Powered by Deep Web Technologies
Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


1

Standard Review Plan (SRP) Modules | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Quality Assurance » Standard Quality Assurance » Standard Review Plan (SRP) Modules Standard Review Plan (SRP) Modules Standard Review Plan - Critical Decision Handbook Overview Project Management Project Execution Plan Review Module (RM) Risk Management RM Integrated Project Team RM Earned Value Management System RM Acquisition Strategy RM Decommissioning Plan RM Site Transition Guidance Engineering and Design Conceptual Design RM Preliminary Design RM Final Design RM Construction Readiness RM Checkout, Testing, and Commissioning Plan RM Readiness Review RM Seismic Design Expectations Report Technology Readiness Assessment Report External Technical Review Report Preparation for Facility Operations RM Safety Safety Design Strategy RM Conceptual Safety Design RM Preliminary Safety Design RM Facility Disposition Safety Strategy RM

2

EM Capital and Major Operating Project Standard Review Plan Edition Two  

Energy.gov (U.S. Department of Energy (DOE))

This memorandum introduces the Second Edition of the Capital and Major Operations Projects Standard Review Plan (SRP).

3

Standard Review Plan Overview  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Technical Framework for EM Projects Critical Decision (CD) Technical Framework for EM Projects Critical Decision (CD) Milestones Review & Approval Standard Review Plan (SRP) E n v i r o n m e n t a l M a n a g e m e n t DOE - EM - SRP - 2010 2nd Edition Overview March 2010 This page intentionally left blank. Standard Review Plan, 2 nd Edition, March 2010 1 Standard Review Plan Overview Technical Framework for EM Projects Critical Decision Milestones Review and Approval The Office of Environmental Management (EM) is responsible for managing the design, construction, operation, and eventual disposition of mission-critical projects/facilities. Coupled with this ongoing mission is the added responsibility for EM to diligently leverage and apply American Recovery and Reinvestment Act (ARRA) funds to accelerate the completion of its

4

Standard Review Plan Preparation for Facility Operations Strengthening...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Strengthening Line Management Oversight and Federal Monitoring of Nuclear Facilities August 2013 2 OFFICE OF ENVIRONMENTAL MANAGEMENT Standard Review Plan (SRP) Preparation...

5

SRP - Net Metering | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

SRP - Net Metering SRP - Net Metering SRP - Net Metering < Back Eligibility Commercial Residential Savings Category Buying & Making Electricity Solar Wind Program Info State Arizona Program Type Net Metering Provider SRP Salt River Project (SRP) modified an existing net-metering program for residential and commercial customers in November 2013. Net metering is now available to customers who generate electricity using photovoltaic (PV), geothermal, or wind systems up to 300 kilowatts (kW) in AC peak capacity. The kilowatt-hours (kWh) delivered to SRP are subtracted from the kWh delivered from SRP for each billing cycle. If the kWh calculation is net positive for the billing cycle, SRP will bill the net kWh to the customer under the applicable price plan, Standard Price Plan E-21, E-23, E-26,

6

Standard Review Plan Preparation for Facility Operations Strengthening Line Management Oversight and  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Standard Review Plan Standard Review Plan Preparation for Facility Operations Strengthening Line Management Oversight and Federal Monitoring of Nuclear Facilities August 2013 2 OFFICE OF ENVIRONMENTAL MANAGEMENT Standard Review Plan (SRP) Preparation for Facility Operations Applicability CD-0 CD-1 CD-2 CD-3 CD-4 Operation Post Operation August 2013 3 Table of Contents Objective ......................................................................................................................................... 4 Requirements .................................................................................................................................. 4 Primary References ......................................................................................................................... 6

7

Seismic Record Processing Program (SRP), Version 1.03  

SciTech Connect

The Seismic Record Processing Program (SRP) is an interactive computer code developed for the calculation of artificial earthquake records that comply with the US Nuclear Regulatory Commission Standard Review Plan. The basic objective of SRP is the calculation of artificial seismic time histories that correspond to Design Response Spectra specified in the US Atomic Energy Commission Regulatory Guide 1.60 and/or the Power Spectral Density (PSD) requirements of the NRC Standard Review Plan. However, SRP is a general computer code and can accommodate any arbitrarily specified Target Response Spectra (TRS) or PSD requirements. In addition, among its other futures, SRP performs quadratic baseline correction and calculates correlations factors for a set of up to three earthquake records. This manual is prepared in two parts. The first part describes the methodologies and criteria used while the second is a user`s manual. In section 1 of the first part, the techniques used for the adjustment of a given earthquake record to a required TRS family of curves for a set of specified damping ratios are presented. Similarly, in section 2 of the first part, the PSD of an earthquake record is compared to a target PSD and adjusted accordingly. Sections 3 and 4 of the first part deal with the subjects of baseline correction and correlation of earthquake records, respectively. The second part is the user`s manual. The user`s manual contains a list of the computer hardware requirements, instructions for the program installation, a description of the user generated input files, and a description of all the program menus and commands.

Karabalis, D.L.; Cokkinides, G.J.; Rizos, D.C. [South Carolina Univ., Columbia, SC (United States). Coll. of Engineering

1992-04-01T23:59:59.000Z

8

SRP - Residential Energy Efficiency Rebate Program | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

SRP - Residential Energy Efficiency Rebate Program SRP - Residential Energy Efficiency Rebate Program Eligibility Residential Savings For Home Weatherization Commercial...

9

Human Factors Review Plan  

SciTech Connect

''Human Factors'' is concerned with the incorporation of human user considerations into a system in order to maximize human reliability and reduce errors. This Review Plan is intended to assist in the assessment of human factors conditions in existing DOE facilities. In addition to specifying assessment methodologies, the plan describes techniques for improving conditions which are found to not adequately support reliable human performance. The following topics are addressed: (1) selection of areas for review describes techniques for needs assessment to assist in selecting and prioritizing areas for review; (2) human factors engineering review is concerned with optimizing the interfaces between people and equipment and people and their work environment; (3) procedures review evaluates completeness and accuracy of procedures, as well as their usability and management; (4) organizational interface review is concerned with communication and coordination between all levels of an organization; and (5) training review evaluates training program criteria such as those involving: trainee selection, qualification of training staff, content and conduct of training, requalification training, and program management.

Paramore, B.; Peterson, L.R. (eds.)

1985-12-01T23:59:59.000Z

10

DOE Retrospective Review Plan Report  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

DOE Retrospective Review Plan Report May 2012 Agency Sub- agency RIN OMB Control Number Title of Initiative RulelCR Brief Description Actual or Target Completion Date...

11

ORISE: Scientific Peer Review Planning  

NLE Websites -- All DOE Office Websites (Extended Search)

Planning Planning Woman participating in a peer review The Oak Ridge Institute for Science and Education (ORISE) begins the peer review planning process by analyzing the purpose of the funds to be distributed. Because each agency's needs are different, ORISE then designs and manages a flexible, scientific peer review process that can be modified based on a sponsor's regulatory, policy and operational requirements. ORISE's existing tools and systems, and knowledge of reviewing proposals from a government agency perspective, are helping to promote the quality and credibility of scientific information and funded research. ORISE's peer review planning process ensures each objective review is completed on schedule, within budget and with a high degree of process integrity.

12

Standard Review Plan - Overview | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Review Plan Overview More Documents & Publications Preliminary Safety Design RM Quality Assurance for Critical Decision Reviews RM Checkout, Testing, and Commissioning Plan RM...

13

Decommissioning Plan RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Decommissioning Plan Review Module Decommissioning Plan Review Module March 2010 CD-0 O 0 C OFFICE OF D C CD-1 F ENVIRO Standard R Decomm Rev Critical Decisi CD-2 M ONMENTAL Review Plan missioning view Module ion (CD) Ap CD March 2010 L MANAGE n (SRP) g Plan e plicability D-3 EMENT CD-4 Post Oper ration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-1189-2008,

14

Project Execution Plan RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Project Execution Plan (PEP) Review Module Project Execution Plan (PEP) Review Module March 2010 CD-0 O 0 OFFICE OF P C CD-1 F ENVIRO Standard R Project E Rev Critical Decis CD-2 M ONMENTAL Review Plan Execution view Module sion (CD) Ap CD March 2010 L MANAGE n (SRP) n Plan e pplicability D-3 EMENT CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-1189-2008,

15

The Standard Review Plan for Review of License Renewal Applications for Nuclear Power  

E-Print Network (OSTI)

Plants (SRP-LR) provides guidance to Nuclear Regulatory Commission staff reviewers in the Office of Nuclear Reactor Regulation. These reviewers perform safety reviews of applications to renew nuclear power plant licenses in accordance with Title 10 of the Code of Federal Regulations Part 54. The principal purposes of the SRP-LR are to ensure the quality and uniformity of staff reviews and to present a well-defined base from which to evaluate applicant programs and activities for the period of extended operation. The SRP-LR is also intended to make information about regulatory matters widely available, to enhance communication with interested members of the public and the nuclear power industry, and to improve public and industry understanding of the staff review process. The safety review is based primarily on the information provided by the applicant in a license renewal application. Each of the individual SRP-LR sections addresses (1) who performs the review, (2) the matters that are reviewed, (3) the basis for review, (4) the way the review is accomplished, and (5) the conclusions that are sought.

Power Plants

2005-01-01T23:59:59.000Z

16

Commissioning Plan RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Checkout, Testing, and Checkout, Testing, and Commissioning Plan Review Module March 2010 CD-0 O Ch 0 OFFICE OF heckout, T C CD-1 F ENVIRON Standard R Testing, a Revi Critical Decis CD-2 Ma NMENTAL Review Plan and Com iew Module sion (CD) Ap CD arch 2010 L MANAGE n (SRP) mmissioni e pplicability D-3 EMENT ing Plan CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-1189-2008,

17

REScheck Residnetial Plan Review Quick Reference Guide  

NLE Websites -- All DOE Office Websites (Extended Search)

RESIDENTIAL PLAN REVIEW RESIDENTIAL PLAN REVIEW QUICK REFERENCE GUIDE Plan review for energy code compliance can be conducted quickly and efficiently. The U.S. Department of Energy's REScheck Compliance Software is designed to create simplified compliance certificates that can be easily reviewed by enforcement personnel. This Quick Reference Guide will guide you, step-by-step, through a typical plan review process. There are three basic steps for conducting a building energy code plan review: Step 1: Verify the documentation has been correctly prepared. Step 2: Verify the levels of efficiency shown on the plans meet or exceed that shown in the documentation. Step 3: Verify all of the information to conduct a field inspection is included in the plans or documentation for the inspector to use on site.

18

SRP RADIOACTIVE WASTE RELEASES S  

Office of Scientific and Technical Information (OSTI)

. . . . . . -- SRP RADIOACTIVE WASTE RELEASES S t a r t u p t h r o u g h 1 9 5 9 September 1 9 6 0 _- R E C O R D - W O R K S T E C H N I C A L D E P A R T M E N T 1 J. E. C o l e , W i l n i 1 4 W. P. 3ebbii 3 H. Worthington, Wilm 16 C. $?. P~.t-Lei-s~:; - 5 J. D. E l l e t t - 17 E. C. Morris 6 F. H. Endorf 19 3 . L. &tier 7 K. W. F r e n c h 20 bi. C . 3 e i n i g 8 J. K. Lower 2 1 2. 3 . 3 G : - x r 9 K. W. M i l l e t t 22 R . FJ . V 2 x 7 : W ~ ~ C k 1 c - 2 J. B. Tinker, W i h L-, i . c . E?-ens 4 W F i l e P. 3 . K t B U ? & J. A. Monier, Jr. 13. : . A. KcClesrer. 1 0 M. 2 . Wahl . - 23 C. Ashley C. W. J. Wende 24 T I S F i l e 11 J. W. Morris - 2s T'pC File D. E. Waters 26 P3D F i l e , 736-C R. B. Fenninger 33 V l ~ a l Records F i l e 12 W. P. Overbeck - 27 -23 P3D % x : r a Czpies P33 2e:ol.d C ~ p l *iB+ ' / - - & OF THIS DQCUMENT I S UNuMITEI) E. 1. ciu /'(I,\ 7' d

19

Planning and Conducting Readiness Reviews  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

3006-2010 3006-2010 ________________________ Superseding DOE-STD-3006-2000 June 2000 DOE STANDARD PLANNING AND CONDUCTING READINESS REVIEWS U.S. Department of Energy AREA OPER Washington, D.C. 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. TS This document has been reproduced directly from the best available copy. Available to DOE and DOE contractors from ES&H Technical Information Services, U.S. Department of Energy, (800) 473-4375, fax: (301) 903-9823. Available to the public from the U.S. Department of Commerce, Technology Administration, National Technical Information Service, Springfield, VA 22161; (703) 605-6000. DOE-STD-3006-YR i CONTENTS FOREWORD................................................................................................................................. 1

20

Project Execution Plan Review Module (RM)  

Energy.gov (U.S. Department of Energy (DOE))

The Project Execution Plan (PEP) Review Module (RM) is a tool that assists DOE federal project review teams in evaluating the adequacy of the PEP development and maintenance for projects of any...

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


21

Readiness Review RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Readiness Review Module Readiness Review Module March 2010 CD-0 O 0 OFFICE OF C CD-1 F ENVIRO Standard R Readin Rev Critical Decis CD-2 M ONMENTAL Review Plan ness Rev view Module sion (CD) Ap CD March 2010 L MANAGE n (SRP) view e pplicability D-3 EMENT CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-

22

Salt River Project SRP | Open Energy Information  

Open Energy Info (EERE)

SRP SRP Jump to: navigation, search Name Salt River Project (SRP) Place Tempe, Arizona Zip 85281-1298 Sector Biomass, Solar Product US utility which sources a percentage of its electricity from biomass plants. It is also involved in the solar power industry. Coordinates 33.42551°, -111.937419° Loading map... {"minzoom":false,"mappingservice":"googlemaps3","type":"ROADMAP","zoom":14,"types":["ROADMAP","SATELLITE","HYBRID","TERRAIN"],"geoservice":"google","maxzoom":false,"width":"600px","height":"350px","centre":false,"title":"","label":"","icon":"","visitedicon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"wmsoverlay":"","layers":[],"controls":["pan","zoom","type","scale","streetview"],"zoomstyle":"DEFAULT","typestyle":"DEFAULT","autoinfowindows":false,"kml":[],"gkml":[],"fusiontables":[],"resizable":false,"tilt":0,"kmlrezoom":false,"poi":true,"imageoverlays":[],"markercluster":false,"searchmarkers":"","locations":[{"text":"","title":"","link":null,"lat":33.42551,"lon":-111.937419,"alt":0,"address":"","icon":"","group":"","inlineLabel":"","visitedicon":""}]}

23

Construction Project Safety and Health Plan RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Construction Project Safety and Construction Project Safety and Health Plan Review Module March 2010 CD-0 Co 0 Le OFFICE O onstructi CD-1 This Review ssons learned f OF ENVIRO Standard ion Proje Rev Critical D CD-2 M w Module has b from the pilot h ONMENTA Review Pla ect Safety view Modul Decision (CD CD March 2010 been piloted at have been inco AL MANAG an (SRP) y and He le D) Applicabili D-3 the INL IWTU orporated in Re GEMENT alth Plan ity CD-4 U Project. eview Module. n Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM

24

City of Dallas - Green Building Expedited Plan Review | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Administration Other Agencies You are here Home Savings City of Dallas - Green Building Expedited Plan Review City of Dallas - Green Building Expedited Plan Review...

25

DOE Retrospective Review Plan Report May 2012 | Department of...  

NLE Websites -- All DOE Office Websites (Extended Search)

Report May 2012 DOE Retrospective Review Plan Report May 2012 May2012 ReportDOE525.pdf More Documents & Publications DOE Retrospective Review Plan and Burden Reduction Report...

26

1969 AUDIT OF SRP RADIOACTIVE WASTE  

Office of Scientific and Technical Information (OSTI)

969 AUDIT OF SRP RADIOACTIVE WASTE 969 AUDIT OF SRP RADIOACTIVE WASTE bY C . Ashley A p r i l 1970 Radiological Sciences Division Savannah River Laboratory E. 1. du Pont de Nemours & Co. Aiken, South Carolina 29801 DISCLAIMER Portions of this document may be illegible in electronic image products. Images are produced from the best avaiiable original document. . . . CONTENTS Page I n t r o d u c t i o n . . . . . . . . . . . . . . . . . . . . . . . . 5 Summary . . . . . . . . . . . . . . . . . . . . . . . . . . 5 Releases t o t h e Atmosphere . . . . . . . . . . . . . . . . . 6 S e p a r a t i o n s Areas . . . . . . . . . . . . . . . . . . . . 6 TNX and Building 773-A . . . . . . . . . . . . . . . . . 8 Reactor Areas . . . . . . . . . . . . . . . . . . . . . . 7 Releases t o E f f l u e n t Streams . . . . . . . . . . . . . . . . 8 S e p a r a t i o n s Areas . . . . . . . . . . . . . . . . . . . . 8 DArea . . . . . . . . . . . . . . . . . . . . . . . . . 8 R e a c t o r A r e a s . . . . . . . . . . . . . . . . . . . . . . 9

27

Strategic Information Systems Planning: A Review  

E-Print Network (OSTI)

Information has emerged as an agent of integration and the enabler of new competitiveness for today's enterprise in the global marketplace. However, has the paradigm of strategic planning changed sufficiently to support the new role of information systems and technology? We reviewed the literature for commonly used or representative information planning methodologies and found that a new approach is needed. There are six methodologies reviewed in this paper. They all tend to regard planning as a separate stage which does not connect structurally and directly to the information systems development. An integration of planning with development and management through enterprise information resources - which capture and characterize the enterprise - will shorten the response cycle and even allow for economic evaluation of information system investment.

Somendra Pant; Cheng Hsu

1995-01-01T23:59:59.000Z

28

Revision 2 Yucca Mountain Review Plan  

E-Print Network (OSTI)

The Yucca Mountain Review Plan provides guidance for the U.S. Nuclear Regulatory Commission staff to evaluate a U.S. Department of Energy license application for a geologic repository. It is not a regulation and does not impose regulatory requirements. The licensing criteria are contained in the U.S. Code of Federal Regulations (CFR) Title 10, Part 63

unknown authors

2003-01-01T23:59:59.000Z

29

Quality Assurance for Critical Decision Reviews RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Quality Assurance for Quality Assurance for Critical Decision Reviews Module March 2010 CD-0 O 0 OFFICE OF Q C CD-1 F ENVIRO Standard R Quality A Rev Critical Decis CD-2 M ONMENTAL Review Plan Assuranc view Module sion (CD) Ap CD March 2010 L MANAGE n (SRP) e (QA) e pplicability D-3 EMENT CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-1189-2008,

30

Review of the Headquarters Facilities Emergency Response Plans  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

March 2002 Review of the Headquarters Facilities Emergency Response Plans OVERSIGHT Table of Contents 1.0 INTRODUCTION ......

31

U-026: Cisco Small Business SRP500 Series Bug Lets Remote Users Inject  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

6: Cisco Small Business SRP500 Series Bug Lets Remote Users 6: Cisco Small Business SRP500 Series Bug Lets Remote Users Inject Commands U-026: Cisco Small Business SRP500 Series Bug Lets Remote Users Inject Commands November 3, 2011 - 8:15am Addthis PROBLEM: Cisco Small Business SRP500 Series Bug Lets Remote Users Inject Commands. PLATFORM: The following models are affected when running firmware prior to version 1.1.24: Cisco SRP521W Cisco SRP526W Cisco SRP527W The following models are affected when running firmware prior to version 1.2.1: Cisco SRP541W Cisco SRP546W Cisco SRP547W ABSTRACT: A remote user can create a URL that, when loaded by the target authenticated administrative user, will execute arbitrary commands on the target system. reference LINKS: Advisory ID: cisco-sa-20111102-srp500 SecurityTracker Alert ID: 1026266

32

Water budget for SRP burial ground area  

SciTech Connect

Radionuclide migration from the SRP burial ground for solid low-level waste has been studied extensively. Most of the buried radionuclides are fixed on the soil and show negligible movement. The major exception is tritium, which when leached from the waste by percolating rainfall, forms tritiated water and moves with the groundwater. The presence of tritium has been useful in tracing groundwater flow paths to outcrop. A subsurface tritium plume moving from the southwest corner of the burial ground toward an outcrop near Four Mile Creek has been defined. Groundwater movement is so slow that much of the tritium decays before reaching the outcrop. The burial ground tritium plume defined to date is virtually all in the uppermost sediment layer, the Barnwell Formation. The purpose of the study reported in this memorandum was to investigate the hypothesis that deeper flow paths, capable of carrying substantial amounts of tritium, may exist in the vicinity of the burial ground. As a first step in seeking deeper flow paths, a water budget was constructed for the burial ground site. The water budget, a materials balance used by hydrologists, is expressed in annual area inches of rainfall. Components of the water budget for the burial ground area were analyzed to determine whether significant flow paths may exist below the tan clay. Mean annual precipitation was estimated as 47 inches, with evapotranspiration, run-off, and groundwater recharge estimated as 30, 2, and 15 inches, respectively. These estimates, when combined with groundwater discharge data, suggest that 5 inches of the groundwater recharge flow above the tan clay and that 10 inches flow below the tan clay. Therefore, two-thirds of the groundwater recharge appears to follow flow paths that are deeper than those previously found. 13 references, 10 figures, 5 tables.

Hubbard, J.E.; Emslie, R.H.

1984-03-19T23:59:59.000Z

33

Reviewing Measurement and Verification Plans for Federal ESPC Projects  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Reviewing Measurement & Verification Plans Reviewing Measurement & Verification Plans for Federal ESPC Projects February 2007 Federal Energy Management Program (FEMP) Office of Energy Efficiency and Renewable Energy U.S. Department of Energy This document was developed for the U.S. Department of Energy's Federal Energy Management Program by Nexant, Inc., and Lawrence Berkeley National Laboratory. This document is posted on FEMP's web site at www.eere.energy.gov/femp/financing/ . [Headers and footers only revised 12/08] Reviewing M&V Plans Contents REVIEWING MEASUREMENT AND VERIFICATION PLANS FOR FEDERAL ESPC PROJECTS ............................................................................................................ 1 STEP 1 - PREPARE CUSTOM REPORT AND CHECKLIST FROM TEMPLATE .......................... 1

34

DOE Retrospective Review Plan and Burden Reduction Report - December...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

and Burden Reduction Report - December 18, 2012 DOE Retrospective Review Plan and Burden Reduction Report - December 18, 2012 DOE EO 13563 December 2012 Update Report and Burden...

35

NSLS Committees | Work Planning/Permit Review Committee  

NLE Websites -- All DOE Office Websites (Extended Search)

require enhanced work planning. Committees review and approve submitted work permits. NSLS reports to Operations Section Head, Emil Zitvogel. NSLS-II reports to ESH Manager,...

36

Review of DOE HQ Emergency Response Plans and Performance  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Review of DOE Headquarters Emergency Response Plans and Performance March 2003 Prepared by Office of Independent Oversight and Performance Assurance Office of the Secretary of...

37

A Review of Operations Research in Mine Planning  

Science Conference Proceedings (OSTI)

Applications of operations research to mine planning date back to the 1960s. Since that time, optimization and simulation, in particular, have been applied to both surface and underground mine planning problems, including mine design, long-and short-term ... Keywords: dispatching, equipment selection, literature review, mine design, mine planning, open-pit mining, optimization, production scheduling, simulation, underground mining

Alexandra M. Newman; Enrique Rubio; Rodrigo Caro; Andrs Weintraub; Kelly Eurek

2010-05-01T23:59:59.000Z

38

Independent Oversight Review of DOE Headquarters Emergency Response Plans  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Review of DOE Headquarters Emergency Response Review of DOE Headquarters Emergency Response Plans and Performance, March 2003 Independent Oversight Review of DOE Headquarters Emergency Response Plans and Performance, March 2003 The Secretary of Energy's Office of Independent Oversight and Performance Assurance (OA) conducted a review of emergency response plans and performance at DOE Headquarters (HQ) in February 2003. The purpose of this review was to evaluate the readiness and effectiveness of the DOE and National Nuclear Security Administration (NNSA) emergency response teams for a postulated emergency at a field site, and the HQ Incident Command Team for an emergency affecting the Forrestal building. In addition, OA was tasked to evaluate the current status of DOE's Continuity of Operations (COOP) program plans and provide recommendations

39

Bald and Golden Eagles of the SRP. (Annual report, 1986)  

Science Conference Proceedings (OSTI)

Both Bald and Golden Eagles have a prior history of occurrence on the Savannah River Plant (SRP). Sightings of Bald Eagles have been uncommon but persistent, while Golden Eagle sightings have been rare. A one-year survey was conducted to assess the use of the SRP by these two species. Thirty-six Bald Eagles were seen during the study period. No Golden Eagles were observed. Over 90% of the Bald Eagle sightings were on Par Pond; three out of four of these birds were adults. Thirteen percent of the sightings were of paired birds, and the remainder were of solitary individuals. Bald Eagles were observed during every month of the survey. The majority were seen between November and May. Sightings were evenly divided between morning and afternoon hours. Two marked Bald Eagles were observed. Since the conclusion of this study, twenty-two Bald Eagles have been reported. Six were new locality records for the SRP. Four of these sightings were on L-Lake. Bald Eagle use of the SRP is higher than was previously thought; Golden Eagle use remains rare.

Mayer, J.J.; Hoppe, R.T.; Kennamer, R.A.

1986-01-01T23:59:59.000Z

40

Chandler - Expedited Plan Review for Green Buildings | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Chandler - Expedited Plan Review for Green Buildings Chandler - Expedited Plan Review for Green Buildings Chandler - Expedited Plan Review for Green Buildings < Back Eligibility Commercial Schools Savings Category Heating & Cooling Home Weatherization Construction Commercial Weatherization Commercial Heating & Cooling Design & Remodeling Bioenergy Solar Lighting Windows, Doors, & Skylights Heating Buying & Making Electricity Water Water Heating Wind Program Info State Arizona Program Type Green Building Incentive Provider City of Chandler The mayor and city council of Chandler, AZ adopted Resolution 4199 in June 2008, establishing incentives for green building in the private sector. Permit applications for buildings registered with the US Green Building Council's (USGBC) Leadership in Energy and Environmental Design (LEED) for

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


41

DOE Retrospective Review Plan and Burden Reduction Report July...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

and Burden Reduction Report July 29, 2013 DOE Retrospective Review Plan and Burden Reduction Report July 29, 2013 DOE 13563 and ICR Report - Final.pdf More Documents & Publications...

42

REScheck Residnetial Plan Review Quick Reference Guide  

NLE Websites -- All DOE Office Websites (Extended Search)

spaces such as a garage, should be included in the wall area. Step Four: Verify the insulation R-values shown on the building plans meet or exceed the values in the Cavity R-value...

43

Review of DOE HQ Emergency Response Plans and Performance  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Review of Review of DOE Headquarters Emergency Response Plans and Performance March 2003 Prepared by Office of Independent Oversight and Performance Assurance Office of the Secretary of Energy OFFICE OF INDEPENDENT OVERSIGHT AND PERFORMANCE ASSURANCE REVIEW OF DOE HEADQUARTERS EMERGENCY RESPONSE PLANS AND PERFORMANCE EXECUTIVE SUMMARY INTRODUCTION The Secretary of Energy's Office of Independent Oversight and Performance Assurance (OA) conducted a review of emergency response plans and performance at DOE Headquarters (HQ) in February 2003. The purpose of this review was to evaluate the readiness and effectiveness of the DOE and National Nuclear Security Administration (NNSA) emergency response teams for a postulated emergency at a field site, and the HQ Incident Command Team for an emergency affecting the Forrestal building. In addition,

44

National Mitigation Planning in Agriculture: Review and Guidelines | Open  

Open Energy Info (EERE)

Agriculture: Review and Guidelines Agriculture: Review and Guidelines Jump to: navigation, search Name National Mitigation Planning in Agriculture: Review and Guidelines Agency/Company /Organization CGIAR's Climate Change, Agriculture and Food Security (CCAFS), Food and Agriculture Organization of the United Nations, UNIQUE Agroforestry Sector Land Focus Area Agriculture Topics Background analysis, Co-benefits assessment, - Environmental and Biodiversity, - Macroeconomic, Low emission development planning, -NAMA, -Roadmap, Pathways analysis, Policies/deployment programs Program Start 2012 Program End 2013 References CGIAR - CCAFS[1] This article is a stub. You can help OpenEI by expanding it. References ↑ "CGIAR - CCAFS" Retrieved from "http://en.openei.org/w/index.php?title=National_Mitigation_Planning_in_Agriculture:_Review_and_Guidelines&oldid=581360"

45

Environmental Impacts from the Operation of Cooling Towers at SRP  

SciTech Connect

An assessment has been made of the environmental effects that would occur from the operation of cooling towers at the SRP reactors. A more realistic numerical model of the cooling tower plume has been used to reassess the environmental impacts. The following effects were considered: (1) the occurrence of fog and ice and their impact on nearby structures, (2) drift and salt deposition from the plume, (3) the length and height of the visible plume, and (4) the possible dose from tritium.

Smith, F.G. III

2001-06-26T23:59:59.000Z

46

ENVIRONMENTAL STANDARD REVIEW PLAN OFFICE OF NUCLEAR REACTOR REGULATION  

E-Print Network (OSTI)

This environmental standard review plan (ESRP) directs the staffs identification and evaluation of impacts to terrestrial ecosystems induced by the operation of heat dissipation systems, especially cooling towers and cooling ponds. The scope of the review directed by this plan will be limited to consideration of the operational aspects of heat dissipation systems in sufficient detail to form a basis for assessing potential operational impacts. Review Interfaces The reviewer for this ESRP should obtain input from or provide input to reviewers for the following ESRPs, as indicated: ` ESRP 2.4.1. Obtain descriptive material on the terrestrial ecology of the site and vicinity to support the analyses made in ESRP 5.3.3.2. ` ESRP 3.4.2. Obtain specific information about the cooling system necessary to assess impacts to the terrestrial environment. ` ESRP 5.3.3.1. Obtain information about heat dissipation to the atmosphere necessary to determine impacts to the terrestrial environment.

unknown authors

1999-01-01T23:59:59.000Z

47

Review of the Headquarters Facilities Emergency Response Plans  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

March 2002 March 2002 Review of the Headquarters Facilities Emergency Response Plans OVERSIGHT Table of Contents 1.0 INTRODUCTION ...................................................................... 1 2.0 OVERVIEW OF RESULTS ........................................................ 3 3.0 DISCUSSION OF RESULTS ...................................................... 5 3.1 Emergency Response Programs, Plans, and Procedures ....... 5 3.2 Emergency Management Requirements, Roles, and Responsibilities ............................................................... 8 3.3 Emergency Facilities and Equipment ................................... 10 4.0 CONCLUSIONS ......................................................................... 12 5.0 OPPORTUNITIES FOR IMPROVEMENTS .............................

48

C-Division annual review and operating plan, August 1990  

SciTech Connect

The Computing and Communications Division is responsible for the Laboratory's Integrated Computing Network as well as Laboratory-wide communications. Our computing network, used by 8000 people distributed throughout the nation, constitutes one of the most powerful scientific computing facilities in the world. The purpose of this publication is to inform our clients of our strategic and operating plans. We review major accomplishments since early 1989 and describe our strategic planning goals and specific projects that will guide our operations over the next couple of years. Our mission statement, planning considerations, and management policies and practices are also included.

Morse, N.R.

1990-11-01T23:59:59.000Z

49

Review and summary of Solar Thermal Conversion Program planning assistance  

DOE Green Energy (OSTI)

The Solar Thermal Conversion Program comprises a major part of the national solar energy program which must be continuously reviewed and modified where necessary. Modifications are typically required to reflect technical achievements and uncertainties which arise from within the program or from other technical programs, changes in budgets available for supporting the program as well as internal program funding priorities, changing goals such as through acceleration or stretch-out of the program schedule, significant organizational changes involving responsible governmental agencies, the introduction of new project management support contractors, and required budget or schedule changes occurring within individual projects that make up the Solar Thermal Conversion Program. The Aerospace Corporation has provided data to assist in planning, review, coordination, and documentation of the overall Solar Thermal Conversion Program. The Solar Thermal Conversion Program Plan is described in detail. Sections 2.0 through 5.0 cover the discussion and detail planning covering the objectives, justification, basic and alternative plans, budgets, and schedules for the Solar Thermal sub-unit portion of the Solar Electric Applications effort. Appendices B1, B2, and B3 include the March 21, March 28, and April 5, 1975, Program Plan submissions of the complete Solar Electric Applications effort. In Appendix B the Solar Thermal, Solar Photovoltaic, Wind Energy, and Ocean Thermal sub-unit texts have been condensed and formatted for integration in the overall ERDA budget package. (WHK)

Not Available

1975-06-01T23:59:59.000Z

50

Planning and Conduct of Operational Readiness Reviews (ORR)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

DOE-STD-3006-2000 DOE-STD-3006-2000 June 2000 Superseding DOE-STD-3006-95 November 1995 DOE STANDARD PLANNING AND CONDUCT OF OPERATIONAL READINESS REVIEWS (ORR) U.S. Department of Energy AREA OPER Washington, D.C. 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. NOT MEASUREMENT SENSITIVE This document has been reproduced directly from the best available copy. Available to DOE and DOE contractors from ES&H Technical Information Services, U.S. Department of Energy, (800) 473-4375, fax: (301) 903-9823 Available to the public from the U.S. Department of Commerce, Technology Administration, National Technical Information Service, Springfield, VA 22161; (703) 605-6000. DOE-STD-3006-2000 iii PLANNING AND CONDUCT OF OPERATIONAL READINESS REVIEWS (ORR)

51

Operational Readiness Team: OPERATIONAL READINESS REVIEW PLAN FOR THE  

NLE Websites -- All DOE Office Websites (Extended Search)

oak ridge oak ridge 12 ...... Prepared by the Operational Readiness Team: OPERATIONAL READINESS REVIEW PLAN FOR THE RAD1 0 1 SOT0 PE THERMOELECTRIC GENERATOR MATERIALS PRODUCTION TASKS R. H. Cooper M. M. Martin C. R. Riggs R. L. Beatty E. K. Ohriner R. N. Escher OISTRIBUTIQM OF THIS DOCUMENT IS UNLIMITED DISCLAIMER This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency Thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately

52

Climate Action Planning: A Review of Best Practices, Key Elements, and  

Open Energy Info (EERE)

Planning: A Review of Best Practices, Key Elements, and Planning: A Review of Best Practices, Key Elements, and Common Climate Strategies for Signatories to the American College & University Presidents' Climate Commitment Jump to: navigation, search Name Climate Action Planning: A Review of Best Practices, Key Elements, and Common Climate Strategies for Signatories to the American College & University Presidents' Climate Commitment Agency/Company /Organization Eastern Research Group Inc. Partner U.S. Environmental Protection Agency Sector Energy Focus Area Greenhouse Gas Phase Bring the Right People Together, Determine Baseline, Evaluate Options, Develop Goals, Prepare a Plan, Get Feedback, Create Early Successes Resource Type Lessons learned/best practices Availability Publicly available; free

53

Implementation plan for WRAP Module 1 operational readiness review  

Science Conference Proceedings (OSTI)

The Waste Receiving and Processing Module 1 (WRAP 1) will be used to receive, sample, treat, and ship contact-handled (CH) transuranic (TRU), low-level waste (LLW), and low-level mixed waste (LLMW) to storage and disposal sites both on the Hanford site and off-site. The primary mission of WRAP 1 is to characterize and certify CH waste in 55-gallon and 85-gallon drums; and its secondary function is to certify CH waste standard waste boxes (SWB) and boxes of similar size for disposal. The WRAP 1 will provide the capability for examination (including x-ray, visual, and contents sampling), limited treatment, repackaging, and certification of CH suspect-TRU waste in 55-gallon drums retrieved from storage, as well as newly generated CH LLW and CH TRU waste drums. The WRAP 1 will also provide examination (X-ray and visual only) and certification of CH LLW and CH TRU waste in small boxes. The decision to perform an Operational Readiness Review (ORR) was made in accordance with WHC-CM-5-34, Solid Waste Disposal Operations Administration, Section 1.4, Operational Readiness Activities. The ORR will ensure plant and equipment readiness, management and personnel readiness, and management programs readiness for the initial startup of the facility. This implementation plan is provided for defining the conduct of the WHC ORR.

Irons, L.G.

1994-11-04T23:59:59.000Z

54

SRP - EarthWise Solar Energy Incentive Program | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

SRP - EarthWise Solar Energy Incentive Program SRP - EarthWise Solar Energy Incentive Program SRP - EarthWise Solar Energy Incentive Program < Back Eligibility Commercial Residential Fed. Government Local Government Nonprofit Schools State Government Savings Category Solar Buying & Making Electricity Heating & Cooling Swimming Pool Heaters Water Heating Maximum Rebate Standard (non OG-300 rated) and solar pool heating commercial solar water heaters: $75,000 per customer per fiscal year, not to exceed 60% of project costs. Residential PV: $500 Small Commercial PV: $30,000 Program Info State Arizona Program Type Utility Rebate Program Rebate Amount ''Incentive Levels as of May 1, 2013:'' Residential PV: $0.10/W Nonprofit, School, and Government PV: $0.04/kWh Small Commercial PV: $0.10/W Residential solar water heaters: $0.35/kWh for 1st year estimated energy

55

Reviewing Measurement and Verification Plans for Federal ESPC...  

NLE Websites -- All DOE Office Websites (Extended Search)

Review Template. O&M cost savings are generally determined and verified separately from energy and water savings. * Principal review efforts should be focused on the measures...

56

Site Visit Report - Independent Oversight Review of Work Planning...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

and surveys. * Brief each stop work to the site manager. * Communicate incidentevent issues through plan of the day and flow down to front line supervision. * Present to...

57

Annual Review of Demand-Side Planning Research: 1985 Proceedings  

Science Conference Proceedings (OSTI)

EPRI's demand-side planning research spans a wide range of utility activities: planning and evaluating demand-side management programs, investigating end-use forecasting techniques, and analyzing the effect of innovative rates. Reflecting efforts to develop utility applications of EPRI research products in 1985, this report focuses on computer models such as REEPS, COMMEND, HELM, and INDEPTH.

None

1987-01-01T23:59:59.000Z

58

Review of SAR for Packaging Report  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

March 2010 March 2010 Standard Review Plan (SRP) E n v i r o n m e n t a l M a n a g e m e n t DOE - EM - SRP - 2010 2nd Edition Review of SAR for Packaging Report UCID-21218 Rev. 3 Packaging Review Guide for Reviewing Safety Analysis Reports for Packagings Revision 3 A. A. DiSabatino D. Biswas M. DeMicco L. E. Fischer R. S. Hafner L. B. Hagler J. J. Haslam G. C. Mok C. S. Patel E. W. Russell S. Sitaraman C. K. Syn J. Wen M. H. West LAWRENCE N A T I O N A L LABORATORY LIVERMORE February 2008 DISCLAIMER This document was prepared as an account of work sponsored by an agency of the United States government. Neither the United States government nor Lawrence Livermore National Security, LLC, nor any of their employees makes any warranty, expressed or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information,

59

Proceedings: 1987 Annual Review of Demand-Side Planning Research  

Science Conference Proceedings (OSTI)

Recent EPRI research in demand-side planning (DSP) has focused on forecasting, end-use technology assessment, demand-side management (DSM), and innovative pricing. These 23 papers discuss vital DSP research, including customer response to interruptible rates, personal computer forecasting tools, integrated value-based planning, customer preference and behavior studies, and a database of end-use load shapes and DSM impacts.

