Powered by Deep Web Technologies
Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


1

Current Test Procedure Waivers  

Energy.gov (U.S. Department of Energy (DOE))

The U.S. Department of Energy's (DOE) regulations for covered products permit a person to seek a waiver, or an interim waiver, from the test procedure requirements for covered appliances and...

2

Rough Ride Test Procedure  

NLE Websites -- All DOE Office Websites (Extended Search)

NTP005 NTP005 Revision 2 Effective December 1, 2004 Electric Vehicle Rough Road Course Test Prepared by Electric Transportation Applications Prepared by: _______________________________ Date:__________ Ryan Harkins Approved by: _________________________________________________ Date: _______________ Donald B. Karner ©2004 Electric Transportation Applications All Rights Reserved Procedure ETA-NTP005 Revision 2 2 TABLE OF CONTENTS 1.0 Objectives 3 2.0 Purpose 3 3.0 Documentation 3 4.0 Initial Conditions and Prerequisites 4 5.0 Testing Activity Requirements 6 6.0 Glossary 12 7.0 References 14 Appendices Appendix A - Electric Vehicle Rough Road Test Data Sheet 15

3

Optimum Statistical Test Procedure  

E-Print Network (OSTI)

In this paper we obtain a test which minimizes the sum of the two error probabilities irrespective of whether $\\sigma^2$ is known or unknown.

Rajesh Singh; Jayant Singh; Florentin Smarandache

2009-04-10T23:59:59.000Z

4

MITG test procedure and results  

DOE Green Energy (OSTI)

Elements and modules for Radioisotope Thermoelectric Generator have been performance tested since the inception of the RTG program. These test articles seldom resembled flight hardware and often lacked adequate diagnostic instrumentation. Because of this, performance problems were not identified in the early stage of program development. The lack of test data in an unexpected area often hampered the development of a problem solution. A procedure for conducting the MITG Test was developed in an effort to obtain data in a systematic, unambiguous manner. This procedure required the development of extensive data acquisition software and test automation. The development of a facility to implement the test procedure, the facility hardware and software requirements, and the results of the MITG testing are the subject of this paper.

Eck, M.B.; Mukunda, M.

1983-01-01T23:59:59.000Z

5

EV America Skid Test Procedure  

NLE Websites -- All DOE Office Websites (Extended Search)

6 6 Revision 2 Effective October 1, 2007 Braking Test Prepared by Electric Transportation Applications Prepared by: _______________________________ Date: _________ Roberta Brayer Approved by: _________________________________________________ Date: _______________ Donald Karner Procedure ETA-HTP06 Revision 2 i TABLE OF CONTENTS 1. Objectives 1 2. Purpose 1 3. Documentation 1 4. Initial Conditions and Prerequisites 1 5. Testing Activity Requirements 3 5.3 Dry Controlled Test 4 6. Glossary 5 7. References 7 Appendices Appendix A - Handling Pad Test Data Sheet 8

6

Building Technologies Office: Current Test Procedure Waivers  

NLE Websites -- All DOE Office Websites (Extended Search)

Test Procedure Test Procedure Waivers to someone by E-mail Share Building Technologies Office: Current Test Procedure Waivers on Facebook Tweet about Building Technologies Office: Current Test Procedure Waivers on Twitter Bookmark Building Technologies Office: Current Test Procedure Waivers on Google Bookmark Building Technologies Office: Current Test Procedure Waivers on Delicious Rank Building Technologies Office: Current Test Procedure Waivers on Digg Find More places to share Building Technologies Office: Current Test Procedure Waivers on AddThis.com... About Standards & Test Procedures Implementation, Certification & Enforcement Rulemakings & Notices Current Rulemakings & Notices Test Procedure Waivers Recent Federal Register Notices How to Participate or Comment

7

Inspection system performance test procedure  

SciTech Connect

This procedure establishes requirements to administer a performance demonstration test. The test is to demonstrate that the double-shell tank inspection system (DSTIS) supplied by the contractor performs in accordance with the WHC-S-4108, Double-Shell Tank Ultrasonic Inspection Performance Specification, Rev. 2-A, January, 1995. The inspection system is intended to provide ultrasonic (UT) and visual data to determine integrity of the Westinghouse Hanford Company (WHC) site underground waste tanks. The robotic inspection system consists of the following major sub-systems (modules) and components: Mobile control center; Deployment module; Cable management assembly; Robot mechanism; Ultrasonic testing system; Visual testing system; Pneumatic system; Electrical system; and Control system.

Jensen, C.E.

1995-01-17T23:59:59.000Z

8

EV America Skid Test Procedure  

NLE Websites -- All DOE Office Websites (Extended Search)

4 4 Revision 1 Effective June 2008 Electromagnetic Interference and Susceptibility Test Prepared by Electric Transportation Applications Prepared by: _______________________________ Date:__________ Garrett P. Beauregard Approved by: ______________________________________________ Date: _______________ Donald B. Karner Procedure ETA-GTP004 Revision 1 2 Table of Contents 1 Objective ..................................................................................................................... 3 2 Purpose........................................................................................................................ 3 3 Documentation............................................................................................................

9

EV America Skid Test Procedure  

NLE Websites -- All DOE Office Websites (Extended Search)

3 3 Revision 1 Effective June 2008 Battery Capacity and Depth of Discharge Test Prepared by Electric Transportation Applications Prepared by: _______________________________ Date:__________ Garrett P. Beauregard Approved by: ______________________________________________ Date: _______________ Donald B. Karner Procedure ETA-GTP003 Revision 1 2 Table of Contents 1 Objective ..................................................................................................................... 3 2 Purpose........................................................................................................................ 3 3 Documentation............................................................................................................

10

EV America Skid Test Procedure  

NLE Websites -- All DOE Office Websites (Extended Search)

2 2 Revision 1 Effective June 2008 Traction System Test Prepared by Electric Transportation Applications Prepared by: _______________________________ Date:__________ Garrett P. Beauregard Approved by: ______________________________________________ Date: _______________ Donald B. Karner Procedure ETA-GTP002 Revision 1 2 Table of Contents 1 Objective ..................................................................................................................... 3 2 Purpose........................................................................................................................ 3 3 Documentation............................................................................................................

11

Building Technologies Office: Standards and Test Procedures  

NLE Websites -- All DOE Office Websites (Extended Search)

Standards and Test Standards and Test Procedures to someone by E-mail Share Building Technologies Office: Standards and Test Procedures on Facebook Tweet about Building Technologies Office: Standards and Test Procedures on Twitter Bookmark Building Technologies Office: Standards and Test Procedures on Google Bookmark Building Technologies Office: Standards and Test Procedures on Delicious Rank Building Technologies Office: Standards and Test Procedures on Digg Find More places to share Building Technologies Office: Standards and Test Procedures on AddThis.com... About Standards & Test Procedures Implementation, Certification & Enforcement Rulemakings & Notices Further Guidance ENERGY STAR® Popular Links Success Stories Previous Next Lighten Energy Loads with System Design. Learn More.

12

Nevada Test Site FFCA Consent Order, March 27, 1996 Summary  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Test Site Federal Facility Compliance Act Test Site Federal Facility Compliance Act Consent Order, March 27, 1996 State Nevada Agreement Type Consent Order Legal Driver(s) FFCAct Scope Summary Enforce the STP and establish procedures for reviewing schedules, deleting waste streams, and administrative procedures Parties DOE; Nevada Division of Environmental Protection Date 3/27/1996 SCOPE * Require DOE to achieve compliance with the requirements of the FFCAct through the STP which contains schedules and applicable strategies for achieving compliance with the applicable LDR standards. * Establish procedures for reviewing schedules, deleting waste streams, and administrative procedures. * Establish enforceable schedules and milestones applicable to this Order. ESTABLISHING MILESTONES *

13

Building Technologies Office: Test Procedure Development and...  

NLE Websites -- All DOE Office Websites (Extended Search)

Test Procedure Development and Revision to someone by E-mail Share Building Technologies Office: Test Procedure Development and Revision on Facebook Tweet about Building...

14

Building Technologies Office: Test Procedure Waivers  

NLE Websites -- All DOE Office Websites (Extended Search)

Waivers on Twitter Bookmark Building Technologies Office: Test Procedure Waivers on Google Bookmark Building Technologies Office: Test Procedure Waivers on Delicious Rank...

15

Test Procedure Waivers | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Appliance & Equipment Standards » Rulemakings & Notices » Test Appliance & Equipment Standards » Rulemakings & Notices » Test Procedure Waivers Test Procedure Waivers Products covered by standards change as manufacturers add new features to their products and update designs in order to compete for consumers. Innovation and product development occasionally causes products to change in ways that either (1) make the results of a test procedure unrepresentative of actual energy use or efficiency, or (2) make it impossible to test in accordance with the relevant test procedure. For this reason, the Department of Energy (DOE) considers petitions for waivers from test procedures under certain circumstances. In general, any interested party-typically a manufacturer-may submit a petition for a test procedure waiver for a basic model of a covered product

16

A general design for energy test procedures  

SciTech Connect

Appliances are increasingly controlled by microprocessors. Unfortunately, energy test procedures have not been modified to capture the positive and negative contributions of the microprocessor to the appliance's energy use. A new test procedure is described which captures both the mechanical and logical features present in many new appliances. We developed an energy test procedure for refrigerators that incorporates most aspects of the proposed new approach. Some of the strengths and weaknesses of the new test are described.

Meier, Alan

2000-06-15T23:59:59.000Z

17

Nevada Test Site Environmental Report 2007 Summary  

SciTech Connect

The U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO) directs the management and operation of the Nevada Test Site (NTS). The NTS is the nation's historical testing site for nuclear weapons from 1951 through 1992 and is currently the nation's unique site for ongoing national-security related missions and high-risk operations. NNSA/NSO strives to provide to the public an understanding of the current activities on the NTS, including environmental monitoring and compliance activities aimed at protecting the public and the environment from radiation hazards and from nonradiological impacts. This document is a summary of the Nevada Test Site Environmental Report (NTSER) for calendar year 2007 (see attached compact disc on inside back cover). The NTSER is a comprehensive report of environmental activities performed at the NTS and offsite facilities over the previous calendar year. It is prepared annually to meet the requirements and guidelines of the U.S. Department of Energy (DOE) and the information needs of NNSA/NSO stakeholders. To provide an abbreviated and more readable version of the NTSER, this summary report is produced. This summary does not include detailed data tables, monitoring methods or design, a description of the NTS environment, or a discussion of all environmental program activities performed throughout the year. The reader may obtain a hard copy of the full NTSER as directed on the inside front cover of this summary report.

Cathy Wills

2008-09-01T23:59:59.000Z

18

Building Technologies Office: Current Test Procedure Waivers  

NLE Websites -- All DOE Office Websites (Extended Search)

Test Procedure Waivers Test Procedure Waivers The U.S. Department of Energy's (DOE) regulations for covered products permit a person to seek a waiver, or an interim waiver, from the test procedure requirements for covered appliances and commercial equipment if certain criteria are satisfied. Regulations applicable to test procedure waivers for appliances can be found at 10 CFR 430.27; those applicable to test procedure waivers for commercial equipment are at 10 CFR 431.401. This table lists all waivers to test procedures that DOE has granted and that are still in effect. The links to the notices provide access to the dockets in Regulations.gov, which contain all notices and public comments. For more information, please email: AS_Waiver_Requests@ee.doe.gov The links to the notices provides access to the docket in regulations.gov, which contains all notices and public comments.

19

EV America Skid Test Procedure  

NLE Websites -- All DOE Office Websites (Extended Search)

6 Revision 3 Effective February 1, 2008 Braking Test Prepared by Electric Transportation Applications Prepared by: Date: Derek Peterson...

20

Standards and Test Procedures | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Standards and Test Procedures Standards and Test Procedures Standards and Test Procedures The Department of Energy (DOE) establishes energy efficiency standards for certain appliances and equipment, and currently covers more than 50 different products. Authority to undertake this effort was granted by Congress, and DOE follows a four phase process when reviewing existing and developing new standards. Each Product page provides information on recent updates, current standards and test procedures, waivers, exceptions, and exemptions, statutory authority, and historical information. For information on current Rulemakings, visit Current Rulemaking and Notices. Consumer Products Battery Chargers and External Power Supplies Ceiling Fans Central Air Conditioners and Heat Pumps Clothes Dryers

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


21

Building Technologies Office: Standards and Test Procedures  

NLE Websites -- All DOE Office Websites (Extended Search)

icon Public Meetings & Comment Deadlines Newsletter Recent Federal Register Notices Standards and Test Procedures The Department of Energy (DOE) establishes energy efficiency...

22

Void fraction instrument acceptance test procedure  

DOE Green Energy (OSTI)

This acceptance test procedure (ATP) was written to test the void fraction instrument (VFI) and verify that the unit is ready for field service. The procedure verifies that the mechanical and electrical features (not specifically addressed in the software ATP) and software alarms are operating as designed.

Pearce, K.L.

1994-09-15T23:59:59.000Z

23

Nitrogen chiller acceptance test procedure  

SciTech Connect

This document includes the inspection and testing requirements for the Nitrogen Chiller unit. The Chiller will support the Rotary Mode core Sampling System during the summer. The Chiller cools the Nitrogen Purge Gas that is used when drilling in tank wastes to cool the drill bit.

Kostelnik, A.J.

1995-03-07T23:59:59.000Z

24

Workshop on Test Procedures for Materials for Hydrogen ...  

Science Conference Proceedings (OSTI)

Test Procedures for Hydrogen Pipelines. ... The NIST Workshop on Materials Test Procedures for Hydrogen Pipelines Proceedings is now available. ...

25

International Comparison of Energy Efficiency Criteria and Test Procedures  

NLE Websites -- All DOE Office Websites (Extended Search)

International Comparison of Energy Efficiency Criteria and Test Procedures International Comparison of Energy Efficiency Criteria and Test Procedures in Standards and Labeling Programs for Computer Monitors and Commercial Gas Stoves Title International Comparison of Energy Efficiency Criteria and Test Procedures in Standards and Labeling Programs for Computer Monitors and Commercial Gas Stoves Publication Type Report LBNL Report Number LBNL-6506E Year of Publication 2013 Authors Khanna, Nina, Nan Zhou, David Fridley, and John Romankiewicz Date Published 12/2013 Publisher Lawrence Berkeley National Laboratory Keywords Standards and labeling Abstract This report presents a technical review and comparative analysis of existing and/or proposed international mandatory energy performance standards, and voluntary and mandatory energy efficiency labels and test procedures for two products - computer monitors and commercial gas stoves - being considered for revised and new minimum energy performance standards (MEPS) in China. An overview of the scope of international programs, energy efficiency and other energy-related requirements, description and detailed summary table of criteria and procedures in major test standards are presented. In addition, an estimation of potential energy savings if China were to adopt revised MEPS comparable to international levels is provided for computer monitors. A proposed methodology for estimating potential energy savings based on the European Union experience is provided for commercial gas stoves in the absence of available sales or energy consumption data.

26

AZ-101 Mixer Pump Test Qualification Test Procedures (QTP)  

SciTech Connect

Describes the Qualification test procedure for the AZ-101 Mixer Pump Data Acquisition System (DAS). The purpose of this Qualification Test Procedure (QTP) is to confirm that the AZ-101 Mixer Pump System has been properly programmed and hardware configured correctly. This QTP will test the software setpoints for the alarms and also check the wiring configuration from the SIMcart to the HMI. An Acceptance Test Procedure (ATP), similar to this QTP will be performed to test field devices and connections from the field.

THOMAS, W.K.

2000-01-10T23:59:59.000Z

27

Biomonitoring test procedures and biological criteria  

SciTech Connect

The Water Environment Federation recently issued a special publication, Biomonitoring in the Water Environment. In this paper, the authors highlight the contents of the chapter 3, Biomonitoring Test Procedures, identify current trends in test procedures and introduce the concept of biological criteria (biocriteria). The book chapter (and this paper) focuses on freshwater and marine chronic and acute toxicity tests used in the National Pollutant Discharge Elimination System (NPDES) permits program to identify effluents and receiving waters containing toxic materials in acutely or chronically toxic concentrations. The two major categories of toxicity tests include acute tests and chronic tests. The USEPA chronic tests required in NPDEs permits have been shortened to 7 days by focusing on the most sensitive life-cycle stages; these tests are often referred to as short-term chronic tests. The type of test(s) required depend on NPDES permit requirements, objectives of the test, available resources, requirements of the test organisms, and effluent characteristics such as variability in flow or toxicity. The permit writer will determine the requirements for toxicity test(s) by considering such factors as dilution, effluent variability, and exposure variability. Whether the required test is acute or chronic, the objective of the test is to estimate the safe or no effect concentration which is defined as the concentration which will permit normal propagation of fish and other aquatic life in the receiving waters. In this paper, the authors review the types of toxicity tests, the commonly used test organisms, and the uses of toxicity test data. In addition, they briefly describe research on new methods and the use of biological criteria.

Kszos, L.A. [Oak Ridge National Lab., TN (United States); Lipschultz, M.J. [City of Las Vegas, NV (United States); Foster, W.E. [Saint Mary`s Coll., Winona, MN (United States)

1997-10-01T23:59:59.000Z

28

Building Technologies Office: ENERGY STAR Test Procedures and...  

NLE Websites -- All DOE Office Websites (Extended Search)

Test Procedures and Verification to someone by E-mail Share Building Technologies Office: ENERGY STAR Test Procedures and Verification on Facebook Tweet about Building Technologies...

29

Meeting Concerning Potential Test Procedures and Energy Conservation...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Concerning Potential Test Procedures and Energy Conservation Standards for Set-Top Boxes and Network Equipment Meeting Concerning Potential Test Procedures and Energy Conservation...

30

Residential photovoltaic power conditioner subsystem test procedures  

DOE Green Energy (OSTI)

The inspections to be made, the conditions for measurement, the variables to be measured and the analyses to be performed in order to characterize the operation of a power-conditioning subsystem (PCS) are described. Of primary concern is the small, utility-interactive PCS in the 2- to 10-kW power range for use in a residential photovoltaic (PV) system feeding a single-phase 120/240-volt line. The procedure is broken down into four main tasks: analysis of the design, tests under nominal conditions, tests under extreme conditions, and accelerated environmental stress tests. The results of these tests will provide an objective assessment of PCS performance under the full range of conditions likely to be encountered in actual applications.

Cox, III, C. H.

1982-02-01T23:59:59.000Z

31

SOLAR HEAT GAIN THROUGH FENESTRATION SYSTEMS CONTAINING SHADING: SUMMARY OF PROCEDURES FOR  

E-Print Network (OSTI)

SOLAR HEAT GAIN THROUGH FENESTRATION SYSTEMS CONTAINING SHADING: SUMMARY OF PROCEDURES that with a drastic simplifying assumption these methods can be used to calculate system solar-optical properties and solar heat gain coefficients for arbitrary glazing systems, while requiring limited data about

32

Test Procedure Development and Revision | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Test Procedure Development and Revision Test Procedure Development and Revision Test Procedure Development and Revision Most energy conservation standards rulemakings are accompanied by a concurrent test procedure rulemaking. Test procedures detail the protocols that manufacturers must follow when testing their products for compliance with Department of Energy (DOE) standards. DOE also uses the test procedures to determine compliance with the applicable standards in any verification or enforcement testing. The procedures specify how to measure and calculate the energy efficiency and/or energy use of each appliance. Test procedures also specify how to calculate an estimate of an appliance's annual operating cost, which is used on the EnergyGuide label as required by the Federal Trade Commission.

33

Alternative Fuels Data Center: Fuel Economy Test Procedures and Labeling  

Alternative Fuels and Advanced Vehicles Data Center (EERE)

Fuel Economy Test Fuel Economy Test Procedures and Labeling to someone by E-mail Share Alternative Fuels Data Center: Fuel Economy Test Procedures and Labeling on Facebook Tweet about Alternative Fuels Data Center: Fuel Economy Test Procedures and Labeling on Twitter Bookmark Alternative Fuels Data Center: Fuel Economy Test Procedures and Labeling on Google Bookmark Alternative Fuels Data Center: Fuel Economy Test Procedures and Labeling on Delicious Rank Alternative Fuels Data Center: Fuel Economy Test Procedures and Labeling on Digg Find More places to share Alternative Fuels Data Center: Fuel Economy Test Procedures and Labeling on AddThis.com... More in this section... Federal State Advanced Search All Laws & Incentives Sorted by Type Fuel Economy Test Procedures and Labeling

34

WRAP Trupact Loading System Operational Test Procedure  

Science Conference Proceedings (OSTI)

This procedure has been prepared to verify the TRUPACT System (TS) operates in accordance with system design and specifications.

DOSRAMOS, E.V.

1999-09-01T23:59:59.000Z

35

Alternative Fuels Data Center: Biodiesel Quality Testing Procedures  

Alternative Fuels and Advanced Vehicles Data Center (EERE)

Biodiesel Quality Biodiesel Quality Testing Procedures to someone by E-mail Share Alternative Fuels Data Center: Biodiesel Quality Testing Procedures on Facebook Tweet about Alternative Fuels Data Center: Biodiesel Quality Testing Procedures on Twitter Bookmark Alternative Fuels Data Center: Biodiesel Quality Testing Procedures on Google Bookmark Alternative Fuels Data Center: Biodiesel Quality Testing Procedures on Delicious Rank Alternative Fuels Data Center: Biodiesel Quality Testing Procedures on Digg Find More places to share Alternative Fuels Data Center: Biodiesel Quality Testing Procedures on AddThis.com... More in this section... Federal State Advanced Search All Laws & Incentives Sorted by Type Biodiesel Quality Testing Procedures Each biodiesel or other renewable diesel producer, distributor, or importer

36

Independent Oversight Inspection, Nevada Test Site, Summary Report -  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Oversight Inspection, Nevada Test Site, Summary Report Oversight Inspection, Nevada Test Site, Summary Report - October 2002 Independent Oversight Inspection, Nevada Test Site, Summary Report - October 2002 October 2002 Inspection of Environment, Safety, and Health and Emergency Management at the Nevada Test Site The Secretary of Energy's Office of Independent Oversight and Performance Assurance (OA) conducted an inspection of environment, safety, and health (ES&H) and emergency management programs at the National Nuclear Security Administration (NNSA) Nevada Test Site (NTS) in September and October 2002. The inspection was performed as a joint effort by the OA Office of Environment, Safety and Health Evaluations and the Office of Emergency Management Oversight. Overall, safety management at NTS has substantially improved in the past

37

Common Information Model Meter Disconnect/Reconnect Interoperability Test Procedure  

Science Conference Proceedings (OSTI)

The Common Information Model (CIM) Disconnect/Reconnect Interoperability Test Procedure is one in a series of EPRI Interoperability Test Procedures (ETIPs) created by EPRI whose purpose is to thoroughly document the actors, interfaces, and test steps for the interoperability testing of specific parts of the International Electrotechnical Commission (IEC) Common Information Model (CIM) standard. The Test Procedures are initially being used for EPRI demonstration tests and are intended, over time, to form ...

2011-12-21T23:59:59.000Z

38

Common Information Model Meter Outage Nominal Interoperability Test Procedure  

Science Conference Proceedings (OSTI)

The CIM Meter Outage Nominal Interoperability Test Procedure is one in a series of EPRI CIM Interoperability Test Procedures (ETIPs) created by EPRI whose purpose is to thoroughly document the actors, interfaces, and test steps for the interoperability testing of specific parts of the International Electrotechnical Commission (IEC) Common Information Model (CIM) standard. The Test Procedures are initially being used for EPRI demonstration tests and are intended, over time, to form the basis of a set of C...

2011-12-16T23:59:59.000Z

39

Common Information Model On Demand Meter Read Interoperability Test Procedure  

Science Conference Proceedings (OSTI)

The Common Information Model (CIM) On Demand Meter Read Interoperability Test Procedure is one in a series of EPRI Interoperability Test Procedures (ETIPs) created by EPRI whose purpose is to thoroughly document the actors, interfaces, and test steps for the interoperability testing of specific parts of the International Electrotechnical Commission (IEC) Common Information Model (CIM) standard. The Test Procedures are initially being used for EPRI demonstration tests and are intended, over time, to form ...

2011-12-14T23:59:59.000Z

40

Common Information Model Meter Tamper Detection Interoperability Test Procedure  

Science Conference Proceedings (OSTI)

The Common Information Model (CIM) Meter Tamper Detection Interoperability Test Procedure is one in a series of EPRI Interoperability Test Procedures (ETIPs) created by EPRI whose purpose is to thoroughly document the actors, interfaces, and test steps for the interoperability testing of specific parts of the International Electrotechnical Commission (IEC) Common Information Model (CIM) standard. The Test Procedures are initially being used for EPRI demonstration tests and are intended, over time, to for...

2011-11-30T23:59:59.000Z

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


41

MIT validation probe acceptance test procedure  

SciTech Connect

As part of the Multi-Functional Instrument Trees (MITs) a Validation Probe is being fabricated by Los Alamos National Laboratories (LANL). The Validation Probe assembly is equipped with a Winch, depth counter, and a Resistance Temperature Detector (RTD) which will render a means for verifying the temperature readings of which will render a means for verifying the temperature readings of the MIT thermocouples. The purpose of this Acceptance Test Procedure (ATP) is to provide verification that the Validation Probe functions properly and accordingly to LANL design and specification. This ATP will be used for all Validation Probes procured from LANL. The ATP consists of a receiving inspection, RTD ambient temperature; RTD electrical failure, RTD insulation resistance, and accurate depth counter operation inspections. The Validation Probe is composed of an intank probe, a cable and winching system, and a riser extension (probe guide) which bolts onto the MIT. The validation`s thermal sensor is an RTD that is housed in a 0.062 inch diameter, magnesium oxide fill, 316 stainless steel tube. The sheath configuration provides a means for spring loading the sensor firmly against the validation tube`s inner wall. A 45 pound cylindrical body is connected above the sheath and is used as a force to lower the probe into the tank. This cylindrical body also provides the means to interconnect both electrically and mechanically to the winch system which lowers the probe to a specified location within the validation tube located in the tank.

Escamilla, S.A.

1994-08-23T23:59:59.000Z

42

702AZ aging waste ventilation facility year 2000 test procedure  

SciTech Connect

This test procedure was developed to determine if the 702AZ Tank Ventilation Facility system is Year 2000 Compliant. The procedure provides detailed instructions for performing the operations necessary and documenting the results. This verification procedure will document that the 702AZ Facility Systems are year 2000 compliant and will correctly meet the criteria established in this procedure.

Winkelman, W.D.

1998-07-22T23:59:59.000Z

43

Nevada Test Site Environmental Report 2008 Summary  

SciTech Connect

The Nevada Test Site Environmental Report (NTSER) 2008 was prepared to meet the information needs of the public and the requirements and guidelines of the U.S. Department of Energy (DOE) for annual site environmental reports. It was prepared by National Security Technologies, LLC (NSTec), for the U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO). This and previous years NTSERs are posted on the NNSA/NSO website at http://www.nv.doe.gov/library/publications/aser.aspx.

Cathy A. Wills

2009-09-01T23:59:59.000Z

44

Tonopah Test Range 2030 Meeting Summary Report  

SciTech Connect

Corrective Action Sites (CASs) and Corrective Action Units (CAUs) at the Tonopah Test Range (TTR) may be placed into three categories: Closed, Closed in Place, or Closure in Progress. CASs and CAUs where contaminants were either not detected or were cleaned up to within regulatory action levels are summarized. CASs and CAUs where contaminants and/or waste have been closed in place are summarized. There is also a table that summarizes the contaminant that has been closed at each site, if land-use restrictions are present, and if post-closure inspections are required.

NSTec Environmental Restoration

2009-04-01T23:59:59.000Z

45

Definitions common to all certification and test procedures are in: D-200 Definitions for Certification Procedures and Test Procedures for Vapor Recovery Systems  

E-Print Network (OSTI)

For the purpose of this procedure, the term "ARB " refers to the State of California Air Resources Board, and the term "ARB Executive Officer " refers to the Executive Officer of the ARB or his or her authorized representative or designate. 1.1 General Applicability This procedure applies to the determination of the one minute static pressure performance of a vapor recovery system of a cargo tank by fluid mechanical principles. This procedure applies to any vapor emissions associated with the dispensing of any fluid, although it is written to reflect application to the hydrocarbon vapors associated with the dispensing of gasoline. 1.2 Determinations of Compliance and Violation Determinations of certain modes of compliance with and violation of certification specifications is outlined in 9. 1.3 Modifications Modification of this procedure may be necessary for vapors and fluids other than the hydrocarbon vapors associated with the dispensing of gasoline. Any modification of this method shall be subject to approval by the ARB Executive Officer. 2 PRINCIPLE AND SUMMARY OF TEST PROCEDURE Upon completion of loading operations at the bulk gasoline distribution facility, the gasoline cargo tank is pressurized, with nitrogen, to 18 inches water column. By using the total cargo California Air Resources Board March 17, 1999 TP-204.2, Page 1tank shell capacity, post-loading headspace volume, and the Ideal Gas Law, a one-minute maximum allowable pressure decay is calculated. The pressure decay is monitored for one minute and compliance is determined by comparison with the maximum allowable calculated value. The leak rate through the cargo tank internal vapor vent valve is similarly obtained. 3

unknown authors

1996-01-01T23:59:59.000Z

46

DOE Issues Final Appliance Test Procedure Rule | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Appliance Test Procedure Rule Appliance Test Procedure Rule DOE Issues Final Appliance Test Procedure Rule December 8, 2006 - 9:46am Addthis WASHINGTON, DC - The U.S. Department of Energy (DOE) today announced a final rule establishing new test procedures and related definitions to determine the energy efficiency of certain residential appliances and commercial equipment. The rulemaking clarifies and codifies the test procedures mandated by the Energy Policy Act (EPAct) of 2005. "These new test procedures are the foundation for standards that will help bring more energy efficient options to the marketplace and result in energy savings for all Americans," said DOE Assistant Secretary for Energy Efficiency and Renewable Energy Andy Karsner. The final rulemaking, which appears in today's Federal Register, will

47

DOE Launches Public Test Procedure Guidance Website | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Launches Public Test Procedure Guidance Website Launches Public Test Procedure Guidance Website DOE Launches Public Test Procedure Guidance Website July 22, 2010 - 4:14pm Addthis The Department of Energy this week launched a new online database offering guidance on the Department's test procedures for appliances and commercial equipment. The new database will provide a publicly accessible forum for anyone with questions about -- or needing clarification of -- DOE's test procedures. This new online resource will also ensure that all manufacturers and members of the public are equally and immediately aware of the Department's interpretations of its test procedures. The database is available here. The database -- which is searchable by product category -- is designed to enable manufacturers, trade associations, and all other interested members

48

DOE Launches Public Test Procedure Guidance Website | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Public Test Procedure Guidance Website Public Test Procedure Guidance Website DOE Launches Public Test Procedure Guidance Website July 22, 2010 - 4:14pm Addthis The Department of Energy this week launched a new online database offering guidance on the Department's test procedures for appliances and commercial equipment. The new database will provide a publicly accessible forum for anyone with questions about -- or needing clarification of -- DOE's test procedures. This new online resource will also ensure that all manufacturers and members of the public are equally and immediately aware of the Department's interpretations of its test procedures. The database is available here. The database -- which is searchable by product category -- is designed to enable manufacturers, trade associations, and all other interested members

49

NFRC Test Procedure for Measuring the Steady-State  

E-Print Network (OSTI)

NFRC Test Procedure for Measuring the Steady-State Thermal Transmittance of Fenestration Systems Adopted: March 15, 1991 Revised: April 17, 1997 Prepared by: Test Laboratory Task Group U Test Procedure for Measuring the Steady-State Thermal Transmittance of Fenestration Systems Adopted

Massachusetts at Amherst, University of

50

Light duty utility arm equipment qualification test procedure  

SciTech Connect

The Equipment Qualification Test described in this test procedure document is the acceptance test procedure (ATP) for the LDUA Baseline System. It verifies that the equipment is complete and in working order, and demonstrates its readiness for being deployed into an actual underground storage tank.

Kiebel, G.R., Westinghouse Hanford

1996-07-22T23:59:59.000Z

51

Summary description of the Fast Flux Test Facility  

SciTech Connect

This document has been compiled and issued to provide an illustrated engineering summary description of the FFTF. The document is limited to a description of the plant and its functions, and does not cover the extensive associated programs that have been carried out in the fields of design, design analysis, safety analysis, fuels development, equipment development and testing, quality assurance, equipment fabrication, plant construction, acceptance testing, operations planning and training, and the like.

Cabell, C.P. (comp.)

1980-12-01T23:59:59.000Z

52

Test Procedures for Faucets, Showerheads, Water Closets, Urinals...  

NLE Websites -- All DOE Office Websites (Extended Search)

Certain Commercial and Industrial Equipment: Test Procedures for Showerheads, Faucets, Water Closets, Urinals, and Commercial Prerinse Spray Valves AGENCY: Office of Energy...

53

Comparison of Test Procedures and Energy Efficiency Criteria...  

NLE Websites -- All DOE Office Websites (Extended Search)

International Standards & Labeling Programs for Copy Machines, External Power Supplies, LED Displays, Residential Gas Cooktops and Televisions Title Comparison of Test Procedures...

54

Test Procedure for 170.302 (p) Emergency Access  

Science Conference Proceedings (OSTI)

... September 24, 2010 1 Test Procedure for 170.302 (p) Emergency Access ... 170.302(p) Emergency Access. Permit authorized users ...

2013-11-06T23:59:59.000Z

55

Additional Guidance Regarding Application of Current Procedures for Testing  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Additional Guidance Regarding Application of Current Procedures for Additional Guidance Regarding Application of Current Procedures for Testing Energy Consumption of Clothes Washers with Warm Rinse Cycles, Issued: June 30, 2010 Additional Guidance Regarding Application of Current Procedures for Testing Energy Consumption of Clothes Washers with Warm Rinse Cycles, Issued: June 30, 2010 Additional Guidance Regarding Application of Current Procedures for Testing Energy Consumption of Clothes Washers with Warm Rinse Cycles, Issued: June 30, 2010. Draft of DOE interpretive rule, which sets out DOE's views on the clothes washer testing procedure described in 10 CFR § 430 Appendix J1, having to do with how to apply the testing procedures to washers with a warm rinse option. This draft interpretive rule represents DOE's interpretation of

56

summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Project Summary HELP Index Summary Scenario Internet Links Student Pages SubjectContent Area: Language Arts and Social Studies Target Audience: This project is designed for third...

57

ENERGY STAR Test Procedures and Verification | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

ENERGY STAR » ENERGY STAR Test ENERGY STAR » ENERGY STAR Test Procedures and Verification ENERGY STAR Test Procedures and Verification The Department of Energy (DOE) is the lead agency in the development and revision of all test procedures for products in the ENERGY STAR® program, including those products that are also subject to DOE's Energy Conservation Standards program. As specifications are updated and new products or metrics are added to the ENERGY STAR program, DOE is responsible for developing and revising methods, responding to stakeholder comments, and answering any testing-related questions that arise as a result of the procedures being utilized. To simplify the process for interested parties, more information on the test procedure development for ENERGY STAR products can be found on each of

58

Rocky Flats ash test procedure (sludge stabilization)  

SciTech Connect

Rocky Flats Ash items have been identified as the next set of materials to be stabilized. This test is being run to determine charge sizes and soak times to completely stabilize the Rocky Flats Ash items. The information gathered will be used to generate the heating rampup cycle for stabilization. This test will also gain information on the effects of the glovebox atmosphere (moisture) on the stabilized material. This document provides instructions for testing Rocky Flats Ash in the HC-21C muffle furnace process.

Winstead, M.L.

1995-09-14T23:59:59.000Z

59

Test procedure forms for sludge retrieval and packaging  

SciTech Connect

This document provides test procedure forms for sludge retrieval and packaging tests in the 305 Cold Test Facility. The completed and approved forms provide all descriptions, criteria and analysis to safely perform sludge equipment tests in the 305 Cold Test Facility.

Feigenbutz, L.V.

1994-09-27T23:59:59.000Z

60

US advanced battery consortium in-vehicle battery testing procedure  

DOE Green Energy (OSTI)

This article describes test procedures to be used as part of a program to monitor the performance of batteries used in electric vehicle applications. The data will be collected as part of an electric vehicle testing program, which will include battery packs from a number of different suppliers. Most data will be collected by on-board systems or from driver logs. The paper describes the test procedure to be implemented for batteries being used in this testing.

NONE

1997-03-01T23:59:59.000Z

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


61

Acceptance test procedure: RMW Land Disposal Facility Project W-025  

SciTech Connect

This ATP establishes field testing procedures to demonstrate that the electrical/instrumentation system functions as intended by design for the Radioactive Mixed Waste Land Disposal Facility. Procedures are outlined for the field testing of the following: electrical heat trace system; transducers and meter/controllers; pumps; leachate storage tank; and building power and lighting.

Roscha, V. [Westinghouse Hanford Co., Richland, WA (United States)

1994-12-12T23:59:59.000Z

62

NERVA Program. Operating procedure: cart cooling system, Test Cell A  

SciTech Connect

The instructions described in this procedure are typical of the operation of Test Cell A relative to the KIWI-B4A. Operation of Test Cell A relative to the NRX reactor will require modifications dictated by specific test requirements. Under NRX conditions, it will be the responsibility of the test cell manager to evaluate the capabilities of Test Cell A in terms of given test requirements and then set forth detailed checklists which will be compatible with the test requirements.

1963-09-01T23:59:59.000Z

63

Approved Test Procedures Version 1.1 Release Notes  

E-Print Network (OSTI)

Approved Test Procedures Version 1.1 Release Notes 1 Change Reason for Change 302.a drugdrug, drug allergy In the Informative Test Description section Added clarification to the example. 302.c Problem List In the Informative Test Description section Added the sentence "The test also

64

NBSBR 84-2867 Test Procedures for Rating  

E-Print Network (OSTI)

NBSBR 84-2867 Test Procedures for Rating Residential Heating and Cooling Absorption Equipment U HEATING AND COOLING ABSORPTION EQUIPMENT Brian Weber Reinhard Radermacher David Didion U.S. DEPARTMENT-fired absorption devices operating in either the heating or cooling modes. These procedures are designed to include

Oak Ridge National Laboratory

65

USABC electric vehicle Battery Test Procedures Manual. Revision 2  

DOE Green Energy (OSTI)

This manual summarizes the procedural information needed to perform the battery testing being sponsored by the United States Advanced Battery Consortium (USABC). This information provides the structure and standards to be used by all testing organizations, including the USABC developers, national laboratories, or other relevant test facilities.

NONE

1996-01-01T23:59:59.000Z

66

DOE Seeks Comment on Application of Clothes Washer Test Procedure |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Application of Clothes Washer Test Procedure Application of Clothes Washer Test Procedure DOE Seeks Comment on Application of Clothes Washer Test Procedure June 30, 2010 - 3:02pm Addthis Today, the U.S. Department of Energy (DOE) issued a draft interpretative rule clarifying its views on the application of the current residential clothes washer test procedure to machines that offer a warm rinse option that is not included in the recommended cycle for washing cotton or linen clothes. The Department is soliciting feedback from the public on the draft interpretive rule, which is available here, until July 30, 2010. Addthis Related Articles Save Energy and More with ENERGY STAR. ENERGY STAR clothes washers use 50% less energy to wash clothes than standard washing machines. Tips: Laundry DOE Solicits Views on the Implementation of Large-Capacity Clothes Washer

67

DOE Seeks Comment on Application of Clothes Washer Test Procedure |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Seeks Comment on Application of Clothes Washer Test Procedure Seeks Comment on Application of Clothes Washer Test Procedure DOE Seeks Comment on Application of Clothes Washer Test Procedure June 30, 2010 - 3:02pm Addthis Today, the U.S. Department of Energy (DOE) issued a draft interpretative rule clarifying its views on the application of the current residential clothes washer test procedure to machines that offer a warm rinse option that is not included in the recommended cycle for washing cotton or linen clothes. The Department is soliciting feedback from the public on the draft interpretive rule, which is available here, until July 30, 2010. Addthis Related Articles DOE Seeks Comment on Definition of Showerhead Save Energy and More with ENERGY STAR. ENERGY STAR clothes washers use 50% less energy to wash clothes than standard washing machines.

68

trona test report summary 1-17-06 .doc  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

1 of 5 1 of 5 Trona Injection Tests Mirant Potomac River Station Unit 1 November 12 to December 23, 2005 Summary Report Mirant Corporation January 17, 2006 Page 2 of 5 1. INTRODUCTION Trona injection tests were conducted at Mirant's Potomac River Station on Unit 1 between November 12 and December 23, 2005. The purpose of these tests was to determine the capability of dry injection of trona to achieve substantial SO 2 removal from the stack discharge, and the determination of other operating impacts from the trona injection, if any. Temporary trona injection equipment was installed on Unit 1, to inject dry trona in the duct between the boiler economizer outlet and the hot precipitator inlet. Trona was obtained with rail car delivery directly from the mine in Green River,

69

Results and conclusions test capabilities task group summary report  

SciTech Connect

This annotated briefing documents an economic analysis of Sandia`s system-level test facilities maintained and operated by the Design, Evaluation, and Test Technology Center 9700. The study was divided into four primary sub-tasks: (1) Estimation of the future system-level test workload, (2) Development of a consistent economic model to estimate the cost of maintaining and operating the test facilities, (3) Determination of the availability of viable alternative test sites, and (4) Assessment of the potential savings through reduction of excess capacity under various facility-closure scenarios. The analysis indicated that potential savings from closing all facilities could approach $6 million per year. However, large uncertainties in these savings remove any sound economic arguments for such closure: it is possible that testing at alternative sites could cost more than maintaining the current set of system-level test facilities. Finally, a number of programmatic risks incurred by facility closure were identified. Consideration of facility closure requires a careful weighing of any projected economic benefit against these programmatic risks. This summary report covers the briefing given to upper management. A more detailed discussion of the data and analyses is given in the full report, available for internal use from the technical library.

Bomber, T.; Pierce, K.; Easterling, R.; Rogers, J.

1996-12-01T23:59:59.000Z

70

Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

RAINFOREST REALITIES Project Summary Scenario Student Pages Internet Links Index SubjectContent Area: Science, Language Arts, Math, and Social Science Target Audience: This...

71

summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Project Summary Scenario Student Page Internet Links Index SubjectContent Area: Math - data collection; Language Arts - expressive and narrative writing and reference skills;...

72

Flammable gas interlock spoolpiece flow response test plan and procedure  

DOE Green Energy (OSTI)

The purpose of this test plan and procedure is to test the Whittaker electrochemical cell and the Sierra Monitor Corp. flammable gas monitors in a simulated field flow configuration. The sensors are used on the Rotary Mode Core Sampling (RMCS) Flammable Gas Interlock (FGI), to detect flammable gases, including hydrogen and teminate the core sampling activity at a predetermined concentration level.

