Powered by Deep Web Technologies
Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


1

LPP Risk Management Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

History and Process History and Process Slide 2 M E Environmental Management Environmental Management History ◦ Current Baseline Process Overview ◦ Identification ◦ Simulation ◦ Management Successes & Challenges Slide 3 M E Environmental Management Environmental Management Current Baseline Risks ◦ 1 Week Risk Summit held week of August 4 th , 2008 Broad representation from all levels of Isotek, DOE, PTC, and outside consultants Focused on risk and opportunity identification Included risk description, assumptions, and triggers No quantification or analysis No restrictions, constraints, or filtering HQ provided facilitator Prescribed format and capture methodology Slide 4 M E Environmental Management Environmental Management Current Baseline RisksRisk Summit Results

2

LPP Risk Management Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Plan More Documents & Publications Software Development Risk Assessment High Risk Plan SC Introduction to Risk Management Energy.gov Careers & Internships For Staff &...

3

Risk Management Plan Electron Beam Ion Source Project  

E-Print Network (OSTI)

. The estimated costs and contingencies to mitigate these risks are incorporated in the Project baseline costRisk Management Plan for the Electron Beam Ion Source Project (EBIS) Project # 06-SC-002 of Nuclear Physics (SC ­ 26) #12;1. Background and References 1.1 Background The EBIS Project will manage

Homes, Christopher C.

4

Integrated Waste Treatment Unit GFSI Risk Management Plan  

SciTech Connect

This GFSI Risk Management Plan (RMP) describes the strategy for assessing and managing project risks for the Integrated Waste Treatment Unit (IWTU) that are specifically within the control and purview of the U.S. Department of Energy (DOE), and identifies the risks that formed the basis for the DOE contingency included in the performance baseline. DOE-held contingency is required to cover cost and schedule impacts of DOE activities. Prior to approval of the performance baseline (Critical Decision-2) project cost contingency was evaluated during a joint meeting of the Contractor Management Team and the Integrated Project Team for both contractor and DOE risks to schedule and cost. At that time, the contractor cost and schedule risk value was $41.3M and the DOE cost and schedule risk contingency value is $39.0M. The contractor cost and schedule risk value of $41.3M was retained in the performance baseline as the contractor's management reserve for risk contingency. The DOE cost and schedule risk value of $39.0M has been retained in the performance baseline as the DOE Contingency. The performance baseline for the project was approved in December 2006 (Garman 2006). The project will continue to manage to the performance baseline and change control thresholds identified in PLN-1963, ''Idaho Cleanup Project Sodium-Bearing Waste Treatment Project Execution Plan'' (PEP).

W. A. Owca

2007-06-21T23:59:59.000Z

5

Integrated Waste Treatment Unit GFSI Risk Management Plan  

SciTech Connect

This GFSI Risk Management Plan (RMP) describes the strategy for assessing and managing project risks for the Integrated Waste Treatment Unit (IWTU) that are specifically within the control and purview of the U.S. Department of Energy (DOE), and identifies the risks that formed the basis for the DOE contingency included in the performance baseline. DOE-held contingency is required to cover cost and schedule impacts of DOE activities. Prior to approval of the performance baseline (Critical Decision-2) project cost contingency was evaluated during a joint meeting of the Contractor Management Team and the Integrated Project Team for both contractor and DOE risks to schedule and cost. At that time, the contractor cost and schedule risk value was $41.3M and the DOE cost and schedule risk contingency value is $39.0M. The contractor cost and schedule risk value of $41.3M was retained in the performance baseline as the contractor's management reserve for risk contingency. The DOE cost and schedule risk value of $39.0M has been retained in the performance baseline as the DOE Contingency. The performance baseline for the project was approved in December 2006 (Garman 2006). The project will continue to manage to the performance baseline and change control thresholds identified in PLN-1963, ''Idaho Cleanup Project Sodium-Bearing Waste Treatment Project Execution Plan'' (PEP).

W. A. Owca

2007-06-21T23:59:59.000Z

6

Managing Carbon Regulatory Risk in Utility Resource Planning: Current  

NLE Websites -- All DOE Office Websites (Extended Search)

Managing Carbon Regulatory Risk in Utility Resource Planning: Current Managing Carbon Regulatory Risk in Utility Resource Planning: Current Practices in the Western United States Title Managing Carbon Regulatory Risk in Utility Resource Planning: Current Practices in the Western United States Publication Type Report Year of Publication 2009 Authors Barbose, Galen L., Ryan H. Wiser, Amol Phadke, and Charles A. Goldman Pagination 28 Date Published 03/2009 Publisher LBNL City Berkeley Keywords carbon emissions, electric utilities, electricity markets and policy group, energy analysis and environmental impacts department, power system planning Abstract Concerns about global climate change have substantially increased the likelihood that future policy will seek to minimize carbon dioxide emissions. As such, even today, electric utilities are making resource planning and investment decisions that consider the possible implications of these future carbon regulations. In this article, we examine the manner in which utilities assess the financial risks associated with future carbon regulations within their long-term resource plans. We base our analysis on a review of the most recent resource plans filed by fifteen electric utilities in the Western United States. Virtually all of these utilities made some effort to quantitatively evaluate the potential cost of future carbon regulations when analyzing alternate supply- and demandside resource options for meeting customer load. Even without Federal climate regulation in the U.S., the prospect of that regulation is already having an impact on utility decision-making and resource choices. That said, the methods and assumptions used by utilities to analyze carbon regulatory risk, and the impact of that analysis on their choice of a particular resource strategy, vary considerably, revealing a number of opportunities for analytic improvement. Though our review focuses on a subset of U.S. electric utilities, this work holds implications for all electric utilities and energy policymakers

7

Operations Risk Management by Planning Optimally the Qualified ...  

E-Print Network (OSTI)

In a real context of enterprise risk management, many decisions must be ...... G. Sullivan, Risk Management-Safeguarding Company Assets, Thomson, 2007.

8

Risk Management Plan for Tank Farm Restoration and Safe Operations Project W-314  

SciTech Connect

The Risk Management Plan for Project W-314 describes the systems, processes and procedures for implementation of applicable risk management practices described in HNF-0842, Volume IV, Section 2.6, ''Risk Management''. This plan is tailored specifically for use by Project W-314.

MCGREW, D.L.

2000-04-19T23:59:59.000Z

9

Life Cycle Management Economic Tools Demonstration: Risk-Informed Long-Term Planning for Equipment  

Science Conference Proceedings (OSTI)

To date, the EPRI Life Cycle Management (LCM) process and economic evaluation software tools have used point-value deterministic calculations to identify the economically optimum long-term plan for a system, structure, or component (SSC). This collaborative project demonstrates the unique capabilities of four tools that use probabilistic techniques to risk-inform LCM planning (i.e., accounting for risk and uncertainty in long-term asset management resource allocation decisions).

2004-03-31T23:59:59.000Z

10

DOE-EM privatization and the 2006 Plan: Principles for procurement policies and risk management  

SciTech Connect

The Department of Energy`s Office of Environmental Remediation and Waste Management (EM) has recently set in place programs to restructure the strategic planning mechanism that will drive its clean-up schedule, The 2006 Plan, and to create a new set of business relationships with private contractors that will reduce costs--privatization. Taken together, the 2006 Plan and privatization will challenge EM to create new business practices to recast its risk management policies to support these initiatives while ensuring that its responsibilities toward the environment, human health, and worker safety (ES and H) are maintained. This paper argues that the 2006 Plan has transformed EM`s traditional, bottoms-up approach based on technical dictates to a top-down approach based on management goals--a transformation from an engineering problem to an economic problem. The 2006 Plan evolved from EM`s Ten-Year Plan, and seeks to convert the largely open-ended planning approach previously undertaken by EM to a plan bounded by time and dollars. The plan emphasizes making tradeoffs and choosing activities that deliver the most clean-up for the dollar. It also recognizes that each major player--stakeholders, DOE, OMB and Congress--has distinct interests that must be resolved if the process is to succeed. This, in turn, has created the need for a corresponding transformation in risk management practices from compliance-driven to benefit/cost-driven.

Bjornstad, D.J.; Jones, D.W.; Duemmer, C.L.

1997-08-01T23:59:59.000Z

11

Management Plan Management Plan  

E-Print Network (OSTI)

of a coevolving naturalcultural system. Suitable ecosystem attributes can be achieved by managing human maintenance that protects the riparian corridor. · Manage recreational use to protect riparian values Creek and the Warm Springs River during runoff periods. · Road systems and upland management practices

12

Management Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Management Plan (SSMP) to be submitted to Congress after the April 2010 release of the Nuclear Posture Review Report. It is aligned with the President's National Security Strategy...

13

Fire risks in the field of architecture and urban planning design process of the civil constructions, management, evaluation and control  

Science Conference Proceedings (OSTI)

Based on the text study of the Firefighting Law, a series of conclusions are risen, that are, in the same time, tasks of fire risks management, evaluation and control within architecture and urban planning design process of constructions. Fire risks ... Keywords: architecture and urban planning design process, educational model, fire risk

Gheorghe Breazu; Cristian Dumitrescu

2010-07-01T23:59:59.000Z

14

Integrated Planning and Performance Management  

NLE Websites -- All DOE Office Websites (Extended Search)

Performance Management (IPPM) Head Program Administrator Planning Coordination Performance Analysis Chief Operating Officer Risk Analysis Lab PlanningGoal Setting Process ...

15

Risk Management Tool Attributes:  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

- Tools & SMEs - Tools & SMEs Outline for Breakout Session TOOLS 1. Types of Tools a. Risk Management - Database & Reports, risk register, risk forms, risk tracking & monitoring, basis of estimate, action item tracking, historical record of risks & changes, configuration control, enterprise-wide, metrics, risk performance index, risk checklist, graphical display, management reporting (various levels), risk communications b. Risk Analysis i. Cost, ii. budgets, funding, cash-flow analysis, iii. Schedule iv. tailoring categories v. Integrated Cost & Schedule vi. Project phase analysis; organization ownership & joint planning c. Risk Knowledge and Lessons Learned Database i. Enterprise-wide ii. Job/owner-specific iii. Workshops - project specific, risk management,

16

SC Introduction to Risk Management | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

are here Home SC Introduction to Risk Management SC Introduction to Risk Management SC Introduction to Risk Management More Documents & Publications LPP Risk Management Plan...

17

Risk-based Inspection Scheduling Planning for Intelligent Agent in the Autonomous Fault Management  

SciTech Connect

This paper developed an autonomous fault management focusing to the inspection scheduling planning which was implemented to the advanced small nuclear reactor without on-site refuelling to assure the safety without human intervention. The inspection scheduling planning was developed optimally on the risk-based approach compromising between two important constraints related to the risk of action planning as such failure probability and shortest path. Performance was represented using computer simulation implemented to the DURESS components location and failure probability. It could be concluded that the first priority to be inspected was flow sensor FB2 which had the largest comparation value of 0.104233 comparing with the other components. The next route would be visited were sequentially FB1, FA2, FA1, FB, FA, VB, pump B, VA, pump A, VB2, VB1, VA2, VA1, reservoir 2, reservoir 1, FR2, and FR1. The movement route planning could be transferred to activate the robot arm which reflected as intelligent agent.

Hari Nugroho, Djoko; Sudarno [Center for Reactor Technology and Nuclear Safety-BATAN, Indonesia Building no 80 PUSPIPTEK Area, Serpong (Indonesia)

2010-06-22T23:59:59.000Z

18

Performance Management Plan  

SciTech Connect

This Performance Management Plan describes the approach for accelerating cleanup activities of U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Operations Office (NNSA/NV) Environmental Management (EM) Program. This approach accelerates the reduction of risk at NNSA/NV sites while performing the work responsibly, effectively, and more efficiently. In May 2002, NNSA/NV EM and the Nevada Division of Environmental Protection signed a Letter of Intent formalizing an agreement to pursue accelerated risk reduction and cleanup for activities within the State of Nevada. This Performance Management Plan provides the strategic direction for implementing the Letter of Intent.

IT Corporation, Las Vegas, NV

2002-08-21T23:59:59.000Z

19

Risk Management RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Risk Management Review Module Risk Management Review Module March 2010 CD-0 O 0 OFFICE OF C CD-1 F ENVIRO Standard R Risk M Rev Critical Decis CD-2 M ONMENTAL Review Plan Managem view Module sion (CD) Ap CD March 2010 L MANAGE (SRP) ment e pplicability D-3 EMENT CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-1189-2008, Integration of Safety into the Design Process, and EM's internal

20

PROJECT MANAGEMENT PLANS Project Management Plans  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

MANAGEMENT PLANS MANAGEMENT PLANS Project Management Plans  Overview  Project Management Plan Suggested Outline Subjects  Crosswalk between the Suggested PMP Outline Subjects and a Listing of Project Planning Elements  Elements of Deactivation Project Planning  Examples From Project Management Plans Overview The purpose here is to assist project managers and project planners in creating a project plan by providing examples and pointing to information that have been successfully used by others in the past. Section 4.2 of DOE Guide 430.1-3, DEACTIVATION IMPLEMENTATION GUIDE discusses the content and purpose of deactivation project management plans. It is presented as a suggested outline followed by other potential subjects. For the convenience of readers, that information is repeated below.

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


21

Plan - Data Management  

NLE Websites -- All DOE Office Websites (Extended Search)

Plan Plan Data Management for Data Providers Click an arrow to follow the data management path of a data set from planning to curation. plan Overview plan Plan manage Manage archive Archive curation DAAC Curation Data Management Overview Plan Manage Archive DAAC Curation Related Links DAAC Help Best Practices PDF Workshops DataONE ESIP Data Management Plans NASA's Terrestrial Ecology Program now requires that each proposal include a Data Management Plan (DMP) of up to two pages. A DMP for a proposal is a brief document that outlines what you will do with your data during and after your research, to ensure your data will be safe, documented, and accessible now and in the future. A DMP - developed early and used throughout the research project - will increase research efficiency by making the data understandable and usable in the future and

22

Strategic planning in electric utilities: Using wind technologies as risk management tools  

Science Conference Proceedings (OSTI)

This paper highlights research investigating the ownership of renewable energy technologies to mitigate risks faced by the electric utility industry. Renewable energy technology attributes of fuel costs, environmental costs, lead time, modularity, and investment reversibility are discussed. Incorporating some of these attributes into an economic evaluation is illustrated using a municipal utility`s decision to invest in either wind generation or natural gas based generation. The research concludes that wind and other modular renewable energy technologies, such as photovoltaics, have the potential to provide decision makers with physical risk-management investments.

Hoff, T E [Pacific Energy Group, Stanford, CA (United States); Parsons, B [National Renewable Energy Lab., Golden, CO (United States)

1996-06-01T23:59:59.000Z

23

Managing Carbon Regulatory Risk in Utility Resource Planning:Current Practices in the Western United States  

Science Conference Proceedings (OSTI)

Concerns about global climate change have substantially increased the likelihood that future policy will seek to minimize carbon dioxide emissions. Assuch, even today, electric utilities are making resource planning and investment decisions that consider the possible implications of these future carbon regulations. In this article, we examine the manner in which utilities assess the financial risks associated with future carbon regulations within their long-term resource plans. We base our analysis on a review of the most recent resource plans filed by fifteen electric utilities in the Western United States. Virtually all of these utilities made some effort to quantitatively evaluate the potential cost of future carbon regulations when analyzing alternate supply- and demand-side resource options for meeting customer load. Even without Federal climate regulation in the U.S., the prospect of that regulation is already having an impact on utility decision-making and resource choices. That said, the methods and assumptions used by utilities to analyze carbon regulatory risk, and the impact of that analysis on their choice of a particular resource strategy, vary considerably, revealing a number of opportunities for analytic improvement. Though our review focuses on a subset of U.S. electric utilities, this work holds implications for all electric utilities and energy policymakers who are seeking to minimize the compliance costs associated with future carbon regulations

Barbose, Galen; Wiser, Ryan; Phadke, Amol; Goldman, Charles

2008-05-16T23:59:59.000Z

24

Managing Carbon Regulatory Risk in Utility Resource Planning: Current Practices in the Western United States  

Science Conference Proceedings (OSTI)

Concerns about global climate change have substantially increased the likelihood that future policy will seek to minimize carbon dioxide emissions. As such, even today, electric utilities are making resource planning and investment decisions that consider the possible implications of these future carbon regulations. In this article, we examine the manner in which utilities assess the financial risks associated with future carbon regulations within their long-term resource plans. We base our analysis on a review of the most recent resource plans filed by fifteen electric utilities in the Western United States. Virtually all of these utilities made some effort to quantitatively evaluate the potential cost of future carbon regulations when analyzing alternate supply- and demand-side resource options for meeting customer load. Even without Federal climate regulation in the U.S., the prospect of that regulation is already having an impact on utility decision-making and resource choices. That said, the methods and assumptions used by utilities to analyze carbon regulatory risk, and the impact of that analysis on their choice of a particular resource strategy, vary considerably, revealing a number of opportunities for analytic improvement. Though our review focuses on a subset of U.S. electric utilities, this work holds implications for all electric utilities and energy policymakers who are seeking to minimize the compliance costs associated with future carbon regulations.

Barbose, Galen; Wiser, Ryan; Phadke, Amol; Goldman, Charles

2008-07-11T23:59:59.000Z

25

High Risk Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Risk Plan Risk Plan John Bashista Melissa Rider Jeff Davis Timeline to date * OMB memo on Improving Government Acquisition issued July 29, 2009 - Review existing contracts and acquisition practices to save 7% of baseline contract spending (3.5% in FY 2010 and 3.5% in FY 2011) - Reduce high risk contracts by 10% the share of dollars obligated in FY2010 - Final plan was due and submitted on November 2, 2009 - OMB reviewed and requested revision Dec 23, 2009 - Revision submitted April 21, 2010 M&Os are an Issue * With respect to reductions in high risk contracting strategies, the M&O contracts was also a challenge since the opportunity to further influence competition and contract type was highly constrained. The Department had already competed approximately 85 percent of its M&O

26

NGNP Risk Management Database: A Model for Managing Risk  

Science Conference Proceedings (OSTI)

To facilitate the implementation of the Risk Management Plan, the Next Generation Nuclear Plant (NGNP) Project has developed and employed an analytical software tool called the NGNP Risk Management System (RMS). A relational database developed in Microsoft Access, the RMS provides conventional database utility including data maintenance, archiving, configuration control, and query ability. Additionally, the tools design provides a number of unique capabilities specifically designed to facilitate the development and execution of activities outlined in the Risk Management Plan. Specifically, the RMS provides the capability to establish the risk baseline, document and analyze the risk reduction plan, track the current risk reduction status, organize risks by reference configuration system, subsystem, and component (SSC) and Area, and increase the level of NGNP decision making.

John Collins

2009-09-01T23:59:59.000Z

27

Environmental Management System Plan  

E-Print Network (OSTI)

3) environmental management programs, (4) training, (5)Management Programs3-5 Structure and Responsibility.3-6 Training,Management System Plan Program Elements Additional information regarding EMS training

Fox, Robert

2009-01-01T23:59:59.000Z

28

Energy planning and management plan  

Science Conference Proceedings (OSTI)

This paper contains printed copies of 60FR 53181, October 12, 1995 and 60 FR 54151. This is a record of decision concerning the Western Area Power Administration`s final draft and environmental impact statement, and Energy Planning and Management Program.

NONE

1996-01-01T23:59:59.000Z

29

Carbon Sequestration Risks and Risk Management  

NLE Websites -- All DOE Office Websites (Extended Search)

Carbon Sequestration Risks and Risk Management Title Carbon Sequestration Risks and Risk Management Publication Type Report Year of Publication 2008 Authors Price, Phillip N.,...

30

LFRG Program Management Plan  

Energy.gov (U.S. Department of Energy (DOE))

The purpose of the EM Low-Level Waste Disposal Facility Federal Review Group Program Management Plan (LFRG PMP) is to establish the LFRG roles and responsibilities, the LFRG management processes,...

31

ICT Supply Chain Risk Management  

Science Conference Proceedings (OSTI)

... ICT Supply Chain Risk Management Manager's Forum ... ICT Supply Chain Risk Management National Institute of Standards and Technology Page 6. ...

2013-06-04T23:59:59.000Z

32

Managing Carbon Regulatory Risk in Utility Resource Planning: Current Practices in the Western United States  

E-Print Network (OSTI)

prices is therefore critical to properly valuing energy efficiency cost-effectiveness and marketenergy planning and investment decisions. Electricity market pricesenergy markets that may be important for energy planners to consider, including: Allowance prices

Barbose, Galen

2008-01-01T23:59:59.000Z

33

Managing Carbon Regulatory Risk in Utility Resource Planning: Current Practices in the Western United States  

E-Print Network (OSTI)

prices is therefore critical to properly valuing energy efficiency cost-effectiveness and marketenergy planning and investment decisions. Electricity market pricesenergy markets that may be important for energy planners to consider, including: Allowance prices

Barbose, Galen

2009-01-01T23:59:59.000Z

34

Transportation Demand Management Plan  

E-Print Network (OSTI)

Transportation Demand Management Plan FALL 2009 #12;T r a n s p o r t a t i o n D e m a n d M a n the transportation impacts the expanded enrollment will have. Purpose and Goal The primary goal of the TDM plan is to ensure that adequate measures are undertaken and maintained to minimize the transportation impacts

35

Reading the Tea Leaves: How Utilities in the West Are Managing Carbon Regulatory Risk in their Resource Plans  

Science Conference Proceedings (OSTI)

The long economic lifetime and development lead-time of many electric infrastructure investments requires that utility resource planning consider potential costs and risks over a lengthy time horizon. One long-term -- and potentially far-reaching -- risk currently facing the electricity industry is the uncertain cost of future carbon dioxide (CO2) regulations. Recognizing the importance of this issue, many utilities (sometimes spurred by state regulatory requirements) are beginning to actively assess carbon regulatory risk within their resource planning processes, and to evaluate options for mitigating that risk. However, given the relatively recent emergence of this issue and the rapidly changing political landscape, methods and assumptions used to analyze carbon regulatory risk, and the impact of this analysis on the selection of a preferred resource portfolio, vary considerably across utilities. In this study, we examine the treatment of carbon regulatory risk in utility resource planning, through a comparison of the most-recent resource plans filed by fifteen investor-owned and publicly-owned utilities in the Western U.S. Together, these utilities account for approximately 60percent of retail electricity sales in the West, and cover nine of eleven Western states. This report has two related elements. First, we compare and assess utilities' approaches to addressing key analytical issues that arise when considering the risk of future carbon regulations. Second, we summarize the composition and carbon intensity of the preferred resource portfolios selected by these fifteen utilities and compare them to potential CO2 emission benchmark levels.

Barbose, Galen; Wiser, Ryan; Phadke, Amol; Goldman, Charles

2008-02-01T23:59:59.000Z

36

Environmental information management plan  

Science Conference Proceedings (OSTI)

The Environmental Information Management Plan provides an overview of the management of environmental information generation by Hanford Site programs. The long-term nature of environmental programs requires that electronic data, documents, and other materials be kept for extended periods in a secure, controlled, and retrievable manner. An important part of the program is the maintenance of administrative records under the Hanford Federal Facility Agreement and Consent Order (Ecology et al. 1989). The Environmental Information Management Plan introduces Westinghouse Hanford records management and engineering document control systems and their relationship to environmental programs. Specific information is provided about the operation of the Environmental Data Management Center, a central facility that receives, processes, and maintains information related to environmental program activities. The Environmental Data Management Center maintains a reference file, coordinates administrative record activities, and distributes administrative record indexes and administrative record documents to the US Environmental Protection Agency, the US Department of Energy, the Washington State Department of Ecology, and four information repositories. 43 refs., 16 figs., 5 tabs.

Michael, L.E.; Main, G.C.; See, E.J.

1990-03-01T23:59:59.000Z

37

Plutonium Vulnerability Management Plan  

Science Conference Proceedings (OSTI)

This Plutonium Vulnerability Management Plan describes the Department of Energy`s response to the vulnerabilities identified in the Plutonium Working Group Report which are a result of the cessation of nuclear weapons production. The responses contained in this document are only part of an overall, coordinated approach designed to enable the Department to accelerate conversion of all nuclear materials, including plutonium, to forms suitable for safe, interim storage. The overall actions being taken are discussed in detail in the Department`s Implementation Plan in response to the Defense Nuclear Facilities Safety Board (DNFSB) Recommendation 94-1. This is included as Attachment B.

NONE

1995-03-01T23:59:59.000Z

38

Waste Management Quality Assurance Plan  

E-Print Network (OSTI)

PROGRAM .4 Organizational Structure ..4 Management Quality Assurance Functions 5 Planning 5 2.0 PERSONNEL TRAINING AND

Waste Management Group

2006-01-01T23:59:59.000Z

39

Catalyst Management Planning  

Science Conference Proceedings (OSTI)

Catalyst used in selective catalytic reduction (SCR) systems for NOx control in coal-fired power plants is susceptible to deactivation over time due to exposure to trace elements contained in the coal. In order to sustain the levels of NOx reduction needed to comply with regulatory requirements, periodic replacement of the catalyst modules with new or regenerated catalyst is an essential element in operating an SCR system. Catalyst management planning is a process whereby decisions are made about when ca...

2010-12-21T23:59:59.000Z

40

Energy Management and Conservation Plan  

E-Print Network (OSTI)

Energy Management and Conservation Plan December 2005 #12;Texas Transportation Institute December 2005 Energy Management and Conservation Plan Page 2 of 24 Table of Contents Section One: Executive: Reporting Progress #12;Texas Transportation Institute December 2005 Energy Management and Conservation Plan

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


41

Environmental Management System Plan  

SciTech Connect

Executive Order 13423, Strengthening Federal Environmental, Energy, and Transportation Management establishes the policy that Federal agencies conduct their environmental, transportation, and energy-related activities in a manner that is environmentally, economically and fiscally sound, integrated, continually improving, efficient, and sustainable. The Department of Energy (DOE) has approved DOE Order 450.1A, Environmental Protection Program and DOE Order 430.2B, Departmental Energy, Renewable Energy and Transportation Management as the means of achieving the provisions of this Executive Order. DOE Order 450.1A mandates the development of Environmental Management Systems (EMS) to implement sustainable environmental stewardship practices that: (1) Protect the air, water, land, and other natural and cultural resources potentially impacted by facility operations; (2) Meet or exceed applicable environmental, public health, and resource protection laws and regulations; and (3) Implement cost-effective business practices. In addition, the DOE Order 450.1A mandates that the EMS must be integrated with a facility's Integrated Safety Management System (ISMS) established pursuant to DOE P 450.4, 'Safety Management System Policy'. DOE Order 430.2B mandates an energy management program that considers energy use and renewable energy, water, new and renovated buildings, and vehicle fleet activities. The Order incorporates the provisions of the Energy Policy Act of 2005 and Energy Independence and Security Act of 2007. The Order also includes the DOE's Transformational Energy Action Management initiative, which assures compliance is achieved through an Executable Plan that is prepared and updated annually by Lawrence Berkeley National Laboratory (LBNL, Berkeley Lab, or the Laboratory) and then approved by the DOE Berkeley Site Office. At the time of this revision to the EMS plan, the 'FY2009 LBNL Sustainability Executable Plan' represented the most current Executable Plan. These DOE Orders and associated policies establish goals and sustainable stewardship practices that are protective of environmental, natural, and cultural resources, and take a life cycle approach that considers aspects such as: (1) Acquisition and use of environmentally preferable products; (2) Electronics stewardship; (3) Energy conservation, energy efficiency, and renewable energy; (4) Pollution prevention, with emphasis on toxic and hazardous chemical and material reduction; (5) Procurement of efficient energy and water consuming materials and equipment; (6) Recycling and reuse; (7) Sustainable and high-performance building design; (8) Transportation and fleet management; and (9) Water conservation. LBNL's approach to sustainable environmental stewardship required under Order 450.1A poses the challenge of implementing its EMS in a compliance-based, performance-based, and cost-effective manner. In other words, the EMS must deliver real and tangible business value at a minimal cost. The purpose of this plan is to describe Berkeley Lab's approach for achieving such an EMS, including an overview of the roles and responsibilities of key Laboratory parties. This approach begins with a broad-based environmental policy consistent with that stated in Chapter 11 of the LBNL Health and Safety Manual (PUB-3000). This policy states that Berkeley Lab is committed to the following: (1) Complying with applicable environmental, public health, and resource conservation laws and regulations. (2) Preventing pollution, minimizing waste, and conserving natural resources. (3) Correcting environmental hazards and cleaning up existing environmental problems, and (4) Continually improving the Laboratory's environmental performance while maintaining operational capability and sustaining the overall mission of the Laboratory. A continual cycle of planning, implementing, evaluating, and improving processes will be performed to achieve goals, objectives, and targets that will help LBNL carry out this policy. Each year, environmental aspects will be identified and their impacts to the environm

Fox, Robert; Thorson, Patrick; Horst, Blair; Speros, John; Rothermich, Nancy; Hatayama, Howard

2009-03-24T23:59:59.000Z

42

Risk Management Process Overview | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Cybersecurity Risk Management Process Risk Management Process Overview Risk Management Process Overview figure depicting three tier risk management process The cybersecurity...

43

Project Management Plan  

SciTech Connect

The mission of the Uranium Mill Tailings Remedial Action (UMTRA) Project is explicitly stated and directed in the Uranium Mill Tailings Radiation Control Act of 1978, Public Law 95-604, 42 USC 7901 (hereinafter referred to as the Act''). Title I of the Act authorizes the Department of Energy (DOE) to undertake remedial actions at 24 designated inactive uranium processing sites and associated vicinity properties containing uranium mill tailings and other residual radioactive materials derived from the processing sites. The Act, amended in January 1983, by Public Law 97-415, also authorizes DOE to perform remedial actions at vicinity properties in Edgemont, South Dakota. Cleanup of the Edgemont processing site is the responsibility of the Tennessee Valley Authority. This document describes the plan, organization, system, and methodologies used to manage the design, construction, and other activities required to clean up the designated sites and associated vicinity properties in accordance with the Act. The plan describes the objectives of the UMTRA Project, defines participants' roles and responsibilities, outlines the technical approach for accomplishing the objectives, and describes the planning and managerial controls to be used in integrating and performing the Project mission. 21 figs., 21 tabs.

Not Available

1988-01-01T23:59:59.000Z

44

Enterprise level IT risk management  

Science Conference Proceedings (OSTI)

Increasing IT budget and over-dependence of business on IT infra-structure makes risk management a critical component of enterprise management. The creation and sustenance of an IT risk management framework is one of the crucial and challenging tasks ... Keywords: enterprise level, information technology, risk management

Nadhirah Azizi; Khairuddin Hashim

2008-11-01T23:59:59.000Z

45

Risk-sensitive planning support for forest enterprises: The YAFO model  

Science Conference Proceedings (OSTI)

YAFO is a planning-support tool for the development of management plans under uncertainty focusing on the forest enterprise level. Based on existing stand data, the software provides the calculation of management scenarios (felling plans) for single ... Keywords: Economic optimization, Forest management planning, Long-term objectives, Nonlinear programming, Operational planning, Risk integration

Fabian HRtl, Andreas Hahn, Thomas Knoke

2013-06-01T23:59:59.000Z

46

Microsoft Word - EM_CM_3_Risk_Management_Best Practices and Gaps.doc  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

CONTRACT AND PROJECT MANAGEMENT CONTRACT AND PROJECT MANAGEMENT ROOT CAUSE ANALYSIS CORRECTIVE ACTION PLAN CORRECTIVE MEASURE 3 IDENTIFICATION OF BEST RISK MANAGEMENT PRACTICES AND ANALYSIS OF DOE RISK MANAGEMENT PLANS SUMMARY REPORT JULY 2009 ii iii Contents 1.0 Introduction......................................................................................................................... 1 2.0 Discussion of Approach...................................................................................................... 2 3.0 Summary of Gaps and Planned Next Steps ........................................................................ 7 Attachment 1- List of Risk Management Plans Reviewed ........................................................ 12 Attachment 2-Risk Management Best Practices

47

CALIFORNIA STATE UNIVERSITY, RISK MANAGEMENT  

E-Print Network (OSTI)

performance within the CSU System. #12;2004 ­ 2005 Risk Management Annual Report Page 3 · Chaired the CSU-04 2004-05 Fullerton System-Wide #12;2004 ­ 2005 Risk Management Annual Report Page 10 University · International travel · Facilities use · Deferred maintenance Working with the University's Risk Management

de Lijser, Peter

48

Reading the Tea Leaves: How Utilities in the West Are Managing Carbon Regulatory Risk in their Resource Plans  

E-Print Network (OSTI)

$24/ton, levelized over 2020-2030) was for a scenario inUtility Resource Plans (2010-2030) .. xii Figure ES - 2.Resource Plans (2010-2030).. 10 Maximum Energy

Barbose, Galen

2008-01-01T23:59:59.000Z

49

Environmental Management System Plan  

E-Print Network (OSTI)

offices, the EMS Program Program Elements Environmental ManagementOffice of Institutional Assurance as stated in the OQMP. 3-7 Environmental ManagementEnvironmental Management System Fiscal Year Improve (EMP classification) Integrated Safety Management System International Organization for Standardization Lawrence Berkeley National Laboratory Office

Fox, Robert

2009-01-01T23:59:59.000Z

50

Emergency Management Plan 2010 March 1 EMERGENCY MANAGEMENT PLAN  

E-Print Network (OSTI)

or Disaster 3.1 Initiation of Level 2 and 3 Emergency Response 4. Activation of Emergency Management Plan.......................................................................................................... 5 1. Emergency Response Levels 2. Planning and Implementation Principles 3. Incident Command System and Authority of Director of Emergency Operations Response Procedures

Argerami, Martin

51

Annual Planning Summaries: Environmental Management (EM) | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Environmental Management (EM) Annual Planning Summaries: Environmental Management (EM) Document(s) Available For Download February 3, 2012 2012 Annual Planning Summary for...

52

AVLIS production plant waste management plan  

Science Conference Proceedings (OSTI)

Following the executive summary, this document contains the following: (1) waste management facilities design objectives; (2) AVLIS production plant wastes; (3) waste management design criteria; (4) waste management plan description; and (5) waste management plan implementation. 17 figures, 18 tables.

Not Available

1984-11-15T23:59:59.000Z

53

Risk management for IT and software projects  

Science Conference Proceedings (OSTI)

Risk management can be defined as a systematic process for identifying, analyzing and controlling risks in projects or organizations. Definitions and illustrations of risks are given; in particular, a list of ten risk factors which occur most frequently ... Keywords: Riskit, analysis of risks, control of risks, identification of risks, monitoring of risks, project risks, quality management, risk definition, risk management, risk management process, risk scenario

E. Wallmller

2002-01-01T23:59:59.000Z

54

Reading the Tea Leaves: How Utilities in the West Are Managing Carbon Regulatory Risk in their Resource Plans  

E-Print Network (OSTI)

acquire all cost-effective energy efficiency and renewableBalancing Cost and Risk: The Treatment of Renewable Energythe cost effectiveness of energy efficiency and renewable

Barbose, Galen

2008-01-01T23:59:59.000Z

55

Sanitary Sewer System Management Plan  

E-Print Network (OSTI)

Indicators PMT Plant Maintenance Technician POSM Pipeline Observation System Management POTW Publicly OwnedSanitary Sewer System Management Plan Prepared by: Environment, Health and Safety Division to enforce any violation iii-10 Section iv: Operation and Maintenance Program iv iv-a: System mapping iv-2 iv

56

NGNP Risk Management Database: A Model for Managing Risk  

Science Conference Proceedings (OSTI)

The Next Generation Nuclear Plant (NGNP) Risk Management System (RMS) is a database used to maintain the project risk register. The RMS also maps risk reduction activities to specific identified risks. Further functionality of the RMS includes mapping reactor suppliers Design Data Needs (DDNs) to risk reduction tasks and mapping Phenomena Identification Ranking Table (PIRTs) to associated risks. This document outlines the basic instructions on how to use the RMS. This document constitutes Revision 1 of the NGNP Risk Management Database: A Model for Managing Risk. It incorporates the latest enhancements to the RMS. The enhancements include six new custom views of risk data - Impact/Consequence, Tasks by Project Phase, Tasks by Status, Tasks by Project Phase/Status, Tasks by Impact/WBS, and Tasks by Phase/Impact/WBS.

John Collins; John M. Beck

2011-11-01T23:59:59.000Z

57

Underground storage tank management plan  

Science Conference Proceedings (OSTI)

The Underground Storage Tank (UST) Management Program at the Oak Ridge Y-12 Plant was established to locate UST systems in operation at the facility, to ensure that all operating UST systems are free of leaks, and to establish a program for the removal of unnecessary UST systems and upgrade of UST systems that continue to be needed. The program implements an integrated approach to the management of UST systems, with each system evaluated against the same requirements and regulations. A common approach is employed, in accordance with Tennessee Department of Environment and Conservation (TDEC) regulations and guidance, when corrective action is mandated. This Management Plan outlines the compliance issues that must be addressed by the UST Management Program, reviews the current UST inventory and compliance approach, and presents the status and planned activities associated with each UST system. The UST Management Plan provides guidance for implementing TDEC regulations and guidelines for petroleum UST systems. (There are no underground radioactive waste UST systems located at Y-12.) The plan is divided into four major sections: (1) regulatory requirements, (2) implementation requirements, (3) Y-12 Plant UST Program inventory sites, and (4) UST waste management practices. These sections describe in detail the applicable regulatory drivers, the UST sites addressed under the Management Program, and the procedures and guidance used for compliance with applicable regulations.

NONE

1994-09-01T23:59:59.000Z

58

Environmental Management System Plan  

E-Print Network (OSTI)

Protection Program, DOE Order 450.1A (June 4, 3. DOE Oand Health Reporting, DOE Order 231.1A (1995, as amended).Emergency Management System, DOE Order 151.1B (October 29,

Fox, Robert

2009-01-01T23:59:59.000Z

59

An application of agribusiness strategic planning under risk  

E-Print Network (OSTI)

Agriculture entered a new era with the passage of the 1996 FAIR Act. This new era will likely be associated with increasing risk factors that agribusiness managers must consider in developing appropriate management strategies. Managers who can anticipate the changes in the economic environment and correctly alter their decisions to maximize returns, given an acceptable level of risk will likely improve the agribusiness's chances of success. The objective of this research is to evaluate an agribusiness's strategic plan in a risky economic environment. A firm level, financial risk analysis model (FRAN) will be used to quantify the probabilistic economic outcomes resulting from alternative equity management decisions. The analysis will provide the decision-makers with a tool to evaluate alternative equity management plans of action. Managers will be able to evaluate the likelihood of adverse risk and the benefits of transferring risk to other parties. This case study was applied to a multi-divisional cooperative on the high plains of Texas to validate the model's ability to reasonably reflect the economic activity of the cooperative. Alternative equity management strategies were analyzed and presented to the board of trustees and manager. These decision-makers found the risk management assessment to be valuable in their decision making process.

Laughlin, Charles Tudor

1999-01-01T23:59:59.000Z

60

Solid Waste Management Program Plan  

SciTech Connect

The objective of the Solid Waste Management Program Plan (SWMPP) is to provide a summary level comprehensive approach for the storage, treatment, and disposal of current and future solid waste received at the Hanford Site (from onsite and offsite generators) in a manner compliant with current and evolving regulations and orders (federal, state, and Westinghouse Hanford Company (Westinghouse Hanford)). The Plan also presents activities required for disposal of selected wastes currently in retrievable storage. The SWMPP provides a central focus for the description and control of cost, scope, and schedule of Hanford Site solid waste activities, and provides a vehicle for ready communication of the scope of those activities to onsite and offsite organizations. This Plan represents the most complete description available of Hanford Site Solid Waste Management (SWM) activities and the interfaces between those activities. It will be updated annually to reflect changes in plans due to evolving regulatory requirements and/or the SWM mission. 8 refs., 9 figs., 4 tabs.

Duncan, D.R.

1990-08-01T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


61

8 Management Plan Introduction  

E-Print Network (OSTI)

in the subbasin to mitigate and protect resources affected by the construction and operation of the Federal ratepayer funds to construct or improve existing infrastructure, to acquire land or protective easements geographic scope are: · Unknown management strategies for the Hanford Reach Monument, because the U.S. Fish

62

Waste Management Quality Assurance Plan  

SciTech Connect

Lawrence Berkeley Laboratory`s Environment Department addresses its responsibilities through activities in a variety of areas. The need for a comprehensive management control system for these activities has been identified by the Department of Energy (DOE). The WM QA (Waste Management Quality Assurance) Plan is an integral part of a management system that provides controls necessary to ensure that the department`s activities are planned, performed, documented, and verified. This WM QA Plan defines the requirements of the WM QA program. These requirements are derived from DOE Order 5700.6C, Quality Assurance, the LBL Operating and Assurance Program Plan (OAP, LBL PUB-3111), and other environmental compliance documents applicable to WM activities. The requirements presented herein, as well as the procedures and methodologies that direct the implementation of these requirements, will undergo review and revisions as necessary. The provisions of this QA Plan and its implementing documents apply to quality-affecting activities performed by and for WM. It is also applicable to WM contractors, vendors, and other LBL organizations associated with WM activities, except where such contractors, vendors, or organizations are governed by their own WM-approved QA programs. References used in the preparation of this document are (1) ASME NQA-1-1989, (2) ANSI/ASQC E4 (Draft), (3) Waste Management Quality Assurance Implementing Management Plan (LBL PUB-5352, Rev. 1), (4) LBL Operating and Assurance Program Plan (OAP), LBL PUB-3111, 2/3/93. A list of terms and definitions used throughout this document is included as Appendix A.

