Sample records for repair project cxs

  1. Repair and Replacement projects help FM to honor its commitment to

    E-Print Network [OSTI]

    Gulliver, Robert

    of the University. Services provided fall into three major categories: preventive maintenance, routine repairs friendly power. Energy Management is continually recognized for the superior maintenance. · Maintenance (www.facm.umn. edu/services/maintenance.html) Maintenance Operations preserves the physical assets

  2. Environmental Assessment and Finding of No Significant Impact: Pond B Dam Repair Project at the Savannah River Site

    SciTech Connect (OSTI)

    N /A

    1999-09-27T23:59:59.000Z

    The Department of Energy (DOE) has prepared an environmental assessment (EA) (DOE/EA-1285) for the proposed repair of the Pond B dam at the Savannah River Site (SRS), located near Aiken, South Carolina. Based on the analyses in the EA, DOE has determined that the proposed action is not a major Federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act of 1969 (NEPA). Therefore, the preparation of an environmental impact statement (EIS) is not required, and DOE is issuing this Finding of No Significant Impact (FONSI) and Floodplain Statement of Findings.

  3. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Ian Harris; Dennis Harwig; Nancy Porter; Mike Sullivan; Chris Neary

    2004-04-12T23:59:59.000Z

    The two broad categories of deposited weld metal repair and fiber-reinforced composite liner repair technologies were reviewed for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Preliminary test programs were developed for both deposited weld metal repair and for fiber-reinforced composite liner repair. Evaluation trials have been conducted using a modified fiber-reinforced composite liner provided by RolaTube and pipe sections without liners. All pipe section specimens failed in areas of simulated damage. Pipe sections containing fiber-reinforced composite liners failed at pressures marginally greater than the pipe sections without liners. The next step is to evaluate a liner material with a modulus of elasticity approximately 95% of the modulus of elasticity for steel. Preliminary welding parameters were developed for deposited weld metal repair in preparation of the receipt of Pacific Gas & Electric's internal pipeline welding repair system (that was designed specifically for 559 mm (22 in.) diameter pipe) and the receipt of 559 mm (22 in.) pipe sections from Panhandle Eastern. The next steps are to transfer welding parameters to the PG&E system and to pressure test repaired pipe sections to failure. A survey of pipeline operators was conducted to better understand the needs and performance requirements of the natural gas transmission industry regarding internal repair. Completed surveys contained the following principal conclusions: (1) Use of internal weld repair is most attractive for river crossings, under other bodies of water, in difficult soil conditions, under highways, under congested intersections, and under railway crossings. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling (HDD) when a new bore must be created to solve a leak or other problem. (3) Typical travel distances can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). All three groups require pig-based systems. A despooled umbilical system would suffice for the first two groups which represents 81% of survey respondents. The third group would require an onboard self-contained power unit for propulsion and welding/liner repair energy needs. (4) Pipe diameter sizes range from 50.8 mm (2 in.) through 1,219.2 mm (48 in.). The most common size range for 80% to 90% of operators surveyed is 508 mm to 762 mm (20 in. to 30 in.), with 95% using 558.8 mm (22 in.) pipe. An evaluation of potential repair methods clearly indicates that the project should continue to focus on the development of a repair process involving the use of GMAW welding and on the development of a repair process involving the use of fiber-reinforced composite liners.

  4. Project Title:

    Broader source: Energy.gov (indexed) [DOE]

    Repair flowline 61-66-SX-3 DOE Code: Project Lead: Wes Riesland NEPA COMPLIANCE SURVEY 291 Project Information Date: 31 12010 Contractor Code: Project Overview In order to...

  5. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Nancy Porter; Mike Sullivan; Chris Neary

    2003-05-01T23:59:59.000Z

    The two broad categories of deposited weld metal repair and fiber-reinforced composite repair technologies were reviewed for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Preliminary test programs were developed for both deposited weld metal repairs and for fiber-reinforced composite repair. To date, all of the experimental work pertaining to the evaluation of potential repair methods has focused on fiber-reinforced composite repairs. Hydrostatic testing was also conducted on four pipeline sections with simulated corrosion damage: two with composite liners and two without.

  6. INTERNAL REPAIR OF PIPELINES REVIEW & EVALUATION OF INTERNAL PIPELINE REPAIR TRIALS REPORT

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Ian Harris; Dennis Harwig; George Ritter; Bill Mohr; Matt Boring; Nancy Porter; Mike Sullivan; Chris Neary

    2004-09-01T23:59:59.000Z

    The two broad categories of fiber-reinforced composite liner repair and deposited weld metal repair technologies were reviewed and evaluated for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Evaluation trials were conducted on pipe sections with simulated corrosion damage repaired with glass fiber-reinforced composite liners, carbon fiber-reinforced composite liners, and weld deposition. Additional un-repaired pipe sections were evaluated in the virgin condition and with simulated damage. Hydrostatic failure pressures for pipe sections repaired with glass fiber-reinforced composite liner were only marginally greater than that of pipe sections without liners, indicating that this type of liner is generally ineffective at restoring the pressure containing capabilities of pipelines. Failure pressure for pipe repaired with carbon fiber-reinforced composite liner was greater than that of the un-repaired pipe section with damage, indicating that this type of liner is effective at restoring the pressure containing capability of pipe. Pipe repaired with weld deposition failed at pressures lower than that of un-repaired pipe in both the virgin and damaged conditions, indicating that this repair technology is less effective at restoring the pressure containing capability of pipe than a carbon fiber-reinforced liner repair. Physical testing indicates that carbon fiber-reinforced liner repair is the most promising technology evaluated to-date. Development of a comprehensive test plan for this process is recommended for use in the next phase of this project.

  7. Rapid road repair vehicle

    DOE Patents [OSTI]

    Mara, Leo M. (Livermore, CA)

    1998-01-01T23:59:59.000Z

    Disclosed is a rapid road repair vehicle capable of moving over a surface to be repaired at near normal posted traffic speeds to scan for and find an the high rate of speed, imperfections in the pavement surface, prepare the surface imperfection for repair by air pressure and vacuum cleaning, applying a correct amount of the correct patching material to effect the repair, smooth the resulting repaired surface, and catalog the location and quality of the repairs for maintenance records of the road surface. The rapid road repair vehicle can repair surface imperfections at lower cost, improved quality, at a higher rate of speed than was was heretofor possible, with significantly reduced exposure to safety and health hazards associated with this kind of road repair activities in the past.

  8. Rapid road repair vehicle

    DOE Patents [OSTI]

    Mara, L.M.

    1998-05-05T23:59:59.000Z

    Disclosed is a rapid road repair vehicle capable of moving over a surface to be repaired at near normal posted traffic speeds to scan for and find at the high rate of speed, imperfections in the pavement surface, prepare the surface imperfection for repair by air pressure and vacuum cleaning, applying a correct amount of the correct patching material to effect the repair, smooth the resulting repaired surface, and catalog the location and quality of the repairs for maintenance records of the road surface. The rapid road repair vehicle can repair surface imperfections at lower cost, improved quality, at a higher rate of speed than was not heretofor possible, with significantly reduced exposure to safety and health hazards associated with this kind of road repair activities in the past. 2 figs.

  9. Developments advance subsea pipelaying, inspection, repair

    SciTech Connect (OSTI)

    NONE

    1997-09-15T23:59:59.000Z

    Recent advances in laying, inspecting, and repairing pipelines are helping to cut both costs and time. A new dredging system that employs jets to clear a subsea trench for pipelay received trials off Belgium last spring. Also, within the last year, projects in the Middle East and North Sea employed technologies that promise to make inspecting the surface of a subsea pipeline in difficult terrain easier, less time consuming, and therefore less costly. Plus, subsea repair of damaged pipelines may take less time with a new ``stabbable`` pipe connector. The paper describes jet dredging, inspection advance, support software, the North Sea site, and pipeline repair.

  10. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Bill Bruce; Nancy Porter; George Ritter; Matt Boring; Mark Lozev; Ian Harris; Bill Mohr; Dennis Harwig; Robin Gordon; Chris Neary; Mike Sullivan

    2005-07-20T23:59:59.000Z

    The two broad categories of fiber-reinforced composite liner repair and deposited weld metal repair technologies were reviewed and evaluated for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Principal conclusions from a survey of natural gas transmission industry pipeline operators can be summarized in terms of the following performance requirements for internal repair: (1) Use of internal repair is most attractive for river crossings, under other bodies of water, in difficult soil conditions, under highways, under congested intersections, and under railway crossings. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling when a new bore must be created to solve a leak or other problem. (3) Typical travel distances can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). All three groups require pig-based systems. A despooled umbilical system would suffice for the first two groups which represents 81% of survey respondents. The third group would require an onboard self-contained power unit for propulsion and welding/liner repair energy needs. (4) The most common size range for 80% to 90% of operators surveyed is 508 mm (20 in.) to 762 mm (30 in.), with 95% using 558.8 mm (22 in.) pipe. Evaluation trials were conducted on pipe sections with simulated corrosion damage repaired with glass fiber-reinforced composite liners, carbon fiber-reinforced composite liners, and weld deposition. Additional un-repaired pipe sections were evaluated in the virgin condition and with simulated damage. Hydrostatic failure pressures for pipe sections repaired with glass fiber-reinforced composite liner were only marginally greater than that of pipe sections without liners, indicating that this type of liner is only marginally effective at restoring the pressure containing capabilities of pipelines. Failure pressures for larger diameter pipe repaired with a semi-circular patch of carbon fiber-reinforced composite lines were also marginally greater than that of a pipe section with un-repaired simulated damage without a liner. These results indicate that fiber reinforced composite liners have the potential to increase the burst pressure of pipe sections with external damage Carbon fiber based liners are viewed as more promising than glass fiber based liners because of the potential for more closely matching the mechanical properties of steel. Pipe repaired with weld deposition failed at pressures lower than that of un-repaired pipe in both the virgin and damaged conditions, indicating that this repair technology is less effective at restoring the pressure containing capability of pipe than a carbon fiber-reinforced liner repair. Physical testing indicates that carbon fiber-reinforced liner repair is the most promising technology evaluated to-date. In lieu of a field installation on an abandoned pipeline, a preliminary nondestructive testing protocol is being developed to determine the success or failure of the fiber-reinforced liner pipeline repairs. Optimization and validation activities for carbon-fiber repair methods are ongoing.

  11. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Ian Harris; Dennis Harwig; George Ritter; Bill Mohr; Matt Boring; Nancy Porter; Mike Sullivan; Chris Neary

    2004-12-31T23:59:59.000Z

    The two broad categories of fiber-reinforced composite liner repair and deposited weld metal repair technologies were reviewed and evaluated for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Principal conclusions from a survey of natural gas transmission industry pipeline operators can be summarized in terms of the following performance requirements for internal repair: (1) Use of internal repair is most attractive for river crossings, under other bodies of water, in difficult soil conditions, under highways, under congested intersections, and under railway crossings. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling when a new bore must be created to solve a leak or other problem. (3) Typical travel distances can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). All three groups require pig-based systems. A despooled umbilical system would suffice for the first two groups which represents 81% of survey respondents. The third group would require an onboard self-contained power unit for propulsion and welding/liner repair energy needs. (4) The most common size range for 80% to 90% of operators surveyed is 508 mm (20 in.) to 762 mm (30 in.), with 95% using 558.8 mm (22 in.) pipe. Evaluation trials were conducted on pipe sections with simulated corrosion damage repaired with glass fiber-reinforced composite liners, carbon fiber-reinforced composite liners, and weld deposition. Additional un-repaired pipe sections were evaluated in the virgin condition and with simulated damage. Hydrostatic failure pressures for pipe sections repaired with glass fiber-reinforced composite liner were only marginally greater than that of pipe sections without liners, indicating that this type of liner is only marginally effective at restoring the pressure containing capabilities of pipelines. Failure pressures for larger diameter pipe repaired with a semi-circular patch of carbon fiber-reinforced composite lines were also marginally greater than that of a pipe section with un-repaired simulated damage without a liner. These results indicate that fiber reinforced composite liners have the potential to increase the burst pressure of pipe sections with external damage Carbon fiber based liners are viewed as more promising than glass fiber based liners because of the potential for more closely matching the mechanical properties of steel. Pipe repaired with weld deposition failed at pressures lower than that of un-repaired pipe in both the virgin and damaged conditions, indicating that this repair technology is less effective at restoring the pressure containing capability of pipe than a carbon fiber-reinforced liner repair. Physical testing indicates that carbon fiber-reinforced liner repair is the most promising technology evaluated to-date. The first round of optimization and validation activities for carbon-fiber repairs are complete. Development of a comprehensive test plan for this process is recommended for use in the field trial portion of this program.

  12. INTERNAL REPAIR OF PIPELINES

    SciTech Connect (OSTI)

    Robin Gordon; Bill Bruce; Ian Harris; Dennis Harwig; George Ritter; Bill Mohr; Matt Boring; Nancy Porter; Mike Sullivan; Chris Neary

    2004-08-17T23:59:59.000Z

    The two broad categories of fiber-reinforced composite liner repair and deposited weld metal repair technologies were reviewed and evaluated for potential application for internal repair of gas transmission pipelines. Both are used to some extent for other applications and could be further developed for internal, local, structural repair of gas transmission pipelines. Principal conclusions from a survey of natural gas transmission industry pipeline operators can be summarized in terms of the following performance requirements for internal repair: (1) Use of internal repair is most attractive for river crossings, under other bodies of water, in difficult soil conditions, under highways, under congested intersections, and under railway. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling when a new bore must be created to solve a leak or other problem. (3) Typical travel distances can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). All three groups require pig-based systems. A despooled umbilical system would suffice for the first two groups which represents 81% of survey respondents. The third group would require an onboard self-contained power unit for propulsion and welding/liner repair energy needs. (4) The most common size range for 80% to 90% of operators surveyed is 508 mm (20 in.) to 762 mm (30 in.), with 95% using 558.8 mm (22 in.) pipe. Evaluation trials were conducted on pipe sections with simulated corrosion damage repaired with glass fiber-reinforced composite liners, carbon fiber-reinforced composite liners, and weld deposition. Additional un-repaired pipe sections were evaluated in the virgin condition and with simulated damage. Hydrostatic failure pressures for pipe sections repaired with glass fiber-reinforced composite liner were only marginally greater than that of pipe sections without liners, indicating that this type of liner is only marginally effective at restoring the pressure containing capabilities of pipelines. Failure pressures for larger diameter pipe repaired with a semi-circular patch of carbon fiber-reinforced composite lines were also marginally greater than that of a pipe section with un-repaired simulated damage without a liner. These results indicate that fiber reinforced composite liners have the potential to increase the burst pressure of pipe sections with external damage Carbon fiber based liners are viewed as more promising than glass fiber based liners because of the potential for more closely matching the mechanical properties of steel. Pipe repaired with weld deposition failed at pressures lower than that of un-repaired pipe in both the virgin and damaged conditions, indicating that this repair technology is less effective at restoring the pressure containing capability of pipe than a carbon fiber-reinforced liner repair. Physical testing indicates that carbon fiber-reinforced liner repair is the most promising technology evaluated to-date. Development of a comprehensive test plan for this process is recommended for use in the field trial portion of this program.

  13. Rapid road repair vehicle

    DOE Patents [OSTI]

    Mara, Leo M. (Livermore, CA)

    1999-01-01T23:59:59.000Z

    Disclosed are improvments to a rapid road repair vehicle comprising an improved cleaning device arrangement, two dispensing arrays for filling defects more rapidly and efficiently, an array of pre-heaters to heat the road way surface in order to help the repair material better bond to the repaired surface, a means for detecting, measuring, and computing the number, location and volume of each of the detected surface imperfection, and a computer means schema for controlling the operation of the plurality of vehicle subsystems. The improved vehicle is, therefore, better able to perform its intended function of filling surface imperfections while moving over those surfaces at near normal traffic speeds.

  14. Window Replacement, Rehabilitation, & Repair Guides - Building...

    Energy Savers [EERE]

    Window Replacement, Rehabilitation, & Repair Guides - Building America Top Innovation Window Replacement, Rehabilitation, & Repair Guides - Building America Top Innovation Effec...

  15. Industrial motor repair in the United States

    SciTech Connect (OSTI)

    Schueler, V.; Leistner, P.; Douglass, J.

    1994-09-01T23:59:59.000Z

    This report characterizes the motor repair industry in the United States; summarizes current motor repair and testing practice; and identifies barriers to energy motor repair practice and recommends strategies for overcoming those barriers.

  16. Mammalian DNA Repair. Final Report

    SciTech Connect (OSTI)

    None

    2003-01-24T23:59:59.000Z

    The Gordon Research Conference (GRC) on Mammalian DNA Repair was held at Harbortown Resort, Ventura Beach, CA. Emphasis was placed on current unpublished research and discussion of the future target areas in this field.

  17. Inspect and Repair Steam Traps

    SciTech Connect (OSTI)

    Not Available

    2006-01-01T23:59:59.000Z

    This revised ITP tip sheet on inspecting and repairing steam traps provide how-to advice for improving industrial steam systems using low-cost, proven practices and technologies.

  18. Verification of Motor Repair Quality

    E-Print Network [OSTI]

    Butler, K.

    Motor testing at Advanced Energy has shown that a motor that has not suffered irreparable damage as a result of failure can be repaired to perform as well as before the failure. But the only way to achieve the performance level of an energy...

  19. Biomolecular Simulation of Base Excision Repair and Protein Signaling

    SciTech Connect (OSTI)

    Straatsma, TP; McCammon, J. A.; Miller, John H.; Smith, Paul E.; Vorpagel, Erich R.; Wong, Chung F.; Zacharias, Martin W.

    2006-03-03T23:59:59.000Z

    The goal of the Biomolecular Simulation of Base Excision Repair and Protein Signaling project is to enhance our understanding of the mechanism of human polymerase-?, one of the key enzymes in base excision repair (BER) and the cell-signaling enzymes cyclic-AMP-dependent protein kinase. This work used molecular modeling and simulation studies to specifically focus on the • dynamics of DNA and damaged DNA • dynamics and energetics of base flipping in DNA • mechanism and fidelity of nucleotide insertion by BER enzyme human polymerase-? • mechanism and inhibitor design for cyclic-AMP-dependent protein kinase. Molecular dynamics simulations and electronic structure calculations have been performed using the computer resources at the Molecular Science Computing Facility at the Environmental Molecular Sciences Laboratory.

  20. The Gordon conference on mammalian DNA repair

    SciTech Connect (OSTI)

    Cleaver, J.E.; Smerdon, M.J.

    1993-12-31T23:59:59.000Z

    A brief overview of the Gordon Conference on Mammalian Repair held February 1-5, 1993 in Ventura, California is presented.

  1. Development and validation of bonded composite doubler repairs for commercial aircraft.

    SciTech Connect (OSTI)

    Roach, Dennis Patrick; Rackow, Kirk A.

    2007-07-01T23:59:59.000Z

    A typical aircraft can experience over 2,000 fatigue cycles (cabin pressurizations) and even greater flight hours in a single year. An unavoidable by-product of aircraft use is that crack, impact, and corrosion flaws develop throughout the aircraft's skin and substructure elements. Economic barriers to the purchase of new aircraft have placed even greater demands on efficient and safe repair methods. The use of bonded composite doublers offers the airframe manufacturers and aircraft maintenance facilities a cost effective method to safely extend the lives of their aircraft. Instead of riveting multiple steel or aluminum plates to facilitate an aircraft repair, it is now possible to bond a single Boron-Epoxy composite doubler to the damaged structure. The FAA's Airworthiness Assurance Center at Sandia National Labs (AANC), Boeing, and Federal Express completed a pilot program to validate and introduce composite doubler repair technology to the U.S. commercial aircraft industry. This project focused on repair of DC-10 fuselage structure and its primary goal was to demonstrate routine use of this repair technology using niche applications that streamline the design-to-installation process. As composite doubler repairs gradually appear in the commercial aircraft arena, successful flight operation data is being accumulated. These commercial aircraft repairs are not only demonstrating the engineering and economic advantages of composite doubler technology but they are also establishing the ability of commercial maintenance depots to safely adopt this repair technique. This report presents the array of engineering activities that were completed in order to make this technology available for widespread commercial aircraft use. Focused laboratory testing was conducted to compliment the field data and to address specific issues regarding damage tolerance and flaw growth in composite doubler repairs. Fatigue and strength tests were performed on a simulated wing repair using a substandard design and a flawed installation. In addition, the new Sol-Gel surface preparation technique was evaluated. Fatigue coupon tests produced Sol-Gel results that could be compared with a large performance database from conventional, riveted repairs. It was demonstrated that not only can composite doublers perform well in severe off-design conditions (low doubler stiffness and presence of defects in doubler installation) but that the Sol-Gel surface preparation technique is easier and quicker to carry out while still producing optimum bonding properties. Nondestructive inspection (NDI) methods were developed so that the potential for disbond and delamination growth could be monitored and crack growth mitigation could be quantified. The NDI methods were validated using full-scale test articles and the FedEx aircraft installations. It was demonstrated that specialized NDI techniques can detect flaws in composite doubler installations before they reach critical size. Probability of Detection studies were integrated into the FedEx training in order to quantify the ability of aircraft maintenance depots to properly monitor these repairs. In addition, Boeing Structural Repair and Nondestructive Testing Manuals were modified to include composite doubler repair and inspection procedures. This report presents the results from the FedEx Pilot Program that involved installation and surveillance of numerous repairs on operating aircraft. Results from critical NDI evaluations are reported in light of damage tolerance assessments for bonded composite doublers. This work has produced significant interest from airlines and aircraft manufacturers. The successful Pilot Program produced flight performance history to establish the durability of bonded composite patches as a permanent repair on commercial aircraft structures. This report discusses both the laboratory data and Pilot Program results from repair installations on operating aircraft to introduce composite doubler repairs into mainstream commercial aircraft use.

  2. Role of DNA repair protein ERCC1 in skin cancer 

    E-Print Network [OSTI]

    Song, Liang

    2009-01-01T23:59:59.000Z

    Nucleotide excision repair (NER) is one of the major repair systems for removal of DNA lesions. The NER pathway has evolved mainly to repair UV-induced DNA damage and is also active against a broad range of endogenously ...

  3. The feasibility of electrophoretic repair of impoundment leaks

    E-Print Network [OSTI]

    Han, Ji-Seok

    2002-01-01T23:59:59.000Z

    finding, repairing and testing the leaks, are tedious, expensive, and dangerous to workers. Electrophoretic repair technique is an innovative, economic, and safe method to repair the leakage of impoundments. A suspension of clay particles is induced...

  4. Automotive Repair by Number Theory Bart Snapp and Chris Snapp

    E-Print Network [OSTI]

    Snapp, Bart

    Automotive Repair by Number Theory Bart Snapp and Chris Snapp While repairing the ignition switch on a 1981 Fiat Spider, we discovered the following connection between number theory and automotive repair

  5. A sociotechnical framework for understanding infrastructure breakdown and repair

    SciTech Connect (OSTI)

    Sims, Benjamin H [Los Alamos National Laboratory

    2009-01-01T23:59:59.000Z

    This paper looks at how and why infrastructure is repaired. With a new era of infrastructure spending underway, policymakers need to understand and anticipate the particular technical and political challenges posed by infrastructure repair. In particular, as infrastructure problems are increasingly in the public eye with current economic stimulus efforts, the question has increasingly been asked: why has it been so difficult for the United Statesto devote sustained resources to maintaining and upgrading its national infrastructure? This paper provides a sociotechnical framework for understanding the challenges of infrastructure repair, and demonstrates this framework using a case study of seismic retrofit of freeway bridges in California. The design of infrastructure is quite different from other types of design work even when new infrastructure is being designed. Infrastructure projects are almost always situated within, and must work with, existing infrastructure networks. As a result, compared to design of more discrete technological artifacts, the design of infrastructure systems requires a great deal of attention to interfaces as well as adaptation of design to the constraints imposed by existing systems. Also, because of their scale, infrastructural technologies engage with social life at a level where explicit political agendas may playa central role in the design process. The design and building of infrastructure is therefore often an enormously complex feat of sociotechnical engineering, in which technical and political agendas are negotiated together until an outcome is reached that allows the project to move forward. These sociotechnical settlements often result in a complex balancing of powerful interests around infrastructural artifacts; at the same time, less powerful interests have historically often been excluded or marginalized from such settlements.

  6. Hurricane-damaged Gulf of Mexico pipeline repaired with cold forging

    SciTech Connect (OSTI)

    Lewis, G. (Texaco Pipeline Inc., Houma, LA (United States)); DeGruy, P. (Texaco Inc., New Orleans, LA (United States)); Avery, L. (Big Inch Marine Systems Inc., Lafayette, LA (United States))

    1993-05-03T23:59:59.000Z

    Damage to Texaco Pipeline Inc.'s Eugene Island Pipeline System (EIPS) in last year's Hurricane Andrew prompted a complex repair project unique for the Gulf of Mexico. Damage, suffered when the anchor of a runaway semisubmersible drilling rig crashed into the 20-in. EPIS during the height of the storm, caused the pipeline to fail under pressure within 48 hr. after start-up following the storm. The paper describes the importance of the EIPS; system safety; Andrew's damage; locating the leak; repair options; the chosen system; mechanical bonding; end connectors and ball flanges; and diving operations.

  7. INTERNAL REPAIR OF GAS PIPLINES SURVEY OF OPERATOR EXPERIENCE AND INDUSTRY NEEDS REPORT

    SciTech Connect (OSTI)

    Ian D. Harris

    2003-09-01T23:59:59.000Z

    A repair method that can be applied from the inside of a gas transmission pipeline (i.e., a trenchless repair) is an attractive alternative to conventional repair methods since the need to excavate the pipeline is precluded. This is particularly true for pipelines in environmentally sensitive and highly populated areas. The objectives of the project are to evaluate, develop, demonstrate, and validate internal repair methods for pipelines; develop a functional specification for an internal pipeline repair system; and prepare a recommended practice for internal repair of pipelines. The purpose of this survey is to better understand the needs and performance requirements of the natural gas transmission industry regarding internal repair. A total of fifty-six surveys were sent to pipeline operators. A total of twenty completed surveys were returned, representing a 36% response rate, which is considered very good given the fact that tailored surveys are known in the marketing industry to seldom attract more than a 10% response rate. The twenty survey responses produced the following principal conclusions: (1) Use of internal weld repair is most attractive for river crossings, under other bodies of water (e.g., lakes and swamps) in difficult soil conditions, under highways, under congested intersections, and under railway crossings. All these areas tend to be very difficult and very costly if, and where, conventional excavated repairs may be currently used. (2) Internal pipe repair offers a strong potential advantage to the high cost of horizontal direct drilling (HDD) when a new bore must be created to solve a leak or other problem in a water/river crossing. (3) The typical travel distances required can be divided into three distinct groups: up to 305 m (1,000 ft.); between 305 m and 610 m (1,000 ft. and 2,000 ft.); and beyond 914 m (3,000 ft.). In concept, these groups require pig-based systems; despooled umbilical systems could be considered for the first two groups. For the last group a self-propelled system with an onboard self-contained power and welding system is required. (4) Pipe size range requirements range from 50.8 mm (2 in.) through 1,219.2 mm (48 in.) in diameter. The most common size range for 80% to 90% of operators surveyed is 508 mm to 762 mm (20 in. to 30 in.) diameter, with 95% using 558.8 mm (22 in.) diameter pipe.

  8. CATASTROPHIC REPAIR REQUEST CHECKLIST Office of Research

    E-Print Network [OSTI]

    Schladow, S. Geoffrey

    Not Meet Policy Not Sure Equipment may not be covered by a service contract that provides for repair Contacted: ______________ Amount of Annual Service Contract: $ ___________ Meets Policy Info Pending Does

  9. Reducing Your Leak Rate Without Repairing Leaks 

    E-Print Network [OSTI]

    Beals, C.

    2005-01-01T23:59:59.000Z

    As plant personnel know, repairing compressed air leaks can be an expensive, labor intensive and never-ending process. This article discusses ways plant personnel can reduce and maintain their leak rate at a lower level ...

  10. Vehicle Repair Policy Outline the policy regarding vehicle repair on University of Michigan (U-M) vehicles.

    E-Print Network [OSTI]

    Kirschner, Denise

    Vehicle Repair Policy Objective Outline the policy regarding vehicle repair on University of Michigan (U-M) vehicles. Policy 1. All vehicle repairs performed on U-M vehicles must be coordinated facility to repair their fleet vehicles. 2. U-M vehicles leased through Fleet Services include routine

  11. Energy and Technology Review: Unlocking the mysteries of DNA repair

    SciTech Connect (OSTI)

    Quirk, W.A.

    1993-04-01T23:59:59.000Z

    DNA, the genetic blueprint, has the remarkable property of encoding its own repair following diverse types of structural damage induced by external agents or normal metabolism. We are studying the interplay of DNA damaging agents, repair genes, and their protein products to decipher the complex biochemical pathways that mediate such repair. Our research focuses on repair processes that correct DNA damage produced by chemical mutagens and radiation, both ionizing and ultraviolet. The most important type of DNA repair in human cells is called excision repair. This multistep process removes damaged or inappropriate pieces of DNA -- often as a string of 29 nucleotides containing the damage -- and replaces them with intact ones. We have isolated, cloned, and mapped several human repair genes associated with the nucleotide excision repair pathway and involved in the repair of DNA damage after exposure to ultraviolet light or mutagens in cooked food. We have shown that a defect in one of these repair genes, ERCC2, is responsible for the repair deficiency in one of the groups of patients with the recessive genetic disorder xeroderma pigmentosum (XP group D). We are exploring ways to purify sufficient quantities (milligrams) of the protein products of these and other repair genes so that we can understand their functions. Our long-term goals are to link defective repair proteins to human DNA repair disorders that predispose to cancer, and to produce DNA-repair-deficient mice that can serve as models for the human disorders.

  12. HYDROGEN EFFECTS ON LASER ENGINEERED NET SHAPE (LENS) REPAIRED WELDMENTS

    SciTech Connect (OSTI)

    Korinko, P; Thad Adams, T

    2006-10-06T23:59:59.000Z

    New methods of repairing mis-machined components are always of interest. In this study, an innovative method using Laser Engineered Net Shape{trademark} (LENS{reg_sign}) forming was used to repair intentionally mis-machined test articles. The components were repaired and subsequently hydrogen charged and burst tested. The LENS repair did not have an adverse effect on the solid state weld process that was used to repair the components. Hydrogen charged samples failed in a similar manner to the uncharged samples. Overall, the prospects for LENS repairing similar products are favorable and further work is encouraged.

  13. ASBESTOS PROJECT MANAGEMENT University of California, San Diego

    E-Print Network [OSTI]

    Aluwihare, Lihini

    in advance if the renovation and demolition project with friable asbestos-containing materials is over 1601 ASBESTOS PROJECT MANAGEMENT University of California, San Diego UC San Diego project managers to maintenance, repair, and construction of UC-owned and leased buildings where asbestos-containing materials

  14. Repairable chip bonding/interconnect process

    DOE Patents [OSTI]

    Bernhardt, Anthony F. (Berkeley, CA); Contolini, Robert J. (Livermore, CA); Malba, Vincent (Livermore, CA); Riddle, Robert A. (Tracy, CA)

    1997-01-01T23:59:59.000Z

    A repairable, chip-to-board interconnect process which addresses cost and testability issues in the multi-chip modules. This process can be carried out using a chip-on-sacrificial-substrate technique, involving laser processing. This process avoids the curing/solvent evolution problems encountered in prior approaches, as well is resolving prior plating problems and the requirements for fillets. For repairable high speed chip-to-board connection, transmission lines can be formed on the sides of the chip from chip bond pads, ending in a gull wing at the bottom of the chip for subsequent solder.

  15. Repairable chip bonding/interconnect process

    DOE Patents [OSTI]

    Bernhardt, A.F.; Contolini, R.J.; Malba, V.; Riddle, R.A.

    1997-08-05T23:59:59.000Z

    A repairable, chip-to-board interconnect process which addresses cost and testability issues in the multi-chip modules is disclosed. This process can be carried out using a chip-on-sacrificial-substrate technique, involving laser processing. This process avoids the curing/solvent evolution problems encountered in prior approaches, as well is resolving prior plating problems and the requirements for fillets. For repairable high speed chip-to-board connection, transmission lines can be formed on the sides of the chip from chip bond pads, ending in a gull wing at the bottom of the chip for subsequent solder. 10 figs.

  16. SNL Researchers Assess Wind Turbine Blade Inspection and Repair...

    Office of Environmental Management (EM)

    Researchers Assess Wind Turbine Blade Inspection and Repair Methods SNL Researchers Assess Wind Turbine Blade Inspection and Repair Methods May 18, 2015 - 5:32pm Addthis A picture...

  17. Phonemic Categorization and Phonotactic Repair as Parallel Sublexical Processes 

    E-Print Network [OSTI]

    Ishikawa, Kiyoshi

    2014-07-01T23:59:59.000Z

    categorization and phonotactic repair are sublexical and simultaneous; phonotactic repairs themselves depend on coarticulation cues. Such models can be implemented in two different versions: suprasegmental matching, according to which a speech signal is matched...

  18. Development of a composite repair system for reinforcing offshore risers

    E-Print Network [OSTI]

    Alexander, Christopher Richard

    2009-05-15T23:59:59.000Z

    A research program was conducted to investigate the application of composite materials in repairing corroded offshore risers, leading to the development of an optimized repair using a hybrid carbon/E-glass system. The objective of this research...

  19. Development program to certify composite doubler repair technique for commercial aircraft

    SciTech Connect (OSTI)

    Roach, D.P.

    1997-07-01T23:59:59.000Z

    Commercial airframes exceeding 20 service years often develop crack and corrosion flaws. Bonded composite doublers offer a cost effective method to safely extend aircraft lives. The Federal Aircraft Authority (FAA) has completed a project to introduce composite doubler repair technology to the commercial aircraft industry. Instead of riveting steel or aluminum plates for repair, a single composite doubler may be bonded to the damaged structure. Adhesive bonding eliminates stress concentrations caused by fastener holes. Composites are readily formed into complex shapes for repairing irregular components. Also, composite doublers can be tailored to meet specific anisotropy needs, eliminating structural stiffening in directions other than those required. Other advantages include corrosion resistance, a high strength-to-weight ratio, and potential time savings in installation. One phase of this study developed general methodologies and test programs to ensure proper performance of the technique. A second phase focused on reinforcement of an L-1011 door frame, and encompassed all lifetime tasks such as design, analysis, installation, and nondestructive inspection. This paper overviews the project and details the activities conducted to gain FAA approval for composite doubler use. Structural tests evaluated the damage tolerance and fatigue performance of composite doublers while finite element models were generated to study doubler design issues. Nondestructive inspection procedures were developed and validated using full-scale test articles. Installation dry-runs demonstrated the viability of applying composite doublers in hangar environments. The project`s documentation package was used to support installation of a Boron-Epoxy composite repair on a Delta Air Lines L-1011 aircraft. A second product of the results is a Lockheed Service Bulletin which allows the door corner composite doubler to be installed on all L-1011 aircraft. 9 refs., 10 figs., 2 tabs.