Schneider, T.C., Fluor Daniel Hanford

1997-02-13T23:59:59.000Z

73

Operability test procedure [Tank] 241-SY-101 equipment removal system  

DOE Green Energy (OSTI)

The 241-SY-101 equipment removal system (ERS) consists of components, equipment, instrumentation and procedures that will provide the means to disconnect, retrieve, contain, load and transport the Mitigation Pump Assembly (MPA) from waste Tank 241-SY-101 to the Central Waste Complex (CWC). The Operability Test Procedure (OTP) will test the interfaces between ERS components and will rehearse the procedure for MPA removal and transportation to the extent they can be mocked-up at the CTF (Cold Test Facility). At the conclusion of the OTP, the ERS components and equipment will be removed from the CTF, entered into the Component Based Recall System (CBRS), and stored until needed for actual MPA removal and transportation.

Mast, J.C.

1994-12-08T23:59:59.000Z

74

Summary  

Science Conference Proceedings (OSTI)

Summary. A, B, C, D, E, F, G, H, I, J, K, L, M, N, O, P, Q, R, S, T, U, V, W, X, Y, Z. 1, STEP File, STEP-File-Analyzer.stp, 2, STEP Directory, C ...

2013-08-12T23:59:59.000Z

75

Summary  

Science Conference Proceedings (OSTI)

Summary. A, B, C, D, E, F, G, H, I, J, K, L, M, N, O, P, Q, R, S, T, U, V, W, X, Y, Z. 1, STEP File, STEP-File-Analyzer-Semantic-PMI.stp, 2, STEP ...

2013-08-12T23:59:59.000Z

76

MEMORANDUM TO: File FROM: David R. Hill RE: Meeting Concerning Potential Test Procedures and Energy Conservation  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

MEMORANDUM MEMORANDUM TO: File FROM: David R. Hill RE: Meeting Concerning Potential Test Procedures and Energy Conservation Standards for Set-Top Boxes and Network Equipment DATE: March 14, 2012 In compliance with the Department of Energy's guidance on ex parte communications (74 Fed. Reg. 52795 (Oct. 14, 2009)), this memorandum provides a summary of a March 7, 2012, meeting with DOE officials concerning potential test procedures and energy conservation standards for set-top boxes and network equipment. Meeting attendees: John Cymbalski (DOE - EE) Jeremy Dommu (DOE - EE) Ashley Armstrong (DOE - EE) Dan Cohen (DOE - GC) Celia Sher (DOE - GC) Cecilia Martaus (AT&T) Mike Pfau (AT&T) Jeff Dygert (AT&T) David Hill (Sidley Austin) The AT&T representatives discussed a number of concerns with DOE's potential promulgation

77

PUREX (SAMCONS) uninterruptible power supply (UPS) acceptance test procedure  

SciTech Connect

This Acceptance Test Procedure for the PUREX Surveillance and Monitoring and Control System (SAMCONS) Uninterruptible Power Supply (UPS) provides for testing and verifying the proper operation of the control panel alarms and trouble functions, the 6roper functioning of the AC inverter, ability of the battery supply to maintain the SAMCONS load for a minimum of two hours , and proper interaction with the SAMCONS Video graphic displays for alarm displays.

Blackaby, W.B.

1997-09-01T23:59:59.000Z

78

241-AZ-101 Mixer Pump Demonstration Test Gamma Cart Acceptance Test Procedure and Quality Test Plan (ATP and QTP)  

Science Conference Proceedings (OSTI)

Shop Test of the Gamma Cart System to be used in the AZ-101 Mixer Pump Demonstration Test. Tests hardware and software. This procedure involves testing the Instrumentation involved with the Gamma Cart System, local and remote, including: depth indicators, speed controls, interface to data acquisition software and the raising and lowering functions. This Procedure will be performed twice, once for each Gamma Cart System. This procedure does not test the accuracy of the data acquisition software.

WHITE, D.A.

2000-03-01T23:59:59.000Z

79

241-AZ-101 Mixer Pump Demonstration Test Gamma Cart Acceptance Test Procedure and Quality Test Plan (ATP and QTP)  

SciTech Connect

Shop test of the sludge mobilization cart system to be used in the AZ-101 Mixer Pump Demonstration Test Tests hardware and software. This procedure involves testing the Instrumentation involved with the Gamma Cart System, local and remote, including depth indicators, speed controls, interface to data acquisition software and the raising and lowering functions. This Procedure will be performed twice, once for each Gamma Cart System. This procedure does not test the accuracy of the data acquisition software.

WHITE, D.A.

2000-01-27T23:59:59.000Z

80

Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Project Summary Project Summary HELP Index Summary Scenario References Student Pages Subject/Content Area: Ecology and Data Collection Target Audience: This project is designed for upper intermediate grade students. Access to a river or stream is critical to the success of this project. Students need access to the Internet and data collection software. Project Goals: When presented with an environmental problem on a local river, students will use their knowledge of river ecology to develop an action plan. Learner Outcomes: The students will be able to Use river monitoring equipment to collect river monitoring data, including biological, physical,and chemical data. Design a project that aids the class in accompolishing one of four goals: Raising smallmouth bass Creating a stream habitat in an aquarium

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


81

Acceptance test report for the AN valve pit leak detection and low point drain assembly mock up test procedure  

SciTech Connect

This document describes The Performance Mock-up Test Procedure for the Valve Pit Leak Detection and Low Point Drain Assembly Performance Mock-Up Test Procedure.

EWER, K.L.

1999-07-20T23:59:59.000Z

82

Summary of geology at the ERDA--MAGMA--SDG and E geothermal test site  

DOE Green Energy (OSTI)

A summary is given of the geologic structure of the test facility in Imperial County. The analysis is based on well records, especially electrical logs. (LBS)

Towse, D.F.; Palmer, T.D.

1976-01-12T23:59:59.000Z

83

Summary  

Science Conference Proceedings (OSTI)

Summary. A, B, C, D, E, F, G, H, I, J, K, L, M, N, O, P, Q, R, S, T, U, V, W, X, Y, Z. 1, CIS/2 File, AISC_Sculpture_J.stp, 2, CIS/2 Directory, C:\\Users ...

2013-05-21T23:59:59.000Z

84

Residential Clothes Washers Test Procedure Notice of Proposed Rulemaking  

NLE Websites -- All DOE Office Websites (Extended Search)

19:12 Sep 20, 2010 19:12 Sep 20, 2010 Jkt 220001 PO 00000 Frm 00001 Fmt 4717 Sfmt 4717 E:\FR\FM\21SEP2.SGM 21SEP2 srobinson on DSKHWCL6B1PROD with PROPOSALS2 Tuesday, September 21, 2010 Part II Department of Energy 10 CFR Part 430 Energy Conservation Program for Consumer Products: Test Procedure for Residential Clothes Washers; Proposed Rule VerDate Mar2010 19:12 Sep 20, 2010 Jkt 220001 PO 00000 Frm 00002 Fmt 4701 Sfmt 4702 E:\FR\FM\21SEP2.SGM 21SEP2 srobinson on DSKHWCL6B1PROD with PROPOSALS2 57556 Federal Register / Vol. 75, No. 182 / Tuesday, September 21, 2010 / Proposed Rules DEPARTMENT OF ENERGY 10 CFR Part 430 [Docket No. EERE-2010-BT-TP-0021] RIN 1904-AC08 Energy Conservation Program for Consumer Products: Test Procedure for Residential Clothes Washers AGENCY: Office of Energy Efficiency and

85

Summary  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Golden Field Office Golden Field Office Office of Energy Efficiency and Renewable Energy DOE/EIS-0407D September 2009 Draft Environmental Impact Statement for the Proposed Abengoa Biorefinery Project near Hugoton, Stevens County, Kansas Summary Cover photos courtesy of (left to right): Southeast Renewable Fuels, LLC DOE National Renewable Energy Laboratory Public domain U.S. Department of Energy Golden Field Office Office of Energy Efficiency and Renewable Energy DOE/EIS-0407D September 2009 Draft Environmental Impact Statement for the Proposed Abengoa Biorefinery Project near Hugoton, Stevens County, Kansas Summary COVER SHEET RESPONSIBLE AGENCY: U.S. Department of Energy (DOE) COOPERATING AGENCY: The U.S. Department of Agriculture-Rural Development is a cooperating agency in the preparation of the Abengoa Biorefinery Project EIS.

86

Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

SPACE SPACE Project Summary HELP Index Summary Scenario Internet Links Student Pages Subject/Content Area: Interdisciplinary: Science - astronomy; Math - problem-solving and measurement; Art; Social Studies - current events; and Language Arts - reference. skills Target Audience: Middle school students, 7th grade, all levels Project Goals: A collaborative, seven-to-ten weeks investigation of the space program, specifically space stations, its impact on our lives and the world Learner Outcomes: Students will be able to: Gather information and use decision-making skills to evaluate this information. Establish connections and to develop decision-making skills about science and technology. Identify and state a problem; design, implement, and evaluate the solution. Gather and use information for research purposes.

87

Test Report for Acceptance Test Procedure for Pumping Instrumentation and Control Skid N  

Science Conference Proceedings (OSTI)

This is a Test Report for Acceptance Test Procedure (ATP) RPP-5489. This test report provides the results of the inspection and testing of the new Pumping Instrumentation and Control (PIC) skid designed as ''N''. The ATP was successfully completed. A copy of the completed ATP is in the Appendix of this document.

KOCH, M.R.

2000-02-03T23:59:59.000Z

88

Summary of Large-and Small-Scale Unreinforced Masonry Test Program  

Science Conference Proceedings (OSTI)

A five-year, large- and small-scale, static and dynamic experimental research program, in which more than 700 tests were conducted, has demonstrated that unreinforced masonry infills are more ductile and resist lateral loads more effectively than anticipated by conventional code procedures. The tests were conducted both in the laboratory and on existing structures at the Department of Energy's Y-12 National Security Complex. The experimental data indicate that the combination of a steel frame and infill material efficiently resists lateral loads--the infilling provides significant lateral stiffness while the surrounding frame adds ductility and confinement to the overall system. The results from approximately 25 moderate- and full-scale tests on infills showed that with simulated seismic loads, the frames confined the masonry, and the load-carrying capacity of the infill was considerably above the load that caused initial cracking. This finding was a significant departure from classical code approaches that assumed first cracking to be failure of an unreinforced masonry wall. The experimental program, performed for the US Department of Energy, consisted of the following large-scale tests on infills: in situ airbag pressure testing, shake-table tests, and the application of quasi-static in-plane and out-of-plane drift loads. This paper provides a summary of the overall experimental methodology and results.

Fricke, K.E.

2002-06-28T23:59:59.000Z

89

Lightning arrestor connector lead magnesium niobate qualification pellet test procedures.  

SciTech Connect

Enhanced knowledge preservation for DOE DP technical component activities has recently received much attention. As part of this recent knowledge preservation effort, improved documentation of the sample preparation and electrical testing procedures for lead magnesium niobate--lead titanate (PMN/PT) qualification pellets was completed. The qualification pellets are fabricated from the same parent powders used to produce PMN/PT lightning arrestor connector (LAC) granules at HWF&T. In our report, the procedures for fired pellet surface preparation, electrode deposition, electrical testing and data recording are described. The dielectric measurements described in our report are an information only test. Technical reasons for selecting the electrode material, electrode size and geometry are presented. The electrical testing is based on measuring the dielectric constant and dissipation factor of the pellet during cooling from 280 C to 220 C. The most important data are the temperature for which the peak dielectric constant occurs (Curie Point temperature) and the peak dielectric constant magnitude. We determined that the peak dielectric constant for our procedure would be that measured at 1 kHz at the Curie Point. Both the peak dielectric constant and the Curie point parameters provide semi-quantitative information concerning the chemical and microstructural homogeneity of the parent material used for the production of PMN/PT granules for LACs. Finally, we have proposed flag limits for the dielectric data for the pellets. Specifically, if the temperature of the peak dielectric constant falls outside the range of 250 C {+-} 30 C we propose that a flag limit be imposed that will initiate communication between production agency and design agency personnel. If the peak dielectric constant measured falls outside the range 25,000 {+-} 10,000 we also propose that a flag limit be imposed.

Tuohig, W. (Honeywell FM& T, Kansas City, MO); Mahoney, Patrick A.; Tuttle, Bruce Andrew; Wheeler, Jill Susanne

2009-02-01T23:59:59.000Z

90

Summary  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Imperial-Mexicali DEIS Imperial-Mexicali DEIS S-1 May 2004 SUMMARY S.1 BACKGROUND S.1.1 Previous NEPA Review and Litigation Baja California Power, Inc. (hereafter referred to as Intergen), applied to the U.S. Department of Energy (DOE) on February 27, 2001, to construct a double-circuit, 230,000-volt (230-kV) transmission line across the U.S.-Mexico border. In a separate but similar proceeding, Sempra Energy Resources (hereafter referred to as Sempra) applied to DOE for a Presidential permit on March 7, 2001, also proposing to construct a double-circuit, 230-kV transmission line across the U.S.-Mexico border. Executive Order (E.O.) 10485 (September 9, 1953), as amended by E.O. 12038 (February 7, 1978), requires that a Presidential permit be issued by DOE before electric transmission facilities may be constructed, operated, maintained,

91

Test Procedure for 170.302.h Incorporate Laboratory Test Results APPROVED Version 1.1 September 24, 2010  

E-Print Network (OSTI)

Test Procedure for §170.302.h Incorporate Laboratory Test Results APPROVED Version 1.1 September 24, 2010 1 Test Procedure for §170.302 (h) Incorporate Laboratory Test Results This document describes the test procedure for evaluating conformance of complete EHRs or EHR modules1

92

Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

test reasonableness of results. Learner Outcomes: (7th grade) Students will design and safely conduct investigations that provide reliable quantitative or qualitative...

93

Acceptance test procedure for SY Tank Farm replacement exhauster unit  

SciTech Connect

The proper functioning of a new 241-SY Tank Farm replacement exhauster will be acceptance tested, to establish operability and to provide an operational baseline for the equipment. During this test, a verification of all of the alarm and control circuits associated with the exhaust, which provide operating controls and/or signals to local and remote alarm/annunciator panels, shall be performed. Test signals for sensors that provide alarms, warnings, and/or interlocks will be applied to verify that alarm, warning, and interlock setpoints are correct. Alarm and warning lights, controls, and local and remote readouts for the exhauster will be verified to be adequate for proper operation of the exhauster. Testing per this procedure shall be conducted in two phases. The first phase of testing, to verify alarm, warning, and interlock setpoints primarily, will be performed in the MO-566 Fab Shop. The second phase of testing, to verify proper operation and acceptable interface with other tank farm systems, will be conducted after the exhauster and all associated support and monitoring equipment have been installed in the SY Tank Farm. The exhauster, which is mounted on a skid and which will eventually be located in the SY tank farm, receives input signals from a variety of sensors mounted on the skid and associated equipment. These sensors provide information such as: exhauster system inlet vacuum pressure; prefilter and HEPA filter differential pressures; exhaust stack sampler status; exhaust fan status; system status (running/shut down); and radiation monitoring systems status. The output of these sensors is transmitted to the exhauster annunciator panel where the signals are displayed and monitored for out-of-specification conditions.

Becken, G.W.

1994-12-16T23:59:59.000Z

94

Federal Test Procedure Emissions Test Results from Ethanol Variable-Fuel Vehicle Chevrolet Luminas  

Alternative Fuels and Advanced Vehicles Data Center (EERE)

Federal Test Procedure Emissions Test Results from Federal Test Procedure Emissions Test Results from Ethanol Variable-Fuel Vehicle Chevrolet Luminas Kenneth J. Kelly, Brent K. Bailey, and Timothy C. Coburn National Renewable Energy Laboratory Wendy Clark Automotive Testing Laboratories, Inc. Peter Lissiuk Environmental Research and Development Corp. Presented at Society for Automotive Engineers International Spring Fuels and Lubricants Meeting Dearborn, MI May 6-8, 1996 The work described here was wholly funded by the U.S. Department of Energy, a U.S. government agency. As such, this information is in the public domain, may be copied and otherwise accessed freely, and is not subject to copyright laws. These papers were previously published in hard copy form by the Society of Automotive Engineers, Inc. (Telephone: 412.776.4970; E-mail: publications@sae.org)

95

Test plan/procedure for the SPM-1 shipping container system. Revision 0  

SciTech Connect

The 49 CFR 173.465 Type A packaging tests will verify that SPM-1 will provide adequate protection and pass as a Type A package. Test will determine that the handle of the Pig will not penetrate through the plywood spacer and rupture the shipping container. Test plan/procedure provides planning, pre-test, setup, testing, and post-testing guidelines and procedures for conducting the {open_quotes}Free Drop Test{close_quotes} procedure for the SPM-1 package.

Flanagan, B.D.

1995-07-01T23:59:59.000Z

96

DOE Releases Data Summary Report for Groundwater and Soil Tests Conducted  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Releases Data Summary Report for Groundwater and Soil Tests Releases Data Summary Report for Groundwater and Soil Tests Conducted at the Riverton UMTRCA Site DOE Releases Data Summary Report for Groundwater and Soil Tests Conducted at the Riverton UMTRCA Site February 19, 2013 - 12:53pm Addthis Contractor, Judy Miller, S.M. Stoller Corporation Public Affairs, (970) 248-6363, jmiller@lm.doe.gov GRAND JUNCTION, Colo. - The U.S. Department of Energy today announced the availability of a Data Summary Report of enhanced characterization fieldwork conducted in August 2012 at the Riverton, Wyoming, Uranium Mill Tailings Radiation Control Act (UMTRCA) Site. "The Department will use the data to assess why levels of groundwater contamination in monitoring wells increased after the 2010 historic flood event of the Little Wind River," said Bill Dam, DOE Riverton site

97

Summary of Compression Testing of U-10Mo  

SciTech Connect

The mechanical properties of depleted uranium plus 10 weight percent molybdenum alloy have been evaluated by high temperature compression testing.

Nyberg, Eric A.; Joshi, Vineet V.; Lavender, Curt A.; Burkes, Douglas

2012-10-31T23:59:59.000Z

98

Nevada Test Site FFCA Consent Order, May 10, 1996 Summary  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Federal Facility Agreement and Consent Order Federal Facility Agreement and Consent Order (FFACO) State Nevada Agreement Type Federal Facility Agreement and Consent Order Legal Driver(s) FFCAct Scope Summary Identify sites of potential historic contamination and implement proposed corrective actions Parties DOE; Department of Defense (DoD); Nevada Division of Environmental Protection (NDEP) Date 5/10/1996 SCOPE * Identify sites of potential historic contamination and implement proposed corrective actions. * Establish specific sampling and monitoring requirements, including drilling and subsurface sampling. ESTABLISHING MILESTONES * Within sixty (60) calendar days following the signing of this Agreement, the parties shall meet to review Appendices II-IV and concur on the classification of all presently

99

Summary  

E-Print Network (OSTI)

The Venus Geochemistry workshop was convened as a way to invigorate the Venus geochemistry community, and to provide assessment of the most crucial investigations for understanding the geochemistry of Venus. In brief, the recommendations of the workshop attendees include the following. ? Geochemical data are needed for all parts of Venus surface, especially its highland areas. Venus highlands are the oldest exposed areas, and thus have the greatest chance of revealing Venus early history and climate. ? Geochemical investigations must address both the mineralogy of surface materials and their chemical compositions, with greatly expanded elemental coverage and much improved precision relative to prior analyses. ? Future geochemical investigations at Venus surface will be facilitated and focused by laboratory investigations at Venus surface conditions and by studies of analog environments on Earth. These precursor studies would focus on: optical properties, E&M (Radar) properties, thermochemistry and reaction kinetics, and physical properties. ? These investigations will require pressure/temperature chambers, which could be small and specific to each investigation. Chambers suitable for spacecraft & instrument testing are not required for geochemical investigations, but would be enabling to these studies if available to the science community ? NASA is encouraged to pursue every opportunity to enhance scientific and technological research relevant to Venus through programs in ROSES, SBIR, NESSF, and other vehicles for student support. 1

Allan H. Treiman; David S. Draper; M. Darby Dyar

2009-01-01T23:59:59.000Z

100

ABB SCADA/EMS System INEEL Baseline Summary Test Report (November 2004) |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

SCADA/EMS System INEEL Baseline Summary Test Report (November SCADA/EMS System INEEL Baseline Summary Test Report (November 2004) ABB SCADA/EMS System INEEL Baseline Summary Test Report (November 2004) This document covers the security evaluation of the "baseline" or "as delivered" system performed in the Idaho National Engineering and Environmental Laboratory (INEEL) SCADA test bed as part of the Critical Infrastructure Test Range Development Program, which is funded by the U.S. Department of Energy; Office of Energy Assurance (DOE/OEA). This report is a nonproprietary version of the report sent to ABB that identified specific issues related to the security vulnerabilities in the ABB SCADA/EMS system. Work was performed by specialists in the fields of control system development, networking, software engineering, and cybersecurity. This

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


101

Summary of electric vehicle dc motor-controller tests  

DOE Green Energy (OSTI)

Available performance data for production motors are usually of marginal value to the electric vehicle designer. To provide at least a partial remedy to this situation, tests of typical dc propulsion motors and controllers were conducted as part of the DOE Electric Vehicle Program. The objectives of this program were to evaluate the differences in the performance of dc motors when operating with chopper-type controllers and when operating on direct current; and to gain an understanding of the interactions between the motor and the controller which cause these differences. Toward this end, motor-controller tests performed by the NASA Lewis Research Center provided some of the first published data that quantified motor efficiency variations for both ripple-free (straight dc) and chopper modes of operation. Test and analysis work at the University of Pittsburgh explored motor-controller relationships in greater depth. And to provide additional data, 3E Vehicles tested two small motors, both on a dynamometer and in a vehicle, and the Eaton Corporation tested larger motors, using sophisticated instrumentation and digital processing techniques. All the motors tested were direct-current types. Of the separately excited types, seven were series wound and two were shunt wound. One self-excited permanent magnet type was also tested. Four of the series wound motors used brush shifting to obtain good commutation. In almost all cases, controller limitations constrained the test envelope so that the full capability of the motors could not be explored.

McBrien, E F; Tryon, H B

1982-09-01T23:59:59.000Z

102

Summary - Disposal Practices at the Nevada Test Site  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Nevada Test Site, NV Nevada Test Site, NV EM Project: Area 5 LLRW & MLLW Disposal ETR Report Date: July 2008 ETR-14 United States Department of Energy Office of Environmental Management (DOE-EM) External Technical Review of Disposal Practices at the Nevada Test Site Why DOE-EM Did This Review Radioactively contaminated materials from the Nevada Test Site (NTS), other DOE facilities and other federal agencies are disposed of at NTS at two low-level radioactive waste (LLRW) management sites: Areas 3 and 5. Disposal operations at Area 3 have been discontinued, but the facility is available for future disposal. The anticipated closure date for Area 3 is 2027. Area 5 is operating and will be expanded to accept future wastes. LLRW and mixed low-level radioactive waste (MLLW) are disposed of in Area 5 in shallow

103

Tonopah Test Range Summary of Corrective Action Units  

SciTech Connect

Corrective Action Sites (CASs) and Corrective Action Units (CAUs) at the Tonopah Test Range (TTR) may be placed into three categories: Clean Closure/No Further Action, Closure in Place, or Closure in Progress.

Ronald B. Jackson

2007-05-01T23:59:59.000Z

104

Summary of the Solar Two Test and Evaluation Program  

Science Conference Proceedings (OSTI)

Solar Two was a collaborative, cost-shared project between eleven US industry and utility partners and the U. S. Department of Energy to validate molten-salt power tower technology. The Solar Two plant, located east of Barstow, CA, was comprised of 1926 heliostats, a receiver, a thermal storage system and a steam generation system. Molten nitrate salt was used as the heat transfer fluid and storage media. The steam generator powered a 10 MWe, conventional Rankine cycle turbine. Solar Two operated from June 1996 to April 1999. The major objective of the test and evaluation phase of the project was to validate the technical characteristics of a molten salt power tower. This paper describes the significant results from the test and evaluation activities.

PACHECO,JAMES E.; REILLY,HUGH E.; KOLB,GREGORY J.; TYNER,CRAIG E.

2000-02-08T23:59:59.000Z

105

H-Disk Aluminum Prototype Heat Transfer Test Summary  

SciTech Connect

The aluminum H-disk was instrumented with heaters (156 ohm on average) and 100 ohm platinum RTD's. Each heater supplies the heat of a double sided H-wedge. Since the flow splits into two flow directions at the inlet fitting, only half of the cooling channel is fully instrumented with RTD's. The other path has a single RTD to check for flow balancing. These items were installed after Greg Derylo petformed the first pressure drop tests. At the time of the test, the desired adhesive for gluing the two halves of the channel together was not available. Therefore, 5-minute epoxy was used on the inner and outer diameters of the halves. Tape was used to set the gap between the two halves. This form of attachment does not make a strong bond between the two halves so the differential pressure between the inside and the outside of the channel was limited to a couple of psi. Therefore, the tests were not conducted in a vacuum.

Squires, B.; /Fermilab

1998-07-28T23:59:59.000Z

106

Summary of lithium-lead alloy safety compatibility tests  

Science Conference Proceedings (OSTI)

Lithium-lead alloy (17Li-83Pb) reactions with air, nitrogen, carbon dioxide, concrete, steam, and water have been characterized to identify potential safety concerns associated with the use of this alloy as a breeding material in fusion reactors. Alloy-material reaction tests were conducted at alloy temperatures up to 700/degree/C to characterize interactions at the highest accident temperatures postulated for most proposed fusion reactors. Test results show that alloy pool-air interactions released limited quantities of heat and aerosols. Alloy spray reactions with air were very mild. Alloy pool reactions with concrete were limited to a reaction with water driven from the concrete. Alloy-steam and water reactions were limited by the lithium present in the alloy. Alloy interactions are considerably less reactive than liquid lithium with these materials in regards to heat generation, material consumption, and aerosol mass generation. Potential radioactive species release from alloy interactions with these materials must be contained. Conventional filtration systems appear adequate to contain the limited quantities of aerosol released. Hydrogen release from alloy interactions with concrete, steam, and water must be controlled. 14 refs., 62 figs., 35 tabs.

Jeppson, D.W.

1989-01-01T23:59:59.000Z

107

Data summary report for fission product release Test VI-7  

SciTech Connect

Test VI-7 was the final test in the VI series conducted in the vertical furnace. The fuel specimen was a 15.2-cm-long section of a fuel rod from the Monticello boiling water reactor (BWR). The fuel had experienced a burnup of {approximately}-40 Mwd/kg U. It was heated in an induction furnace for successive 20-min periods at 2000 and 2300 K in a moist air-helium atmosphere. Integral releases were 69% for {sup 85}Kr, 52% for {sup 125}Sb, 71% for both {sup 134}Cs and {sup 137}Cs, and 0.04% for {sup 154}Eu. For the non-gamma-emitting species, release values for 42% for I, 4.1% for Ba, 5.3% for Mo, and 1.2% for Sr were determined. The total mass released from the furnace to the collection system, including fission products, fuel, and structural materials, was 0.89 g, with 37% being collected on the thermal gradient tubes and 63% downstream on filters. Posttest examination of the fuel specimen indicated that most of the cladding was completely oxidized to ZrO{sub 2}, but that oxidation was not quite complete at the upper end. The release behaviors for the most volatile elements, Kr and Cs, were in good agreement with the ORNL-Booth Model.

Osborne, M.F.; Lorentz, R.A.; Travis, J.R.; Collins, J.L.; Webster, C.S. [Oak Ridge National Lab., TN (United States)

1995-05-01T23:59:59.000Z

108

Data summary report for fission product release test VI-6  

SciTech Connect

Test VI-6 was the sixth test in the VI series conducted in the vertical furnace. The fuel specimen was a 15.2-cm-long section of a fuel rod from the BR3 reactor in Belgium. The fuel had experienced a burnup of {approximately}42 MWd/kg, with inert gas release during irradiation of {approximately}2%. The fuel specimen was heated in an induction furnace at 2300 K for 60 min, initially in hydrogen, then in a steam atmosphere. The released fission products were collected in three sequentially operated collection trains designed to facilitate sampling and analysis. The fission product inventories in the fuel were measured directly by gamma-ray spectrometry, where possible, and were calculated by ORIGEN2. Integral releases were 75% for {sup 85}Kr, 67% for {sup 129}I, 64% for {sup 125}Sb, 80% for both {sup 134}Cs and {sup 137}Cs, 14% for {sup 154}Eu, 63% for Te, 32% for Ba, 13% for Mo, and 5.8% for Sr. Of the totals released from the fuel, 43% of the Cs, 32% of the Sb, and 98% of the Eu were deposited in the outlet end of the furnace. During the heatup in hydrogen, the Zircaloy cladding melted, ran down, and reacted with some of the UO{sub 2} and fission products, especially Te and Sb. The total mass released from the furnace to the collection system, including fission products, fuel, and structural materials, was 0.57 g, almost equally divided between thermal gradient tubes and filters. The release behaviors for the most volatile elements, Kr and Cs, were in good agreement with the ORNL Diffusion Model.

Osborne, M.F.; Lorenz, R.A.; Travis, J.R.; Webster, C.S.; Collins, J.L. [Oak Ridge National Lab., TN (United States)

1994-03-01T23:59:59.000Z

109

Sandia National Laboratories Electrochemical Storage System Abuse Test Procedure Manual  

DOE Green Energy (OSTI)

The series of tests described in this report are intended to simulate actual use and abuse conditions and internally initiated failures that may be experienced in electrochemical storage systems (ECSS). These tests were derived from Failure Mode and Effect Analysis, user input, and historical abuse testing. The tests are to provide a common framework for various ECSS technologies. The primary purpose of testing is to gather response information to external/internal inputs. Some tests and/or measurements may not be required for some ECSS technologies and designs if it is demonstrated that a test is not applicable, and the measurements yield no useful information.

Unkelhaeuser, Terry; Smallwood David

1999-07-01T23:59:59.000Z

110

Integrated Disposal Facility FY2010 Glass Testing Summary Report  

SciTech Connect

Pacific Northwest National Laboratory was contracted by Washington River Protection Solutions, LLC to provide the technical basis for estimating radionuclide release from the engineered portion of the disposal facility (e.g., source term). Vitrifying the low-activity waste at Hanford is expected to generate over 1.6 105 m3 of glass (Puigh 1999). The volume of immobilized low-activity waste (ILAW) at Hanford is the largest in the DOE complex and is one of the largest inventories (approximately 0.89 1018 Bq total activity) of long-lived radionuclides, principally 99Tc (t1/2 = 2.1 105), planned for disposal in a low-level waste (LLW) facility. Before the ILAW can be disposed, DOE must conduct a performance assessement (PA) for the Integrated Disposal Facility (IDF) that describes the long-term impacts of the disposal facility on public health and environmental resources. As part of the ILAW glass testing program PNNL is implementing a strategy, consisting of experimentation and modeling, in order to provide the technical basis for estimating radionuclide release from the glass waste form in support of future IDF PAs. The purpose of this report is to summarize the progress made in fiscal year (FY) 2010 toward implementing the strategy with the goal of developing an understanding of the long-term corrosion behavior of low-activity waste glasses. The emphasis in FY2010 was the completing an evaluation of the most sensitive kinetic rate law parameters used to predict glass weathering, documented in Bacon and Pierce (2010), and transitioning from the use of the Subsurface Transport Over Reactive Multi-phases to Subsurface Transport Over Multiple Phases computer code for near-field calculations. The FY2010 activities also consisted of developing a Monte Carlo and Geochemical Modeling framework that links glass composition to alteration phase formation by 1) determining the structure of unreacted and reacted glasses for use as input information into Monte Carlo calculations, 2) compiling the solution data and alteration phases identified from accelerated weathering tests conducted with ILAW glass by PNNL and Viteous State Laboratory/Catholic University of America as well as other literature sources for use in geochemical modeling calculations, and 3) conducting several initial calculations on glasses that contain the four major components of ILAW-Al2O3, B2O3, Na2O, and SiO2.

Pierce, Eric M.; Bacon, Diana H.; Kerisit, Sebastien N.; Windisch, Charles F.; Cantrell, Kirk J.; Valenta, Michelle M.; Burton, Sarah D.; Serne, R Jeffrey; Mattigod, Shas V.

2010-09-30T23:59:59.000Z

111

Adams disassembly procedure for Bldg. 10, Nevada Test Site  

SciTech Connect

The disassembly of the `Adams` primary was scheduled for April 28, 29, and 30, 1959. The method of disassembly is provided as a procedure to be accomplished in order and the time and initials of the person accomplishing each step recorded.

Beckman, K. F.

1959-04-24T23:59:59.000Z

112

Integrated Disposal Facility FY2011 Glass Testing Summary Report  

SciTech Connect

Pacific Northwest National Laboratory was contracted by Washington River Protection Solutions, LLC to provide the technical basis for estimating radionuclide release from the engineered portion of the disposal facility (e.g., source term). Vitrifying the low-activity waste at Hanford is expected to generate over 1.6 x 10{sup 5} m{sup 3} of glass (Certa and Wells 2010). The volume of immobilized low-activity waste (ILAW) at Hanford is the largest in the DOE complex and is one of the largest inventories (approximately 8.9 x 10{sup 14} Bq total activity) of long-lived radionuclides, principally {sup 99}Tc (t{sub 1/2} = 2.1 x 10{sup 5}), planned for disposal in a low-level waste (LLW) facility. Before the ILAW can be disposed, DOE must conduct a performance assessment (PA) for the Integrated Disposal Facility (IDF) that describes the long-term impacts of the disposal facility on public health and environmental resources. As part of the ILAW glass testing program PNNL is implementing a strategy, consisting of experimentation and modeling, in order to provide the technical basis for estimating radionuclide release from the glass waste form in support of future IDF PAs. The purpose of this report is to summarize the progress made in fiscal year (FY) 2011 toward implementing the strategy with the goal of developing an understanding of the long-term corrosion behavior of low-activity waste glasses.

Pierce, Eric M.; Bacon, Diana H.; Kerisit, Sebastien N.; Windisch, Charles F.; Cantrell, Kirk J.; Valenta, Michelle M.; Burton, Sarah D.; Westsik, Joseph H.

2011-09-29T23:59:59.000Z

113

Fast Flux Test Facility (FFTF) Briefing Book 1 Summary  

SciTech Connect

This report documents the results of evaluations preformed during 1997 to determine what, if an, future role the Fast Flux Test Facility (FFTF) might have in support of the Department of Energys tritium productions strategy. An evaluation was also conducted to assess the potential for the FFTF to produce medical isotopes. No safety, environmental, or technical issues associated with producing 1.5 kilograms of tritium per year in the FFTF have been identified that would change the previous evaluations by the Department of Energy, the JASON panel, or Putnam, Hayes & Bartlett. The FFTF can be refitted and restated by July 2002 for a total expenditure of $371 million, with an additional $64 million of startup expense necessary to incorporate the production of medical isotopes. Therapeutic and diagnostic applications of reactor-generated medical isotopes will increase dramatically over the next decade. Essential medical isotopes can be produced in the FFTF simultaneously with tritium production, and while a stand-alone medical isotope mission for the facility cannot be economically justified given current marker conditions, conservative estimates based on a report by Frost &Sullivan indicate that 60% of the annual operational costs (reactor and fuel supply) could be offset by revenues from medical isotope production within 10 yeas of restart. The recommendation of the report is for the Department of Energy to continue to maintain the FFTF in standby and proceed with preparation of appropriate Nations Environmental Policy Act documentation in full consultation with the public to consider the FFTF as an interim tritium production option (1.5 kilograms/year) with a secondary mission of producing medical isotopes.

WJ Apley

1997-12-01T23:59:59.000Z

114

How to Make Appliance Standards Work: Improving Energy and Water Efficiency Test Procedures  

E-Print Network (OSTI)

test procedures for appliances. Energy and BuildingsEnergy Efficiency In Domestic Appliances And Lighting 4thLBNL # How to Make Appliance Standards Work: Improving

Lutz, Jim

2012-01-01T23:59:59.000Z

115

An evaluation of predictive environmental test procedures for sewage sludge.  

E-Print Network (OSTI)

??This research project aimed at evaluating four internationally accepted leachate extraction tests to determine their applicability on sewage sludge samples. Furthermore, the present analytical method (more)

Kasselman, Graeme

2005-01-01T23:59:59.000Z

116

Summary of well-testing activities at Lawrence Berkeley Laboratory, 1975-1983  

DOE Green Energy (OSTI)

Well test data collected from various geothermal fields by the geothermal group at Lawrence Berkeley Laboratory are presented. The type of well tests conducted, the instrumentation used and the data collected are described. Experience gained through interpretation of the data has helped identify problems in test procedures and interpretative methods.

Bodvarsson, M.G.; Benson, S.M.

1983-08-01T23:59:59.000Z

117

Thermal test procedure for a paraboloid concentrator solar cooker  

SciTech Connect

Suitable thermal tests have been identified for performance evaluation of a concentrating solar cooker. These tests provide parameters that characterize the performance of the solar cooker, and are more or less independent of the climatic variables. The overall heat loss factor is obtained from the cooling curve and the optical efficiency factor is determined from the heating curve - both under full load conditions. The performance characteristic curve for the solar cooker is obtained and discussed. The study indicates that the no load test, which is useful in the case of a box type solar cooker, is not appropriate in the case of concentrator type cookers.

Mullick, S.C.; Kandpal, T.C.; Kumar, S. (Indian Institute of Technology, New Delhi (India))

1991-01-01T23:59:59.000Z

118

Testing a Procedure for Automatic Classification of Hydrometeor Types  

Science Conference Proceedings (OSTI)

Examples of automatic interpretation of polarimetric measurements made with an algorithm that classifies precipitation, from an Oklahoma squall line and a Florida airmass storm are presented. Developed in this paper are sensitivity tests of this ...

Dus?an S. Zrni?; Alexander Ryzhkov; Jerry Straka; Yidi Liu; J. Vivekanandan

2001-06-01T23:59:59.000Z

119

Acceptance test procedure MICON software exhaust fan control modifications  

Science Conference Proceedings (OSTI)

This acceptance test verifies the MICON program changes for the new automatic transfer switch ATS-2 alarms, the Closed Loop Cooling isolator status, the CB-3 position alarm, and the alarms for the new emergency fan damper backup air compressor.

SILVAN, G.R.

1999-05-21T23:59:59.000Z

120

A class of matrices to test inversion procedures  

Science Conference Proceedings (OSTI)

The test matrices given by M. L. Pei [Comm. ACM 5, 10 (Oct. 1962), 508] and R. D. Rodman [Comm. ACM 6, 9 (Sept. 1963, 515] are special cases of a general class of matrices with complex elements for which an explicit ...

Randall E. Cline

1964-12-01T23:59:59.000Z

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


121

Gas characterization system 241-AN-105 field acceptance test procedure  

DOE Green Energy (OSTI)

This document details the field Acceptance Testing of a gas characterization system being installed on waste tank 241-AN-105. The gas characterization systems will be used to monitor the vapor spaces of waste tanks known to contain measurable concentrations of flammable gases.

Schneider, T.C.

1996-03-01T23:59:59.000Z

122

Gas characterization system 241-AW-101 field acceptance test procedure  

DOE Green Energy (OSTI)

This document details the field Acceptance Testing of a gas characterization system being installed on waste tank 241-AW-101. The gas characterization systems will be used to monitor the vapor spaces of waste tanks known to contain measurable concentrations of flammable gases.

Schneider, T.C.

1996-03-01T23:59:59.000Z

123

SUMMARY OF AIR TOXICS -. EMISSIONS TESTING AT SIXTEEN UTILITY POWER PLANTS  

NLE Websites -- All DOE Office Websites (Extended Search)

AIR TOXICS AIR TOXICS -. EMISSIONS TESTING AT SIXTEEN UTILITY POWER PLANTS Prepared for U.S. Department of Energy Pittsburgh Energy Technology Center Prepared Under Burns and Roe Services Corporation Contract No. DE-AC22-94PC92100 .Subtask 44.02 July 1996 SUMMARY OF AIR TOXICS EMISSIONS TESTING AT SIXTEEN . . UTILITY POWER PLANTS Prepared for U.S. Department of Energy Pittsburgh Energy Technology Center . Prepared by Adrian Radziwon and Edward Winter Burns and Roe Services Corporation Terence J. McManus, Oak Ridge Associated Universities July 1996 TABLE OF CONTERlW SECTION 1.0 INTRODUCTION ................... 1 Background . : .................. 1 Objectives .................... 1 Report Structure ................. 3 Uncertainties ................... 3 SECTION 2.0 EXECUTIVE SUMMARY ................. 7

124

Fire Safety Tests for Spherical Resorcinol Formaldehyde Resin: Data Summary Report  

SciTech Connect

A draft safety evaluation of the scenario for spherical resorcinol-formaldehyde (SRF) resin fire inside the ion exchange column was performed by the Hanford Tank Waste Treatment and Immobilization Plant (WTP) Fire Safety organization. The result of this draft evaluation suggested a potential change of the fire safety classification for the Cesium Ion Exchange Process System (CXP) emergency elution vessels, equipment, and piping, which may be overly bounding based on the fire performance data from the manufacturer of the ion exchange resin selected for use at the WTP. To resolve this question, the fire properties of the SRF resin were measured by Southwest Research Institute (SwRI), following the American Society for Testing and Materials (ASTM) standard procedures, through a subcontract managed by Pacific Northwest National Laboratory (PNNL). For some tests, the ASTM standard procedures were not entirely appropriate or practical for the SRF resin material, so the procedures were modified and deviations from the ASTM standard procedures were noted. This report summarizes the results of fire safety tests performed and reported by SwRI. The efforts by PNNL were limited to summarizing the test results provided by SwRI into one consolidated data report. All as-received SwRI reports are attached to this report in the Appendix. Where applicable, the precision and bias of each test method, as given by each ASTM standard procedure, are included and compared with the SwRI test results of the SRF resin.

Kim, Dong-Sang; Peterson, Reid A.; Schweiger, Michael J.

2012-07-30T23:59:59.000Z

125

Qualification test procedures and results for Honeywell solar collector subsystem, single-family residence  

DOE Green Energy (OSTI)

The test procedures and results are described in qualifying the Honeywell solar collector subsystem. Testing began in mid-August 1976, and was concluded in late February 1977. Testing was done in the following areas: pressure, service loads, hail, solar degradation, pollutants, thermal degradation, and outgassing. Results from these tests are summarized.

Not Available

1977-02-01T23:59:59.000Z

126

Building Energy Simulation Test for Existing Homes (BESTEST-EX): Instructions for Implementing the Test Procedure, Calibration Test Reference Results, and Example Acceptance-Range Criteria  

Science Conference Proceedings (OSTI)

This publication summarizes building energy simulation test for existing homes (BESTEST-EX): instructions for implementing the test procedure, calibration tests reference results, and example acceptance-range criteria.