None

1988-08-01T23:59:59.000Z

60

A review of path planning and mapping technologies for autonomous mobile robot systems  

Science Conference Proceedings (OSTI)

This paper presents a review of various technologies for autonomous movement of a robot. Path planning is the process of generating a collision free path to the goal. Simultaneous Localization And Mapping (SLAM) is the process of creating a map of the ... Keywords: SLAM, anytime search algorithm, hippocampus, hybrid map, incremental search algorithm, localization, mapping, path planning, topological map

Nitin Kumar Dhiman; Dipti Deodhare; Deepak Khemani

2012-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


61

Site Visit Report - Independent Oversight Review of Work Planning...  

NLE Websites -- All DOE Office Websites (Extended Search)

Safety and Security (HSS) in support of the Department of Energy Office of Environmental Management (EM). The purpose of the review was to support EM management efforts to...

62

REVIEW PLAN John Redmond Dam Reservoir, Coffee County, Kansas  

E-Print Network (OSTI)

............................................................................................................1 2. REVIEW MANAGEMENT ORGANIZATION (RMO) COORDINATION Report with Responses to HQ Comments and support for John Redmond Dam and Reservoir, Kansas. (6) CEWSL Statement (HQ Policy Compliance Review). (8) SWT-PE-P Memorandum 29 June 2009; Response to HQ Policy

US Army Corps of Engineers

63

SRP_Senior_Management_Handbook_1_29_13v2  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Review Plan Review Plan Senior Management Handbook Capital and Major Construction Projects Critical Decision Review and Approval January 2013 Performance Status & Verification Our experiences with major nuclear design and construction projects continue to highlight the importance of a focused, technically rigorous, and standardized approach to project reviews performed at Critical Decision (CD) approval points. This approach is fundamental to a positive safety culture and effective nuclear safety management. Capital and Major Construction Projects Critical Decision Review and Approval Overview Thomas P. D'Agostino Under Secretary for Nuclear Security DOE O 413.3B, Program and Project Management for the Acquisition of Capital Assets, and DOE-STD-1189-2008, Integration of Safety into the Design Process, provide core

64

Geothermal-subsidence research program plan and review  

DOE Green Energy (OSTI)

The revised Geothermal Subsidence Research Plan (GSRP) presented here is the result of two years of research based on the recommendations of a technical advisory committee and on the DOE/DGE's wish to include specific components applicable to the geopressure resources on the Gulf Coast. This revised plan describes events leading up to FY 1979 and 1980 and the resulting research activities completed for that period. At the time of this writing most of the projects are completed; this document summarizes the accomplishments of the GSRP during FY 1979 and 1980 and includes recommendations for the FY 1981 and 1982 programs.

Goldstein, N.E.; Noble, J.E.; Simkin, T.L.

1980-09-01T23:59:59.000Z

65

Critical success factors in enterprise resource planning systems: Review of the last decade  

Science Conference Proceedings (OSTI)

Organizations perceive ERP as a vital tool for organizational competition as it integrates dispersed organizational systems and enables flawless transactions and production. This review examines studies investigating Critical Success Factors (CSFs) in ... Keywords: CSFs, Critical success factors, ERP, enterprise resource planning, information systems, literature review

Levi Shaul, Doron Tauber

2013-08-01T23:59:59.000Z

66

PUBLIC RELEASE OF THE YUCCA MOUNTAIN REVIEW PLAN,  

E-Print Network (OSTI)

Revision 2, to the Commission for approval to publicly release for comment. The staff received approval, subject to the incorporation of changes, In a Staff Requirements Memorandum (SRM) dated February 25, 2002. In response to the SRM, the staff modified the plan and a request for comments on the plan was announced in a Federal Register notice on March 29, 2002. In addition to the 5-month public comment period which ended August 12, 2002, staff conducted three public meetings in Nevada to solicit comments. Approximately 1000 comments were received, including comments from the Advisory Committee on Nuclear Waste (ACNW), that were binned into eleven categories. In response to comments from the public and the ACNW, staff has prepared the YMRP, Revision 2, NUREG-1 804 (Attachment 1). This version Is being submitted to the Commission for approval. Attachment 2 provides staff's responses to public comments, and Attachment 3 provides staff's specific responses to the ACNW comments. Attachment 4 provides a summary of changes made to the YMRP. Attachment 5 highlights the YMRP modifications, using redline/strikeout, to draft Revision 2 of the YMRP. Following Commission approval the staff plans to follow the Agency's process of:

William D. Travers

2003-01-01T23:59:59.000Z

67

Review of the proposed Strategic National Plan for Civilian Nuclear Reactor Development: Volume 1  

SciTech Connect

On August 9, 1985, the Secretary of Energy requested that the Chairman of the Energy Research Advisory Board establish an ad-hoc Panel to review a draft ''Strategic National Plan for Civilian Nuclear Reactor Development.'' The resulting report, approved by the Board, contains suggestions for improving the draft plan and also contains major recommendations for alleviating the several institutional barriers that appear to preclude the construction of any new nuclear power plants in this country.

1986-10-01T23:59:59.000Z

68

Letter from Elizabeth Chimento and Poul Hertel, Sullivan Environmental Consultants Review of Mirant Unit 1 Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Sent: Monday, December 19, 2005 11:56 AM To: Mansueti, Lawrence Subject: Sullivan Environmental Consultants Review of Mirant Unit 1 Plan Mr. Mansueti, Would you please enter the attached review of the Mirant Unit One Plan in your records for DOE Docket #EO-05-01? Sullivan Environmental Consultants completed this review which Poul Hertel and I commissioned re: ENSR Corp. "Update 1 to: A Dispersion Modeling Analysis of Downwash from Mirant's Potomac River Plant; Modeling Unit 1 Emissions in a Cycling Mode" (9/20/05). As of this date, we have received no response to the questions in the Sullivan analysis. We ask the Department of Energy to consider the issues raised in the Sullivan Review in deciding the plant's future operation.

69

Review of the Waste Isolation Pilot Plant Work Planning and Control Activities, April 2013  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Independent Oversight Review of the Independent Oversight Review of the Waste Isolation Pilot Plant Work Planning and Control Activities April 2013 Office of Safety and Emergency Management Evaluations Office of Enforcement and Oversight Office of Health, Safety and Security U.S. Department of Energy Table of Contents 1.0 Purpose ................................................................................................................................................. 1 2.0 Scope.................................................................................................................................................... 1 3.0 Background........................................................................................................................................... 1 4.0 Methodology......................................................................................................................................... 2

70

DOE Retrospective Review Plan and Burden Reduction Report  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

February 15, 2013 February 15, 2013 Agency/ Sub- agency RIN/ OMB Control Number Title of Initiative/ Rule/lCR Brief Description Actual or Target Completion Date Anticipated savings in costs and/or information collection burdens, together with any anticipated changes in benefits Progress updates and anticipated accomplish- ments Notes DOE/GC N/A Request for information on reducing regulatory burden DOE is continually engaging in review of its rules to determine whether there are burdens on the public that can be avoided by amending or rescinding existing requirements. To that end, while DOE is always open to receiving information about the impact of its regulations, it published this RFI to solicit public input. August 8, 2012 (77 FR 47328) This information solicitation is expected

71

Operational readiness review implementation plan for K Basin sludge water system  

SciTech Connect

This Implementation Plan (IP) has been prepared consistent with the requirements of U.S. Department of Energy (DOE) Order 425.1B, ''Startup and Restart of Nuclear Facilities'', and DOE-STD-3006-2000, ''Planning and Conduct of Operational Readiness Reviews'' (ORR) (DOE 2002). The scope of the DOE ORR is described in the RL ''Plan of Action, K Basin Sludge Water System'' (Veitenheimer 2003), prepared by DOE project line management and approved by the RL Manager, the designated Approval Authority, on March 20, 2003. The scope of the contractor ORR is described in the contractor ''Plan of Action for the K Basins Sludge Water System Operational Readiness Review'' (FH 2002a) which was prepared by Spent Nuclear Fuel (SNF) Project line management and approved by the DOE Richland Operations Office (RL) Manager on December 19, 2002. DOE Order 425.1B indicates that the Secretarial Officer is the Authorization Authority when substantial modifications are made to a Hazard Category 2 nuclear facility. This Authorization Authority has been delegated to the RL Manager by memorandum from Jessie Hill Roberson, dated February 5, 2003 (Roberson 2003). This IP provides the overall approach and guidelines for performance of the DOE ORR. Appendix A contains the Criteria and Review Approach Documents (CRAD), which define the review objectives and criteria as well as the approach for assessing each objective. ORR results will be published in a final report, as discussed in Section 9.4.

IRWIN, R.M.

2003-05-01T23:59:59.000Z

72

Book Review Conserving biodiversity in agricultural landscapes: Model-based planning tools  

E-Print Network (OSTI)

Book Review Conserving biodiversity in agricultural landscapes: Model-based planning tools Robert K of conservation within agricultural landscapes. The book's authors and case studies are predominantly from developed United States and European countries, and as such, the book's application in some ways is lim

Moore, Jeffrey E.

73

Technical Review of Retrieval and Closure Plans for the INEEL INTEC Tank Farm Facility  

SciTech Connect

The purpose of this report is to document the conclusions of a technical review of retrieval and closure plans for the Idaho National Energy and Environmental Laboratory (INEEL) Idaho Nuclear Technology and Engineering Center (INTEC) Tank Farm Facility. In addition to reviewing retrieval and closure plans for these tanks, the review process served as an information exchange mechanism so that staff in the INEEL High Level Waste (HLW) Program could become more familiar with retrieval and closure approaches that have been completed or are planned for underground storage tanks at the Oak Ridge National Laboratory (ORNL) and Hanford sites. This review focused not only on evaluation of the technical feasibility and appropriateness of the approach selected by INEEL but also on technology gaps that could be addressed through utilization of technologies or performance data available at other DOE sites and in the private sector. The reviewers, Judith Bamberger of Pacific Northwest National Laboratory (PNNL) and Dr. Barry Burks of The Providence Group Applied Technology, have extensive experience in the development and application of tank waste retrieval technologies for nuclear waste remediation.

Bamberger, Judith A; Burks, Barry L; Quigley, Keith D; Falter, Diedre D

2001-09-28T23:59:59.000Z

74

DOE-STD-3006-95; DOE Standard Planning and Conduct of Operational Readiness Reviews (ORR)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

3006-95 3006-95 November 1995 SUPERSEDING DOE-STD-3006-93 November 1993 DOE STANDARD PLANNING AND CONDUCT OF OPERATIONAL READINESS REVIEWS (ORR) U.S. Department of Energy AREA MISC Washington, D.C. 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. This document has been reproduced directly from the best available copy. Available to DOE and DOE contractors from the Office of Scientific and Technical Information, P.O. Box 62, Oak Ridge, TN 37831; (615) 576-8401. Available to the public from the U.S. Department of Commerce, Technology Administration, National Technical Information Service, Springfield, VA 22161; (703) 487-4650. DOE-STD-3006-95 i PLANNING AND CONDUCT OF OPERATIONAL READINESS REVIEWS (ORR) FOREWORD 1. DOE 0 425.1 establishes the requirement to conduct Operational Readiness Reviews

75

Operational Readiness Review Implementation Plan for the K Basin Fuel Transfer System  

Science Conference Proceedings (OSTI)

This implementation plan has been prepared to comply with the requirements of U.S. Department of Energy (DOE) Order 425.1A, Startup and Restart of Nuclear Facilities, and DOE-STD-3006-2000, Planning and Conduct of Operational Readiness Reviews (ORR) (DOE 2002). The scope of the ORR is described in the contractor K Basin Fuel Transfer System (FTS) Plan of Action (POA), which was prepared by Spent Nuclear Fuel (SNF) Project line management and approved by the DOE Richland Operations Office (RL) Manager on April 4, 2002 (FH 2002a). While the Project Hanford Management Contractor has been revised to include DOE Order 425.1B, the contractor implementing procedure, ''F-PRO-055, Startup Readiness (Revision 9) has not yet been approved by RL for contractor use. Appendix A provides a crosswalk between the requirements of DOE Order 425.1A and DOE Order 425.1B to show that all requirements of DOE 425.1B are covered by this implementation plan. DOE Order 425.1B indicates that the Secretarial Officer is the Authorization Authority when substantial modifications are made to a Hazard Category 2 nuclear facility. This Authorization Authority has been delegated to the RL Manager by memorandum from Jessie Hill Roberson, dated November 20, 2001 (Roberson 2001). The scope of the ORR is described in the RL Plan of Action, K Basin Fuel Transfer System, prepared by DOE project line management and approved by the RL Manager, the designated approval authority, on September 12, 2002 (Schlender 2002). This implementation plan provides the overall approach and guidelines for performance of the DOE ORR. Appendix B contains the Criteria and Review Approach Documents (CRAD), which define the review objectives and criteria as well as the approach for assessing each objective. ORR results will be published in a final report, as discussed in Section 9.4.

DAVIES, T.H.

2002-09-23T23:59:59.000Z

76

Memo Issuance of EM Capital and Major Operating Project Standard Review Plan Edition Two  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

MAR 2 4 201011 MAR 2 4 201011 MEMORANDUM FOR DISTRIBUTION FROM: DR. STEVEN L. KRAHN DEPUTY ASSISTANT SAFETY AND SECU EIVVIROIVMENTAL MANAGEMENT SUBJECT: Issuance of Environmental Management Capital and Major Operating Project Standard Review Plan Edition Two The Office of Environmental Management (EM) is responsible for managing the design, construction, operation, and eventual disposition of mission critical projects/facilities. Effective management of these projects requires multiple disciplines to be integrated and engaged at various project lifecycle phases. These disciplines include project management, engineering, design, safety, environment, safeguards and security, and quality assurance. The lessons-learned to date from ongoing Headquarters (HQ) and Field project reviews [e.g., Construction Project

77

Comparative Review of a Dozen National Energy Plans: Focus on Renewable and Efficient Energy  

NLE Websites -- All DOE Office Websites (Extended Search)

046 046 March 2009 A Comparative Review of a Dozen National Energy Plans: Focus on Renewable and Efficient Energy Jeffrey Logan and Ted L. James National Renewable Energy Laboratory 1617 Cole Boulevard, Golden, Colorado 80401-3393 303-275-3000 * www.nrel.gov NREL is a national laboratory of the U.S. Department of Energy Office of Energy Efficiency and Renewable Energy Operated by the Alliance for Sustainable Energy, LLC Contract No. DE-AC36-08-GO28308 Technical Report NREL/TP-6A2-45046 March 2009 A Comparative Review of a Dozen National Energy Plans: Focus on Renewable and Efficient Energy Jeffrey Logan and Ted L. James Prepared under Task No. SAO7.9C50 NOTICE This report was prepared as an account of work sponsored by an agency of the United States government.

78

River Protection Project Integrated safety management system phase II verification review plan - 7/29/99  

Science Conference Proceedings (OSTI)

The purpose of this review is to verify the implementation status of the Integrated Safety Management System (ISMS) for the River Protection Project (RPP) facilities managed by Fluor Daniel Hanford, Inc. (FDH) and operated by Lockheed Martin Hanford Company (LMHC). This review will also ascertain whether within RPP facilities and operations the work planning and execution processes are in place and functioning to effectively protect the health and safety of the workers, public, environment, and federal property over the RPP life cycle. The RPP ISMS should support the Hanford Strategic Plan (DOERL-96-92) to safely clean up and manage the site's legacy waste and deploy science and technology while incorporating the ISMS central theme to ''Do work safely'' and protect human health and the environment.

SHOOP, D.S.

1999-09-10T23:59:59.000Z

79

Summary of the planning, management, and evaluation process for the Geothermal Program Review VI conference  

DOE Green Energy (OSTI)

The purpose of this document is to present an overview of the planning, facilitation, and evaluation process used to conduct the Geothermal Program Review VI (PR VI) conference. This document was also prepared to highlight lessons learned from PR VI and, by utilizing the evaluation summaries and recommendations, be used as a planning tool for PR VII. The conference, entitled Beyond Goals and Objectives,'' was sponsored by the US Department of Energy's (DOE) Geothermal Technology Division (GTD), PR VI was held in San Francisco, California on April 19--21, 1988 and was attended by 127 participants. PR VI was held in conjunction with the National Geothermal Association's (NGA) Industry Round Table. This document presents a brief summary of the activities, responsibilities, and resources for implementing the PR VI meeting and provides recommendations, checklists, and a proposed schedule for assisting in planning PR VII.

Not Available

1988-10-01T23:59:59.000Z

80

Scrotal Irradiation in Primary Testicular Lymphoma: Review of the Literature and In Silico Planning Comparative Study  

SciTech Connect

We examined adjuvant irradiation of the scrotum in primary testicular lymphoma (PTL) by means of a literature review in MEDLINE, a telephone survey among Dutch institutes, and an in silico planning comparative study on scrotal irradiation in PTL. We did not find any uniform adjuvant irradiation technique assuring a safe planning target volume (PTV) coverage in published reports, and the definition of the clinical target volume is unclear. Histopathologic studies of PTL show a high invasion rate of the tunica albuginea, the epididymis, and the spermatic cord. In retrospective studies, a prescribed dose of at least 30 Gy involving the scrotum is associated with best survival. The majority of Dutch institutes irradiate the whole scrotum without using a planning computed tomography scan, with a single electron beam and a total dose of 30 Gy. The in silico planning comparative study showed that all evaluated approaches met a D{sub 95%} scrotal dose of at least 85% of the prescription dose, without exceeding the dose limits of critical organs. Photon irradiation with 2 oblique beams using wedges resulted in the best PTV coverage, with a mean value of 95% of the prescribed dose, with lowest maximum dose. Adjuvant photon or electron irradiation of the whole scrotum including the contralateral testicle with a minimum dose of 30 Gy is recommended in PTL. Computed tomography-based radiation therapy treatment planning with proper patient positioning and position verification guarantees optimal dose coverage.

Brouwer, Charlotte L., E-mail: c.l.brouwer@umcg.nl [Department of Radiation Oncology, University of Groningen, University Medical Center Groningen, Groningen (Netherlands); Wiesendanger, Esther M.; Hulst, Peter C. van der [Department of Radiation Oncology, University of Groningen, University Medical Center Groningen, Groningen (Netherlands)] [Department of Radiation Oncology, University of Groningen, University Medical Center Groningen, Groningen (Netherlands); Imhoff, Gustaaf W. van [Department of Hematology, University of Groningen, University Medical Center Groningen, Groningen (Netherlands)] [Department of Hematology, University of Groningen, University Medical Center Groningen, Groningen (Netherlands); Langendijk, Johannes A.; Beijert, Max [Department of Radiation Oncology, University of Groningen, University Medical Center Groningen, Groningen (Netherlands)] [Department of Radiation Oncology, University of Groningen, University Medical Center Groningen, Groningen (Netherlands)

2013-02-01T23:59:59.000Z

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


81

Review of performance-based ratemaking plans for US gas distribution companies  

SciTech Connect

Performance-Based Ratemaking (PBR) is receiving increasing attention by energy utilities and their regulators. PBR is the industry term for forms of regulation that increase financial incentive for performance relative to traditional cost-of-service/rate-of-return (COS/ROR) regulation. In this report, PBR plans filed by US gas local distribution companies (LDCs) are described and reviewed. The rationale behind energy utility PBR is presented and discussed. Using nine plans that have been proposed by eight LDCs as a basis, a framework (typology) to facilitate understanding of gas utility PBR is presented. Plans are categorized according to the range of services covered by the PBR mechanism and the scope of the mechanism`s cost coverage within a service category. Pivotal design issues are identified and, based on the sample of plans, observations are made. Design issues covered include the length of time that the PBR is in effect (term); the relationship between PBR plans and status quo ratemaking; methods for formulating cost or rate indices, earnings sharing mechanisms, and service quality indices; and compatibility with gas utility DSM programs. The report summarizes observations that may be considered supportive of the rationale behind PBR. PBR is, however, not clearly superior to traditional regulation and few PBRs that are broad in scope have been adopted long enough to allow for a empirical analysis. Thus, the report concludes by identifying and describing commonly-cited pitfalls of PBR.

Comnes, G.A. [Lawrence Berkeley Lab., CA (United States). Energy and Environment Div.

1994-11-01T23:59:59.000Z

82

Decommissioning Standard Review Plans and Risk-Informing Decommissioning Regulation: Selected 1999 Industry/NRC Decommissioning Lice nsing Interactions  

Science Conference Proceedings (OSTI)

This report describes the technical support EPRI provided the Nuclear Energy Institute (NEI) Decommissioning Working Group in 1999. This volume includes two initiatives that produced four draft Decommissioning Standard Review Plans (DSRPs). It also includes an evaluation entitled Spent Fuel Pool Seismic Failure Frequency in Support of Risk-Informed Decommissioning -- Emergency Planning.

1999-10-31T23:59:59.000Z

83

Web-Based Training on Reviewing Dose Modeling Aspects of NRC Decommissioning and License Termination Plans  

SciTech Connect

NRC licensees at decommissioning nuclear facilities submit License Termination Plans (LTP) or Decommissioning Plans (DP) to NRC for review and approval. To facilitate a uniform and consistent review of these plans, the NRC developed training for its staff. A live classroom course was first developed in 2005, which targeted specific aspects of the LTP and DP review process related to dose-based compliance demonstrations or modeling. A web-based training (WBT) course was developed in 2006 and 2007 to replace the classroom-based course. The advantage of the WBT is that it will allow for staff training or refreshers at any time, while the advantage of a classroom-based course is that it provides a forum for lively discussion and the sharing of experience of classroom participants. The objective of this course is to train NRC headquarters and regional office staff on how to review sections of a licensee's DP or LTP that pertain to dose modeling. The DP generally refers to the decommissioning of non-reactor facilities, while the LTP refers specifically to the decommissioning of reactors. This review is part of the NRC's licensing process, in which the NRC determines if a licensee has provided a suitable technical basis to support derived concentration guideline levels (DCGLs)1 or dose modeling analyses performed to demonstrate compliance with dose-based license termination rule criteria. This type of training is one component of an organizational management system. These systems 'use a range of practices to identify, create, represent, and distribute knowledge for reuse, awareness and learning'. This is especially important in an organization undergoing rapid change or staff turnover to retain organizational information and processes. NRC is committed to maintaining a dynamic program of training, development, and knowledge transfer to ensure that the NRC acquires and maintains the competencies needed to accomplish its mission. This paper discusses one specific project related to training, developing, and transferring knowledge to NRC staff on how to review dose-modeling portions of licensee-submitted DPs and LTPs. This project identified specific cases and examples, created easily updateable educational modules, represented material in an engaging format through animations, video, and graphics, and distributed information on how to perform these reviews in an accessible, web-based format. WBT promotes consistency in reviews and has the advantage of being able to be used as a resource to staff at any time. The WBT will provide reviewers with knowledge needed to perform risk-informed analyses (e.g., information related to development of realistic scenarios and use of probabilistic analysis). WBT on review of LTP or DP dose modeling will promote staff development, efficiency, and effectiveness in performing risk-informed, performance-based reviews of decommissioning activities at NRC-licensed facilities. One of the key advantages of this type of web-based training is that it can be loaded on-demand and can be reused indefinitely. In addition to the benefits of on-demand training, the modules can also be used for reference. The presentations are hosted on a web server that can be accessed by registered users at any time. Staff can return to a particular module to review the material long after they have completed the course.

LePoire, D.; Cheng, J.J.; Kamboj, S.; Arnish, J.; Richmond, P.; Chen, S.Y. [Argonne National Laboratory, 9700 S. Cass Ave., Argonne, IL 60439 (United States); Barr, C.; McKenney, C. [U.S. Nuclear Regulatory Commission, 11555 Rockville Pike, Rockville, MD 20852 (United States)

2008-01-15T23:59:59.000Z

84

Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Methane Hydrate Multi-Year R&D Program Plan NATIONAL METHANE HYDRATE MULTI-YEAR R&D PROGRAM PLAN U.S. Department of Energy Office of Fossil Energy Federal Energy Technology Center...

85

Solar incentives planning and development: a state-of-the-art review and research agenda  

SciTech Connect

A research agenda designed to assist the Department of Energy in the planning and development of solar energy incentives was developed. A four-element framework for assessing solar incentive policies is presented. In the context of this framework, the available solar research relevant to incentives for solar energy is reviewed. Comparing the requirements identified in the framework and the contents of completed research, major gaps in the literature on solar incentives are identified. An agenda for research is then proposed to eliminate these gaps and to provide information for constructing effective solar energy incentives.

Schiffel, D.; Posner, D.; Hillhouse, K.; Doane, J.; Weis, P.

1978-08-01T23:59:59.000Z

86

Review of the Portsmouth Gaseous Diffusion Plant Work Planning and Control Activities Prior to Work Execution, January 2013  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Review of the Review of the Portsmouth Gaseous Diffusion Plant Work Planning and Control Activities Prior to Work Execution January 2013 Office of Safety and Emergency Management Evaluations Office of Enforcement and Oversight Office of Health, Safety and Security U.S. Department of Energy Table of Contents 1.0 Purpose ................................................................................................................................................. 1 2.0 Scope.................................................................................................................................................... 1 3.0 Background........................................................................................................................................... 1

87

Operational readiness review plan for the radioisotope thermoelectric generator materials production tasks  

DOE Green Energy (OSTI)

In October 1989, a US shuttle lifted off from Cape Kennedy carrying the spacecraft Galileo on its mission to Jupiter. In November 1990, a second spacecraft, Ulysses, will be launched from Cape Kennedy with a mission to study the polar regions of the sun. The prime source of power for both spacecraft is a series of radioisotope thermoelectric generators (RTGs), which use plutonium oxide (plutonia) as a heat source. Several of the key components in this power system are required to ensure the safety of both the public and the environment and were manufactured at Oak Ridge National Laboratory (ORNL) in the 1980 to 1983 period. For these two missions, Martin Marietta Energy Systems, Inc. (Energy Systems), will provide an iridium-alloy component used to contain the plutonia heat source and a carbon-composite material that serves as a thermal insulator. ORNL alone will continue to fabricate the carbon-composite material. Because of the importance to DOE that Energy Systems deliver these high-quality components on time, performance of an Operational Readiness Review (ORR) of these manufacturing activities is necessary. Energy Systems Policy GP-24 entitled Operational Readiness Process'' describes the formal and comprehensive process by which appropriate Energy Systems activities are to be reviewed to ensure their readiness. This Energy System policy is aimed at reducing the risks associated with mission success and requires a management-approved readiness plan'' to be issued. This document is the readiness plan for the RTG materials production tasks. 6 refs., 11 figs., 1 tab.

Cooper, R.H.; Martin, M.M.; Riggs, C.R.; Beatty, R.L.; Ohriner, E.K.; Escher, R.N.

1990-04-19T23:59:59.000Z

88

Review and evaluation of contingency plans for oil and hazardous substances in the upper Great Lakes region. Final report  

SciTech Connect

The purpose of this study was to update and supplement a contingency plan review conducted for the Corps in 1979 by the St. Lawrence-Eastern Ontario Commission for handling oil and hazardous-substance spills on the upper Great Lakes and their connecting channels. Special attention was given to cleanup and control methods described for ice conditions that may exist in the region in winter. The report identifies existing contingency plans in the study area; tabulates amounts, types, and locations of equipment and manpower that exist to implement the plans; describes methods to contain and recover oil in ice conditions; describes spill-mitigation plans and techniques to protect natural resources; describes techniques of deflecting oil in swift flowing waters; and describes disposal plans identified in the contingency plans.

Gundlach, E.R.; Murday, M.; Fanning, W.L.

1986-11-15T23:59:59.000Z

89

Review of power planning in the Pacific Northwest: calendar year 1980  

Science Conference Proceedings (OSTI)

Many of the activities that occurred in the electric power industry in the Pacific Northwest during calendar year 1980 are reviewed in this publication. These include: significant power planning related events, activities, and studies; passage of the Pacific Northwest Electric Power Planning and Conservation Act on December 5, 1980, the Act becoming P.L. 95-501; the development of alternative and renewable energy resources; home weatherization programs; processing of preliminary permits for development of small hydro; investigation of geothermal resources; and nuclear power development setbacks as voters in the states of Montana, Oregon, and Washington passed initiatives regarding storage of nuclear waste and siting of nuclear powerplants. Information is included on: utility load estimates through the year 2020; the resources existing, under construction, and feasible for development in meeting the forecast loads; a large number of small hydro projects which are in various stages of the study and/or licensing process; and a comparison of loads and resources giving the overall picture of the power situation in the Pacific Northwest. It is concluded that deficits in firm energy occur in all of the next 10 years, under critical hydro conditions. Small hydro, wind, and biomass generation, along with an aggressive mandatory energy conservation program could eliminate the deficit. However, the assured cost-effective potential realizable from these resources is unknown. Finally, the activities of the Power Planning Committee during the year are discussed, with a list of Committee publications included. A map titled Electric Power Plants in the Pacific Northwest and Adjacent Areas is included.

Not Available

1981-04-01T23:59:59.000Z

90

A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS  

E-Print Network (OSTI)

Transmission Planning and Wind Energy. Issue Brief. August.of new transmission for wind energy due to the complex andincreasingly including wind energy in transmission plans. We

Mills, Andrew; Wiser, Ryan; Porter, Kevin

2007-01-01T23:59:59.000Z

91

Review of the Portsmouth Gaseous Diffusion Plant Work Planning and Control Activities Prior to Work Execution, January 2013  

NLE Websites -- All DOE Office Websites (Extended Search)

Independent Oversight Review of the Independent Oversight Review of the Portsmouth Gaseous Diffusion Plant Work Planning and Control Activities Prior to Work Execution January 2013 Office of Safety and Emergency Management Evaluations Office of Enforcement and Oversight Office of Health, Safety and Security U.S. Department of Energy Table of Contents 1.0 Purpose ................................................................................................................................................. 1 2.0 Scope.................................................................................................................................................... 1 3.0 Background........................................................................................................................................... 1

92

The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies  

Science Conference Proceedings (OSTI)

The rapid development of wind power that the United States has experienced over the last several years has been coupled with a growing concern that wind development will require substantial additions to the nation's transmission infrastructure. Transmission is particularly important for wind power due to the locational dependence of wind resources, the relatively low capacity factor of wind plants, and the mismatch between the short lead time to build a new wind project and the longer lead time often needed to plan, permit, and construct transmission. It is clear that institutional issues related to transmission planning, siting, and cost allocation will pose major obstacles to accelerated wind power deployment, but also of concern is the potential cost of this infrastructure build out. Simply put, how much extra cost will society bear to deliver wind power to load centers? Without an answer to this question, there can be no consensus on whether or not the cost of developing transmission for wind will be a major barrier to further wind deployment, or whether the institutional barriers to transmission expansion are likely to be of more immediate concern. In this report, we review a sample of 40 detailed transmission studies that have included wind power. These studies cover a broad geographic area, and were completed from 2001-2008. Our primary goal in reviewing these studies is to develop a better understanding of the transmission costs needed to access growing quantities of wind generation. A secondary goal is to gain a better appreciation of the differences in transmission planning approaches in order to identify those methodologies that seem most able to estimate the incremental transmission costs associated with wind development. Finally, we hope that the resulting dataset and discussion might be used to inform the assumptions, methods, and results of higher-level assessment models that are sometimes used to estimate the cost of wind deployment (e.g. NEMS and WinDS). The authors and general location of the 40 detailed transmission studies included in our review are illustrated in Figure ES-1. As discussed in the body of the report, these studies vary considerably in scope, authorship, objectives, methodology, and tools. Though we recognize this diversity and are cognizant that comparisons among these studies are therefore somewhat inappropriate, we nonetheless emphasize such simple comparisons in this report. We do so in order to improve our understanding of the range of transmission costs needed to access greater quantities of wind, and to highlight some of the drivers of those costs. In so doing, we gloss over many important details and differences among the studies in our sample. In emphasizing simple comparisons, our analysis focuses primarily on the unit cost of transmission implied by each of the studies. The unit cost of transmission for wind in $/kW terms on a capacity-weighted basis is estimated by simply dividing the total transmission cost in a study by the total amount of incremental generation capacity (wind and non-wind) modeled in that study. In so doing, this metric assumes that within any individual study all incremental generation capacity imposes transmission costs in proportion to its nameplate capacity rating. The limitations to this approach are described in some detail in the body of the report.

Mills, Andrew D.; Wiser, Ryan; Porter, Kevin

2009-02-02T23:59:59.000Z

93

Review of activities and plans for solar energy in Federal buildings  

DOE Green Energy (OSTI)

The purpose of this report is to provide the Department of Energy's Solar Federal Buildings Program with data on the Federal agencies' activities and plans regarding the use of solar energy in their buildings, and consequently, to make recommendations concerning the Solar Federal Buildings Program's plans. Specifically this report encompasses an analysis of agencies Ten Year Buildings construction, leasing and retrofit plans to provide visibility for and detailed knowledge of Federal agencies planning regarding solar and other renewable energy resources. The results of the analysis conducted, pertinent statistical information regarding planned solar projects, and recommendations concerning the SFBP plans are presented.

Not Available

1980-10-01T23:59:59.000Z

94

Berkeley Lab Strategic Planning  

NLE Websites -- All DOE Office Websites (Extended Search)

and Development (LDRD) BER Review Annual Lab Plan Notable Outcomes Division-Level Strategic Planning Related Links Strategic Planning Laboratory Directed Research and...

95

The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies  

E-Print Network (OSTI)

Transmission Vision for Wind Integration. White Paper.Planning (Xcel). 2006. Wind Integration Study Report OfCharles Smith (Utility Wind Integration Group), Lynn Coles (

Mills, Andrew D.

2009-01-01T23:59:59.000Z

96

The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies  

E-Print Network (OSTI)

Certificates of Need for Transmission Lines to Support theand Preference in Transmission Service. Washington, D.C. :Integrating Wind into Transmission Planning: The Rocky

Mills, Andrew D.

2009-01-01T23:59:59.000Z

97

A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS  

E-Print Network (OSTI)

B. Kirby. 2001. Transmission Planning for a Restructuringindustry_issues/energy_infrastructure/transmission/transmission_hirst.pdf Joskow, P.L. 2005a. Transmission

Mills, Andrew; Wiser, Ryan; Porter, Kevin

2007-01-01T23:59:59.000Z

98

A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS  

E-Print Network (OSTI)

Planning.pdf NWCC. 2007a. FERC Order 890: What Does It Meanof wholesale power competition. FERC Order 2000 providesISO/RTO are being pushed by FERC to expand the transmission

Mills, Andrew; Wiser, Ryan; Porter, Kevin

2007-01-01T23:59:59.000Z

99

A CRITICAL REVIEW OF WIND TRANSMISSION COST ESTIMATES FROM MAJOR TRANSMISSION PLANNING EFFORTS  

E-Print Network (OSTI)

179c/179c9e0086c0.pdf National Wind CoordinatingTransmission Planning and Wind Energy. Issue Brief. August.and Renewable Energy, Wind & Hydropower Technologies Program

Mills, Andrew; Wiser, Ryan; Porter, Kevin

2007-01-01T23:59:59.000Z

100

Management Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Management Plan (SSMP) to be submitted to Congress after the April 2010 release of the Nuclear Posture Review Report. It is aligned with the President's National Security Strategy...

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


101

Performance-based ratemaking for electric utilities: Review of plans and analysis of economic and resource-planning issues. Volume 1  

SciTech Connect

Performance-Based Ratemaking (PBR) is a form of utility regulation that strengthens the financial incentives to lower rates, lower costs, or improve nonprice performance relative traditional regulation, which the authors call cost-of-service, rate-of-return (COS/ROR) regulation. Although the electric utility industry has considerable experience with incentive mechanisms that target specific areas of performance, implementation of mechanisms that cover a comprehensive set of utility costs or services is relatively rare. In recent years, interest in PBR has increased as a result of growing dissatisfaction with COS/ROR and as a result of economic and technological trends that are leading to more competition in certain segments of the electricity industry. In addition, incentive regulation has been used with some success in other public utility industries, most notably telecommunications in the US and telecommunications, energy, and water in the United Kingdom. In this report, the authors analyze comprehensive PBR mechanisms for electric utilities in four ways: (1) they describe different types of PBR mechanisms, (2) they review a sample of actual PBR plans, (3) they consider the interaction of PBR and utility-funded energy efficiency programs, and (4) they examine how PBR interacts with electric utility resource planning and industry restructuring. The report should be of interest to technical staff of utilities and regulatory commissions that are actively considering or designing PBR mechanisms. 16 figs., 17 tabs.

Comnes, G.A.; Stoft, S.; Greene, N. [Lawrence Berkeley Lab., CA (United States). Energy and Environment Div.; Hill, L.J. [Lawrence Berkeley Lab., CA (United States). Energy and Environment Div.]|[Oak Ridge National Lab., TN (United States). Energy Div.

1995-11-01T23:59:59.000Z

102

Uncertainty and Sensitivity Analyses Plan. Draft for Peer Review: Hanford Environmental Dose Reconstruction Project  

Science Conference Proceedings (OSTI)

Hanford Environmental Dose Reconstruction (HEDR) Project staff are developing mathematical models to be used to estimate the radiation dose that individuals may have received as a result of emissions since 1944 from the US Department of Energy`s (DOE) Hanford Site near Richland, Washington. An uncertainty and sensitivity analyses plan is essential to understand and interpret the predictions from these mathematical models. This is especially true in the case of the HEDR models where the values of many parameters are unknown. This plan gives a thorough documentation of the uncertainty and hierarchical sensitivity analysis methods recommended for use on all HEDR mathematical models. The documentation includes both technical definitions and examples. In addition, an extensive demonstration of the uncertainty and sensitivity analysis process is provided using actual results from the Hanford Environmental Dose Reconstruction Integrated Codes (HEDRIC). This demonstration shows how the approaches used in the recommended plan can be adapted for all dose predictions in the HEDR Project.

Simpson, J.C.; Ramsdell, J.V. Jr.

1993-04-01T23:59:59.000Z

103

Web-based training related to NRC staff review of dose modeling aspects of license termination and decommissioning plans.  