Not Available

1993-11-30T23:59:59.000Z

63

SOLID WASTE MANAGEMENT PLAN  

E-Print Network (OSTI)

ACKNOWLEDGMENTS The Chelan County Public Works Department would like to thank the following organizations and individuals for their assistance in the development of this plan: ? Chelan Countys Solid Waste Council members, past and present, and the municipalities they represent. ? Chelan Countys Solid Waste Advisory Committee members, past and present, and the agencies and businesses they represented. ? the ChelanDouglas Health District staff. ? Washington Department of Ecology staff. Chelan County residents and businesses also contributed to this document through comments provided during public meetings and through various other channels. The Board of County Commissioners and the Public Works Department gratefully acknowledge this input by the

unknown authors

2007-01-01T23:59:59.000Z

64

Risk Management RM  

Energy.gov (U.S. Department of Energy (DOE))

This tool is the process of continuous and iterative identification and control of project risks and opportunities. Risks can be technical, financial, or programmatic. The goal for the risk...

65

A reservoir management plan  

DOE Green Energy (OSTI)

There are numerous documented cases of extraction of fluids from the ground causing surface subsidence. The cases include groundwater, oil and gas, as well as geothermal fluid withdrawal. A recent comprehensive review of all types of man-induced land subsidence was published by the Geological Survey of America. At the early stages of a geothermal power development project it is standard practice in most countries for an environmental impact report to be required. The possibility of geothermal subsidence has to be addressed, and usually it falls on the geophysicists and/or geologists to make some predictions. The advice given is vital for planning the power plant location and the borefield pipe and drain layout. It is not so much the vertical settlement that occurs with subsidence but the accompanying horizontal ground strains that can do the most damage to any man-made structure.

Allis, R.G.

1989-06-16T23:59:59.000Z

66

Risk Aversion in Inventory Management  

E-Print Network (OSTI)

Traditional inventory models focus on risk-neutral decision makers, i.e., characterizing replenishment strategies that maximize expected total profit, or equivalently, minimize expected total cost over a planning horizon. ...

Chen, Xin

67

Water Management Planning  

NLE Websites -- All DOE Office Websites (Extended Search)

water efficiency water efficiency at Federal sites Background The Federal Energy Management Program (FEMP) sponsored a water assessment at the Y-12 National Security Complex (Y-12) located in Oak Ridge, Tennessee, during fiscal year 2010. Driven by mandated water reduction goals of Executive Orders 13423 and 13514, the objective of the water assessment was to develop a comprehensive understanding of the current water-consuming applications and equipment at Y-12 and to identify key areas for water efficiency improvements. The water-assessment team learned key lessons from the Y-12 assessment. Therefore, the aim of this document is to share these key lessons to help other large process-driven sites at the Department of Energy (DOE) and beyond develop a comprehensive

68

Water Management Planning  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

water efficiency water efficiency at Federal sites Background The Federal Energy Management Program (FEMP) sponsored a water assessment at the Y-12 National Security Complex (Y-12) located in Oak Ridge, Tennessee, during fiscal year 2010. Driven by mandated water reduction goals of Executive Orders 13423 and 13514, the objective of the water assessment was to develop a comprehensive understanding of the current water-consuming applications and equipment at Y-12 and to identify key areas for water efficiency improvements. The water-assessment team learned key lessons from the Y-12 assessment. Therefore, the aim of this document is to share these key lessons to help other large process-driven sites at the Department of Energy (DOE) and beyond develop a comprehensive

69

Best Management Practice: Water Management Planning | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Best Management Practice: Water Management Planning Best Management Practice: Water Management Planning Best Management Practice: Water Management Planning October 7, 2013 - 3:03pm Addthis A successful water management program starts with developing a comprehensive water management plan. This plan should be included within existing facility operating plans. Water management plans should provide clear information about how a facility uses water from the time it is piped in to its ultimate disposal. Knowing how water is used and what it costs enables Federal agencies to make appropriate water management decisions. Overview Federal facility water management plans should include the following: Water Use Policy Statement and Goals Senior management should indicate support for water efficiency in a material way. This can be done in two ways:

70

Federal Energy Management Program: Plans, Implementation, and...  

NLE Websites -- All DOE Office Websites (Extended Search)

Plans, Implementation, and Results to someone by E-mail Share Federal Energy Management Program: Plans, Implementation, and Results on Facebook Tweet about Federal Energy...

71

Environmental Restoration Program Management Control Plan  

SciTech Connect

This Management Control Plan has been prepared to define the Energy Systems approach to managing its participation in the US DOE's Environmental Restoration (ER) Program in a manner consistent with DOE/ORO 931: Management Plan for the DOE Field Office, Oak Ridge, Decontamination and Decommissioning Program; and the Energy Systems Environmental Restoration Contract Management Plan (CMP). This plan discusses the systems, procedures, methodology, and controls to be used by the program management team to attain these objectives.

1991-09-01T23:59:59.000Z

72

Risk and risk management in software projects: A reassessment  

Science Conference Proceedings (OSTI)

Controlling risk in software projects is considered to be a major contributor to project success. This paper reconsiders the status of risk and risk management in the literature and practice. The analysis is supported by a study of risk practices in ... Keywords: Project management, Risk management, Software projects, Threat management

Paul L. Bannerman

2008-12-01T23:59:59.000Z

73

Annual Planning Summaries: Environmental Management-Consolidated...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Environmental Management-Consolidated Business Service Center (EM-CBC) Annual Planning Summaries: Environmental Management-Consolidated Business Service Center (EM-CBC) Document(s)...

74

Risk Management Tool Attributes:  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

of cost - input cost distribution; expert input on distribution selection g. time-phase input h. scenarios 2. Outputs a. Distributions b. Graphics c. Key risks (tornado) d....

75

VA Energy Management Action Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

VA Energy Management VA Energy Management Action Plan Ken Demers Chief, VA National Energy Business Center Purpose Cited Deficiencies Within VA's Previous Energy Program... *No comprehensive Department-wide policy *Lack of coordinated acquisition and investment strategies throughout the Administrations and Staff Offices *No uniform measurement and verification of energy usage *Unverifiable reporting mechanism *Lack of capturing "lessons learned" and best practices from previous experiences Potential Annual Savings ENERGY COST ($000) CONSUMPTION (Billion Btu) Baseline - FY 2005: $397,577 Baseline - FY 2005: 29,094 Savings Savings SOURCE OF SAVINGS FY 2007 FY 2008 Future TOTAL

76

IX disposition project, project management plan  

SciTech Connect

This subproject management plan defines the roles, responsibilities, and actions required for the execution of the IX Disposition Project.

WILLIAMS, N.H.

1999-05-11T23:59:59.000Z

77

DOCS System Configuration Management Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

DOCS System Configuration Management Plan DOCS System Configuration Management Plan The DOCS Systems Configuration Management Plan (SCMP), from an actual DOE systems engineering...

78

Data Management Planning for KU Social Scientists  

E-Print Network (OSTI)

Data Management Planning for KU Social Scientists drafting Grant Applications Travis Weller Grant Development Specialist Institute for Policy & Social Research #12;Data Management Planning for KU Social Scientists drafting Grant Applications 3/6/13 2 Data Management Planning » Explain the importance of data

Peterson, Blake R.

79

Risk Management Tool Attributes: | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Management Tool Attributes: More Documents & Publications Software Development Risk Assessment Risk Management RM Categorizing Threat Building and Using a Generic Threat Matrix...

80

Demand Response and Risk Management  

Science Conference Proceedings (OSTI)

For several decades, power companies have deployed various types of demand response (DR), such as interruptible contracts, and there is substantial ongoing research and development on sophisticated mechanisms for triggering DR. In this white paper, EPRI discusses the increasing use of electricity DR in the power industry and how this will affect the practice of energy risk management. This paper outlines 1) characteristics of a common approach to energy risk management, 2) the variety of types of DR impl...

2008-12-18T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


81

Integrated Planning and Performance Management  

NLE Websites -- All DOE Office Websites (Extended Search)

DOESC Scientific Facilities Strategic Plan (20 years, major capital projects) * DOE Strategic Plan (7-10 years) * DOE (HEP)Fermilab Strategic Plan (10 years) * FRAFNAL Plan for...

82

Transmission Price Risk Management  

Science Conference Proceedings (OSTI)

This report is concerned with the financial risks that arise from the uncertain price of transmission service in restructured or competitive electricity markets. These risks are most severe in markets with locational pricing (LMP), but they also exist in more traditionally organized electricity markets. This report has two main purposes. The first is to review the existing mathematical models of electricity price formation in spot and forward markets that may be helpful as the foundations for developing ...

2006-12-04T23:59:59.000Z

83

Risk Management Process Overview | Department of Energy  

NLE Websites -- All DOE Office Websites (Extended Search)

» Risk Management Process Overview » Risk Management Process Overview Risk Management Process Overview figure depicting three tier risk management process The cybersecurity risk management process explained in the Electricity Sector Cybersecurity Risk Management Process (RMP) Guideline has two primary components: the risk management model and the the risk management cycle. The risk management model reflects the organization as a three-tiered structure and provides a comprehensive view for the electricity sector organization and how risk management activities are undertaken across the organization. This structure is simple enough that it can be applied to any electricity sector organization regardless of size or operations. The three tiers of the risk management model are: Tier 1: Organization

84

ICDF Complex Operations Waste Management Plan  

SciTech Connect

This Waste Management Plan functions as a management and planning tool for managing waste streams generated as a result of operations at the Idaho CERCLA Disposal Facility (ICDF) Complex. The waste management activities described in this plan support the selected remedy presented in the Waste Area Group 3, Operable Unit 3-13 Final Record of Decision for the operation of the Idaho CERCLA Disposal Facility Complex. This plan identifies the types of waste that are anticipated during operations at the Idaho CERCLA Disposal Facility Complex. In addition, this plan presents management strategies and disposition for these anticipated waste streams.

W.M. Heileson

2006-12-01T23:59:59.000Z

85

Manhole Event Risk Management  

Science Conference Proceedings (OSTI)

This technical update report is an account of continuing research conducted in 2007 on managing and mitigating underground distribution manhole events. Major events that result in collateral damage are rare; but the energy involved in a major event is equivalent to that released by several sticks of dynamite; and it may present significant hazard to the public and result in costly litigation. Research effort in 2007 concentrated mainly on developing a software model of gas-related explosions that can be ...

2007-12-19T23:59:59.000Z

86

SC Introduction to Risk Management  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

OF OF SCIENCE Office of Science Risk Management November 4, 2009 Ray Won Office of Project Assessment Office of Science, U.S. Department of Energy Office of Science, U.S. Department of Energy http://www.science.doe.gov/opa/ 2 AGENDA AGENDA Wednesday, November 4, 2009, Building 2714, Oak Ridge 2:15 p.m. Introduction to SC Risk Management 2:25 p.m. Spallation Neutron Source 2:40 p.m. ORNL Risk Management Process 2:55 p.m. National Synchrotron Light Source II 3:10 p.m. Questions 3:30 p.m. End OFFICE OF SCIENCE 3 DOE Organization DOE Organization OFFICE OF SCIENCE Federal Energy Regulatory Commission Office of the Under Secretary for Nuclear Security/ Administrator for National Nuclear Security Administration Thomas P. D'Agostino Chief of Staff *The Deputy Secretary also serves as the Chief Operating Officer.

87

Revised Acquisition Guide Chapter 42.5, Contract Management Planning  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

2-24 2-24 Date: February 21, 2012 To: Procurement Directors From: Director Contract and Financial Assistance Policy Division Office of Policy Office of Procurement and Assistance Management Subject: Revised Acquisition Guide Chapter 42.5, Contract Management Planning Summary: The Department of Energy (DOE) has been on GAO's High Risk List for the past several years as a result of inadequate contract and project management. Accordingly, the improvement of contract administration is a critical issue for DOE. The Acquisition Guide chapter on Contract Management Planning has been completely revised to address this matter.

88

PFPC: Building an IT Risk Management Competency  

E-Print Network (OSTI)

IT Risk management is becoming increasingly important for CIOs and their executive counterparts. Educators and managers have materials they can use to discuss specific IT risks in project management, security and other ...

Westerman, George

2005-07-29T23:59:59.000Z

89

Risk-Informed Asset Management  

Science Conference Proceedings (OSTI)

This report contains business requirements for Risk-Informed Asset Management (RIAM) software. The requirements pertain to both a full-blown version of RIAM (including uncertainty analysis of the economic and safety risk of a proposed equipment improvement project) and for RIAM Level 1 project screening software. The RIAM Level 1 analysis is a bounding process intended to estimate the most optimistic effect that the proposed investment would have on plant safety, cost, and revenue. The optimistic assumpt...

2006-02-24T23:59:59.000Z

90

Hanford Mission Plan risk-based prioritization methodologies  

SciTech Connect

Sites across the US Department (DOE) complex recognize the critical need for a systematic method for prioritizing among their work scope activities. Here at the Hanford Site, Pacific Northwest Laboratory and Westinghouse Hanford Company (WHC) conducted preliminary research into techniques to meet this need and assist managers in making financial resource allocation decisions. This research is a subtask of the risk management task of the Hanford Mission Plan as described in the WHC Integrated Planning Work Breakdown Structure 1.8.2 Fiscal Year 1994 Work Plan. The research team investigated prioritization techniques used at other DOE sites and compared them with the Priority Planning Grid (PPG), a tool used at Hanford. The authors concluded that the PPG could be used for prioritization of resource allocation, but it needed to be revised to better reflect the Site`s priorities and objectives. The revised PPG was tested with three Hanford programs, the PPG was modified, and updated procedures were prepared.

Hesser, W.A.; Madden, M.S.; Pyron, N.M. [Pacific Northwest Lab., Richland, WA (United States); Butcher, J.L. [Westinghouse Hanford Co., Richland, WA (United States)

1994-08-01T23:59:59.000Z

91

Oak Ridge Reservation Waste Management Plan  

Science Conference Proceedings (OSTI)

This report presents the waste management plan for the Oak Ridge Reservation facilities. The primary purpose is to convey what facilities are being used to manage wastes, what forces are acting to change current waste management systems, and what plans are in store for the coming fiscal year.

Turner, J.W. [ed.

1995-02-01T23:59:59.000Z

92

Oak Ridge National Laboratory Waste Management Plan  

Science Conference Proceedings (OSTI)

The objective of the Oak Ridge National Laboratory Waste Management Plan is to compile and to consolidate information annually on how the ORNL Waste Management Program is conducted, which waste management facilities are being used to manage wastes, what forces are acting to change current waste management systems, what activities are planned for the forthcoming fiscal year (FY), and how all of the activities are documented.

Not Available

1992-12-01T23:59:59.000Z

93

Risk And Risk Management In Geothermal Exploration And Development...  

Open Energy Info (EERE)

Up Search Page Edit with form History Facebook icon Twitter icon Risk And Risk Management In Geothermal Exploration And Development Jump to: navigation, search GEOTHERMAL...

94

Emergency Management: Facility Emergency Plan Template  

NLE Websites -- All DOE Office Websites (Extended Search)

by Todd Slater 20 Jun 2007 (updated AUG. 2010) SLAC-I-730-0A14J-001-R001 2 of 12 Emergency Management: Facility Emergency Plan Template This facility emergency plan (FEP)...

95

Emergency Management: Facility Emergency Plan Template  

NLE Websites -- All DOE Office Websites (Extended Search)

Approved by 20 Jun 2007 (updated AUG. 2010) SLAC-I-730-0A14J-001-R001 2 of 12 Emergency Management: Facility Emergency Plan Template This facility emergency plan (FEP)...

96

Planning and Management Consultants, Limited (PMCL) Task Order # 62: Assessment and Incorporation of Risk Management Principles into USACE Civil Works Infrastructure  

E-Print Network (OSTI)

The project summarized in this report had two objectives. The first objective was to develop and test a valid and viable methodology that could be used by the USACE to prioritize Operations and Maintenance (O&M) general funding between civil infrastructure protection and ongoing maintenance funds. Various multi attribute decision modeling and analysis methodologies were studied and a method based on the Analytic Hierarchy Process (AHP) as implemented in the software tool Expert Choice was proposed for use in a USACE case study. The second objective was to demonstrate the prioritization model in a case study. The North West Division (NWD) was chosen as geographical domain for testing this integrated prioritization methodology and nine USACE project sites on the Columbia/Snake River system were selected as the test bed. This case study required the prioritization of several security work packages and hundreds of operations and maintenance work packages. The case study demonstrated that security related O&M work packages may be integrated into the O&M budget using a structured prioritization method. The AHP based multi-attribute Decision Model constructed for this demonstration project was a four level hierarchy designed to reflect the USACE strategy of managing by business lines. The top Level (Level 1) states the USACE O&M goal, to maintain the design benefits of USACE projects by meeting

Gregory Shaw D. Sc

2005-01-01T23:59:59.000Z

97

Tank waste remediation system configuration management plan  

SciTech Connect

The configuration management program for the Tank Waste Remediation System (TWRS) Project Mission supports management of the project baseline by providing the mechanisms to identify, document, and control the functional and physical characteristics of the products. This document is one of the tools used to develop and control the mission and work. It is an integrated approach for control of technical, cost, schedule, and administrative information necessary to manage the configurations for the TWRS Project Mission. Configuration management focuses on five principal activities: configuration management system management, configuration identification, configuration status accounting, change control, and configuration management assessments. TWRS Project personnel must execute work in a controlled fashion. Work must be performed by verbatim use of authorized and released technical information and documentation. Application of configuration management will be consistently applied across all TWRS Project activities and assessed accordingly. The Project Hanford Management Contract (PHMC) configuration management requirements are prescribed in HNF-MP-013, Configuration Management Plan (FDH 1997a). This TWRS Configuration Management Plan (CMP) implements those requirements and supersedes the Tank Waste Remediation System Configuration Management Program Plan described in Vann, 1996. HNF-SD-WM-CM-014, Tank Waste Remediation System Configuration Management Implementation Plan (Vann, 1997) will be revised to implement the requirements of this plan. This plan provides the responsibilities, actions and tools necessary to implement the requirements as defined in the above referenced documents.

Vann, J.M.

1998-01-08T23:59:59.000Z

98

New Approaches to Managing Transmission Project Risk  

Science Conference Proceedings (OSTI)

This report discusses the growing risks associated with transmission development and the importance of managing or hedging these risks. It presents case studies to illustrate the risks and categorizes approaches to managing them. It describes two EPRI tools that may be useful in managing transmission development risks, suggests how these tools might be further developed, and identifies other useful areas of research.

2006-11-15T23:59:59.000Z

99

2011-2015 Human Capital Management Plan  

Energy.gov (U.S. Department of Energy (DOE))

The Office of Legacy Management (LM) needs skilled and engaged staff to accomplish our mission and carry out our responsibilities to the American people. This Human Capital Management Plan (HCMP or...

100

PROJECT MANGEMENT PLAN EXAMPLES Project Management Plan Examples  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Management Plan Examples Management Plan Examples The following material has been extracted from several project management plans. The order in which it is presented is arbitrary. The elements table below should be used to navigate to the subject of interest. Elements of Deactivation Project Planning Deactivation Project Key Planning Elements Reference DOE O 430.1A Reference DOE G 430.1-3 DOE G 430.1- 3 Fig. 1 Link to Examples Policy & Operational Decisions, Assumptions and Strategies Includes organizational responsibilities and structure, disposition path, future use of facility, S&S Reqs and plan, hazard elimination or mitigation, NEPA, RCRA, CERCLA, HVAC/lighting service reqs, structural integrity reqs, etc. Sect. 6.e.7.a Sect. 4.1.1 Step 1 1. Example 1

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


101

Managing price risk in a multimarket environment  

E-Print Network (OSTI)

AbstractIn a competitive electricity market, a generation company (Genco) can manage its trading risk through trading electricity among multiple markets such as spot markets and contract markets. The question is how to decide the trading proportion of each market in order to maximize the Gencos profit and minimize the associated risk. Based on the mean-variance portfolio theory, this paper proposes a sequential optimization approach to electric energy allocation between spot and contract markets, taking into consideration the risks of electricity price, congestion charge, and fuel price. Especially, the impact of the fuel market on electric energy allocation is analyzed and simulated with historical data in respect of the electricity market and other fuel markets in the U.S. Simulation results confirm that the proposed analytic approach is consistent with intuition and therefore reasonable and feasible for a Genco to make a trading plan involving risks in an electricity market. Index TermsElectricity market, mean-variance portfolio theory, risk management, utility theory. I.

Min Liu; Felix F. Wu

2006-01-01T23:59:59.000Z

102

Integrated Substation Equipment Risk and Performance Assessment Tool for Asset Management and Smart Grid Implementation  

Science Conference Proceedings (OSTI)

Risk assessment and risk management are key elements in any well-developed asset management plan, and an increasing number of utility managers are devoting resources to improving their ability to understand and make risk-based decisions. Consequently, there is growing interest in the tools and methodologies required to better assess equipment performance and risk and provide quantitative information to drive asset management decision processes. In addition, risk and performance assessment tools can be in...

2009-12-23T23:59:59.000Z

103

Risk communications and the Chemical Stockpile Emergency-Planning Program  

Science Conference Proceedings (OSTI)

The CSEPP (Chemical Stockpile Emergency Preparedness Program) was created to improve emergency planning and response capabilities at the eight sites around the country that store chemical weapons. These weapons are scheduled to be destroyed in the near future. In preparation of the Draft Programmatic Environmental Impact Statement (DPEIS) for the Chemical Stockpile Disposal Program (CSDP), it was proposed that the Army mitigate accidents through an enhanced community emergency preparedness program at the eight storage sites. In 1986, the Army initiated the development of an Emergency Response Concept Plan (ERCP) for the CSDP, one of 12 technical support studies conducted during preparation of the Final Programmatic Environmental Impact Statement (FPEIS). The purpose of this document is to provide a fairly comprehensive source book on risk, risk management, risk communication research and recommended risk communication practices. It does not merely summarize each publication in the risk communication literature, but attempts to synthesize them along the lines of a set of organizing principles. Furthermore, it is not intended to duplicate other guidance manuals (such as Covello et al.`s manual on risk comparison). The source book was developed for the CSEPP in support of the training module on risk communications. Although the examples provided are specific to CSEPP, its use goes beyond that of CSEPP as the findings apply to a broad spectrum of risk communication topics. While the emphasis is on communication in emergency preparedness and response specific to the CSEPP, the materials cover other non-emergency communication settings. 329 refs.

Vogt, B.M.; Sorensen, J.H.

1994-09-01T23:59:59.000Z

104

Environmental Restoration Information Resource Management Program Plan  

SciTech Connect

The Environmental Restoration Information Resources Management (ER IRM) Program Plan defines program requirements, organizational structures and responsibilities, and work breakdown structure and to establish an approved baseline against which overall progress of the program as well as the effectiveness of its management will be measured. This plan will guide ER IRM Program execution and define the program`s essential elements. This plan will be routinely updated to incorporate key decisions and programmatic changes and will serve as the project baseline document. Environmental Restoration Waste Management Program intersite procedures and work instructions will be developed to facilitate the implementation of this plan.

Not Available

1994-09-01T23:59:59.000Z

105

Plan for a Nuclear Power Industry Life Cycle Management and Nuclear Asset Management Database  

Science Conference Proceedings (OSTI)

The database development plan in this report is the first phase of providing plants with a useful computerized compendium of existing worldwide equipment reliability, aging, and other life cycle management (LCM) and nuclear asset management (NAM) data for risk-based nuclear asset and project evaluation.

2003-05-30T23:59:59.000Z

106

Environmental Restoration Program Records Management Plan  

SciTech Connect

This document describes the plans, organization, and control systems to be used for management of the Hanford Site Environmental Restoration (ER) Program. The Field Office Management Plan (FOMP), in conjunction with the Environmental Restoration Program Quality Assurance System Requireme ts for the Hanford Site (QASR [DOE-RL 1992a]), provides requirements governing ER Program work activities on the Hanford Site. The FOMP requires a records management plan be written. The Westinghouse Hanford Company (WHC) ER Program Office has developed this ER Program Records Management Plan to fulfill the requirements of the FOMP (DOE-RL 1989). This records management plan will enable the ER Program Office and other ER Program participants to identify, control, and maintain the records generated and used in support of the ER Program.

Montgomery, L.M.

1992-12-01T23:59:59.000Z

107

Project Management Plan (PMP) for Work Management Implementation  

SciTech Connect

The purpose of this document is to provide a project plan for Work Management Implementation by the River Protection Project (RPP). Work Management is an information initiative to implement industry best practices by replacing some Tank Farm legacy system

SHIPLER, C.E.

2000-01-13T23:59:59.000Z

108

High performance in Procurement Risk Management  

E-Print Network (OSTI)

Research on Procurement Risk Management has been conducted by Accenture and MIT in order to identify the best practices used to manage commodity price volatility and supplier risk. In today's increasingly turbulent market ...

Olsha, Maya (Olsha-Yehiav)

2010-01-01T23:59:59.000Z

109

Systems Engineering Management Plan. Volume 5 of the MRS Project Management Plan  

SciTech Connect

The purpose of this Monitored Retrievable Storage (MRS) Project Systems Engineering Management Plan (SEMP) is to define and establish the MRS Project Systems Engineering process that implements the approved policy and requirements of the Office of Civilian Radioactive Waste Management (OCRWM) for the US Department of Energy (DOE). This plan is Volume 5 of the MRS Project Management Plan (PMP). This plan provides the framework for implementation of systems engineering on the MRS Project consistent with DOE Order 4700.1, the OCRWM Program Management System Manual (PMSM), and the OCRWM Systems Engineering Management Plan (SEMP).

1994-01-01T23:59:59.000Z

110

ELECTRICITY SUBSECTOR CYBERSECURITY RISK MANAGEMENT PROCESS  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

complementary to and should be used as part of a more comprehensive enterprise risk management program. i | contents 1. INTRODUCTION ......

111

MA - Office of Management - Energy Conservation Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

MA Energy Conservation Plan MA Energy Conservation Plan January 2010 1 Office of Management Office-Level Energy Conservation Plan January 2010 I. BACKGROUND This energy conservation plan represents an effort to reduce energy consumption within Office of Management (MA) office spaces and to increase employee awareness of and participation in energy conservation measures. II. SCOPE The plan and procedures in this document apply to all Office of Management (MA) office suites in the Forrestal and Germantown Facilities as well as the 950 L'Enfant Plaza Building. The actions and procedures set forth in this plan apply to each separate MA office suite as follows: MA-1: 4A-107 MA-43: 1F-039 MA-70: 7E-074 MA-1.1: 7E-028 MA-43: 1F-037 MA-70: 7E-054 MA-30: GH-081 MA-43:

112

ARM - Data Management and Documentation Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

DocumentationData Management and Documentation Plan DocumentationData Management and Documentation Plan Policies, Plans, Descriptions Data Documentation Home Data Sharing and Distribution Policy Data Management and Documentation Plan Data Product Registration and Submission Reading netCDF and HDF Data Files Time in ARM netCDF Data Files Data Archive Documentation ARM Archive's Catalog of Data Streams (Updated monthly) Access to Historical ARM Data More on Understanding and Finding ARM Data Data Quality Problem Reporting Data Management and Documentation Plan Purpose This document describes datastream documentation requirements and standard formatting and naming protocols for both data users and the infrastructure who produce the data. Definitions Baseline Change Request (BCR): Used by the ARM Infrastructure as a process to provide configuration

113

Configuration Management Plan for K Basins  

SciTech Connect

This plan describes a configuration management program for K Basins that establishes the systems, processes, and responsibilities necessary for implementation. The K Basins configuration management plan provides the methodology to establish, upgrade, reconstitute, and maintain the technical consistency among the requirements, physical configuration, and documentation. The technical consistency afforded by this plan ensures accurate technical information necessary to achieve the mission objectives that provide for the safe, economic, and environmentally sound management of K Basins and the stored material. The configuration management program architecture presented in this plan is based on the functional model established in the DOE Standard, DOE-STD-1073-93, {open_quotes}Guide for Operational Configuration Management Program{close_quotes}.

Weir, W.R.; Laney, T.

1995-01-27T23:59:59.000Z

114

Integrated Safety Management (ISM) - Work Planning and Control  

NLE Websites -- All DOE Office Websites (Extended Search)

Work Planning and Control Integrated Safety Management (ISM) ism logo NNSA Activity Level Work Planning & Control Processes - January 2006...

115

Collateral Risk Analytics for Energy Trading and Portfolio Risk Management  

Science Conference Proceedings (OSTI)

This report describes the need for a strong collateral risk management function as an integral part of an energy companys risk management program. It reviews the basics of margining and collateral both in over-the-counter markets and on exchanges. In addition, it details the technology available to measure collateral risk properly. Then it reviews the recent efforts to regulate OTC derivatives, the potential impact that it could have on energy companies management of cash collateral, and strategies tha...

2010-12-21T23:59:59.000Z

116

India-Natural Resource Management Plan | Open Energy Information  

Open Energy Info (EERE)

Natural Resource Management Plan Jump to: navigation, search Name India-Natural Resource Management Plan AgencyCompany Organization Government of India Sector Land Focus Area...

117

2013 Annual Planning Summary for the Environmental Management...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

3 Annual Planning Summary for the Environmental Management Consolidated Business Center 2013 Annual Planning Summary for the Environmental Management Consolidated Business Center...

118

Real Property Asset Management Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Real Property Asset Management Plan Real Property Asset Management Plan coverbooked.indd More Documents & Publications coverbooked.indd coverbooked.indd Tribal Summit Book.indd...

119

Buried waste integrated demonstration configuration management plan  

SciTech Connect

This document defines plans for the configuration management requirements for the Buried Waste Integrated Demonstration (BWID) Program. Since BWID is managed programmatically by the Waste Technology Development Department (WTDD), WTDD Program Directive (PD) 1.5 (Document Preparation, Review, Approval, Publication, Management and Change Control) is to be followed for all internal EG&G Idaho, Inc., BWID programmatic documentation. BWID documentation generated by organizations external to EG&G Idaho is not covered by this revision of the Configuration Management Plan (CMP), but will be addressed in subsequent revisions.

Cannon, P.G.

1992-02-01T23:59:59.000Z

120

Buried waste integrated demonstration configuration management plan  

SciTech Connect

This document defines plans for the configuration management requirements for the Buried Waste Integrated Demonstration (BWID) Program. Since BWID is managed programmatically by the Waste Technology Development Department (WTDD), WTDD Program Directive (PD) 1.5 (Document Preparation, Review, Approval, Publication, Management and Change Control) is to be followed for all internal EG G Idaho, Inc., BWID programmatic documentation. BWID documentation generated by organizations external to EG G Idaho is not covered by this revision of the Configuration Management Plan (CMP), but will be addressed in subsequent revisions.

Cannon, P.G.

1992-02-01T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


121

Risk Assessment and Risk Management/Mitigation  

Science Conference Proceedings (OSTI)

... Emergency Management Agency FEMP Federal Energy ... defines key terms, designates guidelines, and ... the many software products developed by ...

2007-10-03T23:59:59.000Z

122

Draft of the PHENIX Management Plan  

SciTech Connect

The PHENIX Management Plan provides the baselines and controls that the PHENIX and RHIC Projects will follow to meet the technical, cost, and schedule goals for the PHENIX detector at RHIC. This plan will be reviewed and updated as required, with revisions made by agreement among the signed participants.

Not Available

1994-03-10T23:59:59.000Z

123

2011-2015 Human Capital Management Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

The Office of Legacy Management (LM) needs skilled and engaged staff to accomplish our mission and The Office of Legacy Management (LM) needs skilled and engaged staff to accomplish our mission and carry out our responsibilities to the American people. This (HCMP or Plan) shows how we intend to recruit, hire, train, develop, and retain such employees. Our differs from previous versions not only in enhanced visual appeal (including photos of LM staff and sites) but also in showing direct links between our objectives, strategies, and activities and the human capital issues most important to President Obama's Administration, the Department, and our own management and staff. We thank the LM Management Team and other staff who contributed to and commented on this plan. We all know that for the LM HCMP to succeed we must continually evaluate our progress and adjust our plan

124

Emergency Management: Facility Emergency Plan Template  

NLE Websites -- All DOE Office Websites (Extended Search)

Laboratory Laboratory Building 219, 274 and 278 SSRL Building Facility Emergency Plan In Case of Emergency 9-911 from a SLAC phone 911 from a non-SLAC phone Then notify SLAC Site Security, Ext. 5555 SLAC Emergency Resources SLAC Site Security 5555 On-site Palo Alto Fire Station Number 7 2776 Conventional and Experimental Facilities 8901 Normal working hours only SLAC Medical Department 2281 Waste Management 2399 Building manager Larry Cadapan Assistant building manager Brian Choi Publication date 02/11/2009 Revision date 02/11/2009 Prepared by Behzad Bozorg-Chami Approved by Larry Cadapan 20 Jun 2007 (updated 30 Jun 2007) SLAC-I-730-0A14J-001-R000 2 of 12 Emergency Management: Facility Emergency Plan Template This facility emergency plan (FEP) contains building-specific emergency information for

125

DOE Releases Electricity Subsector Cybersecurity Risk Management...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

that help them manage their cybersecurity risks more effectively." Feedback provided by industry, vendors, and other electricity subsector stakeholders during two comment periods...

126

Risk-Informed Asset Management (RIAM): Method, Process, and Business Requirements  

Science Conference Proceedings (OSTI)

Risk-informed asset management (RIAM) is a composite financial/engineering method that uses risk management technology to support equipment long-term planning and investment decisions at the corporate, fleet, plant, system, or equipment levels of nuclear power enterprises. It gives decision makers improved quantitative information regarding investments in asset management at the levels of individual projects and a portfolio of projects. In a manner similar to use of probabilistic risk assessment and risk...

2005-05-09T23:59:59.000Z

127

Supporting Community Emergency Management Planning through a Geocollaboration Software Architecture  

Science Conference Proceedings (OSTI)

Emergency management is more than just events occurring within an emergency situation. It encompasses a variety of persistent activities such as planning, training, assessment, and organizational change. We are studying emergency management planning ... Keywords: collaboration architecture, emergency planning, software design

Wendy A. Schafer; Craig H. Ganoe; John M. Carroll

2007-10-01T23:59:59.000Z

128

2013 Annual Planning Summary for the Office of Legacy Management...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

3 Annual Planning Summary for the Office of Legacy Management 2013 Annual Planning Summary for the Office of Legacy Management 2013 Annual Planning Summary for the Office of Legacy...

129

Ground water protection management program plan  

SciTech Connect

U.S. Department of Energy (DOE) Order 5400.1 requires the establishment of a ground water protection management program to ensure compliance with DOE requirements and applicable federal, state, and local laws and regulations. The Uranium Mill Tailings Remedial Action (UMTRA) Project Office was prepared this Ground Water Protection Management Program Plan (ground water protection plan) whose scope and detail reflect the program`s significance and address the seven activities required in DOE Order 5400.1, Chapter III, for special program planning. This ground water protection plan highlights the methods designed to preserve, protect, and monitor ground water resources at UMTRA Project processing and disposal sites. The plan includes an overview of the remedial action status at the 24 designated processing sites and identifies technical guidance documents and site-specific documents for the UMTRA Project ground water protection management program. In addition, the plan addresses the general information required to develop a water resources protection strategy at the permanent disposal sites. Finally, the plan describes ongoing activities that are in various stages of development at UMTRA Project sites.

Not Available

1994-02-01T23:59:59.000Z

130

Material stabilization characterization management plan  

SciTech Connect

This document presents overall direction for characterization needs during stabilization of SNM at the Plutonium Finishing Plant (PFP). Technical issues for needed data and equipment are identified. Information on material categories and links to vulnerabilities are given. Comparison data on the material categories is discussed to assist in assessing the relative risks and desired processing priority.

GIBSON, M.W.

1999-08-31T23:59:59.000Z

131

Microsoft Word - ContractManagementPlanningDRIVERS.doc  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Drivers for Ineffective and Effective Drivers for Ineffective and Effective Contract Management and Planning Ineffective Contract Management and Planning Effective Contract Management and Planning 1. Top management does not demonstrate a commitment to contract management planning. 2. Contract team members not clear on contract requirements. 3. Contract team members left out of planning process. 4. Lack of coordination and communication amongst the team members. 5. Contract team members not sure of roles, responsibilities, and limitations. 6. Contract team members not clear on how their responsibilities relate, or interact with, other team members. 1. Top management actively demonstrates a commitment to the contract management planning process. 2. Top management mandates training for the

132

Hanford cultural resources management plan  

Science Conference Proceedings (OSTI)

As a federal agency, the US Department of Energy (DOE) has been directed by Congress and the President to provide leadership in the preservation of prehistoric, historical, and cultural resources on lands it administers, to manage these in a spirit of stewardship for future generations, and to protect and preserve the rights of Native Americans to religious freedom. The purpose of this document is to describe how the DOE-Richland Operations (DOE-RL) will meet those responsibilities on the Hanford Site, pursuant to guidelines for Agency Responsibilities under the Historic Preservation Act (FR 53:31, February 17, 1988). This document is intended for multiple uses. Among other things, the text is designed as a manual for cultural resource managers to follow and as an explanation of the process of cultural resource regulatory compliance for the DOE-RL and Site contractors. 10 refs., 17 figs., 11 tabs.

Chatters, J.C. (ed.)

1989-06-01T23:59:59.000Z

133

Federal Energy Management Program: Renewable Energy Project Planning and  

NLE Websites -- All DOE Office Websites (Extended Search)

Renewable Energy Renewable Energy Project Planning and Implementation to someone by E-mail Share Federal Energy Management Program: Renewable Energy Project Planning and Implementation on Facebook Tweet about Federal Energy Management Program: Renewable Energy Project Planning and Implementation on Twitter Bookmark Federal Energy Management Program: Renewable Energy Project Planning and Implementation on Google Bookmark Federal Energy Management Program: Renewable Energy Project Planning and Implementation on Delicious Rank Federal Energy Management Program: Renewable Energy Project Planning and Implementation on Digg Find More places to share Federal Energy Management Program: Renewable Energy Project Planning and Implementation on AddThis.com... Energy-Efficient Products

134

Hanford emergency management plan - release 15  

SciTech Connect

The Hanford emergency management plan for the US Department of Energy Richland, WA and Office of River Protection. The program was developed in accordance with DOE Orders as well as Federal and State regulations to protect workers and public health and safety.

CARPENTER, G.A.

1999-07-19T23:59:59.000Z

135

Feed Materials Production Center Waste Management Plan  

SciTech Connect

In the process of producing uranium metal products used in Department of Energy (DOE) defense programs at other DOE facilities, various types of wastes are generated at the Feed Materials Production Center (FMPC). Process wastes, both generated and stored, are discussed in the Waste Management Plan and include low-level radioactive waste (LLW), mixed hazardous/radioactive waste, and sanitary/industrial waste. Scrap metal waste and wastes requiring special remediation are also addressed in the Plan. The Waste Management Plan identifies the comprehensive programs developed to address safe storage and disposition of all wastes from past, present, and future operations at the FMPC. Waste streams discussed in this Plan are representative of the waste generated and waste types that concern worker and public health and safety. Budgets and schedules for implementation of waste disposition are also addressed. The waste streams receiving the largest amount of funding include LLW approved for shipment by DOE/ORO to the Nevada Test Site (NTS) (MgF/sub 2/, slag leach filter cake, and neutralized raffinate); remedial action wastes (waste pits, K-65 silo waste); thorium; scrap metal (contaminated and noncontaminated ferrous and copper scrap); construction rubble and soil generated from decontamination and decommissioning of outdated facilities; and low-level wastes that will be handled through the Low-Level Waste Processing and Shipping System (LLWPSS). Waste Management milestones are also provided. The Waste Management Plan is divided into eight major sections: Introduction; Site Waste and Waste Generating Process; Strategy; Projects and Operations; Waste Stream Budgets; Milestones; Quality Assurance for Waste Management; and Environmental Monitoring Program.

Watts, R.E.; Allen, T.; Castle, S.A.; Hopper, J.P.; Oelrich, R.L.

1986-12-31T23:59:59.000Z

136

Ocean Thermal Energy Conversion Program Management Plan  

DOE Green Energy (OSTI)

The Office of the Associate Laboratory Director for Energy and Environmental Technology has established the OTEC Program Management Office to be responsible for the ANL-assigned tasks of the OTEC Program under DOE's Chicago Operations and Regional Office (DOE/CORO). The ANL OTEC Program Management Plan is essentially a management-by-objective plan. The principal objective of the program is to provide lead technical support to CORO in its capacity as manager of the DOE power-system program. The Argonne OTEC Program is divided into three components: the first deals with development of heat exchangers and other components of OTEC power systems, the second with development of biofouling counter-measures and corrosion-resistant materials for these components in seawater service, and the third with environmental and climatic impacts of OTEC power-system operation. The essential points of the Management Plan are summarized, and the OTEC Program is described. The organization of the OTEC Program at ANL is described including the functions, responsibilities, and authorities of the organizational groupings. The system and policies necessary for the support and control functions within the organization are discussed. These functions cross organizational lines, in that they are common to all of the organization groups. Also included are requirements for internal and external reports.