Judkoff, R.; Polly, B.; Bianchi, M.; Neymark, J.; Kennedy, M.

2011-08-01T23:59:59.000Z

127

Developing a standardized test procedure for hybrid vehicles: The challenge of the SAE HEV task force  

DOE Green Energy (OSTI)

In 1992, the Society of Automotive Engineers (SAE) established a task force to develop a procedure for measuring electric energy consumption, all-electric range, fuel economy, and exhaust emissions for hybrid vehicles; the procedure will be submitted to regulatory agencies as representing the automotive industry`s recommendations. The draft procedure is currently being tested on hybrid vehicles. The University of Maryland`s parallel hybrid was tested in September 1994, and the University of California-Davis` parallel hybrid and the University of Illinois` series hybrid will be tested in November 1994 and January 1995, respectively. The procedure is being modified to incorporate any lessons learned, and the task force hopes to recommend the final procedure to the SAE by mid 1995.

Penney, T; Christensen, D [National Renewable Energy Lab., Golden, CO (United States); Poulos, S [General Motors Corp., Warren, MI (United States)

1994-11-01T23:59:59.000Z

128

Novel Battery Testing Procedures and Analytical Methodologies for Hybrid Electric Vehicles  

SciTech Connect

The Idaho National Engineering and Environmental Laboratory has developed novel testing procedures and analytical methodologies to assess the performance of batteries for use in hybrid electric vehicles. Tests include both characterization and cycle life and/or calendar life. Tests have been designed for both Power Assist and Dual Mode applications. Analytical procedures include a battery scaling methodology, the calculation of pulse resistance, pulse power, available energy, and differential capacitance, and the modeling of calendar and cycle life data. At periodic intervals during life testing, a series of Reference Performance Tests are executed to determine changes in the baseline performance of the batteries.

Motloch, Chester George; Batt, J. R.; Christophersen, Jon Petter; Wright, Randy Ben; Hunt, Gary Lynn

2001-06-01T23:59:59.000Z

129

Supervisory Control and Data Acquisition System (SCADA) Substation C3-3 Acceptance Test Procedure  

Science Conference Proceedings (OSTI)

The purpose of this acceptance test procedure (ATP) is to demonstrate that the newly installed Supervisory Control and Data Acquisition (SCADA) computer system functions as intended by the design.

ZAKRAJSEK, M.F.

2000-10-17T23:59:59.000Z

130

Supervisory Control and Data Acquisition System (SCADA) Substation C3S4 Acceptance Test Procedure  

Science Conference Proceedings (OSTI)

The purpose of this acceptance test procedure (ATP) is to demonstrate that the newly installed Supervisory Control and Data Acquisition (SCADA) computer system functions as intended by the design.

ZAKRAJSEK, M.F.

2000-10-17T23:59:59.000Z

131

Solid-State Lighting: IESNA LM-80-08 - An Overview of the Test Procedure  

NLE Websites -- All DOE Office Websites (Extended Search)

IESNA LM-80-08 - An Overview IESNA LM-80-08 - An Overview of the Test Procedure and How it is Used for ENERGY STAR® to someone by E-mail Share Solid-State Lighting: IESNA LM-80-08 - An Overview of the Test Procedure and How it is Used for ENERGY STAR® on Facebook Tweet about Solid-State Lighting: IESNA LM-80-08 - An Overview of the Test Procedure and How it is Used for ENERGY STAR® on Twitter Bookmark Solid-State Lighting: IESNA LM-80-08 - An Overview of the Test Procedure and How it is Used for ENERGY STAR® on Google Bookmark Solid-State Lighting: IESNA LM-80-08 - An Overview of the Test Procedure and How it is Used for ENERGY STAR® on Delicious Rank Solid-State Lighting: IESNA LM-80-08 - An Overview of the Test Procedure and How it is Used for ENERGY STAR® on Digg Find More places to share Solid-State Lighting: IESNA LM-80-08 -

132

Interim test methods and procedures for determining the performance of small photovoltaic systems  

DOE Green Energy (OSTI)

This document provides test methods and procedures for determining the performance of small stand-alone and utility-grid connected PV systems. The procedures in this document provide a common approach for evaluating whether a given PV system is suitable to perform the function it was designed and manufactured to accomplish and meet the application load. This test document fills a testing void and provides the catalyst and focus for establishing the technical foundation and bridging the institutional barriers needed to reduce uncertainty that a system`s performance will be what its designers and builders claim. The need for this document was recently made more apparent with the initiation of a PV Global Approval Program (PVGAP) at the international level and is in response to concerns that PV systems being fielded must meet performance standards and that these standards include system-level performance type tests. The title of these test procedures is prefaced with the word interim because experience in using the procedures is needed before a consensus standard is developed and accepted by the PV community through its activities with the IEEE Standards Coordinating Committee 21 (SCC21) and International Electrotechnical Commission Technical Committee 82 (IEC TC82) national and international standards-making bodies. Both entities have initiated projects to develop test standards and will need the technical basis and validation of test procedures such as those presented in this document before a consensus is achieved by the PV community.

McNutt, P.; Kroposki, B.; Hansen, R.; DeBlasio, R.

1998-07-01T23:59:59.000Z

133

Using virtual reality and mood-induction procedures to test products with consumers of ceramic tiles  

Science Conference Proceedings (OSTI)

This work describes a Virtual Reality Environment (VRE), through which users are able to view and test ceramic tile products. Users' virtual interfacing with the products generated emotional experiences that allowed them to feel ''engaged'' with the ... Keywords: Consumers, Mood-induction procedures, Product testing, Relaxation, Sense of presence, Virtual reality

Berenice Serrano; Cristina Botella; Rosa M. BaOs; Mariano AlcaIz

2013-05-01T23:59:59.000Z

134

Round-robin testing of Soleq EV cort according to the SAE J1634 test procedure dated May 1993  

DOE Green Energy (OSTI)

The Society of Automotive Engineers Recommended Practice, SAE J1634, {open_quotes}Electric Vehicle Energy Consumption and Range Test Procedure{close_quotes}, May 1993, describes a standard method of determining the range and energy consumption for electric vehicles. Consequent to the U.S. Department of Energy`s (DOE) rulemaking released on February 4, 1994, the EPA is currently considering factoring electric vehicles into the Corporate Average Fuel Economy (CAFE) calculations using the SAE J1634 procedure. The purpose of this project is to provide information regarding the suitability of this recommended practice for determining the energy economy value to be factored into the CAFE. Issues leading to possible inconsistent results (such as the repeatability of the procedure, thoroughness of the procedure`s methods, and variance between different laboratories using different dynamometers) need to be resolved prior to passing legislation which will mandate use of this test in determining the electric vehicle CAFE credit. To this end, separate tests were performed on a Soleq EVcort vehicle by the INEL, the EPA, Ford Motor Company, Southwest Research Institute, and the California Air Resources Board using their own facilities and personnel. Acceptable departures from the driving profile prescribed by SAEJ1634 are not well defined. This deficiency in the procedure is even more noticeable due to the EVcort`s marginal acceleration performance.

Cole, G.H.

1993-05-01T23:59:59.000Z

135

Development of an Outdoor Concentrating Photovoltaic Module Testbed, Module Handling and Testing Procedures, and Initial Energy Production Results  

DOE Green Energy (OSTI)

This report addresses the various aspects of setting up a CPV testbed and procedures for handling and testing CPV modules.

Muller, M.

2009-09-01T23:59:59.000Z

136

Energy Efficiency Program for Certain Commercial and Industrial Equipment: Test Procedures for  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

6/2/11 6/2/11 Comments to the following DOE Proposed Rules: 10 CFR Part 431 [Docket No. EERE-2010-BT-TP-0036] RIN 1904-AC38 Energy Efficiency Program for Certain Commercial and Industrial Equipment: Test Procedures for Automatic Commercial Ice Makers Submitted by: Mary C. Howe, President, Howe Corporation, Chicago, IL 60642 mchowe@howecorp.com CORPORATION 1650 N Elston Ave * Chicago, IL. 60642 * (773) 235-0200 * Fax (773) 235-0269 * E-mail: howeinfo@howecorp.com 2 Item 1 - DOE also requests comment on the proposal that the use of amended test procedure be required upon the effective date of any test procedure final rule, 30 days after publication in the Federal Register. In the case of the addition of continuous production remote condenser ACIM's, the outside testing

137

Test procedures and instructions for single shell tank saltcake cesium removal with crystalline silicotitanate  

SciTech Connect

This document provides specific test procedures and instructions to implement the test plan for the preparation and conduct of a cesium removal test, using Hanford Single Shell Tank Saltcake from tanks 24 t -BY- I 10, 24 1 -U- 108, 24 1 -U- 109, 24 1 -A- I 0 1, and 24 t - S-102, in a bench-scale column. The cesium sorbent to be tested is crystalline siticotitanate. The test plan for which this provides instructions is WHC-SD-RE-TP-024, Hanford Single Shell Tank Saltcake Cesium Removal Test Plan.

Duncan, J.B.

1997-01-07T23:59:59.000Z

138

Information Resources: IESNA LM-80-08 - An Overview of the Test Procedure  

NLE Websites -- All DOE Office Websites (Extended Search)

IESNA LM-80-08 - An Overview of the Test Procedure and How it is Used for ENERGY STAR® IESNA LM-80-08 - An Overview of the Test Procedure and How it is Used for ENERGY STAR® This October 30, 2008 webcast provided an overview of LM-80-08, Approved Method for Measuring Lumen Maintenance of LED Light Sources, and how DOE's ENERGY STAR program for Solid-State Lighting (SSL) Luminaires will use LM-80 to estimate lifetime for qualified SSL Luminaires. Richard Karney, U.S. Department of Energy, began the webcast with the announcement that LM-80-08 is now available through IESNA. The test procedure can be purchased online through the IES store at https://www.ies.org/store/. Kevin Dowling, Chairman, Testing Procedures SSL Committee, presented on the specifics of the LM-80 test procedure and the changes reflected in the final version. Jeff McCullough, Pacific Northwest National Laboratory, went through an overview of how the results of LM-80 are used for the DOE ENERGY STAR SSL program.

139

Summary Report on Solid-oxide Electrolysis Cell Testing and Development  

DOE Green Energy (OSTI)

Idaho National Laboratory (INL) has been researching the application of solid-oxide electrolysis cells (SOECs) for large-scale hydrogen production from steam over a temperature range of 800 to 900 C. From 2003 to 2009, this work was sponsored by the United States Department of Energy Nuclear Hydrogen Initiative, under the Office of Nuclear Energy. Starting in 2010, the high-temperature electrolysis (HTE) research program has been sponsored by the INL Next Generation Nuclear Plant Project. This report provides a summaryof program activities performed in Fiscal Year (FY) 2011 and the first quarter of FY-12, with a focus on small-scale testing and cell development activities. HTE research priorities during this period have included the development and testing of SOEC and stack designs that exhibit high-efficiency initial performance and low, long-term degradation rates. This report includes contributions from INL and five industry partners: Materials and Systems Research, Incorporated (MSRI); Versa Power Systems, Incorporated (VPS); Ceramatec, Incorporated; National Aeronautics and Space Administration - Glenn Research Center (NASA - GRC); and the St. Gobain Advanced Materials Division. These industry partners have developed SOEC cells and stacks for in-house testing in the electrolysis mode and independent testing at INL. Additional fundamental research and post-test physical examinations have been performed at two university partners: Massachusetts Institute of Technology (MIT) and the University of Connecticut. Summaries of these activities and test results are also presented in this report.

J.E. O'Brien; X. Zhang; R.C. O'Brien; G.L. Hawkes

2012-01-01T23:59:59.000Z

140

Interim Test Procedures for Evaluating Electrical Performance and Grid Integration of Vehicle-to-Grid Applications  

NLE Websites -- All DOE Office Websites (Extended Search)

Interim Test Procedures for Interim Test Procedures for Evaluating Electrical Performance and Grid Integration of Vehicle-to-Grid Applications S. Chakraborty, W. Kramer, B. Kroposki, G. Martin, P. McNutt, M. Kuss, T. Markel, and A. Hoke Technical Report NREL/TP-5500-51001 June 2011 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency & Renewable Energy, operated by the Alliance for Sustainable Energy, LLC. National Renewable Energy Laboratory 1617 Cole Boulevard Golden, Colorado 80401 303-275-3000 * www.nrel.gov Contract No. DE-AC36-08GO28308 Interim Test Procedures for Evaluating Electrical Performance and Grid Integration of Vehicle-to-Grid Applications S. Chakraborty, W. Kramer, B. Kroposki, G. Martin, P. McNutt, M. Kuss, T. Markel,

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


141

A Functional Test Procedure for the improved commissioning of a VAV system  

E-Print Network (OSTI)

In the context of the IEA40 research project, a specification of a Functional Test Procedure was progressively developed using the CA-MET building in Namur as real size test bench for the application and validation of the procedure. The target system is a typical VAV system devoted to the ventilation, cooling and air conditioning functions. The procedure consists in a series of operations to be applied to the system, considered as a set of connected components and taking into account the following constraints: 1) time availability 2) intrinsic limitations of the system 3) reference performances. The proposed procedure is divided in two sets of actions: 1) a number of preliminary actions allowing to take the best benefit of the subsequent phases: a) identification of available measurement points b) identification of actuators characteristics c) identification of control strategies d) aeraulic network calculations e) selection of measurement techniques and experimental design 2) the verification tasks themselves: The philosophy of the verification process is to bring the system into a number of states which allowed each specific check to be carried out. The organisation of the procedure tries to optimize the time spent for commissioning by logically sequencing the operations according to the following order: 1) test in manual (ie not controlled by the BEMS) operation 2) test in manual (ie not controlled by the BEMS) stop 3) test in normal operation 4) test at maximum flowrate 5) test at minimum flowrate 6) test in automatic stop The paper will provide the specific operations to be carried out at each step and will illustrate the whole process with the prototyping work performed on the CA-MET building in Namur.

Andre, P.; Lacote, P.; Aparecida Silva, C.; Hannay, J.; Lebrun, J.

2004-01-01T23:59:59.000Z

142

PNGV Battery Testing Procedures and Analytical Methodologies for Hybrid Electric Vehicles  

SciTech Connect

Novel testing procedures and analytical methodologies to assess the performance of hybrid electric vehicle batteries have been developed. Tests include both characterization and cycle life and/or calendar life, and have been designed for both Power Assist and Dual Mode applications. Analytical procedures include a battery scaling methodology, the calculation of pulse resistance, pulse power, available energy, and differential capacity, and the modeling of calendar and cycle life data. Representative performance data and examples of the application of the analytical methodologies including resistance growth, power fade, and cycle and calendar life modeling for hybrid electric vehicle batteries are presented.

Motloch, Chester George; Belt, Jeffrey R; Christophersen, Jon Petter; Wright, Randy Ben; Hunt, Gary Lynn; Haskind, H. J.; Tartamella, T.; Sutula, R.

2002-06-01T23:59:59.000Z

143

Summary of TRUEX Radiolysis Testing Using the INL Radiolysis Test Loop  

Science Conference Proceedings (OSTI)

The INL radiolysis and hydrolysis test loop has been used to evaluate the effects of hydrolytic and radiolytic degradation upon the efficacy of the TRUEX flowsheet for the recovery of trivalent actinides and lanthanides from acidic solution. Repeated irradiation and subsequent re-conditioning cycles did result in a significant decrease in the concentration of the TBP and CMPO extractants in the TRUEX solvent and a corresponding decrease in americium and europium extraction distributions. However, the build-up of solvent degradation products upon {gamma}-irradiation, had little impact upon the efficiency of the stripping section of the TRUEX flowsheet. Operation of the TRUEX flowsheet would require careful monitoring to ensure extraction distributions are maintained at acceptable levels.

Dean R. Peterman; Lonnie G. Olson; Rocklan G. McDowell; Gracy Elias; Jack D. Law

2012-03-01T23:59:59.000Z

144

DOE response to questions from AHAM on the supplemental proposed test procedure  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

response to questions from AHAM on the supplemental proposed test procedure for response to questions from AHAM on the supplemental proposed test procedure for residential clothes washers"? (1) What exactly does the language in Part B mean and what is the intent? * The intent of Part B is to use the methodology that AHAM had suggested specifically for extra-hot cycles, but to make it more broadly applicable to any temperature combination that is locked out of the Normal cycle. * The proposed Part (B) language is meant to be consistent with GE's original suggestion in response to the NOPR. (GE, No. 15 at pp. 1-2) * When testing cycles under Part (B), manufacturers would only need to test the temperature combination that is locked out of the Normal cycle.

145

Settlement Agreement on TRU Mixed Waste Storage at Nevada Test Site Summary  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Settlement Agreement for Transuranic (TRU) Mixed Settlement Agreement for Transuranic (TRU) Mixed Waste Storage Issues at the Nevada Test Site (NTS) State Nevada Agreement Type Settlement Agreement Legal Driver(s) RCRA Scope Summary Settle the Finding of Alleged Violation (FOAV) and Order of November 1, 1990, and the FOAV of June 24, 1991, related to the TRU waste storage pad at Area 5 of the NTS Parties DOE; Nevada Department of Environmental Protection Date 6/11/1992 SCOPE * Settle the Finding of Alleged Violation (FOAV) and Order of November 1, 1990, and the FOAV of June 24, 1991, related to the TRU waste storage pad at Area 5 of the NTS. ESTABLISHING MILESTONES * Within 90 days of the effective date of this Agreement, DOE will provide to NDEP documentation of why the current inventory of TRU mixed waste cannot be removed

146

SOLERAS - Solar Cooling Engineering Field Tests Project. Final report. Volume 1. Project summary  

Science Conference Proceedings (OSTI)

The SOLERAS Project Summary - Final Report contains a synopsis of each completed project based on contractors final report. Additionally, a brief description of the limited testing completed by the SOLERAS staff on the collectors is included. SOLERAS comments or opinions expressed in the report are solely based on experiences with the SOLERAS Installations. It must be recognized that many product improvements and design modifications have been made since installation completion, many of which are the result of SOLERAS experience. The last chapter of this report is a synopsis of suggested new research areas for the solar cooling program. These suggestions were made by the participants of the cooling workshop held in Phoenix, Arizona in August 1984.

Not Available

1986-01-01T23:59:59.000Z

147

Interim qualification tests and procedures for terrestrial photovoltaic thin-film flat-plate modules  

DOE Green Energy (OSTI)

This document provides recommended procedures and specifications for qualification tests that are structured to evaluate terrestrial thin-film flat-plate photovoltaic nonconcentrating modules intended for power generation applications. The qualification tests provided in this document are designed to evaluate flat-plate thin-film photovoltaic (PV) module design performance and susceptibility to known failure mechanisms. Emphasis is placed on testing and evaluating module performance characteristics and design features that will affect possible degradation of module performance and physical properties resulting from solar exposure, environmental weathering, mechanical loading, corrosion, and module shadowing. Because of limited thin-film module field operation experience and the evolutionary nature of new thin-film module material technologies and designs, these tests should not be considered definitive or complete, nor do they provide a basis to predict 30-year field life. Current understanding of failure and degradation mechanisms and the relationship between accelerated tests and field reliability is not sufficient to allow accurate estimation of life-expectancy, nor are the cycling tests given in this document considered to be equivalent to a full 30-year field exposure. However, the test and evaluation procedures given in this document provide a common approach for conducting qualification tests. Acceptable results from these tests should provide reasonable assurance that the modules that pass these tests will perform reliably in the field but for an unspecified period of time. 8 refs., 6 figs.

DeBlasio, R.; Mrig, L.; Waddington, D.

1990-01-01T23:59:59.000Z

148

Fire Safety Tests for Cesium-Loaded Spherical Resorcinol Formaldehyde Resin: Data Summary Report  

SciTech Connect

A draft safety evaluation of the scenario for spherical resorcinol formaldehyde (SRF) resin fire inside the ion exchange column was performed by the Hanford Tank Waste Treatment and Immobilization Plant (WTP) Fire Safety organization. The result of this draft evaluation suggested a potential change of the fire safety classification for the Cesium Ion Exchange Process System (CXP) emergency elution vessels, equipment, and piping. To resolve this question, the fire properties of the SRF resin were measured by Southwest Research Institute (SwRI) through a subcontract managed by Pacific Northwest National Laboratory (PNNL). The results of initial fire safety tests on the SRF resin were documented in a previous report (WTP-RPT-218). The present report summarizes the results of additional tests performed by SwRI on the cesium-loaded SRF resin. The efforts by PNNL were limited to summarizing the test results provided by SwRI into one consolidated data report. The as-received SwRI report is attached to this report in the Appendix A. Where applicable, the precision and bias of each test method, as given by each American Society for Testing and Materials (ASTM) standard procedure, are included and compared with the SwRI test results of the cesium-loaded SRF resin.

Kim, Dong-Sang; Schweiger, Michael J.; Peterson, Reid A.

2012-09-01T23:59:59.000Z

149

IN SITU DECOMMISSIONING SENSOR NETWORK, MESO-SCALE TEST BED - PHASE 3 FLUID INJECTION TEST SUMMARY REPORT  

SciTech Connect

The DOE Office of Environmental management (DOE EM) faces the challenge of decommissioning thousands of excess nuclear facilities, many of which are highly contaminated. A number of these excess facilities are massive and robust concrete structures that are suitable for isolating the contained contamination for hundreds of years, and a permanent decommissioning end state option for these facilities is in situ decommissioning (ISD). The ISD option is feasible for a limited, but meaningfull number of DOE contaminated facilities for which there is substantial incremental environmental, safety, and cost benefits versus alternate actions to demolish and excavate the entire facility and transport the rubble to a radioactive waste landfill. A general description of an ISD project encompasses an entombed facility; in some cases limited to the blow-grade portion of a facility. However, monitoring of the ISD structures is needed to demonstrate that the building retains its structural integrity and the contaminants remain entombed within the grout stabilization matrix. The DOE EM Office of Deactivation and Decommissioning and Facility Engineering (EM-13) Program Goal is to develop a monitoring system to demonstrate long-term performance of closed nuclear facilities using the ISD approach. The Savannah River National Laboratory (SRNL) has designed and implemented the In Situ Decommissioning Sensor Network, Meso-Scale Test Bed (ISDSN-MSTB) to address the feasibility of deploying a long-term monitoring system into an ISD closed nuclear facility. The ISDSN-MSTB goal is to demonstrate the feasibility of installing and operating a remote sensor network to assess cementitious material durability, moisture-fluid flow through the cementitious material, and resulting transport potential for contaminate mobility in a decommissioned closed nuclear facility. The original ISDSN-MSTB installation and remote sensor network operation was demonstrated in FY 2011-12 at the ISDSN-MSTB test cube located at the Florida International University Applied Research Center, Miami, FL (FIU-ARC). A follow-on fluid injection test was developed to detect fluid and ion migration in a cementitious material/grouted test cube using a limited number of existing embedded sensor systems. This In Situ Decommissioning Sensor Network, Meso-Scale Test Bed (ISDSN-MSTB) - Phase 3 Fluid Injection Test Summary Report summarizes the test implementation, acquired and processed data, and results from the activated embedded sensor systems used during the fluid injection test. The ISDSN-MSTB Phase 3 Fluid Injection Test was conducted from August 27 through September 6, 2013 at the FIU-ARC ISDSN-MSTB test cube. The fluid injection test activated a portion of the existing embedded sensor systems in the ISDSN-MSTB test cube: Electrical Resistivity Tomography-Thermocouple Sensor Arrays, Advance Tensiometer Sensors, and Fiber Loop Ringdown Optical Sensors. These embedded sensor systems were activated 15 months after initial placement. All sensor systems were remotely operated and data acquisition was completed through the established Sensor Remote Access System (SRAS) hosted on the DOE D&D Knowledge Management Information Tool (D&D DKM-IT) server. The ISDN Phase 3 Fluid Injection Test successfully demonstrated the feasibility of embedding sensor systems to assess moisture-fluid flow and resulting transport potential for contaminate mobility through a cementitious material/grout monolith. The ISDSN embedded sensor systems activated for the fluid injection test highlighted the robustness of the sensor systems and the importance of configuring systems in-depth (i.e., complementary sensors and measurements) to alleviate data acquisition gaps.

Serrato, M.

2013-09-27T23:59:59.000Z

150

Evaluation of fine-particle size catalysts using standard test procedures  

SciTech Connect

The goal of this project is to evaluate and compare the activities/selectivities of fine-particle size catalysts being developed in the DOE/PETC Advanced Research (AR) Liquefaction Program by using standard coal liquefaction activity test procedures. Since bituminous and subbituminous coals have significantly different properties, it is feasible that catalysts may perform differently with these coal types. Because all previous testing has been done with the DECS-17 Blind Canyon bituminous coal, it is important to develop the capability of evaluating catalysts using a subbituminous coal. Initial efforts towards developing a subbituminous coal test are aimed at comparing the reactivities of the Wyodak subbituminous coal and the Blind Canyon bituminous coal. Therefore, the same factorial experimental design was used with the Wyodak coal as was used previously with the Blind Canyon coal. In addition, PNL`s 6-line ferrihydrite catalyst precursor was used in the development of the Wyodak coal test procedure because this catalyst is the best powder catalyst found to date in Sandia`s tests with Blind Canyon coal. Results show that Blind Canyon coal yields higher DHP amounts in the reaction products and higher tetrahydrofuran conversions at the higher severity conditions. Wyodak coal gives higher heptane conversions and higher gas yields for all conditions tested.

Stohl, F.V.; Diegert, K.V.; Goodnow, D.C.

1996-07-01T23:59:59.000Z

151

Sampling and Analysis Procedures for Gas, Condensate, Brine, and Solids: Pleasant Bayou Well Test, 1988-Present  

Science Conference Proceedings (OSTI)

This section covers analyses performed on gas. Chemical analyses can only be related to well performance if the quantity of the various fluids are known. The IGT on-line data computer system measures the flowrate, the pressures, and the temperatures every 10 seconds. These values are automatically recorded over operator selected intervals both on magnetic media and on paper. This allows review of samples versus operating conditions. This paper covers analyses performed on gas, including: An approximate sampling schedule during flow tests; On-site sample handling and storage of gas samples; Addresses of laboratories that perform off site analyses; Sample shipping instructions; Data archiving; and Quality Control/Quality Assurance. It is expected that the above procedures will change as the flow test progresses, but deviations from the written procedures should be approved by C. Hayden of IGT and noted on the results of the analysis.

Hayden, Chris

1988-01-01T23:59:59.000Z

152

Summary of Group Development and Testing for Single Shell Tank Closure at Hanford  

Science Conference Proceedings (OSTI)

This report is a summary of the bench-scale and large scale experimental studies performed by Savannah River National Laboratory for CH2M HILL to develop grout design mixes for possible use in producing fill materials as a part of Tank Closure of the Single-Shell Tanks at Hanford. The grout development data provided in this report demonstrates that these design mixes will produce fill materials that are ready for use in Hanford single shell tank closure. The purpose of this report is to assess the ability of the proposed grout specifications to meet the current requirements for successful single shell tank closure which will include the contracting of services for construction and operation of a grout batch plant. The research and field experience gained by SRNL in the closure of Tanks 17F and 20F at the Savannah River Site was leveraged into the grout development efforts for Hanford. It is concluded that the three Hanford grout design mixes provide fill materials that meet the current requirements for successful placement. This conclusion is based on the completion of recommended testing using Hanford area materials by the operators of the grout batch plant. This report summarizes the regulatory drivers and the requirements for grout mixes as tank fill material. It is these requirements for both fresh and cured grout properties that drove the development of the grout formulations for the stabilization, structural and capping layers.

Harbour, John, R.

2005-04-28T23:59:59.000Z

153

Proposal for a Vehicle Level Test Procedure to Measure Air Conditioning Fuel Use  

SciTech Connect

The air-conditioning (A/C) compressor load significantly impacts the fuel economy of conventional vehicles and the fuel use/range of plug-in hybrid electric vehicles (PHEV). A National Renewable Energy Laboratory (NREL) vehicle performance analysis shows the operation of the air conditioner reduces the charge depletion range of a 40-mile range PHEV from 18% to 30% in a worst case hot environment. Designing for air conditioning electrical loads impacts PHEV and electric vehicle (EV) energy storage system size and cost. While automobile manufacturers have climate control procedures to assess A/C performance, and the U.S. EPA has the SCO3 drive cycle to measure indirect A/C emissions, there is no automotive industry consensus on a vehicle level A/C fuel use test procedure. With increasing attention on A/C fuel use due to increased regulatory activities and the development of PHEVs and EVs, a test procedure is needed to accurately assess the impact of climate control loads. A vehicle thermal soak period is recommended, with solar lamps that meet the SCO3 requirements or an alternative heating method such as portable electric heaters. After soaking, the vehicle is operated over repeated drive cycles or at a constant speed until steady-state cabin air temperature is attained. With this method, the cooldown and steady-state A/C fuel use are measured. This method can be run at either different ambient temperatures to provide data for the GREEN-MAC-LCCP model temperature bins or at a single representative ambient temperature. Vehicles with automatic climate systems are allowed to control as designed, while vehicles with manual climate systems are adjusted to approximate expected climate control settings. An A/C off test is also run for all drive profiles. This procedure measures approximate real-world A/C fuel use and assess the impact of thermal load reduction strategies.

Rugh, J. P.

2010-04-01T23:59:59.000Z

154

Building Energy Simulation Test for Existing Homes (BESTEST-EX): Instructions for Implementing the Test Procedure, Calibration Test Reference Results, and Example Acceptance-Range Criteria  

NLE Websites -- All DOE Office Websites (Extended Search)

Building Energy Simulation Test for Building Energy Simulation Test for Existing Homes (BESTEST-EX): Instructions for Implementing the Test Procedure, Calibration Test Reference Results, and Example Acceptance-Range Criteria Ron Judkoff, Ben Polly, and Marcus Bianchi National Renewable Energy Laboratory Joel Neymark J. Neymark & Associates Mike Kennedy Mike D. Kennedy, Inc. Link to Accompanying Zipped Data Files (3.9 MB) This document is intended for use with the following documents: Building Energy Simulation Test for Existing Homes (BESTEST-EX), NREL/TP-550-47427 Example Procedures for Developing Acceptance-Range Criteria for BESTEST-EX, NREL/TP-550-47502 Technical Report NREL/TP-5500-52414 August 2011 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy

155

Field Testing of Energy-Efficient Flood-Damage-Resistant Residential Envelope Systems Summary Report  

SciTech Connect

The primary purpose of the project was to identify materials and methods that will make the envelope of a house flood damage resistant. Flood damage resistant materials and systems are intended to be used to repair houses subsequent to flooding. This project was also intended to develop methods of restoring the envelopes of houses that have been flooded but are repairable and may be subject to future flooding. Then if the house floods again, damage will not be as extensive as in previous flood events and restoration costs and efforts will be minimized. The purpose of the first pair of field tests was to establish a baseline for typical current residential construction practice. The first test modules used materials and systems that were commonly found in residential envelopes throughout the U.S. The purpose of the second pair of field tests was to begin evaluating potential residential envelope materials and systems that were projected to be more flood-damage resistant and restorable than the conventional materials and systems tested in the first pair of tests. The purpose of testing the third slab-on-grade module was to attempt to dry flood proof the module (no floodwater within the structure). If the module could be sealed well enough to prevent water from entering, then this would be an effective method of making the interior materials and systems flood damage resistant. The third crawl space module was tested in the same manner as the previous modules and provided an opportunity to do flood tests of additional residential materials and systems. Another purpose of the project was to develop the methodology to collect representative, measured, reproducible (i.e. scientific) data on how various residential materials and systems respond to flooding conditions so that future recommendations for repairing flood damaged houses could be based on scientific data. An additional benefit of collecting this data is that it will be used in the development of a standard test procedure which could lead to the certification of building materials and systems as flood damage resistant.

Aglan, H.

2005-08-04T23:59:59.000Z

156

Measurements and calculations on the simple up-down adaptive procedure for speech-in-noise tests  

Science Conference Proceedings (OSTI)

The simple up-down adaptive procedure is a common method for measuringspeech reception thresholds. It is used by the Dutch speech-in-noise telephone screening test [National Hearing test; Smits and Houtgast Ear Hear.26

Cas Smits; Tammo Houtgast

2006-01-01T23:59:59.000Z

157

Using the Bootstrap Method for a Statistical Significance Test of Differences between Summary Histograms  

Science Conference Proceedings (OSTI)

A new method is proposed to compare statistical differences between summary histograms, which are the histograms summed over a large ensemble of individual histograms. It consists of choosing a distance statistic for measuring the difference ...

Kuan-Man Xu

2006-05-01T23:59:59.000Z

158

Test Procedure for 170.306 (d)(2) Electronic Copy of Health ...  

Science Conference Proceedings (OSTI)

... the capability to create a copy of a patient's discharge summary in human ... to her ankle after an episode of syncope with no loss of consciousness. ...

2010-09-24T23:59:59.000Z

159

A Comparison of WD-EPMA Heterogeneity Testing ...  

Science Conference Proceedings (OSTI)

A Comparison of WD-EPMA Heterogeneity Testing Procedures. Summary: The heterogeneity of the four elements in a TiAl ...

2012-10-02T23:59:59.000Z

160

Testing and sampling procedures for geothermal-compressured wells. Final report  

DOE Green Energy (OSTI)

Test wells to tap and sample geothermal-geopressured formations at 15,000 to 20,000 feet in the Gulf Coast area can be drilled routinely utilizing available equipment and methods. Electrical logs, surveys and fluid samplers can be used to obtain accurate and reliable information as to depths, temperatures, pressures, and fluid content of the geopressured formations before the well is completed. But it will be necessary to set casing and flow the well, at least temporarily, to secure fluid production volume and pressure data to evaluate the producibility of the geopressured resource. Electric logging and wireline survey methods are fully developed techniques for measuring the parameters needed to assess a geopressured zone before setting casing. Formation subsidence, though it may be slow to develop, can be measured during radioactivity tracer surveys. The following conclusions are drawn: existing well logging and surveying methods and equipment are generally satisfactory for testing and sampling a geothermal-geopressured resource; no significant areas of research are needed to predict, detect, and evaluate geopressured formations for their potential as geothermal resources. Static and dynamic testing procedures using existing technology are satisfactory to test, sample, and analyze a geopressured reservoir.

Boyd, W.E.

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


161

Alternative Fuel Evaluation Program: Alternative Fuel Light Duty Vehicle Project - Data collection responsibilities, techniques, and test procedures  

DOE Green Energy (OSTI)

This report describes the data gathering and analysis procedures that support the US Department of Energy's implementation of the Alternative Motor Fuels Act (AMFA) of 1988. Specifically, test procedures, analytical methods, and data protocols are covered. The aim of these collection and analysis efforts, as mandated by AMFA, is to demonstrate the environmental, economic, and performance characteristics of alternative transportation fuels.

Not Available

1992-07-01T23:59:59.000Z

162

Alternative Fuel Evaluation Program: Alternative Fuel Light Duty Vehicle Project - Data collection responsibilities, techniques, and test procedures  

DOE Green Energy (OSTI)

This report describes the data gathering and analysis procedures that support the US Department of Energy`s implementation of the Alternative Motor Fuels Act (AMFA) of 1988. Specifically, test procedures, analytical methods, and data protocols are covered. The aim of these collection and analysis efforts, as mandated by AMFA, is to demonstrate the environmental, economic, and performance characteristics of alternative transportation fuels.

Not Available

1992-07-01T23:59:59.000Z

163

Grid Interconnection and Performance Testing Procedures for Vehicle-To-Grid (V2G) Power Electronics: Preprint  

DOE Green Energy (OSTI)

Bidirectional power electronics can add vehicle-to-grid (V2G) capability in a plug-in vehicle, which then allows the vehicle to operate as a distributed resource (DR). The uniqueness of the battery-based V2G power electronics requires a test procedure that will not only maintain IEEE interconnection standards, but can also evaluate the electrical performance of the vehicle working as a DR. The objective of this paper is to discuss a recently published NREL technical report that provides interim test procedures for V2G vehicles for their integration into the electrical distribution systems and for their performance in terms of continuous output power, efficiency, and losses. Additionally, some other test procedures are discussed that are applicable to a V2G vehicle that desires to provide power reserve functions. A few sample test results are provided based on testing of prototype V2G vehicles at NREL.

Kramer, W.; Chakraborty, S.; Kroposki, B.; Hoke, A.; Martin, G.; Markel, T.

2012-03-01T23:59:59.000Z

164

DATA SUMMARY REPORT SMALL SCALE MELTER TESTING OF HLW ALGORITHM GLASSES MATRIX1 TESTS VSL-07S1220-1 REV 0 7/25/07  

SciTech Connect

Eight tests using different HLW feeds were conducted on the DM100-BL to determine the effect of variations in glass properties and feed composition on processing rates and melter conditions (off-gas characteristics, glass processing, foaming, cold cap, etc.) at constant bubbling rate. In over seven hundred hours of testing, the property extremes of glass viscosity, electrical conductivity, and T{sub 1%}, as well as minimum and maximum concentrations of several major and minor glass components were evaluated using glass compositions that have been tested previously at the crucible scale. Other parameters evaluated with respect to glass processing properties were +/-15% batching errors in the addition of glass forming chemicals (GFCs) to the feed, and variation in the sources of boron and sodium used in the GFCs. Tests evaluating batching errors and GFC source employed variations on the HLW98-86 formulation (a glass composition formulated for HLW C-106/AY-102 waste and processed in several previous melter tests) in order to best isolate the effect of each test variable. These tests are outlined in a Test Plan that was prepared in response to the Test Specification for this work. The present report provides summary level data for all of the tests in the first test matrix (Matrix 1) in the Test Plan. Summary results from the remaining tests, investigating minimum and maximum concentrations of major and minor glass components employing variations on the HLW98-86 formulation and glasses generated by the HLW glass formulation algorithm, will be reported separately after those tests are completed. The test data summarized herein include glass production rates, the type and amount of feed used, a variety of measured melter parameters including temperatures and electrode power, feed sample analysis, measured glass properties, and gaseous emissions rates. More detailed information and analysis from the melter tests with complete emission chemistry, glass durability, and melter operating details will be provided in the final report. A summary of the tests that were conducted is provided in Table 1. Each of the seven tests was of nominally one hundred hours in duration. Test B was conducted in two equal segments: the first with nominal additives, and the second with the replacement of borax with a mixture of boric acid and soda ash to determine the effect of alternative OPC sources on production rates and processing characteristics. Interestingly, sugar additions were required near mid points of Tests W and Z to reduce excessive foaming that severely limited feed processing rates. The sugar additions were very effective in recovering manageable processing conditions, albeit over the relatively short remainder of the test duration. Tests W and Z employed the highest melt viscosities but not by a particularly wide margin. Other tests, which did not exhibit such foaming Issues, employed higher concentrations of manganese or iron or both. These results highlight the need for the development of protocols for the a priori determination of which HLW feeds will require sugar additions and the appropriate amounts of sugar to be added in order to control foaming (and maintain throughput) without over-reduction of the melt (which could lead to molten metal formation). In total, over 8,800 kg of feed was processed to produce over 3200 kg of glass. Steady-state processing rates were achieved, and no secondary sulfate phases were observed during any of the tests. Analysis was performed on samples of the glass product taken throughout the tests to verify composition and properties. Sampling and analysis was also performed on melter exhaust to determine the effect of the feed and glass changes on melter emissions.

KRUGER AA; MATLACK KS; PEGG IL

2011-12-29T23:59:59.000Z

165

Brief summary of reactor core component welding for the Fast Flux Test Facility (FFTF)  

SciTech Connect

Included are descriptions of welding methods and joint design, welding equipment, and qualification tests. (DG)

Brown, W.F.

1974-04-15T23:59:59.000Z

166

Summary Report on FY12 Small-Scale Test Activities High Temperature Electrolysis Program  

SciTech Connect

This report provides a description of the apparatus and the single cell testing results performed at Idaho National Laboratory during JanuaryAugust 2012. It is an addendum to the Small-Scale Test Report issued in January 2012. The primary program objectives during this time period were associated with design, assembly, and operation of two large experiments: a pressurized test, and a 4 kW test. Consequently, the activities described in this report represent a much smaller effort.

James O'Brien

2012-09-01T23:59:59.000Z

167

Functional test procedure, Fifth Wheel: SS-R42351, Issue D  

SciTech Connect

This report describes the equipment required for initial assembly/maintenance and inspection/resetting of the Fifth Wheel system. It also gives a step-by-step procedure for initial assembly/maintenance inspection and procedures for resetting the system and Eager-Pac installation. The Fifth Wheel system is associated with a tractor-type vehicle used for materials handling.

1994-07-12T23:59:59.000Z

168

Spent fuel sabotage aerosol ratio program : FY 2004 test and data summary.  

Science Conference Proceedings (OSTI)

This multinational, multi-phase spent fuel sabotage test program is quantifying the aerosol particles produced when the products of a high energy density device (HEDD) interact with and explosively particulate test rodlets that contain pellets of either surrogate materials or actual spent fuel. This program has been underway for several years. This program provides data that are relevant to some sabotage scenarios in relation to spent fuel transport and storage casks, and associated risk assessments. The program also provides significant technical and political benefits in international cooperation. We are quantifying the Spent Fuel Ratio (SFR), the ratio of the aerosol particles released from HEDD-impacted actual spent fuel to the aerosol particles produced from surrogate materials, measured under closely matched test conditions, in a contained test chamber. In addition, we are measuring the amounts, nuclide content, size distribution of the released aerosol materials, and enhanced sorption of volatile fission product nuclides onto specific aerosol particle size fractions. These data are the input for follow-on modeling studies to quantify respirable hazards, associated radiological risk assessments, vulnerability assessments, and potential cask physical protection design modifications. This document includes an updated description of the test program and test components for all work and plans made, or revised, during FY 2004. It also serves as a program status report as of the end of FY 2004. All available test results, observations, and aerosol analyses plus interpretations--primarily for surrogate material Phase 2 tests, series 2/5A through 2/9B, using cerium oxide sintered ceramic pellets are included. Advanced plans and progress are described for upcoming tests with unirradiated, depleted uranium oxide and actual spent fuel test rodlets. This spent fuel sabotage--aerosol test program is coordinated with the international Working Group for Sabotage Concerns of Transport and Storage Casks (WGSTSC) and supported by both the U.S. Department of Energy and the Nuclear Regulatory Commission.

