Study on the financing mechanism and management for decommissioning of nuclear installations in Malaysia

    SciTech Connect (OSTI)

    Saleh, Lydia Ilaiza Ryong, Kim Tae

    2015-04-29

    The whole cycle of the decommissioning process development of repository requires the relevant bodies to have a financial system to ensure that it has sufficient funds for its whole life cycle (over periods of many decades). Therefore, the financing mechanism and management system shall respect the following status: the national position, institutional and legislative environment, technical capabilities, the waste origin, ownership, characteristics and inventories. The main objective of the studies is to focus on the cost considerations, alternative funding managements and mechanisms, technical and non-technical factors that may affect the repository life-cycle costs. As a conclusion, the outcomes of this paper is to make a good recommendation and could be applied to the national planners, regulatory body, engineers, or the managers, to form a financial management plan for the decommissioning of the Nuclear Installation.

  3. PHENIX Work Breakdown Structure. Cost and schedule review copy

    SciTech Connect (OSTI)

    Not Available

    1994-02-01

    The Work Breakdown Structure (WBS) Book begins with this Overview section, which contains the high-level summary cost estimate, the cost profile, and the global construction schedule. The summary cost estimate shows the total US cost and the cost in terms of PHENIX construction funds for building the PHENIX detector. All costs in the WBS book are shown in FY 1993 dollars. Also shown are the institutional and foreign contributions, the level of pre-operations funding, and the cost of deferred items. Pie charts are presented at PHENIX WBS level 1 and 2 that show this information. The PHENIX construction funds are shown broken down to PHENIX WBS level 3 items per fiscal year, and the resulting profile is compared to the RHIC target profile. An accumulated difference of the two profiles is also shown. The PHENIX global construction schedule is presented at the end of the Overview section. Following the Overview are sections for each subsystem. Each subsystem section begins with a summary cost estimate, cost profile, and critical path. The total level 3 cost is broken down into fixed costs (M&S), engineering costs (EDIA) and labor costs. Costs are further broken down in terms of PHENIX construction funds, institutional and foreign contributions, pre-operations funding, and deferred items. Also shown is the contingency at level 3 and the level 4 breakdown of the total cost. The cost profile in fiscal years is shown at level 3. The subsystem summaries are followed by the full cost estimate and schedule sheets for that subsystem. These detailed sheets are typically carried down to level 7 or 8. The cost estimate shows Total, M&S, EDIA, and Labor breakdowns, as well as contingency, for each WBS entry.

  4. PHENIX WBS notes. Cost and schedule review copy

    SciTech Connect (OSTI)

    Not Available

    1994-02-01

    The Work Breakdown Structure (WBS) Book begins with this Overview section, which contains the high-level summary cost estimate, the cost profile, and the global construction schedule. The summary cost estimate shows the total US cost and the cost in terms of PHENIX construction funds for building the PHENIX detector. All costs in the WBS book are shown in FY 1993 dollars. Also shown are the institutional and foreign contributions, the level of pre-operations funding, and the cost of deferred items. Pie charts are presented at PHENIX WBS level 1 and 2 that show this information. The PHENIX construction funds are shown broken down to PHENIX WBS level 3 items per fiscal year, and the resulting profile is compared to the RHIC target profile. An accumulated difference of the two profiles is also shown. The PHENIX global construction schedule is presented at the end of the Overview section. Following the Overview are sections for each subsystem. Each subsystem section begins with a summary cost estimate, cost profile, and critical path. The total level 3 cost is broken down into fixed costs (M&S), engineering costs (EDIA) and labor costs. Costs are further broken down in terms of PHENIX construction funds, institutional and foreign contributions, pre-operations funding, and deferred items. Also shown is the contingency at level 3 and the level 4 breakdown of the total cost. The cost profile in fiscal years is shown at level 3. The subsystem summaries are followed by the full cost estimate and schedule sheets for that subsystem. These detailed sheets are typically carried down to level 7 or 8. The cost estimate Total, M&S, EDIA, and Labor breakdowns, as well as contingency, for each WBS entry.

  5. Income and Cost Analysis: Cooperative Cotton Gins and Cooperative Supply Associations of Texas, Season 1949-50. 

    E-Print Network [OSTI]

    Paulson, W. E.

    1955-01-01

    .237 367 337.1 Total $39.406 $3,934 $5,459 48,799 $44,755 109.0 Figure 1. Income and cost chart-totals and per bale. TABLE 7. CLASSIFICAT~ON OF COSTS OF A SPECIFIC GIN Cost item Costs influenced Common bv volume costs Management $ 6,913 Office... ---_---__-__------.---.-------------__ 6 Trucking -------------~_-_-_-------------------_- 7 Miscellaneous 7 Nonvolume Costs 7 Estimating Standard Cost .--__--_---_---_---------------- 7 Page Profit Chart .--_ _-_----__----__- --------------------------_--------- 8 Spreading...

  6. Preliminary assessment report for Fort Jacob F. Wolters, Installation 48555, Mineral Wells, Texas. Installation Restoration Program

    SciTech Connect (OSTI)

    Dennis, C.B.

    1993-08-01

    This report presents the results of the preliminary assessment (PA) conducted by Argonne National Laboratory at the Texas Army National Guard (TXARNG) property near Mineral Wells, Texas. Preliminary assessments of federal facilities are being conducted to compile the information necessary for completing preremedial activities and to provide a basis for establishing corrective actions in response to releases of hazardous substances. The principal objective of the PA is to characterize the site accurately and determine the need for further action by examining site activities, quantities of hazardous substances present, and potential pathways by which contamination could affect public health and the environment. This PA satisfies, for the Fort Wolters property, the requirement of the Department of Defense Installation Restoration Program.

  7. Preliminary assessment report for Camp Swift Military Reservation, Installation 48070, Bastrop County, Texas. Installation Restoration Program

    SciTech Connect (OSTI)

    Dennis, C.B.