Combs, R E

1980-01-01T23:59:59.000Z

137

Federal Energy Management Program: Advanced Technology Planning for Energy  

NLE Websites -- All DOE Office Websites (Extended Search)

Advanced Advanced Technology Planning for Energy Savings Performance Contracts to someone by E-mail Share Federal Energy Management Program: Advanced Technology Planning for Energy Savings Performance Contracts on Facebook Tweet about Federal Energy Management Program: Advanced Technology Planning for Energy Savings Performance Contracts on Twitter Bookmark Federal Energy Management Program: Advanced Technology Planning for Energy Savings Performance Contracts on Google Bookmark Federal Energy Management Program: Advanced Technology Planning for Energy Savings Performance Contracts on Delicious Rank Federal Energy Management Program: Advanced Technology Planning for Energy Savings Performance Contracts on Digg Find More places to share Federal Energy Management Program:

138

Nevada Test Site Resource Management Plan  

SciTech Connect

The Nevada Test Site (NTS) Resource Management Plan (RMP) describes the NTS Stewardship Mission and how its accomplishment will preserve the resources of the ecoregion while accomplishing the objectives of the mission. The NTS Stewardship Mission is to manage the land and facilities at the NTS as a unique and valuable national resource. The RMP has defined goals for twelve resource areas based on the principles of ecosystem management. These goals were established using an interdisciplinary team of DOE/NV resource specialists with input from surrounding land managers, private parties, and representatives of Native American governments. The overall goal of the RMP is to facilitate improved NTS land use management decisions within the Great Basin and Mojave Desert ecoregions.

NONE

1998-12-01T23:59:59.000Z

139

Independent Verification and Validation Of SAPHIRE 8 Risk Management Project Number: N6423 U.S. Nuclear Regulatory Commission  

Science Conference Proceedings (OSTI)

This report provides an evaluation of the risk management. Risk management is intended to ensure a methodology for conducting risk management planning, identification, analysis, responses, and monitoring and control activities associated with the SAPHIRE project work, and to meet the contractual commitments prepared by the sponsor; the Nuclear Regulatory Commission.

Kent Norris

2009-11-01T23:59:59.000Z

140

Tank Waste Remediation Systems (TWRS) Configuration Management Implementation Plan  

SciTech Connect

The Tank Waste Configuration Management (TWRS) Configuration Management Implementation Plan descibes the execution of the configuration management (CM) that the contractor uses to manage and integrate its programmatic and functional operations to perform work.

WEIR, W.R.

2000-12-18T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


141

Essays in banking and risk management  

E-Print Network (OSTI)

(cont.) Risk Management have begun implementing strategies to provide commodity price and weather insurance in the developing world. In Chapter 3 (joint with Professor Rob Townsend from the University of Chicago), we examine ...

Vickery, James Ian, 1974-

2004-01-01T23:59:59.000Z

142

Managing Energy Price Risk with Derivatives  

NLE Websites -- All DOE Office Websites (Extended Search)

Managing Energy Price Risk with Derivatives Managing Energy Price Risk with Derivatives Speaker(s): Douglas Hale Date: September 18, 2003 - 12:00pm Location: Bldg. 90 Seminar Host/Point of Contact: Joseph Eto Energy derivatives came into being with the deregulation of the petroleum and natural gas industries in the early 1980s. Although derivatives-forwards, futures and options-have been used in American agriculture since the mid-1800's to manage price risk, they were unnecessary in regulated energy industries. Deregulation revealed that oil, gas and electricity prices are exceptionally volatile. Companies were forced to cope with the uncertainty in energy prices; they latched onto derivatives as one tool for managing that risk. Enron's collapse brought energy derivatives to public attention. Following the derivative linked

143

DataONE Example NSF Data Management Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

DataONE Example NSF Data Management Plan www.dataone.org Example Data Management Plan, based on the work of C.D. Keeling and Colleagues, Scripps Institution of Oceanography...

144

First Capitol Risk Management LLC | Open Energy Information  

Open Energy Info (EERE)

Search Page Edit with form History Facebook icon Twitter icon First Capitol Risk Management LLC Jump to: navigation, search Name First Capitol Risk Management, LLC Place...

145

Risk Management II Summit Agenda | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Risk Management II Summit Agenda Risk Management Summit Agenda.pdf More Documents & Publications Spectrum Technology Workshop Tech Transfer Summit Agenda July 19, 2012 SEAB Agenda...

146

New Draft of Cybersecurity Risk Management Process (RMP) Guideline...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Draft of Cybersecurity Risk Management Process (RMP) Guideline Now Available for Public Comment (March 2012) New Draft of Cybersecurity Risk Management Process (RMP) Guideline Now...

147

"Insurance as a Risk Management Instrument for Energy Infrastructure...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

"Insurance as a Risk Management Instrument for Energy Infrastructure Security and Resilience" Report Now Available "Insurance as a Risk Management Instrument for Energy...

148

Strategic plan for Hanford site information management  

SciTech Connect

The Hanford Site missions are to clean up the Site, to provide scientific knowledge and technology to meet global needs, and to partner in the economic diversification of the region. To achieve these long-term missions and increase confidence in the quality of the Site`s decision making process, a dramatically different information management culture is required, consistent with US Department of Energy (DOE) mandates on increased safety, productivity, and openness at its sites. This plan presents a vision and six strategies that will move the Site toward an information management culture that will support the Site missions and address the mandates of DOE.

1994-09-01T23:59:59.000Z

149

LFRG Program Management Plan (LFRG PMP)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

LOW-LEVEL WASTE DISPOSAL FACILITY LOW-LEVEL WASTE DISPOSAL FACILITY FEDERAL REVIEW GROUP PROGRAM MANAGEMENT PLAN SEPTEMBER 18, 2000 LOW-LEVEL WASTE DISPOSAL FACILITY FEDERAL REVIEW GROUP PROGRAM MANAGEMENT PLAN Jay Rhoderick, Co-Chair William E. Murphie, Co-Chair LFRG Members Joel Case, Idaho Operations Office Frank DiSanza, Nevada Operations Office Doug Hildebrand, Richland Operations Office Randy Janke, Ohio Field Office Bill McMillan, Oak Ridge Operations Office Virgil Sauls, Savannah River Operations Office Jim Orban, Albuquerque Operations Office Andy Wallo, Office of Environment, Safety and Health DOE Headquarters Distribution: David M. Michaels, Assistant Secretary for Environment, Safety and Health, EH-1 Madelyn Creedon, Deputy Administrator for Defense Programs, DP-1 Rose E. Gottemoeller, Deputy Administrator for Defense Nuclear Nonproliferation, NN-1

150

Risk-Managed Technical Specifications (RMTS) Guidelines  

Science Conference Proceedings (OSTI)

The Electric Power Research Institute (EPRI) has assessed the role of probabilistic risk assessment (PRA) in the regulation of nuclear power station Technical Specifications. This report presents nuclear utilities with a framework and associated general guidance for implementing Risk-Managed Technical Specifications (RMTS) as a partial replacement for existing Technical Specifications. This report was prepared for EPRI with extensive technical input and review by the Nuclear Energy Institute (NEI) Risk-I...

2006-12-01T23:59:59.000Z

151

Risk-Managed Technical Specifications (RMTS) Guidelines  

Science Conference Proceedings (OSTI)

EPRI has assessed the role of probabilistic risk assessment (PRA) in the regulation of nuclear power plant technical specifications. This report presents nuclear utilities with a framework and associated general guidance for implementing risk managed technical specifications (RMTS) as a partial replacement of existing technical specifications. This report was prepared for EPRI with extensive technical input and review by the Nuclear Energy Institute (NEI) Risk-Informed Technical Specifications Task Force...

2005-12-01T23:59:59.000Z

152

River Protection Project (RPP) Project Management Plan  

SciTech Connect

The Office of River Protection (ORP) Project Management Plan (PMP) for the River Protection Project (RPP) describes the process for developing and operating a Waste Treatment Complex (WTC) to clean up Hanford Site tank waste. The Plan describes the scope of the project, the institutional setting within which the project must be completed, and the management processes and structure planned for implementation. The Plan is written from the perspective of the ORP as the taxpayers' representative. The Hanford Site, in southeastern Washington State, has one of the largest concentrations of radioactive waste in the world, as a result of producing plutonium for national defense for more than 40 years. Approximately 53 million gallons of waste stored in 177 aging underground tanks represent major environmental, social, and political challenges for the U.S. Department of Energy (DOE). These challenges require numerous interfaces with state and federal environmental officials, Tribal Nations, stakeholders, Congress, and the US Department of Energy-Headquarters (DOE-HQ). The cleanup of the Site's tank waste is a national issue with the potential for environmental and economic impacts to the region and the nation.

NAVARRO, J.E.

2001-03-07T23:59:59.000Z

153

42pt5ContractManagementPlanning.pdf | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

ContractManagementPlanning.pdf More Documents & Publications Contract Management Plan Outline Chapter 16 - Types of Contracts Microsoft Word - ContractManagementPlanningDRIVERS.doc...

154

WIPP Facility Work Plan for Solid Waste Management Units  

Science Conference Proceedings (OSTI)

This Facility Work Plan (FWP) has been prepared as required by Module VII,Section VII.M.1 of the Waste Isolation Pilot Plant (WIPP) Hazardous Waste Permit, NM4890139088-TSDF (the Permit); (NMED, 1999a). This work plan describes the programmatic facility-wide approach to future investigations at Solid Waste Management Units (SWMUs) and Areas of Concern (AOCs) specified in the Permit. This FWP addresses the current Permit requirements. It uses the results of previous investigations performed at WIPP and expands the investigations as required by the Permit. As an alternative to the Resource Conservation and Recovery Act (RCRA) Facility Investigation (RFI) specified in Module VII of the Permit, current New Mexico Environment Department (NMED) guidance identifies an Accelerated Corrective Action Approach (ACAA) that may be used for any SWMU or AOC (NMED, 1998). This accelerated approach is used to replace the standard RFI Work Plan and Report sequence with a more flexible decision-making approach. The ACAA process allows a Facility to exit the schedule of compliance contained in the Facilitys Hazardous and Solid Waste Amendments (HSWA) permit module and proceed on an accelerated time frame. Thus, the ACAA process can be entered either before or after an RFI Work Plan. According to NMEDs guidance, a facility can prepare an RFI Work Plan or Sampling and Analysis Plan (SAP) for any SWMU or AOC (NMED, 1998). Based on this guidance, a SAP constitutes an acceptable alternative to the RFI Work Plan specified in the Permit. The scope of work for the RFI Work Plan or SAP is being developed by the Permittees. The final content of the RFI Work Plan or SAP will be coordinated with the NMED for submittal on May 24, 2000. Specific project-related planning information will be included in the RFI Work Plan or SAP. The SWMU program at WIPP began in 1994 under U.S. Environmental Protection Agency (EPA) regulatory authority. NMED subsequently received regulatory authority from EPA. A Phase I RFI was completed at WIPP as part of a Voluntary Release Assessment (VRA). The risk-based decision criteria recommended by EPA for the VRA were contained in a proposed Corrective Action rule for SWMUs (EPA, 1990). EPA Region VI has issued new risk-based screening criteria applicable to the WIPP SWMUs and AOCs.

Washington TRU Solutions LLC

2000-02-25T23:59:59.000Z

155

Excess Uranium Inventory Management Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Excess Uranium Inventory Management Plan Excess Uranium Inventory Management Plan Excess Uranium Inventory Management Plan The 2013 Excess Uranium Inventory Management Plan describes a framework for the effective management of the Energy Department's surplus uranium inventory in support of meeting its critical environmental cleanup and national security missions. The Plan is not a commitment to specific activities beyond those that have already been contracted nor is it a restriction on actions that the Department may undertake in the future as a result of changing conditions. It replaces an earlier plan issued in 2008 and reflects updated information on the Department of Energy's management and disposition of its excess uranium inventories. Excess Uranium Inventory Management Plan More Documents & Publications

156

Emerging M&S application in risk management  

Science Conference Proceedings (OSTI)

There has been compelling signs of the great potential of building further synergy with academics, researchers, and industry practitioners from the areas of Modeling and Simulation (M&S) managing risk events. This paper provides an introduction to risk ... Keywords: engineering management, risk analysis, risk assessment, risk management, systems engineering

C. Ariel Pinto; Andreas Tolk; Michael McShane

2011-04-01T23:59:59.000Z

157

Manhole Event Risk Management Strategies  

Science Conference Proceedings (OSTI)

This report provides a high-level overview of EPRI research into gas-related explosions in structures in underground distribution systems, and various mitigation approaches considered in the past to reduce the risk of damage resulting from an event. The project team tested some of these approaches at the EPRI-Lenox research facility, and the report summarizes the results of these tests. Utilities have also deployed some of the approaches in the field.

2008-12-23T23:59:59.000Z

158

The integrated tank waste management plan at Oak Ridge National Laboratory  

SciTech Connect

DOE`s Environmental Management Program at Oak Ridge has developed an integrated tank waste management plan that combines the accelerated deployment of innovative technologies with an aggressive waste transfer schedule. Oak Ridge is cleaning out waste from aging underground storage tanks in preparation of waste processing, packaging and final safe disposal. During remediation this plan will reduce the risk of environmental, worker, and civilian exposure, save millions of dollars, and cut years off of tank remediation schedules at Oak Ridge.

Billingsley, K. [STEP, Inc., Oak Ridge, TN (United States); Mims, C. [Dept. of Energy, Oak Ridge, TN (United States). Oak Ridge Operations Office; Robinson, S. [Oak Ridge National Lab., TN (United States)

1998-06-01T23:59:59.000Z

159

Environmental restoration risk-based prioritization work package planning and risk ranking methodology. Revision 2  

Science Conference Proceedings (OSTI)

This document presents the risk-based prioritization methodology developed to evaluate and rank Environmental Restoration (ER) work packages at the five US Department of Energy, Oak Ridge Field Office (DOE-ORO) sites [i.e., Oak Ridge K-25 Site (K-25), Portsmouth Gaseous Diffusion Plant (PORTS), Paducah Gaseous Diffusion Plant (PGDP), Oak Ridge National Laboratory (ORNL), and the Oak Ridge Y-12 Plant (Y-12)], the ER Off-site Program, and Central ER. This prioritization methodology was developed to support the increased rigor and formality of work planning in the overall conduct of operations within the DOE-ORO ER Program. Prioritization is conducted as an integral component of the fiscal ER funding cycle to establish program budget priorities. The purpose of the ER risk-based prioritization methodology is to provide ER management with the tools and processes needed to evaluate, compare, prioritize, and justify fiscal budget decisions for a diverse set of remedial action, decontamination and decommissioning, and waste management activities. The methodology provides the ER Program with a framework for (1) organizing information about identified DOE-ORO environmental problems, (2) generating qualitative assessments of the long- and short-term risks posed by DOE-ORO environmental problems, and (3) evaluating the benefits associated with candidate work packages designed to reduce those risks. Prioritization is conducted to rank ER work packages on the basis of the overall value (e.g., risk reduction, stakeholder confidence) each package provides to the ER Program. Application of the methodology yields individual work package ``scores`` and rankings that are used to develop fiscal budget requests. This document presents the technical basis for the decision support tools and process.

Dail, J.L.; Nanstad, L.D.; White, R.K.

1995-06-01T23:59:59.000Z

160

Product development risk management and the role of transparency  

E-Print Network (OSTI)

Risks in product development lead to schedule and cost over-runs and poor product quality. While numerous risk management frameworks have been published and research on specific risk management practices and methods has ...

Olechowski, Alison L. (Alison Louise)

2012-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


161

ELECTRICITY SUBSECTOR CYBERSECURITY RISK MANAGEMENT PROCESS  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

SUBSECTOR CYBERSECURITY SUBSECTOR CYBERSECURITY RISK MANAGEMENT PROCESS U.S. Department of Energy May 2012 DOE/OE-0003 Acknowledgments This electricity subsector cybersecurity Risk Management Process (RMP) guideline was developed by the Department of Energy (DOE), in collaboration with the National Institute of Standards and Technology (NIST) and the North American Electric Reliability Corporation (NERC). Members of industry and utility-specific trade groups were included in authoring this guidance designed to be meaningful and tailored for the electricity sector. The primary goal of this guideline is to describe an RMP that is tuned to the specific needs of electricity subsector organizations. The NIST Special Publication (SP) 800-39, Managing Information Security Risk, provides the foundational methodology for this document. The NIST Interagency Report

162

Mixed Waste Focus Area program management plan  

SciTech Connect

This plan describes the program management principles and functions to be implemented in the Mixed Waste Focus Area (MWFA). The mission of the MWFA is to provide acceptable technologies that enable implementation of mixed waste treatment systems developed in partnership with end-users, stakeholders, tribal governments and regulators. The MWFA will develop, demonstrate and deliver implementable technologies for treatment of mixed waste within the DOE Complex. Treatment refers to all post waste-generation activities including sampling and analysis, characterization, storage, processing, packaging, transportation and disposal.

Beitel, G.A.

1996-10-01T23:59:59.000Z

163

Federal Energy Management Program: Portfolio-Based Planning Process for  

NLE Websites -- All DOE Office Websites (Extended Search)

Portfolio-Based Portfolio-Based Planning Process for Greenhouse Gas Mitigation to someone by E-mail Share Federal Energy Management Program: Portfolio-Based Planning Process for Greenhouse Gas Mitigation on Facebook Tweet about Federal Energy Management Program: Portfolio-Based Planning Process for Greenhouse Gas Mitigation on Twitter Bookmark Federal Energy Management Program: Portfolio-Based Planning Process for Greenhouse Gas Mitigation on Google Bookmark Federal Energy Management Program: Portfolio-Based Planning Process for Greenhouse Gas Mitigation on Delicious Rank Federal Energy Management Program: Portfolio-Based Planning Process for Greenhouse Gas Mitigation on Digg Find More places to share Federal Energy Management Program: Portfolio-Based Planning Process for Greenhouse Gas Mitigation on

164

Massachusetts Ocean Management Plan (Massachusetts) | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Massachusetts Ocean Management Plan (Massachusetts) Massachusetts Ocean Management Plan (Massachusetts) Massachusetts Ocean Management Plan (Massachusetts) < Back Eligibility Construction Industrial Installer/Contractor Investor-Owned Utility Municipal/Public Utility Rural Electric Cooperative Utility Savings Category Water Buying & Making Electricity Wind Program Info State Massachusetts Program Type Siting and Permitting Provider Executive Office of Energy and Environmental Affairs The Massachusetts Ocean Act of 2008 required the state's Secretary of Energy and Environmental Affairs to develop a comprehensive ocean management plan for the state by the end of 2009. That plan identified certain state waters that are eligible for offshore wind, wave and tidal energy development and other state waters where such development is

165

Life cycle cost and risk estimation of environmental management options  

SciTech Connect

The evaluation process is demonstrated in this paper through comparative analysis of two alternative scenarios identified for the management of the alpha-contaminated fixed low-level waste currently stored at INEL. These two scenarios, the Base Case and the Delay Case, are realistic and based on actual data, but are not intended to exactly match actual plans currently being developed at INEL. Life cycle cost estimates were developed for both scenarios using the System Cost Model; resulting costs are presented and compared. Life cycle costs are shown as a function of time and also aggregated by pretreatment, treatment, storage, and disposal activities. Although there are some short-term cost savings for the Delay Case, cumulative life cycle costs eventually become much higher than costs for the Base Case over the same period of time, due mainly to the storage and repackaging necessary to accommodate the longer Delay Case schedule. Life cycle risk estimates were prepared using a new risk analysis method adapted to the System Cost Model architecture for automated, systematic cost/risk applications. Relative risk summaries are presented for both scenarios as a function of time and also aggregated by pretreatment, treatment, storage, and disposal activities. Relative risk of the Delay Case is shown to be higher than that of the Base Case. Finally, risk and cost results are combined to show how the collective information can be used to help identify opportunities for risk or cost reduction and highlight areas where risk reduction can be achieved most economically.

Shropshire, D.; Sherick, M.

1996-04-01T23:59:59.000Z

166

Arid Lands Ecology Facility management plan  

SciTech Connect

The Arid Lands Ecology (ALE) facility is a 312-sq-km tract of land that lies on the western side of the Hanford Site in southcentral Washington. The US Atomic Energy Commission officially set aside this land area in 1967 to preserve shrub-steppe habitat and vegetation. The ALE facility is managed by Pacific Northwest Laboratory (PNL) for the US Department of Energy (DOE) for ecological research and education purposes. In 1971, the ALE facility was designated the Rattlesnake Hills Research Natural Area (RNA) as a result of an interagency federal cooperative agreement, and remains the largest RNA in Washington. it is also one of the few remaining large tracts of shrub-steppe vegetation in the state retaining a predominant preeuropean settlement character. This management plan provides policy and implementation methods for management of the ALE facilities consistent with both US Department of Energy Headquarters and the Richland Field Office decision (US Congress 1977) to designate and manage ALE lands as an RNA and as a component of the DOE National Environmental Research Park System.

None

1993-02-01T23:59:59.000Z

167

Strategic Energy Management Plan for the 1990's  

E-Print Network (OSTI)

This paper describes the strategic energy management plan implemented by the Defense Systems and Electronics Group (DSEG) of Texas Instruments (TI) to enable it to meet its energy management challenge into the 1990's. The strategic energy management plan is the clear vision of energy management over the long term. It provides the focal point for an effective, integrated energy management program. Its components include a situation analysis; energy requirements and costs; issues, objectives, and strategies; action programs; plan results; and sensitivities and assumptions. Factors critical to its success include a policy statement, realistic goals, interactive planning, and an organizational framework.

Fiorino, D. P.; Priest, J. W.

1987-01-01T23:59:59.000Z

168

Risk management program for the 283-W water treatment facility  

Science Conference Proceedings (OSTI)

This Risk Management (RM) Program covers the 283-W Water Treatment Facility (283W Facility), located in the 200 West Area of the Hanford Site. A RM Program is necessary for this facility because it stores chlorine, a listed substance, in excess of or has the potential to exceed the threshold quantities defined in Title 40 of the Code of Federal Regulations (CFR) Part 68 (EPA, 1998). The RM Program contains data that will be used to prepare a RM Plan, which is required by 40 CFR 68. The RM Plan is a summary of the RM Program information, contained within this document, and will be submitted to the U.S. Environmental Protection Agency (EPA) ultimately for distribution to the public. The RM Plan will be prepared and submitted separately from this document.

GREEN, W.E.

1999-05-11T23:59:59.000Z

169

A Stochastic Processes Toolkit for Risk Management ?  

E-Print Network (OSTI)

In risk management it is desirable to grasp the essential statistical features of a time series representing a risk factor. This tutorial aims to introduce a number of different stochastic processes that can help in grasping the essential features of risk factors describing different asset classes or behaviors. This paper does not aim at being exhaustive, but gives examples and a feeling for practically implementable models allowing for stylised features in the data. The reader may also use these models as building blocks to build more complex models, although for a number of risk management applications the models developed here suffice for the first step in the quantitative analysis. The broad qualitative features addressed here are fat tails and mean reversion. We give some orientation on the initial choice of a suitable stochastic process and then explain how the process parameters can be estimated based on historical data. Once the process has been calibrated, typically through maximum likelihood estimation, one may simulate the risk factor and build future scenarios for the risky portfolio. On the terminal simulated distribution of the portfolio one may then single out several risk measures, although here we focus on the stochastic processes estimation preceding the simulation of the risk factors Finally, this first survey report focuses on single time series. Correlation

Damiano Brigo; Antonio Daless; Matthias Neugebauer; Fares Triki

2007-01-01T23:59:59.000Z

170

HotSpot Software Configuration Management Plan  

SciTech Connect

This Software Configuration Management Plan (SCMP) describes the software configuration management procedures used to ensure that the HotSpot dispersion model meets the requirements of its user base, which includes: (1) Users of the PC version of HotSpot for consequence assessment, hazard assessment and safety analysis calculations; and (2) Users of the NARAC Web and iClient software tools, which allow users to run HotSpot for consequence assessment modeling These users and sponsors of the HotSpot software and the organizations they represent constitute the intended audience for this document. This plan is intended to meet Critical Recommendations 1 and 3 from the Software Evaluation of HotSpot and DOE Safety Software Toolbox Recommendation for inclusion of HotSpot in the Department of Energy (DOE) Safety Software Toolbox. HotSpot software is maintained for the Department of Energy Office of Emergency Operations by the National Atmospheric Release Advisory Center (NARAC) at Lawrence Livermore National Laboratory (LLNL). An overview of HotSpot and NARAC are provided.

Walker, H; Homann, S G

2009-03-12T23:59:59.000Z

171

Information Management Strategic Plan. Information: The fuel for success  

SciTech Connect

Reliable information is key to the ultimate success of the Departmental Strategic Plan. To help ensure that success, this Information Management Strategic Plan has been developed, which evolved from and directly supports the Departmental Strategic Plan and the Human Resources and Administration Strategic Plan.

1994-07-01T23:59:59.000Z

172

Modeling Risks in Infrastructure Asset Management  

E-Print Network (OSTI)

The goal of this dissertation research is to model risk in delivery, operation and maintenance phases of infrastructure asset management. More specifically, the two main objectives of this research are to quantify and measure financial risk in privatizing and operational risks in maintenance and rehabilitation of infrastructure facilities. To this end, a valuation procedure for valuing large-scale risky projects is proposed. This valuation approach is based on mean-risk portfolio optimization in which a risk-averse decision-maker seeks to maximize the expected return subject to downside risk. We show that, in complete markets, the value obtained from this approach is equal to the value obtained from the standard option pricing approach. Furthermore, we introduce Coherent Valuation Procedure (CVP) for valuing risky projects in partially complete markets. This approach leads to a lower degree of subjectivity as it only requires one parameter to incorporate user's risk preferences. Compared to the traditional discounted cash flow analysis, CVP displays a reasonable degree of sensitivity to the discount rate since only the risk-free rate is used to discount future cash flows. The application of this procedure on valuing a transportation public-private partnership is presented. %and demonstrate that the breakeven buying price of a risky project is equal to the value obtained from this valuation procedure. Secondly, a risk-based framework for prescribing optimal risk-based maintenance and rehabilitation (M&R) policies for transportation infrastructure is presented. These policies guarantee a certain performance level across the network under a predefined level of risk. The long-term model is formulated in the Markov Decision Process framework with risk-averse actions and transitional probabilities describing the uncertainty in the deterioration process. Conditional Value at Risk (CVaR) is used as the measure of risk. The steady-state risk-averse M&R policies are modeled assuming no budget restriction. To address the short-term resource allocation problem, two linear programming models are presented to generate network-level polices with different objectives. In the first model, decision-maker minimizes the total risk across the network, and in the second model, the highest risk to the network performance is minimized.

Seyedolshohadaie, Seyed Reza

2011-08-01T23:59:59.000Z

173

The management of foreign exchange risk, Second edition  

SciTech Connect

This edition of this introductory textbook to foreign exchange risk management considers: how to measure risk and accurately forecast exchange rates and use those forecasts; the principal hedging procedures; management approaches to risk including the use of export finance companies and management control and centralization. It is written by a team of corporate and banking practioners. Contents include: Measuring foreign exchange risk; Forecasting exchange rates; Using foreign exchange markets and forecasts; Hedging procedures; Management approaches to risk.

Ensor, R.; Antl, B.

1984-01-01T23:59:59.000Z

174

Risk management activities at the DOE Class A reactor facilities  

Science Conference Proceedings (OSTI)

The probabilistic risk assessment (PRA) and risk management group of the Association for Excellence in Reactor Operation (AERO) develops risk management initiatives and standards to improve operation and increase safety of the DOE Class A reactor facilities. Principal risk management applications that have been implemented at each facility are reviewed. The status of a program to develop guidelines for risk management programs at reactor facilities is presented.

Sharp, D.A. [Westinghouse Savannah River Co., Aiken, SC (United States); Hill, D.J. [Argonne National Lab., IL (United States); Linn, M.A. [Oak Ridge National Lab., TN (United States); Atkinson, S.A. [EG and G Idaho, Inc., Idaho Falls, ID (United States); Hu, J.P. [Brookhaven National Lab., Upton, NY (United States)

1993-12-31T23:59:59.000Z

175

Spent Nuclear Fuel project integrated safety management plan  

SciTech Connect

This document is being revised in its entirety and the document title is being revised to ``Spent Nuclear Fuel Project Integrated Safety Management Plan.

Daschke, K.D.

1996-09-17T23:59:59.000Z

176

Idaho National Laboratory Cultural Resource Management Plan  

SciTech Connect

As a federal agency, the U.S. Department of Energy has been directed by Congress, the U.S. president, and the American public to provide leadership in the preservation of prehistoric, historic, and other cultural resources on the lands it administers. This mandate to preserve cultural resources in a spirit of stewardship for the future is outlined in various federal preservation laws, regulations, and guidelines such as the National Historic Preservation Act, the Archaeological Resources Protection Act, and the National Environmental Policy Act. The purpose of this Cultural Resource Management Plan is to describe how the Department of Energy, Idaho Operations Office will meet these responsibilities at the Idaho National Laboratory. This Laboratory, which is located in southeastern Idaho, is home to a wide variety of important cultural resources representing at least 13,500 years of human occupation in the southeastern Idaho area. These resources are nonrenewable; bear valuable physical and intangible legacies; and yield important information about the past, present, and perhaps the future. There are special challenges associated with balancing the preservation of these sites with the management and ongoing operation of an active scientific laboratory. The Department of Energy, Idaho Operations Office is committed to a cultural resource management program that accepts these challenges in a manner reflecting both the spirit and intent of the legislative mandates. This document is designed for multiple uses and is intended to be flexible and responsive to future changes in law or mission. Document flexibility and responsiveness will be assured through annual reviews and as-needed updates. Document content includes summaries of Laboratory cultural resource philosophy and overall Department of Energy policy; brief contextual overviews of Laboratory missions, environment, and cultural history; and an overview of cultural resource management practices. A series of appendices provides important details that support the main text.

Lowrey, Diana Lee

2011-02-01T23:59:59.000Z

177

Idaho National Laboratory Cultural Resource Management Plan  

Science Conference Proceedings (OSTI)

As a federal agency, the U.S. Department of Energy has been directed by Congress, the U.S. president, and the American public to provide leadership in the preservation of prehistoric, historic, and other cultural resources on the lands it administers. This mandate to preserve cultural resources in a spirit of stewardship for the future is outlined in various federal preservation laws, regulations, and guidelines such as the National Historic Preservation Act, the Archaeological Resources Protection Act, and the National Environmental Policy Act. The purpose of this Cultural Resource Management Plan is to describe how the Department of Energy, Idaho Operations Office will meet these responsibilities at Idaho National Laboratory in southeastern Idaho. The Idaho National Laboratory is home to a wide variety of important cultural resources representing at least 13,500 years of human occupation in the southeastern Idaho area. These resources are nonrenewable, bear valuable physical and intangible legacies, and yield important information about the past, present, and perhaps the future. There are special challenges associated with balancing the preservation of these sites with the management and ongoing operation of an active scientific laboratory. The Department of Energy, Idaho Operations Office is committed to a cultural resource management program that accepts these challenges in a manner reflecting both the spirit and intent of the legislative mandates. This document is designed for multiple uses and is intended to be flexible and responsive to future changes in law or mission. Document flexibility and responsiveness will be assured through regular reviews and as-needed updates. Document content includes summaries of Laboratory cultural resource philosophy and overall Department of Energy policy; brief contextual overviews of Laboratory missions, environment, and cultural history; and an overview of cultural resource management practices. A series of appendices provides important details that support the main text.

Julie Braun Williams

2013-02-01T23:59:59.000Z

178

Idaho National Laboratory Cultural Resource Management Plan  

SciTech Connect

As a federal agency, the U.S. Department of Energy has been directed by Congress, the U.S. president, and the American public to provide leadership in the preservation of prehistoric, historic, and other cultural resources on the lands it administers. This mandate to preserve cultural resources in a spirit of stewardship for the future is outlined in various federal preservation laws, regulations, and guidelines such as the National Historic Preservation Act, the Archaeological Resources Protection Act, and the National Environmental Policy Act. The purpose of this Cultural Resource Management Plan is to describe how the Department of Energy, Idaho Operations Office will meet these responsibilities at the Idaho National Laboratory. This Laboratory, which is located in southeastern Idaho, is home to a wide variety of important cultural resources representing at least 13,500 years of human occupation in the southeastern Idaho area. These resources are nonrenewable; bear valuable physical and intangible legacies; and yield important information about the past, present, and perhaps the future. There are special challenges associated with balancing the preservation of these sites with the management and ongoing operation of an active scientific laboratory. The Department of Energy, Idaho Operations Office is committed to a cultural resource management program that accepts these challenges in a manner reflecting both the spirit and intent of the legislative mandates. This document is designed for multiple uses and is intended to be flexible and responsive to future changes in law or mission. Document flexibility and responsiveness will be assured through annual reviews and as-needed updates. Document content includes summaries of Laboratory cultural resource philosophy and overall Department of Energy policy; brief contextual overviews of Laboratory missions, environment, and cultural history; and an overview of cultural resource management practices. A series of appendices provides important details that support the main text.

Lowrey, Diana Lee

2009-02-01T23:59:59.000Z

179

NIST SP 800-39, Managing Information Security Risk ...  

Science Conference Proceedings (OSTI)

... Provide oversight for the risk management activities carried out ... a greater understanding of risk with regard ... serve as a focal point for communicating ...

2012-02-06T23:59:59.000Z

180

IEA-Risk Quantification and Risk Management in Renewable Energy Projects |  

Open Energy Info (EERE)

IEA-Risk Quantification and Risk Management in Renewable Energy Projects IEA-Risk Quantification and Risk Management in Renewable Energy Projects Jump to: navigation, search Tool Summary Name: IEA-Risk Quantification and Risk Management in Renewable Energy Projects Agency/Company /Organization: International Energy Agency Sector: Energy Focus Area: Renewable Energy Topics: Finance, Implementation, Market analysis Resource Type: Presentation, Lessons learned/best practices Website: www.iea-retd.org/files/RISK%20IEA-RETD%20(2011-6).pdf Cost: Free IEA-Risk Quantification and Risk Management in Renewable Energy Projects Screenshot References: IEA-Risk Quantification and Risk Management in Renewable Energy Projects[1] Logo: IEA-Risk Quantification and Risk Management in Renewable Energy Projects "This report presents a transparent and reproducible set of techniques to

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


181

Resource management plan for the Oak Ridge Reservation. Volume 27, Wildlife Management Plan  

SciTech Connect

A plan for management of the wildlife resources on the US Department of Energy`s Oak Ridge Reservation is outlined in this document. Management includes wildlife population control (hunts, trapping, and removal), handling specific problems with wildlife, restoration of species, coordination with researchers on wildlife studies, preservation and management of habitats, and law enforcement. Wildlife resources are divided into five categories, each with a specific set of objectives and procedures for obtaining these objectives. These categories are (1) species-richness management to ensure that all resident wildlife species exist on the Reservation in viable numbers; (2) featured species management to produce selected species in desired numbers on designated land units; (3) management of game species for research, education, recreation, and public safety, (4) endangered species management designed to preserve and protect both the species and habitats critical to the survival of those species; and (5) pest management. Achievement of the objectives is a joint effort between the Tennessee Wildlife Resources Agency and the Oak Ridge National Laboratory`s Environmental Sciences Division.

Parr, P.D. [Oak Ridge National Lab., TN (United States); Evans, J.W. [Tennessee Wildlife Resources Agency, Knoxville, TN (United States)

1992-06-01T23:59:59.000Z

182

DOE G 413.3-7A, Risk Management Guide  

Directives, Delegations, and Requirements

This Guide provides non-mandatory risk management approaches for implementing the requirements of DOE O 413.3B, Program and Project Management for the ...

2011-01-18T23:59:59.000Z

183

Environmental Restoration and Waste Management: Strategic plan  

Science Conference Proceedings (OSTI)

The Brookhaven National Laboratory (BNL) site is currently divided into five major areas, Operable Units (OUs), and several Areas of Concern (AOCs), which are the focus of investigation and clean-up. The primary environmental concern is groundwater contamination and a major emphasis of the restoration activities is focused on this medium. Each year, BNL generates 60 tons of hazardous waste and 7,000 to 8,000 cubic feet of radioactive waste that result from research activities. These wastes are collected at a central location, packaged and shipped off site for disposal. The operations for Hazardous and Radioactive Waste Management are conducted in compliance with EPA and DOE regulations. BNL has continued to actively pursue means by which these wastes may be minimized. Activities in both the remediation and waste management arenas are intimately connected with the future vision of BNL. The long-range goal for remediation in conjunction with vigorous monitoring of BNL`s activities is to restore the site and maintain strong environmental controls. The goals of the waste minimization program include activities to find environmentally safe alternatives to materials currently in use. By careful planning, BNL will minimize the amount of all waste, including sanitary, that is generated on site.

Not Available

1994-09-01T23:59:59.000Z

184

Hanford Sampling Quality Management Plan (HSQMP)  

Science Conference Proceedings (OSTI)

This document provides a management tool for evaluating and designing the appropriate elements of a field sampling program. This document provides discussion of the elements of a program and is to be used as a guidance document during the preparation of project and/or function specific documentation. This document does not specify how a sampling program shall be organized. The HSQMP is to be used as a companion document to the Hanford Analytical Services Quality Assurance Plan (HASQAP) DOE/RL-94-55. The generation of this document was enhanced by conducting baseline evaluations of current sampling organizations. Valuable input was received from members of field and Quality Assurance organizations. The HSQMP is expected to be a living document. Revisions will be made as regulations and or Hanford Site conditions warrant changes in the best management practices. Appendices included are: summary of the sampling and analysis work flow process, a user`s guide to the Data Quality Objective process, and a self-assessment checklist.

Hyatt, J.E.

1995-04-28T23:59:59.000Z

185

Planning Tools For Seismic Risk Mitigation. Rules And Applications  

SciTech Connect

Recently, Italian urban planning research in the field of seismic risk mitigation are renewing. In particular, it promotes strategies that integrate urban rehabilitation and aseismic objectives, and also politicizes that are directed to revitalizes urban systems, coupling physical renewal and socio-economic development.In Italy the first law concerning planning for seismic mitigation dates back 1974, the law n. 64 'Regulation for buildings with particular rules for the seismic areas' where the rules for buildings in seismic areas concerning also the local hazard. This law, in fact, forced the municipalities to acquire, during the formation of the plans, a preventive opinion of compatibility between planning conditions and geomorphology conditions of the territory. From this date the conviction that the seismic risk must be considered inside the territorial planning especially in terms of strategies of mitigation has been strengthened.The town planners have started to take an interest in seismic risk in the [80]s when the Irpinia's earthquake took place. The researches developed after this earthquake have established that the principal cause of the collapse of buildings are due to from the wrong location of urban settlements (on slopes or crowns) After Irpinia's earthquake the first researches on seismic risk mitigation, in particular on the aspects related to the hazards and to the urban vulnerability were made.

De Paoli, Rosa Grazia [Department of Landscape Planning, Mediterranean University of Reggio Calabria (Italy)

2008-07-08T23:59:59.000Z

186

Homecare risk management: nursing issues related to technology  

Science Conference Proceedings (OSTI)

Traditional risk management may not address the needs of technology being introduced into homecare situations for nurses. We propose to augment traditional risk management with insights from Prevention through Design and The 8 Rights giving a more technology ...

Juliana J. Brixey, James P. Turley

2013-07-01T23:59:59.000Z

187

Cultural resource management: The risk of compliance  

Science Conference Proceedings (OSTI)

The statutory mandate for federal agencies to involve American Indians in the management of cultural resources may create a cultural risk for the people those statutes are intended to protect. A conceptual framework is given to help understand this dilemma. Factors that can exacerbate the severity of the adverse cultural impacts for tribal people are also examined. Policy recommendations are offered for reducing tensions among an the participants in the statutory process.

Curtis, S.A.

1994-02-01T23:59:59.000Z

188

Derivatives and Risk Management in the Petroleum, Natural Gas, and ...  

U.S. Energy Information Administration (EIA)

average price of the underlying asset during ... A brokerage enterprise which ... Energy Information Administration / Derivatives and Risk Management in Energy ...

189

Carbon Management Plan www.nottingham.ac.uk/sustainability  

E-Print Network (OSTI)

Carbon Management Plan 2010-2020 www.nottingham.ac.uk/sustainability #12;1 Carbon Management Plan 2010-2020 Contents Introduction 2 UK Carbon Policy 3 University Carbon Baselines 4 Recent Performance Trends and KPIs 5 University Targets 8 Strategic Themes 9 Carbon Saving Projects 12 2010-2012 Projects 13

Li, Jingpeng

190

Integrated Requirements Management System Operations and Maintenance Plan  

Science Conference Proceedings (OSTI)

This document provides a plan for the operations and maintenance of the Integrated Requirements Management Systems (IRMS) database. This document describes the roles and responsibilities for the users of the IRMS. Planning is provided for the configuration management of the DOORS software, hardware and data set. Training consideration for the various categories of users is provided.

ACREE, C.D.