  20. Repairing Type Errors in Functional Programs 

    E-Print Network [OSTI]

    McAdam, Bruce J

    Type systems for programming languages can be used by compilers to reject programs which are found to be unsound and which may, therefore, fail to execute successfully. When a program is rejected the programmer must repair it so that it can be type...

  1. An emergency response team for membrane repair

    E-Print Network [OSTI]

    Kirchhausen, Tomas

    events, which we focus on here. As discussed later, Ca2+ influx at the site of plasma membrane-fusion events are required to repair a torn plasma membrane, and we propose that this emergency products and the plasma membrane. Reseal or die. Plasma-membrane disruption is a normal event in the life

  2. EPA Lead Safety for Renovation, Repair and

    E-Print Network [OSTI]

    Tennessee, University of

    EPA Lead Safety for Renovation, Repair and Painting (RRP) Course Certified Renovators Class, CSP, CHMM, Certified Lead Paint Inspector.; Certified Renovator; EPA Ac- credited Lead RRP trainer or fax registratio Registration Form Cash Method of Payment Check Name Mailing Address Phone Lead Safety

  3. Visualization of Mismatch Repair in Bacterial Cells

    E-Print Network [OSTI]

    Smith, Bradley T.

    We determined the localizations of mismatch repair proteins in living Bacillus subtilis cells. MutS-GFP colocalized with the chromosome in all cells and formed foci in a subset of cells. MutL-GFP formed foci in a subset ...

  4. Regulation of DNA repair by parkin

    SciTech Connect (OSTI)

    Kao, Shyan-Yuan, E-mail: shyan-yuan_kao@meei.harvard.edu [Eaton Peabody Laboratory, Massachusetts Eye and Ear Infirmary, 243 Charles Street, Boston, MA 02114 (United States)] [Eaton Peabody Laboratory, Massachusetts Eye and Ear Infirmary, 243 Charles Street, Boston, MA 02114 (United States)

    2009-05-01T23:59:59.000Z

    Mutation of parkin is one of the most prevalent causes of autosomal recessive Parkinson's disease (PD). Parkin is an E3 ubiquitin ligase that acts on a variety of substrates, resulting in polyubiquitination and degradation by the proteasome or monoubiquitination and regulation of biological activity. However, the cellular functions of parkin that relate to its pathological involvement in PD are not well understood. Here we show that parkin is essential for optimal repair of DNA damage. Parkin-deficient cells exhibit reduced DNA excision repair that can be restored by transfection of wild-type parkin, but not by transfection of a pathological parkin mutant. Parkin also protects against DNA damage-induced cell death, an activity that is largely lost in the pathological mutant. Moreover, parkin interacts with the proliferating cell nuclear antigen (PCNA), a protein that coordinates DNA excision repair. These results suggest that parkin promotes DNA repair and protects against genotoxicity, and implicate DNA damage as a potential pathogenic mechanism in PD.

  5. Antibody specific for a DNA repair protein

    DOE Patents [OSTI]

    Petrini, John H.; Morgan, William Francis; Maser, Richard Scott; Carney, James Patrick

    2006-07-11T23:59:59.000Z

    An isolated and purified DNA molecule encoding a DNA repair protein, p95, is provided, as is isolated and purified p95. Also provided are methods of detecting p95 and DNA encoding p95. The invention further provides p95 knock-out mice.

  6. DNA encoding a DNA repair protein

    DOE Patents [OSTI]

    Petrini, John H.; Morgan, William Francis; Maser, Richard Scott; Carney, James Patrick

    2006-08-15T23:59:59.000Z

    An isolated and purified DNA molecule encoding a DNA repair protein, p95, is provided, as is isolated and purified p95. Also provided are methods of detecting p95 and DNA encoding p95. The invention further provides p95 knock-out mice.

  7. Method for mask repair using defect compensation

    DOE Patents [OSTI]

    Sweeney, Donald W. (San Ramon, CA); Ray-Chaudhuri, Avijit K. (Livermore, CA)

    2001-01-01T23:59:59.000Z

    A method for repair of amplitude and/or phase defects in lithographic masks. The method involves modifying or altering a portion of the absorber pattern on the surface of the mask blank proximate to the mask defect to compensate for the local disturbance (amplitude or phase) of the optical field due to the defect.

  8. Laboratory testing of closure cap repair techniques

    SciTech Connect (OSTI)

    Persoff, P.; Moridis, G. [Lawrence Berkeley National Lab., CA (United States); Tuck, D.M. [Westinghouse Savannah River Company, Aiken, SC (United States)] [and others

    1996-10-01T23:59:59.000Z

    Landfill design requires a low permeability closure cap as well as a low permeability liner. The Savannah River Site, in South Carolina, has approximately 85 acres of mixed waste landfills covered with compacted kaolin clay. Maintaining low permeability of the clay cap requires both that the permeability of the compacted clay itself remain low and that the integrity of the barrier be maintained. Barrier breaches typically result from penetration by roots or animals, and especially cracks caused by uneven settling or desiccation. In this study, clay layers, 0.81 m in diameter and 7.6 cm thick, were compacted in 7 lysimeters to simulate closure caps. The hydraulic conductivity of each layer was measured, and the compacted clay layers (CCL`s) were cracked by drying. Then various repair techniques were applied and the effectiveness of each repair was assessed by remeasuring the hydraulic conductivity. Finally the repaired CCL was again dried and measured to determine how the repair responded to the conditions that caused the original failure. For a full report of this investigation see Persoff et al. Six repair techniques have been tested, four of which involve the use of injectable barrier liquids colloidal silica (CS) and polysiloxane (PSX) described below: (I) covering the crack with a bentonite geosynthetic clay liner (GCL), (ii) recompaction of new kaolinite at STD+3 moisture content joined to existing kaolinite that had dried and shrunk, (iii) direct injection of colloidal silica to a crack, (iv) injection of colloidal silica (CS) to wells in an overlying sand layer, (v) direct injection of polysiloxane to a crack, and (vi), injection of polysiloxane (PSX) to wells in an overlying soil layer.

  9. Helium bubble distributions in reactor tank repair specimens

    SciTech Connect (OSTI)

    Tosten, M.H.; Kestin, P.A.

    1992-03-01T23:59:59.000Z

    This report discusses the Reactor Tank Repair (RTR) program was initiated to develop an in-tank repair process capable of repairing stress corrosion cracks within the SRS reactor tank walls, in the event that such a repair is needed. Previous attempts to repair C-reactor tank with a gas tungsten arc (GTA) welding process were unsuccessful due to significant cracking that occurred in the heat-affected-zones adjacent to the repair welds. It was determined that this additional cracking was a result of helium embrittlement caused by the combined effects of helium (existing within the tank walls), the high heat input associated with the GTA process, and weld shrinkage stresses. Based on the results of earlier studies it was suggested that the effects of helium embrittlement could be minimized by using a low heat input GMA process. Metallographic analysis played an important role throughout the investigation of alternative welding methods for the repair of helium-containing materials.

  10. New Technologies for Repairing Aging Cables in Nuclear Power Plants

    SciTech Connect (OSTI)

    Simmons, Kevin L.; Fifield, Leonard S.; Westman, Matthew P.

    2013-09-11T23:59:59.000Z

    The goal of this project is to demonstrate a proof-of-concept for a technique to repair aging cables that have been subjected to degradation associated with long-term thermal and radiation exposure in nuclear power plants. The physical degradation of the aging cables manifests itself primarily as cracking and increased brittleness of the polymeric electrical insulation. Therefore, the proposed cable-repair concept comprises development of techniques to impart a softening agent within the deteriorated polymer insulation jacket so as to regain the ability of the insulation to stretch without failing and possibly to heal existing cracks in the insulation. Our approach is to use commercially available ethylene-propylene rubber (EPR) as the relevant test material, demonstrate the adsorption of chemical treatments in the EPR and quantify changes in resulting physical and mechanical properties. EPR cable samples have been thermally treated in air to produce specimens corresponding to the full range of cable age-performance points from new (>350% elongation at break) to end-of-life (<50% elongation at break). The current focus is on two chemical treatments selected as candidates for restoring age-related cable elasticity loss: a rubber plasticizer and a reactive silane molecule. EPR specimens of 200, 150, 100, and 50% elongation at break have been soaked in the candidate chemical treatments and the kinetics of chemical uptake, measured by change in mass of the samples, has been determined. Mechanical properties as a function of aging and chemical treatment have been measured including ultimate tensile strength, tensile modulus at 50% strain, elongation at break, and storage modulus. Dimensional changes with treatment and changes in glass transition temperature were also investigated. These ongoing experiments are expected to provide insight into the physical-chemical nature of the effect of thermal degradation on EPR rejuvenation limits and to advance novel methods for restoring the ability of degraded EPR to be compliant and resist fracture. The results of this research reveal that absorption of chemical treatments can lower the glass transition temperature and modulus of EPR. Chemical treatments pursued thus far have proven ineffective at restoring EPR strength and elongation at break. Future work will combine the plasticizer modalities found to successfully increase the volume of the EPR, reduce EPR glass transition temperature and reduce EPR modulus with promising chemistries that will repair the damage of the polymer, potentially using the plasticizer as a host for the new chemistry.

  11. DNA repair is the target of novel antibiotics

    E-Print Network [OSTI]

    Gunderson, Carl Wayne

    2007-01-01T23:59:59.000Z

    W. & A. M. Segall, (2006) DNA repair, a novel antibacterialjunction-trapping peptides induce DNA damage and chromosomePeptide inhibitors of DNA cleavage by tyrosine recombinases

  12. Motor Repair Tech Brief | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels Data Center Home Page onYouTube YouTube Note: Since the.pdfBreaking ofOil &315_ArnibanPriorityof EnergyDepartmentRepair Tech Brief Motor

  13. Project Year Project Title

    E-Print Network [OSTI]

    Gray, Jeffrey J.

    Project Year 2011-2012 Project Title Using M-Health and GIS Technology in the Field to Improve-specialized, but practically useless skill. Solution One goal of this summer's Applied Geographic Information Systems in Public lessons about observational epidemiology. Technologies Used Geographic Info System (GIS), Blackboard

  14. Project Fact Sheet Project Update

    E-Print Network [OSTI]

    & Figures: Budget: Ł51,074,000 Funding Source: Capital Plan Construction Project Programme: Start on SiteProject Fact Sheet Project Update: Project Brief: The concept of the new scheme is to redevelop Gardens project http://www.imperial.ac.uk/princesgardens/ Construction Project Team: Project Facts

  15. Coherent testing and simulation of composite blade repair

    E-Print Network [OSTI]

    McNichols, Brian Glenn

    1997-01-01T23:59:59.000Z

    The objective of this research program is to experimentally and computationally determine the static and fatigue response for two methods of repair to an E/Glass-Epoxy sandwich laminate. The proposed methods of repair are a scarf and overlap patch...

  16. Computational model of aortic valve surgical repair using grafted pericardium

    E-Print Network [OSTI]

    1 Computational model of aortic valve surgical repair using grafted pericardium Peter E. Hammer1, aortic valve repair, membrane, surgical planning, leaflet graft, pericardium ABSTRACT Aortic valve leaflets. Difficulty is largely due to the complex geometry and function of the valve and the lower

  17. Quality electric motor repair: A guidebook for electric utilities

    SciTech Connect (OSTI)

    Schueler, V.; Douglass, J.

    1995-08-01T23:59:59.000Z

    This guidebook provides utilities with a resource for better understanding and developing their roles in relation to electric motor repair shops and the industrial and commercial utility customers that use them. The guidebook includes information and tools that utilities can use to raise the quality of electric motor repair practices in their service territories.

  18. Project Funding

    Broader source: Energy.gov [DOE]

    Federal energy projects require funding to generate results. Carefully matching available funding options with specific project needs can make the difference between a stalled, unfunded project and a successful project generating energy and cost savings.

  19. Using instrument scraper surveys for corrosion repair

    SciTech Connect (OSTI)

    Akhnoukh, S.R.; Baghabrah, M.A. (Aramco (SA))

    1990-07-01T23:59:59.000Z

    This paper reports on a program for overall pipe line repair. This program was implemented to maintain pipe line integrity and for identifying problem areas which require reconditioning or replacing by: reviewing pipe line leak history; checking periodically lifetime expectancy and integrity of pipe coatings; using cathodic protection annual survey results to locate low potential areas (close-interval survey is needed to identify the exact location of corrosion); and hydrotesting the pipe line (using leaks or ruptures from the hydrotest to identify problem areas). The pipe line revalidation plan is insufficient for identifying pipe line leaks. Instrumented pig testing provides more accurate and reliable ways of testing the pipe line for internal or external corrosion or defects.

  20. A tissue engineering strategy for integrative cartilage repair

    E-Print Network [OSTI]

    Mroszczyk, Keri A

    2014-01-01T23:59:59.000Z

    Tissue engineering for cartilage repair is a promising approach for improving the healing of articular defects, as biomaterials and growth factors can be supplied directly to a focal lesion. However, integrating neo-tissue ...

  1. Optimizing chondrogenic factors and protein delivery methods for cartilage repair

    E-Print Network [OSTI]

    Florine, Emily Marie

    2012-01-01T23:59:59.000Z

    Joint injuries are common and often result in damage to cartilage, which has a limited ability to repair itself. Tissue engineering is a promising approach for improving cartilage healing in which biomaterials and chemical ...

  2. Incremental temporal reasoning in job shop scheduling repair

    E-Print Network [OSTI]

    Huang, Y.

    A working predictive schedule can be useless because of the various external or internal disruptions in a job shop. Total rescheduling may cause problems such as shop floor nervousness. Thus, the job shop scheduling repair ...

  3. Availability Analysis of Repairable Computer Systems and Stationarity Detection

    E-Print Network [OSTI]

    Sericola, Bruno

    Availability Analysis of Repairable Computer Systems and Stationarity Detection Bruno Sericola AbstractĐPoint availability and expected interval availability are dependability measures respectively in this paper a new algorithm to compute these two availability measures. This algorithm is based

  4. Intermediate hearth repair technique at Thyssen Stahl AG

    SciTech Connect (OSTI)

    Kowalski, W.; Bachhofen, H.J.; Ruether, P.; Ballewski, T. [Thyssen Stahl AG, Duisburg (Germany)

    1996-12-31T23:59:59.000Z

    Nowadays various techniques for the fastest possible intermediate repair and/or emplacement of refractory materials above the tuyere level allow a significant extension of furnace campaign life. The latter are hence now exclusively determined by the service life of the hearth. The improvement of hearth monitoring and the estimation of residual brick strength of the refractory lining on the basis of temperature measurements in the hearth enable the location of individual zones of premature wear. These measurement methods, which were developed by Thyssen Stahl AG, aid the decision to undertake selective repair of the hearth. Three areas of repair are differentiated: taphole zone; hearth wall, localized; and hearth wall, extensive. This hearth repair method is described in this report using the example of hearth refurbishing blast furnace 8, Hamborn.

  5. Repair Sequences in American Learners of German Interlanguage

    E-Print Network [OSTI]

    Wisbey, Evelyn

    2010-04-25T23:59:59.000Z

    This study in Conversation Analysis investigates the organization of other-initiated repair sequences in American learners of German, i.e., it examines how learners deal with troubles in hearing or understanding that they ...

  6. To: Mansueti, Lawrence Subject: RE: Pepco Scheduled Line Repair...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Sent: Monday, January 29, 2007 6:28 PM To: Mansueti, Lawrence Subject: RE: Pepco Scheduled Line Repair Dec. 1-20, 2006 Larry, Regarding the planned line outage,...

  7. Providing protection: Agencies receive funding to repair, upgrade dams

    E-Print Network [OSTI]

    Wythe, Kathy

    2009-01-01T23:59:59.000Z

    Story by Kathy Wythe tx H2O | pg. 26 Providing protection Agencies receive funding to repair, upgrade dams along with local partners, can apply for grant funds, he said. Construction of the dams began through four federal authorizations..., called floodwater retarding structures and built mostly in rural areas during the 1950s to 1970s, are aging and need repairing. Others now protect urban areas that have developed downstream and need upgrading to meet more stringent safety standards...

  8. Project Controls

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    1997-03-28T23:59:59.000Z

    Project controls are systems used to plan, schedule, budget, and measure the performance of a project/program. The cost estimation package is one of the documents that is used to establish the baseline for project controls. This chapter gives a brief description of project controls and the role the cost estimation package plays.

  9. Project Fact Sheet Project Update

    E-Print Network [OSTI]

    Project Fact Sheet Project Update: Project Brief: The works cover the refurbishment of floors 4, 5, with `wet' labs for molecular biology, materials characterisation, cell culture and flow studies, and `dry operating theatre. The Bionanotechnology Centre is one of the projects funded from the UK Government's ÂŁ20

  10. Project Fact Sheet Project Brief

    E-Print Network [OSTI]

    .union.ic.ac.uk/marketing/building Construction Project Team: Project Facts & Figures: Budget: Ł1,400,000 Funding Source: Capital PlanProject Fact Sheet Project Brief: In the first phase of the Union Building re that it adapts to meet the needs of a changing student body. The re-development plans are grounded in a full

  11. Project Fact Sheet Project Brief

    E-Print Network [OSTI]

    Facts & Figures: Budget: Ł3,500,000 Funding Source: SRIF III Construction Project Programme: StartProject Fact Sheet Project Brief: This project refurbished half of the 5th and 7th floors of work includes: · Building fabric replacement and revised space planning · New mechanical and electrical

  12. Polymer nanocomposites for high-temperature composite repair

    SciTech Connect (OSTI)

    Sheng, Xia

    2008-12-01T23:59:59.000Z

    A novel repair agent for resin-injection repair of advanced high temperature composites was developed and characterized. The repair agent was based on bisphenol E cyanate ester (BECy) and reinforced with alumina nanoparticles. To ensure good dispersion and compatibility with the BECy matrix in nanocomposites, the alumina nanoparticles were functionalized with silanes. The BECy nanocomposites, containing bare and functionalized alumina nanoparticles, were prepared and evaluated for their thermal, mechanical, rheological, and viscoelastic properties. The monomer of BECy has an extremely low viscosity at ambient temperature, which is good for processability. The cured BECy polymer is a highly cross-linked network with excellent thermal mechanical properties, with a high glass transition temperature (T{sub g}) of 270 C and decomposition temperature above 350 C. The incorporation of alumina nanoparticles enhances the mechanical and rheological properties of the BECy nanocomposites. Additionally, the alumina nanoparticles are shown to catalyze the cure of BECy. Characterization of the nanocomposites included dynamic mechanical analysis, differential scanning calorimetry, thermogravimetric analysis, rheological and rheokinetic evaluation, and transmission electron microscopy. The experimental results show that the BECy nanocomposite is a good candidate as repair agent for resin-injection repair applications.

  13. Repairs for damaged bolt holes in continuous fiber reinforced plastics 

    E-Print Network [OSTI]

    Copps, Kevin Daniel

    1992-01-01T23:59:59.000Z

    repair method for damaged bolt holes in such composites. Bolt holes in three types of graphite-epoxy were purposely damaged and then repaired. Each was tested to characterize its static and fatigue behavior. The tests used a special fixture to simulate... composite joints . Bearing-bypass ratio can change the failure mode of bolted composite joints 7 Drilling defects in graphite-epoxy coupons 12 26 The exit side of a IM7/8551-7A 18 ply tape coupon showing the damage due to drilling 27 9 Resin filled...

  14. Development of criteria for fatigue repairs in bridge girders damaged by out-of-plane distortion

    E-Print Network [OSTI]

    Wilson, Scott David

    1994-01-01T23:59:59.000Z

    repaired and unrepaired cracks along the longitudinal web-to-flange connection of a plate girder subjected to a linear bending stress to determine if repair by drilling holes is really necessary. The results of the finite element analyses...

  15. DNA Repair Decline During Mouse Spermiogenesis Results in the Accumulation of Heritable DNA Damage

    E-Print Network [OSTI]

    Marchetti, Francesco

    2008-01-01T23:59:59.000Z

    van Buul, D.G. de Rooij, DNA double-strand breaks and gamma-for the transition proteins in DNA strand break repair, FEBSBoissonneault, Stimulation of DNA repair by the spermatidal

  16. Characterization of Mg Binding to the DNA Repair ProteinApurinic...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Mg Binding to the DNA Repair Protein ApurinicApyrimidic Endonuclease 1 via Solid-State Mg NMR Spectroscopy. Characterization of Mg Binding to the DNA Repair Protein Apurinic...

  17. DNA repair decline during mouse spermiogenesis results in the accumulation of heritable DNA damage

    E-Print Network [OSTI]

    Marchetti, Francesco

    2008-01-01T23:59:59.000Z

    van Buul, D.G. de Rooij, DNA double-strand breaks and gamma-for the transition proteins in DNA strand break repair, FEBSBoissonneault, Stimulation of DNA repair by the spermatidal

  18. An engineering analysis of natural and biomimetic self-repair processes for solar energy harvesting

    E-Print Network [OSTI]

    Boghossian, Ardemis A. (Ardemis Anoush)

    2012-01-01T23:59:59.000Z

    Plants have evolved highly sophisticated mechanisms of self-repair to regenerate proteins that become photo-damaged over time. Key to this self-repair process is the reversible self-assembly of protein complexes, which is ...

  19. The Need for Language Repair The Reformation Algorithm Discussion Reformation: A Domain-Independent Algorithm

    E-Print Network [OSTI]

    St Andrews, University of

    The Need for Language Repair The Reformation Algorithm Discussion Reformation: A Domain of Edinburgh University of St Andrews, 27th November 2013 #12;The Need for Language Repair The Reformation Algorithm Discussion Outline 1 The Need for Language Repair 2 The Reformation Algorithm 3 Discussion #12;The

  20. Development of quick repairing technique for ceramic burner in hot stove of blast furnace

    SciTech Connect (OSTI)

    Kondo, Atsushi; Doura, Kouji; Nakamura, Hirofumi [Sumitomo Metal Industries, Ltd., Wakayama (Japan). Wakayama Steel Works

    1997-12-31T23:59:59.000Z

    Refractories of ceramic burner in hot stoves at Wakayama No. 4 blast furnace were damaged. There are only three hot stoves, so repairing must be done in a short. Therefore, a quick repairing technique for ceramic burners has been developed, and two ceramic burners were repaired in just 48 hours.

  1. HOW TO REPAIR A SECOND-ORDER SURFACE FOR COMPUTER

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    1 HOW TO REPAIR A SECOND-ORDER SURFACE FOR COMPUTER EXPERIMENTS BY KRIGING Astrid JOURDAN and analysis of computer experiments have been widely investigated in the past decade. Two approaches seem describes and compares them briefly in order to present a methodology for computer experiments based

  2. Thermosetting Polymer-Matrix Composites for Strucutral Repair Applications

    SciTech Connect (OSTI)

    William Kirby Goertzen

    2007-12-01T23:59:59.000Z

    Several classes of thermosetting polymer matrix composites were evaluated for use in structural repair applications. Initial work involved the characterization and evaluation of woven carbon fiber/epoxy matrix composites for structural pipeline repair. Cyanate ester resins were evaluated as a replacement for epoxy in composites for high-temperature pipe repair applications, and as the basis for adhesives for resin infusion repair of high-temperature composite materials. Carbon fiber/cyanate ester matrix composites and fumed silica/cyanate ester nanocomposites were evaluated for their thermal, mechanical, viscoelastic, and rheological properties as they relate to their structure, chemistry, and processing characteristics. The bisphenol E cyanate ester under investigation possesses a high glass transition temperature, excellent mechanical properties, and unique ambient temperature processability. The incorporate of fumed silica served to enhance the mechanical and rheological properties of the polymer and reduce thermal expansion without sacrificing glass transition or drastically altering curing kinetics. Characterization of the composites included dynamic mechanical analysis, thermomechanical analysis, differential scanning calorimetry, thermogravimetric analysis, rheological and rheokinetic evaluation, and transmission electron microscopy.

  3. Development/Plasticity/Repair Identification of Nicotinic Acetylcholine Receptor Recycling

    E-Print Network [OSTI]

    Alford, Simon

    Development/Plasticity/Repair Identification of Nicotinic Acetylcholine Receptor Recycling and Its, University of Michigan, Ann Arbor, Michigan 48109 In the CNS, receptor recycling is critical for synaptic plasticity; however, the recycling of receptors has never been observed at peripheral synapses. Using a novel

  4. Corrosion Repair and Corrosion Protection of Reinforced Concrete Structures in

    E-Print Network [OSTI]

    Das, Suman

    11/14/2014 1 Corrosion Repair and Corrosion Protection of Reinforced Concrete Structures in Pulp and Paper Mills Vector Construction / Vector Corrosion Technologies www.vectorgroup.com www.vector-corrosion.com Presentation Outline · Introduction · Corrosion of Reinforced Concrete Structures · Protection of Chests

  5. Methods to alter levels of a DNA repair protein

    DOE Patents [OSTI]

    Petrini, John H.; Morgan, William Francis; Maser, Richard Scott; Carney, James Patrick

    2006-10-17T23:59:59.000Z

    An isolated and purified DNA molecule encoding a DNA repair protein, p95, is provided, as is isolated and purified p95. Also provided are methods of detecting p95 and DNA encoding p95. The invention further provides p95 knock-out mice.

  6. Breakthrough Technologies In Vivo Observation of Cavitation and Embolism Repair

    E-Print Network [OSTI]

    Holbrook, N. Michele

    Breakthrough Technologies In Vivo Observation of Cavitation and Embolism Repair Using Magnetic that approximately 10 vessels had cavitated during this time. Leaf water potentials decreased from 1.25 to 2.1 MPa cavitation. Refilling of xylem vessels occurred as soon as the lights were switched off, with the majority

  7. Development/Plasticity/Repair Group I Metabotropic Glutamate Receptors Control

    E-Print Network [OSTI]

    Grau, James

    Development/Plasticity/Repair Group I Metabotropic Glutamate Receptors Control Metaplasticity the spinal cord can support several forms of plasticity, including response­outcome (instrumental) learning. This inhibi- tion of plasticity in spinal learning is itself a form of plasticity that requires i

  8. Complications of Endovascular Repair of Abdominal Aortic Aneurysms: A Review

    SciTech Connect (OSTI)

    Katzen, Barry T. [Baptist Cardiac and Vascular Institute, Baptist Health Systems, Department of Interventional Radiology, Florida (United States)], E-mail: barryk@baptisthealth.net; MacLean, Alexandra A. [New York Hospital-Queens, Department of Surgery (United States)

    2006-12-15T23:59:59.000Z

    The endovascular procedure for repair of abdominal aortic aneurysms has had an enormous impact on the treatment of this challenging disease. Complications, however, do occur and it is important to have a thorough understanding of the array of complications and appropriate management strategies. In this review of endovascular complications, we describe early and late complications paying particular attention to preventive, treatment and surveillance strategies.

  9. Magnesium Projects

    Broader source: Energy.gov (indexed) [DOE]

    cyberinfrastructure projects and will be augmented by original research in Computer Science and Software Engineering towards the creation of large, distributed, autonomic and...

  10. Project Construction

    Broader source: Energy.gov [DOE]

    Integrating renewable energy into Federal new construction or major renovations requires effective structuring of the construction team and project schedule. This overview discusses key construction team considerations for renewable energy as well as timing and expectations for the construction phase. The project construction phase begins after a project is completely designed and the construction documents (100%) have been issued. Construction team skills and experience with renewable energy technologies are crucial during construction, as is how the integration of renewable energy affects the project construction schedule.

  11. Combined Haploinsufficiency for ATM and RAD9 as a Factor in Cell Transformation, Apoptosis, and DNA Lesion Repair Dynamics

    E-Print Network [OSTI]

    Lesion Repair Dynamics Lubomir B. Smilenov, Howard B. Lieberman, Stephen A. Mitchell, Ronald A. Baker

  12. TidGen Power System Commercialization Project

    SciTech Connect (OSTI)

    Sauer, Christopher R. [President & CEO] [President & CEO; McEntee, Jarlath [VP Engineering & CTO] [VP Engineering & CTO

    2013-12-30T23:59:59.000Z

    ORPC Maine, LLC, a wholly-owned subsidiary of Ocean Renewable Power Company, LLC (collectively ORPC), submits this Final Technical Report for the TidGen® Power System Commercialization Project (Project), partially funded by the U.S. Department of Energy (DE-EE0003647). The Project was built and operated in compliance with the Federal Energy Regulatory Commission (FERC) pilot project license (P-12711) and other permits and approvals needed for the Project. This report documents the methodologies, activities and results of the various phases of the Project, including design, engineering, procurement, assembly, installation, operation, licensing, environmental monitoring, retrieval, maintenance and repair. The Project represents a significant achievement for the renewable energy portfolio of the U.S. in general, and for the U.S. marine hydrokinetic (MHK) industry in particular. The stated Project goal was to advance, demonstrate and accelerate deployment and commercialization of ORPC’s tidal-current based hydrokinetic power generation system, including the energy extraction and conversion technology, associated power electronics, and interconnection equipment capable of reliably delivering electricity to the domestic power grid. ORPC achieved this goal by designing, building and operating the TidGen® Power System in 2012 and becoming the first federally licensed hydrokinetic tidal energy project to deliver electricity to a power grid under a power purchase agreement in North America. Located in Cobscook Bay between Eastport and Lubec, Maine, the TidGen® Power System was connected to the Bangor Hydro Electric utility grid at an on-shore station in North Lubec on September 13, 2012. ORPC obtained a FERC pilot project license for the Project on February 12, 2012 and the first Maine Department of Environmental Protection General Permit issued for a tidal energy project on January 31, 2012. In addition, ORPC entered into a 20-year agreement with Bangor Hydro Electric Company on January 1, 2013 for up to 5 megawatts at a price of $215/MWh, escalating at 2.0% per year.

  13. Testing and evaluation of grout repaired tubular members 

    E-Print Network [OSTI]

    Nunn, John Mansfield

    1992-01-01T23:59:59.000Z

    of Failed Weld Seam page 64 65 66 69 73 74 80 82 31 Ideahzed Tubular Dented Member for the Taby, Zhou, and the Parsanejad Methods. . . . . . . . . . . . . . , . 92 32 Dent Geometry for the Elhnas Method 96 33 Experimental Ultimate Capamty vs P... commonly used to repiur damaged tubular members. These include 1 ) welding a sleeve around the outside of the member in the location of the damage, 2 ) applying an externally grouted clamp, and 3 ) applying internal grout Ideally, the repair method...

  14. Waste-audit study: Automotive repairs. Final report

    SciTech Connect (OSTI)

    Toy, W.M.

    1987-05-01T23:59:59.000Z

    This document reports on a waste audit study which investigated and analyzed the automotive-repair industry in California. It assessed current waste-management practices and developed specific on-site and off-site waste-treatment recycling alternatives. The conclusions identify and address illegal disposal practices. Recommendations include the segregation of specific wastes for proper disposal and economic analysis of on-site waste-recycling equipment.

  15. Project Manager

    Broader source: Energy.gov [DOE]

    A successful candidate in this position will serve as a project manager in the Fuel Cell Technologies Office in the DOE-EERE Office of Transportation responsible for a wide variety of highly...

  16. RENOTER Project

    Broader source: Energy.gov [DOE]

    Overview of French project on thermoelectric waste heat recovery for cars and trucks with focus on cheap, available, efficient, and sustainable TE materials, as well as efficient material integration and production process.

  17. Automobile Repair Shop In 1987, the Alaska Health Project has performed an audit of an automobile

    E-Print Network [OSTI]

    Part 268). 2) Disposal in a authorized high-temperature incinerator. 3) Disposal to an authorized assumes incineration is the disposal method. If the waste is disposed of in a landfill or by recycling, costs may be reduced. However, considering the new solvent ban on land disposal incineration

  18. Return on Investment for State Highway Projects 25th Annual Transportation Research Conference

    E-Print Network [OSTI]

    Minnesota, University of

    Return on Investment for State Highway Projects 25th Annual Transportation Research Conference May ­ Maintain and repair existing roads and bridges · Grow the Economy by Making Your Transportation Investments;8 · Describes strategies states can use to achieve the greatest outcomes at the least cost with transportation

  19. Cloudnet Project

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Hogan, Robin

    Cloudnet is a research project supported by the European Commission. This project aims to use data obtained quasi-continuously for the development and implementation of cloud remote sensing synergy algorithms. The use of active instruments (lidar and radar) results in detailed vertical profiles of important cloud parameters which cannot be derived from current satellite sensing techniques. A network of three already existing cloud remote sensing stations (CRS-stations) will be operated for a two year period, activities will be co-ordinated, data formats harmonised and analysis of the data performed to evaluate the representation of clouds in four major european weather forecast models.

  20. Using 3D Painting to Build and Repair Parts | GE Global Research

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    a part or add material to repair an existing part. Cold spray is part of GE's expanded additive manufacturing toolkit. An error occurred. Unable to execute Javascript. nteneh...

  1. Brain necrosis after fractionated radiation therapy: Is the halftime for repair longer than we thought?

    SciTech Connect (OSTI)

    Bender, Edward T. [Department of Human Oncology, University of Wisconsin-Madison, School of Medicine and Public Health, 600 Highland Avenue, Madison, Wisconsin 53792 (United States)

    2012-11-15T23:59:59.000Z

    Purpose: To derive a radiobiological model that enables the estimation of brain necrosis and spinal cord myelopathy rates for a variety of fractionation schemes, and to compare repair effects between brain and spinal cord. Methods: Sigmoidal dose response relationships for brain radiation necrosis and spinal cord myelopathy are derived from clinical data using nonlinear regression. Three different repair models are considered and the repair halftimes are included as regression parameters. Results: For radiation necrosis, a repair halftime of 38.1 (range 6.9-76) h is found with monoexponential repair, while for spinal cord myelopathy, a repair halftime of 4.1 (range 0-8) h is found. The best-fit alpha beta ratio is 0.96 (range 0.24-1.73)Conclusions: A radiobiological model that includes repair corrections can describe the clinical data for a variety of fraction sizes, fractionation schedules, and total doses. Modeling suggests a relatively long repair halftime for brain necrosis. This study suggests that the repair halftime for late radiation effects in the brain may be longer than is currently thought. If confirmed in future studies, this may lead to a re-evaluation of radiation fractionation schedules for some CNS diseases, particularly for those diseases where fractionated stereotactic radiation therapy is used.

