Sample records for reported oper ating

  1. ANNUAL FINANCIAL REPORT 2010/2011 CALCUL ATING

    E-Print Network [OSTI]

    Haykin, Simon

    TING #12;#12;INSPIRING INNOVATION AND DISCOVERY | mcmaster.ca TABLE OF CONTENTS Year In Review ANNUAL FINANCIAL REPORT 2010/2011 #12;4 YEAR IN REVIEW 2010/11 YEAR IN REVIEW McMaster University, home

  2. University of Minnesota aquifer thermal energy storage (ATES) project report on the third long-term cycle

    SciTech Connect (OSTI)

    Hoyer, M.C.; Hallgren, J.P.; Uebel, M.H.; Delin, G.N.; Eisenreich, S.J.; Sterling, R.L.

    1994-12-01T23:59:59.000Z

    The University of Minnesota aquifer thermal energy storage (ATES) system has been operated as a field test facility (FTF) since 1982. The objectives were to design, construct, and operate the facility to study the feasibility of high-temperature ATES in a confined aquifer. Four short-term and two long-term cycles were previously conducted, which provided a greatly increased understanding of the efficiency and geochemical effects of high-temperature aquifer thermal energy storage. The third long-term cycle (LT3) was conducted to operate the ATES system in conjunction with a real heating load and to further study the geochemical impact that heated water storage had on the aquifer. For LT3, the source and storage wells were modified so that only the most permeable portion, the Ironton-Galesville part, of the Franconia-Ironton-Galesville aquifer was used for storage. This was expected to improve storage efficiency by reducing the surface area of the heated volume and simplify analysis of water chemistry results by reducing the number of aquifer-related variables which need to be considered. During LT3, a total volume of 63.2 {times} 10{sup 3} m {sup 3} of water was injected at a rate of 54.95 m{sup 3}/hr into the storage well at a mean temperature of 104.7{degrees}C. Tie-in to the reheat system of the nearby Animal Sciences Veterinary Medicine (ASVM) building was completed after injection was completed. Approximately 66 percent (4.13 GWh) of the energy added to the aquifer was recovered. Approximately 15 percent (0.64 GWh) of the usable (10 building. Operations during heat recovery with the ASVM building`s reheat system were trouble-free. Integration into more of the ASVM (or other) building`s mechanical systems would have resulted in significantly increasing the proportion of energy used during heat recovery.

  3. Review of simulation techniques for aquifer thermal energy storage (ATES)

    SciTech Connect (OSTI)

    Mercer, J.W.; Faust, C.R.; Miller, W.J.; Pearson, F.J. Jr.

    1981-03-01T23:59:59.000Z

    The storage of thermal energy in aquifers has recently received considerable attention as a means to conserve and more efficiently use energy supplies. The analysis of aquifer thermal energy storage (ATES) systems will rely on the results from mathematical and geochemical models. Therefore, the state-of-the-art models relevant to ATES was reviewed and evaluated. These models describe important processes active in ATES including ground-water flow, heat transport (heat flow), solute transport (movement of contaminants), and geochemical reactions. In general, available models of the saturated ground-water environment are adequate to address most concerns associated with ATES; that is, design, operation, and environmental assessment. In those cases where models are not adequate, development should be preceded by efforts to identify significant physical phenomena and relate model parameters to measurable quantities. Model development can then proceed with the expectation of an adequate data base existing for the model's eventual use. Review of model applications to ATES shows that the major emphasis has been on generic sensitivity analysis and site characterization. Assuming that models are applied appropriately, the primary limitation on model calculations is the data base used to construct the model. Numerical transport models are limited by the uncertainty of subsurface data and the lack of long-term historical data for calibration. Geochemical models are limited by the lack of thermodynamic data for the temperature ranges applicable to ATES. Model applications undertaken with data collection activities on ATES sites should provide the most important contributions to the understanding and utilization of ATES. Therefore, the primary conclusion of this review is that model application to field sites in conjunction with data collection activities is essential to the development of this technology.

  4. SPECTR System Operational Test Report

    SciTech Connect (OSTI)

    W.H. Landman Jr.

    2011-08-01T23:59:59.000Z

    This report overviews installation of the Small Pressure Cycling Test Rig (SPECTR) and documents the system operational testing performed to demonstrate that it meets the requirements for operations. The system operational testing involved operation of the furnace system to the design conditions and demonstration of the test article gas supply system using a simulated test article. The furnace and test article systems were demonstrated to meet the design requirements for the Next Generation Nuclear Plant. Therefore, the system is deemed acceptable and is ready for actual test article testing.

  5. Occurrence Reporting and Processing of Operations Information

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1995-09-25T23:59:59.000Z

    This Manual provides detailed requirements to supplement DOE O 232.1, Occurrence Reporting and Processing of Operations Information. Chg 1 dated 8-12-96.

  6. Reactor Operations informal monthly report September 1994

    SciTech Connect (OSTI)

    Junker, L.

    1994-09-01T23:59:59.000Z

    This paper presents operations at the MRR and HFBR reactors at Brookhaven National Laboratory for September 1994. Reactor run-times, instrumentation, mechanical maintenance, occurrence reports and safety information are listed. Irradiation summaries are included.

  7. Occurrence Reporting and Processing of Operations Information

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1995-09-25T23:59:59.000Z

    To establish and maintain a system for reporting operations information related to DOE-owned or -operated facilities and processing that information to identify the root causes of Unusual, Off -Normal, and Emergency Occurrences and provide for appropriate corrective action. Chg 1, 10-26-95. Canceled by DOE O 231.1B

  8. Occurrence Reporting and Processing of Operations Information

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1996-08-12T23:59:59.000Z

    To establish and maintain a system for reporting operations information related to DOE-owned or -operated facilities and processing that information to identify the root causes of Unusual, Off -Normal, and Emergency Occurrences and provide for appropriate corrective action. Chg 2, 8-12-96

  9. Occurrence Reporting and Processing of Operations Information

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-07-21T23:59:59.000Z

    To establish and maintain a system for reporting operations information related to DOE-owned and -leased facilities and processing that information to identify the root causes of Unusual, Off-Normal, and Emergency Occurrences and provide for appropriate corrective action. Cancels: DOE O 232.1

  10. Overview Report: Normal and Emergency Operation Visualization

    SciTech Connect (OSTI)

    Greitzer, Frank L.

    2011-05-01T23:59:59.000Z

    This is an overview report to document and illustrate methods used in a project entitled “Normal and Emergency Operations Visualization” for a utility company, conducted in 2009-2010 timeframe with funding from the utility company and the U.S. Department of Energy. The original final report (about 180 pages) for the project is not available for distribution because it alludes to findings that assessed the design of an operational system that contained proprietary information; this abridged version contains descriptions of methods and some findings to illustrate the approach used, while avoiding discussion of sensitive or proprietary information. The client has approved this abridged version of the report for unlimited distribution to give researchers and collaborators the benefit of reviewing the research concepts and methods that were applied in this study.

  11. Field Operations Program Activities Status Report

    SciTech Connect (OSTI)

    J. E. Francfort; D. V. O'Hara; L. A. Slezak

    1999-05-01T23:59:59.000Z

    The Field Operations Program is an electric vehicle testing and evaluation program sponsored by US Department of Energy and managed by the Idaho National Engineering and Environmental Laboratory. The Program's goals are to evaluate electric vehicles in real-world applications and environments, support electric vehicle technology advancement, develop infrastructure elements necessary to support significant electric vehicle use, support increased use of electric vehicles in federal fleets, and increase overall awareness and acceptance of electric vehicles. This report covers Program activities from fiscal year 1997 through mid-fiscal year 1999. The Field Operations Program succeeded the Site Operator Program, which ended in September 1996. Electric vehicle testing conducted by the Program includes baseline performance testing (EV America testing), accelerated reliability (life-cycle) testing, and fleet testing. The baseline performance parameters include accelerations, braking, range, energy efficiency, and charging time. The Program collects accelerated reliability and fleet operations data on electric vehicles operated by the Program's Qualified Vehicle Testing (QVT) partners. The Program's QVT partners have over 3 million miles of electric vehicle operating experience.

  12. WRAP operational test report drum non destructive examination system

    SciTech Connect (OSTI)

    HUMPHRYS, K.L.

    1999-07-01T23:59:59.000Z

    This operational test report was performed to verify the WRAP Facility Drum Non-Destructive Examination systems operate in accordance with the system designs and specifications.

  13. Operational readiness review phase-1 final report for WRAP-1

    SciTech Connect (OSTI)

    Bowen, W., Westinghouse Hanford

    1996-12-27T23:59:59.000Z

    This report documents the Operational Readiness Review for WRAP-1 Phase-1 operations. The report includes all criteria, lines of inquiry with resulting Findings and Observations. The review included assessing operational capability of the organization and the computer controlled process and facility systems.

  14. Operations Training Program Status Report 1/28/99

    E-Print Network [OSTI]

    Operations Training Program Status Report 1/28/99 Michael Spata Operations Deputy Group Leader Following is a description of the various aspects of the Operations Group Training program. While most for providing on-the-job training in accelerator specific topics. The mentor will also be able to certify

  15. BPAT Operational Analysis DSO216 Report

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    be counted as 24, no matter when in the hour the action occurred.) 4709 4626 4543 4709 Installed Wind Capacity (as of the end of each month) Report Created On: 1052012 at...

  16. Occurrence Reporting and Processing of Operations Information

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2003-08-19T23:59:59.000Z

    Provides detailed information for reporting occurrences and managing associated activities at DOE facilities, including NNSA facilities. Cancels DOE M 232.1-1A. Canceled by DOE O 232.2.

  17. Groundwater Remediation Systems Quarterly Operations Report

    E-Print Network [OSTI]

    .......................................... 5-1 6. OU III Carbon Tetrachloride Pump and Treat System........................................ 6 = ethylene dibromide * System dismantlement for the Carbon Tetrachloride system was completed in 2010. ** EDB Standby NA 180 Industrial Park Recirculation/ In-Well (AS/Carbon) VOC 7 Operate- 14 Standby- 1 30% NA 1062

  18. Groundwater Remediation Systems Quarterly Operations Report

    E-Print Network [OSTI]

    .......................................... 5-1 6. OU III Carbon Tetrachloride Pump and Treat System ........................................ 6 = ethylene dibromide * System dismantlement for the Carbon Tetrachloride system was completed in 2010. ** EDB Standby NA 180 Industrial Park Recirculation/ In-Well (AS/Carbon) VOC 7 Operate- 14 Standby- 1 Standby NA

  19. Groundwater Remediation Systems Quarterly Operations Report

    E-Print Network [OSTI]

    .......................................... 5-1 6. OU III Carbon Tetrachloride Pump and Treat System ........................................ 6 = ethylene dibromide * System dismantlement for the Carbon Tetrachloride system was completed in 2010. ** EDB% NA 180 Industrial Park Recirculation/ In-Well (AS/Carbon) VOC 7 Operate- 14 Standby-

  20. Groundwater Remediation Systems Quarterly Operations Report

    E-Print Network [OSTI]

    .......................................... 5-1 6. OU III Carbon Tetrachloride Pump and Treat System ........................................ 6 for the Carbon Tetrachloride system was completed in 2010. ** EDB has only been detected in the influent at trace and Recirculate Tritium 4 Operate- 9 Standby- 7 100% NA 180 Industrial Park Recirculation/ In-Well (AS/Carbon) VOC

  1. Groundwater Remediation Systems Quarterly Operations Report

    E-Print Network [OSTI]

    .......................................... 5-1 6. OU III Carbon Tetrachloride Pump and Treat System........................................ 6 = ethylene dibromide * System dismantlement for the Carbon Tetrachloride system was completed in 2010. ** EDB Standby NA 180 Industrial Park Recirculation/ In-Well (AS/Carbon) VOC 7 Operate- 14 Standby- 1 100% 1 1063

  2. BPAT Operational Analysis DSO216 Report

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office511041cloth DocumentationProductsAlternativeOperationalAugustDecade5-F, 2012 In reply referBPAT Customer2

  3. 200-BP-5 operable unit treatability test report

    SciTech Connect (OSTI)

    NONE

    1996-04-01T23:59:59.000Z

    The 200-BP-5 Operable Unit was established in response to recommendations presented in the 200 East Groundwater Aggregate Area Management Study Report (AAMSR) (DOE-RL 1993a). Recognizing different approaches to remediation, the groundwater AAMSR recommended separating groundwater from source and vadose zone operable units and subdividing 200 East Area groundwater into two operable units. The division between the 200-BP-5 and 200-PO-1 Operable Units was based principally on source operable unit boundaries and distribution of groundwater plumes derived from either B Plant or Plutonium/Uranium Extraction (PUREX) Plant liquid waste disposal sites.

  4. Liquid and Gaseous Waste Operations Department annual operating report, CY 1995

    SciTech Connect (OSTI)

    Maddox, J.J.; Scott, C.B.

    1996-03-01T23:59:59.000Z

    This report describes the operating activities, upgrade activities, maintenance, and other activities regarding liquid and gaseous low level radioactive waste management at the Oak Ridge National Laboratory. Miscellaneous activities include training, audits, tours, and environmental restoration support.

  5. Liquid and Gaseous Waste Operations Department Annual Operating Report, CY 1993

    SciTech Connect (OSTI)

    Maddox, J.J.; Scott, C.B.

    1994-02-01T23:59:59.000Z

    This report summarizes the activities of the waste management operations section of the liquid and gaseous waste operations department at ORNL for 1993. The process waste, liquid low-level waste, gaseous waste systems activities are reported, as well as the low-level waste solidification project. Upgrade activities is the various waste processing and treatment systems are summarized. A maintenance activity overview is provided, and program management, training, and other miscellaneous activities are covered.

  6. 200-BP-5 operable unit Technical Baseline report

    SciTech Connect (OSTI)

    Jacques, I.D.; Kent, S.K.

    1991-10-01T23:59:59.000Z

    This report supports development of a remedial investigation/feasibility study work plan for the 200-BP-5 operable unit. The report summarizes baseline information for waste sites and unplanned release sites located in the 200-BP-5 operable unit. The sites were investigated by the Technical Baseline Section of the Environmental Engineering Group, Westinghouse Hanford Company (Westinghouse Hanford). The investigation consisted of review and evaluation of current and historical Hanford Site reports, drawings, and photographs, and was supplemented with recent inspections of the Hanford Site and employee interviews. No field investigations or sampling were conducted.

  7. Institute of Nuclear Power Operations annual report, 1993

    SciTech Connect (OSTI)

    NONE

    1993-12-31T23:59:59.000Z

    This annual report highlights the activities of the Institute of Nuclear Power Operations. The topics of the report include the president and chairmen`s joint message, overview of programs serving as the foundation for most of its activities, performance indicators for the US nuclear utility industry, and INPO`s 1993 financial reports and rosters. INPO has four technical cornerstone programs that serve as the foundation for most of its activities. (1) Evaluations of nuclear power plants operated by member utilities are conducted on a regularly scheduled basis. (2) INPO supports its member utilities in their work to achieve and maintain accreditation of training programs. (3) Events analysis programs identify and communicate lessons learned from plant events so utilities can take action to prevent similar events at their plants. (4) INPO helps members improve in nuclear operations areas through assistance programs and other activities that continually evolve to meet the changing needs of the nuclear industry.

  8. Analysis and evaluation of operational data. Annual report, 1996

    SciTech Connect (OSTI)

    NONE

    1997-12-01T23:59:59.000Z

    The United States Nuclear Regulatory Commission`s Office for Analysis and Evaluation of Operational Data (AEOD) has published reports of its activities since 1984. The first report covered January through June of 1984, and the second report covered July through December of 1984. After those first two semiannual reports, AEOD published annual reports of its activities from 1985 through 1993. Beginning with report for 1986, AEOD Annual Reports have been published as NUREG-1272. Beginning with the report for 1987, NUREG-1272 has been published in two parts, No. 1 covering power reactors and No. 2 covering nonreactors (changed to `nuclear materials` with the 1993 report). AEOD changed its annual report from a calendar year (CY) to a fiscal year report, and added part No. 3 covering technical training, beginning with the combined Annual Report for CY 1994 and fiscal year 1995, NUREG-1272, Vol. 9, Nos. 1-3. This report, NUREG-1272, Vol. 10, No. 2, covers nuclear materials and presents a review of the events and concerns associated with the use of licensed material in applications other than power reactores. NUREG-1272, Vol. 10, No. 1, covers power reactors and presents an overview of the fiscal year 1996 operating experience of the nuclear power industry from the NRC perspective. NUREG-1272, Vol. 10, No. 3, covers technical training and presents the activities of the Technical Training Center in support of the NRC`s mission. Throughout these reports, whenever information is presented for a calendar year, it is so designated. Fiscal year information is designated by the four digits of the fiscal year.

  9. A knowledge based model of electric utility operations. Final report

    SciTech Connect (OSTI)

    NONE

    1993-08-11T23:59:59.000Z

    This report consists of an appendix to provide a documentation and help capability for an analyst using the developed expert system of electric utility operations running in CLIPS. This capability is provided through a separate package running under the WINDOWS Operating System and keyed to provide displays of text, graphics and mixed text and graphics that explain and elaborate on the specific decisions being made within the knowledge based expert system.

  10. United States Department of Energy, Nevada Operations Office, completion report Operation KLAXON, Fiscal Year 1993

    SciTech Connect (OSTI)

    Not Available

    1994-06-01T23:59:59.000Z

    The U.S. Department of Energy, Nevada Operations Office (DOE/NV), Completion Report provides a summary of activities conducted at the Nevada Test Site (NTS) between October 1, 1992, and September 30, 1993, associated with Operation KLAXON. (In the past, each annual Completion Report dealt with a series of underground nuclear detonations; however, because no nuclear tests were conducted during FY 1993, this Report summarizes continuing nonnuclear and nuclear test readiness activities at the NTS sponsored by DOE/NV.) The report serves as a reference for those involved with the planning and execution of Operation KLAXON and also serves as a planning guide for future operations. Information in the report covers the logistics and management of activities. Scientific information and data associated with NTS activities are presented in technical documents published by participating agencies. In September 1992, Congress legislated a nine-month moratorium on the testing of nuclear weapons. The bill also provided for a resumption of testing (with no more than five tests per year, or a total of 15 during the next three years) in July 1993, and mandated an end to nuclear testing, entirely, by 1996. President Bush signed the bill into law in October 1992.

  11. 200-UP-2 Operable Unit technical baseline report

    SciTech Connect (OSTI)

    Deford, D.H.

    1991-02-01T23:59:59.000Z

    This report is prepared in support of the development of a Remedial Investigation/Feasibility Study (RI/FS) Work Plan for the 200-UP-2 Operable Unit by EBASCO Environmental, Incorporated. It provides a technical baseline of the 200-UP-2 Operable Unit and results from an environmental investigation undertaken by the Technical Baseline Section of the Environmental Engineering Group, Westinghouse Hanford Company (Westinghouse Hanford). The 200-UP-2 Operable Unit Technical Baseline Report is based on review and evaluation of numerous Hanford Site current and historical reports, Hanford Site drawings and photographs and is supplemented with Hanford Site inspections and employee interviews. No field investigations or sampling were conducted. Each waste site in the 200-UP-2 Operable Unit is described separately. Close relationships between waste units, such as overflow from one to another, are also discussed. The 200-UP-2 Operable Unit consists of liquid-waste disposal sites in the vicinity of, and related to, U Plant operations in the 200 West Area of the Hanford Site. The U Plant'' refers to the 221-U Process Canyon Building, a chemical separations facility constructed during World War 2. It also includes the Uranium Oxide (UO{sub 3}) Plant, which was constructed at the same time and, like the 221-U Process Canyon Building, was later converted for other missions. Waste sites in the 200-UP-2 Operable Unit are associated with the U Plant Uranium Metal Recovery Program mission that occurred between 1952 and 1958 and the UO{sub 3} Plant's ongoing uranium oxide mission and include one or more cribs, reverse wells, french drains, septic tanks and drain fields, trenches, catch tanks, settling tanks, diversion boxes, waste vaults, and the lines and encasements that connect them. 11 refs., 1 tab.

  12. Richland Operations Office

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Department of Energy Richland Operations Office P.O. Box 550 &?ATES0Richland, Washington 99352 10O-AMSE-0054 A PR I Mr. J. G. Lehew III, President and Chief Executive Officer...

  13. Operations other than war: Requirements for analysis tools research report

    SciTech Connect (OSTI)

    Hartley, D.S. III

    1996-12-01T23:59:59.000Z

    This report documents the research effort to determine the requirements for new or improved analysis tools to support decisions at the strategic and operational levels for military Operations Other than War (OOTW). The work was performed for the Commander in Chief, U.S. Pacific Command (USCINCPAC). The data collection was based on workshops attended by experts in OOTWs: analysis personnel from each of the Combatant Commands, the Services, the Office of the Secretary of Defense (OSD), the Joint Staff, and other knowledgeable personnel. Further data were gathered from other workshops and conferences and from the literature. The results of this research begin with the creation of a taxonomy of OOTWs: categories of operations, attributes of operations, and tasks requiring analytical support. The tasks are connected to the Joint Staff`s Universal Joint Task List (UJTL). Historical OOTWs are analyzed to produce frequency distributions by category and responsible CINC. The analysis products are synthesized into a list of requirements for analytical tools and definitions of the requirements. The report concludes with a timeline or roadmap for satisfying the requirements.

  14. Operational test report -- Project W-320 cathodic protection systems

    SciTech Connect (OSTI)

    Bowman, T.J.

    1998-06-16T23:59:59.000Z

    Washington Administrative Code (WAC) 173-303-640 specifies that corrosion protection must be designed into tank systems that treat or store dangerous wastes. Project W-320, Waste Retrieval Sluicing System (WRSS), utilizes underground encased waste transfer piping between tanks 241-C-106 and 241-AY-102. Corrosion protection is afforded to the encasements of the WRSS waste transfer piping through the application of earthen ionic currents onto the surface of the piping encasements. Cathodic protection is used in conjunction with the protective coatings that are applied upon the WRSS encasement piping. WRSS installed two new two rectifier systems (46 and 47) and modified one rectifier system (31). WAC 173-303-640 specifies that the proper operation of cathodic protection systems must be confirmed within six months after initial installation. The WRSS cathodic protection systems were energized to begin continuous operation on 5/5/98. Sixteen days after the initial steady-state start-up of the WRSS rectifier systems, the operational testing was accomplished with procedure OTP-320-006 Rev/Mod A-0. This operational test report documents the OTP-320-006 results and documents the results of configuration testing of integrated piping and rectifier systems associated with the W-320 cathodic protection systems.

  15. WRAP 1, operational test report 80X non-destructive examination system

    SciTech Connect (OSTI)

    Bottenus, R.J.

    1997-04-14T23:59:59.000Z

    This Operational Test Report was performed to verify the WRAP 1 Facility 80X Non-Destructive Examination systems operate in accordance with the system designs and specifications.

  16. University of Hawaii Advisory Task Group -Operational Assessment Report on System Level Administration Operating Policies and Practices

    E-Print Network [OSTI]

    #12;University of Hawaii ­ Advisory Task Group - Operational Assessment Report on System Level") approved the formation of an Advisory Task Group on Operational and Financial Controls Improvement ("ATG of eight members, four members from the BOR, and four from private industry with expertise in financial

  17. SP-100 operational life model. Fiscal Year 1990 annual report

    SciTech Connect (OSTI)

    Ewell, R.; Awaya, H.

    1990-12-14T23:59:59.000Z

    This report covers the initial year`s effort in the development of an Operational Life Model (OLM) for the SP-100 Space Reactor Power System. The initial step undertaken in developing the OLM was to review all available documentation from GE on their plans for the OLM and on the degradation and failure mechanisms envisioned for the SP-100. In addition, the DEGRA code developed at JPL, which modelled the degradation of the General Purpose Heat Source based Radioisotope Thermoelectric Generator (GPHS-RTG), was reviewed. Based on the review of the degradation and failure mechanisms, a list of the most pertinent degradation effects along with their key degradation mechanisms was compiled. This was done as a way of separating the mechanisms from the effects and allowing all of the effects to be incorporated into the OLM. The emphasis was on parameters which will tend to change performance as a function of time and not on those that are simply failures without any prior degradation.

  18. Planning and Reporting for Operations and Maintenance in Federal...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    and Maintenance Manual for ECMs including: New written operations procedures; Preventive maintenance work procedures and checklists. Project Acceptance IDIQ Attachment...

  19. Independent Activity Report, Richland Operations Office- June 2011

    Broader source: Energy.gov [DOE]

    Hanford Cold Vacuum Drying Facility, Multi-Canister Overpack, Operational Proficiency Demonstration [HIAR-RL-2011-06-22

  20. Annual Report of the EURATOM/CCFE Fusion Programme 2011/12 3 JET Operations

    E-Print Network [OSTI]

    of the JET machine not being exactly as the drawings and CAD models 3JETOperations #12;Annual ReportAnnual Report of the EURATOM/CCFE Fusion Programme 2011/12 3.1 3 JET Operations 3 JET Operations 3 Associate Leader for JET. During the period covered by this report, the major shutdown for the installation

  1. Future peace operations: Lessons from Bosnia. Final report

    SciTech Connect (OSTI)

    Godlewski, J.S.

    1995-05-16T23:59:59.000Z

    The end of the Bi-polar world has increased the requirement for and scope of UN peace operations. This paper examines the current situation in Bosnia from an Operational Command and Control perspective. It points out the shortfalls of force structure, clear direction on both the strategic/operational level and the UN`s inability to coordinate their and NATO`s efforts. It will also discuss the need and framework for `robust` peace operations. It concludes with an examination of options for a command and control structure for future UN peace operations.

  2. Precursor Report of Data Needs and Recommended Practices for PV Plant Availability Operations and Maintenance Reporting.

    SciTech Connect (OSTI)

    Hill, Roger R.; Klise, Geoffrey Taylor; John Balfour, John R Balfour, High Performance PV

    2015-01-01T23:59:59.000Z

    Characterizing the factors that affect reliability of a photovoltaic (PV) power plant is an important aspect of optimal asset management. This document describes the many factors that affect operation and maintenance (O&M) of a PV plant, identifies the data necessary to quantify those factors, and describes how data might be used by O&M service providers and others in the PV industry. This document lays out data needs from perspectives of reliability, availability, and key performance indicators and is intended to be a precursor for standardizing terminology and data reporting, which will improve data sharing, analysis, and ultimately PV plant performance.

  3. INDEPENDENT VERIFICATION SURVEY REPORT FOR THE OPERABLE UNIT-1 LANDFILL TRENCHES, MIAMISBURG CLOSURE PROJECT

    SciTech Connect (OSTI)

    W.C. Adams

    2010-05-24T23:59:59.000Z

    INDEPENDENT VERIFICATION SURVEY REPORT FOR THE OPERABLE UNIT-1 LANDFILL TRENCHES, MIAMISBURG CLOSURE PROJECT, MIAMISBURG, OHIO DCN: 0468-SR-02-0

  4. INDEPENDENT VERIFICATION SURVEY REPORT OPERABLE UNIT-1 LANDFILL TRENCHES, MIAMISBURG CLOSURE PROJECT

    SciTech Connect (OSTI)

    W.C. Adams

    2010-07-21T23:59:59.000Z

    INDEPENDENT VERIFICATION SURVEY REPORT FOR THE OPERABLE UNIT-1 LANDFILL TRENCHES, MIAMISBURG CLOSURE PROJECT, MIAMISBURG, OHIO DCN: 0468-SR-03-0

  5. Feasibility study report for the 200-BP-1 operable unit

    SciTech Connect (OSTI)

    Not Available

    1993-06-01T23:59:59.000Z

    This feasibility study examines a range of alternatives and provides recommendations for selecting a preferred alternative for remediating contamination at the 200-BP-1 operable unit. The 200-BP-1 operable unit is located in the center of the Hanford Site along the northern boundary of the 200 East Area. The 241-BY Tank Farm is located immediately to the south of the operable unit. 200-BP-1 is a source operable unit with contaminated soils associated primarily with nine inactive cribs (known as the 216-B cribs). These cribs were used for disposal of low-level radioactive liquid waste from U Plant uranium recovery operations, and waste storage tank condensate from the adjacent 241-BY Tank Farm. The cribs used for disposal of U Plant waste were in operation from 1955--1965, and the cribs used for disposal of tank condensate were in operation from 1965--1975. In addition to the cribs, four unplanned releases of radioactive materials have occurred within the operable unit. Contaminated surface soils associated with the unplanned releases have been consolidated over the cribs and covered with clean soil to reduce contaminant migration and exposure. Discharge of wastes to the cribs has resulted in soil and groundwater contamination. The groundwater is being addressed as part of the 200 East Aggregate Area, groundwater operable unit. Contaminated soils at the site can be categorized by the types of contaminants, their distribution in the soil column, and the risk posed by the various potential exposure pathways. Below the clean soil cover, the near surface soils contain low-levels of contamination with cesium-137, radium-226, strontium-90, thorium-228, and uranium. The lifetime incremental cancer risk associated with these soils if they were exposed at the surface is 9{times}10{sup {minus}5}.

  6. Independent Activity Report, Richland Operations Office- January 2011

    Broader source: Energy.gov [DOE]

    Presentation of Questions Associated With the Safety Analysis Report for Packaging (Onsite) Multi-Canister Overpack Cask [ARPT-RL-2011-001

  7. Westinghouse Hanford Company Operational Groundwater status report, 1990--1992

    SciTech Connect (OSTI)

    Johnson, V.G.

    1993-03-01T23:59:59.000Z

    This report presents information related to the water quality of ground water at the Hanford Reservation. Included are plume maps, geology, hydrology, and information on various effluent sources.

  8. Breckinridge Project, initial effort. Report IX. Operating cost estimate

    SciTech Connect (OSTI)

    none,

    1982-01-01T23:59:59.000Z

    Operating costs are normally broken into three major categories: variable costs including raw materials, annual catalyst and chemicals, and utilities; semi-variable costs including labor and labor related cost; and fixed or capital related charges. The raw materials and utilities costs are proportional to production; however, a small component of utilities cost is independent of production. The catalyst and chemicals costs are also normally proportional to production. Semi-variable costs include direct labor, maintenance labor, labor supervision, contract maintenance, maintenance materials, payroll overheads, operation supplies, and general overhead and administration. Fixed costs include local taxes, insurance and the time value of the capital investment. The latter charge often includes the investor's anticipated return on investment. In determining operating costs for financial analysis, return on investment (ROI) and depreciation are not treated as cash operating costs. These costs are developed in the financial analysis; the annual operating cost determined here omits ROI and depreciation. Project Annual Operating Costs are summarized in Table 1. Detailed supporting information for the cost elements listed below is included in the following sections: Electrical, catalyst and chemicals, and salaries and wages.

  9. Annual Report of the EURATOM/CCFE Fusion Programme 2009/10 3 JET Operations

    E-Print Network [OSTI]

    Annual Report of the EURATOM/CCFE Fusion Programme 2009/10 3.1 3 JET Operations 3 JET Operations 3 was ex-vessel and no machine vent was required. Plasma operations resumed on 14 July with one week of the scientific tasks highlighting the contributions of CCFE is given in Chapter 4. The machine shutdown

  10. Title 43 CFR 3264 Reports - Drilling Operations | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov YouKizildere IRaghuraji Agro Industries PvtStratosolarTharaldsonInformation 61 Drilling Operations: GettingOperations

  11. WRAP low level waste (LLW) glovebox operational test report

    SciTech Connect (OSTI)

    Kersten, J.K.

    1998-02-19T23:59:59.000Z

    The Low Level Waste (LLW) Process Gloveboxes are designed to: receive a 55 gallon drum in an 85 gallon overpack in the Entry glovebox (GBIOI); and open and sort the waste from the 55 gallon drum, place the waste back into drum and relid in the Sorting glovebox (GB 102). In addition, waste which requires further examination is transferred to the LLW RWM Glovebox via the Drath and Schraeder Bagiess Transfer Port (DO-07-201) or sent to the Sample Transfer Port (STC); crush the drum in the Supercompactor glovebox (GB 104); place the resulting puck (along with other pucks) into another 85 gallon overpack in the Exit glovebox (GB 105). The status of the waste items is tracked by the Data Management System (DMS) via the Plant Control System (PCS) barcode interface. As an item is moved from the entry glovebox to the exit glovebox, the Operator will track an items location using a barcode reader and enter any required data on the DMS console. The Operational Test Procedure (OTP) will perform evolution`s (described below) using the Plant Operating Procedures (POP) in order to verify that they are sufficient and accurate for controlled glovebox operation.

  12. IT Operational Oversight Committee Status Report, February, 2014

    E-Print Network [OSTI]

    or apps for use on mobile devices. The technology has been out a few years but has a few issues and heavy President of Information Technology & CIO The IT Operational Oversight Committee (OOC) was formed as a part of the Purdue University Campus Information Technology Plan (CITP). The OOC focuses on the coordination

  13. Operability test report for K east basin canister cleaning system

    SciTech Connect (OSTI)

    Crystal, J.B.

    1997-01-09T23:59:59.000Z

    This document summarizes test data computed during the operability test procedure for the K East Basin Canister Cleaning System. Test Results show that the canister cleaning system successfully lowered the dose of each canister tested so that each canister could be disposed of as low level waste.

  14. MAR flow mapping of Analytical Chemistry Operations (Preliminary Report)

    SciTech Connect (OSTI)

    Barr, Mary E. [Los Alamos National Laboratory; Farish, Thomas J. [Los Alamos National Laboratory

    2012-06-13T23:59:59.000Z

    The recently released Supplemental Directive, NA-1 SD 1027, updates the radionuclide threshold values in DOE-STD-1027-92 CN1 to reflect the use of modern parameters for dose conversion factors and breathing rates. The directive also corrects several arithmetic errors within the original standard. The result is a roughly four-fold increase in the amount of weapons-grade nuclear material allowed within a designated radiological facility. Radiological laboratory space within the recently constructed Radiological Laboratory Office and Utility Building (RLUOB) is slated to house selected analytical chemistry support activities in addition to small-scale actinide R&D activities. RLUOB is within the same facility operations envelope as TA-55. Consolidation of analytical chemistry activities to RLUOB and PF-4 offers operational efficiency improvements relative to the current pre-CMRR plans of dividing these activities between RLUOB, PF-4, and CMR. RLUOB is considered a Radiological Facility under STD-1027 - 'Facilities that do not meet or exceed Category 3 threshold criteria but still possess some amount of radioactive material may be considered Radiological Facilities.' The supplemental directive essentially increases the allowable material-at-risk (MAR) within radiological facilities from 8.4 g to 38.6 g for {sup 239}Pu. This increase in allowable MAR provides a unique opportunity to establish additional analytical chemistry support functions in RLUOB without negatively impacting either R&D activities or facility operations. Individual radiological facilities are tasked to determine MAR limits (up to the Category 3 thresholds) appropriate to their operational conditions. This study presents parameters that impact establishing MAR limits for RLUOB and an assessment of how various analytical chemistry support functions could operate within the established MAR limits.

  15. Office of Analysis and Evaluation of Operational Data 1989 annual report, Power reactors

    SciTech Connect (OSTI)

    None

    1990-07-01T23:59:59.000Z

    The annual report of the US Nuclear Regulatory Commission's Office for Analysis and Evaluation of Operational Data (AEOD) is devoted to the activities performed during 1989. The report is published in two separate parts. This document, NUREG-1272, Vol. 4, No. 1, covers power reactors and presents an overview of the operating experience of the nuclear power industry from the NRC perspective, including comments about the trends of some key performance measures. The report also includes the principal findings and issues identified in AEOD studies over the past year and summarizes information from such sources as licensee event reports, diagnostic evaluations, and reports to the NRC's Operations Center. This report also compiles the status of staff actions resulting from previous Incident Investigation Team (IIT) reports. 16 figs., 9 tabs.

  16. Annual Report of the EURATOM/CCFE Fusion Programme 2012/13 3 JET Operations

    E-Print Network [OSTI]

    .2.1 TECHNICAL ISSUES By the end of the previous reporting year, restart commissioning of the JET machine hadAnnual Report of the EURATOM/CCFE Fusion Programme 2012/13 3 JET Operations 3.1 INTRODUCTION SinceJETOperations During the period covered by this report, JET experimental campaigns were planned in the period

  17. RESEARCH REPORT 1468-1 INTEGRATED ARTERIAL AND FREEWAY OPERATION

    E-Print Network [OSTI]

    Texas at Austin, University of

    ADVANCED TRAFFIC MANAGEMENT SYSTEMS: RESEARCH REPORT Hani S. Mahmassani, Didier M. Valdes, Randy B. Mahmassani, Didier M. Valdes, Randy B. Machemehl, John S. Tassoulas, and James C. Williams 8. Performing S. Mahmassani Didier M. Valdes Randy B. Machemehl John S. Tassoulas James C. Williams Research

  18. Licensed operating reactors: Status summary report, data as of December 31, 1995. Volume 20

    SciTech Connect (OSTI)

    NONE

    1996-06-01T23:59:59.000Z

    The US Nuclear Regulatory Commission`s monthly summary of licensed nuclear power reactor data is based primarily on the operating data report submitted by licensees for each unit. This report is divided into two sections: the first contains summary highlights and the second contains data on each individual unit in commercial operation. Section 1 availability factors, capacity factors, and forced outage rates are simple arithmetic averages. Section 2 items in the cumulative column are generally as reported by the licensees and notes to the use of weighted averages and starting dates other than commercial operation are provided.

  19. Mobile worksystems for decontamination and decommissioning operations. Final report

    SciTech Connect (OSTI)

    NONE

    1997-02-01T23:59:59.000Z

    This project is an interdisciplinary effort to develop effective mobile worksystems for decontamination and decommissioning (D&D) of facilities within the DOE Nuclear Weapons Complex. These mobile worksystems will be configured to operate within the environmental and logistical constraints of such facilities and to perform a number of work tasks. Our program is designed to produce a mobile worksystem with capabilities and features that are matched to the particular needs of D&D work by evolving the design through a series of technological developments, performance tests and evaluations. The Phase I effort was based on a robot called the Remote Work Vehicle (RWV) that was previously developed by CMU for use in D&D operations at the Three Mile Island Unit 2 Reactor Building basement. During Phase I of this program, the RWV was rehabilitated and upgraded with contemporary control and user interface technologies and used as a testbed for remote D&D operations. We established a close working relationship with the DOE Robotics Technology Development Program (RTDP). In the second phase, we designed and developed a next generation mobile worksystem, called Rosie, and a semi-automatic task space scene analysis system, called Artisan, using guidance from RTDP. Both systems are designed to work with and complement other RTDP D&D technologies to execute selective equipment removal scenarios in which some part of an apparatus is extricated while minimally disturbing the surrounding objects. RTDP has identified selective equipment removal as a timely D&D mission, one that is particularly relevant during the de-activation and de-inventory stages of facility transitioning as a means to reduce the costs and risks associated with subsequent surveillance and monitoring. In the third phase, we tested and demonstrated core capabilities of Rosie and Artisan; we also implemented modifications and enhancements that improve their relevance to DOE`s facility transitioning mission.

  20. Final Report - Membranes and MEA's for Dry, Hot Operating Conditions

    SciTech Connect (OSTI)

    Hamrock, Steven J.

    2011-06-30T23:59:59.000Z

    The focus of this program was to develop a new Proton Exchange Membrane (PEM) which can operate under hotter, dryer conditions than the state of the art membranes today and integrate it into a Membrane Electrode Assembly (MEA). These MEA's should meet the performance and durability requirements outlined in the solicitation, operating under low humidification conditions and at temperatures ranging from -20���ºC to 120���ºC, to meet 2010 DOE technical targets for membranes. This membrane should operate under low humidification conditions and at temperatures ranging from -20���ºC to 120���ºC in order to meet DOE HFCIT 2010 commercialization targets for automotive fuel cells. Membranes developed in this program may also have improved durability and performance characteristics making them useful in stationary fuel cell applications. The new membranes, and the MEA�¢����s comprising them, should be manufacturable at high volumes and at costs which can meet industry and DOE targets. This work included: A) Studies to better understand factors controlling proton transport within the electrolyte membrane, mechanisms of polymer degradation (in situ and ex situ) and membrane durability in an MEA; B) Development of new polymers with increased proton conductivity over the range of temperatures from -20���ºC to 120���ºC and at lower levels of humidification and with improved chemical and mechanical stability; C) Development of new membrane additives for increased durability and conductivity under these dry conditions; D) Integration of these new materials into membranes and membranes into MEA�¢����s, including catalyst and gas diffusion layer selection and integration; E) Verification that these materials can be made using processes which are scalable to commercial volumes using cost effective methods; F) MEA testing in single cells using realistic automotive testing protocols. This project addresses technical barriers A (Durability) and C (Performance) from the Fuel Cells section of the 2005 Hydrogen, Fuel Cells and Infrastructure Technologies Program Multi-Year R&D Plan. In the course of this four-year program we developed a new PEM with improved proton conductivity, chemical stability and mechanical stability. We incorporated this new membrane into MEAs and evaluated performance and durability.

  1. Westinghouse Hanford Company operational environmental monitoring annual report, CY 1992

    SciTech Connect (OSTI)

    Schmidt, J.W.; Johnson, A.R.; McKinney, S.M.; Perkins, C.J.

    1993-07-01T23:59:59.000Z

    This document presents the results of the Westinghouse Hanford Company near-facility operational environmental monitoring for 1992 in the 100, 200/600, and 300/400 Areas of the Hanford Site, in south-central Washington State in 1992. Surveillance activities included sampling and analyses of ambient air, surface water, groundwater, sediments, soil, and biota. Also, external radiation measurements and radiological surveys were taken at waste disposal sites, radiologically controlled areas, and roads. These activities were conducted to assess and to control the impacts of nuclear facilities and waste sites on the workers and the local environment. Additionally, diffuse sources were monitored to determine compliance with Federal, State, and/or local regulations. In general, although impacts from nuclear facilities are still seen on the Hanford Site and are slightly elevated when compared to offsite, these impacts are less than in previous years.

  2. Monticello Mill Tailings Site Operable Unit III Annual Groundwater Report

    Office of Legacy Management (LM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOn AprilA groupTuba City, Arizona, DisposalFourth Five-Year38Report3 Through April 2014

  3. University of Hawai`i ACCESS REQUEST TO DATAAND REPORTS IN OPERATIONAL DATA STORE (ODS)

    E-Print Network [OSTI]

    Olsen, Stephen L.

    University of Hawai`i ACCESS REQUEST TO DATAAND REPORTS IN OPERATIONAL DATA STORE (ODS) Name Title Approved Denied ODS Data Administrator's name (print or type) Signature Date Send completed form to

  4. Licensed operating reactors. Status summary report data as of 12-31-94: Volume 19

    SciTech Connect (OSTI)

    NONE

    1995-04-01T23:59:59.000Z

    The Nuclear Regulatory Commission`s annual summary of licensed nuclear power reactor data is based primarily on the report of operating data submitted by licensees for each unit for the month of December because that report contains data for the month of December, the year to date (in this case calendar year 1994) and cumulative data, usually from the date of commercial operation. The data is not independently verified, but various computer checks are made. The report is divided into two sections. The first contains summary highlights and the second contains data on each individual unit in commercial operation. Section 1 capacity and availability factors are simple arithmetic averages. Section 2 items in the cumulative column are generally as reported by the licensee and notes as to the use of weighted averages and starting dates other than commercial operation are provided.

  5. DIII-D research operations. Annual report, October 1, 1991--September 30, 1992

    SciTech Connect (OSTI)

    Baker, D. [ed.

    1993-05-01T23:59:59.000Z

    This report discusses the research on the following topics: DIII-D program overview; divertor and boundary research program; advanced tokamak studies; tokamak physics; operations; program development; support services; contribution to ITER physics R&D; and collaborative efforts.

  6. Licensed operating reactors: Status summary report data as of December 31, 1991. Volume 16

    SciTech Connect (OSTI)

    NONE

    1992-03-01T23:59:59.000Z

    The Nuclear Regulatory Commission`s annual summary of licensed nuclear power reactor data is based primarily on the report of operating data submitted by licensees for each unit for the month of December because that report contains data for the month of December, the year to date (in this case calendar year 1991) and cumulative data, usually from the date of commercial operation. The data is not independently verified, but various computer checks are made. The report is divided into two sections. The first contains summary highlights and the second contains data on each individual unit in commercial operation. Section 1 capacity and availability factors are simple arithmetic averages. Section 2 items in the cumulative column are generally as reported by the licensee and notes as to the use of weighted averages and starting dates other than commercial operation are provided.

  7. Electric and Hybrid Vehicle Program: Site Operator Program. Quarterly progress report, April--June 1995

    SciTech Connect (OSTI)

    Kiser, D.M.; Brown, H.L.

    1995-09-01T23:59:59.000Z

    This quarterly report details activities of the Department of Energy (DOE) Site Operator Program for the months of April, May, and June 1995. The 12 program participants, their geographic locations, and the principal thrusts of their efforts are provided.

  8. The Influence of Individual Audit Committee Chairs, CEOs, and CFOs on Corporate Reporting and Operating Decisions

    E-Print Network [OSTI]

    Lawson, Bradley

    2012-10-19T23:59:59.000Z

    This paper examines the association between individual managers and corporate reporting and operating decisions. To examine this question, I develop a dataset of 241 individual CEOs and CFOs, as well as audit committee chairs, covering the period...

  9. Sensitivity of Gaussian Channel Capacity and ate-Distortion Function to nonGaussian Contamination

    E-Print Network [OSTI]

    Verdú, Sergio

    Sensitivity of Gaussian Channel Capacity and ate-Distortion Function to nonGaussian Contamination-Gaussian contaminating noise. Although the ca- pacity of such channels cannot be evaluated in general, we analyze the decrease in capacity, or sensitivity of the channel capacity to the weak contaminating noise. We show

  10. MuseuM AssociAtes, inc. A 501(c)(3) not-For-Profit organization

    E-Print Network [OSTI]

    Missouri-Columbia, University of

    MuseuM AssociAtes, inc. A 501(c)(3) not-For-Profit organization in support of the Museum of Art on canvas (61.78) samuel H. Kress study collection (K1112) Printing provided by corporate sponsor ® MuseuM, May 3, 2014 For the benefit of the university of Missouri Museum of Art and Archaeology columbia

  11. Load Board Designs Using Compound Dot Technique and Phase Detector for Hierarchical ATE Calibrations

    E-Print Network [OSTI]

    Ayers, Joseph

    calibration of ATE with or without a single reference clock. Two different relay tree structures's IC test systems have achieved 1024 tester pins per testhead in Gigahertz frequency, and more pins drive edge and the compare edge. It is impossible, however, to build a RF relay matrix for every pin

  12. WASTE PACKAGE OPERATIONS FY99 CLOSURE METHODS REPORT

    SciTech Connect (OSTI)

    M. C. Knapp

    1999-09-23T23:59:59.000Z

    The waste package (WP) closure weld development task is part of a larger engineering development program to develop waste package designs. The purpose of the larger waste package engineering development program is to develop nuclear waste package fabrication and closure methods that the Nuclear Regulatory Commission will find acceptable and will license for disposal of spent nuclear fuel (SNF), non-fuel components, and vitrified high-level waste within a Monitored Geologic Repository (MGR). Within the WP closure development program are several major development tasks, which, in turn, are divided into subtasks. The major tasks include: WP fabrication development, WP closure weld development, nondestructive examination (NDE) development, and remote in-service inspection development. The purpose of this report is to present the objectives, technical information, and work scope relating to the WP closure weld development.and NDE tasks and subtasks and to report results of the closure weld and NDE development programs for fiscal year 1999 (FY-99). The objective of the FY-99 WP closure weld development task was to develop requirements for closure weld surface and volumetric NDE performance demonstrations, investigate alternative NDE inspection techniques, and develop specifications for welding, NDE, and handling system integration. In addition, objectives included fabricating several flat plate mock-ups that could be used for NDE development, stress relief peening, corrosion testing, and residual stress testing.

  13. Design, Operations, and Safety Report for the MERIT Target System

    SciTech Connect (OSTI)

    Graves, Van B [ORNL; Spampinato, Philip Thomas [ORNL

    2007-09-01T23:59:59.000Z

    The Mercury Intense Target Project (MERIT) is a proof-of-principal experiment to determine the feasibility of using a free-jet of Hg as a spallation target in a Neutrino Factory or a Muon Collider facility. The 1-cm-diameter, 20-m/sec jet will be generated inside a 15-Tesla magnetic field, and high-speed optical diagnostics will be used to photograph the interaction between the Hg jet and a 24-GeV proton beam.The experiment is scheduled to be conducted at CERN in 2007. ORNL is responsible for the design, fabrication, and testing of a system to deliver the Hg jet within the confines of the 15-cm magnet bore. This report documents the functional and safety requirements of the Hg system along with descriptions of its interfaces to the other experimental equipment.

  14. Operating experience feedback report: Assessment of spent fuel cooling. Volume 12

    SciTech Connect (OSTI)

    Ibarra, J.G.; Jones, W.R.; Lanik, G.F.; Ornstein, H.L.; Pullani, S.V.

    1997-02-01T23:59:59.000Z

    This report documents the results of an independent assessment by a team from the Office of Analysis and Evaluation of Operational Data of spent-fuel-pool (SFP) cooling in operating nuclear power plants. The team assessed the likelihood and consequences of an extended loss of SFP cooling and suggested corrective actions, based on their findings.

  15. NSTX Weekly Report (Apr. 2, 2010) FY 2010 NSTX plasma operations

    E-Print Network [OSTI]

    Princeton Plasma Physics Laboratory

    NSTX Weekly Report (Apr. 2, 2010) FY 2010 NSTX plasma operations Planned: Total - 15 run weeks experimental operations began this week with the completion of machine proposals (XMP's) to evaluate machine was used extensively this week, as well as neutral beam injection and machine's error field control. HHFW

  16. Smart Infrared Inspection System Field Operational Test Final Report

    SciTech Connect (OSTI)

    Siekmann, Adam [ORNL; Capps, Gary J [ORNL; Franzese, Oscar [ORNL; Lascurain, Mary Beth [ORNL

    2011-06-01T23:59:59.000Z

    The Smart InfraRed Inspection System (SIRIS) is a tool designed to assist inspectors in determining which vehicles passing through the SIRIS system are in need of further inspection by measuring the thermal data from the wheel components. As a vehicle enters the system, infrared cameras on the road measure temperatures of the brakes, tires, and wheel bearings on both wheel ends of commercial motor vehicles (CMVs) in motion. This thermal data is then presented to enforcement personal inside of the inspection station on a user friendly interface. Vehicles that are suspected to have a violation are automatically alerted to the enforcement staff. The main goal of the SIRIS field operational test (FOT) was to collect data to evaluate the performance of the prototype system and determine the viability of such a system being used for commercial motor vehicle enforcement. From March 2010 to September 2010, ORNL facilitated the SIRIS FOT at the Greene County Inspection Station (IS) in Greeneville, Tennessee. During the course of the FOT, 413 CMVs were given a North American Standard (NAS) Level-1 inspection. Of those 413 CMVs, 384 were subjected to a SIRIS screening. A total of 36 (9.38%) of the vehicles were flagged by SIRIS as having one or more thermal issues; with brakes issues making up 33 (91.67%) of those. Of the 36 vehicles flagged as having thermal issues, 31 (86.11%) were found to have a violation and 30 (83.33%) of those vehicles were placed out-of-service (OOS). Overall the enforcement personnel who have used SIRIS for screening purposes have had positive feedback on the potential of SIRIS. With improvements in detection algorithms and stability, the system will be beneficial to the CMV enforcement community and increase overall trooper productivity by accurately identifying a higher percentage of CMVs to be placed OOS with minimal error. No future evaluation of SIRIS has been deemed necessary and specifications for a production system will soon be drafted.

  17. Liquid and Gaseous Waste Operations Department annual operating report, CY 1992

    SciTech Connect (OSTI)

    Gillespie, M.A.; Maddox, J.J.; Scott, C.B.