SciTech Connect

NRC licensees at decommissioning nuclear facilities submit License Termination Plans (LTP) or Decommissioning Plans (DP) to NRC for review and approval. To facilitate a uniform and consistent review of these plans, the NRC developed training for its staff. A live classroom course was first developed in 2005, which targeted specific aspects of the LTP and DP review process related to dose-based compliance demonstrations or modeling. A web-based training (WBT) course is being developed in 2006 to replace the classroom-based course. The advantage of the WBT is that it will allow for staff training or refreshers at any time, while the advantage of a classroom-based course is that it provides a forum for lively discussion and the sharing of experience of classroom participants. The training course consists of the core and advanced modules tailored to specific NRC job functions. Topics for individual modules include identifying the characteristics of simple and complex sites, identifying when outside expertise or consultation is needed, demonstrating how to conduct acceptance and technical reviews of dose modeling, and providing details regarding the level of justification needed for realistic scenarios for both dose modeling and derivation of DCGLs. Various methods of applying probabilistic uncertainty analysis to demonstrate compliance with dose-based requirements are presented. These approaches include: (1) modeling the pathways of radiological exposure and estimating doses to receptors from a combination of contaminated media and radionuclides, and (2) using probabilistic analysis to determine an appropriate set of input parameters to develop derived concentration guideline limits or DCGLs (DCGLs are media- and nuclide-specific concentration limits that will meet dose-based, license termination rule criteria found in 10 CFR Part 20, Subpart E). Calculation of operational (field) DCGL's from media- and nuclide-specific DCGLs and use of operational DCGLs in conducting final status surveys are addressed in the WBT. Realistic case examples are presented and analyzed including the abstraction of a realistic site into a conceptual model and computer model. A case history is also used to demonstrate development of NRC review documents such as requests for additional information (RAIs). To enhance the web-based training experience, audio, animations, linked documents, quizzes, and scripts are being integrated with a commercial web-based training package that supports simple navigation. The course is also being integrated into both existing and state-of-the-art learning management systems. A testing group is being utilized to identify and help resolve training issues prior to deployment of the course. When completed, the course can be accessed for credited training with required modules dependent on the job category of the training participant. The modules will also be accessible to NRC staff for review or refresher following initial course completion. WBT promotes consistency in reviews and has the advantage of being able to be used as a resource to staff at any time. The WBT provides reviewers with knowledge needed to perform risk-informed analyses (e.g., information related to development of realistic scenarios and use of probabilistic analysis). WBT on review of LTP or DP dose modeling promotes staff development, efficiency, and effectiveness in performing risk-informed, performance-based reviews of decommissioning activities at NRC-licensed facilities.

LePoire, D.; Arnish, J.; Cheng, J. J.; Kamboj, S.; Richmond, P.; Chen, S. Y.; Barr, C.; McKenney, C.; Environmental Science Division; NRC

2007-01-01T23:59:59.000Z

104

Web-based training related to NRC staff review of dose modeling aspects of license termination and decommissioning plans  

SciTech Connect

NRC licensees at decommissioning nuclear facilities submit License Termination Plans (LTP) or Decommissioning Plans (DP) to NRC for review and approval. To facilitate a uniform and consistent review of these plans, the NRC developed training for its staff. A live classroom course was first developed in 2005, which targeted specific aspects of the LTP and DP review process related to dose-based compliance demonstrations or modeling. A web-based training (WBT) course is being developed in 2006 to replace the classroom-based course. The advantage of the WBT is that it will allow for staff training or refreshers at any time, while the advantage of a classroom-based course is that it provides a forum for lively discussion and the sharing of experience of classroom participants. The training course consists of the core and advanced modules tailored to specific NRC job functions. Topics for individual modules include identifying the characteristics of simple and complex sites, identifying when outside expertise or consultation is needed, demonstrating how to conduct acceptance and technical reviews of dose modeling, and providing details regarding the level of justification needed for realistic scenarios for both dose modeling and derivation of DCGLs. Various methods of applying probabilistic uncertainty analysis to demonstrate compliance with dose-based requirements are presented. These approaches include 1) modeling the pathways of radiological exposure and estimating doses to receptors from a combination of contaminated media and radionuclides, and 2) using probabilistic analysis to determine an appropriate set of input parameters to develop derived concentration guideline limits or DCGLs (DCGLs are media- and nuclide-specific concentration limits that will meet dose-based, license termination rule criteria found in 10 CFR Part 20, Subpart E). Calculation of operational (field) DCGL's from media- and nuclide-specific DCGLs and use of operational DCGLs in conducting final status surveys are addressed in the WBT. Realistic case examples are presented and analyzed including the abstraction of a realistic site into a conceptual model and computer model. A case history is also used to demonstrate development of NRC review documents such as requests for additional information (RAIs). To enhance the web-based training experience, audio, animations, linked documents, quizzes, and scripts are being integrated with a commercial web-based training package that supports simple navigation. The course is also being integrated into both existing and state-of-the-art learning management systems. A testing group is being utilized to identify and help resolve training issues prior to deployment of the course. When completed, the course can be accessed for credited training with required modules dependent on the job category of the training participant. The modules will also be accessible to NRC staff for review or refresher following initial course completion. WBT promotes consistency in reviews and has the advantage of being able to be used as a resource to staff at any time. The WBT will provide reviewers with knowledge needed to perform risk-informed analyses (e.g., information related to development of realistic scenarios and use of probabilistic analysis). WBT on review of LTP or DP dose modeling will promote staff development, efficiency, and effectiveness in performing risk-informed, performance-based reviews of decommissioning activities at NRC-licensed facilities. (authors)

LePoire, D.; Arnish, J.; Cheng, J.J.; Kamboj, S.; Richmond, P.; Chen, S.Y. [Argonne National Laboratory, Argonne, IL (United States); Barr, C.; McKenney, C. [U.S. Nuclear Regulatory Commission, Rockville, MD (United States)

2007-07-01T23:59:59.000Z

105

Review of Commercial Grade Dedication Plans for the Safety Instrumented System at the Savannah River Site Waste Solidification Building Project, August 2011  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Review of Review of Commercial Grade Dedication Plans for the Safety Instrumented System at the Savannah River Site Waste Solidification Building Project May 2011 August 2011 Office of Safety and Emergency Management Evaluations Office of Health, Safety and Security U.S. Department of Energy i Table of Contents 1.0 Purpose ................................................................................................................................................... 1 2.0 Scope ...................................................................................................................................................... 1 3.0 Background ............................................................................................................................................ 2

106

Review of Commercial Grade Dedication Plans for the Safety Instrumented System at the Savannah River Site Waste Solidification Building Project, August 2011  

NLE Websites -- All DOE Office Websites (Extended Search)

Review of Review of Commercial Grade Dedication Plans for the Safety Instrumented System at the Savannah River Site Waste Solidification Building Project May 2011 August 2011 Office of Safety and Emergency Management Evaluations Office of Health, Safety and Security U.S. Department of Energy i Table of Contents 1.0 Purpose ................................................................................................................................................... 1 2.0 Scope ...................................................................................................................................................... 1 3.0 Background ............................................................................................................................................ 2

107

Review of the Nevada National Security Site Criticality Safety Program Corrective Action Plan Closure, May 2013  

NLE Websites -- All DOE Office Websites (Extended Search)

Nevada National Security Site Nevada National Security Site Criticality Safety Program Corrective Action Plan Closure May 2013 Office of Safety and Emergency Management Evaluations Office of Enforcement and Oversight Office of Health, Safety and Security U.S. Department of Energy Table of Contents 1.0 Purpose................................................................................................................................................ 1 2.0 Scope.................................................................................................................................................. 1 3.0 Background ......................................................................................................................................... 1 4.0 Methodology ....................................................................................................................................... 2

108

Review of the Nevada National Security Site Criticality Safety Program Corrective Action Plan Closure, May 2013  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Nevada National Security Site Nevada National Security Site Criticality Safety Program Corrective Action Plan Closure May 2013 Office of Safety and Emergency Management Evaluations Office of Enforcement and Oversight Office of Health, Safety and Security U.S. Department of Energy Table of Contents 1.0 Purpose................................................................................................................................................ 1 2.0 Scope.................................................................................................................................................. 1 3.0 Background ......................................................................................................................................... 1 4.0 Methodology ....................................................................................................................................... 2

109

Comparative Review of a Dozen National Energy Plans: Focus on Renewable and Efficient Energy  

SciTech Connect

Dozens of groups have submitted energy, environmental, and economic recovery plans for consideration by the Obama administration and the 111th Congress. This report provides a comparative analysis of 12 national proposals, focusing especially on energy efficiency (EE) and renewable energy (RE) market and policy issues.

Logan, J.; James, T. L.

2009-03-01T23:59:59.000Z

110

Geothermal Program Review XII: proceedings. Geothermal Energy and the President's Climate Change Action Plan  

Science Conference Proceedings (OSTI)

Geothermal Program Review XII, sponsored by the Geothermal Division of US Department of Energy, was held April 25--28, 1994, in San Francisco, California. This annual conference is designed to promote effective technology transfer by bringing together DOE-sponsored researchers; utility representatives; geothermal energy developers; suppliers of geothermal goods and services; representatives from federal, state, and local agencies; and others with an interest in geothermal energy. In-depth reviews of the latest technological advancements and research results are presented during the conference with emphasis on those topics considered to have the greatest potential to impact the near-term commercial development of geothermal energy.

Not Available

1994-12-31T23:59:59.000Z

111

Site Visit Report - Independent Oversight Review of Work Planning/Execution and the Employee Concerns Program at Paducah, March 20105-10.doc  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

1 1 Site Visit Report - Review of Work Planning/Execution and the Employee Concerns Program at Paducah - March 2010 This report documents the results of a review activity performed by the Office of Health, Safety and Security (HSS) in support of the Department of Energy Office of Environmental Management (EM). The purpose of the review was to support EM management efforts to resolve issues and enhance planned corrective actions for worker safety concerns expressed by several safety professionals at the Paducah Plant. The review was conducted by the Office of Health Safety and Security with an EM observer during the week of February 8, 2010. Observations and recommendations resulting from this review were discussed with representatives of EM's Environmental Management Safety

112

Site Transition Guidance  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Site Transition Guidance March 2010 Office of Environmental Management U.S. Department of Energy Washington D. C. 20585 Standard Review Plan (SRP) Technical Framework for EM...

113

Operational Readiness Reviews  

NLE Websites -- All DOE Office Websites (Extended Search)

Readiness Reviews Readiness Reviews Home Applicable Directives, Standards, & Handbooks Start Up Notifications, Plan of Actions, and Implementation Plans Functional Area CRADS...

114

DOE-STD-1082-94; DOE Standard Preparation, Review, and Approval of Implementaiton Plans For Nuclear Safety Requirements  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

82-94 82-94 October 1994 DOE STANDARD PREPARATION, REVIEW, AND APPROVAL OF IMPLEMENTATION PLANS FOR NUCLEAR SAFETY REQUIREMENTS U.S. Department of Energy AREA SAFT Washington D.C. 20585 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. This document has been reproduced directly from the best available copy. Available to DOE and DOE contractors from the Office of Scientific and Technical Information, P.O. Box 62, Oak Ridge, TN 37831; (615)576-8401. Available to the public from the U.S. Department of Commerce, Technology Administration, National Technical Information Service, Springfield, VA 22161; (703) 487-4650. Order No. DE95001461 DOE-STD-1082-94 iii FOREWORD 1. This Department of Energy (DOE) technical standard has been prepared by the Office of Environment, Safety and Health with the assistance of Steve

115

Integrated resource planning for local gas distribution companies: A critical review of regulatory policy issues  

SciTech Connect

According to the report, public utility commissions (PUCs) are increasingly adopting, or considering the adoption of integrated resource planning (IRP) for local gas distribution companies (LDCs). The Energy Policy Act of 1992 (EPAct) requires PUCs to consider IRP for gas LDCs. This study has two major objectives: (1) to help PUCs develop appropriate regulatory approaches with regard to IRP for gas LDCs; and (2) to help PUCs respond to the EPAct directive. The study finds that it is appropriate for PUCs to pursue energy efficiency within the traditional regulatory framework of minimizing private costs of energy production and delivery; and PUCs should play a limited role in addressing environmental externalities. The study also finds that in promoting energy efficiency, PUCs should pursue policies that are incentive-based, procompetitive, and sensitive to rate impacts. The study evaluates a number of traditional and nontraditional ratemaking mechanisms on the basis of cost minimization, energy efficiency, competitiveness, and other criteria. The mechanisms evaluated include direct recovery of DSM expenses, lost revenue adjustments for DSM options, revenue decoupling mechanisms, sharing of DSM cost savings, performance-based rate of return for DSM, provision of DSM as a separate service, deregulation of DSM service, price caps, and deregulation of the noncore gas market. The study concludes with general recommendations for regulatory approaches and ratemaking mechanisms that PUCs may wish to consider in advancing IRP objectives.

Harunuzzaman, M.; Islam, M.

1994-08-01T23:59:59.000Z

116

ECOSYSTEM IMPACTS OF GEOENGINEERING: A Review for Developing a Science Plan  

SciTech Connect

Geoengineering methods are intended to reduce the magnitude of climate change. Climate change in some regions is already having demonstrable effects on ecosystem structure and functioning. Two different types of geoengineering activities have been proposed: carbon dioxide removal (CDR), which includes a range of engineered and biological processes to remove carbon dioxide (CO2) from the atmosphere, and solar radiation management (SRM, or sunlight reflection methods), whereby a small percentage of sunlight is reflected back into space to offset warming from greenhouse gases. In this review, we evaluate some of the possible impacts of CDR and SRM on the physical climate and their subsequent influence on ecosystems, including the risks and uncertainties associated with new kinds of purposeful perturbations to Earth. Specifically, we find evidence that, if implemented successfully, some CDR methods and continue use of some SRM methods) could alleviate some of the deleterious ecosystem impacts associated with climate changes that might occur in the foreseeable future.

Russell, Lynn M.; Rasch, Philip J.; Mace, Georgina; Jackson, Robert B.; Shepherd, John; Liss, Peter; Leinen, Margaret; Schimel, David; Vaughan, Naomi E.; Janetos, Anthony C.; Boyd, Philip W.; Norby, Richard J.; Caldeira, Ken; Merikanto, Joonas; Artaxo, Paulo; Melillo, Jerry; Morgan, M. Granger

2012-06-01T23:59:59.000Z

117

ECOSYSTEM IMPACTS OF GEOENGINEERING: A Review for Developing a Science Plan  

Science Conference Proceedings (OSTI)

Geoengineering methods are intended to reduce the magnitude of climate change, which is already having demonstrable effects on ecosystem structure and functioning. Two different types of activities have been proposed: solar radiation management (SRM), or sunlight reflection methods, which involves reflecting a small percentage of solar light back into space to offset the warming due to greenhouse gases, and carbon dioxide removal (CDR), which includes a range of engineered and biological processes to remove carbon dioxide (CO2) from the atmosphere. This report evaluates some of the possible impacts of CDR and SRM on the physical climate and their subsequent influence on ecosystems, which include the risks and uncertainties associated with new kinds of purposeful perturbations to the Earth. Therefore, the question considered in this review is whether CDR and SRM methods would exacerbate or alleviate the deleterious impacts on ecosystems associated with climate changes that might occur in the foreseeable future.Geoengineering methods are intended to reduce the magnitude of climate change, which is already having demonstrable effects on ecosystem structure and functioning. Two different types of activities have been proposed: solar radiation management (SRM), or sunlight reflection methods, which involves reflecting a small percentage of solar light back into space to offset the warming due to greenhouse gases, and carbon dioxide removal (CDR), which includes a range of engineered and biological processes to remove carbon dioxide (CO2) from the atmosphere. This report evaluates some of the possible impacts of CDR and SRM on the physical climate and their subsequent influence on ecosystems, which include the risks and uncertainties associated with new kinds of purposeful perturbations to the Earth. Therefore, the question considered in this review is whether CDR and SRM methods would exacerbate or alleviate the deleterious impacts on ecosystems associated with climate changes that might occur in the foreseeable future.

Russell, Lynn M [University of California, San Diego; Jackson, Robert B [Duke University; Norby, Richard J [ORNL

2012-01-01T23:59:59.000Z

118

Decommissioning Plan RM  

Energy.gov (U.S. Department of Energy (DOE))

The Decommissioning Plan Review (DPR) Module is a tool that assists DOE federal project review teams in evaluating the adequacy of the decommissioning plan prior to approval of the associated CD.

119

Review  

E-Print Network (OSTI)

4) Letter (100126), C. V. Anderson to K. I. McConnell, "Submission of the Phase 1 Decommissioning Plan (DP) for West Valley Demonstration Project (WVDP) for U.S. Nuclear Regulatory Commission (NRC)

unknown authors

2008-01-01T23:59:59.000Z

120

Protocol for EM Review/Field Self-Assessment of Site Specific Quality Assurance Programs/Quality Implementation Plans  

Energy.gov (U.S. Department of Energy (DOE))

Review protocol and lines of inquiry that are used as basis for technical review and approval of site-specific quality assurance programs.

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


121

Risk Assessment Guidance for Superfund: Volume I. Human Health Evaluation Manual (Part D, Standardized Planning, Reporting, and Review of Superfund Risk Assessments)  

NLE Websites -- All DOE Office Websites (Extended Search)

Publication 9285.7-01D Publication 9285.7-01D January 1998 Risk Assessment Guidance for Superfund: Volume I Human Health Evaluation Manual (Part D, Standardized Planning, Reporting, and Review of Superfund Risk Assessments) Interim Office of Emergency and Remedial Response U.S. Environmental Protection Agency Washington, DC 20460 Revision No. 0 ii January 1998 NOTICE This document provides guidance to EPA staff. The guidance is designed to communicate National policy on the planning, reporting and review of Superfund risk assessments. The document does not, however, substitute for EPA's statutes or regulations, nor is it a regulation itself. Thus, it cannot impose legally-binding requirements on EPA, States, or the regulated community, and may not apply to a particular situation based upon

122

CFN Ops Plan | Work Planning  

NLE Websites -- All DOE Office Websites (Extended Search)

Operations Plan Operations Plan Work Planning & Control for Experiments and Operations All experimental work will be conducted in accordance with Work Planning and Control for Experiments and Operations, which ensures proper design and operation of all experiments prior to their commencement. CFN will use the SBMS provided standard form for the formal documentation. The Lead Experimenter/Responsible person will notify the Experimental Safety Review Committee of any new experiments or modifications to existing experiments. CFN will appoint an Experimental Safety Review Committee. This committee will consist of the Experiment Review Coordinator, CFN personnel, Facility Support Representative (FSR), Environmental Compliance Representative (ECR). Additional subject matter experts may be appointed on an ad-hoc

123

Geothermal Technologies Program Strategic Plan  

SciTech Connect

This DOE/EERE program strategic plan builds upon previous program plans and R&D direction reviews with industry representatives and other stakeholders.

2004-08-01T23:59:59.000Z

124

Influence of Pro-Qura-generated Plans on Postimplant Dosimetric Quality: A Review of a Multi-Institutional Database  

SciTech Connect

The influence of Pro-Qura-generated plans vs. community-generated plans on postprostate brachytherapy dosimetric quality was compared. In the Pro-Qura database, 2933 postplans were evaluated from 57 institutions. A total of 1803 plans were generated by Pro-Qura and 1130 by community institutions. Iodine-125 ({sup 125}I) plans outnumbered Palladium 103 ({sup 103}Pd) plans by a ratio of 3:1. Postimplant dosimetry was performed in a standardized fashion by overlapping the preimplant ultrasound and the postimplant computed tomography (CT). In this analysis, adequacy was defined as a V{sub 100} > 80% and a D{sub 90} of 90% to 140% for both isotopes along with a V{sub 150} < 60% for {sup 125}I and < 75% for {sup 103}Pd. The mean postimplant V{sub 100} and D{sub 90} were 88.6% and 101.6% vs. 89.3% and 102.3% for Pro-Qura and community plans, respectively. When analyzed in terms of the first 8 sequence groups (10 patients/sequence group) for each institution, Pro-Qura planning resulted in less postimplant variability for V{sub 100} (86.2-89.5%) and for D{sub 90} (97.4-103.2%) while community-generated plans had greater V{sub 100} (85.3-91.2%) and D{sub 90} (95.9-105.2%) ranges. In terms of sequence groups, postimplant dosimetry was deemed 'too cool' in 11% to 30% of cases and 'too hot' in 12% to 27%. On average, no clinically significant postimplant dosimetric differences were discerned between Pro-Qura and community-based planning. However, substantially greater variability was identified in the community-based plan cohort. It is possible that the Pro-Qura plan and/or the routine postimplant dosimetric evaluation may have influenced dosimetric outcomes at community-based centers.

Allen, Zachariah [Wheeling Hospital, Schiffler Cancer Center, Wheeling, WV (United States)]|[Wheeling Jesuit University, Wheeling, WV (United States)]|[Seattle Prostate Institute, Seattle, WA (United States)]|[Pro-Qura, Seattle, WA (United States); Merrick, Gregory S. [Wheeling Hospital, Schiffler Cancer Center, Wheeling, WV (United States)]|[Wheeling Jesuit University, Wheeling, WV (United States)]|[Seattle Prostate Institute, Seattle, WA (United States)]|[Pro-Qura, Seattle, WA (United States)], E-mail: gmerrick@urologicresearchinstitute.org; Grimm, Peter; Blasko, John; Sylvester, John; Butler, Wayne; Chaudry, Usman-Ul-Haq; Sitter, Michael [Wheeling Hospital, Schiffler Cancer Center, Wheeling, WV (United States)]|[Wheeling Jesuit University, Wheeling, WV (United States)]|[Seattle Prostate Institute, Seattle, WA (United States)]|[Pro-Qura, Seattle, WA (United States)

2008-10-01T23:59:59.000Z

125

Guidelines for preparing and reviewing applications for the licensing of non-power reactors: Standard review plan and acceptance criteria. NUREG - 1537, Part 2  

SciTech Connect

NUREG - 1537, Part 2 gives guidance on the conduct of licensing action reviews to NRC staff who review non-power reactor licensing applications. These licensing actions include construction permits and initial operating licenses, license renewals, amendments, conversions from highly enriched uranium to low-enriched uranium, decommissioning, and license termination.

1996-02-01T23:59:59.000Z

126

Protocol for EM Review/Field Self-Assessment of Site Specific Quality Assurance Programs/Quality Implementation Plans  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Protocol for QAP/QIP Review Protocol for QAP/QIP Review March 2010 1 Table of Content 1.1 Overview ............................................................................................................................................... 2 1.2 Purpose .................................................................................................................................................. 2 1.3 EM-HQ Corporate Review Process ...................................................................................................... 3 1.3.1 Phase 1: EM-HQ Approval for Implementation of QAP/QIP ..................................... 3 1.3.2 Phase 2: EM-HQ Verification and Validation (V&V) of QAP/QIP Implementation . 4 1.4 Contact Information .............................................................................................................................. 5

127

Review  

E-Print Network (OSTI)

review of the Phase I DP for the West Valley Demonstration Project, Rev. I (Reference 1). DOE submitted responses to the other 38 of the 44 RAIs to NRC on August 13, 2009 (Reference 3). Enclosed are 20 paper copies of the RAI response package along with 20 compact disks. Each compact disk contains an electronic copy of the six RAI responses and two calculationQ t Dr. Keith 1. McConnell-3- September 16, 2009 For Further Information Please note that DOE's RAI responses and the proposed decommissioning approach are based on the preferred alternative in the Revised Draft Environmental Impact Statement for

unknown authors

2009-01-01T23:59:59.000Z

128

Book Review: Radiological Conditions in the Dnieper River Basin: Assessment by an International Expert Team and Recommendations for an Action Plan  

SciTech Connect

This article is a book review of a report from the International Atomic Energy Agency that was prepared by a team of scientists from Belarus, the Russian Federation, and Ukraine as an assessment of radiological contamination of the Dnieper River, which flows through these three countries. The topics covered begin with radioactive sources (actual and potential) including areas affected by the Chernobyl nuclear accident, nuclear power plants along the river and its tributaries, uranium mining and ore processing, radioactive waste storage and disposal sites, and non-power sources, such as medicine, industry, and research. The report continues with an assessment of human exposures to radiation from these sources. An additional area of consideration is radiological hot spots in the region. The report finishes with conclusions and recommendations to the regional governments for a strategic action plan and individual government national plans.

Napier, Bruce A.

2007-12-31T23:59:59.000Z

129

SOLERAS - Saudi University Solar Cooling Laboratories Project: King Faisal University. Design analysis study. Volume 1. Design review report, data acquisition plan and experimental plan  

Science Conference Proceedings (OSTI)

Four preliminary passive solar dwelling design concepts were developed based upon previously established climatic design criteria and an identification of applicable passive cooling strategies was made. These were quantitatively compared for their thermal performance based upon a computer program. The selected concept was optimized and preliminary construction drawings and details were submitted for review by SOLERAS. This report deals with the further refinement and development of the design concept and improvements of the performance of the selected passive elements. The final design has been detailed for actual construction and monitoring at the King Faisal University Dammam Campus. In addition this report addresses the comparative evaluation of the previous design concepts utilizing more rigorous computer simulation methods.

Not Available

1986-01-01T23:59:59.000Z

130

Review of hardware cost estimation methods, models and tools applied to early phases of space mission planning  

E-Print Network (OSTI)

Equipment; AHP, Analytic Hierarchy Process; AMCM, Advanced Missions Cost Model; ASPE, American SocietyReview of hardware cost estimation methods, models and tools applied to early phases of space Cost estimation Cost model Parametrics Space hardware Early mission phase a b s t r a c t The primary

Sekercioglu, Y. Ahmet

131

Commercial Grade Dedication RM  

Energy.gov (U.S. Department of Energy (DOE))

The objective of this Standard Review Plan (SRP) on Commercial Grade Dedication (CGD) is to provide guidance for a uniform review of the CGD activities for office of Environmental Management...

132

Introductory materials for committee members: 1) instructions for the Los Alamos National Laboratory fiscal year 2010 capability reviews 2) NPAC strategic capability planning 3) Summary self-assessment for the nuclear and particle physics, astrophysics an  

Science Conference Proceedings (OSTI)

Los Alamos National Laboratory (LANL) uses external peer review to measure and continuously improve the quality of its science, technology and engineering (STE). LANL uses capability reviews to assess the STE quality and institutional integration and to advise Laboratory Management on the current and future health of the STE. Capability reviews address the STE integration that LANL uses to meet mission requirements. STE capabilities are define to cut across directorates providing a more holistic view of the STE quality, integration to achieve mission requirements, and mission relevance. The scope of these capabilities necessitate that there will be significant overlap in technical areas covered by capability reviews (e.g., materials research and weapons science and engineering). In addition, LANL staff may be reviewed in different capability reviews because of their varied assignments and expertise. LANL plans to perform a complete review of the Laboratory's STE capabilities (hence staff) in a three-year cycle. The principal product of an external review is a report that includes the review committee's assessments, commendations, and recommendations for STE. The Capability Review Committees serve a dual role of providing assessment of the Laboratory's technical contributions and integration towards its missions and providing advice to Laboratory Management. The assessments and advice are documented in reports prepared by the Capability Review Committees that are delivered to the Director and to the Principal Associate Director for Science, Technology and Engineering (PADSTE). This report will be used by Laboratory Management for STE assessment and planning. The report is also provided to the Department of Energy (DOE) as part of LANL's Annual Performance Plan and to the Los Alamos National Security (LANS) LLC's Science and Technology Committee (STC) as part of its responsibilities to the LANS Board of Governors.

Redondo, Antonio [Los Alamos National Laboratory

2010-01-01T23:59:59.000Z

133

Work Plans & Manuals | Department of Energy  

NLE Websites -- All DOE Office Websites (Extended Search)

Reports Calendar Year Reports Recovery Act Peer Reviews DOE Directives Performance Strategic Plan Testimony Financial Statements Semiannual Reports Work Plan Mission About Us...

134

Annual Planning Summaries: 2010 | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

for each NEPA review identified. January 29, 2010 2010 Annual Planning Summary for Intelligence and Counterintelligence (IN) Annual Planning Summaries briefly describe the...

135

Peer Reviews | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Reports Calendar Year Reports Recovery Act Peer Reviews DOE Directives Performance Strategic Plan Testimony Financial Statements Semiannual Reports Work Plan Mission About Us...

136

PURADYN Oil Bypass Filtration System Evaluation Test Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

& Infrastructure Department PURADYN OIL BYPASS FILTRATION SYSTEM EVALUATION TEST PLAN October 2002 Reviewed: INEEL Fleet Maintenance Supervisor (Thomas) Date Reviewed:...

137

Strategic Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Plan Strategic Plan Print ALS Strategic Plan Update: March 2013 The Advanced Light Source Strategic Plan, originally published in 2009, has been revised to reflect completed...

138

LFRG Program Management Plan  

Energy.gov (U.S. Department of Energy (DOE))

The purpose of the EM Low-Level Waste Disposal Facility Federal Review Group Program Management Plan (LFRG PMP) is to establish the LFRG roles and responsibilities, the LFRG management processes,...

139

Preparation for Facility Operations RM  

Energy.gov (U.S. Department of Energy (DOE))

The objective of this Standard Review Plan (SRP) on Preparation for Facility Operations is to provide consistency guidance to evaluate the effectiveness of the final project closure of major...

140

Cogeneration Planning  

E-Print Network (OSTI)

Cogeneration, the sequential use of a fuel to generate electricity and thermal energy, has become a widely discussed concept in energy engineering. American-Standard, a world-wide diversified manufacturing corporation, has actively been pursuing cogeneration projects for its plants. Of concern to us are rapidly escalating electrical costs plus concern about the future of some utilities to maintain reserve capacity. Our review to date revolves around (1) obtaining low-cost reliable fuel supplies for the cogeneration system, (2) identifying high cost/low reserve utilities, and (3) developing systems which are base loaded, and thus cost-effective. This paper will be an up-to-date review of our cogeneration planning process.

Mozzo, M. A. Jr.

1985-05-01T23:59:59.000Z

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


141

Report: EM Strategic Planning  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

STRATEGIC PLANNING STRATEGIC PLANNING September 25, 2008 Submitted by the EMAB Strategic Planning Subcommittee Background In Fiscal Year (FY) 2008, the Environmental Management Advisory Board (EMAB) was tasked to assess EM's strategic planning capabilities/processes and, in particular, to review the status of the initiatives pursued by the Office of Strategic Planning and Analysis (EM-32). This charge was derived from the Board's work pertaining to the topics of Discretionary Budgeting and Technical Uncertainty and Risk Reduction, which were addressed in previous reports and recommendations to the Assistant Secretary. The EMAB Strategic Planning Committee was formed to expand on this earlier work and pursue dialogues with the EM Office of Program Planning and Budget (EM-30) in

142

Oak Ridge D and D Plan 3515 Project - Technology Review (2007) and GammaCam Technology Demonstration for Characterizing Building 3515 at Oak Ridge (2007)  

Science Conference Proceedings (OSTI)

This paper presents the results from the Characterization, Decontamination and Decommissioning (CD and D) Study performed by MSE Technology Application, Inc. (MSE) to assist the U.S. Department of Energy (DOE) and Oak Ridge National Laboratory (ORNL) in the preparation of a Project Execution Plan and Remediation Plan for Building 3515 at ORNL. Primary objectives of this study were to identify innovative CD and D technologies and methodologies and recommend alternatives applicable to the CD and D of Building 3515. Building 3515 is a small heavily shielded concrete and cement block structure centrally located in the Bethel Valley portion of the ORNL. The building's interior is extensively contaminated with Cesium 137 (Cs-137), the primary contaminant of concern. A previous attempt to characterize the building was limited to general interior area radiation exposure level measurements and a few surface smears gathered by inserting monitoring equipment into the building on long poles. Consequently, the spatial distribution of the gamma radiation source inside the building was not determined. A subsequent plan for D and D of the building presented a high risk of worker radiation dose in excess of as low as reasonably achievable (ALARA) because the source of the interior gamma radiation field is not completely understood and conventional practices required workers to be in close proximity of the building. As part of an initial literature search, MSE reviewed new generation gamma source characterization technologies and identified the GammaCam{sup TM} portable gamma ray imaging system as an innovative technology applicable to locating the dominant gamma ray sources within the building. The GammaCam{sup TM} gamma-ray imaging system is a commercially available technology marketed by the EDO Corporation. This system consists of a sensor head with a co-aligned camera and a portable computer. The system is designed to provide two-dimensional spatial mappings of gamma ray emitting nuclides in real time. The gamma radiation sensor and camera can be set up within or outside of the radiation field while the system operator and PC can be located 30 to 60 m (100 to 200 ft) from the sensor head. The system has been used successfully at numerous DOE and commercial nuclear facilities to precisely locate gamma radiation sources. However, literature attesting to the ability of this technology to detect radiation sources within heavily shielded structures was not available. Consequently, MSE was not certain if this technology would be capable of locating gamma ray sources within the heavily shielded Building 3515. To overcome this uncertainty, MSE sent two individuals to the EDO Corporation for training. At completion of the training, MSE leased the GammaCam{sup TM} portable system and brought it to ORNL to evaluate the capability of the system. An overview from this evaluation is summarized in this paper. (authors)

Byrne-Kelly, D.; Hart, A.; Brown, Ch.; Jordan, D. [MSE Technology Applications, Inc., Montana (United States); Phillips, E. [U.S. Department of Energy, Oak Ridge Operations Office, Oak Ridge, Tennessee (United States)

2008-07-01T23:59:59.000Z

143

Reviewer Instructions:  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Reviewer Instructions: Reviewer Instructions: 1. All review comments to be provided electronically using this review form. 2. Focus the review on substantive issues within your disciplinary, regulatory, or policy area. 3. Look only at the portions relevant to your agency and the land under your management. The individual land management agencies will be amending land use plans or issuing a Record of Decision, so please don't alter the other agencies' roles and responsibilities. 4. Target the review on the adequacy and reasonableness of text and analyses within your disciplinary, regulatory, or policy area. Please be aware that this is a programmatic EIS. 5. All comments should be as specific as possible. Comments such as "text unclear" or "expand" do not provide sufficient

144

Office of Inspector General Annual Performance Plan 2012 | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Reports Calendar Year Reports Recovery Act Peer Reviews DOE Directives Performance Strategic Plan Testimony Financial Statements Semiannual Reports Work Plan Mission About Us...

145

Annual Performance Report FY 2004 Annual Performance Plan FY...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Reports Calendar Year Reports Recovery Act Peer Reviews DOE Directives Performance Strategic Plan Testimony Financial Statements Semiannual Reports Work Plan Mission About Us...

146

Planned Audits and Inspections FY 2013 | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

FOIA Reports Calendar Year Reports Recovery Act Peer Reviews DOE Directives Performance Strategic Plan Testimony Financial Statements Semiannual Reports Work Plan Mission About...

147

Independent Oversight Review, Portsmouth Gaseous Diffusion Plant- January 2013  

Energy.gov (U.S. Department of Energy (DOE))

Review of the Portsmouth Gaseous Diffusion Plant Work Planning and Control Activities Prior to Work Execution

148

Flight Plan  

E-Print Network (OSTI)

Developing broader linguistic capability and cultural understanding iscritical to prevail in the long war and meet 21 st Century challenges. The Department must dramatically increase the number of personnel proficient in key languagesand make these languages available at all levels of action and decision from the strategic to the tactical. 2006 Quadrennial Defense Review, p. 78 Due to the nature of immediate and likely future challenges, our Joint forces require Airmen capable of influencing the outcomes of US, allied, and coalition operations anywhere in the world. While we, the Air Force, have made considerable initial progress toward building the necessary cross-cultural skills, we recognize the existing processes for obtaining this forceenhancing capability (appropriate culture, region, language and negotiation skills) are not currently mature or robust enough to optimally meet immediate expectations or near-future requirements. Therefore, it is imperative that we tailor our cultural, regional, and language competency development to maximize our efforts and meet Air Force and Joint requirements informed by National guidance. To this end, the Air Force Culture, Region, and Language (CRL) Flight Plan represents our framework for implementing relevant National Security and National Defense strategies via Air Force programs. The dynamic global environment has made Cross-Cultural Competence a critical and necessary capability for the Total Force. The Air Force CRL Flight Plan supports the

unknown authors

2009-01-01T23:59:59.000Z

149

Site Sustainability Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

U.S. Department of Energy U.S. Department of Energy Office of Legacy Management December 2013 LMS/S07225 This page intentionally left blank This page intentionally left blank U.S. Department of Energy Site Sustainability Plan December 2013 Doc. No. S07225 Page i Contents Abbreviations ................................................................................................................................. iii I. Executive Summary ...............................................................................................................1 II. Performance Review and Plan Narrative ...............................................................................9 1 GHG Reduction and Comprehensive GHG Inventory ...........................................................9

150

Energy Efficiency Planning Guidebook  

Science Conference Proceedings (OSTI)

Demand planning is an essential undertaking for utilities looking to understand and quantify the dispatchable resources associated with energy efficiency and demand response programs. Further, demand planning enables a utility to select the most appropriate, cost-effective suite of energy efficiency technologies, demand response technologies, and program delivery mechanisms for its unique market and operating conditions as well as the optimal level of investment. This guidebook reviews and explains a com...

2008-07-07T23:59:59.000Z

151

Lesson Plans!  

NLE Websites -- All DOE Office Websites (Extended Search)

you from other teachers, educators, and professionals. These lesson plans are provided free of charge, to help you planning a challenging curriculum that will instill a love of...

152

Medical Plans  

NLE Websites -- All DOE Office Websites (Extended Search)

Medical Plans Retiree Medical Insurance Blue Cross Blue Shield of New Mexico (BCBSNM) is the provider of medical benefits. Contact Retiree Insurance Providers Medical plan options...

153

Transmission Planning  

NLE Websites -- All DOE Office Websites (Extended Search)

Planning Transmission Planning We accept requests from electric utilities, firm-power customers, private power developers, and independent power generators to interconnect...

154

PROJECT MANGEMENT PLAN EXAMPLES Feedback Examples  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

already in effect for 9206 operations, such as plan-of-the-day, daily crew briefs, pre-job briefs, hazard identification, work planning, review of lessons learned, worker...

155

Planning Workshop  

Science Conference Proceedings (OSTI)

Planning Workshop on Renewable Energy and Climate Science for the Americas: Metrology and Technology Challenges. ...

2013-12-05T23:59:59.000Z

156

Evaluating the use of immersive display media for construction planning  

Science Conference Proceedings (OSTI)

The aim of this research is to develop construction planning and plan review processes within virtual environments that result in the consistent development of more innovative and higher quality construction plans. During the early stages of this research, ...

John I. Messner

2006-06-01T23:59:59.000Z

157

Review: A survey of models and algorithms for emergency response logistics in electric distribution systems. Part I: Reliability planning with fault considerations  

Science Conference Proceedings (OSTI)

Emergency response operations in electric distribution systems involve a host of decision-making problems at the reliability and contingency planning levels. Those operations include fault diagnosis, fault location, fault isolation, restoration, and ... Keywords: Depot location, District design, Electric power distribution, Emergency response, Operations research, System configuration

Nathalie Perrier; Bruno Agard; Pierre Baptiste; Jean-Marc Frayret; Andr Langevin; Robert Pellerin; Diane Riopel; Martin TrPanier

2013-07-01T23:59:59.000Z

158

Published Peer Reviews | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Published Peer Reviews Published Peer Reviews Published Peer Reviews Peer Review Agenda Vehicle Technologies Annual Merit Review Effects of Intermediate Ethanol Blends on Legacy Vehicles and Small Non-Road Engines, Report 1 (pdf) Peer Review Plan for influential scientific assessment entitled, "Effects of Intermediate Ethanol Blends on Legacy Vehicles and Small Non-Road Engines, Report 1." (pdf) Peer Review Plan for Highly Influential Scientific Assessment entitled, "Climate Models: An Assessment of Strengths and Limitations for User Applications" (pdf) Peer Review Plan for Highly Influential Scientific Assessment entitled, "Synthesis and Assessment Report on Scenarios of Greenhouse Gas Emissions and Atmospheric Concentrations and Review of Integrated Scenario

159

The Cost of Transmission for Wind Energy: A Review of Transmission...  

NLE Websites -- All DOE Office Websites (Extended Search)

Wind Energy: A Review of Transmission Planning Studies Title The Cost of Transmission for Wind Energy: A Review of Transmission Planning Studies Publication Type Report Year of...