  2. Spent Nuclear Fuel project, project management plan

    SciTech Connect (OSTI)

    Fuquay, B.J.

    1995-10-25T23:59:59.000Z

    The Hanford Spent Nuclear Fuel Project has been established to safely store spent nuclear fuel at the Hanford Site. This Project Management Plan sets forth the management basis for the Spent Nuclear Fuel Project. The plan applies to all fabrication and construction projects, operation of the Spent Nuclear Fuel Project facilities, and necessary engineering and management functions within the scope of the project

  3. ERIS Project 

    E-Print Network [OSTI]

    Hunter, Philip

    repositories. If these (generally) smaller institutions wished to continue to have access to these hosted repository spaces after the end of the project, it was proposed that these repository-lite services would be administered by the SDLC (the Scottish Digital...

  4. Repair welding of fusion reactor components. Final technical report

    SciTech Connect (OSTI)

    Chin, B.A.; Wang, C.A.

    1997-09-30T23:59:59.000Z

    The exposure of metallic materials, such as structural components of the first wall and blanket of a fusion reactor, to neutron irradiation will induce changes in both the material composition and microstructure. Along with these changes can come a corresponding deterioration in mechanical properties resulting in premature failure. It is, therefore, essential to expect that the repair and replacement of the degraded components will be necessary. Such repairs may require the joining of irradiated materials through the use of fusion welding processes. The present ITER (International Thermonuclear Experimental Reactor) conceptual design is anticipated to have about 5 km of longitudinal welds and ten thousand pipe butt welds in the blanket structure. A recent study by Buende et al. predict that a failure is most likely to occur in a weld. The study is based on data from other large structures, particularly nuclear reactors. The data used also appear to be consistent with the operating experience of the Fast Flux Test Facility (FFTF). This reactor has a fuel pin area comparable with the area of the ITER first wall and has experienced one unanticipated fuel pin failure after two years of operation. The repair of irradiated structures using fusion welding will be difficult due to the entrapped helium. Due to its extremely low solubility in metals, helium will diffuse and agglomerate to form helium bubbles after being trapped at point defects, dislocations, and grain boundaries. Welding of neutron-irradiated type 304 stainless steels has been reported with varying degree of heat-affected zone cracking (HAZ). The objectives of this study were to determine the threshold helium concentrations required to cause HAZ cracking and to investigate techniques that might be used to eliminate the HAZ cracking in welding of helium-containing materials.

  5. Genome-Wide Identification and 3D Modeling of Proteins involved in DNA Damage Recognition and Repair (Final Report)

    SciTech Connect (OSTI)

    Ruben A. Abagyan, PhD

    2004-04-15T23:59:59.000Z

    OAK-B135 DNA Damage Recognition and Repair (DDR and R) proteins play a critical role in cellular responses to low-dose radiation and are associated with cancer. the authors have performed a systematic, genome-wide computational analysis of genomic data for human genes involved in the DDR and R process. The significant achievements of this project include: (1) Construction of the computational pipeline for searching DDR and R genes, building and validation of 3D models of proteins involved in DDR and R; (2) Functional and structural annotation of the 3D models and generation of comprehensive lists of suggested knock-out mutations; (3) Important improvement of macromolecular docking technology and its application to predict the DNA-Protein complex conformation; (4) Development of a new algorithm for improved analysis of high-density oligonucleotide arrays for gene expression profiling; (5) Construction and maintenance of the DNA Damage Recognition and Repair Database; and (6) Producing 14 research papers (10 published and 4 in preparation).

  6. Blade reliability collaborative : collection of defect, damage and repair data.

    SciTech Connect (OSTI)

    Ashwill, Thomas D.; Ogilvie, Alistair B.; Paquette, Joshua A.

    2013-04-01T23:59:59.000Z

    The Blade Reliability Collaborative (BRC) was started by the Wind Energy Technologies Department of Sandia National Laboratories and DOE in 2010 with the goal of gaining insight into planned and unplanned O&M issues associated with wind turbine blades. A significant part of BRC is the Blade Defect, Damage and Repair Survey task, which will gather data from blade manufacturers, service companies, operators and prior studies to determine details about the largest sources of blade unreliability. This report summarizes the initial findings from this work.

  7. Rebels, Activists, and Repairers: Youth and Social Change in Africa

    E-Print Network [OSTI]

    Pollock, Colleen

    2011-12-31T23:59:59.000Z

    #3;answer#3;questions#3; (Irvine#3;1978)#3;(i.e.#3;?“what#3;does#3;the#3;ducky#3;say??”)#3;because#3;such#3;questioning#3;indicates#3;a#3;riddle#3;with#3; a#3;trick#3;answer#3;or#3;a#3;direct#3;challenge,#3;and#3;it#3;is#3;considered#3;an#3;insult#3... Date Defended: May 17, 2011 #3; #3; #3; #3; #3; #3; ii #3; The Thesis Committee for Colleen Pollock certifies that this is the approved version of the following thesis: REBELS, ACTIVISTS, AND REPAIRERS: THE ROLE OF YOUTH IN SOCIAL CHANGE...

  8. Repairs for damaged bolt holes in continuous fiber reinforced plastics

    E-Print Network [OSTI]

    Copps, Kevin Daniel

    1992-01-01T23:59:59.000Z

    ANALYSIS Model Definition Analysis Results Comparing Lay-ups Pin-conditions vs. clamping pressure Stress interactions Repair material CONCLUSIONS REFERENCES APPENDIX VITA 21 22 23 24 25 25 25 26 27 27 28 29 30 30 31 33 33 34 34... under pin conditions . 35 16 A modification was made to the test fixture to relieve the high cyclic stresses on the bolt 37 vu 17 When clamping pressure is applied, a normally drilled, unrepaired, fastener hole is stronger and tends to fail in net...

  9. Project Fact Sheet Project Brief

    E-Print Network [OSTI]

    Name: Centre for Assisted Robotic Surgery Number: BESS1002b Project Champion: Professor Guang-Zong Yang of the refurbishment is to renew and expand the laboratory space for Robotic Assisted Surgery at the South Kensington Campus as par to the Hamlyn Centre for Robotic Surgery. The overall programme incorpo- rates both core

  10. Repairs to silence Tower bells | The Daily Texan http://dailytexanonline.com/news/2012/09/27/repairs-to-silence-tower-bells 2 of 4 10/2/2012 8:55 AM

    E-Print Network [OSTI]

    John, Lizy Kurian

    Repairs to silence Tower bells | The Daily Texan http://dailytexanonline.com/news/2012/09/27/repairs-to-silence-tower-bells 2 of 4 10/2/2012 8:55 AM #12;Repairs to silence Tower bells | The Daily Texan http://dailytexanonline.com/news/2012/09/27/repairs-to-silence-tower-bells 3 of 4 10/2/2012 8

  11. Cooperative Repair with Minimum-Storage Regenerating Codes for Distributed Storage

    E-Print Network [OSTI]

    Li, Baochun

    Cooperative Repair with Minimum-Storage Regenerating Codes for Distributed Storage Jun Li, Baochun--Distributed storage systems store redundant data to tolerate failures of storage nodes and lost data should be repaired when storage nodes fail. A class of MDS codes, called minimum- storage regenerating (MSR) codes

  12. 4 CONCRETE REPAIR BULLETIN MAY/JUNE2001 Laser Profilometry for

    E-Print Network [OSTI]

    Maerz, Norbert H.

    4 CONCRETE REPAIR BULLETIN MAY/JUNE2001 Laser Profilometry for Concrete Substrate Characterization and resins are non- corrosive, they are ideally suited for the repair and retrofitting of concrete bridges highly upon the quality of the bond between the concrete and the laminate. Experience has shown that when

  13. On the Design of an Interactive, Patient-Specific Surgical Simulator for Mitral Valve Repair

    E-Print Network [OSTI]

    On the Design of an Interactive, Patient-Specific Surgical Simulator for Mitral Valve Repair Neil A repair of the mitral valve is a difficult procedure that is often avoided in favor of less effective valve replacement because of the associated technical challenges facing non-expert surgeons

  14. Bridge Damage and Repair Costs from Hurricane Katrina Jamie Padgett1

    E-Print Network [OSTI]

    Padgett, Jamie Ellen

    Bridge Damage and Repair Costs from Hurricane Katrina Jamie Padgett1 ; Reginald DesRoches2 ; Bryant caused significant damage to the transportation system in the Gulf Coast region. The overall cost to repair or replace the bridges damaged during the hurricane is estimated at over $1 billion. This paper

  15. Automatic Repair of Buggy If Conditions and Missing Preconditions with SMT

    E-Print Network [OSTI]

    Paris-Sud XI, Université de

    Automatic Repair of Buggy If Conditions and Missing Preconditions with SMT Favio De into a Satisfiability Modulo Theory (SMT) problem, and translating the SMT result ­ if there exists one ­ into a source, Verification Keywords Automatic repair, test suite, buggy if condition, missing pre- condition, SMT, angelic

  16. Bone Marrow Stimulation of the Medial Femoral Condyle Produces Inferior Cartilage and Bone Repair Compared to the Trochlea in a

    E-Print Network [OSTI]

    Buschmann, Michael

    Bone Marrow Stimulation of the Medial Femoral Condyle Produces Inferior Cartilage and Bone Repair femoral condylar (MFC) versus femoral trochlear (TR) defects 3 months after bone marrow stimulation: cartilage repair; medial femoral condyle; trochlea; bone marrow stimulation; meniscus degeneration Articular

  17. ITERATIVE REPAIR PLANNING FOR SPACECRAFT OPERATIONS USING THE ASPEN SYSTEM Gregg Rabideau, Russell Knight, Steve Chien, Alex Fukunaga, Anita Govindjee

    E-Print Network [OSTI]

    Schaffer, Steven

    ITERATIVE REPAIR PLANNING FOR SPACECRAFT OPERATIONS USING THE ASPEN SYSTEM Gregg Rabideau, Russell and Planning Environment (ASPEN). ASPEN encodes complex spacecraft knowledge of operability constraints, flight generation of low level spacecraft sequences. Using a technique called iterative repair, ASPEN classifies

  18. Injection repair of carbon fiber/bismaleimide composite panels with bisphenol E cyanate ester resin

    SciTech Connect (OSTI)

    Thunga, Mahendra [Ames Laboratory; Bauer, Amy [Iowa State University; Obusek, Kristine [Fleet Readiness Center East; Meilunas, Ray [Naval Air Warfare Center Aircraft Division; Akinc, Mufit [Ames Laboratory; Kessler, Michael R [Ames Laboratory

    2014-08-01T23:59:59.000Z

    Resin injection of bisphenol E cyanate ester, a low viscosity resin that cures into a high temperature thermoset polymer, is investigated as a reliable repair method to restore strength and stiffness in delaminated carbon fiber/bismaleimide composites used in aircraft panels. The influence of temperature on the viscosity of the uncured resin was measured to optimize the injection conditions for high resin infiltration into the delaminations. The repair efficiency of the resin was evaluated by varying the panel thickness and the method by which the delamination damage was created in the composite specimens. Ultrasonic scanning (C-scan), flash thermography images, and cross-section analysis of repaired panels revealed excellent resin infiltration into the damaged region. Evaluation of mechanical repair efficiency using both bending stiffness and in-plain compressive strength of the composite panels as the repair metrics showed values exceeding 100%.

  19. Repair of gamma-ray-induced DNA base damage in xeroderma pigmentosum cells

    SciTech Connect (OSTI)

    Fornace, A.J. Jr.; Dobson, P.P.; Kinsella, T.J.

    1986-04-01T23:59:59.000Z

    The repair of DNA damage produced by /sup 137/Cs gamma irradiation was measured with a preparation from Micrococcus luteus containing DNA damage-specific endonucleases in combination with alkaline elution. The frequency of these endonuclease sensitive sites (ESS) was determined after 54 or 110 Gy of oxic irradiation in normal and xeroderma pigmentosum (XP) fibroblasts from complementation groups A, C, D, and G. Repair was rapid in all cell strains with greater than 50% repair after 1.5 h of repair incubation. At later repair times, 12-17 h, more ESS remained in XP than in normal cells. The frequency of excess ESS in XP cells was approximately 0.04 per 10(9) Da of DNA per Gy which was equivalent to 10% of the initial ESS produced. The removal of ESS was comparable in XP cells with normal radiosensitivity and XP3BR cells which have been reported to be moderately radiosensitive.

  20. PROJECT SUMMARY

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy ChinaofSchaeferAprilOverviewEfficiencyofHSSPIAProperty Management PlanPROJECT SUMMARY 1

  1. Hallmark Project

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy ChinaofSchaefer To: CongestionDevelopmentHEADQUARTERSOutreachApril 23, 2013Project

  2. Project Management

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)IntegratedSpeedingTechnical News,Program DirectionProject ATHENA creates

  3. Project Overview

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)IntegratedSpeedingTechnical News,Program DirectionProject ATHENAManagement

  4. Projects | ORNL

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)IntegratedSpeedingTechnical News,Program DirectionProject ATHENAManagementIn ThisPages

  5. Project Gnome

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible forPortsmouth/Paducah47,193.70 Hg MercuryProject Final Report: HPC-Colony IIProject Gnome

  6. Project Title

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible forPortsmouth/Paducah47,193.70 Hg MercuryProject FinalFluids |Storage Research and

  7. NEPA COMPLIANCE SURVEY Project Information Project Title:

    Broader source: Energy.gov (indexed) [DOE]

    Boxes Date: Nov. 11 , 2010 DOE Code: 6740.010.00000 Contractor Code: 8067-451 Project Lead: Anthony Bowler Project Overview 1. Brief project description include anything that...

  8. Method of tissue repair using a composite material

    DOE Patents [OSTI]

    Hutchens, Stacy A; Woodward, Jonathan; Evans, Barbara R; O'Neill, Hugh M

    2014-03-18T23:59:59.000Z

    A composite biocompatible hydrogel material includes a porous polymer matrix, the polymer matrix including a plurality of pores and providing a Young's modulus of at least 10 GPa. A calcium comprising salt is disposed in at least some of the pores. The porous polymer matrix can comprise cellulose, including bacterial cellulose. The composite can be used as a bone graft material. A method of tissue repair within the body of animals includes the steps of providing a composite biocompatible hydrogel material including a porous polymer matrix, the polymer matrix including a plurality of pores and providing a Young's modulus of at least 10 GPa, and inserting the hydrogel material into cartilage or bone tissue of an animal, wherein the hydrogel material supports cell colonization in vitro for autologous cell seeding.

  9. Neurological Complications Following Endoluminal Repair of Thoracic Aortic Disease

    SciTech Connect (OSTI)

    Morales, J. P.; Taylor, P. R.; Bell, R. E.; Chan, Y. C. [Guy's and St. Thomas' Foundation Hospital NHS Trust, Department of Vascular Surgery (United Kingdom); Sabharwal, T. [Guy's and St. Thomas' Foundation Hospital NHS Trust, Department of Interventional Radiology (United Kingdom); Carrell, T. W. G. [Guy's and St. Thomas' Foundation Hospital NHS Trust, Department of Vascular Surgery (United Kingdom); Reidy, J. F. [Guy's and St. Thomas' Foundation Hospital NHS Trust, Department of Interventional Radiology (United Kingdom)], E-mail: John.Reidy@gstt.nhs.uk

    2007-09-15T23:59:59.000Z

    Open surgery for thoracic aortic disease is associated with significant morbidity and the reported rates for paraplegia and stroke are 3%-19% and 6%-11%, respectively. Spinal cord ischemia and stroke have also been reported following endoluminal repair. This study reviews the incidence of paraplegia and stroke in a series of 186 patients treated with thoracic stent grafts. From July 1997 to September 2006, 186 patients (125 men) underwent endoluminal repair of thoracic aortic pathology. Mean age was 71 years (range, 17-90 years). One hundred twenty-eight patients were treated electively and 58 patients had urgent procedures. Anesthesia was epidural in 131, general in 50, and local in 5 patients. Seven patients developed paraplegia (3.8%; two urgent and five elective). All occurred in-hospital apart from one associated with severe hypotension after a myocardial infarction at 3 weeks. Four of these recovered with cerebrospinal fluid (CSF) drainage. One patient with paraplegia died and two had permanent neurological deficit. The rate of permanent paraplegia and death was 1.6%. There were seven strokes (3.8%; four urgent and three elective). Three patients made a complete recovery, one had permanent expressive dysphasia, and three died. The rate of permanent stroke and death was 2.1%. Endoluminal treatment of thoracic aortic disease is an attractive alternative to open surgery; however, there is still a risk of paraplegia and stroke. Permanent neurological deficits and death occurred in 3.7% of the patients in this series. We conclude that prompt recognition of paraplegia and immediate insertion of a CSF drain can be an effective way of recovering spinal cord function and improving the prognosis.

  10. Project Management Lessons Learned

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-08-05T23:59:59.000Z

    The guide supports DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, and aids the federal project directors and integrated project teams in the execution of projects.

  11. Effect of multiple repairs in girth welds of pipelines on the mechanical properties

    SciTech Connect (OSTI)

    Vega, O.E.; Hallen, J.M. [Departamento de Ingenieria Metalurgica, ESIQIE-IPN, Laboratorios Pesados de Metalurgia, UPALM, Zacatenco, C.P. 07738, Mexico D.F. (Mexico); Villagomez, A. [Construcciones Maritimas Mexicanas, CMM-PROTEXA, Av. Periferica s/n, Fracc. Lomas de Holche, C.P. 24120, Cd. del Carmen, Campeche (Mexico); Contreras, A. [Instituto Mexicano del Petroleo, Investigacion en Ductos, Corrosion y Materiales, Eje Central Lazaro Cardenas Norte 152 Col. San Bartolo Atepehuacan, C.P. 07730, Mexico D.F. (Mexico)], E-mail: acontrer@imp.mx

    2008-10-15T23:59:59.000Z

    This work presents the results of multiple weld repairs in the same area in seamless API X-52 microalloyed steel pipe. Four conditions of shielded metal arc welding repairs and one as-welded specimen of the girth weld were characterized to determine changes in the microstructure, grain size in the heat affected zone, and to evaluate their effect on the mechanical properties of the weld joints. The mechanical properties by means of tension tests, Charpy-V impact resistance and Vickers hardness of the welds were analyzed. The results indicate that significant changes are not generated in the microstructural constituents of the heat affected zone. Grain growth in the heat affected zone at the specimen mid-thickness with the number of repairs was observed. Tensile strength of the weld joints meets the requirement of the API 1104 standard even after the fourth weld repair. Significant reduction in Charpy-V impact resistance with the number of weld repairs was found when the notch location was in the intersection of the fusion line with the specimen mid-thickness. A significant increase in the Vickers hardness of the heat affected zone occurred after the first repair and a gradual decrease in the Vickers hardness occurred as the number of repairs increases.

  12. Fabrication Flaw Density and Distribution In Repairs to Reactor Pressure Vessel and Piping Welds

    SciTech Connect (OSTI)

    GJ Schuster, FA Simonen, SR Doctor

    2008-04-01T23:59:59.000Z

    The Pacific Northwest National Laboratory is developing a generalized fabrication flaw distribution for the population of nuclear reactor pressure vessels and for piping welds in U.S. operating reactors. The purpose of the generalized flaw distribution is to predict component-specific flaw densities. The estimates of fabrication flaws are intended for use in fracture mechanics structural integrity assessments. Structural integrity assessments, such as estimating the frequency of loss-of-coolant accidents, are performed by computer codes that require, as input, accurate estimates of flaw densities. Welds from four different reactor pressure vessels and a collection of archived pipes have been studied to develop empirical estimates of fabrication flaw densities. This report describes the fabrication flaw distribution and characterization in the repair weld metal of vessels and piping. This work indicates that large flaws occur in these repairs. These results show that repair flaws are complex in composition and sometimes include cracks on the ends of the repair cavities. Parametric analysis using an exponential fit is performed on the data. The relevance of construction records is established for describing fabrication processes and product forms. An analysis of these records shows there was a significant change in repair frequency over the years when these components were fabricated. A description of repair flaw morphology is provided with a discussion of fracture mechanics significance. Fabrication flaws in repairs are characterized using optimized-access, high-sensitivity nondestructive ultrasonic testing. Flaw characterizations are then validated by other nondestructive evaluation techniques and complemented by destructive testing.

  13. Livingston Solar Canopy Project The Project

    E-Print Network [OSTI]

    Delgado, Mauricio

    ,000 high efficiency solar panels on canopy structures over two major surface parking areasLivingston Solar Canopy Project The Project: This project entails the installation of more than 40. In conjunction with the existing 1.4 megawatt solar energy facility on this campus, this project will generate

  14. Information Visualization Graduate Project (Group Project)

    E-Print Network [OSTI]

    Rusu, Adrian

    Information Visualization Fall 2011 Graduate Project (Group Project) (100 points total) Handed out:59PM Research Article due by online submission on Sunday, December 11, 2011, 11:59PM Project Demo due last week of classes The idea of the project is to take the knowledge and background that you

  15. DNA Repair Alterations in Children With Pediatric Malignancies: Novel Opportunities to Identify Patients at Risk for High-Grade Toxicities

    SciTech Connect (OSTI)

    Ruebe, Claudia E., E-mail: claudia.ruebe@uks.e [Department of Radiation Oncology, Saarland University, Homburg/Saar (Germany); Fricke, Andreas; Schneider, Ruth; Simon, Karin; Kuehne, Martin; Fleckenstein, Jochen [Department of Radiation Oncology, Saarland University, Homburg/Saar (Germany); Graeber, Stefan [Institute of Medical Biometrics, Epidemiology and Medical Informatics, Saarland University, Homburg/Saar (Germany); Graf, Norbert [Department of Pediatric Hematology and Oncology, Saarland University, Homburg/Saar (Germany); Ruebe, Christian [Department of Radiation Oncology, Saarland University, Homburg/Saar (Germany)

    2010-10-01T23:59:59.000Z

    Purpose: To evaluate, in a pilot study, the phosphorylated H2AX ({gamma}H2AX) foci approach for identifying patients with double-strand break (DSB) repair deficiencies, who may overreact to DNA-damaging cancer therapy. Methods and Materials: The DSB repair capacity of children with solid cancers was analyzed compared with that of age-matched control children and correlated with treatment-related normal-tissue responses (n = 47). Double-strand break repair was investigated by counting {gamma}H2AX foci in blood lymphocytes at defined time points after irradiation of blood samples. Results: Whereas all healthy control children exhibited proficient DSB repair, 3 children with tumors revealed clearly impaired DSB repair capacities, and 2 of these repair-deficient children developed life-threatening or even lethal normal-tissue toxicities. The underlying mutations affecting regulatory factors involved in DNA repair pathways were identified. Moreover, significant differences in mean DSB repair capacity were observed between children with tumors and control children, suggesting that childhood cancer is based on genetic alterations affecting DSB repair function. Conclusions: Double-strand break repair alteration in children may predispose to cancer formation and may affect children's susceptibility to normal-tissue toxicities. Phosphorylated H2AX analysis of blood samples allows one to detect DSB repair deficiencies and thus enables identification of children at risk for high-grade toxicities.

  16. CtIP tetramer assembly is required for DNA-end resection and repair

    E-Print Network [OSTI]

    Davies, Owen R.; Forment, Josep V.; Sun, Meidai; Belotserkovskaya, Rimma; Coates, Julia; Galanty, Yaron; Demir, Mukerrem; Morton, Christopher; Rzechorzek, Neil; Jackson, Stephen P.; Pellegrini, Luca

    2015-01-05T23:59:59.000Z

    1     CtIP tetramer assembly is required for DNA-end resection and repair Owen R. Davies1,4*, Josep V. Forment1,2,3*, Meidai Sun1, Rimma Belotserkovskaya1,2, Julia Coates1,2, Yaron Galanty1,2, Mukerrem Demir1,2, Christopher Morton1... that a CtIP tetramer architecture is essential for effective DSB repair by homologous recombination. Keywords CtIP/RBBP8, double-strand DNA break repair, DNA-end resection, gene conversion, homologous recombination. 3...

  17. Functional Characterization of Kansl2 and Its Role in Mitochondrial DNA Repair and Maintenance

    E-Print Network [OSTI]

    Liau, Wei-Siang

    2012-01-01T23:59:59.000Z

    understanding of the maintenance and repair of the mtDNA,A is necessary for mtDNA maintenance and embryogenesis in1997). Mitochondrial DNA maintenance in vertebrates. Annu

  18. GENETIC AND MOLECULAR ANALYSIS OF DNA DAMAGE REPAIR AND TOLERANCE PATHWAYS.

    SciTech Connect (OSTI)

    SUTHERLAND, B.M.

    2001-07-26T23:59:59.000Z

    Radiation can damage cellular components, including DNA. Organisms have developed a panoply of means of dealing with DNA damage. Some repair paths have rather narrow substrate specificity (e.g. photolyases), which act on specific pyrimidine photoproducts in a specific type (e.g., DNA) and conformation (double-stranded B conformation) of nucleic acid. Others, for example, nucleotide excision repair, deal with larger classes of damages, in this case bulky adducts in DNA. A detailed discussion of DNA repair mechanisms is beyond the scope of this article, but one can be found in the excellent book of Friedberg et al. [1] for further detail. However, some DNA damages and paths for repair of those damages important for photobiology will be outlined below as a basis for the specific examples of genetic and molecular analysis that will be presented below.

  19. Plug repairs of marine glass fiber / vinyl ester laminates subjected to uniaxial tension

    E-Print Network [OSTI]

    Michelis, Alexandros

    2009-01-01T23:59:59.000Z

    Glass fiber/vinyl ester composite laminates are currently being used and proposed for the hulls, bulkheads, and superstructures of large ships. This thesis examines the effectiveness of the repair of such laminates using ...

  20. Review of Maintenance and Repair Times for Components in Technological Facilities

    SciTech Connect (OSTI)

    L. C. Cadwallader

    2012-11-01T23:59:59.000Z

    This report is a compilation of some unique component repair time data and it also presents citations of more extensive reports where lists of repair times can be found. This collection of information should support analysts who seek to quantify maintainability and availability of high technology and nuclear energy production systems. While there are newer sources of repair time information, most, if not all, of the newer sources are proprietary and cannot be shared. This report offers data that, while older, is openly accessible and can serve as reasonable estimates of repair times, at least for initial studies. Some times were found for maintenance times in radiation environments, and some guidance for multiplicative factors to use to account for work in contamination areas.

  1. Modeling and centralization of strategic inventory for repairable and long lead-time spare parts

    E-Print Network [OSTI]

    Duncan, Tyeliah Elaine

    2011-01-01T23:59:59.000Z

    This thesis develops an optimal inventory model for repairable and long leadtime spare parts for an Engine overhaul business. In addition, it presents a business case for centralization of inventory. Pratt & Whitney purchased ...

  2. Emerging Trends in Heart Valve Engineering: Part III. Novel Technologies for Mitral Valve Repair and Replacement

    E-Print Network [OSTI]

    2015-01-01T23:59:59.000Z

    and J. D. Puskas. Mitral-valve repair versus replacement forbioprosthetic heart valves. Ann. Thorac. Surg. 71:S417–mechanics of arti?cial heart valves. Clin. Exp. Pharmacol.

  3. Tiny Terminators: New Micro-Robots Assemble, Repair Themselves and Are Surprisingly Strong

    Broader source: Energy.gov [DOE]

    Tiny robots that can assemble and repair themselves? Watch a video of Argonne National Laboratory's micro-robots that easily perform tasks that can challenge other robots, including moving objects that are larger than themselves.

  4. Consistency Management with Repair Actions Christian Nentwich, Wolfgang Emmerich and Anthony Finkelstein

    E-Print Network [OSTI]

    van der Hoek, André

    Consistency Management with Repair Actions Christian Nentwich, Wolfgang Emmerich and Anthony Finkelstein Department of Computer Science University College London Gower Street, London WC1E 6BT, UK {c.nentwich,w.emmerich

  5. Use of CFRP Overlays to Repair Fatigue Damage in Steel Bridge Girders and Components

    E-Print Network [OSTI]

    Gangel, Regan Elisabeth

    2012-05-31T23:59:59.000Z

    Fatigue damage in steel girder bridges built prior to the mid-1980s is common due to distortion-induced fatigue. Different repair techniques have been developed and implemented to retrofit bridges of this era with existing fatigue damage...

  6. Community-Minded Interns at Savannah River Site Help Area Residents in Need with Home Repairs

    Broader source: Energy.gov [DOE]

    AIKEN, S.C. – More than two dozen college interns who worked at the Savannah River Site (SRS) this summer joined other volunteers and headed into area neighborhoods to help people in need with home repairs.

  7. RESTORING A DAMAGED 16-YEAR -OLD INSULATING POLYMER CONCRETE DIKE OVERLAY: REPAIR MATERIALS AND TECHNOLOGIES.

    SciTech Connect (OSTI)

    SUGAMA,T.

    2007-01-01T23:59:59.000Z

    The objective of this program was to design and formulate organic polymer-based material systems suitable for repairing and restoring the overlay panels of insulating lightweight polymer concrete (ILPC) from the concrete floor and slope wall of a dike at KeySpan liquefied natural gas (LNG) facility in Greenpoint, Brooklyn, NY, just over sixteen years ago. It also included undertaking a small-scale field demonstration to ensure that the commercial repairing technologies were applicable to the designed and formulated materials.

  8. Endovascular Abdominal Aortic Aneurysm Repair in the Presence of a Kidney Transplant: Therapeutic Considerations

    SciTech Connect (OSTI)

    Karkos, Christos D., E-mail: ckarkos@hotmail.com; McMahon, Greg [Leicester Royal Infirmary, Department of Vascular and Endovascular Surgery (United Kingdom); Fishwick, Guy [Leicester Royal Infirmary, Department of Radiology (United Kingdom); Lambert, Kelly; Bagga, Ajay; McCarthy, Mark J. [Leicester Royal Infirmary, Department of Vascular and Endovascular Surgery (United Kingdom)

    2006-04-15T23:59:59.000Z

    Abdominal aortic aneurysm (AAA) repair in the presence of a kidney transplant can be extremely challenging, as it carries significant risks of renal ischemia. Endovascular repair is an attractive option, as it can be performed with little or no impairment of renal arterial flow. We describe the endovascular management of a recurrent AAA in a patient with a functioning renal transplant using a custom-made aorto-uni-iliac device. We discuss the planning and the potential problems of the technique.

  9. In situ repair of a failed compression fitting

    DOE Patents [OSTI]

    Wolbert, R.R.; Jandrasits, W.G.

    1985-08-05T23:59:59.000Z

    A method and apparatus for the in situ repair of a failed compression fitting is provided. Initially, a portion of a guide tube is inserted coaxially in the bore of the compression fitting and locked therein. A close fit dethreading device is then coaxially mounted on the guide tube to cut the threads from the fitting. Thereafter, the dethreading device and guide tube are removed and a new fitting is inserted onto the dethreaded fitting with the body of the new fitting overlaying the dethreaded portion. Finally, the main body of the new fitting is welded to the main body of the old fitting whereby a new threaded portion of the replacement fitting is precisely coaxial with the old threaded portion. If needed, a bushing is located on the dethreaded portion which is sized to fit snugly between the dethreaded portion and the new fitting. Preferably, the dethreading device includes a cutting tool which is moved incrementally in a radial direction whereby the threads are cut from the threaded portion of the failed fitting in increments.

  10. In situ repair of a failed compression fitting

    DOE Patents [OSTI]

    Wolbert, Ronald R. (McKees Rocks, PA); Jandrasits, Walter G. (Pittsburgh, PA)

    1986-01-01T23:59:59.000Z

    A method and apparatus for the in situ repair of a failed compression fitg is provided. Initially, a portion of a guide tube is inserted coaxially in the bore of the compression fitting and locked therein. A close fit dethreading device is then coaxially mounted on the guide tube to cut the threads from the fitting. Thereafter, the dethreading device and guide tube are removed and a new fitting is inserted onto the dethreaded fitting with the body of the new fitting overlaying the dethreaded portion. Finally, the main body of the new fitting is welded to the main body of the old fitting whereby a new threaded portion of the replacement fitting is precisely coaxial with the old threaded portion. If needed, a bushing is located on the dethreaded portion which is sized to fit snugly between the dethreaded portion and the new fitting. Preferably, the dethreading device includes a cutting tool which is moved incrementally in a radial direction whereby the threads are cut from the threaded portion of the failed fitting in increments.

  11. Remote Welding, NDE and Repair of DOE Standardized Canisters

    SciTech Connect (OSTI)

    Eric Larsen; Art Watkins; Timothy R. McJunkin; Dave Pace; Rodney Bitsoi

    2006-05-01T23:59:59.000Z

    The U.S. Department of Energy (DOE) created the National Spent Nuclear Fuel Program (NSNFP) to manage DOE’s spent nuclear fuel (SNF). One of the NSNFP’s tasks is to prepare spent nuclear fuel for storage, transportation, and disposal at the national repository. As part of this effort, the NSNFP developed a standardized canister for interim storage and transportation of SNF. These canisters will be built and sealed to American Society of Mechanical Engineers (ASME) Section III, Division 3 requirements. Packaging SNF usually is a three-step process: canister loading, closure welding, and closure weld verification. After loading SNF into the canisters, the canisters must be seal welded and the welds verified using a combination of visual, surface eddy current, and ultrasonic inspection or examination techniques. If unacceptable defects in the weld are detected, the defective sections of weld must be removed, re-welded, and re-inspected. Due to the high contamination and/or radiation fields involved with this process, all of these functions must be performed remotely in a hot cell. The prototype apparatus to perform these functions is a floor-mounted carousel that encircles the loaded canister; three stations perform the functions of welding, inspecting, and repairing the seal welds. A welding operator monitors and controls these functions remotely via a workstation located outside the hot cell. The discussion describes the hardware and software that have been developed and the results of testing that has been done to date.

  12. Iskuulpa Watershed ProjectIskuulpa Watershed Project BPA Project # 199506001BPA Project # 199506001

    E-Print Network [OSTI]

    Hydroelectric Power Project impacts Improve natural salmonid habitat and production #12;Project ActivitiesProject Activities Land purchaseLand purchase HEP evaluationHEP evaluation Rest from livestockRest from livestock;Project ActivitiesProject Activities Land purchaseLand purchase HEP evaluationHEP evaluation Rest from

  13. Project Name Project Number Tagging Type

    E-Print Network [OSTI]

    Project Name Project Number Primary Tagging Type Secondary Tagging Type Fish Species Tagging/ Secondary Legal Driver (BiOp, MOA, Accord, etc.) Tagging Purpose Funded Entity Tagging Location Retrieval CWT Recovery Project 2010-036-00 CWT PIT Chinook, coho retrieval, analysis, address PSMFC sampling

  14. Project management plan for Project W-178, 219-S secondary containment

    SciTech Connect (OSTI)

    Buckles, D.I.