Brucher, Wenzel (Gesellschaft fur Anlagen- und Reaktorsicherheit, Germany); Koch, Wolfgang (Fraunhofer Institut fur Toxikologie und Experimentelle Medizin, Germany); Pretzsch, Gunter Guido (Gesellschaft fur Anlagen- und Reaktorsicherheit, Germany); Loiseau, Olivier (Institut de Radioprotection et de Surete Nucleaire, France); Mo, Tin (U.S. Nuclear Regulatory Commission, Washington, DC); Billone, Michael C. (Argonne National Laboratory, Argonne, IL); Autrusson, Bruno A. (Institut de Radioprotection et de Surete Nucleaire, France); Young, F. I. (U.S. Nuclear Regulatory Commission, Washington, DC); Coats, Richard Lee; Burtseva, Tatiana (Argonne National Laboratory, Argonne, IL); Luna, Robert Earl; Dickey, Roy R.; Sorenson, Ken Bryce; Nolte, Oliver (Fraunhofer Institut fur Toxikologie und Experimentelle Medizin, Germany); Thompson, Nancy Slater (U.S. Department of Energy, Washington, DC); Hibbs, Russell S. (U.S. Department of Energy, Washington, DC); Gregson, Michael Warren; Lange, Florentin (Gesellschaft fur Anlagen- und Reaktorsicherheit, Germany); Molecke, Martin Alan; Tsai, Han-Chung (Argonne National Laboratory, Argonne, IL)

2005-07-01T23:59:59.000Z

169

Process Knowledge Summary Report for Advanced Test Reactor Complex Contact-Handled Transuranic Waste Drum TRA010029  

SciTech Connect

This Process Knowledge Summary Report summarizes information collected to satisfy the transportation and waste acceptance requirements for the transfer of one drum containing contact-handled transuranic (TRU) actinide standards generated by the Idaho National Laboratory at the Advanced Test Reactor (ATR) Complex to the Advanced Mixed Waste Treatment Project (AMWTP) for storage and subsequent shipment to the Waste Isolation Pilot Plant for final disposal. The drum (i.e., Integrated Waste Tracking System Bar Code Number TRA010029) is currently stored at the Materials and Fuels Complex. The information collected includes documentation that addresses the requirements for AMWTP and applicable sections of their Resource Conservation and Recovery Act permits for receipt and disposal of this TRU waste generated from ATR. This Process Knowledge Summary Report includes information regarding, but not limited to, the generation process, the physical form, radiological characteristics, and chemical contaminants of the TRU waste, prohibited items, and packaging configuration. This report, along with the referenced supporting documents, will create a defensible and auditable record for this TRU waste originating from ATR.

B. R. Adams; R. P. Grant; P. R. Smith; J. L. Weisgerber

2013-09-01T23:59:59.000Z

170

Proposal for a Vehicle Level Test Procedure to Measure Air Conditioning Fuel Use: Preprint  

DOE Green Energy (OSTI)

A procedure is described to measure approximate real-world air conditioning fuel use and assess the impact of thermal load reduction strategies in plug-in hybrid electric vehicles.

Rugh, J.

2010-02-01T23:59:59.000Z

171

Biomass Cofiring: Field Test Results: Summary of Results at the Bailly and Seward Demonstrations  

Science Conference Proceedings (OSTI)

Cofiring, the simultaneous combustion of two dissimilar fuels in a given boiler, is a technology being considered for low-cost, low-risk use of biomass by electricity generating companies. The process of commercializing cofiring has proceeded from engineering studies through parametric tests to longer-term demonstrations. This report summarizes the results of those demonstrations to date, placing them in the context of the previous test programs.

1999-11-01T23:59:59.000Z

172

Photogrammetry and Laser Imagery Tests for Tank Waste Volume Estimates: Summary Report  

SciTech Connect

Feasibility tests were conducted using photogrammetry and laser technologies to estimate the volume of waste in a tank. These technologies were compared with video Camera/CAD Modeling System (CCMS) estimates; the current method used for post-retrieval waste volume estimates. This report summarizes test results and presents recommendations for further development and deployment of technologies to provide more accurate and faster waste volume estimates in support of tank retrieval and closure.

Field, Jim G. [Washington River Protection Solutions, LLC, Richland, WA (United States)

2013-03-27T23:59:59.000Z

173

Deviation to the Test Program and Procedures for the 710 Critical Experiment Reactor Control Drum Mockup Experiment  

SciTech Connect

This document describes a deviation from the "Test Program and Procedures for the 710 Critical Experiment Reactor Control Drum Mockup Experiment," TM-64-3-706, which was made in accordance with ITS Standard Practice J80-81 on September 14, 1964. The deviation did not involve a significant change in the safety of the operation.

Sims, F.L.

1964-09-14T23:59:59.000Z

174

10 MWe solar pilot plant, Daggett, California. Flushing and steam blows preoperational test procedure 980. Revision: 0  

Science Conference Proceedings (OSTI)

Prescribed steps are given for flushing and steam blowing the condenser hotwell, deaerator, inline demineralizers, thermal storage subsystem flash tank, and steam lines of the Barstow Solar Pilot Plant. Included are acceptance criteria, precautions, a list of test equipment, initial conditions, procedures and data collection, and system restoration. (LEW)

Williams, D.L.

1980-01-01T23:59:59.000Z

175

Interim Test Procedures for Evaluating Electrical Performance and Grid Integration of Vehicle-to-Grid Applications  

DOE Green Energy (OSTI)

The objective of this report is to provide a test plan for V2G testing. The test plan is designed to test and evaluate the vehicle's power electronics capability to provide power to the grid, and to evaluate the vehicle's ability to connect and disconnect from the utility according to a subset of the IEEE Std. 1547 tests.

Chakraborty, S.; Kramer, W.; Kroposki, B.; Martin, G.; McNutt, P.; Kuss, M.; Markel, T.; Hoke, A.

2011-06-01T23:59:59.000Z

176

DIRECT CONTACT HEAT EXCHANGER 10 kW POWER LOOP. SECTION 1: EXECUTIVE SUMMARY. SECTION 2: TEST SERIES NO. 1. SECTION 3; TEST SERIES NO. 2  

E-Print Network (OSTI)

Air Tests . . . . . . . . . . . . . . . . . . . . . LOOPCALIBRATION TESTS . . . . . . . . . . . . . . . . . . .ENDURANCE TEST . . . . . . . . . . . .

Engineering, Barber-Nicholas

2011-01-01T23:59:59.000Z

177

Advanced Vehicle Testing Activity: Dodge Ram Wagon Van -- Hydrogen/CNG Operations Summary  

DOE Green Energy (OSTI)

Over the past two years, Arizona Public Service, a subsidiary of Pinnacle West Capital Corporation, in cooperation with the U.S. Department of Energys Advanced Vehicle Testing Activity, tested four gaseous fuel vehicles as part of its alternative fueled vehicle fleet. One vehicle, a Dodge Ram Wagon Van, operated initially using compressed natural gas (CNG) and later a blend of CNG and hydrogen. Of the other three vehicles, one was fueled with pure hydrogen and two were fueled with a blend of CNG and hydrogen. The three blended-fuel vehicles were originally equipped with either factory CNG engines or factory gasoline engines that were converted to run CNG fuel. The vehicles were variously modified to operate on blended fuel and were tested using 15 to 50% blends of hydrogen (by volume). The pure-hydrogen-fueled vehicle was converted from gasoline fuel to operate on 100% hydrogen. All vehicles were fueled from the Arizona Public Services Alternative Fuel Pilot Plant, which was developed to dispense gaseous fuels, including CNG, blends of CNG and hydrogen, and pure hydrogen with up to 99.9999% purity. The primary objective of the test was to evaluate the safety and reliability of operating vehicles on hydrogen and blended hydrogen fuel, and the interface between the vehicles and the hydrogen fueling infrastructure. A secondary objective was to quantify vehicle emissions, cost, and performance. Over a total of 40,000 fleet test miles, no safety issues were found. Also, significant reductions in emissions were achieved by adding hydrogen to the fuel. This report presents results of 22,816 miles of testing for the Dodge Ram Wagon Van, operating on CNG fuel, and a blended fuel of 15% hydrogen85% CNG.

Don Karner; Francfort, James Edward

2003-01-01T23:59:59.000Z

178

Advanced Vehicle Testing Activity: Dodge Ram Wagon Van - Hydrogen/CNG Operations Summary - January 2003  

Science Conference Proceedings (OSTI)

Over the past two years, Arizona Public Service, a subsidiary of Pinnacle West Capital Corporation, in cooperation with the U.S. Department of Energy's Advanced Vehicle Testing Activity, tested four gaseous fuel vehicles as part of its alternative fueled vehicle fleet. One vehicle, a Dodge Ram Wagon Van, operated initially using compressed natural gas (CNG) and later a blend of CNG and hydrogen. Of the other three vehicles, one was fueled with pure hydrogen and two were fueled with a blend of CNG and hydrogen. The three blended-fuel vehicles were originally equipped with either factory CNG engines or factory gasoline engines that were converted to run CNG fuel. The vehicles were variously modified to operate on blended fuel and were tested using 15 to 50% blends of hydrogen (by volume). The pure-hydrogen-fueled vehicle was converted from gasoline fuel to operate on 100% hydrogen. All vehicles were fueled from the Arizona Public Service's Fuel Pilot Plant, which was developed to dispense gaseous fuels, including CNG, blends of CNG and hydrogen, and pure hydrogen with up to 99.9999% purity. The primary objective of the test was to evaluate the safety and reliability of operating vehicles on hydrogen and blended hydrogen fuel, and the interface between the vehicles and the hydrogen fueling infrastructure. A secondary objective was to quantify vehicle emissions, cost, and performance. Over a total of 40,000 fleet test miles, no safety issues were found. Also, significant reductions in emissions were achieved by adding hydrogen to the fuel. This report presents results of 22,816 miles of testing for the Dodge Ram Wagon Van, operating on CNG fuel, and a blended fuel of 15% hydrogen-85% CNG.

Karner, D.; Francfort, J.E.

2003-01-16T23:59:59.000Z

179

Advanced Vehicle Testing Activity: Hydrogen-Fueled Mercedes Sprinter Van -- Operating Summary  

DOE Green Energy (OSTI)

Over the past two years, Arizona Public Service, a subsidiary of Pinnacle West Capital Corporation, in cooperation with the U.S. Department of Energy's Advanced Vehicle Testing Activity, tested four gaseous fuel vehicles as part of its alternative fueled vehicle fleet. One vehicle operated initially using compressed natural gas (CNG) and later a blend of CNG and hydrogen. Of the other three vehicles, one was fueled with pure hydrogen and two were fueled with a blend of CNG and hydrogen. The three blended-fuel vehicles were originally equipped with either factory CNG engines or factory gasoline engines that were converted to run CNG fuel. The vehicles were variously modified to operate on blended fuel and were tested using 15 to 50% blends of hydrogen (by volume). The pure- hydrogen-fueled vehicle was converted from gasoline fuel to operate on 100% hydrogen. All vehicles were fueled from the Arizona Public Service's Alternative Fuel Pilot Plant, which was developed to dispense gaseous fuels, including CNG, blends of CNG and hydrogen, and pure hydrogen with up to 99.9999% purity. The primary objective of the test was to evaluate the safety and reliability of operating vehicles on hydrogen and blended hydrogen fuel, and the interface between the vehicles and the hydrogen fueling infrastructure. A secondary objective was to quantify vehicle emissions, cost, and performance. Over a total of 40,000 fleet test miles, no safety issues were found. Also, significant reductions in emissions were achieved by adding hydrogen to the fuel. This report presents results of testing conducted over 6,864 kilometers (4,265 miles) of operation using the pure-hydrogen-fueled Mercedes Sprinter van.

Karner, D.; Francfort, James Edward

2003-01-01T23:59:59.000Z

180

Advanced Vehicle Testing Activity: Low-Percentage Hydrogen/CNG Blend, Ford F-150 -- Operating Summary  

DOE Green Energy (OSTI)

Over the past two years, Arizona Public Service, a subsidiary of Pinnacle West Capital Corporation, in cooperation with the U.S. Department of Energys Advanced Vehicle Testing Activity, tested four gaseous fuel vehicles as part of its alternative fueled vehicle fleet. One vehicle operated initially using compressed natural gas (CNG) and later a blend of CNG and hydrogen. Of the other three vehicles, one was fueled with pure hydrogen and two were fueled with a blend of CNG and hydrogen. The three blended-fuel vehicles were originally equipped with either factory CNG engines or factory gasoline engines that were converted to run CNG fuel. The vehicles were variously modified to operate on blended fuel and were tested using 15 to 50% blends of hydrogen (by volume). The pure-hydrogen-fueled vehicle was converted from gasoline fuel to operate on 100% hydrogen. All vehicles were fueled from the Arizona Public Services Alternative Fuel Pilot Plant, which was developed to dispense gaseous fuels, including CNG, blends of CNG and hydrogen, and pure hydrogen with up to 99.9999% purity The primary objective of the test was to evaluate the safety and reliability of operating vehicles on hydrogen and blended hydrogen fuel, and the interface between the vehicles and the hydrogen fueling infrastructure. A secondary objective was to quantify vehicle emissions, cost, and performance. Over a total of 40,000 fleet test miles, no safety issues were found. Also, significant reductions in emissions were achieved by adding hydrogen to the fuel. This report presents results of 16,942 miles of testing for one of the blended fuel vehicles, a Ford F-150 pickup truck, operating on up to 30% hydrogen/70% CNG fuel.

Karner, D.; Francfort, James Edward

2003-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


181

Advanced Vehicle Testing Activity: High-Percentage Hydrogen/CNG Blend, Ford F-150 -- Operating Summary  

DOE Green Energy (OSTI)

Over the past two years, Arizona Public Service, a subsidiary of Pinnacle West Capital Corporation, in cooperation with the U.S. Department of Energys Advanced Vehicle Testing Activity, tested four gaseous fuel vehicles as part of its alternative fueled vehicle fleet. One vehicle operated initially using compressed natural gas (CNG) and later a blend of CNG and hydrogen. Of the other three vehicles, one was fueled with pure hydrogen and two were fueled with a blend of CNG and hydrogen. The three blended-fuel vehicles were originally equipped with either factory CNG engines or factory gasoline engines that were converted to run CNG fuel. The vehicles were variously modified to operate on blended fuel and were tested using 15 to 50% blends of hydrogen (by volume). The pure-hydrogen-fueled vehicle was converted from gasoline fuel to operate on 100% hydrogen. All vehicles were fueled from the Arizona Public Services Alternative Fuel Pilot Plant, which was developed to dispense gaseous fuels, including CNG, blends of CNG and hydrogen, and pure hydrogen with up to 99.9999% purity. The primary objective of the test was to evaluate the safety and reliability of operating vehicles on hydrogen and blended hydrogen fuel, and the interface between the vehicles and the hydrogen fueling infrastructure. A secondary objective was to quantify vehicle emissions, cost, and performance. Over a total of 40,000 fleet test miles, no safety issues were found. Also, significant reductions in emissions were achieved by adding hydrogen to the fuel. This report presents the results of 4,695 miles of testing for one of the blended fuel vehicles, a Ford F-150 pickup truck, operating on up to 50% hydrogen50% CNG fuel.

Don Karner; Francfort, James Edward

2003-01-01T23:59:59.000Z

182

Advanced Vehicle Testing Activity: Hydrogen-Fueled Mercedes Sprinter Van Operating Summary - January 2003  

Science Conference Proceedings (OSTI)

Over the past two years, Arizona Public Service, a subsidiary of Pinnacle West Capital Corporation, in cooperation with the U.S. Department of Energy's Advanced Vehicle Testing Activity, tested four gaseous fuel vehicles as part of its alternative fueled vehicle fleet. One vehicle operated initially using compressed natural gas (CNG) and later a blend of CNG and hydrogen. Of the other three vehicles, one was fueled with pure hydrogen and two were fueled with a blend of CNG and hydrogen. The three blended-fuel vehicles were originally equipped with either factory CNG engines or factory gasoline engines that were converted to run CNG fuel. The vehicles were variously modified to operate on blended fuel and were tested using 15 to 50% blends of hydrogen (by volume). The pure-hydrogen-fueled vehicle was converted from gasoline fuel to operate on 100% hydrogen. All vehicles were fueled from the Arizona Public Service's Alternative Fuel Pilot Plant, which was developed to dispense gaseous fuels, including CNG, blends of CNG and hydrogen, and pure hydrogen with up to 99.9999% purity. The primary objective of the test was to evaluate the safety and reliability of operating vehicles on hydrogen and blended hydrogen fuel, and the interface between the vehicles and the hydrogen fueling infrastructure. A secondary objective was to quantify vehicle emissions, cost, and performance. Over a total of 40,000 fleet test miles, no safety issues were found. Also, significant reductions in emissions were achieved by adding hydrogen to the fuel. This report presents results of testing conducted over 6,864 kilometers (4,265 miles) of operation using the pure-hydrogen-fueled Mercedes Sprinter van.

Karner, D.; Francfort, J.E.

2003-01-22T23:59:59.000Z

183

Battery Energy Storage Test (BEST) Facility: Summary report, 1976-1986: Final report  

SciTech Connect

This report summarizes the development, operations, and contributions of the Battery Energy Storage Test Facility. Providing direction for the nation's battery technology research, the facility has generated a better understanding of the work involved in operating energy storage systems and has been instrumental in demonstrating lead-acid battery applications for utilities worldwide.

Hyman, E.A.

1986-12-01T23:59:59.000Z

184

laura.schewel@berkeley.edu 1 VIRTUAL EV TEST DRIVE: INTRODUCTION AND PROJECT SUMMARY  

E-Print Network (OSTI)

, and battery electric vehicles (4) (5). · Many consumers are not interested in strict economic rationality when costs? Her fundamental question: "What does an EV mean for me?" Virtual EV Test Drive helps answer all a plug-in hybrid probably would switch into gasoline mode, and if/where a battery electric would have run

Kammen, Daniel M.

185

Summary and Evaluation of NRC-Sponsored Stellite 6 Aging and Friction Tests  

SciTech Connect

This report describes four sets of tests sponsored by the U.S. Nuclear Regulatory Commission and conducted by the Idaho National Engineering and Environmental Laboratory. The tests support research addressing the need to provide assurance that motor-operated valves are able to perform their intended safety function, usually to open or close against specified (design basis) flow and pressure loads. One of the parameters that affects a gate valve's operability is the friction between the disc seats and the valve body seats. In most gate valves, these surfaces are hardfaced with Stellite 6, a cobalt-based alloy. The tests described in this report investigate the changes that occur in the friction as the Stellite 6 surfaces develop an oxide film as they age. Stellite 6 specimens were aged in a corrosion autoclave, the oxide films were examined and characterized, and the specimens were subjected to friction testing in a friction autoclave. A very thin oxide film formed after only a fe w days of natural aging. Even a very thin oxide film caused an increase in friction. The surface structure of the oxide film was dominated by a hard crystalline structure, such that the friction response was analogous to rubbing two pieces of sandpaper together. In the limited data provided by naturally aged specimens (78 days maximum exposure, very thin oxide films), the friction increased with greater aging time, approaching an as-yet-undetermined plateau. Although the thickness of the oxide film increased with greater aging time, the mechanical properties of the oxide film (larger granules with greater aging time) appeared to play a greater role in the friction response. Friction testing of specimens subjected to simulated in-service testing strokes at intervals during the aging process showed only a slight decrease in friction, compared to other specimens. Results from specimens subjected to accelerated aging were inconclusive, because of differences in the structure and comp osition of the oxide films, compared to naturally aged specimens. For the naturally aged specimens, the highest friction occurred on the first stroke. The first stroke smeared the oxide film and dislodged some of the granules, so that subsequent strokes saw lower friction values and less variation in the friction. This result underscores the importance of planning in-plant tests so that data are collected from the first stroke following a period of inactivity.

J. C. Watkins; K. G. DeWall; D. Bramwell

1999-04-01T23:59:59.000Z

186

Interim Test Procedures for Evaluating Electrical Performance and Grid Integration of Vehicle-to-Grid Applications  

SciTech Connect

The objective of this report is to provide a test plan for V2G testing. The test plan is designed to test and evaluate the vehicle's power electronics capability to provide power to the grid, and to evaluate the vehicle's ability to connect and disconnect from the utility according to a subset of the IEEE Std. 1547 tests.

Chakraborty, S.; Kramer, W.; Kroposki, B.; Martin, G.; McNutt, P.; Kuss, M.; Markel, T.; Hoke, A.

2011-06-01T23:59:59.000Z

187

Stibine/arsine monitoring during EV operation: summary report on preliminary tests at ANL and at LILCO  

DOE Green Energy (OSTI)

A series of tests was performed to monitor the evolution and dispersal of stibine and arsine from the lead-acid propulsion batteries in three different Electra-Van Model 600 vehicles operated by Argonne National Laboratory (ANL) and by the Long Island Lighting Company (LILCO). Ambient air was sampled at several locations inside the vehicles and in the garages where testing was done during charge, equalization charge, and on-the-road discharge operations. In addition, direct sampling of cell off-gases was performed with the ANL van. Interpretation of the individual test results was carried out in the context of vehicle characteristics, sampling protocol, and operating conditions. The test results demonstrated that under the test conditions only small concentrations of stibine and arsine accumulated in occupiable work areas. Measured concentrations in the vehicles and in the garages never exceeded 25% of the Threshold Limit Value-Time Weighted Average (TLV-TWA) standards. A threshold voltage for hydride production, at about 2.45 V per cell, was reflected in the results of the experiments performed during charging of the batteries. Hydride evolution rates were lower during equalization charge than during the overcharge portion of a charge cycle when the on-board charger was used in a normal operating mode. A delayed release of the metal hydrides from the battery cells was observed during on-the-road operation of the vehicles. The implications of these observations for electric vehicle (EV) operation are discussed. An engineering analysis of the generation and dispersal of the metal hydrides is presented, and equations are derived for estimating minimum ventilation requirements for the EV battery compartment and for garages housing EV operations. Recommendations are made regarding safe handling procedures for battery off-gases, procedures for conducting stibine/arsine monitoring tests and future work.

Loutfy, R.O.; Graczyk, D.G.; Varma, R.; Hayes, E.R.; Williams, F.L.; Yao, N.P.

1981-02-01T23:59:59.000Z

188

TANK 18 AND 19-F TIER 1A EQUIPMENT FILL MOCK UP TEST SUMMARY  

SciTech Connect

The United States Department of Energy (US DOE) has determined that Tanks 18-F and 19-F have met the F-Tank Farm (FTF) General Closure Plan Requirements and are ready to be permanently closed. The high-level waste (HLW) tanks have been isolated from FTF facilities. To complete operational closure they will be filled with grout for the purpose of: (1) physically stabilizing the tanks, (2) limiting/eliminating vertical pathways to residual waste, (3) discouraging future intrusion, and (4) providing an alkaline, chemical reducing environment within the closure boundary to control speciation and solubility of select radionuclides. Bulk waste removal and heel removal equipment remain in Tanks 18-F and 19-F. This equipment includes the Advance Design Mixer Pump (ADMP), transfer pumps, transfer jets, standard slurry mixer pumps, equipment-support masts, sampling masts, dip tube assemblies and robotic crawlers. The present Tank 18 and 19-F closure strategy is to grout the equipment in place and eliminate vertical pathways by filling voids in the equipment to vertical fast pathways and water infiltration. The mock-up tests described in this report were intended to address placement issues identified for grouting the equipment that will be left in Tank 18-F and Tank 19-F. The Tank 18-F and 19-F closure strategy document states that one of the Performance Assessment (PA) requirements for a closed tank is that equipment remaining in the tank be filled to the extent practical and that vertical flow paths 1 inch and larger be grouted. The specific objectives of the Tier 1A equipment grout mock-up testing include: (1) Identifying the most limiting equipment configurations with respect to internal void space filling; (2) Specifying and constructing initial test geometries and forms that represent scaled boundary conditions; (3) Identifying a target grout rheology for evaluation in the scaled mock-up configurations; (4) Scaling-up production of a grout mix with the target rheology (16 second flow cone value) from 0.25 cubic feet to 4.3 cubic feet. (Ten 0.43 cubic batches were produced because full-scale equipment was not available for the Tier 1A test.); (5) Demonstrating continuous gravity filling of the ADMP mock up test form; (6) Demonstrating continuous gravity filling of 1 inch and 2 inch schedule 40 pipe; and (7) Demonstrating filling of 1 inch and 2 inch schedule 40 pipe from the bottom up by discharging through a tube inserted into the pipes. The Tier 1A mock-up test focused on the ADMP and pipes at least one inch in diameter. The ADMP which is located in center riser of Tank 18-F is a concern because the column for this long-shaft (55 ft) pump is unique and modification to the pump prior to placing it in service limited the flow path options for filling by creating a single flow path for filling and venting the ADMP support column. The large size, vertical orientation, and complicated flow path in the ADMP warrants a detailed description of this piece of ancillary equipment.

Stefanko, D.; Langton, C.

2011-11-04T23:59:59.000Z

189

Geothermal direct applications hardware systems development and testing. 1979 summary report  

DOE Green Energy (OSTI)

Activities performed during calendar year 1979 for the hardware system development and testing task are presented. The fluidized bed technology was applied to the drying of potato by-products and to the exchange of heat to air in the space heating experiment. Geothermal water was flashed to steam and also used as the prime energy source in the steam distillation of peppermint oil. Geothermal water temperatures as low as 112.8/sup 0/C were utilized to distill alcohol from sugar beet juice, and lower temperature water provided air conditioning through an absorption air conditioning system. These experiments are discussed.

Keller, J.G.

1980-03-01T23:59:59.000Z

190

Prototype geothermal power plant summary of operation for automatic-run test phase  

DOE Green Energy (OSTI)

The Prototype Power Plant was built to demonstrate and learn the operation of a binary power cycle, and then serve as a test bed for pilot scale components, systems, and/or concepts that have the potential for enhancing the feasibility of power generation from a moderate temperature geothermal fluid resource. The operation to date of the prototype plant is summarized with primary emphasis on the automatic-run phase, during which the plant was operated over a five-month period with minimal operator surveillance.

Mines, G.L.

1981-02-01T23:59:59.000Z

191

Summary of seasonal thermal energy storage field test projects in the United States  

DOE Green Energy (OSTI)

Seasonal thermal energy storage (STES) involves storage of available heat or chill for distribution at a later time to meet thermal loads. STES can reduce energy consumption, peak energy demand, and emissions of carbon dioxide to the atmosphere over conventional systems. It is estimated that full-scale application of STES would provide 2% to 4% of total energy needs in the United States. One STES technology, aquifer thermal energy storage (ATES), has been determined to be the most cost-effective option in the United States when site conditions enable its use. ATES has been analyzed in the laboratory and investigated in the field in the United States since the program was established at Pacific Northwest Laboratory (PNL) in 1979. Two field test facilities (FTFs), one for heating ATES at the University of Minnesota and the other for cooling ATES at the University of Alabama, have been primary testing grounds for US ATES research. Computer models have been developed to analyze the complex thermal and fluid dynamics. Extensive monitoring of FTFs has provided verification of and refinements to the computer models. The areas of geochemistry and microbiology have been explored as they apply to the aquifer environment. In general, the two FTFs have been successful in demonstrating the steps needed to make an ATES system operational.

Johnson, B.K.

1989-07-01T23:59:59.000Z

192

A SUMMARY OF TEST OBSERVATIONS WHEN IBUTTONS ARE SUBJECTED TO RF ENERGY  

SciTech Connect

The iButton is a 'one-wire', temperature sensor and data logger in a short metal cylinder package 17 mm in diameter and 6 mm tall. The device is designed to be attached to a surface and acquire temperature samples over time periods as short as 1 second to as long as 300 minutes. Both 8-bit and 16-bit samples are available with 8kB of memory available. Lifetime is limited to an internal battery that cannot be replaced or recharged. The RF test interest originated with the concern that the data logger could inadvertently record electrical emanations from other nearby equipment. The normal operation of the data logger does not support high speed sampling but the control interface will operate at either 15.4 kbps or 125 kbps. There were no observable effects in the operation of the module or in the data that could be attributed to the use of RF energy. They made the assumption that these devices would potentially show RF sensitivity in any of the registers and in the data memory equally, therefore gross changes in the data might show RF susceptibility. No such sensitivity was observed. Because significant power levels were used for these tests they can extrapolate downward in power to state that no RF susceptibility would occur at lower power levels given the same configurations.

Kane, R J; Baluyot, E V

2011-10-26T23:59:59.000Z

193

Giromill wind tunnel test and analysis. Volume I. Executive summary. Final report, June 1976--October 1977  

DOE Green Energy (OSTI)

The study described herein is a continuation of the Giromill investigation in which a wind tunnel test of a model Giromill rotor was performed. The primary objective of the wind tunnel test was to obtain data for comparison with the Larsen cyclogiro vortex theory program employed for predicting the Giromill performance. The model had a rotor diameter of 7 ft. (2.13 meters) and a solidity (total blade area divided by rotor span times diameter) of 0.3. This was achieved by a three bladed rotor having blade chords of 8.4 in. (21.3 cm) and a span of 5 ft. (1.52 meters). The blades were modulated by use of replaceable cams, that simulated the various operating conditions, and a push rod arrangement connected to a bellcrank about the blade pivot point. Rotor RPM control was achieved with an electric motor/generator that could be used to either drive the rotor or absorb the rotor power to maintain RPM.

Moran, W.A.

1977-10-01T23:59:59.000Z

194

Verification/acceptance test plan/procedure for Acromag calibration system  

SciTech Connect

The purpose of this document is to describe and document the test of the Acromag calibration system software. The purpose of this test is to verify that the Acromag Calibration System (ACS) will reliably test the Acromag thermocouple (TC) type input modules and provide a file showing the temperatures at which the modules are tested, the response rom the Acromag station, instrument data, technician data, and date and time of the test. The ACS consists of a thermocouple calibration unit (TCU), a DOS based computer, a hand held resistance temperature detector (RTD) surface probe and connects to a field installed or a bench Acromag unit.

Fordham, C.R.

1994-12-01T23:59:59.000Z

195

Test Summary Report INEEL Sodium-Bearing Waste Vitrification Demonstration RSM-01-1  

SciTech Connect

The U.S. Department of Energy's Idaho National Engineering and Environmental Laboratory is storing large amounts of radioactive and mixed wastes. Most of the sodium-bearing wastes have been calcined, but about a million gallons remain uncalcined, and this waste does not meet current regulatory requirements for long-term storage and/or disposal. As a part of the Settlement Agreement between DOE and the State of Idaho, the tanks currently containing SBW are to be taken out of service by December 31, 2012, which requires removing and treatment the remaining SBW. Vitrification is the option for waste disposal that received the highest weighted score against the criteria used. Beginning in FY 2000, the INEEL high-level waste program embarked on a program for technology demonstration and development that would lead to conceptual design of a vitrification facility in the event that vitrification is the preferred alternative for SBW disposal. The Pacific Northwest National Laborator's Research-Scale Melter was used to conduct these initial melter-flowsheet evaluations. Efforts are underway to reduce the volume of waste vitrified, and during the current test, an overall SBW waste volume-reduction factor of 7.6 was achieved.

Goles, Ronald W.; Perez, Joseph M.; Macisaac, Brett D.; Siemer, Darryl D.; Mccray, John A.

2001-05-21T23:59:59.000Z

196

Light-Duty Alternative Fuel Vehicles: Federal Test Procedure Emissions Results  

DOE Green Energy (OSTI)

In support of the U.S. Department of Energy's development and deployment of alternative fuels for environmental and national security reasons, NREL has managed a series of light-duty vehicle emissions tests on alternative fuel vehicles (AFVs). The purpose of this report is to give a detailed evaluation of the final emissions test results on vehicles tested on methanol, ethanol, and compressed natural gas.

Kelly, K.; Eudy, L.; Coburn, T.

1999-12-13T23:59:59.000Z

197

Developing Test Procedures for Measuring Stored Thermal Energy in Firefighter Protective Clothing.  

E-Print Network (OSTI)

??This research studied stored thermal energy in fire fighter's turnout systems. It developed a novel laboratory apparatus and test protocols for measuring the contribution of (more)

Eni, Egbe Uchechi

2005-01-01T23:59:59.000Z

198

Conference Summary  

Science Conference Proceedings (OSTI)

Summary of the conference, summarizing both theoretical and experimental presentations and discussions.

Brodsky, Stanley J.; /SLAC; Rijssenbeek, Michael; /SUNY, Stony Brook

2005-11-09T23:59:59.000Z

199

Decision Summaries  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

oha/decision-summaries Office of Hearings and Appeals oha/decision-summaries Office of Hearings and Appeals 1000 Independence Ave., SW Washington, DC, 20585 202-287-1566 en Summary of Decisions - December 30, 2013 - January 3, 2014 http://energy.gov/oha/articles/summary-decisions-december-30-2013-january-3-2014 summary-decisions-december-30-2013-january-3-2014" class="title-link">Summary of Decisions - December 30, 2013 - January 3, 2014

200

Acceptance test procedure for removal of CS1K circuit switcher block and trip schemes  

Science Conference Proceedings (OSTI)

This supporting document provides a detailed process to test the functions of the circuit switcher, protective relays, alarms, SCADA and 125VDC control logic of 115kV and 13.8kV systems at B3S4 substation following the removal of trip and blocking schemes to Transformer No.1 Circuit Switcher B594.

HACHE, J.M.

1999-08-25T23:59:59.000Z

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


201

Program mid-year summaries research, development, demonstration, testing and evaluation: Office of Technology Development, FY 1993  

SciTech Connect

This mid-year review provides a summary of activities within the Office of Technology Development with individual presentations being made to DOE HQ and field management staff. The presentations are by EM-541, 542, 551, and 552 organizations.

Not Available

1993-10-01T23:59:59.000Z

202

Toxic Characteristic Leaching Procedure (TCLP) Testing of Waste Glass and K-3 Refractory  

Science Conference Proceedings (OSTI)

The U. S. Environmental Protection Agency (EPA) issued revised Resource Conservation and Recovery Act (RCRA) Phase IV Land Disposal Restrictions (LDR's) on May 26 1998. The new regulation requires that any waste characteristically hazardous for the metals As, Ba, Cd, Cr, Pb, Hg, Se, and Ag will have to be treated to meet the LDR Universal Treatment Standards (UTS) for each metal prior to land disposal. Since EPA regulations continue to become more stringent, here-to-fore unpublished TCLP data generated during testing of simulated High Level Waste (HLW) glass, including the Evnironmental Assessment glass and K-3 melter refractory, will be reviewed. The refractory TCLP data compilation includes K-3 refractory in contact with DWPF simulated glass in a pilot scale melter and K-3 refractory in contact with actual mixed waste glass in a 5 ton a day GTS Duratek melter.

Jantzen, C.M.

1999-04-23T23:59:59.000Z

203

Base program interim phase test procedure - Coherent Laser Vision System (CLVS). Final report, September 27, 1994--January 30, 1997  

Science Conference Proceedings (OSTI)

The purpose of the CLVS research project is to develop a prototype fiber-optic based Coherent Laser Vision System suitable for DOE`s EM Robotics program. The system provides three-dimensional (3D) vision for monitoring situations in which it is necessary to update geometrics on the order of once per second. The CLVS project plan required implementation in two phases of the contract, a Base Contract and a continuance option. This is the Test Procedure and test/demonstration results presenting a proof-of-concept for a system providing three-dimensional (3D) vision with the performance capability required to update geometrics on the order of once per second.

NONE

1997-05-01T23:59:59.000Z

204

EXECUTIVE SUMMARY  

NLE Websites -- All DOE Office Websites (Extended Search)

EXECUTIVE SUMMARY This document contains an assessment of the first project to be completed under the U.S. Department of Energy Clean Coal Technology Program. The project was selected under Round I and is known officially as "The Demonstration of an Advanced Cyclone Coal Combustor, with Internal Sulfur, Nitrogen, and Ash Control for the Conversion of a 23 MMBtu/hour Oil-Fired Boiler to Pulverized Coal." The project was carried out by the Coal Tech Corporation over the period March 1987 February 1991 at the site of the Keeler/Dorr-Oliver Boiler Company in Williamsport, Pennsylvania. The project was a three-year demonstration scale test of a 30 MMBtu/hr air-cooled ceramic slagging cyclone combustor retrofitted to a horizontal 23-MMBtu/hr oil or natural gas-fired Keeler/Dorr-Oliver DS-9

205

A Discussion of Procedures and Equipment for the Comprehensive Test Ban Treaty On-Site Inspection Environmental Sampling and Analysis  

SciTech Connect

This paper is intended to serve as a scientific basis to start discussions of the available environmental sampling techniques and equipment that have been used in the past that could be considered for use within the context of the Comprehensive Nuclear-Test-Ban Treaty (CTBT) on-site inspections (OSI). This work contains information on the techniques, equipment, costs, and some operational procedures associated with environmental sampling that have actually been used in the past by the United States for the detection of nuclear explosions. This paper also includes a discussion of issues, recommendations, and questions needing further study within the context of the sampling and analysis of aquatic materials, atmospheric gases, atmospheric particulates, vegetation, sediments and soils, fauna, and drill-back materials.

Wogman, Ned A.; Milbrath, Brian D.; Payne, Rosara F.; Seifert, Carolyn E.; Friese, Judah I.; Miley, Harry S.; Bowyer, Ted W.; Hanlen, Richard C.; Onishi, Yasuo; Hayes, James C.; Wigmosta, Mark S.

2011-02-01T23:59:59.000Z

206

RFID Interference Test Procedures  

Science Conference Proceedings (OSTI)

... GHz. Active tags contain a power source (eg, battery) and permit higher read ranges and/or lower reader power. Passive ...

2010-10-05T23:59:59.000Z

207

Meeting Concerning Potential Test Procedures and Energy Conservation Standards for Set-Top Boxes and Network Equipment  

Energy.gov (U.S. Department of Energy (DOE))

In compliance with the Department of Energys guidance on ex parte communications (74 Fed. Reg. 52795 (Oct. 14, 2009)), this memorandum provides a summary of a March 7, 2012, meeting with DOE...

208

2013 Annual Planning Summary for the Rocky Mountain Oilfield...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Rocky Mountain Oilfield Testing Center 2013 Annual Planning Summary for the Rocky Mountain Oilfield Testing Center 2013 Annual Planning Summary for the Rocky Mountain Oilfield...

209

Program Summaries  

Office of Science (SC) Website

Program Summaries Program Summaries Basic Energy Sciences (BES) BES Home About Research Facilities Science Highlights Benefits of BES Funding Opportunities Basic Energy Sciences Advisory Committee (BESAC) News & Resources Program Summaries Brochures Reports Accomplishments Presentations BES and Congress Science for Energy Flow Seeing Matter Scale of Things Chart Contact Information Basic Energy Sciences U.S. Department of Energy SC-22/Germantown Building 1000 Independence Ave., SW Washington, DC 20585 P: (301) 903-3081 F: (301) 903-6594 E: sc.bes@science.doe.gov More Information » News & Resources Program Summaries Print Text Size: A A A RSS Feeds FeedbackShare Page Bes Summaries 2012 thumbnail JPG .jpg file (469KB) Basic Energy Sciences FY 2012 Research Summaries This report provides a collection of research abstracts and highlights for

210

Project Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

history page A Summary of Particle Physics THE SUBATOMIC WORLD Particles Prior to Accelerators By the mid 1930s, the understanding of the fundamental structure of matter seemed...

211

Science Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Speciation to Aerosol Solubility: Potential Effects of Aerosol Source on Ocean Photosynthesis summary written by Raven Hanna The world's animals depend on plants, plants depend...

212

Saltcreek Project Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Project Summary Project Summary HELP Index Summary Scenario References Student Pages Subject/Content Area: Environmental Science Target Audience: Middle school level - all students, including gifted, learning-disabled, behavior-disordered and limited English proficient Project Goals: As a result of their participation in the Salt Creek Investigation, the students will develop the abilities necessary to do scientific inquiry. They will increase their understanding of factors affecting environmental quality, including the interdependence of organisms, and human-induced hazards. Students will learn how science and technology can help people solve local, national and global environmental problems. Learner Outcomes: Students will: be able to carry out six types of stream monitoring tests.

213

DIRECT CONTACT HEAT EXCHANGER 10 kW POWER LOOP. SECTION 1: EXECUTIVE SUMMARY. SECTION 2: TEST SERIES NO. 1. SECTION 3; TEST SERIES NO. 2  

E-Print Network (OSTI)

Direct Contact Heat Exchanger . . . . . . . . . .DIRECT CONTACT HEAT EXCHANGER TEST LOOP . . . . . . . . TestCALIBRATION . CONVENTIONAL HEAT EXCHANGER . . . Subcritical

Engineering, Barber-Nicholas

2011-01-01T23:59:59.000Z

214

Analytical Solution of a Simplified Transport Problem with Continuous Energy for Testing Monte Carlo Procedures, this conference  

E-Print Network (OSTI)

A simplified transport problem is presented with continuous energy and neutrons moving only into the +X and X direction. An exact analytical solution is given with a 1/E energy dependence of the space, direction and energy dependent neutron flux. The source function, which also behaves basically as 1/E has to be modified for a certain energy range if a maximum energy is introduced in the problem. At the cost of more complicated mathematics the total and scattering cross sections and the anisotropy of scattering may very with energy. This model can be implemented in a general purpose Monte Carlo code like MCNP5 without modification, but needs a specially prepared cross section library file. The model can be applied to test Monte Carlo procedures, like the generation of multi-group cross section and scattering matrices which can be calculated analytically from the continuous-energy cross section data. From the adjoint equation the optimum importance function can be derived, which can be used to devise a continuous-energy zero-variance Monte Carlo scheme. Key Words: transport problem, analytical solution, continuous energy, Monte Carlo 1.

J. Eduard Hoogenboom

2007-01-01T23:59:59.000Z

215

Annual Planning Summaries: 2013 | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

3 3 Annual Planning Summaries: 2013 March 25, 2013 2013 Annual Planning Summary for the Thomas Jefferson Site Office 2013 Annual Planning Summary for the Thomas Jefferson Site Office March 25, 2013 2013 Annual Planning Summary for the Pacific Northwest Site Office 2013 Annual Planning Summary for the Pacific Northwest Site Office March 25, 2013 2013 Annual Planning Summary for the New Brunswick Laboratory 2013 Annual Planning Summary for the New Brunswick Laboratory March 25, 2013 2013 Annual Planning Summary for the Strategic Petroleum Reserve 2013 Annual Planning Summary for the Strategic Petroleum Reserve March 25, 2013 2013 Annual Planning Summary for the Rocky Mountain Oilfield Testing Center 2013 Annual Planning Summary for the Rocky Mountain Oilfield Testing Center

216

Summary and assessment of METC zinc ferrite hot coal gas desulfurization test program, final report: Volume 2, Appendices  

Science Conference Proceedings (OSTI)

The Morgantown Energy Technology Center (METC) has conducted a test program to develop a zinc ferrite-based high temperature desulfurization process which could be applied to fuel gas entering downstream components such as molten carbonate fuel cells or gas turbines. As a result of prior METC work with iron oxide and zinc oxide sorbents, zinc ferrite evolved as a candidate with the potential for high capacity, low equilibrium levels of H/sub 2/S, and structural stability after multiple regenerations. The program consisted of laboratory-scale testing with a two-inch diameter reactor and simulated fixed-bed gasifier gas; bench-scale testing with a six-inch diameter reactor and actual gas from the METC 42-inch fixed bed gasifier; as well as laboratory-scale testing of zinc ferrite with simulated fluidized bed gasifier gas. Data from sidestream testing are presented. 18 refs.