    1993-03-01T23:59:59.000Z

    A total of 6.05 x 10{sup 7} gal of liquid waste was decontaminated by the Process Waste Treatment Plant (PWTP) ion exchange system during CY 1992. This averaged to 115 gpm throughout the year. When necessary, a wastewater sidestream of 50--80 gpm was treated through the use of a natural zeolite treatment system. An additional 8.00 x 10{sup 6} gal (average of 15 gpm throughout the year) were treated by the zeolite system. Therefore, the average total flow treated at the PWTP for CY 1992 was 130 gpm. In mid-June, the zeolite system was repiped to allow it the capability to treat the ion exchange system`s discharge due to rising Cs problems in the wastewater. While being used to treat the ion exchange system`s discharge, it cannot treat a sidestream of wastewater. During the year, the regeneration of the cation exchange resins resulted in the generation of 7.83 x 10{sup 3} gal of liquid low-level waste (LLLW) concentrate and 1.15 x 10{sup 4} gal of LLLW evaporator feed. The head-end softening process (precipitation/clarification) generated 604 drums (4.40 x 10{sup 3} ft{sup 3}) of solid low-level waste sludge. The zeolite treatment system generated approximately 8.40 x 10{sup 2} ft{sup 3} of spent zeolite resin, which was turned over to the Solid Waste Operations Department for disposal. See Table 1 for a monthly summary of activities at the PWTP. Figures 1, 2, 3, and 4 show a comparison of operations at the PWTP in 1992 with previous years. Figure 5 shows a comparison of annual rainfall at Oak Ridge National Laboratory (ORNL) since 1987. A total of 1.55 x 10{sup 8} gal of liquid waste (average of 294 gpm throughout the year) was treated at the Nonradiological Wastewater Treatment Plant (NRWTP). Of this amount, 1.40 x 10{sup 7} gal were treated by the precipitation/clarification process for removal of heavy metals. Twenty-five boxes (1.60 x 10{sup 3} ft{sup 3}) of solid sludge generated by the precipitation/clarification process were removed from the filter press room.

  18. Liquid and Gaseous Waste Operations Department annual operating report, CY 1992

    SciTech Connect (OSTI)

    Gillespie, M.A.; Maddox, J.J.; Scott, C.B.

    1993-03-01T23:59:59.000Z

    A total of 6.05 x 10[sup 7] gal of liquid waste was decontaminated by the Process Waste Treatment Plant (PWTP) ion exchange system during CY 1992. This averaged to 115 gpm throughout the year. When necessary, a wastewater sidestream of 50--80 gpm was treated through the use of a natural zeolite treatment system. An additional 8.00 x 10[sup 6] gal (average of 15 gpm throughout the year) were treated by the zeolite system. Therefore, the average total flow treated at the PWTP for CY 1992 was 130 gpm. In mid-June, the zeolite system was repiped to allow it the capability to treat the ion exchange system's discharge due to rising Cs problems in the wastewater. While being used to treat the ion exchange system's discharge, it cannot treat a sidestream of wastewater. During the year, the regeneration of the cation exchange resins resulted in the generation of 7.83 x 10[sup 3] gal of liquid low-level waste (LLLW) concentrate and 1.15 x 10[sup 4] gal of LLLW evaporator feed. The head-end softening process (precipitation/clarification) generated 604 drums (4.40 x 10[sup 3] ft[sup 3]) of solid low-level waste sludge. The zeolite treatment system generated approximately 8.40 x 10[sup 2] ft[sup 3] of spent zeolite resin, which was turned over to the Solid Waste Operations Department for disposal. See Table 1 for a monthly summary of activities at the PWTP. Figures 1, 2, 3, and 4 show a comparison of operations at the PWTP in 1992 with previous years. Figure 5 shows a comparison of annual rainfall at Oak Ridge National Laboratory (ORNL) since 1987. A total of 1.55 x 10[sup 8] gal of liquid waste (average of 294 gpm throughout the year) was treated at the Nonradiological Wastewater Treatment Plant (NRWTP). Of this amount, 1.40 x 10[sup 7] gal were treated by the precipitation/clarification process for removal of heavy metals. Twenty-five boxes (1.60 x 10[sup 3] ft[sup 3]) of solid sludge generated by the precipitation/clarification process were removed from the filter press room.

  19. Liquid and Gaseous Waste Operations Project Annual Operating Report CY 1999

    SciTech Connect (OSTI)

    Maddox, J.J.; Scott, C.B.

    2000-03-01T23:59:59.000Z

    A total of 5.77 x 10 7 gallons (gal) of liquid waste was decontaminated by the Process Waste Treatment Complex (PWTC) - Building 3544 ion exchange system during calendar year (CY) 1999. This averaged to 110 gpm throughout the year. An additional 3.94 x 10 6 gal of liquid waste (average of 8 gpm throughout the year) was decontaminated using the zeolite treatment system due to periods of high Cesium levels in the influent wastewater. A total of 6.17 x 10 7 gal of liquid waste (average of 118 gpm throughout the year) was decontaminated at Building 3544 during the year. During the year, the regeneration of the ion exchange resins resulted in the generation of 8.00 x 10 3 gal of Liquid Low-Level Waste (LLLW) concentrate and 9.00 x 10 2 gal of LLLW supernate. See Table 1 for a monthly summary of activities at Building 3544. Figure 1 shows a diagram of the Process Waste Collection and Transfer System and Figure 2 shows a diagram of the Building 3544 treatment process. Figures 3, 4 5, and 6 s how a comparison of operations at Building 3544 in 1997 with previous years. Figure 7 shows a comparison of annual rainfall at Oak Ridge National Laboratory (ORNL) since 1995.

  20. Licensed operating reactors. Status summary report data as of December 31, 1993

    SciTech Connect (OSTI)

    Hartfield, R.A.

    1994-03-01T23:59:59.000Z

    The Nuclear Regulatory Commissions annual summary of licensed nuclear power reactor data is based primarily on the report of operating data submitted by licensees for each unit for the month of December, the year to date (in this case calendar year 1993) and cumulative data, usually for the date of commercial operation. The data is not independently verified, but various computer checks are made. The report is divided into two sections. The first contains summary highlights and the second contains data on each individual unit in commercial operation. Section 1 capacity and availability factors are simple arithmetic averages. Section 2 items in the cumulative column are generally as reported by the licensee and notes as to the use of weighted averages and starting dates other than commercial operation are provided.

  1. Operable Unit 3-13, Group 7, SFE-20 Hot Waste Tank System Remedial Action Report

    SciTech Connect (OSTI)

    Lee Davison

    2009-06-30T23:59:59.000Z

    This Remedial Action Report summarizes activities undertaken to remediate the Operable Unit 3-13, Group 7, SFE-20 Hot Waste Tank System at the Idaho Nuclear Technology and Engineering Center at the Idaho National Laboratory Site. The site addressed in this report was defined in the Operable Unit 3-13 Record of Decision and subsequent implementing documents. This report concludes that remediation requirements and cleanup goals established for the site have been accomplished and is hereafter considered a No Further Action site.

  2. Office for Analysis and Evaluation of Operational Data. Annual report, 1994-FY 95

    SciTech Connect (OSTI)

    none,

    1996-07-01T23:59:59.000Z

    The United States Nuclear Regulatory Commission`s Office for Analysis and Evaluation of Operational Data (AEOD) has published reports of its activities since 1984. The first report covered January through June of 1984, and the second report covered July through December 1984. Since those first two semiannual reports, AEOD has published annual reports of its activities from 1985 through 1993. Beginning with the report for 1986, AEOD Annual Reports have been published as NUREG-1272. Beginning with the report for 1987, NUREG-1272 has been published in two parts, No. 1 covering power reactors and No. 2 covering nonreactors (changed to {open_quotes}nuclear materials{close_quotes} with the 1993 report). The 1993 AEOD Annual Report was NUREG-1272, Volume 8. AEOD has changed its annual report from a calendar year to a fiscal year report to be consistent with the NRC Annual Report and to conserve staff resources. NUREG-1272, Volume 9, No. 1 and No. 2, therefore, are combined calendar year 1994 (1994) and fiscal year 1995 (FY 95) reports which describe activities conducted between January 1, 1994, and September 30, 1995. Certain data which have historically been reported on a calendar year basis, however, are complete through calendar year 1995. Throughout this report, whenever information is presented for fiscal year 1995, it is designated as FY 95 data. Calendar year information is always designated by the four digits of the calendar year. This report, NUREG-1272, Volume 9, No. 1, covers power reactors and presents an overview of the operating experience of the nuclear power industry from the NRC perspective. NUREG-1272, Vol. 9, No. 2, covers nuclear materials and presents a review of the events and concerns associated with the use of licensed material in non-power reactor applications. A new part has been added, NUREG-1272, Volume 9, No. 3, which covers technical training and presents the activities of the Technical Training Center in FY 95 in support of the NRC`s mission.

  3. Operational test report for LERF Basin 242AL-44 integrity test

    SciTech Connect (OSTI)

    Galioto, T.M.

    1994-11-08T23:59:59.000Z

    This operational test report documents the results of LERF operational testing per operational test procedure (OTP) TFPE-WP-0231, ``LERF Basin Integrity Testing.`` The primary purpose of the OTP was to resolve test exceptions generated as a result of TFPE-WP-0184. The TOP was prepared and performed in accordance with WHC-SD-534-OTP-002, ``Operational Test Plan for the 242-A Evaporator Upgrades and the Liquid Effluent Retention Facility.`` WHC-S-086, ``Specification for Operational Testing of the Liquid Effluent Retention Facility, Basin Integrity Testing,`` identified the test requirements and acceptance criteria. The completed, signed-off test procedure is contained in Appendix A. The test log is contained in Appendix B. Section 2.1 describes all the test exceptions written during performance of the Operational Test Procedure. The test revisions generated during the testing are discussed in Section 2.2. The dispositioned test exception forms are contained in Appendix C.

  4. Office for Analysis and Evaluation of Operational Data. 1992 annual report: Nonreactors: Volume 7, No. 2

    SciTech Connect (OSTI)

    Not Available

    1993-10-01T23:59:59.000Z

    The annual report of the US Nuclear Regulatory Commission`s Office for Analysis and Evaluation of Operational Data (AEOD) is devoted to the activities performed during 1992. The report is published in two separate parts. NUREG-1272, Vol. 7, No. 1, covers power reactors and presents an overview of the operating experience of the nuclear power industry from the NRC perspective, including comments about the trends of some key performance measures. The report also includes the principal findings and issues identified in AEOD studies over the past year and summarizes information from such sources as licensee event reports, diagnostic evaluations, and reports to the NRC`s Operations Center. NUREG-1272, Vol. 7, No. 2, covers nonreactors and presents a review of the events and concerns during 1992 associated with the use of licensed material in nonreactor applications, such as personnel overexposures and medical misadministrations. Both reports also contain a discussion of the Incident Investigation Team program and summarize both the Incident Investigation Team and Augmented Inspection Team reports. Each volume contains a list of the AEOD reports issued for 1981--1992.

  5. Office for Analysis and Evaluation of Operational Data 1996 annual report. Volume 10, Number 1: Reactors

    SciTech Connect (OSTI)

    NONE

    1997-12-01T23:59:59.000Z

    This annual report of the US Nuclear Regulatory Commission`s Office for Analysis and Evaluation of Operational Data (AEOD) describes activities conducted during 1996. The report is published in three parts. NUREG-1272, Vol. 10, No. 1, covers power reactors and presents an overview of the operating experience of the nuclear power industry from the NRC perspective, including comments about trends of some key performance measures. The report also includes the principal findings and issues identified in AEOD studies over the past year and summarizes information from such sources as licensee event reports and reports to the NRC`s Operations Center. NUREG-1272, Vol. 10, No. 2, covers nuclear materials and presents a review of the events and concerns during 1996 associated with the use of licensed material in nonreactor applications, such as personnel overexposures and medical misadministrations. Both reports also contain a discussion of the Incident Investigation Team program and summarize both the Incident Investigation Team and Augmented Inspection Team reports. Each volume contains a list of the AEOD reports issued from CY 1980 through 1996. NUREG-1272, Vol. 10, No. 3, covers technical training and presents the activities of the Technical Training Center in support of the NRC`s mission in 1996.

  6. Office for Analysis and Evaluation of Operational Data 1990 annual report

    SciTech Connect (OSTI)

    None

    1991-07-01T23:59:59.000Z

    The annual report of the US Nuclear Regulatory Commission's Office for Analysis and Evaluation of Operational Data (AEOD) is devoted to the activities performed during 1990. The report is published in two separate parts. This document NUREG-1272, Vol. 5, No. 1, covers power reactors and presents an overview of the operating experience of the nuclear power industry from the NRC perspective, including comments about the trends of some key performance measures. The report also includes the principal findings and issues identified in AEOD studies over the past year and summarizes information from such sources as licensee event reports, diagnostic evaluations, and reports to the NRC's Operations Center. NUREG-1272, Vol.5, No. 2, covers nonreactors and presents a review of the events and concerns during 1990 associated with the use of licensed material in nonreactor applications, such as personnel overexposures and medical misadministrations. The reports contain a discussion of the Incident Investigation Team program and summarize the Incident Investigation Team and Augmented Inspection Team reports for that group of licensees. Each volume contains a list of the AEOD reports issued for 1980 through 1990. 9 figs., 8 tabs.

  7. Westinghouse Hanford Company effluent report for 300, 400, and 1100 Area operations for calendar year 1989

    SciTech Connect (OSTI)

    McCarthy, M.J.

    1990-09-01T23:59:59.000Z

    The report tabulates both radioactive and nonradioactive liquid and airborne effluent data for 300, 400, and 1100 Area operations at the Hanford Site. The 300 Area is primarily a research and development area. The 400 Area houses the Fast Flux Test Facility. The 1100 Area contains central stores and vehicle maintenance facilities. Releases to the environment from Westinghouse Hanford Company operations within these areas during calendar year 1989 were both consistent with previous years and within regulatory limits. 2 refs., 10 tabs.

  8. Operational readiness review for the Waste Experimental Reduction Facility. Final report

    SciTech Connect (OSTI)

    Not Available

    1993-11-01T23:59:59.000Z

    An Operational Readiness Review (ORR) at the Idaho National Engineering Laboratory`s (INEL`s) Waste Experimental Reduction Facility (WERF) was conducted by EG&G Idaho, Inc., to verify the readiness of WERF to resume operations following a shutdown and modification period of more than two years. It is the conclusion of the ORR Team that, pending satisfactory resolution of all pre-startup findings, WERF has achieved readiness to resume unrestricted operations within the approved safety basis. ORR appraisal forms are included in this report.

  9. Measurement of Lake Roosevelt Biota in Relation to Reservoir Operations : Final Report 1993.

    SciTech Connect (OSTI)

    Voeller, Amy C.

    1993-01-01T23:59:59.000Z

    The purpose of this study was to collect biological data from Lake Roosevelt to be used in the design of a computer model that will predict biological responses to reservoir operations as part of the System Operation Review Program. This study worked in conjunction with Lake Roosevelt Monitoring Project which investigated the effectiveness of two kokanee salmon hatcheries. This report summarized the data collected from Lake Roosevelt from 1993 and includes limnological, reservoir operation, zooplankton, benthic macroinvertebrate, experimental trawling, and net-pen rainbow trout tagging data. Major components of the Lake Roosevelt model include quantification of impacts to zooplankton, benthic macroinvertebrates, and fish caused by reservoir drawdowns and low water retention times.

  10. Report to the US Nuclear Regulatory Commission on Analysis and Evaluation of Operational Data, 1986

    SciTech Connect (OSTI)

    none,

    1987-05-01T23:59:59.000Z

    This annual report of the US Nuclear Regulatory Commission's Office for Analysis and Evaluation of Operational Data (AEOD) is devoted to the activities performed during calendar year 1986. Comments and observations are provided on operating experience at nuclear power plants and other NRC licensees, including results from selected AEOD studies; summaries of abnormal occurrences involving US nuclear plants; reviews of licensee event reports and their quality, reactor scram experience from 1984 to 1986, engineered safety features actuations, and the trends and patterns analysis program; and assessments of nonreactor and medical misadministration events. In addition, the report provides the year-end status of all recommendations included in AEOD studies, and listings of all AEOD reports issued from 1980 through 1986.

  11. Task 23 - background report on subsurface environmental issues relating to natural gas sweetening and dehydration operations. Topical report, February 1, 1994--February 28, 1996

    SciTech Connect (OSTI)

    Sorensen, J.A.

    1998-12-31T23:59:59.000Z

    This report describes information pertaining to environmental issues, toxicity, environmental transport, and fate of alkanolamines and glycols associated with natural gas sweetening and dehydration operations. Waste management associated with the operations is also discussed.

  12. Site Environmental Report for Calendar Year 1999. DOE Operations at The Boeing Company, Rocketdyne

    SciTech Connect (OSTI)

    None

    2000-09-01T23:59:59.000Z

    OAK A271 Site Environmental Report for Calendar Year 1999. DOE Operations at The Boeing Company, Rocketdyne. This Annual Site Environmental Report (ASER) for 1999 describes the environmental conditions related to work performed for the Department of Energy (DOE) at Area IV of the Rocketdyne Santa Susana Field Laboratory (SSFL). In the past, these operations included development, fabrication, and disassembly of nuclear reactors, reactor fuel, and other radioactive materials under the former Atomics International Division. Other activities included the operation of large-scale liquid metal facilities for testing of liquid metal fast breeder components at the Energy Technology Engineering Center (ETEC), a government-owned, company-operated test facility within Area IV. All nuclear work was terminated in 1988, and subsequently, all radiological work has been directed toward decontamination and decommissioning (D&D) of the previously used nuclear facilities and associated site areas. Large-scale D&D activities of the sodium test facilities began in 1996. This Annual Site Environmental Report provides information showing that there are no indications of any potential impact on public health and safety due to the operations conducted at the SSFL. All measures and calculations of off-site conditions demonstrate compliance with applicable regulations, which provide for protection of human health and the environment.

  13. Integrated Hatchery Operations Team: Policies and Procedures for Columbia Basin Anadromous Salmonid Hatcheries, 1994 Annual Report.

    SciTech Connect (OSTI)

    Integrated Hatchery Operations Team (Northwest Power Planning Council, Portland, OR)

    1995-01-01T23:59:59.000Z

    This document outlines regional policies and procedures for hatchery operations in the Columbia River Basin. The purpose of these policies is to provide regional guidelines by which all anadromous fish hatcheries will be operated. These policies will be adopted by the fisheries co-managers, and will provide guidance to operate hatcheries in an efficient and biologically sound manner. The hatchery policies presented in this manual are not intended to establish production priorities. Rather, the intent is to guide hatchery operations once production numbers are established. Hatchery operations discussed in this report include broodstock collection, spawning, incubation of eggs, fish rearing and feeding, fish release, equipment maintenance and operations, and personnel training. Decisions regarding production priorities must be provided by fishery managers through a comprehensive plan that addresses both natural and hatchery fish production. The Integrated Hatchery Operations Team is a multi-agency group called for by the Northwest Power Planning Council. This team was directed to develop new basinwide policies for managing and operating all existing and future anadromous fish hatcheries in the Columbia River Basin. The parties pledge to confer with each other and to use their authorities and resources to accomplish these mutually acceptable hatchery practices.

  14. Field Report: Long-Baseline Acoustic Navigation for Under-Ice AUV Operations

    E-Print Network [OSTI]

    Singh, Hanumant

    . The drifting pack ice made vehicle recovery more challenging and necessitated atypical adaptations relatively unexplored on account of its location beneath the permanent drifting Arctic ice pack. OurField Report: Long-Baseline Acoustic Navigation for Under-Ice AUV Operations Michael V. Jakuba

  15. Close Out Report for the Ash Pit Operable Unit I Area of Concern 2F

    E-Print Network [OSTI]

    I to the early 1950's. The Ash Pits were also used for disposal of coal ash from various buildingsFinal Close Out Report for the Ash Pit Operable Unit I Area of Concern 2F February 5, 2004..................................................................................................2 Figure 1 - Ash Level Verification Borings

  16. Definition and Evaluation of Bus and Truck Automation Operations Concepts: Final Report

    E-Print Network [OSTI]

    Taso, H. S. Jacob; Botha, Jan L.

    2003-01-01T23:59:59.000Z

    fuel efficiency Higher system capacity Rural Truck-AHS Long-haulhaul other companies’ trucks or just trailers; scheduled AHS Hauling services Better fuelhaul on some freight corridors (expedited Bus and Truck AHS – Final Report to California PATH Mainline Operations: Fuel

  17. Electric and Hybrid Vehicle Program: Site Operation Program. Quarterly progress report, July--September 1995

    SciTech Connect (OSTI)

    Francfort, J.; Bassett, R.R.; Briasco, S. [and others

    1995-12-01T23:59:59.000Z

    The Site Operator Program has evolved substantially since its inception in response to the Electric Vehicle Research and Demonstration Act of 1976. In its original form, a commercialization effort was intended but this was not feasible for lack of vehicle suppliers and infrastructure. Nonetheless, with DOE sponsorship and technical participation, a few results (primarily operating experience and data) were forthcoming. The current Program comprises eleven sites and over 200 vehicles, of which about 50 are latest generation vehicles. DOE partially funds the Program participant expenditures and the INEL receives operating and maintenance data for the DOE-owned, and participant-owned or monitored vehicles, as well as Program reports. As noted elsewhere in this report, participants represent several widely differing categories: electric utilities, academic institutions, and federal agencies. While both the utilities and the academic institutions tend to establish beneficial relationships with the industrial community.

  18. Electric and Hybrid Vehicle Program; Site Operator Program. Quarterly progress report, October--December 1991

    SciTech Connect (OSTI)

    Warren, J.F.

    1992-01-01T23:59:59.000Z

    Activities during the first quarter centered around integrating the new participants into the program. A meeting of the Site Operators, in conjunction with the first meeting of the Electric Vehicle Users Task Force, was held in October. A second meeting of the Task Force was held in December. During these meetings the new contractual requirements were explained to the participants. The Site Operator Data Base was distributed and explained. The Site Operators will begin using the data base in December 1991 and will supply the operating and maintenance data to the INEL on a monthly basis. The Operators requested that they be able to have access to the data of the other Operators and it was agreed that they would be provided this on floppy disk monthly from the INEL. Presentations were made to the DOE sponsored Automotive Technology Development-Contractors Coordination Meeting in October. An overview of the program was given by EG&G. Representatives from Arizona Public Service, Texas A&M University, and York Technical College provided details of their programs and the results and future goals. Work was begun on commercializing the Versatile Data Acquisition System (VDAS). A Scope of Work has been written for a Cooperative Research and Development Agreement (CRADA) to be submitted to the USABC. If implemented, the CRADA will provide funds for the development and commercialization of the VDAS. Participants in the Site Operator Program will test prototypes of the system within their fleets, making the data available to the USABC and other interested organizations. The USABC will provide recommendations on the data to be collected. Major activities by the majority of the Operators were involved with the continued operation and demonstration of existing vehicles. In addition, several of the operators were involved in identifying and locating vehicles to be added to their fleets. A list of the vehicles in each Site Operator fleet is included as Appendix A to this report.

  19. Phase report 1C, TA-21 operable unit RCRA Facility Investigation, Outfalls Investigation

    SciTech Connect (OSTI)

    Not Available

    1994-02-28T23:59:59.000Z

    This phase report summarizes the results of field investigations conducted in 1992 at Technical Area 21 of Los Alamos National Laboratory, as prescribed by the RCRA Facility Investigation work plan for the Technical Area 21 operable unit (also known as OU 1106). This phase report is the last part of a three-part phase report describing the results of field work conducted in 1992 at this operable unit. Phase Report lA, issued on l4 June l993, summarized site geologic characterization activities. Phase report 1B, issued on 28 January 1994, included an assessment of site-wide surface soil background, airborne emissions deposition, and contamination in the locations of two former air filtration buildings. The investigations assessed in Phase Report 1C include field radiation surveys and surface and near-surface sampling to characterize potential contamination at 25 outfalls and septic systems listed as SWMUs in the RFI work plan. Based on the RFI data, it is recommended that no further action is warranted for 8 SWMUs and further action is recommended for 3 SWMUs addressed in this phase report. For 14 SWMUs which represent no immediate threat to human health or environment, deferral of further action/no further action decisions is recommended until outstanding analytical data are received, sampling of adjacent SWMUs is completed, or decisions are made about the baseline risk assessment approach.

  20. Hydrogen and Hydrogen/Natural Gas Station and Vehicle Operations - 2006 Summary Report

    SciTech Connect (OSTI)

    Francfort; Donald Karner; Roberta Brayer

    2006-09-01T23:59:59.000Z

    This report is a summary of the operations and testing of internal combustion engine vehicles that were fueled with 100% hydrogen and various blends of hydrogen and compressed natural gas (HCNG). It summarizes the operations of the Arizona Public Service Alternative Fuel Pilot Plant, which produces, compresses, and dispenses hydrogen fuel. Other testing activities, such as the destructive testing of a CNG storage cylinder that was used for HCNG storage, are also discussed. This report highlights some of the latest technology developments in the use of 100% hydrogen fuels in internal combustion engine vehicles. Reports are referenced and WWW locations noted as a guide for the reader that desires more detailed information. These activities are conducted by Arizona Public Service, Electric Transportation Applications, the Idaho National Laboratory, and the U.S. Department of Energy’s Advanced Vehicle Testing Activity.

  1. Field Operations Program, Toyota PRIUS Hybrid Electric Vehicle Performance Characterization Report

    SciTech Connect (OSTI)

    Francfort, James Edward; Nguyen, N.; Phung, J.; Smith, J.; Wehrey, M.

    2001-12-01T23:59:59.000Z

    The U.S. Department of Energy’s Field Operations Program evaluates advanced technology vehicles in real-world applications and environments. Advanced technology vehicles include pure electric, hybrid electric, hydrogen, and other vehicles that use emerging technologies such as fuel cells. Information generated by the Program is targeted to fleet managers and others considering the deployment of advanced technology vehicles. As part of the above activities, the Field Operations Program has initiated the testing of the Toyota Prius hybrid electric vehicle (HEV), a technology increasingly being considered for use in fleet applications. This report describes the Pomona Loop testing of the Prius, providing not only initial operational and performance information, but also a better understanding of HEV testing issues. The Pomona Loop testing includes both Urban and Freeway drive cycles, each conducted at four operating scenarios that mix minimum and maximum payloads with different auxiliary (e.g., lights, air conditioning) load levels.

  2. Final report on evaluation of cyclocraft support of oil and gas operations in wetland areas

    SciTech Connect (OSTI)

    Eggington, W.J.; Stevens, P.M.; John, C.J.; Harder, B.J.; Lindstedt, D.M.

    1994-10-01T23:59:59.000Z

    The cyclocraft is a proven hybrid aircraft, capable of VTOL, lifting heavy and bulky loads, highly controllable, having high safety characteristics and low operating costs. Mission Research Corporation (MRC), under Department of Energy sponsorship, is evaluating the potential use of cyclocraft in the transport of drill rigs, mud, pipes and other materials and equipment, in a cost effective and environmentally safe manner, to support oil and gas drilling, production, and transportation operations in wetland areas. Based upon the results of an earlier parametric study, a cyclocraft design, having a payload capacity of 45 tons and designated H.1 Cyclocraft, was selected for further study, including the preparation of a preliminary design and a development plan, and the determination of operating costs. This report contains all of the results derived from the program to evaluate the use of cyclocraft in the support of oil and gas drilling and production operations in wetland areas.

  3. Annual Summary Report Calendar Year 2000 for the 100-HR-3, 100-KR-4, and 100-NR-2 Operable Units and Pump-and-Treat Operations

    SciTech Connect (OSTI)

    G. B. Mitchem

    2001-08-22T23:59:59.000Z

    This annual progress and performance evaluation report discusses the groundwater remedial actions in the 100 Area, including the interim actions at the 100-HR-3 and 100-KR-4 Operable Units, and also discusses the expedited response action in the 100-NR-2 operable unit.

  4. Interim operations report for atmospheric fluidized-bed combustion conversion at Northern States Power Company

    SciTech Connect (OSTI)

    Thimsen, D. (Hamilton Maurer International, Inc., Falcon Heights, MN (USA))

    1991-03-01T23:59:59.000Z

    Northern States Power Company converted its Black Dog Station Unit No. 2 boiler from a front wall fired pulverized coal boiler to a bubbling atmospheric fluidized bed combustor (AFBC) boiler. The resulting unit was uprated from 85 MWe to 130 MWe burning western subbituminous coal. This report describes the AFBC operating and maintenance experience in the startup period from initial operation in June 1986 through March 1989 when a turbine oil fire caused a forced outage of 8 months. A brief review of the construction history is given in Section 1. Section 2 chronicles the AFBC operation. Section 3 describes how the boiler is restarted under several conditions. The performance history of the systems in the AFBC that are peculiar to the AFBC process or directly impacted by the AFBC process are described in detail in Section 4. The AFBC conversion at the Black Dog station has met nearly all of the original design objectives: (1) The unit can operate at rated output of 130 MWe burning western subbituminous coal, (2) The design life of the unit has been extended 25 years, (3) It has been shown that the EPA New Source Performance Standards for NO{sub x} and SO{sub 2} can be met with no flue gas treatment, (4) Operators have conducted over 200 routine daily unit restarts confirming the ability of the unit to serve in daily cycling mode, and (5) A variety of fuels have been successfully burned in the AFBC. The only objective that remains partially achieved is routine operation at full load. The boiler/turbine/generator have been shown to be fully capable of operation at full load, but the electrostatic precipitators (which were largely unchanged during the retrofit) have been inadequate to allow full load operation while remaining within permitted opacity and particulate emissions. The unit is currently dispatched in daily cycling service and is limited to operation below 106 MWe by its emissions control permit. 12 refs., 34 figs., 6 tabs.

  5. Site operator program final report for fiscal years 1992 through 1996

    SciTech Connect (OSTI)

    Francfort, J.E. [Lockheed Martin Idaho Technologies Co., Idaho Falls, ID (United States). Idaho National Engineering and Environmental Lab.; Bassett, R.R. [Sandia National Labs., Albuquerque, NM (United States); Birasco, S. [Los Angeles Dept. of Water and Power, CA (United States)] [and others

    1998-01-01T23:59:59.000Z

    The Site Operator Program was an electric vehicle testing and evaluation program sponsored by US Department of Energy and managed at the Idaho National Engineering and Environmental Laboratory. The Program`s goals included the field evaluation of electric vehicles in real-world applications and environments; the support of electric vehicle technology advancement; the development of infrastructure elements necessary to support significant electric vehicle use; and increasing the awareness and acceptance of electric vehicles. This report covers Program activities from 1992 to 1996. The Site Operator Program ended in September 1996, when it was superseded by the Field Operations Program. Electric vehicle testing included baseline performance testing, which was performed in conjunction with EV America. The baseline performance parameters included acceleration, braking, range, energy efficiency, and charging time. The Program collected fleet operations data on electric vehicles operated by the Program`s thirteen partners, comprising electric utilities, universities, and federal agencies. The Program`s partners had over 250 electric vehicles, from vehicle converters and original equipment manufacturers, in their operating fleets. Test results are available via the World Wide Web site at http://ev.inel.gov/sop.

  6. Nez Perce Tribal Hatchery Project; Operations and Maintenance and Planning and Design, 2002 Annual Report.

    SciTech Connect (OSTI)

    Larson, Roy Edward; Walker, Grant W.; Penney, Aaron K. (Nez Perce Tribe, Lapwai, ID)

    2005-12-01T23:59:59.000Z

    This report fulfills the contract obligations based on the Statement of Work (SOW) for the project as contracted with Bonneville Power Administration (BPA). Nez Perce Tribal Hatchery (NPTH) Year-2002 annual report combines information from two contracts with a combined value of $3,036,014. Bonneville Power Administration identifies them as follows; (1) Part I--Operations and Maintenance--Project No. 1983-350-00, Contract No. 4504, and $2,682,635 which includes--Equipment costs of $1,807,105. (2) Part II--Planning and Design--Project No. 1983-35-04, Contract No. 4035, $352,379 for Clearwater Coho Restoration Master Plan development Based on NPPC authorization for construction and operation of NPTH, the annual contracts were negotiated for the amounts shown above under (1) and (2). Construction contracts were handled by BPA until all facilities are completed and accepted.

  7. Pilot plant UF/sub 6/ to UF/sub 4/ test operations report

    SciTech Connect (OSTI)

    Bicha, W.J.; Fallings, M.; Gilbert, D.D.; Koch, G.E.; Levine, P.J.; McLaughlin, D.F.; Nuhfer, K.R.; Reese, J.C.

    1987-02-01T23:59:59.000Z

    The FMPC site includes a plant designed for the reduction of uranium hexafluoride (UF/sub 6/) to uranium tetrafluoride (UF/sub 4/). Limited operation of the upgraded reduction facility began in August 1984 and continued through January 19, 1986. A reaction vessel ruptured on that date causing the plant operation to be shut down. The DOE conducted a Class B investigation with the findings of the investigation board issued in preliminary form in May 1986 and as a final recommendation in July 1986. A two-phase restart of the plant was planned and implemented. Phase I included implementing safety system modifications, changing reaction vessel temperature control strategy, and operating the reduction plant under an 8-week controlled test. The results of the test period are the subject of this report. 41 figs., 11 tabs.

  8. Conceptual design report for tank farm restoration and safe operations, project W-314

    SciTech Connect (OSTI)

    Briggs, S.R., Westinghouse Hanford

    1996-05-02T23:59:59.000Z

    This Conceptual Design Report (CDR) presents the conceptual level design approach that satisfies the established technical requirements for Project W-314, `Tank Farm Restoration and Safe Operations.` The CDR also addresses the initial cost and schedule baselines for performing the proposed Tank Farm infrastructure upgrades. The scope of this project includes capital improvements to Hanford`s existing tank farm facilities(primarily focused on Double- Shell Tank Farms) in the areas of instrumentation/control, tank ventilation, waste transfer, and electrical systems.

  9. Data validation report for the 100-HR-3 Operable Unit, fifth round groundwater samples

    SciTech Connect (OSTI)

    Vukelich, S.E. [Kearney (A.T.), Inc., Chicago, IL (United States)] [Kearney (A.T.), Inc., Chicago, IL (United States)

    1994-01-20T23:59:59.000Z

    The data from the chemical analysis of 68 samples from the 100-HR-3 Operable Unit Third Quarter 1993 Groundwater Sampling Investigation and their related quality assurance samples were reviewed and validated to verify that reported sample results were of sufficient quality to support decisions regarding remedial actions performed at the site. Sample analysis included inorganics and general chemical parameters. Fifty three samples were validated for radiochemical parameters.

  10. Solid Waste Operations Complex W-113: Project cost estimate. Preliminary design report. Volume IV

    SciTech Connect (OSTI)

    NONE

    1995-01-01T23:59:59.000Z

    This document contains Volume IV of the Preliminary Design Report for the Solid Waste Operations Complex W-113 which is the Project Cost Estimate and construction schedule. The estimate was developed based upon Title 1 material take-offs, budgetary equipment quotes and Raytheon historical in-house data. The W-113 project cost estimate and project construction schedule were integrated together to provide a resource loaded project network.

  11. Preliminary report on operational guidelines developed for use in emergency preparedness and response to a radiological dispersal device incident.

    SciTech Connect (OSTI)

    Yu, C.; Cheng, J.-J.; Kamboj, S.; Domotor, S.; Wallo, A.; Environmental Science Division; DOE

    2006-12-15T23:59:59.000Z

    This report presents preliminary operational guidelines and supporting work products developed through the interagency Operational Guidelines Task Group (OGT). The report consolidates preliminary operational guidelines, all ancillary work products, and a companion software tool that facilitates their implementation into one reference source document. The report is intended for interim use and comment and provides the foundation for fostering future reviews of the operational guidelines and their implementation within emergency preparedness and response initiatives in the event of a radiological dispersal device (RDD) incident. The report principally focuses on the technical derivation and presentation of the operational guidelines. End-user guidance providing more details on how to apply these operational guidelines within planning and response settings is being considered and developed elsewhere. The preliminary operational guidelines are categorized into seven groups on the basis of their intended application within early, intermediate, and long-term recovery phases of emergency response. We anticipate that these operational guidelines will be updated and refined by interested government agencies in response to comments and lessons learned from their review, consideration, and trial application. This review, comment, and trial application process will facilitate the selection of a final set of operational guidelines that may be more or less inclusive of the preliminary operational guidelines presented in this report. These and updated versions of the operational guidelines will be made available through the OGT public Web site (http://ogcms.energy.gov) as they become finalized for public distribution and comment.

  12. Operable Unit 1 remedial investigation report, Eielson Air Force Base, Alaska

    SciTech Connect (OSTI)

    Gilmore, T.J.; Fruland, R.M.; Liikala, T.L. [and others

    1994-06-01T23:59:59.000Z

    This remedial investigation report for operable Unit 1 (OU-1) at Eielson Air Force Base presents data, calculations, and conclusions as to the nature and extent of surface and subsurface contamination at the eight source areas that make up OU-1. The information is based on the 1993 field investigation result and previous investigations. This report is the first in a set of three for OU-1. The other reports are the baseline risk assessment and feasibility study. The information in these reports will lead to a Record of Decision that will guide and conclude the environmental restoration effort for OU-1 at Eielson Air Force Base. The primary contaminants of concern include fuels and fuel-related contaminants (diesel; benzene, toluene, ethylbenzene, and xylene; total petroleum hydrocarbon; polycyclic aromatic hydrocarbons), maintenance-related solvents and cleaners (volatile chlorinated hydrocarbons such as trichloroothylene), polychlorinated biphenyls, and dichlorodiphenyltrichloroethane (DDT). The origins of contaminants of concern include leaks from storage tanks, drums and piping, and spills. Ongoing operations and past sitewide practices also contribute to contaminants of concern at OU-1 source areas. These include spraying mixed oil and solvent wastes on unpaved roads and aerial spraying of DDT.

  13. Report on geological surveys in the 300-FF-1 operable unit

    SciTech Connect (OSTI)

    Sandness, G.A.

    1991-03-01T23:59:59.000Z

    This report describes a set of geophysical surveys performed by the Pacific Northwest Laboratory at selected locations within the 300-FF-1 Operable Unit at Hanford. Field work and preliminary data processing activities were initiated in September 1989. These actions were terminated by the Westinghouse Hanford Company before completion in December 1989. Work was reinitiated in October 1990, to complete the processing of the data that had already been collected and to report the results. Because the field work was only partially completed, the task objectives, as presented in the Statement of Work, could not be fully met. This report is, therefore, a progress report covering the work performed through December 11, 1989. This task involved (1) ground-penetrating radar surveys of the 618-4 and 618-5 Burial Grounds, and (2) ground-penetrating radar and electromagnetic induction surveys along the assumed routes of the abandoned process sewers and radioactive liquid waste sewers in the 300-FF-1 Operable Unit. The surveys in the burial grounds were intended to identify burial trenches and pits, to determine the depth of fill, and to locate waste materials, including any that might be outside the perimeter fences. The surveys along the sewer routes were intended, first, to confirm the locations of the sewers as shown on existing maps or to otherwise accurately determine their locations, and second, to attempt to identify locations of possible leaks. 3 refs., 3 figs., 2 tabs.

  14. Electric and Hybrid Vehicle Program, Site Operator Program. Quarterly progress report, January--March 1996

    SciTech Connect (OSTI)

    Francfort, J.E. [Lockheed Martin Idaho Technologies Co., Idaho Falls, ID (United States); Bassett, R.R. [Sandia National Labs., Albuquerque, NM (United States); Briasco, S. [Los Angeles City Dept. of Water and Power, CA (United States)] [and others

    1996-08-01T23:59:59.000Z

    Goals of the site operator program include field evaluation of electric vehicles (EVs) in real-world applications and environments, advancement of electric vehicle technologies, development of infrastructure elements necessary to support significant EV use, and increasing the awareness and acceptance of EVs by the public. The site operator program currently consists of 11 participants under contract and two other organizations with data-sharing agreements with the program. The participants (electric utilities, academic institutions, Federal agencies) are geographically dispersed within US and their vehicles see a broad spectrum of service conditions. Current EV inventories of the site operators exceeds 250 vehicles. Several national organizations have joined DOE to further the introduction and awareness of EVs, including: (1) EVAmerica (a utility program) and DOE conduct performance and evaluation tests to support market development for EVs; (2) DOE, DOT, the Electric Transportation Coalition, and the Electric Vehicle Association of the Americas are conducting a series of workshops to encourage urban groups in Clean Cities (a DOE program) to initiate the policies and infrastructure development necessary to support large-scale demonstrations, and ultimately the mass market use, of EVs. Current focus of the program is collection and dissemination of EV operations and performance data to aid in the evaluation of real- world EV use. This report contains several sections with vehicle evaluation as a focus: EV testing results, energy economics of EVs, and site operators activities.

  15. Measurement of Lake Roosevelt Biota in Relation to Reservoir Operations; 1992 Annual Report.

    SciTech Connect (OSTI)

    Griffith, Janelle R.; McDowell, Amy C.

    1996-01-01T23:59:59.000Z

    The purpose of this research project is to collect data to model resident fish requirements for Lake Roosevelt as part of the Bonneville Power Administration (BPA), Bureau of Reclamation (BoR), and U.S. Army Corps of Engineer`s (ACE) System Operation Review. The System Operation Review (SOR) is a tri-agency team functioning to review the use and partitioning of Columbia Basin waters. User groups of the Columbia have been defined as power, irrigation, flood control, anadromous fish, resident fish, wildlife, recreation, water quality, navigation, and cultural resources. Once completed the model will predict biological responses to different reservoir operation strategies. The model being developed for resident fish is based on Montana Department of Fish, Wildlife, and Parks model for resident fish requirements within Hungry Horse and Libby Reservoirs. While the Montana model predicts fish growth based on the impacts of reservoir operation and flow conditions on primary and secondary production levels, the Lake Roosevelt model will also factor in the affects of water retention time on zooplankton production levels and fish entrainment. Major components of the Lake Roosevelt model include: (1) quantification of impacts to zooplankton, benthic invertebrates, and fish caused by reservoir drawdowns and low water retention times; (2) quantification of number, distribution, and use of fish food organisms in the reservoir by season; (3) determination of seasonal growth of fish species as related to reservoir operations, prey abundance and utilization; and (4) quantification of entrainment levels of fish as related to reservoir operations and water retention times. This report contains the results of the resident fish system operation review program for Lake Roosevelt from January through December 1992.

  16. Report to the US Nuclear Regulatory Commission on analysis and evaluation of operational data - 1987: Power reactors

    SciTech Connect (OSTI)

    none,

    1988-10-01T23:59:59.000Z

    This annual report of the US Nuclear Regulatory Commission's Office for Analysis and Evaluation of Operational Data (AEOD) is devoted to the activities performed during 1987. The report is published in two volumes. NUREG-1272, Vol. 2, No. 1, covers Power Reactors and presents an overview of the operating experience of the nuclear power industry, with comments regarding the trends of some key performance measures. The report also includes the principal findings and issues identified in AEOD studies over the past year, and summarizes information from Licensee Event Reports, the NRC's Operations Center, and Diagnostic Evaluations. NUREG-1272, Vol. 2, No. 2, covers Nonreactors and presents a review of the nonreactors events and misadministration reports that were reported in 1987 and a brief synopsis of AEOD studies published in 1987. Each volume contains a list of the AEOD Reports issued for 1980-1987.

  17. Final Report on the Operation and Maintenance Improvement Program for Concentrating Solar Power Plants

    SciTech Connect (OSTI)

    Cohen Gilbert E.; Kearney, David W.; Kolb, Gregory J.

    1999-06-01T23:59:59.000Z

    This report describes the results of a six-year, $6.3 million project to reduce operation and maintenance (O&M) costs at power plants employing concentrating solar power (CSP) technology. Sandia National Laboratories teamed with KJC Operating Company to implement the O&M Improvement Program. O&M technologies developed during the course of the program were demonstrated at the 150-MW Kramer Junction solar power park located in Boron, California. Improvements were made in the following areas: (a) efficiency of solar energy collection, (b) O&M information management, (c) reliability of solar field flow loop hardware, (d) plant operating strategy, and (e) cost reduction associated with environmental issues. A 37% reduction in annual O&M costs was achieved. Based on the lessons learned, an optimum solar- field O&M plan for future CSP plants is presented. Parabolic trough solar technology is employed at Kramer Junction. However, many of the O&M improvements described in the report are also applicable to CSP plants based on solar power tower or dish/engine concepts.

  18. Superconducting Super Collider site environmental report for calendar year 1991. Pre-operational

    SciTech Connect (OSTI)

    NONE

    1995-05-01T23:59:59.000Z

    This is the first annual SER prepared for the SSC project. It is a pre-operational report, intended primarily to describe the baseline characterization of the Ellis County, Texas site that has been developed subsequent to the Environmental Impact Statement (EIS) and the Supplemental Environmental impact Statement (SEIS). As such, the emphasis will be on environmental compliance efforts, including monitoring and mitigation programs. The SER also reports on the measures taken to meet the commitments made in the EIS and SEIS. These measures are detailed in the Mitigation Action Plan (MAP) (Department of Energy (DOE), 1991), which was prepared following the signing of the Record of Decision (ROD) to construct the SSC in Texas. The SER will continue to be preoperational until the first high-energy (20 trillion electron volt or TeV) protons collisions are observed, at which point the SSC will become operational. At that time, the SER will place more emphasis on the radiological monitoring program. This SER will report on actions taken in 1991 or earlier and briefly mention some of those planned for calendar year 1992. AU actions completed in 1992 will be addressed in the SER for calendar year 1992.

  19. Remedial investigation/feasibility study report for Lower Watts Bar Reservoir Operable Unit

    SciTech Connect (OSTI)

    NONE

    1995-03-01T23:59:59.000Z

    This document is the combined Remedial Investigation and Feasibility Study Report for the lower Watts Bar Reservoir (LWBR) Operable Unit (OU). The LWBR is located in Roane, Rhea, and Meigs counties, Tennessee, and consists of Watts Bar Reservoir downstream of the Clinch river. This area has received hazardous substances released over a period of 50 years from the US Department of Energy`s Oak Ridge Reservation (ORR), a National Priority List site established under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). As required by this law, the ORR and all off-site areas that have received contaminants, including LWBR, must be investigated to determine the risk to human health and the environment resulting from these releases, the need for any remedial action to reduce these risks, and the remedial actions that are most feasible for implementation in this OU. Contaminants from the ORR are primarily transported to the LWBR via the Clinch River. There is little data regarding the quantities of most contaminants potentially released from the ORR to the Clinch River, particularly for the early years of ORR operations. Estimates of the quantities released during this period are available for most radionuclides and some inorganic contaminants, indicating that releases 30 to 50 years ago were much higher than today. Since the early 1970s, the release of potential contaminants has been monitored for compliance with environmental law and reported in the annual environmental monitoring reports for the ORR.

  20. Shutdown and low-power operation at commercial nuclear power plants in the United States. Final report

    SciTech Connect (OSTI)

    Not Available

    1993-09-01T23:59:59.000Z

    The report contains the results of the NRC Staff`s evaluation of shutdown and low-power operations at US commercial nuclear power plants. The report describes studies conducted by the staff in the following areas: Operating experience related to shutdown and low-power operations, probabilistic risk assessment of shutdown and low-power conditions and utility programs for planning and conducting activities during periods the plant is shut down. The report also documents evaluations of a number of technical issues regarding shutdown and low-power operations performed by the staff, including the principal findings and conclusions. Potential new regulatory requirements are discussed, as well as potential changes in NRC programs. A draft report was issued for comment in February 1992. This report is the final version and includes the responses to the comments along with the staff regulatory analysis of potential new requirements.

  1. Operation Cornerstone onsite radiological safety report for announced nuclear tests, October 1988--September 1989

    SciTech Connect (OSTI)

    Not Available

    1990-08-01T23:59:59.000Z

    Cornerstone was the name assigned to the series of underground nuclear experiments conducted at the Nevada Test Site (NTS) from October 1, 1988, through September 30, 1989. This report includes those experiments publicly announced. Remote radiation measurements were taken during and after each nuclear experiment by a telemetry system. Radiation Protection Technicians (RPT) with portable radiation detection instruments surveyed reentry routes into ground zeros (GZ) before other planned entries were made. Continuous surveillance was provided while personnel were in radiation areas and appropriate precautions were taken to protect persons from unnecessary exposure to radiation and toxic gases. Protective clothing and equipment were issued as needed. Complete radiological safety and industrial hygiene coverage were provided during drilling and mineback operations. Telemetered and portable radiation detector measurements are listed. Detection instrumentation used is described and specific operational procedures are defined.

  2. Rocky Mountain 1: Underground coal gasification test, Hanna, Wyoming. Volume 1. Operations. Summary report

    SciTech Connect (OSTI)

    Not Available

    1989-03-01T23:59:59.000Z

    The Rocky Mountain 1 underground coal gasification (UCG) test was conducted near Hanna, Wyoming during the period January 1986 through March 1988. The report focuses on operations phases that included site selection, facility design, facility construction, well drilling, gasification and environmental monitoring. Two technologies were evaluated as separate modules: the Extended Linked Well (ELW) and the Controlled Retracting Injection Point (CRIP) processes. The test results, along with a discussion of the key test parameters and conclusions of the gasification phase, are provided. A bibliography and schematics are included.

  3. Pipeline safety. Information on gas distribution system operators reporting unaccounted for gas

    SciTech Connect (OSTI)

    Not Available

    1986-02-01T23:59:59.000Z

    According to Department of Transportation records, 92 of the 1491 gas distribution system operators reported high levels of unaccounted for gas (unaccounted for gas is the difference between the amount of gas purchased and sold) for 1984, the latest year for which data were available. Of the 92 gas system operators, 64 were municipals (gas systems owned by a governmental entity, such as a city or county) and 28 were nonmunicipals. Based on the data we reviewed, these 92 gas systems did not report any accidents during calendar year 1984. Part I provides more details on the unaccounted for gas of municipal gas systems. Federal and industry officials consider that unaccounted for gas in excess of 15% of gas purchases high and worthy of investigation. High levels of unaccounted for gas can occur for a number of reasons, including errors in metering and billing, not accounting for gas used by city or company facilities, and leaking gas pipelines. While it may, a leak does not always indicate a safety problem. For example, a slow leak in an open area may not be a safety hazard. The Secretary has the authority to regulate any liquid deemed hazardous when transported by pipeline, and therefore could regulate hazardous liquids not currently regulated including methanol and carbon dioxide. However, the Department of Transportation has no plans to regulate any additional liquids. Part II provides more details. 4 figs., 2 tabs.

  4. Final Report - Advanced MEA's for Enhanced Operating Conditions, Amenable to High Volume Manufacture

    SciTech Connect (OSTI)

    Debe, Mark K.