    1995-01-26T23:59:59.000Z

    This Project Management Plan (PMP) establishes the organizational responsibilities, control systems, and procedures for managing the execution of project activities for Project W-178, the 219-S Secondary Containment Upgrade. The scope of this project will provide the 219-S Facility with secondary containment for all tanks and piping systems. Tank 103 will be replaced with a new tank which will be designated as Tank 104. Corrosion protection shall be installed as required. The cells shall be cleaned and the surface repaired as required. The 219-S Waste Handling Facility (219-S Facility), located in the 200 West Area, was constructed in 1951 to support the 222-S Laboratory Facility. The 219-S Facility has three tanks, TK-101, TK-102, and TK-103, which receive and neutralize low level radioactive wastes from the 222-S Laboratory. For purposes of the laboratory, the different low level waste streams have been designated as high activity and intermediate activity. The 219-S Facility accumulates and treats the liquid waste prior to transferring it to SY Tank Farm in the 200-W Area. Transfers are normally made by pipeline from the 219-S Facility to the 241-SY Tank Farm. Presently transfers are being made by tanker truck to the 200-E Area Tank Farms due to the diversion box catch tank which has been removed from service.

  15. Expert Meeting Report: Key Innovations for Adding Energy Efficiency to Maintenance Projects

    SciTech Connect (OSTI)

    Wood, A.; Wiehagen, J.

    2012-09-01T23:59:59.000Z

    This report describes an expert meeting hosted by the Building America research team NAHB Research Center, which was held on February 8, 2012, in Orlando, Florida. The topic, Key Innovations for Adding Energy Efficiency to Maintenance Projects, was intended to provide direction to more focused efforts to increase the efficiency of existing homes; in this meeting, the focus was specifically for re-roofing and the opportunities for adding energy efficiency upgrades during this major home repair activity.

  16. Development of bonded composite doublers for the repair of oil recovery equipment.

    SciTech Connect (OSTI)

    Roach, David W.; Rackow, Kirk A.

    2005-06-01T23:59:59.000Z

    An unavoidable by-product of a metallic structure's use is the appearance of crack and corrosion flaws. Economic barriers to the replacement of these structures have created an aging infrastructure and placed even greater demands on efficient and safe repair methods. In the past decade, an advanced composite repair technology has made great strides in commercial aviation use. Extensive testing and analysis, through joint programs between the Sandia Labs FAA Airworthiness Assurance Center and the aviation industry, have proven that composite materials can be used to repair damaged aluminum structure. Successful pilot programs have produced flight performance history to establish the durability of bonded composite patches as a permanent repair on commercial aircraft structures. With this foundation in place, this effort is adapting bonded composite repair technology to civil structures. The use of bonded composite doublers has the potential to correct the difficulties associated with current repair techniques and the ability to be applied where there are no rehabilitation options. It promises to be cost-effective with minimal disruption to the users of the structure. This report concludes a study into the application of composite patches on thick steel structures typically used in mining operations. Extreme fatigue, temperature, erosive, and corrosive environments induce an array of equipment damage. The current weld repair techniques for these structures provide a fatigue life that is inferior to that of the original plate. Subsequent cracking must be revisited on a regular basis. The use of composite doublers, which do not have brittle fracture problems such as those inherent in welds, can help extend the structure's fatigue life and reduce the equipment downtime. Two of the main issues for adapting aircraft composite repairs to civil applications are developing an installation technique for carbon steel and accommodating large repairs on extremely thick structures. This study developed and proved an optimum field installation process using specific mechanical and chemical surface preparation techniques coupled with unique, in-situ heating methods. In addition, a comprehensive performance assessment of composite doubler repairs was completed to establish the viability of this technology for large, steel structures. The factors influencing the durability of composite patches in severe field environments were evaluated along with related laminate design issues.

  17. Projects | Department of Energy

    Office of Environmental Management (EM)

    Projects Projects All 1703 1705 ATVM Current Portfolio 32.4 B in Loans 55 K Jobs Current Portfolio Loans 32.4 B Jobs 55,000 Loan Program Office Projects 1703 1705 ATVM...

  18. CRSP Power Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    expenses of the project each year, and receive all of the energy it produces. Salt Lake City AreaIntegrated Projects: Power from the Colorado River Storage Project plants was...

  19. Project Selection - Record Keeping

    E-Print Network [OSTI]

    Howard, Jeff W.

    2005-05-10T23:59:59.000Z

    4-H members have many project areas to choose from, depending on where they live. Members should consult with their parents and 4-H leaders when choosing a project. This publication outlines project considerations....

  20. Super Projects (Arkansas)

    Broader source: Energy.gov [DOE]

    A 2004 amendment to the state constitution authorizes the state to attract super projects by issuing bonds to fund a project’s infrastructure, limited to 5% of the net general revenues during the...

  1. Planning and Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Rates Planning Ten-Year Capital Program Projects Lovell-Yellowtail Transmission Line Rebuild project Studies WACM Wind production summary overview (Oct. 2006)...

  2. Project BETA Cover Page

    E-Print Network [OSTI]

    Cover Page, Project BETA

    2012-01-01T23:59:59.000Z

    and Distribution of the Project BETA articles were funded inproduct is discussed in the BETA articles. Western JournalProject BETA: Best practices in Evaluation and Treatment of

  3. Project Finance and Investments

    Broader source: Energy.gov [DOE]

    Plenary III: Project Finance and Investment Project Finance and Investments Chris Cassidy, National Business Renewable Energy Advisor, U.S. Department of Agriculture

  4. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    3 rd Quarter Overall Contract and Project Management Performance Metrics and Targets ContractProject Management Performance Metrics FY 2009 Target FY 2009 Actual Comment 1....

  5. Operations Cost Allocation Project

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Operations Consolidation Project Operations Consolidation Project (OCP) Cost Allocation Presentation - September 20, 2011 OCP Cost Allocation Customer Presentation List of Acronyms...

  6. Clean Coal Projects (Virginia)

    Broader source: Energy.gov [DOE]

    This legislation directs the Virginia Air Pollution Control Board to facilitate the construction and implementation of clean coal projects by expediting the permitting process for such projects.

  7. Falls Creek Hydroelectric Project

    SciTech Connect (OSTI)

    Gustavus Electric Company; Richard Levitt; DOE Project Officer - Keith Bennett

    2007-06-12T23:59:59.000Z

    This project was for planning and construction of a 700kW hydropower project on the Fall River near Gustavus, Alaska.

  8. Relocation and repair of the National Geotechnical Centrifuge. Final report

    SciTech Connect (OSTI)

    Cheney, J.A. [California Univ., Davis, CA (United States). Center for Geotechnical Modeling

    1994-10-01T23:59:59.000Z

    In January of 1984, the large geotechnical centrifuge located at NASA Ames Research Center, was in the first stages of operational checkout when the main thrust bearing of the large D.C. drive motor failed. After many months of investigation and proposals for repair of the facility, it became evident that it would be far more advantageous to the engineering community to remove those components of the centrifuge that were undamaged to the Davis campus and replace the drive system completely. The large centrifuge had cost over 2 million dollars to build, and it would have been irresponsible to simply scrap it. Recognizing this fact, funds were solicited and received from various sources, and Beam Engineering Inc. was contracted to design and construct the centrifuge at its new location. The University of California contributed a quarter of a million dollars and Tyndall Air Force Base, through Los Alamos National Laboratory, contributed $140,000. There were funds also contributed by LANL, LLNL, US Navy and NSF. The first stage in the phased development of the newly located centrifuge is nearing completion, which prompts the writing of this report. By the time that this report reaches the reader the first runs of the centrifuge will have been completed. The present report describes the present capability of the centrifuge and the plans for upgrading as time goes on. Several pilot studies were carried out. The experiments involved (1) the effects of nearby explosions on buried thin walled containers and (2) the advection and dispersion of toxic waste water through soils.

  9. Manhattan Project | Department of Energy

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Manhattan Project Manhattan Project Manhattan Project New Manhattan Project Interactive Website The Department of Energy traces its origins to World War II and the Manhattan...

  10. WHERE MULTIFUNCTIONAL DNA REPAIR PROTEINS MEET: MAPPING THE INTERACTION DOMAINS BETWEEN XPG AND WRN

    SciTech Connect (OSTI)

    Rangaraj, K.; Cooper, P.K.; Trego, K.S.

    2009-01-01T23:59:59.000Z

    The rapid recognition and repair of DNA damage is essential for the maintenance of genomic integrity and cellular survival. Multiple complex and interconnected DNA damage responses exist within cells to preserve the human genome, and these repair pathways are carried out by a specifi c interplay of protein-protein interactions. Thus a failure in the coordination of these processes, perhaps brought about by a breakdown in any one multifunctional repair protein, can lead to genomic instability, developmental and immunological abnormalities, cancer and premature aging. This study demonstrates a novel interaction between two such repair proteins, Xeroderma pigmentosum group G protein (XPG) and Werner syndrome helicase (WRN), that are both highly pleiotropic and associated with inherited genetic disorders when mutated. XPG is a structure-specifi c endonuclease required for the repair of UV-damaged DNA by nucleotide excision repair (NER), and mutations in XPG result in the diseases Xeroderma pigmentosum (XP) and Cockayne syndrome (CS). A loss of XPG incision activity results in XP, whereas a loss of non-enzymatic function(s) of XPG causes CS. WRN is a multifunctional protein involved in double-strand break repair (DSBR), and consists of 3’–5’ DNA-dependent helicase, 3’–5’ exonuclease, and single-strand DNA annealing activities. Nonfunctional WRN protein leads to Werner syndrome, a premature aging disorder with increased cancer incidence. Far Western analysis was used to map the interacting domains between XPG and WRN by denaturing gel electrophoresis, which separated purifi ed full length and recombinant XPG and WRN deletion constructs, based primarily upon the length of each polypeptide. Specifi c interacting domains were visualized when probed with the secondary protein of interest which was then detected by traditional Western analysis using the antibody of the secondary protein. The interaction between XPG and WRN was mapped to the C-terminal region of XPG as well as the C-terminal region of WRN. The physical interaction between XPG and WRN links NER, (made evident by the disease XP) with DSBR, which imparts additional knowledge of the overlapping nature of these two proteins and the previously distinct DNA repair pathways they are associated with. Since genomic integrity is constantly threatened by both endogenous and exogenous (internal and external) damage, understanding the roles of these proteins in coordinating DNA repair processes with replication will signifi cantly further understanding how defects instigate physiological consequences in response to various DNA damaging sources. This ultimately contributes to our understanding of cancer and premature aging.

  11. HANFORD SITE LOW EXPOSURE PIPELINE REPAIR USING A NON-METALLIC COMPOSITE SYSTEM

    SciTech Connect (OSTI)

    HUTH RJ

    2009-11-12T23:59:59.000Z

    At the Department of Energy, Richland Operations (DOE-RL) Hanford site in eastern Washington, a 350 mm (14 inch) diameter high density polyethylene (HDPE) pump recirculation pipeline failed at a bonded joint adjacent to a radiologically and chemically contaminated groundwater storage basin. The responsible DOE-RL contractor, CH2MHill Plateau Remediation Company, applied a fiberglass reinforced plastic (composite) field repair system to the failed joint. The system was devised specifically for the HDPE pipe repair at the Hanford site, and had not been used on this type of plastic piping previously. This paper introduces the pipe failure scenario, describes the options considered for repair and discusses the ultimate resolution of the problem. The failed pipeline was successfully returned to service with minimal impact on waste water treatment plant operating capacity. Additionally, radiological and chemical exposures to facility personnel were maintained as low as reasonably achievable (ALARA). The repair is considered a success for the near term, and future monitoring will prove whether the repair can be considered for long term service and as a viable alternative for similar piping failures at the Hanford site.

  12. MRIP Operations Team Projects (2012 Funded) Project Name Project Description Project Objectives

    E-Print Network [OSTI]

    MRIP Operations Team Projects (2012 Funded) Project Name Project Description Project Objectives vessel registries to conduct recreational catch and effort surveys. Develop a recreational fishing. Accuracy Funded 2012 Oregon Shore and EstuaryBoat Survey Design Review Develop a new or revised

  13. Example Measurement & Verification Plan for a Super ESPC Project

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    REPORTING FOR VERIFICATION ACTIVITIES ... 5 2.4 OPERATIONS, PREVENTIVE MAINTENANCE, REPAIR, AND REPLACEMENT REPORTING REQUIREMENTS...

  14. CX-012576: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Floor Repair in Select Reactor Offices and Admin. Trailer 704-27L CX(s) Applied: B1.3, B1.16Date: 41852 Location(s): South CarolinaOffices(s): Savannah River Operations Office

  15. CX-012744: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Prescott Peacock Transmission Line- Insulator Repair at 3 Structures CX(s) Applied: B1.3Date: 41851 Location(s): ArizonaOffices(s): Western Area Power Administration-Desert Southwest Region

  16. CX-012743: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Mead Substation Service Building Repairs CX(s) Applied: B1.3Date: 41879 Location(s): NevadaOffices(s): Western Area Power Administration-Desert Southwest Region

  17. CX-007956: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    High Resolution 3-Dimensional Laser Imaging for Inspection, Maintenance, Repair, and Operations CX(s) Applied: B3.6 Date: 01/30/2012 Location(s): California Offices(s): National Energy Technology Laboratory

  18. CX-007461: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    High Resolution 3-dimensional Laser Imaging for Inspection, Maintenance, Repair and Operations - Phase II CX(s) Applied: B3.6 Date: 12/20/2011 Location(s): Colorado Offices(s): National Energy Technology Laboratory

  19. CX-012040: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    High Resolution 3-Dimensional Laser Imaging for Inspection, Maintenance, Repair, and Operations - Phase II CX(s) Applied: A9 Date: 04/11/2014 Location(s): Colorado Offices(s): National Energy Technology Laboratory

  20. CX-012039: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    High Resolution 3-Dimensional Laser Imaging for Inspection, Maintenance, Repair, and Operations - Phase II CX(s) Applied: A9, B3.6 Date: 04/11/2014 Location(s): Colorado Offices(s): National Energy Technology Laboratory

  1. CX-012613: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Repair/Reseals Concrete and Asphalt Covers at R- Reactor Seepage Basin CX(s) Applied: B1.3Date: 41801 Location(s): South CarolinaOffices(s): Savannah River Operations Office

  2. CX-008942: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Site-Wide Sidewalk Improvements and Seal and Repair Pavement CX(s) Applied: B1.3 Date: 08/17/2012 Location(s): West Virginia Offices(s): National Energy Technology Laboratory

  3. CX-012337: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Maintain/Repair SPR Radio Communications Network, 2014-2017 CX(s) Applied: B1.7 Date: 06/11/2014 Location(s): CX: none Offices(s): Strategic Petroleum Reserve Field Office

  4. CX-012165: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Mixed Waste Management Facility Cap Drainage Repairs CX(s) Applied: B6.1 Date: 04/28/2014 Location(s): South Carolina Offices(s): Savannah River Operations Office

  5. CX-012229: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Longview-Chehalis #3 Transmission Structure Footing Repair CX(s) Applied: B1.3 Date: 06/12/2014 Location(s): Washington Offices(s): Bonneville Power Administration

  6. CX-002830: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Repairs to Men?s Bathroom in West Hackberry Building 302CX(s) Applied: B1.3Date: 06/21/2010Location(s): West Hackberry, LouisianaOffice(s): Fossil Energy, Strategic Petroleum Reserve Field Office

  7. CX-010848: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    300 square feet of Modified Bitumen Roof Repair CX(s) Applied: B1.3 Date: 07/23/2013 Location(s): South Carolina Offices(s): Savannah River Operations Office

  8. CX-007506: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Record of Categorical Exclusion for Bryan Mound Building BE-2 Drainage Improvements and Foundation Repair CX(s) Applied: B1.3 Date: 11/16/2011 Location(s): Texas Offices(s): Strategic Petroleum Reserve Field Office

  9. CX-012374: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Subcontractor Repair of Roof Leaks at 221-H (Truckwell Airlock) CX(s) Applied: B1.3 Date: 05/29/2014 Location(s): South Carolina Offices(s): Savannah River Operations Office

  10. CX-012167: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Subcontractor Repair of Roof Leaks at 766-H, Room 2121 CX(s) Applied: B1.3 Date: 04/24/2014 Location(s): South Carolina Offices(s): Savannah River Operations Office

  11. CX-012168: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Subcontractor Repair of Roof Leaks at 218-1H CX(s) Applied: B1.3 Date: 04/23/2014 Location(s): South Carolina Offices(s): Savannah River Operations Office

  12. CX-012395: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Subcontractor Repair of Roof Leaks at 221-S CX(s) Applied: B1.3 Date: 05/05/2014 Location(s): South Carolina Offices(s): Savannah River Operations Office

  13. CX-012387: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Subcontractor Repair of Roof Leaks at 701-1K CX(s) Applied: B1.3 Date: 05/13/2014 Location(s): South Carolina Offices(s): Savannah River Operations Office

  14. CX-012163: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Subcontractor Repair of Roof Leaks at 717-16K CX(s) Applied: B1.3 Date: 04/29/2014 Location(s): South Carolina Offices(s): Savannah River Operations Office

  15. CX-012396: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Subcontractor Repair of Roof Leaks at 705-K CX(s) Applied: B1.3 Date: 05/01/2014 Location(s): South Carolina Offices(s): Savannah River Operations Office

  16. CX-012388: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Subcontractor Repair of Roof Leaks 108-1K CX(s) Applied: B1.3 Date: 05/13/2014 Location(s): South Carolina Offices(s): Savannah River Operations Office

  17. CX-010886: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Curecanti-Lost Canyon 230-Kilovolt Emergency Repairs of Downed Conductor CX(s) Applied: B1.3 Date: 08/06/2013 Location(s): Colorado Offices(s): Western Area Power Administration-Rocky Mountain Region

  18. CX-011724: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Repair Corroded Flow Line Near 33-SX-11 CX(s) Applied: B5.4, B5.6 Date: 12/30/2013 Location(s): Wyoming Offices(s): RMOTC

  19. CX-012558: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Roof repairs at 773-A, E-004 CX(s) Applied: B1.3Date: 41872 Location(s): South CarolinaOffices(s): Savannah River Operations Office

  20. CX-012595: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Subcontractor Repair of Roof Leaks at 704-H CX(s) Applied: B1.3Date: 41827 Location(s): South CarolinaOffices(s): Savannah River Operations Office

  1. A survey of repair practices for nuclear power plant containment metallic pressure boundaries

    SciTech Connect (OSTI)

    Oland, C.B.; Naus, D.J. [Oak Ridge National Lab., TN (United States)

    1998-05-01T23:59:59.000Z

    The Nuclear Regulatory Commission has initiated a program at the Oak Ridge National Laboratory to provide assistance in their assessment of the effects of potential degradation on the structural integrity and leaktightness of metal containment vessels and steel liners of concrete containments in nuclear power plants. One of the program objectives is to identify repair practices for restoring metallic containment pressure boundary components that have been damaged or degraded in service. This report presents issues associated with inservice condition assessments and continued service evaluations and identifies the rules and requirements for the repair and replacement of nonconforming containment pressure boundary components by welding or metal removal. Discussion topics include base and welding materials, welding procedure and performance qualifications, inspection techniques, testing methods, acceptance criteria, and documentation requirements necessary for making acceptable repairs and replacements so that the plant can be returned to a safe operating condition.

  2. Evaluation of bisphenol E cyanate ester for the resin-injection repair of advanced composites

    SciTech Connect (OSTI)

    Wilber Yaote Lio

    2009-12-19T23:59:59.000Z

    This thesis is a compilation of a general introduction and literature review that ties together the subsequent chapters which consist of two journal articles that have yet to be submitted for publication. The overall topic relates to the evaluation and application of a new class of cyanate ester resin with unique properties that lend it applicable to use as a resin for injection repair of high glass transition temperature polymer matrix composites. The first article (Chapter 2) details the evaluation and optimization of adhesive properties of this cyanate ester and alumina nanocomposites under different conditions. The second article (Chapter 3) describes the development and evaluation of an injection repair system for repairing delaminations in polymer matrix composites.

  3. Automatic coke oven heating control system at Burns Harbor for normal and repair operation

    SciTech Connect (OSTI)

    Battle, E.T.; Chen, K.L. [Bethlehem Steel Corp., Burns Harbor, IN (United States); [Bethlehem Steel Corp., PA (United States)

    1997-12-31T23:59:59.000Z

    An automatic heating control system for coke oven batteries was developed in 1985 for the Burns Harbor No. 1 battery and reported in the 1989 Ironmaking Conference Proceedings. The original system was designed to maintain a target coke temperature at a given production level under normal operating conditions. Since 1989, enhancements have been made to this control system so that it can also control the battery heating when the battery is under repair. The new control system has improved heating control capability because it adjusts the heat input to the battery in response to anticipated changes in the production schedule. During a recent repair of this 82 oven battery, the pushing schedule changed from 102 ovens/day to 88 ovens/day, then back to 102 ovens/day, then to 107 ovens/day. During this repair, the control system was able to maintain the coke temperature average standard deviation at 44 F, with a maximum 75 F.

  4. Bosh repairs No. 3 blast furnace, Edgar Thomson Plant Mon Valley Works

    SciTech Connect (OSTI)

    Stoupis, M.G.

    1993-01-01T23:59:59.000Z

    The paper describes in detail the steps taken from quenching to dry out of the furnace to repair the bosh area of the No.3 blast furnace. Inspection of the area revealed that there was no brick anywhere in the bosh. Brick in the tuyere breast area had been peeled back to reveal the steel plate, and descaling revealed 14 pipes fully exposed. None were leaking, but one seemed badly deteriorated. Conventional repairs could not take place before the scheduled blow-in. Installation of coolers were instead tried.

  5. Remote reactor repair: GTA (gas tungsten Arc) weld cracking caused by entrapped helium

    SciTech Connect (OSTI)

    Kanne, W.R. Jr.

    1988-01-01T23:59:59.000Z

    A repair patch was welded to the wall of a nuclear reactor tank using remotely controlled thirty-foot long robot arms. Further repair was halted when gas tungsten arc (GTA) welds joining type 304L stainless steel patches to the 304 stainless steel wall developed toe cracks in the heat-affected zone (HAZ). The role of helium in cracking was investigated using material with entrapped helium from tritium decay. As a result of this investigation, and of an extensive array of diagnostic tests performed on reactor tank wall material, helium embrittlement was shown to be the cause of the toe cracks.

  6. Senior projectS corporate Sponsored

    E-Print Network [OSTI]

    Stuart, Josh

    --Professor, Computer Engineering | http://users.soe.ucsc. edu/~larrabee/Site/Professor_Tracy_Larrabee.html Charlie McSenior projectS program corporate Sponsored Partner's Day May 31, 2012 Baskin School of Engineering earning their engineering degree and fulfilling this capstone design sequence. Our students who have

  7. Livingston Campus Geothermal Project The Project

    E-Print Network [OSTI]

    Delgado, Mauricio

    Livingston Campus Geothermal Project The Project: Geothermal power is a cost effective, reliable is a Closed Loop Geothermal System involving the removal and storage of approximately four feet of dirt from the entire Geothermal Field and the boring of 321 vertical holes reaching a depth of 500 feet. These holes

  8. Mitral Web -A New Concept for Mitral Valve Repair: Improved Engineering Design and In-Vitro Studies

    E-Print Network [OSTI]

    Pekkan, Kerem

    Mitral Web - A New Concept for Mitral Valve Repair: Improved Engineering Design and In of Biomedical Engineering, Georgia Institute of Technology, GA, USA Myxomatous mitral valve disease is currently reported that mitral valve repair is preferable to valve replace- ment, as it offers certain advantages

  9. Restoration and repair of 30-year old cooling towers at the Paducah Gaseous Diffusion Plant, Phase I. Draft 1

    SciTech Connect (OSTI)

    Shelton, M.F.

    1985-01-01T23:59:59.000Z

    Early in 1980, a comprehensive reliability study was made to ascertain the ability of the present 30-year old recirculating water system to meet the anticipated load demand through the year 2000. The findings and recommendations of this study were used as a guide to schedule uprating and repairs. This paper deals with the underground distribution system and cooling tower repairs.

  10. The Role of Nucleotide Excision Repair in Restoring Replication Following UV-Induced Damage in Escherichia coli

    E-Print Network [OSTI]

    Courcelle, Justin

    The Role of Nucleotide Excision Repair in Restoring Replication Following UV-Induced Damage DNA synthesis in the absence of nucleotide excision repair does not promote cell survivalA mutants....................... 26 Following low doses of UV irradiation cells lacking nucleotide excision

  11. Hot repair of ceramic burner on hot blast stoves at USS/Kobe`s {number_sign}3 blast furnace

    SciTech Connect (OSTI)

    Bernarding, T.F.; Chemorov, M.; Shimono, S.; Phillips, G.R.

    1997-12-31T23:59:59.000Z

    During the 1992 reline of the No. 3 blast furnace, three new stoves were constructed. The design of the stoves, equipped with internal ceramic burners, was for providing a hot blast temperature of 2,000 F at a wind rate of 140,000 SCFM. After 3 years the performance had deteriorated so the burners were cleaned. When a second cleaning did not improve the performance of No. 3 blast furnace, it was decided to repair the refractory while still hot. The paper describes the hot repair procedures, taking a stove off for repairs, maintenance heat up during repairs, two stove operation, stove commissioning, repair of a ceramic burner, and wet gas prevention.

  12. Solar Water Heating System Maintenance and Repair | Department of Energy

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What'sis Taking Over Our Instagram Secretary Moniz9MorganYouof Energy ProjectsHeaters and the

  13. Information Technology Project Management

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2012-12-03T23:59:59.000Z

    The Order provides program and project management direction for the acquisition and management of IT projects, investments, and initiatives. Cancels DOE G 200.1-1. Admin Chg 1, dated 1-16-2013, cancels DOE O 415.1.

  14. The 4-H Project

    E-Print Network [OSTI]

    Howard, Jeff W.

    2005-05-10T23:59:59.000Z

    As a 4-H volunteer, you will find that projects are useful tools for teaching a wide variety of skills to young people. This publication will help you plan and evaluate 4-H learning projects....

  15. Information Technology Project Management

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2012-12-03T23:59:59.000Z

    The Order provides program and project management direction for the acquisition and management of IT projects, investments, and initiatives. Cancels DOE G 200.1-1. Admin Chg 1 approved 1-16-2013.

  16. CX-012632: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    LURR 20140456 - Salmon Creek Avenue Pathway Project CX(s) Applied: B4.9Date: 41885 Location(s): WashingtonOffices(s): Bonneville Power Administration

  17. CX-009005: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Henderson Solar Energy Project CX(s) Applied: B5.16 Date: 08/22/2012 Location(s): Nevada Offices(s): Golden Field Office

  18. CX-012474: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Refractories/Ceramics Project CX(s) Applied: B3.6Date: 41870 Location(s): OregonOffices(s): National Energy Technology Laboratory

  19. CX-008691: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Mason Substation Metering Replacement Project CX(s) Applied: B1.7 Date: 06/25/2012 Location(s): Washington Offices(s): Bonneville Power Administration

  20. CX-008797: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Coal Pile Basin Project CX(s) Applied: B1.29 Date: 06/04/2012 Location(s): Tennessee Offices(s): Y-12 Site Office

  1. CX-010590: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Kalispell Shunt Cap Addition Project CX(s) Applied: B4.11 Date: 07/01/2013 Location(s): Montana Offices(s): Bonneville Power Administration

  2. Categorical Exclusion Determinations: Western Area PowerAdministratio...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Center October 26, 2009 CX-005544: Categorical Exclusion Determination Power Rate Formula for the Provo River Project of the Western Area Power Administration CX(s) Applied:...

  3. CX-008684: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Metaline Radio Station Upgrade Project CX(s) Applied: B1.19 Date: 07/11/2012 Location(s): Washington Offices(s): Bonneville Power Administration

  4. CX-008215: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Small Hydropower Research and Development Technology Project CX(s) Applied: A9 Date: 04/03/2012 Location(s): Colorado Offices(s): Golden Field Office

  5. CX-011391: Categorical Exclusion Determination | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Exclusion Determination CX-011391: Categorical Exclusion Determination Municipal Complex Solar Power Project CX(s) Applied: B3.14 Date: 12102013 Location(s): New Jersey...

  6. CX-007111: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Exclusion Determination CX-007111: Categorical Exclusion Determination Shallow Carbon Sequestration Demonstration Project (Iatan Generating Station) CX(s) Applied: B3.1...

  7. CX-007118: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Exclusion Determination CX-007118: Categorical Exclusion Determination Shallow Carbon Sequestration Demonstration Project CX(s) Applied: B3.1 Date: 10042011...

  8. CX-007388: Categorical Exclusion Determination | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Exclusion Determination CX-007388: Categorical Exclusion Determination Regional Test Center Project: Solar Technology Acceleration Center (SolarTAC) CX(s) Applied: B1.15,...

  9. CX-008235: Categorical Exclusion Determination | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Exclusion Determination CX-008235: Categorical Exclusion Determination Harnessing the Hydro-Electric Potential of Engineered Drops in the Columbia Basin Project: Phase 1 CX(s)...

  10. CX-003904: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    904: Categorical Exclusion Determination CX-003904: Categorical Exclusion Determination Hydro Electric Project - Snohomish Public Utility District CX(s) Applied: A9, A11, B5.1...

  11. CX-009542: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Solar Parks Project CX(s) Applied: B5.16 Date: 11/09/2012 Location(s): Florida Offices(s): Golden Field Office

  12. CX-003403: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    CX-003403: Categorical Exclusion Determination The Snake River Geothermal Drilling Project - Innovative Approaches to Geothermal Exploration CX(s) Applied: A9, B3.7...

  13. CX-002745: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    CX-002745: Categorical Exclusion Determination The Snake River Geothermal Drilling Project - Innovative Approaches to Geothermal Exploration CX(s) Applied: B3.1, A9...

  14. CX-003208: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Exclusion Determination CX-003208: Categorical Exclusion Determination Michigan 85% Ethanol Fuel (E85) Infrastructure Project CX(s) Applied: B5.1 Date: 08032010 Location(s):...

  15. CX-003471: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Exclusion Determination CX-003471: Categorical Exclusion Determination Pennsylvania Ethanol Fuel (E85) Corridor Project - Lew's Service Center CX(s) Applied: B5.1 Date: 0823...

  16. CX-011131: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Puget Sound Pilot Tidal Energy Project CX(s) Applied: A9 Date: 08/13/2013 Location(s): Washington Offices(s): Golden Field Office

  17. CX-008683: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Shaniko Radio Station Replacement Project CX(s) Applied: B1.19 Date: 07/11/2012 Location(s): Oregon Offices(s): Bonneville Power Administration

  18. CX-008803: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Milling Machine Replacement Projects CX(s) Applied: B1.31 Date: 05/14/2012 Location(s): Tennessee Offices(s): Y-12 Site Office

  19. CX-007358: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Categorical Exclusion Determination Integration of the University of Oregon's Cogeneration Project CX(s) Applied: B1.7 Date: 12012011 Location(s): Oregon Offices(s):...

  20. CX-010155: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Augspurger Radio Tower Replacement Project CX(s) Applied: B1.19 Date: 04/03/2013 Location(s): Washington Offices(s): Bonneville Power Administration

  1. CX-001403: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Exclusion Determination CX-001403: Categorical Exclusion Determination West New York Energy Efficiency Projects CX(s) Applied: B5.1 Date: 04092010 Location(s): West New...

  2. CX-009210: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Silver Butte Fiber Burial Project CX(s) Applied: B.47 Date: 08/28/2012 Location(s): Montana, Montana Offices(s): Bonneville Power Administration

  3. CX-012117: Categorical Exclusion Determination | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Exclusion Determination CX-012117: Categorical Exclusion Determination Fuel Cell Hybrid Walk-In Van Deployment Project CX(s) Applied: A9 Date: 05212014 Location(s):...

  4. CX-007517: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    UPF Mock Wall Project CX(s) Applied: B3.6 Date: 11/29/2011 Location(s): Tennessee Offices(s): Y-12 Site Office

  5. CX-004085: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Determination Project T-221, Hazardous Material Management and Emergency Response (HAMMER) Operations Building CX(s) Applied: B1.15 Date: 10082010 Location(s): Richmond,...

  6. CX-100018: Categorical Exclusion Determination | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Determination Wind Generator Project CX(s) Applied: A9 Date: 08152014 Location(s): Michigan Offices(s): Golden Field Office Technology Office: Wind Program Award Number:...

  7. CX-000653: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Determination CX-000653: Categorical Exclusion Determination Helios - Project: Photovoltaic Crystalline Module Assembly Plant CX(s) Applied: B5.1 Date: 01272010 Location(s):...

  8. CX-002945: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Exclusion Determination CX-002945: Categorical Exclusion Determination Pennsylvania Green Energy Works Targeted Grant - Native Energy Biogas Project CX(s) Applied: B1.15,...

  9. CX-004376: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Categorical Exclusion Determination City of Woodward, Oklahoma Ground Source Heat Pump Project Beyond State Template CX(s) Applied: B5.1 Date: 11012010 Location(s):...

  10. CX-008571: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Project Blue Energy CX(s) Applied: A9 Date: 06/20/2012 Location(s): Utah Offices(s): Golden Field Office

  11. CX-000998: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Categorical Exclusion Determination CX-000998: Categorical Exclusion Determination Biodiesel Infrastructure Project (Coulee) CX(s) Applied: A1, A9, B5.1 Date: 01272010...

  12. CX-000712: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Categorical Exclusion Determination CX-000712: Categorical Exclusion Determination Biodiesel Infrastructure Project (Coulee) CX(s) Applied: A1, A9, B5.1 Date: 01272010...

  13. CX-006500: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Determination CX-006500: Categorical Exclusion Determination Magellan Des Moines Biodiesel Terminal Project CX(s) Applied: B5.1 Date: 09062011 Location(s): Des Moines, Iowa...

  14. CX-008588: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    St. Petersburg Solar Pilot Project CX(s) Applied: B5.1 Date: 07/19/2012 Location(s): Florida Offices(s): Golden Field Office

  15. CX-002698: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    98: Categorical Exclusion Determination CX-002698: Categorical Exclusion Determination Seismic Testing (Under Task 5 of Statement of Project Objectives) CX(s) Applied: B3.1 Date:...