Underkoffler, V.S.

1986-12-01T23:59:59.000Z

217

Deviation of the Test Program and Procedures for the 710 Critical Experiment Reactor Related to Changes in the core Material Volume Fractions  

SciTech Connect

This document describes a deviation from the "Test Program and Procedures for the 710 Critical Experiment Reactor Loading and Rod Calibrations," TM-63-1-702, which was made in accordance with ITS Standard Practice J80-81 on March 13, 1963. The deviation did not involve a significant change in the safety of the operation.

Sims, F.L.

1963-03-13T23:59:59.000Z

218

Summary of Chariton Valley Switchgrass Co-Fire Testing at the Ottumwa Generating Station in Chillicothe, Iowa: Milestone Completion Report  

DOE Green Energy (OSTI)

Results of the switchgrass co-firing tests conducted at the Ottumwa Generating Station in Chillicothe, Iowa as part of the Chariton Valley Biomass Project. After several years of planning, the Chariton Valley Biomass Project successfully completed two months of switchgrass co-fire testing at the Ottumwa Generating Station (OGS) in Chillicothe, Iowa. From November 30, 2000, through January 25, 2001, the switchgrass team co-fired 1,269 tons (1,151 tonnes) of switchgrass at rates up to 16.8 tons/h (15.2 tonne/h), representing about 3% heat input to the 725-MW power plant. Stack testing was completed when co-firing switchgrass and when burning only coal. Fuel and ash samples were collected for analysis, and boiler performance and emissions data were collected. Numerous improvements were made to the feed-handling equipment during testing. The co-fire testing was completed with no environmental incidents, no injuries to personnel, and no loss in electricity output from OGS. The goals of the this--the first of three rounds of co-fire tests--were: to identify the effects of co-firing on boiler performance, to measure any changes in emissions during co-firing, and to gather information to improve the design of the switchgrass handling equipment. All three of these goals were met. The design target for the switchgrass handling system was 12.5 ton/h (11.3 tonne/h), which we exceeded after a redesign of the secondary grinder in our system. We had hoped to burn over 3,000 tons (2,722 tonnes) of switchgrass during this first round of testing, but because of poor equipment performance in December, we were unable to meet this target before the planned boiler shutdown in January. There were, however, several days in January when we burned more than 100 tons (91 tonnes) of switchgrass.

Amos, W.

2002-07-01T23:59:59.000Z

219

P9 Summary Presentation  

NLE Websites -- All DOE Office Websites (Extended Search)

Learned Learned WTP Prototypic Mixing and Sampling System Vijay Jain Manager, Research & Technology (Vitrification) May 18-21, 2009 Waste Treatment & Immobilization Plant Project Presented at EM-21 Technical Exchange Denver, CO Jain 04102009 2 Outline Background Test requirements and system design Test status Technical issues during testing Test results Summary Jain 04102009 3 Highlights Testing system is prototypic Major technical and design issues resolved LAW report (3 simulants) - issued HLW & LAW tests - complete Data analyses - 08/09 Reports - 12/09 Jain 04102009 4 Background Compliance to waste specifications is critical to the success of WTP vitrification operations: - Mixing and sampling of waste and melter feed is an integral part

220

Advanced Vehicle Testing Activity: Low-Percentage Hydrogen/CNG Blend Ford F-150 Operating Summary - January 2003  

Science Conference Proceedings (OSTI)

Over the past two years, Arizona Public Service, a subsidiary of Pinnacle West Capital Corporation, in cooperation with the U.S. Department of Energy's Advanced Vehicle Testing Activity, tested four gaseous fuel vehicles as part of its alternative fueled vehicle fleet. One vehicle operated initially using compressed natural gas (CNG) and later a blend of CNG and hydrogen. Of the other three vehicles, one was fueled with pure hydrogen and two were fueled with a blend of CNG and hydrogen. The three blended-fuel vehicles were originally equipped with either factory CNG engines or factory gasoline engines that were converted to run CNG fuel. The vehicles were variously modified to operate on blended fuel and were tested using 15 to 50% blends of hydrogen (by volume). The pure-hydrogen-fueled vehicle was converted from gasoline fuel to operate on 100% hydrogen. All vehicles were fueled from the Arizona Public Service's Alternative Fuel Pilot Plant, which was developed to dispense gaseous fuels, including CNG, blends of CNG and hydrogen, and pure hydrogen with up to 99.9999% purity. The primary objective of the test was to evaluate the safety and reliability of operating vehicles on hydrogen and blended hydrogen fuel, and the interface between the vehicles and the hydrogen fueling infrastructure. A secondary objective was to quantify vehicle emissions, cost, and performance. Over a total of 40,000 fleet test miles, no safety issues were found. Also, significant reductions in emissions were achieved by adding hydrogen to the fuel. This report presents results of 16,942 miles of testing for one of the blended fuel vehicles, a Ford F-150 pickup truck, operating on up to 30% hydrogen/70% CNG fuel.

Karner, D.; Francfort, J.E.

2003-01-22T23:59:59.000Z

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


221

Advanced Vehicle Testing Activity: High-Percentage Hydrogen/CNG Blend Ford F-150 Operating Summary - January 2003  

Science Conference Proceedings (OSTI)

Over the past two years, Arizona Public Service, a subsidiary of Pinnacle West Capital Corporation, in cooperation with the U.S. Department of Energy's Advanced Vehicle Testing Activity, tested four gaseous fuel vehicles as part of its alternative fueled vehicle fleet. One vehicle operated initially using compressed natural gas (CNG) and later a blend of CNG and hydrogen. Of the other three vehicles, one was fueled with pure hydrogen and two were fueled with a blend of CNG and hydrogen. The three blended-fuel vehicles were originally equipped with either factory CNG engines or factory gasoline engines that were converted to run CNG fuel. The vehicles were variously modified to operate on blended fuel and were tested using 15 to 50% blends of hydrogen (by volume). The pure-hydrogen-fueled vehicle was converted from gasoline fuel to operate on 100% hydrogen. All vehicles were fueled from the Arizona Public Service's Alternative Fuel Pilot Plant, which was developed to dispense gaseous fuels, including CNG, blends of CNG and hydrogen, and pure hydrogen with up to 99.9999% purity. The primary objective of the test was to evaluate the safety and reliability of operating vehicles on hydrogen and blended fuel, and the interface between the vehicles and the hydrogen fueling infrastructure. A secondary objective was to quantify vehicle emissions, cost, and performance. Over a total of 40,000 fleet test miles, no safety issues were found. Also, significant reductions in emissions were achieved by adding hydrogen to the fuel. This report presents the results of 4,695 miles of testing for one of the blended fuel vehicles, a Ford F-150 pickup truck, operating on up to 50% hydrogen-50% CNG fuel.

Karner, D.; Francfort, J.E.

2003-01-22T23:59:59.000Z

222

Energynet Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Project Summary Project Summary HELP Index Summary Scenario Reference Student Pages Subject/Content Area: Physical science/electricity, geometry and applied mathematics Target Audience: Middle school level - all students including gifted, learning-disabled, behavior-disordered and limited English proficient Project Goals: As a result of their participation in the Activating the EnergyNet project, the students will develop the abilities necessary to do scientific inquiry. They will increase their understanding of factors affecting energy cost and consumption, including the impact of energy production on the environment and the available technology and conversion costs. Students will use problem-solving strategies to design and implement interventions, assess the outcome, share data and strategies with other schools, and present

223

2004 Annual Summary Report for the Area 3 and Area 5 Radioactive Waste Management Sites at the Nevada Test Site, Nye County, Nevada  

SciTech Connect

The Maintenance Plan for the Performance Assessments and Composite Analyses for the Area 3 and Area 5 Radioactive Waste Management Sites at the Nevada Test Site (Bechtel Nevada, 2000) requires an annual review to assess the adequacy of the performance assessments (PAs) and composite analyses (CAs) for each of the facilities, and reports the results in an annual summary report to the U.S. Department of Energy Headquarters. The Disposal Authorization Statements for the Area 3 and Area 5 Radioactive Waste Management Sites (RWMSs) also require that such reviews be made and that secondary or minor unresolved issues be tracked and addressed as part of the maintenance plan (U.S. Department of Energy [DOE]). The U.S. Department of Energy National Nuclear Security Administration Nevada Site Office performed annual reviews in fiscal year (FY) 2004 by evaluating operational factors and research results that impact the continuing validity of the PA and CA results. This annual summary report presents data and conclusions from the FY 2004 review, and determines the adequacy of the PAs and CAs. Operational factors, such as the waste form and containers, facility design, waste receipts, closure plans, as well as monitoring results and research and development (R&D) activities were reviewed in FY 2004 for the determination of the adequacy of the PAs. Likewise, the environmental restoration activities at the Nevada Test Site relevant to the sources of residual radioactive material that are considered in the CAs, the land-use planning, and the results of the environmental monitoring and R&D activities were reviewed for the determination of the adequacy of the CAs.

Vefa Yucel

2005-01-01T23:59:59.000Z

224

HiR Thermal Testing Results  

NLE Websites -- All DOE Office Websites (Extended Search)

Thermal Testing Data Summary - Summary Plots - - Comparison Plots - - Prototype Drawings - Prototype Summary prototype prototype description (test conditions: cold side -18C,...

225

Summary of Conclusions and Recommendations Drawn from the DeepCWind Scaled Floating Offshore Wind System Test Campaign: Preprint  

DOE Green Energy (OSTI)

The DeepCwind consortium is a group of universities, national labs, and companies funded under a research initiative by the U.S. Department of Energy (DOE) to support the research and development of floating offshore wind power. The two main objectives of the project are to better understand the complex dynamic behavior of floating offshore wind systems and to create experimental data for use in validating the tools used in modeling these systems. In support of these objectives, the DeepCwind consortium conducted a model test campaign in 2011 of three generic floating wind systems, a tension-leg platform (TLP), a spar-buoy (spar), and a semisubmersible (semi). Each of the three platforms was designed to support a 1/50th-scale model of a 5 MW wind turbine and was tested under a variety of wind/wave conditions. The focus of this paper is to summarize the work done by consortium members in analyzing the data obtained from the test campaign and its use for validating the offshore wind modeling tool, FAST.

Robertson, A. N.; Jonkman, J. M.; Masciola, M. D.; Molta, P.; Goupee, A. J.; Coulling, A. J.; Prowell, I.; Browning, J.

2013-07-01T23:59:59.000Z

226

Summary of Decisions - September 17, 2012 - September 21, 2012 |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Summary of Decisions - September 17, 2012 - September 21, 2012 Summary of Decisions - September 17, 2012 - September 21, 2012 Summary of Decisions - September 17, 2012 - September 21, 2012 September 21, 2012 - 9:09am Addthis Application for Exception (10 CFR Part 430) On September 17, 2012, OHA issued a decision granting an Application for Exception filed by Westinghouse Lighting Corporation (Westinghouse) for relief from the provisions of 10 C.F.R. Part 430, Energy Conservation Program: Energy Conservation Standards and Test Procedures for General Service Fluorescent Lamps and Incandescent Reflector Lamps (Lighting Efficiency Standards). In its exception request, Westinghouse asserted that it would suffer a serious hardship, gross inequity and an unfair distribution of burdens if required to adhere to the Lighting Efficiency

227

Gulf Coast geopressured-geothermal program summary report compilation. Volume 2-A: Resource description, program history, wells tested, university and company based research, site restoration  

DOE Green Energy (OSTI)

The US Department of Energy established a geopressured-geothermal energy program in the mid 1970`s as one response to America`s need to develop alternate energy resources in view of the increasing dependence on imported fossil fuel energy. This program continued for 17 years and approximately two hundred million dollars were expended for various types of research and well testing to thoroughly investigate this alternative energy source. This volume describes the following studies: Geopressured-geothermal resource description; Resource origin and sediment type; Gulf Coast resource extent; Resource estimates; Project history; Authorizing legislation; Program objectives; Perceived constraints; Program activities and structure; Well testing; Program management; Program cost summary; Funding history; Resource characterization; Wells of opportunity; Edna Delcambre No. 1 well; Edna Delcambre well recompletion; Fairfax Foster Sutter No. 2 well; Beulah Simon No. 2 well; P.E. Girouard No. 1 well; Prairie Canal No. 1 well; Crown Zellerbach No. 2 well; Alice C. Plantation No. 2 well; Tenneco Fee N No. 1 well; Pauline Kraft No. 1 well; Saldana well No. 2; G.M. Koelemay well No. 1; Willis Hulin No. 1 well; Investigations of other wells of opportunity; Clovis A. Kennedy No. 1 well; Watkins-Miller No. 1 well; Lucien J. Richard et al No. 1 well; and the C and K-Frank A. Godchaux, III, well No. 1.

John, C.J.; Maciasz, G.; Harder, B.J.

1998-06-01T23:59:59.000Z

228

FY 1994 program summary: Office of Technology Development, Office of Research and Development, Office of Demonstration, Testing, and Evaluation  

SciTech Connect

The US Department of Energy (DOE) Office of Environmental Management, formerly the Office of Environmental Restoration and Waste Management (EM), was established in November 1989 as the first step toward correcting contamination problems resulting from nearly 50 years of nuclear weapons production and fuel processing activities. EM consolidates several DOE organizations previously responsible for the handling, treatment, and disposition of radioactive and hazardous waste. Within EM, the Office of Technology Development (OTD/EM-50) is responsible for developing technologies to meet DOE`s goal for environmental restoration. OTD manages an aggressive national program of applied research, development, demonstration, testing, and evaluation (RDDT and E) for environmental cleanup, waste management, and related technologies. The program is designed to resolve major technical issues, to rapidly advanced beyond current technologies for environmental restoration and waste management operations, and to expedite compliance with applicable environmental laws and regulations. This report summarizes Fiscal Year 1994 (FY94) programmatic information, accomplishments, and planned activities relevant to the individual activities within OTD`s RDDT and E.

1994-10-01T23:59:59.000Z

229

Executive Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Executive Summary Executive Summary Highway-based excise taxes are paid by highway users, and the tax revenues are distributed to States for supporting highways, safety, and transit programs. The processes for collecting these taxes and redistributing them to the States are very complex. The U.S. Treasury collects most of the taxes from a relatively small number of large corporations located in only a few States. The Internal Revenue Service (IRS) does not have an accurate picture of where the motor fuel is eventually consumed. Because the actual State-by-State contributions are not available, detailed analyses are required to estimate a State's on-highway motor fuel use. The attribution process uses State-reported data and nationally applied statistical models to determine how much fuel is used on highways in each State and the proportion of each State's usage in comparison to the total motor fuel usage for all States.

230

EXECUTIVE SUMMARY  

National Nuclear Security Administration (NNSA)

FUSION ENERGY SCIENCE ADVISORY COMMITTEE FUSION ENERGY SCIENCE ADVISORY COMMITTEE Panel on High Energy Density Laboratory Plasmas ADVANCING THE SCIENCE OF HIGH ENERGY DENSITY LABORATORY PLASMAS January 2009 UNITED STATES DEPARTMENT OF ENERGY 1 TABLE OF CONTENTS EXECUTIVE SUMMARY.......................................................................................... 5 1 HIGH ENERGY DENSITY LABORATORY PLASMA SCIENCE .................................... 15 2 THE CHARGE TO FESAC ...................................................................................... 19 3 THE PANEL PROCESS ............................................................................................ 20 4 STEWARDSHIP OF THE JOINT PROGRAM ............................................................... 23

231

Battery Usage and Thermal Performance of the Toyota Prius and Honda Insight for Various Chassis Dynamometer Test Procedures: Preprint  

DOE Green Energy (OSTI)

This study describes the results from the National Renewable Energy Laboratory's (NREL) chassis dynamometer testing of a 2000 model year Honda Insight and 2001 model year Toyota Prius. The tests were conducted for the purpose of evaluating the battery thermal performance, assessing the impact of air conditioning on fuel economy and emissions, and providing information for NREL's Advanced Vehicle Simulator (ADVISOR).

Kelly, K. J.; Mihalic, M.; Zolot, M.

2001-11-20T23:59:59.000Z

232

Summary of Blast Shield and Material Testing for Development of Solid Debris Collection at the National Ignition Facility (NIF)  

SciTech Connect

The ability to collect solid debris from the target chamber following a NIF shot has application for both capsule diagnostics, particularly for fuel-ablator mix, and measuring cross sections relevant to the Stockpile Stewardship program and nuclear astrophysics. Simulations have shown that doping the capsule with up to 10{sup 15} atoms of an impurity not otherwise found in the capsule does not affect its performance. The dopant is an element that will undergo nuclear activations during the NIF implosion, forming radioactive species that can be collected and measured after extraction from the target chamber. For diagnostics, deuteron or alpha induced reactions can be used to probe the fuel-ablator mix. For measuring neutron cross sections, the dopant should be something that is sensitive to the 14 MeV neutrons produced through the fusion of deuterium and tritium. Developing the collector is a challenge due to the extreme environment of the NIF chamber. The collector surface is exposed to a large photon flux from x-rays and unconverted laser light before it is exposed to a debris wind that is formed from vaporized material from the target chamber center. The photons will ablate the collector surface to some extent, possibly impeding the debris from reaching the collector and sticking. In addition, the collector itself must be mechanically strong enough to withstand the large amount of energy it will be exposed to, and it should be something that will be easy to count and chemically process. In order to select the best material for the collector, a variety of different metals have been tested in the NIF chamber. They were exposed to high-energy laser shots in order to evaluate their postshot surface characterization, morphology, degree of melt, and their ability to retain debris from the chamber center. The first set of samples consisted of 1 mm thick pieces of aluminum that had been fielded in the chamber as blast shields protecting the neutron activation diagnostic. Ten of these pieces were fielded at the equator and one was fielded on the pole. The shields were analyzed using a combination of scanning electron microscopy (SEM), energy dispersive spectroscopy (EDS), x-ray fluorescence (XRF), neutron activation analysis (NAA) and chemical leaching followed by mass spectrometry. On each shield, gold debris originating from the gold hohlraum was observed, as well as large quantities of debris that were present in the center of the target chamber at the time of the shot (i.e., stainless steel, indium, copper, etc.) Debris was visible in the SEM as large blobs or splats of material that had encountered the surface of the aluminum and stuck. The aluminum itself had obviously melted and condensed, and some of the large debris splats arrived after the surface had already hardened. Melt depth was determined by cross sectioning the pieces and measuring the melted surface layers via SEM. After the SEM analysis was completed, the pieces were sent for NAA at the USGS reactor and were analyzed by U. Greife at the Colorado School of Mines. The NAA showed that the majority of gold mass present on the shields was not in the form of large blobs and splats, but was present as small particulates that had most likely formed as condensed vapor. Further analysis showed that the gold was entrained in the melted aluminum surface layers and did not extend down into the bulk of the aluminum. Once the gold mass was accounted for from the NAA, it was determined that the aluminum fielded at the equator was collecting a fraction of the total gold hohlraum mass equivalent to 120% {+-} 10% of the solid angle subtended by the shield. The attached presentation has more information on the results of the aluminum blast shield analysis. In addition to the information given in the presentation, the surfaces of the shields have been chemically leached and submitted for mass spectrometric analysis. The results from that analysis are expected to arrive after the due date of this report and will be written up at a later time. Based on the results of the aluminum b

Shaughnessy, D A; Gostic, J M; Moody, K J; Grant, P M; Lewis, L A; Hutcheon, I D

2011-11-21T23:59:59.000Z

233

Office of Technology Development FY 1993 program summary: Office of Research and Development, Office of Demonstration, Testing and Evaluation. Revision 1  

SciTech Connect

This report summarizes significant FY93 programmatic information and accomplishments relevant to the individual activities within the Office of Technology Development Program for Research, Development, Demonstration, Testing, and Evaluation (RDDT&E). A brief discussion of the mission of the Office of Environmental Restoration and Waste Management (EM) and the Office of Technology Development is presented. An overview is presented of the major problem areas confronting DOE. These problem areas include: groundwater and soils cleanup; waste retrieval and processing; and pollution prevention. The organizational elements within EM are highlighted. An EM-50 Funding Summary for FY92 and FY93 is also provided. RDDT&E programs are discussed and their key problem areas are summarized. Three salient program-formulating concepts are explained. They are: Integrated Demonstrations, Integrated Programs, and the technology window of opportunity. Detailed information for each of the programs within RDDT&E is presented and includes a fact sheet, a list of technical task plans and an accomplishments and objectives section.

Not Available

1994-02-01T23:59:59.000Z

234

Executive Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Worker Safety and Health Program LBNL/PUB-3851, Rev. 2.2 (March 2012) Worker Safety and Health Program LBNL/PUB-3851, Rev. 2.2 (March 2012) Worker Safety and Health Program Lawrence Berkeley National Laboratory LBNL Worker Safety and Health Program LBNL/PUB-3851, Rev. 2.2 (March 2012) This page intentionally left blank. LBNL Worker Safety and Health Program LBNL/PUB-3851, Rev. 2.2 (March 2012) i Contents Executive Summary .............................................................................................. v 1. Introduction................................................................................................... 1 1.1 Work Activities .............................................................................................. 1

235

Test Procedure for 170.304 e Clinical Decision Support APPROVED Version 1.1 September 24, 2010  

E-Print Network (OSTI)

; and laboratory test results. 1 Department of Health and Human Services, 45 CFR Part 170 Health Information in 45 CFR Part 170 Subpart C of the Final Rule for Health Information Technology: Initial Set of standards, Implementation Specifications, and Certification Criteria for Electronic Health Record Technology

236

Test Procedure for 170.306.c Clinical Decision Support APPROVED Version 1.1 September 24, 2010  

E-Print Network (OSTI)

; and laboratory test results. 1 Department of Health and Human Services, 45 CFR Part 170 Health Information in 45 CFR Part 170 Subpart C of the Final Rule for Health Information Technology: Initial Set of standards, Implementation Specifications, and Certification Criteria for Electronic Health Record Technology

237

Partnership Overview and Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Phase III Field Test Phase III Field Test Overview and Summary RCSP Initiative Annual Review Meeting Pittsburgh, PA October 6 - 8, 2008 Presented by Brian J. McPherson Southwest Regional Partnership on Carbon Sequestration New Mexico Tech 2 Southwest Regional Partnership on Carbon Sequestration Acknowledgements * Many thanks to the U.S. Department of Energy and NETL for supporting this project * We express our gratitude also to our many industry partners, who have committed a great deal of time, funding and other general support for these projects * The work presented today is co-authored by all partners in the Southwest Partnership 3 Southwest Regional Partnership on Carbon Sequestration * Phase II - Phase III Integration * Summary of Phase III Project * location * site characterization

238

Emergency Procedures  

Energy.gov (U.S. Department of Energy (DOE))

Note: This page is pending deletion, please refer to the Safety and health main page for emergency procedure information:

239

Training and Medical Training Issues Topic Group Meeting Summary  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

and Medical Training Issues Topic Group Meeting Summary and Medical Training Issues Topic Group Meeting Summary Philadelphia, PA July 13, 1999 Fire Chief Bill Ruting (La Grange, IL, Fire Department) presented the results of the topic group's discussions: The MERRTT (Modular Emergency Response Radiological Transportation Training) series, comprised of 16 modules, is in the process of being finalized and pilot tested in a number of locations in the U.S. Pilot testing will include: using a needs assessment tool; developing model procedures; and actual training delivery of the MERRTT modules. The topic group, working with the regional government group staff representatives to TEC/WG, has sent a survey to State points-of-contact

240

Science Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

February 25, 2010 February 25, 2010 seafloor_biofilms Image of pillow basalts from inside the Pisces Submersible. » Links Scientific Highlight Templeton Lab EMSL News Imaging at SSRL » Share this Article Laboratree Ologeez SciLink LabSpaces Researchers Discover an Unexpected Source of Energy for Deep-sea Microbial Communities summary written by Raven Hanna New rock formed by deep undersea volcanoes does not stay bare long. Microbes quickly move onto these basalts to form communities in the form of biofilms. As these biofilms grow and develop, they change the geology of their environment, forming mineral deposits. Since many of these communities are deep in the cold ocean waters, where sunlight does not reach, they must use alternative sources of energy. What these might be is unknown, but a common theory posits that the microbes may be obtaining

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


241

Science Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

10 10 image Outside view of the T=4 subunit arrangement. » Links Scientific Highlight Johnson Lab » Share this Article Laboratree Ologeez SciLink LabSpaces Following the pH-dependent Conformational Changes of a Maturing Viral Capsid summary written by Raven Hanna The capsid that surrounds viruses is formed from subunit proteins that interact in specific ways to form a tight shell. The processes of coming together and forming interactions are multistep and complex and are fundamental events to acquire viral infectivity. The capsid maturation process of the Nudaurelia capensis omega virus includes pH-dependant conformational changes and auto-proteolysis. Like many human viruses such as HIV and herpes virus, NwV, an insect virus, requires these specific structural changes to become infectious.

242

Science Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

July 30, 2009 July 30, 2009 » Links Scientific Highlight Center for Advanced Molecular Photovoltaics, Stanford University » Share this Article Laboratree Ologeez SciLink LabSpaces Molecular Mixing in Organic Solar Cells summary written by Raven Hanna Solar panels contain a number of solar cells that convert light into electricity. Solar cells are traditionally made of crystalline silicon, which presently have 15-20% efficiency in conversion of light into electricity. However, these traditional cells are bulky and have high production costs that can take 5-7 years of solar panel operation to recover. Using solar cells made from organic materials could lower their production costs. This would lessen the time it takes for solar panels to generate more energy than consumed during production and would also result

243

Science Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

pseudogap image pseudogap image » Links Scientific Highlight SIMES Shen Lab SLAC Today Article » Share this Article Laboratree Ologeez SciLink LabSpaces Scientists Find Unexpected Electron Behavior in the Pseudogap of High-temperature Superconductors summary written by Raven Hanna Superconductivity is a hot topic in physics for good reason. With an electrical resistance of zero, superconductors transport electrical current with no loss of energy. Unfortunately, scientists have only found materials to be superconducting at very low temperatures, much too low for widespread use. In the 1980s, scientists discovered a class of "high-temperature" superconductors that can be used at the temperature of liquid nitrogen (~-200°C). This discovery has raised scientists' hopes that materials may

244

Science Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Hasan Research Hasan Research Princeton News Release » Share this Article Laboratree Ologeez SciLink LabSpaces Macroscopic Quantum Insulator State Observed summary written by Raven Hanna One of the strangest consequences of quantum mechanics is the seemingly instantaneous communication of subatomic particles over long distances. Known as quantum entanglement, pairs or groups of particles can become linked so that any changes made to one will cause the others to respond quicker than the time it takes for light to travel between them. Scientists are interested in finding a material that shows quantum entanglement on a macroscopic scale but which is neither a superconductor nor a superfluid. Dubbed a topological insulator, this theorized, exotic state of matter would have unusual conducting properties. For example,

245

Science Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

03, 2008 03, 2008 » Links Scientific Highlight Tainer Website Scripps Press Release » Share this Article Laboratree Ologeez SciLink LabSpaces Role of Specific Protein Mutations in Causing Human Disease Revealed summary written by Brad Plummer, SLAC Communication Office Scientists are one step closer to understanding a piece of the machinery involved in DNA transcription and repair, thanks to work done in part at the SSRL macromolecular crystallography Beam Line 11-1. The team, led by The Scripps Research Institute researcher John Tainer, and colleagues worked out the structure of an important enzyme call XPD, a member of the helicase family of enzymes, found in all living organisms. The results were published in the May 2008 edition of the journal Cell. In eukaryotes, XPD is responsible for unwinding double-stranded DNA

246

Science Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

25, 2008 25, 2008 » Links Scientific Highlight Saphire Website Scripps Press Release Tracking Ebola, Scripps At the Forefront » Share this Article Laboratree Ologeez SciLink LabSpaces Revealing a Structural Weakness of the Deadly Ebolavirus summary written by Brad Plummer, SLAC Communication Office Scientists are one step closer to conquering the deadly Ebolavirus, thanks to research conducted at SSRL structural biology Beam Lines 9-2 and 11-1 and ALS Beam Line 5.02 by a team of researchers led by Erica Ollmann Saphire from The Scripps Research Institute. The results were published in the July 10 edition of the journal Nature. Using macromolecular crystallography techniques, the team solved the structure of a protein on the Ebolavirus's surface, called glycoprotein GP,

247

The potential for use of waste-to-energy facility ash: Executive summary. Final report  

DOE Green Energy (OSTI)

This executive summary presents an overview of the investigations, findings, conclusions, and recommendations of the Long Island Regional Planning Board (LIRPB) study of the Potential for Beneficial Use of Waste-to-Energy Facility Ash. The full report consists of the following volumes: Executive Summary; Volume 1: Long Island Ash Management Status; Volume 2: Sampling and Testing Procedures; Volume 3: Environmental Properties; Volume 4: Engineering Properties; Volume 5: Environmental Assessment; Volume 6: Engineering and Economic Evaluation; and Volume 7: Legal and Institutional Issues. Volumes one through seven are briefly summarized in this executive summary with the exception of Volume 2 of the report, which serves as the documentation of the sampling conditions and testing methods used in measuring chemical and physical properties of the ash tested. The study investigated the feasibility of the use of incinerator ash as a substitute for natural aggregate in construction applications.

Koppelman, L.E.; Tanenbaum, E.G. [Long Island Regional Planning Board, Hauppauge, NY (United States)

1994-05-01T23:59:59.000Z

248

September 2008 EMAB Recommendation Summary  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

SUMMARY OF RECOMMENDATIONS SUMMARY OF RECOMMENDATIONS Recommendation 2008-12: Develop a strategic communications plan, or roadmap, in preparation for the next administration. Recommendation 2008-13: Expand outreach efforts to build support for, and acceptance of the EM program. Recommendation 2008-14: Update publications and other informational materials that help promote EM's mission. Recommendation 2008-15: Encourage efforts that promote and institutionalize the use of plain language in all communications. Recommendation 2008-16: Develop Standard Operating Policies and Procedures for the Office of Communications and External Affairs. Recommendation 2008-17: Complete the build-out of financial, analytical tools for strategic planning. Recommendation 2008-18:

249

HVAC BESTEST: A Procedure for Testing the Ability of Whole-Building Energy Simulation Programs to Model Space Conditioning Equipment: Preprint  

DOE Green Energy (OSTI)

Validation of Building Energy Simulation Programs consists of a combination of empirical validation, analytical verification, and comparative analysis techniques (Judkoff 1988). An analytical verification and comparative diagnostic procedure was developed to test the ability of whole-building simulation programs to model the performance of unitary space-cooling equipment that is typically modeled using manufacturer design data presented as empirically derived performance maps. Field trials of the method were conducted by researchers from nations participating in the International Energy Agency (IEA) Solar Heating and Cooling (SHC) Programme Task 22, using a number of detailed hourly simulation programs from Europe and the United States, including: CA-SIS, CLIM2000, PROMETHEUS, TRNSYS-TUD, and two versions of DOE-2.1E. Analytical solutions were also developed for the test cases.

Neymark, J,; Judkoff, R.; Knabe, G.; Le, H.-T.; Durig, M.; Glass, A.; Zweifel, G.

2001-07-03T23:59:59.000Z

250

Test procedures and protocols: Their relevance to the figure of merit for thermal distribution systems. Volume 1: Informal report  

Science Conference Proceedings (OSTI)

A conceptual framework is developed that categorizes measurement protocols for forced-air thermal distribution systems in small buildings. This framework is based on the distinction between two generic approaches. The {open_quote}system-comparison{close_quote} approach seeks to determine, via a pair of whole-house energy-use measurements, the difference in energy use between the house with the as-found duct system and the same house with no energy losses attributable to the thermal distribution system. The {open_quote}component loss-factor{close_quote} approach identifies and measures the individual causes of duct losses, and then builds up a value for the net overall duct efficiency, usually with the help of computer simulation. Examples of each approach are analyzed and related to a proposed Figure of Merit for thermal distribution systems. This Figure of Merit would serve as the basis for a Standard Method of Test analogous to those already in place for furnaces, boilers, air conditioners, and heat pumps.

Andrews, J.W.

1993-09-01T23:59:59.000Z

251

TEST PLAN AND PROCEDURE FOR THE EXAMINATION OF TANK 241-AY-101 MULTI-PROBE CORROSION MONITORING SYSTEM  

SciTech Connect

This test plan describes the methods to be used in the forensic examination of the Multi-probe Corrosion Monitoring System (MPCMS) installed in the double-shell tank 241-AY-101 (AY-101). The probe was designed by Applied Research and Engineering Sciences (ARES) Corporation. The probe contains four sections, each of which can be removed from the tank independently (H-14-107634, AY-101 MPCMS Removable Probe Assembly) and one fixed center assembly. Each removable section contains three types of passive corrosion coupons: bar coupons, round coupons, and stressed C-rings (H-14-l07635, AY-101 MPCMS Details). Photographs and weights of each coupon were recorded and reported on drawing H-14-107634 and in RPP-RPT-40629, 241-AY-101 MPCMS C-Ring Coupon Photographs. The coupons will be the subject of the forensic analyses. The purpose of this examination will be to document the nature and extent of corrosion of the 29 coupons. This documentation will consist of photographs and photomicrographs of the C-rings and round coupons, as well as the weights of the bar and round coupons during corrosion removal. The total weight loss of the cleaned coupons will be used in conjunction with the surface area of each to calculate corrosion rates in mils per year. The bar coupons were presumably placed to investigate the liquid-air-interface. An analysis of the waste level heights in the waste tank will be investigated as part of this examination.

WYRWAS RB; PAGE JS; COOKE GS

2012-04-19T23:59:59.000Z

252

Developing Fatigue Pre-crack Procedure to Evaluate Fracture Toughness of Pipeline Steels Using Spiral Notch Torsion Test  

SciTech Connect

The spiral notch torsion test (SNTT) has been utilized to investigate the crack growth behavior of X52 steel base and welded materials used for hydrogen infrastructures. The X52 steel materials are received from a welded pipe using friction stir welding techniques. Finite element models were established to study the crack growth behavior of steel SNTT steel samples, which were assumed to be isotropic material. A series SNTT models were set up to cover various crack penetration cases, of which the ratios between crack depth to diameter (a/D ratio) ranging from 0.10 to 0.45. The evolution of compliance and energy release rates in the SNTT method have been investigated with different cases, including different geometries and materials. Indices of characteristic compliance and energy release rates have been proposed. Good agreement has been achieved between predictions from different cases in the same trend. These work shed lights on a successful protocol for SNTT application in wide range of structural materials. The further effort needed for compliance function development is to extend the current developed compliance function to the deep crack penetration arena, in the range of 0.55 to 0.85 to effectively determine fracture toughness for extremely tough materials.

Wang, Jy-An John [ORNL; Tan, Ting [ORNL; Jiang, Hao [ORNL; Zhang, Wei [ORNL; Feng, Zhili [ORNL

2012-10-01T23:59:59.000Z

253

Concrete Electrical Conductivity Test  

Science Conference Proceedings (OSTI)

Concrete Electrical Conductivity Test. Description/Summary: ... Details. Type of software: Virtual concrete electrical conductivity test. Authors: ...

2013-06-11T23:59:59.000Z

254

Nevada Test Site closure program  

SciTech Connect

This report is a summary of the history, design and development, procurement, fabrication, installation and operation of the closures used as containment devices on underground nuclear tests at the Nevada Test Site. It also addresses the closure program mothball and start-up procedures. The Closure Program Document Index and equipment inventories, included as appendices, serve as location directories for future document reference and equipment use.

Shenk, D.P.

1994-08-01T23:59:59.000Z

255

Wildlife Trade: Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Project Summary Project Summary Scenario Student Pages Internet Links Index Subject/Content Area: Physical Science, Social Studies, Mathematics, and Learning Strategies Target Audience: Thornridge is a comprehensive high school serving approximately 2,000 ninth through twelfth grade students living southeast of the Chicago city limits. Student backgrounds vary greatly socio-economically (below the poverty line to approximately six figures), ethnically (7% Caucasian, 87% African-American, 6% Hispanic) and culturally. Mobility and unemployment are high. Steel mills, the auto industry, steel processing plants and the construction trades have been the major employers; however, many no longer exist. Student test scores in all areas are below the state mean. Eighty freshmen, identified as performing

256

CMS Procedure  

Science Conference Proceedings (OSTI)

... Tabletop Exercise. Tailoring. Tape Management System. Technical Safeguard. Tempest. Test Plan. Test. Threat Agent. Threat Analysis. ...

2009-06-30T23:59:59.000Z

257

Operating Experience Summaries  

NLE Websites -- All DOE Office Websites (Extended Search)

Operating Experience Summaries The Office of Health, Safety and Security (HSS) Office of Analysis publishes the Operating Experience Summary to exchange lessons-learned information...

258

ExecSummary_SRG _staff_  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Section 180(c) Policy and Procedures Section 180(c) Policy and Procedures This package describes the Section 180(c) Policy and Procedures that the Office of Civilian Radioactive Waste Management (OCRWM) Office of National Transportation (ONT) staff recommends to Department of Energy (DOE) management. This package concludes eighteen months of intensive cooperative work by several stakeholder groups and OCRWM staff. There are three parts to this package: (1) the Executive Summary; (2) two Federal Register Notices -- the Draft Section 180(c) Policy and Procedures and the Draft Grant Application Package; and (3) the Appendices. Background Section 180(c) of the Nuclear Waste Policy Act requires DOE to "provide technical assistance and funds to States for training for public safety officials of appropriate units of

259

Summary of Construction Activities and Results from Six Initial Accelerated Pavement Tests Conducted on Asphalt Concrete Pavement Section for Modified-Binder Overlay  

E-Print Network (OSTI)

a relationship between nuclear test and laboratory test air-Caltrans 308 or Nuclear Test, % AV(Nuclear) = 0.90AV(T-166)R2 = 0.77 Caltrans 308 Nuclear Test Linear (Nuclear Test)

Bejarano, Manuel O.; Morton, Bruce S.; Scheffy, Clark

2005-01-01T23:59:59.000Z

260

Set Top Boxes Test Procedure  

NLE Websites -- All DOE Office Websites (Extended Search)

Commission. Jessie F. Quichocho, Division of Policy and Rulemaking, Office of Nuclear Reactor Regulation. FR Doc. 2011-32389 Filed 12-15-11; 8:45 am BILLING CODE 7590-01-P...

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


261

Summary and Outlook  

E-Print Network (OSTI)

This summary is organized into four parts. In the first section (News) I discuss the SuperKamiokande results on atmospheric neutrino oscillations, as well as recent results from cosmology. The second section (Refinements) focuses on electroweak tests, recent results in the flavor sector and in probing QCD, as well as searches for new particles. The third section (Mysteries) discusses issues associated with neutrino masses and mixings in more depth. Finally, in the last section (Hopes) I reflect on both the short and long term future of the field.

R. D. Peccei

1998-11-11T23:59:59.000Z

262

Statewide Air Emissions Calculations From Wind and Other Renewables Summary Report Draft, a Report to the TCEQ for the Period Sept. 2005 - August 2006  

E-Print Network (OSTI)

This executive summary provides summaries of the key areas of accomplishment this year, including: development of stakeholders meetings; reporting of NOx emissions reductions from renewable energy generation in the 2005 report to the TCEQ; results of preliminary literature search of previous methods; proposed weather normalization procedure for a single wind turbine; proposed weather normalization procedure for a wind farm containing multiple wind turbines; testing of the models; weather data collection efforts, and proposed modifications to the Laboratorys Quality Assurance Project Plan.

Haberl, J. S.; Culp, C.; Yazdani, B.; Subbarao, K.; Verdict, M.; Liu, Z.; Baltazar-Cervantes, J. C.; Gilman, D.; Fitzpatrick, T.; Turner, W. D.

2006-10-25T23:59:59.000Z

263

Executive Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Quarter 2009 Quarter 2009 ConocoPhillips Gas Hydrate Production Test Submitted by: ConocoPhillips 700 G Street Anchorage, AK 99501 Principle Investigator: David Schoderbek Prepared for: United States Department of Energy National Energy Technology Laboratory June 26, 2009 Office of Fossil Energy Disclaimer This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific

264

Executive Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Second Half 2012 Second Half 2012 ConocoPhillips Gas Hydrate Production Test Submitted by: ConocoPhillips 600 North Dairy Ashford Houston, TX 77079 Principal Investigator: David Schoderbek Prepared for: United States Department of Energy National Energy Technology Laboratory January 25, 2013 Office of Fossil Energy Disclaimer This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or

265

Executive Summary  

E-Print Network (OSTI)

Air traffic is partly reopening., based on more accurate risk assessments using data collected in a number of test flights that have been conducted on Saturday 17 and Sunday 18 April. Lufthansa and Air Frances KLM unit reported successful testing of flights without passengers during the weekend, and Air France said an inspection of an Airbus A320 flown yesterday from Paris to Toulouse showed no anomalies. The Association of European Airlines, which represents 36 carriers, said it wants an immediate assessment of the airspace restrictions. (Business week) Additional flights authorized by Italian ENAC and have found no measureable traces of the ash in the Italian air space. This is a statement by the Italian Civil Protection Italy is constantly monitoring the fallout of ashes produced by the eruption of the Icelandic volcano. Following a preliminary assessment made on the Alps snow surface, no ashes fallout has been detected. To this regard, we will be grateful to the Participating States involved in the phenomenon if they would kindly provide us with information on the ashes fallout in their respective countries. The Italian scientific community and the national Agencies responsible of flight control and safety has requested detailed information regarding the threshold values adopted by the scientific models currently under analysis of the VAAC (Volcanic Ash Advisory Centre) based in London. In fact, the VAAC reports are increasingly precise in their delineation of the area covered by ash (thinner polygons). Yet, the criteria for this delineation (ash concentration thresholds) are unknown. The satellite image below shows the ash plume as of 18 April 2010, as seen from MODIS optical satellite imagery.

unknown authors

2010-01-01T23:59:59.000Z

266

Meson Summary Table See  

NLE Websites -- All DOE Office Websites (Extended Search)

Meson Summary Table See also the table of suggested qq quark-model assignments in the Quark Model section. * Indicates particles that appear in the preceding Meson Summary Table....

267

NIST Additive Manufacturing Test Artifact  

Science Conference Proceedings (OSTI)

NIST Additive Manufacturing Test Artifact. Summary. ... The test artifact is to be built using the AM system under investigation. ...