    2007-09-30T23:59:59.000Z

    This report summarizes the work completed under a 3M/DOE contract directed at advancing the key fuel cell (FC) components most critical for overcoming the polymer electrolyte membrane fuel cell (PEMFC) performance, durability & cost barriers. This contract focused on the development of advanced ion exchange membranes & electrocatalysts for PEMFCs that will enable operation under ever more demanding automotive operating conditions & the use high volume compatible processes for their manufacture. Higher performing & more durable electrocatalysts must be developed for PEMFCs to meet the power density & lifetime hours required for FC vehicles. At the same time the amount of expensive Pt catalyst must be reduced to lower the MEA costs. While these two properties are met, the catalyst must be made resistant to multiple degradation mechanisms to reach necessary operating lifetimes. In this report, we present the work focused on the development of a completely new approach to PEMFC electrocatalyts, called nanostructured thin film (NSTF) catalysts. The carbon black supports are eliminated with this new approach which eliminates the carbon corrosion issue. The thin film nature of the catalyst significantly improves its robustness against dissolution & grain growth, preserving the surface area. Also, the activity of the NSTF for oxygen reduction is improved by over 500% compared to dispersed Pt catalyts. Finally, the process for fabricating the NSTF catalysts is consistent with high volume roll-good manufacturing & extremely flexible towards the introduction of new catalyst compositions & structures. This report documents the work done to develop new multi-element NSTF catalysts with properties that exceed pure Pt, that are optimized for use with the membranes discussed below, & advance the state-of-the-art towards meeting the DOE 2010 targets for PEMFC electrocatalysts. The work completed advances the understanding of the NSTF catalyst technology, identifies new NSTF-ternary catalyst materials for higher performance, documents enhanced durability under multiple types of accelerated tests by factors of 10x to 50x over conventional catalysts, & demonstrates their performance & durability in large area MEA FC stack tests. The PEMFC ion exchange membrane is the other key functioning FC component on which work was completed. While improvements have been made to standard PFSA type membranes, they still require humidification to achieve adequate proton conductivity & so their use at elevated temperatures & drier operating conditions is limited. Membranes with increased durability & conductivity under hotter, drier conditions allow the use of FC's in many applications, particularly automotive. Towards this goal, 2 approaches were pursued in the work reported here. The first part was designed for immediate application at drier conditions & operating temperatures between 85C and 120C, focused on the development of a membrane based on a low equivalent weight (EW), perfluorinated sulfonic acid (PFSA) ionomer for good ionic conductivity at low humidification, & the use of stabilizing additives for improved oxidative stability. The ionomer used was developed at 3M & has a shorter acid containing side-chain than the Nafion™ ionomer. This ionomer also has a higher T? & higher modulus than that of a Nafion™ membrane of the same EW, allowing lower EW ionomers to be prepared with very good mechanical properties. In addition, more than 50 stabilizing additives were evaluated in ex-situ, Fenton’s tests & more than 10 of these were incorporated into membranes & evaluated in accelerated FC tests. This work led to thin (25-30 micron) cast membranes with substantially improved conductivity & durability under simulated automotive conditions, compared to membranes currently available. The 2nd body of membrane work was focused on developing & characterizing 3 approaches for making new PEM's for operation under hot (>120C) & dry (dew point <80C) FC conditions: inorganic materials with enhanced proton conductivity, polymer matrices swollen with lo

  5. Site Environmental Report for Calendar Year 2003 DOE Operations at The Boeing Company, Rocketdyne Propulsion & Power

    SciTech Connect (OSTI)

    Liu, Ning; Rutherford, Phil; Samuels, Sandy; Lee, Majelle

    2004-09-30T23:59:59.000Z

    This Annual Site Environmental Report (ASER) for 2003 describes the environmental conditions related to work performed for the Department of Energy (DOE) at Area IV of Boeing Rocketdyne’s Santa Susana Field Laboratory (SSFL). In the past, the Energy Technology Engineering Center (ETEC), a government-owned, company-operated test facility, was located in Area IV. The operations at ETEC included development, fabrication, and disassembly of nuclear reactors, reactor fuel, and other radioactive materials. Other activities at ETEC involved the operation of large-scale liquid metal facilities that were used for testing liquid metal fast breeder components. All nuclear work was terminated in 1988; all subsequent radiological work has been directed toward decontamination and decommissioning (D&D) of the former nuclear facilities and their associated sites. Closure of the liquid metal test facilities began in 1996. Results of the radiological monitoring program for the calendar year 2003 continue to indicate that there are no significant releases of radioactive material from Area IV of SSFL. All potential exposure pathways are sampled and/or monitored, including air, soil, surface water, groundwater, direct radiation, transfer of property (land, structures, waste), and recycling.

  6. AN ACCELERATED JITTER TOLERANCE TEST TECHNIQUE ON ATE FOR 1.5GB/S AND 3GB/S SERIAL-ATA

    E-Print Network [OSTI]

    Zilic, Zeljko

    AN ACCELERATED JITTER TOLERANCE TEST TECHNIQUE ON ATE FOR 1.5GB/S AND 3GB/S SERIAL-ATA Y. Fan', Y ABSTRACT In our previous publication [1], we demonstrated the ability to generate the proper mix of jitter on ATE to enable the jitter tolerance test for 1.5/3Gbps SATA applications. Obviously

  7. Environmental impact report addendum for the continued operation of Lawrence Livermore National Laboratory

    SciTech Connect (OSTI)

    Weston, R. F. [Roy F. Weston, Inc. (United States)

    1996-10-01T23:59:59.000Z

    An environmental impact statement/environmental impact report (ES/EIR) for the continued operation and management of Lawrence Livermore National Laboratory (LLNL) was prepared jointly by the U.S. Department of Energy (DOE) and the University of California (UC). The scope of the document included near-term (within 5-10 years) proposed projects. The UC Board of Regents, as state lead agency under the California Environmental Quality Act (CEQA), certified and adopted the EIR by issuing a Notice of Determination on November 20, 1992. The DOE, as the lead federal agency under the National Environmental Policy Act (NEPA), adopted a Record of Decision for the ES on January 27, 1993 (58 Federal Register [FR] 6268). The DOE proposed action was to continue operation of the facility, including near-term proposed projects. The specific project evaluated by UC was extension of the contract between UC and DOE for UC`s continued operation and management of LLNL (both sites) from October 1, 1992, through September 30, 1997. The 1992 ES/EIR analyzed impacts through the year 2002. The 1992 ES/EIR comprehensively evaluated the potential environmental impacts of operation and management of LLNL within the near-term future. Activities evaluated included programmatic enhancements and modifications of facilities and programs at the LLNL Livermore site and at LLNL`s Experimental Test Site (Site 300) in support of research and development missions 2048 established for LLNL by Congress and the President. The evaluation also considered the impacts of infrastructure and building maintenance, minor modifications to buildings, general landscaping, road maintenance, and similar routine support activities.

  8. Data validation report for the 100-HR-3 Operable Unit first quarter 1994 groundwater sampling data

    SciTech Connect (OSTI)

    Biggerstaff, R.L.

    1994-06-24T23:59:59.000Z

    Westinghouse-Hanford has requested that a minimum of 20% of the total number of Sample Delivery Groups be validated for the 100-HR-3 Operable Unit First Quarter 1994 Groundwater Sampling Investigation. Therefore, the data from the chemical analysis of twenty-four samples from this sampling event and their related quality assurance samples were reviewed and validated to verify that reported sample results were of sufficient quality to support decisions regarding remedial actions performed at this site. The samples were analyzed by Thermo-Analytic Laboratories (TMA) and Roy F. Weston Laboratories (WESTON) using US Environmental Protection Agency (EPA) CLP protocols. Sample analyses included: inorganics; and general chemical parameters. Forty-two samples were validated for radiochemical parameters by TMA and Teledyne.

  9. LDRD final report : a lightweight operating system for multi-core capability class supercomputers.

    SciTech Connect (OSTI)

    Kelly, Suzanne Marie; Hudson, Trammell B. (OS Research); Ferreira, Kurt Brian; Bridges, Patrick G. (University of New Mexico); Pedretti, Kevin Thomas Tauke; Levenhagen, Michael J.; Brightwell, Ronald Brian

    2010-09-01T23:59:59.000Z

    The two primary objectives of this LDRD project were to create a lightweight kernel (LWK) operating system(OS) designed to take maximum advantage of multi-core processors, and to leverage the virtualization capabilities in modern multi-core processors to create a more flexible and adaptable LWK environment. The most significant technical accomplishments of this project were the development of the Kitten lightweight kernel, the co-development of the SMARTMAP intra-node memory mapping technique, and the development and demonstration of a scalable virtualization environment for HPC. Each of these topics is presented in this report by the inclusion of a published or submitted research paper. The results of this project are being leveraged by several ongoing and new research projects.

  10. Indoor-air-quality management for operations and maintenance personnel. Final report

    SciTech Connect (OSTI)

    Sliwinski, B.J.; Kermath, D.; Kemme, M.R.; Imel, M.R.

    1991-09-01T23:59:59.000Z

    There is a growing body of information related to facility indoor air quality (IAQ) and its affect on the health and productivity of building occupants. Indoor air pollution can increase employee absenteeism and reduce productivity. Poor IAQ may be a result of poor building or ventilation design, improper maintenance, or inappropriate energy conservation strategies. To help ensure the health, welfare, and productivity of Army personnel and the performance of Army facilities, installation operations and maintenance (O and M) personnel need access to relevant and useful information about IAQ issues. This report includes background information for O and M managers and staff, an installation-level IAQ management plan, and practical O and M procedures for correcting the problems that most commonly lead to IAQ-related complaints.

  11. Preliminary definition of the DOE/OCRWM transportation operating system: Final report

    SciTech Connect (OSTI)

    Rawl, R.R.; Kline, S.C.

    1988-01-01T23:59:59.000Z

    This paper is based on the report ''Preliminary Definition of the Transportation Operations System'' and presents a summary of the preliminary definition of transportation operations activities for the cask shipment cycle, commencing with the dispatch of an empty cask, to loading and unloading of cask contents, and preparation of the empty cask for redispatch. It first presents a high-level description of the transportation cycle and then further describes each of the major activities in greater detail. For simplicity of presentation, the highway mode of transport is most often used to describe activities. The reader should keep in mind that the use of other modes will slightly alter the activities and possibly the sequences. Major activities and functions of the system are organized into a first cut of how they could be allocated to specific facilities. The reader should keep in mind that the assignment of functions and the aggregation of these into specific facilities are tasks which have yet to be performed. This paper simply presents a first look at possible groupings of the functions on a facility basis. 12 figs.

  12. Operational Impacts of Wind Energy Resources in the Bonneville Power Administration Control Area - Phase I Report

    SciTech Connect (OSTI)

    Makarov, Yuri V.; Lu, Shuai

    2008-07-15T23:59:59.000Z

    This report presents a methodology developed to study the future impact of wind on BPA power system load following and regulation requirements. The methodology uses historical data and stochastic processes to simulate the load balancing processes in the BPA power system, by mimicking the actual power system operations. Therefore, the results are close to reality, yet the study based on this methodology is convenient to conduct. Compared with the proposed methodology, existing methodologies for doing similar analysis include dispatch model simulation and standard deviation evaluation on load and wind data. Dispatch model simulation is constrained by the design of the dispatch program, and standard deviation evaluation is artificial in separating the load following and regulation requirements, both of which usually do not reflect actual operational practice. The methodology used in this study provides not only capacity requirement information, it also analyzes the ramp rate requirements for system load following and regulation processes. The ramp rate data can be used to evaluate generator response/maneuverability requirements, which is another necessary capability of the generation fleet for the smooth integration of wind energy. The study results are presented in an innovative way such that the increased generation capacity or ramp requirements are compared for two different years, across 24 hours a day. Therefore, the impact of different levels of wind energy on generation requirements at different times can be easily visualized.

  13. Duck Valley Reservoirs Fish Stocking and Operation and Maintenance, 2006-2007 Annual Progress Report.

    SciTech Connect (OSTI)

    Sellman, Jake; Dykstra, Tim [Shoshone-Paiute Tribes

    2009-05-11T23:59:59.000Z

    The Duck Valley Reservoirs Fish Stocking and Operations and Maintenance (DV Fisheries) project is an ongoing resident fish program that serves to partially mitigate the loss of anadromous fish that resulted from downstream construction of the hydropower system. The project's goals are to enhance subsistence fishing and educational opportunities for Tribal members of the Shoshone-Paiute Tribes and provide resident fishing opportunities for non-Tribal members. In addition to stocking rainbow trout (Oncorhynchus mykiss) in Mountain View, Lake Billy Shaw, and Sheep Creek Reservoirs, the program is also designed to maintain healthy aquatic conditions for fish growth and survival, to provide superior facilities with wilderness qualities to attract non-Tribal angler use, and to offer clear, consistent communication with the Tribal community about this project as well as outreach and education within the region and the local community. Tasks for this performance period are divided into operations and maintenance plus monitoring and evaluation. Operation and maintenance of the three reservoirs include fences, roads, dams and all reservoir structures, feeder canals, water troughs and stock ponds, educational signs, vehicles and equipment, and outhouses. Monitoring and evaluation activities included creel, gillnet, wildlife, and bird surveys, water quality and reservoir structures monitoring, native vegetation planting, photo point documentation, control of encroaching exotic vegetation, and community outreach and education. The three reservoirs are monitored in terms of water quality and fishery success. Sheep Creek Reservoir was very unproductive this year as a fishery. Fish morphometric and water quality data indicate that the turbidity is severely impacting trout survival. Lake Billy Shaw was very productive as a fishery and received good ratings from anglers. Mountain View was also productive and anglers reported a high number of quality sized fish. Water quality (specifically dissolved oxygen and temperature) is the main limiting factor in our fisheries.

  14. Data validation report for the 100-FR-3 Operable Unit, third round groundwater samples

    SciTech Connect (OSTI)

    Ayres, J.M.

    1994-03-31T23:59:59.000Z

    Westinghouse-Hanford has requested that a minimum of 20% of the total number of Sample Delivery Groups be validated for the 100-FR-3 operable Unit Third Round Groundwater sampling investigation. Therefore, the data from the chemical analysis of 51 samples from this sampling event and their related quality assurance samples were reviewed and validated to verify that reported sample results were of sufficient quality to support decisions regarding remedial actions performed at this site. The report is broken down into sections for each chemical analysis and radiochemical analysis type. Each section addresses the data package completeness, holding time adherence, instrument calibration and tuning acceptability, blank results, accuracy, precision, system performance, as well as the compound identification and quantitation. In addition, each section has an overall assessment and summary for the data packages reviewed for the particular chemical/radiochemical analyses. Detailed backup information is provided to the reader by SDG No. and sample number. For each data package, a matrix of chemical analyses per sample number is presented, as well as data qualification summaries.

  15. Detailed design report for an operational phase panel-closure system

    SciTech Connect (OSTI)

    NONE

    1996-01-11T23:59:59.000Z

    Under contract to Westinghouse Electric Corporation (Westinghouse), Waste Isolation Division (WID), IT Corporation has prepared a detailed design of a panel-closure system for the Waste Isolation Pilot Plant (WIPP). Preparation of this detailed design of an operational-phase closure system is required to support a Resource Conservation and Recovery Act (RCRA) Part B permit application and a non-migration variance petition. This report describes the detailed design for a panel-closure system specific to the WIPP site. The recommended panel-closure system will adequately isolate the waste-emplacement panels for at least 35 years. This report provides detailed design and material engineering specifications for the construction, emplacement, and interface-grouting associated with a panel-closure system at the WIPP repository, which would ensure that an effective panel-closure system is in place for at least 35 years. The panel-closure system provides assurance that the limit for the migration of volatile organic compounds (VOC) will be met at the point of compliance, the WIPP site boundary. This assurance is obtained through the inherent flexibility of the panel-closure system.

  16. Analysis of radiation doses from operation of postulated commercial spent fuel transportation systems: Main report

    SciTech Connect (OSTI)

    Schneider, K.J.; Hostick, C.J.; Ross, W.A.; Peterson, R.W.; Smith, R.I.; Stiles, D.L.; Daling, P.M.; Weakley, S.A.; Grinde, R.B.; Young, J.R.

    1987-11-01T23:59:59.000Z

    This report contains a system study of estimated radiation doses to the public and workers resulting from the transport of spent fuel from commercial nuclear power reactors to a geologic repository. The report contains a detailed breakdown of activities and a description of time/distance/dose-rate estimates for each activity within the system. Collective doses are estimated for each of the major activities at the reactor site, in transit, and at the repository receiving facility. Annual individual doses to the maximally exposed individuals or groups of individuals are also estimated. A total of 17 alternatives and subalternatives to the postulated reference transportation system are identified, conceptualized, and their dose-reduction potentials and costs estimated. Resulting ratios of ..delta..cost/..delta..collective system dose for each alternative relative to the postulated reference transportation system are given. Most of the alternatives evaluated are estimated to provide both cost and dose reductions. Major reductions in transportation system dose and cost are estimated to result from using higher-capacity rail and truck casks, and particularly when replacing legalweight truck casks with ''advanced design'' overweight truck casks. The greatest annual dose reduction to the highest exposed individual workers (i.e., at the repository) is estimated to be achieved by using remote handling equipment for the cask handling operations at the repository. Additional shielding is also effective in reducing doses to both radiation workers at the reactor and repository and to transport workers. 69 refs., 36 figs., 156 tabs.

  17. Office for Analysis and Evaluation of Operational Data 1996 annual report. Volume 10, Number 3: Technical training

    SciTech Connect (OSTI)

    NONE

    1997-12-01T23:59:59.000Z

    This annual report of the US Nuclear Regulatory Commission`s Office for Analysis and Evaluation of Operational Data (AEOD) describes activities conducted during 1996. The report is published in three parts. NUREG-1272, Vol. 10, No. 1, covers power reactors and presents an overview of the operating experience of the nuclear power industry from the NRC perspective, including comments about trends of some key performance measures. The report also includes the principal findings and issues identified in AEOD studies over the past year and summarizes information from such sources as licensee event reports and reports to the NRC`s Operations Center. NUREG-1272, Vol. 10, No. 2, covers nuclear materials and presents a review of the events and concerns during 1996 associated with the use of licensed material in nonreactor applications, such as personnel overexposures and medical misadministrations. Both reports also contain a discussion of the Incident Investigation Team program and summarize both the Incident Investigation Team and Augmented Inspection Team reports. Each volume contains a list of the AEOD reports issued from CY 1980 through 1996. NUREG-1272, Vol. 10, No. 3, covers technical training and presents the activities of the Technical Training Center in support of the NRC`s mission in 1996.

  18. Office for Analysis and Evaluation of Operational Data 1994-FY 95 annual report. Volume 9, Number 2

    SciTech Connect (OSTI)

    NONE

    1996-09-01T23:59:59.000Z

    This annual report of the US Nuclear Regulatory Commission`s Office for Analysis and Evaluation of Operational Data (AEOD) describes activities conducted during CY 1994 and FY 1995. The report is published in three parts. NUREG-1272, Vol. 9, No. 1, covers power reactors and presents an overview of the operating experience of the nuclear power industry from the NRC perspective, including comments about the trends of some key performance measures. The report also includes the principal findings and issues identified in AEOD studies over the past year and summarizes information from such sources as licensee event reports, diagnostic evaluations, and reports to the NRC`s Operations Center. NUREG-1272, Vol. 9, No. 2, covers nuclear materials and presents a review of the events and concerns associated with the use of licensed material in nonreactor applications, such as personnel overexposures and medical misadministrations. Both reports also contain a discussion of the Incident Investigation Team program and summarize both the Incident Investigation Team and Augmented Inspection Team reports. Each volume contains a list of the AEOD reports issued from 1980 through FY 1995. NUREG-1272, Vol. 9, No. 3, covers technical training and presents the activities of the Technical Training Center in support of the NRC`s mission.

  19. Office for Analysis and Evaluation of Operational Data 1992 annual report: Power reactors. Volume 7, No. 1

    SciTech Connect (OSTI)

    none,

    1993-07-01T23:59:59.000Z

    The annual report of the US Nuclear Regulatory Commission`s Office for Analysis and Evaluation of Operational Data (AEOD) is devoted to the activities performed during 1992. The report is published in two separate parts. NUREG-1272, Vol. 7, No. 1, covers power reactors and presents an overview of the operating experience of the nuclear power industry from the NRC perspective, including comments about the trends of some key performance, measures. The report also includes the principal findings and issues identified in AEOD studies over the past year, and summarizes information from such sources as licensee event report% diagnostic evaluations, and reports to the NRC`s Operations Center. The reports contain a discussion of the Incident Investigation Team program and summarize the Incident Investigation Team and Augmented Inspection Team reports for that group of licensees. NUREG-1272, Vol. 7, No. 2, covers nonreactors and presents a review of the events and concerns during 1992 associated with the use of licensed material in nonreactor applications, such as personnel overexposures and medical misadministrations. Each volume contains a list of the AEOD reports issued for 1984--1992.

  20. FEASIBILITY STUDY REPORT FOR THE 200-ZP-1 GROUNDWATER OPERABLE UNIT

    SciTech Connect (OSTI)

    BYRNES ME

    2008-07-18T23:59:59.000Z

    The Hanford Site, managed by the U.S. Department of Energy (DOE), encompasses approximately 1,517 km{sup 2} (586 mi{sup 2}) in the Columbia Basin of south-central Washington State. In 1989, the U.S. Environmental Protection Agency (EPA) placed the 100, 200, 300, and 1100 Areas of the Hanford Site on the 40 Code of Federal Regulations (CFR) 300, 'National Oil and Hazardous Substances Pollution Contingency Plan' National Contingency Plan [NCPD], Appendix B, 'National Priorities List' (NPL), pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). The 200 Areas NPL sites consist of the 200 West and 200 East Areas (Figure 1-1). The 200 Areas contain waste management facilities, inactive irradiated fuel reprocessing facilities, and the 200 North Area (formerly used for interim storage and staging of irradiated fuel). Several waste sites in the 600 Area, located near the 200 Areas, also are included in the 200 Areas NPL site. The 200 Areas NPL site is in a region referred to as the 'Central Plateau' and consists of approximately 700 waste sites, excluding sites assigned to the tank farm waste management areas (WMAs). The 200-ZP-1 Groundwater Operable Unit (OU) consists of the groundwater located under the northern portion of the 200 West Area. Waste sources that contributed to the 200-ZP-1 OU included cribs and trenches that received liquid and/or solid waste in the past from the Z Plant and T Plant aggregate areas, WMA-T, WMA-TX/TY, and the State-Approved Land Disposal Site (SALDS). This feasibility study (FS) for the 200-ZP-1 Groundwater OU was prepared in accordance with the requirements of CERCLA decision documents. These decision documents are part of the Administrative Record for the selection of remedial actions for each waste site and present the selected remedial actions that are chosen in accordance with CERCLA, as amended by the Superfund Amendments and Reauthorization Act of 1986, and to the extent practicable, the NCP. This FS conforms to the conditions set forth in the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) (Ecology et al. 2003) and amendments, signed by the Washington State Department of Ecology (Ecology), EPA, and DOE Richland Operations Office (RL). This also includes Tri-Party Agreement Milestone M-015-00C for completing all 200 Area non-tank farm OU pre-Record of Decision (ROD) documents on or before December 31, 2011. This FS supports the final remedy selection for the 200-ZP-1 OU, as described in the Remedial Investigation/Feasibility Study Work Plan for the 200-ZP-1 Groundwater Operable Unit (referred to as the 200-ZP-1 RI/FS work plan) (DOE/RL-2003-55), as agreed upon by RL and EPA. Tri-Party Agreement Milestone M-015-48B required Draft A of the 200-ZP-1 OU FS and proposed plan to be transmitted to EPA by September 30, 2007. As agreed to with EPA in the 200 Area Unit Managers Meeting Groundwater Operable Unit Status (FH-0503130), the baseline risk assessment (BRA) was delayed from inclusion in the remedial investigation (RI) report and is completed and documented in this FS. The Remedial Investigation Report for 200-ZP-1 Groundwater Operable Unit (referred to as the 200-ZP-1 RI report) (DOE/RL-2006-24) included an evaluation of human health and ecological risks and hazards. The RI report identified the radiological and chemical contaminants of potential concern (COPCs) that represent the primary risks to human health and the environment. The complete risk assessment in this FS incorporates additional analytical data from the unconfined aquifer that were obtained during or after preparation of the RI report, particularly for carbon tetrachloride and technetium-99. This FS also includes the initial results from an ongoing study of technetium-99 contamination near WMA-T, the sampling of new wells near the 216-W-LC laundry waste crib and T Plant, updated Hanford vadose zone fate and transport modeling, and groundwater particle-tracking analysis. The purpose of this FS is to develop and evaluate alternatives for remediation of

  1. US Department of Energy Nevada Operations Office annual site environmental report, 1992. Volume 1

    SciTech Connect (OSTI)

    Black, S.C.; Latham, A.R.; Townsend, Y.E. [eds.

    1993-09-01T23:59:59.000Z

    This report contains the environmental monitoring and assessment results for the Nevada Test Site for 1992. Monitoring and surveillance on and around the NTS by DOE contractors and Site user organizations during 1992 indicated that underground nuclear testing operations were conducted in compliance with regulations, i.e., the dose the maximally exposed offsite individual could have received was less than 0.15 percent of the guideline for air exposure. All 1992 nuclear events took place during the first three quarters of the calendar year prior to the Congressional testing moratorium. All discharges of radioactive liquids remained onsite in containment ponds, and there was no indication of potential migration of radioactivity to the offsite area through groundwater. Surveillance around the NTS indicated that airborne radioactivity from test operations was not detectable offsite, and no measurable net exposure to members of the offsite population was detected through the offsite dosimetry program. Using the CAP88-PC model and NTS radionuclide emissions data, the calculated maximum effective dose equivalent offsite would have been 0.012 mrem. Any person receiving this dose was also exposed to 78 mrem from natural background radiation. There were no nonradiological releases to the offsite area. Hazardous wastes were shipped to EPA-approved disposal facilities. Compliance with the various regulations stemming from the National Environmental Policy Act is being achieved and, where mandated, permits for air and water discharges and waste management have been obtained from the appropriate agencies. Non-NTS support facilities complied with the requirements of air quality permits and state or local wastewater discharge and hazardous waste permits.

  2. Multi-Collector Inductively Coupled Plasma Mass Spectrometer – Operational Performance Report

    SciTech Connect (OSTI)

    Matthew Watrous; Anthony Appelhans; Robert Hague; John Olson; Tracy Houghton

    2013-06-01T23:59:59.000Z

    The INL made an assessment of the commercially available inductively coupled plasma mass spectrometers (ICPMS) for actinide analysis; emphasizing low detection limits for plutonium. INL scientists subsequently determined if plutonium was present on a swipe, at a 10 million atom decision level. This report describes the evaluation of ICPMS instruments and the operational testing of a new process for the dissolution, separation and analysis via ICPMS of swipes for plutonium and uranium. The swipe dissolution, plutonium and uranium isolation, separation and purification are wet chemistry methods following established procedures. The ICPMS is a commercially available multi-collector magnetic sector mass spectrometer that utilizes five ion counting detectors operating simultaneously. The instrument includes a sample introduction system allowing for sample volumes of < 1 mL to be reproducibly injected into the instrument with minimal waste of the sample solution, while maximizing the useable signal. The performance of the instrument was measured using SRM 996 (244Pu spike) at concentrations of 12 parts per quadrillion (ppq, fg/mL) and with SRM 4350B Columbia River Sediment samples spiked onto swipes at the 10 million atom level. The measured limit of detection (LOD, defined as 3s) for 239Pu is 310,000 atoms based upon the instrument blank data. The limit of quantification (LOQ defined as 10 s) for 239Pu is 105,000 atoms. The measured limit of detection for 239Pu from the SRM 4350B spiked onto a swipe was 2.7 million atoms with the limit of quantification being 9.0 million atoms.

  3. REPORT on the TRUCK BRAKE LINING WORKSHOP and FLEET OPERATORS' SURVEY

    SciTech Connect (OSTI)

    Blau, P.J.

    2003-02-03T23:59:59.000Z

    The report summarizes what transpired during brake linings-related workshop held at the Fall 2003 meeting of the Technology and Maintenance Council (TMC) in Charlotte, NC. The title of the workshop was ''Developing a Useful Friction Material Rating System''. It was organized by a team consisting of Peter Blau (Oak Ridge National Laboratory), Jim Britell (National Highway Traffic Safety Administration), and Jim Lawrence (Motor and Equipment Manufacturers Association). The workshop was held under the auspices of TMC Task Force S6 (Chassis), chaired by Joseph Stianche (Sanderson Farms, Inc.). Six invited speakers during the morning session provided varied perspectives on testing and rating aftermarket automotive and truck brake linings. They were: James R. Clark, Chief Engineer, Foundation Brakes and Wheel Equipment, Dana Corporation, Spicer Heavy Axle and Brake Division; Charles W. Greening, Jr, President, Greening Test Labs; Tim Duncan, General Manager, Link Testing Services;Dennis J. McNichol, President, Dennis NationaLease; Jim Fajerski, Business Manager, OE Sales and Applications Engineering, Federal Mogul Corporation; and Peter J. Blau, Senior Materials Development Engineer, Oak Ridge National Laboratory. The afternoon break-out sessions addressed nine questions concerning such issues as: ''Should the federal government regulate aftermarket lining quality?''; ''How many operators use RP 628, and if so, what's good or bad about it?''; and ''Would there be any value to you of a vocation-specific rating system?'' The opinions of each discussion group, consisting of 7-9 participants, were reported and consolidated in summary findings on each question. Some questions produced a greater degree of agreement than others. In general, the industry seems eager for more information that would allow those who are responsible for maintaining truck brakes to make better, more informed choices on aftermarket linings. A written fleet operator survey was also conducted during the TMC meeting. Twenty-one responses were received, spanning fleet sizes between 12 and 170,000 vehicles. Responses are summarized in a series of tables separated into responses from small (100 or fewer powered vehicles), medium (101-1000 vehicles), and large fleets (>1000 vehicles). The vast majority of fleets do their own brake maintenance, relying primarily on experience and lining manufactures to select aftermarket linings. At least half of the responders are familiar to some extent with TMC Recommended Practice 628 on brake linings, but most do not use this source of test data as the sole criterion to select linings. Significant shortfalls in the applicability of TMC RP 628 to certain types of brake systems were noted.

  4. NSTX Weekly Report (July 23, 2010) FY 2010 NSTX plasma operations

    E-Print Network [OSTI]

    Princeton Plasma Physics Laboratory

    insulation, and the integrated system testing for restoring TF/OH operations. Access to the NSTX test cell building. Research Operations (M. Bell) Boundary Physics Operations (H. Kugel) Alignments and spatial and six old optical fibers viewing the LLD. (V. Soukhanovskii) Testing of a new automated filling

  5. Fiscal Year 2009 Annual Report for Operable Unit 3-14, Tank Farm Soil and INTEC Groundwater

    SciTech Connect (OSTI)

    Forsythe, Howard S.

    2010-04-10T23:59:59.000Z

    This annual report summarizes maintenance, monitoring, and inspection activities performed to implement the selected remedy for Waste Area Group 3, Operable Unit 3-14, Tank Farm soil and groundwater at the Idaho Nuclear Technology and Engineering Center located within the Idaho National Laboratory Site. Results from monitoring perched water and groundwater at the Idaho Nuclear Technology and Engineering Center are also presented.

  6. FY 1993 progress report on the ANS thermal-hydraulic test loop operation and results

    SciTech Connect (OSTI)

    Siman-Tov, M.; Felde, D.K.; Farquharson, G. [and others

    1994-07-01T23:59:59.000Z

    The Thermal-Hydraulic Test Loop (THTL) is an experimental facility constructed to support the development of the Advanced Neutron Source Reactor (ANSR) at Oak Ridge National Laboratory (ORNL). Highly subcooled heavy-water coolant flows vertically upward at a very high mass flux of almost 27 MG/m{sup 2}-s. In a parallel fuel plate configuration as in the ANSR, the flow is subject to a potential excursive static-flow instability that can very rapidly lead to flow starvation and departure from nucleate boiling (DNB) in the ``hot channel``. The current correlations and experimental data bases for flow excursion (FE) and critical heat flux (CHF) seldom evaluate the specific combination of ANSR operating parameters. The THTL facility was designed and built to provide known thermal-hydraulic (T/H) conditions for a simulated full-length coolant subchannel of the ANS reactor core, thus facilitating experimental determination of FE and CHF thermal limits under expected ANSR T/H conditions. A series of FE tests with water flowing vertically upward was completed over a nominal heat flux range of 6 to 17 MW/m{sup 2}, a mass flux range of 8 to 28 Mg/m{sup 2}-s, an exit pressure range of 1.4 to 2.1 MPa, and an inlet temperature range of 40 to 50 C. FE experiments were also conducted using as ``soft`` a system as possible to secure a true FE phenomena (actual secondary burnout). True DNB experiments under similar conditions were also conducted. To the author`s knowledge, no other FE data have been reported in the literature to date that dover such a combination of conditions of high mass flux, high heat flux, and moderately high pressure.

  7. Solid Waste Operations Complex W-113, Detail Design Report (Title II). Volume 1: Title II design report

    SciTech Connect (OSTI)

    NONE

    1995-09-01T23:59:59.000Z

    The Solid Waste Retrieval Facility--Phase 1 (Project W113) will provide the infrastructure and the facility required to retrieve from Trench 04, Burial ground 4C, contact handled (CH) drums and boxes at a rate that supports all retrieved TRU waste batching, treatment, storage, and disposal plans. This includes (1) operations related equipment and facilities, viz., a weather enclosure for the trench, retrieval equipment, weighing, venting, obtaining gas samples, overpacking, NDE, NDA, shipment of waste and (2) operations support related facilities, viz., a general office building, a retrieval staff change facility, and infrastructure upgrades such as supply and routing of water, sewer, electrical power, fire protection, roads, and telecommunication. Title I design for the operations related equipment and facilities was performed by Raytheon/BNFL, and that for the operations support related facilities including infrastructure upgrade was performed by KEH. These two scopes were combined into an integrated W113 Title II scope that was performed by Raytheon/BNFL. Volume 1 provides a comprehensive narrative description of the proposed facility and systems, the basis for each of the systems design, and the engineering assessments that were performed to support the technical basis of the Title II design. The intent of the system description presented is to provide WHC an understanding of the facilities and equipment provided and the A/E`s perspective on how these systems will operate.

  8. Phase I remedial investigation report for the 300-FF-5 operable unit, Volume 1

    SciTech Connect (OSTI)

    NONE

    1994-01-01T23:59:59.000Z

    The focus of this remedial investigation (RI) is the 300-FF-5 operable unit, one of five operable units associated with the 300 Area aggregate of the U.S. Department of Energy`s (DOE`s) Hanford Site. The 300-FF-5 operable unit is a groundwater operable unit beneath the 300-FF-1, 300-FF-2, and 300-FF-3 source operable units. This operable unit was designated to include all contamination detected in the groundwater and sediments below the water table that emanates from the 300-FF-1, 300-FF-2, and 300-FF-3 operable units (DOE-RL 1990a). In November 1989, the U.S. Environmental Protection Agency (EPA) placed the 300 Area on the National Priorities List (NPL) contained within Appendix B of the National Oil and Hazardous Substance Pollution Contingency Plan (NCP, 53 FR 51391 et seq.). The EPA took this action pursuant to their authority under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA, 42 USC 9601 et seq.). The DOE Richland Operations Office (DOE-RL), the EPA and Washington Department of Ecology (Ecology) issued the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement), in May 1989 (Ecology et al. 1992, Rev. 2). This agreement, among other matters, governs all CERCLA efforts at the Hanford Site. In June 1990, a remedial investigation/feasibility study (RI/FS) workplan for the 300-FF-5 operable unit was issued pursuant to the Tri-Party Agreement.

  9. Turlock Lake Powerhouse. Turlock Irrigation District design report and operations manual

    SciTech Connect (OSTI)

    None

    1981-01-01T23:59:59.000Z

    The development of equipment selection and design is outlined and operational criteria for the hydroelectric power drop at the Turlock Lake California Powerhouse are established.

  10. Dredging Operations Technical-Support Program. A framework for assessing the need for seasonal restrictions on dredging and disposal operations. Final report

    SciTech Connect (OSTI)

    LaSalle, M.W.; Clarke, D.G.; Homziak, J.; Lunz, J.D.; Fredette, T.J.

    1991-07-01T23:59:59.000Z

    Seasonal restrictions on dredging and/or disposal operations are based upon concerns about potential dredging- or disposal-induced negative impacts to biological resources. In many cases, however, information on the degree to which either naturally occurring or dredging-induced environmental alterations directly or indirectly affect organisms is poorly quantified, in which case restrictions are based upon a reason to believe notion. This report addresses the general acceptability of seasonal restrictions through a compilation of available information on physical-chemical environmental alterations associated with dredging and disposal operations, and critical information regarding the effects of these alterations on principal biological resources. Based on this information, a method for evaluating existing or proposed seasonal restrictions on dredging and/or disposal operations is presented. This framework reflects the present understanding of effects of dredging- or disposal-induced, as well as naturally occurring, environmental alterations upon biological resources. In many cases, the magnitude of dredging- or disposal-induced alterations falls well within the range of naturally occurring phenomena and imposes little or no additional stress upon resource populations. In some cases, however, the magnitude of alterations may exceed that which occurs naturally, whereby concerns about dredging- or disposal-induced alterations are justified and should be considered when planning a project.

  11. Columbia River System Operation Review : Final Environmental Impact Statement, Main Report.

    SciTech Connect (OSTI)

    Columbia River System Operation Review (U.S.); United States. Bonneville Power Administration; United States. Army. Corps of Engineers. North Pacific Division; United States. Bureau of Reclamation. Pacific Northwest Region.

    1995-11-01T23:59:59.000Z

    The System Operation Review (SOR) Final EIS addresses four actions: (a) need to develop coordinated strategy for managing the multiple uses of the Federal Columbia River system (System Operating Strategy [SOS]); (b) need to provide interested parties other than management agencies with a long-term role in system planning (Forum); (c) need to renew or change current Canadian Entitlement Allocation Agreements (CEAA); and (d) need to renegotiate and renew the Pacific Northwest Coordination Agreement (PNCA). SOS alternatives analyzed are: (1) operation prior to Endangered Species Act listings of salmon stocks; (2) current operations (no action); (3) stable storage project operation; (4) natural river operation; (5) fixed drawdown; (6) operating strategies proposed by the U.S. Fish and Wildlife Service, National Marine Fisheries Service, State fisheries agencies, Native American tribes, and Federal operating agencies; and (7) Preferred Alternative. The seven Forum alternatives analyzed are: (1) decisionmaking by the SOR lead agencies (preferred alternative); (2) decisionmaking by SOR lead agencies and recommendations by an existing regional entity; (3) decisionmaking by SOR lead agencies and recommendations by a new regional entity; (4) decisionmaking by a Federal consultation forum; (5) decisionmaking by a new entity; (6) decisionmaking by one Federal operating agency; (7) decisionmaking by a Federal agency other than an operating agency. PNCA alternatives analyzed are: (1) no replacement contract; (2) contract to maximize regional power benefits; (3) roll over existing PNCA; (4) current PNCA with modified operating procedures (preferred alternative); (5) current PNCA with nonpower modifications. CEAA alternatives include: (1) no action (no replacement of current allocation agreements); (2) entitlement allocation: 55 percent Federal; 45 percent non-Federal; (3) entitlement allocation: 70 percent Federal, 30 percent non-Federal (preferred alternative); (4) no agreement.

  12. Annual Report of the EURATOM/CCFE Fusion Programme 2013 3 JET Operations

    E-Print Network [OSTI]

    .1 INTRODUCTION Since January 2000, CCFE has had the responsibility for the operation and safety of the JET, in line with a highly optimised planned schedule of only 50 operating days, completion of the Neutral Beam Enhancement (part of the JET EP2 series of machine upgrades) resulting in new records of Neutral Beam heating

  13. Electric and hybrid vehicle project. Quarterly report of private-sector operations, first quarter 1982

    SciTech Connect (OSTI)

    None

    1982-06-01T23:59:59.000Z

    As of January 1, 1982 sixteen private-sector site operators at 30 sites in the US were involved in electric and hybrid electric-powered vehicle demonstration programs. Data for 1981 and the first quarter of 1982 are presented on vehicle selection, miles accumulated, energy usage, maintenance requirements, reliability and operating performance for demonstration vehicles at each site. (LCL)

  14. Electric and hybrid vehicle program site operator program. Quarterly progress report, January 1995--March 1995

    SciTech Connect (OSTI)

    Kiser, D.M.; Brown, H.L.

    1995-08-01T23:59:59.000Z

    The Site Operator Program was initially established by the Department of Energy (DOE) to incorporate the electric vehicle activities dictated by the Electric and Hybrid Vehicle Research, Development and Demonstration Act of 1976. In the ensuing years, the Program has evolved in response to new legislation and interests. The Program currently includes twelve sites located in diverse geographic, metrologic, and metropolitan areas across the United States. Information is shared reciprocally with a thirteenth site, not under Program contract. The vehicles are operator-owned. The Mission Statement of the Site Operator Program includes three major activities: (1) Advancement of electric vehicle technologies; (2) Development of infrastructure elements necessary to support significant electric vehicle use; and (3) Increasing the awareness and acceptance of electric vehicles (EVs) by the public. The current participants in the Site Operator Program are shown. Table 1 indicates the EVs in each of the Site Operator fleets. Table 2 provides baseline information on several EVs currently in use by the Site Operators, or which have evolved to the point that they may be introduced in the near future. The Program is currently managed by personnel of the Electric and Hybrid Vehicle Program at the Idaho National Engineering Laboratory (INEL). The current principal management functions include: Coordination of Site Operator efforts in the areas of public awareness and infrastructure development (program-related meetings, and educational presentations).

  15. Feasibility study report for the 200-BP-1 operable unit. Revision 1

    SciTech Connect (OSTI)

    Not Available

    1994-01-01T23:59:59.000Z

    This feasibility study (FS) examines a range of alternatives and provides recommendations for selecting a preferred altemative for remediating contamination at the 200-BP-1 operable unit. The 200-BP-1 operable unit is located in the center of the Hanford Site along the northern boundary of the 200 East Area. The 241-BY Tank Farm is located immediately to the south of the operable unit. 200-BP-1 is a source operable unit with contaminated soils associated primarily with nine inactive cribs (known as the 216-B cribs). These cribs were used for disposal of low-level radioactive liquid waste from U Plant uranium recovery operations, and waste storage tank condensate from the adjacent 241-BY Tank Farm. The cribs used for disposal of U Plant waste were in operation from 1955--1965, and the cribs used for disposal of tank condensate were in operation from 1965-1975. In addition to the cribs, four unplanned releases of radioactive materials have occurred within the operable unit. Contaminated surface soils associated with the unplanned releases have been consolidated over the cribs and covered with clean soil to reduce contaminant migration and exposure. Discharge of wastes to the cribs has resulted in soil and groundwater contamination. The groundwater is being addressed as part of the 200 East Aggregate Area groundwater operable unit. Contaminated soils at the site can be categorized by the types of contaminants, their distribution in the soil column, and the risk posed by the various potential exposure pathways. Below the clean soil cover, the near surface soils contain low-:levels of contamination with cesium-137, radium-226, strontium-90, thorium-228 and uranium. The lifetime incremental cancer risk associated with these soils if they were exposed at the surface is 9 {times} 10{sup 5}.

  16. Hatchery Evaluation Report / Lyons Ferry Hatchery - Fall Chinook : An Independent Audit Based on Integrated Hatchery Operations Teams (IHOT) Performance Measures : Final Report.

    SciTech Connect (OSTI)

    Watson, Montgomery

    1996-05-01T23:59:59.000Z

    This report presents the findings of the independent audit of the Lyons Ferry Hatchery (Fall Chinook). The audit is being conducted as a requirement of the Northwest Power Planning Council (NPPC) ``Strategy for Salmon`` and the Columbia River Basin Fish and Wildlife Program. Under the audit, the hatcheries are evaluated against policies and related performance measures developed by the Integrated Hatchery Operations Team (IHOT). IHOT is a multi-agency group established by the NPPC to direct the development of new basinwide standards for managing and operating fish hatcheries. The audit was conducted in April 1996 as part of a two-year effort that will include 67 hatcheries and satellite facilities located on the Columbia and Snake River system in Idaho, Oregon, and Washington. The hatchery operating agencies include the US Fish and Wildlife Service, Idaho Department of Fish and Game, Oregon Department of Fish and Wildlife, and Washington Department of Fish and Wildlife.

  17. Evaluation of enhanced recovery operations in Smackover fields of southwest Alabama. Draft topical report on Subtasks 5 and 6

    SciTech Connect (OSTI)

    Hall, D.R.

    1992-06-01T23:59:59.000Z

    This report contains detailed geologic and engineering information on enhanced-recovery techniques used in unitized Smackover fields in Alabama. The report also makes recommendations on the applicability of these enhanced-recovery techniques to fields that are not now undergoing enhanced recovery. Eleven Smackover fields in Alabama have been unitized. Three fields were unitized specifically to allow the drilling of a strategically placed well to recover uncontacted oil. Two fields in Alabama are undergoing waterflood projects. Five fields are undergoing gas-injection programs to increase the ultimate recovery of hydrocarbons. Silas and Choctaw Ridge fields were unitized but no enhanced-recovery operations have been implemented.

  18. Mitigation for the Construction and Operation of Libby Dam, 2000 Annual Report.

    SciTech Connect (OSTI)

    Hoffman, Greg; Marotz, Brian L.; Dunnigan, James (Montana Department of Fish, Wildlife and Parks, Libby, MT)

    2002-09-01T23:59:59.000Z

    ''Mitigation for the Construction and Operation of Libby Dam'' is part of the Northwest Power Planning Council's resident fish and wildlife program. The program was mandated by the Northwest Planning Act of 1980, and is responsible for mitigating for damages to fish and wildlife caused by hydroelectric development in the Columbia River Basin. The objective of Phase I of the project (1983 through 1987) was to maintain or enhance the Libby Reservoir fishery by quantifying seasonal water levels and developing ecologically sound operational guidelines. The objective of Phase II of the project (1988 through 1996) was to determine the biological effects of reservoir operations combined with biotic changes associated with an aging reservoir. The objectives of Phase III of the project (1996 through present) are to implement habitat enhancement measures to mitigate for dam effects, to provide data for implementation of operational strategies that benefit resident fish, monitor reservoir and river conditions, and monitor mitigation projects for effectiveness.

  19. 2014 Annual Workforce Analysis and Staffing Plan Report- Richland Operations Office

    Broader source: Energy.gov [DOE]

    Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

  20. 2011 Annual Workforce Analysis and Staffing Plan Report- Idaho Operations Office

    Broader source: Energy.gov [DOE]

    Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

  1. 2010 Annual Workforce Analysis and Staffing Plan Report- Idaho Operations Office

    Broader source: Energy.gov [DOE]

    Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

  2. 2012 Annual Workforce Analysis and Staffing Plan Report- Idaho Operations Office

    Broader source: Energy.gov [DOE]

    Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

  3. 2010 Annual Workforce Analysis and Staffing Plan Report- Richland Operations Office

    Broader source: Energy.gov [DOE]

    Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

  4. Nuclear Plant Feedwater Heater Handbook. Volume 3. Operation and maintenance guidelines. Final report

    SciTech Connect (OSTI)

    Bell, R.J.; Hardy, C.D. Jr.

    1985-06-01T23:59:59.000Z

    This document is the third part of a three-volume handbook covering closed feedwater heaters for nuclear electric power generating plants. This third volume covers the operation and maintenance of closed feedwater heaters. 11 refs., 23 figs., 5 tabs.

  5. Planning and Reporting for Operations and Maintenance in Federal Energy Savings Performance Contracts

    E-Print Network [OSTI]

    Kumar, Satish; Webster, Lia

    2005-01-01T23:59:59.000Z

    the success of an ESPC. Either the ESCO or the government (as part of an ESPC. However, the ESCO is ultimatelyESCO will both operate and perform all maintenance activities on equipment installed in an ESPC

  6. NSTX Weekly Report (Jan. 29, 2009) FY 2010 NSTX plasma operations

    E-Print Network [OSTI]

    Princeton Plasma Physics Laboratory

    of flat line density via ELM triggering and gas fueling optimization. (R. Maingi) · The article vessel bake. Access to the NSTX test cell will be restricted during the 1st shift this coming week during MPTS diagnostic operations. R

  7. 2014 Annual Workforce Analysis and Staffing Plan Report- Savannah River Operations Office

    Broader source: Energy.gov [DOE]

    Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

  8. 2013 Annual Workforce Analysis and Staffing Plan Report- Savannah River Operations Office

    Broader source: Energy.gov [DOE]

    Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

  9. 2012 Annual Workforce Analysis and Staffing Plan Report- Savannah River Operations Office

    Broader source: Energy.gov [DOE]

    Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

  10. 2010 Annual Workforce Analysis and Staffing Plan Report- Savannah River Operations Office

    Broader source: Energy.gov [DOE]

    Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

  11. 2011 Annual Workforce Analysis and Staffing Plan Report- Savannah River Operations Office

    Broader source: Energy.gov [DOE]

    Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

  12. 2014 Annual Workforce Analysis and Staffing Plan Report- Idaho Operations Office

    Broader source: Energy.gov [DOE]

    Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

  13. 2013 Annual Workforce Analysis and Staffing Plan Report- Idaho Operations Office

    Broader source: Energy.gov [DOE]

    Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

  14. 2013 Annual Workforce Analysis and Staffing Plan Report- Richland Operations Office

    Broader source: Energy.gov [DOE]

    Managers perform an annual workforce analysis of their organization and develop staffing plans that identify technical capabilities and positions they need to ensure safe operation of defense nuclear facilities.

  15. Collaborative Operations for Personnel Recovery Final Report on DARPA/AFRL 

    E-Print Network [OSTI]

    Tate, Austin; Dalton, J; Stader, J; Wickler, G; Hansberger, J

    2007-08-31T23:59:59.000Z

    The Collaborative Operations for Personnel Recovery (Co-OPR) project sought to provide collaborative task support for a Search and Rescue coordination center. The project aimed to create a prototype “Personnel Recovery ...

  16. Kalispel Resident Fish Project- Kalispel Tribal Hatchery Operations and Maintenance, 1997 Annual Report.

    SciTech Connect (OSTI)

    Kalispel Tribe, Department of Natural Resources

    1998-01-01T23:59:59.000Z

    In 1996, construction activities commenced on a largemouth bass hatchery located on the Kalispel Indian Reservation. The major construction activities were complete as of October 1997. Of the six objectives identified in the 1997 Annual Operating Plan two objectives were fully achieved: the assembly of the life support system, and the preparation of the hatchery Operations and Maintenance Manual. The remaining four objectives were not fully achieved due to the hatchery not being completed before the spawning season (spring).

  17. Multifamily Building Operator Job/Task Analysis and Report: September 2013

    SciTech Connect (OSTI)

    Owens, C. M.

    2013-09-01T23:59:59.000Z

    The development of job/task analyses (JTAs) is one of three components of the Guidelines for Home Energy Professionals project and will allow industry to develop training resources, quality assurance protocols, accredited training programs, and professional certifications. The Multifamily Building Operator JTA identifies and catalogs all of the tasks performed by multifamily building operators, as well as the knowledge, skills, and abilities (KSAs) needed to perform the identified tasks.

  18. annual report 2005 cover picture

    E-Print Network [OSTI]

    Haviland, David

    Ation AdministrAtion 36 foundation capital 36 operations 36 Profit And Loss stAtement 38 bALAnce sHeet 39 LicentiAte of Science in Engineering, a master's, licentiate or doctoral degree. There are technical preparatory courses

  19. Solid waste operations complex W-113: Specifications. Preliminary design report. Volume III

    SciTech Connect (OSTI)

    NONE

    1995-01-01T23:59:59.000Z

    This document is Volume III of the Preliminary Design report for the Solid Waste Retrieval Facility at Hanford. The report was prepared by Raytheon and BNFL Inc. and submitted to Westinghouse Hanford Company in January 1995. This volume is a complete listing of the specifications for construction and the required material and equipment.

  20. Walla Walla River Fish Passage Operations Program, 2004-2005 Annual Report.

    SciTech Connect (OSTI)

    Bronson, James P. (Confederated Tribes of the Umatilla Indian Reservation, Department of Natural Resources, Pendleton, OR); Duke, Bill B. (Oregon Department of Fish and Wildlife, Pendleton, OR)

    2006-02-01T23:59:59.000Z

    In the late 1990s, the Confederated Tribes of the Umatilla Indian Reservation, Oregon Department of Fish and Wildlife, and Washington Department of Fish and Wildlife, along with many other agencies, began implementing fisheries restoration activities in the Walla Walla Basin. An integral part of these efforts is to alleviate the inadequate fish migration conditions in the basin. The migration concerns are being addressed by removing diversion structures, constructing fish passage facilities, implementing minimum instream flow requirements, and providing trap and haul efforts when needed. The objective of the Walla Walla River Fish Passage Operations Project is to increase the survival of migrating adult and juvenile salmonids in the Walla Walla River basin. The project is responsible for coordinating operation and maintenance of ladders, screen sites, bypasses, trap facilities, and transportation equipment. In addition, the project provides technical input on passage criteria and passage and trapping facility design and operation. Operation of the various passage facilities and passage criteria guidelines are outlined in an annual operations plan that the project develops. During the 2004-2005 project year, there were 590 adult summer steelhead, 31 summer steelhead kelts (Oncorhynchus mykiss), 70 adult bull trout (Salvelinus confluentus); 80 adult and 1 jack spring Chinook (O. tshawytscha) enumerated at the Nursery Bridge Dam fishway video counting window between December 13, 2004, and June 16, 2005. Summer steelhead and spring chinook were observed moving upstream while bull trout were observed moving both upstream and downstream of the facility. In addition, the old ladder trap was operated by ODFW in order to enumerate fish passage. Of the total, 143 adult summer steelhead and 15 summer steelhead kelts were enumerated at the west ladder at Nursery Bridge Dam during the video efforts between February 4 and May 23, 2005. Operation of the Little Walla Walla River juvenile trap for trap and haul purposes was not necessary this year.

