National Library of Energy BETA

Sample records for repair project cxs

  1. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Ian Harris; Dennis Harwig; Nancy Porter; Mike Sullivan; Chris Neary

    2004-04-12

    The two broad categories of deposited weld metal repair and fiber-reinforced composite liner repair technologies were reviewed for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Preliminary test programs were developed for both deposited weld metal repair and for fiber-reinforced composite liner repair. Evaluation trials have been conducted using a modified fiber-reinforced composite liner provided by RolaTube and pipe sections without liners. All pipe section specimens failed in areas of simulated damage. Pipe sections containing fiber-reinforced composite liners failed at pressures marginally greater than the pipe sections without liners. The next step is to evaluate a liner material with a modulus of elasticity approximately 95% of the modulus of elasticity for steel. Preliminary welding parameters were developed for deposited weld metal repair in preparation of the receipt of Pacific Gas & Electric's internal pipeline welding repair system (that was designed specifically for 559 mm (22 in.) diameter pipe) and the receipt of 559 mm (22 in.) pipe sections from Panhandle Eastern. The next steps are to transfer welding parameters to the PG&E system and to pressure test repaired pipe sections to failure. A survey of pipeline operators was conducted to better understand the needs and performance requirements of the natural gas transmission industry regarding internal repair. Completed surveys contained the following principal conclusions: (1) Use of internal weld repair is most attractive for river crossings, under other bodies of water, in difficult soil conditions, under highways, under congested intersections, and under railway crossings. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling (HDD) when a new bore must be created to solve a leak or other problem. (3) Typical travel distances can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). All three groups require pig-based systems. A despooled umbilical system would suffice for the first two groups which represents 81% of survey respondents. The third group would require an onboard self-contained power unit for propulsion and welding/liner repair energy needs. (4) Pipe diameter sizes range from 50.8 mm (2 in.) through 1,219.2 mm (48 in.). The most common size range for 80% to 90% of operators surveyed is 508 mm to 762 mm (20 in. to 30 in.), with 95% using 558.8 mm (22 in.) pipe. An evaluation of potential repair methods clearly indicates that the project should continue to focus on the development of a repair process involving the use of GMAW welding and on the development of a repair process involving the use of fiber-reinforced composite liners.

  2. Turbine repair process, repaired coating, and repaired turbine component

    SciTech Connect (OSTI)

    Das, Rupak; Delvaux, John McConnell; Garcia-Crespo, Andres Jose

    2015-11-03

    A turbine repair process, a repaired coating, and a repaired turbine component are disclosed. The turbine repair process includes providing a turbine component having a higher-pressure region and a lower-pressure region, introducing particles into the higher-pressure region, and at least partially repairing an opening between the higher-pressure region and the lower-pressure region with at least one of the particles to form a repaired turbine component. The repaired coating includes a silicon material, a ceramic matrix composite material, and a repaired region having the silicon material deposited on and surrounded by the ceramic matrix composite material. The repaired turbine component a ceramic matrix composite layer and a repaired region having silicon material deposited on and surrounded by the ceramic matrix composite material.

  3. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Nancy Porter; Mike Sullivan; Chris Neary

    2003-05-01

    The two broad categories of deposited weld metal repair and fiber-reinforced composite repair technologies were reviewed for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Preliminary test programs were developed for both deposited weld metal repairs and for fiber-reinforced composite repair. To date, all of the experimental work pertaining to the evaluation of potential repair methods has focused on fiber-reinforced composite repairs. Hydrostatic testing was also conducted on four pipeline sections with simulated corrosion damage: two with composite liners and two without.

  4. INTERNAL REPAIR OF PIPELINES REVIEW & EVALUATION OF INTERNAL PIPELINE REPAIR TRIALS REPORT

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Ian Harris; Dennis Harwig; George Ritter; Bill Mohr; Matt Boring; Nancy Porter; Mike Sullivan; Chris Neary

    2004-09-01

    The two broad categories of fiber-reinforced composite liner repair and deposited weld metal repair technologies were reviewed and evaluated for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Evaluation trials were conducted on pipe sections with simulated corrosion damage repaired with glass fiber-reinforced composite liners, carbon fiber-reinforced composite liners, and weld deposition. Additional un-repaired pipe sections were evaluated in the virgin condition and with simulated damage. Hydrostatic failure pressures for pipe sections repaired with glass fiber-reinforced composite liner were only marginally greater than that of pipe sections without liners, indicating that this type of liner is generally ineffective at restoring the pressure containing capabilities of pipelines. Failure pressure for pipe repaired with carbon fiber-reinforced composite liner was greater than that of the un-repaired pipe section with damage, indicating that this type of liner is effective at restoring the pressure containing capability of pipe. Pipe repaired with weld deposition failed at pressures lower than that of un-repaired pipe in both the virgin and damaged conditions, indicating that this repair technology is less effective at restoring the pressure containing capability of pipe than a carbon fiber-reinforced liner repair. Physical testing indicates that carbon fiber-reinforced liner repair is the most promising technology evaluated to-date. Development of a comprehensive test plan for this process is recommended for use in the next phase of this project.

  5. Rapid road repair vehicle

    DOE Patents [OSTI]

    Mara, Leo M. (Livermore, CA)

    1998-01-01

    Disclosed is a rapid road repair vehicle capable of moving over a surface to be repaired at near normal posted traffic speeds to scan for and find an the high rate of speed, imperfections in the pavement surface, prepare the surface imperfection for repair by air pressure and vacuum cleaning, applying a correct amount of the correct patching material to effect the repair, smooth the resulting repaired surface, and catalog the location and quality of the repairs for maintenance records of the road surface. The rapid road repair vehicle can repair surface imperfections at lower cost, improved quality, at a higher rate of speed than was was heretofor possible, with significantly reduced exposure to safety and health hazards associated with this kind of road repair activities in the past.

  6. Rapid road repair vehicle

    DOE Patents [OSTI]

    Mara, L.M.

    1998-05-05

    Disclosed is a rapid road repair vehicle capable of moving over a surface to be repaired at near normal posted traffic speeds to scan for and find at the high rate of speed, imperfections in the pavement surface, prepare the surface imperfection for repair by air pressure and vacuum cleaning, applying a correct amount of the correct patching material to effect the repair, smooth the resulting repaired surface, and catalog the location and quality of the repairs for maintenance records of the road surface. The rapid road repair vehicle can repair surface imperfections at lower cost, improved quality, at a higher rate of speed than was not heretofor possible, with significantly reduced exposure to safety and health hazards associated with this kind of road repair activities in the past. 2 figs.

  7. Developments advance subsea pipelaying, inspection, repair

    SciTech Connect (OSTI)

    1997-09-15

    Recent advances in laying, inspecting, and repairing pipelines are helping to cut both costs and time. A new dredging system that employs jets to clear a subsea trench for pipelay received trials off Belgium last spring. Also, within the last year, projects in the Middle East and North Sea employed technologies that promise to make inspecting the surface of a subsea pipeline in difficult terrain easier, less time consuming, and therefore less costly. Plus, subsea repair of damaged pipelines may take less time with a new ``stabbable`` pipe connector. The paper describes jet dredging, inspection advance, support software, the North Sea site, and pipeline repair.

  8. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Bill Bruce; Nancy Porter; George Ritter; Matt Boring; Mark Lozev; Ian Harris; Bill Mohr; Dennis Harwig; Robin Gordon; Chris Neary; Mike Sullivan

    2005-07-20

    The two broad categories of fiber-reinforced composite liner repair and deposited weld metal repair technologies were reviewed and evaluated for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Principal conclusions from a survey of natural gas transmission industry pipeline operators can be summarized in terms of the following performance requirements for internal repair: (1) Use of internal repair is most attractive for river crossings, under other bodies of water, in difficult soil conditions, under highways, under congested intersections, and under railway crossings. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling when a new bore must be created to solve a leak or other problem. (3) Typical travel distances can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). All three groups require pig-based systems. A despooled umbilical system would suffice for the first two groups which represents 81% of survey respondents. The third group would require an onboard self-contained power unit for propulsion and welding/liner repair energy needs. (4) The most common size range for 80% to 90% of operators surveyed is 508 mm (20 in.) to 762 mm (30 in.), with 95% using 558.8 mm (22 in.) pipe. Evaluation trials were conducted on pipe sections with simulated corrosion damage repaired with glass fiber-reinforced composite liners, carbon fiber-reinforced composite liners, and weld deposition. Additional un-repaired pipe sections were evaluated in the virgin condition and with simulated damage. Hydrostatic failure pressures for pipe sections repaired with glass fiber-reinforced composite liner were only marginally greater than that of pipe sections without liners, indicating that this type of liner is only marginally effective at restoring the pressure containing capabilities of pipelines. Failure pressures for larger diameter pipe repaired with a semi-circular patch of carbon fiber-reinforced composite lines were also marginally greater than that of a pipe section with un-repaired simulated damage without a liner. These results indicate that fiber reinforced composite liners have the potential to increase the burst pressure of pipe sections with external damage Carbon fiber based liners are viewed as more promising than glass fiber based liners because of the potential for more closely matching the mechanical properties of steel. Pipe repaired with weld deposition failed at pressures lower than that of un-repaired pipe in both the virgin and damaged conditions, indicating that this repair technology is less effective at restoring the pressure containing capability of pipe than a carbon fiber-reinforced liner repair. Physical testing indicates that carbon fiber-reinforced liner repair is the most promising technology evaluated to-date. In lieu of a field installation on an abandoned pipeline, a preliminary nondestructive testing protocol is being developed to determine the success or failure of the fiber-reinforced liner pipeline repairs. Optimization and validation activities for carbon-fiber repair methods are ongoing.

  9. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Ian Harris; Dennis Harwig; George Ritter; Bill Mohr; Matt Boring; Nancy Porter; Mike Sullivan; Chris Neary

    2004-12-31

    The two broad categories of fiber-reinforced composite liner repair and deposited weld metal repair technologies were reviewed and evaluated for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Principal conclusions from a survey of natural gas transmission industry pipeline operators can be summarized in terms of the following performance requirements for internal repair: (1) Use of internal repair is most attractive for river crossings, under other bodies of water, in difficult soil conditions, under highways, under congested intersections, and under railway crossings. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling when a new bore must be created to solve a leak or other problem. (3) Typical travel distances can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). All three groups require pig-based systems. A despooled umbilical system would suffice for the first two groups which represents 81% of survey respondents. The third group would require an onboard self-contained power unit for propulsion and welding/liner repair energy needs. (4) The most common size range for 80% to 90% of operators surveyed is 508 mm (20 in.) to 762 mm (30 in.), with 95% using 558.8 mm (22 in.) pipe. Evaluation trials were conducted on pipe sections with simulated corrosion damage repaired with glass fiber-reinforced composite liners, carbon fiber-reinforced composite liners, and weld deposition. Additional un-repaired pipe sections were evaluated in the virgin condition and with simulated damage. Hydrostatic failure pressures for pipe sections repaired with glass fiber-reinforced composite liner were only marginally greater than that of pipe sections without liners, indicating that this type of liner is only marginally effective at restoring the pressure containing capabilities of pipelines. Failure pressures for larger diameter pipe repaired with a semi-circular patch of carbon fiber-reinforced composite lines were also marginally greater than that of a pipe section with un-repaired simulated damage without a liner. These results indicate that fiber reinforced composite liners have the potential to increase the burst pressure of pipe sections with external damage Carbon fiber based liners are viewed as more promising than glass fiber based liners because of the potential for more closely matching the mechanical properties of steel. Pipe repaired with weld deposition failed at pressures lower than that of un-repaired pipe in both the virgin and damaged conditions, indicating that this repair technology is less effective at restoring the pressure containing capability of pipe than a carbon fiber-reinforced liner repair. Physical testing indicates that carbon fiber-reinforced liner repair is the most promising technology evaluated to-date. The first round of optimization and validation activities for carbon-fiber repairs are complete. Development of a comprehensive test plan for this process is recommended for use in the field trial portion of this program.

  10. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Ian Harris; Dennis Harwig; George Ritter; Bill Mohr; Matt Boring; Nancy Porter; Mike Sullivan; Chris Neary

    2004-08-17

    The two broad categories of fiber-reinforced composite liner repair and deposited weld metal repair technologies were reviewed and evaluated for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Principal conclusions from a survey of natural gas transmission industry pipeline operators can be summarized in terms of the following performance requirements for internal repair: (1) Use of internal repair is most attractive for river crossings, under other bodies of water, in difficult soil conditions, under highways, under congested intersections, and under railway. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling when a new bore must be created to solve a leak or other problem. (3) Typical travel distances can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). All three groups require pig-based systems. A despooled umbilical system would suffice for the first two groups which represents 81% of survey respondents. The third group would require an onboard self-contained power unit for propulsion and welding/liner repair energy needs. (4) The most common size range for 80% to 90% of operators surveyed is 508 mm (20 in.) to 762 mm (30 in.), with 95% using 558.8 mm (22 in.) pipe. Evaluation trials were conducted on pipe sections with simulated corrosion damage repaired with glass fiber-reinforced composite liners, carbon fiber-reinforced composite liners, and weld deposition. Additional un-repaired pipe sections were evaluated in the virgin condition and with simulated damage. Hydrostatic failure pressures for pipe sections repaired with glass fiber-reinforced composite liner were only marginally greater than that of pipe sections without liners, indicating that this type of liner is only marginally effective at restoring the pressure containing capabilities of pipelines. Failure pressures for larger diameter pipe repaired with a semi-circular patch of carbon fiber-reinforced composite lines were also marginally greater than that of a pipe section with un-repaired simulated damage without a liner. These results indicate that fiber reinforced composite liners have the potential to increase the burst pressure of pipe sections with external damage Carbon fiber based liners are viewed as more promising than glass fiber based liners because of the potential for more closely matching the mechanical properties of steel. Pipe repaired with weld deposition failed at pressures lower than that of un-repaired pipe in both the virgin and damaged conditions, indicating that this repair technology is less effective at restoring the pressure containing capability of pipe than a carbon fiber-reinforced liner repair. Physical testing indicates that carbon fiber-reinforced liner repair is the most promising technology evaluated to-date. Development of a comprehensive test plan for this process is recommended for use in the field trial portion of this program.

  11. Rapid road repair vehicle

    DOE Patents [OSTI]

    Mara, Leo M. (Livermore, CA)

    1999-01-01

    Disclosed are improvments to a rapid road repair vehicle comprising an improved cleaning device arrangement, two dispensing arrays for filling defects more rapidly and efficiently, an array of pre-heaters to heat the road way surface in order to help the repair material better bond to the repaired surface, a means for detecting, measuring, and computing the number, location and volume of each of the detected surface imperfection, and a computer means schema for controlling the operation of the plurality of vehicle subsystems. The improved vehicle is, therefore, better able to perform its intended function of filling surface imperfections while moving over those surfaces at near normal traffic speeds.

  12. Staged Program Repair in SPR (Supplementary Material)

    E-Print Network [OSTI]

    Long, Fan

    2015-03-05

    We present SPR, a new program repair system that uses condition synthesis to instantiate transformation schemas to repair program defects. SPR's staged repair strategy combines a rich space of potential repairs with a ...

  13. Window Replacement, Rehabilitation, & Repair Guides - Building...

    Energy Savers [EERE]

    Window Replacement, Rehabilitation, & Repair Guides - Building America Top Innovation Window Replacement, Rehabilitation, & Repair Guides - Building America Top Innovation Effec...

  14. Verification of Motor Repair Quality 

    E-Print Network [OSTI]

    Butler, K.

    1998-01-01

    is done properly. But how can an industrial customer know that the motor has been repaired properly?...

  15. CX-012770: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Shiprock Access Road Repair Project San Juan County, New Mexico CX(s) Applied: B1.3Date: 41858 Location(s): New MexicoOffices(s): Western Area Power Administration-Rocky Mountain Region

  16. CX-008879: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Pearl-Marion No.1 Line Tower 21/1 Bank Repair Project CX(s) Applied: B1.3 Date: 08/13/2012 Location(s): Oregon Offices(s): Bonneville Power Administration

  17. Service and Repair Work

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of NaturalDukeWakefieldSulfateSciTechtail.Theory ofDidDevelopment Top Scientific Impact SinceService and Repair Work

  18. Awarded Products Maintenance, Repair & Operations TOOLS & HARDWARE

    E-Print Network [OSTI]

    California at San Diego, University of

    Awarded Products Maintenance, Repair & Operations (MRO): TOOLS & HARDWARE Such as hand and power tools, cutting tools, fasteners, etc. Maintenance, Repair & Operations (MRO): TOOLS & HARDWARE Such as hand and power tools, cutting tools, fasteners, etc. Maintenance, Repair & Operations (MRO): TOOLS

  19. Selected Bibliography on Electric Motor Repair | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Selected Bibliography on Electric Motor Repair Selected Bibliography on Electric Motor Repair The following series of repair documents related to electric motors were produced by...

  20. Overview of NCHRP Design Guideline for EPS-Block Geofoam in Slope Stabilization and Repair

    E-Print Network [OSTI]

    Manhattan College Bronx, New York 10471 Tel: (718) 826-7177 E-mail: john.horvath@manhattan.edu Dov and repair applications based on the results of National Cooperative Highway Research Program (NCHRP) Project was performed under NCHRP Project 24-11(01) and produced a design guideline for use of EPS blocks in stand

  1. The biomechanics of cruciate ligament repair 

    E-Print Network [OSTI]

    Ferry, Katheryn Irene

    2013-02-22

    -1 THE BIOMECHAIVICS OF CR UCIA TE LIGAMEJV T REPAIR A Senior Thesis By Katheryn Irene Ferry 1997-98 University Undergraduate Research Fellow Texas A&M University Group: Engineering II THE BIOMECHANICS OF CRUCIATE LIGAMENT REPAIR by KATHRYN IRENE FERRY... by the The Biomechanics of Cruciate Ligament Repair femorotibial ligaments which include the collateral ligaments, the cranial cruciate ligament, and the caudal cruciate ligament (Vasseur, 1993). The anatomy and spatial arrangement of the femorotibial ligaments...

  2. Chemical Fume Hood Maintenance, Repair and Certification

    E-Print Network [OSTI]

    Jia, Songtao

    in the lab. Removes lockout of hoods, if used. g. Notify EH&S to perform re-certification after repair

  3. Development and validation of bonded composite doubler repairs for commercial aircraft.

    SciTech Connect (OSTI)

    Roach, Dennis Patrick; Rackow, Kirk A.

    2007-07-01

    A typical aircraft can experience over 2,000 fatigue cycles (cabin pressurizations) and even greater flight hours in a single year. An unavoidable by-product of aircraft use is that crack, impact, and corrosion flaws develop throughout the aircraft's skin and substructure elements. Economic barriers to the purchase of new aircraft have placed even greater demands on efficient and safe repair methods. The use of bonded composite doublers offers the airframe manufacturers and aircraft maintenance facilities a cost effective method to safely extend the lives of their aircraft. Instead of riveting multiple steel or aluminum plates to facilitate an aircraft repair, it is now possible to bond a single Boron-Epoxy composite doubler to the damaged structure. The FAA's Airworthiness Assurance Center at Sandia National Labs (AANC), Boeing, and Federal Express completed a pilot program to validate and introduce composite doubler repair technology to the U.S. commercial aircraft industry. This project focused on repair of DC-10 fuselage structure and its primary goal was to demonstrate routine use of this repair technology using niche applications that streamline the design-to-installation process. As composite doubler repairs gradually appear in the commercial aircraft arena, successful flight operation data is being accumulated. These commercial aircraft repairs are not only demonstrating the engineering and economic advantages of composite doubler technology but they are also establishing the ability of commercial maintenance depots to safely adopt this repair technique. This report presents the array of engineering activities that were completed in order to make this technology available for widespread commercial aircraft use. Focused laboratory testing was conducted to compliment the field data and to address specific issues regarding damage tolerance and flaw growth in composite doubler repairs. Fatigue and strength tests were performed on a simulated wing repair using a substandard design and a flawed installation. In addition, the new Sol-Gel surface preparation technique was evaluated. Fatigue coupon tests produced Sol-Gel results that could be compared with a large performance database from conventional, riveted repairs. It was demonstrated that not only can composite doublers perform well in severe off-design conditions (low doubler stiffness and presence of defects in doubler installation) but that the Sol-Gel surface preparation technique is easier and quicker to carry out while still producing optimum bonding properties. Nondestructive inspection (NDI) methods were developed so that the potential for disbond and delamination growth could be monitored and crack growth mitigation could be quantified. The NDI methods were validated using full-scale test articles and the FedEx aircraft installations. It was demonstrated that specialized NDI techniques can detect flaws in composite doubler installations before they reach critical size. Probability of Detection studies were integrated into the FedEx training in order to quantify the ability of aircraft maintenance depots to properly monitor these repairs. In addition, Boeing Structural Repair and Nondestructive Testing Manuals were modified to include composite doubler repair and inspection procedures. This report presents the results from the FedEx Pilot Program that involved installation and surveillance of numerous repairs on operating aircraft. Results from critical NDI evaluations are reported in light of damage tolerance assessments for bonded composite doublers. This work has produced significant interest from airlines and aircraft manufacturers. The successful Pilot Program produced flight performance history to establish the durability of bonded composite patches as a permanent repair on commercial aircraft structures. This report discusses both the laboratory data and Pilot Program results from repair installations on operating aircraft to introduce composite doubler repairs into mainstream commercial aircraft use.

  4. Role of DNA repair protein ERCC1 in skin cancer 

    E-Print Network [OSTI]

    Song, Liang

    2009-01-01

    Nucleotide excision repair (NER) is one of the major repair systems for removal of DNA lesions. The NER pathway has evolved mainly to repair UV-induced DNA damage and is also active against a broad range of endogenously ...

  5. Leveraging Service Calls and Emergency Repairs for Energy Efficiency...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Service Calls and Emergency Repairs for Energy Efficiency Marketing Leveraging Service Calls and Emergency Repairs for Energy Efficiency Marketing Better Buildings Residential...

  6. Solar Water Heating System Maintenance and Repair | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Solar Water Heating System Maintenance and Repair Solar Water Heating System Maintenance and Repair May 30, 2012 - 2:35pm Addthis Rooftop solar water heaters need regular...

  7. From Validation to Automated Repair & Beyond with Constraint Solving

    E-Print Network [OSTI]

    Samimi, Hesam

    2013-01-01

    HTML GenerationRepair: Automated Repair of HTML Generation Errors in PHPrenderings of our invalid HTML page in Google Chrome 13.0 (

  8. Reducing Your Leak Rate Without Repairing Leaks 

    E-Print Network [OSTI]

    Beals, C.

    2005-01-01

    below the header pressure have the added advantage of reducing the air consumption of equipment, as well as reducing the leak rate. Turn Off the Air to Idle Equipment In most plants, when production equipment operators shut off their equipment... of the reason why plant personnel often find leak repair unproductive. The other reason relates to the compressor controls. If the plant had several lubricated rotary screw compressors operating in modulation, repairing 2,000 cfm in leaks may only reduce...

  9. INTERNAL REPAIR OF GAS PIPLINES SURVEY OF OPERATOR EXPERIENCE AND INDUSTRY NEEDS REPORT

    SciTech Connect (OSTI)

    Ian D. Harris

    2003-09-01

    A repair method that can be applied from the inside of a gas transmission pipeline (i.e., a trenchless repair) is an attractive alternative to conventional repair methods since the need to excavate the pipeline is precluded. This is particularly true for pipelines in environmentally sensitive and highly populated areas. The objectives of the project are to evaluate, develop, demonstrate, and validate internal repair methods for pipelines; develop a functional specification for an internal pipeline repair system; and prepare a recommended practice for internal repair of pipelines. The purpose of this survey is to better understand the needs and performance requirements of the natural gas transmission industry regarding internal repair. A total of fifty-six surveys were sent to pipeline operators. A total of twenty completed surveys were returned, representing a 36% response rate, which is considered very good given the fact that tailored surveys are known in the marketing industry to seldom attract more than a 10% response rate. The twenty survey responses produced the following principal conclusions: (1) Use of internal weld repair is most attractive for river crossings, under other bodies of water (e.g., lakes and swamps) in difficult soil conditions, under highways, under congested intersections, and under railway crossings. All these areas tend to be very difficult and very costly if, and where, conventional excavated repairs may be currently used. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling (HDD) when a new bore must be created to solve a leak or other problem in a water/river crossing. (3) The typical travel distances required can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). In concept, these groups require pig-based systems; despooled umbilical systems could be considered for the first two groups. For the last group a self-propelled system with an onboard self-contained power and welding system is required. (4) Pipe size range requirements range from 50.8 mm (2 in.) through 1,219.2 mm (48 in.) in diameter. The most common size range for 80% to 90% of operators surveyed is 508 mm to 762 mm (20 in. to 30 in.) diameter, with 95% using 558.8 mm (22 in.) diameter pipe.

  10. HYDROGEN EFFECTS ON LASER ENGINEERED NET SHAPE (LENS) REPAIRED WELDMENTS

    SciTech Connect (OSTI)

    Korinko, P; Thad Adams, T

    2006-10-06

    New methods of repairing mis-machined components are always of interest. In this study, an innovative method using Laser Engineered Net Shape{trademark} (LENS{reg_sign}) forming was used to repair intentionally mis-machined test articles. The components were repaired and subsequently hydrogen charged and burst tested. The LENS repair did not have an adverse effect on the solid state weld process that was used to repair the components. Hydrogen charged samples failed in a similar manner to the uncharged samples. Overall, the prospects for LENS repairing similar products are favorable and further work is encouraged.

  11. Repairable chip bonding/interconnect process

    DOE Patents [OSTI]

    Bernhardt, Anthony F. (Berkeley, CA); Contolini, Robert J. (Livermore, CA); Malba, Vincent (Livermore, CA); Riddle, Robert A. (Tracy, CA)

    1997-01-01

    A repairable, chip-to-board interconnect process which addresses cost and testability issues in the multi-chip modules. This process can be carried out using a chip-on-sacrificial-substrate technique, involving laser processing. This process avoids the curing/solvent evolution problems encountered in prior approaches, as well is resolving prior plating problems and the requirements for fillets. For repairable high speed chip-to-board connection, transmission lines can be formed on the sides of the chip from chip bond pads, ending in a gull wing at the bottom of the chip for subsequent solder.

  12. Repairable chip bonding/interconnect process

    DOE Patents [OSTI]

    Bernhardt, A.F.; Contolini, R.J.; Malba, V.; Riddle, R.A.

    1997-08-05

    A repairable, chip-to-board interconnect process which addresses cost and testability issues in the multi-chip modules is disclosed. This process can be carried out using a chip-on-sacrificial-substrate technique, involving laser processing. This process avoids the curing/solvent evolution problems encountered in prior approaches, as well is resolving prior plating problems and the requirements for fillets. For repairable high speed chip-to-board connection, transmission lines can be formed on the sides of the chip from chip bond pads, ending in a gull wing at the bottom of the chip for subsequent solder. 10 figs.

  13. Development of a composite repair system for reinforcing offshore risers 

    E-Print Network [OSTI]

    Alexander, Christopher Richard

    2009-05-15

    A research program was conducted to investigate the application of composite materials in repairing corroded offshore risers, leading to the development of an optimized repair using a hybrid carbon/E-glass system. The objective of this research...

  14. Solar Water Heating System Maintenance and Repair | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Water Heating System Maintenance and Repair Solar Water Heating System Maintenance and Repair May 30, 2012 - 2:35pm Addthis Rooftop solar water heaters need regular maintenance to...

  15. Repairable File and Storage Systems A Dissertation Presented

    E-Print Network [OSTI]

    Chiueh, Tzi-cker

    Repairable File and Storage Systems A Dissertation Presented by Ningning Zhu to The Graduate School of the Dissertation Repairable File and Storage System by Ningning Zhu Doctor of Philosophy in Computer Science Stony stream file/storage system. Repairable file/storage system needs to perform two tasks. First it has

  16. Asymptotic Interference Alignment for Exact Repair in Distributed Storage Systems

    E-Print Network [OSTI]

    Jafar, Syed A.

    Asymptotic Interference Alignment for Exact Repair in Distributed Storage Systems Viveck R. Cadambe consider a distributed storage system where a file of size M is stored in n distributed storage nodes using of this paper is to repair failed nodes in the storage system, by replacing them by their replicas (exact repair

  17. Emergency pipe line repair connects subsea pipe lines

    SciTech Connect (OSTI)

    Lerique, M.P.; Thiberge, P. ); Wright, N. )

    1990-11-01

    Emergency repair of any subsea line pipe must form a high-integrity, metal-to-metal seal. This paper presents a remote, diverless repair system that utilizes master flanges, a connector and a spool piece to repair line pipe in deep offshore waters.

  18. Level of Repair Analysis and Minimum Cost Homomorphisms of Graphs

    E-Print Network [OSTI]

    Gutin, Gregory

    of Lillian Barros Abstract. Level of Repair Analysis (LORA) is a prescribed procedure for defence logistics, LORA seeks to determine an optimal provision of repair and maintenance facilities to minimize overall on bipartite graphs is polynomial time solvable. Keywords: Computational Logistics; Level of Repair Analysis

  19. EPA Lead Safety for Renovation, Repair and

    E-Print Network [OSTI]

    Tennessee, University of

    EPA Lead Safety for Renovation, Repair and Painting (RRP) Course Certified Renovators Class, CSP, CHMM, Certified Lead Paint Inspector.; Certified Renovator; EPA Ac- credited Lead RRP trainer or fax registratio Registration Form Cash Method of Payment Check Name Mailing Address Phone Lead Safety

  20. Visualization of Mismatch Repair in Bacterial Cells

    E-Print Network [OSTI]

    Smith, Bradley T.

    We determined the localizations of mismatch repair proteins in living Bacillus subtilis cells. MutS-GFP colocalized with the chromosome in all cells and formed foci in a subset of cells. MutL-GFP formed foci in a subset ...

  1. New Technologies for Repairing Aging Cables in Nuclear Power Plants

    SciTech Connect (OSTI)

    Simmons, Kevin L. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Fifield, Leonard S. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States); Westman, Matthew P. [Pacific Northwest National Lab. (PNNL), Richland, WA (United States)

    2013-09-11

    The goal of this project is to demonstrate a proof-of-concept for a technique to repair aging cables that have been subjected to degradation associated with long-term thermal and radiation exposure in nuclear power plants. The physical degradation of the aging cables manifests itself primarily as cracking and increased brittleness of the polymeric electrical insulation. Therefore, the proposed cable-repair concept comprises development of techniques to impart a softening agent within the deteriorated polymer insulation jacket so as to regain the ability of the insulation to stretch without failing and possibly to heal existing cracks in the insulation. Our approach is to use commercially available ethylene-propylene rubber (EPR) as the relevant test material, demonstrate the adsorption of chemical treatments in the EPR and quantify changes in resulting physical and mechanical properties. EPR cable samples have been thermally treated in air to produce specimens corresponding to the full range of cable age-performance points from new (>350% elongation at break) to end-of-life (<50% elongation at break). The current focus is on two chemical treatments selected as candidates for restoring age-related cable elasticity loss: a rubber plasticizer and a reactive silane molecule. EPR specimens of 200, 150, 100, and 50% elongation at break have been soaked in the candidate chemical treatments and the kinetics of chemical uptake, measured by change in mass of the samples, has been determined. Mechanical properties as a function of aging and chemical treatment have been measured including ultimate tensile strength, tensile modulus at 50% strain, elongation at break, and storage modulus. Dimensional changes with treatment and changes in glass transition temperature were also investigated. These ongoing experiments are expected to provide insight into the physical-chemical nature of the effect of thermal degradation on EPR rejuvenation limits and to advance novel methods for restoring the ability of degraded EPR to be compliant and resist fracture. The results of this research reveal that absorption of chemical treatments can lower the glass transition temperature and modulus of EPR. Chemical treatments pursued thus far have proven ineffective at restoring EPR strength and elongation at break. Future work will combine the plasticizer modalities found to successfully increase the volume of the EPR, reduce EPR glass transition temperature and reduce EPR modulus with promising chemistries that will repair the damage of the polymer, potentially using the plasticizer as a host for the new chemistry.

  2. Repair of ultraviolet-light-induced damage

    SciTech Connect (OSTI)

    Sutherland, B.M.

    1981-01-01

    Studies are reviewed which present three major new findings in the photobiology of skin. First, detectable numbers of dimers are formed even at sub-erythymal doses. Second, excision of dimers is much more rapid than would be predicted from results obtained in cell culture. Third, comparison of the rates of excision and photoreactivation in skin indicates that in normal sunlight exposure, photoreactivation may well be the predominant repair pathway in skin. (ACR)

  3. Summer Projects 2013 Major Capital Projects

    E-Print Network [OSTI]

    Alvarez, Pedro J.

    Sidewalk #12;Rice Stadium Electrical Repairs · Electrical switchgear · Home locker room floor · Football

  4. ASTRID sodium cooled fast reactor: Program for improving in service inspection and repair

    SciTech Connect (OSTI)

    Jadot, F.; De Dinechin, G.; Augem, J. M.; Sibilo, J.

    2011-07-01

    In the frame of the CEA, EDF, AREVA coordinated research program for the development of Generation IV sodium-cooled fast reactors (SFR), the ASTRID project was launched in 2010. For the future prototype, the improvement of in-service inspection and repair (ISI and R) capabilities was identified as a major issue. Following the pluri-annual SFR research program, the ISI and R main R and D axes remain: i) improvement of the primary system conceptual design, ii) development of measurement and inspection techniques (continuous monitoring instrumentation and periodic inspection tools), iii) accessibility and associated robotics, and iv) development and validation of repair processes. Associated ISI and R needs are being defined through an iterative method between designers and instrumentation specialists: adaptation of the Design to ISI and R requirements, fission chamber development, validation of the ultrasonic and chemical transducers, of ultrasonic non destructive simulation, of acoustic surveillance, of laser repair intervention processes, of connected robotic equipment. Moreover, CEA, as leader of the ASTRID Project, is willing to find new contributors, partners or suppliers, in order to get innovative, diversified, exhaustive and efficient solutions. (authors)

  5. Project Year Project Team

    E-Print Network [OSTI]

    Gray, Jeffrey J.

    Project Year 2001 Project Team Faculty: Grace Brush, Geography & Environmental Engineering, Whiting School of Engineering Fellow: Dan Bain, Geography & Environmental Engineering, Whiting School. Through this project, the team proposes to develop a variety of resources: a set of general, web

  6. SNL Researchers Assess Wind Turbine Blade Inspection and Repair...

    Broader source: Energy.gov (indexed) [DOE]

    also inform how blade inspections are conducted at manufacturing facilities and wind farms, thereby improving maintenance and repair procedures for wind turbine blades. SNL is...

  7. Solar Cells, Wound Repair Winning GVC Technologies | ornl.gov

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Solar Cells, Wound Repair Winning GVC Technologies March 26, 2010 Graduate student teams from the University of Arkansas and the University of Maryland earned first place in the...

  8. Protein Bridges DNA Base and Nucleotide Excision Repair Pathways

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Bridges DNA Base and Nucleotide Excision Repair Pathways Print Alkyltransferase proteins (AGT) protect cells from the biological effects of DNA damage caused by the addition...

  9. Model Repair Specifications for Low Voltage Induction Motors

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EASA AR100-1998 Recommended Practice For The Repair of Rotating Electrical Apparatus IEEE IEEE Std. 43, Recommended Practice for Testing Insulation Resistance of Rotating...

  10. Investigating the Role of Vitamin D and DNA Repair in Influencing Cancer Presentation and Outcomes 

    E-Print Network [OSTI]

    Syed, Moinuddin Mohammed

    2014-09-26

    differences in DNA repair genes exist, which may in turn contribute to underlying differences in DNA repair capacity. These genes with high Fst value represent all six known common DNA repair pathways and DDR response. This supports our hypothesis...

  11. Waste minimization in an autobody repair shop

    SciTech Connect (OSTI)

    Baria, D.N.; Dorland, D.; Bergeron, J.T.