2013-04-26T23:59:59.000Z

268

Photon 2009 - Experimental Summary  

E-Print Network (OSTI)

I present a summary of the experimental talks given at the Photon 2009 conference held at DESY, Hamburg, Germany.

P. J. Bussey

2009-08-04T23:59:59.000Z

269

Albuquerque Roundtable Summary  

Energy.gov (U.S. Department of Energy (DOE))

Summary from the DOE Office of Indian Energy roundtable session on April 6, 2011, in Albuquerque, New Mexico.

270

Las Vegas Roundtable Summary  

Energy.gov (U.S. Department of Energy (DOE))

Summary report from the DOE Office of Indian Energy roundtable held on March 16, 2011, in Las Vegas, Nevada.

271

Mobile Energy Laboratory Procedures  

SciTech Connect

Pacific Northwest Laboratory (PNL) has been tasked to plan and implement a framework for measuring and analyzing the efficiency of on-site energy conversion, distribution, and end-use application on federal facilities as part of its overall technical support to the US Department of Energy (DOE) Federal Energy Management Program (FEMP). The Mobile Energy Laboratory (MEL) Procedures establish guidelines for specific activities performed by PNL staff. PNL provided sophisticated energy monitoring, auditing, and analysis equipment for on-site evaluation of energy use efficiency. Specially trained engineers and technicians were provided to conduct tests in a safe and efficient manner with the assistance of host facility staff and contractors. Reports were produced to describe test procedures, results, and suggested courses of action. These reports may be used to justify changes in operating procedures, maintenance efforts, system designs, or energy-using equipment. The MEL capabilities can subsequently be used to assess the results of energy conservation projects. These procedures recognize the need for centralized NM administration, test procedure development, operator training, and technical oversight. This need is evidenced by increasing requests fbr MEL use and the economies available by having trained, full-time MEL operators and near continuous MEL operation. DOE will assign new equipment and upgrade existing equipment as new capabilities are developed. The equipment and trained technicians will be made available to federal agencies that provide funding for the direct costs associated with MEL use.

Armstrong, P.R.; Batishko, C.R.; Dittmer, A.L.; Hadley, D.L.; Stoops, J.L.

1993-09-01T23:59:59.000Z

272

Computer Forensics Tool Testing  

Science Conference Proceedings (OSTI)

Computer Forensics Tool Testing (CFTT). Summary: For more information, visit: http://www.cftt.nist.gov/. There is a critical ...

2010-10-05T23:59:59.000Z

273

2012 Reliability & Markets Peer Review - Presentation Summaries |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Review - Presentation Summaries Review - Presentation Summaries 2012 Reliability & Markets Peer Review - Presentation Summaries The Transmission Reliability R&D Reliability & Markets Peer Review included 11 presentations over 2 days on August 7 - 8, 2012 at Cornell University in Ithaca, NY. Presentation summaries are available below. The full presentations are also available. 2012 R&M Peer Review - Summary: Transmission Investment Under Uncertainty - Ben Hobbs 2012 R&M Peer Review - Summary: Renewable Integration Through Risk-Limiting Dispatch - Pravin Varaiya 2012 R&M Peer Review - Summary: Development and Testing of New Tools - Ray Zimmerman 2012 R&M Peer Review - Summary: Commercialization of the SuperOPF Framework - Hsiao-Dong Chiang 2012 R&M Peer Review - Summary: Essence of Structure Preserving Network

274

ALUMINUM REMOVAL AND SODIUM HYDROXIDE REGENERATION FROM HANFORD TANK WASTE BY LITHIUM HYDROTALCITE PRECIPITATION SUMMARY OF PRIOR LAB-SCALE TESTING  

Science Conference Proceedings (OSTI)

Scoping laboratory scale tests were performed at the Chemical Engineering Department of the Georgia Institute of Technology (Georgia Tech), and the Hanford 222-S Laboratory, involving double-shell tank (DST) and single-shell tank (SST) Hanford waste simulants. These tests established the viability of the Lithium Hydrotalcite precipitation process as a solution to remove aluminum and recycle sodium hydroxide from the Hanford tank waste, and set the basis of a validation test campaign to demonstrate a Technology Readiness Level of 3.

SAMS TL; GUILLOT S

2011-01-27T23:59:59.000Z

275

Proceedings of second geopressured geothermal energy conference, Austin, Texas, February 23--25, 1976. Volume II. Resource assessment. [Geologic procedures for test- or industrial-site selection along Texas Gulf coast  

DOE Green Energy (OSTI)

This report describes techniques being used in the assessment of geopressured geothermal resources along the Texas Gulf Coast and defines geologic procedures for test- or industrial-site selection. These approaches have been proven in petroleum exploration and are applicable in geothermal exploration here in the Gulf basin and in other sedimentary basins.

Bebout, D.G.

1976-01-01T23:59:59.000Z

276

Microsoft PowerPoint - AVTALeaftestinganalysis_Major summary092112...  

NLE Websites -- All DOE Office Websites (Extended Search)

results - Battery performance, depletion and charging - Accessory load summary Thermal testing - 72F results - 20F results - 95F with solar load results Conclusions...

277

Workshop Summary & Conclusions  

Link project needs with research, development and ... Office of Environmental Management. Title: Microsoft PowerPoint - 5-Kosson Summary SRNL Dec ...

278

Summary of talks. [Abstracts  

DOE Green Energy (OSTI)

Twenty-two summaries of the talks given at the LASL 1978 Hot Dry Rock Geothermal Information Conference are presented. (MHR)

Not Available

1979-01-01T23:59:59.000Z

279

TE HNOLOGY SUMMARY  

nano oral high surfa e area platinum atalysts to improve fuel ell effi ien y te hnology summary te hnology readiness level: 4 key elements have een demonstrated ...

280

Plan Descriptions & Summaries  

NLE Websites -- All DOE Office Websites (Extended Search)

Plan Descriptions & Summaries Retiree Insurance Plans Retiree health and welfare benefits are managed by AonHewitt and Associates. Contact Retiree Insurance Providers Plan...

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


281

2009 Annual Summary Report for the Area 3 and Area 5 Radioactive Waste Management Sites at the Nevada Test Site, Nye County, Nevada: Review of the Performance Assessments and Composite Analysis  

SciTech Connect

The U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office performed an annual review of the Area 3 and Area 5 Radioactive Wate Management Site (RWMS) Performance Assessments (PAs) and Composite Analyses (CAs) in fiscal year (FY) 2009. This annual summary report presents data and conclusions from the FY 2009 review, and determines the adequacy of the PAs and CAs. Operational factors (e.g., waste forms and containers, facility design, and waste receipts), closure plans, monitoring results, and research and development (R&D) activities were reviewed to determine the adequacy of the PAs. Likewise, the environmental restoration activities at the Nevada Test Site relevant to the sources of residual radioactive material that are considered in the CAs, the land-use planning, and the results of the environmental monitoring and R&D activities were reviewed to determine the adequacy of the CAs.

NSTec Environmental Management

2010-03-15T23:59:59.000Z

282

Test Cell Location  

NLE Websites -- All DOE Office Websites (Extended Search)

2012 Fiat 500 Test Cell Location 2WD Vehicle Setup Information Downloadable Dynamometer Database (D 3 )- Test Summary Sheet Vehicle Architecture Conventional Vehicle Dynamometer...

283

Test Cell Location  

NLE Websites -- All DOE Office Websites (Extended Search)

2013 Nissan Altima Test Cell Location 2WD Vehicle Setup Information Downloadable Dynamometer Database (D 3 )- Test Summary Sheet Vehicle Architecture Conventional Vehicle...

284

Test Cell Location  

NLE Websites -- All DOE Office Websites (Extended Search)

Focus Test Cell Location 2WD Vehicle Setup Information Downloadable Dynamometer Database (D 3 )- Test Summary Sheet Vehicle Architecture Conventional Vehicle Dynamometer Input...

285

Test Cell Location  

NLE Websites -- All DOE Office Websites (Extended Search)

Chrysler 300 Test Cell Location 2WD Vehicle Setup Information Downloadable Dynamometer Database (D 3 )- Test Summary Sheet Vehicle Architecture Conventional Vehicle Dynamometer...

286

Test Cell Location  

NLE Websites -- All DOE Office Websites (Extended Search)

Mazda 3 i-Stop Test Cell Location APRF- 4WD Vehicle Setup Information Downloadable Dynamometer Database (D 3 )- Test Summary Sheet Vehicle Architecture Conventional- Start Stop...

287

Gulf Coast geopressured-geothermal program summary report compilation. Volume 2-B: Resource description, program history, wells tested, university and company based research, site restoration  

DOE Green Energy (OSTI)

The US Department of Energy established a geopressured-geothermal energy program in the mid 1970`s as one response to America`s need to develop alternate energy resources in view of the increasing dependence on imported fossil fuel energy. This program continued for 17 years and approximately two hundred million dollars were expended for various types of research and well testing to thoroughly investigate this alternative energy source. This volume describes the following studies: Design well program; LaFourche Crossing; MG-T/DOE Amoco Fee No. 1 (Sweet Lake); Environmental monitoring at Sweet Lake; Air quality; Water quality; Microseismic monitoring; Subsidence; Dow/DOE L.R. Sweezy No. 1 well; Reservoir testing; Environmental monitoring at Parcperdue; Air monitoring; Water runoff; Groundwater; Microseismic events; Subsidence; Environmental consideration at site; Gladys McCall No. 1 well; Test results of Gladys McCall; Hydrocarbons in production gas and brine; Environmental monitoring at the Gladys McCall site; Pleasant Bayou No. 2 well; Pleasant Bayou hybrid power system; Environmental monitoring at Pleasant Bayou; and Plug abandonment and well site restoration of three geopressured-geothermal test sites. 197 figs., 64 tabs.

John, C.J.; Maciasz, G.; Harder, B.J.

1998-06-01T23:59:59.000Z

288

Solid-State Lighting: CALiPER Application Summary Reports  

NLE Websites -- All DOE Office Websites (Extended Search)

Market-Based Programs Printable Version Share this resource Send a link to Solid-State Lighting: CALiPER Application Summary Reports to someone by E-mail Share Solid-State Lighting: CALiPER Application Summary Reports on Facebook Tweet about Solid-State Lighting: CALiPER Application Summary Reports on Twitter Bookmark Solid-State Lighting: CALiPER Application Summary Reports on Google Bookmark Solid-State Lighting: CALiPER Application Summary Reports on Delicious Rank Solid-State Lighting: CALiPER Application Summary Reports on Digg Find More places to share Solid-State Lighting: CALiPER Application Summary Reports on AddThis.com... LED Lighting Facts CALiPER Program About the Program FAQs Summary Reports Detailed Reports Benchmark Reports Exploratory Studies Testing Laboratories

289

Summary report on the HFED (High-Uranium-Loaded Fuel Element Development) miniplate irradiations for the RERTR (Reduced Enrichment Research and Test Reactor) Program  

SciTech Connect

An experiment to evaluate the irradiation characteristics of various candidate low-enriched, high-uranium content fuels for research and test reactors was performed for the US Department of Energy Reduced Enrichment Research and Test Reactor Program. The experiment included the irradiation of 244 miniature fuel plates (miniplates) in a core position in the Oak Ridge Research Reactor. The miniplates were aluminum-based, dispersion-type plates 114.3 mm long by 50.8 mm wide with overall plate thicknesses of 1.27 or 1.52 mm. Fuel core dimensions varied according to the overall plate thicknesses with a minimum clad thickness of 0.20 mm. Tested fuels included UAl/sub x/, UAl/sub 2/, U/sub 3/O/sub 8/, U/sub 3/SiAl, U/sub 3/Si, U/sub 3/Si/sub 1.5/, U/sub 3/Si/sub 2/, U/sub 3/SiCu, USi, U/sub 6/Fe, and U/sub 6/Mn/sub 1.3/ materials. Although most miniplates were made with low-enriched uranium (19.9%), some with medium-enriched uranium (40 to 45%), a few with high-enriched uranium (93%), and a few with depleted uranium (0.2 to 0.4%) were tested for comparison. These fuel materials were irradiated to burnups ranging from /approximately/27 to 98 at. % /sup 235/U depletion. Operation of the experiment, measurement of miniplate thickness as the irradiation progressed, ultimate shipment of the irradiated miniplates to various hot cells, and preliminary results are reported here. 18 refs., 12 figs., 7 tabs.

Senn, R.L.

1989-04-01T23:59:59.000Z

290

AFIP-6 Characterization Summary Report  

Science Conference Proceedings (OSTI)

The AFIP-6 (ATR Full-size-plate In center flux trap Position) Characterization Summary Report outlines the fresh fuel characterization efforts performed during the AFIP-6 experiment. The AFIP-6 experiment was designed to evaluate the performance of monolithic uranium-molybdenum (U-Mo) fuels at a scale prototypic of Advanced Test Reactor (ATR) fuel plates (45-inches long). The AFIP-6 test was the first test with plates that were swaged into the rails of the assembly. This test served to examine the effects of a plate in a swaged condition with longer fuel zones (22.5-inches long), that were centered in the plate. AFIP-6 test plates employed a zirconium interlayer that was co-rolled with the fuel foil. Previous mini-plate and AFIP irradiation experiments performed in ATR have demonstrated the stable behavior of the interface between the U-Mo fuel and the zirconium interlayer.

Dr. Dennis D. Keiser

2011-12-01T23:59:59.000Z

291

Untitled Page -- Other Sites Summary  

Office of Legacy Management (LM)

Other Sites Summary Other Sites Summary Search Other Sites Considered Sites Other Sites All LM Quick Search All Other Sites 11 E (2) Disposal Cell - 037 ANC Gas Hills Site - 040 Argonne National Laboratory - West - 014 Bodo Canyon Cell - 006 Burro Canyon Disposal Cell - 007 Cheney Disposal Cell - 008 Chevron Panna Maria Site - 030 Clive Disposal Cell - 036 Commercial (Burial) Disposal Site Maxey Flats Disposal Site - KY 02 Conoco Conquista Site - 031 Cotter Canon City Site - 009 Dawn Ford Site - 038 EFB White Mesa Site - 033 Energy Technology Engineering Center - 044 Estes Gulch Disposal Cell - 010 Exxon Ray Point Site - 032 Fermi National Accelerator Laboratory - 016 Fernald Environmental Management Project - 027 Fort St Vrain - 011 Geothermal Test Facility - 001 Hecla Durita Site - 012

292

Call Forwarding: New NIST Procedure Could Speed Cell ...  

Science Conference Proceedings (OSTI)

Call Forwarding: New NIST Procedure Could Speed Cell Phone Testing. For Immediate Release: March 2, 2010. ...

2010-10-05T23:59:59.000Z

293

DOE/EA-1673: Environmental Assessment for Energy Conservation Program for Certain Industrial Equipment: Energy Conservation Standards and Test Procedures for Commercial Heating, Air-Conditioning, and Water-Heating Equipment (July 2009)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

3 3 Environmental Assessment for 10 CFR 431 Energy Conservation Program for Certain Industrial Equipment: Energy Conservation Standards and Test Procedures for Commercial Heating, Air- Conditioning, and Water-Heating Equipment July 2009 8-i CHAPTER 8. ENVIRONMENTAL ASSESSMENT TABLE OF CONTENTS 8.1 INTRODUCTION ............................................................................................................... 8-1 8.2 AIR QUALITY ANALYSIS ............................................................................................... 8-1 8.3 AIR POLLUTANT DESCRIPTIONS ................................................................................ 8-1 8.4 AIR QUALITY REGULATIONS ...................................................................................... 8-3

294

Comparison of Test Procedures and Energy Efficiency Criteria in Selected International Standards and Labeling Programs for Clothes Washers, Water Dispensers, Vending Machines and CFLs  

E-Print Network (OSTI)

etc. ) during which energy consumption is measured, the typedoes not specify energy consumption measurements but rather,test in which water and energy consumption are measured. The

Fridley, David

2010-01-01T23:59:59.000Z

295

Fractionally distilled SRC-I, SRC-II, EDS, H-Coal and ITSL direct coal liquefaction process materials: a comparative summary of chemical analysis and biological testing  

DOE Green Energy (OSTI)

This document reports and compares the results compiled from chemical analyses and biological testing of coal liquefaction process materials which were fractionally distilled, after production, into various comparable boiling-point range cuts. Comparative analyses were performed on solvent refined coal (SRC)-I, SRC-II, H-Coal, EDS an integrated two-stage liquefaction (ITSL) distillate materials. Mutagenicity and carcinogenicity assays were conducted in conjunction with chromatographic and mass spectrometric analyses to provide detailed, comparative, chemical and biological assessments. Where possible, results obtained from the distillate cuts are compared to those from coal liquefaction materials with limited boiling ranges. Work reported here was conducted by investigators in the Biology and Chemistry Department at the Pacific Northwest Laboratory (PNL), Richland, WA. 38 refs., 16 figs., 27 tabs.

Wright, C.W.; Later, D.W.; Dauble, D.D.; Wilson, B.W.

1985-07-01T23:59:59.000Z

296

Renewable Energy Specifications, Testing and Certification Terms of  

Open Energy Info (EERE)

Renewable Energy Specifications, Testing and Certification Terms of Renewable Energy Specifications, Testing and Certification Terms of Reference Jump to: navigation, search Tool Summary Name: Renewable Energy Specifications, Testing and Certification Terms of Reference Agency/Company /Organization: World Bank Sector: Energy Focus Area: Solar, - Solar PV Topics: Market analysis, Co-benefits assessment Website: web.worldbank.org/WBSITE/EXTERNAL/TOPICS/EXTENERGY2/EXTRENENERGYTK/0,, References: Renewable Energy Specifications, Testing and Certification Terms of Reference[1] Resources Establishment of Local PV Systems Certification Capability Preparation of Small Private Power Producers Grid Connection Standards Establishment of Local PV System Battery Testing Procedure References ↑ "Renewable Energy Specifications, Testing and Certification

297

Nuclear Safety Workshop Summary  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Workshop Summary Workshop Summary September 19-20, 2012 1 Nuclear Safety Workshop Summary On September 19-20, 2012, the U.S. Department of Energy (DOE) held a second Nuclear Safety Workshop covering the results of the Department's actions to improve its posture for analyzing and responding to severe accidents in light of lessons learned from the March 2011 nuclear accident in Japan. Sponsored by DOE and championed by Deputy Secretary of Energy Daniel Poneman, the two-day workshop discussed the lessons learned in a national and international context. The workshop's theme

298

Biofuels: Project summaries  

DOE Green Energy (OSTI)

The US DOE, through the Biofuels Systems Division (BSD) is addressing the issues surrounding US vulnerability to petroleum supply. The BSD goal is to develop technologies that are competitive with fossil fuels, in both cost and environmental performance, by the end of the decade. This document contains summaries of ongoing research sponsored by the DOE BSD. A summary sheet is presented for each project funded or in existence during FY 1993. Each summary sheet contains and account of project funding, objectives, accomplishments and current status, and significant publications.

Not Available

1994-07-01T23:59:59.000Z

299

Compilation of ETR Summaries  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Summaries Summaries Office of Technology Innovation and Development Office of Environmental Management November 2011 External Technical Review Summaries Number Title Report Date ETR-1 Flowsheet for the Hanford Waste Treatment Plant (WTP) March 2006 ETR-2 Tank 48 at the Savannah River Site (SRS) August 2006 ETR-3 Demonstration Bulk Vitrification System (DBVS) for Low Activity Waste (LAW) at Hanford September 2006 ETR-4 Salt Waste Processing Facility Design at the Savannah River Site (SRS) November 2006 ETR-5 Remedial System Performance Improvement for the 200-ZP-1/PW-1 Operable Units at Hanford February 2007 ETR-6 Operational Issues at the Environmental Restoration

300

2008 Annual Summary Report for the Area 3 and Area 5 Radioactive Waste Management Sites at the Nevada Test Site, Nye County, Nevada: Review of the Performance Assessments and Composite Analyses  

Science Conference Proceedings (OSTI)

The Maintenance Plan for the Performance Assessments and Composite Analyses for the Area 3 and Area 5 Radioactive Waste Management Sites at the Nevada Test Site requires an annual review to assess the adequacy of the Performance Assessments (PAs) and Composite Analyses (CAs) for each of the facilities, with the results submitted annually to U.S. Department of Energy (DOE) Headquarters. The Disposal Authorization Statements for the Area 3 and Area 5 Radioactive Waste Management Sites (RWMSs) also require that such reviews be made and that secondary or minor unresolved issues be tracked and addressed as part of the maintenance plan. The U.S. Department of Energy, National Nuclear Security Administration Nevada Site Office (NNSA/NSO) performed an annual review in fiscal year (FY) 2008 by evaluating operational factors and research results that impact the continuing validity of the PAs and CAs. This annual summary report presents data and conclusions from the FY 2008 review, and determines the adequacy of the PAs and CAs. Operational factors (e.g., waste forms and containers, facility design, and waste receipts), closure plans, monitoring results, and research and development (R&D) activities were reviewed to determine the adequacy of the PAs. Likewise, the environmental restoration activities at the Nevada Test Site relevant to the sources of residual radioactive material that are considered in the CAs, the land-use planning, and the results of the environmental monitoring and R&D activities were reviewed to determine the adequacy of the CAs.

NSTec Environmental Management

2009-03-30T23:59:59.000Z

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


301

Summary of Decisions - September 17, 2012 - September 21, 2012 |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

7, 2012 - September 21, 2012 7, 2012 - September 21, 2012 Summary of Decisions - September 17, 2012 - September 21, 2012 September 21, 2012 - 9:09am Addthis Application for Exception (10 CFR Part 430) On September 17, 2012, OHA issued a decision granting an Application for Exception filed by Westinghouse Lighting Corporation (Westinghouse) for relief from the provisions of 10 C.F.R. Part 430, Energy Conservation Program: Energy Conservation Standards and Test Procedures for General Service Fluorescent Lamps and Incandescent Reflector Lamps (Lighting Efficiency Standards). In its exception request, Westinghouse asserted that it would suffer a serious hardship, gross inequity and an unfair distribution of burdens if required to adhere to the Lighting Efficiency Standards, which became effective July 14, 2012 (2009 Final Rule), with

302

Summary of Decisions - February 18, 2013-February 22, 2013 | Department  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

8, 2013-February 22, 2013 8, 2013-February 22, 2013 Summary of Decisions - February 18, 2013-February 22, 2013 February 22, 2013 - 1:35pm Addthis Application for Exception On February 22, 2013, OHA issued a decision granting an Application for Exception filed by Technical Consumer Products, Inc. (TCP) for relief from the provisions of 10 CFR Part 430, Energy Conservation Program: Energy Conservation Standards and Test Procedures for General Service Fluorescent Lamps and Incandescent Reflector Lamps (Lighting Efficiency Standards). In its exception request, TCP asserted that it will suffer a serious hardship, gross inequity and an unfair distribution of burdens if required to adhere to the new Lighting Efficiency Standards, effective July 14, 2012 (2009 Final Rule), with respect to its 700 series T8 General Service

303

Summary of Decisions - September 3 - September 7, 2012 | Department of  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

- September 7, 2012 - September 7, 2012 Summary of Decisions - September 3 - September 7, 2012 September 10, 2012 - 1:18pm Addthis Application for Exception (10 CFR Part 430) On September 6, 2012, OHA issued a decision denying an Application for Exception filed by DLU Lighting USA (DLU) for relief from the provisions of 10 C.F.R. Part 430, Energy Conservation Program: Energy Conservation Standards and Test Procedures for General Service Fluorescent Lamps and Incandescent Reflector Lamps (Lighting Efficiency Standards). In its exception request, DLU asserted that it will suffer a serious hardship, gross inequity, and an unfair distribution of burdens if required to adhere to the new Lighting Efficiency Standards, effective July 14, 2012 (2009 Final Rule), with respect to its 700 series T8 General

304

Summary of Decisions - November 19, 2012 - November 23, 2012 | Department  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

9, 2012 - November 23, 2012 9, 2012 - November 23, 2012 Summary of Decisions - November 19, 2012 - November 23, 2012 November 23, 2012 - 1:10pm Addthis Application for Exception On November 16, 2012, OHA issued a decision granting an Application for Exception filed by Topaz Lighting Corporation (Topaz) for relief from the provisions of 10 C.F.R. Part 430, Energy Conservation Program: Energy Conservation Standards and Test Procedures for General Service Fluorescent Lamps and Incandescent Reflector Lamps (Lighting Efficiency Standards). In its exception request, Topaz asserted that it will suffer a serious hardship, gross inequity and an unfair distribution of burdens if required to adhere to the new Lighting Efficiency Standards, effective July 14, 2012 (2009 Final Rule), with respect to its 700 series T8 General Service

305

NPP References and Summaries  

NLE Websites -- All DOE Office Websites (Extended Search)

Full references and selected summaries (in alphabetical order of first author name by data set): Chinese Forests NPP Data Set References Gao, Q. and X.S. Zhang (1997) A simulation...

306

Sorption Storage Technology Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Storage Technology Summary DOE H2 Storage Workshop, Feb 14-15, 2011, Washington, DC 1 Compressed & Cryo-Compressed Hydrogen Storage Workshop February 14 - 15, 2011, Washington, DC...

307

Summary.qxd  

NLE Websites -- All DOE Office Websites (Extended Search)

DOEEIS-0287 Idaho HLW & FD EIS 2.0 Activities since the Issuance of the Draft EIS 2.1 Summary of Public Comments and Agency Responses The Draft EIS was mailed to the public and...

308

Advanced Vehicle Testing Activity: Testing Reports  

NLE Websites -- All DOE Office Websites (Extended Search)

Reports NEVAmerica Baseline Performance Testing Summaries A neighborhood electric vehicle (NEV) is defined as a "low-speed vehicle" (LSV) by the National Highway Traffic...

309

Acceptance Test Procedure for Project 251W, WBS 3, Substation A-8, Building 251-W, Bus {number_sign}2 switchgear replacement  

Science Conference Proceedings (OSTI)

This document records the steps taken and results of the acceptance testing of the new 13.8kV switchgear installed at 251W. This gear is under the administrative control of Electrical Utilities.

VanBaalen, R.A.

1995-02-01T23:59:59.000Z

310

Site environmental report summary  

Science Conference Proceedings (OSTI)

In this summary of the Fernald 1992 Site Environmental Report the authors will describe the impact of the Fernald site on man and the environment and provide results from the ongoing Environmental Monitoring Program. Also included is a summary of the data obtained from sampling conducted to determine if the site complies with DOE, US Environmental Protection Agency (USEPA), and Ohio EPA (OEPA) requirements. These requirements are set to protect both man and the environment.

Not Available

1992-12-31T23:59:59.000Z

311

Model Driven Security Functional Testing  

Science Conference Proceedings (OSTI)

Model Driven Security Functional Testing. Summary: Model-Driven Engineering (MDE) is emerging as a promising approach ...

2013-01-15T23:59:59.000Z

312

Summary of Natural Resources that Potentially Influence Human Intrusion at the Area 5 Radioactive Waste Management Site, Nevada Test Site, Nye County, Nevada  

DOE Green Energy (OSTI)

In 1993, Raytheon Services Nevada completed a review of natural resource literature and other sources to identify potentially exploitable resources and potential future land uses near the Area 5 Radioactive Waste Management Site (RWMS) of the Nevada Test Site (NTS), Nye County, Nevada, that could lead to future inadvertent human intrusion and subsequent release of radionuclides to the accessible environment. National Security Technologies, LLC, revised the original limited-distribution document to conform to current editorial standards and U.S. Department of Energy requirements for public release. The researchers examined the potential for future development of sand, gravel, mineral, petroleum, water resources, and rural land uses, such as agriculture, grazing, and hunting. The study was part of the performance assessment for Greater Confinement Disposal boreholes. Sand and gravel are not considered exploitable site resources because the materials are common throughout the area and the quality at the Area 5 RWMS is not ideal for typical commercial uses. Site information also indicates a very low mineral potential for the area. None of the 23 mining districts in southern Nye County report occurrences of economic mineral deposits in unconsolidated alluvium. The potential for oil and natural gas is low for southern Nye County. No occurrences of coal, tar sand, or oil shale on the NTS are reported in available literature. Several potential future uses of water were considered. Agricultural irrigation is impractical due to poor soils and existing water supply regulations. Use of water for geothermal energy development is unlikely because temperatures are too low for typical commercial applications using current technology. Human consumption of water has the most potential for cause of intrusion. The economics of future water needs may create a demand for the development of deep carbonate aquifers in the region. However, the Area 5 RWMS is not an optimal location for extraction of groundwater from the deep carbonate aquifer. Grazing and hunting are unlikely to be potential causes for inadvertent human intrusion into waste areas because of vegetation characteristics and lack of significant game animal populations.

NSTec Environmental Management

2007-06-01T23:59:59.000Z

313

Nondestructive Evaluation: Plant-Specific Applications of Qualified Nozzle Inner Radius and Nozzle-to-Shell Weld Ultrasonic Testing Procedures Using EPRI Computer Models -- 2002-2010  

Science Conference Proceedings (OSTI)

This report is the fourth in a series of periodic technical updates documenting plant-specific applications of qualified nozzle inner radius and nozzle-to-shell weld ultrasonic testing techniques developed using the Electric Power Research Institute Nondestructive Evaluation programs three-dimensional nozzle models. This particular update covers the period 20022010.

2010-11-16T23:59:59.000Z

314

Slimhole Handbook- Procedures And Recommendations For Slimhole...  

Open Energy Info (EERE)

Slimhole Handbook- Procedures And Recommendations For Slimhole Drilling And Testing In Geothermal Exploration Jump to: navigation, search GEOTHERMAL ENERGYGeothermal Home Report:...

315

Additional Guidance Regarding Application of Current Procedures...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Additional Guidance Regarding Application of Current Procedures for Testing Energy Consumption of Clothes Washers with Warm Rinse Cycles, Issued: June 30, 2010 Additional Guidance...

316

Fire Protection Program: Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Summary Summary Since May 1950, an Annual Fire Protection Program Summary has been submitted by DOE's fire protection community. Currently, this report is required by section 5a.(8) of DOE Order 231.1. "Environment, Safety and Health Reporting." In 1999, an automation initiative was undertaken to streamline data collection and provide a more through review of DOE Reporting Element activities. This action resulted in the delayed publications of the CY 1999 and 2000 reports until 2002. It is now possible however to view all Annual Summary Reporting Element responses since 1991 at the Site, Operations, Lead Program Secretarial Office and Headquarters levels. Additionally, a build-in reference to other DOE reporting activities (CAIRS and ORPS) is available that allows Reporting Elements and managers the opportunity to review all fire protection events along previously mentioned categories. Reports listed below were generated from this application. To obtain a copy of the Annual Summary Application please contact Jim Bisker in the Office of Nuclear and Facility Safety Policy (EH-53) at (301)903-6542 or Jim Bisker.

317

TEST  

Science Conference Proceedings (OSTI)

This is an abstract. TEST Lorem ipsum dolor sit amet, consectetur adipiscing elit. Cras lacinia dui et est venenatis lacinia. Vestibulum lacus dolor, adipiscing id mattis sit amet, ultricies sed purus. Nulla consectetur aliquet feugiat. Maecenas ips

318

MHV Fleet Testing - Summary Fact Sheet  

NLE Websites -- All DOE Office Websites (Extended Search)

mile Operating Cost: .17mile** Total Ownership Cost: *** Operating Performance: Total miles driven: 116,785 Cumulative MPG: 27.9 Major Operations & Maintenance Events: None...

319

Summary-Final.PDF  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

SUMMARY SUMMARY June 2000 1 SUMMARY This document constitutes the first edition of a long-term research and development (R&D) plan for nuclear technology in the United States. Introduction In 1998, DOE established the Nuclear Energy Research Advisory Committee (NERAC) to provide advice to the Secretary and to the Director, Office of Nuclear Energy, Science, and Technology (NE), on the broad range of non-defense DOE nuclear technology programs. The NERAC recommended development of a long-range R&D program. This R&D plan is a result of that recommendation and is the first of what is expected to be an iterated series of long-range plans for nuclear energy in the Department of Energy. To develop this plan, 145 nuclear and non-nuclear scientists, engineers, and academics

320

BNL | ATF Operations Weekly Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Operations Weekly Summary Operations Weekly Summary Week Starts E-beam Status CO2 Status 2013/12/30 Up time: 0 days Down time: 5 days Activity: Maintenance & holiday week Up time: 0 days Down time: 5 days (setup) Activity: OPA work & holiday week 2013/12/23 Up time: 1 days Down time: 4 days (holiday week) Exp: Beam Studies Group: ATF Energy: 57.6 MeV Charge: 500 pC Up time: 0 days Down time: 5 days Activity: OPA work & holiday week 2013/12/16 Up time: Down time: Exp: AE-58, ERL BPM testing + beam studies Group: AE58, BNL (C-AD) / ATF Energy: 57.6 MeV Charge: 500 pC Up time: 0 days Down time: 5 days (setup) Activity: OPA work, EUVL test setup (AE59) and maintenance 2013/12/09 Up time: Down time: Exp: AE-52, Beam Manipulation by self wakefield Group: AE52, Euclid techlabs Energy: 57.6 MeV

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


321

ESPC ENABLE: ECM Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

ESPC ENABLE: ECM Summary ESPC ENABLE: ECM Summary ECM Included Not Included Lighting * Lamps, Ballasts, Fixtures * Controls: Occupancy, Day lighting (on/off, dimming) * Solar Lighting (off-grid installations allowed) Water * Sanitary plumbing fixtures: sinks, toilets, urinals, showers * Irrigation * Leak repair * Domestic/commercial hot water heaters * Water based appliances: dishwasher, ice machine, clothes washer, etc. * Heating/Cooling system improvements (cooling towers, once through cooling, condensate reclaim) HVAC Controls Whole building control strategies including: * Time/Temperature Set-back * Demand/Night Ventilation * Advanced Controls 1 : Energy Management Control Systems (EMCS) / Building Automation Systems (BAS) HVAC Equipment Basic whole building/system one-for-one replacement

322

ESPC ENABLE: ECM Summary  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

ESPC ENABLE: ECM Summary ESPC ENABLE: ECM Summary ECM Included Not Included Lighting * Lamps, Ballasts, Fixtures * Controls: Occupancy, Day lighting (on/off, dimming) * Solar Lighting (off-grid installations allowed) Water * Sanitary plumbing fixtures: sinks, toilets, urinals, showers * Irrigation * Leak repair * Domestic/commercial hot water heaters * Water based appliances: dishwasher, ice machine, clothes washer, etc. * Heating/Cooling system improvements (cooling towers, once through cooling, condensate reclaim) HVAC Controls Whole building control strategies including: * Time/Temperature Set-back * Demand/Night Ventilation * Advanced Controls 1 : Energy Management Control Systems (EMCS) / Building Automation Systems (BAS) HVAC Equipment Basic whole building/system one-for-one replacement

323

Methodology to Develop and Test an Easy-to-use Procedure for the Preliminary Selection of High-performance Systems for Office Buildings in Hot and Humid Climates  

E-Print Network (OSTI)

A procedure has been developed for the preliminary selection of high-performance systems for office buildings in hot and humid climates. High-performance building systems and components were surveyed for buildings in the U.S., which were applicable for office buildings in hot and humid climates. This research developed a calibrated DOE-2.1e simulation model of a prototypical large office building. In addition, a Simplified Geometry DOE-2.1e (SGDOE-2.1e) model, was also developed, which used a simplified geometry to demonstrate the use of a proposed easy-to-use tool. The calibrated DOE-2.1e simulation model and the SGDOE-2.1e were compared and showed a good match with each. The SGDOE-2.1e model was then further modified based on the ASHRAE Standard 90.1-1999 commercial building energy code. A code-compliant (ASHRAE Standard 90.1-1999) SGDOE-2.1e simulation model was then used as a baseline for the evaluation of the high-performance measures. A total of 14 high-performance measures were implemented including the energy savings, while the comfort level was maintained based on the ASHRAE comfort zone. In addition to the 14 high-performance measures, solar thermal and solar PV system analysis were integrated with the SGDOE-2.1e simulation model to further reduce the annual energy use. Finally, specifications of the proposed easy-to-use simulation tool were developed. This tool includes options to choose systems from the 14 high-performance measures and solar systems. The proposed easy-to-use systems selection tool can be used for new building practitioners and existing building owners as well to evaluate the performance of their new buildings compared to the ASHRAE Standard 90.1-1999 code-compliant building, and to assess the feasibility of implementing high-performance measures to their existing buildings in terms of energy and cost savings.

Cho, Sool Yeon

2009-08-01T23:59:59.000Z

324

Methodology to Develop and Test an Easy-To-Use Procedure for the Preliminary Selection of High-Performance Systems for Office Buildings in Hot and Humid Climates  

E-Print Network (OSTI)

A procedure has been developed for the preliminary selection of high-performance systems for office buildings in hot and humid climates. High-performance building systems and components were surveyed for buildings in the U.S., which were applicable for office buildings in hot and humid climates. This research developed a calibrated DOE-2.1e simulation model of a prototypical large office building. In addition, a Simplified Geometry DOE-2.1e (SGDOE-2.1e) model, was also developed, which used a simplified geometry to demonstrate the use of a proposed easy-to-use tool. The calibrated DOE-2.1e simulation model and the SGDOE-2.1e were compared and showed a good match with each. The SGDOE-2.1e model was then further modified based on the ASHRAE Standard 90.1-1999 commercial building energy code. A code-compliant (ASHRAE Standard 90.1-1999) SGDOE-2.1e simulation model was then used as a baseline for the evaluation of the high-performance measures. A total of 14 high-performance measures iv were implemented including the energy savings, while the comfort level was maintained based on the ASHRAE comfort zone. In addition to the 14 high-performance measures, solar thermal and solar PV system analysis were integrated with the SGDOE-2.1e simulation model to further reduce the annual energy use. Finally, specifications of the proposed easy-to-use simulation tool were developed. This tool includes options to choose systems from the 14 high-performance measures and solar systems. The proposed easy-to-use systems selection tool can be used for new building practitioners and existing building owners as well to evaluate the performance of their new buildings compared to the ASHRAE Standard 90.1-1999 code-compliant building, and to assess the feasibility of implementing high-performance measures to their existing buildings in terms of energy and cost savings.

Cho, S.

2009-08-01T23:59:59.000Z

325

EXTINGUISHMENT TESTS OF CONTINUOUSLY ...  

Science Conference Proceedings (OSTI)

... Page 8. Table 2. Summary of Conductive Heating Tests with HFC-227ea. CONDOM CONDO06 CONDO07 CONDO13 CONDO 1 8 SAMPLE -=I=- ...

2011-10-13T23:59:59.000Z

326

Geothermal energy. Program summary  

DOE Green Energy (OSTI)

Brief descriptions of geothermal projects funded through the Department of Energy during FY 1978 are presented. Each summary gives the project title, contractor name, contract number, funding level, dates, location, and name of the principal investigator, together with project highlights, which provide informaion such as objectives, strategies, and a brief project description. (MHR)

Not Available

1979-06-01T23:59:59.000Z

327

Test | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Test Test Summary Test More Documents & Publications Evaluation Report: OAS-M-12-01 Evaluation Report: OAS-M-11-01 Evaluation Report: OAS-L-13-01...

328

Summary of Changes  

NLE Websites -- All DOE Office Websites (Extended Search)

to to Procedure 200.4 Records Management Revised Version Issued as P 200.4B LM Procedure 200.4, Records Management of 3/14/07 has undergone revisions. The procedure has been revised to reflect changes in definitions and formatting and to reflect LM's increased emphasis on electronic records. Please replace LM Procedure 200.4A with LM Procedure 200.4B. The most recent and official controlled hard copy version of this document resides with LM's Directives Coordinator. An electronic version of the controlled document has been placed on the LM Intranet for employee use. Printed hard copies of this electronic version are considered uncontrolled documents. INITIATED BY: Office of Business Operations NO. OF PAGES/ATTACHMENTS: 19 pages, 9 attachments

329

Summary of Changes  

NLE Websites -- All DOE Office Websites (Extended Search)

1-1 1-1 File Plan Usage Revised Version Issued as P 200.1-1C LM Procedure 200.1-1B, File Plan of 11/1/07, has undergone revisions. The revised procedure includes formatting updates and extensive revisions to the definitions section. Please replace LM Procedure 200.1-1B with LM Procedure 200.1-1C. The most recent and official controlled hard copy version of this document resides with LM's Directives Coordinator. An electronic version of the controlled document has been placed on the LM Intranet for employee use. Printed hard copies of this electronic version are considered uncontrolled documents. U.S. Department of Energy Office of Legacy Management Procedure: 200.1-1C Effective: 1/26/09 SUBJECT: FILE PLAN USAGE 1. PURPOSE. To provide personnel with instructions for identifying, filing, maintaining, and

330

Decision Summaries | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Decision Summaries Decision Summaries Decision Summaries RSS January 16, 2014 Summary of Decisions - December 30, 2013 - January 3, 2014 Decisions were issued on: - Privacy Act Appeal January 10, 2014 Summary of Decisions - MM DD YYYY - MM DD YYYY Decisions were issued on: - Personnel Security (10 CFR Part 710) December 27, 2013 Summary of Decisions - December 23, 2013 - December 27, 2013 Decisions were issued on: - Freedom of Information Act Appeal - Personnel Security (10 CFR Part 710) December 20, 2013 Summary of Decisions - December 16, 2013 - December 20, 2013 Decisions were issued on: - Freedom of Information Act Appeal - Personnel Security (10 CFR Part 710) December 13, 2013 Summary of Decisions - December 9, 2013 - December 13, 2013 Decisions were issued on: - Freedom of Information Act Appeal

331

Microsoft Word - Summary.doc  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Summary Summary v TABLE OF CONTENTS Table of Contents .......................................................................................................................................................... v List of Figures .............................................................................................................................................................. vi List of Tables ................................................................................................................................................................ vi Acronyms, Abbreviations, and Conversion Charts ..................................................................................................... vii S.1 Introduction and Purpose and Need ...........................................................................................................S-1

332

DOE-ID Operations Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

September 10, 2013 DOE-ID Operations Summary For the Period August 12, 2013 through August 26, 2013 EDITOR'S NOTE: The following is a summary of contractor operations at the Idaho...

333

OE Summary 2005-09  

NLE Websites -- All DOE Office Websites (Extended Search)

Issue OPERATING EXPERIENCE SUMMARY U.S. Department of Energy Office of Environment, Safety and Health OE Summary 2005-09 June 7, 2005 EH Publishes "Just-In-Time" Reports The...

334

Department of Energy Idaho Operations Summary Releases  

NLE Websites -- All DOE Office Websites (Extended Search)

Press Box > DOE-Idaho Operations Summary DOE-Idaho Operations Summary These summaries provide information on health, safety and environmental incidents at DOE facilities in Idaho....