160

Planning Team | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Planning Team Planning Team Planning Team October 16, 2013 - 5:11pm Addthis Photo of three men standing together reviewing a large print document. The men have bright orange and yellow construction vests and hard hats. A data center manager reviews blueprints with an IT project manager and data center coordinator during construction of a Federal facility. Planning is the time to bring renewable energy expertise to the table, including a strong renewable energy planning team that will be part of the project though completion. It is important to have a team in place with the skills required to advocate for renewable energy and the agency's best interests throughout the project. The planning team set the goals and objectives for the project as well as criteria for design team selection and should be convened at the outset of

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


161

Guidelines for strategic planning  

SciTech Connect

Strategic planning needs to be done as one of the integral steps in fulfilling our overall Departmental mission. The role of strategic planning is to assure that the longer term destinations, goals, and objectives which the programs and activities of the Department are striving towards are the best we can envision today so that our courses can then be set to move in those directions. Strategic planning will assist the Secretary, Deputy Secretary, and Under Secretary in setting the long-term directions and policies for the Department and in making final decisions on near-term priorities and resource allocations. It will assist program developers and implementors by providing the necessary guidance for multi-year program plans and budgets. It is one of the essential steps in the secretary's Strategic Planning Initiative. The operational planning most of us are so familiar with deals with how to get things done and with the resources needed (people, money, facilities, time) to carry out tasks. Operating plans like budgets, capital line item projects, R D budgets, project proposals, etc., are vital to the mission of the Department. They deal, however, with how to carry out programs to achieve some objective or budget assumption. Strategic planning deals with the prior question of what it is that should be attempted. It deals with what objectives the many programs and activities of the Department of Department should be striving toward. The purpose of this document is to provide guidance to those organizations and personnel starting the process for the first time as well as those who have prepared strategic plans in the past and now wish to review and update them. This guideline should not be constructed as a rigid, restrictive or confining rulebook. Each organization is encouraged to develop such enhancements as they think may be useful in their planning. The steps outlined in this document represent a very simplified approach to strategic planning. 9 refs.

1991-07-01T23:59:59.000Z

162

Construction Project Safety and Health Plan RM  

Energy.gov (U.S. Department of Energy (DOE))

The Construction Project Safety and Health Plan (CPSHP) Review Module is a tool that assists DOE federal project review teams in evaluating the technical sufficiency of the project readiness in...

163

High Risk Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Risk Plan Risk Plan John Bashista Melissa Rider Jeff Davis Timeline to date * OMB memo on Improving Government Acquisition issued July 29, 2009 - Review existing contracts and acquisition practices to save 7% of baseline contract spending (3.5% in FY 2010 and 3.5% in FY 2011) - Reduce high risk contracts by 10% the share of dollars obligated in FY2010 - Final plan was due and submitted on November 2, 2009 - OMB reviewed and requested revision Dec 23, 2009 - Revision submitted April 21, 2010 M&Os are an Issue * With respect to reductions in high risk contracting strategies, the M&O contracts was also a challenge since the opportunity to further influence competition and contract type was highly constrained. The Department had already competed approximately 85 percent of its M&O

164

May 2012 Crab Plan Team Report C3(a)(2) Crab Plan Team report  

E-Print Network (OSTI)

Management Council's Crab Plan Team (CPT) met May 7-10, 2012 at the Hilton Hotel in Anchorage, AK. Crab Plan the review included: (1) survey efficiency and vessel use (e.g., the utility of corner stations for Pribilof

165

Security Plans  

Science Conference Proceedings (OSTI)

... Appendix A Glossary - A glossary of security terms used within the security planning document. ... F, Glossary. None applicable.

2013-09-30T23:59:59.000Z

166

Codes and standards and other guidance cited in regulatory documents  

SciTech Connect

As part of the U.S. Nuclear Regulatory Commission (NRC) Standard Review Plan Update and Development Program (SRP-UDP), Pacific Northwest National Laboratory developed a listing of industry consensus codes and standards and other government and industry guidance referred to in regulatory documents. The SRP-UDP has been completed and the SRP-Maintenance Program (SRP-MP) is now maintaining this listing. Besides updating previous information, Revision 3 adds approximately 80 citations. This listing identifies the version of the code or standard cited in the regulatory document, the regulatory document, and the current version of the code or standard. It also provides a summary characterization of the nature of the citation. This listing was developed from electronic searches of the Code of Federal Regulations and the NRC`s Bulletins, Information Notices, Circulars, Enforcement Manual, Generic Letters, Inspection Manual, Policy Statements, Regulatory Guides, Standard Technical Specifications and the Standard Review Plan (NUREG-0800).

Nickolaus, J.R.; Bohlander, K.L.

1996-08-01T23:59:59.000Z

167

Fermilab | Directorate | Program Planning Office  

NLE Websites -- All DOE Office Websites (Extended Search)

Program Planning Office Program Planning Office Steve Geer, Head The Program Planning Office within the Fermilab Directorate coordinates the experimental physics program carried out at the Laboratory. The office provides a link between ongoing and planned experiments and the Directorate, by: Acting as liaison between experimenters and laboratory staff regarding beam conditions during accelerator operation. Establishing priorities between accelerator studies and experiments and among experiments, in consultation with the Director, and resolving conflicting requests from experiments. Coordinating Division and Section reviews of draft Memoranda of Understanding for approved experiments. Coordinating updates to the "Procedures for Researchers" which provides a guide for researchers using Fermilab facilities.

168

Task Plans  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Task Plans Task Plans This page contains links to a tentative listing of active and closed TEC Task Plans. Final status of these task plans will be determined after the July 2000 TEC meeting. Task Plan Number/Title DOE Lead Staff Last Update Comment Status/ New No. After 7/27/00 GP-1, Section 180(c) Coordination (begun 1/96) C. Macaluso 7/98 DOE published a Revised Proposed Policy and Procedures in April 1998; no final policy will be issued until a definitive date for NWPA shipments is determined, based on site suitability or other legislative direction. To the extent that any issues related to Section 180(c) arise in TEC meetings, they are being discussed in the context of the consolidated grant topic group which is covered by another task plan. Closed

169

Decommissioning Planning  

Science Conference Proceedings (OSTI)

The purpose of this EPRI Technical Report is to provide a series of pre-planning guidance documents for the decommissioning of a nuclear power plant. This guidance is based in part upon Nuclear Decommissioning Plans (NDPs) developed by Commonwealth Edison (now Exelon) following the premature closure of Zion Station in 1998 as well as from other industry references and experience. These NDPs focus on the planning activities over the period from prior to final shutdown through the transition period into de...

2006-11-15T23:59:59.000Z

170

Strategic plan for infrastructure optimization  

SciTech Connect

This document represents Fluor Daniel Hanford`s and DynCorp`s Tri-Cities Strategic Plan for Fiscal Years 1998--2002, the road map that will guide them into the next century and their sixth year of providing safe and cost effective infrastructure services and support to the Department of Energy (DOE) and the Hanford Site. The Plan responds directly to the issues raised in the FDH/DOE Critical Self Assessment specifically: (1) a strategy in place to give DOE the management (systems) and physical infrastructure for the future; (2) dealing with the barriers that exist to making change; and (3) a plan to right-size the infrastructure and services, and reduce the cost of providing services. The Plan incorporates initiatives from several studies conducted in Fiscal Year 1997 to include: the Systems Functional Analysis, 200 Area Water Commercial Practices Plan, $ million Originated Cost Budget Achievement Plan, the 1OO Area Vacate Plan, the Railroad Shutdown Plan, as well as recommendations from the recently completed Review of Hanford Electrical Utility. These and other initiatives identified over the next five years will result in significant improvements in efficiency, allowing a greater portion of the infrastructure budget to be applied to Site cleanup. The Plan outlines a planning and management process that defines infrastructure services and structure by linking site technical base line data and customer requirements to work scope and resources. The Plan also provides a vision of where Site infrastructure is going and specific initiatives to get there.

Donley, C.D.

1998-05-27T23:59:59.000Z

171

Emergency Plans  

Science Conference Proceedings (OSTI)

... Early Dismissal (Early Closing) Due to Inclement Weather - Snow/Ice or Emergency Situation. ... Emergency Situation - "Shelter-in-Place" Plan. ...

2013-02-18T23:59:59.000Z

172

Annual Planning Summaries: 2010 | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

0 0 Annual Planning Summaries: 2010 February 24, 2010 2010 Annual Planning Summary for Energy Efficiency and Renewable Energy Annual Planning Summaries briefly describe the status of ongoing NEPA compliance activities, any EAs expected to be prepared in the next 12 months, any EISs expected to be prepared in the next 24 months, and the planned cost and schedule for each NEPA review identified. February 2, 2010 2010 Annual Planning Summary for Chief Financial Officer (CFO) Annual Planning Summaries briefly describe the status of ongoing NEPA compliance activities, any EAs expected to be prepared in the next 12 months, any EISs expected to be prepared in the next 24 months, and the planned cost and schedule for each NEPA review identified. February 1, 2010 2010 Annual Planning Summary for Oak Ridge (OR)

173

DOE OIG Strategic Plan Fiscal Years 2003-2008 | Department of...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Reports Calendar Year Reports Recovery Act Peer Reviews DOE Directives Performance Strategic Plan Testimony Financial Statements Semiannual Reports Work Plan Mission About Us...

174

Institutional Plan FY 2003 - 2007  

Science Conference Proceedings (OSTI)

The Fiscal Year (FY) 2003-2007 Institutional Plan describes the strategic directions and key issues that Lawrence Berkeley National Laboratory management must address with the Department of Energy (DOE) in charting its future as a multiprogram national laboratory. The Plan provides an overview of the Laboratory's mission, strategic plan, initiatives, and the resources required to fulfill its role in support of national needs in fundamental science and technology, energy resources, and environmental quality. The Plan facilitates the Department of Energy's ongoing efforts to strengthen the Integrated Laboratory System. Preparation and review of the Institutional Plan is one element of the Department of Energy's strategic management planning activities, implemented through an annual planning process. The Plan supports the President's Management Agenda and the Government Performance and Results Act of 1993. The Plan complements the current performance-based contract between the Department of Energy and the Regents of the University of California, and summarizes Best Management Practices for a potential future results-based contract as a basis for achieving DOE goals and the Laboratory's scientific and operations objectives. It identifies technical and administrative directions in the context of national energy policy and research needs and the Department of Energy's program planning initiatives. Preparation of the Plan is coordinated by the Planning and Strategic Development Office from information contributed by Berkeley Lab's scientific and support divisions and DOE comments on prior years' plans. The Laboratory Mission section identifies the specific strengths of Berkeley Lab that contribute to the mission in general and the Integrated Laboratory System in particular. The Laboratory Strategic Plan section identifies the existing activities in support of DOE Office of Science and other sponsors; support for DOE goals; and the Laboratory Scientific Vision and operations goals. The Initiatives section describes some of the specific new research programs representing major long-term opportunities for the Department of Energy and Berkeley Lab. The Operations Strategic Planning section describes our strategic thinking in the areas of human resources; site and cyber security; workforce diversity; communications and trust; integrated safety management; and technology transfer activities. The Infrastructure Strategic Planning section describes Berkeley Lab's facilities planning process and our site and facility needs. The Summary of Major Issues section provides context for discussions at the Institutional Planning On-Site Review. The Resource Projections are estimates of required budgetary authority for Berkeley Lab's research programs.

Chartock, Michael; Hansen, Todd

2003-01-27T23:59:59.000Z

175

DOE Review  

NLE Websites -- All DOE Office Websites (Extended Search)

Review 2007 Review 2007 AWA Facility Update, High Gradient Wakefield Generation, and Future Upgrades Manoel Conde, Sergey Antipov, Felipe Franchini, Wei Gai, Feng Gao, Chunguang Jing, Richard Konecny, Wanming Liu, Jidong Long, John Power, Haitao Wang, Zikri Yusof Argonne Wakefield Accelerator Group High Energy Physics Division April 25 - 27, 2007 2 Outline Description of AWA Facililty. Wakefield structures built and tested. Measurements and simulations. List of next experiments to be performed. Plans for Facility upgrades. 3 AWA Drive Beamline Drive Gun Linac & Steering Coils Quads Wakefield Structure Experimental Chambers 4.5 m GV GV YAG1 YAG2 Spectrometer YAG5 Dump/ Faraday Cup Slits YAG4 YAG3 ICT1 ICT2 BPM Single bunch operation - Q=1-100 nC - Energy=15 MeV - High Current = 10 kAmp

176

GRIPS Plan  

DOE Green Energy (OSTI)

The GRIPS (Geothermal Resources Impact Projection Study) Commission was established by a Joint Powers Agreement between the California Counties of Lake, Mendocino, Napa, and Sonoma. The objectives of GRIPS are primarily to develop and use a cooperative environmental data collection and use system including natural, social, and economic considerations to facilitate their independent decisions and those of State and Federal agencies related to the environmental effects of geothermal development. This GRIPS Plan was prepared from a wide range of studies, workshops, and staff analyses. The plan is presented in four parts: summary and introduction; environmental data status report; planned programs; and budget. (MHR)

Not Available

1978-07-31T23:59:59.000Z

177

Energy Conservation Plans | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Conservation Plans Conservation Plans Energy Conservation Plans Headquarters Program and Staff Office Energy Conservation Plans As part of the Department's Energy Efficiency campaign, each Headquarters Program and Staff Office participated in a contest early in 2010 to develop the best Energy Conservation Plan. These plans involved simple changes that employees could implement as part of their daily routines to help conserve energy. Plans were then divided into categories and reviewed by a panel to determine the best plan in each category. Employee Participation Category: Office of Fossil Energy (FE) Lighting Category: Office of Management (MA) Copier, Scanner, Fax Category: Office of Energy Efficiency & Renewable Energy (EE) Best Overall Plan: Office of Nuclear Energy (NE)

178

Energy Conservation Plans | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Energy Conservation Plans Energy Conservation Plans Energy Conservation Plans Headquarters Program and Staff Office Energy Conservation Plans As part of the Department's Energy Efficiency campaign, each Headquarters Program and Staff Office participated in a contest early in 2010 to develop the best Energy Conservation Plan. These plans involved simple changes that employees could implement as part of their daily routines to help conserve energy. Plans were then divided into categories and reviewed by a panel to determine the best plan in each category. Employee Participation Category: Office of Fossil Energy (FE) Lighting Category: Office of Management (MA) Copier, Scanner, Fax Category: Office of Energy Efficiency & Renewable Energy (EE) Best Overall Plan: Office of Nuclear Energy (NE)

179

Test plan  

U.S. Energy Information Administration (EIA)

3.0 TEST PLAN METHODOLOGY 8. 3.1 Assumptions 8. 3.2 Methodology 8. 4.0 COMMENTS ON INITIAL VIEW OF THE DATA 16 1.0 INTRODUCTION. EIA tasked Allied ...

180

RADIOLOGICAL EMERGENCY RESPONSE PLANNING FOR NUCLEAR POWER PLANTS IN CALIFORNIA. VOLUME 4 OF THE FINAL REPORT ON HEALTH AND SAFETY IMPACTS OF NUCLEAR, GEOTHERMAL, AND FOSSIL-FUEL ELECTRIC GENERATION IN CALIFORNIA  

E-Print Network (OSTI)

Population Evaluation Emergency Planning for Nuclear PowerPotential Definition of Nuclear Emergencies Developingan Emergency Plan . . . . Regulatory Review of Utilities!

Yen, W.W.S.

2010-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


181

1969 audit of SRP radioactive waste  

SciTech Connect

This report summarizes releases of radioactive waste to the environs of the Savannah River Plant during the calendar year 1969. Total quantities of radioactive waste released from plant startup through 1969 are also reported. Accuracy is not always implied to the degree indicated by the number of significant figures reported. Values were not rounded off, since data will be used in future cumulative summaries. No explanations are given for unusual releases; this information may be found in the Radiological Sciences Division Monthly Reports and in the Semi-annual and Annual Environmental Monitoring Reports for 1969.

Ashley, C.

1970-04-01T23:59:59.000Z

182

SRP radioactive waste releases. Startup through 1959  

SciTech Connect

This report summarizes and documents radioactive waste released to the environs of the Savannah River Plant from startup through 1959. During this period, the quantity of beta-emitting radioisotopes released was determined by a total or ``gross`` analysis. However, advanced instrumentation and technology now permit an economical determination of most individual radionuclides. Therefore, future waste audit reports, beginning with January 1960, will record the quantity of specific radioisotopes released rather than gross amounts.

Ashley, C.

1960-09-01T23:59:59.000Z

183

1965 audit of SRP radioactive waste  

SciTech Connect

This report summarizes releases of radioactive waste to the environs of the Savannah River Plant during the calendar year 1965. Total quantities of radioactive waste released from plant startup through 1965 are also reported. Accuracy is not always implied to the degree indicated by the number of significant figures reported. Values were not rounded off, since data will be used in future cumulative summaries. No explanations are given for unusual releases; this information may be found in the Radiological and Environmental Sciences Division Monthly Reports and in the Semi- annual and Annual Environmental Monitoring Reports for 1965.

Ashley, C.

1966-05-01T23:59:59.000Z

184

Plans, Procedures  

NLE Websites -- All DOE Office Websites (Extended Search)

of Newly Identified Solid Waste Management Units (SWMUs) and Areas of Concern (AOCs) and Newly Discovered Releases EP-WES-SOP-4006 Review of Projects for Impacts to...

185

2010 Annual Planning Summary for Nevada Site Office | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

to be prepared in the next 24 months, and the planned cost and schedule for each NEPA review identified. 2010 Annual Planning Summary for Nevada Site Office More Documents &...

186

2010 Annual Planning Summary Livermore Site Office (LSO) | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

to be prepared in the next 24 months, and the planned cost and schedule for each NEPA review identified. 2010 Annual Planning Summary Livermore Site Office (LSO) More Documents...

187

2010 Annual Planning Summary for Kansas City Site Office (KCSO...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

to be prepared in the next 24 months, and the planned cost and schedule for each NEPA review identified. 2010 Annual Planning Summary for Kansas City Site Office (KCSO) More...

188

2010 Annual Planning Summary for Los Alamos Site Office (LASO...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

to be prepared in the next 24 months, and the planned cost and schedule for each NEPA review identified. 2010 Annual Planning Summary for Los Alamos Site Office (LASO) More...

189

2010 Annual Planning Summary for Richland Operations Office ...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

to be prepared in the next 24 months, and the planned cost and schedule for each NEPA review identified. 2010 Annual Planning Summary for Richland Operations Office (RL) More...

190

2011 Annual Planning Summary for Argonne Site Office (Argonne...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

to be prepared in the next 24 months, and the planned cost and schedule for each NEPA review identified. 2011 Annual Planning Summary for Argonne Site Office (ArSO) More...

191

2011 Annual Planning Summary for Pacific Northwest Site Office...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

to be prepared in the next 24 months, and the planned cost and schedule for each NEPA review identified. 2011 Annual Planning Summary for Pacific Northwest Site Office (PNSO)...

192

2010 Annual Planning Summary for Idaho Operations Office (ID...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

to be prepared in the next 24 months, and the planned cost and schedule for each NEPA review identified. 2010 Annual Planning Summary for Idaho Operations Office (ID) More...

193

2010 Annual Planning Summary for Savannah River Operations Office...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

to be prepared in the next 24 months, and the planned cost and schedule for each NEPA review identified. 2010 Annual Planning Summary for Savannah River Operations Office (SRS)...

194

Alaska Strategic Energy Plan and Planning Handbook | Department...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Alaska Strategic Energy Plan and Planning Handbook Alaska Strategic Energy Plan and Planning Handbook The Alaska Strategic Energy Plan and Planning Handbook, published by the...

195

EMSL: External Peer Reviewers  

NLE Websites -- All DOE Office Websites (Extended Search)

EXTERNAL PEER REVIEWERS EXTERNAL PEER REVIEWERS Additional Information User Portal 2014 Call for Proposals 2014 Proposal Guidance 2014 Proposal Review Criteria Guidance for Letters of Intent to JGI-EMSL Collaborative Science Call Guidance for Full Proposals to JGI-EMSL Collaborative Science Call (Invited Only) 2014 Proposal Planning 2014 Proposal Summary/Extension Previous Calls External Peer Reviewers Fellowships and Awards Nufo, logo External peer reviewers are valuable contributors to EMSL's user proposals process. They provide objective evaluations of the quality of the proposals according to established review criteria, and participate on Review Panels that calibrate the proposals into a ranked order. EMSL is truly grateful to the researchers who donated their time and efforts in fiscal year 2012 to

196

ACQUISITION PLANNING  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Chapter 7.1 (May 2012 second revision) Chapter 7.1 (May 2012 second revision) 2 ACQUISITION PLANNING REFERENCES 1. FAR 4.803(a)(1) Contents of Contract Files 2. FAR 5.405(a) Exchange of Acquisition Information 3. FAR Part 7 Acquisition Planning 4. FAR Part 8 Required Sources of Supply 5. FAR Part 10 Market Research 6. FAR 11.402 Factors to Consider in Establishing Schedules 7. FAR 15.201(c) Exchanges with Industry Before Receipt of Proposals 8. FAR Subpart 16.1 Selecting Contract Types 9. FAR 16.504(c) Indefinite-Quantity Contracts - Multiple Award Preference 10. FAR 17.5 Interagency Acquisitions 11. FAR Subpart 17.6 Management and Operating Contracts 12. FAR Part 19 Small Business Programs Guiding Principles  Sound acquisition planning ensures that the contracting process is

197

ACQUISITION PLANNING  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

January 2011) January 2011) 2 ACQUISITION PLANNING REFERENCES 1. FAR 4.803(a)(1) Contents of Contract Files 2. FAR 5.405(a) Exchange of Acquisition Information 3. FAR Part 7 Acquisition Planning 4. FAR Part 8 Required Sources of Supply 5. FAR Part 10 Market Research 6. FAR 11.402 Factors to Consider in Establishing Schedules 7. FAR 15.201(c) Exchanges with Industry Before Receipt of Proposals 8. FAR Subpart 16.1 Selecting Contract Types 9. FAR 16.504(c) Indefinite-Quantity Contracts - Multiple Award Preference 10. FAR Subpart 17.6 Management and Operating Contracts 11. FAR Part 19 Small Business Programs 12. FAR 25.802(a)(2) Other International Agreements and Coordination Guiding Principles  Sound acquisition planning ensures that the contracting process is

198

ACQUISITION PLANNING  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

OCTOBER 2010) OCTOBER 2010) 2 ACQUISITION PLANNING REFERENCES 1. FAR 4.803(a)(1) Contents of Contract Files 2. FAR 5.405(a) Exchange of Acquisition Information 3. FAR Part 7 Acquisition Planning 4. FAR Part 8 Required Sources of Supply 5. FAR Part 10 Market Research 6. FAR 11.402 Factors to Consider in Establishing Schedules 7. FAR 15.201(c) Exchanges with Industry Before Receipt of Proposals 8. FAR Subpart 16.1 Selecting Contract Types 9. FAR 16.504(c) Indefinite-Quantity Contracts - Multiple Award Preference 10. FAR Subpart 17.6 Management and Operating Contracts 11. FAR Part 19 Small Business Programs 12. FAR 25.802(a)(2) Other International Agreements and Coordination Guiding Principles  Sound acquisition planning ensures that the contracting process is

199

ACQUISITION PLANNING  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

-Chapter 7.1 (May 2012) -Chapter 7.1 (May 2012) 2 ACQUISITION PLANNING REFERENCES 1. FAR 4.803(a)(1) Contents of Contract Files 2. FAR 5.405(a) Exchange of Acquisition Information 3. FAR Part 7 Acquisition Planning 4. FAR Part 8 Required Sources of Supply 5. FAR Part 10 Market Research 6. FAR 11.402 Factors to Consider in Establishing Schedules 7. FAR 15.201(c) Exchanges with Industry Before Receipt of Proposals 8. FAR Subpart 16.1 Selecting Contract Types 9. FAR 16.504(c) Indefinite-Quantity Contracts - Multiple Award Preference 10. FAR 17.5 Interagency Acquisitions 11. FAR Subpart 17.6 Management and Operating Contracts 12. FAR Part 19 Small Business Programs Guiding Principles  Sound acquisition planning ensures that the contracting process is

200

ACQUISITION PLANNING  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

PLANNING PLANNING REFERENCES 1. FAR 4.803(a)(1) Contents of Contract Files 2. FAR 5.405(a) Exchange of Acquisition Information 3. FAR Part 6 Competition Requirements 4. FAR Part 7 Acquisition Planning 5. FAR Part 8 Required Sources of Supply 6. FAR Part 9 Contractor Qualifications 7. FAR Part 10 Market Research 8. FAR Part 11 Describing Agency Needs 9. FAR 15.201(c) Exchanges with Industry Before Receipt of Proposals 10. FAR Subpart 16.1 Selecting Contract Types 11. FAR 16.504(c) Indefinite-Quantity Contracts - Multiple Award Preference 12. FAR 17 Special Contracting Methods 13. FAR Part 19 Small Business Programs 14. FAR 25.802(a)(2) Other International Agreements and Coordination 15. FAR 34.004 Acquisition Strategy

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


201

Comprehensive facilities plan  

Science Conference Proceedings (OSTI)

The Ernest Orlando Lawrence Berkeley National Laboratory`s Comprehensive Facilities Plan (CFP) document provides analysis and policy guidance for the effective use and orderly future development of land and capital assets at the Berkeley Lab site. The CFP directly supports Berkeley Lab`s role as a multiprogram national laboratory operated by the University of California (UC) for the Department of Energy (DOE). The CFP is revised annually on Berkeley Lab`s Facilities Planning Website. Major revisions are consistent with DOE policy and review guidance. Facilities planing is motivated by the need to develop facilities for DOE programmatic needs; to maintain, replace and rehabilitate existing obsolete facilities; to identify sites for anticipated programmatic growth; and to establish a planning framework in recognition of site amenities and the surrounding community. The CFP presents a concise expression of the policy for the future physical development of the Laboratory, based upon anticipated operational needs of research programs and the environmental setting. It is a product of the ongoing planning processes and is a dynamic information source.

NONE

1997-09-01T23:59:59.000Z

202

Long-term Planning and Investment for Transmission and Generation...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

and generating capacity. Long-term Planning and Investment for Transmission and Generation More Documents & Publications 2012 Reliability & Markets Peer Review -...

203

Audit of Groundwater Remediation Plans at Savannah River, ER...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Ombudsman FOIA Reports Calendar Year Reports Recovery Act Peer Reviews DOE Directives Performance Strategic Plan Testimony Financial Statements Semiannual Reports Work...

204

PROJECT MANGEMENT PLAN EXAMPLES  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

End Point Closeout Examples Example 77 7.5 Endpoint Closure The endpoint documents have grouped the building spaces and systems into a number of manageable areas. The areas are closely related to the engineering work plans that guide completion of many of the endpoints. Endpoint closure methods and practices are provided in the attachment of this PMP. On completion of an endpoint, a BWHC field representative will initial complete on the field copy of the endpoint document. A BHI field representative will verify acceptable completion of the applicable activity. Verification may be performed by reviewing documents, letters, photos, work packages, or work plans, or by visual inspection. When all the endpoints for a specific area of the building have been completed and verified, designated BWHC and BHI management will sign for completion and acceptance of that

205

Mitigation Action Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

212 212 Mitigation Action Plan for the Lease of Land for the Development of a Research Park at Los Alamos National Laboratory Departme~t of Energy Albuquerque Operations Office Los Alamos Area Office Los Alamos, New Mexico MITIGATION ACTION PLAN for the LEASE OF LAND FOR THE DEVELOPMENT OF A RESEARCH PARK AT LOS ALAMOS NATIONAL LABORATORY Background on the Lease of Land at Los Alamos National Laboratory: The U. S. Department of Energy (DOE) has approved an Environmental Assessment (EA) on the Lease of Land for the Development of a Research Park at Los Alamos National Laboratory (LANL)(DOE/EA-1212), Los Alamos, New Mexico. The DOE released a Predecisional Draft of this EA for State and Tribal review and made the draft document available to the public on July 24, 1997 for

206

Rail Planning Timeline  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Planning Timeline: By Responsible Party Planning Timeline: By Responsible Party Rev. 4.0, November 2006 Timeframe Offeror/Agent FRA Railroad(s) Other Post Shipment * DOE conducts Lessons Learned Review. During Shipment(s) * The offeror (shipper) will ensure that the appropriate FRA point of contact is notified of any changes 1 in the transportation schedule upon confirmation of the change (modification of SCOP OI-4). * DOE will notify the state Governors or designees and designated tribal points of contact by telephone in the event of schedule changes greater than six hours (DOE Manual 8.2.1). * In the event of a substantial unanticipated delay en route (e.g., greater than 2 hours), the affected states and tribes will be notified of the event by TRANSCOM. 2 TRANSCOM will notify the affected states and tribes

207

RHIC STATUS AND PLANS.  

Science Conference Proceedings (OSTI)

RHIC ended successfully its second year of operation in January 2002 after a six month run with gold ions and two months of polarized proton collisions. I will review the machine performance and accomplishments, that include reaching design energy (100 GeV/u) and design luminosity during the gold run, and the first high energy (100 GeV) polarized proton collisions. I will also discuss the machine development strategy and the main performance milestones. The goals and plans for the shutdown and the nest run, scheduled to start in November 2002 have been the focus of a RHIC Retreat in March 2002. I will summarize findings and plans for the upcoming run and outline a vision for the nest few years of RHIC operation and upgrades.

PILAT,R.

2002-06-02T23:59:59.000Z

208

Checkout, Testing, and Commissioning Plan RM  

Energy.gov (U.S. Department of Energy (DOE))

The CP RM Module is a tool that assists DOE federal project review teams in evaluating the sufficiency of the Commissioning Plan and its implementation. The CP RM can be used by the DOE federal...

209

SCIENCE AND IMPLEMENTATION PLAN Introduction  

E-Print Network (OSTI)

SCIENCE AND IMPLEMENTATION PLAN Introduction The cross-cutting review of science and research undertaken by the Government in 2000 identified e-Science as one of three priority research areas, allocating the new industries of the future. The Science Budget defines e-Science as 'science increasingly done

Brierley, Andrew

210

Summary - System Planning for Low-Activity Waste Treatment at...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

(DOE-EM) External Technical Review of System Planning for Low-Activity Waste Treatment at Hanford Why DOE-EM Did This Review Construction of the facilities of the Hanford site's...

211

Master Plan Review Team August 29, 2002  

E-Print Network (OSTI)

-generation students · Enrollment of, retention rates for, and degrees awarded to Pell Grant recipients · Enrollment% of resident undergraduates (fall 2009) · Enrollment of undergraduate Pell Grant recipients: 20% of resident of undergraduate first-generation students: 37% of undergraduates (fall 2009) · Enrollment of undergraduate Pell

Rhode Island, University of

212

PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

System Closure Plan Examples System Closure Plan Examples Example 61 7.5 Endpoint Closure The endpoint documents have grouped the building spaces and systems into a number of manageable areas. The areas are closely related to the engineering work plans that guide completion of many of the endpoints. Endpoint closure methods and practices are provided in the attachment of this PMP. On completion of an endpoint, a BWHC field representative will initial complete on the field copy of the endpoint document. A BHI field representative will verify acceptable completion of the applicable activity. Verification may be performed by reviewing documents, letters, photos, work packages, or work plans, or by visual inspection. When all the endpoints for a specific area of the building have been completed and verified, designated BWHC and BHI management will sign for completion and acceptance of that

213

Draft of the PHENIX Management Plan  

SciTech Connect

The PHENIX Management Plan provides the baselines and controls that the PHENIX and RHIC Projects will follow to meet the technical, cost, and schedule goals for the PHENIX detector at RHIC. This plan will be reviewed and updated as required, with revisions made by agreement among the signed participants.

Not Available

1994-03-10T23:59:59.000Z

214

INDEPENDENT TECHNICAL REVIEW OF THE FOCUSED FEASIBILITY STUDY AND PROPOSED PLAN FOR DESIGNATED SOLID WASTE MANAGEMENT UNITS CONTRIBUTING TO THE SOUTHWEST GROUNDWATER PLUME AT THE PADUCAH GASEOUS DIFFUSION PLANT  

SciTech Connect

The U. S. Department of Energy (DOE) is currently developing a Proposed Plan (PP) for remediation of designated sources of chlorinated solvents that contribute contamination to the Southwest (SW) Groundwater Plume at the Paducah Gaseous Diffusion Plant (PGDP), in Paducah, KY. The principal contaminants in the SW Plume are trichloroethene (TCE) and other volatile organic compounds (VOCs); these industrial solvents were used and disposed in various facilities and locations at PGDP. In the SW plume area, residual TCE sources are primarily in the fine-grained sediments of the Upper Continental Recharge System (UCRS), a partially saturated zone that delivers contaminants downward into the coarse-grained Regional Gravel Aquifer (RGA). The RGA serves as the significant lateral groundwater transport pathway for the plume. In the SW Plume area, the four main contributing TCE source units are: (1) Solid Waste Management Unit (SWMU) 1 / Oil Landfarm; (2) C-720 Building TCE Northeast Spill Site (SWMU 211A); (3) C-720 Building TCE Southeast Spill Site (SWMU 211B); and (4) C-747 Contaminated Burial Yard (SWMU 4). The PP presents the Preferred Alternatives for remediation of VOCs in the UCRS at the Oil Landfarm and the C-720 Building spill sites. The basis for the PP is documented in a Focused Feasibility Study (FFS) (DOE, 2011) and a Site Investigation Report (SI) (DOE, 2007). The SW plume is currently within the boundaries of PGDP (i.e., does not extend off-site). Nonetheless, reasonable mitigation of the multiple contaminant sources contributing to the SW plume is one of the necessary components identified in the PGDP End State Vision (DOE, 2005). Because of the importance of the proposed actions DOE assembled an Independent Technical Review (ITR) team to provide input and assistance in finalizing the PP.

Looney, B.; Eddy-Dilek, C.; Amidon, M.; Rossabi, J.; Stewart, L.

2011-05-31T23:59:59.000Z

215

Energy planning and management plan  

Science Conference Proceedings (OSTI)

This paper contains printed copies of 60FR 53181, October 12, 1995 and 60 FR 54151. This is a record of decision concerning the Western Area Power Administration`s final draft and environmental impact statement, and Energy Planning and Management Program.

NONE

1996-01-01T23:59:59.000Z

216

ACQUISITION PLANNING  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

7.1 (May 2010) 7.1 (May 2010) 1 ACQUISITION PLANNING REFERENCES 1. FAR 4.803(a)(1) Contents of Contract Files 2. FAR 5.405(a) Exchange of Acquisition Information 3. FAR Part 7 Acquisition Planning 4. FAR Part 8 Required Sources of Supply 5. FAR Part 10 Market Research 6. FAR 11.402 Factors to Consider in Establishing Schedules 7. FAR 15.201(c) Exchanges with Industry Before Receipt of Proposals 8. FAR Subpart 16.1 Selecting Contract Types 9. FAR 16.504(c) Indefinite-Quantity Contracts - Multiple Award Preference 10. FAR Subpart 17.6 Management and Operating Contracts 11. FAR Part 19 Small Business Programs 12. FAR 25.802(a)(2) Other International Agreements and Coordination 13. FAR 34.004 Acquisition Strategy Guiding Principles

217

ACQUISITION PLANNING  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

--Chapter 7.1 (JUNE 2010) --Chapter 7.1 (JUNE 2010) 2 ACQUISITION PLANNING REFERENCES 1. FAR 4.803(a)(1) Contents of Contract Files 2. FAR 5.405(a) Exchange of Acquisition Information 3. FAR Part 7 Acquisition Planning 4. FAR Part 8 Required Sources of Supply 5. FAR Part 10 Market Research 6. FAR 11.402 Factors to Consider in Establishing Schedules 7. FAR 15.201(c) Exchanges with Industry Before Receipt of Proposals 8. FAR Subpart 16.1 Selecting Contract Types 9. FAR 16.504(c) Indefinite-Quantity Contracts - Multiple Award Preference 10. FAR Subpart 17.6 Management and Operating Contracts 11. FAR Part 19 Small Business Programs 12. FAR 25.802(a)(2) Other International Agreements and Coordination Guiding Principles

218

Plan Descriptions & Summaries  

NLE Websites -- All DOE Office Websites (Extended Search)

Plan Descriptions & Summaries Retiree Insurance Plans Retiree health and welfare benefits are managed by AonHewitt and Associates. Contact Retiree Insurance Providers Plan...

219

Construction Readiness RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Construction Readiness Review Module Construction Readiness Review Module March 2010 CD- [This Rev Readiness -0 view Module w s Review (CRR OFFICE O CD-1 was used to dev R). This Review OF ENVIRO Standard R Construc Rev Critical D CD-2 M velop the Revie w Module cont ONMENTA Review Pla ction Rea view Modul Decision (CD C March 2010 ew Plan for Sal tains the lesson Review.] AL MANAG an (SRP) adiness le D) Applicabili D-3 lt Waste Proce ns learned from GEMENT ity CD-4 ssing Facility ( m the SWPF Co Post Ope (SWPF) Const onstruction Re eration truction eadiness Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental

220

Final Design RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Final Design Review Module Final Design Review Module March 2010 CD-0 [This Rev Design Re O 0 view Module w eview of the OR OFFICE OF C CD-1 was used to dev R U 233 Dispo F ENVIRO Standard R Fin Rev Critical Decis CD-2 M velop the Revie osition Project ONMENTAL Review Plan al Design view Module sion (CD) Ap CD March 2010 ew Plan for 90% in 2009. Lesso Module.] L MANAGE n (SRP) n e pplicability D-3 % Design Revi ons learned hav EMENT CD-4 iew of SWPF i ve been incorpo Post Ope in 2008 and for orated in the R eration r 60% Review Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively.

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


221

CRAD, Federal Assurance Capability Plan - February 11, 2009 | Department of  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Federal Assurance Capability Plan - February 11, 2009 Federal Assurance Capability Plan - February 11, 2009 CRAD, Federal Assurance Capability Plan - February 11, 2009 February 11, 2009 Federal Assurance Capability Plan Inspection Criteria and Approach, DNFSB 2004-1, Commitment 16 (HSS CRAD 64-40, Rev. 0) Federal Assurance Capability Review Plan provides a plan, including criteria, approaches, and the lines of inquiry, to be used for assessing the effectiveness of areas relating to the establishment of a robust Federal assurance capability. The review plan covers all areas in Section 5.1 of the DOE Implementation Plan (IP) except for Section 5.1.3, Instituting a Nuclear Safety Research Function. CRAD, Federal Assurance Capability Plan - February 11, 2009 More Documents & Publications CRAD, Operating Experience - February 11, 2009

222

Book Reviews Book Reviews*  

E-Print Network (OSTI)

Book Reviews Book Reviews* J. Am. Chem. SOC.,Vol. 108, No. 17, 1986 5313 Handbook of Gaussian Basis + 556 pp. $85.00. This book is a collection of chapters authored by individuals or groups experienced. The present book, dealing with the latter topic, is one of the only extensive intro- ductions of which I am

Pines, Alexander

223

Alaska Strategic Energy Plan and Planning Handbook  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Alaska Strategic Energy Plan and Planning Handbook A. Dane and L. Doris National Renewable Energy Laboratory U.S. Department of Energy | Office of Indian Energy 1000 Independence...

224

Book reviews  

Science Conference Proceedings (OSTI)

If you are interested in reviewing books for intelligence, please contact book review editor Karen Sutherland at intelligence_book-reviews@acm.org.