    1994-12-31

    This work was done to document the waste minimization incorporated in a new autobody repair facility in Hermantown, Minnesota. Humes Collision Center incorporated new waste reduction techniques when it expanded its old facilities in 1992 and it was able to achieve the benefits of cost reduction and waste reduction. Humes Collision Center repairs an average of 500 cars annually and is a very small quantity generator (VSQG) of hazardous waste, as defined by the Minnesota Pollution Control Agency (MPCA). The hazardous waste consists of antifreeze, batteries, paint sludge, refrigerants, and used oil, while the nonhazardous waste consists of cardboard, glass, paint filters, plastic, sanding dust, scrap metal, and wastewater. The hazardous and nonhazardous waste output were decreased by 72%. In addition, there was a 63% reduction in the operating costs. The waste minimization includes antifreeze recovery and recycling, reduction in unused waste paint, reduction, recovery and recycle of waste lacquer thinner for cleaning spray guns and paint cups, elimination of used plastic car bags, recovery and recycle of refrigerant, reduction in waste sandpaper and elimination of sanding dust, and elimination of waste paint filters. The rate of return on the investment in waste minimization equipment is estimated from 37% per year for the distillation unit, 80% for vacuum sanding, 146% for computerized paint mixing, 211% for the refrigerant recycler, to 588% per year for the gun washer. The corresponding payback time varies from 3 years to 2 months.

  12. Computational model of aortic valve surgical repair using grafted pericardium

    E-Print Network [OSTI]

    1 Computational model of aortic valve surgical repair using grafted pericardium Peter E. Hammer1, aortic valve repair, membrane, surgical planning, leaflet graft, pericardium ABSTRACT Aortic valve leaflets. Difficulty is largely due to the complex geometry and function of the valve and the lower

  13. Injury and Repair: Retinal Remodeling Robert E. Marc

    E-Print Network [OSTI]

    Marc, Robert E.

    Injury and Repair: Retinal Remodeling Robert E. Marc Department of Ophthalmology John A. Moran Eye Center 65 Mario Capecchi Dr University of Utah Salt Lake City, UT 84132 robert.marc@hsc.utah.edu Keywords photoreceptors In press Elsevier Encyclopedia of the Eye Robert E. Marc :: Chapter 220 :: Injury and Repair

  14. Coherent testing and simulation of composite blade repair 

    E-Print Network [OSTI]

    McNichols, Brian Glenn

    1997-01-01

    The objective of this research program is to experimentally and computationally determine the static and fatigue response for two methods of repair to an E/Glass-Epoxy sandwich laminate. The proposed methods of repair are a scarf and overlap patch...

  15. Simplification and Repair of Polygonal Models Using Volumetric Techniques

    E-Print Network [OSTI]

    Turk, Greg

    data sets. Medical sensing technology such as MRI, CT, and PET scanners produce large volume data sets that are nonmanifold and simplification of models. Repair is the process of taking a model that may have undesirable representation that yields a simple yet effective solution to polygon repair. The same voxelization process

  16. Regulation of endometrial repair and its impact on heavy menstrual bleeding 

    E-Print Network [OSTI]

    Maybin, Jacqueline Ann

    2011-11-25

    Introduction: The human endometrium has a remarkable capacity for efficient cyclical repair following the inflammatory process of menstruation. Defective postmenstrual repair may contribute to the common complaint of ...

  17. LASER ENGINEERED NET SHAPING FOR REPAIR AND HYDROGEN COMPATIBILITY

    SciTech Connect (OSTI)

    Korinko, P.; Adams, T.

    2011-08-05

    A method to repair mismatched or damaged components using Laser Engineered Net Shaping{sup R} (LENS) technology to apply material was investigated for its feasibility for components exposed to hydrogen. The mechanical properties of LENS bulk materials were also tested for hydrogen compatibility. The LENS process was used to repair simulated and actual mismachined components. These sample components were hydrogen charged and burst tested in the as-received, as-damaged, and as-repaired conditions. The testing showed that there was no apparent additional deficiency associated with hydrogen charging compared to the repair technique. The repair techniques resulted in some components meeting the requirements while others did not. Additional procedure/process development is required prior to recommending production use of LENS.

  18. DNA repair: Dynamic defenders against cancer and aging

    SciTech Connect (OSTI)

    Fuss, Jill O.; Cooper, Priscilla K.

    2006-04-01

    You probably weren't thinking about your body's cellular DNA repair systems the last time you sat on the beach in the bright sunshine. Fortunately, however, while you were subjecting your DNA to the harmful effects of ultraviolet light, your cells were busy repairing the damage. The idea that our genetic material could be damaged by the sun was not appreciated in the early days of molecular biology. When Watson and Crick discovered the structure of DNA in 1953 [1], it was assumed that DNA is fundamentally stable since it carries the blueprint of life. However, over 50 years of research have revealed that our DNA is under constant assault by sunlight, oxygen, radiation, various chemicals, and even our own cellular processes. Cleverly, evolution has provided our cells with a diverse set of tools to repair the damage that Mother Nature causes. DNA repair processes restore the normal nucleotide sequence and DNA structure of the genome after damage [2]. These responses are highly varied and exquisitely regulated. DNA repair mechanisms are traditionally characterized by the type of damage repaired. A large variety of chemical modifications can alter normal DNA bases and either lead to mutations or block transcription if not repaired, and three distinct pathways exist to remove base damage. Base excision repair (BER) corrects DNA base alterations that do not distort the overall structure of the DNA helix such as bases damaged by oxidation resulting from normal cellular metabolism. While BER removes single damaged bases, nucleotide excision repair (NER) removes short segments of nucleotides (called oligonucleotides) containing damaged bases. NER responds to any alteration that distorts the DNA helix and is the mechanism responsible for repairing bulky base damage caused by carcinogenic chemicals such as benzo [a]pyrene (found in cigarette smoke and automobile exhaust) as well as covalent linkages between adjacent pyrimidine bases resulting from the ultraviolet (UV) component of sunlight. NER can be divided into two classes based on where the repair occurs. NER occurring in DNA that is not undergoing transcription (i.e., most of the genome) is called global genome repair (GGR or GGNER), while NER taking place in the transcribed strand of active genes is called transcription-coupled repair (TCR or TC-NER). We will explore NER in more detail below. Mismatch repair (MMR) is another type of excision repair that specifically removes mispaired bases resulting from replication errors. DNA damage can also result in breaks in the DNA backbone, in one or both strands. Single-strand breaks (SSBs) are efficiently repaired by a mechanism that shares common features with the later steps in BER. Double-strand breaks (DSBs) are especially devastating since by definition there is no intact complementary strand to serve as a template for repair, and even one unrepaired DSB can be lethal [3]. In cells that have replicated their DNA prior to cell division, the missing information can be supplied by the duplicate copy, or sister chromatid, and DSBs in these cells are faithfully repaired by homologous recombination involving the exchange of strands of DNA between the two copies. However, most cells in the body are non-dividing, and in these cells the major mechanism for repairing DSBs is by non-homologous end joining (NHEJ), which as the name implies involves joining two broken DNA ends together without a requirement for homologous sequence and which therefore has a high potential for loss of genetic information.

  19. Using instrument scraper surveys for corrosion repair

    SciTech Connect (OSTI)

    Akhnoukh, S.R.; Baghabrah, M.A. (Aramco (SA))

    1990-07-01

    This paper reports on a program for overall pipe line repair. This program was implemented to maintain pipe line integrity and for identifying problem areas which require reconditioning or replacing by: reviewing pipe line leak history; checking periodically lifetime expectancy and integrity of pipe coatings; using cathodic protection annual survey results to locate low potential areas (close-interval survey is needed to identify the exact location of corrosion); and hydrotesting the pipe line (using leaks or ruptures from the hydrotest to identify problem areas). The pipe line revalidation plan is insufficient for identifying pipe line leaks. Instrumented pig testing provides more accurate and reliable ways of testing the pipe line for internal or external corrosion or defects.

  20. Best Management Practices (BMPs) for the Ship and Boat Building and Repair

    E-Print Network [OSTI]

    .................................................................................................................. 1 1.3 PROFILE OF THE B.C. SHIPBUILDING AND REPAIR INDUSTRY

  1. Intermediate hearth repair technique at Thyssen Stahl AG

    SciTech Connect (OSTI)

    Kowalski, W.; Bachhofen, H.J.; Ruether, P.; Ballewski, T. [Thyssen Stahl AG, Duisburg (Germany)

    1996-12-31

    Nowadays various techniques for the fastest possible intermediate repair and/or emplacement of refractory materials above the tuyere level allow a significant extension of furnace campaign life. The latter are hence now exclusively determined by the service life of the hearth. The improvement of hearth monitoring and the estimation of residual brick strength of the refractory lining on the basis of temperature measurements in the hearth enable the location of individual zones of premature wear. These measurement methods, which were developed by Thyssen Stahl AG, aid the decision to undertake selective repair of the hearth. Three areas of repair are differentiated: taphole zone; hearth wall, localized; and hearth wall, extensive. This hearth repair method is described in this report using the example of hearth refurbishing blast furnace 8, Hamborn.

  2. Repair Sequences in American Learners of German Interlanguage

    E-Print Network [OSTI]

    Wisbey, Evelyn

    2010-04-25

    This study in Conversation Analysis investigates the organization of other-initiated repair sequences in American learners of German, i.e., it examines how learners deal with troubles in hearing or understanding that they ...

  3. Extended mechanical stimulations of cartilage for growth and repair

    E-Print Network [OSTI]

    Lee, Gary C. (Gary Chiaray), 1980-

    2004-01-01

    Extended mechanical stimulation of articular cartilage in an in vitro model explant system promotes growth and repair. An alternating day mechanical loading protocol consisting of dynamic sinusoidal compression results in ...

  4. Factories: The Shipbuilding and Ship-repairing Regulations 1960 

    E-Print Network [OSTI]

    Hare, John

    1960-01-01

    These Regulations revoke the Shipbuilding Regulations, 1931, which were designed for the safety, health and welfare of persons employed in the construction and repair of ships in sbipbuilding yards. The present Regulations, ...

  5. Development/Plasticity/Repair Dorsally and Ventrally Derived Oligodendrocytes Have

    E-Print Network [OSTI]

    Richardson, William D.

    Development/Plasticity/Repair Dorsally and Ventrally Derived Oligodendrocytes Have Similar derived oligodendrocyte (OL) lineage cells have different properties. We generated a dual reporter mouse line to color code ventrally and dorsally derived OLPs (vOLPs and d

  6. Repairs for damaged bolt holes in continuous fiber reinforced plastics 

    E-Print Network [OSTI]

    Copps, Kevin Daniel

    1992-01-01

    of fastened joints and to investigate previous techniques for the repair of continuous fiber reinforced plastics. LITERATURE REVIEW Characterizing Failure Modes There is very little agreement about what conditions constitute failure in composite joints... of possible methods for preventing and repairing fastener hole defects. Proper drilling technique The optimal drilling conditions for fiber reinforced parts are hard to control, and can differ depending on the structural application. The proper technique...

  7. Biochemical characterization of the E. coli Very Short Patch Repair pathway and its coordination with methyltransferase repair of 0?-methylguanine

    E-Print Network [OSTI]

    Rye, Peter Thomas

    2006-01-01

    The E. coli Very Short Patch Repair (VSPR) system corrects T:G mismatches that arise through Dcm-mediated methylation and subsequent deamination of the underlined cytosine residue in the palindromic sequence 5'-CCWGG-3' ...

  8. Application of discrete event simulation techniques for prioritization of U.S. Air Force Military Family Housing Projects 

    E-Print Network [OSTI]

    Krukenberg, Harry J.

    1996-01-01

    This study, through the use of discrete event simulation and modeling, explores various prioritization disciplines for U.S. Air Force Military Family Housing maintenance, repair, and renovation projects. Actual data from the Military Family Housing...

  9. Project Plan Remote Target Fabrication Refurbishment Project

    SciTech Connect (OSTI)

    Bell, Gary L; Taylor, Robin D

    2009-08-01

    In early FY2009, the DOE Office of Science - Nuclear Physics Program reinstated a program for continued production of {sup 252}Cf and other transcurium isotopes at the Radiochemical Engineering Development Center (REDC) at Oak Ridge National Laboratory (ORNL). The FY2009 major elements of the workscope are as follows: (1) Recovery and processing of seven transuranium element targets undergoing irradiation at the High Flux Isotope Reactor (HFIR) at ORNL; (2) Development of a plan to manufacture new targets for irradiation beginning in early- to mid-FY10 to supply irradiated targets for processing Campaign 75 (TRU75); and (3) Refurbishment of the target manufacturing equipment to allow new target manufacture in early FY10 The {sup 252}Cf product from processing Campaign 74 (recently processed and currently shipping to customers) is expected to supply the domestic demands for a period of approximately two years. Therefore it is essential that new targets be introduced for irradiation by the second quarter of FY10 (HFIR cycle 427) to maintain supply of {sup 252}Cf; the average irradiation period is {approx}10 HFIR cycles, requiring about 1.5 calendar years. The strategy for continued production of {sup 252}Cf depends upon repairing and refurbishing the existing pellet and target fabrication equipment for one additional target production campaign. This equipment dates from the mid-1960s to the late 1980s, and during the last target fabrication campaign in 2005- 2006, a number of component failures and operations difficulties were encountered. It is expected that following the target fabrication and acceptance testing of the targets that will supply material for processing Campaign 75 a comprehensive upgrade and replacement of the remote hot-cell equipment will be required prior to subsequent campaigns. Such a major refit could start in early FY 2011 and would take about 2 years to complete. Scope and cost estimates for the repairs described herein were developed, and authorization for the work was received in July 2009 under the Remote Target Fabrication Refurbishment Task of the Enhanced Utilization of Isotope Facilities project (Project Identification Code 2005230) funded by the American Recovery and Reinvestment Act of 2009. The goal of this project is to recover the capability to produce 4-5 curium targets for the irradiation period starting with HFIR cycle 427, currently scheduled to begin 2/17/10. Assuming success, the equipment would then be used to fabricate 6-7 additional targets to hold for the next irradiation campaign specified by the program. Specific objectives are the return to functionality of the Cubicle 3 Pellet Fabrication Line; Cubicle 2 Target Assembly equipment; and Cubicle 1 Target Inspection and Final Assembly system.

  10. Polymer nanocomposites for high-temperature composite repair

    SciTech Connect (OSTI)

    Sheng, Xia

    2008-12-01

    A novel repair agent for resin-injection repair of advanced high temperature composites was developed and characterized. The repair agent was based on bisphenol E cyanate ester (BECy) and reinforced with alumina nanoparticles. To ensure good dispersion and compatibility with the BECy matrix in nanocomposites, the alumina nanoparticles were functionalized with silanes. The BECy nanocomposites, containing bare and functionalized alumina nanoparticles, were prepared and evaluated for their thermal, mechanical, rheological, and viscoelastic properties. The monomer of BECy has an extremely low viscosity at ambient temperature, which is good for processability. The cured BECy polymer is a highly cross-linked network with excellent thermal mechanical properties, with a high glass transition temperature (T{sub g}) of 270 C and decomposition temperature above 350 C. The incorporation of alumina nanoparticles enhances the mechanical and rheological properties of the BECy nanocomposites. Additionally, the alumina nanoparticles are shown to catalyze the cure of BECy. Characterization of the nanocomposites included dynamic mechanical analysis, differential scanning calorimetry, thermogravimetric analysis, rheological and rheokinetic evaluation, and transmission electron microscopy. The experimental results show that the BECy nanocomposite is a good candidate as repair agent for resin-injection repair applications.

  11. The repair and rehabilitation method of Tokyo gas

    SciTech Connect (OSTI)

    Yagi, Shuichi [Tokyo Gas Co., Ltd. (Japan)

    1996-08-01

    It has been an important matter for gas utilities to maintain their pipelines easily and economically. But pipes that have become old suffer from progressive corrosion, and as a result of vibration caused by traffic or the effects of land subsidence, joints can become loosened. To repair pipes that have suffered in such ways, the usual method to do is to dig them up and replace them with new ones. But this method requires a large amount of excavation, so the work takes a long time to complete and is costly. To deal with these problems, Tokyo Gas developed number of repair and rehabilitation methods to permit renewal of pipelines without replacing them. In this paper, I would like to introduce our repair and rehabilitation methods for low-pressure pipeline. 4 refs., 9 figs., 4 tabs.

  12. CX-008144: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Planned Repair of Flow Lines CX(s) Applied: B5.4 Date: 08/09/2011 Location(s): Wyoming Offices(s): RMOTC

  13. CX-010656: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Stormwater Drainage Repair CX(s) Applied: B1.3 Date: 06/18/2013 Location(s): South Carolina Offices(s): Savannah River Operations Office

  14. Ice plug employed on subsea pipeline bend during repair

    SciTech Connect (OSTI)

    1997-12-22

    The first controlled-temperature ice plug in the bend of an offshore gas trunkline has been carried out for Phillips Petroleum Co. Norway on its Norpipe A.S. platform in the German sector of the North Sea. The procedure was part of a subsea valve repair operation. The ice plug was successfully formed offshore and tested to a differential pressure of 1,450 psi. Repair of two valves required only 5 days during which time gas production was operating at close to 50--60% via the platform bypass, says the service company. The paper discusses the procedure.

  15. Project Year Project Team

    E-Print Network [OSTI]

    Gray, Jeffrey J.

    & Sciences Project Title Visualize Physical Principles with Virtual Lab Modules Audience Undergraduate provide easy access to digital information, but don't provide experience with right- hand screws, electric of the last generation of physics students. The result is that today's students don't have an intuitive

  16. Project Year Project Title

    E-Print Network [OSTI]

    Gray, Jeffrey J.

    . Pedagogical Issue One of the challenges in teaching the Introduction to Computer Music course is the lack flow and practices. These resources will provide an online space through which students will be able piece of this project will be an animated studio walkthrough requiring user interaction and providing

  17. From Breaking Bad to Worse: Exploiting Homologous DNA Repair Deficiency in Cancer

    E-Print Network [OSTI]

    Hemann, Michael

    DNA repair deficiencies are common among cancer cells and represent a potential vulnerability that might be exploited by targeting compensatory repair pathways. However, the identification of synthetically lethal combinations ...

  18. The cellular role of the specific immune system in fracture repair 

    E-Print Network [OSTI]

    Gaston, Mark S

    2009-01-01

    This thesis embodies a novel investigation into the cellular role of the specific immune system in fracture repair....

  19. New Technologies for Repairing Aging Cables in Nuclear Power Plants: M3LW-14OR0404015 Cable Rejuvenation Report

    SciTech Connect (OSTI)

    Simmons, Kevin L.; Fifield, Leonard S.; Westman, Matthew P.; Roberts, John A.

    2014-09-08

    The goal of this project is to conceptually demonstrate techniques to repair cables that have degraded through subjection to long-term thermal and radiation exposure in nuclear power plants. In fiscal year 2014 (FY14) we focused on commercially available ethylene-propylene rubber (EPR) as the relevant test material, isolated a high surface area form of the EPR material to facilitate chemical treatment screening and charaterization, and measured chemical changes in the material due to aging and treatment using Fourier Transfrom Infrared (FTIR) spectroscopy.

  20. Development of quick repairing technique for ceramic burner in hot stove of blast furnace

    SciTech Connect (OSTI)

    Kondo, Atsushi; Doura, Kouji; Nakamura, Hirofumi [Sumitomo Metal Industries, Ltd., Wakayama (Japan). Wakayama Steel Works

    1997-12-31

    Refractories of ceramic burner in hot stoves at Wakayama No. 4 blast furnace were damaged. There are only three hot stoves, so repairing must be done in a short. Therefore, a quick repairing technique for ceramic burners has been developed, and two ceramic burners were repaired in just 48 hours.

  1. Attacking and Repairing the Improved ModOnions Protocol

    E-Print Network [OSTI]

    Borisov, Nikita

    Attacking and Repairing the Improved ModOnions Protocol Nikita Borisov1 , Marek Klonowski2 presented in ACNS 2008. The protocol itself was proposed as an improved version of ModOnions, which uses universal re-encryption in order to avoid replay attacks. How- ever, ModOnions allowed the detour attack

  2. Availability Analysis of Repairable Computer Systems and Stationarity Detection

    E-Print Network [OSTI]

    Sericola, Bruno

    Availability Analysis of Repairable Computer Systems and Stationarity Detection Bruno Sericola computer system and we assume, as usual, that the system is modeled by a finite Markov process. We propose of performability measures. Index TermsĐRepairable computer systems, dependability, availability, performability

  3. Ancient bacteria show evidence of DNA repair Sarah Stewart Johnson*

    E-Print Network [OSTI]

    Nielsen, Rasmus

    Ancient bacteria show evidence of DNA repair Sarah Stewart Johnson* , Martin B. Hebsgaard , Torben for review June 14, 2007) Recent claims of cultivable ancient bacteria within sealed environ- ments highlight-term survival of bacteria sealed in frozen conditions for up to one million years. Our results show evidence

  4. Development/Plasticity/Repair Analogous Synaptic Plasticity Profiles Emerge from

    E-Print Network [OSTI]

    Narayanan, Rishikesh

    Development/Plasticity/Repair Analogous Synaptic Plasticity Profiles Emerge from Disparate Channel Institute of Technology, Calicut 637 601, India, and 3Bio-Medical Technology Wing, Sree Chitra Thirunal Institute for Medical Science & Technology, Trivandrum 695 012, India An open question within

  5. Development/Plasticity/Repair Group I Metabotropic Glutamate Receptors Control

    E-Print Network [OSTI]

    Grau, James

    Development/Plasticity/Repair Group I Metabotropic Glutamate Receptors Control Metaplasticity the spinal cord can support several forms of plasticity, including response­outcome (instrumental) learning. This inhibi- tion of plasticity in spinal learning is itself a form of plasticity that requires i

  6. The Self-Construction and -Repair of a Foraging

    E-Print Network [OSTI]

    Siegelmann , Hava T

    at explicit design of self-constructing and -repairing systems by hierarchical specification of elementary intracellular mechanisms via a kind of genetic code. The interplay between individual cells and the gradually are usually designed and constructed by a process that transforms an explicit, abstract description

  7. Thermosetting Polymer-Matrix Composites for Strucutral Repair Applications

    SciTech Connect (OSTI)

    William Kirby Goertzen

    2007-12-01

    Several classes of thermosetting polymer matrix composites were evaluated for use in structural repair applications. Initial work involved the characterization and evaluation of woven carbon fiber/epoxy matrix composites for structural pipeline repair. Cyanate ester resins were evaluated as a replacement for epoxy in composites for high-temperature pipe repair applications, and as the basis for adhesives for resin infusion repair of high-temperature composite materials. Carbon fiber/cyanate ester matrix composites and fumed silica/cyanate ester nanocomposites were evaluated for their thermal, mechanical, viscoelastic, and rheological properties as they relate to their structure, chemistry, and processing characteristics. The bisphenol E cyanate ester under investigation possesses a high glass transition temperature, excellent mechanical properties, and unique ambient temperature processability. The incorporate of fumed silica served to enhance the mechanical and rheological properties of the polymer and reduce thermal expansion without sacrificing glass transition or drastically altering curing kinetics. Characterization of the composites included dynamic mechanical analysis, thermomechanical analysis, differential scanning calorimetry, thermogravimetric analysis, rheological and rheokinetic evaluation, and transmission electron microscopy.

  8. http://nnr.sagepub.com Neurorehabilitation and Neural Repair

    E-Print Network [OSTI]

    Prochazka, Arthur

    displayed on a computer.The time taken to move to and click on each target was recorded. Results. The use of Neurorehabilitation can be found at:Neurorehabilitation and Neural RepairAdditional services and information for http/2/188Citations at UNIV OF ALBERTA LIBRARY on February 18, 2010http://nnr.sagepub.comDownloaded from #12;Research

  9. Development/Plasticity/Repair Identification of Nicotinic Acetylcholine Receptor Recycling

    E-Print Network [OSTI]

    Alford, Simon

    Development/Plasticity/Repair Identification of Nicotinic Acetylcholine Receptor Recycling and Its plasticity; however, the recycling of receptors has never been observed at peripheral synapses. Using a novel the regulation of receptor density, which could lead to rapid alterations in synaptic efficacy. Key words: toxin

  10. Simplification and Repair of Polygonal Models Using Volumetric Techniques

    E-Print Network [OSTI]

    California at Berkeley, University of

    Simplification and Repair of Polygonal Models Using Volumetric Techniques Fakir S. Nooruddin a method for converting polygonal models to a volumetric representation in a way that handles models by converting a model to and from the volumetric domain. We also describe a new topology-altering simplification

  11. Project Controls

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28

    Project controls are systems used to plan, schedule, budget, and measure the performance of a project/program. The cost estimation package is one of the documents that is used to establish the baseline for project controls. This chapter gives a brief description of project controls and the role the cost estimation package plays.

  12. Development of a rapid design procedure for emergency repair of bridge columns using fiber-reinforced polymers

    E-Print Network [OSTI]

    Slater, Susan E.

    2008-01-01

    ACI), Building Research Establishment, Ltd. (BRE), Concrete Society and International Concrete Repair Institute jointly publish standards

  13. Testing and evaluation of grout repaired tubular members 

    E-Print Network [OSTI]

    Nunn, John Mansfield

    1992-01-01

    of Failed Weld Seam page 64 65 66 69 73 74 80 82 31 Ideahzed Tubular Dented Member for the Taby, Zhou, and the Parsanejad Methods. . . . . . . . . . . . . . , . 92 32 Dent Geometry for the Elhnas Method 96 33 Experimental Ultimate Capamty vs P... commonly used to repiur damaged tubular members. These include 1 ) welding a sleeve around the outside of the member in the location of the damage, 2 ) applying an externally grouted clamp, and 3 ) applying internal grout Ideally, the repair method...

  14. Providing protection: Agencies receive funding to repair, upgrade dams 

    E-Print Network [OSTI]

    Wythe, Kathy

    2009-01-01

    by Kathy Wythe tx H2O | pg. 26 Providing protection Agencies receive funding to repair, upgrade dams along with local partners, can apply for grant funds, he said. Construction of the dams began through four federal authorizations passed between... 1944 and 1981. Land rights were acquired from landowners, and local agencies constructed the dams with federal money from NRCS (formerly the Soil Conservation Service). Local sponsors?including cities, counties, local soil and water conservation...

  15. WPN 12-9: Weatherization Assistance Program Incidental Repair Measure Guidance

    Broader source: Energy.gov [DOE]

    To provide guidance on incidental repair measures (IRM) allowable under the U.S. Department of Energy Weatherization Assistance Program (WAP).

  16. adaptation of DNA repair Byrne, Rose T; Klingele, Audrey J; Cabot...

    Office of Scientific and Technical Information (OSTI)

    Evolution of extreme resistance to ionizing radiation via genetic adaptation of DNA repair Byrne, Rose T; Klingele, Audrey J; Cabot, Eric L; Schackwitz, Wendy S; Martin, Jeffrey A;...

  17. Brain necrosis after fractionated radiation therapy: Is the halftime for repair longer than we thought?

    SciTech Connect (OSTI)

    Bender, Edward T.

    2012-11-15

    Purpose: To derive a radiobiological model that enables the estimation of brain necrosis and spinal cord myelopathy rates for a variety of fractionation schemes, and to compare repair effects between brain and spinal cord. Methods: Sigmoidal dose response relationships for brain radiation necrosis and spinal cord myelopathy are derived from clinical data using nonlinear regression. Three different repair models are considered and the repair halftimes are included as regression parameters. Results: For radiation necrosis, a repair halftime of 38.1 (range 6.9-76) h is found with monoexponential repair, while for spinal cord myelopathy, a repair halftime of 4.1 (range 0-8) h is found. The best-fit alpha beta ratio is 0.96 (range 0.24-1.73)Conclusions: A radiobiological model that includes repair corrections can describe the clinical data for a variety of fraction sizes, fractionation schedules, and total doses. Modeling suggests a relatively long repair halftime for brain necrosis. This study suggests that the repair halftime for late radiation effects in the brain may be longer than is currently thought. If confirmed in future studies, this may lead to a re-evaluation of radiation fractionation schedules for some CNS diseases, particularly for those diseases where fractionated stereotactic radiation therapy is used.

  18. Development/Plasticity/Repair Identification of Modulators of Hair Cell Regeneration in the

    E-Print Network [OSTI]

    Rubel, Edwin

    Development/Plasticity/Repair Identification of Modulators of Hair Cell Regeneration levels, environmental toxins, and some medications can readily induce damage or loss of hair cells, often

  19. Development/Plasticity/Repair Glycine Transporter-1 Inhibition Promotes Striatal Axon

    E-Print Network [OSTI]

    Sulzer, David

    Development/Plasticity/Repair Glycine Transporter-1 Inhibition Promotes Striatal Axon Sprouting via injections of the toxin 6-hydroxydopamine. We used apharmacologicalapproachtoenhance

  20. project management

    National Nuclear Security Administration (NNSA)

    3%2A en Project Management and Systems Support http:www.nnsa.energy.govaboutusouroperationsapmprojectmanagementandsystemssupport

  1. Project Complete

    Broader source: Energy.gov [DOE]

    DOE has published its Record of Decision announcing and explaining DOE’s chosen project alternative and describing any commitments for mitigating potential environmental impacts. The NEPA process...

  2. Project Construction

    Broader source: Energy.gov [DOE]

    Integrating renewable energy into Federal new construction or major renovations requires effective structuring of the construction team and project schedule. This overview discusses key construction team considerations for renewable energy as well as timing and expectations for the construction phase. The project construction phase begins after a project is completely designed and the construction documents (100%) have been issued. Construction team skills and experience with renewable energy technologies are crucial during construction, as is how the integration of renewable energy affects the project construction schedule.

  3. Research Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    projects that involve UCSD faculty members and graduate students from the structural engineering (SE), mechanical and aerospace engineering (MAE), electrical and computer...

  4. RESEARCH PROJECTS February 13

    E-Print Network [OSTI]

    Schenato, Luca

    RESEARCH PROJECTS FP7 February 13 #12; FP7 COOPERATION #12; INTERNATIONAL RESEARCH PROJECTS FP7 COOPERATION ENERGY PROJECT ACRONYM: EFONET PROJECT TITLE: Energy foresight network PROJECT

  5. Blade reliability collaborative : collection of defect, damage and repair data.

    SciTech Connect (OSTI)

    Ashwill, Thomas D.; Ogilvie, Alistair B.; Paquette, Joshua A.

    2013-04-01

    The Blade Reliability Collaborative (BRC) was started by the Wind Energy Technologies Department of Sandia National Laboratories and DOE in 2010 with the goal of gaining insight into planned and unplanned O&M issues associated with wind turbine blades. A significant part of BRC is the Blade Defect, Damage and Repair Survey task, which will gather data from blade manufacturers, service companies, operators and prior studies to determine details about the largest sources of blade unreliability. This report summarizes the initial findings from this work.

  6. The rebuilding and repairing of electric motors and generators

    E-Print Network [OSTI]

    Ridenour, Roy Everett

    1918-01-01

    Motor After Coils had been Put Back in Place In the repairing and rebuilding of electric motors and generators there are three principal factors which must be considered. These factors are, service, cost and reliability. If a machine can easily... motor. This motor had been through a fire in a Cripple Creek mine. The insulation had been burned from the coils except in the slots where mica had been used. The solder was*melted from the rotor and the babbitt from the bearings. Water had been...

  7. TidGen Power System Commercialization Project

    SciTech Connect (OSTI)

    Sauer, Christopher R.; McEntee, Jarlath

    2013-12-30

    ORPC Maine, LLC, a wholly-owned subsidiary of Ocean Renewable Power Company, LLC (collectively ORPC), submits this Final Technical Report for the TidGen® Power System Commercialization Project (Project), partially funded by the U.S. Department of Energy (DE-EE0003647). The Project was built and operated in compliance with the Federal Energy Regulatory Commission (FERC) pilot project license (P-12711) and other permits and approvals needed for the Project. This report documents the methodologies, activities and results of the various phases of the Project, including design, engineering, procurement, assembly, installation, operation, licensing, environmental monitoring, retrieval, maintenance and repair. The Project represents a significant achievement for the renewable energy portfolio of the U.S. in general, and for the U.S. marine hydrokinetic (MHK) industry in particular. The stated Project goal was to advance, demonstrate and accelerate deployment and commercialization of ORPC’s tidal-current based hydrokinetic power generation system, including the energy extraction and conversion technology, associated power electronics, and interconnection equipment capable of reliably delivering electricity to the domestic power grid. ORPC achieved this goal by designing, building and operating the TidGen® Power System in 2012 and becoming the first federally licensed hydrokinetic tidal energy project to deliver electricity to a power grid under a power purchase agreement in North America. Located in Cobscook Bay between Eastport and Lubec, Maine, the TidGen® Power System was connected to the Bangor Hydro Electric utility grid at an on-shore station in North Lubec on September 13, 2012. ORPC obtained a FERC pilot project license for the Project on February 12, 2012 and the first Maine Department of Environmental Protection General Permit issued for a tidal energy project on January 31, 2012. In addition, ORPC entered into a 20-year agreement with Bangor Hydro Electric Company on January 1, 2013 for up to 5 megawatts at a price of $215/MWh, escalating at 2.0% per year.

  8. Genome-Wide Identification and 3D Modeling of Proteins involved in DNA Damage Recognition and Repair (Final Report)

    SciTech Connect (OSTI)

    Ruben A. Abagyan, PhD

    2004-04-15

    OAK-B135 DNA Damage Recognition and Repair (DDR and R) proteins play a critical role in cellular responses to low-dose radiation and are associated with cancer. the authors have performed a systematic, genome-wide computational analysis of genomic data for human genes involved in the DDR and R process. The significant achievements of this project include: (1) Construction of the computational pipeline for searching DDR and R genes, building and validation of 3D models of proteins involved in DDR and R; (2) Functional and structural annotation of the 3D models and generation of comprehensive lists of suggested knock-out mutations; (3) Important improvement of macromolecular docking technology and its application to predict the DNA-Protein complex conformation; (4) Development of a new algorithm for improved analysis of high-density oligonucleotide arrays for gene expression profiling; (5) Construction and maintenance of the DNA Damage Recognition and Repair Database; and (6) Producing 14 research papers (10 published and 4 in preparation).

  9. Genome-Wide Identification and 3D Modeling of Proteins involved in DNA Damage Recognition and Repair (Final Report)

    SciTech Connect (OSTI)

    Abagyan, Ruben; An, Jianghong

    2005-08-12

    DNA Damage Recognition and Repair (DDR&R) proteins play a critical role in cellular responses to low-dose radiation and are associated with cancer. We have performed a systematic, genome-wide computational analysis of genomic data for human genes involved in the DDR&R process. The significant achievements of this project include: 1) Construction of the computational pipeline for searching DDR&R genes, building and validation of 3D models of proteins involved in DDR&R; 2) Functional and structural annotation of the 3D models and generation of comprehensive lists of suggested knock-out mutations; and the development of a method to predict the effects of mutations. Large scale testing of technology to identify novel small binding pockets in protein structures leading to new DDRR inhibitor strategies 3) Improvements of macromolecular docking technology (see the CAPRI 1-3 and 4-5 results) 4) Development of a new algorithm for improved analysis of high-density oligonucleotide arrays for gene expression profiling; 5) Construction and maintenance of the DNA Damage Recognition and Repair Database; 6) Producing 15 research papers (12 published and 3 in preparation).

  10. EA-2008: Colorado River Storage Project Programmatic Operations and Maintenance Project; Coconino, Maricopa, Navajo, and Yavapai Counties (Arizona) and San Juan County (Utah)

    Broader source: Energy.gov [DOE]

    Western Area Power Administration is preparing an EA that assesses the potential environmental impacts of Western’s programmatic operations and management (O&M) process and an integrated vegetation management (IVM) program on the Colorado River Storage Project System. O&M activities would consist of aerial and ground patrols, regular and preventive maintenance, inspections and repairs, and road repair. The IVM program would remove vegetation to protect facilities from fire, control the spread of noxious weeds to protect environmental quality, establish and maintain stable, low-growing plant communities in the ROW, and activities for public and worker safety around transmission lines and other facilities.