335

Baldrige Program Business Plan Summary  

Science Conference Proceedings (OSTI)

... This summary describes the Baldrige Performance Excellence Program's transition from funding via federal appropriations to a self-sustaining ...

2013-02-14T23:59:59.000Z

336

Mirror Confinement Systems: project summaries  

SciTech Connect

This report contains descriptions of the projects supported by the Mirror Confinement Systems (MCS) Division of the Office of Fusion Energy. The individual project summaries were prepared by the principal investigators, in collaboration with MCS staff office, and include objectives and milestones for each project. In addition to project summaries, statements of Division objectives and budget summaries are also provided.

1980-07-01T23:59:59.000Z

337

DESIGN GUIDELINE SUMMARY  

NLE Websites -- All DOE Office Websites (Extended Search)

3 Rev. 3 3 Rev. 3 August 2003 Rev. June 2004 Design Guideline Summary Based on the GEOVISION Report of Stanford Linear Accelerator Tunnel Vibration Measurements Parsons Pasadena, CA For Stanford Linear Accelerator Center Stanford University Stanford, CA Abstract: This summary report is provided in order to suggest how the measurement data from the GEOVision report might be used by SLAC for their proposed Next Linear Collider facility. See the referenced report "Stanford Linear Accelerator Tunnel Vibration Measurements, Conducted at MTA Universal Subway Station, North Hollywood, California", by GEOVision dated July 28, 2003. The following discussions are an attempt to determine an upper bound methodology that can be used for design purposes. The data in the

338

Preliminary Summary of Findings  

NLE Websites -- All DOE Office Websites (Extended Search)

Diversity Focus Groups Diversity Focus Groups Summary Report Prepared by Doug Sarno, The Perspectives Group This report provides a summary of 23 focus groups conducted between November 2008 and January 2009 with Fermilab employees and users. Purpose of the Focus Groups The purpose of the focus groups was to further explore the issues raised by the report of the Committee on the Status of Women in Physics (CSWP) and the Committee on Minorities (COM) of the American Physical Society (APS) on their visit to Fermilab on May 20-21, 2008. That visit included conversations with 47 self-selected participants and raised a number of important issues regarding diversity and workplace issues at Fermilab. The report can be found at http://www.fnal.gov/pub/diversity/files/APS_Report.pdf

339

5.0 SUMMARY  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

0 SUMMARY 0 SUMMARY This environmental assessment provides an analysis of several approaches to the handling of hazardous and mixed wastes at DOE's Mound Plant in Miamisburg, Ohio. The first approach considered, the proposed action, involves the operation of an existing glass metter (also known as a Penberthy Pyro·Converter joule·heated glass furnace) for the treatment of hazardous and mixed wastes. The analysis also considers the no-action alternative, involving the continuance of existing practices at Mound for the handling of hazardous and mixed wastes, as well as various on-site and off-site treatment, storage, or disposal alternatives, Under the proposed action, the primary potential sources of environmental impact are air emissions and effluent discharges, Potential changes in air and water quality may

340

COR Summary of Experience  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

COR SUMMARY OF EXPERIENCE COR SUMMARY OF EXPERIENCE Effective January 1, 2012 CORs who are applying for certification must demonstrate past contracting, acquisition, procurement, program/project management, and general business experience. This experience is based on a set of competencies. Some of the competencies are listed below to use as a reference when you are documenting your previous experience. Use this template to document your experience. Experience should be supported by a written confirmation from the cognizant Contracting Officer/Contract Specialist showing the contract number, title and date(s) to which the experience applied. Once you have completed this document, please forward it and its supporting statement(s) to your Site Acquisition Career Manager (SACM) as part of your application for COR certification.

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


341

GLOVEBOX GLOVE CHARACTERIZATION SUMMARY  

SciTech Connect

A task was undertaken to determine primarily the permeation behavior of various glove compounds from four manufacturers. As part of the basic characterization task, the opportunity to obtain additional mechanical and thermal properties presented itself. Consequently, a total of fifteen gloves were characterized for permeation, Thermogravimetric Analysis, Puncture Resistance, Tensile Properties and Dynamic Mechanical Analysis. Detailed reports were written for each characterization technique used. This report contains the summary of the results.

Korinko, P.

2012-05-14T23:59:59.000Z

342

Computerized procedures system  

DOE Patents (OSTI)

An online data driven computerized procedures system that guides an operator through a complex process facility's operating procedures. The system monitors plant data, processes the data and then, based upon this processing, presents the status of the current procedure step and/or substep to the operator. The system supports multiple users and a single procedure definition supports several interface formats that can be tailored to the individual user. Layered security controls access privileges and revisions are version controlled. The procedures run on a server that is platform independent of the user workstations that the server interfaces with and the user interface supports diverse procedural views.

Lipner, Melvin H. (Monroeville, PA); Mundy, Roger A. (North Huntingdon, PA); Franusich, Michael D. (Upper St. Clair, PA)

2010-10-12T23:59:59.000Z

343

Geothermal Energy Summary  

DOE Green Energy (OSTI)

Following is complete draft.Geothermal Summary for AAPG Explorer J. L. Renner, Idaho National Laboratory Geothermal energy is used to produce electricity in 24 countries. The United States has the largest capacity (2,544 MWe) followed by Philippines (1,931 MWe), Mexico (953 MWe), Indonesia (797 MWe), and Italy (791 MWe) (Bertani, 2005). When Chevron Corporation purchased Unocal Corporation they became the leading producer of geothermal energy worldwide with projects in Indonesia and the Philippines. The U. S. geothermal industry is booming thanks to increasing energy prices, renewable portfolio standards, and a production tax credit. California (2,244 MWe) is the leading producer, followed by Nevada (243 MWe), Utah (26 MWe) and Hawaii (30 MWe) and Alaska (0.4 MWe) (Bertani, 2005). Alaska joined the producing states with two 0.4 KWe power plants placed on line at Chena Hot Springs during 2006. The plant uses 30 liters per second of 75C water from shallow wells. Power production is assisted by the availability of gravity fed, 7C cooling water (http://www.yourownpower.com/) A 13 MWe binary power plant is expected to begin production in the fall of 2007 at Raft River in southeastern Idaho. Idaho also is a leader in direct use of geothermal energy with the state capital building and several other state and Boise City buildings as well as commercial and residential space heated using fluids from several, interconnected geothermal systems. The Energy Policy Act of 2005 modified leasing provisions and royalty rates for both geothermal electrical production and direct use. Pursuant to the legislation the Bureau of Land management and Minerals Management Service published final regulations for continued geothermal leasing, operations and royalty collection in the Federal Register (Vol. 72, No. 84 Wednesday May 2, 2007, BLM p. 24358-24446, MMS p. 24448-24469). Existing U. S. plants focus on high-grade geothermal systems located in the west. However, interest in non-traditional geothermal development is increasing. A comprehensive new MIT-led study of the potential for geothermal energy within the United States predicts that mining the huge amounts of stored thermal energy in the Earths crust not associated with hydrothermal systems, could supply a substantial portion of U.S. electricity with minimal environmental impact (Tester, et al., 2006, available at http://geothermal.inl.gov). There is also renewed interest in geothermal production from other non-traditional sources such as the overpressured zones in the Gulf Coast and warm water co-produced with oil and gas. Ormat Technologies, Inc., a major geothermal company, recently acquired geothermal leases in the offshore overpressured zone of Texas. Ormat and the Rocky Mountain Oilfield Testing Center recently announced plans to jointly produce geothermal power from co-produced water from the Teapot Dome oilfield (Casper Star-Tribune, March 2, 2007). RMOTC estimates that 300 KWe capacity is available from the 40,000 BWPD of 88C water associated with oil production from the Tensleep Sandstone (Milliken, 2007). The U. S. Department of Energy is seeking industry partners to develop electrical generation at other operating oil and gas fields (for more information see: https://e-center.doe.gov/iips/faopor.nsf/UNID/50D3734745055A73852572CA006665B1?OpenDocument). Several web sites offer periodically updated information related to the geothermal industry and th

J. L. Renner

2007-08-01T23:59:59.000Z

344

Summary of Changes  

Office of Legacy Management (LM)

3 3 Processing Litigation Requests Revised Version Issued as P 200.1-3C LM Procedure 200.1-3B, Processing Litigation Requests of 10/24/07, has undergone revisions. The revised procedure includes updated definitions, a reference to Vaughn indexes, and minor formatting adjustments. Please replace LM Procedure 200.1-3B with LM Procedure 200.1-3C. U.S. Department of Energy Office of Legacy Management The most recent and official controlled hard copy version of this document resides with LM's Directives Coordinator. An electronic version of the controlled document has been placed on the LM Intranet for employee use. Printed hard copies of this electronic version are considered uncontrolled documents. INITIATED BY: Office of Business Operations

345

Summary of Changes  

NLE Websites -- All DOE Office Websites (Extended Search)

341.1 341.1 Energy Employees Occupational Illness Compensation Program Act (EEOICPA) Processing Revised Version Issued as P 341.1C LM Procedure 341.1B, Energy Employees Occupational Illness Compensation Program Act (EEOICPA) Processing of 9/25/07, has undergone minor revisions. The revised procedure includes updated definitions and formatting. Please replace LM Procedure 341.1B with LM Procedure 341.1C. The most recent and official controlled hard copy version of this document resides with LM's Directives Coordinator. An electronic version of the controlled document has been placed on the LM Intranet for employee use. Printed hard copies of this electronic version are considered uncontrolled documents. U.S. Department of Energy Office of Legacy Management

346

Summary of Changes  

Office of Legacy Management (LM)

341.1 Energy Employees Occupational Illness Compensation Program Act (EEOICPA) Processing Revised Version Issued as P 341.1C LM Procedure 341.1B, Energy Employees Occupational...

347

Team Summary | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Team Summary Team Summary Team Summary Team Summary Purpose: Identify, prioritize, and resolve issues for effective site revitalization. Address crosscutting issues. Incorporate ARI's mission into programmatic business practices. Team Attributes and Functions: Coordinate using existing site and program protocols (ARI Task Force is not responsible for site-specific ARI projects or programs). Resolve issues through: Lessons learned Information resources Policy statements Process improvement techniques Proposed legislative changes Partnering with other agencies Facilitation Define, prioritize, and establish deliverable timelines and manage resources. Incorporate co-leadership and cross-functional membership. Team Summaries: Steering Committee Objective: Set the strategic direction, provide overarching leadership,

348

Human factoring administrative procedures  

Science Conference Proceedings (OSTI)

In nonnuclear business, administrative procedures bring to mind such mundane topics as filing correspondence and scheduling vacation time. In the nuclear industry, on the other hand, administrative procedures play a vital role in assuring the safe operation of a facility. For some time now, industry focus has been on improving technical procedures. Significant efforts are under way to produce technical procedure requires that a validated technical, regulatory, and administrative basis be developed and that the technical process be established for each procedure. Producing usable technical procedures requires that procedure presentation be engineered to the same human factors principles used in control room design. The vital safety role of administrative procedures requires that they be just as sound, just a rigorously formulated, and documented as technical procedures. Procedure programs at the Tennessee Valley Authority and at Boston Edison's Pilgrim Station demonstrate that human factors engineering techniques can be applied effectively to technical procedures. With a few modifications, those same techniques can be used to produce more effective administrative procedures. Efforts are under way at the US Department of Energy Nuclear Weapons Complex and at some utilities (Boston Edison, for instance) to apply human factors engineering to administrative procedures: The techniques being adapted include the following.

Grider, D.A.; Sturdivant, M.H.

1991-11-01T23:59:59.000Z

349

DOE/EA-1652: Final Environmental Assessment Wind Technology Testing Center (August 2009)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Wind Technology Testing Center Boston, Massachusetts August 2009 DOE/EA-1652 Department of Energy National Renewable Energy Laboratory 1617 Cole Boulevard Golden, CO 80401-3393 NREL - ENVIRONMENTAL ASSESSMENT FOR THE WIND TECHNOLOGY TESTING CENTER, BOSTON, M.A. FINAL EA, AUGUST 2009 i Table of Contents SUMMARY ................................................................................................................................. S-1 1.0 INTRODUCTION ............................................................................................................... 1 1.1 THE NATIONAL ENVIRONMENTAL POLICY ACT AND RELATED PROCEDURES ................................ 1 1.2 PURPOSE AND NEED ....................................................................................................................... 2

350

Large-Scale Offshore Wind Power in the United States: Executive Summary  

DOE Green Energy (OSTI)

This document provides a summary of a 236-page NREL report that provides a broad understanding of today's offshore wind industry, the offshore wind resource, and the associated technology challenges, economics, permitting procedures, and potential risks and benefits.

Musial, W.; Ram, B.

2010-09-01T23:59:59.000Z

351

Federal Agency NEPA Procedures  

Energy.gov (U.S. Department of Energy (DOE))

Each Federal agency is required to develop NEPA procedures that supplement the CEQ Regulations. Developed in consultation with CEQ, Federal agency NEPA procedures must meet the standards in the CEQ...

352

TECMIPT Test Operations Procedures (TTOP) For Passive ...  

Science Conference Proceedings (OSTI)

... Conducted disturbances induced by bursts and radio ... on the ingress protection rating (IP) requirement as ... of the initial mean gamma-ray or neutron ...

2013-01-10T23:59:59.000Z

353

ebXML Test Procedures DRAFT Document  

Science Conference Proceedings (OSTI)

... An attack is a specific application of an exploit [After AP-Glossary]. ... Page 7. NIST SP 500-269 January 2008 Page 7 of 13 1.5 Glossary of Terms ...

2013-05-07T23:59:59.000Z

354

Building Technologies Office: Current Test Procedure Waivers  

NLE Websites -- All DOE Office Websites (Extended Search)

2805 72FR71387 121707 Air Conditioners and Heat Pumps, Residential Multi-zone Unitary Small Air Conditioners and Heat Pumps ECR International, Inc. 78FR47681 080613 Heat Pump...

355

EM Policies and Procedures  

NLE Websites -- All DOE Office Websites (Extended Search)

Environmental Management (EM) Desktop References This page offers Environmental Management (EM) operating policies, procedures, standards, workaids, organizational charts, and...

356

Fingerprint Technology Testing for Identity Management  

Science Conference Proceedings (OSTI)

Fingerprint Technology Testing for Identity Management. Summary: The long term goal of this project is to address fingerprint ...

2010-10-05T23:59:59.000Z

357

Solar Total Energy Project final test report  

DOE Green Energy (OSTI)

The Solar Total Energy Project (STEP), a cooperative effort between the United States Department of Energy (DOE) and Georgia Power Company (GPC) located at Shenandoah, Georgia, has undergone several design modifications based on experience from previous operations and test programs. The experiences encountered were discussed in detail in the Solar Total Energy Project Summary Report'' completed in 1987 for DOE. Most of the proposed changes discussed in this report were installed and tested in 1987 as part of two 15-day test programs (SNL Contract No. 06-3049). However, several of the suggested changes were not completed before 1988. These plant modifications include a new distributed control system for the balance of plant (BOP), a fiber a optical communications ring for the field control system, and new control configuration reflecting the new operational procedures caused by the plant modifications. These modifications were tested during a non-consecutive day test, and a 60-day field test conducted during the autumn of 1989. These test were partially funded by SNL under Contract No. 42-4859, dated June 22, 1989. Results of these tests and preliminary analysis are presented in this test summary report. 9 refs., 19 figs., 7 tabs.

Nelson, R.F.; Abney, L.O.; Towner, M.L. (Georgia Power Co., Shenandoah, GA (USA))

1990-09-01T23:59:59.000Z

358

Summary Site Environmental Report  

NLE Websites -- All DOE Office Websites (Extended Search)

Site Environmental Report Site Environmental Report for Calendar Year 2011 ANL-12/02 (Summary) Environment, Safety, and Quality Assurance Division Argonne National Laboratory Disclaimer This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor UChicago Argonne, LLC, nor any of their employees or officers, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product,

359

FY 2009 Summary Report  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

of Performance and financial information FY 2009 DOE/CF-0045 The Reports Consolidation Act of 2000 authorizes Federal agencies, with the Office of Management and Budget's (OMB) concurrence, to consolidate various reports in order to provide performance, financial and related information in a more meaningful and useful format. In accordance with the Act, the Department of Energy (Department or DOE), has produced a consolidated Performance and Accountability Report (PAR) in previous years. For fiscal year (FY) 2009, the Department has chosen to produce an alternative report to the consolidated PAR and will produce an Agency Financial Report, an Annual Performance Report and a Summary of Performance and Financial

360

FY 1996 activity summary  

Science Conference Proceedings (OSTI)

The US Department of Energy Office of Nuclear and Facility Safety provides nuclear safety policy, independent technical evaluation, and technical support. A summary of these activities is provided in this report. These include: (1) changing the mission of the former production facilities to storage and waste management; (2) stabilizing nuclear materials not recycled due to production cessation or interruptions; (3) reformulating the authorization basis for existing facilities to convert to a standards based approach for operations consistent with modern expectations; and (4) implementing a modern regulatory framework for nuclear facilities. Enforcement of the Price-Anderson Amendments Act is also reported.

NONE

1997-04-01T23:59:59.000Z

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


361

EPRI BWR BRAC Summary  

Science Conference Proceedings (OSTI)

This report provides a summary of BRAC point average dose rates for the forty-six BWRs (thirty-five U.S., two Mexican, five European, and four Asian) currently participating in the EPRI BWR Chemistry Monitoring and Assessment project. The BRAC value is normally the average of the reactor recirculation suction and discharge contact dose rates measured with a shielded directional probe in the vertical piping sections. The results are categorized by chemistry regime, drains path, and, for NMCA plants, by BW...

2009-08-31T23:59:59.000Z

362

Preliminary designs for OTEC Stationkeeping Subsystems (SKSS). Summary report  

DOE Green Energy (OSTI)

This summary report presents a condensation of the designs as developed from requirements and concept selection to preliminary design. The study consists of the following six tasks: (1) Design requirements: establish design environmental conditions and criteria. Develop methodology to both assess SKSS reliability and performance, and minimize life cycle costs. (2) Conceptual design: develop at least two SKSS conceptual designs for both barge and spar platform (eight in all). Consider commercial plant SKSS, verify feasibility, define problem areas, estimate life cycle cost. Develop deployment, operation and maintenance scenarios. Recommend an SKSS concept for each platform. (3) Preliminary design; prepare preliminary designs for two SKSS concepts selected by NOAA/DOE. Optimize the designs, provide deployment and retrieval procedures, support requirements, evaute reliability and performance. Assess effects of watch circle and water depth variation. (4) Development and testing recommendations: recommend programs required to confirm design assumptions and performance predictions, including material and component development, and soils investigation. Estimate cost and schedule required to perform these programs. (5) Cost-time analysis: develop a detailed cost and schedule for the acquisition, transportation, deployment, inspection, maintenance, spares, replacement and salvage for the SKSS designs. (6) Commercial plant SKSS recommendations: assess applicability of designs to commercial plant SKSS. Recommend development program and at-sea tests as requied with estimate of cost and schedule. (WHK)

None

1979-02-15T23:59:59.000Z

363

Test report for cesium powder and pellets inner container decontamination method determination test  

SciTech Connect

This report documents the decontamination method determination testing that was performed on three cesium powder and pellets inner container test specimens The test specimens were provided by B and W Hanford Company (BVMC). The tests were conducted by the Numatec Hanford Company (NHC), in the 305 Building. Photographic evidence was also provided by NHC. The Test Plan and Test Report were provided by Waste Management Federal Services, Inc., Northwest Operations. Witnesses to testing included a test engineer, a BC project engineer, and a BC Quality Assurance (QA) representative. The Test Plan was modified with the mutual decision of the test engineer, the BWHC project engineer, and the BVMC QA representative. The results of this decision were written in red (permanent type) ink on the official copy of the test procedure, Due to the extent of the changes, a summary of the test results are provided in Section 3.0 of this Test Report. In addition, a copy of the official copy field documentation obtained during testing is included in Appendix A. The original Test Plan (HNF-2945) will be revised to indicate that extensive changes were required in the field during testing, however, the test documentation will stand as is (i.e., it will not be retyped, text shaded, etc.) due to the inclusion of the test parameters and results into this Test Report.

Kelly, D.L.

1998-08-17T23:59:59.000Z

364

Past DOE Technical Standards Program Procedures | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Past DOE Technical Standards Program Procedures Past DOE Technical Standards Program Procedures Past DOE Technical Standards Program Procedures TSPP July 2009 September 26, 2009 DOE-TSPP-0, Technical Standards Program Procedures - July 1, 2009 This document is the summary page for all of the DOE Technical Standards Program Procedures. August 26, 2009 DOE-TSPP-1, Technical Standards Program Responsibilities - July 1, 2009 This procedure describes the responsibilities of persons who are charged with implementing the DOE Technical Standards Program. August 26, 2009 DOE-TSPP-2, Establishing the Need for a Technical Standard - July 1, 2009 This procedure provides guidance for the routine maintenance of DOE Technical Standards. August 26, 2009 DOE-TSPP-3, Use of Non-Government Standards and Interaction with Non-Government Standards Bodies - July 1, 2009

365

LAI References and Summaries  

NLE Websites -- All DOE Office Websites (Extended Search)

Cart Sign In/Register Quick Data Search Help icon Go NASA Meatball Cart Sign In/Register Quick Data Search Help icon Go NASA Meatball No JAVASCRIPT Capabilities. This site will not function without JavaScript. Please use the Web Product Tree. or anonymous FTP at ftp://daac.ornl.gov/data. Global Leaf Area Index Data from Field Measurements, 1932-2000 References and summaries for literature on leaf area index (reviews, methodology, etc.) Barclay, H. J. (1998) Conversion of total leaf area to projcted leaf area in lodgepole pine and Douglas-fir. Tree PHysiology 18, 185-193. Summary It is noted that three distinct definitions of leaf area index (LAI) in the literature have no predictable relationship with each other. Conversion factors were derived, from total LAI to projected LAI of horizontal leaves and to projected LAI for inclined leaves of lodgepole pine and coastal Douglas-fir, enabling comparison of results from different studies. An algorithm was derived to allow determination of these factors based on twig angles and the angles that the foliage subtends with the twig. The conversion factor was more sensitive to differences in vertical angles of the twigs than to twig rotation or foliar arrangement on the twig.

366

Fourth Novatek Hammer Field Test Department of Energy Well PM-2-31  

NLE Websites -- All DOE Office Websites (Extended Search)

Novatek Hammer Field Test Novatek Hammer Field Test Department of Energy Well PM-2-31 Garfield County, Colorado September, 1995 Report Prepared for Mud Hammer Development Project Partners Mobil Oil Novatek Brian Tarr, MEPTEC Drilling MOBIL EXPLORATION AND PRODUCTION TECHNICAL CENTER Dallas, Texas September 1995 Fourth Novatek Hammer Field Test Department of Energy Well PM-2-31 September 1995 Contents Page EXECUTIVE SUMMARY 3 CONCLUSIONS 4 RECOMMENDATIONS5 5 Field Test Procedure and Results 6 APPENDIX 1 - Well Data 10 APPENDIX 2 - ∆P Calculations APPENDIX 3 - Novatek hammer drawings and photo.'s Fourth Novatek Hammer Field Test Department of Energy Well PM-2-31 September 1995 EXECUTIVE SUMMARY Objectives The primary objective of the fourth field test was to establish if the threshold level of power required to increase rock bit

367

OE Summary 2005-13  

NLE Websites -- All DOE Office Websites (Extended Search)

OE Summary 2005-13 September 6, 2005 * Unremoved ground cluster causes 1382.4 kV transformer damage ... 1 * Dewar tips over during transport, causing liquid...

368

,"South Dakota Natural Gas Summary"  

U.S. Energy Information Administration (EIA) Indexed Site

,"Workbook Contents" ,"South Dakota Natural Gas Summary" ,"Click worksheet name or tab at bottom for data" ,"Worksheet Name","Description"," Of Series","Frequency","Latest Data...

369

DOE ETV-1 electric test vehicle. Phase III: performance testing and system evaluation. Final report  

DOE Green Energy (OSTI)

The DOE ETV-1 represents the most advanced electric vehicle in operation today. Engineering tests have been conducted by the Jet Propulsion Laboratory in order to characterize its overall system performance and component efficiencies within the system environment. A dynamometer was used in order to minimize the ambient effects and large uncertainties present in track testing. Extensive test requirements have been defined and procedures were carefully controlled in order to maintain a high degree of credibility. Limited track testing was performed in order to corroborate the dynamometer results. Test results include an energy flow analysis through the major subsystems and incorporate and aerodynamic and rolling losses under cyclic and various steady speed conditions. A complete summary of the major output from all relevant dynamometer and track tests is also included as an appendix.

Kurtz, D. W.

1981-12-01T23:59:59.000Z

370

The National Criticality Experiments Research Center at the Device Assembly Facility, Nevada National Security Site: Status and Capabilities, Summary Report  

SciTech Connect

The National Criticality Experiments Research Center (NCERC) was officially opened on August 29, 2011. Located within the Device Assembly Facility (DAF) at the Nevada National Security Site (NNSS), the NCERC has become a consolidation facility within the United States for critical configuration testing, particularly those involving highly enriched uranium (HEU). The DAF is a Department of Energy (DOE) owned facility that is operated by the National Nuclear Security Agency/Nevada Site Office (NNSA/NSO). User laboratories include the Lawrence Livermore National Laboratory (LLNL) and Los Alamos National Laboratory (LANL). Personnel bring their home lab qualifications and procedures with them to the DAF, such that non-site specific training need not be repeated to conduct work at DAF. The NNSS Management and Operating contractor is National Security Technologies, LLC (NSTec) and the NNSS Safeguards and Security contractor is Wackenhut Services. The complete report provides an overview and status of the available laboratories and test bays at NCERC, available test materials and test support configurations, and test requirements and limitations for performing sub-critical and critical tests. The current summary provides a brief summary of the facility status and the method by which experiments may be introduced to NCERC.

S. Bragg-Sitton; J. Bess; J. Werner

2011-09-01T23:59:59.000Z

371

Summary.qxd  

NLE Websites -- All DOE Office Websites (Extended Search)

S-10 S-10 Summary 3.0 Alternatives For purposes of analysis, DOE used a modular approach in developing alternatives for this EIS. Under this approach, DOE identified a series of discrete projects, which can be linked together in different combinations to achieve the goals of the proposed action. Thus, some projects are included in more than one waste processing alternative. This modular approach provides DOE flexibility in analyzing waste processing alternatives and treatment options and in select- ing the preferred alternative. The facility disposition alternatives analysis con- siders all of the facilities that would be required to implement each waste processing alternative. 3.1 Identifying Alternatives DOE undertook and documented a process to identify the range of reasonable alternatives for

372

Meeting Summary Notes  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

National Transportation Stakeholders Forum (NTSF) National Transportation Stakeholders Forum (NTSF) May 26, 2010 Meeting Summary Notes Opening Remarks - Steve O'Connor, DOE Office of Packaging and Transportation Steve O'Connor, DOE/EM Office of Packaging and Transportation welcomed the group to this first National Transportation Stakeholders Forum (NTSF) and thanked the planning committee and the dedication of the Midwest Council of State Government for hosting the meeting. The NTSF will focus on transportation across the DOE complex. Mr. O'Connor announced that the meeting would be recorded and questions for the panel could either be written down and passed to the session moderator or asked via the central microphone. Planners for the meeting have worked to ensure a more engaging panel format and to minimize the use of formal presentations. Mr. O'Connor

373

COR Summary of Experience  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

COR SUMMARY OF EXPERIENCE Effective January 1, 2012, the Office of Federal Procurement Policy (OFPP) added a requirement for past COR experience to qualify for FAC-COR Level II (journeyman level) and III (senior/expert level). At least 1 year of COR experience is required to qualify for Level II; 2 years for Level III. OFPP strongly advises that applicants for Level III have prior experience at Level II. Applicants with no prior experience as an appointed COR must demonstrate proficiency in the specific competencies listed below for the same time period, validated by a cognizant Contracting Officer or Contract Specialist by signature below or an accompanying e-mail. Submit this form to your Site Acquisition Career Manager (SACM) as part of your application

374

Compilation of TRA Summaries  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

September 2011 September 2011 Technology Readiness Assessment Summary Number Title Report Date TRA-1 Waste Treatment and Immobilization Plant (WTP) Analytical Laboratory, Balance of Facilities and LAW Waste Vitrification Facilities at Hanford March 2007 TRA-2 Waste Treatment and Immobilization Plant (WTP) HLW Waste Vitrification Facility at Hanford March 2007 TRA-3 Waste Treatment and Immobilization Plant (WTP) Pretreatment Facility at Hanford March 2007 TRA-4 K Basins Sludge Treatment Process at Hanford August 2007 TRA-5 Savannah River Site Tank 48H Waste Treatment Project at SRS July 2007 TRA-6 233Uranium Downblending and Disposition Project at Oak Ridge/ORNL September 2008 TRA-7 SRS Salt Waste Processing Facility at SRS July 2009

375

Pinellas Remediation Agreement Summary  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Pinellas Pinellas Agreement Name Remediation Agreement for the Four and One-Half Acre Site in Largo, Pinellas County, Florida State Florida Agreement Type Remediation Agreement Legal Driver(s) CERCLA/ Atomic Energy Act of 1954, as amended/ Florida Air and Water Pollution Control Act Scope Summary Remediation of property adjacent to the former Pinellas Plant Parties DOE; Florida Department of Environmental Protection Date 3/12/2001 SCOPE * Remediate the groundwater under a parcel of property adjacent to DOE's former Pinellas Plant to levels consistent with industrial use. * Complete remedial actions at the site in accordance with a Remedial Action Plan prepared by DOE and approved by FDEP. * Submit quarterly reports of interim remedial actions at the Site.

376

Partnership Overview and Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

SWP Phase 3 Deployment Project: SWP Phase 3 Deployment Project: Overview and Summary Brian McPherson and Reid Grigg RCSP Annual Review Meeting October 5-7, 2010 Pittsburgh, PA 2 Acknowledgements * Many thanks to the U.S. Department of Energy and NETL for supporting this project * We express our gratitude also to our many industry partners, who have committed a great deal of time, funding and other general support for these projects * The work presented today is co-authored by all partners in the Southwest Partnership 3 Southwest Regional Partnership In all partner states: * major universities * geologic survey * other state agencies * over 50 partners as well as * Western Governors Association * five major utilities * seven energy companies * three federal agencies * the Navajo Nation * many other critical partners

377

2011 NTSF Meeting Summary  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

2 2 National Transportation Stakeholders Forum Denver, Colorado May 11-12, 2011 Meeting Summary Notes The second annual meeting of the National Transportation Stakeholders Forum (NTSF) was held in Denver, Colorado, and was hosted by the Western Governors' Association. Day 1, May 11, 2011 OPENING PLENARY, Keynote: Cynthia Anderson, Chief Operating Officer, Office of Environmental Management, DOE - A Journey to Excellence Ms. Anderson spoke about the Office of Environmental Management's (EM) Journey to Excellence. The mission of EM is to safely transform the environmental legacy of the Cold War into assets available for the Nation's future by completing quality cleanup work on schedule and within cost, delivering demonstrated value to the American taxpayer. Priorities for EM include:

378

FullSummary  

NLE Websites -- All DOE Office Websites (Extended Search)

Selected Selected NERSC Initiative for Scientific Exploration (NISE) Research Summaries: 2010 Project: D ecadal P redictability i n C CSM4 PI: H aiyan T eng a nd G rant B ranstator, NCAR NERSC R epo: m p9 NISE h ours a warded: 1 .6 M With the NISE award, we have carried out two 25---member CCSM4 ensemble experiments with perturbed initial condition. The ensemble experiment has led to findings that should influence the direction of major ongoing international climate research efforts. In order to provide society with the most accurate possible estimates of climate in the coming decades, the scientific community is devoting much effort to initializing some forecasts in the next IPCC assessment report with estimates of the current state of the climate system. The results

379

Retlif Testing Laboratories  

Science Conference Proceedings (OSTI)

... of radio disturbance characteristics of electrical motor-operated and ... and Test Procedures for Airborne Equipment - Section 15 - Magnetic Effect. ...

2014-01-03T23:59:59.000Z

380

University of Waste Procedures  

E-Print Network (OSTI)

University of Maryland Hazardous And Regulated Waste Procedures Manual Revised July 2001 #12;Review II. HAZARDOUS WASTE MANAGEMENT III. BIOLOGICAL, PATHOLOGICAL AND MEDICAL WASTE (BPMW) MANAGEMENT IV. LOW-LEVEL RADIOACTIVE WASTE (LLRW) MANAGEMENT V. EMERGENCY PROCEDURES VI. WASTE MINIMIZATION VII

Rubloff, Gary W.

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


381

NERSC-InitialSummary.pptx  

NLE Websites -- All DOE Office Websites (Extended Search)

Day-1 Summary Day-1 Summary Large Scale Computing and Storage Requirements for Biological and Environmental Research Joint BER / ASCR / NERSC Workshop NERSC Lawrence Berkeley National Laboratory May 7-8, 2009 Summary * Users need for more resources for DOE SC computing - But we need more concrete, science-based justification * Need for predictable throughput - Microbial Genomics and GFDL ESM - Need to differentiate between real-time needs and higher desired batch turnaround * Slow batch turnaround time may be because of queue policy or because of insufficient resources Summary * Data management issues transcend all science areas, multiple projects - Exponentially increasing - Some disagreement on volume at a single site Summary * Users see need for guidance / help in

382

2010 Hyundai LPI Hybrid Test Cell Location  

NLE Websites -- All DOE Office Websites (Extended Search)

Hyundai LPI Hybrid Test Cell Location APRF- 4WD Vehicle Setup Information Downloadable Dynamometer Database (D 3 )- Test Summary Sheet Vehicle Architecture Alternative Fuel Hybrid...

383

VEHICLE TECHNOLOGIES PROGRAM Advanced Vehicle Testing Activity  

NLE Websites -- All DOE Office Websites (Extended Search)

Testing Activity North American PHEV Demonstration Monthly Summary Report - Hymotion Prius (V2Green data logger) Total Number Vehicles - 169 (May 2010) Total Cumulative Test...

384

2010 Volkswagen Golf TDI Test Cell Location  

NLE Websites -- All DOE Office Websites (Extended Search)

Golf TDI Test Cell Location APRF- 4WD Vehicle Setup Information Downloadable Dynamometer Database (D 3 )- Test Summary Sheet Vehicle Architecture Conventional- Start Stop Vehicle...

385

Summary of Waste Calcination at INTEC  

SciTech Connect

Fluidized-bed calcination at the Idaho Nuclear Technologies and Engineering Center (INTEC, formally called the Idaho Chemical Processing Plant) has been used to solidify acidic metal nitrate fuel reprocessing and incidental wastes wastes since 1961. A summary of waste calcination in full-scale and pilot plant calciners has been compiled for future reference. It contains feed compositions and operating conditions for all the processing campaigns for the original Waste Calcining Facility (WCF), the New Waste Calcining Facility (NWCF) started up in 1982, and numerous small scale pilot plant tests for various feed types. This summary provides a historical record of calcination at INTEC, and will be useful for evaluating calcinability of future wastes.

O' Brien, Barry Henry; Newby, Bill Joe

2000-10-01T23:59:59.000Z

386

Appendix B: Summary Tables  

Gasoline and Diesel Fuel Update (EIA)

U.S. Energy Information Administration | Analysis of Impacts of a Clean Energy Standard as requested by Chairman Bingaman U.S. Energy Information Administration | Analysis of Impacts of a Clean Energy Standard as requested by Chairman Bingaman Appendix B: Summary Tables Table B1. The BCES and alternative cases compared to the Reference case, 2025 2009 2025 Ref Ref BCES All Clean Partial Credit Revised Baseline Small Utilities Credit Cap 2.1 Credit Cap 3.0 Stnds + Cds Generation (billion kilowatthours) Coal 1,772 2,049 1,431 1,305 1,387 1,180 1,767 1,714 1,571 1,358 Petroleum 41 45 43 44 44 44 45 45 45 43 Natural Gas 931 1,002 1,341 1,342 1,269 1,486 1,164 1,193 1,243 1,314 Nuclear 799 871 859 906 942 889 878 857 843 826 Conventional Hydropower 274 306 322 319 300 321 316 298 312 322 Geothermal 15 25 28 25 31 24 27 22 23 24 Municipal Waste 18 17 17 17 17 17 17 17 17 17 Wood and Other Biomass 38 162 303 289 295 301 241 266

387

Annual Planning Summaries: 2013 | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

3 3 Annual Planning Summaries: 2013 March 25, 2013 2013 Annual Planning Summary for the Argonne Site Office 2013 Annual Planning Summary for the Argonne Site Office March 25, 2013 2013 Annual Planning Summary for the Argonne Site Office 2013 Annual Planning Summary for the Argonne Site Office January 30, 2013 2013 Annual Planning Summary for the Carlsbad Field Office 2013 Annual Planning Summary for the Carlsbad Field Office January 30, 2013 2013 Annual Planning Summary for the Oak Ridge Office 2013 Annual Planning Summary for the Oak Ridge Office January 30, 2013 2013 Annual Planning Summary for the Western Area Power Administration 2013 Annual Planning Summary for the Western Area Power Administration January 29, 2013 2013 Annual Planning Summary for the Idaho Operations Office

388

FY 2014 Budget Request Summary Table | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Summary Table FY 2014 Budget Request Summary Table Summary Table by Appropriations Summary Table by Organization More Documents & Publications FY 2014 Budget Justification Details...

389

2013 Annual NEPA Planning Summary | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Annual NEPA Planning Summary 2013 Annual NEPA Planning Summary 2013 Annual NEPA Planning Summary 2013 Annual NEPA Planning Summary More Documents & Publications 2013 Annual...

390

Milwaukee Meeting Summary - July, 1998  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Milwaukee Meeting Summary - July, 1998 Milwaukee Meeting Summary - July, 1998 Over 150 Members, participants, and observers representing state, tribal, and local governments, regional groups, industry, professional organizations, and the Department of Energy, met to address a variety of issues related to DOE's transportation activities for radioactive materials. A number of Departmental Programs with transportation components were represented, including: the Office of Environmental Management, the Office of Civilian Radioactive Waste Management (including the Yucca Mountain Project Office), the Office of Naval Reactors, the Waste Isolation Pilot Project, and the Office of Defense Programs. Topic Group Summaries and Comments DOE Program Office Discussions General Planning Breakout Discussions

391

NFRC Procedures for Laminates  

NLE Websites -- All DOE Office Websites (Extended Search)

Laminates Laminates Last update: 12/10/2013 07:29 PM NFRC now has a procedure for making laminates in Optics5 and importing those laminate constructions into WINDOW5 to be used in a whole product calculation. The information presented below is provided to help simulators with this process. Feel free to contact us at WINDOWHelp@lbl.gov with questions or comments. NFRC Laminate Procedure Laminate Procedures (approved by NFRC) (PDF file) Approved Interlayer List (IGDB 33.0) (PDF file) NFRC Laminate Procedure Training Powerpoint with Examples (This Powerpoint presentation was used in the NFRC web based training sessions in December 2006 and January 2007) PowerPoint Presentation (PPT file) PowerPoint Presentation (PDF file) Help and Troubleshooting Error Messages The table below contains common warnings and error messages that may appear in Optics5 when calculating a laminate. Some of the messages can be ignored, and some are significant, which is indicated in the table.

392

NSLS Services | Shipping Procedures  

NLE Websites -- All DOE Office Websites (Extended Search)

NSLS Shipping Procedures For shipments arriving at the NSLS from other locations, please ship via Federal Express. If this is not possible, or if you have any questions, please...

393

PROCEDURE FOR PREPARING  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

PROCEDURE FOR PREPARING PROCEDURE FOR PREPARING RECORDS INVENTORY AND DISPOSITION SCHEDULES (RIDS) Revision 1 November 1, 2007 Records Management Division, IM-23 PROCEDURE FOR PREPARING RECORDS INVENTORY AND DISPOSITION SCHEDULES (RIDS) 1. If the records have not yet been inventoried, see "Procedure for Conducting a Records Inventory." An inventory must be completed prior to preparing the RIDS. 2. The Records Inventory and Disposition Schedules (RIDS) should be reviewed and updated at least annually on DOE F 1324.10 and DOE F 1324.9. The RIDS covers all record, administrative and programmatic, as well as non- record material. The RIDS must include: a. Complete and detailed information identifying the organization (s) responsible for the records.

394

Operating Procedures Guideline  

Science Conference Proceedings (OSTI)

The intention of this report is to provide guidance for generating stations management and personnel striving for successful methods of developing effective operating procedures. Standard operating procedure management is used in most businesses and industries to assist in the safe and efficient operation of those companies. Effectively managing the program is essential in order to comply with mandatory regulations, maintain the highest possible level of plant integrity, minimize human ...

2012-12-12T23:59:59.000Z

395

Annual Planning Summaries: Stanford Linear Accelerator (SLAC...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Stanford Linear Accelerator (SLAC) Annual Planning Summaries: Stanford Linear Accelerator (SLAC) Document(s) Available For Download January 11, 2012 2012 Annual Planning Summary...

396

Annual Planning Summaries: Environmental Management (EM) | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Environmental Management (EM) Annual Planning Summaries: Environmental Management (EM) Document(s) Available For Download February 3, 2012 2012 Annual Planning Summary for...

397

University of Colorado Technology Marketing Summaries - Energy ...  

University of Colorado Technology Marketing Summaries. Here youll find marketing summaries for technologies available for licensing from the University of Colorado ...

398

Annual Planning Summaries: 2010 | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

for each NEPA review identified. January 29, 2010 2010 Annual Planning Summary for Intelligence and Counterintelligence (IN) Annual Planning Summaries briefly describe the...

399

Annual Planning Summaries: National Nuclear Security Administration...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Annual Planning Summary for National Nuclear Security Administration Service Center (NNSA-SC) Annual Planning Summaries briefly describe the status of ongoing NEPA compliance...

400

Energy Savings Performance Contracts Summary | Department of...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Centers Field Sites Power Marketing Administration Other Agencies You are here Home Energy Savings Performance Contracts Summary Energy Savings Performance Contracts Summary...

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


401

Annual Planning Summaries | Department of Energy  

NLE Websites -- All DOE Office Websites (Extended Search)

Status & Schedules Annual Planning Summaries Annual Planning Summaries NEPA Documents Status & Schedules DOE Order 451.1B, National Environmental Compliance Program, Section...

402

TEST TEST TEST  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

NNSA/EA-1375 NNSA/EA-1375 Environmental Assessment for Construction and Operation of a New Office Building and Related Structures within TA-3 at Los Alamos National Laboratory, Los Alamos, New Mexico July 26, 2001 Department of Energy National Nuclear Security Administration Los Alamos Area Office Environmental Assessment for Proposed Construction and Operation of a New Office Building and Related Structures NNSA/LAAO July 26,, 2001 iii Contents Acronyms and Terms .................................................................................................................. vi Executive Summary ..................................................................................................................... ix 1.0 Purpose and Need

403

Advanced Vehicle Testing Activity: Neighborhood Electric Vehicle...  