  1. Phase 1 remedial investigation report for 200-BP-1 operable unit. Volume 1

    SciTech Connect (OSTI)

    Not Available

    1993-09-01T23:59:59.000Z

    The US Department of Energy (DOE) Hanford Site, in Washington State is organized into numerically designated operational areas including the 100, 200, 300, 400, 600, and 1100 Areas. The US Environmental Protection Agency (EPA), in November 1989 included the 200 Areas of the Hanford Site on the National Priority List (NPL) under the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (CERCLA). Inclusion on the NPL initiated the remedial investigation (RD process for the 200-BP-1 operable unit. These efforts are being addressed through the Hanford Federal Facility Agreement and Consent Order (Ecology et al. 1989) which was negotiated and approved by the DOE, the EPA, and the State of Washington Department of Ecology (Ecology) in May 1989. This agreement, known as the Tri-Party Agreement, governs all CERCLA efforts at Hanford. In March of 1990, the Department of Energy, Richland Operations (DOE-RL) issued a Remedial Investigation/Feasibility Study (RI/FS) work plan (DOE-RL 1990a) for the 200-BP-1 operable unit. The work plan initiated the first phase of site characterization activities associated with the 200-BP-1 operable unit. The purpose of the 200-BP-1 operable unit RI is to gather and develop the necessary information to adequately understand the risks to human health and the environment posed by the site and to support the development and analysis of remedial alternatives during the FS. The RI analysis will, in turn, be used by Tri-Party Agreement signatories to make a risk-management-based selection of remedies for the releases of hazardous substances that have occurred from the 200-BP-1 operable unit.

  2. W-026, transuranic waste restricted waste management (TRU RWM) glovebox operational test report

    SciTech Connect (OSTI)

    Leist, K.J.

    1998-02-18T23:59:59.000Z

    The TRU Waste/Restricted Waste Management (LLW/PWNP) Glovebox 401 is designed to accept and process waste from the Transuranic Process Glovebox 302. Waste is transferred to the glovebox via the Drath and Schraeder Bagless Transfer Port (DO-07401) on a transfer stand. The stand is removed with a hoist and the operator inspects the waste (with the aid of the Sampling and Treatment Director) to determine a course of action for each item. The waste is separated into compliant and non compliant. One Trip Port DO-07402A is designated as ``Compliant``and One Trip Port DO-07402B is designated as ``Non Compliant``. As the processing (inspection, bar coding, sampling and treatment) of the transferred items takes place, residue is placed in the appropriate One Trip port. The status of the waste items is tracked by the Data Management System (DMS) via the Plant Control System (PCS) barcode interface. As an item is moved for sampling or storage or it`s state altered by treatment, the Operator will track an items location using a portable barcode reader and entry any required data on the DMS console. The Operational Test Procedure (OTP) will perform evolutions (described here) using the Plant Operating Procedures (POP) in order to verify that they are sufficient and accurate for controlled glovebox operation.

  3. Turbine Reliability and Operability Optimization through the use of Direct Detection Lidar Final Technical Report

    SciTech Connect (OSTI)

    Johnson, David K; Lewis, Matthew J; Pavlich, Jane C; Wright, Alan D; Johnson, Kathryn E; Pace, Andrew M

    2013-02-01T23:59:59.000Z

    The goal of this Department of Energy (DOE) project is to increase wind turbine efficiency and reliability with the use of a Light Detection and Ranging (LIDAR) system. The LIDAR provides wind speed and direction data that can be used to help mitigate the fatigue stress on the turbine blades and internal components caused by wind gusts, sub-optimal pointing and reactionary speed or RPM changes. This effort will have a significant impact on the operation and maintenance costs of turbines across the industry. During the course of the project, Michigan Aerospace Corporation (MAC) modified and tested a prototype direct detection wind LIDAR instrument; the resulting LIDAR design considered all aspects of wind turbine LIDAR operation from mounting, assembly, and environmental operating conditions to laser safety. Additionally, in co-operation with our partners, the National Renewable Energy Lab and the Colorado School of Mines, progress was made in LIDAR performance modeling as well as LIDAR feed forward control system modeling and simulation. The results of this investigation showed that using LIDAR measurements to change between baseline and extreme event controllers in a switching architecture can reduce damage equivalent loads on blades and tower, and produce higher mean power output due to fewer overspeed events. This DOE project has led to continued venture capital investment and engagement with leading turbine OEMs, wind farm developers, and wind farm owner/operators.

  4. Mitigation for the Construction and Operation of Libby Dam, 2004-2005 Annual Report.

    SciTech Connect (OSTI)

    Dunnigan, James; DeShazer, Jay; Garrow, Larry (Montana Department of Fish, Wildlife and Parks, Libby, MT)

    2005-06-01T23:59:59.000Z

    ''Mitigation for the Construction and Operation of Libby Dam'' is part of the Northwest Power and Conservation Council's (NPCC) resident fish and wildlife program. The program was mandated by the Northwest Planning Act of 1980, and is responsible for mitigating damages to fish and wildlife caused by hydroelectric development in the Columbia River Basin. The objective of Phase I of the project (1983 through 1987) was to maintain or enhance the Libby Reservoir fishery by quantifying seasonal water levels and developing ecologically sound operational guidelines. The objective of Phase II of the project (1988 through 1996) was to determine the biological effects of reservoir operations combined with biotic changes associated with an aging reservoir. The objectives of Phase III of the project (1996 through present) are to implement habitat enhancement measures to mitigate for dam effects, to provide data for implementation of operational strategies that benefit resident fish, monitor reservoir and river conditions, and monitor mitigation projects for effectiveness. This project completes urgent and high priority mitigation actions as directed by the Kootenai Subbasin Plan. Montana Fish, Wildlife & Parks (MFWP) uses a combination of techniques to collect physical and biological data within the Kootenai River Basin. These data serve several purposes including: the development and refinement of models used in management of water resources and operation of Libby Dam; investigations into the limiting factors of native fish populations, gathering basic life history information, tracking trends in endangered and threatened species, and the assessment of restoration or management activities designed to restore native fishes and their habitats.

  5. Solid Waste Operations Complex W-113, Detail Design Report (Title II). Volume 4: Project cost estimate

    SciTech Connect (OSTI)

    NONE

    1995-09-01T23:59:59.000Z

    The Solid Waste Retrieval Facility--Phase 1 (Project W113) will provide the infrastructure and the facility required to retrieve from Trench 04, Burial ground 4C, contact handled (CH) drums and boxes at a rate that supports all retrieved TRU waste batching, treatment, storage, and disposal plans. This includes (1) operations related equipment and facilities, viz., a weather enclosure for the trench, retrieval equipment, weighing, venting, obtaining gas samples, overpacking, NDE, NDA, shipment of waste and (2) operations support related facilities, viz., a general office building, a retrieval staff change facility, and infrastructure upgrades such as supply and routing of water, sewer, electrical power, fire protection, roads, and telecommunication. Title I design for the operations related equipment and facilities was performed by Raytheon/BNFL, and that for the operations support related facilities including infrastructure upgrade was performed by KEH. These two scopes were combined into an integrated W113 Title II scope that was performed by Raytheon/BNFL. This volume represents the total estimated costs for the W113 facility. Operating Contractor Management costs have been incorporated as received from WHC. The W113 Facility TEC is $19.7 million. This includes an overall project contingency of 14.4% and escalation of 17.4%. A January 2001 construction contract procurement start date is assumed.

  6. Walla Walla River Fish Passage Operations Program, 2002-2003 Annual Report.

    SciTech Connect (OSTI)

    Bronson, James P. (Confederated Tribes of the Umatilla Indian Reservation, Department of Natural Resources, Pendleton, OR); Duke, Bill B. (Oregon Department of Fish and Wildlife, Pendleton, OR)

    2004-03-01T23:59:59.000Z

    In the late 1990's, the Confederated Tribes of the Umatilla Indian Reservation, Oregon Department of Fish and Wildlife, and Washington Department of Fish and Wildlife, along with many other agencies, began implementing fisheries restoration activities in the Walla Walla Basin. An integral part of these efforts is to alleviate the inadequate fish migration conditions in the basin. The migration concerns are being addressed by removing diversion structures, constructing fish passage facilities, implementing minimum instream flow requirements, and initiating trap and haul efforts. The objective of the Walla Walla River Fish Passage Operations Project is to increase the survival of migrating adult and juvenile salmonids in the Walla Walla River basin. The project is responsible for coordinating operation and maintenance of ladders, screen sites, bypasses, trap facilities, and transportation equipment. In addition, the project provides technical input on passage criteria and passage and trapping facility design and operation. Operation of the various passage facilities and passage criteria guidelines are outlined in an annual operations plan that the project develops. During the 2002-2003 project year, there were 545 adult summer steelhead (Oncorhynchus mykiss), 29 adult bull trout (Salvelinus confluentus); 1 adult and 1 jack spring chinook (O. tshawytscha) enumerated at the Nursery Bridge Dam fishway adult trap between January 1 and June 23, 2003. Summer steelhead and spring chinook were observed moving upstream while bull trout were observed moving both upstream and downstream of the facility. Operation of the Little Walla Walla River juvenile trap for trap and haul purposes was not necessary this year. The project transported 21 adult spring chinook from Ringold Springs Hatchery and 281 from Threemile Dam to the South Fork Walla Walla Brood Holding Facility. Of these, 290 were outplanted in August for natural spawning in the basin.

  7. Walla Walla River Fish Passage Operations Program, 2003-2004 Annual Report.

    SciTech Connect (OSTI)

    Bronson, James P. (Confederated Tribes of the Umatilla Indian Reservation, Department of Natural Resources, Pendleton, OR)

    2004-12-01T23:59:59.000Z

    In the late 1990s, the Confederated Tribes of the Umatilla Indian Reservation, Oregon Department of Fish and Wildlife, and Washington Department of Fish and Wildlife, along with many other agencies, began implementing fisheries restoration activities in the Walla Walla Basin. An integral part of these efforts is to alleviate the inadequate fish migration conditions in the basin. The migration concerns are being addressed by removing diversion structures, constructing fish passage facilities, implementing minimum instream flow requirements, and providing trap and haul efforts when needed. The objective of the Walla Walla River Fish Passage Operations Project is to increase the survival of migrating adult and juvenile salmonids in the Walla Walla River basin. The project is responsible for coordinating operation and maintenance of ladders, screen sites, bypasses, trap facilities, and transportation equipment. In addition, the project provides technical input on passage criteria and passage and trapping facility design and operation. Operation of the various passage facilities and passage criteria guidelines are outlined in an annual operations plan that the project develops. During the 2003-2004 project year, there were 379 adult summer steelhead (Oncorhynchus mykiss), 36 adult bull trout (Salvelinus confluentus); 108 adult and 3 jack spring chinook (O. tshawytscha) enumerated at the Nursery Bridge Dam fishway video counting window between December 21, 2003, and June 30, 2004. Summer steelhead and spring chinook were observed moving upstream while bull trout were observed moving both upstream and downstream of the facility. In addition, the old ladder trap was operated by the WWBNPME project in order to radio tag spring chinook adults. A total of 2 adult summer steelhead, 4 bull trout, and 23 adult spring chinook were enumerated at the west ladder at Nursery Bridge Dam during the trapping operations between May 6 and May 23, 2004. Operation of the Little Walla Walla River juvenile trap for trap and haul purposes was not necessary this year. The project transported adult spring chinook from Threemile Dam to the South Fork Walla Walla Brood Holding Facility. A total of 239 spring chinook were outplanted in August for natural spawning in the basin.

  8. Data Summary Report for Savannah River Integrator Operable Unit Fish Tissue

    SciTech Connect (OSTI)

    Craig, B.

    2001-02-13T23:59:59.000Z

    This report presents the results of the verification and validation of the analytical data for the Savannah River Fish (SRF) investigation. The data were validated to determine if the records conform to the technical criteria associated with definitive data.

  9. NSTX Weekly Report (May 28, 2010) FY 2010 NSTX plasma operations

    E-Print Network [OSTI]

    Princeton Plasma Physics Laboratory

    . Twelve papers have been submitted for publication in Journal of Nuclear Materials. The poster given Lithium Evaporation onto the NSTX Vessel Walls" by D. Stotler, "Macroscopic Motion of Liquid Metal Plasma operations resumed this past week after completion of combined field power testing, leading to the successful

  10. NSTX Weekly Report (November 24, 2010) FY 2011 NSTX plasma operations started on October 4, 2010

    E-Print Network [OSTI]

    Princeton Plasma Physics Laboratory

    in NSTX" by V. A. Soukhanovskii (LLNL) et al. has been accepted for publication in Nuclear Fusion Operations (A. von Halle, C. Neumeyer) The NSTX outage continued this past week with in-vessel diagnostic removed and brought to the Vacuum Prep Lab for transmission testing. A water leak was discovered

  11. Solid Waste Operations Complex W-113, Detail Design Report (Title II). Volume 3: Specifications

    SciTech Connect (OSTI)

    NONE

    1995-09-01T23:59:59.000Z

    The Solid Waste Retrieval Facility--Phase 1 (Project W113) will provide the infrastructure and the facility required to retrieve from Trench 04, Burial ground 4C, contact handled (CH) drums and boxes at a rate that supports all retrieved TRU waste batching, treatment, storage, and disposal plans. This includes (1) operations related equipment and facilities, viz., a weather enclosure for the trench, retrieval equipment, weighing, venting, obtaining gas samples, overpacking, NDE, NDA, shipment of waste and (2) operations support related facilities, viz., a general office building, a retrieval staff change facility, and infrastructure upgrades such as supply and routing of water, sewer, electrical power, fire protection, roads, and telecommunication. Title I design for the operations related equipment and facilities was performed by Raytheon/BNFL, and that for the operations support related facilities including infrastructure upgrade was performed by KEH. These two scopes were combined into an integrated W113 Title II scope that was performed by Raytheon/BNFL. Volume 3 is a compilation of the construction specifications that will constitute the Title II materials and performance specifications. This volume contains CSI specifications for non-equipment related construction material type items, performance type items, and facility mechanical equipment items. Data sheets are provided, as necessary, which specify the equipment overall design parameters.

  12. NSTX Weekly Report (Mar. 5, 2010) FY 2010 NSTX plasma operations

    E-Print Network [OSTI]

    Princeton Plasma Physics Laboratory

    obtained by lowering the edge density with lithium wall conditioning. Lithium conditioning allowed of rf power. Visible and infrared camera images show that fast wave interactions can deposit Physics Operations (H. Kugel) · Liquid Lithium Divertor (LLD) Diagnostics - Filters for the Divertor Fast

  13. Annual Report of the EURATOM/UKAEA Fusion Programme 2006/07 4 JET Operations

    E-Print Network [OSTI]

    2006. The reliability and availability of the JET systems remained low during this period out a review of the reliability of JET systems, which took place in September 2006. All JET systems were reviewed and all the main equipment failures that had affected JET operation during the last few

  14. Environmental assessment for device assembly facility operations, Nevada Test Site, Nye County, Nevada. Final report

    SciTech Connect (OSTI)

    NONE

    1995-05-01T23:59:59.000Z

    The U.S. Department of Energy, Nevada Operations Office (DOE/NV), has prepared an environmental assessment (EA), (DOE/EA-0971), to evaluate the impacts of consolidating all nuclear explosive operations at the newly constructed Device Assembly Facility (DAF) in Area 6 of the Nevada Test Site. These operations generally include assembly, disassembly or modification, staging, transportation, testing, maintenance, repair, retrofit, and surveillance. Such operations have previously been conducted at the Nevada Test Site in older facilities located in Area 27. The DAF will provide enhanced capabilities in a state-of-the-art facility for the safe, secure, and efficient handling of high explosives in combination with special nuclear materials (plutonium and highly enriched uranium). Based on the information and analyses in the EA, DOE has determined that the proposed action would not constitute a major federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.). Therefore, an environmental impact statement is not required, and DOE is issuing this finding of no significant impact.

  15. Final Report for Organic Partitioning Resulting from Operation of an INTEC Double-needle Sampler

    SciTech Connect (OSTI)

    Michael B. Heiser

    2003-09-01T23:59:59.000Z

    The double needle sampler testing is a continuation of previous test series that investigated the fate of organic species in the Process Equipment Waste Evaporator (PEWE) system at the Idaho Nuclear Technology and Engineering Center (INTEC). This test series was designed to investigate the effects of operation of the double needle sampling systems on volatile organic constituents in an acidic feed matrix.

  16. Limited field investigation report for the 100-HR-3 operable unit

    SciTech Connect (OSTI)

    Not Available

    1994-09-01T23:59:59.000Z

    This limited field investigation (LFI) was conducted to assess the applicability of interim remedial measures (IRM) for reducing human health and environmental risks within the 100-HR-3 Groundwater Operable Unit. The 100-HR-3 Operable Unit is comprised of three subareas; the 100 D Area, the 100 H Area and those portions of the 600 Area between the two reactor areas. The operable unit is one of seven operable units associated with the 100 D and H Areas. Operable units 100-DR-1, 100-DR-2, 100-DR-3, 100-HR-1, 100-HR-2 and 100-IU-4 address contaminant sources while 100-HR-3 addresses contamination present in the underlying groundwater. The primary method of field investigation used during this LFI was the installation and sampling of monitoring wells. Samples were collected from the groundwater and soils, and submitted for laboratory analysis. Boreholes were surveyed for radiological contamination using downhole geophysical techniques to further delineate the locations and levels of contaminants. All samples were screened to ascertain the presence of volatile organic compounds and radionuclides. Analytical data were subjected to validation; all round one, two and three and a minimum of 10% of round four data associated with the LFI were validated. A screening method was used to identify contaminants of potential concern (COPC). This screening method eliminated from further consideration, constituents that were below background. Constituents which are considered non-toxic to humans were eliminated from the human health evaluation. Data consistency and blank contamination were also evaluated in the screening process. These COPC were then evaluated further in the qualitative risk assessment (QRA). A human health QRA was performed using conservative (maximum equilibrated contaminant levels from the LFI) analyses.

  17. Naval Petroleum and Oil Shale Reserves annual report of operations for fiscal year 1996

    SciTech Connect (OSTI)

    NONE

    1996-12-31T23:59:59.000Z

    During fiscal year 1996, the Department of Energy continued to operate Naval Petroleum Reserve No. 1 in California and Naval Petroleum Reserve No. 3 in Wyoming through its contractors. In addition, natural gas operations were conducted at Naval Petroleum Reserve No. 3. All productive acreage owned by the Government at Naval Petroleum Reserve No. 2 in California was produced under lease to private companies. The locations of all six Naval Petroleum and Oil Shale Reserves are shown in a figure. Under the Naval Petroleum Reserves Production Act of 1976, production was originally authorized for six years, and based on findings of national interest, the President was authorized to extend production in three-year increments. President Reagan exercised this authority three times (in 1981, 1984, and 1987) and President Bush authorized extended production once (in 1990). President Clinton exercised this authority in 1993 and again in October 1996; production is presently authorized through April 5, 2000. 4 figs. 30 tabs.

  18. Integrated DWPF Melter System (IDMS) campaign report: The first two noble metals operations

    SciTech Connect (OSTI)

    Hutson, N.D.; Zamecnik, J.R.; Smith, M.E.; Miller, D.H.; Ritter, J.A.

    1991-06-06T23:59:59.000Z

    The Integrated DWPF Melter System (IDMS) is designed and constructed to provide an engineering-scale representation of the DWPF melter and its associated feed preparation and off-gas systems. The facility is the first pilot-scale melter system capable of processing mercury, and flowsheet levels of halides and noble metals. In order to characterize the processing of noble metals (Pd, Rh, Ru, and Ag) on a large scale, the IDMS will be operated batchstyle for at least nine feed preparation cycles. The first two of these operations are complete. The major observation to date occurred during the second run when significant amounts of hydrogen were evolved during the feed preparation cycle. The runs were conducted between June 7, 1990 and March 8, 1991. This time period included nearly six months of ``fix-up`` time when forced air purges were installed on the SRAT MFT and other feed preparation vessels to allow continued noble metals experimentation.

  19. Report on inspection of the performance based incentive program at the Richland Operations Office

    SciTech Connect (OSTI)

    NONE

    1997-03-10T23:59:59.000Z

    The Fiscal Year (FY) 1995 Performance Based Incentive (PBI) Program at the Department of Energy`s (DOE) Richland Operations Office (Richland) was initiated by Richland as one part of the broader DOE Contract Reform Initiative being implemented at the Hanford Site in FY 1995. This program was identified as an area of concern by the Office of Inspections as a result of previous inspection work. Specifically, during a limited review of the construction of an Effluent Treatment Facility at the Hanford Site, we were unable to identify any written policies describing PBI program controls or implementation procedures. We were told that Richland Operations Office Program Management personnel were not directly involved in the selection of the Effluent Treatment Facility project for the PBI Program, or in the determination that this particular PBI would be established with a potential fee of $1 million.

  20. Kalispel Resident Fish Project: Kalispel Tribal Hatchery Operations and Maintenance, 2000 Annual Report.

    SciTech Connect (OSTI)

    Bluff, Stanley

    2000-12-01T23:59:59.000Z

    No Annual Production Goals were achieved for the year. The Kalispel Hatchery experienced two episodes of brood fish mortality. The first due to a standpipe malfunction and the second attributed to gas bubble disease caused by elevated Total Dissolved Gases (TDG's) in the reservoir. To date, the hatchery has 29 brood fish in the raceway and ready to spawn. If all things go well this spring, hatchery operations should be well underway next year.

  1. ANNUAL REPORT 2012 CONTINUING EDUCATION

    E-Print Network [OSTI]

    -13 tuition rates IMAGINING POSSIBILITIES CONNECTING COMMUNITIES2012 SAw TwO BIG UPdATES fOr CONTINUING EdUCATIONANNUAL REPORT 2012 CONTINUING EDUCATION AT THE UNIVERSITY OF UTAH #12;As one of the top knowledge the U) becomes. For well over 100 years, Continuing Education at the University of Utah has been opening

  2. Co-operativeEducation&Internships Why hire a Co-op Student?

    E-Print Network [OSTI]

    Seldin, Jonathan P.

    Co-operativeEducation&Internships Why hire a Co-op Student? employer information Co-building,interpersonalandtimemanagementskills.Ultimately,thegreatestbenefitwasthe workexperienceIgainedfromthisCo-opworkterm. GavinMcAtee,BASc(Co-op) #12;What is Co-op? TheCo-operativeEducation&Internships(Co-andlong-termrecruitingneeds.Studentsmakepositive contributionstotheorganizationthroughplanned,supervisedworkterms. ThroughCo

  3. Operational Readiness Review Final Report For F-Canyon Restart. Phase 1

    SciTech Connect (OSTI)

    McFarlane, A.F.; Spangler, J.B.

    1995-04-05T23:59:59.000Z

    An independent WSRC Operational Readiness Review was performed for the restart of Phase 1 processing in F-Canyon, Building 221-F. Readiness to restart the Second Plutonium Cycle process and solvent recovery was assessed. The ORR was conducted by an ORR board of ten members with the support of a subject matter expert. The chairman and four members were drawn from the Operational Safety Evaluation Department, ESH& QA Division; additional members were drawn from other WSRC divisions, independent of the F-Canyon operating division (NMPD). Based on the results of the readiness verification assessments performed according to the ORR plan and the validation of pre-restart corrective actions, the WSRC independent ORR Board has concluded that the facility has achieved the state of readiness committed to in the Restart Plan. Also, based on the scope of the ORR, it is the opinion of the board that F-Canyon Phase 1 processes can be restarted without undue risk to the safety of the public and onsite workers and without undue risk to the environment.

  4. W-026 integrated engineering cold run operational test report for balance of plant (BOP)

    SciTech Connect (OSTI)

    Kersten, J.K.

    1998-02-24T23:59:59.000Z

    This Cold Run test is designed to demonstrate the functionality of systems necessary to move waste drums throughout the plant using approved procedures, and the compatibility of these systems to function as an integrated process. This test excludes all internal functions of the gloveboxes. In the interest of efficiency and support of the facility schedule, the initial revision of the test (rev 0) was limited to the following: Receipt and storage of eight overpacked drums, four LLW and four TRU; Receipt, routing, and staging of eleven empty drums to the process area where they will be used later in this test; Receipt, processing, and shipping of two verification drums (Route 9); Receipt, processing, and shipping of two verification drums (Route 1). The above listed operations were tested using the rev 0 test document, through Section 5.4.25. The document was later revised to include movement of all staged drums to and from the LLW and TRU process and RWM gloveboxes. This testing was performed using Sections 5.5 though 5.11 of the rev 1 test document. The primary focus of this test is to prove the functionality of automatic operations for all mechanical and control processes listed. When necessary, the test demonstrates manual mode operations as well. Though the gloveboxes are listed, only waste and empty drum movement to, from, and between the gloveboxes was tested.

  5. Site Environmental Report for Calendar Year 2007. DOE Operations at The Boeing Company, Santa Susana Field Laboratory, Area IV

    SciTech Connect (OSTI)

    none,

    2008-09-30T23:59:59.000Z

    This Annual Site Environmental Report (ASER) for 2007 describes the environmental conditions related to work performed for the Department of Energy (DOE) at Area IV of Boeing’s Santa Susana Field Laboratory (SSFL). The Energy Technology Engineering Center (ETEC), a government-owned, company-operated test facility, was located in Area IV. The operations in Area IV included development, fabrication, and disassembly of nuclear reactors, reactor fuel, and other radioactive materials. Other activities in the area involved the operation of large-scale liquid metal facilities that were used for testing non-nuclear liquid metal fast breeder components. All nuclear work was terminated in 1988; all subsequent radiological work has been directed toward decontamination and decommissioning (D&D) of the former nuclear facilities and their associated sites. In May 2007, the D&D operations in Area IV were suspended until DOE completes the SSFL Area IV Environmental Impact Statement (EIS). The environmental monitoring programs were continued throughout the year. Results of the radiological monitoring program for the calendar year 2007 continue to indicate that there are no significant releases of radioactive material from Area IV of SSFL. All potential exposure pathways are sampled and/or monitored, including air, soil, surface water, groundwater, direct radiation, transfer of property (land, structures, waste), and recycling. All radioactive wastes are processed for disposal at DOE disposal sites and/or other licensed sites approved by DOE for radioactive waste disposal. No liquid radioactive wastes were released into the environment in 2007.

  6. ANNUAL REPORT FOR THE FINAL GROUNDWATER REMEDIATION, TEST AREA NORTH, OPERABLE UNIT 1-07B, FISCAL YEAR 2009

    SciTech Connect (OSTI)

    FORSYTHE, HOWARD S

    2010-04-14T23:59:59.000Z

    This Annual Report presents the data and evaluates the progress of the three-component remedy implemented for remediation of groundwater contamination at Test Area North, Operable Unit 1-07B, at the Idaho National Laboratory Site. Overall, each component is achieving progress toward the goal of total plume remediation. In situ bioremediation operations in the hot spot continue to operate as planned. Progress toward the remedy objectives is being made, as evidenced by continued reduction in the amount of accessible residual source and decreases in downgradient contaminant flux, with the exception of TAN-28. The injection strategy is maintaining effective anaerobic reductive dechlorination conditions, as evidenced by complete degradation of trichloroethene and ethene production in the biologically active wells. In the medial zone, the New Pump and Treat Facility operated in standby mode. Trichloroethene concentrations in the medial zone wells are significantly lower than the historically defined concentration range of 1,000 to 20,000 ?g/L. The trichloroethene concentrations in TAN-33, TAN-36, and TAN-44 continue to be below 200 ?g/L. Monitoring in the distal zone wells outside and downgradient of the plume boundary demonstrate that some plume expansion has occurred, but less than the amount allowed in the Record of Decision Amendment. Additional data need to be collected for wells in the monitored natural attenuation part of the plume to confirm that the monitored natural attenuation part of the remedy is proceeding as predicted in the modeling.

  7. Libby Mitigation Program, 2007 Annual Progress Report: Mitigation for the Construction and Operation of Libby Dam.

    SciTech Connect (OSTI)

    Dunnigan, James; DeShazer, J.; Garrow, L.

    2009-05-26T23:59:59.000Z

    Libby Reservoir was created under an International Columbia River Treaty between the United States and Canada for cooperative water development of the Columbia River Basin (Columbia River Treaty 1964). Libby Reservoir inundated 109 stream miles of the mainstem Kootenai River in the United States and Canada, and 40 miles of tributary streams in the U.S. that provided habitat for spawning, juvenile rearing, and migratory passage (Figure 1). The authorized purpose of the dam is to provide power (91.5%), flood control (8.3%), and navigation and other benefits (0.2%; Storm et al. 1982). The Pacific Northwest Power Act of 1980 recognized possible conflicts stemming from hydroelectric projects in the northwest and directed Bonneville Power Administration to 'protect, mitigate, and enhance fish and wildlife to the extent affected by the development and operation of any hydroelectric project of the Columbia River and its tributaries' (4(h)(10)(A)). Under the Act, the Northwest Power Planning Council was created and recommendations for a comprehensive fish and wildlife program were solicited from the region's federal, state, and tribal fish and wildlife agencies. Among Montana's recommendations was the proposal that research be initiated to quantify acceptable seasonal minimum pool elevations to maintain or enhance the existing fisheries (Graham et al. 1982). Research to determine how operations of Libby Dam affect the reservoir and river fishery and to suggest ways to lessen these effects began in May 1983. The framework for the Libby Reservoir Model (LRMOD) was completed in 1989. Development of Integrated Rule Curves (IRCs) for Libby Dam operation was completed in 1996 (Marotz et al. 1996). The Libby Reservoir Model and the IRCs continue to be refined (Marotz et al 1999). Initiation of mitigation projects such as lake rehabilitation and stream restoration began in 1996. The primary focus of the Libby Mitigation project now is to restore the fisheries and fish habitat in basin streams and lakes. 'Mitigation for the Construction and Operation of Libby Dam' is part of the Northwest Power and Conservation Council's (NPCC) resident fish and wildlife program. The program was mandated by the Northwest Planning Act of 1980, and is responsible for mitigating damages to fish and wildlife caused by hydroelectric development in the Columbia River Basin. The objective of Phase I of the project (1983 through 1987) was to maintain or enhance the Libby Reservoir fishery by quantifying seasonal water levels and developing ecologically sound operational guidelines. The objective of Phase II of the project (1988 through 1996) was to determine the biological effects of reservoir operations combined with biotic changes associated with an aging reservoir. The objectives of Phase III of the project (1996 through present) are to implement habitat enhancement measures to mitigate for dam effects, to provide data for implementation of operational strategies that benefit resident fish, monitor reservoir and river conditions, and monitor mitigation projects for effectiveness. This project completes urgent and high priority mitigation actions as directed by the Kootenai Subbasin Plan.

  8. Technical Qualification Program Self-Assessment Report- Idaho Operations Office- 2011

    Broader source: Energy.gov [DOE]

    This TQP self-assessment was performed by a review team with extensive assessment experience. The assessment approach consisted of interviewing Managers, Division Directors, Team Leads, Qualifying Officials, and a representative sample of TQP participants, reviewing applicable records, reports, and IDMS documents, and observing continuing training activities.

  9. Tank farm restoration and safe operation, project W-314, upgrade scope summary report (USSR)

    SciTech Connect (OSTI)

    Jacobson, R.W.

    1997-04-01T23:59:59.000Z

    This revision to the Project W-314 Upgrade Scope Summary Report (USSR), incorporates changes to the project scope from Alternative Generation Analysis (AGA), customer guidance, and changing requirements. It defines the actual upgrades currently in scope, and provides traceability to the requirements and/or drivers.

  10. Operational Arome New Arome version in test Radar observation Report 2009

    E-Print Network [OSTI]

    Ribes, Aurélien

    , a new version of our Earth-System model has been prepared to guarantee our contributions to the upcoming 5th IPCC report. Consultations with IPSL have started to share a larger part of the Earth System modelling infrastructure. Re- search has largely contributed to the gro- wing offer of Météo

  11. U.S. Department of Energy, Nevada Operations Office, environmental data report for the Nevada Test Site -- 1995

    SciTech Connect (OSTI)

    Black, S.C.; Townsend, Y.E. [eds.; Kinnison, R.R.

    1997-10-01T23:59:59.000Z

    The US Department of Energy (DOE) Order 5400.1, ``General Environmental Protection Program,`` establishes environmental protection program requirements, authorities, and responsibilities for DOE operations. These mandates require compliance with applicable federal, state, and local environmental protection regulations. During calendar year (CY) 1995 environmental protection and monitoring programs were conducted at the Nevada Test Site (NTS) and other DOE Nevada Operations Office (DOE/NV) managed sites in Nevada and across the United States. A detailed discussion of these environmental protection and monitoring programs, and summary data and assessments for environmental monitoring results at these sites in CY 1995 are provided in the DOE/NV, Annual Site Environmental Report--1995, (ASER) DOE/NV/11718-037. A brief description of the scope of this environmental monitoring is provided below, categorized by ``on-NTS`` and ``off-NTS`` monitoring.

  12. Characterization ReportOperational Closure Covers for the Area 5 Radioactive Waste Management Site at the Nevada Test Site

    SciTech Connect (OSTI)

    Bechtel Nevada Geotechnical Sciences

    2005-06-01T23:59:59.000Z

    Bechtel Nevada (BN) manages two low-level Radioactive Waste Management Sites (RWMSs) at the Nevada Test Site (NTS) for the U.S. Department of Energy (DOE) National Nuclear Security Administration Nevada Site Office (NNSA/NSO). The Area 3 RWMS is located in south-central Yucca Flat and the Area 5 RWMS is located about 15 miles south, in north-central Frenchman Flat. Though located in two separate topographically closed basins, they are similar in climate and hydrogeologic setting. The Area 5 RWMS uses engineered shallow-land burial cells to dispose of packaged waste, while the Area 3 RWMS uses subsidence craters formed from underground testing of nuclear weapons for the disposal of packaged and unpackaged bulk waste. Over the next several decades, most waste disposal units at both the Area 3 and Area 5 RWMSs are anticipated to be closed. Closure of the Area 3 and Area 5 RWMSs will proceed through three phases: operational closure, final closure, and institutional control. Many waste disposal units at the Area 5RWMS are operationally closed and final closure has been placed on one unit at the Area 3 RWMS (U-3ax/bl). Because of the similarities between the two sites (e.g., type of wastes, environmental factors, operational closure cover designs, etc.), many characterization studies and data collected at the Area 3 RWMS are relevant and applicable to the Area 5 RWMS. For this reason, data and closure strategies from the Area 3 RWMS are referred to as applicable. This document is an interim Characterization ReportOperational Closure Covers, for the Area 5 RWMS. The report briefly describes the Area 5 RWMS and the physical environment where it is located, identifies the regulatory requirements, reviews the approach and schedule for closing, summarizes the monitoring programs, summarizes characterization studies and results, and then presents conclusions and recommendations.

  13. Mitigation for the Construction and Operation of Libby Dam, 2001-2002 Annual Report.

    SciTech Connect (OSTI)

    Dunnigan, James L.; Marotz, Brian L.; DeShazer, Jay (Montana Department of Fish, Wildlife and Parks, Libby, MT)

    2003-06-01T23:59:59.000Z

    Libby Reservoir was created under an International Columbia River Treaty between the United States and Canada for cooperative water development of the Columbia River Basin (Columbia River Treaty 1964). Libby Reservoir inundated 109 stream miles of the mainstem Kootenai River in the United States and Canada, and 40 miles of tributary streams in the U.S. that provided habitat for spawning, juvenile rearing, and migratory passage (Figure 1). The authorized purpose of the dam is to provide power (91.5%), flood control (8.3%), and navigation and other benefits (0.2%; Storm et al. 1982). The Pacific Northwest Power Act of 1980 recognized possible conflicts stemming from hydroelectric projects in the northwest and directed Bonneville Power Administration to ''protect, mitigate, and enhance fish and wildlife to the extent affected by the development and operation of any hydroelectric project of the Columbia River and its tributaries...'' (4(h)(10)(A)). Under the Act, the Northwest Power Planning Council was created and recommendations for a comprehensive fish and wildlife program were solicited from the region's federal, state, and tribal fish and wildlife agencies. Among Montana's recommendations was the proposal that research be initiated to quantify acceptable seasonal minimum pool elevations to maintain or enhance the existing fisheries (Graham et al. 1982). Research to determine how operations of Libby Dam affect the reservoir and river fishery and to suggest ways to lessen these effects began in May, 1983. The framework for the Libby Reservoir Model (LRMOD) was completed in 1989. Development of Integrated Rule Curves (IRCs) for Libby Dam operation was completed in 1996 (Marotz et al. 1996). The Libby Reservoir Model and the IRCs continue to be refined (Marotz et al 1999). Initiation of mitigation projects such as lake rehabilitation and stream restoration began in 1996. The primary focus of the Libby Mitigation project now is to redevelop fisheries and fisheries habitat in basin streams and lakes.

  14. Duck Valley Reservoirs Fish Stocking and Operation and Maintenance, 2005-2006 Annual Progress Report.

    SciTech Connect (OSTI)

    Sellman, Jake; Dykstra, Tim [Shoshone-Paiute Tribes

    2009-05-11T23:59:59.000Z

    The Duck Valley Reservoirs Fish Stocking and Operations and Maintenance (DV Fisheries) project is an ongoing resident fish program designed to enhance both subsistence fishing, educational opportunities for Tribal members of the Shoshone-Paiute Tribes, and recreational fishing facilities for non-Tribal members. In addition to stocking rainbow trout (Oncorhynchus mykiss) in Mountain View, Lake Billy Shaw, and Sheep Creek Reservoirs, the program also intends to afford and maintain healthy aquatic conditions for fish growth and survival, to provide superior facilities with wilderness qualities to attract non-Tribal angler use, and to offer clear, consistent communication with the Tribal community about this project as well as outreach and education within the region and the local community. Tasks for this performance period are divided into operations and maintenance plus monitoring and evaluation. Operation and maintenance of the three reservoirs include fences, roads, dams and all reservoir structures, feeder canals, water troughs and stock ponds, educational signs, vehicles and equipment, and outhouses. Monitoring and evaluation activities included creel, gillnet, wildlife, and bird surveys, water quality and reservoir structures monitoring, native vegetation planting, photo point documentation, control of encroaching exotic vegetation, and community outreach and education. The three reservoirs are monitored in terms of water quality and fishery success. Sheep Creek Reservoir was the least productive as a result of high turbidity levels and constraining water quality parameters. Lake Billy Shaw trout were in poorer condition than in previous years potentially as a result of water quality or other factors. Mountain View Reservoir trout exhibit the best health of the three reservoirs and was the only reservoir to receive constant flows of water.

  15. Transferable methods identified during the monitoring of the DOE Chicago Operations Office Weatherization Assistance Program. Final report. Task F

    SciTech Connect (OSTI)

    Not Available

    1983-05-01T23:59:59.000Z

    This report provides the outcomes of the analyses performed under this task. The first of these is the presentation of a range of materials/approaches initially found by contract monitoring teams to be potentially unique/innovative/useful to Weatherization Program operators. The second is a summary of the general categories of information eventually selected as having good transfer potential. The third is a listing of areas of information currently needed by grantees. The final step is a matching of useful information to needs cited by grantees.

  16. Solid waste operations complex W-113: Preliminary design report. Volume I

    SciTech Connect (OSTI)

    NONE

    1995-01-01T23:59:59.000Z

    This document is Volume I of a Preliminary Design Report (Title I) for the Solid Waste Retrieval Facilities-Phase I (Project W-113) at Hanford. It was prepared by Raytheon and BNFL Inc. and submitted to Westinghouse Hanford Company in January 1995. This volume provides a project overview and a discussion of the waste handling systems, the data acquisition and control systems, the building systems, and the site/building structure.

  17. Phase I and II feasibility study report for the 300-FF-5 operable unit

    SciTech Connect (OSTI)

    NONE

    1993-12-31T23:59:59.000Z

    The purpose of this Phase I/II feasibility study is to assemble and screen a list of alternatives for remediation of the 300-FF-5 operable site on the Hanford Reservation. This screening is based on information gathered in the Phase I Remedial Investigation (RI) and on currently available information on remediation technologies. The alternatives remaining after screening provide a range of response actions for remediation. In addition, key data needs are identified for collection during a Phase II RI (if necessary). This Phase I/II FS represents a primary document as defined by the Tri-Party Agreement, but will be followed by a Phase III FS that will further develop the alternatives and provide a detailed evaluation of them. The following remedial action objectives were identified for the 300-FF-5 operable unit: Limit current human exposure to contaminated groundwater in the unit; Limit discharge of contaminated groundwater to the Columbia River; Reduce contaminant concentrations in groundwater below acceptable levels by the year 2018.

  18. Naval Petroleum and Oil Shale Reserves. Annual report of operations, Fiscal year 1992

    SciTech Connect (OSTI)

    Not Available

    1992-12-31T23:59:59.000Z

    During fiscal year 1992, the reserves generated $473 million in revenues, a $181 million decrease from the fiscal year 1991 revenues, primarily due to significant decreases in oil and natural gas prices. Total costs were $200 million, resulting in net cash flow of $273 million, compared with $454 million in fiscal year 1991. From 1976 through fiscal year 1992, the Naval Petroleum and Oil Shale Reserves generated more than $15 billion in revenues and a net operating income after costs of $12.5 billion. In fiscal year 1992, production at the Naval Petroleum Reserves at maximum efficient rates yielded 26 million barrels of crude oil, 119 billion cubic feet of natural gas, and 164 million gallons of natural gas liquids. From April to November 1992, senior managers from the Naval Petroleum and Oil Shale Reserves held a series of three workshops in Boulder, Colorado, in order to build a comprehensive Strategic Plan as required by Secretary of Energy Notice 25A-91. Other highlights are presented for the following: Naval Petroleum Reserve No. 1--production achievements, crude oil shipments to the strategic petroleum reserve, horizontal drilling, shallow oil zone gas injection project, environment and safety, and vanpool program; Naval Petroleum Reserve No. 2--new management and operating contractor and exploration drilling; Naval Petroleum Reserve No. 3--steamflood; Naval Oil Shale Reserves--protection program; and Tiger Team environmental assessment of the Naval Petroleum and Oil Shale Reserves in Colorado, Utah, and Wyoming.

  19. The Airline Operation Control Centre : an overview of Garuda's Operation Control (EM) at Cengkereng Jakarta, Indonesia : final report to PT Garuda Indonesia

    E-Print Network [OSTI]

    Clarke, Michael D. D.

    1995-01-01T23:59:59.000Z

    Introduction: Airline operations are generally handled in two phases, strategic and tactical. Strategic operations are concerned with schedule planning. Given the desired schedule of services to be offered to passengers ...

  20. GTRI Remote Monitoring System: Training and Operational Needs Assessment Analysis Report

    SciTech Connect (OSTI)

    Day, Debra E.; Fox, Sorcha

    2012-04-20T23:59:59.000Z

    The mission of the United States Department of Energy (DOE) National Nuclear Security Administrations (NNSA's) Global Threat Reduction Initiative (GTRI) is to identify, secure, recover and facilitate the disposition of vulnerable nuclear and high-risk radioactive materials around the world that pose a threat to the United States and the international community. The GTRI's unique mission to reduce and protect vulnerable nuclear and radiological materials located at civilian sites worldwide directly addresses recommendations of the 9/11 Commission1, and is a vital part of the President's National Security Strategy and the Global Initiative. The GTRI Remote Monitoring System (RMS) is a standalone security system that includes radiation and tamper alarms, and CCTV; which can be transmitted securely over the Internet to multiple on-site and off-site locations. Through our experiences during installation of the system at 162 sites, plus feedback received from Alarm Response Training course participants, site input to project teams and analysis of trouble calls; indications were that current system training was lacking and inconsistent. A survey was undertaken to gather information from RMS users across the nation, to evaluate the current level of training and determine what if any improvements needed to be made. Additional questions were focused on the operation of the RMS software. The training survey was initially sent electronically to 245 users at the RMS sites and achieved a 37.6% return rate. Analysis of the resulting data revealed that 34.6% of the respondents had not received training or were unsure if they had, despite the fact that vendor engineers provide training at installation of the system. Any training received was referred to as minimal, and brief, not documented, and nothing in writing. 63.7% of respondents said they were either not at all prepared or only somewhat prepared to use the RMS software required to effectively operate the system. As a result of this analysis, a formal training curriculum will be designed and implemented to include several blended learning delivery options. This training will be piloted at RMS sites; initial training will become a required element of RMS installation and refresher training will be considered for sustainability of operations.

  1. Westinghouse Hanford Company operational environmental monitoring annual report, calendar year 1994

    SciTech Connect (OSTI)

    Schmidt, J.; Fassett, J.W.; Johnson, A.R.; Johnson, V.G.; Markes, B.M.; McKinney, S.M.; Moss, K.J.; Perkins, C.J.; Richterich, L.R.

    1995-08-01T23:59:59.000Z

    This document presents the results of the Westinghouse Hanford Company near-facility operational environmental monitoring for 1994 in the 100, 200/600, and 300/400 Areas of the Hanford Site, in south-central Washington State. Surveillance activities included sampling and analyses of ambient air surface water, groundwater, soil, sediments, and biota. Also, external radiation measurements and radiological surveys were taken at waste disposal sites, radiologically controlled areas, and roads. These activities were conducted to assess and control the effects of nuclear facilities and waste sites on the local environment. In addition, diffuse sources were monitored to determine compliance with Federal, State, and/or local regulations. In general, although effects from nuclear facilities are still seen on the Hanford Site and radiation levels are slightly elevated when compared to offsite locations, the differences are less than in previous years.

  2. Westinghouse Hanford Company operational environmental monitoring annual report - calendar year 1995

    SciTech Connect (OSTI)

    Schmidt, J.W., Westinghouse Hanford

    1996-07-30T23:59:59.000Z

    This document summarizes the results of the Westinghouse Hanford Company (WHC) near-facility operational environmental monitoring for 1995 in the 100, 200/600, and 300/400 Areas of the Hanford Site, in south-central Washington State. Surveillance activities included sampling and analyses of ambient air, surface water,groundwater, soil, sediments, and biota. Also, external radiation measurements and radiological surveys were taken at waste disposal sites, radiologically controlled areas, and roads. These activities were conducted to assess and control the effects of nuclear facilities and waste sites on the local environment. In addition, diffuse sources were monitored to determine compliance with Federal, State, and/or local regulations. In general, although effects from nuclear facilities can still be observed on the Hanford Site and radiation levels are slightly elevated when compared to offsite locations, the differences are less than in previous years.

  3. On the Modeling and Analysis of Jitter in ATE Using Matlab Kyung Ki Kim, Jing Huang, Yong-Bin Kim, Fabrizio Lombardi

    E-Print Network [OSTI]

    Ayers, Joseph

    On the Modeling and Analysis of Jitter in ATE Using Matlab Kyung Ki Kim, Jing Huang, Yong-Bin Kim This paper presents a new jitter component analysis method for mixed mode VLSI chip testing in Automatic Test. The Matlab simulation shows how jitter components combine and how the total jitter depends on the jitter

  4. AppAlAchiAn StAte UniverSity UndergrAdUAte BUlletin 2009-2010 The College of Fine and Applied Arts

    E-Print Network [OSTI]

    Rose, Annkatrin

    of the following eight departments: Art communication Family and consumer Sciences health, leisure and exerciseAppAlAchiAn StAte UniverSity UndergrAdUAte BUlletin 2009-2010 The College of Fine and Applied Arts The College of Fine and Applied Arts Glenda J. Treadaway, Dean Nina-Jo Moore, Associate Dean in cooperation

  5. Type B Accident Investigation Board Report of the July 2, 1997, Curium Intake by Shredder Operator at Building 513, Lawrence Livermore National Laboratory, Livermore, California

    Broader source: Energy.gov [DOE]

    This report is an independent product of the Type B Accident Investigation Board appointed by James M. Turner, Ph.D., Manager of the U.S. Department of Energy, Oakland Operations Office.

  6. Site environmental report for calendar year 2002. DOE operations at the Boeing Company, Rocketdyne Propulsion and Power

    SciTech Connect (OSTI)

    none,

    2003-09-30T23:59:59.000Z

    This Annual Site Environmental Report (ASER) for 2002 describes the environmental conditions related to work performed for the Department of Energy (DOE) at Area IV of Boeing' s Santa Susana Field Laboratory (SSFL)). In the past, the Energy Technology Engineering Center (ETEC), a government-owned, company-operated test facility, was located in Area IV. The operations at ETEC included development , fabrication , and disassembly of nuclear reactors , reactor fuel, and other radioactive materials . Other activities at ETEC involved the operation of large-scale liquid metal facilities that were used for testing liquid metal fast breeder components. All nuclear work was terminated in 1988, and, subsequently, all radiological work has been directed toward decontamination and decommissioning (D&D) of the former nuclear facilities and their associated sites . Closure of the liquid metal test facilities began in 1996. Results of the radiological monitoring program for the calendar year 2002 continue to indicate that there are no significant releases of radioactive material from Area IV of SSFL . All potential exposure pathways are sampled and/or monitored , including air , soil, surface water, groundwater , direct radiation , transfer of property ( land, structures, waste), and recycling. All radioactive w astes are processed for disposal at DOE disposal sites and/or other licensed sites approved by DOE for radioactive waste disposal . No liquid radioactive wastes are released into the environment, and no structural debris from buildings w as transferred to municipal landfills or recycled in 2002.

  7. Office of Inspector General report on audit of Department of Energy management and operating contractor available fees

    SciTech Connect (OSTI)

    NONE

    1996-05-01T23:59:59.000Z

    The Office of Procurement and Assistance Management has proposed changes to the method used to annually calculate and negotiate ``for profit`` management and operating contractor available fees. This proposal will increase contractor fees in exchange for the contractor`s purported assumption of additional risk. In 1991, the Department, through the Accountability Rule, increased contractor fees as an incentive to improve contractor performance and accountability. Despite the lack of measurable benefits of this effort, the Department is crafting a new fee policy which will, depending upon how it is executed, increase fees above the amount provided through the Accountability Rule as an incentive to the Department`s management and operating contractors. The objective of the audit was to determine whether the Department`s proposed change to the fee structure for determining management and operating contractor fees will be cost effective. This report describes the study`s approach, its findings and recommendations, management and auditor comments, and includes appendices with further data.

  8. INTERNAL REPAIR OF GAS PIPLINES SURVEY OF OPERATOR EXPERIENCE AND INDUSTRY NEEDS REPORT

    SciTech Connect (OSTI)

    Ian D. Harris

    2003-09-01T23:59:59.000Z

    A repair method that can be applied from the inside of a gas transmission pipeline (i.e., a trenchless repair) is an attractive alternative to conventional repair methods since the need to excavate the pipeline is precluded. This is particularly true for pipelines in environmentally sensitive and highly populated areas. The objectives of the project are to evaluate, develop, demonstrate, and validate internal repair methods for pipelines; develop a functional specification for an internal pipeline repair system; and prepare a recommended practice for internal repair of pipelines. The purpose of this survey is to better understand the needs and performance requirements of the natural gas transmission industry regarding internal repair. A total of fifty-six surveys were sent to pipeline operators. A total of twenty completed surveys were returned, representing a 36% response rate, which is considered very good given the fact that tailored surveys are known in the marketing industry to seldom attract more than a 10% response rate. The twenty survey responses produced the following principal conclusions: (1) Use of internal weld repair is most attractive for river crossings, under other bodies of water (e.g., lakes and swamps) in difficult soil conditions, under highways, under congested intersections, and under railway crossings. All these areas tend to be very difficult and very costly if, and where, conventional excavated repairs may be currently used. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling (HDD) when a new bore must be created to solve a leak or other problem in a water/river crossing. (3) The typical travel distances required can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). In concept, these groups require pig-based systems; despooled umbilical systems could be considered for the first two groups. For the last group a self-propelled system with an onboard self-contained power and welding system is required. (4) Pipe size range requirements range from 50.8 mm (2 in.) through 1,219.2 mm (48 in.) in diameter. The most common size range for 80% to 90% of operators surveyed is 508 mm to 762 mm (20 in. to 30 in.) diameter, with 95% using 558.8 mm (22 in.) diameter pipe.