  11. DOE/EA-2008: Colorado River Storage Project Programmatic Operations and Maintenance Project; Coconino, Maricopa, Navajo, and Yavapai Counties (Arizona) and San Juan County (Utah)

    Broader source: Energy.gov [DOE]

    Western Area Power Administration is preparing an EA that assesses the potential environmental impacts of Western’s programmatic operations and management (O&M) process and an integrated vegetation management (IVM) program on the Colorado River Storage Project System. O&M activities would consist of aerial and ground patrols, regular and preventive maintenance, inspections and repairs, and road repair. The IVM program would remove vegetation to protect facilities from fire, control the spread of noxious weeds to protect environmental quality, establish and maintain stable, low-growing plant communities in the ROW, and activities for public and worker safety around transmission lines and other facilities.

  12. Inter-individual variation in DNA repair capacity: A need for multi-pathway functional assays to promote translational DNA repair research

    E-Print Network [OSTI]

    Nagel, Zachary D.

    Why does a constant barrage of DNA damage lead to disease in some individuals, while others remain healthy? This article surveys current work addressing the implications of inter-individual variation in DNA repair capacity ...

  13. A Lightweight Network Repair Scheme for Data Collection Applications in ZigBee WSNs

    E-Print Network [OSTI]

    Tseng, Yu-Chee

    1 A Lightweight Network Repair Scheme for Data Collection Applications in ZigBee WSNs Meng networks (WSNs). In [4], a quick convergecast solution is proposed for data collection in a ZigBee beacon-enabled tree- based WSN. However, it does not consider the network repair issue. When a ZigBee router loses its

  14. On the Design of an Interactive, Patient-Specific Surgical Simulator for Mitral Valve Repair

    E-Print Network [OSTI]

    On the Design of an Interactive, Patient-Specific Surgical Simulator for Mitral Valve Repair Neil A repair of the mitral valve is a difficult procedure that is often avoided in favor of less effective valve replacement because of the associated technical challenges facing non-expert surgeons

  15. Cooperative Repair with Minimum-Storage Regenerating Codes for Distributed Storage

    E-Print Network [OSTI]

    Li, Baochun

    Cooperative Repair with Minimum-Storage Regenerating Codes for Distributed Storage Jun Li, Baochun--Distributed storage systems store redundant data to tolerate failures of storage nodes and lost data should be repaired when storage nodes fail. A class of MDS codes, called minimum- storage regenerating (MSR) codes

  16. Bridge Damage and Repair Costs from Hurricane Katrina Jamie Padgett1

    E-Print Network [OSTI]

    Padgett, Jamie Ellen

    Bridge Damage and Repair Costs from Hurricane Katrina Jamie Padgett1 ; Reginald DesRoches2 ; Bryant to repair or replace the bridges damaged during the hurricane is estimated at over $1 billion. This paper describes the observed damage patterns to bridges, including damage attributed to storm surge, wind, impact

  17. A Systematic Study of Automated Program Repair: Fixing 55 out of 105 Bugs for $8 Each

    E-Print Network [OSTI]

    New Mexico, University of

    maintenance, which consumes a daunting fraction of the total cost of software production [1]. AutomatedA Systematic Study of Automated Program Repair: Fixing 55 out of 105 Bugs for $8 Each Claire Le-source programs totaling 5.1 million lines of code and involving 10,193 test cases. GenProg automatically repairs

  18. Best Management Practices (BMPs) for Ship and Boat Building and Repair

    E-Print Network [OSTI]

    document for major British Columbia shipbuilding and repair facilities, Environment Canada has conducted a survey of existing practices at all shipbuilding facilities in B.C. (Peter Hatfield, 1993). These survey to the shipbuilding and repair industry. Many of the recommended practices are equally applicable to many other

  19. Proposal to negotiate an amendment to an existing blanket contract for the repair, recondioning or replacement of klystrons

    E-Print Network [OSTI]

    2012-01-01

    Proposal to negotiate an amendment to an existing blanket contract for the repair, recondioning or replacement of klystrons

  20. RaDON --Repair and Diagnosis in Ontology Networks Qiu Ji, Peter Haase, Guilin Qi, Pascal Hitzler, Steffen Stadtmuller

    E-Print Network [OSTI]

    Hitzler, Pascal

    RaDON -- Repair and Diagnosis in Ontology Networks Qiu Ji, Peter Haase, Guilin Qi, Pascal Hitzler by integrating multiple distributed ontologies. Our RaDON system pro- vides functionalities to repair ontologies. To meet the above mentioned needs, we develop the RaDON system to repair and diagnose not only

  1. Method of tissue repair using a composite material

    DOE Patents [OSTI]

    Hutchens, Stacy A; Woodward, Jonathan; Evans, Barbara R; O'Neill, Hugh M

    2014-03-18

    A composite biocompatible hydrogel material includes a porous polymer matrix, the polymer matrix including a plurality of pores and providing a Young's modulus of at least 10 GPa. A calcium comprising salt is disposed in at least some of the pores. The porous polymer matrix can comprise cellulose, including bacterial cellulose. The composite can be used as a bone graft material. A method of tissue repair within the body of animals includes the steps of providing a composite biocompatible hydrogel material including a porous polymer matrix, the polymer matrix including a plurality of pores and providing a Young's modulus of at least 10 GPa, and inserting the hydrogel material into cartilage or bone tissue of an animal, wherein the hydrogel material supports cell colonization in vitro for autologous cell seeding.

  2. PROJECT MANGEMENT PLAN EXAMPLES

    Broader source: Energy.gov (indexed) [DOE]

    accelerates the project schedule and significantly reduces the project total life cycle cost. Current Baseline (FY99 MYWP) Revised Project Baseline Project Scope: ...

  3. DNA repair of a single UV photoproduct in a designed nucleosome

    SciTech Connect (OSTI)

    Kosmoskil, Joseph V.; Ackerman, Eric J. ); Smerdon, Michael J.

    2001-08-28

    Eukaryotic DNA repair enzymes must interact with the architectural hierarchy of chromatin. The challenge of finding damaged DNA complexed with histone proteins in nucleosomes is complicated by the need to maintain local chromatin structures involved in regulating other DNA processing events. The heterogeneity of lesions induced by DNA-damaging agents has led us to design homogeneously damaged substrates to directly compare repair of naked DNA with that of nucleosomes. Here we report that nucleotide excision repair in Xenopus nuclear extracts can effectively repair a single UV radiation photoproduct located 5 bases from the dyad center of a positioned nucleosome, although the nucleosome is repaired at about half the rate at which the naked DNA fragment is. Extract repair within the nucleosome is > 50-fold more rapid than either enzymatic photoreversal or endonuclease cleavage of the lesion in vitro. Furthermore, nucleosome formation occurs (after repair) only on damaged naked DNA ( 165-bp fragments) during a 1-h incubation in these extracts, even in the presence of a large excess of undamaged DNA. This is an example of selective nucleosome assembly by Xenopus nuclear extracts on a short linear DNA fragment containing a DNA lesion.

  4. Cloudnet Project

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Hogan, Robin

    2008-01-15

    Cloudnet is a research project supported by the European Commission. This project aims to use data obtained quasi-continuously for the development and implementation of cloud remote sensing synergy algorithms. The use of active instruments (lidar and radar) results in detailed vertical profiles of important cloud parameters which cannot be derived from current satellite sensing techniques. A network of three already existing cloud remote sensing stations (CRS-stations) will be operated for a two year period, activities will be co-ordinated, data formats harmonised and analysis of the data performed to evaluate the representation of clouds in four major european weather forecast models.

  5. Cloudnet Project

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Hogan, Robin

    Cloudnet is a research project supported by the European Commission. This project aims to use data obtained quasi-continuously for the development and implementation of cloud remote sensing synergy algorithms. The use of active instruments (lidar and radar) results in detailed vertical profiles of important cloud parameters which cannot be derived from current satellite sensing techniques. A network of three already existing cloud remote sensing stations (CRS-stations) will be operated for a two year period, activities will be co-ordinated, data formats harmonised and analysis of the data performed to evaluate the representation of clouds in four major european weather forecast models.

  6. Project Overview

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration wouldMass mapSpeedingProgramExemptions |(Conference) | SciTechProjectITER Project

  7. Project Tour

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration wouldMass mapSpeedingProgramExemptions |(Conference)Project Tour Project Tour See NMSSUP from

  8. Spent Nuclear Fuel project, project management plan

    SciTech Connect (OSTI)

    Fuquay, B.J.

    1995-10-25

    The Hanford Spent Nuclear Fuel Project has been established to safely store spent nuclear fuel at the Hanford Site. This Project Management Plan sets forth the management basis for the Spent Nuclear Fuel Project. The plan applies to all fabrication and construction projects, operation of the Spent Nuclear Fuel Project facilities, and necessary engineering and management functions within the scope of the project

  9. Lemon Project Spring Symposium

    E-Print Network [OSTI]

    Fashing, Norman

    Lemon Project: A Journey of Reconciliation." The BOV defined Lemon "as a long- term research project

  10. Modeling and centralization of strategic inventory for repairable and long lead-time spare parts

    E-Print Network [OSTI]

    Duncan, Tyeliah Elaine

    2011-01-01

    This thesis develops an optimal inventory model for repairable and long leadtime spare parts for an Engine overhaul business. In addition, it presents a business case for centralization of inventory. Pratt & Whitney purchased ...

  11. Emerging Trends in Heart Valve Engineering: Part III. Novel Technologies for Mitral Valve Repair and Replacement

    E-Print Network [OSTI]

    2015-01-01

    and J. D. Puskas. Mitral-valve repair versus replacement forbioprosthetic heart valves. Ann. Thorac. Surg. 71:S417–mechanics of arti?cial heart valves. Clin. Exp. Pharmacol.

  12. The COP9 signalosome is vital for timely repair of DNA double-strand breaks

    E-Print Network [OSTI]

    Meir, Michal; Galanty, Yaron; Kashani, Lior; Blank, Michael; Khosravi, Rami; Fernández-Ávila, María Jesús; Cruz-García, Andrés; Star, Ayelet; Shochot, Lea; Thomas, Yann; Garrett, Lisa J.; Chamovitz, Daniel A.; Bodine, David M.; Kurz, Thimo; Huertas, Pablo; Ziv, Yael; Shiloh, Yosef

    2015-04-08

    is critical for proper DSB repair, and that loss of this phosphorylation site alone is sufficient to cause a DDR deficiency phenotype in the mouse. This novel branch of the DSB response thus significantly affects genome stability....

  13. Review of Maintenance and Repair Times for Components in Technological Facilities

    SciTech Connect (OSTI)

    L. C. Cadwallader

    2012-11-01

    This report is a compilation of some unique component repair time data and it also presents citations of more extensive reports where lists of repair times can be found. This collection of information should support analysts who seek to quantify maintainability and availability of high technology and nuclear energy production systems. While there are newer sources of repair time information, most, if not all, of the newer sources are proprietary and cannot be shared. This report offers data that, while older, is openly accessible and can serve as reasonable estimates of repair times, at least for initial studies. Some times were found for maintenance times in radiation environments, and some guidance for multiplicative factors to use to account for work in contamination areas.

  14. Tiny Terminators: New Micro-Robots Assemble, Repair Themselves and Are Surprisingly Strong

    Broader source: Energy.gov [DOE]

    Tiny robots that can assemble and repair themselves? Watch a video of Argonne National Laboratory's micro-robots that easily perform tasks that can challenge other robots, including moving objects that are larger than themselves.

  15. Bruce Podwal Seminar Series Implementing Emergency Foundation Repairs on I-495 in Delaware

    E-Print Network [OSTI]

    Sun, Yi

    to be misaligned. Delaware Department of Transportation (DelDOT) responded immediately by shutting down the bridgeBruce Podwal Seminar Series Implementing Emergency Foundation Repairs on I-495 in Delaware Tuesday

  16. Development/Plasticity/Repair Persistence of Experience-Induced Homeostatic Synaptic

    E-Print Network [OSTI]

    Lee, Hey-Kyoung

    Development/Plasticity/Repair Persistence of Experience-Induced Homeostatic Synaptic Plasticity. Theoretical analyses indicate that there are two synaptic plasticity mechanisms required: input. Experience-dependent homeostatic synaptic plasticity mechanisms have subsequently been demonstrated

  17. Use of CFRP Overlays to Repair Fatigue Damage in Steel Bridge Girders and Components

    E-Print Network [OSTI]

    Gangel, Regan Elisabeth

    2012-05-31

    Fatigue damage in steel girder bridges built prior to the mid-1980s is common due to distortion-induced fatigue. Different repair techniques have been developed and implemented to retrofit bridges of this era with existing ...

  18. REPAIR OF BRIDGE STEEL GIRDERS DAMAGED BY DISTORTION-INDUCED FATIGUE

    E-Print Network [OSTI]

    Alemdar, Fatih

    2011-12-31

    This study investigates the repair of steel bridge girders damaged by distortion-induced fatigue. The study is presented in three parts. The first part describes finite element modeling techniques used to evaluate the ...

  19. Plug repairs of marine glass fiber / vinyl ester laminates subjected to uniaxial tension

    E-Print Network [OSTI]

    Michelis, Alexandros

    2009-01-01

    Glass fiber/vinyl ester composite laminates are currently being used and proposed for the hulls, bulkheads, and superstructures of large ships. This thesis examines the effectiveness of the repair of such laminates using ...

  20. A Self-Repairing Peer-to-Peer System Resilient to Dynamic Adversarial Churn

    E-Print Network [OSTI]

    A Self-Repairing Peer-to-Peer System Resilient to Dynamic Adversarial Churn Fabian Kuhn, Stefan at any time. Such peers join and leave the P2P system at high rates ("churn"), a problem

  1. A Self-Repairing Peer-to-Peer System Resilient to Dynamic Adversarial Churn

    E-Print Network [OSTI]

    A Self-Repairing Peer-to-Peer System Resilient to Dynamic Adversarial Churn Fabian Kuhn, Stefan rates ("churn"), a problem that is not existent in orthodox distributed systems. In other words, a P2P

  2. Inorganic-Organic Shape Memory Polymers and Foams for Bone Defect Repairs 

    E-Print Network [OSTI]

    Zhang, Dawei

    2013-04-16

    The ultimate goal of this research was to develop a “self-fitting” shape memory polymer (SMP) scaffold for the repair of craniomaxillofacial (CMF) bone defects. CMF defects may be caused by trauma, tumor removal or congenital abnormalities...

  3. Community-Minded Interns at Savannah River Site Help Area Residents in Need with Home Repairs

    Broader source: Energy.gov [DOE]

    AIKEN, S.C. – More than two dozen college interns who worked at the Savannah River Site (SRS) this summer joined other volunteers and headed into area neighborhoods to help people in need with home repairs.

  4. RESTORING A DAMAGED 16-YEAR -OLD INSULATING POLYMER CONCRETE DIKE OVERLAY: REPAIR MATERIALS AND TECHNOLOGIES.

    SciTech Connect (OSTI)

    SUGAMA,T.

    2007-01-01

    The objective of this program was to design and formulate organic polymer-based material systems suitable for repairing and restoring the overlay panels of insulating lightweight polymer concrete (ILPC) from the concrete floor and slope wall of a dike at KeySpan liquefied natural gas (LNG) facility in Greenpoint, Brooklyn, NY, just over sixteen years ago. It also included undertaking a small-scale field demonstration to ensure that the commercial repairing technologies were applicable to the designed and formulated materials.

  5. Hydropower Projects

    SciTech Connect (OSTI)

    2015-04-02

    The Water Power Program helps industry harness this renewable, emissions-free resource to generate environmentally sustainable and cost-effective electricity. Through support for public, private, and nonprofit efforts, the Water Power Program promotes the development, demonstration, and deployment of advanced hydropower devices and pumped storage hydropower applications. These technologies help capture energy stored by diversionary structures, increase the efficiency of hydroelectric generation, and use excess grid energy to replenish storage reserves for use during periods of peak electricity demand. In addition, the Water Power Program works to assess the potential extractable energy from domestic water resources to assist industry and government in planning for our nation’s energy future. From FY 2008 to FY 2014, DOE’s Water Power Program announced awards totaling approximately $62.5 million to 33 projects focused on hydropower. Table 1 provides a brief description of these projects.

  6. PROJECT SUMMARY

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankADVANCED MANUFACTURINGEnergy Bills andOrder 422.1, CONDUCT P - . . -Pathways)PROJECT SUMMARY 1 TITLE

  7. Hallmark Project

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:FinancingPetroleum12,ExecutiveFinancing Programs |ReferencePowerHaier: OrderProject

  8. Development of bonded composite doublers for the repair of oil recovery equipment.

    SciTech Connect (OSTI)

    Roach, David W.; Rackow, Kirk A.

    2005-06-01

    An unavoidable by-product of a metallic structure's use is the appearance of crack and corrosion flaws. Economic barriers to the replacement of these structures have created an aging infrastructure and placed even greater demands on efficient and safe repair methods. In the past decade, an advanced composite repair technology has made great strides in commercial aviation use. Extensive testing and analysis, through joint programs between the Sandia Labs FAA Airworthiness Assurance Center and the aviation industry, have proven that composite materials can be used to repair damaged aluminum structure. Successful pilot programs have produced flight performance history to establish the durability of bonded composite patches as a permanent repair on commercial aircraft structures. With this foundation in place, this effort is adapting bonded composite repair technology to civil structures. The use of bonded composite doublers has the potential to correct the difficulties associated with current repair techniques and the ability to be applied where there are no rehabilitation options. It promises to be cost-effective with minimal disruption to the users of the structure. This report concludes a study into the application of composite patches on thick steel structures typically used in mining operations. Extreme fatigue, temperature, erosive, and corrosive environments induce an array of equipment damage. The current weld repair techniques for these structures provide a fatigue life that is inferior to that of the original plate. Subsequent cracking must be revisited on a regular basis. The use of composite doublers, which do not have brittle fracture problems such as those inherent in welds, can help extend the structure's fatigue life and reduce the equipment downtime. Two of the main issues for adapting aircraft composite repairs to civil applications are developing an installation technique for carbon steel and accommodating large repairs on extremely thick structures. This study developed and proved an optimum field installation process using specific mechanical and chemical surface preparation techniques coupled with unique, in-situ heating methods. In addition, a comprehensive performance assessment of composite doubler repairs was completed to establish the viability of this technology for large, steel structures. The factors influencing the durability of composite patches in severe field environments were evaluated along with related laminate design issues.

  9. Custom Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would like submit theCovalent Bonding in ActinideRailCurrent ResearchInnovationCustom-Projects

  10. Project Title

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankADVANCED MANUFACTURINGEnergy Bills andOrderNATIONALofDefineEnergy NationalDepartmentProjectNE I&C

  11. Project Gnome

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration wouldMass mapSpeedingProgramExemptions |(Conference) | SciTechProject Gnome Double Beta Decay

  12. Project Title

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration wouldMass mapSpeedingProgramExemptions |(Conference) | SciTechProjectITERFebruaryStorage

  13. About Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity of NaturalDukeWakefieldSulfateSciTechtail.Theory of raregovAboutRecovery Act Recovery ActARM OverviewAbout GEDOE Projects

  14. Line Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration would likeUniverseIMPACTThousand CubicResourcelogo and-E C H2015Tray and|Projects Pages default

  15. Relocation and repair of the National Geotechnical Centrifuge. Final report

    SciTech Connect (OSTI)

    Cheney, J.A.

    1994-10-01

    In January of 1984, the large geotechnical centrifuge located at NASA Ames Research Center, was in the first stages of operational checkout when the main thrust bearing of the large D.C. drive motor failed. After many months of investigation and proposals for repair of the facility, it became evident that it would be far more advantageous to the engineering community to remove those components of the centrifuge that were undamaged to the Davis campus and replace the drive system completely. The large centrifuge had cost over 2 million dollars to build, and it would have been irresponsible to simply scrap it. Recognizing this fact, funds were solicited and received from various sources, and Beam Engineering Inc. was contracted to design and construct the centrifuge at its new location. The University of California contributed a quarter of a million dollars and Tyndall Air Force Base, through Los Alamos National Laboratory, contributed $140,000. There were funds also contributed by LANL, LLNL, US Navy and NSF. The first stage in the phased development of the newly located centrifuge is nearing completion, which prompts the writing of this report. By the time that this report reaches the reader the first runs of the centrifuge will have been completed. The present report describes the present capability of the centrifuge and the plans for upgrading as time goes on. Several pilot studies were carried out. The experiments involved (1) the effects of nearby explosions on buried thin walled containers and (2) the advection and dispersion of toxic waste water through soils.

  16. PROJECT MANGEMENT PLAN EXAMPLES Project Organization Examples

    Energy Savers [EERE]

    is responsible for supporting the FDH and RL project offices with adequate day-to-day planning and review technical management, coordination, control, and reporting of project...

  17. DNA repair decline during mouse spermiogenesis results in the accumulation of heritable DNA damage

    SciTech Connect (OSTI)

    Marchetti, Francesco; Marchetti, Francesco; Wryobek, Andrew J

    2008-02-21

    The post-meiotic phase of mouse spermatogenesis (spermiogenesis) is very sensitive to the genomic effects of environmental mutagens because as male germ cells form mature sperm they progressively lose the ability to repair DNA damage. We hypothesized that repeated exposures to mutagens during this repair-deficient phase result in the accumulation of heritable genomic damage in mouse sperm that leads to chromosomal aberrations in zygotes after fertilization. We used a combination of single or fractionated exposures to diepoxybutane (DEB), a component of tobacco smoke, to investigate how differential DNA repair efficiencies during the three weeks of spermiogenesis affected the accumulation of DEB-induced heritable damage in early spermatids (21-15 days before fertilization, dbf), late spermatids (14-8 dbf) and sperm (7- 1 dbf). Analysis of chromosomalaberrations in zygotic metaphases using PAINT/DAPI showed that late spermatids and sperm are unable to repair DEB-induced DNA damage as demonstrated by significant increases (P<0.001) in the frequencies of zygotes with chromosomal aberrations. Comparisons between single and fractionated exposures suggested that the DNA repair-deficient window during late spermiogenesis may be less than two weeks in the mouse and that during this repair-deficient window there is accumulation of DNA damage in sperm. Finally, the dose-response study in sperm indicated a linear response for both single and repeated exposures. These findings show that the differential DNA repair capacity of post-meioitic male germ cells has a major impact on the risk of paternally transmitted heritable damage and suggest that chronic exposures that may occur in the weeks prior to fertilization because of occupational or lifestyle factors (i.e, smoking) can lead to an accumulation of genetic damage in sperm and result in heritable chromosomal aberrations of paternal origin.

  18. DNA Repair Decline During Mouse Spermiogenesis Results in the Accumulation of Heritable DNA Damage

    SciTech Connect (OSTI)

    Marchetti, Francesco; Marchetti, Francesco; Wyrobek, Andrew J.

    2007-12-01

    The post-meiotic phase of mouse spermatogenesis (spermiogenesis) is very sensitive to the genomic effects of environmental mutagens because as male germ cells form mature sperm they progressively lose the ability to repair DNA damage. We hypothesized that repeated exposures to mutagens during this repair-deficient phase result in the accumulation of heritable genomic damage in mouse sperm that leads to chromosomal aberrations in zygotes after fertilization. We used a combination of single or fractionated exposures to diepoxybutane (DEB), a component of tobacco smoke, to investigate how differential DNA repair efficiencies during the three weeks of spermiogenesis affected the accumulation of DEB-induced heritable damage in early spermatids (21-15 days before fertilization, dbf), late spermatids (14-8 dbf) and sperm (7-1 dbf). Analysis of chromosomal aberrations in zygotic metaphases using PAINT/DAPI showed that late spermatids and sperm are unable to repair DEB-induced DNA damage as demonstrated by significant increases (P<0.001) in the frequencies of zygotes with chromosomal aberrations. Comparisons between single and fractionated exposures suggested that the DNA repair-deficient window during late spermiogenesis may be less than two weeks in the mouse and that during this repair-deficient window there is accumulation of DNA damage in sperm. Finally, the dose-response study in sperm indicated a linear response for both single and repeated exposures. These findings show that the differential DNA repair capacity of post-meioitic male germ cells has a major impact on the risk of paternally transmitted heritable damage and suggest that chronic exposures that may occur in the weeks prior to fertilization because of occupational or lifestyle factors (i.e, smoking) can lead to an accumulation of genetic damage in sperm and result in heritable chromosomal aberrations of paternal origin.

  19. Categorical Exclusion Determinations: Office of River Protection...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    2014 CX-012329: Categorical Exclusion Determination PNNL Projects Involving Small-Scale Research and Development, Laboratory Operations, and Pilot Projects in the 300 Area CX(s)...

  20. PROJECT MANAGEMENT Professional Organizations

    E-Print Network [OSTI]

    Acton, Scott

    PROJECT MANAGEMENT Professional Organizations: Association of Collegiate Computing Services) Project Management Institute (PMI) Events & Training: UVA Local Support Partners (LSP) program training Project Management Institute webinars Project Management Institute events Scrum Alliance events Learning

  1. Project Management Lessons Learned

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-08-05

    The guide supports DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, and aids the federal project directors and integrated project teams in the execution of projects.

  2. PROJECT MANAGEMENT Professional Organizations

    E-Print Network [OSTI]

    Acton, Scott

    PROJECT MANAGEMENT Professional Organizations: Project Management Institute International Association of Project and Program Management (IAPPM) Events & Training: UVa Center for Leadership Excellence classes SkillSoft classes PMO Symposium through PMI Project Management Institute (PMI) webinars American

  3. Perspectives on Project Finance

    Broader source: Energy.gov [DOE]

    Plenary III: Project Finance and Investment Perspectives on Project Finance John May, Managing Partner, Stern Brothers & Co.

  4. Community Renewables Projects

    Broader source: Energy.gov [DOE]

    This webinar covered introduction and barriers to individual renewable projects, resources for community and group buy projects, and permitting guidelines.

  5. HANFORD SITE LOW EXPOSURE PIPELINE REPAIR USING A NON-METALLIC COMPOSITE SYSTEM

    SciTech Connect (OSTI)

    HUTH RJ

    2009-11-12

    At the Department of Energy, Richland Operations (DOE-RL) Hanford site in eastern Washington, a 350 mm (14 inch) diameter high density polyethylene (HDPE) pump recirculation pipeline failed at a bonded joint adjacent to a radiologically and chemically contaminated groundwater storage basin. The responsible DOE-RL contractor, CH2MHill Plateau Remediation Company, applied a fiberglass reinforced plastic (composite) field repair system to the failed joint. The system was devised specifically for the HDPE pipe repair at the Hanford site, and had not been used on this type of plastic piping previously. This paper introduces the pipe failure scenario, describes the options considered for repair and discusses the ultimate resolution of the problem. The failed pipeline was successfully returned to service with minimal impact on waste water treatment plant operating capacity. Additionally, radiological and chemical exposures to facility personnel were maintained as low as reasonably achievable (ALARA). The repair is considered a success for the near term, and future monitoring will prove whether the repair can be considered for long term service and as a viable alternative for similar piping failures at the Hanford site.

  6. Computer Vision Project Topics Project Reports

    E-Print Network [OSTI]

    Zhu, Zhigang

    (contour projection?). step5: choose a tolerance value(3 or 5 pixels) to evaluate the image with eachComputer Vision Project Topics CSc I6716 Spring2011 #12;Project Reports 1. Introduction (problem up with Nikolaos Markou? · Key Components ­ The project is to find a target image from bunch

  7. Project Final Report UBC LBS Project Services1 Project Final Report UBC LBS Project Services2

    E-Print Network [OSTI]

    is used as a foundation for all development, land use, and transportation activities at UBC. LBS Project Services is a fee-for-service provider of development, design, and project management servicesProject Final Report UBC LBS Project Services1 #12;Project Final Report UBC LBS Project Services2

  8. Automatic coke oven heating control system at Burns Harbor for normal and repair operation

    SciTech Connect (OSTI)

    Battle, E.T.; Chen, K.L. [Bethlehem Steel Corp., Burns Harbor, IN (United States); [Bethlehem Steel Corp., PA (United States)

    1997-12-31

    An automatic heating control system for coke oven batteries was developed in 1985 for the Burns Harbor No. 1 battery and reported in the 1989 Ironmaking Conference Proceedings. The original system was designed to maintain a target coke temperature at a given production level under normal operating conditions. Since 1989, enhancements have been made to this control system so that it can also control the battery heating when the battery is under repair. The new control system has improved heating control capability because it adjusts the heat input to the battery in response to anticipated changes in the production schedule. During a recent repair of this 82 oven battery, the pushing schedule changed from 102 ovens/day to 88 ovens/day, then back to 102 ovens/day, then to 107 ovens/day. During this repair, the control system was able to maintain the coke temperature average standard deviation at 44 F, with a maximum 75 F.

  9. A survey of repair practices for nuclear power plant containment metallic pressure boundaries

    SciTech Connect (OSTI)

    Oland, C.B.; Naus, D.J.

    1998-05-01

    The Nuclear Regulatory Commission has initiated a program at the Oak Ridge National Laboratory to provide assistance in their assessment of the effects of potential degradation on the structural integrity and leaktightness of metal containment vessels and steel liners of concrete containments in nuclear power plants. One of the program objectives is to identify repair practices for restoring metallic containment pressure boundary components that have been damaged or degraded in service. This report presents issues associated with inservice condition assessments and continued service evaluations and identifies the rules and requirements for the repair and replacement of nonconforming containment pressure boundary components by welding or metal removal. Discussion topics include base and welding materials, welding procedure and performance qualifications, inspection techniques, testing methods, acceptance criteria, and documentation requirements necessary for making acceptable repairs and replacements so that the plant can be returned to a safe operating condition.

  10. Evaluation of bisphenol E cyanate ester for the resin-injection repair of advanced composites

    SciTech Connect (OSTI)

    Wilber Yaote Lio

    2009-12-19

    This thesis is a compilation of a general introduction and literature review that ties together the subsequent chapters which consist of two journal articles that have yet to be submitted for publication. The overall topic relates to the evaluation and application of a new class of cyanate ester resin with unique properties that lend it applicable to use as a resin for injection repair of high glass transition temperature polymer matrix composites. The first article (Chapter 2) details the evaluation and optimization of adhesive properties of this cyanate ester and alumina nanocomposites under different conditions. The second article (Chapter 3) describes the development and evaluation of an injection repair system for repairing delaminations in polymer matrix composites.

  11. Expert Meeting Report: Key Innovations for Adding Energy Efficiency to Maintenance Projects

    SciTech Connect (OSTI)

    Wood, A.; Wiehagen, J.

    2012-09-01

    This report describes an expert meeting hosted by the Building America research team NAHB Research Center, which was held on February 8, 2012, in Orlando, Florida. The topic, Key Innovations for Adding Energy Efficiency to Maintenance Projects, was intended to provide direction to more focused efforts to increase the efficiency of existing homes; in this meeting, the focus was specifically for re-roofing and the opportunities for adding energy efficiency upgrades during this major home repair activity.

  12. Bosh repairs No. 3 blast furnace, Edgar Thomson Plant Mon Valley Works

    SciTech Connect (OSTI)

    Stoupis, M.G.

    1993-01-01

    The paper describes in detail the steps taken from quenching to dry out of the furnace to repair the bosh area of the No.3 blast furnace. Inspection of the area revealed that there was no brick anywhere in the bosh. Brick in the tuyere breast area had been peeled back to reveal the steel plate, and descaling revealed 14 pipes fully exposed. None were leaking, but one seemed badly deteriorated. Conventional repairs could not take place before the scheduled blow-in. Installation of coolers were instead tried.

  13. Mitral Web -A New Concept for Mitral Valve Repair: Improved Engineering Design and In-Vitro Studies

    E-Print Network [OSTI]

    Pekkan, Kerem

    Mitral Web - A New Concept for Mitral Valve Repair: Improved Engineering Design and In of Biomedical Engineering, Georgia Institute of Technology, GA, USA Myxomatous mitral valve disease is currently reported that mitral valve repair is preferable to valve replace- ment, as it offers certain advantages

  14. Restoration and repair of 30-year old cooling towers at the Paducah Gaseous Diffusion Plant, Phase I. Draft 1

    SciTech Connect (OSTI)

    Shelton, M.F.

    1985-01-01

    Early in 1980, a comprehensive reliability study was made to ascertain the ability of the present 30-year old recirculating water system to meet the anticipated load demand through the year 2000. The findings and recommendations of this study were used as a guide to schedule uprating and repairs. This paper deals with the underground distribution system and cooling tower repairs.

  15. Hot repair of ceramic burner on hot blast stoves at USS/Kobe`s {number_sign}3 blast furnace

    SciTech Connect (OSTI)

    Bernarding, T.F.; Chemorov, M.; Shimono, S.; Phillips, G.R.

    1997-12-31

    During the 1992 reline of the No. 3 blast furnace, three new stoves were constructed. The design of the stoves, equipped with internal ceramic burners, was for providing a hot blast temperature of 2,000 F at a wind rate of 140,000 SCFM. After 3 years the performance had deteriorated so the burners were cleaned. When a second cleaning did not improve the performance of No. 3 blast furnace, it was decided to repair the refractory while still hot. The paper describes the hot repair procedures, taking a stove off for repairs, maintenance heat up during repairs, two stove operation, stove commissioning, repair of a ceramic burner, and wet gas prevention.

  16. Protein Bridges DNA Base and Nucleotide Excision Repair Pathways

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration wouldMass mapSpeedingProgramExemptions |(Conference)ProjectProposedAmerica'sTrapProtein Bridges

  17. Protein Bridges DNA Base and Nucleotide Excision Repair Pathways

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration wouldMass mapSpeedingProgramExemptions |(Conference)ProjectProposedAmerica'sTrapProtein

  18. Protein Bridges DNA Base and Nucleotide Excision Repair Pathways

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration wouldMass mapSpeedingProgramExemptions |(Conference)ProjectProposedAmerica'sTrapProteinProtein

  19. Protein Bridges DNA Base and Nucleotide Excision Repair Pathways

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home RoomPreservation of Fe(II) by Carbon-Rich MatricesstudentsProjectsPropertymaterials | ArgonneProtein

  20. Projective ML Didier Remy

    E-Print Network [OSTI]

    RĂ©my, Didier

    Projective ML Didier Remy INRIA-Rocquencourt Apr 10, 1992 Abstract We propose a projective lambda calculus as the ba- sis for operations on records. Projections operate on elevations, that is, records projective ML from this calculus by adding the ML Let typing rule to the simply typed projective calculus. We

  1. DNA repair efficiency in germ cells and early mouse embryos and consequences for radiation-induced transgenerational genomic damage

    SciTech Connect (OSTI)

    Marchetti, Francesco; Wyrobek, Andrew J.

    2009-01-18

    Exposure to ionizing radiation and other environmental agents can affect the genomic integrity of germ cells and induce adverse health effects in the progeny. Efficient DNA repair during gametogenesis and the early embryonic cycles after fertilization is critical for preventing transmission of DNA damage to the progeny and relies on maternal factors stored in the egg before fertilization. The ability of the maternal repair machinery to repair DNA damage in both parental genomes in the fertilizing egg is especially crucial for the fertilizing male genome that has not experienced a DNA repair-competent cellular environment for several weeks prior to fertilization. During the DNA repair-deficient period of spermatogenesis, DNA lesions may accumulate in sperm and be carried into the egg where, if not properly repaired, could result in the formation of heritable chromosomal aberrations or mutations and associated birth defects. Studies with female mice deficient in specific DNA repair genes have shown that: (i) cell cycle checkpoints are activated in the fertilized egg by DNA damage carried by the sperm; and (ii) the maternal genotype plays a major role in determining the efficiency of repairing genomic lesions in the fertilizing sperm and directly affect the risk for abnormal reproductive outcomes. There is also growing evidence that implicates DNA damage carried by the fertilizing gamete as a mediator of postfertilization processes that contribute to genomic instability in subsequent generations. Transgenerational genomic instability most likely involves epigenetic mechanisms or error-prone DNA repair processes in the early embryo. Maternal and embryonic DNA repair processes during the early phases of mammalian embryonic development can have far reaching consequences for the genomic integrity and health of subsequent generations.