    1993-08-01

    This report presents the results of the preliminary assessment (PA) conducted by Argonne National Laboratory at the Texas Army National Guard property in Bastrop County, Texas. Preliminary assessments of federal facilities are being conducted to compile the information necessary for completing preremedial activities and to provide a basis for establishing corrective actions in response to releases of hazardous substances. The principal objective of the PA is to characterize the site accurately and determine the need for further action by examining site activities, quantities of hazardous substances present, and potential pathways by which contamination could affect public health and the environment. This PA satisfies, for the Camp Swift property, the requirement of the Department of Defense Installation Restoration Program (IRP). The review of both historical and current practices at the property indicated that the activities at Camp Swift include no operations considered to have an adverse impact to the environment. The recommendation, therefore, is that no further IRP action is necessary at this property.

  8. Preliminary assessment report for Fort Custer Training Center, Installation 26035, Augusta, Michigan. Installation Restoration Program

    SciTech Connect (OSTI)

    Flaim, S.; Krokosz, M.

    1993-08-01

    This report presents the results of the preliminary assessment (PA) conducted by Argonne National Laboratory at the Michigan Army National Guard property near Augusta, Michigan. Preliminary assessments of federal facilities are being conducted to compile the information necessary for completing preremedial activities and to provide a basis for establishing corrective actions in response to releases of hazardous substances. The principal objective of the PA is to characterize the site accurately and determine the need for further action by examining site activities, quantities of hazardous substances present, and potential pathways by which contamination could affect public health and the environment. This PA satisfies, for the Fort Custer Training Center, phase I of the Department of Defense Installation Restoration Program. The environmentally significant operations associated with the property are (1) storage of hazardous materials and hazardous waste, (2) storage and dispensing of fuel, (3) washing of vehicles and equipment, and (4) weapons training ranges that may have accumulated lead.

  9. Quality Cost Analysis: Benefits and Risks Copyright Cem Kaner

    E-Print Network [OSTI]

    Quality Cost Analysis: Benefits and Risks Copyright © Cem Kaner January, 1996 All rights reserved quality-related costs as a means of communication between the quality staff departments and the company of quality-related costs since 1951. Feigenbaum made it one of the core ideas underlying the Total Quality

  10. Costs of Generating Electrical Energy 1.0 Overview

    E-Print Network [OSTI]

    McCalley, James D.

    /kg. The total cost of bringing uranium to the fuel rods of a nuclear power plant, considering mining, sometimes called production costs. We begin with nuclear. Enriched uranium (3.5% U-235) in a light water, "Parametric Study ofFront-EndNuclearFuelCycle Costs Using Reprocessed Uranium," January 2010. 2 This is a very

  11. What History Can Teach Us about the Future Costs

    E-Print Network [OSTI]

    Kammen, Daniel M.

    Viewpointt What History Can Teach Us about the Future Costs of U.S. NUCLEAR POWER Past experience suggests that high-cost surprises should be included in the planning process. NATHAN E. HULTMAN GEORGETOWN total cost, and incur financial risks no greater than those for other energy technologies. In this ar

  12. Cost Estimation Package

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter focuses on the components (or elements) of the cost estimation package and their documentation.

  13. A chronicle of costs

    SciTech Connect (OSTI)

    Elioff, T.

    1994-04-01

    This report contains the history of all estimated costs associated with the superconducting super collider.

  14. Life Cycle Cost Estimate

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Life-cycle costs (LCCs) are all the anticipated costs associated with a project or program alternative throughout its life. This includes costs from pre-operations through operations or to the end of the alternative.This chapter discusses life cycle costs and the role they play in planning.

  15. Banner Job Installation Security Form Office of Information Technology

    E-Print Network [OSTI]

    Karsai, Istvan

    Banner Job Installation Security Form Office of Information Technology 424 Roy S. Nicks Hall, Box: ______________________________ Job Description: ______________________________ Section 3. Security Information Banner Module 70728 Johnson City, Tennessee 37614 (423) 439-4648 · oithelp@etsu.edu Section 1. Requestor Information

  16. Offshore Wind Energy Market Installed Capacity is Anticipated...

    Open Energy Info (EERE)

    Offshore Wind Energy Market Installed Capacity is Anticipated to Reach 52,120.9 MW by 2022 Home > Groups > Renewable Energy RFPs Wayne31jan's picture Submitted by Wayne31jan(150)...

  17. Seeing solar on campus : a visible photovoltaic installation on campus

    E-Print Network [OSTI]

    Guarda, Daniel Jair Alves

    2006-01-01

    This paper presents a methodology for selecting a site on the MIT campus for a visible solar photovoltaic installation. Visibility, solar exposure, advertising potential, aesthetics, interactivity and direct or important ...

  18. ARRA Program Celebrates Milestone 600,000 Smart Meter Installations

    Broader source: Energy.gov [DOE]

    On April 11, 2012, DOE Recovery Act funding recipient Sacramento Municipal Utility District (SMUD) celebrated a major milestone in the development of a regional smart grid in California: the installation of over 600,000 smart meters.

  19. Hindawi Publishing Corporation Science and Technology of Nuclear Installations

    E-Print Network [OSTI]

    Demazière, Christophe

    Hindawi Publishing Corporation Science and Technology of Nuclear Installations Volume 2013, Article Department of Nuclear Chemistry, Chalmers University of Technology, 412 96 Gothenburg, Sweden 2 Department of Nuclear Engineering, Chalmers University of Technology, 412 96 Gothenburg, Sweden Correspondence should

  20. Video Installation Design: Appropriation and Assemblage As Projection Surface Geometry 

    E-Print Network [OSTI]

    Weaver, Timothy A.

    2010-07-14

    This area of research focuses on the use of video projections in the context of fine art. Emphasis is placed on creating a unique video installation work that incorporates assemblage and appropriation as a means to develop multiple complex...