  9. Quality Assurance Baseline Assessment Report to Los Alamos National Laboratory Analytical Chemistry Operations

    SciTech Connect (OSTI)

    Jordan, R. A.

    1998-09-01T23:59:59.000Z

    This report summarizes observations that were made during a Quality Assurance (QA) Baseline Assessment of the Nuclear Materials Technology Analytical Chemistry Group (NMT-1). The Quality and Planning personnel, for NMT-1, are spending a significant amount of time transitioning out of their roles of environmental oversight into production oversight. A team from the Idaho National Engineering and Environmental Laboratory Defense Program Environmental Surety Program performed an assessment of the current status of the QA Program. Several Los Alamos National Laboratory Analytical Chemistry procedures were reviewed, as well as Transuranic Waste Characterization Program (TWCP) QA documents. Checklists were developed and the assessment was performed according to an Implementation Work Plan, INEEL/EXT-98-00740.

  10. US Department of Energy Nevada Operations Office annual site environmental report: 1993. Volume 2: Appendices

    SciTech Connect (OSTI)

    Black, S.C.; Glines, W.M.; Townsend, Y.E.

    1994-09-01T23:59:59.000Z

    This report is comprised of appendices which support monitoring and surveillance on and around the Nevada Test Site (NTS) during 1993. Appendix A contains onsite Pu-238, gross beta, and gamma-emitting radionuclides in air. Appendix B contains onsite tritium in air. Appendix C contains onsite Pu-238, Sr-90, gross alpha and beta, gamma-emitting radionuclides, Ra-226, Ra-228 and tritium in water. A summary of 1993 results of offsite radiological monitoring is included in Appendix D. Appendix E contains radioactive noble gases in air onsite. Appendix F contains onsite thermoluminescent dosimeter data. Historical trends in onsite thermoluminescent dosimeter data are contained in Appendix G. Appendix H summarizes 1993 compliance at the DOE/NV NTS and non-NTS facilities. Appendix I summarizes the 1993 results of non radiological monitoring.

  11. The probability of intersystem LOCA: impact due to leak testing and operational changes. Technical report

    SciTech Connect (OSTI)

    Rubin, M.P.

    1980-05-01T23:59:59.000Z

    The Reactor Safety Study (WASH-1400) identified the potential intersystem LOCA in a pressurized water reactor as a significant contributor to the risk resulting from core melt. Similar scenarios are also possible in boiling water reactors. This report evaluates various pressure isolation valve configurations used in reactors to determine the probability of intersystem LOCA. It is shown that periodic leak testing of these valves can substantially reduce intersystem LOCA probability. Specific analyses of the high pressure/low pressure interfaces in the Sequoyah (PWR) and Alan B. Barton (BWR) plants show that periodic leak testing of the pressure isolation check valves will reduce the intersystem LOCA probability to below 0.000001 per year.

  12. Aquatic impacts from operation of three midwestern nuclear power stations: Cooper Nuclear Station environmental appraisal report

    SciTech Connect (OSTI)

    Brice, J.R.

    1981-10-01T23:59:59.000Z

    Cooper Nuclear Station is located on the Nebraska side of the Missouri River in Nemaha County. The station utilizes a boiling water reactor and steam turbine generator to produce 778 MW (net) of electrical power. The cooling system is a once-through design that withdraws water from, and discharges to, the Missouri River. No significant adverse impacts to the biota of the Missouri River from the Cooper Nuclear Station discharge were detected. Localized effects in the vicinity of the discharge have been observed. These include changes in the diversity and productivity of phytoplankton, periphyton, and benthic invertebrates at certain times of the year. The station appears to entrain large numbers of catostomid larvae, but this loss is not reflected in the available commercial fisheries statistics. Large numbers of gizzard shad and freshwater drum are impinged annually by Cooper Nuclear Station, but neither of these species seem to be adversely affected. Bigmouth buffalo populations could potentially suffer losses, but as was the case with the other catostomids, commercial catches of bigmouth buffalo did not seem to be affected by station operation.

  13. A waterjet mining machine for use in room and pillar mining operations. [Final report

    SciTech Connect (OSTI)

    Summers, D.A.

    1990-06-01T23:59:59.000Z

    A new mining machine is constructed for use in room and pillar mining operations. This machine uses the action of computer controlled, centrally located high pressure cutting lances to cut deep slots in a coal face. These slots stress relieve the coal ahead of the machine and outline blocks of coal. The movement forward of the machine then wedges up the lower block of coal. This wedging action is assisted by the gathering arms of the loader section of the machine, and by underlying oscillating waterjets which create a slot ahead of the loading wedge as it advances. Finally the top section of coal is brought down by the sequential advance of wedge faced roof support members, again assisted by the waterjet action from the central cutting arms. The machine is designed to overcome major disadvantages of existing room and pillar mining machines in regard to a reduction in respirable dust, the creation of an immediate roof support, and an increase in product size, with concomitant reduction in cleaning costs.

  14. Electric and Hybrid Vehicle Program, Site Operator Program. Quarterly progress report, October--December 1995 (first quarter of fiscal year 1996)

    SciTech Connect (OSTI)

    Francfort, J.E. [Lockheed Idaho Technologies Co., Idaho Falls, ID (United States); Bassett, R.R. [Sandia National Labs., Albuquerque, NM (United States); Briasco, S. [Los Angeles Dept. of Water and Power, CA (United States)] [and others

    1996-03-01T23:59:59.000Z

    This is the Site Operator Program quarterly report for USDOE electric and hybrid vehicle research. Its mission now includes the three major activity categories of advancement of electric vehicle (EV) technologies, development of infrastructure elements needed to support significant EV use and increasing public awareness and acceptance of EVs. The 11 Site Operator Program participants, their geographic locations, and the principal thrusts of their efforts are identified. The EV inventories of the site operators totals about 250 vehicles. The individual fleets are summarized.

  15. Real-Time Traffic Information for Emergency Evacuation Operations: Phase A Final Report

    SciTech Connect (OSTI)

    Franzese, Oscar [ORNL; Zhang, Li [Mississippi State University (MSU); Mahmoud, Anas M. [Mississippi State University (MSU); Lascurain, Mary Beth [ORNL; Wen, Yi [Mississippi State University (MSU)

    2010-05-01T23:59:59.000Z

    There are many instances in which it is possible to plan ahead for an emergency evacuation (e.g., an explosion at a chemical processing facility). For those cases, if an accident (or an attack) were to happen, then the best evacuation plan for the prevailing network and weather conditions would be deployed. In other cases (e.g., the derailment of a train transporting hazardous materials), there may not be any previously developed plan to be implemented and decisions must be made ad-hoc on how to proceed with an emergency evacuation. In both situations, the availability of real-time traffic information plays a critical role in the management of the evacuation operations. To improve public safety during a vehicular emergency evacuation it is necessary to detect losses of road capacity (due to incidents, for example) as early as possible. Once these bottlenecks are identified, re-routing strategies must be determined in real-time and deployed in the field to help dissipate the congestion and increase the efficiency of the evacuation. Due to cost constraints, only large urban areas have traffic sensor deployments that permit access to some sort of real-time traffic information; any evacuation taking place in any other areas of the country would have to proceed without real-time traffic information. The latter was the focus of this SERRI/DHS (Southeast Region Research Initiative/Department of Homeland Security) sponsored project. That is, the main objective on the project was to improve the operations during a vehicular emergency evacuation anywhere by using newly developed real-time traffic-information-gathering technologies to assess traffic conditions and therefore to potentially detect incidents on the main evacuation routes. Phase A of the project consisted in the development and testing of a prototype system composed of sensors that are engineered in such a way that they can be rapidly deployed in the field where and when they are needed. Each one of these sensors is also equipped with their own power supply and a GPS (Global Positioning System) device to auto-determine its spatial location on the transportation network under surveillance. The system is capable of assessing traffic parameters by identifying and re-identifying vehicles in the traffic stream as those vehicles pass over the sensors. The system of sensors transmits, through wireless communication, real-time traffic information (travel time and other parameters) to a command and control center via an NTCIP (National Transportation Communication for ITS Protocol) -compatible interface. As an alternative, an existing NTCIP-compatible system accepts the real-time traffic information mentioned and broadcasts the traffic information to emergency managers, the media and the public via the existing channels. A series of tests, both in a controlled environment and on the field, were conducted to study the feasibility of rapidly deploying the system of traffic sensors and to assess its ability to provide real-time traffic information during an emergency evacuation. The results of these tests indicated that the prototype sensors are reliable and accurate for the type of application that is the focus of this project.

  16. Report on audit of the Richland Operations Office Site Characterization Program

    SciTech Connect (OSTI)

    NONE

    1995-03-01T23:59:59.000Z

    In 1989 the Secretary of Energy changed the mission of the Richland Operations Office (ROO) from supporting weapons production to environmental restoration and waste management. Through the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement), ROO was required to survey Hanford for contaminants, analyze samples, and determine the most cost-effective method to clean up the waste identified. The objective of this audit was to determine if the Department of Energy (DOE) and ROO had evaluated alternatives to accomplish certain site characterization activities in a cost-effective manner. This audit showed that neither the DOE nor ROO evaluated alternatives to ensure that two site characterization activities were accomplished in a cost-effective manner. First, DOE accelerated the core sampling program for high-level radioactive waste tanks from 6 to 3 years. DOE made this decision in response to a Defense Nuclear Facilities Safety Board (Safety Board) recommendation without first determining if the method chosen (core sampling) was the most efficient and economical method to satisfy the Safety Board`s concerns. This 3-year acceleration would cost over $71 million with little increase in benefits. Second, ROO agreed to a Tri-Party Agreement Amendment to require low-level waste samples be analyzed within 25 miles of Hanford. ROO estimated that the 25-mile restriction will require an additional $46 million over an 8-year period. It is recommended that DOE (1) notify the appropriate parties that characterization of the high-level radioactive waste tanks will be completed in the most cost-effective method to achieve program objectives, and (2) negotiate to remove the requirement to perform 80% of low-level waste sample analyses within 25 miles of Hanford. It is also recommended that management perform economic analyses of alternatives before making decisions as to how program objectives will be accomplished.

  17. US Department of Energy Nevada Operations Office annual site environmental report: 1993. Volume 1

    SciTech Connect (OSTI)

    Black, S.C.; Glines, W.M.; Townsend, Y.E. [eds.

    1994-09-01T23:59:59.000Z

    Monitoring and surveillance on and around the Nevada Test Site (NTS) by DOE contractors and NTS user organizations during 1993 indicated that operations on the NTS were conducted in compliance with applicable federal and DOE guidelines, i.e., the dose the maximally exposed offsite individual could have received was less than 0.04 percent of the 10 mrem per year guide for air exposure. No nuclear tests were conducted due to the moratorium. All discharges of radioactive liquids remained onsite in containment ponds, and there was no indication of potential migration of radioactivity to the offsite area through groundwater. Surveillance around the NTS indicated that airborne radioactivity from diffusion, evaporation of effluents, or resuspension was not detectable offsite, and no measurable net exposure to members of the offsite population was detected through the offsite dosimetry program. Using the CAP88-PC model and NTS radionuclide emissions data, the calculated effective dose equivalent to the maximally exposed individual offsite would have been 0.004 mrem. Any person receiving this dose would also have received 97 mrem from natural background radiation. There were no nonradiological releases to the offsite area. Hazardous wastes were shipped offsite to approved disposal facilities. Compliance with the various regulations stemming from the National Environmental Policy Act is being achieved and, where mandated, permits for air and water discharges and waste management have been obtained from the appropriate agencies. Support facilities at off-NTS locations compiled with the requirements of air quality permits and state or local wastewater discharge and hazardous waste permits.

  18. DIII-D research operations. Annual report, October 1, 1992--September 30, 1993

    SciTech Connect (OSTI)

    La Haye, R.J. [ed.

    1994-05-01T23:59:59.000Z

    The DIII-D tokamak research program is carried out by General Atomics (GA) for the U.S. Department of Energy (DOE). The DIII-D is the most flexible tokamak in the world. The primary goal of the DIII-D tokamak research program is to provide data to develop a conceptual physics blueprint for a commercially attractive electrical demonstration plant (DEMO) that would open a path to fusion power commercialization. In doing so, the DIII-D program provides physics and technology R&D outputs to aid the Tokamak Physics Experiment (TPX) and the International Thermonuclear Experimental Reactor (ITER). Specific DIII-D objectives include the steady-state sustainment of plasma current as well as demonstrating techniques for microwave heating, divertor heat removal, fuel exhaust and tokamak plasma control. The DIII-D program is addressing these objectives in an integrated fashion with high beta and with good confinement. The long-range plan is organized into two major thrusts; the development of an advanced divertor and the development of advanced tokamak concepts. These two thrusts have a common goal: an improved DEMO reactor with lower cost and smaller size than the present DEMO which can be extrapolated from the conventional ITER operational scenario. In order to prepare for the long-range program, in FY93 the DIII-D research program concentrated on three major areas: Divertor and Boundary Physics, Advanced Tokamak Studies, and Tokamak Physics. The major goals of the Divertor and Boundary Physics studies are the control of impurities, efficient heat removal and understanding the strong role that the edge plasma plays in the global energy confinement of the plasma. The advanced tokamak studies initiated the investigation into new techniques for improving energy confinement, controlling particle fueling and increasing plasma beta. The major goal of the Tokamak Physics Studies is the understanding of energy and particle transport in a reactor relevant plasma.

  19. Final report: Task 4a.2 20% wind scenario assessment of electric grid operational features

    SciTech Connect (OSTI)

    Toole, Gasper L. [Los Alamos National Laboratory

    2009-01-01T23:59:59.000Z

    Wind integration modeling in electricity generation capacity expansion models is important in that these models are often used to inform political or managerial decisions. Poor representation of wind technology leads to under-estimation of wind's contribution to future energy scenarios which may hamper growth of the industry. The NREL's Wind Energy Deployment System (WinDS) model provides the most detailed representation of geographically disperse renewable resources and the optimization of transmission expansion to access these resources. Because WinDS was selected as the primary modeling tool for the 20% Wind Energy by 2030 study, it is the ideal tool for supplemental studies of the transmission expansion results. However, as the wind industry grows and knowledge related to the wind resource and integration of wind energy into the electric system develops, the WinDS model must be continually improved through additional data and innovative algorithms to capture the primary effects of variable wind generation. The detailed representation of wind technology in the WinDS model can be used to provide improvements to the simplified representation of wind technology in other capacity expansion models. This task did not employ the WinDS model, but builds from it and its results. Task 4a.2 provides an assessment of the electric grid operational features of the 20% Wind scenario and was conducted using power flow models accepted by the utility industry. Tasks 2 provides information regarding the physical flow of electricity on the electric grid which is a critical aspect of infrastructure expansion scenarios. Expanding transmission infrastructure to access remote wind resource in a physically realizable way is essential to achieving 20% wind energy by 2030.

  20. Umatilla River Fish Passage Operations Project : Annual Progress Report October 2007 - September 2008.

    SciTech Connect (OSTI)

    Bronson, James P.; Loffink, Ken; Duke, Bill

    2008-12-31T23:59:59.000Z

    Threemile Falls Dam (Threemile Dam), located near the town of Umatilla, is the major collection and counting point for adult salmonids returning to the Umatilla River. Returning salmon and steelhead were enumerated at Threemile Dam from June 7, 2007 to August 11, 2008. A total of 3,133 summer steelhead (Oncorhynchus mykiss); 1,487 adult, 1,067 jack, and 999 subjack fall Chinook (O. tshawytscha); 5,140 adult and 150 jack coho (O. kisutch); and 2,009 adult, 517 jack, and 128 subjack spring Chinook (O. tshawytscha) were counted. All fish were enumerated at the east bank facility. Of the fish counted, 1,442 summer steelhead and 88 adult and 84 jack spring Chinook were hauled upstream from Threemile Dam. There were 1,497 summer steelhead; 609 adult, 1,018 jack and 979 subjack fall Chinook; 5,036 adult and 144 jack coho; and 1,117 adult, 386 jack and 125 subjack spring Chinook either released at, or allowed to volitionally migrate past, Threemile Dam. Also, 110 summer steelhead; 878 adult and 43 jack fall Chinook; and 560 adult and 28 jack spring Chinook were collected as broodstock for the Umatilla River hatchery program. In addition, there were 241 adult and 15 jack spring Chinook collected at Threemile Dam for outplanting in the South Fork Walla Walla River and Mill Cr, a tributary of the mainstem Walla Walla River. The Westland Canal juvenile facility (Westland), located near the town of Echo at river mile (RM) 27, is the major collection point for out-migrating juvenile salmonids and steelhead kelts. The canal was open for 158 days between February 11, 2008 and July 18, 2008. During that period, fish were bypassed back to the river 150 days and were trapped 6 days. There were also 2 days when fish were directed into and held in the canal forebay between the time the bypass was closed and the trap opened. An estimated 64 pounds of fish were transported from the Westland trapping facility. Approximately 25.8% of the fish transported were salmonids. In addition, one adult Pacific lamprey was trapped and released above the Westland ladder this year. The Threemile Dam west bank juvenile bypass was opened on March 11, 2008 in conjunction with water deliveries and continued through the summer. West Extension Irrigation District (WEID) discontinued diverting live flow on June 24, 2008 but the bypass remained open throughout the project year. The juvenile trap was not operated this project year.

  1. Umatilla River Fish Passage Operations Program, 2003-2004 Annual Report.

    SciTech Connect (OSTI)

    Bronson, James P. (Confederated Tribes of the Umatilla Indian Reservation, Department of Natural Resources, Pendleton, OR); Duke, Bill B. (Oregon Department of Fish and Wildlife, Pendleton, OR)

    2005-08-01T23:59:59.000Z

    Threemile Falls Dam (Threemile Dam), located near the town of Umatilla, is the major collection and counting point for adult salmonids returning to the Umatilla River. Returning salmon and steelhead were enumerated at Threemile Dam from August 19, 2003 to July 8, 2004. A total of 3,388 summer steelhead (Oncorhynchus mykiss); 1,482 adult, 638 jack, and 2,150 subjack fall chinook (O. tshawytscha); 8,319 adult and 667 jack coho (O. kisutch); and 2,965 adult and 270 jack spring chinook (O. tshawytscha) were counted. All fish were enumerated at the east bank facility. Of the fish counted, 34 summer steelhead and 31 adult and 9 jack spring chinook were hauled upstream from Threemile Dam. There were 3,166 summer steelhead; 1,076 adult, 554 jack and 2,026 subjack fall chinook; 8,213 adult and 647 jack coho; and 2,152 adult and 174 jack spring chinook either released at, or allowed to volitionally migrate past, Threemile Dam. Also, 121 summer steelhead; 388 adult and 19 jack fall chinook; and 561 adult and 29 jack spring chinook were collected for brood. In addition, 239 spring chinook were collected for the outplanting efforts in the Walla Walla Basin. There were also 25 pair hatchery steelhead adults collected for the progeny maker study. The Westland Canal juvenile facility (Westland), located near the town of Echo at rivermile (RM) 27, is the major collection point for outmigrating juvenile salmonids and steelhead kelts. The canal was open for 184 days between January 12 and July 6, 2004. During that period, fish were bypassed back to the river 173 days and were trapped 10 days. An estimated 44 pounds of juvenile fish were transported from Westland to the Umatilla River boat ramp (RM 0.5). Approximately 84% of the juveniles transported were salmonids. No steelhead kelts were hauled from Westland this year. The Threemile Dam west bank juvenile bypass was opened on February 10, 2004 for outmigration sampling and continued until July 7, 2004 when sampling was discontinued. The juvenile bypass ran at the 5 cfs level until the initiation of Phase I on August 15, 2004. The juvenile trap was operated by the Oregon Department of Fish and Wildlife (ODFW) under the Evaluation of Umatilla Juvenile Salmonid Outmigration Project.

  2. OPERATOR'S MANUAL IMPORTANT NOTES

    E-Print Network [OSTI]

    Hart, Gus

    . An ISO 9001 Company. ©2010, KEPCO, INC. P/N 228-1724 REV 1 ATE 1/2 RACK POWER SUPPLY AUTOMATIC TEST

  3. A Complexity Science-Based Framework for Global Joint Operations Analysis to Support Force Projection: LDRD Final Report.

    SciTech Connect (OSTI)

    Lawton, Craig R.

    2015-01-01T23:59:59.000Z

    The military is undergoing a significant transformation as it modernizes for the information age and adapts to address an emerging asymmetric threat beyond traditional cold war era adversaries. Techniques such as traditional large-scale, joint services war gaming analysis are no longer adequate to support program evaluation activities and mission planning analysis at the enterprise level because the operating environment is evolving too quickly. New analytical capabilities are necessary to address modernization of the Department of Defense (DoD) enterprise. This presents significant opportunity to Sandia in supporting the nation at this transformational enterprise scale. Although Sandia has significant experience with engineering system of systems (SoS) and Complex Adaptive System of Systems (CASoS), significant fundamental research is required to develop modeling, simulation and analysis capabilities at the enterprise scale. This report documents an enterprise modeling framework which will enable senior level decision makers to better understand their enterprise and required future investments.

  4. ECOSystem: Managing Energy as a First Class Operating System Heng Zeng, Xiaobo Fan, Carla Ellis, Alvin Lebeck, and Amin Vahdat

    E-Print Network [OSTI]

    Lebeck, Alvin R.

    ECOSystem: Managing Energy as a First Class Operating System Resource Heng Zeng, Xiaobo Fan focus in this paper is to investigate what role the oper- ating system can play in improving energy as a significant layer in the design of energy efficient computing systems [8]. It is now a widely held view

  5. Report on the oversight assessment of the operational readiness review of the Replacement Tritium Facility at Savannah River Site

    SciTech Connect (OSTI)

    Lee, B.T.

    1993-03-01T23:59:59.000Z

    This report presents the results of an oversight assessment (OA) conducted by the US Department of Energy's (DOE) Office of Environment, Safety and Health (EH) of operational readiness review (ORR) activities for the Replacement Tritium Facility (RTF) located at Savannah River Site (SRS). The EH OA of this facility took place concurrently with an ORR conducted by the DOE Office of Defense Programs (DP). The DP ORR was conducted from January 19 through February 5, 1993. The EH OA was performed in accordance with the protocol and procedures specified in EH Program for Oversight Assessment of Operational Readiness Evaluations for Startups and Restarts,'' dated September 15, 1992. The EH OA Team evaluated the DP ORR to determine whether it was thorough and demonstrated sufficient inquisitiveness to verify that the implementation of programs and procedures adequately ensures the protection of worker safety and health. The EH OA Team performed its evaluation of the DP ORR in the following technical areas: occupational safety, industrial hygiene, and respiratory protection; fire protection; and chemical safety. In the areas of fire protection and chemical safety, the EH OA Team conducted independent vertical-slice reviews to confirm DP ORR results. Within each technical area, the EH OA Team reviewed the DP ORR Plan, including the Criteria Review and Approach Documents (CRADs); the qualifications of individual DP ORR team members; the performance of planned DP ORR activities; and the results of the DP ORR.

  6. Recovery Efficiency Test Project: Phase 1, Activity report. Volume 1: Site selection, drill plan preparation, drilling, logging, and coring operations

    SciTech Connect (OSTI)

    Overbey, W.K. Jr.; Carden, R.S.; Kirr, J.N.

    1987-04-01T23:59:59.000Z

    The recovery Efficiency Test well project addressed a number of technical issues. The primary objective was to determine the increased efficiency gas recovery of a long horizontal wellbore over that of a vertical wellbore and, more specifically, what improvements can be expected from inducing multiple hydraulic fractures from such a wellbore. BDM corporation located, planned, and drilled a long radius turn horizontal well in the Devonian shale Lower Huron section in Wayne County, West Virginia, demonstrating that state-of-the-art technology is capable of drilling such wells. BDM successfully tested drilling, coring, and logging in a horizontal well using air as the circulating medium; conducted reservoir modeling studies to protect flow rates and reserves in advance of drilling operations; observed two phase flow conditions in the wellbore not observed previously; cored a fracture zone which produced gas; observed that fractures in the core and the wellbore were not systematically spaced (varied from 5 to 68 feet in different parts of the wellbore); observed that highest gas show rates reported by the mud logger corresponded to zone with lowest fracture spacing (five feet) or high fracture frequency. Four and one-half inch casting was successfully installed in the borehole and was equipped to isolate the horizontal section into eight (8) zones for future testing and stimulation operations. 6 refs., 48 figs., 10 tabs.

  7. educAtionAl leAderShip certificAte of AdvAnced StudieS (cAS)

    E-Print Network [OSTI]

    Suzuki, Masatsugu

    educAtionAl leAderShip certificAte of AdvAnced StudieS (cAS) School of Education tAke the le New York state administrative leadership certifications our cAS progrAm prepAreS leAderS for A wide v for summer sessions) fAll educ 606: Curriculum Leadership (required) educ 675: Planning and Policy

  8. Electric and Hybrid Vehicle Program, Site Operator Program. Quarterly progress report for July through September 1994 (Fourth quarter of fiscal year 1994)

    SciTech Connect (OSTI)

    Kiser, D.M.; Brown, H.L.

    1995-03-01T23:59:59.000Z

    The Site Operator Program was initially established by the Department of Energy (DOE) to incorporate the electric vehicle activities dictated by the Electric and Hybrid Vehicle Research, Development and Demonstration Act of 1976. In the ensuing years, the Program has evolved in response to new legislation and interests. The Program currently includes twelve sites located in diverse geographic, metrologic, and metropolitan areas across the US. Information is shared reciprocally with a thirteenth site, not under Program contract. The vehicles are operator-owned, except for two Griffon vans. The Mission Statement of the Site Operator Program includes three major activities: advancement of electric vehicle technologies; development of infrastructure elements necessary to support significant electric vehicle use; and increasing the awareness and acceptance of electric vehicles (EVs) by the public. The current participants in the Site Operator Program are shown. The ultimate thrust of program activities varies among sites, reflecting not only the Operator`s business interests but also geographic and climate-related operating conditions. This fourth quarter report (FY-94) includes a summary of activities from the previous three quarters. The report section sequence has been revised to provide a more easily seen program overview, and specific operator activities are now found in Appendix A.

  9. FOR IMMEDI ATE RELEASE

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Averna (859) 219-4010 Loretta.averna@lex.doe.gov Kids Go 'Green' at Department of EnergyCitizens' Advi sory Board Eco Fair By Joe Walk er LATA Kentuck y Sixth-graders came...

  10. Waste Area Group 10, Operable Unit 10-08, Remedial Investigation/Feasibility Study Annual Status Report for Fiscal Year 2006

    SciTech Connect (OSTI)

    R. P. Wells

    2007-05-09T23:59:59.000Z

    This report provides a status of the progress made in Fiscal Year 2006 on tasks identified in the Waste Area Group 10, Operable Unit 10-08, Remedial Investigation/Feasibility Study Work Plan. Major accomplishments include: (1) groundwater sampling and review of the groundwater monitoring data, (2) installation of a Sitewide groundwater-level monitoring network, (3) update of the Groundwater Monitoring and Field Sampling Plan of Operable Unit 10-08, (4) re-evaluation of the risk at Site TSF-08, (5) progress on the Operable Unit 10-08 Sitewide Groundwater Model.

  11. Waste Area Group 10, Operable Unit 10-08, Annual Monitoring Status Report for Fiscal Year 2009

    SciTech Connect (OSTI)

    Howard Forsythe

    2010-02-04T23:59:59.000Z

    This report documents the status of Fiscal Year 2009 groundwater monitoring performed in Waste Area Group 10 at the U.S. Department of Energy Idaho National Laboratory Site, as identified in the Groundwater Monitoring and Field Sampling Plan for Operable Unit 10-08. Twelve of the fourteen required wells were sampled, and all ten required intervals from the Westbay wells were sampled. Two wells were not sampled because they were in the process of being converted into multiple-sample-interval Westbay wells by the U.S. Geological Survey. Groundwater samples were analyzed for volatile organic compounds identified on the Contract Laboratory Program target analyte list as well as metals (filtered), anions, and radionuclides (i.e., I-129, tritium, Tc-99, gross alpha, gross beta, and Sr-90). No contaminant exceeded maximum contaminant levels in wells along the southern boundary of the Idaho National Laboratory Site or in guard wells. Iron was above its secondary maximum contaminant level of 300 ug/L in one well. The cause of the elevated iron concentration is uncertain. Lead was detected just below its action level. However, the zinc concentration was also elevated in these wells, and the source of the lead is probably galvanized riser pipe in the wells. Once the galvanized pipe is replaced, both lead and zinc concentrations should decline, as has been observed at other Waste Area Group 10 wells.

  12. Evaluation of potential severe accidents during low power and shutdown operations at Grand Gulf, Unit 1: Evaluation of severe accident risks for plant operational state 5 during a refueling outage. Main report and appendices, Volume 6, Part 1

    SciTech Connect (OSTI)

    Brown, T.D.; Kmetyk, L.N.; Whitehead, D.; Miller, L. [Sandia National Labs., Albuquerque, NM (United States); Forester, J. [Science Applications International Corp., Albuquerque, NM (United States); Johnson, J. [GRAM, Inc., Albuquerque, NM (United States)

    1995-03-01T23:59:59.000Z

    Traditionally, probabilistic risk assessments (PRAS) of severe accidents in nuclear power plants have considered initiating events potentially occurring only during full power operation. Recent studies and operational experience have, however, implied that accidents during low power and shutdown could be significant contributors to risk. In response to this concern, in 1989 the Nuclear Regulatory Commission (NRC) initiated an extensive program to carefully examine the potential risks during low power and shutdown operations. Two plants, Surry (pressurized water reactor) and Grand Gulf (boiling water reactor), were selected as the plants to be studied. The program consists of two parallel projects being performed by Brookhaven National Laboratory (Surry) and Sandia National Laboratories (Grand Gulf). The program objectives include assessing the risks of severe accidents initiated during plant operational states other than full power operation and comparing the estimated risks with the risk associated with accidents initiated during full power operation as assessed in NUREG-1150. The scope of the program is that of a Level-3 PRA. The subject of this report is the PRA of the Grand Gulf Nuclear Station, Unit 1. The Grand Gulf plant utilizes a 3833 MWt BUR-6 boiling water reactor housed in a Mark III containment. The Grand Gulf plant is located near Port Gibson, Mississippi. The regime of shutdown analyzed in this study was plant operational state (POS) 5 during a refueling outage, which is approximately Cold Shutdown as defined by Grand Gulf Technical Specifications. The entire PRA of POS 5 is documented in a multi-volume NUREG report (NUREG/CR-6143). The internal events accident sequence analysis (Level 1) is documented in Volume 2. The Level 1 internal fire and internal flood analyses are documented in Vols 3 and 4, respectively.

  13. Reports

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Reports Reports Individual Permit reports are prepared annually to facilitate public review of activities for the previous year. Contact Environmental Communication & Public...

  14. Type B Accident Investigation Board Report of the Plutonium Intake between August 4, 1996, and February 10, 1997, by a Crane Operator at the Savannah River Site F-Canyon

    Broader source: Energy.gov [DOE]

    This report is an independent product of an accident investigation board appointed by Dr. Mario P. Fiori, Manager, Savannah River Operations Office, U.S. Department of Energy.

  15. Hardware Development of a Laboratory-Scale Microgrid Phase 1--Single Inverter in Island Mode Operation: Base Year Report, December 2000 -- November 2001

    SciTech Connect (OSTI)

    Venkataramanan, G.; Illindala, M. S.; Houle, C.; Lasseter, R. H.

    2002-11-01T23:59:59.000Z

    This report summarizes the activities of the first year of a three-year project to develop control software for micro-source distributed generation systems. The focus of this phase was on internal energy storage requirements, the modification of an off-the-shelf motor drive system inverter to supply utility-grade ac power, and a single inverter system operating in island mode. The report provides a methodology for determining battery energy storage requirements, a method for converting a motor drive inverter into a utility-grade inverter, and typical characteristics and test results of using such an inverter in a complex load environment.

  16. Electric and hybrid vehicle program: Site operator program. Quarterly progress report, April--June, 1994 (3rd quarter of FY-1994)

    SciTech Connect (OSTI)

    Kiser, D.M.; Brown, H.L.

    1994-10-01T23:59:59.000Z

    The DOE Site Operator Program was initially established to meet the requirements of the Electric and Hybrid Vehicle Research, Development, and Demonstration Act of 1976. The Program has since evolved in response to new legislation and interests. Its mission now includes three major activity categories; advancement of Electric Vehicle (EV) technologies, development of infrastructure elements needed to support significant EV use, and increasing public awareness and acceptance of EVs. The 13 Program participants, their geographic locations, and the principal thrusts of their efforts are identified. The EV inventories of each participant are summarized. This third quarter report (FY-94) will include a summary of activities from the previous three quarters. The report section sequence has been revised to provide a more easily seen program overview, and specific operator activities are now included.

  17. Advanced dexterous manipulation for IED defeat : report on the feasibility of using the ShadowHand for remote operations.

    SciTech Connect (OSTI)

    Anderson, Robert J.

    2011-01-01T23:59:59.000Z

    Improvised Explosive Device (IED) defeat (IEDD) operations can involve intricate operations that exceed the current capabilities of the grippers on board current bombsquad robots. The Shadow Dexterous Hand from the Shadow Robot Company or 'ShadowHand' for short (www.shadowrobot.com) is the first commercially available robot hand that realistically replicates the motion, degrees-of-freedom and dimensions of a human hand (Figure 1). In this study we evaluate the potential for the ShadowHand to perform potential IED defeat tasks on a mobile platform.

  18. UBC Social Ecological Economic Development Studies (SEEDS) Student Report Integrating Vermicomposting into AMS SUB Operations -Phase 3 -Compiled presentations

    E-Print Network [OSTI]

    Vermicomposting into AMS SUB Operations - Phase 3 - Compiled presentations GRS 497B November 04, 2014 634 1679 TO CHANGE THE WORLD social equity ecological health economic prosperity #12;#12;OBJECTIVE Explore material, production of humus ACTS AS: nutrient recycler, soil conditioner RESULTS IN: IMPROVED SOIL

  19. Solid Waste Operations Complex W-113, Detail Design Report (Title II). Volume 5: Design validation assessments and lists

    SciTech Connect (OSTI)

    NONE

    1995-09-01T23:59:59.000Z

    The Solid Waste Retrieval Facility--Phase 1 (Project W113) will provide the infrastructure and the facility required to retrieve from Trench 04, Burial ground 4C, contact handled (CH) drums and boxes at a rate that supports all retrieved TRU waste batching, treatment, storage, and disposal plans. This includes (1) operations related equipment and facilities, viz., a weather enclosure for the trench, retrieval equipment, weighing, venting, obtaining gas samples, overpacking, NDE, NDA, shipment of waste and (2) operations support related facilities, viz., a general office building, a retrieval staff change facility, and infrastructure upgrades such as supply and routing of water, sewer, electrical power, fire protection, roads, and telecommunication. Title I design for the operations related equipment and facilities was performed by Raytheon/BNFL, and that for the operations support related facilities including infrastructure upgrade was performed by KEH. These two scopes were combined into an integrated W113 Title II scope that was performed by Raytheon/BNFL. The following Code Evaluation analyzes the applicable sections of the National Fire Protection Association (NFPA) 101, Life Safety Code, 1994 Edition and the 1994 Edition of the Uniform Building Code (UBC) to the W113 Trench Enclosure. A Building Code Analysis generally establishes four primary design criteria: occupancy classification; separation requirements; egress requirements; and construction type. The UBC establishes requirements for all criteria. This analysis is limited to the Trench Enclosure Building. The General Office Building and the Retrieval Staff Change Building is not within the scope of this analysis.

  20. Reservoir Operation in Texas

    E-Print Network [OSTI]

    Wurbs, Ralph A.

    management of the surface water resources of the various river basins of the state. The operation of these essential water control facilities is examined in this report. Reservoir operation is viewed here from the perspective of deciding how much water...

  1. U.S. Department of Energy electric and hybrid vehicle Site Operator Program at Platte River Power Authority. Final report, July 3, 1991--August 31, 1996

    SciTech Connect (OSTI)

    Emmert, R.A.

    1996-12-31T23:59:59.000Z

    The Platte River Power Authority (Platte River) is a political subdivision of the state of Colorado, owned by the four municipalities of Fort Collins, Loveland, Longmont and Estes Park, Colorado. Platte River is a non-profit, publicly owned, joint-action agency formed to construct, operate and maintain generating plants, transmission systems and related facilities for the purpose of delivering to the four municipalities electric energy for distribution and resale. Platte River, as a participant in the US Department of Energy (DOE) Site Operator Program, worked to accomplish the Site Operator Program goals and objectives to field test and evaluate electric and electric-hybrid vehicles and electric vehicle systems in a real world application/environment. This report presents results of Platte River`s program (Program) during the five-years Platte River participated in the DOE Site Operator Program. Platte River participated in DOE Site Operator Program from July 3, 1991 through August 31, 1996. During its Program, Platte River conducted vehicle tests and evaluations, and electric vehicle demonstrations in the Front Range region of Northern Colorado. Platte River also investigated electric vehicle infrastructure issues and tested infrastructure components. Platte River`s Program objectives were as follows: evaluate the year round performance, operational costs, reliability, and life cycle costs of electric vehicles in the Front Range region of Northern Colorado; evaluate an electric vehicle`s usability and acceptability as a pool vehicle; test any design improvements or technological improvements on a component level that may be made available to PRPA and which can be retrofit into vehicles; and develop, test and evaluate, and demonstrate components to be used in charging electric vehicles.

  2. R&D on an Ultra-Thin Composite Membrane for High-Temperature Operation in PEMFC. Final Report

    SciTech Connect (OSTI)

    Yuh, C.-Y.

    2003-10-06T23:59:59.000Z

    FuelCell Energy developed a novel high-temperature proton exchange membrane for PEM fuel cells for building applications. The laboratory PEM fuel cell successfully operated at 100-400{supdegree}C and low relative humidity to improve CO tolerance, mitigate water and thermal management challenges, and reduce membrane cost. The developed high-temperature membrane has successfully completed 500h 120C endurance testing.

  3. Testing fluidized bed incinerators for energy-efficient operation for the Southtowns Sewage Treatment Agency. Final report

    SciTech Connect (OSTI)

    NONE

    1996-01-01T23:59:59.000Z

    Two methods for improving the energy efficiency of fluidized bed sludge incinerators were evaluated. The first method used paper pulp and polymer as conditioning agents for municipal sludge instead of lime and ferric chloride. Automatic control of the incinerator was the second method evaluated for energy savings. To evaluate the use of paper pulp and polymer as conditioning agents, varying quantities of paper pulp were added to the liquid sludge to determine the optimal sludge-to-paper pulp ratio. The effect of the paper pulp and polymer-conditioned sludge on plant operations also was evaluated. When compared to sludge conditioned with lime and ferric chloride, the paper pulp and polymer-conditioned sludge had similar cake release and feed characteristics, higher BTU values for the dry sludge solids, required less auxiliary fuel for incineration, and generated less ash for disposal. The paper pulp and polymer did not have any appreciable negative effects on the operation of the wastewater treatment plant. It was estimated that processing and incinerating the sludge conditioned with paper pulp and polymer resulted in a cost savings of up to $91.73 per dry ton of activated sludge solids. To evaluate the effect of automatic control, all the incinerator operating parameters including air flow rates, fuel oil feed rates, and sludge feed rates, were automatically monitored and controlled to minimize auxiliary fuel oil use and to keep the incinerator running at optimal conditions. Although effective, the estimated cost savings for automatic control of the incinerator were small.

  4. Electric and hybrid vehicle program, site operator program quarterly progress report for April through June 1996 (third quarter of fiscal year 1996)

    SciTech Connect (OSTI)

    Francfort, J. [Lockheed Idaho Technologies Co., Idaho Falls, ID (United States); Bassett, R.R. [Sandia National Labs., Albuquerque, NM (United States); Briasco, S. [Los Angeles Dept. of Water and Power, CA (United States)] [and others

    1997-01-01T23:59:59.000Z

    The US Department of Energy (DOE) Site Operator Program was initially established to meet the requirements of the Electric and Hybrid Vehicle Research, Development, and Demonstration Act of 1976. The Program has since evolved in response to new legislation and interests. The goals of the Site Operator Program include the field evaluation of electric vehicles (EVs) in real-world applications and environments; the advancement of electric vehicle technologies; the development of infrastructure elements necessary to support significant electric vehicle use; and increasing the awareness and acceptance of EVs by the public. The Site Operator Program currently consists of eleven participants under contract and two other organizations that have data-sharing agreements with the Program (Table ES-1). Several national organizations have joined DOE to further the introduction and awareness of electric vehicles, including: (1) EVAmerica (a utility program) and DOE conduct performance and evaluation tests to support market development for electric vehicles; and (2) DOE, the Department of Transportation, the Electric Transportation Coalition, and the Electric Vehicle Association of the Americas are conducting a series of workshops to encourage urban groups in Clean Cities (a DOE program) to initiate the policies and infrastructure development necessary to support large-scale demonstrations, and ultimately the mass market use, of electric vehicles. The current focus of the Program is the collection and dissemination of EV operations and performance data to aid in the evaluation of real-world EV use. This report contains several sections with vehicle evaluation as a focus.

  5. Operating experience feedback report: Reliability of safety-related steam turbine-driven standby pumps. Commercial power reactors, Volume 10

    SciTech Connect (OSTI)

    Boardman, J.R.

    1994-10-01T23:59:59.000Z

    This report documents a detailed analysis of failure initiators, causes and design features for steam turbine assemblies (turbines with their related components, such as governors and valves) which are used as drivers for standby pumps in the auxiliary feedwater systems of US commercial pressurized water reactor plants, and in the high pressure coolant injection and reactor core isolation cooling systems of US commercial boiling water reactor plants. These standby pumps provide a redundant source of water to remove reactor core heat as specified in individual plant safety analysis reports. The period of review for this report was from January 1974 through December 1990 for licensee event reports (LERS) and January 1985 through December 1990 for Nuclear Plant Reliability Data System (NPRDS) failure data. This study confirmed the continuing validity of conclusions of earlier studies by the US Nuclear Regulatory Commission and by the US nuclear industry that the most significant factors in failures of turbine-driven standby pumps have been the failures of the turbine-drivers and their controls. Inadequate maintenance and the use of inappropriate vendor technical information were identified as significant factors which caused recurring failures.

  6. Design, development and validation of a training system for roof bolt equipment operators. Open file report, 21 September 1978-10 April 1982

    SciTech Connect (OSTI)

    Hinton, W.M. Jr.; Menzer, G.W.; Reilly, R.E.; Baker, R.M.

    1982-04-10T23:59:59.000Z

    This report describes the approach, procedures, and results of a program to develop training materials for roof bolter operators. The objective of the program was to design and produce a training sequence which would prepare roof bolter trainees for job performance. Data were collected and analyzed using the general procedures of Instructional Systems Development (ISD). Input data came from previous roof bolter training analysis program. These data were expanded and structured through a series of ISD steps: objectives hierarchies, media selection, syllabus, lesson specifications, and training materials development. The resulting program consisted of an ordered sequence of 15 lessons. The media mix for the 15 lessons included lectures, slide-tape lessons, and hands-on instruction using operational roof bolters. Contents of all lessons were reviewed and approved by the Bureau of Mines.

  7. Post-Closure Monitoring Report for Corrective Action Unit 339: Area 12 Fleet Operations Steam Cleaning Effluent Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    K. B. Campbell

    2002-09-01T23:59:59.000Z

    The Area 12 Fleet Operations Steam Cleaning Effluent site is located in the southeastern portion of the Area 12 Camp at the Nevada Test Site. This site is identified in the Federal Facility Agreement and Consent Order (1996) as Corrective Action Site (CAS) 12-19-01 and is the only CAS assigned to Corrective Action Unit (CAU) 339. Post-closure sampling and inspection of the site were completed on March 27, 2002. Post-closure monitoring activities were scheduled biennially (every two years) in the Post-Closure Monitoring Plan provided in the Closure Report for CAU 339: Area 12 Fleet Operations Steam Cleaning Effluent, Nevada Test Site (U.S. Department of Energy, Nevada Operations Office [DOEN], 1997). A baseline for the site was established by sampling in 1997. Based on the recommendations from the 1999 post-closure monitoring report (DOE/NV, 1999), samples were collected in 2000, earlier than originally proposed, because the 1999 sample results did not provide the expected decrease in total petroleum hydrocarbon (TPH) concentrations at the site. Sampling results from 2000 (DOE/NV, 2000) and 2001 (DOE/NV, 2001) revealed favorable conditions for natural degradation at the CAU 339 site, but because of differing sample methods and heterogeneity of the soil, data results from 2000 and later were not directly correlated with previous results. Post-closure monitoring activities for 2002 consisted of the following: (1) Soil sample collection from three undisturbed plots (Plots A, B, and C, Figure 2). (2) Sample analysis for TPH as oil and bio-characterization parameters (Comparative Enumeration Assay [CEA] and Standard Nutrient Panel [SNP]). (3) Site inspection to evaluate the condition of the fencing and signs. (4) Preparation and submittal of the Post-Closure Monitoring Report.

  8. Model Development to Establish Integrated Operational Rule Curves for Hungry Horse and Libby Reservoirs - Montana, 1996 Final Report.

    SciTech Connect (OSTI)

    Marotz, Brian; Althen, Craig; Gustafson, Daniel

    1996-01-01T23:59:59.000Z

    Hungry Horse and Libby dams have profoundly affected the aquatic ecosystems in two major tributaries of the Columbia River by altering habitat and water quality, and by imposing barriers to fish migration. In 1980, the U.S. Congress passed the Pacific Northwest Electric Power Planning and Conservation Act, designed in part to balance hydropower development with other natural resources in the Columbia System. The Act formed the Northwest Power Planning Council (Council) who developed a program to protect, mitigate and enhance fish and wildlife on the Columbia River and its tributaries. Pursuant to the Council`s Fish and Wildlife Program for the Columbia River System (1987), we constructed computer models to simulate the trophic dynamics of the reservoir biota as related to dam operation. Results were used to develop strategies to minimize impacts and enhance the reservoir and riverine fisheries, following program measures 903(a)(1-4) and 903(b)(1-5). Two FORTRAN simulation models were developed for Hungry Horse and Libby reservoirs located in northwestern Montana. The models were designed to generate accurate, short-term predictions specific to two reservoirs and are not directly applicable to other waters. The modeling strategy, however, is portable to other reservoir systems where sufficient data are available. Reservoir operation guidelines were developed to balance fisheries concerns in the headwaters with anadromous species recovery actions in the lower Columbia (Biological Rule Curves). These BRCs were then integrated with power production and flood control to reduce the economic impact of basin-wide fisheries recovery actions. These Integrated Rule Curves (IRCs) were developed simultaneously in the Columbia Basin System Operation Review (SOR), the Council`s phase IV amendment process and recovery actions associated with endangered Columbia Basin fish species.

  9. Safety evaluation report related to the operation of Watts Bar Nuclear Plant, Units 1 and 2 (Docket Nos. 50-390 and 50-391). Supplement No. 14

    SciTech Connect (OSTI)

    Tam, P.S.

    1994-12-01T23:59:59.000Z

    Supplement No. 14 to the Safety Evaluation Report for the application filed by the Tennessee Valley Authority for license to operate Watts Bar Nuclear Plant, Units 1 and 2, Docket Nos. 50-390 and 50-391, located in Rhea County, Tennessee, has been prepared by the Office of Nuclear Reactor Regulation of the Nuclear Regulatory Commission. The purpose of this supplement is to update the Safety Evaluation with additional information submitted by the applicant since Supplement No. 13 was issued, and matters that the staff had under review when Supplement No. 13 was issued.

  10. Pacific Northwest Laboratory: Annual report for 1986 to the Assistant Secretary for Environment, Safety and Health: Part 5, Nuclear and operational safety

    SciTech Connect (OSTI)

    Faust, L.G.; Kennedy, W.E.; Steelman, B.L.; Selby, J.M.

    1987-02-01T23:59:59.000Z

    Part 5 of the 1986 Annual Report to the Department of Energy's Assistant Secretary for Environment, Safety and Health presents Pacific Northwest Laboratory's progress on work performed for the Office of Nuclear Safety, the Office of Operational Safety, and for the Office of Environmental Analysis. For each project, as identified by the Field Task Proposal/Agreement, articles describe progress made during fiscal year 1986. Authors of these articles represent a broad spectrum of capabilities derived from three of the seven research departments of the Laboratory, reflecting the interdisciplinary nature of the work.

  11. Regional Operations Research Program for Commercialization of Geothermal Energy in the Rocky Mountain Basin and Range. Final Technical Report, January 1980--March 1981

    SciTech Connect (OSTI)

    None

    1981-07-01T23:59:59.000Z

    This report describes the work accomplished from January 1980 to March 1981 in the Regional Operations Research efforts for the Rocky Mountain Basin and Range Geothermal Commercialization Program. The scope of work is as described in New Mexico State University Proposal 80-20-207. The work included continued data acquisition and extension of the data base, enhancement and refinement of the economic models for electric and direct use applications, site-specific and aggregated analyses in support of the state teams, special analyses in support of several federal agencies, and marketing assistance to the state commercialization teams.

  12. Electric and hybrid vehicle program site operator program. Quarterly progress report, October 1994--December 1994 (First quarter of FY-95)

    SciTech Connect (OSTI)

    Kiser, D.M.; Brown, H.L.

    1995-07-01T23:59:59.000Z

    The DOE Site Operator Program was initially established to meet the requirements of the Electric and Hybrid Vehicle Research, Development, and Demonstration Act of 1976. The Program has since evolved in response to new legislation and interests. Its mission now includes three ma or activity categories: (1) Advancement of Electric Vehicle (EV) technologies, (2) Development of infrastructure elements needed to support significant EV use, and (3) Increasing public awareness and acceptance of EVs. The 13 Program participants, their geographic locations, and the principal thrusts of their efforts are identified in Table ES-1. The EV inventories of each participant are summarized in Table ES-2.

  13. A radiological assessment of nuclear power and propulsion operations near Space Station Freedom. Contract report, January 1988-January 1990

    SciTech Connect (OSTI)

    Bolch, W.E.; Thomas, J.K.; Peddicord, K.L.; Nelson, P.; Marshall, D.T.; Busche, D.M.

    1990-03-01T23:59:59.000Z

    Scenarios were identified which involve the use of nuclear power systems in the vicinity of Space Station Freedom (SSF) and their radiological impact on the SSF crew was quantified. Several of the developed scenarios relate to the use of SSF as an evolutionary transportation node for lunar and Mars missions. In particular, radiation doses delivered to SSF crew were calculated for both the launch and subsequent return of a Nuclear Electric Propulsion (NEP) cargo vehicle and a Nuclear Thermal Rocket (NTR) personnel vehicle to low earth orbit. The use of nuclear power on co-orbiting platforms and the storage and handling issues associated with radioisotope power systems were also explored as they relate to SSF. A central philosophy in these analyses was the utilization of a radiation dose budget, defined as the difference between recommended dose limits from all radiation sources and estimated doses received by crew members from natural space radiations. Consequently, for each scenario examined, the dose budget concept was used to identify and quantify constraints on operational parameters such as launch separation distances, returned vehicle parking distances, and reactor shutdown times prior to vehicle approach. The results indicate that realistic scenarios do not exist which would preclude the use of nuclear power sources in the vicinity of SSF. The radiation dose to the SSF crew can be maintained at safe levels solely by implementing proper and reasonable operating procedures.