  2. CX-010136: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Repair Sanitary Sewer Line South of 725-N CX(s) Applied: B1.3 Date: 03/11/2013 Location(s): South Carolina Offices(s): Savannah River Operations Office

  3. CX-000873: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Clean, Inspect, and Repair BMT-27CX(s) Applied: B1.3Date: 02/11/2010Location(s): TexasOffice(s): Fossil Energy, Strategic Petroleum Reserve Field Office

  4. CX-006661: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Repair Flowline at 83-AX-4CX(s) Applied: B5.2, B5.4Date: 02/24/2010Location(s): Casper, WyomingOffice(s): RMOTC

  5. CX-007506: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Record of Categorical Exclusion for Bryan Mound Building BE-2 Drainage Improvements and Foundation Repair CX(s) Applied: B1.3 Date: 11/16/2011 Location(s): Texas Offices(s): Strategic Petroleum Reserve Field Office

  6. CX-011839: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    MiniBooNE Berme Repair CX(s) Applied: B2.5 Date: 01/15/2014 Location(s): Illinois Offices(s): Fermi Site Office

  7. CX-012744: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Prescott Peacock Transmission Line- Insulator Repair at 3 Structures CX(s) Applied: B1.3Date: 41851 Location(s): ArizonaOffices(s): Western Area Power Administration-Desert Southwest Region

  8. CX-010860: Categorical Exclusion Determination | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Determination Repair Roof at 192-2K CX(s) Applied: B1.3 Date: 07112013 Location(s): South Carolina Offices(s): Savannah River Operations Office C.E. Bourne, a subcontractor,...

  9. CX-012168: Categorical Exclusion Determination | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Repair of Roof Leaks at 218-1H CX(s) Applied: B1.3 Date: 04232014 Location(s): South Carolina Offices(s): Savannah River Operations Office C. E. Bourne, a roofing...

  10. CX-007956: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    High Resolution 3-Dimensional Laser Imaging for Inspection, Maintenance, Repair, and Operations CX(s) Applied: B3.6 Date: 01/30/2012 Location(s): California Offices(s): National Energy Technology Laboratory

  11. CX-007461: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    High Resolution 3-dimensional Laser Imaging for Inspection, Maintenance, Repair and Operations - Phase II CX(s) Applied: B3.6 Date: 12/20/2011 Location(s): Colorado Offices(s): National Energy Technology Laboratory

  12. CX-012342: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Liberty Parker #2 Transmission Line - Erosion Repair at Structure 53/1 CX(s) Applied: B4.6 Date: 06/09/2014 Location(s): Arizona Offices(s): Western Area Power Administration-Desert Southwest Region

  13. CX-004400: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Repair Brick Support Plates on Connecting Bridges - Building 58CX(s) Applied: B2.3Date: 11/05/2010Location(s): Allegheny City, PennsylvaniaOffice(s): Fossil Energy, National Energy Technology Laboratory

  14. CX-009603: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    716-N Yard Sinkhole Repair CX(s) Applied: B1.3 Date: 12/07/2012 Location(s): South Carolina Offices(s): Savannah River Operations Office

  15. CX-010934: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Active, Tailorable Adhesives for Dissimilar Material Bonding, Repair and Reassembly CX(s) Applied: B3.6 Date: 09/18/2013 Location(s): Michigan Offices(s): National Energy Technology Laboratory

  16. CX-010935: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Active, Tailorable Adhesives for Dissimilar Material Bonding, Repair and Reassembly CX(s) Applied: B3.6 Date: 09/18/2013 Location(s): Michigan Offices(s): National Energy Technology Laboratory

  17. CX-012337: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Maintain/Repair SPR Radio Communications Network, 2014-2017 CX(s) Applied: B1.7 Date: 06/11/2014 Location(s): CX: none Offices(s): Strategic Petroleum Reserve Field Office

  18. CX-011139: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    105-L Transfer Bay Drainage Repair CX(s) Applied: B1.3 Date: 08/27/2013 Location(s): South Carolina Offices(s): Savannah River Operations Office

  19. CX-012564: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    782-2A A-Area Domestic Water Storage Tank Coating Repairs CX(s) Applied: B1.3Date: 41870 Location(s): South CarolinaOffices(s): Savannah River Operations Office

  20. CX-012582: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    782-A A-Area Service and Fire Water Storage Tank Coating Repairs CX(s) Applied: B1.3Date: 41841 Location(s): South CarolinaOffices(s): Savannah River Operations Office

  1. CX-012743: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Mead Substation Service Building Repairs CX(s) Applied: B1.3Date: 41879 Location(s): NevadaOffices(s): Western Area Power Administration-Desert Southwest Region

  2. CX-012595: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Subcontractor Repair of Roof Leaks at 704-H CX(s) Applied: B1.3Date: 41827 Location(s): South CarolinaOffices(s): Savannah River Operations Office

  3. Project Reports for Haida Corporation- 2010 Project

    Office of Energy Efficiency and Renewable Energy (EERE)

    The Reynolds Creek Hydroelectric Project ("Reynolds Creek" or the "Project") is a 5 MW hydroelectric resource to be constructed on Prince of Wales Island, Alaska, approximately 10 miles east of Hydaburg.

  4. Dependability Modelling of Repairable Systems using Bayesian Networks Martin Neil *, David Marquez**

    E-Print Network [OSTI]

    Neil, Martin

    : We present a Hybrid Bayesian Network (HBN) framework to model the availability of renewable systems repair (renewal) distributions might be modelled using HBNs. Keywords: Bayesian Networks; Bayesian systems represented by a series of models each designed to model distinct stages in the renewal process

  5. Fast Interactive Simulations of Mitral Valve Repair Neil A. Tenenholtz, Peter E. Hammer, Robert D. Howe

    E-Print Network [OSTI]

    Fast Interactive Simulations of Mitral Valve Repair Neil A. Tenenholtz, Peter E. Hammer, Robert D. Howe Keywords: Surgical simulation, human-computer interaction, haptics, mitral valve, cardiac surgery. I. Problem Solved A healthy mitral valve ensures the one-way flow of oxygenated blood from the left

  6. Development/Plasticity/Repair The Bone Morphogenetic Protein Roof Plate Chemorepellent

    E-Print Network [OSTI]

    Butler, Samantha

    Development/Plasticity/Repair The Bone Morphogenetic Protein Roof Plate Chemorepellent Regulates, Toronto, Ontario, Canada M5G 1X8 Commissural spinal axons extend away from the roof plate (RP) in response to the dorsal midline and are generated by the bone morphogenetic proteins (BMPs) in the roof plate (RP) (Liem

  7. Model Repair --Aligning Process Models to Reality Dirk Fahland, Wil M.P. van der Aalst

    E-Print Network [OSTI]

    van der Aalst, Wil

    discovery and (2) conformance checking. Process discovery techniques automatically construct a process model an existing process model does not conform to reality one could -- in principle -- use process discoveryModel Repair -- Aligning Process Models to Reality Dirk Fahland, Wil M.P. van der Aalst Eindhoven

  8. FFaacciilliittiieess MMaannaaggeemmeenntt//EEnnvviirroonnmmeennttaall HHeeaalltthh && SSaaffeettyy Hazardous Work Area/Equipment Repair Form

    E-Print Network [OSTI]

    Mojzsis, Stephen J.

    Hazardous Work Area/Equipment Repair Form Form Instructions: Client is responsible for completing this form to assure that equipment and/or immediate work areas are not contaminated with any hazardous materials, tissue, etc.) Do Safety Hazards exist in the work area? N ___ Y ___ (Electrical, burn, or trip hazards

  9. Development/Plasticity/Repair Dendritic Spine Dynamics Regulate the Long-Term Stability

    E-Print Network [OSTI]

    van Rossum, Mark

    Development/Plasticity/Repair Dendritic Spine Dynamics Regulate the Long-Term Stability of Synaptic Plasticity Cian O'Donnell,1,2 Matthew F. Nolan,3 and Mark C. W. van Rossum1 1Institute for Adaptive of Edinburgh, Edinburgh EH8 9XD, United Kingdom Long-term synaptic plasticity requires postsynaptic influx

  10. Development/Plasticity/Repair Dendritic BDNF Synthesis Is Required for Late-Phase Spine

    E-Print Network [OSTI]

    Stryker, Michael

    Development/Plasticity/Repair Dendritic BDNF Synthesis Is Required for Late-Phase Spine Maturation paradigm for experience-dependent cortical development is called ocular dominance (OD) plasticity, where closing one eye for a few days during a critical period of heightened plasticity leads to marked decrease

  11. Development/Plasticity/Repair Wiring Stability of the Adult Drosophila Olfactory Circuit

    E-Print Network [OSTI]

    Luo, Liqun

    Development/Plasticity/Repair Wiring Stability of the Adult Drosophila Olfactory Circuit after Institute of Molecular Pathology, 1030 Vienna, Austria Neuronal wiring plasticity in response to experience. Here, we assess wiring plasticity in a discrete neural map represented by the adult Drosophila

  12. Development/Plasticity/Repair Dark Exposure Extends the Integration Window for

    E-Print Network [OSTI]

    Lee, Hey-Kyoung

    Development/Plasticity/Repair Dark Exposure Extends the Integration Window for Spike-Timing-Dependent Plasticity Yatu Guo,1,2 Shiyong Huang,1 Roberto de Pasquale,1 Kevin McGehrin,4 Hey-Kyoung Lee,1,3,4 Kanxing-timing-dependent plasticity, in which the polarity of plasticity is determined not by the stimulationfrequency

  13. Development/Plasticity/Repair Simultaneous NMDA-Dependent Long-Term Potentiation of

    E-Print Network [OSTI]

    Segal, Menahem

    Development/Plasticity/Repair Simultaneous NMDA-Dependent Long-Term Potentiation of EPSCs and Long activity-dependent long-term plasticity of neuronal networks is the interplay between excitatory, whereas a nitric oxide synthase inhibitor was ineffec- tive. Finally, network-induced plasticity

  14. Development/Plasticity/Repair STAT1 Regulates the Homeostatic Component of Visual

    E-Print Network [OSTI]

    Sur, Mriganka

    Development/Plasticity/Repair STAT1 Regulates the Homeostatic Component of Visual Cortical Plasticity via an AMPA Receptor-Mediated Mechanism Ikue Nagakura, Audra Van Wart, Jeremy Petravicz, Daniela signaling in neuronal function; however, its role in experience-dependent plasticity is unknown. Here we

  15. Toward a State of Good Repair for Railroad Bridges through Structural Health Monitoring

    E-Print Network [OSTI]

    Bustamante, Fabián E.

    Toward a State of Good Repair for Railroad Bridges through Structural Health Monitoring NUTC of this research is to add a new tool to the asset management toolbox: structural health monitoring, particularly is Structural Health Monitoring (SHM)? SHM is process of intelligently collecting data from sensors on critical

  16. Multilayer sulfur-resistant composite metal membranes and methods of making and repairing the same

    DOE Patents [OSTI]

    Way, J. Douglas; Hatlevik, Oyvind

    2014-07-15

    The invention relates to thin, hydrogen-permeable, sulfur-resistant membranes formed from multi-layers of palladium or palladium-alloy coatings on porous, ceramic or metal supports, methods of making these membranes, methods of repairing layers of these membranes and devices that incorporate these membranes.

  17. Development/Plasticity/Repair The ERK2 Mitogen-Activated Protein Kinase Regulates the

    E-Print Network [OSTI]

    Development/Plasticity/Repair The ERK2 Mitogen-Activated Protein Kinase Regulates the Timing Oligodendrocytedevelopmentistightlycontrolledbyavarietyofextracellulargrowthanddifferentiationfactors.Themitogen-activated protein kinases (MAPKs), ERK1 and ERK2, are critical intracellular signaling (ERKs) are ubiquitously expressed, coordinately regulated, and highly similar, but Erk2 deletion in mice

  18. Development/Plasticity/Repair Phosphatidylinositol 3-Kinase Activates ERK in Primary

    E-Print Network [OSTI]

    Clapham, David E.

    Development/Plasticity/Repair Phosphatidylinositol 3-Kinase Activates ERK in Primary Sensory activation to inflammatory pain. We further investigated the correlationbetweenthePI3KandtheERK294002 and wortmannin, indicative of the activation of PI3K by both agents. ERK activation by capsaicin

  19. Is the Cure Worse Than the Disease? Overfitting in Automated Program Repair

    E-Print Network [OSTI]

    Brun, Yuriy

    Is the Cure Worse Than the Disease? Overfitting in Automated Program Repair Edward K. Smith Earl T techniques validate patch correctness with respect to user-provided or inferred contracts [24 undertested functionality. Permission to make digital or hard copies of all or part of this work for personal

  20. Is the Cure Worse Than the Disease? Overfitting in Automated Program Repair

    E-Print Network [OSTI]

    Fernandez, Thomas

    Is the Cure Worse Than the Disease? Overfitting in Automated Program Repair Edward K. Smith Earl T-provided or inferred contracts [26,46,60], a larger proportion use test cases. Permission to make digital or hard copies of all or part of this work for personal or classroom use is granted without fee provided

  1. Metal inhibition of human alkylpurine-DNA-N-glycosylase activity in base excision repair

    E-Print Network [OSTI]

    Wang, Ping; Guliaev, Anton B.; Hang, Bo

    2006-01-01

    0.38 nM ) Zn 2+ Cd 2 + Metal ion (µM) Product % Relativeof hAPE1 Zn 2 + Cd 2 + Metal ion (µM) Figure 6 Figure 7Interactions by carcinogenic metal compounds with DNA repair

  2. Development/Plasticity/Repair NG2 Glia Generate New Oligodendrocytes But Few

    E-Print Network [OSTI]

    Richardson, William D.

    Development/Plasticity/Repair NG2 Glia Generate New Oligodendrocytes But Few Astrocytes in a Murine-derived growth factor receptor subunit (PDGFRA) and the NG2 proteoglycan. These "NG2 cells" descend from and white matter of the postnatal brain. It has been proposed that NG2 cells can also

  3. The Stumbling Block in Lung Repair of Emphysema: Elastic Fiber Assembly

    E-Print Network [OSTI]

    Mecham, Robert

    The Stumbling Block in Lung Repair of Emphysema: Elastic Fiber Assembly Adrian Shifren and Robert P properties of the lung are largely determined by the connective tissue networks laid down during development. The macromolecules most important for lung mechanics and structural integrity are collagen, elastin

  4. A New Rhenanite ( -NaCaPO4) and Hydroxyapatite Biphasic Biomaterial for Skeletal Repair

    E-Print Network [OSTI]

    Tas, A. Cuneyt

    A New Rhenanite ( -NaCaPO4) and Hydroxyapatite Biphasic Biomaterial for Skeletal Repair Sahil Abstract: Biphasic -rhenanite ( -NaCaPO4)­hydroxyapatite (Ca10(PO4)6(OH)2) biomaterials were prepared% rhenanite) biomaterials, while retaining their submicron particle sizes and high surface areas. -rhenanite

  5. Accepting Failure: Availability through Repair-centric System Design Aaron Brown

    E-Print Network [OSTI]

    California at Berkeley, University of

    1 Accepting Failure: Availability through Repair-centric System Design Aaron Brown Qualifying Exam Proposal 3 April 2001 Abstract Motivated by the lack of rapid improvement in the availability of Internet server systems, we introduce a new philosophy for designing highly-available systems that better reflects

  6. Development/Plasticity/Repair A Specific Requirement of Arc/Arg3.1 for Visual

    E-Print Network [OSTI]

    Lee, Hey-Kyoung

    Development/Plasticity/Repair A Specific Requirement of Arc/Arg3.1 for Visual Experience-Induced Homeostatic Synaptic Plasticity in Mouse Primary Visual Cortex Ming Gao,1 Kenneth Sossa,1 Lihua Song,1 Lauren.OurresultsdemonstratethatArc/Arg3.1playsaselectiveroleinregulatingvisualexperience-dependent homeostatic plasticity of excitatory

  7. Development/Plasticity/Repair Hair Cell Replacement in Adult Mouse Utricles after

    E-Print Network [OSTI]

    Rubel, Edwin

    Development/Plasticity/Repair Hair Cell Replacement in Adult Mouse Utricles after Targeted Ablation of Hair Cells with Diphtheria Toxin Justin S. Golub,1 Ling Tong,1 Tot B. Ngyuen,1 Cliff R. Hume,1 Richard utricle by inserting the human diphtheria toxin receptor (DTR) gene into the Pou4f3 gene, which encodes

  8. Project Selection - Record Keeping 

    E-Print Network [OSTI]

    Howard, Jeff W.

    2005-05-10

    4-H members have many project areas to choose from, depending on where they live. Members should consult with their parents and 4-H leaders when choosing a project. This publication outlines project considerations.

  9. Brazos Island Harbor, Texas Channel Improvement Project 25 June 2014

    E-Print Network [OSTI]

    US Army Corps of Engineers

    (BSC). In addition to offshore oil rig repair and shipbreaking, Brownsville is a bulk commodity port

  10. Clean Coal Projects (Virginia)

    Broader source: Energy.gov [DOE]

    This legislation directs the Virginia Air Pollution Control Board to facilitate the construction and implementation of clean coal projects by expediting the permitting process for such projects.

  11. 2016 Technology Innovation Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Projects FY 2016 Technology Innovation Project Briefs Demand Response TIP 292: Advanced Heat Pump Water Heater Research TIP 336: Scaled Deployment and Demonstration of Demand...

  12. Contract/Project Management

    Office of Environmental Management (EM)

    Contract and Project Management Performance Metrics and Targets 1 ContractProject Management Primary Performance Metrics FY 2011 Target FY 2011 Actual & Forecast FY 2011...

  13. Contract/Project Management

    Office of Environmental Management (EM)

    and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Primary Performance Metrics FY 2011 Target FY 2011 Forecast FY 2011 Pre- &...

  14. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Contract and Project Management Performance Metrics and Targets 1 ContractProject Management Primary Performance Metrics FY 2010 Target FY 2010 Actual FY 2010 Pre- &...

  15. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    Contract and Project Management Performance Metrics and Targets 1 ContractProject Management Primary Performance Metrics FY 2010 Target FY 2010 Forecast FY 2010 Pre- &...

  16. Contract/Project Management

    Energy Savers [EERE]

    and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Performance Metric FY 2012 Target FY 2012 Forecast FY 2012 Pre- & Post-CAP...

  17. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Performance Metric FY 2012 Target FY 2012 Final FY 2012 Pre- & Post-CAP Final...

  18. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    2 nd Quarter Overall Contract and Project Management Performance Metrics and Targets ContractProject Management Performance Metrics FY 2009 Target FY 2009 Actual Comment 1....

  19. Contract/Project Management

    Office of Environmental Management (EM)

    1 st Quarter Overall Contract and Project Management Performance Metrics and Targets ContractProject Management Performance Metrics FY 2009 Target FY 2009 Actual Comment 1....

  20. Contract/Project Management

    Office of Environmental Management (EM)

    3 rd Quarter Overall Contract and Project Management Performance Metrics and Targets ContractProject Management Performance Metrics FY 2009 Target FY 2009 Actual Comment 1....

  1. Contract/Project Management

    Energy Savers [EERE]

    Third Quarter Overall Contract and Project Management Improvement Performance Metrics and Targets 1 ContractProject Management Performance Metric FY 2012 Target FY 2012 Forecast...

  2. Project 1640 Palomar Procedures

    E-Print Network [OSTI]

    Project 1640 Palomar Procedures Version 0.1 7/7/08 2:11:08 PM #12;2 Project 1640 Design..................................................................................................................... 1 Palomar Procedures

  3. Project Finance and Investments

    Broader source: Energy.gov [DOE]

    Plenary III: Project Finance and Investment Project Finance and Investments Chris Cassidy, National Business Renewable Energy Advisor, U.S. Department of Agriculture

  4. Falls Creek Hydroelectric Project

    SciTech Connect (OSTI)

    Gustavus Electric Company; Richard Levitt; DOE Project Officer - Keith Bennett

    2007-06-12

    This project was for planning and construction of a 700kW hydropower project on the Fall River near Gustavus, Alaska.

  5. CX-008588: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    St. Petersburg Solar Pilot Project CX(s) Applied: B5.1 Date: 07/19/2012 Location(s): Florida Offices(s): Golden Field Office

  6. CX-008684: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Metaline Radio Station Upgrade Project CX(s) Applied: B1.19 Date: 07/11/2012 Location(s): Washington Offices(s): Bonneville Power Administration

  7. CX-010618: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Midwest Region Alternative Fuels Project CX(s) Applied: 0 Date: 07/19/2013 Location(s): Missouri Offices(s): National Energy Technology Laboratory

  8. CX-008438: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Biogas Reconditioning Project CX(s) Applied: B5.1 Date: 06/27/2012 Location(s): Nevada Offices(s): National Energy Technology Laboratory

  9. CX-008282: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Biogas Reconditioning Project CX(s) Applied: B5.1 Date: 05/01/2012 Location(s): Nevada Offices(s): National Energy Technology Laboratory

  10. Categorical Exclusion Determinations: Western Area PowerAdministratio...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Center October 26, 2009 CX-005544: Categorical Exclusion Determination Power Rate Formula for the Provo River Project of the Western Area Power Administration CX(s) Applied:...

  11. CX-008799: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Jack Case Showers Projects CX(s) Applied: B1.3 Date: 06/04/2012 Location(s): Tennessee Offices(s): Y-12 Site Office

  12. CX-009923: Categorical Exclusion Determination | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    CX-009923: Categorical Exclusion Determination CX-009923: Categorical Exclusion Determination Project Icebreaker CX(s) Applied: A9, B3.1 Date: 01072013 Location(s): Ohio...

  13. CX-012097: Categorical Exclusion Determination

    Office of Energy Efficiency and Renewable Energy (EERE)

    Microgrid Demonstration Project CX(s) Applied: B5.15 Date: 03/24/2014 Location(s): Idaho Offices(s): Idaho Operations Office

  14. CX-012122: Categorical Exclusion Determination

    Office of Energy Efficiency and Renewable Energy (EERE)

    OCGen Module Mooring Project CX(s) Applied: B5.25 Date: 04/29/2014 Location(s): Maine Offices(s): Golden Field Office

  15. CX-010109: Categorical Exclusion Determination | Department of...

    Office of Environmental Management (EM)

    09: Categorical Exclusion Determination CX-010109: Categorical Exclusion Determination Curecanti-Poncha 230 Kilovolt Transmission Line Cross Bar Ranch Project CX(s) Applied: B1.3...

  16. CX-008683: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Shaniko Radio Station Replacement Project CX(s) Applied: B1.19 Date: 07/11/2012 Location(s): Oregon Offices(s): Bonneville Power Administration

  17. CX-010155: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Augspurger Radio Tower Replacement Project CX(s) Applied: B1.19 Date: 04/03/2013 Location(s): Washington Offices(s): Bonneville Power Administration

  18. CX-011630: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    9831 Wall Construction Project CX(s) Applied: B1.3 Date: 06/05/2013 Location(s): Tennessee Offices(s): Y-12 Site Office

  19. CX-012482: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Mid-Atlantic Regional Infrastructure Development Project CX(s) Applied: B5.22Date: 41862 Location(s): MarylandOffices(s): National Energy Technology Laboratory

  20. CX-008803: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Milling Machine Replacement Projects CX(s) Applied: B1.31 Date: 05/14/2012 Location(s): Tennessee Offices(s): Y-12 Site Office

  1. CX-012632: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    LURR 20140456 - Salmon Creek Avenue Pathway Project CX(s) Applied: B4.9Date: 41885 Location(s): WashingtonOffices(s): Bonneville Power Administration

  2. Categorical Exclusion Determinations: Western Area PowerAdministratio...

    Energy Savers [EERE]

    Mountain Region August 14, 2014 CX-012767: Categorical Exclusion Determination Medicine Bow Substation Control Building Installation Project Carbon County, Wyoming CX(s)...

  3. CX-012474: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Refractories/Ceramics Project CX(s) Applied: B3.6Date: 41870 Location(s): OregonOffices(s): National Energy Technology Laboratory

  4. CX-011626: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Line Yard Fence Project CX(s) Applied: B1.11 Date: 06/05/2013 Location(s): Tennessee Offices(s): Y-12 Site Office

  5. A novel role for the transcriptional modulator NusA in DNA repair/damage tolerance pathways in Escherichia coli

    E-Print Network [OSTI]

    Cohen, Susan E., Ph. D. Massachusetts Institute of Technology

    2009-01-01

    All organisms must contend with the consequences of DNA damage, induced by a variety of both endogenous and exogenous sources. Mechanisms of DNA repair and DNA damage tolerance are crucial for cellular survival after DNA ...

  6. Using Differential Adhesion to Control Self-Assembly and Self-Repair of Collections of Modular Mobile Robots 

    E-Print Network [OSTI]

    Ottery, Peter

    This thesis presents a novel distributed control method which allows a collection of independently mobile robotic units, with two or three dimensional movement, to self-assemble into self-repairing hierarchical structures. ...

  7. Subterranean barriers, methods, and apparatuses for forming, inspecting, selectively heating, and repairing same

    DOE Patents [OSTI]

    Nickelson, Reva A. (Shelley, ID); Sloan, Paul A. (Rigby, ID); Richardson, John G. (Idaho Falls, ID); Walsh, Stephanie (Idaho Falls, ID); Kostelnik, Kevin M. (Idaho, ID)

    2009-04-07

    A subterranean barrier and method for forming same are disclosed, the barrier including a plurality of casing strings wherein at least one casing string of the plurality of casing strings may be affixed to at least another adjacent casing string of the plurality of casing strings through at least one weld, at least one adhesive joint, or both. A method and system for nondestructively inspecting a subterranean barrier is disclosed. For instance, a radiographic signal may be emitted from within a casing string toward an adjacent casing string and the radiographic signal may be detected from within the adjacent casing string. A method of repairing a barrier including removing at least a portion of a casing string and welding a repair element within the casing string is disclosed. A method of selectively heating at least one casing string forming at least a portion of a subterranean barrier is disclosed.

  8. Weld Repair of a Stamped Pressure Vessel in a Radiologically Controlled Zone

    SciTech Connect (OSTI)

    Cannell, Gary L.; Huth, Ralph J.; Hallum, Randall T.

    2013-08-26

    In September 2012 an ASME B&PVC Section VIII stamped pressure vessel located at the DOE Hanford Site Effluent Treatment Facility (ETF) developed a through-wall leak. The vessel, a steam/brine heat exchanger, operated in a radiologically controlled zone (by the CH2MHill PRC or CHPRC), had been in service for approximately 17 years. The heat exchanger is part of a single train evaporator process and its failure caused the entire system to be shut down, significantly impacting facility operations. This paper describes the activities associated with failure characterization, technical decision making/planning for repair by welding, logistical challenges associated with performing work in a radiologically controlled zone, performing the repair, and administrative considerations related to ASME code requirements.

  9. Chondrocyte outgrowth into a gelatin scaffold in a single impact load model of damage/repair - effect of BMP-2

    E-Print Network [OSTI]

    Henson, Frances M D; Vincent, Thea A

    2007-12-05

    damage repair response in mature equine articular cartilage explants following single impact load and subsequent culture [3]. This response is characterised Published: 5 December 2007 BMC Musculoskeletal Disorders 2007, 8:120 doi:10... ) degenerative joint disease, specifically osteoarthritis (OA) [2]. by the appearance of chondrocyte repair cells on damaged cartilage. This apparent mobilisation of chondrocytes has BMC Musculoskeletal Disorders 2007, 8:120 http://www.biomedcentral.com/1471...

  10. Precracked RC T-beams Repaired in Shear with Externally Bonded CFRP Sheets

    E-Print Network [OSTI]

    Dirar, Samir; Lees, Janet M.; Morley, Chris T.

    2012-03-01

    and repair of existing structures, advanced numerical analyses, glass fiber reinforced polymer pipelines and sustainable concrete. Chris Morley is a former Senior Lecturer in Concrete Structures at Cambridge University, UK. He has always been interested... , particularly in the case of bridges. Further factors that can have detrimental effects on capacity include corrosion of internal steel reinforcement, changes in use, poor initial design and more stringent assessment codes. One viable solution is to use fiber...

  11. Inhibition of Hsp27 Radiosensitizes Head-and-Neck Cancer by Modulating Deoxyribonucleic Acid Repair

    SciTech Connect (OSTI)

    Guttmann, David M.; Hart, Lori; Du, Kevin; Seletsky, Andrew; Koumenis, Constantinos

    2013-09-01

    Purpose: To present a novel method of tumor radiosensitization through Hsp27 knockdown using locked nucleic acid (LNA) and to investigate the role of Hsp27 in DNA double strand break (DSB) repair. Methods and Materials: Clonogenic survival assays, immunoblotting, the proximity ligation assay, and ?H2AX foci analysis were conducted in SQ20B and FaDu human head-and-neck cancer cell lines treated with Hsp27 LNA and Hsp27 short hairpin RNA (shRNA). Additionally, nude mice with FaDu flank tumors were treated with fractionated radiation therapy after pretreatment with Hsp27 LNA and monitored for tumor growth. Results: Hsp27 LNA and Hsp27 shRNA radiosensitized head-and-neck cancer cell lines in an Hsp27-dependent manner. Ataxia-Telangectasia Mutated-mediated DNA repair signaling was impaired in irradiated cells with Hsp27 knockdown. ATM kinase inhibition abrogated the radiosensitizing effect of Hsp27. Furthermore, Hsp27 LNA and shRNA both attenuated DNA repair kinetics after radiation, and Hsp27 was found to colocalize with ATM in both untreated and irradiated cells. Last, combined radiation and Hsp27 LNA treatment in tumor xenografts in nude mice suppressed tumor growth compared with either treatment alone. Conclusions: These results support a radiosensitizing property of Hsp27 LNA in vitro and in vivo, implicate Hsp27 in double strand break repair, and suggest that Hsp27 LNA might eventually serve as an effective clinical agent in the radiotherapy of head-and-neck cancer.

  12. Cell-autonomous progeroid changes in conditional mouse models for repair endonuclease XPG deficiency

    SciTech Connect (OSTI)

    Barnhoorn, Sander [Erasmus University Medical Center, Rotterdam (The Netherlands). Dept. of Genetics.; Uittenboogaard, Lieneke M. [Erasmus University Medical Center, Rotterdam (The Netherlands). Dept. of Genetics.; Jaarsma, Dick [Erasmus Univ. Medical Center, Rotterdam (The Netherlands). Dept. of Neuroscience.; Vermeij, Wilbert P. [Erasmus University Medical Center, Rotterdam (The Netherlands). Dept. of Genetics.; Tresini, Maria [Erasmus University Medical Center, Rotterdam (The Netherlands). Dept. of Genetics.; Weymaere, Michael [Erasmus University Medical Center, Rotterdam (The Netherlands). Dept. of Genetics.; Menoni, Hervé [Erasmus University Medical Center, Rotterdam (The Netherlands). Dept. of Genetics.; Brandt, Renata M. C. [Erasmus University Medical Center, Rotterdam (The Netherlands). Dept. of Genetics.; de Waard, Monique C. [VU Univ. Medical Center, Amsterdam (The Netherlands). Dept. of Intensive Care.; Botter, Sander M. [Uniklinik Balgrist, Zurich (Switzerland); Sarker, Altaf H. [Lawrence Berkeley National Lab. (LBNL), Berkeley, CA (United States). Life Sciences Division.; Jaspers, Nicolaas G. J. [Erasmus University Medical Center, Rotterdam (The Netherlands). Dept. of Genetics; van der Horst, Gijsbertus T. J. [Erasmus University Medical Center, Rotterdam (The Netherlands). Dept. of Genetics.; Cooper, Priscilla K. [Lawrence Berkeley National Lab. (LBNL), Berkeley, CA (United States). Life Sciences Division.; Hoeijmakers, Jan H. J. [Erasmus University Medical Center, Rotterdam (The Netherlands). Dept. of Genetics.; van der Pluijm, Ingrid [Erasmus University Medical Center, Rotterdam (The Netherlands). Dept. of Genetics and Dept. of Vascular Surgery.; Niedernhofer, Laura J. [The Scripps Research Institute, San Diego, CA (United States)

    2014-10-09

    As part of the Nucleotide Excision Repair (NER) process, the endonuclease XPG is involved in repair of helix-distorting DNA lesions, but the protein has also been implicated in several other DNA repair systems, complicating genotype-phenotype relationship in XPG patients. Defects in XPG can cause either the cancer-prone condition xeroderma pigmentosum (XP) alone, or XP combined with the severe neurodevelopmental disorder Cockayne Syndrome (CS), or the infantile lethal cerebro-oculo-facio-skeletal (COFS) syndrome, characterized by dramatic growth failure, progressive neurodevelopmental abnormalities and greatly reduced life expectancy. Here, we present a novel (conditional) Xpg-/- mouse model which—in a C57BL6/FVB F1 hybrid genetic background—displays many progeroid features, including cessation of growth, loss of subcutaneous fat, kyphosis, osteoporosis, retinal photoreceptor loss, liver aging, extensive neurodegeneration, and a short lifespan of 4–5 months. We show that deletion of XPG specifically in the liver reproduces the progeroid features in the liver, yet abolishes the effect on growth or lifespan. In addition, specific XPG deletion in neurons and glia of the forebrain creates a progressive neurodegenerative phenotype that shows many characteristics of human XPG deficiency. Our findings therefore exclude that both the liver as well as the neurological phenotype are a secondary consequence of derailment in other cell types, organs or tissues (e.g. vascular abnormalities) and support a cell-autonomous origin caused by the DNA repair defect itself. In addition they allow the dissection of the complex aging process in tissue- and cell-type-specific components. Moreover, our data highlight the critical importance of genetic background in mouse aging studies, establish the Xpg-/- mouse as a valid model for the severe form of human XPG patients and segmental accelerated aging, and strengthen the link between DNA damage and aging.

  13. Lethal Hemorrhage Caused by Aortoesophageal Fistula Secondary to Stent-Graft Repair of the Thoracic Aorta

    SciTech Connect (OSTI)

    Sager, Hendrik B., E-mail: hendrik.sager@uk-sh.de [Universitaet zu Luebeck, Medizinische Klinik II (Germany); Wellhoener, Peter [Universitaet zu Luebeck, Medizinische Klinik I (Germany); Wermelt, Johanna A. [Klinikum Neustadt, Klinik fuer Innere Medizin (Germany); Schunkert, Heribert; Kurowski, Volkhard [Universitaet zu Luebeck, Medizinische Klinik II (Germany)

    2011-02-15

    Aortoesophageal fistula (AEF) is a rare but life-threatening complication after endovascular or surgical aortic repair. Here we report a patient with AEF secondary to aortic stent-placement 2 years earlier who presented with hematemesis and died from hemorrhagic shock. By means of this case and the literature, we highlight potential bleeding sources in such a scenario because this is of crucial importance for the management strategy.