NLE Websites -- All DOE Office Websites (Extended Search)

Procedures to someone by E-mail Share Advanced Vehicle Testing Activity: Neighborhood Electric Vehicle Specifications and Test Procedures on Facebook Tweet about Advanced Vehicle...

404

Neutron Irradiation of Hydrided Cladding Material in HFIR Summary of  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Neutron Irradiation of Hydrided Cladding Material in HFIR Summary Neutron Irradiation of Hydrided Cladding Material in HFIR Summary of Initial Activities Neutron Irradiation of Hydrided Cladding Material in HFIR Summary of Initial Activities Irradiation is known to have a significant impact on the properties and performance of Zircaloy cladding and structural materials (material degradation processes, e.g., effects of hydriding). This UFD study examines the behavior and performance of unirradiated cladding and actual irradiated cladding through testing and simulation. Three capsules containing hydrogen-charged Zircaloy-4 cladding material have been placed in the High Flux Isotope Reactor (HFIR). Irradiation of the capsules was conducted for post-irradiation examination (PIE) metallography. Neutron Irradiation of Hydrided Cladding Material in HFIR Summary of

405

ARM - Datastreams - aeri01summary  

NLE Websites -- All DOE Office Websites (Extended Search)

summary summary Documentation Data Quality Plots Citation DOI: 10.5439/1025141 [ What is this? ] Generate Citation ARM Data Discovery Browse Data Comments? We would love to hear from you! Send us a note below or call us at 1-888-ARM-DATA. Send Datastream : AERI01SUMMARY Atmospheric Emitted Radiance Interferometer (AERI) 01: summary data Active Dates 1995.07.22 - 2014.01.02 Measurement Categories Radiometric Originating Instrument Atmospheric Emitted Radiance Interferometer (AERI) Measurements Only measurements considered scientifically relevant are shown below by default. Show all measurements Measurement Units Variable Ambient blackbody temperature - apex K ABBapexTemp ( time ) Ambient blackbody temperature K ABBbottomTemp ( time ) Ambient blackbody temperature - rim top K ABBtopTemp ( time )

406

Sight and Sound - Project Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Summary Scenario Student Pages Internet Links Index SubjectContent Area: PhysicsBiology Target Audience: This project primarily targets grades 9-12. The project is best suited as...

407

OE Summary 2005-14  

NLE Websites -- All DOE Office Websites (Extended Search)

Inside This Issue U.S. Department of Energy Office of Environment, Safety and Health OE Summary 2005-14 November 16, 2005 * Dump truck severs overhead power lines .... 1 * Improper...

408

Executive Summary Introduction  

E-Print Network (OSTI)

implications of a detailed study of the health impact on the American people of radioactive fallout from estimates of doses and health risks from exposure to radioactive fallout from nuclear weapons tests exposed to radioactive fallout, and all organs and tissues 1 #12;of the body have received some radiation

409

Experiment DTA report for semiscale transparent vessel countercurrent flow tests  

SciTech Connect

Steady state air-water tests were performed as part of the Semiscale Blowdown and Emergency Core Cooling (ECC) Project to investigate downcomer countercurrent flow and downcomer bypass flow phenomena. These tests were performed in a plexiglass representation of the Semiscale pressure vessel which allowed changes to be madein the geometry of the upper annulus and downcomer for the purpose of investigating the sensitivity of downcomer and bypass flow to changes in system geometry. Tests were also performed to investigate the effects of two-phase inlet flows and different initial system pressures on countercurrent and bypass flow. Results for each test are presented in the form of computer printout of the measurements and of a summary of the pertinent calculated flow rates, pressures, and dimensionless volumetric fluxes. Descriptions of the test facility, instrumentation, operating procedures, and test conditions are also presented. An error analysis is presented for selected volumetric flux calculations. 10 references. (auth)

Hanson, D.J.

1975-10-01T23:59:59.000Z

410

Awardee Share Procedures  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Awardee Share Procedures Awardee Share Procedures Procedures for Correctly Reporting Awardee Share on the FAADS/FAADS Plus reporting screen in STRIPES To ensure proper reporting by DOE to USASpending.gov, you must enter the awardee share (also known as the cost share, recipient share, and non-federal share) manually on the FAADS/FAADS Plus reporting screen in STRIPES. The FAADS/FAADS Plus file is the financial assistance equivalent of the FPDS-NG data entry for acquisition awards. The awardee share amount is not system generated on the FAADS/FAADS Plus reporting screen like the obligation amount is. The fields on the FAADS/FAADS Plus form which must be entered when reporting a Cost-share Financial Assistance Award are: Field #17 Non-Federal Funding Sign Choose 'Obligation', which refers to a positive amount (sign), or 'Deobligation', which refers to a

411

Radiation Emergency Procedure Demonstrations  

NLE Websites -- All DOE Office Websites (Extended Search)

Managing Radiation Emergencies Managing Radiation Emergencies Procedure Demonstrations Procedure Demonstrations Note: RealPlayer is needed for listening to the narration that accompany these demonstrations. Real Player Dressing To Prevent the Spread of Radioactive Contamination This demonstration shows how your team can dress to prevent the spread of radioactive contamination. Click to begin presentation on dressing to prevent the spread of radioactive contamination. Preparing The Area This demonstration shows basic steps you can take to gather equipment and prepare a room to receive a patient who may be contaminated with radioactive material. Click to begin presentation on preparing a room to receive a radioactive contaminated patient. Removing Contaminated Clothing This demonstration shows the procedure for removing clothing from a patient who may be contaminated with radioactive material.

412

Final test report: demonsration testing in support of the Track 3system waste dislodging, retrieval and conveyance concepts  

SciTech Connect

This report contains the quantitative and qualitative data and information collected during performance of the Track 3 System testing protocol. Information contained herein focuses on the data collected during performance ofthe following Tests Procedures. *Test Procedure-1, Position Management Test Procedure-2, Waste Dislodging, Retrieval, and Conveyance and Decontamination *Test Procedure-3, Dynamic Response Test procedures, Safety Demonstration

Berglin, E.J.

1997-07-24T23:59:59.000Z

413

Advanced Vehicle Testing Activity: Urban Electric Vehicle Specificatio...  

NLE Websites -- All DOE Office Websites (Extended Search)

Test Procedures to someone by E-mail Share Advanced Vehicle Testing Activity: Urban Electric Vehicle Specifications and Test Procedures on Facebook Tweet about Advanced Vehicle...

414

Advanced Vehicle Testing Activity: Hybrid Electric Vehicle Specificati...  

NLE Websites -- All DOE Office Websites (Extended Search)

Test Procedures to someone by E-mail Share Advanced Vehicle Testing Activity: Hybrid Electric Vehicle Specifications and Test Procedures on Facebook Tweet about Advanced Vehicle...

415

Advanced Vehicle Testing Activity: Oil Bypass Filter Specifications...  

NLE Websites -- All DOE Office Websites (Extended Search)

and Test Procedures to someone by E-mail Share Advanced Vehicle Testing Activity: Oil Bypass Filter Specifications and Test Procedures on Facebook Tweet about Advanced...

416

Precipitator Performance Estimation Procedure  

Science Conference Proceedings (OSTI)

Increased availability of data to use with an existing computer model makes it possible for utilities to calculate electrostatic precipitator performance without access to industry databases. This report examines the accuracy of the model and develops procedures to make it a more useful tool for troubleshooting precipitator performance and for selecting the size of a new unit.

1986-12-22T23:59:59.000Z

417

Conceptual design summary  

Science Conference Proceedings (OSTI)

The Advanced Neutron Source (ANS) is a new basic and applied research facility based on a powerful steady-state research reactor that provides beams of neutrons for measurements and experiments in the fields of materials science and engineering, biology, chemistry, materials analysis, and nuclear science. The useful neutron flux for these experiments will be at least five times, and in some cases twenty times, more than is available at the world's best existing facilities. In addition, ANS will provide irradiation capabilities for the production of radioisotopes for medical applications, research, and industry and facilities for materials irradiation testing. The need for a new steady-state neutron research facility in the United States was emphasized by the 1984 National Academy Report and confirmed by the Department of Energy's (DOE's) Energy Research Advisory Board in 1985. These studies defined a minimum thermal neutron flux requirement of 5 {times} 10{sup 19} m{sup {minus}2} {center dot} s{sup {minus}1}. The National Steering Committee for an Advanced Neutron Source, with representation from the major fields of science that will use the facility, was established in 1986 and has continued to define the performance requirements and instrument layouts needed by the user community. To minimize technical risks and safety issues, the project adopted a policy of not relying upon new inventions to meet the minimum performance criteria, and the design presented in this report is built on technologies already used in other facilities and development programs: for example, the involute aluminum-clad fuel plates common to HFIR and ILL and the uranium silicide fuel developed in DOE's Reduced Enrichment for Research and Test Reactors program and tested in reactors worldwide. At the same time, every state-of-the-art technique has been implemented to optimize neutron beam delivery at the experiments.

Peretz, F.J.

1992-09-01T23:59:59.000Z

418

Conceptual design summary  

Science Conference Proceedings (OSTI)

The Advanced Neutron Source (ANS) is a new basic and applied research facility based on a powerful steady-state research reactor that provides beams of neutrons for measurements and experiments in the fields of materials science and engineering, biology, chemistry, materials analysis, and nuclear science. The useful neutron flux for these experiments will be at least five times, and in some cases twenty times, more than is available at the world`s best existing facilities. In addition, ANS will provide irradiation capabilities for the production of radioisotopes for medical applications, research, and industry and facilities for materials irradiation testing. The need for a new steady-state neutron research facility in the United States was emphasized by the 1984 National Academy Report and confirmed by the Department of Energy`s (DOE`s) Energy Research Advisory Board in 1985. These studies defined a minimum thermal neutron flux requirement of 5 {times} 10{sup 19} m{sup {minus}2} {center_dot} s{sup {minus}1}. The National Steering Committee for an Advanced Neutron Source, with representation from the major fields of science that will use the facility, was established in 1986 and has continued to define the performance requirements and instrument layouts needed by the user community. To minimize technical risks and safety issues, the project adopted a policy of not relying upon new inventions to meet the minimum performance criteria, and the design presented in this report is built on technologies already used in other facilities and development programs: for example, the involute aluminum-clad fuel plates common to HFIR and ILL and the uranium silicide fuel developed in DOE`s Reduced Enrichment for Research and Test Reactors program and tested in reactors worldwide. At the same time, every state-of-the-art technique has been implemented to optimize neutron beam delivery at the experiments.

Peretz, F.J.

1992-09-01T23:59:59.000Z

419

Home Energy Score Pilot Summaries | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Home Energy Score Pilot Summaries Home Energy Score Pilot Summaries Home Energy Score Pilot Summaries The U.S. Department of Energy (DOE) partnered with counties, utilities, and non-profit organizations ("Pilots") across the country to test and evaluate the Home Energy Score from November 2010 through July 2011. Through these Pilots, DOE tested a wide range of issues associated with the program and the associated software, the Home Energy Scoring Tool, including: How homeowners responded to the Home Energy Score and process Training of the home energy assessors and reaction to the Scoring Tool Methods to conduct Quality Assurance Climatic sensitivity of the Home Energy Scoring Tool The Pilots were spread out across varied climates, represented most U.S. regions, and included both urban and rural communities. DOE and the Pilots

420

00394_SummaryRpt_Apr2001_May2003.doc  

NLE Websites -- All DOE Office Websites (Extended Search)

Summary Report Summary Report Hydrate Drill: development, testing, monitoring April 2001 through May 2003 Submitted by Ian R. MacDonald Dept. of Physical and Life Sciences ST320 Texas A&M University - Corpus Christi Corpus Christi, TX 78412 316-825-2234 imacdonald@falcon.tamucc.edu Overview: This is a summary report documenting effort and accomplishment on two related awards from NETL to Texas A&M University - I.R. MacDonald, principal investigator. The awards were tasked with advancing the technical capabilities for sampling and monitoring shallow deposits of gas hydrates. Major thrust areas have been development, fabrication, and testing of a unique hydrate drill system for recovering intact samples of gas hydrate and time-series monitoring of the sampling sites to quantify in-situ physical

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


421

Emergency Procedures | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Services Employee Services Safety and Health Emergency Procedures Emergency Procedures Note: This page is pending deletion, please refer to the Safety and health main page...

422

Physics and Cancer Project Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

Project Summary Project Summary HELP Index Summary Scenario Reference Student Pages Subject/Content Area: Physics and/or Integrated Biology, Chemistry and Physics Target Audience: This project primarily targets grades 9-12. The relevant curricular guidelines include electrical forces and interactions, the spectrum and energy of electromagnetic radiation, a basic understanding of the Standard Model, conservation of mass/energy, effects of radiation on living cells, etc. Students will primarily be physics students or integrated lab science students who are involved in an analysis of an open-ended study of the application of physics to radiation therapy. Skills that are required include a basic background in the language of science and the ability to perform independent research (including searching with the Internet),

423

DOE-ID Operations Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

26, 2013 26, 2013 DOE-ID Operations Summary For the Period July 29, 2013 through August 12, 2013 EDITOR'S NOTE: The following is a summary of contractor operations at the Idaho National Laboratory, managed by DOE- Idaho Operations Office. It has been compiled in response to a request from stakeholders for more information on health, safety and environmental incidents at DOE facilities in Idaho. It also includes a brief summary of accomplishments at the Site. POC -Danielle Miller, (208) 526-5709. Advanced Mixed Waste Treatment Project (AMWTP) July 31, 2013: The Idaho Treatment Group, LLC (ITG), the managing contractor for the Advanced Mixed Waste Treatment Project received a warning letter from the State of Idaho's Department of Environmental quality regarding self- reported RCRA permit violations which

424

DOE-ID Operations Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

June 5, 2013 June 5, 2013 DOE-ID Operations Summary For the Period May 16, through May 30, 2013 EDITOR'S NOTE: The following is a summary of contractor operations at the Idaho National Laboratory, managed by DOE- Idaho Operations Office. It has been compiled in response to a request from stakeholders for more information on health, safety and environmental incidents at DOE facilities in Idaho. It also includes a brief summary of accomplishments at the Site. POC - Shannon Brennan, DOE-ID, (208) 526-3993. Advanced Mixed Waste Treatment Project (AMWTP) [No items to Report] Idaho Cleanup Project (ICP) May 15 - 30, 2013: CH2M-WG Idaho, LLC discovered three instances of new information at the Integrated Waste Treatment Unit (IWTU) which have the potential to impact the nuclear safety analysis

425

Summary | Building Energy Codes Program  

NLE Websites -- All DOE Office Websites (Extended Search)

Summary Summary The impact of energy codes on our future is apparent. From environmental and resource conservation to national security, energy concerns, and our economic challenges, energy codes will continue to be a key component of a sound public policy. For further information on building energy code adoption, compliance, and enforcement, review the ACE toolkits Adoption Compliance Enforcement Popular Links ACE Learning Series ACE Overview Top 10 Reasons for Energy Codes Development of Energy Codes Adoption of Energy Codes Compliance with Energy Codes Enforcement of Energy Codes Going Beyond Code Summary Acronyms and Abbreviations Toolkit Definitions Adoption Toolkit Compliance Toolkit Enforcement Toolkit Contacts Web Site Policies U.S. Department of Energy USA.gov Last Updated: Thursday, January 31, 2013 - 15:19

426

DOE-ID Operations Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

January 6, 2014 January 6, 2014 DOE-ID Operations Summary For the Period November 01, 2013 through November 30, 2013 EDITOR'S NOTE: The following is a summary of contractor operations at the Idaho National Laboratory, managed by DOE- Idaho Operations Office. It has been compiled in response to a request from stakeholders for more information on health, safety and environmental incidents at DOE facilities in Idaho. It also includes a brief summary of accomplishments at the Site. POC -Danielle Miller, (208) 526-5709. Advanced Mixed Waste Treatment Project (AMWTP) Nothing to Report Notable Accomplishments: Contracting companies supporting EM's cleanup program and the Office of Nuclear Energy at the Idaho site volunteered to be among the first to use a new DOE

427

EIA - AEO2010 - Executive Summary  

Gasoline and Diesel Fuel Update (EIA)

Executive Summary Executive Summary Annual Energy Outlook 2010 with Projections to 2035 Executive Summary In 2009, U.S. energy markets continued to show the impacts of the economic downturn that began in late 2007. After falling by 1 percent in 2008, total electricity generation dropped by another 3 percent in 2009. Although other factors, including weather, contributed to the decrease, it was the first time in the 60-year data series maintained by the EIA that electricity use fell in two consecutive years. Over the next few years, the key factors influencing U.S. energy markets will be the pace of the economic recovery, any lasting impacts on capital-intensive energy projects from the turmoil in financial markets, and the potential enactment of legislation related to energy and the environment.

428

Wind energy systems: program summary  

Science Conference Proceedings (OSTI)

The Federal Wind Energy Program (FWEP) was initiated to provide focus, direction and funds for the development of wind power. Each year a summary is prepared to provide the American public with an overview of government sponsored activities in the FWEP. This program summary describes each of the Department of Energy's (DOE) current wind energy projects initiated or renewed during FY 1979 (October 1, 1978 through September 30, 1979) and reflects their status as of April 30, 1980. The summary highlights on-going research, development and demonstration efforts and serves as a record of progress towards the program objectives. It also provides: the program's general management structure; review of last year's achievements; forecast of expected future trends; documentation of the projects conducted during FY 1979; and list of key wind energy publications.

None

1980-05-01T23:59:59.000Z

429

DOE-ID Operations Summary  

NLE Websites -- All DOE Office Websites (Extended Search)

18, 2013 18, 2013 DOE-ID Operations Summary For the Period September 30, 2013 through October 31, 2013 EDITOR'S NOTE: The following is a summary of contractor operations at the Idaho National Laboratory, managed by DOE- Idaho Operations Office. It has been compiled in response to a request from stakeholders for more information on health, safety and environmental incidents at DOE facilities in Idaho. It also includes a brief summary of accomplishments at the Site. POC -Danielle Miller, (208) 526-5709. Advanced Mixed Waste Treatment Project (AMWTP) October 15, 2013: A manager at the Advanced Mixed Waste Treatment Project (AMWTP) determined that the AMWTP Safety Analysis process required review due to an operational trend of fire/combustion events in the Treatment Facility (TF) box lines. Safety analysis for the TF is

430

Vitrification Facility integrated system performance testing report  

Science Conference Proceedings (OSTI)

This report provides a summary of component and system performance testing associated with the Vitrification Facility (VF) following construction turnover. The VF at the West Valley Demonstration Project (WVDP) was designed to convert stored radioactive waste into a stable glass form for eventual disposal in a federal repository. Following an initial Functional and Checkout Testing of Systems (FACTS) Program and subsequent conversion of test stand equipment into the final VF, a testing program was executed to demonstrate successful performance of the components, subsystems, and systems that make up the vitrification process. Systems were started up and brought on line as construction was completed, until integrated system operation could be demonstrated to produce borosilicate glass using nonradioactive waste simulant. Integrated system testing and operation culminated with a successful Operational Readiness Review (ORR) and Department of Energy (DOE) approval to initiate vitrification of high-level waste (HLW) on June 19, 1996. Performance and integrated operational test runs conducted during the test program provided a means for critical examination, observation, and evaluation of the vitrification system. Test data taken for each Test Instruction Procedure (TIP) was used to evaluate component performance against system design and acceptance criteria, while test observations were used to correct, modify, or improve system operation. This process was critical in establishing operating conditions for the entire vitrification process.

Elliott, D.

1997-05-01T23:59:59.000Z

431

NEV PROCEDURE PUNCH LIST  

NLE Websites -- All DOE Office Websites (Extended Search)

END OF LIFE TEST SEQUENCE Revision 0 September 1, 2006 Prepared by Electric Transportation Applications Prepared by: Date: Roberta Brayer...

432

NEV PROCEDURE PUNCH LIST  

NLE Websites -- All DOE Office Websites (Extended Search)

BASELINE TEST SEQUENCE Revision 1 September 1, 2006 Prepared by Electric Transportation Applications Prepared by: Date: Roberta Brayer...

433

NEV PROCEDURE PUNCH LIST  

NLE Websites -- All DOE Office Websites (Extended Search)

NEVAmerica TEST SEQUENCE Revision 2 Effective February 1, 2008 Prepared by Electric Transportation Applications Prepared by: Date: Nick...

434

Iowa_2012_summary  

NLE Websites -- All DOE Office Websites (Extended Search)

U U niversity o f I owa Q uarknet 2 012 The summer of 2012 found 5 students and 3 teachers involved in many activities related to the high energy particle physics group at The University of Iowa. Some of the things the teachers and students did over the summer: * Performed tests on equipment * Prepared specimens for beam exposure * Put on a weeklong institute for 19 high school teachers Teacher I nstitute All of these activities were focused on the performance and success of Compact Muon Solenoid (CMS) at CERN's Large Hadron Collider (LHC). The Iowa group also ran a week-long outreach program to 16 other teachers from all over the state of Iowa. During this institute, the teachers became updated on the latest high-energy efforts and how it impacts cosmology. Each participant

435

Summary.qxd  

NLE Websites -- All DOE Office Websites (Extended Search)

3 3 DOE/EIS-0287 Idaho HLW & FD EIS cussed below. Options excluded from DOE's Preferred Alternative are, storage of calcine in the bin sets for an indefinite period under the Continued Current Operations Alternative, the shipment of calcine to the Hanford Site for treatment under the Minimum INEEL Processing Alternative, and disposal of mixed low-level waste on the INEEL under any alter- native. The selection of any one of, or combi- nation of, technologies or options used to implement the proposed action would be based on performance criteria that include risk, cost, time, and compliance factors. The selection may also be based on the results of laboratory and demonstration scale evaluations and com- parisons using actual wastes in proof of process tests.

436

Summary of Prioritized Research Opportunities  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Summary of Prioritized Summary of Prioritized Research Opportunities Building America Program Planning Meeting Washington, D.C. - November 2-4, 2010 February 2011 NOTICE This report was prepared as an account of work sponsored by an agency of the United States government. Neither the United States government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name,

437

Experimental Plasma Research project summaries  

SciTech Connect

This report contains descriptions of the activities supported by the Experimental Plasma Research Branch of APP. The individual project summaries were prepared by the principal investigators and include objectives and milestones for each project. The projects are arranged in six research categories: Plasma Properties; Plasma Heating; Plasma Diagnostics; Atomic, Molecular and Nuclear Physics; Advanced Superconducting Materials; and the Fusion Plasma Research Facility (FPRF). Each category is introduced with a statement of objectives and recent progress and followed by descriptions of individual projects. An overall budget summary is provided at the beginning of the report.

1980-09-01T23:59:59.000Z

438

Experimental plasma research project summaries  

SciTech Connect

This report contans descriptions of the activities supported by the Experimental Plasma Research Branch of APP. The individual project summaries were prepared by the principal investigators and include objectives and milestones for each project. The projects are arranged in six research categories: Plasma Properties; Plasma Heating; Plasma Measurements and Instrumentation; Atomic, Molecular and Nuclear Physics; Advanced Superconducting Materials; and the Fusion Plasma Research Facility (FPRF). Each category is introduced with a statement of objectives and recent progress and followed by descriptions of individual projects. An overall budget summary is provided at the beginning of the report.

1978-08-01T23:59:59.000Z

439

TRANSPARENCY RECYCLING PROGRAM PROCEDURES  

NLE Websites -- All DOE Office Websites (Extended Search)

TRANSPARENCY RECYCLING Don't throw out your used overhead transparencies! RECYCLE them for REUSE. It's Easy! Follow these simple procedures: 1.) COLLECT used transparencies to be recycled. 2.) SEPARATE the transparencies from ringed binders, plastic or paper folders, envelopes, and/or files. 3.) PLACE the transparencies (only) into an intra-laboratory mail envelope. 4.) SEND the envelope to: Terri Schneider, Building 201, 1D-10. Terri will prepare a

440

DOE Reasonable Accommodation Procedures  

Energy.gov (U.S. Department of Energy (DOE))

Pursuant to Executive Order 13164, the Department of Energy (hereinafter referred to as the department), is charged with establishing written procedures for the facilitation of reasonable accommodation for: (1) individuals with disabilities in the application process for employment with the Department; (2) Department employees with disabilities to perform the essential functions of a position; and (3) Department employees with disabilities to enjoy benefits and privileges of employment equal to those enjoyed by employees without disabilities.

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


441

Photon-photon interactions. [Brief summary of present status  

Science Conference Proceedings (OSTI)

A brief summary of the present status of photon-photon interactions is presented. Stress is placed on the use of two-photon collisions to test present ideas on the quark constituents of hadrons and on the theory of strong interactions.

Gilman, F.J.

1980-01-01T23:59:59.000Z

442

CMS System Security Plan Procedure  

Science Conference Proceedings (OSTI)

... TASK 5: SYSTEM DECOMMISSION. ... BPSSM Business Partners Systems Security Manual. ... of Information Technology, Policy, Procedures, & Audits. ...

2009-06-30T23:59:59.000Z

443

Microsoft PowerPoint - AVTALeaftestinganalysis_Major summary092112.pptx  

NLE Websites -- All DOE Office Websites (Extended Search)

AVTA Nissan Leaf testing and analysis October 12 th 2012 Henning Lohse-Busch, PhD Mike Duoba, Eric Rask, Mark Meyer, APRF & Co., Argonne National Laboratory Sponsored by Lee Slezak Note: This presentation summarizes the major finding which have been presented at several different occasions in the past. Overview  Vehicle information  Instrumentation and test plan  General test results - SAE J1634 Short cut test method - Energy Consumption and range - Two Leafs, two different results - Battery performance, depletion and charging - Accessory load summary  Thermal testing - 72F results - 20F results - 95F with solar load results  Conclusions 2 Advanced Powertrain Research Facility Nissan Leaf -

444

Comparisons of field performance to closed-door test T ABLE 1 ratings indicate the laboratory procedure is a valid indica-Design Options to Improve the Energy Efficiency of a  

E-Print Network (OSTI)

#12;#12;Comparisons of field performance to closed-door test T ABLE 1 ratings indicate commercially manufactured refrigerators were u~ as laboratory test beds, a testing sequence of ..as PHASE I cabinets with an optimized Option 2 Evaporator/condenser size, surface r~frige~tion circuit or cvcle were

Oak Ridge National Laboratory

445

Hot Dry Rock - Summary  

SciTech Connect

Hot Dry Rock adds a new flexibility to the utilization of geothermal energy. Almost always the approach has been to limit that utilization to places where there is a natural source of water associated with a source of heat. Actually, the result was that steam was mined. Clearly there are much larger heat resources available which lack natural water to transport that energy to the surface. Also, as is found in hydrothermal fields being mined for steam, the water supply finally gets used up. There is a strong motive in the existing capital investment to revitalize those resources. Techniques for introducing, recovering and utilizing the water necessary to recover the heat from below the surface of the earth is the subject of this session. Implicit in that utilization is the ability to forecast with reasonable accuracy the busbar cost of that energy to the utility industry. The added element of supplying the water introduces costs which must be recovered while still supplying energy which is competitive. Hot Dry Rock technology can supply energy. That has been proved long since. The basic barrier to its use by the utility industry has been and remains proof to the financial interests that the long term cost is competitive enough to warrant investment in a technology that is new to utility on-grid operations. As the opening speaker for this session states, the test that is underway will ''simulate the operations of a commercial facility in some ways, but it will not show that energy from HDR can be produced at a variety of locations with different geological settings''. Further, the Fenton Hill system is a research facility not designed for commercial production purposes, but it can give indications of how the system must be changed to provide economic HDR operations. And so it is that we must look beyond the long term flow test, at the opportunities and challenges. Proving that the huge HDR resources can be accessed on a worldwide scale must involve the construction of additional sites, preferably to the specifications of the now Federal geothermal community. These facilities will have to be engineered to produce and market energy at competitive prices. At the same time, we must not rest on our technological laurels, though they be many. Design and operational techniques have been conceived which could lead to improved economics and operations for HDR. These must be pursued and where merit is found, vigorously pursued. Accelerated research and development ought to include revolutionary drilling techniques, reservoir interrogation, and system modeling to assure the competitiveness and geographical diversity of applications of HDR. Much of this work will be applicable to the geothermal industry in general. More advanced research ought to include such innovations as the utilization of other operating fluids. Supercritical carbon dioxide and the ammonia/water (Kalina) cycle have been mentioned. But even as the near and more distant outlook is examined, today's work was reported in the HDR session. The start-up operations for the current test series at the Fenton Hill HDR Pilot Plant were described. The surface plant is complete and initial operations have begun. While some minor modifications to the system have been required, nothing of consequence has been found to impede operations. Reliability, together with the flexibility and control required for a research system were shown in the system design, and demonstrated by the preliminary results of the plant operations and equipment performance. Fundamental to the overall success of the HDR energy resource utilization is the ability to optimize the pressure/flow impedance/time relationships as the reservoir is worked. Significant new insights are still being developed out of the data which will substantially affect the operational techniques applied to new systems. However, again, these will have to be proved to be general and not solely specific to the Fenton Hill site. Nevertheless, high efficiency use of the reservoir without unintended reservoir grow

Tennyson, George P. Jr.

1992-03-24T23:59:59.000Z

446

Summary of the HANFORD SITE  

E-Print Network (OSTI)

milestones completed in 2003 were related to work on Hanford waste storage tanks. During 2003, there were 36Summary of the HANFORD SITE Environmental Report for Calendar Year 2003 EDITORS R.W. HANF L Northwest National Laboratory under contract DE-AC06-76RL01830, with contributions from Bechtel Hanford, Inc

447

A Summary Report Minneapolis, Minnesota  

E-Print Network (OSTI)

Metropolitan Council Transportation Club of Minneapolis and St. Paul The Future is Front and CenterA Summary Report Minneapolis, Minnesota In cooperation with: Minnesota Department ofTransportation: The Impacts of Economic Change on Freight Transportation Sponsored by: Center forTransportation Studies 15th

Minnesota, University of

448

CCPExecutiveSummary Storing Wind  

E-Print Network (OSTI)

CCPExecutiveSummary July 2011 Storing Wind for a Rainy Day W: www.uea.ac.uk/ccp T: +44 (0)1603 593715 A: UEA, Norwich, NR4 7TJ Storing Wind for a Rainy Day: What kind of electricity does Denmark export? BACKGROUND The last decade has seen a remarkable increase in the number of wind installations

Feigon, Brooke

449

Characterization Summary Report for the  

E-Print Network (OSTI)

(LLNL) are submitting this Characterization Summary Report for the Building 865 study area at LLNL Site 300. This letter report summarizes the results of environmental investigations performed in the Building 865 study area to determine if contamination has been released to the environment as a result of past activities. The results of this remedial investigation are organized

Ms. Kathy Setian; Mr. Jacinto Soto; Ms. Susan Timm

2006-01-01T23:59:59.000Z

450

Separations innovative concepts: Project summary  

Science Conference Proceedings (OSTI)

This project summary includes the results of 10 innovations that were funded under the US Department's Innovative Concept Programs. The concepts address innovations that can substantially reduce the energy used in industrial separations. Each paper describes the proposed concept, and discusses the concept's potential energy savings, market applications, technical feasibility, prior work and state of the art, and future development needs.

Lee, V.E. (ed.)

1988-05-01T23:59:59.000Z

451

Biomass energy systems program summary  

DOE Green Energy (OSTI)

Research programs in biomass which were funded by the US DOE during fiscal year 1978 are listed in this program summary. The conversion technologies and their applications have been grouped into program elements according to the time frame in which they are expected to enter the commercial market. (DMC)

None

1980-07-01T23:59:59.000Z

452

Experimental Plasma Research. Project summaries  

SciTech Connect

This is the fifth in a series of Project Summary books going back to 1976. They are issued approximately every two years and provide a short description of each project supported by the Experimental Plasma Research Branch of the Division of Applied Plasma Physics in the Office of Fusion Energy (OFE).

1984-12-01T23:59:59.000Z

453

Demand Forecast INTRODUCTION AND SUMMARY  

E-Print Network (OSTI)

Demand Forecast INTRODUCTION AND SUMMARY A 20-year forecast of electricity demand is a required of any forecast of electricity demand and developing ways to reduce the risk of planning errors that could arise from this and other uncertainties in the planning process. Electricity demand is forecast

454

WASC PREPARATORY REVIEW EXECUTIVE SUMMARY  

E-Print Network (OSTI)

in its culture of diversity, creativity and discovery. In the final essay, we indicate how sharedWASC PREPARATORY REVIEW EXECUTIVE SUMMARY Fiat Lux University of California motto he four essays, administrators, and alumni to determine the topics to be covered in the essays and to review the many drafts

California at Santa Cruz, University of

455

Moriond Electroweak 2006: Theory summary  

SciTech Connect

A concise look at the big picture of particle physics, including the status of the Standard Model, neutrinos, supersymmetry, extra dimensions and cosmology. Based upon the theoretical summary presented at the XLIst Rencontres de Moriond on Electroweak Interactions and Unified Theories, La Thuile, 11-18 March 2006.

Lykken, Joseph D.; /Fermilab

2006-07-01T23:59:59.000Z

456

LARGE SCALE PERMEABILITY TEST OF THE GRANITE IN THE STRIPA MINE AND THERMAL CONDUCTIVITY TEST  

E-Print Network (OSTI)

No.2 LARGE SCALE PERMEABILITY TEST OF THE GRANITE' IN THEMINE AND, THERMAL CONDUCTIVITY TEST Lars Lundstrom and HakanSUMMARY REPORT Background TEST SITE Layout of test places

Lundstrom, L.

2011-01-01T23:59:59.000Z

457

Summary Protocol: Identification, Characterization, Designation, Remedial  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Summary Protocol: Identification, Characterization, Designation, Summary Protocol: Identification, Characterization, Designation, Remedial Action, Certification Summary Protocol: Identification, Characterization, Designation, Remedial Action, Certification Summary Protocol: Identification, Characterization, Designation, Remedial Action, Certification (January 1986) Summary Protocol: Identification, Characterization, Designation, Remedial Action, Certification (January 1986) More Documents & Publications Supplement No. 1 to the FUSRAP Summary Protocol - Designation/Elimination Protocol Pre-MARSSIM Surveys in a MARSSIM World: Demonstrating How Pre-MARSSIM Radiological Data Demonstrate Protectiveness at Formerly Utilized Sites Remedial Action Program Sites U.S. Department of Energy Guidelines for Residual Radioactive Material at

458

Annual Planning Summaries: 2011 | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Annual Planning Summaries: 2011 Annual Planning Summaries: 2011 Annual Planning Summaries: 2011 January 20, 2011 2011 Annual Planning Summary for Chicago Operations Office (CH) The ongoing and projected Environmental Assessments and Environmental Impact Statements for 2011 and 2012 within the Chicago Operations Office (CH) (See Science APS). January 20, 2011 2011 Annual Planning Summary for Nevada Site Office (NSO) The ongoing and projected Environmental Assessments and Environmental Impact Statements for 2011 and 2012 within the Nevada Site Office (NSO). January 19, 2011 2011 Annual Planning Summary for Southeastern Power Administration (SEPA) The ongoing and projected Environmental Assessments and Environmental Impact Statements for 2011 and 2012 within the Southeastern Power Administration (SEPA).

459

Staff summary of Issues & Recommendations Renewable Energy  

E-Print Network (OSTI)

1 Staff summary of Issues & Recommendations Renewable Energy *Preliminary draft, please refer fish and wildlife impacts associated with renewable energy development. The Council also received invasive plants as biofeedstocks. I. Summary A. Consider the effects of renewable energy development

460

2.1E BDL Summary  

E-Print Network (OSTI)

SCHEDULE BLOCK-CHARGE UTILITY-RATE RATCHET COMPONENT-COSTjaccepts u-name of another UTILITY-RATE) BILLING-DAYS(B-D)(SUMMARY ES-E SUMMARY OF UTILITY-RATE: U-NAME ES-F BLOCK-

Winkelmann, F.C.

2010-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


461

Operating Experience Summary 2003-17  

NLE Websites -- All DOE Office Websites (Extended Search)

OPERATING EXPERIENCE SUMMARY U.S. Department of Energy Office of Environment, Safety and Health OE Summary 2003-17 August 25, 2003 * Underrated and unmaintained hoist used to lift...

462

Disposal Practices at the Nevada Test Site 2008 | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Disposal Practices at the Nevada Test Site 2008 Disposal Practices at the Nevada Test Site 2008 Full Document and Summary Versions are available for download Disposal Practices at...

463

Trona Injection Tests: Mirant Potomac River Station, Unit 1,...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Trona Injection Tests: Mirant Potomac River Station, Unit 1, November 12 to December 23, 2005, Summary Report Trona Injection Tests: Mirant Potomac River Station, Unit 1, November...

464

EA-1097: Solid waste Disposal - Nevada Test Site, Nye County...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

7: Solid waste Disposal - Nevada Test Site, Nye County, Nevada EA-1097: Solid waste Disposal - Nevada Test Site, Nye County, Nevada SUMMARY This EA evaluates the environmental...

465

2012 Ford Fusion V6 Test Cell Location  

NLE Websites -- All DOE Office Websites (Extended Search)

Fusion V6 Test Cell Location 2WD Vehicle Setup Information Downloadable Dynamometer Database (D 3 )- Test Summary Sheet Vehicle Architecture Conventional Vehicle Dynamometer Input...

466

SANS Training Voucher Program Registration Procedures | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

SANS Training Voucher Program Registration Procedures SANS Training Voucher Program Registration Procedures SANS Training Voucher Program Registration Procedures For Federal...

467

2012 Annual Planning Summary for Science | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

within Science. More Documents & Publications 2011 Annual Planning Summary for Science (SC) 2012 Annual Planning Summary for Environmental Management 2012 Annual Planning Summary...

468

2010 Annual Planning Summary for National Energy Technology Laboratory...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Annual Planning Summary for National Nuclear Security Administration Service Center (NNSA-SC) 2010 Annual Planning Summary for Oak Ridge (OR) 2010 Annual Planning Summary for Idaho...

469

2013 Annual Planning Summary for the Savannah River Operations...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

3 Annual Planning Summary for the Savannah River Operations Office 2013 Annual Planning Summary for the Savannah River Operations Office 2013 Annual Planning Summary for the...

470

2013 Annual Planning Summary for the Savannah River Operations...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

2013 Annual Planning Summary for the Savannah River Operations Office 2013 Annual Planning Summary for the Savannah River Operations Office 2013 Annual Planning Summary for the...

471

2013 Annual Planning Summary for the Idaho Operations Office...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

3 Annual Planning Summary for the Idaho Operations Office 2013 Annual Planning Summary for the Idaho Operations Office 2013 Annual Planning Summary for the Idaho Operations Office...

472

2013 Annual Planning Summary for the Portsmouth and Paducah Project...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

2013 Annual Planning Summary for the Portsmouth and Paducah Project Office 2013 Annual Planning Summary for the Portsmouth and Paducah Project Office 2013 Annual Planning Summary...

473

2013 Annual Planning Summary for the Southwestern Area Power...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

2013 Annual Planning Summary for the Southwestern Area Power Administration 2013 Annual Planning Summary for the Southwestern Area Power Administration 2013 Annual Planning Summary...

474

2013 Annual Planning Summary for the Nevada Site Office | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

3 Annual Planning Summary for the Nevada Site Office 2013 Annual Planning Summary for the Nevada Site Office 2013 Annual Planning Summary for the The ongoing and projected...

475

Hanford Site C Tank Farm Meeting Summary - May 2011 | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

May 2011 Hanford Site C Tank Farm Meeting Summary - May 2011 Hanford Site C Tank Farm Meeting Summary More Documents & Publications Hanford Site C Tank Farm Meeting Summary -...

476

Hanford Site C Tank Farm Meeting Summary - March 2010 | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

March 2010 Hanford Site C Tank Farm Meeting Summary - March 2010 Meeting Summary for Development of the Hanford Site C Tank Farm Performance Assessment Meeting Summary for...

477

Workshop on polarized targets and materials. Summary  

DOE Green Energy (OSTI)

Summaries are given of presentations of developments in: irradiated ammonia; polarized atomic hydrogen; polarized target technology; and chemical doping. (GHT)

Hill, D.

1982-01-01T23:59:59.000Z

478

Summary of the Heavy Flavours Working Group  

E-Print Network (OSTI)

This is a summary of the contributions presented in the Heavy Flavours Working Group of the DIS2006 Workshop.

U. Karshon; I. Schienbein; P. Thompson

2006-08-10T23:59:59.000Z

479

Summary of Linear Elastic Fracture Mechanics Concepts  

Science Conference Proceedings (OSTI)

...in this Volume."Stress Intensity Factors"A brief summary of linear elastic fracture mechanics (LEFM) concepts

480

CNEA Fresh Fuel Plate Characterization Summary Report  

SciTech Connect

Characterization summary report outlining the findings of the fresh fuel examinations of the plates received from CNEA.

D. Keiser; F. Rice

2012-02-01T23:59:59.000Z

Note: This page contains sample records for the topic "test procedure summary" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


481

NIST Appropriations Summary FY 2012 - FY 2014  

Science Conference Proceedings (OSTI)

*. Bookmark and Share. National Institute of Standards and Technology Appropriations Summary. FY 2012 - FY 2014 (Dollars in Table in Millions). ...

2013-04-26T23:59:59.000Z

482

FY 2008 Summary Federal Tech Transfer  

Science Conference Proceedings (OSTI)

Summary Report on Federal Laboratory Technology Transfer FY2008. For Immediate Release: April 30, 2010. Contact: Cathleen ...

2013-06-26T23:59:59.000Z

483

NEHRP - Summary Overview of the Research and ...  

Science Conference Proceedings (OSTI)

Library. Summary Overview of the Research and Development (R&D) Roadmap. The National Earthquake Hazards Reduction ...

484

BOP Pressure Summary 28 May 2010  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Pressures (psi) +/- 50 psi" Pressures (psi) +/- 50 psi" ,,,,,,,"Pre Kill","Post Kill","Post Junk","Post Junk shot 2" ,,,,,,,2250,2250,2250,2250 ,,,,,,"Delta",310,250,229 ,,,,,,,2560,2500,2479 ,,,,,,"Delta",60,120,108,493 ,,,,,,,2620,2620,2587,2743 ,,,,,,"Delta",620,510,794,410 ,,,,,,,3240,3130,3381,3153 ,,,,,,"Delta",430,150,284,242 ,,26.51,,,,,3670,3280,3665,3395 ,,,,,,"Delta",730,40,32,101 ,,,,,,"BOP Pres",4400,3320,3697,3496 ,,,,,,"(corrected)","(Test Ram closed)","(Test Ram open)","(