2001-03-26T23:59:59.000Z

191

Plan for the management of radioactive waste, Savannah River Plant  

SciTech Connect

The following areas are covered in the Savannah River Plant's radioactive waste management plan: program administration; description of waste generating processes; waste management facilities; radioactive wastes stored; plans and budget projections; and description of decontamination and decommissioning . (LK)

1975-07-01T23:59:59.000Z

192

Uranium Mill Tailings Remedial Action Project surface project management plan  

SciTech Connect

This Project Management Plan describes the planning, systems, and organization that shall be used to manage the Uranium Mill Tailings Remedial Action Project (UMTRA). US DOE is authorized to stabilize and control surface tailings and ground water contamination at 24 inactive uranium processing sites and associated vicinity properties containing uranium mill tailings and related residual radioactive materials.

Not Available

1994-09-01T23:59:59.000Z

193

CONSERVATION AND MANAGEMENT PLAN PREBLE'S MEADOW JUMPING MOUSE  

E-Print Network (OSTI)

dependent upon maintenance of a healthy and functioning riparian system and associated uplands. AlterationsCONSERVATION AND MANAGEMENT PLAN FOR PREBLE'S MEADOW JUMPING MOUSE ON THE U.S. AIR FORCE ACADEMY, Suite 40 USAF Academy, CO 80840-2400 October 26, 1999 #12;CONSERVATION AND MANAGEMENT PLAN FOR PREBLE

194

Life Cycle Management Planning Sourcebooks, Volume 5: Main Generator  

Science Conference Proceedings (OSTI)

EPRI is producing a series of "Life Cycle Management Planning Sourcebooks," each containing a compilation of industry experience and data on aging degradation and historical performance for a specific type of system, structure, or component (SSC). This sourcebook provides information and guidance for implementing cost-effective life cycle management (LCM) planning for main generators.

2003-07-28T23:59:59.000Z

195

Plant Support Engineering: Life Cycle Management Planning Sourcebooks - Chillers  

Science Conference Proceedings (OSTI)

The Electric Power Research Institute (EPRI) is producing a series of Life Cycle Management Planning Sourcebooks, each containing a compilation of industry experience information and data on aging degradation and historical performance for a specific type of system, structure, or component (SSC). In addition, this sourcebook provides information and guidance for implementing cost8212effective life cycle management (LCM) planning for chillers.

2007-12-21T23:59:59.000Z

196

Mitch S. Daugherty Nuclear Engineering and Planning Manager  

E-Print Network (OSTI)

. Daugherty also headed the Nuclear Refueling Division, the Nuclear Test Engineering Division, and the NuclearMitch S. Daugherty Nuclear Engineering and Planning Manager Naval Sea Systems Command, Norfolk Naval Shipyard Mitch Daugherty is the Nuclear Engineering and Planning Manager and the senior civilian

197

Flight Plan Specification and Management for Unmanned Aircraft Systems  

Science Conference Proceedings (OSTI)

This paper presents a new concept for specifying Unmanned Aircraft Systems (UAS) flight operations that aims at improving the waypoint based approach, found in most autopilot systems, by providing higher level fligh plan specification primitives. The ... Keywords: Flight plan management, Flight plan specification, Unmanned aircraft systems (UAS)

Eduard Santamaria; Enric Pastor; Cristina Barrado; Xavier Prats; Pablo Royo; Marc Perez

2012-07-01T23:59:59.000Z

198

Mission Plan for the Civilian Radioactive Waste Management Program |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Mission Plan for the Civilian Radioactive Waste Management Program Mission Plan for the Civilian Radioactive Waste Management Program Mission Plan for the Civilian Radioactive Waste Management Program Summary In response to the the requirement of the Nuclear Waste Policy Act of 1982, the Office of Civilian Radioactive Waste Management in the Department of Energy (DOE) has prepared this Mission Plan for the Civilian Radioactive Waste Management Program. The Mission Plan is divided into two parts. Part I describes the overall goals, objectives, and strategy for the disposal of spent nuclear fuel and high-level waste. It explains that, to meet the directives of the Nuclear Waste Policy Act, the DOE intends to site, design, construct., and start operating a mined geologic repository by January 31, 1998. The Act specifies that the costs of these

199

Environmental Restoration Remedial Action Program records management plan  

SciTech Connect

The US Department of Energy-Richland Operations Office (DOE-RL) Environmental Restoration Field Office Management Plan ((FOMP) DOE-RL 1989) describes the plans, organization, and control systems to be used for management of the Hanford Site environmental restoration remedial action program. The FOMP, in conjunction with the Environmental Restoration Remedial Action Quality Assurance Requirements document ((QARD) DOE-RL 1991), provides all the environmental restoration remedial action program requirements governing environmental restoration work on the Hanford Site. The FOMP requires a records management plan be written. The Westinghouse Hanford Company (Westinghouse Hanford) Environmental Restoration Remedial Action (ERRA) Program Office has developed this ERRA Records Management Plan to fulfill the requirements of the FOMP. This records management plan will enable the program office to identify, control, and maintain the quality assurance, decisional, or regulatory prescribed records generated and used in support of the ERRA Program. 8 refs., 1 fig.

Michael, L.E.

1991-07-01T23:59:59.000Z

200

Configuration Management Plan for the Tank Farm Contractor  

Science Conference Proceedings (OSTI)

The Configuration Management Plan for the Tank Farm Contractor describes configuration management the contractor uses to manage and integrate its technical baseline with the programmatic and functional operations to perform work. The Configuration Management Plan for the Tank Farm Contractor supports the management of the project baseline by providing the mechanisms to identify, document, and control the technical characteristics of the products, processes, and structures, systems, and components (SSC). This plan is one of the tools used to identify and provide controls for the technical baseline of the Tank Farm Contractor (TFC). The configuration management plan is listed in the management process documents for TFC as depicted in Attachment 1, TFC Document Structure. The configuration management plan is an integrated approach for control of technical, schedule, cost, and administrative processes necessary to manage the mission of the TFC. Configuration management encompasses the five functional elements of: (1) configuration management administration, (2) configuration identification, (3) configuration status accounting, (4) change control, and (5 ) configuration management assessments.

WEIR, W.R.

2000-04-21T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


201

Industrial Energy Efficiency as a Risk Management Strategy  

E-Print Network (OSTI)

Industry utilizes risk management as a tool in efforts to maximize the bottom line. Industry embraced risk management strategies in the 1960s and since then it has become a key component of a comprehensive business strategy. Peter Fusaro, author of Energy Risk Management explains, The risk management process reduces financial exposure associated with price volatility by substituting a transaction made now for one that would be made at a later date. Risk management aids companies in minimizing operational surprises or losses. In recent decades, energy has become a greater risk to profitability due to the volatility that exists in the oil and natural gas markets. Therefore, companies now consider energy as an element of their risk management portfolio. Traditional strategies to combat against unwanted exposure in this market include hedging and long term and futures contracts. However, the following explores the topic of considering energy efficiency as a risk management tool in reducing exposure to the volatility of the energy market.

Naumoff, C.; Shipley, A. M.

2007-01-01T23:59:59.000Z

202

Risk-sensitive plan execution for connected sustainable home  

Science Conference Proceedings (OSTI)

This paper presents a risk-sensitive model-based plan executive, p-Sulu, as well as its application to energy-efficient room temperature control of a smart residential building called Connected Sustainable Home. p-Sulu minimizes the use of heating and ... Keywords: chance-constraint, flexible temporal constraint, smart building

Masahiro Ono; Wesley Graybill; Brian C. Williams

2012-11-01T23:59:59.000Z

203

IX Disposition Project - project management plan  

SciTech Connect

This report presents plans for resolving saving and disposal concerns for ion exchange modules, cartridge filters and columns. This plan also documents the project baselines for schedules, cost, and technical information.

Choi, I.G.

1994-12-08T23:59:59.000Z

204

Project Management Plan Examples 1 - 80 | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Project Management Plan Examples 1 - 80 Project Management Plan Examples 1 - 80 Project Management Plan Examples 1 - 80 The following material has been extracted from several project management plans. The order in which it is presented is arbitrary. The descriptions below should be used to navigate to the subject of interest. Policy & Operational Decisions, Assumptions and Strategies - Examples 1 & 2 - Includes organizational responsibilities and structure, disposition path, future use of facility, S&S Reqs and plan, hazard elimination or mitigation, NEPA, RCRA, CERCLA, HVAC/lighting service reqs, structural integrity reqs, etc. Facility End State Decisions - Examples 3, 4 & 5 - Includes expected conditions at completion of the deactivation, DOE mission use, extended S&M, decommissioned and/or dismantled, etc.

205

Water Management Plans for Surface Coal Mining Operations (North Dakota) |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Management Plans for Surface Coal Mining Operations (North Management Plans for Surface Coal Mining Operations (North Dakota) Water Management Plans for Surface Coal Mining Operations (North Dakota) < Back Eligibility Utility Fed. Government Commercial Agricultural Investor-Owned Utility State/Provincial Govt Industrial Construction Municipal/Public Utility Local Government Residential Installer/Contractor Rural Electric Cooperative Tribal Government Low-Income Residential Schools Retail Supplier Institutional Multi-Family Residential Systems Integrator Fuel Distributor Nonprofit General Public/Consumer Transportation Program Info State North Dakota Program Type Siting and Permitting A water management plan is required for all surface coal mining operations. This plan must be submitted to the State Engineer of the State Water Commission at the same time a surface mining permit is submitted to the

206

Energy Risk Management: Enterprise, Volatility, and "Black Swans"  

Science Conference Proceedings (OSTI)

Financial risk management in the banking industry is in turmoil. Some firms with the most sophisticated risk management practices were hit the hardest during the 2007-2009 economic crisis. However, their measures of financial risk appear to have provided false comfort. Energy firms use risk management practices derived from those used in banking and operate in commodity markets that are far less liquid, far less transparent, and subject to more substantial price swings than most of the markets in which b...

2009-12-28T23:59:59.000Z

207

United States Department of Energy Information Management Strategic Plan - partners for progress in corporate management  

SciTech Connect

This plan establishes a shared vision for the information management community. The plan provides overall direction for management information, reflects a strong customer focus, seeks an increased understanding of of DOE business lines and missions, and fosters a corporate collaborative approach to information management.

1997-09-01T23:59:59.000Z

208

Real options in information technology risk management: an empirical validation of risk-option relationships  

Science Conference Proceedings (OSTI)

Recently, an option-based risk management (OBRiM) framework has been proposed to control risk and maximize value in information technology investment decisions. While the framework is prescriptive in nature, its core logic rests on a set of normative ... Keywords: IT investment, real options, risk, risk management

Michel Benaroch; Yossi Lichtenstein; Karl Robinson

2006-12-01T23:59:59.000Z

209

Los Alamos National Laboratory emergency management plan. Revision 1  

SciTech Connect

The Laboratory has developed this Emergency Management Plan (EMP) to assist in emergency planning, preparedness, and response to anticipated and actual emergencies. The Plan establishes guidance for ensuring safe Laboratory operation, protection of the environment, and safeguarding Department of Energy (DOE) property. Detailed information and specific instructions required by emergency response personnel to implement the EMP are contained in the Emergency Management Plan Implementing Procedure (EMPIP) document, which consists of individual EMPIPs. The EMP and EMPIPs may be used to assist in resolving emergencies including but not limited to fires, high-energy accidents, hazardous material releases (radioactive and nonradioactive), security incidents, transportation accidents, electrical accidents, and natural disasters.

Ramsey, G.F.

1998-07-15T23:59:59.000Z

210

Storm Water Management Plan Program (Nebraska) | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Storm Water Management Plan Program (Nebraska) Storm Water Management Plan Program (Nebraska) Storm Water Management Plan Program (Nebraska) < Back Eligibility Agricultural Commercial Construction Fed. Government Fuel Distributor General Public/Consumer Industrial Installer/Contractor Institutional Investor-Owned Utility Local Government Low-Income Residential Multi-Family Residential Municipal/Public Utility Nonprofit Residential Retail Supplier Rural Electric Cooperative Schools State/Provincial Govt Systems Integrator Transportation Tribal Government Utility Savings Category Alternative Fuel Vehicles Hydrogen & Fuel Cells Buying & Making Electricity Water Home Weatherization Solar Wind Program Info State Nebraska Program Type Grant Program Provider Natural Resources This legislation implements the National Pollutant Discharge Elimination

211

Mississippi Headwaters Planning and Management (Minnesota) | Department of  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Headwaters Planning and Management (Minnesota) Headwaters Planning and Management (Minnesota) Mississippi Headwaters Planning and Management (Minnesota) < Back Eligibility Utility Fed. Government Commercial Agricultural Investor-Owned Utility State/Provincial Govt Industrial Construction Municipal/Public Utility Local Government Residential Installer/Contractor Rural Electric Cooperative Tribal Government Low-Income Residential Schools Retail Supplier Institutional Multi-Family Residential Systems Integrator Fuel Distributor Nonprofit General Public/Consumer Transportation Savings Category Alternative Fuel Vehicles Hydrogen & Fuel Cells Buying & Making Electricity Water Home Weatherization Solar Wind Program Info State Minnesota Program Type Siting and Permitting Construction and development is restricted and largely prohibited near the

212

Natural Resource Management Plan for Brookhaven National Laboratory  

SciTech Connect

This comprehensive Natural Resource Management Plan (NRMP) for Brookhaven National Laboratory (BNL) was built on the successful foundation of the Wildlife Management Plan for BNL, which it replaces. This update to the 2003 plan continues to build on successes and efforts to better understand the ecosystems and natural resources found on the BNL site. The plan establishes the basis for managing the varied natural resources located on the 5,265 acre BNL site, setting goals and actions to achieve those goals. The planning of this document is based on the knowledge and expertise gained over the past 10 years by the Natural Resources management staff at BNL in concert with local natural resource agencies including the New York State Department of Environmental Conservation, Long Island Pine Barrens Joint Planning and Policy Commission, The Nature Conservancy, and others. The development of this plan is an attempt at sound ecological management that not only benefits BNL's ecosystems but also benefits the greater Pine Barrens habitats in which BNL is situated. This plan applies equally to the Upton Ecological and Research Reserve (Upton Reserve). Any difference in management between the larger BNL area and the Upton Reserve are noted in the text. The purpose of the Natural Resource Management Plan (NRMP) is to provide management guidance, promote stewardship of the natural resources found at BNL, and to sustainably integrate their protection with pursuit of the Laboratory's mission. The philosophy or guiding principles of the NRMP are stewardship, sustainability, adaptive ecosystem management, compliance, integration with other plans and requirements, and the incorporation of community involvement, where applicable. The NRMP is periodically reviewed and updated, typically every five years. This review and update was delayed to develop documents associated with a new third party facility, the Long Island Solar Farm. This two hundred acre facility will result in significant changes to this plan warranting the delay. The body of this plan establishes the management goals and actions necessary for managing the natural resources at BNL in a sustainable manner. The appendices provide specific management requirements for threatened and endangered amphibians and fish (Appendices A and B, respectively), and lists of actions in tabular format - including completed items as well as ongoing and new action items (Appendices C and D, respectively).

green, T.

2011-08-15T23:59:59.000Z

213

Natural Resource Management Plan for Brookhaven National Laboratory  

SciTech Connect

This comprehensive Natural Resource Management Plan (NRMP) for Brookhaven National Laboratory (BNL) was built on the successful foundation of the Wildlife Management Plan for BNL, which it replaces. This update to the 2003 plan continues to build on successes and efforts to better understand the ecosystems and natural resources found on the BNL site. The plan establishes the basis for managing the varied natural resources located on the 5,265 acre BNL site, setting goals and actions to achieve those goals. The planning of this document is based on the knowledge and expertise gained over the past 10 years by the Natural Resources management staff at BNL in concert with local natural resource agencies including the New York State Department of Environmental Conservation, Long Island Pine Barrens Joint Planning and Policy Commission, The Nature Conservancy, and others. The development of this plan is an attempt at sound ecological management that not only benefits BNL's ecosystems but also benefits the greater Pine Barrens habitats in which BNL is situated. This plan applies equally to the Upton Ecological and Research Reserve (Upton Reserve). Any difference in management between the larger BNL area and the Upton Reserve are noted in the text. The purpose of the Natural Resource Management Plan (NRMP) is to provide management guidance, promote stewardship of the natural resources found at BNL, and to sustainably integrate their protection with pursuit of the Laboratory's mission. The philosophy or guiding principles of the NRMP are stewardship, sustainability, adaptive ecosystem management, compliance, integration with other plans and requirements, and the incorporation of community involvement, where applicable. The NRMP is periodically reviewed and updated, typically every five years. This review and update was delayed to develop documents associated with a new third party facility, the Long Island Solar Farm. This two hundred acre facility will result in significant changes to this plan warranting the delay. The body of this plan establishes the management goals and actions necessary for managing the natural resources at BNL in a sustainable manner. The appendices provide specific management requirements for threatened and endangered amphibians and fish (Appendices A and B, respectively), and lists of actions in tabular format - including completed items as well as ongoing and new action items (Appendices C and D, respectively).

green, T.

2011-08-15T23:59:59.000Z

214

Preliminary characterization of risks in the nuclear waste management system based on information in the literature  

Science Conference Proceedings (OSTI)

This document presents preliminary information on the radiological and nonradiological risks in the nuclear waste management system. The objective of the study was to (1) review the literature containing information on risks in the nuclear waste management system and (2) use this information to develop preliminary estimates of the potential magnitude of these risks. Information was collected on a broad range of risk categories to assist the US Department of Energy (DOE) in communicating information about the risks in the waste management systems. The study examined all of the portions of the nuclear waste management system currently expected to be developed by the DOE. The scope of this document includes the potential repository, the integral MRS facility, and the transportation system that supports the potential repository and the MRS facility. Relevant literature was reviewed for several potential repository sites and geologic media. A wide range of ``risk categories`` are addressed in this report: (1) public and occupational risks from accidents that could release radiological materials, (2) public and occupational radiation exposure resulting from routine operations, (3) public and occupational risks from accidents involving hazards other than radioactive materials, and (4) public and occupational risks from exposure to nonradioactive hazardous materials during routine operations. The report is intended to provide a broad spectrum of risk-related information about the waste management system. This information is intended to be helpful for planning future studies.

Daling, P.M.; Rhoads, R.E.; Van Luick, A.E.; Fecht, B.A.; Nilson, S.A.; Sevigny, N.L. [Pacific Northwest Lab., Richland, WA (United States); Armstrong, G.R. [Westinghouse Hanford Co., Richland, WA (United States); Hill, D.H.; Rowe, M.; Stern, E. [Brookhaven National Lab., Upton, NY (United States)

1992-01-01T23:59:59.000Z

215

Bruneau Subbasin Management Plan Contracted by  

E-Print Network (OSTI)

..................................................................................................................75 5 COORDINATION WITH EXISTING PROGRAMS...........................................................................................85 5.3 Coordination of Plan Implementation members. Table 2. Bruneau Project Team Name Affiliation Position Darin Saul Ecovista project coordinator

216

DOE Releases Electricity Subsector Cybersecurity Risk Management Process  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Releases Electricity Subsector Cybersecurity Risk Management Releases Electricity Subsector Cybersecurity Risk Management Process (RMP) Guideline DOE Releases Electricity Subsector Cybersecurity Risk Management Process (RMP) Guideline May 23, 2012 - 9:30am Addthis News Media Contact: (202) 586-4940 For Immediate Release: May 23, 2012 Department of Energy Releases Electricity Subsector Cybersecurity Risk Management Process (RMP) Guideline Public-Private Sector Collaboration Produces Guidance to Help Electric Utilities Better Understand and Assess Cybersecurity Risk WASHINGTON, DC - The Department of Energy's (DOE) Office of Electricity Delivery and Energy Reliability, in collaboration with the National Institute of Standards and Technology (NIST) and the North American Electric Reliability Corporation (NERC), today released guidance to help

217

Risk management in design engineering bids  

SciTech Connect

Accurate engineering cost estimates are critical in developing bids for new work, and for effective resource allocation and project control. This study reports on design estimating methods found in the literature, and on the results of two empirical studies of how estimating techniques are used in professional practice and their accuracy. The study found great reliance on a classic {open_quotes}activity analysis{close_quotes} approach to estimating design resources, and significant hazards in commonly used parametric techniques. The study found that project managers expect their estimates to be accurate (with 80% confidence interval) of between -10% to +25%. The study also found that actual bids between engineering firms had a much greater range (-40% to +45%) than can be explained by accuracy. Perhaps most importantly the study found that none of the sampled design firms used probabilistic techniques to optimize their project bids or to manage financial risk in view of the uncertainty of their estimates. The study concludes with techniques to reduce risk, and recommended future study.

Hudgins, D.W. [AlliedSignal Inc., Kansas City, MO (United States). Kansas City Division; Lavelle, J.P. [Kansas State Univ., Manhattan, KS (United States). Dept. of Industrial & Manufacturing Systems Engineering

1995-06-01T23:59:59.000Z

218

Threat based risk management in the federal sector  

Science Conference Proceedings (OSTI)

The United States federal government has many regulations and laws today that require federal agencies to implement a risk management program. Despite these efforts, computer security intrusions and data loss continue to rise. The need for a adaptable ... Keywords: FISMA, NIST, computer security, cybersecurity, risk, risk management, security programs

Nathan Volk

2010-10-01T23:59:59.000Z

219

Large engineering project risk management using a Bayesian belief network  

Science Conference Proceedings (OSTI)

This paper presents a scheme for large engineering project risk management using a Bayesian belief network and applies it to the Korean shipbuilding industry. Twenty-six different risks were deduced from expert interviews and a literature review. A survey ... Keywords: Bayesian belief network, Risk management in large engineering projects, Shipbuilding industry

Eunchang Lee; Yongtae Park; Jong Gye Shin

2009-04-01T23:59:59.000Z

220

Disruption Management ( Operations Research between planning and  

E-Print Network (OSTI)

creasing the cost of production gives rise to an increased demand for robustness in plans and calls ... T he monitoring and re-planning process is referred to as the control process. A s ..... have little help in estimating the quality of the recovery action they are about to. 8 .... and equipment , both of w hich are scarce resources.

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


221

Probabilistic Plan Management Laura M. Hiatt  

E-Print Network (OSTI)

.1.2 Search-Based Contingency Planning . . . . . . . . . . . . . . . . . . . . . 23 2.1.3 Conformant Planning strengthening strategy explores the full search space of the different orderings of backfills, swapping. . . . . . . . . . . . . . . . 40 3.2 A summary of non-local effect (NLE) types. . . . . . . . . . . . . . . . . . . . . . 42 5

222

Federal Energy Management Program: Plans, Implementation, and Results  

NLE Websites -- All DOE Office Websites (Extended Search)

Plans, Implementation, and Results Plans, Implementation, and Results The U.S. Department of Energy's Federal Energy Management Program (FEMP) works with key individuals to accomplish energy change within organizations, by bringing expertise from all levels of project and policy implementation, to enable Federal agencies to meet energy-related goals and provide energy leadership to the country. This Web page includes links to documents that support the office management process and the results and public benefits that derive from it. Overview Learn more about this EERE office. Plans Discover the plans, budgets, and analyses that set the direction of this office's priorities and activities. Implementation Find out how this office controls, implements, and adjusts its plans and manages its activities.

223

The Department of Energy's Office of Environmental Management's Budget Allocation Plan, OAS-L-12-03  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

The Department of Energy's Office The Department of Energy's Office of Environmental Management's Budget Allocation Plan OAS-L-12-03 March 2012 Department of Energy Washington, DC 20585 March 15, 2012 MEMORANDUM FOR THE SENIOR ADVISOR FOR ENVIRONMENTAL MANAGEMENT FROM: Daniel M. Weeber, Director Eastern Audits Division Office of Inspector General SUBJECT: INFORMATION: Audit Report on "The Department of Energy's Office of Environmental Management's Budget Allocation Plan" BACKGROUND The Department of Energy's Office of Environmental Management is tasked with managing the technically challenging risks posed by the world's largest nuclear cleanup effort. At the end of Fiscal Year 2010, EM had responsibility for nuclear cleanup activities at 18 sites covering more

224

Federal Energy Management Program: Renewable Energy Project Planning...  

NLE Websites -- All DOE Office Websites (Extended Search)

Planning and Implementation Federal renewable energy projects can be large or small and managed by a third-party or the agency. Typically, large-scale projects-larger than 10...

225

Management plan -- Multi-Function Waste Tank Facility. Revision 1  

SciTech Connect

This Westinghouse Hanford Company (WHC) Multi-Function Waste Tank Facility (MWTF) Management Plan provides guidance for execution WHC MWTF Project activities related to design, procurement, construction, testing, and turnover. This Management Plan provides a discussion of organizational responsibilities, work planning, project management systems, quality assurance (QA), regulatory compliance, personnel qualifications and training, and testing and evaluations. Classified by the US Department of Energy (DOE) as a major systems acquisition (MSA), the MWTF mission is to provide a safe, cost-effective, and environmentally sound method for interim storage of Hanford Site high-level wastes. This Management Plan provides policy guidance and direction to the Project Office for execution of the project activities.

Fritz, R.L.

1995-01-11T23:59:59.000Z

226

FY 1999 Spent Nuclear Fuel Interim Management Plan  

SciTech Connect

This document has been prepared to present in one place the near and long-term plans for safe management of SRS SNF inventories until final disposition has been identified and implemented.

Dupont, M.

1998-12-21T23:59:59.000Z

227

2012 Annual Planning Summary for Environmental Management  

Energy.gov (U.S. Department of Energy (DOE))

The ongoing and projected Environmental Assessments and Environmental Impact Statements for 2012 and 2013 within Environmental Management.

228

RCDA: Architecting as a risk- and cost management discipline  

Science Conference Proceedings (OSTI)

We propose to view architecting as a risk- and cost management discipline. This point of view helps architects identify the key concerns to address in their decision making, by providing a simple, relatively objective way to assess architectural significance. ... Keywords: Cost management, Risk Management, Software architecture

Eltjo R. Poort; Hans Van Vliet

2012-09-01T23:59:59.000Z

229

The mixed waste management facility, FY95 plan  

SciTech Connect

This document contains the Fiscal Year 1995 Plan for the Mixed Waste Management Facility (MWMF) at Lawrence Livermore National Laboratory. Major objectives to be completed during FY 1995 for the MWMF project are listed and described. This report also contains a budget plan, project task summaries, a milestone control log, and a responsibility assignment matrix for the MWMF project.

Streit, R.

1994-12-01T23:59:59.000Z

230

Excess Uranium Inventory Management Plan 2008 | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Excess Uranium Inventory Management Plan 2008 Excess Uranium Inventory Management Plan 2008 Excess Uranium Inventory Management Plan 2008 On March 11, 2008, Secretary of Energy Samuel W. Bodman signed a policy statement1 on the management of the U.S. Department of Energy's (DOE) excess uranium inventory (Policy Statement). This Policy Statement provides the framework within which DOE will make decisions concerning future use and disposition of this inventory. The Policy Statement commits DOE to manage those inventories in a manner that: (1) is consistent with all applicable legal requirements; (2) maintains sufficient uranium inventories at all times to meet the current and reasonably foreseeable needs of DOE missions; (3) undertakes transactions involving non-U.S. Government entities in a transparent and competitive manner, unless the Secretary of

231

NATURAL RESOURCE MANAGEMENT PLAN FOR BROOKHAVEN NATIONAL LABORATORY.  

SciTech Connect

Brookhaven National Laboratory (BNL) is located near the geographic center of Long Island, New York. The Laboratory is situated on 5,265 acres of land composed of Pine Barrens habitat with a central area developed for Laboratory work. In the mid-1990s BNL began developing a wildlife management program. This program was guided by the Wildlife Management Plan (WMP), which was reviewed and approved by various state and federal agencies in September 1999. The WMP primarily addressed concerns with the protection of New York State threatened, endangered, or species of concern, as well as deer populations, invasive species management, and the revegetation of the area surrounding the Relativistic Heavy Ion Collider (RHIC). The WMP provided a strong and sound basis for wildlife management and established a basis for forward motion and the development of this document, the Natural Resource Management Plan (NRMP), which will guide the natural resource management program for BNL. The body of this plan establishes the management goals and actions necessary for managing the natural resources at BNL. The appendices provide specific management requirements for threatened and endangered amphibians and fish (Appendices A and B respectively), lists of actions in tabular format (Appendix C), and regulatory drivers for the Natural Resource Program (Appendix D). The purpose of the Natural Resource Management Plan is to provide management guidance, promote stewardship of the natural resources found at BNL, and to integrate their protection with pursuit of the Laboratory's mission. The philosophy or guiding principles of the NRMP are stewardship, adaptive ecosystem management, compliance, integration with other plans and requirements, and incorporation of community involvement, where applicable.

GREEN,T.ET AL.

2003-12-31T23:59:59.000Z

232

Price Risk Management in the Midst of a Credit Crisis  

E-Print Network (OSTI)

Agricultural producers today face volatile markets, tight credit, economic uncertainty and escalating input costs. Understanding and using risk management tools in this environment can reduce much of the price risk and may improve financial returns.

Welch, Mark; Amosson, Stephen H.; Robinson, John; Falconer, Lawrence

2009-03-26T23:59:59.000Z

233

Vulnerability and social risk management in India and Mexico  

E-Print Network (OSTI)

The development of effective community, regional and national risk-management strategies, especially for systemic risks, such as natural disasters, entails understanding the determinants of social vulnerability in individuals ...

Flores Ballesteros, Luis

2008-01-01T23:59:59.000Z

234

Systems engineering management and implementation plan for Project W-465, immobilized low-activity waste plan  

SciTech Connect

The Systems Engineering Management and Implementation Plan (SEMIP) for TWRS Project W-465 describes the project implementation of the Tank Waste Remediation System Systems Engineering Management Plan (TWRS SEMP), Rev. 1. The SEMIP outlines systems engineering (SE) products and processes to be used by the project for technical baseline development. A formal graded approach is used to determine the products necessary for requirements, design, and operational baseline completion. SE management processes are defined, and roles and responsibilities for management processes and major technical baseline elements are documented.

Latray, D.A.

1998-05-15T23:59:59.000Z

235

WILDLAND FIRE MANAGEMENT PLAN FOR BROOKHAVEN NATIONAL LABORATORY.  

SciTech Connect

This Wildland Fire Management Plan (FMP) for Brookhaven National Lab (BNL) and the Upton Ecological and Research Reserve (Upton Reserve) is based on the U.S. Fish & Wildlife Service (FWS) fire management planning procedures and was developed in cooperation with the Department of Energy (DOE) by Brookhaven Science Associates. As the Upton Reserve is contained within the BNL 5,265-acre site, it is logical that the plan applies to both the Upton Reserve and BNL. The Department of the Interior policy for managing wildland fires requires that all areas managed by FWS that can sustain fire must have an FMP that details fire management guidelines for operational procedures and specifies values to be protected or enhanced. Fire management plans provide guidance on fire preparedness, fire prevention, wildfire suppression, and the use of controlled, ''prescribed'' fires and mechanical means to control the amount of available combustible material. Values reflected in the BNL/Upton Reserve Wildland FMP include protecting life and public safety; Lab properties, structures and improvements; cultural and historical sites; neighboring private and public properties; and endangered and threatened species and species of concern. Other values supported by the plan include the enhancement of fire-dependent ecosystems at BNL and the Upton Reserve. This FMP will be reviewed periodically to ensure the fire program advances and evolves with the missions of FWS, BNL, and the Upton Reserve. This Fire Management Plan is a modified version of the Long Island National Wildlife Refuge Complex Fire plan (updated in 2000), which contains all FWS fire plan requirements and is presented in the format specified by the national template for fire management plans adopted under the National Fire Plan. The DOE is one of the signatory agencies on the National Fire Plan. FWS shall be, through an Interagency Agreement dated November 2000 (Appendix C), responsible for coordinating and implementing prescribed burns and fuel reduction projects in the Upton Reserve. Prescribed fire and fuel reduction in locations outside the Upton Reserve will be coordinated through the Natural Resource Management Program at BNL, and done in consultation with FWS. This FMP is to be used and implemented for the entire BNL site including the Upton Reserve and has been reviewed by FWS, The Nature Conservancy, New York State Department of Environmental Conservation Forest Rangers, and DOE, as well as appropriate BNL emergency services personnel.

ENVIRONMENTAL AND WASTE MANAGEMENT SERVICES DIVISION

2003-09-01T23:59:59.000Z

236

WILDLAND FIRE MANAGEMENT PLAN FOR BROOKHAVEN NATIONAL LABORATORY.  

SciTech Connect

This Wildland Fire Management Plan (FMP) for Brookhaven National Lab (BNL) and the Upton Ecological and Research Reserve (Upton Reserve) is based on the U.S. Fish & Wildlife Service (FWS) fire management planning procedures and was developed in cooperation with the Department of Energy (DOE) by Brookhaven Science Associates. As the Upton Reserve is contained within the BNL 5,265-acre site, it is logical that the plan applies to both the Upton Reserve and BNL. The Department of the Interior policy for managing wildland fires requires that all areas managed by FWS that can sustain fire must have an FMP that details fire management guidelines for operational procedures and specifies values to be protected or enhanced. Fire management plans provide guidance on fire preparedness, fire prevention, wildfire suppression, and the use of controlled, ''prescribed'' fires and mechanical means to control the amount of available combustible material. Values reflected in the BNL/Upton Reserve Wildland FMP include protecting life and public safety; Lab properties, structures and improvements; cultural and historical sites; neighboring private and public properties; and endangered and threatened species and species of concern. Other values supported by the plan include the enhancement of fire-dependent ecosystems at BNL and the Upton Reserve. This FMP will be reviewed periodically to ensure the fire program advances and evolves with the missions of FWS, BNL, and the Upton Reserve. This Fire Management Plan is a modified version of the Long Island National Wildlife Refuge Complex Fire plan (updated in 2000), which contains all FWS fire plan requirements and is presented in the format specified by the national template for fire management plans adopted under the National Fire Plan. The DOE is one of the signatory agencies on the National Fire Plan. FWS shall be, through an Interagency Agreement dated November 2000 (Appendix C), responsible for coordinating and implementing prescribed burns and fuel reduction projects in the Upton Reserve. Prescribed fire and fuel reduction in locations outside the Upton Reserve will be coordinated through the Natural Resource Management Program at BNL, and done in consultation with FWS. This FMP is to be used and implemented for the entire BNL site including the Upton Reserve and has been reviewed by FWS, The Nature Conservancy, New York State Department of Environmental Conservation Forest Rangers, and DOE, as well as appropriate BNL emergency services personnel.

ENVIRONMENTAL AND WASTE MANAGEMENT SERVICES DIVISION

2003-09-01T23:59:59.000Z

237

Risk Prioritization  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Quality Managers Quality Managers Software Quality Assurance Subcommittee Reference Document SQAS21.01.00 - 1999 Software Risk Management A Practical Guide February, 2000 Abstract This document is a practical guide for integrating software risk management into a software project. The purpose of Risk Management is to identify, assess and control project risks. Identified risks are analyzed to determine their potential impact and likelihood of occurrence. Risk Management Plans are developed to document the project's approach to risk management, risks, and decisions made about what should be done with each risk. Risks and risk actions are then tracked to closure. Software Risk Management: A Practical Guide SQAS21.01.00 Acknowledgments This document was prepared for the Department of Energy (DOE) by a Working Group of the DOE

238

Moving Forward with the Electric Sector Cybersecurity Risk Management...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Sector Cybersecurity Risk Management Maturity" program, a White House initiative led by the Department of Energy in partnership with the Department of Homeland Security...

239

Managing Electricity Reliability Risk Through the Futures Markets  

E-Print Network (OSTI)

LBNL-47645 Managing Electricity Reliability Risk Through the Futures Markets Afzal S. Siddiqui Environmental Energy Technologies Division Ernest Orlando Lawrence Berkeley National Laboratory Berkeley for Operations Research and the Management Sciences INFORMS Annual Meeting in San Antonio, TX, November 2000

240

A companion modelling approach applied to forest management planning  

Science Conference Proceedings (OSTI)

To assist the Societe Civile des Terres du Larzac (SCTL) in its effort to develop alternative forest management plans, a group of researchers and extension officers proposed applying a companion modelling approach. The objective was to support forest ... Keywords: Companion modelling, Forest management, Livestock farming, Multi-agent system, Participatory modelling

C. Simon; M. Etienne

2010-11-01T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


241

Managing project risk using combined analytic hierarchy process and risk map  

Science Conference Proceedings (OSTI)

The main purpose of the study is to develop an integrated framework for managing project risks by analyzing risk across project, work package and activity levels, and developing responses. Design/methodology/approach: The study first reviews the literature ... Keywords: Analytic hierarchy process, Hierarchical approach, Oil pipeline construction, Project risk management

Prasanta Kumar Dey

2010-09-01T23:59:59.000Z

242

Wildland Fire Management Plan for Brookhaven National Laboratory  

SciTech Connect

This Wildland Fire Management Plan (FMP) for Brookhaven National Lab (BNL) updates the 2003 plan incorporating changes necessary to comply with DOE Order 450.1 and DOE P 450.4, Federal Wildland Fire Management Policy and Program Review; Wildland and Prescribed Fire Management Policy and implementation Procedures Reference Guide. This current plan incorporates changes since the original draft of the FMP that result from new policies on the national level. This update also removes references and dependence on the U.S. Fish & Wildlife Service and Department of the Interior, fully transitioning Wildland Fire Management responsibilities to BNL. The Department of Energy policy for managing wildland fires requires that all areas, managed by the DOE and/or its various contractors, that can sustain fire must have a FMP that details fire management guidelines for operational procedures associated with wild fire, operational, and prescribed fires. Fire management plans provide guidance on fire preparedness, fire prevention, wildfire suppression, and the use of controlled, 'prescribed' fires and mechanical means to control the amount of available combustible material. Values reflected in the BNL Wildland FMP include protecting life and public safety; Lab properties, structures and improvements; cultural and historical sites; neighboring private and public properties; and endangered, threatened, and species of concern. Other values supported by the plan include the enhancement of fire-dependent ecosystems at BNL. This FMP will be reviewed periodically to ensure the fire program advances and evolves with the missions of the DOE and BNL. This Fire Management Plan is presented in a format that coverers all aspects specified by DOE guidance documents which are based on the national template for fire management plans adopted under the National Fire Plan. The DOE is one of the signatory agencies on the National Fire Plan. This FMP is to be used and implemented for the entire BNL site including the Upton Reserve and has been reviewed by, The Nature Conservancy, New York State Department of Environmental Conservation Forest Rangers, and DOE, as well as appropriate BNL emergency services personnel. The BNL Fire Department is the lead on wildfire suppression. However, the BNL Natural Resource Manager will be assigned to all wildland fires as technical resource advisor.

Green,T.

2009-10-23T23:59:59.000Z

243

Wildland Fire Management Plan for Brookhaven National Laboratory  

SciTech Connect

This Wildland Fire Management Plan (FMP) for Brookhaven National Lab (BNL) updates the 2003 plan incorporating changes necessary to comply with DOE Order 450.1 and DOE P 450.4, Federal Wildland Fire Management Policy and Program Review; Wildland and Prescribed Fire Management Policy and implementation Procedures Reference Guide. This current plan incorporates changes since the original draft of the FMP that result from new policies on the national level. This update also removes references and dependence on the U.S. Fish & Wildlife Service and Department of the Interior, fully transitioning Wildland Fire Management responsibilities to BNL. The Department of Energy policy for managing wildland fires requires that all areas, managed by the DOE and/or its various contractors, that can sustain fire must have a FMP that details fire management guidelines for operational procedures associated with wild fire, operational, and prescribed fires. Fire management plans provide guidance on fire preparedness, fire prevention, wildfire suppression, and the use of controlled, 'prescribed' fires and mechanical means to control the amount of available combustible material. Values reflected in the BNL Wildland FMP include protecting life and public safety; Lab properties, structures and improvements; cultural and historical sites; neighboring private and public properties; and endangered, threatened, and species of concern. Other values supported by the plan include the enhancement of fire-dependent ecosystems at BNL. This FMP will be reviewed periodically to ensure the fire program advances and evolves with the missions of the DOE and BNL. This Fire Management Plan is presented in a format that coverers all aspects specified by DOE guidance documents which are based on the national template for fire management plans adopted under the National Fire Plan. The DOE is one of the signatory agencies on the National Fire Plan. This FMP is to be used and implemented for the entire BNL site including the Upton Reserve and has been reviewed by, The Nature Conservancy, New York State Department of Environmental Conservation Forest Rangers, and DOE, as well as appropriate BNL emergency services personnel. The BNL Fire Department is the lead on wildfire suppression. However, the BNL Natural Resource Manager will be assigned to all wildland fires as technical resource advisor.

Green,T.

2009-10-23T23:59:59.000Z

244

UNIVERSITY COLLEGE LONDON STANDARD ASBESTOS MANAGEMENT PLAN  

E-Print Network (OSTI)

If ACM's are kept in good condition and left undisturbed, fibres will not get into the air where they can to the health risks associated with asbestos. · To identify and monitor of Asbestos Containing Materials (ACM

Saunders, Mark

245

Spent Nuclear Fuel project systems engineering management plan  

SciTech Connect

The purpose of the WHC Systems Engineering Management Plan (SEMP) is to describe the systems engineering approach and methods that will be integrated with established WHC engineering practices to enhance the WHC engineering management of the SNF Project. The scope of the SEMP encompasses the efforts needed to manage the WHC implementation of systems engineering on the SNF Project. This implementation applies to, and is tailored to the needs of the SNF project and all its subprojects, including all current and future subprojects

Womack, J.C.