  14. Cell-autonomous progeroid changes in conditional mouse models for repair endonuclease XPG deficiency

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Barnhoorn, Sander; Uittenboogaard, Lieneke M.; Jaarsma, Dick; Vermeij, Wilbert P.; Tresini, Maria; Weymaere, Michael; Menoni, Hervé; Brandt, Renata M. C.; de Waard, Monique C.; Botter, Sander M.; et al

    2014-10-09

    As part of the Nucleotide Excision Repair (NER) process, the endonuclease XPG is involved in repair of helix-distorting DNA lesions, but the protein has also been implicated in several other DNA repair systems, complicating genotype-phenotype relationship in XPG patients. Defects in XPG can cause either the cancer-prone condition xeroderma pigmentosum (XP) alone, or XP combined with the severe neurodevelopmental disorder Cockayne Syndrome (CS), or the infantile lethal cerebro-oculo-facio-skeletal (COFS) syndrome, characterized by dramatic growth failure, progressive neurodevelopmental abnormalities and greatly reduced life expectancy. Here, we present a novel (conditional) Xpg-/- mouse model which—in a C57BL6/FVB F1 hybrid genetic background—displays manymore »progeroid features, including cessation of growth, loss of subcutaneous fat, kyphosis, osteoporosis, retinal photoreceptor loss, liver aging, extensive neurodegeneration, and a short lifespan of 4–5 months. We show that deletion of XPG specifically in the liver reproduces the progeroid features in the liver, yet abolishes the effect on growth or lifespan. In addition, specific XPG deletion in neurons and glia of the forebrain creates a progressive neurodegenerative phenotype that shows many characteristics of human XPG deficiency. Our findings therefore exclude that both the liver as well as the neurological phenotype are a secondary consequence of derailment in other cell types, organs or tissues (e.g. vascular abnormalities) and support a cell-autonomous origin caused by the DNA repair defect itself. In addition they allow the dissection of the complex aging process in tissue- and cell-type-specific components. Moreover, our data highlight the critical importance of genetic background in mouse aging studies, establish the Xpg-/- mouse as a valid model for the severe form of human XPG patients and segmental accelerated aging, and strengthen the link between DNA damage and aging.« less

  15. Quality Improvement Guidelines for Imaging Detection and Treatment of Endoleaks following Endovascular Aneurysm Repair (EVAR)

    SciTech Connect (OSTI)

    Rand, T.; Uberoi, R.; Cil, B.; Munneke, G.; Tsetis, D.

    2013-02-15

    Major concerns after aortic aneurysm repair are caused by the presence of endoleaks, which are defined as persistent perigraft flow within the aortic aneurysm sac. Diagnosis of endoleaks can be performed with various imaging modalities, and indications for treatment are based on further subclassifications. Early detection and correct classification of endoleaks are crucial for planning patient management. The vast majority of endoleaks can be treated successfully by interventional means. Guidelines for Imaging Detection and Treatment of endoleaks are described in this article.

  16. Livingston Campus Geothermal Project The Project

    E-Print Network [OSTI]

    Delgado, Mauricio

    Livingston Campus Geothermal Project The Project: Geothermal power is a cost effective, reliable is a Closed Loop Geothermal System involving the removal and storage of approximately four feet of dirt from the entire Geothermal Field and the boring of 321 vertical holes reaching a depth of 500 feet. These holes

  17. A deficiency in chromatin repair, genetic instability, and predisposition to cancer

    SciTech Connect (OSTI)

    Sanford, K.K.; Parshad, R.; Gantt, R.R.; Tarone, R.E. (National Cancer Institute, Bethesda, MD (USA))

    1989-01-01

    This review traces steps leading to malignant neoplastic transformation of rodent and human cells in culture and in vivo. Emphasis is placed on an abnormal response characterized by persistent chromatid damage following irradiation of cells in culture with X-rays or fluorescent light during G2 phase of the cell cycle. Evidence is presented that deficient or unbalanced DNA repair during G2 accounts for the abnormal response. This G2 repair deficiency can be inherited or acquired by normal tissue cells during the process of or following attainment of infinite lifespan. It appears as an early, possibly initiating step in neoplastic transformation. It characterizes all human tumor cells examined irrespective of histopathology or tissue of origin. It has a genetic basis. In an animal model, the BALB/c mouse, this phenotype is associated with genes on chromosomes 1 and 4. It characterizes skin fibroblasts and blood lymphocytes from individuals with genetic or familial conditions predisposing to cancer and can be used to identify clinically normal family members carrying a gene(s) for any one of the three cancer-prone genetic disorders studied to date. Furthermore, it can provide the basis of a test for carriers of genes predisposing to a high risk of cancer. We conclude that the G2 repair deficiency, whether inherited or acquired, is a prerequisite for cancer development and that it accounts for the genetic instability of the cancer cell. 167 refs.

  18. Judge Evaluation Scoring Form for Project Technical Report PROJECT .#.: ..Project Title......

    E-Print Network [OSTI]

    Dahlberg, Teresa A.

    Judge Evaluation Scoring Form for Project Technical Report PROJECT .#.: ..Project Title of the project?) Excellent Very Good Good Fair Unsatisfactory COMMENTS: #12;Judge Evaluation Scoring Form for REU) #12;Judge Evaluation Scoring Form for Poster Presentation PROJECT.#.: ...Title.. PARTICIPANTS: DATE

  19. Sample Project Execution Plan

    Broader source: Energy.gov [DOE]

    The project execution plan (PEP) is the governing document that establishes the means to execute, monitor, and control projects.  The plan serves as the main communication vehicle to ensure that...

  20. Haida Corporation- 2010 Project

    Office of Energy Efficiency and Renewable Energy (EERE)

    The Reynolds Creek Hydroelectric Project ("Reynolds Creek" or the "Project") is a 5 MW hydroelectric resource to be constructed on Prince of Wales Island, Alaska, approximately 10 miles east of Hydaburg.

  1. Iskuulpa Watershed ProjectIskuulpa Watershed Project BPA Project # 199506001BPA Project # 199506001

    E-Print Network [OSTI]

    Basin Fish and Wildlife Mitigation ProjectMitigation Project Established by the CTUIR in 1995Established by the CTUIR in 1995 Provides dual benefit to fish and wildlifeProvides dual benefit to fish and wildlife while

  2. Rooftop Unit Network Project

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Network Project RTU Network Project Michael Brambley, Ph.D. Pacific Northwest National Laboratory Michael.Brambley@pnnl.gov (509) 375-6875 April 4, 2013 2 | Building Technologies...

  3. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    100% Post-CAP This is based on a 3-year rolling average (FY10). TPC is Total Project Cost. 3. Certified EVM Systems: Post CD-3, 95% of line item projects and EM cleanup...

  4. Planning the Project Meeting 

    E-Print Network [OSTI]

    Howard, Jeff W.

    2005-05-10

    Project group meetings must be planned well in advance. Members should be involved in completing some type of work before the next meeting. This helps the leader plan the next project meeting and makes efficient use of time.

  5. The 4-H Project 

    E-Print Network [OSTI]

    Howard, Jeff W.

    2005-05-10

    As a 4-H volunteer, you will find that projects are useful tools for teaching a wide variety of skills to young people. This publication will help you plan and evaluate 4-H learning projects.

  6. Contract/Project Management

    Energy Savers [EERE]

    on a 3-year rolling average (FY09 to FY11). TPC is Total Project Cost. 2a. EM Cleanup (Soil and Groundwater Remediation, D&D, and Waste Treatment and Disposal) Projects: (Pre-...

  7. Rabbit Project Reference Manual 

    E-Print Network [OSTI]

    Wootton, Chad

    2000-05-04

    This publication explains how to raise rabbits for a 4-H rabbit project. It discusses project options; breeds; equipment; breeding and kindling; sanitation; diseases, parasites and illnesses; processing; marketing; and grooming and showing. Although...

  8. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    within 12 months of the original CD- 34 duration. 90% 91% FY10-FY12 Seventy completions to date. Schedule Compliance, Projects greater than 5 years Duration: Projects will...

  9. Infrastructure Projects | Jefferson Lab

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    conditions for many, as well as a change to the layout of the laboratory due to ancillary projects. The project has received approval to make early purchases in the...

  10. Information Technology Project Management

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2012-12-03

    The Order provides program and project management direction for the acquisition and management of IT projects, investments, and initiatives. Cancels DOE G 200.1-1. Admin Chg 1 approved 1-16-2013.

  11. GHPsRUS Project

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Battocletti, Liz

    The GHPsRUS Project's full name is "Measuring the Costs and Benefits of Nationwide Geothermal Heat Pump Deployment." The dataset contains employment and installation price data collected by four economic surveys: (1)GHPsRUS Project Manufacturer & OEM Survey, (2) GHPsRUS Project Geothermal Loop Survey, (3) GHPsRUS Project Mechanical Equipment Installation Survey, and (4) GHPsRUS Geothermal Heat Pump Industry Survey

  12. WIPP Projects Interative Map

    Broader source: Energy.gov [DOE]

    View WIPP Projects in a larger map. To report corrections, please email WeatherizationInnovation@ee.doe.gov.

  13. GHPsRUS Project

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Battocletti, Liz

    2013-07-09

    The GHPsRUS Project's full name is "Measuring the Costs and Benefits of Nationwide Geothermal Heat Pump Deployment." The dataset contains employment and installation price data collected by four economic surveys: (1)GHPsRUS Project Manufacturer & OEM Survey, (2) GHPsRUS Project Geothermal Loop Survey, (3) GHPsRUS Project Mechanical Equipment Installation Survey, and (4) GHPsRUS Geothermal Heat Pump Industry Survey

  14. LENS repair and modification of metal NW components:materials and applications guide.

    SciTech Connect (OSTI)

    Smugeresky, John E. (Sandia National Laboratories, Livermore, CA); Gill, David Dennis; Oberhaus, Jason (BWXT Y-12); Adams, Thad (Savannah River National Laboratory); VanCamp, Chad (Kansas City Plant)

    2006-11-01

    Laser Engineered Net Shaping{trademark} (LENS{reg_sign}) is a unique, layer additive, metal manufacturing technique that offers the ability to create fully dense metal features and components directly from a computer solid model. LENS offers opportunities to repair and modify components by adding features to existing geometry, refilling holes, repairing weld lips, and many other potential applications. The material deposited has good mechanical properties with strengths typically slightly higher that wrought material due to grain refinement from a quickly cooling weld pool. The result is a material with properties similar to cold worked material, but without the loss in ductility traditionally seen with such treatments. Furthermore, 304L LENS material exhibits good corrosion resistance and hydrogen compatibility. This report gives a background of the LENS process including materials analysis addressing the requirements of a number of different applications. Suggestions are given to aid both the product engineer and the process engineer in the successful utilization of LENS for their applications. The results of testing on interface strength, machinability, weldability, corrosion resistance, geometric effects, heat treatment, and repair strategy testing are all included. Finally, the qualification of the LENS process is briefly discussed to give the user confidence in selecting LENS as the process of choice for high rigor applications. The testing showed LENS components to have capability in repair/modification applications requiring complex castings (W80-3 D-Bottle bracket), thin wall parts requiring metal to be rebuilt onto the part (W87 Firing Set Housing and Y-12 Test Rings), the filling of counterbores for use in reservoir reclamation welding (SRNL hydrogen compatibility study) and the repair of surface defects on pressure vessels (SRNL gas bottle repair). The material is machinable, as testing has shown that LENS deposited material machines similar to that of welded metal. Tool wear is slightly higher in LENS material than in wrought material, but not so much that one would be concerned with increased tooling cost. The LENS process achieved process qualification for the AY1E0125 D-Bottle Bracket from the W80-3 LEP program, and in the effort, also underwent testing in weapons environments. These tests included structural dynamic response testing and drop testing. The LENS deposited parts were compared in these tests with conventionally machined parts and showed equivalency to such an extent that the parts were accepted for use in parallel path subsystem-level weapon environment testing. The evaluation of LENS has shown that the process can be a viable option when either complete metal parts are needed or existing metal parts require modification or repair. The LENS Qualification Technology Investment team successfully investigated new applications for the LENS process and showed that it has great applicability across the Nuclear Weapons Complex as well as in other high rigor applications.

  15. Ferdinand Project Middleware List

    E-Print Network [OSTI]

    ://java.dzone.com/articles/case-study-how-lastfm-uses] - hornetq-vm: VM for testing of clustered scenarios [http://sourceforge.net/projects/hornetq-vm/] EvaluationFerdinand Project Middleware List Jaroslav Keznikl2 , Michal Malohlava1 , Lukás Marek1 , Petr Tma1 phone +420-266053831 #12;FERDINAND PROJECT MIDDLEWARE LIST PURPOSE The purpose of this report

  16. TEAM PROJECT: WORKING PROTOTYPE

    E-Print Network [OSTI]

    .) Value: the report is worth 10% of the Team Project grade. #12;Next steps: You will evaluateTEAM PROJECT: WORKING PROTOTYPE Due: Week of April 5-8 at time to be scheduled with GTA Format that will be polished into the final project for which you will create a final report and give a final presentation

  17. Project Description 1 Introduction

    E-Print Network [OSTI]

    VanDeGrift, Tammy

    Project Description 1 Introduction This project will investigate "commonsense computing": what, and 3. Apply our findings to changes in classroom pedagogy in ways that can be rigorously evalu- ated. 1 0736572 #12;In the exploratory part of this project, which we are proposing here, we will concentrate

  18. Kansas Advanced Semiconductor Project

    SciTech Connect (OSTI)

    Baringer, P.; Bean, A.; Bolton, T.; Horton-Smith, G.; Maravin, Y.; Ratra, B.; Stanton, N.; von Toerne, E.; Wilson, G.

    2007-09-21

    KASP (Kansas Advanced Semiconductor Project) completed the new Layer 0 upgrade for D0, assumed key electronics projects for the US CMS project, finished important new physics measurements with the D0 experiment at Fermilab, made substantial contributions to detector studies for the proposed e+e- international linear collider (ILC), and advanced key initiatives in non-accelerator-based neutrino physics.

  19. PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans...

    Energy Savers [EERE]

    qualitativelysubjectively assess the project risk. The approach is modeled after project risk assessment processes outlined in standard project management texts and training...

  20. BEACON SOLAR ENERGY PROJECT (08-AFC-2) Project Title: Beacon Solar Energy Project (Beacon)

    E-Print Network [OSTI]

    BEACON SOLAR ENERGY PROJECT (08-AFC-2) FACT SHEET Project Title: Beacon Solar Energy Project and operate the Beacon Solar Energy Project (Beacon). Location: The project is located in eastern Kern County;BEACON SOLAR ENERGY PROJECT (08-AFC-2) FACT SHEET Licensing: The Beacon project would have a nominal

  1. Clean-coal technology by-products used in a highway embankment stabilization demonstration project. Master's thesis

    SciTech Connect (OSTI)

    Nodjomian, S.M.

    1994-01-01

    Clean-coal technology by-products are used in a highway embankment demonstration project. This research chronicles the procedures used in the process and analyzes the stability of a repaired highway embankment. The reconstructed slope is analyzed using an Intelligent Discussion Support System that was developed from a slope stability program. Water quality studies are performed and an instrumentation plan is suggested. The calculated factors of safety and the observed embankment performance give indications that the field demonstration project was a success. Long-term monitoring will be the best barometer for determining embankment gross movement and the future of FGD by-products as a stabilizing material.

  2. Proposal to negotiate the renewal of an existing blanket purchase contract for the repair, reconditioning or replacement of klystrons for CTF3 and associated accessories

    E-Print Network [OSTI]

    2012-01-01

    Proposal to negotiate the renewal of an existing blanket purchase contract for the repair, reconditioning or replacement of klystrons for CTF3 and associated accessories

  3. National Compact Stellarator Experiment Project Closeout Report PROJECT CLOSEOUT REPORT

    E-Print Network [OSTI]

    Princeton Plasma Physics Laboratory

    Approved by Jeffrey Makiel DOE Federal Project Director for the National Compact Stellarator Experiment II.....................................................................................1 3. PROJECT HISTORY

  4. PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans...

    Broader source: Energy.gov (indexed) [DOE]

    addressing the following key elements of project management and control: Project Management Control System (PMCS) - Work breakdown structure - Baseline developmentupdate...

  5. Development and validation of nondestructive inspection techniques for composite doubler repairs on commercial aircraft

    SciTech Connect (OSTI)

    Roach, D.; Walkington, P.

    1998-05-01

    Composite doublers, or repair patches, provide an innovative repair technique which can enhance the way aircraft are maintained. Instead of riveting multiple steel or aluminum plates to facilitate an aircraft repair, it is possible to bond a single boron-epoxy composite doubler to the damaged structure. In order for the use of composite doublers to achieve widespread use in the civil aviation industry, it is imperative that methods be developed which can quickly and reliably assess the integrity of the doubler. In this study, a specific composite application was chosen on an L-1011 aircraft in order to focus the tasks on application and operation issues. Primary among inspection requirements for these doublers is the identification of disbonds, between the composite laminate and aluminum parent material, and delaminations in the composite laminate. Surveillance of cracks or corrosion in the parent aluminum material beneath the doubler is also a concern. No single nondestructive inspection (NDI) method can inspect for every flaw type, therefore it is important to be aware of available NDI techniques and to properly address their capabilities and limitations. A series of NDI tests were conducted on laboratory test structures and on full-scale aircraft fuselage sections. Specific challenges, unique to bonded composite doubler applications, were highlighted. An array of conventional and advanced NDI techniques were evaluated. Flaw detection sensitivity studies were conducted on applicable eddy current, ultrasonic, X-ray and thermography based devices. The application of these NDI techniques to composite doublers and the results from test specimens, which were loaded to provide a changing flaw profile, are presented in this report. It was found that a team of these techniques can identify flaws in composite doubler installations well before they reach critical size.

  6. Suberoylanilide Hydroxyamic Acid Modification of Chromatin Architecture Affects DNA Break Formation and Repair

    SciTech Connect (OSTI)

    Singh, Sheetal; Le Hongan; Shih, S.-J.; Ho, Bay [Department of Radiation Oncology, University of California at Davis, 4501 X St., Sacramento, California 95817 (United States); Vaughan, Andrew T., E-mail: andrew.vaughan@ucdmc.ucdavis.ed [Department of Radiation Oncology, University of California at Davis, 4501 X St., Sacramento, California 95817 (United States); Department of Veterans Affairs, Mather, California 95655 (United States)

    2010-02-01

    Purpose: Chromatin-modifying compounds that inhibit the activity of histone deacetylases have shown potency as radiosensitizers, but the action of these drugs at a molecular level is not clear. Here we investigated the effect of suberoylanilide hydroxyamic acid (SAHA) on DNA breaks and their repair and induction of rearrangements. Methods and Materials: The effect of SAHA on both clonogenic survival and repair was assessed using cell lines SCC-25, MCF7, and TK6. In order to study unique DNA double-strand breaks, anti-CD95 antibody was employed to introduce a DNA double-strand break at a known location within the 11q23 region. The effects of SAHA on DNA cleavage and rearrangements were analyzed by ligation-mediated PCR and inverse PCR, respectively. Results: SAHA acts as radiosensitizer at 1 {mu}M, with dose enhancement factors (DEFs) at 10% survival of: SCC-25 - 1.24 +- 0.05; MCF7 - 1.16 +- 0.09 and TK6 - 1.17 +- 0.05, and it reduced the capacity of SCC-25 cells to repair radiation induced lesions. Additionally, SAHA treatment diffused site-specific fragmentation over at least 1 kbp in TK6 cells. Chromosomal rearrangements produced in TK6 cells exposed to SAHA showed a reduction in microhomology at the breakpoint between 11q23 and partner chromosomes. Conclusions: SAHA shows efficacy as a radiosensitizer at clinically obtainable levels. In its presence, targeted DNA strand breaks occur over an expanded region, indicating increased chromatin access. The rejoining of such breaks is degraded by SAHA when measured as rearrangements at the molecular level and rejoining that contributes to cell survival.

  7. Project Surveillance and Maintenance Plan. [UMTRA Project

    SciTech Connect (OSTI)

    Not Available

    1985-09-01

    The Project Surveillance and Maintenance Plan (PSMP) describes the procedures that will be used by the US Department of Energy (DOE), or other agency as designated by the President to verify that inactive uranium tailings disposal facilities remain in compliance with licensing requirements and US Environmental Protection Agency (EPA) standards for remedial actions. The PSMP will be used as a guide for the development of individual Site Surveillance and Maintenance Plans (part of a license application) for each of the UMTRA Project sites. The PSMP is not intended to provide minimum requirements but rather to provide guidance in the selection of surveillance measures. For example, the plan acknowledges that ground-water monitoring may or may not be required and provides the (guidance) to make this decision. The Site Surveillance and Maintenance Plans (SSMPs) will form the basis for the licensing of the long-term surveillance and maintenance of each UMTRA Project site by the NRC. Therefore, the PSMP is a key milestone in the licensing process of all UMTRA Project sites. The Project Licensing Plan (DOE, 1984a) describes the licensing process. 11 refs., 22 figs., 8 tabs.

  8. JAG Tearing Technique with Radiofrequency Guide Wire for Aortic Fenestration in Thoracic Endovascular Aneurysm Repair

    SciTech Connect (OSTI)

    Ricci, Carmelo [Azienda Ospedaliera Universitaria Senese, Policlinico Santa Maria alle Scotte, Radiologia Interventistica (Italy); Ceccherini, Claudio, E-mail: claudiocec@hotmail.it; Leonini, Sara [Radiologia Universitaria, Azienda Ospedaliera Universitaria Senese, Policlinico Santa Maria alle Scotte (Italy); Cini, Marco; Vigni, Francesco [Azienda Ospedaliera Universitaria Senese, Policlinico Santa Maria alle Scotte, Radiologia Interventistica (Italy); Neri, Eugenio; Tucci, Enrico; Benvenuti, Antonio; Tommasino, Giulio; Sassi, Carlo [Azienda Ospedaliera Universitaria Senese, Policlinico Santa Maria alle Scotte, Chirurgia dell'Aorta Toracica (Italy)

    2012-02-15

    An innovative approach, the JAG tearing technique, was performed during thoracic endovascular aneurysm repair in a patient with previous surgical replacement of the ascending aorta with a residual uncomplicated type B aortic dissection who developed an aneurysm of the descending thoracic aorta with its lumen divided in two parts by an intimal flap. The proximal landing zone was suitable to place a thoracic stent graft. The distal landing zone was created by cutting the intimal flap in the distal third of the descending thoracic aorta with a radiofrequency guide wire and intravascular ultrasound catheter.

  9. Exposure Evaluation for Benzene, Lead and Noise in Vehicle and Equipment Repair Shops

    SciTech Connect (OSTI)

    Sweeney, Lynn C.

    2013-04-10

    An exposure assessment was performed at the equipment and vehicle maintenance repair shops operating at the U. S. Department of Energy Hanford site, in Richland, Washington. The maintenance shops repair and maintain vehicles and equipment used in support of the Hanford cleanup mission. There are three general mechanic shops and one auto body repair shop. The mechanics work on heavy equipment used in construction, cranes, commercial motor vehicles, passenger-type vehicles in addition to air compressors, generators, and farm equipment. Services include part fabrication, installation of equipment, repair and maintenance work in the engine compartment, and tire and brake services. Work performed at the auto body shop includes painting and surface preparation which involves applying body filler and sanding. 8-hour time-weighted-average samples were collected for benzene and noise exposure and task-based samples were collected for lead dust work activities involving painted metal surfaces. Benzene samples were obtained using 3M™ 3520 sampling badges and were analyzed for additional volatile organic compounds. These compounds were selected based on material safety data sheet information for the aerosol products used by the mechanics for each day of sampling. The compounds included acetone, ethyl ether, toluene, xylene, VM&P naphtha, methyl ethyl ketone, and trichloroethylene. Laboratory data for benzene, VM&P naphtha, methyl ethyl ketone and trichloroethylene were all below the reporting detection limit. Airborne concentrations for acetone, ethyl ether, toluene and xylene were all less than 10% of their occupational exposure limit. The task-based samples obtained for lead dusts were submitted for a metal scan analysis to identify other metals that might be present. Laboratory results for lead dusts were all below the reporting detection limit and airborne concentration for the other metals observed in the samples were less than 10% of the occupational exposure limit. Noise dosimetry sampling was performed on a random basis and was representative of the different work activities within the four shops. Twenty three percent of the noise samples exceeded the occupational exposure limit of 85 decibels for an 8-hour time-weightedaverage. Work activities where noise levels were higher included use of impact wrenches and grinding wheels.

  10. The CHPRC Columbia River Protection Project Quality Assurance Project Plan

    SciTech Connect (OSTI)

    Fix, N. J.

    2008-11-30

    Pacific Northwest National Laboratory researchers are working on the CHPRC Columbia River Protection Project (hereafter referred to as the Columbia River Project). This is a follow-on project, funded by CH2M Hill Plateau Remediation Company, LLC (CHPRC), to the Fluor Hanford, Inc. Columbia River Protection Project. The work scope consists of a number of CHPRC funded, related projects that are managed under a master project (project number 55109). All contract releases associated with the Fluor Hanford Columbia River Project (Fluor Hanford, Inc. Contract 27647) and the CHPRC Columbia River Project (Contract 36402) will be collected under this master project. Each project within the master project is authorized by a CHPRC contract release that contains the project-specific statement of work. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by the Columbia River Project staff.

  11. Federal Methanol Fleet Project final report

    SciTech Connect (OSTI)

    West, B.H.; McGill, R.N.; Hillis, S.L.; Hodgson, J.W.

    1993-03-01

    The Federal Methanol Fleet Project concluded with the termination of data collection from the three fleet sites in February 1991. The Lawrence Berkeley Laboratory (LBL) completed five years of operation, Argonne National Laboratory (ANL) completed its fourth year in the project, and Oak Ridge National Laboratory (ORNL) completed its third. Twenty of the thirty-nine vehicles in the fleet were powered by fuel methanol (typically M85, 85 % methanol, 15 % unleaded gasoline, although the LBL fleet used M88), and the remaining control vehicles were comparable gasoline vehicles. Over 2.2 million km (1.4 million miles) were accumulated on the fleet vehicles in routine government service. Data collected over the years have included vehicle mileage and fuel economy, engine oil analysis, emissions, vehicle maintenance, and driver acceptance. Fuel economies (on an energy basis) of the methanol and gasoline vehicles of the same type were comparable throughout the fleet testing. Engine oil analysis has revealed higher accumulation rates of iron and other metals in the oil of the methanol vehicles, although no significant engine damage has been attributed to the higher metal content. Vehicles of both fuel types have experienced degradation in their emission control systems, however, the methanol vehicles seem to have degraded their catalytic converters at a higher rate. The methanol vehicles have required more maintenance than their gasoline counterparts, in most cases, although the higher levels of maintenance cannot be attributed to ``fuel-related`` repairs. According to the daily driver logs and results from several surveys, drivers of the fleet vehicles at all three sites were generally satisfied with the methanol vehicles.

  12. Federal Methanol Fleet Project final report

    SciTech Connect (OSTI)

    West, B.H.; McGill, R.N. ); Hillis, S.L.; Hodgson, J.W. )

    1993-03-01

    The Federal Methanol Fleet Project concluded with the termination of data collection from the three fleet sites in February 1991. The Lawrence Berkeley Laboratory (LBL) completed five years of operation, Argonne National Laboratory (ANL) completed its fourth year in the project, and Oak Ridge National Laboratory (ORNL) completed its third. Twenty of the thirty-nine vehicles in the fleet were powered by fuel methanol (typically M85, 85 % methanol, 15 % unleaded gasoline, although the LBL fleet used M88), and the remaining control vehicles were comparable gasoline vehicles. Over 2.2 million km (1.4 million miles) were accumulated on the fleet vehicles in routine government service. Data collected over the years have included vehicle mileage and fuel economy, engine oil analysis, emissions, vehicle maintenance, and driver acceptance. Fuel economies (on an energy basis) of the methanol and gasoline vehicles of the same type were comparable throughout the fleet testing. Engine oil analysis has revealed higher accumulation rates of iron and other metals in the oil of the methanol vehicles, although no significant engine damage has been attributed to the higher metal content. Vehicles of both fuel types have experienced degradation in their emission control systems, however, the methanol vehicles seem to have degraded their catalytic converters at a higher rate. The methanol vehicles have required more maintenance than their gasoline counterparts, in most cases, although the higher levels of maintenance cannot be attributed to fuel-related'' repairs. According to the daily driver logs and results from several surveys, drivers of the fleet vehicles at all three sites were generally satisfied with the methanol vehicles.

  13. Structuring small projects

    SciTech Connect (OSTI)

    Pistole, C.O.

    1995-11-01

    One of the most difficult hurdles facing small project developers is obtaining financing. Many major banks and institutional investors are unwilling to become involved in projects valued at less than $25 million. To gain the interest of small project investors, developers will want to present a well-considered plan and an attractive rate of return. Waste-to-energy projects are one type that can offer diversified revenue sources that assure maximum profitability. The Ripe Touch Greenhouse project, a $14.5 million waste tire-to-energy facility in Colorado, provides a case study of how combining the strengths of the project partners can help gain community and regulatory acceptance and maximize profit opportunities.

  14. Battleground Energy Recovery Project

    SciTech Connect (OSTI)

    Daniel Bullock

    2011-12-31

    In October 2009, the project partners began a 36-month effort to develop an innovative, commercial-scale demonstration project incorporating state-of-the-art waste heat recovery technology at Clean Harbors, Inc., a large hazardous waste incinerator site located in Deer Park, Texas. With financial support provided by the U.S. Department of Energy, the Battleground Energy Recovery Project was launched to advance waste heat recovery solutions into the hazardous waste incineration market, an area that has seen little adoption of heat recovery in the United States. The goal of the project was to accelerate the use of energy-efficient, waste heat recovery technology as an alternative means to produce steam for industrial processes. The project had three main engineering and business objectives: Prove Feasibility of Waste Heat Recovery Technology at a Hazardous Waste Incinerator Complex; Provide Low-cost Steam to a Major Polypropylene Plant Using Waste Heat; and ď?· Create a Showcase Waste Heat Recovery Demonstration Project.

  15. Operational Waste Volume Projection

    SciTech Connect (OSTI)

    STRODE, J.N.

    2000-08-28

    Waste receipts to the double-shell tank system are analyzed and wastes through the year 2015 are projected based on generation trends of the past 12 months. A computer simulation of site operations is performed, which results in projections of tank fill schedules, tank transfers, evaporator operations, tank retrieval, and aging waste tank usage. This projection incorporates current budget planning and the clean-up schedule of the Tri-Party Agreement. Assumptions were current as of June. 2000.

  16. Microwave solidification project overview

    SciTech Connect (OSTI)

    Sprenger, G.

    1993-01-01

    The Rocky Flats Plant Microwave Solidification Project has application potential to the Mixed Waste Treatment Project and the The Mixed Waste Integrated Program. The technical areas being addressed include (1) waste destruction and stabilization; (2) final waste form; and (3) front-end waste handling and feed preparation. This document covers need for such a program; technology description; significance; regulatory requirements; and accomplishments to date. A list of significant reports published under this project is included.

  17. Operational Waste Volume Projection

    SciTech Connect (OSTI)

    STRODE, J.N.

    1999-08-24

    Waste receipts to the double-shell tank system are analyzed and wastes through the year 2018 are projected based on assumption as of July 1999. A computer simulation of site operations is performed, which results in projections of tank fill schedules, tank transfers, evaporator operations, tank retrieval, and aging waste tank usage. This projection incorporates current budget planning and the clean-up schedule of the Tri-Party Agreement.

  18. Mascoma: Frontier Biorefinery Project

    Broader source: Energy.gov [DOE]

    This project involves the construction and operation of a biorefinery that produces ethanol and other co-products from cellulosic materials through advanced consolidated bioprocessing.

  19. Integrated Project Team RM

    Office of Environmental Management (EM)

    acquisition process and will be utilized during all phases of a project life cycle. The IPT is a team of professionals representing diverse disciplines with the specific...

  20. Mentors and Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    ideas. Borovsky, Joe Mentor Joe Borovsky General Interests Magnetospheric physics, solar-wind physics, solar-windmagnetosphere coupling Suggested Project Topics Theory and...

  1. Penobscot Tribe- 2012 Project

    Broader source: Energy.gov [DOE]

    With this award, the Penobscot Indian Nation will advance the preconstruction activities required to secure funding for the proposed 227-megawatt (MW) Alder Stream wind project.

  2. Bacteria TMDL Projects 

    E-Print Network [OSTI]

    Wythe, Kathy

    2007-01-01

    stream_source_info Bacteria TMDL projects.pdf.txt stream_content_type text/plain stream_size 2550 Content-Encoding ISO-8859-1 stream_name Bacteria TMDL projects.pdf.txt Content-Type text/plain; charset=ISO-8859-1 tx H2O... of the projects are listed below. ? Peach CreekWater Quality Improvement Project ? Monitoring and Educational Programs Focused on Bacteria and Nutrient Runoff on Dairy Operations in the LeonWatershed ? Development of the Plum CreekWPP ? Impact of Proper...

  3. Whistling Ridge Energy Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    build, own and operate the wind project and their associated facilities. The Final Environmental Impact Statement (FEIS) has been issued for the proposed Whistling Ridge...

  4. TThe {\\sc Majorana} Project

    E-Print Network [OSTI]

    The MAJORANA collaboration

    2009-10-23

    The {\\sc Majorana} Project, a neutrinoless double-beta decay experiment is described with an emphasis on the choice of Ge-detector configuration.

  5. The MAJORANA project

    SciTech Connect (OSTI)

    Elliott, Steven R [Los Alamos National Laboratory

    2009-01-01

    The Majorana Project, a neutrinoless double-beta decay experiment is described with an emphasis on the choice of Ge-detector configuration.

  6. Power Systems Past Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    loop and its six associated substations. An upgrade of the INL loop, designed by Power Systems personnel, was completed in 1997. This project consists of transmission line...

  7. Project Reports for Kootznoowoo Incorporated- 2010 Project

    Office of Energy Efficiency and Renewable Energy (EERE)

    Thayer Lake Hydropower Development (TLHD) consists of a 1 MW+ run of the river hydropower project located in the Tongass Forest in the Admiralty Island National Monument Park that will provide the energy to the City of Angoon and Angoon Community Association (traditional tribe as recognized by Indian Reorganization Act).

  8. Dofasco`s No. 4 blast furnace hearth breakout, repair and rescue

    SciTech Connect (OSTI)

    Donaldson, R.J.; Fischer, A.J.; Sharp, R.M.; Stothart, D.W. [Dofasco Inc., Hamilton, Ontario (Canada)

    1995-12-01

    On May 5, 1994, after producing 9.5 million metric tons of iron, Dofasco`s No. 4 Blast Furnace experienced a hearth breakout 250 millimeters below the west taphole. The hot metal spill caused a fire resulting in severe damage and 33 days of lost production. During a 26-day period, electrical wiring, water drainage systems and both tapholes were repaired. Recovery from an unprepared furnace stop of this length, with the deadman depleted is difficult. To aid with the rescue Hoogovens-designed oxygen/fuel lances were commissioned. The furnace recovery began with a lance in each taphole and all tuyeres plugged. Six days after startup the furnace was casting into torpedo cars, and after nine days operation had returned to normal. This incident prompted Dofasco to expand the hearth monitoring system to detect and prevent similar occurrences. During the repair, 203 new thermocouples were installed in the hearth, concentrating on the tapholes and elephant foot areas. These thermocouples were installed at various depths and locations to allow heat flux calculations. This hearth monitoring system has already identified other problem areas and provided valuable information about hearth drainage patterns. This information has allowed them to develop control strategies to manage localized problem areas.

  9. Repair processes and radiation quality in neoplastic transformation of mammalian cells

    SciTech Connect (OSTI)

    Han, A.; Hill, C.K.; Elkind, M.M.

    1984-08-01

    Appropriate in vitro mammalian cell systems facilitate the study of cellular mechanisms of radiation oncogenesis. C3H 10T1/2 cells derived from mouse embryo have been used to study the effects of protracted irradiation on cell killing and incidence of neoplastic transformation. Protracted exposures of /sup 60/Co ..gamma.. rays or fission-spectrum neutrons (from the JANUS reactor at the Argonne National Laboratory) were given either at low dose rates or as multifractionated regimens using high dose rates. Dose protraction of ..gamma.. rays by multifractionation at a high dose rate (50 rad/min) results in appreciable reduction in cell killing and also significantly reduces the incidence of neoplastic transformation. Irradiation at a low dose rate has the same qualitative effect. In contrast, protracted exposures of fission-spectrum neutrons, given at a low dose rate (0.086 or 0.43 rad/min), result in significant enhancement of the frequency of transformation in the dose region of up to 80 rad. However, the survival of cells is essentially the same as that for the same single dose of neutrons given at a high dose rate. These observations are consistent with net ''error-free'' repair of transformational damage following protracted exposure of a low LET radiation and possibly a net ''error-prone'' repair of transformational damage after protracted irradiations with fission-spectrum neutrons.