  1. Fact #893: October 5, 2015 Incentives for the Installation of...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    common type of incentive is a state tax credit, but there are also states that give rebates, grants, tax exemptions, and loans to those installing EVSE. The incentives can apply...

  2. NMDOT Application for Permit to Install Utility Facilities Within...

    Open Energy Info (EERE)

    Application for Permit to Install Utility Facilities Within Public ROW Jump to: navigation, search OpenEI Reference LibraryAdd to library Legal Document- OtherOther: NMDOT...

  3. Army installations of the future : urban + shrinkage + landscape

    E-Print Network [OSTI]

    Howell, Dwight D. (Dwight Dee)

    2015-01-01

    The US Army has set a course to transition to a future force that is adaptive, modern, and at the forefront of change. This strategic vision lacks a refined installation strategy to meet the needs of the future force. In ...

  4. DoD Energy Innovation on Military Installations

    Energy Savers [EERE]

    Operational Energy Facility Energy 49% 32% 8% 7% 3% 1% 0% Electricity Natural Gas Fuel Oil Coal Steam LPG Other Test Bed Focus 4 Smart Secure Installation Energy Management *...

  5. New concept for a general purpose subsea installation system

    SciTech Connect (OSTI)

    Citi, G.; Cowen, S.; Radicioni, A.

    1996-12-31

    The first use of the Agip SAF System (Sistema Alti Fondali), an installation and maintenance system for subsea production systems up to 1,000 m water depth, was successfully performed on the Luna 40 well in 180 m w.d. The system successfully installed the christmas tree, flowline jumpers, control system and high pressure cap as well as deploying the LMRP to allow the commissioning of the well. The SAF system performed all the planned tasks during the installation of the Luna 40 subsea tree and now has to be considered an operational success. The system is based around a Master Vehicle that provides hydraulic power to, and controls a set of dedicated work modules. During the 2 test and 5 working dives, the Master Vehicle and the modules were subsea for a considerable period of time, up to 75 hours continuously, without any operational failures. This installation uncovered some system deficiencies that will have to be studied to improve the reliability and operability of the system. From the experience gained during this operation it has been shown that the system of a Master Vehicle providing locally generated hydraulic power is a feasible approach to many subsea installation problems. This paper describes the SAF system including improvements to be performed before being used operationally in up to 1,000 m of water and over. It also covers the necessary modifications required to allow the system to be deployed from a wide range of installation vessel.

  6. Solar Total Energy Project final test report

    SciTech Connect (OSTI)

    Nelson, R.F.; Abney, L.O.; Towner, M.L. (Georgia Power Co., Shenandoah, GA (USA))

    1990-09-01

    The Solar Total Energy Project (STEP), a cooperative effort between the United States Department of Energy (DOE) and Georgia Power Company (GPC) located at Shenandoah, Georgia, has undergone several design modifications based on experience from previous operations and test programs. The experiences encountered were discussed in detail in the Solar Total Energy Project Summary Report'' completed in 1987 for DOE. Most of the proposed changes discussed in this report were installed and tested in 1987 as part of two 15-day test programs (SNL Contract No. 06-3049). However, several of the suggested changes were not completed before 1988. These plant modifications include a new distributed control system for the balance of plant (BOP), a fiber a optical communications ring for the field control system, and new control configuration reflecting the new operational procedures caused by the plant modifications. These modifications were tested during a non-consecutive day test, and a 60-day field test conducted during the autumn of 1989. These test were partially funded by SNL under Contract No. 42-4859, dated June 22, 1989. Results of these tests and preliminary analysis are presented in this test summary report. 9 refs., 19 figs., 7 tabs.

  7. A least-cost optimisation model of CO{sub 2} capture applied to major UK power plants within the EU-ETS framework

    SciTech Connect (OSTI)

    Kemp, A.G.; Kasim, A.S.

    2008-02-15

    Concerns about the cost of CO{sub 2} capture and sequestration, and the effectiveness of carbon abatement policies loom large in discussions on climate change mitigation. Several writers address the issue from various perspectives. This paper attempts to add relative realism to discussions on CO{sub 2} capture costs and the deployment of carbon capture technology in the UK by using publicly available company data on the long term capacity expansion and CO{sub 2} capture investment programmes of selected power plants in the UK. With an estimated 8 billion plan to install a generation capacity of GW and capture capability of 44 Mt CO{sub 2}/year, it is imperative to optimise this huge potential investment. A least-cost optimisation model was formulated and solved with the LP algorithm available in GAMS. The model was then applied to address a number of issues, including the choice of an optimal carbon abatement policy within the EU-ETS framework. The major findings of the study include (a) the long term total cost curve of CO{sub 2} capture has three phases rising, plateau, rising; (b) alternative capture technologies do not have permanent relative cost advantages or disadvantages; (c) Government incentives encourage carbon capture and the avoidance of emission penalty charges; and (d) the goals of EU-ETS are more effectively realised with deeper cuts in the EUA ratios than merely hiking the emission penalty, as proposed in EU-ETS Phase II.

  8. Purpose Destination Date Parts Labor Costs

    E-Print Network [OSTI]

    Rock, Chris

    Report Previous Month Odometer Lub./ Fluid or Fuel Qty. Cost YearType Trip/Daily Ending Odometer Vehicle as necessary. $ $ $ Fuel/Fluid Type CNG=COMP.NAT.GAS DSL=DIESEL ELE=ELECTRICITY ETH=ETHANOL GAS=UNLEADEDGAS LPG=PROPANE MTH=METHANOL BDL=BIODIESEL Total Costs $ $ $ Fuel data entry must be per transaction A D D A D D #12;

  9. Potential for Photovoltaic Solar Installation in Non-Irrigated Corners of Center Pivot Irrigation Fields in the State of Colorado

    SciTech Connect (OSTI)

    Roberts, B.