1995-10-03T23:59:59.000Z

246

AFRD EH&S: Integrated Safety Management Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Integrated Safety Management Integrated Safety Management The AFRD Integrated Safety Management or ISM Plan is the master document that guides AFRD policies and practices in environment, safety, and health. The guiding principles and core functions (below left) are the key to understanding ISM. Below, right are the topically arranged sections of the AFRD ISM Plan. Depending on your workplace and duties, more than one topic may apply to you. The ISM Plan is updated as of October 2013. Please contact us with any feedback. Guiding Principles Line-management responsibility for safety Clear roles and responsibilities Competence commensurate with responsibilities Balanced Priorities Identification of ES&H standards and requirements Hazard controls (including environmental controls) tailored to work being performed

247

IT Capital Planning Corporate Management Improvement Program (CMIP) |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

IT Capital Planning Corporate Management Improvement Program (CMIP) IT Capital Planning Corporate Management Improvement Program (CMIP) IT Capital Planning Corporate Management Improvement Program (CMIP) The Corporate Management Improvement Program (CMIP) was initiated by the Department in recognition of the fact that corporate legacy systems that support administrative functions were nearing the end of their life cycles. An investment to replace and modernize severely outdated information technology (IT) systems would prove a much more efficient expenditure of scarce IT dollars than the continued enhancement, maintenance, and operation of legacy systems. CMIP is an initiative to modernize and improve software applications, hardware, and infrastructure which support a wide range of Department-wide IT based business systems. CMIP permits the

248

Project Management Plan for the INEL technology logic diagrams  

SciTech Connect

This Project Management Plan (PjMP) describes the elements of project planning and control that apply to activities outlined in Technical Task Plan (TTP) ID-121117, ``Technology Logic Diagrams For The INEL.`` The work on this project will be conducted by personnel in EG&G Idaho, Inc.`s Waste Technology Development Program. Technology logic diagrams represent a formal methodology to identify technology gaps or needs within Environmental Restoration/Waste Management Operations, which will focus on Office of Environmental Restoration and Waste Management (EM-50) research and development, demonstration, test, and evaluation efforts throughout the US Department of Energy complex. This PjMP describes the objectives, organization, roles and responsibilities, workscope and processes for implementing and managing the technology logic diagram for the Idaho National Engineering Laboratory project.

Rudin, M.J.

1992-10-01T23:59:59.000Z

249

Project Management Plan for the INEL technology logic diagrams  

SciTech Connect

This Project Management Plan (PjMP) describes the elements of project planning and control that apply to activities outlined in Technical Task Plan (TTP) ID-121117, Technology Logic Diagrams For The INEL.'' The work on this project will be conducted by personnel in EG G Idaho, Inc.'s Waste Technology Development Program. Technology logic diagrams represent a formal methodology to identify technology gaps or needs within Environmental Restoration/Waste Management Operations, which will focus on Office of Environmental Restoration and Waste Management (EM-50) research and development, demonstration, test, and evaluation efforts throughout the US Department of Energy complex. This PjMP describes the objectives, organization, roles and responsibilities, workscope and processes for implementing and managing the technology logic diagram for the Idaho National Engineering Laboratory project.

Rudin, M.J.

1992-10-01T23:59:59.000Z

250

CRAD, Configuration Management Assessment Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Configuration Management Assessment Plan Configuration Management Assessment Plan CRAD, Configuration Management Assessment Plan Performance Objective: The objective of this assessment is to determine whether a Configuration Management Program (CM) is in place which allows for the availability and retrievability of accurate information, improves response to design and operational decisions, enhances worker safety, increases facility safety and reliability, increases efficiency of work efforts, and helps maintain integrity of interfacing orders. Criteria: The CM program supports DOE program implementation through the following: It provides the mechanisms for identifying, cataloging, and maintaining the design requirements and design basis (established to satisfy DOE O 420.1 Facility Safety). It carries forward the technical baseline established in the design

251

Department of Energy Environment, Safety and Health Management Plan. Fiscal year 1996  

SciTech Connect

This report describes efforts by the Department of Energy (DOE) to effectively plan for environment, safety and health activities that protect the environment, workers and the public from harm. This document, which covers fiscal year 1996, reflects planning by operating contractors and Program Offices in early 1994, updated to be consistent with the President`s FY 1996 budget submittal to Congress, and subsequent Department of Energy Program refinements. Prior to 1992, only a small number of facilities had a structured process for identifying environment, safety and health (ES and H) needs, reporting the costs (in both direct and indirect budgets) of ES and H requirements, prioritizing and allocating available resources, and efficiently communicating this information to DOE. Planned costs for ES and H activities were usually developed as an afterthought to program budgets. There was no visible, consistently applied mechanism for determining the appropriate amount of resources that should be allocated to ES and H, or for assuring that significant ES and H vulnerabilities were planned to be funded. To address this issue, the Secretary (in November 1991) directed DOE to develop a Safety and Health Five-Year Plan to serve as a line management tool to delineate DOE-wide programs to reduce and manage safety and health risks, and to establish a consistent framework for risk-based resource planning and allocation.

1996-01-01T23:59:59.000Z

252

Underground Test Area Project Waste Management Plan (Rev. No. 2, April 2002)  

Science Conference Proceedings (OSTI)

The U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Operations Office (NNSA/NV) initiated the UGTA Project to characterize the risk posed to human health and the environment as a result of underground nuclear testing activities at the Nevada Test Site (NTS). The UGTA Project investigation sites have been grouped into Corrective Action Units (CAUs) in accordance with the most recent version of the Federal Facility Agreement and Consent Order. The primary UGTA objective is to gather data to characterize the groundwater aquifers beneath the NTS and adjacent lands. The investigations proposed under the UGTA program may involve the drilling and sampling of new wells; recompletion, monitoring, and sampling of existing wells; well development and hydrologic/ aquifer testing; geophysical surveys; and subsidence crater recharge evaluation. Those wastes generated as a result of these activities will be managed in accordance with existing federal and state regulations, DOE Orders, and NNSA/NV waste minimization and pollution prevention objectives. This Waste Management Plan provides a general framework for all Underground Test Area (UGTA) Project participants to follow for the characterization, storage/accumulation, treatment, and disposal of wastes generated by UGTA Project activities. The objective of this waste management plan is to provide guidelines to minimize waste generation and to properly manage wastes that are produced. Attachment 1 to this plan is the Fluid Management Plan and details specific strategies for management of fluids produced under UGTA operations.

IT Corporation, Las Vegas

2002-04-24T23:59:59.000Z

253

Disruption Management | Operations Research between planning ...  

E-Print Network (OSTI)

in the airline industry, production management and logistics. At the department .... the status of the system forming the basis for operation is monitored. 4 .... In addition hereto airlines regularly face restrictive weather conditions, maintenance .

254

Certification process of safety analysis and risk management computer codes at the Savannah River Site  

Science Conference Proceedings (OSTI)

The commitment by Westinghouse Savannah River Company (WSRC) to bring safety analysis and risk management codes into compliance with national and sitewide quality assurance requirements necessitated a systematic, structured approach. As a part of this effort, WSRC, in cooperation with the Westinghouse Hanford Company, has developed and implemented a certification process for the development and control of computer software. Safety analysis and risk management computer codes pertinent to reactor analyses were selected for inclusion in the certification process. As a first step, documented plans were developed for implementing verification and validation of the codes, and establishing configuration control. User qualification guidelines were determined. The plans were followed with an extensive assessment of the codes with respect to certification status. Detailed schedules and work plans were thus determined for completing certification of the codes considered. Although the software certification process discussed is specific to the application described, it is sufficiently general to provide useful insights and guidance for certification of other software.

Ades, M.J. (Westinghouse Savannah River Co., Aiken, SC (United States)); Toffer, H.; Lewis, C.J.; Crowe, R.D. (Westinghouse Hanford Co., Richland, WA (United States))

1992-01-01T23:59:59.000Z

255

Certification process of safety analysis and risk management computer codes at the Savannah River Site  

Science Conference Proceedings (OSTI)

The commitment by Westinghouse Savannah River Company (WSRC) to bring safety analysis and risk management codes into compliance with national and sitewide quality assurance requirements necessitated a systematic, structured approach. As a part of this effort, WSRC, in cooperation with the Westinghouse Hanford Company, has developed and implemented a certification process for the development and control of computer software. Safety analysis and risk management computer codes pertinent to reactor analyses were selected for inclusion in the certification process. As a first step, documented plans were developed for implementing verification and validation of the codes, and establishing configuration control. User qualification guidelines were determined. The plans were followed with an extensive assessment of the codes with respect to certification status. Detailed schedules and work plans were thus determined for completing certification of the codes considered. Although the software certification process discussed is specific to the application described, it is sufficiently general to provide useful insights and guidance for certification of other software.

Ades, M.J. [Westinghouse Savannah River Co., Aiken, SC (United States); Toffer, H.; Lewis, C.J.; Crowe, R.D. [Westinghouse Hanford Co., Richland, WA (United States)

1992-05-01T23:59:59.000Z

256

ENVIRONMENT, HEALTH & SAFETY Risk Management Services, University of Alberta  

E-Print Network (OSTI)

of contracted testing (air quality) Biosafety Provide technical expertise and support to ensure a safe working Management Plan and ACM database management Chemical Safety Management Occupational Hygiene evaluations e.g. noise, chemical exposures, etc Air quality assessments. Laboratory Audits WHMIS / Chemical Spill

Machel, Hans

257

Department of Environmental Health & Safety Risk Management Services  

E-Print Network (OSTI)

Department of Environmental Health & Safety Risk Management Services November 2009 Version 1 receive health & safety training specific to the hazards present in the lab. Where a laboratory or core of Environmental Health & Safety Risk Management Services November 2009 Version 1 January 2012 Version 2

Machel, Hans

258

Comments Requested on Risk Management Publication  

Science Conference Proceedings (OSTI)

... and costly. These dangers can come from human error, environmental problems and planned attacks. They can compromise ...

2011-07-18T23:59:59.000Z

259

Livestock Risk Protection-Lamb: New Insurance Program to Help Ranchers Manage Lamb Price Risk  

E-Print Network (OSTI)

USDA is offering a new insurance program to help livestock producers manage lamb price risk. This publication explains requirements of the program and the way it works.

Pena, Jose G.; Thompson, Bill; Bevers, Stan; Anderson, David P.

2008-10-07T23:59:59.000Z

260

Methodology for Fire Configuration Risk Management  

Science Conference Proceedings (OSTI)

This report presents a methodology for performing bounding fire risk assessments at nuclear power plants (NPPs) for on-line equipment configurations. The methodology is designed to support risk assessments prior to performing maintenance, as required by 10CFR50.65 Section (a)(4), the Maintenance Rule. Risk assessments are typically performed for internal events using probabilistic risk assessments (PRAs). However, fire probabilistic risk assessments (FPRAs) are often not available or their use for this p...

2005-12-20T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


261

Radiation and Chemical Risk Management [EVS Program Area]  

NLE Websites -- All DOE Office Websites (Extended Search)

Radiation and Chemical Risk Management Radiation and Chemical Risk Management EVS helps meet the challenge of protecting human health and the environment through the management of risk associated with radiation and chemicals in the environment. Protecting human health, welfare, and the environment in a world affected by energy production and technology is a global challenge. EVS helps to meet this challenge through research and analysis on the management of risk associated with radiation and chemicals in the environment. To improve the management of risk associated with nuclear and chemical materials and wastes at contaminated sites, we develop information and tools that support decision making related to health, safety, environmental, economic, and social-cultural concerns. Nuclear Materials and Waste Disposition

262

Cybersecurity Risk Management Process (RMP) Guideline - Final (May 2012) |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Cybersecurity Risk Management Process (RMP) Guideline - Final (May Cybersecurity Risk Management Process (RMP) Guideline - Final (May 2012) Cybersecurity Risk Management Process (RMP) Guideline - Final (May 2012) This electricity subsector cybersecurity Risk Management Process (RMP) guideline was developed by the Department of Energy, in collaboration with the National Institute of Standards and Technology (NIST) and the North American Electric Reliability Corporation (NERC). The RMP is written with the goal of enabling organizations- regardless of size or organizational or governance structure-to apply effective and efficient risk management processes and tailor them to meet their organizational requirements. This guideline may be used to implement a new cybersecurity program within an organization or to build upon an organization's existing internal

263

Cybersecurity Risk Management Process (RMP) Guideline - Final (May 2012) |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Cybersecurity Risk Management Process (RMP) Guideline - Final (May Cybersecurity Risk Management Process (RMP) Guideline - Final (May 2012) Cybersecurity Risk Management Process (RMP) Guideline - Final (May 2012) This electricity subsector cybersecurity Risk Management Process (RMP) guideline was developed by the Department of Energy, in collaboration with the National Institute of Standards and Technology (NIST) and the North American Electric Reliability Corporation (NERC). The RMP is written with the goal of enabling organizations- regardless of size or organizational or governance structure-to apply effective and efficient risk management processes and tailor them to meet their organizational requirements. This guideline may be used to implement a new cybersecurity program within an organization or to build upon an organization's existing internal

264

Risk Management Resources Available from PMI and AACEI  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Risk Management Workshop Risk Management Workshop Oak Ridge, TN November 4-6, 2009 Presented by Chris Gruber, LMI Consultant PMI, AACEI, GAO Risk Management Perspectives and Resources Presentation Objectives Highlight available resources, including recommended or best practices, guidance, certification programs, etc. available through the Project Management Institute (PMI) and AACE International (AACEI), the Association for the Advancement of Cost Engineering, as well as recent guidance from GAO. These organizations represent a variety of industries and have derived common approaches, terminology, and practices that are applicable to a wide spectrum of projects and technologies. DOE has cooperative agreements in place with PMI and AACEI and the use or adaptation of these resources may

265

Pursuing Energy Efficiency as a Hedge against Carbon Regulatory Risks: Current Resource Planning Practices in the West  

Science Conference Proceedings (OSTI)

Uncertainty surrounding the nature and timing of future carbon regulations poses a fundamental and far-reaching financial risk for electric utilities and their ratepayers. Long-term resource planning provides a potential framework within which utilities can assess carbon regulatory risk and evaluate options for mitigating exposure to this risk through investments in energy efficiency and other low-carbon resources. In this paper, we examine current resource planning practices related to managing carbon regulatory risk, based on a comparative analysis of the most-recent long-term resource plans filed by fifteen major utilities in the Western U.S. First, we compare the assumptions and methods used by utilities to assess carbon regulatory risk and to evaluate energy efficiency as a risk mitigation option. Although most utilities have made important strides in beginning to address carbon regulatory risk within their resource plan, we also identify a number of opportunities for improvement and offer recommendations for resource planners and state regulators to consider. We also summarize the composition and carbon intensity of the preferred resource portfolios selected by the fifteen Western utilities, highlighting the contribution of energy efficiency and its impact on the carbon intensity of utilities' proposed resource strategies. Energy efficiency and renewables are the dominant low-carbon resources included in utilities' preferred portfolios. Across the fifteen utilities, energy efficiency constitutes anywhere from 6percent to almost 50percent of the preferred portfolio energy resources, and represents 22percent of all incremental resources in aggregate.

Barbose, Galen; Wiser, Ryan; Phadke, Amol; Goldman, Charles

2008-08-01T23:59:59.000Z

266

Pursuing Energy Efficiency as a Hedge against Carbon Regulatory Risks: Current Resource Planning Practices in the West  

Science Conference Proceedings (OSTI)

Uncertainty surrounding the nature and timing of future carbon regulations poses a fundamental and far-reaching financial risk for electric utilities and their ratepayers. Long-term resource planning provides a potential framework within which utilities can assess carbon regulatory risk and evaluate options for mitigating exposure to this risk through investments in energy efficiency and other low-carbon resources. In this paper, we examine current resource planning practices related to managing carbon regulatory risk, based on a comparative analysis of the most-recent long-term resource plans filed by fifteen major utilities in the Western U.S. First, we compare the assumptions and methods used by utilities to assess carbon regulatory risk and to evaluate energy efficiency as a risk mitigation option. Although most utilities have made important strides in beginning to address carbon regulatory risk within their resource plan, we also identify a number of opportunities for improvement and offer recommendations for resource planners and state regulators to consider. We also summarize the composition and carbon intensity of the preferred resource portfolios selected by the fifteen Western utilities, highlighting the contribution of energy efficiency and its impact on the carbon intensity of utilities' proposed resource strategies. Energy efficiency and renewables are the dominant low-carbon resources included in utilities' preferred portfolios. Across the fifteen utilities, energy efficiency constitutes anywhere from 6percent to almost 50percent of the preferred portfolio energy resources, and represents 22percent of all incremental resources in aggregate.

Barbose, Galen; Wiser, Ryan; Phadke, Amol; Goldman, Charles

2008-07-11T23:59:59.000Z

267

CH2M Hill Hanford Group Inc (CHG) Information Resource Management (IRM) Strategic Plan  

SciTech Connect

The CH2M Hill Hanford Group, Inc., Information Resource Management Strategic Plan is the top-level planning document for applying information and information resource management to achieve the CHG mission for the management of the River Protection Project

NELSON, R.L.

2000-05-08T23:59:59.000Z

268

Project management plan for Project W-320, Tank 241-C-106 sluicing  

SciTech Connect

This Project Management Plan establishes the organization, plans, and systems for management of Project W-320 as defined in DOE Order 4700.1, Project Management System (DOE 1987).

Phillips, D.R.

1994-12-01T23:59:59.000Z

269

Hanford Site Environmental Safety and Health Fiscal Year 2001 Budget-Risk management summary  

SciTech Connect

The Hanford Site Environment, Safety and Health (ES&H) Budget-Risk Management Summary report is prepared to support the annual request to sites in the U.S. Department of Energy (DOE) Complex by DOE, Headquarters. The request requires sites to provide supplementary crosscutting information related to ES&H activities and the ES&H resources that support these activities. The report includes the following: (1) A summary status of fiscal year (FY) 1999 ES&H performance and ES&H execution commitments; (2)Status and plans of Hanford Site Office of Environmental Management (EM) cleanup activities; (3) Safety and health (S&H) risk management issues and compliance vulnerabilities of FY 2001 Target Case and Below Target Case funding of EM cleanup activities; (4) S&H resource planning and crosscutting information for FY 1999 to 2001; and (5) Description of indirect-funded S&H activities.

REEP, I.E.

1999-05-12T23:59:59.000Z

270

ORNL long-range environmental and waste management plan  

SciTech Connect

This report, the ORNL Long-Range Environmental and Waste Management Plan, is the annual update in a series begun in fiscal year 1985. Its primary purpose is to provide a thorough and systematic planning document to reflect the continuing process of site assessment, strategy development, and planning for the current and long-term control of environmental issues, waste management practices, and remedial action requirements. The document also provides an estimate of the resources required to implement the current plan. This document is not intended to be a budget document; it is, however, intended to provide guidance to both Martin Marietta Energy Systems, Inc., and the US Department of Energy (DOE) management as to the near order of magnitude of the resources (primarily funding requirements) and the time frame required to execute the strategy in the present revision of the plan. As with any document of this nature, the near-term (one to three years) part of the plan is a pragmatic assessment of the current program and ongoing capital projects and reflects the efforts perceived to be necessary to comply with all current state and federal regulations and DOE orders. It also should be in general agreement with current budget (funding) requests and obligations for these immediate years. 55 figs., 72 tabs.

Baldwin, J.S.; Bates, L.D.; Brown, C.H.; Easterday, C.A.; Hill, L.G.; Kendrick, C.M.; McNeese, L.E.; Myrick, T.E.; Payne, T.L.; Pepper, C.E.; Robinson, S.M.; Rohwer, P.S.; Scanlan, T.F.; Smith, M.A.; Stratton, L.E.; Trabalka, J.R.

1989-09-01T23:59:59.000Z

271

Continuing Developments in PV Risk Management: Strategies, Solutions, and Implications  

Science Conference Proceedings (OSTI)

As the PV industry matures, successful risk management practices will become more imperative to ensure investor confidence, control costs, and facilitate further growth. This report discusses several key aspects of risk management during the commercial- and utility-scale project life cycle, from identification of risks, to the process of mitigating and allocating those risks among project parties, to transferring those risks through insurance. The report also explores novel techniques in PV risk management, options to offload risks onto the capital markets, and innovative insurance policies (namely warranty policies) that address risks unique to the PV sector. One of the major justifications for robust risk management in the PV industry is the cost-reduction opportunities it affords. If the PV industry can demonstrate the capability to successfully manage its risks, thereby inspiring confidence in financiers, it may be able to obtain a lower cost of capital in future transactions. A lower cost of capital translates to a lower cost of energy, which will in turn enhance PV?s competitiveness at a time when it will have to rely less on subsidies to support its market penetration.

Lowder, T.; Mendelsohn, M.; Speer, B.; Hill, R.

2013-02-01T23:59:59.000Z

272

River Protection Project (RPP) Project Management Plan  

SciTech Connect

The U.S. Department of Energy (DOE), in accordance with the Strom Thurmond National Defense Authorization Act for Fiscal Year 1999, established the Office of River Protection (ORP) to successfully execute and manage the River Protection Project (RPP), formerly known as the Tank Waste Remediation System (TWRS). The mission of the RPP is to store, retrieve, treat, and dispose of the highly radioactive Hanford tank waste in an environmentally sound, safe, and cost-effective manner. The team shown in Figure 1-1 is accomplishing the project. The ORP is providing the management and integration of the project; the Tank Farm Contractor (TFC) is responsible for providing tank waste storage, retrieval, and disposal; and the Privatization Contractor (PC) is responsible for providing tank waste treatment.

SEEMAN, S.E.

2000-04-01T23:59:59.000Z

273

The Waste Management Quality Assurance Implementing Management Plan (QAIMP)  

E-Print Network (OSTI)

meeting applicable requirements of LBL, DOE, DOT, and otherDOE Orders, and waste management acceptance requirements ofwith the requirements of this QAIMP and DOE Order 1324.2A.

Albert editor, R.

2009-01-01T23:59:59.000Z

274

CULTURAL RESOURCE MANAGEMENT PLAN FOR BROOKHAVEN NATIONAL LABORATORY.  

Science Conference Proceedings (OSTI)

The Cultural Resource Management Plan (CRMP) for Brookhaven National Laboratory (BNL) provides an organized guide that describes or references all facets and interrelationships of cultural resources at BNL. This document specifically follows, where applicable, the format of the U.S. Department of Energy (DOE) Environmental Guidelines for Development of Cultural Resource Management Plans, DOE G 450.1-3 (9-22-04[m1]). Management strategies included within this CRMP are designed to adequately identify the cultural resources that BNL and DOE consider significant and to acknowledge associated management actions. A principal objective of the CRMP is to reduce the need for additional regulatory documents and to serve as the basis for a formal agreement between the DOE and the New York State Historic Preservation Officer (NYSHPO). The BNL CRMP is designed to be a ''living document.'' Each section includes identified gaps in the management plan, with proposed goals and actions for addressing each gap. The plan will be periodically revised to incorporate new documentation.

DAVIS, M.

2005-04-01T23:59:59.000Z

275

Investigation-Derived Waste Management Plan. Revision 2  

SciTech Connect

SRS has implemented a comprehensive environmental program to maintain compliance with environmental regulations and mitigate impacts to the environment. One element of the environmental program is the investigation of inactive waste units. Environmental Investigation-Derived Waste (IDW). IDW may include purge water , soil cuttings, drilling fluids, well pumping test and development water, decontamination solutions, contaminated equipment, and personal protection equipment (PPE). In cases where investigations confirm the presence of contamination and the IDW contains waste constituents in concentrations high enough to be of environmental or health concern, special management procedures are warranted. This IDW Management Plan describes specific SRS initiatives for IDW management. The goal is the development of a plan for prudent management of IDW from environmental investigations that is protective of human health and the environment.

Molen, G.

1995-05-24T23:59:59.000Z

276

Program management plan for the Molten Salt Reactor Experiment Remediation Project at Oak Ridge National Laboratory, Oak Ridge, Tennessee  

SciTech Connect

The primary mission of the Molten Salt Reactor Experiment (MSRE) Remediation Project is to effectively implement the risk-reduction strategies and technical plans to stabilize and prevent further migration of uranium within the MSRE facility, remove the uranium and fuel salts from the system, and dispose of the fuel and flush salts by storage in appropriate depositories to bring the facility to a surveillance and maintenance condition before decontamination and decommissioning. This Project Management Plan (PMP) for the MSRE Remediation Project details project purpose; technical objectives, milestones, and cost objectives; work plan; work breakdown structure (WBS); schedule; management organization and responsibilities; project management performance measurement planning, and control; conduct of operations; configuration management; environmental, safety, and health compliance; quality assurance; operational readiness reviews; and training.

NONE

1996-09-01T23:59:59.000Z

277

Using Risk Management as Input to Operational Decisions  

Science Conference Proceedings (OSTI)

This report documents how most of plants in the fossil power industry that were reviewed make decisions that affect the risk involved in operational decisions. The report also gives guidance for a formal process that can be used to more consistently identify and manage risk. The risks include day to day operating activities plus testing and decisions on maintenance of equipment both routine and emergent. Some of these risks are taken frequently and some are only taken occasionally. The consequences of ta...

2005-12-23T23:59:59.000Z

278

Configuration management program plan for Hanford site systems engineering  

SciTech Connect

This plan establishes the integrated configuration management program for the evolving technical baseline developed through the systems engineering process. This configuration management program aligns with the criteria identified in the DOE Standard, DOE-STD-1073-93. Included are specific requirements for control of the systems engineering RDD-100 database, and electronic data incorporated in the database that establishes the Hanford site technical baseline.

Hoffman, A.G.

1994-11-14T23:59:59.000Z

279

In situ redox manipulation treatability test -- waste management plan  

DOE Green Energy (OSTI)

This Waste Management Plan provides guidance for the management of waste generated from groundwater well installations in the 100-HR-3 Operable Unit. The well installations are necessary to implement the In Situ Redox Manipulation Treatability Test to determine methods for in situ remedial efforts to prevent discharge of hexavalent chromium at levels above those considered protective of aquatic life in the Columbia River and riverbed sediments

A. J. Knepp

1997-12-31T23:59:59.000Z

280

Integrated safeguards and security management plan  

Science Conference Proceedings (OSTI)

Berkeley Lab is committed to scientific excellence and stewardship of its assets. While security principles apply to all work performed at the Laboratory, their implementation is flexible. Berkeley Lab adheres to the following principles: Line management owns security; Security roles and responsibilities are clearly defined and communicated; Security functions are integrated; An open environment supports the Laboratory's Mission; The security program must support the scientific and operational missions of the Laboratory and must be value added; and Security controls are tailored to individual and facility requirements.

Bowen, Sue, editor

2001-04-16T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


281

Strategic plan for Hanford Site Environmental Restoration Information Management  

SciTech Connect

This strategic plan addresses information management for the Environmental Restoration (ER) Program at the Hanford Site. This Program leads the cleanup of the Hanford Site`s soil, groundwater, buried waste, and the decontamination and decommissioning of facilities. The vision that drives this strategic plan is to ensure that quality information is available to the people who need it, when they need it, at a convenient location, in a usable form, and at an acceptable cost. Although investments are being made in managing the vast amounts of information, which include data, records and documents associated with the Hanford Site`s production history and new cleanup mission, it is widely recognized that efforts to date have not accomplished the vision. Effective information management involves more than the compilation of massive amounts of electronic and non-electronic information. It also involves integrating information management into business processes that support user`s needs and decisionmaking. Only then can information management complement and enable environmental restoration priorities and practices, help identify environmental restoration requirements, and enable communication within the Environmental Restoration Program and between the Program and its stakeholders. Successfully accomplishing the Hanford Site mission requires an integrated approach to information management that crosses organizational boundaries, streamlines existing systems, and builds new systems that support the needs of the future. This plan outlines that approach.

Cowley, P.J.; Beck, J.E.; Gephart, R.E. [and others

1994-06-01T23:59:59.000Z

282

Security risk assessment: toward a comprehensive practical risk management  

Science Conference Proceedings (OSTI)

This paper introduces a unique approach to a more integrated security risk assessment SRA. This is formalised based on the proven mathematical methods described in various articles in the literature and combined with the work developed by the author. ...

Danilo Valeros Bernardo

2012-01-01T23:59:59.000Z

283

Cybersecurity Risk Management Process (RMP) | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

(RMP) (RMP) Cybersecurity Risk Management Process (RMP) The electricity subsector cybersecurity Risk Management Process (RMP) guideline was developed by the Department of Energy (DOE), in collaboration with the National Institute of Standards and Technology (NIST) and the North American Electric Reliability Corporation (NERC). Members of industry and utility-specific trade groups were included in authoring this guidance designed to be meaningful and tailored for the electricity subsector. The NIST Special Publication (SP) 800-39, Managing Information Security Risk, provides the foundational methodology for this document. The NIST Interagency Report (NISTIR) 7628, Guidelines for Smart Grid Cyber Security, and NERC critical infrastructure cybersecurity standards further refine the

284

LIVERMORE SITE OFFICE CONTRACT MANAGEMENT PLAN For LAWRENCE LIVERMORE NATIONAL  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

LIVERMORE SITE OFFICE CONTRACT MANAGEMENT PLAN For LAWRENCE LIVERMORE NATIONAL LABORATORY CONTRACT NO. DE-AC52-07NA27344 LSO_CMP_6-10-088 i CONTENTS Contents 1. INTRODUCTION.............................................................................................................. 3 2. PURPOSE .......................................................................................................................... 3 2.2 Maintenance and Distribution ......................................................................................... 4 3. CONTRACT SUMMARY AND PRINCIPAL FEATURES............................................. 4 3.1 Contract Summary ...........................................................................................................

285

Gulf of Mexico Fishery Management Plans 1. Atlantic Red Drum  

E-Print Network (OSTI)

#12; Gulf of Mexico Fishery Management Plans 1. Atlantic Red Drum 2. Shrimp 3. Stone Crab 4. Coral, Coral Reef, and Live/Hard Bottom Habitats (with SAFMC) Key Gulf of Mexico Commercial Species Commercially-important species and species groups in the Gulf of Mexico include: blue crab, stone crab

286

Project Management Plan Examples 1 - 80 | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Examples 1 - 80 Examples 1 - 80 Project Management Plan Examples 1 - 80 The following material has been extracted from several project management plans. The order in which it is presented is arbitrary. The descriptions below should be used to navigate to the subject of interest. Policy & Operational Decisions, Assumptions and Strategies - Examples 1 & 2 - Includes organizational responsibilities and structure, disposition path, future use of facility, S&S Reqs and plan, hazard elimination or mitigation, NEPA, RCRA, CERCLA, HVAC/lighting service reqs, structural integrity reqs, etc. Facility End State Decisions - Examples 3, 4 & 5 - Includes expected conditions at completion of the deactivation, DOE mission use, extended S&M, decommissioned and/or dismantled, etc.

287

Energy-MAP: energy management and action plan  

DOE Green Energy (OSTI)

The City of Garden Grove created an energy program within its municipal operation during 1980, and subsequently developed the Energy Management and Action Plan (Energy-MAP). A community energy audit was conducted and an energy policy was developed. The policy established general guidelines for the Energy-MAP. The plan was designed to be a working document to guide in the future development of specific objectives and strategies to address the problems of increasing demand for energy resources, rapidly increasing costs of energy resources, and potential shortages or inadequate supplies of energy available to the community. Energy-MAP is described. The internal components address primary government operations, including vehicle fleet operations, municipal buildings operations, employee programs, lighting energy management, and water services operations. The external components include a community education/communications design, a transportation efficiency plan, information on potential alternative energy resources development, and a preliminary draft energy element.

Not Available

1981-12-15T23:59:59.000Z

288

Best-in-Class Project Management Initiative Corporate Implementation Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Best-in-Class Project Management Initiative Best-in-Class Project Management Initiative Corporate Implementation Plan Final Prepared for: U.S. Department of Energy Prepared by: U.S. Army Corps of Engineers, Huntington District and Project Time & Cost, Inc. 2727 Paces Ferry Road, Suite 1-1200 Atlanta, Georgia 30339 March 14, 2008 TOC - 1 Table of Contents Executive Summary ............................................................................................................. i 1.0 Introduction................................................................................................................ 1 1.1 Vision for Best-in-Class Project Management Initiative ........................................ 1 1.2 Strategy for Achieving BICPM ..............................................................................

289

Balancing Cost and Risk: The Treatment of Renewable Energy in Western Utility Resource Plans  

E-Print Network (OSTI)

Energy Efficiency and Renewable Energy (Office of Planning,I. Introduction Markets for renewable electricity have grownRisk: The Treatment of Renewable Energy in Western Utility

Wiser, Ryan; Bolinger, Mark

2005-01-01T23:59:59.000Z

290

Balancing Cost and Risk: The Treatment of Renewable Energy in Western Utility Resource Plans  

E-Print Network (OSTI)

Risk: The Treatment of Renewable Energy in Western Utilityutilities in evaluating renewable energy options. For anthe treatment of renewable energy in each of the plans is

Wiser, Ryan; Bolinger, Mark

2005-01-01T23:59:59.000Z

291

Rainwater Wildlife Area Management Plan : Executive Summary.  

SciTech Connect

The purpose of the project is to protect, enhance, and mitigate fish and wildlife resources impacted by Columbia River Basin hydroelectric development. The effort is one of several wildlife mitigation projects in the region developed to compensate for terrestrial habitat losses resulting from the construction of McNary and John Day Hydroelectric facilities located on the mainstem Columbia River. While this project is driven primarily by the purpose and need to mitigate for wildlife habitat losses, it is also recognized that management strategies will also benefit many other non-target fish and wildlife species and associated natural resources. The Northwest Power Act directs the NPPC to develop a program to ''protect, mitigate, and enhance'' fish and wildlife of the Columbia River and its tributaries. The overarching goals include: A Columbia River ecosystem that sustains an abundant, productive, and diverse community of fish and wildlife; Mitigation across the basin for the adverse effects to fish and wildlife caused by the development and operation of the hydrosystem; Sufficient populations of fish and wildlife for abundant opportunities for tribal trust and treaty right harvest and for non-tribal harvest; and Recovery of the fish and wildlife affected by the development and operation of the hydrosystem that are listed under the Endangered Species Act.

Childs, Allen B.; Confederated Tribes of the Umatilla Indian Reservation in Oregon.

2002-02-01T23:59:59.000Z

292

SAPHIRE 8 Software Configuration Management Plan  

Science Conference Proceedings (OSTI)

The INL software developers use version control for both the formally released SAPHIRE versions, as well as for source code. For each formal release of the software, the developers perform an acceptance test: the software must pass a suite of automated tests prior to official release. Each official release of SAPHIRE is assigned a unique version identifier. The release is bundled into a standard installation package for easy and consistent set-up by individual users. Included in the release is a list of bug fixes and new features for the current release, as well as a history of those items for past releases. Each formal release of SAPHIRE will have passed an acceptance test. In addition to assignment of a unique version identifier for an official software release, each source code file is kept in a controlled library. Source code is a collection of all the computer instructions written by developers to create the finished product. The library is kept on a server, where back-ups are regularly made. This document describes the configuration management approach used as part of the SAPHIRE development.

Curtis Smith

2010-01-01T23:59:59.000Z

293

Advanced Hybrid Particulate Collector Project Management Plan  

SciTech Connect

As the consumption of energy increases, its impact on ambient air quality has become a significant concern. Recent studies indicate that fine particles from coal combustion cause health problems as well as atmospheric visibility impairment. These problems are further compounded by the concentration of hazardous trace elements such as mercury, cadmium, selenium, and arsenic in fine particles. Therefore, a current need exists to develop superior, but economical, methods to control emissions of fine particles. Since most of the toxic metals present in coal will be in particulate form, a high level of fine- particle collection appears to be the best method of overall air toxics control. However, over 50% of mercury and a portion of selenium emissions are in vapor form and cannot be collected in particulate control devices. Therefore, this project will focus on developing technology not only to provide ultrahigh collection efficiency of particulate air toxic emissions, but also to capture vapor- phase trace metals such as mercury and selenium. Currently, the primary state-of-the-art technologies for particulate control are fabric filters (baghouses) and electrostatic precipitators (ESPs). However, they both have limitations that prevent them from achieving ultrahigh collection of fine particulate matter and vapor-phase trace metals. The objective of this project is to develop a highly reliable advanced hybrid particulate collector (AHPC) that can provide > 99.99 % particulate collection efficiency for all particle sizes between 0.01 and 50 14m, is applicable for use with all U.S. coals, and is cost-0443competitive with existing technologies. Phase I of the project is organized into three tasks: Task I - Project Management, Reporting, and Subcontract Consulting Task 2 - Modeling, Design, and Construction of 200-acfm AHPC Model Task 3 - Experimental Testing and Subcontract Consulting

Miller, S.J.

1995-11-01T23:59:59.000Z

294

Environmental Enterprise Risk Management Benefits for a Government Contractor  

SciTech Connect

An often overlooked advantage that an Environmental Enterprise Risk Management System (ERMS) has to organizations is the added protection from the Civil False Claims Act (FCA) for activities under a government contract.

Linda Guinn

2012-05-01T23:59:59.000Z

295

Managing the Risks of Climate Change and Terrorism  

SciTech Connect

The article describes challenges to comparative risk assessment, a key approach for managing uncertainty in decision making, across diverse threats such as terrorism and climate change and argues new approaches will be particularly important in addressing decisions related to sustainability.

Rosa, Eugene; Dietz, Tom; Moss, Richard H.; Atran, Scott; Moser, Susanne

2012-04-07T23:59:59.000Z

296

A statistical model for risk management of electric outage forecasts  

Science Conference Proceedings (OSTI)

Risk management of power outages caused by severe weather events, such as hurricanes, tornadoes, and thunderstorms, plays an important role in electric utility distribution operations. Damage prediction based on weather forecasts on an appropriate spatial ...

H. Li; L. A. Treinish; J. R. M. Hosking

2010-05-01T23:59:59.000Z

297

Business Continuity: IT Risk Management for International Corporations  

Science Conference Proceedings (OSTI)

From the Publisher:Risk Management and Business Continuity are essential for the competitive capacity of any international corporation. The temporary unavailability of technology and services can endanger the existence of any company. It is cruical to ...

Martin Wieczorek; Bob Bartlett; Uwe Naujoks

2002-04-01T23:59:59.000Z

298

New Draft of Cybersecurity Risk Management Process (RMP) Guideline Now  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Draft of Cybersecurity Risk Management Process (RMP) Guideline Draft of Cybersecurity Risk Management Process (RMP) Guideline Now Available for Public Comment (March 2012) New Draft of Cybersecurity Risk Management Process (RMP) Guideline Now Available for Public Comment (March 2012) March 1, 2012 - 3:26pm Addthis The Department of Energy, in collaboration with the National Institute of Standards and Technology (NIST) and the North American Electric Reliability Corporation (NERC), has released a second draft of the Electricity Subsector Cybersecurity Risk Management Process (RMP) guideline for public comment. This new draft, which will be the last opportunity for public comment prior to final publication, incorporates input submitted by the electric sector during the first public comment period. Many of the submitted comments suggested that the guideline:

299

The Department of Energy Releases Draft of Cybersecurity Risk Management  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

The Department of Energy Releases Draft of Cybersecurity Risk The Department of Energy Releases Draft of Cybersecurity Risk Management Process (RMP) Guideline for Public Comment (September 2011) The Department of Energy Releases Draft of Cybersecurity Risk Management Process (RMP) Guideline for Public Comment (September 2011) September 12, 2011 - 10:05am Addthis Public-Private Sector Collaboration Produces Guidance to Help Electric Utilities Better Understand and Assess Cybersecurity Risk WASHINGTON, DC - The Department of Energy, in collaboration with the National Institute of Standards and Technology and the North American Electric Reliability Corporation, has released a draft of the Electricity Sector Cybersecurity Risk Management Process (RMP) Guideline for public comment. The RMP Guideline was drafted by a joint public-private sector

300

The Department of Energy Releases Draft of Cybersecurity Risk Management  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

The Department of Energy Releases Draft of Cybersecurity Risk The Department of Energy Releases Draft of Cybersecurity Risk Management Process (RMP) Guideline for Public Comment The Department of Energy Releases Draft of Cybersecurity Risk Management Process (RMP) Guideline for Public Comment Public-Private Sector Collaboration Produces Guidance to Help Electric Utilities Better Understand and Assess Cybersecurity Risk WASHINGTON, DC - The Department of Energy, in collaboration with the National Institute of Standards and Technology and the North American Electric Reliability Corporation, has released a draft of the Electricity Sector Cybersecurity Risk Management Process (RMP) Guideline for public comment. The RMP Guideline was drafted by a joint public-private sector team that also included representatives from the Federal Energy Regulatory

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


301

Energy Risk Management: Current Practices and Future Directions  

Science Conference Proceedings (OSTI)

This report summarizes insights obtained from interviews conducted jointly by the Electric Power Research Institute (EPRI) and lectricit de France (EDF) of risk managers at ten companies operating in the US electric power industry. The primary objective of these interviews was to learn how companies are assessing and managing commodity price, load, credit, operational, and hydro inflow risks in the restructured power markets. The report also describes the techniques respondents used to account for the re...