  10. Operational results of shaft repair by installing stave type cooler at Kimitsu Nos. 3 and 4 blast furnaces

    SciTech Connect (OSTI)

    Oda, Hiroshi; Amano, Shigeru; Sakamoto, Aiichiro; Anzai, Osamu [Nippon Steel Corp., Kimitsu, Chiba (Japan). Kimitsu Works; Nakagome, Michiru; Kuze, Toshisuke [Nippon Steel Corp., Futtsu, Chiba (Japan); Imuta, Akira [Nippon Steel Corp., Tokyo (Japan). Plant and Machinery Div.

    1997-12-31

    Nos. 3 and 4 blast furnaces in Nippon Steel Corporation Kimitsu Works were both initially fitted with cooling plate systems. With the aging of each furnace, the damage to their respective inner-shaft profiles had become serious. Thus, in order to prevent operational change and prolong the furnace life, the inner-shaft profile of each furnace was repaired by replacing the former cooling plate system with the stave type cooler during the two-week-shutdowns. With this repair, stability of burden descent and gas flow near the wall part of the furnace have been achieved. Thus the prolongation of the furnace life is naturally expected.

  11. Detection and Repair of Ionizing Radiation-Induced DNA Double Strand Breaks: New Developments in Nonhomologous End Joining

    SciTech Connect (OSTI)

    Wang, Chen [Departments of Biochemistry and Molecular Biology and Oncology, and Southern Alberta Cancer Research Institute, University of Calgary, Calgary (Canada)] [Departments of Biochemistry and Molecular Biology and Oncology, and Southern Alberta Cancer Research Institute, University of Calgary, Calgary (Canada); Lees-Miller, Susan P., E-mail: leesmill@ucalgary.ca [Departments of Biochemistry and Molecular Biology and Oncology, and Southern Alberta Cancer Research Institute, University of Calgary, Calgary (Canada)

    2013-07-01

    DNA damage can occur as a result of endogenous metabolic reactions and replication stress or from exogenous sources such as radiation therapy and chemotherapy. DNA double strand breaks are the most cytotoxic form of DNA damage, and defects in their repair can result in genome instability, a hallmark of cancer. The major pathway for the repair of ionizing radiation-induced DSBs in human cells is nonhomologous end joining. Here we review recent advances on the mechanism of nonhomologous end joining, as well as new findings on its component proteins and regulation.

  12. The human genome project

    SciTech Connect (OSTI)

    Yager, T.D.; Zewert, T.E.; Hood, L.E. )

    1994-04-01

    The Human Genome Project (HGP) is a coordinated worldwide effort to precisely map the human genome and the genomes of selected model organisms. The first explicit proposal for this project dates from 1985 although its foundations (both conceptual and technological) can be traced back many years in genetics, molecular biology, and biotechnology. The HGP has matured rapidly and is producing results of great significance.

  13. The Home Microbiome Project

    SciTech Connect (OSTI)

    Gilbert, Jack

    2014-08-25

    The Home Microbiome Project is an initiative aimed at uncovering the dynamic co-associations between people's bacteria and the bacteria found in their homes.The hope is that the data and project will show that routine monitoring of the microbial diversity of your body and of the environment in which you live is possible.

  14. LEP Dismantling Project

    E-Print Network [OSTI]

    Poole, John; CERN. Geneva. SPS and LHC Division

    2001-01-01

    The LEP Dismantling Project has been in its operational phase since late in the year 2000. This report briefly reviews the development of the project and the current status. The report has been prepared for presentation to the Radiation Protection Committee in May 2001 and consequently it has a bias towards Radiation Protection activities.

  15. Project organizations and schedules

    SciTech Connect (OSTI)

    Briggs, R.J.

    1990-07-01

    The Superconducting Super Collider Laboratory (SSCL) faces the challenge of simultaneously carrying out a large-scale construction project with demanding cost, schedule, and performance goals; and creating a scientific laboratory capable of exploiting this unique scientific instrument. This paper describes the status of the laboratory organization developed to achieve these goals, and the major near-term schedule objectives of the project.

  16. TEAM PROJECT: USER TESTING

    E-Print Network [OSTI]

    TEAM PROJECT: USER TESTING Due: Wed April 21 (section 2) Thu April 22 (section 1) Now that you have: usability inspection, Neilsen's heuristic evaluation, pluralistic walk through, or GOMS analysis (without part of your project. You might consider a joint session with another team! Format: 3-4 page report

  17. Coal. [Great Plains Project

    SciTech Connect (OSTI)

    Not Available

    1981-03-01

    The status of various research projects related to coal is considered: gasification (approximately 30 processes) and in-situ gasification. Methanol production, retrofitting internal combustion engines to stratified charge engines, methanation (Conoco), direct reduction of iron ores, water resources, etc. Approximately 200 specific projects related to coal are considered with respect to present status. (LTN)

  18. The Home Microbiome Project

    ScienceCinema (OSTI)

    Gilbert, Jack

    2014-09-15

    The Home Microbiome Project is an initiative aimed at uncovering the dynamic co-associations between people's bacteria and the bacteria found in their homes.The hope is that the data and project will show that routine monitoring of the microbial diversity of your body and of the environment in which you live is possible.

  19. Exemption from Application of the Service Contract Act -Requirements UT-B Contracts Div Maintenance, Calibration, or Repair of Certain Equipment

    E-Print Network [OSTI]

    Maintenance, Calibration, or Repair of Certain Equipment Jan 2008 Page 1 of 1 exemp-sca-equip-requirement-ext-jan08.doc EXEMPTION FROM APPLICATION OF THE SERVICE CONTRACT ACT ­ MAINTENANCE, CALIBRATION, OR REPAIR quantities to the general public in the course of normal business operations. (b) The services shall

  20. Exemption from Application of the Service Contract Act -Certification UT-B Contracts Div Maintenance, Calibration, or Repair of Certain Equipment

    E-Print Network [OSTI]

    Maintenance, Calibration, or Repair of Certain Equipment Mar 2009 Page 1 of 1 exemp-sca-equip-certification-ext-venx-mar09.doc EXEMPTION FROM APPLICATION OF THE SERVICE CONTRACT ACT ­ MAINTENANCE, CALIBRATION, OR REPAIR in the course of normal business operations. (2) The services will be furnished at prices which are

  1. Investigations of DNA damage induction and repair resulting from cellular exposure to high dose-rate pulsed proton beams

    SciTech Connect (OSTI)

    Renis, M.; Malfa, G.; Tomasello, B.; Borghesi, M.; Schettino, G.; Favetta, M.; Romano, F.; Cirrone, G. A. P.; Manti, L.

    2013-07-26

    Studies regarding the radiobiological effects of low dose radiation, microbeam irradiation services have been developed in the world and today laser acceleration of protons and heavy ions may be used in radiation therapy. The application of different facilities is essential for studying bystander effects and relating signalling phenomena in different cells or tissues. In particular the use of ion beams results advantageous in cancer radiotherapy compared to more commonly used X-rays, since the ability of ions in delivering lethal amount of doses into the target tumour avoiding or limiting damage to the contiguous healthy tissues. At the INFN-LNS in Catania, a multidisciplinary radiobiology group is strategically structured aimed to develop radiobiological research, finalised to therapeutic applications, compatible with the use of high dose laser-driven ion beams. The characteristic non-continuous dose rates with several orders of magnitude of laser-driven ion beams makes this facility very interesting in the cellular systems' response to ultra-high dose rates with non-conventional pulse time intervals cellular studies. Our group have projected to examine the effect of high dose laser-driven ion beams on two cellular types: foetal fibroblasts (normal control cells) and DU145 (prostate cancer cells), studying the modulation of some different bio-molecular parameters, in particular cell proliferation and viability, DNA damage, redox cellular status, morphological alterations of both the cytoskeleton components and some cell organelles and the possible presence of apoptotic or necrotic cell death. Our group performed preliminary experiments with high energy (60 MeV), dose rate of 10 Gy/min, doses of 1, 2, 3 Gy and LET 1 keV/?m on human foetal fibroblasts (control cells). We observed that cell viability was not influenced by the characteristics of the beam, the irradiation conditions or the analysis time. Conversely, DNA damage was present at time 0, immediately following irradiation in a dose-dependent manner. The analysis of repair capability showed that the cells irradiated with 1 and 2 Gy almost completely recovered from the damage, but not, however, 3 Gy treated cells in which DNA damage was not recovered. In addition, the results indicate the importance of the use of an appropriate control in radiobiological in vitro analysis.

  2. Energy Efficiency Measures to Incorporate into Remodeling Projects

    SciTech Connect (OSTI)

    Liaukus, C.

    2014-12-01

    Energy improvements in a home are often approached as one concerted effort, beginning with a simple walk-through assessment or more in-depth energy audit and followed by the installation of recommended energy measures. While this approach allows for systems thinking to guide the efforts, comprehensive energy improvements of this nature are undertaken by a relatively small number of the households in our nation compared to more piecemeal remodeling efforts. Even when programs like the Weatherization Assistance Program and Home Performance with ENERGY STAR are considered, homes that have had a comprehensive energy makeover still represent a small fraction of the 111.1 million households. In this report, the U.S Department of Energy Building America Retrofit Alliance research team looks at the improvement of a home's energy performance in an opportunistic way: it examines what can be done to incorporate energy efficiency measures into general remodeling work and home repair projects. This allows for the possibility for people who would not normally pursue energy efficiency but will remodel their kitchen or re-side their home to improve their home's performance at the same time. There are challenges to this approach, not the least of which being that the work will take place over time in potentially many separate projects. The opportunity to improve a home's energy efficiency at one time expands or contracts with the scope of the remodel. As such, guidance on how to do each piece thoughtfully and with consideration for potential future projects, is critical.

  3. Energy Efficiency Measures to Incorporate into Remodeling Projects

    SciTech Connect (OSTI)

    Liaukus, C.

    2014-12-01

    Energy improvements in a home are often approached as one concerted effort, beginning with a simple walk-through assessment or more in-depth energy audit and followed by the installation of recommended energy measures. While this approach allows for systems thinking to guide the efforts, comprehensive energy improvements of this nature are undertaken by a relatively small number of U.S. households compared to piecemeal remodeling efforts. In this report, the U.S Department of Energy Building America Retrofit Alliance research team examines the improvement of a home’s energy performance in an opportunistic way by examining what can be done to incorporate energy efficiency measures into general remodeling work and home repair projects. This allows for energy efficiency upgrades to occur at the same time as remodeling proejcts. There are challenges to this approach, not the least of which being that the work will take place over time in potentially many separate projects. The opportunity to improve a home’s energy efficiency at one time expands or contracts with the scope of the remodel. As such, guidance on how to do each piece thoughtfully and with consideration for potential future projects, is critical.

  4. North American LNG Project Sourcebook

    SciTech Connect (OSTI)

    2007-06-15

    The report provides a status of the development of LNG Import Terminal projects in North America, and includes 1-2 page profiles of 63 LNG projects in North America which are either in operation, under construction, or under development. For each project, the sourcebook provides information on the following elements: project description, project ownership, project status, projected operation date, storage capacity, sendout capacity, and pipeline interconnection.

  5. Nikon Instruments Inc. | Resource Center -Research Papers -New insights into DNA repair http://www.nikoninstruments.com/Resource-Center/Research-Papers/New-insights-into-DNA-repair[4/10/2012 10:42:30 AM

    E-Print Network [OSTI]

    Kowalczykowski, Stephen C.

    Nikon Instruments Inc. | Resource Center - Research Papers - New insights into DNA repair http:42:30 AM] change locationAMS EN Nikon Instruments Inc. on Facebook Like You like th Page · Ins Resource constrain available 3D conformations and slow the rate of homologous pairing while longer ssDNA strands

  6. Energy Efficiency Project Development

    SciTech Connect (OSTI)

    IUEP

    2004-03-01

    The International Utility Efficiency Partnerships, Inc. (IUEP) has been a leader among the industry groups that have supported voluntary initiatives to promote international energy efficiency projects and address global climate change. The IUEP maintains its leadership by both supporting international greenhouse gas (GHG) reduction projects under the auspices of the U.S. Department of Energy (DOE) and by partnering with U.S. and international organizations to develop and implement strategies and specific energy efficiency projects. The goals of the IUEP program are to (1) provide a way for U.S. industry to maintain a leadership role in international energy efficiency infrastructure projects; (2) identify international energy project development opportunities to continue its leadership in supporting voluntary market-based mechanisms to reduce GHG emissions; and (3) demonstrate private sector commitment to voluntary approaches to global climate issues. The IUEP is dedicated to identifying, promoting, managing, and assisting in the registration of international energy efficiency projects that result in demonstrated voluntary reductions of GHG emissions. This Final Technical Report summarizes the IUEP's work in identifying, promoting, managing, and assisting in development of these projects and IUEP's effort in creating international cooperative partnerships to support project development activities that develop and deploy technologies that (1) increase efficiency in the production, delivery and use of energy; (2) increase the use of cleaner, low-carbon fuels in processing products; and (3) capture/sequester carbon gases from energy systems. Through international cooperative efforts, the IUEP intends to strengthen partnerships for energy technology innovation and demonstration projects capable of providing cleaner energy in a cost-effective manner. As detailed in this report, the IUEP met program objectives and goals during the reporting period January 1, 2001 through December 31, 2002. At the request of the DOE, we have also included in this report additional activities during the reporting period January, 1999 through January, 2001. This additional information had been reported earlier in the Final Technical Reports that summarized activities undertaken in those earlier periods.

  7. Published on Science 2.0 (http://www.science20.com) Home > Life Sciences > Genetics & Molecular Biology > News Articles > Rad51: Watching Single Strands Of DNA Being Prepped For Repair Could Help Fight Breast Cancer

    E-Print Network [OSTI]

    Kowalczykowski, Stephen C.

    Biology > News Articles > Rad51: Watching Single Strands Of DNA Being Prepped For Repair Could Help Fight Breast Cancer Rad51: Watching Single Strands Of DNA Being Prepped For Repair Could Help Fight Breast: Watching Single Strands Of DNA Being Prepped For Repair Could Help Fight Br... 6/17/2013http

  8. Hydropower major rehabilitation projects

    SciTech Connect (OSTI)

    Norlin, J.A. [Army Corps of Engineers, Portland, OR (United States)

    1995-12-31

    The Corps of Engineers has developed an active Major Rehabilitation Program to handle large, long duration restoration projects. These projects are funded by specific appropriations and subsequently are required to have detailed rehabilitation plans to justify the work. The emphasis of the Major Rehabilitation Program is correcting reliability problems. Papers that were presented at Waterpower `93 discussed the basic concepts that are required in preparing a Major Rehabilitation Evaluation Report. This paper will cover the current status of each of the current major rehabilitation projects that the Corps of Engineers has in progress.

  9. LIMB demonstration project extension

    SciTech Connect (OSTI)

    Not Available

    1990-09-21

    The purpose of the DOE limestone injection multistage burner (LIMB) Demonstration Project Extension is to extend the data base on LIMB technology and to expand DOE's list of Clean Coal Technologies by demonstrating the Coolside process as part of the project. The main objectives of this project are: to demonstrate the general applicability of LIMB technology by testing 3 coals and 4 sorbents (total of 12 coal/sorbent combinations) at the Ohio Edison Edgewater plant; and to demonstrate that Coolside is a viable technology for improving precipitator performance and reducing sulfur dioxide emissions while acceptable operability is maintained. Progress is reported. 3 figs.

  10. NAVAJO ELECTRIFICATION DEMONSTRATION PROJECT

    SciTech Connect (OSTI)

    Terry W. Battiest

    2008-06-11

    The Navajo Electrification Demonstration Project (NEDP) is a multi-year project which addresses the electricity needs of the unserved and underserved Navajo Nation, the largest American Indian tribe in the United States. The program serves to cumulatively provide off-grid electricty for families living away from the electricty infrastructure, line extensions for unserved families living nearby (less than 1/2 mile away from) the electricity, and, under the current project called NEDP-4, the construction of a substation to increase the capacity and improve the quality of service into the central core region of the Navajo Nation.

  11. Drilling and Microfracture Lead to Different Bone Structure and Necrosis during Bone-Marrow Stimulation for Cartilage Repair

    E-Print Network [OSTI]

    Buschmann, Michael

    Drilling and Microfracture Lead to Different Bone Structure and Necrosis during Bone following microfracture and comparing to drilling in a mature rabbit model of cartilage repair. Microfracture holes were made to a depth of 2 mm and drill holes to either 2 mm or 6 mm under cooled irrigation

  12. Image-Guided Techniques Improve the Short-term Outcome of Autologous Osteochondral Cartilage Repair Surgeries -An

    E-Print Network [OSTI]

    Stewart, James

    Image-Guided Techniques Improve the Short-term Outcome of Autologous Osteochondral Cartilage Repair and deliver osteochondral grafts remains problematic. We investigated whether image-guided methods (optically-guided and template-guided) can improve the outcome of mo- saic arthroplasty procedures. Methods: Fifteen sheep were

  13. Homologous recombination contributes to the repair of DNA double-strand breaks induced by high-energy iron ions

    SciTech Connect (OSTI)

    Zafar, Faria; Seidler, Sara B.; Kronenberg, Amy; Schild, David; Wiese, Claudia

    2010-06-29

    To test the contribution of homologous recombinational repair (HRR) in repairing DNA damaged sites induced by high-energy iron ions, we used: (1) HRR-deficient rodent cells carrying a deletion in the RAD51D gene and (2) syngeneic human cells impaired for HRR by RAD51D or RAD51 knockdown using RNA interference. We show that in response to iron ions, HRR contributes to cell survival in rodent cells, and that HRR-deficiency abrogates RAD51 foci formation. Complementation of the HRR defect by human RAD51D rescues both enhanced cytotoxicity and RAD51 foci formation. For human cells irradiated with iron ions, cell survival is decreased, and, in p53 mutant cells, the levels of mutagenesis are increased when HRR is impaired. Human cells synchronized in S phase exhibit more pronounced resistance to iron ions as compared with cells in G1 phase, and this increase in radioresistance is diminished by RAD51 knockdown. These results implicate a role for RAD51-mediated DNA repair (i.e. HRR) in removing a fraction of clustered lesions induced by charged particle irradiation. Our results are the first to directly show the requirement for an intact HRR pathway in human cells in ensuring DNA repair and cell survival in response to high-energy high LET radiation.

  14. Direct observations of DNA provides new insights into how genetic material is copied and repaired News-Medical.Net

    E-Print Network [OSTI]

    Kowalczykowski, Stephen C.

    Direct observations of DNA provides new insights into how genetic material is copied and repaired News-Medical.Net · Home Page Direct observations of DNA provides new insights into how genetic material to a Friend Direct observations of DNA are giving new insights into how genetic material is copied

  15. Global-to-Local Rule Generation for Self-Assembly and Self-Repair by Robot Swarms

    E-Print Network [OSTI]

    Southern California, University of

    Global-to-Local Rule Generation for Self-Assembly and Self-Repair by Robot Swarms Daniel Arbuckle a reactive self-assembly technique intended for use in swarms of simple robots, the other a distributed in the possibility that swarms of general-purpose self-assembling robots might be used to replace many such objects

  16. International Journal of Adhesion & Adhesives 26 (2006) 314324 Dynamic response of a repaired composite beam with an adhesively

    E-Print Network [OSTI]

    Vaziri, Ashkan

    2006-01-01

    International Journal of Adhesion & Adhesives 26 (2006) 314­324 Dynamic response of a repaired composite beam with an adhesively bonded patch under a harmonic peeling load A. Vaziri1 , H. Nayeb with adhesive. In the theoretical part, the equations of motion in the axial and transverse directions were

  17. Charge-transport-mediated recruitment of DNA repair enzymes Pak-Wing Fok,1,2,a

    E-Print Network [OSTI]

    Levine, Alex J.

    Charge-transport-mediated recruitment of DNA repair enzymes Pak-Wing Fok,1,2,a Chin-Lin Guo,3 and Tom Chou2,4,b 1 Applied and Computational Mathematics, California Institute of Technology, Pasadena, California 91125, USA 2 Department of Biomathematics, UCLA, Los Angeles, California 90095-1766, USA 3 Applied

  18. NNSA project receives DOE Secretary's Award for Project Management...

    National Nuclear Security Administration (NNSA)

    project receives DOE Secretary's Award for Project Management Improvement | National Nuclear Security Administration Facebook Twitter Youtube Flickr RSS People Mission Managing the...

  19. Contract/Project Management

    Office of Environmental Management (EM)

    (Post- RCACAP) 80% Cleanup 86% Cleanup 67% Pre-CAP 88% Post-CAP This is based on a 3-year rolling average (FY09 to FY11, Note: zero cleanup projects completed in FY09). TPC is...

  20. CNEEC - Research Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    of developing systems that can lead to break-out high-efficiency, cost-effective solar energy-to-fuel technologies. The projects are closely tied together through two mechanisms:...

  1. Hualapai Tribe- 2010 Project

    Broader source: Energy.gov [DOE]

    The project will build on the potential for renewable energy development on the Hualapai Reservation that was identified during the Phase l renewable energy resource assessment conducted by the Hualapai Tribe since 2005.

  2. Solar Forecast Improvement Project

    Office of Energy Efficiency and Renewable Energy (EERE)

    For the Solar Forecast Improvement Project (SFIP), the Earth System Research Laboratory (ESRL) is partnering with the National Center for Atmospheric Research (NCAR) and IBM to develop more...

  3. AVTA: The EV Project

    Broader source: Energy.gov [DOE]

    The EV Project partnered with city, regional and state governments, utilities, and other organizations in 18 cities to deploy about 12,500 public and residential charging stations.  It also...

  4. Winnebago Tribe- 2014 Project

    Broader source: Energy.gov [DOE]

    Following through with the Winnebago Tribe's commitment to reduce energy usage and consumption, the Winnebago Tribe Solar Project will focus on renewable energy production and energy cost savings consistent with protecting our natural environment.

  5. Offshore Wind Project Map

    Broader source: Energy.gov [DOE]

    Image that shows the demonstration project site and developer headquarters for two funding opportunity announcements: the 2011 Grants for Technology Development and the 2011 Grants for Removing Market Barriers.

  6. QUEST2 Energy Project 

    E-Print Network [OSTI]

    Clary, A. T.

    2007-01-01

    methodical process to identify primarily behavioral or procedural opportunities to improve energy efficiency. A key component of this process was to put control plans in place to maintain any gains that were achieved. The project resulting in finding...

  7. Portsmouth Paducah Project Office

    Broader source: Energy.gov [DOE]

    The U.S. Department of Energy (DOE) established the Portsmouth/Paducah Project Office (PPPO) on October 1, 2003, to provide focused leadership to the Environmental Management missions at the...

  8. Contract/Project Management

    Energy Savers [EERE]

    76% This is a 3-year rolling average Data includes FY06 to FY08. (3748) 2. EM Cleanup (Soil and Groundwater Remediation, D&D, and Waste Treatment and Disposal) Projects: 90% of EM...

  9. Federal Project Facilitators

    Office of Energy Efficiency and Renewable Energy (EERE)

    The following are U.S. Department of Energy (DOE) approved project facilitators who are required under the DOE indefinite-delivery, indefinite-quantity contract to develop federal energy savings performance contracts.

  10. PROJECTION PURSUIT Jiayang Sun

    E-Print Network [OSTI]

    Sun, Jiayang

    PROJECTION PURSUIT Jiayang Sun Many data sets are high dimensional. It has been a common practice Friedman [7], Hall [11], Morton [21], Sun [23, 24], Cook et al. [2], Li and Cheng [19] and Roosen

  11. St. Bernard Project Update

    Broader source: Energy.gov [DOE]

    The folks at St. Bernard Project are helping survivors of Hurricane Katrina get back into their homes -- and are using new technologies to reduce energy and save money for the returning residents.

  12. Project financial evaluation

    SciTech Connect (OSTI)

    None, None

    2009-01-18

    The project financial section of the Renewable Energy Technology Characterizations describes structures and models to support the technical and economic status of emerging renewable energy options for electricity supply.

  13. Navajo Electrification Demonstraiton Project

    SciTech Connect (OSTI)

    Larry Ahasteen, Project Manager

    2006-07-17

    This is a final technical report required by DOE for the Navajo Electrification Demonstration Program, This report covers the electric line extension project for Navajo families that currently without electric power.

  14. Lake Charles CCS Project

    SciTech Connect (OSTI)

    Leib, Thomas; Cole, Dan

    2015-06-30

    In late September 2014 development of the Lake Charles Clean Energy (LCCE) Plant was abandoned resulting in termination of Lake Charles Carbon Capture and Sequestration (CCS) Project which was a subset the LCCE Plant. As a result, the project was only funded through Phase 2A (Design) and did not enter Phase 2B (Construction) or Phase 2C (Operations). This report was prepared relying on information prepared and provided by engineering companies which were engaged by Leucadia Energy, LLC to prepare or review Front End Engineering and Design (FEED) for the Lake Charles Clean Energy Project, which includes the Carbon Capture and Sequestration (CCS) Project in Lake Charles, Louisiana. The Lake Charles Carbon Capture and Sequestration (CCS) Project was to be a large-scale industrial CCS project intended to demonstrate advanced technologies that capture and sequester carbon dioxide (CO2) emissions from industrial sources into underground formations. The Scope of work was divided into two discrete sections; 1) Capture and Compression prepared by the Recipient Leucadia Energy, LLC, and 2) Transport and Sequestration prepared by sub-Recipient Denbury Onshore, LLC. Capture and Compression-The Lake Charles CCS Project Final Technical Report describes the systems and equipment that would be necessary to capture CO2 generated in a large industrial gasification process and sequester the CO2 into underground formations. The purpose of each system is defined along with a description of its equipment and operation. Criteria for selection of major equipment are provided and ancillary utilities necessary for safe and reliable operation in compliance with environmental regulations are described. Construction considerations are described including a general arrangement of the CCS process units within the overall gasification project. A cost estimate is provided, delineated by system area with cost breakdown showing equipment, piping and materials, construction labor, engineering, and other costs. The CCS Project Final Technical Report is based on a Front End Engineering and Design (FEED) study prepared by SK E&C, completed in [June] 2014. Subsequently, Fluor Enterprises completed a FEED validation study in mid-September 2014. The design analyses indicated that the FEED package was sufficient and as expected. However, Fluor considered the construction risk based on a stick-build approach to be unacceptable, but construction risk would be substantially mitigated through utilization of modular construction where site labor and schedule uncertainty is minimized. Fluor’s estimate of the overall EPC project cost utilizing the revised construction plan was comparable to SKE&C’s value after reflecting Fluor’s assessment of project scope and risk characteristic. Development was halted upon conclusion of Phase 2A FEED and the project was not constructed.Transport and Sequestration – The overall objective of the pipeline project was to construct a pipeline to transport captured CO2 from the Lake Charles Clean Energy project to the existing Denbury Green Line and then to the Hastings Field in Southeast Texas to demonstrate effective geologic sequestration of captured CO2 through commercial EOR operations. The overall objective of the MVA portion of the project was to demonstrate effective geologic sequestration of captured CO2 through commercial Enhanced Oil Recovery (EOR) operations in order to evaluate costs, operational processes and technical performance. The DOE target for the project was to capture and implement a research MVA program to demonstrate the sequestration through EOR of approximately one million tons of CO2 per year as an integral component of commercial operations.

  15. Term Pricing Project

    E-Print Network [OSTI]

    Jeff Beckley

    2015-10-29

    Term Pricing Project. Your job is to reprice Purdue Life's 20 Year Term. You are to write a one page memo or report summarizing your work. The report should ...

  16. A Mobile Robot Project

    E-Print Network [OSTI]

    Brooks, Rodney A.

    We are building a mobile robot which will roam around the AI lab observing and later perhaps doing. Our approach to building the robot and its controlling software differs from that used in many other projects in a number ...

  17. Method and apparatus for in-system redundant array repair on integrated circuits

    DOE Patents [OSTI]

    Bright, Arthur A. (Croton-on-Hudson, NY); Crumley, Paul G. (Yorktown Heights, NY); Dombrowa, Marc B. (Bronx, NY); Douskey, Steven M. (Rochester, MN); Haring, Rudolf A. (Cortlandt Manor, NY); Oakland, Steven F. (Colchester, VT); Ouellette, Michael R. (Westford, VT); Strissel, Scott A. (Byron, MN)

    2008-07-08

    Disclosed is a method of repairing an integrated circuit of the type comprising of a multitude of memory arrays and a fuse box holding control data for controlling redundancy logic of the arrays. The method comprises the steps of providing the integrated circuit with a control data selector for passing the control data from the fuse box to the memory arrays; providing a source of alternate control data, external of the integrated circuit; and connecting the source of alternate control data to the control data selector. The method comprises the further step of, at a given time, passing the alternate control data from the source thereof, through the control data selector and to the memory arrays to control the redundancy logic of the memory arrays.

  18. Method and apparatus for in-system redundant array repair on integrated circuits

    DOE Patents [OSTI]

    Bright, Arthur A. (Croton-on-Hudson, NY); Crumley, Paul G. (Yorktown Heights, NY); Dombrowa, Marc B. (Bronx, NY); Douskey, Steven M. (Rochester, MN); Haring, Rudolf A. (Cortlandt Manor, NY); Oakland, Steven F. (Colchester, VT); Ouellette, Michael R. (Westford, VT); Strissel, Scott A. (Byron, MN)

    2007-12-18

    Disclosed is a method of repairing an integrated circuit of the type comprising of a multitude of memory arrays and a fuse box holding control data for controlling redundancy logic of the arrays. The method comprises the steps of providing the integrated circuit with a control data selector for passing the control data from the fuse box to the memory arrays; providing a source of alternate control data, external of the integrated circuit; and connecting the source of alternate control data to the control data selector. The method comprises the further step of, at a given time, passing the alternate control data from the source thereof, through the control data selector and to the memory arrays to control the redundancy logic of the memory arrays.

  19. Method and apparatus for in-system redundant array repair on integrated circuits

    DOE Patents [OSTI]

    Bright, Arthur A. (Croton-on-Hudson, NY); Crumley, Paul G. (Yorktown Heights, NY); Dombrowa, Marc B. (Bronx, NY); Douskey, Steven M. (Rochester, MN); Haring, Rudolf A. (Cortlandt Manor, NY); Oakland, Steven F. (Colchester, VT); Ouellette, Michael R. (Westford, VT); Strissel, Scott A. (Byron, MN)

    2008-07-29

    Disclosed is a method of repairing an integrated circuit of the type comprising of a multitude of memory arrays and a fuse box holding control data for controlling redundancy logic of the arrays. The method comprises the steps of providing the integrated circuit with a control data selector for passing the control data from the fuse box to the memory arrays; providing a source of alternate control data, external of the integrated circuit; and connecting the source of alternate control data to the control data selector. The method comprises the further step of, at a given time, passing the alternate control data from the source thereof, through the control data selector and to the memory arrays to control the redundancy logic of the memory arrays.

  20. Design structure for in-system redundant array repair in integrated circuits

    DOE Patents [OSTI]

    Bright, Arthur A.; Crumley, Paul G.; Dombrowa, Marc; Douskey, Steven M.; Haring, Rudolf A.; Oakland, Steven F.; Quellette, Michael R.; Strissel, Scott A.

    2008-11-25

    A design structure for repairing an integrated circuit during operation of the integrated circuit. The integrated circuit comprising of a multitude of memory arrays and a fuse box holding control data for controlling redundancy logic of the arrays. The design structure provides the integrated circuit with a control data selector for passing the control data from the fuse box to the memory arrays; providing a source of alternate control data, external of the integrated circuit; and connecting the source of alternate control data to the control data selector. The design structure further passes the alternate control data from the source thereof, through the control data selector and to the memory arrays to control the redundancy logic of the memory arrays.

  1. Innovative Self- Generating Projects 

    E-Print Network [OSTI]

    Kelly, L.

    2013-01-01

    ? All rights reserved. Case Studies on Canadian Customer Generation Projects Innovative Self-Generation Projects Liam Kelly, M.A.Sc, CMVP Energy Engineer Willis Energy Services A CLEAResult company ESL-IE-13-05-06 Proceedings of the Thrity...-05-06 Proceedings of the Thrity-Fifth Industrial Energy Technology Conference New Orleans, LA. May 21-24, 2013 ? 2013 CLEAResult ? All rights reserved. Overcoming Challenges ? Look for innovative opportunities ? Leverage available incentives ? Quantify other...

  2. Black Pine Circle Project

    SciTech Connect (OSTI)

    Mytko, Christine

    2014-03-31

    A group of seventh graders from Black Pine Circle school in Berkeley had the opportunity to experience the Advanced Light Source (ALS) as "users" via a collaborative field trip and proposal project. The project culminated with a field trip to the ALS for all seventh graders, which included a visit to the ALS data visualization room, a diffraction demonstration, a beamline tour, and informative sessions about x-rays and tomography presented by ALS scientists.

  3. Black Pine Circle Project

    ScienceCinema (OSTI)

    Mytko, Christine

    2014-09-15

    A group of seventh graders from Black Pine Circle school in Berkeley had the opportunity to experience the Advanced Light Source (ALS) as "users" via a collaborative field trip and proposal project. The project culminated with a field trip to the ALS for all seventh graders, which included a visit to the ALS data visualization room, a diffraction demonstration, a beamline tour, and informative sessions about x-rays and tomography presented by ALS scientists.

  4. The Mississippi CCS Project

    SciTech Connect (OSTI)

    Doug Cathro

    2010-09-30

    The Mississippi CCS Project is a proposed large-scale industrial carbon capture and sequestration (CCS) project which would have demonstrated advanced technologies to capture and sequester carbon dioxide (CO{sub 2}) emissions from industrial sources into underground formations. Specifically, the Mississippi CCS Project was to accelerate commercialization of large-scale CO{sub 2} storage from industrial sources by leveraging synergy between a proposed petcoke to Substitute Natural Gas (SNG) plant that is selected for a Federal Loan Guarantee and would be the largest integrated anthropogenic CO{sub 2} capture, transport, and monitored sequestration program in the U.S. Gulf Coast Region. The Mississippi CCS Project was to promote the expansion of enhanced oil recovery (EOR) in the Mississippi, Alabama and Louisiana region which would supply greater energy security through increased domestic energy production. The capture, compression, pipeline, injection, and monitoring infrastructure would have continued to sequester CO{sub 2} for many years after the completion of the term of the DOE agreement. The objectives of this project were expected to be fulfilled through two distinct phases. The overall objective of Phase 1 was to develop a fully definitive project basis for a competitive Renewal Application process to proceed into Phase 2 - Design, Construction and Operations. Phase 1 included the studies that establish the engineering design basis for the capture, compression and transportation of CO{sub 2} from the MG SNG Project, and the criteria and specifications for a monitoring, verification and accounting (MVA) plan at the Soso oil field in Mississippi. The overall objective of Phase 2, was to execute design, construction and operations of three capital projects: the CO{sub 2} capture and compression equipment, the Mississippi CO{sub 2} Pipeline to Denbury's Free State Pipeline, and an MVA system at the Soso oil field.

  5. Projects | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:Financing Tool FitsProject Develops Student-Stakeholders ProjectBaseload

  6. Judge Evaluation Scoring Form for Project Technical Report PROJECT .#.: ..Project Title......

    E-Print Network [OSTI]

    Dahlberg, Teresa A.

    Judge Evaluation Scoring Form for Project Technical Report PROJECT .#.: ..Project Title...... #12 of the project?) Excellent Very Good Good Fair Unsatisfactory COMMENTS: #12;Judge Evaluation Scoring Form for REU and click! PROJECT TITLE REU Site: Computing Research for Undergraduates: Visualization, Virtual

  7. Project Title: Earthquake Documentary Interviews

    E-Print Network [OSTI]

    Hickman, Mark

    Project Title: Earthquake Documentary Interviews Bachelor of Arts Internship Company: Chris Thomson Academic Adviser: Mary Wiles Project Reference Number: S112/CEISMIC/29/NP - Earthquake collected on the earthquake, its survivors and their stories. This project is unique

  8. Projects of the year

    SciTech Connect (OSTI)

    Hansen, T.