  14. Effect of the Operation of Kerr and Hungry Horse Dams on the Reproductive Success of Kokanee in the Flathead System; Technical Addendum to the Final Report.

    SciTech Connect (OSTI)

    Beattie, Will; Tohtz, Joel

    1990-03-01T23:59:59.000Z

    This addendum to the Final Report presents results of research on the zooplankton and fish communities of Flathead Lade. The intent of the Study has been to identify the impacts of hydroelectric operations at Kerr and Hungry Horse Dam on the reproductive success of kokanee an to propose mitigation for these impacts. Recent changes in the trophic ecology of the lake, have reduced the survival of kokanee. In the last three year the Study has been redirected to identify, if possible, the biological mechanisms which now limit kokanee survival, and to test methods of enhancing the kokanee fishery by artificial supplementation. These studies were necessary to the formulation of mitigation plans. The possibility of successfully rehabilitating the kokanee population, is the doubt because of change in the trophic ecology of the system. This report first presents the results of studies of the population dynamics of crustacean zooplankton, upon which planktivorous fish depend. A modest effort was directed to measuring the spawning escapement of kokanee in 1988. Because of its relevance to the study, we also report assessments of 1989 kokanee spawning escapement. Hydroacoustic assessment of the abundance of all fish species in Flathead Lake was conducted in November, 1988. Summary of the continued efforts to document the growth rates and food habits of kokanee and lake whitefish are included in this report. Revised kokanee spawning and harvest estimates, and management implications of the altered ecology of Flathead Lake comprise the final sections of this addendum. 83 refs., 20 figs., 25 tabs.

  15. Improving central heating plant performance at the defense construction supply center (DCSC): Advanced operation and maintenance methods. Final report

    SciTech Connect (OSTI)

    Savoie, M.J.; Standerfer, J.; Schmidt, C.M.; Gostich, J.; Mignacca, J.

    1994-11-01T23:59:59.000Z

    A 1987 air pollution emissions test done by the U.S. Army Environmental Hygiene Agency (USAEHA) identified several problems with the central heating plant (CHP) at the Defense Construction Supply Center (DCSC), Columbus, OH. Though DCSC repaired the specified problems, improved coal specifications, and tried to reduce air infiltration, CHP performance remained at unacceptable levels. Consequently, DCSC contracted the U.S. Army Construction Engineering Research Laboratories (USACERL) to apply advanced operation and maintenance procedures to improve its combustion system. This study employed a system-wide approach to evaluate the CHP 5 fuel storage, combustion, heat distribution, and the control of air emissions. Many short-term improvements to the CHP were identified and tested. Subsequent combustion and air emissions tests revealed that the recommended improvements successfully increased CHP efficiency. Long-term improvements were also recommended to help maintain the short-term improvements.

  16. Long-term effects of dredging operations program: Assessing bioaccumulation in aquatic organisms exposed to contaminated sediments. Final report

    SciTech Connect (OSTI)

    Clarke, J.U.; McFarland, V.A.

    1991-07-01T23:59:59.000Z

    This paper synthesizes previous work on bioaccumulation to provide a working document for the environmental impact on the aquatic environment due to bioaccumulation of sediment contaminants resulting from dredging operations and dredged material placement. Emphasis is placed on explanation of basic concepts concerning, and factors influencing, sediment contaminant bioaccumulation and bioavailability. The paper presents several numerical methods for assessing bioaccumulation, including a simple method for estimating theoretical bioaccumulation potential (TBP) from sediment chemistry for neutral organic chemicals. Methods are also given for projecting contaminant concentrations in organism tissues when steady state is achieved, based on laboratory or field exposures to contaminated sediments. These assessments are presented in the context of the US Environmental Protection Agency's tiered testing approach for dredged material evaluation. The various numerical methods for bioaccumulation assessment are illustrated and compared using step-by-step example calculations with hypothetical and actual data.

  17. Residential and commercial space heating and cooling with possible greenhouse operation; Baca Grande development, San Luis Valley, Colorado. Final report

    SciTech Connect (OSTI)

    Goering, S.W.; Garing, K.L.; Coury, G.E.; Fritzler, E.A.

    1980-05-01T23:59:59.000Z

    A feasibility study was performed to evaluate the potential of multipurpose applications of moderate-temperature geothermal waters in the vicinity of the Baca Grande community development in the San Luis Valley, Colorado. The project resource assessment, based on a thorough review of existing data, indicates that a substantial resource likely exists in the Baca Grande region capable of supporting residential and light industrial activity. Engineering designs were developed for geothermal district heating systems for space heating and domestic hot water heating for residences, including a mobile home park, an existing motel, a greenhouse complex, and other small commercial uses such as aquaculture. In addition, a thorough institutional analysis of the study area was performed to highlight factors which might pose barriers to the ultimate commercial development of the resource. Finally, an environmental evaluation of the possible impacts of the proposed action was also performed. The feasibility evaluation indicates the economics of the residential areas are dependent on the continued rate of housing construction. If essentially complete development could occur over a 30-year period, the economics are favorable as compared to existing alternatives. For the commercial area, the economics are good as compared to existing conventional energy sources. This is especially true as related to proposed greenhouse operations. The institutional and environmental analyses indicates that no significant barriers to development are apparent.

  18. DIII-D research operations. Annual report to the Department of Energy, October 1, 1991--September 30, 1992

    SciTech Connect (OSTI)

    Baker, D. [ed.

    1993-05-01T23:59:59.000Z

    The DIII-D tokamak research program is carried out by, General Atomics (GA) for the U.S. Department of Energy (DOE). The DIII-D is the most flexible tokamak in the world. The primary goal of the DIII-D tokamak research program is to provide data needed by International Thermonuclear Experimental Reactor (ITER) and to develop a conceptual physics blueprint for a commercially attractive electrical demonstration plant (DEMO) that would open a path to fusion power commercialization. Specific DIII-D objectives include the steady-state sustainment of plasma current as well as demonstrating techniques for microwave heating, divertor heat removal, fuel exhaust and tokamak plasma control. The DIII-D program is addressing these objectives in an integrated fashion with high beta and with good confinement. The DIII-D long-range plan is organized into two major thrusts; the development of an advanced divertor and the development of advanced tokamak concepts. These two thrusts have a common goal: an improved DEMO reactor with lower cost and smaller size than the present DEMO which can be extrapolated from the conventional ITER operational scenario. In order to prepare for the long-range program, in FY92 the DIII-D research program concentrated on three major areas: Divertor and Boundary Physics, Advanced Tokamak Studies, and Tokamak Physics.

  19. Apollo Multiplexer operations manual

    SciTech Connect (OSTI)

    Miller, M.M.

    1985-04-01T23:59:59.000Z

    This report describes the operation of the the Apollo Multiplexer, a microprocessor based communications device designed to process data between an Apollo computer and up to four Gandalf PACXIV data switches. Details are given on overall operation, hardware, and troubleshooting. The reader should gain sufficient knowledge from this report to understand the operation of the multiplexer and effectively analyze and correct any problems that might occur.

  20. Atmospheric fluidized-bed combustor design whose performance will significantly exceed conventional FBC operation performance. Final report

    SciTech Connect (OSTI)

    Hsiao, K.H.; Lin, Y.Y.; Guglietta, G.W.; Cares, W.R.; Fraley, L.D.; Schreiner, W.C.; Schlossman, M.; Solbakken, A.

    1982-12-01T23:59:59.000Z

    It is the goal of this project to bring forth a bench-scale design and test program to establish the merits of the circulating bed concept of atmospheric fluidized bed combustors (AFBC) and to show what the process development unit elements might be. The circulating fluid dynamics were modeled. From such a model the physical dimensions of a test system and the matrix for a test program can be established which will allow determination of parameters for scale-up evaluation of effectiveness and cost. This report presents an analysis of circulating bed boiler design methodology, alternative bench-scale designs for two coal feed levels (20 lbs/h and 80 lbs/h), including costs, and a test program. It is shown that the circulating bed concept has great merit for meeting DOE's advanced AFBC combustor criteria. A conceptual AFBC bench-scale design has been developed for an innovative AFBC system, specifically, a circulating bed boiler (CBB) for which two geometrically-similar designs, differing only in size, are presented.

  1. Post-Closure Monitoring Report for Corrective Action Unit 339: Area 12 Fleet Operations Steam Cleaning Discharge Area Nevada Test Site, Nevada

    SciTech Connect (OSTI)

    A. T. Urbon

    2001-08-01T23:59:59.000Z

    The Area 12 Fleet Operations Steam Cleaning site is located in the southeast portion of the Area 12 Camp at the Nevada Test Site (Figure 1). This site is identified in the Federal Facility Agreement and Consent Order (FFACO, 1996) as Corrective Action Site (CAS) 12-19-01 and is the only CAS assigned to Corrective Action Unit (CAU) 339. Post-closure sampling and inspection of the site were completed on March 23, 2001. Because of questionable representativeness and precision of the results, the site was resampled on June 12, 2001. Post-closure monitoring activities were scheduled biennially (every two years) in the Post-Closure Monitoring Plan provided in the December 1997 Closure Report for CAU 339: Area 12 Fleet Operations Steam Cleaning Discharge Area, Nevada Test Site (U.S. Department of Energy, Nevada Operations Office [DOE/NV], 1997). If after six years the rate of degradation appears to be so slow that the greatest concentration of total petroleum hydrocarbons (TPH) present at the site would not decay within 30 years of the site closure, the site will be reevaluated with consideration to enriching the impacted soil at the site to enhance the degradation process. A baseline for the site was established by sampling in 1997. Based on the recommendations from the 1999 post-closure monitoring report, samples were collected in 2000, earlier than originally proposed, because the 1999 sample results did not provide the expected decrease in TPH concentrations at the site. Sampling results from 2000 revealed favorable conditions for natural degradation at the CAU 339 site, but because of differing sample methods and heterogeneity of the soil, the data results from 2000 were not directly correlated with previous results. Post-closure monitoring activities for 2001 consisted of the following: Soil sample collection from three undisturbed plots (Plots A, B, and C, Figure 2); Sample analysis for TPH as oil and bio-characterization parameters (Comparative Enumeration Assay [CEA] and Standard Nutrient Panel [SNP]); Site inspection to evaluate the condition of the fencing and signs; and Preparation and submittal of the Post-Closure Monitoring Report.

  2. Environmental Management System 2 2011 SITE ENVIRONMENTAL REPORT2-1

    E-Print Network [OSTI]

    , and health management into all work planning and execution. The purpose of BNL's ISMS is to ensure MANAGEMENT SYSTEM IDENTIFY AND ANALYZE HAZARDS ASSOCI- ATED WITH THE WORK: Hazards associated with the workEnvironmental Management System 2 2011 SITE ENVIRONMENTAL REPORT2-1 One of Brookhaven National

  3. Environmental Management System 2 2012 SITE ENVIRONMENTAL REPORT2-1

    E-Print Network [OSTI]

    management into all work planning and execution. The purpose of BNL's ISMS is to ensure that the way we do MANAGEMENT SYSTEM IDENTIFY AND ANALYZE HAZARDS ASSOCI- ATED WITH THE WORK: Hazards associated with the workEnvironmental Management System 2 2012 SITE ENVIRONMENTAL REPORT2-1 One of Brookhaven National

  4. Hatchery Evaluation Report/Lyons Ferry Hatchery - Summer Steelhead : an Independent Audit Based on Integrated Hatchery Operations Team (IHOT) Performance Measures.

    SciTech Connect (OSTI)

    Watson, Montgomery.

    1996-05-01T23:59:59.000Z

    This report presents the findings of the independent audit of the Lyons Ferry Hatchery (Summer Steelhead). Lyons Ferry Hatchery is located downstream of the confluence of the Palouse and Snake rivers, about 7 miles west of Starbuck, Washington. The hatchery is used for adult collection of tall chinook and summer steelhead, egg incubation of fall chinook, spring chinook, steelhead, and rainbow trout and rearing of fall chinook, spring chinook, summer steelhead, and rainbow trout. The audit was conducted in April 1996 as part of a two-year effort that will include 67 hatcheries and satellite facilities located on the Columbia and Snake River system in Idaho, Oregon, and Washington. The hatchery operating agencies include the U.S Fish and Wildlife Service, Idaho Department of Fish and Game, Oregon Department of Fish and Wildlife, and Washington Department of Fish and Wildlife.

  5. Hatchery Evaluation Report/Lyons Ferry Hatchery - Spring Chinook : an Independent Audit Based on Integrated Hatchery Operations Team (IHOT) Performance Measures.

    SciTech Connect (OSTI)

    Watson, Montgomery.

    1996-05-01T23:59:59.000Z

    This report presents the findings of the independent audit of the Lyons Ferry Hatchery (Spring Chinook). Lyons Ferry Hatchery is located downstream of the confluence of the Palouse and Snake rivers, about 7 miles west of Starbuck, Washington. The hatchery is used for adult collection of fall chinook and summer steelhead, egg incubation of fall chinook, spring chinook, steelhead. and rainbow trout and rearing of fall chinook, spring chinook, summer steelhead, and rainbow trout. The audit was conducted in April 1996 as part of a two-year effort that will include 67 hatcheries and satellite facilities located on the Columbia and Snake River system in Idaho, Oregon, and Washington. The hatchery operating agencies include the U.S Fish and Wildlife Service, Idaho Department of Fish and Game, Oregon Department of Fish and Wildlife, and Washington Department of Fish and Wildlife.

  6. Maintenance and operation of the U.S. DOE Alternative Fuel Center. Final subcontract report, 5 August 1994--4 August 1995

    SciTech Connect (OSTI)

    Erwin, J.; Moulton, D.S. [Southwest Research Inst., San Antonio, TX (United States)

    1996-04-01T23:59:59.000Z

    The Alternative Fuel Center (AFC) was established by the US Department of Energy (DOE) as part of the Alternative Fuel Utilization Program (AFUP). The AFC is designed to provide drum quantities of finished transportation fuels from a variety of sources. DOE funded the design, construction, and installation of a hydrogenation pilot plant capable of performing a range of hydrotreating, reforming, and hydrocracking operations. Southwest Research Institute provided the building, utilities, and laboratory and safety systems needed for the pilot plant. The AFC work reported here contributes to the two primary objectives of the AFUP: data for alternative-fuel-capable vehicles to enhance energy security, and data for controlling emissions for improved air quality.

  7. DETERMINATION OF CORROSION INHIBITOR CRITERIA FOR TYPE III/IIIA TANKS DURING SALT DISSOLUTION OPERATIONS INTERIM REPORT

    SciTech Connect (OSTI)

    Counts, K; Bruce Wiersma, B; John Mickalonis, J

    2007-12-31T23:59:59.000Z

    Preparation of high level waste for vitrification involves in part the dissolution of salt cake from the carbon steel storage tanks. During dissolution, a point is reached in which the corrosion inhibitors, hydroxide and nitrite, are diluted below established guidelines, and nitrate stress corrosion cracking (SCC) is possible. Because the addition of inhibitors may be counterproductive to process efficiency and waste minimization, corrosion testing was initiated to revisit and possibly revise the guidelines for inhibitor limits. The bases for the work summarized in this status report are results from previously-completed phases of study. In the first two phases of study, several reduced-inhibitor levels were tested in HLW simulants with nitrate concentrations ranging from 4.5 M to 8.5 M. The first two phases of work determined, among other things, the reduced-inhibitor levels and solution chemistries in which heat-treated and non-heat-treated A537 carbon steel is susceptible to SCC, crevice corrosion, and pitting. The work covered in this current task both builds on and verifies the conclusions of the previous work. The current work involves testing of low levels of inhibitors in HLW simulants with 5.5 M to 8.5 M nitrate concentrations. Stressed U-bend specimens, both polarized and non-polarized, were tested. Non-polarized U-bend testing is ongoing, with the U-bends currently in test for 100 days. The purpose of the testing is to determine SCC susceptibility in the vapor space (VS) and liquid air interface (LAI) regions of the HLW tanks under conditions expected during salt dissolution, and also to verify previous accelerated testing. The simulated wastes being tested have nitrate concentrations of 5.5 M and 8.5 M and inhibitor levels of 0.01 M/0.01 M hydroxide/nitrite and 0.1 M/ 0.1 M hydroxide/nitrite. The open circuit potential measurements being monitored and the corrosion morphology of the U-bends are in agreement with results and observations of previous phases of work. No SCC has occurred in the first 100 days of testing. The LAI specimens experienced minor corrosion at the liquid line with corrosion products visible on the weld material and in the heat-affected zones on either side of the welds. The VS specimens are more evenly and slightly more corroded. Polarized U-bend testing is complete after approximately 80 days of testing. No SCC occurred, but the results are inconclusive due to a competing, unexpected galvanic corrosion mechanism that interfered in the last 50 days of testing. No cracking was indicated during the first month. The tests will be repeated in order to satisfy the original objective which was to determine the effect of grinding HLW tank welds and heat treating the tanks had on corrosion. Both the non-polarized and polarized U-bend tests will continue. Additionally, cyclic polarization (CP) testing will be performed to examine the effects of surface oxides on corrosion and the differences in corrosion susceptibility between welded and un-welded areas.

  8. Reports

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Scienceand Requirements Recently ApprovedReliability TechnologyRenewalReport Period:Reports

  9. Safety evaluation report related to the operation of Watts Bar Nuclear Plant, Units 1 and 2 (Docket Nos. 50-390 and 50-391). Supplement No. 15

    SciTech Connect (OSTI)

    Tam, P.S.

    1995-06-01T23:59:59.000Z

    This report supplements the Safety Evaluation Report (SER), NUREG-0847 (June 1982), Supplement No. 1 (September 1982), Supplement No. 2 (January 1984), Supplement No. 3 (January 1985), Supplement No. 4 (March 1985), Supplement No. 5 (November 1990), Supplement No. 6 (April 1991), Supplement No. 7 (September 1991), Supplement No. 8 (January 1992), Supplement No. 9 (June 1992), Supplement No. 10 (October 1992), Supplement No. 11 (April 1993), Supplement No. 12 (October 1993), Supplement No. 13 (April 1994), and Supplement No. 14 (December 1994) issued by the Office of Nuclear Reactor Regulation of the US Nuclear Regulatory Commission with respect to the application filed by the Tennessee Valley Authority, as applicant and owner, for licenses to operate the Watts Bar Nuclear Plant, Units 1 and 2 (Docket Nos. 50-390 and 50-391). The facility is located in Rhea County, Tennessee, near the Watts Bar Dam on the Tennessee River. This supplement provides recent information regarding resolution of some of the outstanding and confirmatory items, and proposed license conditions identified in the SER.

  10. 2008 Annual Report

    SciTech Connect (OSTI)

    none,

    2008-01-01T23:59:59.000Z

    This annual report includes: a brief overview of Western; FY 2008 operational highlights; and financial data.

  11. Sustainment Operations Team Final Report

    E-Print Network [OSTI]

    Harris, Wesley

    Improvement of Mission Capable Rate (MCR) depends on factors such as transportation & logistics, resource loading & scheduling, and Available Parts & materials (AP&M). As shown in Figure 1, AP&M is a function of forecasting ...

  12. ARM - ARM Operations Quarterly Reports

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOnItemResearchSOLICITATIONIMODI FICATION OF CONTRACTOperationsYear Research Related

  13. REPORT

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOn April 23, 2014, an OHASeptember 2010In addition to 1 |D I S P U REPORT of the

  14. DIII-D research operations annual report to the U.S. Department of Energy, October 1, 1996 through September 30, 1997

    SciTech Connect (OSTI)

    NONE

    1998-10-01T23:59:59.000Z

    The main goals of the DIII-D experiments in 1997 were, by extending and integrating the understanding of fusion science, to make progress in the tokamak concept improvements as delineated in the DIII-D Long Range Plan and to make substantial contributions to urgently needed R and D for the ITER Engineering Design Activity. For these purposes, the authors modified the top divertor to include pumping with baffling of high triangularity shaped plasmas and brought into operation two megawatt-level-gyrotrons for electron cyclotron heating (ECH) and off-axis current drive. The elements of the DIII-D experimental program and its objectives are organized into five topical areas: Stability and Disruption Physics, Transport and Turbulence Physics, Divertor and Boundary Physics, Wave-Particle Physics, and Integrated Fusion Science and Innovative Concept Improvement. The resulting DIII-D fusion science accomplishments are described in detail in this report. This year was characterized by a number of important activities, most notably, two 110 GHz ECH gyrotrons were installed and commissioned, the upper RDP cryopump and baffle was installed, and the ohmic heating coil lead was successfully reinforced to allow return to the design coil configuration and an increase to 7.5 V-s next year. Real-time ``Isoflux`` plasma control was implemented to control the shape and position of the plasma. This system solves the MHD equilibrium equation in real time to accurately determine the location of the plasma boundary. At the same time, the authors were able to improve their safety record with three minor accidents and no lost time accidents. The staff available for operations tasks was substantially reduced owing to recent budget reductions and this impacted a number of activities.

  15. Liquid-phase methanol process development unit: installation, operation, and support studies. Technical progress report No. 1, 28 September 1981-31 December 1981

    SciTech Connect (OSTI)

    Not Available

    1982-01-20T23:59:59.000Z

    During this period the Work Breakdown Structure Dictionary was established. Task 1 was completed with submittal of the Project Work Plan and the Quality Assurance Manual. CSI produced basic process design information and a preliminary flowsheet for the LaPorte LPMeOH PDU. APCI developed the flowsheet further and set up the process on APCI's process simulator. The flowsheet development revealed a number of major changes necessary in the existing LPM pilot plant; this has led to pursuit of a unified design concept. Approval was requested for the unified design concept as well as advanced schedule for relocation of the LPM unit and advanced procurement of long delivery equipment items. A number of preliminary heat and material balances were calculated for the LPMeOH PDU and preliminary process specifications were prepared for the equipment items. The final design basis was established. The design pressure was set at 1000 psig. Eight design operating cases were defined for the following range of reactor operating conditions: Pressure - 500 to 900 psig, Temperature - 220 to 270/sup 0/C, Liquid-Fluidized Space Velocity - 1000 to 4000 l/hr-kg catalyst, Liquid-Entrained Space Velocity - 2000 to 10,000 l/hr-kg catalyst, and Liquid-Entrained Catalyst Loading - 0.1 to 0.4 kg catalyst/l oil. The methanol production rate for these cases ranges from 0.2 to 9.7 short tons per day. Preliminary equipment arrangement and site layout drawings were prepared for the PDU. In the laboratories, CSI began autoclave testing of in-situ catalyst reduction procedures. The specification and evaluation of equipment for the CSI laboratory PDU progressed. CSI prepared and issued a Topical Report covering liquid-entrained LPMeOH lab development work accomplished under advance funding. APCI's laboratories progressed with the design of the bench scale slurry reactor.

  16. FINAL REPORT SUMMARY OF DM 1200 OPERATION AT VSL VSL-06R6710-2 REV 0 9/7/06

    SciTech Connect (OSTI)

    KRUGER AA; MATLACK KS; DIENER G; BARDAKCI T; PEGG IL

    2011-12-29T23:59:59.000Z

    The principal objective of this report was to summarize the testing experience on the DuraMelter 1200 (DMI200), which is the High Level Waste (HLW) Pilot Melter located at the Vitreous State Laboratory (VSL). Further objectives were to provide descriptions of the history of all modifications and maintenance, methods of operation, problems and unit failures, and melter emissions and performance while processing a variety of simulated HL W and low activity waste (LAW) feeds for the Hanford Waste Treatment and Immobilization Plant (WTP) and employing a variety of operating methods. All of these objectives were met. The River Protection Project - Hanford Waste Treatment and Immobilization Plant (RPP-WTP) Project has undertaken a 'tiered' approach to vitrification development testing involving computer-based glass formulation, glass property-composition models, crucible melts, and continuous melter tests of increasing, more realistic scales. Melter systems ranging from 0.02 to 1.2 m{sup 2} installed at the Vitreous State Laboratory (VSL) have been used for this purpose, which, in combination with the 3.3 m{sup 2} low activity waste (LAW) Pilot Melter at Duratek, Inc., span more than two orders of magnitude in melt surface area. In this way, less-costly small-scale tests can be used to define the most appropriate tests to be conducted at the larger scales in order to extract maximum benefit from the large-scale tests. For high level waste (HLW) vitrification development, a key component in this approach is the one-third scale DuraMelter 1200 (DM 1200), which is the HLW Pilot Melter that has been installed at VSL with an integrated prototypical off-gas treatment system. That system replaced the DM1000 system that was used for HLW throughput testing during Part B1. Both melters have similar melt surface areas (1.2 m{sup 2}) but the DM1200 is prototypical of the present RPP-WTP HLW melter design whereas the DM1000 was not. In particular, the DM1200 provides for testing on a vitrification system with the specific train of unit operations that has been selected for both HLW and LAW RPP-WTP off-gas treatment.

  17. Effects of Hydroelectric Dam Operations on the Restoration Potential of Snake River Fall Chinook Salmon (Oncorhynchus tshawytscha) Spawning Habitat Final Report, October 2005 - September 2007.

    SciTech Connect (OSTI)

    Hanrahan, Timothy P.; Richmond, Marshall C.; Arntzen, Evan V. [Pacific Northwest National Laboratory

    2007-11-13T23:59:59.000Z

    This report describes research conducted by the Pacific Northwest National Laboratory for the Bonneville Power Administration (BPA) as part of the Fish and Wildlife Program directed by the Northwest Power and Conservation Council. The study evaluated the restoration potential of Snake River fall Chinook salmon spawning habitat within the impounded lower Snake River. The objective of the research was to determine if hydroelectric dam operations could be modified, within existing system constraints (e.g., minimum to normal pool levels; without partial removal of a dam structure), to increase the amount of available fall Chinook salmon spawning habitat in the lower Snake River. Empirical and modeled physical habitat data were used to compare potential fall Chinook salmon spawning habitat in the Snake River, under current and modified dam operations, with the analogous physical characteristics of an existing fall Chinook salmon spawning area in the Columbia River. The two Snake River study areas included the Ice Harbor Dam tailrace downstream to the Highway 12 bridge and the Lower Granite Dam tailrace downstream approximately 12 river kilometers. These areas represent tailwater habitat (i.e., riverine segments extending from a dam downstream to the backwater influence from the next dam downstream). We used a reference site, indicative of current fall Chinook salmon spawning areas in tailwater habitat, against which to compare the physical characteristics of each study site. The reference site for tailwater habitats was the section extending downstream from the Wanapum Dam tailrace on the Columbia River. Fall Chinook salmon spawning habitat use data, including water depth, velocity, substrate size and channelbed slope, from the Wanapum reference area were used to define spawning habitat suitability based on these variables. Fall Chinook salmon spawning habitat suitability of the Snake River study areas was estimated by applying the Wanapum reference reach habitat suitability criteria to measured and modeled habitat data from the Snake River study areas. Channel morphology data from the Wanapum reference reach and the Snake River study areas were evaluated to identify geomorphically suitable fall Chinook salmon spawning habitat. The results of this study indicate that a majority of the Ice Harbor and Lower Granite study areas contain suitable fall Chinook salmon spawning habitat under existing hydrosystem operations. However, a large majority of the currently available fall Chinook salmon spawning habitat in the Ice Harbor and Lower Granite study areas is of low quality. The potential for increasing, through modifications to hydrosystem operations (i.e., minimum pool elevation of the next downstream dam), the quantity or quality of fall Chinook salmon spawning habitat appears to be limited. Estimates of the amount of potential fall Chinook salmon spawning habitat in the Ice Harbor study area decreased as the McNary Dam forebay elevation was lowered from normal to minimum pool elevation. Estimates of the amount of potential fall Chinook salmon spawning habitat in the Lower Granite study area increased as the Little Goose Dam forebay elevation was lowered from normal to minimum pool elevation; however, 97% of the available habitat was categorized within the range of lowest quality. In both the Ice Harbor and Lower Granite study areas, water velocity appears to be more of a limiting factor than water depth for fall Chinook salmon spawning habitat, with both study areas dominated by low-magnitude water velocity. The geomorphic suitability of both study areas appears to be compromised for fall Chinook salmon spawning habitat, with the Ice Harbor study area lacking significant bedforms along the longitudinal thalweg profile and the Lower Granite study area lacking cross-sectional topographic diversity. To increase the quantity of available fall Chinook salmon spawning habitat in the Ice Harbor and Lower Granite study area, modifications to hydroelectric dam operations beyond those evaluated in this study likely would be necessary. M

  18. MEMORANDUM FO~~~ ATE DIRECTORS FROM:

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOEThe Bonneville PowerCherries 82981-1cnHigh SchoolIn12electron 9November 6, In this3,Office of Science Washington,

  19. Evaluation of potential severe accidents during low power and shutdown operations at Grand Gulf, Unit 1. Volume 2, Part 1C: Analysis of core damage frequency from internal events for plant operational State 5 during a refueling outage, Main report (Sections 11--14)

    SciTech Connect (OSTI)

    Whitehead, D. [Sandia National Labs., Albuquerque, NM (United States); Darby, J. [Science and Engineering Associates, Inc., Albuquerque, NM (United States); Yakle, J. [Science Applications International Corp., Albuquerque, NM (United States)] [and others

    1994-06-01T23:59:59.000Z

    This document contains the accident sequence analysis of internally initiated events for Grand Gulf, Unit 1 as it operates in the Low Power and Shutdown Plant Operational State 5 during a refueling outage. The report documents the methodology used during the analysis, describes the results from the application of the methodology, and compares the results with the results from two full power analyses performed on Grand Gulf.

  20. Assessment of economic impact of offshore and coastal discharge requirements on present and future operations in the Gulf of Mexico. Final report

    SciTech Connect (OSTI)

    Lindsey, R. [Bartlesville Project Office, OK (United States)

    1996-06-01T23:59:59.000Z

    The high potential costs of compliance associated with new effluent guidelines for offshore and coastal oil and gas operations could significantly affect the economics of finding, developing, and producing oil and gas in the Gulf of Mexico. This report characterizes the potential economic impacts of alternative treatment and discharge regulations for produced water on reserves and production in Gulf of Mexico coastal, territorial and outer continental shelf (OCS) waters, quantifying the impacts of both recent regulatory changes and possible more stringent requirements. The treatment technologies capable of meeting these requirements are characterized in terms of cost, performance, and applicability to coastal and offshore situations. As part of this analysis, an extensive database was constructed that includes oil and gas production forecasts by field, data on existing platforms, and the current treatment methods in place for produced water treatment and disposal on offshore facilities. This work provides the first comprehensive evaluation of the impacts of alternative regulatory requirements for produced water management and disposal in coastal and offshore areas of the Gulf of Mexico.

  1. Remedial investigation report on Chestnut Ridge Operable Unit 2 (filled coal ash pond/Upper McCoy Branch) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Volume 2: Appendixes

    SciTech Connect (OSTI)

    Not Available

    1994-08-01T23:59:59.000Z

    This report comprises appendices A--J which support the Y-12 Plant`s remedial action report involving Chestnut Ridge Operable Unit 2 (filled coal ash pond/Upper McCoy Branch). The appendices cover the following: Sampling fish from McCoy Branch; well and piezometer logs; ecological effects of contaminants in McCoy Branch 1989-1990; heavy metal bioaccumulation data; microbes in polluted sediments; and baseline human health risk assessment data.

  2. Operations & Maintenance

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations and Maintenance Operations OASIS: OATI (Note: this site is not hosted by Western and requires a digital certificate and login for full access.) Contact Information...

  3. Operations & Maintenance

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Rates Operations & Maintenance Operations OASIS: WACM (Note: this site is not hosted by Western and requires a digital certificate and login for full access.) wesTTrans Common...

  4. Addendum to the Closure Report for Corrective Action Unit 339: Area 12 Fleet Operations Steam Cleaning Discharge Area, Nevada Test Site, Revision 0

    SciTech Connect (OSTI)

    Grant Evenson

    2009-05-01T23:59:59.000Z

    This document constitutes an addendum to the Closure Report for CAU 339: Area 12 Fleet Operations Steam Cleaning Discharge Area Nevada Test Site, December 1997 as described in the document Supplemental Investigation Report for FFACO Use Restrictions, Nevada Test Site, Nevada (SIR) dated November 2008. The SIR document was approved by NDEP on December 5, 2008. The approval of the SIR document constituted approval of each of the recommended UR removals. In conformance with the SIR document, this addendum consists of: • This page that refers the reader to the SIR document for additional information • The cover, title, and signature pages of the SIR document • The NDEP approval letter • The corresponding section of the SIR document This addendum provides the documentation justifying the cancellation of the UR for CAS 12-19-01, A12 Fleet Ops Steam Cleaning Efflu. This UR was established as part of a Federal Facility Agreement and Consent Order (FFACO) corrective action and is based on the presence of contaminants at concentrations greater than the action levels established at the time of the initial investigation (FFACO, 1996). Since this UR was established, practices and procedures relating to the implementation of risk-based corrective actions (RBCA) have changed. Therefore, this UR was reevaluated against the current RBCA criteria as defined in the Industrial Sites Project Establishment of Final Action Levels (NNSA/NSO, 2006). This re-evaluation consisted of comparing the original data (used to define the need for the UR) to risk-based final action levels (FALs) developed using the current Industrial Sites RBCA process. The re-evaluation resulted in a recommendation to remove the UR because contamination is not present at the site above the risk-based FALs. Requirements for inspecting and maintaining this UR will be canceled, and the postings and signage at this site will be removed. Fencing and posting may be present at this site that are unrelated to the FFACO UR such as for radiological control purposes as required by the NV/YMP Radiological Control Manual (NNSA/NSO, 2004). This modification will not affect or modify any non-FFACO requirements for fencing, posting, or monitoring at this site.

  5. Conceptual Design Report Cask Loadout Sys and Cask Drop Redesign for the Immersion Pail Support Structure and Operator Interface Platform at 105 K West

    SciTech Connect (OSTI)

    LANGEVIN, A.S.

    1999-07-12T23:59:59.000Z

    This conceptual design report documents the redesign of the IPSS and the OIP in the 105 KW Basin south loadout pit due to a postulated cask drop accident, as part of Project A.5/A.6, Canister Transfer Facility Modifications. Project A.5/A.6 involves facility modifications needed to transfer fuel from the basin into the cask-MCO. The function of the IPSS is to suspend, guide, and position the immersion pail. The immersion pail protects the cask-MCO from contamination by basin water and acts as a lifting device for the cask-MCO. The OIP provides operator access to the south loadout pit. Previous analyses studied the effects of a cask-MCO drop on the south loadout pit concrete structure and on the IPSS. The most recent analysis considered the resulting loads at the pit slab/wall joint (Kanjilal, 1999). This area had not been modeled previously, and the analysis results indicate that the demand capacity exceeds the allowable at the slab/wall joint. The energy induced on the south loadout pit must be limited such that the safety class function of the basin is maintained. The solution presented in this CDR redesigns the IPSS and the OIP to include impact-absorbing features that will reduce the induced energy. The impact absorbing features of the new design include: Impact-absorbing material at the IPSS base and at the upper portion of the IPSS legs. A sleeve which provides a hydraulic means of absorbing energy. Designing the OIP to act as an impact absorber. The existing IPSS structure in 105 KW will be removed. This conceptual design considers only loads resulting from drops directly over the IPSS and south loadout pit area. Drops in other areas of the basin are not considered, and will be covered as part of a future revision to this CDR.

  6. Evaluation of potential severe accidents during low power and shutdown operations at Surry, Unit 1: Evaluation of severe accident risk during mid-loop operations. Main report. Volume 6. Part 1

    SciTech Connect (OSTI)

    Jo, J.; Lin, C.C.; Neymotin, L. [Brookhaven National Lab., Upton, NY (United States)] [and others

    1995-05-01T23:59:59.000Z

    During 1989, the Nuclear Regulatory Commission (NRC) initiated an extensive program to carefully examine the potential risks during low power and shutdown operations. The program includes two parallel projects being performed by Brookhaven National Laboratory (BNL) and Sandia National Laboratories (SNL). Two plants, Surry (pressurized water reactor) and Grand Gulf (boiling water reactor), were selected as the plants to be studied. The objectives of the program are to assess the risks of severe accidents initiated during plant operational states other than full power operation and to compare the estimated core damage frequencies, important accident sequences and other qualitative and quantitative results with those accidents initiated during full power operation as assessed in NUREG-1150. The scope of the program includes that of a level-3 PRA. A phased approach was used in the level-1 program. In phase 1 which was completed in Fall 1991, a coarse screening analysis including internal fire and flood was performed for all plant operational states (POSs). The objective of the phase 1 study was to identify potential vulnerable plant configurations, to characterize (on a high, medium, or low basis) the potential core damage accident scenarios, and to provide a foundation for a detailed phase 2 analysis. In phase 2, mid-loop operation was selected as the plant configuration to be analyzed based on the results of the phase 1 study. The objective of the phase 2 study is to perform a detailed analysis of the potential accident scenarios that may occur during mid-loop operation, and compare the results with those of NUREG-1150. The results of the phase 2 level 2/3 study are the subject of this volume of NUREG/CR-6144, Volume 6.

  7. Distributed Generation Operational Reliability and Availability...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Reliability and Availability Database, Final Report, January 2004 Distributed Generation Operational Reliability and Availability Database, Final Report, January 2004 This final...

  8. Operated by the Association of Universities for Research in Astronomy, Inc., for the National Aeronautics and Space Administration Instrument Science Report ACS 2005-06

    E-Print Network [OSTI]

    Sirianni, Marco

    Aeronautics and Space Administration Instrument Science Report ACS 2005-06 Demonstration of a Significant examples where major scien- #12;Instrument Science Report ACS 2005-06 2 tific discoveries have only been

  9. Fuel efficient train operations: A preliminary investigation with the locomotive data acquisition package on the Union Pacific Railroad. Interim report Jun-Nov 80

    SciTech Connect (OSTI)

    Larsen, K.W.

    1981-12-01T23:59:59.000Z

    The Locomotive Data Acquisition Package (LDAP) is a research data acquisition system designed for use on board diesel locomotives. Between June 1980 and November 1980, a fuel efficient train operations experiment was conducted in cooperation with the Union Pacific Railroad using the LDAP. The experiment served both as a checkout of the LDAP unit, and as a preliminary study of the relationship between train handling and fuel consumption. The LDAP unit was operated on a Union Pacific Locomotive for 127 days during which data were collected for 53,936 miles of locomotive operation.

  10. Operating Reserves and Variable Generation

    SciTech Connect (OSTI)

    Ela, E.; Milligan, M.; Kirby, B.

    2011-08-01T23:59:59.000Z

    This report tries to first generalize the requirements of the power system as it relates to the needs of operating reserves. It also includes a survey of operating reserves and how they are managed internationally in system operations today and then how new studies and research are proposing they may be managed in the future with higher penetrations of variable generation.

  11. RECONSTRUCTION OF DOSE TO THE RESIDENTS OF OZERSK FROM THE OPERATION OF THE MAYAK PRODUCTION ASSOCIATION: 1948-2002: Progress Report on Project 1.4

    SciTech Connect (OSTI)

    Mokrov, Y.; Rovny, Sergey I.; Anspaugh, L. R.; Napier, Bruce A.

    2009-10-23T23:59:59.000Z

    This Progress Report for Project 1.4 of the U.S.–Russia Joint Coordinating Committee on Radiation Effects Research continues in the abbreviated format of providing details only on the work accomplished during this six-month reporting period.

  12. Phase II - final report study of alternatives for future operations of the naval petroleum and oil shale reserves NPR-3, Wyoming

    SciTech Connect (OSTI)

    NONE

    1996-12-01T23:59:59.000Z

    The U.S. Department of Energy (DOE) has asked Gustavson Associates, Inc. to serve as an Independent Petroleum Appraiser under contract DE-AC01-96FE64202. This authorizes a study and recommendations regarding future development of Naval Petroleum Reserve No. 3 (NPR-3) in Natrona County, Wyoming. The report that follows is the Phase II Final Report for that study.

  13. Hurricane slams gulf operations

    SciTech Connect (OSTI)

    Not Available

    1992-09-07T23:59:59.000Z

    This paper reports that reports of damage by Hurricane Andrew escalated last week as operators stepped up inspections of oil and gas installations in the Gulf of Mexico. By midweek, companies operating in the gulf and South Louisiana were beginning to agree that earlier assessments of damage only scratched the surface. Damage reports included scores of lost, toppled, or crippled platforms, pipeline ruptures, and oil slicks. By midweek the U.S. coast Guard had received reports of 79 oil spills. Even platforms capable of resuming production in some instances were begin curtailed because of damaged pipelines. Offshore service companies the another 2-4 weeks could be needed to fully assess Andrew's wrath. Lack of personnel and equipment was slowing damage assessment and repair.

  14. Electric and hybrid vehicle program; Site Operator Program. Quarterly progress report, January--March 1992 (Second quarter of fiscal year 1992)

    SciTech Connect (OSTI)

    Warren, J.F.

    1992-05-01T23:59:59.000Z

    Activities during the second quarter included the second meeting of the Site Operators in Phoenix, AZ in late April. The meeting was held in conjunction with the Solar and Electric 500 Race activities. Delivery of vehicles ordered previously has begun, although two of the operators are experiencing some delays in receiving their vehicles. Public demonstration activities continue, with an apparent increasing level of awareness and interest being displayed by the public. Initial problems with the Site Operator Database have been corrected and revised copies of the program have been supplied to the Program participants. Operating and Maintenance data is being supplied and submitted to INEL on a monthly basis. Interest in the Site Operator Program is being reflected in requests for information from several organizations from across the country, representing a wide diversity of interests. These organizations have been referred to existing Site Operators with the explanation that the program will not be adding new participants, but that most of the existing organizations are willing to work with other groups. The exception to this was the addition of Potomac Electric Power Company (PEPCO) to the program. PEPCO has been awarded a subcontract to operate and maintain the DOE owned G-Van and Escort located in Washington, DC. They will provide data on these vehicles, as well as a Solectria Force which PEPCO has purchased. The Task Force intends to be actively involved in the infrastructure development in a wide range of areas. These include, among others, personnel development, safety, charging, and servicing. Work continues in these areas. York Technical College (YORK) has completed the draft outline for the EV Technician course. This is being circulated to organizations around the country for comments. Kansas State University (KSU) is working with a private sector company to develop a energy dispensing meter for opportunity charging in public areas.

  15. Solar production of industrial process steam. Phase III. Operation and evaluation of the Johnson and Johnson solar facility. Final report, January 1, 1980-March 31, 1981

    SciTech Connect (OSTI)

    Brink, D.F.; Kendall, J.M.; Youngblood, S.B.

    1981-03-01T23:59:59.000Z

    A solar facility that generates 177/sup 0/C (350/sup 0/F) process steam has been designed and constructed by Acurex Corporation and has operated for 1 yr supplying steam to the Johnson and Johnson manufacturing plant in Sherman, Texas. The facility consists of 1068 m/sup 2/ (11,520 ft/sup 2/) of parabolic trough concentrating collectors, a 18,900 1 (5000 gal) flash boiler, and an 18.6 kW (25 hp) circulating pump. In the first year of operation the system was available 97 percent of the days, and with sufficient solar radiation available it operated 70 percent of the days during this period. The measured data showed that the collector field operated at an efficiency of 25.4 percent for the year, and that at least 75 percent of the energy reaching the flash boiler was delivered to the plant as steam. A total of 309,510 kg (682,400 lb) of steam was produced by the solar facility for the first year. An analysis of the data showed that the delivered energy was within 90 to 100 percent of the predicted value. The successful completion of the first year of operation has demonstrated the technical feasibility of generating industrial process steam with solar energy.

  16. Improvement of operations and maintenance techniques research program: an evaluation of the standard elutriate test as an estimator of contaminant release at the point of dredging. Final report

    SciTech Connect (OSTI)

    Ludwig, D.D.; Sherrad, J.H.; Amende, R.A.

    1988-08-01T23:59:59.000Z

    While release of contaminants during dredged material disposal operations has long been the subject of environmental concern for some projects, the potential release of pollutants during the dredging process has recently come under the scrutiny of Federal and State regulatory agencies. Maintenance of shipping channels may require the removal of sediments suspected to contain high concentrations of contaminants. During any dredging operation, sediments become resuspended to varying degrees according to sediment type, hydrologic conditions, type of dredging equipment used, and operational procedures employed. Contaminants may be released in soluble form directly to the water column, or they may remain adsorbed to the fine resuspended sediment particles. The primary mode of environmental impact is from the soluble fraction, since dissolved forms of pollutants are more available for aquatic biota uptake than those that remain adsorbed to sediment particles.

  17. U.S. DOE Geopressured/Geothermal Program: Final report on well plug and abandonment operations and well site restoration, Louisiana and Texas wells

    SciTech Connect (OSTI)

    None

    1994-08-30T23:59:59.000Z

    Some of the critical operations conducted during the plugging and abandonment of the three producing wells of the U.S. DOE GEOPRESSURED/GEOTHERL PROGRAM were witnessed by D-O-R Engineering personnel. All operations witnessed by D-O-R personnel were in compliance with the respective state regulations and were conducted as per D-O-R's recommendations to the Department of Energy and their prime contractor, EG&G Idaho. It is our belief that competent cement plugs were left in all three wells. The following describes the work actually witnessed by D-O-R personnel.

  18. Inspection of Environment, Safety, and Health and Emergency Management at the Oak Ridge Operations Office and East Tennessee Technology Park, Summary Report, May 2003

    Broader source: Energy.gov [DOE]

    This report provides the results of an inspection of environment, safety, and health and emergency management programs at the U.S. Department of Energy's (DOE) East Tennessee Technology Park (ETTP).

  19. Operating experience feedback report-reliability of safety-related steam turbine-driven standby pumps used in US commerical nuclear power plants

    SciTech Connect (OSTI)

    Boardman, J.R. [Nuclear Regulatory Commission, Washington, DC (United States)

    1995-01-01T23:59:59.000Z

    Pump failure experience is collected by two primary means: (1) Licensee Event Reports, and (2) Nuclear Plant Reliability Data System failure reports. Certain safety-related turbine-driven standby pumps were identified by these data systems as experiencing significant ongoing repetitive failures of their turbine drivers, resulting in low reliability of the pump units. The root causes of identified failures were determined, and actions to preclude these repetitive failures were identified. 5 refs., 1 tab.

  20. Solid Waste Operations Complex W-113, Detail Design Report (Title II). Volume 2: Solid waste retrieval facilities -- Phase 1, detail design drawings

    SciTech Connect (OSTI)

    NONE

    1995-09-01T23:59:59.000Z

    The Solid Waste Retrieval Facility--Phase 1 (Project W113) will provide the infrastructure and the facility required to retrieve from Trench 04, Burial ground 4C, contact handled (CH) drums and boxes at a rate that supports all retrieved TRU waste batching, treatment, storage, and disposal plans. This includes (1) operations related equipment and facilities, viz., a weather enclosure for the trench, retrieval equipment, weighing, venting, obtaining gas samples, overpacking, NDE, NDA, shipment of waste and (2) operations support related facilities, viz., a general office building, a retrieval staff change facility, and infrastructure upgrades such as supply and routing of water, sewer, electrical power, fire protection, roads, and telecommunication. Title I design for the operations related equipment and facilities was performed by Raytheon/BNFL, and that for the operations support related facilities including infrastructure upgrade was performed by KEH. These two scopes were combined into an integrated W113 Title II scope that was performed by Raytheon/BNFL. Volume 2 provides the complete set of the Detail Design drawings along with a listing of the drawings. Once approved by WHC, these drawings will be issued and baselined for the Title 3 construction effort.

  1. report 2013 Front cover image: Greenough River Solar Farm, Western Australia.

    E-Print Network [OSTI]

    Green, Donna

    R heAtinG 59 WinD PoWeR 65 appendiCes 65 APPenDiX 1: toP 10 SolAR PoStCoDeS by StAte 68 APPenDiX 2 #12. From jobs and investment in regional areas to solar panels, solar hot water and high efficiencyClean energy australia report 2013 #12;Front cover image: Greenough River Solar Farm, Western

  2. Installing and operating FEGTEMs

    SciTech Connect (OSTI)

    Hetherington, C.J.; Cullis, A.G.; Walker, S.; Turner, J.; Nelson, E.C.; O'Keefe, M.A.

    1997-11-03T23:59:59.000Z

    In order to operate at full potential, Field-Emission-Gun Transmission Electron Microscopes (FEG-TEMs) require special environments designed to minimize the effects of vibration and electromagnetic noise. This report shows how careful attention to these details can enable such instruments to achieve their design parameters and produce information transfer to sub-Angstrom resolutions.

  3. Operating Costs

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    This chapter is focused on capital costs for conventional construction and environmental restoration and waste management projects and examines operating cost estimates to verify that all elements of the project have been considered and properly estimated.

  4. Demonstration of the enrichment of medium quality gas from gob wells through interactive well operating practices. Final report, June--December, 1995

    SciTech Connect (OSTI)

    Blackburn, S.T.; Sanders, R.G.; Boyer, C.M. II; Lasseter, E.L.; Stevenson, J.W.; Mills, R.A.

    1995-12-01T23:59:59.000Z

    Methane released to the atmosphere during coal mining operations is believed to contribute to global warming and represents a waste of a valuable energy resource. Commercial production of pipeline-quality gob well methane through wells drilled from the surface into the area above the gob can, if properly implemented, be the most effective means of reducing mine methane emissions. However, much of the gas produced from gob wells is vented because the quality of the gas is highly variable and is often below current natural gas pipeline specifications. Prior to the initiation of field-testing required to further understand the operational criteria for upgrading gob well gas, a preliminary evaluation and assessment was performed. An assessment of the methane gas in-place and producible methane resource at the Jim Walter Resources, Inc. No. 4 and No. 5 Mines established a potential 15-year supply of 60 billion cubic feet of mien methane from gob wells, satisfying the resource criteria for the test site. To understand the effect of operating conditions on gob gas quality, gob wells producing pipeline quality (i.e., < 96% hydrocarbons) gas at this site will be operated over a wide range of suction pressures. Parameters to be determined will include absolute methane quantity and methane concentration produced through the gob wells; working face, tailgate and bleeder entry methane levels in the mine; and the effect on the economics of production of gob wells at various levels of methane quality. Following this, a field demonstration will be initiated at a mine where commercial gob gas production has not been attempted. The guidelines established during the first phase of the project will be used to design the production program. The economic feasibility of various utilization options will also be tested based upon the information gathered during the first phase. 41 refs., 41 figs., 12 tabs.

  5. Regional operations research program for commercialization of geothermal energy in the Rocky Mountain Basin and Range. Final report, August 1, 1978-February 28, 1980

    SciTech Connect (OSTI)

    Marlin, J.M.; Cunniff, R.; McDevitt, P.; Nowotny, K.; O'Dea, P.

    1981-01-01T23:59:59.000Z

    The work accomplished from August 1978 to February 1980 in the Regional Operations Research efforts for the Rocky Mountain Basin and Range Geothermal Commercialization Program are described. The work included continued data acquisition and extension of the data base, enhancement and refinement of the economic models for electric and direct use applications, site-specific and aggregated analyses in support of the state teams and special analyses in support of several federal agencies.

  6. Addendum to the remedial investigation report on Bear Creek Valley Operable Unit 2 (Rust Spoil Area, Spoil Area 1, and SY-200 Yard) at the Oak Ridge Y-12 Plant Oak Ridge, Tennessee. Volume 1: Main text

    SciTech Connect (OSTI)

    NONE

    1995-04-01T23:59:59.000Z

    This addendum to the Remedial Investigation (RI) Report on Bear Creek Valley Operable Unit (OU) 2 at the Oak Ridge Y-12 Plant was prepared in accordance with requirements under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) for reporting the results of a site characterization for public review. This addendum is a supplement to a document that was previously issued in January 1995 and that provided the Environmental Restoration Program with information about the results of the 1993 investigation performed at OU 2. The January 1995 D2 version of the RI Report on Bear Creek Valley OU 2 included information on risk assessments that have evaluated impacts to human health and the environment. Information provided in the document formed the basis for the development of the Feasibility Study Report. This addendum includes revisions to four chapters of information that were a part of the document issued in January 1995. Specifically, it includes revisions to Chaps. 2, 3, 4, and 9. Volume 1 of this document is not being reissued in its entirety as a D3 version because only the four chapters just mentioned have been affected by requested changes. Note also that Volume 2 of this RI Report on Bear Creek Valley OU 2 is not being reissued in conjunction with Volume 1 of this document because there have been no changes requested or made to the previously issued version of Volume 2 of this document.