2006-12-18T23:59:59.000Z

302

Enterprise Risk Management (ERM) Framework for Directives  

Directives, Delegations, and Requirements

Explains the new ERM framework for developing, revising, and reviewing directives. This memo directs the Office of Management to institutionalize ERM into the ...

2012-07-09T23:59:59.000Z

303

Extremely Hazardous Substances Risk Management Act (Delaware)  

Energy.gov (U.S. Department of Energy (DOE))

This act lays out provisions for local governments to implement regulations and standards for the management of extremely hazardous substances, which are defined and categorized as follows:

304

Electricity derivatives and risk management S.J. Denga,*  

E-Print Network (OSTI)

Electricity derivatives and risk management S.J. Denga,* , S.S. Orenb a School of Industrial Engineering and Operations Research, University of California, Berkeley, CA 94720, USA Abstract Electricity of electricity production and distribution. Uncontrolled exposure to market price risks can lead to devastating

305

Program on Technology Innovation: Managing the Risks of Climate Policies  

Science Conference Proceedings (OSTI)

Climate policy creates substantial risks and opportunities for companies in the electric sector and the broader energy sector. Understanding these risks and making investment choices that explicitly recognize future policy uncertainty are critical to effective risk management. Today, many electric companies are actively considering substantial investments in new capacity. The technology choices these companies make and the financial return on these investments are integrally tied to future environmental ...

2005-12-22T23:59:59.000Z

306

Resource management plan for the Oak Ridge Reservation  

SciTech Connect

A plan for management of the wildlife resources on the US Department of Energy's Oak Ridge Reservation is outlined in this document. Management includes wildlife population control (hunts, trapping, and removal), handling specific problems with wildlife, restoration of species, coordination with researchers on wildlife studies, preservation and management of habitats, and law enforcement. Wildlife resources are divided into five categories, each with a specific set of objectives and procedures for obtaining these objectives. These categories are (1) species-richness management to ensure that all resident wildlife species exist on the Reservation in viable numbers; (2) featured species management to produce selected species in desired numbers on designated land units; (3) management of game species for research, education, recreation, and public safety, (4) endangered species management designed to preserve and protect both the species and habitats critical to the survival of those species; and (5) pest management. Achievement of the objectives is a joint effort between the Tennessee Wildlife Resources Agency and the Oak Ridge National Laboratory's Environmental Sciences Division.

Parr, P.D. (Oak Ridge National Lab., TN (United States)); Evans, J.W. (Tennessee Wildlife Resources Agency, Knoxville, TN (United States))

1992-06-01T23:59:59.000Z

307

Resource management plan for the Oak Ridge Reservation  

SciTech Connect

A plan for management of the wildlife resources on the US Department of Energy's Oak Ridge Reservation is outlined in this document. Management includes wildlife population control (hunts, trapping, and removal), handling specific problems with wildlife, restoration of species, coordination with researchers on wildlife studies, preservation and management of habitats, and law enforcement. Wildlife resources are divided into five categories, each with a specific set of objectives and procedures for obtaining these objectives. These categories are (1) species-richness management to ensure that all resident wildlife species exist on the Reservation in viable numbers; (2) featured species management to produce selected species in desired numbers on designated land units; (3) management of game species for research, education, recreation, and public safety, (4) endangered species management designed to preserve and protect both the species and habitats critical to the survival of those species; and (5) pest management. Achievement of the objectives is a joint effort between the Tennessee Wildlife Resources Agency and the Oak Ridge National Laboratory's Environmental Sciences Division.

Parr, P.D. (Oak Ridge National Lab., TN (United States)); Evans, J.W. (Tennessee Wildlife Resources Agency, Knoxville, TN (United States))

1992-06-01T23:59:59.000Z

308

Risk Management Techniques and Practice Workshop Workshop Report  

Science Conference Proceedings (OSTI)

At the request of the Department of Energy (DOE) Office of Science (SC), Lawrence Livermore National Laboratory (LLNL) hosted a two-day Risk Management Techniques and Practice (RMTAP) workshop held September 18-19 at the Hotel Nikko in San Francisco. The purpose of the workshop, which was sponsored by the SC/Advanced Scientific Computing Research (ASCR) program and the National Nuclear Security Administration (NNSA)/Advanced Simulation and Computing (ASC) program, was to assess current and emerging techniques, practices, and lessons learned for effectively identifying, understanding, managing, and mitigating the risks associated with acquiring leading-edge computing systems at high-performance computing centers (HPCCs). Representatives from fifteen high-performance computing (HPC) organizations, four HPC vendor partners, and three government agencies attended the workshop. The overall workshop findings were: (1) Standard risk management techniques and tools are in the aggregate applicable to projects at HPCCs and are commonly employed by the HPC community; (2) HPC projects have characteristics that necessitate a tailoring of the standard risk management practices; (3) All HPCC acquisition projects can benefit by employing risk management, but the specific choice of risk management processes and tools is less important to the success of the project; (4) The special relationship between the HPCCs and HPC vendors must be reflected in the risk management strategy; (5) Best practices findings include developing a prioritized risk register with special attention to the top risks, establishing a practice of regular meetings and status updates with the platform partner, supporting regular and open reviews that engage the interests and expertise of a wide range of staff and stakeholders, and documenting and sharing the acquisition/build/deployment experience; and (6) Top risk categories include system scaling issues, request for proposal/contract and acceptance testing, and vendor technical or business problems. HPC, by its very nature, is an exercise in multi-level risk management. Every aspect of stewarding HPCCs into the petascale era, from identification of the program drivers to the details of procurement actions and simulation environment component deployments, represents unprecedented challenges and requires effective risk management. The fundamental purpose of this workshop was to go beyond risk management processes as such and learn how to weave effective risk management practices, techniques, and methods into all aspects of migrating HPCCs into the next generation of leadership computing systems. This workshop was a follow-on to the Petascale System Integration Workshop hosted by Lawrence Berkeley National Laboratory (LBNL)/NERSC last year. It was intended to leverage and extend the risk management experience of the participants by looking for common best practices and unique processes that have been especially successful. This workshop assessed the effectiveness of tools and techniques that are or could be helpful in HPCC risk management, with a special emphasis on how practice meets process. As the saying goes: 'In theory, there is no difference between theory and practice. In practice there is'. Finally, the workshop brought together a network of experts who shared information as technology moves into the petascale era and beyond.

Quinn, T; Zosel, M

2008-12-02T23:59:59.000Z

309

Revised management plan, milestone plan, cost plan, and manpower plan. Sixth and seventh monthly status reports, October 1-November 30, 1978  

DOE Green Energy (OSTI)

The following are included: project background and discussion, technical progress reports for all subtasks, contract management summary report, milestone schedule and status report, milestone log, cost plans, cost management reports, manpower plans, and manpower management reports. The following appendices are included: selection of heat pumps simulation locations, economic computations, fuel costs, system studies, recommended methodology for calculating residential load models, potential performance of heat pumps, data required from cooling contractors, cooling locations, thermal outputs: cooling, recommended inputs for the 25 ton advanced cooling simulation study, meteorological data, and contract modification. (MHR)

None,

1978-01-01T23:59:59.000Z

310

Safety Analysis, Hazard and Risk Evaluations [Nuclear Waste Management  

NLE Websites -- All DOE Office Websites (Extended Search)

Safety Analysis, Hazard Safety Analysis, Hazard and Risk Evaluations Nuclear Fuel Cycle and Waste Management Technologies Overview Modeling and analysis Unit Process Modeling Mass Tracking System Software Waste Form Performance Modeling Safety Analysis, Hazard and Risk Evaluations Development, Design, Operation Overview Systems and Components Development Expertise System Engineering Design Other Major Programs Work with Argonne Contact us For Employees Site Map Help Join us on Facebook Follow us on Twitter NE Division on Flickr Nuclear Waste Management using Electrometallurgical Technology Safety Analysis, Hazard and Risk Evaluations Bookmark and Share NE Division personnel had a key role in the creation of the FCF Final Safety Analysis Report (FSAR), FCF Technical Safety Requirements (TSR)

311

Software configuration management plan for the Hanford site technical database  

Science Conference Proceedings (OSTI)

The Hanford Site Technical Database (HSTD) is used as the repository/source for the technical requirements baseline and programmatic data input via the Hanford Site and major Hanford Project Systems Engineering (SE) activities. The Hanford Site SE effort has created an integrated technical baseline for the Hanford Site that supports SE processes at the Site and project levels which is captured in the HSTD. The HSTD has been implemented in Ascent Logic Corporation (ALC) Commercial Off-The-Shelf (COTS) package referred to as the Requirements Driven Design (RDD) software. This Software Configuration Management Plan (SCMP) provides a process and means to control and manage software upgrades to the HSTD system.

GRAVES, N.J.

1999-05-10T23:59:59.000Z

312

Project L-070, ``300 Area process sewer piping system upgrade`` Project Management Plan  

Science Conference Proceedings (OSTI)

This document is the project management plan for Project L-070, 300 Area process sewer system upgrades.

Wellsfry, H.E.

1994-09-16T23:59:59.000Z

313

Project Management Plan (PMP), W-364, 209E septic system upgrade, 200 East Area  

SciTech Connect

The document is the Project Management Plan (PMP) of the design and installation of the 209E Septic System Upgrade.

Lott, D.T.

1994-09-20T23:59:59.000Z

314

Waste management plan for Hanford spent nuclear fuel characterization activities  

SciTech Connect

A joint project was initiated between Westinghouse Hanford Company (WHC) and Pacific Northwest Laboratory (PNL) to address critical issues associated with the Spent Nuclear Fuel (SNF) stored at the Hanford Site. Recently, particular attention has been given to remediation of the SNF stored in the K Basins. A waste management plan (WMP) acceptable to both parties is required prior to the movement of selected material to the PNL facilities for examination. N Reactor and Single Pass Reactor (SPR) fuel has been stored for an extended period of time in the N Reactor, PUREX, K-East, and K-West Basins. Characterization plans call for transport of fuel material form the K Basins to the 327 Building Postirradiation Testing Laboratory (PTL) in the 300 Area for examination. However, PNL received a directive stating that no examination work will be started in PNL hot cell laboratories without an approved disposal route for all waste generated related to the activity. Thus, as part of the Characterization Program Management Plan for Hanford Spent Nuclear Fuel, a waste management plan which will ensure that wastes generated as a result of characterization activities conducted at PNL will be accepted by WHC for disposition is required. This document contains the details of the waste handling plan that utilizes, to the greatest extent possible, established waste handling and disposal practices at Hanford between PNL and WHC. Standard practices are sufficient to provides for disposal of most of the waste materials, however, special consideration must be given to the remnants of spent nuclear fuel elements following examination. Fuel element remnants will be repackaged in an acceptable container such as the single element canister and returned to the K Basins for storage.

Chastain, S.A. [Westinghouse Hanford Co., Richland, WA (United States); Spinks, R.L. [Pacific Northwest Lab., Richland, WA (United States)

1994-10-17T23:59:59.000Z

315

Moving Forward with the Electric Sector Cybersecurity Risk Management  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Moving Forward with the Electric Sector Cybersecurity Risk Moving Forward with the Electric Sector Cybersecurity Risk Management Maturity Initiative Moving Forward with the Electric Sector Cybersecurity Risk Management Maturity Initiative January 20, 2012 - 10:28am Addthis Since the January 5, 2012 launch of the "Electric Sector Cybersecurity Risk Management Maturity" program, a White House initiative led by the Department of Energy in partnership with the Department of Homeland Security (DHS) to create a more comprehensive and consistent approach to protecting the nation's electric grid against cyber attacks, we have seen a tremendous response from the electric sector. More and more companies are stepping forward, saying they want to participate. We are capitalizing on the growing momentum in several ways. One of our

316

Application of Risk Assessment and Management to Nuclear Safety |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Application of Risk Assessment and Management to Nuclear Safety Application of Risk Assessment and Management to Nuclear Safety Application of Risk Assessment and Management to Nuclear Safety September 20, 2012 Presenter: Commissioner George Apostolakis US Nuclear Regulatory Commission Topics covered: Management of (unquantified at the time) uncertainty was always a concern. Defense-in-depth and safety margins became embedded in the regulations. "Defense-in-Depth is an element of the NRC's safety philosophy that employs successive compensatory measures to prevent accidents or mitigate damage if a malfunction, accident, or naturally caused event occurs at a nuclear facility." [Commission's White Paper, February 1999] Design Basis Accidents are postulated accidents that a nuclear facility must be designed and built to withstand without loss to the

317

OCRWM Systems Engineering Management Plan (SEMP). Revision 3  

SciTech Connect

The Office of Civilian Radioactive Waste Management Systems Engineering Management Plan (OCRWM SEMP) specifies the technical management approach for the development of the waste management system, and specifies the approach for the development of each of the system elements -- the waste acceptance system, the transportation system, the Monitored Retrievable Storage (MRS) facility, and the mined geologic disposal system, which includes site characterization activity. The SEMP also delineates how systems engineering will be used by OCRWM to describe the system development process; it identifies responsibilities for its implementation, and specifies the minimum requirements for systems engineering. It also identifies the close interrelationship of system engineering and licensing processes. This SEMP, which is a combined OCRWM and M&O SEMP, is part of the top-level program documentation and is prepared in accordance with the direction provided in the Program Management System Manual (PMSM). The relationship of this document to other top level documents in the CRWMS document hierarchy is defined in the PMSM. A systems engineering management plan for each project, which specifies the actions to be taken in implementing systems engineering at the project level, shall be prepared by the respective project managers. [``Program`` refers to the CRWMS-wide activity and ``project`` refers to that level responsible for accomplishing the specific activities of that segment of the program.] The requirements for the project level SEMPs are addressed in Section 4.2.2.2. They represent the minimum set of requirements, and do not preclude the broadening of systems engineering activities to meet the specific needs of each project.

1994-06-01T23:59:59.000Z

318

Risk and Work Configuration Management as a Function of Integrated Safety Management  

Science Conference Proceedings (OSTI)

National Security Technologies, LLC (NSTec), has established a work management program and corresponding electronic Facilities and Operations Management Information System (e-FOM) to implement Integrated Safety Management (ISM). The management of work scopes, the identification of hazards, and the establishment of implementing controls are reviewed and approved through electronic signatures. Through the execution of the program and the implementation of the electronic system, NSTec staff work within controls and utilize feedback and improvement process. The Integrated Work Control Manual further implements the five functions of ISM at the Activity level. By adding the Risk and Work Configuration Management program, NSTec establishes risk acceptance (business and physical) for liabilities within the performance direction and work management processes. Requirements, roles, and responsibilities are specifically identified in the program while e-FOM provides the interface and establishes the flowdown from the Safety Chain to work and facilities management processes to company work-related directives, and finally to Subject Matter Expert concurrence. The Program establishes, within the defined management structure, management levels for risk identification, risk mitigation (controls), and risk acceptance (business and physical) within the Safety Chain of Responsibility. The Program also implements Integrated Safeguards and Security Management within the NSTec Safety Chain of Responsibility. Once all information has been entered into e-FOM, approved, and captured as data, the information becomes searchable and sortable by hazard, location, organization, mitigating controls, etc.

Lana Buehrer, Michele Kelly, Fran Lemieux, Fred Williams

2007-11-30T23:59:59.000Z

319

Risk-embedded Bayesian acceptance sampling plans via conditional value-at-risk with Type II censoring  

Science Conference Proceedings (OSTI)

An acceptance sampling plan is usually determined by minimizing the expectation of the sum of the relevant costs involved. This expected cost minimization approach, however, could result in a great cost at a probability that is unacceptable to a decision ... Keywords: Bayesian acceptance sampling, Conditional value-at-risk, Life distribution, Reliability, Risk aversion, Type II censoring

Chung-Chi Hsieh, Yu-Ting Lu

2013-08-01T23:59:59.000Z

320

Westinghouse Hanford Company FY 1995 Materials Management Plan (MMP)  

SciTech Connect

The safe and sound operation of facilities and storage of nuclear material are top priorities within Hanford`s environmental management, site restoration mission. The projected materials estimates, based on the Materials Management Plan (MMP) assumptions outlined below, were prepared for Department of Energy (DOE) use in long-range planning. The Hanford MMP covers the period FY 1995 through FY 2005, as directed by DOE. All DOE Richland Operations (RL) Office facilities are essentially funded by the Office of Transition and Facilities Management, Environmental Restoration and Waste Management (EM). These facilities include PUREX, the UO{sub 3} plant, N-Reactor, T-Plant, K-Basins, FFTF, PFP and the 300 Area Fuel Fabrication facilities. Currently DP provides partial funding for the latter two facilities. Beginning in FY 1996 (in accordance with DOE-HQ MMP assumptions), EM will fund expenses related to the storage, monitoring, and safeguarding of all Special Nuclear Material (SNM) in the PFP. Ownership and costs related to movement and/or stabilization of that material will belong to EM programs (excluding NE material). It is also assumed that IAEA will take over inventory validation and surveillance of EM owned SNM at this time (FY 1996).

Higginson, M.C.

1994-10-01T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


321

Applying an Integrated Risk Management Approach to Risks from Severe Geomagnetic Disturbances  

Science Conference Proceedings (OSTI)

High-impact, low-frequency (HILF) events such as coordinated risk attacks, pandemics, severe geomagnetic disturbances (GMDs), electromagnetic pulse weapons (EMPs), and high-altitude electromagnetic pulse weapons (HEMPs) have the potential to cause significant damage to the power grid; but because they are rare or have never occurred the industry has little experience in dealing with them. An integrated risk-management strategy is needed to address them. Such a strategy could include a thorough risk ...

2012-10-31T23:59:59.000Z

322

Tank waste remediation system systems engineering management plan  

Science Conference Proceedings (OSTI)

This Systems Engineering Management Plan (SEMP) describes the Tank Waste Remediation System (TWRS) implementation of the US Department of Energy (DOE) systems engineering policy provided in 97-IMSD-193. The SEMP defines the products, process, organization, and procedures used by the TWRS Project to implement the policy. The SEMP will be used as the basis for tailoring the systems engineering applications to the development of the physical systems and processes necessary to achieve the desired end states of the program. It is a living document that will be revised as necessary to reflect changes in systems engineering guidance as the program evolves. The US Department of Energy-Headquarters has issued program management guidance, DOE Order 430. 1, Life Cycle Asset Management, and associated Good Practice Guides that include substantial systems engineering guidance.

Peck, L.G.

1998-01-08T23:59:59.000Z

323

Wildlife Management Plan for the Oak Ridge Reservation  

Science Conference Proceedings (OSTI)

This document outlines a plan for management of the wildlife resources on the Department of Energy's (DOE's) Oak Ridge Reservation. Management includes wildlife population control through hunting, trapping, removal, and habitat manipulation; wildlife damage control; restoration of wildlife species; preservation, management, and enhancement of wildlife habitats; coordination of wildlife studies and characterization of areas; and law enforcement. Wildlife resources are divided into several categories, each with a specific set of objectives and procedures for attaining them. These objectives are management of (1) wildlife habitats to ensure that all resident wildlife species exist on the Reservation in viable numbers; (2) featured species to produce selected species in desired numbers on designated land units; (3) game species for research, education, recreation, and public safety; (4) the Three Bend Scenic and Wildlife Management Refuge Area; (5) nuisance wildlife, including nonnative species, to achieve adequate population control for the maintenance of health and safety on the Reservation; (6) sensitive species (i.e., state or federally listed as endangered, threatened, of special concern, or in need of management) through preservation and protection of both the species and habitats critical to the survival of those species; and (7) wildlife disease. Achievement of the objectives is a joint effort between the Tennessee Wildlife Resources Agency (TWRA) and the Oak Ridge National Laboratory through agreements between TWRA and DOE and between DOE and UT-Battelle, LLC.

Giffen, Neil R [ORNL; Evans, James W. [TWRA; Parr, Patricia Dreyer [ORNL

2007-10-01T23:59:59.000Z

324

Software requirements specification for the program analysis and control system risk management module  

Science Conference Proceedings (OSTI)

TWR Program Analysis and Control System Risk Module is used to facilitate specific data processes surrounding the Risk Management program of the Tank Waste Retrieval environment. This document contains the Risk Management system requirements of the database system.

SCHAEFER, J.C.

1999-06-02T23:59:59.000Z

325

Strategic Energy Management Plan For Fort Buchanan, Puerto Rico  

SciTech Connect

This document reports findings and recommendations as a result of a design assistance project with Fort Buchanan with the goals of developing a Strategic Energy Management Plan for the Site. A strategy has been developed with three major elements in mind: 1) development of a strong foundation from which to build, 2) understanding technologies that are available, and 3) exploring financing options to fund the implementation of improvements. The objective of this report is to outline a strategy that can be used by Fort Buchanan to further establish an effective energy management program. Once a strategy is accepted, the next step is to take action. Some of the strategies defined in this Plan may be implemented directly. Other strategies may require the development of a more sophisticated tactical, or operational, plan to detail a roadmap that will lead to successful realization of the goal. Similarly, some strategies are not single events. Rather, some strategies will require continuous efforts to maintain diligence or to change the culture of the Base occupants and their efforts to conserve energy resources.

Parker, Steven A.; Hunt, W. D.

2001-10-31T23:59:59.000Z

326

WIPP Facility Work Plan for Solid Waste Management Units  

Science Conference Proceedings (OSTI)

This 2001 Facility Work Plan (FWP) has been prepared as required by Module VII, Section VII.M.1 of the Waste Isolation Pilot Plant (WIPP) Hazardous Waste Facility Permit, NM4890139088-TSDF (the Permit); (NMED, 1999a), and incorporates comments from the New Mexico Environment Department (NMED) received on December 6, 2000 (NMED, 2000a). This February 2001 FWP describes the programmatic facility-wide approach to future investigations at Solid Waste Management Units (SWMUs) and Areas of Concern (AOCs) specified in the Permit. The permittees are evaluating data from previous investigations of the SWMUs and AOCs against the newest guidance proposed by the NMED. Based on these data, the permittees expect that no further sampling will be required and that a request for No Further Action (NFA) at the SWMUs and AOCs will be submitted to the NMED. This FWP addresses the current Permit requirements. It uses the results of previous investigations performed at WIPP and expands the investigations as required by the Permit. As an alternative to the Resource Conservation and Recovery Act (RCRA) Facility Investigation (RFI) specified in Module VII of the Permit, current NMED guidance identifies an Accelerated Corrective Action Approach (ACAA) that may be used for any SWMU or AOC (NMED, 1998). This accelerated approach is used to replace the standard RFI Work Plan and Report sequence with a more flexible decision-making approach. The ACAA process allows a Facility to exit the schedule of compliance contained in the Facilitys Hazardous and Solid Waste Amendments (HSWA) permit module and proceed on an accelerated time frame. Thus, the ACAA process can be entered either before or after an RFI Work Plan. According to the NMED's guidance, a facility can prepare an RFI Work Plan or Sampling and Analysis Plan (SAP) for any SWMU or AOC (NMED, 1998). Based on this guidance, a SAP constitutes an acceptable alternative to the RFI Work Plan specified in the Permit.

Washington TRU Solutions LLC

2001-02-25T23:59:59.000Z

327

Risk-Managed Technical Specifications (RMTS) Guidelines: Interim Development Report  

Science Conference Proceedings (OSTI)

This report presents nuclear utilities with a technical framework and associated general guidance for implementation of risk-managed technical specifications (RMTS) as a partial replacement for existing conventional plant technical specifications. This interim report, intended for both Westinghouse and non-Westinghouse reactor plants and for future reference and application by the Nuclear Energy Institute (NEI), will probably be updated in the future as risk-informed applications technology continues to ...

2003-11-21T23:59:59.000Z

328

PUREX/UO{sub 3} deactivation project management plan  

Science Conference Proceedings (OSTI)

From 1955 through 1990, the Plutonium-Uranium Extraction Plant (PUREX) provided the United States Department of Energy Hanford Site with nuclear fuel reprocessing capability. It operated in sequence with the Uranium Trioxide (UO{sub 3}) Plant, which converted the PUREX liquid uranium nitrate product to solid UO{sub 3} powder. Final UO{sub 3} Plant operation ended in 1993. In December 1992, planning was initiated for the deactivation of PUREX and UO{sub 3} Plant. The objective of deactivation planning was to identify the activities needed to establish a passively safe, environmentally secure configuration at both plants, and ensure that the configuration could be retained during the post-deactivation period. The PUREX/UO{sub 3} Deactivation Project management plan represents completion of the planning efforts. It presents the deactivation approach to be used for the two plants, and the supporting technical, cost, and schedule baselines. Deactivation activities concentrate on removal, reduction, and stabilization of the radioactive and chemical materials remaining at the plants, and the shutdown of the utilities and effluents. When deactivation is completed, the two plants will be left unoccupied and locked, pending eventual decontamination and decommissioning. Deactivation is expected to cost $233.8 million, require 5 years to complete, and yield $36 million in annual surveillance and maintenance cost savings.

Washenfelder, D.J.

1993-12-01T23:59:59.000Z

329

Federal Energy Management Program: Energy Security Planning for Sustainable  

NLE Websites -- All DOE Office Websites (Extended Search)

Security Planning for Sustainable Buildings Security Planning for Sustainable Buildings For energy security, Federal facility managers have a responsibility to consider a broad array of potential threats and incident scenarios. An underlying process or methodology is essential to comprehensively and intelligently address all elements of energy security analysis. Given recent blackouts and concerns about vulnerable infrastructure, many public and private organizations are taking steps to ensure reliable power and continuity of operations in the event of future outages. Some government facilities have the capacity to survive short-term power outages, but are now evaluating whether their back-up power capabilities are sufficient to serve their most critical needs during a prolonged outage.

330

Waste Isolation Pilot Plant Groundwater Protection Management Program Plan  

SciTech Connect

U.S. Department of Energy (DOE) Order 5400.1, General Environmental Protection Program, requires each DOE site to prepare a Groundwater Protection Management Program Plan. This document fulfills the requirement for the Waste Isolation Pilot Plant (WIPP). This document was prepared by the Hydrology Section of the Westinghouse TRU Solutions LLC (WTS) Environmental Compliance Department, and it is the responsibility of this group to review the plan annually and update it every three years. This document is not, nor is it intended to be, an implementing document that sets forth specific details on carrying out field projects or operational policy. Rather, it is intended to give the reader insight to the groundwater protection philosophy at WIPP.

Washington TRU Solutions

2002-09-24T23:59:59.000Z

331

DOE-NE Proliferation and Terrorism Risk Assessment: FY12 Plans Update  

SciTech Connect

This presentation provides background information on FY12 plans for the DOE Office of Nuclear Energy Proliferation and Terrorism Risk Assessment program. Program plans, organization, and individual project elements are described. Research objectives are: (1) Develop technologies and other solutions that can improve the reliability, sustain the safety, and extend the life of current reactors; (2) Develop improvements in the affordability of new reactors to enable nuclear energy; (3) Develop Sustainable Nuclear Fuel Cycles; and (4) Understand and minimize the risks of nuclear proliferation and terrorism - Goal is to enable the use of risk information to inform NE R&D program planning.

Sadasivan, Pratap [Los Alamos National Laboratory

2012-06-21T23:59:59.000Z

332

A comprehensive GIS-based poultry litter management system for nutrient management planning and litter transportation  

Science Conference Proceedings (OSTI)

Confined poultry (broiler) production in Alabama results in about 1.8 million tons of litter annually. Because poultry production mainly occurs in the Appalachian Plateau region of north Alabama, this region suffers from excessive land application of ... Keywords: Broiler litter, Comprehensive nutrient management plan, Decision support system, Geographic information system, Poultry litter, Transportation analysis

M. S. Kang; P. Srivastava; T. Tyson; J. P. Fulton; W. F. Owsley; K. H. Yoo

2008-12-01T23:59:59.000Z

333

Civilian radioactive waste management program plan. Revision 2  

SciTech Connect

This revision of the Civilian Radioactive Waste Management Program Plan describes the objectives of the Civilian Radioactive Waste management Program (Program) as prescribed by legislative mandate, and the technical achievements, schedule, and costs planned to complete these objectives. The Plan provides Program participants and stakeholders with an updated description of Program activities and milestones for fiscal years (FY) 1998 to 2003. It describes the steps the Program will undertake to provide a viability assessment of the Yucca Mountain site in 1998; prepare the Secretary of Energy`s site recommendation to the President in 2001, if the site is found to be suitable for development as a repository; and submit a license application to the Nuclear Regulatory Commission in 2002 for authorization to construct a repository. The Program`s ultimate challenge is to provide adequate assurance to society that an operating geologic repository at a specific site meets the required standards of safety. Chapter 1 describes the Program`s mission and vision, and summarizes the Program`s broad strategic objectives. Chapter 2 describes the Program`s approach to transform strategic objectives, strategies, and success measures to specific Program activities and milestones. Chapter 3 describes the activities and milestones currently projected by the Program for the next five years for the Yucca Mountain Site Characterization Project; the Waste Acceptance, Storage and Transportation Project; ad the Program Management Center. The appendices present information on the Nuclear Waste Policy Act of 1982, as amended, and the Energy Policy Act of 1992; the history of the Program; the Program`s organization chart; the Commission`s regulations, Disposal of High-Level Radioactive Wastes in geologic Repositories; and a glossary of terms.

1998-07-01T23:59:59.000Z

334

Martin Marietta Energy Systems, Inc., Groundwater Program Management Plan  

Science Conference Proceedings (OSTI)

The purpose of the Martin Marietta Energy Systems, Inc., (Energy Systems) Groundwater Program Management Plan is to define the function, organizational structure (including associated matrix organizations), interfaces, roles and responsibilities, authority, and relationship to the Department of Energy for the Energy Systems Groundwater Program Office (GWPO). GWPO is charged with the responsibility of coordinating all components of the groundwater program for Energy Systems. This mandate includes activities at the three Oak Ridge facilities [Oak Ridge National Laboratory, the Oak Ridge Y-12 Plant, and the Oak Ridge K-25 Site], as well as the Paducah and Portsmouth Gaseous Diffusion Plants.

Early, T.O.

1994-05-01T23:59:59.000Z

335

Standard Review Plan Preparation for Facility Operations Strengthening Line Management Oversight and  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Standard Review Plan Standard Review Plan Preparation for Facility Operations Strengthening Line Management Oversight and Federal Monitoring of Nuclear Facilities August 2013 2 OFFICE OF ENVIRONMENTAL MANAGEMENT Standard Review Plan (SRP) Preparation for Facility Operations Applicability CD-0 CD-1 CD-2 CD-3 CD-4 Operation Post Operation August 2013 3 Table of Contents Objective ......................................................................................................................................... 4 Requirements .................................................................................................................................. 4 Primary References ......................................................................................................................... 6

336

Comparative risk analysis for the Rocky Flats Plant integrated project planning  

Science Conference Proceedings (OSTI)

The Rocky Flats Plant is developing, with active stakeholder a comprehensive planning strategy that will support transition of the Rocky Flats Plant from a nuclear weapons production facility to site cleanup and final disposition. Final disposition of the Rocky Flats Plant materials and contaminants requires consideration of the interrelated nature of sitewide problems, such as material movement and disposition, facility and land use endstates, costs relative risks to workers and the public, and waste disposition. Comparative Risk Analysis employs both incremental risk and cumulative risk evaluations to compare risks from postulated options or endstates. These postulated options or endstates can be various remedial alternatives, or future endstate uses of federal agency land. Currently, there does not exist any approved methodology that aggregates various incremental risk estimates. Comparative Risk Analysis has been developed to aggregate various incremental risk estimates to develop a site cumulative risk estimate. This paper discusses development of the Comparative Risk Analysis methodology, stakeholder participation and lessons learned from these challenges.

Jones, M.E.; Shain, D.I.

1994-05-01T23:59:59.000Z

337

Managing transmission curtailment risk in wholesale power markets  

SciTech Connect

Risk resulting from transmission loading relief calls made by transmission system operators can be managed with information estimated by a statistical model capable of predicting one day in advance the probability that a particular wholesale power transaction might be curtailed. The model predicts this probability with a reasonable degree of accuracy using information on variables that can be obtained publicly. (author)

Morey, Mathew J.; Kirsch, Laurence D.

2009-11-15T23:59:59.000Z

338

Managing Risk in Disaster Scenarios with Autonomous Robots  

E-Print Network (OSTI)

of damage. · The initial response to the disaster is limited to only those local rescue assets that have had some limited use in disaster response, most notably the responses led by the Center for Robot1 Managing Risk in Disaster Scenarios with Autonomous Robots Daniel P. Stormont and Vicki H. Allan

Allan, Vicki H.

339

Modelling and forecasting wind speed intensity for weather risk management  

Science Conference Proceedings (OSTI)

The main interest of the wind speed modelling is on the short-term forecast of wind speed intensity and direction. Recently, its relationship with electricity production by wind farms has been studied. In fact, electricity producers are interested in ... Keywords: ARFIMA-FIGARCH, Auto Regressive Gamma, Gamma Auto Regressive, Weather risk management, Wind speed modelling, Wind speed simulation

Massimiliano Caporin; Juliusz Pre

2012-11-01T23:59:59.000Z

340

Distribution Applications of the Asset and Risk Management (ARM) Workstation  

Science Conference Proceedings (OSTI)

Significant opportunities exist to improve maintenance, operation, and asset utilization of distribution systems and equipment. To improve the reactive (run-to-failure) maintenance practices typically employed today, a key hurdle to overcome is the lack of needed distribution system and equipment data. This report describes approaches that enable utilities to overcome this hurdle, reduce maintenance costs, and improve operations using current and planned distribution applications of the Asset and Risk Ma...

2004-12-13T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


341

RCRA Groundwater Monitoring Plan for Single-Shell Tank Waste Management Area A-AX at the Hanford Site  

Science Conference Proceedings (OSTI)

This document describes the interim status groundwater monitoring plan for Waste Management Area A-AX.

Narbutovskih, Susan M.; Horton, Duane G.

2001-01-18T23:59:59.000Z

342

Configuration Management Plan for Tank Farm Restoration and Safe Operations Project W-314  

Science Conference Proceedings (OSTI)

The Configuration Management Plan for Project W-314 describes the systems, processes and procedures for implementation of applicable configuration management practices described in HNF-0842, Volume 111, Section 3.1, ''Configuration Management Implementation''. This plan is tailored specifically for use by Project W-314.

MCGREW, D.L.

2000-04-19T23:59:59.000Z

343

CH2M Hill Hanford Group Inc (CHG) Information Resource Management (IRM) Strategic Plan  

SciTech Connect

The CH2M HILL Hanford Group, Inc. (CHG), Information Resource Management Strategic Plan is the top-level planning document for applying information and information resource management to achieve the CHG mission for the management of the River Protection Project waste tank farm.

NELSON, R.L.

2000-06-06T23:59:59.000Z

344

Robust, goal-directed plan execution with bounded risk  

E-Print Network (OSTI)

There is an increasing need for robust optimal plan execution for multi-agent systems in uncertain environments, while guaranteeing an acceptable probability of success. For example, a fleet of unmanned aerial vehicles ...

Ono, Masahiro, Ph. D. Massachusetts Institute of Technology

2012-01-01T23:59:59.000Z

345

WIPP Facility Work Plan for Solid Waste Management Units  

Science Conference Proceedings (OSTI)

This 2002 Facility Work Plan (FWP) has been prepared as required by Module VII, Permit Condition VII.U.3 of the Waste Isolation Pilot Plant (WIPP) Hazardous Waste Facility Permit, NM4890139088-TSDF (the Permit) (New Mexico Environment Department [NMED], 1999a), and incorporates comments from the NMED received on December 6, 2000 (NMED, 2000a). This February 2002 FWP describes the programmatic facility-wide approach to future investigations at Solid Waste Management Units (SWMU) and Areas of Concern (AOC) specified in the Permit. The Permittees are evaluating data from previous investigations of the SWMUs and AOCs against the most recent guidance proposed by the NMED. Based on these data, and completion of the August 2001 sampling requested by the NMED, the Permittees expect that no further sampling will be required and that a request for No Further Action (NFA) at the SWMUs and AOCs will be submitted to the NMED. This FWP addresses the current Permit requirements. It uses the results of previous investigations performed at WIPP and expands the investigations as required by the Permit. As an alternative to the Resource Conservation and Recovery Act (RCRA) Facility Investigation (RFI) specified in Module VII of the Permit, current NMED guidance identifies an Accelerated Corrective Action Approach (ACAA) that may be used for any SWMU or AOC (NMED, 1998). This accelerated approach is used to replace the standard RFI Work Plan and Report sequence with a more flexible decision-making approach. The ACAA process allows a facility to exit the schedule of compliance contained in the facility's Hazardous and Solid Waste Amendments (HSWA) permit module and proceed on an accelerated time frame. Thus, the ACAA processcan be entered either before or after an RFI Work Plan. According to the NMED's guidance, a facility can prepare an RFI Work Plan or Sampling and Analysis Plan (SAP) for any SWMU or AOC (NMED, 1998). Based on this guidance, a SAP constitutes an acceptable alternative to the RFI Work Plan specified in the Permit. The NMED accepted that the Permittees are using the ACAA in a letter dated April 20, 2000.

Washington TRU Solutions LLC

2002-02-14T23:59:59.000Z

346

Research and Development Planning: Program 57 Siting, Vegetation Management, and Avian Issues  

Science Conference Proceedings (OSTI)

This report documents the outcome of two planning sessions conducted in 2006 and 2007 to support research and development planning for Program 57Rights of Way: Siting, Vegetation Management, and Avian Issues.

2007-06-18T23:59:59.000Z

347

Project Management Plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory  

Science Conference Proceedings (OSTI)

The purpose of the Isotopes Facilities Deactivation Project (IFDP) is to place former isotopes production facilities at the Oak Ridge National Laboratory in a safe, stable, and environmentally sound condition suitable for an extended period of minimum surveillance and maintenance (S&M) and as quickly and economically as possible. Implementation and completion of the deactivation project will further reduce the already small risks to the environment and to public safety and health. Furthermore, the project should result in significant S&M cost savings in the future. The IFDP management plan has been prepared to document the project objectives, define organizational relationships and responsibilities, and outline the management control systems to be employed in the management of the project. The project has adopted a strategy to deactivate the simple facilities first, to reduce the scope of the project, and to gain experience before addressing more difficult facilities. A decision support system is being developed to identify those activities, that best promote the project mission and result in largest cost savings. The Work Plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory (Energy Systems 1994) defines the project schedule, the cost estimate, and the technical approach for the project.

NONE

1995-04-01T23:59:59.000Z

348

Work plan for conducting an ecological risk assessment at J-Field, Aberdeen Proving Ground, Maryland  

Science Conference Proceedings (OSTI)

The Environmental Management Division of Aberdeen Proving Ground (APG), Maryland, is conducting a remedial investigation and feasibility study (RI/FS) of the J-Field area at APG pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended. J-Field is within the Edgewood Area of APG in Harford County, Maryland, and activities at the Edgewood Area since World War II have included the development, manufacture, testing, and destruction of chemical agents and munitions. The J-Field site was used to destroy chemical agents and munitions by open burning and open detonation. This work plan presents the approach proposed to conduct an ecological risk assessment (ERA) as part of the RI/FS program at J-Field. This work plan identifies the locations and types of field studies proposed for each area of concern (AOC), the laboratory studies proposed to evaluate toxicity of media, and the methodology to be used in estimating doses to ecological receptors and discusses the approach that will be used to estimate and evaluate ecological risks at J-Field. Eight AOCs have been identified at J-Field, and the proposed ERA is designed to evaluate the potential for adverse impacts to ecological receptors from contaminated media at each AOC, as well as over the entire J-Field site. The proposed ERA approach consists of three major phases, incorporating field and laboratory studies as well as modeling. Phase 1 includes biotic surveys of the aquatic and terrestrial habitats, biological tissue sampling and analysis, and media toxicity testing at each AOC and appropriate reference locations. Phase 2 includes definitive toxicity testing of media from areas of known or suspected contamination or of media for which the Phase 1 results indicate toxicity or adverse ecological effects. In Phase 3, the uptake models initially developed in Phase 2 will be finalized, and contaminant dose to each receptor from all complete pathways will be estimated.

Hlohowskyj, I.; Hayse, J.; Kuperman, R. [Argonne National Lab., IL (United States). Environmental Assessment Div.] [and others

1995-03-01T23:59:59.000Z

349

Fermilab | Directorate | Office of Integrated Planning & Performance  

NLE Websites -- All DOE Office Websites (Extended Search)

Office of Integrated Planning & Performance Management (IPPM) Office of Integrated Planning & Performance Management (IPPM) Integrated Planning Diagram Integrated Planning Diagram [Download PPT] Mission: The Office of Integrated Planning and Performance Management (IPPM) within the Fermilab Directorate provides systems and management processes for institutional planning and performance assessment and evaluation. The office of IPPM leads multi-year, forward-looking planning and integration of institutional plans, programs, projects, operations and budgets. In addition it develops, implements and maintains integrated laboratory systems and management processes for strategic planning and goal setting, project and program oversight, enterprise risk management and performance planning and oversight. IPPM Facilitates:

350

Nuclear Safety Risk Management in Refueling Outage of Qinshan Nuclear Power Plant  

SciTech Connect

The NPP is used to planning maintenance, in-service inspection, surveillance test, fuel handling and design modification in the refueling outage; the operator response capability will be reduced plus some of the plant systems out of service or loss of power at this time. Based on 8 times refueling outage experiences of the Qinshan NPP, this article provide some good practice and lesson learned for the nuclear safety risk management focus at four safety function areas of Residual Heat Removal Capability, Inventory Control, Power availability and Reactivity control. (authors)

Meijing Wu; Guozhang Shen [Qinshan Nuclear power company (China)

2006-07-01T23:59:59.000Z

351

Daymet Follow-On Proposal: Data Management Plan R.B. Cook, M...  