    2007-01-15

    The Peabody Hotel, Orlando, Florida was the site of Power Engineering magazine's 2006 Projects of the Year Awards Banquet, which kicked-off the Power-Gen International conference and exhibition. The Best Coal-fired Project was awarded to Tri-State Generation and Transmission Association Inc., owner of Springenville Unit 3. This is a 400 MW pulverized coal plant in Springeville, AZ, sited with two existing coal-fired units. Designed to fire Powder River Basin coal, it has low NOx burners and selective catalytic reduction for NOx control, dry flue gas desulfurization for SO{sub 2} control and a pulse jet baghouse for particulate control. It has a seven-stage feedwater heater and condensers to ensure maximum performance. Progress Energy-Carolinas' Asheville Power Station FGD and SCR Project was awarded the 2006 coal-fired Project Honorable Mention. This plant in Skyland, NC was required to significantly reduce NOx emissions. When completed, the improvements will reduce NOx by 93% compared to 1996 levels and SO{sub 2} by 93% compared to 2001 levels. Awards for best gas-fired, nuclear, and renewable/sustainable energy projects are recorded. The Sasyadko Coal-Mine Methane Cogeneration Plant near Donezk, Ukraine, was given the 2006 Honorable Mention for Best Renewable/Sustainable Energy Project. In November 2004, Ukraine was among 14 nations to launch the Methane to Markets partnership. The award-winning plant is fuelled by methane released during coal extraction. It generates 42 MW of power. 4 photos.

  9. Geysers Project Geothermal Project | Open Energy Information

    Open Energy Info (EERE)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on QA:QA J-E-1 SECTION J APPENDIXsource History View New Pages RecentPlant <Silver Peak Area (DOEEnergyProject

  10. Project Analysis Standard Operating Procedure

    Office of Environmental Management (EM)

    Standard Operating Procedure (EPASOP) Issued by Office of Acquisition and Project Management MA-63 March 12, 2014 DEPARTMENT OF ENERGY Office of Acquisition and Project...

  11. Jefferson Lab Project Control System Manual

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Project Control System Manual Technical Engineering Development Facility (TEDF) Utilities Infrastructure Modernization (UIM) Office of Project Management Project Control...

  12. July 2015 Project Dashboard.xls

    Broader source: Energy.gov (indexed) [DOE]

    Date: 07232015 Program Contractor Project Number Project Title Original Project Budget Project Budget Monthly Overall Assessment Cost Performance Schedule Performance 1 EM...

  13. September 2015 Project Dashboard | Department of Energy

    Energy Savers [EERE]

    September 2015 Project Dashboard September 2015 Project Dashboard Post CD-2 Active Projects (as of September 29, 2015) September 2015 Project Dashboard More Documents &...

  14. Instrument validation project

    SciTech Connect (OSTI)

    Reynolds, B.A.; Daymo, E.A.; Geeting, J.G.H.; Zhang, J.

    1996-06-01

    Westinghouse Hanford Company Project W-211 is responsible for providing the system capabilities to remove radioactive waste from ten double-shell tanks used to store radioactive wastes on the Hanford Site in Richland, Washington. The project is also responsible for measuring tank waste slurry properties prior to injection into pipeline systems, including the Replacement of Cross-Site Transfer System. This report summarizes studies of the appropriateness of the instrumentation specified for use in Project W-211. The instruments were evaluated in a test loop with simulated slurries that covered the range of properties specified in the functional design criteria. The results of the study indicate that the compact nature of the baseline Project W-211 loop does not result in reduced instrumental accuracy resulting from poor flow profile development. Of the baseline instrumentation, the Micromotion densimeter, the Moore Industries thermocouple, the Fischer and Porter magnetic flow meter, and the Red Valve Pressure transducer meet the desired instrumental accuracy. An alternate magnetic flow meter (Yokagawa) gave nearly identical results as the baseline fischer and Porter. The Micromotion flow meter did not meet the desired instrument accuracy but could potentially be calibrated so that it would meet the criteria. The Nametre on-line viscometer did not meet the desired instrumental accuracy and is not recommended as a quantitative instrument although it does provide qualitative information. The recommended minimum set of instrumentation necessary to ensure the slurry meets the Project W-058 acceptance criteria is the Micromotion mass flow meter and delta pressure cells.

  15. 2020 Vision Project Summary

    SciTech Connect (OSTI)

    Gordon, K.W.; Scott, K.P.

    2000-11-01

    Since the 2020 Vision project began in 1996, students from participating schools have completed and submitted a variety of scenarios describing potential world and regional conditions in the year 2020 and their possible effect on US national security. This report summarizes the students' views and describes trends observed over the course of the 2020 Vision project's five years. It also highlights the main organizational features of the project. An analysis of thematic trends among the scenarios showed interesting shifts in students' thinking, particularly in their views of computer technology, US relations with China, and globalization. In 1996, most students perceived computer technology as highly beneficial to society, but as the year 2000 approached, this technology was viewed with fear and suspicion, even personified as a malicious, uncontrollable being. Yet, after New Year's passed with little disruption, students generally again perceived computer technology as beneficial. Also in 1996, students tended to see US relations with China as potentially positive, with economic interaction proving favorable to both countries. By 2000, this view had transformed into a perception of China emerging as the US' main rival and ''enemy'' in the global geopolitical realm. Regarding globalization, students in the first two years of the project tended to perceive world events as dependent on US action. However, by the end of the project, they saw the US as having little control over world events and therefore, we Americans would need to cooperate and compromise with other nations in order to maintain our own well-being.

  16. Radiation Embrittlement Archive Project

    SciTech Connect (OSTI)

    Klasky, Hilda B; Bass, Bennett Richard; Williams, Paul T; Phillips, Rick; Erickson, Marjorie A; Kirk, Mark T; Stevens, Gary L

    2013-01-01

    The Radiation Embrittlement Archive Project (REAP), which is being conducted by the Probabilistic Integrity Safety Assessment (PISA) Program at Oak Ridge National Laboratory under funding from the U.S. Nuclear Regulatory Commission s (NRC) Office of Nuclear Regulatory Research, aims to provide an archival source of information about the effect of neutron radiation on the properties of reactor pressure vessel (RPV) steels. Specifically, this project is an effort to create an Internet-accessible RPV steel embrittlement database. The project s website, https://reap.ornl.gov, provides information in two forms: (1) a document archive with surveillance capsule(s) reports and related technical reports, in PDF format, for the 104 commercial nuclear power plants (NPPs) in the United States, with similar reports from other countries; and (2) a relational database archive with detailed information extracted from the reports. The REAP project focuses on data collected from surveillance capsule programs for light-water moderated, nuclear power reactor vessels operated in the United States, including data on Charpy V-notch energy testing results, tensile properties, composition, exposure temperatures, neutron flux (rate of irradiation damage), and fluence, (Fast Neutron Fluence a cumulative measure of irradiation for E>1 MeV). Additionally, REAP contains data from surveillance programs conducted in other countries. REAP is presently being extended to focus on embrittlement data analysis, as well. This paper summarizes the current status of the REAP database and highlights opportunities to access the data and to participate in the project.

  17. New Mexico State University Campus geothermal demonstration project

    SciTech Connect (OSTI)

    Cuniff, R.A.; Fisher, K.P.; Chintawongvanich, P.

    1984-04-01

    This report presents the design, construction highlights, and performance of the New Mexico State University Campus Geothermal Demonstration Project at Las Cruces, New Mexico. Construction started in July 1981, first system use was January 1982, and the system was dedicated on April 21, 1982. Included herein are summary observations after two years of use. The geothermal hot water from New Mexico State University wells is used to heat potable water, which in turn provides 83 percent of the domestic hot water on the New Mexico State University campus, as well as space heat to two buildings, and for two heated swimming pools. The original system is providing service to 30 total buildings, with two additional buildings (150,000 square feet) in process of geothermal conversion.) The system overall performance has been excellent, except for geothermal well pump problems. In terms of operating efficiency, the system has exceeded the design parameters. In spite of abnormally high costs for well and pump repairs, the system has shown a positive cost avoidance of more than $118,000 for the first year of operation. For the first two full years of operation, the system has produced a net positive cost avoidance of more than $200,000. Payback on the total investment of $1,670,000 is projected to be 6 to 10 years, depending on the future prices of natural gas and electricity.

  18. AIDP -Apple Interface Design Project

    E-Print Network [OSTI]

    Tollmar, Konrad

    AIDP - Apple Interface Design Project AIDP - Apple Interface Design Project m 92-95 m Joy Mountford m Design Centre, Advanced Technology Group m Apple's Industrial Design Group "Encourage ProjectThe Project m Bridge the gulf between the physical and virtual worlds - Apple m Design a new way

  19. Combined Heat and Power Projects

    Broader source: Energy.gov [DOE]

    DOE's CHP Technical Assistance Partnerships (CHP TAPs) have compiled a select number of CHP project profiles.

  20. Innovation Program Student Initiated Project

    E-Print Network [OSTI]

    Bertini, Robert L.

    Innovation Program Student Initiated Project Proposal Guidelines Eligibility The team must include of the problem the innovation is meant to solve A clear description of the work to be done for the project Milestones for the project, as well as a projected 'end product' Background with enough detail

  1. Degree project in Communication Systems

    E-Print Network [OSTI]

    Maguire Jr., Gerald Q.

    and evaluate web-based application which could utilize sensor data. In this project, we focused on two aspectsDegree project in Communication Systems Second level, 30.0 HEC Stockholm, Sweden Y E T I A N A Web This thesis describes the project "A new Web Server for sensors". The project has created a demonstration web

  2. Enhanced Geothermal Systems Demonstration Projects

    SciTech Connect (OSTI)

    Geothermal Technologies Office

    2013-08-06

    Several Enhanced Geothermal Systems (EGS) demonstration projects are highlighted on this Geothermal Technologies Office Web page.

  3. Project Management Plan Chinese Food

    E-Print Network [OSTI]

    Igusa, Kiyoshi

    impact of this project? · Data management: How do we collect, preserve and sort all of the files? Which special equipment, facilities needed or wanted? According to http://project-management-knowledge.com/ weProject Management Plan Chinese Food According to NSF, the basic elements of a project management

  4. Cogeneration Project Analysis Update 

    E-Print Network [OSTI]

    Robinson, A. M.; Garcia, L. N.

    1987-01-01

    -1 ------------ COGENERATION PROJECT ANALYSIS UPDATE by Arthur M. Robinson & Luis N. Garcia ROBINSON & GARCIA Energy Consultants P. O. Box 1203, Destrehan, LA 70047 ABSTRACT Not long ago, to evaluate the feasibility of a cogeneration project, a simple economic analysis... pressure steam produced from the turbine exhaust. And fed to an extraction condensing steam turbine, coupled to a second generator. A depiction with typical values is shown in Figure 2. ~) ~ EL.eCTRICJTY FRCM (iE/.)eRATORS BoiLE.R GAS / Fl/EL R...

  5. CONNECTICUT BIOFUELS TECHNOLOGY PROJECT

    SciTech Connect (OSTI)

    BARTONE, ERIK

    2010-09-28

    DBS Energy Inc. (“DBS”) intends on using the Connecticut Biofuels Technology Project for the purpose of developing a small-scale electric generating systems that are located on a distributed basis and utilize biodiesel as its principle fuel source. This project will include research and analysis on the quality and applied use of biodiesel for use in electricity production, 2) develop dispatch center for testing and analysis of the reliability of dispatching remote generators operating on a blend of biodiesel and traditional fossil fuels, and 3) analysis and engineering research on fuel storage options for biodiesel of fuels for electric generation.

  6. Investor Confidence Project 

    E-Print Network [OSTI]

    Golden, M.

    2013-01-01

    Environmental Defense Fund’s Investor Confidence Project Delivering Investment Quality Energy Efficiency to Market ESL-KT-13-12-38 CATEE 2013: Clean Air Through Energy Efficiency Conference, San Antonio, Texas Dec. 16-18 Investor Confidence Project... Actionable Data ESL-KT-13-12-38 CATEE 2013: Clean Air Through Energy Efficiency Conference, San Antonio, Texas Dec. 16-18 Near-Term: Not Enough Deal-Flow • High Transaction Costs • Lack of Viable Origination Channels • Highly Variable Performance • Complex...

  7. Showcasing a Project 

    E-Print Network [OSTI]

    Miller, Kari

    2007-01-01

    Dr. John Sij, an agronomist at The Texas A&M University System Agricultural Research and Extension Center at Vernon. Story by Kari Miller SHOWCASING A PROJECT Groups work to solve stream?s impairment... present and most of them were landowners in that watershed,? he said. ?That was one of the Showcasing a Project tx H2O | pg. 9 best-attended meetings of landowners we?ve probably had in the state.? The team is bringing in Dr. George Di Giovanni...

  8. Projects | The Ames Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration wouldMass mapSpeedingProgramExemptions |(Conference)Project Tour Project Tour

  9. Engineering Endostatin-Producing Cartilaginous Constructs for Cartilage Repair Using Nonviral Transfection of Chondrocyte-Seeded and Mesenchymal-Stem-Cell-Seeded Collagen Scaffolds

    E-Print Network [OSTI]

    Jeng, Lily

    Although there is widespread recognition of the importance of angiogenesis in tissue repair, there is little work on the inhibition of angiogenesis in the context of tissue engineering of naturally avascular tissues, like ...

  10. Histone H3K4me3 Binding Is Required for the DNA Repair and Apoptotic Activities of ING1 Tumor

    E-Print Network [OSTI]

    Verkhusha, Vladislav V.

    of growth 1 (ING1) is implicated in oncogenesis, DNA damage repair, and apoptosis. Mutations within the ING11) is a member of the recently discovered family of tumor suppressors implicated in oncogenesis

  11. Background & Projects Publications

    E-Print Network [OSTI]

    Home Background & Projects Calendar Publications Staff Directory Links Search MAES Home | Field Stations | Station Home | Publications | FruitNet Weekly Report Northern Michigan FruitNet 2006 Weekly vineyards. Side hedging and/or topping shoots will be needed to get light and air to the fruiting zone

  12. Rank Project Name Directorate,

    E-Print Network [OSTI]

    ,000 0.5 400 lbs industrial waste, eliminates potential for oil contaminated run-off 3 RetrofitRank Project Name Directorate, Dept/Div and POC Cost Savings Payback (Years) Waste Reduction 1 Minimization of Silver Waste from Silver-Staining Electrophoretic Mini-Gels Life Sciences, Biology (B

  13. Project Summary Partnership Inspiration

    E-Print Network [OSTI]

    Everest, Graham R

    Businesses are hunting for solutions to reduce their carbon footprint and energy spend. This project follows as they help overcome the challenges of auditing and reducing the organisational carbon footprint. A television strategy underpinning their carbon footprint understanding and slashing carbon emissions by 10

  14. Final Year Project Report

    SciTech Connect (OSTI)

    Hubsch, Tristan

    2013-06-20

    In the last years of this eighteen-year grant project, the research efforts have focused mostly on the study of off-shell representations of supersymmetry, both on the worldline and on the world- sheet, i.e., both in supersymmetric quantum mechanics and in supersymmetric field theory in 1+1-dimensional spacetime.

  15. Kootznoowoo Incorporated- 2010 Project

    Broader source: Energy.gov [DOE]

    Thayer Lake Hydropower Development (TLHD) consists of a 1 MW+ run of the river hydropower project located in the Tongass Forest in the Admiralty Island National Monument Park that will provide the energy to the City of Angoon and Angoon Community Association (traditional tribe as recognized by Indian Reorganization Act).

  16. Pioneering Heat Pump Project

    Broader source: Energy.gov [DOE]

    Project objectives: To install and monitor an innovative WaterFurnace geothermal system that is technologically advanced and evolving; To generate hot water heating from a heat pump that uses non-ozone depleting refrigerant CO2. To demonstrate the energy efficiency of this system ground source heat pump system.

  17. Universitt Project EURAT

    E-Print Network [OSTI]

    Heermann, Dieter W.

    of individual people in far less time today than at the conclusion of the Human Genome Project in 2003 (Collins of Whole Human Genome Sequencing" Position Paper Cornerstones for an ethiCally and legally informed Pra 60 61 63 65 67 69 70 71 73 88 96 100 #12;4 5Ethical and Legal Aspects of Whole Human Genome

  18. Information Technology Project Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-09-12

    This Guide provides Department of Energy recommended guidelines to ensure that the acquisition of information technology capital assets is performed in compliance with DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, dated 7-28-06. Canceled by DOE N 251.105.

  19. Environmental of Forestry Projects

    E-Print Network [OSTI]

    Environmental Impact Assessment of Forestry Projects #12;EnvironmentalImpactAssessment 2 Flow chart Details of the Environmental Statement publicised for comment FC considers ES and any comments received FC the issues of concern that need to be covered in the Environmental Statement (ES). The Environmental

  20. PROJECT PROPOSAL FPGA PAINT

    E-Print Network [OSTI]

    PROJECT PROPOSAL FPGA PAINT Design of Embedded Systems, Advanced Course Faculty to develop a paint program on Digilent Nexys2 FPGA board. We expect it to be a platform of painting on a plain space or painting an existing picture outline with color. There would be options for changing

  1. Baytown Cogeneration Project 

    E-Print Network [OSTI]

    Lorenz, M. G.

    2007-01-01

    The Baytown Cogeneration Project installed a GE 7FA gas turbine generator that produces 160 MW of electricity and 560-klB/hr of superheated 1500-psig steam. All of the steam and electricity are consumed by the ExxonMobil Refinery & Chemical Plant...

  2. Accounting Projects Company Description

    E-Print Network [OSTI]

    Dahl, David B.

    and international tax work for individuals, closely held companies, family offices and clients expecting a liquidityAccounting Projects Company Description: CPA firm performing accounting services, bookkeeping. Company Description: a full service CPA firm headquartered in the San Francisco Bay Area. Nationally

  3. Project Title: Residential wind turbine design Project Description: This project aims to

    E-Print Network [OSTI]

    Muradoglu, Metin

    that wind is expected to come. Therefore it may be a good idea to consider a vertical-axis wind turbine of the conventional wind turbines use horizontal- axis configuration (see Fig. 1) and is aligned with the directionPROJECT 1: Project Title: Residential wind turbine design Project Description: This project aims

  4. Reducing Poverty Risk in Developing Countries Project No. Project Title Project Leader

    E-Print Network [OSTI]

    Krivobokova, Tatyana

    1 Reducing Poverty Risk in Developing Countries Project No. Project Title Project Leader 1 Dynamic). At the same time, there will be substantial collaboration between the projects to develop this common research in developing countries Lay 5 Informal risk sharing networks as an strategy to reduce poverty risk Ibanez

  5. Ceramic Technology Project

    SciTech Connect (OSTI)

    Not Available

    1992-03-01

    The Ceramic Technology Project was developed by the USDOE Office of Transportation Systems (OTS) in Conservation and Renewable Energy. This project, part of the OTS's Materials Development Program, was developed to meet the ceramic technology requirements of the OTS's automotive technology programs. Significant accomplishments in fabricating ceramic components for the USDOE and NASA advanced heat engine programs have provided evidence that the operation of ceramic parts in high-temperature engine environments is feasible. These programs have also demonstrated that additional research is needed in materials and processing development, design methodology, and data base and life prediction before industry will have a sufficient technology base from which to produce reliable cost-effective ceramic engine components commercially. A five-year project plan was developed with extensive input from private industry. In July 1990 the original plan was updated through the estimated completion of development in 1993. The objective is to develop the industrial technology base required for reliable ceramics for application in advanced automotive heat engines. The project approach includes determining the mechanisms controlling reliability, improving processes for fabricating existing ceramics, developing new materials with increased reliability, and testing these materials in simulated engine environments to confirm reliability. Although this is a generic materials project, the focus is on the structural ceramics for advanced gas turbine and diesel engines, ceramic bearings and attachments, and ceramic coatings for thermal barrier and wear applications in these engines. To facilitate the rapid transfer of this technology to US industry, the major portion of the work is being done in the ceramic industry, with technological support from government laboratories, other industrial laboratories, and universities.

  6. Economic Development Impacts of Community Wind Projects. A Review and Empirical Evaluation

    SciTech Connect (OSTI)

    Lantz, E.; Tegen, S.

    2009-04-01

    "Community wind" refers to a class of wind energy ownership structures. The extent of local ownership may range from a small minority share to full ownership by persons in the immediate area surrounding the wind project site. Potential project owners include local farmers, businesses, Native American tribes, universities, cooperatives, or any other local entity seeking to invest in wind energy. The opposite of community wind is an "absentee" project, in which ownership is completely removed from the state and community surrounding the facility. Thus, there is little or no ongoing direct financial benefit to state and local populations aside from salaries for local repair technicians, local property tax payments, and land lease payments. In recent years, the community wind sector has been inhibited by manufacturers' preference for larger turbine orders. This often puts smaller community wind developers and projects at a competitive disadvantage. However, state policies specifically supporting community wind may become a more influential market factor as turbines are now more readily available given manufacturer ramp-ups and the slow-down in the industry that has accompanied the recent economic and financial crises. This report examines existing literature to provide an overview of economic impacts resulting from community wind projects, compares results, and explains variability.

  7. Homologous recombination and non-homologous end-joining repair pathways in bovine embryos with different developmental competence

    SciTech Connect (OSTI)

    Henrique Barreta, Marcos; Laboratorio de Biotecnologia e Reproducao Animal-BioRep, Universidade Federal de Santa Maria, Santa Maria, RS ; Garziera Gasperin, Bernardo; Braga Rissi, Vitor; Cesaro, Matheus Pedrotti de; Ferreira, Rogerio; Oliveira, Joao Francisco de; Goncalves, Paulo Bayard Dias; Bordignon, Vilceu

    2012-10-01

    This study investigated the expression of genes controlling homologous recombination (HR), and non-homologous end-joining (NHEJ) DNA-repair pathways in bovine embryos of different developmental potential. It also evaluated whether bovine embryos can respond to DNA double-strand breaks (DSBs) induced with ultraviolet irradiation by regulating expression of genes involved in HR and NHEJ repair pathways. Embryos with high, intermediate or low developmental competence were selected based on the cleavage time after in vitro insemination and were removed from in vitro culture before (36 h), during (72 h) and after (96 h) the expected period of embryonic genome activation. All studied genes were expressed before, during and after the genome activation period regardless the developmental competence of the embryos. Higher mRNA expression of 53BP1 and RAD52 was found before genome activation in embryos with low developmental competence. Expression of 53BP1, RAD51 and KU70 was downregulated at 72 h and upregulated at 168 h post-insemination in response to DSBs induced by ultraviolet irradiation. In conclusion, important genes controlling HR and NHEJ DNA-repair pathways are expressed in bovine embryos, however genes participating in these pathways are only regulated after the period of embryo genome activation in response to ultraviolet-induced DSBs.

  8. Post local forms of repair: The (extended) situation of virtualised technical support 

    E-Print Network [OSTI]

    Pollock, N.; Williams, R.; D'Adderio, Luciana; Grimm, C.

    2009-10-01

    We address the seemingly implausible project of moving the technical support of complex organisational technologies online. We say ‘implausible’ because from the point of view of micro-sociological analysis and the influential work of Julian Orr...

  9. Evaluating indoor exposure modeling alternatives for LCA: A case study in the vehicle repair industry

    SciTech Connect (OSTI)

    Demou, Evangelia; Hellweg, Stefanie; Wilson, Michael P.; Hammond, S. Katharine; McKone, Thomas E.

    2009-05-01

    We evaluated three exposure models with data obtained from measurements among workers who use"aerosol" solvent products in the vehicle repair industry and with field experiments using these products to simulate the same exposure conditions. The three exposure models were the: 1) homogeneously-mixed-one-box model, 2) multi-zone model, and 3) eddy-diffusion model. Temporally differentiated real-time breathing zone volatile organic compound (VOC) concentration measurements, integrated far-field area samples, and simulated experiments were used in estimating parameters, such as emission rates, diffusivity, and near-field dimensions. We assessed differences in model input requirements and their efficacy for predictive modeling. The One-box model was not able to resemble the temporal profile of exposure concentrations, but it performed well concerning time-weighted exposure over extended time periods. However, this model required an adjustment for spatial concentration gradients. Multi-zone models and diffusion-models may solve this problem. However, we found that the reliable use of both these models requires extensive field data to appropriately define pivotal parameters such as diffusivity or near-field dimensions. We conclude that it is difficult to apply these models for predicting VOC exposures in the workplace. However, for comparative exposure scenarios in life-cycle assessment they may be useful.

  10. Human HLTF mediates postreplication repair by its HIRAN domain-dependent replication fork remodelling

    DOE Public Access Gateway for Energy & Science Beta (PAGES Beta)

    Achar, Yathish Jagadheesh; Balogh, David; Neculai, Dante; Juhasz, Szilvia; Morocz, Monika; Gali, Himabindu; Dhe-Paganon, Sirano; Venclovas, ?eslovas; Haracska, Lajos

    2015-09-08

    Defects in the ability to respond properly to an unrepaired DNA lesion blocking replication promote genomic instability and cancer. Human HLTF, implicated in error-free replication of damaged DNA and tumour suppression, exhibits a HIRAN domain, a RING domain, and a SWI/SNF domain facilitating DNA-binding, PCNA-polyubiquitin-ligase, and dsDNA-translocase activities, respectively. Here, we investigate the mechanism of HLTF action with emphasis on its HIRAN domain. We found that in cells HLTF promotes the filling-in of gaps left opposite damaged DNA during replication, and this postreplication repair function depends on its HIRAN domain. Our biochemical assays show that HIRAN domain mutant HLTF proteinsmore »retain their ubiquitin ligase, ATPase and dsDNA translocase activities but are impaired in binding to a model replication fork. These data and our structural study indicate that the HIRAN domain recruits HLTF to a stalled replication fork, and it also provides the direction for the movement of the dsDNA translocase motor domain for fork reversal. We suggest functional similarities between the HIRAN, the OB, the HARP2, and other domains found in certain motor proteins, which may explain why only a subset of DNA translocases can carry out fork reversal.« less

  11. The introduction of heat recoverable couplings to ship repair and maintenance

    SciTech Connect (OSTI)

    Liberatore, D.J.; Backerville, J.E.

    1982-12-01

    Although Heat Recoverable Couplings (HRCs), used to join pipe, may be labeled innovative ''state-of-the-art'' technology for U.S. Naval Shipyards, they have been in use in foreign ships and high technology industries for over a decade. HRCs provide a permanent leak-proof pipe joint in specified applications without the use of high temperature and the inherent hazards of an open flame. Manufactured from NITINOL, a nickel-titanium alloy developed by the U.S. Navy, the couplings exhibit a ''shape memory'' characteristic. That is, they return (shrink) to a specified shape (pipe diameter) thus forming a mechanical seal when the expanded coupling is removed from a cryogenic environment and warmed above approximately-130/sup 0/C. This paper provides background information into the development of NITINOL, technical explanation of shape memory metallurgy, and a summary of results, with specific examples, describing the trial use of HRCs at Pearl Harbor and Norfolk Naval Shipyards. Limited return cost data and recommendations for future use are presented. Then, using the HRC Program as a basis, the Authors discuss the conservative nature of the ship repair and maintenance environment. This environment, in the Authors' opinion, couples with complex contractual constraints and requirements which serve to restrict the introduction of new ideas. An analogy is made to Russian tenacity of recent years which promotes ''exploring and doing'' while we in the U.S. Navy are frequently content to study.

  12. California Hydrogen Infrastructure Project

    SciTech Connect (OSTI)

    Edward C. Heydorn

    2013-03-12

    Air Products and Chemicals, Inc. has completed a comprehensive, multiyear project to demonstrate a hydrogen infrastructure in California. The specific primary objective of the project was to demonstrate a model of a ���¢��������real-world���¢������� retail hydrogen infrastructure and acquire sufficient data within the project to assess the feasibility of achieving the nation���¢��������s hydrogen infrastructure goals. The project helped to advance hydrogen station technology, including the vehicle-to-station fueling interface, through consumer experiences and feedback. By encompassing a variety of fuel cell vehicles, customer profiles and fueling experiences, this project was able to obtain a complete portrait of real market needs. The project also opened its stations to other qualified vehicle providers at the appropriate time to promote widespread use and gain even broader public understanding of a hydrogen infrastructure. The project engaged major energy companies to provide a fueling experience similar to traditional gasoline station sites to foster public acceptance of hydrogen. Work over the course of the project was focused in multiple areas. With respect to the equipment needed, technical design specifications (including both safety and operational considerations) were written, reviewed, and finalized. After finalizing individual equipment designs, complete station designs were started including process flow diagrams and systems safety reviews. Material quotes were obtained, and in some cases, depending on the project status and the lead time, equipment was placed on order and fabrication began. Consideration was given for expected vehicle usage and station capacity, standard features needed, and the ability to upgrade the station at a later date. In parallel with work on the equipment, discussions were started with various vehicle manufacturers to identify vehicle demand (short- and long-term needs). Discussions included identifying potential areas most suited for hydrogen fueling stations with a focus on safe, convenient, fast-fills. These potential areas were then compared to and overlaid with suitable sites from various energy companies and other potential station operators. Work continues to match vehicle needs with suitable fueling station locations. Once a specific site was identified, the necessary agreements could be completed with the station operator and expected station users. Detailed work could then begin on the site drawings, permits, safety procedures and training needs. Permanent stations were successfully installed in Irvine (delivered liquid hydrogen), Torrance (delivered pipeline hydrogen) and Fountain Valley (renewable hydrogen from anaerobic digester gas). Mobile fueling stations were also deployed to meet short-term fueling needs in Long Beach and Placerville. Once these stations were brought online, infrastructure data was collected and reported to DOE using Air Products���¢�������� Enterprise Remote Access Monitoring system. Feedback from station operators was incorporated to improve the station user���¢��������s fueling experience.

  13. UWA Renewable Energy Vehicle Project Available Projects: 2nd

    E-Print Network [OSTI]

    1 UWA Renewable Energy Vehicle Project Available Projects: 2nd Semester 2005 Time commitment values materials and distribute 4) Educate team on marketing strategies 5) Contact potential sponsors, media

  14. NSTX Upgrade Project Execution Plan NSTX Upgrade Project

    E-Print Network [OSTI]

    Princeton Plasma Physics Laboratory

    10/12/2012 Update to WBS Level 2 Threshold (top of page 20), Change DOE Federal Project Director ..............................................................................................................................1 1.2.1 DOE-approved project documents:..............................................................................................1 1.2.2 DOE certified institutional systems or plans

  15. Project Reports for San Carlos Apache Tribe- 2012 Project

    Broader source: Energy.gov [DOE]

    Under this project, the San Carlos Apache Tribe will study the feasibility of solar energy projects within the reservation with the potential to generate a minimum of 1 megawatt (MW).

  16. Evaluation of Technology Risk in Project Cogeneration Project Returns 

    E-Print Network [OSTI]

    Thoennes, C. M.

    1985-01-01

    The economic returns of a cogeneration project are a direct function of the project margin, that is, the difference between revenues and expenses. Revenues and expenses, of course, are made up of both variable and fixed components. The revenues...

  17. CX-008597: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Alder Stream Wind Project Feasibility Project CX(s) Applied: A9, B3.1 Date: 07/03/2012 Location(s): Maine Offices(s): Golden Field Office

  18. Nucla CFB Demonstration Project

    SciTech Connect (OSTI)

    Not Available

    1990-12-01

    This report documents Colorado-Ute Electric Association's Nucla Circulating Atmospheric Fluidized-Bed Combustion (AFBC) demonstration project. It describes the plant equipment and system design for the first US utility-size circulating AFBC boiler and its support systems. Included are equipment and system descriptions, design/background information and appendices with an equipment list and selected information plus process flow and instrumentation drawings. The purpose of this report is to share the information gathered during the Nucla circulating AFBC demonstration project and present it so that the general public can evaluate the technical feasibility and cost effectiveness of replacing pulverized or stoker-fired boiler units with circulating fluidized-bed boiler units. (VC)

  19. Healy Clean Coal Project

    SciTech Connect (OSTI)

    None

    1997-12-31

    The Healy Clean Coal Project, selected by the U.S. Department of Energy under Round 111 of the Clean Coal Technology Program, has been constructed and is currently in the Phase 111 Demonstration Testing. The project is owned and financed by the Alaska Industrial Development and Export Authority (AIDEA), and is cofunded by the U.S. Department of Energy. Construction was 100% completed in mid-November of 1997, with coal firing trials starting in early 1998. Demonstration testing and reporting of the results will take place in 1998, followed by commercial operation of the facility. The emission levels of nitrogen oxides (NOx), sulfur dioxide (S02), and particulate from this 50-megawatt plant are expected to be significantly lower than current standards.

  20. The Nautilus project

    SciTech Connect (OSTI)

    Salis, J. de

    1996-02-01

    The objective of the Nautilus project is to design, build, and evaluate a subsea multiphase electrical booster system to demonstrate its operability and reliability. The subsea station will reflect the integration of existing, tested, and recently developed equipment. The integration of various technologies, control, and maintenance in a subsea environment represents the challenging aspect of the project. Boosted by a helicoaxial pump, the produced multiphase effluent receives enough energy to reach either a host platform or the shore where the classical separation and treatment operations are performed. For deep offshore developments, the concept should induce a lower investment than alternative solutions. The concept should also give access to marginal fields, currently undeveloped for economical reasons, with the benefit of maximizing existing infrastructure. Furthermore, where sea traffic or environment concerns may limit offshore surface developments, Nautilus should demonstrate itself as an economical alternative.

  1. Debt collection project report

    SciTech Connect (OSTI)

    Not Available

    1980-05-01

    In October 1979 the Office of Management and Budget initiated a review of debt collection within the Federal Government. A DOE Debt Collection Project Team was established, and seven activites were selected for review. These were Albuquerque Operations Office; Bonneville Power Administration; Chicago Operations and Regional Office; Naval Petroleum Reserves, California; Oak Ridge Operations Office; Washington Financial Services Division; and Western Area Power Administration. The team visited each of these activities to collect data on the size, age, and types of receivables managed and procedures for billing, aging, and handling overdue accounts. Various deficiencies were found to exist at several of the DOE entities that are not consistent with good management practices in the performance of their debt collection functions. Also, the Debt Collection Project Team identified a wide variation in the procedures followed by DOE activities in the management of accounts receivable, and a wide variation in the effectiveness of the debt management functions. 1 figure, 17 tables. (RWR)

  2. Forecasting potential project risks through leading indicators to project outcome 

    E-Print Network [OSTI]

    Choi, Ji Won

    2007-09-17

    for the degree of MASTER OF SCIENCE May 2007 Major Subject: Civil Engineering FORECASTING POTENTIAL PROJECT RISKS THROUGH LEADING INDICATORS TO PROJECT OUTCOME A Thesis by JI WON CHOI... Guikema Head of Department, David Rosowsky May 2007 Major Subject: Civil Engineering iii ABSTRACT Forecasting Potential Project Risks through Leading Indicators to Project Outcome. (May 2007) Ji Won Choi, B.S., Han-Yang University...