Karen Sutherland

2001-12-01T23:59:59.000Z

225

Paying Upfront: A Review of Salt River Project's M-Power Prepaid Program  

Science Conference Proceedings (OSTI)

Arizonas Salt River Project (SRP) has operated M-Power, the largest electricity prepayment program in the United States, since 1993. The customer population has grown to about 100,000 (approximately 12% of all residences served by SRP), and it has expanded from the initial target populationconsumers with arrears facing service terminations and low-income customersto include consumers with different expectations from M-Power service. The in-home portion of the SRP prepay configuration consists of a user d...

2010-10-12T23:59:59.000Z

226

PAE Evaluation Portfolio Peer Review  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Report from the Peer Review Panel Report from the Peer Review Panel on activities within the Planning, Analysis and Evaluation Unit Office of Planning, Budget and Analysis Office of Energy Efficiency and Renewable Energy U.S. Department of Energy Team Members: Kathryn Newcomer, The George Washington University (Chair) Irwin Feller, The Pennsylvania State University (Retired) Stephanie Shipman, Government Accountability Office Kathleen Sedlak O'Brien, Environmental Protection Agency Faith Lambert, EERE Final Report February 1, 2008 1 EXECUTIVE SUMMARY The Office of Energy Efficiency and Renewable Energy (EERE) within the U.S. Department of Energy asked a panel of experts with relevant knowledge to review the evaluation activities of the Planning, Analysis and Evaluation Unit (PAE) within EERE's Office of Planning, Budget and

227

Energy Department Infrastructure Improvement Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Energy Department Infrastructure Improvement Plan Energy Department Infrastructure Improvement Plan Energy Department Infrastructure Improvement Plan AGENCY PLAN FOR IMPROVING PERFORMANCE OF FEDERAL PERMITTING AND REVIEW OF INFRASTRUCTURE PROJECTS On March 22, 2012, the President issued Executive Order 13604 (EO), which is intended to improve the performance of Federal agencies in the permitting and review of infrastructure projects. Among its many objectives, the EO describes the President's government-wide initiative to modernize Federal permitting and review processes to achieve better projects, improve environmental and community outcomes, and shorten decision-making and review timelines for infrastructure projects. This Department of Energy (DOE) Agency Plan describes DOE's efforts to implement the Federal Plan, including DOE-specific strategies and actions

228

Integrated Project Team RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Integrated Project Team (IPT) Review Module Integrated Project Team (IPT) Review Module March 2010 CD-0 This R O 0 Review Modul OFFICE OF Inte C CD-1 le was piloted F ENVIRO Standard R grated P Rev Critical Decis CD-2 M at the OR U 23 incorporated ONMENTAL Review Plan Project Te view Module sion (CD) Ap CD March 2010 33 Disposition in the Review L MANAGE n (SRP) eam (IPT e pplicability D-3 Project in 200 Module. EMENT T) CD-4 09. Lessons lea Post Ope arned have been eration n Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM

229

Safety Design Strategy RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Safety Design Strategy Review Module Safety Design Strategy Review Module March 2010 OFFICE OF ENVIRONMENTAL MANAGEMENT Standard Review Plan (SRP) Safety Design Strategy (SDS) Review Module Critical Decision (CD) Applicability CD-0 CD-1 CD-2 CD-3 CD-4 Post Operation March 2010 Standard Review Plan, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-1189-2008,

230

1997 Operating plan for the Office of International Health Programs  

Science Conference Proceedings (OSTI)

One year ago, the Office of International Health Programs provided you with our 1996 Operating Plan, which defined our ideas and ideals for conducting business in 1996. We have again this year undertaken an intensive planning effort, first reviewing our accomplishments and shortcomings during 1996, and then developing plans and priorities for the upcoming year, taking into account input from customers and outside review panels, and ensuring that the demands on the office have been balanced with anticipated human, financial, and material resources.

NONE

1996-11-01T23:59:59.000Z

231

Related Links on Energy Planning | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Planning Planning Related Links on Energy Planning Below are related links to energy planning resources. EPA State and Local Climate and Energy Program Access information on technical assistance, analytical tools, and outreach support available for state, local, and tribal governments through the EPA State and Local Climate and Energy Program. View case studies of state and local projects and see examples of greenhouse gas inventories and climate action plans. Local Energy Planning in Practice: A Review of Recent Experiences This American Council for an Energy Efficient Economy (ACEEE) research report reviews the energy-related plans in 30 U.S. locations. The report summarizes progress made in planning processes and choices made by community leaders, and identifies both advantages and difficulties

232

Waste Minimization and Pollution Prevention Awareness Plan  

SciTech Connect

The purpose of this plan is to document Lawrence Livermore National Laboratory (LLNL) projections for present and future waste minimization and pollution prevention. The plan specifies those activities and methods that are or will be used to reduce the quantity and toxicity of wastes generated at the site. It is intended to satisfy Department of Energy (DOE) requirements. This Plan provides an overview of projected activities from FY 1994 through FY 1999. The plans are broken into site-wide and problem-specific activities. All directorates at LLNL have had an opportunity to contribute input, to estimate budget, and to review the plan. In addition to the above, this plan records LLNL`s goals for pollution prevention, regulatory drivers for those activities, assumptions on which the cost estimates are based, analyses of the strengths of the projects, and the barriers to increasing pollution prevention activities.

Not Available

1994-04-01T23:59:59.000Z

233

Preliminary Safety Design RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Preliminary Safety Design Review Module Preliminary Safety Design Review Module March 2010 CD-0 O 0 OFFICE OF Pr C CD-1 F ENVIRO Standard R reliminar Rev Critical Decis CD-2 M ONMENTAL Review Plan ry Safety view Module sion (CD) Ap CD March 2010 L MANAGE n (SRP) y Design e pplicability D-3 EMENT CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-1189-2008,

234

Facility Disposition Safety Strategy RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Facility Disposition Safety Strategy Review Module Facility Disposition Safety Strategy Review Module March 2010 CD-0 O 0 OFFICE OF Facilit C CD-1 F ENVIRO Standard R ty Dispos Rev Critical Decis CD-2 M ONMENTAL Review Plan sition Saf view Module sion (CD) Ap CD March 2010 L MANAGE n (SRP) fety Strat e pplicability D-3 EMENT tegy CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-1189-2008,

235

Earned Value Management System RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Earned Value Management System Review Module Earned Value Management System Review Module March 2010 CD-0 O Ea 0 OFFICE OF arned Va C CD-1 F ENVIRO Standard R alue Man Rev Critical Decis CD-2 M ONMENTAL Review Plan agement view Module sion (CD) Ap CD March 2010 L MANAGE n (SRP) t System e pplicability D-3 EMENT (EVMS) CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-1189-2008,

236

Facility Software Quality Assurance for Capital Project Decisions RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Facility Software Quality Assurance (SQA) for Facility Software Quality Assurance (SQA) for Capital Project Critical Decisions Review Module March 2010 OFFICE OF ENVIRONMENTAL MANAGEMENT Standard Review Plan (SRP) Facility Software Quality Assurance (SQA) for Capital Project Critical Decisions Review Module Critical Decision (CD) Applicability CD-0 CD-1 CD-2 CD-3 CD-4 Post Operation March 2010 Standard Review Plan, 2 nd Edition, March 2010 FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1,

237

Seismic Design Expectations Report  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Seismic Design Expectations Report Seismic Design Expectations Report March 2010 CD- This Rev of th Se -0 view Module w he overall Cons OFFICE O eismic De C CD-1 was used to dev struction Projec inco OF ENVIRO Standard esign Exp Critical Deci CD-2 M velop the Revie ct Review cond orporated in the ONMENTA Review Pla pectation ision (CD) A C March 2010 ew Plan for the ducted in 2009 e current versio AL MANAG an (SRP) ns Report Applicability D-3 e Oak Ridge Bl 9. Lessons lear on of the Modu GEMENT t (SDER) CD-4 ldg. 3019 60% rned from this r ule. ) Post Ope design review review have be eration w as part een Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental

238

Conceptual Safety Design RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Conceptual Safety Design Review Module Conceptual Safety Design Review Module March 2010 CD-0 O 0 OFFICE OF C C CD-1 F ENVIRO Standard R Conceptua Rev Critical Decis CD-2 M ONMENTAL Review Plan al Safety view Module sion (CD) Ap CD March 2010 L MANAGE n (SRP) y Design e pplicability D-3 EMENT CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital

239

Conceptual Design RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Conceptual Design Review Module Conceptual Design Review Module March 2010 CD-0 O 0 OFFICE OF C CD-1 F ENVIRO Standard R Concep Rev Critical Decis CD-2 M ONMENTAL Review Plan ptual De view Module sion (CD) Ap CD March 2010 L MANAGE n (SRP) sign e pplicability D-3 EMENT CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-1189-2008,

240

Acquisition Strategy RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Acquisition Strategy Review Module Acquisition Strategy Review Module March 2010 CD-0 O 0 OFFICE OF C CD-1 F ENVIRO Standard R Acquisi Rev Critical Decis CD-2 M ONMENTAL Review Plan ition Stra view Module sion (CD) Ap CD March 2010 L MANAGE n (SRP) ategy e pplicability D-3 EMENT CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets,

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


241

Risk Management RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Risk Management Review Module Risk Management Review Module March 2010 CD-0 O 0 OFFICE OF C CD-1 F ENVIRO Standard R Risk M Rev Critical Decis CD-2 M ONMENTAL Review Plan Managem view Module sion (CD) Ap CD March 2010 L MANAGE (SRP) ment e pplicability D-3 EMENT CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-1189-2008, Integration of Safety into the Design Process, and EM's internal

242

Prelminary Design RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Preliminary Design Review Module Preliminary Design Review Module March 2010 CD-0 O 0 OFFICE OF C CD-1 F ENVIRO Standard R Prelim Rev Critical Decis CD-2 M ONMENTAL Review Plan inary De view Module sion (CD) Ap CD March 2010 L MANAGE n (SRP) esign e pplicability D-3 EMENT CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-1189-2008,

243

PROJECT MANAGEMENT PLANS Project Management Plans  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

MANAGEMENT PLANS MANAGEMENT PLANS Project Management Plans  Overview  Project Management Plan Suggested Outline Subjects  Crosswalk between the Suggested PMP Outline Subjects and a Listing of Project Planning Elements  Elements of Deactivation Project Planning  Examples From Project Management Plans Overview The purpose here is to assist project managers and project planners in creating a project plan by providing examples and pointing to information that have been successfully used by others in the past. Section 4.2 of DOE Guide 430.1-3, DEACTIVATION IMPLEMENTATION GUIDE discusses the content and purpose of deactivation project management plans. It is presented as a suggested outline followed by other potential subjects. For the convenience of readers, that information is repeated below.

244

Review/Verify Strategic Skills Needs/Forecasts/Future Mission...  

NLE Websites -- All DOE Office Websites (Extended Search)

ReviewVerify Strategic Skills NeedsForecastsFuture Mission Shifts Annual Lab Plan (1-10 yrs) Fermilab Strategic Agenda (2-5 yrs) Sector program Execution Plans (1-3...

245

Biomass fuels: a national plan  

SciTech Connect

The options and potentials of biomass fuel production for the U.S. are reviewed. The following options are discussed: plant or vegetable oils, direct combustion of wood, production of biogas, and alcohol fuels. It is considered essential that a national planning model is developed to integrate the biofuel requirements for arable land and commercial forests with those for food and other traditional uses. (Refs. 32)

Mitchell, T.E.; Schroer, B.J.; Ziemke, M.C.; Peters, J.F.

1983-04-01T23:59:59.000Z

246

Water Power Program: Program Plans, Implementation, and Results  

NLE Websites -- All DOE Office Websites (Extended Search)

Water Power Program Water Power Program HOME ABOUT RESEARCH & DEVELOPMENT FINANCIAL OPPORTUNITIES INFORMATION RESOURCES NEWS EVENTS EERE » Water Power Program » About Key Activities Plans, Implementation, & Results Budget Peer Review 2011 Contacts Plans, Implementation, and Results Here you'll find an overview of the Water Power Program and links to its program planning, implementation, and results documents. This list summarizes the program's water power research, development, and demonstration activities. Read more about: Overview Learn more about this EERE Office. Plans Discover the plans, budgets, and analyses that set the direction of office priorities and activities. Implementation Find out how the office controls, implements, and adjusts its plans and manages its activities.

247

Water Power Program: Program Plans, Implementation, and Results  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Water Power Program Water Power Program HOME ABOUT RESEARCH & DEVELOPMENT FINANCIAL OPPORTUNITIES INFORMATION RESOURCES NEWS EVENTS EERE » Water Power Program » About Key Activities Plans, Implementation, & Results Budget Peer Review 2011 Contacts Plans, Implementation, and Results Here you'll find an overview of the Water Power Program and links to its program planning, implementation, and results documents. This list summarizes the program's water power research, development, and demonstration activities. Read more about: Overview Learn more about this EERE Office. Plans Discover the plans, budgets, and analyses that set the direction of office priorities and activities. Implementation Find out how the office controls, implements, and adjusts its plans and manages its activities.

248

Employment Opportunities (Consultant) Program Review Lead  

E-Print Network (OSTI)

. Working with the Program Manager, the Program Review Lead will facilitate discussions with an advisory group and will work with instructors and other subject matter experts to complete the program review of the program review process; working with instructors to develop learning plans and advising on instructional

Hitchcock, Adam P.

249

Hanford Site Development Plan  

SciTech Connect

The Hanford Site Development Plan (Site Development Plan) is intended to guide the short- and long-range development and use of the Hanford Site. All acquisition, development, and permanent facility use at the Hanford Site will conform to the approved plan. The Site Development Plan also serves as the base document for all subsequent studies that involve use of facilities at the Site. This revision is an update of a previous plan. The executive summary presents the highlights of the five major topics covered in the Site Development Plan: general site information, existing conditions, planning analysis, Master Plan, and Five-Year Plan. 56 refs., 67 figs., 31 tabs.

Rinne, C.A.; Curry, R.H.; Hagan, J.W.; Seiler, S.W.; Sommer, D.J. (Westinghouse Hanford Co., Richland, WA (USA)); Yancey, E.F. (Pacific Northwest Lab., Richland, WA (USA))

1990-01-01T23:59:59.000Z

250

A reservoir management plan  

DOE Green Energy (OSTI)

There are numerous documented cases of extraction of fluids from the ground causing surface subsidence. The cases include groundwater, oil and gas, as well as geothermal fluid withdrawal. A recent comprehensive review of all types of man-induced land subsidence was published by the Geological Survey of America. At the early stages of a geothermal power development project it is standard practice in most countries for an environmental impact report to be required. The possibility of geothermal subsidence has to be addressed, and usually it falls on the geophysicists and/or geologists to make some predictions. The advice given is vital for planning the power plant location and the borefield pipe and drain layout. It is not so much the vertical settlement that occurs with subsidence but the accompanying horizontal ground strains that can do the most damage to any man-made structure.

Allis, R.G.

1989-06-16T23:59:59.000Z

251

STRATEGIC PLANNING  

E-Print Network (OSTI)

The National Academy of Public Administration is an independent, nonprofit organization chartered by Congress to improve governance at all levelslocal, regional, state, national, and international. The Academys membership of more than 550 Fellows includes current and former members of Congress, cabinet-level appointees, senior federal executives, state and local practitioners, businesspeople, nonprofit leaders, and scholars with distinguished records in public management. Since its establishment in 1967, the Academy has assisted hundreds of federal agencies, congressional committees, state and local governments, civic organizations, and institutions overseas through problemsolving, research, analysis, information sharing, developing strategies for change, and connecting people and ideas. Most reports and papers issued by Academy panels respond to specific requests and needs of public agencies. Projects also address governmentwide and broader societal topics identified by the Academy. In addition to government institutions, the Academy is also supported by businesses, foundations, and nonprofit organizations. A Final Report by a Panel of the NATIONAL ACADEMY OF PUBLIC ADMINISTRATION for the Office of Strategic Planning

Hale Champion; Mary Jane England; Harry Hatry

2001-01-01T23:59:59.000Z

252

Readiness Review Program  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Review Program Review Program FUNCTIONAL AREA GOAL: DOE/NNSA Headquarters and Field organizations and their contractors responsible for the startup and operation of nuclear facilities have defined and implemented contractual requirements to manage, evaluate, and approve the startup and restart of nuclear facilities and activities. REQUIREMENTS:  DOE Order 425.1C, Startup and Restart of Nuclear Facilities  DOE P 450.4, Safety Management System Policy  DOE/NNSA Safety Management Functions, Responsibilities and Authorities Manual Guidance:  DOE-STD-3006-2000, Planning and Conduct of Operational Readiness Reviews  DOE-HDBK- 3012-2003, Operational Readiness Review Team Leaders Handbook  DOE G 450.4-1B, Integrated Safety Management System Guide

253

LANS DB PENSION PLAN  

NLE Websites -- All DOE Office Websites (Extended Search)

December 2010 December 2010 u:\my documents\pension plan\revised tcp1 db plan spd dec 2010.doc LANS Defined Benefit Pension Plan Summary Plan Description This Summary Plan Description (SPD) is intended to provide a summary of the principal features of the LANS Defined Benefit Pension Plan ("Plan") and is not meant to interpret, extend or change the Plan in any way. This SPD will continue to be updated. Please check back on a regular basis for the most recent version. Nothing in the Plan and/or this SPD shall be construed as giving any member the right to be retained in service with LANS or any affiliated company, or as a guarantee of any rights or benefits under the Plan. LANS, in its sole discretion, reserves the right to amend the SPD or Plan, or to terminate the Plan, at any time.

254

ENERGY EMERGENCY RESPONSE PLAN  

E-Print Network (OSTI)

CALIFORNIA ENERGY COMMISSION ENERGY EMERGENCY RESPONSE PLAN COMMISSIONREPORT October 2006 CEC-600 Deputy Director FUELS AND TRANSPORTATION DIVISION #12;The Energy Emergency Response Plan is prepared, safety, and welfare. #12;ACKNOWLEDGEMENTS The Energy Emergency Response Plan was prepared from

255

Readiness Assessment Plan, Hanford 200 areas treated effluent disposal facilities  

SciTech Connect

This Readiness Assessment Plan documents Liquid Effluent Facilities review process used to establish the scope of review, documentation requirements, performance assessment, and plant readiness to begin operation of the Treated Effluent Disposal system in accordance with DOE-RLID-5480.31, Startup and Restart of Facilities Operational Readiness Review and Readiness Assessments.

Ulmer, F.J.

1995-02-06T23:59:59.000Z

256

CHEMICAL HYGIENE PLAN HAZARD COMMUNICATION PLAN  

E-Print Network (OSTI)

CHEMICAL HYGIENE PLAN AND HAZARD COMMUNICATION PLAN Occupational Exposures to Hazardous Chemicals Safety 2723 Environmental Health/Safety Chemical Hygiene Officer Radiation Safety Officer Biological (Accident Reports) 2204 Bioengineering 2965 #12;TABLE OF CONTENTS CHEMICAL HYGIENE PLAN (CHP) (4/2007) 1

Oliver, Douglas L.

257

CHEMICAL HYGIENE PLAN HAZARD COMMUNICATION PLAN  

E-Print Network (OSTI)

CHEMICAL HYGIENE PLAN AND HAZARD COMMUNICATION PLAN Occupational Exposures to Hazardous Chemicals and Safety Numbers Research Safety 2723 Environmental Health/Safety Chemical Hygiene Officer Radiation Safety Human Resources (Accident Reports) 4589 Bioengineering 2965 #12;TABLE OF CONTENTS CHEMICAL HYGIENE PLAN

Kim, Duck O.

258

Independent Oversight Review of Nevada Site Office Criticality...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Safety CEF Criticality Experiments Facility CRAD Criteria and Review Approach Documents CSP Criticality Safety Plan DAF Device Assembly Facility DOE Department of Energy DSA...

259

NEPA and CEQA: Integrating State and Federal Environmental Reviews...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Governor's Office of Planning and Research, issued on March 5, 2013, a draft handbook on integrating NEPA and California Environmental Quality Act (CEQA) review processes....

260

Book Review  

E-Print Network (OSTI)

Book Review: Bridging: How Gloria Anzalduas Life and Workoverlapping identities, the book is comprised of fiveand again (203). Fowler| Book Review: Bridging: How Gloria

Fowler, Rebecca

2013-01-01T23:59:59.000Z

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


261

Waste Management Quality Assurance Plan  

SciTech Connect

Lawrence Berkeley Laboratory`s Environment Department addresses its responsibilities through activities in a variety of areas. The need for a comprehensive management control system for these activities has been identified by the Department of Energy (DOE). The WM QA (Waste Management Quality Assurance) Plan is an integral part of a management system that provides controls necessary to ensure that the department`s activities are planned, performed, documented, and verified. This WM QA Plan defines the requirements of the WM QA program. These requirements are derived from DOE Order 5700.6C, Quality Assurance, the LBL Operating and Assurance Program Plan (OAP, LBL PUB-3111), and other environmental compliance documents applicable to WM activities. The requirements presented herein, as well as the procedures and methodologies that direct the implementation of these requirements, will undergo review and revisions as necessary. The provisions of this QA Plan and its implementing documents apply to quality-affecting activities performed by and for WM. It is also applicable to WM contractors, vendors, and other LBL organizations associated with WM activities, except where such contractors, vendors, or organizations are governed by their own WM-approved QA programs. References used in the preparation of this document are (1) ASME NQA-1-1989, (2) ANSI/ASQC E4 (Draft), (3) Waste Management Quality Assurance Implementing Management Plan (LBL PUB-5352, Rev. 1), (4) LBL Operating and Assurance Program Plan (OAP), LBL PUB-3111, 2/3/93. A list of terms and definitions used throughout this document is included as Appendix A.

Not Available

1993-11-30T23:59:59.000Z

262

Science Review Review Definitions  

NLE Websites -- All DOE Office Websites (Extended Search)

IPTS Proposal Review Ratings IPTS Proposal Review Ratings 5 Extraordinary The proposal involves cutting-edge research of great scientific importance. Proposed research will significantly advance knowledge in a specific field or scientific discipline. The characteristics of the SNS and/or HFIR are essential to the success of the proposed work. I believe this proposal must be supported with the highest priority. 4.5 Excellent to Extraordinary -- 4 Excellent The proposed research is of high quality and has potential for making an important contribution to a specific field or scientific discipline. The work is innovative and is likely to be published in a leading scientific journal. The use of SNS and/or HFIR is highly desirable for the success of the proposed work. I strongly recommend that this proposal

263

Integrated Planning and Performance Management  

NLE Websites -- All DOE Office Websites (Extended Search)

DOESC Scientific Facilities Strategic Plan (20 years, major capital projects) * DOE Strategic Plan (7-10 years) * DOE (HEP)Fermilab Strategic Plan (10 years) * FRAFNAL Plan for...

264

Facility Representative Program: Criteria Review and Approach Document  

NLE Websites -- All DOE Office Websites (Extended Search)

Assessment Tools Assessment Tools Surveillance Guides Manager's Guide for Safety and Health Walkthroughs Criteria Review and Approach Document This page provides Criteria Review and Approach Documents (CRADS) to assist Facility Representatives. Please submit your CRADS for posting by sending them to the HQ FR Program Manager. Please include the subject, date, and a contact person. Communications NASA Benchmarks Communications Assessment Plan Configuration Management Configuration Management Assessment Plan Confined Space Confined Spaces Assessment Plan Conduct of Operations Conduct of Operations Assessment Plan Electrical Assessment Electrical Safety Assessment Plan Facility Procedures Verification and Validation of Facility Procedures Assessment Plan Hoisting and Rigging

265

NEHRP - Final Plan Development  

Science Conference Proceedings (OSTI)

... However, NEHRP funds do not support targeted ... FEMA does provide linkage of ongoing work in ... Plan discussion about Strategic Planning Principles ...

266

NSLS Work Planning & Controls  

NLE Websites -- All DOE Office Websites (Extended Search)

Work Planning & Controls NSLS Work Planning and Control Procedure Lead Working Guidelines Information on Working in Areas Subject to Radiation from VUV Injection Procedure for...

267

Prepared by:  

E-Print Network (OSTI)

Standard Review Plans (SRPs) are issued to describe and make available to the public information such as methods acceptable to the NRC staff for implementing specific parts of the NRC's regulations, techniques used by the staff in evaluating specific problems or postulated accidents, and data needed by the NRC staff in its review of applications for permits and licenses. This standard review plan was issued as a draft for public comment in November 2001. Based on use of this document and the public comments provided on the November 2001 version, the SRP has been revised. This SRP guides the NRC staff in performing a review of each of the decommissioning cost estimates that licensees are required to submit in accordance with 10 CFR 50.75, Reporting and Recordkeeping for Decommissioning Planning, and 10 CFR 50.82, Termination of License. The principal purpose of the SRP is to ensure the quality and uniformity of NRC staff reviews and to present a well-defined base from which to evaluate the decommissioning cost estimates that are submitted before decommissioning and at various phases of the decommissioning process. It is also the purpose of the SRP to make the information about regulatory matters widely available so that interested members

Power Reactors; C. L. Pittiglio

2004-01-01T23:59:59.000Z

268

Preliminary Plan for Retrospective Analysis of Existing Rules  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Preliminary Plan for Retrospective Analysis of Existing Rules Preliminary Plan for Retrospective Analysis of Existing Rules April 29, 2011 Draft Executive Summary On January 18, 2011, the President issued Executive Order 13563, ‗‗Improving Regulation and Regulatory Review,'' to ensure that Federal regulations seek more affordable, less intrusive means to achieve policy goals, and that agencies give careful consideration to the benefits and costs of those regulations. Executive Order 13563 recognizes the importance of maintaining a consistent culture of retrospective review and analysis throughout the executive branch. To that end, Executive Order 13563 requires agencies, by May 18, 2011, to develop a plan for review of

269

High Performance Sustainable Building Design RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

High Performance Sustainable High Performance Sustainable Building Design Review Module March 2010 CD-0 O High 0 This Re Les OFFICE OF h Perform CD-1 eview Module ssons learned f F ENVIRON Standard R mance Su Revi Critical D CD-2 M has been pilot from the pilot h NMENTAL Review Plan ustainabl iew Module Decision (CD C March 2010 ted at the SRS have been incor L MANAGE n (SRP) le Buildin e D) Applicabili D-3 SWPF and MO rporated in Rev EMENT ng Design ity CD-4 OX FFF projec view Module n Post Ope cts. eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The

270

Strengthening Line Management Oversight and Federal Monitoring of Nuclear Facilities  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

14 14 Strengthening Line Management Oversight and Federal Monitoring of Nuclear Facilities Standard Review Plan Commercial Grade Dedication (CGD) August 2013 2 of 14 OFFICE OF ENVIRONMENTAL MANAGEMENT Standard Review Plan (SRP) Commercial Grade Dedication (CGD) Applicability CD-0 CD-1 CD-2 CD-3 CD-4 Operation Post Operation August 2013 3 of 14 Table of Contents Objective ....................................................................................................................................................... 4 Overview of Commercial Grade Dedication for Nuclear Facilities .............................................................. 4 Requirements ................................................................................................................................................ 5

271

Summary - ASCEM Review  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

ASCEM EM is ground world. passiv at DOE Advan Manag state-o unders transp ASCE predict identify calcula quantif The re docum Implem inform The pr and st time of condu review The pu techni projec Site: A roject: E Report Date: S ited States Peer R Why DOE M Model Diagram faced with one dwater and soi A major goal ve remediation E sites. To aid nced Simulation gement (ASCE of-the-art scien standing and p port in natural a M modeling too ting releases fr ying exposure ations, and con fication. eview team was ment: ASCEM F mentation Plan ation provided rimary objective rategic develop f the review the ct a detailed te w will be schedu To view the full E http://www.em.doe. urpose of an Externa ical risk associated w ct decisions. Technic All Sites Environmenta September 20 Departmen Review o Environ E-EM Did This

272

Internal Program Review  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Synchrophasor Initiative (NASPI) and Synchrophasor Initiative (NASPI) and Advanced Applications Research & Development (AARD) Internal Program Review 27-28 June 2013 Washington, DC Joe Eto Lawrence Berkeley National Lab DOE/OE Transmission Reliability Program 2 Management Review Topics  Project objective  Major technical accomplishments that will be completed this year  Deliverables and schedule for activities to be completed under FY13 funding  Risk factors affecting timely completion of planned activities as well as movement through RD&D cycle  Early thoughts on follow-on work that should be considered for funding in FY14 3 Management Review Issues  RD&D stage of the project: - Theoretical study-proof of concept - Modeling/simulation-using real data?

273

Program Plans, Implementation, and Results | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

About » Program Plans, Implementation, and Results About » Program Plans, Implementation, and Results Program Plans, Implementation, and Results The Building Technologies Office (BTO) carries out technology research, development, and deployment through an ongoing process of planning and analysis, implementation, and review. This Web page includes links to documents that guide, support, and document the program management process and associated results and public benefits. Program Overview Program Plans Program Implementation Program Results Relevant Laws Program Overview Documents Better Buildings, Brighter Future: an overview of BTO activities. Program Presentation: outlines the program's priorities and goals for improving the energy efficiency of buildings. Building Energy Codes Overview Energy Efficiency Trends in Residential and Commercial Buildings

274

Fuel Cell Technologies Office: Plans, Implementation, and Results  

NLE Websites -- All DOE Office Websites (Extended Search)

About About Key Activities Plans, Implementation, & Results Budget Accomplishments Organization Chart & Contacts Quick Links Hydrogen Production Hydrogen Delivery Hydrogen Storage Fuel Cells Technology Validation Codes & Standards Education Systems Analysis Plans, Implementation, and Results The Fuel Cell Technologies Office carries out technology research, development, and deployment through an ongoing process of planning and analysis, implementation, and review. This Web page includes links to documents that support and document the program management process, and the results and public benefits that derive from it. Overview Learn more about this EERE Office. Plans Discover the plans, budgets, and analyses that set the direction of office priorities and activities.

275

Develop an Institutional Change Action Plan for Sustainability | Department  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Develop an Institutional Change Action Plan for Sustainability Develop an Institutional Change Action Plan for Sustainability Develop an Institutional Change Action Plan for Sustainability October 8, 2013 - 11:50am Addthis Graphic showing 5 gears. They progress from Determine Goal to Identify Context-Rules, Roles and Tools to Develop Action Plan to Implement Plan to Measure and Evaluate. Institutional Change Continuous Improvement Cycle After establishing a goal and assessing the rules, roles, and tools, Federal agencies can develop an action plan (select the strategies that will be implemented over time to achieve and maintain energy and sustainability goals). This action plan should target specific audiences with tailored strategies and take into account the need to review and revise strategies in the long-term. The action plan must include appropriate metrics and regular

276

Underground storage tank management plan  

Science Conference Proceedings (OSTI)

The Underground Storage Tank (UST) Management Program at the Oak Ridge Y-12 Plant was established to locate UST systems in operation at the facility, to ensure that all operating UST systems are free of leaks, and to establish a program for the removal of unnecessary UST systems and upgrade of UST systems that continue to be needed. The program implements an integrated approach to the management of UST systems, with each system evaluated against the same requirements and regulations. A common approach is employed, in accordance with Tennessee Department of Environment and Conservation (TDEC) regulations and guidance, when corrective action is mandated. This Management Plan outlines the compliance issues that must be addressed by the UST Management Program, reviews the current UST inventory and compliance approach, and presents the status and planned activities associated with each UST system. The UST Management Plan provides guidance for implementing TDEC regulations and guidelines for petroleum UST systems. (There are no underground radioactive waste UST systems located at Y-12.) The plan is divided into four major sections: (1) regulatory requirements, (2) implementation requirements, (3) Y-12 Plant UST Program inventory sites, and (4) UST waste management practices. These sections describe in detail the applicable regulatory drivers, the UST sites addressed under the Management Program, and the procedures and guidance used for compliance with applicable regulations.

NONE

1994-09-01T23:59:59.000Z

277

The impact of physical planning policy on household energy use and greenhouse emissions .  

E-Print Network (OSTI)

??This thesis investigates the impact of physical planning policy on combined transport and dwelling-related energy use by households. Separate analyses and reviews are conducted into (more)

Rickwood, Peter

278

Reviews and Validations | Department of Energy  

NLE Websites -- All DOE Office Websites (Extended Search)

Reviews and Reviews and Validations Reviews and Validations External Independent Review (EIR) Procedures Under DOE O 413.3B, Program and Project Management for the Acquisition of Capital Assets, the Office of Acquisition and Project Management (OAPM) must perform a Performance Baseline External Independent Review (EIR) prior to Critical Decision (CD) 2, and a Construction/Execution Readiness EIR for all Major System projects prior to CD-3. The EIR Standard Operating Procedures (SOP) discuss all elements of EIRs including review scope, review process, Corrective Action Plans, and OAPM's Performance Baseline Validation Process. The intent of the SOP is to make clear the OAPM expectations for both the CD-2 and CD-3 EIR, and thereby facilitate the project planning process. In particular, OAPM expects that the Scope of

279

Institutional plan. FY 1998-2003  

SciTech Connect

During the DOE Onsite Review in August 1996, Sandia`s Executive Vice President formally proposed combining Sandia`s Institutional Plan and Operating Plan, and their associated processes. The Assistant Secretary for Defense Programs subsequently approved a pilot plan to do so. This pilot plan is intended to comply with one of our new strategic objectives (see section 3.7), which entails creating an infrastructure that is a competitive advantage for our strategic missions. Therefore, Sandia`s planning organization integrated the information in the two plans and collected the data with a unified call. These data can not be combined in multiple ways, depending on customer requirements. Recently, executive management revamped Sandia`s Strategic Plan by creating eight new strategic objectives: four primary whats and four supporting hows. The new strategic objectives are set forth in chapters 3 through 5 of this document. The four primary objectives cover nuclear weapons responsibilities, nonproliferation and materials control, energy and critical infrastructures, and emerging national security threats. The major programmatic initiatives in chapter 7 are grouped accordingly. However, the programmatic descriptions in chapter 6 and the associated funding tables in chapter 9 continue to be presented by DOE Budget and Reporting Code, as in previous Sandia institutional plans. As an aid to the reader, the four primary strategic objectives in chapter 3 are cross-referenced to the program information in chapter 6.

1997-11-01T23:59:59.000Z

280

2011 ANNUAL PLANNING SUMMARY FOR ADVANCED RESEARCH AND PROJECTS...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

for each NEPA review identified. APS-2011-WAPA.xls More Documents & Publications 2010 Annual Planning Summary for Advanced Research Projects Agency-Energy (ARPA-E) 2011 Annual...

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


281

Plan - Data Management  

NLE Websites -- All DOE Office Websites (Extended Search)

Plan Plan Data Management for Data Providers Click an arrow to follow the data management path of a data set from planning to curation. plan Overview plan Plan manage Manage archive Archive curation DAAC Curation Data Management Overview Plan Manage Archive DAAC Curation Related Links DAAC Help Best Practices PDF Workshops DataONE ESIP Data Management Plans NASA's Terrestrial Ecology Program now requires that each proposal include a Data Management Plan (DMP) of up to two pages. A DMP for a proposal is a brief document that outlines what you will do with your data during and after your research, to ensure your data will be safe, documented, and accessible now and in the future. A DMP - developed early and used throughout the research project - will increase research efficiency by making the data understandable and usable in the future and

282

Guidance for Planning Exercises  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

for Planning, Conducting and Evaluating for Planning, Conducting and Evaluating Transportation Emergency Preparedness Tabletops, Drills and Exercises Prepared for the Department of Energy Office of Transportation and Emergency Management 02B00215-10.p65 This page intentionally left blank table of contents Transportation Emergency Preparedness Program (TEPP) planning tools planning tools Guidance f Guidance f Guidance f Guidance f Guidance for Planning, Conducting and Ev or Planning, Conducting and Ev or Planning, Conducting and Ev or Planning, Conducting and Ev or Planning, Conducting and Evaluating aluating aluating aluating aluating T T T T Tr r r r ransportation Emer ansportation Emer ansportation Emer ansportation Emer ansportation Emergenc genc genc genc gency Pr y Pr y Pr y Pr y Prepar epar epar epar eparedness T

283

Safeguards and Security and Cyber Security RM  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Safeguards and Security and Safeguards and Security and Cyber Security Review Module March 2010 CD- -0 OFFICE O S CD-1 OF ENVIRO Standard Safeguar and Cy Rev Critical D CD-2 M ONMENTA Review Pla rds and S yber Secu view Modul Decision (CD CD March 2010 AL MANAG an (SRP) Security urity le D) Applicabili D-3 GEMENT ity CD-4 Post Ope eration Standard Review Plan, 2 nd Edition, March 2010 i FOREWORD The Standard Review Plan (SRP) 1 provides a consistent, predictable corporate review framework to ensure that issues and risks that could challenge the success of Office of Environmental Management (EM) projects are identified early and addressed proactively. The internal EM project review process encompasses key milestones established by DOE O 413.3A, Change 1, Program and Project Management for the Acquisition of Capital Assets, DOE-STD-

284

Book Reviews  

Science Conference Proceedings (OSTI)

In Book Reviews, we review an extensive and diverse range of books. They cover theory and applications in operations research, statistics, management science, econometrics, mathematics, computers, and information systems. In addition, we include ...

Benjamin Lev

2007-09-01T23:59:59.000Z

285

Book Reviews  

Science Conference Proceedings (OSTI)

In Book Reviews, we review an extensive and diverse range of books. They cover theory and applications in operations research, statistics, management science, econometrics, mathematics, computers, and information systems. In addition, we include ...

Graham K. Rand

2013-01-01T23:59:59.000Z

286

Book Reviews  

Science Conference Proceedings (OSTI)

In Book Reviews, we review an extensive and diverse range of books. They cover theory and applications in operations research, statistics, management science, econometrics, mathematics, computers, and information systems. In addition, we include ...

Graham K. Rand

2013-03-01T23:59:59.000Z

287

National Ignition Facility Title II Design Plan  

Science Conference Proceedings (OSTI)

This National Ignition Facility (NIF) Title II Design Plan defines the work to be performed by the NIF Project Team between November 1996, when the U.S. Department of Energy (DOE) reviewed Title I design and authorized the initiation of Title H design and specific long-lead procurements, and September 1998, when Title 11 design will be completed.

Kumpan, S

1997-03-01T23:59:59.000Z

288

Book Review  

E-Print Network (OSTI)

Work Transformed Our Own Rebecca Fowler Bridging: How Gloriaagain and again (203). Fowler| Book Review: Bridging: How

Fowler, Rebecca

2013-01-01T23:59:59.000Z

289

Improving LEC incentive regulation plans. [local exchange carriers (LEC)  

Science Conference Proceedings (OSTI)

This article recommends improving local exchange carriers (LEC) incentive regulation plans. The benefits of incentive regulation to customers/ratepayers, stockholders, LEC management, and regulators is reviewed. The potential pitfalls in recession risk, investment decisions and pricing inflexibility are examined. A review of the various forms of modified rate of return incentive regulation is included as a way to examine the characteristics needed for a successful incentive regulation plan.

Kraemer, J.S. (Deloitte and Touche, Washington, DC (United States))

1991-02-01T23:59:59.000Z

290

Microsoft Word - prjct planning  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Planning Checklist Planning Checklist The following checklist is intended to provide system owners, project managers, and other information system development and maintenance professionals with guidance in identifying and preparing project planning activities. The checklist reflects recognized project planning activities to be performed throughout the information systems project life cycle. Project planning is generally characterized as a process for selecting the strategies, policies, programs, and procedures for achieving the objectives and goals of the project. The objectives of project planning for information systems projects are summarized as the following: C User's environment is analyzed. C Project objectives and scope are defined. C High-level functional requirements are estimated.