NLE Websites -- All DOE Office Websites (Extended Search)

Data Management Plan was part of the NASA ROSES 2012 Proposal Daymet Follow-On: Surface Weather Data with Uncertainty Quantification for Terrestrial Ecosystem Process Models...

352

Waste Isolation Pilot Plant Land Management Plan DOE/WIPP-93...  

NLE Websites -- All DOE Office Websites (Extended Search)

with WIPP facility maintenance protocol) (see Waste Isolation Pilot Plant Land Management Plan DOEWIPP-93-004 64 Chapter 13, Maintenance and Work Control) to the road in...

353

High-level waste management technology program plan  

Science Conference Proceedings (OSTI)

The purpose of this plan is to document the integrated technology program plan for the Savannah River Site (SRS) High-Level Waste (HLW) Management System. The mission of the SRS HLW System is to receive and store SRS high-level wastes in a see and environmentally sound, and to convert these wastes into forms suitable for final disposal. These final disposal forms are borosilicate glass to be sent to the Federal Repository, Saltstone grout to be disposed of on site, and treated waste water to be released to the environment via a permitted outfall. Thus, the technology development activities described herein are those activities required to enable successful accomplishment of this mission. The technology program is based on specific needs of the SRS HLW System and organized following the systems engineering level 3 functions. Technology needs for each level 3 function are listed as reference, enhancements, and alternatives. Finally, FY-95 funding, deliverables, and schedules are s in Chapter IV with details on the specific tasks that are funded in FY-95 provided in Appendix A. The information in this report represents the vision of activities as defined at the beginning of the fiscal year. Depending on emergent issues, funding changes, and other factors, programs and milestones may be adjusted during the fiscal year. The FY-95 SRS HLW technology program strongly emphasizes startup support for the Defense Waste Processing Facility and In-Tank Precipitation. Closure of technical issues associated with these operations has been given highest priority. Consequently, efforts on longer term enhancements and alternatives are receiving minimal funding. However, High-Level Waste Management is committed to participation in the national Radioactive Waste Tank Remediation Technology Focus Area. 4 refs., 5 figs., 9 tabs.

Harmon, H.D.

1995-01-01T23:59:59.000Z

354

The design of a decision support system for supply chain risk management  

E-Print Network (OSTI)

Where can things go wrong? This deceptively simple question has fascinated mankind since time immemorial. The question in fact forms the basis of risk management. The focus of this thesis is the risk management of supply ...

Deshmukh, Vinay (Vinay D.)

2007-01-01T23:59:59.000Z

355

Evolutionary supply chain risk management : transforming culture for sustainable competitive advantage  

E-Print Network (OSTI)

In today's fast-paced and turbulent global economy, the topic of risk management has gained significant interest in the business and academic world. However, in practice, risk management remains rather underdeveloped and ...

Lvy, Romain (Romain Georges Jean)

2008-01-01T23:59:59.000Z

356

Ministry of Forests Forest Science ProgramLandslide Risk Case Studies in Forest Development Planning and Operations  

E-Print Network (OSTI)

Ministry of Forests Forest Science ProgramThe use of trade, firm, or corporation names in this publication is for the information and convenience of the reader. Such use does not constitute an official endorsement or approval by the Government of British Columbia of any product or service to the exclusion of any others that may also be suitable. This document should be regarded as technical information and not as government policy. National Library of Canada Cataloguing in Publication Data Main entry under title. Landslide risk case studies in forest development planning and operations (Land management handbook, ISSN 0229-1622; 56) Includes bibliographical references: p.

Mike Wise; Glenn Moore; Doug Vandine; Mike Wise; Glenn Moore; Doug Vandine

2004-01-01T23:59:59.000Z

357

Environmental guidelines for development of Cultural Resource Management plans. Final report  

Science Conference Proceedings (OSTI)

The purpose of this document is to provide guidelines to the DOE field managements with responsibility for the development of an individual Cultural Resource Management Plan for each DOE facility and program.

NONE

1995-08-01T23:59:59.000Z

358

Microsoft PowerPoint - Risk_Portfolio_Manager(RPM)_overview_Under_Sec_DOE__2011_V4 Final 3-22-2011.ppt [Read-Only] [Compatibili  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Corporate Headquarters: Corporate Headquarters: Risk Management: Overview of 1010 Wayne Avenue, Suite 1150 Silver Spring, Maryland 20910 301.565.2988 Telephone 301.565.2995 Facsimile www.e-mcinc.com Overview of e-Gov Risk Portfolio Manager(tm) (e Gov RPM(tm)) V4 Satellite Offices: 80 M Street, S.E., Suite 715 Washington, DC 20003 13800 Coppermine Road, Suite 221 (e-Gov RPM(tm)) V4 for Under Secretary of Energy 13800 Coppermine Road, Suite 221 Herndon, Virginia 20171 e-Management - Proprietary Information March 2011 Today's Agenda 1) eGov RPM and use at DOE EM 2) Overview of the capabilities of eGov RPM(tm) 3) eGov RPM supports the Under Secretary of Energy's Program Cyber Security Plan (PCSP) Cyber Security Plan (PCSP) e-Management - Proprietary Information 2 e-Gov Risk Portfolio Manager is a multi-user, web based tool used for continuous monitoring

359

EIS-0480: Long-Term Experimental and Management Plan for the Operation of  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

0: Long-Term Experimental and Management Plan for the 0: Long-Term Experimental and Management Plan for the Operation of Glen Canyon Dam EIS-0480: Long-Term Experimental and Management Plan for the Operation of Glen Canyon Dam SUMMARY Two agencies of the Department of the Interior, Bureau of Reclamation and National Park Service, are jointly preparing a Long-Term Experimental and Management Plan for the Glen Canyon Dam and an EIS for adoption of the Plan. The Glen Canyon Dam, on the Colorado River in northern, Arizona, generates hydroelectric power that is marketed by DOE's Western Area Power Administration, a cooperating agency. PUBLIC COMMENT OPPORTUNITIES None available at this time. DOCUMENTS AVAILABLE FOR DOWNLOAD July 6, 2011 EIS-0480: Notice of Intent to Prepare a Draft Environmental Impact Statement Long-Term Experimental and Management Plan for the Operation of Glen Canyon

360

A Dynamical Systems Model for Nuclear Power Plant Risk Management  

Science Conference Proceedings (OSTI)

This report provides a mathematical dynamical systems model of the effect of plant processes and programs on nuclear plant safety. That is, it models the safety risk management process. Responses of this model to postulated changes in performance and coupling parameters were verified to be in accordance with experience from years of commercial nuclear power plant operation. A preliminary analysis of the model was performed using the techniques of dynamical systems theory to determine regions of operation...

2003-10-31T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


361

Approaches To Crisis Prevention In Lean Product Development By High Performance Teams And Through Risk Management  

E-Print Network (OSTI)

This thesis investigates crisis prevention in lean product development, focusing on high performance teams and risk management methods.

Oehmen, Josef

362

Business Management and Planning (BMP) Division | U.S. DOE Office of  

NLE Websites -- All DOE Office Websites (Extended Search)

Business Business Management and Planning (BMP) Division Business Policy and Operations (BPO) BPO Home Leadership Organization Chart .pdf file (195KB) Business Management and Planning (BMP) Division SC Systems and Operations (SCSO) Division Contact Information Business Policy & Operations U.S. Department of Energy SC-45/Germantown Building 1000 Independence Ave., SW Washington, DC 20585 P: (301) 903-0192 F: (301) 903-2481 More Information » Business Management and Planning (BMP) Division Print Text Size: A A A RSS Feeds FeedbackShare Page The Business Management and Planning (BMP) Division provides planning, design, implementation, and overall project management for SC mission-support IT Initiatives such as research grants and financial management systems; network modernization; and IT Strategic and Operational

363

Quality Assurance Program Plan (QAPP) Waste Management Project  

SciTech Connect

This document is the Quality Assurance Program Plan (QAPP) for Waste Management Federal Services of Hanford, Inc. (WMH), that implements the requirements of the Project Hanford Management Contract (PHMC), HNF-MP-599, Project Hanford Quality Assurance Program Description (QAPD) document, and the Hanford Federal Facility Agreement with Consent Order (Tri-Party Agreement), Sections 6.5 and 7.8. WHM is responsible for the treatment, storage, and disposal of liquid and solid wastes generated at the Hanford Site as well as those wastes received from other US Department of Energy (DOE) and non-DOE sites. WMH operations include the Low-Level Burial Grounds, Central Waste Complex (a mixed-waste storage complex), a nonradioactive dangerous waste storage facility, the Transuranic Storage Facility, T Plant, Waste Receiving and Processing Facility, 200 Area Liquid Effluent Facility, 200 Area Treated Effluent Disposal Facility, the Liquid Effluent Retention Facility, the 242-A Evaporator, 300 Area Treatment Effluent Disposal Facility, the 340 Facility (a radioactive liquid waste handling facility), 222-S Laboratory, the Waste Sampling and Characterization Facility, and the Hanford TRU Waste Program.

VOLKMAN, D.D.

1999-10-27T23:59:59.000Z

364

[Environmental Hazards Assessment Program annual report, June 1992--June 1993]. Survey of environmental management training coordinators: Risk assessment/risk management training needs  

SciTech Connect

The Medical University of South Carolina (MUSC) is conducting a survey of Risk Assessment and Risk Management. They are developing information on the existing level of risk associated with training and the perceived need for this training by both federal and private organizations. The purpose of the questionnaire is to determine the available training and the perception of the Risk Management process in the DOE. Of particular interest is the requirement for Risk Assessment/Management training in organizations that will be involved in the Decontamination and Decommissioning of DOE Facilities. The survey questions and instructions are included.

1993-12-01T23:59:59.000Z

365

Fuzzy-genetic approach to aggregate production-distribution planning in supply chain management  

Science Conference Proceedings (OSTI)

Aggregate production-distribution planning (APDP) is one of the most important activities in supply chain management (SCM). When solving the problem of APDP, we are usually faced with uncertain market demands and capacities in production environment, ... Keywords: Aggregate production-distribution planning, Fuzzy mathematical programming, Genetic algorithm, Supply chain management

R. A. Aliev; B. Fazlollahi; B. G. Guirimov; R. R. Aliev

2007-10-01T23:59:59.000Z

366

Balancing Cost and Risk: The Treatment of Renewable Energy in Western Utility Resource Plans  

DOE Green Energy (OSTI)

Markets for renewable energy have historically been motivated primarily by policy efforts, but a less widely recognized driver is poised to also play a major role in the coming years: utility integrated resource planning (IRP). Resource planning has re-emerged in recent years as an important tool for utilities and regulators, particularly in regions where retail competition has failed to take root. In the western United States, the most recent resource plans contemplate a significant amount of renewable energy additions. These planned additions--primarily coming from wind power--are motivated by the improved economics of wind power, a growing acceptance of wind by electric utilities, and an increasing recognition of the inherent risks (e.g., natural gas price risk, environmental compliance risk) in fossil-based generation portfolios. This report examines how twelve western utilities treat renewable energy in their recent resource plans. In aggregate, these utilities supply approximately half of all electricity demand in the western United States. Our purpose is twofold: (1) to highlight the growing importance of utility IRP as a current and future driver of renewable energy, and (2) to identify methodological/modeling issues, and suggest possible improvements to methods used to evaluate renewable energy as a resource option. Here we summarize the key findings of the report, beginning with a discussion of the planned renewable energy additions called for by the twelve utilities, an overview of how these plans incorporated renewables into candidate portfolios, and a review of the specific technology cost and performance assumptions they made, primarily for wind power. We then turn to the utilities' analysis of natural gas price and environmental compliance risks, and examine how the utilities traded off portfolio cost and risk in selecting a preferred portfolio.

Bolinger, Mark; Wiser, Ryan

2005-08-10T23:59:59.000Z

367

Savannah River Site Waste Management Program Plan, FY 1993. Revision 1  

SciTech Connect

The primary purpose of the Waste Management Program Plan is to provide an annual report on facilities being used to manage wastes, forces acting to change current waste management (WM) systems, and how operations are conducted. This document also reports on plans for the coming fiscal year and projects activities for several years beyond the coming fiscal year to adequately plan for safe handling and disposal of radioactive wastes generated at the Savannah River Site (SRS) and for developing technology for improved management of wastes.

1993-06-01T23:59:59.000Z

368

Asset Management Toolkit Modules: An Approach for Risk-Informed Performance-Focused Asset Management in the Power Delivery Industry  

Science Conference Proceedings (OSTI)

With the growing emphasis on risk management, decision makers need both quantified estimates of the risk/uncertainty and actionable results for capital and operation and maintenance (O&M) investments in power delivery projects. This report describes the concepts and modular automation framework for an asset management toolkit that embodies the methods and processes of risk-informed, performance-focused asset management in the power delivery industry.

2005-06-30T23:59:59.000Z

369

Risk-Based Disposal Plan for PCB Paint in the TRA Fluorinel Dissolution Process Mockup and Gamma Facilities Canal  

SciTech Connect

This Toxic Substances Control Act Risk-Based Polychlorinated Biphenyl Disposal plan was developed for the Test Reactor Area Fluorinel Dissolution Process Mockup and Gamma Facilities Waste System, located in Building TRA-641 at the Reactor Technology Complex, Idaho National Laboratory Site, to address painted surfaces in the empty canal under 40 CFR 761.62(c) for paint, and under 40 CFR 761.61(c) for PCBs that may have penetrated into the concrete. The canal walls and floor will be painted with two coats of contrasting non-PCB paint and labeled as PCB. The canal is covered with open decking; the access grate is locked shut and signed to indicate PCB contamination in the canal. Access to the canal will require facility manager permission. Protective equipment for personnel and equipment entering the canal will be required. Waste from the canal, generated during ultimate Decontamination and Decommissioning, shall be managed and disposed as PCB Bulk Product Waste.

R. A. Montgomery

2008-05-01T23:59:59.000Z

370

Radioactive and mixed waste management plan for the Lawrence Berkeley Laboratory Hazardous Waste Handling Facility  

SciTech Connect

This Radioactive and Mixed Waste Management Plan for the Hazardous Waste Handling Facility at Lawrence Berkeley Laboratory is written to meet the requirements for an annual report of radioactive and mixed waste management activities outlined in DOE Order 5820.2A. Radioactive and mixed waste management activities during FY 1994 listed here include principal regulatory and environmental issues and the degree to which planned activities were accomplished.

NONE

1995-01-01T23:59:59.000Z

371

Environmental Management Waste Management Facility (EMWMF) Site-Specific Health and Safety Plan, Oak Ridge, Tennessee  

SciTech Connect

The Bechtel Jacobs Company LLC (BJC) policy is to provide a safe and healthy workplace for all employees and subcontractors. The implementation of this policy requires that operations of the Environmental Management Waste Management Facility (EMWMF), located one-half mile west of the U.S. Department of Energy (DOE) Y-12 National Security Complex, be guided by an overall plan and consistent proactive approach to environment, safety and health (ES&H) issues. The BJC governing document for worker safety and health, BJC/OR-1745, 'Worker Safety and Health Program', describes the key elements of the BJC Safety and Industrial Hygiene (IH) programs, which includes the requirement for development and implementation of a site-specific Health and Safety Plan (HASP) where required by regulation (refer also to BJC-EH-1012, 'Development and Approval of Safety and Health Plans'). BJC/OR-1745, 'Worker Safety and Health Program', implements the requirements for worker protection contained in Title 10 Code of Federal Regulations (CFR) Part 851. The EMWMF site-specific HASP requirements identifies safe operating procedures, work controls, personal protective equipment, roles and responsibilities, potential site hazards and control measures, site access requirements, frequency and types of monitoring, site work areas, decontamination procedures, and outlines emergency response actions. This HASP will be available on site for use by all workers, management and supervisors, oversight personnel and visitors. All EMWMF assigned personnel will be briefed on the contents of this HASP and will be required to follow the procedures and protocols as specified. The policies and procedures referenced in this HASP apply to all EMWMF operations activities. In addition the HASP establishes ES&H criteria for the day-to-day activities to prevent or minimize any adverse effect on the environment and personnel safety and health and to meet standards that define acceptable waste management practices. The HASP is written to make use of past experience and best management practices to eliminate or minimize hazards to workers or the environment from events such as fires, falls, mechanical hazards, or any unplanned release to the environment.

Flynn, N.C. Bechtel Jacobs

2008-04-21T23:59:59.000Z

372

Planning for mitigating climate change risk to metropolitan areas (USA)  

E-Print Network (OSTI)

In the last couple of decades, there has been increasing evidence of changes in global climate. With urban areas identified as the primary contributors to the climate change, there is an impetus for initiatives to persuade major contributors of greenhouse gases to undertake policy measures for climate change mitigation. The support for such initiatives at the international level has been mixed with many nations, including the United States, not accepting the Kyoto protocol. In view of the evident disagreement at the international level, initiatives promoting local communities to adopt self regulating policies for climate change mitigation have gained importance. One such initiative is the Cities for Climate Protection (CCP) supported by the International Council for Local Environmental Initiatives. This research explores the differences in the socio-economic and civic characteristics of metropolitan areas in the contiguous United States that have committed to CCP (as a policy measure for climate change mitigation) to those that have not. The data in this study has been primarily collected from the census documents and government publications. The indicators are grouped into risk, stress and civic variables. The differences amongst the metropolitan areas with CCP committed jurisdictions and those with non-committed jurisdictions have been analyzed through statistical t-tests and use of geographical information system (GIS). The research reveals that metropolitan areas with a higher degree of risk are more likely to commit to climate change mitigation policies whereas those with higher stress index are less likely to commit. The metropolitan areas with higher civic index were also found more likely to commit to policy measures for climate change mitigation. The results of the study are significant as they reveal that communities that are at risk are not necessarily adding to the climate stress and those contributing the most to the climatic stress are not committed to climate change mitigation. The results of the study support the need to discontinue the closed box approach and instead adopt an approach with vertical integration. Cooperation and coordination amongst the hierarchical aggregate levels of communities, from a place to a region, are imperative for effective implementation of climate mitigation initiatives.

Grover, Himanshu

2006-08-01T23:59:59.000Z

373

Peaking World Oil Production: Impacts, Mitigation and Risk Management  

E-Print Network (OSTI)

The peaking of world oil production presents the U.S. and the world with an unprecedented risk management problem. As peaking is approached, liquid fuel prices and price volatility will increase dramatically, and, without timely mitigation, the economic, social, and political costs will be unprecedented. Viable mitigation options exist on both the supply and demand sides, but to have substantial impact, they must be initiated more than a decade in advance of peaking. In 2003, the world consumed nearly 80 million barrels per day (MM bpd) of oil. U.S. consumption was almost 20 MM bpd,

Robert L. Hirsch; Roger H. Bezdek; Robert M. Wendling

2005-01-01T23:59:59.000Z

374

Managing concurrency in temporal planning using planner-scheduler interaction  

Science Conference Proceedings (OSTI)

Metric temporal planning involves both selecting and organising actions to satisfy the goals and also assigning to each of these actions its start time and, where necessary, its duration. The assignment of start times to actions is a central concern ... Keywords: Planning and scheduling, Temporal planning, pddl 2.1

Andrew Coles; Maria Fox; Keith Halsey; Derek Long; Amanda Smith

2009-01-01T23:59:59.000Z

375

RPP-PLAN-47325 Revision 0 Radioactive Waste Determination Process Plan for Waste Management Area C Tank  

E-Print Network (OSTI)

This plan describes the radioactive waste determination process that the U.S. Department of Energy (DOE) will use for Hanford Site Waste Management Area C (WMA C) tank waste residuals subject to DOE authority under DOE Order 435.1, Radioactive Waste Management. Preparation of this plan is a required component of actions the DOE-Office of River Protection (ORP) must take to fulfill proposed Hanford Federal Facility Agreement and Consent Order Milestone M-045-80. Waste Management Area C is comprised of various single-shell tanks, encased and direct-buried pipes, diversion boxes, pump pits, and unplanned release sites (sites contaminated as a result of spills of tank waste to the environment). Since operations began in the late 1940s, the tanks in WMA C have continuously stored waste managed as high-level waste (HLW) that was derived from defense-related nuclear research, development, and weapons production activities. Planning for the final closure of WMA C is underway. This radioactive waste determination process plan assumes that tank closure will follow retrieval of as much tank waste as technically and economically practical. It is also assumed for the purposes of this plan that after completion

Waste Residuals; J. R. Robertson

2010-01-01T23:59:59.000Z

376

Savannah River Site`s Site Specific Plan. Environmental restoration and waste management, fiscal year 1992  

SciTech Connect

This Site Specific Plan (SSP) has been prepared by the Savannah River Site (SRS) in order to show the Environmental Restoration and Waste Management activities that were identified during the preparation of the Department of Energy-Headquarters (DOE-HQ) Environmental Restoration and Waste Management Five-Year Plan (FYP) for FY 1992--1996. The SSP has been prepared in accordance with guidance received from DOE-HQ. DOE-SR is accountable to DOE-HQ for the implementation of this plan. The purpose of the SSP is to develop a baseline for policy, budget, and schedules for the DOE Environmental Restoration and Waste Management activities. The plan explains accomplishments since the Fiscal Year (FY) 1990 plan, demonstrates how present and future activities are prioritized, identifies currently funded activities and activities that are planned to be funded in the upcoming fiscal year, and describes future activities that SRS is considering.

1991-08-01T23:59:59.000Z

377

Where do the Nuclear Materials Management functions fit in the Materials Control and Accountability (MC and A) plan  

Science Conference Proceedings (OSTI)

Safeguards had its beginning in the early 1940s and has continued to grow through the stormy years in dealing with nuclear materials. MC and A Plans have been developed for each facility which includes requirements for containment, surveillance, internal controls, measurements, statistics, records and report systems, and inventory certification of its nuclear materials, in the context of how precisely the inventory is known at stated risk or confidence levels. The I and E Regulations, the newest document affecting the control system, are used for testing the current MC and A plan in place at each facility. Nuclear Materials Management activities also have reporting requirements that include: (1) Annual Forecast, (2) Materials Management Plan, (3) Quarterly Status Report, (4) Assessment Report, and (5) Scrap and Excess Material Management. Data used to generate reports for both functions come from the same data base and source documents at most facilities. The separation of sponsoring groups at the DOE for NM Accountability and NM Management can and does pose problems for contractors. In this paper, we will try to separate and identify these overlaps at the Facility and DOE level.

DeVer, E.A.

1987-01-01T23:59:59.000Z

378

Proposed framework for the Western Area Power Administration Environmental Risk Management Program  

Science Conference Proceedings (OSTI)

The Western Area Power Administration (Western) views environmental protection and compliance as a top priority as it manages the construction, operation, and maintenance of its vast network of transmission lines, substations, and other facilities. A recent Department of Energy audit of Western`s environmental management activities recommends that Western adopt a formal environmental risk program. To accomplish this goal, Western, in conjunction with Pacific Northwest Laboratory, is in the process of developing a centrally coordinated environmental risk program. This report presents the results of this design effort, and indicates the direction in which Western`s environmental risk program is heading. Western`s environmental risk program will consist of three main components: risk communication, risk assessment, and risk management/decision making. Risk communication is defined as an exchange of information on the potential for threats to human health, public safety, or the environment. This information exchange provides a mechanism for public involvement, and also for the participation in the risk assessment and management process by diverse groups or offices within Western. The objective of risk assessment is to evaluate and rank the relative magnitude of risks associated with specific environmental issues that are facing Western. The evaluation and ranking is based on the best available scientific information and judgment and serves as input to the risk management process. Risk management takes risk information and combines it with relevant non-risk factors (e.g., legal mandates, public opinion, costs) to generate risk management options. A risk management tool, such as decision analysis, can be used to help make risk management choices.

Glantz, C.S.; DiMassa, F.V.; Pelto, P.J.; Brothers, A.J. [Pacific Northwest Lab., Richland, WA (United States); Roybal, A.L. [Western Area Power Administration, Golden, CO (United States)

1994-12-01T23:59:59.000Z

379

Proceedings of 2001 Workshop on Life Cycle Management Planning for Systems, Structures, and Components  

Science Conference Proceedings (OSTI)

These proceedings provide nuclear plant owners with an overview of the state of development of methods and tools for performing long-term planning for maintenance, aging management, and obsolescence management of systems, structures, and components important to a plant's long-term safety, power production, and plant value. Results of applying life-cycle management (LCM) at four plants are summarized.

2001-12-20T23:59:59.000Z

380

Environmental management 1994. Progress and plans of the environmental restoration and waste management program  

SciTech Connect

The Department of Energy currently faces one of the largest environmental challenges in the world. The Department`s Environmental Restoration and Waste Management program is responsible for identifying and reducing risks and managing waste at 137 sites in 34 States and territories where nuclear energy or weapons research and production resulted in radioactive, hazardous, and mixed waste contamination. The number of sites continues to grow as facilities are transferred to be cleaned up and closed down. The program`s main challenge is to balance technical and financial realities with the public`s expectations and develop a strategy that enables the Department to meet its commitments to the American people. This document provides a closer look at what is being done around the country. Included are detailed discussions of the largest sites in the region, followed by site activities organized by state, and a summary of activities at FUSRAP and UMTRA sites in the region.

Not Available

1994-02-01T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


381

"Insurance as a Risk Management Instrument for Energy Infrastructure  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

"Insurance as a Risk Management Instrument for Energy "Insurance as a Risk Management Instrument for Energy Infrastructure Security and Resilience" Report (March 2013) "Insurance as a Risk Management Instrument for Energy Infrastructure Security and Resilience" Report (March 2013) The Office of Electricity Delivery and Energy Reliability has released a report that examines the key risks confronting critical energy infrastructure and ways in which the insurance industry can help manage these risks. In most developed countries, insurance is one of the principal risk management instruments for aiding in recovery after a disaster and for encouraging future investments that are more resilient to potential hazards. The "Insurance as a Risk Management Instrument for Energy Infrastructure Security and Resilience" report examines how the

382

"Insurance as a Risk Management Instrument for Energy Infrastructure  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

"Insurance as a Risk Management Instrument for Energy "Insurance as a Risk Management Instrument for Energy Infrastructure Security and Resilience" Report Now Available "Insurance as a Risk Management Instrument for Energy Infrastructure Security and Resilience" Report Now Available March 28, 2013 - 4:15pm Addthis The Office of Electricity Delivery and Energy Reliability has released a report that examines the key risks confronting critical energy infrastructure and ways in which the insurance industry can help manage these risks. In most developed countries, insurance is one of the principal risk management instruments for aiding in recovery after a disaster and for encouraging future investments that are more resilient to potential hazards. The "Insurance as a Risk Management Instrument for Energy

383

Hybrid Kansei-SOM model using risk management and company assessment for stock trading  

Science Conference Proceedings (OSTI)

Risk management and stock assessment are key methods for stock trading decisions. In this paper, we present a new stock trading method using Kansei evaluation integrated with a Self-Organizing Map model for improvement of a stock trading system. The ... Keywords: Hybrid intelligent trading system, Investment risk, Kansei evaluation, Risk management, Self-Organizing Map, Stock trading system

Hai V. Pham, Eric W. Cooper, Thang Cao, Katsuari Kamei

2014-01-01T23:59:59.000Z

384

Waste Isolation Pilot Plant Groundwater Protection Management Program Plan  

SciTech Connect

The DOE established the Groundwater Monitoring Program (GMP) (WP 02-1) to monitor groundwater resources at WIPP. In the past, the GMP was conducted to establish background data of existing conditions of groundwater quality and quantity in the WIPP vicinity, and to develop and maintain a water quality database as required by regulation. Today the GMP is conducted consistent with 204.1.500 NMAC (New MexicoAdministrative Code), "Adoption of 40 CFR [Code of Federal Regulations] Part 264,"specifically 40 CFR 264.90 through 264.101. These sections of 20.4.1 NMAC provide guidance for detection monitoring of groundwater that is, or could be, affected by waste management activities at WIPP. Detection monitoring at WIPP is designed to detect contaminants in the groundwater long before the general population is exposed. Early detection will allow cleanup efforts to be accomplished before any exposure to the general population can occur. Title 40 CFR Part 264, Subpart F, stipulates minimum requirements of Resource Conservation and Recovery Act of 1976 (42 United States Code [U.S.C.] 6901 et seq.) (RCRA) groundwater monitoring programs including the number and location of monitoring wells; sampling and reporting schedules; analytical methods and accuracy requirements; monitoring parameters; and statistical treatment of monitoring data. This document outlines how WIPP intends to protect and preserve groundwater within the WIPP Land Withdrawal Area (WLWA). Groundwater protection is just one aspect of the WIPP environmental protection effort. An overview of the entire environmental protection effort can be found in DOE/WIPP 99-2194, Waste Isolation Pilot Plant Environmental Monitoring Plan. The WIPP GMP is designed to statistically determine if any changes are occurring in groundwater characteristics within and surrounding the WIPP facility. If a change is noted, the cause will then be determined and the appropriate corrective action(s) initiated.

Washington Regulatory and Environmental Services

2005-07-01T23:59:59.000Z

385

Automated Home Energy Management (AHEM) Standing Technical Committee Strategic Plan - February 2012  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Automated Home Energy Management (AHEM) Automated Home Energy Management (AHEM) Standing Technical Committee Strategic Plan, v2011c - February 2012 Committee Chair: 2011 Kurt Roth Fraunhofer 2012 Lieko Earle, Bethany Sparn NREL 2 Prioritization of Gaps, Barriers and Needs The following table lists a prioritization for the Gaps, Barriers and Needs included in the Building America AHEM STC Strategic Plan. Table 1. Gaps and Barriers for AHEM STC. Rank Description 1 Energy Savings / ROI Insufficiently Quantified 2 Lack of Consumer Awareness of AHEM Products 3 Low Interest in Managing Energy Use 4 Complexity of AHEM Products Contents Summary of AHEM STC Strategic Plan ..................................................................................................................... 3

386

EMP Attachment 2 DOE-SC PNNL Site Data Management Plan  

Science Conference Proceedings (OSTI)

This Data Management Plan (DMP) describes the data management processes and activities under the Pacific Northwest National Laboratory (PNNL) Site Environmental Monitoring Plan. The activities currently in the Plan are limited to offsite environmental surveillance of PNNL Site radiological releases to the air. The DMP provides guidance on data capture, processing and transmittal, and database configuration management. The requirements for the PNNL Site Environmental Monitoring (SEM) Database and associated records are documented in order to assure that vital data are recorded accurately, stored in a manner that retains data integrity, and are suitable for analyst to use. Protocols and procedures must ensure the data will be adequate and robust.

Bisping, Lynn E.

2011-12-21T23:59:59.000Z

387

The Optimized Integration of the Decontamination Plan and the Radwaste Management Plan into Decommissioning Plan to the VVR-S Research Reactor from Romania  

SciTech Connect

The paper presents the progress of the Decontamination Plan and Radioactive Waste Management Plan which accompanies the Decommissioning Plan for research reactor VVR-S located in Magurele, Ilfov, near Bucharest, Romania. The new variant of the Decommissioning Plan was elaborated taking into account the IAEA recommendation concerning radioactive waste management. A new feasibility study for VVR-S decommissioning was also elaborated. The preferred safe management strategy for radioactive wastes produced by reactor decommissioning is outlined. The strategy must account for reactor decommissioning, as well as rehabilitation of the existing Radioactive Waste Treatment Plant and the upgrade of the Radioactive Waste Disposal Facility at Baita-Bihor. Furthermore, the final rehabilitation of the laboratories and reusing of cleaned reactor building is envisaged. An inventory of each type of radioactive waste is presented. The proposed waste management strategy is selected in accordance with the IAEA assistance. Environmental concerns are a part of the radioactive waste management strategy. In conclusion: The current version 8 of the Draft Decommissioning Plan which include the Integrated concept of Decontamination and Decommissioning and Radwaste Management, reflects the substantial work that has been incorporated by IFIN-HH in collaboration with SITON, which has resulted in substantial improvement in document The decommissioning strategy must take into account costs for VVR-S Reactor decommissioning, as well as costs for much needed refurbishments to the radioactive waste treatment plant and the Baita-Bihor waste disposal repository. Several improvements to the Baita-Bihor repository and IFIN-HH waste treatment facility were proposed. The quantities and composition of the radioactive waste generated by VVR-S Reactor dismantling were again estimated by streams and the best demonstrated practicable processing solution was proposed. The estimated quantities of materials to be managed in the near future raise some issues that need to be solved swiftly, such as treatment of aluminum and lead and graphite management. It is envisaged that these materials to be treated to Subsidiary for Nuclear Research (SCN) Pitesti. (authors)

Barariu, G. [National Authority for Nuclear Activity-Subsidiary of Technology and Engineering for Nuclear Projects (Romania)

2008-07-01T23:59:59.000Z

388

Columbia Basin Wildlife Mitigation Project : Rainwater Wildlife Area Final Management Plan.  

DOE Green Energy (OSTI)

This Draft Management Plan has been developed by the Confederated Tribes of the Umatilla Indian Reservation (CTUIR) to document how the Rainwater Wildlife Area (formerly known as the Rainwater Ranch) will be managed. The plan has been developed under a standardized planning process developed by the Bonneville Power Administration (BPA) for Columbia River Basin Wildlife Mitigation Projects (See Appendix A and Guiding Policies Section below). The plan outlines the framework for managing the project area, provides an assessment of existing conditions and key resource issues, and presents an array of habitat management and enhancement strategies. The plan culminates into a 5-Year Action Plan that will focus our management actions and prioritize funding during the Fiscal 2001-2005 planning period. This plan is a product of nearly two years of field studies and research, public scoping, and coordination with the Rainwater Advisory Committee. The committee consists of representatives from tribal government, state agencies, local government, public organizations, and members of the public. The plan is organized into several sections with Chapter 1 providing introductory information such as project location, purpose and need, project goals and objectives, common elements and assumptions, coordination efforts and public scoping, and historical information about the project area. Key issues are presented in Chapter 2 and Chapter 3 discusses existing resource conditions within the wildlife area. Chapter 4 provides a detailed presentation on management activities and Chapter 5 outlines a monitoring and evaluation plan for the project that will help assess whether the project is meeting the intended purpose and need and the goals and objectives. Chapter 6 displays the action plan and provides a prioritized list of actions with associated budget for the next five year period. Successive chapters contain appendices, references, definitions, and a glossary.

Childs, Allen

2002-03-01T23:59:59.000Z

389

Management-By-Objectives Plan: Fiscal Year 1989  

SciTech Connect

This is an internal DOE Geothermal Program planning and control document. Many of these reports were issued only in draft form.

1988-12-01T23:59:59.000Z

390

2010 Annual Planning Summary for Civilian Radioactive Waste Management...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Annual Planning Summary for National Nuclear Security Administration Service Center (NNSA-SC) Energy.gov Careers & Internships Guidance & Requirements Contact Us About This Site...

391

2010 Annual Planning Summary for Legacy Management | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Annual Planning Summary for National Nuclear Security Administration Service Center (NNSA-SC) Energy.gov Careers & Internships Guidance & Requirements Contact Us About This Site...

392

Evolution of Risk Management at NASA in the Context of Achieving Adequate  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Evolution of Risk Management at NASA in the Context of Achieving Evolution of Risk Management at NASA in the Context of Achieving Adequate Safety Evolution of Risk Management at NASA in the Context of Achieving Adequate Safety September 20, 2012 Presenter: Homayoon Dezfuli, Ph.D. NASA Technical Fellow for System Safety Office of Safety and Mission Assurance NASA Headquarters Topics Covered: Historical Perspective on NASA Risk Management (RM) * RM Approach After 2008 * Future Direction of RM at NASA - The Concept of "Adequate Safety" - The Issue of Risk Analysis Completeness (Rationale for Future Trends in RM) Summary 2 Acknowledgment Evolution of Risk Management at NASA in the Context of Achieving Adequate Safety More Documents & Publications DOE Standard on Development and Use of Probabilistic Risk Assessment in DOE

393

Proceedings: 2003 Workshop on Life Cycle Management Planning for Systems, Structures, and Components  

Science Conference Proceedings (OSTI)

These proceedings of the 2003 EPRI Life Cycle Management Workshop provide nuclear plant owners with an overview of the state of development of methods and tools for performing long-term planning for maintenance, aging management, and obsolescence management of systems, structures, and components important to a plant's long-term safety, power production, and value in a market-driven industry. The proceedings summarize the results of applying life cycle management at several plants.

2003-12-17T23:59:59.000Z

394

Proceedings: 2003 Workshop on Life Cycle Management Planning for Systems, Structures, and Components  

SciTech Connect

These proceedings of the 2003 EPRI Life Cycle Management Workshop provide nuclear plant owners with an overview of the state of development of methods and tools for performing long-term planning for maintenance, aging management, and obsolescence management of systems, structures, and components important to a plant's long-term safety, power production, and value in a market-driven industry. The proceedings summarize the results of applying life cycle management at several plants.

None

2003-12-01T23:59:59.000Z

395

Systems engineering management and implementation plan for Project W-464, immobilized high-level waste storage  

SciTech Connect

The Systems Engineering Management and Implementation Plan (SEMIP) for TWRS Project W-46 describes the project implementation of the Tank Waste Remediation System Systems Engineering Management Plan. (TWRS SEMP), Rev. 1. The SEMIP outlines systems engineering (SE) products and processes to be used by the project for technical baseline development. A formal graded approach is used to determine the products necessary for requirements, design, and operational baseline completion. SE management processes are defined, and roles and responsibilities for management processes and major technical baseline elements are documented.

Wecks, M.D.

1998-04-15T23:59:59.000Z

396

The Weather Risk Management Industry's Climate Forecast and Data Needs: A Workshop Report  

Science Conference Proceedings (OSTI)

The National Oceanic and Atmospheric Administration (NOAA), the Risk Prediction Initiative, and the Weather Risk Management Association jointly sponsored a workshop that examined a variety of issues related to climate forecastand data products ...

Richard J. Murnane; Michael Crowe; Allan Eustis; Susan Howard; Judy Koepsell; Robert Leffler; Robert Livezey

2002-08-01T23:59:59.000Z

397

Energy Planning And Management Program, Wapa Programmatic Doe/eis-0182  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

1995/01eis0182_ep.html[6/27/2011 10:56:10 AM] 1995/01eis0182_ep.html[6/27/2011 10:56:10 AM] Energy Planning and Management Program Environmental Impact Statement DOE/EIS-0182 Western Area Power Administration Energy Planning and Management Program Environmental Impact Statement Energy Planning And Management Program, Wapa Programmatic Doe/eis-0182 file:///I|/Data%20Migration%20Task/EIS-0182-FEIS-1995/02eis0182_cov.html[6/27/2011 10:56:06 AM] COVER SHEET Title: Energy Planning and Management program Agency: Western Area Power Administration Contact: Mr. Robert Fullerton Western Area Power Administration

398

Microsoft Word - DOE-CBFO-01-3107 PDP Management Plan_Final  

NLE Websites -- All DOE Office Websites (Extended Search)

CBFO-01-3107 CBFO-01-3107 PERFORMANCE DEMONSTRATION PROGRAM MANAGEMENT PLAN Revision 6 June 2013 U.S. Department of Energy Carlsbad Field Office Office of the National TRU Program This document supersedes DOE/CBFO-01-3107, Revision 5 DOE/CBFO-01-3107 Revision 6 PDP Management Plan June 2013 2 Performance Demonstration Program Management Plan DOE/CBFO-01-3107 Revision 6 June 2013 Approved By: //signature on file// Date: 6-14-13 Office Director Office of the National TRU Program Concurred By: //signature on file// Date: 6-14-13 Office Director Office of Quality Assurance Prepared By: //signature on file// Date: 6-14-13 PDP Appointee Office of the National TRU Program DOE/CBFO-01-3107 Revision 6 PDP Management Plan June 2013

399

Strategic Plan for Sustainable Energy Management and Environmental Stewardship for Los Angeles Unified School District  

SciTech Connect

This Strategic Plan for Sustainable Energy Management and Environmental Stewardship states goals, measures progress toward goals and how actions are monitored to achieve continuous improvement for the Los Angeles Unified School District.

Walker, A.; Beattie, D.; Thomas, K.; Davis, K.; Sim, M.; Jhaveri, A.

2007-11-01T23:59:59.000Z

400

Integrating regional strategic transportation planning and supply chain management : along the path to sustainability  

E-Print Network (OSTI)

A systems perspective for regional strategic transportation planning (RSTP) for freight movements involves an understanding of Supply Chain Management (SCM). This thesis argues that private sector freight shippers and ...