  16. CX-012097: Categorical Exclusion Determination

    Broader source: Energy.gov [DOE]

    Microgrid Demonstration Project CX(s) Applied: B5.15 Date: 03/24/2014 Location(s): Idaho Offices(s): Idaho Operations Office

  17. CX-008624: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    Abandonment of the Western Sector Dynamic Underground Stripping (DUS) Project Steam Injection Wells CX(s) Applied: B3.1 Date: 06202012 Location(s): South Carolina...

  18. CX-005076: Categorical Exclusion Determination | Department of...

    Broader source: Energy.gov (indexed) [DOE]

    CX-005076: Categorical Exclusion Determination Jefferson County Sheriff's Department Propane Infrastructure Project CX(s) Applied: B5.1 Date: 01272011 Location(s): Jefferson,...

  19. CX-012122: Categorical Exclusion Determination

    Office of Energy Efficiency and Renewable Energy (EERE)

    OCGen Module Mooring Project CX(s) Applied: B5.25 Date: 04/29/2014 Location(s): Maine Offices(s): Golden Field Office

  20. GHPsRUS Project

    SciTech Connect (OSTI)

    Battocletti, Liz

    2013-07-09T23:59:59.000Z

    The GHPsRUS Project's full name is "Measuring the Costs and Benefits of Nationwide Geothermal Heat Pump Deployment." The dataset contains employment and installation price data collected by four economic surveys: (1)GHPsRUS Project Manufacturer & OEM Survey, (2) GHPsRUS Project Geothermal Loop Survey, (3) GHPsRUS Project Mechanical Equipment Installation Survey, and (4) GHPsRUS Geothermal Heat Pump Industry Survey

  1. GHPsRUS Project

    DOE Data Explorer [Office of Scientific and Technical Information (OSTI)]

    Battocletti, Liz

    The GHPsRUS Project's full name is "Measuring the Costs and Benefits of Nationwide Geothermal Heat Pump Deployment." The dataset contains employment and installation price data collected by four economic surveys: (1)GHPsRUS Project Manufacturer & OEM Survey, (2) GHPsRUS Project Geothermal Loop Survey, (3) GHPsRUS Project Mechanical Equipment Installation Survey, and (4) GHPsRUS Geothermal Heat Pump Industry Survey

  2. WIPP Projects Interative Map

    Broader source: Energy.gov [DOE]

    View WIPP Projects in a larger map. To report corrections, please email WeatherizationInnovation@ee.doe.gov.

  3. Bacteria TMDL Projects 

    E-Print Network [OSTI]

    Wythe, Kathy

    2007-01-01T23:59:59.000Z

    of the projects are listed below. ? Peach CreekWater Quality Improvement Project ? Monitoring and Educational Programs Focused on Bacteria and Nutrient Runoff on Dairy Operations in the LeonWatershed ? Development of the Plum CreekWPP ? Impact of Proper... Star Healthy Streams * ? Environmental Management of Grazing Lands * *TWRI-managed projects More information on the initiative is available at www.tsswcb.state.tx.us/managementprogram/ initiatives/bacteria. Bacteria Projects Across the State...

  4. Kansas Advanced Semiconductor Project

    SciTech Connect (OSTI)

    Baringer, P.; Bean, A.; Bolton, T.; Horton-Smith, G.; Maravin, Y.; Ratra, B.; Stanton, N.; von Toerne, E.; Wilson, G.

    2007-09-21T23:59:59.000Z

    KASP (Kansas Advanced Semiconductor Project) completed the new Layer 0 upgrade for D0, assumed key electronics projects for the US CMS project, finished important new physics measurements with the D0 experiment at Fermilab, made substantial contributions to detector studies for the proposed e+e- international linear collider (ILC), and advanced key initiatives in non-accelerator-based neutrino physics.

  5. Toward a State of Good Repair for Railroad Bridges through Structural Health Monitoring

    E-Print Network [OSTI]

    Bustamante, Fabián E.

    Toward a State of Good Repair for Railroad Bridges through Structural Health Monitoring NUTC of this research is to add a new tool to the asset management toolbox: structural health monitoring, particularly is Structural Health Monitoring (SHM)? SHM is process of intelligently collecting data from sensors on critical

  6. Multilayer sulfur-resistant composite metal membranes and methods of making and repairing the same

    DOE Patents [OSTI]

    Way, J. Douglas; Hatlevik, Oyvind

    2014-07-15T23:59:59.000Z

    The invention relates to thin, hydrogen-permeable, sulfur-resistant membranes formed from multi-layers of palladium or palladium-alloy coatings on porous, ceramic or metal supports, methods of making these membranes, methods of repairing layers of these membranes and devices that incorporate these membranes.

  7. Development/Plasticity/Repair Deletion of ERK2 Mitogen-Activated Protein Kinase

    E-Print Network [OSTI]

    Development/Plasticity/Repair Deletion of ERK2 Mitogen-Activated Protein Kinase Identifies Its Key University, Piscataway, New Jersey 08855-8082 The mitogen-activated protein (MAP) kinases ERK1 and ERK2-specific functions in vivo. We have examined the role of ERK2 in neural development by conditional inactivation

  8. Development/Plasticity/Repair The ERK2 Mitogen-Activated Protein Kinase Regulates the

    E-Print Network [OSTI]

    Development/Plasticity/Repair The ERK2 Mitogen-Activated Protein Kinase Regulates the Timing Oligodendrocytedevelopmentistightlycontrolledbyavarietyofextracellulargrowthanddifferentiationfactors.Themitogen-activated protein kinases (MAPKs), ERK1 and ERK2, are critical intracellular signaling (ERKs) are ubiquitously expressed, coordinately regulated, and highly similar, but Erk2 deletion in mice

  9. Development/Plasticity/Repair Phosphatidylinositol 3-Kinase Activates ERK in Primary

    E-Print Network [OSTI]

    Clapham, David E.

    Development/Plasticity/Repair Phosphatidylinositol 3-Kinase Activates ERK in Primary Sensory activation to inflammatory pain. We further investigated the correlationbetweenthePI3KandtheERK294002 and wortmannin, indicative of the activation of PI3K by both agents. ERK activation by capsaicin

  10. Development/Plasticity/Repair Disrupted ERK Signaling during Cortical Development Leads

    E-Print Network [OSTI]

    Development/Plasticity/Repair Disrupted ERK Signaling during Cortical Development Leads to Abnormal disorders arising from copy number variations in the ERK (extracellular signal-regulated kinase) MAP that these changes are due to ERK-dependent dysregulation of cyclin D1 and p27Kip1 , resulting in cell cycle

  11. Lazy Means Smart: Reducing Repair Bandwidth Costs in Erasure-coded Distributed Storage

    E-Print Network [OSTI]

    Alvisi, Lorenzo

    ,10)-encoded storage in this system results in hundreds of terabytes of daily recovery traffic through Top- Of an energy-conserving, storage-efficient, hybrid hadoop compute cluster. In Proceedings of the 2010Lazy Means Smart: Reducing Repair Bandwidth Costs in Erasure-coded Distributed Storage Mark

  12. FFaacciilliittiieess MMaannaaggeemmeenntt//EEnnvviirroonnmmeennttaall HHeeaalltthh && SSaaffeettyy Hazardous Work Area/Equipment Repair Form

    E-Print Network [OSTI]

    Mojzsis, Stephen J.

    Hazardous Work Area/Equipment Repair Form Form Instructions: Client is responsible for completing this form to assure that equipment and/or immediate work areas are not contaminated with any hazardous materials, tissue, etc.) Do Safety Hazards exist in the work area? N ___ Y ___ (Electrical, burn, or trip hazards

  13. Fast Interactive Simulations of Mitral Valve Repair Neil A. Tenenholtz, Peter E. Hammer, Robert D. Howe

    E-Print Network [OSTI]

    Fast Interactive Simulations of Mitral Valve Repair Neil A. Tenenholtz, Peter E. Hammer, Robert D. Howe Keywords: Surgical simulation, human-computer interaction, haptics, mitral valve, cardiac surgery. I. Problem Solved A healthy mitral valve ensures the one-way flow of oxygenated blood from the left

  14. Home Maintenance and Repair Owning a home is a major responsibility.

    E-Print Network [OSTI]

    maintenance is conducted. Regular, preventive maintenance can pay off in peace of mind, utility cost savings, routine maintenance helps to prolong the life of the home and may prevent the need for major repairs of Benjamin Franklin, "An ounce of prevention is worth a pound of cure." Regular, routine maintenance enhances

  15. Investigation of Corrosion Damage and Repair System in a Concrete Jetty Structure

    E-Print Network [OSTI]

    Mobasher, Barzin

    Investigation of Corrosion Damage and Repair System in a Concrete Jetty Structure Farid Moradi of the deterioration was reinforcement corrosion, which initiated within few years after the completion of the jetty structure. The structure underwent major corrosion rehabilitation after 7 years of service. Despite the use

  16. Development/Plasticity/Repair The Bone Morphogenetic Protein Roof Plate Chemorepellent

    E-Print Network [OSTI]

    Butler, Samantha

    Development/Plasticity/Repair The Bone Morphogenetic Protein Roof Plate Chemorepellent Regulates, Toronto, Ontario, Canada M5G 1X8 Commissural spinal axons extend away from the roof plate (RP) in response to the dorsal midline and are generated by the bone morphogenetic proteins (BMPs) in the roof plate (RP) (Liem

  17. Development/Plasticity/Repair A Structural MRI Study of Human Brain Development from

    E-Print Network [OSTI]

    Utah, University of

    Development/Plasticity/Repair A Structural MRI Study of Human Brain Development from Birth to 2 Carolina, Chapel Hill, North Carolina 27599-7510 Brain development in the first 2 years after birth and schizophrenia. Knowledge regarding this period is currently quite limited. We studied structural brain

  18. Efficacy of Low Level Laser Therapy After Hand Flexor Tendon Repair

    SciTech Connect (OSTI)

    Ayad, K. E.; Abd El Mejeed, S. F. [Faculty of Physical Therapy, Cairo University (Egypt); El Gohary, H. M.; Abd Elrahman, M.; Bekheet, A. B. [Al Sahel Teaching Hospital, Cairo (Egypt)

    2009-09-27T23:59:59.000Z

    Flexor tendon injury is a common problem requiring suturing repair followed by early postoperative mobilization. Muscle atrophy, joint stiffness, osteoarthritis, infection, skin necrosis, ulceration of joint cartilage and tendocutaneous adhesion are familiar complications produced by prolonged immobilization of surgically repaired tendon ruptures. The purpose of this study was to clarify the importance of low level laser therapy after hand flexor tendon repair in zone II. Thirty patients aging between 20 and 40 years were divided into two groups. Patients in group A (n = 15) received a conventional therapeutic exercise program while patients in group B (n = 15) received low level laser therapy combined with the same therapeutic exercise program. The results showed a statistically significant increase in total active motion of the proximal and distal interphalangeal joints as well as maximum hand grip strength at three weeks and three months postoperative, but improvement was more significant in group B. It was concluded that the combination of low level laser therapy and early therapeutic exercises was more effective than therapeutic exercises alone in improving total active motion of proximal and distal interphalangeal joints and hand grip strength after hand flexor tendon repair.

  19. Provably Repairing the ISO/IEC 9798 Standard for Entity Authentication

    E-Print Network [OSTI]

    Basin, David

    , or authentication of transmitted data [27,33]. The ISO (International Organization for Standardization) and IECProvably Repairing the ISO/IEC 9798 Standard for Entity Authentication David Basin, Cas Cremers the family of entity authentication protocols defined by the ISO/IEC 9798 standard and find numerous

  20. Provably Repairing the ISO/IEC 9798 Standard for Entity Authentication

    E-Print Network [OSTI]

    Basin, David

    (International Organization for Standardization) and IEC (Interna- tional Electrotechnical Commission) jointlyProvably Repairing the ISO/IEC 9798 Standard for Entity Authentication David Basin, Cas Cremers the family of entity authentication proto- cols defined by the ISO/IEC 9798 standard and find numerous

  1. Mitochondrial and nuclear DNA base excision repair are affected differently by caloric restriction1

    E-Print Network [OSTI]

    Stuart, Jeffrey A.

    Mitochondrial and nuclear DNA base excision repair are affected differently by caloric restriction1 of Biology, Brock University, St. Catharines, Ontario, Canada; and Gazi University, Faculty of Pharmacy in kidney mitochondria. 4. CR increases nuclear BER activity BER activity and the activities of proteins

  2. Development/Plasticity/Repair Dendritic Spine Dynamics Regulate the Long-Term Stability

    E-Print Network [OSTI]

    van Rossum, Mark

    Development/Plasticity/Repair Dendritic Spine Dynamics Regulate the Long-Term Stability of Synaptic Plasticity Cian O'Donnell,1,2 Matthew F. Nolan,3 and Mark C. W. van Rossum1 1Institute for Adaptive of Edinburgh, Edinburgh EH8 9XD, United Kingdom Long-term synaptic plasticity requires postsynaptic influx

  3. Development/Plasticity/Repair A Refractory Period for Rejuvenating GABAergic Synaptic

    E-Print Network [OSTI]

    Gruner, Daniel S.

    Development/Plasticity/Repair A Refractory Period for Rejuvenating GABAergic Synaptic Transmission and Ocular Dominance Plasticity with Dark Exposure Shiyong Huang,1* Yu Gu,2* Elizabeth M. Quinlan,2 Dark exposure initiated in adulthood reactivates robust ocular dominance plasticity in the visual

  4. Development/Plasticity/Repair Simultaneous NMDA-Dependent Long-Term Potentiation of

    E-Print Network [OSTI]

    Segal, Menahem

    Development/Plasticity/Repair Simultaneous NMDA-Dependent Long-Term Potentiation of EPSCs and Long activity-dependent long-term plasticity of neuronal networks is the interplay between excitatory, whereas a nitric oxide synthase inhibitor was ineffec- tive. Finally, network-induced plasticity

  5. The Stumbling Block in Lung Repair of Emphysema: Elastic Fiber Assembly

    E-Print Network [OSTI]

    Mecham, Robert

    The Stumbling Block in Lung Repair of Emphysema: Elastic Fiber Assembly Adrian Shifren and Robert P properties of the lung are largely determined by the connective tissue networks laid down during development. The macromolecules most important for lung mechanics and structural integrity are collagen, elastin

  6. Development/Plasticity/Repair Identification of Modulators of Hair Cell Regeneration in the

    E-Print Network [OSTI]

    Rubel, Edwin

    Development/Plasticity/Repair Identification of Modulators of Hair Cell Regeneration compounds that modulate hair cell regeneration in zebrafish. Of the 1680 compounds evaluated, we identified,aresyntheticglucocorticoidsthatpotentiatedhaircellnumbersduringregenerationandalsoinducedhair cell addition in the absence of damage. BrdU analysis confirmed that the extra hair cells arose from

  7. Development/Plasticity/Repair Hair Cell Replacement in Adult Mouse Utricles after

    E-Print Network [OSTI]

    Rubel, Edwin

    Development/Plasticity/Repair Hair Cell Replacement in Adult Mouse Utricles after Targeted Ablation of Hair Cells with Diphtheria Toxin Justin S. Golub,1 Ling Tong,1 Tot B. Ngyuen,1 Cliff R. Hume,1 Richard developed a transgenic mouse to permit conditional and selective ablation of hair cells in the adult mouse

  8. Product Guide Project Standard and Project Professional

    E-Print Network [OSTI]

    Narasayya, Vivek

    ................................................................................................................................................................6 Manage Projects and Programs, or other intellectual property that are the subject matter of this document. #12;Table of Contents .......................................................................................................9 Make It Yours ­ Personalize the Ribbon

  9. West Hackberry Tertiary Project. Quarterly technical progress report, January 1, 1996--March 31, 1996

    SciTech Connect (OSTI)

    Gillham, T.; Cerveny, B.; Turek, E.

    1996-04-10T23:59:59.000Z

    The goal of the West Hackberry Tertiary Project is to demonstrate the technical and economic feasibility of combining air injection with the Double Displacement Process for tertiary oil recovery. The Double Displacement Process is the gas displacement of a water invaded oil column for the purpose of recovering oil through gravity drainage. The novel aspect of this project is the use of air as the injection fluid. The target reservoir for the project is the Camerina C-1,2,3 sand located on the West Flank of West Hackberry Field in Cameron Parish, Louisiana. If successful, this project will demonstrate that the use of air injection in the Double Displacement Process can economically recover oil in reservoirs where tertiary oil recovery is presently uneconomic. The first quarter of 1996 was outstanding both in terms of volume of air injected and low cost operations. More air was injected during this quarter than in any preceding quarter. The compressors experienced much improved run time with minimal repairs. Low operating costs resulted from no repairs required for injection or production wells. A discussion of the following topics are contained herein: (1) performance summary for the injection and production wells, (2) air compressor operations, (3) updated bottom hole pressure data, (4) technology transfer activities and (5) plans for the upcoming quarter.

  10. The CHPRC Columbia River Protection Project Quality Assurance Project Plan

    SciTech Connect (OSTI)

    Fix, N. J.

    2008-11-30T23:59:59.000Z

    Pacific Northwest National Laboratory researchers are working on the CHPRC Columbia River Protection Project (hereafter referred to as the Columbia River Project). This is a follow-on project, funded by CH2M Hill Plateau Remediation Company, LLC (CHPRC), to the Fluor Hanford, Inc. Columbia River Protection Project. The work scope consists of a number of CHPRC funded, related projects that are managed under a master project (project number 55109). All contract releases associated with the Fluor Hanford Columbia River Project (Fluor Hanford, Inc. Contract 27647) and the CHPRC Columbia River Project (Contract 36402) will be collected under this master project. Each project within the master project is authorized by a CHPRC contract release that contains the project-specific statement of work. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by the Columbia River Project staff.

  11. River Protection Project (RPP) Project Management Plan

    SciTech Connect (OSTI)

    SEEMAN, S.E.

    2000-04-01T23:59:59.000Z

    The U.S. Department of Energy (DOE), in accordance with the Strom Thurmond National Defense Authorization Act for Fiscal Year 1999, established the Office of River Protection (ORP) to successfully execute and manage the River Protection Project (RPP), formerly known as the Tank Waste Remediation System (TWRS). The mission of the RPP is to store, retrieve, treat, and dispose of the highly radioactive Hanford tank waste in an environmentally sound, safe, and cost-effective manner. The team shown in Figure 1-1 is accomplishing the project. The ORP is providing the management and integration of the project; the Tank Farm Contractor (TFC) is responsible for providing tank waste storage, retrieval, and disposal; and the Privatization Contractor (PC) is responsible for providing tank waste treatment.

  12. Battleground Energy Recovery Project

    SciTech Connect (OSTI)

    Daniel Bullock

    2011-12-31T23:59:59.000Z

    In October 2009, the project partners began a 36-month effort to develop an innovative, commercial-scale demonstration project incorporating state-of-the-art waste heat recovery technology at Clean Harbors, Inc., a large hazardous waste incinerator site located in Deer Park, Texas. With financial support provided by the U.S. Department of Energy, the Battleground Energy Recovery Project was launched to advance waste heat recovery solutions into the hazardous waste incineration market, an area that has seen little adoption of heat recovery in the United States. The goal of the project was to accelerate the use of energy-efficient, waste heat recovery technology as an alternative means to produce steam for industrial processes. The project had three main engineering and business objectives: Prove Feasibility of Waste Heat Recovery Technology at a Hazardous Waste Incinerator Complex; Provide Low-cost Steam to a Major Polypropylene Plant Using Waste Heat; and ď?· Create a Showcase Waste Heat Recovery Demonstration Project.

  13. Operational Waste Volume Projection

    SciTech Connect (OSTI)

    STRODE, J.N.

    1999-08-24T23:59:59.000Z

    Waste receipts to the double-shell tank system are analyzed and wastes through the year 2018 are projected based on assumption as of July 1999. A computer simulation of site operations is performed, which results in projections of tank fill schedules, tank transfers, evaporator operations, tank retrieval, and aging waste tank usage. This projection incorporates current budget planning and the clean-up schedule of the Tri-Party Agreement.

  14. Operational Waste Volume Projection

    SciTech Connect (OSTI)

    STRODE, J.N.

    2000-08-28T23:59:59.000Z

    Waste receipts to the double-shell tank system are analyzed and wastes through the year 2015 are projected based on generation trends of the past 12 months. A computer simulation of site operations is performed, which results in projections of tank fill schedules, tank transfers, evaporator operations, tank retrieval, and aging waste tank usage. This projection incorporates current budget planning and the clean-up schedule of the Tri-Party Agreement. Assumptions were current as of June. 2000.

  15. Operational waste volume projection

    SciTech Connect (OSTI)

    Koreski, G.M.

    1996-09-20T23:59:59.000Z

    Waste receipts to the double-shell tank system are analyzed and wastes through the year 2015 are projected based on generation trends of the past 12 months. A computer simulation of site operations is performed, which results in projections of tank fill schedules, tank transfers, evaporator operations, tank retrieval, and aging waste tank usage. This projection incorporates current budget planning and the clean-up schedule of the Tri-Party Agreement. Assumptions were current as of June 1996.

  16. Project: BELLA Bldg. #: 71

    E-Print Network [OSTI]

    TO CONSTRUCTION AS OF 10/4/2011 Current/Approved Projects Project: Solar Energy Research Center Bldg. #:TBD. #: TBD Affected Area: R1 Road & V Road (58) Dates: 8/2011 - 9/2013 6 Small Projects: A. B50 Electrical/1/2014 N3 (58) 42 11/1/2011 2/1/2014 M-1 (35) 12 10/1/2010 11/1/2011 B81 (21) 18 10/1/2010 11/1/2011 V Road

  17. 2015 Technology Innovation Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    for RTU and Lighting Retrofits Energy Efficiency TIP 140: Energy Efficiency Emerging Technology Assessment and Demonstration Projects TIP 261: Determining and Improving the...

  18. Custom Renewable Energy Projects

    Broader source: Energy.gov [DOE]

    Project development assistance funding is available for a variety of purposes, including grant writing, feasibility studies, or technical assistance with design, permitting, or utility interconne...

  19. Mascoma: Frontier Biorefinery Project

    Broader source: Energy.gov [DOE]

    This project involves the construction and operation of a biorefinery that produces ethanol and other co-products from cellulosic materials through advanced consolidated bioprocessing.

  20. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    by FY12. 95% Line Item 85% Cleanup 97% Line Item 85% Cleanup EVM represents Earned Value Management. FY2011 Second Quarter Overall Contract and Project Management Improvement...

  1. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    by FY12. 95% Line Item 85% Cleanup 100% Line Item 88% Cleanup EVM represents Earned Value Management. FY2011 Fourth Quarter Overall Contract and Project Management Improvement...

  2. Contract/Project Management

    Energy Savers [EERE]

    by FY12. 95% Line Item 85% Cleanup 100% Line Item 88% Cleanup EVM represents Earned Value Management. FY2011 First Quarter Overall Contract and Project Management Performance...

  3. Contract/Project Management

    Energy Savers [EERE]

    by FY12. 95% Line Item 85% Cleanup 97% Line Item 89% Cleanup EVM represents Earned Value Management. FY2011 Third Quarter Overall Contract and Project Management Improvement...

  4. Recovery Act Project Stories

    Broader source: Energy.gov [DOE]

    Funded by the American Recovery and Reinvestment Act, these Federal Energy Management Program (FEMP) projects exemplify the range of technical assistance provided to federal agencies.

  5. Project Finance Case Studies

    Broader source: Energy.gov [DOE]

    Presentation covers the Project Finance Case Studies and is given at the Spring 2010 Federal Utility Partnership Working Group (FUPWG) meeting in Rapid City, South Dakota.

  6. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    capital asset line item projects (less than 50 million) are fully funded in one Fiscal Year (one Appropriation). NA NA Policy memorandum drafted and in review 12. Cost...

  7. TThe {\\sc Majorana} Project

    E-Print Network [OSTI]

    The MAJORANA collaboration

    2009-10-23T23:59:59.000Z

    The {\\sc Majorana} Project, a neutrinoless double-beta decay experiment is described with an emphasis on the choice of Ge-detector configuration.

  8. The MAJORANA project

    SciTech Connect (OSTI)

    Elliott, Steven R [Los Alamos National Laboratory

    2009-01-01T23:59:59.000Z

    The Majorana Project, a neutrinoless double-beta decay experiment is described with an emphasis on the choice of Ge-detector configuration.

  9. Energy Markets and Projections

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    National Governors Association Governors' Advisors Energy Policy Institute July 24, 2014 | Washington, DC By Adam Sieminski, EIA Administrator Energy Markets and Projections NGA...

  10. Our Project Regional, community,

    E-Print Network [OSTI]

    Minnesota, University of

    City departments -City Engineering and Traffic Engineering Public engagement early in project process modes and all users See.Safe.Smart.Rochester campaign to decrease modal conflict Connection

  11. Barstow Wind Turbine Project

    Broader source: Energy.gov [DOE]

    Presentation covers the Barstow Wind Turbine project for the Federal Utility Partnership Working Group (FUPWG) meeting, held on November 18-19, 2009.

  12. Prison Solar Project

    Broader source: Energy.gov [DOE]

    Presentation covers the Prison Solar Project for the Federal Utility Partnership Working Group (FUPWG) meeting, held on November 18-19, 2009.

  13. Using Differential Adhesion to Control Self-Assembly and Self-Repair of Collections of Modular Mobile Robots 

    E-Print Network [OSTI]

    Ottery, Peter

    This thesis presents a novel distributed control method which allows a collection of independently mobile robotic units, with two or three dimensional movement, to self-assemble into self-repairing hierarchical structures. ...

  14. The role of vascular endothelial growth factor (VEGF) in repair and recovery from acute respiratory distress syndrome (ARDS) 

    E-Print Network [OSTI]

    Medford, Andrew R.L

    2007-01-01T23:59:59.000Z

    Acute Respiratory Distress Syndrome (ARDS) is the most extreme form of acute lung injury and continues to have a significant morbidity and mortality. Unfortunately, the mechanisms involved in the recovery and repair of ...

  15. River Protection Project (RPP) Project Management Plan

    SciTech Connect (OSTI)

    NAVARRO, J.E.

    2001-03-07T23:59:59.000Z

    The Office of River Protection (ORP) Project Management Plan (PMP) for the River Protection Project (RPP) describes the process for developing and operating a Waste Treatment Complex (WTC) to clean up Hanford Site tank waste. The Plan describes the scope of the project, the institutional setting within which the project must be completed, and the management processes and structure planned for implementation. The Plan is written from the perspective of the ORP as the taxpayers' representative. The Hanford Site, in southeastern Washington State, has one of the largest concentrations of radioactive waste in the world, as a result of producing plutonium for national defense for more than 40 years. Approximately 53 million gallons of waste stored in 177 aging underground tanks represent major environmental, social, and political challenges for the U.S. Department of Energy (DOE). These challenges require numerous interfaces with state and federal environmental officials, Tribal Nations, stakeholders, Congress, and the US Department of Energy-Headquarters (DOE-HQ). The cleanup of the Site's tank waste is a national issue with the potential for environmental and economic impacts to the region and the nation.

  16. Repair of localized defects in multilayer-coated reticle blanks for extreme ultraviolet lithography

    DOE Patents [OSTI]

    Stearns, Daniel G. (Los Altos, CA); Sweeney, Donald W. (San Ramon, CA); Mirkarimi, Paul B. (Sunol, CA)

    2004-11-23T23:59:59.000Z

    A method is provided for repairing defects in a multilayer coating layered onto a reticle blank used in an extreme ultraviolet lithography (EUVL) system. Using high lateral spatial resolution, energy is deposited in the multilayer coating in the vicinity of the defect. This can be accomplished using a focused electron beam, focused ion beam or a focused electromagnetic radiation. The absorbed energy will cause a structural modification of the film, producing a localized change in the film thickness. The change in film thickness can be controlled with sub-nanometer accuracy by adjusting the energy dose. The lateral spatial resolution of the thickness modification is controlled by the localization of the energy deposition. The film thickness is adjusted locally to correct the perturbation of the reflected field. For example, when the structural modification is a localized film contraction, the repair of a defect consists of flattening a mound or spreading out the sides of a depression.

  17. Nondestructive evaluation and characterization of damage and repair to continuous-fiber ceramic composite panels.

    SciTech Connect (OSTI)

    Sun, J. G.; Petrak, D. R.; Pillai, T. A. K.; Deemer, C.; Ellingson, W. A.

    1998-04-01T23:59:59.000Z

    Continuous fiber ceramic matrix composites are currently being developed for a variety of high-temperature applications. Because of the high costs of making these components, minor damage incurred during manufacturing or operation must be rewired in order to extend the life of the components. In this study, five ceramic-grade Nicalon{trademark} fiber/SiNC-matrix composite panels were intentionally damaged with a pendulum-type impactor during an impact test. The damaged panels were then repaired at Dow Corning Corporation. Three nondestructive evaluation (NDE) methods were used to study the characteristics of the panels after the damage and again after the panels were repaired. The NDE methods were X-ray radiography, infrared thermal imaging, and air-coupled ultrasound. The results showed that the impact test induced various types of damage in the panels. The NDE data that were obtained by the three NDE methods were correlated with each other.

  18. Weld Repair of a Stamped Pressure Vessel in a Radiologically Controlled Zone

    SciTech Connect (OSTI)

    Cannell, Gary L. [Fluor Enterprises, Inc.; Huth, Ralph J. [CH2MHill Plateau Remediation Company; Hallum, Randall T. [Fluor Government Group

    2013-08-26T23:59:59.000Z

    In September 2012 an ASME B&PVC Section VIII stamped pressure vessel located at the DOE Hanford Site Effluent Treatment Facility (ETF) developed a through-wall leak. The vessel, a steam/brine heat exchanger, operated in a radiologically controlled zone (by the CH2MHill PRC or CHPRC), had been in service for approximately 17 years. The heat exchanger is part of a single train evaporator process and its failure caused the entire system to be shut down, significantly impacting facility operations. This paper describes the activities associated with failure characterization, technical decision making/planning for repair by welding, logistical challenges associated with performing work in a radiologically controlled zone, performing the repair, and administrative considerations related to ASME code requirements.

  19. Subterranean barriers, methods, and apparatuses for forming, inspecting, selectively heating, and repairing same

    DOE Patents [OSTI]

    Nickelson, Reva A. (Shelley, ID); Sloan, Paul A. (Rigby, ID); Richardson, John G. (Idaho Falls, ID); Walsh, Stephanie (Idaho Falls, ID); Kostelnik, Kevin M. (Idaho, ID)

    2009-04-07T23:59:59.000Z

    A subterranean barrier and method for forming same are disclosed, the barrier including a plurality of casing strings wherein at least one casing string of the plurality of casing strings may be affixed to at least another adjacent casing string of the plurality of casing strings through at least one weld, at least one adhesive joint, or both. A method and system for nondestructively inspecting a subterranean barrier is disclosed. For instance, a radiographic signal may be emitted from within a casing string toward an adjacent casing string and the radiographic signal may be detected from within the adjacent casing string. A method of repairing a barrier including removing at least a portion of a casing string and welding a repair element within the casing string is disclosed. A method of selectively heating at least one casing string forming at least a portion of a subterranean barrier is disclosed.

  20. Template strand scrunching during DNA gap repair synthesis by human polymerase [lamda

    SciTech Connect (OSTI)

    Garcia-Diaz, Miguel; Bebenek, Katarzyna; Larrea, Andres A.; Havener, Jody M.; Perera, Lalith; Krahn, Joseph M.; Pedersen, Lars C.; Ramsden, Dale A.; Kunkel, Thomas A.; (NIH); (UNC)

    2009-09-25T23:59:59.000Z

    Family X polymerases such as DNA polymerase {lambda}(Pol {lambda}) are well suited for filling short gaps during DNA repair because they simultaneously bind both the 5{prime} and 3{prime} ends of short gaps. DNA binding and gap filling are well characterized for 1-nucleotide (nt) gaps, but the location of yet-to-be-copied template nucleotides in longer gaps is unknown. Here we present crystal structures revealing that, when bound to a 2-nt gap, Pol {lambda} scrunches the template strand and binds the additional uncopied template base in an extrahelical position within a binding pocket that comprises three conserved amino acids. Replacing these amino acids with alanine results in less processive gap filling and less efficient NHEJ when 2-nt gaps are involved. Thus, akin to scrunching by RNA polymerase during transcription initiation, scrunching occurs during gap filling DNA synthesis associated with DNA repair.

  1. "You Can Do It" Basic Home Repair Using Hand and Power Tools

    E-Print Network [OSTI]

    1 "You Can Do It" Basic Home Repair Using Hand and Power Tools by Janie L. Harris Extension Housing guard housing. Place the tool rest 1/8 inch from the wheel on bench-mounted units. Before starting://www.cdc.gov/nasd/docs/ University of Denver, Risk Management http://www.du.edu/risk/Tool_Safety.html #12;2 "You Can Do It" Basic

  2. The strengthening and repair of underground structures: A new approach to the management of nuclear waste

    SciTech Connect (OSTI)

    Colgate, S.A.

    1991-01-01T23:59:59.000Z

    This paper presents three closely related ideas and technologies: (1) The secure, repairable, long time confinement of nuclear radioactive waste underground by a large surrounding region of compressive overstress; (2) The inherent tectonic weakness and vulnerability of the normal underground environment and its modification by overstress; (3) The process of creating overstress by the sequential periodic high pressure injection of a finite gel strength rapid setting grout. 12 refs., 6 figs.

  3. Note: A Graph-Theoretical Approach to Level of Repair Analysis

    E-Print Network [OSTI]

    2004-08-29T23:59:59.000Z

    Aug 29, 2004 ... cilities to minimize overall life-cycle costs. ... decisions, LORA seeks to determine an optimal provision of repair and maintenance ... Their heuristic is based on a relaxation of LORA into a pair of ... R2 is a consequence of R1 and a policy of .... from the fact that one can find a minimum cut in N(B) in time O(n2.

  4. Lethal Hemorrhage Caused by Aortoesophageal Fistula Secondary to Stent-Graft Repair of the Thoracic Aorta

    SciTech Connect (OSTI)

    Sager, Hendrik B., E-mail: hendrik.sager@uk-sh.de [Universitaet zu Luebeck, Medizinische Klinik II (Germany); Wellhoener, Peter [Universitaet zu Luebeck, Medizinische Klinik I (Germany); Wermelt, Johanna A. [Klinikum Neustadt, Klinik fuer Innere Medizin (Germany); Schunkert, Heribert; Kurowski, Volkhard [Universitaet zu Luebeck, Medizinische Klinik II (Germany)

    2011-02-15T23:59:59.000Z

    Aortoesophageal fistula (AEF) is a rare but life-threatening complication after endovascular or surgical aortic repair. Here we report a patient with AEF secondary to aortic stent-placement 2 years earlier who presented with hematemesis and died from hemorrhagic shock. By means of this case and the literature, we highlight potential bleeding sources in such a scenario because this is of crucial importance for the management strategy.