291

CHEMICAL HYGIENE PLAN HAZARD COMMUNICATION PLAN  

E-Print Network (OSTI)

CHEMICAL HYGIENE PLAN AND HAZARD COMMUNICATION PLAN Occupational Exposures to Hazardous Chemicals and Safety Numbers Research Safety 2723 Environmental Health/Safety Chemical Hygiene Officer Radiation Safety Human Resources (Accident Reports) 4589 Clinical Engineering 2964 #12;TABLE OF CONTENTS CHEMICAL HYGIENE

Oliver, Douglas L.

292

Transit planning in metropolitan Seattle: a historical perspective. Final report  

SciTech Connect

The document provides a historical overview of trends in transit planning to casing on the experiences of Seattle, Washington as a case study. It focuses on the period from the 1940's to the present, detailing major transit initiatives and the planning process which led to them. The document includes a detailed chronological review of events affecting transportation planning, both in Seattle and nationwide.

Malm, R.

1986-04-01T23:59:59.000Z

293

Disabled Parking & Access Plan Campus Disabled Persons (DP)  

E-Print Network (OSTI)

ongoing survey service contract · Accurate Parking Space Counts ­ Yearly aerial photos for review Plan Ongoing Objectives · Keep Campus Survey and Campus-wide Access Plan Current · Follow Up Feedback ­ Computer-based survey of surface features, buildings, parking lot striping, pedestrian walkways ­ Campus

de Lijser, Peter

294

Draft Mission Plan Amendment  

SciTech Connect

The Department of Energy`s Office Civilian Radioactive Waste Management has prepared this document to report plans for the Civilian Radioactive Waste Management Program, whose mission is to manage and dispose of the nation`s spent fuel and high-level radioactive waste in a manner that protects the health and safety of the public and of workers and the quality of the environment. The Congress established this program through the Nuclear Waste Policy Act of 1982. Specifically, the Congress directed us to isolate these wastes in geologic repositories constructed in suitable rock formations deep beneath the surface of the earth. In the Nuclear Waste Policy Amendments Act of 1987, the Congress mandated that only one repository was to be developed at present and that only the Yucca Mountain candidate site in Nevada was to be characterized at this time. The Amendments Act also authorized the construction of a facility for monitored retrievable storage (MRS) and established the Office of the Nuclear Waste Negotiator and the Nuclear Waste Technical Review Board. After a reassessment in 1989, the Secretary of Energy restructured the program, focusing the repository effort scientific evaluations of the Yucca Mountain candidate site, deciding to proceed with the development of an MRS facility, and strengthening the management of the program. 48 refs., 32 figs.

1991-09-01T23:59:59.000Z

295

NSLS Industrial User Enhancement Plan The overall goal of this plan for enhancing the NSLS Industrial Users' Program is to encourage greater  

NLE Websites -- All DOE Office Websites (Extended Search)

Industrial User Enhancement Plan Industrial User Enhancement Plan The overall goal of this plan for enhancing the NSLS Industrial Users' Program is to encourage greater use of synchrotron tools by industry researchers, improve access to NSLS beamlines by industrial researchers, and facilitate research collaborations between industrial researchers and NSLS staff, as well as researchers from university and government laboratories. The implementation of this plan will also involve modifications of the existing user access policy. The plan includes the following major elements: Improve the NSLS proposal review system:  Proposal rating review criteria has been modified to reflect the importance of technology

296

Wellness Planning Session Report  

E-Print Network (OSTI)

Wellness Planning Session Report September 12, 2008 #12;Wellness Planning Session Report Printed.............................................................................1 Explored what wellness program should look like at NMSU .......................2 Considered for the Wellness committee..................................2 Identified the next meeting date and meeting agenda

Castillo, Steven P.

297

Strategic Planning History  

NLE Websites -- All DOE Office Websites (Extended Search)

Strategy for Global Change Research Related Federal Climate Efforts Strategic Planning History Print E-mail Below is a timeline of past strategic plans that have guided The U.S....

298

Business Continuity Planning  

Science Conference Proceedings (OSTI)

This article considers various strategies for protecting an organisation from both natural and man-made disasters. The differences between business continuity planning, and disaster recovery planning are recognised. 1997 John Wiley & Sons, ...

Martin Nemzow

1997-07-01T23:59:59.000Z

299

Hydrogen Posture Plan  

Fuel Cell Technologies Publication and Product Library (EERE)

The Hydrogen Posture Plan, published in December 2006, outlines a coordinated plan for activities under the Hydrogen Fuel Initiative, both at the Department of Energy and the Department of Transportat

300

RM Capital Investment Plans  

NLE Websites -- All DOE Office Websites (Extended Search)

Capital Investment Plans FY 2004 (568kb pdf) FY 2005 (625kb pdf) FY 2006 (625kb pdf) FY 2007 (1.45mb pdf) Meter policy Capital Investment Plans...

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


301

Draft 2013 Annual Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Draft 2013 Annual Plan Draft 2013 Annual Plan Section 999: Draft 2013 Annual Plan Section 999 - Draft 2013 Annual Plan...

302

Strategic Plan Submitted to the Secretary  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

4 Volume 1, Number 3 4 Volume 1, Number 3 In This Issue * Executive Order Update * $1 Million for Manhattan Project Preservation * 2004 DOE Cultural Resources Forum * ES&H Cultural Resources Update * FPO Site Visits * Oppenheimer and the Manhattan Project Event * Museum Notes * Save America's Treasures * Featured Photo: Oak Ridge, 1949 Strategic Plan Submitted to the Secretary The strategic plan for history and heritage resources that Secretary Abraham directed the Federal Preservation Officer to prepare has been submitted and is under review. Following the December 2, 2003, briefing at which the Secretary directed preparation of a plan to make recommendations for the full range of the Department's history and heritage resources, FPO Skip Gosling and Deputy FPO Terry Fehner put together a small planning

303

National Security Technology Incubator Action Plan  

SciTech Connect

This report documents the action plan for developing the National Security Technology Incubator (NSTI) program for southern New Mexico. The NSTI program is being developed as part of the National Security Preparedness Project (NSPP), funded by Department of Energy (DOE)/National Nuclear Security Administration (NNSA). This action plan serves as a tool in measuring progress in the development process and delivery of services for the NSTI program. Continuous review and evaluation of the action plan is necessary in the development process of the NSTI. The action plan includes detailed steps in developing the NSTI program based on recommended best practices in incubator development by the National Business Incubation Association (NBIA). Included are tasks required to implement the NSTI, developed within a work breakdown structure. In addition, a timeline is identified for each task.

2008-02-28T23:59:59.000Z

304

BNL | Center for Functional Nanomaterials Operations Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Basic Rules Everyone Must Know Basic Rules Everyone Must Know Work Planning All work must be planned and reviewed for safety. Experimental Safety Reviews (ESRs), Safety Approval Forms (SAFs), and Work Permits are the documents used at the CFN. Make sure your project is reviewed and approved before you begin your work and that you follow all rules, regulations, and postings. Changes in procedures need to be approved before work commences. All individuals performing work at BNL are required to obtain a guest or permanent appointment before beginning work. You must wear your badge/ID at all times. Radioactive materials, chemicals, and equipment may not be brought into the Department without prior notification. Shipping ANY sample from BNL needs to be done through the shipping desk located in B98. Any radioactive material must be evaluated by the

305

Sandia Strategic Plan 1997  

SciTech Connect

Sandia embarked on its first exercise in corporate strategic planning during the winter of 1989. The results of that effort were disseminated with the publication of Strategic Plan 1990. Four years later Sandia conducted their second major planning effort and published Strategic Plan 1994. Sandia`s 1994 planning effort linked very clearly to the Department of Energy`s first strategic plan, Fueling a Competitive Economy. It benefited as well from the leadership of Lockheed Martin Corporation, the management and operating contractor. Lockheed Martin`s corporate success is founded on visionary strategic planning and annual operational planning driven by customer requirements and technology opportunities. In 1996 Sandia conducted another major planning effort that resulted in the development of eight long-term Strategic Objectives. Strategic Plan 1997 differs from its predecessors in that the robust elements of previous efforts have been integrated into one comprehensive body. The changes implemented so far have helped establish a living strategic plan with a stronger business focus and with clear deployment throughout Sandia. The concept of a personal line of sight for all employees to this strategic plan and its objectives, goals, and annual milestones is becoming a reality.

1997-12-01T23:59:59.000Z

306

HR Fundamentals Retirement Plans  

E-Print Network (OSTI)

FY 12-13 #12;Professional & Faculty Retirement · TIAA/CREF · Defined Contribution Retirement Plan 401 & State Taxes are deferred · Immediate Vesting · www.tiaa-cref.org (800) 842-2776 FY 12-13 #12;TIAA - Public Employee's Retirement System "Defined Contribution Plan" 3) TIAA/CREF ­ Defined Contribution Plan

Dyer, Bill

307

Conversion Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Conversion Plan Conversion Plan This template is used to document the conversion plan that clearly defines the system or project's conversion procedures; outlines the installation...

308

Strategic Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Sites Power Marketing Administration Other Agencies You are here Home About Us Strategic Plan Strategic Plan Leadership Budget Our Organization Strategic Plan Careers Our...

309

Training Plan | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Training Plan Training Plan This template is used to define the plan, scope, environment, roles and responsibilities for training needs for systemsoftware development and...

310

Institutional Plan FY 2003 - 2007  

E-Print Network (OSTI)

III. LABORATORY STRATEGIC PLAN DOE Program Focus on ResultsInstitutional Plan addresses the strategic goals of DOE andbelow does not support those elements of the strategic plan

Chartock, Michael; Hansen, Todd

2002-01-01T23:59:59.000Z

311

2006 Department of Energy Strategic Plan - Linking Strategic Goals to  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

2006 Department of Energy Strategic Plan - Linking Strategic Goals 2006 Department of Energy Strategic Plan - Linking Strategic Goals to Annual Performance Goals 2006 Department of Energy Strategic Plan - Linking Strategic Goals to Annual Performance Goals Section 10 of the U.S. Department of Energy's Strategic Plan discusses Linking Strategic Goals to Annual Performance Goals through Program Assessment. DOE uses a variety of methods and tools to assess its programs. Internally, programs are required to report quarterly on their progress in meeting annual performance metrics. The data is then consolidated for senior management review. 2006 Department of Energy Strategic Plan - Linking Strategic Goals to Annual Performance Goals More Documents & Publications 2006 Department of Energy Strategic Plan U.S Department of Energy Strategic Plan

312

Nanomaterials Safety Implementation Plan, Ames Laboratory | Department of  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Nanomaterials Safety Implementation Plan, Ames Laboratory Nanomaterials Safety Implementation Plan, Ames Laboratory Nanomaterials Safety Implementation Plan, Ames Laboratory Ames Laboratory has limited activities involving nanomaterials. Potential hazards associated with nanomaterials work are addressed through the Laboratory's Integrated Safety Management System (ISMS) and specifically the Readiness Review process. Readiness Review provides the identification and evaluation of potential hazards and establishes effective control mechanisms to ensure protection of the employee and the environment. To date, hazards associated with projects involving nanomaterials have been determined to be amenable to conventional controls such as ventilation and use of personal protective equipment. The Laboratory recognizes that nanotechnology is an emerging field and that

313

Alaska Strategic Energy Plan and Planning Handbook  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Alaska Strategic Energy Alaska Strategic Energy Plan and Planning Handbook A. Dane and L. Doris National Renewable Energy Laboratory U.S. Department of Energy | Office of Indian Energy 1000 Independence Ave. SW, Washington DC 20585 | 202-586-1272 energy.gov/indianenergy | indianenergy@hq.doe.gov Alaska Strategic Energy Plan and Planning Handbook ii NOTICE This report was prepared as an account of work sponsored by an agency of the United States government. Neither the United States government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned

314

Operating plan FY 1998  

SciTech Connect

This document is the first edition of Argonne`s new Operating Plan. The Operating Plan complements the strategic planning in the Laboratory`s Institutional Plan by focusing on activities that are being pursued in the immediate fiscal year, FY 1998. It reflects planning that has been done to date, and it will serve in the future as a resource and a benchmark for understanding the Laboratory`s performance. The heart of the Institutional Plan is the set of major research initiatives that the Laboratory is proposing to implement in future years. In contrast, this Operating Plan focuses on Argonne`s ongoing R&D programs, along with cost-saving measures and other improvements being implemented in Laboratory support operations.

1997-10-01T23:59:59.000Z

315

Reliabilit PlanningReliability Planning David Duebner, Expansion Planningp g  

E-Print Network (OSTI)

EE552 Reliabilit PlanningReliability Planning David Duebner, Expansion Planningp g September 27, 2010 #12;Reliability Planning OverviewReliability Planning Overview · Midwest ISO Transmission Expansion Plan (MTEP)p ( ) · MTEP Reliability Study Process ­ Planning Criteriag ­ Reliability Analysis

McCalley, James D.

316

Page not found | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

31 - 22540 of 28,905 results. 31 - 22540 of 28,905 results. Contributor David Shafer David Shafer is the Team Leader for the Asset Management Team in the Office of Legacy Management (LM). The team provides support to the Environmental Teams in the areas of environmental compliance... http://energy.gov/lm/contributors/david-shafer Page Standard Review Plan (SRP) Modules Standard Review Plan - Critical Decision Handbook http://energy.gov/em/standard-review-plan-srp-modules Page EIS-0288: Production of Tritium in a Commercial Light Water Reactor This Environmental Impact Statement for the Production of Tritium in a Commercial Light Water Reactor (CLWR EIS) evaluates the environmental impacts associated with producing tritium at one or more... http://energy.gov/nepa/eis-0288-production-tritium-commercial-light-water-reactor

317

Page not found | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

81 - 19390 of 28,560 results. 81 - 19390 of 28,560 results. Page Standard Review Plan (SRP) Modules Standard Review Plan - Critical Decision Handbook http://energy.gov/em/standard-review-plan-srp-modules Page EIS-0288: Production of Tritium in a Commercial Light Water Reactor This Environmental Impact Statement for the Production of Tritium in a Commercial Light Water Reactor (CLWR EIS) evaluates the environmental impacts associated with producing tritium at one or more... http://energy.gov/nepa/eis-0288-production-tritium-commercial-light-water-reactor Download CX-008589: Categorical Exclusion Determination Clearwater Campus District Cooling - Activity 3 Geothermal Test Bores CX(s) Applied: A9, B3.1 Date: 07/23/2012 Location(s): Florida Offices(s): Golden Field Office http://energy.gov/nepa/downloads/cx-008589-categorical-exclusion-determination

318

DOE Preliminary Plan for Retrospective Analysis of Existing Rules |  

NLE Websites -- All DOE Office Websites (Extended Search)

Preliminary Plan for Retrospective Analysis of Existing Rules Preliminary Plan for Retrospective Analysis of Existing Rules DOE Preliminary Plan for Retrospective Analysis of Existing Rules On January 18, 2011, the President issued Executive Order 13563, "Improving Regulation and Regulatory Review," to ensure that Federal regulations seek more affordable, less intrusive means to achieve policy goals, and that agencies give careful consideration to the benefits and costs of those regulations. Executive Order 13563 recognizes the importance of maintaining a consistent culture of retrospective review and analysis throughout the executive branch. To that end, Executive Order 13563 requires agencies, by May 18, 2011, to develop a plan for review of their existing significant regulations. DOE_05_18_2011.pdf More Documents & Publications

319

DOE Plans | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Management Certifications and Professional Development Real Estate History DOE Strategic Plans Strategic Plan for the Department of Energy Environmental Restoration...

320

System Planning for Low-Activity Waste at Hanford  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Technical Review of System Planning Technical Review of System Planning for Low-Activity Waste Treatment at Hanford November 2008 Dr. David S. Kosson, Vanderbilt University Dr. David R. Gallay, Logistics Management Institute Dr. Ian L. Pegg, The Catholic University of America Dr. Ray G. Wymer, Oak Ridge National Laboratory (ret.) Dr. Steven Krahn, U. S. Department of Energy ii ACKNOWLEDGEMENT The Review Team thanks Mr. Ben Harp, Office of River Protection (ORP), and Mr. James Honeyman, CH2M HILL, for their exceptional support during this review. Mr. Harp was the lead Department of Energy (DOE) representative responsible for organizing reviews held on-site by the Review Team. Mr. Honeyman, and his staff, provided responsive support through technical presentations, telephone conferences, and numerous reference documents.

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


321

Commentary Should research be part of advance care planning?  

E-Print Network (OSTI)

Advance care planning is a process to help people to formulate and communicate their preferences regarding future care during critical illness. Reviews of the advance care planning process in its current form have been disappointing. Improvements in care at the end of life and palliative care are necessary for the provision of modern medical care. Medical research has led to many improvements at the physiological and technological levels. It is only by applying the same rigour of scientific study and research ethics that improvements in the advance care planning process can be made. Keywords advance care planning, critical illness, palliative care, research ethics

Alexandra M Easson

2004-01-01T23:59:59.000Z

322

Retirement TimeLine TIAA-CREF/Fidelity Retirement Plan Participant  

E-Print Network (OSTI)

1 Retirement TimeLine TIAA-CREF/Fidelity Retirement Plan Participant Retirement planning is essential early in your career! Your TIAA-CREF/Fidelity retirement account is based on the University retirement accounts ­ it is never too early to plan for your retirement! · Review your TIAA

323

Buried waste integrated demonstration configuration management plan  

SciTech Connect

This document defines plans for the configuration management requirements for the Buried Waste Integrated Demonstration (BWID) Program. Since BWID is managed programmatically by the Waste Technology Development Department (WTDD), WTDD Program Directive (PD) 1.5 (Document Preparation, Review, Approval, Publication, Management and Change Control) is to be followed for all internal EG&G Idaho, Inc., BWID programmatic documentation. BWID documentation generated by organizations external to EG&G Idaho is not covered by this revision of the Configuration Management Plan (CMP), but will be addressed in subsequent revisions.

Cannon, P.G.

1992-02-01T23:59:59.000Z

324

Buried waste integrated demonstration configuration management plan  

SciTech Connect

This document defines plans for the configuration management requirements for the Buried Waste Integrated Demonstration (BWID) Program. Since BWID is managed programmatically by the Waste Technology Development Department (WTDD), WTDD Program Directive (PD) 1.5 (Document Preparation, Review, Approval, Publication, Management and Change Control) is to be followed for all internal EG G Idaho, Inc., BWID programmatic documentation. BWID documentation generated by organizations external to EG G Idaho is not covered by this revision of the Configuration Management Plan (CMP), but will be addressed in subsequent revisions.

Cannon, P.G.

1992-02-01T23:59:59.000Z

325

Action Item Review and Status  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Waste Corporate Board Waste Corporate Board Action Items Action Item Resolution Action Item Strategic Planning Initiative Optimization Study Resolution Presentation by S. Schneider (HLW System Integrated Project Team) Pretreatment Whitepaper Presentation by W. Wilmarth (Role of Liquid Waste Pretreatment Technologies in Solving the DOE Clean-up Mission) Draft Charter for Performance Assessment Sub-Committee Presentation by J. Marra (Performance Assessment Community of Practice) Final Report from Slurry Transport Workshop In final stages of review and Approval; will be distributed when complete This document is intended for planning and analysis purposes, assuming a continuing constrained budget environment. Every effort will be made to comply with all applicable environmental and legal obligations,

326

New Planning Framework  

Science Conference Proceedings (OSTI)

This report describes an investigation into how various regulatory, economic, and technical changes are likely to affect the framework for transmission planning. It begins with an overview of the Existing Planning Framework, structured along the lines of five key aspects that encompass the purview, role, and responsibilities of transmission planning. The report then explores seven scenarios (future states) of transformative change in the electricity industryranging from the greater penetration of wind ge...

2010-12-22T23:59:59.000Z

327

Buildings characterization sampling plan, Weldon Spring Site  

SciTech Connect

The purpose of the Buildings Sampling Plan is to provide a systematic approach to characterizing radiological, asbestos and chemical contamination in and around the buildings and structures at the Weldon Spring Chemical Plant Site (WSCPS). This sampling plan reviews historical information; identifies data needs; and outlines sampling procedures, quality assurance, data documentation and reporting requirements for the buildings and equipment characterization at the Weldon Spring Site (WSS). The scope of this plan is limited to the buildings, structures, and equipment from the previous operation of the WSCPS. The Buildings Sampling Plan is divided into nine sections: introduction, background, data needs and sampling plan objectives, sampling rationale and procedure, sample analysis, quality assurance, data documentation, reporting requirements, and references. The data needs, sampling rationale and procedures and sample analysis sections of this work plan are subdivided into radiological, asbestos and chemical sections. Because different sampling techniques and analyses will be required for radiological, asbestos and chemical contamination, separate subsections are used. The investigations for each contaminant will be conducted independently. Similar historical and descriptive information is repeated in the subsections, but the perspective and information vary slightly. 24 refs., 5 figs., 14 tabs.

Not Available

1988-08-01T23:59:59.000Z

328

JGI - Sequencing Plans  

NLE Websites -- All DOE Office Websites (Extended Search)

Sequencing Plans Sequencing Plans JGI engages users from the National Laboratory system, academic institutions, and private industry to perform sequencing projects that directly relate to the DOE Office of Biological and Environmental Research's missions in alternative energy, global carbon cycling, and bioremediation. JGI's sequencing portfolio is drawn from its user programs, including the Community Science Program and the new Bioenergy Research Centers, as well as targets chosen by DOE to meet programmatic objectives. Plans by Program and Year All projects GEBA Sequencing Plans Community Science Program FY2014 Community Sequencing Program FY2013 Community Sequencing Program FY2012 Community Sequencing Program FY2011 Community Sequencing Program FY2010 Community Sequencing Program FY2009

329

Business Plan Competition Opportunities  

The Draper Fisher Jurvetson Venture Challenge is a West Coast business plan competition available to the colleges and universities across the West Coast that

330

Environmental Protection Implementation Plan  

SciTech Connect

This Environmental Protection Implementation Plan is intended to ensure that the environmental program objectives of Department of Energy Order 5400.1 are achieved at SNL/California. This document states SNL/California`s commitment to conduct its operations in an environmentally safe and responsible manner. The Environmental Protection Implementation Plan helps management and staff comply with applicable environmental responsibilities. This report focuses on the following: notification of environmental occurrences; general planning and reporting; special programs and plans; environmental monitoring program; and quality assurance and data verification.

Brekke, D.D.

1995-11-01T23:59:59.000Z

331

SEAB Climate Action Plan  

Energy.gov (U.S. Department of Energy (DOE))

A presentation on the Climate Action Plan presented by Dr. Jonathan Pershing, Deputy Assistant Secretary for Climate Change at the U.S. Department of Energy.

332

Planning, Budget, and Analysis  

NLE Websites -- All DOE Office Websites (Extended Search)

EERE Planning, Budget, and Analysis (Revised) Philip Patterson (Economist) and Jeff Dowd (Economist) DOE Hydrogen, Fuel Cells, and Infrastructure Technologies Program Systems...

333

Climate Action Plan (Kentucky)  

Energy.gov (U.S. Department of Energy (DOE))

The Commonwealth of Kentucky established the Kentucky Climate Action Plan Council (KCAPC) process to identify opportunities for Kentucky to respond to the challenge of global climate change while...

334

Cost Sensitive Conditional Planning  

E-Print Network (OSTI)

While POMDPs provide a general platform for conditional planning under a wide range of quality metrics they have limited scalability. On the other hand, uniform probability conditional planners scale very well, but many lack the ability to optimize plan quality metrics. We present an innovation to planning graph based heuristics that helps uniform probability conditional planners both scale and generate high quality plans when using actions with non uniform costs. We make empirical comparisons with two state of the art planners to show the benefit of our techniques.

Daniel Bryce; Subbarao Kambhampati

2005-01-01T23:59:59.000Z

335

Operations Strategic Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Operations Strategic Plan Updated July 2009 Operations Organization Chief Operating Officer (COO) Deputy COO Environment, Health & Safety EH&S Facilities FAC Project Management...

336

Workforce Diversity Action Plans  

NLE Websites -- All DOE Office Websites (Extended Search)

Workforce Diversity Action Plans Workforce Diversity Office Best Practices Diversity Council Compendium of Diversity Activities Principles for a Diverse Community Lawrence Berkeley...

337

Hoisting & Rigging Lift Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Authorized Personnel (attach more sheets if necessary) Printed name Signature Date SSRL Hoisting & Rigging Lift Plan Stanford Synchrotron Radiation Laboratory May 16, 2005...

338

Planning and Projects  

NLE Websites -- All DOE Office Websites (Extended Search)

Planning Ten-Year Capital Program Projects Lovell-Yellowtail Transmission Line Rebuild project Studies WACM Wind production summary overview (Oct. 2006)...

339

ORISE: Exercise Planning  

NLE Websites -- All DOE Office Websites (Extended Search)

Oak Ridge Institute for Science and Education (ORISE) helps federal, state and local emergency management personnel plan and prepare for the threat of a national security or...

340

Hanford Site Strategic Facilities Plan: Site planning  

SciTech Connect

This plan revises the Hanford Site Strategic Facilities Plan submitted by Westinghouse Hanford Company in 1988. It separates the Hanford Site facilities into two categories: ''strategically required'' facilities and ''marginal'' facilities. It provides a comparison of future facility requirements against existing capacities and proposed projects to eliminate or consolidate marginal facilities (i.e., those facilities that are not fully utilized or are no longer required to accomplish programmatic missions). The objective is to enhance the operating efficiency of the Hanford Site by maximizing facility use and minimizing unnecessary facility operating and maintenance costs. 11 refs.

1989-03-01T23:59:59.000Z

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


341

CROSSFLOW FILTRATON: LITERATURE REVIEW  

Science Conference Proceedings (OSTI)

As part of the Filtration task EM-31, WP-2.3.6, which is a joint effort between Savannah River National Laboratory (SRNL) and the Pacific Northwest National Laboratory (PNNL), tests were planned to evaluate crossflow filtration in order to the improve the use of existing hardware in the waste treatment plants at both the Department of Energy (DOE) Savannah River Site (SRS) and Hanford Site. These tests included experiments to try different operating conditions and additives, such as filter aids, in order to create a more permeable filter cake and improve the permeate flux. To plan the SRNL tests a literature review was performed to provide information on previous experiments performed by DOE laboratories, and by academia. This report compliments PNNL report (Daniel, et al 2010), and is an attempt to try and capture crossflow filtration work performed in the past that provide a basis for future testing. However, not all sources on crossflow filtration could be reviewed due to the shear volume of information available. In this report various references were examined and a representative group was chosen to present the major factors that affect crossflow filtration. The information summarized in this review contains previous operating conditions studied and their influence on the rate of filtration. Besides operating conditions, other attempted improvements include the use of filter aids, a pre-filtration leaching process, the backpulse system, and various types of filter tubes and filter coatings. The results from past research can be used as a starting point for further experimentation that can result in the improvement in the performance of the crossflow filtration. The literature reviewed in this report indicates how complex the crossflow issues are with the results of some studies appearing to conflict results from other studies. This complexity implies that filtration of mobilized stored waste cannot be explained in a simple generic sense; meaning an empirical model develop from one waste-filter combination will more than likely not be applicable to another combination. It appears that filtration performance varies as wide as the range of the types of slurry wastes that exist. However, conclusions can be elicited from existing information so that filter performance can be better understood, and hopefully improved. Those conclusions and recommendations for the planned tests are listed.

Duignan, M.

2011-01-01T23:59:59.000Z

342

Waste minimization and pollution prevention awareness plan. Revision 1  

SciTech Connect

The purpose of this plan is to document Lawrence Livermore National Laboratory (LLNL) projections for present and future waste minimization and pollution prevention. The plan specifies those activities and methods that are or will be used to reduce the quantity and toxicity of wastes generated at the site. It is intended to satisfy Department of Energy (DOE) requirements. This Waste Minimization and Pollution Prevention Awareness Plan provides an overview of projected activities from FY 1994 through FY 1999. The plans are broken into site-wide and problem-specific activities. All directorates at LLNL have had an opportunity to contribute input, estimate budgets, and review the plan. In addition to the above, this plan records LLNL`s goals for pollution prevention, regulatory drivers for those activities, assumptions on which the cost estimates are based, analyses of the strengths of the projects, and the barriers to increasing pollution prevention activities.

Not Available

1994-07-01T23:59:59.000Z

343

Book Reviews  

E-Print Network (OSTI)

community of concerned social scientists. Cricket: A Bridge of Peace by Shaharyar M. Khan, Oxford University Press, Oxford, 2005, viii, 230 pp. Reviewed by Michelle Cooksley University of Leeds Not so long ago, Test cricket was dismissed...

Thapa, Deepak

2005-01-01T23:59:59.000Z

344

Book Review  

E-Print Network (OSTI)

the chapters. However, Durable Disorder presents a good introduction to the complicated and thorny subject matter of the Northeast for the unacquainted reader. Reviewed by Susanne Kranz University of Leeds ...

Kranz, Susanne

2006-01-01T23:59:59.000Z

345

Book Reviews  

E-Print Network (OSTI)

for the remainder of the book. Hence, this mix of personalBook Reviews U rban Sprawl : Causes, Conseq uences, & Policyo choose. Therefore, this book argues that it would be both

Deng, Lan; Ronegerude, Jane; Sandoval, Gerardo

2004-01-01T23:59:59.000Z

346

Book Review  

E-Print Network (OSTI)

2:1 2013 I recommend this book to activists, organizers,like. I also rec- ommend this book to anyone who still seesBook Review: Medicine Stories: History,Culture and the

Jagernauth, Tanuja

2013-01-01T23:59:59.000Z

347

LFRG Program Management Plan (LFRG PMP)  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

LOW-LEVEL WASTE DISPOSAL FACILITY LOW-LEVEL WASTE DISPOSAL FACILITY FEDERAL REVIEW GROUP PROGRAM MANAGEMENT PLAN SEPTEMBER 18, 2000 LOW-LEVEL WASTE DISPOSAL FACILITY FEDERAL REVIEW GROUP PROGRAM MANAGEMENT PLAN Jay Rhoderick, Co-Chair William E. Murphie, Co-Chair LFRG Members Joel Case, Idaho Operations Office Frank DiSanza, Nevada Operations Office Doug Hildebrand, Richland Operations Office Randy Janke, Ohio Field Office Bill McMillan, Oak Ridge Operations Office Virgil Sauls, Savannah River Operations Office Jim Orban, Albuquerque Operations Office Andy Wallo, Office of Environment, Safety and Health DOE Headquarters Distribution: David M. Michaels, Assistant Secretary for Environment, Safety and Health, EH-1 Madelyn Creedon, Deputy Administrator for Defense Programs, DP-1 Rose E. Gottemoeller, Deputy Administrator for Defense Nuclear Nonproliferation, NN-1

348

National conference on integrated resource planning: Proceedings  

Science Conference Proceedings (OSTI)

Until recently, state regulators have focused most of their attention on the development of least-cost or integrated resource planning (IRP) processes for electric utilities. A number of commissions are beginning to scrutinize the planning processes of local gas distribution companies (LDCs) because of the increased control that LDCs have over their purchased gas costs (as well as the associated risks) and because of questions surrounding the role and potential of gas end-use efficiency options. Traditionally, resource planning (LDCs) has concentrated on options for purchasing and storing gas. Integrated resource planning involves the creation of a process in which supply-side and demand-side options are integrated to create a resource mix that reliably satisfies customers' short-term and long-term energy service needs at the lowest cost. As applied to gas utilities, an integrated resource plan seeks to balance cost and reliability, and should not be interpreted simply as the search for lowest commodity costs. The National Association of Regulatory Utility Commissioners' (NARUC) Energy Conservation committee asked Lawrence Berkeley Laboratory (LBL) to survey state PUCs to determine the extent to which they have undertaken least cost planning for gas utilities. The survey included the following topics: status of state PUC least-cost planning regulations and practices for gas utilities; type and scope of natural gas DSM programs in effect, including fuel substitution; economic tests and analysis methods used to evaluate DSM programs; relationship between prudency reviews of gas utility purchasing practices and integrated resource planning; key regulatory issued facing gas utilities during the next five years.

Not Available

1991-01-01T23:59:59.000Z

349

National conference on integrated resource planning: Proceedings  

Science Conference Proceedings (OSTI)

Until recently, state regulators have focused most of their attention on the development of least-cost or integrated resource planning (IRP) processes for electric utilities. A number of commissions are beginning to scrutinize the planning processes of local gas distribution companies (LDCs) because of the increased control that LDCs have over their purchased gas costs (as well as the associated risks) and because of questions surrounding the role and potential of gas end-use efficiency options. Traditionally, resource planning (LDCs) has concentrated on options for purchasing and storing gas. Integrated resource planning involves the creation of a process in which supply-side and demand-side options are integrated to create a resource mix that reliably satisfies customers` short-term and long-term energy service needs at the lowest cost. As applied to gas utilities, an integrated resource plan seeks to balance cost and reliability, and should not be interpreted simply as the search for lowest commodity costs. The National Association of Regulatory Utility Commissioners` (NARUC) Energy Conservation committee asked Lawrence Berkeley Laboratory (LBL) to survey state PUCs to determine the extent to which they have undertaken least cost planning for gas utilities. The survey included the following topics: status of state PUC least-cost planning regulations and practices for gas utilities; type and scope of natural gas DSM programs in effect, including fuel substitution; economic tests and analysis methods used to evaluate DSM programs; relationship between prudency reviews of gas utility purchasing practices and integrated resource planning; key regulatory issued facing gas utilities during the next five years.

Not Available

1991-12-31T23:59:59.000Z

350

A probabilistic plan recognition algorithm based on plan tree grammars  

Science Conference Proceedings (OSTI)

We present the PHATT algorithm for plan recognition. Unlike previous approaches to plan recognition, PHATT is based on a model of plan execution. We show that this clarifies several difficult issues in plan recognition including the execution of multiple ... Keywords: Action grammars, Bayesian methods, Goal recognition, Intent inference, Plan recognition, Probabilistic grammars, Task tracking

Christopher W. Geib; Robert P. Goldman

2009-07-01T23:59:59.000Z

351

Review of 2XIIB project  

SciTech Connect

A review is given of the 2X project, including project history and recent results, with the intent that both those new to CTR engineering and those people familiar with its progress will benefit. The current 2XII Program plan is reviewed, with emphasis on the major device fabrication underway at the present time. This construction consists primarily of a new magnet for 2XII, and has been designated 2XIIB. The injection of a 800-A neutral beam is described. The final portion of the paper is a progress report and a summary of cost estimates and scheduling. (auth)

Anderson, C.J.

1973-08-20T23:59:59.000Z

352

FTCP 2009 Operational Plan Closeout Summary  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

09 Operational Plan Closeout Summary 09 Operational Plan Closeout Summary 1 Brief Summary Objective Complete (Yes or No) Carried Over to 2010 Operational Plan Goal # Goal 1 Champion: Jim Todd, SSO Improve Processes Objectives Establish Record Keeping Requirements Champions: Jim Todd and Allen Tate, SSO Resulted in Issue Paper, FTCP-09-003 Yes No Develop Functional Area Qualification Standard (FAQS) Champion: Ali Ghovanlou, HSS Performed a consistency review of all FAQS based on accepted expectations and revised the template. Yes No Integrate Safety and Security Champions: Winnie Lehman, NNSA SC and Pat Worthington, HSS Evaluated and recommended inclusion of additional security elements to General Technical Base. Developed and implemented the Safeguards and Security FAQS.

353

Equipment qualification research program: program plan  

Science Conference Proceedings (OSTI)

The Lawrence Livermore National Laboratory (LLNL) under the sponsorship of the US Nuclear Regulatory Commission (NRC) has developed this program plan for research in equipment qualification (EQA). In this report the research program which will be executed in accordance with this plan will be referred to as the Equipment Qualification Research Program (EQRP). Covered are electrical and mechanical equipment under the conditions described in the OBJECTIVE section of this report. The EQRP has two phases; Phase I is primarily to produce early results and to develop information for Phase II. Phase I will last 18 months and consists of six projects. The first project is program management. The second project is responsible for in-depth evaluation and review of EQ issues and EQ processes. The third project is responsible for detailed planning to initiate Phase II. The remaining three projects address specific equipment; i.e., valves, electrical equipment, and a pump.

Dong, R.G.; Smith, P.D.

1982-06-08T23:59:59.000Z

354

Modeling renewable energy resources in integrated resource planning  

SciTech Connect

Including renewable energy resources in integrated resource planning (IRP) requires that utility planning models properly consider the relevant attributes of the different renewable resources in addition to conventional supply-side and demand-side options. Otherwise, a utility`s resource plan is unlikely to have an appropriate balance of the various resource options. The current trend toward regulatory set-asides for renewable resources is motivated in part by the perception that the capabilities of current utility planning models are inadequate with regard to renewable resources. Adequate modeling capabilities and utility planning practices are a necessary prerequisite to the long-term penetration of renewable resources into the electric utility industry`s resource mix. This report presents a review of utility planning models conducted for the National Renewable Energy Laboratory (NREL). The review examines the capabilities of utility planning models to address key issues in the choice between renewable resources and other options. The purpose of this review is to provide a basis for identifying high priority areas for advancing the state of the art.

Logan, D.; Neil, C.; Taylor, A. [RCG/Hagler, Bailly, Inc., Boulder, CO (United States)

1994-06-01T23:59:59.000Z

355

Graphite technology development plan  

Science Conference Proceedings (OSTI)

This document presents the plan for the graphite technology development required to support the design of the 350 MW(t) Modular HTGR within the US National Gas-Cooled Reactor Program. Besides descriptions of the required technology development, cost estimates, and schedules, the plan also includes the associated design functions and design requirements.

NONE

1986-07-01T23:59:59.000Z

356

Transportation Demand Management Plan  

E-Print Network (OSTI)

Transportation Demand Management Plan FALL 2009 #12;T r a n s p o r t a t i o n D e m a n d M a n the transportation impacts the expanded enrollment will have. Purpose and Goal The primary goal of the TDM plan is to ensure that adequate measures are undertaken and maintained to minimize the transportation impacts

357

Environmental Protection Implementation Plan  

SciTech Connect

This Environmental Protection Implementation Plan is intended to ensure that the environmental program objectives of Department of Energy Order 5400.1 are achieved at SNL/California. The Environmental Protection Implementation Plan serves as an aid to management and staff to implement new environmental programs in a timely manner.

Brekke, D.D.

1994-01-01T23:59:59.000Z

358

DISASTER PLAN Library Materials  

E-Print Network (OSTI)

New York: Neal-Schuman; 1992. Kahn, Miriam. Disaster Response and Prevention for Computer And DataDISASTER PLAN Library Materials For the University of Toronto Library System September 2013 disaster planning for archives, libraries and record centres. Second edition. Boston: Scarecrow Press, 2002

Sokolowski, Marla

359

Manufacturing research strategic plan  

SciTech Connect

This plan provides an overall strategic roadmap for the DOE-defense programs advanced manufacturing research program which supports the national science based stockpile stewardship program. This plan represents a vision required to develop the knowledge base needed to ensure an enduring national capability to rapidly and effectively manufacture nuclear weapons.