    2011-07-01

    The State of Colorado expressed an interest in assessing the potential for photovoltaic (PV) solar installations on non-irrigated corners of center-pivot irrigation (CPI) fields throughout the state. Using aerial imagery and irrigated land data available from the Colorado Water Conservation Board, an assessment of potentially suitable sites was produced. Productivity estimates were calculated from that assessment. The total area of non-irrigated corners of CPI fields in Colorado was estimated to be 314,674 acres, which could yield 223,418 acres of installed PV panels assuming 71% coverage in triangular plots. The total potential annual electricity production for the state was estimated to be 56,821 gigawatt hours (GWH), with an average of 1.3 GWH per available plot.

  10. Low-Cost Spectral Sensor Development Description.

    SciTech Connect (OSTI)

    Armijo, Kenneth Miguel; Yellowhair, Julius

    2014-11-01

    Solar spectral data for all parts of the US is limited due in part to the high cost of commercial spectrometers. Solar spectral information is necessary for accurate photovoltaic (PV) performance forecasting, especially for large utility-scale PV installations. A low-cost solar spectral sensor would address the obstacles and needs. In this report, a novel low-cost, discrete- band sensor device, comprised of five narrow-band sensors, is described. The hardware is comprised of commercial-off-the-shelf components to keep the cost low. Data processing algorithms were developed and are being refined for robustness. PV module short-circuit current ( I sc ) prediction methods were developed based on interaction-terms regression methodology and spectrum reconstruction methodology for computing I sc . The results suggest the computed spectrum using the reconstruction method agreed well with the measured spectrum from the wide-band spectrometer (RMS error of 38.2 W/m 2 -nm). Further analysis of computed I sc found a close correspondence of 0.05 A RMS error. The goal is for ubiquitous adoption of the low-cost spectral sensor in solar PV and other applications such as weather forecasting.

  11. U.S. Total Exports

    Gasoline and Diesel Fuel Update (EIA)

    Total to Spain Cameron, LA Sabine Pass, LA Total to United Kingdom Sabine Pass, LA LNG Exports from Babb, MT LNG Exports from Buffalo, NY LNG Exports from Kenai, AK LNG Exports...

  12. Pollution prevention cost savings potential

    SciTech Connect (OSTI)

    Celeste, J.

    1994-12-01

    The waste generated by DOE facilities is a serious problem that significantly impacts current operations, increases future waste management costs, and creates future environmental liabilities. Pollution Prevention (P2) emphasizes source reduction through improved manufacturing and process control technologies. This concept must be incorporated into DOE`s overall operating philosophy and should be an integral part of Total Quality Management (TQM) program. P2 reduces the amount of waste generated, the cost of environmental compliance and future liabilities, waste treatment, and transportation and disposal costs. To be effective, P2 must contribute to the bottom fine in reducing the cost of work performed. P2 activities at LLNL include: researching and developing innovative manufacturing; evaluating new technologies, products, and chemistries; using alternative cleaning and sensor technologies; performing Pollution Prevention Opportunity Assessments (PPOAs); and developing outreach programs with small business. Examples of industrial outreach are: innovative electroplating operations, printed circuit board manufacturing, and painting operations. LLNL can provide the infrastructure and technical expertise to address a wide variety of industrial concerns.

  13. Facilities and Administration (Indirect) Costs Rates Facilities and Administrative (indirect) costs rates are the result of negotiations with the U.S.

    E-Print Network [OSTI]

    Saldin, Dilano

    Facilities and Administration (Indirect) Costs Rates Facilities and Administrative (indirect) costs (Indirect Costs) Source of Funds Applicable To F&A Rate DHHS Federally Negotiated Rates: Federal, Non or a different rate has been approved by the Director of OSP. *MTDC Base: Modified total direct costs consist

  14. Parabolic Trough Collector Cost Update for the System Advisor Model (SAM)

    SciTech Connect (OSTI)

    Kurup, Parthiv; Turchi, Craig S.

    2015-11-01

    This report updates the baseline cost for parabolic trough solar fields in the United States within NREL's System Advisor Model (SAM). SAM, available at no cost at https://sam.nrel.gov/, is a performance and financial model designed to facilitate decision making for people involved in the renewable energy industry. SAM is the primary tool used by NREL and the U.S. Department of Energy (DOE) for estimating the performance and cost of concentrating solar power (CSP) technologies and projects. The study performed a bottom-up build and cost estimate for two state-of-the-art parabolic trough designs -- the SkyTrough and the Ultimate Trough. The SkyTrough analysis estimated the potential installed cost for a solar field of 1500 SCAs as $170/m2 +/- $6/m2. The investigation found that SkyTrough installed costs were sensitive to factors such as raw aluminum alloy cost and production volume. For example, in the case of the SkyTrough, the installed cost would rise to nearly $210/m2 if the aluminum alloy cost was $1.70/lb instead of $1.03/lb. Accordingly, one must be aware of fluctuations in the relevant commodities markets to track system cost over time. The estimated installed cost for the Ultimate Trough was only slightly higher at $178/m2, which includes an assembly facility of $11.6 million amortized over the required production volume. Considering the size and overall cost of a 700 SCA Ultimate Trough solar field, two parallel production lines in a fully covered assembly facility, each with the specific torque box, module and mirror jigs, would be justified for a full CSP plant.

  15. Benchmarking Soft Costs for PV Systems in the United States (Presentation)

    SciTech Connect (OSTI)

    Ardani, K.

    2012-06-01

    This paper presents results from the first U.S. based data collection effort to quantify non-hardware, business process costs for PV systems at the residential and commercial scales, using a bottom-up approach. Annual expenditure and labor hour productivity data are analyzed to benchmark business process costs in the specific areas of: (1) customer acquisition; (2) permitting, inspection, and interconnection; (3) labor costs of third party financing; and (4) installation labor.

  16. Direct/Indirect Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    This chapter provides recommended categories for direct and indirect elements developed by the Committee for Cost Methods Development (CCMD) and describes various estimating techniques for direct and indirect costs.