  5. REPAIR OF A DAMAGED PART ON HYDRAULIC TRACT KAPLAN TURBINE WITH "LIQUID METAL"

    E-Print Network [OSTI]

    Fuad ?atovi?; Prof Emeritus; Edin Džiho Msc; Mostar Bih; Mustafa Šehi?; Hydroelectric Power Plant Neretva; Jablanica Bih

    During 2011 on unit no.2 reparation work was carried out aimed at fault removal on Kaplan turbine impeller, while extending the lifespan of the entire installed equipment. The overhaul included all vital parts, replacement of all gasket compresses, machine processing to achieve the required tolerances, NDT equipment control according to "Quality Control Plan", repairing equipment, etc. This paper describes the recovery of defects on the blades of the guide vanes using epoxy masses.

  6. Endovascular Repair of a Pseudoaneurysm of the Abdominal Aorta Secondary to Translumbar Aortography

    SciTech Connect (OSTI)

    Mir, Naheed; Nunzio, Mario De; Pollock, John G [Derbyshire Royal Infirmary, Department of Clinical Radiology (United Kingdom)], E-mail: JG.Pollock@derbyhospitals.nhs.uk

    2006-12-15T23:59:59.000Z

    This report describes an incidental finding of a pseudoaneurysm of the abdominal aorta on a computed tomography (CT) renal angiogram during investigation of chronic renal failure in a 73-year-old man. The patient had undergone a translumbar aortogram 20 years previously. An increase in the size of the aneurysm by 7 mm over 6 months prompted treatment and the aneurysm underwent successful endovascular repair with a custom-made stent-graft.

  7. The Home Microbiome Project

    ScienceCinema (OSTI)

    Gilbert, Jack

    2014-09-15T23:59:59.000Z

    The Home Microbiome Project is an initiative aimed at uncovering the dynamic co-associations between people's bacteria and the bacteria found in their homes.The hope is that the data and project will show that routine monitoring of the microbial diversity of your body and of the environment in which you live is possible.

  8. Bacteria TMDL Projects

    E-Print Network [OSTI]

    Wythe, Kathy

    2007-01-01T23:59:59.000Z

    of TMDL projects for water bodies where swimming or wading may be unsafe or harvesting of oysters is limited or prohibited due to high concentrations of bacteria. ? Atascosa River: A TMDL Project for Bacteria ? Buffalo andWhite Oak Bayous: A TMDL...

  9. The DNA Single-Strand Break Repair Machinery Facilitates CAF-1-Mediated Histone Deposition at Oxidative DNA Strand Breaks

    E-Print Network [OSTI]

    Arman Nabatiyan; Zhihong Zeng; Keith W. Caldecott

    2012-02-01T23:59:59.000Z

    Oxidative DNA single strand breaks arise continuously in cells and defects in their repair have been implicated in neurological disease. While much progress has been made in understanding how chromosomal single strand breaks are repaired little is known about the changes chromatin structure that accompany this process. Here, we show that nascent recombinant histone H3.1 protein accumulates and is deposited into chromatin at sites of DNA strand breakage in quiescent human cells following oxidative stress, and that core components of the single-strand break repair machinery are required for this process. We show that the SSBR sensor and scaffold proteins poly (ADP-ribose) polymerase and XRCC1 facilitate accumulation of chromatin assembly factor-1 (CAF-1) at sites of oxidative DNA strand breakage, which in turn mediates the deposition of Histone H3.1. We also demonstrate that depletion of CAF-1 slows global rates of DNA strand break repair in quiescent cells following oxidative stress, demonstrating that single-strand break repair and histone deposition are tightly coordinated processes. These data describe a novel role for the DNA singlestrand break repair machinery and implicate histone turnover as a core component of the cellular response of quiescent cells to oxidative damage.

  10. Plasma transferred arc repair welding of the nickel-base superalloy IN-738LC

    SciTech Connect (OSTI)

    Su, C.Y.; Chou, C.P. [National Chiao Tung Univ., Hsinchu (Taiwan, Province of China). Dept. of Mechanical Engineering; Wu, B.C.; Lih, W.C. [Industrial Technology Research Inst., Hsinchu (Taiwan, Province of China). Materials Research Labs.

    1997-10-01T23:59:59.000Z

    Plasma transferred arc welding (PTA) has been considered a promising process to restore worn areas of land-based gas turbine blades and vanes. The objective of this investigation was to study the effect of PTA welding on the repairing of IN-738LC superalloy components. Tensile tests were conducted on specimens welded with various combinations of parameters. Room temperature, 760 C, and 980 C were selected as tensile test temperatures. High-temperature phase transformed, during solidification, were identified by differential thermal analysis (DTA). The weld-pool shapes and microstructures of welded specimens prepared by various welding parameters were evaluated by optical metallography (OM), a scanning electron microscope (SEM) equipped with energy dispersive x-ray spectrometer (EDS), and microhardness testing. Results of this study showed that PTA welded specimens exhibited 96% nominal tensile strength of IN-738LC base materials. Specimen failure was observed predominantly in the base materials instead of in the heat-affected zone (HAZ) for gas tungsten arc weld (GTAW) repair weldments. IN-738LC is considered susceptible to weld cracking during fusion welding; however, using a low-input repair welding process (PTA), cracking susceptibility could be minimized by the optimized welding parameters.

  11. North American LNG Project Sourcebook

    SciTech Connect (OSTI)

    NONE

    2007-06-15T23:59:59.000Z

    The report provides a status of the development of LNG Import Terminal projects in North America, and includes 1-2 page profiles of 63 LNG projects in North America which are either in operation, under construction, or under development. For each project, the sourcebook provides information on the following elements: project description, project ownership, project status, projected operation date, storage capacity, sendout capacity, and pipeline interconnection.

  12. LENS repair and modification of metal NW components:materials and applications guide.

    SciTech Connect (OSTI)

    Smugeresky, John E. (Sandia National Laboratories, Livermore, CA); Gill, David Dennis; Oberhaus, Jason (BWXT Y-12); Adams, Thad (Savannah River National Laboratory); VanCamp, Chad (Kansas City Plant)

    2006-11-01T23:59:59.000Z

    Laser Engineered Net Shaping{trademark} (LENS{reg_sign}) is a unique, layer additive, metal manufacturing technique that offers the ability to create fully dense metal features and components directly from a computer solid model. LENS offers opportunities to repair and modify components by adding features to existing geometry, refilling holes, repairing weld lips, and many other potential applications. The material deposited has good mechanical properties with strengths typically slightly higher that wrought material due to grain refinement from a quickly cooling weld pool. The result is a material with properties similar to cold worked material, but without the loss in ductility traditionally seen with such treatments. Furthermore, 304L LENS material exhibits good corrosion resistance and hydrogen compatibility. This report gives a background of the LENS process including materials analysis addressing the requirements of a number of different applications. Suggestions are given to aid both the product engineer and the process engineer in the successful utilization of LENS for their applications. The results of testing on interface strength, machinability, weldability, corrosion resistance, geometric effects, heat treatment, and repair strategy testing are all included. Finally, the qualification of the LENS process is briefly discussed to give the user confidence in selecting LENS as the process of choice for high rigor applications. The testing showed LENS components to have capability in repair/modification applications requiring complex castings (W80-3 D-Bottle bracket), thin wall parts requiring metal to be rebuilt onto the part (W87 Firing Set Housing and Y-12 Test Rings), the filling of counterbores for use in reservoir reclamation welding (SRNL hydrogen compatibility study) and the repair of surface defects on pressure vessels (SRNL gas bottle repair). The material is machinable, as testing has shown that LENS deposited material machines similar to that of welded metal. Tool wear is slightly higher in LENS material than in wrought material, but not so much that one would be concerned with increased tooling cost. The LENS process achieved process qualification for the AY1E0125 D-Bottle Bracket from the W80-3 LEP program, and in the effort, also underwent testing in weapons environments. These tests included structural dynamic response testing and drop testing. The LENS deposited parts were compared in these tests with conventionally machined parts and showed equivalency to such an extent that the parts were accepted for use in parallel path subsystem-level weapon environment testing. The evaluation of LENS has shown that the process can be a viable option when either complete metal parts are needed or existing metal parts require modification or repair. The LENS Qualification Technology Investment team successfully investigated new applications for the LENS process and showed that it has great applicability across the Nuclear Weapons Complex as well as in other high rigor applications.

  13. Energy Efficiency Measures to Incorporate into Remodeling Projects

    SciTech Connect (OSTI)

    Liaukus, C.

    2014-12-01T23:59:59.000Z

    Energy improvements in a home are often approached as one concerted effort, beginning with a simple walk-through assessment or more in-depth energy audit and followed by the installation of recommended energy measures. While this approach allows for systems thinking to guide the efforts, comprehensive energy improvements of this nature are undertaken by a relatively small number of the households in our nation compared to more piecemeal remodeling efforts. Even when programs like the Weatherization Assistance Program and Home Performance with ENERGY STAR are considered, homes that have had a comprehensive energy makeover still represent a small fraction of the 111.1 million households. In this report, the U.S Department of Energy Building America Retrofit Alliance research team looks at the improvement of a home's energy performance in an opportunistic way: it examines what can be done to incorporate energy efficiency measures into general remodeling work and home repair projects. This allows for the possibility for people who would not normally pursue energy efficiency but will remodel their kitchen or re-side their home to improve their home's performance at the same time. There are challenges to this approach, not the least of which being that the work will take place over time in potentially many separate projects. The opportunity to improve a home's energy efficiency at one time expands or contracts with the scope of the remodel. As such, guidance on how to do each piece thoughtfully and with consideration for potential future projects, is critical.

  14. NAVAJO ELECTRIFICATION DEMONSTRATION PROJECT

    SciTech Connect (OSTI)

    Terry W. Battiest

    2008-06-11T23:59:59.000Z

    The Navajo Electrification Demonstration Project (NEDP) is a multi-year project which addresses the electricity needs of the unserved and underserved Navajo Nation, the largest American Indian tribe in the United States. The program serves to cumulatively provide off-grid electricty for families living away from the electricty infrastructure, line extensions for unserved families living nearby (less than 1/2 mile away from) the electricity, and, under the current project called NEDP-4, the construction of a substation to increase the capacity and improve the quality of service into the central core region of the Navajo Nation.

  15. LIMB demonstration project extension

    SciTech Connect (OSTI)

    Not Available

    1990-09-21T23:59:59.000Z

    The purpose of the DOE limestone injection multistage burner (LIMB) Demonstration Project Extension is to extend the data base on LIMB technology and to expand DOE's list of Clean Coal Technologies by demonstrating the Coolside process as part of the project. The main objectives of this project are: to demonstrate the general applicability of LIMB technology by testing 3 coals and 4 sorbents (total of 12 coal/sorbent combinations) at the Ohio Edison Edgewater plant; and to demonstrate that Coolside is a viable technology for improving precipitator performance and reducing sulfur dioxide emissions while acceptable operability is maintained. Progress is reported. 3 figs.

  16. NEPA COMPLIANCE SURVEY Project Information Project Title: Casing...

    Broader source: Energy.gov (indexed) [DOE]

    Casing Drilling Test Date: 5-17-201 1 DOE Code: 6730-020-72000 Contractor Code: 8067-806 Project Lead: Marl< Duletsky Project Overview 1, Brief project description nclude The...

  17. Kellogg and Russ Forest projects. 2002 Project sand highlights

    E-Print Network [OSTI]

    Kellogg and Russ Forest projects. 2002 Project sand highlights MacCready Reserve a new property of insects Galeerucella calmariensis,and G.pusilla to control purple loosestrife on May 13. #12;New Project

  18. NEPA COMPLIANCE SURVEY Project Information Project Title: South...

    Broader source: Energy.gov (indexed) [DOE]

    Facility 2 Da te: 1-6-10 DOE Code: 6730.020.0000 Contracto r Code: 8067-788 Project Lead: Anthony Bowler Project Ove rview The purpose of the project is to build an additional...

  19. Flash Steam Recovery Project 

    E-Print Network [OSTI]

    Bronhold, C. J.

    2000-01-01T23:59:59.000Z

    /condensate recovery system, resulting in condensate flash steam losses to the atmosphere. Using computer simulation models and pinch analysis techniques, the Operational Excellence Group (Six Sigma) was able to identify a project to recover the flash steam losses as a...

  20. RM Power Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    rate-setting functions were integrated in 1990. The projects serve Colorado, Kansas, Nebraska and Wyoming with 830 MW of installed capacity and 3,360 miles of transmission line....

  1. Navajo Electrification Demonstraiton Project

    SciTech Connect (OSTI)

    Larry Ahasteen, Project Manager

    2006-07-17T23:59:59.000Z

    This is a final technical report required by DOE for the Navajo Electrification Demonstration Program, This report covers the electric line extension project for Navajo families that currently without electric power.

  2. Financing energy efficiency projects

    SciTech Connect (OSTI)

    Hansen, S.J.; Weisman, J.C. [Hansen Associates (United States)

    1999-07-01T23:59:59.000Z

    Getting an energy project financed should be a shared effort between the ESCO and the customer, but the perspectives are different. It is the ESCO`s responsibility to put together a bankable project. The ESCO typically arranges the financing. Its reputation and history often add surety, which offers financiers added confidence. The customer usually incurs the debt and needs to know the financing options available. This article first addresses what constitutes a bankable project from the ESCO perspective. Then, the types of financing available to owners are explored. ESCOs, who have been in this business for a few years, remember knocking on the financial doors until their knuckles were bloody. Today, the financiers knock on the ESCO doors...if, and it`s a big IF, ESCOs can put together bankable projects.

  3. Contract/Project Management

    Broader source: Energy.gov (indexed) [DOE]

    EVM Systems: Post CD-3, (greater than 20 million). 95%* 94% EVM represents Earned Value Management. Certified FPD's at CD-1: Projects have certified FPDs no later than CD-1....

  4. Contract/Project Management

    Energy Savers [EERE]

    EVM Systems: Post CD-3, (greater than 20 million). 95%* 98% EVM represents Earned Value Management. Certified FPD's at CD-1: Projects have certified FPDs no later than CD-1....

  5. Contract/Project Management

    Office of Environmental Management (EM)

    EVM Systems: Post CD-3, (greater than 20 million). 95%* 100% EVM represents Earned Value Management. Certified FPD's at CD-1: Projects have certified FPDs no later than CD-1....

  6. Contract/Project Management

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    EVM Systems: Post CD-3, (greater than 20 million). 95%* 96% EVM represents Earned Value Management. Certified FPD's at CD-1: Projects have certified FPDs no later than CD-1....

  7. IT Project Manager

    Broader source: Energy.gov [DOE]

    This position is located in the IT Project Management Office (JP). A successful candidate in this position will serve as an IT Program Manager and technical expert responsible for directly managing...

  8. Healthcare Project Performance Benchmarks

    Broader source: Energy.gov [DOE]

    Reports five major performance metrics that can be used to benchmark proposed energy service company projects within the healthcare industry, disaggregated and reported by major retrofit strategy. Author: U.S. Department of Energy

  9. Simulation Server Project 25

    E-Print Network [OSTI]

    1 Simulation Server for Project 25: Inter-RF Subsystem Interface (ISSI) September 30, 2011 Simulation Server v1.0.0 #12;2 1. Executive Overview..................................................................................................................... 5 3.1. Starting the Server

  10. Quality Assurance Project Plan

    SciTech Connect (OSTI)

    Holland, R. C.

    1998-06-01T23:59:59.000Z

    This Quality Assurance Project Plan documents the quality assurance activities for the Wastewater/Stormwater/Groundwater and Environmental Surveillance Programs. This QAPP was prepared in accordance with DOE guidance on compliance with 10CFR830.120.

  11. Contract/Project Management

    Office of Environmental Management (EM)

    Post-CAP This is based on a 3-year rolling average (FY08 to FY10). TPC is Total Project Cost. 2a. EM Cleanup (Soil and Groundwater Remediation, D&D, and Waste Treatment and...

  12. St. Bernard Project Update

    Broader source: Energy.gov [DOE]

    The folks at St. Bernard Project are helping survivors of Hurricane Katrina get back into their homes -- and are using new technologies to reduce energy and save money for the returning residents.

  13. Contract/Project Management

    Energy Savers [EERE]

    Qtr FY09 completions. This is a 3-year rolling average (FY07 to FY09). 2. EM Cleanup (Soil and Groundwater Remediation, D&D, and Waste Treatment and Disposal) Projects: 90% of EM...

  14. Contract/Project Management

    Energy Savers [EERE]

    in the 2 nd Qtr FY09. This is a 3-year rolling average (FY07 to FY09). 2. EM Cleanup (Soil and Groundwater Remediation, D&D, and Waste Treatment and Disposal) Projects: 90% of EM...

  15. RESEARCH PROJECTS February 13

    E-Print Network [OSTI]

    Schenato, Luca

    will demonstrate geothermal heat pump (GSHP) systems for heating and cooling of measured SPF>5,0 in 8 demonstration systems for heating and cooling in Mediterranean climate PROJECT REFERENCE: 218895 CALL: FP7-ENERGY-2007

  16. Portsmouth Paducah Project Office

    Broader source: Energy.gov [DOE]

    U.S. Department of Energy (DOE) established the Portsmouth/Paducah Project Office (PPPO) on October 1, 2003, to provide focused leadership to the Environmental Management missions at the Portsmouth...

  17. Offshore Wind Project Map

    Broader source: Energy.gov [DOE]

    Image that shows the demonstration project site and developer headquarters for two funding opportunity announcements: the 2011 Grants for Technology Development and the 2011 Grants for Removing Market Barriers.

  18. Y-12 Steam Plant Project Received National Recognition for Project...

    National Nuclear Security Administration (NNSA)

    Steam Plant Project Received National Recognition for Project Management Excellence | National Nuclear Security Administration Facebook Twitter Youtube Flickr RSS People Mission...

  19. NNSA project receives DOE Secretary's Award for Project Management...

    National Nuclear Security Administration (NNSA)

    project receives DOE Secretary's Award for Project Management Improvement | National Nuclear Security Administration Facebook Twitter Youtube Flickr RSS People Mission Managing the...

  20. The Mississippi CCS Project

    SciTech Connect (OSTI)

    Doug Cathro

    2010-09-30T23:59:59.000Z

    The Mississippi CCS Project is a proposed large-scale industrial carbon capture and sequestration (CCS) project which would have demonstrated advanced technologies to capture and sequester carbon dioxide (CO{sub 2}) emissions from industrial sources into underground formations. Specifically, the Mississippi CCS Project was to accelerate commercialization of large-scale CO{sub 2} storage from industrial sources by leveraging synergy between a proposed petcoke to Substitute Natural Gas (SNG) plant that is selected for a Federal Loan Guarantee and would be the largest integrated anthropogenic CO{sub 2} capture, transport, and monitored sequestration program in the U.S. Gulf Coast Region. The Mississippi CCS Project was to promote the expansion of enhanced oil recovery (EOR) in the Mississippi, Alabama and Louisiana region which would supply greater energy security through increased domestic energy production. The capture, compression, pipeline, injection, and monitoring infrastructure would have continued to sequester CO{sub 2} for many years after the completion of the term of the DOE agreement. The objectives of this project were expected to be fulfilled through two distinct phases. The overall objective of Phase 1 was to develop a fully definitive project basis for a competitive Renewal Application process to proceed into Phase 2 - Design, Construction and Operations. Phase 1 included the studies that establish the engineering design basis for the capture, compression and transportation of CO{sub 2} from the MG SNG Project, and the criteria and specifications for a monitoring, verification and accounting (MVA) plan at the Soso oil field in Mississippi. The overall objective of Phase 2, was to execute design, construction and operations of three capital projects: the CO{sub 2} capture and compression equipment, the Mississippi CO{sub 2} Pipeline to Denbury's Free State Pipeline, and an MVA system at the Soso oil field.

  1. Black Pine Circle Project

    ScienceCinema (OSTI)

    Mytko, Christine

    2014-09-15T23:59:59.000Z

    A group of seventh graders from Black Pine Circle school in Berkeley had the opportunity to experience the Advanced Light Source (ALS) as "users" via a collaborative field trip and proposal project. The project culminated with a field trip to the ALS for all seventh graders, which included a visit to the ALS data visualization room, a diffraction demonstration, a beamline tour, and informative sessions about x-rays and tomography presented by ALS scientists.

  2. Baytown Energy Project

    E-Print Network [OSTI]

    Porter, J.

    2006-01-01T23:59:59.000Z

    which maximize the yield of saleable products. Distillation towers consume most of the energy required for aromatics separation. BEP reconfigured the existing towers in the product recovery section to a new fractionation scheme. The new... and toluene sidestream from the primary benzene recovery tower. The result was a 30% reduction in energy in the benzene/toluene fractionation area. The project also debottlenecked the toluene disproportionation unit by 20%. The project was completed...

  3. Black Pine Circle Project

    SciTech Connect (OSTI)

    Mytko, Christine

    2014-03-31T23:59:59.000Z

    A group of seventh graders from Black Pine Circle school in Berkeley had the opportunity to experience the Advanced Light Source (ALS) as "users" via a collaborative field trip and proposal project. The project culminated with a field trip to the ALS for all seventh graders, which included a visit to the ALS data visualization room, a diffraction demonstration, a beamline tour, and informative sessions about x-rays and tomography presented by ALS scientists.

  4. BEACON SOLAR ENERGY PROJECT (08-AFC-2) Project Title: Beacon Solar Energy Project (Beacon)

    E-Print Network [OSTI]

    BEACON SOLAR ENERGY PROJECT (08-AFC-2) FACT SHEET Project Title: Beacon Solar Energy Project (Beacon) Sponsor: Beacon Solar, LLC (Beacon Solar), a Delaware limited liability company and wholly owned and operate the Beacon Solar Energy Project (Beacon). Location: The project is located in eastern Kern County

  5. GREEN JOBS PROJECT Daniel Kammen

    E-Print Network [OSTI]

    Kammen, Daniel M.

    GREEN JOBS PROJECT Memo Daniel Kammen Meng Cai Karim El Alami December 2nd , 2014 #12;Contents.............................................................................................................................................3 1 Base of the Green jobs project per state ........................................................................................3 1.1 The Green jobs project from 2009

  6. ENLACE Mentor Project **.......................................................... Student Affairs

    E-Print Network [OSTI]

    de Lijser, Peter

    1 2 2 3 3 4 4 1 ENLACE Mentor Project .......................................................................... 5 #12;ENLACE Mentor Project Program Description: The ENLACE Mentor Project is designed to encourage employment opportunities, counseling, peer mentoring, faculty mentoring, academic and career advisement

  7. Projects of the year

    SciTech Connect (OSTI)

    Hansen, T.

    2007-01-15T23:59:59.000Z

    The Peabody Hotel, Orlando, Florida was the site of Power Engineering magazine's 2006 Projects of the Year Awards Banquet, which kicked-off the Power-Gen International conference and exhibition. The Best Coal-fired Project was awarded to Tri-State Generation and Transmission Association Inc., owner of Springenville Unit 3. This is a 400 MW pulverized coal plant in Springeville, AZ, sited with two existing coal-fired units. Designed to fire Powder River Basin coal, it has low NOx burners and selective catalytic reduction for NOx control, dry flue gas desulfurization for SO{sub 2} control and a pulse jet baghouse for particulate control. It has a seven-stage feedwater heater and condensers to ensure maximum performance. Progress Energy-Carolinas' Asheville Power Station FGD and SCR Project was awarded the 2006 coal-fired Project Honorable Mention. This plant in Skyland, NC was required to significantly reduce NOx emissions. When completed, the improvements will reduce NOx by 93% compared to 1996 levels and SO{sub 2} by 93% compared to 2001 levels. Awards for best gas-fired, nuclear, and renewable/sustainable energy projects are recorded. The Sasyadko Coal-Mine Methane Cogeneration Plant near Donezk, Ukraine, was given the 2006 Honorable Mention for Best Renewable/Sustainable Energy Project. In November 2004, Ukraine was among 14 nations to launch the Methane to Markets partnership. The award-winning plant is fuelled by methane released during coal extraction. It generates 42 MW of power. 4 photos.

  8. Proposal to negotiate two contracts, without competitive tendering, for the supply and the repair of compressors for the LHC 18 kW helium refrigeration plants

    E-Print Network [OSTI]

    2011-01-01T23:59:59.000Z

    Proposal to negotiate two contracts, without competitive tendering, for the supply and the repair of compressors for the LHC 18 kW helium refrigeration plants

  9. Sustainable Places Project/Project Connect

    E-Print Network [OSTI]

    Spillar, R.; Arguello, J.

    2013-01-01T23:59:59.000Z

    Needs and Opportunities Project Details System: Corridors and Gaps System Optimization Funding Organization All answered…at the system level ESL-KT-13-12-50 CATEE 2013: Clean Air Through Energy Efficiency Conference, San Antonio, Texas Dec. 16-18 14...1Presented to: Clean Air Trough Energy Efficiency CATEE Conference San Antonio December 18, 2013 ESL-KT-13-12-50 CATEE 2013: Clean Air Through Energy Efficiency Conference, San Antonio, Texas Dec. 16-18 2• Capital Metro jurisdiction, and prior...

  10. PROJECT MANGEMENT PLAN EXAMPLES Project Execution Example

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy ChinaofSchaeferAprilOverviewEfficiencyofHSSPIAProperty Management Plan ExamplesProject

  11. Portsmouth/Paducah Project Office

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Paducah Site Recovery Act project director. Recovery Act Projects East End Smelter - Recovery Act funding accelerated by 22 years the cleanup and demolition of a...

  12. National Ignition Facility project execution plan

    SciTech Connect (OSTI)

    Paisner, J., LLNL

    1997-08-01T23:59:59.000Z

    This project execution plan covers: Justification of Mission Need; Project Description; Management Roles and Responsibilities; Project Execution; Method of Accomplishment.

  13. Renewable Energy & Energy Efficiency Projects: Loan Guarantee...

    Energy Savers [EERE]

    Renewable Energy & Energy Efficiency Projects: Loan Guarantee Solicitation Renewable Energy & Energy Efficiency Projects: Loan Guarantee Solicitation Plenary III: Project Finance...

  14. DNA Repair Biomarkers Predict Response to Neoadjuvant Chemoradiotherapy in Esophageal Cancer

    SciTech Connect (OSTI)

    Alexander, Brian M., E-mail: bmalexander@lroc.harvard.edu [Department of Radiation Oncology, Dana-Farber/Brigham and Women's Cancer Center, Boston, Massachusetts (United States); Wang Xiaozhe [On-Q-ity, Inc., Waltham, Massachusetts (United States); Niemierko, Andrzej [Department of Radiation Oncology, Massachusetts General Hospital, Boston, Massachusetts (United States); Weaver, David T. [On-Q-ity, Inc., Waltham, Massachusetts (United States); Mak, Raymond H. [Department of Radiation Oncology, Dana-Farber/Brigham and Women's Cancer Center, Boston, Massachusetts (United States); Roof, Kevin S. [Southeast Radiation Oncology, Charlotte, North Carolina (United States); Fidias, Panagiotis [Department of Medicine, Massachusetts General Hospital, Boston, Massachusetts (United States); Wain, John [Department of Surgery, Massachusetts General Hospital, Boston, Massachusetts (United States); Choi, Noah C. [Department of Radiation Oncology, Massachusetts General Hospital, Boston, Massachusetts (United States)

    2012-05-01T23:59:59.000Z

    Purpose: The addition of neoadjuvant chemoradiotherapy prior to surgical resection for esophageal cancer has improved clinical outcomes in some trials. Pathologic complete response (pCR) following neoadjuvant therapy is associated with better clinical outcome in these patients, but only 22% to 40% of patients achieve pCR. Because both chemotherapy and radiotherapy act by inducing DNA damage, we analyzed proteins selected from multiple DNA repair pathways, using quantitative immunohistochemistry coupled with a digital pathology platform, as possible biomarkers of treatment response and clinical outcome. Methods and Materials: We identified 79 patients diagnosed with esophageal cancer between October 1994 and September 2002, with biopsy tissue available, who underwent neoadjuvant chemoradiotherapy prior to surgery at the Massachusetts General Hospital and used their archived, formalin-fixed, paraffin-embedded biopsy samples to create tissue microarrays (TMA). TMA sections were stained using antibodies against proteins in various DNA repair pathways including XPF, FANCD2, PAR, MLH1, PARP1, and phosphorylated MAPKAP kinase 2 (pMK2). Stained TMA slides were evaluated using machine-based image analysis, and scoring incorporated both the intensity and the quantity of positive tumor nuclei. Biomarker scores and clinical data were assessed for correlations with clinical outcome. Results: Higher scores for MLH1 (p = 0.018) and lower scores for FANCD2 (p = 0.037) were associated with pathologic response to neoadjuvant chemoradiation on multivariable analysis. Staining of MLH1, PARP1, XPF, and PAR was associated with recurrence-free survival, and staining of PARP1 and FANCD2 was associated with overall survival on multivariable analysis. Conclusions: DNA repair proteins analyzed by immunohistochemistry may be useful as predictive markers for response to neoadjuvant chemoradiotherapy in patients with esophageal cancer. These results are hypothesis generating and need confirmation in an independent data set.

  15. JAG Tearing Technique with Radiofrequency Guide Wire for Aortic Fenestration in Thoracic Endovascular Aneurysm Repair

    SciTech Connect (OSTI)

    Ricci, Carmelo [Azienda Ospedaliera Universitaria Senese, Policlinico Santa Maria alle Scotte, Radiologia Interventistica (Italy); Ceccherini, Claudio, E-mail: claudiocec@hotmail.it; Leonini, Sara [Radiologia Universitaria, Azienda Ospedaliera Universitaria Senese, Policlinico Santa Maria alle Scotte (Italy); Cini, Marco; Vigni, Francesco [Azienda Ospedaliera Universitaria Senese, Policlinico Santa Maria alle Scotte, Radiologia Interventistica (Italy); Neri, Eugenio; Tucci, Enrico; Benvenuti, Antonio; Tommasino, Giulio; Sassi, Carlo [Azienda Ospedaliera Universitaria Senese, Policlinico Santa Maria alle Scotte, Chirurgia dell'Aorta Toracica (Italy)

    2012-02-15T23:59:59.000Z

    An innovative approach, the JAG tearing technique, was performed during thoracic endovascular aneurysm repair in a patient with previous surgical replacement of the ascending aorta with a residual uncomplicated type B aortic dissection who developed an aneurysm of the descending thoracic aorta with its lumen divided in two parts by an intimal flap. The proximal landing zone was suitable to place a thoracic stent graft. The distal landing zone was created by cutting the intimal flap in the distal third of the descending thoracic aorta with a radiofrequency guide wire and intravascular ultrasound catheter.

  16. Exposure Evaluation for Benzene, Lead and Noise in Vehicle and Equipment Repair Shops

    SciTech Connect (OSTI)

    Sweeney, Lynn C.

    2013-04-10T23:59:59.000Z

    An exposure assessment was performed at the equipment and vehicle maintenance repair shops operating at the U. S. Department of Energy Hanford site, in Richland, Washington. The maintenance shops repair and maintain vehicles and equipment used in support of the Hanford cleanup mission. There are three general mechanic shops and one auto body repair shop. The mechanics work on heavy equipment used in construction, cranes, commercial motor vehicles, passenger-type vehicles in addition to air compressors, generators, and farm equipment. Services include part fabrication, installation of equipment, repair and maintenance work in the engine compartment, and tire and brake services. Work performed at the auto body shop includes painting and surface preparation which involves applying body filler and sanding. 8-hour time-weighted-average samples were collected for benzene and noise exposure and task-based samples were collected for lead dust work activities involving painted metal surfaces. Benzene samples were obtained using 3M™ 3520 sampling badges and were analyzed for additional volatile organic compounds. These compounds were selected based on material safety data sheet information for the aerosol products used by the mechanics for each day of sampling. The compounds included acetone, ethyl ether, toluene, xylene, VM&P naphtha, methyl ethyl ketone, and trichloroethylene. Laboratory data for benzene, VM&P naphtha, methyl ethyl ketone and trichloroethylene were all below the reporting detection limit. Airborne concentrations for acetone, ethyl ether, toluene and xylene were all less than 10% of their occupational exposure limit. The task-based samples obtained for lead dusts were submitted for a metal scan analysis to identify other metals that might be present. Laboratory results for lead dusts were all below the reporting detection limit and airborne concentration for the other metals observed in the samples were less than 10% of the occupational exposure limit. Noise dosimetry sampling was performed on a random basis and was representative of the different work activities within the four shops. Twenty three percent of the noise samples exceeded the occupational exposure limit of 85 decibels for an 8-hour time-weightedaverage. Work activities where noise levels were higher included use of impact wrenches and grinding wheels.

  17. Endovascular Stent-Graft Repair as a Late Secondary Procedure After Previous Aortic Grafts

    SciTech Connect (OSTI)

    Matsagas, Miltiadis I. [School of Medicine, University of Ioannina, Department of Surgery - Vascular Surgery Unit (Greece)], E-mail: mimats@cc.uoi.gr; Anagnostopoulos, Constantine E. [School of Medicine, University of Ioannina, Department of Cardiothoracic Surgery (Greece); Papakostas, John C. [School of Medicine, University of Ioannina, Department of Surgery - Vascular Surgery Unit (Greece); DeRose, Joseph J. [St. Luke's-Roosevelt Hospital, Columbia University, Department of Cardiothoracic Surgery (United States); Siminelakis, Stavros [School of Medicine, University of Ioannina, Department of Cardiothoracic Surgery (Greece); Katsouras, Christos S. [School of Medicine, University of Ioannina, Department of Cardiology (Greece); Toumpoulis, Ioannis K.; Drossos, George E. [School of Medicine, University of Ioannina, Department of Cardiothoracic Surgery (Greece); Michalis, Lampros K. [School of Medicine, University of Ioannina, Department of Cardiology (Greece)

    2006-08-15T23:59:59.000Z

    Thoracic and abdominal aortic endovascular procedures as alternatives to aortic reoperations were studied in three different cases. An anastomotic aneurysm after previous thoracic aortic graft for coarctation, a second-stage elephant trunk repair (descending thoracic aortic aneurysm), and a secondary aneurysm proximal to a previous abdominal aortic graft were successfully treated with endovascular stent-grafts. During the follow-up period no lethal events or major aortic or graft-related complications were observed, except a type II endoleak in the anastomotic aortic aneurysm case. An endovascular stent-graft can be safely deployed into a previously implanted vascular graft, avoiding repeat surgery.