Sgouridis, Sgouris P

2005-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


401

Risk Assess - updated  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Software Development Risk Assessment Software Development Risk Assessment Note: The purpose of this prompt list is to provide project managers with a tool for identifying and planning for potential project risks. It is process-based and supports the framework established by the DOE Software Engineering Methodology. It will be used within the stage exit process as an additional tool to ensure that the project manager has identified and is managing known risk factors. Additional detailed information describes the various risk factors and how to score them. Performing a risk assessment is an important step in being prepared for potential problems that can occur within any software project. During the risk assessment, if a potential risk is identified, a solution or plan of action should be developed. (A problem analyzed and planned

402

Groundwater Monitoring Guidance for the Industry Action Plan on Coal Combustion Product Management  

Science Conference Proceedings (OSTI)

The US Environmental Protection Agency (USEPA) is scheduled to release federal guidelines for management of coal combustion products (CCPs) in 2007. The utility industry has developed a voluntary Action Plan as an alternative to the federal guidelines. In either case, groundwater monitoring will be required. The purpose of this report is to provide guidance for implementing a groundwater-monitoring program at CCP management sites consistent with the Action Plan proposed by the utility industry.

2005-12-07T23:59:59.000Z

403

System Engineering Management and Implementation Plan for Project W-211 Initial Tank Retrieval Systems (ITRS)  

Science Conference Proceedings (OSTI)

This systems Engineering Management and Implementation Plan (SEMIP) describes the Project W-211 implementation of the Tank Farm Contractor Systems Engineering Management Plan (TFC SEMP). The SEMIP defines the systems engineering products and processes used by the project to comply with the TFC SEMP, and provides the basis for tailoring systems engineering processes by applying a graded approach to identify appropriate systems engineering requirements for W-211.

VAN BEEK, J.E.

2000-05-05T23:59:59.000Z

404

Life Cycle Management Value Planning Tool (LcmVALUE) Code, Version 1.0  

Science Conference Proceedings (OSTI)

An important aspect of equipment aging or life cycle management (LCM) planning is the comparison of the long term economics of alternative plans, all of which satisfy safety and reliability requirements. These economic evaluations must be performed on a net present value basis, and must include factors such as failure rates, value of lost production, consequential costs of potential regulatory sanctions and adverse public relations, and the costs of planned preventive maintenance (PM) and unplanned corre...

2002-08-15T23:59:59.000Z

405

Waste Management Plan for the Oak Ridge National Remedial Investigation/Feasibility Study  

SciTech Connect

In accordance with the requirements of the Remedial Investigation/Feasibility Study (RI/FS) Project Quality Assurance Plan, this Waste Management Plan establishes clear lines of responsibility and authority, documentation requirements, and operational guidance for the collection, identification, segregation, classification, packaging, certification, and storage/disposal of wastes. These subjects are discussed in the subsequent sections of this document.

1988-04-01T23:59:59.000Z

406

A comprehensive solution to ATM network planning and bandwidth management using Genetic Algorithm  

Science Conference Proceedings (OSTI)

Wireless Asynchronous Transfer Mode (ATM) is fast becoming an option in the telecommunication area and consequently there is a renewed interest in developing broadband integrated service of digital network technologies namely ATM. In order to ... Keywords: ATM networks, ATM planning, GAs, asynchronous transfer mode, bandwidth management, genetic algorithms, network design, network planning, optimisation, passive optical networks, wireless ATM

Susmi Routray; Arun Mohan Sherry; B. V. R. Reddy

2008-03-01T23:59:59.000Z

407

Survey on the Use of Configuration Risk and Safety Management Tools at Nuclear Power Plants  

Science Conference Proceedings (OSTI)

A joint project of Electricite de France (EDF) and EPRI, this project analyzed use of configuration safety and risk management tools at nuclear power plants.

1998-09-24T23:59:59.000Z

408

Web-Based and Geospatially Enabled Tool for Water and Wastewater Pipeline Infrastructure Risk Management.  

E-Print Network (OSTI)

??Advanced pipeline risk management is contingent on accurately locating the buried pipelines, the milieu, and also the physical condition of the pipelines. The web-based and (more)

Sekar, Varun Raj

2011-01-01T23:59:59.000Z

409

Risk-Managed Technical Specifications - Lessons Learned from Initial Application at South Texas Project  

Science Conference Proceedings (OSTI)

This report describes research that documents lessons learned from the initial year of implementation of Risk-Managed Technical Specifications (RMTS) at South Texas Project (STP).

2008-12-11T23:59:59.000Z

410

Soil Management Plan for the Oak Ridge Y-12 National Security Complex Oak Ridge, Tennessee  

Science Conference Proceedings (OSTI)

This Soil Management Plan applies to all activities conducted under the auspices of the National Nuclear Security Administration (NNSA) Oak Ridge Y-12 National Security Complex (Y-12) that involve soil disturbance and potential management of waste soil. The plan was prepared under the direction of the Y-12 Environmental Compliance Department of the Environment, Safety, and Health Division. Soil disturbances related to maintenance activities, utility and building construction projects, or demolition projects fall within the purview of the plan. This Soil Management Plan represents an integrated, visually oriented, planning and information resource tool for decision making involving excavation or disturbance of soil at Y-12. This Soil Management Plan addresses three primary elements. (1) Regulatory and programmatic requirements for management of soil based on the location of a soil disturbance project and/or the regulatory classification of any contaminants that may be present (Chap. 2). Five general regulatory or programmatic classifications of soil are recognized to be potentially present at Y-12; soil may fall under one or more these classifications: (a) Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) pursuant to the Oak Ridge Reservation (ORR) Federal Facilities Agreement; (b) Resource Conservation and Recovery Act (RCRA); (c) RCRA 3004(u) solid waste managements units pursuant to the RCRA Hazardous and Solid Waste Amendments Act of 1984 permit for the ORR; (d) Toxic Substances and Control Act-regulated soil containing polychlorinated biphenyls; and (e) Radiologically contaminated soil regulated under the Atomic Energy Act review process. (2) Information for project planners on current and future planned remedial actions (RAs), as prescribed by CERCLA decision documents (including the scope of the actions and remedial goals), land use controls implemented to support or maintain RAs, RCRA post-closure regulatory requirements for former waste management units, legacy contamination source areas and distribution of contamination in soils, and environmental infrastructure (e.g., caps, monitoring systems, etc.) that is in place or planned in association with RAs. (3) Regulatory considerations and processes for management and disposition of waste soil upon generation, including regulatory drivers, best management practices (BMPs), waste determination protocols, waste acceptance criteria, and existing waste management procedures and BMPs for Y-12. This Soil Management Plan provides information to project planners to better coordinate their activities with other organizations and programs with a vested interest in soil disturbance activities at Y-12. The information allows project managers and maintenance personnel to evaluate and anticipate potential contaminant levels that may be present at a proposed soil disturbance site prior to commencement of activities and allows a more accurate assessment of potential waste management requirements.

None

2005-03-02T23:59:59.000Z

411

2010 Annual Planning Summary for Civilian Radioactive Waste Management (CRWM)  

Energy.gov (U.S. Department of Energy (DOE))

Annual Planning Summaries briefly describe the status of ongoing NEPA compliance activities, any EAs expected to be prepared in the next 12 months, any EISs expected to be prepared in the next 24...

412

Capacity planning and change management in an aerospace overhaul cell  

E-Print Network (OSTI)

Purpose - This thesis analyzes the transformation of the Small Components Cell in Pratt & Whitney's aftermarket division through lean manufacturing techniques. The thesis focuses on use of a labor capacity planning model, ...

Walker, David, M.B.A. Massachusetts Institute of Technology

2013-01-01T23:59:59.000Z

413

Risk management at the Oak Ridge National Laboratory research reactors  

SciTech Connect

In November of 1986, the High Flux Isotope Reactor (HFIR) was shut down by Oak Ridge National Laboratory (ORNL) due to a concern regarding embrittlement of the reactor vessel. A massive review effort was undertaken by ORNL and the Department of Energy (DOE). This review resulted in an extensive list of analyses and design modifications to be completed before restart could take place. The review also focused on the improvement of management practices including implementation of several of the Institute of Nuclear Power Operations (INPO) requirements. One of the early items identified was the need to perform a Probabilistic Risk Assessment (PRA) on the reactor. It was decided by ORNL management that this PRA would not be just an exercise to assess the ``bottom`` line in order to restart, but would be used to improve the overall safety of the reactor, especially since resources (both manpower and dollars) were severely limited. The PRA would become a basic safety tool to be used instead of a more standard deterministic approach to safety used in commercial reactor power plants. This approach was further reinforced, because the reactor was nearly 25 years old at this time, and the design standards and regulations had changed significantly since the original design, and many of the safety issues could not be addressed by compliance to codes and standards.

Flanagan, G.F.; Linn, M.A.; Proctor, L.D.; Cook, D.H.

1994-12-31T23:59:59.000Z

414

INL Site Executable Plan for Energy and Transportation Fuels Management  

Science Conference Proceedings (OSTI)

It is the policy of the Department of Energy (DOE) that sustainable energy and transportation fuels management will be integrated into DOE operations to meet obligations under Executive Order (EO) 13423 "Strengthening Federal Environmental, Energy, and Transportation Management," the Instructions for Implementation of EO 13423, as well as Guidance Documents issued in accordance thereto and any modifcations or amendments that may be issued from time to time. In furtherance of this obligation, DOE established strategic performance-based energy and transportation fuels goals and strategies through the Transformational Energy Action Management (TEAM) Initiative, which were incorporated into DOE Order 430.2B "Departmental Energy, Renewable energy, and Transportation Management" and were also identified in DOE Order 450.1A, "Environmental Protection Program." These goals and accompanying strategies are to be implemented by DOE sites through the integration of energy and transportation fuels management into site Environmental Management Systems (EMS).

Ernest L. Fossum

2008-11-01T23:59:59.000Z

415

Environmental restoration and waste management site-specific plan for Richland Operations Office. [Contains glossary  

SciTech Connect

This document was prepared to implement and support the US Department of Energy-Headquarters (DOE-HQ) national plan. The national plan, entitled Environmental Restoration and Waste Management Five-Year Plan (DOE 1990b) (hereinafter referred to as the DOE-HQ Five-Year Plan) is the cornerstone of the US Department of Energy's (DOE) long-term strategy in environmental restoration and waste management. The DOE-HQ Five-Year Plan addresses overall philosophy and environmental and waste-related activities under the responsibilities of the DOE Office of Environmental Restoration and Waste Management. The plan also reaffirms DOE-HQ goals to bring its nuclear sites into environmental compliance in cooperation with its regulators and the public, and to clean up and restore the environment by 2019 (the commitment for the Hanford Site is for one year sooner, or 2018). This document is part of the site-specific plan for the US Department of Energy-Richland Operations Office (DOE-RL). It is the first revision of the original plan, which was dated December 1989 (DOE-RL 1989a). This document is a companion document to the Overview of the Hanford Cleanup Five-Year Plan (DOE-RL 1989d) and The Hanford Site Environmental Restoration and Waste Management Five-Year Plan Activity Data Sheets (DOE-RL 1991). Although there are three documents that make up the complete DOE-RL plan, this detailed information volume was prepared so it could be used as a standalone document. 71 refs., 40 figs., 28 tabs.

Not Available

1991-09-01T23:59:59.000Z

416

Environmental restoration and waste management site-specific plan for Richland Operations Office. [Contains glossary  

SciTech Connect

This document was prepared to implement and support the US Department of Energy-Headquarters (DOE-HQ) national plan. The national plan, entitled Environmental Restoration and Waste Management Five-Year Plan (DOE 1990b) (hereinafter referred to as the DOE-HQ Five-Year Plan) is the cornerstone of the US Department of Energy's (DOE) long-term strategy in environmental restoration and waste management. The DOE-HQ Five-Year Plan addresses overall philosophy and environmental and waste-related activities under the responsibilities of the DOE Office of Environmental Restoration and Waste Management. The plan also reaffirms DOE-HQ goals to bring its nuclear sites into environmental compliance in cooperation with its regulators and the public, and to clean up and restore the environment by 2019 (the commitment for the Hanford Site is for one year sooner, or 2018). This document is part of the site-specific plan for the US Department of Energy-Richland Operations Office (DOE-RL). It is the first revision of the original plan, which was dated December 1989 (DOE-RL 1989a). This document is a companion document to the Overview of the Hanford Cleanup Five-Year Plan (DOE-RL 1989d) and The Hanford Site Environmental Restoration and Waste Management Five-Year Plan Activity Data Sheets (DOE-RL 1991). Although there are three documents that make up the complete DOE-RL plan, this detailed information volume was prepared so it could be used as a standalone document. 71 refs., 40 figs., 28 tabs.

1991-09-01T23:59:59.000Z

417

Energy Management: A Corporate Objective in the Five-Year Business Plan  

E-Print Network (OSTI)

This paper presents the Energy Management Program developed by the Western Electric Company. The program includes managerial accountabilities; administrative and technical activities; and a most recently implemented comprehensive five-year energy planning process. The main focus of this paper is on the energy planning process. This process is designed to (1) provide increased corporate energy direction; (2) assure that all Company locations have comprehensive energy management programs; (3) improve communications to reduce duplication of effort; (4) provide engineering effort and capital required for energy related projects, and (5) provide increased energy conservation input to the Corporate Business Plan.

Mulhern, T. A.

1982-01-01T23:59:59.000Z

418

2011 Annual Planning Summary for Environmental Management (EM)  

Energy.gov (U.S. Department of Energy (DOE))

The ongoing and projected Environmental Assessments and Environmental Impact Statements for 2011 and 2012 within the Office of Environmental Management (EM).

419

Oak Ridge National Laboratory Waste Management Plan, fiscal year 1994. Revision 3  

Science Conference Proceedings (OSTI)

US Department of Energy (DOE) Order 5820.2A was promulgated in final form on September 26, 1988. The order requires heads of field organizations to prepare and to submit updates on the waste management plans for all operations under their purview according to the format in Chap. 6, {open_quotes}Waste Management Plan Outline.{close_quotes} These plans are to be submitted by the DOE Oak Ridge Operations Office (DOE-ORO) in December of each year and distributed to the DP-12, ES&H-1, and other appropriate DOE Headquarters (DOE-HQ) organizations for review and comment. This document was prepared in response to this requirement for fiscal year (FY) 1994. The Oak Ridge National Laboratory (ORNL) waste management mission is reduction, collection, storage, treatment, and disposal of DOE wastes, generated primarily in pursuit of ORNL missions, in order to protect human health and safety and the environment. In carrying out this mission, waste management staff in the Waste Management and Remedial Action Division (WMRAD) will (1) guide ORNL in optimizing waste reduction and waste management capabilities and (2) conduct waste management operations in a compliant, publicly acceptable, technically sound, and cost-efficient manner. Waste management requirements for DOE radioactive wastes are detailed in DOE Order 5820.2A, and the ORNL Waste Management Program encompasses all elements of this order. The requirements of this DOE order and other appropriate DOE orders, along with applicable Tennessee Department of Environment and Conservation and US Environmental Protection Agency (EPA) rules and regulations, provide the principal source of regulatory guidance for waste management operations at ORNL. The objective of this document is compilation and consolidation of information on how the ORNL Waste Management Program is conducted, which waste management facilities are being used to manage wastes, what activities are planned for FY 1994, and how all of the activities are documented.

Turner, J.W. [ed.

1993-12-01T23:59:59.000Z

420

Integrated Environment and Safety and Health Management System (ISMS) Implementation Project Plan  

SciTech Connect

The Integrated Environment, Safety and Health Management System (ISMS) Implementation Project Plan serves as the project document to guide the Fluor Hanford, Inc (FHI) and Major Subcontractor (MSC) participants through the steps necessary to complete the integration of environment, safety, and health into management and work practices at all levels.

MITCHELL, R.L.

2000-01-10T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


421

Developing a Process-Oriented Notation for Modeling Operational Risks - A Conceptual Metamodel Approach to Operational Risk Management in Knowledge Intensive Business Processes within the Financial Industry  

Science Conference Proceedings (OSTI)

According to the Basel II committee operational risks are the least understood and manageable risks in banks. Operational risks in banks are closely linked to the underlying business process landscape. Recently, researchers have suggested to model this ...

Burkhard Weiss; Axel Winkelmann

2011-01-01T23:59:59.000Z

422

Strategy for Developing 10-Year Energy Management Plans at U.S. Army Forces Command Installations.  

SciTech Connect

In order to reach the energy reduction and sustainability goals of the Executive Order 13123, and to minimize overall energy and water costs, the U.S Army Forces Command (FORSCOM), with assistance of PNNL, has embarked on a program to develop comprehensive 10-year Energy Management Plans for each of the 11 major FORSCOM installations. These plans will identify activities and projects critical to the installation's reaching the Executive Order (E.O.) goals as well as help ensure a reliable and secure energy supply. Each FORSCOM installation will be responsible for developing a plan that is closely linked with the installation Master Plan. The Energy Management Plan will cover elements on both the demand side and the supply side, as well as energy/water security assessments and funding/financing resource requirements.

Parker, Graham B. (BATTELLE (PACIFIC NW LAB)); Gillespie, Adrian (U.S. Army Forces Command); Dixon, Douglas R. (BATTELLE (PACIFIC NW LAB)); Brown, Daryl R. (BATTELLE (PACIFIC NW LAB)); Reilly, Raymond W. (BATTELLE (PACIFIC NW LAB)); Warwick, William M. (BATTELLE (PACIFIC NW LAB))

2002-10-01T23:59:59.000Z

423

Managing risk in premium fruit and vegetable supply chains  

E-Print Network (OSTI)

Production planning in premium fresh produce supply chains is challenging due to the uncertainty of both supply and demand. A two-stage planning algorithm using mixed integer linear programming and Monte Carlo simulation ...

Merrill, Joshua Matthew

2007-01-01T23:59:59.000Z

424

Risk management practices in IS outsourcing: an investigation into commercial banks in Nigeria  

Science Conference Proceedings (OSTI)

This research work focuses on the risk management practices adopted by Commercial Banks in Nigeria that are related to the outsourcing of information systems (IS). The need for the research emerged from the lack of studies addressing these problems in ... Keywords: Commercial bank, IS risk management, IS strategic thinking, Information systems outsourcing

Bunmi Cynthia Adeleye; Fenio Annansingh; Miguel Baptista Nunes

2004-04-01T23:59:59.000Z

425

Plan-based policies for efficient multiple battery load management  

Science Conference Proceedings (OSTI)

Efficient use of multiple batteries is a practical problem with wide and growing application. The problem can be cast as a planning problem under uncertainty. We describe the approach we have adopted to modelling and solving this problem, seen as a Markov ...

Maria Fox; Derek Long; Daniele Magazzeni

2012-05-01T23:59:59.000Z

426

State Solid Waste Management and Resource Recovery Plan (Montana)  

Energy.gov (U.S. Department of Energy (DOE))

The State supports the "good management of solid waste and the conservation of natural resources through the promotion or development of systems to collect, separate, reclaim, recycle, and dispose...

427

A 3-Tier Planning Architecture for Managing Tutorial Dialogue  

Science Conference Proceedings (OSTI)

Managing tutorial dialogue is an intrinsically complex task that is only partially covered by current models of dialogue processing. After an analysis of such models identifying their strengths and weaknesses, we propose a flexible, modular, and thus ...

Claus Zinn; Johanna D. Moore; Mark G. Core

2002-06-01T23:59:59.000Z

428

Environmental Management Root Cause Analysis Corrective Action Plan Performance  

Energy.gov (U.S. Department of Energy (DOE))

As part of the Departments effort to build a strong project and contract management foundation,a Root Cause Analysis (RCA) was developed through extensive collaboration between DOE'sHeadquarters...

429

Transmission Rights-of-Way Vegetation Management Plan Framework  

Science Conference Proceedings (OSTI)

The North American Electric Reliability Corporation (NERC) FAC-003-1 standards for vegetation management on electric transmission line rights-of-way (ROWs) have been in place since April 2006. These mandatory standards regulate electric transmission line vegetation management across the United States, and are narrowly focused on minimizing vegetation caused outages in electricity transmission. The NERC FAC-003-1 standards are potentially broadened by the voluntary American National Standards Institute (A...

2008-08-05T23:59:59.000Z

430

UNEP-GEF Renewable Energy Project Financial Risk Management in Developing  

Open Energy Info (EERE)

UNEP-GEF Renewable Energy Project Financial Risk Management in Developing UNEP-GEF Renewable Energy Project Financial Risk Management in Developing Countries Jump to: navigation, search Name UNEP-GEF Renewable Energy Project Financial Risk Management in Developing Countries Agency/Company /Organization United Nations Environment Programme Partner Global Environment Facility Sector Energy Focus Area Renewable Energy Topics Finance, Market analysis Website http://www.unep.fr/energy/acti References UNEP Financial Risk Management [1] "This UNEP/GEF targeted research project aims to catalyse new thinking in the risk management area, examining existing instruments and approaches and suggesting potential modalities for new instruments that could be developed in partnership with private and public sector financial institutions. The

431

Rainwater Wildlife Area, Watershed Management Plan, A Columbia Basin Wildlife Mitigation Project, 2002.  

DOE Green Energy (OSTI)

This Management Plan has been developed by the Confederated Tribes of the Umatilla Indian Reservation (CTUIR) to document how the Rainwater Wildlife Area (formerly known as the Rainwater Ranch) will be managed. The plan has been developed under a standardized planning process developed by the Bonneville Power Administration (BPA) for Columbia River Basin Wildlife Mitigation Projects (See Appendix A and Guiding Policies Section below). The plan outlines the framework for managing the project area, provides an assessment of existing conditions and key resource issues, and presents an array of habitat management and enhancement strategies. The plan culminates into a 5-Year Action Plan that will focus our management actions and prioritize funding during the Fiscal 2001-2005 planning period. This plan is a product of nearly two years of field studies and research, public scoping, and coordination with the Rainwater Advisory Committee. The committee consists of representatives from tribal government, state agencies, local government, public organizations, and members of the public. The plan is organized into several sections with Chapter 1 providing introductory information such as project location, purpose and need, project goals and objectives, common elements and assumptions, coordination efforts and public scoping, and historical information about the project area. Key issues are presented in Chapter 2 and Chapter 3 discusses existing resource conditions within the wildlife area. Chapter 4 provides a detailed presentation on management activities and Chapter 5 outlines a monitoring and evaluation plan for the project that will help assess whether the project is meeting the intended purpose and need and the goals and objectives. Chapter 6 displays the action plan and provides a prioritized list of actions with associated budget for the next five year period. Successive chapters contain appendices, references, definitions, and a glossary. The purpose of the project is to protect, enhance, and mitigate fish and wildlife resources impacted by Columbia River Basin hydroelectric development. The effort is one of several wildlife mitigation projects in the region developed to compensate for terrestrial habitat losses resulting from the construction of McNary and John Day Hydroelectric facilities located on the mainstem Columbia River. While this project is driven primarily by the purpose and need to mitigate for wildlife habitat losses, it is also recognized that management strategies will also benefit many other non-target fish and wildlife species and associated natural resources. The Rainwater project is much more than a wildlife project--it is a watershed project with potential to benefit resources at the watershed scale. Goals and objectives presented in the following sections include both mitigation and non-mitigation related goals and objectives.

Childs, Allen B.

2002-03-01T23:59:59.000Z

432

The framework and tools for the Western Area Power Administration`s Environmental Risk Management Program  

SciTech Connect

Pacific Northwest Laboratory (PNL) is working with various government agencies to develop and implement environmental risk management programs. One such program is being developed for the U.S. Department of Energy`s Western Area Power Administration (Western). In this paper, we describe the risk framework and assessment tools being developed by Western and PNL to help Western`s management staff make effective and defensible decisions on issues that involve environmental risk.

Di Massa, F.V.; Glantz, C.S. [Pacific Northwest Lab., Richland, WA (United States); Roybal, A.L. [Western Area Power Administration, Golden, CO (United States)

1995-06-01T23:59:59.000Z

433

Peaking of world oil production: Impacts, mitigation, & risk management  

SciTech Connect

The peaking of world oil production presents the U.S. and the world with an unprecedented risk management problem. As peaking is approached, liquid fuel prices and price volatility will increase dramatically, and, without timely mitigation, the economic, social, and political costs will be unprecedented. Viable mitigation options exist on both the supply and demand sides, but to have substantial impact, they must be initiated more than a decade in advance of peaking.... The purpose of this analysis was to identify the critical issues surrounding the occurrence and mitigation of world oil production peaking. We simplified many of the complexities in an effort to provide a transparent analysis. Nevertheless, our study is neither simple nor brief. We recognize that when oil prices escalate dramatically, there will be demand and economic impacts that will alter our simplified assumptions. Consideration of those feedbacks will be a daunting task but one that should be undertaken. Our aim in this study is to-- Summarize the difficulties of oil production forecasting; Identify the fundamentals that show why world oil production peaking is such a unique challenge; Show why mitigation will take a decade or more of intense effort; Examine the potential economic effects of oil peaking; Describe what might be accomplished under three example mitigation scenarios. Stimulate serious discussion of the problem, suggest more definitive studies, and engender interest in timely action to mitigate its impacts.

Hirsch, R.L. (SAIC); Bezdek, Roger (MISI); Wendling, Robert (MISI)

2005-02-01T23:59:59.000Z

434

The Mixed Waste Management Facility. Design basis integrated operations plan (Title I design)  

SciTech Connect

The Mixed Waste Management Facility (MWMF) will be a fully integrated, pilotscale facility for the demonstration of low-level, organic-matrix mixed waste treatment technologies. It will provide the bridge from bench-scale demonstrated technologies to the deployment and operation of full-scale treatment facilities. The MWMF is a key element in reducing the risk in deployment of effective and environmentally acceptable treatment processes for organic mixed-waste streams. The MWMF will provide the engineering test data, formal evaluation, and operating experience that will be required for these demonstration systems to become accepted by EPA and deployable in waste treatment facilities. The deployment will also demonstrate how to approach the permitting process with the regulatory agencies and how to operate and maintain the processes in a safe manner. This document describes, at a high level, how the facility will be designed and operated to achieve this mission. It frequently refers the reader to additional documentation that provides more detail in specific areas. Effective evaluation of a technology consists of a variety of informal and formal demonstrations involving individual technology systems or subsystems, integrated technology system combinations, or complete integrated treatment trains. Informal demonstrations will typically be used to gather general operating information and to establish a basis for development of formal demonstration plans. Formal demonstrations consist of a specific series of tests that are used to rigorously demonstrate the operation or performance of a specific system configuration.

NONE

1994-12-01T23:59:59.000Z

435

Water Management Planning: A Case Study at Blue Grass Army Depot  

Science Conference Proceedings (OSTI)

Executive Order 13123, Greening the Government Through Efficient Energy Management, mandates an aggressive policy for reducing potable water consumption at federal facilities. Implementation guidance from the U.S. Department of Energy (DOE) set a requirement for each federal agency to reduce potable water usage by implementing life cycle, cost-effective water efficiency programs that include a water management plan, and not less than four Federal Energy Management Program (FEMP) Best Management Practices (BMPs). The objective of this plan is to gain full compliance with Executive Order 13123 and associated DOE implementation guidance on behalf of Blue Grass Army Depot (BGAD), Richmond, Kentucky. In accordance with this plan, BGAD must: Incorporate the plan as a component of the Installation energy conservation plan Investigate the water savings potential and life-cycle cost effectiveness of the Operations and Maintenance (O&M) and retrofit/replacement options associated with the ten FEMP BMPs Put into practice all applicable O&M options Identify retrofit/replacement options appropriate for implementation (based upon calculation of the simple payback periods) Establish a schedule for implementation of applicable and cost-effective retrofit/replacement options.

Solana, Amy E.; McMordie-Stoughton, Katherine L.

2006-04-03T23:59:59.000Z

436

GHG and Carbon Emissions Management Strategic Planning Tooƒ  

NLE Websites -- All DOE Office Websites (Extended Search)

Strategic Strategic Planning Tools - Localized Strategic Planning For The U.S. Department of Energy National Energy Technology Laboratory Under Contract Number: DE-AM-26-99FT40465 Task 50113, Subtask 3 Augusta Systems Report Number: AS-NETL-50113-3-FR December 31, 2002 DISCLAIMER AND ACKNOWLEDGEMENTS Disclaimer This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference therein to any specific commercial

437

340 waste handling complex: Deactivation project management plan  

SciTech Connect

This document provides an overview of the strategy for deactivating the 340 Waste Handling Complex within Hanford`s 300 Area. The plan covers the period from the pending September 30, 1998 cessation of voluntary radioactive liquid waste (RLW) transfers to the 340 Complex, until such time that those portions of the 340 Complex that remain active beyond September 30, 1998, specifically, the Retention Process Sewer (RPS), can also be shut down and deactivated. Specific activities are detailed and divided into two phases. Phase 1 ends in 2001 after the core RLW systems have been deactivated. Phase 2 covers the subsequent interim surveillance of deactivated and stand-by components during the period of continued RPS operation, through the final transfer of the entire 340 Complex to the Environmental Restoration Contractor. One of several possible scenarios was postulated and developed as a budget and schedule planning case.

Stordeur, R.T.

1998-06-25T23:59:59.000Z

438

RCRA Groundwater Monitoring Plan for Single-Shell Tank Waste Management Area C at the Hanford Site  

SciTech Connect

This document describes the groundwater monitoring plan for Waste Management Area C located in the 200 East Area of the DOE Hanford Site. This plan is required under Resource Conservation and Recovery Act of 1976 (RCRA).

Horton, Duane G.; Narbutovskih, Susan M.

2001-01-01T23:59:59.000Z

439

Savannah River Site`s Site Specific Plan. Environmental restoration and waste management, fiscal year 1992: Executive summary  

SciTech Connect

This report describes the environmental restoration and waste management (ER/WM) planning process, communicates ER/WM`s philosophy and overall strategy for achieving its compliance and cleanup goals, summarizes multi-year program plans and assesses progress made during the previous year. The FYP goal is to ensure that risks to human health and safety and to the environment posed by the Department`s past, present, and future operations are either eliminated to reduced to safer levels by the year 2019. The SSP applies the overall strategic goals and commitments of the FYP, incorporating site-specific and local public considerations. It will address accomplishments since the FY 1990 plan, document planned activities focused on the upcoming fiscal year (FY 1992) and discuss milestones and objectives based on restricted and nonrestricted budget conditions for FY 1993--1997. The SSP is the primary means of demonstrating the relationship of local cleanup and compliance activities to broad environmental goals set forth in the FYP. The SSP provides an important channel for conveying information to regulators, the public, special interest groups, and other DOE organizations. This summary will briefly review the site`s facilities and missions, current and future program objectives, major accomplishments, funding levels, and major milestones for the five-year period.

1991-08-01T23:59:59.000Z

440

Project management plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory. Environmental Restoration Program  

Science Conference Proceedings (OSTI)

The purpose of the Isotopes Facilities Deactivation Project (IFDP) is to place nineteen former isotopes production facilities at the Oak Ridge National Laboratory in a safe, stable, and environmentally sound condition suitable for an extended period of minimum surveillance and maintenance (S&M) and as quickly and economically as possible. Implementation and completion of the deactivation project win further reduce the already small risks to the environment and to public safety and health. Furthermore, the project should result in significant S&M cost savings in the future. The IFDP management plan has been prepared to document the project objectives, define organizational relationships and responsibilities, and outline the management control systems to be employed in the management of the project. The project has adopted a strategy to deactivate the simple facilities first, to reduce the scope of the project, and to gain experience before addressing more difficult facilities. A decision support system is being developed to identify those activities that best promote the project mission and result in largest cost savings. The Work Plan for the Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory (Energy Systems 1994) defines the project schedule, the cost estimate, and the technical approach for the project.

NONE

1995-04-01T23:59:59.000Z

Note: This page contains sample records for the topic "risk management plan" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


441

Waste management/waste certification plan for the Oak Ridge National Laboratory Environmental Restoration Program  

Science Conference Proceedings (OSTI)

This Waste Management/Waste Certification (C) Plan, written for the Environmental Restoration (ER) Program at Oak Ridge National Laboratory (ORNL), outlines the criteria and methodologies to be used in the management of waste generated during ORNL ER field activities. Other agreed upon methods may be used in the management of waste with consultation with ER and Waste Management Organization. The intent of this plan is to provide information for the minimization, handling, and disposal of waste generated by ER activities. This plan contains provisions for the safe and effective management of waste consistent with the U.S. Environmental Protection Agency`s (EPA`s) guidance. Components of this plan have been designed to protect the environment and the health and safety of workers and the public. It, therefore, stresses that investigation derived waste (IDW) and other waste be managed to ensure that (1) all efforts be made to minimize the amount of waste generated; (2) costs associated with sampling storage, analysis, transportation, and disposal are minimized; (3) the potential for public and worker exposure is not increased; and (4) additional contaminated areas are not created.

Clark, C. Jr.; Hunt-Davenport, L.D.; Cofer, G.H.

1995-03-01T23:59:59.000Z

442

EMAB Risk Subcommittee Interim Report  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

FIRST INTERIM REPORT TO THE ENVIRONMENTAL MANAGEMENT ADVISORY BOARD Incorporating Risk and Sustainability into Decision Making Submitted by the EMAB Risk Subcommittee December 3, 2012 Background: In December 2011, then Acting Assistant Secretary for Environmental Management David Huizenga, asked the Environmental Management Advisory Board (EMAB or Board) to establish a Risk Subcommittee. In February 2012, the Subcommittee's Work Plan was approved. Under the Work Plan, the purpose of the Subcommittee is to evaluate "risk-informed decision making," specifically whether the prioritization tool developed by the Consortium for Risk Evaluation with Stakeholder Participation (CRESP) for use at the Oak Ridge Reservation (Oak Ridge) is one that

443

Decommissioning Standard Review Plans and Risk-Informing Decommissioning Regulation: Selected 1999 Industry/NRC Decommissioning Lice nsing Interactions  

Science Conference Proceedings (OSTI)

This report describes the technical support EPRI provided the Nuclear Energy Institute (NEI) Decommissioning Working Group in 1999. This volume includes two initiatives that produced four draft Decommissioning Standard Review Plans (DSRPs). It also includes an evaluation entitled Spent Fuel Pool Seismic Failure Frequency in Support of Risk-Informed Decommissioning -- Emergency Planning.

1999-10-31T23:59:59.000Z

444

Managing the Risks of Climate Change and Terrorism  

SciTech Connect

Society has difficult decisions to make about how best to allocate its resources to ensure future sustainability. Risk assessment can be a valuable tool: it has long been used to support decisions to address environmental problems. But in a time when the risks to sustainability range from climate change to terrorism, applying risk assessment to sustainability will require careful rethinking. For new threats, we will need a new approach to risk assessment.

Rosa, Eugene; Dietz, Tom; Moss, Richard H.; Atran, Scott; Moser, Susanne

2012-04-07T23:59:59.000Z

445

Program Planning & Management Forms (5000-5999) | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Program Planning & Management Forms (5000-5999) Program Planning & Management Forms (5000-5999) Program Planning & Management Forms (5000-5999) DOE F 5160.1 (pdf) Reprogramming, Restructuring, and Appropriation Transfer Summary DOE F 5480.4 (pdf) Contractor Employee Occupational Safety or Health Complaint DOE F 5484.3 (pdf) Individual Accident/Incident Report DOE F 5484.4 (pdf) Tabulation of Work-Hours and Vehicle Usage, and Property Valuation DOE F 5500.2 (pdf) Operational Incident Report DOE F 5631.18 (pdf) Security Acknowledgement DOE F 5631.20 (fillable pdf) Request for Visit or Access Approval DOE F 5631.29 (pdf) Security Termination Statement DOE F 5631.34 (pdf) Data Report on Spouse/Cohabitant DOE F 5634.1 (pdf) Safeguards and Security Survey Report DOE F 5635.9 (pdf) Record of Destruction

446

Environmental guidelines for Development of Cultural Resource Management plans. Working draft for comment  

Science Conference Proceedings (OSTI)

DOE has stewardship responsibilities for managing the cultural resources remaining on DOE-owned and other lands impacted by DOE programs. Goal of the DOE-wide Cultural Resource Management (CRM) program is to identify and consolidate compliance actions associated with statutory and regulatory requirements. This document is to provide guidelines to DOE field managers; its implementation is intended to assure that each DOE facility and program complies with executive orders, statutes, and regulations governing the management of cultural resources. It covers CRM goals, existing conditions, CRM methods, CRM procedures and administration, and plan attachments. Glossary, legislation, and documents are covered in appendices.

Not Available

1994-04-01T23:59:59.000Z

447

Least cost planning regulation; Restructuring the roles of utility management and regulators  

Science Conference Proceedings (OSTI)

This purpose of this paper is to examine the roles of regulators in long-range utility resource planning. Summary of major points include: Three regulatory options exist today with respect to integrated resource planning: Command and Control Regulation; Incentive Regulation; and Flexible Regulation. If deregulation is likely in the end, flexible regulation today offers the greatest promise of long-run success. Flexible regulation requires commissions and companies to agree on underlying principles and for utility management to exercise defensible judgment.

Donovan, D.J.; Goldfield, S.R. (Richard Metzler and Associates, Northbrook, IL (US))

1992-01-01T23:59:59.000Z

448

EIS-0480: Long-Term Experimental and Management Plan for the Operation of Glen Canyon Dam  

Energy.gov (U.S. Department of Energy (DOE))

Two agencies of the Department of the Interior, Bureau of Reclamation and National Park Service, are jointly preparing a Long-Term Experimental and Management Plan for the Glen Canyon Dam and an EIS for adoption of the Plan. The Glen Canyon Dam, on the Colorado River in northern, Arizona, generates hydroelectric power that is marketed by DOE's Western Area Power Administration, a cooperating agency.

449

RCRA Assessment Plan for Single-Shell Tank Waste Management Area A-AX at the Hanford Site  

Science Conference Proceedings (OSTI)

This document describes a groundwater assessment plan for the single-shell tank systems in Waste Management Area A-AX at the Hanford Site.

Narbutovskih, Susan M.; Chou, Charissa J.

2006-03-03T23:59:59.000Z

450

Operable Unit 3-13, Group 3, Other Surface Soils Remediation Sets 4-6 (Phase II) Waste Management Plan  

SciTech Connect

This Waste Management Plan describes waste management and waste minimization activities for Group 3, Other Surface Soils Remediation Sets 4-6 (Phase II) at the Idaho Nuclear Technology and Engineering Center located within the Idaho National Laboratory. The waste management activities described in this plan support the selected response action presented in the Final Record of Decision for Idaho Nuclear Technology and Engineering Center, Operable Unit 3-13. This plan identifies the waste streams that will be generated during implementation of the remedial action and presents plans for waste minimization, waste management strategies, and waste disposition.

G. L. Schwendiman

2006-07-01T23:59:59.000Z

451

ORNL long-range environmental and waste management plan: Program overview and summary  

SciTech Connect

The primary purpose of this report is to provide a thorough and systematic planning document to reflect the continuing process of site assessment, strategy development, and planning for the current and long-term control of environmental issues, waste management practices, and remedial action requirements. The docuemnt also provides an estimate of the resources required to implement the current plan. This document is not intended to be a budget document: it is, however, intended to provide guidance to both Martin Marietta Energy Systems, Inc., and the US Department of Energy (DOE) Management as to the near order of magnitude of the resources (primarily funding requirements) and the time frame required to execute the strategy in the present revision of the plan. The near-term (one to three years) part of the plan is a realistic assessment of the current program and ongoing capital projects and reflects the efforts preceived to be necessary to comply with all current state and federal regulations and DOE orders. It also should be in general agreement with current budget (funding) requests and obligations for these immediate years. Beyond the immediate time frame, the document reflects the strategy and the project and funding estimates as a snapshot at the time of publication. Annual revision will reflect the continuing evoltuion and development of environmental and waste management processes, characterizations, remedial actions, regulations, an strategies for the establishment and conduct of a comprehensive environmental and waste management program. 15 figs., 10 tabs.

Bates, L.D.; Berry, J.B.; Butterworth, G.E.; du Mont, S.P.; Easterday, C.A.; Geisler, A.H.; Hill, L.G.; Kendrick, C.M.; McNeese, L.E.; Myrick, T.E.; Pudelek, R.E.; Rohwer, P.S.; Scanlan, T.F.; Stratton, L.E.; Trabalka, J.R.; Youngblood, E.L.

1988-04-01T23:59:59.000Z

452

Site specific plan. [Environmental Restoration and Waste Management, Savannah River Site  

SciTech Connect

The Environmental Restoration and Waste Management Five-Year Plan (FYP) covers the period for FY 1989 through FY 1995. The plan establishes a Department of Energy -- Headquarters (DOE-HQ) agenda for cleanup and compliance against which overall progress can be measured. The FYP covers three areas: Corrective Activities, Environmental Restoration, and Waste Management Operations. Corrective Activities are those activities necessary to bring active or standby facilities into compliance with local, state, and federal environmental regulations. Environmental restoration activities include the assessment and cleanup of surplus facilities and inactive waste sites. Waste management operations includes the treatment, storage, and disposal of wastes which are generated as a result of ongoing operations. This Site Specific Plan (SSP) has been prepared by the Savannah River Site (SRS) in order to show how environmental restoration and waste management activities that were identified during t