  17. Developing Information on Energy Savings and Associated Costs and Benefits of Energy Efficient Emerging Technologies Applicable in California

    E-Print Network [OSTI]

    Xu, Tengfang

    2011-01-01

    and grid owners. Energy (and cost) savings might be found inSystem to Offset Peak Energy Cost at a Wastewater TreatmentSavings Estimation (GWh) Energy Costs Current Other Total

  18. Renewable Energy Assessment Methodology for Japanese OCONUS Army Installations

    SciTech Connect (OSTI)

    Solana, Amy E.; Horner, Jacob A.; Russo, Bryan J.; Gorrissen, Willy J.; Kora, Angela R.; Weimar, Mark R.; Hand, James R.; Orrell, Alice C.; Williamson, Jennifer L.

    2010-08-30

    Since 2005, Pacific Northwest National Laboratory (PNNL) has been asked by Installation Management Command (IMCOM) to conduct strategic assessments at selected US Army installations of the potential use of renewable energy resources, including solar, wind, geothermal, biomass, waste, and ground source heat pumps (GSHPs). IMCOM has the same economic, security, and legal drivers to develop alternative, renewable energy resources overseas as it has for installations located in the US. The approach for continental US (CONUS) studies has been to use known, US-based renewable resource characterizations and information sources coupled with local, site-specific sources and interviews. However, the extent to which this sort of data might be available for outside the continental US (OCONUS) sites was unknown. An assessment at Camp Zama, Japan was completed as a trial to test the applicability of the CONUS methodology at OCONUS installations. It was found that, with some help from Camp Zama personnel in translating and locating a few Japanese sources, there was relatively little difficulty in finding sources that should provide a solid basis for conducting an assessment of comparable depth to those conducted for US installations. Project implementation will likely be more of a challenge, but the feasibility analysis will be able to use the same basic steps, with some adjusted inputs, as PNNL’s established renewable resource assessment methodology.

  19. HighCharts Non-commercial installation and activation help needed...

    Open Energy Info (EERE)

    Non-commercial installation and activation help needed Home > Groups > Databus Hi, I have installed Databus. After a fewdays the dashboard went blank with the message to...

  20. Supersonic Air Jets Preserve Tree Roots in Underground Pipeline Installation1

    E-Print Network [OSTI]

    Supersonic Air Jets Preserve Tree Roots in Underground Pipeline Installation1 Rob Gross 2 trenching operations for pipeline installation. Although mechanical soil excavation using heavy equipment

  1. Power Plant Cycling Costs

    SciTech Connect (OSTI)

    Kumar, N.; Besuner, P.; Lefton, S.; Agan, D.; Hilleman, D.

    2012-07-01

    This report provides a detailed review of the most up to date data available on power plant cycling costs. The primary objective of this report is to increase awareness of power plant cycling cost, the use of these costs in renewable integration studies and to stimulate debate between policymakers, system dispatchers, plant personnel and power utilities.

  2. Energy Department Completes Cool Roof Installation on DC Headquarters...

    Broader source: Energy.gov (indexed) [DOE]

    cost to adding the cool roof as part of the roof replacement project and it will save taxpayers 2,000 every year in building energy costs. Cool roofs use lighter-colored...

  3. Solar heating system installed at Troy, Ohio. Final report

    SciTech Connect (OSTI)

    None

    1980-09-01

    This document is the Final Report of the Solar Energy System located at Troy-Miami County Public Library, Troy, Ohio. The completed system is composed of tree basic subsystems: the collector system consisting of 3264 square feet of Owens Illinois evacuated glass tube collectors; the storage system which includes a 5000-gallon insulated steel tank; and the distribution and control system which includes piping, pumping and control logic for the efficient and safe operation of the entire system. This solar heating system was installed in an existing facility and is, therefore, a retrofit system. This report includes extracts from the site files, specifications, drawings, installation, operation and maintenance instructions.

  4. The Draugen platform and subsea structures, installation and foundation aspects

    SciTech Connect (OSTI)

    Alm, T.; Bye, A.; Sandvik, K.; Egeland, S.

    1995-12-01

    Installation data from the Draugen GBS and subsea structures have been processed and analyzed in order to verify the design assumptions with regards to soil reactions. These results have shown that penetration of concrete skirts and piles into the very hard clay layer, typically found at the Haltenbanken area is feasible. The resistances may be predicted with reasonable accuracy using conventional methods and average soil strength values as obtained by traditional soil testing. This paper reveals and comments the installation data both for the gravity platform and the piles for the different subsea structures and provides and updated basis for foundation design of similar structures in the area.

  5. Offshore Wind Plant Balance-of-Station Cost Drivers and Sensitivities (Poster)

    SciTech Connect (OSTI)

    Saur, G.; Maples, B.; Meadows, B.; Hand, M.; Musial, W.; Elkington, C.; Clayton, J.

    2012-09-01

    With Balance of System (BOS) costs contributing up to 70% of the installed capital cost, it is fundamental to understanding the BOS costs for offshore wind projects as well as potential cost trends for larger offshore turbines. NREL developed a BOS model using project cost estimates developed by GL Garrad Hassan. Aspects of BOS covered include engineering and permitting, ports and staging, transportation and installation, vessels, foundations, and electrical. The data introduce new scaling relationships for each BOS component to estimate cost as a function of turbine parameters and size, project parameters and size, and soil type. Based on the new BOS model, an analysis to understand the non-turbine costs associated with offshore turbine sizes ranging from 3 MW to 6 MW and offshore wind plant sizes ranging from 100 MW to 1000 MW has been conducted. This analysis establishes a more robust baseline cost estimate, identifies the largest cost components of offshore wind project BOS, and explores the sensitivity of the levelized cost of energy to permutations in each BOS cost element. This presentation shows results from the model that illustrates the potential impact of turbine size and project size on the cost of energy from US offshore wind plants.