  7. Occurrence Reporting

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1995-09-25T23:59:59.000Z

    To establish and maintain a system for reporting operations information related to DOE-owned or -operated facilities and processing that information to identify the root causes of Unusual, Off-Normal, and Emergency Occurrences and provide for appropriate corrective action. Cancels DOE 5000.3B.

  8. Nuclear Power 2010 Program Dominion Virginia Power Cooperative Project U.S. Department of Energy Cooperative Agreement DE-FC07-05ID14635 Construction and Operating License Demonstration Project Final Report

    SciTech Connect (OSTI)

    Eugene S. Grecheck

    2010-11-30T23:59:59.000Z

    This report serves to summarize the major activities completed as part of Virginia Electric and Power Company's North Anna construction and operating license demonstration project with DOE. Project successes, lessons learned, and suggestions for improvement are discussed. Objectives of the North Anna COL project included preparation and submittal of a COLA to the USNRC incorporating ESBWR technology for a third unit a the North Anna Power Station site, support for the NRC review process and mandatory hearing, obtaining NRC approval of the COLA and issuance of a COL, and development of a business case necessary to support a decision on building a new nuclear power plant at the North Anna site.

  9. DIII-D research operations

    SciTech Connect (OSTI)

    Baker, D. (ed.)

    1993-05-01T23:59:59.000Z

    This report discusses the research on the following topics: DIII-D program overview; divertor and boundary research program; advanced tokamak studies; tokamak physics; operations; program development; support services; contribution to ITER physics R D; and collaborative efforts.

  10. AEC and Oak Ridge Operations

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    which reported to the Manager of Oak Ridge Operations. These area offices include: 1. Paducah, KY 2. Portsmouth, OH 3. Cincinnati, OH 4. St. Louis, MO 5. New Brunswick, NJ 6....

  11. Operations Videos

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)IntegratedSpeeding access toTest and EvaluationOperational ManagementCenterOperations

  12. Functional and operational design requirements for decontamination and decommissioning of the EBR-I Mark-II NaK: Final report. [NaK eutectics

    SciTech Connect (OSTI)

    Brown, B.W.; Crandall, D.L.; Dafoe, R.E.; Dolenc, M.R.; LaRue, D.M.

    1987-09-01T23:59:59.000Z

    Approximately 180 gal of sodium/potassium (NaK) eutectic liquid metal were severely radioactively contaminated during a meltdown of the Mark-II core of the Experimental Breeder Reactor-I (EBR-I) in November 1955. This contaminated NaK, which is contained in four vessels, is currently stored in an underground bunker located at the Army Reentry Vehicle Facility Site (ARVFS) located approximately at the center of the Idaho National Engineering Laboratory (INEL). This document presents the Functional and Operational Requirements (F and ORs) for the D and D of the contaminated NaK and the ARVFS bunker site. This project will chemically deactivate the NaK; dispose of the radioactively contaminated product at a designated burial site; chemically deactivate any residual NaK in the containers, and dispose of the containers at a designated burial site; decontaminate and decommission any contaminated process equipment used in these operations, and decontaminate and decommission the ARVFS bunker site. Completion of the above technical objectives will allow for the effective disposition of the NaK, and will return the ARFVS bunker and immediate area to a reusable condition. Upon completion, the ARVFS NaK, which is now considered a significant potential hazard, will be removed from the Surplus Facilities Management Program priority listing of projects. 33 refs., 8 figs.

  13. Lease Operations Environmental Guidance Document

    SciTech Connect (OSTI)

    Bureau of Land Management

    2001-02-14T23:59:59.000Z

    This report contains discussions in nine different areas as follows: (1) Good Lease Operating Practices; (2) Site Assessment and Sampling; (3) Spills/Accidents; (4) Containment and Disposal of Produced Waters; (5) Restoration of Hydrocarbon Impacted Soils; (6) Restoration of Salt Impacted Soils; (7) Pit Closures; (8) Identification, Removal and Disposal of Naturally Occurring Radioactive Materials (NORM); and (9) Site Closure and Construction Methods for Abandonment Wells/Locations. This report is primary directed towards the operation of oil and gas producing wells.

  14. Freight Operators’ Perceptions of Congestion Problems and the Application of Advanced Technologies: Results from a 1998 Survey of 1200 Companies Operating in California

    E-Print Network [OSTI]

    Regan, Amelia C.; Golob, Thomas F.

    2000-01-01T23:59:59.000Z

    to answer the survey and had operations in California. Thethe survey reported never having their operations impactedINTERMODAL OPERATIONS The remaining section of the survey

  15. Gulf operators resuming production

    SciTech Connect (OSTI)

    Koen, A.D.

    1992-09-14T23:59:59.000Z

    This paper reports that Gulf of Mexico operators last week were gradually restoring production at installations struck by Hurricane Andrew. The Minerals Management Service continued receiving reports of more damage. By the end of the day Sept. 8, MMS had received reports of damage to 83 pipeline segments and 193 platforms and satellite installations. Damage reports listed 112 installations with structural damage, 13 platforms toppled and five leaning, and 30 satellite platforms toppled and 33 leaning. But despite the extent of damage the storm inflicted on oil and gas installations in the gulf, it pales in comparison to the misery and suffering the storm caused in Florida and Louisiana, an oil company official said.

  16. Independent Activity Report, Hanford Plutonium Finishing Plant...

    Broader source: Energy.gov (indexed) [DOE]

    National Laboratory - January 2014 Independent Activity Report, Richland Operations Office - April 2013 Independent Activity Report, Paducah Gaseous Diffusion Plant - July...

  17. Advanced characterization of forms of chlorine, organic sulfur, and trace elements in available coals from operating Illinois mines. [Quarterly] technical report, September 1--November 30, 1994

    SciTech Connect (OSTI)

    Chou, M.I.M.; Demir, I.; Ruch, J.M. [Illinois State Geological Survey (United States)] [and others

    1994-12-31T23:59:59.000Z

    A set of 34 as-shipped coal samples from operating Illinois mines is available for this study to determine the forms of chlorine and sulfur and leachability of chlorine during wet grinding and froth flotation. The forms of chlorine may be inorganic, ionic, and organic. The forms of organic sulfur will include organic sulfide and thiophenic sulfur. Chlorine can be leached from coal during wet grinding. The potential for removal of chlorine from the samples during fine ({minus}200 mesh) and ultrafine ({minus}400 mesh) wet-grinding and during froth flotation designed primarily for removal of pyrite and ash will be determined. In addition, the organic/inorganic affinities of trace elements in as-shipped Illinois coals will be assessed so that the current physical coal cleaning results may be better interpreted.

  18. Extreme Performance Scalable Operating Systems Final Progress Report (July 1, 2008 ���¢�������� October 31, 2011)

    SciTech Connect (OSTI)

    Allen D. Malony; Sameer Shende

    2011-10-31T23:59:59.000Z

    This is the final progress report for the FastOS (Phase 2) (FastOS-2) project with Argonne National Laboratory and the University of Oregon (UO). The project started at UO on July 1, 2008 and ran until April 30, 2010, at which time a six-month no-cost extension began. The FastOS-2 work at UO delivered excellent results in all research work areas: * scalable parallel monitoring * kernel-level performance measurement * parallel I/0 system measurement * large-scale and hybrid application performance measurement * onlne scalable performance data reduction and analysis * binary instrumentation

  19. Independent Oversight Activity Report for the Operational Awareness Oversight Visit of the Nevada National Security Site, May 5-7, 2014

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33Frequently Asked Questions for DOEthe RankingReform atSolar Energy Report Number:IEA Independent

  20. Water Use in the Development and Operations of Geothermal Power...

    Energy Savers [EERE]

    Water Use in the Development and Operations of Geothermal Power Plants Water Use in the Development and Operations of Geothermal Power Plants This report summarizes what is...

  1. Water Use in the Development and Operations of Geothermal Power...

    Energy Savers [EERE]

    Operations of Geothermal Power Plants Water Use in the Development and Operations of Geothermal Power Plants This report summarizes what is currently known about the life cycle...

  2. Water Use in the Development and Operation of Geothermal Power...

    Energy Savers [EERE]

    Operation of Geothermal Power Plants Water Use in the Development and Operation of Geothermal Power Plants This report summarizes what is currently known about the life cycle water...

  3. Impacts of Water Level Fluctuations on Kokanee Reproduction in Flathead Lake; Effects of Operation of Kerr and Hungry Horse Dam on Reproductive Success, 1983 Annual Report.

    SciTech Connect (OSTI)

    Decker-Hess, Janet; McMullin, Steve L.

    1983-11-01T23:59:59.000Z

    Koktneesalmon (Oncorhvnchusnerka), the land-locked form of sockeye salmon, were originally introduced to Flathead Lake in 1916. My 1933, kokanee had become established in the lake and provided a popular summer trolling fishery as well as a fall snagging fishery in shoreline areas. Presently, Flathead Lake supports the second highest fishing pressure of any lake or reservoir in Montana (Montana Department of Fish and Game 1976). During 1981-82, the lake provided 168,792 man-days of fishing pressure. Ninety-two percent of the estimated 536,870 fish caught in Flathead Lake in 1981-82 were kokanee salmon. Kokanee also provided forage for bull trout seasonally and year round for lake trout. Kokanee rear to maturity in Flathead Lake, then return to various total grounds to spawn. Spawning occurred in lake outlet streams, springs, larger rivers and lake shoreline areas in suitable but often limited habitat. Shoreline spawning in Flathead Lake was first documented in the mid-1930's. Spawning kokanee were seized from shoreline areas in 1933 and 21,000 cans were processed and packed for distribution to the needy. Stefanich (1953 and 1954) later documented extensive but an unquantified amount of spawning along the shoreline as well as runs in Whitefish River and McDonald Creek in the 1950's. A creel census conducted in 1962-63 determined 11 to 13 percent of the kokanee caught annually were taken during the spawning period (Robbins 1966). During a 1981-82 creel census, less than one percent of the fishermen on Flathead Lake were snagging kokanee (Graham and Fredenberg 1982). The operation of Kerr Dam, located below Flathead Lake on the Flathead River, has altered seasonal fluctuations of Flathead Lake. Lake levels presently remain high during kokanee spawning in November and decline during the incubation and emergence periods. Groundwater plays an important role in embryo and fry survival in redds of shoreline areas exposed by lake drawdown. Stefanich (1954) and Domrose (1968) found live eggs and fry only in shoreline spawning areas wetted by groundwater seeps. Impacts of the operation of Kerr Dam on lakeshore spawning have not been quantified. Recent studies have revealed that operation of Hungry Horse Dam severely impacted successful kokanee spawning and incubation in the Flathead River above Flathead Lake (Graham et al. 1980, McMullin and Graham 1981, Fraley and Graham 1982 and Fraley and McMullin 1983). Flows from Hungry Horse Dam to enhance kokanee reproduction in the river system have been voluntarily met by the Bureau of Reclamation since 1981. In lakeshore spawning areas in other Pacific Northwest systems, spawning habitat for kokanee and sockeye salmon was characterized by seepage or groundwater flow where suitable substrate composition existed (Foerster 1968). Spawning primarily occurred in shallower depths (<6 m) where gravels were cleaned by wave action (Hassemer and Rieman 1979 and 1980, Stober et al. 1979a). Seasonal drawdown of reservoirs can adversely affect survival of incubating kokanee eggs and fry spawned in shallow shoreline areas. Jeppon (1955 and 1960) and Whitt (1957) estimated 10-75 percent kokanee egg loss in shoreline areas of Pend Oreille Lake, Idaho after regulation of the upper three meters occurred in 1952. After 20 years of operation, Bowler (1979) found Pend Oreille shoreline spawning to occur in fewer areas with generally lower numbers of adults. In studies on Priest Lake, Idaho, Bjornn (1957) attributed frozen eggs and stranded fry to winter fluctuations of the upper three meters of the lake. Eggs and fry frozen during winter drawdown accounted for a 90 percent loss to shoreline spawning kokanee in Donner Lake, California (Kimsey 1951). Stober et al. (1979a) determined irrigation drawdown of Banks Lake, Washington reduced shoreline survival during five of the seven years the system was studied. The goal of this phase of the study was to evaluate and document effects of the operation of Kerr Dam on kokanee shoreline reproduction in Flathead Lake. Specific objectives to meet this goal are: (1) Del

  4. Office of Inspector General inspection report on ``Inspection of an allegation regarding the voluntary separation program at the Savannah River Operations Office``

    SciTech Connect (OSTI)

    NONE

    1998-10-01T23:59:59.000Z

    In April 1996, the Savannah River Operations Office received approval from DOE Headquarters to offer Westinghouse Savannah River Company (WSRC) and Bechtel Savannah River, Inc. (BSRI) employees early termination incentives to facilitate downsizing of the contractor workforce thereby minimizing involuntary separations. In 1996, 217 individuals at the Savannah River Site (SRS) accepted a Voluntary Separation Program (VSP) incentive. The Office of Inspector General (OIG) received an allegation that a former senior manager of the WSRC was provided an opportunity to terminate employment through a VSP. The complainant wrote that after separating from WSRC, and receiving a large bonus for doing so, the former senior manager returned to work at the Savannah River Site (SRS) without observing a required waiting period of one year. The inspection determined that the former senior manager terminated employment with WSRC under the VSP program. It was found that the former senior manager`s departure from WSRC was delayed for six months, until December 31, 1996, in order for a replacement to be relocated from Pittsburgh, Pennsylvania, to SRS and be familiarized with the position. The underlying principle of the VSP was to allow WSRC and BSRI employees to voluntarily leave the SRS workforce, and, if necessary, only be replaced by current SRS employees. The Office of Inspector General concluded that WSRC allowed the former senior manager to participate in the VSP, and then replaced the senior manager with an individual from Westinghouse`s headquarters in Pittsburgh. Consequently, WSRC did not meet the test of prudent business judgment required by its contract with DOE. It was recommended that both the former senior manager`s VSP bonus payment of $99,762, as well as $36,892 in travel and relocation costs expended to move the replacement from Pittsburgh to SRS, be recovered from WSRC. They also recommended that the Manager, Savannah River Operations Office, determine whether any other senior WSRC or BSRI personnel who participated in the VSP were replaced by non-SRS personnel, and, if so, recover from the appropriate contractor the associated costs.

  5. Operation Poorman

    SciTech Connect (OSTI)

    Pruvost, N.; Tsitouras, J.

    1981-03-18T23:59:59.000Z

    The objectives of Operation Poorman were to design and build a portable seismic system and to set up and use this system in a cold-weather environment. The equipment design uses current technology to achieve a low-power, lightweight system that is configured into three modules. The system was deployed in Alaska during wintertime, and the results provide a basis for specifying a mission-ready seismic verification system.

  6. Operating Strategies

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for RenewableSpeeding accessSpeedingOctoberResearchOpen→ globalOPERATING PLAN

  7. Operations Office

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for RenewableSpeeding accessSpeedingOctoberResearchOpen→ globalOPERATING

  8. Physical Property Analysis and Report for Sediments at 100-BC-5 Operable Unit, Boreholes C7505, C7506, C7507, and C7665

    SciTech Connect (OSTI)

    Lindberg, Michael J.

    2010-09-28T23:59:59.000Z

    Between October 14, 2009 and February 22, 2010 sediment samples were received from 100-BC Decision Unit for geochemical studies. This is an analytical data report for sediments received from CHPRC at the 100 BC 5 OU. The analyses for this project were performed at the 325 building located in the 300 Area of the Hanford Site. The analyses were performed according to Pacific Northwest National Laboratory (PNNL) approved procedures and/or nationally recognized test procedures. The data sets include the sample identification numbers, analytical results, estimated quantification limits (EQL), and quality control data. The preparatory and analytical quality control requirements, calibration requirements, acceptance criteria, and failure actions are defined in the on-line QA plan 'Conducting Analytical Work in Support of Regulatory Programs' (CAW). This QA plan implements the Hanford Analytical Services Quality Assurance Requirements Documents (HASQARD) for PNNL.

  9. Disruption Management --Operations Research between

    E-Print Network [OSTI]

    Larsen Allan Larsen§ Jesper Hansen¶ Informatics and Mathematical Modelling Technical University. This report will describe real-world examples of a novel way of applying Operations Research: As plans have and revised version of this report has appeared in OR/MS Today vol. 28, No. 5, page 40-43 (October 2001

  10. Environmental and economic assessment of discharges from Gulf of Mexico Region oil and gas operations. Quarterly technical progress report, 23 June 1992--30 September 1992

    SciTech Connect (OSTI)

    Gettleson, D.A.

    1992-11-10T23:59:59.000Z

    A Sampling and Analysis Plan was prepared and submitted to a Scientific Review Committee for comment. Substantial comments relative to study objectives, sampling design, and sampling periods coupled with the passage of Hurricane Andrew precluded the scheduled initiation of sampling at offshore and coastal sites (Tasks 3 -- Environmental Field Sampling and Analysis of Naturally Occurring Radioactive Materials (NORM), Heavy Metals, and Organics and 4 -- Monitoring of the Recovery of Impacted Wetland and Open Bay Produced Water Discharge Sites in Coastal Louisiana and Texas). A proposed revised schedule has been prepared for Tasks 3 and 4. Task 5 (Assessment of Economic Impacts of Offshore and Coastal Discharge Requirements on Present and Future Operations in the Gulf of Mexico Region), activities have involved identification and collection of the necessary data for the economic analysis. Task 6 (Synthesis of Gulf of Mexico Region Consumption and Use Patterns), activities have included near completion of the literature review and a reevaluation of the data collection efforts relative to the wholesaler, process plant, and restaurant components. Task 7 (Technology Transfer Plan), work has been delayed due to the Tasks 3 and 4 delay and cancellation of the annual US Minerals Management Service Gulf of Mexico Region Information Transfer Meeting.

  11. Development Operations Hypersaline Geothermal Brine Utilization...

    Open Energy Info (EERE)

    Hypersaline Geothermal Brine Utilization Imperial County, California Jump to: navigation, search OpenEI Reference LibraryAdd to library Report: Development Operations Hypersaline...

  12. Sandia National Laboratories: optimal solar asset operations...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    operations and maintenance Sandia-Electric Power Research Institute Partnership Publishes Photovoltaic Reliability Report On January 21, 2014, in Energy, Facilities, Grid...

  13. Office of Enterprise Assessments Operational Awareness Record...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    (EA) Operational Awareness Record Report Number: OAR-ANL-2014-11-03 Site: Argonne National Laboratory (ANL) Subject: Oversight of Argonne National Laboratory and New Brunswick...

  14. System design study to reduce capital and operating cost of a moving distributor, AFB advanced concept - comparison with an oil-fired boiler. Final report

    SciTech Connect (OSTI)

    Mah, C.S.; West, L.K.; Anderson, R.E.; Berkheimer, I.L.; Cahill, D.V.

    1985-12-01T23:59:59.000Z

    The Aerojet Energy Conversion Company, under contract with the United States Department of Energy, has performed a comparative economic study of the Aerojet Universal Atmospheric Fluidized Bed Combustion (UAFBC) system and a coventional atmospheric fluidized bed combustion (AFBC) system. The program title, ''System Design Study to Reduce Capital and Operating Cost and Bench Scale Testing of a Moving Distributor, AFB Concept,'' is a good description of the general objective of the program. The specific objective was to compare the UAFBC with the conventional AFBC in terms of normalized steam cost. The boilers were designed for 150,00 lb/hr of steam at 650 psig and 750/sup 0/F. The reference coal used in the analysis was Pittsburgh No. 8 coal with a sulfur content of 4.3% and a higher heating value of 12,919 Bru/lb. The analysis assumed a plant life of 20 years and a discount rate of 15%. The UAFBC systems included the usual elements of the conventional cola-fired AFBC steam plant, but the coal preparation sysbsystem for the UAFBC was considerably simpler because the system can use ''run-of-mine'' coal. The UAFBC boiler itself consisted of a staged-combustion fluidized-bed, superimposed over a static bed, the latter supported by a moving distributor. It incorporated a fines burnup combustor, an entrained reciculating gas cleanup bed, and conventional convection boiler. The key features of the UAFBC design were: High fuel flexibility; low NO/sub x/ emission; and superior turndown capability. 30 refs., 52 figs., 12 tabs.

  15. Environmental and economic assessment of discharges from Gulf of Mexico region oil and gas operations. Quarterly technical progress report, April--June 1993

    SciTech Connect (OSTI)

    Gettleson, D.A.

    1993-07-26T23:59:59.000Z

    Continental Shelf Associates, Inc. (CSA) was contracted to conduct a three-year study of the environmental and health related impacts of produced water and sand discharges from oil and gas operations. Data on naturally occurring radioactive materials (NORM), heavy metals, and hydrocarbons in water, sediment, and biota will be collected and evaluated. Health related impacts will be studied through field collections and analyses of commercially- and recreationally-important fish and shellfish tissues. Additionally, information on seafood catch, consumption, and use patterns for the Gulf of Mexico will be gathered and analyzed. The facilities to be studied will include both offshore and coastal facilities in the Gulf of Mexico. Coastal sites will be additionally studied to determine ecological recovery of impacted wetland and open bay areas. The economic impact of existing and proposed effluent federal and state regulations will also be evaluated. The primary objectives of the project are to increase the base of scientific knowledge concerning (1) the fate and environmental effects of organics, trace metals, and NORM in water, sediment, and biota near several offshore oil and gas facilities; (2) the characteristics of produced water and produced sand discharges as they pertain to organics, trace metals, and NORM variably found in association with the discharges; (3) the recovery of four terminated produced water discharge sites located in wetland and high-energy open bay sites of coastal Louisiana and Texas; (4) the economic and energy supply impacts of existing and anticipated federal and state offshore and coastal discharge regulations; and (5) the catch, consumption and human use patterns of seafood species collected from coastal and offshore waters. Accomplishments for this period are described.

  16. U.S. Department of Energy Office of Inspector General report on inspection of Westinghouse Savannah River Company fees for managing and operating the Savannah River Site

    SciTech Connect (OSTI)

    NONE

    1995-08-03T23:59:59.000Z

    During the first five years of its contract with the Department of Energy, Westinghouse Savannah River Company was paid over $130 million in fees to manage and operate the Savannah River Site. Fees paid to Westinghouse steadily increased over the five year period. For example, fees paid for the last six months of this five year period were over three times as large as fees paid for the first six months. The purpose of this inspection was to review the Department`s annual negotiation of total available fees with Westinghouse, and to examine the reasons for the growth in fees over this five year period. The review disclosed that, after Fiscal Year 1989, the Department used an increasing number of fee bases in calculating Westinghouse Savannah River Company`s fixed-fee-equivalents from the maximum fee schedules within the Department of Energy Acquisition Regulation. The authors found that the Department had significantly increased the percentage of the dollar value of subcontracts being placed in Westinghouse`s fee bases for fee calculation purposes. They found that the Department had effectively increased Westinghouse`s fixed-fee-equivalents by approximately $3 million in both Fiscal Year 1993 and 1994 to, in large part, fund an unallowable employee incentive compensation program. They found that Westinghouse`s total paid fees for the five year period increased significantly over what they would have been had the terms resulting from the original competitive negotiations been maintained. The authors recommended that the Deputy Assist Secretary for Procurement and Assistance Management require that changes in either the number or composition of fee bases used in calculating fees from the maximum fee schedules be submitted to the Department`s Procurement Executive for approval.

  17. Single particle counting diagnostic system for measuring fine particulates at high number densities in research and industrial applications. Final report summarizing instrument development, validation and operating instructions

    SciTech Connect (OSTI)

    Holve, D.J.

    1983-10-01T23:59:59.000Z

    Optical methods for particle size distribution measurements in practical high temperature environments have achieved feasibility and offer significant advantages over conventional sampling methods. The present report describes a mobile electro-optical system which has been designed for general use in a wide range of research and industrial environments. Specific features of this system include a method of providing in situ alignment and incorporation of an extinction measurement for application to optically thick aerosol flows. The instrument has demonstrated capability for measuring individual particles in the size range 0.25 to 100 microns at number densities up to 10/sup 12//m/sup 3/. In addition to demonstration of the system's wide dynamic range, we show the utility of the in situ alignment method in hot (1100 K) turbulent flows where beam steering can be a problem. As an example of the instrument's application, number and mass frequency distribution measurements of flyash and pulverized coal obtained in an atmospheric combustion exhaust simulator show that the raw pulverized coal contains large numbers of submicron particles similar to the flyash formed after combustion.

  18. Operational Excellence

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOnItemResearch > TheNuclear Astrophysics One ofSpeedingthis site » OpenOperational

  19. Operations Information

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for RenewableSpeeding accessSpeedingOctoberResearchOpen→ globalOPERATING Who We

  20. Gulf operations still recovering

    SciTech Connect (OSTI)

    Koen, A.D.

    1992-09-21T23:59:59.000Z

    This paper reports that reports of damage caused by Hurricane Andrew were leveling off last week at the U.S. Minerals Management Service as Gulf of Mexico operators pressed ahead with repairs. The hurricane struck South Florida Aug. 4, churned west into the gulf, then swung north and hit the South Louisiana coast Aug. 5. By the close of business Sept. 8 MMS had received damage reports covering 83 pipeline segments and 193 platforms and satellite installations. MMS last week estimated about 500 MMcfd of gas production had been restored in the gulf and 100,000-150,000 b/d of oil. Production still lost as a result of Andrew was estimated at 2-2.5 bcfd of gas and 90,000-120 b/d of oil. MMS estimates Gulf of Mexico wells before the storm were producing about 12.5-13 bcfd of gas and 750,000 b/d of oil.

  1. Effect of the Operation of Kerr and Hungry Horse Dams on the Reproduction Success of Kokanee in the Flathead River System, 1986 Annual Progress Report.

    SciTech Connect (OSTI)

    Beattie, Will; Clancey, Patrick

    1987-03-01T23:59:59.000Z

    The 1985 kokanee spawning run in the Flathead system was the strongest in five years. Escapement to the Flathead River system was 147,000 fish, including 123,000 in McDonald Creek and an estimated 20,000 in the main stem. Enumeration of spawners and redds in the Flathead River was hindered by high fall flows and early freezing in November. The upstream spawning migration from Flathead Lake began in late August. Schools of kokanee were seen six miles above the lake on September 4. We counted 1,156 redds in Flathead Lake, distributed primarily along the southeastern shore. An unusually high proportion (90 percent) of lakeshore spawning occurred in the zone above minimum pool, where egg mortality is very high because of exposure from drawdown. Escapement to the Swan River was 1,350 fish. Four year old (III+) fish comprised 95 percent of the spawning run in the Flathead system. This continues a five-year trend toward dominance of the III+ year class. The age composition of spawners has varied considerably for the past 15 years. The average size of spawning fish was 365 mm, which is identical to the average size of the parent year class in 1981. One of the goals of managing Flathead kokanee is to produce mature fish 300-330 mm in length. In the main stem Flathead River, pre-emergent survival was 80 percent. Survival in McDonald Creek, unaffected by hydroelectric operations, was 83 percent. Sampling showed few hatched alevins, probably due to unusually cold winter temperatures. Egg survival at Blue Bay, a spawning area on Flathead Lake where redds are concentrated below minimum pool, varied in relation to depth and dissolved oxygen concentration in the substrate. Eggs survived 78 days at 2,880 feet where dissolved oxygen was 5.7 mg/l. Eggs survived 35 days at 2,870 feet where dissolved oxygen concentration averaged 2.9 mg/l. Low dissolved oxygen contributed to poor survival to emergence at all elevations in Blue Ray. Experiments in Skidoo Bay confirmed that survival of eggs above minimum pool depends on redds being wetted by groundwater seeps. After 40 days exposure by drawdown, eggs in groundwater seeps showed 86 percent survival, whereas outside of the groundwater seeps eggs survived less than six days. These results confirm that exposure by drawdown is the primary factor that limits kokanee reproductive success in redds above minimum pool. We surveyed the west and south shoreline of Flathead Lake to locate potential kokanee spawning habitat. We found conditions which could support incubating eggs at two sites in South Ray and two sites on the west shore of the lake. Seven other sites on the west shore were not suitable due to low groundwater discharge or low dissolved oxygen. In all these areas suitable substrate existed only within the drawdown zone. The lake should be drafted earlier in the fall, and filled earlier in the spring to improve recruitment from lakeshore spawning. We conducted creel surveys during 1985, and estimated that anglers caught 192,000 kokanee. Anglers harvested 49,200 fish during the ice fishery in Skidoo Bay, 129,000 fish during the summer fishery on the lake, and 13,800 during the fall river fishery. Estimated fishing pressure for the year exceeded 188,000 angler hours. The abundance of mysid shrimp in Flathead Lake, measured at six index stations, increased to 130/mIf in 1986. My&Is increased tenfold from 1984 to 1985, and about threefold from 1985 to 1986. Monitoring of mysid shrimp and zooplankton populations in Flathead Lake is supplementing an investigation of the growth and survival of juvenile kokanee. Kokanee and mysid shrimp feed primarily on planktonic crustaceans. This work was designed to detect a potential decline in kokanee recruitment or growth brought about by competitive interaction with mysid shrimp. Fluctuation in adult kokanee year class strength is in part attributable to the negative effects of hydroelectric dam operation on reproductive success in the main stem Flathead River and in Flathead Lake. Our results show that egg survival in the river has improved in response to sta

  2. Reed Reactor Facility Annual Report

    SciTech Connect (OSTI)

    Frantz, Stephen G.

    2000-09-01T23:59:59.000Z

    This is the report of the operations, experiments, modifications, and other aspects of the Reed Reactor Facility for the year.

  3. Nuclear Power 2010 Program: Combined Construction and Operating...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Power 2010 Program: Combined Construction and Operating License & Design Certification Demonstration Projects Lessons Learned Report Nuclear Power 2010 Program: Combined...

  4. Final report, Ames Mobile Laboratory Project: The development and operation of instrumentation in a mobile laboratory for in situ, real-time screening and characterization of soils using the laser ablation sampling technique

    SciTech Connect (OSTI)

    Anderson, M.S.; Braymen, S.D.

    1995-01-27T23:59:59.000Z

    The main focus of the Ames Laboratory`s Technology Integration Program, TIP, from May 1991 through December 1994 was the development, fabrication, and demonstration of a mobile instrumentation laboratory incorporating rapid in situ sampling systems for safe, rapid, and cost effective soil screening/characterization. The Mobile Demonstration Laboratory for Environmental Screening Technologies, MDLEST, containing the analysis instrumentation, along with surface and subsurface sampling probe prototypes employing the laser ablation sampling technique were chosen to satisfy the particular surface and subsurface soil characterization needs of the various Department of Energy facilities for determining the extent of heavy metal and radionuclide contamination. The MDLEST, a 44 foot long 5th wheel trailer, is easily configured for the analysis instrumentation and sampling system required for the particular site work. This mobile laboratory contains all of the utilities needed to satisfy the operating requirements of the various instrumentation installed. These utilities include, an electric generator, a chilled water system, process gases, a heating/air conditioning system, and computer monitoring and automatic operating systems. Once the MDLEST arrives at the job site, the instrumentation is aligned and calibration is completed, sampling and analysis operations begin. The sample is acquired, analyzed and the results reported in as little as 10 minutes. The surface sampling probe is used in two modes to acquire samples for analysis. It is either set directly on the ground over the site to be sampled, in situ sampling, or in a special fixture used for calibrating the sampling analysis system with standard soil samples, having the samples brought to the MDLEST. The surface sampling probe was used to in situ sample a flat concrete surface (nondestructively) with the ablated sample being analyzed by the instrumentation in the MDLEST.

  5. Occidental vertical modified in situ process for the recovery of oil from oil shale, Phase 2. Construction, operation, testing, and environmental impact. Final report, August 1981-December 1982. Volume 1

    SciTech Connect (OSTI)

    Stevens, A.L.; Zahradnik, R.L.; Kaleel, R.J.

    1984-01-01T23:59:59.000Z

    Occidential Oil Shale, Inc. (OOSI) recently completed the demonstration of mining, rubblization, ignition, and simulataneous processing of two commericalized modified in situ (MIS) retorts at the Logas Wash facility near DeBeque, Colorado. Upon completion of Retort 6 in 1978, Occidential began incorporating all of the knowledge previously acquired in an effort to design two more commercial-sized MIS retorts. Any commercial venture of the future would require the ability to operate simultaneously more than one retort. Thus, Retorts 7 and 8 were developed during 1980 and 1981 through joint funding of the DOE and OOSI in Phase II. Rubblization of the retorts produced an average rubble void of 18.5% in the low grade shale (17 gallons per ton) at the Logan Wash site. After rubblization, bulkheads were constructed, inlet and offgas pipes were installed and connected to surface processing facilities and liquid product handling systems were connected to the retorts. Extensive instrumentation was installed in cooperation with Sandia National Laboratories for monitoring the complete operation of the retorts. After pre-ignition testing, Retort 8 was ignited in December of 1981 and Retort 7 was ignited in January of 1982. The retorts were operated without interruption from ignition until mid- November of 1982 at which time inlet gas injection was terminated and water quenching was begun. Total product yield from the two retorts was approximately 200,000 barrels of oil, or 70% of the Fischer Assay oil-in-place in the rubblized rock in the two retrots. Water quenching studies were conducted over a period of several months, with the objective of determining the rate of heat extraction from the retorts as well as determining the quantity and quality of offgas and water coming out from the quenching process. Data from these studies are also included in this Summary Report. 62 figs., 18 tabs.

  6. System design study to reduce capital and operating costs and bench-scale testing of a circulating-bed AFB advanced concept. Phase 1, Task 2: interim report on Task 1 results

    SciTech Connect (OSTI)

    Fraley, L.D.; Hsiao, K.H.; Lee, M.M.; Lin, Y.Y.; Sadhukhan, P.; Schlossman, M.; Schreiner, W.C.; Solbakken, A.

    1985-08-01T23:59:59.000Z

    The M.W. Kellogg Company has had under consideration for many years a combustor design involving a circulating fluid bed of ash, coal, lime/limestone sorbent, and calcium sulfate. In a previous study for the Department of Energy, M.W. Kellogg performed a design analysis for an atmospheric fluidized-bed combustor whose performance should significantly exceed conventional FBC operation performance, i.e., the Kellogg CFBC. The analysis conclusively showed that the Kellogg CFBC met or exceeded performance criteria for advanced atmospheric FBC's. This is superior to those FBC's currently in the market place. The objective of the study presented here was to reduce capital and operating costs of the Kellogg CFBC, configured into an industrial boiler system of 150,000 pounds per hour steaming capacity. This report presents the design optimization, detailed designs, and cost estimates required to compare CFBC with conventional AFB. The results show the Kellogg CFBC to be a very economical concept. Technically, the Kellogg CFBC can meet or exceed all of the design criteria established for an advanced AFBC. Its compact design resembles an FCC unit in structure and operation. By staged combustion, NO/sub x/ emissions are controlled by the reducing atmosphere and sulfur absorption enhanced in the improved kinetics of the H/sub 2/S-CaO reaction. The unique combustor/riser design keeps the boiler tubes from exposure to corrosive combustion gases, solving the erosion and corrosion problems existing in conventional bubbling-bed AFB. 7 refs., 28 figs., 17 tabs.

  7. SSCL Commissioning and Operations

    SciTech Connect (OSTI)

    NONE

    1992-03-31T23:59:59.000Z

    The SSC, with an energy of 20 TeV/Beam, requires a sequence of individual accelerators of increasing energy in the injector chain. These are the Linac, Low Energy Booster, Medium Energy Booster, and High Energy Booster. Each accelerator system must be completed in sequence in order to provide beam to the next higher energy accelerator. The collider itself is comprised of ten sectors, each of which in terms of superconducting magnet bending strength, is equivalent to two HEB injectors. The completion of all injectors and collider sectors is required before stored beams can circulate in preparation for colliding beam operation. Four experimental halls are planned for the detector systems. Each major detector will be assembled in one of the halls by a world-wide collaboration of scientists. In addition, above ground facilities provide shops and test facilities for accelerator technical systems, superconducting magnet and materials research and development, and for detector assembly and operations. The purpose of this report is to present a plan for the sequential commissioning and operation of these individual accelerators and other technical facilities of the SSC. A central objective of this plan is to describe the activities at the SSCL that are not included as part of the construction project TPC, even though they occur during the overall project construction time-frame. Examples of such activities include the operation of general laboratory facilities and services not specifically related to construction, the operating costs for the individual accelerators in the injector chain once these facilities have been commissioned, and the costs of SSCL physics research groups. The Department of Energy has provided the following decision with regard to these operations categories for the SSCL.

  8. CRADA Final Report For CRADA NO. CR-12-006 [Operation and Testing of an SO{sub 2}-depolarized Electrolyzer (SDE) for the Purpose of Hydrogen and Sulfuric Acid Production

    SciTech Connect (OSTI)

    Summers, W. A.; Colon-Mercado, H. R.; Steimke, J. L.; Zahn, Steffen

    2014-02-24T23:59:59.000Z

    Over the past several years, Savannah River National Laboratory (SRNL) has led a team of collaborators under the Department of Energy’s (DOE) nuclear hydrogen production program to develop the Hybrid Sulfur (HyS) Process. HyS is a 2-step water-splitting process consisting of high temperature decomposition of sulfuric acid to generate SO{sub 2}, followed by the electrolysis of aqueous SO{sub 2} to generate hydrogen and sulfuric acid. The latter is fed back into the high temperature reactor. SRNL designed and built an SO{sub 2}-depolarized electrolyzer (SDE) and a test facility. Over 40 SDE’s were tested using different catalysts, membranes and other components. SRNL demonstrated that an SDE could be operated continuously for approximately 200 hours under certain conditions without buildup of sulfur at the SDE’s cathode, thus solving a key technical problem with SDE technology. Air Products and Chemicals, Inc. (APCI) is a major supplier of hydrogen production systems, and they have proprietary technology that could benefit from the SDE developed by SRNS, or some improved version thereof. However, to demonstrate that SRNL’s SDE is a truly viable approach to the electrolyzer design, continuous operation for far greater periods of time than 200 hours must be demonstrated, and the electrolyzer must be scaled up to greater hydrogen production capacities. SRNL and Air Products entered into a Cooperative Research and Development Agreement with the objective of demonstrating the effectiveness of the SDE for hydrogen and sulfuric acid production and to demonstrate long-term continuous operation so as to dramatically increase the confidence in the SDE design for commercial operation. SRNL prepared a detailed technical report documenting previous SDE development, including the current SDE design and operating conditions that led to the 200-hour sulfurfree testing. SRNL refurbished its single cell SDE test facility and qualified the equipment for continuous operation. A new membrane electrode assembly (MEA) was fabricated and installed in the single cell electrolyzer (60 cm{sup 2} active cell area). Shakedown testing was conducted, and several modifications were made to the test facility equipment. Seven different MEAs were used during testing. Beginning on May 20, 2013, SRNL was able to test the SDE continuously for 1200 hours, including 1000 hours under power to generate hydrogen at an average rate of 10.8 liters per hour. The SDE was not removed or repaired during the 50-day test and was successfully restarted after each shutdown. The test was intentionally stopped after 1200 hours (1000 hours of hydrogen production) due to funding constraints. Post-test examination of the MEA using Scanning Electron Microscopy (SEM) and Energy Dispersive X-ray Microanalysis (EDAX) showed no elemental sulfur deposits or sulfur layer inside the cell, thus successfully achieving the test goals. The results demonstrated that the SDE could be operated for extended periods without major performance degradation or the buildup of sulfur inside the MEA. Air Products conducted an assessment of the economic viability of the SDE based on the “as tested” design. The results indicated that the SDE faces significant economic obstacles in its current state. Further development and scale-up are necessary before the SDE is ready for commercialization.

  9. Reactor operation safety information document

    SciTech Connect (OSTI)

    Not Available

    1990-01-01T23:59:59.000Z

    The report contains a reactor facility description which includes K, P, and L reactor sites, structures, operating systems, engineered safety systems, support systems, and process and effluent monitoring systems; an accident analysis section which includes cooling system anomalies, radioactive materials releases, and anticipated transients without scram; a summary of onsite doses from design basis accidents; severe accident analysis (reactor core disruption); a description of operating contractor organization and emergency planning; and a summary of reactor safety evolution. (MB)

  10. Occurrence Reporting and Processing of Operations Information

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1995-09-25T23:59:59.000Z

    This Manual provides detailed requirements to supplement DOE O 232.1. Canceled by DOE M 232.1-1A dated 07/21/1997

  11. Occurrence Reporting and Processing of Operations Information

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2011-08-30T23:59:59.000Z

    The order promotes organizational learning consistent with DOE’s Integrated Safety Management System goal of enhancing mission safety, and sharing effective practices to support continuous improvement and adaptation to change.

  12. Cell Reports Operator Sequence Alters Gene Expression

    E-Print Network [OSTI]

    Phillips, Rob

    ,8 Jeff Gelles,4,* Jane Kondev,5,* and Rob Phillips2,* 1Department of Physics 2Department of Applied: gelles@brandeis.edu (J.G.), kondev@brandeis.edu (J.K.), phillips@pboc.caltech.edu (R.P.) http

  13. ARM Operations Quarterly Report - April - June 2012

    SciTech Connect (OSTI)

    Voyles, JW

    2012-07-18T23:59:59.000Z

    Individual raw datastreams from instrumentation at the Atmospheric Radiation Measurement (ARM) Climate Research Facility fixed and mobile sites are collected and sent to the Data Management Facility (DMF) at Pacific Northwest National Laboratory (PNNL) for processing in near real-time. Raw and processed data are then sent approximately daily to the ARM Data Archive, where they are made available to the research community. For each instrument, we calculate the ratio of the actual number of processed data records received daily at the Archive to the expected number of data records. The results are tabulated by (1) individual datastream, site, and month for the current year and (2) site and fiscal year (FY) dating back to 1998.

  14. Independent Activity Report, Hanford Operations Office - July...

    Broader source: Energy.gov (indexed) [DOE]

    2010 Joint Assessment of the Effectiveness of Corrective Actions for the Building 336 Accident The U.S. Department of Energy, Office of Independent Oversight, within the Office of...

  15. Hazard Analysis Reports for Nuclear Explosive Operations

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy ChinaofSchaefer To:Department of Energy Completing theWhiz! |Nearly six weeks

  16. Distributed Generation Operational Reliability, Executive Summary Report,

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't Your Destiny:Revised Finding of No53197E T ADRAFTJanuary 2004 | DepartmentJanuary 2004 |

  17. FLORIDA ATLANTIC UNIVERSITY 2004-2005 UNIVERSITY OPERATING BUDGET

    E-Print Network [OSTI]

    Fernandez, Eduardo

    1 FLORIDA ATLANTIC UNIVERSITY 2004-2005 UNIVERSITY OPERATING BUDGET JULY 1, 2004 TO DECEMBER 31, 2004 SECOND QUARTER REPORT Educational and General Operating Budget Student Financial Aid Operating Budget Grants and Contracts-Sponsored Research Operating Budget Auxiliary Enterprises Operating Budget

  18. FLORIDA ATLANTIC UNIVERSITY 2004-2005 UNIVERSITY OPERATING BUDGET

    E-Print Network [OSTI]

    Fernandez, Eduardo

    1 FLORIDA ATLANTIC UNIVERSITY 2004-2005 UNIVERSITY OPERATING BUDGET JULY 1, 2004 TO MARCH 31, 2005 THIRD QUARTER REPORT Educational and General Operating Budget Student Financial Aid Operating Budget Grants and Contracts-Sponsored Research Operating Budget Auxiliary Enterprises Operating Budget Athletics

  19. FLORIDA ATLANTIC UNIVERSITY 2004-2005 UNIVERSITY OPERATING BUDGET

    E-Print Network [OSTI]

    Fernandez, Eduardo

    FLORIDA ATLANTIC UNIVERSITY 2004-2005 UNIVERSITY OPERATING BUDGET JULY 1, 2004 TO SEPTEMBER 30, 2004 FIRST QUARTER REPORT Educational and General Operating Budget Student Financial Aid Operating Budget Grants and Contracts-Sponsored Research Operating Budget Auxiliary Enterprises Operating Budget

  20. FLORIDA ATLANTIC UNIVERSITY 2008-09 UNIVERSITY OPERATING BUDGET

    E-Print Network [OSTI]

    Fernandez, Eduardo

    1 FLORIDA ATLANTIC UNIVERSITY 2008-09 UNIVERSITY OPERATING BUDGET JULY 1, 2008 TO DECEMBER 31, 2008 SECOND QUARTER REPORT Educational and General Operating Budget Student Financial Aid Operating Budget Grants and Contracts-Sponsored Research Operating Budget Auxiliary Enterprises Operating Budget Athletics

  1. FLORIDA ATLANTIC UNIVERSITY 2005-2006 UNIVERSITY OPERATING BUDGET

    E-Print Network [OSTI]

    Fernandez, Eduardo

    1 FLORIDA ATLANTIC UNIVERSITY 2005-2006 UNIVERSITY OPERATING BUDGET JULY 1, 2005 TO DECEMBER 31, 2005 SECOND QUARTER REPORT Educational and General Operating Budget Student Financial Aid Operating Budget Grants and Contracts-Sponsored Research Operating Budget Auxiliary Enterprises Operating Budget

  2. FLORIDA ATLANTIC UNIVERSITY 2010-11 UNIVERSITY OPERATING BUDGET

    E-Print Network [OSTI]

    Fernandez, Eduardo

    1 FLORIDA ATLANTIC UNIVERSITY 2010-11 UNIVERSITY OPERATING BUDGET JULY 1, 2010 TO DECEMBER 31, 2010 SECOND QUARTER REPORT Educational and General Operating Budget Student Financial Aid Operating Budget Grants and Contracts-Sponsored Research Operating Budget Auxiliary Enterprises Operating Budget

  3. FLORIDA ATLANTIC UNIVERSITY 2008-09 UNIVERSITY OPERATING BUDGET

    E-Print Network [OSTI]

    Fernandez, Eduardo

    1 FLORIDA ATLANTIC UNIVERSITY 2008-09 UNIVERSITY OPERATING BUDGET JULY 1, 2008 TO SEPTEMBER 30, 2008 FIRST QUARTER REPORT Educational and General Operating Budget Student Financial Aid Operating Budget Grants and Contracts-Sponsored Research Operating Budget Auxiliary Enterprises Operating Budget

  4. FLORIDA ATLANTIC UNIVERSITY 2005-2006 UNIVERSITY OPERATING BUDGET

    E-Print Network [OSTI]

    Fernandez, Eduardo

    1 FLORIDA ATLANTIC UNIVERSITY 2005-2006 UNIVERSITY OPERATING BUDGET JULY 1, 2005 TO MARCH 15, 2006 THIRD QUARTER REPORT Educational and General Operating Budget Student Financial Aid Operating Budget Grants and Contracts-Sponsored Research Operating Budget Auxiliary Enterprises Operating Budget Athletics

  5. FLORIDA ATLANTIC UNIVERSITY 2007-2008 UNIVERSITY OPERATING BUDGET

    E-Print Network [OSTI]

    Fernandez, Eduardo

    1 FLORIDA ATLANTIC UNIVERSITY 2007-2008 UNIVERSITY OPERATING BUDGET JULY 1, 2007 TO MARCH 31, 2008 THIRD QUARTER REPORT Educational and General Operating Budget Student Financial Aid Operating Budget Grants and Contracts-Sponsored Research Operating Budget Auxiliary Enterprises Operating Budget Athletics

  6. FLORIDA ATLANTIC UNIVERSITY 2007-2008 UNIVERSITY OPERATING BUDGET

    E-Print Network [OSTI]

    Fernandez, Eduardo

    1 FLORIDA ATLANTIC UNIVERSITY 2007-2008 UNIVERSITY OPERATING BUDGET JULY 1, 2007 TO DECEMBER 31, 2007 SECOND QUARTER REPORT Educational and General Operating Budget Student Financial Aid Operating Budget Grants and Contracts-Sponsored Research Operating Budget Auxiliary Enterprises Operating Budget

  7. FLORIDA ATLANTIC UNIVERSITY 2007-2008 UNIVERSITY OPERATING BUDGET

    E-Print Network [OSTI]

    Fernandez, Eduardo

    1 FLORIDA ATLANTIC UNIVERSITY 2007-2008 UNIVERSITY OPERATING BUDGET JULY 1, 2007 TO SEPTEMBER 30, 2007 FIRST QUARTER REPORT Educational and General Operating Budget Student Financial Aid Operating Budget Grants and Contracts-Sponsored Research Operating Budget Auxiliary Enterprises Operating Budget

  8. FLORIDA ATLANTIC UNIVERSITY 2005-2006 UNIVERSITY OPERATING BUDGET

    E-Print Network [OSTI]

    Fernandez, Eduardo

    1 FLORIDA ATLANTIC UNIVERSITY 2005-2006 UNIVERSITY OPERATING BUDGET JULY 1, 2005 TO SEPTEMBER 30, 2005 FIRST QUARTER REPORT Educational and General Operating Budget Student Financial Aid Operating Budget Grants and Contracts-Sponsored Research Operating Budget Auxiliary Enterprises Operating Budget

  9. e Ecologica ated 10/26/2

    E-Print Network [OSTI]

    Baltisberger, Jay H.

    .......................................................................................... 14 SENS House ...................................................................................... 20 #12;INTRODUCTION With the ecological renovation of several campus buildings, the creation

  10. Chroma ATE Inc | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page onYou are now leaving Energy.gov You are now leaving Energy.gov You are beingZealand JumpConceptual Model, click here.TelluricPower International NewOklahoma:Christine,

  11. VICE PRESIDENT FINANCE, RESOURCES & OPERATIONS

    E-Print Network [OSTI]

    Handy, Todd C.

    VICE PRESIDENT FINANCE, RESOURCES & OPERATIONS PIERRE OUILLET EA to VP Carolina Cerna ASSOCIATE VP ADMINISTRATION & FINANCE OKANAGAN CAMPUS Jackie Podger Michael Shakespeare (Interim) ASSOCIATE VP CAMPUS Dennis Silva FINANCE UBCO Carla Waters FINANCE UBCO Carla Waters BUDGET AND MGMT REPORTING Andrew Glynn

  12. Independent Activity Report, Sandia National Laboratories - September...

    Broader source: Energy.gov (indexed) [DOE]

    September 2012 Operational Awareness Oversight of Sandia National Laboratories HIAR SNL-2012-09-13 This Independent Activity Report documents an operational awareness activity...

  13. Independent Activity Report, West Valley Demonstration Project...

    Broader source: Energy.gov (indexed) [DOE]

    July 2012 Operational Awareness Oversight of the West Valley Demonstration Project HIAR WVDP-2012-07-30 This Independent Activity Report documents an operational awareness...