  3. Repair of radiation-induced heat-labile sites is independent of DNA-PKcs, XRCC1 or PARP

    SciTech Connect (OSTI)

    Stenerlöw, Bo; Karlsson, Karin H.; Radulescu, Irina; Rydberg, Bjorn; Stenerlow, Bo

    2008-04-29

    Ionizing radiation induces a variety of different DNA lesions: in addition to the most critical DNA damage, the DSB, numerous base alterations, SSBs and other modifications of the DNA double-helix are formed. When several non-DSB lesions are clustered within a short distance along DNA, or close to a DSB, they may interfere with the repair of DSBs and affect the measurement of DSB induction and repair. We have previously shown that a substantial fraction of DSBs measured by pulsed-field gel electrophoresis (PFGE) are in fact due to heat-labile sites (HLS) within clustered lesions, thus reflecting an artifact of preparation of genomic DNA at elevated temperature. To further characterize the influence of HLS on DSB induction and repair, four human cell lines (GM5758, GM7166, M059K, U-1810) with apparently normal DSB rejoining were tested for bi-phasic rejoining after gamma irradiation. When heat-released DSBs were excluded from the measurements the fraction of fast rejoining decreased to less than 50% of the total. However, neither the half-times of the fast (t{sub 1/2} = 7-8 min) or slow (t{sub 1/2} = 2.5 h) DSB rejoining were changed significantly. At t=0 the heat-released DSBs accounted for almost 40% of the DSBs, corresponding to 10 extra DSB/cell/Gy in the initial DSB yield. These heat-released DSBs were repaired within 60-90 min in all tested cells, including M059K cells treated with wortmannin or DNA-PKcs defect M059J cells. Furthermore, cells lacking XRCC1 or Poly(ADP-ribose) polymerase-1 (PARP-1) rejoined both total DSBs and heat-released DSBs similar to normal cells. In summary, the presence of heat-labile sites have a substantial impact on DSB induction yields and DSB rejoining rates measured by pulsed-field gel electrophoresis, and HLS repair is independent of DNA-PKcs, XRCC1 and PARP.

  4. Baytown Energy Project 

    E-Print Network [OSTI]

    Porter, J.

    2006-01-01

    Mobil's Baytown Chemical Plant, the Baytown Energy Project (BEP) utilized this planning strategy to redeploy assets by changing the fractionation configuration of the plant. In the aromatics recovery plant, aromatics (benzene, toluene and xylenes... prefractionator followed by a set of integrated towers to separate the ternary product mixture of benzene toluene and xylenes from a toluene disproportionation unit. The towers also fractionated a concentrated benzene and toluene sidestream from the primary...

  5. Advanced Biomass Gasification Projects

    SciTech Connect (OSTI)

    Not Available

    1997-08-01

    DOE has a major initiative under way to demonstrate two high-efficiency gasification systems for converting biomass into electricity. As this fact sheet explains, the Biomass Power Program is cost-sharing two scale-up projects with industry in Hawaii and Vermont that, if successful, will provide substantial market pull for U.S. biomass technologies, and provide a significant market edge over competing foreign technologies.

  6. Popeye Project: Subsea system

    SciTech Connect (OSTI)

    Ritter, P.B.; Langner, C.G.; Sgouros, G.E.; Saucier, B.J.; Voss, R.K.

    1996-12-31

    The subsea system installed for Shell Offshore Inc. (SOI) Popeye Project represents an advancement in deep water subsea technology. It is a diverless, guidelineless, 10,000 psi cluster manifold concept, the first of its kind. The cluster concept was selected in large part based on SOI`s deep water experience and anticipated future subsea development needs. This paper describes how the innovative Popeye subsea system was selected, designed, tested, and successfully installed.

  7. Popeye project: Subsea system

    SciTech Connect (OSTI)

    Ritter, P.B.; Sgouros, G.E.; Langner, C.G.; Saucier, B.J.; Voss, R.K.

    1997-12-01

    The subsea system installed for the Shell Offshore Inc. (SOI) Popeye project represents an advance in deepwater subsea technology. It is a diverless, guidelineless, 10,000-psi cluster-manifold concept, the first of its kind. The cluster concept was selected in large part based on SOI`s deepwater experience and anticipated future subsea-development needs. This paper describes how the innovative Popeye subsea system was selected, designed, tested, and successfully installed.

  8. BETO Active Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:FinancingPetroleum Based Fuels Research atDepartmentAuditsDepartmentj.BETO Active Project

  9. Desert Peak EGS Project

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious Rank EERE:FinancingPetroleum Based| Department8, 20153Danielthrough theKDesert Peak EGS Project DOE Award:

  10. Project Submission Template

    Energy Savers [EERE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on DeliciousMathematicsEnergyInterested PartiesBuildingBudget | DepartmentLogisticalProjectDepartmentCooperation

  11. The Human Genome Diversity Project

    SciTech Connect (OSTI)

    Cavalli-Sforza, L.

    1994-12-31

    The Human Genome Diversity Project (HGD Project) is an international anthropology project that seeks to study the genetic richness of the entire human species. This kind of genetic information can add a unique thread to the tapestry knowledge of humanity. Culture, environment, history, and other factors are often more important, but humanity`s genetic heritage, when analyzed with recent technology, brings another type of evidence for understanding species` past and present. The Project will deepen the understanding of this genetic richness and show both humanity`s diversity and its deep and underlying unity. The HGD Project is still largely in its planning stages, seeking the best ways to reach its goals. The continuing discussions of the Project, throughout the world, should improve the plans for the Project and their implementation. The Project is as global as humanity itself; its implementation will require the kinds of partnerships among different nations and cultures that make the involvement of UNESCO and other international organizations particularly appropriate. The author will briefly discuss the Project`s history, describe the Project, set out the core principles of the Project, and demonstrate how the Project will help combat the scourge of racism.

  12. The IPHI Project

    SciTech Connect (OSTI)

    Ferdinand, Robin; Beauvais, Pierre-Yves

    2005-06-08

    High Power Proton Accelerators (HPPAs) are studied for several projects based on high-flux neutron sources driven by proton or deuteron beams. Since the front end is considered as the most critical part of such accelerators, the two French national research agencies CEA and CNRS decided to collaborate in 1997 to study and build a High-Intensity Proton Injector (IPHI). The main objective of this project is to master the complex technologies used and the concepts of manufacturing and controlling the HPPAs. Recently, a collaboration agreement was signed with CERN and led to some evolutions in the design and in the schedule. The IPHI design current was maintained at 100 mA in Continuous Wave mode. This choice should allow to produce a high reliability beam at reduced intensity (typically 30 mA) tending to fulfill the Accelerator Driven System requirements. The output energy of the Radio Frequency Quadrupole (RFQ), was reduced from 5 to 3 MeV, allowing then the adjunction and the test, in pulsed operation of a chopper line developed by CERN for the Superconducting Proton Linac (SPL). In a final step, the IPHI RFQ and the chopper line should become parts of the SPL injector. In this paper, the IPHI project and the recent evolutions are reported together with the construction and operation schedule.

  13. Project Management Plan

    SciTech Connect (OSTI)

    Not Available

    1988-01-01

    The mission of the Uranium Mill Tailings Remedial Action (UMTRA) Project is explicitly stated and directed in the Uranium Mill Tailings Radiation Control Act of 1978, Public Law 95-604, 42 USC 7901 (hereinafter referred to as the Act''). Title I of the Act authorizes the Department of Energy (DOE) to undertake remedial actions at 24 designated inactive uranium processing sites and associated vicinity properties containing uranium mill tailings and other residual radioactive materials derived from the processing sites. The Act, amended in January 1983, by Public Law 97-415, also authorizes DOE to perform remedial actions at vicinity properties in Edgemont, South Dakota. Cleanup of the Edgemont processing site is the responsibility of the Tennessee Valley Authority. This document describes the plan, organization, system, and methodologies used to manage the design, construction, and other activities required to clean up the designated sites and associated vicinity properties in accordance with the Act. The plan describes the objectives of the UMTRA Project, defines participants' roles and responsibilities, outlines the technical approach for accomplishing the objectives, and describes the planning and managerial controls to be used in integrating and performing the Project mission. 21 figs., 21 tabs.

  14. Final Project Report

    SciTech Connect (OSTI)

    Bogucz, E A

    2010-12-13

    This project pursued innovations to improve energy efficiency and indoor environmental quality (IEQ) in commercial and residential buildings. For commercial buildings, the project developed a testbed for “intelligent nested environmental systems technologies (iNEST),” which monitor and control energy flows and IEQ across a cascade of spaces from individuals’ desktops to office suites to floors to whole buildings. An iNEST testbed was constructed at Syracuse University and was used to assess the use of devices such as personal badges and CO2 sensors to study how reduced energy use and improved IEQ could be achieved. For residential buildings, resources were targeted in support of DoE’s Builders Challenge Program and to recruit Syracuse, NY builders. Three homes in Syracuse’s Near Westside neighborhood were also registered under the program by Syracuse University team, with an additional home registered by one of the builders. Findings from the work at the iNEST testbed facility, and results from other related projects were disseminated through Syracuse Center of Excellence in Environmental and Energy Systems (SyracuseCoE) 2008 Annual Symposium, the 9th International Healthy Buildings 2009 Conference & Exhibition, and through SyracuseCoE’s website and eNewsletters to inform the broader community of researchers, designers and builders. These public communication activities helped enhance the understanding of high performance buildings and facilitate further market acceptance.

  15. Final project report

    SciTech Connect (OSTI)

    Nitin S. Baliga and Leroy Hood

    2008-11-12

    The proposed overarching goal for this project was the following: Data integration, simulation and visualization will facilitate metabolic and regulatory network prediction, exploration, and formulation of hypotheses. We stated three specific aims to achieve the overarching goal of this project: (1) Integration of multiple levels of information such as mRNA and protein levels, predicted protein-protein interactions/associations and gene function will enable construction of models describing environmental response and dynamic behavior. (2) Flexible tools for network inference will accelerate our understanding of biological systems. (3) Flexible exploration and queries of model hypotheses will provide focus and reveal novel dependencies. The underlying philosophy of these proposed aims is that an iterative cycle of experiments, experimental design, and verification will lead to a comprehensive and predictive model that will shed light on systems level mechanisms involved in responses elicited by living systems upon sensing a change in their environment. In the previous years report we demonstrated considerable progress in development of data standards, regulatory network inference and data visualization and exploration. We are pleased to report that several manuscripts describing these procedures have been published in top international peer reviewed journals including Genome Biology, PNAS, and Cell. The abstracts of these manuscripts are given and they summarize our accomplishments in this project.

  16. NREL Smart Grid Projects

    SciTech Connect (OSTI)

    Hambrick, J.

    2012-01-01

    Although implementing Smart Grid projects at the distribution level provides many advantages and opportunities for advanced operation and control, a number of significant challenges must be overcome to maintain the high level of safety and reliability that the modern grid must provide. For example, while distributed generation (DG) promises to provide opportunities to increase reliability and efficiency and may provide grid support services such as volt/var control, the presence of DG can impact distribution operation and protection schemes. Additionally, the intermittent nature of many DG energy sources such as photovoltaics (PV) can present a number of challenges to voltage regulation, etc. This presentation provides an overview a number of Smart Grid projects being performed by the National Renewable Energy Laboratory (NREL) along with utility, industry, and academic partners. These projects include modeling and analysis of high penetration PV scenarios (with and without energy storage), development and testing of interconnection and microgrid equipment, as well as the development and implementation of advanced instrumentation and data acquisition used to analyze the impacts of intermittent renewable resources. Additionally, standards development associated with DG interconnection and analysis as well as Smart Grid interoperability will be discussed.

  17. Guest Project: Personal Information Title of the Project

    E-Print Network [OSTI]

    ! ! Guest Project: Personal Information ! ! Title of the Project: ! ! Project Coordinator: ! Name? ! 1. 2. 3... #12;! Rules and Acceptance: ! The primary purpose of the ICTP SciFabLab is to support, models, and codes developed within the ICTP Scientific FabLab as open source / open hardware

  18. Financing Energy Projects in Dow 

    E-Print Network [OSTI]

    Dingwall, D. C.

    1984-01-01

    in size, and authorized and financed as a part of Dow's regular capital program. Capital projects relating to the more efficient generation of energy generally refer to DOW'S large Gulf Coast combined cycle cogeneration projects, most of which came...

  19. Degree project in Communication Systems

    E-Print Network [OSTI]

    Maguire Jr., Gerald Q.

    cloud. This thesis project designed, implemented, and evaluated the use of open shortest path firstDegree project in Communication Systems Second level, 30.0 HEC Stockholm, Sweden A M I R R O O Z B

  20. Environmental Management (EM) Cleanup Projects

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-09-24

    The guide supports DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, and provides guidance on environmental management cleanup projects. Canceled by DOE N 251.105.

  1. Risk Management In Major Projects 

    E-Print Network [OSTI]

    Baker, Scott William

    The integration of risk management in major projects within the construction and oil and gas industries has never been more significant especially as these projects are becoming larger and more complex. The increased ...

  2. Geothermal Outreach and Project Financing

    SciTech Connect (OSTI)

    Elizabeth Battocletti

    2006-04-06

    The ?Geothermal Outreach and Project Financing? project substantially added to the understanding of geothermal resources, technology, and small business development by both the general public as well as those in the geothermal community.

  3. Smart Grid Demonstration Project

    SciTech Connect (OSTI)

    Miller, Craig; Carroll, Paul; Bell, Abigail

    2015-03-11

    The National Rural Electric Cooperative Association (NRECA) organized the NRECA-U.S. Department of Energy (DOE) Smart Grid Demonstration Project (DE-OE0000222) to install and study a broad range of advanced smart grid technologies in a demonstration that spanned 23 electric cooperatives in 12 states. More than 205,444 pieces of electronic equipment and more than 100,000 minor items (bracket, labels, mounting hardware, fiber optic cable, etc.) were installed to upgrade and enhance the efficiency, reliability, and resiliency of the power networks at the participating co-ops. The objective of this project was to build a path for other electric utilities, and particularly electrical cooperatives, to adopt emerging smart grid technology when it can improve utility operations, thus advancing the co-ops’ familiarity and comfort with such technology. Specifically, the project executed multiple subprojects employing a range of emerging smart grid technologies to test their cost-effectiveness and, where the technology demonstrated value, provided case studies that will enable other electric utilities—particularly electric cooperatives— to use these technologies. NRECA structured the project according to the following three areas: Demonstration of smart grid technology; Advancement of standards to enable the interoperability of components; and Improvement of grid cyber security. We termed these three areas Technology Deployment Study, Interoperability, and Cyber Security. Although the deployment of technology and studying the demonstration projects at coops accounted for the largest portion of the project budget by far, we see our accomplishments in each of the areas as critical to advancing the smart grid. All project deliverables have been published. Technology Deployment Study: The deliverable was a set of 11 single-topic technical reports in areas related to the listed technologies. Each of these reports has already been submitted to DOE, distributed to co-ops, and posted for universal access at www.nreca.coop/smartgrid. This research is available for widespread distribution to both cooperative members and non-members. These reports are listed in Table 1.2. Interoperability: The deliverable in this area was the advancement of the MultiSpeak™ interoperability standard from version 4.0 to version 5.0, and improvement in the MultiSpeak™ documentation to include more than 100 use cases. This deliverable substantially expanded the scope and usability of MultiSpeak, ™ the most widely deployed utility interoperability standard, now in use by more than 900 utilities. MultiSpeak™ documentation can be accessed only at www.multispeak.org. Cyber Security: NRECA’s starting point was to develop cyber security tools that incorporated succinct guidance on best practices. The deliverables were: cyber security extensions to MultiSpeak,™ which allow more security message exchanges; a Guide to Developing a Cyber Security and Risk Mitigation Plan; a Cyber Security Risk Mitigation Checklist; a Cyber Security Plan Template that co-ops can use to create their own cyber security plans; and Security Questions for Smart Grid Vendors.

  4. Why Cogeneration Development Projects Fail 

    E-Print Network [OSTI]

    Greenwood, R. W.

    1987-01-01

    ENERATION DEVElDHmNT PROJECTS FAIL RALPH w. GRBBtMX>D Regional Manager Bbasco Services Incorporated Houston, Texas ABSTRACT Cogeneration projects that are organized by developers fail to reach fruition for reasons other than the basic economical... here to discuss those additional problems unique to small projects. A developnent project is defined as one where a third party, the developer, provides preliminary econanic options, licensing, business structure, financing, detailed engineering...

  5. Degree project in Communication Systems

    E-Print Network [OSTI]

    Maguire Jr., Gerald Q.

    Degree project in Communication Systems Second level, 30.0 HEC Stockholm, Sweden G U O J U N W A N Abstract The goal of this thesis project is to improve industrial system testing efficiency. The thesis. The work load for testers can be decreased and more projects could be carried out in parallel

  6. Degree project in Communication Systems

    E-Print Network [OSTI]

    Maguire Jr., Gerald Q.

    and competitive activities which in this thesis project were evaluated in a educational process contextDegree project in Communication Systems Second level, 30.0 HEC Stockholm, Sweden F R A N C I S C O interaction in areas, such as health care, computer games, and robotics. Although many research projects have

  7. Degree project in Communication Systems

    E-Print Network [OSTI]

    Maguire Jr., Gerald Q.

    Degree project in Communication Systems Second level, 30.0 HEC Stockholm, Sweden A L I S A R R A F(KTH) Kista, Stockholm, Sweden. #12;#12;Abstract Today, the number of software projects having large number of tools that have evolved to improve the quality of development in such projects. In addition, building

  8. Degree project in Communication Systems

    E-Print Network [OSTI]

    Maguire Jr., Gerald Q.

    Degree project in Communication Systems Second level, 30.0 HEC Stockholm, Sweden S A A D A H M E D, Sweden #12;Abstract The project focuses on the packaging process of the smart card manufacturing industry. The idea of the project concerns how to increase production packaging efficiency by introducing a control

  9. Degree project in Communication Systems

    E-Print Network [OSTI]

    Maguire Jr., Gerald Q.

    of the main achievements of this thesis project. Evaluation of the measurement results indicates that fiberDegree project in Communication Systems Second level, 30.0 HEC Stockholm, Sweden M O Z H G A N for small cell backhaul. This thesis project investigates if a small cell network's requirements can

  10. The Piazza Project Presented by

    E-Print Network [OSTI]

    Ives, Zachary G.

    The Piazza Project Presented by: Mengmeng Liu and Shirley Cohen CIS 650 #12;Agenda · Project aspects #12;Piazza Project Members AnHai Doan Oren Etzioni Steven Gribble Zack Ives Alon Halevy Jayant (PDMS): · n mediated peer schemas as few as (n - 1) mappings between them ­ evaluated transitively · m

  11. Degree project in Communication Systems

    E-Print Network [OSTI]

    Maguire Jr., Gerald Q.

    by a review of related work. The overall project's goal is to create and evaluate an authorization schemaDegree project in Communication Systems Second level, 30.0 HEC Stockholm, Sweden A L E X I S M A R #12;#12;i Abstract This master's thesis project began at the Karolinska University Hospital

  12. Addendum to Fake Projective Planes

    E-Print Network [OSTI]

    Yeung, Sai-Kee

    ingenious group theoretic computations that the twenty eight classes of fake projective planes altogether- damental group of eight of the one hundred fake projective planes do not admit an embedding into SU(2, 1. In [1] we proved that if the fundamental group of a fake projective plane is an arithmetic subgroup

  13. Office: ITO PE/Project

    E-Print Network [OSTI]

    Mills, Kevin

    Mgr.: Mills/Swinson PAD No.: Smart Spaces Moving Through Smart Spaces "city-wide appliances" "in1 DARPA Office: ITO PE/Project: Pgm No.: Pgm Mgr.: Mills/Swinson PAD No.: Smart Spaces Personal Information Projection · Develop techniques for projecting personal information from cyberspace into smart

  14. Indian River Hydroelectric Project Grant

    SciTech Connect (OSTI)

    Rebecca Garrett

    2005-04-29

    This Final Technical Report provides a concise retrospective and summary of all facets of the Sheldon Jackson College electrical Infrastructure Renovation portion of the Indian River Hydroelectric Project Grant of the City and Borough of Sitka, Alaska. The Project Overview describes the origins of the project, the original conditions that provided the impetus for the grant funding, how the grant amendment was developed, the conceptual design development, and the actual parameters of the final project as it went out to bid. The Project Overview also describes the ''before and after'' conditions of the project. The Objectives division of this Final Technical Report describes the amendment-funded goals of the project. It also describes the milestones of project development and implementation, as well as, the rationale behind the milestone array. The Description of Activities Performed division of this report provides an in-depth chronological analysis of progressive project implementation. Photographs will provide further illustration of particular functional aspects of the renovation project within project parameters. The Conclusions and Recommendations division of this report provides a comprehensive retrospective analysis of the project.

  15. Erythropoietin promotes oligodendrogenesis and myelin repair following lysolecithin-induced injury in spinal cord slice culture

    SciTech Connect (OSTI)

    Cho, Yun Kyung; Kim, Gunha; Park, Serah; Sim, Ju Hee; Won, You Jin [Department of Anatomy and Cell Biology, University of Ulsan College of Medicine, 388-1 Pungnap-dong, Songpa-gu, Seoul 138-736 (Korea, Republic of)] [Department of Anatomy and Cell Biology, University of Ulsan College of Medicine, 388-1 Pungnap-dong, Songpa-gu, Seoul 138-736 (Korea, Republic of); Hwang, Chang Ho [Department of Physical Medicine and Rehabilitation, Ulsan University Hospital, University of Ulsan College of Medicine, 290-3 Jeonha-dong, Dong-gu, Ulsan 682-714 (Korea, Republic of)] [Department of Physical Medicine and Rehabilitation, Ulsan University Hospital, University of Ulsan College of Medicine, 290-3 Jeonha-dong, Dong-gu, Ulsan 682-714 (Korea, Republic of); Yoo, Jong Yoon, E-mail: jyyoo@amc.seoul.kr [Department of Rehabilitation Medicine, University of Ulsan College of Medicine, 388-1 Pungnap-dong, Songpa-gu, Seoul 138-736 (Korea, Republic of); Hong, Hea Nam, E-mail: hnhong@amc.seoul.kr [Department of Anatomy and Cell Biology, University of Ulsan College of Medicine, 388-1 Pungnap-dong, Songpa-gu, Seoul 138-736 (Korea, Republic of)

    2012-01-13

    Highlights: Black-Right-Pointing-Pointer Lysolecithin-induced demyelination elevated EpoR expression in OPCs. Black-Right-Pointing-Pointer In association with elevated EpoR, EPO increased OPCs proliferation. Black-Right-Pointing-Pointer EPO enhanced the oligodendrogenesis via activation of JAK2 pathway. Black-Right-Pointing-Pointer EPO promoted myelin repair following lysolecithin-induced demyelination. -- Abstract: Here, we sought to delineate the effect of EPO on the remyelination processes using an in vitro model of demyelination. We report that lysolecithin-induced demyelination elevated EPO receptor (EpoR) expression in oligodendrocyte progenitor cells (OPCs), facilitating the beneficial effect of EPO on the formation of oligodendrocytes (oligodendrogenesis). In the absence of EPO, the resultant remyelination was insufficient, possibly due to a limiting number of oligodendrocytes rather than their progenitors, which proliferate in response to lysolecithin-induced injury. By EPO treatment, lysolecithin-induced proliferation of OPCs was accelerated and the number of myelinating oligodendrocytes and myelin recovery was increased. EPO also enhanced the differentiation of neural progenitor cells expressing EpoR at high level toward the oligodendrocyte-lineage cells through activation of cyclin E and Janus kinase 2 pathways. Induction of myelin-forming oligodendrocytes by high dose of EPO implies that EPO might be the key factor influencing the final differentiation of OPCs. Taken together, our data suggest that EPO treatment could be an effective way to enhance remyelination by promoting oligodendrogenesis in association with elevated EpoR expression in spinal cord slice culture after lysolecithin-induced demyelination.

  16. Identification of Intrinsic Order and Disorder in the DNA Repair Protein XPA

    SciTech Connect (OSTI)

    Iakoucheva, Lilia M.; Kimzey, Amy L.; Masselon, Christophe D.; Bruce, James E.; Garner, Ethan C.; Brown, Celeste J.; Dunker, A. K.; Smith, Richard D.; Ackerman, Eric J.

    2001-03-01

    The damage recognition protein XPA is required to recognize a wide variety of bulky lesions during nucleotide excision repair (NER). Independent NMR solution structures of a human XPA protein (hXPA) fragment comprising approximately one-third of the full-length protein, the minimal DNA-binding domain (MBD), revealed that ~30% of the molecule was structurally disordered. To better characterize structural features of XPA, we performed time-resolved trypsin proteolysis on active, full-length recombinant Xenopus XPA protein (xXPA). The resulting proteolytic fragments were analyzed by electrospray ionization interface coupled to a Fourier transform ion cyclotron resonance (ESI-FTICR) mass spectrometry, SDS-polyacrylamide gel electrophoresis (PAGE), and selected N-terminal sequence determinations. The mass spectrum of the full-length xXPA was consistent with the predicted sequence, 30922.02 vs. 30922.45 Da; respectively. Moreover, the mass spectrometric data allowed the assignment of multiple xXPA fragments not resolvable by SDS PAGE. Full-length xXPA exhibited aberrant mobility on SDS-PAGE with an apparent MW of ~40 kDa. To test predictions that a Glu-rich region (E70-E76) or other local regions of high charge were responsible for this ~40% aberrant SDS-PAGE mobility, the MW's of partial proteolytic fragments from ~5 to 25 kDa precisely determined by ESI-FTICR MS were correlated with their gel positions. Surprisingly, all tested partial tryptic fragments within this size-range exhibited 10-42% divergence between calculated MW and that estimated by SDS-PAGE, thus indicating the origin of anomalous migration of XPA is not localized. The computer program Predictor of Natural Disordered Regions (PONDR) correctly identified several regions of xXPA either sensitive or resistant to partial proteolysis, thereby indicating that disorder in XPA shares sequence features with other well-characterized intrinsically unstructured proteins.

  17. Large Diameter Limbs for Dilated Common Iliac Arteries in Endovascular Aneurysm Repair. Is It Safe?

    SciTech Connect (OSTI)

    Malagari, Katerina Brountzos, Elias; Gougoulakis, Alexandros; Papathanasiou, Matilda; Alexopoulou, Efthymia; Mastorakou, Renata; Kelekis, Dimitris

    2004-09-15

    In this prospective study we examined whether dilated common iliac arteries (CIAs) can provide a safe distal seal in endovascular aneurysm repair (EVAR) with the use of bifurcated stent grafts with large diameter limbs. Sixteen patients with 26 dilated CIAs with a diameter of {>=}6 mm who were offered EVAR using stent grafts with large diameter limbs were included in the study (Group A). Forty-two patients who also underwent EVAR without iliac dilatation, matched for age, sex and surgical risk were used for comparison (controls-Group B). In group A mean CIA diameter was 18.2 mm (16-28) and mean abdominal aortic aneurysm (AAA) diameter was 6.87 {+-} 1.05 cm; mean age was 77.2 {+-} 4.8 yrs (67-81). Mean follow-up was 33.6 months (2.8 yrs). CIA diameter changes and development of endoleaks were assessed by CT angiography (CTA). Overall iliac dilatation was present in 16/58 of our patients (27.6%). In 10 patients dilatation was bilateral (17.3%). Partial or complete flow to the internal iliac artery (IIA) territories was preserved in all patients post-EVAR. On follow-up, stable caliber of the dilated CIAs was observed in 21 patients (84%), enlargement of 1mm in 3 (16%), and failure of the distal attachment in 1 (6.2%). Compared to the control group there was no statistical significance in the incidence of complications. Dilated common iliac arteries provide a safe distal seal in patients who have undergone EVAR, thus obviating the need for additional endovascular procedures and sparing flow in the IIA vascular bed.

  18. Summer Student Project Report

    E-Print Network [OSTI]

    Kazan, Oguz

    2013-01-01

    My project covered a preliminary R&D phase in which an HPD tube with 163-pixels and external readout was tested. The external readout electronics were based on the existing Beetle front-end chip. The HPD performance for single-photon detection was assessed. The experimental setup made use of a fast laser light sources and an electronics readout chain specifically developed for laboratory tests. In parallel to the measurements, I improved the software which was used to make measurements and to display the data in a useful way.

  19. Project Earth Lover

    SciTech Connect (OSTI)

    Slobotski, Stephanie,

    2011-09-01

    Under this project, the Ponca Tribe of Nebraska (PTN) will conduct An Energy Options Analysis (EOA) to empower Tribal Leadership with critical information to allow them to effectively screen energy options that will further develop the Tribe's long-term strategic plan and energy vision. The PTN will also provide community workshops to enhance Tribal Members' capabilities, skills and awareness of energy efficiency and conservation technology and practices. A 90- minute workshop will be conducted at each of the 5 sites and one-hundred tribal members will receive an erergy efficiency kit.

  20. Indonesia project underway

    SciTech Connect (OSTI)

    Not Available

    1988-12-01

    Unocal Corporation has given the Indonesian Government notice of intent to proceed with a geothermal project to provide steam for a 110 megawatt electrical generating plant. The company has drilled 11 wells, and has confirmed reserves for more than 230 megawatts of generating capacity. Indonesia's state electric company, PLN, will build the power plant. Ansaldo, an Italian company, will supply equipment and manage the construction. With the notice of intent to proceed, Unocal Geothermal of Indonesia, Ltd. will begin drilling additional wells and build the field facilities necessary to provide steam to the power plant.

  1. Autostereoscopic projection viewer

    DOE Patents [OSTI]

    Toeppen, John S. (Livermore, CA)

    2006-12-19

    An autostereoscopic viewer is employed to produce aberration corrected images to simulate a virtual presence by employing pairs of projector optical components coupled with an image corrector plate and a field lens. Images are designed with magnifications and optical qualities and positioned at predetermined eyezones having controlled directional properties. The viewer's eyes are positioned in these eyezones. The size of these zones is related to the aperture of the projection lenses, the magnification produced by the Fresnel(s), and the optical properties and position of the image corrector plate.

  2. Buckman Direct Diversion Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 OutreachProductswsicloudwsiclouddenDVA N C E D B L OBransen PlasmaEnergy, science,Buckman Direct Diversion Project

  3. ARM Observations Projected

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 OutreachProductswsicloudwsicloudden Documentation Data Management Facility PlotsProductsObservations Projected

  4. NREL: Transportation Research - Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration wouldMass map shines lightGeospatial ToolkitSMARTSWorking With UsSimulatorTruckNewsProjects

  5. PSERC Current Projects Overview

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page on Delicious RankADVANCED MANUFACTURINGEnergy Bills andOrder 422.1, CONDUCT P - . . -Pathways)PROJECT SUMMARY 11OE0000652

  6. Sandia National Laboratories: Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power AdministrationRobust, High-ThroughputUpcoming Release of thePrograms:Mode Stirred ChamberReuse ReuseProjects

  7. Protection Upgrades Project (4580)

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantityBonneville Power Administration wouldMass mapSpeedingProgramExemptions |(Conference)ProjectProposedAmerica'sTrap and

  8. Production Project Accounts

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home RoomPreservation of Fe(II) by Carbon-Rich Matrices inPrincipalFirmProduction Project Accounts

  9. Project File System

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Homesum_a_epg0_fpd_mmcf_m.xls" ,"Available from WebQuantity ofkandz-cm11 Outreach Home RoomPreservation of Fe(II) by Carbon-Rich Matricesstudents working1999-2000University 4 Project

  10. Savings Project: Lower Water Heating Temperature | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Savings Project: Lower Water Heating Temperature Savings Project: Lower Water Heating Temperature Addthis Project Level Easy Energy Savings 12-30 annually for each 10F...

  11. Pacific Direct Current Intertie (PDCI) Upgrade Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    & Reliability Projects Expand Projects Skip navigation links Line Projects Big Eddy-Knight Central Ferry Lower Monumental Grand Coulee Transmission Line Replacement...

  12. Grand Coulee Transmission Line Replacement Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    & Reliability Projects Expand Projects Skip navigation links Line Projects Big Eddy-Knight Central Ferry Lower Monumental Grand Coulee Transmission Line Replacement...

  13. June 2015 Project Dashboard | Department of Energy

    Office of Environmental Management (EM)

    June 2015 Project Dashboard June 2015 Project Dashboard June 2015 Project Dashboard.pdf More Documents & Publications The Weekend Ozone Effect - The Weekly Ambient Emissions...

  14. Preparing for Project Implementation Assigning Accountability...

    Office of Environmental Management (EM)

    Assigning Accountability for Each Project, April 14, 2010 Preparing for Project Implementation Assigning Accountability for Each Project, April 14, 2010 Assigning Accountability...

  15. Searchlight Wind Energy Project FEIS Appendix E

    Office of Environmental Management (EM)

    June 2, 2009 District Las Vegas Field Office Resource Area Activity (program) Proposed Wind Generation SECTION A. PROJECT INFORMATION 1. Project Name Searchlight Wind Project 4....

  16. SOFTWARE QUALITY & SYSTEMS ENGINEERING PROGRAM: Project Tracking...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Project Tracking Checklist SOFTWARE QUALITY & SYSTEMS ENGINEERING PROGRAM: Project Tracking Checklist The following checklist is intended to provide system owners, project...

  17. project information | netl.doe.gov

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Project Information Biomass Feed and Gasification Archived Projects Agreement Number Project Title Performer Name Technology Area FE0023577 Advanced Gasifier and Water Gas Shift...

  18. Projection optics box

    DOE Patents [OSTI]

    Hale, Layton C. (Livermore, CA); Malsbury, Terry (Tracy, CA); Hudyma, Russell M. (San Ramon, CA); Parker, John M. (Tracy, CA)

    2000-01-01

    A projection optics box or assembly for use in an optical assembly, such as in an extreme ultraviolet lithography (EUVL) system using 10-14 nm soft x-ray photons. The projection optics box utilizes a plurality of highly reflective optics or mirrors, each mounted on a precision actuator, and which reflects an optical image, such as from a mask, in the EUVL system onto a point of use, such as a target or silicon wafer, the mask, for example, receiving an optical signal from a source assembly, such as a developed from laser system, via a series of highly reflective mirrors of the EUVL system. The plurality of highly reflective optics or mirrors are mounted in a housing assembly comprised of a series of bulkheads having wall members secured together to form a unit construction of maximum rigidity. Due to the precision actuators, the mirrors must be positioned precisely and remotely in tip, tilt, and piston (three degrees of freedom), while also providing exact constraint.

  19. Device Oriented Project Controller

    SciTech Connect (OSTI)

    Dalesio, Leo; Kraimer, Martin

    2013-11-20

    This proposal is directed at the issue of developing control systems for very large HEP projects. A de-facto standard in accelerator control is the Experimental Physics and Industrial Control System (EPICS), which has been applied successfully to many physics projects. EPICS is a channel based system that requires that each channel of each device be configured and controlled. In Phase I, the feasibility of a device oriented extension to the distributed channel database was demonstrated by prototyping a device aware version of an EPICS I/O controller that functions with the current version of the channel access communication protocol. Extensions have been made to the grammar to define the database. Only a multi-stage position controller with limit switches was developed in the demonstration, but the grammar should support a full range of functional record types. In phase II, a full set of record types will be developed to support all existing record types, a set of process control functions for closed loop control, and support for experimental beam line control. A tool to configure these records will be developed. A communication protocol will be developed or extensions will be made to Channel Access to support introspection of components of a device. Performance bench marks will be made on both communication protocol and the database. After these records and performance tests are under way, a second of the grammar will be undertaken.

  20. LIMB Demonstration Project Extension

    SciTech Connect (OSTI)

    Not Available

    1990-09-21

    The DOE LIMB Demonstration Project Extension is a continuation of the EPA Limestone Injection Multistage Burner (LIMB) Demonstration. EPA ultimately expects to show that LIMB is a low cost control technology capable of producing moderate SO{sub x} and NO{sub x} control (50--60 percent) with applicability for retrofit to the major portion of the existing coal-fired boiler population. The current EPA Wall-Fired LIMB Demonstration is a four-year project that includes design and installation of a LIMB system at the 105-MW Unit 4 boiler at Ohio Edison's Edgewater Station in Lorain, Ohio. LIMB Extension testing continued during the quarter with lignosulfonated hydrated lime, pulverized limestone, and hydrated dolomitic lime while firing 1.8% and 3% sulfur coals. Sulfur dioxide removal efficiencies were equivalent to the results found during EPA, base LIMB testing. Sulfur dioxide removal efficiencies were lower than expected while testing with pulverized limestone without humidification. A slight increase in sulfur capture was noted while injecting pulverized limestone at the 187' elevation and with the humidifier outlet temperature at 145{degree}F.