  6. U.S. Balance-of-Station Cost Drivers and Sensitivities (Presentation)

    SciTech Connect (OSTI)

    Maples, B.

    2012-10-01

    With balance-of-system (BOS) costs contributing up to 70% of the installed capital cost, it is fundamental to understanding the BOS costs for offshore wind projects as well as potential cost trends for larger offshore turbines. NREL developed a BOS model using project cost estimates developed by GL Garrad Hassan. Aspects of BOS covered include engineering and permitting, ports and staging, transportation and installation, vessels, foundations, and electrical. The data introduce new scaling relationships for each BOS component to estimate cost as a function of turbine parameters and size, project parameters and size, and soil type. Based on the new BOS model, an analysis to understand the non?turbine costs has been conducted. This analysis establishes a more robust baseline cost estimate, identifies the largest cost components of offshore wind project BOS, and explores the sensitivity of the levelized cost of energy to permutations in each BOS cost element. This presentation shows results from the model that illustrates the potential impact of turbine size and project size on the cost of energy from U.S. offshore wind plants.

  7. Cost Model for Digital Curation: Cost of Digital Migration

    E-Print Network [OSTI]

    Kejser, Ulla Bøgvad; Nielsen, Anders Bo; Thirifays, Alex

    2009-01-01

    Steece, B. 2000. Software cost estimation with COCOMO II.Developing a Framework of Cost Elements for PreservingAshley, K. 1999. Digital archive costs: Facts and fallacies.

  8. Development of a deepwater installation and maintenance concept for subsea production systems

    SciTech Connect (OSTI)

    Brancart, C.P.; Henkener, J.A.

    1996-09-01

    Most of the world`s remaining high output petroleum reservoirs tend to be located in the deep ocean. Existing capabilities are challenged for producing oil in 3,000 to 6,000 feet of sea water. It may be possible to extrapolate these existing capabilities for deeper operations but with an associated exponential cost increase. Based on technologies derived from Department of Defense programs, the authors have proposed a subsea completion installation and maintenance concept that requires no mechanical ties between the surface and the bottom of the ocean. Using tetherless underwater vehicles, a modularized subsea completion system can be delivered to the ocean floor, where it is assembled, inter-connected, and tested. The concept is further amplified in the paper.

  9. Cost of Oil Dependence: A 2000 Update

    SciTech Connect (OSTI)

    Greene, D.L.; Tishchishyna, N.I.

    2000-05-01

    Oil dependence remains a potentially serious economic and strategic problem for the United States. This report updates previous estimates of the costs of oil dependence to the U.S. economy and introduces several methodological enhancements. Estimates of the costs to the U.S. economy of the oil market upheavals of the last 30 years are in the vicinity of $7 trillion, present value 1998 dollars, about as large as the sum total of payments on the national debt over the same period. Simply adding up historical costs in 1998 dollars without converting to present value results in a Base Case cost estimate of $3.4 trillion. Sensitivity analysis indicates that cost estimates are sensitive to key parameters. A lower bound estimate of $1.7 trillion and an upper bound of $7.1 trillion (not present value) indicate that the costs of oil dependence have been large under almost any plausible set of assumptions. These cost estimates do not include military, strategic or political costs associated with U.S. and world dependence on oil imports.

  10. Costs of Oil Dependence: A 2000 Update

    SciTech Connect (OSTI)

    Greene, D.L.

    2000-05-17

    Oil dependence remains a potentially serious economic and strategic problem for the United States. This report updates previous estimates of the costs of oil dependence to the U.S. economy and introduces several methodological enhancements. Estimates of the costs to the U.S. economy of the oil market upheavals of the last 30 years are in the vicinity of $7 trillion, present value 1998 dollars, about as large as the sum total of payments on the national debt over the same period. Simply adding up historical costs in 1998 dollars without converting to present value results in a Base Case cost estimate of $3.4 trillion. Sensitivity analysis indicates that cost estimates are sensitive to key parameters. A lower bound estimate of $1.7 trillion and an upper bound of $7.1 trillion (not present value) indicate that the costs of oil dependence have been large under almost any plausible set of assumptions. These cost estimates do not include military, strategic or political costs associated with U.S. and world dependence on oil imports.

  11. MUJERES TOTAL BIOLOGIA 21 32

    E-Print Network [OSTI]

    Autonoma de Madrid, Universidad

    CIENCIAS ECON�MICAS Y EMPRESARIALES TOTAL DERECHO Nº de tesis leídas y aprobadas por centro y departamento en el año 2014 CENTRO DEPARTAMENTO Nº DE TESIS CIENCIAS MEDICINA TOTAL MEDICINA #12;MUJERES TOTAL Nº de tesis leídas y aprobadas por centro y departamento en el año 2014 CENTRO DEPARTAMENTO Nº DE TESIS

  12. Total..........................................................

    Gasoline and Diesel Fuel Update (EIA)

    1.4 0.4 0.5 1.0 1.2 1.4 2.1 1.3 Table HC5.2 Living Space Characteristics by Year of Construction, 2005 Living Space Characteristics 1970 to 1979 1980 to 1989 1990 to 1999 2000 to...

  13. Total..........................................................

    U.S. Energy Information Administration (EIA) Indexed Site

    Table HC7.7 Air-Conditioning Usage Indicators by Household Income, 2005 Below Poverty Line Eligible for Federal Assistance 1 2005 Household Income Housing Units (millions)...

  14. Total..........................................................

    U.S. Energy Information Administration (EIA) Indexed Site

    ... 65.9 3.9 15.1 15.6 11.1 7.0 5.2 8.0 Without a Heat Pump... 53.5 3.5 12.9 12.7 8.6 5.5 4.2 6.2 With a Heat...