  18. 1 October, 2012 PROJECT COMMISSIONING FOR SMALL PROJECTS

    E-Print Network [OSTI]

    Kamat, Vineet R.

    1 October, 2012 PROJECT COMMISSIONING FOR SMALL PROJECTS This procedure defines the process for performing construction-phase commissioning (Cx) on small projects, typically projects consisting of a single system with a few pieces of equipment. When the process is performed by an external commissioning firm

  19. Perspectives on Project Finance | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Perspectives on Project Finance Perspectives on Project Finance Plenary III: Project Finance and Investment Perspectives on Project Finance John May, Managing Partner, Stern...

  20. GEOL 5303 Project Presentations Presenter name: ______________________________________________

    E-Print Network [OSTI]

    Smith-Konter, Bridget

    pertinent materials. 10 7 4 0 Conclusion: What did you learn? Presenter summarizes total project (triumphsGEOL 5303 Project Presentations Presenter name: ______________________________________________ Project title: ___________________________________________________________ Project content Superb

  1. 2020 Vision Project Summary

    SciTech Connect (OSTI)

    Gordon, K.W.; Scott, K.P.

    2000-11-01T23:59:59.000Z

    Since the 2020 Vision project began in 1996, students from participating schools have completed and submitted a variety of scenarios describing potential world and regional conditions in the year 2020 and their possible effect on US national security. This report summarizes the students' views and describes trends observed over the course of the 2020 Vision project's five years. It also highlights the main organizational features of the project. An analysis of thematic trends among the scenarios showed interesting shifts in students' thinking, particularly in their views of computer technology, US relations with China, and globalization. In 1996, most students perceived computer technology as highly beneficial to society, but as the year 2000 approached, this technology was viewed with fear and suspicion, even personified as a malicious, uncontrollable being. Yet, after New Year's passed with little disruption, students generally again perceived computer technology as beneficial. Also in 1996, students tended to see US relations with China as potentially positive, with economic interaction proving favorable to both countries. By 2000, this view had transformed into a perception of China emerging as the US' main rival and ''enemy'' in the global geopolitical realm. Regarding globalization, students in the first two years of the project tended to perceive world events as dependent on US action. However, by the end of the project, they saw the US as having little control over world events and therefore, we Americans would need to cooperate and compromise with other nations in order to maintain our own well-being.

  2. Instrument validation project

    SciTech Connect (OSTI)

    Reynolds, B.A.; Daymo, E.A.; Geeting, J.G.H.; Zhang, J.

    1996-06-01T23:59:59.000Z

    Westinghouse Hanford Company Project W-211 is responsible for providing the system capabilities to remove radioactive waste from ten double-shell tanks used to store radioactive wastes on the Hanford Site in Richland, Washington. The project is also responsible for measuring tank waste slurry properties prior to injection into pipeline systems, including the Replacement of Cross-Site Transfer System. This report summarizes studies of the appropriateness of the instrumentation specified for use in Project W-211. The instruments were evaluated in a test loop with simulated slurries that covered the range of properties specified in the functional design criteria. The results of the study indicate that the compact nature of the baseline Project W-211 loop does not result in reduced instrumental accuracy resulting from poor flow profile development. Of the baseline instrumentation, the Micromotion densimeter, the Moore Industries thermocouple, the Fischer and Porter magnetic flow meter, and the Red Valve Pressure transducer meet the desired instrumental accuracy. An alternate magnetic flow meter (Yokagawa) gave nearly identical results as the baseline fischer and Porter. The Micromotion flow meter did not meet the desired instrument accuracy but could potentially be calibrated so that it would meet the criteria. The Nametre on-line viscometer did not meet the desired instrumental accuracy and is not recommended as a quantitative instrument although it does provide qualitative information. The recommended minimum set of instrumentation necessary to ensure the slurry meets the Project W-058 acceptance criteria is the Micromotion mass flow meter and delta pressure cells.

  3. Radiation Embrittlement Archive Project

    SciTech Connect (OSTI)

    Klasky, Hilda B [ORNL] [ORNL; Bass, Bennett Richard [ORNL] [ORNL; Williams, Paul T [ORNL] [ORNL; Phillips, Rick [ORNL] [ORNL; Erickson, Marjorie A [ORNL] [ORNL; Kirk, Mark T [ORNL] [ORNL; Stevens, Gary L [ORNL] [ORNL

    2013-01-01T23:59:59.000Z

    The Radiation Embrittlement Archive Project (REAP), which is being conducted by the Probabilistic Integrity Safety Assessment (PISA) Program at Oak Ridge National Laboratory under funding from the U.S. Nuclear Regulatory Commission s (NRC) Office of Nuclear Regulatory Research, aims to provide an archival source of information about the effect of neutron radiation on the properties of reactor pressure vessel (RPV) steels. Specifically, this project is an effort to create an Internet-accessible RPV steel embrittlement database. The project s website, https://reap.ornl.gov, provides information in two forms: (1) a document archive with surveillance capsule(s) reports and related technical reports, in PDF format, for the 104 commercial nuclear power plants (NPPs) in the United States, with similar reports from other countries; and (2) a relational database archive with detailed information extracted from the reports. The REAP project focuses on data collected from surveillance capsule programs for light-water moderated, nuclear power reactor vessels operated in the United States, including data on Charpy V-notch energy testing results, tensile properties, composition, exposure temperatures, neutron flux (rate of irradiation damage), and fluence, (Fast Neutron Fluence a cumulative measure of irradiation for E>1 MeV). Additionally, REAP contains data from surveillance programs conducted in other countries. REAP is presently being extended to focus on embrittlement data analysis, as well. This paper summarizes the current status of the REAP database and highlights opportunities to access the data and to participate in the project.

  4. Project Management Plan Chinese Food

    E-Print Network [OSTI]

    Igusa, Kiyoshi

    impact of this project? · Data management: How do we collect, preserve and sort all of the files? Which special equipment, facilities needed or wanted? According to http://project-management-knowledge.com/ weProject Management Plan Chinese Food According to NSF, the basic elements of a project management

  5. Combined Heat and Power Projects

    Broader source: Energy.gov [DOE]

    DOE's CHP Technical Assistance Partnerships (CHP TAPs) have compiled a select number of CHP project profiles.

  6. Project Project Funding Operational & Maintenance Costs Univ. Project Title GSF Brief Description of Project Location Amount Source

    E-Print Network [OSTI]

    Slatton, Clint

    Estimated Annual Amount For Amount Source STATE UNIVERSITY SYSTEM 2012-2013 Fixed Capital Outlay ProjectsProject Project Funding Operational & Maintenance Costs Univ. Project Title GSF Brief Description that will respond to the latest trends in small-group learning, technology resources, and collaboration spaces

  7. 3. PROJECT GOVERNANCE 1. Introduction

    E-Print Network [OSTI]

    3. PROJECT GOVERNANCE 1. Introduction In October 2010, the CEI UPF-Icŕria project, led by Pompeu Fabra University (UPF), was named an International Campus of Excellence (CEI). The project defined a set I. CEI UPF-Icŕria governance model Source: CEI UPF-Icŕria project The specific purpose of each unit

  8. MASTER OF SCIENCE Enterprise Project

    E-Print Network [OSTI]

    Yang, Eui-Hyeok

    the traditional tools, tactics, and PMI certification preparation taught in most project management programs MASTER OF SCIENCE According to PMI, the median salary of a project manager with 10 years of project management experience is $105K. According to the Project Management Institute (PMI), "Between 2006 and 2016

  9. Biofuels: Project summaries

    SciTech Connect (OSTI)

    Not Available

    1994-07-01T23:59:59.000Z

    The US DOE, through the Biofuels Systems Division (BSD) is addressing the issues surrounding US vulnerability to petroleum supply. The BSD goal is to develop technologies that are competitive with fossil fuels, in both cost and environmental performance, by the end of the decade. This document contains summaries of ongoing research sponsored by the DOE BSD. A summary sheet is presented for each project funded or in existence during FY 1993. Each summary sheet contains and account of project funding, objectives, accomplishments and current status, and significant publications.

  10. CONNECTICUT BIOFUELS TECHNOLOGY PROJECT

    SciTech Connect (OSTI)

    BARTONE, ERIK

    2010-09-28T23:59:59.000Z

    DBS Energy Inc. (“DBS”) intends on using the Connecticut Biofuels Technology Project for the purpose of developing a small-scale electric generating systems that are located on a distributed basis and utilize biodiesel as its principle fuel source. This project will include research and analysis on the quality and applied use of biodiesel for use in electricity production, 2) develop dispatch center for testing and analysis of the reliability of dispatching remote generators operating on a blend of biodiesel and traditional fossil fuels, and 3) analysis and engineering research on fuel storage options for biodiesel of fuels for electric generation.

  11. Solar Dish Project

    SciTech Connect (OSTI)

    Robert F. Boehm

    2004-06-06T23:59:59.000Z

    (Original wording, now somewhat outdated.) The Nevada Solar Dish Project is designed to deploy at least 1 MW of dish-based, field validation power generation systems in a mini-power plant near Las Vegas, Nevada, as a transitional precursor to the full commercialization of the technology. This will occur over a period of about three years, from 2001 through 2004. The statement of work defines activities that the University of Nevada Las Vegas (UNLV) will provide by establishing a test site for two dish/Stirling systems on the UNLV campus and providing operation, test and training, and education in support of the project.

  12. Integrated Project Team RM

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative Fuels Data Center Home Page on Google Bookmark EERE: Alternative Fuels DataDepartment of Energy Your Density Isn't YourTransport(FactDepartment of EnergyIndustry Research ProjectIntegrated Project Team (IPT)

  13. Dofasco`s No. 4 blast furnace hearth breakout, repair and rescue

    SciTech Connect (OSTI)

    Donaldson, R.J.; Fischer, A.J.; Sharp, R.M.; Stothart, D.W. [Dofasco Inc., Hamilton, Ontario (Canada)

    1995-12-01T23:59:59.000Z

    On May 5, 1994, after producing 9.5 million metric tons of iron, Dofasco`s No. 4 Blast Furnace experienced a hearth breakout 250 millimeters below the west taphole. The hot metal spill caused a fire resulting in severe damage and 33 days of lost production. During a 26-day period, electrical wiring, water drainage systems and both tapholes were repaired. Recovery from an unprepared furnace stop of this length, with the deadman depleted is difficult. To aid with the rescue Hoogovens-designed oxygen/fuel lances were commissioned. The furnace recovery began with a lance in each taphole and all tuyeres plugged. Six days after startup the furnace was casting into torpedo cars, and after nine days operation had returned to normal. This incident prompted Dofasco to expand the hearth monitoring system to detect and prevent similar occurrences. During the repair, 203 new thermocouples were installed in the hearth, concentrating on the tapholes and elephant foot areas. These thermocouples were installed at various depths and locations to allow heat flux calculations. This hearth monitoring system has already identified other problem areas and provided valuable information about hearth drainage patterns. This information has allowed them to develop control strategies to manage localized problem areas.

  14. Percutaneous Stent-Graft Repair of a Mycotic Pulmonary Artery Pseudoaneurysm

    SciTech Connect (OSTI)

    Chou Meichun; Liang Hueilung, E-mail: hlliang@isca.vghks.gov.tw; Pan Huayban; Yang Chienfang [Kaohsiung Veterans General Hospital, Department of Radiology (China)

    2006-10-15T23:59:59.000Z

    Ruptured mycotic pulmonary pseudoaneurysm is a lethal complication. Emergent surgical repair is usually recommended, but still associated with a high mortality rate. We present a patient in whom mycotic pulmonary pseudoaneurysm was a complication after surgical lobectomy 2 weeks earlier. This patient had suffered from repeated massive hemoptysis. After emergent surgical repair of the ruptured pulmonary artery stump, another episode of massive hemorrhage occurred. The pulmonary arteriogram revealed a segmental stenosis and a large, wide-necked, lobulated pseudoaneurysm at the left proximal pulmonary artery. We deployed a balloon-expandable stent-graft (48 mm in length mounted on a 12 mm x 40 mm angioplasty balloon) across the stenotic segment and the neck of the pulmonary pseudoaneurysm. Hemostasis was achieved immediately and, under a 4-week antibiotic treatment, patient was transferred to a local hospital for medical care. This case report demonstrates the benefit of minimally invasive endovascular therapy in a critically ill patient. A literature review of the etiology and management of mycotic pulmonary pseudoaneurysm is included.

  15. Operational results of shaft repair by installing stave type cooler at Kimitsu Nos. 3 and 4 blast furnaces

    SciTech Connect (OSTI)

    Oda, Hiroshi; Amano, Shigeru; Sakamoto, Aiichiro; Anzai, Osamu [Nippon Steel Corp., Kimitsu, Chiba (Japan). Kimitsu Works; Nakagome, Michiru; Kuze, Toshisuke [Nippon Steel Corp., Futtsu, Chiba (Japan); Imuta, Akira [Nippon Steel Corp., Tokyo (Japan). Plant and Machinery Div.

    1997-12-31T23:59:59.000Z

    Nos. 3 and 4 blast furnaces in Nippon Steel Corporation Kimitsu Works were both initially fitted with cooling plate systems. With the aging of each furnace, the damage to their respective inner-shaft profiles had become serious. Thus, in order to prevent operational change and prolong the furnace life, the inner-shaft profile of each furnace was repaired by replacing the former cooling plate system with the stave type cooler during the two-week-shutdowns. With this repair, stability of burden descent and gas flow near the wall part of the furnace have been achieved. Thus the prolongation of the furnace life is naturally expected.

  16. Inhibition of X-ray-induced potentially lethal damage (PLD) repair in aerobic plateau-phase Chinese hamster cells by misonidazole

    SciTech Connect (OSTI)

    Brown, D.M.

    1984-01-01T23:59:59.000Z

    The effect of the 2-nitroimidazole radiosensitizer misonidazole (MISO) and the hydrophilic analog SR-2508 on the repair of X-ray-induced potentially lethal damage (PLD) was studied in plateau-phase Chinese Hamster ovary (HA-1) cells. It was found that although MISO does not radiosensitize aerobic cells, it inhibits the repair of PLD. However, under hypoxic conditions, MISO has no effect on PLD repair. The major portion of the inhibition of PLD repair in aerobic cells requires the presence of MISO only during irradiation; little or no additional inhibition occurs when MISO is present during the postirradiation repair period. Also, treatment of aerobic cells with 5 mM MISO for either 5 or 30 min prior to irradiation is equally inhibitory. This suggests that the presence of MISO in some way modifies the initial lesion under aerobic conditions since it does not increase cell killing as determined by immediate plating but inhibits subsequent repair. The inhibition is concentration dependent; 0.5 mM MISO inhibits PLD repair by one-half while 5-10 mM totally inhibits the repair measured 6 hr postirradiation. This phenomenon suggests that radiosensitization of tissue in vivo by MISO and other 2-nitroimidazoles may not be unequivocal proof of the presence of hypoxic cells.

  17. Subj: Educational and General (E&G) Facility Support Provide an overview of Facility Operations, Maintenance, Repair and Renovation and Space

    E-Print Network [OSTI]

    support, and, preventive and unscheduled maintenance of all building systems, with the exception of BAS Operations, Maintenance, Repair and Renovation and Space Management Procedures and Practices. KEY DEFINITIONS chambers, fume hoods, fixed seating, etc. are normally considered part of the building. Maintenance, repair

  18. Performance and Impact from Duct Repair and Ventilation Modifications of Two Newly Constructed Manufactured Houses Located in a Hot and Humid Climate

    E-Print Network [OSTI]

    Withers, C.; Moyer, N.; Chasar, D.; Chandra, S.

    2002-01-01T23:59:59.000Z

    airtightness was adjusted until it was the same in each house, and duct leaks were sealed so that the ducts were tight and there was equal tightness in both houses. A ventilation system was also added at the same time of duct repair. Duct repair...

  19. New Project Opportunities

    E-Print Network [OSTI]

    Michelson, David G.

    and heavy mineral concentrates. Basic and advanced mineral characterization of various PIMS minerals has, the next phase of this project has started and MDRU are looking for industry partners. Exploring Lithocaps with industry partners for 2014 and beyond. We are looking for Expressions of Interest from potential partners

  20. ISOE Pilot Project Update

    SciTech Connect (OSTI)

    D. A. Hagemeyer D. E. Lewis

    2012-05-05T23:59:59.000Z

    This slide show introduces the Pilot Project to increase the value of Information System on Occupational Exposure (ISOE)#11;data by increasing participation and amount of data reported from the U.S., reduce the hurdles and effort in participating, streamline the process of reporting and reduce time delay, and eliminate data entry and redundant effort.

  1. Information Technology Project Guide

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-09-12T23:59:59.000Z

    This Guide provides Department of Energy recommended guidelines to ensure that the acquisition of information technology capital assets is performed in compliance with DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, dated 7-28-06. Canceled by DOE N 251.105.

  2. Project Summary Partnership Inspiration

    E-Print Network [OSTI]

    Everest, Graham R

    %. This earned Adnams the CRed Business Standard (a systematic framework for reducing carbon based energy costs Businesses are hunting for solutions to reduce their carbon footprint and energy spend. This project follows as 6 tonnes of CO2 per employee. The Carbon Trust estimates that UK businesses waste 30% energy through

  3. MINERAL FACILITIES MAPPING PROJECT

    E-Print Network [OSTI]

    Gilbes, Fernando

    MINERAL FACILITIES MAPPING PROJECT Yadira Soto-Viruet Supervisor: David Menzie, Yolanda Fong-Sam Minerals Information Team (MIT) USGS Summer Internship 2009 U.S. Department of the Interior U.S. Geological Minerals Information Team (MIT): Annually reports on the minerals facilities of more than 180 countries

  4. Baytown Cogeneration Project

    E-Print Network [OSTI]

    Lorenz, M. G.

    2007-01-01T23:59:59.000Z

    The Baytown Cogeneration Project installed a GE 7FA gas turbine generator that produces 160 MW of electricity and 560-klB/hr of superheated 1500-psig steam. All of the steam and electricity are consumed by the ExxonMobil Refinery & Chemical Plant...

  5. Environmental of Forestry Projects

    E-Print Network [OSTI]

    Environmental Impact Assessment of Forestry Projects #12;EnvironmentalImpactAssessment 2 Flow chart Details of the Environmental Statement publicised for comment FC considers ES and any comments received FC the issues of concern that need to be covered in the Environmental Statement (ES). The Environmental

  6. Scientific Motivation Project Overview

    E-Print Network [OSTI]

    van Dyk, David

    and Tracking of Solar Features David Stenning1 Vinay Kashyap2 Thomas Lee3 David van Dyk4 C. Alex Young5 1 Flight Center Stenning, David Automatic Classifying and Tracking of Solar Features #12;Scientific Classifying and Tracking of Solar Features #12;Scientific Motivation Project Overview Methodology Results

  7. COFIN project Concentration Fluctuations

    E-Print Network [OSTI]

    COFIN project Concentration Fluctuations in Gas Releases by Industrial Accidents Final Summary of random concentration fluctuations in hazardous gas releases and the method was to derive empirical. In each measurement cycle the Lidar emits a short laser light pulse and detects the light Lidar reflected

  8. Baytown Cogeneration Project 

    E-Print Network [OSTI]

    Lorenz, M. G.

    2007-01-01T23:59:59.000Z

    The Baytown Cogeneration Project installed a GE 7FA gas turbine generator that produces 160 MW of electricity and 560-klB/hr of superheated 1500-psig steam. All of the steam and electricity are consumed by the ExxonMobil Refinery & Chemical Plant...

  9. Final Year Project Report

    SciTech Connect (OSTI)

    Hubsch, Tristan [Howard University

    2013-06-20T23:59:59.000Z

    In the last years of this eighteen-year grant project, the research efforts have focused mostly on the study of off-shell representations of supersymmetry, both on the worldline and on the world- sheet, i.e., both in supersymmetric quantum mechanics and in supersymmetric field theory in 1+1-dimensional spacetime.

  10. Pioneering Heat Pump Project

    Broader source: Energy.gov [DOE]

    Project objectives: To install and monitor an innovative WaterFurnace geothermal system that is technologically advanced and evolving; To generate hot water heating from a heat pump that uses non-ozone depleting refrigerant CO2. To demonstrate the energy efficiency of this system ground source heat pump system.

  11. Overview of composite projects at the FAA Airworthiness Assurance Validation Center

    SciTech Connect (OSTI)

    Shurtleff, W.W.; Roach, D.P.; Valley, M.T.

    1997-03-01T23:59:59.000Z

    The Airworthiness Assurance NDI Validation Center (AANC) was established by the Federal Aviation Administration (FAA) William J. Hughes Technical Center at Sandia National Laboratories in 1991 to support nondestructive inspection (NDI) technology development and assessment. The evaluations are done using a variety of characterized test specimens and test beds including entire transport and commuter aircraft. Although the initial work at the Center concentrated on metallic structure, the FAA has more recently expanded the AANC`s charter to include projects directed at composite repair and inspection. The three projects briefly described in this paper are: (1) the validation and technology transfer of a thermographic techniques for composite inspection, (2) the development of generic composite laminate and honeycomb calibration reference standards, and (3) the certification of the use of boron epoxy doubler on a Lockheed L-1011.

  12. Project Title: Residential wind turbine design Project Description: This project aims to

    E-Print Network [OSTI]

    Muradoglu, Metin

    that wind is expected to come. Therefore it may be a good idea to consider a vertical-axis wind turbine of the conventional wind turbines use horizontal- axis configuration (see Fig. 1) and is aligned with the directionPROJECT 1: Project Title: Residential wind turbine design Project Description: This project aims

  13. Ceramic Technology Project

    SciTech Connect (OSTI)

    Not Available

    1992-03-01T23:59:59.000Z

    The Ceramic Technology Project was developed by the USDOE Office of Transportation Systems (OTS) in Conservation and Renewable Energy. This project, part of the OTS's Materials Development Program, was developed to meet the ceramic technology requirements of the OTS's automotive technology programs. Significant accomplishments in fabricating ceramic components for the USDOE and NASA advanced heat engine programs have provided evidence that the operation of ceramic parts in high-temperature engine environments is feasible. These programs have also demonstrated that additional research is needed in materials and processing development, design methodology, and data base and life prediction before industry will have a sufficient technology base from which to produce reliable cost-effective ceramic engine components commercially. A five-year project plan was developed with extensive input from private industry. In July 1990 the original plan was updated through the estimated completion of development in 1993. The objective is to develop the industrial technology base required for reliable ceramics for application in advanced automotive heat engines. The project approach includes determining the mechanisms controlling reliability, improving processes for fabricating existing ceramics, developing new materials with increased reliability, and testing these materials in simulated engine environments to confirm reliability. Although this is a generic materials project, the focus is on the structural ceramics for advanced gas turbine and diesel engines, ceramic bearings and attachments, and ceramic coatings for thermal barrier and wear applications in these engines. To facilitate the rapid transfer of this technology to US industry, the major portion of the work is being done in the ceramic industry, with technological support from government laboratories, other industrial laboratories, and universities.

  14. Paul Glowaski: Garden Director, Homeless Garden Project

    E-Print Network [OSTI]

    Reti, Irene H.

    2010-01-01T23:59:59.000Z

    Regional History Project, University Library, 2003) http://History Project, University Library, UCSC, 1996. ) http://

  15. California Hydrogen Infrastructure Project

    SciTech Connect (OSTI)

    Edward C. Heydorn

    2013-03-12T23:59:59.000Z

    Air Products and Chemicals, Inc. has completed a comprehensive, multiyear project to demonstrate a hydrogen infrastructure in California. The specific primary objective of the project was to demonstrate a model of a ���¢��������real-world���¢������� retail hydrogen infrastructure and acquire sufficient data within the project to assess the feasibility of achieving the nation���¢��������s hydrogen infrastructure goals. The project helped to advance hydrogen station technology, including the vehicle-to-station fueling interface, through consumer experiences and feedback. By encompassing a variety of fuel cell vehicles, customer profiles and fueling experiences, this project was able to obtain a complete portrait of real market needs. The project also opened its stations to other qualified vehicle providers at the appropriate time to promote widespread use and gain even broader public understanding of a hydrogen infrastructure. The project engaged major energy companies to provide a fueling experience similar to traditional gasoline station sites to foster public acceptance of hydrogen. Work over the course of the project was focused in multiple areas. With respect to the equipment needed, technical design specifications (including both safety and operational considerations) were written, reviewed, and finalized. After finalizing individual equipment designs, complete station designs were started including process flow diagrams and systems safety reviews. Material quotes were obtained, and in some cases, depending on the project status and the lead time, equipment was placed on order and fabrication began. Consideration was given for expected vehicle usage and station capacity, standard features needed, and the ability to upgrade the station at a later date. In parallel with work on the equipment, discussions were started with various vehicle manufacturers to identify vehicle demand (short- and long-term needs). Discussions included identifying potential areas most suited for hydrogen fueling stations with a focus on safe, convenient, fast-fills. These potential areas were then compared to and overlaid with suitable sites from various energy companies and other potential station operators. Work continues to match vehicle needs with suitable fueling station locations. Once a specific site was identified, the necessary agreements could be completed with the station operator and expected station users. Detailed work could then begin on the site drawings, permits, safety procedures and training needs. Permanent stations were successfully installed in Irvine (delivered liquid hydrogen), Torrance (delivered pipeline hydrogen) and Fountain Valley (renewable hydrogen from anaerobic digester gas). Mobile fueling stations were also deployed to meet short-term fueling needs in Long Beach and Placerville. Once these stations were brought online, infrastructure data was collected and reported to DOE using Air Products���¢�������� Enterprise Remote Access Monitoring system. Feedback from station operators was incorporated to improve the station user���¢��������s fueling experience.

  16. Evaluation of Technology Risk in Project Cogeneration Project Returns

    E-Print Network [OSTI]

    Thoennes, C. M.

    The economic returns of a cogeneration project are a direct function of the project margin, that is, the difference between revenues and expenses. Revenues and expenses, of course, are made up of both variable and fixed components. The revenues...

  17. NEPA COMPLIANCE SURVEY Project Information Project Title: Liner...

    Broader source: Energy.gov (indexed) [DOE]

    Liner Drilling Date: 4-5-10 DOE Code: 71092 Cont ractor Code: 8067-766 Project Lead: Frank Ingham Project Overview Nothing out of the ordinary for drilling an existing location 1....

  18. PROJECT SELF-EVALUATION METHODOLOGY: THE HEALTHREATS PROJECT CASE STUDY

    E-Print Network [OSTI]

    Bohanec, Marko

    PROJECT SELF-EVALUATION METHODOLOGY: THE HEALTHREATS PROJECT CASE STUDY Martin Znidarsic1 , Marko, Slovenia e-mail: martin.znidarsic@ijs.si Tel: +386 1 477 3366; fax: +386 1 477 3315 ABSTRACT The paper

  19. NEPA COMPLIANCE SURVEY Project Information Project Title: T-2...

    Broader source: Energy.gov (indexed) [DOE]

    T-2-33 Date: 12-22-2010 DOE Code: Contractor Code: Project Lead: Bernard Winfree Project Overview 1. What are the environmental The existing manifold building will be moved off...

  20. The Multimedia Project Quarked!

    E-Print Network [OSTI]

    Bean, Alice

    2011-01-01T23:59:59.000Z

    Can exposure to fundamental ideas about the nature of matter help motivate children in math and science and support the development of their understanding of these ideas later? Physicists, designers, and museum educators at the University of Kansas created the Quarked!(tm) Adventures in the subatomic Universe project to provide an opportunity for youth to explore the subatomic world in a fun and user friendly way. The project components include a website (located at http://www.quarked.org) and hands-on education programs. These are described and assessment results are presented. Questions addressed include the following. Can you engage elementary and middle school aged children with concepts related to particle physics? Can young children make sense of something they can't directly see? Do teachers think the material is relevant to their students?

  1. Healy Clean Coal Project

    SciTech Connect (OSTI)

    None

    1997-12-31T23:59:59.000Z

    The Healy Clean Coal Project, selected by the U.S. Department of Energy under Round 111 of the Clean Coal Technology Program, has been constructed and is currently in the Phase 111 Demonstration Testing. The project is owned and financed by the Alaska Industrial Development and Export Authority (AIDEA), and is cofunded by the U.S. Department of Energy. Construction was 100% completed in mid-November of 1997, with coal firing trials starting in early 1998. Demonstration testing and reporting of the results will take place in 1998, followed by commercial operation of the facility. The emission levels of nitrogen oxides (NOx), sulfur dioxide (S02), and particulate from this 50-megawatt plant are expected to be significantly lower than current standards.

  2. Debt collection project report

    SciTech Connect (OSTI)

    Not Available

    1980-05-01T23:59:59.000Z

    In October 1979 the Office of Management and Budget initiated a review of debt collection within the Federal Government. A DOE Debt Collection Project Team was established, and seven activites were selected for review. These were Albuquerque Operations Office; Bonneville Power Administration; Chicago Operations and Regional Office; Naval Petroleum Reserves, California; Oak Ridge Operations Office; Washington Financial Services Division; and Western Area Power Administration. The team visited each of these activities to collect data on the size, age, and types of receivables managed and procedures for billing, aging, and handling overdue accounts. Various deficiencies were found to exist at several of the DOE entities that are not consistent with good management practices in the performance of their debt collection functions. Also, the Debt Collection Project Team identified a wide variation in the procedures followed by DOE activities in the management of accounts receivable, and a wide variation in the effectiveness of the debt management functions. 1 figure, 17 tables. (RWR)

  3. Nucla CFB Demonstration Project

    SciTech Connect (OSTI)

    Not Available

    1990-12-01T23:59:59.000Z

    This report documents Colorado-Ute Electric Association's Nucla Circulating Atmospheric Fluidized-Bed Combustion (AFBC) demonstration project. It describes the plant equipment and system design for the first US utility-size circulating AFBC boiler and its support systems. Included are equipment and system descriptions, design/background information and appendices with an equipment list and selected information plus process flow and instrumentation drawings. The purpose of this report is to share the information gathered during the Nucla circulating AFBC demonstration project and present it so that the general public can evaluate the technical feasibility and cost effectiveness of replacing pulverized or stoker-fired boiler units with circulating fluidized-bed boiler units. (VC)

  4. Moisture Metrics Project

    SciTech Connect (OSTI)

    Schuchmann, Mark

    2011-08-31T23:59:59.000Z

    the goal of this project was to determine the optimum moisture levels for biomass processing for pellets commercially, by correlating data taken from numerous points in the process, and across several different feedstock materials produced and harvested using a variety of different management practices. This was to be done by correlating energy consumption and material through put rates with the moisture content of incoming biomass ( corn & wheat stubble, native grasses, weeds, & grass straws), and the quality of the final pellet product.This project disseminated the data through a public website, and answering questions form universities across Missouri that are engaged in biomass conversion technologies. Student interns from a local university were employed to help collect data, which enabled them to learn firsthand about biomass processing.

  5. Saudi MTBE project revived

    SciTech Connect (OSTI)

    NONE

    1996-01-17T23:59:59.000Z

    Alujain Corp., a member of the Xenel group of Saudi Arabia, is going ahead with plans to build an 800,000-m.t./year methyl tert-butyl ether (MTBE) plant. Bechtel has been appointed project manager for the plant, which will be owned by a new company, National Fuel Additives (Tahseen). Bechtel will help evaluate proposals already submitted for the lump sum turnkey job.

  6. Cogeneration Project Analysis Update

    E-Print Network [OSTI]

    Robinson, A. M.; Garcia, L. N.

    diverse factors, such as, but no limited to: Fuel Considerations, Heat System Analysis, Electric Power Considerations, Key Technical Project Considerations, and Economic Analysis. INTRODUCTION The cogeneration systems being developed for industrial... power marched upward at a higher rate than fuel, capital equipment cost, and the prime interest rate. Typical Cogeneration System One system has been chosen as typical. This is one of the cogeneration systems which have proliferated over the past...

  7. Awarded ESPC Projects

    Broader source: Energy.gov [DOE]

    Since the inception of the U.S. Department of Energy's (DOE) energy savings performance contracts (ESPCs) in 1998, 325 DOE ESPC projects have been awarded. More than $3.41 billion has been invested in Federal energy efficiency and renewable energy improvements. These improvements have resulted in more than 398 trillion Btu life cycle energy savings and more than $8.53 billion of cumulative energy cost savings for the Federal Government.

  8. Advanced thyristor valve project

    SciTech Connect (OSTI)

    Damsky, B.L.

    1984-01-01T23:59:59.000Z

    General Electrics's thyristor valve project incorporates the most advanced technologies available. With joint funding from the Electric Power Research Institute, commercial application of the separate light-triggered thyristor is now underway. The cesium vapor lamp source to trigger the light sensitive thyristors will reduce component complexity and cost. A unique thermal management feature relies on forced vaporization cooling with Freon-113, which equals the thermal performance of water without posing insulation reliability problems. 7 figures.

  9. Robotics research projects report

    SciTech Connect (OSTI)

    Hsia, T.C. (ed.)

    1983-06-01T23:59:59.000Z

    The research results of the Robotics Research Laboratory are summarized. Areas of research include robotic control, a stand-alone vision system for industrial robots, and sensors other than vision that would be useful for image ranging, including ultrasonic and infra-red devices. One particular project involves RHINO, a 6-axis robotic arm that can be manipulated by serial transmission of ASCII command strings to its interfaced controller. (LEW)

  10. Sandia National Laboratories: Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's PossibleRadiationImplementingnpitche Home AboutMeeting: ProgramFebruaryJunePowerProjects Threat

  11. Original Full Length Article Inkjet-based biopatterning of SDF-1 augments BMP-2-induced repair of

    E-Print Network [OSTI]

    Weiss, Lee E.

    Original Full Length Article Inkjet-based biopatterning of SDF-1 augments BMP-2-induced repair Biopatterning BMP-2 SDF-1 TGF-1 Background: A major problem in craniofacial surgery is non-healing bone defects-derived factor-1 (SDF-1), transforming growth factor-1 (TGF-1), or co-therapies thereof. We tested the hypothesis

  12. The Effect of Debris on Collector Optics, its Mitigation and Repair: Next-Step a Gaseous Sn EUV DPP Source

    E-Print Network [OSTI]

    Spila, Timothy P.