  14. Remedial Investigation Report on Chestnut Ridge Operable Unit 2 (Filled Coal Ash Pond/Upper McCoy Branch) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Volume 1. Main Text

    SciTech Connect (OSTI)

    Not Available

    1994-08-01T23:59:59.000Z

    This document is a report on the remedial investigation (RI) of Chestnut Ridge Operable Unit (OU) 2 at the Oak Ridge Y-12 Plant. Chestnut Ridge OU 2 consists of Upper McCoy Branch (UMB), the Filled Coal Ash Pond (FCAP), and the area surrounding the Sluice Channel formerly associated with coal ash disposal in the FCAP. Chestnut Ridge OU 2 is located within the U.S. Department of Energy`s (DOE`s) Oak Ridge Reservation in Anderson County, Tennessee, approximately 24 miles west of Knoxville. The pond is an 8.5-acre area on the southern slope of Chestnut Ridge, 0.5 mile south of the main Y-12 Plant and geographically separated from the Y-12 Plant by Chestnut Ridge. The elevation of the FCAP is {approximately} 950 ft above mean sea level (msl), and it is relatively flat and largely vegetated. Two small ponds are usually present at the northeast and northwest comers of the FCAP. The Sluice Channel Area extends {approximately}1000 ft from the northern margin of the FCAP to the crest of Chestnut Ridge, which has an elevation of {approximately}1100 ft above msl. The Sluice Channel Area is largely vegetated also. McCoy Branch runs from the top of Chestnut Ridge across the FCAP into Rogers Quarry and out of the quarry where it runs a short distance into Milton Hill Lake at McCoy Embayment, termed UMB. The portion south of Rogers Quarry, within Chestnut Ridge OU 4, is termed Lower McCoy Branch. The DOE Oak Ridge Y-12 Plant disposed of coal ash from its steam plant operations as a slurry that was discharged into an ash retention impoundment; this impoundment is the FCAP. The FCAP was built in 1955 to serve as a settling basin after coal ash slurried over Chestnut Ridge from the Y-12 Plant. The FCAP was constructed by building an earthen dam across the northern tributary of McCoy Branch. The dam was designed to hold 20 years of Y-12 steam plant ash. By July 1967, ash had filled up the impoundment storage behind the dam to within 4 ft of the top.

  15. Technical Report Documentation Page 1. Report No.

    E-Print Network [OSTI]

    currently has 41 short line railroads that operate on more than 2,600 miles of track, which represents for many rural agriculture communities. Texas currently has 41 short line railroads that operate on more No. 3. Recipient's Catalog No. 5. Report Date October 2006 4. Title and Subtitle IMPORTANCE OF SHORT

  16. Organic solvent topical report

    SciTech Connect (OSTI)

    Cowley, W.L.

    1998-04-30T23:59:59.000Z

    This report is the technical basis for the accident and consequence analyses used in the Hanford Tank Farms Basis for Interim Operation. The report also contains the scientific and engineering information and reference material needed to understand the organic solvent safety issue. This report includes comments received from the Chemical Reactions Subcommittee of the Tank Advisory Panel.

  17. Operations and compositions in transrecursive operators

    SciTech Connect (OSTI)

    Burgin, M.S.; Borodyanskii, Yu.M.

    1995-03-01T23:59:59.000Z

    The present study is a continuation of a study focusing on introduction and analysis of operations on transrecursive operators, which are similar to the operators considered in the theory of algorithms. Such operations may be standard product of algorithms) or special ({alpha}-disjunction and {alpha}-iteration. In some respects, these operations in the class of transrecursive operators are similar to their traditional analogs. In other respects, however, they are essentially different. For instance, they may have different types and modes. Specific features of operations on transrecursive operators are attributable to explicit omission of some restrictions on their construction compared with the construction of algorithms. The standard approaches to mathematical modeling of the concept of algorithm assume a number of essential restrictions. Specifically, they assume finiteness of (1) the input data arriving during a finite time interval; (2) the list of rules underlying the operations of the algorithm; (3) the transformations executed by a single operation; (4) the description of each rule; (5) the time to execute one operation; (6) the time to execute one operation; (7) the number of cycles that the algorithm executes in order to realize the mapping. In application to Turing machines, these restrictions imply finiteness of the initial word, finiteness of the command table of the read head, and ultimate stopping when the result is obtained after finitely many steps. Various classes of transrecursive operators are constructed by dropping various combinations of the {open_quotes}finiteness{close_quotes} restrictions. Two classes of transrecursive operators - the limit (inductive) Turing machines and transalgorithms - have been obtained by dropping respectively the assumption of finiteness of the number of execution cycles and the assumption of finiteness of the list of rules.

  18. National Synchrotron Light Source guidelines for the conduct of operations

    SciTech Connect (OSTI)

    Fewell, N.

    1990-03-01T23:59:59.000Z

    This report briefly discusses the following topics: NSLS operations organization and administration; shift routines and operating practices; NSLS control room activities; communications; control of on-shift training; investigation of abnormal events; notifications; control of equipment and system status; lock-out tagout; independent verification; logkeeping; shift turnover; required reading; shift orders; equipment operations guides; operator aid postings; and equipment labeling.

  19. Environmental Management Performance Report 11/1999

    SciTech Connect (OSTI)

    EDER, D.M.

    2000-02-01T23:59:59.000Z

    The purpose of the Environmental Management Performance Report (EMPR) is to provide the Department of Energy Richland Operations Office's (DOE-RL's) report of Hanford's Environmental Management performance by: US Department of Energy, Richland Operation

  20. Operating Permits (New Jersey)

    Broader source: Energy.gov [DOE]

    The owner or operator of a facility subject to this article shall obtain and maintain an operating permit for the facility. The owner or operator of a facility subject to this article shall ensure...

  1. Cogeneration Operational Issues

    E-Print Network [OSTI]

    Williams, M.

    operations. Other operational issues also include utility transmission planning, generation planning and fuel mix decisions. All of these operational problems have an impact on the ratepayer in regard to quality of electric service and future rates. Both...

  2. Heat Transfer Operators Associated with Quantum Operations

    E-Print Network [OSTI]

    Ç. Aksak; S. Turgut

    2011-04-14T23:59:59.000Z

    Any quantum operation applied on a physical system is performed as a unitary transformation on a larger extended system. If the extension used is a heat bath in thermal equilibrium, the concomitant change in the state of the bath necessarily implies a heat exchange with it. The dependence of the average heat transferred to the bath on the initial state of the system can then be found from the expectation value of a hermitian operator, which is named as the heat transfer operator (HTO). The purpose of this article is the investigation of the relation between the HTOs and the associated quantum operations. Since, any given quantum operation on a system can be realized by different baths and unitaries, many different HTOs are possible for each quantum operation. On the other hand, there are also strong restrictions on the HTOs which arise from the unitarity of the transformations. The most important of these is the Landauer erasure principle. This article is concerned with the question of finding a complete set of restrictions on the HTOs that are associated with a given quantum operation. An answer to this question has been found only for a subset of quantum operations. For erasure operations, these characterizations are equivalent to the generalized Landauer erasure principle. For the case of generic quantum operations however, it appears that the HTOs obey further restrictions which cannot be obtained from the entropic restrictions of the generalized Landauer erasure principle.

  3. Building Operator Certification

    E-Print Network [OSTI]

    Lilley, D.

    2013-01-01T23:59:59.000Z

    Building Operator Certification Energy Efficiency through Operator Training CATEE December 18, 2013 – San Antonio, TX Dennis Lilley, CEM, PMP ESL-KT-13-12-49 CATEE 2013: Clean Air Through Energy Efficiency Conference, San Antonio, Texas Dec. 16...-18 Building Operator Certification Energy Efficiency through Operator Training What is Building Operator Certification? Industry-recognized credential in energy efficient building operation practices Created with 100 industry experts Launched in 1996 9...

  4. Operation and Maintenance

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations and Maintenance Operations OASIS: WALC-DSW (Note: this site is not hosted by Western and requires a digital certificate and login for full access.) Contact Information...

  5. Operations Information for Studies

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations Information for Studies This page contains historical information about hydropower operations. Reclamation UC Region 24-Month Studies FY2009 Load Information (pdf) SLIP...

  6. Operations Cost Allocation Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations Consolidation Project Operations Consolidation Project (OCP) Cost Allocation Presentation - September 20, 2011 OCP Cost Allocation Customer Presentation List of Acronyms...

  7. Operations Research Analyst

    Broader source: Energy.gov [DOE]

    The incumbent in this position will serve as an Operations Research Analyst in the Generation Scheduling (PGS). The Operations Research Analyst is responsible for analytical work that involves...

  8. Technical Report Documentation Page 1. Report No.

    E-Print Network [OSTI]

    Texas at Austin, University of

    Technical Report Documentation Page 1. Report No. FHWA/TX-04/0-4266-2 2. Government Accession No. 3 significant changes in traffic operation and safety. A review of the design standard documents shows Statement No restrictions. This document is available to the public through the National Technical

  9. Technical Report Documentation Page 1. Report No.

    E-Print Network [OSTI]

    Texas at Austin, University of

    Technical Report Documentation Page 1. Report No. FHWA/TX-10/0-6655-CT-1 2. Government Accession No presents four documents created by the TxDOT Multi-Tier Pavement Management Workgroup. 17. Key Words System Operation, Preservation Optimization 18. Distribution Statement No restrictions. This document is available

  10. Site Environmental Report for 2008, Volume 1

    E-Print Network [OSTI]

    Lackner, Regina

    2009-01-01T23:59:59.000Z

    Joint Genome Institute in Walnut Creek, California Chapter 3 Site Environmental Report for 2008 Berkeley Lab continued operating

  11. Independent Oversight Activity Report, Hanford Sludge Treatment...

    Office of Environmental Management (EM)

    Project Engineered Container Retrieval and Transfer System Preliminary Documented Safety Analysis, Revision 00 - April 2015 Independent Activity Report, Richland Operations...

  12. Reply: Davies et al. (2012), Hydraulic fractures: How far can they go? Richard J. Davies a,*, Gillian R. Foulger a

    E-Print Network [OSTI]

    Foulger, G. R.

    2012-01-01T23:59:59.000Z

    propagating stimulated hydraulic fractures, gener- ated by fracking operations for gas and oil exploitation

  13. A cask fleet operations study

    SciTech Connect (OSTI)

    Not Available

    1988-03-01T23:59:59.000Z

    This document describes the cask fleet currently available to transport spent nuclear fuels. The report describes the proposed operational procedures for these casks and the vehicles intended to transport them. Included are techniques for loading the cask, lifting it onto the transport vehicle, preparing the invoices, and unloading the cask at the destination. The document concludes with a discussion on the maintenance and repair of the casks. (tem) 29 figs.

  14. Reed Reactor Facility. Final report

    SciTech Connect (OSTI)

    Frantz, S.G.

    1994-12-31T23:59:59.000Z

    This report discusses the operation and maintenance of the Reed Reactor Facility. The Reed reactor is mostly used for education and train purposes.

  15. Operational Awareness Oversight of the Portsmouth/Paducah Project...

    Energy Savers [EERE]

    Evaluations Activity Report for Operational Awareness Oversight of the PortsmouthPaducah Project Office (PPPO) Performance of the Contractor Assurance System (CAS) Program...

  16. Model Predictive Control for the Operation of Building Cooling Systems

    E-Print Network [OSTI]

    Ma, Yudong

    2010-01-01T23:59:59.000Z

    storage in building cooling systems. Technical report,storage in building cooling systems. Decision and Control,for the Operation of Building Cooling Systems Yudong Ma ? ,

  17. NUCLEAR PLANT OPERATIONS AND

    E-Print Network [OSTI]

    Pázsit, Imre

    NUCLEAR PLANT OPERATIONS AND CONTROL KEYWORDS: neutron flux, cur- rent noise, vibration diagnostics: Swedish Nuclear Powe

  18. OPERATIONS MANAGEMENT Spring 2008

    E-Print Network [OSTI]

    Almor, Amit

    the operations and supply chain strategy. This survey course in operations management introduces students1 MGSC 395 OPERATIONS MANAGEMENT Spring 2008 Course Syllabus Instructor: Professor Anand Nair Class MATERIALS Required Text Books Textbook: Krajewski, Lee, Ritzman, Larry, and Malhotra, Manoj. Operations

  19. Report on System operation A background report prepared by the Nordel Operation

    E-Print Network [OSTI]

    /OPG in the Nordel project on Enhancing efficient functioning of the Nordic electricity market 21 December 2004 #12 AND EDUCATION.................................................................................... 10 #12;3 1 between these will provide the technical prerequisites for trading of power on an open electricity market. T

  20. Operator pencil passing through a given operator

    SciTech Connect (OSTI)

    Biggs, A., E-mail: khudian@manchester.ac.uk, E-mail: adam.biggs@student.manchester.ac.uk; Khudaverdian, H. M., E-mail: khudian@manchester.ac.uk, E-mail: adam.biggs@student.manchester.ac.uk [School of Mathematics, University of Manchester, Oxford Road, Manchester M13 9PL (United Kingdom)

    2013-12-15T23:59:59.000Z

    Let ? be a linear differential operator acting on the space of densities of a given weight ?{sub 0} on a manifold M. One can consider a pencil of operators ?-circumflex(?)=(?{sub ?}) passing through the operator ? such that any ?{sub ?} is a linear differential operator acting on densities of weight ?. This pencil can be identified with a linear differential operator ?-circumflex acting on the algebra of densities of all weights. The existence of an invariant scalar product in the algebra of densities implies a natural decomposition of operators, i.e., pencils of self-adjoint and anti-self-adjoint operators. We study lifting maps that are on one hand equivariant with respect to divergenceless vector fields, and, on the other hand, with values in self-adjoint or anti-self-adjoint operators. In particular, we analyze the relation between these two concepts, and apply it to the study of diff?(M)-equivariant liftings. Finally, we briefly consider the case of liftings equivariant with respect to the algebra of projective transformations and describe all regular self-adjoint and anti-self-adjoint liftings. Our constructions can be considered as a generalisation of equivariant quantisation.

  1. Long-Term Surveillance Operations and Maintenance Fiscal Year...

    Office of Environmental Management (EM)

    3 Year-End Summary Report Long-Term Surveillance Operations and Maintenance Fiscal Year 2013 Year-End Summary Report LTS-O&M is at the core of LM efforts to fulfill a strategy that...

  2. Factory Flow Benchmarking Report

    E-Print Network [OSTI]

    Shields, Thomas J.

    LAI benchmarked representative part fabrications and some assembly operations within its member companies of the defense aircraft industry. This paper reports the results of this benchmarking effort. In addition, this ...

  3. Internet Polling Development Report

    E-Print Network [OSTI]

    Klima, P.; Lockhart, D.; Haberl, J. S.

    2001-01-01T23:59:59.000Z

    This is the final report which documents the development of Internet-based data logger polling. The project consists of two main tasks: the development of automated polling procedures that can be launched remotely with no operator input...

  4. Storage Ring Operation Modes

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Longitudinal bunch profile and Up: APS Storage Ring Parameters Previous: Source Parameter Table Storage Ring Operation Modes Standard Operating Mode, top-up Fill pattern: 102 mA in...

  5. Aerosol Sampler Operations Manual

    E-Print Network [OSTI]

    Fischer, Emily V.

    -1123 Laboratory FAX (916) 752-4107 Standard Operating Procedures Technical Information Document TI 201A #12;TI 201.................................................................................................................................................. 3 1.0 Weekly Maintenance ProceduresIMPROVE Aerosol Sampler Operations Manual February 10, 1997 Air Quality Group Crocker Nuclear

  6. Climate Data Operators (CDO)

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Climate Data Operators (CDO) Climate Data Operators (CDO) Description and Overview CDO is a large tool set for working on climate data. NetCDF 34, GRIB including SZIP compression,...

  7. Assessment of the O2Diesel Operational Safety Program: December 23, 2002 -- June 30, 2007

    SciTech Connect (OSTI)

    TIAX LLC

    2006-06-01T23:59:59.000Z

    This report assesses O2Diesel's operational safety program using its ethanol-diesel blended fuel product.

  8. U-208: HP Operations Agent Bugs Let Remote Users Execute Arbitrary Code

    Broader source: Energy.gov [DOE]

    Two vulnerabilities were reported in HP Operations Agent. A remote user can execute arbitrary code on the target system

  9. SWPF Crane Lift Operation

    SciTech Connect (OSTI)

    None

    2010-01-01T23:59:59.000Z

    A multiple vview shot of the SWPF crane lift operation at the Savannah River Site. Funded by the Recovery Act.

  10. Coal transfer: can an environmentally safe coal transfer operation be undertaken in the lower Delaware Bay. Delaware Estuary situation report. [Dusts from transport of coal from barges to colliers

    SciTech Connect (OSTI)

    Biggs, R.B.; Sharp, J.H.; Manus, A.T.; Wypyszinski, A.W.

    1983-01-01T23:59:59.000Z

    Effective August 1983, the U.S. Coast Guard authorized coal transfer between vessels moored in Anchorage Area A, off Big Stone Beach in lower Delaware Bay. Two general methods may be used to transfer coal from shallow-draft barges to deep-draft colliers: auger or conveyor-belt operation and clamshell operation. Although dust emission is inherent in coal transfer, best available data from similar situations indicate dust emission can vary from 0.168 pounds per ton for clamshell to 0.0024 pounds per ton for auger/conveyor transfer. Air quality and bottom water deterioration are the major potential environmental impacts.

  11. Top 100 Operators: Proved Reserves and Production, Operated vs...

    Annual Energy Outlook 2013 [U.S. Energy Information Administration (EIA)]

    Top 100 Operators: Proved Reserves and Production, Operated vs Owned, 2009 1 Top 100 Operators: Proved Reserves and Production, Operated vs Owned, 2009 The operator of an oil or...

  12. Courses: Nursing (NURS) Page 367Sonoma State University 2013-2014 Catalog nurS 313 BACCALAureAte nurSing perSpeCtiVeS ii (4)

    E-Print Network [OSTI]

    Ravikumar, B.

    goals of current health care system reform including nursing¿s expanded professional role in promoting health and mitigating health care disparities and inequities. Prerequisites are admission to the nursing, and communities. Determinants of health and operations of the health care system will be discussed

  13. Independent Activity Report, Pantex Plant - October 2011 | Department...

    Broader source: Energy.gov (indexed) [DOE]

    Plant Operational Awareness Site Visit HIAR PTX-2011-10-28 This Independent Activity Report documents an operational awareness activity conducted by Office of Health, Safety and...

  14. Remedial Investigation Report on Bear Creek Valley Operable Unit 2 (Rust Spoil Area, Spoil Area 1, and SY-200 Yard) at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee. Volume 1, Main text

    SciTech Connect (OSTI)

    NONE

    1995-01-01T23:59:59.000Z

    This report on the BCV OU 2 at the Y-12 Plant, was prepared in accordance with requirements under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) for reporting the results of a site characterization for public review. It provides the Environmental Restoration Program with information about the results of the 1993 investigation. It includes information on risk assessments that have evaluated impacts to human health and the environment. Field activities included collection of subsurface soil samples, groundwater and surface water samples, and sediments and seep at the Rust Spoil Area (RSA), SY-200 Yard, and SA-1.

  15. Cask fleet operations study

    SciTech Connect (OSTI)

    Not Available

    1988-01-01T23:59:59.000Z

    The Nuclear Waste Policy Act of 1982 assigned to the Department of Energy's (DOE) Office of Civilian Waste Management the responsibility for disposing of high-level waste and spent fuel. A significant part of that responsibility involves transporting nuclear waste materials within the federal waste management system; that is, from the waste generator to the repository. The lead responsibility for transportation operations has been assigned to Oak Ridge Operations, with Oak Ridge National Laboratory (ORNL) providing technical support through the Transportation Operations Support Task Group. One of the ORNL support activities involves assessing what facilities, equipment and services are required to assure that an acceptable, cost-effective and safe transportation operations system can be designed, operated and maintained. This study reviews, surveys and assesses the experience of Nuclear Assurance Corporation (NAC) in operating a fleet of spent-fuel shipping casks to aid in developing the spent-fuel transportation system.

  16. Generalized computer-assisted operations; A comprehensive system for day-to-day oilfield operations

    SciTech Connect (OSTI)

    Dunham, C.L.; Anderson, S.R. (Shell Oil Co. (US))

    1991-03-01T23:59:59.000Z

    This paper reports that Shell Oil Co. and a U.S. subsidiary, Shell Western E and P Inc., developed a comprehensive, generalized, computer-assisted-operations (CAO) system for day-to-day oilfield operations. The system addresses many of the daily operating needs of data acquisition, well and facility monitoring and control, problem detection and diagnosis, design and/or redesign of artificial-lift systems, and oilfield data management. It is generalized in that one system, with common computer hardware, software, and techniques, serves several different oil fields with diverse operating requirements and conditions.

  17. HQ- Human Resources Operations

    Broader source: Energy.gov [DOE]

    HQs Human Recources Operations delivers services, including position management, recruitment, staffing and classification, and reduction in force at Headquarters.  Click the "Contacts" Link to find...

  18. Hyponormality of Toeplitz Operators

    E-Print Network [OSTI]

    1910-40-52T23:59:59.000Z

    Amer. Math. Soc. 82(1976), 494-496. [12] S. C. Power. Hankel Operators on Hilbert Space, Pitman, Boston, 1982. [13] D. Sarason. Generalized interpolation in H.

  19. Spectral Operators of Matrices

    E-Print Network [OSTI]

    2014-01-10T23:59:59.000Z

    Jan 10, 2014 ... a thorough study on a new class of matrix valued functions, coined as spectral operators of ..... not self-adjoint. ...... 9 (1981) 1135–1151.

  20. Pipeline Operations Program (Louisiana)

    Broader source: Energy.gov [DOE]

    The Pipeline Operations Program regulates the construction, acquisition, abandonment and interconnection of natural gas pipelines, as well as, the transportation and use of natural gas supplies.

  1. Stack Monitor Operating Experience Review

    SciTech Connect (OSTI)

    L. C. Cadwallader; S. A. Bruyere

    2009-05-01T23:59:59.000Z

    Stack monitors are used to sense radioactive particulates and gases in effluent air being vented from rooms of nuclear facilities. These monitors record the levels and types of effluents to the environment. This paper presents the results of a stack monitor operating experience review of the U.S. Department of Energy (DOE) Occurrence Reporting and Processing System (ORPS) database records from the past 18 years. Regulations regarding these monitors are briefly described. Operating experiences reported by the U.S. DOE and in engineering literature sources were reviewed to determine the strengths and weaknesses of these monitors. Electrical faults, radiation instrumentation faults, and human errors are the three leading causes of failures. A representative “all modes” failure rate is 1E-04/hr. Repair time estimates vary from an average repair time of 17.5 hours (with spare parts on hand) to 160 hours (without spare parts on hand). These data should support the use of stack monitors in any nuclear facility, including the National Ignition Facility and the international ITER project.

  2. Ordered involutive operator spaces

    E-Print Network [OSTI]

    Blecher, David P; Neal, Matthew; Werner, Wend

    2007-01-01T23:59:59.000Z

    This is a companion to recent papers of the authors; here we construct the `noncommutative Shilov boundary' of a (possibly nonunital) selfadjoint ordered space of Hilbert space operators. The morphisms in the universal property of the boundary preserve order. As an application, we consider `maximal' and `minimal' unitizations of such ordered operator spaces.

  3. Operations Research + Information Engineering

    E-Print Network [OSTI]

    Keinan, Alon

    and the equipment they operate to perform most efficiently. The allocation of resources may be represented of the techniques and modeling concepts needed to analyze and design complex systems. As an operations researcher. All business systems are complex and need sophisticated decision-making methods that enable employees

  4. Humanitarian Operations Pinar Keskinocak

    E-Print Network [OSTI]

    Li, Mo

    1 Humanitarian Operations Pinar Keskinocak H. Milton Stewart School of Industrial & Systems for Allocating Urban Emergency Units: A Survey Larson (1972), Urban Police Patrol Analysis Larson and Odoni (1981), Urban Operations Research Jones and Eden (1981), O.R. in the Community Pollock, Rothkopf, Barnett (1994

  5. Data Management Group Annual Report

    E-Print Network [OSTI]

    Toronto, University of

    Data Management Group Annual Report 1997 #12;Data Management Group Annual Report 1997 A co-operative project that is jointly funded by members of the Toronto Area Transportation Planning Data Collection: (416) 978-3941 #12;Data Management Group 1997 Annual Report Table of Contents 1 INTRODUCTION

  6. Hydrogen Deployment System Modeling Environment (HyDS ME) Documentation: Milestone Report FY 2006

    SciTech Connect (OSTI)

    Parks. K.

    2006-11-01T23:59:59.000Z

    This report introduces the Hydrogen Deployment System Modeling Environment model, assumptions, and basic operations.

  7. Final Report

    SciTech Connect (OSTI)

    Yelton, John Martin [UF; Mitselmakher, Guenakh [UF; Korytov, Andrey [UF; Avery, Paul [UF; Furic, Ivan [UF; Acosta, Darin [UF; Konigsberg, Jacobo [UF; Field, Richard [UF; Matchev, Konstantin [UF; Ramond, Pierre [UF; Thorn, Richard [UF; Sikivie, Pierre [UF; Ray, Heather [UF; Tanner, David [UF

    2013-10-10T23:59:59.000Z

    We report on progress in a series of different directions within high energy physics research. 1. Neutrino research in hardware and software on the Minerva and MiniBooNE experiments 2. Experimental particle physics at the hadron colliders, with emphasis on research and development and data analysis on the CMS experiment operating at the CERN LHC. This includes research on the discovery and properties on the Higgs Boson. 3. Educational outreach through the Quarknet program, taking physics research into High School classrooms. 4. Theoretical and Phenomenological High Energy research, covering a broad range of activities ranging from fundamental theoretical issues to areas of immediate phenomenological importance. 5. Experiment searches for the Axion, as part of the ADMX experiment.

  8. Quantum Operation Time Reversal

    SciTech Connect (OSTI)

    Crooks, Gavin E.

    2008-03-25T23:59:59.000Z

    The dynamics of an open quantum system can be described by a quantum operation: A linear, complete positive map of operators. Here, I exhibit a compact expression for the time reversal of a quantum operation, which is closely analogous to the time reversal of a classical Markov transition matrix. Since open quantum dynamics are stochastic, and not, in general, deterministic, the time reversal is not, in general, an inversion of the dynamics. Rather, the system relaxes toward equilibrium in both the forward and reverse time directions. The probability of a quantum trajectory and the conjugate, time reversed trajectory are related by the heat exchanged with the environment.

  9. Operation Prognostics and Operation Diagnostics—Technologies for Enhanced Operations and Controls

    E-Print Network [OSTI]

    Baumann, O.

    PROGNOSTICS AND OPERATION DIAGNOSTICS ? NEW TECHNOLOGIES FOR ENHANCED OPERATIONS AND CONTROLS OLIVER BAUMANN, PRESIDENT 202-608-1334 EBERT & BAUMANN CONSULTING ENGINEERS, WASHINGTON D.C. The Methodologies of Operation Prognostics and Operation...

  10. Conduct of Operations

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2010-06-29T23:59:59.000Z

    This Order defines the requirements for establishing and implementing Conduct of Operations Programs at Department of Energy (DOE), including National Nuclear Security Administration (NNSA), facilities and projects. Cancels DOE O 5480.19. Admin Chg 1, 6-25-13

  11. Operation Research Analyst

    Broader source: Energy.gov [DOE]

    The incumbent in this position will serve as an Operation Research Analyst in the Market Analysis and Pricing organization of Power Services. This organization is responsible for performing market...

  12. Operations Security Program

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1992-04-30T23:59:59.000Z

    To establish policies, responsibilities and authorities for implementing and sustaining the Department of Energy (DOE) Operations Security (OPSEC) Program. Cancels DOE O 5632.3B. Canceled by DOE O 471.2 of 9-28-1995.

  13. Nuclear material operations manual

    SciTech Connect (OSTI)

    Tyler, R.P.

    1981-02-01T23:59:59.000Z

    This manual provides a concise and comprehensive documentation of the operating procedures currently practiced at Sandia National Laboratories with regard to the management, control, and accountability of nuclear materials. The manual is divided into chapters which are devoted to the separate functions performed in nuclear material operations-management, control, accountability, and safeguards, and the final two chapters comprise a document which is also issued separately to provide a summary of the information and operating procedures relevant to custodians and users of radioactive and nuclear materials. The manual also contains samples of the forms utilized in carrying out nuclear material activities. To enhance the clarity of presentation, operating procedures are presented in the form of playscripts in which the responsible organizations and necessary actions are clearly delineated in a chronological fashion from the initiation of a transaction to its completion.

  14. Protection Program Operations

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2014-10-14T23:59:59.000Z

    This Order establishes requirements for the management and operation of the Department of Energy (DOE) Federal Protective Forces (FPF), Contractor Protective Forces (CPF), and the Physical Security of property and personnel under the cognizance of DOE.

  15. Continuity of Operations

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2005-01-14T23:59:59.000Z

    The notice defines requirements and responsibilities for continuity of operations planning within the DOE to ensure the capability to continue essential Departmental functions across a wide range of all hazard emergencies. Does not cancel other directives.

  16. Operations | Argonne National Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations Argonne mentors students for the next generation of scientistsMay 28, 2015 On May 6, the accomplishments of seventeen Chicago-area high school students that had been...

  17. SNS Target Systems Operational

    E-Print Network [OSTI]

    McDonald, Kirk

    a failed gas seal on the shaft and leaking oil seals but has operated well since then · The moderator 7.5 k First target replacement · No observed corrosion · Internal Boroscope examination in progress · ~ 50 mm

  18. Operational Waste Volume Projection

    SciTech Connect (OSTI)

    STRODE, J.N.

    1999-08-24T23:59:59.000Z

    Waste receipts to the double-shell tank system are analyzed and wastes through the year 2018 are projected based on assumption as of July 1999. A computer simulation of site operations is performed, which results in projections of tank fill schedules, tank transfers, evaporator operations, tank retrieval, and aging waste tank usage. This projection incorporates current budget planning and the clean-up schedule of the Tri-Party Agreement.

  19. Operational Waste Volume Projection

    SciTech Connect (OSTI)

    STRODE, J.N.

    2000-08-28T23:59:59.000Z

    Waste receipts to the double-shell tank system are analyzed and wastes through the year 2015 are projected based on generation trends of the past 12 months. A computer simulation of site operations is performed, which results in projections of tank fill schedules, tank transfers, evaporator operations, tank retrieval, and aging waste tank usage. This projection incorporates current budget planning and the clean-up schedule of the Tri-Party Agreement. Assumptions were current as of June. 2000.

  20. Operational waste volume projection

    SciTech Connect (OSTI)

    Koreski, G.M.

    1996-09-20T23:59:59.000Z

    Waste receipts to the double-shell tank system are analyzed and wastes through the year 2015 are projected based on generation trends of the past 12 months. A computer simulation of site operations is performed, which results in projections of tank fill schedules, tank transfers, evaporator operations, tank retrieval, and aging waste tank usage. This projection incorporates current budget planning and the clean-up schedule of the Tri-Party Agreement. Assumptions were current as of June 1996.

  1. National Security Technology Incubator Operations Plan

    SciTech Connect (OSTI)

    None

    2008-04-30T23:59:59.000Z

    This report documents the operations plan for developing the National Security Technology Incubator (NSTI) program for southern New Mexico. The NSTI program will focus on serving businesses with national security technology applications by nurturing them through critical stages of early development. The NSTI program is being developed as part of the National Security Preparedness Project (NSPP), funded by Department of Energy (DOE)/National Nuclear Security Administration (NNSA). The operation plan includes detailed descriptions of the structure and organization, policies and procedures, scope, tactics, and logistics involved in sustainable functioning of the NSTI program. Additionally, the operations plan will provide detailed descriptions of continuous quality assurance measures based on recommended best practices in incubator development by the National Business Incubation Association (NBIA). Forms that assist in operations of NSTI have been drafted and can be found as an attachment to the document.

  2. 2002 SITE ENVIRONMENTAL REPORT.

    SciTech Connect (OSTI)

    BROOKHAVEN NATIONAL LABORATORY

    2003-10-01T23:59:59.000Z

    The 2002 Site Environmental Report (SER) is prepared in accordance with DOE Order 231.1, ''Environment, Safety and Health Reporting'', and summarizes the status of Brookhaven National Laboratory's (BNL) environmental programs and performance and restoration efforts, as well as any impacts, both past and present, that Laboratory operations have had on the environment. The document is intended to be technical in nature. A summary of the report is also prepared as a separate document to provide a general overview and includes a CD version of the full report. Operated by Brookhaven Science Associates (BSA) for the Department of Energy (DOE), BNL manages its world-class scientific research with particular sensitivity to environmental and community issues. BNL's motto, ''Exploring Life's Mysteries...Protecting its Future'', reflects BNL's management philosophy to fully integrate environmental stewardship into all facets of its missions, with a health balance between science and the environment.

  3. Property description and fact-finding report for NPR-3 Natrona County, Wyoming. Addendum to 22 August 1996 study of alternatives for future operations of the naval petroleum and oil shale reserves NPR-3

    SciTech Connect (OSTI)

    NONE

    1997-05-01T23:59:59.000Z

    The U.S. Department of Energy has asked Gustavson Associates, Inc. to serve as an Independent Petroleum Consultant under contract DE-AC01-96FE64202. This authorizes a study and recommendations regarding future development of Naval Petroleum Reserve No. 3 (NPR-3) in Natrona County, Wyoming. The report that follows is the Phase I fact-finding and property description for that study. The United States of America owns 100 percent of the mineral rights and surface rights in 9,321-acre NPR-3. This property comprises the Teapot Dome oil field and related production, processing and other facilities. Discovered in 1914, this field has 632 wells producing 1,807 barrels of oil per day. Production revenues are about $9.5 million per year. Remaining recoverable reserves are approximately 1.3 million barrels of oil. Significant plugging and abandonment (P&A) and environmental liabilities are present.

  4. DOE Bottleneck Report-Final.PDF

    Broader source: Energy.gov (indexed) [DOE]

    of RTOs to facilitate grid expansion and to improve the operation of competitive wholesale electricity markets. The Electricity Advisory Board's Subcommittee report defines...

  5. Independent Activity Report, Pacific Northwest National Laboratory...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    January 2012 January 2012 Pacific Northwest National Laboratory Orientation Visit HIAR-PNNL-2012-01-11 This Independent Activity Report documents an operational awareness...

  6. Phil Taylor, E&E reporter

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    RENEWABLE ENERGY: Oil industry waste could be geothermal treasure (05202010) Phil Taylor, E&E reporter For more than a century, oilfield operators have viewed wastewater as a...

  7. Independent Oversight Activity Report, Hanford Waste Treatment...

    Broader source: Energy.gov (indexed) [DOE]

    Hanford Waste Treatment and Immobilization Plant Engineering Activities and Tank Farm Operations HIAR-HANFORD-2014-01-13 This Independent Oversight Activity Report documents...

  8. Independent Oversight Activity Report, Savannah River Site -...

    Office of Environmental Management (EM)

    Activity Report, Savannah River Site - February 2014 February 2014 Operational Awareness Visit of the Savannah River Site HIAR-SRS-2014-02-25 This Independent Activity...

  9. Independent Oversight Activity Report, Nevada National Security...

    Office of Environmental Management (EM)

    Report, Nevada National Security Site - March 3-6, 2014 March 2014 Operational Awareness Oversight of the Nevada National Security Site HIAR NNSS-2014-03-03 This...

  10. Independent Activity Report, Oak Ridge National Laboratory -...

    Broader source: Energy.gov (indexed) [DOE]

    October 2011 Operational Awareness Tour of Building 3525 Irradiated Fuels Examination Hot Cell Laboratory HIAR OR-2011-10-21 This Independent Activity Report documents an...

  11. Independent Activity Report, Nevada National Security Site -...

    Energy Savers [EERE]

    Security Site - December 2012 December 2012 Nevada National Security Site Operational Awareness Visit HIAR NNSS-2012-12-03 This Independent Activity Report documents an...

  12. Pressurized fluidized-bed hydroretorting of eastern oil shales. Volume 4, Task 5, Operation of PFH on beneficiated shale, Task 6, Environmental data and mitigation analyses and Task 7, Sample procurement, preparation, and characterization: Final report, September 1987--May 1991

    SciTech Connect (OSTI)

    Not Available

    1992-03-01T23:59:59.000Z

    The objective of Task 5 (Operation of Pressurized Fluidized-Bed Hydro-Retorting (PFH) on Beneficiated Shale) was to modify the PFH process to facilitate its use for fine-sized, beneficiated Eastern shales. This task was divided into 3 subtasks: Non-Reactive Testing, Reactive Testing, and Data Analysis and Correlations. The potential environment impacts of PFH processing of oil shale must be assessed throughout the development program to ensure that the appropriate technologies are in place to mitigate any adverse effects. The overall objectives of Task 6 (Environmental Data and Mitigation Analyses) were to obtain environmental data relating to PFH and shale beneficiation and to analyze the potential environmental impacts of the integrated PFH process. The task was divided into the following four subtasks. Characterization of Processed Shales (IGT), 6.2. Water Availability and Treatment Studies, 6.3. Heavy Metals Removal and 6.4. PFH Systems Analysis. The objective of Task 7 (Sample Procurement, Preparation, and Characterization) was to procure, prepare, and characterize raw and beneficiated bulk samples of Eastern oil shale for all of the experimental tasks in the program. Accomplishments for these tasks are presented.

  13. Annual Site Environmental Report

    SciTech Connect (OSTI)

    Finley, Virginia [PPPL

    2014-10-02T23:59:59.000Z

    This report provides the U.S. Department of Energy (DOE) and the public with information on the level of radioactive and non-radioactive pollutants (if any) that are added to the environment as a result of Princeton Plasma Physics Laboratory’s (PPPL) operations. The results of the 2013 environmental surveillance and monitoring program for PPPL’s are presented and discussed. The report also summarizes environmental initiatives, assessments, and community involvement programs that were undertaken in 2013.

  14. LANSCE Activity Report

    SciTech Connect (OSTI)

    Amy Robinson; Audrey Archuleta; Barbara Maes; Dan Strottman; Earl Hoffman; Garth Tietjen; Gene Farnum; Geoff Greene; Joyce Roberts; Ken Johnson; Paul Lewis; Roger Pynn; Stan Schriber; Steve Sterbenz; Steve Wender; Sue Harper

    1999-02-01T23:59:59.000Z

    The Los Alamos Neutron Science Center Activity Report describes scientific and technological progress and achievements in LANSCE Division during the period of 1995 to 1998. This report includes a message from the Division Director, an overview of LANSCE, sponsor overviews, research highlights, advanced projects and facility upgrades achievements, experimental and user program accomplishments, news and events, and a list of publications. The research highlights cover the areas of condensed-matter science and engineering, accelerator science, nuclear science, and radiography. This report also contains a compact disk that includes an overview, the Activity Report itself, LANSCE operations progress reports for 1996 and 1997, experiment reports from LANSCE users, as well as a search capability.

  15. An evaluation of the effects of valve body erosion on motor-operated valve operability

    SciTech Connect (OSTI)

    Hunt, T.H.; Nitzel, M.E.; Weidenhamer, G.H.

    1995-12-01T23:59:59.000Z

    INEL engineers evaluated effects of erosion-induced valve wall thinning on motor-operated valve operability. The authors reviewed reports that identified the extent and location of erosion damage in nuclear plant valves and chose a globe valve with severe erosion damage to assess the potential for loss of operability. They developed a finite element model of the selected valve and performed structural analyses with valve closing forces, seismic effects, and increased erosion areas to analyze effects of erosion on structural integrity. Results indicate that while some local stresses at the points of maximum erosion exceeded yield, the general stresses were well below yield. Therefore, displacements will be small and bending will not occur. It is concluded that erosion-related wall thinning is not likely to create an operability problem for motor-operated valves.

  16. Groundwater Report Goes Online, Interactive

    Broader source: Energy.gov [DOE]

    RICHLAND, Wash. – EM’s Richland Operations Office (RL) has moved its 1,200-page annual report on groundwater monitoring to a fully online and interactive web application.

  17. Final Safety Evaluation Report to license the construction and operation of a facility to receive, store, and dispose of 11e.(2) byproduct material near Clive, Utah (Docket No. 40-8989)

    SciTech Connect (OSTI)

    Not Available

    1994-01-01T23:59:59.000Z

    The Final Safety Evaluation Report (FSER) summarizes the US Nuclear Regulatory Commission (NRC) staff`s review of Envirocare of Utah, Inc.`s (Envirocare`s) application for a license to receive, store, and dispose of uranium and thorium byproduct material (as defined in Section 11e.(2) of the Atomic Energy Act of 1954, as amended) at a site near Clive, Utah. Envirocare proposes to dispose of high-volume, low-activity Section 11e.(2) byproduct material in separate earthen disposal cells on a site where the applicant currently disposes of naturally occurring radioactive material (NORM), low-level waste, and mixed waste under license by the Utah Department of Environmental Quality. The NRC staff review of the December 23, 1991, license application, as revised by page changes dated July 2 and August 10, 1992, April 5, 7, and 10, 1993, and May 3, 6, 7, 11, and 21, 1993, has identified open issues in geotechnical engineering, water resources protection, radon attenuation, financial assurance, and radiological safety. The NRC will not issue a license for the proposed action until Envirocare adequately resolves these open issues.

  18. Microsoft Word - DOE_2014-Final_Tech_Report-MG1.doc

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Title: Collaborative Research, Type 1: Decadal Prediction and Stochastic Simulation of Hydro clim ate Over M onsoonal Asia Principal Investigators: Drs. Andrew W. Robertson (IRI,...

  19. 2008 annual report Chapterhead

    E-Print Network [OSTI]

    Weston, Ken

    -mail hedick@magnet.fsu.edu. Chapter 1 2008 Year in review . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 194 researChhighlights #12;2008 annual report CHapter 1 3 2008-Yearinreview Chapter 1: 2008 - Year in review all user programs and magnets operated throughout 2008! that is really saying something, because

  20. Data Management Group Annual Report

    E-Print Network [OSTI]

    Toronto, University of

    Data Management Group Annual Report 2000 prepared by: Data Management Group Joint Program the operation of the EMME/2 simu- lation package on the Data Management Group's computer system. During the year computing resource at the DMG. A major challenge in 2000 was to maintain this service while operating out

  1. An operational semantics of a timely bounded agent abstract machine

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    An operational semantics of a timely bounded agent abstract machine Technical Report LIRMM #RR an agent abstract machine and its operational semantics. The dynamics of the agent abstract machine of the agent abstract machine using parallel evaluations. Simplicity and expressiveness are important features

  2. Conduct of Operations

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2010-06-29T23:59:59.000Z

    This Order defines the requirements for establishing and implementing Conduct of Operations Programs at Department of Energy (DOE), including National Nuclear Security Administration (NNSA), facilities and projects. Cancels DOE O 5480.19. Admin Chg 1, dated 6-25-13, cancels DOE O 422.1. Certified 12-3-14.

  3. Conduct of Operations

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2010-06-29T23:59:59.000Z

    This Order defines the requirements for establishing and implementing Conduct of Operations Programs at Department of Energy (DOE), including National Nuclear Security Administration (NNSA), facilities and projects. Cancels DOE O 5480.19. Admin Chg 2, dated 12-3-14, cancels Admin Chg 1.

  4. OPERATIONAL RISK RODNEY COLEMAN

    E-Print Network [OSTI]

    Coleman, Rodney

    is entered into with the aim of generating wealth, in the pursuit of returns Wiley Encyclopedia of Operations, not only because losses are widely expressed in monetary terms but also since the industry is highly the loss events are penalties imposed for contravening regulations, they enter the public domain. Onetime

  5. Structuring Structural Operational

    E-Print Network [OSTI]

    Mousavi, Mohammad

    aan de Technische Universiteit Eindhoven, op gezag van de Rector Magnificus, prof.dr.ir. C.J. van.A. Reniers CIP­DATA LIBRARY TECHNISCHE UNIVERSITEIT EINDHOVEN Mousavi, MohammadReza Structuring Structural Operational Semantics / MohammadReza Mousavi. ­ Eindhoven : Technische Universiteit Eindhoven, 2005

  6. Structuring Structural Operational

    E-Print Network [OSTI]

    Reniers, Michel

    aan de Technische Universiteit Eindhoven, op gezag van de Rector Magnificus, prof.dr.ir. C.J. van.A. Reniers CIP-DATA LIBRARY TECHNISCHE UNIVERSITEIT EINDHOVEN Mousavi, MohammadReza Structuring Structural Operational Semantics / MohammadReza Mousavi. - Eindhoven : Technische Universiteit Eindhoven, 2005

  7. REACTOR OPERATIONS AND CONTROL

    E-Print Network [OSTI]

    Pázsit, Imre

    REACTOR OPERATIONS AND CONTROL KEYWORDS: core calculations, neural networks, control rod elevation of a control rod, or a group of control rods, is an important parameter from the viewpoint of reactor control DETERMINATION OF PWR CONTROL ROD POSITION BY CORE PHYSICS AND NEURAL NETWORK METHODS NINOS S. GARIS* and IMRE

  8. NUCLEAR PLANT OPERATIONS AND

    E-Print Network [OSTI]

    Demazière, Christophe

    NUCLEAR PLANT OPERATIONS AND CONTROL KEYWORDS: moderator temper ature coefficient, reactivity co reactor Unit 4 of the Ringhals Nuclear Power Plant (Sweden) during fuel cycle 16 is analyzed absorption cross-section behavior. Consequently, if NUCLEAR TECHNOLOGY VOL. 140 NOV. 2002 147 #12;Demazière

  9. NUCLEAR PLANT OPERATIONS AND

    E-Print Network [OSTI]

    Pázsit, Imre

    NUCLEAR PLANT OPERATIONS AND CONTROL KEYWORDS: moderator temper- ature coefficient, reactivity co reactor Unit 4 of the Ringhals Nuclear Power Plant (Sweden) during fuel cycle 16 is analyzed. Consequently, if*E-mail: demaz@nephy.chalmers.se NUCLEAR TECHNOLOGY VOL. 140 NOV. 2002 147 #12;high-burnup fuel

  10. Operation and Maintenance

    E-Print Network [OSTI]

    van Hemmen, J. Leo

    in this Publication is provided as is and has been prepared solely for the purpose of evaluating data center designOperation and Maintenance InRow® RD Air Cooled ACRD100 ACRD101 #12;This manual is available assumes no liability for damages, violations of codes, improper installation, system failures, or any

  11. Intelligent Potroom Operation

    SciTech Connect (OSTI)

    Jan Berkow; Larry Banta

    2003-07-29T23:59:59.000Z

    The Intelligent Potroom Operation project focuses on maximizing the performance of an aluminum smelter by innovating components for an intelligent manufacturing system. The Intelligent Potroom Advisor (IPA) monitors process data to identify reduction cells exhibiting behaviors that require immediate attention. It then advises operational personnel on those heuristic-based actions to bring the cell back to an optimal operating state in order to reduce the duration and frequency of substandard reduction cell performance referred to as ''Off-Peak Modes'' (OPMs). Techniques developed to identify cells exhibiting OPMs include the use of a finite element model-based cell state estimator for defining the cell's current operating state via advanced cell noise analyses. In addition, rule induction was also employed to identify statistically significant complex behaviors that occur prior to OPMs. The intelligent manufacturing system design, concepts and formalisms developed in this project w ere used as a basis for an intelligent manufacturing system design. Future research will incorporate an adaptive component to automate continuous process improvement, a technology platform with the potential to improve process performance in many of the other Industries of the Future applications as well.

  12. Safe Chain Saw Operation

    E-Print Network [OSTI]

    Nelson, Gary S.

    1982-01-01T23:59:59.000Z

    Z TA24S.7 8873 NO.1409 B-1409 SAFE CHAIN SAW OPERATION Gary S. Nelson* A chain saw is a portable power cutting machine. Used properly, it will trim or cut down trees, clear land or cut fireplace wood. Improperly used, a chain saw can...

  13. DCO Operations Interesting Statistics

    E-Print Network [OSTI]

    DRY BULB TEMPERATURE - °F 01 51 02 52 03 53 04 54 05 55 55 06 06 RIAYRDFODNUOPREPUTB-YPLAHTNE ENTHALPY - BTU PER POUND OF DRY AIR 51 02 52 03 53 04 54 05 RIA YRD F O DNU OP REP UTB- YPLAHTNE F°- ERUTAREP MET operate 1560 hard disks, totaling 530 TB of storage · Eight air conditioners within the zones process

  14. Concept of Operations: Essence

    SciTech Connect (OSTI)

    Hutton, William J.

    2014-04-01T23:59:59.000Z

    This concept of operations is designed to give the reader a brief overview of the National Rural Electric Cooperative Association’s Essence project and a description of the Essence device design. The data collected by the device, how the data are used, and how the data are protected are also discussed in this document.

  15. Office of Business Operations

    Broader source: Energy.gov [DOE]

    The Office of Business Operations manages financial and acquisition management programs throughout the Associate Under Secretary for the Office of Environment, Health, Safety and Security (AU), including the formulation and execution of the AU budget; funding control and accounting activities; preparation of management studies; and provision of acquisition management support.

  16. Impact of High Wind Power Penetration on Hydroelectric Unit Operations in the WWSIS

    SciTech Connect (OSTI)

    Hodge, B.-M.; Lew, D.; Milligan, M.

    2011-07-01T23:59:59.000Z

    This report examines the impact of this large amount of wind penetration on hydroelectric unit operations. Changes in hydroelectric unit operating patterns are examined both for an aggregation of all hydro generators and for select individual plants.

  17. Operations and Maintenance Program Structure

    Broader source: Energy.gov [DOE]

    The Federal Energy Management Program recommends Federal operations and maintenance (O&M) programs comprise of five distinct functions: operations, maintenance, engineering, training, and...

  18. Final Report REPORT ON THE REVIEW OF METHOD 115

    E-Print Network [OSTI]

    this standard at this time, especially in view of renewed interest in uranium exploration and recoveryFinal Report REPORT ON THE REVIEW OF METHOD 115 TO MONITOR RADON EMISSIONS FROM URANIUM TAILINGS Operating Uranium Mills (40 CFR 61.25), this document has been reviewed and approved by the following

  19. STANDARD OPERATING PROCEDURES Sampler Maintenance by Site Operators

    E-Print Network [OSTI]

    Fischer, Emily V.

    IMPROVE STANDARD OPERATING PROCEDURES SOP 201 Sampler Maintenance by Site Operators Date Last.0 PURPOSE AND APPLICABILITY This standard operating procedure (SOP) describes the procedures and schedules. The procedural steps for weekly maintenance and repairs performed by the site operator are included in TI 201A

  20. A Computuerized Operator Support System Prototype

    SciTech Connect (OSTI)

    Ken Thomas; Ronald Boring; Roger Lew; Tom Ulrich; Richard Villim

    2013-08-01T23:59:59.000Z

    A report was published by the Idaho National Laboratory in September of 2012, entitled Design to Achieve Fault Tolerance and Resilience, which described the benefits of automating operator actions for transients. The report identified situations in which providing additional automation in lieu of operator actions would be advantageous. It recognized that managing certain plant upsets is sometimes limited by the operator’s ability to quickly diagnose the fault and to take the needed actions in the time available. Undoubtedly, technology is underutilized in the nuclear power industry for operator assistance during plant faults and operating transients. In contrast, other industry sectors have amply demonstrated that various forms of operator advisory systems can enhance operator performance while maintaining the role and responsibility of the operator as the independent and ultimate decision-maker. A computerized operator support system (COSS) is proposed for use in nuclear power plants to assist control room operators in addressing time-critical plant upsets. A COSS is a collection of technologies to assist operators in monitoring overall plant performance and making timely, informed decisions on appropriate control actions for the projected plant condition. The COSS does not supplant the role of the operator, but rather provides rapid assessments, computations, and recommendations to reduce workload and augment operator judgment and decision-making during fast-moving, complex events. This project proposes a general model for a control room COSS that addresses a sequence of general tasks required to manage any plant upset: detection, validation, diagnosis, recommendation, monitoring, and recovery. The model serves as a framework for assembling a set of technologies that can be interrelated to assist with each of these tasks. A prototype COSS has been developed in order to demonstrate the concept and provide a test bed for further research. The prototype is based on four underlying elements consisting of a digital alarm system, computer-based procedures, PI&D system representations, and a recommender module for mitigation actions. At this point, the prototype simulates an interface to a sensor validation module and a fault diagnosis module. These two modules will be fully integrated in the next version of the prototype. The initial version of the prototype is now operational at the Idaho National Laboratory using the U.S. Department of Energy’s Light Water Reactor Sustainability (LWRS) Human Systems Simulation Laboratory (HSSL). The HSSL is a full-scope, full-scale glass top simulator capable of simulating existing and future nuclear power plant main control rooms. The COSS is interfaced to the Generic Pressurized Water Reactor (gPWR) simulator with industry-typical control board layouts. The glass top panels display realistic images of the control boards that can be operated by touch gestures. A section of the simulated control board was dedicated to the COSS human-system interface (HSI), which resulted in a seamless integration of the COSS into the normal control room environment.