  15. Total..........................................................

    Gasoline and Diesel Fuel Update (EIA)

    em... 65.9 51.7 43.9 2.5 0.7 1.6 3.1 Without a Heat Pump... 53.5 41.1 34.8 2.1 0.5 1.2 2.6 With a Heat...

  16. Total..........................................................

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... 65.9 11.0 16.5 13.5 8.7 16.1 6.4 17.2 Without a Heat Pump... 53.5 9.4 13.6 10.7 7.1 12.7 5.4 14.5 With a Heat...

  17. Total..........................................................

    U.S. Energy Information Administration (EIA) Indexed Site

    1.5 2.3 3.0 6.0 For Two Housing Units... 0.9 0.3 0.4 Q Q N Q 0.4 Heat Pump... 9.2 1.2 2.2 2.0 1.3 2.4 0.6 1.9...

  18. Total..........................................................

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... 65.9 3.7 2.6 6.1 6.8 11.2 13.2 13.9 8.2 Without a Heat Pump... 53.5 3.6 2.3 5.5 5.8 9.5 10.1 10.3 6.4 With a...

  19. Total..........................................................

    U.S. Energy Information Administration (EIA) Indexed Site

    tem... 65.9 14.1 3.6 1.5 2.1 6.4 0.6 Without a Heat Pump... 53.5 12.4 3.1 1.3 1.8 5.7 0.6 With a Heat...

  20. Total..........................................................

    U.S. Energy Information Administration (EIA) Indexed Site

    75.6 9.6 18.0 16.4 11.3 20.3 6.4 17.9 Most-Used Personal Computer Type of PC Desk-top Model... 58.6 7.6 14.2 13.1 9.2 14.6 5.0 14.5 Laptop...

  1. Total..........................................................

    U.S. Energy Information Administration (EIA) Indexed Site

    75.6 30.3 12.5 18.1 14.7 Most-Used Personal Computer Type of PC Desk-top Model... 58.6 22.9 9.8 14.1 11.9...

  2. Total..........................................................

    U.S. Energy Information Administration (EIA) Indexed Site

    ... 75.6 17.5 12.1 5.4 Most-Used Personal Computer Type of PC Desk-top Model... 58.6 14.1 10.0 4.0...

  3. Total..........................................................

    U.S. Energy Information Administration (EIA) Indexed Site

    75.6 13.7 17.5 26.6 17.8 Most-Used Personal Computer Type of PC Desk-top Model... 58.6 10.4 14.1 20.5 13.7...

  4. Total..........................................................

    U.S. Energy Information Administration (EIA) Indexed Site

    ... 75.6 26.6 14.5 4.1 7.9 Most-Used Personal Computer Type of PC Desk-top Model... 58.6 20.5 11.0 3.4 6.1...

  5. Total..........................................................

    Gasoline and Diesel Fuel Update (EIA)

    ... 0.7 Q Q Q Type of Monitor Used on Most-Used PC Desk-top CRT (Standard Monitor)... 45.0 11.4 8.1 3.3 Flat-panel...

  6. Total..........................................................

    Gasoline and Diesel Fuel Update (EIA)

    ... 0.7 Q Q Q 0.3 Type of Monitor Used on Most-Used PC Desk-top CRT (Standard Monitor)... 45.0 7.9 11.4 15.4 10.2 Flat-panel...

  7. Total..........................................................

    Gasoline and Diesel Fuel Update (EIA)

    ... 0.7 Q Q Q Q Type of Monitor Used on Most-Used PC Desk-top CRT (Standard Monitor)... 45.0 2.3 2.5 3.1 4.8...

  8. Total..........................................................

    Gasoline and Diesel Fuel Update (EIA)

    ... 0.7 Q Q Q Type of Monitor Used on Most-Used PC Desk-top CRT (Standard Monitor)... 45.0 7.9 5.6 2.4 Flat-panel...

  9. Total..........................................................

    Annual Energy Outlook [U.S. Energy Information Administration (EIA)]

    ... 0.7 Q Q Q Q Type of Monitor Used on Most-Used PC Desk-top CRT (Standard Monitor)... 45.0 15.4 7.9 2.8 4.8 Flat-panel...

  10. Total..........................................................

    Gasoline and Diesel Fuel Update (EIA)

    ... 0.7 0.3 Q Q Q Type of Monitor Used on Most-Used PC Desk-top CRT (Standard Monitor)... 45.0 17.7 7.5 10.2 9.6 Flat-panel...

  11. Total..........................................................

    U.S. Energy Information Administration (EIA) Indexed Site

    ... 75.6 17.8 5.3 12.5 Most-Used Personal Computer Type of PC Desk-top Model... 58.6 13.7 4.2 9.5 Laptop...

  12. Total..........................................................

    Annual Energy Outlook [U.S. Energy Information Administration (EIA)]

    ... 0.7 0.3 Q Q Type of Monitor Used on Most-Used PC Desk-top CRT (Standard Monitor)... 45.0 10.2 3.2 7.0 Flat-panel...

  13. Total..........................................................

    Annual Energy Outlook [U.S. Energy Information Administration (EIA)]

    ... 75.6 4.2 5.0 5.3 9.0 Most-Used Personal Computer Type of PC Desk-top Model... 58.6 3.2 3.9 4.0 6.7...

  14. Total..........................................................

    Annual Energy Outlook [U.S. Energy Information Administration (EIA)]

    1.2 0.5 0.9 3 or More... 0.6 Q Q Q Q Q N Q Plasma Television Sets... 3.6 0.6 0.8 0.5 0.6 1.2 0.3 0.9...

  15. Total..........................................................

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Q 0.4 3 or More Units... 5.4 0.3 Q Q Central Air-Conditioning Usage Air-Conditioned Floorspace (Square Feet)...

  16. Total..........................................................

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ... 1.9 1.1 Q Q 0.3 Q Do Not Use Central Air-Conditioning... 45.2 24.6 3.6 5.0 8.8 3.2 Use a Programmable...