1995-11-01T23:59:59.000Z

360

Program Operations Plan  

SciTech Connect

The Department of Energy's Atmospheric Chemistry Program (ACP) was initiated in 1991 to coordinate DOE's university and federal-laboratory atmospheric-chemistry research, and to focus these efforts on national and international information requirements in the atmospheric-chemistry field. This Program Operations Plan describes the structure and vision of the effort designed to fulfill these needs, and is divided into two major components. The first of these is a Strategic Plan, which outlines the ACP's rationale, objectives, and vision, and describes its products that are anticipated over a future ten-year period. Although based on realistic appraisals of goals that are attainable given the financial, material, and intellectual resources of the ACP community, this Strategic Plan does not describe these resources themselves. The second component of the Program Operations Plan, the Implementation Plan, deals directly with these resource considerations. As such it focuses on practical implementation of Strategic-Plan elements at the individual research institutions, the anticipated scientific contributions of these groups, and their coordination within the ACP. In contrast to the Strategic Plan, this Implementation Plan extends only five years into the future.

1993-04-01T23:59:59.000Z

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


361

Industry-Laboratory Partnerships A Review of the Sandia Science and Technology Park Initiative  

Science Conference Proceedings (OSTI)

The ''Sandia'' report summarizes a conference held to review the Sandia Science and Technology Park, its rationale and plans, and to identify potential operational and policy issues.

Wessner, C. W. (Editor)

1999-01-01T23:59:59.000Z

362

PROJECT PLANNING TEMPLATE  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Plan i Issue Date: 4/24/2009 Plan i Issue Date: 4/24/2009 U.S. Department of Energy Office of Engineering and Construction Management Project Plan for the Project Assessment and Reporting System (PARS II) Version 2.0a (Public) April 20, 2009 Submitted by: Energy Enterprises Solutions 20440 Century Blvd. Suite 150 Germantown, MD 20874 Phone 301-916-0050 Fax 301-916-0066 www.eesllc.net PARS II Project Plan ii Issue Date: 4/24/2009 Title Page Document Name: Project Plan for the Project Assessment and Reporting System (PARS II), V2.0a Publication Date: April 24, 2009 Contract Number: DE-AT01-06IM00102 Project Number: 1ME07, CLIN 2 Prepared by: Judith Bernsen, PMC, LLC Kai Mong, Energy Enterprise Solutions, LLC

363

Operational Area Monitoring Plan  

Office of Legacy Management (LM)

' ' SECTION 11.7B Operational Area Monitoring Plan for the Long -Term H yd rol og ical M o n i to ri ng - Program Off The Nevada Test Site S . C. Black Reynolds Electrical & Engineering, Co. and W. G. Phillips, G. G. Martin, D. J. Chaloud, C. A. Fontana, and 0. G. Easterly Environmental Monitoring Systems Laboratory U. S. Environmental Protection Agency October 23, 1991 FOREWORD This is one of a series of Operational Area Monitoring Plans that comprise the overall Environmental Monitoring Plan for the DOE Field Office, Nevada (DOEINV) nuclear and non- nuclear testing activities associated with the Nevada Test Site (NTS). These Operational Area Monitoring Plans are prepared by various DOE support contractors, NTS user organizations, and federal or state agencies supporting DOE NTS operations. These plans and the parent

364

Transportation Institutional Plan  

SciTech Connect

This Institutional Plan is divided into three chapters. Chapter 1 provides background information, discusses the purposes of the Plan and the policy guidance for establishing the transportation system, and describes the projected system and the plans for its integrated development. Chapter 2 discusses the major participants who must interact to build the system. Chapter 3 suggests mechanisms for interaction that will foster wide participation in program planning and implementation and provides a framework for managing and resolving the issues related to development and operation of the transportation system. A list of acronyms and a glossary are included for the reader's convenience. Also included in this Plan are four appendices. Of particular importance is Appendix A, which includes detailed discussion of specific transportation issues. Appendices B, C, and D provide supporting material to assist the reader in understanding the roles of the involved institutions.

1986-08-01T23:59:59.000Z

365

Strong planning under partial observability  

Science Conference Proceedings (OSTI)

Rarely planning domains are fully observable. For this reason, the ability to deal with partial observability is one of the most important challenges in planning. In this paper, we tackle the problem of strong planning under partial observability in ... Keywords: Binary decision diagrams, Heuristic search in belief space, Planning in nondeterministic domains, Planning under partial observability, Symbolic model checking

Piergiorgio Bertoli; Alessandro Cimatti; Marco Roveri; Paolo Traverso

2006-04-01T23:59:59.000Z

366

Reading Through a Plan: A Visual Theory of Plan Interpretation  

E-Print Network (OSTI)

Problem: Planners may read plans often, but the profession continues to view the interpretation of plan content as something that is either too obvious or too unimportant to require explicit discussion. Plans are seldom ...

Ryan, Brent D.

367

LBNL Institutional Plan, FY 1996--2001. Draft  

SciTech Connect

The FY 1996-2001 Institutional Plan provides an overview of the Lawrence Berkeley National Laboratory mission, strategic plan, core business areas, critical success factors, and the resource requirements to fulfill its mission in support of national needs in fundamental science and technology, energy resources, and environmental quality. The Strategic Plan section identifies long-range conditions that will influence the Laboratory, as well as potential research trends and management implications. The Core Business Areas section identifies those initiatives that are potential new research programs representing major long-term opportunities for the Laboratory, and the resources required for their implementation. It also summarizes current programs and potential changes in research program activity, science and technology partnerships, and university and science education. The Critical Success Factors section reviews human resources; work force diversity; environment, safety, and health programs; management practices; site and facility needs; and communications and trust. The Resource Projections are estimates of required budgetary authority for the Laboratory`s ongoing research programs. The Institutional Plan is a management report for integration with the Department of Energy`s strategic planning activities, developed through an annual planning process. The plan identifies technical and administrative directions in the context of the national energy policy and research needs and the Department of Energy`s program planning initiatives. Preparation of the plan is coordinated by the Office for Planning and Communications from information contributed by the Laboratory`s scientific and support divisions.

1995-06-01T23:59:59.000Z

368

Audit Report on Review of the Status of the U.S. Department of...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Review of the Status of the U.S. Department of Energy's Counterintelligence Implementation Plan, DOEIG-0448 Audit Report on Review of the Status of the U.S. Department of Energy's...

369

EMSL Strategic Plan 2008  

SciTech Connect

This Strategic Plan is EMSLs template for achieving our vision of simultaneous excellence in all aspects of our mission as a national scientific user facility. It reflects our understanding of the long-term stewardship we must work toward to meet the scientific challenges of the Department of Energy and the nation. During the next decade, we will implement the strategies contained in this Plan, working closely with the scientific community, our advisory committees, DOEs Office of Biological and Environmental Research, and other key stakeholders. This Strategic Plan is fully aligned with the strategic plans of DOE and its Office of Science. We recognize that shifts in science and technology, national priorities, and resources made available through the Federal budget process create planning uncertainties and, ultimately, a highly dynamic planning environment. Accordingly, this Strategic Plan should be viewed as a living document for which we will continually evaluate changing needs and opportunities posed by our stakeholders (i.e., DOE, users, staff, advisory committees), work closely with them to understand and respond to those changes, and align our strategy accordingly.

Campbell, Allison A.

2008-08-15T23:59:59.000Z

370

Public affairs plan  

SciTech Connect

The purpose of the Uranium Mill Tailings Remedial Action (UMTRA) Project Public Affairs Plan is to establish goals for the Fiscal Year 1995 UMTRA public affairs program and identify specific activities to be conducted during the year. It also describes the roles of various agencies involved in the conduct of the public affairs program and defines the functions of the Technical Assistance Contractor (TAC) Public Affairs Department. It integrates and replaces the Public Participation Plan (DOE/AL/62350-47D) and Public Information Plan (DOE/AL/623590-71). The plan describes the US Department of Energy`s (DOE) plans to keep stakeholders and other members of the public informed about project policies, plans, and activities, and provide opportunities for stakeholders and interested segments of the public to participate in project decision-making processes. The plan applies to the UMTRA Project Office; the DOE Albuquerque Operations Office, Office of Intergovernmental and External Affairs (OIEA); the UMTRA TAC; the UMTRA Remedial Action Contractor (RAC); and other cooperating agencies.

Not Available

1994-09-01T23:59:59.000Z

371

EMSL Contribution Plan  

Science Conference Proceedings (OSTI)

This Contribution Plan is EMSLs template for achieving our vision of simultaneous excellence in all aspects of our mission as a national scientific user facility. It reflects our understanding of the long-term stewardship we must work toward to meet the scientific challenges faced by the Department of Energy (DOE) and the nation. During the next decade, we will implement the strategies contained in this Plan, working closely with the scientific community, our advisory committees, DOEs Office of Biological and Environmental Research, and other key stakeholders. This Plan is fully aligned with the strategic plans of DOE, its Office of Science, and the Pacific Northwest National Laboratory (PNNL). We recognize that shifts in science and technology, national priorities, and resources made available through the Federal budget process create planning uncertainties and, ultimately, a highly dynamic planning environment. Accordingly, this Plan should be viewed as a living document and we continually evaluate the changing needs and opportunities posed by our stakeholders (i.e., DOE, users, staff, advisory committees), work closely with them to understand and respond to those changes, and align our strategy accordingly. This Plan is organized around two sections. Section 1 describes our vision and four strategic outcomes: 1) Scientific Innovation, 2) Capabilities that Transform Science, 3) Outstanding Management and Operations, and Engaged and Proactive Users. These outcomes provide the framework for seven critical actions we must take during the next 3 to 5 years: 1) Establishing leadership in EMSL science themes, 2) building and deploying transformational capabilities, 3) integrating computation with experiment, 4) ensuring EMSLs workforce meets the scientific challenges of the future, 5) creating partnerships, 6) attracting and engaging users in EMSLs long-term strategy, and 7) building a research infrastructure that meets emerging scientific needs. Section 2 describes EMSLs detailed business plan, including an analysis of opportunity, organizational investments, and actionable milestones.

Campbell, Allison A.

2008-12-01T23:59:59.000Z

372

SRP - PowerWise Business Solutions Energy Efficiency Rebate Program...  

Open Energy Info (EERE)

is designed to help architects, engineering professionals and building owners optimize energy savings within commercial new construction projects. To participate, facilities must...

373

SRP - PowerWise Business Solutions Energy Efficiency Rebate Program...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

ton, depending on efficiency of the installed unit VFDs: 55 per hp on controlled HVAC fan and pump motors Refrigeration Measures: Varies widely by application ECM Motors...

374

SRP - EarthWise Solar Energy Incentive Program (Arizona) | Open...  

Open Energy Info (EERE)

Commercial PV: 0.10W Residential solar water heaters: 0.35kWh for 1st year estimated energy savings (based on SRCC rating) Commercial solar water heaters: 0.35kWh for 1st...

375

10-Yr. Transmission Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Power Marketing Rates Power Marketing Rates 10-Yr Transmission Plan 2012 Customer Meeting Announcement Agenda 120611 CRSP South Projects CRSP South PowerPoint Presentation CRSP South 2009-2011 Capitalized Execution CRSP North Projects CRSP North PowerPoint Presentation CRSP North 2009-2011 Capitalized Execution About Power Marketing Transmission Newsroom Business Policies Products Plan contents OASIS News features Careers No FEAR act Organization chart Plan processes Functions News releases Doing business Privacy policy History General power contract provisions OATT Revisions Fact sheets Energy Services Accessibility Financial information Rates and Repayment Interconnection Publications EPTC Adobe PDF Power projects EPAMP Infrastructure projects Federal Register Notices

376

Plan recognition in exploratory domains  

Science Conference Proceedings (OSTI)

This paper describes a challenging plan recognition problem that arises in environments in which agents engage widely in exploratory behavior, and presents new algorithms for effective plan recognition in such settings. In exploratory domains, agents@? ... Keywords: Plan recognition, User modeling

Yaakov Gal; Swapna Reddy; Stuart M. Shieber; Andee Rubin; Barbara J. Grosz

2012-01-01T23:59:59.000Z

377

Guidance for evaluation of operational emergency plans  

Science Conference Proceedings (OSTI)

The purpose of this document is to provide guidance for development of emergency plans for the USDOE Office of Defense Programs, Office of Energy Research, and Office of Environmental Management facilities. It gathers emergency planning policy and guidance from applicable federal regulations, DOE Orders and related guidance documents. This material, along with recommended good practices, is presented as a checklist against which emergency plans can be reviewed by DOE Headquarters. The Office of Emergency Response (DP-23), Office of Environment, Safety and Health Technical Support (ER-8), and Office of Transportation, Emergency Management and Analytical Services (EM-26) will use this checklist to evaluate plans submitted by DP, ER, and EM field elements. The scope of this document encompasses plans for operational emergencies at DOE facilities, both nuclear and non-nuclear. Operational emergencies, as defined in Attachment 2 to DOE Order 5500.1B (April 30, 1991) are ``significant accidents, incidents, events, or natural phenomena which seriously degrade the safety or security of DOE facilities. Operational Emergencies apply to DOE reactors and other DOE facilities (nuclear and non-nuclear) involved with hazardous materials; DOE-controlled nuclear weapons, components, or test devices; DOE safeguards and security events; and transportation accidents involving hazardous materials under DOE control.``

NONE

1995-03-01T23:59:59.000Z

378

COMMUNITY INVOLVEMENT PLAN APRIL 15, 1999.  

Science Conference Proceedings (OSTI)

This Community Involvement Plan has been prepared by the Brookhaven National Laboratory's Community Involvement Office with the input of the community, Laboratory employees and representatives of the U.S. Department of Energy. The process to develop the plan began with the formation of a focus group consisting of representatives from: the community at large; special interest groups within the community; the business community; Laboratory retirees; senior and line management from the Laboratory; and the U.S. Department of Energy. The focus group reviewed an initial outline developed by the Office of Community involvement, held in-depth roundtable discussions of community involvement needs, and created a draft plan based on their discussions. A workshop was held to present the draft Community Involvement Plan to a wider audience for their input and insights on how Brookhaven should involve the community in decision making. This workshop was advertised in local newspapers and within the Laboratory. It was attended by community members, special interest group representatives, Laboratory employees and managers, U.S. Department of Energy-Brookhaven Group management, and members of the Laboratory's Community Advisory Council. The results of the workshop discussions are incorporated in this plan.

GEIGER,K.

1999-04-15T23:59:59.000Z

379

Interconnection Transmission Planning: Awards | Department of...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Interconnection Transmission Planning: Awards Interconnection Transmission Planning: Awards List of Interconnection Transmission Planning awards under the American Recovery and...

380

Independent Oversight Review, Nevada National Security - May 2013 |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

National Security - May 2013 National Security - May 2013 Independent Oversight Review, Nevada National Security - May 2013 May 2013 Review of the Nevada National Security Site Criticality Safety Program Corrective Action Plan Closure The U.S. Department of Energy (DOE) Office of Enforcement and Oversight (Independent Oversight), within the Office of Health, Safety and Security, conducted an independent review of the National Nuclear Security Administration (NNSA) Nevada Field Office (NFO) and National Security Technologies, LLC (NSTec) concurrent assessments to confirm the level of compliance with the closure actions of the NSTec corrective action plan (CAP) for nuclear criticality safety. Independent Oversight Review, Nevada National Security - May 2013 More Documents & Publications

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


381

Annual Training Plan Template | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Plan Template Annual Training Plan Template The Annual Training Plan Template is used by an organization's training POC to draft their organization's annual training plan. The...

382

WIPP - Passive Institutional Controls (PICs) Plans  

NLE Websites -- All DOE Office Websites (Extended Search)

Plans Files below are in PDF format and can be viewed with Adobe Acrobat Reader. PICs Implementation Plan Permanent Markers Implementation Plan Permanent Markers Testing Plan...

383

Microsoft Word - PeerReview_CCSP.doc  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

the Peer Review of the U.S. Climate Change Science Program the Peer Review of the U.S. Climate Change Science Program Synthesis and Assessment Report entitled 'Climate Models: An Assessment of Strengths and Limitations for User Applications' Pursuant to Section V of the "Information Quality Bulletin for Peer Review" of the Office of Management and Budget (OMB), under the authority of the Information Quality Act of 2000 (P.L. 106-554), the U.S. Climate Change Science Program (CCSP) announces a plan for the peer review of its Synthesis and Assessment Report entitled 'Climate Models: An Assessment of Strengths and Limitations for User Applications'. The CCSP is an interagency research, planning, and coordinating entity that integrates federal research on climate and global change, as sponsored by thirteen federal agencies and overseen by the Office of Science and Technology

384

NRRI summary of Texas Utility Commission staff analysis of the incentive regulation plan established in Docket No. 8585: The first three years  

Science Conference Proceedings (OSTI)

A Texas Public Utility Commission Staff review of Southwestern Bell Telephone Company of Texas` (SWBT of Texas) incentive regulation plan (the Plan) yielded mixed results. The evaluation of the Plan found that it provided benefits to Texas ratepayers, yet, as with any experiment, there have been both successes and failures in different aspects of the Plan.

NONE

1995-12-31T23:59:59.000Z

385

Analytical Review  

DOE Green Energy (OSTI)

ANL Performs Independent Review for DOE on the following topics: (1) Systematic analysis--Depends on question asked; (2) Compare technologies and pathways--Examples: (a) fuels, power plant technologies, vehicle materials; (b) Total lifecycle analysis reveals national and global impacts; and (3) Direction of R&D to most fruitful areas.

Frank Stodolsky

2000-04-11T23:59:59.000Z

386

Building Technologies Office: Strategic Plans  

NLE Websites -- All DOE Office Websites (Extended Search)

Strategic Plans to Strategic Plans to someone by E-mail Share Building Technologies Office: Strategic Plans on Facebook Tweet about Building Technologies Office: Strategic Plans on Twitter Bookmark Building Technologies Office: Strategic Plans on Google Bookmark Building Technologies Office: Strategic Plans on Delicious Rank Building Technologies Office: Strategic Plans on Digg Find More places to share Building Technologies Office: Strategic Plans on AddThis.com... About Take Action to Save Energy Partner With DOE Activities Solar Decathlon Building America Research Innovations Research Tools Building Science Education Climate-Specific Guidance Solution Center Partnerships Meetings Publications Home Energy Score Home Performance with ENERGY STAR Better Buildings Neighborhood Program Challenge Home

387

Integrated Planning and Performance Management  

NLE Websites -- All DOE Office Websites (Extended Search)

Performance Management (IPPM) Head Program Administrator Planning Coordination Performance Analysis Chief Operating Officer Risk Analysis Lab PlanningGoal Setting Process ...

388

2011-2020 Strategic Plan  

Energy.gov (U.S. Department of Energy (DOE))

LM has completed its 2011-2020 Strategic Plan. The new plan provides our organization with clear directions for the future.

389

Waste Minimization Plan Prepared by  

E-Print Network (OSTI)

Waste Minimization Plan Prepared by: Environmental Health and Safety Department Revised February 2012 #12;Waste Minimization Plan Table of Contents Policy Statement........................................................... 3 Centralized Waste Management Program

390

Emergency Action Plan (EAP) Template  

NLE Websites -- All DOE Office Websites (Extended Search)

00q09e011.doc i (042013) Local Emergency Plan BUILDING: COMPLEX: ZONE: PLAN APPROVAL DATE: Approved by Name Signature Date Local Emergency Coordinator John Cintorino Facility...

391

STAFF PAPER A Review of Transmission Losses in  

E-Print Network (OSTI)

STAFF PAPER A Review of Transmission Losses in Planning Studies Lana Wong Electricity Analysis Office Electricity Supply Analysis Division California Energy Commission would like to acknowledge the following individuals for providing their insight into transmission

392

Argonne National Laboratory institutional plan FY 2001--FY 2006.  

SciTech Connect

This Institutional Plan describes what Argonne management regards as the optimal future development of Laboratory activities. The document outlines the development of both research programs and support operations in the context of the nation's R and D priorities, the missions of the Department of Energy (DOE) and Argonne, and expected resource constraints. The Draft Institutional Plan is the product of many discussions between DOE and Argonne program managers, and it also reflects programmatic priorities developed during Argonne's summer strategic planning process. That process serves additionally to identify new areas of strategic value to DOE and Argonne, to which Laboratory Directed Research and Development funds may be applied. The Draft Plan is provided to the Department before Argonne's On-Site Review. Issuance of the final Institutional Plan in the fall, after further comment and discussion, marks the culmination of the Laboratory's annual planning cycle. Chapter II of this Institutional Plan describes Argonne's missions and roles within the DOE laboratory system, its underlying core competencies in science and technology, and six broad planning objectives whose achievement is considered critical to the future of the Laboratory. Chapter III presents the Laboratory's ''Science and Technology Strategic Plan,'' which summarizes key features of the external environment, presents Argonne's vision, and describes how Argonne's strategic goals and objectives support DOE's four business lines. The balance of Chapter III comprises strategic plans for 23 areas of science and technology at Argonne, grouped according to the four DOE business lines. The Laboratory's 14 major initiatives, presented in Chapter IV, propose important advances in key areas of fundamental science and technology development. The ''Operations and Infrastructure Strategic Plan'' in Chapter V includes strategic plans for human resources; environmental protection, safety, and health; site and facilities; security, export control, and counterintelligence; information management; communications, outreach, and community affairs; performance-based management; and productivity improvement and overhead cost reduction. Finally, Chapter VI provides resource projections that are a reasonable baseline for planning the Laboratory's future.

Beggs, S.D.

2000-12-07T23:59:59.000Z

393

Policy & Strategic Planning  

NLE Websites -- All DOE Office Websites (Extended Search)

Laboratory Directed R&D Laboratory Directed R&D Office of Technology Commercialization and Partnerships Other Information BNL Site Index Can't View PDFs? Policy & Strategic Planning Directorate Policy and Strategic Planning (P&SP) Directorate coordinates development of the Laboratory Strategic Plan and annual business plans at the institutional and organizational Level. This function includes administration of the Laboratory Directed Research and Development (LDRD) program. The Directorate is also responsible for the Laboratory's technology transfer functions, including collaborations with industry and work for others; and for increasing funding from sources other than DOE. Organization Chart (pdf) Top of Page Last Modified: June 4, 2013 Please forward all questions about this site to: Teresa Baker

394

DOE Retro Analysis Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Retro Analysis Plan Retro Analysis Plan August 2, 2011 Page 1 August 2, 2011 Daniel Cohen, Esq. Office of General Counsel U.S. Department of Energy 1000 Independence Avenue, SW Washington, DC 20585 Re: Preliminary Plan for Retrospective Analysis Dear Mr. Cohen: These comments are submitted by the Air-Conditioning, Heating, and Refrigeration Institute (AHRI) in response to the U.S. Department of Energy's (DOE) notice appearing in the July 11, 2011 Federal Register requesting comments on the Preliminary Plan for Retrospective Analysis of Existing Rules. We are encouraged by DOE's efforts to implement Executive Order 13563. We appreciate the actions already taken by DOE to address our concerns regarding the Final Rule on Certification, Compliance, and Enforcement Regulations for Consumer Products and Commercial and

395

Plan Your School Visit  

NLE Websites -- All DOE Office Websites (Extended Search)

Plan Your School Visit Plan Your School Visit For Teachers Teachers Visit the Museum We Visit You Teacher Resources Home Schoolers Plan Your School Visit invisible utility element Plan Your School Visit Chaperones To ensure that your students have the best possible experience at the Museum, we ask that you provide one chaperone for every 6 children. The chaperones should stay with their assigned group of students throughout the entire visit and model positive behavior. General Before arriving at the Museum, please remind your students about the following guidelines: If possible, leave food and drinks on the bus. Respect other visitors in the Museum by using inside voices, walking, etc. Please be gentle with the exhibits. Cameras are welcome at the Bradbury Science Museum. Have fun! Upon your arrival

396

Milestone Plan Process Improvement  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Milestone Plan Process Improvement Milestone Plan Process Improvement Milestone Plan Process Improvement Background In response to our community's concern over the milestone plan (MP) process within the system, the STRIPES Project Office initiated an in-depth evaluation of the required steps and issues surrounding this process. We concluded that the MP process could be improved for most users by tuning the system configuration. With the approval of both the STRIPES Executive Steering Committee and the STRIPES Project Office, we launched the MP Process Improvement Initiative. After many meetings with members of the STRIPES Team and Working Group, we are ready to "go-live" with this initiative. On October 1 st , 2012 the new MP process will be implemented for use by most field offices.

397

Milestone Plan Process Improvement  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

to our community's concern over the milestone plan (MP) process within the system, the STRIPES Project Office initiated an in-depth evaluation of the required steps and issues...

398

Environmental Monitoring Plan  

Science Conference Proceedings (OSTI)

This Environmental Monitoring Plan was written to fulfill the requirements of Department of Energy (DOE) Order 5400.1 and DOE Environmental Regulatory Guide DOE/EH 0173T. This Plan documents the background, organizational structure, and methods used for effluent monitoring and environmental surveillance at Sandia National Laboratories/California. The design, rationale, and historical results of the environmental monitoring system are discussed in detail. Throughout the Plan, recommendations for improvements to the monitoring system are made. This revision to the Environmental Monitoring Plan was written to document the changes made to the Monitoring Program during 1992. Some of the data (most notably the statistical analyses of past monitoring data) has not been changed.

Holland, R.C. [Science Applications International Corp., San Diego, CA (United States)

1993-07-01T23:59:59.000Z

399

TECHNOLOGY PROGRAM PLAN  

NLE Websites -- All DOE Office Websites (Extended Search)

TURBINES U.S. DEPARTMENT OF ENERGY TECHNOLOGY PROGRAM PLAN PREfACE ii DISCLAIMER This report was prepared as an account of work sponsored by an agency of the United States...

400

TECHNOLOGY PROGRAM PLAN  

NLE Websites -- All DOE Office Websites (Extended Search)

SEPTEMBER 2013 CARBON STORAGE U.S. DEPARTMENT OF ENERGY TECHNOLOGY PROGRAM PLAN PREfACE ii DISCLAIMER This report was prepared as an account of work sponsored by an agency of the...

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


401

TECHNOLOGY PROGRAM PLAN  

NLE Websites -- All DOE Office Websites (Extended Search)

SOLID OXIDE FUEL CELLS U.S. DEPARTMENT OF ENERGY TECHNOLOGY PROGRAM PLAN PREFACE ii DISCLAIMER This report was prepared as an account of work sponsored by an agency of the United...

402

Environmental Implementation Plan  

SciTech Connect

The purpose of the Environmental Implementation Plan (EIP) is to show the current and future (five years) environmental plans from individual site organizations and divisions, as well as site environmental programs and initiatives which are designed to protect the environment and meet or exceed changing environmental/regulatory requirements. Communicating with site organizations, departments, and committees is essential in making the site's environmental-planning process work. The EIP gives the site the what, when, how, and why for environmental requirements. Through teamwork and proactive planning, a partnership for environmental excellence is formed to achieve the site vision for SRS to become the recognized model for Environmental Excellence in the Department of Energy's Nuclear Weapons Complex.

Not Available

1993-03-15T23:59:59.000Z

403

Climate Action Plan (Maine)  

Energy.gov (U.S. Department of Energy (DOE))

In June 2003, the Maine State Legislature passed a bill charging the Department of Environmental Protection (DEP) with developing an action plan with the goal of reducing greenhouse gas (GHG)...

404

Environmental Implementation Plan  

SciTech Connect

The purpose of the Environmental Implementation Plan (EIP) is to show the current and future (five years) environmental plans from individual site organizations and divisions, as well as site environmental programs and initiatives which are designed to protect the environment and meet or exceed changing environmental/regulatory requirements. Communicating with site organizations, departments, and committees is essential in making the site`s environmental-planning process work. The EIP gives the site the what, when, how, and why for environmental requirements. Through teamwork and proactive planning, a partnership for environmental excellence is formed to achieve the site vision for SRS to become the recognized model for Environmental Excellence in the Department of Energy`s Nuclear Weapons Complex.

1993-03-15T23:59:59.000Z

405

Environmental Implementation Plan  

SciTech Connect

The purpose of the Environmental Implementation Plan (EIP) is to show the current and future (five years) environmental plans from individual site organizations and divisions, as well as site environmental programs and initiatives which are designed to protect the environment and meet or exceed changing environmental/regulatory requirements. Communicating with site organizations, departments, and committees is essential in making the site's environmental-planning process work. The EIP gives the site the what, when, how, and why for environmental requirements. Through teamwork and proactive planning, a partnership for environmental excellence is formed to achieve the site vision for SRS to become the recognized model for Environmental Excellence in the Department of Energy's Nuclear Weapons Complex.

1993-03-15T23:59:59.000Z

406

Climate Action Plan (Delaware)  

Energy.gov (U.S. Department of Energy (DOE))

The Delaware Climate Change Action Plan (DCCAP) was prepared with funding from the Delaware State Energy Office and the U.S. Environmental Protection Agencys State and Local Climate Change Program...

407

Climate Action Plan (Maryland)  

Energy.gov (U.S. Department of Energy (DOE))

On April 20, 2007, Governor Martin OMalley signed Executive Order 01.01.2007.07 establishing the Maryland Climate Change Commission (MCCC) charged with collectively developing an action plan to...

408

EMSL 2006 Strategic Plan  

SciTech Connect

The 2006 EMSL Strategic Plan describes the elements of EMSLs 5-year strategy to provide outstanding value to its user community and to meet evolving goals of the DOE Office of Biological Research.

Campbell, Allison A.

2005-12-21T23:59:59.000Z

409

Environmental Management System Plan  

E-Print Network (OSTI)

3) environmental management programs, (4) training, (5)Management Programs3-5 Structure and Responsibility.3-6 Training,Management System Plan Program Elements Additional information regarding EMS training

Fox, Robert

2009-01-01T23:59:59.000Z

410

Regional hydrothermal commercialization plan  

SciTech Connect

This plan for the Rocky Mountain Basin and Range Region articulates the complete range of initiatives (federal, state, local, and industrial) required for the early commercialization of the regions geothermal resources. (MHR)

1978-07-14T23:59:59.000Z

411

WESTERN UNIVERSITY Disaster Plan  

E-Print Network (OSTI)

.7 Assumptions 1.7.1 Emergency 1.7.2 Disaster 1.8 Concept of Operations 1.8.1 Background 1.8.2 Emergency Response/Administrative Unit Responsibilities 1.8.8 Situation Reports 2. UTILIZING THE DISASTER PLAN 2.1 Emergency Process Members ­ Individual Responsibilities #12;WESTERN UNIVERSITY Disaster Plan January, 2013 2.7.1 VP

Sinnamon, Gordon J.

412

Environmental protection Implementation Plan  

SciTech Connect

This ``Environmental Protection Implementation Plan'' is intended to ensure that the environmental program objectives of Department of Energy Order 5400.1 are achieved at SNL/California. This document states SNL/California's commitment to conduct its operations in an environmentally safe and responsible manner. The ``Environmental Protection Implementation Plan'' helps management and staff comply with applicable environmental responsibilities.

R. C. Holland

1999-12-01T23:59:59.000Z

413

Book Review of Electrolytes...  

Science Conference Proceedings (OSTI)

Book Review of Electrolytes. Properties of Solutions. ... We review the book entitled, "Electrolytes. Properties of Solutions. ...

414

International Photovoltaic Program Plan  

SciTech Connect

The International Photovoltaics Program Plan is in direct response to the Solar Photovoltaic Energy Research, Development, and Demonstration Act of 1978 (PL 95-590). As stated in the Act, the primary objective of the plan is to accelerate the widespread use of photovoltaic systems in international markets. Benefits which could result from increased international sales by US companies include: stabilization and expansion of the US photovoltaic industry, preparing the industry for supplying future domestic needs; contribution to the economic and social advancement of developing countries; reduced world demand for oil; and improvements in the US balance of trade. The plan outlines programs for photovoltaic demonstrations, systems developments, supplier assistance, information dissemination/purchaser assistance, and an informaion clearinghouse. Each program element includes tactical objectives and summaries of approaches. A program management office will be established to coordinate and manage the program plan. Although the US Department of Energy (DOE) had the lead responsibility for preparing and implementing the plan, numerous federal organizations and agencies (US Departments of Commerce, Justice, State, Treasury; Agency for International Development; ACTION; Export/Import Bank; Federal Trade Commission; Small Business Administration) were involved in the plan's preparation and implementation.

Costello, D.; Koontz, R.; Posner, D.; Heiferling, P.; Carpenter, P.; Forman, S.; Perelman, L.

1979-12-01T23:59:59.000Z

415

International Photovoltaic Program Plan  

DOE Green Energy (OSTI)

The International Photovoltaics Program Plan is in direct response to the Solar Photovoltaic Energy Research, Development, and Demonstration Act of 1978 (PL 95-590). As stated in the Act, the primary objective of the plan is to accelerate the widespread use of photovoltaic systems in international markets. Benefits which could result from increased international sales by US companies include: stabilization and expansion of the US photovoltaic industry, preparing the industry for supplying future domestic needs; contribution to the economic and social advancement of developing countries; reduced world demand for oil; and improvements in the US balance of trade. The plan outlines programs for photovoltaic demonstrations, systems developments, supplier assistance, information dissemination/purchaser assistance, and an informaion clearinghouse. Each program element includes tactical objectives and summaries of approaches. A program management office will be established to coordinate and manage the program plan. Although the US Department of Energy (DOE) had the lead responsibility for preparing and implementing the plan, numerous federal organizations and agencies (US Departments of Commerce, Justice, State, Treasury; Agency for International Development; ACTION; Export/Import Bank; Federal Trade Commission; Small Business Administration) were involved in the plan's preparation and implementation.

Costello, D.; Koontz, R.; Posner, D.; Heiferling, P.; Carpenter, P.; Forman, S.; Perelman, L.

1979-12-01T23:59:59.000Z

416

Independent technical review of the Pinellas Plant  

Science Conference Proceedings (OSTI)

This report documents an Independent Technical Review (ITR) of facilities, organizations, plans, activities and various other elements required to successfully transition the Pinellas Plant from Defense Program (DP) funded operation to either community developed reuse or safe deactivation leading to decontamination and decommissioning (D&D). The review was conducted at the request of the Department of Energy (DOE) Deputy Assistant Secretary for Facility Transition and Management (EM-60) and is a consensus of the nine member ITR Team.

Not Available

1994-07-01T23:59:59.000Z

417

Technology Review  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Earth Nation Earth Nation Biomass Feasibility Study DOE Award DE-EE0005635 November 16, 2012 Jerome Lhotka, Director, Economic Development Mike Triplett, Planner White Earth Nation Presentation Overview * Study Objectives * Accomplishments to Date * Initial Findings * Observations * Plans Forward 2 Study Objectives * Primary Objectives: * Conduct a due diligence grade feasibility study to assess the opportunity to convert existing thermal and power systems at the Shooting Star Casino to a sustainable bioenergy system. * Background * The Casino is utilizing fuel oil and propane fired boilers as primary source of thermal energy. Electricity is provided by the local public utility district (Otter Tail Power). * Implementation Schedule: * Start - May 2012

418

First Nations Community Planning Model [EDRA / Places Awards, 2003 -- Planning  

E-Print Network (OSTI)

EDRA/Places planning awards should principally recognizeoutcomes. But others felt the awards should also recognize

Moffat, David

2004-01-01T23:59:59.000Z

419

Municipal Waste Planning, Recycling and Waste Reduction Act (Pennsylvania)  

Open Energy Info (EERE)

Waste Planning, Recycling and Waste Reduction Act (Pennsylvania) Waste Planning, Recycling and Waste Reduction Act (Pennsylvania) No revision has been approved for this page. It is currently under review by our subject matter experts. Jump to: navigation, search Last modified on February 13, 2013. EZFeed Policy Place Pennsylvania Name Municipal Waste Planning, Recycling and Waste Reduction Act (Pennsylvania) Policy Category Other Policy Policy Type Environmental Regulations Affected Technologies Biomass/Biogas, Coal with CCS, Concentrating Solar Power, Energy Storage, Fuel Cells, Geothermal Electric, Hydroelectric, Hydroelectric (Small), Natural Gas, Nuclear, Solar Photovoltaics, Wind energy Active Policy Yes Implementing Sector State/Province Program Administrator Pennsylvania Department of Environmental Protection

420

Notice of Availability of Preliminary Plan for Retrospective Analysis of  

NLE Websites -- All DOE Office Websites (Extended Search)

Availability of Preliminary Plan for Retrospective Availability of Preliminary Plan for Retrospective Analysis of Existing Rules Notice of Availability of Preliminary Plan for Retrospective Analysis of Existing Rules Through this notice, the Department of Energy (DOE) announces the availability of its preliminary plan for retrospective analysis of existing rules to make the agency's regulatory program more effective and less burdensome in achieving its regulatory objectives. As part of its implementation of Executive Order 13563, ''Improving Regulation and Regulatory Review,'' issued by the President on January 18, 2011, DOE sought public comments on whether any of its existing regulations should be modified, streamlined, expanded, or repealed. DOE has considered these comments in the development of its preliminary plan.

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


421

Notice of Availability of Preliminary Plan for Retrospective Analysis of  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Notice of Availability of Preliminary Plan for Retrospective Notice of Availability of Preliminary Plan for Retrospective Analysis of Existing Rules Notice of Availability of Preliminary Plan for Retrospective Analysis of Existing Rules Through this notice, the Department of Energy (DOE) announces the availability of its preliminary plan for retrospective analysis of existing rules to make the agency's regulatory program more effective and less burdensome in achieving its regulatory objectives. As part of its implementation of Executive Order 13563, ''Improving Regulation and Regulatory Review,'' issued by the President on January 18, 2011, DOE sought public comments on whether any of its existing regulations should be modified, streamlined, expanded, or repealed. DOE has considered these comments in the development of its preliminary plan.