    The Effect of Debris on Collector Optics, its Mitigation and Repair: Next-Step a Gaseous Sn EUV DPP to advanced fuel plasma EUV sources is collector lifetime. The Illinois Debris-mitigation EUV Applications based on this work. Keywords: EUV source, debris, optics, collector lifetime, mitigation, plasma

  13. Image-Guided Techniques Improve the Short-term Outcome of Autologous Osteochondral Cartilage Repair Surgeries -An

    E-Print Network [OSTI]

    Stewart, James

    Image-Guided Techniques Improve the Short-term Outcome of Autologous Osteochondral Cartilage Repair and deliver osteochondral grafts remains problematic. We investigated whether image-guided methods (optically-guided and template-guided) can improve the outcome of mo- saic arthroplasty procedures. Methods: Fifteen sheep were

  14. Surgical technique, using skin, for repair of simultaneously ruptured anterior cruciate and medial collateral ligaments of the canine femorotibial articulation

    E-Print Network [OSTI]

    Chastain, Jamie Neal

    1959-01-01T23:59:59.000Z

    Agricultural and Mechanical College of Texan In Partial Fulfillnent of the !Iequireaents for the Degree Meeter of Science in Veterinary Medicine and Surgery by Janie Neal Chaetain January 1&359 SURGICAL TECHNI((UE ~ USIN'G SKIN ~ FOR REPAIR...

  15. Diet-dependent survival of protein repair-deficient miceB Christine E. Farrar, Steven ClarkeT

    E-Print Network [OSTI]

    Clarke, Steven

    Diet-dependent survival of protein repair-deficient miceB Christine E. Farrar, Steven Clarke, and mice lacking this enzyme accumulate damaged proteins in multiple tissues, die at an early age from and in vivo [1­7]. Mice lacking the enzyme (Pcmt1Ŕ/Ŕ mice) accu- mulate damaged proteins in multiple tissues

  16. Homologous recombination contributes to the repair of DNA double-strand breaks induced by high-energy iron ions

    SciTech Connect (OSTI)

    Zafar, Faria; Seidler, Sara B.; Kronenberg, Amy; Schild, David; Wiese, Claudia

    2010-06-29T23:59:59.000Z

    To test the contribution of homologous recombinational repair (HRR) in repairing DNA damaged sites induced by high-energy iron ions, we used: (1) HRR-deficient rodent cells carrying a deletion in the RAD51D gene and (2) syngeneic human cells impaired for HRR by RAD51D or RAD51 knockdown using RNA interference. We show that in response to iron ions, HRR contributes to cell survival in rodent cells, and that HRR-deficiency abrogates RAD51 foci formation. Complementation of the HRR defect by human RAD51D rescues both enhanced cytotoxicity and RAD51 foci formation. For human cells irradiated with iron ions, cell survival is decreased, and, in p53 mutant cells, the levels of mutagenesis are increased when HRR is impaired. Human cells synchronized in S phase exhibit more pronounced resistance to iron ions as compared with cells in G1 phase, and this increase in radioresistance is diminished by RAD51 knockdown. These results implicate a role for RAD51-mediated DNA repair (i.e. HRR) in removing a fraction of clustered lesions induced by charged particle irradiation. Our results are the first to directly show the requirement for an intact HRR pathway in human cells in ensuring DNA repair and cell survival in response to high-energy high LET radiation.

  17. A review of "To Repair the Ruins: Reading Milton" edited by Mary C. Fenton and Louis Schwartz

    E-Print Network [OSTI]

    Welch, Anthony

    2013-01-01T23:59:59.000Z

    that deserve the attention he gives them. Mary C. Fenton and Louis Schwartz, eds. To Repair the Ruins: Reading Milton. Pittsburgh: Duquesne University Press, #18;#17;#16;#18;. xii + #1;#30; pp. + #18;#18; illus. $#14;#15;.#17;#17;. Review by #8...

  18. Economic Development Impacts of Community Wind Projects: A Review and Empirical Evaluation; Preprint

    SciTech Connect (OSTI)

    Lantz, E.; Tegen, S.

    2009-04-01T23:59:59.000Z

    'Community wind' refers to a class of wind energy ownership structures. The extent of local ownership may range from a small minority share to full ownership by persons in the immediate area surrounding the wind project site. Potential project owners include local farmers, businesses, Native American tribes, universities, cooperatives, or any other local entity seeking to invest in wind energy. The opposite of community wind is an 'absentee' project, in which ownership is completely removed from the state and community surrounding the facility. Thus, there is little or no ongoing direct financial benefit to state and local populations aside from salaries for local repair technicians, local property tax payments, and land lease payments. In recent years, the community wind sector has been inhibited by manufacturers' preference for larger turbine orders. This often puts smaller community wind developers and projects at a competitive disadvantage. However, state policies specifically supporting community wind may become a more influential market factor as turbines are now more readily available given manufacturer ramp-ups and the slow-down in the industry that has accompanied the recent economic and financial crises. This report examines existing literature to provide an overview of economic impacts resulting from community wind projects, compares results, and explains variability.

  19. Milliwatt Generator Project

    SciTech Connect (OSTI)

    Latimer, T.W.; Rinehart, G.H.

    1992-05-01T23:59:59.000Z

    This report covers progress on the Milliwatt Generator Project from April 1986 through March 1988. Activities included fuel processing and characterization, production of heat sources, fabrication of pressure-burst test units, compatibility studies, impact testing, and examination of surveillance units. The major task of the Los Alamos Milliwatt Generator Project is to fabricate MC2893A heat sources (4.0 W) for MC2730A radioisotope thermoelectric generators (RTGS) and MC3599 heat sources (4.5 W) for MC3500 RTGs. The MWG Project interfaces with the following contractors: Sandia National Laboratories, Albuquerque (designer); E.I. du Pont de Nemours and Co. (Inc.), Savannah River Plant (fuel); Monsanto Research Corporation, Mound Facility (metal hardware); and General Electric Company, Neutron Devices Department (RTGs). In addition to MWG fabrication activities, Los Alamos is involved in (1) fabrication of pressure-burst test units, (2) compatibility testing and evaluation, (3) examination of surveillance units, and (4) impact testing and subsequent examination of compatibility and surveillance units.

  20. Surfactant EOR project evaluated

    SciTech Connect (OSTI)

    Holm, L.W.

    1984-07-16T23:59:59.000Z

    The Union Oil Co.'s Uniflood process has successfully mobilized and produced tertiary oil from a micellar-polymer pilot project on the Hegberg lease in the El Dorado field, Kansas. This half-completed EOR flood has recovered over 11% of the waterflood residual oil and is currently producing at an oil cut of 10%. Oil recovery has been limited by (1) the presence of gypsum in portions of the reservoir which adversly affects injected chemicals, (2) poor quality reservoir rock in one quadrant of the pilot, and (3) a substantial fluid drift (30 ft/year) which causes a portion of the injected chemicals to flow out of the pilot pattern. The El Dorado demonstration project is a joint experiment covered by a cost-sharing contract between the U.S. Department of Energy and Cities Service Company. It was proposed as a micellar-polymer process in a highly saline (10 wt % salts) reservoir that had been waterflooded to residual oil. Despite the extended project life, and indications that total recovery efficiency will be less than originally predicted, oil response in the Hegberg pattern is encouraging for application of the micellar-polymer process in high brine reservoirs.

  1. Final Project Report

    SciTech Connect (OSTI)

    Bogucz, E A

    2010-12-13T23:59:59.000Z

    This project pursued innovations to improve energy efficiency and indoor environmental quality (IEQ) in commercial and residential buildings. For commercial buildings, the project developed a testbed for “intelligent nested environmental systems technologies (iNEST),” which monitor and control energy flows and IEQ across a cascade of spaces from individuals’ desktops to office suites to floors to whole buildings. An iNEST testbed was constructed at Syracuse University and was used to assess the use of devices such as personal badges and CO2 sensors to study how reduced energy use and improved IEQ could be achieved. For residential buildings, resources were targeted in support of DoE’s Builders Challenge Program and to recruit Syracuse, NY builders. Three homes in Syracuse’s Near Westside neighborhood were also registered under the program by Syracuse University team, with an additional home registered by one of the builders. Findings from the work at the iNEST testbed facility, and results from other related projects were disseminated through Syracuse Center of Excellence in Environmental and Energy Systems (SyracuseCoE) 2008 Annual Symposium, the 9th International Healthy Buildings 2009 Conference & Exhibition, and through SyracuseCoE’s website and eNewsletters to inform the broader community of researchers, designers and builders. These public communication activities helped enhance the understanding of high performance buildings and facilitate further market acceptance.

  2. NREL Smart Grid Projects

    SciTech Connect (OSTI)

    Hambrick, J.

    2012-01-01T23:59:59.000Z

    Although implementing Smart Grid projects at the distribution level provides many advantages and opportunities for advanced operation and control, a number of significant challenges must be overcome to maintain the high level of safety and reliability that the modern grid must provide. For example, while distributed generation (DG) promises to provide opportunities to increase reliability and efficiency and may provide grid support services such as volt/var control, the presence of DG can impact distribution operation and protection schemes. Additionally, the intermittent nature of many DG energy sources such as photovoltaics (PV) can present a number of challenges to voltage regulation, etc. This presentation provides an overview a number of Smart Grid projects being performed by the National Renewable Energy Laboratory (NREL) along with utility, industry, and academic partners. These projects include modeling and analysis of high penetration PV scenarios (with and without energy storage), development and testing of interconnection and microgrid equipment, as well as the development and implementation of advanced instrumentation and data acquisition used to analyze the impacts of intermittent renewable resources. Additionally, standards development associated with DG interconnection and analysis as well as Smart Grid interoperability will be discussed.

  3. Project Management Plan

    SciTech Connect (OSTI)

    Not Available

    1988-01-01T23:59:59.000Z

    The mission of the Uranium Mill Tailings Remedial Action (UMTRA) Project is explicitly stated and directed in the Uranium Mill Tailings Radiation Control Act of 1978, Public Law 95-604, 42 USC 7901 (hereinafter referred to as the Act''). Title I of the Act authorizes the Department of Energy (DOE) to undertake remedial actions at 24 designated inactive uranium processing sites and associated vicinity properties containing uranium mill tailings and other residual radioactive materials derived from the processing sites. The Act, amended in January 1983, by Public Law 97-415, also authorizes DOE to perform remedial actions at vicinity properties in Edgemont, South Dakota. Cleanup of the Edgemont processing site is the responsibility of the Tennessee Valley Authority. This document describes the plan, organization, system, and methodologies used to manage the design, construction, and other activities required to clean up the designated sites and associated vicinity properties in accordance with the Act. The plan describes the objectives of the UMTRA Project, defines participants' roles and responsibilities, outlines the technical approach for accomplishing the objectives, and describes the planning and managerial controls to be used in integrating and performing the Project mission. 21 figs., 21 tabs.

  4. The Human Genome Diversity Project

    SciTech Connect (OSTI)

    Cavalli-Sforza, L. [Stanford Univ., CA (United States)

    1994-12-31T23:59:59.000Z

    The Human Genome Diversity Project (HGD Project) is an international anthropology project that seeks to study the genetic richness of the entire human species. This kind of genetic information can add a unique thread to the tapestry knowledge of humanity. Culture, environment, history, and other factors are often more important, but humanity`s genetic heritage, when analyzed with recent technology, brings another type of evidence for understanding species` past and present. The Project will deepen the understanding of this genetic richness and show both humanity`s diversity and its deep and underlying unity. The HGD Project is still largely in its planning stages, seeking the best ways to reach its goals. The continuing discussions of the Project, throughout the world, should improve the plans for the Project and their implementation. The Project is as global as humanity itself; its implementation will require the kinds of partnerships among different nations and cultures that make the involvement of UNESCO and other international organizations particularly appropriate. The author will briefly discuss the Project`s history, describe the Project, set out the core principles of the Project, and demonstrate how the Project will help combat the scourge of racism.

  5. The Boeing Company Project Fuel Tank Design Project Recap

    E-Print Network [OSTI]

    Demirel, Melik C.

    which consist of a 15o double angle displacement, 10 to 12 oscillations per minute oscillation frequencyThe Boeing Company Project Fuel Tank Design Project Recap The Boeing Company came to the Pennsylvania State University with a project for the mitigation of fuel slosh by utilizing different baffle

  6. LATEST PROJECTS & Preview a few of our latest research projects

    E-Print Network [OSTI]

    California at Davis, University of

    , disseminate informa- tion, and facilitate programs that reduce cooling system electrical demand and energy applied research through Western Cooling Challenge Demonstrations and many other ongoing projects. Our feaLATEST PROJECTS & UPDATES Preview a few of our latest research projects & updates pg. 10 OUTREACH

  7. Design structure for in-system redundant array repair in integrated circuits

    DOE Patents [OSTI]

    Bright, Arthur A.; Crumley, Paul G.; Dombrowa, Marc; Douskey, Steven M.; Haring, Rudolf A.; Oakland, Steven F.; Quellette, Michael R.; Strissel, Scott A.

    2008-11-25T23:59:59.000Z

    A design structure for repairing an integrated circuit during operation of the integrated circuit. The integrated circuit comprising of a multitude of memory arrays and a fuse box holding control data for controlling redundancy logic of the arrays. The design structure provides the integrated circuit with a control data selector for passing the control data from the fuse box to the memory arrays; providing a source of alternate control data, external of the integrated circuit; and connecting the source of alternate control data to the control data selector. The design structure further passes the alternate control data from the source thereof, through the control data selector and to the memory arrays to control the redundancy logic of the memory arrays.

  8. Designer's guidebook for first wall/blanket/shield assembly, maintenance, and repair

    SciTech Connect (OSTI)

    Not Available

    1983-12-30T23:59:59.000Z

    This is the initial issue of the guidebook. Since a guidebook of this type must incorporate information concerning a wide range of subjects, much additional data will eventually be included. The guidebook will document, in summary and easily referenceable form, data, designs, design concepts, design guidelines and background information useful to the FWBS and to the Maintenance System designer. In providing guidelines for the AMR of the FWBS, the guidebook must, of necessity, include guidelines for all aspects of maintenance associated with the FWBS. These include most maintenance operations within the reactor room necessary to gain access, identify faults, and handle equipment related to FWBS maintenance. In addition, the guidelines include those required to define facility requirements for handling and repair of FWBS and related reactor components external to the reactor room. Particular emphasis is given to remote maintenance design and operations.

  9. Uncompahgre Mesas Forest Restoration Project

    E-Print Network [OSTI]

    March 2010 Uncompahgre Mesas Forest Restoration Project Collaboration Case Study #12;Uncompahgre Mesas Forest Restoration Project 1 1 Colorado Forest Restoration Institute Collaboration Case Study at Colorado State University, to conduct case studies of two collaborative forest health efforts

  10. Environmental Management (EM) Cleanup Projects

    Broader source: Directives, Delegations, and Requirements [Office of Management (MA)]

    2008-09-24T23:59:59.000Z

    The guide supports DOE O 413.3A, Program and Project Management for the Acquisition of Capital Assets, and provides guidance on environmental management cleanup projects. Canceled by DOE N 251.105.

  11. Risk Management In Major Projects 

    E-Print Network [OSTI]

    Baker, Scott William

    The integration of risk management in major projects within the construction and oil and gas industries has never been more significant especially as these projects are becoming larger and more complex. The increased ...

  12. Texas Stream Team Special Projects

    E-Print Network [OSTI]

    Texas Stream Team Special Projects · TMDL and Watershed Protection Plan Projects · Steering ­ Transparency tube ­ E. coli · Web site resources · Materials ­ Maps, Watershed Models Orange County Adams training sessions · Quality control · NPS education sessions · Volunteers of the month · Orange county

  13. Project Approval Form Concentration in

    E-Print Network [OSTI]

    Goldberg, Bennett

    Project Approval Form Concentration in Nanotechnology Return completed form to ENG Undergraduate of Graduation:____________________________ Instructions: Please check one of the following ways in which you Plan to complete the project as a requirement for the concentration in Nanotechnology. Depending upon

  14. ADVANCE! Leadership Experience Project Guidelines

    E-Print Network [OSTI]

    Hone, James

    ADVANCE! Leadership Experience Project Guidelines Fieldwork Practicum Description: The fieldwork component of the ADVANCE! leadership program offers students the opportunity to integrate theory exposure to that industry. Together, they design a leadership project in which the student takes an active

  15. PETITION FOR INSIGNIFICANT PROJECT MODIFICATION

    E-Print Network [OSTI]

    Cosumnes River Boulevard Interchange SMUD Cogeneration Pipeline Project Docket No. 92-AFC-2P July 2007, CA 95833 #12;SMUD COGENERATION PIPELINE PROJECT Table of Contents K:\\Wprocess\\25832\\SMUD

  16. Geothermal Outreach and Project Financing

    SciTech Connect (OSTI)

    Elizabeth Battocletti

    2006-04-06T23:59:59.000Z

    The ?Geothermal Outreach and Project Financing? project substantially added to the understanding of geothermal resources, technology, and small business development by both the general public as well as those in the geothermal community.

  17. Trotter's product formula for projections

    E-Print Network [OSTI]

    Shvydkoy, Roman

    -semigroup etB is replaced by the simplest of degenerate semigroups, i.e. a projection P L P denotes a bounded projection. Now, in (1) we replace the C0-semigroup etB by the continuous

  18. ESPC Project Developer's Resource Guide

    Energy Savers [EERE]

    in the charts, and are identified alongside additional detail in Section 4. 4 *Items in blue are project deliverables. 5 *Items in blue are project deliverables. 6 *Items in blue...

  19. Executing major projects through Contractors

    E-Print Network [OSTI]

    McKenna, Nicholas A. (Nicholas Alan)

    2005-01-01T23:59:59.000Z

    Project based organizational structures are utilized in many industries. The firms engaged in these significant endeavors, project sponsor and contractor alike, risk both capital and reputation in the market-place with ...

  20. TSSWCB Bacteria-Related Projects 

    E-Print Network [OSTI]

    Wythe, Kathy

    2007-01-01T23:59:59.000Z

    of the projects are listed below. ? Peach CreekWater Quality Improvement Project ? Monitoring and Educational Programs Focused on Bacteria and Nutrient Runoff on Dairy Operations in the LeonWatershed ? Development of the Plum CreekWPP ? Impact of Proper... Star Healthy Streams * ? Environmental Management of Grazing Lands * *TWRI-managed projects More information on the initiative is available at www.tsswcb.state.tx.us/managementprogram/ initiatives/bacteria. Bacteria Projects Across the State...

  1. Addendum to Fake Projective Planes

    E-Print Network [OSTI]

    Yeung, Sai-Kee

    ingenious group theoretic computations that the twenty eight classes of fake projective planes altogether- damental group of eight of the one hundred fake projective planes do not admit an embedding into SU(2, 1. In [1] we proved that if the fundamental group of a fake projective plane is an arithmetic subgroup

  2. Degree project in Communication Systems

    E-Print Network [OSTI]

    Maguire Jr., Gerald Q.

    Degree project in Communication Systems Second level, 30.0 HEC Stockholm, Sweden M A N X I N G D U in upgrading their network capacity. However, an important conclusion from this thesis project be more efficient. It should be noted that the mobile terminals covered in the project are connected

  3. Degree project in Communication Systems

    E-Print Network [OSTI]

    Maguire Jr., Gerald Q.

    Degree project in Communication Systems First level, 15.0 HEC Stockholm, Sweden R A F I D K A R I M is considered by many to be a driving force in the next generation Internet. This project uses very in expensive the desired user functionality. This bachelor's thesis project made it possible for a PoE powered circuit

  4. Muddy River Restoration Project Begins

    E-Print Network [OSTI]

    US Army Corps of Engineers

    Muddy River Restoration Project Begins Page 5 #12;2 YANKEE ENGINEER February 2013 Yankee Voices of the Muddy River Restoration project. Inset photo: Flooding at the Muddy River. Materials provided by Mike Project Manager, on the passing of his father in law, Francis James (Jim) Murray, Jan. 9. ... to Laura

  5. PI & Project Team PAF Changes

    E-Print Network [OSTI]

    Shyy, Wei

    Proposal Management PI & Project Team PAF Changes Step-By-Step Procedures Last updated: 4/1/2013 1 of 10 http://eresearch.umich.edu PAF Changes This procedure details how the PI & Project Team can: Make. Page 9 Important Information Before a PAF is routed for approval, the PI & Project Team can make

  6. Office: ITO PE/Project

    E-Print Network [OSTI]

    Mills, Kevin

    Mgr.: Mills/Swinson PAD No.: Smart Spaces Moving Through Smart Spaces "city-wide appliances" "in1 DARPA Office: ITO PE/Project: Pgm No.: Pgm Mgr.: Mills/Swinson PAD No.: Smart Spaces Personal Information Projection · Develop techniques for projecting personal information from cyberspace into smart

  7. Projects Funded by the American Recovery and Reinvestment Act...

    Broader source: Energy.gov (indexed) [DOE]

    remodeling, improving, extending, or making other changes to a facility, exclusive of maintenance repairs that are preventive in nature. The term includes planning,...

  8. RECORD OF CATEGORICAL EXCLUSION DETERMINATION Project ID No....

    Broader source: Energy.gov (indexed) [DOE]

    318 Title: WH Air ConditioningHeating Repairs, 2010-2013 Description: Subcontractor shall provide all labor, materials, tools, equipment, transportation and supervision required...

  9. Project Earth Lover

    SciTech Connect (OSTI)

    Slobotski, Stephanie,

    2011-09-01T23:59:59.000Z

    Under this project, the Ponca Tribe of Nebraska (PTN) will conduct An Energy Options Analysis (EOA) to empower Tribal Leadership with critical information to allow them to effectively screen energy options that will further develop the Tribe's long-term strategic plan and energy vision. The PTN will also provide community workshops to enhance Tribal Members' capabilities, skills and awareness of energy efficiency and conservation technology and practices. A 90- minute workshop will be conducted at each of the 5 sites and one-hundred tribal members will receive an erergy efficiency kit.

  10. The STACEE Project

    E-Print Network [OSTI]

    Ong, R A; Ong, Rene A.; Covault, Corbin E.

    1997-01-01T23:59:59.000Z

    The Solar Tower Atmospheric Cherenkov Effect Experiment (STACEE) is a telescope designed to explore the gamma-ray sky between 20 and 250 GeV using the atmospheric Cherenkov technique. STACEE is currently under construction. When completed, it will use 48 large heliostat mirrors at the solar research facility at Sandia National Laboratories (Albuquerque, NM) to reflect Cherenkov light created in gamma-ray air showers to secondary mirrors on a central tower. The secondary mirrors image this light onto photomultiplier tube cameras. This paper provides an overview of the STACEE project, including a description of the experimental site and an outline of the current design for the detector components.

  11. The STACEE Project

    E-Print Network [OSTI]

    Rene A. Ong; Corbin E. Covault

    1997-11-25T23:59:59.000Z

    The Solar Tower Atmospheric Cherenkov Effect Experiment (STACEE) is a telescope designed to explore the gamma-ray sky between 20 and 250 GeV using the atmospheric Cherenkov technique. STACEE is currently under construction. When completed, it will use 48 large heliostat mirrors at the solar research facility at Sandia National Laboratories (Albuquerque, NM) to reflect Cherenkov light created in gamma-ray air showers to secondary mirrors on a central tower. The secondary mirrors image this light onto photomultiplier tube cameras. This paper provides an overview of the STACEE project, including a description of the experimental site and an outline of the current design for the detector components.

  12. CLIC Project Overview

    ScienceCinema (OSTI)

    Andrea Latina

    2010-01-08T23:59:59.000Z

    The CLIC study is exploring the scheme for an electron-positron collider with a centre-of-mass energy of 3 TeV in order to make the multi-TeV range accessible for physics. The current goal of the project is to demonstrate the feasibility of the technology by the year 2010. Recently, important progress has been made concerning the high-gradient accelerating structure tests and the experiments with beam in the CLIC test facility, CTF3. On the organizational side, the CLIC international collaborations have significantly gained momentum, boosting the CLIC study.

  13. CLIC Project Overview

    SciTech Connect (OSTI)

    Andrea Latina

    2009-06-10T23:59:59.000Z

    The CLIC study is exploring the scheme for an electron-positron collider with a centre-of-mass energy of 3 TeV in order to make the multi-TeV range accessible for physics. The current goal of the project is to demonstrate the feasibility of the technology by the year 2010. Recently, important progress has been made concerning the high-gradient accelerating structure tests and the experiments with beam in the CLIC test facility, CTF3. On the organizational side, the CLIC international collaborations have significantly gained momentum, boosting the CLIC study.

  14. NDLGS project update

    SciTech Connect (OSTI)

    Lienert, Thomas J [Los Alamos National Laboratory; Sutton, Jacob O [Los Alamos National Laboratory; Piltch, Martin S [Los Alamos National Laboratory; Lujan, Dennis J [Los Alamos National Laboratory

    2011-01-14T23:59:59.000Z

    Recent results for laser and ESD processing for the NDLGS project will be reviewed. Conclusions are: (1) Short mix passes have profound effect on window T; (2) Multiple drill and re-weld at single location has been shown to be feasible and successful; (3) Kapton beam profiling method has been successfully developed. Comparison of 100 mm and 120 mm lenses gives reasonable and consistent results; (4) Manifold pumpdown data has been presented; (5) ESO results can be accurately predicted once a repeatable efficiency has been established; and (6) The electrode-workpiece geometry may play an important on ESO efficiency. Experiments are planned to investigate these effects.

  15. Investor Confidence Project

    E-Print Network [OSTI]

    Golden, M.

    2013-01-01T23:59:59.000Z

    Actionable Data ESL-KT-13-12-38 CATEE 2013: Clean Air Through Energy Efficiency Conference, San Antonio, Texas Dec. 16-18 Near-Term: Not Enough Deal-Flow • High Transaction Costs • Lack of Viable Origination Channels • Highly Variable Performance • Complex... Custom Projects ESL-KT-13-12-38 CATEE 2013: Clean Air Through Energy Efficiency Conference, San Antonio, Texas Dec. 16-18 Long-Term: High Cost of Capital • More equity than debt • Not enough volume to securitize • Insufficient actuarial data...

  16. Autostereoscopic projection viewer

    DOE Patents [OSTI]

    Toeppen, John S. (Livermore, CA)

    2006-12-19T23:59:59.000Z

    An autostereoscopic viewer is employed to produce aberration corrected images to simulate a virtual presence by employing pairs of projector optical components coupled with an image corrector plate and a field lens. Images are designed with magnifications and optical qualities and positioned at predetermined eyezones having controlled directional properties. The viewer's eyes are positioned in these eyezones. The size of these zones is related to the aperture of the projection lenses, the magnification produced by the Fresnel(s), and the optical properties and position of the image corrector plate.

  17. Rabbit Project Reference Manual

    E-Print Network [OSTI]

    Wootton, Chad

    2000-05-04T23:59:59.000Z

    breed or produc- tion standards whenever possible to 4-H mem- bers or other people wishing to raise rabbits. You might sell fryers live to commercial rab- bit processors or to laboratory animal suppli- ers. Or, dress and sell the fryers to friends, rela... or more litters are raised. Offspring are sold for breed stock and show animals. Members should also market the young. Members are encouraged to use pure- bred commercial breeds for this project, al- though crossbred rabbits are acceptable. Mem- bers must...

  18. PSERC Current Projects Overview

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742Energy ChinaofSchaeferAprilOverviewEfficiencyofHSSPIAProperty Management PlanPROJECT1OE0000652

  19. Project Execution Plan RM

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic2 OPAM615_CostNSAR - TProcuring Solar forProject Develops

  20. Project Management Practices

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33 1112011 Strategic2 OPAM615_CostNSAR - TProcuring Solar forProject DevelopsDepartmentACQUISITION

  1. Step 4: Project Implementation

    Office of Environmental Management (EM)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742 33Frequently AskedEnergyIssues DOE's NuclearSpurringSteam Systems Steam Systems4: Project

  2. PROJECT TASK STATEMENT

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level:Energy: Grid Integration Redefining What's Possible for RenewableSpeedingBiomassPPPO Website Directory PPPO WebsitePREP |Dan5,PROJECT TASK

  3. Project Submission Template

    Broader source: Energy.gov (indexed) [DOE]

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOn April 23, 2014, an OHASeptember 2010 |of Energy TEESAdoptionCooperation Project

  4. NREL: Biomass Research - Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Saleshttp://www.fnal.gov/directorate/nalcal/nalcal02_07_05_files/nalcal.gifNREL NRELChemical and CatalystNew ChallengesProjects

  5. Projects & Initiatives

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)IntegratedSpeedingTechnical News,Program DirectionProject ATHENAManagementIn ThisPages

  6. Projects | The Ames Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office of Science (SC)IntegratedSpeedingTechnical News,Program DirectionProject ATHENAManagementIn

  7. CNEEC - Research Projects

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645 3,625 1,006 492 742EnergyOnItem NotEnergy,ARMForms About Batteries BatteriesCAESMission Welcome to theProjects CNEEC

  8. ARM Observations Projected

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    AFDC Printable Version Share this resource Send a link to EERE: Alternative Fuels Data Center Home Page to someone by E-mail Share EERE: Alternative Fuels Data Center Home Page on Facebook Tweet about EERE: Alternative Fuels Data Center Home Page on Twitter Bookmark EERE: Alternative1 First Use of Energy for All Purposes (Fuel and Nonfuel), 2002; Level: National5Sales for4,645U.S. DOE Office511041cloth DocumentationProducts (VAP) VAP Update Information on new, existing, andObservations Projected

  9. CX-002356: Categorical Exclusion Determination | Department of...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    City of Lincoln Nebraska Energy Efficiency and Conservation Block Grant Project 18 Energy Demonstration Project CX(s) Applied: A9, A11, B5.1 Date: 05072010 Location(s):...

  10. Searchlight Wind Energy Project FEIS Appendix E

    Office of Environmental Management (EM)

    June 2, 2009 District Las Vegas Field Office Resource Area Activity (program) Proposed Wind Generation SECTION A. PROJECT INFORMATION 1. Project Name Searchlight Wind Project 4....

  11. EMP: Earth Microbiome Project | Argonne National Laboratory

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    Data-Intensive Science Applied Mathematics Science & Engineering Applications EMP: Earth Microbiome Project EMP: Earth Microbiome Project The Earth Microbiome Project is a...

  12. Infrastructure and Operations Improvement Project Director |...

    Broader source: All U.S. Department of Energy (DOE) Office Webpages (Extended Search)

    project risks. -Ensure that required and effective project management and control systems are developed, deployed and implemented to successfully manage and assess the project...

  13. Energy Savings Performance Contract Project Facilitators | Department...

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    developing U.S. Department of Energy (DOE) energy savings performance contract (ESPC) projects are required to work with a qualified project facilitator. Project...

  14. SOFTWARE QUALITY & SYSTEMS ENGINEERING PROGRAM: Project Tracking...

    Office of Environmental Management (EM)

    Project Tracking Checklist SOFTWARE QUALITY & SYSTEMS ENGINEERING PROGRAM: Project Tracking Checklist The following checklist is intended to provide system owners, project...

  15. SOFTWARE QUALITY & SYSTEMS ENGINEERING PROGRAM: Project Planning...

    Broader source: Energy.gov (indexed) [DOE]

    PROGRAM: Project Planning Checklist SOFTWARE QUALITY & SYSTEMS ENGINEERING PROGRAM: Project Planning Checklist The following checklist is intended to provide system owners, project...

  16. Renewable energy projects approved | Department of Energy

    Office of Energy Efficiency and Renewable Energy (EERE) Indexed Site

    Renewable energy projects approved Renewable energy projects approved July 30, 2008 - 3:13pm Addthis CARSON CITY, Nev.-Two renewable energy projects representing a 100...

  17. Tribal Renewable Energy Advanced Course: Project Development...

    Broader source: Energy.gov (indexed) [DOE]

    slides. This course provides in-depth information on project development concepts for renewable energy projects on tribal lands, including: Risk and uncertainty Tribal project...

  18. DOE Energy Challenge Project

    SciTech Connect (OSTI)

    Frank Murray; Michael Schaepe

    2009-04-24T23:59:59.000Z

    Project Objectives: 1. Promote energy efficiency concepts in undergraduate and graduate education. 2. Stimulate and interest in pulp and paper industrial processes, which promote and encourage activities in the area of manufacturing design efficiency. 3. Attract both industrial and media attention. Background and executive Summary: In 1997, the Institute of Paper Science and Technology in conjunction with the U.S. Department of Energy developed a university design competition with an orientation to the Forest Products Industry. This university design competition is in direct alignment with DOE’s interests in instilling in undergraduate education the concepts of developing energy efficient processes, minimizing waste, and providing environmental benefits and in maintaining and enhancing the economic competitiveness of the U.S. forest products industry in a global environment. The primary focus of the competition is projects, which are aligned with the existing DOE Agenda 2020 program for the industry and the lines of research being established with the colleges comprising the Pulp and Paper Education and Research Alliance (PPERA). The six design competitions were held annually for the period 1999 through 2004.

  19. Projection optics box

    DOE Patents [OSTI]

    Hale, Layton C. (Livermore, CA); Malsbury, Terry (Tracy, CA); Hudyma, Russell M. (San Ramon, CA); Parker, John M. (Tracy, CA)

    2000-01-01T23:59:59.000Z

    A projection optics box or assembly for use in an optical assembly, such as in an extreme ultraviolet lithography (EUVL) system using 10-14 nm soft x-ray photons. The projection optics box utilizes a plurality of highly reflective optics or mirrors, each mounted on a precision actuator, and which reflects an optical image, such as from a mask, in the EUVL system onto a point of use, such as a target or silicon wafer, the mask, for example, receiving an optical signal from a source assembly, such as a developed from laser system, via a series of highly reflective mirrors of the EUVL system. The plurality of highly reflective optics or mirrors are mounted in a housing assembly comprised of a series of bulkheads having wall members secured together to form a unit construction of maximum rigidity. Due to the precision actuators, the mirrors must be positioned precisely and remotely in tip, tilt, and piston (three degrees of freedom), while also providing exact constraint.

  20. Device Oriented Project Controller

    SciTech Connect (OSTI)

    Dalesio, Leo; Kraimer, Martin

    2013-11-20T23:59:59.000Z

    This proposal is directed at the issue of developing control systems for very large HEP projects. A de-facto standard in accelerator control is the Experimental Physics and Industrial Control System (EPICS), which has been applied successfully to many physics projects. EPICS is a channel based system that requires that each channel of each device be configured and controlled. In Phase I, the feasibility of a device oriented extension to the distributed channel database was demonstrated by prototyping a device aware version of an EPICS I/O controller that functions with the current version of the channel access communication protocol. Extensions have been made to the grammar to define the database. Only a multi-stage position controller with limit switches was developed in the demonstration, but the grammar should support a full range of functional record types. In phase II, a full set of record types will be developed to support all existing record types, a set of process control functions for closed loop control, and support for experimental beam line control. A tool to configure these records will be developed. A communication protocol will be developed or extensions will be made to Channel Access to support introspection of components of a device. Performance bench marks will be made on both communication protocol and the database. After these records and performance tests are under way, a second of the grammar will be undertaken.