  17. Total..........................................................

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    3.3 2.9 Q Q Q N For Two Housing Units... 1.4 Q Q 0.5 0.8 N Central Warm-Air Furnace... 2.8 2.4 Q Q Q 0.2 Other...

  18. Total..........................................................

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    3 or More Units... 5.4 2.4 1.4 0.7 0.9 Central Air-Conditioning Usage Air-Conditioned Floorspace (Square Feet)...

  19. Total..........................................................

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    s... 58.2 9.2 4.9 7.8 7.1 8.8 8.4 7.8 4.2 Central Warm-Air Furnace... 44.7 5.2 3.1 5.6 5.2 7.1 7.4 7.3 3.9 For...

  20. Total..........................................................

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    3 or More Units... 5.4 2.3 1.7 0.6 Central Air-Conditioning Usage Air-Conditioned Floorspace (Square Feet)...

  1. Total..........................................................

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    3 or More Units... 5.4 2.1 0.9 0.2 1.0 Central Air-Conditioning Usage Air-Conditioned Floorspace (Square Feet)...

  2. Total..........................................................

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    38.9 12.9 Have Equipment But Do Not Use it... 1.9 0.3 Q 0.5 1.0 Air-Conditioning Equipment 1, 2 Central System......

  3. Total..........................................................

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    0.3 3 or More Units... 5.4 0.7 0.5 Q Central Air-Conditioning Usage Air-Conditioned Floorspace (Square Feet)...

  4. Total..........................................................

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    3 or More Units... 5.4 2.3 0.7 2.1 0.3 Central Air-Conditioning Usage Air-Conditioned Floorspace (Square Feet)...

  5. Total..............................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.4 12.55.6 111.1 86.6

  6. Total................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.4 12.55.6 111.1

  7. Total........................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.4 12.55.6 111.1 111.1

  8. Total..........................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.4 12.55.6 111.1

  9. Total...........................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.4 12.55.6 111.1Q

  10. Total...........................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.4 12.55.6 111.1QQ

  11. Total...........................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.4 12.55.6 111.1QQ14.7

  12. Total...........................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.4 12.55.6

  13. Total............................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.4

  14. Total............................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.4

  15. Total.............................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8 20.6 13.1

  16. Total..............................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8 20.6

  17. Total..............................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8 20.6Do Not

  18. Total...............................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8 20.6Do

  19. Total...............................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8 20.6Do0.7

  20. Total...............................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8

  1. Total...............................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8Do Not Have

  2. Total...............................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8Do Not

  3. Total................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8Do Not

  4. Total.................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8Do Not49.2

  5. Total.................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8Do

  6. Total.................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8Do26.7 28.8

  7. Total..................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8Do26.7

  8. Total..................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8Do26.733.0

  9. Total..................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7 28.8Do26.733.0.

  10. Total...................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.7

  11. Total...................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.715.2 7.8 1.0 1.2

  12. Total...................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.715.2 7.8 1.0

  13. Total...................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.715.2 7.8 1.0Type

  14. Total...................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.715.2 7.8

  15. Total....................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.715.2 7.814.7 7.4

  16. Total.......................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.715.2 7.814.7

  17. Total.......................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.715.2 7.814.75.6

  18. Total.......................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.715.2

  19. Total........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.715.225.6 40.7

  20. Total........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.715.225.6

  1. Total........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.715.225.65.6 17.7

  2. Total........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.715.225.65.6

  3. Total........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7 7.426.715.225.65.64.2

  4. Total........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.7

  5. Total........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0 22.7 22.3 Do

  6. Total.........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0 22.7 22.3

  7. Total..........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0 22.7 22.325.6

  8. Total..........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0 22.7 22.325.6.

  9. Total..........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0 22.7

  10. Total..........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0 22.70.7 21.7

  11. Total..........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0 22.70.7 21.74.2

  12. Total..........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0 22.70.7

  13. Total..........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0 22.70.77.1 19.0

  14. Total...........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0 22.70.77.1

  15. Total...........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0 22.70.77.15.6

  16. Total...........................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0

  17. Total.............................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0Do Not Have

  18. Total.............................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0Do Not

  19. Total.............................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0Do NotCooking

  20. Total.............................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0Do NotCookingDo

  1. Total.............................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0Do

  2. Total.............................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0DoCooking

  3. Total.............................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0DoCookingDo Not

  4. Total.............................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0DoCookingDo

  5. Total..............................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 19.0DoCookingDo20.6

  6. Total..............................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1

  7. Total..............................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 111.1 7.1 7.0 8.0

  8. Total..............................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 111.1 7.1 7.0 8.07.1

  9. Total.................................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 111.1 7.1 7.0

  10. Total.................................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 111.1 7.1 7.07.1 7.0

  11. Total....................................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 111.1 7.1 7.07.1

  12. Total....................................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 111.1 7.1 7.07.15.6

  13. Total....................................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 111.1 7.1

  14. Total....................................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 111.1 7.1Personal

  15. Total....................................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 111.1 7.1Personal4.2

  16. Total....................................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 111.1

  17. Total....................................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 111.1 111.1 47.1

  18. Total.........................................................................................

    Gasoline and Diesel Fuel Update (EIA)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of Natural GasAdjustments (Billion Cubic Feet) Wyoming963 1.969 1.979 1.988Prices,Flight.... 111.1 14.77.1 111.1 111.1

  19. Total

    U.S. Energy Information Administration (EIA) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home PageMonthly","10/2015"4,"Ames5 Tables July 1996 Energy Information Administration Office of Coal, Nuclear,DecadeYearbyWithdrawalsHome6,672(MillionFeet) Oil4)5,Product:

  20. Total

    U.S. Energy Information Administration (EIA) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home PageMonthly","10/2015"4,"Ames5 Tables July 1996 Energy Information Administration Office of Coal, Nuclear,DecadeYearbyWithdrawalsHome6,672(MillionFeet)