422

title Survey of Western U S Electric Utility Resource Plans  

NLE Websites -- All DOE Office Websites (Extended Search)

Survey of Western U S Electric Utility Resource Plans Survey of Western U S Electric Utility Resource Plans journal Energy Policy year month abstract p We review long term electric utility plans representing nbsp textquoteright of generation within the Western U S and Canadian provinces nbsp We nbsp address what utility planners assume about future growth of electricity demand and supply what types of risk they consider in their long term resource planning and the consistency in which they report resource planning related data The region is anticipated to grow by annually by before Demand Side Management nbsp About nbsp two thirds of nbsp the utilities that provided an annual energy forecast also nbsp reported energy efficiency savings projections in aggregate they anticipate an average reduction in energy and nbsp reduction in

423

Electrical Safety Assessment Plan--NNSA/NSO IOD Facility Representative,  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Electrical Safety Assessment Plan--NNSA/NSO IOD Facility Electrical Safety Assessment Plan--NNSA/NSO IOD Facility Representative, 12/03 Electrical Safety Assessment Plan--NNSA/NSO IOD Facility Representative, 12/03 An assessment of the Electrical Safety (ES) program at XXXX was conducted during the week of December XX-XX, 2003. The assessment team evaluated the program using the programmatic areas and specific Lines of Inquiry (LOI) contained in the approved Assessment plan provided. The team consisted of the Facility Representative from National Nuclear Security Administration, as well as ES, Subject Matter Expert support. The assessment plan identified 5 areas of review for Electrical Safety. An integrated process has been established to ensure electrical safety hazards are identified and that adequate controls are defined and

424

EERE Corporate-Level Documents for Plans, Implementation, and Results |  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

EERE Corporate-Level Documents for Plans, Implementation, and EERE Corporate-Level Documents for Plans, Implementation, and Results EERE Corporate-Level Documents for Plans, Implementation, and Results The Office of Energy Efficiency and Renewable Energy (EERE) carries out technology research, development, and deployment through an ongoing process of planning and analysis, implementation, and review. This page includes documents that support EERE's overall, corporate-level program management process, and the results and public benefits that derive from it. EERE Overview Plans Implementation Results EERE Overview EERE works to strengthen the United States' energy security, environmental quality, and economic vitality in public-private partnerships. It supports this goal through (1) enhancing energy efficiency and productivity; and (2)

425

Microsoft Word - PeerReview_SAR.doc  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

a Peer Review of a "Synthesis and Assessment Report on a Peer Review of a "Synthesis and Assessment Report on Scenarios of Greenhouse Gas Emissions and Atmospheric Concentrations and Review of Integrated Scenario Development and Application" Pursuant to Section V of the "Information Quality Bulletin for Peer Review" of the Office of Management and Budget (OMB), under the authority of the Information Quality Act of 2000 (P.L. 106-554), the U.S. Climate Change Science Program (CCSP) announces a plan for a peer review of its Synthesis and Assessment Report 2.1 entitled "Scenarios of Greenhouse Gas Emissions and Atmospheric Concentrations and Review of Integrated Scenario Development and Application" The CCSP (see http://www.climatescience.gov for details) integrates federal

426

Independent Oversight Focused Program Review, Argonne National  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Focused Program Review, Argonne National Focused Program Review, Argonne National Laboratory-West - May 2001 Independent Oversight Focused Program Review, Argonne National Laboratory-West - May 2001 May 2001 Focused Program Review at Argonne National Laboratory-West The U.S. Department of Energy (DOE) Office of Emergency Management Oversight, within the Secretary of Energy's Office of Independent Oversight and Performance Assurance, conducted a focused review of the emergency management program at Argonne National Laboratory-West (ANL-W) in May 2001. There were two primary objectives for this review: to evaluate the extent to which the emergency planning hazards assessment (EPHA) document serves as an effective foundation for the ANL-W emergency management program, and to determine whether the necessary interfaces have been established among

427

Generalizing GraphPlan by Formulating Planning as a CSP  

E-Print Network (OSTI)

We examine the approach of encoding planning problems as CSPs more closely. First we present a simple CSP encoding for planning problems and then a set of transformations that can be used to eliminate variables and add new constraints to the encoding. We show that our transformations uncover additional structure in the planning problem, structure that subsumes the structure uncovered by GRAPHPLAN planning graphs. We solve the CSP encoded planning problem by using standard CSP algorithms. Empirical evidence is presented to validate the effectiveness of this approach to solving planning problems, and to show that even a prototype implementation is more effective than standard GRAPHPLAN. Our prototype is even competitive with far more optimized planning graph based implementations. We also demonstrate that this approach can be more easily lifted to more complex types of planning than can planning graphs. In particular, we show that the approach can be easily extended to planning with resources.

Adriana Lopez; Fahiem Bacchus

2003-01-01T23:59:59.000Z

428

Summary of Market Assessment of Upcoming Planned Refinery Outages  

Gasoline and Diesel Fuel Update (EIA)

Summary of Market Assessment of Upcoming Planned Refinery Outages Summary of Market Assessment of Upcoming Planned Refinery Outages Summary of Market Assessment of Upcoming Planned Refinery Outages Market Assessment of Upcoming Planned Refinery Outages, December 2008 - March 2009 reviews planned U.S. refinery outages from December 2008 though March 2009 in order to identify any regions where outages might create enough supply pressure to impact prices significantly. As required under Section 804 of the Energy Independence and Security Act of 2007 (Pub. L. 110-140), this report reviews the supply implications of planned refinery outages for December 2008 through March 2009, which covers the winter period when demand for distillate fuels (diesel and heating oil) is high. As a result, emphasis in this report is on distillate rather than gasoline. Refinery outages are the result of planned maintenance and unplanned outages. Maintenance is usually scheduled during the times when demand is lowest - in the first quarter and again in the fall. Unplanned outages, which occur for many reasons including mechanical failures, fires, and flooding, can occur at any time.

429

Operations, Maintenance, and Replacement 10-Year Plan, 1990 -1999.  

SciTech Connect

In 1988 Bonneville Power Administration (BPA) began work on this Operations, Maintenance, and Replacement 10-Year Plan to develop a levelized program that would assure high system reliability. During the Programs in Perspective (PIP) meetings in the late summer and fall of 1988, many of the concerns to be addressed in an Operations, Maintenance, and Replacement Plan were identified. Following these PIP meetings BPA established internal work groups. During the winter and spring of 1989, these work groups developed technical background and issue papers on topics that ranged from substation maintenance to environmental protection. In addition, a customer forum group was established and met on several occasions to review work on the plan, to offer ideas and points of view, and to assure that BPA understood customer concerns. Based on recommendations from the work group reports and customer input, BPA's O M Management Team developed the draft Operations, Maintenance, and Replacement 10-Year Plan that was released for public comment during the spring of 1990. During the public review period, BPA received a number of written comments from customers and the interested public. In addition, special meetings were held with interested customers. This final Operations, Maintenance, and Replacement 10-Year Plan reflects BPA's response to customers and interested public on each topic discussed in the 10-Year Plan. The plan is a distillation of BPA's strategies to achieve a levelized program over 10 years.

United States. Bonneville Power Administration.

1990-08-01T23:59:59.000Z

430

Operations, Maintenance, and Replacement 10-Year Plan, 1990--1999  

SciTech Connect

In 1988 Bonneville Power Administration (BPA) began work on this Operations, Maintenance, and Replacement 10-Year Plan to develop a levelized program that would assure high system reliability. During the Programs in Perspective (PIP) meetings in the later summer and fall of 1988, many of the concerns to be addressed in an Operations, Maintenance, and Replacement Plan were identified. Following these PIP meetings BPA established internal work groups. During the winter and spring of 1989, these work groups developed technical background and issue papers on topics that ranged from substation maintenance to environmental protection. In addition, a customer forum group was established and met on several occasions to review work on the plan, to offer ideas and points of view, and to assure that BPA understood customer concerns. Based on recommendations from the work group reports and customer input, BPA's O M Management Team developed the draft Operations, Maintenance, and Replacement 10-Year Plan that was released for public comment during the spring of 1990. During the public review period, BPA received a number of written comments from customers and the interested public. In addition, special meetings were held with interested customers. This final Operations, Maintenance, and Replacement 10-year Plan reflects BPA's response to customers and interested public on each topic discussed in the 10-Year Plan. The plan is a distillation of BPA's strategies to achieve a levelized program over 10 years.

Not Available

1990-08-01T23:59:59.000Z

431

A Review  

NLE Websites -- All DOE Office Websites (Extended Search)

Review Review of BNL Direct-Wind Superconducting IR Magnet Experience 30th Advanced ICFA Beam Dynamics Workshop on High Luminosity e+e - Collisions October 13-16, 2003 Stanford, California Presented by Brett Parker for the Brookhaven Superconducting Magnet Division * Overview of Past and Current Projects. - HERA-II Luminosity Upgrade IR Magnets. - NLC Superconducting Final Focus Magnets. - BEPC-II Luminosity Upgrade IR Magnets. * Winding Technology Overview. - New Types of "Serpentine" Coil Windings. - Winding Test of BEPC-II Serpentine Coil. * Some Issues Relevant for Super B-Factory. - Cryostat & Warm Bore Allowance. - Quadrupole Coil Layout Options. - Magnetic Length Vs. Slot Length. - Dipole Torque Considerations. " A R e v i e w o f B N L D i r e c t - W i n d Superconducting IR Magnet Experience." HERA-II GO Magnet Installed in H1 BNL Winding Machine Stainless

432

Protocol, Development and Maintenance of Criteria and Review Approach  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Development and Maintenance of Criteria and Review Development and Maintenance of Criteria and Review Approach Documents - July 2013 Protocol, Development and Maintenance of Criteria and Review Approach Documents - July 2013 July 2013 Protocol for the Development and Maintenance of Criteria and Review Approach Documents The purpose of this protocol is to establish the requirements and responsibilities for the development and maintenance of Criteria and Review Approach Documents (CRADs) used by the Office of Safety and Emergency Management Evaluations (HS-45). The HS-45 CRADS are carefully selected, modified (if required), and referenced in HS-45 appraisal plans. These plans are used to provide an outline of the activities planned to assess the effectiveness of safety and emergency management processes and

433

CMS System Security Plan Template  

Science Conference Proceedings (OSTI)

System Security Plan (SSP) Template Instructions. This template contains boiler plate language. Each template must be ...

2009-06-30T23:59:59.000Z

434

Environmental Implementation Plan  

SciTech Connect

The Environmental Implementation Plan (EIP) is a dynamic long-range environmental-protection plan for SRS. The EIP communicates the current and future (five year) environmental plans from individual organizations and divisions as well as site environmental initiatives which are designed to protect the environment and meet or exceed compliance with changing environmental/ regulatory requirements. Communication with all site organizations is essential for making the site environmental planning process work. Demonstrating environmental excellence is a high priority embodied in DOE and WSRC policy. Because of your support and participation in the three EIP initiatives; Reflections, Sectional Revision, and Integrated Planning, improvements are being made to the EIP and SRS environmental protection programs. I appreciate the ``Partnership in Environmental Excellence`` formed by the environmental coordinators and professionals who work daily toward our goal of compliance and environmental excellence. I look forward to seeing continued success and improvement in our environmental protection programs through combined efforts of all site organizations to protect our employees, the public health, and the environment. Together, we will achieve our site vision for SRS to be the recognized model for Environmental Excellence in the DOE Nuclear Weapons Complex.

1994-02-01T23:59:59.000Z

435

Draft Transportation Institutional Plan  

SciTech Connect

The Department of Energy recognizes that the success of its program to develop and implement a national system for nuclear waste management and disposal depends on broad-based public understanding and acceptance. While each program element has its particular sensitivity, the transportation of the waste may potentially affect the greatest number of people, and accordingly is highly visible and potentially issue-laden. Therefore, the Office of Civilian Radioactive Waste Management has developed this Transportation Institutional Plan to lay the foundation for interaction among all interested parties for the purpose of identifying and resolving issues of concern. The Plan is divided into four chapters. Chapter 1 provides bachground information and discusses the purpose of the Plan and the policy guidance for establishing the transportation system. Chapter 2 introduces the major participants who must interact to build both the system itself and the consensus philosophy that is essential for effective operations. Chapter 3 suggests mechanisms for interaction that will ensure wide participation in program planning and implementation. And, finally, Chapter 4 suggests a framework for managing and resolving the issues related to development and operation of the transportation system. A list of acronyms and a glossary are included for the reader's convenience. The Plan's appendices provide supporting material to assist the reader in understanding the roles of the involved institutions. 4 figs., 1 tab.

1985-09-01T23:59:59.000Z

436

Review of Plans and Methods | Open Energy Information  

Open Energy Info (EERE)

and Policies International Clean Energy Analysis Low Emission Development Strategies Oil & Gas Smart Grid Solar U.S. OpenLabs Utilities Water Wind Page Actions View source History...

437

DOE Retrospective Review Plan and Burden Reduction Report  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

if their product or equipment cannot be tested under the DOE test procedure, or if testing under the DOE test procedure would evaluate the product or equipment in a manner...

438

Climate Action Planning: A Review of Best Practices, Key Elements...  

Open Energy Info (EERE)

Successes Resource Type Lessons learnedbest practices Availability Publicly available; free Publication Date 20101005 Website http:www.presidentsclimateco Locality Signatories...

439

Review of Utility Resource Plans in the West: Resource Strategies...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Coordination and Implementation DOE Grid Tech Team Energy Assurance Cybersecurity Information Center Congressional Testimony Recovery Act Educational Resources Reporting Library...

440

Independent Scientific Review Panel for the Northwest Power Planning Council  

E-Print Network (OSTI)

. Headquartered in Albuquerque, New Mexico, COMPA has offices in Nevada, California, Idaho, and Washington State, General Sciences, and Operations www.lbl.gov #12;In operation since 1949, Idaho National Laboratory products, and technical training ­ deliver value throughout the complete equipment lifecycle, from system

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


441

Master Plan Review Team Minutes Friday, January 20, 2006  

E-Print Network (OSTI)

Data for New York State by Carl W. Stover and Jerry Coffman, Seismicity of the United States, 1568 water wells went dry. Source: Earthquake Data for New York State by Carl W. Stover and Jerry Coffman of Irondale went dry immediately after the shock, and the water level in many others was lowered. At Pell City

Rhode Island, University of

442

Master Plan Review Team Minutes Thursday, August 25, 2005  

E-Print Network (OSTI)

SRI INTERNATIONAL : DESCRIPTION OF THE TACITUS SYSTE M AS USEI) FOR MUC-3 Jerry R. Hobbs SRI in the MUC-3 effort were Douglas Appelt, John Bear, Jerry Hobbs, David Magerman, An n Podlozny, Mark Stickel Lynn Boyd, William Croft, Todd Davies, Douglas Edwards, Kenneth Laws , Paul Martin, and Barney Pell

Rhode Island, University of

443

City of Dallas- Green Building Expedited Plan Review  

Energy.gov (U.S. Department of Energy (DOE))

The Dallas Green Building Program establishes expedited permitting for green buildings. During Phase 1 of the program (October 1, 2009 - September 30, 2011), applicants must provide a checklist...

444

Review of Commercial Grade Dedication Plans for the Safety Instrumente...  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

... 10 Acronyms BPCS Basic Process Control System CGD Commercial Grade Dedication CHAP Consolidated Hazard Analysis Process...

445

Independent Scientific Review Panel for the Northwest Power Planning Council  

E-Print Network (OSTI)

Riparian Buffer Systems Wasco SWCD Deschutes $67,119 No - Fundable 6 25015 Emergency Flow Augmentation Sponsor Subbasin 2002 Request Response Needed? Page 25036 The Impact of Flow Regulation on Riparian measurements of flow, temperature, channel morphology, riparian condition, and benthic macroinvertebrates

446

Reviewed by The Plan Teams for the Groundfish Fisheries  

E-Print Network (OSTI)

.......................................................................................................................68 Northern fur seal....................................................................................................................75 Harbor seal into summer. June and July storms are less effective mixers because they are weaker and the thermocline has

447

Reviewed by The Plan Teams for the Groundfish Fisheries  

E-Print Network (OSTI)

. The device is a cylindrical rotor surrounded by a mixing bowl. The spinning rotor acts as a mixer EAM potential developed for plutonium by M. Baskes [10]. #12;19 This is important since Pu

448

Review of Commercial Grade Dedication Plans for the Safety Instrumente...  

NLE Websites -- All DOE Office Websites (Extended Search)

of Health, Safety and Security IO InputOutput LAW Low Activity Waste LED Light-Emitting Diode NA-262 NNSA Site Engineering and Project Integration Division NA-266 NNSA WSB...

449

Peer Review Plan Date: 6/27/12  

E-Print Network (OSTI)

Quality and Geochemistry in the Fayetteville Shale Gas Production Area, North-Central Arkansas Subject groundwater in the Fayetteville Shale gas production area in north-central Arkansas. The shallow domestic wells used for sampling are within the Fayetteville Shale. The Fayetteville Shale is an area of ongoing

450

DRAFT Bear Safety Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

Bear Safety Plan June 2010 Bear Safety Plan June 2010 NSA_bsp_Rev9.doc 1 Atmospheric Radiation Measurement Climate Research Facility/ North Slope of Alaska/Adjacent Arctic Ocean (ACRF/NSA/AAO) Bear Safety Plan Background As a major part of DOE's participation in the US Global Change Research Program (USGCRP), the North Slope of Alaska (NSA) and Adjacent Arctic Ocean (AAO) Climate Research Facility (ACRF) exists on the North Slope of Alaska with its Central Facility near the town of Barrow. A secondary facility exists at Atqasuk, a town 100km inland from Barrow. Other instrumentation locations in more remote areas on the North Slope may be established in later stages of the project. Polar bears, and to a lesser extent, brown bears (barren ground grizzly) are significant hazards within the ACRF/NSA/AAO

451

PROJECT MANGEMENT PLAN EXAMPLES  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Baselines - Baselines - Performance Baseline Examples Example 34 6.0 PROJECT BASELINE This section presents a summary of the PFP Stabilization and Deactivation Project baseline, which was prepared by an inter- contractor team to support an accelerated planning case for the project. The project schedules and associated cost profiles presented in this section are compared to the currently approved project baseline, as contained in the Facility Stabilization Project Fiscal Year 1999 Multi-Year Work Plan (MYWP) for WBS 1.4 (FDH 1998). These cost and schedule details will provide the basis for a baseline change request that will be processed to revise the MYWP, consistent with the accelerated project plan presented below. 6.1 Project Baseline Overview This section of the IPMP presents the PFP baseline cost and schedule summary. The currently approved PFP Stabilization and

452

Report: Strategic Planning Impacts  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Strategic Planning Impacts Strategic Planning Impacts September 30, 2009 Submitted by the EMAB ARRA Implementation and Oversight Subcommittee Background: EM plans to use the influx of stimulus funding from the American Recovery and Reinvestment Act (ARRA) to fulfill compliance agreements, complete construction projects, and address the program's lower-tier activities such as decontamination and decommissioning (D&D) and soil and groundwater remediation. Using the ARRA funds to reduce the physical size of the EM complex will also help to lower overall lifecycle costs, create jobs, and allow the program to capitalize on its past successes. Implementation of ARRA is a high-visibility endeavor that has the potential to impact the EM base program's day-to-day operations and processes.

453

Customer Service Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Customer Service Plan Department of Energy Customer Service Plan - 2011 1 A Message from the Secretary Over the past two and a half years, the Obama Administration and the Department of Energy have worked to make the federal government more open for the American public and its own employees. Through these efforts, we have significantly expanded the amount and breadth of information available online about our programs and services. We have also transformed the way we communicate with the public by relaunching Energy.gov, making it an interactive, streamlined information platform. In April, President Obama directed federal agencies to take this ongoing effort one step further and establish Customer Service Plans, improving the public's interactions with the

454

MITIGATION ACTION PLAN  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

MITIGATION ACTION PLAN MITIGATION ACTION PLAN KEMPER COUNTY IGCC PROJECT KEMPER COUNTY, MISSISSIPPI U.S. Department of Energy National Energy Technology Laboratory September 2010 2 INTRODUCTION The Department of Energy (DOE) issued a Final Environmental Impact Statement (EIS) for the Kemper County IGCC Project (Project) (DOE/EIS-0409) in May 2010 and a Record of Decision (ROD) in August 2010 (75 FR 51248). The ROD identified commitments to mitigate potential adverse impacts associated with the project. This Mitigation Action Plan (MAP) describes the monitoring and mitigation actions the recipient must implement during the design, construction, and demonstration of the Project. DOE prepared this MAP in accordance with 10 CFR § 1021.331. PURPOSE Section 1021.331 of the DOE regulations implementing NEPA (10 CFR Part 1021) provides

455

INL Executable Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

ID-11383 ID-11383 Revision 2 INL FY 2011 Site Sustainability Plan with the FY 2010 Annual Report December 2010 (This Page Intentionally Left Blank) DOE/ID-11383 Revision 2 INL FY 2011 Site Sustainability Plan with the FY 2010 Annual Report December 2010 Prepared for the U.S. Department of Energy DOE Idaho Operations Office (This Page Intentionally Left Blank) (This Page Intentionally Left Blank) (This Page Intentionally Left Blank) (This Page Intentionally Left Blank) INL FY 2011 Site Sustainability Plan with the FY 2010 Annual Report DOE/ID-11383 Revision 2 December 2010 Approved By: ~~~/ Jeffrey~USseau Fa~ 7 Dlte President and General Manager , - Bechtel BWXT Idaho, LLC Advanced Mixed Waste Treatment Project (This Page Intentionally Left Blank)

456

DOE CONTRACTOR PENSION PLANS  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

1-13 1-13 For use in M&O and non-M&O cost reimbursement solicitations and contracts where work had been previously performed under a DOE M&O contract and the successor Contractor is (a) required to employ all or part of the former Contractor's workforce and sponsors the employee pension and benefit plans; or (b) retains sponsorship of benefit plans that survive performance of the contract work scope. Contracts in this latter category include, but are not limited to, environmental remediation, infrastructure services and other site-specific project completion contracts. DOE-H-1002 EMPLOYEE COMPENSATION: PAY AND BENEFITS (a) Contractor Employee Compensation Plan The Contractor shall submit, for Contracting Officer approval, by (fill-in

457

IT Capital Planning  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

IT Capital Planning IT Capital Planning and Architecture Division (IM-21) Carol Blackston, Director (Acting) IM Organization Structure (as of 1/13/2014) Chief Information Officer (IM-1) Robert Brese Deputy Chief Information Officer Donald Adcock Associate CIO for Cyber Security (IM-30) Paul Cunningham (Acting) Corporate IT Project Management Office (IM-40) Frank Husson, Director Associate CIO for IT Planning, Architecture, and E-Government (IM-20) Russell Pereira (Acting) Associate CIO for Technology Evaluation and Chief Technology Officer (IM-50) Peter Tseronis Associate CIO for IT Corporate Management (IM-10) Sarah Gamage Associate CIO for Energy IT Services (IM-60) Virginia Arreguin Deputy Associate CIO for Cyber Security Paul Cunningham Deputy Associate CIO for Energy IT Services Steve Cox (Acting)

458

Human Capital Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Plan Plan Bea Dukes Melissa Rider AHCP Issues  Decentralization of Contracting Process within DOE  In spite of MA and CFO guidance, the actual (FTE) growth of Acquisition Workforce depends on Program Office and/or site level management Recap of this year's planning process  Thanks for your efforts on the development and consolidation of this year's AHCP  Collaborative effort with most HCA level activities  A few glitches ◦ OMB Template very confusing and required much clarification ◦ Many changes throughout the process  Thanks for your patience ◦ Lesson Learned: SPE, CFO, HC and Program Offices must be in synchronization Fallout  Additional funding called out in FY11 -

459

Optics Supply Planning System  

Science Conference Proceedings (OSTI)

The purpose of this study is to specify the design for an initial optics supply planning system for NIF, and to present quality assurance and test plans for the construction of the system as specified. The National Ignition Facility (NIF) is a large laser facility that is just starting operations. Thousands of specialized optics are required to operate the laser, and must be exchanged over time based on the laser shot plan and predictions of damage. Careful planning and tracking of optic exchanges is necessary because of the tight inventory of spare optics, and the long lead times for optics procurements and production changes. Automated inventory forecasting and production planning tools are required to replace existing manual processes. The optics groups members who are expected to use the supply planning system are the stakeholders for this project, and are divided into three groups. Each of these groups participated in a requirements specification that was used to develop this design. (1) Optics Management--These are the top level stakeholdersk, and the final decision makers. This group is the interface to shot operations, is ultimately responsible for optics supply, and decides which exchanges will be made. (2) Work Center Managers--This group manages the on site optics processing work centers. They schedule the daily work center operations, and are responsible for developing long term processing, equipment, and staffing plans. (3) Component Engineers--This group manages the vendor contracts for the manufacture of new optics and the off site rework of existing optics. They are responsible for sourcing vendors, negotiating contracts, and managing vendor processes. The scope of this analysis is to describe the structure and design details of a system that will meet all requirements that were described by stakeholders and documented in the analysis model for this project. The design specifies the architecture, components, interfaces, and data stores of the system at a level of detail that can be used for construction and deployment. Test and quality assurance plans are also included to insure that the system delivers all requirements when it is built. The design is for an automated forecasting prototype that allocates inventory and processing resources in response to potentially daily changes in the forecasted optics exchanges required to operate NIF. It will automatically calculate future inventory levels and processing rates based on current inventory and projected exchanges, procurements, and capacities. It will include screens that allow users to readily assess the feasibility of the forecast, identify failures to meet the demand, revise input data, and re-run the automated forecast calculation. In addition, the system will automatically retrieve the current exchange demand from an external database. Approved forecasts from the system will automatically update work order plans and procurement plans in the existing inventory and production control database. The timing of optics exchanges affects the forecast of damage and future exchanges, so an approved exchange plan will be fed back to the demand database and be used to calculate the next demand projection. The system will read the demand data and update the forecast and output files daily. This specification has been divided into two parts. This document, Part 1 lays out the major design decisions and specifies the architectural, component, and data structure designs. Part 2 will add interface designs, quality assurance and testing plans, and deployment details.

Gaylord, J

2009-04-30T23:59:59.000Z

460

Energy Organizational Planning  

SciTech Connect

As the Seneca Nation of Indians (SNI) continues to refine and finalize its Strategic Energy Plan, it became necessary to insure that a sustainable organization structure was developed through which the energy program and its initiatives could be nurtured and managed. To that end, SNI undertook a study to thoroughly evaluate the existing organizational structures and assess the requisite changes and/or additions to that framework that would complement the mission of the Strategic Plan. The goal of this study was to analyze, work with staff and leadership and recommend the most effective plan for the development of an organizational framework within which the Seneca could more effectively exercise energy sovereignty control and manage their natural resource assets i.e. develop its own energy resources, meet the current and projected energy needs of their community, and sit at the table with other regional energy providers to deal with issues on a peer-to-peer basis.

Gina C. Paradis; James Yockey; Tracey LeBeau

2009-04-17T23:59:59.000Z

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.


461

IT Capital Planning  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

IT Capital Planning IT Capital Planning and Architecture Division (IM-21) Peter Lenentine, Director IM Organization Structure (as of 12/19/2013) Chief Information Officer (IM-1) Robert Brese Deputy Chief Information Officer Donald Adcock Associate CIO for Cyber Security (IM-30) Paul Cunningham (Acting) Corporate IT Project Management Office (IM-40) Frank Husson, Director Associate CIO for IT Planning, Architecture, and E-Government (IM-20) TheAnne Gordon Technology Evaluation Office (IM-50) Peter Tseronis, Director (Acting) Associate CIO for IT Corporate Management (IM-10) Sarah Gamage Associate CIO for Energy IT Services (IM-60) Virginia Arreguin Deputy Associate CIO for Cyber Security Paul Cunningham Deputy Associate CIO for Energy IT Services John Berthiaume (Acting) Human Capital and Administrative

462

Alaska Strategic Energy Plan and Planning Handbook | Department of Energy  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Alaska Strategic Energy Plan and Planning Handbook Alaska Strategic Energy Plan and Planning Handbook Alaska Strategic Energy Plan and Planning Handbook The Alaska Strategic Energy Plan and Planning Handbook, published by the Office of Indian Energy, is a tool for Alaska Native Villages and communities to use in achieving energy goals in both the near- and long-term. This Handbook intends to help Alaska Native leaders and community members define their unique energy goals and priorities through stakeholder input, dialog, and consensus-building. The Handbook: Provides a step-by-step process that Alaska Native villages and communities may wish to use as a roadmap for discussion and decisions related to strategic energy planning and energy project prioritization Includes blank text boxes for communities to input their own

463

Corporate strategic plan for safeguards and security  

SciTech Connect

Department of Energy (DOE) safeguards and security (S and S) is a team effort, consisting of Field, National Laboratories, Program Office, and Headquarters units cooperating to support the Department`s diverse security needs. As an integral part of the nation`s security structure, the DOE S and S Program regularly supports and works in cooperation with other US Government agencies and private industry to improve the national security posture. Thus, inter- and intra-agency partnerships play an invaluable role in the continuing efforts to integrate and implement improved ways of doing business. Their Corporate Strategic Plan provides a road map to guide, track, and provide feedback for the incorporation and implementation of S and S activities within DOE. Part 1 Planning Framework, describes those overarching factors which influence the planning endeavors. Part 2, Strategic Perspective, outlines where the S and S Program has been and how they will move to the future through core competencies, changing cultural thinking, and implementing their strategies. Part 3, Strategic and Operational Integration, details critical focus areas, strategies, and success indicators designed to enhance inter-agency S and S integration and promote cooperation with external agencies. This Plan will be reviewed annually to ensure it remains supportive and fully-engaged with the nation`s and international security environments.

1997-06-01T23:59:59.000Z

464

EMSL Strategic Plan 2008  

NLE Websites -- All DOE Office Websites (Extended Search)

7753 7753 EMSL Strategic Plan 2008 AA Campbell August 2008 Prepared for the U.S. Department of Energy's Office of Biological and Environmental Research under Contract DE-AC05-76RL01830 Pacific Northwest National Laboratory Richland, Washington 99352 iii Environmental Molecular Sciences Laboratory Strategic Plan Our Mission EMSL, a U.S. Department of Energy national scientific user facility located at Pacific Northwest National Laboratory, provides integrated experimental and computational resources for discovery and technological innovation in the environmental molecular

465

Permanent Markers Implementation Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

WIPP 04-3302 WIPP 04-3302 Permanent Markers Implementation Plan August 19, 2004 United States Department of Energy Waste Isolation Pilot Plant Carlsbad Field Office Carlsbad, New Mexico DOE/WIPP 04-3302 ii Permanent Markers Implementation Plan Waste Isolation Pilot Plant Carlsbad, New Mexico August 19, 2004 Prepared for: Washington Regulatory and Environmental Services an affiliate of Washington TRU Solutions, LLC P.O. Box 2078 Carlsbad, New Mexico 88221 Prepared by: John Hart and Associates, P.A. 2815 Candelaria Road, N.W. Albuquerque, New Mexico 87107 (505) 344-7868 DOE/WIPP 04-3302 iii Table of Contents Table of Contents.................................................................................................

466

Environmental protection implementation plan  

SciTech Connect

This Environmental Protection Implementation Plan is intended to ensure that the environmental program objectives of Department of Energy Order 5400.1 are achieved at SNL/California. This document states SNL/California`s commitment to conduct its operations in an environmentally safe and responsible manner. The Environmental Protection Implementation Plan helps management and staff comply with applicable environmental responsibilities. SNL is committed to operating in full compliance with the letter and spirit of applicable environmental laws, regulations, and standards. Furthermore, SNL/California strives to go beyond compliance with legal requirements by making every effort practical to reduce impacts to the environment to levels as low as reasonably achievable.

Holland, R.C.

1998-03-01T23:59:59.000Z

467

Thermal Stabilization Blend Plan  

SciTech Connect

The Blend Plan was written to identify items stored outside of the 213 MBA that will be moved into the MBA for thermal stabilization processing. Product quality oxide items stored in our vaults are found in Appendix A. A table is included in Appendix A which details the isotopic values for the oxide items and calculates the amount of material of any specific run that can be placed in a product can and maintain the 15 watt limit to meet storage vault specifications. This Revision of the Blend Plan adds items of lesser dose rate to lower the exposure of the workers until additional shielding can be added to the gloveboxes.

RISENMAY, H.R.

2000-04-20T23:59:59.000Z

468

Performance Management Plan  

SciTech Connect

This Performance Management Plan describes the approach for accelerating cleanup activities of U.S. Department of Energy (DOE), National Nuclear Security Administration Nevada Operations Office (NNSA/NV) Environmental Management (EM) Program. This approach accelerates the reduction of risk at NNSA/NV sites while performing the work responsibly, effectively, and more efficiently. In May 2002, NNSA/NV EM and the Nevada Division of Environmental Protection signed a Letter of Intent formalizing an agreement to pursue accelerated risk reduction and cleanup for activities within the State of Nevada. This Performance Management Plan provides the strategic direction for implementing the Letter of Intent.

IT Corporation, Las Vegas, NV

2002-08-21T23:59:59.000Z

469

Plutonium Vulnerability Management Plan  

Science Conference Proceedings (OSTI)

This Plutonium Vulnerability Management Plan describes the Department of Energy`s response to the vulnerabilities identified in the Plutonium Working Group Report which are a result of the cessation of nuclear weapons production. The responses contained in this document are only part of an overall, coordinated approach designed to enable the Department to accelerate conversion of all nuclear materials, including plutonium, to forms suitable for safe, interim storage. The overall actions being taken are discussed in detail in the Department`s Implementation Plan in response to the Defense Nuclear Facilities Safety Board (DNFSB) Recommendation 94-1. This is included as Attachment B.

NONE

1995-03-01T23:59:59.000Z

470

Guam Strategic Energy Plan  

SciTech Connect

Describes various energy strategies available to Guam to meet the territory's goal of diversifying fuel sources and reducing fossil energy consumption 20% by 2020.The information presented in this strategic energy plan will be used by the Guam Energy Task Force to develop an energy action plan. Available energy strategies include policy changes, education and outreach, reducing energy consumption at federal facilities, and expanding the use of a range of energy technologies, including buildings energy efficiency and conservation, renewable electricity production, and alternative transportation. The strategies are categorized based on the time required to implement them.

Conrad, M. D.

2013-07-01T23:59:59.000Z

471

PICs Implementation Plan  

NLE Websites -- All DOE Office Websites (Extended Search)

WIPP 04-2301 WIPP 04-2301 Passive Institutional Controls Implementation Plan August 19, 2004 United States Department of Energy Waste Isolation Pilot Plant Carlsbad Field Office Carlsbad, New Mexico DOE/WIPP 04-2301 Passive Institutional Controls Implementation Plan Waste Isolation Pilot Plant Carlsbad, New Mexico August 19, 2004 Prepared for: Washington Regulatory and Environmental Services an affiliate of Washington TRU Solutions, LLC P.O. Box 2078 Carlsbad, New Mexico 88221 Prepared by: John Hart and Associates, P.A. 2815 Candelaria Road, N.W. Albuquerque, New Mexico 87107 (505) 344-7868 DOE/WIPP 04-2301 i Table of Contents List of Tables .....................................................................................................................ii

472

Strategic Action Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Utility Program Strategic Action Plan David McAndrew Background * Result of FUPWG Fall 2006 Meeting * Responds to challenge issued FEMP's Director * Based on the feedback from the FUPWG Fall working group session * Will require FUPWG member active participation for success FEMP Challenge * Accelerate project planning and implementation * Double current project investment levels * Double the number of utilities offering UESCs * Enhance the partnerships between utilities and agencies * Maximize the use, by agencies, of additional services offered by utilities to meet the government's goals for EERE Fall FUPWG Working Session Questions * How can we double the level of project investment from its current level

473

LLE Review  

SciTech Connect

This volume of the LLE Review, covering the period January--March 1992, contains articles on the use of diffraction gratings in laser applications, and the fabrication of gratings for use in these applications. there are two articles on the use of lasers to explore fundamental physics issues and an article on the use of a solid-state diode array for x-ray imaging. Finally, the activities of the National Laser Users Facility and the GDL and OMEGA laser systems are summarized.

Keck, R.L. (ed.)

1992-01-01T23:59:59.000Z

474

FY 2011 Service Contract Inventory Analysis Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

1 Service Contract Inventory Analysis 1 Service Contract Inventory Analysis Plan Department of Energy Office of Procurement & Assistance Management Strategic Programs Division (MA-622) December 2011 Department of Energy FY 2011 Service Contract Inventory Plan for Analysis The Department of Energy (DOE) approach will be performed in accordance with the criteria set out in Consolidated Appropriations Act, 2010, (Pub. L. No. 111-117, § 743 (2009)) and Appendix D of the November 5, 2010 OMB Memorandum on Service Contract Inventories, and will ultimately identify contracts for a more in-depth review. DOE will develop the basic inventory in accordance with OMB guidance using FPDS-NG data to address a number of the inventory requirements consistent with the Consolidated Appropriations Act and collect

475

FY 2012 Service Contract Inventory Analysis Plan  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Service Contract Inventory Service Contract Inventory Analysis Plan Department of Energy Office of Acquisition and Project Management Strategic Programs Division (MA-622) December 2012 Department of Energy FY 2012 Service Contract Inventory Plan for Analysis The Department of Energy (DOE) approach will be performed in accordance with the criteria set out in Consolidated Appropriations Act, 2010, (Pub. L. No. 111-117, § 743 (2009)) and Appendix D of the November 5, 2010 OMB Memorandum on Service Contract Inventories, and will ultimately identify contracts for a more in-depth review. DOE will develop the basic inventory in accordance with OMB guidance using FPDS-NG data to address a number of the inventory requirements consistent with the Consolidated Appropriations Act. APM will

476

Maintenance implementation plan for fuel supply shutdown  

Science Conference Proceedings (OSTI)

This Maintenance Implementation Plan is written to satisfy the requirements of DOE Order 4330.4B, ``MAINTENANCE MANAGEMENT PROGRAM``, that specifies the general policy and objectives for the establishment of DOE controlled maintenance programs. These Programs provide for the management and performance of cost-effective maintenance and repair of Department of Energy (DOE) property, which includes facilities. A review of DOE Order 4330.4B, particularly Chapter II the nuclear portion, against existing WHC site programs and policies has provided assurance that most requirements of this order have already been implemented by existing WHC programs. Applicable requirements and guidelines of 4330.4B that are deficient or not implemented are presently being developed and implemented through WHC site policies and programs. Where no program is presently identified or being developed for 4330.4B requirements, responsibility for implementation has been assigned within this plan.

Stephenson, R.L.

1995-06-01T23:59:59.000Z

477

Wyoming geothermal commercialization planning. Semi-annual progress report, January 1, 1979-June 30, 1979  

DOE Green Energy (OSTI)

The objectives, project tasks, and specific task descriptions and products are reviewed. The resource assessment data for the state is not available and the planning activity is based on speculation at this date. (MHR)

James, R.W.

1979-06-30T23:59:59.000Z

478

CASL Validation Data: An Initial Review  

SciTech Connect

The study aims to establish a comprehensive view of data needed for supporting implementation of the Consortium of Advanced Simulation of LWRs (CASL). Insights from this review (and its continual refinement), together with other elements developed in CASL, should provide the foundation for developing the CASL Validation Data Plan (VDP). VDP is instrumental to the development and assessment of CASL simulation tools as predictive capability. Most importantly, to be useful for CASL, the VDP must be devised (and agreed upon by all participating stakeholders) with appropriate account for nature of nuclear engineering applications, the availability, types and quality of CASL-related data, and novelty of CASL goals and its approach to the selected challenge problems. The initial review (summarized on the January 2011 report version) discusses a broad range of methodological issues in data review and Validation Data Plan. Such a top-down emphasis in data review is both needed to see a big picture on CASL data and appropriate when the actual data are not available for detailed scrutiny. As the data become available later in 2011, a revision of data review (and regular update) should be performed. It is expected that the basic framework for review laid out in this report will help streamline the CASL data review in a way that most pertinent to CASL VDP.

Nam Dinh

2011-01-01T23:59:59.000Z

479

Microsoft Word - Merit Review Guide FINAL JULY 2013  

Energy.gov (U.S. Department of Energy (DOE)) Indexed Site

Acquisition and Project Management Acquisition and Project Management Office of Policy Procurement & Assistance Policy Division, MA-611 July 2013 ii TABLE OF CONTENTS I. INTRODUCTION .................................................................................................................. 1-2 II. MERIT REVIEW .......................................................................................................................2 III. MERIT REVIEW PARTICIPANTS ...................................................................................... 3-5 IV. CONFLICTS OF INTEREST AND CONFIDENTIALITY .................................................. 5-7 V. EVALUATION AND SELECTION PLANS ...................................................................... 7-11

480

Hybrid vehicle potential assessment. Volume 7. Hybrid vehicle review  

DOE Green Energy (OSTI)

Review of hybrid vehicles (HVs) built during the past ten years or planned to be built in the near future is presented. An attempt is made to classify and analyze these vehicles to get an overall picture of their key characteristics. The review includes on-road hybrid passenger cars, trucks, vans, and buses.

Leschly, K.O.

1979-09-30T23:59:59.000Z

Note: This page contains sample records for the topic "review plan srp" from the National Library of EnergyBeta (NLEBeta).
While these samples are representative of the content of NLEBeta,
they are not comprehensive nor are they the most current set.
We encourage you to perform a real-time search of NLEBeta
to obtain the most current and comprehensive results.